# U.S. DOT/RSPA - Final Regulatory Evaluation - Pipeline Integrity Management in High Consequence Areas (Gas Transmission Pipelines)

**Citation:** 0900006480e8a887  
**Type / status:** rulemaking / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** Not stated

U.S. Department of Transportation Research and Special Programs Administration Final Regulatory Evaluation Pipeline Integrity Management in High Consequence Areas (Gas Transmission Pipelines) Docket RSPA-00-7666 35-6 The technical requirements, costs, and benefits associated with this alternative would be identical to those for the ‘‘no action” alternative, since the substantive technical requirements would be the samc, i.e., those imposed by the Act. As described above, RSPNOPS determined that those requirements would result in...

## Document text

<<<PAGE 1>>>

U.S. Department of Transportation
Research and Special Programs Administration
Final Regulatory Evaluation
Pipeline Integrity Management in High Consequence Areas
(Gas Transmission Pipelines)
Docket RSPA-00-7666 35-6

<<<PAGE 2>>>

INTRODUCTION
The U.S. Department of Transportation Research and Special Programs Office of Pipeline Safety
(RSPA/OPS) is changing pipeline safety regulations to require operators of certain pipelines to
validate the integrity of their pipelines in high consequence areas. The rule applies to operators of
natural and other gas transmission pipelines. The objective of the change is to reduce the risk of
pipeline incidents in these areas. High consequence areas are redefined in this rule. Under the
redefinition, operators must choose one of two options to designate high consequence areas:
All class 3 & 4 locations (these are areas where there are at least 46 buildings intended for
human occupancy or where buildings with four or more stories above ground are prevalent
within 660 feet of the pipeline along any continuous mile of its length) plus areas where a
potential impact circle of radius greater than 660 feet includes 20 or more buildings
intended for human occupancy, or
a Locations where the potential impact circle, of whatever size, includes 20 or more
buildings intended for human occupancy.
Under either option, pipeline operators must also include as high consequence areas any potential
impact circle that contains:
a A hospital, school, prison, day care center or other facility having persons who are
confined or of limited mobility, or
Outdoor locations or open structures where 20 or more persons congregate at least 50 days
in any 12-month period, or
A building in which 20 or more persons gather 5 days a week for 10 weeks in any 12-
month period (the days and weeks need not be consecutive).
The potential impact circle used in any of these determinations is a circle, centered on the
pipeline, of a radius calculated based on the size and pressure of the pipeline. The potential
impact circle approximates the area that could be affected by a rupture and subsequent explosion
occurring on the pipeline.
To validate the integrity of their pipelines in high consequence areas under the regulatory change,
pipeline operators must implement an integrity management program for such pipelines including
periodic inspection and testing and integration of information related to pipeline integrity. The
purpose of this report is to assess the benefits and costs of the regulatory change.
This rule is similar to rules promulgated earlier for hazardous liquid pipeline operators. High
consequence areas were defined differently for hazardous liquid pipelines, because the
1

<<<PAGE 3>>>

environmental consequences of leaks from hazardous liquid pipelines are different than those
from natural gas pipelines. The elements of an integrity management program required by this
rule are similar, however, to the elements previously required of hazardous liquid pipeline
operators. This report considers the costs and benefits of these requirements in a manner similar
to the analysis of costs and benefits prepared for the earlier rulemakings.
TARGET PROBLEM
Natural and other gas pipeline breaks can result in explosions and fires that can impact on human
health and safety. The magnitude of this impact differs. There are some areas in which the
impact of a pipe break will be more significant than it would be in others due to concentrations of
people near the pipeline and who thus could be affected. Because of the potential for dire
consequences of pipeline failures in certain areas, these areas merit a higher level of protection.
The OPS is promulgating this regulation to afford the necessary additional protection to these
“high consequence areas”.
Numerous investigations by RSPNOPS and the National Transportation Safety Board (NTSB)
have highlighted the importance of protecting the public from pipeline failures. The NTSB has
made several recommendations to ensure the integrity of pipelines near populated areas. These
recommendations included requiring periodic testing and inspection to identify corrosion and
other damage, establishing criteria to determine appropriate intervals for inspections and tests, and
determining hazards to public safety from electric resistance welded pipe.
Congress also directed RSPAIOPS to undertake additional safety measures in areas that are
densely populated. These statutory requirements included having RSPA/OPS prescribe standards
for identifying pipelines in high density population areas and issue standards requiring periodic
inspections using internal inspection devices on pipelines in densely-populated areas.
This rulemaking addresses the target problem described above, and is a comprehensive response
to the NTSB’s recommendations and Congressional mandates, as well as pipeline safety and
environmental issues raised over the years.
ALTERNATIVES CONSIDERED
The OPS considered several alternatives to provide the necessary increased level of protection to
high consequence areas. These alternatives were:
1. No action.
2. Publishing a rule that would adopt requirements of the Pipeline Safety Improvement Act of
2002 and establish procedures to seek waiver of reassessment intervals
3. Prescriptive requirements for inspection and repair of pipelines in high consequence areas.
4. Requiring pipeline operators to develop integrity management programs providing for
inspection and testing based on risk factors and integration of information related to pipeline risk.
2

<<<PAGE 4>>>

5 . Requiring pipeline operators to develop integrity management programs providing for
expedited inspection and testing.
INITIAL SCREENING OF ALTERNATIVES
1. No action.
Regulatory analyses typically consider an alternative in which the agency would not take any
action, because it would maintain the status quo. No new requirements would be levied. No costs
would be incurred to implement new requirements. No new benefits would result. In this case,
however, the “no action” alternative does not maintain the status quo. The status quo has been
changed by Act of Congress.
The Pipeline Safety Improvement Act of 2002 (PSIA-2002)’ signed into law on December 17,
2002, imposes requirements directly on pipeline operators. To be sure, PSIA-2002 directs the
Secretary of Transportation to publish, within one year, standards for integrity management plans
that would require periodic assessment of pipelines in high consequence areas. PSIA-2002 goes
on to require that operators of gas transmission pipelines, regardless of whether or not the
Secretary publishes such standards, must conduct a risk analysis, implement integrity management
programs, and begin baseline assessments of their pipeline facilities in high consequence areas
within 18 months. Baseline assessments must be completed on all gas transmission pipeline
segments in high consequence areas within 10 years. Each gas transmission pipeline segment in a
high consequence area must be reassessed at least every 7 years.
The assessment requirements in PSIA-2002 apply to “each of the operator’s facilities in areas
identified pursuant to subsection (a)(l) [of 49 U.S.C. 5 601091 and defined in chapter 192 of title
49, Code of Federal Regulations, including any subsequent modifications’’ (emphasis added)’.
The cited provision of the U.S. Code is the legislative requirement that the DOT establish criteria
for identifyng pipelines in high-density population areas, or high consequence areas. The
reference to the definition in title 49 of the Code of Federal Regulations is thus a reference to the
definition of high consequence areas established by DOT. The applicability of the Act’s
requirements to any “subsequent modifications” of that definition allows the DOT to revise its
criteria and further focus the actions required of pipeline operators. Absent a change to the
definition embodied in part 192, however, operators would be required to conduct assessments of
all pipeline segments meeting the current definition.
RSPNOPS has, in fact, been considering changes to the definition of high consequence areas in
part 192 to further refine the criteria and to focus better on areas most at risk and for which special
requirements are appropriate. Making those changes would reduce the amount of pipeline on
which integrity assessments are required to be performed without significantly reducing the
‘Pipeline Safety Iniprovement Act of 2002, Section 14, “Risk Analysis and Integrity Management Programs
for Gas Pipelines”
3

<<<PAGE 5>>>

benefits to be realized from those assessments.
PSIA-2002 requires that the pipeline assessments specified in the Act must be conducted using in-
line inspection, pressure testing, or direct assessment. The Act also allows assessments to be
conducted using “an alternative method that the Secretary [of Transportation] determines would
provide an equal or greater level of safety”.* Here, again, RSPNOPS has been considering
additional methods for conducting assessments. Confirmatory Direct Assessment (CDA) was
discussed in the proposed rule for integrity management in gas transmission pipeline^.^ This
method allows for assessment of pipeline integrity at less cost to operators and resulting in less
potential interruption in pipeline operations. In addition, RSPNOPS has been considering
alternative methods of assessing low-pressure pipeline, for which pipe wall stresses are much
lower and failure by leakage is much more likely than ruptures, which would also provide
assurance of integrity at less cost than the methods specified in PSIA-2002.
Taking no action would leave the definition of high consequence areas in part 192 unchanged. It
would also mean that no alternative method, other than those specified in PSIA-2002, could be
defined for conducting assessments of gas transmission pipelines in high consequence areas. The
result would be conduct of assessments on more pipeline than is needed to address the underlying
safety issue using more expensive assessment methods. RSPNOPS evaluated the costs operators
would incur under this alternative, as described in the appendix to this analysis, and found that
they would be significantly higher than those that would result from other alternatives.
In addition, taking no action would not be responsive to the requirement in PSIA-2002 that DOT
“issue regulations prescribing standards to direct an operator’s conduct of a risk analysis and
adoption and implementation of an integrity management p r ~ g r a m . ” ~
For these reasons, the “no action” alternative was not considered further
2. Publishing a rule that would adopt requirements of the Pipeline Safety Improvement Act of
2002 and establish procedures to seek waiver of reassessment intervals
PSIA-2002 allows the Secretary of Transportation to waive or modify requirements for
reassessments for reasons that may include the need to maintain local product supply or the lack
of internal inspection devices, provided that such a waiver is not inconsistent with pipeline safety.
Another alternative would be to publish a rule that adopts the substantive requirements of PSIA-
2002, without change, but establishes procedures for approving the allowed waivers.
’Ibid
‘Feifernl Register, January 28, 2003 (68 FR 4278), “49 CFR 192, Pipeline Safety: Pipeline Integrity
Management in High Consequence Areas (Gas Transmission Pipelines); Proposed Rule”.
4 . Pipeline Safety Improvement Act of 2002, Section 14, “Risk Analysis and Integrity Management Programs
for Gas Pipelines”
4

<<<PAGE 6>>>

The technical requirements, costs, and benefits associated with this alternative would be identical
to those for the ‘‘no action” alternative, since the substantive technical requirements would be the
samc, i.e., those imposed by the Act. As described above, RSPNOPS determined that those
requirements would result in unnecessary expense for assessments using the most costly methods
to address more pipeline than RSPNOPS has determined is necessary to address the underlying
safety need.
For this reason, the option of publishing a rule that only establishes procedures for waivers was
not evaluated flirther.
3. Prescriptive requirements for inspection and repair of pipelines in high consequence areas and
for incorporating accident mitigative features.
Pipeline circumstances differ, even within high consequence areas. These differences would
make it difficult, at best, to establish prescriptive requirements that would appropriately address
all possible combinations of pipeline size, type, and configuration or to consider other factors that
contribute to the risk of failure of a particular pipeline. It is likely that creating detailed
prescriptive requirements would result in a need for a large number of waivers to address the
issues of importance to specific pipelines and high consequence areas. The result would be a
patchwork of specific, but different requirements. It would be an inefficient use of industry and
government resources to establish requirements in this fashion.
Prescriptive requirements also would tend to stifle technological innovation. They do not allow
for different approaches based on advances in the technology. The technology associated with in-
line inspection of pipelines (Le., pigging) is advancing at a rapid pace. Establishing prescriptive
requirements could slow this advancement, or could preclude use of new techniques that may be
developed. In the extreme, prescriptive requirements could stop technological innovation in this
area completely.
Establishing prescriptive requirements would not assure the integration of information, which
experience has shown is vital to preventing pipeline accidents. Two major pipeline accidents
have occurred in recent years despite the fact that information about the causative factors should
have, or could have, been known - at Edison Township, NJ and Carlsbad, NM. In the first case,
in-line inspection (pigging) of the pipeline had taken place. The operator either failed to identify,
during the pig runs, the areas of damage that eventually caused the rupture or the damage occurred
in the years following the inspection. In addition, the operator failed to integrate information
about the pipeline, including the presence of significant construction activity in the area, in a
continuing assessment of the line’s integrity, In the latter case, the accident resulted from internal
corrosion due to collection of moisture in a low spot which could not be inspected by pigging.
The operator failed to consider the possibility of such accumulation of moisture and resulting
corrosion and thus did not intercede to prevent the pipeline failure. It appears that information
was available that, if correlated to current pig results (in the case of Edison Township) or other
information about the pipeline, could have highlighted the need for action regarding the problems
5

<<<PAGE 7>>>

that ultimately resulted in failure of the pipe.
An integrity management program is required to assure this integration of available information.
Outside review of the integrity management program by regulators (Federal and state), is
necessary to assure that it is complete and properly implemented. This outside review cannot be
assured without a requirement for such a program that establishes the requirements against which
such a review will be conducted.
Most importantly, establishing prescriptive requirements would not be consistent with
requirements imposed by PSIA-2002. The Act requires that DOT prescribe rules to direct an
operator’s conduct of a risk assessment and adoption and implementation of an integrity
management program. Prescriptively establishing when and where integrity assessments must be
performed would be inconsistent with the requirements of the Act.
For these reasons, the option of establishing prescriptive requirements was not evaluated further.
4. Requiring pipeline operators to develop integrity management programs providing for
inspection and testing based on risk factors and integration of infomation related to pipeline risk.
Pipeline operators are uniquely qualified to develop integrity management programs and provide
for the necessary integration of information. They have the best knowledge of their pipelines and
the factors affecting its risk. Integration of information requires that the management systems of
the company be aligned and operated to assure that necessary information is shared and that it is
evaluated in its proper context by knowledgeable personnel. These are actions that are difficult to
require through prescriptive regulation. Requiring that operators develop such programs is the
best way to assure that they exist. Such a requirement also provides the regulatory basis for
RSPA/OPS and states to audit, review, and assess these programs and their implementation.
The best integrity management plans, when implemented properly, can reduce the risk of pipeline
accidents. They cannot, however, eliminate that risk. Leaks and ruptures could still occur, from
unforeseen outside impacts on the pipeline or from unanticipated interactions among factors
contributing to pipeline risk. It is therefore important that features and procedures be available to
mitigate the effects of accidents that may occur.
Here again, circumstances differ between pipelines and between regions and local jurisdictions.
The differences make it difficult to establish prescriptive requirements that will provide the best
protection for each high consequence area. Requiring that operators explicitly consider the need
for mitigative features and provisions and that they implement those found necessary is the most
effective means of providing such protection. Such a requirement also provides the regulatory
basis for audit and review by RSPNOPS and state regulators.
Establishing requirements for operators to develop and adopt integrity management programs is
also most consistent with the requirements imposed on DOT by PSIA-2002. This option also
6

<<<PAGE 8>>>

allows RSPNOPS to make changes in the definition of high consequence areas to improve the
focus of the new requirements, and to establish alternative methods that are acceptable for
performing integrity assessments. Both of these changes will reduce the costs imposed on
industry without significantly reducing the benefits to be realized.
For these reasons, this option was selected for further development.
5 . Requiring pipeline operators to develop integrity management programs providing for
expedited inspection and retesting.
RSPMOPS considered the need for requiring integrity management programs that would require
inspection and testing of pipelines to recur over short intervals, e.g., a few years. The ability to
require frequent testing is limited by the available resources for testing and inspection.
The companion rule covering hazardous liquid pipelines requires reassessments at least every five
years, with limited exceptions. The current capacity to perform pipeline inspections will be
challenged by this required schedule. The OPS concluded that the spur provided by the regulation
would be likely to result in an increase in testing capacity over the next five years that will then be
able to accommodate testing at accelerated rates. The OPS also concluded that protection from
environmental damage that can be caused by a leak or rupture of a hazardous liquid pipeline, and
the occurrelice in hazardous liquid pipelines of frequent pressure cycles that can cause defects to
grow, necessitated such frequent inspection. Adding requirements for similarly frequent
inspection of natural gas pipelines would complicate the existing testing capacity issue and likely
make it difficult for any of the testing requirements to be met.
Existing regulations already provide some additional protection from accidents on gas
transmission pipelines that could affect high consequence areas. The requirements of 49 CFR
192.61 1 specify that pipelines in class 3 or 4 areas must operate at pressures that produce
significantly lower hoop stresses in the pipe than is allowed in more rural areas. As a practical
matter, operators meet this requirement by reducing operating pressure or using heavier-walled
pipe in class 3 and 4 areas. Hazardous liquid pipelines do not afford similar protection in high
consequence areas. The additional protection already provided by natural gas transmission
pipelines justifies assessment on a more extended interval than for hazardous liquid pipelines.
Additionally, the natural gas pipeline network supplies gas for use in real time. This is riot the
case for hazardous liquid pipelines, which move product in batches and have significant storage
capacity. Assessment of natural gas pipelines can therefore result in interruptions of gas supply.
This can have a safety impact, iii addition to its economic effect, due to the need to restart gas
servicc in a controlled manner so as to avoid explosions at the point of service. The likelihood of
service interruptions, with attendant costs and safety concerns, increases as the assessment
interval is shortened, since operators have less flexibility to conduct assessments at times when
demand is lower.
7

<<<PAGE 9>>>

Finally, significant environmental damage is not expected to result from failure of a natural gas
pipeline, unlike hazardous liquid pipelines, since gas is lighter than air and dissipates in the
atmosphere.
The PSIA-2002 requires reassessments on no greater than ’7-year intervals. The OPS has
established requirements in this rule that would provide for a more focused assessment on this
shorter interval, to reduce the likelihood of supply interruptions. The “no rule” option, which
would not allow for this alternative method, would be similar to this alternative in that it would
require assessments using in-line inspection, pressure testing, or direct assessment at no more than
seven year intervals. As described above and in the appendix, RSPNOPS has evaluated the costs
of that option. Costs would increase significantly without addition of commensurate benefits.
For these reasons, RSPNOPS concluded that assessment of natural gas pipelines need not be
required as frequently as for hazardous liquid pipelines.
BASELINE REGULATORY ENVIRONMENT
In order to assess the costs and benefits of the new regulation, it is necessary first to ascertain the
current level of activity in areas addressed by the rule. As described above, legislation recently
enacted will impose a change in this level of activity, requiring the implementation of integrity
management plans and conduct of integrity assessments that have not previously been performed.
Still, it is necessary to determine the level of activity that has been occurring. The costs, and
benefits, of implementing either this rule, or the requirements of PSIA-2002 without a rule, must
be measured against this historical background. In this instance, it is necessary to determine the
rate at which pipeline inspections are being performed, and the prevalence and nature of integrity
management plans siniilar to those required by the nile.
The OPS has interacted with gas pipeline operators in recent years as part of development of an
integrity management standard by the American Society of Mechanical Engineers (ASME). The
standard includes many of the elements of this rule, and has been adopted as a consensus standard.
As a result of these interactions, RSPAIOPS understands that many gas pipeline operators
currently have, or are developing, integrity management programs including many aspects
required by this regulation.
These current integrity management programs include inspection of their pipelines by some
operators. The amount of such inspection is relatively low, however. Much of the testing being
conducted by these operators is the initial inspection of pipelines. The rate at which subsequent
inspections would be performed is now unknown. It is likely that some pipeline would be
identified for reinspection routinely (e.g., every ten years). It is equally likely that some pipeline
would not be reinspected at all.
Integrity management plans are a key element of this rule. To better understand and promote
8

<<<PAGE 10>>>

more comprehensive and integrated approaches to safety and environmental protection,
RSPNOPS created the Risk Management Demonstration Program, and the System Integrity
Inspection Pilot Program. These programs encourage and evaluate operator-developed safety and
environmental management processes that incorporate operator- and pipeline-specific information
and data to identify, assess, and address pipeline risks. These programs are helping RSPA’s
Office of Pipeline Safety refine its regulatory oversight processes. These processes help to ensure
that pipeline operators have effective processes in place to identify the most important risks to the
public and the environment, and to develop and implement cost-effective preventive and
mitigative actions to manage these risks. Many of these initiatives have validated the importance
of focusing resources and establishing higher levels of protection in areas where a pipeline failure
could have significant consequences.
Through the Risk Management Demonstration Program and the System Integrity Inspection Pilot
Program, RSPNOPS has improved its understanding of pipeline operator integrity management
systems and activities. This experience has shown that a number of pipeline operators have
formalized niaiiagement systems to identify and address the most significant integrity threats to
their pipeline systems. In the Risk Management Program, participants perform systematic and
comprehensive risk assessments to identify the specific nature and location of the most significant
risks posed by operation of their pipeline system. An essential feature of these risk assessments is
the integration of information from many diverse sources to fully understand the integrity threats
at specific locations on the pipeline. The impact on nearby population is explicitly considered in
these risk assessments. Through formal, risk-based decision making processes, these companies
use the risk assessment results to identify projects and activities that address potential system
integrity threats, thereby preventing leaks and accidents. These investigative risk management
programs, and the preventive and mitigative risk control activities that evolve from them,
supplement the minimum regulatory requirements established in 49 CFR 192.
The System Integrity Inspection Program is focused on developing a more integrity-based
approach to RSPA/OPS inspections. Instead of using a “checklist” approach, RSPNOPS is
focusing the inspection process on an operator’s integrity management processes and activities.
Through working with the operator, RSPNOPS is able to understand and influence the methods
and approaches used to assess pipeline integrity, and the approaches to integrating integrity
assessment data with other pipeline specific information, to identify the most significant integrity
threats to the system, Specifically, RSPNOPS has observed how operators examine internal
inspection data in conjunction with other surveillance and operating data, expected population
growth, land use, construction activity along the pipeline, and other infomation relevant to
assuring the integrity of the pipeline in high population areas and in environmentally sensitive
areas. Through this interaction RSPNOPS is acquiring a broader understanding and a greater
confidence that effective programs are in place to address the most significant risks. Similar to
the Risk Management Program, the SI1 Program is emphasizing how operators evaluate their
system condition and its risks, and use this information to make sound integrity management
decisions.
9

<<<PAGE 11>>>

The RSPNOPS experience in the Risk Management Demonstration Program and the System
Integrity Inspection Program indicates that integrity management programs such as that required
by this rule have been developed. They are far from universal, however.
CONSIDERATION OF PUBLIC COMMENTS
A number of comments were received in response to the proposed rule (68 FR 4278) and the
regulatory analysis supporting it (referred to herein as the draft regulatory analysis). Comments
from industry generally agreed that the earlier analysis had significantly underestimated the costs
of complying with the proposed rule. The Interstate Natural Gas Association of America
(INGAA) and the American Gas Association (AGA) made specific recommendations for changes
to the proposed rule. In each case, the associations provided estimates of the costs, and savings,
that would result from their changes.
RSPA/OPS acknowledges that the earlier regulatory analysis underestimated the costs of
complying with the proposed rule. There were two principal reasons for this understatement.
First, RSPA/OPS used outdated information for estimating the costs of performing modifications
on pipelines (e.g., to accomniodate in-line inspection devices) and to perform inspections. The
RSPA/OPS estimates were based on studies that were performed in the early 1990s. Costs had
been escalated to 2001 using the producer price index (i.e., to reflect inflation). Changes since
1990 in how this work must be performed, particularly costs associated with complying with
improved environmental standards, significantly outpaced inflation during this period.
RSPNOPS acknowledges this deficiency. For this analysis, RSPNOPS has adopted the unit
costs (i.e., costs per mile or costs per company) used by INGAA and AGA in their analyses, as
described herein for individual cost elements.
The unit costs used by INGAA and AGA in their cost estimates differ. AGA explains the reason
for this difference as the higher costs to do any kind of work, particularly work requiring
excavation, in the urban environment in which its members operate. RSPNOPS acknowledges
that costs are likely higher for urban work, and agrees that use of different unit costs for
companies in such areas is reasonable. RSPNOPS has restructured this analysis to estimate costs
separately for companies operating long-distance transmission pipelines in mostly rural areas
(similar to SNGAA members) and those operating transmission pipelines in urban areas (similar to
AGA members). Unit costs derived from INGAA comments have been used for the long-distance
estimates, and those froin AGA’s comments are used to estimate costs for companies in urban
environments. (RSPNOPS has also updated the estimated costs associated with the proposed
rule, using the new unit costs. These estimates are provided in the appendix, in order to illustrate
the effect on costs of changes made between the proposed rule and the final rule).
Second, RSPNOPS used a much lower estimate for the amount of “overtesting” that will occur
than used by INGAA in its analysis. Overtesting refers to pipeline not in high consequence areas
that must be tested in order to test segments of pipeline that are within those areas. This
10

<<<PAGE 12>>>

principally affects in-line inspection (Le., pigging). Inspection tools (Le., pigs) must be inserted
into the pipeline, run over the length of pipe to be inspected, and removed. Insertion and removal
must occur at locations where there are launchers and receivers, structures attached to the pipeline
which allow for insertion and removal of these large tools. RSPNOPS’s preliminary draft
regulatory analysis in support of the proposed rule had estimated the amount of overtesting as 25
percent (i.e., for every 10 high consequence area miles tested, 12.5 total miles would be tested).
The Technical Pipeline Safety Standards Committee recommended that this assumption be
increased when it reviewed the preliminary draft regulatory analysis. That analysis was changed
to assume 200 percent overtesting.
The comments submitted by INGAA and AGA used different estimates for overtesting. AGA
assumed 100 percent overtesting for pigging, and no overtesting for pressure testing or direct
assessment. This reflects that a significant portion of the transmission pipeline mileage of AGA
niernbers is likely to be in high consequence areas and that the distance between pig launchers and
receivers in urban areas is relatively short. INGAA did not report a percentage assumption for
overtesting. Instead, INGAA surveyed its members to obtain an estimate of the number of miles
that they believed would be classified as high consequence areas and the number of miles that
would have to be tested in order to pig those segments. The total number of miles that would be
inspected was reported to be 7.25 times the estimated length of the high consequence area
segments. RSPNOPS finds that this factor, while considerably higher than the 200 percent
overtesting assumed in the draA analysis, is reasonable. High consequence areas are likely to be
widely dispersed on long-distance transmission pipelines. The distance between pig launchers
and receivers on those pipelines is relatively long, on the order of 50 miles. The combination of
these factors makes it likely that a significant amount of overtesting will occur on these pipelines.
RSPA/OPS has adopted, for purposes of this analysis, an assumption of 625 percent overtesting,
for pigging, consistent with the results of the INGAA survey. INGAA assumed 25 percent
overtesting for pressure testing, which is the same factor RSPNOPS uses in this analysis. There
is no overtesting required for assessments performed by direct assessment.
INGAA also commented that the draft regulatory analysis underestimated the costs associated
with data integration. The draft analysis had assumed that this would cost $1 00,000 in the first
year for each company operating more than 40 miles of transmission pipeline and $50,000
annually thereafter. (The corresponding numbers for operators with fewer transmission miles
were $25,000 and $12,500 respectively). INGAA agreed that more costs would be incurred in the
first year, when record systems must be realigned and older records, many in paper form, must be
converted for later analysis. INGAA estimated that the costs to perform this work would be
$1,359 per mile in the first year, and $1 13 per mile annually thereafter. RSPAIOPS agrees that
estimating these costs on a per-mile basis (as opposed to per-company) is more reasonable, since
the number of records that must be considered is proportional to the amount of pipeline an
operator has. RSPNOPS also accepts that the costs for retrieval and conversion of older, paper
records is likely to be high. RSPNOPS has adopted the JNGAA per-mile estimates for estimating
the cost of data integration.
11

<<<PAGE 13>>>

Commenters also addressed the benefits of the proposed rule. Carol Parker noted that the
Carlsbad accident had a significant economic impact on the state of California due to reductions
in gas delivery following the accident. Ms. Parker suggested that avoiding future economic
impacts of this type is a benefit reasonably attributable to this rule. RSPNOPS agrees.
RSPA/OPS has estimated the magnitude of the economic impact that the Carlsbad accident had
on California and describes that in this analysis among the benefits of the final rule. RSPA/OPS
notes, however, that information is not readily available to estimate the likelihood (i.e.,
probability) that another accident like Carlsbad, with similar economic consequences will occur.
RSPNOPS is thus not able to estimate with precision the amount of benefit attributable to this
rule in avoiding such economic consequences.
REVIEW BY TECHNICAL PIPELINE SAFETY STANDARDS COMMITTEE
The OPS presented a preliminary draft of this regulatory analysis to the Technical Pipeline Safety
Standards Committee (TPSSC) at a public meeting on July 31, 2003. TPSSC is a Federal
advisory committee charged with responsibility for advising on the technical feasibility,
reasonableness, cost-effectiveness, and practicability of gas pipeline safety standards. The
TPSSC, by law, serves as the peer reviewer for RSPNOPS regulatory analyses.
The TPSSC noted that the provisions of PSIA-2002 impose restrictions that make it difficult to
optimize the costs and benefits of the rule. In particular, the Act requires that pipeline segments
in high consequence areas be subjected to baseline assessments within 10 years and be reassessed
every seven years. This has two effects.
0 It results in an “overlap” period in the eighth, ninth, and tenth years after the law was
enacted, in which both baseline and reassessments will be performed. The increased level
of testing in these years increases costs and increases the likelihood that pipelines being
taken out of service for assessment will result in curtailment of gas supply
It requires pipelines to be inspected more frequently than is likely needed, particularly for
pipelines operating at low stress levels.
The TPSSC acknowledged that RSPNOPS had done as much as possible, within the restrictions
of the Act, to minimize the effect of these restrictions. The committee unanimously found that the
cost-benefit analysis supported going forward with the final rule.
SCOPE AND PARAMETERS OF ANALYSIS
This analysis of benefits and costs takes the following approach. First, the mileage impacted by
the regulatory change is identified and estimated. Mileage is estimated separately for long-
distance transmission pipeline operators (representative of INGAA members) and for local
distribution companies (LDC, representative of AGA members). Then the potential benefits of
the rule are discussed. In the next section the potential costs of the rule are examined. Costs are
estimated separately for long-distance operators and LDCs, due to the differences in unit costs for
12

<<<PAGE 14>>>

work done by each class of operator (as discussed above). Finally, a discussion of the costs versus
the benefits is presented. Tt should be noted that, unless otherwise specified, all dollar values in
this report are given in constant 2001
Furthermore, this analysis will arbitrarily consider
only the first twenty years after the effective date of the final rule. Including additional years
would not be expected to materially affect the conclusions of this analysis.
ANALYSIS
Impacted Mileage
In this section the total pipeline mileage impacted by the regulatory change is estimated. That
mileage is located in or nearby high consequence areas, defined by the change as areas in which
defined numbers of people or facilities housing people of limited mobility are within specified
distances of the pipeline. The distances vary depending on the diameter of the pipe and the
pressure at which it operates.
Total Pipeline Mileage
In total, there is an estimated 285 thousand miles of regulated onshore natural gas transmission
pipelines in the U.S.6 This rule would not apply to all of this mileage. The principal requirements
of the final rule apply to pipeline mileage in high consequence areas, which is estimated below.
The rule also applies to transmission pipelines for hydrogen, synthetic gas and other products
subject to 49 CFR Part 192 that are not included in the natural gas transmission pipeline totals.
RSPA/OPS does not have data on the total transmission mileage for these other gases. This
analysis uses the available natural gas transmission pipeline total mileage, which is considered to
be very close to the total pipeline mileage potentially affected by the regulation.
Impacted Mileage in High Consequence Areas
The major elements of the regulatory change apply to that transmission pipeline that is in high
consequence areas. As described earlier, the rule provides two options for an operator to
determine whether a segment of pipeline is in a high consequence area. Under option a, all
pipeline in class 3 and 4 areas, as defined in 49 CFR 192.5, would be included, as well as
additional pipeline having an identified site within a potential impact circle. Under option b,
operators would determine what pipe is in high consequence areas by evaluating potential impact
circles along the entire pipeline.
5
Dollars are converted fiom nominal values to real 2001 values using the Producer Price Index (PPI), Intemiediate
Materials, Supplies, and Components. The source of the PPI index numbers is the U.S. Bureau of Statistics Web
page.
'Jurisdictional natural gas transmission pipeline mileage (onshore) for 200 1. This mileage was obtained from annual
reports filed by pipeline operators with the Office of Pipeline Safety. Data available on the OPS web page.
13

<<<PAGE 15>>>

LDC High Conseguevice Area mileage
Pipeline operators are presently required to maintain data on the population near their pipeline in
order to determine pipeline that is in class 3 or class 4 areas. That mileage is not estimated here.
This option was included in the rule principally for smaller distribution operators with a limited
amount of transmission pipeline mileage. Many of these operators have historically designed and
operated their entire systems as if they were class 3 or class 4 rather than collecting and analyzing
population data near their pipelines to determine the class location. This option would let them
take the same approach to determining high consequence areas, i.e., treat the entire length of their
transmission pipelines as if they were in high consequence areas. RSPNOPS does not expect that
many operators will use this option.
Much of the transmission pipeline operated by LDCs is low-pressure pipeline. Much is also small
diameter pipeline. Operating pressure and pipe diameter are factors used to define the potential
impact radius. For small-diameter, low-pressure pipelines, the radius will be small. For example,
the potential impact radius for a 6-inch diameter pipeline operating at 300 psi is 72 feet. As a
practical matter, it is very unlikely that 20 buildings intended for human occupancy or an
identified site will be located within a 72-ft radius circle. RSPNOPS expects that most LDC
operators will recognize that using method b, Le., defining high consequence areas on the basis of
evaluating potential impact circles, will result in little or none of their pipeline being determined
to be in high consequence areas. This will minimize the costs to those operators of implementing
this rule. In this analysis, RSPNOPS assumes that all operators will use method b.
One provision of this rille would apply to low-pressure pipeline in class 3 and 4 areas that is
outside of high consequence areas. RSPNOPS relied upon comments by AGA and the American
Public Gas Association (APGA) to estimate this mileage. AGNAPGA comments indicated that
their members operate approximately 16,000 miles of pipeline in class 3 and 4 areas.7 RSPNOPS
has assumed that all of this pipeline operates at low stress (Le., less than 30% SMYS).
RSPNOPS has increased this number by 1000 miles to account for customer owned service lines
and operators not members of AGA or APGA. A total of 17,000 miles of low-pressure pipeline is
estimated to be in class 3 or 4 locations for purposes of this analysis.
The amount of transmission pipeline mileage in high Consequence areas has also been estimated
based on comments from the trade associations. AGA estimated that 2 1,800 miles of member
pipeline (AGA stated that its estimates included pipelines of APGA members) meet the “general
concept” of high consequence area.* This was based on the earlier definition of high consequence
area, which included all class 3 and 4 locations. RSPNOPS adjusted this estimate to account for
the reduced pipeline mileage that will be identified as in high consequence areas using method b.
As a first step in this ad-justment, RSPA apportioned the AGA total estimate to pipeline operating
7
Lori Traweek, ACA, letter to docket dated April 8, 2003, RSPA-2000-7666-203, page 3.
‘Lon Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-294, page 1 .
14

<<<PAGE 16>>>

in different pressure ranges. AGA estimated that 45 percent of their member pipeline in high
consequence area operates below 30% SMYS.’ AGA also estimated that 19 percent of its
members’ pipeline operates above 50% SMYS.” This implies that 36% operates between 30 and
50% SMYS. Applying these percentages, AGA’s 21,800 mile estimate was apportioned to these
operating pressure ranges. RSPNOPS then reduced the number of miles in each range to reflect
the likelihood that pipeline in class 3 and 4 locations, operating at those pressures, would not be
determined to be in a high consequence area using method b. For pipeline operating at >50%
SMYS, little reduction was assumed, since potential impact circles for that pipeline will be
relatively large. For pipeline operating below 30% SMYS, a significant reduction was assumed,
since potential impact circles there will be quite small, as described above. The resultant estimate
of LDC pipeline transmission mileage in each pressure range is presented in Exhibit 1.
Pressure Range Apportioned AGA
Estimate
Estimated HCA
Miles
>50% SMYS 4,142
4,000
30 to 50% SMYS 7,848
4,000
<30% SMYS 9,810
2,000
Total 21,800
10,000
Long-distance Pipeline High Consequence Area mileage
RSPNOPS also relied upon industry comments to estimate the amount of high consequence
mileage for long-distance pipelines.
Method b for identifying high consequence areas was largely based on a proposal submitted by
INGAA in response to the proposed rule. TNGAA conducted a survey of its members, asking
them to apply the new recommended method and determine the amount of pipeline mileage that
would be classified as high consequence areas if it were used. INGAA reported, in a set of
spreadsheets submitted to the docket,” that members operating 166,000 miles of pipeline had
estimated that 8,496 miles would be classified as high consequence areas on the basis of the
housing density portion of method b. Extrapolating this estimate to the entire 225,000 miles of
long-distance pipelines results in an estimated 1 1,5 16 miles of high consequence area.
INGAA’s survey addressed only the housing density portion of method b. This method would
2
‘Ibid., page 2
‘“Lon Traweek, AGA, letter to docket dated April 8, 2003, RSPA-2000-7666-274, Attachment B, page 1 of
‘INGAA conunents to docket, April 30, 2003, RSPA-2000-7666-297.
15

<<<PAGE 17>>>

also iiiclude areas where an “identified site”, consisting of a building housing a population of
limited mobility or a place where people gather (meeting specific criteria), is within a potential
impact circle. Pipeline operators can not now determine how much pipeline will be classified as
high consequence areas based on the presence of an identified site, because they have not
historically collected information on facilities within the identified site definition. (An exception
is places where people gather that are within 300 feet of the pipeline, since that is part of the
definition of class 3). RSPNOPS increased the estimated high consequence area mileage by 30
percent to account for miles that will be added due to identified sites. (The 30 percent factor is the
same multiplier used for this purpose in the draft regulatory analysis).
The estimated total amount of long distance pipeline in high consequence areas is thus estimated
to be 14,970 miles. Most long-distance pipeline operates at high pressures. For purposes of this
analysis, RSPNOPS assumes that all of this mileage operates at 250% SMYS.
Intrastate Gas Transmission Pipeliiie Mileage in Texas
The high consequence area mileage associated with intrastate pipelines in Texas must be
subtracted from these totals. This is because Texas pipeline is subject to a state rule that already
requires i~ispection and assessment. No additional testing costs will be incurred as a result of this
rule. (Programmatic requirements imposed by this rule will have an impact on Texas intrastate
operators, but these costs are estimated mostly on a per-company, as opposed to a per-mile, basis).
RSPNOPS estimated for purposes of the draft regulatory analysis that there are 5,432 miles of
intrastate gas transmission pipeline in Texas.’* For this analysis, RSPNOPS reduced that
estimate to 3,500 miles, proportionate to the reduction in the estimated amount of total high
consequence area mileage as a result of changes in the final rule. RSPNOPS further apportioned
this estimate between long-distance pipeline (2,500 miles) and LDC-type pipeline (1,000 miles)
on the basis of a rough estimate of the proportion of Texas mileage in each category. RSPNOPS
further assumed that the 1000 LDC miles are distributed among the operating pressure ranges in
the same proportions as used for LDC operators in general. The resultant estimate of pipeline
transmission mileage in high consequence areas is thus as shown in Exhibit 2.
I2Draft Final Regulatory Evaluation, Pipeline Integrity Management in High Consequence Areas,
(Gas Transmission Pipelines), RSPA-2000-7666- 166, page 12.
16

<<<PAGE 18>>>

Pressure Range
>50% SMYS
30 to 50% SMYS
<30% SMYS
Total
LDC HCA Miles Long-distance HCA Miles
3,600 12,470
3,600 0
1,800 0
9,000 12,470
BENE FITS
The benefits resulting from the final rule are discussed in this section. Those benefits are
expected to result from detection of problems that could cause pipeline failures before the failure
occurs, thereby averting accidents. The inspection and assessment required by the rule is designed
to detect problems related to internal corrosion, external corrosion, stress corrosion cracking and
external damage to the pipeline, all of which can result in pipeline ruptures. Natural gas pipeline
accidents usually involve explosions and fire and can result in death, serious injury, and property
damage. Preventing accidents will result in reduced numbers of deaths and serious injuries and in
reduced property damage. These reductions, then, are principal benefits of the nile. The rule will
also reduce costs to industry (compared with implementing the provisions of PSIA-2002 without a
rule), provide improved assurance of pipeline safety, provide a basis for increased public
acceptance of the risks from natural gas transmission pipelines, and will provide other, less
tangible, benefits. Each of these categories of benefits is discussed below.
Pipeline operators also have strong incentives to ensure the integrity of their pipelines. In addition
to the positive safety and societal benefits, the lost product and unscheduled downtime for repairs
following a major incident can significantly impact the company’s financial performance and its
ability to satisfy customer commitments. Operators cannot afford to have these critical
transportation assets out of service for lengthy periods of time in today’s coiiipetitive business
environment. In addition, the damage to the company’s public image and reputation, as well as
the legal implications of serious incidents, can pose an even broader and longer term negative
impact on the company’s business operations. For these and other reasons, many pipeline
operators have implemented and are continuing to improve more systematic safety and
environmental management processes, many of which already embody many of the principles in
this rule.
17

<<<PAGE 19>>>

Benefits from reduced death and serious in-i~ry'~
Accident reports submitted to the OPS during the period 1986 to 2002 (this period was chosen
because this data is publicly available on the OPS website) identify that there were 1,371 incidents
on natural gas transmission pipelines, resulting in 59 fatalities and 224 serious injuries. The
consequences of future pipeline accidents could differ, and are likely to be more severe, as
discussed below. Nevertheless, it is reasonable to use this 17-year record as an estimate of
consequences that would be likely to occur without changes in the manner in which pipeline
safety is assured. (Although the accident data base is I 7 years and costs are calculated in this
analysis for 20 years, this is not a problem as the accident data is used to estimate an average
benefit value per year).
The rule is expected to reduce the consequences of future accidents, through identification and
remediation of the kinds of anomalies that can cause pipeline accidents before those accidents
occur. Accidents that will be prevented by the rule should include a high percentage of those that
result in death and serious injury, since the rule is focused on pipelines in areas which have the
largest concentrations of people in the vicinity of the pipeline.
This rule will not eliminate all pipeline accidents. It is not possible to estimate precisely how
effective it will be in reducing such accidents. The theoretical maximum benefit that could be
achieved would be elimination of accidents causing death and serious injury. Based on this
historical record, the maximum value that could be realized from reducing deaths and serious
injuries is thus $289 million over 17 years or $17 million per year.I4
Benefits from reduced property damage
The same accident data base indicates that $328,3 13,111 in property damage occurred as a result
of those 1,371 pipeline incidents. A recent study indicates that this total may be low due to under-
reporting of accident ~ o s t s . ' ~ , ' ~
13
With respect to deaths and serious injuries, the following assumptions are made:
A life is valued at $3 million
A serious injury is valued at $500 thousand
These valuations are standard assumptions currently used in Office of Pipeline Safety and DOT benefitlcost
analyses.
"The accident data used here is national data. Since intrastate transmission pipeline in Texas has been
excluded from this analysis, the contribution of any accidents on that pipeline should also be excluded. This has not
been done. RSPA/OPS did riot examine the specific accident reports that lie behind the tabulated accident
infomiation on its web site for the period 1986 to 2002, and does not know whether any intrastate Texas pipeline is
represented in that data. None of the major accidents in this period occurred on that pipeline. The OPS expects that
the effect of excluding accidents on intrastate Texas pipelines from the computation of benefits in this analysis would
be small, likely well within the errors associated with the simplifying assumptions used to make the analysis possible.
IS"
Report on the ACCLN~CY of Cost Data from Incident Reports", General Physics Corporation, December
2001, unpublished.
"RSPAIOPS has not attempted to exclude any property damage occurring during this period on Texas
intrastate natural gas transmission pipelines for the same reasons described above for deaths and serious injuries.
18

<<<PAGE 20>>>

The study compared accident costs reported to RSPNOPS with other information, including press
reports and costs reported in operators’ post-accident financial filings. The study considered 49
accidents, of which only four were natural gas pipeline accidents. (Two of these accidents had not
been reported to RSPNOPS). The study found that actual costs for accidents involving hazardous
liquid pipelines were three times the amount reported to RSPNOPS. For the limited set of gas
pipeline accidents considered, costs were under-reported by a factor of 1.62. RSPA/OPS believes
that a larger study of gas pipeline accidents might show more under-reporting of costs, similar to
the situation revealed for hazardous liquid pipelines. For purposes of this analysis, RSPNOPS
assunies that costs may have been under-reported for natural gas pipeline accidents by up to a
factor of 2. Thus, the true value of property damage experienced in natural gas transmission
pipeline incidents over the last 17 years is in the range of $328 to approximately $656 million.
This range is used in this analysis as representative of the property damages caused by historical
natural gas pipeline accidents. As before, the historical record provides a reasonable estimate of
the consequences of potential future accidents. Again, the rule is expected to reduce the number
of accidents, and thus the amount of property damage that occurs. The extent of such reduction
cannot be estimated. The maximum benefit that could be achieved if the historical damage is at
the upper end of this range and property damage consequences were eliminated by
implementation of the rule is $656 million over 17 years, or $38.6 million per year.
Consequences of Pipeline Accidents are Likelv to Increase
Urban areas are rapidly expanding in the United States. Housing starts have increased 57% over
the last ten-year period. Increasingly, this brings additional population into the proximity of the
natural gas transmission pipelines that serve our urban areas. Rural areas that pipelines may have
passed through ten years ago are more likely today to be populated, and that likelihood will further
increase over time. Natural gas pipeline accidents that occur in rural areas have limited
consequences, particularly in causing deaths and serious injuries. Accidents in urban areas can be
much more severe.
The March 23, 1994, accident in Edison Township, New Jersey is a case in point. This area was
already urbanized at the time of the accident, but the accident demonstrates the potential for major
consequences. Rupture of a 36-inch diameter natural gas transmission line resulted in an
explosion and fire that destroyed six apartment buildings. Property damage exceeded $25 million.
Approximately 1,500 residents were evacuated from the apartments. Immediate evacuation
prevented any deaths, although one resident living approximately one mile from the scene of the
accident suffered a fatal heart attack.” Had circumstances been only a little different, significant
loss of life could have occurred.
Increased development makes it likely that the actual consequences of natural gas pipeline
“National Trailsportation Safety Board, Pipeline Accident Report Texas Eartern Trmsinmion
Corporation NatimiI Gas Pipeline ExploJion arid Fire Edisoiz, New Jer~ey March 23, 1994, January 18, 1995, p v
19

<<<PAGE 21>>>

accidents over the next 17 years, assuming no changes in the regulatory environment, would be
more severe than suggested by the historical record. RSPNOPS has not estimated by how much
those consequences might increase, because such an estimate would be highly speculative.
Nevertheless, the trend indicates that use of the historical record to estimate the likely
consequences of ftiture accidents is almost certainly conservative.
Total Benefits from Averted Deaths, Serious Injuries. and Property Damage
The maximum total benefit represented by the historical record is approximately $55.6 million per
year, the siini of the benefits for deaths and serious injuries and for property daniage as described
above. RSPNOPS believes that the rule will have significant effect in reducing the occurrence of
the kinds of accidents that resulted in these consequences. Given the magnitude of the potential
benefit represented by the historical record and the likelihood that consequences of future
accidents would increase, RSPNOPS concludes that the benefit of the rule in eliminating deaths,
serious injuries, and property damage is on the order of $40 million per year. Over the 20 years
considered in this analysis, the total benefit is thus $800 million.
Consequential Impact of Natural Gas Pipeline Accidents
The accident impacts described above are direct effects, i.e., they are caused directly by the
pipeline rupture and resulting explosion and fire. The consequences of natural gas transmission
pipeline accidents often do not stop there. Other impacts include disruption of business activities
in the immediate area of the accident and possibly in areas near the accident.
Many communities are served by natural gas distribution companies that receive their product via
single lateral pipelines from a natural gas transmission pipeline (so-called “sole-source laterals”).
If an accident occurs on the transmission pipeline that results in interruption of the flow of natural
gas, service to customers in communities served by sole-source laterals may be cut off. The
interruption niay be temporary, if gas supply can be restored by valving out the damaged section
of pipe and re-establishing supply from undamaged portions of the line. Even so, there is both an
economic and a safety consequence to such service interruptions.
When natural gas service is cut off, pilot valves on gas appliances go out. Service cannot simply
be restored, since gas would enter homes and businesses through the open pilot valves, potentially
build to explosive concentrations, and result in fires, explosions and additional collateral damage.
For this reason, restoration of natural gas service requires that local distribution companies follow
labor-intensive procedures. Representatives of the distribution company must enter each business
or residence to which service was intemrpted. They must close valves to pilot lights. Distribution
mains and laterals must be purged to eliminate air that may have become entrained. Only then
can service be restored.
Restoration of service again requires that an employee of the distribution operator must enter the
premises, reopen pilot light valves, and re-light the pilot lights. This process can take several
days. A recent service outage involved loss of natural gas service to approximately 4500
20

<<<PAGE 22>>>

customers. Service was restored in 48 hours, but only by the efforts of 400 personnel, many
supplied by other local distribution companies to assist in the emergency recovery effort.
Economic consequences included business interruption for the period of the outage, overtime for
local operator personnel, and the need for the local operator to house and feed personnel loaned
from other operators to assist. For purposes of illustration, if we estimate the labor costs of those
400 personnel at $75 per hour and they worked 24 hours (2 twelve hour days) the labor cost alone
would be $360,000. Additional costs would include transportation, leased emergency equipment,
lost revenue from the customers who were not served. It is easy to see how the cost of such an
accident on a small line with only 4500 customers could easily approach $1-2 million.
There is a potential that the impact of consequential damages from service interruptions could
grow. Natural gas is currently being used to power many new electrical generating facilities. As
more of the nation’s electricity is generated from natural gas, the supply of electricity will also
become more dependent on reliable, continuous availability of natural gas. It is possible that
future accidents on major interstate natural gas transmission pipelines in certain areas could result
in loss of natural gas supply to multiple electrical generating stations. Electricity generators
typically have a supply margin to account for the unexpected loss of a generating facility. If too
many generators are lost simultaneously, however, the margin can be overwhelmed and electrical
blackouts, with their attendant consequences, could result.
Reducins Costs of Assuring Pipeline Integrity
As described above, this rule does not impose requirements to assure pipeline integrity where
otherwise no requirements would exist. The Pipeline Safety Improvement Act of 2002 (PSIA-
2002), enacted into law on December 17, 2002, requires that pipeline operators implement
integrity management programs and perform integrity assessments on their pipelines. PSIA-2002
requires that operators use one of three methods to perform assessments, in-line inspection,
pressure testing, or direct assessment. The Act requires that operators begin baseline assessments
within 18 months (i.e., by June 17, 2004), and that they complete a baseline assessment of all of
their pipeline segments that can affect high consequence areas within 10 years (i.e., by December
17, 2002). The Act further requires that assessments be repeated on these segments at intervals no
less frequent than once every seven years.
The Act applies to pipelines that have been determined to be in high consequence areas pursuant
to criteria defined in 49 CFR Part I92 pursuant to earlier legislative mandate. PSIA-2002
explicitly allows, however, for subsequent modification of these criteria.I8 This final rule makes
such modifications. The changes made in this rule refine the criteria to permit a better focus on
those portions of the pipeline system where accidents can truly result in high consequences. As a
result of these refinements, the number of pipeline miles determined to be in high consequence
areas will be significantly less than it would otherwise be if this rule were not adopted.
’8Pipeline Safety Improvement Act of 2002, Section 14, “Risk Analysis and Integrity Management
Programs for Gas Pipelines”
21

<<<PAGE 23>>>

RSPNOPS has estimated, above, that the total number of high consequence area miles of
transmission pipeline affected by this rule is 18,970 miles. RSPNOPS estimated the number of
high consequence area miles in the draft regulatory analysis supporting the proposed rule (i.e.,
before the refinements in this final rule were included) as 36,854 miles.I9 If this rule is not
adopted, pipeline operators would therefore be required to perform assessments on nearly twice as
much pipeline mileage as they will need to assess to comply with this rule.
PSIA-2002 also grants authority to the Secretary of Transportation to designate alternative
assessment methods that would provide an equal or greater level of safety. This rule designates
two alternative methods of assessment.
The first alternative assessment method, confirmatory direct assessment, was introduced in the
proposed rule. The final rule allows it to be used to perform assessments required to meet the
statutory seven-year periodicity. The rule allows inspections using the other, more expensive,
methods to be performed at intervals of ten, fifteen, or twenty years, depending on the operating
stress levels in the pipeline. RSPNOPS has determined that use of assessments using the
methods specified in PSiA-2002 at these longer intervals, combined with confirmatory direct
assessment at seven-year intervals, provides an equivalent level of safety as the provisions in the
statute.
The second alternative assessment method allowed by this rule is low-pressure assessment. This
is applicable to pipeline operating below 30% SMYS. It recognizes that the failure mode for pipe
at these lower pressures is almost always leakage, rather than rupture. For such pipeline,
increased leak surveys, more focused attention on the potential for internal corrosion, and
electrical surveys to assure protection against external corrosion are a more effective assessment
method. The rule allows this method to be used to meet the statutory seven year requirement.
Assessments using the more expensive methods are required at 20-year intervals.
if this nile is not adopted, operators would not be able to use these more appropriate, and less
expensive, assessment methods. Instead, they would be required to implement the more costly
methods specified in the statute at seven-year intervals. This would significantly increase the cost
for conducting required assessments.
RSPNOPS estimated the costs to operators of complying with the statute without the refinements
included in this final rule. This estimate is described in the appendix to this regulatory analysis.
The total implementation costs, over 20 years, were then compared to the costs for implementing
the final rule as estimated in this analysis. The costs for implementing the statute, without the
changes made by this rule, are estimated to be $6.2 billion higher than the costs for implementing
this rule.
"Draft Final Regulatory Evaluation, Pipeline Integrity Management in High Consequence Areas,
(Gas 'Transmission Pipelines), RSPA-2000-7666- 166, pagt: 12.
22

<<<PAGE 24>>>

This total is thus a benefit attributable to this rule. It is not speculative. It does not presume that
RSPNOPS mirht impose more costly requirements if this rule is not adopted. The more costly
requirements have already been imposed, by Act of Congress. The Act allowed flexibility for
RSPNOPS to refine its scope, which is accomplished in this rule. The savings of $6.2 billion,
over 20 years, are real.
Public Confidence
The most significant benefit of the final rule is less tangible. It will provide a basis for improved
public confidence in pipeline safety. Public confidence has been shaken as a result of several
recent accidents with significant consequences. These accidents were widely reported by national
media, becoming known well beyond the communities in which they occurred. These included
the 1994 pipeline rupture, explosion, and fire at Edison Township, NJ (discussed above), a June
10, 1999, rupture of a hazardous liquid pipeline in Bellingham, WA, with subsequent fire, and an
August 19,2000, natural gas pipeline rupture, explosion and fire near Carlsbad, NM. Three
pcrsons were killed in the Bellingham accident. Twelve persons were killed in the Carlsbad
accident. (Hazardous Liquid pipelines, such as the one involved in the Bellinghain accident,
would not be affected by this rule. They are covered by similar rules for hazardous liquid
pipelines, which have already become effective.)
Improving public confidence is, in itself, important. It will, however, also result in economic
benefits.
One way in which public concern regarding pipeline safety manifests itself is in increased public
opposition to new pipelines. Local governments can impose additional requirements and
restrictions that delay construction and result in significant additional costs. A recent example
involved the conversion of an existing hazardous liquid pipeline in Texas. Community reaction in
the city of Austin resulted in delays and significant additional costs. In response to the
community reaction, the operator replaced 12 miles of the existing pipeline with 21 miles that
looped to the south of the city, avoiding most populated areas. This significantly increased the
cost of the pipeline project. According to data published in the Oil and Gas Journal, the costs of
constructing pipeline have increased sigiiificantly over the last 15 years. The average cost of
constructing on-shore natural gas transmission pipelines between 1995 and 2000 was $1.12
million per mile, A similar re-route for a natural gas transmission pipeline thus would have cost
approximately $23.5 million.
Increased public opposition can also result in delays in implementing pipeline projects. In some
cases, the related costs associated with responding to public concerns, participation in public
hearings, and financing of major construction projects during delays can be as significant as, or
more than, the cost of installing new pipeline. In the extreme, increasing public concern could
make it impossible to site and construct new natural gas transmission pipelines.
The United States needs additional natural gas transmission pipeline capacity to ineet current and
future needs. The Energy Information Administration predicts that total demand for natural gas
23

<<<PAGE 25>>>

will increase approximately 1.8 percent per year from 2001 to 2025, rising from 22.7 to 34.9
trillion cubic feet annually.20 Demand growth in particular areas could greatly exceed this national
average. If operators are unable to construct new pipelines, the existing pipeline system would
rapidly reach its capacity limit, and the ability to meet this increased demand could be challenged.
New applications of natural gas as a fuel would need to be foregone. The ability to use natural gas
as an environnientally-preferable fuel for new electric generating capacity would be lost.
Curtailment of existing natural gas usage would likely be required. For all of these reasons, it is
vitally important that the public have confidence that the national network of natural gas
transmission pipelines is safe.
The final rule provides a foundation for an improvement in public confidence. It requires
operators to implement inspection and assessment programs directed at identifying the causes of
the major pipeline accidents summarized above, and other potential causes of pipeline accidents,
and correcting them before pipeline accidents can occur. The resulting increase in public
confidence of pipeline safety may well result in less opposition to new pipelines, faster permitting,
and less delay caused by local government efforts to require additional provisions or re-routing to
improve safety.
It is difficult to quantify the benefit that will result from increased public acceptance of natural gas
pipelines. Gas prices are relatively inelastic. Prices can rise significantly with even a minor
shortfall in ability to meet demand. The impact on the U.S. economy if natural gas demand
cannot be met could be significant.
Avoiding an Accident with Very High Consequences
As noted above, the population near gas transmission pipelines is increasing in many areas. This
increases the potential for an accident with consequences greater than any that has yet been
experienced.
The potential impact circle (i.e., the area in which the effects of a rupture and explosion would be
felt immediately) for a large, high-pressure pipeline can be 1,000 feet or more in radius. A circle
of 1000 ft. radius encompasses 72 acres of land. If a housing density of 2 dwellings per acres is
assumed, 144 houses could be within the potential impact radius.21 If each dwelling is assumed to
house an average of 2.5 occupants, this puts 360 people potentially at risk from a rupture and
explosion on that pipeline.
2 0
Energy hifoilnation Administration, Annual Energy Outlook 2003, With Projections to 2025, January
2003, paqe 4.
'This ignores the fact that there would be a cleared right of way associated with such a pipeline, on which
no structures would be built. For purposes o f this analysis, RSPA/OPS has ignored the effect of this cleared area.
RSPA/OPS considers that any non-conservatism introduced by this assumption is offset by the use of 2 dwellings per
acre as the assumed housing density. Housing densities in urban areas can be considerably higher than this.
Approved zoning densities for townhouse communities can approach 10 dwellings per acre.
24

<<<PAGE 26>>>

The chances of an explosion in these areas is, to be sure, already small. Pipeline ruptures are
infrequent events, and relatively few areas in the pipeline network are subject to these population
densities. It is informative, however, to consider the possibilities.
Pipeline ruptures occur approximately 22 times per year. Over the 20 years considered in this
analysis, 440 ruptures would be expected to occur (without the integrity improvements embodied
in this rule). The likelihood that a rupture would occur in this period that would affect areas with
very high population densities can be estimated by multiplying the total number of ruptures
expected by the fraction of transmission pipeline where such high populations exist. If 0.1% of
the total U.S. transmission pipeline mileage (representing 285 miles of pipeline across the U.S.) is
assumed to include high population densities, then 0.44 ruptures would be expected to affect these
areas during this analysis period.
An explosion in a high density population area would be expected to cause significant casualties.
It is not possible to estimate with certainty how many of the 360 residents potentially involved in
such an explosion would be killed and how many would be seriously injured. It is likely that few,
if any, would escape without injuries. For purposes of this analysis, RSPNOPS assumes that one-
half of the residents at risk would be killed and that the other half would be seriously injured.
Using the standard DOT values for attributing value to deaths and injuries (described above) this
would be equivalent to an economic consequence of $630 million.
This value, of course, assumes that the accident occurs. It must be converted into an “expected”
cost by multiplying times the expectation that the accident will occur. Using the expectation of
0.44 such ruptures during the analysis period leads to an estimated benefit from avoiding such a
high consequence accident of $277.2 million.
This rule contains provisions that will contribute to avoiding high consequence accidents and
realizing this benefit. Many of these provisions go beyond the requirements in PSIA-2002,
making the rule more effective in achieving this end. These provisions include:
Repair criteria specified in a very precise manner, going beyond any industry consensus
standards. Experience has demonstrated that aggressive repair criteria have had greater
impact than other safety actions. Many pipelines that had accidents in the 1990s had
been tested, but operators, by themselves, were not making best use of the available data.
A requirement for a threat-by-threat evaluation of the pipeline to focus on those threats of
significance.
A requirement to apply lessons learned from assessing covered pipe segments to similar
pipeline not in high consequence areas. These provisions respond to recommendations of
the National Transportation Safety Board, and will significantly expand the impact of the
rule.
A requirement to gather, monitor and report measures of performance that will allow
operators, regulators and the public to observe the downward trends in the number of
significant defects in gas pipeline.
Preventive and mitigative measures that will significantly reduce the likelihood of
25

<<<PAGE 27>>>

accidents caused by time-independent events such as those caused by third-party damage.
These provisions will have particular benefit in areas where significant growth is
expected, with attendant excavations and potential for pipeline damage. This type of
accident would not be addressed by implementing the provisions of PSIA-2202 alone.
It is possible that an accident with even higher consequences could occur. This might result from
a large concentration of people, such as might be found in a stadium or office building, were in
proximity to a pipeline accident. The likelihood of such a very high consequence accident is even
lower. Places of assembly in which large numbers of people might gather are typically used much
less frequently than residences. In addition, the amount of transmission pipeline mileage on
which such places are potentially exposed is very small. Nevertheless, they could occur. The
actions prescribed by this rule will have a significant effect on reducing the likelihood even
further.
Preventive Maintenance vs. Accident Response
The final rule requires operators to implement programs that are intended to identify areas on their
pipelines needing remediation and repair and to accomplish the necessary remediation and repair
efforts. If not found and repaired, some of the anomalies could cause accidents, and thus require
repair (and recovery activities). The rule can thus be seen, in part, to be a substitution of
“preventive maintenance” (i .e., identify problems early and address them) for reactive response to
accidents.
The rule includes schedules by which required remediation actions must be taken, which vary
depending on the severity of the identified anomalies. Operators would be permitted to take
longer than these schedules if they provide additional margin of safety by reducing pressure or if
they notify RSPA/OPS of the circumstances requiring additional time (which will allow
RSPA/OPS to review those circumstances and oversee the operator’s actions). Remediation of
identified anomalies is thus more in the nature of preventive maintenance: operators can schedule
their efforts based on important factors such as availability of repair resources and when demand
on the pipeline is relatively reduced. If the line must be taken out of service for the repairs,
advanced preparations can avoid the need for service interruptions and their consequences (as
described above).
Not identifying and resolving these anomalies could cause some of them to result in accidents.
Then, operators have no flexibility. Repair resources must be made immediately available,
regardless of other demands. Overtime and use of “borrowed” crews from other pipeline
operators is almost always involved. In addition, the accident may cause additional damage to the
pipeline involved or to other pipelines on the same right-of-way. Damaged pipelines may be out
of service for extended periods (see below).
Informal discussions with natural gas transmission pipeline operators indicate that typical costs to
repair defects found by inspection range from about $20,000 to $60,000, depending on whether
service must be interrupted to effect the repair. The cost of unplanned recovery from a leak can
26

<<<PAGE 28>>>

be up to an order of magnitude higher. The cost of recovering from a major pipe failure can be
two or more orders of magnitude higher, i.e., in excess of $5 million,
Costs to the operator to repair the damage caused directly by the Carlsbad accident amounted to
approximately $1 million. Indirect damage caused by the accident resulted in approximately an
additional $4 million in costs. Repairs and modifications necessary to return the pipeline to
service cost an additional $3 million. Total costs directly attributable to the accident were thus on
the order of $8 million.
Edison and Carlsbad were both accidents that resulted in significant direct costs to the operator.
Recent experience thus indicates that such accidents occur about once each decade. This rule will
not prevent all accidents. Due to the significant amount of overtesting that is expected, however,
it can prevent many of them. (Overtesting is discussed below). RSPNOPS estimates that a total
of 7 1,780 miles of transmission pipeline will be assessed to comply with this rule. This represents
25 percent of the total transmission pipeline mileage. If we assume that accidents causing
significant direct costs would otherwise be equally likely at any location on the pipeline, this rule
will avoid 25 percent of them. If two such accidents are expected during the 20-year period of
this analysis, then this rule will result in avoiding 0.5 such accidents during the period, for a
benefit of $4 million.
Quicker Return to Service Following an Accident
Perhaps most important consequence of the Carlsbad accident was that the pipeline was out of
service for a total of 324 days. Even then, the line was returned to service, pursuant to
requirements imposed by RSPNOPS, at reduced pressure. Pressure was increased in steps as
additional inspections were perfornied and confidence was gained, but operation at full pre-
accident pressure did not resume for approximately an additional year.
The reason for this extensive period and cautious approach to return to service was that additional
work needed to be performed to ascertain the condition of portions of the pipeline not involved in
the accident. Since the accident occurred, the integrity of the entire line was put in question.
Additional information needed to be gathered to permit an evaluation of its integrity. Information
about the integrity of much of the pipeline will be more readily available in the future as a result
of the requirements of this rule.
As noted above, 25 percent of transmission pipeline mileage is expected to be assessed
periodically to comply with this nile. This will provide current information about that portion of
the pipeline mileage, which will be available to be used following any accident. The requirements
that operators identify and remediate anomalies found during assessments will also improve the
confidence that RSPNOPS will have in that portion of the pipeline. Finally, the data integration
requirements in this rule will make other information about the entire pipeline more readily
available, and the availability of this information will also make recovery from an accident easier.
The circumstances of each accident will differ. The amount of time that will be saved in returning
27

<<<PAGE 29>>>

pipelines to full service will vary as a result of those differences. RSPNOPS has not attempted to
quantify the benefit that would be associated with quicker post-accident return of pipelines.
Economic Consequences of Accident-Induced Supply Restrictions
The largest impact of an accident such as that which occurred at Carlsbad does not fall on the
pipeline operator. It is the result of restrictions in the supply of gas and increases in its price that
result from a major pipeline being out of service. The Carlsbad accident provides an informative
example.
Public comments received in response to the proposed rule pointed to the cost impact of the
Carlsbad accident on California as justification for this rule. The Carlsbad accident resulted in
curtailment of natural gas supply to California. The cost increases resulting from this curtailment
were only part of the broader costs associated with energy trading and other issues affecting the
2000 energy price problems in California. A FERC evaluation concluded, however, that evidence
“strongly implies that the Carlsbad rupture contributed significantly to extraordinarily high
California spot gas prices.’’22 The FERC study infers that the effect of the Carlsbad rupture was
an increase in gas prices of approximately $5 per thousand cubic feet. This amounts to
approximately $1 7.25 million per day for
As noted above, the pipeline was out of service for 324 days and operated at reduced pressure
when first returned to service. RSPNOPS cannot say, however, that the supply/demand
imbalance that resulted in the $5 price increase lasted for this entire period. There were other
pipelines delivering gas to California during the period, and the market likely adjusted to
accommodate the reduced supply from the out-of-service pipeline. If the reduction continued at
its initial magnitude for two months, however, the total effect would be slightly over $1 billion.
As described above, implementing the provisions of this rule are expected to significantly reduce
the likelihood of accidents resulting in this kind of supply effect on approximately 25 percent of
total transniission pipeline mileage. As also described above, accidents of this type would be
expected to occur about once each decade if this rule is not adopted. As a result, RSPNOPS
estimates that implementing this rule will result in an economic benefit, from avoided cost effects
of accident-induced supply restrictions, of approximately $1 billion during the 20-year period of
this analysis. FERC has stated to RSPNOPS that avoiding unexpected gas supply interruptions
of this nature would be a major benefit to the U.S. economy.
”Final Report on Price Manipulation in Western Markets: Fact-Finding Investigation of Potential
Manipulation of Electric and Natural Gas Piices”, Docket No PA02-2-000, Prepared by the Staff of the Federal
Energy Regulatory Commission, March 2003
21
Based on applying the estimated $5 per thousand cf to average daily deliveries fiom Arizona to California
during 2001. estimated in Energy Information Adrmnistration, Natural Gas Annual 200/, Table 12, to total 3,440
million cubic feet per day.
28

<<<PAGE 30>>>

Quantifying the avoided cost of potential accident-induced supply interruptions as a benefit
should be accompanied by estimation of the cost of supply interruptions that may occur as a result
of implementing the rule. These costs are not included in this analysis, for reasons described
below. There is a potential for such treatment to significantly increase the estimated costs. While
the exact number is under debate, a recent study by EEA under contract to INGAA has estimated
the cost to consumers associated with supply restrictions over the first twenty years following
implementation of the proposed rule would be $12.4 billion. Several assumptions have been
made in the EENTNGAA analysis that could cause the predicted cost to swing significantly up or
down, including:
6. 7.
8.
9.
That operators have perfect knowledge of each other’s assessment plans, so they can plan
an optimum assessment schedule. This assumption could clearly lead to an under-
prediction of consumer cost impacts.
That the mix of assessment techniques used by operators during the time when the
baseline assessments overlap the first reassessment will be the same as for the baseline.
This assumption ignores the fact that the rule would allow use of confirmatory direct
assessment (CDA) for reassessment or low-pressure reassessment of most lines during that
overlap period. These methods result in much less disruption of gas service. This
assumption will lead to significant over-prediction of consumer costs.
That the cost of all gas will follow the spot market price. In reality, much of the gas
supply is delivered under long-term agreements for which costs are more stable.
That there would be no regulatory means for operators to avoid supply interruptions.
Provisions in PSIA-2002 allow waivers from required reassessment schedules to mitigate
supply interactions, Those provisions are incorporated in this rule. This allows operators
added flexibility in avoiding supply interruptions.
RSPNOPS strongly believes that the waiver authority provided in PSIA-2002, and this rule,
represents a significant tool in our ability to help relieve supply impacts.
Consideration of Increases in Operating Pressure
Pipeline safety regulations presently limit pipeline operating pressures in order to limit stresses in
the pipe, thus providing a safety margin. The allowable pressure is based on the pressure at which
the pipe has been tested, which is, itself, determined by the ultimate strength of the pipe. In rural
areas, pipelines are allowed to operate at pressures that induce stresses in the pipe wall equal to 80
percent of those that have been demonstrated acceptable by pressure test. In class 3 and 4 areas,
which would be included among high consequence areas under the rule, the corresponding limits
are 66.7 and S5.S percent respectively. The corresponding hoop stress may not exceed 72 percent
of SMYS in class 2 locations, 60 percent of SMYS in class 3 locations, and SO percent of SMYS
in class 4 locations24. The reason for these lower limits has been to provide additional margin
2449 CFR 192.6 1 1, “Change in Class Location: Confirmation or Revision of Maximum Allowable
Operating Pressure”, paragraph (a)( 1)
29

<<<PAGE 31>>>

against accidents in areas where the population near the pipeline is higher. The margin is, in part,
to account for unknown problems and pipe degradation that could result in accidents.
This rule will require operators to inspect natural gas transmission piping in areas where the
largest concentrations of people exist near the pipeline. Anomalies that could threaten pipe
integrity will be identified and appropriate remedial actions will be taken. This will improve
knowledge of the condition o f the pipe and reduce the need for additional margin, in the form of
lower stresses in the pipe wall, to account for uncertainties regarding pipe condition.
Accordingly, this nile could provide a basis under which RSPNOPS could approve operation of
some natural gas transinission pipelines at higher pressures than are presently allowed. (The
particular circumstances of each area would need to be taken into account in deciding whether
operation at increased pressures is acceptable).
RSPA/OPS has some experience in granting such approvals. Operators who participated in the
Risk Management Demonstration Program (RMDP) implemented various activities to improve
their knowledge of the factors causing risk on their pipelines and to address those factors. Many
of the activities implemented were similar to elements required in integrity management programs
mandated by this rule. Some natural gas pipeline operators participating in RMDP were granted
authority to implement risk management alternatives in lieu of reducing pressure or replacing pipe
in areas where population growth had resulted in a change in class location. The effect was
operation of the pipe at a higher pressure than otherwise would be required by 49 CFR 192.61 1,
based on the improved knowledge of, and control over, risk in those areas. Mature integrity
management programs, addressing risks in high consequence areas could provide a basis for
authorizing operation at higher pressures in the same manner as did RMDP alternatives.
For a natural gas transmission pipeline, increased operating pressure results in additional
throughput, i.e., delivery of larger quantities o f gas without need to replace the pipe with one of
larger diameter. An increase in operating hoop stress from 72 to 80 percent SMYS, for example,
would result in at least 11 percent more gas throughput. The possibility of operating pipelines at
higher pressures thus affords operators the opportunity to increase natural gas deliveries from the
existing pipeline infrastructure.
On a long-term basis, pressure increases could obviate or delay the need for some new pipelines.
It would also increase the availability o f natural gas to meet all of the needs described earlier.
Informal discussions with pipeline operators have indicated that the increased gas deliveries that
would result from an increase in pressure associated with a ten percent increase in allowable pipe
wall stresses would more than offset the costs of complying with the requirements of this rule,
including the costs required to make a line piggable.
In emergency situations, like that experienced in California in 2000, temporary increases in
operating pressure could make additional gas available in rapid order to alleviate the emergency
situation. RSPNOPS has the authority to allow increases above the stress levels allowed by
current regulations via waivers. RSPNOPS would only exercise that authority if it had
confidence that the pipeline would operate safely at the higher pressures. The elements of
30

<<<PAGE 32>>>

integrity niariagenient programs required by this rule would go a long way towards engendering
that confidence. Integrity management programs that operators would implement to comply with
PSIA-2002, i.e., if there were no rule, would likely not produce the necessary confidence.
Provisions in this rule, not in the Act, that would contribute to the necessary confidence include:
1. 2.
3.
4.
The requirement that operators follow national consensus standards. Operators would
likely use these standards for guidance if they implemented programs without a rule, but
the degree of adherence to standard provisions would likely be less.
The requirement that lessons learned be applied, as appropriate, to the entire pipeline.
This will help assure that integrity problems do not occur in areas outside high
consequence areas. No such assurance would be likely in programs implemented without
this rule.
The requirement that performance measures be implemented, and that some of these
measures be reported to RSPNOPS. An increasing trend of pipeline performance will be
a significant element in assuring confidence in the pipeline.
That consistency and quality of operator integrity management plans, and their
implementation, can be known. This can only be assured through regulatory oversight,
and the nile provides the basis for such oversight.
RSPA/OPS is unable to quantify the benefit afforded by the ability to approve operation at
increased pressures. That benefit depends on the nature of future energy emergencies and on the
location and effect of potential shortfalls in gas supply. These are unknown at this time. When
emergencies occur, as seen in California in 2000, any ability to increase the supply of gas to an
affected area is a significant benefit.
Consideration of Alternatives to Pipe Replacement for Class Location Changes
As described above, existing regulations require that pipelines operate at lower pressures in areas
where the population along the pipeline is greater. As population near the pipeline grows, the
class location of a segment of pipe may change. Operators are required to perform a study
whenever populatioi~ increase indicates such a change may have occurred.25 If the study confirms
a change in class location, operators must reduce the pressure in the pipeline within 18 months2‘
A reduction in pressure would, however, mean lower throughput. Areas in which the population
is growing, i.e., where class location changes occur, are likely to need more, not less natural gas.
As a result, operators almost always replace pipe, using pipe with thicker walls, so that operation
can continue at the same pressures while reducing the stress in the pipe wall to comply with the
regulations.
INGAA conducted a survey in 1996 in which it asked members to report the costs they incur in
meeting class location change requirements. Operators representing 166,000 miles of
2549 CFR 192.609, “Change in Class Location: Required Study”
2”49 CFR 192.6 I 1, “Change in Class Location: Confirmation or Revision of Maximum Allowable
Operating Pressure”
31

<<<PAGE 33>>>

transmission pipeline responded. INGAA reports that the annual costs reported by these
operators, if rnultiplied by 20 years, would total $1.3 billion for pipe replacement and $149
million for pressure tests to justify higher operating pressures. Extrapolating these costs to all
225,000 miles of long-distance pipeline results in a 20-year estimate of expenditures totaling
$1.96 billion. Correcting for inflation provides an estimated expenditure of $2.02 billion over the
20 years considered in this analysis. LDC operators may also incur expenses related to class
location changes, but they are expected to be much lower, largely since many LDCs already
design and operate their pipeline systems as though all areas were class 3 or higher. For purposes
o f this analysis, LDC costs have been conservatively ignored.
RSPNOPS would not change the class location requirements to eliminate the need to replace
pipe, at least not initially. Rather, RSPNOPS would entertain requests for waivers from these
requirements. As described above, RSPNOPS has experience approving such waivers under the
Risk Management Demonstration Program, and this rule will provide information similar to that
relied upon for those waivers. That information would not be available until after a baseline
assessment had been performed on a given segment. The number of pipeline segments potentially
eligible for such waivers would therefore be small at first, but would increase over time until, after
10 years, all transmission pipeline segments in high consequence areas would potentially be
eligible. RSPNOPS is likely to be cautious in approving initial waivers. As confidence is
gained, and additional information is made available from future assessments, the number of
waivers approved is likely to increase.
It is not possible to estimate precisely how much pipeline mileage might benefit from waiver of
class location change requirements. It is possible, though, that relief could be granted by waiver
for up to half of all pipeline that would otherwise be subject to those requirements. The benefit to
industry, over the course of this analysis, thus could be as high as $1 billion. Experience gained
through review and approval of waivers would also establish a record that could be used at a later
time to modify or eliminate the class location change requirements. If this is done, future benefits
could be even greater.
Improvements in Pipeline Testing Technology -.
This rule will provide a spur to development of new and improved methods of pipeline inspection.
Internal inspection of natural gas pipelines has heretofore not been required. Some operators have
implemented voluntary testing programs. This rule, and its companion rules for hazardous liquid
pipelines, will significantly increase the demand for internal pipeline inspection services. This
dcinand will be long term and reliable, since the rules require periodic re-inspection. (Voluntary
prograins might not have resulted in re-inspection of pipelines or in re-inspection at much longer
intervals). In the short term, growth is expected among the companies providing inspection
services for natural gas transmission pipeline operators. In the longer term, increased competition
to provide these services can be expected.
The relatively improved economic position of inspection services companies will allow them to
invest in research to improve their inspection technology. Improved technologies might be able to
32

<<<PAGE 34>>>

detect anomalies that can not now be identified by internal inspection. Research might be able to
improve or develop new techniques to evaluate pipe using direct assessment. Improved methods
may allow inspections to be done more efficiently, at reduced cost to operators and with less
interruption to natural gas service. Inspection companies will have an incentive to develop these
improvements in order to improve their ability to obtain contracts from pipeline operators to
conduct inspections.
Society will benefit from improvements in inspection technology through the safer pipe that will
result from identifying and remediating anomalies that can not now be addressed.
Summary of Benefits
The benefits that will result from implementation of the requirements in this final rule are
summarized in Exhibit 3.
Exhibit 3. Summary of Expected Benefits
(in millions of dollars, over 20 years)
Benefit
Reduced death and serious injury and reduced property damage
Reduced costs for assuring pipeline integrity
Avoiding a very-high consequence accident
Reduced costs from preventive maintenance vs. accident response
Avoiding the economic impacts of supply-intempting accidents
Relief from class location requirements to replace pipe
Improved basis for public confidence in pipeline safety, e.g.
iniproved ability to site and construct new pipelines
Reduced consequential damages from unexpected interruption of
natural gas service
Quicker return to service following an accident
Facilitate consideration of increases in operating pressure
Foster iniprovements in pipeline testing technology
Total Estimated Benefits
Value
800
6,200
277
4
1,000
1,000
Not
Estimated
Not
Estimated
Not
Estimated
Not
Estimated
Not
Estimated
9,28 1
33

<<<PAGE 35>>>

COSTS
The final rule requires that operators, within one year of the effective date:
( I ) identify pipeline segments that are in high consequence areas,
(2) prepare a written plan for initial (or baseline) assessment of all pipeline that could affect a high
consequence area, and
(3) prepare a framework addressing each element of an integrity management plan for their
pipelines.
These documents will detail testing methods to be used, risk factors considered in selecting the
appropriate testing methods for each particular high consequence area, and the schedule of testing
and inspection. Appropriate testing methods include:
(1) pressure testing,
(2) internal inspection,
(3) direct assessm cnt,
(4) equivalent alternatives (in terms of knowledge of the pipeline provided), and
( 5 ) confirmatory direct assessment (for those segments for which regular assessments are
conducted on intervals greater than seven years).
Once the plans have been prepared they will be used for baseline integrity testing. That testing
must be conipleted within ten years of the effective date of the final rule. (Half of the testing must
be completed within the first half of the required period). RSPNOPS inspections will verify the
plans and assure they are implemented thoroughly.
The rule requires that pipeline operators retest their pipeline mileage in high consequence areas
periodically. Assessments of some type must be conducted no less frequently than once each seven
years. Full retests must be conducted at least once every ten, fifteen, or twenty years, depending on
the operating pressure of the pipeline. Pipeline operating above 50% SMYS must be tested every
10 years. Pipeline operating between 30 and 50% SMYS must be tested every fifteen years. Low-
pressure pipeline, ].e., that operating below 30% SMYS requires full retest every twenty ycars.
Full retests may be required more frequently, depending on risk factors, and operators must
consider the need for more frequent testing as part of their risk analysis and integrity management
program.
The risk from pipeline operating at low pressures is different. Failures on such pipelines occur as
leaks, rather than ruptures. The most important threat is usually outside force from third party
damage. In recognition of these differences, this rule establishes different requirements for the
seven-year reassessment of low pressure pipelines. Those requirements focus on assuring that
protective systems are functioning properly and include leak surveys. Additional protection is also
afforded by requiring additional preventive measures, to reduce the chances of third party damage.
34

<<<PAGE 36>>>

These protective measures apply to all low pressure pipeline in class 3 and class 4 areas, including
pipeline not in high consequence areas.
Pipeline operators must also evaluate their pipeline segments in high consequence areas to
determine whether installation of automatic shutoff valves or remotely controlled valves, or other
preventive and mitigative devices, is necessary to reduce risk. Operators would be required to
install such valves where they are found necessary.
Based on the foregoing requirements, the costs that can be expected to result from the regulatory
change will be those associated with the major provisions of this rule, which are:
1. Identifying pipeline segments that can affect high consequence areas
2. Framework - setting up integrity management program;
3. Baseline assessment - internal inspection, pressure testing, or direct assessment;
4. Periodic assessment (inspection) & evaluation;
5. Evaluating automatic shutoff and remotely controlled valves;
6. Data integration
7. Preventive Measures for low-stress pipeline in class 3 and class 4; and
8. Remedial action.
Number of Pipeline Operators Affected
RSPNOPS estimated, in the draft regulatory analysis supporting the proposed rule, that 668
operating companies would be affected by the proposed rule. This was based OII a review of
annual reports submitted to OPS for 2000. In excess of 1000 entities submitted reports.
RSPNOPS reduced this number by taking into account known ownership/subsidiary linkages
among the reporting entities. Upon further review, RSPNOPS has concluded that there are
additional linkages and the actual number of companies that will be affected by this rule is much
less than 668. RSPNOPS has taken a different approach to estimating the number of affected
companies in the final analysis.
INGAA’s web site lists 29 member companies. INGAA’s comments indicate that its members
operate approximately 180,000 miles of transmission pipeline, and that there are an additional
45,000 miles of such pipeline operated by companies that are not members. RSPNOPS based its
estimate of the number of long-distance pipeline companies that will be affected on the INGAA
membership total. RSPNOPS increased this total in recognition of the fact that there are long-
distance pipeline operators who are not members of INGAA. For purposes of this analysis,
RSPA/OPS estimates that there are 35 companies in the long-distance category.
AGA’s comments state that there are 166 gas distribution utilities that own and operate
transmission pipelines. This includes members of AGA and APGA and companies that are not
members of either association. RSPNOPS has relied upon this estimate in this analysis.
35

<<<PAGE 37>>>

There are other operators of gas transmission pipelines that are not utilities. This includes
intrastate transmission companies and customer-owned service lines. The limited amount of
pipeline mileagc operated by these companies makes their situation more like that of LDCs than of
long-distance operators, and they are included in that category in this analysis. RSPA/OPS’s
review of the 2001 annual reports identified approximately 75 companies that were either intrastate
transmission companies or operated customer-owned service lines.
RSPNOPS expects that some costs will be less for companies operating only a few miles of
transmission pipeline. In the draft regulatory analysis, we assumed that operators with less than 40
miles of pipeline would see lower costs. For this analysis, we have revised that threshold to 30
miles. RSPMOPS’s review of 2001 annual reports identified 89 companies operating less than 30
miles of transniission pipeline, and this number is used in this analysis.
Per-company costs for “LDC operators” are thus applied to 240 companies, 15 1 operating more
than 30 miles of transmission pipeline and 89 operating less than 30 miles. Costs for long-distance
operators are applied to 35 companies, all assumed to operate more than 30 miles of pipeline.
The Costs of Identifying Pipeline Segments in High Consequence Areas
Natural and other gas transmission pipeline operators are currently required to monitor the
population along their pipeline. The number of occupied dwellings in a sliding mile within 660
feet of the pipeline has been the basis for determining the “class” of the pipeline for many years.
“Method a” of the definition of high consequence areas for natural gas pipelines builds off this
existing knowledge, starting with the portions of the pipeline that are class 3 and class 4. This
information should already be known to the operators, and there is therefore no cost in identifying
class 3 and class 4 areas as a result of this rule.
(Some local distribution conipany - LDC - operators treat all of their piping as though it were class
3 or 4 rather than performing the population monitoring that would be required to determine the
specific class location of a particular segment of pipe. This approach will also be acceptable for
the final rule, although all requirements of the rule would then apply to all of the company’s
transniission piping. OPS presumes that all of the pipeline mileage of LDC operators following
this approach was included in the mileage totals submitted by AGA and APGA. Since this
analysis bases its estimate of the affected mileage on those comments, the entire transmission
mileage operated by LDCs taking this approach is included in this analysis).
High consequence areas for natural gas transmission pipelines, even under method a, involve more
than just class 3 and class 4, however. The additional factors include the presence of buildings
housing people with limited mobility and places where people congregate in proximity to the
pipeline. Some of these locations may exist outside current class 3/4 locations. Operators using
method a will need to conduct additional surveys of the areas near their pipeline to determine if
there are any such areas that require additional pipe to be classified as being able to affect a high
consequence area.
36

<<<PAGE 38>>>

“Method b” of the definition of high consequence areas requires the evaluation of potential impact
circles, representing the area that could be affected by a postulated explosion on the pipeline, over
the entire length of an operator’s pipeline. Calculation of the size of the potential impact circles
themselves is a straightforward exercise. The relevant parameters are maximum allowable
operating pressure and pipe diameter. These parameters change incrementally along the pipeline.
Once the size of the circles is known, the operator must evaluate its pipeline to determine whether
any circle contains more than 20 buildings intended for human occupancy or an identified site
(meeting criteria specified in the rule). This evaluation will be more resource intensive. Some
pipeline, e.g., that operating in undeveloped remote areas or that in very densely populated areas,
will be able to be dispositioned easily. Other pipeline mileage will require a detailed evaluation to
determine whether the circles contain the number of buildings, or an identified site, that would
constitute a high consequence area.
Existing regulations require that operators monitor the population within 660 feet of their pipelines
(to determine class location). Operators are therefore expected to have data to evaluate the housing
density component of method b for all but the largest transmission pipelines. (The potential impact
circle for a 30-inch diameter pipeline operating at 1000 psi is 655 feet). The rule allows operators
to use this data to evaluate potential impact circles larger than 660 feet, by prorating the housing
density criterion, for a period of three years. This will reduce costs for collecting the necessary
additional data for larger pipelines, allowing much to be gathered during the normal course of
business. All operators will need to gather data concerning identified sites, and this data must be
acc~imulated within one year.
RSPNOPS estimates that each affected operator will incur costs of $10,000 to calculate potential
impact circles. This element will thus total $2.75 million.
The costs to evaluate potential impact circles will almost all be incurred on those sections of the
pipeline that can not be disposed of easily (Le., areas that are remote or are highly developed).
AGA’s comments estimate that evaluating potential impact circles will cost $300 per
RSPNOPS considers that a per-mile estimate is appropriate, since that is how the pipeline will
need to be treated, and has adopted the AGA estimate. The question is how much pipeline will
require evaluation?
INGAA reported that approximately 6.4 percent of its members’ pipeline is in class 3 and 4 areas
(based on a survey to which members operating approximately 166,000 miles of transmission
pipeline responded). This indicates that much of the 225,000 miles of transmission pipeline in the
long-distance category is in rural areas. In many of those areas, only a cursory search for identified
sites will be needed, at most. For LDC operators, many potential impact circles will be so small
that they will not require detailed evaluation. For example, the potential impact circle for a 6-inch
pipeline operating at 150 psi is 50 feet in radius. Circles for smaller-diameter or lower-pressure
_ _ _ _ ~ ~ ~
*’Lon Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 8.
37

<<<PAGE 39>>>

piping will obviously be even smaller. Circles of this size will also be amenable to prompt
disposition on the basis of inability to contain 20 housing units.
RSPNOPS estimates that long-distance operators will need to evaluate potential impact circles
along 25,000 miles of pipeline, roughly 60% more than the number of HCA miles estimated by
INGAA (extrapolated for non-INGAA members and members not responding to the survey).
RSPNOPS estimates that LDC operators will need to evaluate potential impact circles for 16,000
miles, representing all of the pipeline in this group operating above 50% SMYS, a large portion of
that operating between 30 and 50% SMYS, and a small portion of that operating below 30%
SMYS.
The cost to evaluate potential impact circles is thus estimated to be $7.5 million for long-distance
operators and $4.8 million for LDCs. This makes the total cost for identifying high consequence
areas $15.05 million.
The Costs of Plans and Reports
The single most important part of this rule is the requirement for the integrity plan and framework.
The creation, development and implementation of these documents will provide for the necessary
integration of information regarding pipeline condition. Integration is important to assure
RSPA/OPS, and the public, that pipeline operators are considering fully the unique risks that gas
transmission pipelines pose to high consequence areas. Plan development will assure not only that
they are considering these risks but that they have developed a plan that requires extra scrutiny and
precautions in these areas to safeguard the public. These safeguards include the use of periodic
testing.
Evaluation is an ongoing process. Operators will be expected to consider the risk factors and their
relative priorities in establishing assessment schedules. This allows operators to develop an
internal inspection and testing program that is customized to the particular operating characteristics
and risks associated with different portions of their systern(s).
The plans and reports required by this rule are: (1) a written plan for baseline assessment of all
pipelines that could affect high consequence areas, (2) a framework addressing each elenient of an
integrity management program, and (3) other documents supporting the decisions made, analyses
made, and actions taken in the implementation of the integrity management program.
Cost of the Written Plan and Framework
Pipeline integrity management plans are relatively new. Such plans were required of hazardous
liquid pipeline operators through regulations promulgated in 2000 and 2001. The deadlines under
those rules for developing the plans have only recently passed. RSPNOPS has no data on the cost
to hazardous liquid pipeline operators for development of the required plans.
38

<<<PAGE 40>>>

For long-distance operators:
INGAA estimated that it would cost an operator $500,000 to develop an integrity management plan
and $50,000 per year thereafter to maintain the plan2’ The $500,000 estimate is higher than the
value used by OPS in the draft regulatory analysis. RSPNOPS interactions with hazardous liquid
pipeline operators who are developing integrity management plans in response to earlier rules
indicates that the amount of effort involved is considerable. RSPNOPS concludes that the
INGAA estimate appears reasonable. RSPNOPS estimated $1 6,000 per company for plan
maintenance in the draft regulatory analysis, included there as part of the reports category
(redesignated as recordkeeping in this analysis). RSPNOPS recognizes that $50,000 represents a
portion of one full-time professional, and considers this an appropriate estimate for long-term
oversight and management of the integrity management plan. RSPNOPS has used the INGAA
estimates in this analysis.
OPS assumed, in the draft regulatory analysis, that 25 percent of affected operators with more than
40 miles of pipeline already have developed integrity management plans that meet the
requirements of the rule. RSPNOPS has learned from its inspections of hazardous liquid pipeline
operators that few, if any, integrity management plans developed prior to the integrity management
rule did not require significant revision to meet the requirements of that rule. In this analysis,
RSPNOPS has not assumed that any operators already have plans meeting the rule requirements.
For LDC operators:
AGA estimated costs of approximately $1 million to develop plans and $57,000 per year for
maint~nance.~” RSPNOPS believes these estimates, particularly the development estimate, are too
high. (Some of these costs may be associated with data integration. See discussion below). Many
LDC operators will have limited amounts of affected pipeline mileage, particularly after
application of potential inipact circles. The elements of a plan will be the same as for long-
distance operators, but their treatment should be easier for smaller lengths of involved piping.
Some operators in this group will have only a few miles of pipeline. This would include, for
example, customer-owned supply lines of one or two miles in length. (These operators are
included in this group, because their characteristics are more like LDCs than like long-distance
operators). Plan development costs for these operators are expected to be considerably lower.
RSPNOPS uses the same estimates in this analysis as for long-distance operators (i.e., $500,000
for plan development and $50,000 annually for maintenance) for operators in the LDC group that
have more than 30 miles of pipeline. Lower costs are estimated for operators with less than 30
miles of pipeline - $1 25,000 miles for development and $25,000 annually for maintenance.
2x
INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297
29L0s1 Tsaweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, attachment A.
39

<<<PAGE 41>>>

Applying these values results in a total estimated cost to develop written plans and frameworks of
$104.125 million, all of which is assumed to be expended in the first year. (RSPNOPS recognizes
that plan development is likely to continue after preparation of the initial framework in the first
year, but extending these costs over several years would not change the estimated total in this
analysis). Annual maintenance costs are estimated at $1 1.525 million.
Recordkeeping
RSPA/OPS estimated in the draft regulatory analysis that recordkeeping associated with integrity
management plans, principally consisting of reports, would cost $4,000 per company per year.
INGAA's comments estimated a $50,000 per company initial setup charge and $5,000 per year
thereafter.30 RSPNOPS accepts that more management involvement and data system changes will
be needed in the first year, and that costs in that year will be higher. RSPNOPS has used the
INGAA estimates for long-distance operators and LDC operators with more than 30 miles of
pipeline. RSPNOPS believes that the setup costs will be less for operators with only a few miles
of pipeline. This analysis assumes a $20,000 per company setup charge for LDC operators with
less than 30 miles of pipeline. An annual charge of $5,000 is assumed for these companies, as for
those with more mileage, since it is unlikely that routine generation and review of reports will be
any less costly simply because the reports address fewer miles of pipeline.
The total cost for recordkeeping is thus estimated to be $1 1.08 million in the first year and $1.375
million each year thereafter.
Total Cost of Plans and Reports
Based on the foregoing, the total cost for plans and reports will consist of a one-time cost of
$1 15,205,000 plus an annual cost of $12,900,000.31
Inspection and Testing
The rule requires baseline and subsequent testing of the impacted mileage using in-line inspection,
pressure testing, direct assessment, or alternative methods. Acceptable in-line inspection includes
high resolution, low resolution, and ultrasonic pigging. Acceptable pressure testing consists of
hydrostatic testing. Acceptable techniques for direct assessment are as described in an industry
consensus standard. Acceptable alternative methods include any other methods that would provide
a level of safety equivalent to that provided by the specified methods. In addition, a more focused
application of direct assessment, confirmatory direct assessment, would be required for pipeline
segments that would be assessed using one of the other methods at intervals greater than seven
years.
''INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297
"This does not iiiclude cost incurred by the Federal government in setting up the review process
(including development of review protocols and training) and in the actual review of the plans and programs.
40

<<<PAGE 42>>>

Internal inspection (pigging) requires that an instrument (pig) be inserted into a pipeline, travel
through the line, and be removed. The points at which the pig is inserted and removed are referred
to as launchers and receivers. These are usually permanent installations, and are often located at
compressor stations. An jndividual pig inspection thus covers an amount of pipeline mileage
roughly equal to the spacing between compressor stations, which is typically about 50 miles for
long-distance pipelines.
Baseline Testing
The nile requires that baseline testing be completed within ten years. As noted above, at least
some gas transmission pipeline operators currently have integrity management programs that
include some testing. It is therefore likely that some of the affected mileage would be tested even
if the final rule were not promulgated.
The Interstate Natural Gas Association of America (INGAA) has estimated that 25 percent of the
natural gas transmission pipeline system has been pigged since inspection devices became
generally available in 1 980.32 This testing did not occur at a constant rate over that period. Rather,
pigging was conducted sparingly in the early 1980s and the amount of pipeline pigging being
performed has increased in recent years. For purposes of this analysis RSPNOPS assumes that the
current rate of pigging for natural gas transmission pipelines would inspect 25 percent of the
transmission piping in approximately 10 years, or 2.5 percent per year.
The definition of high consequence areas makes it unlikely that these areas will occur uniformly
throughout the natural gas transmission pipeline network. Rather, they would be expected to be
concentrated in areas with higher population, and to occur much less often in rural areas. This
means that it is possible that a pig inspection conducted in a rural area could inspect 50 miles of
pipeline and not inspect any pipe segment that could affect a high consequence area. It is likely
that some pigging being conducted today is in such rural areas. As a result, it would be
unreasonable to assunie that 2.5 percent of the pipeline that can affect high consequence areas
would be inspected each year if the final rule were not promulgated. For purposes of this analysis,
RSPA/OPS assumes that 1.5 percent of the pipeline in high consequence areas would be pigged
each year under current industry practices and that this rate of pigging would continue indefinitely
if the rule did not become effective.
Subsea uent Testing
Once baseline testing has been performed on a segment of pipe, the rule requires that subsequent
testing be undertaken on that segment. Some type of assessment, at a minimum consisting of
application of confirmatory direct assessment or low-pressure reassessment, must be conducted on
all affected pipe segments at least every seven years. Testing using one of the other accepted
32"Consumer Effects of the Anticipated Integrity Rule for High Consequence Areas," prepared for the
INGAA Foundation, Inc. by Energy and Environmental Analysis, Inc., 2002
41

<<<PAGE 43>>>

methods must be performed, based on risk factors, at least once every ten, fifteen, or twenty years,
depending on the operating stress level.
The planned rate of re-testing of pipeline by operators if this rule is not promulgated is unknown.
Some operators currently have programs under which pipe is tested periodically. It is also likely
that some pipe being tested for the first time might never be reinspected absent this rule.
RSPNOPS has estimated that testing would continue indefinitely at the present rate, i.e., 1.5
percent of mileage that can affect high consequence areas would be inspected by pigging annualIy.
RSPNOPS has assumed that no re-testing by hydrostatic tests or direct assessment would be
performed without the requirements of the rule.
Operators will need to do some subsequent testing at the same time they are doing baseline testing.
This results froin the combination of a ten-year baseline period and the requirement that some form
of reassessment be performed every seven years. Pipeline segments that are baseline tested in year
1 will require reassessment in year 8, while other baseline assessments may still be underway. This
“overlap” will occur in years 8, 9, and 10. The rule allows use of confirmatory direct assessment to
perform the reassessments required in those years. Confirmatory direct assessment results in the
least service interruption of any assessment method. Use of this method should help to minimize
gas supply problems that could occur when pipeline segments are taken out of service for
assessments.
The Costs of Testing
For the purposes of this analysis, it is assumed that all required testing will be accomplished by
either (1) hydrostatic testing (pressure testing), (2) smart pigging (internal inspection), (3) direct
assessment, or (4) confirmatory direct assessment (for interim retesting of those pipeline segments
tested using one of the other methods on intervals exceeding seven years). Alternative methods are
not yet to the point where their costs for pipeline testing can be reliably estimated.
Hydrostatic Testing
The total cost of hydrostatic testing has been previously estimated by RSPAIOPS to be $4,656 per
mile in 1990 dollars,33 which equates to $5,274 per mile in 2001 dollars. (This estimate, as well as
those for other testing methods, does not include the cost of any necessary repairs). This cost was
used in the draft regulatory analysis to estimate costs resulting from hydrotesting. Comments from
industry indicated that this value seriously underestimates the costs operators expect to incur to test
using this method.
”Office of Pipeline Safety, “49 CFR Part 195 Econormc Evaluation, NPRM - Hydrostatic Testing of
Certain Hazardous Liquid and Caibon Dioxide Pipelines,” Docket No PS-121, Notice 1, May 13, 1991
42

<<<PAGE 44>>>

INGAA estimated, in its comments, that the cost to hydrostatically test long-distance pipelines is
$29,700 per AGA reported an average cost of $40,000 per mile for this work in the more-
urban environments in which their members operate.35 RSPNOPS recognizes that changed
circumstances (e.g., new environmental requirements) could have increased hydrostatic testing
costs since the 1990 study. RSPNOPS has used the INGAA and AGA estimates in this analysis as
the costs for pressure testing of long-distance pipeline and LDC pipelines respectively.
Smart Pigging
The total cost of smart pigging has been previously estimated by RSPNOPS to be $2,839 per mile
in 1992 dollars,36 which equates to $3,210 per mile in 2001 dollars. This estimate does not include
the cost of making a pipeline piggable (i.e., adding pig launchers and receivers or modifying
pipeline that cannot pass instrumented pigs). Again, the industry trade association comments
indicated that these costs have been underestimated. INGAA estimated pigging costs to be $3,669
per mile.37 AGA estimated costs for this method at $9,600 per
As with pressure testing,
RSPNOPS acknowledges that costs to conduct this work may have increased since I992 at greater
than the lcvel of inflation. INGAA's estimate is not considerably higher than the inflation-adjusted
RSPNOPS estimate. The AGA estimate is higher, but not unreasonably so, recognizing the higher
costs to perfonn work in an urban environment and the normally shorter distance between
launchers and receivers in those areas (over which the fixed costs of conducting an inspection must
be distributed). RSPNOPS has again used the INGAA and AGA estimates as the costs for
performing pigging on long-distance pipeline and LDC pipeline respectively.
Modifving Pipelines for Pigging
Much natural gas transmission pipeline is not currently piggable. Comments submitted by the
trade associations estimate the percentage of member pipelines in various categories describing
their ability to be pigged as:
Exhibit 4. Piggable Status of Natural Gas Transmission Pipeline
(percentage of total mileage)
34
INGAA spreadsheets submltted to the docket April 30, 2003, RSPA-2000-7666-297
3iLori Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 10
''Office of Pipeline Safety, Imti*umented Internal Inspection Devices (A Stu& Mcrntkuted by P L 100-
551), Research and Special Programs Admnistration, November 1992, p. 44.
3 1
INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297
"Lon Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 9.
43

<<<PAGE 45>>>

Percentage by
Category
Piggable
Long-
distance39
30
AGA4'
12
APGA
13
RSPNOPS uses the INGAA estimates, in this analysis, as its assumption for the distribution of
pipelines operated by long-distance operators.
RSPA/OPS assumes that the percentages reported by AGA and APGA represent the proportion of
all piping operated by their members. OPS further assumes that a higher proportion of the piping
operating at greater than 50% SMYS is piggable than these overall averages. It is this higher-
pressure LDC pipe where most assessment by pigging will occur. Th~is, it was necessary to
develop estimates for this higher-pressure LDC piping.
For purposes of this analysis, RSPNOPS assumes that 30 percent of the LDC pipeline operating at
greater than 50% SMYS is now piggable (j.e., the same percentage as reported for long-distance
transmission lines). This assumption, combined with the reduction in the overall percentage of
LDC pipeline expected to be pigged (described above) significantly reduces the amount of LDC
pipeline that will require modifications. The AGA estimates submitted to the docket assumed
modification of some hard-to-pig piping. RSPNOPS assumes that these modifications will no
longer be made, since the final rule will allow use of direct assessment as an equivalent primary
assessment mechanism without condition. RSPNOPS has assumed that only pipeline that can be
easily modified will be changed by LDCs.
The costs to perform the necessary modifications will vary between long-distance and LDC
pipelines:
For long-distance operators:
INGAA estimated costs to add launchers and receivers, make other modifications, and for gas that
will be lost when blowing down lines to make modifications for two types of changes. The first
was for 40-mile sections requiring little change other than the addition of launchers and receivers.
The second was for 10-mile sections requiring more significant modifications or pipe replacement.
The INGAA estimates for these changes were $1 l,750/mile and $76,500/miIe, re~pectively.~' This
'"INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297.
40
Lori Traweek, ACA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 6.
41
INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297; unit costs derived
by dividing stated costs for adding launchers, modifying hard-to-plg pipe, and lost gas over stated number of miles
44

<<<PAGE 46>>>

analysis uses these estimates as the cost to modify long-distance pipeline that can easily be
modified and hard-to-pig pipe respectively.
For LDC operators:
RSPNOPS assumes that much less pipe will be modified for pigging by LDC operators, since
costs to do so are very high and direct assessment is an available assessment option. Nevertheless,
AGA estimates that the percentage of pipeline that will be pigged exceeds the percentage of it’s
members’ pipeline that is now piggable. The amount of “easily modified” pipeline exceeds the
difference, so OPS assumes that all LDC pipeline that will be modified will come from this
category. AGA estimates that such pipe can be made piggable for “less than $50,000 per mile.”42
RSPNOPS has used $50,000 per mile as an estimate for these modifications.
Direct Assessment
Direct assessment is a technique for assessing the integrity of line pipe that is in the early stages of
development. Industry consensus standards governing the application of direct assessment were
only recently approved. The process consists of several steps.
The first step is pre-assessment. This involves collection and evaluation of data regarding potential
threats to pipeline integrity and their relative risks. Based on this evaluation, locations on the
pipeline are selected for indirect inspection. Inspection requires use of a minimum of two different
“tools”. Examples of direct assessment tools include close interval surveys (CIS), direct current
voltage gradient (DCVG), and pipeline current mapper (PCM). The results of the indirect
inspections are then used to identify locations for direct examination, excavation of the pipeline to
permit visual inspection. Each use of direct assessment requires at least one direct exam. The final
stage in the direct assessment process is post-assessment in which the composite set of data (Le.,
risk factors identified in pre-assessment and assessment results) are considered to identify
continuing excavation needs, determine if additional assessment technologies are needed, and to
establish a re-assessment interval.
There is very limited experience at this time from which to estimate tlie costs of performing direct
assessment on natural gas transmission pipelines. INGAA estimates these costs at $15,000 per
mile,”3 and RSPNOPS has used this estimate for long-distance pipeline. AGA reported that their
members estimate costs for direct assessment at $7,000 to $8,000 per mile, without any verification
digs.44 AGA further commented that excavation digs can cost from $2,500 to $250,000 with an
average of $40,000 for a typical large transmission line. These estimates did not prove particularly
useful due to the wide range stated for verification costs and the expectation that much LDC
pipeline is not “typical large transmission line”. Pacific Gas & Electric (PG&E), which is
42
Lori Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 6.
“INGAA spreadsheets submtted to the docket April 30, 2003, RSPA-2000-7666-297
44
Lori Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, page 9.
45

<<<PAGE 47>>>

performing direct assessment in rural and urban environments as part of research and development
to validate the process, reported an average cost to perform direct assessment in LDC environments
of $29,000 including verification digs. PG&E reported that they are using this value in their
budget planning. RSPNOPS has used the same value in this analysis for the cost to perform direct
assessment on LDC pipelines.
Confirmatory Direct Assessment
Confirmatory direct assessment is a more-focused application of the principles and techniques of
direct assessment. This method is concentrated on identifying critical segments of suspected
corrosion. The effort involved is less than full application of direct assessment.
The OPS has structured the requirements for confirmatory direct assessnient in a manner intended
to allow maximum flexibility for operators. Indirect examinations may be performed using only
one, rather than two, tools. Corrosion regions may be larger than for regular direct assessments.
The number of excavations required per region is less. These changes will allow operators to plan
and conduct confirmatory direct assessments in a manner that is most cost-effective, i.e., identifies
areas of concern at lowest cost.
There is no data available at present regarding the cost to implement confimatory direct
assessment. In their comments, INGAA estimated that Confirmatory direct assessment (CDA)
would cost $1000 per mile.45 AGA estimated $3,360 per mile, but that appears not to include
verification digs.'(' The rule requires at least one verification dig per CDA Region. RSPA/OPS has
used an estimate of $8,000 per mile for CDA costs to LDCs, reflecting the required verification.
Additional Mileage Must Be Tested
It is usually not possible to hydrostatically test or pig pipe in high consequence areas without also
testing some adjacent piping. Hydrostatic testing requires valves that can isolate the pipe segment
being tested. Pigs niust be run between available pig launchers and receivers, which are seldom
located immediately adjacent to the boundaries of high consequence areas. Valves arc spaced
closer together than launchers and receivers, meaning that the amount of additional mileage that
must be subjected to hydrostatic tests is less than that which will be pigged.
RSPNOPS, in the draft regulatory analysis, estimated the amount of overtest mileage at 200
percent for pigging and 25 percent for pressure testing. (No additional mileage must be tested for
direct assessment). These assumptions had been increased as a result of comments by tlie
Technical Pipeline Safety Standards Committee. Industry comments indicated that the revised
estimates still significantly underestimated the amount of overtesting that would occur for long-
distance pipeline that will be tested by pigging.
"INGAA spreadsheets submitted to the docket April 30, 2003, RSPA-2000-7666-297.
4 (I
Lori Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, attachment A.
46

<<<PAGE 48>>>

For long-distance operators:
INGAA estimated the amount of mileage that would need to be pigged in order to inspect all HCA
miles by surveying a sample of their members. They reported that 37,976 miles of pipeline would
need to be inspected in order to cover 5,244 miles of HCA pipeline expected to be pigged.47 This
equates to a factor of 7.25. RSPNOPS has used this factor for overtesting mileage for pigging of
long-distance transmission lines.
INGAA’s analysis used a multiplier of 1.3 (i.e., 30 percent additional mileage) for pressure testing.
RSPNOPS adopts the same factor.
For LDC operators:
The analysis submitted with AGA’s April 30,2003, letter to the docket assumed 100 percent
overtesting for pigging and no overtesting for pressure te~ting.~’ RSPNOPS has adopted these
estimates.
Choice of Assessment Method
Informal discussions with pipeline operators suggest that hydrostatic testing is the least preferred
method for assessing pipeline integrity. This was confirmed in discussions at the July 18, 2002,
TPSSC meeting, and in comments submitted in response to the proposed rule. This is at least in
part because hydrostatic testing can be destructive, while the other two methods are not.
Hydrostatic testing also usually requires that a line be taken out of service for a longer period than
does pigging. (Direct assessment requires limited out-of-service time or curtailment of pipeline
capacity). In addition, care must be taken in drying the pipeline subsequent to a hydrostatic test to
assure that all moisture is removed. Remaining moisture can cause internal corrosion problems
and can also lead to operational problems in freezing weather.
Pigging appears to be the preferred method of assessment for pipeline. As described above, the
per-mile cost for pigging is less than that for direct assessment or hydrostatic testing. INGAA’s
response to the OPS’s June 27, 2001, Federal Register notice indicated that the percentage of its
members piping in class 3 and 4 areas that has been pigged at least once is approximately equal to
the percentage of their mileage that is easily ~ i g g a b l e ~ ~ , despite the fact that there is currently no
requirement that pigging be performed.
The choice between direct assessment and pigging is not so obvious for pipeline that must be
modified to be made piggable. Direct assessment has the advantage of requiring little or no
interruption in normal operation of the transmission pipeline. It would likely be the method of
“INGAA spreadsheets submitted to the docket April 30,2003, RSPA-2000-7666-297.
“Lori Traweek, AGA, letter to docket dated April 30, 2003, RSPA-2000-7666-274, attachment A.
49 INGAA, Subject: Pipeline Safety: Pipeline Integrity Management in High Consequence Areas (Gas
Transmission Pipelines) (Docket No. RSPA-00-7666; Notice 2}, no date, page 45.
47

<<<PAGE 49>>>

choice for assessing those areas where supply interruption can be most problematic (e.g., single-
source laterals supplying small distribution operators). On the other hand, the costs for direct
assessment are higher than for pigging. Finally, while the direct assessment process produces a
significant amount of information about the pipeline, pigging still provides operators the most
information from actual examination of the pipe wall.
The percentage of affected pipeline that will be assessed by each method, as assumed in this
analysis, is estimated in Exhibit 5 :
Percentage by Pig DA
Pressure
Method
test
Long-distance 62 33
5
LDC 20 75
5
These estimates were drawn from the trade association analyses. They have been adjusted to
reflect changes of which the associations were not aware when they made these estimates.
INGAA estimated that 225 1 miles of affected piping would be assessed using direct assessment for
the first 5-year reassessment, based on an INGAA Foundation report. This is 26 percent of the
total HCA mileage estimated under INGAA’s bifurcated definition. Conditions on the use of
direct assessment as a primary assessment method (principally that direct assessment could not be
used unless it was not possible to assess using pigging or pressure testing) have been eliminated
since the Foundation’s report. RSPNOPS has adjusted the percentages between DA and Pressure
Testing to reflect its understanding of the strong preference of operators to use a method other than
pressure testing.
AGA’s comments estimated that the relative percentages would be 3 5 , 60, and 5 if direct
assessnient were treated equivalently to the other assessment methods. Again, these estimates were
made before the conditions on use of DA as a primary method were eliminated. RSPNOPS has
adjusted the AGA estimates to reduce the amount of pigging and increase the amount of pipeline
treated with direct assessment, reflecting the high cost estimated by AGA to modify pipe for
pigging .
Mileage Tested Per Year
Estimating costs requires determining how much transmission pipeline mileage will be tested each
year. This requires an estimate of the reassessment periodicity for individual pipeline segments
that are subject to the rule.
The rule requires that baseline assessments be conducted over a ten-year period and that some kind
48

<<<PAGE 50>>>

of re-assessment must be conducted at least every 7 years. The rule allows use of confirmatory
direct assessment as an interim reassessment for those segments reassessed using one of the other
methods at intervals greater than seven years. Reassessments using those methods are required at
10-year intervals for pipe operating above 50% SMYS, 15 years for pipe operating between 30 and
50% SMYS, and twenty years for pipe operating at less than 30 percent SMYS.
Operators of pipe requiring full reassessment every 15 years would be expected to perform an
interim assessment using confirmatory direct assessment seven years after their baseline
assessment. These operators would then have the option to conduct another confirmatory direct
assessment fourteen years after their baseline and full assessment in the following year, or they
could perform their flill assessment in the fourteenth year. RSPNOPS assumes that the costs
associated with repeating assessments within one year, even if the first were of the limited scope
applicable to confirmatory direct assessment, will lead most operators in these circumstances to
elect to perform their full assessments every 14 years. Piping for which full reassessment is
required every 15 years is thus assumed to be subjected to reassessment every 14 years with an
interim confirmatory direct assessment mid-way through the assessment interval.
Pipeline that operates below 30% SMYS is assumed to be subject to a baseline assessment and
then confirmatory direct assessment at seven and fourteen years following the baseline. Full
reassessments would likely occur at 20 years, but that is beyond the period considered in this
analysis.
The decision is less straight-forward for operators of pipe required to be assessed at ten year
intervals. These operators could perform confirmatory direct assessnient seven years following a
baseline (or full reassessment) and a reassessment using pressure testing or in-line inspection at ten
years. Seven years could then expire before another confirmatory direct assessment must be
conducted, followed in three years by a full assessment. This cycle would repeat.
These operators could, instead, perform full assessments at seven year intervals and thus avoid the
need to apply confirmatory direct assessment. The decision as to whether to shorten their full
reassessment interval, or to use confirmatory direct assessment for interim assessments, will be
made by each operator in consideration of the costs and benefits associated with each choice.
Holding to the longer reassessment intervals allowed by the rule would involve administrative
costs to maintain two different assessment programs (the regular assessment method and
confirmatory direct assessment). Field work would also be required twice within three years on
affected segments of piping. At the same time, confirmatory direct assessment requires testing of
no additional piping beyond that which can affect high consequence areas, has a lower per-mile
cost than hydrostatic testing or in-line inspection, and results in less disruption to pipeline
operation. Decisions by individual operators will depend upon factors specific to their pipeline
systems, including the total amount of piping that requires assessment and the amount of additional
piping that requires assessment when pressure testing or in-line inspection are used. For purposes
of this analysis, RSPA/OPS assumes that half of the pipeline segments that would be required to be
assessed at ten year intervals, and thus to conduct interim assessments using confirmatory direct
49

<<<PAGE 51>>>

assessment, will instead be assessed at seven year intervals. The other half are assumed to test at
ten year intervals and to use confirmatory direct assessment for interim assessments.
The number of miles to be tested each year using each assessment method will change as different
portions of the affected piping enter reassessment. For the first seven years, all assessments will be
baseline assessments. In year eight, reassessments will begin for that portion of affected piping to
be assessed by pigging or hydrostatic testing that it is assumed will be tested on seven-year
intervals. In the eleventh year, all baseline assessments will be completed and reassessments will
begin for that pipe to be reassessed on ten-year intervals. Additional piping will begin
reassessment in year fifteen, at which time piping operating between 30 and 50 percent SMYS will
begin reassessment. Ln each year, the amount of piping assumed to be pigged as a result of this
rule has been reduced by the assumption that pigging of 1.5 percent of affected piping would have
occurred even without this rule.
Confirmatory direct assessments or low-pressure reassessmeiits will also begin for some piping in
year seven. These assessments will be conducted for pipe that is to be reassessed using one of the
other methods at ten-, fourteen-, or twenty-year intervals. The confirmatory direct assessments will
stop in year fifteen for pipe that is to be reassessed on fourteen-year intervals, since this analysis
assumes that operators will alternate confirmatory direct assessments and full reassessments on this
pipe every seven years.
The total amount of pipeline mileage that will be assessed using each method in the years
following the effective date of this final rule, given the assumptions described above, is displayed
in Exhibit 6.
50

<<<PAGE 52>>>

Year after Pigging Hydrostatic Direct
Effective Testing Assessment
Date
Base Re Base Re Base Re
Confirmatory DA
1-7 5,125 0 126 0 1,087 0
8 - 10 5,125 4,261 126 90 1,087 390
11 - 14 0 6,403 0 153 0 664
15 - 17 0 6,403 0 153 0 921
18 - 20 0 6,403 0 153 0 92 1
IO-yr IS-yr 20-yr
pipe pipe pipe
0 0
4,612 257 Note 1
4,612 257 Note 1
4,612 0 Note 1
0 0 Note 1
51

<<<PAGE 53>>>

Note 1 Pipeline subject to 20-year reassessments is low-stress pipeline and is assumed to receive low-stress
reassessment at 7-year intervals rather than confirmatory DA Costs for the low-stress reassessment ale consideled
along with preventive measures for that pipeline
Cost of Baseline Testing
Baseline testing costs are estimated by applying the per-mile cost estimates described above to the
mileage to be tested each year. This includes the cost to modify piping requiring modification.
Cost of Subsequent Testing
The cost of subsequent testing will be reduced, since the permanent pig launchers and receivers
and other modifications installed for baseline testing will be used and no additional pipeline
modifications will be needed. Costs to perform testing may increase slightly due to growth of
populated areas near the pipeline. (Costs may not grow as much as populated areas grow, since
additional piping that may be determined to be in high consequence areas may have been included
in the additional miles pigged or hydrotested during the baseline period and would therefore not
add to the total miles to be tested). RSPA/OPS has not considered this growth in this analysis.
Total Cost of Testing
The total cost of testing is thus as shown in Exhibit 7
Year after Pigging Hydrostatic Direct
Effective Testing Assessment
Date
Base Re Base Re Base Re
Confirmatory DA
1-7 232.1 0 4.21 0 25.75 0
8 - 1 0 232 1 17.12 4.21
3.0 25.75 7.21
11 - 14 0 26.08 0 5.1 1 0
12.25
1 5 - 17 0 26.08 0 5.1 1 0 19.71
1 8 - 2 0 0 26.08 0 5.1 1 0 19.71
10-yr 15-yr 20-yr
Pipe pipe pipe
0 0 0
6.41 2.06 Note 1
6.41 2.06 Note 1
6.41 0 Note 1
0 0 Note 1
Costs of Service Interniption
52

<<<PAGE 54>>>

The Interstate Natural Gas Association of America (INGAA) sponsored an analysis5" evaluating
the costs to consumers from service interruptions that they presumed would occur if testing
requirements such as those included in the proposed rule were imposed. This analysis is available
in the docket. It concluded that consumer costs would rise, perhaps significantly, due to increased
costs of gas transmission if portions of the transmission pipeline network were required to be
removed from service for testing.
Both the Department of Energy (DOE) and the Office of Pipeline Safety have analyzed the INGAA
report. RSPA/OPS contracted with the Volpe National Transportation Systems Center to review
INGAA's report. Both evaluations were performed considering the estimates in the preliminary
draft regulatory evaluation prepared for discussion with TPSSC in July 2002. Both DOE and the
Volpe Center concluded that the proposed rule would not have an impact on the domestic price of
natural gas. RSPNOPS notes that the conclusions of DOE and the Volpe Center were both
predicated, in part, on the ability of operators to conduct inspections during non-peak demand
periods, and under the assumptions used in the preliminary draft analysis most testing should have
been able to be performed during off-peak times. This is likely no longer the case.
Changes k a t have been made in this analysis reduce the number of high consequence area miles
estimated to require testing compared to the situation reviewed by DOE and Volpe. At the same
time, the revised estimate of overtesting mileage results in more total miles being tested. This
greatly curtails, probably eliminating, the ability of operators to perform all testing during off-peak
periods.
Other changes in the final rule will result in less pipeline being removed from service for testing.
The changes in reassessment requirements for low stress piping are particularly important in this
regard. These changes are unlikely to offset completely, the likelihood of supply effects from the
considerable amount of high-pressure long-distance piping that will be assessed.
As a result, RSPNOPS acknowledges that there likely will be some cost increase to consumers as
a result of curtailmeiit of the ability to transport gas during testing. RSPNOPS does not know how
large this cost will be and has not included it in the cost estimates in this analysis. A summary of
the issues raised in review of the INGANEEA analysis, and the positions taken by the various
reviewers, is provided in the appendix.
Consideration of Remote Control Valves (RCV) and Automatic Shutoff Valves (ASV)
The final rule requires operators to conduct a risk analysis of their pipeline to identify additional
actions to enhance public safety. Such actions include, but are not limited to, installing ASVs or
RCVs, computerized monitoring and leak detection systems, extensive inspection and maintenance
programs, etc. If an operator deterniines that an ASV or RCV is needed to protect high
consequence areas in the event of a gas release, the operator must install the valve.
50"
Consumer Effects of the Anticipated Integrity Rule for High Consequence Areas," prepared for the
INGAA Foundation, Inc. by Energy and Environmental Analysis, Inc., 2002
53

<<<PAGE 55>>>

Natural gas transmission lines are already required to be equipped with sectionalizing block
valves.” The required spacing of these valves varies for different class locations. Valves must be
no more than 5 miles apart in class 4 areas, 8 miles apart in class 3, 15 miles apart in class 2 and 20
miles apart in class 1 . Some of these valves are presently remotely operable. The requirement of
this rule will have the primary effect of requiring operators to conduct risk assessments to
determine if conversion of any of the now-manual valves to remote or automatic operation is
needed.
RSPA/OPS completed a feasibility study on remotely controlled valves on interstate natural gas
pipelines in 1999.” In conjunction with that study, RSPNOPS conducted a public meeting and
solicited written comments (see 62 Federal Register 5 1624, October 2, 1997). The study
determined that conversion of valves to remote operation was not economically feasible. Most
fatalities and injuries resulting from natural gas pipeline ruptures occur very quickly, before the
time that would be required to isolate the pipeline using RCVs. Similarly, a significant amount of
the property damage experienced in historical accidents occurred immediately after the rupture.
The 1999 feasibility study detemiined that the value of gas lost before the pipeline could be
isolated would be the principal benefit, and that the value of that benefit did not offset the costs of
converting the valves.
Operators will need to re-visit this generic conclusion for particular pipeline segments that can
affect high consequence areas. RSPNOPS expects that the conclusion that most fatalities and
injuries could not be avoided by conversion of valves will not be changed, since historical accident
experience shows that injuries and fatalities occur very quickly after any pipeline rupture.
Circumstances specific to individual pipeline segments that can affect high consequence areas
could, however, change the generic conclusion that significant property damage cannot be avoided
through use of RCVs. This could lead to a need to convert some sectional valves to remote
operation.
The 1999 study reported on the results of a one-year field evaluation of RCVs conducted by Texas
Eastern Transmission Corporation (TETCO) pursuant to a settlement agreement in the compliance
case involving the 1994 pipeline rupture in Edison Township, NJ. The study reported that TETCO
experience indicated that costs to install a RCV ranged from $1 50,000 to $500,000, depending on
the number of valves at the same locations and variatioiis in permitting costs. The study further
estimated that the cost for converting an existing valve, on average, was between $1 25,000 and
$150,000, including efficiencies that could be realized by dividing site costs over a number of
valves in an individual location, The study concluded that there was no significant impact on
direct operating costs, since the maintenance activities for the additional equipment were absorbed
in the iiinction of the personnel working valve sites for other purposes.
5149 CFR 192 179, “Transnxssion Line Valves”
5 2 ‘ , Remotely Controlled Valves on Interstate Natural Gas Pipeliiies (Feasibility Detemlination Mandated by
the Accountable Pipeline Safety and Partnership Act of 1996)”, September 1999.
54

<<<PAGE 56>>>

RSPNOPS does not have any information on which to base a conclusion about how many natural
gas transmission line sectional valves may be converted to RCVs. Because there are so many
factors in an operator’s decision to install or not to install these valves, RSPNOPS has decided
there would be no valid approach, including a sensitivity analysis, to make such an estimate. The
OPS has thus not estimated the industry costs to convert valves. The OPS assumes that operators
will not make such conversions unless the benefits (expected reduced property damage and value
of lost gas) exceed the approximately $1 50,000 conversion cost, and thus there should be no net
cost from valve conversions.
Operators will be required to analyze their systems to determine whether it is cost-beneficial to
convert valves. RSPMOPS assumes that these analyses will be conducted by staff engineers. The
time required for these analyses is expected to be relatively small, since generic conclusions are
already available and the effect of site-specific factors will be the focus of operator evaluations.
RSPNOPS estimates that this will require approximately several man-months for pipeline
operators with more than 30 miles of pipeline, at a cost of approximately $50,000. Operators with
less than 30 miles of pipeline should be able to conduct these evaluations in about half the time at a
cost of approxiniately $25,000.
The total cost for considering the need to convert valves to ASV or RCV is thus $1 1,525,000.
These costs will be incurred once and are assumed to be incurred in the first year after the rule
becomes effective.
The Costs of Data Integration
As described above, integration of all information relevant to the integrity of the pipeline is a key
element of the integrity management plans required for high consequence areas. Assuring this
integration will require that operators’ internal data management systems be aligned and managed
in such a way that relevant information is brought together. It will also require that the importance
of this information be assessed by experienced pipeline safety professionals.
RSPMOPS estimated these costs on a per-company basis in the draft regulatory analysis. That
analysis projected that first year costs for operators with 40 or more miles of pipeline would be
$100,000 and that continuing costs would be $50,000 annually thereafter. For operators with less
than 40 miles of pipeline, the draft regulatory analysis estimated that first year costs will be
$25,000, and that continuing costs will be $1 2,500.
Industry comments suggested that the draft regulatory analysis had seriously underestimated the
initial costs. INGAA estimated that operators would incur costs of $1,359 per mile to retrieve old
data and set up the integration system. Annual costs thereafter, by INGAA’s estimate, would be
$1 13 per mile.53 RSPNOPS agrees that initial costs to retrieve relevant data could be high. Much
existing pipeline was installed many years ago. Records for installation and early years of
operation are on paper and are not always readily accessible. Operators will need to access those
s31NGAA spreadsheets submitted to the docket April 30,2003, RSPA-2000-7666-297
55

<<<PAGE 57>>>

records and to convert many of them to electronic form for future use. RSPNOPS also agrees that
it is reasonable to estimate costs for these efforts on a per-mile basis. The records involved relate
to the pipe, and it is reasonable to assume that there would be 10 times as many records for 1,000
miles of pipeline as for 100 miles. RSPNOPS has adopted the INGAA estimates for use in this
analysis.
The work of gathering records and integrating data applies to more than pipeline segments that are
in high consequence areas. The rule requires that a risk analysis be performed that considers the
entire pipeline. The rule also requires that lessons learned through assessment of pipeline
segments that are in high consequence areas be applied, as appropriate, to other areas of the
pipeline with similar characteristics and potential for similar problems. Operators will not be able
to comply with these requirements unless they retrieve records and organize data for their entire
pipelines. The per-mile costs for data integration must thus be applied to the entire length of
transmission pipeline mileage, not -just to pipeline in high consequence areas.
The result of these changes is a significant increase in the estimated costs for data integration over
those estimated in the draft regulatory analysis. RSPNOPS estimates that long-distance operators,
with 225,000 miles of pipeline, will incur costs of $305,775,000 for setup (assumed incurred in the
first year) and $25,425,000 annually thereafter. For LDC operators, with 60,000 miles of pipeline,
the corresponding costs are $8 1,540,000 for the first year and $6,780,000 annually thereafter.
The Cost of Preventive Measures for Low-Stress Pipeline
The final rule recognizes that low-stress pipeline (i.e., that operating below 30% SMYS) is
different from pipeline that sees higher stresses. Low-stress pipeline tends to fail by leakage rather
than rupture. Accordingly, the rule includes different methods for interim assessment of low-stress
pipelines, which focus on preventing corrosion failures that could result in leaks. These
assessments are required for low-stress pipeline that is in high consequence areas. As described
above, the amount of such pipeline is expected to be small, since the corresponding potential
impact circles are small. Accordingly, the rule also requires preventive measures to be applied to
all low-stress pipeline in class 3 and class 4 areas. These measures include required participation
in one-call systems, use of qualified personnel for conducting and supervising excavations,
improved public communication programs, and increased monitoring and patrolling. These
measures are designed to reduce the likelihood that outside force, from third party excavations, will
damage the pipeline. Third party damage is the most likely cause of catastrophic failures on low-
stress pipelines.
RSPNOPS has estimated the cost to perform the low-stress reassessment applicable to pipeline in
high consequence areas as $1,000 per mile. These reassessments would be conducted on the 1,800
miles of low-stress pipeline estimated to be in high consequence areas at seven-year intervals. The
annual cost to perform these reassessments is thus $257,143.
RSPA/OPS estimates that the cost to implement the preventive measures required for all low-stress
pipeline in class 3 and class 4 areas is $1 50 per mile per year. Those measures are required on a
56

<<<PAGE 58>>>

continual basis, so these costs will be incurred every year. For purposes of this analysis,
RSPNOPS has assumed that these costs apply to all 17,000 miles of LDC pipeline estimated to be
in class 3 and 4 areas. The annual costs for these preventive measures is thus $2,550,000.
The Cost of Remedial Action
Inspection and testing and integration of other relevant data will identify anomalies that must be
investigated and remediated. Real improvement in pipeline safety will not occur unless problems
are addressed. The number of anomalies that will require action or the cost of that action can not
be known until the assessments are performed. In addition, other provisions of Part 192 require
operators to repair known anomalies that can impact pipeline integrity; the requirements of the rule
merely serve to identify the anomalies. Costs. associated with remediation are therefore not
estimated as part of this analysis.
TOTAL COSTS
Costs have been estimated for: ( I ) identifying pipeline segments that can affect HCAs, (2) plans
and reports, (3) evaluating valves for possible conversion to automatic closing or remote operation,
(4)testing ( 5 ) data integration, and (6) preventive measures for low-stress pipelines. Exhibit 8
presents a summary of these costs, presented by the year that they are incurred after the effective
date of the final rule.
57

<<<PAGE 59>>>

EXHIBIT 8. THE ESTIMATED COST OF THE FINAL RULE
(Costs in millions of 2001 dollars)
58

<<<PAGE 60>>>

CONCLUSIONS
Issuance of this final rule will ensure that all operators will perform at least to a baseline safety
level and will contribute to an overall higher level of safety nationwide. It will lead to greater
uniformity in how risk is evaluated and addressed and will provide more clarity in discussion by
government, industry and the public about safety issues and how they can be resolved.
The flexibility of a perfomlance-based approach provides several advantages. It encourages
development and use of new technologies. It is an important feature in supporting operators’
development of more formal, structured risk evaluation programs and in RSPA/OPS’s evaluation
of them. It provides greater ability for operators to customize their long term maintenance
programs. It has also stimulated the development of a supplemental industry standard, which is
referenced in the rule. A performance-based approach will also encourage the development and
maturing of risk-based approaches to integrity management.
Our emphasis on the integrity management system encourages a balanced program, addressing the
range of prevention and mitigation needs and avoiding reliance on any single tool or overemphasis
on any single cause of failure. This orientation will lead to addressing the most significant risks,
and is the best opportunity to improve industry performance and assure that the high consequence
areas get the protection they need. It also addresses the interrelationships among failure causes and
benefits. It promotes the coordination of risk control actions, beyond what a compliance-based
approach would achieve.
The rule provides for a verification process, which gives the regulator a better opportunity to
influence the methods of assessment and the interpretation of results. This is not to say the
regulator would overstep the bounds of oversight, but would provide a beneficial challenge to the
adequacy of the operators’ decision process. This leads to greater accountability to the public.
A particularly significant benefit is the quality of information that will be gathered as a result of
this rule to aid operators’ decisions about providing additional protections. Two essential elements
of the integrity management program are that an operator continually assess and evaluate the
pipeline’s integrity and perform an analysis that integrates all available information about the
pipeline’s integrity. The process of planning, assessment and evaluation will provide operators
with better data on which to judge a pipeline’s condition and the location of potential problems that
must be addressed.
Integrating this data with the safety concerns associated with high consequence areas will help
prompt operators and the Federal and state governments to focus time and resources on potential
risks and consequences that require greater scrutiny and the need for more intensive preventive and
mitigation measures. If baseline and periodic assessment data is not evaluated in the proper
context, it is of little or no value. It is imperative that the information an operator gathers is
assessed in a systematic way as part of the operator’s ongoing examination of all threats to the
pipeline integrity. This rule is intended to accomplish that.
59

<<<PAGE 61>>>

The cost estimates in this evaluation reflect the estimated costs for operators to establish the
necessary integrity plans and data integration processes, to integrate and analyze the data, to
consider the need to convert some valves, to perform testing of piping in high consequence areas,
and to implement additional protective measures for low-stress pipeline in class 3 and 4 locations.
The evaluation reflects the fact that some operators have begun testing programs and would be
expected to continue those programs without this rule.
The cost for operators to identify pipeline segments that can affect high consequence areas is
estimated to be $1 5.05 million. These costs will be incurred in the first year after the effective date
of the rule.
The integrated cost to all operators for developing integrity management plans is estimated to be
$1 04.13 million. First-year costs for establishing required reports are estimated to total $1 1.08
million. Annual costs of $12.9 1 million are projected to review the plans, make changes as
needed, and to prepare routine reports.
Data integration is a significant cost, but it is also one of the most important elements of the rule.
First year costs to retrieve old data, prepare it for use with future integrity information, and to
realign data management systems to facilitate integration are estimated to be $387.32 million.
Retrieval of old data is a one-time cost. Costs for data integration reduce to $32.21 million per
year after the first year.
Testing is a key element of the rule. A portion of transmission pipeline in high consequence areas
will be inspected each year, using one of three specified methods. (The rule would allow operators
to use alternative methods, with adequate justification, but no additional methods are projected in
this analysis). Modification of some pipeline will be required initially to permit the use of in-line
inspection tools. These modifications add to the cost of performing the initial, or baseline,
inspections. Baseline inspection costs across the industry are estimated to be $262.12 million
annually for the ten years of the baseline period. Testing costs will increase in the eighth year,
because operators will be required to begin re-assessing piping. Testing costs in years 8, 9, and 10
will increase by $35.84 million as a result of the additional testing for reassessments. After ten
years, all necessary modifications will be completed. Testing costs will then be reduced to
between $50.9 and $57.3 million per year, depending on which pipeline is due for reassessment
during each year.
The total of all costs expected to be incurred over the 20 years following the effective date of this
rule is $4.7 billion.
The benefits expected to be realized as a result of implementing this rule more than offset its costs.
As described in the evaluation, total benefits are estimated to be $9.3 billion. Of these, $7 billion
is reasonably certain. This consists of $800 million in safety benefit from expected reductions in
deaths, serious injuries, and property damage from pipeline accidents, and $6.2 billion in reduced
costs to industry over what it would otherwise cost to implement the requirements of the Pipeline
Safety Improvement Act of 2002 without the refinements and flexibility added by this rule.
60

<<<PAGE 62>>>

The remaining $2.3 billion in quantified benefits is more uncertain. There is little doubt that an
accident of much greater consequences than any previously experienced could occur. There is also
no doubt that implementing the requirements in this rule makes such an accident less likely.
Quantifyng the value of this improvement is difficult, since it requires making assumptions about
very unlikely events occurring concurrently. RSPNOPS is confident that the estimate in this
analysis of $277 million represents the order of magnitude of this benefit, although the precise
value is highly uncertain. Similarly, the estimate that a $1 billion benefit accrues due to avoiding
the economic impacts of future accident-induced gas supply interruptions also has a high degree of
uncertainty. It is clear from the experience in California in 2000, though, that economic impacts of
this magnitude can result from gas transmission pipeline accidents, and RSPNOPS believes that
this estimate, though uncertain, is reasonable.
The final benefit of $1 billion in reduced cost due to relief from class location requirements for
pipe replacement is more certain. Granting relief from these requirements is within the authority of
RSPNOPS. The agency has experience exercising that authority, through the Risk Management
Demonstration Program. There is some uncertainty regarding when sufficient information will
have been generated by integrity management program to grant future relief. This could reduce the
benefit realized during the 20-year period of this analysis somewhat. It is virtually certain,
however, that the entire benefit will be realized, and it is very likely that even more benefit will be
seen after this 20-year period from further relief or changes to the class location change
requirements.
As described in the analysis, there are also a number of qualitative benefits that will be realized as
a result of implementing this rule. Foremost among these is providing a basis for improved public
confidence in pipeline safety. Economic benefits are expected to accrue from this increased level
of confidence, including reduced costs for siting and constructing new pipeline, thereby allowing
access to the environmental benefits of increased use of natural gas in lieu of other fuels.
Comments by members of the Technical Pipeline Safety Standards Committee (TPSSC), and
members of the interested public who spoke at their July 18,2002, meeting, indicate their belief
that the benefit of increased public confidence to be realized by implementing the rule, alone,
justifies its costs.
The estimated costs are certainly large, but need to be considered in context. Many of these costs
will be reflected as increases in the cost of natural gas. During 2001, a total of 20.48 trillion cubic
feet of natural gas was delivered to US. consumers.54 If the total projected first-year costs of
$793.77 million are divided over this quantity of natural gas, the result would be an increase in
delivered price of 3.87 cents per thousand cubic feet. The average U.S. residential customer used
79 thousand cubic feet of natural gas in 2001 .j5 The effect of these costs would therefore be an
increase in the nionthly bill for this average residential consumer of 25 cents. After the first ten
5 4 N ~ t ~ i m l Gas Annual 2001, Energy Information Administration, page 44.
551bid, page 45. Determined by dividing the reported total volume of natural gas delivered to consumers by
the reported number of consumers.
61

<<<PAGE 63>>>

years, when all pipeline modifications are completed, the increase in average residential cost would
be 3.2 cents per month.
RSPNOPS believes that the process of developing an integrity framework and schedule and
integrating data related to pipeline integrity is an important process for the operator, the
government and the general public. The creation, and development of the plan will alert operators
to the potential risks and consequences unique to high consequence areas. The planning process,
including the testing schedule, also provides a level of confidence to Federal and state pipeline
inspectors that pipeline operators are considering, examining, testing, and repairing if necessary,
natural and other gas transmission pipelines that potentially pose severe consequences to public
safety. Finally, standardizing the requirements nationally for transmission pipelines will save
operators having to face potentially different testing and inspection requirements from the various
state pipeline agencies.
The OPS concludes that the benefits justify the costs associated with initial implementation of the
requirements in the final rule.
Appendix
Costs of Implementing Pipeline Safetv Improvement Act of 2002
The Pipeline Safety Iniprovement Act of 2002 (PSIA-2002) requires that RSPAIOPS issue a rule
establishing requirements for integrity management plans for gas transmission pipelines. PSIA-
2002 also imposes requirements directly on pipeline operators. The Act requires that operators
must develop integrity management plans and must conduct assessments even if RSPNOPS fails
to publish a rule establishing requirements. If this rule is not published, therefore, operators would
need to develop plans and conduct testing to comply with the law.
PSIA-2002 establishes no detailed requirements for integrity management plans. RSPNOPS
presumes that most operators would use the industry consensus standard, ASME/ANSI B3 1.8S, as
the basis for plans they would develop. That standard is referenced in the final rule, and forms the
basis for integrity management plans that the rule requires. Costs to operators would thus be
similar for developing and managing their integrity management programs under the rule or under
PSIA-2002 in the absence of a
Costs of testing would increase significantly, however. There are several changes made in this rule
that have the effect of significantly reducing testing costs. These are:
56
The detailed requirements in the rule provide a basis for RSPA/OPS and state pipeline safety regulators to
oversee operator development of integrity management plans and to use their enforcement authority to assure that the
plans are complete and are thoroughly implemented. In the absence of such oversight, some operators nlight not
fully iniplement all provisions of ASMEiANSI B3 1.8S, resulting in lower costs. For purposes of this analysis, any
such reduction in costs has been ignored.
62

<<<PAGE 64>>>

2. 3. Changes in the definition of high consequence areas. PSIA-2002 requires that assessments
be performed on “each of the operator’s facilities in areas identified pursuant to subsection
(a)(l) [of 49 U.S.C.
601091 and defined in chapter 192 of title 49, Code of Federal
Regulations, including any subsequent modifications” (emphasis added).57 The
referenced portion of the U.S. Code reflects previous legislative action directing
RSPNOPS to define high consequence areas. The reference to 49 CFR 192 is thus to the
definition of high consequence areas. This rule makes changes to that definition. The rule
requirements therefore apply to the reduced amount of pipeline mileage expected to be
determined to be in high consequence areas under the modified definition. Without these
modifications, significantly more pipeline would be subject to assessment requirements.
Introduction of confirmatory direct assessment (CDA). PSIA-2002 requires that an
assessment be performed every seven years. It specifies acceptable assessment methods as
in-line inspection, pressure testing, direct assessment and “an alternative method that the
Secretary [of Transportation] determines would provide an equal or greater level of
safety”.58 This rule establishes CDA as such an alternative method. If this rule were not
adopted, all assessments would need to be performed using one of the other three listed
methods. Those methods are all more expensive to use than CDA, and pose greater
potential for interruption in gas service.
Low-pressure reassessment. Here, again, RSPNOPS is exercising its authority to
determine that alternative assessment methods are acceptable. This rule provides that low-
stress pipeline (i.e., pipeline operating below 30% SMYS) be assessed every seven years
using tests to assure the adequacy of corrosion protection. These tests are less expensive,
and less intrusive than CDA, and considerably less expensive than the other specified
assessment methods. If this rule is not published, all low-stress pipeline would be required
to be assessed using the more expensive methods on seven-year intervals.
RSPNOPS has estimated the costs that would be incurred if PSIA-2002 were implemented
without the changes made in this rule. This analysis uses the high consequence area mileage
estimated for the draft regulatory analysis, before the changes in high consequence area definition
included in this rule. The analysis uses the updated unit costs (i.e., costs per niile or costs per
company for various elements) adopted from industry comments for this final regulatory analysis,
so that a direct comparison between costs estimated here and those estimated for implementing the
rule would be valid.
The costs to implement PSIA-2002, without the changes made in the final rule, are estimated in
Exhibit 9.
Exhibit 9. Pipeline Safety Improvement Act of 2002
57Pipeline Safety Improvement Act of 2002, Section 14, “Risk Analysis and Integrity Management
Programs for Gas Pipelines”
581bid.
63

<<<PAGE 65>>>

(in millions of dollars)
Year Segment Integrity Valve Annual Baseline Subsequent
ID Plans Analysis Reports Testing Testing
1 13.77 104.13 11.53 11.08 810.23 -
2 - 11.53 - 1.38 810.23
3 1 1 .53 - 1.38 810.23 -
4 11.53 1.38 810.23 -
- -
5 - 11.53 - 1.38 810.23
6 11.53 - 1.38 810.23 -
7 - 11.53 1.38 810.23
~
8 11.53 - 1.38 810.23 111.69
9 - 11.53 1.38 810.23 111.69
10 11.53 1.38 810.23 11 1.69
- -
1 1 11.53 1.38 - 111.69
12 - 11.53 1.38 1 1 1.69
13 11.53 1.38 - 11 1.69
- -
14 11.53 1.38 11 1.69
15 11.53 1.38 - 11 1.69
- -
16 11.53 - 1.38 - 1 11.69
17 11.53 - 1.38 1 1 1.69
18 11.53 1.38 111.69
19 - 11.53 1.38 11 1.69
20
11.53 - 1.38 111.69
Integration Total
~~~ ~
387.32 1,338.04
32.21 855.33
32.21 855.33
32.2 1 855.33
32.21 855.33
32.21 855.33
32.21 855.33
32.21 967.03
32.21 967.03
32.21 967.03
32.21 156.80
32.21 156.80
32.21 156.80
32.2 1 156.80
32.21 156.80
32.21 156.80
32.21 156.80
32.21 156.80
32.21 156.80
32.21 156.80
20-yr 10,939.12
total
The total 20-year cost of $1 0.94 billion compares to the corresponding total for implementing the
final rule of $4.7 billion. The difference of $6.24 billion represents a savings to the pipeline
industry from establishment of the requirements in the final rule.
Updated Cost Estimates for the Proposed Rule
As described in the analysis, RSPNOPS revised the unit costs used in this analysis. Industry
comments indicated that the costs used in the draft regulatory analysis were significantly below the
current costs for activities that would be required by this rule. Industry comments also indicated
that a much greater amount of pipeline mileage would be “overtested”, i.e., more miles outside of
high consequence areas would be pigged in order to assess miles within high consequence areas.
The cost estimates included in the draft regulatory analysis, reflecting the estimated costs for
implementing the rule as originally proposed, are much lower than they would have been had the
new unit costs been used in that analysis.
RSPA/OPS has re-estimated the costs to comply with the proposed rule, so that the effect of
changes made in the final rule can be better understood. The draft regulatory analysis considered
64

<<<PAGE 66>>>

two scenarios, one in which a significant amount of pipeline would be modified to accommodate
pigs (called the pipe modification scenario) and one in which only easy-to-modify piping would be
modified (the limited modification scenario). Industry comments, both written and in the public
meetings that occurred during the comment period, strongly indicated that hard-to-modify pipe
would be changed and that pigging would be the predominant method used for conducting
assessments. Based on those comments, RSPMOPS did not consider two scenarios in the final
regulatory analysis. The costs were estimated based on the assumption that significant amounts of
pipeline will be modified, similar to the pipe modification scenario in the draft regulatory analysis.
Cost estimates have been updated for the pipe modification scenario of the draft regulatory
analysis, which is most comparable to the pipe modification assuniptions made in the final
regu I atory analysis.
The revised cost estimates for the proposed rule (pipe modification scenario) are presented in
Exhibit 10.
Year
I
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
(in millions of 2001 dollars)
Segment Integrity Valve Annual Baselin Sub. Integration Total
ID Plans Analysis Reports e Testing
Testing
13.77 104.13 11.53 11.08 816.84 387.32 1,344.65
- - 1.38 816.84 32.21 850.42
- 1.38 816.84 - 32.21 850.42
- - 1.38 816.84 32.21 850.42
- - - 1.38 816.84 - 32.21 850.42
- - 1.38 816.84 30.85 32.21 88 1.26
- - 1.38 816.84 30.85 32.21 881.26
- - 1.38 794.81 61.80 32.21 890.18
- - 1.38 794.81 61.80 32.21 890.18
- - 1.38 794.81 61.80 32.21 890.18
- 1.38 66.89 32.21 100.47
- 1.38 66.89 32.21 100.47
- - 1.38 - 66.89 32.2 1 100.47
- - 1.38 66.89 32.2 1 100.47
- - -
1.38 89.1 1 32.21 122.69
- -
1.38 89.1 1 32.21 122.69
- - 1.38 - 89.11 32.2 1 122.69
- 1.38 89.1 1 32.21 122.69
- 1.38 89.1 I 32.2 1 122.69
- - 1.38 89.1 1 32.2 1 122.69
20-yr total 10,3 17.40
The total estimated cost for implementing the rule as originally proposed is $10.32 billion, less
than 10 percent below the cost estimated to implement PSIA-2002 if no rule is adopted. This is
65

<<<PAGE 67>>>

despite the fact that the proposed rule included use of confirmatory direct assessment (CDA) to
meet the seven-year assessment requirement of PSIA-2002, significantly reducing subsequent
assessment costs. The reason that costs for the proposed rule are not considerably less than costs to
implement PSIA-2002 is that the proposed rule included shorter intervals for assessments to be
conducted using direct assessment (DA). As proposed, baseline DA assessments were to be
completed in seven years (vs. ten) and reassessments would have been required every five (vs. ten
fifteen, or twenty). The increase in costs associated with more frequent DA assessments nearly
offsets the cost reduction afforded by the inclusion of CDA.
Changes made in the filial rule thus reduced the estimated 20-year costs by $5.62 billion. The
principal changes resulting in these savings are revising the assessment intervals for DA to be like
those for other assessment methods and refining the definition of high consequence areas. This
reduces significantly the amount of pipeline that will be determined to be in high consequence
areas, and thus will require assessment. The change better focuses attention on those areas in
which significant population could be at risk. The mileage deleted represents areas that meet the
definition of class 3 locations but which are relatively more sparsely populated, in which 20
buildings intended for human occupancy are not within the potential impact circle associated with
a postulated pipeline accident.
The introduction of low-stress reassessment, better focusing reassessment requirements for low-
stress pipelines on the failure mode expected for such pipelines, also contributes to the reduction in
costs from the proposed rule.
RSPNOPS concludes that the changes made in the final rule are appropriate, are responsive to
public comments, and have significantly reduced the estimated costs for complying with the rule.
Potential Supply Curtailments due to Assessment Requirements
INGAA submitted to the docket an analysis performed by Energy and Environmental Analysis, Inc.
that predicted the potential for significant supply interruptions resulting in increases in the price of
natural gas to the consumer. The analysis was performed prior to publication of the proposed rule,
and considered the likely effects of provisions that might have been included in the rule. The
model is designed to look at changes in gas supply and the effect on monthly prices at market hubs.
The analysis was reviewed for RSPNOPS by DOE and the Volpe National Transportation Systems
Center. The major issues and positioils of the various agencies and INGAA are summarized in the
following table.59
'"At a meeting with RSPAIRSPAIOPS on July 10, 2003, FERC noted that recent years have seen high
sunimei load factors, relatively fewer periods of low demand, and thus a higher potential for service interruptions.
FERC noted that interruptions for planned maintenance, including assessments, should be less costly than unplanned
interruptions duc to accidents.
66

<<<PAGE 68>>>

Reviews of EEA Analysis of Potential Supply Interruption
Issues
id Positions of RI
iewers
INGAA
DOE
Issue RSPNOPS
Volpe
Applicability of
EEA Model
Ability of natural
gas transportation
system to
accommodate
inspections
Effect of redundant
pipeline capacity,
loop lines, etc.
Improvements in
efficiency and
scheduling of testing
Effect of unplanned
outages
Model is integrated
tool, best for
predicting market
prices
Lack of capacity in
some regions will
lead to down time
and potentially
significant spikes in
market price.
Model accounts for
redundant systems.
They are not
sufficient to
accommodate all
needs.
Model is
proprietary, not
designed to examine
impact of ongoing
rule
Given reasonable
planning time,
inspections can be
scheduled to
rmnimze down
time, like routine
maintenance
Existing storage and
redundancies will
prevent supply
interruptions in most
cases
INGAA did not
account for
improvements in
efficiency of
scheduling and
conducting
inspections over
time
The effect of
unplanned outages,
e.g., accidents,
could be far greater
Inspections can be
accommodated as
part of routine
maintenance
Position is similar to
DOE
Concurs with DOE
RSPA/OPS cannot
validate the model.
Output is very
dependent on
assumptions. Point
estimates of effect
of rule are difficult.
Agrees with DOE
Whether
interruptions can be
ehmnated is
unknown The
situation is without
piecedent
Sufficiency of
redundancies IS
unknown Single-
supply lines could
be a problem
RSPA/OPS agrees
that experience is
likely to lead to
greater efficiencies,
but they are difficult
to estimate without
past experience to
guide us.
Concurs with DOE
Impact on wellhead
and production
Testing in peak
season
Some testing will
need to be done at
peak periods. Dual-
peak systems make
it more difficult to
schedule non-peak
Testing done in off-
peak seasons will
have little effect on
prices
The rule will have
no effect on
wellhead prices or
production capacity
Concurs with Volpe
Concurs with DOE Agrees off-peak
scheduling will
mitigate effect.
Ability to complete
required testing off-
peak is unknown
67

<<<PAGE 69>>>

Significant changes were made to the rule following completion of the EEA analysis. These
reduce the amount of pipeline mileage expected to be in high consequence areas. The distributed
nature of these areas, however, may mean that the amount of long-distance transmission pipeline
that will be pigged to comply with the rule has not changed significantly. In addition, elimination
of conditions on the use of direct assessment makes that a more viable assessment option. The
actual amount of testing that will be performed, and whether some expected pigging will shift to
direct assessnient, are currently unknown. Future additions to pipeline capacity will also affect the
likelihood of supply interruptions, but the magnitude of that effect cannot now be estimated with
any certainty.
In conclusion, the situation is unprecedented. There is a possibility that interruptions in the supply
of gas may occur. It is unlikely that gas will be cut off to consumers, but increases in gas price
may occur as the market responds to curtailments on individual transmission pipelines.
Transmission and distribution operators could face additional costs to provide alternative supply
for some customers. RSPA/OPS believes that the rule has been revised so that the likelihood of
such interruptions has been reduced as much as practicable. This likelihood has probably not been
eliminated. RSPNOPS is unable to estimate the costs that may result from supply interruptions.
68

## Provenance

- Official: Yes
- Source: <https://downloads.regulations.gov/PHMSA-RSPA-2000-7666-0356/attachment_1.pdf>
- Source ID: `regulations-gov`
- SHA-256: `95ff656f453fa9c0ba22a49fd8887e6d2aca2706e39bbeb9488a0a4e1bc4d75e`
- Retrieved: 2026-08-20T02:22:46.679Z
- Exported: 2026-08-24T17:48:44.494Z
- Document slug: `regulations-gov-attachment-0900006480e8a887`

### Source metadata

```json
{
  "materialSubtype": "regulations_gov_agency_attachment",
  "parentDocumentId": "regulations-gov-document-phmsa-rspa-2000-7666-0356",
  "regulationsGovDocumentId": "PHMSA-RSPA-2000-7666-0356",
  "docketId": "PHMSA-RSPA-2000-7666",
  "attachmentId": "0900006480e8a887",
  "format": "pdf",
  "authorshipClass": "agency_authored",
  "rightsClass": "federal_work",
  "ingestionDecision": "ingest",
  "decisionBasis": [
    "organization:U.S. DOT/RSPA",
    "title:U.S. DOT/RSPA - Final Regulatory Evaluation - Pipeline Integrity Management in High Consequence Areas (Gas Transmission Pipelines)"
  ],
  "summaryEligibility": "eligible",
  "jurisdiction": "US"
}
```
