# Pennsylvania Public Utility Commission — Pipeline Safety Interpretation

**Citation:** PI-19-0016  
**Type / status:** guidance / guidance  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2020-01-27

PI-19-0016 response to Pennsylvania Public Utility Commission concerning 191.3.

## Document text

<<<PAGE 1>>>

U.S. Department
ofTransportation
Pipeline and Hazardous Materials
Safety Administration
1200 New Jersey Avenue SE
Washington DC 20590
JAN 2 :120,0
Ms. Stephanie M. Wimer
Senior Prosecutor
Pennsylvania PUC
P.O. Box 3265
Harrisburg, PA 17105-3 265
Dear Ms. Wimer:
In a letter to the Pipeline and Hazardous Materials Safety Administration (PHMSA) dated
October 17, 2019, you requested an interpretation of the pipeline safety regulations in 49 Code of
Federal Regulations (CFR) Parts 191 and 192. Specifically, you requested clarification on the
definition of ''transportation of gas" under § 191.3.
You stated the Pennsylvania Public Utility Commission's (Commission) Bureau of Investigation
and Enforcement (l&E) Safety Division is currently investigating a natural gas pipeline incident
that happened on September 10, 2018, in Center Township, Beaver County, Pennsylvania. The
incident occurred on the Revolution Pipeline, which is made of carbon steel and is 24 inches in
diameter. The pipeline runs approximately 42 miles from a compressor station in Butler County,
Pennsylvania to a cryogenic processing plant in Washington County, Pennsylvania.
You stated the Revolution Pipeline is owned and operated by Energy Transfer Company (ETC),
OPID 32099, and construction of the pipeline was completed in or about March 2018. When the
incident occurred on September 10, 2018, the line was being brought up to optimal operating
pressure and the valve serving the cryogenic processing plant was closed. With that valve
closed, the cryogenic processing plant was unable to receive natural gas. You stated that on the
date of the incident, ETC had not reached the deadline to register the Revolution Pipeline with
the Commission, because registration of pipeline miles for the 2018 calendar year was due on
March 31, 2019.
You stated that on the date of the incident, the Revolution Pipeline was in the commissioning
phase and, therefore, not all valves along the pipeline were open for packing the line and, as
noted above, the valve at the cryogenic processing plant was shut such that the plant could not
receive gas.
You ask PHMSA's responses for the following questions:
Question 1: Is packing the pipeline with product during the commissioning phase,
where the line is in the process of being brought up to optimal operating pressure, remote
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations (49 CFR
Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations are not generally applicable, do not create legally-enforceable rights or
obligations, and are provided to help the specific requestor understand how to comply with the regulations.

<<<PAGE 2>>>

2
valves are disengaged and the downstream valve to the cryogenic processing plant is
closed, still deemed the "transportation of gas?"
Response to Question 1:
Yes, once a pipeline has gas to flow into it, regardless of flow conditions and pressurization, the
line is in-service and deemed to be transporting gas.
Section 191.3 defines transportation of gas as:
Transportation of gas means the gathering, transmission, or distribution of gas by
pipeline, or the storage of gas in or affecting interstate or foreign commerce.
Placing gas into an empty pipeline during the commissioning phase, and adding pressure into it
is ''transportation of gas."
Question 2: If Question 1 is answered in the negative, does PHMSA agree that the Revolution
Pipeline was not jurisdictional to the Commission at the time of the September 10, 2018
incident?
Response to question 2:
The answer to Question 1 is in the affirmative. Therefore, the Revolution Pipeline was a
regulated pipeline at the time of the incident. It is important to note that the Revolution Pipeline
was also subject to the pipeline safety regulations before the line began transporting gas. Part
192 of the pipeline safety regulations prescribes the minimum safety requirements for pipeline
facilities and the transportation of gas. See, 49 C.F .R. § 192.1. The pipeline safety regulations
apply to the materials, design, construction and testing of the Revolution Pipeline before the
facility transported gas.
Ifwe can be of further assistance, plea,se contact Tewabe Asebe at 202-366-5523.
Sincerely,
Director, Office of Standards
and Rulemaking
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations (49 CFR
Parts 190-199) in the fonn of interpretation letters. These letters reflect the agency's current application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations are not generally applicable, do not create legally-enforceable rights or
obligations, and are provided to help the specific requestor understand how to comply with the regulations.

<<<PAGE 3>>>

,u-1 utu r m1,c11aarn.Jo"
COMMONWEALTH OF PENNSYLVANIA
PENNSYLVANIA PUBLIC UTILITY COMMISSION
P.O. BOX 3265, HARRISBURG, PA 17105-3265
October 17, 2019
Via Electronic Mail and First-Class Mail
Mr. Shane Kelley
Director, Standards and Rulemaking Division
U.S. Department of Transportation
Pipeline and Hazardous Materials Safety Administration
1200 New Jersey Avenue SE
Washington, DC 20590
in focntr(a),dot. gov
Re: Request for Written Regulatory Interpretation
Dear Mr. Kelley:
This letter represents a request from the Safety Division of the Pennsylvania
Public Utility Commission's ("Commission") Bureau of Investigation and Enforcement
("I&E") for an interpretation of the Pipeline and Hazardous Materials Safety
Administration ("PHMSA") pipeline safety regulations under 49 CFR § 191.3 related to
the definition of "transportation of gas."
The I&E Safety Division participates in PHMSA's State Pipeline Safety Program.
Through its agreement with PHMSA and participation in the Program, the I&E Safety
Division has assumed the safety responsibilities of intrastate pipeline facilities in
Pennsylvania over which it has jurisdiction as authorized by state law.
Pursuant to Pennsylvania's Gas and Hazardous Liquids Pipelines Act, 58 P.S.
§ 801.101 et seq., the Commission has authority to regulate and supervise pipeline
operators within Pennsylvania consistent with Federal pipeline safety laws. 58 P.S.
§ 801.50l(a). Pipeline operators are defined as "a person that owns or operates
equipment or facilities in this Commonwealth/or the transportation of gas or hazardous
liquids by pipeline or pipeline facility regulated under Federal pipeline safety laws." 5 8
P .S. § 801.102 ( emphasis added). Pipeline operators are required to register with the
Commission by March 31 of each year and report gathering, transmission and
distribution pipeline mileage in class 1, 2, 3 and 4 locations for the preceding calendar
year. See 58 P.S. § § 801.30l(c)(l) and Act 127 of 2011 - The Gas and Hazardous
Liquids Pipeline Act; Assessment of Pipeline Operators, Docket No. M-2012-2282031
(Final Implementation Order entered February 17, 2012).
The PHMSA pipeline safety regulations define "operator" as a "person who
engages in the transportation of gas." 49 CFR §§ 191.3 and 192.3 (emphasis added).
Moreover, "pipeline" means "all parts of those physical facilities thorough which gas
IN REPLY PLEASE
REFER TO OUR FILE

<<<PAGE 4>>>

Shane Kelley
October 17, 2019
Page 2
moves in transportation." 49 CFR § 192.3 (emphasis added). "Pipeline facility" is
defined as "new and existing pipelines, rights-of-way, and any equipment, facility, or
building used in the transportation of gas or in the treatment of gas during the course of
transportation." 49 CFR § 192.3 ( emphasis added).
The I&E Safety Division is currently investigating a natural gas pipeline incident
that happened on September 10, 2018 in Center Township, Beaver County, Pennsylvania.
The incident occurred on the Revolution Pipeline, which is a twenty-four (24) inch
carbon steel pipeline that was constructed between 2016 and 2018. The pipeline extends
approximately forty-two (42) miles from a compressor station in Butler County, PA to a
cryogenic processing plant in Washington County, PA. The Revolution Pipeline is
owned and operated by Energy Transfer Company ("ETC"), OPID 32099.
Construction of the Revolution Pipeline was completed in approximately March of
2018. When the incident occurred on September 10, 2018, the line was being brought up
to optimal operating pressure and the valve serving the cryogenic processing plant was
closed. Thus, the cryogenic processing plant was unable to receive natural gas.
As of the date of the incident, ETC had not reached the deadline to register the
Revolution Pipeline with the Commission pursuant to the Gas and Hazardous Liquids
Pipelines Act as construction of the pipeline was only completed in March of 2018.
Registration of pipeline miles for the 2018 calendar year was due on March 31, 2019.
On the date of the incident, the Revolution Pipeline was in the commissioning
phase in that construction of the pipeline was complete but transportation had not started.
Some, but not all, of the valves along the pipeline were open for packing the line and
notably, the valve at the cryogenic processing plant was shut such that the plant could not
receive gas. While it is clear that the Revolution Pipeline was constructed to transport
gas by pipeline, it appears that such transportation had not yet been initiated. The
PHMSA pipeline safety regulations, as mentioned above, appear to be predicated on a
pipeline transporting gas, and not merely packing gas, in order for the regulations to
apply to this incident.
I&E seeks an interpretation from PHMSA related to the definition of
"transportation of gas," which means "the gathering, transmission, or distribution of gas
by pipeline, or the storage of gas in or affecting interstate or foreign commerce." 49 CFR
§ 191.3. The I&E Safety Division has classified the Revolution Pipeline as a gathering
line and the incident occurred on an area of the pipeline that the l&E Safety Division
classified as a class 3 gathering line. A "gathering line" is defined as a "pipeline that
transports gas from a current production facility to a transmission line or main." 49 CFR
§ 192.3. The I&E Safety Division's classification of the Revolution Pipeline as a
gathering line is also based upon the definition of "gathering line" in the American

<<<PAGE 5>>>

Shane Kelley
October 17, 2019
Page 3
Petroleum Institute's Recommended Practice 80, API RP80, incorporated by reference,
Docket No. PHMSA-1998-4868; Arndt. 192-102, Final Rule April 14, 2006. 1
l&E's questions to PHMSA are as follows:
( 1) Is packing the pipeline with product during the commissioning phase where the
line is in the process of being brought up to optimal operating pressure, remote
valves are disengaged and the downstream valve to the cryogenic processing plant
is closed still deemed the "transportation of gas?"; and
(2) If Question No. 1 is answered in the negative, does PHMSA agree that the
Revolution Pipeline was not jurisdictional to the Commission at the time of the
September 10, 2018 incident?
Thank you for your consideration in this matter. Should you have any questions
or seek further clarification or details with respect to this request, please do not hesitate to
contact the undersigned.
Sincerely,
Stephanie M. Wimer
Senior Prosecutor
PA Public Utility Commission
Bureau oflnvestigation and Enforcement
717.772.8839
stwimer@pa.gov
cc: Richard A. Kanaskie, Director, l&E (via e-mail only)
Michael L. Swindler, Deputy Chief Prosecutor, I&E (via e-mail only)
Michael Chilek, l&E Safety Division (via e-mail only)
Matthew Matse, l&E Safety Division (via e-mail only)
1 Should PHMSA disagree with I&E's classification of the Revolution Pipeline as a gathering line, I&E
would also request PHMSA's interpretation with respect to the pipeline's classification.

## Provenance

- Official: Yes
- Source: <https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/73266/pennsylvania-puc-pi-19-0016-01-27-2019-part191-3.pdf>
- Source ID: `phmsa`
- SHA-256: `fffebb484bd5733bcceada7429d585ef4c64ab49658841a23b9abd08019608e5`
- Retrieved: 2026-08-20T00:59:31.977Z
- Exported: 2026-08-22T04:24:41.605Z
- Document slug: `phmsa-interpretation-pi-19-0016`

### Source metadata

```json
{
  "materialSubtype": "interpretation",
  "interpretationArea": "pipeline_safety",
  "representation": "full_text_from_official_pdf",
  "companies": [
    "Pennsylvania Public Utility Commission"
  ],
  "individuals": [
    "Ms. Stephanie M. Wimer"
  ],
  "refIds": [
    "PI-19-0016"
  ],
  "catalogDates": [
    "2020-01-27"
  ],
  "catalogParts": [
    191
  ],
  "catalogRowCount": 1,
  "sourceRecordUrls": [
    "https://www.phmsa.dot.gov/node/71931"
  ],
  "linkedAttachmentUrls": [],
  "unavailableResponseUrls": [],
  "duplicateRepresentationUrls": [],
  "citedSections": [
    "191.3",
    "192.1",
    "192.3"
  ],
  "catalogPageUrls": [
    "https://www.phmsa.dot.gov/regulations/title49/section/1913"
  ],
  "pdfUrls": [
    "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/73266/pennsylvania-puc-pi-19-0016-01-27-2019-part191-3.pdf"
  ],
  "representations": [
    {
      "viewUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/73266/pennsylvania-puc-pi-19-0016-01-27-2019-part191-3.pdf",
      "detailUrl": null,
      "detailHtmlPath": null,
      "pdfUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/73266/pennsylvania-puc-pi-19-0016-01-27-2019-part191-3.pdf",
      "pdfArtifactPath": "data/sources/phmsa-interpretations/pi-19-0016.pdf",
      "pdfArtifactSha256": "5307d151327d07605efb551dcb5bae243cddcfb0f5d4ca3030e1b1a38c2646ad",
      "extractedTextPath": "data/sources/phmsa-interpretations/pi-19-0016.v2.txt",
      "extractedTextSha256": "1e71e9239fb35a21b2eed36df41900db9695f0448ee64eda7f2240ef3cc252f6",
      "pageCount": 5,
      "extractionVersion": 2
    }
  ],
  "caveat": "Interpretations apply regulations to the facts presented and do not create independently enforceable requirements.",
  "jurisdiction": "US"
}
```
