# Texas Gas Transmission LLC — Pipeline Special Permit

**Citation:** PHMSA-2008-0067  
**Type / status:** permit / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** 2008-07-31  
**Published:** 2008-07-31

PHMSA-2008-0067, issued 2008-07-31 for Texas Gas Transmission LLC's gas transmission system.

## Document text

PHMSA pipeline special permit PHMSA-2008-0067. Operator: Texas Gas Transmission LLC. System: Gas Transmission. Issue date: 2008-07-31.

<<<PAGE 1>>>

BOARDWALK
SEP 2 8 2010
OOO
PIPELINE PARTNERS™
September, 27, 2010
Mr. Jeffrey Wiese
JS Department of Transportation
Issociate Administrator for Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
1200 New Jersey Avenue, SE E22
Washington, DC 20590
Re:
Notice to Increase Operating Pressures up to Special Permit Levels on the
Fayetteville Lateral Only, under the Special Permit issued July 31, 2008
("Special Permit") and the Modification Agreement, dated April 30, 2009,
as Amended
Documents");
and Supplemented (collectively, "Special Permit
Fayetteville/Greenville Lateral Pipelines, Docket No. PHMSA-2008-0067
Dear Mr. Wiese:
Boardwalk Pipeline Partners, LP, by and through its subsidiary Texas Gas Transmission,
LLC (hereinafter "Boardwalk"), in cooperation with the Pipeline and Hazardous Materials Safety
Administration (hereinafter "PHMSA"), has been actively engaged in satisfying the terms and
conditions set forth in the Special Permit Documents. As part of those terms and conditions,
Boardwalk is required to provide PHMSA with thirty (30) days prior notice of its intent to
operate the applicable pipeline at Special Permit operating pressures. This letter shall serve as
Boardwalk's thirty (30) day prior notice for the Fayetteville Lateral only. Boardwalk will, at a
later date, submit a similar thirty (30) day notice to PHMSA to operate the Greenville Lateral at
Special Permit operating pressures.
With respect to the Fayetteville Lateral, Boardwalk has satisfied all of the terms and conditions
of the Special Permit Documents, except for those two conditions discussed below. Specifically,
Boardwalk has successfully implemented Conditions 1 (Steel Properties), 2 (Manufacturing
Standards), 3 (Fracture Control), 4 (Steel Plate Quality Control), 5 (Pipe Seam Quality Control),
6 (Mill Hydrostatic Test), 7 (Pipe Coating), 8 (Field Coating), 9 (Coatings for Trenchless
Installation), 10 (Bends Quality), 11 (Fittings), 12 (Design Factor - Pipelines), 13 (Temperature
Control), 14 (Overpressure Protection Control), 15 (Welding Procedures), 16 (Depth of Cover),
@GUL CROSSING
, GULF SOUTH'
OH, LLO
9 Greenway Plaza, Sulte 2800, Houston, Texas 77046 713.479.8000

<<<PAGE 2>>>

BOARDWALK
PIPELINE PARTNERS™
17 (Construction Quality), 18 (Interference Currents Control), 19 (Test Level), 20
(Assessment of Test Failures), 21 (SCADA System Capabilities), 22 (SCADA Procedures), 23
(Mainline Valve Control), 24 (Pipeline Inspection), 25 (Gas Quality Monitoring), 28 (Gas
Quality Control), 29 (Gas Quality Monitoring Equipment), 33 (Verification of Cathodic
Protection), 36 (Pipeline Markers), 44 (Potential Impact Radius Calculation Updates), and 46
(Reporipel- 30 day) during the design, pipe manufacturing, construction and operating phases
In addition, the following conditions of the Special Permit have been incorporated into
the Boardwalk Operations & Maintenance Manual: Condition 3 (Fracture Control), 7 (Pipe
Coating), 8 (Field Coating), 9 (Coatings for Trenchless Installation), 10 (Bends Quality), 11
(Fittings), 12 (Design Factor - Pipelines), 13 (Temperature Control), 14 (Overpressure
Protection Control), 16 (Depth of Cover), 18 (Interference Currents Control), 21 (SCADA
System Capabilities), 22 (SCADA Procedures), 23 (Mainline Valve Control), 24 (Pipeline
Inspection), 25 (Gas Quality Monitoring), 26 (Pigging Plan), 27 (H2S Sampling), 28 (Gas
Quality Control), 29 (Gas Quality Monitoring Equipment), 30 (Cathodic Protection), 31
(Interference Current Surveys), 32 (Corrosion Surveys), 33 (Verification of Cathodic Protection),
34 (Initial CIS), 35 (Initial Coating Assessment), 36 (Pipeline Markers), 37 (Pipeline Patrolling),
38 (Monitoring of Ground Movement), 39 (Initial ILL), 40 (Future ILI), 41 (Direct Assessment
Plan), 42 (Damage Prevention Program), 43 (Anomaly Evaluation and Repair), 44 (Potential
Impact Radius Calculation Updates), 45 (Reporting - Immediate), 46 (Reporting - 30 Day), and
47 (Annual Reporting).
For Condition 31 (Interference Current Surveys), Boardwalk completed the interference
surveys within six (6) months of placing the Fayetteville Lateral pipeline in service. Since that
time, Boardwalk discovered interference issues at two foreign pipeline crossing locations at
Station 3383+77 and Station 3365+29. Site-specific interference tests were completed at each of
these two pipeline crossings, and the sites were both excavated and remediated to address the
interference issues. To ensure the remediation was effective, in September of 2010, Boardwalk
performed a close interval survey (CIS) of the entire Fayetteville Lateral, including these two
locations, and the CIS data confirms there are no interference issues on the entire pipeline and
the stray currents at these two specific locations have been remedied. (For more detailed
information, please see the attached Special Permit Book in CD format, hereinafter "Special
Permit CD." These interference issues and mitigative measures will also be reported in the next
& GULF CROSSING GULFSOUTH
TEXAS OAS
9 Greenway Plaza, Suite 2800, Houston, Texas 77046 713.479.8000

<<<PAGE 3>>>

BOARDWALK
OOO
PIPELINE PARTNERS™
For Condition 35 (Initial Coating Assessment), the required DCVG testing was
completed on the Fayetteville Lateral with the exception of some in-accessible waterways and
flooded areas that were not feasible to access with DCVG or ACVG surveys. These skipped
(PCM). When both CIS and PCM data are integrated, a determination of the coating condition
under the body of water can be made. The PCM and CIS field work has been completed for
these skip areas. Integration of the CIS and PCM data is currently being analyzed. The
threshold levels for monitored, scheduled, and immediate anomaly response will be established
utilizing the criteria set forth in the Boardwalk External Corrosion Direct Assessment Plan. In
any event, Boardwalk will submit a separate letter to PHMSA to confirm the completion of this
Condition 35 prior to operating the Fayetteville Lateral at Special Permit pressures.
Please consider this letter as Boardwalk's thirty (30) day notice of intent to increase its
operating pressures to those
set forth in the Special Permit for the Fayetteville Lateral.
Specifically, Boardwalk intends to operate the Fayetteville Lateral with design factors of 0.80 in
Class 1 and 0.67 in Class 2 locations. As noted above, the Greenville Lateral will not be
operated under the Special Permit until such time as Boardwalk sends a similar notice to
PHMSA certifying completion of all the conditions of the Special Permit Documents for the
Greenville Lateral.
For your convenience, please find attached to this letter the Special Permit CD. The
Special Permit CD contains documentation of Boardwalk's compliance with the conditions of
the Special Permit Documents. Boardwalk requests that PHMSA treat the information contained
on the Special Permit CD as "confidential business information" and that Boardwalk is deemed a
"submitter" within the meaning of the Freedom of Information Act, 5 U.S.C. § 552.
& GULF CROSSING
GULF SOUTH
* TAXAS AR
9 Greenway Plaza, Suite 2800, Houston, Texas 77046 713.479,8000

<<<PAGE 4>>>

...
..
BOARDWALK
:
O00
PIPELINE PARTNERS™
Boardwalk appreciates PHMSA's continuing efforts to address these important issues. If
you have any questions or require any additional information, please contact Frank Maraia at
(985) 898-1004 or Frank.Maraia@bwpmlp.com.
Sincerely,
and bood.
David Goodwin
Vice President
cc: Mr. Rod Seeley
Ms. Linda Daugherty
Mr. Alan Mayberry
Mr. Wayne Lemoi
Mr. Chris Taylor
Mr. Anthony Rallis
& GULF CROSSING
GULF SOUTH"
TEXAS A
9 Greenway Plaza, Sulte 2800, Houston, Texas 77046 713.479.8000

## Provenance

- Official: Yes
- Source: <https://www.regulations.gov/docket/PHMSA-2008-0067>
- Source ID: `phmsa-special-permits`
- SHA-256: `8ef2806f058fdd57260b6d6d2ea749d8f9667903059b30c0bcaacba37d6c181c`
- Retrieved: 2026-08-20T01:06:17.853Z
- Exported: 2026-08-22T05:33:45.543Z
- Document slug: `phmsa-special-permit-phmsa-2008-0067`

### Source metadata

```json
{
  "materialSubtype": "pipeline_special_permit",
  "operator": "Texas Gas Transmission LLC",
  "system": "Gas Transmission",
  "issuedOn": "2008-07-31",
  "issuanceStatus": "issued",
  "renewal": null,
  "indexUrl": "https://www.phmsa.dot.gov/pipeline/special-permits-state-waivers/special-permits-issued",
  "docketUrl": "https://www.regulations.gov/docket/PHMSA-2008-0067",
  "docketDocumentCount": 14,
  "decisionDocumentCount": 1,
  "decisions": [
    {
      "id": "PHMSA-2008-0067-0011-0900006480e91fd6",
      "regulationsGovDocumentId": "PHMSA-2008-0067-0011",
      "title": "Notice to PHMSA from Oprator (Increase of Operating Pressure as per Existing Special Permit Conditions)(Fayetteville Lateral)",
      "postedDate": "2010-10-18",
      "documentUrl": "https://www.regulations.gov/document/PHMSA-2008-0067-0011",
      "pdfUrl": "https://downloads.regulations.gov/PHMSA-2008-0067-0011/attachment_1.pdf",
      "pdfArtifactPath": "data/sources/phmsa-special-permits/artifacts/phmsa-2008-0067/phmsa-2008-0067-0011.pdf",
      "pdfArtifactSha256": "33675d4e1b056b337ec9a8e9b18f8b4424ef73819b7b38d6a8d52543ddcdf9ff",
      "extractedTextPath": "data/sources/phmsa-special-permits/artifacts/phmsa-2008-0067/phmsa-2008-0067-0011.txt",
      "extractedTextSha256": "06191d31b8ba6c420decdfa6788ec8bb01eae06a90f8e636afffff32909be3d9",
      "pageCount": 4,
      "extractionVersion": 2
    }
  ],
  "citedSections": [],
  "caveat": "The issued-permit index establishes issuance, not current validity or applicability to facilities beyond those covered by the permit. Read the official decision and conditions.",
  "jurisdiction": "US",
  "operatorName": "Texas Gas Transmission LLC"
}
```