PI-78-0106
September 21, 1978
Mr. Warren McDonald, President
Tampa Pipe Line Corporation
P.O. Box 19201
Tampa, Florida 33686
Dear Mr. McDonald:
We have received a letter from Gonzalo Ancira of Ancira Engineering Services, Inc., in response to our letter to
you dated July 21, 1978, outlining proposed requirements your Corporation must meet to properly inhibit
stress-corrosion cracking on the Tampa-Bartow anhydrous ammonia pipeline. Mr. Ancira's letter indicates that
you have no objection to these requirements.
In view of the above, please be advised that the order dated July 9, 1978, prohibiting transport of the
commodity in the proposed manner is hereby lifted as long as the requirements in our July 21 letter are met.
Mr. Ancira raised the question about the Department's regulatory jurisdiction over the pipeline. We believe
the pipeline is engaged in foreign commerce, and thus subject to 49 CFR 195, because the only two consignees
on the pipeline purchase the commodity directly from a foreign source and there are no other deliveries made
to or from the terminal tanks used to store the commodity.
Sincerely,
SIGNED
Cesar De Leon
Associate Director for
Pipeline Safety Regulation
Materials Transportation Bureau

<<<PAGE 2>>>

Ancira Engineering Services, Inc.
Suite 228
Hamilton Hotel
P.O. Box 480
Laredo, Texas 78040
August 7, 1978
Mr. Cesar de Leon
Associate Director for Pipeline Safety Reg.
Material Transportation Bureau
Department of Transportation
Washington, D. C. 20590
Dear Mr. de Leon:
With reference to your letter dated July 2, 1978 to Mr. Warren McDonald, Tampa Bay Pipeline
Corporation, we would like to call your attention the following observations in the same sequence as your
letter.
Tampa Bay Pipeline Corporation will monitor the water content of the Anhydrous Ammonia and will
not accept ammonia for shippment which does not meet the Federal requirement of 0.2% water content.
Tampa, however; will not be permitted to alter the quality of the product without consent from the shipper
and so far the shipper has advised that they have provisions for injecting water into the ammonia system
themselves.
Tampa Bay Pipeline Corporation has contracted the Thornton Laboratories of Tampa, Fla. to run
analysis and monitor all ammonia shipments.
The proposed prescribed requirements as outlined in your letter will be meet as follows:
1 - Water content will be 0.20 percent.
2 - Carrier is providing a monitor system and run the necessary analysis of each shipment insure that
the shipper has complied with thas requirement.
3 - The carrier has prepared and established written proceedures of the pipeline system in compliance
with 195.402 of the minimum Federal Safety Standards for liquid pipelines.
Tampa Bay Pipeline accepts full responsibility for the quality of product to be transported and all
product not meeting said requirement will not be accepted for shipment.
In reviewing the minimum Federal Safety Standars for liquid pipelines with our legal department, it was
called to our attention that under subpart A- General 195.1 scope, our pipeline is intrastate and you should
not have any jurisdiction if jou claim jurisdiction based on foreign commerce of hazardous material, our legal
departament claims that no such foreign commerce exists between the carrier and the shipper nameley
(Tampa-RoysterGrace). The fact that some of the ammonia is of foreign origen constitutes foreign commerce
at the port of entry between the shippers storage and thevessel making the delivery from a foreign source.
Our legal departament advises us that Tampa Bay Pipeline is in no way involved in foreign commerce, if
we are, please advise in writting how we can be classified as such.
Tampa Bay will comply with all Federal regulations for safety purposes regardless of whether or not we
are under your jurisdiction or not.
Yours very truly,
Gonzalo Ancira

<<<PAGE 3>>>

July 21, 1978
Mr. Warren McDonald
Tampa Pipe Line Corporation
P.O. Box 19201
Tampa, Florida 33686
Dear Mr. McDonald:
We have received a letter from Gonzalo Ancira of Ancira Engineering Services, Inc., Laredo, Texas, in response
to our Order dated June 9, 1978, concerning the potential stress corrosion cracking problem on the proposed
Tampa-Bartow anhydrous ammonia pipeline. His letter indicates that the Tampa Pipeline Corporation's plan to
inhibit stress corrosion cracking in the pipeline amounts to submitting certifications from the shippers that the
water content of the commodity to be transported will not be below 0.30 percent.
We do not find that this proposed plan provides an acceptable means of assuring protection against stress
corrosion cracking because (1) the means of protection would be under the control of the shipper rather than
the carrier and, (2) since water content is subject to change, the plan should include a way to satisfactorily
monitor the percentage of water content and to maintain a proper percentage.
We propose to prescribe the following requirements to properly inhibit stress corrosion cracking on the
Tampa-Bartow pipeline:
1. The water content of anhydrous ammonia transported in the pipeline must not be less than 0.20
percent by volume.
2. The carrier shall monitor the water content and add water into the system if necessary.
3. The operating procedures prepared under Section 195.402 must include provisions for monitoring and
maintaining water content.
You are invited to submit comments on these proposed requirements by August 31, 1978, so that we may
consider them before issuing a final order on the manner in which anhydrous ammonia may be transported in
the Tampa-Bartow pipeline.
Consistent with Mr. Ancira's proposed action and Section 195.10, you might wish to make arrangements with
the shippers to meet proposed requirements 1 and 2 above (e.g., by checking the water content of each
shipment prior to its delivery to the pipeline). Doing so, however, would not relieve the Tampa Pipeline
Corporation of any responsibility for compliance.
Sincerely,
SIGNED
Cesar De Leon
Associate Director for
Pipeline Safety Regulation Materials Transportation Bureau

<<<PAGE 4>>>

Ancira Engineering Services, Inc.
Suite 228
Hamilton Hotel
P.O. Box 480
Laredo, Texas 78040
June 27, 1978
Mr. Cesar De Leon
Associate Director For Pipeline
Safety Regulation
Material Transportation Bureau
Department of Transportation
Washington, D.C. 20590
Subject: Tampa Bay Pipeline Corp.
Provision for Inhibit Stress Corrosion.
Dear Mr. De Leon:
Please refer to your letter dated June 9, 1978 to Mr. Warren McDonald on subject matter. We have
fully complied with the inhibitor requirement by requiring that all shippers, namely W.R. Grace and Royster
furnish the anhydrous ammonia with the inhibitor already in it.
We are here-by submitting to you, a copy of such compliance in writting by W.R. Grace, Royster
certification will follow.
As soon as such certification is in your power, we will request that you kindly remove the restriction
placed on our pipeline system. Or advice if there is any other certification you may require from us.
Yours Very Truly,
Gonzalo Ancira

<<<PAGE 5>>>

Agricultural Chemicals Group
W.R. Grace & Co.
P.O. Box 630
Wilmington, N.C. 28401
June 21, 1978
Mr. W. R. McDonald
Tampa Bay Pipeline
c/o Tampa Pipeline Corporation
P. O. Box 19201
Tampa, Florida 33616
Dear Warren:
Subject: W. R. Grace Ammonia Terminal, Port Sutton
This is to certify that the ammonia received for storage and reshipment through the subject terminal
will at all times be 0.30% minimum water content per our anhydrous ammonia agricultural grade product
specifications.
Sincerely,
W. R. Grace & Co.
James L. Smith
Chief Engineer

<<<PAGE 6>>>

June 9
Mr. Warren McDonald
Tampa Pipe Line Corporation
P.O. Box 19201
Tampa, Florida 33686
Dear Mr. McDonald:
This refers to our letter dated April 11, 1973, to Mr. Shields D. Clark III, West Coast Engineering Corporation
(copy enclosed), regarding a proposed anhydrous ammonia pipeline between Tampa and Bartow, Florida.
Our investigation indicates that apparently no provision has been made to inhibit stress-corrosion cracking, a
problem of particular concern with this type of pipeline. For this reason, we have determined that the
transportation of the commodity in the proposed manner would be unduly hazardous. Therefore, in
accordance with 49 CFR 195.6(a), you are hereby ordered not to transport the commodity in the proposed
manner until further notice.
Please submit your plans to address the stress-corrosion cracking problem.
Sincerely,
SIGNED
Cesar De Leon
Associate Director for
Pipeline Safety Regulation
Materials Transportation Bureau

## Provenance

- Official: Yes
- Source: <https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1978/g78-09-21_McDonald_195.1-wmx.pdf>
- Source ID: `phmsa`
- SHA-256: `7fb346b9e246e0f13aa791a430f67ee5edff17bd2de33ead9abb4b73d59dd2c3`
- Retrieved: 2026-08-20T00:59:31.977Z
- Exported: 2026-08-25T02:49:58.497Z
- Document slug: `phmsa-interpretation-pi-78-0106`

### Source metadata

```json
{
  "materialSubtype": "interpretation",
  "interpretationArea": "pipeline_safety",
  "representation": "full_text_from_official_pdf",
  "companies": [],
  "individuals": [],
  "refIds": [
    "PI-78-0106"
  ],
  "catalogDates": [
    "1978-09-21"
  ],
  "catalogParts": [
    195
  ],
  "catalogRowCount": 1,
  "sourceRecordUrls": [
    "https://www.phmsa.dot.gov/node/47371"
  ],
  "linkedAttachmentUrls": [],
  "unavailableResponseUrls": [],
  "duplicateRepresentationUrls": [],
  "citedSections": [
    "195.1",
    "195.402",
    "195.10",
    "195.6(a)"
  ],
  "catalogPageUrls": [
    "https://www.phmsa.dot.gov/regulations/title49/section/1951"
  ],
  "pdfUrls": [
    "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1978/g78-09-21_McDonald_195.1-wmx.pdf"
  ],
  "representations": [
    {
      "viewUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1978/g78-09-21_McDonald_195.1-wmx.pdf",
      "detailUrl": null,
      "detailHtmlPath": null,
      "pdfUrl": "https://www.phmsa.dot.gov/sites/phmsa.dot.gov/files/legacy/interpretations/Interpretation%20Files/Pipeline/1978/g78-09-21_McDonald_195.1-wmx.pdf",
      "pdfArtifactPath": "data/sources/phmsa-interpretations/pi-78-0106.pdf",
      "pdfArtifactSha256": "07c1a49b1b132c2d1bbddc29b21abc93532fb16cc1569d9e065f3f025e778af8",
      "extractedTextPath": "data/sources/phmsa-interpretations/pi-78-0106.v2.txt",
      "extractedTextSha256": "0a2999c20e5566b655e5b19b6b70ac7fa524388b0269ea3df1a6ce4cc562efe2",
      "pageCount": 6,
      "extractionVersion": 2
    }
  ],
  "caveat": "Interpretations apply regulations to the facts presented and do not create independently enforceable requirements.",
  "jurisdiction": "US"
}
```