# Puget Sound Energy — Pipeline Safety Interpretation

**Citation:** PI-21-0007  
**Type / status:** guidance / guidance  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** 2022-04-20

PI-21-0007 response to Puget Sound Energy concerning 192.631.

## Document text

<<<PAGE 1>>>

U.S. Department
of Transportation
Pipeline and Hazardous
Materials Safety Administration April 18, 2022
1200 New Jersey Avenue, SE
Washington, DC 20590
Ms. Kaaren Daugherty
Manager, Compliance and Quality Management
Puget Sound Energy
P.O. Box 97034
Bellevue, WA 98009-9734
Dear Ms. Daugherty:
In a letter to the Pipeline and Hazardous Materials Safety Administration (PHMSA), dated
June 28, 2021, Puget Sound Energy (PSE) requested an interpretation of the applicability of
certain sections of 49 Code of Federal Regulation (CFR) part 192 to your pipeline facilities.
Specifically, you requested an interpretation as to the applicability of § 192.631 to the Jackson
Prairie natural gas storage project (Jackson Prairie) located 10 miles southeast of Chehalis,
Washington, which is jointly owned by Puget Sound Energy, Inc., Avista Utilities, and Williams
Northwest Pipeline (Joint Owners).
You described Jackson Prairie as follows: (1) feeder lines, consisting of 4 parallel transmission
lines, ranging in size from 14-inch to 24-inch diameter and each approximately 1.7 miles long;
(2) storage field; (3) processing facility; and (4) a meter station. You also stated that the feeder
lines are bi-directional and are used to inject and withdraw from the storage field. You stated
that the feeder lines merge into a common header that connects to the meter station piping and
Williams Northwest Pipeline as the operator of the meter station.
In addition, you stated that PSE personnel are present 24 hours, 7 days a week at Jackson Prairie,
and have sole responsibility for operating the station equipment within the processing facility
boundaries and the property limits of the adjacent storage field and the feeder lines. You stated
the Jackson Prairie operations center receives information from data points located inside the
fence line of the processing facility to ensure equipment, such as gas and fire detectors, are
operating safely. You stated the data point on the west header line is located within the fence
and measures suction or discharge pressures of gas entering or exiting the compressors. You
stated that in the event the pressure goes above or below a predetermined safe operating pressure,
the automatic shut-off valve on the west header pipe is programmed to close.
You described the Joint Owners’ functions for the gas transmission pipeline operations, farm
taps, and Jackson Prairie as: (1) Williams Northwest is responsible for remotely monitoring and
controlling the valves and piping at the storage project delivery point meter station (located
approximately 1.7 miles to the west of Jackson Prairie storage facility) via a Supervisory Control
and Data Acquisition (SCADA) system from a control room. Williams Northwest personnel can
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations (49 CFR
Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the specific facts
presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and are provided to
help the public understand how to comply with the regulations.

<<<PAGE 2>>>

2
also use the SCADA information to direct Jackson Prairie personnel to take action at the feeder
lines or the processing facility; (2) PSE operations center is responsible for remotely monitoring
the safety-related operations and the inlet to the Chehalis farm tap via a SCADA system from a
PSE control room in Redmond, WA. In addition, the PSE SCADA system collects and displays
information about the Chehalis farm tap inlet pressure to dispatch pressure control personnel to
take action at the farm tap; and (3) other than the meter station, PSE technicians are onsite and
locally monitor and control operation of the processing facility equipment within the fenced
boundary. You stated that this relationship is governed by the Jackson Prairie Gas Storage
Project Agreement (Project Agreement), on file with the Federal Energy Regulatory Commission
(FERC). The storage field and the feeder lines are not connected to a SCADA system and the
operations center is limited to the processing facility. All human-machine interface data points
are located within the fenced boundary, however you also stated that Jackson Prairie does
receive a duplicate screen from the Williams Northwest SCADA system at the meter station for
non-operational information purposes only.
On July 12, 2021, you provided the following additional information: (1) schematic for Chehalis
farm tap station; and (2) schematic for Jackson Prairie processing facility and storage field. You
also stated that the compressors are located within the fence of the Jackson Prairie processing
facility and Jackson Prairie uses the compressors for withdrawal of gas that is pushed towards
Williams Northwest meter station about 1.7 miles away, and for injection of gas that is pushed
towards the storage field. You stated that Williams Northwest has its own compressors used for
transportation of gas through their interstate transmission pipelines. You stated that Williams
Northwest controls and monitors flow of gas to the Chehalis farm tap and to Jackson Prairie’s
processing facility. In addition, you stated that Williams Northwest manages the nomination of
gas to be stored or withdrawn without the involvement of PSE’s employees located at Jackson
Prairie. You stated Williams Northwest provides the notification to PSE’s Jackson Prairie
personnel when gas needs to be withdrawn or injected.
On September 3, 2021, PHMSA again requested additional information and, per your request, on
October 22, 2021, PSE and PHMSA staff had a conference call to discuss PHMSA’s questions
related to the control room responsibilities of the Jackson Prairie facility. The original Safety
Program Relationship (SPR) provided to PHMSA did not indicate that the gas transmission
pipeline operations control room management plan (CRM) safety program was handled by
Williams, but instead indicated that it was addressed by PSE. Additionally, information
provided to PHMSA verbally indicated that contract arrangements between Williams Northwest
and PSE were not in alignment with that identified in the letter submitted regarding operations
and abnormal operating response. And while duplicate screen information was available to PSE
at Jackson Prairie, pressure information at Jackson Prairie had not been provided to Williams
Northwest. Verbal information communicated to PHMSA indicated that Jackson Prairie, rather
than Williams Northwest, made the decision about starting and stopping compressors affecting
gas transmission pressures on withdrawal and responding to the abnormal operations.
On January 11, 2022, you responded to PHMSA’s questions. You indicated in this response that
during the October 22nd meeting, PHMSA and PSE discussed operations and maintenance of the
gas transmission pipelines (feeder lines), including emergency response, and confirmed Jackson
Prairie is governed by the Project Agreement. Based on the information provided and discussed,
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations
(49 CFR Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the
specific facts presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and
are provided to help the public understand how to comply with the regulations.

<<<PAGE 3>>>

3
PSE indicated they would make changes in the SPR related to the CRM including the gas
transmission operations, provide additional pressure information to Williams Northwest, modify
the emergency procedures, and make modifications to the Project Agreement, which would be
filed with the FERC.
Your January 11, 2022 response shows that PSE did not provide procedural information that
indicated how operations and maintenance, including aspects associated with compression and
instrumentation.
The emergency procedure information you provided illustrates that the storage facility at Jackson
Prairie is functioning as a 49 CFR Part 192 regulated control room because the procedures
indicated that the storage facility would turn off the gas supply source.
PHMSA requested but did not receive the start and stop procedures for Jackson Prairie and for
Chehalis locations. Based upon this, PHMSA cannot confirm that start and stop operations
would be directed by Williams Northwest as indicated in the January 11, 2022, PSE response.
This is an important factor for understanding the applicable Part 192 control room operator.
Based on the information provided, the storage facility at Jackson Prairie was the only location
monitoring mainline pressure at the end of the gas transmission pipelines for injection
operations, and at the beginning of the pipeline for withdrawal operations. This information is a
significant component in determining the presence of an abnormal operation or emergency
condition.
There are several operators involved with the gas transmission pipeline operation between
Williams Northwest Meter Station, and the Storage facility at Jackson Prairie with no clear
documentation submitted that Williams has responsibility for control room function based on the
information provided to date and as stated in the request for interpretation.
Should PSE correct all elements that were identified in the email response of September 3, 2021,
and the meeting on October 22, 2021, implement activities with associated records providing
substantiation of the changes made, and submit those records to PHMSA for review, Williams
Northwest could be recognized as the control room of record on a go forward basis.
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations
(49 CFR Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the
specific facts presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and
are provided to help the public understand how to comply with the regulations.

<<<PAGE 4>>>

4
However, based on the information provided and reviewed by PHMSA, and as configured in
SPR, a control room currently exists at the storage facility at Jackson Prairie to monitor and
control the gas transmission pipeline operation. As such, § 192.631 requirements are applicable
to the storage facility at Jackson Prairie and associated gas transmission assets. In addition, as an
operator of a regulated underground natural gas storage facility, you must comply with
applicable 49 CFR Parts 191 and 192 requirements (see §§ 191.17 and 192.12).
If we can be of further assistance, please contact Tewabe Asebe at 202-366-5523.
Sincerely,
John A. Gale
Director, Office of Standards
and Rulemaking
The Pipeline and Hazardous Materials Safety Administration, Office of Pipeline Safety provides written clarifications of the Regulations
(49 CFR Parts 190-199) in the form of interpretation letters. These letters reflect the agency's current application of the regulations to the
specific facts presented by the person requesting the clarification. Interpretations do not create legally-enforceable rights or obligations and
are provided to help the public understand how to comply with the regulations.

<<<PAGE 5>>>

DocuSign Envelope ID: 1ED0C908-29A4-404A-B918-D17840D08AC3
June 28, 2021
By Federal Express
Alan K. Mayberry
Associate Administrator for Pipeline Safety
Office of Pipeline Safety
U.S. Department of Transportation
Pipeline and Hazardous Materials Safety Administration
1200 New Jersey Avenue, SE
Washington, DC 20590
RE: Request for Written Interpretation -- Control Room Management (49 C.F.R. §
192.631)
Dear Mr. Mayberry:
Puget Sound Energy, Inc. (PSE) is the operator of three elements of the Jackson Prairie
Natural Gas Storage Project (Jackson Prairie) and certain other natural gas facilities in the
state of Washington under operator identification number, OPID 22189. PSE seeks a
written interpretation from the Department of Transportation Pipeline and Hazardous
Materials Safety Administration (PHMSA) regarding the applicability of the Control
Room Management Rule (49 CFR. § 192.631 (CRM Rule)) to its operation of Jackson
Prairie.
I. Background and Description of Jackson Prairie
Jackson Prairie is located approximately 10 miles southeast of Chehalis, Washington and
is jointly owned by PSE, Avista Utilities (Avista), and Williams Northwest Pipeline
(Northwest), collectively, the Joint Owners. Jackson Prairie consists of four primary
elements:
A. Storage Field, including individual Storage Reservoirs, wells, and associated field
lines. Isolation valves for the field lines that connect the Storage Field to the
Processing Facility are located within the fence lines of Processing Facility.
B. Processing Facility, including all the necessary compressor, dehydration, and
filtration units; local piping, an operations building, and a maintenance shop.

<<<PAGE 6>>>

DocuSign Envelope ID: 1ED0C908-29A4-404A-B918-D17840D08AC3
These facilities are situated in an approximately 5 acre area surrounded by a
fence.
C. Feeder Lines, consisting of four (4) parallel transmission lines, ranging in size
from 14” to 24” diameter and approximately 1.7 miles each. The Feeder Lines
connect the Processing Facility to the Meter Station at the Storage Project
delivery point.
D. Meter Station, situated at the Storage Project Delivery Point, serves as the point of
interconnection of the Feeder Lines and Northwest’s Natural Gas Transmission
system. Through bi-directional metering, the Meter Station measures and controls
the quantity of natural gas injected into and withdrawn from Jackson Prairie. Per
the Joint Owner agreement, Northwest serves as the operator of the Meter Station.
Inside the fence line of the Processing Facility, there is a normally open, manually
operated isolation valve on each of the Feeder Lines. The Feeder Lines merge into a
common (west) header inside the fence, before entering the Processing Facility. The
west header piping has a locally operated valve that is used to control the flow of gas into
and out of the Processing Facility. This valve remains closed when the Processing
Facility is not injecting or withdrawing gas.
Inside the fence line of the Meter Station, there is a normally open, manually operated
isolation valve on each of the four Feeder Lines. The Feeder Lines merge into a common
header that connects to the Meter Station piping. There are multiple valves used for
operation, including 20” and 24” tap valves from Northwest’s mainline.
One other nuance to Jackson Prairie is the existence of the Chehalis Farm Tap off the 14”
transmission line. Contractually, this farm tap is defined as a “transportation delivery
point from Northwest to PSE located within the Storage Project”. This Farm Tap serves
five (5) customers and is operated and maintained by PSE pressure control personnel that
are not part of the Jackson Prairie staff.
Please refer to the schematic in Figure 1.
II. Jackson Prairie Monitoring and Control
PSE personnel are present 24 hours, 7 days a week at Jackson Prairie. These employees
exclusively operate the station equipment within the Processing Facility boundaries and
the property limits of the adjacent Storage Field and the Feeder Lines. Per CRM FAQ
A.20, they do not remotely monitor and control the Feeder Lines outside of the fence line.
The Jackson Prairie Operations Center receives information from data points located
inside the fence line of the Processing Facility to ensure equipment, such as gas and fire
detectors, are operating safely. The data point on the west header line is located within
the fence and measures suction or discharge pressures of gas entering or exiting the
compressors. In the event the pressure goes above or below a predetermined safe
operating pressure, the automatic shut-off valve on the west header pipe is programmed
to close. Jackson Prairie also receives a duplicate screen shot from Northwest’s SCADA
system at the Meter Station for non-operational information purposes only.
- 2 -

<<<PAGE 7>>>

DocuSign Envelope ID: 1ED0C908-29A4-404A-B918-D17840D08AC3
Northwest Controllers remotely monitor the Meter Station through various data points
connected to their SCADA system at a CRM Rule compliant Control Room located in
Houston, Texas. The Northwest Controllers can remotely control the 20” and 24” tap
valves and are able to issue injection, withdrawal and shut in commands which activates
logic based configuration of various other valves in the Meter Station. In the event the
SCADA data indicates a safety related condition requiring a shut in command, the
Northwest Controllers would also notify Jackson Prairie personnel to take action at the
Processing Facility as needed. By default, the monitoring and control of the data points
at the Meter Station by the Northwest Controllers provides defacto remote monitoring
and control for the Feeder Lines. If an abnormal condition or emergency resulting in
release of gas or overpressure was to occur on any of the Feeder Lines, the resulting
pressure change would register at the data points at the Meter Station and the Northwest
Controller would take appropriate action, including contacting Jackson Prairie personnel.
If injection or withdrawal activities were in process at the time, the automatic shut-off
valve within the fence line of the Processing Facility would activate to isolate the
Processing Facility. Additionally, in the case of a pipeline rupture on any of the Feeder
Lines, Jackson Prairie personnel would get auditory or visual evidence of this due to the
short length of these lines and the local proximity to the Processing Facility.
Any issue with the 14” transmission line that feeds the Chehalis Farm Tap, would be
picked up by the inlet RTU that is monitored and controlled by Controllers in PSE’s
Control Room located in Redmond, Washington.
In the table below, we have outlined the Jackson Prairie configuration compared to the
CRM Rule’s definitions of Control Room, Controller, and SCADA system for easy
reference.
Defined Term -- 49 C.F.R. § 192.3 (emphasis
added).
Jackson Prairie Configuration
Control Room: an operations center staffed by
personnel charged with the responsibility for
remotely monitoring and controlling a pipeline
facility.
The operations center at Jackson Prairie is staffed by
“boots on the grounds” technicians with the
responsibility to locally monitor and control operation
within the fenced boundary of the Processing Facility and
the property limits of the adjacent Storage Field and the
Feeder Lines.
The Northwest operations center in Houston, Texas, is
staffed by personnel charged with the responsibility for
remotely monitoring and controlling the Meter Station
piping at the Jackson Prairie Storage Project Delivery
Point.
The PSE operations center in Redmond, Washington is
staffed by personnel charged with the responsibility for
remotely monitoring the inlet to the Chehalis Farm Tap.
- 3 -

<<<PAGE 8>>>

DocuSign Envelope ID: 1ED0C908-29A4-404A-B918-D17840D08AC3
Controller: a qualified individual who remotely
monitors and controls the safety-related
operations of a pipeline facility via a SCADA
system from a control room, and who has
operational authority and accountability for
the remote operational functions of the
pipeline facility
Jackson Prairie technicians are onsite and locally monitor
and control operation of the Processing Facility
equipment within the fenced boundary. JP personnel
have operational authority and accountability exclusively
for the Jackson Prairie Storage Project, except for the
Meter Station. The Storage Field and the Feeder Lines
are not connected to a SCADA system.
Northwest staffs its Houston, Texas Control Room with
qualified individuals that remotely monitor and control
the safety-related operations of the Meter Station via a
SCADA system from a Control Room. Northwest
personnel have operational authority and accountability
for the remote operational functions of the valves at the
Meter Station.
PSE staffs its Redmond, Washington Control Room with
qualified individuals that remotely monitor and control
the safety-related operations of the Chehalis Farm Tap
via a SCADA system from a Control Room. PSE personnel
in Redmond have operational authority and
accountability for the remote operational functions of
the Farm Tap.
Supervisory Control and Data Acquisition
(SCADA) system: a computer-based system or
systems used by a controller in a control room
that collects and displays information about a
pipeline facility and may have the ability to
send commands back to the pipeline facility
Operations Center at Jackson Prairie is limited to the
Processing Facility and all HMI data points are located
within the fenced boundary. The Operations Center at
Jackson Prairie is not a SCADA system used by a
Controller in a Control Room as those terms are defined
in the CRM Rule.
The Northwest SCADA system is used by a Controller in a
Control Room that collects and displays information
about the Meter Station; this information is used to
remotely control valves at the Meter Station. Northwest
personnel can also use this information to direct Jackson
Prairie personnel to take action at the Feeder Lines or
the Processing Facility.
The PSE SCADA system is used by a Controller in a
Control Room that collects and displays information
about the Chehalis Farm Tap inlet pressure; this
information is used to dispatch PSE pressure control
personnel to take action at the Farm Tap.
- 4 -

<<<PAGE 9>>>

DocuSign Envelope ID: 1ED0C908-29A4-404A-B918-D17840D08AC3
III. Conclusion
PSE believes that the operations center at Jackson Prairie does not fall within the scope of
the CRM Rule. Jackson Prairie field technicians are onsite and locally monitor and
control the operation of the Processing Facility equipment within the fenced boundary.
They have operational authority and accountability exclusively for the Processing Facility
within the fenced boundary, the Storage Field within the property limits, and the Feeder
Lines. Northwest has sole control over the safety related operations of the Meter Station.
While nothing in the CRM Rule requires pipeline operators to implement or use a
SCADA system to remotely operate facilities, the remote monitoring and control of the
Meter Station by Northwest effectively covers the Feeder Lines connecting the Meter
Station to the Processing Facility at Jackson Prairie.
PSE appreciates the Administrator’s time in providing a written interpretation of the
CRM Rule applicability to the unique operational setup of Jackson Prairie. Should you
have any questions, please contact Vidushi Raina, Gas Pipeline Safety Compliance
Program Manager, at 425-424-7839 or vidushi.raina@pse.com.
Sincerely,
Kaaren Daugherty
Manager, Compliance and Quality Management
Kaaren.daugherty@pse.com
Cc:
Troy Hutson, Puget Sound Energy
Mark Carlson, Puget Sound Energy
Pat Haworth, Puget Sound Energy
Rob Harmon, Williams Northwest Pipeline
Jody Morehouse, Avista
Sean Mayo, WUTC Director Pipeline Safety
John Gale, PHMSA Director Standards & Rulemaking
- 5 -

## Provenance

- Official: Yes
- Source: <https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/76426/puget-sound-energy-inc-pi-21-0007-04-18-2022-part192631.pdf>
- Source ID: `phmsa`
- SHA-256: `30d4214f5e8dd83e7cf2313eb8c415740eb0de31ec98eb4e8c21c2c1ec307476`
- Retrieved: 2026-08-20T00:59:31.977Z
- Exported: 2026-08-22T20:33:44.984Z
- Document slug: `phmsa-interpretation-pi-21-0007`

### Source metadata

```json
{
  "materialSubtype": "interpretation",
  "interpretationArea": "pipeline_safety",
  "representation": "full_text_from_official_pdf",
  "companies": [
    "Puget Sound Energy"
  ],
  "individuals": [
    "Kaaren Daugherty"
  ],
  "refIds": [
    "PI-21-0007"
  ],
  "catalogDates": [
    "2022-04-20"
  ],
  "catalogParts": [
    192
  ],
  "catalogRowCount": 1,
  "sourceRecordUrls": [
    "https://www.phmsa.dot.gov/node/73146"
  ],
  "linkedAttachmentUrls": [],
  "unavailableResponseUrls": [],
  "duplicateRepresentationUrls": [],
  "citedSections": [
    "192.631",
    "191.17",
    "192.12",
    "192.3"
  ],
  "catalogPageUrls": [
    "https://www.phmsa.dot.gov/regulations/title49/section/192631"
  ],
  "pdfUrls": [
    "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/76426/puget-sound-energy-inc-pi-21-0007-04-18-2022-part192631.pdf"
  ],
  "representations": [
    {
      "viewUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/76426/puget-sound-energy-inc-pi-21-0007-04-18-2022-part192631.pdf",
      "detailUrl": null,
      "detailHtmlPath": null,
      "pdfUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/docs/standards-rulemaking/pipeline/interpretations/76426/puget-sound-energy-inc-pi-21-0007-04-18-2022-part192631.pdf",
      "pdfArtifactPath": "data/sources/phmsa-interpretations/pi-21-0007.pdf",
      "pdfArtifactSha256": "c9840d9f3a9e3a65f9258067410383e9ceeb4dd72c33457378b41a54df830688",
      "extractedTextPath": "data/sources/phmsa-interpretations/pi-21-0007.v2.txt",
      "extractedTextSha256": "016ff70a35fbb72c6ed3964034bef4d1947d582c6159819e2ae12411259e410b",
      "pageCount": 9,
      "extractionVersion": 2
    }
  ],
  "caveat": "Interpretations apply regulations to the facts presented and do not create independently enforceable requirements.",
  "jurisdiction": "US"
}
```
