# U.S. DOT/PHMSA - Final Environmental Assessment of the Longhorn Pipeline Reversal - Volume 1 of 2: Chapters 1-6

**Citation:** 09000064811add8f  
**Type / status:** rulemaking / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** Not stated

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL VOLUME 1: CHAPTERS 1 - 6 PHMSA-2012-0175 December 2012 FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL 5.3.3.5 Process Hazard Analysis ....................................................... 5-37 5.3.3.6 Preventive and Mitigative Measures Analysis ........................ 5-38 5.3.4 CONTROL SYSTEMS (SCADA)...

## Document text

<<<PAGE 1>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE
LONGHORN PIPELINE REVERSAL
VOLUME 1: CHAPTERS 1 - 6
PHMSA-2012-0175
December 2012

<<<PAGE 2>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CONTENTS
1.0 INTRODUCTION .................................................................................................. 1-1
1.1 THE ENVIRONMENTAL ASSESSMENT PROCESS.......................................................... 1-1
1.2 PROJECT DESCRIPTION ............................................................................................ 1-1
1.3 ROLE OF FEDERAL AGENCIES ................................................................................... 1-2
1.4 ORGANIZATION OF THE FEA ..................................................................................... 1-3
2.0 PURPOSE AND NEED FOR THE PROPOSED PROJECT ................................ 2-1
2.1 PURPOSE ................................................................................................................. 2-1
2.2 NEED ....................................................................................................................... 2-1
3.0 DESCRIPTION OF PROPOSED PROJECT, CONNECTED ACTIONS,
AND ALTERNATIVES ......................................................................................... 3-1
3.1 DESCRIPTION OF THE PROPOSED PROJECT ............................................................... 3-1
3.1.1 PROJECT OVERVIEW ..................................................................................... 3-1
3.1.2 PROJECT DETAIL .......................................................................................... 3-2
3.2 CONNECTED ACTIONS .............................................................................................. 3-5
3.3 3.2.1 ORION EXPANSION ........................................................................................ 3-5
3.2.2 3.2.3 3.2.4 3.2.5 ODESSA TO CRANE ....................................................................................... 3-6
EL PASO GATEWAY ....................................................................................... 3-6
CRANE TO EL PASO ...................................................................................... 3-6
9TH STREET JUNCTION TO SPEED JUNCTION ................................................... 3-6
3.2.6 EAST HOUSTON TO HOLLAND AVENUE ........................................................... 3-6
OPERATION AND MAINTENANCE ................................................................................ 3-6
3.4 3.3.1 PROPOSED PROJECT .................................................................................... 3-6
3.3.2 CONNECTED ACTIONS ................................................................................... 3-8
ELIMINATION OF ALTERNATIVES FROM DETAILED CONSIDERATION ............................ 3-8
3.5 NO-ACTION ALTERNATIVE ........................................................................................ 3-9
4.0 AFFECTED ENVIRONMENT ............................................................................... 4-1
4.1 HUMAN RESOURCES AND LAND USES ....................................................................... 4-1
4.1.1 REGIONAL SETTING ...................................................................................... 4-1
4.1.1.1 4.1.1.2 4.1.1.3 Potentially Affected Communities ............................................ 4-2
Regional Land Uses ................................................................. 4-3
Regional Population Density .................................................... 4-4
4.1.1.3.1 Housing .............................................................. 4-4
4.1.1.3.2 Population .......................................................... 4-5
4.1.1.4 Transportation Networks .......................................................... 4-5
4.1.1.5 Parks and Natural Areas .......................................................... 4-5
4.1.2 OTHER RECEPTORS IN THE HOUSTON AND AUSTIN AREAS ............................. 4-6
4.1.2.1 Houston Area ........................................................................... 4-6
4.1.2.1.1 Special Use Areas ............................................. 4-6
4.1.2.2 Austin Area .............................................................................. 4-6
4.1.2.2.1 Special Use Areas ............................................. 4-7
I

<<<PAGE 3>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.2 PHYSICAL RESOURCES ............................................................................................. 4-7
4.2.1 GROUNDWATER RESOURCES ........................................................................ 4-7
4.2.1.1 Aquifers Traversed by the Zone of Potential Impact and
General Nature ........................................................................ 4-7
4.2.1.2 Relative Vulnerability of Aquifers within the Zone of
Potential Impact ....................................................................... 4-8
4.2.1.2.1 Relative Aquifer Vulnerability Evaluation
Methodologies .................................................... 4-8
4.2.1.2.2 Relative Aquifer Vulnerability Evaluation ......... 4-11
4.2.1.3 Potentially Vulnerable Public Water Supply (PWS) Water
Wells ...................................................................................... 4-22
4.2.1.4 Identification of Sensitive Groundwater Resource Areas ....... 4-24
4.2.2 SURFACE WATER ........................................................................................ 4-26
4.2.2.1 Description of Surface Water Resources ............................... 4-26
4.2.2.1.1 Description of Significant Stream
Crossings Along Route .................................... 4-27
4.2.2.1.2 Water Quality Downstream of Pipeline
Crossings ......................................................... 4-29
4.2.2.1.3 Identification of Downstream Water Users ....... 4-30
4.2.2.2 Surface Water Resources, Including Vulnerable Areas ......... 4-34
4.2.2.2.1 Data Sources ................................................... 4-34
4.2.2.2.2 Identification of Surface Water Vulnerability
to Spills ............................................................ 4-35
4.2.2.2.2.1 Spill Mobility ..................................................... 4-35
4.2.2.2.2.2 Ability to Contain and Remediate a Spill .......... 4-37
4.2.2.2.2.3 Relative Importance of Potentially
Impacted Surface Waters ................................ 4-37
4.2.2.2.3 Summary Ranking of Stream
Vulnerabilities ................................................... 4-38
4.2.2.3 Wetlands ................................................................................ 4-38
4.2.3 GEOLOGIC HAZARDS ................................................................................... 4-39
4.2.3.1 Earthquake/Seismic Hazards ................................................. 4-40
4.2.3.2 Landslide/Mass Movement Hazards ...................................... 4-40
4.2.3.3 Faulting/Subsidence Hazards ................................................ 4-40
4.2.3.4 Soil Stress Hazards ............................................................... 4-41
4.2.3.5 Scour at Stream Crossings .................................................... 4-41
4.2.4 CLIMATE AND AIR QUALITY .......................................................................... 4-41
4.2.4.1 Climate ................................................................................... 4-41
4.2.4.2 Air Quality .............................................................................. 4-42
4.3 ECOLOGICAL RESOURCES ...................................................................................... 4-44
4.3.1 TERRESTRIAL RESOURCES .......................................................................... 4-44
4.3.1.1 Terrestrial Fauna and Flora ................................................... 4-45
4.3.2 AQUATIC RESOURCES ................................................................................. 4-48
4.3.2.1 Aquatic Fauna and Flora ........................................................ 4-51
4.3.2.1.1 San Jacinto River Basin ................................... 4-52
II

<<<PAGE 4>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.3.2.1.2 4.3.2.1.3 Brazos River Basin .......................................... 4-53
Colorado River Basin ....................................... 4-53
4.3.3 THREATENED AND ENDANGERED SPECIES ................................................... 4-54
4.3.3.1 4.3.3.2 Protected Terrestrial Species ................................................. 4-55
Federally Protected Species .................................................. 4-56
4.3.3.2.1 State Protected Species .................................. 4-57
4.4 CULTURAL RESOURCES ......................................................................................... 4-59
4.4.1 PIPELINES................................................................................................ 4-59
4.4.1.1 Proposed Project (East Houston to Crane) ............................ 4-59
4.4.2 PUMP STATIONS ..................................................................................... 4-64
4.4.2.1 Buckhorn Station .................................................................... 4-64
4.4.2.2 Industry Station ...................................................................... 4-64
4.4.2.3 Warda Station ........................................................................ 4-64
4.4.2.4 Bastrop Station ...................................................................... 4-65
4.4.2.5 Eckert Station ......................................................................... 4-65
4.4.2.6 James River Station ............................................................... 4-65
4.4.2.7 Cartman Station ..................................................................... 4-66
4.4.2.8 Barnhart Station ..................................................................... 4-66
4.4.2.9 Texon Station ......................................................................... 4-66
4.4.2.10 East Houston Terminal .......................................................... 4-66
4.5 REFERENCES ......................................................................................................... 4-67
5.0 PIPELINE INTEGRITY ANALYSIS ...................................................................... 5-1
5.1 INTRODUCTION ......................................................................................................... 5-1
5.1.1 APPLICABLE REGULATIONS ........................................................................... 5-2
5.1.1.1 5.1.1.2 5.1.1.3 Pipeline Safety Regulations ..................................................... 5-3
Longhorn Mitigation Plan (LMP) .............................................. 5-3
National Oil and Hazardous Substance Pollution
Contingency Plan ..................................................................... 5-3
5.1.1.4 Spill Prevention, Control, and Countermeasures Plan
(SPCC) ..................................................................................... 5-4
5.1.1.5 Hazardous Waste Operations and Emergency Response
(HAZWOPER) .......................................................................... 5-4
5.1.1.6 Transportation Security Administration (TSA) Pipeline
Security .................................................................................... 5-4
5.1.2 INFORMATION ANALYZED ............................................................................... 5-4
5.1.2.1 Key Documents ........................................................................ 5-5
5.1.2.2 Databases ................................................................................ 5-6
5.2 CONSTRUCTION/EXISTING SYSTEM ........................................................................... 5-6
5.2.1 GENERAL ATTRIBUTES .................................................................................. 5-6
5.2.2 5.2.3 5.2.4 5.2.5 EFFECTS OF AGE .......................................................................................... 5-7
MANUFACTURING AND CONSTRUCTION METHODS .......................................... 5-8
COUNTERING AGE EFFECTS .......................................................................... 5-9
MAINTENANCE REPAIRS AND REHABILITATION ............................................. 5-10
5.2.6 FACILITIES .................................................................................................. 5-11
III

<<<PAGE 5>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.2.6.1 Tanks ..................................................................................... 5-11
5.2.6.1.1 External or In-Service Inspections ................... 5-11
5.2.6.1.2 Internal or Out-of-Service Inspection ............... 5-11
5.2.6.2 Pump Stations ........................................................................ 5-11
5.2.6.3 Mainline Block Valves ............................................................ 5-12
5.3 NORMAL OPERATIONS ............................................................................................ 5-13
5.3.1 THREATS .................................................................................................... 5-14
5.3.1.1 Commodity Characteristics .................................................... 5-14
5.3.1.2 Internal Corrosion .................................................................. 5-14
5.3.1.3 Hydrogen Blistering ................................................................ 5-15
5.3.1.4 Surge and Hydraulic Profile ................................................... 5-16
5.3.1.5 Cracking/Fatigue Monitoring .................................................. 5-18
5.3.1.6 Stress Corrosion Cracking (SCC) .......................................... 5-18
5.3.1.7 Incorrect Operations .............................................................. 5-19
5.3.1.8 Security .................................................................................. 5-19
5.3.1.9 Atmospheric Corrosion .......................................................... 5-19
5.3.1.10 External Corrosion ................................................................. 5-20
5.3.1.10.1 Pipe Coating. ................................................... 5-21
5.3.1.10.2 Cathodic Protection .......................................... 5-22
5.3.1.10.3 IR Drop (CP Voltage Measurement
Criteria) ............................................................ 5-23
5.3.1.10.4 Casings ............................................................ 5-24
5.3.1.10.5 Microbiologically Influenced Corrosion
(MIC) ................................................................ 5-25
5.3.1.10.6 AC Induced Corrosion. ..................................... 5-25
5.3.1.10.7 Stray Currents .................................................. 5-26
5.3.1.10.8 Selective Seam Corrosion ............................... 5-26
5.3.1.11 Third Party Damage ............................................................... 5-27
5.3.1.11.1 One Call ........................................................... 5-27
5.3.1.11.2 Public Education .............................................. 5-27
5.3.1.11.3 Excavator Education ........................................ 5-28
5.3.1.11.4 Depth of Cover and Exposed Pipe ................... 5-29
5.3.1.11.5 Pipeline Markers .............................................. 5-30
5.3.1.11.6 Pipeline Surveillance ........................................ 5-30
5.3.1.11.7 Encroachments and ROW Maintenance .......... 5-31
5.3.1.12 External Forces ...................................................................... 5-31
5.3.1.12.1 Flooding ........................................................... 5-32
5.3.1.12.2 Geohazards ..................................................... 5-32
5.3.1.12.3 Crossings ......................................................... 5-32
5.3.2 5.3.3 STAFFING AND TRAINING ............................................................................. 5-33
RISK ASSESSMENT PROCESSES .................................................................. 5-33
5.3.3.1 Operational Reliability Assessment (ORA) ............................ 5-34
5.3.3.2 Data Management ................................................................. 5-35
5.3.3.3 Pipeline Risk Assessment ...................................................... 5-36
5.3.3.4 Facility Risk Assessment ....................................................... 5-37
IV

<<<PAGE 6>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.3.5 Process Hazard Analysis ....................................................... 5-37
5.3.3.6 Preventive and Mitigative Measures Analysis ........................ 5-38
5.3.4 CONTROL SYSTEMS (SCADA) .................................................................... 5-38
5.3.4.1 Leak Detection ....................................................................... 5-39
5.3.4.2 Control Room Procedures ..................................................... 5-41
5.3.5 PIPELINE INSPECTION AND TESTING ............................................................ 5-41
5.3.5.1 Pressure Testing .................................................................... 5-42
5.3.5.2 In-Line Inspection (ILI) ........................................................... 5-43
5.3.5.2.1 ILI Findings ...................................................... 5-44
5.3.5.2.2 Follow-up Excavations ..................................... 5-46
5.3.5.3 Visual and NDE Inspections .................................................. 5-47
5.4 ACCIDENTAL RELEASES ......................................................................................... 5-47
5.4.1 LEAK ANALYSIS ........................................................................................... 5-47
5.4.1.1 Leak Causes .......................................................................... 5-47
5.4.1.2 Comparisons with Other Pipeline Leak Data ......................... 5-48
5.4.2 SPILL AND EMERGENCY RESPONSE PLAN .................................................... 5-48
5.4.2.1 Compliance with Regulations ................................................. 5-48
5.4.2.2 Sensitive Areas Response ..................................................... 5-50
5.4.2.3 Recent Emergency Response Experience ............................ 5-52
5.4.2.4 Trench Integrity Assessment – Edwards Aquifer
Recharge Zone ...................................................................... 5-52
5.4.3 CONSEQUENCE POTENTIAL (COF) ............................................................... 5-53
5.5 CONCLUSIONS ........................................................................................................ 5-54
5.6 REFERENCES ......................................................................................................... 5-54
6.0 PIPELINE RISK ASSESSMENT .......................................................................... 6-1
6.1 INTRODUCTION ......................................................................................................... 6-1
6.2 THREATS .................................................................................................................. 6-1
6.2.1.1 Internal Corrosion .................................................................... 6-2
6.2.1.2 Hydrogen Blistering .................................................................. 6-5
6.2.1.3 Surge and Hydraulic Profile ..................................................... 6-6
6.2.1.4 Cracking/ Fatigue Monitoring ................................................... 6-7
6.2.1.5 Stress Corrosion Cracking (SCC) ............................................ 6-8
6.2.1.6 Incorrect Operations ................................................................ 6-8
6.2.1.7 Security .................................................................................... 6-9
6.2.1.8 Atmospheric Corrosion .......................................................... 6-10
6.2.1.9 External Corrosion ................................................................. 6-10
6.2.1.9.1 Pipe Coatings ................................................... 6-11
6.2.1.9.2 Cathodic Protection and CP Verifications ........ 6-11
6.2.1.9.3 IR Drop (CP Voltage Measurement
Criteria) ............................................................ 6-12
6.2.1.9.4 Casings ............................................................ 6-13
6.2.1.9.5 Microbiological Influenced Corrosion (MIC) ..... 6-13
6.2.1.9.6 AC Induced Corrosion ...................................... 6-14
6.2.1.9.7 Stray Currents .................................................. 6-14
V

<<<PAGE 7>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
6.2.1.9.8 Selective Seam Corrosion (SSC) ..................... 6-15
6.2.1.10 Third Party Damage ............................................................... 6-15
6.2.1.10.1 One Call ........................................................... 6-16
6.2.1.10.2 Public Education .............................................. 6-16
6.2.1.10.3 Excavator Education ........................................ 6-17
6.2.1.10.4 Depth of Cover and Exposed Pipe ................... 6-18
6.2.1.10.5 Pipeline Markers .............................................. 6-18
6.2.1.10.6 Pipeline Surveillance ........................................ 6-19
6.2.1.10.7 Encroachments and ROW Maintenance .......... 6-19
6.2.1.11 External Forces ...................................................................... 6-20
6.2.1.11.1 Flooding ........................................................... 6-20
6.2.1.11.2 Geohazards ..................................................... 6-21
6.2.1.11.3 Crossings ......................................................... 6-21
6.2.2 6.2.3 STAFFING AND TRAINING ............................................................................. 6-21
RISK ASSESSMENT PROCESSES .................................................................. 6-21
6.2.3.1 ORA ....................................................................................... 6-21
6.2.3.2 Data Management ................................................................. 6-22
6.2.3.3 Pipeline Risk Assessment ...................................................... 6-22
6.2.3.4 Facility Risk Assessment ....................................................... 6-22
6.2.3.5 PHA/LOPA ............................................................................. 6-23
6.2.4 CONTROL SYSTEMS (SCADA) .................................................................... 6-23
6.2.4.1 Leak Detection ....................................................................... 6-23
6.2.4.2 Control Room Procedures ..................................................... 6-24
6.2.5 PIPELINE INSPECTION AND TESTING ............................................................ 6-24
6.2.5.1 Pressure Testing .................................................................... 6-24
6.2.5.2 In-Line Inspections (ILI) ......................................................... 6-25
6.2.6 SPILL AND EMERGENCY RESPONSE PLANS .................................................. 6-25
6.2.7 WORST CASE SPILL VOLUME ...................................................................... 6-25
6.3 CONSEQUENCE POTENTIAL (COF) .......................................................................... 6-26
6.4 CONCLUSIONS ........................................................................................................ 6-27
6.5 REFERENCES ......................................................................................................... 6-27
VI

<<<PAGE 8>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
TABLES
Table 4.1.1-1 Apartment Facilities within the Zone of Potential Impact of Proposed
Project
Table 4.1.1-2 Population within the Zone of Potential Impact of Proposed Project by MP
Segment
Table 4.1.2-1 Vulnerable Receptors within the Zone of Potential Impact of the Proposed
Project in the Houston Area
Table 4.1.2-2 Vulnerable Receptors within the Zone of Potential Impact of the Proposed
Project in the Austin Area
Table 4.2.1-1 Table 4.2.1-2 Aquifers Within the Zone of Potential Impact of the Proposed Project
TCEQ Aquifer Average DRASTIC Index and Vulnerability Ranking of
Aquifers within the Zone of Potential Impact of the Proposed Project
Table 4.2.1-3 Pettyjohn et. al. Aquifer Classification and Vulnerability of Aquifers Within
the Zone of Potential Impact of the Proposed Project
Table 4.2.1-4 Table 4.2.1-5 Table 4.2.2-1 Groundwater Resource Area Sensitivity Ranking
Public Water Supply Wells Within the Zone of Potential Impact
Summary of Chemical Analyses on Surface Water Samples from
STORET Stations Within the Zone of Potential Impact of the Proposed
Project
Table 4.2.2-2 Summary of 2008 Texas 303(d) Stream Segments Within the Zone of
Potential Impact of the Proposed Project
Table 4.2.2-3 Distances from Stream Crossings to Downstream Water Rights Within the
Zone of Potential Impact of the Proposed Project
Table 4.2.2-4 Table 4.2.2-5 Table 4.2.2-6 Ranking of Stream Crossings in Terms of Spill Transport Potential
Ranking of Stream Crossings in Terms of Spill Control Potential
Ranking of Stream Crossings in Terms of Downstream Resource
Importance as a Water Supply
Table 4.2.2-7 Table 4.2.2-8 Summary of Vulnerability Rankings, Surface Water Crossings
Wetlands Inventory for Proposed Project from East Houston/9th Street
Junction to Crane
Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the
Zone of Potential Impact of the Proposed Project1
Table 5.1.1-1 Compliance Audit Findings
Table 5.2.1-1a Pipe Characteristics
Table 5.2.1-1b Pipe Characteristics Detail by Manufacturer
Table 5.2.1-1c Pipe Characteristics Detail by Coating Type
Table 5.2.1-2 Overview of Pipeline Construction Specifications
Table 5.2.6-1 Valve Locations and Types for the Longhorn Pipeline
Table 5.2.6-2 Locations of Check Valves Installed per LCRA Settlement and Valve
Studies
Table 5.2.6-3 Estimated Maximum Release Volumes
Table 5.3.1-1 ILI Tool Runs
Table 5.3.1-2 ILI Features Summary
Table 5.3.1-3 Pressure-Cycle-Induced Fatigue Cracking Analysis from the 2010 ORA
for the Current Westward Product Flow Direction
VII

<<<PAGE 9>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Table 5.3.1-4 Table 5.3.4-1 Table 5.3.4-1a Table 5.3.5-1 Table 5.3.5-2 Table 5.3.5-3 Table 5.3.5-4 Table 5.4.1-1 Table 5.4.1-2 Table 5.4.1-3 Table 5.4.1-4 Table 5.4.1-5 Table 5.4.1-6 Test Point Exceptions for 2011
Alarm and Shutdown Devices
Leak Detection System Alarm and Response Table
Basic Inspection and Test Methods
Summary of Hydrostatic Tests
Summary of Hydrostatic Tests (2005 to 2011)
Summary of ILI Repair Criteria
Pipeline and Facility Spill Data Since 2002
Summary of Cause of Release for Facilities
Summary of Cause of Release for Pipeline (Not Facilities)
Texas Reportable Incidents and Frequencies
US Reportable Incidents and Frequencies
Longhorn Reportable Incident Frequencies
VIII

<<<PAGE 10>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
FIGURES
Figure 3.1-1 Project Location of Longhorn Pipeline
Figure 3.2-1a Project Location of Connected Actions
Figure 3.2-1b Project Location of Connected Actions
Figure 4.1.2-1a Houston Area Land Use and Housing Density
Figure 4.1.2-1b Houston Area Land Use and Housing Density
Figure 4.1.2-1c Houston Area Land Use and Housing Density
Figure 4.1.2-1d Houston Area Land Use and Housing Density
Figure 4.1.2-1e Houston Area Land Use and Housing Density
Figure 4.1.2-1f Houston Area Land Use and Housing Density
Figure 4.1.2-1g Houston Area Land Use and Housing Density
Figure 4.1.2-1h Houston Area Land Use and Housing Density
Figure 4.1.2-1i Houston Area Land Use and Housing Density
Figure 4.1.2-2a Austin Area Land Use and Housing Density
Figure 4.1.2-2b Austin Area Land Use and Housing Density
Figure 4.1.2-2c Austin Area Land Use and Housing Density
Figure 4.1.2-2d Austin Area Land Use and Housing Density
Figure 4.1.2-2e Austin Area Land Use and Housing Density
Figure 4.1.2-2f Austin Area Land Use and Housing Density
Figure 4.1.2-2g Austin Area Land Use and Housing Density
Figure 4.2.1-1 Major Aquifers
Figure 4.2.1-2 Minor Aquifers
Figure 4.2.1-3a Public Water Supply Wells within Zone of Impact
Figure 4.2.1-3b Public Water Supply Wells within Zone of Impact
Figure 4.2.1-3c Public Water Supply Wells within Zone of Impact
Figure 4.2.1-3d Public Water Supply Wells within Zone of Impact
Figure 4.2.2-1 Hydrography with Surface Water Rights per TCEQ Database
Figure 4.2.2-2 Hydrography with STORET Stations
Figure 4.2.2-3 Houston Area TMDLs
Figure 4.2.2-4 Satsuma Area TMDLs
Figure 4.2.2-5 Austin Area TMDLs
Figure 4.2.2-6 Pedernales Falls State Park API
Figure 4.2.2-7 Pipeline Crossings within Pedernales State Park API
Figure 4.2.2-8 Surface Water Vulnerability Methodology Flow Chart
Figure 4.3.1-1 ECO Regions
IX

<<<PAGE 11>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDICES
Appendix 3 SIP Overview
Appendix 4A Highway and Railroad Crossings
Appendix 4B Biological Assessment
Appendix 4C Programmatic Agreement
Appendix 4D SHPO Concurrence Letter
Appendix 5A Referenced Procedures of the 2012 Magellan SIP
Appendix 5B Valve Schematic
Appendix 5C Trench Integrity and Construction Methodology of the Magellan Longhorn
Pipeline from Mile Post 169.88 to 188.8
Appendix 5D Trench Integrity Inspection Report of the Magellan Longhorn Pipeline
from Mile Post 169.88 to 173.38
Appendix 6A Risk Assessment Methodology
Appendix 6B Crude Oil Specifications
Appendix 6C EnhanceCo. Report
Appendix 6D Drag Reducing Agent Material Safety Data Sheet
Appendix 6E Referenced Procedures of the 2012 Magellan SIP
Appendix 6F Surge Analysis Summary
Appendix 6G Risk Implication Matrix
Appendix 6H Spartan Engineering Report
X

<<<PAGE 12>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
ACRONYMS
µm Micrometers
AAQS Ambient Air Quality Standards
ACHP Advisory Council on Historic Preservation
AHPA archeological high probability area
APE area of potential effect
API Area of Primary Influence
BA Biological Assessment
BEG Bureau of Economic Geology
BFZ Balcones Fault Zone
BG Block Group
bgl below ground level
BLM Bureau of Land Management
BMP best management practices
BO Biological Opinion
bpd barrels per day
BSEACD Barton Springs/Edwards Aquifer Conservation District
CDC Center for Disease Control
CDP census designated place
CEQ Council on Environmental Quality
CFR Code of Federal Regulations
CO carbon monoxide
CO2 carbon dioxide
COA City of Austin
CoF Consequence of Potential
CP Cathodic Protection
CPM Computational Pipeline Monitoring
CT census tract
DEM Digital Elevation Model
DOC depth of cover
DOI Department of Interior
DOT US Department of Transportation
DRASTIC EPA Methodology Standardized System used for evaluating
groundwater
EA Environmental Assessment
EFRD emergency flow reduction devices
EGP Electronic geometry pig
EIS Environmental Impact Statement
EJ Environmental Justice
EO Executive Order
EPA US Environmental Protection Agency
ESA Endangered Species Act
ESL Effects Screening Level
XXX

<<<PAGE 13>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
FBE fusion bonded epoxy
FEA Final Environmental Assessment
FM Farm-to-Market
FR Federal Register
FRP Facility Response Plan
ft2/d feet squared per day
USFWS U.S. Fish and Wildlife Service
GAM Groundwater Availability Modeling
GHG greenhouse gas
GIS Geographic Information System
GLO General Land Office
gpm gallons per minute
GW groundwater
H2S hydrogen sulfide
HAP hazardous air pollutant
HAZWOPER Hazardous Waste Operations and Emergency Response
HC Hill Country
HCA High Consequence Area
HCFCD Harris County Flood Control District
HHS Department of Health and Human Services
HIC hydrogen induced cracking
IH Interstate Highway
ILI in-line inspection
IMP Integrated Management Plan
IP implementation plan
LAER lowest achievable emission rate
LCRA Lower Colorado River Authority
LDAR leak detection and repair
LMC Longhorn Mitigation Commitment
LMP Longhorn Mitigation Plan
LOPA layer of protection analysis
LST Localized Significance Thresholds
MASP maximum allowable surge pressure
MCL maximum contaminant level
mg/l milligrams per liter
MIC microbiological influenced corrosion
MOCR Management of Change Request
MP milepost
MS4 municipal separate storm sewer systems (MS4s)
MSL mean sea level
MTBE Methyl Tertiary Butyl Ether
MUD Municipality Utility District
NAAQS National Ambient Air Quality Standards
NACE National Association of Corrosion Engineers
XXXI

<<<PAGE 14>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
NAIP National Agricultural Inventory Program
NDE non-destructive examination
NEIC National Enforcement Investigations Center
NEPA National Environmental Policy Act
NFPA National Fire Protection Agency
NHD National Hydrography Dataset
NHPA National Historic Preservation Act
NLCD National Land Cover Database
NNSR nonattainment new source review
NO2 nitrogen dioxide
NOx oxides of nitrogen
NPDES National Pollutant Discharge Elimination System
NPMS National Pipeline Mapping System
NPS National Park Service
NRCS Natural Resources Conservation Service
NRHP National Register of Historic Places
NWI National Wetland Inventory
O3 ozone
OPS Office of Pipeline Safety
ORA Operational Reliability Assessment
OSHA Occupational Health and Safety Administration
PA Programmatic Agreement
Pb lead
PGA peak ground acceleration
PHA Process Hazard Analysis
PHMSA Pipeline and Hazardous Materials Safety Administration
PLDS pipeline leak detection system
POE probability of exceedance
PoF probability of failure
PM particulate matter
PM10 particulate matter with a diameter of 10 micrometers (um) or less
PM2.5 particulate matter with a diameter of 2.5 micrometers (um) or less
ppb parts per billion
PWS Public Water System
QRA quantitative risk assessment
REMM Riparian Emergency Management Model
ROW right-of-way
RRC Texas Railroad Commission
RSPA Research and Special Programs Administration
SCADA Supervisory Control and Data Acquisition Systems
SCAQMD South Coast Air Quality Management District
SCC stress corrosion cracking
SDWA Safe Drinking Water Act
SHPO State Historic Preservation Officer
XXXII

<<<PAGE 15>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
SIP System Integrity Plan
SO2 sulfur dioxide
SO4 Sulfates
SPCC spill prevention, control, and countermeasure
SSESR Site Specific Environmental Study Report
STORET EPA database
SWSA Source Water Susceptibility Assessment
T&E threatened and endangered
TAS Turpin & Sons, Inc.
TCEQ Texas Commission on Environmental Quality
TDS total dissolved solids
TEA Texas Education Agency
THC Texas Historical Commission
THPO Tribal Historic Preservation Officer
TMDL Total Maximum Daily Load
TNRIS Texas Natural Resources Information System
TPDES Texas Pollutant Discharge Elimination System
TPWD Texas Parks and Wildlife Department
TWDB Texas Water Development Board
TxDOT Texas Department of Transportation
TXNDD Texas Natural Diversity Database
USACE United States Army Corp of Engineers
USC United States Code
USGS United States Geologic Survey
UT University of Texas
UTPB University of Texas Permian Basin
VOC volatile organic compounds
WCID Water Control and Improvement District
WPP watershed protection plans
WSD water supply district
XXXIII

<<<PAGE 16>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
1.0 INTRODUCTION
1.1 THE ENVIRONMENTAL ASSESSMENT PROCESS
The Pipeline and Hazardous Safety Administration (PHMSA) has prepared this final
environmental assessment (FEA) in accordance with the National Environmental Policy Act
(NEPA) (42 USC §§ 4321–4347) and the Council on Environmental Quality’s (CEQ) NEPA
Implementing Regulations (40 CFR Parts 1500–1508). NEPA provides a framework to evaluate
a proposed project or “Federal action” and the potential of that action to have significant effects
the human environment. The NEPA process helps the decision maker and the public
understand and evaluate the potential environmental impacts of a proposed action prior to an
agency’s final decision on the proposal. Another goal of NEPA is to facilitate public involvement.
Therefore, PHMSA prepared a draft FEA and sought comments from interested members of the
public. This FEA reflects changes in responses to these comments. Additionally, a list of the
comment’s and PHMSA’s responses are posted in the docket at regulations.gov, docket
“PHMSA-2012-0175.”
1.2 PROJECT DESCRIPTION
The existing Longhorn Pipeline runs from El Paso, Texas to Houston, Texas and is owned and
operated by Magellan Pipeline Company, L.P (Magellan). The Longhorn Pipeline currently
transports refined petroleum products east to west, from Houston to El Paso. The proposed
project would convert a segment of the Longhorn Pipeline from Crane, Texas to East Houston,
Texas to crude oil service and reverse the flow, so that crude oil would flow west to east, from
Crane to Houston. Longhorn would continue to transport refined products east to west, from
Crane to El Paso, by connecting to the existing Orion West Pipeline that is located to the north
of the Longhorn Pipeline and runs from Frost, Texas to El Paso, Texas. In the proposed
project, refined products would flow from the Orion West Pipeline to the Longhorn Pipeline via
an existing pipeline segment from Odessa, Texas to Crane, Texas. The refined products would
then enter the Longhorn Pipeline at Crane and flow west to El Paso.
The Longhorn Pipeline System’s current operations are subject to the Longhorn Mitigation Plan
(LMP). A summary of the Longhorn Mitigation Commitments is provided in Appendix 9A of this
document. The LMP was developed following litigation regarding a reversal that took place in
2005. At that time, the Longhorn Pipeline transported crude oil west to east, and the proposed
action was to reverse the flow to transport refined petroleum. As part of the LMP, the Research
and Special Programs Administration (RSPA)1 and the U.S. Environmental Protection Agency
(EPA), Region 6 agreed to conduct an “Enhanced EA”, (1999 EA) for that project. RSPA and
EPA Region 6 issued a joint finding of no significant impact (FONSI) on November 3, 2000. The
1 At the time of the litigation, PHMSA was the Research and Special Programs Administration.
1-1

<<<PAGE 17>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
1999 EA and the FONSI documents are available of the EPA Region 6 website at
http://www.epa.gov/region6/6en/xp/longhorn.htm.
Although PHMSA does not normally serve as a lead agency for pipeline construction projects
because it has no authority over pipeline siting, the LMP includes a provision for NEPA
adherence for some future construction activities. Therefore, PHMSA has prepared this FEA for
the proposed changes to the pipeline. Although this EA is independent of the 1999 EA, PHMSA
incorporates applicable sections within the 1999 EA by reference to avoid repetitive discussions
and focus on pertinent issues for discussion (40 CFR 1502.21).
Like the 1999 EA, an environmental contractor helped prepare this FEA by assisting with the
technical analyses and preparing drafts of the FEA. PHMSA approved the hiring of Zephyr
Environmental Corporation (hereinafter, Contractor), which is based in Austin, Texas, to prepare
drafts of this FEA. Magellan funded the technical analyses performed by the Contractor. This
arrangement puts the cost burden on the project proponent while ensuring that the study
direction and decision-making is solely in the control of the Federal Government.
1.3 ROLE OF FEDERAL AGENCIES
PHMSA is responsible for regulating the transportation of hazardous liquids via pipeline
pursuant to the Pipeline Safety Laws, 49 USC § 60101 et seq. PHMSA has promulgated and
enforces the Pipeline Safety Regulations that dictate requirements for construction, design,
testing, operation, and maintenance of hazardous liquid (including crude oil, petroleum
products, and anhydrous ammonia) pipelines. 49 CFR Parts 190, 195, and 199. PHMSA does
not typically serve as lead agency for pipeline construction projects, as it has no authority over
pipeline siting and does not issue any approval or authorization to commence a pipeline
construction project.
Under the Clean Water Act (CWA), as amended by the Oil Pollution Act, PHMSA has
responsibility for review and approval of oil spill response plans for transportation-related
onshore pipeline facilities. The CWA and PHMSA’s oil spill response plan regulations dictate
the criteria required for approval of spill response plans. 33 USC §§ 1231, 1321; 49 CFR Part
194.
EPA, Region 6 served as co-lead agency for the 1999 EA. On January 31, 2011, PHMSA
invited EPA, Region 6 to serve as a cooperating agency, and EPA accepted on February 10,
2011.
The Proposed Project is not federally owned, operated, or funded. It is a private undertaking
initiated by Magellan. Neither PHMSA nor EPA has the statutory authority to grant overall
project approval or to determine the routing or placement of pipelines. The final agency action
in this matter will be the issuance of a Finding of No Significant Impact (FONSI).
1-2

<<<PAGE 18>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
1.4 ORGANIZATION OF THE FEA
The body of this FEA includes Chapters 1 through 9 that are written to be consistent with the
structure of the 1999 EA in order to facilitate comparison of the two documents. Each chapter in
this EA references applicable information from the 1999 EA, provides updated or new
information where applicable, and summarizes information as appropriate. A tenth chapter has
been added to include a thorough evaluation of Connected Actions to the Proposed Project
(Connected Actions). Chapter 11 has been added to evaluate cumulative impacts that may
result from the Proposed Project and Connected Actions and other substantial projects. The
contents of these chapters are described below:
• Chapter 1 - Introduction: This chapter of the FEA provides a brief description of the
environmental process, references the 1999 EA, describes the roles of the lead agency,
and describes the organization of this FEA.
• Chapter 2 - Purpose and Need for the Proposed Project: This chapter describes the
purpose and the underlying needs for the currently proposed project.
• Chapter 3 - Description of the Proposed Project and Alternatives: This chapter
describes the proposed features of the project and the alternatives. It identifies the route,
operation and maintenance, control systems, and the construction of Connected Actions.
• Chapter 4 - Affected Environment: This chapter describes the existing environment for
each component of the Proposed Project. Reference is made to pertinent information
provided in the 1999 EA, providing summary of information, updated information, and
new information as necessary. This chapter focuses on those resources that are
considered sensitive from both public safety and environmental impact criteria.
• Chapter 5 - Pipeline Integrity Analysis: This chapter discusses the integrity of the
existing pipeline system.
• Chapter 6 - Overall Pipeline Risk Assessment: This chapter is a probabilistic risk
assessment of the integrity for the entire Longhorn Pipeline with greater emphasis on
those areas deemed sensitive. This risk assessment seeks to identify the probability and
magnitude of product releases along the pipeline.
• Chapter 7 - Potential Impacts Analysis: For the Longhorn portion of the project, Chapter
7 draws from Chapter 6 to describe how potential releases could affect human safety,
water quality, wildlife, and other environmental assessment categories. Potential
impacts to relevant resources are provided for all components of the project.
• Chapter 8 - Environmental Justice: This chapter describes whether the impacts
described in Chapter 7 disproportionately affect minority and low-income populations.
1-3

<<<PAGE 19>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Chapter 9 - Analysis of Mitigation: This chapter identifies and provides analyses of
mitigation activities for the Proposed Project.
• Chapter 10 - Connected Actions: This chapter describes the existing environment and
potential impacts analysis for each of the Connected Actions of the Proposed Project.
Like Chapter 4, this chapter focuses on those resources that are considered sensitive
from both public safety and environmental impact criteria. It will also describe an
assessment of risk as conducted within the current Integrated Management Plan (IMP).
This information will be used to describe how potential releases could affect human
safety, water quality, wildlife, and other environmental assessment categories consistent
with NEPA review. Potential impacts to relevant resources are provided for all
components of the Connected Actions.
• Chapter 11 – Cumulative Impacts: This chapter describes potential cumulative impacts
resulting from the Proposed Project and associated Connected Actions with the impacts
of substantial projects within the zone of potential impact that have occurred in the past,
are currently occurring, or are proposed for the reasonably foreseeable future. The
evaluation focuses on resources potentially affected by the proposed project and uses
information publicly available for other projects noting effects on the same resources.
1-4

<<<PAGE 20>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
2.0 PURPOSE AND NEED FOR THE PROPOSED PROJECT
2.1 PURPOSE
The purpose of the Proposed Project is to allow West Texas crude oil and Eagle Ford shale
production to be transported to Houston area refineries. The Connected Actions will expand
access to the Proposed Project for transport of West Texas crude oil to Houston while allowing
continued supply of refined petroleum products to El Paso, Texas.
2.2 NEED
The Proposed Project would address the underlying need for West Texas and Eagle Ford shale
crudes to be transported to Houston area refineries. Crude supply patterns are changing due to
increased production in the West Texas area, oversupply of crude in Cushing, Oklahoma, and a
relatively new crude and natural gas play in the Eagle Ford shale area.
Permian Basin (West Texas) has shown steady increases in crude production primarily due to
enhanced oil recovery techniques and this trend is projected to continue. The oversupply in
Cushing, Oklahoma (where the majority of West Texas production moves today) was primarily
caused by a new large diameter pipeline constructed from Canada into Cushing which has
created an oversupply of crude for the mid-continent market. This oversupply has or will result in
crude production to be stranded or pricing discounts for West Texas crude to move to this
distribution hub. West Texas crude needs another outlet for their production, with Houston area
refineries being the logical choice.
The Eagle Ford shale area is evolving, but geographically the Longhorn Pipeline is a logical
pipeline outlet for some of this crude production. In addition, there continues to be a need for
Gulf Coast refined petroleum products to supply the El Paso, Texas; Juarez, Mexico;
Albuquerque, New Mexico, and Arizona markets. These dynamics both for crude and refined
products distribution have created the underlying basis for the Proposed Project and the
Connected Actions.
2-1

<<<PAGE 21>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
3.0 DESCRIPTION OF PROPOSED PROJECT, CONNECTED ACTIONS,
AND ALTERNATIVES
This chapter provides a detailed description of the Proposed Project, Connected Actions, and
Alternatives, including the No-Action Alternative.
3.1 DESCRIPTION OF THE PROPOSED PROJECT
3.1.1 Project Overview
The Proposed Project will convert segments of Magellan’s existing Longhorn Pipeline (from
Crane, Texas to Houston, Texas) into a crude oil pipeline and reverse the current flow to
transport West Texas and Eagle Ford crude production to the U.S. Gulf Coast at Houston. The
Proposed Project will require constructing and modifying infrastructure, but will not require
constructing any new pipeline segments.
The Proposed Project is defined as the existing pipeline and associated infrastructure
requirements beginning at Crane, Texas and ending nine miles south of the existing East
Houston Terminal (i.e. 9th Street Junction) (see Figure 3.1-1). The route generally goes east-
southeast across parts of 18 counties.
The Proposed Project will have an initial capacity of 134,000 barrels per day (bpd) of crude oil
with the potential capacity to expand to 225,000 bpd. New pump stations are proposed to be
constructed as capacity requirements are needed along the pipeline at Texon, Barnhart,
Cartman, James River, Eckert, Bastrop, Warda, Industry, and Buckhorn Stations along with
reversing the existing pump stations at Crane, Kimble County, Cedar Valley, and Satsuma
Stations. New crude oil tanks (three 250,000-barrel tanks) and a truck unloading facility are
proposed to be constructed at Crane Station. New crude oil tanks (six 250,000-barrel tanks),
along with additional pumping capacity are also proposed to be constructed at East Houston
Terminal. Magellan proposes to construct new infrastructure (metering stations, manifolds, etc.)
at Crane, Texon, Barnhart, Bastrop, Warda, and Industry with the existing metering at East
Houston Terminal reversed. The Proposed Project also anticipates conversion of existing check
valves to emergency flow reduction devices (EFRD), potential replacement of existing mainline
gate valves as needed, engineering reviews of surge pressure, leak modeling and detection,
facility response plan and public education updates, along with other modifications necessary to
comply with the LMP.
All assets currently subject to the LMP will continue to be subject to the LMP. In other words,
Magellan will continue to operate the existing pipeline assets and infrastructure that are part of
the Proposed Project and subject to the LMP under the LMP. The Longhorn Pipeline segment
remaining in refined products service (from Crane to El Paso and Odessa to Crane) will
continue to be operated under the LMP.
3-1

<<<PAGE 22>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
3.1.2 Project Detail
The Proposed Project will be conducted in two separate phases. Phase I will facilitate the
reversal in flow direction, and Phase II will facilitate the expansion to a capacity of 225,000 bpd.
The following section provides a brief itemized list of infrastructure improvements and
construction needed in each phase.
Phase I: The Longhorn Pipeline will be reversed from Crane to East Houston by modifying the
piping at existing pump stations (Kimble County, Cedar Valley, Satsuma) along with adding a
pump unit at the existing Crane station. Hydraulic analysis indicates that the maximum flow rate
for the pipeline will be 134,000 bpd based upon the viscosity, gravity, and drag reducing agent
(DRA) injection rate of the crude that will be transported.
Crane Station:
• A mainline unit consisting of pump and motor associated with boosting the
product down the pipeline will be installed at Crane Station.
• Drag Reducing Agent (DRA) will be installed downstream of the mainline unit.
• A new meter station will be constructed to provide supervisory measurement
for Crane to East Houston operations.
• Three 50,000-bbl tanks currently in refined product service will be converted
to crude service and three 250,000-bbl crude tanks will be constructed.
• Tank lines to the unit suction manifold and metering will be installed.
• A connection for third party facilities consisting of manifold and metering will
be installed.
• A crude unloading system to unload crude tank trucks into tankage will be
installed.
• A corrosion inhibitor injection system will be installed.
Kimble Station:
• The existing Kimble County Station will be re-piped to pump from Crane to
East Houston.
• DRA will be installed downstream of the mainline unit.
• A pressure reducing valve will be installed to control static head pressure
resulting from elevation changes.
Cedar Valley Station:
• The existing Cedar Valley Station will be re-piped to pump from Crane to East
Houston.
• DRA will be installed downstream of the mainline unit.
• A pressure reducing valve will be installed to control static head pressure
resulting from elevation changes.
Bastrop Junction:
• A pressure reducing valve will be installed to control static head pressure
resulting from elevation changes.
• DRA will be installed downstream of the pressure reducing valve.
3-2

<<<PAGE 23>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Satsuma Station:
• The existing mainline unit at Satsuma will be taken out of service and re-
piped to allow crude oil to flow to East Houston.
• DRA will be installed downstream of the mainline unit.
• A pressure reducing valve will be installed to control static head pressure
resulting from elevation changes.
Ft. McKavett, Warda, and Eckert Trap Sites:
• Scraper traps will be reversed.
East Houston:
• Metering system will be reversed.
• Six 250,000-bbl tanks for crude with tank pumps will be constructed.
• Tank lines from crude manifold to tank will be installed.
• Crude manifold for new crude tanks will be expanded.
• Line from Longhorn incoming manifold to crude manifold will be constructed.
• Line from Crude manifold to outgoing pipelines will be constructed.
Check Valve Replacement:
• Emergency flow check valves at 27 sites with motor operated gate valves will
be replaced.
• Power and SCADA connection will be provided.
Pipeline Integrity:
• Pipeline repairs based upon new hydraulic surge analysis will be performed.
Line Displacement:
• Refined petroleum product will be displaced with nitrogen then the pipeline
will be filled with crude oil.
Phase II: The Crane to East Houston pipeline will be expanded to a capacity of 225,000 bpd.
This will be accomplished by installing larger mainline units at existing pump stations plus
addition of intermediate pump stations along the pipeline.
Crane Station:
• Two mainline units will be installed at existing station.
Texon Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
• A connection to third party facilities consisting of manifold and metering will
be installed.
• A corrosion inhibitor injection system will be installed.
3-3

<<<PAGE 24>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Barnhart Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
• A connection to third party facilities consisting of manifold and metering will
be installed.
• A corrosion inhibitor injection system will be installed.
Cartman Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
Kimble Station:
• Two mainline units will be installed at existing station.
James River Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
Eckert Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
Cedar Valley Station:
• Two mainline units at existing station will be installed.
Bastrop Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
• A connection to third party facilities consisting of manifold and metering will
be installed.
• A corrosion inhibitor injection system will be installed.
Warda Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
• A connection to third party facilities consisting of manifold and metering will
be installed.
• A corrosion inhibitor injection system will be installed.
3-4

<<<PAGE 25>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Industry Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
• A connection to third party facilities consisting of manifold and metering will
be installed.
• A corrosion inhibitor injection system will be installed.
Buckhorn Station:
• A new intermediate pump station consisting of two mainline units will be
constructed.
• DRA will be installed downstream of the mainline units.
Satsuma Station:
• Two mainline units will be installed at existing station.
East Houston:
• Mainline units will be installed at East Houston to pump crude south to Speed
Junction will be installed.
• Outbound metering for flow-rate and operating pressure will be revised.
• Manifold to connect crude tanks to mainline units will be constructed.
East Houston to Speed Junction:
• 20” pipeline from East Houston to 9th Street Junction will be hydro-tested to
establish higher MOP.
• A 2.5 mile, 20” pipeline from 9th Street Junction to Speed Junction will be
constructed.
3.2 CONNECTED ACTIONS
Connected Actions are those that are “closely related” to the Proposed Project. Connected
Actions are interdependent parts of a larger action and depend on the larger action for their
justification. Although these projects would not necessarily require a NEPA review, they are
dependent on the Proposed Project and are therefore included in the scope of this FEA. See 40
CFR §1508.25. Figures 3.2-1a and 1b show the Connected Actions.
3.2.1 Orion Expansion
The Orion West Pipeline expansion will consist of an increase in pipeline throughput capacity
and storage capacity, and equipment upgrades. The increase in pipeline throughput capacity
will be provided by the addition of two new pump stations located at DeLeon and Iatan. Storage
capacity for refined product at the existing Frost Terminal will be expanded to include one
250,000-barrel tank, one 200,000-barrel tank, and one 125,000-barrel tank. Refined petroleum
storage capacity at the East Houston Terminal will be expanded to include four 150,000-barrel
tanks and additional pumping capacity. Additional expansion includes infrastructure upgrades at
existing facilities at Frost, Walnut Springs (including DRA facilities), Clyde, Midland, and Odessa
3-5

<<<PAGE 26>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Terminal. The addition of the two facilities and existing infrastructure upgrades will increase
pump rates from approximately 72,000 bpd to approximately 110,000 bpd along this pipeline
system.
3.2.2 Odessa to Crane
The Orion West Pipeline expansion will include an existing 8-inch refined product pipeline that
extends approximately 29 miles from the Odessa Terminal to the Crane Station. The pipeline
will continue to be in refined petroleum service, but the flow reversed and a mainline pumping
unit (including DRA) added at Odessa.
3.2.3 El Paso Gateway
This Connected Action includes a new 6-inch pipeline (approximately 6 miles) from the
Longhorn El Paso Terminal to the proposed El Paso Gateway. The proposed activity will allow
continued supply of refined product to a local refinery and includes the addition of a pump unit
and meter station at the Longhorn El Paso Terminal.
3.2.4 Crane to El Paso
This Connected Action includes an existing segment of the Longhorn Pipeline from Crane to El
Paso that will increase pipeline capacity throughput from approximately 72,000 bpd to
approximately 110,000 bpd. This segment will require a new pump station at Cottonwood
Station, new pump units at the existing Crane Station, and upgraded metering at the El Paso
Terminal.
3.2.5 9th Street Junction to Speed Junction
This Connected Action is the construction of a 20-inch crude oil pipeline from the existing 9th
Street Junction to Speed Junction (approximately 2.8 miles). This segment will allow crude oil to
be further distributed in the Houston area.
3.2.6 East Houston to Holland Avenue
This Connected Action is the construction of an 8-inch refined product pipeline from the existing
East Houston Terminal to Holland Avenue (approximately 8.0 miles). This segment will allow
refined petroleum to be further distributed in the Houston area.
3.3 OPERATION AND MAINTENANCE
3.3.1 Proposed Project
Operation and maintenance of the current assets will follow the operating practices set forth in
Magellan’s System Integrity Plan (SIP) and the LMP to the extent applicable. The SIP is a
3-6

<<<PAGE 27>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
management system designed to minimize the risks associated with operating Magellan assets.
The SIP is a comprehensive, process-focused approach to operation and maintenance. See
Appendix 3 for high-level summary of SIP categories. The identification and management of
risks associated with the operation of the pipeline system is critical to ensure long-term safety to
the public and employees, and to minimize negative impacts to the environment. Of equal
importance, the SIP is intended to function in coordination with the DOT PHMSA Pipeline Safety
Regulation, Title 49, Subchapter D, Part 195 (Transportation of Hazardous Liquids by Pipeline).
Both the SIP and the LMP are focused on two fundamental areas in relation to the risk
management process:
1) Management of risks of current pipeline assets, and
2) Mitigation of existing and minimization of future pipeline risks.
The LMP consists of certain specific Process Elements. Implementation of the Process
Elements will ensure that the Longhorn components of the Proposed Project will effectively
identify, analyze, and responsibly manage the most critical threats to the System. The Process
Elements form an effective approach to operation and maintenance, and are as follows:
1) Corrosion Management Plan - Activities such as system surveys and evaluations, pipe
design, coating section and application, and cathodic protection are designed to
maintain the System in a manner that ensures safety and environmental protection, with
special attention paid to discrete concerns associated with Tier I, Tier II and Tier III
segments of the pipeline.
2) In-Line Inspection and Rehabilitation Program - Employs current technology in a range
of in-line inspection tools, uses a 360-degree end-to-end look at the System, and the
benefit of a risk-based system of re-inspection.
3) Key Risk Areas Identification and Assessment - Magellan will maintain its focus on risk
mitigation, analysis, and management, drawing input from a variety of sources.
4) Damage Prevention Program - Mitigates the risk of injury to the public and environment
through a program of pipeline marking, aggressive aerial surveillance, and multi-focused
education.
5) Encroachment Procedures - Ensures the maintenance of a clear and unobstructed right-
of-way (ROW), which is crucial to the safe operation of any pipeline system.
6) Incident Investigation Program - Uses a root cause analysis so that preventive action
may be taken to prevent recurrences.
7) Management of Change – Magellan gives full consideration to the operational basis of
change through design review, risk assessment, team communication, and training
protocols.
3-7

<<<PAGE 28>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
8) Depth of Cover Program - Designed to mitigate risks to the public and the environment,
by identifying and mitigating shallow or exposed pipe locations under dynamic
circumstances, with special attention paid to sensitive and hypersensitive areas.
9) Fatigue Analysis and Monitoring Program - A program that identifies and mitigates
pressure-cycle-induced fatigue-related cracking through the evaluation of data
generated in the course of pipeline operations.
10) Scenario Based Risk Mitigation Analysis - An analysis to determine appropriate
preventive measures and system modification to reduce the risk of release of product
(refined product or crude oil), on a pipeline segment by pipeline segment basis.
11) Incorrect Operation Mitigation - Evaluates potential human error (design, construction,
maintenance, and operation) and prevention strategies.
12) System Integrity Plan Scorecarding and Performance Metrics Plan - Provides specific
program performance monitoring and continual improvement through a structure
featuring its ongoing System Integrity Plan Audit, direct accountability, and regular
reporting to PHMSA.
3.3.2 Connected Actions
Magellan will operate and maintain the Connected Actions consistent with Magellan’s SIP and
the IMP, Title 49 Part 195, and where applicable, the LMP. See Appendix 3 for a high-level
summary of Magellan’s SIP.
3.4 ELIMINATION OF ALTERNATIVES FROM DETAILED CONSIDERATION
The only other potentially viable alternative to the Proposed Project is the conversion of the
Orion West Pipeline System into a crude oil pipeline and reversing the flow from Odessa, Texas
to Frost, Texas. As part of this conversion, a new pipeline from Frost to East Houston would
have been constructed since the existing pipeline (East Houston to Frost) supplies refined
petroleum to markets in Dallas and various points in Oklahoma which must continue. This
alternative was dismissed from detailed consideration for the following reasons:
1) Orion West Pipeline reversal would not satisfy the projected pipeline capacity needed to
move West Texas crude to Houston refineries and would not be geographically
positioned to capture Eagle Ford crude production.
2) The construction of new pipeline from Frost Station to East Houston Terminal would be
more environmentally disruptive (i.e. the Orion reversal would require over 200 miles of
new pipeline construction in heavily populated areas, whereas the Proposed Project and
Connected Actions would require less than 17 miles of new pipeline).
3-8

<<<PAGE 29>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
3) The Orion West Pipeline reversal would not be cost effective compared to the Proposed
Project.
3.5 NO-ACTION ALTERNATIVE
The No-Action Alternative is the environmental baseline against which the Proposed Project is
compared. In this FEA, the No-Action Alternative is the continuation of refined product
shipments along the current Longhorn and Orion West pipeline systems.
The environmental impacts from the No-Action Alternative include those identified and analyzed
in the 1999 EA. Also, an examination of the Longhorn Pipeline’s operations and leak history is
included in Chapter 5 of this FEA, which identify the environmental impacts from releases that
have occurred during its startup and operation since the 1999 EA.
In addition to the impacts identified in the 1999 EA, the No-Action Alternative would require the
use of existing delivery systems, including rail deliveries, to move capacity that cannot be
transported by existing pipelines from West Texas and Eagle Ford. Therefore, additional air
quality impacts associated with transporting by rail would remain.
No permitting or additional mitigative measures would be required if the No-Action Alternative
was selected.
The No-Action Alternative does not meet the purpose and need to bring West Texas and Eagle
Ford crude oil to Gulf Coast refineries.
3-9

<<<PAGE 30>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 3
FIGURES
3-1

<<<PAGE 31>>>

Andrews
Martin
Abilene
-Howard
Hood 377
Mitchell
Nolan
20
Midland
273
Taylor
Callahan
Eastland
Houston Area Inset
Ector
283
Erath
15
Odessa
Midland
20
Glasscock
Coke
833
2843
Comanché
610
Sterling
Runnels
281
Bosque
-Coleman
Brown
EAST HOUSTON
Crane
- CRANE
Hamilton
Upton
Reagan
San Angelo
TEXON
Tom Green
Mills
Irion
183
9TH STREET
Concho
5283
Coryell
184}
C61g
259}
6673
833
Mcculloch
San Saba
·190
5 BARNHART
277
Lampass
Menard
Killeen
203
45
Pecos
•enterchen
Bell
11905
Robertson
Crockett
CARȚMAN
FT MCKAVETT
{873
190
Madison
Mason
Llano
Burnet
2190
285
KIMBLE COUNTY
JAMES RIVER
2183
walison
Brazos
Walker
190
Sutton
Kimble
Round Reck
Burleson i
Grimes
San Jacinto
Terrell
ECKERT
a vs
- 2903
Gillespie
CEDAR VALLEY
833
52905
Blánco
Austin
Lee
Montgomery
- BASTROP
Washington
Kerr
281
Hays
WARDA
+ BUCKHORN
1593
277
war varde
Edwards
Kendall
Bastrop
290
•SATSUMA
Real
873
Comal
Caldwell
'INDUSTRY
Austin
Bandera
Fayette
Houston
EAST HOUSTON
Guadalupe 50}
Colorado
Pasadena
Fort Bend
Kinney
Uvalde
410 Bexar
San Antonio
Gonzales
183
9TH STREET
45
{903
Lavaca
Maverick
{833
Wilson
{873
wenarton
Brazorial
Atascosa
2131
De Witt
1593
Jackson
— Longhorn Pipeline
Interstate
Environmental Assessment
Longhorn Pipeline Reversal
Texas
Crude Oil Service
371
US Highway
Figure 3.1-1
N
Project Location of
A Proposed Magellan Pipeline Facility Expansion
City Boundary
Longhorn Pipeline
• Existing Magellan Pipeline Facility Improvement
County Boundary
29
1 Miles
Job No.: 100019708
ts|M_NiMagellan_Midstream_Partners|100019708 geolfig_EAV
Date: Jul 19, 2012

<<<PAGE 32>>>

Cochran
£ ¤380
£ ¤82
Yoakum
£ ¤83
King
£ ¤62
Gaines
£ ¤67
Presidio
£ ¤90
Jeff Davis
JUNCTION
GATEWAY
§ ¨ ¦10
§ ¨ ¦20
Reeves
COTTONWOOD
!
!
!
!
!
!
! !
! !
! ! !
!
!
"
!
!
!
!
!
!
Hudspeth
!
£ ¤285
Culberson
! !
! !
!
§ ¨ ¦10
! !
!
!
! !
!
!
!
Loving
£ ¤62
! !
!
!
!
"
"
!
El Paso
£ ¤54
EL PASO
El Paso
Winkler
!
CRANE
Upton
£ ¤67
Reagan
Irion
Ward
!
! !
!
£ ¤67
£ ¤385
Brewster
£ ¤385
§ ¨ ¦27
£ ¤62
£ ¤385
£ ¤82
£ ¤82
Wichita Falls
£ ¤377
Lubbock
Baylor
Crosby
Dickens
Knox Clay
£ ¤287
Montague
Hockley
Archer
£ ¤82
Cooke
Lubbock
£ ¤84
Grayson
£ ¤183
£ ¤281
§ ¨ ¦35
£ ¤62
£ ¤75
Terry
£ ¤277
£ ¤81
Garza
£ ¤380
Lynn
Haskell
Jack
Kent
Young
£ ¤380
Denton
McKinney
Collin
£ ¤87
Stonewall
Throckmorton
Wise
£ ¤380
Denton
Plano
£ ¤81
Lewisville
Dawson
£ ¤180
Garland
Borden
Fisher
£ ¤180
£ ¤180
§ ¨ ¦820
Irving
Dallas
§ ¨ ¦635
Palo Pinto
Scurry
£ ¤84
Jones
§ ¨ ¦20
Fort Worth
§ ¨ ¦30
Dallas
£ ¤80
£ ¤83
Shackelford
Stephens
Parker
Tarrant
§ ¨ ¦20
Arlington
§ ¨ ¦20
Mitchell
Grand Prairie
£ ¤67
§ ¨ ¦45
Howard
CLYDE
Martin
£ ¤183
§ ¨ ¦20
Hood
£ ¤377
§ ¨ ¦35
Andrews
£ ¤385
§ ¨ ¦20
)
Abilene
"
Nolan
Johnson
Eastland
Erath
Midland
IATAN
Ellis
£ ¤287
Callahan
Taylor
£ ¤67
"
ODESSA DELEON
)
§ ¨ ¦35
FROST
Odessa
MIDLAND
£ ¤87
£ ¤84
"
"
"
Glasscock
Midland
Coke
£ ¤277
£ ¤377
Comanche
Hill
Sterling
Bosque
Navarro
§ ¨ ¦45
Ector
£ ¤83
Brown
£ ¤281
Runnels
Coleman
WALNUT
£ ¤67
Hamilton
Crane
SPRINGS
! !
!
£ ¤84
!
! ! !
! !
"
!
£ ¤83
£ ¤283
San Angelo
Mills
£ ¤183
Mclennan
Waco
Limestone
£ ¤84
Concho
Coryell
§ ¨ ¦35
Tom Green
£ ¤87
£ ¤77
Mcculloch
£ ¤190
Falls
San Saba
Killeen
£ ¤190
Bell
Pecos
£ ¤190
Menard
Robertson
Burnet
Milam
£ ¤190
Mason
Williamson
Llano
£ ¤79
£ ¤377
£ ¤183
£ ¤277
Kimble
Sutton
Round Rock
Burleson
£ ¤87
Gillespie
£ ¤281
Travis
£ ¤83
Austin
Lee
£ ¤290
Blanco
£ ¤290
£ ¤377
£ ¤87
Bastrop
Kerr
Hays
Edwards
Austin
Kendall
Real
Comal
Caldwell
Fayette
Bandera
£ ¤77
§ ¨ ¦10
§ ¨ ¦35
§ ¨ ¦10
Bexar
£ ¤183
Colorado
Kinney
Uvalde
Medina
§ ¨ ¦410
Gonzales Lavaca
San Antonio
£ ¤90 £ ¤90
£ ¤83
£ ¤90
§ ¨ ¦37
Wilson
§ ¨ ¦35
I
0 39 78
Miles
Environmental Assessment
Longhorn Pipeline Reversal
Figure 3.2-1a
Project Location of
Connected Actions
Prepared By: Atkins/19685
Scale: 1" = 39 mi
Job No.: 100019708
Date: Apr 26, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_3.2-1a_ProjectLocation_ConnectedActions_a.mxd
£ ¤190
Schleicher
Crockett
§ ¨ ¦10
Terrell
£ ¤90
Val Verde
£ ¤277
) § ¨ ¦20
Proposed Magellan Pipeline Facility
"
Existing Magellan Pipeline Facility
£ ¤ 87
Refined Product Service
Texas
Connected Actions
Odessa to Crane Pipeline
Midland to Crane Pipeline
El Paso to GatewayJunction Pipeline
Orion Expansion Pipeline
Odessa to Black River Pipeline
! ! ! Crane to El Paso Pipeline
Interstate
US Highway
City Boundary
County Boundary

<<<PAGE 33>>>

§ ¨ ¦45
HOUSTON
£ ¤ 59
GRIMES
MONTGOMERY
HARRIS
FORT BEND
WHARTON
BRAZORIA
SAN JACINTO POLK
LIBERTY
CHAMBERS
GALVESTON
£ ¤ 59
£ ¤ 90
§ ¨ ¦610
EAST HOUSTON
"
§ ¨ ¦10
§ ¨ ¦10
HOLLAND AVE
"
"
9TH STREET
§ ¨ ¦610
SPEED JUNCTION
"
£ ¤ 90
PASADENA
§ ¨ ¦45
Connected Actions
Holland Ave. to East Houston
9th St. to Speed Junction
) § ¨ ¦20
Proposed Magellan Pipeline Facility
"
Existing Magellan Pipeline Facility
£ ¤ 87
Refined Product Service
Crude Oil Service
Interstate
US Highway
City Boundary
County Boundary
I
0.75
0 1.5 3
Miles
Environmental Assessment
Longhorn Pipeline Reversal
Figure 3.2-1b
Project Location of
Connected Actions
Prepared By: Atkins/24125
Scale: 1" = 39 mi
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_3.2-1b_ProjectLocation_ConnectedActions_b.mxd

<<<PAGE 34>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 3
APPENDICES

<<<PAGE 35>>>

SYSTEM INTEGRITY PLAN
Magellan Management Commitment and Support
INTRODUCTION
The Magellan Midstream Partners, L.P. (MMP) System Integrity Plan (SIP) is a management
system designed to minimize the risks associated with operating MMP assets. It is a
comprehensive, process-focused approach to operational excellence defining how we design,
construct, operate, maintain and manage our assets. As such, the SIP is integral to the success
of our business. Incorporated into the SIP is Magellan’s commitment to continuous improvement
of environmental, health and safety performance. MMP’s successful execution of the SIP will
enable continued improvement in:
• Safe and efficient operations
• Compliance with applicable laws and regulations
• Stewardship of Company resources
The SIP will further allow MMP to:
• Operate our assets as a “prudent” operator
• Ensure that our facilities are built and operated on sound technical and business
principles, in compliance with regulatory requirements and in accordance with industry
standards
• Facilitate full and open discussion to address responsible standards and practices where
laws and regulations do not exist or apply
• Provide a safe and secure environment for our employees and the communities in which
we serve
• Ensure that all employees are trained to safely perform their respective duties
• Ensure that all parties working on MMP’s behalf operate to our expectations
• Ensure that the processes that are the backbone of SIP are routinely reviewed
MMP Leadership is committed to ensure that:
• Each business plan includes measurable SIP goals
• MMP’s SIP performance is openly reported and routinely shared with employees
• Pursuit of SIP performance improvement is expected and recognized
MMP strongly believes that the success of the SIP is dependent upon the actions and attitudes of
its employees. The foundation for the success of the SIP is MMP leadership commitment.
Ultimately, MMP’s success is dependent upon having each employee recognizing his or her SIP
identified responsibilities and holding themselves accountable for SIP implementation within his
or her area of responsibility.
The responsibilities of the SIP are directly focused on the employees who operate, maintain and
commercially develop Magellan assets. However, other Magellan employees have an indirect role
in maintaining the integrity of MMP’s assets and as such, are encouraged to familiarize
themselves with the SIP.
Through the individual and collective execution of the SIP, MMP expects to optimize our
resources, improve our profitability and minimize the risks to our employees and to the
communities in which we operate.
MMP embraces implementation, execution and pursuit of continual improvement of the SIP as
the fundamental strategy necessary in its pursuit of operational excellence.
Magellan Midstream Partners Management

<<<PAGE 36>>>

2012 SYSTEM INTEGRITY PLAN
PREFACE
The System Integrity Plan (SIP) is Magellan’s system for managing the risks of operating the
Company’s assets. Therefore, the SIP applies to all Company operated assets. Operations,
Technical Services and Commercial have the primary responsibility for asset operation,
maintenance and management, and the SIP applies directly to the employees in those areas.
SIP references to “the leadership” or “the supervisors” apply only to the leadership or supervisors
in the Operations, Technical Services or Commercial groups, not all leadership or supervisors in
the Company. The role listed as responsible party is accountable for ensuring the requirement is
met.
SIP establishes the minimum standards and procedures for operating, maintaining and managing
Magellan’s assets. A business group or work area may establish more stringent requirements
depending on the need and subject to approval processes established by the respective business
unit; however, they cannot develop less stringent standards than those specified by SIP.
Mitigation Plan specific requirements have been incorporated into the SIP and are thus subject to
the same level of management, authority and responsibility as any other SIP requirement.
Within the SIP are all the initiatives, procedures, forms and other supporting documents for the
element. The SIP utilizes hyperlinks to “link” all these documents together. In some cases, there
are links to documents that are not SIP documents, such as Company policies, or external
websites. These particular linked documents are not considered part of SIP, meaning that the
Element Owners and teams do not “own” them and cannot change them. However, if an SIP
standard requires the use of one of these documents, their use is required per SIP.
The most up-to-date version of SIP is available electronically in Livelink, which all employees
have access to. Any printed documents, including the SIP book, may not be the most current
version of SIP. Although Magellan strives to minimize changes throughout the year, changes to
the SIP may occur if a midyear modification is deemed critical. Employees are encouraged to
use the electronic source documents in Livelink whenever possible to make sure they are using
the most current version of SIP.
For newly acquired assets, Magellan management has established an SIP implementation period
of one year from the date Magellan commences operations, unless regulatory requirements, or
other Company requirements, mandate a more rigorous timeframe (such as with Facility
Response Plans; Spill Prevention, Control & Countermeasure Plans; Facility Security Plans and
Operator Qualification). Other implementation periods may be established with the permission of
the Vice President of the asset.

<<<PAGE 37>>>

SIP ROLES AND RESPONSIBILITIES
Most employees understand that SIP is our operational playbook, or our procedure manual for
operating the assets and for ensuring that we comply with applicable regulations. But the SIP is
also our documented method of reducing the operational risks of operating and managing the
assets. That is, each element within SIP contains written instructions that when implemented and
executed properly, should reduce the risk associated with that element. For example, following
the preventive maintenance procedures and inspections in Asset Integrity (Element 7) helps
reduce the risk of equipment failure and potential subsequent releases or injuries. Similarly,
completing the training listed in the Training Matrix (Element 2) helps reduce the risk of injuries
that could occur during certain activities like working in a confined space. Because SIP is a
comprehensive and integrated playbook, it is the “way we do things around here”, and thus
makes up a large part of our Company culture.
Four teams have specific responsibilities towards developing and maintaining SIP. These teams
and their roles in managing the SIP are described below.
• SIP Oversight Council
• SIP Council
• EHS&S
• Element Review Teams (Element Owners and Stakeholders)
SIP Oversight Council Responsibilities
The SIP Oversight Council is comprised of senior management and is primarily focused on the
cultural aspects of SIP. In other words, they concentrate on ensuring that management sends a
consistent message about SIP goals through metrics, incentives, organizational structure and
resources. Additionally, they actively seek best practices throughout the energy industry and
from other experts. Finally, they work closely with Audit Services to develop the SIP audit
schedule and review results from those audits. They meet twice per year.
The Oversight Council Chair is responsible for establishing the agenda and scheduling and
facilitating the meetings.
SIP Council Responsibilities
The SIP Council is comprised of mid-senior level management, and is the steering team for SIP.
Their main purpose is to develop and track SIP Council goals and ensure that the appropriate
level of resources is allocated to meet the SIP Council goals. They meet quarterly or more often
if needed. A summary of the Council’s responsibilities is below.
• Selects Element Owners
• Reviews and approve proposed significant changes to the SIP
• Establishes SIP Council goals and set direction
• Determines priorities within SIP should resources become limited
• Approves personnel and financial resources for SIP necessary to meet goals
• Resolves conflict, if needed
• Reviews implementation and compliance progress, adjust timelines, priorities or
resources if necessary
• Analyzes the Operational Performance Metrics to identify opportunities to improve
performance related to SIP processes and procedures.
There are specific roles within the Council that ensure the Council meetings run smoothly, are
efficient and that the Council addresses emergent and priority issues. These roles are the
Council Chair and the Council Facilitator.
Revised 1/1/12

<<<PAGE 38>>>

The Council Chair approves the agenda, sets the priorities and runs the meetings. The Chair is
also the Element Owner for Element 1, Magellan Commitment. The Council nominates a new
chair annually; the nomination is approved by the Chief Executive Officer.
The Council Facilitator schedules meetings, drafts the agenda, prepares pre-read materials for
the meetings, monitors completion of action items, and issues meeting notes. The Facilitator also
provides support to the Council Chair. Finally, the facilitator communicates any messages from
the Council to the Element Owners and Element teams.
EHS&S
EHS&S has organizational responsibility for developing and maintaining SIP including SIP
Program management, CMS Project management and SIP Council Meeting facilitation.
Additional SIP responsibilities include:
• Provide quality assurance to the SIP to minimize corporate liability and substantiate
regulatory compliance.
• Manages the Conflict Resolution Process for the element teams
• Act as a focal point and SIP subject matter expert for the organization.
• Manage SIP documentation in Livelink including document control and version history.
• Manages the SIP suggestion process
• Manages SIP change management, including Change Communications
• Leads the annual SIP review process
• Oversees CMS
• Distributes monthly SIP metrics
• Prepares and distributes the quarterly analysis and assessment of incident investigations
• Prepares, facilitates and coordinates the quarterly operational performance results and
meeting
SIP Review Teams
These teams are composed of the Element Owner and stakeholders. The teams are responsible
for establishing, maintaining and improving the documents within their element. Specifically, they
review employee suggestions and make updates if needed, ensure the element meets any
applicable regulations, and ensure the documents within the element support all aspects of SIP
including:
• Providing instructions to employees
• Reducing the operational risk of operating and managing the assets
• Supporting an improved safety culture
Element Owner Responsibilities
The primary responsibility for an element owner is to lead the review process for their element. In other
words, they are project managers accountable for reviewing their element. Specific responsibilities are
shown below.
• Lead the annual review
• Perform their regular jobs in addition to their element owner responsibilities
• In conjunction with the SMEs, ensure SIP meets regulatory requirements
• Get input from Legal department if needed
• Complete annual review on time; communicate if delays occur
• Address feedback on suggestions and responds to the person who made the suggestion
• Select stakeholders who represent impacted areas within MMP
• Ensure stakeholders are actively engaged
• Work with other element owners to resolve conflicts, changes or in other elementsRevised 1/1/12

<<<PAGE 39>>>

• Manage the first level of conflict resolution
• Simplify initiatives, procedures, forms when practical
• Work with the SME to update regulatory cross-references
Stakeholders
Stakeholders are individuals whose work group is affected by the element. They may be subject
matter experts, have experience with the element, or just be very interested in the subject. Their
primary role is to ensure that their work group’s perspective is heard during the review process.
Additional responsibilities include:
• Actively participate in the review process
• Support the team’s decisions
• Understand the purpose of the element
• Provide constructive feedback to your work group on the review process and on their
suggestions
• Provide subject matter expertise as applicable
• Manage time commitments; notify element owner and leadership if time conflicts develop
Revised 1/1/12

<<<PAGE 40>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.0 AFFECTED ENVIRONMENT
This chapter describes the human, physical, biological, and cultural environment that may be
affected by the Proposed Project. Similar to the scope of analysis that was performed in the
1999 EA, this FEA analyzes a potential impact corridor that is at a minimum 1,250 feet from
each side of the Longhorn Pipeline centerline and extends outward to include an overland flow
boundary, which considers the land surface area that could be potentially affected by a spill.
The overland flow boundary was created using a model which uses worst-case drain down
volumes for selected points along the pipeline, which are then overlaid onto a United States
Geologic Survey (USGS) Digital Elevation Model (DEM) 30-meter grid. The volume of crude oil
used in the modeling was defined as a worst-case spill which includes a worst-case drain down
volume plus the volume generated by 12.5 minutes of pumping prior to shut-down. An algorithm
was used to determine a topographical flow direction across the DEM grid. The algorithm
assumes one-half inch of crude oil volume to flow along the spread path until the total product
volume for the selected point is exhausted. A 500 foot buffer extends the overland flow
boundary beyond this point. The measured thicknesses of released product (crude oil) from ten
documented U. S. crude oil pipeline releases were between 2-4 inches. A thickness of one-half
inch of crude oil was used in the algorithm because it assumed a greater spread and resulted in
an added level of conservatism. This zone of potential impact is used consistently throughout
this section, unless otherwise provided.
4.1 HUMAN RESOURCES AND LAND USES
Human resources were evaluated to identify the distribution of population, vulnerable receptors
(e.g., schools, parks, health care facilities, and overnight lodging facilities), existing and planned
land uses, and transportation features along the Proposed Project. The human resources
analysis identifies segments of the pipeline that were determined to be environmentally
vulnerable areas due to population density and/or proximity to vulnerable land uses and
receptors.
4.1.1 Regional Setting
Human resources and land uses along the entirety of the Proposed Project are discussed in a
regional perspective in the following text. The context of the discussion includes:
• Potentially affected communities;
• Regional land uses;
• Regional population density;
• Transportation network; and
• Parks and natural areas.
Detailed analyses of the Houston and Austin metropolitan areas are provided in Sections
4.1.2.1 and 4.1.2.2, respectively.
4-1

<<<PAGE 41>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.1.1.1 Potentially Affected Communities
The Proposed Project crosses 20 counties in the State of Texas. Five incorporated areas are
crossed:
• Galena Park (Harris County);
• Houston (Harris County);
• Jacinto City (Harris County);
• Jersey Village (Harris County); and
• Austin (Travis County).
The Proposed Project is adjacent to several rural and unincorporated neighborhoods and
subdivisions, including:
• Indian Lake Estates (Bastrop County);
• Lake Thunderbird Estates (Bastrop County);
• Oak River Estates (Bastrop County);
• Stony Point (Bastrop County);
• Stoney Ridge (Travis County);
• Lookout Point (Travis County); and
• Cedar Valley (Travis County).
Officials with the Cities of Austin, Bastrop, and Houston, as well as Travis County, were
contacted to determine if any new developments had occurred since publication of the 1999 EA.
The City of Austin did not identify any large developments within the zone of potential impact,
but did have records of some individual platted lots. Travis County reportedly provides all
development plans to the City of Austin for inclusion in the City’s Geographic Information
System (GIS). The City of Houston and surrounding metropolitan area within Harris County is
densely populated with a limited potential for large residential developments. The City of
Bastrop did not identify any large developments within the zone of potential impact.
Large municipalities in the vicinity of the Proposed Project include:
• Johnson City (4 miles south of the pipeline in Blanco County);
• Junction (12 miles south of the pipeline in Kimble County);
• Eldorado (2 miles north of the pipeline in Schleicher County);
• Big Lake (2 miles south of the pipeline in Reagan County); and
• Crane (3 miles south of the pipeline in Reagan County).
The Proposed Project crosses through, and is in proximity to, numerous unincorporated
communities between Austin and Houston, including:
• Pleasant Grove (approximately 1.5 miles north of the pipeline in Rusk County);
• Eckert (1.5 miles south of the pipeline in Gillespie County);
• Travis and Scranton Grove (0.5 miles north of the pipeline in Austin County);
4-2

<<<PAGE 42>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Shelby (crossed by the pipeline in Austin County);
• Blieblerville (crossed by the pipeline in Austin County);
• Welcome (crossed by the pipeline in Austin County);
• Walhalla (crossed by the pipeline in Fayette County);
• Nechanitz and Warda (1.5 miles north of the pipeline in Fayette County);
• St. Martin (0.5 miles north of the pipeline in Fayette County);
• Shiloh (0.5 miles south of the pipeline in Bastrop County);
• Wrights (1.0 mile north of the pipeline in Bastrop County);
• Pilot Knob (crossed by the pipeline in eastern Travis County); and
• Willow City (2.0 miles south of the pipeline in Gillespie County).
4.1.1.2 Regional Land Uses
Data from the 2006 National Land Cover Database (NLCD) was obtained in an effort to
characterize the land uses crossed by the Proposed Project. The table below summarizes the
types of land uses within the zone of potential impact along the pipeline from Crane to East
Houston.
Land Use Types Traversed by the Proposed Project
NLCD Class Description Acres Percent
Barren Land (Rock/Sand/Clay) 347.7 0.16%
Cultivated Crops 3,756.3 1.76%
Deciduous Forest 10,097.8 4.77%
Developed, High Intensity 1,765.3 0.83%
Developed, Low Intensity 6,553.8 3.10%
Developed, Medium Intensity 6,592.9 3.12%
Developed, Open Space 10,534.5 4.98%
Emergent Herbaceous Wetlands 584.9 0.28%
Evergreen Forest 13,061.2 6.18%
Grassland/Herbaceous 8,304.4 3.93%
Mixed Forest 1,502.0 0.71%
Open Water 554.4 0.26%
Pasture/Hay 21,910.0 10.36%
Scrub-shrub 119,443.5 56.47%
Woody Wetlands 6,490.9 3.07%
Total 211,499.9 100.00%
As shown above, the majority of the area is characterized as scrub-shrub, which is defined by
the NLCD as “areas dominated by shrubs; less than five meters tall with shrub canopy typically
greater than 20% of total vegetation. This class includes true shrubs, young trees in an early
successional stage, or trees stunted from environmental conditions” (NLCD, 2001). Though not
4-3

<<<PAGE 43>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
defined as such by the NLCD, this type of land in Texas is frequently dedicated to cattle grazing
and other agricultural activities. Other agricultural uses crossed by the pipeline include
pasture/hay and cultivated crops.
Developed land (high, medium, and low intensity, and open space) accounts for only 12.03% of
the land crossed by the pipeline. These areas are within and surrounding Houston and Austin,
and include a range of uses from “highly developed areas where people reside or work in high
numbers” (high intensity) to “areas with a mixture of constructed materials and vegetation often
including single-family residences” (low intensity). Open space developed land is typically
comprised of vacant lots and open spaces in urban and suburban areas (NLCD, 2001).
4.1.1.3 Regional Population Density
4.1.1.3.1 Housing
The number of housing units within the zone of potential impact was determined through the
interpretation of 2010 National Agricultural Imagery Program (NAIP) aerial photography. This
count was then used as the basis for estimating the population within an area adjacent to the
pipeline defined as the area of potential impact. The photo-interpretation process included an
initial identification of single-family and multi-family units, and health care facilities. If possible,
the names and number of units of apartment buildings and other multi-family facilities were
determined. If unit numbers could not be found, they were estimated based on approximate
size. Locations of schools were determined using Texas Education Agency (TEA) data.
Dwelling unit numbers along the pipeline route were compiled by 1-mile segments along the
pipeline from Crane to East Houston and numbers of persons per household were applied to
estimate total population numbers within each 1-mile segment, as described in the following
section “Population”.
Areas along the pipeline were classified by a measure of population density. Three zones were
defined according to the number of residential units within the zone of potential impact: low
density is 0-20 residential units per mile; moderate density is 21 to 1,000 residential units per
mile; and high density is greater than 1,000 residential units per mile.
Of the 466 miles of pipeline from Crane to East Houston, 19 miles (4.1%) are categorized as
high density; 62 miles (13.3%) are categorized as medium density; and the remaining 385 miles
(82.6%) are categorized as low density.
The greatest concentration of housing and population is in the Houston area where
approximately 37,898 dwelling units were identified within the zone of potential impact. The
second-most concentrated area of housing occurs within the Austin area, where approximately
8,927 dwelling units were identified within the pipeline’s zone of potential impact. A list of multi-
family facilities (apartments, condominiums, and townhomes) within the Houston and Austin
metropolitan areas is provided in Table 4.1.1-1.
4-4

<<<PAGE 44>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.1.1.3.2 Population
The total population of the 19 counties (Harris, Waller, Austin, Lee, Fayette, Bastrop, Travis,
Hays, Blanco, Gillespie, Llano, Mason, Kimble, Menard, Schleicher, Crockett, Reagan, Upton,
and Crane, Counties) crossed by the Longhorn Pipeline was an estimated to be 5,509,531 in
2009 (U.S. Census Bureau 2009). Population estimates along the Crane to East Houston
pipeline were based on an inventory of dwelling units and average population per household
numbers by county as determined by 2000 U.S. Census Bureau data. Results of that analysis
indicate that approximately 131,477 persons reside within the zone of potential impact. Detailed
information is included in Table 4.1.1-2.
Of the 131,477 persons living within the zone of potential impact, approximately 105,726
(80.4%) reside between milepost (MP) 1 and MP 40 of the Longhorn Pipeline and along MP1
and MP 9 of the East Houston to 9th Street segment. Most of the remaining 4,453 (3.4%)
persons along the pipeline reside between Houston and Austin. Approximately 994 (1.5%)
persons live within the zone of potential impact between Austin and Crane.
4.1.1.4 Transportation Networks
The Proposed Project crosses 23 federal highways, 24 state highways, and numerous state-
designated Farm-to-Market (FM) and Ranch roads. The pipeline also crosses numerous city
streets (primarily in the Houston and Austin metropolitan areas), county roads, and 22 railroads.
Highway and railroad crossings are listed by county in Appendix 4A.
4.1.1.5 Parks and Natural Areas
The Proposed Project crosses Buescher and Pedernales Falls State Parks, and portions of the
zone of potential impact cover areas of McKinney Falls State Park. In addition to these state
parks, several other recreational areas are either crossed by the pipeline or have areas within
the zone of potential impact. These include Fox Creek Golf Club (Waller County), Pine Forest
Golf Club (Bastrop County), Scallorn Cemetery (Bastrop County), Big Lake (Reagan County),
and the Crane Country Club (Crane County). Additional recreational areas in the Houston and
Austin areas are discussed in sections 4.1.2.1 and 4.1.2.2, respectively.
Buescher State Park, Bastrop County. The park consists of 1,017 acres in the Lost Pines
region of Texas. Amenities include camping, non-motorized boating, fishing, hiking, and biking
(TPWD, 2011).
Pedernales Falls State Park, Blanco County. According to Texas Parks and Wildlife
Department (TPWD), the park consists of 5,212 acres and typifies the Edwards Plateau terrain
of the surrounding region. Activities offered include camping, picnicking, hiking, river swimming,
tubing, wading, mountain biking, fishing, bird watching, and horseback riding (TPWD, 2011).
McKinney Falls State Park, Travis County in South Austin. The park consists of 744 acres
and includes historic structures dating to the mid-1800s. Activities offered at the park include
4-5

<<<PAGE 45>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
camping, hiking, mountain biking, road biking, picnicking, fishing, wildlife observation, and
swimming in Onion Creek (TPWD, 2011).
4.1.2 Other Receptors in the Houston and Austin Areas
4.1.2.1 Houston Area
The Proposed Project originates nine miles south of the East Houston Terminal in an industrial
area of the Houston metropolitan area and extends to the north through portions of the City of
Houston and unincorporated areas of Harris County. Although residential land uses dominate
much of the area adjacent to the alignment, industrial/commercial use areas are concentrated in
the Galena Park Station industrial area and along major arterials such as Market Street,
Wallisville Road, Interstate Highway 10 (IH-10), and US 90. Subdivisions and neighborhoods
crossed by the pipeline within the eastern Houston area include Groveland Terrace, Holiday
Forest, Songwood, Wood Bayou, Wallisville Gardens, Ralston Acres, Houmont Park, and Green
River. Urban undeveloped land is scattered as small parcels throughout the area. Land uses
along the East Houston portion of the pipeline are shown on Figure 4.1.2-1a and 1b.
The pipeline turns toward the west at Green River Road and crosses through urban residential
areas and urban undeveloped land to the northwestern city limits, as shown on Figure 4.1.2-1c
through Figure 4.1.2-1i. Neighborhoods and subdivisions along the alignment include Parkwood
East, Lake Forest Estates, Glenwood Forest, Kentshire Place, Park North, Scenic Woods,
Fontaine Place, Sherwood Place, Oakwilde, Melrose Place, Willow Run, Heather Glen, West
Mount Houston, Inwood North, Inwood North Estates, Rolling Fork, Arbor Vineyards,
Willowbridge, Winchester Country, Steeplechase, Steeplechase Park, Crossroads, Northmead
Village, and Aberdeen Trails. Rural residential land use areas begin approximately 2 miles west
of US 290 and extend as relatively isolated subdivisions and population centers from the
Houston metropolitan area to central Waller County.
4.1.2.1.1 Special Use Areas
Special use areas along the pipeline include numerous schools, parks and recreation centers,
and health care facilities. A special use area and potential vulnerable receptor within the area
includes Herman Brown Park which is located in Houston. Public and private schools in the area
occur in residential areas of Jacinto City, Houston, and unincorporated Harris County. The
Proposed Project crosses seven school districts in the Houston metropolitan area. Thirty-one
public schools, five private schools, one health care facility, and 30 parks and recreational
facilities are within the zone of potential impact. These are summarized in Table 4.1.2-1 and are
shown on Figures 4.1.2-1a through 4.1.2-1i.
4.1.2.2 Austin Area
Land uses within the Austin area, including eastern and western Travis County, are shown on
Figures 4.1.2-2a through 4.1.2-2g. The uses are predominantly urban residential with the
heaviest concentration east of Brodie Lane. Rural residential and agricultural/rangeland land
4-6

<<<PAGE 46>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
uses within the Austin metropolitan area are limited to those within unincorporated western
Bastrop County and eastern and western Travis County.
Subdivisions/neighborhoods crossed by the alignment (east to west) include: Onion Creek
Forest, Silverstone, Indian Hills, Meadow Creek, Park Ridge, Buckingham Estates, Parkwood,
Tanglewood Forest, Shiloh, Southwest Oaks, Cherry Creek, Sendera Oaks, Sendera Glen, and
Village at Western Oaks. Other subdivisions within the metropolitan area include: Indian Lake,
Lake Thunderbird, Oak River Estates, and Stony Point in Bastrop County and East Travis Hills
and Stoney Ridge in eastern Travis County.
The planning department for the City of Austin was contacted to determine if any new
developments were planned for the area surrounding the pipeline. The City of Austin did not
identify any large developments within the overland flow boundary, but did have records of
some individual platted lots.
4.1.2.2.1 Special Use Areas
The Proposed Project crosses four school districts in the Austin area. Within the overland flow
boundary there are four public schools, one private school, one healthcare facility, and 12
recreational areas. These are identified in Table 4.1.2-2 and shown on Figures 4.1.2-2a through
4.1.2-2g.
4.2 PHYSICAL RESOURCES
4.2.1 Groundwater Resources
4.2.1.1 Aquifers Traversed by the Zone of Potential Impact and General Nature
The Texas Water Development Board (TWDB) Groundwater Availability Modeling (GAM)
program recognizes and has differentiated 9 major and 21 minor aquifers within Texas. The
names used by the TWDB GAM program for those major and minor aquifers traversed by the
zone of potential impact are also used in this FEA. One unclassified aquifer, a smaller, localized
aquifer that is not officially designated by the TWDB as an aquifer, is also traversed by the zone
of potential impact.
Those major, minor and unclassified aquifers identified as underlying the zone of potential
impact for the Proposed Project are listed in Table 4.2.1-1. The aquifers are listed on this table
in the order encountered by the Proposed Project from east to west. A summary of the
characteristics of each aquifer is also provided in Table 4.2.1-1. The locations where the
Proposed Project traverses these aquifers are shown on Figures 4.2.1-1 and 4.2.1-2.
The land surface exposure, or outcrop area, of the formation(s) comprising an aquifer is the
area corresponding to the principal recharge zone for the aquifer. Groundwater encountered
within the recharge zone is normally under a watertable or unconfined condition, and has a high
degree of vulnerability to contamination. When water-bearing strata dip below the surface and
4-7

<<<PAGE 47>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
are covered by less permeable strata, such as clay, and hydrostatic pressure within the strata
increased, the aquifer becomes confined or under an artesian condition. Confined aquifers,
“covered aquifers”, have a very low degree of vulnerability to contamination.
4.2.1.2 Relative Vulnerability of Aquifers within the Zone of Potential Impact
4.2.1.2.1 Relative Aquifer Vulnerability Evaluation Methodologies
General. The relative drinking water resource vulnerability of those aquifers listed on Table
4.2.1-1 to a crude oil release within the zone of potential impact was systematically evaluated
using both the Pettyjohn et al. Aquifer Classification Scheme (EPA, 1991), and the TCEQ
aquifer vulnerability ranking system based on the average DRASTIC index of each Texas
aquifer. The DRASTIC and Pettyjohn et al. methodologies were developed for the EPA as
standardized techniques for evaluating the relative vulnerability of aquifers to surface or near
surface sources of pollution.
The qualitative vulnerability rankings of high, medium and low are assigned to each aquifer
using the average TCEQ DRASTIC index and Pettyjohn et al. methodologies separately.
Aquifer drinking water vulnerability under both methods was numerically ranked from 1 (high
vulnerability) to 3 (low vulnerability). The sum of TCEQ DRASTIC index and Pettyjohn et al.
numerical ranking is used along with potential public water supply water well vulnerability
numerical rankings to aquifer drinking water vulnerability within the zone of potential impact.
More detailed explanations of the qualitative analyses, numerical ranking system and use in
determining aquifer sensitivity are presented in following paragraphs, Section 4.2.1.2 and
Section 4.2.1.4.
The Pettyjohn et al. aquifer classification scheme was also utilized to qualitatively identify those
aquifers traversed by the zone of potential impact that potentially serve as, or are hydraulically
connected to, aquatic habitats.
DRASTIC. The DRASTIC methodology was developed for the EPA as a standardized system
for systemically evaluating groundwater pollution potential. The DRASTIC methodology is
presented in detail in the EPA document: “DRASTIC: A Standardized System for Evaluating
Groundwater Pollution Potential Using Hydrogeologic Settings” (EPA/600/2-87/035 June 1987).
The DRASTIC acronym is composed of letters for each of the measurable parameters for which
data are generally available from a variety of sources. These measurement parameters from
which the DRASTIC acronym is derived are:
D - Depth to water
R - net Recharge
A - Aquifer media
S - Soil media
T - Topography
I - Impact of the vadose zone media
C - Hydraulic Conductivity of the aquifer
4-8

<<<PAGE 48>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The TCEQ developed an aquifer vulnerability ranking system based on the average DRASTIC
indices calculated using the above-referenced parameters for the major and minor aquifers of
Texas. The TCEQ uses this ranking system because it is a reasonable method of determining
the relative vulnerability of aquifers to surface activities.
The information sources from which the TCEQ obtained the above-referenced measurement
parameters included, but were not limited to, the TWDB, Natural Resource Conservation
Service, Bureau of Economic Geology and USGS. In the DRASTIC methodology, each of these
factors has a "range" and associated "rating". Appendix D of the TCEQ document “Texas
Nonpoint Source Management Program Report” dated December 2005, lists the average
DRASTIC index and aquifer vulnerability ranking assigned by the TCEQ to each of the major
and minor aquifers. The qualitative vulnerability rankings assigned by the TCEQ to these
aquifers are high, medium and low.
As indicated in Appendix D, an average DRASTIC index and vulnerability ranking have not been
calculated and assigned for one minor aquifer. The absence of an index and ranking are most
likely due to this minor aquifer being recently recognized as an official aquifer by the TWDB at
the time the TCEQ was preparing the rankings. It should also be noted that the TCEQ has not
assigned an average DRASTIC index or aquifer vulnerability ranking for the unclassified
alluvium aquifer traversed by the zone of potential impact, most likely because this aquifer is not
recognized by the TWDB as a major or minor aquifer.
The formation that comprises the recently recognized minor aquifer belongs to the same
geologic group as those formations comprising older aquifers in that same geologic group.
These formations have similar lithologies and environments of deposition. Therefore, the more
conservative DRASTIC index and aquifer vulnerability ranking for a ranked aquifer of that
geologic group is appropriate for the recently recognized minor aquifer. Following this same
rationale, an average DRASTIC index and aquifer vulnerability ranking equal to that of the
recognized minor alluvium aquifer traversed by the zone of potential impact is fitting for the
unclassified alluvium aquifer. Table 4.2.1-2 lists the major and minor aquifers along with their
average DRASTIC indices and aquifer vulnerability rankings as assigned by the TCEQ or
determined using the above-described rationale.
Pettyjohn et al. Aquifer Classification Scheme. The Pettyjohn et al. Aquifer Classification
Scheme was developed for the EPA to assess the vulnerability of surficial and relatively shallow
aquifers to contamination from shallow injection wells, as well as, surface or near surface
sources of contamination. The EPA attempted to evaluate all aquifers in the conterminous
United States on the basis of their reported physical properties, hydrologic characteristics and
behavior as reported in published reports and maps. Details pertaining to this aquifer
classification scheme are presented in the EPA document: “Regional Assessment of Aquifer
Vulnerability and Sensitivity in the Conterminous United States” (EPA/600/ 2-91/043 August
1991). This classification scheme is used by the DOT to identify aquifers that are unusually
sensitive drinking water resources as defined in 49 CFR Part 195, Pipeline Safety: Areas
Unusually Sensitive to Environmental Damage.
4-9

<<<PAGE 49>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The Pettyjohn et al. Aquifer Classification Scheme divides aquifers into four classes. The first
two classes are further subdivided based on various characteristics. The aquifer classifications
and their characteristics are described below.
Class I aquifers are surficial or shallow, permeable and highly vulnerable to contamination. This
class of aquifer includes the following four subdivisions:
Class Ia. This class of aquifer consists of surficial, unconsolidated, and permeable sand
and gravel, commonly interbedded to some degree with silt and clay lain down as alluvial,
terrace, outwash, beach, dune and other similar deposits. A Class 1a aquifer generally contains
layers.
Class Ib. Soluble and fractured bedrock consisting of limestone, dolomite, and, locally,
evaporites are the lithologies that make up a Class Ib aquifer. This aquifer class contains
documented karst features or solution channels, of which size is not important. A Class Ib
aquifer generally exhibits a wide range in permeability and well yields. Groundwater movement
is largely controlled by the secondary openings, potentially allowing for the rapid vertical and
horizontal groundwater movement, and a high degree of vulnerability. Also, included in this
class are aquifers comprised of sedimentary, metamorphic and igneous (intrusive and extrusive)
rocks that are significantly faulted, fractured, or jointed.
Class Ic. Aquifers falling under Class Ic are semi-consolidated; contain poorly to
moderately-indurated sand and gravel, and are interbedded with clay and silt. The semi-
consolidated condition may be from the introduction of clay and caliche matrix into primarily
unconsolidated to poorly consolidated strata.
Class Id. Any Class I aquifer overlain by less than 50 feet of low permeability,
unconsolidated material, such as glacial till, lacustrian, and loess deposits.
Class II aquifers are consolidated bedrock aquifers that are moderately vulnerable. There are
three subdivisions within this aquifer class, which are described below:
Class IIa. This subdivision includes higher yield bedrock aquifers generally consisting of
fairly permeable sandstone or conglomerate containing lesser amounts of interbedded shale,
siltstone and/or mudstone. Interbedded carbonate strata may also be present. To be included in
this aquifer class, well yields must exceed 50 gpm. Local fracturing or jointing may contribute to
the dominant primary porosity and permeability of this class of aquifer.
Class IIb. For the most part, Class IIb aquifers are lower yield bedrock aquifers
consisting of sedimentary or crystalline rocks of the same types present in Class IIa aquifer.
However, grain size in the Class IIb rocks is generally smaller and cementation or induration is
greater, resulting in lower permeability. Well yields are generally less than 50 gpm, but may be
greater in some areas.
4-10

<<<PAGE 50>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Class IIc. This aquifer class consists of any Class IIa or lIb aquifer that is overlain by less
than 50 feet of unconsolidated material of low permeability.
Class III aquifers are unconsolidated and consolidated aquifers overlain by more than 50 feet of
low permeability material, and are the least vulnerable of all the classes. These aquifers are
naturally protected by a thick layer of fine-grained material, such as clay or shale. There are no
subdivisions within this aquifer class.
Undifferentiated aquifers are designated as Class U. This classification is used when a map-
able area contains several lithologic and hydrologic conditions that cannot be differentiated due
to mapping scale constraints, the presence of undelineated members within a formation or
group, or the presence of non-uniformly occurring features, such as fracturing or joints. This
class suggests a wider range of vulnerability than is usually contained within any other aquifer
class.
For consistency, the TCEQ qualitative rankings of high, medium and low were used to rank
aquifer vulnerability. These rankings are based on the aquifer lithology, confining layer
thickness, confined condition and well yield. All Class I group aquifers and Class IIa aquifers
have a high vulnerability ranking. Class IIb, Class IIc and Class U aquifers are ranked as
medium vulnerability. Class III aquifers are ranked as low vulnerability.
Section 2 of EPA/600/ 2-91/043, August 1991 presents an evaluation of the aquifers in the
conterminous US using the Pettyjohn et al. Aquifer Classification Scheme. With regard to
Texas, this evaluation concluded that approximately:
• 25% of Texas is covered by Class la aquifers;
• 13% of Texas has Class Ib aquifer outcrops;
• 25% of Texas is Class Ic aquifer outcrops;
• 7% of Texas has surface exposures of Class lIa aquifers;
• 24% of Texas is covered by Class III aquifers and,
• 6% of Texas is covered by undifferentiated aquifers.
This indicates that about 70% of Texas is covered by Classes I and IIa aquifers that are
potentially unusually sensitive areas of drinking water resources. The above percentage
breakdown of aquifer classes also points out that approximately 45% of Texas aquifers are
Class Ia (alluvium), Ib (karst) and IIa (outcropping bedrock) aquifers which potentially serve as
or are hydraulically connected to aquatic habitats. Table 4.2.1-3 lists the major and minor
aquifers crossed by the zone of potential impact and the associated Pettyjohn et al. Aquifer
Classification.
4.2.1.2.2 Relative Aquifer Vulnerability Evaluation
Aquifer drinking water vulnerability within the zone of potential impact was qualitatively analyzed
on two levels, the TCEQ DRASTIC aquifer vulnerability ranking and the Pettyjohn et al. Aquifer
Classification Scheme. Aquifer drinking water vulnerability for both evaluation levels was ranked
4-11

<<<PAGE 51>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
from 1 (high vulnerability) to 3 (low vulnerability) as shown in Table 4.2.1-4. The vulnerability of
aquifer associated aquatic habitats was also qualitatively evaluated using the Pettyjohn et al.
Aquifer Classification Scheme and literature documentation that natural discharge to streams is
a common and frequent occurrence. Aquifer aquatic habitat vulnerability is also a numerical
ranking of 1 (high vulnerability) to 3 (low vulnerability). The aquifer aquatic habitat ranking is
also shown on Table 4.2.1-4. The relevant aquifer information used and the findings of the
above referenced qualitative analyses for each aquifer traversed by the potential zone of impact
from east to west are summarized below.
Gulf Coast Aquifer System. The Gulf Coast Aquifer System is a major aquifer that occupies a
wide belt along the Gulf Coast of Texas. This aquifer system is a complex of interbedded clay
silt, sand, and gravel strata of several formations that are hydrologically interconnected forming
a large, leaky artesian aquifer system. Recharge to the Gulf Coast Aquifer is mainly by rainfall
infiltrating outcropping sand and gravel (permeable) strata. Water also enters the aquifer from
some of the numerous streams that cut into the permeable strata of this aquifer. However, there
are a few area seeps and springs that do discharge into some streams as base flow where
those streams cut into groundwater-bearing strata.
The relative drinking water vulnerability rankings established for the Gulf Coast Aquifer System
using the two qualitative methodologies were high and medium. The TCEQ calculated a 95
average DRASTIC Index, a medium vulnerability ranking for this aquifer. This medium TCEQ
vulnerability ranking equates to a numerical ranking of 2. Outcrop areas of this aquifer system
comprised of sand and gravel qualify as Pettyjohn et al. Classes Ia and Ic, with the remaining
outcrop areas being Class U. Therefore, the drinking water vulnerability is high for all Class I
areas, and medium for all Class U areas, with FEA drinking water vulnerability numerical
rankings of 1 and 2, respectively.
The above Pettyjohn et al. classifications indicate that the aquifer aquatic habitat vulnerability
ranking for the Gulf Coast Aquifer System is medium. This ranking takes into account that
hydraulic communication between this aquifer and those streams that cross it is not continuous
along the zone of potential impact. Hence, the overall FEA aquifer aquatic habitat numerical
ranking is 2.
Brazos River Alluvium Aquifer. The Brazos River Alluvium Aquifer is a minor aquifer that
occupies the Brazos River Valley. This aquifer consists of alluvial terrace and floodplain
deposits of sand, gravel, silt, and clay sediments. The aquifer is generally unconfined with the
watertable surface generally sloping towards the Brazos River, indicating that the aquifer
naturally discharges to the river as seeps and springs above the river water line. Recharge to
this aquifer is primarily from infiltrating rainfall.
The average TCEQ DRASTIC Index calculated for the Brazos River Alluvium Aquifer is 144, a
high drinking water vulnerability ranking. This aquifer also meets the Pettyjohn et al. criteria for
Class Ia, which point to a high drinking water vulnerability. The above qualitative evaluations
show that FEA numerical drinking water vulnerability rankings of 1 are applicable for the finding
of both evaluation methods.
4-12

<<<PAGE 52>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The Pettyjohn et. al. Aquifer Classification given above signifies that the Brazos River Alluvium
Aquifer is ranked high with regard to aquatic habitat vulnerability. Accordingly, the FEA
numerical ranking is 1 for aquatic habitat vulnerability.
Yegua-Jackson Aquifer. The Yegua-Jackson Aquifer was recognized as a minor aquifer in
2002. It is present as a narrow band extending from East Texas to South Texas, and inland of
the Gulf Coast Aquifer System. Interbedded sand, silt, and clay strata of the Yegua Formation
and Jackson Group, along with some occurrences of lignite, limestone, tuff, shells, and gypsum,
make up this aquifer. Groundwater is under watertable (unconfined) conditions in the Yegua-
Jackson Aquifer outcrop areas and under artesian (confined) conditions in the deeper, dipping
sediments. Groundwater flow in the unconfined portion of the aquifer is influenced by the
topography and generally flows from the topographically high areas to topographically low areas
into creeks and rivers as springs and seeps. Recharge to the Yegua-Jackson aquifer occurs by
precipitation, irrigation subsurface return flow, and stream or reservoir leakage at the outcrop
area.
A TCEQ calculated DRASTIC Index and vulnerability ranking were not given in the previously
referenced 2005 TCEQ report. A surrogate DRASTIC Index and vulnerability ranking were
developed by comparing the Yegua-Jackson Aquifer hydrogeologic characteristics to those
characteristics of the Sparta and Queen City Aquifers. All three of these aquifers belong to the
same geologic group and have similar lithology and environment of deposition. Therefore, the
more conservative DRASTIC index and aquifer vulnerability ranking of the Queen City Aquifer,
108 and medium, were determined to be appropriate for the Yegua-Jackson Aquifer.
The above surrogate TCEQ DRASTIC drinking vulnerability ranking for the Yegua-Jackson
Aquifer points to an FEA drinking vulnerability numerical ranking of 2. The Pettyjohn et al.
Aquifer Classification Scheme qualitative analysis established that this aquifer is Class Ic. This
indicates the drinking water vulnerability ranking is high, with an FEA numerical ranking of 1 for
this vulnerability type.
The Pettyjohn et al. Aquifer Classification given above denotes that the aquatic habitat
vulnerability ranking for the Yegua-Jackson Aquifer is high at outcrop areas. Therefore, the FEA
aquifer aquatic habitat vulnerability numerical ranking is 1 for the outcrop area of this aquifer.
Sparta Aquifer. The Sparta Aquifer is a minor aquifer that extends in a narrow band from the
Frio River in South Texas northeastward to the Texas-Louisiana state line, and inland of the
Yegua-Jackson Aquifer. This aquifer is comprised entirely of the Sparta Formation and consists
of sand and interbedded clay with small amounts of lignite in some locations. Groundwater
within the Sparta Aquifer is under watertable conditions in its outcrop areas and artesian
conditions downdip of its outcrops where the aquifer is overlain by low permeable formations.
Infiltrating precipitation, stream or reservoir leakage, or irrigation return flow infiltration provide
recharge to this Sparta at outcrop areas. Springs usually occur in topographically low areas in
stream valleys or in areas of the outcrop where hydrogeologic conditions preferentially reject
recharge.
4-13

<<<PAGE 53>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The TCEQ calculated an average DRASTIC Index of 98 for the Sparta Aquifer giving it a
medium drinking water vulnerability ranking and a FEA numerical ranking of 2. Under the
Pettyjohn et al. Aquifer Classification Scheme, the outcrop area of this aquifer qualifies as Class
Ic, with the subcrop, confined portion being Class III. Therefore, the drinking water vulnerability
ranking based on Pettyjohn et al. is high for the outcrop area and low for the confined portion.
The above Pettyjohn et al. qualitative evaluations show that FEA numerical drinking water
rankings of 1 and 3 are applicable to the outcrop and subcrop areas, respectively.
The Pettyjohn et al. classifications given above signify that the Sparta Aquifer aquatic habitat
vulnerability change greatly going from the outcrop areas to the subcrop areas. The Class Ic
classification and natural discharge via springs to topographically low areas in stream valleys of
the outcrop area being common ranks the outcrop areas as having high aquatic habitat
vulnerability, for a FEA numerical ranking of 1. A low aquifer aquatic vulnerability ranking,
corresponding to a FEA numerical ranking of 3, is appropriate for the subcrop portion of the
Sparta Aquifer due to being Class III under Pettyjohn et al., and having little to no natural
discharge by way of springs to stream valleys.
Queen City Aquifer. The Queen City Aquifer is a minor aquifer that extends in a narrow band
across Texas from the Frio River in South Texas northeastward to the Texas-Louisiana state
line. This aquifer is comprised entirely of sand, loosely cemented sandstone, and interbedded
clay strata of the Queen City Formation. The Queen City Aquifer is under watertable conditions
in its outcrop areas and under artesian conditions downdip of the outcrops where overlain by
younger low permeable formations. Sources for recharge to this aquifer include precipitation
and stream or reservoir leakage infiltrating the outcropping strata. Springs usually occur in
topographically low areas in stream valleys or in areas of the outcrop where hydrogeologic
conditions preferentially reject recharge.
The average DRASTIC Index assigned by the TCEQ to the Queen City Aquifer is 108 for a
medium drinking water vulnerability ranking for a FEA numerical ranking of 2. As with the Sparta
Aquifer, the Queen City Pettyjohn et al. classification is Class Ic in outcrop areas and Class III in
subcrop areas. Accordingly, Queen City Aquifer outcrops have a high drinking water
vulnerability ranking and subcrop portions are ranked as being low with regard to drinking water
vulnerability. The above Pettyjohn et al. classifications equate to FEA drinking water
vulnerability numerical rankings of 1 for outcrop areas and 3 where the Queen City is in
subcrop.
As with the Sparta Aquifer, the Queen City aquatic habitat vulnerability ranking differs in outcrop
and subcrop. The Pettyjohn et al. classification of Class Ic, and the frequent occurrence of
natural discharge as springs in stream valleys indicate that outcrop areas have high aquatic
habitat vulnerability ranking. Therefore, the Queen City Aquifer outcrop areas are given a FEA
numerical ranking of 1. The Pettyjohn et al. Class III designation and little to no natural
discharge by way of springs where in subcrop earns this portion of the Queen City Aquifer a low
aquifer aquatic vulnerability ranking and a FEA numerical ranking of 3 for this vulnerability
category.
4-14

<<<PAGE 54>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Colorado River Alluvium Aquifer. The Colorado River Alluvium Aquifer has not been
classified as a major or minor aquifer by the TWDB. This aquifer is restricted, for the most part,
to the Colorado River Valley and is comprised of groundwater saturated alluvium and terrace
sand and gravel strata. The aquifer outcrop areas, which generally coincide with the river valley,
receive recharge from infiltrating rainfall and from the tributaries of the Colorado River that cross
the outcrop areas. Groundwater in the Colorado River Alluvium Aquifer is unconfined with the
watertable surface generally sloping towards the river and naturally discharging to the river as
springs.
A TCEQ DRASTIC Index and vulnerability ranking were not given in the previously referenced
2005 TCEQ report. A surrogate DRASTIC Index and vulnerability ranking (Brazos River
Alluvium Aquifer) was assigned to the Colorado River Alluvium Aquifer based on similar
hydrogeologic characteristics and depositional environments. The TCEQ DRASTIC index and
aquifer drinking water vulnerability ranking given to the Queen City Aquifer are 144 and high,
respectively, for a FEA numerical ranking of 1. The qualitative analysis under the Pettyjohn et al.
Aquifer Classification Scheme established that this aquifer is Class Ia with a high drinking water
vulnerability ranking. Accordingly, the FEA scheme established that this aquifer is Class Ia with
a high drinking water vulnerability numerical ranking of 1.
The Pettyjohn et al. aquifer classification given above denotes that the Colorado River Alluvium
Aquifer has a high aquatic habitat vulnerability ranking. Therefore, the FEA aquatic habitat
vulnerability numerical ranking is 1 for this aquifer.
Carrizo-Wilcox Aquifer. The Carrizo-Wilcox Aquifer is a major aquifer extending from the
Texas-Louisiana state line to the Texas-Mexico border as a narrow band that runs parallel with
the Gulf Coast. This aquifer consists primarily of sand strata locally interbedded with gravel, silt,
clay, and lignite beds of the Wilcox Group and Carrizo Formation, which are hydrologically
connected. Groundwater within the Carrizo-Wilcox Aquifer is under watertable conditions in the
outcrop areas and confined conditions downdip of the outcrop areas. Sources for recharge to
the Carrizo-Wilcox Aquifer include precipitation and stream or reservoir leakage infiltrating the
outcropping permeable strata. Natural discharge usually occurs as springs in topographically
low areas in river valleys or in areas of the outcrop where hydrogeologic conditions
preferentially reject recharge.
The TCEQ assigned an average DRASTIC Index of 117 to the Carrizo-Wilcox Aquifer and a
medium drinking water vulnerability ranking for a FEA numerical ranking of 2. The qualitative
evaluation following the Pettyjohn et al. Aquifer Classification Scheme produced two results.
The Carrizo-Wilcox outcrop area meets the Class Ic criteria, and thereby, a high drinking water
vulnerability ranking. The subcrop portion of this aquifer is Class III for a low drinking water
vulnerability ranking. Hence, Carrizo-Wilcox Aquifer outcrop areas have a FEA numerical
ranking of 1 with subcrop portions being ranked as 3 under the Pettyjohn et al. Aquifer
Classification Scheme evaluation.
4-15

<<<PAGE 55>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The Carrizo-Wilcox Aquifer aquatic habitat vulnerability ranking is dependent on whether the
aquifer is outcropping or in subcrop. The Class Ic Pettyjohn et al. classification for the outcrop
area, and natural discharge commonly occurring as springs in river valleys in this area point out
a high aquatic habitat vulnerability ranking for the outcrop area. This high aquifer aquatic habitat
vulnerability ranking for Carrizo-Wilcox outcrop areas lead to a FEA aquifer aquatic habitat
vulnerability numerical ranking of 1. The Class III Pettyjohn et al. designation for the subcrop
portion and little to no natural discharge by way of springs where the Carrizo-Wilcox is covered
by low permeability strata brings about a low aquifer aquatic vulnerability ranking, and a FEA
numerical ranking of 3 for this vulnerability type.
Edwards (Balcones Fault Zone) Aquifer-Barton Springs Segment. The Edwards (Balcones
Fault Zone or BFZ) Aquifer is a major aquifer in South-Central Texas. This karst, sole-source
aquifer occupies a narrow belt extending from the eastern half of Kinney County through the
San Antonio area northeastward to the Leon River in Bell County. The Barton Springs Segment
of the Edwards (BFZ) Aquifer is hydrologically distinct from the rest of the Edwards (BFZ)
Aquifer. The northeastern banks of Onion Creek and Plum Creek near Kyle, Texas serve as the
southern boundary for the Barton Springs Segment when flow conditions are high. During low-
flow drought conditions, the southern boundary shifts further south to the Blanco River (Save
Barton Creek Association Newsletter, 2010). The northern limit of the Edwards (BFZ) Aquifer is
defined by the southwestern bank of the Colorado River. The Barton Springs Segment of the
Edwards (BFZ) Aquifer consists of dissolution-modified, faulted, and fractured limestone of the
Edwards Group. The Barton Springs Segment of the Edwards (BFZ) Aquifer is unconfined in its
outcrop area and confined in subcrop where overlain by younger formation. Recharge to the
Edwards (BFZ) Aquifer is not restricted to karst features with surface expression. Hauwert
(2009) and Hauwert and others (2010) concluded that upland recharge (i.e. non-cave/sinkhole
or non-creek direct recharge) could contribute a significant percentage of the total recharge to
the aquifer. Detailed evaluation of the Longhorn Pipeline trench across the outcrop of the
Edwards (BFZ) Aquifer indicated numerous smaller karst features across the outcrop. Sources
of recharge to this aquifer include the downward percolation of surface water from streams
crossing the outcrop area, by direct infiltration of precipitation on the outcrop area and cross-
formational flow from the underlying Trinity Aquifer.
The aquifer feeds several well-known recreational springs, as well as lesser known springs, and
underlies some of the most environmentally sensitive areas in the state. A recent study by the
City of Austin (COA) and the Barton Springs/Edwards Aquifer Conservation District (BSEACD)
has shown that most of the outcrop of the Edwards in Travis County should be considered as
highly vulnerable. A key sensitive receptor within the Barton Springs system is the Barton
Spring salamander. This amphibian lives only at the spring out flows of Barton Springs (TPWD,
2012). Turner and O’Donnell (2004) developed a four-tiered Barton Springs salamander rescue
plan in case an instantaneous gasoline pipeline spill occurred on the outcrop of the Barton
Springs Segment of the Edwards (BFZ) Aquifer. Available dye tracer study results for the Barton
Springs Segment were used to validate peak concentration predictions derived using a
published regression equation developed from dye tracing data in a number of carbonate
aquifers. The tiered responses are based on the estimated volume of gasoline entering the
aquifer under various flow scenarios and spill distance from Barton Springs.
4-16

<<<PAGE 56>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The TCEQ calculated an average DRASTIC Index of 126 for the Edwards (BFZ)-Barton Springs
Segment Aquifer, and a high drinking water vulnerability ranking giving a FEA numerical ranking
of 1. The Pettyjohn et al. Aquifer Classification Scheme qualitative evaluation placed the
Edwards (BFZ)-Barton Springs Segment Aquifer outcrop area in Class Ib for a high drinking
water vulnerability ranking. The subcrop portion, also known as the Confined Zone, of this
aquifer meets the Class III criteria and low drinking water vulnerability ranking. Based on the
Pettyjohn et al. Aquifer Classification Scheme evaluation, the Edwards (BFZ)-Barton Springs
Segment outcrop areas have a FEA numerical ranking of 1, while subcrop portions have a
ranking of 3 for drinking water vulnerability.
The Edwards (BFZ)-Barton Springs Segment Aquifer aquatic habitat vulnerability ranking is
dependent on whether a spill occurs in the outcrop or subcrop areas. A high aquatic habitat
vulnerability ranking for the outcrop area of this aquifer is warranted because of 1) the Class Ib
Pettyjohn et al. Classification for the outcrop area; 2) well-documented natural discharge via
numerous springs in this area, and 3) the presence of no critical aquatic habitat to which
aquifer-supplied springs discharge into. The aquifer aquatic habitat vulnerability ranking of high
scores the Edwards (BFZ)-Barton Springs Segment outcrop areas a FEA numerical ranking of
1. The Class III Pettyjohn et al. designation for the Confined Zone of the Edwards (BFZ)-Barton
Springs Segment and little to no natural discharge by way of springs in this portion of the aquifer
leads to a low aquifer aquatic vulnerability ranking, and a FEA numerical ranking of 3.
Trinity Aquifer System-Hill Country. The Trinity Aquifer System-Hill Country (Trinity-HC) of
South-Central Texas is part of the Trinity Aquifer, and is a major aquifer system. The Trinity-HC
includes all or parts of Bandera, Bexar, Blanco, Comal, Gillespie, Hays, Kendall, Kerr, Kimble,
Medina, Travis, and Uvalde Counties. The Trinity-HC Aquifer is comprised of the formations that
belong to the Trinity Group. The Upper and Middle portions of the Trinity-HC Aquifer consist of
limestone with groundwater occurring primarily in fractures, along bedding planes and in karst
features. The Lower Trinity-HC is predominately sand and gravel. The Upper and Middle Trinity-
HC are unconfined in outcrop areas with the Middle Trinity-HC becoming semi-confined in its
eastern reaches. The Lower Trinity-HC is artesian and covered by a shale stratum that forms a
leaky confining layer. Rainfall infiltration and seepage from streams and lakes on outcrop areas
are the primary sources of recharge to the Upper and Middle Trinity-HC. Recharge to the Lower
Trinity-HC is mainly by leakage from overlying and underlying aquifers, although some stream
seepage contributes a small amount of recharge where a limited outcrop of the Lower Trinity-
HC occurs along the Pedernales River. Springs and seeps originating from the Upper and
Middle Trinity-HC provide most of the base flow in waterways such as Barton Creek, Onion
Creek, and the Pedernales River.
The average DRASTIC Index assigned by the TCEQ to the Trinity-HC is 95 with a medium
drinking water vulnerability ranking. These TCEQ rankings correspond to a FEA numerical
ranking of 2. The Upper and Middle Trinity-HC quality for Pettyjohn et al. classifications of Class
IIa in outcrop and where this upper portion of this aquifer is in contact with the Edwards (BFZ)
aquifer. The Lower Trinity-HC being overlain by a confining shale stratum and being present
mainly in subcrop is Class III. The drinking water vulnerability rankings for the Upper and Middle
4-17

<<<PAGE 57>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Trinity-HC are high, while the Lower Trinity-HC ranks low for drinking water vulnerability. Based
on the above Pettyjohn et al. classifications, the FEA numerical rankings for the Upper and
Middle Trinity-HC are 1, and the ranking for the Lower Trinity-HC is 3 with regard to drinking
water vulnerability.
The Pettyjohn et al. classification of Class IIa and the frequent occurrence of natural discharge
as springs in stream valleys dictate that the Upper and Middle Trinity-HC be assigned high
aquatic habitat vulnerability rankings. As a result, the Upper and Middle Trinity-HC have FEA
aquatic habitat vulnerability numerical rankings of 1. The Pettyjohn et al. Class III designation
and no natural discharge by way of springs directly from an outcrop of the Lower Trinity-HC
warrants a low aquifer aquatic vulnerability ranking and a FEA numerical ranking of 3 for this
vulnerability category.
Marble Falls Aquifer. The Marble Falls Aquifer is a minor aquifer, the subsurface extent of
which is unknown. This aquifer is restricted to the flanks of the Llano Uplift region of Texas, and
provides groundwater to parts of Blanco, Burnet, Lampasas, McCulloch, and San Saba
Counties, and smaller areas of Kimble, Llano, and Mason Counties. The Marble Falls Limestone
comprises the entire aquifer, with groundwater occurring in fractures and karst features such as
solution cavities and channels in this formation. Groundwater in the outcrop areas is under
watertable conditions with artesian conditions occurring downdip where younger formations
overlie the Marble Falls Limestone. In most areas, the artesian portion is not extensive.
Recharge to the Marble Falls Aquifer occurs in the outcrop areas where rainfall enters through
karst features and stream seepage through faults at stream crossings. Springs and seeps from
this aquifer are often associated with faults that also add considerably to the ease of recharge to
the aquifer.
The Marble Falls Aquifer is assigned an average DRASTIC Index of 126 and a high drinking
water vulnerability ranking by the TCEQ resulting in a FEA numerical ranking of 1. The
qualitative evaluation by the Pettyjohn et al. Aquifer Classification Scheme places this aquifer in
Class Ib for a high drinking water vulnerability ranking. Based on the Pettyjohn et al. Aquifer
Classification Scheme results, the Marble Falls Aquifer FEA numerical ranking is 1 for drinking
water vulnerability.
As with the Edwards (BFZ)-Barton Springs Segment Aquifer, the Marble Falls Aquifer aquatic
habitat vulnerability ranking is dependent on whether a spill occurs in its outcrop areas. The
Class Ib Pettyjohn et al. classification and documented natural discharge via numerous springs
to streams justify a high aquatic habitat vulnerability ranking for this aquifer. The high aquatic
habitat vulnerability ranking also equates a FEA numerical ranking of 1 for this ranking category.
The vulnerabilities of the confined portion of the Marble Falls Aquifer were not ranked given that
this aquifer is overlain by younger aquifer strata. The strata of the overlying younger aquifers
offer a degree of protection for this aquifer, inhibiting the vertical migration of released crude oil.
Ellenburger-San Saba Aquifer. The Ellenburger-San Saba Aquifer is a minor aquifer that
occupies a roughly circular area in parts of 16 counties within and adjacent to the Llano Uplift
4-18

<<<PAGE 58>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
region. Hydrologically connected limestones and dolomites of the San Saba Limestone Member
of the Wilberns Formation and formations of the Ellenburger Group make up this aquifer.
Groundwater occurs within karst features, fractures and faults within the strata comprising this
aquifer. Groundwater in the outcrop areas of the Ellenburger-San Saba Aquifer is under
watertable conditions. Downdip, artesian conditions exist where strata of younger aquifers
overlie the strata of this aquifer. Precipitation and stream seepage are the main sources of
recharge to the Ellenburger-San Saba Aquifer. Sinkholes, caves, and other karst features, most
associated with faults, are present on the aquifer outcrop and add considerably to the ease of
recharge to the aquifer. Springs and seeps from this aquifer are often associated with faults that
also add considerably to the ease of recharge to the aquifer.
The TCEQ assigned an average DRASTIC Index of 126 and a high drinking water vulnerability
ranking to the Ellenburger-San Saba Aquifer, which corresponds to a FEA numerical ranking of
1. A qualitative evaluation of the lithologic and hydrologic characteristics of this aquifer produced
a Pettyjohn et al. classification of Class Ib and a high drinking water vulnerability ranking. Based
on the Pettyjohn et al. classification results, the Ellenburger-San Saba Aquifer has a FEA
numerical ranking of 1 with regard to drinking water vulnerability.
The Ellenburger-San Saba Aquifer aquatic habitat vulnerability ranking is similar to the Marble
Falls Aquifer, being dependent on whether a spill occurs in its outcrop areas. A high aquatic
habitat vulnerability ranking for this aquifer is warranted because of the 1) Class Ib Pettyjohn et
al. classification; 2) presence of karst features; and 3) documented natural discharge via
numerous springs to streams. The above Pettyjohn et al. classification therefore warrants an
FEA numerical ranking of 1 for aquifer aquatic habitat vulnerability.
Ranking of the confined portion of the Ellenburger-San Saba Aquifer was not performed due to
the aquifer being covered by younger aquifer strata. The strata of the overlying aquifers afford a
measure of protection for this aquifer, inhibiting the vertical migration of released crude oil.
Hickory Aquifer. The Hickory Aquifer, a minor bedrock aquifer, occupies parts of 19 counties in
the Llano Uplift region. This aquifer consists exclusively of the Hickory Sandstone Member of
the Riley Formation. The Hickory Sandstone is a mixture of sandstones, siltstones, and
mudstones. Outcrops of the Hickory Sandstone are discontinuous and overlie the flanks of the
exposed Precambrian rocks that form the central core of the Llano Uplift. The aquifer is
unconfined in outcrop areas and becomes artesian downdip of the outcrop areas. Block faulting
has compartmentalized the Hickory Aquifer thereby restricting groundwater flow across the fault
planes. Recharge to the Hickory Aquifer is from rainfall infiltrating the sandy outcrop and where
streams cross the aquifer outcrop areas. Springs and seeps from this aquifer are often
associated with faults which also add considerably to the ease of recharge to the aquifer.
An average DRASTIC Index of 114 and a medium drinking water vulnerability ranking were
assigned to the Hickory Aquifer by the TCEQ. The medium ranking is concurrent with a FEA
drinking water vulnerability numerical ranking of 1. The lithologic and hydrologic characteristics
of this aquifer point to a Pettyjohn et al. classification of Class IIa and a high drinking water
4-19

<<<PAGE 59>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
vulnerability ranking. Based on the Pettyjohn et al. classification results, the Hickory Aquifer has
a FEA drinking water vulnerability numerical ranking of 1.
The Hickory Aquifer aquatic habitat vulnerability ranking is comparable to the Marble Falls and
the Ellenburger-San Saba aquifers, in that secondary structures (faults and fractures) increase
vulnerability to crude oil releases that occur in the outcrop areas. A high aquatic habitat
vulnerability ranking for this aquifer is warranted because of the 1) Class IIa Pettyjohn et al.
classification; 2) porous medium comprising this aquifer; 3) presence of faults and fractures at
the outcrop surface; and 4) documented natural discharge via numerous springs to streams.
The above Pettyjohn et al. classification and associated vulnerability merits an FEA numerical
ranking of 1 for aquifer aquatic habitat vulnerability.
As with the Marble Falls and Ellenburger-San Saba Aquifer, the vulnerabilities of the confined
portion of the Hickory Aquifer were not ranked since this aquifer is covered by younger aquifer
strata. The overlying younger aquifer strata offer a degree of protection for this aquifer,
hindering the vertical migration of released crude oil.
Edwards-Trinity (Plateau) Aquifer. The Edwards-Trinity (Plateau) Aquifer is a major aquifer
that underlies the Edwards Plateau extending from the Hill Country of Central Texas to the
Trans-Pecos region of West Texas. The water-bearing strata comprising the Edwards-Trinity
(Plateau) Aquifer are predominantly karst-modified limestone and dolomite formations of the
Edwards Group and limestones and sands of the Trinity Group. The aquifer is generally
unconfined; but, may be confined to semi-confined locally where relatively impermeable
sediments of the overlying basal member of the Edwards Group exist. Recharge to the
Edwards-Trinity (Plateau) Aquifer occurs mainly from precipitation infiltrating joints, crevices,
and solution openings on the Edwards Group outcrop area and from stream losses from the
many intermittent streams crossing this outcrop. The Trinity Group, having few outcrops areas
to receive direct recharge, gets much of its water by cross-formational flow from the overlying
Edwards Group. Springs and seeps from the Edwards-Trinity (Plateau) Aquifer occur mostly
along the margins of the aquifer from where the watertable intersects the land surface, and
provide base flow to many streams of the plateau.
The Edwards-Trinity (Plateau) Aquifer is assigned an average DRASTIC Index of 107 and a
medium drinking water vulnerability ranking by the TCEQ, which equates to a FEA drinking
water vulnerability numerical ranking of 1. The qualitative evaluation performed using the
Pettyjohn et al. Aquifer Classification Scheme qualified this aquifer as meeting the criteria for
Class Ib, and a high drinking water vulnerability ranking. Based on the Pettyjohn et al. Aquifer
Classification Scheme results, the Edwards-Trinity (Plateau) Aquifer FEA numerical ranking is 1
with regard to drinking water vulnerability.
The Pettyjohn et al. classification of Class Ib and the frequent occurrence of natural discharge
as springs and seeps from the Edwards-Trinity (Plateau) Aquifer are evidence for a high aquatic
habitat vulnerability ranking. Thus, this aquifer warrants a FEA aquatic habitat vulnerability
numerical ranking of 1.
4-20

<<<PAGE 60>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Pecos Valley Aquifer. The Pecos Valley Aquifer is a major aquifer located in the upper part of
the Pecos River Valley of West Texas and provides water to parts of Andrews, Crane, Ector,
Loving, Pecos, Reeves, Upton, Ward, and Winkler Counties. Lacustrine sediments, sand,
mudstone, siltstone, conglomerate, limestone, shale, and gypsum deposited in several
structural basins of the Pecos Valley comprise this aquifer. The Pecos Valley Aquifer is an
unconfined aquifer that occurs only in outcrop. The Pecos Valley Aquifer receives recharge from
infiltrating precipitation and from cross-formational flow from the Edwards-Trinity (Plateau)
Aquifer. Surface water diverted from the Pecos River also recharges the Pecos Valley Aquifer
as seepage from irrigation fields. The Pecos Valley Aquifer also sustains numerous springs that
discharge into the Pecos River.
The TCEQ calculated an average DRASTIC Index of 95 and assigned a medium drinking water
vulnerability ranking for the Pecos Valley Aquifer. The above TCEQ drinking water vulnerability
ranking amounts to a FEA numerical ranking of 2 for drinking water vulnerability. The qualitative
evaluation using the Pettyjohn et al. classification scheme produced a Class Ia result pointing to
a high drinking vulnerability. The above qualitative evaluation shows that a FEA numerical
drinking water vulnerability ranking of 1 is applicable.
The Pettyjohn et al. aquifer classification given above and the fact that Pecos Valley Aquifer
also sustains numerous springs to the Pecos River denotes that this aquifer ranks high with
regard to aquifer aquatic habitat vulnerability. Accordingly, the FEA numerical ranking is 1 for
aquatic habitat vulnerability.
Southern Ogallala Aquifer. The Southern Ogallala Aquifer is a major aquifer in the High Plains
region of Texas extending south of the Canadian Breaks to Winkler, Ector, Midland, and
Glasscock Counties and from the eastern escarpment of the Southern High Plains westward to
the Texas-New Mexico border. Fluvial gravel, sand, silt, clay, and eolian sand and silt of the
Ogallala Formation comprise the Southern Ogallala Aquifer. The Southern Ogallala outcrops
throughout the Southern High Plains Region and is under watertable conditions. Recharge to
this aquifer occurs principally by infiltration of precipitation on the surface and, to a lesser extent,
by upward leakage from underlying formations. The primary sources of recharge to the
Southern Ogallala Aquifer are direct rainfall infiltration on the outcrop, indirect rainfall infiltration
through playas and headwater creeks, irrigation return flow, and upward cross-formational flow
from underlying minor aquifers such as the Edwards-Trinity (High Plains) Aquifer and the
Dockum Aquifer. Numerous springs and seeps occur along the eastern High Plains escarpment,
within the draws, and along the margins of salt lake basins. For many municipalities, the
Southern Ogallala Aquifer is the sole source of drinking water.
The average DRASTIC Index of 99 and medium drinking water vulnerability ranking assigned by
the TCEQ for the Southern Ogallala Aquifer corresponds to a FEA drinking water vulnerability
numerical ranking of 2. The Pettyjohn et al. qualitative evaluation shows that this aquifer meets
the Class Ic criteria, and thereby, qualifies for a high drinking water vulnerability ranking. Under
the above Pettyjohn et al. evaluation, the Southern Ogallala Aquifer has a FEA drinking water
vulnerability numerical ranking of 1.
4-21

<<<PAGE 61>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The Class Ic Pettyjohn et al. classification for the Southern Ogallala Aquifer and natural
discharge occurring as numerous springs draws and basins point out a high aquatic habitat
vulnerability ranking for this aquifer. This high aquifer aquatic habitat vulnerability ranking for the
Southern Ogallala Aquifer yields a FEA aquifer aquatic habitat vulnerability numerical ranking of
1.
4.2.1.3 Potentially Vulnerable Public Water Supply (PWS) Water Wells
The 1996 Safe Drinking Water Act (SDWA) Amendments required all states to assess the
susceptibility of every public drinking water source within that state. In response, the TCEQ
assessed every PWS for susceptibility to certain chemical constituents by May 2003 to comply
with this federal regulation. A PWS is defined as a public water system that supplies water to
the public (more than 15 individuals) and is regulated by the TCEQ. The results of this source
water susceptibility assessment were provided to the PWS for use in implementing local source
water protection projects. The TCEQ placed the spatial datasets created during the source
water susceptibility assessment process into a web-based GIS viewer titled “The Source Water
Assessment Viewer” that is accessible through the TCEQ website. This web-based viewer is
designed to allow public access to the PWS source water susceptibility assessment spatial
datasets. The information contained in these spatial datasets are specific to each PWS, such
as but not limited to aquifer used, water well depth, well screen depth, and the area that
comprises a PWS water well capture zone.
A capture zone is a three-dimensional area that surrounds a pumping water well. Groundwater
within the capture zone flows to and is captured by that water well. Groundwater outside the
capture zone boundary will not flow to or be captured by that pumping well. A well capture zone
is usually determined from aquifer characteristics, pumping rate and well construction details.
The TCEQ calculated “time-of-travel capture zones” for public supply water wells using
computer algorithms based upon the hydrogeology of the area specific to a well and parameters
specific to that well. A time-of-travel capture zone is delineated by an isochronal boundary. A
water particle and any contaminant associated that water particle located at that isochronal
boundary will take “x” number of years to migrate to the associated pumping water well and be
“captured” by that water well. For example, a water particle located at a 2-year time-of-travel
capture zone boundary will take two years to reach and be captured by that zone’s pumping
water well. When some of the required information was missing for a PWS water well, the
TCEQ, by default, assigned a half-mile diameter circle, a fixed radius, to delineate the capture
zone for that particular PWS water well. This fixed radius is not based on well-specific
construction and hydrogeologic information.
A qualitative analysis was performed on spatial datasets of PWS water wells exported from the
TCEQ Source Water Assessment Viewer website and loaded into a GIS. The first step in the
qualitative analysis process was to filter out from the spatial datasets those PWS water wells
located outside the area of review (AOR). The AOR runs parallel with and extends
approximately five miles on either side of the zone of potential impact. The resulting spatial
datasets for those PWS water wells located within the AOR were evaluated to identify those
4-22

<<<PAGE 62>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
PWS water wells with the greatest potential vulnerability risk to a crude oil release from the
System.
The next qualitative analysis step involved sorting the spatial datasets into groups and
subgroups. The initial grouping placed the AOR PWS water wells into one of two groups:
• Group 1 - Those PWS water wells located within the zone of potential impact boundary;
and,
• Group 2 - Those PWS water wells located outside the zone of potential impact
boundary.
Those PWS water wells belonging to Group 1, due to being located within the zone of potential
impact, have the greatest potential vulnerability risk to a crude oil release from the System. The
PWS water well placed within Group 2 required further evaluation to ascertain the degree of
potential vulnerability risk to a release within the zone of potential impact. The spatial datasets
for those PWS water wells located outside the zone of potential impact were sorted and placed
into four subgroups:
• Subgroup 2a - Those PWS water wells with 2-year time-of-travel and 0.5-mile fixed
radius capture zones that do not encroach into the potential zone of impact;
• Subgroup 2b - Those PWS water wells with 2-year time-of-travel capture zones that
encroach into the potential zone of impact;
• Subgroup 2c - Those PWS water wells with 0.5-mile fixed radius capture zones that
encroach into the potential zone of impact, and do not encompass and/or are not
immediately adjacent to 2-year time-of-travel capture zones; and,
• Subgroup 2d - Those PWS water wells with 0.5-mile fixed radius capture zones that
encroach into the potential zone of impact, and do encompass and/or are immediately
adjacent to 2-year time-of-travel capture zones.
The 2-year time-of-travel capture zone (the shortest calculated by the TCEQ) was selected to
identify those PWS water wells located outside the zone of potential impact having the highest
probable vulnerability to a release. The rationale for using the 2-year time-of-travel capture
zones is that those wells having 2-year time-of-travel capture zones that encroach into the zone
of potential impact would be affected much sooner than those public supply wells having 2-year
time-of-travel capture zones that do not encroach into the zone of potential impact. The 0.5-mile
fixed radius capture zone was used when a 2-year time-of-travel capture zone was not
calculated by the TCEQ.
The Subgroup 2a PWS water wells have the least potential vulnerability risk to a crude oil
release occurring within the zone of potential impact. Groundwater underlying the zone of
potential impact is least likely to be captured by the Subgroup 2a water wells. Those PWS water
wells belonging to Subgroups 2b and 2c have the same potential vulnerability risk to a System
crude oil release as do the Subgroup 1 PWS water wells. Groundwater underlying the zone of
potential impact would flow to and be captured by those PWS water well belonging to
Subgroups 2b and 2c.
4-23

<<<PAGE 63>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The incursion of Subgroup 2d PWS water well capture zones into the zone of potential impact
indicates by default that this subgroup of water well has a potential vulnerability risk equal to
that of Subgroup 1. However, the presence of 2-year time-of-travel capture zones within the
boundaries of and/or immediately adjacent to a 0.5-mile fixed radius capture zones are usable
as a secondary line of evidence for a more in-depth qualitative analysis of the Subgroup 2d
potential vulnerability risk. The coverage areas of 2-year time-of-travel capture zones that are
present within and/or surrounding a 0.5-mile fixed radius capture zone reflect the hydrogeologic
characteristics of the aquifer within that fixed radius capture zone coverage area. Therefore, it is
reasonable that a 2-year time-of-travel capture zone for the same water well, if had been
calculated by the TCEQ, would have a coverage area of similar size as those time-of-travel
capture zones located within and immediately surrounding the fixed radius capture zone of
interest. This in-depth qualitative analysis was performed by relocating the largest 2-year time-
of-travel capture zone within the limits of or immediately adjacent to the 0.5-mile fixed radius
capture zone of interest to the fixed radius capture zone PWS water well location. Those
Subgroup 2d PWS water wells with relocated 2-year time-of-travel capture zones not
encroaching into the zone of potential impact have the least potential vulnerability risk to a crude
oil release occurring within the zone of potential impact, and were filtered from the spatial
dataset. Those Subgroup 2d PWS water wells having relocated 2-year time-of-travel capture
zones encroaching into the zone of potential impact have the same potential vulnerability risk to
a System crude oil release as do the Subgroup 1 PWS water wells.
The qualitative analysis identified 134 PWS wells in total that are present within or have
qualified capture zones incursions into the zone of potential impact. The locations of these 134
PWS water wells are shown on Figures 4.2.1-3a through 3d. Table 4.2.1-5 lists the PWSs
associated with those potentially vulnerable PWS water wells; the aquifers utilized by these
water wells; and, the cross-reference PWS water well ID number for Figures 4.2.1-3a to 3d.
4.2.1.4 Identification of Sensitive Groundwater Resource Areas
In this FEA, a sensitive groundwater resource area is a drinking water resource, as generally
defined in 49 CFR Part 195.6 as related to aquifers, within the zone of potential impact, and
aquifer with a potential connection to an aquatic habitat that is sensitive to environmental
damage from a crude oil release from the Proposed Project. A qualitative numerical ranking
system was devised for this assessment to identify sensitive groundwater resource areas within
the zone of potential impact. The criteria by which a sensitive groundwater resource area was
determined to be present are discussed in Sections 4.2.1.1 through 4.2.1.3 of this assessment.
Aquifer drinking water vulnerability within the zone of potential impact was determined on two
levels, the TCEQ DRASTIC Aquifer Vulnerability Ranking and the Pettyjohn et al. Aquifer
Classification Scheme. Vulnerability for both levels was ranked from 1 (high vulnerability) to 3
(low vulnerability) as shown in Table 4.2.1-4.
The vulnerability of aquifer-associated aquatic habitats was also qualitatively evaluated using
the Pettyjohn et al. Aquifer Classification Scheme and literature documentation that natural
4-24

<<<PAGE 64>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
discharge to streams is a common and frequent occurrence. Aquifer aquatic habitat vulnerability
was ranked from 1 (high vulnerability) to 3 (low vulnerability). The aquifer aquatic habitat ranking
is also shown on Table 4.2.1-4.
The vulnerability ranking for PWS water wells within the zone of potential impact was based on
1) the presence or absence of PWS water wells within the zone as determined in Section
4.2.1.3; and 2) well depth. Drinking water resource vulnerability was given a ranking of either 1
(wells present, <50 feet below ground level (bgl), or wells producing from a karst sole-source
aquifer); 2 (wells present, >50 feet bgl producing from an aquifer not sole-source); or 3 (wells
not present).
A GIS was used to overlay map files of 1) the major/minor aquifers from the TWDB; 2) PWS
water wells and capture zones from the TCEQ; and 3) the zone of potential impact. This
mapping method allowed for the reasonable ranking of aquifer and drinking water resource
vulnerability within the zone of potential impact. The pipeline MP markers were used to locate
the start and end of an aquifer outcrop or subcrop within the zone of potential impact along the
pipeline route. The sum of the aquifer and PWS water well vulnerability rankings was used to
identify sensitive and non-sensitive groundwater resource areas. A ranking sum less than 7
indicates that an aquifer outcrop or subcrop is a sensitive groundwater resource area. The
results of the sensitivity ranking along the zone of potential impact are presented in Table 4.2.1-
4. Those aquifer areas identified as sensitive groundwater resource areas are summarized
below.
Gulf Coast Aquifer System. That area of the Gulf Coast Aquifer System from MP 20 to MP 21
qualifies as a sensitive groundwater resource area. The Pettyjohn et al. Aquifer Classification
Scheme ranking of Class Ia and the presence of PWS water wells 50 feet or less in depth within
the zone of potential impact are the critical ranking parameters.
Brazos River Alluvium Aquifer. The segment of the Brazos River Alluvium Aquifer located
between MPs 59.5 and 66 ranks as being a sensitive groundwater resource. The TCEQ,
Pettyjohn et al., and aquatic habitat vulnerability rankings are the key ranking factors.
Colorado River Alluvium. Several areas of the Colorado River Alluvium Aquifer are ranked as
sensitive groundwater resource areas based on the TCEQ, Pettyjohn et al., and aquatic habitat
vulnerability rankings. These sensitive areas are located in the following MP intervals: 119-
120.5, 121-123, 125-126.5, 128-129.5, and 130.5-141.5.
Edwards (BFZ) Aquifer-Barton Springs Segment. The outcrop area of the Edwards (BFZ)
Aquifer located between MPs 170.5 and 173.5 ranks as a sensitive groundwater resource for all
four ranking parameters. The sum of all rankings listed on Table 4.2.1-4 indicates this aquifer
area to be the most sensitive along the zone of potential impact.
Trinity Aquifer System-Hill Country. The ranking sum for the Trinity Aquifer-HC outcrop
shows this aquifer to be a sensitive groundwater resource where crossed by the zone of
potential impact. A Pettyjohn et al. Aquifer Classification Scheme ranking of Class IIa, high
4-25

<<<PAGE 65>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
aquatic aquifer habitat ranking, and the presence of PWS water wells or encroaching capture
zone are the critical ranking parameters. The aquifer outcrops within the following MP intervals:
173.5-198.5, 206-207.5, 216-220, and 222.5-224.5.
Marble Falls Aquifer. The sum rankings for the Marble Falls Aquifer outcrop area located
between MPs 198.5 and 199 qualify this area as a sensitive groundwater resource. The critical
factors for this ranking are the TCEQ ranking, Pettyjohn et al. Class Ib classification, and high
aquifer aquatic habitat ranking.
Ellenburger-San Saba Aquifer. The Ellenburger-San Saba Aquifer sum ranking indicates that
this aquifer is a sensitive groundwater resource where traversed by the zone of potential impact
with the TCEQ ranking, Pettyjohn et al. Class Ib classification, and high aquifer aquatic habitat
ranking being the critical rankings. Those MP intervals crossing the Ellenburger-San Saba are:
199-206, 249.5-254.5, 264-270, 272-274, and 275.5-276.5.
Edwards-Trinity (Plateau) Aquifer. The ranking sum for the Edwards-Trinity (Plateau) Aquifer
outcrop show this aquifer to be a sensitive groundwater resource where crossed by the zone of
potential impact. A Pettyjohn et al. Aquifer Classification Scheme ranking of Class Ib and high
aquatic aquifer habitat ranking are the key ranking parameters. The aquifer outcrops within the
following MP intervals: 222-222.5, 227-227.5, 232.5-233, 237-237.5, 238-238.5, 246-246.5,
254.5-257.5, 270-272, 274-275.5, and 277.5-447.
4.2.2 Surface Water
4.2.2.1 Description of Surface Water Resources
The surface water bodies associated with the Proposed Project are unchanged from those
contained in the 1999 EA. Accordingly, much of the spatial information regarding surface water
is extracted from the 1999 EA. Because the pipeline from Crane Station to El Paso will not
change product service and is a “connected action” of the Proposed Project, it is not addressed
in this section. Changes were also made to update information that has changed since the time
of preparation of the 1999 EA.
The Proposed Project intersects the following major river basins, from east to west: San Jacinto
River, Brazos River, and Colorado River. This section identifies the streams crossed by the
pipeline and defines the characteristics relevant in comparing stream size, water quality, and
use (i.e., public water supply and irrigation). The Proposed Project crosses 58 streamlines
according to the USGS 1:100,000 hydrography. Thirty-eight of the streams crossed are of
second-order or higher (meaning the streams are downstream of a junction of at least two
streamlines). The pipeline crosses the mainstem of the Brazos River, Colorado River,
Pedernales River, and the Llano River. A number of significant tributaries of these rivers are
also crossed, e.g., the James River (a tributary of the Llano River) and Onion Creek (a tributary
of the Colorado River). Each tributary has a basin area exceeding 200 square miles upstream of
the pipeline. The watersheds upstream of the pipeline for each of the second-order (or higher)
streams crossing the pipeline are delineated in Figure 4.2.2-1. The basin areas of the bayous in
4-26

<<<PAGE 66>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Harris County (White Oak Bayou, Greens Bayou, Halls Bayou, and Hunting Bayou) were not
delineated and are represented in later tables by data collected from nearby flow/water quality
gauges. The crossings are numbered using the Longhorn Pipeline mileposts in increasing order
from east to west.
4.2.2.1.1 Description of Significant Stream Crossings Along Route
The descriptions of individual major streams crossed by the Proposed Project are provided
below. These descriptions include the general uses of these streams as they are stated in the
Texas Water Quality Standards which are codified in Title 30, Chapter 307 of the Texas
Administrative Code. These Standards establish explicit goals for the quality of streams, rivers,
lakes, and bays throughout the state. The Standards identify appropriate uses for the state’s
surface waters, including aquatic life, recreation, and sources of public water supply (or drinking
water). The criteria used by the TCEQ for evaluating support of those uses include dissolved
oxygen, temperature, pH, dissolved minerals, toxic substances, and bacteria.
Greens Bayou. The Proposed Project crosses Greens Bayou in Harris County near MP 7.
Greens Bayou is located within the San Jacinto River Basin and is designated by the TCEQ to
be suitable for primary contact recreation and limited aquatic life use. The water uses do not
include public water supply. Greens Bayou is channelized with sloping banks that contain very
little native vegetation and are mainly covered with Bermuda grass. The water is slow-moving
over a bottom substrate partially composed of gravel and silt.
White Oak Bayou. The Proposed Project crosses White Oak Bayou in Harris County near MP
32. White Oak Bayou is located within the San Jacinto River Basin and is designated by the
TCEQ to be suitable for primary contact recreation and limited aquatic life use. The water uses
do not include public water supply. White Oak Bayou is a completely channelized body of water.
The banks are steeply sloped and covered in Bermuda grass. There is very little native
vegetation near the channel. Water flow is slow but constant.
Cypress Creek. The Proposed Project crosses Cypress Creek in Harris County near MP 47.
Cypress Creek is located within the San Jacinto River Basin and is designated by the TCEQ to
be suitable for primary contact recreation and high aquatic life use. The water uses include
public water supply. Cypress Creek is partially channelized due to the installation of flood
control measures. Vegetation in the vicinity of the creek consists primarily of native cypress, the
creek’s namesake.
Brazos River. The Proposed Project crosses the Brazos River at the Waller-Washington
County line near MP 65. The Brazos River is located within the Brazos River Basin and is
designated by the TCEQ to be suitable for primary contact recreation and high aquatic life use.
The water uses include public water supply. The Brazos River is a slow-moving, meandering
river with turbid water and a silt-dominated substrate. Its tree-lined banks are relatively wide and
steep. The river supports many fish species and is a popular location for recreational fishing.
4-27

<<<PAGE 67>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Colorado River. While passing through Bastrop County, the pipeline crosses the Colorado
River near MP 136. The Colorado River is located within the Colorado River Basin and is
designated by the TCEQ to be suitable for primary contact recreation and high aquatic life use.
The water uses include public water supply. Generally, the Colorado River is a wide and slow-
moving flow over a substrate of silt. The riverbanks are lined with willow, cottonwood, pecan,
elm, and sycamore trees, which help to prevent erosion and provide excellent cover for fish.
Onion Creek. Onion Creek is crossed in Travis County 167. Onion Creek is located within the
Colorado River Basin and is designated by the TCEQ to be suitable for primary contact
recreation and high aquatic life use. The water uses include public water supply and Aquifer
Protection use. The Aquifer Protection use applies to the contributing, recharge, and transition
zones of the Edwards Aquifer. The creek flows through both the Edwards Plateau and the
Blackland Prairies regions. In the Edwards Plateau region, the banks of Onion Creek are
limestone and lined with bald cypress, sycamore, cottonwood, American and cedar elm, and
pecan trees. In the Blackland Prairie natural region, the vegetation remains the same, but the
banks are more erodable due to deeper soils.
Barton Creek. The pipeline crosses Barton Creek in Travis County near MP 184. Barton Creek
is located within the Colorado River Basin and is designated by the TCEQ to be suitable for
primary contact recreation and high aquatic life use. While not designated as a public water
supply, the water uses include Aquifer Protection use. The Aquifer Protection use applies to the
contributing, recharge, and transition zones of the Edwards Aquifer. Barton Creek is spring-fed
with limestone banks and substrate. The creek flows between multiple pools and riffles
throughout its length. The banks are vegetated with bald cypress, sycamore, cottonwood,
American and cedar elm, and pecan trees, and the creek provides good habitat for numerous
fish species.
Pedernales River. The Pedernales River is crossed in Blanco County near MP 202. The
Pedernales River is located within the Colorado River Basin and is designated by the TCEQ to
be suitable for primary contact recreation and high aquatic life use. The water uses include
public water supply. The Pedernales River is generally shallow and flows clear along rocky
banks that are lined with bald cypress and cottonwood trees. Flows of this river can increase
dramatically after a heavy rain.
Llano River. The pipeline encounters the Llano River in Kimble County near MP 281. The Llano
River is located within the Colorado River Basin and is designated by the TCEQ to be suitable
for primary contact recreation and high aquatic life use. The water uses include public water
supply. The river is spring-fed and flows over limestone and gravel substrate, which produces
many small riffles. Limestone banks vary in slope and are lined with trees and dense vegetation.
The river provides excellent habitat for fish with abundant cover and shade. Although the Llano
River produces one of the best fisheries in Texas, it is relatively under-utilized due to limited
access.
4-28

<<<PAGE 68>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.2.2.1.2 Water Quality Downstream of Pipeline Crossings
In the 1999 EA, the surface water quality sampling sites downstream of the Proposed Project
were identified using the EPA database, STORET. Sites were selected which were the closest
to the pipeline crossings and that had significant analyses since 1985. The locations for these
sites are shown in Figure 4.2.2-2. The inorganic and coliform analytical data for each of these
sites were aggregated as averages into Table 4.2.2-1. This table is intended for relative
comparisons of general water quality along the route, and the averaging was performed on the
raw numbers provided in the database. Measurements reported as equal to the analytical
detection limit were included in the averages. Outliers of more than two standard deviations
from the statistical mean were not included in these averages. The STORET database was
reviewed for the period from the year 2000 through 2011 for the same STORET station
numbers provided on Table 4.2.2-1 in the 1999 EA. The only additional surface water analytical
data identified was for TCEQ stations 11576, 12451, 12377, and 14231. Analysis of this data
indicated that there were no significant changes in the average value of the reported
concentrations of the water quality parameters monitored versus those presented in the 1999
EA for the same station numbers. Table 4.2.2-1 is modified to include this updated data.
An important aspect of the water quality concerns is the water bodies that have been identified
by the TCEQ to be impaired. In this regard, the TCEQ maintains what is referred to as a Total
Maximum Daily Load (TMDL) Program that is authorized by and created to fulfill the
requirements of Section 303(d) of the Federal Clean Water Act and its implementing
regulations. The TMDL Program was developed with the purpose of improving the water quality
in rivers, lakes, and estuaries in the state. TMDLs are developed for surface waters that are
impaired, i.e., quality limited, due to a pollutant or adverse condition. Based on the
environmental target in the TMDL, the state develops an implementation plan (IP) to mitigate
sources of pollution within the watershed and restore impaired uses. A TMDL is like a budget for
pollution, i.e., determining the extent to which pollutant concentrations must be reduced to meet
quality standards.
An IP usually puts the TMDL into action by outlining the steps necessary to reduce pollutant
loads through regulatory and voluntary activities. In some instances, TMDLs are implemented
through watershed protection plans (WPPs). Since the time that the 1999 EA was prepared,
there have been changes in the surface waters that have been designated as being subject to
TMDLs. Certain streams have been added, removed, and in some cases remain subject to the
303(d) requirements.
A summary of 303(d)-listed stream segments that are located within the zone of potential impact
along the Proposed Project is provided on Table 4.2.2-2. This table also provides the year that
the segment was first listed and the type of impairment that caused it to be listed. None of these
303(d)-listed segments are impaired due to the presence of petroleum hydrocarbons. Figures
4.2.2-3, 4.2.2-4, and 4.2.2-5 depict the locations of these segments.
4-29

<<<PAGE 69>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.2.2.1.3 Identification of Downstream Water Users
The 1999 EA identified potentially vulnerable surface water resources along the Longhorn
Pipeline and quantifies their relative importance and vulnerabilities. This information is relatively
unchanged in this FEA. Since the time the 1999 EA was prepared, the TCEQ has prepared
Source Water Susceptibility Assessment (SWSA) reports for every public water supply in the
State as required by the 1996 SDWA Amendments. The SDWA Amendments required all states
to assess the susceptibility of public drinking water sources to contamination. The TCEQ
provided the results of the assessments to each PWS in 2003. These comprehensive SWSA
reports represent years of research, analysis, and investigation by state officials, trade
organizations, federal, state and local agencies, and water service providers. The assessments
contain information specific to each PWS, its source waters, and areas of concern which may
impact source waters. The information is intended to enhance the ability of a PWS to protect its
source waters and ensure their continued reliability. Within the context of the FEA, the SWSA
program did take into consideration potential impacts associated with petroleum pipelines such
as the Longhorn Pipeline.
The TCEQ and the USGS developed procedures to assess the susceptibility of PWS source
waters to 227 selected drinking-water contaminants. The procedures, as implemented in
automated software, enable TCEQ staff, PWSs, and others to (1) identify the most susceptible
PWSs on which to focus source-water protection efforts, (2) reduce monitoring costs associated
with ensuring safe drinking water, (3) enhance public understanding of source-water protection,
and (4) identify land-management practices needed to protect source waters.
A surface water susceptibility assessment for a PWS has eight components. Several of the
components result in relative susceptibility ratings of high, medium, or low. These ratings are
designed to support an overall susceptibility rating for the PWS sources and system. The
components are:
1. Identification Component - determination of hydrologic attributes (for example,
topography and drainage network) used to delineate the area(s) that potentially
contribute source water for a PWS.
2. Delineation Component - delineation of PWS source area(s) based on attributes
determined by the identification component.
3. Intrinsic Susceptibility Component - determination of the intrinsic attributes (for
example, soil erodibility or mean annual runoff) within PWS source areas and evaluation
of their potential to make the PWS more or less susceptible to contamination. This
component produces a relative susceptibility rating for all contaminants.
4. Nonpoint-Source Susceptibility Component - determination of statistical relations
between measured contaminants in surface water and watershed characteristics (for
example, land use or pesticide use) within PWS source areas. Statistical model results
will determine the probability that a drinking-water contaminant will exceed a TCEQ-
specified threshold concentration. In cases of few or no data, a relative susceptibility
4-30

<<<PAGE 70>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
rating is assigned and is based on the frequency of contaminant detection or level of
land-use activities within the PWS source area associated with contaminant production
or use.
5. Point-Source Susceptibility Component - determination of potential point sources of
contaminants to the PWS. A relative susceptibility rating is produced for each
contaminant and is based on the permitted discharges from known point-source
locations (for example, oil refineries). Estimates of contaminant concentrations at low
streamflow will be calculated from permitted releases from point sources within the PWS
source area. A relative susceptibility rating is assigned to each contaminant and is based
on the ratio of total permitted releases to mean annual streamflow.
6. Area of Primary Influence (API) Component - determination of the proximity of a
potentially adverse land use (for example, pipeline or railroad). An analysis is performed
for the potential contaminants associated with the potentially adverse land use that is
within a limited area (2-hour travel or 1,000-foot buffer) around the PWS surface water
intake (or reservoir). A relative susceptibility rating is produced for each contaminant and
is based on number, type, size, and location of the potentially adverse activities in the
PWS source area.
7. Contaminant Occurrence Component - determination of contaminant detections (at or
greater than TCEQ specified threshold concentrations) at water-quality monitoring sites
or other nearby PWS. A relative susceptibility rating of “high” is assigned to the
contaminant if it has been detected greater than the threshold concentration at a nearby
site. No relative susceptibility rating is assigned to the contaminant if it has not been
detected greater than the contaminant threshold concentration.
8. Susceptibility Summary Component - combination of the seven components into a
summary relative susceptibility rating for each PWS source and a single summary rating
for the PWS.
For this assessment, the locations of PWS were obtained from the May 2011, version of the
TCEQ SWSA Viewer files. The viewer contains the spatial datasets used and created during a
source water susceptibility assessment process that was conducted by the TCEQ. These files
were then imported into the GIS database depicting the location of the Proposed Project and the
zone of potential impact. The exact locations of all PWS intakes with an API within the zone of
potential impact were then identified and included in this FEA. Based upon this database, the
only API located within the zone of potential impact is the surface water intake for the
Pedernales Falls State Park (PWS ID No. 0160004) located on the Pedernales River. Figure
4.2.2-6 depicts this API boundary and the location of State Park water intake. This intake is 3.58
stream miles from the Proposed Project crossing of the Pedernales River. Figure 4.2.2-7
identifies three petroleum pipelines, including the Proposed Project that cross the Pedernales
River. An assessment was performed by the TCEQ for the API of the Pedernales Falls State
Park water supply system. The findings of the TCEQ assessment are as follows:
4-31

<<<PAGE 71>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Pedernales Falls State Park Water System
The SWSA susceptibility ratings are divided into three divisions: “High”, “Medium”, and “Low”. In
the case of the Pedernales Falls State Park, the potential for contamination from volatile organic
chemicals (i.e., the category that would include oil pipelines) was rated as being “Medium”. The
meanings of the SWSA ratings are provided below:
“High” susceptibility means there are activities near the source water and the natural
conditions of the aquifer or watershed make it very likely that chemical constituents may
come into contact with the source water. It does not mean that there are any health risks
present.
“Medium” susceptibility means there are activities near the source water and the natural
conditions of the aquifer or watershed make it somewhat likely that chemical constituents
may come into contact with the source water. It does not mean that there are any health
risks present.
“Low” susceptibility means there are activities near the source water and the natural
conditions of the aquifer or watershed make it unlikely that chemical constituents may
come into contact with the source water.
The API boundary for the headwaters of Lake Travis are located 6.1 stream miles downstream
of the Proposed Project and the Mansfield dam is located 66.1 stream miles from the pipeline.
Besides Pedernales Falls State Park, there are currently 10 water supply users located within
Lake Travis and downstream of this stream crossing (see following table).
PWS Name
Miles Downstream of
Pedernales Stream
Crossing
Lago Vista 39.8
Village of Briarcliff 40.3
Travis County Municipality Utility District
(MUD) 10 43.4
4-32

<<<PAGE 72>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
PWS Name
Miles Downstream of
Pedernales Stream
Crossing
47.1
50.4
50.9
51.6
52.0
55.7
62.2
Inverness Point Lakeway MUD Hurst Creek MUD Travis County WCID Point Venture Lakeway MUD Travis County Water Control and
Improvement District (WCID) 17 Sail Haven City of Austin Water Treatment Plant
(WTP) No. 41 64.7
1 The City of Austin is in the process of constructing Water Treatment Plant No. 4.
Lake Austin is located downgradient of Lake Travis and upgradient of Lady Bird Lake. The
length of this segment is 20.25 stream miles and starts at Mansfield Dam and ends at the Tom
Miller Dam. There are nine water supply intakes from Lake Austin including private and public
water supplies. The only avenue of contaminants to Lake Austin from the Longhorn Pipeline
would be through the Mansfield Dam. This is due to the fact that there is no other hydrologic
connection between the Longhorn Pipeline and Lake Austin. The discharge through Mansfield
Dam is a controlled release below the water surface that flows through a hydroelectric
generator. Any impacts to Lake Austin would likely to be associated with dissolved constituents.
The concentrations of any dissolved constituents, most likely benzene, would be expected to be
below levels of human health concern for any of these nine water supply intakes. Accordingly,
both the 1999 EA and this FEA make the assumption that there would be no harmful impacts to
Lake Austin as a result of a pipeline release.
Although located outside of the zone of potential impact, the API for Hill Country Springs is
located on Slaughter Creek at a point 1.42 miles beyond the zone of potential impact and its
water supply intake is located 8.2 miles downstream. Because of this, the Hill Country Springs
water supply intake was added to the list of stream crossings ranked in terms of resource
importance.
In the 1999 EA, potential water users downstream of the pipeline were identified using the
TCEQ Water Rights Database (as available from TNRIS). This information is provided in Table
4.2.2-3. For this FEA, the TCEQ Water Rights Database File was downloaded and compared to
the data presented in the 1999 EA for the period from the year 2000 through June 2011. For this
period, there were 744 additional water rights added to the database. This list was modified to
retain those water rights evaluated in the 1999 EA (municipal/domestic, industrial, mining,
irrigation, and recreation). The list was further modified to delete those water right amendments
included in the 1999 EA, the water rights on the Highland Lakes that were already addressed as
APIs, and water rights terminations. The remaining water rights were systematically reviewed
for their locations downstream of the pipeline crossing. No other water users besides those
4-33

<<<PAGE 73>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
categories addressed above were noted in the remaining water rights listed in the TCEQ Water
Rights Database.
The TCEQ database of public surface water supplies identifies numerous additional water users
downstream of the pipeline. In the 1999 EA, the locations for these public water users were
imported into the study area mapping, were edited to contain only users downstream of the
pipeline, and were identified in Figure 4.2.2-1 with a symbol designating the water use. This
database was the source for the identification of the location of the numerous water users
contiguous to the Highland Lakes. For this FEA, the locations of public water supply intakes
were reviewed for their proximity of their API to the zone of potential impact. The water intake
on Slaughter Creek for Hill Country Springs was added to the list of downstream water supplies
due its close proximity to the zone of potential impact.
The 1999 EA identified the closest surface water supply source to a pipeline stream crossing as
being the small water right (30 acre-ft) for Pedernales Falls State Park. The next closest surface
water supply is that of the Hill Country Springs located on Slaughter Creek approximately 8.2
miles from the zone of potential impact. This water supply was not addressed in the 1999 EA.
The next closest water rights are on the Llano and San Saba rivers and consist of the municipal
water use for the communities of Llano and Menard. There is also a large municipal water right
on the Brazos River held by the Galveston County Water Authority about 50 miles downstream
of the pipeline crossing of the Brazos River. As noted above, the Highland Lakes and Lady Bird
Lake (formerly Town Lake) are the major water supply source for numerous communities along
the lakes. The distance from the lakes (that is, the centerlines of Lake LBJ, Lake Travis, or Lady
Bird Lake) to the closest pipeline stream crossing ranges from about 26 to 35 miles.
In addition, there are a number of shallow public water supply wells located downstream of the
pipeline in stream/river alluvium. These include: 24 wells between Lady Bird Lake and the
pipeline crossing over the mainstem of the Colorado River, within the river alluvium. One of
these is along Dry Creek about eight miles downstream of the pipeline crossing. These shallow
wells are hydrologically connected to surface water and therefore would be at a higher risk in
the event of a pipeline spill.
4.2.2.2 Surface Water Resources, Including Vulnerable Areas
The purpose of this section is to identify vulnerable surface water resources along the pipeline
route. The focus of this evaluation is water supplies, both public water supplies and irrigation
supplies, along the route. Recreational, biological, and cultural resources associated with water
are discussed in Sections 4.1, 4.3, and 4.4, respectively.
4.2.2.2.1 Data Sources
In the 1999 EA, the primary data sources for the identification of vulnerable surface water
resources were: (1) hydrologic and water quality data available from water resource agencies,
(2) water rights data maintained and assembled into a spatial database by the TCEQ, (3)
available topographic mapping, (4) regional water studies for various water resources along the
4-34

<<<PAGE 74>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
pipeline route, and (5) data provided by interested parties, including comments provided on the
draft Longhorn EA.
The result of this research was a spatial database that includes the following layers:
• 1:100,000 scale streamlines (hydrography);
• Vulnerable geology affecting surface-water transport (karst area contributing and
recharge zone boundaries);
• Delineations of watershed areas draining to pipeline crossings;
• Identification of downstream water rights for a variety of uses (primarily municipal,
irrigation, mining, and industrial);
• Identification of public water supply sources downstream of the pipeline stream
crossings;
• Identification of water quality sampling stations on streams downstream of pipeline
stream crossings; and
• Identification of impaired stream segments downstream of the pipeline crossings per the
Federal Clean Water Act Section 303(d).
4.2.2.2.2 Identification of Surface Water Vulnerability to Spills
This section provides an assessment of the vulnerability of surface water to spills along the
pipeline route. The assessment considers surface water vulnerability to be a function of:
• Spill mobility;
• Ability to contain and remediate a spill; and
• Relative importance of potentially impacted surface waters.
For each of these three considerations, the entire pipeline route was assessed for relative
vulnerability at each pipeline stream crossing location. The relative vulnerabilities at these
locations were assigned a level of impact using a separate rating system for each of the three
types of vulnerability evaluated. Once the relative vulnerabilities were assigned for each pipeline
stream crossing, a cumulative vulnerability of each pipeline stream crossing location was
calculated by adding the vulnerability rating from all three considerations. The total vulnerability
scores were then ranked based upon their combined score, with the lowest total scores
representing the highest assigned vulnerability. Figure 4.2.2-8 illustrates the ranking
methodology to determine vulnerability.
4.2.2.2.2.1 Spill Mobility
The pipeline stream crossings were ranked on a scale of 1 (highest) to 6 (lowest) for their ability
to transport a spill. The factors considered in this FEA with regard to spill movement are the
pipeline location relative to the regional occurrence of rainfall, size of river and stream
crossings, the size of the watersheds where the stream crossing occurs, and the stream flow
during flood conditions. A discussion of these ranking factors is provided in more detail below:
4-35

<<<PAGE 75>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Regional Occurrence of Rainfall
As was the case in the 1999 EA, annual rainfall across the pipeline length varies by over a
factor of three, with over 48 inches of annual rainfall in Houston, over 32 inches of annual
rainfall in Austin, and about 16 inches of annual rainfall in Crane. Watersheds in east Texas
have significantly larger base flows than watersheds of a similar size in west Texas, which
typically only flow seasonally. Streams west of the Llano River basin have small base flows and
median flows, and can generally be considered to have less transport power, regardless of
tributary basin area upstream of the pipeline, than watersheds to the east.
Size of River and Stream Crossings
Major Crossings
At major river and stream crossings in central and east Texas, where there are
significant base flows, spills are transported more quickly than for the bulk of the pipeline
crossings. Several large rivers and tributaries (stream order greater than third-order)
occur in this region (Colorado River, Brazos River, Llano River, Pedernales River,
James River, and Onion Creek). These streams were given a ranking of 1 in the 1999
EA. The ranking system provided in the 1999 EA remains valid and is adopted in this
FEA.
Minor Crossings
As noted in the 1999 EA, there are 12 third-order and above streams in the east/central
region (i.e. between MP I – 250) that are likely to have relatively more transport power
than lesser streams. These streams were given a ranking of 2 in the 1999 EA. The
ranking provided in the 1999 EA remains valid and is adopted in this FEA.
Mean Annual Flood
The remaining streams (west Texas streams and second order and below streams in
east/central Texas) are ranked by mean annual (two-year) flood. This flood can be estimated by
Texas hydrologic region, and watershed parameters (basin area, basin shape factor, and basin
slope). Those with relatively high, medium, medium-low, and low two-year floods were assigned
rankings of 3, 4, or 5; respectively. The resulting ranking of streams in terms of relative ability for
a spill movement is summarized in Table 4.2.2-4. Seventeen of the 56 total streams for the
Longhorn Pipeline segment from East Houston to Crane were rated based upon characteristics
such as basin size, “major crossing,” and high stream order rather than upon actual stream
flows. On average, the major streams had a flow of greater than 20,000 cubic feet per second
and high stream order water bodies had a flow of approximately 2,500 cubic feet per second.
Minor changes in these stream characteristics resulted from the recalculation of the 2-year flood
flows based upon updated data. Six of 56 streams in this table are listed as having the highest
ability to transport. All six of these listings are based upon the characteristic described as “major
crossing” on Table 4.2.2-4.
4-36

<<<PAGE 76>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.2.2.2.2.2 Ability to Contain and Remediate a Spill
In the 1999 EA the pipeline stream crossings were ranked on a scale of 1 (most difficult to
remediate) to 6 (least difficult) based on the degree of difficulty associated with the control and
remediation of spills to surface water bodies along the pipeline route. For purposes of
consistency, this same methodology is used in this FEA. The factors used in the ranking are as
follows:
Location on Main Stem
Mainstems have substantially higher flows (greater transport power) and a greater
volume of streambed and bank alluvium (providing greater pore volume for contaminant
storage). These major crossings are assigned a vulnerability of 1.
Location on Karst Aquifer
Stream crossings within karst aquifers having a high DRASTIC Index (as described in
Section 4.2.1.2.2) are assigned a vulnerability ranking of 1 because of the extreme
difficulty in remediating or preventing pollutant spread in these formations. Along this
pipeline route, the Edwards/Balcones contributing zone falls into this category.
Location Near Karst Aquifer or On Alluvium
Stream crossings near karst aquifers that have a high DRASTIC Index or are located on
vulnerable alluviums are assigned a vulnerability ranking of 2 because of the relative
difficulty in remediating or preventing pollutant spread in these formations. Along the
pipeline route these ranking includes those stream crossings that are near the
Ellenburger-San Saba aquifer and those that are on the Colorado River Alluvium.
Location Proximity to Main Stem
In the absence of other considerations as discussed above, the vulnerability of a water
body to a pipeline crossing is assumed to decrease as the distance of the location of the
spill increases. Stream crossings that are located within two miles of a main stem are
assigned a vulnerability of 2, crossings located 3 to 10 miles from a main stem are
assigned a vulnerability of 3, crossings within 10-20 miles of a stem are assigned a
vulnerability of 4, crossings within 20-30 miles of a stem are assigned a vulnerability of
5, and crossings greater than 35 miles from a stem are assigned a vulnerability of 6.
Table 4.2.2-5 provides the ranking of streams in terms of relative ability to control a spill.
4.2.2.2.2.3 Relative Importance of Potentially Impacted Surface Waters
In the 1999 EA, municipal water supply sources, which require water of a higher quality than
needed for other uses (e.g., mining, industrial, and irrigation), were considered more vulnerable
than other sources. Because human health is a prime concern, they were also considered
relatively more important than other sources, particularly where the source is the prime source
for consumption. This FEA adopts the same methodology as was used in the 1999 EA. Table
4.2.2-6 provides a ranking of the pipeline stream crossings on a scale from 1 (most important) to
4-37

<<<PAGE 77>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
6 (least important) in terms of the importance of the water resource downstream. The ranking
criteria are summarized in the table below:
Ranking Basis
1
Within approximately 15 miles of Colorado
Alluvium; or within 40 miles of Highland Lakes; or
Alluvial Public Well within two miles
2 Municipal water right within 75 miles; or within 75
miles of Highland Lakes
3 Large irrigation water right within 20 miles
downstream
4
Small irrigation right within 20 miles downstream or
Colorado River Alluvium between 40 to 75 miles
downstream
5 Small water right within 40 to 60 miles downstream
or poor water quality
6 Small irrigation within 40 to 60 miles
7 No uses identified
4.2.2.2.3 Summary Ranking of Stream Vulnerabilities
The rankings for each crossing performed in the preceding section were assembled into a
summary table, Table 4.2.2-7. The rankings for each crossing were summed and then sorted,
so that the lowest sum is shown at the top of the table. The “sum of ranks” value of 3 represents
the crossings most vulnerable to a spill. The crossings listed thereafter in the table are
progressively less vulnerable.
As noted above, these rankings do not include an evaluation of the recreational, biological, and
cultural resource characteristics of each stream crossing, since these issues are addressed in
Sections 4.1, 4.3, and 4.4, respectively.
4.2.2.3 Wetlands
An inventory of wetlands present within the zone of potential impact from East Houston to Crane
shows that 2,898 wetlands, consisting of approximately 5,852 acres, are present. This inventory
also shows a total of approximately 449 stream locations accounting for approximately 121.2
miles or 642,048 linear feet.
The U.S. Fish and Wildlife Service (USFWS) National Wetland Inventory (NWI) maps were
evaluated through GIS to determine specific numbers (density per linear mile), types, and aerial
extent of wetlands that are located within the zone of potential impact. Digital NWI maps at a
scale of 1:24,000 were used for wetland identification in Harris County to approximately 55
miles west. Scanned and digitized NWI maps at a scale of 1:100,000 were used for the
remaining of the pipeline from MP 55 to Crane. The digital NWI maps used at a scale of
4-38

<<<PAGE 78>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
1:24,000 portray all wetland data in a polygon, including stream segments. The scanned NWI
maps at 1:100,000 do not have polygons for stream segments. Results of these stream
segments from MP 55 and westward are provided in the table below and Table 4.2.2-8 for the
entire route from East Houston to Crane and were used in this evaluation.
The Proposed Project from the East Houston Terminal to the Crane Terminal is within 1,250
feet or within the overland flow boundary of three different wetland types: riverine, palustrine
and lacustrine. The greatest concentration of wetlands along the pipeline (approximately 13.7
per linear mile) is located between MP 20 and MP 160, which includes western Harris County,
Waller County, Austin County, Fayette County, Bastrop County, and eastern Travis County. The
density of wetlands (per linear mile) decreases to a range of approximately 5 per linear mile
between MP 160 and MP 280, which includes western Travis, Hays, Blanco, Gillespie, Llano,
Mason and Kimble Counties. West of Kimble County to Crane, the density of wetlands
decreases steadily to an average of 1.3 per mile.
By using GIS and NWI maps, the aerial extent of wetlands were calculated for each type of
wetland where a polygon was located within the zone of potential impact. Rivers and streams
where a line was used in GIS rather than a polygon was measured in total miles/linear feet
crossed within the zone of potential impact. The following table summarizes these acreages and
miles of each wetland.
Wetland Polygons Wetland Lines
Wetland Classification Count Acres Count Miles
Intermittent 10 20.1 383 113.32
Lacustrine Open Water 5 34.0
Lacustrine Unconsolidated Bottom 2 41.9
Lacustrine Unconsolidated Shore 1 23.81
Lower Perennial 107 533.7 62 6.67
Palustrine Aquatic Bed 6 13.7
Palustrine Emergent 613 2877.2
Palustrine Forested 941 1179.1
Palustrine Open Water 520 295.3 2 1.08
Palustrine Scrub-shrub 107 293.3
Palustrine Unconsolidated Bottom 295 225.2
Palustrine Unconsolidated Shore 291 314.6 2 0.19
Total 2,898 5,851.9 449 121.16
The wetlands identified within the zone of potential impact are compiled by MP and county and
presented on Table 4.2.2-8.
4.2.3 Geologic Hazards
The geologic hazards (geohazards) discussed in this section are limited to earthquake/seismic
hazards, landslide/mass movement hazards, soil stress-induced hazards (shrink-swell),
4-39

<<<PAGE 79>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
subsidence associated with active faulting in the Gulf Coastal Plain, and erosion (scour) at
stream crossings.
4.2.3.1 Earthquake/Seismic Hazards
There is no appreciable difference between the findings of this section and those presented in
the 1999 EA. Therefore, Section 4.2.3.1 (Earthquake/Seismic Hazards) of the 1999 EA is
included by reference in this FEA.
(See http://www.epa.gov/region6/6en/xp/longhorn_nepa_documents/lppchap4.pdf)
4.2.3.2 Landslide/Mass Movement Hazards
There is no appreciable difference between the findings of this section and those presented in
the 1999 EA. Therefore, Section 4.2.3.2 (Landslide/Mass Movement Hazards) of the 1999 EA is
included by reference in this FEA.
(See http://www.epa.gov/region6/6en/xp/longhorn_nepa_documents/lppchap4.pdf)
4.2.3.3 Faulting/Subsidence Hazards
Aseismic faulting occurs in the Houston metropolitan area. It is considered aseismic because
the movements are too small and too frequent to cause measurable earth tremors. The faulting
is primarily due to consolidation of unconsolidated marine soils as water and petroleum products
are pumped from these materials. As pore water pressures decrease in these formations due to
pumping, the effective overburden stress increases resulting in consolidation. The result of the
consolidation is seen at the ground surface as subsidence defined by movement across small
faults.
Review of elevation data from 1906 to 2000 indicates total subsidence on the order of 7 ft in the
area of the pipeline (Harris Galveston Subsidence District http://mapper.subsidence.org/). This
area of magnitude occurs along the pipeline over a distance of approximately 55 miles within
the Houston metropolitan area (Harris Galveston Subsidence District
http://mapper.subsidence.org/). Movements of this magnitude over such a distance will not pose
a threat to the integrity of the pipeline.
The Proposed Project crosses several faults between East Houston/Galena Park and Crane.
None of the faults west of Harris County are known to be active. Within Harris County, the
pipeline crosses three aseismic faults, at five separate locations, that are considered to be
active. Selected faults in Harris County have been monitored since March 2004 in accordance
with the Operational Reliability Assessment. The data collected and analyzed indicate no
measurable movement over time on two of the faults (Melde and Breen faults), with only slight
movement of 0.06 inches over the last 5½ years for the Akron fault and -0.08 inches during the
same period for the Hockley fault.
4-40

<<<PAGE 80>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.2.3.4 Soil Stress Hazards
There is no appreciable difference between the findings of this section and those presented in
the 1999 EA. Therefore, Section 4.2.3.4 (Soil Stress Hazards) of the 1999 EA is included by
reference in this FEA.
(See http://www.epa.gov/region6/6en/xp/longhorn_nepa_documents/lppchap4.pdf)
4.2.3.5 Scour at Stream Crossings
The process of scour, or washout, may occur at stream crossings typically during a flood event
and pose a geologic hazard to a pipeline. The scour could remove the depth of cover, expose
the pipe, and/or remove needed support from the pipe, thereby threatening the integrity of the
pipeline. Conditions which affect the scour potential include topography, stream velocity, soil
conditions, grain size, depth of cover, and pipe position. If specific conditions exist common to a
flood event such as high stream velocity and absence of cover, the pipeline could float up into
the stream flow and be exposed to flood velocity-induced stresses causing a leak.
The Proposed Project crosses a total of 63 streams. Some stream crossings are elevated over
the stream, while most are subsurface and buried under the stream bed. An extensive study
(Longhorn Pipeline Stream Crossing Study: A summary of Stream Scour Potential and Potential
for Pipeline Failure, April 7, 2000) was conducted in 2000 to evaluate scour and erosion
potential during flooding at all stream crossings along the pipeline. Stream crossings were
evaluated by their hydrologic and hydraulic characteristics, history of scour-related leaks,
evidence of channel instability, and other physical characteristics. Fifteen crossings were
selected for detailed, site-specific analysis. These included the six major river crossings (Brazos
River, Colorado River, Onion Creek, Pedernales River, Llano River, and Pecos River), four
crossings identified by an aerial photographic analysis (JD Creek, Long Branch, Barton Creek,
and Sandy Creek at MP 236.7), all hypersensitive (Tier 3) crossings with alluvial (as opposed to
rock) streambeds (Marble Creek, Boggy Creek, Slaughter Creek), and all sensitive (Tier 2)
crossings identified as potentially having excessive flood velocities (Alum Creek). The Rabbs
Creek and Cedar Creek crossings, which were known from earlier observation to be unstable,
were also studied as part of the remedial design process.
The studies identified recommended mitigation efforts to reduce the likelihood of damage to the
pipeline as a result of scour. Furthermore, the measures identified in the LMP are designed to
maintain and proactively identify areas of shallow or exposed pipe at all stream crossings
through regular inspections and aerial surveys.
4.2.4 Climate and Air Quality
4.2.4.1 Climate
The findings of this section are identical to those presented in the 1999 EA. Therefore, Section
4.2.4.1 (Climate) of the 1999 EA is included by reference in this FEA.
4-41

<<<PAGE 81>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
(See http://www.epa.gov/region6/6en/xp/longhorn_nepa_documents/lppchap4.pdf)
4.2.4.2 Air Quality
The EPA has established National Ambient Air Quality Standards (NAAQS) for six “criteria” air
pollutants: ozone (O3), particulate matter (PM), nitrogen dioxide (NO2), sulfur dioxide (SO2),
carbon monoxide (CO), and lead (Pb). NAAQS have been developed for two forms of PM: PM
with a diameter of 10 micrometers (µm) or less (PM10) and PM with a diameter of 2.5 µm or less
(PM2.5), which is sometimes referenced as “fine” PM. EPA has designated these pollutants as
criteria air pollutants because it regulates them by developing human health-based and/or
environmentally-based criteria (science-based guidelines) for setting permissible levels.
The sources of the criteria air pollutants are varied. Ozone is not usually emitted directly into the
air, but is formed at ground-level through a series of complex reactions between oxides of
nitrogen (NOx) and volatile organic compounds (VOC) – ozone precursors – in the presence of
sunlight. In the earth's lower atmosphere, this ground-level ozone, at elevated concentrations, is
harmful to human health. Motor vehicle exhaust and industrial emissions, gasoline vapors, and
chemical solvents as well as natural sources emit NOx and VOC that help form ozone. PM is
emitted directly from a variety of sources and is also formed in the atmosphere through
chemical processes. PM is a complex mixture of small solid particles and liquid droplets that
may be composed of a number of constituents, including acids (e.g., sulfates and nitrates),
organic compounds, metals, and soil or dust particles. NO2 is an indirect product of combustion
processes that quickly forms in the atmosphere from emissions from cars, trucks and buses,
power plants, and off-road equipment. In addition to contributing to the formation of ground-level
ozone, as well as fine PM, NO2 is linked with a number of adverse effects on the respiratory
system. SO2 is a direct product of the refining and combustion of fossil fuels (e.g., coal and oil)
that contain sulfur as a natural component. CO is a colorless, odorless gas emitted as a
byproduct of combustion processes (e.g., mobile sources and power plants). The most
significant sources of lead emissions have historically been motor vehicles (more specifically,
the lead additives in vehicle fuels) and industrial sources (e.g., lead smelters).
County or multi-county regions of a state, such as Texas, where measured ambient levels of a
criteria pollutant exceed a NAAQS (based on a statistical analysis of the data) are considered to
be in “nonattainment” of that pollutant’s NAAQS, and are formally designated as nonattainment
areas. Knowledge of the attainment/nonattainment status of an area can provide a
representative description of the air quality in that area. The current attainment/nonattainment
status of each geographic area of Texas through which the Proposed Project (Crane to East
Houston) traverses is discussed below.
In addition to the above-described, historically-regulated criteria pollutants, EPA now regulates
“greenhouse gases” (GHGs). The six key GHGs are carbon dioxide (CO2), methane, nitrous
oxide, hydrofluorocarbons, perfluorocarbons, and sulfur hexafluoride. Air quality permitting is
required for GHG emissions from the nation’s largest GHG sources, most notably power plants,
refineries, and cement production facilities.
4-42

<<<PAGE 82>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
For this assessment, the primary GHGs of concern are CO2, resulting from fuel-burning in
construction equipment, and methane, resulting from the transport/storage of crude oil.
Emissions of these GHGs are being estimated (and presented in this FEA) for anticipated
construction and operational activities associated with the Proposed Project and Connected
Actions. Note that, unlike for the criteria pollutants, there are no ambient monitoring programs
for GHGs that could be used to establish current background levels in the atmosphere.
Southeast Texas
The Houston-Galveston-Brazoria area (comprised of Brazoria, Chambers, Fort Bend,
Galveston, Harris, Liberty, Montgomery, and Waller Counties) in southeast Texas is designated
a “severe” nonattainment area for the 8-hr ozone NAAQS2 (40 CFR 81.344). As a result, this
area has an EPA-imposed attainment deadline of June 2019. Except for the ozone
nonattainment designation for the Houston-Galveston-Brazoria area, southeast Texas is
designated to be in attainment of the NAAQS for all other criteria pollutants. However, since
promulgation of the 8-hr ozone NAAQS in 1997, exceedances of the standard have been
measured (as recently as 2010) at one or more ambient monitors in the Beaumont-Port Arthur
area (comprised of Hardin, Jefferson, and Orange Counties), which currently is not formally
designated as an ozone nonattainment area (see TCEQ website http://www.tceq.state.tx.us/cgi-
bin/compliance/monops/8hr_attainment.pl). Note that a 3-year average, as opposed to
individual 8-hr measurements, that exceeds the NAAQS for ozone is required in order for a
region to receive the nonattainment designation.
South Central Texas
South Central Texas is currently in attainment of the NAAQS for all criteria pollutants (40 CFR
81.344), although exceedances of the ozone NAAQS have been measured at one or more
ambient monitors in the Austin and San Antonio metropolitan areas in recent years (see TCEQ
website http://www.tceq.state.tx.us/cgi-bin/compliance/monops/8hr_attainment.pl). Therefore,
despite the current attainment designation, ozone levels are currently a concern in both areas.
West Texas
West Texas is currently in attainment of the NAAQS for all criteria pollutants (40 CFR 81.344),
primarily because this region has relatively little industrial development and a low population
density. Based on these factors, air quality does not appear to be a concern in this region.
2 In July 1997, EPA stipulated an 8-hour NAAQS for ground-level ozone of 0.08 parts per million (ppm). The EPA
phased out and replaced the previous 1-hour standard with this 8-hour standard to protect public health against
longer exposure to this pollutant. In March 2008, the EPA revised the 8-hour NAAQS for ozone, lowering it to 0.075
ppm. However, EPA’s formally-designated attainment/nonattainment status for ozone is based on the originally-
promulgated NAAQS.
4-43

<<<PAGE 83>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.3 ECOLOGICAL RESOURCES
Ecological resources pertain to biomes (communities of living organisms of a single major
ecological region), flora and fauna, and threatened and endangered (T&E) species that could be
affected by pipeline operations, maintenance, or an accidental release of crude oil. The
following sections describe natural regions, vegetation, aquatic biology, and terrestrial biology.
The information presented was obtained primarily from the USFWS and the TPWD.
This assessment considers all federal and state listed threatened or endangered species and
federal listed candidate species that are known to be within counties that are crossed by the
pipeline from East Houston to Crane. The list provided in Table 4.3.1-1 includes 67 threatened
or endangered species and 3 candidate species. Table 4.3.1-1 is compiled from the Annotated
County List of Rare Species from both TPWD and USFWS.
4.3.1 Terrestrial Resources
Natural Regions Traversed by the Proposed Project from East Houston to Crane
The TPWD lists 11 natural regions within the state (TPWD, 1978), of which four are crossed by
the Proposed Project from East Houston/Galena Park to Crane. The regions crossed, listed
from east to west, are: Gulf Coast Prairies and Marshes, Blackland Prairies, Oak Woodlands
and Prairies, and Edwards Plateau (see Figure 4.3.1-1). The pipeline also crosses the “Lost
Pines” subregion of the Oak Woodlands and Prairie natural region. These regions are
summarized in the following text.
Gulf Coast Prairies and Marshes
Harris and Waller counties are located at the northern edge of the Gulf Coast Prairies and
Marshes natural region that extends inland approximately 50 miles. The area exhibits little
topographic relief and is comprised of sluggish rivers, creeks, bayous, swamps, and freshwater
marshes. Climax vegetation in the area is principally grassland (tall-grass prairie) and post oak
savannah; however, much of the area has been invaded by trees and brush such as mesquite
(Prosopis glandulosa), live oak (Quercus virginiana), prickly pear (Opuntia spp.), and several
species of acacias. Dominant grasses include big bluestem (Andropogon gerardi), eastern
grama (Tripsacum dactyloides), gulf muhly (Muhlenbergia capillaris), and several species of
panicum. Portions of the natural region crossed by the pipeline extend from MP 0.0 to MP 71.2,
as shown on Figure 4.3.1-1.
Blackland Prairies
The Blackland Prairies natural region consists of two relatively narrow zones separated with
zones of oak woodlands and prairies. The eastern portion of the region extends from the Gulf
Coast Prairies and Marshes at MP 71.2; the western extent of the Blackland Prairies region lies
along the eastern margin of the Balcones Escarpment and the Edwards Plateau natural region
(MP 167.2). A relatively narrow band of Oak Woodlands and Prairies natural region crosses the
Blackland Prairies region from MP 105.8 to MP 148.9. Regional topography of the Blackland
Prairies region is characterized as gently rolling prairies dissected by well-defined streams and
drainages. Tall-grass communities dominate the native vegetation within the region, and post
4-44

<<<PAGE 84>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
oak (Quercus stellata) and blackjack oaks (Quercus marilandica) are common. Important grass
species include hairy grama (Bouteloua hirsuta) and dropseed (Sporobolus spp.).
Oak Woodlands and Prairies
The Oak Woodlands and Prairies natural region (also known as the Cross Timbers and Prairies
Vegetational Area) supports a wide variety of flora and fauna species. The region consists of
woodlands dominated by oaks and hickories, interspersed with a mosaic of prairie. Dominant
woody species include post oak and blackjack oak; however, cedar elm (Ulmus craassifolia)
and pecan (Carya illinoinensis) are common along streams and rivers. Common grasses
include little bluestem (Schizachrium scoparium), big bluestem (Andropogon gerardi), Indian
grass (Sorghastrum avenaceum), switchgrass (Panicum virgatum), and Canada wild-rye
(Elymus canadensis). Parts of the region were historically used for grazing, which has
contributed to the development of thickets of yaupon (Ilex vomitoria) and brumelia, and
extensive areas that have become dominated by mesquite. Approximately 43 linear miles of the
Proposed Project crosses the region, from MP 105.8 to MP 148.9.
The Lost Pines subregion, which lies within the Oak Woodlands and Prairies natural region, is
comprised of mature loblolly pines (Pinus taeda) within a unique sandy soil environment. The
pipeline crosses the subregion in central Bastrop County from MP 127.5 to MP 128.8.
Edwards Plateau
The Edwards Plateau natural region extends from the Balcones Escarpment in Austin through
west central Texas to the Stockton Plateau. Streams and rivers within the region typically are
fast flowing and clear or nearly clear. The region is comprised of cedar breaks with dense
growths of juniper, scrub oaks, and mesquite. Dominant grasses of the Plateau include
switchgrass and several species of bluestems and gramas. Rocky soils of the area typically
support a tall-grass understory and a brush overstory that is generally comprised of oaks,
junipers, and mesquite. Streams throughout the area are often well-drained ephemeral
drainages that provide habitat for a variety of plant and animal species not common in more
upland areas of the Plateau. Approximately 278.9 linear miles of the pipeline cross the Plateau,
including approximately 66.3 miles that cross the Llano Uplift, which is a subregion of the
Plateau.
4.3.1.1 Terrestrial Fauna and Flora
The Proposed Project traverses a variety of wildlife habitats and passes through the
distributional ranges of many species from East Houston to Crane. As the route crosses the
state from east to west, species composition is influenced by the vegetation present, water
availability, and to a large degree, by land ownership and land management practices. From
East Houston to Crane, the pipeline crosses three of the seven biotic provinces of Texas
described by Blair (1950). From east to west, the Proposed Project traverses the Austroriparian,
Texan and Balconian Biotic Provinces. The following provides a brief description of each
province and associated wildlife.
4-45

<<<PAGE 85>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Austroriparian Province
This province includes the Gulf Coast plain from the Atlantic to eastern Texas. The Proposed
Project begins just inside the western boundary of this province in Harris County. The
Austroriparian Province is home to a wide variety of different species throughout Texas.
Common species found throughout the Austroriparian Province are described in the following
paragraphs.
Mammals typical of this province include Virginia opossum (Didelphis virginaiana), eastern mole
(Scalopus aquaticus), eastern pipistrelle (Pipistrellus subflavus), eastern red bat (Lasiurus
borealis), eastern gray squirrel (Sciurus carolinesis), eastern flying squirrel (Glaucomys volans),
Baird's pocket gopher (Geomys breviceps), white-footed mouse (Peromyscus leucopus), hispid
cotton rat (Sigmodon hispidus), eastern woodrat (Neotoma floridana), eastern cottontail
(Sylvilagus floridanus), and swamp rabbit (Sylvilagus aquaticus).
Land turtles common to this province are ornate box turtle (Terrapene ornata) and eastern box
turtle (Terrapene carolina). Common snake species found in this Texas region include:
cottonmouth moccasin (Agkistrodon piscivorus leucostoma), copperhead (Agkistrodon
contortirx), rough green snake (Opheodrys aestivus), rat snake (Elaphe obsoleta), coachwhip
(Masticophis flagellum) and speckled kingsnake (Lampropeltis geluta holbrooki). Other species
include the spotted salamander (Ambystoma maculatum), marbled salamander (Ambystoma
opacum), mole salamander (Ambystoma talpoideum), pig frog (Rana grylio), and pickerel frog
(Rana palustris).
Texan Province
This province is located within a transitional area between forests of the Austroriparian province
and the grasslands to the west in Texas. The integration of woodlands and grasslands within
the region results in a mixture of wildlife species typical of the two general habitats. The
vertebrate fauna of the Texan Biotic Province consists of at least 49 species of mammals, 16
lizards, two land turtles, 39 snakes, 18 anurans (frogs and toads), and five urodeles
(salamanders, newts, etc.) (Blair, 1950).
Mammals typical of this province include the Virginia opossum (Didelphis virginiana), eastern
mole (Scalopus aquaticus), fox squirrel (Sciurus niger), Louisiana pocket gopher (Geomys
breviceps), fulvous harvest mouse (Reithrodontomys fulvescens), white-footed mouse
(Peromyscus leucopus), hispid cotton rat (Sigmodon hispidus), eastern cottontail (Sylvilagus
floridanus), and swamp rabbit (S. aquaticus). Animals typical of grasslands of this province
include the thirteen-lined ground squirrel (Spermophilus tridecemlineatus), hispid pocket mouse
(Chaetodipus hispidus), deer mouse (Peromyscus maniculatus), and black-tailed jackrabbit
(Lepus californicus). Typical anuran species to this province are the Hurter's spadefoot
(Scaphiopus holbrookii hurteri), Gulf Coast toad (Bufo valliceps), Woodhouse's toad (Bufo
woodhousii), gray treefrog (Hyla versicolor/chrysoscelis), green treefrog (Hyla cinerea), bullfrog
(Rana catesbeiana), southern leopard frog (Rana sphenocephala), and eastern narrowmouth
toad (Microhylla carolinensis).
4-46

<<<PAGE 86>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Balconian Province
This province is located primarily within the Edwards Plateau region of Texas. The Balconian
Biotic Province is a mixture of species characteristic of surrounding major provinces, even
though its primary vegetation is distinctly different. The vertebrate fauna consists of 57 species
of mammals, 16 lizards, 1 land turtle, 36 snakes, 15 anurans, and 7 urodeles (Blair 1950).
Mammals common to this province are the nine-banded armadillo (Dasypus novimcinctus), fox
squirrel (Sciurus niger), white-footed mouse (Peromyscus leucopus), black rat (Rattus rattus),
house mouse (Mus musculus), raccoon (Procyon lotor), and white-tailed deer (Odocoileus
virginiana).
Approximately 400 avian species have been recorded as occurring in the Balconian Biotic
Province. Common species include mourning dove (Zenaida macroura), yellow-billed cuckoo
(Coccyzus americanus), chimney swift (Chaetura pelagica), black-chinned hummingbird
(Archilochus alexandri), red-bellied woodpecker (Melanerpes carolinus), purple martin (Progne
subis), cliff swallow (Hirundo pyrrhonota), blue jay (Cyanocitta cristata), Carolina chickadee
(Parus carolinensis), tufted titmouse (Parus bicolor), Carolina wren (Thryothorus ludovicianus),
Bewick's wren (Thryomanes bewickii), northern mockingbird (Mimus polyglottos), white-eyed
vireo (Vireo griseus), black-and-white warbler (Mniotilta varia), northern cardinal (Cardinalis
cardinalis), rufous-crowned sparrow (Aimophila ruficeps), lark sparrow (Chodestes grammacus),
great-tailed grackle (Quiscalus mexicanus), and house sparrow (Passer domesticus).
Dominant vegetation and habitat types for much of the wildlife are described in Section 4.3.1
above. All four ecoregions crossed have different plant species and other particular habitat
types that determine the distribution of wildlife from East Houston to Crane along the pipeline
route.
White-tailed deer (Odocoileus virginianus) is an important big game animal in areas along the
pipeline and throughout other parts of the state. Other big game animals along the pipeline
include javelina (Pecari tajacu), mule deer (Odocoileus hemionus), and pronghorn antelope
(Antilocapra americana). Javelina populations are scattered, but are highest in the Trans-Pecos
natural region. Mule deer and pronghorn antelope are found primarily in the Trans-Pecos but
also inhabit areas of isolated habitat in the Edwards Plateau natural region.
In addition to the native big game species, many landowners along the western portions of the
route augment their income through commercial hunting of imported or exotic game species.
More than 80% of the exotic species that are raised for hunting comprise six species: axis deer,
blackbuck antelope, nilgai, Barbary sheep, Sika deer, and fallow deer. The axis deer (Axis axis)
is an abundant exotic ungulate in Texas and are free-ranging in southern Texas; however, the
majority are in captivity in ranches spread over 67 counties. The second most abundant exotic
species is the blackbuck antelope (Antilopa cervicapra), with the highest concentration in the
Edwards Plateau region. The nilgai (Boselaphus tragocamelus) is an abundant free-ranging
exotic ungulate in Texas. The fifth-ranked Barbary sheep (Ammotragus lervia) was introduced in
Palo Duro Canyon and has since spread to the Edwards Plateau, Trans-Pecos, Oak
Woodlands, and other parts of Texas. Sika deer (Cervus hippon) is widely distributed in central
4-47

<<<PAGE 87>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
and south Texas, including counties along the Proposed Project (Traweek 1985). Fallow deer
(Cervus dama) occur in 93 Texas counties, predominantly within the Edward’s Plateau Region.
A variety of nongame mammals, birds, reptiles, and amphibians are supported by the varied
habitats that exist along the pipeline route. Depending on the type of ecosystem, dominant
mammals may include raccoon (Procyon lotor), coyote (Canis latrans), bobcat (Lynx rufus),
badger (Taxidea taxus), and gray fox (Urocyon cinereoargenteus). These species, along with
the armadillo (Dasypus novemcinctus), opossum (Didelphis virginiana), blacktailed jackrabbit
(Lepus californicus), and striped skunk (Mephitis mephitis) comprise the most common
mammals found in proximity to the pipeline (TPWD, 1994).
Over 620 species of birds are known to occur in Texas (TPWD, 1994), many of which are
migratory. Most permanent resident species have some economic or recreational value.
Raptors provide a level of rodent control, and vultures are important as common scavengers.
Species of gamebirds include dove (Columba spp.), quail (Callipepla spp.), turkey (Meleagris
gallopavo), ducks, and geese. Songbirds, such as sparrows, finches, and warblers, serve as
insectivores, as well as being important species for recreational bird watchers.
Amphibian and reptilian species present along the Proposed Project route are diverse.
Amphibians such as the Texas Toad (Bufo speciosus), Red-spotted Toad (Bufo punctatus), and
Barred Tiger Salamander (Ambystoma tigrinum mavortium) are restricted to rivers, lakes, and
springs along the route and increase in frequency of occurrence from west to east.
4.3.2 Aquatic Resources
The Proposed Project crosses approximately 450 streamlines (based on USGS 1:24,000-scale
hydrography) from East Houston/Galena Park to Crane. Of the streams in which the Proposed
Project crosses, ten were considered ecologically important because they reflect the natural
regions discussed in the previous section. These streams and the MP crossings are listed in the
following table and their location is illustrated in Figure 4.3.1-1. Each of the nine streams and
their tributaries support fish species indigenous to Texas. In addition, each of the nine streams
support multiple game fish species.
Ecologically Important River Crossings and
Associated Natural Region from East Houston to Crane
Surface Water Feature County MP Associated Natural Region
Greens Bayou Harris 3.2, 6.0 Gulf Prairies and Marsh
White Oak Bayou Harris 32.0 Gulf Prairies and Marsh
Cypress Creek Harris 47.1 Gulf Prairies and Marsh
Brazos River Austin/Waller 64.0 Blackland Prairies
Colorado River Bastrop 134.5 Oak Woodlands and Prairies
Onion Creek Travis 164.0 Oak Woodlands and Prairies
Barton Creek Travis 180.9 Edwards Plateau
Pedernales River Blanco 198.8 Edwards Plateau
Llano River Kimble 276.5 Edwards Plateau/Llano Uplift
James River Mason 293.9 Edwards Plateau
4-48

<<<PAGE 88>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Gulf Prairies and Marsh
Greens Bayou, White Oak Bayou, and Cypress Creek
The Proposed Project crosses Greens Bayou at two locations (MP 3.2 and MP 6.0). White Oak
Bayou and Cypress Creek are crossed at MP 32.0 and MP 47.1, respectively. Greens Bayou
and White Oak Bayou are within an urban setting, and both have been channelized for flood
control. Both bayous have sloping banks that are maintained with invasive and native grasses to
aid in bank stabilization. Available fish habitat in White Oak and Greens bayous is exceptionally
limited. The drainages are maintained free of woody debris and aquatic vegetation to improve
flood drainage. Base flow in the bayous is dominated by the discharge of reclaimed wastewater.
Velocity is relatively low with most substrates consisting of clay, sand, fine gravel, and silt. Since
the channels are maintained for flood control, there is little riparian vegetation. The water is
slow-moving over a bottom substrate partially comprised of gravel and silt. The Proposed
Project crosses Cypress Creek in rural Harris County. The creekstream channel is partially
channelized due to the installation of flood control measures; however, a large portion of the
waterway has not been modified. Vegetation along the creek margin is comprised of bald
cypress (Taxodium distichum), hackberry (Celtis occidentalis), and willow (Salix spp).
Greens Bayou and White Oak Bayou are classified by the USFWS as palustrine with scrub-
shrub vegetation (Moring, 1999). Cypress Creek, at the pipeline crossing, is classified by the
USFWS as palustrine.
Blackland Prairie
Brazos River
The Brazos River is crossed at MP 64, which is in the Gulf Coast Parries and Marshes
ecoregion. The Brazos River is characterized as among the widest of the Texas rivers, with
gentle relief and low velocities. The river maintains a very heavy silt load, resulting in perennially
high turbidity. Substrates consist of clay, sand, and silt. Coarse woody debris is abundant in the
river channel and is among important aquatic habitats in the river. Riverbanks are lined with
willow, cottonwood and elm, which provide cover for many aquatic species. This portion of the
river is located within the Blackland Prairies region.
Oak Woodlands and Prairies
Colorado River
The Colorado River is crossed at MP 134.5, and is in a transitional area between the Blackland
Prairie and Post Oak Savannah ecoregions. The Colorado River in the vicinity of the Proposed
Pipeline crossing is highly modified by the highland lakes, return wastewater flows from Austin,
and hydroelectric station pulsed-flow releases. The river is generally wide with alternating riffles,
runs, and pools. Due to broad variations in channel morphology and substrates, habitats vary
widely. Coarse woody debris is an important habitat within the river. Substrates consist of clay,
sand, gravel, and cobble. Turbidity is generally low under low-flow conditions, but can increase
with higher flows. Aquatic plants are present in the river, which provide important nursery cover
for fish and food for over-wintering waterfowl. River banks are lined with willow, cottonwood,
elm, and sycamore, which aid in bank stability and provide cover for fish. Large areas within the
river floodplain are under cultivation and used for pecan production. The Proposed Project
4-49

<<<PAGE 89>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
crossing is classified by the USFWS as open water and forested palustrine (Bonn, 1980; Hubbs,
1982).
Onion Creek
Onion Creek is crossed at MP 164.0, within the Austin city limits. The creek flows from the
Edwards Plateau to the Blackland Prairies natural ecoregions, and the location crossed by the
proposed Pipeline Project pipeline is approximately 3 linear miles from the transition of the two
natural areas. Onion Creek discharges into the Colorado River downstream of Austin in Travis
County. Reaches along within the Edward’s Plateau are characteristically deeply incised with
steep river banks that are cut to Cretaceous limestone. Along this reach, the substrates consist
of bedrock, boulders, cobble, gravel, and deposits of sand and silt. The channel within the
Blackland Prairies ecoregion (including the pipeline crossing location) is broader with less
defined slopes. Substrates generally consist of clay and gravel. The flow in Onion Creek is
intermittent, although perennial pools exist during most dry periods. Due to the intermittent
nature of Onion Creek, aquatic life use is highly variable. Important aquatic habitats include
boulders, cobble, gravel, and coarse woody debris. Dominant species associated with the river
include sycamore (Platanus occidentalis), cottonwood (Populus deltoides), American elm
(Ulmus americana), cedar elm, and pecan trees. NWI data for the Onion Creek crossing
indicate that area wetlands are classified as emergent palustrine, forested palustrine, and
intermittent riverine.
Edwards Plateau
Barton Creek
The pipeline crosses Barton Creek in Travis County at MP 180.9. Barton Creek is on the
Edward’s Plateau and the reach of stream near the proposed Pipeline Project crossing is
intermittent and prone to scouring flows during storm events. During wet periods, spring flows
maintain flow in the stream, which is typically low in turbidity and very clear. During dry periods,
springs flows cease and the stream flows cease.
The lower reach of Barton Creek maintains perennial flow via Barton Springs. This reach of
stream is very clear and the substrates consist of bedrock, boulders, cobble, gravel, and silt.
This reach of stream is extensively used for contact recreation, paddling sports, and fishing.
Barton springs/Barton Creek discharges into the south shore of Lady Bird Lake. Barton Creek is
on the Edwards Plateau, is spring-fed, and has limestone banks and substrate. The creek flows
between multiple pools and riffles throughout its length, and vegetation composition along
Barton Creek is characteristic of the Edwards Plateau natural ecoregion. Dominant species
along the creek margin include bald cypress, sycamore, cottonwood, American elm, cedar elm,
and pecan trees. The USFWS classifies this pipeline crossing location as palustrine, scrub-
shrub palustrine with an unconsolidated bottom.
Pedernales River
The Proposed Project crosses the Pedernales River in Blanco County at MP 198.8. The river is
on the Edward’s Plateau and is typical of a hill country stream with alternating riffles, runs, and
pools. Due to steep watershed gradients, stream flow can be highly variable after storm events.
Numerous seeps and springs throughout the watershed maintain base flow that is typically
4-50

<<<PAGE 90>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
clear. The streambed is mostly scoured bedrock with deposits of cobble, gravel, sand, and silt.
The Pedernales River discharges into Lake Travis, which is an impoundment of the Colorado
shallow throughout much of its length and generally flows clear along rocky banks that are lined
with bald cypress and cottonwood trees. River flows can increase dramatically after a heavy
rain, and flooding of riverine areas is common. The Pedernales River crossing location is
classified by the USFWS as forested palustrine (Simmons, In Press).
Edwards Plateau/Llano Uplift
Llano River
The Llano River is crossed in Kimble County at MP 276.5. The Llano River is also on the
Edward’s Plateau and is typical of a hill country stream with alternating riffles, runs, and pools.
Due to steep watershed gradients, stream flow can be highly variable after storm events.
Numerous seeps and springs throughout the watershed maintain base flow that is typically
clear. The streambed is mostly scoured bedrock with deposits of cobble, gravel, and sand,
although clay banks and substrate are also common. The Llano River discharges into Lake LBJ,
which is an impoundment of the Colorado River. The spring-fed river flows over limestone and
gravel substrate, producing many small riffles. Limestone banks vary in slope. Wetlands at the
crossing are classified by the USFWS as scrub-shrub palustrine and lower perennial riverine
(Simmons, In Press).
James River
The James River is a 37-mile tributary of the Llano River, which begins near the Kimble and
Kerr County line and intersects the Llano River approximately seven miles south of Mason,
Texas. The James River is crossed by the Proposed Project in Mason County at MP 264. The
James River is similar to the Llano River, but is considered less spoiled by adverse land use
and habitat alteration. The stream channel is mostly gravel as it crosses the Edwards Plateau
and changes to primarily bedrock at the edge of the Llano Uplift. The channel widens to over
200 feet in places and forms canyons up to 100 feet tall. Springs, which form fractures and
faults along the margins of the uplift, contribute additional flow to the river (Broad, 2010). The
NWI data for the James River crossing indicate that the river is classified as lower perennial
riverine and the area wetlands are classified as palustrine emergent and scrub-shrub.
4.3.2.1 Aquatic Fauna and Flora
Aquatic resources habitats within Proposed Project study area consist of open-water perennial
and intermittent streams, man-made impoundments, playa lakes, and stock tanks, as well as
other various wetland features. Hydric habitats are generally associated with streams, creeks,
impoundments, and topographic lows. Bottomland/riparian hardwood forests are often
associated with the streams and creeks. Impoundments generally result in either permanent or
ephemeral freshwater wetlands, marshes, or fringe marshes.
The Proposed Project crosses four river basins from East Houston to Crane. These river basins
include the San Jacinto, Brazos and Colorado rivers and the eastern most portion of the Rio
Grande. The Proposed Project also crosses numerous tributaries of these rivers. The food webs
in these dynamic ecosystems are very complex. In general, benthic macro invertebrates are
4-51

<<<PAGE 91>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
important food resources among lotic systems, whereas zooplankton is important in lentic
systems and, to some extent, in larger streams. Emergent and submerged aquatic vascular
plants and algae provide important food and cover where water clarity is supporting, but is less
important in the more turbid environments. In the eastern streams, coarse woody debris and
organic material is among the most important habitats in lotic systems, whereas in the western
streams, boulder, cobble, and rock substrates are more important. Similarly, water quality can
be highly variable. Eastern streams often consist of soft water with higher turbidity and oxygen
concentrations can be limiting due to heavy shading and higher biochemical oxygen demand
associated with organic loading. To the west, the stream gradients become steeper, with higher
velocity, less riparian shading and allochthonous inputs, and typically less turbid waters. As
such, the fish communities can vary widely across the state. Faunal communities important in
aquatic habitats include phytoplankton, zooplankton, benthic macro invertebrates, infauna and
epifauna, as well as nekton species. These communities vary according to aquatic habitat
characteristics and the habitat requirements and distribution of species. Collectively, these
species often construct complex food webs within aquatic systems.
4.3.2.1.1 San Jacinto River Basin
The streams within the San Jacinto River basin, including the San Jacinto River, are typically
more turbid, with heavy riparian shading, organic inputs, and abundant coarse woody debris.
With the exception of the streams in the Houston metropolitan area, most of the drainages have
natural riparian corridors and the fish communities are generally unaltered. The exception to this
is the San Jacinto River, which has been impacted by the construction of reservoirs, and the
Houston-area bayous that have been channelized for flood control and the flows are dominated
by reclaimed wastewater. The habitats in those streams have been severely impacted and the
fish communities have been greatly altered. Greens and White Oak bayous have little or no
riparian corridor since they are maintained for flood control. Aquatic vegetation is limited to
filamentous algae or invasive species, such as alligator weed (Alternanthera philoxeroides).
Although some of the channel has been modified, riparian vegetation can be found along
Cypress Creek. The riparian community is dominated by willow (Salix ssp.), Chinese tallow,
hackberry (Celtis occidentalis), and, along the lower reaches, some bald cypress (Taxodium
distichum).
Some of the most common fish species in the Houston bayous are invasive exotics, including
grass carp (Ctenopharyngodon idella), common carp (Cyprinus carpio), suckermouth catfish
(Hypostomus plecostomus), Amazon molly (Poecilia latipinna), and a variety of other species
that have been introduced through the aquarium trade. Native species are typically those that
are ubiquitous and adapted to altered environments, such as bluegill (Lepomis macrochirus),
western mosquitofish (Gambusia affinis), red shiner (Cyprinella lutrensis), bullhead catfish
(Ameiurus spp.), and in the larger bayous, smallmouth buffalo (Ictiobus bubalus). Streams
outside of the Houston area that are less altered have communities typical of southeast Texas.
Common fish species that occur in the San Jacinto River basin include spotted gar (Lepisosteus
oculatus), bowfin (Amia calva), gizzard shad (Dorosoma cepedianum), blacktail shiner
(Cyprinella venusta), blacktail redhorse (Moxostoma poecilurum), yellow bullhead (A. natalis),
grass pickerel (Esox americanus), blackstripe topminnow (Fundulus notatus), western
4-52

<<<PAGE 92>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
mosquitofish (Gambusia affinis), bluegill, green sunfish (L. cyanellus), white crappie (Pomoxis
annularis), largemouth bass (Micropterus salmoides), and bluntnose darter (Etheostoma
chlorosoma) (Bonner, 2011; Hubbs et al, 2008; Thomas et al., 2007).
4.3.2.1.2 Brazos River Basin
The riparian corridor along the Brazos River consists of coastal prairie and riparian forest that
include willow, cottonwood (Populus deltoids), pecan (Carya illinoinensis), and elm (Ulmus
spp.). Due to periodic flooding and high turbidity, aquatic plants are scarce along the river.
Common fish species that occur in the Brazos River in the vicinity of the proposed Pipeline
Project crossing are characteristic of large, Texas coastal rivers. The species in the river are
generally those adapted to high turbidity and soft substrates. These include longnose gar (L.
osseus), gizzard shad, common carp, sharpnose shiner (Notropis oxyrhynchus), which is a
species of concern, red shiner, mimic shiner (N. volucellus), smallmouth buffalo, channel catfish
(Ictalurus punctatus), flathead catfish (Pylodictis olivaris), and freshwater drum (Aplodinotus
grunniens), Guadalupe bass (Micropterus treculii), and black crappie (Pomoxis nigromaculatus)
(Thomas et al., 2007).
The fish communities in the tributaries of the Brazos River in the vicinity of the proposed
Pipeline Project are generally reflective of small streams of east Texas. Common species
include spotted gar, bowfin, blacktail shiner, blackspot shiner, ribbon shiner (Lythrurus fumeus),
spotted sucker (Minytrema melanops), bullhead catfish, blackstripe topminnow, western
mosquitofish, and bluntnose darter (Bonner, 2011; Hubbs et al, 2008; Thomas et al., 2007).
4.3.2.1.3 Colorado River Basin
Colorado River - The Colorado River downstream of Austin is an area of transition between the
habitats and species common to east Texas and those in the Edwards Plateau and west Texas.
The riparian corridor along the river consists of willow, sycamore (Platanus occidentalis),
cottonwood, elm, and pecan. During prolonged low-flow or drought conditions, the Colorado
River downstream of Austin is typically clear, supporting a variety of submerged aquatic plants
including waterstargrass (Heteranthera dubia), water milfoil (Myriophyllum spicatum), coontail
(Ceratophyllum demersum) , and occasionally hydrilla (Hydrilla verticillata).
Since the flows are highly regulated by the upstream dams, sunfish are among the most
common species immediately downstream of Austin. These include longear sunfish, bluegill,
green sunfish, largemouth bass, and hybridized Guadalupe/spotted/smallmouth bass, the
genetics of which are not clearly understood. Although within their historic range, most experts
agree that the Guadalupe bass in the lower Colorado River are hybrids or intergrades of other
black bass. Other common species include longnose and spotted gar, gizzard shad, blacktail
shiner, bullhead minnow, shoal chub (Macrhybopsis hyostoma), smallmouth buffalo, blue sucker
(Cycleptus elongatus), which is a state-listed threatened species, channel catfish, flathead
catfish, inland silverside (Menidia beryllina), white bass (Morone chrysops), dusky darter
4-53

<<<PAGE 93>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
(Percina sciera), Texas logperch (P.carbonaria), and freshwater drum (Bonner, 2011; Hubbs et
al, 2008; Thomas et al., 2007).
Onion Creek – Due to scouring flows and periodic dry conditions, aquatic plants are generally
scarce along Onion Creek. Filamentous algae is the most common plant, often forming dense
mats along the margin of the stream. Dominant tree species associated with Onion Creek
include sycamore, cottonwood, American elm, cedar elm, box elder, and pecan. Fish species
common to Onion Creek and other area tributaries of the lower Colorado River include spotted
gar, red shiner, blacktail shiner, mimic shiner, central stoneroller (Campostoma anomalum),
bullhead catfish, various sunfish, and greenthroat darter (E. lepidum) [Bonner, 2011; Hubbs et
al, 2008; Thomas et al., 2007].
Barton Creek – Since Barton Creek is subject to scouring flows and the upper reach is
intermittent, submerged aquatic plants are uncommon throughout most of the stream. However,
submerged plants, including Eurasian milfoil (M. spicatum) and pondweeds (Potomogeaton
spp.) are common at the confluence of Lady Bird Lake. Dominant tree species associated with
Barton Creek include sycamore, cottonwood, American elm, cedar elm, box elder, pecan, and
along the lower reach, bald cypress.
The fish community in the vicinity of the Proposed Project crossing (upstream of Barton Spring)
is limited since flows are intermittent. Downstream of Barton Springs, common fish include gray
redhorse (M. congestum), bluegill, redear sunfish (L. microlophus), green sunfish, largemouth
bass, channel catfish, orangethroat darter (E. spectabile) and Mexican tetra (Astyanax
mexicanus), an introduced species (TCEQ, 2012).
Pedernales and Llano Rivers - The Pedernales and Llano rivers share similar fish
communities. Due to their typically clear water, the most common fish species include sunfish,
such as bluegill, longear sunfish, green sunfish, largemouth bass, and Guadalupe bass, which
have hybridized with smallmouth bass that were historically stocked by the TPWD. Other
common species include spotted gar, gizzard shad, common carp, blacktail shiner, red shiner,
bullhead minnow, mimic shiner, gray redhorse, bullhead catfish, channel catfish, western
mosquitofish, Texas logperch, and dusky darter (Bonner, 2011; Hubbs et al, 2008; Thomas et
al., 2007). Due to periodic scouring flood flows along these rivers, the growth of submerged
aquatic plants is limited. However, filamentous algae can be common. In addition, water willow
(Justicia americana) is a common and important emergent plant that provides important nursery
cover for fish along pools and runs. Riparian tress, along these rivers, include bald cypress,
sycamore, cedar elm, cottonwood, and pecan.
4.3.3 Threatened and Endangered Species
The Endangered Species Act (ESA) (16 USC 1531 et seq.) of 1973, as amended, was enacted
to provide a program for the preservation of threatened and endangered (T&E) species and to
provide protection for the ecosystems upon which these species depend for their survival. All
federal agencies are required to implement protection programs for these designated species
and to use their authorities to further the purposes of the Act. Responsibility for identification of
4-54

<<<PAGE 94>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
T&E species and any potential recovery plans lies within the Secretary of the Interior and the
Secretary of Commerce.
In February 2000, a Biological Assessment (BA) was conducted for the 1999 EA from East
Houston to Crane. This BA was prepared in two phases in accordance with the ESA to
determine the potential impacts to federally-listed T&E species through consultation with the
USFWS. The Phase I portion of the BA and Biological Opinion (BO) addressed ROW
maintenance operations. The Phase II BA and USFWS concurrence letter addressed long-term
operation, maintenance, and emergency response issues. Phase I and II BAs are included in
Appendix 4B.
The results of the Phase I BA (Crane to East Houston) concluded that eight federally-listed T&E
species could potentially be affected by maintenance, construction activities, or a potential
release of product from the pipeline. The eight species of the Phase I BA include four avian
birds, one amphibian species, and three plant species.
Potential impacts to federally-listed T&E species are addressed in Sections 7.4 and 7.5. Habitat
assessments were conducted at all proposed pump station locations to evaluate the potential
for habitat for federally and/or state-listed T&E and candidate species. The habitat assessments
were conducted by experienced biologists authorized by the FWS to conduct presence/absence
surveys for many of the same species identified in the BA.
4.3.3.1 Protected Terrestrial Species
In 2000, an extensive biological survey for T&E species, as well as their habitats, was
conducted along the Longhorn Pipeline ROW from East Houston to Crane, Texas. Along with
the survey, other sources of information were obtained for all listed T&E species. Other sources
aside from the ground survey included various published, agency files, personal communication
sources through TPWD and USFWS and recognized experts for certain species, published
species documentation, and published reference books.
Through previous consultation and studies which are outlined in the Phase I BA described in
Section 4.3.3, it was determined that eight terrestrial species would require further attention and
were deemed susceptible to potential impacts. All other listed species were ruled out due to lack
of habitat, population, or other variables. The following eight species were either documented to
occur or have been identified within the area of potential impact for pipeline safety operations
and maintenance due to the presence of potential suitable habitat. None of the eight species
had been documented to occur within the pipeline ROW. These potential species include the
Texas prairie dawn flower (Hymenoxys texana), Navasota ladies-tresses (Spiranthes paksii),
Tobusch fishhook cactus (Ancistrcactus tobuschii), Houston toad (Bufo houstonensis), golden
cheeked warbler (Dendroica chrysoparia), black-capped vireo (Vireo atricapillus), bald eagle
(Haliaeetus leucocephalus), and the interior least tern (Sterna antillarum athalassos).
Since the Phase I BA and concurrence from USFWS in 2000, several new species have been
listed in several counties along the Longhorn Pipeline route. These species identified in the
4-55

<<<PAGE 95>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
latest Annotated County List of Rare Species from both TPWD and FWS, are listed in Table
4.3.1-1 along with their status and counties of occurrence, and are described below.
One reptile, the Trans-Pecos black headed snake (Tantilla cucullata), is listed as threatened by
the TPWD in Crockett County. There have been no recent sightings of this snake in Crockett
County. Most recently, most sightings have occurred south of the pipeline location in Val Verde,
Jeff Davis, Brewster and Presidio Counties. This snake is typically found in mesquite-creosote
and pinyon-juniper-oak type habitats.
Two new mammal species are listed in counties crossed by the Proposed Project. The ocelot
(Leopardus pardalis) is listed as endangered by TPWD in Crockett County. The ocelot is
primarily found in dense chaparral thickets, mesquite-thorn scrub and live oak mottes. Ocelots
will typically avoid open areas. The Louisiana black bear (Ursus americanus luteolus) is listed
as threatened by TPWD in Harris County. This species would be considered a possible
transient in Harris County and preferable habitat includes bottomland hardwoods and large
tracts of inaccessible forested areas.
One new avian species was listed in counties crossed by the Proposed Project. The red-
cockaded woodpecker (Picoides borealis) is listed as endangered in Harris County by the
TPWD. The red cockaded woodpecker will have cavity nests in older mature pines (60+years),
but may forage in younger pines (30+years). This species prefers to nest or forage in longleaf,
shortleaf and loblolly pines.
One invertebrate is listed as a candidate species. The Warton’s cave meshweaver (Cicurina
wartoni) is listed in Travis County. This is a very small cave dwelling spider found only in Travis
County.
4.3.3.2 Federally Protected Species
One amphibian is listed as endangered by both USFWS and TPWD in Travis and Hays
Counties. The Barton Springs salamander (Eurycea sosorum) is epigean and is mostly
restricted to subterranean cavities of the Edwards Aquifer. This salamander is dependent upon
water flow/quality from the Barton Springs segment of the Edwards Aquifer. This salamander is
only known to be in the outlets of Barton Springs. These outlets that form Barton Springs
include Upper Barton Springs, Sunken Garden Spring, Eliza Spring and Parthenia Spring.
One mammal is listed as endangered by the USFWS in Harris County. The West Indian
manatee (Trichechus manatus) is a marine mammal found in marine, estuarine, and freshwater
environments. Suitable habitat for these species is not located along the pipeline corridor or
zone of potential impact.
Two amphibians are listed federally as candidate species. The Austin blind salamander
(Eurycea waterlooensis) and Jollyville Plateau salamander (Eurycea tonkawae) are both
candidate species in Travis County. The Austin blind salamander is known only from the
outflows of Barton Springs in the City of Austin, Travis County, Texas. The Austin blind
4-56

<<<PAGE 96>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
salamander is thought to spend its entire life in the aquifer. Those individuals observed are
presumably washed through the spring outlets of Barton Springs (www.austintexas.gov, 2012).
The Jollyville Plateau salamander occurs in the Jollyville Plateau and Brushy Creek areas of the
Edwards Plateau in Travis and Williamson Counties, Texas. This amphibian lives primarily in
the springs and streams of northwest Austin and southern Williamson County
(www.austintexas.gov, 2012).
4.3.3.2.1 State Protected Species
Fish
An annotated list of aquatic species, listed as threatened or endangered by the TPWD that may
potentially occur in the counties related to the Longhorn pipeline portion of the Proposed Project
(East Houston to Crane), is provided in Table 4.3.1-1.
There are two state-listed threatened species listed for the counties in which the Proposed
Project is located. These are the creek chubsucker (Erimyzon oblongus) and blue sucker.
The creek chubsucker inhabits small tributaries in east and southeast Texas, including
tributaries of the San Jacinto River (Thomas, 2007; TPWD, 2012). Within the zone of potential
impact of the Proposed Project, the creek chubsucker is restricted to Harris County. The
species may occur within small intermittent and perennial streams and may be found in riffles,
pools, and spring areas.
The blue sucker inhabits large rivers ranging from the Colorado River to the Rio Grande
(Thomas, 2007; Hubbs, 2008; TPWD, 2012). Within the Proposed Project area, the blue sucker
may be found in the vicinity of the Colorado River crossing. The fish has been well studied in the
Lower Colorado River (LCRA, 2008). The fish inhabits all habitat types and often migrates from
the lower basin to near Austin to spawn.
Mussels
Approximately 52 species of native freshwater mussels in the mussel family, Unionidae, live in
Texas waters. On November 5, 2009, TPWD added 15 to the state’s list of threatened species
(TPWD, 2009). Of those 15 mussels, seven species are listed as potentially occurring within
counties from Harris in the east to Crane in the west (TPWD, 2011) (Table 4.3.1-1). Below is a
list of those seven species and summaries of their previously known occurrence in the counties
included in the Proposed Project. Those streams include: Greens Bayou, White Oak Bayou,
and Cypress Bayou (Harris County), Brazos River, Colorado River, Onion Creek, Barton Creek,
Pedernales River, and Llano River.
Four reports summarizing occurrence of mussels in Texas were reviewed. Howells et al. (1996)
summarized the known occurrence of freshwater mussels in Texas based on review of
published and unpublished literature and Howell’s field investigations. Burlakova et al. (2010)
sampled 139 sites in 11 river basins in Texas over the period from 2003 to 2009. Winemiller et
al. (2010) conducted an intensive review of museum records focused on mussels collected in
4-57

<<<PAGE 97>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Texas waters. The USFWS (Federal Register, 2011) describes the historical distribution and
known current distribution of five mussels it has listed as candidate species.
On October 6, 2011, the USFWS announced it had completed a status review of five Texas
mussel species: Texas fatmucket (Lampsilis bracteata), Texas pimpleback (Quadrula petrina),
golden orb (Quadrula aurea), Texas fawnsfoot (Truncilla macrodon), and smooth pimpleback
(Quadrula houstonensis) (Federal Register, 2011). When resources allow in the future, the
USFWS will determine if these species should be considered as threatened or endangered and
if critical habitat should be designated for them. The USFWS status review of these five species
includes detailed information about their distribution in Texas waters.
Additional information was gathered from annual reports written by Howells (2000, 2001, 2002,
2004, 2005, and 2006) that summarized annual results of mussel surveys in Texas by Texas
Parks and Wildlife Department biologists and trained volunteers. These surveys did not include
all river basins each year. Survey of the Colorado River between the cities of Austin and
Bastrop during 2003 did not encounter any state-listed species of mussels (Howells, 2004).
Barton Springs in Travis County was also surveyed in 2003 without state-listed mussels being
found (Howells, 2004). Readily available literature did not identify mussels collected from
Greens Bayou, White Oak Bayou, or Cypress Creek in Harris County. The following describes
areas where the listed mussels were collected or were sampled for, but not collected with
respect to the watersheds within the Proposed Project.
False spike (Quadrula mitchelli):
• Llano River in Mason County (Howells et al., 1996);
• Llano River (Winemiller et al., 2010); and
• Burlakova et al. (2010) surveyed the Llano River during their statewide study from 2003
through 2009 and did not encounter it there.
Golden orb (Quadrula aurea):
• Llano River drainage (Howells et al., 1996);
• Burlakova et al. (2010) did not find it at any of their sampling sites in the Brazos or
Colorado River basins;
• Colorado and Llano drainages (Winemiller et al., 2010); and
• Federal Register’s (2011) review of literature indicates that golden orb has not occurred
in the Colorado, Brazos, or Rio Grande watersheds. Reports of its occurrence in these
drainages are attributed to misidentifications.
Sandbank pocketbook (Lampsilis satura):
• Although reported as possibly occurring in the San Jacinto River basin in Harris County,
it has never been documented from the San Jacinto watershed (Howells et al., 1996;
Burlakova et al., 2010; and Winemiller et al., 2010).
Smooth pimpleback (Quadrula houstonensis):
• Llano River and Colorado River drainage in Travis County (Howells et al., 1996);
4-58

<<<PAGE 98>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Burlakova et al. (2010) and Winemiller et al. (2010) indicate it has been found in the
Colorado and Brazos River drainages;
• Llano River drainage (Winemiller et al., 2010); and
• Federal Register (2011) indicates its historical distribution included the Llano River,
Onion Creek, and the mainstems of the Colorado and Brazos rivers.
Texas fatmucket (Lampsilis bracteata):
• Pedernales River drainage and Llano River (Howells et al., 1996);
• Colorado, Pedernales, Llano, and Onion Creek drainages (Winemiller et al., 2010);
• Llano River and Live Oak Creek (Burlakova et al., 2010);
• Live Oak Creek portion of the Pedernales River watershed (Howells 2002, 2005, and
2006); and
• Colorado River upstream of Travis County, Pedernales and Llano rivers, and Onion
Creek (Federal Register, 2011).
Texas fawnsfoot (Truncilla macrodon):
• Lower Colorado and Brazos rivers, Colorado River drainage in Travis County, and the
Llano River (Howells et al., 1996). Although it was not reported from those rivers in
Waller, Austin, Fayette, or Bastrop counties;
• Burlakova et al. (2010) report it from the Colorado and Brazos rivers;
• Winemiller et al. (2010) report Texas fawnsfoot from the Colorado and Llano rivers; and
• Historically this species inhabited the Llano River, Onion Creek, and much of the
Colorado River.
Texas pimpleback (Quadrula petrina):
• Howells et al. (1996) report this species from the Pedernales and Llano River
watersheds;
• Neither Burlakova et al. (2010) or Winemiller et al. (2010) reported this species in the
counties covered in this report; and
• Federal Register (2011) describes historical records of this species from much of the
mainstem Colorado River, Llano and Pedernales rivers, and Onion Creek.
4.4 CULTURAL RESOURCES
4.4.1 PIPELINES
4.4.1.1 Proposed Project (East Houston to Crane)
The Proposed Project ROW extending between Crane, Texas and Houston/Galena Park, Texas
was constructed in the 1950s, prior to the passing of Section 106 of the National Historic
Preservation Act (NHPA) of 1966, as amended, which requires federal agencies to take into
consideration the effects of federally-permitted or funded actions on significant cultural
resources. As a result, no formal cultural resources surveys were conducted prior to the original
construction of the pipeline, and any undocumented cultural resources that may have been
present within the ROW were disturbed to some degree during the original construction efforts
4-59

<<<PAGE 99>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
and subsequent maintenance activities. Because of this, there exists little to no potential for
significant, intact cultural deposits within the original trench that was excavated for the pipeline
installation. However, the potential for intact cultural deposits still exists within the limits of the
ROW beyond the limits of the previously disturbed trench.
In compliance with Section 106 of the NHPA, cultural resources survey and monitoring efforts
were conducted at select locations along the proposed ROW in the 1990s during upgrades to
the pipeline. These survey and monitoring efforts served to identify a number of previously
undocumented archeological sites within the limits of the ROW.
In 2000, the EPA and the DOT, in consultation with the Texas State Historic Preservation
Officer (SHPO), Tribal Historic Preservation Officer(s) (THPO) (or other Tribal officer), and the
Advisory Council on Historic Preservation (ACHP), executed a Programmatic Agreement (PA)
to comply with Section 106 of the NHPA. Stipulations of the PA include requirements that
Longhorn enter into consultation with the SHPO/THPO to identify all archaeological or historic
properties within the ROW that are listed on or considered eligible for listing on the National
Register of Historic Places (NRHP) and that may be affected directly or indirectly by subsequent
ground-disturbing activities within the ROW. In accordance with the requirements of the PA,
resource recovery plans are to be developed and implemented when adverse impacts to
identified cultural resources listed on or considered eligible for listing on the NRHP cannot be
avoided. A copy of the PA can be found in Appendix 4C.
As per the PA for the Longhorn Pipeline, Horizon Environmental Services, Inc. (Horizon), on
behalf of Magellan conducts cultural resources surveys at the locations of all necessary
maintenance activities along the ROW. In an effort to allow these maintenance activities to
comply with the time constraints of DOT requirements for identified pipeline anomalies and the
Section 106 consultation process, Horizon designated archeological high and low probability
areas along the length of the ROW based on a variety of factors including the locations of
previously recorded archeological sites, distance from water sources, topographic settings, and
the results of previous cultural resources surveys along the ROW. In compliance with Section
106 of the NHPA, the maps of the delineated high and low archeological probability areas were
submitted to the SHPO for review. This submittal also included recommendations that: 1) no
cultural resources surveys were warranted within the delineated low probability areas; 2)
maintenance activities be allowed to proceed in the delineated low probability areas without
further consultation with the SHPO; and 3) cultural resources surveys only be required within
delineated archeological high probability areas (AHPAs). The SHPO concurred with these
recommendations on 23 May 2007 (Appendix 4D). Since that time, the full extent of each
delineated AHPA has been surveyed for cultural resources as maintenance activities arise in
each.
In compliance with the PA and Section 106 of the NHPA, a review of the Texas Historical
Commission’s (THC’s) Texas Archeological Sites Atlas (Atlas) website was performed by
Horizon for this FEA. The cultural resources review was conducted for an area defined as the
area of potential effect (APE), which is 1,250 feet from the pipeline. This area is consistent with
1999 EA. The review of the THC’s Atlas website indicated the presence of 103 previously-
4-60

<<<PAGE 100>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
recorded archeological sites and eight cemeteries within the APE, while a review of the National
Park Service’s (NPS) NRHP Google Earth map layer indicated the presence of no historic
properties listed within the APE. These cultural resources and their distances from the ROW are
summarized below.
Documented Cultural Resources within 1,250 feet of Proposed Project Centerline
Site Trinomial,
Cemetery, or Historic
Property
Site Type NRHP Eligibility
Status
Distance/Direction
from Centerline
41HR806 Historic dairy Undetermined 787.4 feet north
41HR401 Historic homestead Undetermined 262.5 feet north
41HR328 Prehistoric lithic
scatter Undetermined 557.7 feet south
41WL14 Prehistoric campsite Undetermined 131.2 feet south
41WL15 Prehistoric campsite Undetermined 213.3 feet north
41WL17 Prehistoric campsite Undetermined 918.6 feet north
41AU72 Historic well Ineligible 1,148.3 feet south
41AU96 Prehistoric campsite Undetermined On centerline
41AU71 Historic homestead Ineligible On centerline
41FY448 Historic farmstead Ineligible 131.2 feet north
41FY534 Prehistoric campsite Ineligible On centerline
41FY497 Prehistoric lithic
procurement area Ineligible 1,017.1 feet south
41FY532 Prehistoric lithic
procurement area Ineligible On centerline
41LE40 Undetermined Undetermined 557.7 feet south
41FY495 Prehistoric lithic
procurement area Ineligible 557.7 feet south
41FY533 Prehistoric campsite Ineligible On centerline
41FY508 Prehistoric campsite Undetermined On centerline
41FY496 Prehistoric lithic
scatter Ineligible 295.3 feet south
41BP299 Prehistoric campsite Undetermined On centerline
41FY498 Prehistoric lithic
scatter Ineligible 885.8 feet north
41BP673
Prehistoric
campsite/Historic
scatter
Ineligible 49.2 feet north
41BP280 Prehistoric campsite Ineligible 492.1 feet southeast
41BP856
Prehistoric campsite
and lithic procurement
area
Undetermined On centerline
41BP48 Prehistoric campsite Undetermined 131.2 feet north
41BP51 Prehistoric campsite Undetermined 131.2 feet north
41BP645 Prehistoric campsite Ineligible On centerline
41TV1665 Undefined prehistoric
site Undetermined 98.4 feet south
41TV2000 Historic farmstead Undetermined 1,099.1 feet south
41TV1394 Historic homestead Ineligible 705.4 feet north
41TV1393 Prehistoric lithic
procurement area Ineligible 1,279.5 feet north
41TV1396 Historic schoolhouse Ineligible 754.6 feet north
41TV1095 Prehistoric lithic
procurement area Ineligible 754.6 feet north
41TV401
Prehistoric campsite
and lithic procurement
area
Undetermined On centerline
4-61

<<<PAGE 101>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Site Trinomial,
Cemetery, or Historic
Property
Site Type NRHP Eligibility
Status
Distance/Direction
from Centerline
41TV399 Prehistoric campsite Undetermined On centerline
41TV400 Prehistoric campsite Undetermined 246.1 feet north
41TV402
Prehistoric campsite
and lithic procurement
area
Undetermined 787.4 feet north
41TV1827 Prehistoric lithic
procurement area Undetermined 591.0 feet southwest
41TV683 Prehistoric lithic
procurement area Ineligible 607.0 feet southwest
41TV358 Prehistoric campsite Undetermined 951.4 feet southwest
41TV1826 Historic homestead Undetermined 98.4 feet north
41TV1825 Prehistoric lithic
procurement area Ineligible 492.1 feet northeast
41TV2331
Historic
homestead/Prehistoric
lithic scatter
Ineligible On centerline
41TV362
Prehistoric campsite
with burned rock
midden features
Undetermined 1,049.9 feet south
41TV329 Prehistoric lithic
scatter Undetermined 557.7 feet south
41TV1824 Prehistoric lithic
procurement area Undetermined 1,164.7 feet northeast
41TV1061 Prehistoric campsite Ineligible 869.4 feet south
41TV1060 Prehistoric lithic
scatter Ineligible 524.9 feet south
41TV555 Prehistoric campsite Ineligible 377.3 feet north
41TV1077 Prehistoric campsite Ineligible 492.1 feet north
41TV1076 Prehistoric campsite Ineligible 738.2 feet northeast
41TV1071 Prehistoric lithic
procurement area Ineligible 1,082.7 feet north
41TV1068
Prehistoric campsite
and lithic procurement
area
Undetermined 393.7 feet northeast
41TV1066
Prehistoric campsite
and lithic procurement
area
Ineligible 49.2 feet north
41TV1069
Prehistoric campsite
and lithic procurement
area
Ineligible 1,181.1 feet northeast
41TV1067
Prehistoric campsite
and lithic procurement
area
Ineligible 262.5 feet north
41TV1065
Prehistoric campsite
and lithic procurement
area
Ineligible 360.9 feet northeast
41TV344 Historic homestead Undetermined 1,033.5 feet northeast
41BC137 Prehistoric campsite Ineligible 377.3 feet southeast
41BC146 Prehistoric lithic
scatter Ineligible On centerline
41BC91
Prehistoric rock
shelter and lithic
scatter
Undetermined 131.2 feet south
41GL301 Prehistoric campsite Ineligible On centerline
41GL300 Prehistoric campsite Ineligible On centerline
41GL410 Prehistoric lithic Undetermined 853.0 feet south
4-62

<<<PAGE 102>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Site Trinomial,
Cemetery, or Historic
Property
Site Type NRHP Eligibility
Status
Distance/Direction
from Centerline
scatter
41GL310 Prehistoric campsite Ineligible On centerline
41GL367 Prehistoric lithic
scatter Ineligible On centerline
41GL299 Prehistoric lithic
scatter Ineligible On centerline
41GL368 Prehistoric campsite Ineligible On centerline
41GL335 Prehistoric lithic
procurement area Ineligible 1,066.3 feet north
41LL469 Prehistoric campsite Ineligible On centerline
41MS79 Prehistoric lithic
scatter Ineligible On centerline
41MS80 Prehistoric lithic
scatter Ineligible On centerline
41MS81 Prehistoric campsite Ineligible On centerline
41MS27 Prehistoric campsite Undetermined On centerline
41MS65
Prehistoric campsite
with burned rock
midden features
Undetermined On centerline
41KM234 Prehistoric lithic
scatter Ineligible On centerline
41KM206 Prehistoric campsite Ineligible On centerline
41KM165
Prehistoric campsite
with burned rock
midden features
Undetermined On centerline
41KM231 Prehistoric lithic
scatter Ineligible On centerline
41KM207 Prehistoric lithic
scatter Undetermined On centerline
41KM103 No site form available Undetermined On centerline
41KM102 No site form available Undetermined On centerline
41KM232 Prehistoric lithic
scatter Ineligible On centerline
41KM164 Prehistoric lithic
scatter Ineligible On centerline
41KM163
Prehistoric campsite
with burned rock
midden features
Ineligible 164.0 feet south
41KM233 Prehistoric lithic
scatter Ineligible On centerline
41SL23 Prehistoric lithic
scatter Ineligible On centerline
41SL22
Prehistoric campsite
and lithic procurement
area
Ineligible On centerline
41RG42 Prehistoric lithic
scatter Ineligible 853.0 feet northeast
41RG43 Prehistoric campsite Ineligible 591.0 feet northeast
41RG44 Prehistoric campsite Ineligible 721.8 feet northeast
41RG45 Historic stone
structure Ineligible 164.0 feet northeast
41RG46 Prehistoric campsite Ineligible 229.7 feet northeast
41RG50 Prehistoric campsite Ineligible 1,181.1 feet southwest
41RG47 Prehistoric campsite Ineligible 229.7 feet northeast
41RG48 Prehistoric campsite Ineligible 164.0 feet southwest
41RG49 Prehistoric campsite Ineligible 262.5 feet southwest
4-63

<<<PAGE 103>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Site Trinomial,
Cemetery, or Historic
Property
Site Type NRHP Eligibility
Status
Distance/Direction
from Centerline
41RG51 Prehistoric campsite Ineligible 607.0 feet southwest
41RG52 Prehistoric campsite Ineligible 984.3 feet southwest
41RG59 Prehistoric campsite Ineligible On centerline
41RG57 Prehistoric campsite Ineligible On centerline
41RG54 Prehistoric campsite Ineligible 1,082.7 feet northeast
41RG27 Prehistoric campsite Ineligible 721.8 feet northwest
41RG56 Prehistoric campsite Ineligible 1,148.3 feet northeast
Ellerbracht Cemetery Cemetery N/A 1250.0 feet south
Schneider Cemetery Cemetery N/A 1,250.0 feet southwest
Unnamed Cemetery Cemetery N/A 100.0 feet northeast
Community Cemetery Cemetery N/A 542.0 feet north
Higgins Cemetery Cemetery N/A Immediately adjacent
to ROW
Claiborne Cemetery Cemetery N/A 200.0 feet south
Thompson-Morris
Cemetery Cemetery N/A 930.0 feet north
Travis Cemetery Cemetery N/A 620.0 feet north
4.4.2 PUMP STATIONS
4.4.2.1 Buckhorn Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed Buckhorn Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
Based on the Atlas data, this location has not been previously assessed for cultural resources.
However, this station is located within a portion of the existing Longhorn Pipeline ROW that is
defined within the PA as having a low probability for archeological sites. Therefore, no further
investigation is warranted.
4.4.2.2 Industry Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed Industry Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
Based on the Atlas data, this location has not been previously assessed for cultural resources.
However, this station is located within a portion of the existing Longhorn Pipeline ROW that is
defined within the PA as having a low probability for archeological sites. Therefore, no further
investigation is warranted.
4.4.2.3 Warda Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
4-64

<<<PAGE 104>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
existing Warda Station. Similarly, a review of the NPS NRHP Google Earth map layer indicated
the presence of no historic properties listed on the NRHP within the review perimeter. This is an
existing, previously disturbed facility that was previously assessed for cultural resources by TAS
in 2005. This site was previously assessed and documented in a Site Specific Environmental
Study Report (SSESR) to contain no significant cultural resources eligible for the NRHP exist
within the APE of the project.
4.4.2.4 Bastrop Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of two cemeteries within 1,250.0 feet of the Bastrop Station, while a review of the NPS NRHP
Google Earth map layer indicated the presence of no historic properties listed on the NRHP
within the review perimeter. These cultural resources and their distances from the proposed
ROW are summarized below. Based on the Atlas data, this location has not been previously
assessed for cultural resources, although it does border a section of ROW that was surveyed in
2006 with negative results. The proposed site is located within a portion of the Longhorn
Pipeline ROW that is defined within the PA as having a low probability for archeological sites.
Therefore, no further investigation is warranted.
Documented Cultural Resources within 1,250 feet of the Bastrop Station
Site Trinomial,
Cemetery, or Historic
Property
Site Type NRHP Eligibility
Status
Distance/Direction from
Centerline
Community Cemetery Cemetery N/A 900.0 feet east
Unnamed Cemetery Cemetery N/A 1,200.0 feet east
4.4.2.5 Eckert Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
existing Eckert Station. Similarly, a review of the NPS NRHP Google Earth map layer indicated
the presence of no historic properties listed on the NRHP within the review perimeter. This is an
existing, previously disturbed facility. According to the Atlas data, TAS surveyed this site in 2005
with negative results. This site was previously assessed and documented in a SSESR to
contain no significant cultural resources eligible for the NRHP.
4.4.2.6 James River Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed James River Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
Based on the Atlas data, this location has not been previously assessed for cultural resources.
However, it is located within a Longhorn Pipeline AHPA that Horizon surveyed with negative
results.
4-65

<<<PAGE 105>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.4.2.7 Cartman Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed Cartman Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
Based on the Atlas data, this location has not been previously investigated for cultural
resources. However, this station is located within a portion of the Longhorn Pipeline ROW that is
defined within the PA as having a low probability for archeological sites. Therefore, no further
investigation is warranted.
4.4.2.8 Barnhart Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed Barnhart Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
This station is located within a section of the Longhorn Pipeline that TAS, in 2005, and Horizon,
in 2008, surveyed with negative results. This site was previously assessed and documented in a
SSESR to contain no significant cultural resources eligible for the NRHP.
4.4.2.9 Texon Station
A review of the THC’s Atlas website performed by Horizon for this FEA indicated the presence
of no previously recorded archeological sites or cemeteries within a 1,250.0-foot radius of the
proposed Texon Station. Similarly, a review of the NPS NRHP Google Earth map layer
indicated the presence of no historic properties listed on the NRHP within the review perimeter.
Based on the Atlas data, this location has not been previously assessed for cultural resources.
However, this station is located within a portion of the Longhorn Pipeline ROW that is defined as
having a low probability for archeological sites. Therefore, no further investigation is warranted.
4.4.2.10 East Houston Terminal
A review of the THC’s Atlas website indicated the presence of no previously recorded
archeological sites or cemeteries within 1,250.0 feet of the boundaries of the existing East
Houston Terminal. Similarly, a review of the NPS NRHP Google Earth map layer indicated the
presence of no historic properties listed on the NRHP within the review perimeter. Based on the
Atlas data, the majority of the area of this existing terminal has not been previously surveyed for
cultural resources. However, the banks of Hunting Bayou, which runs through this terminal,
were assessed via a reconnaissance level survey with negative results for an assessment
conducted for the Harris County Flood Control District (HCFCD) in 2001. This existing facility is
to undergo infrastructure improvements within the existing facility footprint.
4-66

<<<PAGE 106>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
4.5 REFERENCES
Anaya, R. 2001. An Overview of the Edwards-Trinity Aquifer System, Central–West Texas:
Mace, R.E., Mullican III, W.F., and Angle, E.S. eds. Aquifers of West Texas: Texas
Water Development Board Report 356. pp. 107 – 116.
Anaya, R. 2004. Conceptual Model for the Edwards–Trinity (Plateau) Aquifer System, Texas:
Mace, R.E., Angle, E.S., and Mullican, W.F., III, eds. Aquifers of the Edwards Plateau:
Texas Water Development Board Report 360, pp. 42 – 53.
Anaya, R. and Jones, I. 2009. Groundwater Availability Model for the Edwards-Trinity (Plateau)
and Pecos Valley Aquifers of Texas: Texas Water Development Board Report 373. pp.
25 -34 and 42 – 48.
Ashworth, J.B. 1983. Ground-water Availability of the Lower Cretaceous Formations in the Hill
Country of South-Central Texas: Texas Water Development Board Report 273. pp. 9 –
33, 39 – 44 and 47 – 48.
Ashworth, J.B. 1990. Evaluation of Ground-Water Resources in EI Paso County, Texas: Texas
Water Development Board Report 324. pp. 5 – 6.
Ashworth, J.B. and Hopkins, J. 1995. Aquifers of Texas: Texas Water Development Board
Report 345. pp. 10 – 21, 24 – 27, 31 – 37, 39 -40, 47 – 48, 57 – 58 and 61 – 66.
Asquith, W.H. and Raymond M. Slade, Jr., Regional Equations for Estimation of Peak-
Streamflow Frequency for Natural Basins in Texas. US Geological Survey, Water-
Resources Investigations Report 96-4307, p 62, 1997.
Asquith, W.H., Raymond M. Slade, Jr., and Jennifer Lanning-Rush, US Department of the
Interior, US Geological Survey, Peak-Flow Frequency and Extreme Flood Potential for
Streams in the Vicinity of the Highland Lakes, Central Texas. US Geological Survey,
Water-Resources Investigations Report 96-4072, 1996.
Asquith, W.H., USGS, Peak-Flow Frequency for Tributaries of the Colorado River Downstream
of Austin, Texas, Water-Resources Investigations Report 98-4015, p 18, 1998.
Austin, City of, Watershed Protection Department. The Official Website of the City of Austin.
http://www.austintexas.gov/department/salamander
Baker, E.T., Personal Communication, USGS, 1999.
Barker, Rene A. and Ardis, Ann F., “Hydrogeologic Framework of the Edwards-Trinity Aquifer
US Geological Survey Professional Paper 1421-B, 1996.
Blair, W.F. 1950. The biotic provinces of Texas. Texas Journal of Science 2:93–117.
Blandford, T.N., Blazer, D.J., Calhoun, K.C., Dutton, A.R., Naing, T., Reedy, R.C., and Scanlon,
B.R. 2003. Groundwater Availability of the Southern Ogallala Aquifer in Texas and New
Mexico: Numerical Simulations Through 2050: Texas Water Development Board Report
No. __. pp. 14 – 20 and 25 – 56.
Boghici, R. and Van Broekhoven, N.G. 2001. Hydrogeology of the Rustler Aquifer, Trans-Pecos
Texas: Mace, R.E., Mullican III, W.F., and Angle, E.S. eds. Aquifers of West Texas:
Texas Water Development Board Report 356. pp. 207 – 219.
Bonn, T.D., Existing Reservoir and Steam Management Recommendations: Lower Colorado
River, 1979, TPWD, Job Completion Report, 1980.
4-67

<<<PAGE 107>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Bradley, R.G., and Kalaswad, S. 2001. The Dockum Aquifer in West Texas: Mace, R.E.,
Mullican III, W.F., and Angle, E.S. eds. Aquifers of West Texas: Texas Water
Development Board Report 356. pp. 167 – 172.
Bradley, R.G., and Kalaswad, S. 2003. The Groundwater Resources of the Dockum Aquifer in
Texas: Texas Water Development Board Report 359. pp. 8 – 35.
Bradley, R.G., and Kalaswad, S. 2004. The Dockum Aquifer in the Edwards Plateau: Mace,
R.E., Angle, E.S., and Mullican, W. F., III, eds. Aquifers of the Edwards Plateau: Texas
Water Development Board Report 360, pp. 152 – 157.
Burlakova, L. E., Karatayev, A. Y., Karatayev, V. A., Mays, M. E., Bennett, D. L., and M. J.
Cook. 2010. Endemic species: Contribution to community uniqueness, effect of habitat
alteration, and conservation priorities. Biological Conservation (2010), doi:
10.1016/j.biocon.2010.08.010.
Campbell, Linda. 1996. Exploring Texas Ecoregions. Texas Parks and Wildlife Department.
Austin
Carr, J.T., Jr., The Climate and Physiography of Texas, Texas Water Development Board
Report 53, p 27, 1967.
Chowdhury, A.H. and Turco, M.J. 2006. Geology of the Gulf Coast Aquifer, Texas: Mace, R.E.,
Mullican III, W.F., and Angle, E.S. eds. Aquifers of the Gulf Coast of Texas: Texas
Water Development Board Report 365. pp. 37 – 44.
Davidson, S.C. and Mace, R.E. 2006. Aquifers of the Gulf Coast of Texas: An Overview: Mace,
R.E., Mullican III, W.F., and Angle, E.S. eds. Aquifers of the Gulf Coast of Texas: Texas
Water Development Board Report 365. pp. 1 – 10.
Davidson, S.C. Brown, B.J. and Mace, R.E. 2009. Aquifers of the Upper Coastal Plains:
Hutchison, W.R., Davidson, S.C., Brown, B.J. and Mace, R.E. eds. Aquifers of the Upper
Coastal Plains of Texas: Texas Water Development Board Report 374. pp. 5 – 10.
DeCook, K.J. 1960. Geology and Ground-Water of Hays County, Texas: Texas Board of Water
Engineers (TBWE) Bulletin 6004. pp. 11 – 36 and 50 – 54.
Deeds, N.E., Fryar, D., Dutton, A., and Nicot, J. 2009. Hydrogeology of the Carrizo-Wilcox
Aquifer: Hutchison, W.R., Davidson, S.C., Brown, B.J. and Mace, R.E. eds. Aquifers of
the Upper Coastal Plains of Texas: Texas Water Development Board Report 374. pp.
35 - 50.
Department of Transportation (DOT), Federal Highway Administration, “Stream Stability at
Highway Structures,” Hydraulic Engineering Circular No. 20, February 1991.
Dixon, J.R. 2000. Amphibians and Reptiles of Texas. Texas A&M University Press, College
Station.
Dunn, David, “Trends in Nutrient Inflows to the Gulf of Mexico From Streams Draining the
Conterminous United States, 1972-1983,” US Geological Survey, Water-Resources
Investigations Report 96-4133, 1996.
Dutton, A.R., Harden, B., Nicot, J., and O’Rourke, D. 2003. Groundwater Availability Model for
the Central Part of the Carrizo-Wilcox Aquifer in Texas: Texas Water Development
Board Contract Number 2001-483-378. pp. 19 – 28 and 32 – 34.
El-Hage, Albert; Moulton, Daniel. 1998. Evaluation of Selected Natural Resources in El Paso
County, Texas. Texas Parks and Wildlife, Austin
4-68

<<<PAGE 108>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Escabar, R., Personal Communication, Facilities Manager, Ysleta ISD, 1999.
Federal Register. 2011. 62166 / Vol. 76, No. 194 / Thursday, October 6, 2011 / Proposed Rules
Department of the Interior Fish and Wildlife Service 50 CFR Part 17 [FWS–R2–ES–
2011–0079; MO 92210–0–0008 B2] Endangered and Threatened Wildlife and Plants;
12-Month Finding on a Petition To List Texas Fatmucket, Golden Orb, Smooth
Pimpleback, Texas Pimpleback, and Texas Fawnsfoot as Threatened or Endangered
AGENCY: Fish and Wildlife Service, Interior. ACTION: Notice of 12-month petition.
Fish and Wildlife Service (FTWS), 2011. Endangered species list: list of species by county for
Texas. http://www.fws.gov/southwest/es/EndangeredSpecies/ (accessed June 10,
2011).
Google Earth Pro (Accessed June 2011)
Gould, F.W., G.O. Hoffman, and C.A. Rechenthin. 1960. Vegetational areas of Texas. Texas
Agricultural Extension Service. L-492.
Griffith, G., Bryce, S., Omernik, J., Comstock, J., Rogers, A., Harrison, B., Hatch, S., and
Bezanson, D. 2004. Ecoregions of Texas (color poster with map, descriptive text, and
photographs): Reston, Virginia, U.S. Geological Survey (map scale 1:2,500,000).
Harris Galveston Subsidence Districts website with 1906-2000 Subsidence Contour map:
http://mapper.subsidence.org/Static%20Maps/SubsidenceMap1906-2000.pdf)
Hatch, S.L., K.N. Gandhi, and L.E. Brown. 1990. Checklist of the vascular plants of Texas.
Texas Agricultural Experiment Station, College Station.
Hauwert, N., Hunt, B., Gary, M., and Johnson, S., 2010, Blanco River Recharges Barton
Springs During Drought, Save Barton Creek Association.
http://savebartoncreek.org/blanco-river-recharges-barton-springs-during-drought/.
Accessed on April 11, 2012.
Hauwert, N.M. 2009. Groundwater Flow and Recharge within the Barton Springs Segment of
the Edwards Aquifer, Southern Travis and Northern Hays Counties, Texas: The
University of Texas, Austin, Doctoral Dissertation CM-CM-2009-1.
Hauwert, N.M. and Hiers, S.E. 2010. Understanding Upland Recharge for Geologic
Assessment: Austin Geological Society Guidebook TM-2009-1.
Howells, R. G. 2000. Distributional Surveys of Freshwater Bivalves in Texas. Progress Report
for 1999. TPWD Data Series 170.
Howells, R. G. 2001. Distributional Surveys of Freshwater Bivalves in Texas. Progress Report
for 2000. TPWD Data Series 187.
Howells, R. G. 2002. Distributional Surveys of Freshwater Bivalves in Texas. Progress Report
for 2001. TPWD Data Series 200.
Howells, R. G. 2004. Distributional Surveys of Freshwater Bivalves in Texas. Progress Report
for 2003. TPWD Data Series 222.
Howells, R. G. 2005. Distributional Surveys of Freshwater Bivalves in Texas. Progress Report
for 2004. TPWD Data Series 233.
Howells, R. G. 2006. Statewide Freshwater Mussel Survey. State Wildlife Grant Report to
TPWD.
Howells, R. G., Neck, R. W., and H. D. Murray. 1996. Freshwater Mussels of Texas. 218 pp.
4-69

<<<PAGE 109>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Jones, I.C. 2001. Cenozoic Pecos Alluvium Aquifer: Mace, R.E., Mullican III, W.F., and Angle,
E.S. eds. Aquifers of West Texas: Texas Water Development Board Report 356. pp.
121 – 128.
Jones, I.C. 2004. Cenozoic Pecos Alluvium Aquifer: Mace, R.E., Angle, E.S., and Mullican,
W.F., III, eds. Aquifers of the Edwards Plateau: Texas Water Development Board Report
360, pp. 135 – 144.
Jones, I.C., Anaya, R. and Wade, S. 2009. Groundwater Availability Model for the Hill Country
Portion of the Trinity Aquifer System, Texas: Texas Water Development Board Report.
pp. 6 – 14 and 15 – 17.
Kasmarek, M.C. and Robinson, J.L. 2004. Hydrogeology and Simulation of Ground-Water Flow
and Land-Surface Subsidence in the Northern Part of the Gulf Coast Aquifer System,
Texas: U.S. Geological Survey Scientific Investigations Report 2004–5102. pp 10-36.
Kelley, V.A., Deeds, N.E., Fryar, D.G. and Nicot, J. 2004. Groundwater Availability Models for
the Queen City and Sparta Aquifers: Texas Water Development Board, Austin. pp. 2-25
– 2-28 and 4-1.
Kelley, V.A., Fryar, D.G. and Deeds, N.E. 2009. Hydrogeology of the Queen City and Sparta
Aquifers with an Emphasis on Regional Mechanisms of Discharge: Hutchison, W.R.,
Davidson, S.C., Brown, B.J. and Mace, R.E. eds. Aquifers of the Upper Coastal Plains of
Texas: Texas Water Development Board Report 374. pp. 90 – 104.
Land, L. F., Hunt, B.B., Smith, B.A., and Lemonds, P.J., 2011. Hydrologic Connectivity in the
Edwards Aquifer between San Marcos Springs and Barton Springs during 2009 Drought
Conditions: Texas Water Journal, Volume 2, Number 1, Texas Water Resources
Institute. pp. 39, 40, 47 and 50.
Mace, R.E. 2001. Aquifers of West Texas: An Overview: Mace, R.E., Mullican III, W.F., and
Angle, E.S. eds. Aquifers of West Texas: Texas Water Development Board Report 356.
pp. 3 – 9.
Mace, R.E., Angle, E.S. 2004 Aquifers of the Edwards Plateau: Mace, R.E., Angle, E.S., and
Mullican, W.F., III, eds. Aquifers of the Edwards Plateau: Texas Water Development
Board Report 360. pp. 6 – 12.
McMahan, C.A., R.G. Frye, and K.L. Brown. 1984. The vegetation types of Texas, including
cropland. Wildlife Division, Texas Parks and Wildlife Department, Austin.
National Park Service’s National Register of Historic Places Google Earth Map Layer – South
Region. http://nrhp.focus.nps.gov/natreg/docs/Google_Earth_Layers.html.
O’Rourke, D. 2006. Conjunctive Use of the Brazos River Alluvium Aquifer: Mullican III, W.F.,
and Angle, E.S. eds. Aquifers of the Gulf Coast of Texas: Texas Water Development
Board Report 365. pp. 61 – 67.
Pemberton, E.L., and J.M Lara, “Computing Degradation and Local Scour,” Technical Guideline
for Bureau of Reclamation, 1984.
Pettyjohn, W.A., Savoca, M.E., and Self, Dale, “Regional Assessment of Aquifer Vulnerability
and Sensitivity in the Continental United States,” US Environmental Protection Agency
Report EPA/600/2-91/043, p 319, 1991.
Preston, R.D. 2006. The Yegua-Jackson Aquifer: Mace, R.E., Mullican III, W.F., and Angle,
E.S. eds. Aquifers of the Gulf Coast of Texas: Texas Water Development Board Report
365. pp. 53 – 56.
4-70

<<<PAGE 110>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Rines, T.N., Peak-Discharge Frequency and Potential Extreme Peak Discharge for Natural
Rose, P.R. 1972. Edwards Group, Surface and Subsurface, Central Texas: The University of
Texas, Austin, Bureau of Economic Geology Report of Investigations 74. pp. 18 – 20
and 24 – 25.
Schertz, Terry L., Frank C. Wells, and Dane J. Ohe, Sources of Trends in Water-Quality Data
for Selected Streams in Texas, 1975-89 Water Years, US Geological Survey, Water-
Resources Investigations Report 94-4213, 1994.
Simmons, E., Public Waters of Texas, TPWD, In Press.
Small, T.A., Hanson, J.A., and Hauwert, N.M. 1996. Geologic Framework and Hydrogeologic
Characteristics of the Edwards Aquifer Outcrop (Barton Springs Segment), Northeastern
Hays and Southwestern Travis Counties, Texas: U.S. Geological Survey Water-
Resources Investigations Report 96–4306. pp 4-11.
Smith, R. 2004. Paleozoic Aquifers of the Llano Uplift: Mace, R.E., Angle, E.S., and Mullican,
W.F., III, eds. Aquifers of the Edwards Plateau: Texas Water Development Board Report
360, pp. 183 -191
Standen, A. and Ruggiero, R. 2007. Llano Uplift Aquifers Structure and Stratigraphy:
0604830614. pp. 2 – 7.
Standen, A.R., and Opdyke, D.R. 2004. Contamination Migration, Characteristics, and
Responses for the Edwards–Trinity (Plateau) Aquifer: Mace, R.E., Angle, E.S., and
Mullican, W.F., III, eds. Aquifers of the Edwards Plateau: Texas Water Development
Board Report 360, pp. 211-218.
Stoeser, D.B., Green, G.N., Morath, L.C., Heran, W.D., Wilson, A.B., Moore, D.W., and Van
Gosen, B.S. 2005. Preliminary integrated geologic map databases for the United States:
Central States: Montana, Wyoming, Colorado, New Mexico, North Dakota, South
Dakota, Nebraska, Kansas, Oklahoma, Texas, Iowa, Missouri, Arkansas, and Louisiana:
U.S. Geological Survey Open-File Report 2005-1351.
http://pubs.usgs.gov/of/2005/1351/#TX. Accessed on April 28, 2011.
Streams in the Brazos River Basin, Texas, US Geological Survey, Water-Resources
Investigations Report 98-4178, p 34, 1998.
Texas Commission on Environmental Quality (TCEQ) database, TNRIS database,
http://www.tceq.state.tx.us/gis/.
Texas Commission on Environmental Quality (TCEQ), 2002. Effects of Leaking Petroleum
Storage Tanks on the Trinity Group Aquifer: TCEQ publication SFR-073. pp. vii – viii, 6
and 15 – 30.
Texas Commission on Environmental Quality (TCEQ), 2005. Texas Nonpoint Source
Management Program: SFR-068/04. Appendix D: Aquifer Vulnerability Ranking
System. pp. 254 – 256.
Texas Commission on Environmental Quality (TCEQ), 2011. Website:
http://www.tceq.state.tx.us/cgi-bin/compliance/monops/8hr_attainment.pl
Texas Commission on Environmental Quality (TCEQ), 2012. Underwater life in Barton Springs.
Available on the internet at: http://www.tec.org/bartonsprings/hansen_1.html. Accessed
on February 21, 2012.
4-71

<<<PAGE 111>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Texas Commission on Environmental Quality (TCEQ). Source Water Assessment Viewer.
http://gis3.tceq.state.tx.us/swav/Controller/index.jsp?wtrsrc=
Texas Historical Commission (THC). Atlas Texas Archeological Sites Atlas Restricted
Database. http://www.pedernales.thc.state.tx.us/.
Texas Parks and Wildlife Department (TPWD), 1984. The Vegetation Types of Texas Map.
Austin, Texas.
Texas Parks and Wildlife Department (TPWD), 2009. Commission Agenda Item No. 7. Action
Listing of Certain Mussel Species as State-Threatened. November 5, 2009.
http://www.tpwd.state.tx.us/business/feedback/meetings/2010/1105/agenda/item_7/
Texas Parks and Wildlife Department (TPWD), 2011. “The Rare, Threatened, and Endangered
Species by County” web page.
http://www.tpwd.state.tx.us/landwater/land/maps/gis/ris/endangered_species/
Texas Parks and Wildlife Department (TPWD), 2011. Annotated County Lists of Rare,
Threatened, and Endangered Species for Austin, Bastrop, Blanco, Crane, Crockett,
Culberson, Ector, El Paso, Fayette, Gillespie, Harris, Hays, Hudspeth, Kimble, Mason,
Menard, Pecos, Reagan, Reeves, Schleicher, Travis, Upton, Waller, and Ward Counties
Texas Parks and Wildlife Department (TPWD), 2011. Find a park. Accessed 15 June 2011 at
http://www.tpwd.state.tx.us/spdest/findadest/.
Texas Parks and Wildlife Department (TPWD), 2011. Natural Regions of Texas Map. Adapted
from Preserving Texas’ Natural Heritage, LBJ School of Public Affairs Policy Research
Project 31, 1978.
Texas Parks and Wildlife Department (TPWD), 2011. Plant Guidance by Ecoregions.
http://www.tpwd.state.tx.us/huntwild/wild/wildscapes/guidance/plants/ecoregions/
(Accessed June1, 2011)
Texas Parks and Wildlife Department (TPWD), 2012. Factsheet, Barton Springs Salamander
(Eurycea sosorum),
http://www.tpwd.state.tx.us/huntwild/wild/species/bartonspringssalamander/
Texas Parks and Wildlife Department (TPWD), Nov. 5, 2009. 15 Texas Freshwater Mussels
Placed on State Threatened List.
http://www.tpwd.state.tx.us/newsmedia/releases/?req=20091105c&nrtype=all&nrspan=2
009&nrsearch= (accessed June 2, 2011).
Texas Water Development Board (TWDB), 2011. Source Water Assessment Viewer.
http://gis3.tceq.state.tx.us/swav/Controller/index.jsp?wtrsrc= . PWS Wells and Intakes
database. Well Capture Zones database. Accessed on April 28, 2011.
Texas Water Development Board (TWDB). 2007. GIS Data. Major Aquifers of Texas Shapefiles
and Minor Aquifers of Texas Shapefiles.
http://www.twdb.state.tx.us/mapping/gisdata.asp. Accessed on April 28, 2011.
Texas Water Development Board (TWDB). 2007. Water for Texas: Document No. GP-8-1.
Volume II. Ch. 7. pp. 176-186, 190-195, 197-201, 205, 207-209, 211, 213-214, and 216-
217.
Thomas, C., Bonner, T., and Whiteside, B. 2007. Freshwater Fishes of Texas: A Field Guide.
Texas A&M Press, College Station, Texas.
4-72

<<<PAGE 112>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Turner, M. and O’Donnell, L. 2004. Response Tier Development Document Barton Springs
Salamander Catastrophic Spill Plan. SR-05-01.
U.S. Census Bureau. 2009. 2009 population estimates. Retrieved 15 June 2011 from
http://factfinder.census.gov/servlet/SAFFPopulation?_submenuId=population_0&_sse=o
n
U.S. Department of Transportation (DOT). 2000. Pipeline Safety: Areas Unusually Sensitive to
Environmental Damage: 49 CFR Part 195. Federal Register, Vol. 65, No. 246. pp.
80532 and 80544.
U.S. Environmental Protection Agency (EPA), 1999. Region 6 Office, Final Longhorn
Environmental Assessment (original) for the Longhorn Pipeline: See
http://www.epa.gov/region6/6en/xp/longhorn.htm.
U.S. Environmental Protection Agency (EPA), 2011. Watersheds Homepage.
http://water.epa.gov/type/watersheds/ (Accessed June 13, 2011).
U.S. Environmental Protection Agency (EPA), DRASTIC: A Standardized System for Evaluating
Groundwater Pollution Potential Using Hydrogeologic Settings” (EPA/600/2-87/035 June
1987).
U.S. Environmental Protection Agency (EPA), Region 6, EPA STORET database records @
http://www.epa.gov/storpubl
U.S. Environmental Protection Agency (EPA). 1991. Regional Assessment of Aquifer
Vulnerability and Sensitivity in the Conterminous United States: EPA/600/2-91/043. pp.
5 – 8 and 207.
URS Dames & Moore, Calculation of Fluid Loads on Pipeline, May 9, 2000.
URS Radian. Summary of Scour-related Study, June 2000.
Veenhuis, J.E., US Geological Survey, "Water-Quality Management" section by David Buzan,
Texas Water Commission, National Water Summary 1990-91 - Stream Water Quality:
Texas, US Geological Survey Water Supply Paper 2400, 1992.
Walker, L.E. 1979. Occurrence, Availability and Chemical Quality of Ground Water in the
Edwards Plateau Region of Texas: Texas Water Development Board Report 235. pp.
47 – 55.
Wierman, D.A., Broun, A.S., and Hunt, B.B. 2010. Hydrogeologic Atlas of the Hill Country Trinity
Aquifer, Blanco, Hays, and Travis Counties, Central Texas: Prepared by the Hays-
Trinity, Barton Springs/Edwards Aquifer, and Blanco Pedernales Groundwater
Conservation Districts.
Winemiller, K., Lujan, N. K., Wilkins, R. N., Snelgrove, R. T., Dube, A. M., Skow, K. L., and A. G.
Snelgrove. 2010. Status of Freshwater Mussels in Texas. 64 pp.
http://irnr.tamu.edu/media/297520/status_of_freshwater_mussels_in_texas_tamu-
irnr_05-2010_1.pdf
Young, S.C., Knox, P.R., Baker, E., Budge, T., Hamlin, S., Galloway, B., Kalbouss, R., and
Deeds, N. 2010. Hydrostratigraphy of the Gulf Coast Aquifer from the Brazos River to
the Rio Grande: Report ###: Texas Water Development Board, Austin, Texas. pp 7-28,
47-61 and 88-95.
4-73

<<<PAGE 113>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 4
TABLES

<<<PAGE 114>>>

Table 4.1.1-1 Apartment Facilities within the Zone of Potential
Impact of Proposed Project
Facility Name Address
Estimated
Number
of Units
Houston Area
Justill’s Apartments Holland between Munn St. and Flaxman St. 20
Lake Crest Village Apartments 9393 Tidwell Rd. 224
Commons of Grace 9110 Tidwell Rd. 108
Sterlingshire 9002 Sterlingshire St. 200
Dyersdale Village 9700 Mesa Dr. 152
Glenwood Forest Apartments 8600 Sterlingshire St. 159
Swiss Village 9603 Homestead Rd. 32
Unnamed duplex Haddick Street and Caddo Road 2
Unnamed duplex Madera Road between Wiloak St. and Haddick St. 2
Unnamed duplex Madera Road between Wiloak St. and Haddick St. 2
Unnamed duplex Madera Road and Wiloak Street 2
Unnamed duplex Charlesmont St. and Wiloak St. 2
Unnamed duplex Charlesmont St. and Rhobell St. 2
Unnamed triplex Caddo Road between Greenwich St. and Wiloak St. 3
Unnamed duplex Caddo Road between Greenwich St. and Wiloak St. 2
Unnamed duplex Rhobell St. and Greenwich St. 2
Unnamed duplex Rhobell St. and Greenwich St. 2
Unnamed duplex Greenwich St. and Bigwood St. 2
Unnamed duplex Cabot St. and Greenwich St. 2
Unnamed duplex Cabot St. and Greenwich St. 2
Unnamed duplex Claiborne St. and Greenwich St. 2
Unnamed duplex Claiborne St. and Greenwich St. 2
Unnamed duplex Gallahad St. between Greenwich St. and Wiloak St. 2
North Forest Trails Apartments 9550 North Wayside Dr. 168
Unidentified structure Galaxy St. and Wayside Dr. 7
Unnamed duplex Okay St. and Langley Rd. 2
Unidentified structure North end of Meadowshire St. 14
Coppertree Village 1415 West Gulf Bank Rd. 168
Unidentified complex W Mount Houston Rd. and W Montgomery Rd. 288
Oaks of Inwood 5300 West Gulf Bank Rd. 376
Park Lane 5714 West Gulf Bank Rd. 48
Chesapeake Village 8430 Antoine Dr. 72
Unidentified Rodney Ray Blvd. and Windfern Rd. 16
Tiburon Apartments 8989 West Rd. 336
Watermarke Apartments 9404 West Rd. 288
Villas At West Road 9500 West Rd. 352
Unidentified complex Jones Rd. and Steeplepark Dr. 39

<<<PAGE 115>>>

Table 4.1.1-1 Apartment Facilities within the Zone of Potential Impact (continued)
Facility Name Address
Estimated
Number
of Units
Winchester Place 10910 Gold Point Dr. 256
Ascot Court 10910 West Rd. 149
Ranchstone 10901 Ranchstone Dr. 160
Stone Canyon 10919 West Rd. 216
Pointe At Steeplechase 8901 Jones Rd. 316
Camden Steeplechase 9001 Jones Rd. 390
Trails At Corinthian Creek 8655 Jones Rd. 36
Trails At Rock Creek 12502 Seattle Slew 656
Bristol Place 11245 West Rd. 390
Meadowlands 12424 Steeple Way Blvd. 192
Sugar Creek 11501 West Rd. 288
Sprucewood 12200 Steeple Way Blvd. 152
Unidentified Steepleway Blvd. and Thoroughbred Dr. 104
Steepleway Downs 11910 Thoroughbred Dr. 224
Unidentified Thoroughbred Dr. and Saville Ln. 64
Unidentified Saville Ln. and Castlebridge Dr. 96
Falls At Copper Lake 9140 Highway 6 North 374
Villas At Huffmeister 15050 Copper Grove Blvd. 294
Villa Toscana 9125 Highway 6 576
Lodge At Copperfield 15125 West Rd. 96
Villages of Copperfield 8727 Point Park Dr. 964
Landmark At Cypress Falls 15511 Tuckerton Dr. 312
Austin Area
Unidentified complex Misty Slope Ln. and Lovely Ln. 100
Bluff Springs Townhomes 7100 Bluff Springs Rd. 104
Waters At Bluff Springs 7707 South IH-35 304
Circle S Apartments 7201 South Congress Ave. 200
Unidentified complex S Congress Ave. between Olguin St. and W Dittmar Rd. 8
Unidentified complex S Congress Ave. between Olguin St. and W Dittmar Rd. 4
Villages of Bella Vista 8515 Brodie Ln. 402
Ridgeview Apartments 8600 Brodie Ln. 336
Camden Stoneleigh 4825 Davis Ln. 432
Legacy at Western Oaks 8801 La Cresada Dr. 479
Unidentified complex Davis Ln. and Beckett Rd. 4

<<<PAGE 116>>>

Table 4.1.1-2 Population within the Zone of Potential Impact of
Proposed Project by MP Segment
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
0.0 1.0 277 0 Harris 2.79 773
1.0 2.0 342 20 Harris 2.79 1,010
2.0 3.0 547 0 Harris 2.79 1,526
3.0 4.0 248 0 Harris 2.79 692
4.0 5.0 14 0 Harris 2.79 39
5.0 6.0 140 0 Harris 2.79 391
6.0 7.0 33 0 Harris 2.79 92
7.0 8.0 22 0 Harris 2.79 61
8.0 9.0 71 0 Harris 2.79 198
3.0 4.0 32 0 Harris 2.79 89
4.0 5.0 29 0 Harris 2.79 81
5.0 6.0 138 0 Harris 2.79 385
6.0 7.0 18 0 Harris 2.79 50
7.0 8.0 96 0 Harris 2.79 268
8.0 9.0 190 0 Harris 2.79 530
9.0 10.0 208 0 Harris 2.79 580
10.0 11.0 226 0 Harris 2.79 631
11.0 12.0 467 684 Harris 2.79 3,211
12.0 13.0 1,028 359 Harris 2.79 3,870
13.0 14.0 1,368 7 Harris 2.79 3,836
14.0 15.0 1,657 34 Harris 2.79 4,718
15.0 16.0 704 0 Harris 2.79 1,964
16.0 17.0 1,425 0 Harris 2.79 3,976
17.0 18.0 771 0 Harris 2.79 2,151
18.0 19.0 602 0 Harris 2.79 1,680
19.0 20.0 817 0 Harris 2.79 2,279
20.0 21.0 885 14 Harris 2.79 2,508
21.0 22.0 1,422 0 Harris 2.79 3,967
22.0 23.0 1,678 168 Harris 2.79 5,150
23.0 24.0 727 0 Harris 2.79 2,028
24.0 25.0 551 712 Harris 2.79 3,524
25.0 26.0 969 72 Harris 2.79 2,904
26.0 27.0 353 1 Harris 2.79 988
27.0 28.0 713 0 Harris 2.79 1,989
28.0 29.0 451 16 Harris 2.79 1,303
29.0 30.0 347 336 Harris 2.79 1,906
30.0 31.0 1,118 640 Harris 2.79 4,905
31.0 32.0 708 1,526 Harris 2.79 6,233

<<<PAGE 117>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
32.0 33.0 274 2,202 Harris 2.79 6,908
33.0 34.0 139 0 Harris 2.79 388
34.0 35.0 9 1,244 Harris 2.79 3,496
35.0 36.0 2,679 1,372 Harris 2.79 11,302
36.0 37.0 2,174 0 Harris 2.79 6,065
37.0 38.0 1,282 0 Harris 2.79 3,577
38.0 39.0 280 0 Harris 2.79 781
39.0 40.0 192 0 Harris 2.79 536
40.0 41.0 0 0 Harris 2.79 0
41.0 42.0 0 0 Harris 2.79 0
42.0 43.0 0 0 Harris 2.79 0
43.0 44.0 3 0 Harris 2.79 8
44.0 45.0 0 0 Harris 2.79 0
45.0 46.0 0 0 Harris 2.79 0
46.0 47.0 0 0 Harris 2.79 0
47.0 48.0 0 0 Harris 2.79 0
48.0 49.0 0 0 Harris 2.79 0
49.0 50.0 0 0 Harris 2.79 0
28,491 9,407 Harris Total 105,735
50.0 51.0 0 0 Waller 2.79 0
51.0 52.0 0 0 Waller 2.79 0
52.0 53.0 0 0 Waller 2.79 0
53.0 54.0 0 0 Waller 2.79 0
54.0 55.0 0 0 Waller 2.79 0
55.0 56.0 6 0 Waller 2.79 17
56.0 57.0 2 0 Waller 2.79 6
57.0 58.0 6 0 Waller 2.79 17
58.0 59.0 7 0 Waller 2.79 20
59.0 60.0 4 0 Waller 2.79 11
60.0 61.0 0 0 Waller 2.79 0
61.0 62.0 1 0 Waller 2.79 3
62.0 63.0 0 0 Waller 2.79 0
63.0 64.0 2 0 Waller 2.79 6
28 0 Waller Total 78
64.0 65.0 2 0 Austin 2.67 5
65.0 66.0 12 0 Austin 2.67 32
66.0 67.0 3 0 Austin 2.67 8
67.0 68.0 8 0 Austin 2.67 21
68.0 69.0 14 0 Austin 2.67 37
69.0 70.0 11 0 Austin 2.67 29
70.0 71.0 1 0 Austin 2.67 3

<<<PAGE 118>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
71.0 72.0 3 0 Austin 2.67 8
72.0 73.0 7 0 Austin 2.67 19
73.0 74.0 2 0 Austin 2.67 5
74.0 75.0 34 0 Austin 2.67 91
75.0 76.0 36 0 Austin 2.67 96
76.0 77.0 12 0 Austin 2.67 32
77.0 78.0 1 0 Austin 2.67 3
78.0 79.0 0 0 Austin 2.67 0
79.0 80.0 7 0 Austin 2.67 19
80.0 81.0 5 0 Austin 2.67 13
81.0 82.0 1 0 Austin 2.67 3
82.0 83.0 7 0 Austin 2.67 19
83.0 84.0 10 0 Austin 2.67 27
84.0 85.0 10 0 Austin 2.67 27
85.0 86.0 3 0 Austin 2.67 8
86.0 87.0 7 0 Austin 2.67 19
87.0 88.0 7 0 Austin 2.67 19
88.0 89.0 4 0 Austin 2.67 11
89.0 90.0 4 0 Austin 2.67 11
90.0 91.0 2 0 Austin 2.67 5
91.0 92.0 5 0 Austin 2.67 13
92.0 93.0 5 0 Austin 2.67 13
93.0 94.0 20 0 Austin 2.67 53
243 0 Austin Total 649
94.0 95.0 3 0 Fayette 2.44 7
95.0 96.0 3 0 Fayette 2.44 7
96.0 97.0 5 0 Fayette 2.44 12
97.0 98.0 4 0 Fayette 2.44 10
98.0 99.0 1 0 Fayette 2.44 2
99.0 100.0 4 0 Fayette 2.44 10
100.0 101.0 13 0 Fayette 2.44 32
101.0 102.0 15 0 Fayette 2.44 37
102.0 103.0 13 0 Fayette 2.44 32
103.0 104.0 1 0 Fayette 2.44 2
104.0 105.0 5 0 Fayette 2.44 12
105.0 106.0 2 0 Fayette 2.44 5
106.0 107.0 5 0 Fayette 2.44 12
107.0 108.0 4 0 Fayette 2.44 10
108.0 109.0 2 0 Fayette 2.44 5
109.0 110.0 4 0 Fayette 2.44 10
110.0 111.0 2 0 Fayette 2.44 5

<<<PAGE 119>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
111.0 112.0 3 0 Fayette 2.44 7
112.0 113.0 6 0 Fayette 2.44 15
113.0 114.0 4 0 Fayette 2.44 10
114.0 115.0 3 0 Fayette 2.44 7
115.0 116.0 4 0 Fayette 2.44 10
116.0 117.0 1 0 Fayette 2.44 2
107 0 Fayette Total 261
117.0 118.0 2 0 Lee 2.65 5
118.0 119.0 3 0 Lee 2.65 8
5 0 Lee Total 13
119.0 120.0 6 0 Fayette 2.44 15
6 0 Fayette Total 15
120.0 121.0 Bastrop 2.77 0
121.0 122.0 4 0 Bastrop 2.77 11
122.0 123.0 3 0 Bastrop 2.77 8
123.0 124.0 46 0 Bastrop 2.77 127
124.0 125.0 9 0 Bastrop 2.77 25
125.0 126.0 18 0 Bastrop 2.77 50
126.0 127.0 1 0 Bastrop 2.77 3
127.0 128.0 1 0 Bastrop 2.77 3
128.0 129.0 2 0 Bastrop 2.77 6
129.0 130.0 18 0 Bastrop 2.77 50
130.0 131.0 10 0 Bastrop 2.77 28
131.0 132.0 1 0 Bastrop 2.77 3
132.0 133.0 19 0 Bastrop 2.77 53
133.0 134.0 18 0 Bastrop 50
134.0 135.0 30 0 Bastrop 2.77 94
135.0 136.0 0 4 Bastrop 2.77 0
136.0 137.0 0 0 Bastrop 137.0 138.0 0 0 Bastrop 138.0 139.0 1 0 Bastrop 139.0 140.0 5 0 Bastrop 2.77 14
2.77 0
2.77 0
2.77 3
2.77 140.0 141.0 2 0 Bastrop 2.77 6
141.0 142.0 5 0 Bastrop 2.77 14
142.0 143.0 14 0 Bastrop 2.77 39
143.0 144.0 27 0 Bastrop 2.77 75
144.0 145.0 31 0 Bastrop 2.77 86
145.0 146.0 40 0 Bastrop 2.77 111
146.0 147.0 20 0 Bastrop 2.77 55
147.0 148.0 31 0 Bastrop 2.77 86
148.0 149.0 10 0 Bastrop 2.77 28

<<<PAGE 120>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
149.0 150.0 0 0 Bastrop 2.77 0
150.0 151.0 1 0 Bastrop 2.77 3
151.0 152.0 1 0 Bastrop 2.77 3
152.0 153.0 95 0 Bastrop 2.77 263
153.0 154.0 175 0 Bastrop 2.77 485
638 4 Bastrop Total 1,778
154.0 155.0 73 0 Travis 2.47 180
155.0 156.0 2 0 Travis 2.47 5
156.0 157.0 9 0 Travis 2.47 22
157.0 158.0 33 0 Travis 2.47 82
158.0 159.0 148 0 Travis 2.47 366
159.0 160.0 25 0 Travis 2.47 62
160.0 161.0 100 0 Travis 2.47 247
161.0 162.0 22 0 Travis 2.47 54
162.0 163.0 6 0 Travis 2.47 15
163.0 164.0 109 0 Travis 2.47 269
164.0 165.0 606 100 Travis 2.47 1,744
165.0 166.0 756 408 Travis 2.47 2,875
166.0 167.0 295 212 Travis 2.47 1,252
167.0 168.0 520 0 Travis 2.47 1,284
168.0 169.0 622 0 Travis 2.47 1,536
169.0 170.0 835 0 Travis 2.47 2,062
170.0 171.0 342 738 Travis 2.47 2,668
171.0 172.0 634 911 Travis 2.47 3,816
172.0 173.0 805 4 Travis 2.47 1,998
173.0 174.0 267 0 Travis 2.47 659
174.0 175.0 99 0 Travis 2.47 245
175.0 176.0 41 0 Travis 2.47 101
176.0 177.0 50 0 Travis 2.47 124
177.0 178.0 47 0 Travis 2.47 116
178.0 179.0 14 0 Travis 2.47 35
179.0 180.0 55 0 Travis 2.47 136
180.0 181.0 39 0 Travis 2.47 96
6,554 2,373 Travis Total 22,050
181.0 182.0 30 0 Hays 2.69 81
182.0 183.0 65 0 Hays 2.69 175
183.0 184.0 34 0 Hays 2.69 91
184.0 185.0 6 0 Hays 2.69 16
185.0 186.0 10 0 Hays 2.69 27
186.0 187.0 11 0 Hays 2.69 30
187.0 188.0 14 0 Hays 2.69 38

<<<PAGE 121>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
188.0 189.0 13 0 Hays 2.69 35
189.0 190.0 29 0 Hays 2.69 78
190.0 191.0 5 0 Hays 2.69 13
191.0 192.0 5 0 Hays 2.69 13
192.0 193.0 5 0 Hays 2.69 13
227 0 Hays Total 611
193.0 194.0 8 0 Blanco 2.50 20
194.0 195.0 0 0 Blanco 2.50 0
195.0 196.0 0 0 Blanco 2.50 0
196.0 197.0 0 0 Blanco 2.50 0
197.0 198.0 1 0 Blanco 2.50 3
198.0 199.0 1 0 Blanco 2.50 3
199.0 200.0 0 0 Blanco 2.50 0
200.0 201.0 0 0 Blanco 2.50 0
201.0 202.0 0 0 Blanco 2.50 0
202.0 203.0 2 0 Blanco 2.50 5
203.0 204.0 4 0 Blanco 2.50 10
204.0 205.0 3 0 Blanco 2.50 8
205.0 206.0 0 0 Blanco 2.50 0
206.0 207.0 0 0 Blanco 2.50 0
207.0 208.0 0 0 Blanco 2.50 0
208.0 209.0 0 0 Blanco 2.50 0
209.0 210.0 4 0 Blanco 2.50 10
210.0 211.0 0 0 Blanco 2.50 0
211.0 212.0 2 0 Blanco 2.50 5
212.0 213.0 0 0 Blanco 2.50 0
213.0 214.0 2 0 Blanco 2.50 5
214.0 215.0 0 0 Blanco 2.50 0
215.0 216.0 0 0 Blanco 2.50 0
216.0 217.0 0 0 Blanco 2.50 0
217.0 218.0 0 0 Blanco 2.50 0
27 0 Blanco Total 68
218.0 219.0 0 0 Gillespie 2.38 0
219.0 220.0 2 0 Gillespie 2.38 5
220.0 221.0 0 0 Gillespie 2.38 0
221.0 222.0 0 0 Gillespie 2.38 0
222.0 223.0 1 0 Gillespie 2.38 2
223.0 224.0 0 0 Gillespie 2.38 0
224.0 225.0 1 0 Gillespie 2.38 2
225.0 226.0 1 0 Gillespie 2.38 2
226.0 227.0 3 0 Gillespie 2.38 7

<<<PAGE 122>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
227.0 228.0 1 0 Gillespie 2.38 2
228.0 229.0 1 0 Gillespie 2.38 2
229.0 230.0 0 0 Gillespie 2.38 0
230.0 231.0 0 0 Gillespie 2.38 0
231.0 232.0 1 0 Gillespie 2.38 2
232.0 233.0 3 0 Gillespie 2.38 7
233.0 234.0 1 0 Gillespie 2.38 2
234.0 235.0 1 0 Gillespie 2.38 2
235.0 236.0 2 0 Gillespie 2.38 5
236.0 237.0 0 0 Gillespie 2.38 0
237.0 238.0 0 0 Gillespie 2.38 0
238.0 239.0 1 0 Gillespie 2.38 2
239.0 240.0 0 0 Gillespie 2.38 0
240.0 241.0 7 0 Gillespie 2.38 17
26 0 Gillespie Total 62
241.0 242.0 2 0 Llano 2.13 4
2 0 Llano Total 4
242.0 243.0 0 0 Mason 2.31 0
243.0 244.0 0 0 Mason 2.31 0
244.0 245.0 1 0 Mason 2.31 2
245.0 246.0 1 0 Mason 2.31 2
246.0 247.0 0 0 Mason 2.31 0
247.0 248.0 0 0 Mason 2.31 0
248.0 249.0 0 0 Mason 2.31 0
249.0 250.0 1 0 Mason 2.31 2
250.0 251.0 0 0 Mason 2.31 0
251.0 252.0 0 0 Mason 2.31 0
252.0 253.0 2 0 Mason 2.31 5
253.0 254.0 0 0 Mason 2.31 0
254.0 255.0 0 0 Mason 2.31 0
255.0 256.0 0 0 Mason 2.31 0
256.0 257.0 0 0 Mason 2.31 0
257.0 258.0 1 0 Mason 2.31 2
258.0 259.0 0 0 Mason 2.31 0
259.0 260.0 0 0 Mason 2.31 0
260.0 261.0 0 0 Mason 2.31 0
261.0 262.0 0 0 Mason 2.31 0
262.0 263.0 0 0 Mason 2.31 0
263.0 264.0 1 0 Mason 2.31 2
264.0 265.0 0 0 Mason 2.31 0
265.0 266.0 0 0 Mason 2.31 0

<<<PAGE 123>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
266.0 267.0 0 0 Mason 2.31 0
267.0 268.0 1 0 Mason 2.31 2
268.0 269.0 0 0 Mason 2.31 0
269.0 270.0 0 0 Mason 2.31 0
270.0 271.0 0 0 Mason 2.31 0
271.0 272.0 0 0 Mason 2.31 0
272.0 273.0 2 0 Mason 2.31 5
273.0 274.0 1 0 Mason 2.31 2
11 0 Mason Total 25
274.0 275.0 0 0 Kimble 2.37 0
275.0 276.0 0 0 Kimble 2.37 0
276.0 277.0 3 0 Kimble 2.37 7
277.0 278.0 0 0 Kimble 2.37 0
278.0 279.0 0 0 Kimble 2.37 0
279.0 280.0 0 0 Kimble 2.37 0
280.0 281.0 2 0 Kimble 2.37 5
281.0 282.0 0 0 Kimble 2.37 0
282.0 283.0 0 0 Kimble 2.37 0
283.0 284.0 0 0 Kimble 2.37 0
284.0 285.0 0 0 Kimble 2.37 0
285.0 286.0 0 0 Kimble 2.37 0
286.0 287.0 1 0 Kimble 2.37 2
287.0 288.0 3 0 Kimble 2.37 7
288.0 289.0 2 0 Kimble 2.37 5
289.0 290.0 0 0 Kimble 2.37 0
290.0 291.0 1 0 Kimble 2.37 2
291.0 292.0 0 0 Kimble 2.37 0
292.0 293.0 1 0 Kimble 2.37 2
293.0 294.0 0 0 Kimble 2.37 0
294.0 295.0 0 0 Kimble 2.37 0
295.0 296.0 0 0 Kimble 2.37 0
296.0 297.0 0 0 Kimble 2.37 0
297.0 298.0 0 0 Kimble 2.37 0
298.0 299.0 1 0 Kimble 2.37 2
299.0 300.0 0 0 Kimble 2.37 0
300.0 301.0 0 0 Kimble 2.37 0
301.0 302.0 0 0 Kimble 2.37 0
302.0 303.0 0 0 Kimble 2.37 0
303.0 304.0 0 0 Kimble 2.37 0
304.0 305.0 0 0 Kimble 2.37 0
305.0 306.0 1 0 Kimble 2.37 2

<<<PAGE 124>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
306.0 307.0 1 0 Kimble 2.37 2
307.0 308.0 0 0 Kimble 2.37 0
308.0 309.0 0 0 Kimble 2.37 0
309.0 310.0 1 0 Kimble 2.37 2
17 0 Kimble Total 40
310.0 311.0 1 0 Menard 2.34 2
311.0 312.0 0 0 Menard 2.34 0
312.0 313.0 0 0 Menard 2.34 0
1 0 Menard Total 2
313.0 314.0 0 0 Schleicher 2.59 0
314.0 315.0 1 0 Schleicher 2.59 3
315.0 316.0 0 0 Schleicher 2.59 0
316.0 317.0 0 0 Schleicher 2.59 0
317.0 318.0 0 0 Schleicher 2.59 0
318.0 319.0 0 0 Schleicher 2.59 0
319.0 320.0 0 0 Schleicher 2.59 0
320.0 321.0 0 0 Schleicher 2.59 0
321.0 322.0 0 0 Schleicher 2.59 0
322.0 323.0 0 0 Schleicher 2.59 0
323.0 324.0 0 0 Schleicher 2.59 0
324.0 325.0 0 0 Schleicher 2.59 0
325.0 326.0 1 0 Schleicher 2.59 3
326.0 327.0 0 0 Schleicher 2.59 0
327.0 328.0 2 0 Schleicher 2.59 5
328.0 329.0 1 0 Schleicher 2.59 3
329.0 330.0 2 0 Schleicher 2.59 5
330.0 331.0 3 0 Schleicher 2.59 8
331.0 332.0 0 0 Schleicher 2.59 0
332.0 333.0 0 0 Schleicher 2.59 0
333.0 334.0 0 0 Schleicher 2.59 0
334.0 335.0 1 0 Schleicher 2.59 3
335.0 336.0 0 0 Schleicher 2.59 0
336.0 337.0 0 0 Schleicher 2.59 0
337.0 338.0 0 0 Schleicher 2.59 0
338.0 339.0 0 0 Schleicher 2.59 0
339.0 340.0 1 0 Schleicher 2.59 3
340.0 341.0 0 0 Schleicher 2.59 0
341.0 342.0 0 0 Schleicher 2.59 0
342.0 343.0 2 0 Schleicher 2.59 5
343.0 344.0 0 0 Schleicher 2.59 0
344.0 345.0 1 0 Schleicher 2.59 3

<<<PAGE 125>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
345.0 346.0 1 0 Schleicher 2.59 3
346.0 347.0 2 0 Schleicher 2.59 5
347.0 348.0 6 0 Schleicher 2.59 16
348.0 349.0 0 0 Schleicher 2.59 0
349.0 350.0 0 0 Schleicher 2.59 0
350.0 351.0 2 0 Schleicher 2.59 5
351.0 352.0 0 0 Schleicher 2.59 0
352.0 353.0 0 0 Schleicher 2.59 0
353.0 354.0 0 0 Schleicher 2.59 0
354.0 355.0 0 0 Schleicher 2.59 0
355.0 356.0 0 0 Schleicher 2.59 0
356.0 357.0 1 0 Schleicher 2.59 3
357.0 358.0 0 0 Schleicher 2.59 0
358.0 359.0 1 0 Schleicher 2.59 3
359.0 360.0 3 0 Schleicher 2.59 8
360.0 361.0 0 0 Schleicher 2.59 0
361.0 362.0 0 0 Schleicher 2.59 0
362.0 363.0 0 0 Schleicher 2.59 0
363.0 364.0 0 0 Schleicher 2.59 0
364.0 365.0 0 0 Schleicher 2.59 0
365.0 366.0 0 0 Schleicher 2.59 0
31 0 Schleicher Total 80
366.0 367.0 0 0 Crockett 2.65 0
367.0 368.0 0 0 Crockett 2.65 0
368.0 369.0 0 0 Crockett 2.65 0
369.0 370.0 0 0 Crockett 2.65 0
370.0 371.0 0 0 Crockett 2.65 0
371.0 372.0 0 0 Crockett 2.65 0
372.0 373.0 0 0 Crockett 2.65 0
373.0 374.0 0 0 Crockett 2.65 0
374.0 375.0 0 0 Crockett 2.65 0
375.0 376.0 0 0 Crockett 2.65 0
376.0 377.0 0 0 Crockett 2.65 0
377.0 378.0 0 0 Crockett 2.65 0
378.0 379.0 0 0 Crockett 2.65 0
379.0 380.0 0 0 Crockett 2.65 0
380.0 381.0 0 0 Crockett 2.65 0
381.0 382.0 0 0 Crockett 2.65 0
382.0 383.0 0 0 Crockett 2.65 0
383.0 384.0 0 0 Crockett 2.65 0
384.0 385.0 0 0 Crockett 2.65 0

<<<PAGE 126>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
385.0 386.0 0 0 Crockett 2.65 0
386.0 387.0 0 0 Crockett 2.65 0
387.0 388.0 0 0 Crockett 2.65 0
388.0 389.0 0 0 Crockett 2.65 0
389.0 390.0 0 0 Crockett 2.65 0
390.0 391.0 0 0 Crockett 2.65 0
391.0 392.0 0 0 Crockett 2.65 0
0 0 Crockett Total 0
392.0 393.0 Reagan 2.96 0
393.0 394.0 0 0 Reagan 2.96 0
394.0 395.0 0 0 Reagan 2.96 0
395.0 396.0 0 0 Reagan 2.96 0
396.0 397.0 0 0 Reagan 2.96 0
397.0 398.0 0 0 Reagan 2.96 0
398.0 399.0 1 0 Reagan 2.96 3
399.0 400.0 0 0 Reagan 2.96 0
400.0 401.0 0 0 Reagan 2.96 0
401.0 402.0 0 0 Reagan 2.96 0
402.0 403.0 0 0 Reagan 2.96 0
403.0 404.0 0 0 Reagan 2.96 0
404.0 405.0 0 0 Reagan 2.96 0
405.0 406.0 1 0 Reagan 2.96 3
406.0 407.0 0 0 Reagan 2.96 0
407.0 408.0 0 0 Reagan 2.96 0
408.0 409.0 0 0 Reagan 2.96 0
409.0 410.0 0 0 Reagan 2.96 0
410.0 411.0 0 0 Reagan 2.96 0
411.0 412.0 0 0 Reagan 2.96 0
412.0 413.0 0 0 Reagan 2.96 0
413.0 414.0 0 0 Reagan 2.96 0
414.0 415.0 0 0 Reagan 2.96 0
415.0 416.0 0 0 Reagan 2.96 0
416.0 417.0 0 0 Reagan 2.96 0
417.0 418.0 0 0 Reagan 2.96 0
418.0 419.0 0 0 Reagan 2.96 0
419.0 420.0 0 0 Reagan 2.96 0
2 0 Reagan Total 6
420.0 421.0 0 0 Upton 2.68 0
421.0 422.0 0 0 Upton 2.68 0
422.0 423.0 0 0 Upton 2.68 0
423.0 424.0 0 0 Upton 2.68 0

<<<PAGE 127>>>

Table 4.1.1-2 Population within the Zone of Potential Impact by MP Segment
(continued)
Mile Segment Single-Family
Units
Multi-Family
Units County
Persons Per
Household
Estimated
Population
From To
424.0 425.0 0 0 Upton 2.68 0
425.0 426.0 0 0 Upton 2.68 0
426.0 427.0 0 0 Upton 2.68 0
427.0 428.0 0 0 Upton 2.68 0
428.0 429.0 0 0 Upton 2.68 0
429.0 430.0 0 0 Upton 2.68 0
430.0 431.0 0 0 Upton 2.68 0
431.0 432.0 0 0 Upton 2.68 0
432.0 433.0 0 0 Upton 2.68 0
433.0 434.0 0 0 Upton 2.68 0
434.0 435.0 0 0 Upton 2.68 0
435.0 436.0 0 0 Upton 2.68 0
436.0 437.0 0 0 Upton 2.68 0
437.0 438.0 0 0 Upton 2.68 0
438.0 439.0 0 0 Upton 2.68 0
439.0 440.0 0 0 Upton 2.68 0
440.0 441.0 0 0 Upton 2.68 0
441.0 442.0 0 0 Upton 2.68 0
442.0 443.0 0 0 Upton 2.68 0
443.0 444.0 0 0 Upton 2.68 0
444.0 445.0 0 0 Upton 2.68 0
445.0 446.0 0 0 Upton 2.68 0
446.0 447.0 0 0 Upton 2.68 0
447.0 448.0 0 0 Upton 2.68 0
448.0 449.0 0 0 Upton 2.68 0
449.0 450.0 0 0 Upton 2.68 0
450.0 451.0 0 0 Upton 2.68 0
451.0 452.0 0 0 Upton 2.68 0
452.0 453.0 0 0 Upton 2.68 0
453.0 454.0 0 0 Upton 2.68 0
0 0 Upton Total 0
454.0 455.0 0 0 Crane 2.91 0
455.0 456.0 0 0 Crane 2.91 0
456.0 457.0 0 0 Crane 2.91 0
Crane Total 0
Grand Total 131,477

<<<PAGE 128>>>

Table 4.1.2-1 Vulnerable Receptors within the Zone of Potential
Impact of the Proposed Project in the Houston Area
Facility Approximate Location
Public Schools
Kipp North Forest Lower School 9634 Mesa Rd.
Kipp Voyage Academy for Girls 10711 Kipp Way
Kipp Legacy Preparatory School 10711 Kipp Way
Kipp Polaris Academy for Boys 10711 Kipp Way
Kipp North Forest Lower Girls School 10711 Kipp Way
Kirby Middle School 9709 Mesa Dr.
Yes Prep North Forest Campus 9709 Mesa Dr.
W.E. Rogers Elementary School 10550 James L. Reaux Dr.
Fonwood Elementary School 10710 Seneca St.
Scarborough Elementary School 3021 Little York Rd.
Texas Serenity Academy 530 N Sam Houston parkway, Suite 213
Carroll Academy 423 W Gulfbank Rd.
Keeble EC/Pre-K Center 203 W Gulfbank Rd.
Eiland Elementary School 6700 N Klein Circle Dr.
Klein Intermediate 4710 W Mount Houston Rd.
Labay Middle School 15435 Willow River Dr.
Nitsch Elementary School 4702 W Mount Houston Rd.
Ralph G. Goodman Elementary School 9325 Deer Trail Dr.
Fiest Elementary School 8425 Pine Falls
Bang Elementary School 8900 Rio Grande
Gleason Elementary School 9202 Willowbridge Park Blvd.
Cypress Fall High School 9811 Huffmeister Rd.
Rennell Elementary School 19500 Tuckerton Blvd.
Eisenhower Ninth Grade School 3550 West Gulf Bank Rd.
Cook Middle School 9811 Huffmeister Rd.
Reed Elementary School 8700 Tami Renee
Eisenhower Senior High School 7922 Antoine Dr.
Worsham Elementary School 3007 Hartwick Rd.
B.C. Elmore Middle School 8200 Tate
Pyburn Elementary School 12302 Coulson St.
Private Schools
Northeast Christian School 7300 Langley Rd.
Sandcastle Montessori Academy 15226 West Rd.
Cypress Montessori School 9507 Huffmeister Rd.
Leading Stars Montessori School 15330 Willow River Dr.
Woodland Acres Christian School 12338 Coulson St.
Healthcare Facilities
Houston Community Hospital (St. Anthony’s)
Parks

<<<PAGE 129>>>

Table 4.1.2-1 Vulnerable Receptors within the Zone of Potential Impact
in the Houston Area (continued)
Facility Approximate Location
Clark Henry Park Equador St. north of Jersey Dr.
Groveland Terrace Park 3921 Herald St.
Circle Drive Park Circle Dr. at US 90
Smith Park Smith Park Rd. and Market Street Rd.
Stuebner-Airline Park 9201 Veterans Memorial Dr.
West Mount Houston Park 10300 N. Houston Rosslyn Rd.
Pinewood Village Park 2800 Briarwick Ln.
Withers Park 10400 Royal Pine Dr.
Keith Wiess Park 12300 Aldine Westfield Rd.
Gleason Park 7200 Gleason Rd.
Lake Forest Park Lake Park St. and E Houston Dyersdale Rd.
Scenic Woods Park Gleason Rd. and Cheeves Dr.
Tidwell Park 9720 Spaulding St.
Hirsch Road Park 10800 Hirsch Rd.
Brock Park 8201 John Ralston Rd.
Strickland Park 300 High Ridge St.
Cool Green Corridor 12800 Coolgreen Ave.
Herman Brown Park 400 Mercury Dr.
Circle Drive Park 90 Circle Dr.
Cullen Park 19008 Saums Rd.
East Tidwell Park 9300 E. Tidwell Rd.
Halls Bayou Park 8000 Tidwell Rd.
Langham Creek Park 9701 Barker Cypress Rd
James Driver Park 10918 ½ Bentley St.
Paul D. Rushing Park 9114 Katy Hockley Rd.
Ella Hike and Bike Trail 8700 Ella Blvd.
John Paul's Landing Katy Hockley Cutoff
Other Recreational Facilities
Texaco Country Club 12800 Texaco Road
Houston National Golf Club 16500 Houston National Blvd.
Hearthstone Country Club 7615 Ameswood

<<<PAGE 130>>>

Table 4.1.2-2 Vulnerable Receptors within the Zone of Potential
Impact of the Proposed Project in the Austin Area
Facility Location
Public Schools
Texas Neurorehabilitation Center Campus 1106 W Dittmar Rd.
Langford Elementary School 2206 Blue Meadow Dr.
Boone Elementary School 8101 Croftwood Dr.
Williams Elementary School 500 Mairo
Private Schools
Legacy Oaks Christian School 7915 Manchaca Rd.
Hospitals
Texas Neurorehabilitation Center 1106 W Dittmar Rd.
Parks
Dick Nichols Park 8011 Beckett Rd.
McKinney Falls State Park 5808 McKinney Falls Parkway
Circle C Ranch Metropolitan Park 6301 W. Slaughter Ln.
Goat Cave Karst Nature Preserve 3900 Deer Ln.
Davis Hill Neighborhood Park 3402 Davis Ln.
Dittmar Park and Recreation Center 1009 W. Dittmar Rd.
South Boggy Creek Greenbelt 7701 Circle S Rd.
Onion Creek Greenbelt 7004 Onion Creek Dr.
Richard Moya Park 10001 Burleson Rd.
Onion Creek Soccer Complex 5600 E. William Cannon
Other Recreational Facilities
Jimmy Clay Golf Course 5400 Jimmy Clay Dr.

<<<PAGE 131>>>

Table 4.2.1-1 Aquifers Within the Zone of Potential Impact of
the Proposed Project
Aquifer Age Lithology TWDB
Designation
Gulf Coast Aquifer System Quaternary-
Tertiary Sand, silt clay, and gravel Major Aquifer
Brazos River Alluvium
Aquifer Quaternary
Unconsolidated alluvium including
sand, gravel, with interbedded silts
and clays
Minor Aquifer
Yegua-Jackson Aquifer Tertiary Complexly interbedded sand, silt
and clay Minor Aquifer
Sparta Aquifer Tertiary Interbedded sands and clays Minor Aquifer
Queen City Aquifer Tertiary Sand, loosely cemented sandstone
with interbedded clay Minor Aquifer
Carrizo-Wilcox Aquifer
System Tertiary Sand, sandstone, clay, silt, lignite,
gravel Major Aquifer
Colorado River Alluvium Quaternary
Unconsolidated alluvium, terrace
and high gravel deposits including
sand, gravel, with interbedded silts
and clays
Other1
Edwards Aquifer-Barton
Springs Segment Cretaceous Solutioned and fractured limestones
and dolomites Major
Trinity Aquifer-Hill Country Cretaceous
Upper and Middle are solutioned
and fractured limestones and
dolomites, Lower is sand, gravel,
and conglomerate with interbedded
clay
Major
Marble Falls Aquifer Pennsylvanian Solutioned, faulted and fractured
limestones and dolomites Minor
Ellenburger-San Saba
Aquifer
Cambrian -
Ordovician
Solutioned, faulted and fractured
limestones and dolomites Minor
Hickory Aquifer Cambrian Fractured and faulted sandstone,
medium to coarse grained Minor
Edwards-Trinity (Plateau)
Aquifer Cretaceous Solutioned and jointed limestone,
dolomite and sandstones Major
Pecos Valley Aquifer Quaternary-
Tertiary
Discontinuous alluvium, lacustrine,
eolian and valley fill deposits of
sand, silt, conglomerate, limestone,
mudstone, shale and gypsum
Major
Southern Ogallala Aquifer Quaternary-
Tertiary
Fluvial, lacustrine and eolian
deposits of sand, gravel, silt and
clay
Major
Source: Texas Water Development Board
Note: 1 – Not designated as a Major or Minor Aquifer by the Texas Water Development Board

<<<PAGE 132>>>

Table 4.2.1-2 TCEQ Aquifer Average DRASTIC Index and
Vulnerability Ranking of Aquifers within the Zone of Potential
Impact of the Proposed Project
Major Aquifers Average DRASTIC Index Vulnerability Ranking
Gulf Coast 95 Medium
Carrizo-Wilcox 117 Medium
Edwards (BFZ)-Barton Springs 126 High
Trinity (Hill Country) 95 Medium
Edwards-Trinity (Plateau) 107 Medium
Pecos Valley 95 Medium
Southern Ogallala 99 Medium
Minor Aquifers Average DRASTIC Index Vulnerability Ranking
Brazos River Alluvium 144 High
Yegua-Jackson1 108 Medium
Sparta 98 Medium
Queen City 108 Medium
Marble Falls 126 High
Ellenberger-San Saba 126 High
Hickory 114 Medium
Other Aquifers Average DRASTIC Index Vulnerability Ranking
Colorado River Alluvium2 144 High
1 -- Average DRASTIC Index and Vulnerability Ranking was not available; index and ranking
determination based on most conservative value for the Sparta and Queen City aquifers
which are geologically similar to the Yegua-Jackson Aquifer.
2 -- Average DRASTIC Index and Vulnerability Ranking was not available; index and ranking
determination based on Brazos River Alluvium Aquifer which is geologically similar to the
Colorado River Alluvium Aquifer.

<<<PAGE 133>>>

Table 4.2.1-3 Pettyjohn et. al. Aquifer Classification and
Vulnerability of Aquifers Within the Zone of Potential Impact of
the Proposed Project
Major Aquifers
Pettyjohn et. al.
Classification Rationale Vulnerability
Gulf Coast
Class Ia, Ic and
Class U
Classes Ia & Ic where sands of Lissie
and Oakville formations outcrop,
respectively;
Class U where Beaumont and Cataholu
formations outcrop
High – All Class I
Medium – Class U
Carrizo-Wilcox - Outcrop Class Ic
Sandstone, sand and gravel outcrops of
the Carrizo Formation and Wilcox
Group High
Carrizo-Wilcox - Subcrop Class III
Overlain by more than 50 feet of low
permeability strata of the Reklaw
Formation Low
Edwards (BFZ)-Barton
Springs - Outcrop Class Ib
Outcropping limestone, dolomite and
some evaporates containing known
karst features High
Edwards (BFZ)-Barton
Springs - Subcrop Class III
Overlain by more than 50 feet of low
permeability strata of the Upper
Cretaceous Low
Trinity (Hill Country)-Outcrop
and Under Edwards Outcrop Class IIa
Bedrock aquifer having well yield
commonly exceeding 50 gpm High
Trinity (Hill Country)-Subcrop Class III
Overlain by more than 50 feet of low
permeability strata of the Upper
Cretaceous Low
Edwards-Trinity (Plateau) Class Ib
Outcropping limestone, dolomite and
some evaporates containing known
karst features High
Pecos Valley Class Ia
Massive unconfined alluvium, lacustrine
and eolian deposits High
Southern Ogallala Class 1c
sand and gravel outcrops of the
Ogalalla Formation High
Minor Aquifers
Pettyjohn et. al.
Classification Rationale Vulnerability
Brazos River Alluvium Class Ia
Unconfined, Pleistocene terrace and
Holocene alluvium deposits shallow
watertable High
Yegua-Jackson Class Ic
Sandstone, sand and gravel outcrops of
the Yegua Formation and Jackson
Group High

<<<PAGE 134>>>

Table 4.2.1-3 Pettyjohn et. al. Aquifer Classification and Vulnerability
(continued)
Minor Aquifers
Pettyjohn et. al.
Classification Rationale Vulnerability
Sparta-Outcrop Class Ic
Sandstone, sand and gravel outcrops of
the Yegua Formation and Jackson
Group High
Sparta-Subcrop Class III
Overlain by more than 50 feet of low
permeability strata of the Cook
Mountain Formation Low
Queen City-Outcrop Class Ic
Sandstone, sand and gravel outcrops of
the Yegua Formation and Jackson
Group High
Queen City-Outcrop Class III
Overlain by more than 50 feet of low
permeability strata of the Weches
Formation Low
Marble Falls Class Ib
Outcropping limestone containing
known karst features High
Ellenberger-San Saba Class Ib
Outcropping limestone and dolomite
known karst features High
Hickory Class IIa
Bedrock aquifer having well yield
commonly exceeding 50 gpm High
Colorado River Alluvium Class Ia
Unconfined, Pleistocene terrace and
High Gravel deposits and Holocene
alluvium deposits shallow watertable High

<<<PAGE 135>>>

Table 4.2.1-4 Groundwater Resource Area Sensitivity Ranking
Starting
MP
Ending
MP Aquifer
TCEQ
Vulnerability
Ranking
Pettyjohn
et al
Ranking
Aquatic
Habitat
Ranking
PWS
Water
Well
Ranking
Sum of
Rankings
Sensitive
Area
9.47a 3 Gulf Coast Aquifer1 2 2 2 3 9 No
3 2.5 Gulf Coast Aquifer1 2 2 2 2 8 No
2.5 0a Gulf Coast Aquifer1 2 2 2 3 9 No
0b 16 Gulf Coast Aquifer1 2 2 2 2 8 No
16 20 Gulf Coast Aquifer2 2 1 2 2 7 No
20 21 Gulf Coast Aquifer2 2 1 2 1 6 Yes
21 38 Gulf Coast Aquifer2 2 1 2 2 7 No
38 58 Gulf Coast Aquifer2 2 1 2 3 8 No
58 59.5 Gulf Coast Aquifer2 2 1 2 2 7 No
59.5 66 Brazos River Alluvium 1 1 1 3 6 Yes
66 93 Gulf Coast Aquifer2 2 1 2 3 8 No
93 94 Gulf Coast Aquifer2 2 1 2 2 7 No
94 105 Gulf Coast Aquifer2 2 1 2 3 8 No
105 108 Gulf Coast Aquifer1 2 2 2 3 9 No
108 119 Yegua-Jackson 2 1 1 3 7 No
119 120.5 Colorado River
Alluvium 1 1 1 3 6 Yes
120.5 121 Sparta-Subcrop 2 3 3 3 11 No
121 123 Colorado River
Alluvium 1 1 1 3 6 Yes
123 125.5 Sparta-Subcrop 2 3 3 2 10 No
125.5 126.5 Colorado River
Alluvium 1 1 1 3 6 Yes
126.5 127.5 Sparta-Outcrop 2 1 1 3 7 No
127.5 128.5 Queen City-Subcrop 2 3 3 3 11 No
1 1 1 3 129.5 130.5 Queen City-Subcrop 2 1 3 3 130.5 141.5 128.5 129.5 Colorado River
Alluvium Colorado River
Alluvium 1 3 2 3 6 Yes
9 No
141.5 150.5 1 1 156.5 166.5 Trinity (Hill Country)-
Subcrop Edwards (BFZ)-
Barton Springs -
Subcrop
3 3 6 Yes
Carrizo-Wilcox-
Outcrop 2 1 1 3 7 No
150.5 156.5 No Major/Minor
Aquifer Present 3 3 3 3 12 No
11 No
166.5 170.5
1 3 3 2 9 No
170.5 173.5
Edwards (BFZ)-
Barton Springs -
Outcrop
1 1 1 1 4 Yes
173.5 198.5 Trinity (Hill Country)-
Outcrop 2 1 1 2 6 Yes
198.5 199 Marble Falls 1 1 1 2 5 Yes

<<<PAGE 136>>>

Table 4.2.1-4 Groundwater Resource Area Sensitivity Ranking
(continued)
Starting
MP
Ending
MP Aquifer
TCEQ
Vulnerability
Ranking
Pettyjohn
et al
Ranking
Aquatic
Habitat
Ranking
PWS
Water
Well
Ranking
Sum of
Rankings
Sensitive
Area
199 206 Ellenberger-San
Saba-Outcrop 1 1 1 2 5 Yes
206 207.5 Trinity (Hill Country)-
Outcrop 2 1 1 2 6 Yes
207.5 209 Hickory-Subcrop 2 1 3 3 9 No
209 209.5 Hickory-Outcrop 2 1 1 3 7 No
209.5 210 No Major/Minor
Aquifer Present 3 3 3 3 12 No
210 214.5 Hickory-Outcrop 2 1 1 3 7 No
214.5 216 Hickory-Subcrop 2 1 3 3 9 No
216 220 Trinity (Hill Country)-
Outcrop 2 1 1 2 6 Yes
220 220.5 Hickory-Subcrop 2 1 3 3 9 No
220.5 221 Hickory-Outcrop 2 1 1 3 7 No
221 222 Hickory-Subcrop 2 2 3 3 9 No
222 222.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
222.5 224.5 Trinity (Hill Country)-
Outcrop 2 1 1 2 6 Yes
224.5 226 No Major/Minor
Aquifer Present 3 3 3 3 12 No
226 226.5 Hickory-Outcrop 2 1 1 3 7 No
226.5 227 No Major/Minor
Aquifer Present 3 3 3 3 12 No
227 227.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
227.5 232.5 232.5 233 3 3 237 237.5 Edwards-Trinity
(Plateau)3 1 2 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
233 237 No Major/Minor
Aquifer Present 3 3 3 3 12 No
No Major/Minor
Aquifer Present 3 3 2 1 12 No
6 Yes
237.5 238 No Major/Minor
Aquifer Present 3 3 3 3 12 No
238 238.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
238.5 240 Hickory-Subcrop 2 1 3 3 9 No
240 245 Hickory-Outcrop 2 1 1 3 7 No
245 246 Hickory-Subcrop 2 1 3 3 9 No
246 246.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
245.5 248.5 Hickory-Subcrop 2 1 3 3 9 No
248.5 249.5 Hickory-Outcrop 2 1 1 3 7 No
249.5 254 Ellenberger-San
Saba-Subcrop 1 1 2 2 6 Yes
254 254.5 Ellenberger-San
Saba-Outcrop 1 1 1 2 5 Yes
254.5 257.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes

<<<PAGE 137>>>

Table 4.2.1-4 Groundwater Resource Area Sensitivity Ranking
(continued)
Starting
MP
Ending
MP Aquifer
TCEQ
Vulnerability
Ranking
Pettyjohn
et al
Ranking
Aquatic
Habitat
Ranking
PWS
Water
Well
Ranking
Sum of
Rankings
Sensitive
Area
257.5 261.5 Hickory-Subcrop 2 1 3 3 9 No
261.5 263.5 Ellenberger-San
Saba-Outcrop 1 1 1 2 5 Yes
263.5 264 Hickory-Subcrop 2 1 3 3 9 No
264 270 Ellenberger-San
Saba-Outcrop 1 1 1 2 5 Yes
270 272 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
272 274 Ellenberger-San
Saba-Outcrop 1 1 1 2 5 Yes
274 275.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
275.5 276.5
Ellenberger-San
Saba-Marble Falls-
Outcrops
1 1 1 2 5 Yes
276.5 277.5 Hickory-Subcrop 2 1 3 3 9 No
277.5 294.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
295 329.5 330.5 339.5 2 1 346.0 349.0 Edwards-Trinity
(Plateau)3 1 2 340.5 341.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
Edwards-Trinity
(Plateau)3 1 2 2 1 6 Yes
Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
6 Yes
350 352.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
353 354 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
358 359 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
360 366.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
367.5 368 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
369 369.5 370 372 2 1 376.5 377 Edwards-Trinity
(Plateau)3 1 2 372.5 374 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
Edwards-Trinity
(Plateau)3 1 2 2 1 6 Yes
Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
6 Yes
386 388 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
390 392.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
393.5 394 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
395.5 405 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
406 407 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes

<<<PAGE 138>>>

Table 4.2.1-4 Groundwater Resource Area Sensitivity Ranking
(continued)
Starting
MP
Ending
MP Aquifer
TCEQ
Vulnerability
Ranking
Pettyjohn
et al
Ranking
Aquatic
Habitat
Ranking
PWS
Water
Well
Ranking
Sum of
Rankings
Sensitive
Area
431 434 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
14.5 16.5 Edwards-Trinity
(Plateau)3 2 1 1 2 6 Yes
24.5 29 Southern Ogallala 2 1 1 3 7 No
a-East Houston to 9th Street Junction
b-East Houston to Crane
1-Beaumont or Catahula Outcrop (Clay Dominant)
2-Lissie or Oakville Outcrop (Sand Dominant)
3-Edwards Group Outcrop, Includes Hensell Sand Formation

<<<PAGE 139>>>

Table 4.2.1-5 Public Water Supply Wells Within the Zone of
Potential Impact
PWS ID
Number
Figure 4.2.1-3
PWS Well ID
Number
PWS Name Aquifer Used
Number
of Water
Wells
1013224 1 Galena Park ISD
Gulf Coast
Aquifer System 1
1011057 2 and 3 Greens Bayou Electric
Generating S
Gulf Coast
Aquifer System 2
1013100 4 Garlock Metallic Gaskets
Gulf Coast
Aquifer System 1
1010196 5 and 6 Ralston Acres Water Supply Corp
Gulf Coast
Aquifer System 2
1013171 7 Texas Steel Conversion
Gulf Coast
Aquifer System 1
1012135 8 Parkway Grocery & Hardware
Center
Gulf Coast
Aquifer System 1
1013001 9 The Rhodes School
Gulf Coast
Aquifer System 1
1010307 10 Redwood Estates Mobile Home
Park
Gulf Coast
Aquifer System 1
1010013
11,12, 13, 14, 15,
16, 17, 22, 23,
44, 45, 81, 82,
83, 89 and 95
City of Houston Gulf Coast
Aquifer System 16
1013455 18 Sigma Askins Houston Facility
Gulf Coast
Aquifer System 1
1013386 19 La Sultana Refresqueria
Gulf Coast
Aquifer System 1
1012940 20 Winners Corner 2
Gulf Coast
Aquifer System 1
1013232 21 Dagoberto Silva Well
Gulf Coast
Aquifer System 1
1010011
24, 25, 26, 27
and 28 Greenwood Village
Gulf Coast
Aquifer System 5
1010022 29, 30, 31 and 32 Sunbelt FWSD Oakwilde
Subdivision
Gulf Coast
Aquifer System 4
1010100 33, 37 and 38 Mary Francis Subdivision
Gulf Coast
Aquifer System 3
1010533 34 and 35 Sundown Mobile Home Park
Gulf Coast
Aquifer System 2
1012885 36 Houston Well Screen Company
Gulf Coast
Aquifer System 1
1011713 39 and 40 Hooks Mobile Home Park LTD
Gulf Coast
Aquifer System 2
1013245 41 and 42 Mesquite Mobile Home Park
Gulf Coast
Aquifer System 2
1011609 43 Ashbrook Corp
Gulf Coast
Aquifer System 1
1010746 46 and 47 Fatima Family Village MHP
Gulf Coast
Aquifer System 2
1010664 48 and 49 Lone Willow Mobile Home Park
Gulf Coast
Aquifer System 2

<<<PAGE 140>>>

Table 4.2.1-5 Public Water Supply Wells Within the Zone of Potential Impact
(continued)
PWS ID
Number
Figure 4.2.1-3
PWS Well ID
Number
PWS Name Aquifer Used
Number
of Water
Wells
1011971 50 and 51 Rosewood Mobile Home Park
Gulf Coast
Aquifer System 2
1010658 52 and 53 Aldine Oaks MHP
Gulf Coast
Aquifer System 2
1011947 54 and 55 Westfield Garden Mobile Home
Park
Gulf Coast
Aquifer System 2
1010663 56 Lone Willow West Mobile Home
Park
Gulf Coast
Aquifer System 1
1011618 57 Hungry Farmer BBQ & Catering
Gulf Coast
Aquifer System 1
1010452 58 and 59 Mercado-Sabadomingo
Gulf Coast
Aquifer System 2
1013010 60 Taqueria Buey de Y Vaca
Gulf Coast
Aquifer System 1
1012700 61 and 65 Sunny Flea Market
Gulf Coast
Aquifer System 2
1012625 62 and 63 Sinta Flea Market
Gulf Coast
Aquifer System 2
1012666 64 Airline Square
Gulf Coast
Aquifer System 1
1010689 66 Balaban Apartments 1
Gulf Coast
Aquifer System 1
1011028 67 Balaban Apartments 2
Gulf Coast
Aquifer System 1
1010826 68, 69 and 70 Pin Oak Mobile Home Park
Gulf Coast
Aquifer System 3
1010744 71 Meadowview MHP
Gulf Coast
Aquifer System 1
1010832 72 North Point Villa
Gulf Coast
Aquifer System 1
1011118 73 and 75 New Oasis of Faith Cathedral
Gulf Coast
Aquifer System 2
1012157 74 Sweetwater Business Park
Gulf Coast
Aquifer System 1
1010117 76 and 77 Northline Terrace Subdivision
Gulf Coast
Aquifer System 2
1010012 78 and 79 Hidden Valley Subdivision
Gulf Coast
Aquifer System 2
1012952 80 Raceway 6772
Gulf Coast
Aquifer System 1
1012890 84 and 85 Chevron 249
Gulf Coast
Aquifer System 2
1010419 86 and 87 Heather Glen Subdivision
Gulf Coast
Aquifer System 2
1012892 88 Kingmont Mobile Home Park
Gulf Coast
Aquifer System 1
1010670 90 West Montgomery Utility
Gulf Coast
Aquifer System 1
1010897 91 and 92 Harris County MUD 118
Gulf Coast
Aquifer System 2

<<<PAGE 141>>>

Table 4.2.1-5 Public Water Supply Wells Within the Zone of Potential Impact
(continued)
PWS ID
Number
Figure 4.2.1-3
PWS Well ID
Number
PWS Name Aquifer Used
Number
of Water
Wells
1010626 93 and 94 Harris County MUD 119
Gulf Coast
Aquifer System 2
1010357 96 Rolling Fork PUD
Gulf Coast
Aquifer System 1
1011647 97 Creekside Estates South
Gulf Coast
Aquifer System 1
1010322 98 White Oak Manor Mobile Home
Park
Gulf Coast
Aquifer System 1
1010924 99 Windfern Forest Utility District
Gulf Coast
Aquifer System 1
1012858 100 West Harris County MUD 11
Gulf Coast
Aquifer System 1
1012058 101 West Harris County MUD 10
Gulf Coast
Aquifer System 1
1011798 102 West Harris County MUD 9
Gulf Coast
Aquifer System 1
1011783 103 Harris County MUD 168
Gulf Coast
Aquifer System 1
1010016 104 City of Jersey Village
Gulf Coast
Aquifer System 1
1012293 105 Northwest Harris County MUD 29
Gulf Coast
Aquifer System 1
1011412 106, 107 and 108 SPX Process Equipment Houston
Gulf Coast
Aquifer System 3
1012097 109 and 110 Harris County MUD 130
Gulf Coast
Aquifer System 2
1010583 111, 112 and 113 West Houston Mobile Home
Community
Gulf Coast
Aquifer System 3
1010237 114 Harris County FWSD 61
Gulf Coast
Aquifer System 1
1011848 115 Harris County MUD 179
Gulf Coast
Aquifer System 1
1011982 116 Harris County MUD 188
Gulf Coast
Aquifer System 1
1012214 117 Harris County MUD 186
Gulf Coast
Aquifer System 1
1011612 118 Harris County MUD 162
Gulf Coast
Aquifer System 1
1012213 119 Harris County MUD 163
Gulf Coast
Aquifer System 1
1012001 120 W. Harris County MUD 15
Gulf Coast
Aquifer System 1
1012970 121 Harris County MUD 172 Gulf Coast
Aquifer System 1
1013074 122 and 123 Remington MUD 1
Gulf Coast
Aquifer System 2
1011690 124 and 125 Harris County MUD 70
Gulf Coast
Aquifer System 2
0080005 126 West End WSC
Gulf Coast
Aquifer System 1

<<<PAGE 142>>>

Table 4.2.1-5 Public Water Supply Wells Within the Zone of Potential Impact
(continued)
PWS ID
Number
Figure 4.2.1-3
PWS Well ID
Number
PWS Name Aquifer Used
Number
of Water
Wells
0110013 127, 128 and 129 Aqua WSC
Carrizo-Wilcox
Aquifer 3
130
2270004
City of Sunset Valley
Edwards (BFZ)-
Barton Springs
Segment 1
131 and 132
2270212
Shady Hollow Estates WSC
Edwards (BFZ)-
Barton Springs
Segment 2
133 and 134
0160015
Flat Creek Crossing Ranch
Trinity Aquifer
System-Hill
Country 2

<<<PAGE 143>>>

Table 4.2.2-1 Summary of Chemical Analyses on Surface Water Samples from STORET
Stations Within the Zone of Potential Impact of the Proposed Project
Mean Analytical Results / # of Samples Analyzed
Arsenic
(µg/L)
Chloride,
Total in
Water
(mg/L)
Fluoride,
(mg/L) Iron (µg/L)
Nitrite Plus
Nitrate
(mg/L, as
N)
Oxygen
(mg/L)
Phos-
Phorus,
Total
(mg/L as P)
Sulfate,
Total
(Mg/L)
Standard
50 250 4.0 300 100
5 or 6
exceptional 0.01 to 0.3 250 Type of Standard
Map
ID
STORET
Station Year Station Name
Primary Secondary Primary Secondary Primary Aquatic Secondary 4 8075770 2006 Hunting Bayou at I-
610, Houston, Texas 6.0/ 26 52.7/ 30 0.59/ 30 27.6/ 25 3.9/ 13 6.8/ 33 1.12/ 26 49.9/ 29 5 8076000 Greens Bayou near
Houston, Texas 6.2/ 30 72.1/ 29 0.30/ 29 26.7/ 29 3.7/ 13 6.9/ 36 2.28/ 25 32.6/ 27 7 11332
Cypress Creek at
Grant Rd Near
Cypress
32.7/ 51 7.2/ 49 1.24/ 51 13.0/ 53
9 11848 Brazos River at FM
1093 118.0/ 13 9.0/ 15 0.00/ 14 90.0/ 11
10 11578
Clear Creek at FM
1887 Northwest of
Monaville
48.8/ 6 7.5/ 5 0.00/ 6 15.0/ 4
2006 Mill Creek at Hwy 36 5.0/ 4 44.8/ 13 0.00/ 5 53.8/ 4 8.1/ 9 0.00/ 8 15.3/ 12
12 11576
2010 39.9/ 17 0.28/ 1 7.8/ 13 12/ 16
13 11574
Mill Creek at County
Road 2.8 Miles
Southwest of Bellville
48.7/ 6 7.1/ 26 0.00/ 6 13.5/ 6
15 12290 Colorado River at Old
Hwy 71 1.8/ 5 50.5/ 87 0.33/ 53 12.6/ 5 0.9/ 5 8.0/ 109 0.37/ 92 46.0/ 84 16 12249 Cummins Creek at FM
109 north of Columbus 3.5/ 13 66.3/ 46 80.3/ 4 7.8/ 67 0.00/ 47 11.4/ 44
Fecal
Coliform,
MF,M-FC,
0.7 µm (cols/
100 mL)
400
Recreation
2,611/ 33
2,336/ 37
2,430/ 6

<<<PAGE 144>>>

Map
ID
17 18 20 21 22 23 25 26 27 29 30 31 Table 4.2.2-1 Summary of Chemical Analyses on Surface Water Samples from Study Area Streams (per STORET)
(continued)
Mean Analytical Results / # of Samples Analyzed
Arsenic
(µg/L)
Chloride,
Total in
Water
(mg/L)
Fluoride,
(mg/L) Iron (µg/L)
Nitrite Plus
Nitrate
(mg/L, as
N)
Oxygen
(mg/L)
Phos-
Phorus,
Total
(mg/L as P)
Sulfate,
Total
(Mg/L)
Standard
50 250 4.0 300 100
5 or 6
exceptional 0.01 to 0.3 250 Type of Standard
STORET
Station Year Station Name
Primary Secondary Primary Secondary Primary Aquatic Secondary 12292 Colorado River at Hwy
71 at La Grange 51.6/ 16 7.8/ 29 0.00/ 14 40.1/ 16
12457
Colorado River at Hwy
95/Hwy Loop 230 at
Smithville
58.0/ 29 8.4/ 30 0.31/ 29 51.6/ 29
8159200 Colorado River at
Bastrop, Texas 63.0/ 52 0.35/ 54 2.1/ 10 8.2/ 54 0.45/ 44 53.7/ 53
12466 Colorado River at
County Park 64.2/ 53 8.7/ 54 0.53/ 55 56.5/ 55
8158650 Colorado River below
Austin, Texas 1.0/ 32 60.9/ 55 0.34/ 57 6.3/ 34 2.2/ 16 9.1/ 56 0.38/ 41 48.5/ 55 12435 Onion Creek upstream
from FM 973 29.7/ 37 7.8/ 51 0.14/ 35 48.6/ 38
8158000 Colorado River at
Austin, Texas 1.0/ 25 60.6/ 36 0.23/ 37 6.2/ 31 0.3/ 34 9.0/ 33 0.02/ 34 45.8/ 34 8155505
Barton Creek below
Barton Springs, Austin,
Texas
1.0/ 1 13.0/ 1 0.10/ 1 16.0/ 1 0.6/ 11 8.5/ 1 0.15/ 11 25.0/ 1 8155500 Barton Springs at
Austin, Texas 1.0/ 43 26.9/ 46 0.22/ 45 4.1/ 41 1.3/ 32 6.5/ 55 0.02/ 59 29.8/ 46 8155300 Barton Creek at Loop
360, Austin, Texas 1.0/ 27 13.5/ 31 0.16/ 32 10.2/ 27 0.2/ 66 8.9/ 25 0.10/ 112 22.8/ 30 12448
Onion Creek 0.7 mile
north of Buda next to
Mopac
22.3/ 62 9.3/ 60 0.00/ 62 30.8/ 57
8155240
Barton Creek at Lost
Creek Blvd. near
Austin, Texas
1.0/ 23 28.6/ 25 0.19/ 24 5.9/ 22 0.2/ 94 8.1/ 34 0.08/ 110 52.3/ 24 Fecal
Coliform,
MF,M-FC,
0.7 µm (cols/
100 mL)
400
Recreation
252/ 54
166/ 34
11,758/ 10
184/ 56
12,268/ 99
5,236/ 102

<<<PAGE 145>>>

Map
ID
32 34 35 36 36 37 38 39 46 47 Table 4.2.2-1 Summary of Chemical Analyses on Surface Water Samples from Study Area Streams (per STORET)
(continued)
Mean Analytical Results / # of Samples Analyzed
Arsenic
(µg/L)
Chloride,
Total in
Water
(mg/L)
Fluoride,
(mg/L) Iron (µg/L)
Nitrite Plus
Nitrate
(mg/L, as
N)
Oxygen
(mg/L)
Phos-
Phorus,
Total
(mg/L as P)
Sulfate,
Total
(Mg/L)
Standard
50 250 4.0 300 100
5 or 6
exceptional 0.01 to 0.3 250 Type of Standard
STORET
Station Year Station Name
Primary Secondary Primary Secondary Primary Aquatic Secondary 8155220
Barton Creek at Barton
Creek Blvd., Austin,
Texas
1.0/ 5 35.8/ 5 0.30/ 5 7.4/ 5 0.1/ 8 7.5/ 9 0.01/ 9 44.2/ 5 8154510
Colorado River below
Mansfield Dam, Austin,
Texas
80.3/ 39 0.23/ 37 6.4/ 40 0.00/ 40 59.2/ 39
8155200
Barton Creek at Hwy
71 near Oak Hill,
Texas
1.0/ 26 17.1/ 27 0.20/ 22 4.2/ 23 0.1/ 124 8.1/ 42 0.05/ 124 26.4/ 25 8158700 Onion Creek near
Driftwood, Texas 1.0/ 36 14.2/ 38 0.19/ 40 5.1/ 34 0.2/ 24 8.6/ 47 0.02/ 51 31.8/ 38 8158700 Onion Creek near
Driftwood, Texas 1.0/ 36 14.2/ 38 0.19/ 40 5.1/ 34 0.2/ 24 8.6/ 47 0.02/ 51 31.8/ 38 2007 Onion Creek at FM
150 1.0/ 29 13.9/ 34 0.19/ 33 5.1/ 28 0.1/ 6 8.6/ 87 0.02/ 41 30.8/ 33 12451
2011 19.2/ 13 9.2/ 6 60.8/ 13
12369
Pedernales River at Cr
962 at Hammett's
Crossing
40.5/ 11 8.0/ 32 0.00/ 11 24.9/ 10
12260 Flat Creek at Blanco
Cr 201 11.5/ 2 7.0/ 8 0.00/ 2 31.0/ 2
12383
Llano River County
Road 6.5 Miles
upstream from Lake
LBJ
20.7/ 30 9.2/ 48 0.00/ 31 16.3/ 30
12265 North Grape Creek at
FM 1320 44.0/ 2 7.8/ 8 0.00/ 2 20.5/ 2
Fecal
Coliform,
MF,M-FC,
0.7 µm (cols/
100 mL)
400
Recreation
25/ 8
5,898/ 114
1,171/ 60
1,171/ 60
589/ 45

<<<PAGE 146>>>

Map
ID
48 49 50 51 53 54 55 56 Table 4.2.2-1 Summary of Chemical Analyses on Surface Water Samples from Study Area Streams (per STORET)
(continued)
Mean Analytical Results / # of Samples Analyzed
Arsenic
(µg/L)
Chloride,
Total in
Water
(mg/L)
Fluoride,
(mg/L) Iron (µg/L)
Nitrite Plus
Nitrate
(mg/L, as
N)
Oxygen
(mg/L)
Phos-
Phorus,
Total
(mg/L as P)
Sulfate,
Total
(Mg/L)
Standard
50 250 4.0 300 100
5 or 6
exceptional 0.01 to 0.3 250 Type of Standard
STORET
Station Year Station Name
Primary Secondary Primary Secondary Primary Aquatic Secondary 12386
Llano River 0.4 mile
downstream from
bridge on State Hwy
16.
2.2/ 6 20.1/ 9 0.26/ 7 6.5/ 6 0.1/ 6 8.9/ 8 0.01/ 9 15.7/ 9 8151500 Llano River at Llano,
Texas 2.2/ 6 21.3/ 7 0.26/ 7 6.5/ 6 0.1/ 6 8.9/ 7 0.02/ 7 15.4/ 7 2006 Pedernales River
Goehman Lane 66.8/ 12 8.7/ 20 0.00/ 12 29.5/ 10
12377
2010 60.3/ 16 0.375. 4 9.2/ 6 9.3/ 23
12380
Pedernales River US
290 SE of
Fredericksburg
59.8/ 26 0.00/ 14 8.6/ 8 0.00/ 26 33.8/ 16
12208
James River on private
Ranch Road 1.2 miles
upstream
30.0/ 1 7.9/ 28 0.00/ 1 20.0/ 1
12210
James River at upper
Mason County Road
Crossing
28.0/ 1 8.8/ 4 0.00/ 1 20.0/ 1
Llano River at Yates
Crossing 14.0/ 8 8.0/ 7 0.00/ 8 7.4/ 8
14231
14.5/ 23 1.2/ 6 9.3/ 23
12389
Llano River at County
Road 9.5 mi. northeast
of Junction
14.4/ 30 8.4/ 28 0.00/ 30 12.0/ 28
Fecal
Coliform,
MF,M-FC,
0.7 µm (cols/
100 mL)
400
Recreation
63/ 6
63/ 6

<<<PAGE 147>>>

Table 4.2.2-2 Summary of 2008 Texas 303(d) Stream Segments Within the Zone of Potential
Impact of the Proposed Project
MP Segment
No. Segment Name Yr First
Listed
Impairment
Category* Type Impairment(s)
2002 5a Bacteria
2.31 - 5 1007R Hunting Bayou Above Tidal
2002 5c Depressed dissolved
oxygen
7 1006_03 Houston Ship channel
Tidal/Greens Bayou Tidal
1996 5a Dioxin in edible tissue
2002 5a PCBs in edible tissue
7 – 8 1006H Spring Gully Above Tidal 2002 5a Bacteria
10 - 16 1006D Halls Bayou 2002 5a Bacteria
10 1016 Greens Bayou Above Tidal 1996 5a Bacteria
16 1006J Unnamed Tributary of Halls
Bayou 2002 5a Bacteria
34 1017 Whiteoak Bayou Above Tidal 1996 5a Bacteria
47 1009 Cypress Creek 1996 5a Bacteria
172 - 178 1427A Slaughter Creek 2002 5b Impaired macrobenthic
community
152 - 164 1428 Colorado River Below Town
Lake 2006 5c Bacteria
Category 5a - A TMDL us underway, scheduled, or will be scheduled
Category 5b - A review of the water quality standards of this water body will be conducted before a TMDL is scheduled.
Category 5c - Additional data and information will be collected before a TMDL is scheduled.

<<<PAGE 148>>>

Table 4.2.2-3 Distances from Stream Crossings to Downstream Water Rights Within the Zone
of Potential Impact of the Proposed Project
Municipal Irrigation Industrial Mining Distance to
Rights (ac-ft/no. of rights)
Within:
Rights (ac-ft/no. of rights)
Rights (ac-ft/no. of rights)
Rights (ac-ft/no. of rights)
Within:
Within:
Within:
Crossing
No.
5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi
Downstrea
m Lake
Mainstream
(mi)
Lake
Name
Cypress Creek 34 3,041/ 2 3,041/ 2 3,041/ 2
Mound Creek 37 Live Oak 38 75,000/ 1
Clear Creek 44 48 75,000/ 1 Unnamed Trib.
to Cypress
Creek 36 Harris Creek
Harris Creek
Trib. Trib. 41 75,000/ 1
42 Brazos River 45 Muddy Branch East Fork Mill
Creek 57 Dogwood
Creek 60 West Fork Mill
Creek 61 Cummins
Creek Rabbs Creek 78 JD Creek 82 Alum Creek 3,041/ 2 3,041/ 2 3,041/ 2
3,041/ 2 3,041/ 2 3,041/ 2
3,041/ 2 3,041/ 2 3,041/ 2
136/ 1 136/ 1 136/ 1 136/ 1 10/ 1 10/ 1
136/ 1 136/ 1 136/ 1 136/ 1 10/ 1 10/ 1
10/ 1 10/ 1 10/ 1
10/ 1 10/ 1
10/ 1 10/ 1
10/ 1 10/ 1
Jacks Creek 67 73/ 1 73/ 1
68 73/ 1 73/ 1
74 33/ 2 33/ 2 148/ 6 148/ 6
Knobbs Creek 77 35/ 1 150/ 5 150/ 5
Dreissner
Branch 35/ 1 150/ 5 150/ 5
Pin Oak Creek 80 35/ 1 150/ 5 150/ 5
Gravelly Creek 81 35/ 1 150/ 5 150/ 5
35/ 1 35/ 1 150/ 5
86 35/ 1 150/ 5
Little Alum
Creek 87 89 35/ 1 150/ 5
Colorado River 35/ 1 35/ 1

<<<PAGE 149>>>

Table 4.2.2-3 Distances from Stream Crossings to Downstream Water Rights
(continued)
Municipal Rights (ac-ft/no. of rights)
Within:
Irrigation Rights (ac-ft/no. of rights)
Within:
Industrial Rights (ac-ft/no. of rights)
Within:
Mining Rights (ac-ft/no. of rights)
Within:
Crossing
No.
5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi
Distance to
Downstrea
m Lake
Mainstream
(mi)
Lake
Name
Unnamed 92 35/ 1 35/ 1
Cedar Creek 93 35/ 1 35/ 1
35/ 1
67/ 1 67/ 1 67/ 1
Marble Creek 101 67/ 1 67/ 1 67/ 1
67/ 1 67/ 1 67/ 1
40/ 1 40/ 1 Flat Creek 112 34/ 1 34/ 1 34/ 1 Maha Creek 97 Dry Creek Cottonmouth
Creek 99
100 Onion Creek 103 Barton Creek 109 Pedernales
Cottonwood
Creek River 115 30/ 1 30/ 1 30/ 1 30/ 1 34/ 1 34/ 1 34/ 1 119 Hickory Creek White Oak
Creek 125 127 Cherry Spring
Creek 142 1,200/ 1 1,200/ 1 46/ 1 46/ 1 187/ 5 247/ 6 Marshall Creek Squaw Creek 32.9
Town
Lake
26.8
Lake
Travis
33.2
Lake
Travis
30/ 1 30/ 1 30/ 1 34/ 1 34/ 1 34/ 1 41.1
Lake
Travis
30/ 1 30/ 1 34/ 1 34/ 1 53.7
Lake
Travis
30/ 1 Lake
Travis
Crabapple
Creek 135 1/ 1 1/ 1 1/ 1 4/ 1 4/ 1 4/ 1 33.3
Bernst Creek 140 1,200/ 1 1,200/ 1 46/ 1 46/ 1 187/ 5 247/ 6 143 30/ 1 1,200/ 1 34/ 1 34/ 1 59.9
Lake
LBJ
51.3
Lake
LBJ
50.2
Lake
LBJ
1,200/ 1 46/ 1 46/ 1 187/ 5 247/ 6 50.7
Lake
LBJ
150 1,200/ 1 49/ 2 139/ 4 163/ 6 304/ 10 31/ 2 31/ 2 63.2
Lake
LBJ
Threadgill
Creek 151 1,200/ 1 49/ 2 139/ 4 163/ 6 304/ 10 31/ 2 31/ 2 63.5
Lake
LBJ
161 Lake
LBJ
Mill Creek 164 James River 166 168 173 1,200/ 1 1,200/ 1 46/ 1 222/ 5 351/ 10 492/ 14 31/ 2 31/ 2 Rocky Creek Llano River 237/ 6 53/ 1 Unnamed 46/ 1 84/ 3 351/ 10 492/ 14 31/ 2 31/ 2 69.5
71
Lake
LBJ
46/ 1 46/ 1 351/ 9 492/ 14 31/ 2 95.1
Lake
LBJ
53/ 1 358/ 9 358/ 10 31/ 2 79.7
Lake
LBJ
2,651/18 2,704/19 116.3 Lake

<<<PAGE 150>>>

Table 4.2.2-3 Distances from Stream Crossings to Downstream Water Rights
(continued)
Crossing
No.
5 mi Municipal Rights (ac-ft/no. of rights)
Within:
60 mi Irrigation Rights (ac-ft/no. of rights)
Within:
Industrial Rights (ac-ft/no. of rights)
Within:
Mining Rights (ac-ft/no. of rights)
Within:
20 mi 40 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi 5 mi 20 mi 40 mi 60 mi
Distance to
Downstrea
m Lake
Mainstream
(mi)
Tributary (first-
order)
Unnamed
Tributary (first-
order) 174 192/ 4 1,338/30 3,664/41 60/ 1 60/ 1 128
Unnamed
Tributary (first-
order) 175 76/ 5 1,227/31 3,513/40 60/ 1 60/ 1 129.8
Terret Draw 185 1,016/ 1 1,016/ 1 531/ 6 6,068/37 7,997/62 3/ 1 6/ 2 6/ 2
Middle Valley 192 1,016/ 1 1,016/ 1 285/ 3 5,302/28 7,997/62 3/ 1 6/ 2 6/ 2
Antelope Draw 197 1016/ 1 110/ 1 559/ 9 7,178/44 3/ 1 3/ 1 6/ 2
Lake
Name
LBJ
Lake
LBJ
Lake
LBJ

<<<PAGE 151>>>

Table 4.2.2-4 Ranking of Stream Crossings in Terms of Spill Transport Potential
Stream at Crossing Map ID
Pipeline
Crossing
(MP)
Slope of
Channel
at
Crossing
Basin
Area
(sq mi)
Stream
Order
2-Year
Flood
(cfd)
Rank in
Potential to
Transports
Spill (1-
highest) Basis for Rank
Hunting Bayou 1 0.1 0.0006 14.4 Urban Urban 4 Basin size
Greens Bayou 3 3.2,6.0 0.0000 182 Urban Urban 2 High Stream Order
Halls Bayou 8 13.2 0.0009 24.7 Urban Urban 4 Basin size
Cypress Creek 34 47.1 0.0009 89.9 3 2701 2 High Stream Order
Unnamed Tributary to
Cypress Creek 36 48.7 0.0010 3.9 2 311 5 Med-Iow 2-year
flood
Mound Creek 37 50.4 0.0013 43.0 2 1,211 4 Med 2-year flood
Live Oak 38 53.9 0.0017 10.1 2 782 4 Med 2-year flood
Harris Creek Tributary 41 58.7 0.0033 7.5 2 576 5 Med-Iow 2-year
flood
Harris Creek Tributary 42 59.7 0.0020 8.0 2 596 5 Med-Iow 2-year
flood
Clear Creek 1 44 62.6 0.0010 74.3 3 2,245 2 High Stream Order
Brazos River 45 64.0 0.00013 44,000 Major 57,800 1 Major Crossing
Muddy Branch 48 69.2 0.0022 9.2 2 1,172 4 Med 2-year flood
East Fork Mill Creek 57 81.2 0.0007 126.0 3 3,539 2 High Stream Order
Dogwood Creek 60 89.2 0.0025 11.1 2 988 4 Med 2-year flood
West Fork Mill Creek 61 90.8 0.0013 44.0 3 2,034 2 High Stream Order
Jacks Creek 67 98.3 0.0030 11.8 2 1,019 4 Med 2-year flood
Cummins Creek 68 99.2 0.0018 94.3 3 4,155 2 High Stream Order
Rabbs Creek 74 112.3 0.0013 81.3 3 4,366 2 High Stream Order
Knobbs Creek 77 118.8 0.0033 23.2 2 1,453 4 Med 2-year flood
Dreissner Branch 78 119.9 0.0033 6.8 2 761 5 Med-Iow 2-year
flood
Pin Oak Creek 80 122.5 0.0014 50.1 3 3,668 2 High Stream Order
Gravelly Creek 81 123.0 0.0025 18.7 2 1,297 4 Med 2-year flood
JD Creek 82 126.7 0.0050 6.7 2 755 5 Med-Iow 2-year
flood
Alum Creek 86 131.5 0.0028 46.1 3 3,884 2 High Stream Order
Little Alum Creek 87 132.3 0.0056 4.6 2 622 5 Med-low 2-year flood
Colorado River 89 134.5 0.00033 39.8 Major 48,300 1 Major Crossing
Unnamed 92 142.9 0.0048 7.3 2 691 5 Med-Iow 2-year
flood
Cedar Creek 2 93 142.8 0.0014 90 3 4,079 2 High Stream Order
Maha Creek 3 97 151.7 0.0029 32.7 2 2,677 3 High 2-year flood
Dry Creek 99 157.4 0.0029 22.2 2 1,312 4 Med 2-year flood
Cottonmouth Creek 100 162.3 0.0040 2.2 1 324 5 Med-Iow 2-year
flood
Marble Creek 101 163.5 0.0143 3.8 1 449 5 Med-Iow 2-year
flood
Onion Creek 103 164.0 0.0014 284.4 Large 6,983 1 Major Crossing
Barton Creek 109 180.9 0.0050 40.9 2 2,392 3 High 2-year flood
Flat Creek 112 193.2 0.0091 31.0 3 1,919 2 High Stream Order

<<<PAGE 152>>>

Table 4.2.2-4 Ranking of Stream Crossings in Terms of Spill Transport Potential
(continued)
Stream at Crossing Map ID
Pipeline
Crossing
(MP)
Slope of
Channel
at
Crossing
Basin
Area
(sq mi)
Stream
Order
2-Year
Flood
(cfd)
Rank in
Potential to
Transports
Spill (1-
highest) Basis for Rank
Pedernales River 115 198.8 0.0026 1,000.0 Large 15,488 1 Major Crossing
Cottonwood Creek 119 203.2 0.0111 10.3 2 901 4 Med 2-year flood
Hickory Creek 125 209.9 0.0063 12.2 2 1,024 4 Med 2-year flood
White Oak Creek 127 213.3 0.0100 7.5 2 829 4 Med 2-year flood
Crabapple Creek 135 229.3 0.0100 63.4 3 2,876 2 High Stream Order
Bernst Creek 140 237.8 0.0100 3.8 2 543 5 Med-Iow 2-year
flood
Cherry Spring Creek 142 241.7 0.0040 11.0 2 1,011 4 Med 2-year flood
Marshall Creek 143 242.7 0.0059 10.9 2 947 4 Med 2-year flood
Squaw Creek 150 24S.5 0.0063 39.6 2 2,231 3 High 2-year flood
Threadgill Creek 151 250.0 0.0042 1,17.3 4 4,363 2 High Stream Order
James River 161 263.9 0.0029 322.1 Large 8,030 1 Major Crossing
Mill Creek 164 267.9 0.0067 7.3 2 786 4 Med 2-year flood
Rocky Creek 166 273.7 0.0100 10.5 2 993 4 Med 2-year flood
Llano River 168 276.5 Major 1 Major Crossing
Terret Draw 185 315.9 0.0028 34.6 3 1,711 3 High 2-year flood
Middle Valley 192 324.2 0.001 I 137.2 3 3,545 3 High 2-year flood
Antelope Draw 197 334.3 0.0018 62.0 3 2,273 3 High 2-year flood
Big Lake Draw 211 402.6 0.0030 46.0 2 627 5 Med-low 2-year
flood
Garrison 216 415.8 0.0022 24.5 2 499 5 Med-Iow 2-year
flood
China Draw 224 433.1 0.0026 17. 1 2 374 5 Med-Iow 2-year
flood
Mayfield Draw 234 450.2 0.0025 76.3 3 508 5 Med-Iow 2-year
flood
1 Clear Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 85 meters.
2 Cedar Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 320 meters.
3 Maha Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 180 meters.

<<<PAGE 153>>>

Table 4.2.2-5 Ranking of Stream Crossings in Terms of Spill Control Potential
Stream at Crossing
Map
ID
Pipeline
Crossing
(MP)
Distance to
Main Stem of
River
Downstream
(mi)
Rank in Potential
to Control a Spill
(1 = most difficult
to control) Basis for Rank
Hunting Bayou 1 0.1 N/A 6 In urban setting, within levees
Greens Bayou 3 3.2,6 N/A 6 In urban setting, within levees
Halls Bayou 8 13.2 N/A 6 In urban setting, within levees
Cypress Creek 34 47.1 0.0 1 Main stem
Unnamed Tributary to
Cypress Creek 36 48.7 1.9 2 Within 2 miles of main stem
Mound Creek 37 50.4 7.5 3 3 to 10 miles from main stem
Live Oak 38 53.9 9.9 3 3 to 10 miles from main stem
Harris Creek Tributary 41 58.7 20.9 5 20-30 miles from main stem
Harris Creek Tributary 42 59.7 20.6 5 20-30 miles from main stem
Clear Creek 1 44 62.6 1.2 2 Within 2 miles of main stem
Brazos River 45 64.0 0.0 1 Main stem
Muddy Branch 48 69.2 7.0 3 3 to 10 miles from main stem
East Fork Mill Creek 57 81.2 26.5 5 20-30 miles from main stem
Dogwood Creek 60 89.2 38.1 6 Over 35 miles from main stem
West Fork Mill Creek 61 90.8 38.7 6 Over 35 miles from main stem
Jacks Creek 67 98.3 37.0 6 Over 35 miles from main stem
Cummins Creek 68 99.2 36.9 6 Over 35 miles from main stem
Rabbs Creek 74 112.3 6.9 3 3 to 10 miles from main stem
Knobbs Creek 77 118.8 9.6 3 3 to 10 miles from main stem
Dreissner Branch 78 119.9 9.0 3 3 to 10 miles from main stem
Pin Oak Creek 80 122.5 9.6 3 3 to 10 miles from main stem
Gravelly Creek 81 123.0 9.8 3 3 to 10 miles from main stem
JD Creek 82 126.7 2.2 2 Near main stem
Alum Creek 86 131.5 3.3 2 On Colorado River Alluvium
Little Alum Creek 87 132.3 3.3 2 On Colorado River Alluvium
Colorado River 89 134.5 0.0 1 Main stem
Unnamed 92 142.9 13.2 2 On Colorado River Alluvium
Cedar Creek 2 93 142.8 13.0 2 On Colorado River Alluvium
Maha Creek 3 97 151.7 26.5 2 On Colorado River Alluvium
Dry Creek 99 157.4 14.9 4 10-20 miles from main stem
Cottonmouth Creek 100 162.3 4.0 3 3 to 10 miles from main stem
Marble Creek 101 163.5 0.2 1 Essentially at main stem
Onion Creek 103 164.0 15.3 1 Major tributary
Barton Creek 109 180.9 26.3 1 On Edwards/Balcones Contributing
Zone
Flat Creek 112 193.2 3.8 3 3 to 10 miles from main stem
Pedernales River 115 198.8 33.2 1 Main stem, major tributary
Cottonwood Creek 119 203.2 1.2 2 Within 2 miles of main stem
Hickory Creek 125 209.9 2.6 2 Very near main stem

<<<PAGE 154>>>

Table 4.2.2-5 Ranking of Stream Crossings in Terms of Spill Control Potential
(continued)
Stream at Crossing
Map
ID
Pipeline
Crossing
(MP)
Distance to
Main Stem of
River
Downstream
(mi)
Rank in Potential
to Control a Spill
(1 = most difficult
to control) Basis for Rank
White Oak Creek 127 213.3 6.0 2 Near Ellenburger-San Saba
Aquifer (karst)
Crabapple Creek 135 229.3 33.3 2 Near Ellenburger~SanSaba
Aquifer (karst)
Bernst Creek 140 237.8 22.7 5 20-30 miles from main stem
Cherry Spring Creek 142 241.7 21.6 5 20-30 miles from main stem
Marshall Creek 143 242.7 22.1 5 20~30 miles from main stem
Squaw Creek 150 248.5 14.2 1 On Ellenburger·San Saba Aquifer
(karst)
Threadgill Creek 151 250.0 14.5 2 On Ellenburger·San Saba Aquifer
(karst)
James River 161 263.9 9.1 1 Main stem, major tributary
Mill Creek 164 267.9 7.0 2 On Ellenburger-San Saba Aquifer
(karst)
Rocky Creek 166 273.7 2.8 2 Near Ellenburger-San Saba
Aquifer (karst)
Llano River 168 276.5 0.0 1 On Ellenburger-San Saba Aquifer
(karst), major river
Terret Draw 185 315.9 9.5 2 On Edwards-Trinity (karst)
Middle Valley 192 324.2 14.9 2 On Edwards-Trinity (karst)
Antelope Draw 197 334.3 24.6 2 On Edwards-Trinity (karst)
Big Lake Draw 211 402.6 35.5 1 On Edwards-Trinity (karst), near
known karst feature
Garrison 216 415.8 40.3 2 Cenozoic Pecos Alluvium
China Draw 224 433.1 28.2 2 Cenozoic Pecos Alluvium
Mayfield Draw 234 450.2 22.6 2 Cenozoic Pecos Alluvium
1 Clear Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 85 meters.
2 Cedar Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 320 meters.
3 Maha Creek does not cross the pipeline, but at one location parallels the pipeline at a distance of 180 meters.

<<<PAGE 155>>>

Table 4.2.2-6 Ranking of Stream Crossings in Terms of Downstream Resource
Importance as a Water Supply
Stream at Crossing Map ID
Pipeline
Crossing
(MP)
Rank in Importance of
Proximity and Type of
Downstream Water
Supply (1= most
important) Basis for Rank
Hunting Bayou 1 2.5 6 Low quality water
Greens Bayou 3 7.0 6 Low quality water
Halls Bayou 8 16.0 6 Low quality water
Cypress Creek 34 47.1 3 Large irrigation right within 20 miles
Unnamed Tributary to Cypress
Creek 36 48.7 3 Large irrigation right within 20 miles
Mound Creek 37 50.4 3 Large irrigation right within 20 miles
Live Oak 3& 53.9 3 Large irrigation right within 20 miles
Harris Creek Tributary 41 51.0 3 Large irrigation right within 20 miles
Harris Creek Tributary 42 59.7 3 Large irrigation right within 20 miles
Clear Creek1 44 62.6 5 Small irrigation right within 20 miles
Brazos River 45 64.0 5 Small irrigation right within 20 miles
Muddy Branch 48 69.2 2 Municipal right within 75 miles downstream
East Fork Mill Creek 57 81.2 6 Small right, within 40/60 miles
Dogwood Creek 60 89.2 6 Small right, within 40/60 miles
West Fork Mill Creek 61 90.8 6 Small right, within 40/60 miles
Jacks Creek 67 98.3 6 Small right. within 40/60 miles
Cummins Creek 68 99.2 6 Small right, within 40/60 miles
Rabbs Creek 74 112.3 5 Small irrigation right within 20 miles
Knobbs Creek 77 118.8 5 Small irrigation right within 20 miles
Dreissner Branch 78 119.9 5 Small irrigation right within 20 miles
Pin Oak Creek 80 122.5 5 Small irrigation right within 20 miles
Gravelly Creek 81 123.0 5 Small irrigation right within 20 miles
JD Creek 82 126.7 5 On Colorado River Alluvium
Alum Creek 86 131.5 5 Alluvial irrigation well within 20 miles
Little Alum Creek 87 132.3 5 Alluvial irrigation well within 20 miles
Colorado River 89 134.5 5 Alluvial irrigation well within 20 miles
Unnamed 92 142.9 5 Alluvial irrigation well within 20 miles
Cedar Creek1 93 142.8 5 Alluvial irrigation well within 20 miles
Maha Creek1 97 151.7 5 Alluvial irrigation well within 20 miles
Dry Creek 99 157.4 1 14.9 miles to Colorado River Alluvium
Cottonmouth Creek 100 162.3 1 12.7 miles to Colorado River Alluvium
Marble Creek 101 163.5 1 13.7 miles to Colorado River Alluvium
Onion Creek 103 164.0 1 15.3 miles to Colorado River Alluvium
Slaughter Creek NS 174.0 1 8.2 miles to Hill Country Springs water intake
Barton Creek 109 180.9 1 26.3 miles to Edwards Balcones recharge
Flat Creek 112 193.2 1 Highland Lake within 40 miles downstream

<<<PAGE 156>>>

Table 4.2.2-6 Ranking of Stream Crossings in Terms of Downstream Resource
Importance as a Water Supply (continued)
Stream at Crossing Map ID
Pipeline
Crossing
(MP)
Rank in Importance of
Proximity and Type of
Downstream Water
Supply (1= most
important) Basis for Rank
Pedernales River 115 198.8 1 Highland Lake within 40 miles downstream
Cottonwood Creek 119 203.2 2 Highland Lake within 75 miles downstream
Hickory Creek 125 209.9 2 Highland Lake within 75 miles downstream
White Oak Creek 127 213.3 2 Highland Lake within 75 miles downstream
Crabapple Creek 135 229.3 2 Highland Lake within 75 miles downstream
Sandy Creek1 138 234.9 1 Alluvial public water supply well within 2 mi
Sandy Creek1 139 236.6 1 Alluvial public water supply well within 2 mi
Bernst Creek 140 237.8 1 Highland Lake within 40 miles downstream
Cherry Spring Creek 142 241.7 2 Highland Lake within 40 miles downstream
Marshall Creek 143 242.7 2 Highland Lake within 75 miles downstream
Squaw Creek 150 248.5 2 Highland Lake within 75 miles downstream
Threadgill Creek 151 250.0 2 Highland Lake within 75 miles downstream
James River 161 263.9 2 Highland Lake within 75 miles downstream
Mill Creek 164 267.9 2 Highland Lake within 75 miles downstream
Rocky Creek 166 273.7 5 Small irrigation right within 20 miles
Llano River 168 276.5 5 Small irrigation right within 20 miles
Terret Draw 185 315.9 2 Alluvial public water supply well within 60 mi
Middle Valley 192 324.2 4 Large irrigation right within 40 miles
Antelope Draw 197 334.3 4 Large irrigation right within 40 miles
Big Lake Draw 211 402.6 7 No uses identified within 60 miles
Garrison 216 415.8 7 No uses identified within 60 miles
China Draw 224 433.1 7 No uses identified within 60 miles
Mayfield Draw 234 450.2 7 No uses identified within 60 miles
1 - Does not cross the pipeline, but is within the zone of potential impact.

<<<PAGE 157>>>

Table 4.2.2-7 Summary of Vulnerability Rankings, Surface Water Crossings
Stream at Crossing Map ID
Pipeline
Station for
Crossing
(miles)
Rank in Importance
of Proximity and
Type of
Downstream Water
Supply (1= most
important)
Rank in Potential
to Control a Spill
(1 = most
difficult to
control)
Rank in Potential
to Transport a
Spill (1= highest)
Sum of
Ranks
Onion Creek 103 164.0 I 1 1 3
Pedernales River 115 198.8 I 1 1 3
James River 161 263.9 2 1 1 4
Barton Creek 109 180.9 1 1 3 5
Threadgill Creek 151 250.0 2 1 2 5
Cypress Creek 34 47.1 3 1 2 6
Flat Creek 112 193.2 1 3 2 6
Crabapple Creek 135 229.3 2 2 2 6
Squaw Creek 150 248.5 2 1 3 6
Terret Draw 185 315.9 2 1 3 6
Brazos River 45 64.0 5 1 1 7
Colorado River 89 134.5 5 1 1 7
Mill Creek 164 267.9 2 1 4 7
Llano River 168 276.5 5 1 1 7
Alum Creek 86 131.5 5 1 2 8
Cedar Creek 93 142.8 5 1 2 8
Cottonwood Creek 119 203.2 2 2 4 8
Hickory Creek 125 209.9 2 2 4 8
White Oak Creek 127 213.3 2 2 4 8
Middle Valley 192 324.2 4 1 3 8
Antelope Draw 197 334.3 4 1 3 8
Clear Creek 44 62.6 5 2 2 9
Muddy Branch 48 69.2 2 3 4 9
Maha Creek 97 151.7 5 1 3 9
Dry Creek 99 157.4 I 4 4 9
Unnamed Trib to Cypress
Creek 36 48.7 3 2 5 10
Mound Creek 37 50.4 3 3 4 10
Live Oak 38 53.9 3 3 4 10
Rabbs Creek 74 112.3 5 3 2 10
Pin Oak Creek 80 122.5 5 3 2 10
Cottonmouth Creek 100 162.3 I 4 5 10
Marble Creek 101 163.5 I 4 5 10
JD Creek 82 126.7 5 1 5 11
Little Alum Creek 87 132.3 5 1 5 11
Unnamed 92 142.9 5 1 5 11
Sandy Creek (1) 138 234.9 I 5 5 11
Sandy Creek (2) 139 236.6 1 5 5 11

<<<PAGE 158>>>

Table 4.2.2-7 (continued)
Summary of Vulnerability Rankings, Surface Water Crossings
Stream at Crossing Map ID
Pipeline
Station for
Crossing
(miles)
Rank in Importance
of Proximity and
Type of
Downstream Water
Supply (1= most
important)
Rank in Potential
to Control a Spill
(1 = most
difficult to
control)
Rank in Potential
to Transport a
Spill (1= highest)
Sum of
Ranks
Bernst Creek 140 237.8 I 5 5 11
Cherry Spring Creek 142 241.7 2 5 4 11
Knobbs Creek 77 118.8 5 3 4 12
Gravelly Creek 81 123.0 5 3 4 12
Harris Creek Trib 41 58.7 3 5 5 13
Harris Creek Trib 42 59.7 3 5 5 13
East Fork Mill Creek 57 81.2 6 5 2 13
Dreissner Branch 78 119.9 5 3 5 13
Big Lake Draw 211 402.6 7 1 5 13
Garrison 216 415.8 7 1 5 13
China Draw 224 433.1 7 1 5 13
Mayfield Draw 234 450.2 7 1 5 13
West Fork Mill Creek 61 90.8 6 6 2 14
Cummins Creek 68 99.2 6 6 2 14
Greens Bayou 3 10.0 6 6 2 14
Dogwood Creek 60 89.2 6 6 4 16
Jacks Creek 67 98.3 6 6 4 16
Hunting Bayou 1 4.0 6 6 4 16
Halls Bavou 8 17.3 6 6 4 16

<<<PAGE 159>>>

Table 4.2.2-8 Wetlands Inventory for Proposed Project from East
Houston/9th Street Junction to Crane
MP
From MP to
Wetland
Area Count
Wetland
Area Acres
Stream
Count
Wetland
Stream Miles County
0 10 79 195.05 0 0.00 Harris
10 20 69 131.48 0 0.00 Harris
20 30 107 264.05 0 0.00 Harris
30 40 192 555.37 0 0.00 Harris
40 50 113 2217.11 0 0.00 Harris
50 60 141 269.62 0 0.00 Harris/Waller
60 70 198 490.52 0 0.00 Austin/Waller
70 80 96 106.56 9 2.01 Austin
80 90 171 195.47 1 0.69 Austin
90 100 145 103.98 1 0.53 Austin/Fayette
100 110 151 115.54 9 1.11 Fayette
110 120 150 88.25 42 7.81 Bastrop/Fayette/Lee
120 130 151 75.29 3 1.13 Bastrop/Fayette
130 140 57 121.90 2 1.17 Bastrop
140 150 132 56.67 0 0.00 Bastrop
150 160 119 38.87 1 0.25 Bastrop/Travis
160 170 68 53.89 8 3.49 Travis
170 180 27 10.00 23 5.78 Travis
180 190 114 49.27 20 3.98 Hays/Travis
190 200 62 76.37 38 10.58 Blanco/Hays
200 210 54 17.85 26 6.35 Blanco
210 220 52 26.53 17 4.87 Blanco/Gillespie
220 230 47 18.76 34 7.07 Gillespie
230 240 44 9.47 41 12.66 Gillespie/Llano
240 250 60 71.98 18 6.84 Gillespie/Llano/Mason
250 260 28 29.58 21 6.36 Mason
260 270 22 61.31 29 7.92 Mason
270 280 20 80.72 20 6.15 Kimble/Mason
280 290 2 0.65 11 3.00 Kimble
290 300 7 3.41 37 11.52 Kimble
300 310 14 3.91 20 5.28 Kimble/Menard
310 320 5 4.17 5 1.33 Kimble/Menard/Schleicher
320 330 6 8.34 0 0.00 Schleicher
330 340 11 2.77 0 0.00 Schleicher
340 350 16 40.58 0 0.00 Schleicher
350 360 20 35.83 0 0.00 Schleicher

<<<PAGE 160>>>

Table 4.2.2-8 Wetlands Inventory for Proposed Project from East Houston/9th Street
Junction to Crane (continued)
MP
From MP to
Wetland
Area Count
Wetland
Area Acres
Stream
Count
Wetland
Stream Miles County
360 370 25 96.36 0 0.00 Crockett/Schleicher
370 380 16 44.16 0 0.00 Crockett
380 390 16 28.84 0 0.00 Crockett
390 400 12 2.64 0 0.00 Crockett/Reagan
400 410 21 13.24 11 3.09 Reagan
410 420 29 24.42 2 0.19 Reagan
420 430 20 8.54 0 0.00 Reagan/Upton
430 440 3 0.53 0 0.00 Upton
440 450 5 1.65 0 0.00 Upton
450 456 1 0.40 0 0.00 Crane/Upton
2.898 5,851.90 449 121.16

<<<PAGE 161>>>

Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the Zone of
Potential Impact of the Proposed Project1
Status3
Common Name2 Scientific Name2 FWS TPWD Counties of Potential Occurrence4 Potential for Occurrence5
BIRDS
American Peregrine
Falcon Falco peregrinus anatum NL T
Austin, Bastrop, Blanco, Crane, Crockett,
Fayette, Gillespie, Harris, Hays, Kimble,
Mason, Menard, Reagan, Schleicher,
Travis, Upton, Waller
Attwater’s Greater Prairie-
Chicken
Tympanuchus cupido
attawateri E E Austin, Waller
Bald Eagle Haliaeetus leucocephalus DL T
Blanco, Crockett, Gillespie, Hays,
Kimble, Mason, Menard, Reagan,
Schleicher, Travis, Upton, Potential Migrant
Black-Capped Vireo Vireo atricapilla E E
Blanco, Crockett, Gillespie, Hays, Pecos,
Kimble, Mason, Menard, Reagan,
Schleicher, Travis, Upton No
Brown Pelican Pelecanus occidentalis NL E Harris No
Golden-Cheeked Warbler Dendroica chrysoparia E E
Blanco, Gillespie, Hays, Kimble, Mason,
Menard, Travis No
Interior Least Tern Sterna antillarum athalassos NL E
Austin, Bastrop, Crane, Crockett,
Fayette, Travis, Waller Potential Migrant
Peregrine Falcon Falco peregrinus DL T
Austin, Bastrop, Blanco, Crane, Crockett,
Fayette, Gillespie, Harris, Hays, Kimble,
Mason, Menard, Reagan, Schleicher,
Travis, Upton, Waller Potential Migrant
Red-cockaded
Woodpecker Picoides borealis NL E Harris
Reddish Egret Egretta rufescens NL T Pecos, Reeves
White-Faced Ibis Plegadis chihi NL T Austin, Harris, Waller Potential Migrant
White Tailed Hawk Buteo albicaudatus NL T Austin, Harris, Waller

<<<PAGE 162>>>

Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the Zone of Potential Impact of the
Proposed Project (continued)
Status3
Common Name2 Scientific Name2 FWS TPWD Counties of Potential Occurrence4 Potential for Occurrence5
Whooping Crane Grus americana E E
Austin, Bastrop, Blanco, Fayette,
Gillespie, Harris, Hays, Kimble, Mason,
Menard, Reagan, Schleicher, Travis,
Waller Potential Migrant
Wood Stork Mycteria americana NL T Austin, Bastrop, Fayette, Harris, Waller No
Zone-Tailed Hawk Buteo albonotatus NL T
Blanco, Crockett, Gillespie, Hays,
Kimble, Mason, Menard Potential Migrant
Fishes
Blue Sucker Cycleptus elongatus NL T Bastrop, Fayette, Hays No
Clear Creek gambusia Gambusia heterochir E E Menard No
Creek Chubsucker Erimyzon oblongus NL T Harris, Waller No
Fountain Darter Etheostoma fonticola E E Hays No
Pecos Pupfish Cyprinodon pecosensis NL T Crane, Crockett No
Proserpine Shiner Cyprinella proserpina NL T Crockett No
Rio Grande Darter Etheostoma grahami NL T Crockett No
San Marcos Gambusia Gambusia georgei E E Hays No
Smalltooth Sawfish Pristis pectinata NL E Harris No
Mammals
Black Bear Ursus americanus NL T
Austin, Blanco, Crane, Crockett,
Gillespie, Kimble, Mason, Reagan,
Schleicher, Upton No
Gray Wolf Canis lupus EXP E
Blanco, Crane, Crockett, Gillespie,
Kimble, Mason, Menard, Reagan,
Schleicher, Upton
Louisiana Black Bear Ursus americanus luteolus NL T Austin, Harris No
Ocelot Leopardus pardalis NL E Crockett No
Rafinesque’s Big-eared Corynorhinus rafinesquii NL T Harris

<<<PAGE 163>>>

Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the Zone of Potential Impact of the
Proposed Project (continued)
Status3
Common Name2 Scientific Name2 FWS TPWD Counties of Potential Occurrence4 Potential for Occurrence5
Bat
Red Wolf Canis rufus NL E
Austin, Bastrop, Blanco, Fayette,
Gillespie, Harris, Hays, Kimble, Mason,
Menard, Schleicher, Travis, Waller
Trichechus manatus
West Indian Manatee
E NL Harris No
Mollusks and other
Invertebrates
False Spike Mussel Quadrula mitchelli NL T
Austin, Bastrop, Blanco, Crane, Crockett,
Fayette, Gillespie, Hays, Kimble, Mason,
Menard, Travis, Waller
Golden Orb Quadrula aurea NL T Blanco. Gillespie, Hays
Louisiana Pigtoe Pleurobema riddellii NL T Harris
Sandbank Pocketbook Lamsilis satura NL T Harris
Smooth Pimpleback Quadrula houstonensis NL T
Austin, Bastrop, Blanco, Fayette, Mason,
Menard, Travis, Waller
Texas Hornshell Popenaias popeii NL T Crane, Crockett, Schleicher
Texas Fatmucket Lampsilis bracteata NL T
Crane, Gillespie, Hays, Kimble, Mason,
Menard, Travis
Texas Fawnsfoot Truncilla macrodon NL T
Austin, Bastrop, Blanco, Fayette, Kimble,
Mason, Menard, Travis
Texas Pigtoe Fusconaia askewi NL T Harris
Texas Pimpleback Quadrula petrina NL T
Bastrop, Blanco, Fayette, Gillespie,
Hays, Kimble, Mason, Menard, Travis
Bee Creek Cave
Harvestman Texella reddelli E NL Travis
Bone Cave Harvestman Texella reyesi E NL Travis

<<<PAGE 164>>>

Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the Zone of Potential Impact of the
Proposed Project (continued)
Status3
Common Name2 Scientific Name2 FWS TPWD Counties of Potential Occurrence4 Potential for Occurrence5
Comal Springs Dryopid
Beetle Stygoparnus comalensis E NL Hays
Comal Springs Riffle
Beetle Heterelmis comalensis E NL Hays
Tooth Cave Ground
Beetle Rhadine persephone E NL Travis
Tooth Cave
Pseudoscorpion Tartarocreagris texana E NL Travis
Tooth Cave Spider Neoleptoneta myopica E NL Travis
Warton’s Cave
Meshweaver Cicurina wartoni C C Travis
Reptiles
Alligator Snapping Turtle Macroclemys temmincki NL T Austin, Harris, Waller
Cagle’s Map Turtle Graptemys caglei NL T Hays
Green Sea Turtle Chelonia mydas NL T Harris No
Kemp’s Ridley Sea Turtle Lepidochelys kempii NL E Harris No
Leatherback Sea Turtle Dermochelys coriacea NL E Harris No
Loggerhead Sea Turtle Caretta caretta NL T Harris No
Smooth Green Snake Liochlorophis vernalis NL T Austin, Harris
Texas Horned Lizard Phyrnosoma cornutum NL T
Austin, Bastrop, Blanco, Crane, Crockett,
Fayette, Gillespie, Harris, Hays, Kimble,
Mason, Menard, Reagan, Schleicher,
Travis, Upton, Waller
Timber/canebrake
Rattlesnake Crotalus horridus NL T Austin, Bastrop, Fayette, Harris, Waller
Trans-Pecos Black
Headed Snake Tantilla cucullata NL T Crockett

<<<PAGE 165>>>

Table 4.3.1-1 Threatened and Endangered Species of Possible Occurrence Within the Zone of Potential Impact of the
Proposed Project (continued)
Status3
Common Name2 Scientific Name2 FWS TPWD Counties of Potential Occurrence4 Potential for Occurrence5
Amphibians
Austin Blind Salamander Eurycea waterlooensis C C Hays, Travis
Barton Springs
Salamander Eurycea sosorum E E Hays, Travis
Houston Toad Bufo houstonensis E E Austin, Bastrop, Harris, Waller
Jollyville Plateau
Salamander Eurycea tonkawae C NL Travis
San Marcos Salamander Eurycea nana T T Hays
Texas Blind Salamander Eurycea rathbuni E E Hays
Plants
Navasota Ladies’-tresses Spiranthes parksii E E Bastrop, Fayette
Texas Prairie dawn Hymenoxys texana E E Harris
Texas Snowbells Styrax texana E NL Kimble
Texas Wild-rice Zizania texana E E Hays
Tobusch Fishhook Cactus Ancistrocactus tobuschii E E Kimble
1According to TPWD (2011) and FWS (2011)
2Nomenclature follows Hubbs et al. (2008), AOU (1998, 2000, 2002, 2003, 2004, 2005, 2006, 2007, 2008, 2009), Crother et al. (2000, 2001, 2003, 2008), Baker et al.
(2003), TPWD (2011), and FWS (2011)
3E – Endangered; T – Threatened; T/SA – Threatened by similarity of appearance; DL – Federally delisted; PDL – Proposed for Federal Delisting; PE – Federally proposed
endangered; PT – Federally proposed threatened; C – Federal candidate species; NL – Not listed.
4 Counties included are for both state and federal lists. More often, the state listed more counties for potential occurrence than the federal list.
5 Potential for occurrence within or immediately adjacent to new construction sites for Longhorn.

<<<PAGE 166>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 4
FIGURES

<<<PAGE 167>>>

£ ¤ 90
ilibert
Elbert
Kirkpatrick
£ ¤ 90
Tree Path
Oak Brook
"
" )7
" )5
"
Needham
Maxey
Pecan
Pecan Grove
Grand
Hewrick
Exchange
Terminal
Salina
Iris
Alderson
Force
Gainesville
Longview
Texarkana
Eagle Pass
Victoria
Meters
Exchange
Terminal
Laredo
Hillsboro
Waxahachie
Hershe
Hershe
Terminal
East
Grimes
Waller
Fort Bend
Birmingham
Parkhurst
Nashville
King
Queen
Amy
Miley
Attwater
Barton
Sparta
Ina
Amy
Fairchild Clu
Peab
Eastover
Nashville
Betty Boop
Henson
Henson
Queensl
Mesa
Railspu
Belroit
Nielan
Spikewood
Express
"
Earhart
Nielan
Midway
Haight
Sunbury
Ethel
Ethel
Fleta
Chateau
Saint Louis
Bacher
Blue
Bobby Burns
Queensland
Norwich
Wileywood
Crim
Foxfern
Howton
Turtlewood
Lewiston
Fairchild
Boy
Howton
Filltop
Wedgefield
Dollar
Danshire
Lodgepole
Little
Wayside
Jeffery
Fitzhugh
Oates
Miley
Knute
Perch Creek
Foxhunter
Attwater
Attwater
Harris County Cemetery
Barnesworth
Edenglen
Kenton
Pinewest
Nordic
Angus
Northlake
Pinewest
Sandy
Fowlie
Fernlake
Hanna
Hanna
Thrasher
Cinderella
Sparta
Hollow Pines
Northport
Homeview
Wood Bend
Flair
Dartwood
Sparta
Bonaire
Tommye
Barlow
Bonaire
Queensland
Teal
Teal
Rainy Sun
Javelina
Beau Harp
Tatefield
Tate
Manton
Wonfour
Booker
Eastland
Kelford
Nielan
Tate
Penelope
Callixtus
Comets Run
Lourdes
Wayside
Fields
Balfour
Fields
Evangeline
BC ELMORE MIDDLE
Swoopes
Wynnewood
Amayas
Lake Houston
Ina
Amy
Fairchild
Sexton
Hollow Pines
Lorne
Lorne
Merry Meadow
Meyersville
Hopetown
Pandora
Gorman
Graycliff
n n
Gates
" )4
" )8 " )7
Seclusion
Morinscott
Pardee
"
Gloria
" )6
"
Janeths
Ranger
Rand
Rand
Liberty
"
"
ï
" )6
Circle Drive Park
Debra
"
Hollow Pines
Trail Wind
Callahan
Wood Bend
Wallisville
§ ¨ ¦610
Millard
Settegast
Millard
Romea
" )3
Shadrack
Normandy
Ranger
"
Citypark
O S T
Guessena
Clara
G
Herschell
Colvin
Royce
Green Dolphin
r
e
en
" )9
Cibolo
Holland
Dattner
s
"
£ ¤ 90
Saltillo
Harvey
Bayou
Manitou
Coahuila
Groveland Terrace Park
Rafael
San Pedro
Texaco
Thornhill Oaks
Wayside
Carlos
ï
Banner
Santa Cruz
Zaballos
Old Pine
Killene
Ophelia
Old Spring
Old Pine
Ripplewood
Amoor
Beaver
San Carlos
Herald
Mesa
Texaco Country Club
" )2.31
Alsuma
Aguila
Villita
Eve
Claudia
s
Forestwood
Wood
Hidden Castle
"
Farqueson
EAST HOUSTON
"
"
Trailmobile
Baca
Profet
" )9.47
La Retama
Coolgreen Corridor (PB 4)
Coolgreen
ï
Stillington
" )5
Hunt
"
Glenstone
Strickland Park
Tammarack
i
Wild Plum
Highridge
ï
Oates
o
u
B a
Eastbrook
n
g
y
Spaniel
Labelle
Woodforest
Labelle
Rauch
Brown (Herman) Park
Charlie Voix
ï
Glesby
Wood Forest
La Grove
Province Point
Chambly
La Riviera
Aire
Neuville
Bienville
Aire
§ ¨ ¦610
Wood Forest
Bowhead
Woodbuck
Badgerwood
Wood Smoke
Woodforest
Coolwood
Wood Vista
Woodhurst
Saint Edwards Green
Dijon
Beaupre Point
Toulouse
La Rochelle
Halifax
Saint Michel
Chalmette
Versailles
Corsica
Nice
Rue Fontaine
Cheam
Woodshaver White Water
Borderwood
Wood Mist
Joliet
Wood Bayou
Dijon
Joliet
Laredo
Dividend
Crystalwood
Coolwood
Woodcliff
Touche
Fawn
Corpus Christi
Peoria
Orleans
Hillsboro
Ranger
Waxahachie
Pearl
Aleen
Hershe
Portwall
Currency
East
Community College
Broadstairs
Dunvegan
Brockhampton
Heysham
Oldcastle
Cappamore
Garrick
Rainy Meadow
Baca
Garrick
Filey
Soft Shadows
Wild Wind
Donnacorey
Caney
Buffalo
Falloon
Fox
Elk
Royale
Addicks
Normandy Crossing
Grand Oaks
Peoria
Redondo
Rosewick
Emporia
Lafferty Oaks
Falloon
Knollcrest
Lafferty Oaks
Lyons
East
"
Mile Post
Land Use
Montgomery
Switzer
Fleming
Valencia
Housing Density
Kilroy
Wild Wind
"
" )4
Wood Shadows
Summerwood
Church
Maple
Liberty
Westshire
Valencia
Wood Shadows
Coolwood
Bluemist
Mae
Westmont
Æ P Healthcare Facility
Developed
Duncum
Aleen
0 - 20 Units/Mile
Duncum
n School
Forest
East
21 - 100 Units/Mile
John Ralston
Centerwood
Autumnwood
Fleming
Greatwood
Sachamo
I
Roundtree
Environmental Assessment
Longhorn Pipeline Reversal
ï Park
§ ¨ ¦10
Lear
Gellhorn
Wetlands
>100 Units/Mile
Luther
Greens Bayou
Garber
Dawnwood
Figure 4.1.2-1a
Harris
s Country Club/Golf Course
Agricultural
Rumar
La Crosse
La Crosse
Walkway
Baca
Verano
Maxey
Sheffield
Halsey
McNair
Houston Area Land Use
Akron
² ¶ Overnight Lodging
Loop
Loop
La Crosse
Open Water
Muscatine
Dacus
Muscatine
Shrub/Scrub
Fidelity
Oates
Flint
Challenger 7
Invierno
Hunting Bayou
Mae
Keyport
Falcon
and Housing Density
East
§ ¨ ¦10
Nimitz
Portwall
SHEET 1 OF 9
Longhorn Pipeline
Brazoria
Galveston 0 0.5 1
Candy
Laurentide
Siesta
Oates
Keyport
Oswego
Meris
Prepared By: Atkins/19685
Market St
Dove
Barcus
Scale: 1:24,000
Barren Land (Rock/Sand/Clay)
Kilroy
Mae
Maxey
Job No.: 100019708
Dwight
Lear
Land Use Source: USGS 2006 NLCD
Fannette
Palestine
Falcon
Miles
Dewey
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Market Street
Berndale
Switzer
Palestine
Akron
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Rye
tville
Silverdale
Tilgham
Wiggins
Gellhorn
Cowart
Norvic
Kilroy
Cowart
Mercury
Walkway
Sheryl
Horatio
Tilia
Judy
Kathryn
Yancy
Kathryn
Alice
Elsies
Sarahs
Capistra
Yancy
Vickie
irley
Nola
Nolas
Blythe
Berwick
Vicksbur
Chelto
Laguna
Candlewick
Rockglen

<<<PAGE 168>>>

Laredo
Hillsboro
Waxahachie
Hershe
East
Pearl
Aleen
Lyons
Aleen
Rye
Silverdale
Portwall
Wiggins
Gellhorn
Munn
Demaree
Silverdale
Fillmore
Cargill
Richcroft
Northton
Grimes
Waller
Portwall
Teanaway
Pleasantville
Demaree
Teanaway
Bucroft
High Level
Fort Bend
end
Currency
Community College
Broadstairs
Dunvegan
a
Brockhampton
Heysham
Oldcastle
Cappamore
Garrick
Rainy Meadow
Baca
Garrick
Filey
Soft Shadows
Wild Wind
Donnacorey
Caney
Buffalo
Falloon
Fox
Elk
Royale
Addicks
mandy Crossing
Grand Oaks
Peoria
Redondo
Rosewick
Emporia
Lafferty Oaks
East
Falloon
Knollcrest
Lafferty Oaks
Switzer
Fleming
Valencia
Kilroy
Wild Wind
"
" )4
Wood Shadows
Summerwood
Church
Duncum
Westshire
Valencia
Wood Shadows
Coolwood
Bluemist
Mae
Duncum
East
John Ralston
Centerwood
Autumnwood
Fleming
e
n
s Ba
y
ou
§ ¨ ¦10
Greatwood
Sachamo
Roundtree
Gellhorn
Luther
Garber
Greens Bayou
Dawnwood
Rumar
La Crosse
La Crosse
Walkway
Baca
Verano
Maxey
Sheffield
Halsey
McNair
Akron
Loop
Loop
La Crosse
Muscatine
Dacus
Fidelity
Muscatine
Oates
Flint
² ¶
Hunting Bayou
Mae
Keyport
Falcon
East
Gr e
Maple
Westmont
Lear
§ ¨ ¦10
Candy
Laurentide
Challenger 7
Invierno
Siesta
Market St
Oates
Oswego
Keyport
Nimitz
Meris
Dove
Barcus
Kilroy
Mae
Fannette
Maxey
Dwight
Lear
Palestine
Berndale
Tilgham
Wiggins
Switzer
Palestine
Falcon
Dewey
Market Street
Akron
Cowart
Cowart
Norvic
Kilroy
Mercury
Walkway
Sheryl
Horatio
Tilia
Judy
Kathryn
Yancy
Wiggins
Burman
Kathryn
Alice
Elsies
Sarahs
Pattibob
Pillot
" )3
Celtis
Seagram
Capistrano
Yancy
Vickie
Dorwayne
Powell
Josie
Munn
Hart
"
Lord
Chadwick
Flossie Mae
Maryknoll
Falcon
Shirley
Celia
Berthas
Century
Kerbey
Hiller
Myrtle
Othello
Ledwicke
Quaker
Flaxman
Flaxman
Fairfax
Guinevere
Chazen
Cheston
Caspersen
Serpentine
Peppertree
Coulson
Adelia
Coulson
PYBURN EL
Industrial
Mylla
Sheffield
n
Peggys
Lanewell
Lane
Lanewell
Jennifer
Maricopa
Watkin
Rita
Belin
Janey
Samuel
Lila
Strick
Fillmore
Flagship
§ ¨ ¦610
Cargill
Harcroft
Miles
Bucroft
Dunaway
Pinky
Birdie
Parkey
Ellen
Richcroft
Kerr
Claudia
Cain
Tuffly
Holland
Masterson
Turning Basin
Kayla
Garcroft
Kitty
Signet
Plummer
Main
Stedman
Ledger
Bennett
Industrial
Turnbow
Veyblum
" )2
Nedwald
"
Racine
Mimbrough
Pelsey
Fidelity
19th
18th
Tite
Tite
Tennessee
16th
Benson
Westway
18th
17th
Eastway
17th
Parkside
18th
17th
Sol
Mississippi
15th
Hunter
16th
Calloway
Wolfe
Calloway
14th
Borden
Clearwater
Leggett
15th
15th
15th
Crown
Pugh
14th
Keene
Maxine
Georgia
13th
Cartersville
Craig
Westway
14th
13th
13th
13th
American Petroleum
Teal
Defender
12th
Zuber
Owens
12th
12th
Owens
North Carolina
11th
Center
12th
De Haven
10th
Sage
Zachary
Leggett
11th
11th
10th
10th
" )1.23
Gate 1
De Haven
Midway
Bolden
Clinton Park
Bolden
Bank
9th
Craig
9th
Delaware
8th
8th
Pennsylvania
7th
Westway
9th
8th
8th
Sinclair
9th
Galena
Crown
"
River
7th
Parkside
Wolfe
8th
7th
Rhode Island
7th
Armstrong
Armstrong
6th
6th
6th
6th
6th
6th
Gans
Loop
5th
5th
Gans
Loop
Connecticut
4th
Graham
McConnico
Westway
5th
5th
5th
5th
4th
3rd
3rd
Westway
3rd
Sinclair
4th
4th
Eastway
Stewart
3rd
Crown
2nd
"
Witter
Mile Post
Land Use
Housing Density
Liberty
Æ P Healthcare Facility
Developed
0 - 20 Units/Mile
n School
Forest
21 - 100 Units/Mile
I
ï Park
Wetlands
>100 Units/Mile
Harris
s Country Club/Golf Course
Agricultural
² ¶ Overnight Lodging
Open Water
Longhorn Pipeline
Shrub/Scrub
Brazoria
Barren Land (Rock/Sand/Clay)
Galveston 0 0.5 1
Land Use Source: USGS 2006 NLCD
Miles
Blythe
Berwick
Cimarron
Mobile
Oakstone
Vicksburg
Chelton
Laguna
Candlewick
Glenalbyn
Rockglen
Kokomo
Bandera
Utica
Evanston
Duluth
Boise
Topeka
Uvalde
Haden
Taylor
Jackson
Clinton
Federal
Montgomery
Jefferson
Olin Mathieson
1st
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-1b
Houston Area Land Use
and Housing Density
1st
SHEET 2 OF 9
Prepared By: Atkins/19685
Scale: 1:24,000
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Ironwood

<<<PAGE 169>>>

Shady
ï
Tidwell Park
Lockern
Styling
Barnham
Bainbridge
Wicklowe
Onslow
Bucknell
Castleton
Wolbrook
Envoy
Bretton
Hollyglen
Royal Oaks
Rockaway
rwick
Bainbri
Langley
Onsl
Briarwick
Wo
S
Allwood
Ferol
Ina
Fala
NORTHEAST CHRISTIAN
Okay
n
Marilyn
Orlando
Lera
" )14
Tully
W E ROGERS EL
Spinet
Navasota
Melanie
J L Reaux
n
n
"
Saunders
Gleason Park
Scenic Woods Park
ï
Woodwick
Forest Hollow
Gore
Blades
ï
Rebel
Lakewood
Kelburn
Mayberry
Lakewood
Colton
Boggess
Cockburn
Lakewood
Boggess
Deanna
Lebra
Harmaston
" )13
Parker
Everglade
"
Wiley
Yoe
Yoe
Stonewood
Madera
Nyssa
Haddick
Nyssa
Yoe
Rhobell
Cheeves
Rhobell
Charlesmont
Rhobell
Caddo
Ribbonwood
Kentshire
Thorn
League
Madera
Deanna
Caddo
Rebel
Bigwood
Woodwick
Hillis
Caddo
Bigwood
Sterlingshire
Haddick
Arvin
Bella Pine
Sterlingshire
Cabot
Matson
Cabot
Maddox
Sterlingshire
" )12
Thorn
Cabot
Claiborne
Galaxy
Claiborne
Farragut
Bretshire
Locksley
Claiborne
Maddox
Greenwich
Cabot
Hillis
"
Gillman
Lum
Denning
YES PREP NORTH FOREST CAMPUS
Claiborne
n n
n n
Trumpet
Kerry Glen
Caballero
Courben
Alcanterra
Linares
Shive
ll
s
B
a
y
o
u
H
a
Hallshire
Hamlet
Hanford
Locksley
Hillis
Guest
KIRBY MIDDLE
Alcala
Gallahad
KIPP VOYAGE ACADEMY FOR GIRLS
Tidwell
Maddox
KIPP POLARIS ACADEMY FOR BOYS
Hamlet
KIPP LEGACY PREPARATORY
n n n
n n n
Halls Bayou Park (PB2)
Balsam
Tidwell
Pereida
ï
Mosswood
KIPP NORTH FOREST LOWER
KIPP NORTH FOREST LOWER GIRLS
" )11
Wiloak
ï
"
Sundown
Count
Count
Seeker
Hillis
Parkette
East Tidwell Park
Record
Record
Haddick
Bean
Lake Forest Park
Southwark
ï
Firnat
Teesdale
Snowden
Snowden
Arvin
Fringewood
Forest View
Pembrook
Bellingham
Sunderland
Lanewood
Kelburn
Crofton
Levering
Lynette
Tremont
Kellett
Kellett
Kellett
Lake Park
Mirawood
Spaulding
Sherbourne
Kellett
Way
Lazydale
Lake Forest
Sundown
Wayside
Talton
Monterrey
Talton
Talton
Roane
Livings
Surry
Chatwood
Leighton
Shreveport
Fawnridge
Homewood
Seeker
Burl
Homewood
Spode
Glen Manor
Compton
Laura Koppe
Darien
Woodwick
Woodlyn
Woodlyn
Arlen
Sultan
Homewood
Laura Koppe
Laura Koppe
Laura Koppe
Touchstone
Springdale
Settegast
Oak Knoll
Oak Knoll
Linda Vista
Las Cruces
Woodlyn
Grandriver
Linda Vista
Oak Knoll
Strathmore
Banting
Touchstone
Denton
Westcott
Bywood
Parkhurst
Richland
Feland
Linda Vista
Weyburn
Leben
Weyburn
Wayside
Crestview
Mestina
Crestview
Richland
Carolwood
Carolwood
Hall
Flintridge
Flintridge
Knoll
Darlington
Darlington
Carothers
Palo Blanco
DeWitt
Palo Alto
Orville Green River
Orville
Winship
Green River
Delavan
Larkstone
Weaver
Herschell
Houston
Leycrest
Ley
Landor
Elbert
Darien
Finch
Furray
Tremont
Furray
Fitzhugh
Las Cruces
Tipton
Finch
Finch
Dockal
Pond
Kittridge
Lebate
Brim
Safebuy
Roundhouse
Senna
Ritz
Safebuy
Banyan
Penrod
Cluett
Peabody
Joy
Birmingham
Tommye
Railwood
Parkhurst
Eastover
Nashville
Nashville
Betty Boop
Henson
Queensland
Mesa
Railspur
Belroit
Henson
Nielan
Spikewood
Apache
Express
Elbert
Earhart
Philibert
Nielan
Midway
Haight
Sunbury
King
Ethel
Grimes
Kirkpatrick
Ethel
Queen
Fleta
Chateau
"
Saint Louis
Bacher
Mile Post
Land Use
Montgomery
Blue
Bobby Burns
Queensland
Norwich
Liberty
Æ P Healthcare Facility
Howton
Amy
Fairchild
Boy
Howton
Filltop
Wedgefield
Dollar
Housing Density
Developed
Miley
Waller
n School
Little
Wayside
Jeffery
Forest
Fitzhugh
0 - 20 Units/Mile
Miley
Knute
21 - 100 Units/Mile
ï Park
Attwater
Wetlands
Attwater
Attwater
>100 Units/Mile
Harris County Cemetery
Harris
s Country Club/Golf Course
Kenton
Agricultural
Angus
² ¶ Overnight Lodging
Sandy
Fowlie
Open Water
Hanna
Hanna
Fort Bend
Longhorn Pipeline
Barton
Shrub/Scrub
Cinderella
Sparta
Sparta
Brazoria
Sparta
Barlow
Barren Land (Rock/Sand/Clay)
Galveston 0 0.5 1
Land Use Source: USGS 2006 NLCD
Bonaire
Tommye
Bonaire
Queensland
Tree Path
Oak Brook
Ina
Amy
Fairchild
Tatefield
Tate
Tate
Manton
Penelope
Wonfour
Kelford
Nielan
Callixtus
Comets Run
Miles
rchild
Wayside
Booker
Fields
Eastland
Balfour
Fields
Evangeline
BC ELMORE MIDDLE
Swoopes
Wynnewood
Amayas
Pandora
Meadow Bend
Garden Gale
Roxdale Ridge
John Ralston
Cay Sol
Kona Cay
Islamorada
Jasamine Path
Island Song
Hazy Hill
Valley Hollow
Valley Lake
Valley Mill
Valley Park
Valley Side
Brock Park
Valley Sun
Valley Breeze
Valley Flag
Valley Club
Valley Club
Valley Meadow
Valley Ledge
Valley Wind
Valley Wind
Valley Rock
Valley Song
Valley Forest
s
Brook Park and Golf Course
" )10
"
Brock Park
ï
Scenic River
Rio Verde
Palo Verde
Cyrl
Spicewood
Ley-Green River
Housely
Danvers
Park Trail
Drifting Winds
Coral Reef
Blue Island
Aloha Trail
Ginger Lei
San
Fern Forest
Enchanted Path
Drifting Winds
Parkway Forest
Yvonne
Barker
Crenshaw
Lambert
Ticonderoga
Nodding Pines
Robert E Lee
Redbird
Green River
"
" )9
Bridle Path
Heather Row
Westgard
Jeanne
Pamela
Clark Wheeler
Kindred
" )8
"
C E King
Gregdale
Westbay
Bracrest
Lake Houston
Charpiot
£ ¤ 90
Greens Bayou
£ ¤ 90
Oates
I
Crim
Foxfern
Wileywood
Lodgepole
Turtlewood
Danshire
Environmental Assessment
Longhorn Pipeline Reversal
Perch Creek
Figure 4.1.2-1c
Barnesworth
Houston Area Land Use
Foxhunter
and Housing Density
SHEET 3 OF 9
Thrasher
"
Prepared By: Atkins/19685
" )7
Scale: 1:24,000
Teal
Teal
Javelina
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Lake Houston
Seclus

<<<PAGE 170>>>

Slater
Hill
Erwin
Chrisman
Collins
dy
Hartwick
Wedgewood
Birchwood
Mooney
Hardy Toll
Chamberlain
Kitchener
Woodcourt
Cliffside
Parkstone
Oak Glen
Brooklyn
Mesquite
Isom
Aldine Westfield
" )18
"
Aldine Park
Exeter
Havner
Sunny
Maymount
Norlinda
Rusty
July
Hartley
Gloger
Winfield
Eastex
Hillside
Collins
Illene
Gaston
Charwon
Hartwick
Harmon
Van Zandt
Percy
Haile
Allwood
Hanley
Mohawk
Warner
Askins
Lakeside
Royal Lake
Pine Island
Smith
Westway
Peaceful
Hermann
Mount Houston
Sheridan
Sherway
Cayey
Micollet
Tomahawk
Indian Spring
Cobble Hill
Arrowrock
Flatrock
Knotty Pine
Lone Shadow
Furay
Palmala
Moray
Owl Roost
Fernlea
Leedale
Ledford
Burningbush
Hedgewood
Pinehook
Haverton
Pittswood
Heath
Ensworth
Thackery
Lone Oak
Michulka
Hardy
Hardy Toll
Hardy Toll
Hardy
Irvington
Grimes
Waller
Exeter
Exeter
Fort Bend
Bethany
Winfield
Fall Meadow
Blue Meadow
Sandy Meadow
Pear Meadow
Pine Meadow
Hay Meadow
Shady Meadow
Plum Meadow
Connor
Hirsch
Sugar Ridge
Vickery
Hermann
Mandy
Brunswick
Orange Grove
Orange
Northington
Daun
Varnell
Magnolia
Sachar
Elberta
Huse
Keith-Wiess Park
ï
Ashworth
Northpost
Justin
Justin
Collins
Danford
Foxhill
Mierianne
Oakville
Washington
Collins
Gaston
Roughlock
Mierianne
Gaston
Gaston
Suburban
Ruby Rose
Rechelle
Gaston
Bertrand
Korpink
Charwon
Task
Mesquite
Sam Houston
Monitor
Micollet
Fishel
Lera
Micollet
Merrimac
Cobalt
Castledale
WORSHAM EL
Castledale
Cobalt
Blades
Cheeves
Lemond
Spottswood
Quiet
Shady
Royal Pine
n
n
Hartwick
Harrow
Hartwick
Havner
£ ¤ 59
Annunciation
Raincove
Danford
Ribstone
Cobalt
Turn
Wedgewood
7 Mile
Hurlingham
Guadalupe
Brea Crest
Brea Crest
Delman
Lemond
Annunciation
Mooney
Sunny
Wardmont
Seven Mile
Harmon
Somerset
Mooney
Innsbury
Mooney
" )17
Van Zandt
Lera
Blades
Rebel
Vailview
"
Tamworth
Wardmont
Wardville
Hopper
Van Archer
Heath
Dalebrook
Warwick
Cohutta
Symbol
Hopper
Vailview
Ledford
Hanley
Cromwell
Cromwell
Bentley
Mohawk
Eastex
Mohawk
Ivy Leaf
Hanley
Mohawk
Lera
Rosemary
Chamberlain
Royal Pine
Cedar Hill
Copley
Holbrook
Rosemary
Rosemary
" )16
Mock
Cedar Hill
Spottswood
Vailview
Tamworth
Hanley
William Tell
Kowis
Kowis
James Driver Park
"
Shelton
ï
Sagebrush
Wicklowe
Askins
White Thorn
Mardale
Lera
Leedale
Linvale
Ledford
Epsom
Harcourt
White Pine
Trenton
Royal Pine
Cricket
Nuggent
Darwin
Keith
Ell
Three Sisters
United
Tautenhahn
Maple Leaf
Lucerne
Lera
Bluestone
Tautenhahn
Trenton
Somerset
Trenton
Tolar
Shady
Æ P
Barksdale
SCARBOROUGH EL
Vivian
Peach
Hirsch Road Park
n
n
ï
Littlecrest
Homestead
Yorkwood
" )15
Pine Tree
Willie
Yorkwood
Wicklowe
Castleton
Ida Wells Forest
n
n
Seven Mile
Pine Tree
Fleetwood
"
Durwood
Rothermel
Knightwood
FONWOOD EL
Hardwood
Pinewood Village Park
Park
Woody
ï
Briarwick
Strickland
Stafford
Briarwick
Bainbridge
Onslow
Wolbrook
Seneca
Ferol
Briarwick
Ina
Langley
Withers Park
Langley
Langley
Fala
NORTHEAST CHRISTIAN
ï
Marilyn
Okay
n
Tully
W E ROGERS EL
Margaret
Foy
Orlando
Jensen
Friendly
Willie
Noldale
Marilyn
Orlando
Lera
" )14
Saunders
Peach
Spinet
Saunders
"
Nolridge
Moreau
Saunders
Navasota
Melanie
J L Reaux
n
n
Gwen
Bantum
H
Lakewood
Marzelle
Goodloe
a
l
l
s
Lowrie
Larry
Edgewater
Calgary
Charles
Carlington
Ba
Dodson
Farb
Caxton
Gateway
u
y o
Allbritton
Lakewood
Terrell
Nold
Barnham
Bainbridge
Wicklowe
Onslow
Castleton
Wolbrook
Gleason Park
Scenic Woods Park
Envoy
Bretton
Hollyglen
ï ï
Woodwick
Deutser
Deutser
Willie
Bucknell
Royal Oaks
Gore
Blades
Rebel
Lakewood
Raymondville
Haywood
Glen Nook
Wiley
Belridge
Rockaway
Kelburn
Colton
Boggess
Lakewood
Wiley
Piedmont
Boggess
Deanna
Lebra
Harmaston
" )13
Parker
"
Chapis
Gager
Gager
Friendly
Farrington
Styling
Haywood
Wiley
Yoe
Parker
Yoe
Lockern
Stonewood
Madera
Nyssa
Haddick
Charlesmont
Burden
Shady
Larry
Wiley
Yoe
Rhobell
Hitchcock
Edgeworth
Hollis
Topping
Folger
£ ¤ 59
Dodson
Peach
Kandarian
Epsom
Downs
Peachtree
Rhobell
Cheeves
Rhobell
Folger
Deanna
Caddo
Hitchcock
Wages
Macha
Topping
Amalie
Marian
Westbrook
Shady
Tidwell Park
Caddo
Rebel
Bigwood
Woodwick
Hillis
Hitchcock
Hitchcock
Downs
Bigwood
Pate
Allwood
ï
Sterlingshire
Haddick
Arvin
Trout
Sterlingshire
Cabot
Matson
Cabot
Maddox
Sterlingshire
" )12
Cabot
Claiborne
Galaxy
"
Mile Post
Land Use
Claiborne
Farragut
Housing Density
Claiborne
Bretshire
Greenwich
Cabot
Hillis
"
YES PREP NORTH FOREST CAMPUS
n n
n n
Liberty
Æ P Healthcare Facility
Developed
0 - 20 Units/Mile
n School
Hallshire
Forest
21 - 100 Units/Mile
I
Locksley
Maddox
Claiborne
Environmental Assessment
KIRBY MIDDLE
Hamlet
Hanford
Locksley
Hillis
Guest
Longhorn Pipeline Reversal
Gallahad
KIPP VOYAGE ACADEMY FOR GIRLS
Tidwell
Wetlands
Maddox
KIPP POLARIS ACADEMY FOR BOYS
Hamlet
Figure 4.1.2-1d
KIPP LEGACY PREPARATORY
n n
n n
ï Park
>100 Units/Mile
Halls Bayou Park (PB2)
Houston Area Land Use
Harris
s Country Club/Golf Course
Agricultural
Pereida
ï
and Housing Density
Mosswood
KIPP NORTH FOREST LOWER
KIPP NORTH FOREST LOWER GIRLS
Wiloak
² ¶ Overnight Lodging
Open Water
Hillis
Shrub/Scrub
Sundown
Count
Count
Seeker
Record
Record
Haddick
Bean
SHEET 4 OF 9
Southwark
Longhorn Pipeline
Barren Land (Rock/Sand/Clay)
Firnat
Prepared By: Atkins/19685
Scale: 1:24,000
Brazoria
Galveston 0 0.5 1
Land Use Source: USGS 2006 NLCD
Pembrook
Teesdale
Snowden
Snowden
Arvin
Fringewood
Job No.: 100019708
Bellingham
Date: Apr 10, 2012
Sunderland
Lanewood
Kelburn
Lynette
Spaulding
Sherbourne
Crofton
Levering
Miles
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Tremont
Kellett
Kellett
Kellett
Sundown
Wayside
Way
Talton
Talton
Roane
Livings
Surry
Leighton
Shreveport
Fawnridge
Homewood
Seeker
Burl
dwick
York
Skinner
Margaret
Trippel
Charles
Cresline
Mayberry
Lakewood
Cockburn
Wellington
Roxella
Exeter
Schilder
Montgomery

<<<PAGE 171>>>

Stuebner Park
Halls Bayou
Hardy
Walston
Luthe
Connorvale
Anice
Reeveston
Sandydale
Charriton
Debeney
Washington
Lincoln
NITSCH EL
Lovington
T C Jester
Fort Royal
McKinley
Big John
Royal Place
Royal Village
Royal Sage
Colter Forest
" )24
"
Jorent
Paradise Cemetery
McCrarey
Cliffmarshall
Bonazzi
Proswimmer
Gloyna
Whitehead
Lonallen
Cadiz
Mallorca
Travelers
Gibraltar
Avila
Piedmont
Hermitage
Estaril
Spur
Manacor
Almenar
Cordoba
Tara
Cordoba
Pine Desert
Jorent
Fallen Pine
Joseph Pine
Drayton
Anthony Pine
Rosslyn
Pine Landing
Logger Pine Trails
Hardy Toll
Regena
Slater
Chrisman
¬ «249
Cora
Isom
Carmilenda
Hill
Erwin
Lone Willow
Collins
Rainy River
Lochland
Mickleton
Hampton
Wavell
Brook
Banch Orhard
Chelsea Elm
Lynda
Stallings
n
n
NTH GRADE
Villa Glen
Red Fir
Lakeworth
Cedar Top
Roaring Point
Cold Lake
Wild Basin
Scenic Green
Storm Creek
d F rest Country
Abinger
Athlone
Alperton
Draco
Sardis
Ashmole
Sardis
Almington
Almington
ks
Mayfield Oaks
Saratoga
Ashmole
Black Locust
Votaw
Ashmole
Elmcrest
T C Jester
Elmcrest
Cherry Forest
Badger Forest
Trappers Forest
Garden City
Vega
Ellington
Haynes
Blue Sky
Orion
Rigel
Venus
Zume
Sunnyhill
Fort Bend
Moorebrook
Sharpton
Lasaber
Woodico
Rosbrook
Midland
Silver Bell
Lilac Mist
Northville
Northville
Northville
Berwyn
Blue Rock
Odessa
Midland
Hambrick
Connorvale
Corvette
Pear
Rose Shadow
Bellville
Village Bell
Daisy Mist
Deer Trail
Korff
Blue Bell
Candytuft
Periwinkle
Ella
Kathi Ann
Debbie
Periwinkle
Marek
Rose Mist
Murley
Blue Bell
Sunnywood
Mading
Moonglow
Memory
Debrah
Berwyn
Angie
Darla
Wallboard
Dorita
§ ¨ ¦45
Shane
¬ «261
Raymac
Turney
Turney
Frazer
Frazer
Hambrick
Dogwood Tree
Holtman
Busch
Dale
Aldine Mail
Hawkins
Nicar
Lorino
Connorvale
Corvette
Walston
Corvette
Isetta
Charriton
Sweeney
Dalewood
Sunwick
Burtcliff
Landfair
Sellers
Stoneshire
Henry
Lillja
Kershaw
Lyngrove
RALPH G GOODMAN
Twin Falls
n
n
Rim Rock
Dormstom
Still River
Helms
Valwood
Mosher
Valley Stream
Westbrook
Helms
Cheswick
Aldsworth
Beaver Bend
Sprads
Helms
Hill
Scoregga
Burford
Barnsley
Glen Shadow
Deer Trail
Beaver Bend
Twinbrooke
Twinbrooke
Mosher
Hidden Valley
Mosher
Hidden Valley
Cobbleshire
Beaver Bend
Beaver Bend
Rainy River
Rocky Mount
Rocky Mountain
Roberts
Robertsvale
Courrege
Woodmoss
Jaycrest
Faber
Pine Vale
Braunston
Twinbrooke
Ella
Ella Boulevard Hike and Bike Trail
Deer Trail
Saddle Rock
Rainy River
Bunzel
ï
Hidden Valley
Saddle Rock
Colendale
Donley
Terrydale
" )23
Rainy River
Rainy River
Saddle Rock
Rutherford
Ivy Spring
Glen Echo
Peach Spring
Peach Spring
Peach Spring
Cobbleshire
Glenbury
Rockcliff
"
Ryton
Bedworth
Brackley
Bisley
Glenhouse
GLF Bank
Cool Spring
Meadowview
Meadowshire
Airway
Lucario
Atlasta
Walla
Gulf Bank
Drayton
Chipping
Cool Spring
Ryton
Burford
Stuebner-Airline Park
Donley
Willow Rock
ï
Nelda
Ver Lee
CARROLL ACADEMY
Nelda
n n
n n
KEEBLE EC/PRE-K CENTER
Lucario
Glennlast
Gina
Rose M H
Fatima Family
Brooklyn
Winter Bay
Brackley
Gulf Bank
Glenda
Deerhurst
Breezeway
Televista
Bauman
Mesquite
" )22 " )
"
Glen Shadow
Bunny Run
Mierianne
Mierianne
Bertrand
Bertrand
" )21
Meadowview
" )20
" )19
Hampton
Tillison
Cottage Gate
Citation
Fashion Hill
Ardley
Diplomat
Old Ledge
Whitecastle
"
Louise
Smart
Rockcliff
Hartwick
Hartwick
"
Castledale
"
Castledale
"
Aldine Park
Havner
Havner
Tarberry
Greyfriar
Horne
Mitchell
Lorna
Ferraro
Mitchell
Turner Place
Castledale
McClosky
Hartwick
Havner
Iroquois
Hartwick
Havner
Dewalt
TEXAS SERENITY ACADEMY
Mitchell
n
n
Karen
Brea Crest
Tina
Fieldworth
Brea Crest
Hardy
Hartwick
Wedgewood
Birchwood
Mooney
Exeter
Havner
Irby
Maxroy
Wheatley
Ellington
Ellington Arrowdale
Knox
Marcolin
Grenshaw
Grenshaw
Whitecastle
Berwyn
Cheswick
Arrowdale
Nellis
Nellis
Airline
Margie
Maria Edna
Mooney
Mooney
Bauman
Sunny
Cardiff
Easter
Easter
Easter
Observatory
Arabelle
Marcolin
Ponnel
Marcolin
Conklin
Randolph
Modley
Hacker
Odet
Avert
Ferguson
Lawn
Sweetwater
Deepgrove
Yale
Doverfield
Carby
Carby
Marjorie
Carver
Sandle
Phillips
Phillips
Ferguson
Sealey
Hanfro
Willow
Double
Prairie View
Candler
South
Marjorie
Williamsdell
Mahalia
Junell
Banjo
Meadowshire
James Franklin
Junell
Enterprise
Saint Clair
Fortune
Virgil
Maxroy
Hanfro
Ringold
De Priest
Fair
Banjo
Stuebner Airline
§ ¨ ¦45
Meadowgrove
Meadowlink
Fred
Charles
Lawn
Prosper
Victory
Meadowyork
Meadowview
Meadowshire
Candler
Vashti
Maack
Werner
Schade
Gracia
Northline
Arnett
Tomlin
Gracia
Bellmar
Deepgrove
Doverfield
Carby
Werner
Vashti
Alfano
Dewville
Echo Brook
John Alber
Werner
Wardmont
Foxridge
Wardmont
Hopper
Hopper
Carby
Candler
Cromwell
Cardiff
Kitchener
Hardy Toll
Canino
Chamberlain
Van Ness
Meadowfair
Nordling
Gurney
Roselane
Emma Lou
Lucky
Hezekiah
Charlie
Dyer
Bradmar
Burt
Mount
Little York
Star
Cora
Sandle
Knox
Virgil
Maxroy
Wall
Domino
Frail
"
Mile Post
Land Use
Housing Density
Liberty
Æ P Healthcare Facility
Developed
0 - 20 Units/Mile
n School
Forest
21 - 100 Units/Mile
Meadowgreen
Meadowpass
Anchick
Aggie
Clairy
Paseo Arboles
Wilkie
Marnie
John Alber
Roselane
Mazzola
Biscayne
Frels
O Donnell
Bannister
Kearny
Benbrook
I
Downey
Winfrey
Rubenstein
Fairday
Faircrest
Cardiff
McGallion
Woodcourt
Downey
Carla
Art
Bauman
Cliffside
York
Cliffside
Courtshire
Parkstone
Oak Glen
Benbrook
Environmental Assessment
Longhorn Pipeline Reversal
ï Park
Wetlands
Figure 4.1.2-1e
Michulka
>100 Units/Mile
Houston Area Land Use
Harris
s Country Club/Golf Course
Agricultural
² ¶ Overnight Lodging
Open Water
and Housing Density
Shrub/Scrub
SHEET 5 OF 9
Longhorn Pipeline
Brazoria
Barren Land (Rock/Sand/Clay)
Galveston 0 0.5 1
Scale: 1:24,000
Hardy
Land Use Source: USGS 2006 NLCD
Date: Apr 10, 2012
Miles
Hardy Toll
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Hardy Toll
Irvington
Hardy
Dewalt
Ellington
Tower
Beckley
Redrock
Garfield
Orebo
Cora
Beckley
Burg
Hezekiah
Esther
Conklin
Sunny
Norlinda
Rusty
July
Exeter
Lone Oak
Grimes
Easter
Lucky
Wall
Morehouse
Montgomery
Waller
Prepared By: Atkins/19685
Job No.: 100019708
Skinn
Margaret
Exeter
Welling
Roxella
Exeter
S

<<<PAGE 172>>>

ch Park
Sam H
Little Branch
Sam
de
Beltway 8
Willow Trace
GLEASON EL
Castle
n
n
ge Park
" )30
Uppercove
"
Willacy
Bexar
Bridge Park
Eastcove
Eaglecove
Backcove
m
Upshur
Glascock
Westcove
Westwillow
Bearcove
Honolulu
Welwyn
nbury
Tahoe
Clevedon
Chichester
Sierra
Yampa
Glamorgan
Mauna Loa
Ashburton
Argentina
lwood
Leeds
Ginger
Colwyn
Zilonis
Hamilton
Equador
Shanghai
Australia
Clark Henry Park
ï
Equador
Oakland
Maple Leaf
Concord
Cornett
Plum Ridge
Red Maple
Silver Maple
Sugar Maple
Shimmering Maple
Rustling Maple
Zaka
Railhead
Golden Spike
West
Old Foltin
Elsie
Reid Lake
Windfern
Prairie
Taub
Kay
Barren
Old Country
Greenfield
Moorpark
Comet
Birnam Garden
Norkey
Chippewa
Fennemore
Killough
Mosielee
Bobbie
Euclaire
Sara Jo
Romona
Lane
Paddock Brook
Banch Orhard
Chelsea Elm
Killough
Proctor
Killough
¬ «249
Youpon
Montgomery
Warren
Regal
Bent Oak
Grimes
Waller
Chicago Bridge and Iron
Round Bank
Wayward
Upperbrook
Sunbonnet
Bridgefoot
Parasol
Redcliff
Rivercross
Lamppost
Bova
Little River
Old Meadow
Sunbonnet
Twin Lamps
Church Light
Blacksmith
Tiltrum
West
Riverside Walk
Smokey
Daycoach
Bridgefoot
Parasol
Carriage Creek
Snowbank
Pebbledowne
Sorrel
Fur Market
Gage
Harmony
Leather Market
Apothecary
Drum Roll
Fur Market
Leather Market
Big Creek
Spindle
Zuinn
Spindle
Everhart
Gessner
Desert Cloud
Creek Vine
Westbank
Westbank
Getty
Westbank
Westbank
Fort Ro
" )29
Galayda
Breen
Washington
"
Village
McKinley
Big John
Laurel
Walnut Brook
Brookside Forest
Laurel
Payette
Metrodale
Fairbloom
" )28
Pecan Glen
Waynemer
Mayside
Rodney Ray
"
Friobend
Woodland Oaks
Gum Valley
Lincoln
Oak Pines
Lori
Lawncliff
Windfern Forest
Kelsey Meadows
Terrace
Terrace Brook
Donys
Donys
REED EL
Whisper Pointcir
Preston Pine
Bayou Crest
" )27
Mount Houston
Winnsboro
Downwood Forest
Fair Forest
Fair Forest
Grand Haven
Mixie
"
Ashland Forest
Saratoga Forest
Arlington Forest
Parkhill Forest
Antoine
Fairview Forest
Fairview Forest
Longforest
Trailridge Forest
NITSCH EL
Shadow Gate
Royal Village
Royal P
Rocky
Rocky
Rocky
n
n
Wind Free
Windell
Windoak
Windy Oaks
Partlow
Tessa
Mauna Loa
Tami Renee
Crystral Moon
Redland Woods
Julie
Ince N
Loren
Gray Jay
Baskove
Cheshire Park
" )26
Bold Forest
KLEIN INT
Bird Forest
n n
n n
" )25
Lovington
Colter Forest
Royal Sa
Windfall
Wind Cave
Windy Trail
Windlea
Spring Wind
Prairie Wind
Longshire
"
Terrace Wind
Country Wind
Silvan Wind
Tiger
Pasha
Trica
Cher
Debbie Gay
"
Cienna
Evergreen Terrace
Wildforest
Klein Circle
Cherie Crest
T C Jester
Bo Jack
Summertree
Brook Trail
Julie
Ince
Loren
Baskove
West Mount Houston Park
Wind Forest
Mauna Loa
Letica
Merna
Oratorio
Ivan Reid
Gatehouse
Holmwood
Spring Fern
n
n
ï
Winehill
EILAND EL
Whitter Forest
Cathedral Grove
Ogden Forest
Victoria Forest
" )24
Harper Forest
Windsor Forest
Streamside
"
Beltway 8
Symphonic
Wilson Reid
Country View
Canyon Forest
Windy Creek
Clarion
Sinfonia
Ensemble
Melissa Lea
Hillbarn
Sonata
Terra Cotta
Fall Glen
Log View
Log View
Rolling Mill
Maywood Forest
Regency
Moonlight Forest
Jorent
Greenhill Forest
Windy Acres
Wind Lawn
Philippine
Stoneyway
Adagio
Rythem
Cantata
Brahms
Woodwind Lakes
Andante
Ivan Reid
Ridge
Ridge
Golden Chord
Trail Blazer
Woodland Oaks
Trailside
Log Hollow
Ince
Log Hollow
Copperwood
Hannon
Aspen Wood
Log Hollow
Opus
Sawmill
Serenade
Big Oak Trail
Yellow Pine
Branchwood
Sawmill
Yellow Pine
Inwood Hollow
Briarwood Forest
Hibernia
Casablanca
Milda
Barbados
Prairie Mist
Tocatta
Split Pine
Lumber Jack
Kindletree
Lumber Jack
Pine Moss
Brabant
Barbarella
Inwood West
Inwood Shadows
Gallant Forest
Elkwood Forest
Caruso Forest
Cactus Forest
Bihia Forest
Bridge Forest
Paradise Cemetery
Burger
Rhapsody
Concerto
Melody
Western Oak
Sweetgum Trace
Woodsman
Woodsman
Stoner
Warren
Bayou Forest
Pincay Oaks
Cadenza
Prelude
Woodsman
Vera Jean
Enchanted Forest
Knightwood Forest
McCrarey
Streamside
Cliffmarshall
Bonazzi
Proswimmer
Gloyna
Whitehead
Lonallen
Stallings
Oak Fern
Rolling Fork
k
r
Old Trail
Battlepine
Fo
Allegro
Western Trail
Battlepine
ollin g
Hannon
Battlewood
Jasmine Arbor
Gailey
R
Rolling Rock
Winding Meadow
Flair Oaks
Kell
Split Oak
Gulf Bank
Pardue
Streamside
Congo
Wind Side
Brookriver
Lake
Wind Trail
Wind Dale
Bart
Storm Wood
Wood Bluff
Woodland West
Split Oak
Eblen
Jaywood
Haven
Rocktree
Park Heath
Battlecreek
Salge
Swonke
Summer Laurel
Pecan Wood
Green Falls
Avenue D
Woodoak
Deadwood
Battleoak Abinger
Zimmermann
n
n
EISENHOWER NINTH GRADE
Gar
River Fern
Avenue E
GLF Bank
Pierrepont
Shady Vale
Hannon
Kindletree
Majestic Oaks
Houston Rosslyn
Pinole Forest
Villa Glen
Woodland Forest
Donwhite
EISENHOWER SENIOR H S
n
n
Red Fir
Lakeworth
Cedar Top
Vega
Previn
Arncliffe
Streamside
White Oak
Wind Stream
Avenue A
Hanus
Deanwood
Greenway Forest
Council Grove
Roaring Point
Cold Lake
Avenue G
Avenue I
Scenic Green
Blue Sk
Wood Bluff
Hollister
Garsee
Jaywood
Bayou Forest
Green Lawn
Haynes
Bateman
Challie
Turfwood
Blackjack
Moss Glenn
Wild Basin
Orion
Bent Oak
Ertel
Holmsley
Coaldale
Fairbanks N Houston
Kellwood
Vernwood
Vanwood
Vernwood
Wenwood
Mosewood
Jadewood
Long Leaf
Fairwood
Council Grove
Maple Tree
White Fir
Mosewood
Moss Glenn
V
o
g
Bent Bough
e
l
Shady Vale
C
Vinetree
Nook
Long Barrel
Woodland Trails
Loren
Breezeway
Gauguin
r
Beau Geste
Water Leaf
Maple Tree
e
e
k
Inwood Forest Country
Storm Creek
Rigel
Athlone
Alperton
Draco
Ashmole
Emmott
Wood Downe
Shady Mill
Williams
Guywood
Ertel
Lou Anna
Bond
Vinetree
Whiteoak Bayou
Shady Corners
Alejo
Bayou Oaks
Sardis
Sardis
Woodlong
Green Terrace
Lawn
Long Creek
Almington
Bent Bough
Almington
Mayfield Oaks
Mayfield Oaks
Lou Anna
Keough
San Antonio
Wood Bluff
Wood Orchard
Gauguin
Wood Canyon
Nook
Ince
Shady Grove
Hidden Arbor
Lautrec
Shady Grove
Deirdre Anne
Saratoga
Saratoga
Ashmole
Houston
Shady Arbor
£ ¤ 290
Woodland West
Machala
Loren
Langfield
Landwood
Bent Bough
Shady Arbor
Fairbanks White Oak
Woodfern
Arbor Wood
French Chateau
Lemon Tree
Stonegate
Stone Brook
Silver Chalice
Alabonson
Darkwood
Brush Wood
Votaw
Zume
Oaknut
Little York
Hahl
Oakwood
Brook Stone
Oakwood Forest
Chateau Forest
Oak Bough
Bent Branch
Deep Forest
Black Locust
Black Locust
Littleberry
Vogel
Ashmole
Birchcroft
Elmcrest
Elmcrest
Cole Creek
Flintlock
Guhn
Oakwood Bend
Hollister
Twisting Vine
Brookfir
Wagonwheel
Tall Pines
Maple Hill
T C Jester
Caracara
Scaup
Stonefir
Tall Willow
King Post
Cherry Forest
Athlone
Badger Forest
Trappers Forest
"
Mile Post
Land Use
Montgomery
Housing Density
Liberty
Æ P Healthcare Facility
Developed
0 - 20 Units/Mile
n School
Forest
21 - 100 Units/Mile
I
Environmental Assessment
Longhorn Pipeline Reversal
ï Park
Wetlands
Figure 4.1.2-1f
>100 Units/Mile
Houston Area Land Use
Harris
s Country Club/Golf Course
Agricultural
and Housing Density
² ¶ Overnight Lodging
Open Water
SHEET 6 OF 9
Shrub/Scrub
Fort Bend
Longhorn Pipeline
Brazoria
Barren Land (Rock/Sand/Clay)
Galveston 0 0.5 1
Land Use Source: USGS 2006 NLCD
Miles
Battleoak
Battle Plains
GLF Bank
Gulf Bank
Empire Central
Regal
Brookhollow West
Prepared By: Atkins/19685
Scale: 1:24,000
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd

<<<PAGE 173>>>

Berwick
Berwick
Whithorn
Splintered Oak
Wimbledon Oaks
Overton
Fallsbridge
Turnbridge
Azalea Creek
Apple Forest
Birch Falls
Hillside Glen
Carriage Lake
Rabbit Oak
Tara Oak
Belmont
Piney Oaks
Oak Acres
Pecan Oak
Oak Limb
Pear Oak
Den Oak
White Cliff
Wolsley
Wortham Grove
Durbridge Trail
Bretford
Bainbridge
Wortham
£ ¤ 290
Wortham Center Dr
Village Trail
Wortham
Park Sam Houston
Wolfe
Fox
Highway 6
² ¶
" )34
"
"
SATSUMA
Cicero
HL&P Satsuma Station
Lure
Tarton Way
Capshaw
Brookhaven Park
Crossridge
Kilrenny
Maple Leaf
Red Maple
Silver Maple
Sugar Maple
Shimmering Maple
Oakland
Concord
Tifco
Greenwater
Hammond
Steepletop
Bridgedown
Crescent Moon
Buffalo Bend
Staghill
Lazy Meadows
Skybird
Walnut Glen
Perry
Rippling Fields
Northwind
Waving Fields
Springsong
W
hi
t
e
o
Spring Harvest
Waving Fields
Sky Bird
Golden Grain
Broken Sky
Walnut Glen
Twilight Moon
Walnut Glen
Strawgrass
Willowmist
B
a k
Indian Vista
Hidden Moon
Gusty Winds
Fairstone
Rustling Winds
Walnut Glen
Harvest Sun
Fallbrook
Twila Springs
Key Biscayne
Springland
a
Twilight Moon
Mantle
y
o
u
Foxrow
Berry Tree
Port Erroll
Mission Arch
Sunrise
Birdhill
b
Lynette Falls
Hedge Way
Jones
Barr Lake
White Oak Falls
May Showers
Newport Shore
High Bridge
Staghill
White Oak Falls
Sand Dollar
Lazy Lagoon
Ripple Lake
Churchill Way
Indian Ledge
White Oak Bend
Autumn Meadow
Goodspring
Redoak Pass
Encino Cove
Elm Meadow
Pony Express
Willow Crossing
Laurel Branch
Hickory Trail
Sable Trail
Crayford
Chiselhurst
White Falls
Hambleton
Bayou Trail
Burntfork
Elm Bluff
Legacy Park
Kirkton
Mission Falls
FM 1960
Sunset Lake
ckerton
Drifting Oaks
CYPRESS FALLS H S
Bestin
Coleburn
Tuckerton
n
n
Miramar Shores
Jockey Club
Crayford
Trail Ridge
Creighton
White Oak Trail
Elm Knoll
Elk Point
Tablerock
Villa Verde
Cedaredge
Rapid Falls
Totem
Storm Meadow
Red Wolf
Tallowbend
Bowmore
Orison
Prestige
" )36
Stampede Pass
Crossroads Park
Caritas
Speyburn
CYPRESS MONTESSORI
"
n
" )35
Brants Way
Haven Crossing
Hedgedown
Hedgedown
Saddlehorn
Wayward Wind
Hanging Moss
Stableway
Gold Cup
Wayward Wind
Prospect Hill
Prospect Hill
Cedaredge
Summer Run
Chiselhurst
Canterhurst
Paddock
Hedgegate
Bent Spur
Horseshoe Bend
Horseshoe Bend
Territory
Cabin Creek
Branch Park
Sam Houston
Sam Houston
bergreen
Newburgh
Copper Branch
Point Park
"
Knights
Garett Green
Paddock Way
Overmead
Yorkshire Oaks
Autumn Chase
Meadowchase
reen Castle
Guiness
Shango
Point Northwest
Swandale
Autumn Sky
Holland Field
Withers Way
Top Gallant
Ash Fork
Round Up
Sand Pass
Pale Star
Arrowgrass
Little Branch
Thunderhead
Spotted Horse
Goldenglade
Autumn Way
Aberdeen Oaks
Bonnyview
Sweetrose
Sherina Park
Rosehearty
Blaire
Tall
Aberdeen Trails
Poplar
Foster Springs
¬ «6
Apple Mill
Red Hill
Baber
Shapiro Springs
Secretariat
Oldenburg
Savile
Cleveland Bay
Yearling
Steeplecrest
Ranchstone
Ash Fork
Poynes
Bent Spur
Trading Post
Linecamp
Silver City
Territory
Cabin Creek
Green Valley
Beltway 8
Cade
Kentwater
Dapple
Goldfield
Arrowgrass
Trailing Moss
Winter Run
Jamie Lee
Spring
Jamie Lee
Meadow
Tysor Park
CYPRESS FALLS H S
Point Northwest
n
n
" )33
West
Flaxen
Trailblazer
Kleberg Place
Fetlock
Winchester Village
Big Willow
n Sands
Oak Mountain
Laurel Trails
Sunny Ridge
Canton Park
Grove Park
"
Barnhart
Thoroughbred
Great Plains
Villa
Willow Trace
Wagon Trail
Sparkling Springs
Spring Green
Pine Falls
Oak Mountain
Spruce Mill
Timbercraft
Greenleaf Lake
Canton Park
Point Park
Point Six
Saville
Castlebridge
Majestic Prince
Gold Point
" )32
Bent Spur
Gold Point
Rock Pass
COOK MIDDLE
Willowlake
Tepee
Cornett
Lake Crystal
Pebble Lake
Saddle
Common Crest
Brightbrook
Seattle Slew
"
Prairie Hawk
Hondo Hill
n
n
Villa
Stoney Lake
lum Lake
Lake Crystal
Swan Creek
Highfield
Pearl Lake
Chapelbrook
Trailbrook
Meadow Village
Pleasantbrook
Castlegate
Chazenwood
Cutting Horse
Steeplepark
" )31
Restover
Sandtown
Slate Stone
Stone Porch
Station
Windriver
Karter
Dude
"
Wheatland
Plu
GLEASON EL
Misty Trail
n
SANDCASTLE MONTESSORI ACADEMY BANG EL
Westplain
Hoot Owl
Skipping Stone
Stone Castle
n
n
Elmbank
Hot Springs
Majesticbrook
Westfair East
n n
n n
Castlebridge
Wilbarger
Iron
Pinyon Creek
Ferncliff
FIEST EL
Lakedale
Town Creek
Silent Cedars
Red Cloud
" )30
Windy Cove
Westland East
Copperbrook
Eldridge
Wendigo
Sand Hills
Bent Spur
Copperdale
Minturn
Pearl
Crazy Horse
Ballinger
Dallam
Kinslowe
Refugio
Therrell
Palacios
Willowbridge Park
Uppercove
"
Willacy
eetwater Creek
Silver Fir
Riverglade
Sunny Ridge
Ivy Bridge
Willow River
Clover Gardens
Willancy
Pebble Beach
Shindler
Bexar
Bridge Park
Eastcove
Eaglecove
Backcove
Viney Creek
Forest Trails
LABAY MIDDLE
Chetland Place
Sunbury
Jackrabbit
Wescan
Steeple Way
Ruffian
Cherry Hills
Oakmont
ory Cove
n
n
LEADING STARS MONTESSORI
Brannon Field
Waylord
Wyndham Village
Brenham
Ricaby
Tarrant
Pearsall
Upshur
Glascock
Westcove
Westwillow
Ivy Falls
Bearcove
Parmer
Villa Lake
n
Big sur
New Hastings
Tustin
Carmel
Makaha
Laguna
Honolulu
Kevindale
Swan Hollow
Koester
Golf Course
Rauch
Welwyn
Clevedon
Haven
Shady Palms
Knolls Lodge
s
ï
H o r
e
Park
pe n
C
Inverrary
Rio Pinar
Oceanside
r
Signal Creek
e e
k
Alamar
Royal Birkdale
Owens
Chateau Point
Sonoma Oak
Musgrove
s
Ingle Oak
Taylor
Rio Grande
Achgill
Kube
Tenbury
Tahoe
Hanley
Lewis
Senate
Hawaii
Chichester
Garden Hill
Brook Springs
Service Center
Parkway
Smith
Sierra
Sandalfoot
Silver Sands
Trophy Club
Vista Mar
Capri
Pickford Knolls
Traders Village
Verde Mar
Fairview
Village Green
Yampa
Crawford
Glamorgan
Club Lake
Tahoe
Chimney Sweep
Carlsbad
Epernay
Capri
Mauna Loa
Creek Glen
Muirfield
Sugar Mill
Senate
Windy Glen
¬ «6
Knoll Lake
Hearthstone Country Club
Virginia Water
Capri
Argentina
Spyglass
Flagstone
Andiron
Kite Hill
Stone Pine
Weatherhill
Stamen
Shaddock
Log Cradle
Millbrae
Pepperbrook
Pebblewalk
Harms
Village
Ashburton
Wall
Lemma
Tallow
£ ¤ 290
Elwood
Leeds
Vista Oro
Sue
s
Blazey
Vista Brook
Wright
De Lozier
Ginger
Colwyn
Lakeview Haven
Ridge Park
Mesa Gardens
Echo Lodge
Pleasant Ridge
Zilonis
Foxton Place
Hollow Ridge
Broken Ridge
Betanna
Elmont
Bull Creek
Beechmoor
Huffmeister
Saint Helier
Cart Gate
Firebrick
Suddley Castle
Cornwall
Hamilton
Millbrae
Starbridge
Sugar Ridge
Clear Valley
Benwich
El Miranda
Trailside
Creek Crest
Holly Court
Tunbury
Muirwood
Stone Pine
Weatherhill
Breccia
Andiron
Fieldstone
Cornwall Bridge
Chaston
Jersey
Juneau
Equador
Gateridge
Noblecrest
Acapulco
Tiny
Carlsbad
Shanghai
Clark Henry Park
rook Knoll
Palisades Heights
Valley Creek
Grimes
Glen Chase
Cherry Park
Charles
Lakeview
Gendley
Congo
Australia
ï
River Garden
Montgomery
Willow Bridge
Indian Quail
"
Land Use
Runbell
Quail Field
Mile Post
Housing Density
Liberty
Æ P Healthcare Facility
Halfpenny
Winding Walk
Developed
0 - 20 Units/Mile
n School
Islandwoods
Forest
21 - 100 Units/Mile
I
Equador
Environmental Assessment
Longhorn Pipeline Reversal
Waller
Figure 4.1.2-1g
Fairway Square
ï Park
Wetlands
>100 Units/Mile
GLF Bank
Houston Area Land Use
Moss Boulder
Gulf Bank
Empire Central
Harris
Shining Sumac
Old Hearth
Madison
Shasta
s Country Club/Golf Course
Jasmine
Agricultural
and Housing Density
Regal
Bent Oak
² ¶ Overnight Lodging
Open Water
Wicker
SHEET 7 OF 9
Weiman
Crimson
Shrub/Scrub
Fort Bend
Falmouth
Brazoria
Galveston 0 0.5 1
Weeping Cedar
Cleft Stone
Hearthstone Place
Longhorn Pipeline
Scale: 1:24,000
Barren Land (Rock/Sand/Clay)
Job No.: 100019708
Date: Apr 10, 2012
Willow Hearth
Gorham
Langham
Bellport
Montauk
Mulberry Meadows
Addicks Satsuma
Land Use Source: USGS 2006 NLCD
Hertford Park
Miles
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Regal
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Brookhollow West
aldron
llfield Manor
Covesville
Ringfield
Felgate Creek
aurel
Windfall
Beltway 8
Brookside Forest
Payette
Oak Pines
Windfern Fore
Wind Free
Windell
Windoak
Wind Cave
Windy Oaks
Windlea
Wind Forest
M
W
Wind Law
Philippine
Prepared By: Atkins/19685
Smithstone

<<<PAGE 174>>>

I
Harris
Fort Bend
Waller
Montgomery
Liberty
Brazoria
Grimes
Galveston 0 0.5 1
Miles
s
ï
ï
ï
n n
n LEADING STARS MONTESSORI
LABAY MIDDLE
Park
Cullen Park (Lease)
Hearthstone Country Club
FM 529
Jackrabbit
Forest Heights
Greenhouse
Gummert
Sandalfoot
Coventry Park
Silver Sky
Shangrila
Judyleigh
Kite Hill
Glenledi
Blazey
River Garden
Elmont
Lerwick
Sommerall
Lyford
Royal Gardens
Rebel Yell
Lobo
Wimbledon
Kentwick
Club Lake
Santrey
Wild Willow
Ridge Park
Huffmeister
Queenston
Alden
Glenpatti
Laurel
Macleish
Bouldgreen
Vanlynn
Allerton
Northhagen
Inverrary
Girnigoe
Muirfield
Creek
River Sage
Livery
Rainbow Lake
Glenstein
Holly Forest
Ridgeberry
Park Falls
Glenray
Tilley
Garden Manor
Addicks Satsuma
Alisa
Sandelford
Karenbeth
Grampin
Weiman
Carly Park
Windsong
Ashton
Flint Hill
Glenmorris
Cairnleigh
Little York
Baxter
Liner
Daylight
Oter Tril
Bliss
Forest Cedars
Cherry Park
Greenwood Point
Hamilwood
Loch Bruceray
Renata
Sunlight
Creek Village
W
Crystal Point
Millshire
Dennington
Yaupon Mist
Rockbend
Falmouth
Dunnethead
Sweetwater Creek
Forest Trails
Skylight
Wheatbridge
Newbury
Loch Langham
River Rock
Village Lake
Catarina
Dew Mist
Windstone
Bridoon
Langham Way
Haven Creek
Austinville
Fox Springs
Little Pine
Longenbaugh
s
Broadelm
Mountain Dale
Granite Ridge
Berkshire Manor
Yaupon Ranch
Glenmark
Lakeview Haven
Signal Creek
Cart Gate
Glenwolf
Rustic Lake
Benwich
Carbridge
opper Lakes
Hamstead Park
Headland
Rexton
Autumn Thistle
River Pines
Virginia Water
Wimberly Park
Co
Mansor
Smithsone
Willow River
Caledonia
Anna Green
Tahoka Springs
Fieldglen
Andiron
Echo Lodge
Bryngrove
Verde Mar
Smithstone
Halfpenny
Chetland Place
Fort Sumter
Ashley Grove
Barton Oaks
Nordway
Gable Oak
Shining Sumac
Brooknoll
Swan Valley
Tunbury
Tobacco
El Miranda
Breccia
Andalusian
Pine Cliff
Rum River
Barker
McCormick
Willancy
Northfalk
Davenway
Knoll Lake
Margeson
Clerkenwell
Tinker
Haughland
Ringfield
Howland
Lippizaner
Nancet
Skybright
Stamen
Canaan Bridge
Glen Chase
Bright Falls
Cross Falls
Knolls Lodge
Grand Colony
Mesa Gardens
Saxon
Masonridge
Fairgrove Park
Western Pass
Kilwinning
Salinas
Prairie Village
Crossway
Scotchwood
Porterway
Rumford
Hollyhock
Autumn Laurel
Odinglen
Bosley
Poplar Hill
Boulder Oaks
Cape Hatteras
Crakston
Garnercrest
Bear Springs
Azalea Valley
Spinney Lane
Fieldstone
Highland Farms
Colefield
Anchor
Creek Glen
Gallant Glen
Lost Fable
Clairson
Remington Grove
Applecross
Starbridge
Dusty Creek
Alamar
River Bottom
Hidden Oaks
Saddle Bred
Willow Moss
Terrace Park
Pattiglen
Deep South
Hickory Point
Mossy Ridge
Clear Valley
Rigdale
Larkspur Hills
Saxon Hollow
Horsepen Bayou
Paddock Bend
Cross Junction
Neston
Brenwood Glen
Creek Crest
Holly Court
Red Wolf
Sky Blue
Sandy Hollow
Brenwood
Wellers
Newly
Flagstone
Stoney Haven
Stone Pine
Galleon Field
Gable
Geral
Grackle
Goodman
Montauk
Painted Trail
Shaddock
Beechmoor
Crimson
Barkerview
Great Glen
Oat Mill
Creekshore
Stonewater
Hazel Cove
James River
Terra Canyon
Yorkpoint
Sisterdale
Holly Green
Gaelicglen
Arbor Creek
Winding Walk
Calm
Poppy Trails
Lexi
Heathridge
Highland Canyon
Rolff
Hudson Oaks
Autumn Flowers
Cairns
Sonnet Glen
Forest Dew
Legacy Pines
Billington
Indian Desert
Hatfield Glen
Mountain Pines
Willow Bluff
Clover Gardens
Britterige
Marston Park
Hayman
Valerian
Eagle Ridge
Heather Hollow
Maplemont
Garden Hill
Langham
Laguna Springs
Dunsley
Bull Creek
Winston Hill
Vistaglen
Coventry Oaks
Golden Ridge
High Village
M
Scenic Lakes
Covesville
Dogwood Falls
Rio Pinar
Springville
Copinsay
Stardust
Santolina
Hollow Field
Magazine Bradford Colony
Creekpoint
Boysenberry
Sprey
Cotton Gin
Felgate Creek
Chateau Point
Pebbleglen
Seaton
Crested Hill
Fern Basin
Weeping Cedar
Crestbury
Old Greenhouse
Bluebottle
Meadow Heights
Northland
Pagehurst
Willow Hearth
Beckland
Runbell
Bishop Knoll
Chantalle
Prairie Creek
Somersworth
Cairngorm
ch
Sandisfield
Brannon Field
Harrow
Chatham Woods
Hilton Hollow
Autumn Hills
Quail Field
Autumn Trails
Clan MacIntosh
Copper Shore
Drewlaine Fields
Wolf Hollow
Millridge
Willow Bridge
West Gate Park
Dillsbury
Fuller
Westminster Village
Viney Creek
Heathmoor
Pickford Knolls
Connemara
Silver Sands
Aspen Trails
Northern Star
Flemington
Yucca Field
Laurel Trail
Clan MacGregor
Smoke House
New Hastings
Billinsgate
Sundance Trail
Leamington
Shasta
Forest Dawn
Valley Creek
Mulberry Meadows
Lapis Meadow
Praire Bluff
Park Hollow
Bethan Glen
Almond Springs
Oceanside
Crystalglen
Langhamwood
Basswood Dale
Pago
Silver Fir
Tuscola
Timber Mist
Bishops Glen
Wemyss Bay
Maple Brook
Leedswell
Hidden Shadow
Georgetown Colony
Trophy Club
Sutton Falls
Burlcreek
Valemist
Wilmington Park
Regina
W
Taymouth
Hopeview
Kemble Creek
Emerald Brair
Clintridge
Amber
Bellport
Vinemont
Cherry
Old Tybee
Destiny Park
Big sur
Bowtrail
W
Hearthstone Place
Cornwall Bridge
Shady Manor
Packwood
Misty Dale
Anthurium
Catherwood
Dew Drop
Rustling Aspen
Vista Mar
Raven Creek
Weatherhill
Cleft Stone
Highbury
Glenhagen
Moss Boulder
Society
Haley Falls
Feather Springs
Gorham
Bubbling Brooks
Spruce Point
Waverly Grove
Berry Branch
Hertford Park
Crestford Park
Slippery Elm
Stonepath
Chimneystone
Sheffield Bend
Broken Stone
Briar Moss
eef
Kransburg Ranch
Plaistow
Sonoma Oak
Brenwood Manor
Madison
Eden Falls
Mill Village
Kenmark
Coventry
Bradworthy
Ivory Crossing
Chatham Springs
Britford
Yorkglen
Palisades Heights
Desert Moon
Sugar Mill
Stoneygrove
Dempley
April Glen
Redwicke
Tustin
Bellfield Manor
Billineys Park
Millbrae
Cliffsage
Cairngrove
Fairway Square
Winter Stone
Graftondale
Appaloosa
High Knoll
Sentry Park
Gettysburg Valley
Gillian Park
Cabots Landing
Blueberry Hill
Juniper Crossing
Betonica
Stonerun
Evergrin Rose
Lilac Vale
Lipps
Rockstone
Concho Springs
Magnolia Shadows
Old Glory
Vermilton
Dusty Terrace
Cashel Park
Searston
Ivy Trail
Belleshire
Crescent Canyon
Binalong
Twin Creek
Timber Creek Place
Islandwoods
Brookhollow Oaks
Rush Trace
Carpet Bagger
Cricketbriar
Carlisle Park
Gleneviss
Dinner Creek
Ferry Boat
Lone Meadow
Augusta Pine
Maple Point
Sparks Valley
Shelbourne Park
Shining Leaf
Jasmine
Pheasant Grove
Bellwick
Old Hearth
Royal Birkdale
American Holly
Yorktown Colony
Summer Dew
Service Center
Foxton Place
Fleethaven
Silver Ash
Angel Falls
Suddley Castle
Fernchase
Carshalton
Afton Ridge
Trafalgar
Prarie Fire
Sun Terrace
Hollow Cove
Sweno
Maple Mist
Dusty Yaupon
Northway
Sage Manor
Great Elms
Postwick
Swan Hollow
Colony Point
Roehampton
Yorktown Meadow
Plumtree Forest
Redwoo Manor
Blairstone
Pebble Falls
Brockland
Central Falls
Leaf Point
Heather Heights
Driftwood Springs
Crown Meadow
Dove Field
Narcissus Brook
Barker Village
Misty Fern
Muirwood
Spruce Haven
Morning Rose
Brockman
Pennworth
Samsarah
Danbury Run
Glenbank
Grand Cypress
Towerglen
Sweeney Park
Ivy Bridge
Willow Cove
Cannon
Ridgegrove
Delta Queen
Makaha
Portmanshire
Fern Hollow
Quiet Dawn
Kintyre Point
Wildwood Brook
Langham Mist
Hayward
Summer Mist
Shady Cypress
Misty Loch
Brooktondale
Windy Glen
Tall Maple
Millstead
Spyglass
Hickory Cove
Brenwood Park
Grand Terrace
Oak Park Bend
Evergreen Brook
Stone
Carmel
M
Hollow Ridge
Lolly
River Pointe
Cozy Terrace
Pleasant Ridge
Rowena
Ingle Oak
Oleander Ridge
Cheshire Bend
Betanna
Haven Point
Waldron
Eastwood
Westcliffe
Northcairn
Cozy Cabbin
Plantation Grove
Rusting Willow
Autumn Manor
Crestbrook Manor
Villa Lake
Tawny Bluff
Brookhollow Pine
Allenwick
Silver Rock
View Park
Grayton
Preston Springs
Glenbrook Knoll
Mockingbird Valley
Bear Meadow
Poppy Grove
Stonechase
Indian Quail
Kadabra
Windgate
Hillwood
Peach Forest
Westbury
Savannah Pines
Strathmore Place
Broken Ridge
Scarlet Oak
Riverglade
Plantation Tree
Morrisglen
Travis Point
Longdale
Golden Pond
Waylord
Brook Springs
Caldermont
Dewcrest
Stratwood
Morningshine
Rittenberg
Cashel Point
Cedar Point
Blushing Pear
Barley Mill
Langbrook
Holly Falls
Wicker
Willowland
Black Gap
Arbor Park
Westhall
Pleasant Lily
Sand Hill Glen
Tree Lark
Belleshire Glen
Shady Palms
Dawson Mill
Elm Point
Wisteria Ridge
Pipingwood
Millbrae
Autumn Hills
Weatherhill
Clan MacIntosh
Grackle
Sunny Ridge
Sky Blue
Concord
Dew Drop
Wild Willow
Poppy Trails
Somersworth
Sky Blue
Ash
Wild Willow
Glenpatti
Clan MacGregor
Grampin
Sunbury
Stone Pine
Capri
Stonerun
Sonnet Glen
Fieldglen
Sugar Ridge
Goodman
Applecross
Macleish
Maplemont
Kilwinning
Rigdale
Prairie Village
Greenhouse
Langham
Andiron
Langham
Summer Dew
Oak Glen
Harrow
Carbridge
Livery
Grackle
York
Spring
Forest Trails
Glenmark
Battlecreek
Carbridge
Laguna
Maplemont
Autumn Hills
Brenwood
Trailside
Owens
Langham
¬ «6
¬ «6
Langham Creek
Dinner Creek
H
o r
s
e
pe
n
C
r
e
e
k
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-1h
Houston Area Land Use
and Housing Density
Prepared By: Atkins/19685
Job No.: 100019708
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Scale: 1:24,000
Date: Apr 10, 2012
Land Use Source: USGS 2006 NLCD
SHEET 8 OF 9
"
Mile Post
Æ P Healthcare Facility
n School
ï Park
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Land Use
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile

<<<PAGE 175>>>

Village
Kolbe
Laura
£ ¤ 290
Telge
Berwick
" )42
"
Berwick
" )41
"
Fry
Whithorn
Grimes
Montgomery
Waller
Harris
Fort Bend
Cypress Villa
Hilltop Park
Jadestone Creek
Barker Gate
Barket View
Woodwind Shadows
Mystic Grove
Bandit Trail
Cactus Point
Muleshoe
Trail Brook
Riata Ranch
Desert
Stoney Falls
Ruby Canyon
Stone Prairie
Lake Riata
Belwood Park
Laguna Trail
Sunset Bluff
Miners
Pampass
Canyon Oak
Stone Mallow
Chalk Maple
Falls
Windy Grove
Bottlebrush
Southern Stone
Cypress Creek Bend
Twilight Creek
Coralbend
Riata Lake
Silverado Trace
Branch Canyon
Queenston
Vienna Trails
Zinnia
Stoney Meadow
Columbia Springs
Country Arbor
Creek Bluff
Lone Wolf
Laguna Trail
Red River
Ivy Wild
Wind Mist
Brushy River
Sonoma del Norte
Acanthus
Brandon Gate
Golden Hearht
Sawmill Creek
Shoalwood
Coyotillo
Shadow Cypress
Riata Springs
Whispering Star
Kingston Creek
Riata Manor
Heartwind
Desert
Shadow Lawn
Indian Paintbrush
Keystone Fairway
Sea Myrtle
Echo Falls
Apache Way
Castle Peak
Mandavilla
Barker Cypress
Sanibel Falls
Little Riata
Kiowa River
Feather Fall
Hoover Garden
Opal Ridge
Oleander Point
Lyndon Meadows
Obsidian
" )40
Marble Crest
Falling River
Prospect Meadows
Summit Canyon
Willow Ranch
Wax Mallow
Sablebrook
Pavonia
Canterra
Cobalt Falls
4WD Road
"
" )39
Sulphur Stream
Turquoise Stream
Red Rugossa
Roaring
Eldoro Canyon
Lost Mill
"
Cottonwood Canyon
Falcons Cove
Cliff Haven
Bald Ridge
" )38
Caldera Canyon
Palisade Lakes
"
RENNELL EL
Meridian Lakes
Hahns Peak
Pinon Vista
Red Mesa
Port Erroll
Pine Flats
Temple
Houston National Golf Club
Barrett Post
Adobe
Bluff Springs
s
n
n
Tuckerton
Mesa Point
Kirkton
Wakefield Village
Chestnut Bluff
" )37
Oxford Grove
Cape Breeze
"
Tuckerton
Drif
Copper Mist
Danbury Bridge
Burkhart Ridge
Beckwood Post
Coleburn
Walford Mill
Bark Ridge
Wheaton Edge
Locust Springs
Pine Bank
Queenston
Coyote Creek
Pine Castle
Sperry Gardens
Libson Falls
Greenbriar Point
Torridon
Mammoth Springs
Shorewood Lakes
Dunain Park
Find Horn
Balvenie
Rosewell
Brechin
Appin
Bowmore
" )36
Speyburn
"
Farley Pass
Gaslamp
Curry Landing
Copperbluff
Bristle Creek
Vander Rock
Aberdeen Green
Starlamp
Sunlamp
Aberdeen Lake
Abergreen
Newburgh
Newlight Bend
Copper Cove
Grenada Falls
Catawissa
Aberdeen Park
Aber Trail
Green Castle
Guiness
Shango
Bonnyview
Swandale
Sweetrose
Green House
Taftsberry
Berkshire Forest
Green Smoke
Aberdeen Oaks
Angel Hill
Whitaker Creek
Sherina Park
Rosehe
Blaire
Tall
Aberdeen Trails
Wheat Cross
Raven Canyon
Mosbriar
Distant Woods
Dawnblush
Apple Mill
Red Hill
Cade
Kentwa
Jamie Lee
Spring
Jamie Lee
Rock Arbor
Lilac Spring
Ambermist
Red Falls
Floralgate
Lasting Light
Light Fall
M
Hollow Bay
Gentle Stone
Brinton
Golden Sands
Oak Mountain
H
o
Kinrush
rs
e p
Pool Creek
Laurel Trails
Pine Falls
Spruce Mill
Sunny Ridge
Canton Park
Canton Park
Wheaton Forest
Cascade Hollow
e
n
Torry View
Gentlewood
Star Hollow
Country Brook
Cree
k
Crystal View
Sparkling Springs
Spring Green
Oak Mountain
Greenleaf Lake
Copperbluff
Shoal Lake
Rippling Brook
Timbercraft
Lake Crystal
Bright Grove
River Cliff
Drystone
Copper Village
Broken Timber
Plum Lake
Highfie
Secret Branch
Meadow Crossing
Sandestine
Candlerock
Lake Crystal
Misty Trail
Langham Creek Park
Windy Thicket
Morning Oak
Woodland Knoll
ï
Bending Branch
Sunrise Meadow
Shining Rock
Cypress Laurel
Amber Mist
Summer Reef
Island Manor
Stoneside
Innisbrook
Moncur
Harvester
Crossfield
Willingham
Elmbank
Hot Springs
n
n
Pinyon Creek
Ferncliff
FIEST EL
Town Creek
Silent Cedars
Oak Park Bend
Quiet Dawn
Oak Glen
Fairgrove Park
Copper Lakes
Millrun
Ashton
Millers
Lakedale
Wellers
Timber Mist
Gable Oak
Laguna Springs
Copper Shore
Millridge
Millshire
Oat Mill
Battlecreek
Sweetwater Creek
Silver Fir
Chimneystone
Wemyss Bay
Cairngorm
Maple Brook
Ivy Bridge
Willow River
Ri
Longenbaugh
Sun Terrace
Morning Rose
Mill Village
Crescent Canyon
Preston Springs
Barley Mill
Salinas
Dawson Mill
Leamington
Kintyre Point
Sunny Ridge
Highland Canyon
McCormick
Viney Creek
LABA
Ashton
Hickory Cove
n
n
Holly Falls
Park Hollow
Villa Lake
"
Mile Post
Tawny Bluff
Æ P Healthcare Facility
Chatham Springs
Redwoo Manor
High Knoll
Rustling Aspen
Leaf Point
Land Use
Housing Density
Tall Maple
Silver Ash
Ivy Trail
Scenic Lakes
High Village
ï
Cross Falls
Developed
Rustic Lake
Forest
Terra Canyon
Dusty Yaupon
Poppy Grove
Indian Desert
Royal Gardens
0 - 20 Units/Mile
I
Peach Forest
Highland Farms
Hidden Oaks
Environmental Assessment
Heather Heights
Springville
Spruce Haven
Shady Palms
Knolls Lodge
S
n School
21 - 100 Units/Mile
Wetlands
ï Park
Galleon Field
Cliffsage
Desert Moon
Yaupon Ranch
Praire Bluff
Black Gap
Wild Willow
West Gate Park
>100 Units/Mile
Crestbrook Manor
Mossy Ridge
Feather Springs
Forest Heights
Meadow Heights
Colony Point
Misty Fern
Granite Ridge
Autumn Laurel
Shangrila
Longhorn Pipeline Reversal
View Park
Park Falls
Signal Creek
Rainbow Lake
Crested Hill
Agricultural
Westhall
Lone Meadow
Western Pass
Figure 4.1.2-1i
Brook Springs
Hayward
s Country Club/Golf Course
Laurel Trail
Brockland
Windgate
Garnercrest
Gable
Saxon
Almond Springs
Poplar Hill
Garden Hill
Hidden Shadow
Open Water
Sisterdale
Prarie Fire
Sundance Trail
Kenmark
Ridgegrove
Masonridge
Wildwood Brook
Forest Dawn
² ¶ Overnight Lodging
River Pines
American Holly
Crown Meadow
Magnolia Shadows
Plumtree Forest
Wisteria Ridge
and Housing Density
Evergreen Brook
Houston Area Land Use
Elm Point
Club Lake
Creek Glen
Windy Glen
¬ «6
Stratwood
Pheasant Grove
Shrub/Scrub
Yaupon Mist
Yucca Field
Knoll Lake
Hollow Cove
Autumn Manor
Hickory Point
SHEET 9 OF 9
Longhorn Pipeline
Maple Point
Clairson
Colefield
Grand Terrace
Hamilwood
Dogwood Falls
Sheffield Bend
Narcissus Brook
Kransburg Ranch
Eastwood
Scarlet Oak
Barren Land (Rock/Sand/Clay)
Haley Falls
Wimberly Park
Brazoria
Galveston 0 0.5 1
Land Use Source: USGS 2006 NLCD
Stoney Haven
Winston Hill
Bubbling Brooks
Maplemont
Maplemont
Maplemont
Prepared By: Atkins/19685
Pebbleglen
Job No.: 100019708
Odinglen
Lakeview Haven
Scale: 1:24,000
Ridge Park
Mesa Gardens
Pleasant R
Date: Apr 10, 2012
Echo Lodge
Hollow Ridge
Broken Ridge
Westcliffe
Village Lake
Greenwood Point
Oleander Ridge
Livery
Swan Valley
Connemara
Heathridge
Liner
Boysenberry
Daylight
Foxton Place
Sutton Falls
Prairie Village
Lapis Meadow
Remington Grove
Grackle
Dove Field
Legacy Pines
Headland
Haughland
Crestbury
Andalusian
Hollow Field
Ivory Crossing
Broadelm
Augusta Pine
Terrace Park
Slippery Elm
Barton Oaks
Sonnet Glen
Miles
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-1a-i_Houston_HousingDensity.mxd
Sunlight
Skylight
Dew Mist
Silver Sky
Crystalglen
Postwick
Starbridge
Sugar Ridge
Clear Valle
Larkspur Hills
Grackle
Hazel Cove
Lost Fable
Dew Drop
llant Glen
Summer Dew
Skybright
Dew Drop
Glenbrook Knoll
nbank
mmer Mist
Summer Dew
Palisades Heights
Valley Creek
Arbor Park
berry
River Garden
Glen Chase
L
angh
a
m
C
re
e k
Liberty
Raven Creek
Bellwick

<<<PAGE 176>>>

Wolf
" )156
"
Fagerquist
Jacobson
Swiss
Chalet
Alps
Alpine
Bern
Zurick
Vevey
Dobush
Forest Glenn
Panorama
Timber Hills
" )155
"
High Noon
" )154
Hayride
"
Fagerquist
Maha Creek
Maschmeier
Wolf
Pearce
" )153
"
High Ridge
Stony Creek
Maha
Point
Post Oak
Stony Point
Rock Creek
Stony Mont
High Ridge
Algarita
County Road 41
Edgemount
Edge Rock
Linden
Burnet
Blanco
Hays
Williamson
Travis
Bastrop
Comal Caldwell
County Road 255
County Road 364
Reines
Brents
Scrappers
County Road 354
"
Mile Post
Æ P Healthcare Facility
n School
ï Park
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Land Use Source: USGS 2006 NLCD
Rainbow
County Road 355
Land Use
County Road 414
County Road 386
Developed
Forest
Headquarters
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Caballo
Privada
County Road 256
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Cottonwood Creek
Shadow Wood
Mockingbird
County Road 110
Winecup
Oriole
County Road 301
High Point
" )152
"
" )151
"
" )150
"
Private
County Road 348
County Road 350
County Road 347
I
0 0.5 1
Miles
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-2a
Austin Area Land Use
and Housing Density
SHEET 1 OF 7
Prepared By: Atkins/19685
Scale: 1:24,000
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd

<<<PAGE 177>>>

Colton
Hillmoore
Airline
anda
Foley
Reservist
Feller
Dearbonne
Gilwell
Diwa
Mathra
Vizquel
Bahan
Lofton Cliff
Sexson Ridge
Tabitha
Manowar Stretch
Sea Biscuit
Alysheba
War Admiral
Fryman Hill
Clouds Reach
Overlook Ranch
Country View
Rangeland
Community Center
La Guardia
Algel
Las Alas
Los Dios
Sky Harbor
Paloma Blanca
Country Meadow
Country Mesa
Campana
Sky Park
Sky Park Ross
Los Cielos
La Paz
Quirin
Thome Valley
Coomes
Winters
Malarkey
Alomar
Nijmegn
Perconte
Lipton
Welsh
Pearce
Night Sky
Vida Nueva
Ross
Randleman
Onion Creek
Cottonmouth Creek
General Aviation
Richard Moya Park
ï
" )160
"
FM 812
McKenzie
Moores Bridge
Linda Vista
FM 973
" )159
"
Bain
San Jose
Lonesome
North Fork Dry Creek
FM 973
Dry Creek
Ponder
Citation
Man O War
Ruidosa
Engler Park
Moores Crossing
Darrin
Hewers
Tickford
Apperson
Gemmer
Railton
Maybach
Kellner
Wardman
Proud Panda
Iwanna
Schebler
Morning View
Great Panda
Arrowmound
Towery
Williamson
Burnet
"
Mile Post
Æ P Healthcare Facility
n School
Travis
Blanco
Bastrop
ï Park
s Country Club/Golf Course
² ¶ Overnight Lodging
Hays
Longhorn Pipeline
Comal Caldwell
Land Use Source: USGS 2006 NLCD
Black Panda
White Panda
" )158
"
Kellam
" )157
"
Elroy
McAngus
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Land Use
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Navarro Creek
Alice
" )156
"
Fagerquist
Plover
Jacobson
Swiss
Chalet
Alps
Alpine
Bern
Zurick
Vevey
Dobush
0 0.5 1
Maha Creek
I
Miles
Forest Glenn
Panorama
Timber Hills
" )155
"
Maha Creek
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-2b
Austin Area Land Use
Linden
and Housing Density
Maschmeier
SHEET 2 OF 7
Scale: 1:24,000
Date: Apr 10, 2012
Prepared By: Atkins/19685
Job No.: 100019708
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd

<<<PAGE 178>>>

Clearday
Star
Meteor
guin
Congress
Circle S
elt
Foremost
§ ¨ ¦35
Chaparral
Corral
North Bluff
§ ¨ ¦35
Boggy Creek
" )166
"
Boggy Creek
Omni
Shallowbrook
Hayride
Charles Goodnight
Shaw
McKinney Fa
Onion Creek
Williamson Creek
Williamson Creek
Meadow
Atascosa
Parell
Ferret
Galen
Palo Blanco
Walnut Grove
China Berry
Mesquite Grove
Hickory
Blackjack
George
Teri
Jimmy Clay
Icon
McKinney Falls State Park
ï
Wagon Crossing
Wagon
Dove Springs
Lakehurst
Eastridge
Bluff
Westwood
Commodore
Stonleigh
Bendridge
Rockridge
Bitter Creek
Branchwood
Blue Dawn
Spruce Gum
Elm Creek
Deer Run
LANGFORD EL
Blue Meadow
n
Trendal
Bitteroot
Hyland
Nogales
Alegre
Encanto
Tranquilo
Lendall
Patsy
Dan
Eds
Silverstone
Quicksilver
Ashley
Edge Park
Jenibeth
Sunny Hills
Muirlands
Ardmore
Barkdale
Village
Palo Verde
Encinal
Dove
Dovemeadow
Dovewood
Dovehill
Pino
Dove Creek
Leatherleaf
Candletree
Hammermill
Turnstone
Turtle Dove
Wing Feather
Softwood
Flicker
Creek Bend
Teewood
Brushy Ridge
Avalon
Ripple
Raleigh
Lambs
Fontenay
Bucks
Granger
Glade Line
Meadow Lake
Tournus
Loire
Misty Slope
Magin Meadow
Cliffridge
Deep
" )165
"
Borage
Vinca
Saguaro
Savorey
Chateau Village
Edge Creek
Hidden Brook
Ainez
Village Square
Nuckols Crossing
Nesting
Brassiewood
Onion Creek Soccer Complex
Vougeot
Jimmy Clay Golf Course
Canella
Pleasant Valley
Onion Creek
Sand Hill
Little Cypress
Onion Crossing
Onion Crossing
Shady Cedar
Catclaw
Thornhill
Springville
Wild Onion
Ladybug
Thatch
Firefly
Vine Hill
Glowworm
Walkingstick
Honeybee
Onion Creek
Katydid
ï
s
William Cannon
" )164
"
Onion Creek Greenbelt
ï
Orleans
Lake Charles
Conti
Rhett
Green Grass
Spring Fever
Asa
Running Water
Crepe Myrtle
Dixie
Tupelo
Salt Springs
Marble Crest
Redrick
Cats Eye
Springtime
Tara
Marl
Piedras Blanco
Marble Creek
Bixler
Roseborough
Ringsby
Villa Acuna
Bannock
Eudora
Thaxton
Verbank Villa
Ken Caryl
Rosenberry
Bramble Bush
Panadero
" )163
"
Zequiel
Brockman
Mozelle
Cecil
Perkins
Old Lockhart
Fall Meadow
Forbsdale
Georgie Trace
Quinton
Wiley
Colton Bluff Springs
Alum Rock
Marble Ridge
Briarton
Marble Creek
Broad Brook
Flaxen
Felipe
Sabrina
Doyal
Walkup
Deja
Brandt
Land Use
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Cottonmouth School
" )162
"
North Fork Dry Creek
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Perimeter
Burleson
Norwood
£ ¤ 183
Colton
Cottonmouth Creek
Colton
Hillmoore
Dee Gabriel Collins
Colton
" )161
Airline
"
Viewing
Wanda
Creedmoor
Lava Hill
£ ¤ 183
FM 1625
I
0 0.5 1
Miles
" )160
"
FM 812
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-2c
Austin Area Land Use
and Housing Density
SHEET 3 OF 7
FM 973
Scale: 1:24,000
McKenzie
Date: Apr 10, 2012
Prepared By: Atkins/19685
Burnet
Blanco
Grelle
Nuckols Crossing
Slaughter
Cheryl Lynn
"
Mile Post
Williamson
Æ P Healthcare Facility
n School
Travis
ï Park
Bastrop
Hays
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Comal Caldwell
Land Use Source: USGS 2006 NLCD
Job No.: 100019708
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd

<<<PAGE 179>>>

I
Travis
Hays
Bastrop
Williamson
Comal Caldwell
Burnet
Blanco
0 0.5 1
Miles
ï
ï
ï
ï
ï
n
n
n
n
Æ P
"
"
"
"
"
"
"
" )171
" )166
" )167
" )172
" )168
" )169
" )170
LEGACY OAKS CHRISTIAN
BOONE EL
WILLIAMS EL
TEXAS NEUROREHABILITATION CTR
Dick Nichols Park
South Boggy Creek Greenbelt
Davis Hill Neighborhood Park
Dittmar Park/Recreation Center
Goat Cave Karst Nature Preserve
1st
Dittmar
Manchaca
Old Lockhart
Latta
Deer
Lunar
Matthews
Curlew
Bluff
Eskew
Circle S
Palace
Doe
Libyan
Sahara
Berkett
Cooper
Shiloh
Nairn
Eberhart
Marsh
Ramble
Beckett
Emerald Forest
Woodhue
Riddle
Monarch
Alexandria
Leo
Dunn
Speer
Cullen
Longview
Lear
Lost
Echo
Miles
Congress
Mairo
Tello
Hubach
Wynne
Quicksilver
Holt
Davis
Turtle Creek
Armadillo
Paisano
Brodie
Kandy
Minturn
Manassas
Albert
Ralph Ablanedo
Convict Hill
Drew
Copano
Wolftrap
Lindshire
Alcott
Milford
Norman
Beard
Forest Wood
Squirrel
Chisholm
Idalia
Finch
Great Britain
Mauai
Aldford
Oak
Baxter
Blarwood
Shadywood
Tetbury
Iriona
Windrift
Wasson
Coastal
Harpers Ferry
Elijah
Strickland
Stassney
Sawmill
Plantation
Inridge
Wyldwood
Ovalla
Norfolk
Peaceful Hill
Cannonleague
Bissel
Magee
Corral
Allred
Willet
Ganttcrest
Tamil
Thelma
Toulouse
Shep
Nancy
Slaughter Creek
Radam
Natali
Yarsa
Dixon
Frock
Sherwood
Minnie
Soho
Cameron
Lilac
Croftwood
Clarno
Dalton
Aftonshire
La Cresada
Pratt
Nightjar
Cecil
Gail
Blake
Bill Hughes
Cougar
United Kingdom
Vassal
Mimosa
Taylorcrest
Parkside
Blumie
Hoffman
Carlow
Cloudview
Keepsake
Cortina
Eganhill
Headly
Whispering Oaks
Stonecroft
Gobi
Alta Loma
Tiombe
Elm Forest
Silk Oak
Axis
Tecate
Collingwood
Sanford
Shady Valley
Stoneoak
Seminary Ridge
Bramble
Francia
Blackberry
Islander
Gate
Jorwoods
Nesbit
Cedar
Little Texas
Avocet
Texas Sun
Berkeley
Trede
Reynosa
Shadow
Gettysburg
Tiffany
Verona
Gaines Mill
North Bluff
Queenswood
Evaline
Treys
Sunstrip
Campfield
Meadow Lea
Capriola
Reno
Notches
Wagtail
Zuniga
Salida
Chaparral
Cohoba
Kentish
Boxcar
Clubway
Capistrano
Antelope
Empress
Cattle
Loganberry
Woodshire
Hitcher
Rochelle
Huxley
Creekline
Trace
Crow
Sweet Clover
Bilbrook
Kempler
Aldea
Skynook
Western
Crownspoint
Lancret Hill
Kimono Ridge
Wessex
Texas Oaks
Ramies
West Gate
Graybuck
Buffalo
Stanley
Clearday
Willers
Neider
Arbor
Blue Valley
Middleham
Tensley
Indian Point
Whispering Winds
Wilcrest
Tea Rose
Chippeway
Red Bird
Leadville
Washita
Idlewood
Stormy Ridge
Mockingbird
Merriwood
Ampezo
Doliver
Skyloop
Jubilee
Bremner
Deatonhill
Ranch
Krollton
Mojave
Starstreak
Meadow Creek
Anna
Spearson
Brantley
Blanco River
McGregor
Blueberry
Foremost
Brookhill
Treehouse
Struie
Forest Heights
Molokai
Roxanna
Stone River
Zeke
Harley
Sunny Vista
Eureka
Oak Ledge
Bankside
Sir Gawain
Piney Creek
Latteridge
Kavanagh
Burly Oak
Devine
Bluestar
Bradner
King Albert
Bodark
Kestrel
Reaburn
Castlewood
Hillston
Kellywood
Shady Hollow
Clarksburg
Steamboat
Wakefield
Alabama
Glen Oak
Redleaf
Mozelle
Dan Jean
Taline
Bobby
Epping
Calico
Sendera Mesa
Manzanillo
Kearsarge
Birmingham
Flournoy
Kenyon
Cedardale
Perkins
Keota
Alfred
Romney
Linton
Wommack
Barnsdale
Darnell
Steed
Dunliegh
Austin Highlands
Tyhurst
Silkgrass
Greenock
Old Manchaca
Blythewood
Trout
Genoa
Dulwich
Alegre
Austral
Olguin
Waycross
Lazy Oaks
Cache
Firecrest
Pecanwood
Comburg Castle
Salem Hill
Mount Carrell
Galesburg
Bushnell
Cannonwood Dunstan
Hale
Lancaster
Linnet
Sandra
Bernoulli
Goldbridge
Dempsey
Whitestone
Hethcock
Evanston
Appomattox
Salem Walk
Rocky Ford
Mulberry
Navarro
Lynnbrook
Escabosa
Hood
Corran Ferry
Cockburn
Leafield
Rocking Horse
Dobbin
Heartwood
Hibiscus Valley
Tinmouth
Glenhollow
Boggy Creek
Starbright
Aspen Creek
Tranquil
Hove
Keswick
Star
Amber
Moose
Whitt
Vigen
Bannockburn
Culberson
Marchmont
Sedgemoor
Ruddington
Chesney Ridge
Simonetti
Comburg
Okner
Molera
Sarasota
Campden
David Moore
Cornwall
Baldridge
Barge
Lowdes
Emerald Wood
Jesse James
Dryden
Saloma
Harwin
Whitsun
Heatherwood
Raspberry
La Naranja
Linkmeadow
Skycrest
Stage Coach
Acorn Oaks
Swindon
Roehampton
Piping Rock
Briar Ridge
Walsall
Lochinvar
Wood Cliff
Falcon Hill
Hill Wood
Brisbane
Dulcet
Bluesky
Pannier
Hackamore
Shant
Sugar Hill
Harvest
Jacky
Bradsher
Woodcroft
Sika
Fitchwood
Korth
Keilbar
Wykeham
Bender
Greenland
Huebinger
Thistlewood
Dandelion
Margra
Bryonhall
Winterstein
Hedgewood
N
Kings
Brasher
Tavistock
Garden Oaks
Deeringhill
Broken Oak
Brown Rock
Foxton
Canus
Persimmon
Mosquero
Harleyhill
Alderwood
Glen Meadow
Hyde Park
Breezewood
Buckingham
Danli
Meteor
Teaberry
Greycloud
Grasshopper
Velasco
Rearden
King Edward
Palacios
Pectoral
Brecon
Grennock
Barasinga
Caspian
Counselor
Saffron
Hillside Oaks
Doncaster
Craigmont
Boleynwood
Minot
Muskdeer
Keneshaw
Humming Bird
Lenora
Ainsworth
Encanto
Barnsley
Malvern Hill
Wood Bine
Sunnysky
Apache Forest
Meacham
Cheney
Pusch Ridge
Wales
Fitzroy
Kalama
Arrow
Edenwood
Cayuga
Wycombe
Wishing Well
Malone
Shackelford
Quivira
Creekmere
Bavaria
Sheri Oak
Swansons Ranch
Croydon
Brockman
Loch Lommond
Lambeth
Estancia
Bill Hickcock
Lyric
Collazo
Gwendolyn
Snapdragon
Ivanhoe
Towering Oaks
Emerald
Cretys
York Bridge
Holly Springs
Hazen
Fentonridge
Lillian
Huntingdon
Hornet
Rustic Oak
Lagerway
Twisted Oaks
Crosswood
China
Nordham
Sissinghurst
Manipari
Southwind
Shelby Oak
Teresina
Brock
Mabry
Dillion Hill
Charlesworth
Sirocco
Granberry
Caladium
Aylesbury
Lanna Bluff
Meadows
Courtney
Collins
Wordham
Garrettson
Brodie Springs
Cherry Meadow
Steamline
Denbar
Jaffna
Scottish Thistle
Wilton
Ibis
Mesa Verde
Silmarillion
Tockington
Wadsworth
Siskin
Dos Cabezas
Boggy Ridge
Triboro
Cherry
Mitchell
Galapagos
Fuente
Belclaire
Beaconcrest
Azalea Blossom
Copperas
Rose Hill
Independence
Bloomfield
Broomflower
Fancy Gap
Aoudad
Plumpton
Dee
Tawny
Tobago
Gee
Coyote
Kansas River
Chickasaw
Dominic
Galliano
Lomita Verde
Cannes
Beauregard
Dowling
Barrow Glen
Spruce Gum
Ramblewood
Ferndale
Cherrydale
Edge Park
Treasure
Gallop
Oak Hedge
Aletha
Uvalde
Whiteworth
Salmon
Evadean
Leah
Dan
Ardmore
Castledale
Caymen
Blue
Lightwood
Salem Meadow
Bordley
Amber Oak
Saint Amant
Grigsby
Centralia
Alcorn
Mosswood
Constantino
Sarong
Lewood
Leisure Run
Lishill
Clydesdale
Puckett
gewell
Orr
Kittyhawk
Apricot
Shier
Turquoise
Star Grass
Larson
San Paublo
Moat
Apple Carrie
Brickford
Cloudberry
Melville
Cedrick
Glen Hollow
Kangaroo
Ivory Key
Irish Bend
Tabor
Calumet
Shale
Bexton
Darvone
Clearsky
Kellywood
Ranch
Harvest
William Cannon
Glen Meadow
Davis
Cherry
Gail
Berkeley
Gettysburg
Meadow
Chisholm
Cattle
Slaughter Creek
Davis
Oak Valley
§ ¨ ¦35
§ ¨ ¦35
¬ «1
¬ «1
¬ «1
Boggy Creek
Slaughter Creek
Williamson Creek
Williamson Creek
Slaughter Creek
Williamson Creek
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-2d
Austin Area Land Use
and Housing Density
Prepared By: Atkins/19685
Job No.: 100019708
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd
Scale: 1:24,000
Date: Apr 10, 2012
"
Mile Post
Æ P Healthcare Facility
n School
ï Park
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Land Use
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Land Use Source: USGS 2006 NLCD
SHEET 4 OF 7

<<<PAGE 180>>>

" )178
"
Antler Bend
Weir Loop
Michael
Kay
Rod
Vikki
Geneva
Weir Loop
Eitel
Ledgestone
Hillside
Tangleridge
Circle
Grape Creek
Oliver Cemetary
Baxter
" )177
"
Valley Vista
Spring Valley
Oliver
Schmidt
Clemente
Derecho
Shallowford
Hourglass
Bronzewood
Spring
Rock Way
Twilight
Elm Grove
Peak Ridge
" )176
"
Sandstone
£ ¤ 290
Friar Villa
Rimrock
Morningstar
Morninghill
Morningsun
County Road 355
Kit Carson
Signal Hill
Burnet
Blanco
Jim Bridger
Davy Crockett
Old Baldy
Bisson Buckskin
Appaloosa Run
Cedar Paw
"
Mile Post
Williamson
Æ P Healthcare Facility
n School
Travis
ï Park
Midmorning
McMeans
Trailmaster
Appaloosa
Bastrop
Hays
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Comal Caldwell
Land Use Source: USGS 2006 NLCD
Fenton
Banpass
Circle
Mowinkle
Thunderbird
Circle
Scenic Brook
Thunderbird
Haskel
Boling
South Bend
South View
Candelaria
Butler
Scarlet
Tara
View
Feather Hill
Oak Valley
Cima
Crest View
Deer Haven
La Fauna
Espanola
Putt
San Diego
Flintrock
Sisquoc
Vera Cruz
San Juan
Honeycomb
Ramble Three
" )175
"
El Dorado
Kali
Young
Silver Mountain
Shankel
McGrath
Fleenor
Lewis Mountain
La Plata
Boxtree
Arterial 12
Edgecomb
Swelfling
Blazyk
La Crosse
Aldenburgh
Spruce Canyon
Zyle
Via Grande
Brecourt Manor
Sky Rock
Split Stone
Tera Land
Slaughter CR
FM 1826
Doswell
Pairnoy
Cusseta
Spruce Canyon
McMeans
Jess
Sharl
¬ «45
Housing Density
¬ «45
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Land Use
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
Old Bee Caves
Williamson Creek
South Brook
Whispering Creek
¬ «71
Silver Dale
Oak Meadow
Callbram
Landsman
Upslope
El Rey
Acton
Rosson
Hudson
Phoenix
La Tosca
Apache Springs
Granada Hills
Summervale
High Valley
Crazy Horse
Broken Lance
Adobe
Gallant Fox
Callbram
Tiverton
Amicus
Landsman
Dark Ridge
Twilight Terrace
£ ¤ 290
Breezy
La Concha
Corrie
Debcoe
Telluride
Shadowridge
Orrick
Kenosha
Wolfcreek
Hill Oaks
Latigo
Gentle Oak
Kenosha
Samar
Poncha
Bending Oak
Jumano
Ridge Oak
Robert Kleburg
Convict Hill
Zadock Woods
Oliver Loving
John Chisum
Whistlestop
Open Range
Twilight Mesa
Dark Valley
Rotan
Hot Springs
Twilight Shadow
Colberg
Bella Vista
" )174
"
J C Ranton
McKown
Seranton
Hachita
Beatty
Allerton
Gabion
Gaur
Edwardson
Fainwood
Auckland
Barstow
Taylorcrest
Donner
Ruxton
" )173
"
Slaughter
Hopeland
Bungalow
Argyle
Carrington
Prescott
Vinemont
La Siesta
Siringo
Oasis
Cheno Cortina
Richard King
Henry Kinney
Isaac Pryor
Clay Allison
Clairmont
Dunsmere
Abilene
Farmdale
La Naranja
San Paublo
Clarion
Lantana
Salcon Cliff
Hillside Terrace
Sommerland
Wampton
Sautelle
Colebrook
Kayview
Wheel Rim
Doe Meadow
Brown Rock
Blanco River
Forest Heights
Ganttcrest
Beckett
Magee
Tyhurst
Fitchwood
Marchmont
Pecanwood
Mesa Verde
Lomita Verde
Taylorcrest
Meacham
Ridgewell
Sunny Vista
York Bridge
Bavaria
Manipari
Neider
Hitcher
Tiombe
Mabry
La Cresada
Korth
"
" )172
Chesney Ridge
Norman
Zuniga
S
Cap Stone
Seneca Falls
Nubian
Maelin
ï
Slaughter Creek
Hansa
Tollesboro
Tasajillo
Circle C Ranch Metropolitan Park
Escarpment
Esquel
¬ «1
Estancia
Van Winkle
Austral
Dedham
La Crosse
Natick
Danvers
Orourk
Nusser
Freesia
Ames
Redmond
Needham
Goodall
Walpole
Roxbury
Ariock
Walebridge
Old Harbor
Londonshire
I
Rhett Butler
Dahlgreen
Ballenton
Stellar
Bluestar
Scottish Thistle
Eclipse
¬ «1
Environmental Assessment
Hibiscus Valley
Longhorn Pipeline Reversal
Broomflower
Figure 4.1.2-2e
Austin Area Land Use
Snapdragon
and Housing Density
SHEET 5 OF 7
Scale: 1:24,000
Prepared By: Atkins/19685
Date: Apr 10, 2012
Job No.: 100019708
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
0 0.5 1
Miles
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd
Salmo

<<<PAGE 181>>>

dwood
County Hwy 184
Stillman
Silver Creek
BBB
BBB
Triple Creek
B
Crumley Ranch
Bonham Ranch
Johnson
" )183
"
Fitzhugh
Crumley Ranch
" )182
"
Fitzhugh
" )181
"
Pauls Valley
Cambrian Creek
Roy Branch
Summit
Circle G Ranch
Lookout
High Sierra
Red Gate
Wells Fargo
Piasano Pass
Canyonwood
Timberline
Blue Hills
Paisano
Canyon Rim
Oak Crest
Upland
Cottonwood Branch
Cottonwood Creek
Oakwood
Terrace Canyon
Bending Oak
Creek
Clear Creek
Burnet
Roy Creek
"
Mile Post
Williamson
County Road 185
Land Use
Æ P Healthcare Facility
n School
Developed
Forest
Travis
Wetlands
Blanco
ï Park
Bastrop
Hays
s Country Club/Golf Course
² ¶ Overnight Lodging
Agricultural
Open Water
Shrub/Scrub
Longhorn Pipeline
Comal Caldwell
Barren Land (Rock/Sand/Clay)
Land Use Source: USGS 2006 NLCD
Fitzhugh
Carol Ann
Shoshoni
Trail Driver
Bonham
Bonham
Barton Creek
Little Thicket
White Tail
Long Branch
" )180
"
Sleepy Hollow
Sickle
Drift
Winding Creek
Cole
Sundown
Housing Density
Garrett
Trails End
0 - 20 Units/Mile
21 - 100 Units/Mile
>100 Units/Mile
Tall Oaks
D Morgan
White Branch
Kinser
Long
" )179
Wagon
"
Myrtle Creek
Hillside
Fitzhugh
Long Branch
Longwood
Laurel
Oaks
Antler Bend
Oak Branch
Long Creek
I
0 0.5 1
Miles
"
" )178
Tangleridge
Circle
£ ¤ 290
Slaughter Creek
Friar Villa
Environmental Assessment
Rimrock
Longhorn Pipeline Reversal
Figure 4.1.2-2f
Austin Area Land Use
and Housing Density
SHEET 6 OF 7
Valley Vista
Spring Valley
" )17
"
Prepared By: Atkins/19685
Scale: 1:24,000
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd

<<<PAGE 182>>>

Lost Creek
" )188
"
Oak
Oak
River
Oak Forest Bell Springs
Cordwood
Bell Springs
" )187
"
Medlin Creek
Barton Creek
Darter
Harmon Hills
Farm-To-Market Road 348
Sullivan
Patricks
Burnet
Williamson
Hart
Travis
"
Mile Post
Spring Valley
Æ P Healthcare Facility
n School
Blanco
ï Park
Bastrop
Hays
s Country Club/Golf Course
² ¶ Overnight Lodging
Longhorn Pipeline
Comal Caldwell
Land Use Source: USGS 2006 NLCD
Sunrise
Lander
Stirrup
Winchester
Bridal
Lariat
Fitzhugh Creek
Barton
" )186
"
Kevins
Land Use
Barton
Ted Burger
Barton
Developed
Forest
Wetlands
Agricultural
Open Water
Shrub/Scrub
Barren Land (Rock/Sand/Clay)
" )185
"
Barton
Barton Ranch
Housing Density
0 - 20 Units/Mile
21 - 100 Units/Mile
FM 12
>100 Units/Mile
view
Horseshoe
The Entrance
Horseshoe
Brooks Ranch
Hill Country Skyline
Surveyors
Compass
Twin Lake
Linkhill
Linkwood
West Cave
Shepherds Corral
West Cave
Hideaway
Saddletree
Cave
Cave
West Cave
Turkey Trot
Montecito
Fawns
Montevista
Westward Look
Mason Dixon
Bubbas
Bubbas
Longhorn
Hilltop
VL
Parkwood
Village
Sandy Beach
Thomas
Janet
George Hill
Little Creek
Westlake
Earl
Lake Park
Rocky Creek
Lakeshore
Creekwood
Lake Beach
Cave
Eastward Look
Panorama
Lakewood
Oak Cliff
Brooks Ranch
Glenview
Wildwood
Oakwood
Timber
Timber
Deer Creek
Scenic
Green Oak
Twin Creek
Bonham Ranch
Bonham Ranch
" )184
Wildwood
"
Bonham Ranch
Crossroads
" )183
"
Fitzhugh
Silver Creek
Triple Creek
Barton Creek
Brooks
County Hwy 184
BBB
BBB
Stillman
Johnson
Crumley Ranch
" )182
"
Barton Creek
I
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.1.2-2g
Austin Area Land Use
and Housing Density
SHEET 7 OF 7
0 0.5 1
Miles
Crumley Ranch
Prepared By: Atkins/19685
Scale: 1:24,000
Job No.: 100019708
Date: Apr 10, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.1.2-2a-g_Austin_HousingDensity.mxd

<<<PAGE 183>>>

450
400
350
300
250
200
150
100
50
0 50
Miles
Mile Post
Overland Spread Longhorn
Longhorn Pipeline Existing
Major Aquifers of Texas
Carrizo - Wilcox (outcrop)
Carrizo - Wilcox (subcrop)
Edwards BFZ (outcrop)
Edwards BFZ (subcrop)
Edwards - Trinity Plateau (outcrop)
Edwards - Trinity Plateau (subcrop)
Gulf Coast
Hueco - Mesilla Bolson
Ogallala
Pecos Valley
Seymour
Trinity (outcrop)
Trinity (subcrop)
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.1-1
Major Aquifers
Prepared By: Atkins/13029
Scale: 1" = 50 miles
Job No.: 100019708
Date: June 6, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.1-1_Major_Aquifers.mxd

<<<PAGE 184>>>

450
400
350
300
250
200
0 50
Miles
Mile Post
Overland Spread Longhorn
Longhorn Pipeline Existing
Minor Aquifers of Texas
Blaine (outcrop)
Blaine (subcrop)
Brazos River Alluvium
Captain Reef Complex
Dockum (outcrop)
Dockum (subcrop)
Edwards-Trinity (High Plains)
Ellenburger-San Saba (outcrop)
Ellenburger-San Saba (subcrop)
Hickory (outcrop)
Hickory (subcrop)
Lipan (outcrop)
Lipan (subcrop)
Marathon
Marble Falls
Nacatoch (outcrop)
150
100
50
Nacatoch (subcrop)
Queen City (outcrop)
Queen City (subcrop)
Rustler (subcrop)
Sparta (outcrop)
Sparta (subcrop)
Woodbine (outcrop)
Woodbine (subcrop)
Yegua Jackson
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.1-2
Minor Aquifers
Prepared By: Atkins/13029
Scale: 1" = 50 miles
Job No.: 100019708
Date: June 6, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.1-2_Minor_Aquifers.mxd

<<<PAGE 185>>>

- 68
- 67
60
69
-66
70
- 65
59
-64
58
• 63
56
55
• SATSUMA
72-
71
105
80
79
77
114-
78
76
123
102
85
84
1537
120
83
103
* 101
82
100 99
92
122
94
121
115
- 104
~ 95
125
- 106
97
93
15
119—
Harris
124
118—
107
- 98
•13
91
57
117-
L 109
- 108
90-
45-
26
- 110
89
87
44-
/25
22
116
-111
88
86
24
17
23
- 112
38-
16
10
14
12
0 LO
- 113
81
37
36
Waller
75—
74-
73-
EAST HOUSTON
Harris
Fort Bend
* Cross reference well ID number to Table 4.2.1-2
Public Water Supply Wells within Zone of
Potential Impact for public water system name.
9TH STREET
Environmental Assessment
•
Public Water Supply Well
• Proposed Magellan Pipeline Facility
Longhorn Pipeline Reversal
Texas
2-Year Capture Zone
• Existing Magellan Pipeline Facility
Figure 4.2.1-3a
0.5-Mile Fixed Capture Zone
- Longhorn Pipeline
Public Water Supply Wells
within Zone of Potential Impact
Orion Expansion Overland Spread
Sheet 1 of 4
County Boundary
0
3.5
7
10.5
= Miles
Prepared By: Atkins/19685
Scale: 1' = 3 mi
Job No.: 100019708
le: N:ClientsIM_NIMagellan_Midstream_Partnersl100019708lgeolfig_EA
Date: Jul 19, 2012
g 4.2.1-38-a PWo wells Longnorn.m.

<<<PAGE 186>>>

Washington
-INDUSTRY
126
• BUCKHORN
Waller
Fayette
Austin
Colorado
*Cross reference well ID number to Table 4.2.1-2
Public Water Supply Wells within Zone of
Potential Impact for public water system name.
Environmental Assessment
•
Public Water Supply Well
Proposed Magellan Pipeline Facility
Longhorn Pipeline Reversal
Texas
2-Year Capture Zone
Existing Magellan Pipeline Facility
Figure 4.2.1-3b
0.5-Mile Fixed Capture Zone
Public Water Supply Wells
Longhorn Pipeline
within Zone of Potential Impact
Orion Expansion Overland Spread
Sheet 2 of 4
County Boundary
3.5
7
10.5
= Miles
Prepared By: Atkins/19685
Job No.: 100019708
le: N:ClientsIM_NIMagellan_Midstream_Partners|1000 19708 geolfig_EA
Date: Jul 19, 2012

<<<PAGE 187>>>

Lee
Washington
Bastrop
- WARDA
Fayette
* Cross reference well ID number to Table 4.2.1-2
Public Water Supply Wells within Zone of
Potential Impact for public water system name.
Environmental Assessment
•
Public Water Supply Well
Proposed Magellan Pipeline Facility
Longhorn Pipeline Reversal
Texas
2-Year Capture Zone
Existing Magellan Pipeline Facility
Figure 4.2.1-3c
0.5-Mile Fixed Capture Zone
Longhorn Pipeline
Public Water Supply Wells
within Zone of Potential Impact
Orion Expansion Overland Spread
Sheet 3 of 4
County Boundary
0
3.5
10.5
Prepared By: Atkins/19685
= Miles
Job No.: 100019708
le: N:ClientsIM_NIMagellan_Midstream_Partners1100019708lgeolfig_EA
Date: Jul 19, 2012
9_4.2.1-3a-d_PWS wells_Longhorn.mx

<<<PAGE 188>>>

Blanco
Travis
< 134)
133-
CEDAR VALLEY
130
132
- 131
Hays
Bastrop
* Cross reference well ID number to Table 4.2.1-2
Public Water Supply Wells within Zone of
Potential Impact for public water system name.
Caldwell
Environmental Assessment
•
Public Water Supply Well
Proposed Magellan Pipeline Facility
Longhorn Pipeline Reversal
Texas
2-Year Capture Zone
Existing Magellan Pipeline Facility
Figure 4.2.1-3d
0.5-Mile Fixed Capture Zone
Longhorn Pipeline
N
Public Water Supply Wells
within Zone of Potential Impact
Orion Expansion Overland Spread
Sheet 4 of 4
County Boundary
3.5
7
10.5
- Miles
Scale: 1" = 3 mil
Job No.: 100019708
ile: N:ClientsIM_NIMagellan_Midstream_Partners|100019708 geolfig_EAl
Date: Jul 19, 2012
1g 4.2.1-sa-a Po wells Longnom.mx:

<<<PAGE 189>>>

Source data: Texas Commission on Environmental Quality (TCEQ)
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-1
Hydrography with
Surface Water Rights
per TCEQ Database
Prepared By: Atkins/13029
Scale:
Job No.: 100019708
Date: June 6, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-1_Water_Rights_TCEQ.mxd

<<<PAGE 190>>>

Source data: Texas Commission on Environmental Quality (TCEQ)
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-2
Hydrography with
STORET Stations
Prepared By: Atkins/13029
Scale:
Job No.: 100019708
Date: June 6, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-2_STORET_Stations.mxd

<<<PAGE 191>>>

GS-6
Seg ID: 1006J
Seg ID: 1006D
Seg ID: 1007R
" )17
" )16
" )15
" )14
Seg ID: 1006B
" )13
" )12
! .
" )11
MESA ROAD
" )10
" )9
Seg ID: 1006I
Seg ID: 1006
" )8
" )7
" )4
" )5 " )6
" )3
" )2.31
! .
EAST HOUSTON
Seg ID: 1007R
Seg ID: 1016
Seg ID: 1006H
Seg ID: 1006F
Seg ID: 1006
Seg ID: 1006
9TH STREET
! .
Grimes
Montgomery
Waller
Harris
Fort Bend
Liberty
Chambers
Chambers
Galveston
Brazoria
I
0 1 2
Miles
! . Facilities Magellan Pts
Railroads
Impaired Streams 2008
# 0 Magellen Mile Post
Existing Magellen Pipeline
Seg ID: 1007R
!
!
County Line
Overland Spread
City Limits
!
!
Seg ID: 1006
! .
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-3
Houston Area TMDLs
Prepared By: Atkins/13029
Scale: 1" = 1.5 miles
Job No.: 100019708
Date: Apr 10, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-3_Houston_TMDL.mxd

<<<PAGE 192>>>

Seg ID: 1009
" )49
" )48
" )47
" )46
" )45
" )44
" )43
Brazos San Jacinto
Grimes
Washington
Waller
Austin
Colorado
Montgomery
Harris
Fort Bend
Wharton Brazoria
I
0 1 2
Miles
Seg ID: 1009E
Seg ID: 1016
Seg ID: 1017
" )42
" )41
" )40
" )39
" )38
" )37
" )36
" )35
" )34
! .
" )33
" )32
" )31
" )30
SATSUMA
" )29
JERSEY VILLAGE
Jersey Village
Houston
HOUSTON
Seg ID: 1014E
! . Facilities Magellen Pts
Railroads
Impaired Streams 2008
# 0 Magellen Mile Post
Existing Magellen Pipeline
County Line
!
!
!
Overland Spread
City Limits
!
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-4
Satsuma Area TMDLs
Prepared By: Atkins/13029
Scale: 1" = 2 miles
Job No.: 100019708
Date: Apr 10, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-4_Satsuma_TMDL.mxd

<<<PAGE 193>>>

Seg ID: 1429B
Seg ID: 1428
" )179
" )178
" )177
" )176
" )175
! .
" )174
" )173
" )172
WEST EDWARDS AQUIFER
" )171
" )170
" )169
" )168
" )167
! .
" )166
" )165
EAST EDWARDS AQUIFER
" )164
" )163
" )162
" )161
" )160
" )159
" )158
" )157
" )156
" )155
" )154
" )153
" )152
" )151
" )150
" )149
Seg ID: 1427A
Burnet
Blanco
Williamson
Travis
Hays
Caldwell
Comal
Milam
Lee
Bastrop
Fayette
I
0 1 2 3
Miles
! . Facilities Magellen Pts
Railroads
Impaired Streams 2008
# 0 Magellen Mile Post
Existing Magellen Pipeline
County Line
!
!
!
!
Overland Spread
City Limits
Water Supply API TCEQ
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-5
Austin Area TMDLs
Prepared By: Atkins/13029
Scale: 1" = 3 miles
Job No.: 100019708
Date: Apr 10, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-5_Austin_TMDL.mxd

<<<PAGE 194>>>

Pedernales State Park
Water Intake
Pedernales State Park
API Zone
" )202
" )201
" )200
" )199
! .
EAST PEDERNALES RIVER
" )198
" )197
Pipeline
Crossing
Lake Travis
API Zone
" )196
" )195
" )194
" )193
" )192
" )191
Llano
Burnet
I
Gillespie
Kendall
Blanco
Comal
Hays
Williamson
Travis
Caldwell ! A # 0 Public Water Supply Water Intake
! . Magellan Facility
Magellan Pipeline Existing Mile Post
Existing Magellan Pipeline
API Boundary
Longhorn Overland Spread
! !
!
!
!
City Limit
Subwatershed Boundary
0 1 2
Miles
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-6
Pedernales Falls State Park API
Prepared By: Atkins/19685
Scale: 1" = 1 mi
Job No.: 100019708
Date: Apr 10, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-6_API_PedernalesFallsSP.mxd

<<<PAGE 195>>>

Llano
Gillespie
Kendall
Burnet
Williamson
Travis
Blanco
Hays
Comal
Caldwell p o
Public Water Supply Water Intake
Stream
River
Existing Pipeline
I
Major Road
Road
API Boundary
Water Body
0 1 2
Miles
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-7
Pipeline Crossings within
Pedernales Falls State Park API
Prepared By: Atkins/19685
Scale: 1" = 1 mi
Job No.: 100019708
Date: Apr 10, 2012
N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-7_API_PedernalesFallsSP_PipelineXing.mxd

<<<PAGE 196>>>

Rank Stream Crossing for Importance
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.2.2-8
Surface Water Vulnerability
Methodology Flow Chart
Prepared By: Atkins/13188
Scale: N/A
Job No.: 100019708
Date: June 22, 2012
File: N:\Clients\M_N\Magellan_Midstream_Partners\100019708\geo\fig_EA\
Fig_4.2.2-8_Flow_Diagram.mxd

<<<PAGE 197>>>

" )450
# 0
" )400
# 0
" )350
# 0
I
0 50
Miles
" )300
# 0
" )250
# 0
" )200
# 0
" )150
# 0
# 0 Mile Post
Gulf Prairies
Overland Spread Longhorn
High Plains
Longhorn Pipeline Existing
Piney Woods
ECO Regions
Post Oak Savanah
Blackland Prairie
Cross Timbers
Edwards Plateau
Rolling Plains
South Texas Plains
Trans-Pecos
" )100
# 0
" )50
# 0
Environmental Assessment
Longhorn Pipeline Reversal
Figure 4.3.1-1
ECO Regions
Prepared By: Atkins/13029
Scale: 1" = 50 miles
Job No.: 100019708
Date: Apr 26, 2012
N:\Clients\M_N\Mag_Mid_Part\100019708\geo\fig_EA\Fig_4.3.1-1_ECO_Regions_Longhorn.mxd

<<<PAGE 198>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 4
APPENDICES

<<<PAGE 199>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 4A
HIGHWAY AND RAILROAD CROSSINGS

<<<PAGE 200>>>

Appendix 4A
Highway and Railroad Crossings – LONGHORN PIPELINE
Harris County –I-610, Union Pacific Railroad (14), US Hwy 90, Mesa Dr. (E. Houston
Dyersdale Rd.), US Hwy 59, Hardy Toll Road (2), I-45, Veterans Memorial Dr. (State Hwy
261), Burlington Northern Santa Fe Corporation Railroad, Sam Houston Pkwy (2), SH Beltway
8, US 290 Frontage, US Hwy 290, SH 6.
Waller County – FM 362, FM 359, FM 1887.
Austin County – FM 331, SH 159, FM 1456, Burlington Northern Santa Fe Railroad, SH 36,
FM 2754, FM 2502, FM 109, FM 1457, FM 389.
Fayette County – SH 237, FM 1291, FM 2145, US 77, FM 448Union Pacific Railroad.
Lee County – None Crossed
Bastrop County – FM 2104, SH 71, Union Pacific Railroad, SH 304, FM 20, SH 21.
Travis County – SH 130, FM 973, FM 812, US 183, I-35, Loop 275 (S. Congress Ave.), Union
Pacific Railroad, FM 2304 (Manchaca Rd.), Loop 1 (S. Mopac Expressway/SH 1), FM 1826, US
290.
Hays County – FM 12.
Blanco County – Park Road 6026, US 281, FM 1323, FM 1320.
Gillespie County – FM 1323, SH 16, FM 965, FM 2323.
Llano County – None crossed.
Mason County –US 87, FM 783, FM 1871.
Kimble County –US 377, US 83, FM 2291.
Menard County – FM 1674.
Schleicher County –FM 864, FM 2596, US 277, US 190, FM 1828.
Crockett County – SH 163.
Reagan County – SH 137, FM 1676, Texas Pacifico Transportation Limited Railroad, South
Orient Railroad, US 67, FM 1555.
Upton County – State Highway 349, State Highway 329 (2).
Crane County – US 385

<<<PAGE 201>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 4B
BIOLOGICAL ASSESSMENT

<<<PAGE 202>>>

Phase 1 Biological Assessment
February 14, 2000

<<<PAGE 203>>>

HJN 990144
BIOLOGICAL ASSESSMENT
LONGHORN PIPELINE PROJECT
MAINTENANCE ACTIVITIES
AND MINOR CONSTRUCTION
HOUSTON TO CRANE, TEXAS
Prepared For:
Longhorn Partners Pipeline, L.P.
US Environmental Protection Agency
Region 6
US Department of Transportation
Office of Pipeline Safety
Prepared By:
Horizon Environmental Services, Inc.
Austin - Beaumont - Houston - Shreveport
February 14, 2000
990144BA.v-6
- 2/14/2000

<<<PAGE 204>>>

TABLE OF CONTENTS
Section
Page
1.0
INTRODUCTION.
.1
2.0
PROJECT OVERVIEW.
.7
3.0
EXISTING ENVIRONMENT...
...9
3.1
GENERAL...
.9
3.2
VEGETATION........
..9
3.2.1 Gulf Prairies and Marshes Vegetational Area.
...9
3.2.2 Post Oak Savannah Vegetational Area...
12
3.2.3 Blackland Prairies Vegetational Area ...
.12
3.2.4 Edwards Plateau Vegetational Area.......
..13
3.2.5 The Trans-Pecos, Mountains and Basins Vegetational Area...
..13
3.3
WILDLIFE..............
..14
3.3.1 Austroriparian Biotic Province
..14
3.3.2 Texan Biotic Province.
..14
3.3.3 Balconian Biotic Province
..16
3.3.4 Kansan Biotic Province..
16
3.3.5 Chihuahuan Biotic Province
..16
3.4
THREATENED AND ENDANGERED SPECIES
17
4.0
PROJECT DESCRIPTION...
.37
4.1
RIGHT-OF-WAY CLEARING AND MARKING.
.37
4.2
PIPELINE MAINTENANCE-CONSTRUCTION PLANNING.
39
4.3
PROJECT ENVIRONMENTAL INSPECTORS
45
4.4
SITE PREPARATION.........
45
4.5
SITE ENTRY.......
..46
4.6
PIPELINE LOWERING AND/OR REPLACEMENT - OPEN TERRAIN
47
4.7
PIPELINE LOWERING AND/OR REPLACEMENT - CREEK CROSSINGS
51
990144BA.v-6
- 2/14/2000

<<<PAGE 205>>>

4.8
TRENCHING...
.51
4.9
BORING..
4.10
HYDROSTATIC TESTING - OVERVIEW OF ACTIVITIES
4.11 HYDROSTATIC TESTING - POTENTIAL FAILURE OF PIPELINE.
4.12 CATHODIC PROTECTION ENHANCEMENTS
4.13 SURGE PRESSURE PROTECTION
4.14 INVESTIGATIONS........
59
5.0
POTENTIAL IMPACTS (TAKE) AND COMPENSATION.
60
5.1
SPECIES-BY-SPECIES IMPACT ANALYSIS
64
5.2
AVOIDANCE AND MINIMIZATION
69
5.3
PROPOSED COMPENSATION FOR POTENTIAL TAKE
71
6.0
REFERENCES...................
............77
990144BA.v-6
2/14/2000

<<<PAGE 206>>>

LIST OF FIGURES
Figure
Page
1
LOCATION MAP ......
10
2
VEGETATIONAL AREAS OF TEXAS TRAVERSED BY THE
LONGHORN PIPELINE
11
3
BIOTIC PROVINCES OF TEXAS TRAVERSED BY THE
LONGHORN PIPELINE
15
4 - 12
AREAS OF FEDERALLY LISTED, THREATENED, OR
ENDANGERED SPECIES TRAVERSED BY THE LONGHORN
PIPELINE - HOUSTON TO CRANE .
..22-30
LIST OF TABLES
Table
Page
1
FEDERALLY LISTED THREATENED OR ENDANGERED
SPECIES WHICH OCCUR IN COUNTIES TRAVERSED BY THE
LONGHORN PIPELINE -HOUSTON TO CRANE
18
2
2000 MAINTENANCE CONSTRUCTION, TESTING AND
CLEARING, LONGHORN PIPELINE ..
40
3
ROW CLEARING AND ADDITIONAL MAINTENANCE
CONSTRUCTION IMPACTS - LONGHORN PIPELINE -
HOUSTON TO CRANE.
62
4
LONGHORN PIPELINE TAKE COMPENSATION
|.........75
APPENDIX
PROJECT DOCUMENTATION APPENDIX
ACCOMPANYING DOCUMENT
990144BA.v-6
2/14/2000

<<<PAGE 207>>>

1.0 INTRODUCTION
This Biological Assessment (BA) is prepared in connection with the draft
Environmental Assessment of the Longhorn Pipeline owned by Longhorn
Partners Pipeline, L.P. (Longhorn). That Environmental Assessment was the
product of a settlement reached in the matter of Spiller, et al v. Walker, et al
pending in the United States District Court in Austin, Texas. The plaintiffs in that
lawsuit alleged failure on the part of numerous federal agencies to adequately
analyze the potential environmental impacts of the Longhorn Pipeline. Though
the federal defendants and Longhorn denied the plaintiffs' allegations, the parties
reached a negotiated settlement that was approved by the Court on March 5,
1999. Parties to that settlement included Longhorn, the US Environmental
Protection Agency (EPA), the US Department of Transportation (DOT), the US
Department of Justice, the City of Austin, the Lower Colorado River Authority,
and the remaining plaintiffs.
As part of that Court ordered settlement, the agencies involved in the
original litigation were required to conduct an Environmental Assessment,
including specific consideration of species protected under the Endangered
Species Act (ESA). The Court ordered EPA and DOT, acting as Lead Agencies,
to be responsible for the Environmental Assessment, and ordered the
Department of Army to act as a cooperating agency. A draft Environmental
Assessment, with a preliminary Finding of No Significant Impact (FONSI), was
prepared by Radian International LLP at the direction of and pursuant to a work
plan approved by the Lead Agencies. As a result of the Environmental
Assessment, and with the support of the Lead Agencies, Longhorn has
committed to implement a slate of 34 pipeline mitigation measures. (The pipeline
mitigation measures are identified and described in the Longhorn Mitigation Plan
included in the accompanying Project Documentation Appendix at Tab 2). The
pipeline mitigation measures focus on two general areas: first, the enhancement
of pipeline integrity to reduce the probability of a pipeline release and to reduce
risks to pipeline integrity, and second, enhancement of emergency response
capability and development of plans for corrective action in the unlikely event of a
pipeline release. Both categories of pipeline mitigation measures are discussed
below in greater detail in Section 4.0, Project Description.
990144BA.v-6
- 2/14/2000

<<<PAGE 208>>>

Pursuant to Section 7 of the ESA, the Lead Agencies have requested
consultation with the US Fish and Wildlife Service (the Service) regarding the
Draft Environmental Assessment and the package of pipeline mitigation
measures upon which the Lead Agencies' preliminary FONSI is predicated. In
connection with the inter-agency consultation, Longhorn prepared and submitted
to the Service a draft BA on the entire pipeline project on September 27, 1999.
The Service responded to the September draft BA with comments and requests
for additional information in the form of a letter to Horizon Environmental
Services, Inc., dated December 15, 1999 (the Comment Letter - see
accompanying Project Documentation Appendix at Tab 12).
On February 3, 2000, the Lead Agencies designated Longhorn has a non-
federal representative for the purpose of consultation with the Service and
preparation of a BA on the Longhorn project.
The Spiller Court's order provides that issuance of any FONSI with regard
to the Longhorn project "shall be conditioned upon implementation" of measures
to protect public safety and the environment. Settlement Stipulation at 6. The
order also prohibits the DOT from authorizing Longhorn to commence operations
until Longhorn has implemented those mitigation measures upon which the
FONSI is conditioned. Settlement Stipulation at 7. The order contemplates that
Longhorn will apply for, and accept, such ESA permits as may be required in
connection with the implementation of any mitigation measures upon which a
FONSI may be conditioned. Id.
The results of this consultation by the Lead Agencies with the Service are
expected to be incorporated in the Record of Decision issued by the Lead
Agencies. If the Lead Agencies issue an EA/FONSI, the terms and conditions,
mitigatory measures and protections incorporated herein for the benefit of
species will be adopted and incorporated by Longhorn in its operating and
maintenance manuals submitted to, and enforceable by, DOT pursuant to the
Pipeline Safety Act (49 U.S.C. §60101, et seq.) or the Longhorn mitigation
commitments.
The Office of Pipeline Safety (OPS) administers DOT's regulatory program
to ensure the safe transportation of various hazardous liquids by pipeline under
990144BA.v-6
2
- 2/14/2000

<<<PAGE 209>>>

the Pipeline Safety Act. OPS is responsible for inspecting pipelines before they
are placed in service to ensure that they are in accordance with DOT's
regulations and are being operated safely. The OPS's published statement of its
authority is set out below:
The Department of Transportation's (DOI) Research
and
Special Programs
Administration (RSPA),
acting
through
the
Office
of Pipeline Safety
(OPS), administers
the Department's
national
regulatory
program
assure
the
safe
other
transportation of natural gas, petroleum, and
hazardous
materials
by pipeline. OPS
develops regulations and other approaches to risk
management
assure safety in
design,
construction,
testing,
operation,
maintenance,
emergency response of pipeline
facilities.
Although the Service and the Lead Agencies are in consultation with
respect to the entire proposed Longhorn Project, this consultation is being
approached in two distinct, yet related phases'. The first phase of the
consultation (Phase I) relates to pipeline maintenance, pipeline testing and the
first category of measures that Longhorn will take to fulfill its commitment to
ensure pipeline safety and integrity. These measures focus on pipeline integrity
enhancements such as a number of pipe replacements, lowering of some
sections of pipe, investigation of possible pipe flaws, hydrostatic pressure testing,
and similar actions.
The second phase of the consultation (Phase I) will be more directly
related to the actual operation of the pipeline, specifically the operation and
maintenance of the pipeline system and the potential effects of the unlikely event
of a pipeline release. Additional mitigation measures, such as internal pipeline
inspections and construction in two particular areas, also will be addressed in
Phase II. Those areas are (a) Houston toad habitat and (b) areas of potential
effect to the Barton Springs Salamander over the Edwards Aquifer Recharge
Zone. A two-stage consultation offers the most protection to the species,
because the second phase will benefit from and build upon species information
gathered in the first stage of review, while allowing the most efficient route to
402.14(k) provides a mechanism for the Service to review a project, and provide biological opinions on each
U.S. Fish and Wildlife regulations allow for a staged consultation. 50 C.F.R § 402.14(k). Section
incremental step.
990144BA.v-6
- 2/14/2000

<<<PAGE 210>>>

startup of the pipeline.
The Spiller settlement specifically contemplates that Longhorn will
undertake certain construction and maintenance activities prior to issuance of a
final agency decision in this matter. Settlement Stipulation at 8-11. The parties to
the settlement specifically agreed that any such investments by Longhorn in
Kimble, Menard, Hays, Travis, Caldwell, Bastrop and any counties within the
jurisdiction of the LCRA after August 25, 1998 would not be considered "for the
purposes of determining the reasonableness of alternatives" (Settlement
Stipulation at 11), meaning that these investments would not constitute
irretrievable commitments of resources for the purposes of the National
Environmental Policy Act or Section 7(d) of the ESA.
Phase I of the consultation focuses on near-term discrete tasks that are
requisite preliminary activities-tasks that Longhorn must complete before it can
place the pipeline into operation, such as right-of-way clearing and pipeline safety
mitigation measures. They will be implemented in a manner that avoids and
minimizes potential effects upon species and habitat.
Phase II of the consultation will focus on long-term programmatic
activities, operation and maintenance of the pipeline, and the possibility of an
emergency response. These activities are either (a) not necessarily discrete or
(b) not precisely estimable before the fact. Phase II activities carry different risks
from Phase I activities. For example, the operation and maintenance activities
are ongoing and long-term. Further, though the probability of a pipeline release
will be minimized as a result of the Longhorn Mitigation Plan, should a release
occur, it has the potential to result in adverse effects to species and habitat at
locations and of magnitudes that are difficult to predict with precision.
Nevertheless, because of the low risk of such a release and the comprehensive
nature of the Longhorn Mitigation Plan, Longhorn and the Lead Agencies believe
that it is appropriate to conclude that there is a reasonable likelihood that the
entire project is not likely to jeopardize the continued existence of any
endangered or threatened species or result in the destruction or adverse
modification of critical habitat. This is because the Phase I review is being
conducted against the backdrop of a larger mitigation package, which the Service
has had an opportunity to review. The Service had an opportunity to review and
990144BA.v-6
4
- 2/14/2000

<<<PAGE 211>>>

comment on the entire project based upon the September draft BA.
The two phases thus can be logically separated. Phase I of the Service's
review (this BA) will focus on those actions that are designed to make the
pipeline safer. The Service can complete this stage of review without pre-judging
whether or not the pipeline will be used. Phase II of the Service's review will
focus on whether and how the pipeline will be used. The Phase I procedures are
routine in the US pipeline industry, during operation, for periodic maintenance,
testing and repair of hazardous liquids and gas pipelines. However, to ensure
that the pipeline is safe, the Longhorn Mitigation Plan specifies that these
activities shall be conducted prior to startup of the Longhorn Pipeline under its
proposed use.
This BA encompasses Phase I of the consultation. Included in this phase
are maintenance of the pipeline right-of-way; maintenance construction to
replace and/or lower certain segments of the pipeline, along with investigation
and repair of possible flaws in the pipe at an identified number of locations;
enhancements to the pipeline cathodic protection system; and hydrostatic
pressure testing of the pipeline to ensure the integrity of the pipe for its intended
service. None of these activities constitutes an irreversible or irretrievable
commitment of resources, natural or monetary, which have the effect of
foreclosing the formulation or implementation of any reasonable and prudent
alternative measures.
This BA is provided to facilitate a formal Section 7 consultation between
the EPA, the DOT, and the Service to evaluate the potential for adverse effects
to listed species resulting from activities related to the implementation of pipeline
mitigation measures to improve pipeline integrity and thereby enhance pipeline
safety. Those pipeline mitigation measures are referred to hereafter in this BA as
projects. The specific maintenance and testing projects to be implemented are
described in detail in Section 4.0 of this BA.
Where appropriate, this BA generally comports with EPA Guidelines for
Ecological Risk Assessment. See Guidelines for Ecological Risk Assessment, 63
Fed. Reg. 26,846 (1998). For example, EPA guidelines suggest that a suitable
990144BA.v-6
5
- 2/14/2000

<<<PAGE 212>>>

assessment approach will identify the explicit, ecologically relevant expressions
of environmental value that are to be protected. See 63 Fed. Reg. at 26,858. To
that end, the BA guides project development, in part, by identifying particular
species of concern within the project area, and suggesting mitigation efforts
which will minimize exposure and impact to those species. Where uncertainty
has been encountered, doubt has been resolved in favor of the species, and in
this regard, the results of a precise application of EPA Guidelines have likely
been exceeded. Precise application of the Guidelines would likely reveal far
fewer areas of ecological sensitivity than have been assumed.
990144BA.v-6
6
• 2/14/2000|

<<<PAGE 213>>>

2.0
PROJECT OVERVIEW
Longhorn proposes to operate a 723-mile refined petroleum products
pipeline system from the GATX Terminal in Galena Park, Texas, to a refined
petroleum products terminal in El Paso, Texas. The pipeline also has a 28-mile
intermediate connection from a station in Crane County to a planned meter
station in Odessa, Texas. The pipeline consists of a combination of 20-inch and
18-inch diameter pipe from Galena Park Station to El Paso Terminal and an 8-
inch diameter pipeline from a station in Crane County to a meter station in
Odessa, Texas. Finally, three as yet to be built pipelines will connect the El Paso
terminal to interstate common carrier pipelines west of El Paso. The pipeline's
initial capacity of 72,000 barrels per day (bpd) will be supplied by a new pump
station at Galena Park and five newly constructed booster pump stations at the
following locations: Satsuma (Harris County), Cedar Valley (Hays County),
Kimble County (Kimble County), Crane (Crane County), and El Paso (El Paso
County).
Two new pipeline construction projects remain to be completed. An 8-inch
diameter, 2500-foot lateral that originates at the terminus of the existing Odessa
lateral will connect to a terminal facility in Odessa, Texas, owned by Equilon.
Three 8.3-mile lateral pipelines, which originate at the El Paso Terminal, will
connect with Kinder Morgan (formerly the Santa Fe Pacific pipeline) and Chevron
pipelines in the El Paso area. The connection to Kinder Morgan will consist of
one 8-inch diameter pipeline and one 12-inch diameter pipeline. The Chevron
connection will consist of an 8-inch diameter pipeline. The purpose of the lateral
pipelines is to connect into Kinder Morgan and Chevron pipelines to distribute
product into the Phoenix, Tucson, and Albuquerque (New Mexico) markets.
Chevron operates an 8-inch pipeline that delivers product to the Albuquerque
market; Kinder Morgan operates one 12-inch pipeline and one 8-inch pipeline
serving the Tucson market. Other Kinder Morgan pipelines connect Tucson to
the Phoenix market.
The proposed project includes both new construction and refurbishment of
990144BA.v-6
7
- 2/14/2000

<<<PAGE 214>>>

an existing pipeline that has been converted from its former use of transporting
crude oil from West Texas to the Gulf Coast area, the majority of which is
complete. As described in this chapter, the existing pipeline has been modified
to transport refined petroleum products, with flow going from east to west.
Williams Pipeline Company (later to become part of Williams Energy Services)
will be the contract operator of the Longhorn Pipeline System. Longhorn intends
to transport multiple grades of gasoline and distillates, which will include special
reformulated grades of gasoline needed to control air emissions in certain areas
of the Southwest.
The Longhorn Pipeline System is designed for service in excess of 50
years and is made up of four main pipeline segments, several stations, and one
terminal, as listed below:
• New and refurbished 20-inch diameter pipeline from Galena Park
Station to Satsuma Station
• Refurbished 18-inch diameter pipeline from Satsuma Station to Crane
Station
New 18-inch diameter pipeline from Crane Station to El Paso Terminal
New lateral pipeline connections to Odessa and to other pipelines at El
Paso
• New Pump Stations
• El Paso Terminal
• Odessa Meter Station
A detailed description of the Longhorn Pipeline System is included in the
Longhorn Pipeline Project Description section of the accompanying Project
Documentation Appendix at Tab 1. More detailed descriptions of the project
components that are subject to this BA are included in Section 4.0. Future
pipeline upgrades, repairs, and maintenance beyond that identified in this
document will be addressed in Phase II of the consultation.
990144BA.v-6
8
- 2/14/2000

<<<PAGE 215>>>

3.0
SEXISTING ENVIRONMENT
3.1
GENERAL
The Longhorn Pipeline traverses the State of Texas from east to west
originating in east Houston, Harris County and extending westward to Crane
Station, Crane County (Figure 1). Auxiliary lines extend from Crane Station
northward to Odessa and westward to El Paso in far west Texas. The area
traversed by the pipeline varies physiographically from flat or rolling coastal
prairie in the Houston region to hilly woodlands of the Edwards Plateau in central
Texas to the xeric Permian Basin region of west Texas.
3.2
VEGETATION
From east to west, the Longhorn Pipeline traverses the Gulf Prairies and
Marshes, Post Oak Savannah, Blackland Prairies, Edwards Plateau, and Trans-
Pecos, Mountains and Basins Vegetational Areas (Gould, 1975; Figure 2). The
following provides a summary description of each ecological region.
3.2.1 Gulf Prairies and Marshes Vegetational Area
This ecological region, approximately 9.5 million acres in extent, is divided
into the Coastal Prairie and Gulf Coast Marshlands. The Coastal Prairie is a
nearly level plain less than 150 feet above mean sea level (MSL) and dissected
by streams and rivers flowing into the Gulf of Mexico while the Gulf Coast
Marshlands are limited to narrow belts of low wet marsh immediately adjacent to
the coast and along waterways. Surface soils are acid sands, sandy loams, and
clays with low permeability and droughty in nature. Annual precipitation
averages from 20 inches in the west to 50 inches in the east (Gould, 1975).
The climax vegetation is largely grassland or post oak savannah (Gould,
1975). Ranches and rangelands are interspersed by farms. Most of the marsh
areas are grazed by cattle within large land holdings.
990144BA.v-6
9
- 2/14/2000

<<<PAGE 216>>>

MARILO Coo
Oklahoma
Mexico
New
LuBBOCK
• Т корт орт райм
Louisiana
ODESSA
MIDLAND
SAN ANGELO
Mexico
Mexico
DEL RIO
LAREDO
Mexico
Gulf of
- Longhor Refined Products Pipeline
for far:
2003
• 7i21
No.
FIGURE I
NOT TO SCALE
LONGHORN PIPELINE
LOCATION MAP
MAP SOURCES:
TEXAS NATURAL RESOURCE INFORMATION SYSTEM
LONGHORN PIPELINE

<<<PAGE 217>>>

Longhorn Refined Products Pipeline
10
MEXICO
GULF
VEGETATIONAL AREAS OF TEXAS
1. .
2.
Gulf Prairies and Marshes
Pineywoods
3.
4.
Post Oak Savannah
5.
Blackland Prairies
6.
South Texas Plains
Cross Timbers and Prairies
:50
8. Rolling Plains
7. Edwards Plateau
Mile
100
10. Trans-Pecos, Mountains and Basins
High Plains
Horizon
ENVIRONMENTAL SERVICES, INC.
FIGURE 2
LONGHORN PIPELINE
IN RELATION TO THE
Source:
Gould, 1975.
VEGETATIONAL AREAS OF TEXAS

<<<PAGE 218>>>

3.2.2 Post Oak Savannah Vegetational Area
This ecological region, approximately 8.5 million acres in extent, is
bordered by the Pineywoods region to the east and the Blackland Prairie region
to the west. The topography is gently rolling to hilly, and elevations range from
300 to 800 feet above mean sea level (MSL). Generally, surface soils of higher
elevations are light-colored, acidic sandy loams or sands while those of lower
elevations are darker, acidic sandy loams or clays. Annual precipitation
averages from 35 to 45 inches, and May or June is generally the high rainfall
month (Gould, 1975).
The Post Oak Savannah was historically dominated by prairie climax
grasses and scattered trees. The most prevalent trees were oaks and cedar elm.
The deterioration of the climax plant communities in the region is evidenced by
an increase of certain grass species, forb species, and woody species (Gould,
1975). Moderate to dense post oak dominated woodlands have developed in
many areas as a result of man's suppression of fire. The bottomland woodland
remains the most diverse vegetation type of this ecological area.
3.2.3 Blackland Prairies Vegetational Area
This ecological region, approximately 11.5 million acres in extent, includes
the San Antonio and Fayette Prairies. Land surface ranges in elevation from 300
to 800 feet, gently rolling to nearly level, and well dissected and rapidly drained.
Surface soils are fairly uniform, dark-colored calcareous clays
interspersed with gray acid sandy loams. Annual precipitation averages from 30
inches in the west to 40 inches in the east (Gould, 1975).
The climax native vegetation is true prairie (Gould, 1975). The majority of
this ecological area has been brought under cultivation. Farms are interspersed
among ranches and rangelands.
990144BA.v-6
12
- 2/14/2000

<<<PAGE 219>>>

3.2.4 Edwards Plateau Vegetational Area
This ecological region encompasses approximately 24 million acres in
west-central Texas. Land surface ranges in elevation from 100 to 3000 feet
above MSL, rough and well drained, and dissected by several river systems.
Surface soils are usually shallow and underlain by material ranging from
limestone or caliche to granite. Annual precipitation averages from 15 inches in
the west to over 33 inches in the east, and droughts are not uncommon (Gould,
1975).
The Edwards Plateau Vegetational Area is predominantly rangeland
(Gould, 1975). Bottomland areas of this ecological area having deeper soils
have been brought under cultivation. Small farms are interspersed among
ranches and rangelands.
3.2.5 Trans-Pecos, Mountains and Basins Vegetational Area
This ecological region encompasses approximately 19 million acres of
mountains and arid valleys in extreme west Texas. Land surface ranges in
elevation from 2500 to over 8500 feet, rough and well drained, and dissected by
several river systems.
Surface soils have developed from out-wash materials from mountains,
varied in texture, calcareous, and some areas are alkaline due to poor drainage.
Surface conditions include stony hills, clay flats, sands, salty-saline soils, gypsum
flats, deep upland, rough stony mountains, gravelly outwash, and badlands
(Gould, 1975). The average annual precipitation for the area is less than 12
inches while higher elevations can range from 16 to 20 inches (Gould, 1975).
Cultivated areas are confined largely to irrigable valleys. The majority of
land is in large holdings as native range. Ranch operations include cattle, sheep,
and goats.
3.3
WILDLIFE
990144BA.v-6
13
- 2/14/2000

<<<PAGE 220>>>

From east to west, the Longhorn Pipeline traverses the Austroriparian,
Texan, Balconian, Kansan, and Chihuahuan Biotic Provinces described by Blair
(1950; Figure 3). The following provides a summary description of each biotic
province.
3.3.1 Austroriparian Biotic Province
This province includes the Gulf coast plain from the Atlantic to eastern
Texas. The western boundary of this province in Texas is along a line running
approximately north from western Harris County to western Red River County.
The pine and hardwood forest of the Austroriparian is limited to the west by
available moisture.
The vertebrate fauna of the Austroriparian Province in Texas is typical of
the species in the province to the east. At least 47 species of mammals occur in
this province in Texas. Some 29 species of snakes, 10 lizards, 2 land turtles, 17
anurans, and 18 urodels are known to occur in the Texas part of this province
(Blair, 1950).
3.3.2 Texan Biotic Province
This province is a transitional area and is recognized as a broad ecotone
between the forests of the Austroriparian and Carolinian provinces of eastern
Texas and Oklahoma, and the grasslands of the western parts of these states.
The integration of woodlands and grasslands within the region results in a
mixture of wildlife species typical of the 2 general habitats. The vertebrate fauna
of the Texan Biotic Province consists of at least 49 species of mammals,
16 lizards, 2 land turtles, 39 snakes, 18 anurans (frogs and toads), and
5 urodeles (salamanders, newts, etc.) (Blair, 1950). No endemic vertebrates are
known from the Texan Province.
990144BA.v-6
14
- 2/14/2000

<<<PAGE 221>>>

Kansan
Navahonian
Texan
Balconian
Chihuahuan
MEXICO
Tamaulipan
of
GULF
Longhorn Refined Products Pipeline
we 3 070€
50
100
Miles
Horizon
ENVIRONMENTAL SERVICES, INC
FIGURE 3
LONGHORN PIPELINE
IN RELATION TO THE
BIOTIC PROVINCES OF TEXAS

<<<PAGE 222>>>

3.3.3 Balconian Biotic Province
This province is synonymous with the Edwards Plateau and is a
physiographically discrete unit. The name Balconian is derived from the
Balcones Fault Zone which forms the southern and eastern boundaries of this
province.
The vertebrate fauna of the Balconian Biotic Province is a mixture of
species characteristic of surrounding major provinces, even though its
characteristic vegetation is distinctly different. The vertebrate fauna consists of
57 species of mammals, 16 lizards, 1 land turtle, 36 snakes, 15 anurans (frogs
and toads), and 7 urodeles (salamanders, newts, etc.) (Blair, 1950). There are
several endemic vertebrates known from the Balconian Biotic Province.
3.3.4 Kansan Biotic Province
This province is divided into 3 distinct biotic districts: the Mixed-grass
District, Mesquite Plains District, and Short-grass Plains District. All of these
biotic districts have areas of dune sand. Moisture is deficient throughout the
Kansan Biotic Province, and there is a decrease in available moisture from east
to west. The Short-grass Plains District occurs in the area of Crane, Texas.
The vertebrate fauna of the Kansan Biotic Province is a mixture of species
from each of its biotic provinces. The vertebrate fauna consists of 59 species of
mammals, 14 lizards, 1 land turtle, 31 snakes, 9 anurans (frogs and toads), and
14 urodeles (salamanders, newts, etc.) (Blair, 1950). There are 6 endemic
vertebrates known from the Balconian Biotic Province.
3.3.5 Chihuahuan Biotic Province
Within Texas, the Chihuahuan Biotic Province includes all of the Trans-
Pecos Texas except the Guadalupe Mountains in Culberson County. The
physiography of the province includes desert basins, mountains, and major
waterways and drainages. Even though the climate of most of the province in
Texas is arid and seriously deficient of moisture for plant growth, vegetational
communities are very diverse.
990144BA.v-6
16
- 2/14/2000

<<<PAGE 223>>>

The vertebrate fauna of the Chihuahuan Biotic Province is extremely
diverse and many of the same species can be found in both desert basin and
mountain areas. The vertebrate fauna consists of 83 species of mammals,
22 lizards, 1 land turtle, 38 snakes, 13 anurans (frogs and toads), and 1 urodele
(salamanders, newts, etc.) (Blair, 1950). There are 6 endemic vertebrates known
from the Balconian Biotic Province.
3.4
THREATENED AND ENDANGERED SPECIES
Horizon Environmental Services,
Inc. (Horizon) has performed
investigations along the existing Longhorn Pipeline right-of-way (ROW) and
vicinity from Houston to Crane for the possible occurrence of all federally-listed,
threatened, or endangered species which are known to exist in all counties of
Texas traversed by the Longhorn Pipeline (Table 1). Following investigation of
the species which potentially occur in these counties, several species were
identified for which there was a possibility of occurrence within the area of
potential effect for pipeline maintenance construction, routine ROW maintenance,
hydrostatic pressure testing, and the remaining integrity related activities. The
area of potential direct effects for the Phase I activities includes the immediate,
existing 50-foot wide ROW, and those additional construction specific adjacent
areas up to 100 feet either side of the ROW, and other areas that could
reasonably and foreseeably be affected by the subject pipeline maintenance,
construction, and testing activities (ie., hydrotest releases). No areas of indirect
effect are anticipated due to avoidance and minimization procedures.
A biological investigation was conducted along the pipeline ROW and
immediately adjacent lands to determine if these species and/or suitable habitat
were present within the area of concern. Horizon conducted habitat
assessments and survey efforts throughout April, May, and June 1999 from
990144BA.v-6
17
- 2/14/2000

<<<PAGE 224>>>

Kimble
18ULS1
Hays
x3321
0 0o
ste even are mercies
192282623002
Harris
30-92 САлЕрих ИЗ оласТЕЯ
Gillespie
3003
Henbanensi
Fayette
densitem
sida
Ector
2ovi
2233
Table 1: Federally-listed Threatened or Endangered Species which occur in counties traversed by Longhorn Pipeline
Crockett
epot linen
Crane
00г)
soys boons
state br
2005100228/008
nucol Sne
Blanco
Sub be sha
X - Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
xx
20000000 254 волар и 1610р
Source of Species: US Fish and Wildlife Service
Bastrop
PDL - Proposed to be De-listed
E - Listed Endangered
Austin
*
T - Listed Threatened
Species - Federal Classification
American alligator - TSA
Attwater's prairie-chicken - E
Barton Springs salamander - E
Bee Creek Cave harvestman - E
Bald eagle - T(PDL)
Black-capped vireo - E
Bone Cave harvestman - E
Clear Creek gambusia - E
Comal Springs dryopid beetle - E
Comal Springs riffle beetle - E
Devil's River Minnow - PE
Golden-cheeked warbler - E
Kretschmar Cave mold beetle - E
Navasota Ladies-tresses - E
Fountain darter - E
Houston toad - E
Interior least tem - E
San Marcos gambusia - E
San Marcos salamander - T
Texas blind salamander - E
Texas prairie dawn-flower - E
Tobusch fishhook cactus - E
Tooth Cave ground beetle - E
Tooth Cave pseudoscorpion - E
Texas snowbells - E
Texas wild-rice - E
Tooth Cave spider - E
Whooping crane - E

<<<PAGE 225>>>

Downstream
Waller
0 x
Upton
Travis
0 0 0=
Schleicher
Table 1: Federally-listed Threatened or Endangered Species which occur in counties traversed by Longhorn Pipeline
Reagan
Menard
Mason
X - Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
Source of Species: US Fish and Wildlife Service
Llano
PDL - Proposed to be De-listed
E - Listed Endangered
T - Listed Threatened
Lee
Species - Federal Classification
American alligator - TSA
Attwater's prairie-chicken - E
Barton Springs salamander - E
Bee Creek Cave harvestman - E
Bald eagle - T(PDL)
Black-capped vireo - E
Bone Cave harvestman - E
Comal Springs dryopid beetle - E
Clear Creek gambusia - E
Comal Springs riffle beetle - E
Kretschmarr Cave mold beetle - E
Devil's River Minnow - PE
Golden-cheeked warbler. - E
Navasota Ladies-tresses - E
Fountain darter- E
Houston toad - E
Interior least tem - E
San Marcos gambusia - E
San Marcos salamander - T
Texas blind salamander - E
Texas prairie dawn-flower - E
Tobusch fishhook cactus - E
Tooth Cave ground beetle - E
Tooth Cave pseudoscorpion - E
Texas snowbells - E
Texas wild-rice - E
Tooth Cave spider - E
Whooping crane - E

<<<PAGE 226>>>

Crane Station, Crane County, Texas to Highway 6 in Houston, Harris County,
Texas. The portion of the pipeline extending from Crane to El Paso is not subject
to this BA since none of the subject activities will apply to that pipeline segment
area. Species which potentially occur in or near waterways downstream of the
pipeline were assessed based on literature and agency file information. In 1998,
the Service concurred with Longhorn's conclusion that the project was not likely
to adversely affect species and habitat along the pipeline segment between
Crane and El Paso (a copy of the Service's concurrence is included in the
accompanying Project Documentation Appendix at Tab 13).
As indicated in Table 1, many species have been excluded from further
consideration due to Horizon=s determination that the activities are not likely to
adversely affect these species. S
Horizon's determination was based on
information regarding distribution of the various species obtained from various
published, agency file, or personal communication sources such as the Texas
Parks and Wildlife Department, the US Fish and Wildlife Service, recognized
experts for certain species, published species documentation, and published
reference books. Those species indicated by an AO@ in Table 1 have been
determined not likely to occur within the area of potential effect. Those additional
species indicated by an AM@ are migrants that would not likely be affected.
Species indicated by an AX@ are those determined by Horizon-s studies to occur
or possibly occur in the area of potential effect for present purposes. Those
species are addressed in more detail below and on attached maps.
Texas Prairie Dawn-flower (Hymenoxys texana)
Small, delicate annual to 6 inches tall with single or branching stems.
Small yellow flowers blooming in late March to early April. Occurs in sparsely
vegetated areas of fine-sandy compacted soil. Specifically, the species occurs in
the northern part of the Gulf Coastal Prairie, where it is found in poorly drained
depressions or saline swales around the periphery of low, natural mounds (mima
mounds) in open grasslands. These mostly barren areas are sparsely vegetated,
and the soil is often covered with a blue-green alga (Nostoc sp.). It can also
occur on disturbed soils such as rice fields, vacant lots, and pastures if the soil
structure remains relatively intact.
990144BA.v-6
20
- 2/14/2000

<<<PAGE 227>>>

An assessment of potentially suitable habitat for the prairie dawn was
conducted by Horizon in early June 1999 along the Longhorn pipeline ROW in
western Harris and eastern Waller counties from the Satsuma Station on the
west edge of Houston to near Monaville in Waller County. Three areas along the
ROW, one in Waller County and two in Harris County, exhibited native range
conditions with suitable soils that could be considered potentially suitable habitat
areas for the prairie dawn (Figures 4 to 12). All other areas along the pipeline
within the area investigated had been converted to row crop (corn), monoculture,
hay or grazing pasture, or disturbed for land development. A survey for the
prairie dawn has not been conducted within the potentially suitable habitat areas
to confirm its presence or absence. Longhorn will conduct a survey of the ROW
within the potential habitat areas in March of 2000 to determine if the prairie
dawn is present, and if so, its distribution and abundance.
Navasota Ladies-tresses (Spiranthes parksil)
The Navasota Ladies-Tresses (NLT) occurs primarily in moist, sandy soils
in small openings amongst Post Oak Savannah vegetation associated with the
Navasota, Brazos, and Trinity River drainages. The plant has previously been
found in Brazos, Burleson, Freestone, Grimes, Fayette, Leon, Madison, Jasper,
Robertson, and Washington counties. NLT are typically found on erosional
remnants between rills in slightly to moderately eroded areas along minor
intermittent tributaries of the Navasota, Brazos, and Trinity Rivers. NLT grows on
sandy loam soils and is often associated with post oak, blackjack oak, yaupon,
slender bigelowia (Bigelowia nuttallii), and Spiranthes cernua. The species has
also been recorded in open savannahs and shrublands that have experienced
little or no grazing pressure, and in hillside seepages.
990144BA.v-6
21
_ 2/14/2000

<<<PAGE 228>>>

Louisiana
FIGURE 4
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
SHEET LOCATION MAP
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
LONGHORN PIPELINE
Gulf of Mexico
FIGURE 5
HOUSTON
HARRIS
WALLER
FIGURE 6
AUSTIN
FIGURE 8
FAYETTE
FIGURE 7
RAVIST
AUSTIN
BASTROP
HAYS
FIGURE 10
LLANO
BLANCO
GILLESPIE
MASON
FIGURE 9
MENARD
KIMBLE
FIGURE 11
SCHLEICHER
12°
NOT TO SCALE
FIGURE
REAGAN
CROCKETT
LONGHORN REFINED PRODUCTS
APPROXIMATE CITY LOCATIONS FOR
Mexico
2: TEXAS NATURAL SUE 10197)
(http://www.tnris.state.tx.us/data__az.html),1998
UPTON
PIPELINE
REFERENCE
ECTOR
ODESSA
CRANE
CRANE
EXPLANATION
CRANE

<<<PAGE 229>>>

FIGURE 5
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
DT-20a(K)
DAWN-FLOWE!
HARRIS
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT Bufo houstonenses
GOLDEN-CHEEKED WARBLER
(Dendracia chrysoporio)
BAD CADAD MIRED
(SPOTA POES -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
ROSTER OTT
TEXAS PRAIRIE
-10
- CR-/
- SURGE 4
PIPELINE/
COUNTY BOUNDARY
199 HIGHMAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
HERBON AGAIN LOCATIONS
LONGHORN PIPELINE
ROADS
BRIDGES
CEMETERY
—I1P-2516 MANTENICE CONSTRUCTION
TEXAS PRAIRIE DAWN-FLOWER
WALLER
EXPLANATION
##### RAILWAYS
-
-50756-3
1.5
MILES
PINE ISLAND
4. TROT: HOREON SNORIN SE IS 1909AE
8. HORIZON MPONMONTAL SERMICES, INC, SITE BMESTIGATION (JIME 1990)
5 PER TO PASS ME PAL BED MIS PUNTS OF
159
2. RESOURCES ORATION SET 1700
2. TS NEH MOD BIA SONG 10D, OF TEAS
529
SON SAMS

<<<PAGE 230>>>

USTIN,
WASHINGTON
FIGURE 6
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
NAVASOTA LADIES-TRESSES
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Condo CO MARGUER
BAD CAPPED VIREO
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
257
OLDENBURI
- CR-1
- SURGE 4
EE HONY OR MANOR ROMOS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— LIP-2546 MICATONICE CONSTRUCTION
EXPLANATION
- SITE 6-3
NAVASOTA LADIES-TRES:
FAYETTE
MILES
6. HORIZON EIMIRONMENTAL SERNCES, INC, SITE IMMESTGATION (JUNE 1999)
* PONTES TREAD ELBERT MATE PUNTS OF
2. RESOURCES TORTON SISTEN 37/
2. TAS ABA MO BE SERE 1OED, OF TOUS.
LEE
SOURCES

<<<PAGE 231>>>

FIGURE 7
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
SES-TEAS
COLORADO
HOUSTON TOAD
(POTENTIAL HABITAT)
PIPE REPLACEMENT
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - POTENTIAL
HOUSTON TOAD
- DESIGNATED CRITICAL HABITAT
HABITA (Bufo houstonemsis)
BAD CARD VIRED
MAMOTAY POTS-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
-67-1
- SURGE 4
- HIGHWAY OR MAJOR ROADS
BASTROP®
— COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—4P-2516 LOCATTMNICE CONSTRUCTON
EXPLANATION
- SITE 6-3
INC, SITE INSTIGATION (JUNE 1999)
DED MATE PUNTS OF
BUT SERE TOES OF TOAS
1. TOAS NATURAL DE
3. DETERMATION OF CRITICAL
8. HORIZON EMIROMMENTAL SERMICES,
2. Tot COUNTY
4. THREATE P

<<<PAGE 232>>>

FIGURE 8
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
EDWARDS
HAYS
TRAVİS
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Tomotocette tok CTUs
SANSON POTS -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
ONTRIBUTING ZONE
-CR-/
- SURGE 4
DRIPPING
SPRINGS
HIGHWAY OR MAJOR ROADS
• COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
HENDER ANG PETON LOCATIONS
LONGHORN PIPEUNE
GOLDEN CHEEKED MA
RONDS
RAILWAYS
BRIDGES
CEMETERY
—LLP-2516 MANTEMANCE CONSTRUCTION
EXPLANATION
--
######
— SITE 6-8
SITE 6-
PEDES MESTICATIONS, F REGUME
PONCORD SPORES, OF TEUS
6. HORIZON DRONENTAL SERMCES, INC, SITE ESTIGATON (UNE 1999)
* POTES PRES LA SEPT ME FURTS OF
BLANÇO
ME SAMOS

<<<PAGE 233>>>

FIGURE 9
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
BLACK-CAPPED VIREO
BLANCO
• GOLDEN-CHEEKED WARBLER
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Taco Deto TobacTS
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-/
- SURGE 4
HIGHWAY OR MAJOR ROADS
WARBLER
- COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
MEMBER AS RATIN COCATIONS
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—LP-2516 MANTENNCE CONSTRUCTION
EXPLANATION
— SITE 6-3
Cool
PIPELINE
DIGORED SPECIES NESTIOMONS, EPPELME
ÇILLESPIE
3. OCTEPMATO, OE CEMEM, HA PS AR HT SIR RT
&. HORIZON EMIROMMENTAL SERVICES, MC, SITE INVESTIGATION (JUNE 1999)
SPORTED PRESSED FLOURE DET MIME PUNTS OF
2 TS TO ME BUT SAME TOE OF TENS
LLANO
SAT MATRA SEA
MAP SANCES
4. THREATEN HORROR

<<<PAGE 234>>>

ELINE
LIANO
FIGURE 10
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
E BLACK-CAPPED VIREO
y GOLDEN-CHÉEKED WARBLER
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOTTA TO NOLOTOROMENTAL
GILLESPIE
NAVASOTA LADIES-TRESSES
(Spironthes portsil)
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
LOVEY
CHERRY
2242
GOLDEN-CHEEKED WARBLER
- CR-/
- SURGE 4
COUNTY BOUNDARY
• HIGHWAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTERAMCE CONSTRUCTION
EXPLANATION
!
- S175 6-8
SITE
MASON
MC, SITE IMESTONOM (AME 1990)
DES OF TENS:
MILES
5 PRETE PASS ME UP DEPT ME RUNTS OF
ENTAL SERVES
PIPELINE
QURASS
MAR SOUPOSS
4. THREATENED OR DID
&. HORIZON

<<<PAGE 235>>>

-GILLESPIE
BLACK-CAPPED VIREO
FIGURE 11
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
MASON
0т-90 (K)
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT (Buto houstonensis)
MASOTA PORS-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-/
- SURGE 4
- COUNTY BOUNDARY
→ I HIGHNAY OR MOR ROADS
CITY STREETS -
RIVERS AND STREAMS
NTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— LLP-2546 MOCATIMANCE CONSTRUCTION
1-8 ALIS
SURGE 4.
871
EXPLANATION
иннинин
KIMBLE
- SITE 6-3
LONDON
TOBUSCH FISHHOOK CACTUS
3480 YATES
EACUP
POUNCERED SORDES oF TEMS.
6. HORIZON ENMRONMENTAL SERVICES, IMC., SITE IMVESTIGATION (JUME 1999)
SO PARCE PROTEST MADE PLANTS OF
MENARD
HAS SOURCES
I BEATENED OR EHDAN
2. THREATPNED AND

<<<PAGE 236>>>

BLACK-CAPPED VIREO
FIGURE 12
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
CACTÚS LOCATION
SITE 8-3
CPGB-s :
KIMBLE
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT (Bufo houstonents
COLDEN-CHEEKED WARBLER
Dendrocio chrysaparna
LAVASOTA LADIES-TRESSES
TOBUSCH FISHHOOK CACTUS
Spiranthes pantsi
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-1
- SURGE 4
MENARD
HEADER ANSARI LOCATIONS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
CITY STREETS
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTELANCE CONSTRUCTION
EXPLANATION
— SITE 6-2
B-8 JUIS
ANGERED SPECES, MISTATORS, EZ PROLAE
6. HORIZON EMRONMENTAL SERMCES, INC, SITE MESTONTOM (JUNE 1990)
5 PEAS TEE PRESIDE ST MINE PUNTS OF
2 RESOURCES TORMATION SITE 15P
ORVETT
SUTTON
SCHLEICHER
" Copperas
MAR SORCES
A THREATE

<<<PAGE 237>>>

In Fayette County, the species is known from one small population
approximately 6 miles south of the pipeline and 2 miles north of the town of
Fayette. Based on analysis of soil distribution, vegetative cover, physiographic
setting, and field assessment by Horizon in November of 1999, two small areas
of potential habitat for NLT are present along the pipeline corridor (Figures 4 to
12). No surveys for the species have been conducted along the pipeline.
Longhorn will conduct a Fall survey (15 October to 15 November, 2000) for this
species within the ROW if suitable climatic conditions occur to determine the
presence or absence of this species, and if present, its distribution and
abundance.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii)
Rounded, biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5
inches in diameter. There are 3 to 5 central spines with the upper 2 to 3 erect
and straight and the lower central spines hooked at the tip and spreading.
Occurs on limestone gravels of stream terraces, limestone ledges, ridges, and
openings on the rocky hills of live oak - juniper woodlands. The Tobusch
fishhook cactus has been documented in Kimble County. An assessment of
potentially suitable habitat and pedestrian survey for the cacti was conducted by
Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble
County, and no specimens were observed within the ROW. However, one
Tobusch fishhook cactus was observed approximately 50 feet north of the
cleared ROW (Figures 4 to 12). Longhorn will conduct a blooming period survey
(March to April 2000) within the ROW throughout Kimble County to determine the
species' distribution and abundance.
Houston Toad (Bufo houstonensis)
The Houston toad is 2.0 to 3.5 inches long with general coloration varying
from light brown to gray or purplish gray, sometimes with green patches. The
pale ventral (underneath) surfaces often have small dark spots. The toad is a
terrestrial amphibian associated with deep sandy soils within the Post Oak
Savannah vegetational area of east central Texas. The vegetation type of
currently known Houston toad sites can typically be described as pine or oak
990144BA.v-6
31
- 2/14/2000

<<<PAGE 238>>>

woodland or savannah, with native bunchgrasses and forbs (flowering plants)
present in open areas.
For breeding, including egg and tadpole development, Houston toads also
require still or slow-flowing bodies of water that persist for at least 30 days. The
source of ephemeral or permanent water should be located within one-half to
three-quarters miles of the toad=s hibernation/foraging habitat (deep sands
supporting woodland or savannah).
Critical habitat was designated for the Houston toad 31 January 1978, of
which a portion of Longhorn pipeline traverses through in Bastrop County
(Figures 4 to 12).
The Longhorn Pipeline ROW within the Houston toad Critical Habitat area
is immediately adjacent to the Phillips EZ Pipeline ROW which Horizon studied in
1991 for endangered species. As part of Horizon's studies, a Houston toad
survey was conducted along the EZ Pipeline corridor in 1991 by Dr. James R.
Dixon of Texas A&M University with negative results, although minor potential
habitat areas were noted (Horizon, 1991). Horizon conducted a reevaluation of
suitable habitat along the Longhorn Pipeline ROW within Bastrop County. The
field reconnaissance was conducted on 2 June 1999 from the Colorado River,
southeast of Bastrop, to FM 2104. Within the designated Critical Habitat,
portions of the area along the pipeline had been cleared and planted in improved
grasses. These areas were determined to be unsuitable for Houston toad
occupation.
Based on field observations, and confirmation by the Service, it was
determined that two areas of potentially suitable habitat existed along and
adjacent to the pipeline ROW. One area included Buescher State Park from
approximately 1/2 of a mile to the east of the eastern boundary of the park
westward to near Highway 71. The majority of this area contained a moderately
thick understory with all drainages flowing south toward the Colorado River.
The second area began approximately 500 feet to the west of FM 2104
and extended westward approximately 3/4 of a mile. This area contained two
stock tanks with the majority of the surrounding area exhibiting a moderately
990144BA.v-6
32
- 2/14/2000

<<<PAGE 239>>>

thick understory and pine re-growth. The drainages in this area also flowed to the
south toward the Colorado River.
One or more additional spring surveys (as acceptable to the Service) for
the toad will be conducted along and downstream of the pipeline to determine the
presence or absence of toads and their overall distribution and abundance.
Golden-cheeked Warbler (Dendroica chrysoparia)
The golden-cheeked warbler (GCW) is a small, migratory songbird, 4.5 to
5 inches long, with a wingspan of about 8 inches. The male has a black back,
throat, and cap, and yellow cheeks with a black stripe through the eye. Females
are similar, but less colorful. The lower breast and belly of both sexes are white
with black streaks on the flanks. Typical nesting habitat is found in tall, dense,
mature stands of Ashe juniper (cedar) mixed with trees such as Texas (Spanish)
oak, Lacey oak, shin (scalybark) oak, live oak, post oak, Texas ash, cedar elm,
hackberry, bigtooth maple, sycamore, Arizona walnut, escarpment cherry, and
pecan. This type of woodland generally grows in relatively moist areas such as
steep-sided canyons and slopes. A mix of juniper and deciduous trees on the
slopes, along drainage bottoms, and in creeks and draws provide an ideal mix of
vegetation for birds. Warblers are also occasionally found in drier, upland
juniper-oak (i.e. live oak, post oak, blackjack oak) woodlands over flat
topography.
An assessment of potentially suitable habitat and surveys for the GCW
was conducted by Horizon in April and May 1999 along the Longhorn pipeline
ROW from Austin, Texas, to the Mason/Kimble County line. Although no
potentially suitable habitat areas were observed within the Longhorn ROW,
several areas were located adjacent to the previously cleared permanent ROW.
All areas were surveyed by Horizon a minimum of 5 times during April and May
on days with favorable weather conditions for bird activity, per US Fish and
Wildlife Service guidelines (FWS, 1994). Surveys were conducted on 8, 9, 12,
27,28 April, and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres
were spent at each site, based on habitat size. No GCWs were found to be
utilizing any of the potentially suitable habitat areas on or immediately adjacent to
the ROW. One to two additional spring breeding season surveys (as acceptable
990144BA.v-6
33
- 2/14/2000

<<<PAGE 240>>>

to the Service) will be conduced for the GCW along and adjacent to the ROW
within the potential habitat areas to determine habitat utilization and overall
distribution and abundance.
Black-capped Vireo (Vireo atricapillus)
The black-capped vireo (BCV) is a 4.5 inch long, insect-eating songbird.
Mature males are olive green above and white below with faint greenish-yellow
flanks. The crown and upper half of the head is black with a partial white eye-
ring. The iris is brownish-red and the bill black. The plumage of the female is
duller than the male. Females have a dark slate gray head. In Texas, vireo
habitat is found on rocky limestone soils of the Edwards Plateau, Cross Timbers
and Prairies, eastern Trans-Pecos, and, to a limited extent, on igneous soils in
the Chisos Mountains. BCVs require shrub vegetation reaching to ground level
for nesting cover. They typically nest in shrublands.
An assessment of potentially suitable habitat and surveys for the BCV was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW
from Austin, Texas to Crane County. Potentially suitable habitat areas were
observed within the Longhorn ROW as well as several areas located immediately
adjacent to the previously cleared permanent ROW. All areas were surveyed by
Horizon a minimum of 5 times during April and May on days with favorable
weather conditions for bird activity, per US Fish and Wildlife Service guidelines
(FWS, 1994). Surveys were conducted on 8, 9, 12, 27, 28 April, and 3, 11, 19
May. An equivalent of 4 person-hours per 100 acres were spent at each site,
based on size. No BCVs were found to be utilizing any of the potentially suitable
habitat areas on or immediately adjacent to the ROW. One to two additional
spring breeding season surveys (as acceptable to the Service) will be conduced
for the BCV along and adjacent to the ROW within the potential habitat areas to
determine habitat utilization and overall distribution and abundance.
Bald Eagle (Haliaeetus leucocephalus)
The bald eagle is a migrant and winter resident in Texas. The bald eagle
was recently down-listed from endangered to threatened due to successful
conservation efforts and is now proposed for de-listing. Migrating and wintering
990144BA.v-6
34
- 2/14/2000

<<<PAGE 241>>>

bald eagles typically arrive in Texas in November and depart sometime in
February. They are found primarily in association with reservoirs, rivers or other
large bodies of water where they feed on fish, carrion, and waterfowl. Nesting
bald eagles in Texas are found in the eastern portion of the state and along the
coastal plain as far south as Calhoun and Refugio counties. No bald eagle nests
have been identified near the pipeline ROW, however, bald eagles may occur
along major waterways (Brazos and Colorado rivers, or major tributaries with
impoundments) downstream of the pipeline corridor.
The Federal Register, Volume 64 No. 128 (Tuesday, July 6, 1999; Page
36454) puts forth a proposed rule to remove the bald eagle from the List of
Threatened and Endangered Wildlife In the Lower 48 States of the United States
and de-listing is expected in the near future. The action is proposed because
available data indicates that the species has recovered.
Interior Least Tern (Sterna antillarum athalassos)
Premier nesting sites for the interior least tern are salt flats, broad
sandbars, and barren shores along wide, shallow rivers. Important breeding
habitat characteristics include: (1) presence of bare or nearly bare ground and
alluvial islands or sandbars for nesting; (2) availability of food (primarily small
fish); and (3) favorable water levels during the nesting season (so nests remain
above water). They usually nest on sites devoid of vegetation, but have been
found in areas with an average of 11 to 30% vegetative cover, composed of
grasses, shrubs, and trees and ranging from 1 to 3 feet in height. Vegetation, if
present, is usually located well away from the colony, with the exception of
bugseed, eastern cottonwood, and sandbar willow. As natural nesting sites have
become sparse, birds have used sand and gravel pits, ash disposal areas of
power plants, reservoir shorelines, gravel levee roads, and other manmade sites.
The typical nesting period for the least tern in Texas is mid-April to mid-August.
While the interior least tern has not been documented along the pipeline
corridor, potential habitat for the tern is present downstream of the pipeline along
several major waterways including the Brazos, Colorado, Llano, and James
Rivers, and Squaw, Beaver, and Sandy Creeks. The seasonal occurrence
990144BA.v-6
35
- 2/14/2000

<<<PAGE 242>>>

(spring and summer) and potential nesting of least terns is possible in these
areas.
Conclusions
In conclusion, of the 29 federally listed species of potential occurrence in
counties traversed by the Longhorn Pipeline between Houston and Crane, only 8
of those species are documented or estimated to occur within the area of
potential effect for the pipeline safety projects due to the presence of potentially
suitable habitat. None of the species have been documented to occur within the
existing ROW of the pipeline, but several have been documented within
proximity, either by suitable habitat, or by sightings of individuals. Additional
surveys for the Texas prairie dawn-flower, Navasota ladies-tresses, Tobusch
fishhook cactus, Houston toad golden-cheeked warbler, and black-capped vireo
will be conducted to further document their presence or absence and population
densities in the vicinity of the pipeline. These surveys must be conducted during
certain narrow seasons, and therefore, can only be conducted once per year.
The survey season for the prairie dawn, fishhook cactus, and Houston toad is
February to April. The season for the GCW and BCV are late March to late May.
The season for the ladies-tresses is October to November.
990144BA.v-6
36
• 2/14/2000

<<<PAGE 243>>>

4.0
PROJECT DESCRIPTION
Longhorn will
implement various pipeline safety and integrity
enhancements for the pipeline that include various methods of pipeline testing,
anomaly investigations, ROW maintenance, section replacements, cathodic
protection enhancements, and pipeline lowerings. Table 2 contains a summary of
the proposed projects relating to clearing, maintenance construction, hydrostatic
testing, and other integrity-related projects that are addressed in this BA (ref.
Project Documentation Appendix at Tab 2).
Following is a general description of these safety enhancement projects
and the methods by which they will be implemented for the Longhorn Pipeline
System. Additional detail may be found in Construction Specification CS4
contained in the accompanying Project Documentation Appendix at Tab 4.
4.1
RIGHT-OF-WAY CLEARING AND MARKING
Longhorn has committed to bring the surface of the ground within the
ROW into "excellent condition" in order to facilitate surveillance prior to startup of
the pipeline (ref. Project Documentation Appendix at Tab 2). Excellent condition
is that condition which provides a clear line of sight for aerial and ground
surveillance patrols in order to effectively monitor and inspect the ground surface
along the ROW. A clean and clearly marked ROW provides a distinctive line of
demarcation, indicating a change in land use, where surrounding terrain is
natural or heavily developed.
ROW maintenance will include mowing, brush-hogging, back-dragging, or
hand trimming of tall grass or woody re-growth, trimming of tree canopies
overhanging the ROW, setting signs, marking points of intersection (horizontal
bends) in the pipeline with PVC posts, and painting cross-fence posts.
ROW mowing is performed by a twin-blade mower or a brush-hog drawn
by a tractor, to a height between two and four inches. Back-dragging is a method
of clearing in rocky terrain; back-dragging involves pulling a dozer blade
backwards across the ground surface which has the effect of bending vegetation
over at the ground surface. Back-dragging typically does not result in the
990144BA.v-6
37
- 2/14/2000

<<<PAGE 244>>>

uprooting of vegetation. Rather, the vegetation is bent or broken just above the
ground surface. Back-dragging is used only in areas where rocks on the surface
pose a risk of damage to a mower or brush-hog. Weedy vegetation around
surface facilities such as valve settings is at times treated with herbicides such as
Roundup and Rodeo.
Hand trimming involves line trimmers, chain saws, and similar hand-held
equipment.
Tree canopies are trimmed by workers, using chain saws, that are
raised within reach of the canopies by a man-lift.
Steel sign posts are typically set by driving the posts directly into the
ground. PVC posts are set into shallow holes dug by post-hole digger. In limited
circumstances such as when vandals repeatedly remove pipeline markers, sign-
posts are dug by post-hole digger to allow the posts to be set into concrete.
Clearing within areas identified as endangered species habitat will not
result in any ground disturbance because only mechanical or hand cutting will be
employed. The term ground disturbance is intended to mean soil disturbance
that would result from grubbing brush and tree stumps; rather, they will be cut at
ground level. In limited circumstances, stumps directly over the pipeline, which
could have adverse effects on the pipe, will be hand-treated with minimal
amounts of non-aromatic and non-persistent herbicide to retard re-growth.
Herbicides will be applied in accordance with EPA-approved label directions.
These activities are routine and are conducted periodically by pipeline
operators in the United States.
All areas of the ROW are subject to periodic clearing form time to time.
ROW clearing occurs at intervals that depend upon the rate of vegetation growth,
typically averaging once per year in arid and semi-arid territory (generally, from
Austin to Crane) and typically averaging twice per year in territory with greater
rainfall (generally, Houston to Austin). Further, metropolitan areas may be
mowed as frequently as monthly to meet municipal ordinance requirements and
in response to landowner requests. ROW clearing will be conducted on a
schedule that avoids impacts to species; for example, Houston toad habitat will
be avoided during the warmer seasons (February through November) when
990144BA.v-6
38
- 2/14/2000

<<<PAGE 245>>>

toads are typically active and potentially upon the surface of the ROW, and plant
habitat areas are avoided during the respective blooming seasons.
4.2
PIPELINE MAINTENANCE - CONSTRUCTION PLANNING
Prior to project engineering and scheduling, each site is surveyed by
qualified personnel to determine whether or not the activity (a) may affect
threatened or endangered species and habitat, (b) may cause disturbance of
cultural resources, (c) may be subject to Clean Water Act Section 404 (U.S.
Army Corps of Engineers jurisdiction over dredge and fill materials in waters of
the United States), or (d) may be subject to other federal, state or local laws,
regulations or ordinances. Appropriate authorizations are obtained (such as this
consultation), and necessary requirements are identified and incorporated into
project planning and engineering documentation.
Project engineers and technicians perform site inspections to identify site-
specific conditions and features that require consideration in project planning,
such as site ingress/egress routes, workspace requirements, spoil management,
equipment storage, servicing and parking needs, and the like (ref. Tab 5,
Environmental Protection Plan, and Tab 6, Storm Water Pollution Prevention
Plan in the accompanying Project
Documentation Appendix). Such
considerations are incorporated into project planning and engineering activities.
Unless required by the particular project or by site conditions, workspace is
limited to the established ROW. Where workspace is required beyond the limits
of the established ROW, those areas have been incorporated into project
documentation.
990144BA.v-6
39
- 2/14/2000

<<<PAGE 246>>>

Comments
Avoid February through April
Avoid February through April
Avoid February through April
Avoid October through November
Avoid October through November
Avoid February through October
Avoid February through October
Avoid March 15 through September 1:
Avold March 15 through September 1.
Avoid March 15 through September 1
Avoid March 15 through September 1
Avoid March 15 through September 1
Avoid March 15 through September 1
Avold March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avold March through July
Avold March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Species
Texas Prairie Dawni
Texas Prairie Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Navasota Ladies-Tresses
Houston Toad
Houston Toad ::
EA Contributing Zone
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Black-Capped Vireo
Black-Capped Vireo
Tobusch Fishhook Cactus
TABLE 2
2000 MAINTENANCE ACTIVITIES
TESTING AND CLEARING
LONGHORN PIPELINE
County
Harris
Harris
Waller
Fayette
Fayette
Bastrop
Bastrop
Travis/Hays
Hays
Hays
Hays
Hays
Hays/Blanco
Blanco
Blanco
Blanco
Blanco
Gillespie
Gillespie
Gillespie
Gillespie
Gillespie i
Gillespie
Mason
Mason
Mason
Mason
Mason
Mason
Kimble
End Station
2279+20
2411+20
2831+84
5128+64
5948+80
6638+72
6864+00
9961+60
9674+72
9762+72
9926+40
10036+40
10199+20
10461+44
11036+96
11105+60
11441+76
11751+52
11821+92
12149+28
12606+88
12631+52
12728+32
12953+60
13110+24
13217+60
13305+60
13437+60
13578+40
16329+28
Right-of-Way Clearing (Maintenance) - See Comments for Avoidance Timing
Begin Station
2013+44
2310+88
2684+00
5095+20
5936+48
6600+00
6723+20
9152+00
9657+12
9724+00
9850+72
9945+76
10164+00
10266+08
11008+80
11080+96
11295+68
11691+68
11791+28
12114+08.
12513+60
12596+32
12633+28
12921+92
13043+36
13203+52
13277+44
13381+28
13513+28
14476+00
Site
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way 50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-or-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50*)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)

<<<PAGE 247>>>

Comments
Avoid March 15 through September 1
nvestigation of possible dent; access from
improved road to ROW, then 1000 feet down
nvestigation of possible anomaly: access
from improved road to ROW, then 3000 feet
Site entry only, via 5936+48-5948+80
Lowering / Replacement; access. under
mproved road to ROW, then 1000 feet down
Lowering / Replacement; access from
Lowering / Replacement: access from
improved road to ROW, then 1000 feet down
improved road to field road, then via field road
Lowering / Replacement: access from
Lowering / Replacement; access from
improved road to ROW, then 600 feet down
Lowering / Replacement; access 800 feet
down ROW from Site LPP-2751
Lowering / Replacement; access from
improved road to ROW, then 2500 feet down
Investigation of possible dent; access from
improved road and dirt road to ROW, then
nvestigation of possible dent; access from
improved road to ROW, then 1000 feet down
nvestigation of possible dent; access from
Improved road, 3700 feet of unimproved road
to ROW. then 7000 feet to project site
ROW
down ROW
development
ROW
to project site.
ROW to project site
1300 feet down ROW
ROW
ROW
Species
Black-Capped Vireo
Texas Prairie-Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Black-Capped Vireo
Black-Capped Vireo
EA Contributing Zone
County
Kimble
Harris
Harris
Fayette
Travis
Travis
Travis
Hays
Blanco
Blanco
Gillespie
Gillespie
Gillespie
Mason
Travis
End Station
15234+56
2073+52
2737+37
5931+12
9197+24
9222+24
9488+24
9807+42
10373+24
10381+24
11725+71
12659+39
12682+16
14012+73
Begin Station
15153+60
2073+52
2737+37
5926+74
9195+80
9220+80
9483+31
9807+10
10369+55
10380+60
11725+22
12659+39
12682+16.
14012+73
Hydrostatic Pressure Test - Header Installation Locations
9338+50
Site
Maintenance Construction
Right-of-Way (50")
DT-20a (K)
Crossing (K)
2008 (K) Ph. 1
LPP-2467
LPP.2471
LPP-2546
LPP-2627
LPP-2751
LPP-2753
2016
DT-12a (K)
DT-11
DT-9a (K).
Site 5-5

<<<PAGE 248>>>

Comments
CP Ground Bed - Kimble County Station
Coating Reconditioning
Coating Reconditioning
Coating Reconditioning
Species
Near Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Texas Prairie Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Barton Springs Salamander (EA Contributing Zone) and
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler and Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler and Black-Capped Vireo
Golden-Cheeked Warbler and Black-Capped Vireo
Black-Capped Vireo
Tobusch Fishhook Cactus and Black-Capped Vireo
Tobusch Fishhook Cactus and Black Capped Vireo
Texas Prairie Dawn
Houston Toad
Houston Toad
Tobusch Fishhook Cactus
County
Blanco
Blanco
Blanco
Mason
Kimble
Kimble
Kimble
Kimble
Harris-Waller
Waller
Fayette
Travis-Hays
Hays-Blanco
Blanco
Blanco
Blanco
Blanco-Gillespie
Gillespie
Gillespie-Mason
Mason
Mason
Kimble
Kimble
Harris
Bastrop
Bastrop
Kimble
2128+97
6612+99
7085+24
End Station
2415+50
3385+00
5966+47
10163+00
10265+00
10504+50
11188+00
11385+50
12033+73
12360+00
13040+00
13435+00
13910+00
14606+00
16992+40
15592+90
10163+00
10265+00
10742+50
11188+00
11385+50
12033+73
12360+00
13040+00.
13435+00
14373+00
2127+97
14606+00
6609+49
7084+74
Begin Station:
10163+00
10280+00
11385+50
13435+00
14606+00
15143+00
15586+00
16167+00
1802+63
2415+50
5039+00
9647+00
15592+90
Hydrostatic Pressure Test - Test Segments
Cathodic Protection Enhancements
Site
Site 6-1
Site 6-2
Site 6-6
Site 7-3
Site 8-1
Site 8-2
Site 8-3
Site 8-4
Segment 2
›Section 1
›Section 2
Segment 3
Section 2
›Section 6
Surge Pressure Protection
Segment 5.
Segment 6
> Section 1
> Section 2
›Section 4
> Section 5.
›Section 6
›Section 7
Segment7
›Section 1
›Section 2
›Section 3.
›Section 6
Segment 8 (all)
CR-1
CRA
CR-5
CPGB-5

<<<PAGE 249>>>

P 42 (aloiasua pota o, pus berapie is0 2:
:2 AN25 CACOODCE DuNG. шо д
: w Й becseegepe extnogou of Aru0o20.
DA caco sabuo anioos Osgow S s 0020
.. i. god me bbonte noucu po erockhon
Bypass Valve - Liano River East Bank; Same
Location as Hydrostatic Test Header Location,
s0 monic no s000sa0 at a
8
¡ oise to omel oi obreco biba.
mos miepentee sust uecoeism sit.et
600.
r gognno tuondu bicly sompue i
homo grin bioleg ais coucy
pes ga. piar exebueur co.coon
.23-
.3CS0 32 ir moa pA 700 i 0u0
Species
Tobusch Fishhook Cactus
O4 2!
•.txcile sucotubaer
: a00 0 00l00ne) touecs Colp
piespo Biotect pear wansdos
trciecr bpumuo msi
•A .
:3G
County
Kimble
280
s.::00.sm1bou e bebstey o
spo bucioct
aLoDü:
3 LeME0 A O3DeOU:
End Station
14606+51
amoura ne sioleci
7 ue pipee eug ynoigee
Begin Station
14606+51
W500 wedmustene
iiK:W0N S.00ORDU
Site
2 JGane
Surge 4.
nosge sednpen
its pudneuce o exeup)
S слома
higig roosgon sisb.

<<<PAGE 250>>>

Workspace beyond the limits of the established ROW may be required for
a number of reasons. First, avoidance of habitat or the natural terrain along one
side of the ROW may necessitate expansion of workspace along the opposite
side of the ROW. Second, a sloping surface gradient at a project site may require
that spoil removed from the pipeline trench be stockpiled with a wider base,
extending off of the ROW, than would be required at a project site with a level
surface. Further, a project to lower or replace pipe at a creek crossing may
require water diversion measures that necessitate a workspace wider than the
established ROW. In addition, though project equipment is typically aligned
along the existing pipeline ROW, project site conditions such as size, shape
and/or slope may require that equipment be centralized in an equipment
marshalling area (typically 25 ft. wide by 100 ft. long). for temporary storage,
security and/or service.
Biological surveys encompass both areas of potential surface disturbance
and areas within the zone of potential indirect construction impacts, such as
noise.
In addition, applicable project best management practices (BMPs) are
identified at this stage of project planning and incorporated into planning
documentation.
A Project Construction Plan is prepared for each individual project location
to document project planning. The Project Construction Plan contains the
following sections of detailed information:
a.
Description of Work for the Project
b. Responsibilities and Authorities
Safety Requirements
d.
Job Contacts and Notification Requirements Matrix
e.
Pre-Job Training Requirements
a.
Environmental Protection
b.
Project Schedule
C.
Forms / Documents Required
a.
Chronological Sequence of Events
b.
Appendices as follows:
i.
Appendix 1 - Location Map
ii. Appendix 2 - Drawings, Calculations, and
990144BA.v-6
43
- 2/14/2000

<<<PAGE 251>>>

ili.
Specifications
iV.
Appendix 3 - Environmental Protection Plan
V.
Appendix 4 - Storm Water Pollution
Vi.
Prevention Plan
vii.
Appendix 5 - Safety Procedures Document
vili.
Appendix 6 - Sample Forms
An example Project Construction Plan (Site LPP-2627, pipeline
lowering/replacement in Hays County, Texas) is included in the accompanying
Project Documentation Appendix, at Tab 3, for reference. A Project Construction
Plan relating to each project identified in Table 2 is presently under development;
Longhorn will provide to the Service a copy of each Project Construction Plan as
it is completed.
Project BMPs are defined as procedures and specifications by which
environmental controls will be implemented and include such items as
sedimentation and erosion controls, reclamation procedures, minimization and
avoidance procedures, inspection and reporting procedures, spill containment
and cleanup procedures, procedures for addressing unforeseen circumstances,
procedures for addressing foreseen, but unpredictable circumstances, and
others. Project BMPs are identified and adapted from technical guidance
manuals generally accepted as providing the appropriate environmental
protection measures, such as the Texas Natural Resource Conservation
Commission (TNRCC) technical guidance manual, Federal Energy Regulatory
Commission (FERC) Environmental Guidance Manuals, and the City of Austin
Environmental Criteria Manual. BMPs are incorporated within the Longhorn
Storm Water Pollution Prevention Plan (SWPPP); an example of an SWPPP is
included the accompanying Project Documentation Appendix at Tab 6.
990144BA.v-6
44
2/14/2000

<<<PAGE 252>>>

4.3
PROJECT ENVIRONMENTAL INSPECTORS
Longhorn and Williams shall employ the services of environmental
inspectors (such as Horizon and 3D/International) at every project site with
associated species-related constraints. These environmental inspectors are
qualified under FERC guidelines. The environmental inspector will remain at
each project site during the period of activity to ensure compliance with all project
constraints and project BMPs. The inspector is authorized to dictate any
additional project BMPs that may become necessary during the activity and to
modify work activities and progress to the extent necessary to ensure compliance
with project environmental constraints. However, in the event of a conflict
between project constraints and sound engineering practices, the inspector shall
consult with project engineers and the Service, as appropriate, to achieve project
goals while minimizing any impacts to the environment. The environmental
inspector retains oversight of site closure and performs, or supervises the
performance of, post-activity inspections of project BMPs until site stabilization is
achieved. The environmental inspector will produce appropriate documentation
for each construction location to include BMP compliance logs, photographs, as-
built dimensions of disturbance, and any encounters with listed species during
the construction process. The reports will be provided to the Service after
completion.
4.4
SITE PREPARATION
Prior to site entry, at locations where avoidance and/or minimization of
species effects has been recommended, a qualified biologist will clearly identify
areas for avoidance and will stake and/or flag such areas. The project
environmental inspector also surveys the site to ensure that all such avoidance
areas are clearly identified in accordance with conditions approved in the
consultation process and confirms other site-specific areas in which disturbances
may occur such as routes of ingress/egress, spoil management areas,
equipment marshalling areas, workspace areas, and the like. Project BMPs are
reviewed prior to site entry, and the locations of any necessary physical control
measures to be employed are identified.
A survey crew will precede the project equipment and mark the project
990144BA.v-6
45
- 2/14/2000

<<<PAGE 253>>>

boundaries. In addition, the pipeline centerline is marked at 100 foot to 200 foot
intervals.
4.5
SITE ENTRY
Upon site entry, the necessary project equipment is transported to the site
via the designated route for ingress/egress. Site access is achieved via
improved roadways and the established ROW, using the shortest available route
between improved roadways and the project site. Routes of ingress/egress take
into account any potential for effects to threatened and endangered species and
habitat that may exist along the ROW between the improved roadway and the
project site, as well as accounting for other potential impacts to the environment.
At times, equipment will remain on-site only during the time that it is in active use
to allow it to be shared between project sites in close proximity.
Prior to any excavation, site vegetation is removed, and project BMPs are
installed.
Site vegetation is cleared to the extent necessary for project
completion, so long as the vegetation is not located in areas identified for
avoidance. Clearing is accomplished by the methods described in Section 4.1,
Right-of-Way Clearing, though vegetation within the workspace may require
removal. Project BMPs are installed in accordance with project planning
documentation and in accordance with the site-specific SWPPP.
The following task descriptions identify process steps that occur once all
authorizations are obtained and regulatory requirements are identified and
incorporated into project planning and engineering documentation. Detailed
procedures for each of the activities summarized below are available in Pipeline
Construction Specification CS4, which is included in the accompanying Project
Documentation Appendix at Tab 4. In the event of a conflict between
Construction Specification CS4 and the site-specific components of the Project
Construction Plan, the Project Construction Plan controls.
4.6
PIPELINE LOWERING AND/OR REPLACEMENT - OPEN TERRAIN
Once the project site has been prepared and equipment brought onto the
location, the following major activities take place:
990144BA.v-6
46
- 2/14/2000

<<<PAGE 254>>>

•
Isolate pipeline segment to be replaced by cutting and plugging at
boundaries. Williams operating personnel will establish that the line
is unpressurized and properly isolated such that the contractor may
cut the pipeline at the project limit boundaries. Mechanical plug
devices will be utilized to prevent residual product leakage from the
pipeline segments or entry of foreign materials into the pipeline.
These devices shall be secured to prevent their loss or tampering.
•
Remove large rocks, if any, from ROW work area to appropriate
disposal/storage area. Trackhoes with buckets are used, unless
larger rocks require grapple capable (clam) buckets.
•
Remove and set aside topsoil spoil (double ditch practices).
Double-ditching will be required in areas where native plant
communities need to be re-established, or there are topsoil
improvements, such as sodded lawn areas and cultivated fields.
Double-ditching allows topsoil management by making two passes
to remove and segregate spoil; one to remove and set aside topsoil
and one to remove and set aside subsoils.
•
Remove overburden and expose pipe. Utilizing track hoes, remove
and set aside overburden from the pipeline and load and remove
excess amounts from the work site for disposal. Unsuitable
overburden (i.e., large rocks) will be disposed of in approved sites.
•
Cut pipe into subsections at road and water crossings. Expose and
cut the pipeline at road crossing boundaries to isolate the removal
section into subsections. Utilize drain pans to recover any
remaining liquids as the cut is made. Install mechanical plugs in all
exposed pipe ends.
•
Raise and crib pipe on side of trench. Properly manage any coating
which comes loose from the pipe.
990144BA.v-6
47
- 2/14/2000

<<<PAGE 255>>>

Prepare and wrap pipe for disposal. Double wrap the pipe sections
with 6-mil thickness plastic wrap, taping and sealing each wrapping
separately. Ensure that the ends are sealed to prevent any release
of coating.
•
Remove pipe from ROW. Load and remove the wrapped pipe
sections by truck. Care will be taken to preserve the plastic
wrapping on the pipe. Secure the pipe to the trailer and haul to the
disposal site for final disposition.
•
Cleanup and grade ROW for survey and trenching operations
•
Capture,
contain, and remove any remaining coating
materials/scraps using project-prescribed methods for asbestos
containing materials. Prepare the grade on either side of the ditch
to accommodate the trenching machinery, removing any large
rocks. Survey crew should mark and stake the centerline offsets as
required by the trenching crew.
•
Deepen trench to new depth. Depending upon the length of the
desired lowering and/or replacement, and depending upon whether
the trench is in soil or rock, a track-hoe or wheel trencher (rock
saw") deepens the trench to the new depth. A wheel trencher is
typically used for longer trenches and trenches in consolidated
rock. Dust generation is monitored during trenching, and a water
fog of the trenching mechanism may be employed to minimize
airborne dust in non-rural areas.
•
String new pipe along trench. As the ditch is prepared, the pipe
may be strung along the workpad in anticipation of measuring and
marking for bending, welding, and lowering operations. The survey
crew will note the pipe heat and identification numbers sequence
for the individual pieces as they are placed. The survey crew will
survey the new ditch profile and mark the pipe for calculated field
bends.
90144BA.v-
48
2/14/200

<<<PAGE 256>>>

•
Make field bends. The field bending crew will proceed ahead of the
welding crew to make any required field bends. The contractor
may also elect to set up field bending in one of the equipment
marshalling areas and perform bending there rather than on the
ROW.
Weld and Radiograph new pipeline. The welding crew will proceed
to weld the pipeline. Inspectors and survey will note the weld
numbers and identification of the welders for this activity. The
radiography crew will follow the welding crew. Inspection will be
per standard specification API 1104 and include 100% radiography
of all girth welds.
•
Apply weld joint coating and inspect pipeline coating for "holidays";
a holiday is a point where the coating fails to electrically insulate the
pipe. Weld joint coating will be applied as specified in the Project
Construction Plan. This will be by field-applied FBE (fusion bond
ероху). Following weld joint coating, the entire coating system will
be inspected for holidays and repaired as required.
•
Pad and lower pipe. Pad the ditch and lower the pipeline as
specified in Construction Specification CS4. Install ditch plugs as
required to stabilize pipeline during hydrotest and backfilling. The
pipeline coating will receive a final "jeeping" as the pipe is lowered
to ensure its integrity. Jeeping is the process of electrically
inspecting the pipeline coating to ensure that no "holidays" exist in
the coating, so named due to the "jeeping" sound the inspection
device emits when a holiday is identified.
•
Complete as-built survey. Complete as-built survey activities,
noting weld locations, pipe identification codes, and location and
stationing of bends, fittings and other such features for inclusion in
alignment sheet drawings.
•
Backfill and compact trench. Backfill and compact the ditch
according to Construction Specification CS4, maintaining sufficient
990144BA.v-6
49
- 2/14/2000

<<<PAGE 257>>>

cover to allow for settling. Install ditch breakers and silt fencing as
appropriate for surface erosion control until the site is stabilized.
•
Perform hydrostatic pressure test on new pipeline segment. Obtain
fresh water for pressure test and begin line fill behind a pig. The
test pressure and test duration will be established and specified in
the Project Construction Plan or in separate hydrostatic testing
plans.
Drain and dispose of hydrostatic test water. Upon completion of
the hydrostatic test, the test water is either pushed with nitrogen to
a subsequent test site or removed into mobile tanks for hauling to a
disposal facility. Test water is controlled to ensure that it is fully
contained in order to prevent discharge to the environment.
•
Perform Final Tie-Ins. Remove the test headers and make the final
tie-ins of the new pipe segment to the existing pipeline. The tie-in
welds will be 100% radiographed to ensure their integrity. Coat the
tie-in welds with an appropriate joint coating system compatible
with both FBE and coal tar coatings. The coating is inspected, or
"jeeped," and any holidays are repaired. The tie-in locations are
backfilled and compacted.
•
Clean, Grade, and Seed Right-of-Way. Following installation of
erosion control measures, re-seed the right-of-way with native
grass seed and/or sod as prescribed for the location. Re-install
pipeline markers and any traffic control devices to limit or restrict
ROW access by motor vehicles.
•
Perform Site Cleanup and Restoration. Clean up equipment
marshalling and material storage sites, ensure that the worksite
access roads are restored to prime condition, and that any road
access ways are cleaned and restored.
4.7
PIPELINE LOWERING AND/OR REPLACEMENT - CREEK CROSSING
50

<<<PAGE 258>>>

Pipeline lowering and/or replacement at creek crossings follows generally
the same sequence of activities described above for open terrain; however, the
additional activities described below apply to the actual creek crossing area. In
addition, creeks may be crossed by either trenching or boring. Each crossing
method is summarized separately below.
4.8
TRENCHING
A trenched crossing is lowered and replaced in much the same manner as
an open terrain project; however, incremental measures are employed to ensure
both that erosion and sedimentation are minimized and that no potentially
harmful materials are discharged to the waterway. Pipeline Construction
Specification CS4 provides additional details.
Cut Pipe at Creek Crossings. Expose and cut the pipeline at the
creek crossing boundaries to isolate the removal section into
subsections. Utilize drain pans to recover any remaining liquids as
the cut is made. Install mechanical plugs in all exposed pipe ends.
•
Implement Water Quality Protection Measures. Staging areas,
spoil storage areas, and additional workspace areas are located in
upland areas above the creek bed. Hazardous materials such as
chemicals, fuels, lubricating oils and any other potentially harmful
materials are maintained at least 100 feet from the water body.
BMPs are installed to prevent sedimentation. Flumes, dams,
equipment bridges and other diversion devices are installed as
necessary to perform "dry ditch" excavation.
•
Erosion control measures are employed after project completion to
ensure that stream flows do not cause erosion of disturbed areas
and subsequent sedimentation. Erosion controls protect against
sedimentation and prevent stream flow from removing pipeline
cover which could expose the pipe to steam bed forces. Erosion
control measures are site-specific, depending upon site conditions,
and include berms, dikes, water bars (perpendicular to the pipeline
990144BA.v-6
51
- 2/14/2000

<<<PAGE 259>>>

alignment), silt fences, staked hay bales, seeding, mulching,
hydromulching, riprap, and trench plugs.
4.9
BORING
Stream crossings may be installed by boring rather than trenching,
depending upon hydrologic and engineering considerations and soil types. The
existing pipeline may be abandoned in place after obtaining approvals from the
landowner and, if necessary, state and federal authorities, and after (a) filling the
pipe with an inert material such as grout or concrete, or (b) sealing the ends of
the pipe. The pipe may not be abandoned in place if its presence could interfere
with stream flows or interfere with future uses of the waterway.
Boring a stream crossing requires the use of a work space for installation
of bore pits in which the boring equipment operates. The boring operations
typically require a workspace approximately 100 to 250 feet wide by 150 feet
long. The workspaces are located above the high water mark unless topography
or other factors dictate otherwise. Typically, no instream soil disturbance occurs,
and BMPs are employed to ensure that spoil storage and other project activities
do not cause erosion or sedimentation.
From within the bore pits, the boring equipment creates a parabolic
pathway to the pit on the other side of the stream bed. Bored material is
circulated out of the bore and retained at the upland spoil storage area. The bore
is sealed with grout or bentonite to fill fissures along the course and to ensure
bore stability.
The new pipe is then pulled through the bore using equipment designed
for that purpose. Once the pipe is welded, inspected, surveyed, coated and
tested, the excavations are filled and compacted, and the site is restored. Site
restoration and stabilization is achieved in the same manner as described in
Section 4.6, Pipeline Lowering and/or Replacement - Open Terrain. Any
necessary erosion and sedimentation controls are employed, and the site is
inspected and maintained until final stabilization is reached.
990144BA.v-6
52
- 2/14/2000

<<<PAGE 260>>>

4.10 HYDROSTATIC TESTING - OVERVIEW OF ACTIVITIES
A hydrostatic pressure test is scheduled to be performed to ensure the
integrity of the system. This test is scheduled to commence in February 2000
and conclude in May 2000.
Hydrostatic testing will start at the Longhorn GATX pump station in
Galena Park (Houston) and proceed westward to Crane Station. The test
medium will be potable water from a local municipal supply source. In the event
some water is lost due to pipe failure, or if water is needed to fill longer test
sections, fresh make-up water will be acquired, by permit, from sources crossed
by the pipeline (i.e., from rivers or streams).
The hydrostatic testing occurs in segments, which are subdivided into
test sections of varying lengths. Factors that contribute to test section length
include (a) target test pressures; (b) pipe size and grade; (c) the presence or
absence of species and habitat; (d) the location of valves and pump stations; and
(e) elevation changes along the pipeline.
Due to additional factors, two test sections will not be tested during the
Houston to Crane hydrostatic testing project. Those two sections are (a)
Segment 4, Section 1, which encompasses habitat for the endangered Houston
toad and (b) Segment 5, Section 4, which encompasses the recharge zone of the
Edwards Aquifer and part of the adjacent contributing zone, areas of potential
effect to the endangered Barton Springs Salamander. Rather, those sections will
be tested after Phase II consultation relating to pipeline operation, maintenance
and emergency response, and after maintenance construction to replace pipeline
segments in those areas is completed.
The current hydrostatic testing schedule is as follows:
TEST SEGMENT
START DATE - END DATE
Segment 1
February 11 - February 13
Segment 2
February 14 - February 20
Segment 3
February 21 - February 27
53
221420

<<<PAGE 261>>>

Segment 4
February 28 - March 5 (Section 1 after
completion of maintenance construction (May))
Segment 5
After completion of maintenance construction (May)
Segment 6
March 6 - March 15
Segment 7
March 16 - March 26
Segment 8
March 27 - April 2
Segment 9
April 3 - April 9
Segment 10
April 10 - April 16
Segment 11
April 17 - April 23
As noted above, the test sections traversing Houston toad habitat and the
Edwards Aquifer Recharge Zone will not be tested until after the completion of
maintenance construction in those areas, which will not commence until after
completion of Phase II of this consultation. The start date for Segment 1
identifies the date that actual testing is scheduled to begin; however, for the
remaining test segments, the start date identifies the date on which test water is
scheduled to be introduced into that segment from the preceding segment. In
addition, any delay encountered during testing, such as to replace a failed
segment of pipe, will result in equivalent delays in the remainder of the test
schedule.
To facilitate hydrostatic testing of the pipeline, headers will be installed on
the pipeline at intervals along its length which divide the pipeline into segments
for discrete testing. There are forty (40) header sites involved in the test. A
general description of the installation of the test headers follows. Additional
information is provided in the accompanying Project Documentation Appendix at
Tab 8, including a graphic depiction of a typical header site. Headers vary in
configuration; however, all function similarly to allow the introduction of test
water, the pressurization of the test segment and the displacement, after testing,
of the test water to the following test section.
Prior to any work, the sites will be subject to an environmental,
endangered species, and archeological survey conducted by
qualified third-party biologists and archeologists. The headers will
be installed by excavating an area approximately 20 ft. wide x 80 ft.
long × 4 ft. deep around and under the pipeline. The spoil will be
990144BA.v-6
54
- 2/14/2000

<<<PAGE 262>>>

stored on the temporary work easement. The topsoil will be
segregated from the sub-grade for restoration of the site following
the hydrostatic test. Storm water management during construction
and testing will be by methods prescribed in the SWPPP, an
example of which is included in the Project Documentation
Appendix at Tab 6.
•
The exposed pipe will be cut and spread apart horizontally, and
pre-fabricated headers will be welded to each section. The
downstream header shall have a wire brush pig and displacement
pig inserted in it before it is welded on the pipeline. A 6-inch
temporary crossover pipe with valve will be installed between the
upstream and downstream header. Upon completion of the test,
the hydrostatic test water will be displaced into the next test
segment by nitrogen. The test section will be vented to atmosphere
and the temporary piping and headers will be removed. The
pipeline will be tied back together with a joint of new pre-tested pipe
and the joints will then be coated and wrapped to provide corrosion
protection. Coating is inspected for holidays, and repairs are made
if holidays are identified. The excavated area will be backfilled and
compacted with the subgrade material in the spoil pile followed by
the topsoil to finished grade to match the surrounding terrain. The
disturbed area is seeded with native grasses or sod, and BMPs are
inspected and maintained until the site is stabilized. Total surface
workspace requirements for test header installations are about 100
feet wide by 150 feet long along the pipeline.
4.11
HYDROSTATIC TESTING - POTENTIAL FAILURE OF PIPE
Hydrostatic testing of the existing Longhorn Pipeline between Houston and
Crane is expected to result in a number of failures. Some of those failures, and
actions taken to locate failure locations, could have effects upon both species
and habitat. However, the calculation of the effects of such failures is difficult to
estimate since the location of any such failure cannot be predicted and since the
volume of test water that may be discharged is difficult to predict.
990144BA.v-6
55
- 2/14/2000

<<<PAGE 263>>>

Calculations by a pipeline integrity consulting firm estimate that
approximately 18 to 20 failures will occur at the high test pressures planned.
Since the most likely failure location is at pipeline flaws, the location of the
expected failure cannot be predicted with any accuracy; at most, a minimal
number of recently replaced sections of pipe may be eliminated from
consideration. Therefore, the expected failures will approximate a random
distribution over the Houston to Crane segment. A finite number of failures could
be assigned to the habitat areas based upon the proportional share of pipeline
mileage in habitat areas; however, that methodology would probably result in
either overestimation or underestimation of the number of failures in habitat
areas.
In addition, the potential volume of test water discharged in the event of
failure is difficult to estimate. First, if a failure results in rapid depressurization of
the test segment, the volume of test water discharged will be the sum of (a) water
expelled as the pipe returns to atmospheric pressure, which depends upon test
pressure and test segment length, and (b) drainage from any adjacent segments
at elevations higher than the failure location. Second, if a failure results in a
slow depressurization of the test segment, it may be readily identifiable and
quickly contained. If a slow leak is difficult to locate, one or more investigative
excavations could be required to either search for the failure or plug a portion of
the segment so that lengths of pipe may be eliminated from the search.
Therefore, given that failure location and size cannot be predicted, potential
effects on species and/or habitat cannot be reasonably estimated in advance.
Another factor that makes such estimates difficult is the existence of residual
amounts of diesel fuel that remain in the pipeline from cleaning during 1998. As
the hydrostatic testing proceeds from east to west, the test water may be
expected to reflect relatively higher levels of hydrocarbon content; however,
those concentrations cannot be predicted. Spill response equipment such as
booms, sorbant pads, and other containment and cleanup equipment will be
maintained in the vicinity of the test sites during the procedure.
In summary, the locations of hydrostatic test failures cannot be predicted,
the volume of test water discharged may not be calculated, and the number of
investigative excavations cannot be predicted.
990144BA.v-6
56
- 2/14/2000

<<<PAGE 264>>>

4.12 CATHODIC PROTECTION ENHANCEMENTS
Enhancements of the pipeline cathodic protection system consist of (a)
installation of anode beds and (b) re-coating of sections of existing pipe. The
cathodic protection system protects the pipe from corrosion. These
enhancements are identified and described in the accompanying Project
Documentation Appendix at Tab 2, and the locations where activities may affect
species and habitat are identified in Table 2. Project planning is performed in a
manner similar to that described in Sections 4.3 through 4.5 above.
Installation of deep anode ground beds requires a series of vertical bores
within which sacrificial anodes are placed; the anodes within each bore and
among the series of bores are connected by subsurface wiring that is then
connected to the pipeline. The bores and wiring trenches are installed within the
existing ROW. During boring, a circulating pit is dug to contain cuttings removed
from the bore. After project completion, the pit is filled, excess cuttings are
removed for disposal, and the site is closed in the manner described in previous
discussions of construction site closure.
An example project work plan and related diagrams that provide additional
detail about deep ground-bed installation are included in the accompanying
Project Documentation Appendix at Tab 11.
Pipeline coating reconditioning involves the same activities required for a
pipeline lowering or replacement, with the exception of the process steps to
remove existing pipe and install new pipe. A coating replacement site undergoes
the project planning, site preparation, site entry, and site closure steps much as
described above in Sections 4.2 through 4.6. Since the pipe is not cut, any
residual liquids within the pipe do not present contamination potential. Asbestos
containing pipe coating is managed in accordance with the provisions of the
Environmental Protection Plan and the Project Construction Plan (ref. the
accompanying Project Documentation Appendix at Tabs 5 and 3, respectively).
All coating reconditioning is inspected, or "jeeped," and any holidays are
repaired.
4.13 SURGE PRESSURE PROTECTION
990144BA.v-6
57
- 2/14/2000

<<<PAGE 265>>>

To reduce the risk of over-pressurization of the pipeline, Longhorn will
implement system changes and operating practices to limit surge pressures to no
more than maximum operating pressure in sensitive and hypersensitive areas
identified by the Lead Agencies (ref. Project Documentation Appendix at Tab 2).
One system change involves the installation of over-pressure activated by-
pass systems that will allow a pressure spike to be relieved around certain gate
valves. The installation of a by-pass system involves the same process steps as
the installation and removal of a hydrostatic test header; see Section 4.10. The
by-pass system to be installed at the east bank of the Llano River will use the
same work location as the hydrostatic test header to be installed at that valve
site.
4.14
INVESTIGATIONS
Projects to investigate possible pipe dents and corrosion anomalies follow
the
same
planning
and
preparation procedures
for a pipeline
lowering/replacement, but on a lesser scale. Table 2 identifies relevant
information for, and the locations of, projects to investigate possible pipe dents
and corrosion anomalies.
Typical investigation sites require a trench approximately 20 feet in length.
If a dent or anomaly cannot be field repaired, a segment of pipe will be removed
and replaced, with the length replaced at least twice the pipe diameter. Coating
and coating inspection and repair, as well as site closure, follow the procedures
described in Section 4.0.
990144BA.v-6
58
- 2/14/2000

<<<PAGE 266>>>

5.0
POTENTIAL IMPACTS (TAKE) AND COMPENSATION
ATake@ of listed species is defined in the ESA and implementing
regulations as the act or attempted act of pursuing, hunting, shooting, wounding,
killing, trapping, capturing, collecting, harming, or harassing. Harm and harass
are defined as the act of disturbing individuals or modifying habitat to the extent
that wildlife are actually killed or injured by impairment of essential behavioral
patterns such as breeding, feeding, or sheltering.
Potential take of certain listed species could occur from a number of
actions or events associated with the implementation of the subject project
activities described in Section 4.0, including maintenance construction,
hydrostatic testing, ROW maintenance, and cathodic protection enhancements.
No individuals of any listed species have thus far been documented within the
existing pipeline ROW; however, the potential for incidental take cannot be
eliminated. Surveys and detailed habitat assessments have been conducted for
a number of species of concern, and additional surveys are scheduled for the
near future; however, the Service has recommended in the December 15, 1999
Comment Letter that additional surveys be conducted for several years into the
future to confirm the presence or absence of species within areas of potential
habitat. Furthermore, the hydrostatic testing project could affect habitat areas,
but no reasonable means exists to predict or to quantify the potential for take.
Alternatively, take may be assumed without reference to the presence or
absence of species. Assumed take will very likely result in overcompensation;
that is, since surveys have not identified individuals in the pipeline ROW,
assumed take will result in compensation for areas of potential habitat where
species utilization has, to date, not been confirmed.
That overcompensation will provide a net benefit to the species for several
reasons. First, surveys to date have not identified individuals in the area of
impact for the subject maintenance construction activities; thus, compensation
occurs even though there is no documented take. Second, Longhorn will
implement numerous controls to ensure that the project activities are conducted
first to avoid, and otherwise to minimize, potential effects to species and habitat.
Examples include identifying and marking habitat areas for avoidance; planning
project implementation to minimize the potential for any effects; use of FERC-
990144BA.v-6
59
- 2/14/2000

<<<PAGE 267>>>

qualified inspectors with authority to alter a project in areas with species related
concerns; adjusting project timing to avoid periods of activity and blooming
seasons; and implementing storm water pollution control BMPs even when not
required by permit. Thus, any potential adverse effects will be avoided or
minimized. Third, potential habitat has been assumed over broad areas when, in
fact, detailed surveys could reveal that occupied habitat is either absent or of
doubtful viability to a species. The end result is that the potentially affected
species benefit
by conservation efforts on a scale greater than any likely
incidental take.
Longhorn proposes, therefore, to assume an incidental take for the entire
width of the pipeline ROW traverse of broad areas of potential habitat. This
conservative assumption will result in overcompensation to the benefit of the
potentially affected species and habitats. Take is calculated based on the extent
of potentially suitable habitat within the established ROW (50-foot width x length)
and within temporary workspaces that exceed the ROW (i.e., equipment staging
areas, spoil management areas, and stream diversion areas, the size of which
varies by location). On that basis, the take for each species is calculated as
indicated in Table 3.
As discussed in Section 4.11, Hydrostatic Testing - Potential Failure of
Pipe, the locations of potential hydrostatic test failures cannot be accurately
predicted, the volume of test water discharged cannot be accurately predicted or
calculated, and the number of investigative excavations cannot be predicted. The
inability to accurately predict the potential impacts of hydrostatic test failures
precludes any pre-activity attempt to predict and/or estimate the potential effects
of test failures. Any such attempt would be likely to result in inaccurate
estimates. Therefore, Longhorn proposes to provide for a contingent
methodology for calculating any such effects.
990144BA.v-6
60
_ 2/14/2000|

<<<PAGE 268>>>

Table 3:
ROW Clearing/Maintenance and Additional Construction Impacts* Within
Listed Species Habitat - Longhorn Pipeline
ROW Clearing/Maintenance Area:
Texas Prairie Dawn
53,392 linear feet × 50 feet
61.3 acres
Navasota Ladies-tresses
4,576 linear feet x 50 feet
5.2 acres
Houston Toad
17,952 linear feet x 50 feet
20.6 acres
Golden-cheeked Warbler
90,096 linear feet x 50 feet
103.4 acres
Black-capped Vireo
36,256 linear feet x 50 feet
41.6 acres
Tobusch Fishhook Cactus
185,328 linear feet × 50 feet
212.7 acres
TOTAL ROW IMPACTS = 444.8 acres
Additional Maintenance Construction Area
Construction
Dimensions** Species
Impact
Site
Stationing
Acres
LPP-2753
LPP-2751
10369+55 - 10373+24
200 × 1033
200 × 1000
GCW
4.7
2016
10380+60 - 10381+24
200 × 806
GCW
GCW
4.6
Hydrostatic Header
3.7
And Test Sites
Site 6-6
Site 6-2
10280+00
50 × 100
GCW
50 × 100
GCW
0.1
0.1
11385+50
Site 8-2
Site 7-3
13435+00
15143+00
50 × 100
50 × 100
TFC
BCV
0.1
Site 8-3
15586+00
16167+00
50 × 100
TFC
0.1
Hydrostatic Transfer
Site 8-4
0.1
50 x 100
TFC
0.1
Sites
Site 6-1
Site 8-1
10163+00
50 x 150
GCW
0.2
And Surge-4
14606+00
50 × 150
TFC
0.2
TOTAL MAINTENANCE
CONSTRUCTION IMPACTS
14.0
TOTAL IMPACTS
458.8.
Of the methodologies available for calculating the effects of activities upon
2214200 G

<<<PAGE 269>>>

species and habitat, the most applicable is the Habitat Equivalency Analysis
(HEA) methodology developed by the National Oceanic and Atmospheric
Administration for Natural Resources Damages Assessments (NRDAs). The
HEA methodology is briefly described by the following steps:
The duration and extent of injury are documented and estimated
from the time of injury until the resource recovers to baseline;
•
The services provided by a compensatory project are documented
and estimated over the full life of the project;
•
The size of a compensatory project is calculated such that the total
increase in services provided by the compensatory project equals
the total interim loss of services due to the injury; and
•
The cost of the compensatory project is calculated.
A more detailed description of the HEA methodology is provided in
accompanying Project Documentation Appendix at Tab 10.
Longhorn's proposal, then, is to execute the following sequence of
measures in the event a hydrostatic test discharge occurs in areas of concern for
species and/or habitat:
•
In the event of a test failure, immediately notify a qualified biologist,
who will be maintained on standby along the test segment, and
direct the biologist to the failure site;
•
If a discharge occurs, the biologist will assist the identification of
response actions to minimize potential impacts to the environment;
and,
•
The biologist will perform a field survey to document the loss of,
destruction of, or injury to natural resources (a) at the location of
any excavation, whether the excavation is for location of a failure or
for repair of pipe; (b) within the area of impact of the test water; and
(c) in any other areas affected by the response to the test failure, as
at any other construction site.
The effects, if any, of the hydrostatic test failure upon species and/or
habitat will then be calculated pursuant to the HEA methodology. Longhorn shall
990144BA.v-6
62
• 2/14/2000|

<<<PAGE 270>>>

compensate for the value of any such adverse effects by paying the monetary
value of an appropriate compensation project to conservation efforts directed at
the preservation and recovery of the affected species and habitat in the region
where the impact occurred. For example, if a hydrostatic test resulted in a take
of golden-cheeked warbler or black-capped vireo habitat, Longhorn would
contribute the requisite monies to appropriate conservation entities acceptable to
the Service, such as Balcones Canyonlands Conservation Plan, The Texas
Nature Conservancy, or similar initiatives.
5.1
SPECIES BY SPECIES IMPACT ANALYSIS
Texas Prairie Dawn (Hymenoxys texana)
Potential impacts to the Texas prairie dawn may result from a number of
activities. Right-of-way maintenance will occur with the periodic (typically twice
per year) use of tractor drawn mowers. Tractors will be rubber-tired, but crushing
of plants could occur from time to time, particularly during blooming periods.
Mowing height will typically be 3 to 4 inches. Since only the blooming shoot is
usually that high, impacts from mowing are deemed to be minimal, except during
blooming. Impacts, while not believed to be significant, are quantified as the total
ROW (50') through the entire area of identified potential habitat. As indicated in
Table 3, this area constitutes approximately 61.3 acres. As an avoidance and
minimization measure, mowing will be scheduled to avoid the February through
April blooming season. A blooming season survey of the ROW and adjacent
areas is recommended to identify any plant locations for specific avoidance, if
present.
Three construction sites have been identified for completion in the near-
term, two dent investigations, and one anomaly investigation (ref. to Table 2).
Impact for these three construction areas will be contained within the existing 50'
ROW for relatively short distances along the pipeline (see Table 3). Within these
areas, excavation, temporary spoil storage, equipment movement, and grading
will likely result in elimination of any prairie dawn plants that may occur within the
ROW in the construction areas. The area of these impacts is already included in
the total ROW impact mentioned above.
990144BA.v-6
63
- 2/14/2000

<<<PAGE 271>>>

Navasota Ladies-tresses (Spiranthes parksil)
As in the case of the prairie dawn, periodic (twice per year) mowing with
rubber-tired tractor mowers may result in sporadic crushing of plants under
tractor tires or mower wheels, or cutting of bloom stalks. Impacts from periodic
mowing are again not expected to be significant, but in the absence of detailed
plant inventory information for the ROW, an assumed total impact for the ROW
through the identified potential habitat areas constitutes 5.2 acres (Table 3). As
an avoidance and minimization measure, mowing will be scheduled to avoid the
October and November blooming season. A blooming season survey of the
ROW and adjacent areas is recommended to identify any plant locations for
specific avoidance, if present.
No areas of construction are identified in the two potential habitat areas.
However, construction will occur just east of the most westerly potential habitat
area. The ROW is to be used for access to the construction zone (see Table 3).
It is presumed that heavy equipment movement along this portion of the ROW
will result in destruction of any plants growing at that locality. Access will be kept
within the existing 50' ROW; therefore, potential impacts have already been
calculated in the ROW maintenance value above.
Houston Toad (Bufo houstonensis)
Right-of-way maintenance will again include periodic mowing with rubber-
tired tractors.
Mowing could generally reduce grass thickness and height,
thereby improving mobility for Houston toads. However, since Houston toads are
mobile, the possibility exists for run-overs by tractor tires or jumping into the
mower blades by toads. Toads are predominantly active during a few months of
the year; therefore, the possibilities of encounter are fairly remote. As a means
of providing additional avoidance procedures, pipeline ROW maintenance will be
timed to occur in the late fall through early spring (November to January) when
the toads are generally inactive to limit the possibility of direct impact. In addition
to these avoidance procedures and the low likelihood of encounters, Longhorn
will assume that all areas of potential habitat traversed by the pipeline ROW are
suitable and will commit to compensate for the entire ROW width. From Table 3,
this amount is approximately 20.6 acres. Horizon has recommended a spring
990144BA.v-6
64
- 2/14/2000

<<<PAGE 272>>>

breeding season survey for the toad in the vicinity of, and downstream of the
pipeline to determine possible toad presence, population, and breeding areas
that could be affected.
No construction impacts to Houston toads are contemplated in this
consultation. Pipe replacements within the toad habitat area will be addressed in
the second phase consultation.
Edwards Aquifer Contributing Zone - Barton Springs Salamander
Right-of-way maintenance and four construction locations are presently
contemplated to occur within the contributing zone of the Edwards Aquifer in
Travis and Hays counties. The principal concern for impacts to listed species in
this area is by siltation from disturbed areas being transported by storm runoff to
streams that eventually run onto the Edwards Aquifer Recharge Zone, potentially
entering the aquifer, and lowering the quality of water utilized by the Barton
Springs salamander. While single projects are not likely to have any
demonstrable effects on the salamander, the cumulative effects of many
development projects throughout the recharge zone and contributing zone may
collectively cause negative impacts.
Right-of-way maintenance, consisting of mowing and trimming, is not likely
to result in any level of sedimentation or impacts since the activity will not result
in ground disturbance. Enhanced Best Management Practices (BMPs) will be
utilized throughout construction in disturbed areas to prevent sediment loads
from reaching the aquifer or significantly reduce such loads. BMPs are identified
in the Project Documentation Appendix, Stormwater Pollution Prevention Plan
(Tab 6). The BMPs will also include reclamation of disturbed areas immediately
following construction for rapid growth and stabilization of grasses and annuals.
As a result of these enhanced BMPs, no significant impacts to the aquifer
or Barton Springs salamander are contemplated.
Golden-cheeked Warbler - (Dendroica chrysoparia)
Golden-cheeked warbler habitat does not exist in the established ROW,
990144BA.v-6
65
- 2/14/2000

<<<PAGE 273>>>

but is presently adjacent to the ROW in a number of locations from Hays County
westward to Mason County. Right-of-way maintenance will not directly affect
warbler habitat, except for hand pruning of canopies which overhang the ROW.
Indirect effects may result from mowing noise or activity if birds are present in the
vicinity during maintenance activities. As a minimization procedure, Longhorn
will schedule maintenance activities to occur during the non-nesting season
(September 1 to March 1) within or near warbler habitat areas to avoid indirect
impacts. While no significant impacts are anticipated to occur, Longhorn will
mitigate for the full ROW width (50') through potential warbler habitat areas. The
area of potential effect is determined to be 103.4 acres (Table 3).
Six areas of pipeline maintenance construction or investigation are
anticipated to occur along the pipeline within areas identified as potential warbler
habitat (Table 2). Each of those areas are estimated to require additional
construction space in excess of the existing ROW by variable widths (Table 3).
The total additional impact to warbler habitat resulting from construction clearing
is 13.4 acres. The additional areas of temporary work space are needed in these
areas to facilitate temporary spoil storage, machinery access, pipe stacking, and
miscellaneous construction related activities. As avoidance and minimization
procedures, Longhorn will to the extent possible, schedule construction activities,
particularly clearing, to occur during the non-nesting period (September 1 to
March 1). As with the immediately impending construction schedule, clearing will
commence prior to March 1st and construction activities will continue continuously
until completion.
Total estimated impacts to potential warbler habitat are 116.8 acres.
Black-capped Vireo - (Vireo atricapillus)
Seven areas of potential black-capped vireo habitat exist along the ROW
between Blanco and Kimble counties. Black-capped vireo habitat, being an early
successional stage of brushy regrowth, does exist within the existing ROW in
locations where previous maintenance activities have not occurred in several
years. In this case, ROW maintenance will directly impact potential habitat within
the existing ROW. The area of direct impact for the full 50' width of the ROW
through the various habitat areas constitutes approximately 41.6 acres. Indirect
990144BA.v-6
66
- 2/14/2000

<<<PAGE 274>>>

impacts from ROW maintenance are not likely since maintenance activities will
be conducted during the non-nesting season (September 1 to March 15) for
vireos.
Four maintenance construction locations have been proposed within the
areas identified as potential vireo habitat (Table 2). Only one of those
construction sites will require clearing beyond the 50' ROW width. An additional
50' of temporary work space will be needed to facilitate temporary spoils storage,
equipment access, pipe layout and construction room. The additional acreage of
disturbance for this construction site is 0.1 acre.
The total area of impact to potential black-capped vireo habitat is 41.7
acres.
Tobusch Fishhook Cactus - (Ancistrocactus tobuschit)
Potential habitat for the fishhook cactus is very generally estimated from
general soils and plant distribution information to include the entire reach of the
pipeline's traverse of Kimble County. Without specific survey information for the
cactus, it is assumed that the entire ROW across Kimble County is potential
cactus habitat. As with the Texas prairie dawn and Navasota ladies-tresses, the
Tobusch fishhook cactus is low growing and not likely to be directly affected by
mowing, except for possible crushing by tractor tires. However, due to the
significant extent of large rocks within the ROW, mowing is not always feasible in
this region. A preferred method in rocky terrain is to back drag a bulldozer blade
across the ground which knocks down undesirable woody vegetation. This
activity can disrupt the ground surface and possibly injure or destroy cactus
plants. Therefore, direct impacts to fishhook cactus habitat may occur from time
to time. The total area occupied by the ROW across Kimble County is 212.7
acres.
Four test header installation locations are planned within the potential
fishhook cactus habitat. Each site will disturb an additional 50' width beyond the
ROW for the construction of the headers. The additional space is required to
facilitate temporary spoils storage, equipment access, pipe construction, and
testing equipment. The additional area of impact per site is between 0.1 and 0.2
990144BA.v-6
67
- 2/14/2000

<<<PAGE 275>>>

acre. The total additional impact to cactus habitat is 0.5 acre.
The total impact acreage for Tobusch fishhook cactus is 213.2 acres.
Other Species
Listed species that may occur away from or downstream of the pipeline
corridor (ie., bald eagle, interior least tern, American alligator, Barton Springs
salamander) are not likely to be adversely affected by the proposed maintenance
and minor construction activities. Any discharges of hydrotest waters are not
expected to contain levels of hydrocarbons or other toxic materials sufficient to
result in adverse impacts.
5.2
AVOIDANCE AND MINIMIZATION
Longhorn will, to the extent reasonably possible, conduct the maintenance
construction, testing, and other subject activities in a manner that avoids potential
effects to species and habitat. If avoidance is reasonably and practically
unachievable, Longhorn will conduct the activities in a manner that minimizes any
potential effects. Controls and other measures designed to achieve that goal are
described in the foregoing descriptions of the various activities. A number of
those controls and measures are summarized as follows:
1.
Identifying and marking habitat areas for avoidance;
2.
Planning project implementation to minimize the potential for any
effects;
3.
Use of FERC-qualified environmental inspectors with authority to
alter project implementation procedures in sensitive areas;
Adjusting project timing to avoid breeding populations; for example,
projects in Houston toad habitat will avoid the months of February
through November, and projects in GCW and BCV habitat areas
will avoid March through August and April through September,
respectively;
Implementing storm water pollution control BMPs even when not
required by permit;
6.
Maintaining qualified biologists in hydrostatic test project areas for
990144BA.v-6
68
- 2/14/2000

<<<PAGE 276>>>

immediate response in the event of a test water release in a habitat
area;
Avoiding, until project planning is accomplished, hydrostatic testing
over
the Edwards Aquifer recharge zone, portions of the
contributing zone, and in Houston Toad habitat areas; and
Conducting additional species surveys along the pipeline ROW to
determine actual presence or absence of species and populations
where present.
Additionally, work in areas of noise-sensitive species (i.e., GCW, BCV) will
be avoided during the breeding/nesting season. If work must occur in habitat
areas during a noise-sensitive seasons, the Service will immediately be notified.
Biological surveys of the habitat areas will be conducted prior to construction to
determine the presence or absence of species and specific locations if present.
Avoidance and minimization procedures, as appropriate to protect the species,
will be implemented based on these surveys.
5.3 PROPOSED COMPENSATION FOR POTENTIAL TAKE
Longhorn proposes the following steps for calculating compensation, for
funding that compensation, for implementing the process by which the
compensation is valued initially and in the future, and for assuring the Service,
the public and interested parties that the total compensation will be funded in full.
Longhorn has applied a formula recommended by the Service to
determine appropriate compensation. The formula is: Impact acreage × 1.2 x
fair market value of land in the area. This formula is modified for Houston toad
habitat to use a 3x multiplier instead of 1.2 due to the more critically imperiled
nature of the toad population in general. The Service also recommends the
application of a one-time 10% inflation factor to anticipate increases in land
values over time. Longhorn has calculated compensation for purposes of this BA
on the basis of this formula and best estimates of land values in the area of each
respective species. Longhorn proposes that actual land values be determined
for purposes of calculating compensation on the basis of land appraisals
according to the following process.
990144BA.v-6
69
- 2/14/2000

<<<PAGE 277>>>

Within 60 days following the Biological Opinion, Longhorn will engage two
licensed appraisers to determine the average value of land in the vicinity of the
impact areas for each species along the pipeline. If the two appraisals differ by
greater than 5%, then a third appraisal shall be engaged to reach a
determination. All appraisals shall take into account land uses and conditions in
such vicinity. The current calculation of compensation, set out below, will then
be revised based upon the average of the two or three, as the case may be,
appraisals.
Longhorn proposes a series of payments over time to fund the necessary
compensation, with such payments being made in a manner which will maximize
benefits to the potentially affected species. For example, maximum benefit to
the species may be achieved through Service concurrence that the initial
payment go toward conservation efforts directed to the Houston toad and the
Tobusch fishhook cactus; since those species face a relatively greater prospect
of decline than the remaining species.
Longhorn proposes to provide this compensation amount to one or more
conservation funds devoted to conservation of the affected species, on an annual
basis over a six year period. Future land values shall be determined on the basis
of appraisals performed every second year following the initial appraisals and
determined employing the same methodology as described above. The
remaining compensation due from Longhorn shall then be recalculated based
upon the compensation acreage remaining to be funded and the most recent
land appraisals for such acreage.
Longhorn has solicited the participation of the Service in the identification
of conservation funds that provide the greatest benefit to the affected species as
a whole. In particular, Longhorn's intent is for the funds to support conservation
efforts that employ preservation and recovery actions at least as comprehensive
as the actions recommended in the Service's December 15, 1999 Comment
Letter and in the relevant species recovery plans. Potential recipients may
include the National Fish and Wildlife Foundation, the Texas Parks and Wildlife
Department (TPWD), Texas Nature Conservancy, Texas Land Trust, Trust For
Public Lands, and similar comprehensive conservation initiatives. Longhorn
990144BA.v-6
70
- 2/14/2000

<<<PAGE 278>>>

prefers that the payments be directed to the National Fish and Wildlife
Foundation and TPWD.
This amortized payment scale will provide a reliable funding stream for the
subject species for an extended period to purchase and manage habitat areas,
enhance habitats, fund artificial propagation, and conduct other recovery efforts
identified by the various species' recovery plans.
The amortized payment schedule encourages an adaptive approach to
managing these species by allowing the Service to redirect the funds over time to
their highest and best use. As scientific research on the needs of these species
continues, the Service may find that resources for the protection of the species
should be redirected-perhaps to management and recovery practices of which
the scientific community is not yet aware. Rather than committing all the
conservation funds to one particular endeavor now, the amortized payment
schedule allows the Service to apply the funds strategically over time as
conservation priorities change and the understanding of the species grows.
An amortized payment schedule also allows the regulated community,
such as Longhorn, to commit a greater amount of funds than might otherwise be
available. A payment schedule such as this one may establish a useful
precedent that will provide an incentive for other private entities, including
pipelines, to enter into conservation agreements that otherwise may seem
financially prohibitive. This encourages voluntary compliance which ultimately
benefits the species.
The implementation of the Longhorn proposal will require that appraisals
be obtained for calculation of present-day compensation. Longhorn proposes to
accomplish the foregoing over the 60 day period following issuance of the
Service's biological opinion.
Longhorn may at its discretion, at any point in time, (a) pay all outstanding
compensation on the basis of the most recent appraised values; or (b) purchase
required acreage acceptable to the Service for any given species. Exercise of
the foregoing discretion shall reduce remaining obligations and security
requirements.
990144BA.v-6
71
- 2/14/2000

<<<PAGE 279>>>

Given the timing matters identified above, Longhorn will provide
assurance to the Service that the calculated compensation (refined on the basis
of actual land appraisals) will be funded on time and in full. Such assurance will
take the form of security that assures the Service that the compensation will be
funded. Longhorn proposes such methods as a bond, a letter of credit, an
escrow, or similar such mechanism reasonably acceptable to the Service.
The
security will cover compensation not proposed for immediate funding and the
one-time 10% escalation value applied to same. Longhorn makes this proposal
conditioned upon the requirement that, as payments are made or in-kind
compensation is provided, a corresponding reduction be made in the
compensation acreage outstanding and thus in the amount of security required.
At issuance of the Biological Opinion, Longhorn shall provide to the Service
reasonable evidence that the security is in place. The proposed payments, as
secured, will assure that the compensation acreage is in fact acquired to benefit
the species.
Based upon the Service's recommended formula, the impacts described in
Section 5.1, and best estimates of present land values, the present calculation of
compensation would be as follows:
Texas Prairie Dawn
61.3 acres × 1.2 = 73.56 acres x $3,000/ac + 10% = $242,748
Navasota Ladies-Tresses
5.2 acres × 1.2 = 6.24 acres x $1,000/ac + 10% = $ 6,864
Houston Toad
20.6 acres × 3.0 = 61.80 acres x $2,000/ac = $123,600
Golden-Cheeked Warbler
116.8 acres × 1.2 = 140.16 acres x $2,000/ac + 10% = $308,352
Black-Capped Vireo
990144BA.v-6
72
- 2/14/2000

<<<PAGE 280>>>

41.7 acres × 1.2 = 50.04 acres × $1,000/ac + 10% = $ 55,044
Tobusch Fishhook Cactus
213.2 acres × 1.2 = 255.84 acres x $1,000/ac = $255,840
Total Compensation
$992,448
The total compensation figure stated above is to be funded according to the
schedule in Table 4.
990144BA.v-6
73
2/14/2000

<<<PAGE 281>>>

Table 4
Longhorn Pipeline
Take Compensation
Bonded Amounts
Year
HT
TFC
TPD/NLT/GCW/BCV
TOTAL•
2000
123,600
255,840
379,440
2001
102,168
102,168
2002
102,168
102,168
2003
102,168
102,168
2004
102,168
102,168
2005
102,168
102,168
2006
102,168
102,168
TOTAL
123,600
255,840
613,008
992,448
Prepay Option
Longhorn may elect to prepay amounts earlier than scheduled with
corresponding drop in security and compensation requirements.
In-Kind Option
Longhorn may purchase required acreage acceptable to the Service with
corresponding drop in security and compensation requirements.
Subject to adjustment based upon appraisals to be obtained by Longhorn.
990144BA.v-6
74
- 2/14/2000

<<<PAGE 282>>>

Thus, the Longhorn proposal, which is tabulated in Table 4, may be
summarized as follows:
At issuance of Biological Opinion: Provide security for total
estimated compensation of $992,448;
During 60 days following Biological Opinion: Obtain land appraisals
to determine current value of total compensation;
3.
Within 30 days of Appraisals: Fund acreage attributable to Houston
Toad and Tobusch fishhook cactus based upon initial appraisals;
Adjust security requirement to reflect appraised values and initial
payment;
Annually following Biological Opinion:
a.
Scheduled payments are made; and
b.
A corresponding reduction is made in the compensation
acreage outstanding, and the required security is reduced to
an amount necessary to secure the then outstanding
compensation acreage; and
6.
Bi-Annually following Biological Opinion: Obtain appraisals to
determine average land values, and adjust security requirement to
reflect changes in land uses.
This commitment is being made without regard to whether or not the
pipeline is eventually placed into service; rather, this commitment is based upon
the level of take that occurs as described above.
990144BA.v-6
75
2/14/2000

<<<PAGE 283>>>

6.0 REFERENCES
Arroyo, Bryan. Threatened and Endangered Species of Texas. Austin, Texas:
US Fish and Wildlife Service, Revised June 1995.
Blair, W.F., The Biotic Provinces of Texas. Texas Journal of Science. 2:93-117,
1950.
Campbell, Linda. Endangered and Threatened Animals of Texas. Austin, Texas:
Texas Parks and Wildlife Department; Resource Protection Division,
Davis, W.D. & Schmidly, D.J.. The Mammals of Texas. Texas Parks and Wildlife
Department. Austin, Texas, 1994.
Gould, F.W.. Texas Plants: A Checklist and Ecological Summary. Texas A&M
University Agricultural Experiment Station. MP-585/Revised. College
Station, Texas, 1975.
Horizon Environmental Services, Inc. Threatened or Endangered Species
Investigations - EZ Pipeline Project. 1991.
Poole, Jackie M. and David H. Riskind. Endangered, Threatened, or Protected
Native Plants of Texas. Austin, Texas: Texas Parks and Wildlife
Department, 1987.
United States Fish and Wildlife Service. Determination of Critical Habitat for the
Houston toad. Federal Register 43(21):4022-4026. 1978.
United States Fish and Wildlife Service. Minimum Procedures for Determining
the Presence/Absence of Golden-Checked Warblers and Black-Capped
Vireos. March 7, 1994 Memorandum, Austin Field Office. 1994.
990144ba.v-6
- 2/14/2000
76

<<<PAGE 284>>>

Phase I FWS Biological Opinion
February 17, 2000

<<<PAGE 285>>>

ted States aND mere see the Inter gre
Ecological Services Field Office
FISH AND WILDLIFE SERVICE
10711 Burnet Road, Suite 200
(512) 490-0057 / 490-0974
Austin,
Texas
78758
(iax)
MARCH
18A9
February 17, 2000
Consultation Number
2-15-00-F-413
Gregg Cooke
Regional Administrator, Region 6
U.S. Environmental Protection Agency
1445 Ross Avenue, Suite 1200
Dallas, Texas 75202-2733
Rodrick Seeley
Regional Director, Southwest Region
U.S. Department of Transportation, Office of Pipeline Safety
2320 LaBranch Road, Room Number 2116
Houston, Texas 77004
Dear Mr. Cooke and Mr. Seeley:
The U.S. Environmental Protection Agency, Region 6 (EPA) (February 10, 2000) and the U.S.
Department of Transportation, Office of Pipeline Safety, Southwest Region (OPS) (February 17,
2000) submitted letters requesting consultation with a Biological Assessment for the proposed
Longhorn Pipeline Project, Maintenance Activities and Minor Construction, Houston to Crane,
Texas. This letter acknowledges the U.S. Fish and Wildlife Service's (Service) receipt of your
requests for the initiation of formal consultation under the Endangered Species Act of 1973 as
amended (U.S.C. 1531 et seq.) (ESA). The Longhorn Pipeline Partners L.P., is the applicant and
designated "non-federal Representative" for this project, and Horizon Environmental Services,
Incorporated, prepared the Biological Assessment for EPA, OPS, and Longhorn. All information
required of you to initiate consultation was either included with your letters or is otherwise
accessible for our consideration and reference. We have assigned this consultation the number 2-15-
00-F-413 and this number should be included in all future correspondence.
This letter also transmits the Service's biological opinion on the Longhorn Pipeline Project
Maintenance Activities and Minor Construction, Houston to Crane, Texas, proposed for
authorization by EPA and OPS. The Service is able to complete this consultation in the short time
frame because of the extensive coordination that occurred during informal consultation. This
Biological Opinion is only related to the activities proposed in this Phase One of the overall
consultation. The phased approach to this consultation is explained in further detail below.
1

<<<PAGE 286>>>

BIOLOGICAL OPINION
Longhorn Pipeline - Phase One
INTRODUCTION
This document represents the Service's biological opinion on the effects of the proposed actions
on the species listed in Texas. The Service has reviewed the proposed plans for the Longhorn
Pipeline Project Maintenance Activities and Minor Construction from Houston to Crane, Texas,
as outlined in the Biological Assessment provided by EPA and OPS. The first phase of the
consultation (Phase One) relates to pipeline right-of-way (ROW) maintenance (clearing and
marking, selected pipeline maintenance construction activities (pipe replacements and
lowering), and pipeline testing (investigation of possible flaws and hydrostatic pressure testing).
The Biological Assessment is hereby incorporated into this Biological Opinion by reference.
The Service will not duplicate all maps, tables, and figures but will instead refer to the Biological
Assessment. There are no species proposed for listing that would be impacted by the proposed
action, therefore, no conference opinion will be issued.
The draft Environmental Assessment on Longhorn Pipeline, and the associated Biological
Assessment are the product of a settlement reached in the matter of Spiller et al. v. Walker et al.
pending in the United States District Court in Austin, Texas (Appendix One). As part of the
Court ordered settlement, the agencies involved in the original litigation were required to
conduct an Environmental Assessment, including specifically, consideration of species listed
under the ESA. The Court ordered EPA and OPS, acting as Lead Agencies, to be responsible for
the Environmental Assessment.
The Court order provides that issuance of any finding of no significant impact (FONSI) with
regard to the proposed Longhorn Pipeline project "shall be conditioned upon implementation" of
measures to protect public safety and the environment (Settlement Stipulation at 6). The order
also prohibits the OPS from authorizing Longhorn to commence operations until Longhorn has
implemented those mitigation measures upon which any FONSI is conditioned (Settlement
Stipulation at 7). The order contemplates that Longhorn will apply for such ESA permits as may
be required in connection with the implementation of any mitigation measures upon which a
FONSI may be conditioned. (Settlement Stipulation at 7). The results of this consultation by the
Lead Agencies with the Service are expected to be incorporated in the Record of Decision issued
by the Lead Agencies. The terms and conditions, mitigatory measures and protections
incorporated herein for the benefit of species are expected to be adopted and incorporated by
Longhorn in its enforceable mitigation commitments or in its operating and maintenance
manuals subject to inspection by, and enforceable by OPS, pursuant to the Pipeline Safety Act
(49 USC 60101 et seq.).
The Court settlement specifies that Longhorn will undertake certain construction and
maintenance activities prior to issuance of a final agency decision in this matter (Settlement
Stipulation at 8-11). The parties to the settlement specifically agreed that any such investments
by Longhorn in Kimble, Menard, Hays, Travis, Caldwell, Bastrop and any counties within the
jurisdiction of the Lower Colorado River Authority after August 25, 1998 would not be
considered "for the purposes of determining the reasonableness of alternatives" (Settlement
Stipulation at 11).
2

<<<PAGE 287>>>

Although the Service and the Lead Agencies are in consultation with respect to the entire
proposed Longhorn project, this consultation is being approached in two distinct, yet related
phases. Service regulations allow for a staged consultation (50 CFR 402.14(k)) where the
Service reviews a project, and provides biological opinions on each incremental step provided
that no irreversible or irretrievable commitments of resources are made. The first phase of the
consultation (Phase One) relates to pipeline ROW maintenance (clearing and marking), selected
pipeline maintenance construction activities (pipe replacements and lowering), and pipeline
testing (investigation of possible flaws and hydrostatic pressure testing). The proposed actions
for Phase One are focused on activities that Longhorn wishes to perform before the final decision
on the environmental review process is made by EPA and OPS. The Service believes that, by
submitting the proposed action, EPA and OPS have made a determination that these activities
can proceed before the final environmental decision is made because these activities are
consistent with the current operational approvals for this pipeline and the settlement agreement.
The Longhorn Pipeline Partners wish to conduct these activities before a final decision is made
because of the potential delay in accomplishing this work due to seasonal constraints placed on
the activities by the presence of endangered or threatened species. The golden-cheeked warbler
and black-capped vireo are migratory birds that would be impacted less if this work were to
commence before the birds return to Central Texas from their wintering habitat in Mexico.
Because the pipeline is existing, routine maintenance is supposed to be occurring, and the
construction impacts proposed are prudent for whatever liquid would flow through the pipeline,
the Service believes that none of these activities constitute an irreversible or irretrievable
commitment of resources, natural or monetary, which have the effect of foreclosing the
formulation or implementation of any reasonable and prudent alternatives or measures. The
Service believes that these investments would not constitute irretrievable commitments of
resources for the purposes of Section 7(d) of the ESA. The Service has evaluated the proposed
activities only with regard to the potential impacts to listed species and compliance with the
ESA. This Biological Opinion does not indicate Service support for any alternatives, including
routing, in the EPA and OPS environmental review process and in no way should be viewed as a
factor in deciding the outcome of that process. Alternative routes may have less potential impact
to listed species. In the opinion of the Service, implementing the proposed projects before
completion of the environmental review process is a business decision made by the Longhorn
Pipeline Partners.
The second phase of the consultation (Phase Two) will be more directly related to the actual
operation of the pipeline, specifically the operation and maintenance of the pipeline system and
the potential effects of a pipeline release. The two phases can be logically separated. Phase One
of the Service's review will focus on those actions that are designed to make the pipeline safer.
The Service can complete this stage of review without pre-judging whether or not the pipeline
will be used. Phase Two of the Service's review will focus on whether and how the pipeline will
be used. It is anticipated that the consultation for the Longhorn Pipeline will also include a
Phase Two Biological Assessment and Biological Opinion that will address issues directly
related to the actual long-term operation and maintenance of the pipeline, specifically the
operation and maintenance of the pipeline system and the potential effects of emergency
response activities in the event of a pipeline release. Both EPA and OPS, within the Biological
3

<<<PAGE 288>>>

Assessment, have committed to continuing the next phase (Phase Two) of consultation.
Based on information available on the proposed project, the Service determines that there is a
reasonable likelihood that the entire project is not likely to jeopardize the continued existence of
any endangered or threatened species or result in the destruction or adverse modification of
critical habitat. During the Phase Two consultation, the Service may change this determination,
based on further review of the existing information or new information gathered during the
Environmental Assessment process or the Phase Two consultation.
This biological opinion is based on: (1) the information that EPA and OPS provided with a
request for formal consultation including the Biological Assessment, (2) the information
previously provided as part of the informal consultation (including the draft Environmental
Assessment), (3) information in our office (including information provided by the public and the
plaintiffs in the lawsuit on the Longhorn Pipeline), (4) field investigations, and (5) other sources
of information. In the request for formal consultation, EPA and OPS attached the Biological
Assessment and copies of all consultation documents for the activities proposed to be addressed
by this Biological Opinion on Phase One activities associated with the Longhorn Pipeline.
CONSULTATION HISTORY
Informal consultation between the Service, Longhorn, and the EPA has been in process since
February 1999. Longhorn was formally designated as the Non-federal Representative for
conducting informal consultation on behalf of the EPA and OPS on February 3, 2000. The
history of consultation (both informal and formal) actions follows in Table One.
Table One.
CONSULTATION HISTORY
DATE
HISTORY
10 February, 1999
Meeting Between Service and Longhorn Representatives
25 February, 1999
Meeting Between Service and Longhorn Representatives
9 March, 1999
Meeting of Service and Radian (consultants writing EA for EPA and OPS)
22 March, 1999
Meeting Between Service and Longhorn Representatives
30 April, 1999
Meeting Between Service and Longhorn Representatives
11 May, 1999
Meeting Between Service and Longhorn Representatives
12 May, 1999
Meeting with the Plaintiffs to discuss the Settlement Agreement
1 June, 1999
Meeting with Barton Springs/Edwards Aquifer Conservation District
8 June, 1999
Meeting Between Service and Longhorn Representatives
11 June, 1999
Multi-Agency Field Tour of Longhorn Pipeline in and near Austin, Texas
29 June, 1999
Meeting Between Service and Longhorn Representatives
4

<<<PAGE 289>>>

Table One.
CONSULTATION HISTORY
30 June, 1999
Telephone Conference Between Service and Department of Justice
19 July, 1999
Meeting Between Service and Longhorn Representatives
27 August, 1999
Meeting Between Service and Longhorn Representatives
10 September, 1999
Meeting Between Service and Longhorn Representative
Meeting Between Service and EP/
13 September, 1999
Meeting Between Service, Austin and Regional Director
27 September, 1999
leeting between Service Austin Office and Washington Offic
Original Draft Biological Assessment Submitted to Servic
30 September, 1999
Meeting Between Service and Longhorn Representatives
4 November, 1999
Meeting Between Service and Longhorn Representatives
9 November, 1999
Meeting Between Service and Longhorn Representatives
16 November, 1999
EPA and OPS Longhorn Public Meeting, Austin
22 November, 1999
Meeting Between Service and Longhorn Representatives
7 December, 1999
Meeting Between Service and Longhorn Representatives
8 December, 1999
Meeting Between Service and EPA
15 December, 1999
Meeting Between Service and Longhorn Representatives
Service Issues Comments on Original Draft Biological Assessment
"Not Likely to Adversely Affect" Determination.
Service Issues Response to EPA Regarding EPA's initial Request for Concurrence on a
17 December, 1999
Meeting Between Service and Longhorn Representatives
6 January, 2000
Meeting Between Service and Longhorn Representatives
Maintenance and Construction Activities in Non-habitat Areas for Listed Species.
Longhorn Requests Concurrence from Service for "Not Likely to Adversely Affect" for
10 January, 2000
EPA and OPS Longhorn Public Meeting, Austin
11 January, 2000
Meeting Between Service, EPA and OPS
17 January, 2000
Meeting Between Service and Longhorn Representatives
18 January, 2000
Meeting Between Service and Longhorn Representative
28 January, 2000
Draft First Phase Biological Assessment received for review
7 February, 2000
Meeting Between Service and Longhorn Representatives
1 February, 2000
Telephone Conference Between Service and Congressman Doggett's Staff
3 February, 2000
consultation
EPA and OPS designate Longhorn the "non-federal repersentative" for purposes of
10 February, 2000
Received EPA Request for Formal Consultation
5

<<<PAGE 290>>>

Table One.
CONSULTATION HISTORY
17 February, 2000
Received Revised Phase One Biological Assessment
17 February, 2000
Received OPS Request for Formal Consultation
DESCRIPTION OF THE PROPOSED ACTION
Project Overview - (Both Phase One and Phase Two)
The following is an overview of the project as proposed by Longhorn Pipeline and is provided to
give an overall context of the proposed project. The specific activities proposed for this
Biological Opinion are detailed in the next section.
Longhorn proposes to operate a 723-mile refined petroleum products (gasoline and jet fuel)
pipeline system from the GATX Terminal in Galena Park, Texas, (near Houston, Texas) to a
refined petroleum products terminal in El Paso, Texas. The pipeline also has a 28-mile
intermediate connection from a station in Crane County to a planned meter station in Odessa,
Texas. The pipeline consists of a combination of 20-inch and 18-inch diameter pipe from
Galena Park Station to El Paso Terminal and an 8-inch diameter pipeline from a station in Crane
County to a meter station in Odessa, Texas. Finally, three as yet to be built pipelines will
connect the El Paso terminal to interstate common carrier pipelines west of El Paso. The
pipeline's initial capacity of 72,000 barrels per day (bpd) will be supplied by a new pump station
at Galena Park and five newly constructed booster pump stations at the following locations:
Satsuma (Harris County), Cedar Valley (Hays County), Kimble County (Kimble County), Crane
(Crane County), and El Paso (El Paso County).
Two new pipeline construction projects remain to be completed. An 8-inch diameter, 2500-foot
lateral that originates at the terminus of the existing Odessa lateral will connect to a terminal
facility in Odessa, Texas, owned by Equilon. Three 8.3-mile lateral pipelines, which originate at
the El Paso Terminal, will connect with Kinder Morgan (formerly the Santa Fe Pacific pipeline)
and Chevron pipelines in the El Paso area. The connection to Kinder Morgan will consist of one
8-inch diameter pipeline and one 12-inch diameter pipeline. The Chevron connection will
consist of an 8-inch diameter pipeline. The purpose of the lateral pipelines is to connect into
Kinder Morgan and Chevron pipelines to distribute product into the Phoenix, Tucson, and
Albuquerque markets. Chevron operates an 8-inch pipeline that delivers product to the
Albuquerque market; Kinder Morgan operates one 12-inch pipeline and one 8-inch pipeline
serving the Tucson market. Other Kinder Morgan pipelines connect Tucson to the Phoenix
market.
The proposed project includes both new construction and refurbishment of an existing pipeline
that has been converted from its former use of transporting crude oil from West Texas to the
Gulf Coast area, the majority of which has been completed. As described in this chapter, the
existing pipeline has been modified to transport refined petroleum products, with flow going
from east to west. Williams Pipeline Company will be the contract operator of the Longhorn
6

<<<PAGE 291>>>

Pipeline System. Longhorn intends to transport multiple grades of gasoline and distillates,
which will include special reformulated grades of gasoline needed to control air emissions in
certain areas of the Southwest.
The Longhorn Pipeline System is designed for service in excess of 50 years and is made up of
four main pipeline segments, several stations, and one terminal, as listed below:
1.
New and refurbished 20-inch diameter pipeline from Galena Park to Satsuma;
2.
Refurbished 18-inch diameter pipeline from Satsuma Station to Crane Station;
3.
New 18-inch diameter pipeline from Crane Station to El Paso Terminal;
4.
New lateral pipeline connections to Odessa and to other pipelines at El Paso;
New Pump Stations;
6.
El Paso Terminal; and
7.
Odessa Meter Station.
A detailed description of the Longhorn Pipeline System is included in the Biological Assessment
(Project Documentation Appendix at Tab One). Future pipeline upgrades, repairs, and
maintenance beyond that identified in the Biological Assessment will be addressed in Phase Two
of the consultation.
Project Description (Actions addressed under this Biological Opinion)
This Biological Opinion only covers those portions of the overall project that have been
specifically identified in the Phase One - Biological Assessment. Appendix Two contains a list
of all of the activities covered in this Phase One consultation including ROW clearing and
maintenance, pipeline maintenance and construction, pipeline testing, and other integrity-related
projects.
Following is a description of each of these procedures and the methods by which they will be
implemented for the Longhorn Pipeline System. Additional detail may be found in Construction
Specification CS4 contained in the Biological Assessment (Project Documentation Appendix at
Tab Four.
Right-of-way (ROW) Clearing, Marking, and Maintenance
The existing pipeline ROW is about 50 feet wide and 723 miles long and most of it has been
routinely maintained and cleared for over 50 years. Longhorn has committed to bring the
surface of the ground within the ROW into "excellent condition" in order to facilitate
surveillance prior to startup of the pipeline (Biological Assessment - Project Documentation
Appendix at Tab 2). Excellent condition is that condition which provides a clear line of sight for
aerial and ground surveillance patrols in order to effectively monitor and inspect the ground
surface along the ROW. A clean and clearly marked ROW provides a distinctive line of
demarcation, indicating a change in land use, where surrounding terrain is natural or heavily
developed. These activities are routine and are conducted periodically by pipeline operators in
the United States.
7

<<<PAGE 292>>>

ROW maintenance will include mowing, brush-hogging, back-dragging, and/or hand trimming
of tall grass or woody re-growth, trimming of tree canopies overhanging the ROW, setting signs,
marking points of intersection (horizontal bends) in the pipeline with PVC posts, and painting
cross-fence posts. ROW mowing is performed by a twin-blade mower or a brush-hog drawn by
a tractor, to a height between two and four inches.
Back-dragging is a method of clearing in rocky terrain; back-dragging involves pulling a dozer
blade backwards across the ground surface which has the effect of bending vegetation over at the
ground surface. Back-dragging typically does not result in the uprooting of vegetation. Rather,
the vegetation is bent or broken just above the ground surface. Back-dragging is used only in
areas where rocks on the surface pose a risk of damage to a mower or brush-hog. Vegetation
around surface facilities such as valve settings is at times spot-treated, by hand application, with
herbicides such as Roundup and Rodeo.
Hand trimming involves line trimmers, chain saws, and similar hand-held equipment. Tree
canopies are trimmed by workers, using chain saws, that are raised within reach of the canopies
by a man-lift. Steel sign posts are typically set by driving the posts directly into the ground.
PVC posts are set into shallow holes dug by post-hole digger. In limited circumstances such as
when vandals repeatedly remove pipeline markers, sign-posts are dug by post-hole digger to
allow the posts to be set into concrete.
Clearing within areas identified as endangered species habitat will not result in any substantial
ground disturbance because only mechanical or hand cutting will be employed. The term ground
disturbance is intended to mean soil disturbance that would result from grubbing brush and tree
stumps. Back-dragging will result in some minor disturbance of the soil surface similar to
grubbing. In limited circumstances, stumps directly over the pipeline, which could have adverse
effects on the pipe, will be spot-treated by hand application, with minimal amounts of non-
aromatic and non-persistent herbicide to retard re-growth. Herbicides will be applied in
accordance with EPA-approved label directions.
All areas of the ROW are subject to periodic clearing from time to time. ROW clearing occurs at
intervals that depend upon the rate of vegetation growth, typically averaging once per year in
arid and semi-arid territory (generally, from Austin to Crane) and typically averaging twice per
year in territory with greater rainfall (generally, Houston to Austin). Further, metropolitan areas
may be mowed as frequently as monthly to meet municipal ordinance requirements and in
response to landowner requests. ROW clearing will be conducted on a schedule that avoids
impacts to species.
8

<<<PAGE 293>>>

Pipeline Maintenance - Construction Planning
Prior to project engineering and scheduling, each site is surveyed by qualified personnel to
determine whether or not the activity (a) may affect threatened or endangered species and
habitat, (b) may cause disturbance of cultural resources, (c) may be subject to Clean Water Act
Section 404 (U.S. Army Corps of Engineers jurisdiction over dredge and fill materials in waters
of the United States), or (d) may be subject to other federal, state or local laws, regulations or
ordinances. Appropriate authorizations are obtained (such as this consultation), and necessary
requirements are identified and incorporated into project planning and engineering
documentation.
Project engineers and technicians perform site inspections to identify site-specific conditions and
features that require consideration in project planning, such as site ingress/egress routes,
workspace requirements, spoil management, equipment storage, servicing and parking needs,
and the like (Biological Assessment - Project Documentation Appendix at Tab 5 and Tab 6).
Such considerations are incorporated into project planning and engineering activities. Unless
required by the particular project or by site conditions, workspace is limited to the established
ROW. Where workspace is required beyond the limits of the established ROW, those areas have
been incorporated into project documentation.
Workspace beyond the limits of the established ROW may be required for a number of reasons.
First, avoidance of habitat or the natural terrain along one side of the ROW may necessitate
expansion of workspace along the opposite side of the ROW. Second, a sloping surface gradient
at a project site may require that spoil removed from the pipeline trench be stockpiled with a
wider base, extending off of the ROW, than would be required at a project site with a level
surface. Further, a project to lower or replace pipe at a creek crossing may require water
diversion measures that necessitate a workspace wider than the established ROW. In addition,
though project equipment is typically aligned along the existing pipeline ROW, project site
conditions such as size, shape and/or slope may require that equipment be centralized in an
equipment marshaling area (typically 25 ft. wide by 100 ft. long) for temporary storage, security
and/or service.
Biological surveys encompass both areas of potential surface disturbance and areas within the
zone of potential indirect construction impacts, such as noise. In addition, applicable project
best management practices (BMPs) are identified at this stage of project planning and
incorporated into planning documentation.
A Project Construction Plan is prepared for each individual project location to document project
planning. The Project Construction Plan contains the following sections of detailed information:
Description of Work for the Project;
Responsibilities and Authorities;
Safety Requirements;
Job Contacts and Notification Requirements Matrix;
Pre-Job Training Requirements;
Environmental Protection;
Project Schedule;
Forms / Documents Required;
9

<<<PAGE 294>>>

Chronological Sequence of Events; and
Appendices as follows:
Appendix 1 - Location Map
Appendix 2 - Drawings, Calculations, and Specifications
Appendix 3 - Environmental Protection Plan
Appendix 4 - Storm Water Pollution Prevention Plan
Appendix 5 - Safety Procedures Document
Appendix 6 - Sample Forms
Project BMPs are defined as procedures and specifications by which environmental controls will
be implemented and include such items as sedimentation and erosion controls, reclamation
procedures, minimization and avoidance procedures, inspection and reporting procedures, spill
containment and cleanup procedures, procedures for addressing unforeseen circumstances,
procedures for addressing foreseen, but unpredictable circumstances, and others. Project BMPs
are identified and adapted from technical guidance manuals generally accepted as providing the
appropriate environmental protection measures, such as the Texas Natural Resource
Conservation Commission (TNRCC) technical guidance manual, Federal Energy Regulatory
Commission (FERC) Environmental Guidance Manuals, and the City of Austin Environmental
Criteria Manual. BMPs are incorporated within the Longhorn Storm Water Pollution Prevention
Plan (SWPPP); an example of an SWPPP is included the Biological Assessment (Project
Documentation Appendix at Tab 6).
Project Environmental Inspectors
Longhorn and Williams shall employ the services of environmental inspectors (such as Horizon
Environmental Service Inc. and 3D/International) at every project site with associated species-
related constraints. These environmental inspectors are qualified under FERC guidelines. The
environmental inspector will remain at each project site during the period of activity to ensure
compliance with all project constraints and project BMPs. The inspector is authorized to dictate
any additional project BMPs that may become necessary during the activity and to modify work
activities and progress to the extent necessary to ensure compliance with project environmental
constraints. However, in the event of a conflict between project constraints and sound
engineering practices, the inspector shall consult with project engineers and the Service, as
appropriate, to achieve project goals while minimizing any impacts to listed species or the
environment. The environmental inspector retains oversight of site closure and performs, or
supervises the performance of, post-activity inspections of project BMPs until site stabilization is
achieved. The environmental inspector will produce appropriate documentation for each
construction location to include BMP compliance logs, photographs, as-built dimensions of
disturbance, and any encounters with listed species during the construction process. The
completion reports for projects listed in Appendix Two, will be provided to the EPA, OPS, and
the Service, annually.
Site Preparation
Prior to site entry, at locations where avoidance and/or minimization of species effects has been
recommended, a qualified biologist will clearly identify areas for avoidance and will stake and/or
flag such areas. The project environmental inspector also surveys the site to ensure that all such
avoidance areas are clearly identified in accordance with conditions approved in the consultation
process and confirms other site-specific areas in which disturbances may occur such as routes of
10

<<<PAGE 295>>>

ingress/egress, spoil management areas, equipment marshaling areas, workspace areas, and
similar areas needed for construction. Project BMPs are reviewed prior to site entry, and the
locations of any necessary physical control measures to be employed are identified. A survey
crew will precede the project equipment and mark the project boundaries. In addition, the
pipeline centerline will be marked at 100-foot to 200-foot intervals.
Site Entry
Upon site entry, the necessary project equipment is transported to the site via the designated
route for ingress/egress. Site access is achieved via improved roadways and the established
ROW, using the shortest available route between improved roadways and the project site.
Routes of ingress/egress account for any potential for effects to threatened and endangered
species and habitat that may exist along the ROW between the improved roadway and the project
site, as well as accounting for other potential impacts to the environment. At times, equipment
will remain on-site only during the time that it is in active use to allow it to be shared between
nearby project sites. However, impacts to potential habitat for listed species from site
ingress/egress will be minimized to the maximum extent practicable.
Prior to any excavation, site vegetation is removed, and project BMPs are implemented. Site
vegetation is cleared to the extent necessary for project completion, so long as the vegetation is
not located in areas identified for avoidance. Clearing is accomplished by the methods described
in above (ROW Clearing), though vegetation within the workspace may require removal.
Project BMPs are installed in accordance with project planning documentation and in accordance
with the site-specific SWPPP.
Task Descriptions - (Process Once All Authorizations Are Obtained)
The following task descriptions identify process steps that occur once all authorizations are
obtained and regulatory requirements are identified and incorporated into project planning and
engineering documentation. Detailed procedures for each of the activities summarized below are
available in Pipeline Construction Specification CS4, which is included in the Biological
Assessment (Project Documentation Appendix at Tab 4). In the event of a conflict between
Construction Specification CS4 and the site-specific components of the Project Construction
Plan, the Project Construction Plan will be followed.
Pipeline Lowering and/or Replacement - Open Terrain
Once the project site has been prepared and equipment brought onto the location, the following
major activities take place.
•
The pipeline segment to be replaced is isolated by cutting and plugging at
boundaries. Williams operating personnel will establish that the line is not
pressurized and is properly isolated such that the contractor may cut the pipeline
at the project limit boundaries. Mechanical plug devices will be utilized to
prevent residual product leakage from the pipeline segments or entry of foreign
materials into the pipeline. These devices shall be secured to prevent their loss or
tampering.
11

<<<PAGE 296>>>

Remove large rocks, if any, from ROW work area to appropriate disposal/storage
area. Track hoes with buckets are used, unless larger rocks require grapple
capable (clam) buckets.
Remove and set aside topsoil spoil (double ditch practices). Double-ditching will
be required in areas where native plant communities need to be re-established, or
there are topsoil improvements, such as sodded lawn areas and cultivated fields.
Double-ditching allows topsoil management by making two passes to remove and
segregate spoil; one to remove and set aside topsoil and one to remove and set
aside subsoils.
Remove overburden and expose pipe. Utilizing track hoes, remove and set aside
overburden from the pipeline and load and remove excess amounts from the work
site for disposal. Unsuitable overburden (i.e., large rocks) will be disposed of in
approved sites.
Cut pipe into subsections at road and water crossings. Expose and cut the
pipeline at road crossing boundaries to isolate the removal section into
subsections. Utilize drain pans to recover any remaining liquids as the cut is
made. Install mechanical plugs in all exposed pipe ends.
Raise and crib pipe alongside the trench. Properly manage any coating which
comes loose from the pipe.
• Prepare and wrap pipe for disposal. Double wrap the pipe sections with 6-mil
thickness plastic wrap, taping and sealing each wrapping separately. Ensure that
the ends are sealed to prevent any release of coating.
• Remove pipe from ROW. Load and remove the wrapped pipe sections by truck.
Care will be taken to preserve the plastic wrapping on the pipe. Secure the pipe
to the trailer and haul to the disposal site for final disposition.
• Cleanup and grade ROW for survey and trenching operations.
•
Capture, contain, and remove any remaining coating materials/scraps using
project-prescribed methods for asbestos containing materials. Prepare the grade
on either side of the ditch to accommodate the trenching machinery, removing
any large rocks. Survey crew should mark and stake the centerline offsets as
required by the trenching crew.
•
Deepen trench to new depth. Depending upon the length of the desired lowering
and/or replacement, and depending upon whether the trench is in soil or rock, a
track-hoe or wheel trencher (rock saw") deepens the trench to the new depth. A
wheel trencher is typically used for longer trenches and trenches in consolidated
rock. Dust generation is monitored during trenching, and a water fog of the
trenching mechanism may be employed to minimize airborne dust in non-rural
areas.
12

<<<PAGE 297>>>

•
String new pipe along trench. As the ditch is prepared, the pipe may be strung
along the workpad in anticipation of measuring and marking for bending,
welding, and lowering operations. The survey crew will note the pipe heat and
identification numbers sequence for the individual pieces as they are placed. The
survey crew will survey the new ditch profile and mark the pipe for calculated
field bends.
Make field bends. The field bending crew will proceed ahead of the welding
crew to make any required field bends. The contractor may also elect to set up
field bending in one of the equipment marshaling areas and perform bending there
rather than on the ROW.
Weld and Radiograph new pipeline. The welding crew will proceed to weld the
pipeline. Inspectors will survey and note the weld numbers and identification of
the welders for this activity. The radiography crew will follow the welding crew.
Inspection will be per standard specification API 1104 and include 100%
radiography of all girth welds.
•
Apply weld joint coating and inspect pipeline coating for "holidays". A holiday
is a point where the coating fails to electrically insulate the pipe. Weld joint
coating will be applied as specified in the Project Construction Plan. This will be
by field-applied FBE (fusion bond epoxy). Following weld joint coating, the
entire coating system will be inspected for holidays and repaired as required.
Pad and lower pipe. Pad the ditch and lower the pipeline as specified in
Construction Specification CS4. Install ditch plugs as required to stabilize
pipeline during hydrotest and backfilling. The pipeline coating will receive a
final "jeeping" as the pipe is lowered to ensure its integrity. Jeeping is the
process of electrically inspecting the pipeline coating to ensure that no holidays
exist in the coating, so named due to the "jeeping" sound the inspection device
emits when a holiday is identified.
•
Complete as-built survey. Complete as-built survey activities, noting weld
locations, pipe identification codes, and location and stationing of bends, fittings
and other such features for inclusion in alignment sheet drawings.
Backfill and compact trench. Backfill and compact the ditch according to
Construction Specification CS4, maintaining sufficient cover to allow for settling.
Install ditch breakers and silt fencing as appropriate for surface erosion control
until the site is stabilized.
Perform hydrostatic pressure test on new pipeline segment. Obtain fresh water
for pressure test and begin line fill behind a pig. The test pressure and test
duration will be established and specified in the Project Construction Plan or in
separate hydrostatic testing plans.
•
Drain and dispose of hydrostatic test water. Upon completion of the hydrostatic
test, the test water is either pushed with nitrogen to a subsequent test site or
13

<<<PAGE 298>>>

removed into mobile tanks for hauling to a disposal facility. Test water is
controlled to ensure that it is fully contained in order to prevent discharge to the
environment.
•
Perform final tie-ins. Remove the test headers and make the final tie-ins of the
new pipe segment to the existing pipeline. The tie-in welds will be 100%
radiographed to ensure their integrity. Coat the tie-in welds with an appropriate
joint coating system compatible with both FBE and coal tar coatings. The coating
is inspected, or jeeped, and any holidays are repaired. The tie-in locations are
backfilled and compacted.
•
Clean, grade, and seed ROW. Following installation of erosion control measures,
re-seed the ROW with native grass seed and/or sod as prescribed for the location.
Re-install pipeline markers and any traffic control devices to limit or restrict
ROW access by motor vehicles.
•
Perform site cleanup and restoration. Clean up equipment marshaling and
material storage sites, ensure that the worksite access roads are restored to prime
condition, and that any road access ways are cleaned and restored.
Pipeline Lowering and/or Replacement - Creek Crossing
Pipeline lowering and/or replacement at creek crossings follows generally the same sequence of
activities described above for open terrain; however, the additional activities described below
apply to the actual creek crossing area. In addition, creeks may be crossed by either trenching or
boring. Each crossing method is summarized separately below.
Trenching
A trenched crossing is lowered and replaced in much the same manner as an open terrain project;
however, incremental measures are employed to ensure both that erosion and sedimentation are
minimized and that no potentially harmful materials are discharged to the waterway. Pipeline
Construction Specification CS4 in the Biological Assessment (Project Documentation Appendix
at Tab 4) provides additional details.
•
Cut pipe at creek crossings. Expose and cut the pipeline at the creek crossing
boundaries to isolate the removal section into subsections. Utilize drain pans to
recover any remaining liquids as the cut is made. Install mechanical plugs in all
exposed pipe ends.
•
Implement water quality protection measures. Staging areas, spoil storage areas,
and additional workspace areas are located in upland areas above the creek bed.
Hazardous materials such as chemicals, fuels, lubricating oils and any other
potentially harmful materials are maintained at least 100 feet from the water body.
BMPs are implemented to prevent sedimentation. Flumes, dams, equipment
bridges and other diversion devices are installed as necessary to perform "dry
ditch" excavation.
14

<<<PAGE 299>>>

•
Erosion control measures are employed after project completion to ensure that
stream flows do not cause erosion of disturbed areas and subsequent
sedimentation. Erosion controls protect against sedimentation and prevent
stream flow from removing pipeline cover which could expose the pipe to stream
bed forces. Erosion control measures are site-specific, depending upon site
conditions, and include berms, dikes, water bars (perpendicular to the pipeline
alignment), silt fences, staked hay bales, seeding, mulching, hydro-mulching, rip-
rap, and trench plugs.
Boring
Stream crossings may be installed by boring rather than trenching, depending upon hydrologic
setting, engineering considerations, and soil types. The existing pipeline may be abandoned in
place after obtaining approvals from the landowner and, if necessary, state and federal
authorities, and after (a) filling the pipe with an inert material such as grout or concrete, or (b)
sealing the ends of the pipe. The pipe may not be abandoned in place if its presence could
interfere with stream flows or interfere with future uses of the waterway.
Boring a stream crossing requires the use of a work space for installation of bore pits in which
the boring equipment operates. The boring operations typically require a workspace
approximately 100 to 250 feet wide by 150 feet long. The work spaces are located above the
high water mark unless topography or other factors dictate otherwise. Typically, no instream soil
disturbance occurs, and BMPs are employed to ensure that spoil storage and other project
activities do not cause erosion or sedimentation.
From within the bore pits, the boring equipment creates a parabolic pathway to the pit on the
other side of the stream bed. Bored material is circulated out of the bore and retained at the
upland spoil storage area. The bore is sealed with grout or bentonite to fill fissures along the
course and to ensure bore stability.
The new pipe is then pulled through the bore using equipment designed for that purpose. Once
the pipe is welded, inspected, surveyed, coated and tested, the excavations are filled and
compacted, and the site is restored. Site restoration and stabilization is achieved in the same
manner as described in above (Pipeline Lowering and/or Replacement - Open Terrain). Any
necessary erosion and sedimentation controls are employed, and the site is inspected and
maintained until final stabilization is reached.
Hydrostatic Testing - Overview of Activities
A hydrostatic pressure test is scheduled to be performed to ensure the integrity of the system.
This test is scheduled to commence in February 2000 and conclude in May 2000. Hydrostatic
testing will start at the Longhorn GATX pump station in Galena Park (Houston) and proceed
westward to Crane Station. The test medium will be potable water from a local municipal supply
source. In the event some water is lost due to pipe failure, or if water is needed to fill longer test
sections, fresh make-up water will be acquired, by permit, from sources crossed by the pipeline
(i.e., from rivers or streams) or other sources of fresh water.
The hydrostatic testing occurs in segments, which are subdivided into test sections of varying
lengths. Factors that contribute to test section length include:
15

<<<PAGE 300>>>

(a)
target test pressures;
(b)
pipe size and grade;
(c)
the presence or absence of species and habitat;
(d)
the location of valves and pump stations; and
(e)
elevation changes along the pipeline.
Due to additional factors, two test sections will not be tested during the Houston to Crane
hydrostatic testing project. Those two sections are areas that encompass habitat for the Houston
toad and areas of potential effect to the Barton Springs Salamander (including the recharge zone
and part of the adjacent contributing zone (on each side) of the Edwards Aquifer). Rather, those
sections will be tested after Phase Two consultation relating to pipeline operation, maintenance
and emergency response, and after maintenance construction to replace pipeline segments in
those areas is completed.
To facilitate hydrostatic testing of the pipeline, headers will be installed on the pipeline at
intervals along its length which divide the pipeline into segments for discrete testing. There are
forty (40) header sites involved in the test. A general description of the installation of the test
headers follows. Additional information is provided in the Biological Assessment (Project
Documentation Appendix at Tab 8). Headers vary in configuration; however, all function
similarly to allow the introduction of test water, the pressurization of the test segment and the
displacement, after testing, of the test water to the following test section.
•
Prior to any work, the sites will be subject to an environmental, endangered
species, and archeological survey conducted by qualified third-party biologists
and archeologists. The headers will be installed by excavating an area
approximately 20 ft. wide x 80 ft. long x 4 ft. deep around and under the pipeline.
The spoil will be stored on the temporary work easement. The topsoil will be
segregated from the sub-grade for restoration of the site following the hydrostatic
test. Storm water management during construction and testing will be by methods
prescribed in the SWPPP, an example of which is included in the Biological
Assessment (Project Documentation Appendix at Tab 6).
•
The exposed pipe will be cut and spread apart horizontally, and pre-fabricated
headers will be welded to each section. The downstream header shall have a wire
brush pig and displacement pig inserted in it before it is welded on the pipeline.
A 6-inch temporary crossover pipe with valve will be installed between the
upstream and downstream header. Upon completion of the test, the hydrostatic
test water will be displaced into the next test segment by nitrogen. The test
section will be vented to atmosphere and the temporary piping and headers will
be removed. The pipeline will be tied back together with a joint of new pre-tested
pipe and the joints will then be coated and wrapped to provide corrosion
protection. Coating is inspected for holidays, and repairs are made if holidays are
identified. The excavated area will be backfilled and compacted with the sub-
grade material in the spoil pile followed by the topsoil to finished grade to match
the surrounding terrain. The disturbed area is seeded with native grasses or sod,
and BMPs are inspected and maintained until the site is stabilized. Total surface
16

<<<PAGE 301>>>

workspace requirements for test header installations are about 100 feet wide by
150 feet long along the pipeline.
Hydrostatic Testing - Potential Failure of Pipe
The locations of potential hydrostatic test failures cannot be accurately predicted, the volume of
test water discharged cannot be accurately predicted or calculated, and the number of
investigative excavations cannot be predicted. The inability to accurately predict the potential
impacts of hydrostatic test failures precludes any pre-activity attempt to predict and/or estimate
the potential effects of test failures. Any such attempt would be likely to result in inaccurate
estimates. Therefore, Longhorn proposes to provide for a contingent methodology for
calculating any such effects.
Of the methodologies available for calculating the effects of activities upon species and habitat,
the most applicable is the Habitat Equivalency Analysis (HEA) methodology developed by the
National Oceanic and Atmospheric Administration for Natural Resources Damages Assessments
(NRDAs).
The HEA methodology is briefly described by the following steps.
•
The duration and extent of injury are documented and estimated from the time of
injury until the resource recovers to baseline.
The services provided by a compensatory project are documented and estimated
over the full life of the project.
•
The size of a compensatory project is calculated such that the total increase in
services provided by the compensatory project equals the total interim loss of
services due to the injury.
•
The cost of the compensatory project is calculated.
A more detailed description of the HEA methodology is provided in Biological Assessment
Project Documentation Appendix at Tab 10. Longhorn's will execute the following sequence of
measures in the event a hydrostatic test discharge occurs in areas of concern for species and/or
habitat:
In the event of a test failure, immediately notify a qualified biologist, who will be
maintained on standby along the test segment, and direct the biologist to the
failure site;
•
If a discharge occurs, the biologist will assist the identification of response
actions to minimize potential impacts to the environment; and,
•
The biologist will perform a field survey to document the loss of, destruction of,
or injury to natural resources (a) at the location of any excavation, whether the
excavation is for location of a failure or for repair of pipe; (b) within the area of
17

<<<PAGE 302>>>

impact of the test water; and (c) in any other areas affected by the response to the
test failure, as at any other construction site.
The effects, if any, of the hydrostatic test failure upon species and/or habitat will then be
calculated pursuant to the HEA methodology. Longhorn shall compensate for the value of any
such adverse effects by paying the monetary value of an appropriate compensation project to
conservation efforts directed at the preservation and recovery of the affected species and habitat
in the region where the impact occurred. For example, if a hydrostatic test resulted in a take of
golden-cheeked warbler or black-capped vireo habitat, Longhorn would contribute the requisite
monies to appropriate conservation entities acceptable to the Service, such as Balcones
Canyonlands Conservation Plan, The Texas Nature Conservancy, or similar initiatives.
Cathodic Protection Enhancements
Enhancements of the pipeline cathodic protection system consist of (a) installation of anode beds
and (b) re-coating of sections of existing pipe. The cathodic protection system protects the pipe
from corrosion. These enhancements are identified and described in the Biological Assessment
(Project Documentation Appendix at Tab 2), and the locations where activities may affect
species and habitat are identified in Appendix Two. Project planning is performed in a manner
similar to that described above.
Installation of deep anode ground beds requires a series of vertical bores within which sacrificial
anodes are placed; the anodes within each bore and among the series of bores are connected by
subsurface wiring that is then connected to the pipeline. The bores and wiring trenches are
installed within the existing ROW. During boring, a circulating pit is dug to contain cuttings
removed from the bore. After project completion, the pit is filled, excess cuttings are removed
for disposal, and the site is closed in the manner described in previous discussions of
construction site closure. An example project work plan and related diagrams that provide
additional detail about deep ground-bed installation are included in the Biological Assessment
(Project Documentation Appendix at Tab 11).
Pipeline coating reconditioning involves the same activities required for a pipeline lowering or
replacement, with the exception of the process steps to remove existing pipe and install new
pipe. A coating replacement site undergoes the project planning, site preparation, site entry, and
site closure steps much as described above. Since the pipe is not cut, any residual liquids within
the pipe do not present contamination potential. Asbestos containing pipe coating is managed in
accordance with the provisions of the Environmental Protection Plan and the Project
Construction Plan (Biological Assessment - Project Documentation Appendix at Tabs 5 and 3,
respectively). All coating reconditioning is inspected, or "jeeped," and any holidays are
repaired.
Surge Pressure Protection
To reduce the risk of over-pressurization of the pipeline, Longhorn will implement system
changes and operating practices to limit surge pressures to no more than maximum operating
pressure in sensitive and hypersensitive areas identified by the EPA and OPS. (Biological
Assessment - Project Documentation Appendix at Tab 2). One system change involves the
installation of over-pressure activated by-pass systems that will allow a pressure spike to be
relieved around certain gate valves. The installation of a by-pass system involves the same
18

<<<PAGE 303>>>

process steps as the installation and removal of a hydrostatic test header; see above (Hydrostatic
Testing - Overview of Activities). The by-pass system to be installed at the east bank of the
Llano River will use the same work location as the hydrostatic test header to be installed at that
valve site.
Investigations
Projects to investigate possible pipe dents and corrosion anomalies follow the same planning and
preparation procedures for a pipeline lowering/replacement, but on a lesser scale. Table 2
identifies relevant information for, and the locations of, projects to investigate possible pipe
dents and corrosion anomalies.
Typical investigation sites require a trench approximately 20 feet in length. If a dent or anomaly
cannot be field repaired, a segment of pipe will be removed and replaced, with the length
replaced at least twice the pipe diameter. Coating and coating inspection and repair, as well as
site closure, follow the procedures described in Section 4.0 of the Biological Assessment.
Avoidance and Minimization
Longhorn will, to the extent reasonably possible, conduct the maintenance construction, testing,
and other subject activities in a manner that avoids potential effects to species and habitat. If
avoidance is reasonably and practically not achievable, Longhorn will conduct the activities in a
manner that minimizes any potential effects. Controls and other measures designed to achieve
that goal are described in the foregoing descriptions of the various activities. A number of those
controls and measures are summarized as follows:
• Identifying and marking habitat areas for avoidance;
• Planning project implementation to minimize the potential for any effects;
Using FERC qualified environmental inspectors with authority to alter project
implementation procedures in sensitive areas;
Adjusting project timing to avoid breeding populations; for example, projects in
Houston toad habitat will avoid the months of January through June and projects
in golden-cheeked warbler and black-capped vireo habitat areas will be avoided
March 1 through August 1 and March15 through September 1, respectively;
•
Implementing storm water pollution control BMPs even when not required by
permit;
•
Maintaining qualified biologists in hydrostatic test project areas for immediate
response in the event of a test water release in a habitat area;
•
Avoiding, until project planning is accomplished, hydrostatic testing over the
Toad habitat areas; and
Edwards Aquifer recharge zone, portions of the contributing zone, and in Houston
19

<<<PAGE 304>>>

•
Conducting additional species surveys along the pipeline ROW to determine
actual presence or absence of species and populations where present.
Additionally, work in areas of noise-sensitive species (i.e., golden-cheeked warbler and black-
capped vireo) will be avoided during the breeding/nesting season. If work must occur in habitat
areas during noise-sensitive seasons, the Service will immediately be notified.
Proposed Minimization to Offset Impacts to Listed Species
Land Conservation Funding
The extent of the project and timetable for implementation prevent Longhorn from completing
detailed surveys for threatened and endangered species in all potential habitat where disturbance
or destruction may occur, due to the variable survey times for each species and extensive
amounts of habitat areas involved. Exact quantification of impacts to all listed species from
scheduled activities is not possible if the project is to be completed on a timely basis. Therefore,
Longhorn has requested that the Service prepare a biological opinion based on an evaluation of
impacts to potential habitat, rather than impacts to individuals or identified occupied habitat.
Longhorn proposes to provide benefits to the species based on potential habitat impacts as if it
were occupied. This will insure that all possible impacts are considered and provide maximum
species benefits. Longhorn will apply a standard formula to potential impacts to determine
appropriate minimization. The formula is: impact acreage × 1.2 x fair market value of land in the
area. This formula is modified for Houston toad habitat to use a 3x multiplier instead of 1.2 due
to the more critically imperiled nature of the toad population in general. Longhorn will also
apply a one-time 10% inflation factor to anticipate increases in land values over time.
Within 60 days following the Biological Opinion, Longhorn will engage two licensed appraisers
to determine the average value of land in the vicinity of the impact areas for each species along
the pipeline. If the two appraisals differ more than 5%, then a third appraisal shall be obtained to
reach a determination. All appraisals shall take into account land uses and conditions in the
vicinity. The current calculation of compensation, set out below, will then be revised based upon
the average of the two or three appraisals.
Longhorn proposes a series of payments over time to fund the habitat acquisition, with such
payments being made in a manner which will maximize benefits to the potentially affected
species. The initial payment will go toward conservation efforts directed to the Houston toad
and the Tobusch fishhook cactus because those species face a relatively greater prospect of
decline than the remaining species.
Longhorn will provide the land conservation funding amount to one or more conservation
organizations with funds devoted to conservation of the affected species. Payments will be made
on an annual basis over a six-year period. Future land values shall be determined on the basis of
appraisals performed every second year following the initial appraisals and determined
employing the same methodology as described above. The remaining compensation due from
Longhorn shall then be recalculated based upon the compensation acreage remaining to be
funded and the most recent land appraisals for such acreage.
20

<<<PAGE 305>>>

Longhorn and the Service will identify conservation organizations that provide the greatest
benefit to the affected species as a whole. Potential recipients may include the National Fish and
Wildlife Foundation, the Texas Parks and Wildlife Department (TPWD), Texas Nature
Conservancy, Texas Land Trust, Trust For Public Lands, the Hill Country Conservancy and
similar comprehensive conservation initiatives. The Service will also work with TPWD and
other partners to accomplish the greatest benefit for listed species.
Longhorn may at its discretion, at any point in time, (a) pay all outstanding compensation on the
basis of the most recent appraised values; or (b) purchase required acreage acceptable to the
Service for any given species.
Given the timing matters identified above, Longhorn will provide assurance to the Service that
the calculated compensation (refined on the basis of actual land appraisals) will be funded on
time and in full. Such assurance will take the form of security that assures the Service that the
compensation will be funded. Longhorn proposes such methods as a bond, a letter of credit, an
escrow, or similar such mechanism reasonably acceptable to the Service. The security will cover
compensation not proposed for immediate funding and the one-time 10% escalation value
applied to same. Longhorn makes this proposal conditioned upon the requirement that, as
payments are made or in-kind compensation is provided, a corresponding reduction be made in
the compensation acreage outstanding and thus in the amount of security required. Before
issuance of the Biological Opinion, Longhorn shall provide to the Service reasonable evidence
that the security is in place.
Based upon the formula, and the impacts described above, and assumed land values, the present
calculation of land conservation funds for minimizing adverse affects would be as follows in
Table Two.
Table Two. Proposed Minimization to Offset Impacts to Listed Species
Price
Inflation
Species
Acres
Multiplier
Acres
per acre
factor
Total ($)
Texas prairie
61.3
1.2
73.56
$3000
10%
242,748
dawn
Navasota
5.2
1.2
6.24
$ 1000
10%
6,864
ladies'-tresses
Houston toad
20.6
3.0
61.80
$2000
pay now
123,600
Golden-
116.8
12
140.16
$2000
10%
308,352
cheeked
warbler
Black-capped
41.7
1.2
50.04
$ 1000
10%
55,044
vireo
Tobusch
213.2
1.2
255.84
$1000
pay now
255,840
fishhook cactus
21

<<<PAGE 306>>>

Total
992,448
Longhorn's Monitoring Commitment
In addition to Longhorn's land conservation funding, they have also committed to survey the
existing ROW to determine the presence/absence of listed species. The following summarizes
the Longhorn Monitoring Commitment for each potentially affected species.
Longhorn will survey for the Texas prairie dawn within the potentially suitable
habitat areas to confirm its presence or absence. The survey will be conducted
within the ROW in areas identified as potential habitat in March of 2000 to
determine if the Texas prairie dawn is present, and if so, its distribution and
abundance.
Longhorn will conduct a Fall survey (15 October to 15 November, 2000) for the
Navasota ladies'- tresses within the ROW if suitable climatic conditions occur to
determine the presence or absence of this species, and if present, its distribution
and abundance.
•
For the Tobusch fishook cactus, Longhorn will conduct a blooming period survey
(March to April 2000) within the ROW throughout Kimble County to determine
the species' distribution and abundance.
One or more additional Spring surveys (as acceptable to the Service) for the
Houston toad will be conducted along and downstream of the pipeline to
determine the presence or absence of toads and their overall distribution and
abundance.
•
One to two additional Spring breeding season surveys (as acceptable to the
Service) will be conduced for the golden-cheeked warbler along and adjacent to
the ROW within the potential habitat areas to determine habitat utilization and
overall distribution and abundance.
•
One to two additional spring breeding season surveys (as acceptable to the
Service) will be conduced for the black-capped vireo along and adjacent to the
ROW within the potential habitat areas to determine habitat utilization and overall
distribution and abundance.
STATUS OF THE SPECIES/ENVIRONMENTAL BASELINE
Status of the Species and Distribution
The following is a review of the status of each species being considered in this biological
opinion that may be adversely affected by the proposed action. The Service has reviewed the list
of threatened and endangered species and identified potential impacts to the following species.
Texas prairie dawn (Hymenoxys texana) - The Texas prairie dawn is a small, delicate annual to
6 inches tall with single or branching stems. It has small yellow flowers blooming in late March
22

<<<PAGE 307>>>

to early April. It occurs in sparsely vegetated areas of fine-sandy compacted soil. Specifically,
the species occurs in the northern part of the Gulf Coastal Prairie in Harris and Fort Bend
counties, where it is found in poorly drained depressions or saline swales around the periphery of
low, natural mounds (mima mounds) in open grasslands. These mostly barren areas are sparsely
vegetated, and the soil is often covered with a blue-green alga (Nostoc sp.). It can also occur on
disturbed soils such as rice fields, vacant lots, pastures, and possibly pipeline ROW if the soil
structure remains relatively intact.
There are fewer than 35 known sites recorded for the species, and several have been lost in
recent years to urbanization in the Houston area. Most populations remaining are small, and are
on private land. Very few sites currently have any form of protection. The primary threat to the
species is habitat destruction as a result of urbanization, roadway construction, and conversion of
habitat for agricultural purposes.
An assessment of potentially suitable habitat for the Texas prairie dawn was conducted by
Horizon in early June 1999 along the Longhorn pipeline ROW in western Harris and eastern
Waller counties from the Satsuma Station on the west edge of Houston to near Monaville in
Waller County. Three areas along the ROW, one in Waller County and two in Harris County,
exhibited native range conditions with suitable soils that could be considered potentially suitable
habitat areas for the prairie dawn. All other areas along the pipeline within the area investigated
had been converted to row crop (corn), monoculture, hay or grazing pasture, or disturbed for
land development. A survey for the prairie dawn has not been conducted within the potentially
suitable habitat areas to confirm its presence or absence.
Navasota ladies'-tresses (Spiranthes parksii) - The Navasota ladies' tresses was listed as
endangered on May 6, 1982, without critical habitat. This member of the orchid family occurs
primarily in moist, sandy soils in small openings in post oak savanna vegetation. The species is
known to occur in Brazos, Burleson, Fayette, Freestone, Grimes, Jasper, Leon, Madison,
Robertson, and Washington counties (USFWS 1984b).
Currently, approximately 149 sites have been recorded, representing perhaps 75-80 distinct
population areas, predominantly concentrated around two centers of distribution, one in southern
Brazos County and one in central Grimes County. Some of these recorded sites have been
damaged or destroyed since they were reported. Together these population centers contain the
majority of known sites and individuals (Wilson 1993). However, the majority of sites contain
fewer than 25 recorded plants. It is known that for this species not all individuals in a population
are visible above ground in a given year, and most of these sites have been visited only once, so
demographic data on populations is very limited. Nevertheless there is great concern among
botanists that most of these sites may not represent viable populations.
Navasota ladies'-tresses occur in a variety of moist sandy soils near drainages, in the Post Oak
Savannah vegetation associated with the Navasota, Brazos, and Trinity River watersheds.
Navasota ladies'-tresses are typically found on erosional remnants between rills in slightly to
moderately eroded areas along minor intermittent tributaries, from the upper drainage head,
extending along the edges of temporary streams to the flood plain of permanent streams.
Navasota ladies-tresses grow on sandy loam soils and are often associated with post oak,
blackjack oak, yaupon, slender bigelowia (Bigelowia nuttallii), and Spiranthes cernua.. Typical
23

<<<PAGE 308>>>

habitat consists of natural openings in upland Post Oak Savanna vegetation (Poole and Riskind
1987, USFWS 1984b, Wilson 1993). Plants are believed to be situated where subsurface flow or
seepage of water occurs seasonally, a common feature in other species of the genus (Arft and
Ranker 1995, Kathy Parker, pers. comm.). While Navasota ladies'-tresses is found in small
naturally created openings in the post oak woodlands, it cannot be regarded as a disturbance
species, as it usually occurs in well developed woodland and is not a colonizer of extensively
disturbed areas. There are few records in flood plain forests, open savannahs and shrublands that
have experienced little or no grazing pressure, and in hillside seepages.
Navasota ladies'-tresses is extremely slow-growing and long-lived. Rosette leaves support the
formation of a storage tuber between November and March that sequesters resources in
preparation for sending up a leafless bloom stalk at some future time. It is believed that often
plants require more than one year of photosynthate storage to successfully send up a bloom stalk.
If local conditions have not been favorable for forming sufficient below ground reserves, the
plant may not bloom (Wilson 1993).
Navasota ladies'-tresses apparently does not transplant well. In a mining project in Grimes
county by Texas Municipal Power Association (TMPA), plants in the impact area were removed
and transplanted into an adjacent habitat area. Plant survival has been low in most sites (TMPA
1996). Similarly, in an experiment in Lick Creek Park near College Station, Dr. Hugh Wilson
planted some seedlings which survived into their second season, but died prior to the third
growing season (Wilson 1993).
Because of the low numbers of individuals reported from populations, the slow growing nature
of the plants, its unusual habitat requirements of openings in mature vegetation, and its
sensitivity to disturbance and transplanting attempts, the species is not regarded as being very
resilient, and recovery following any damage to a population is expected to be slow.
The primary threat to Navasota ladies'-tresses is destruction or modification of habitat due to
urbanization, clearing for agricultural production, or mining (47 FR 19539, USFWS 1995,
1984b). Destruction of understory by feral pigs is also a problem in some areas. More than 40
known sites have been lost in the last ten years to mining or urbanization. Post oak savannah in
many of these counties continues to be converted to bermuda grass pasture. Subsequently,
habitat loss continues, particularly in the areas of Brazos and Grimes counties where most sites
are located. The City of College Station in Brazos County is growing rapidly, particularly in the
southern and southeastern fringes where most known populations are located. Mining in Grimes
County disturbs more than 7,000 acres every 5 years (Wilson 1993).
In Fayette County, the species is known from one small population approximately 6 miles south
of the pipeline and 2 miles north of the town of Fayette. Based on analysis of soil distribution,
vegetative cover, physiographic setting, and field assessment by Horizon in November of 1999,
two small areas of potential habitat for Navasota ladies'-tresses are present along the pipeline
corridor. No surveys for the species have been conducted along the pipeline.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii) - Tobusch fishhook cactus is a rounded,
biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5 inches in diameter. There are 3 to 5
central spines with the upper 2 to 3 erect and straight and the lower central spines hooked at the
tip and spreading. The plants are very inconspicuous, and produce cream to yellow flowers from
February through early April. These cacti have been demonstrated to be obligate outcrossers
24

<<<PAGE 309>>>

pollinated by native bees with a foraging distance of about 1/4 mile, and seeds are dispersed by
native ants.
The species occurs on limestone gravels of stream terraces, limestone ledges, ridges, and
openings on the rocky hills of live oak - juniper woodlands in Bandera, Edwards, Kerr, Kimble,
Kinney, Real, Uvalde, and Val Verde counties. A significant number of populations have been
documented in Kimble County.
Currently about 50 sites are recorded for the species, following a recent range - wide
representative survey. Most of the populations are extremely small (5-20 plants), with
individuals widely scattered. Known sites are separated by large distances. Most existing
populations are on private land, and there are very few protected sites. Demographic data
collected in monitoring studies over the last five years or so show that only one of the known
populations is even marginally viable. The species is extremely slow growing and does not
appear to reproduce until 10-17 years of age. It takes four successful flowers/fruits to produce
one seedling (Jackie Poole, Texas Parks and Wildlife, pers. comm.). It is estimated that very few
viable populations (10-15) remain over the 8 county range of the species. The survival and
recovery of the species will require restoration and careful management, to provide sufficient
numbers of populations and individuals in effective proximity to each other for successful
pollination (and gene flow) to ensure the continuity of the species.
Studies examining the probable reasons for population declines are underway. Threats to the
species are believed to include inappropriate timing of range management practices (such as fire
and clearing practices that disturb the soil), extensive predation by beetle grubs, loss of habitat to
real estate development, and some collection by cactus enthusiasts.
An assessment of potentially suitable habitat and pedestrian survey for the cacti was conducted
by Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble County, and
no specimens were observed within the ROW. However, one Tobusch fishhook cactus was
observed about 50 feet north of the cleared ROW. All of the ROW within Kimble County has
been identified as potentially suitable habitat.
Golden-cheeked Warbler (Dendroica chrysoparia) - The golden-cheeked warbler is a small,
migratory songbird, 4.5 to 5 inches long, with a wingspan of about 8 inches. The male has a
black back, throat, and cap, and yellow cheeks with a black stripe through the eye. Females are
similar, but less colorful. The lower breast and belly of both sexes are white with black streaks
on the flanks. Typical nesting habitat is found in tall, dense, mature stands of Ashe juniper
(cedar) mixed with trees such as Texas (Spanish) oak, Lacey oak, shin (scalybark) oak, live oak,
post oak, Texas ash, cedar elm, hackberry, bigtooth maple, sycamore, Arizona walnut,
escarpment cherry, and pecan. This type of woodland generally grows in relatively moist areas
such as steep-sided canyons and slopes. A mix of juniper and deciduous trees on the slopes,
along drainage bottoms, and in creeks and draws provides ideal vegetation for birds. Warblers
are also occasionally found in drier, upland juniper-oak (i.e., live oak, post oak, blackjack oak)
woodlands over flat topography.
An assessment of potentially suitable habitat and surveys for the golden-cheeked warbler was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from Austin,
Texas, to the Mason/Kimble County line. Although no potentially suitable habitat areas were
25

<<<PAGE 310>>>

observed within the Longhorn ROW, several areas were located adjacent to the previously
cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5 times during
April and May on days with favorable weather conditions for bird activity, per U.S. Fish and
Wildlife Service guidelines (USFWS, 1994a). Surveys were conducted on 8, 9, 12, 27, 28 April,
and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres were spent at each site, based
on habitat size. No golden-cheeked warblers were found to be utilizing any of the potentially
suitable habitat areas on or immediately adjacent to the ROW. However, three years of survey
are necessary to confirm presence/absence under Service guidelines (USFWS 1994a).
Black-capped Vireo (Vireo atricapillus) -The black-capped vireo is a 4.5 inch long, insect-
eating songbird. Mature males are olive green above and white below with faint greenish-yellow
flanks. The crown and upper half of the head is black with a partial white eye-ring. The iris is
brownish-red and the bill black. The plumage of the female is duller than the male. Females
have a dark slate gray head. In Texas, vireo habitat is found on rocky limestone soils of the
Edwards Plateau, Cross Timbers and Prairies, eastern Trans-Pecos, and, to a limited extent, on
igneous soils in the Chisos Mountains. Black-capped vireos require shrub vegetation reaching to
ground level for nesting cover. They typically nest in shrublands.
An assessment of potentially suitable habitat and surveys for the black-capped vireo was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from Austin,
Texas to Crane County. Potentially suitable habitat areas were observed within the Longhorn
ROW as well as several areas located immediately adjacent to the previously cleared permanent
ROW. All areas were surveyed by Horizon a minimum of 5 times during April and May on days
with favorable weather conditions for bird activity, per Service guidelines (USFWS, 1994a).
Surveys were conducted on April 8, 9, 12, 27, 28, and May 3, 11, and 19. An equivalent of 4
person-hours per 100 acres were spent at each site, based on size. No black-capped vireos were
found to be utilizing any of the potentially suitable habitat areas on or immediately adjacent to
the ROW. However, three years of survey are necessary to confirm presence/absence under
Service guidelines (USFWS 1994a).
Bald Eagle (Haliaeetus leucocephalus) - The bald eagle is a migrant and winter resident in
Texas. The bald eagle was recently down-listed from endangered to threatened due to successful
conservation efforts and is now proposed for de-listing. Migrating and wintering bald eagles
typically arrive in Texas in November and depart around February. They are found primarily in
association with reservoirs, rivers or other large bodies of water where they feed on fish, carrion,
and waterfowl. Nesting bald eagles in Texas are found in the eastern portion of the state and
along the coastal plain as far south as Calhoun and Refugio counties. No bald eagle nests have
been identified near the pipeline ROW, however, bald eagles may occur along major waterways
(Brazos and Colorado rivers, or major tributaries with impoundments) downstream of the
pipeline corridor. The Federal Register, (Volume 64 No. 128, Tuesday, July 6, 1999; Page
36454) contains a proposed rule to remove the bald eagle from the List of Threatened and
Endangered Wildlife in the Lower 48 States of the United States.
Interior Least Tern (Sterna antillarum athalassos) - Premier nesting sites for the interior least
tern are salt flats, broad sandbars, and barren shores along wide, shallow rivers. Important
breeding habitat characteristics include: (1) presence of bare or nearly bare ground and alluvial
islands or sandbars for nesting; (2) availability of food (primarily small fish); and (3) favorable
26

<<<PAGE 311>>>

water levels during the nesting season (so nests remain above water). They usually nest on sites
devoid of vegetation, but have been found in areas with an average of 11 to 30% vegetative
cover, composed of grasses, shrubs, and trees and ranging from 1 to 3 feet in height. Vegetation,
if present, is usually located well away from the colony, with the exception of bugseed, eastern
cottonwood, and sandbar willow. As natural nesting sites have become sparse, birds have used
sand and gravel pits, ash disposal areas of power plants, reservoir shorelines, gravel levee roads,
and other manmade sites. The typical nesting period for the least tern in Texas is mid-April to
mid-August.
While the interior least tern has not been documented along the pipeline corridor, potential
habitat for the tern is present downstream of the pipeline along several major waterways
including the Brazos, Colorado, Llano, and James Rivers, and Squaw, Beaver, and Sandy
Creeks. The seasonal occurrence (Spring and Summer) and potential nesting of least terns is
possible in these areas.
Barton Springs Salamander (Eurycea sosorum)- The Barton Spring salamander was listed as
endangered in 1997, without critical habitat. The Barton Springs salamander belongs to a group
of related salamanders that are endemic to the Edwards Plateau region of central Texas. All
members of this group are obligately aquatic because the adults retain the larval, gill-breathing
morphology throughout their lives. The Barton Springs salamander, formally described in 1993,
was first collected from Barton Springs in 1946 and has been found only at the four
hydrologically connected outlets of Barton Springs in Zilker Park within the City of Austin
(Brune, 1981; Chippindale et. al., 1993). This salamander is a small species, adults reaching 2.5
inches (about 68 mm) in total length with reduced eyes and elongate, spindly limbs indicative of
a semi-subterranean lifestyle. Barton Springs salamanders are found in the flowing, thermally
constant water issuing from the spring outlets in association with aquatic macrophytes, leaves
and organic debris, and gravel and rock substrates having little silt and sediment deposition.
Water from the contributing and recharge zones of the Barton Springs segment of the Edwards
Aquifer influences the conditions at Barton Springs. The main threat to the species has been
identified as degradation of water quality from future growth and development on the Barton
Springs segment of the Edwards Aquifer (Federal Register 62:23385).
Houston Toad (Bufo houstonensis) - The Houston toad was listed as endangered in 1970
(Federal Register, October 13, 1970) and Critical Habitat was designated in Bastrop and
Burleson counties in 1978 (Federal Register, January 31, 1978). Houston toads are generally
brown and speckled, although individual toad coloration can vary considerably. Some may
appear light brown, others almost black and they may also have a slightly reddish, yellowish, or
greyish hue. Two dark bands extend down from each eye to the mouth. Their legs are also
banded with darker pigment. A variable white stripe streaks along the sides of the toad's body.
Their undersides are usually pale with small, dark spots. Males have a dark throat which appears
bluish when distended. Adult Houston toads are 2 to 3.5 inches long and like all toads, are
covered with raised skin patches that contain chemicals that make the toad distasteful and
sometimes poisonous to predators.
The toad was eliminated from three counties (Harris, Fort Bend, Liberty) prior to the 1970s due
to habitat loss resulting from urban expansion. Although Houston toad populations have been
found in nine other counties (Austin, Bastrop, Burleson, Colorado, Lavaca, Lee, Leon, Milam,
27

<<<PAGE 312>>>

Robertson), the Service is concerned about the long-term viability of these populations. The
small population in Lavaca County has not been seen since its discovery in 199l; the population
at the critical habitat site (Woodrow Lake) in Burleson County has not been seen since 1983; and
the population in Leon County lies within an expanding residential area. The largest known
population of Houston toads occurs within the pine/oak woodland region of Bastrop County.
This area also contains federally designated critical habitat.
All known Houston toad populations occur along bands of geologic formations that support deep
sands. Six populations occur on a band running through Bastrop County northeast to Freestone
County. Three other populations occur on another band through Lavaca, Austin, and Colorado
counties (USFWS, 1994b). Houston toad habitat consists of rolling uplands characterized by
pine and/or oak woodlands (loblolly pine, post oak, blackjack or sandjack oak) underlain by
pockets of deep, sandy soils. Because their skin is semi-permeable to water, Houston toads
become dormant to escape harsh weather conditions, such as winter cold (hibernation) and
drought (estivation). They seek protection during this time by burrowing into sand or hiding
under rocks, leaf litter, logs or in abandoned animal burrows (TPWD, 1993). Although Houston
toads are typically associated with woodland habitat, they also breed in and migrate across
sparsely wooded and cleared areas near woodlands. They may also breed in and traverse areas
that do not support deep sandy soils, including clay and gravel substrates, provided these areas
are near woodlands underlain by pockets of deep sandy soils.
Houston toads breed from January to June, with a peak in February and March. During the
breeding season, toads appear to move randomly from one breeding site to another, achieving
genetic transfer between populations that may appear isolated, thus creating a metapopulation, an
aggregation of smaller populations linked genetically and demographically and functioning
almost as a single population. Presently, the most reliable breeding sites are stock ponds and
similar impoundments, though in wet years breeding may occur wherever sufficient standing
water is present. For successful breeding, water must persist for at least 30-60 days to allow egg
hatching, tadpole maturation, and emergence of toadlets. Mortality in young is high, due to
predation and drying of breeding sites, with significantly less than one percent of eggs laid
believed to survive to adulthood (USFWS, 1984a, 1994b, 1995).
The Houston toad is vulnerable to extinction primarily due to habitat loss, degradation, and
fragmentation. Over the last 50 years, the historic range of Houston toads has contracted and
several populations have been lost. Threats include expanding urbanization and conversion of
woodlands to agricultural production areas, such as coastal bermuda pastures, use of fertilizers
and pesticides that impact the toad directly or its food supply, and loss of suitable breeding
habitat because of alterations in watershed drainages and wetland alterations or destruction (such
as degraded water quality, draining/filling of wetlands, stocking with predatory fish, etc.).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Houston toad, the Service
believes this phase of the project will provide a net conservation benefit for this species.
According to the Houston Toad Recovery Plan (USFWS 1984a), Houston toad breeding sights
have been recorded in Buescher State Park south of Longhorn Pipeline. Houston toads have also
been heard chorusing on the adjacent property owned by the University of Texas to the north of
Buescher State Park and Longhorn Pipeline (USFWS, unpublished data). Dr. James R. Dixon of
28

<<<PAGE 313>>>

Texas A&M University conducted a survey along the Longhorn Pipeline ROW and adjacent
Phillips EZ Pipeline ROW in 1991 with negative results, although areas of potential habitat were
noted (Horizon 1991).
Horizon Environmental Services, Inc. conducted a reevaluation of suitable habitat along the
Longhorn Pipeline ROW within Bastrop County. The field reconnaissance was conducted on 2
June 1999 from the Colorado River, southeast of Bastrop, to FM 2104. Portions of the area
along the pipeline had recently been cleared and planted in improved grasses. Based on field
observations and discussions with the Service, two areas of suitable habitat were identified along
and adjacent to the pipeline ROW. One area includes Buescher State Park from approximately
0.5 mile east of the eastern boundary of the park westward to near Highway 71. The second area
begins about 500 feet to the west of FM 2104 and extends westward approximately 0.75 mile.
The drainages in both of these areas flow south toward the Colorado River.
EFFECTS OF THE ACTIONS
Direct and Indirect Effects
Texas Prairie Dawn - Potential impacts to the Texas prairie dawn may result from a number of
activities. ROW maintenance will occur with the periodic (typically twice per year) use of
tractor drawn mowers. Tractors will be rubber-tired, and crushing of plants could occur from
time to time, particularly during blooming periods. Mowing height will typically be 3 to 4
inches. Since only the blooming shoot is usually that high, impacts from mowing are deemed to
be minimal, except during blooming. Longhorn has chosen to quantify impacts as the total
ROW (50 feet) through the entire area of identified potential habitat. This area constitutes
approximately 61.3 acres. As an avoidance and minimization measure, mowing will be
scheduled to avoid the February through April blooming season.
Three construction sites have been identified for completion in the near-term, two pipeline dent
investigations, and one anomaly investigation (Appendix Two). Impact for these three
construction areas will be contained within the existing 50 foot ROW for relatively short
distances along the pipeline. Within these areas, excavation, temporary spoil storage, equipment
movement, and grading will likely result in elimination of any prairie dawn plants that may
occur within the ROW in the construction areas. The area of these impacts is already included in
the total ROW impact mentioned above (61.3 acres).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Texas prairie dawn, the
Service believes this phase of the project will provide a net conservation benefit for this species.
Navasota Ladies'-tresses - As in the case of the prairie dawn, periodic (twice per year) mowing
with rubber-tired tractor mowers may result in sporadic crushing of plants under tractor tires or
mower wheels, or cutting of bloom stalks. Impacts from periodic mowing, in the absence of
detailed plant inventory information for the ROW, are quantified as of total impact for the ROW
through the identified potential habitat areas constitutes 5.2 acres. As an avoidance and
minimization measure, mowing will be scheduled to avoid the October and November blooming
29

<<<PAGE 314>>>

season. A blooming season survey of the ROW and adjacent areas will be conducted to identify
any plant locations for specific avoidance, if present.
No areas of construction are identified in the two potential habitat areas. However, construction
will occur just east of the most westerly potential habitat area. The ROW is to be used for access
to the construction zone. It is presumed that heavy equipment movement along this portion of
the ROW will result in destruction of any plants growing at that locality. Access will be kept
within the existing 50 foot ROW; therefore, potential impacts have already been calculated in the
ROW maintenance value above (5.2 acres).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Navasota Ladies-tresses,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Tobusch Fishhook Cactus - Potential habitat for the fishhook cactus is very generally estimated
from general soils and plant distribution information to include the entire reach of the pipeline's
traverse of Kimble County. Without specific survey information for the cactus, it is assumed
that the entire ROW across Kimble County is potential cactus habitat. As with the Texas prairie
dawn and Navasota ladies'-tresses, the Tobusch fishhook cactus is low growing and not likely to
be directly affected by mowing, except for possible crushing by tractor tires. However, due to
the significant extent of large rocks within the ROW, mowing is not always feasible in this
region. A preferred method in rocky terrain is to back drag a bulldozer blade across the ground
which knocks down undesirable woody vegetation. This activity can disrupt the ground surface
and possibly injure or destroy cactus plants. Therefore, direct impacts to fishhook cactus habitat
may occur. The total area occupied by the ROW across Kimble County is 212.7 acres.
Four test header installation locations are planned within the potential fishhook cactus habitat.
Each site will disturb an additional 50-foot width beyond the ROW for the construction of the
headers. The additional space is required to facilitate temporary spoils storage, equipment
access, pipe construction, and testing equipment. The additional area of impact per site is
between 0.1 and 0.2 acre. The total additional impact to cactus habitat is 0.5 acre. The total
impact acreage for Tobusch fishhook cactus is 213.2 acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Tobusch fishhook cactus,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Golden-cheeked Warbler - Golden-cheeked warbler habitat does not exist in the established
ROW, but is presently adjacent to the ROW in a number of locations from Hays County
westward to Mason County. ROW maintenance will not directly affect warbler habitat, except
for hand pruning of canopies which overhang the ROW. Indirect effects may result from
mowing noise or activity if birds are present in the vicinity during maintenance activities. As a
minimization procedure, Longhorn will schedule maintenance activities to occur during the non-
30

<<<PAGE 315>>>

nesting season (September 1 to March 1) within or near warbler habitat areas to avoid indirect
impacts. The area of potential effect is determined to be 103.4 acres.
Six areas of pipeline maintenance, construction, or investigation are anticipated to occur along
the pipeline within potential warbler habitat (Appendix Two). Each of those areas are estimated
to require additional construction space in excess of the existing ROW by variable widths. The
total additional impact to warbler habitat resulting from construction clearing is 13.4 acres. The
additional areas of temporary work space are needed in these areas to facilitate temporary spoil
storage, machinery access, pipe stacking, and miscellaneous construction related activities. As
avoidance and minimization of project impacts, Longhorn will schedule clearing, to occur during
the non-nesting period (September 1 to March 1). As with the immediately impending
construction schedule, clearing will commence prior to March 1 and construction activities will
be continuous until completion. Total estimated impacts to potential warbler habitat are 116.8
acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the golden-cheeked warbler,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Black-capped Vireo - Seven areas of potential black-capped vireo habitat exist along the ROW
between Blanco and Kimble counties. Black-capped vireo habitat, being an early successional
stage of brushy regrowth, does exist within the existing ROW in places where previous
maintenance activities have not occurred in several years. In this case, ROW maintenance will
directly impact potential habitat within the existing ROW. The area of direct impact for the full
50 foot width of the ROW through the various habitat areas constitutes approximately 41.6 acres.
Indirect impacts from ROW maintenance are not likely since maintenance activities will be
conducted during the non-nesting season (September 1 to March 15) for vireos.
Four maintenance construction locations have been proposed within the areas identified as
potential vireo habitat (Table 2). Only one of those construction sites will require clearing
beyond the 50 foot ROW width. An additional 50 feet of temporary work space will be needed
to facilitate temporary spoils storage, equipment access, pipe layout and construction room. The
additional acreage of disturbance for this construction site is 0.1 acre. The total area of impact to
potential black-capped vireo habitat is 41.7 acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the black-capped vireo, the
Service believes this phase of the project will provide a net conservation benefit for this species.
Houston Toad - ROW maintenance will include periodic mowing with rubber-tired tractors. To
avoid mortality of toads that may occur within the ROW during mowing, maintenance activities
will be timed to occur in the late summer through fall (July through December) when the toads
tend to be less active and are not breeding. In addition to these avoidance procedures and the
low likelihood of encounters, Longhorn will assume that all areas of potential habitat traversed
31

<<<PAGE 316>>>

by the pipeline ROW are suitable habitat. This area (ROW width of 50 feet times length) is
about 20.6 acres. To minimize edge effects, the ROW will be maintained in native bunchgrasses
to facilitate dispersal and provide cover from predators. No construction impacts to Houston
toads are contemplated in this consultation. Pipe replacements within the toad habitat area will
be addressed in the second phase of consultation.
32

<<<PAGE 317>>>

Because of the toad's vulnerability to development activities, the Service believes that the
combined impact of the existing and anticipated habitat fragmentation and destruction in Bastrop
County could jeopardize its continued existence and adversely modify its critical habitat at some
point in the future, unless immediate efforts are implemented to protect enough remaining
habitat to support viable, self-sustaining populations. Several large, high quality, interconnected
habitat blocks are needed to promote population viability (USFWS 1994b, Houston Toad
Recovery Team 1999). The Houston Toad Recovery Team believes that 20,000-30,000 acres of
suitable (undeveloped) habitat in blocks of 5,000 acres or greater are needed to support a viable,
self-sustaining population of toads with low risk of extinction, with an absolute minimum of
15,000 acres provided this 15,000 acres is in large, interconnected blocks of the best habitat
remaining.
The Service intends to ensure the toad's long-term survival and recovery by ensuring that any
activities authorized under the Endangered Species Act provide long-term protection for the
Houston toad. Thus, any actions authorized by the Service must permit the persistence of at least
20,000-30,000 acres in large, unfragmented habitat blocks in Bastrop County. Toads must be
able to disperse between the habitat blocks through direct connections and/or through migration
corridors that allow dispersal to occur (i.e., multiple smaller upland habitat patches and riparian
corridors).
Currently, the habitat blocks north of Highway 21 and in and around Bastrop State Park are most
likely to continue to support toad populations, provided no additional habitat destruction occurs
that significantly disrupts normal feeding, breeding, and sheltering behavior. Since much of the
area south of Highway 71 has already been extensively fragmented by development, the Service
believes that this area is less likely to continue to support toads over the long-term. The area in
and around the University of Texas Science Park and Buescher State Park has potential to
support a population, provided enough habitat remains contiguous and undisturbed. Until
sufficient high quality habitat has been secured and managed to provide population viability in
perpetuity, the Service believes that any further development that would impact the integrity of
the remaining habitat blocks or their connections would jeopardize the toad and adversely
modify its critical habitat.
Without permanent habitat protection to ensure the persistence of the largest known population
of toads in Bastrop County, the Houston toad faces an imminent risk of extinction. Thus, it is
imperative that the impacts from any activity authorized by the Service provide habitat
protection and maintain migration corridors. By ensuring that all clearing and development
activities implement sufficient measures to minimize impacts, the Service believes many projects
in toad habitat can move forward without reducing the likelihood of survival and recovery of the
species. The Service will continue to assess the impacts of existing and proposed projects and
evaluate whether or not this goal is being achieved.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Houston toad, the Service
believes this phase of the project will provide a net conservation benefit for this species.
33

<<<PAGE 318>>>

Other Species - Listed species that may occur away from or downstream of the pipeline corridor
(bald eagle, interior least tern, Barton Springs salamander) are not likely to be adversely affected
by the proposed maintenance and minor construction activities. Any discharges of hydrotest
waters are not expected to contain levels of hydrocarbons or other toxic materials sufficient to
result in adverse impacts.
Effects of Hydrostatic Testing - Potential Failure of Pipe
Hydrostatic testing of the existing Longhorn Pipeline between Houston and Crane is expected to
result in a number of failures. Some of those failures, and actions taken to locate failure
locations, could have effects upon both species and habitat. However, the calculation of the
effects of such failures is difficult to estimate since the location of any such failure cannot be
predicted and since the volume of test water that may be discharged is difficult to predict.
Calculations by a pipeline integrity consulting firm estimate that approximately 18 to 20 failures
will occur at the high test pressures planned. Since the most likely failure location is at pipeline
flaws, the location of the expected failure cannot be predicted with any accuracy; at most, a
minimal number of recently replaced sections of pipe may be eliminated from consideration.
Therefore, the expected failures will approximate a random distribution over the Houston to
Crane segment. A finite number of failures could be assigned to the habitat areas based upon the
proportional share of pipeline mileage in habitat areas; however, that methodology would
probably result in either overestimation or underestimation of the number of failures in habitat
areas.
In addition, the potential volume of test water discharged in the event of failure is difficult to
estimate. First, if a failure results in rapid depressurization of the test segment, the volume of
test water discharged will be the sum of (a) water expelled as the pipe returns to atmospheric
pressure, which depends upon test pressure and test segment length, and (b) drainage from any
adjacent segments at elevations higher than the failure location. Second, if a failure results in a
slow depressurization of the test segment, it may be readily identifiable and quickly contained.
If a slow leak is difficult to locate, one or more investigative excavations could be required to
either search for the failure or plug a portion of the segment so that lengths of pipe may be
eliminated from the search. Therefore, given that failure location and size cannot be predicted,
potential effects on species and/or habitat cannot be reasonably estimated in advance. Another
factor that makes such estimates difficult is the existence of residual amounts of diesel fuel that
remain in the pipeline from cleaning during 1998. As the hydrostatic testing proceeds from east
to west, the test water may be expected to reflect relatively higher levels of hydrocarbon content.
Those concentrations cannot be predicted but are not expected to contain levels of hydrocarbons
or other toxic materials sufficient to result in adverse impacts. Spill response equipment such as
booms, absorbent pads, and other containment and cleanup equipment will be maintained in the
vicinity of the test sites during the procedure.
In summary, the locations of hydrostatic test failures cannot be predicted, the volume of test
water discharged can not be calculated, and the number of investigative excavations cannot be
predicted. In the event of a pipeline failure in or near habitat for listed species, incidental take
may occur. The level of potential take is impossible to predict. Basically, take from failure of
the pipeline during this testing would require reinitiation of this consultation.
34

<<<PAGE 319>>>

Cumulative Effects
Cumulative effects of future State, local or private actions that are reasonably certain to occur in
the action area are considered in this biological opinion. Future Federal actions that are
unrelated to the proposed action are not considered in this section because they require separate
consultation pursuant to Section 7 of the Act. Because of the linear nature of the pipeline and the
long history of clearing (about 50 years) the Service anticipates no cumulative effects from the
activities proposed. The majority of the counties involved in the project are predominantly rural,
and imminent future actions identified that may affect each of the listed species are either not
considered to be of sufficient magnitude to result in jeopardy to the species or will include
minimization necessary to avoid jeopardy.
Conclusion
The Service in developing its biological opinion has thoroughly reviewed the proposed action
submitted by EPA, OPS, and Longhorn Pipeline Partners. This Biological Opinion is predicated
on the compliance and the full and complete adherence by EPA, OPS and the Longhorn Pipeline
Partners to the Description of the Proposed Action provided earlier in this document. In
consideration of the above and after reviewing the current status of the potentially affected
species, the environmental baseline for the action area, the effects of the proposed action
including direct, and indirect and cumulative effects, it is the Service's biological opinion that
the action as proposed by EPA, OPS, and the Longhorn Pipeline Partners for Longhorn Pipeline
Project Maintenance Activities and Minor Construction from Houston to Crane, Texas, is not
likely to jeopardize the continued existence of any Federally listed species. In addition the
proposed action is not likely to destroy or adversely modify the designated critical habitat of the
Houston toad. In addition, the Service concurs with the not likely to adversely affect
determination, made by EPA and OPS for areas that are not habitat for threatened or endangered
species.
INCIDENTAL TAKE STATEMENT
Section 9 of the ESA and Federal regulations pursuant to section 4(d) of the ESA prohibit the
take of endangered and threatened species, respectively, without special exemption. Take is
defined as to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture or collect, or to attempt
to engage in any such conduct. Harm is further defined by the Service to include significant
habitat modification or degradation that results in death or injury to listed species by
significantly impairing essential behavioral patterns, including breeding, feeding, or sheltering.
Harass is defined by the Service as intentional or negligent actions that create the likelihood of
injury to listed species to such an extent as to significantly disrupt normal behavior patterns
which include, but are not limited to, breeding, feeding or sheltering. Incidental take is defined
as take that is incidental to, and not the purpose of, the carrying out of an otherwise lawful
activity. Under the terms of section 7(b)(4) and section 7(o)(2), taking that is incidental to and
not intended as part of the agency action is not considered to be prohibited taking under the Act
provided that such taking is in compliance with the terms and conditions of this Incidental Take
Statement.
The term take in the Endangered Species Act is not defined for plants and therefore plants are
not included in the incidental take statement of biological opinions. However, Federal agencies
35

<<<PAGE 320>>>

are required under section 7 (a)(1) of the Act to consult with the Service on actions that may
affect listed plants, and to insure that any agency action is not likely to jeopardize the continued
existence of the species or result in the destruction or adverse modification of critical habitat.
Further, section 7(a)(2) of the Act applies equally to plants and animals.
Amount or Extent of Take
The Service anticipates that the level of incidental take from the proposed activities will be low.
The seasonal restrictions placed on these activities, and alternative techniques planned for
sensitive habitat areas (land conservation funding), and other conservation actions planned
should avoid and minimize the potential for incidental take to the maximum extent practicable.
The amount or extent of incidental take resulting from the proposed action on listed species is
difficult to assess since comprehensive survey information is not available for all species that
could be affected. The approach taken for most of the potentially affected species is to assume
that they are present in the identified potential habitat areas and that take will occur. The
proposed action uses the potential habitat to define the possible extent of any take that could
occur. Based on the proposed action, the Service will assume incidental take for the entire width
of the pipeline ROW (and edge effects from the ROW) as it traverses broad areas of potential
habitat for listed species. Take is calculated based on the extent of suitable habitat within the
established ROW (50-foot width x length) and within temporary work spaces that exceed the
ROW (variable by location). The following summarizes by species the amount of potentially
suitable habitat that will be impacted by the proposed action (Table Three).
Table Three. Potential Suitable Habitat
Species
Area Impacted
Texas prairie dawn
61.3 acres
Navasota ladies'- tresses
5.2 acres
Houston toad
20.6 acres
Golden-cheeked warbler
116.8 acres
Black-capped vireo
41.7 acres
Tobusch fishhook cactus
213.2 acres
Effect of Take
In the accompanying biological opinion, the Service determined that the level of anticipated take
identified is not likely to result in jeopardy to the species or destruction or adverse modification
of critical habitat. Implementation of this project should result in net benefit to the species listed
above in Table Two, to the extent that conservation benefits planned exceed expected impacts to
the species.
Reasonable and Prudent Measures
The Service believes the following reasonable and prudent measures are necessary and
appropriate to minimize take associated with the proposed Phase One - Longhorn Pipeline
Project Maintenance Activities and Minor Construction Houston to Crane, Texas.
36

<<<PAGE 321>>>

The measures described below are non-discretionary, and must be undertaken by EPA and/or
OPS so that they become binding conditions on the Longhorn Pipeline Partners, as appropriate,
for the exemption in section 7(o)(2) to apply. EPA and OPS have a continuing duty to regulate
the activities addressed by this incidental take statement. If EPA or OPS, (1) fails to assume and
implement the terms and conditions or (2) fails to require the Longhorn Pipeline Partners to
adhere to the terms and conditions of the incidental take statement through enforceable terms and
conditions, the protective coverage of section 7(0)(2) may lapse.
In order to monitor the impact of incidental take, EPA, OPS, and/or Longhorn Pipeline Partners
must report the progress of the action and its impact on the species to the Service as specified in
the incidental take statement (below) [50 CFR §402.14(I)(3)].
Reasonable and Prudent Measure 1: The proposed actions, as described in the above
"PROJECT DESCRIPTION (Actions addressed under this Biological Opinion)" and the
accompanying Biological Assessment must be followed. In areas where the Biological
Assessment and the Biological Opinion are not in agreement, the Biological Opinion will be
followed. The Service will be available to clarify any questions that may arise during
implementation.
Reasonable and Prudent Measure 2: EPA and/or OPS must ensure that the activities are
carried out by the Longhorn Pipeline Partners as they are proposed. Monitoring of these
activities must be accomplished to ensure compliance. The level of monitoring must include
onsite review of activities with a relatively intense focus on the first year when construction will
occur. EPA and/or OPS must submit a monitoring plan detailing the level of monitoring that
will occur. Service concurrence with the level and type of monitoring proposed is a requirement.
Terms and Conditions
In order to be exempt from the prohibitions of section 9 of the Act, EPA and OPS must comply
with the following terms and conditions, which implement the reasonable and prudent measures
conditions are non-discretionary.
described above and outline required reporting/monitoring requirements. These terms and
Terms and Conditions to Implement Reasonable and Prudent Measure 1
This term and condition is effective immediately.
Terms and Conditions to Implement Reasonable and Prudent Measure 2
This term and condition is effective immediately. Given that the proposed work is scheduled to
begin with the issuance of this opinion, EPA and/or OPS must submit a monitoring plan
detailing the level of monitoring within two weeks of the receipt of the Biological Opinion. On
site review of the projects should begin before March 1, 2000.
Conservation Recommendations
Section 7(a)(1) of the Act directs Federal agencies to utilize their authorities to further the
purposes of the Act by carrying out conservation programs for the benefit of endangered and
threatened species. Conservation recommendations are discretionary agency activities to
37

<<<PAGE 322>>>

minimize or avoid adverse effects of a proposed action on listed species or critical habitat, to
help implement recovery plans, or to develop information.
It is recommended that in areas where surveys are completed ahead of destructive
project actions, any plants in the action area be protected and avoided wherever
possible. Where Tobusch fishook cactus plants are found that cannot be avoided
and will be destroyed by the project activities, the Service recommends these
plants be removed and transferred to the conservation collection of the Desert
Botanical Garden in Phoenix, Arizona, where they can be cultivated for seed
production and cryopreservation for use in future restoration work for the species.
Contact Desert Botanical Garden prior to removals to arrange transfer and obtain
any special instruction. In general, plants should be removed by digging at least a
one foot diameter area around the plant, carefully rinsing to bare root, thoroughly
drying the entire subsoil area and any wounds before transport (by placing on
newspapers in a cool shaded location) and then (when dry) carefully packing in
newspaper in a box, and then packing in a second box surrounded by protective
packing materials before express shipping.
•
It is recommended that maintenance practices be implemented that will help
minimize impacts to the vegetation community, fragmentation of Houston toad
habitat, and edge effects.
To facilitate dispersal for Houston toads that cross the ROW, Longhorn Pipeline
has agreed to maintain the ROW in native bunchgrasses rather than sod-forming
grasses, which inhibit movement. The height of native bunchgrass communities
shall be maintained several inches (i.e., ≥ 4 inches) above ground level to provide
adequate cover for toads.
•
Avoid using herbicides and pesticides in Houston toad areas. If herbicide use
cannot be avoided, direct application techniques shall be used to minimize
amount of application and areas of the habitat impacted. Avoiding the use of
herbicides and pesticides is particularly critical near any wetland areas and during
the breeding season (January through June). Avoiding the use of chemicals in
habitat minimizes the risk of harm through toxic effects to the toads and tadpoles
themselves or their food base.
•
To protect the Houston toad from predation by red imported fire ants (Solenopsis
invicta), periodically inspect the ROW for fire ant activity. Inspections should
occur when fire ants are most active. If fire ants are found, individually treat fire
ant mounds using commercial fire ant bait in accordance with label instructions.
Bait should be placed only near fire ant mounds and not near the mounds of
native ant species. To avoid affects on non-target species, apply bait when ants
are actively foraging and prevent accumulations of excess bait.
Reinitiation Notice
This concludes formal consultation for Phase One - Longhorn Pipeline Project Maintenance
Activities and Minor Construction Houston to Crane, Texas. As provided in 50 CFR $402.16,
38

<<<PAGE 323>>>

reinitiation of formal consultation is required where discretionary Federal agency involvement or
control over the action has been retained (or is authorized by law) and if: (1) the amount or
extent of incidental take is exceeded; (2) new information reveals effects of the agency action
that may affect listed species or critical habitat in a manner or to an extent not considered in this
opinion; (3) the agency action is subsequently modified in a manner that causes an effect to the
listed species or critical habitat not considered in this opinion; or (4) a new species is listed or
critical habitat designated that may be affected by the action. In instances where the amount or
extent of incidental take is exceeded, any operations causing such take must cease pending
reinitiation.
In closing we wish to thank EPA, OPS, and the Longhorn Pipeline Partners for the cooperation
and patience shown during this consultation. Thank you for your interest in protecting our
federal trust resources. If you have any questions, please contact Matthew Lechner (512) 490-
0057, extension 234.
Sincerely,
/s/ William M. Seawell (for)
David C. Frederick
Supervisor
39

<<<PAGE 324>>>

Appendix One
Confidential Settlement Agreement
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF TEXAS
AUSTIN DIVISION
Ethel Spiller, et al., Plaintiffs
versus
Robert M. Walker, et al. Defendants
CIVIL NO. A-98-CA-255-SS
Settlement Stipulation
40

<<<PAGE 325>>>

Appendix Three
Literature Cited
Arft, A. and T. Ranker. 1995. Demography of the rare orchid Spiranthes diluvialis: implications
for conservation. Program and Abstracts, 9*h annual meeting of the Society for Conservation
Biology, June 7-11, Fort Collins, Colorado. Abstract, notes from presentation attended. U.S.
Fish and Wildlife Service, Austin, Texas.
Brune, G. 1981. Springs of Texas: Volume 1. Branch-Smith Inc. Fort Worth, Texas.
Chippindale, P., D. Hillis, and A. Price. 1990. Central Texas Salamander Studies. Section 6
report submitted by Texas Parks and Wildlife Department to U.S. Fish and Wildlife Service.
Federal Aid Project No: E-1-2, Job No. 3.4. Austin, Texas.
Horizon Environmental Services, Inc. 1991. Threatened or Endangered Species Investigations -
EZ Pipeline Project. Horizon Environmental Service, Inc. Austin, Texas.
Poole, J.M,. and D.H. Riskind. 1987. Endangered, Threatened, or Protected Native Plants of
Texas. Austin, Texas: Texas Parks and Wildlife Department, State of Texas.
U.S. Fish and Wildlife Service (USFWS). 1984a. Houston toad recovery plan. U.S. Fish and
Wildlife Service. Albuquerque, New Mexico. 73pp.
U.S. Fish and Wildlife Service (USFWS). 1984b. Navasota ladies'-tresses recovery plan. U.S.
Fish and Wildlife Service. Albuquerque, New Mexico.
U.S. Fish and Wildlife Service (USFWS). 1994a. Minimum Procedures for Determining the
Presence/Absence of Golden-Checked Warblers and Black-Capped Vireos. March 7, 1994
Memorandum, Austin Field Office.
U.S. Fish and Wildlife Service (USFWS). 1994b. Population and habitat viability assessment:
Houston toad (Bufo houstonensis). Workshop conducted by IUCN/SSC Conservation Breeding
Specialist Group in partial fulfillment of USFWS contract #94-172. Apple Valley, Minnesota.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and endangered species of Texas
(revised). U.S. Fish and Wildlife Service. Austin, Texas.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and Endangered Species of Texas.
Austin, Texas: US Fish and Wildlife Service, Revised June, 1995.
U.S. Fish and Wildlife Service (USFWS). Houston Toad Recovery Team. 1999. March 31-April
1, 1999 Meeting Minutes. U.S. Fish and Wildlife Service, Austin, Texas.
Texas Parks and Wildlife. 1993. Endangered species information for Hilltop Lakes. Texas Parks
and Wildlife Resource Protection Division, Austin, Texas.
Wilson, H. 1993. Contractors partial draft of recovery plan revision for Navasota ladies'-tresses
(unfinished contract). U.S. Fish and Wildlife Service, Austin, Texas.
41

<<<PAGE 326>>>

Phase Il Biological Assessment
April 10, 2000
Addendum September 14, 2000
42

<<<PAGE 327>>>

Horizon Job No. 990144
PHASE TWO
BIOLOGICAL ASSESSMENT
OPERATION, LONG-TERM MAINTENANCE,
AND EMERGENCY RESPONSE,
LONGHORN PIPELINE PROJECT
HOUSTON TO EL PASO, TEXAS
PREPARED FOR:
LONGHORN PARTNERS PIPELINE
U.S. DEPARTMENT OF TRANSPORTATION
AND
U.S. ENVIRONMENTAL PROTECTION AGENCY
REGION 6
PREPARED BY:
HORIZON ENVIRONMENTAL SERVICES, INC.
AUSTIN - BEAUMONT - HOUSTON - SHREVEPORT
APRIL 10, 2000
Addendum September 14, 2000
99144ba2.v8

<<<PAGE 328>>>

TABLE OF CONTENTS
Section
Page
1.0
INTRODUCTION
1
2.0
CONSULTATION HISTORY
.4
3.0
DESCRIPTION OF THE PROPOSED ACTIONS.
7
3.1
Project Overview....
.7
3.2
Pipeline Operation
22
3.3
Long-Term Maintenance..
.22
3.4
Emergency Response.....
29
3.5
Edwards Aquifer Protections..
43
3.6
Pipeline Maintenance Construction.
46
3.6.1 Buescher State Park
46
3.6.2 Edwards Aquifer Protections.
47
3.7
Hydrostatic Pressure Testing And Proof Testing
51
3.8
Right-of-Way Maintenance
52
3.9
Corrosion Inhibitor ..
52
4.0
AVOIDANCE AND CONSERVATION MEASURES
55
Avoidance
55
4.2
Status of the Species/Environmental Baseline
57
4.3
Effects of the Actions....
68
4.4
Planned, But Unscheduled Construction ..
75
4.5
Future Additional, But Currently Unforseen Construction
76
4.6
Bays and Estuaries Issues.
76
4.7
Summary of Conservation Measures
77
5.0
REFERENCES
...81
99144ba2.v8

<<<PAGE 329>>>

LIST OF TABLES
Table
Page
1
Consultation History - Phases One And Two.
..4
2
Chronology of Longhorn Pipeline Actions..
10
3
List of Endangered Species Habitat Areas along the Longhorn Pipeline...
..12
4
Federally Listed Threatened or Endangered Species Which Occur
In Counties Traversed By The Longhorn Pipeline
Houston to El Paso........
.. 58 - 59
LIST OF FIGURES
Figure
Page
1
Location Map................
...8
2 - 10
Areas of Potential Threatened or Endangered Species Habitat Along
the Longhorn Pipeline - Houston to El Paso.
.. 13 - 21
APPENDIX
Phase Two Project Documentation Appendix
Accompanying Document
Longhorn Facility Response Plan
Accompanying Document
99144ba2.v8

<<<PAGE 330>>>

1.0 INTRODUCTION
This document is the Biological Assessment (BA) of the potential for effects, arising out of
the activities proposed by Longhorn Partners Pipeline, L.P. (Longhorn), on federally-listed
species in Texas. This BA presents data and information describing the proposed plans for
the second phase of consultation for the Longhorn Pipeline Project -- Operation,
Maintenance, and Response Activities, Houston to El Paso, Texas. The first phase of the
consultation (Phase One), which has already been completed, related to pipeline right-of-
way maintenance, clearing and marking, selected pipeline maintenance construction
activities (pipe replacements and lowering), and pipeline testing (investigation of possible
flaws and hydrostatic pressure testing). The Service found that Longhorn's Phase One
activities were not likely to jeopardize the continued existence of any federally listed
species, nor was it likely to destroy or adversely modify the designated critical habitat of the
Houston toad. The Phase One BA, dated February 14, 2000, and the Phase One Biological
Opinion (BO), dated February 17, 2000, are hereby incorporated into this Phase Two BA by
reference (see Phase Two Project Documentation Appendix at Tabs 1 and 2).
The draft Environmental Assessment (EA) of the proposed Longhorn Pipeline System and
these BAs are the product of a settlement reached in the matter of Spiller et al. v. Walker et
al. pending in the United States District Court in Austin, Texas (See Phase Two Project
Documentation Appendix at Tab 3; the Settlement Stipulation). As part of the Court
approved settlement, two agencies involved in the original litigation were required to
conduct an EA including, specifically, consideration of species listed under the Endangered
Species Act (ESA). The Court ordered the U.S. Environmental Protection Agency (EPA)
and the U.S. Department of Transportation (DOT), to be responsible for the EA. EPA and
the DOT Office of Pipeline Safety (OPS) act as Lead Agencies in the EA process. Radian
International LLC (Radian) is a contract preparer of the EA and works at the direction of the
Lead Agencies.
The Court order provides that issuance of any finding of no significant impact (FONSI) with
regard to the
proposed Longhorn Pipeline project "shall be conditioned upon
implementation" of measures to protect public safety and the environment (Settlement
Stipulation at 6). The order also prohibits OPS from authorizing Longhorn to commence
operations until Longhorn has implemented those mitigation measures upon which any
FONSI is conditioned (Settlement Stipulation at 7). The order contemplates that Longhorn
will apply for such ESA permits as may be required in connection with the implementation
of any mitigation measures upon which a FONSI may be conditioned. (Settlement
Stipulation at 7). The results of this consultation by the Lead Agencies with the Service are
expected to be incorporated in the Record of Decision issued by the Lead Agencies. The
terms and conditions, mitigatory measures and protections incorporated herein for the
benefit of species are expected to be adopted and incorporated by Longhorn in its
enforceable mitigation commitments or in its operating and maintenance manuals subject
to inspection by, and enforceable by, OPS pursuant to the Pipeline Safety Act (49 U.S.C.
60101 et seq.).
Although the Service and the Lead Agencies are in consultation with respect to the entire
proposed Longhorn pipeline project, this consultation is being approached in two distinct,
yet related phases.
Service regulations allow for a staged consultation (50 CFR
402.14(k)) where the Service reviews a project and provides biological opinions on each
99144ba2.v8
1

<<<PAGE 331>>>

incremental step, provided that no irreversible or irretrievable commitments of resources
are made.
This second phase of the consultation will be directly related to the actual operation of the
pipeline, specifically the operation and maintenance of the pipeline system and the potential
effects of a pipeline release and related emergency response. Like Phase One, Phase
Two activities also include implementation of some mitigation measures, specifically the
replacement of pipe in Buescher State Park (see Longhorn Mitigation Commitment 34
(LMC 34) of the Longhorn Mitigation Plan (LMP) dated September 1, 2000; see Phase Two
Project Documentation Appendix at Tab 4) and the replacement of some 19 miles of pipe
over the Edwards Aquifer recharge and contributing zones with thick-walled pipe. On its
own initiative, Longhorn will lower two other sections of pipe in Buescher Park where the
pipe crosses streams. Phase Two also includes (a) hydrostatic pressure testing of pipeline
segments not tested pursuant to Phase One, specifically, Houston toad habitat areas and
areas of potential effect to the Barton Springs Salamander, (b) treatment of the pipeline
internally with corrosion inhibitor, and (c) right-of-way clearing in areas of potential effect to
the Barton Springs Salamander.
Since none of the Phase Two work will be undertaken by Longhorn until this consultation is
complete, neither the federal agencies nor Longhorn will engage in any irreversible or
irretrievable commitment of resources during the course of the consultation.
The two phases have been logically separated. Phase One of the Service's review focused
on those actions that were designed to make the pipeline safer. That review did not pre-
judge whether or not the pipeline would be used. This second phase of the consultation
will focus on whether and how the pipeline will be used. New construction of pipe between
Crane and El Paso was reviewed by the Service in 1997 and resulted in a not likely to
adversely affect determination (See Tab 5 of the Phase Two Project Documentation
Appendix).
The Service can logically conclude that operation and maintenance of the Longhorn
Pipeline will not jeopardize the continued existence of any federally listed species, and that
it is not likely to destroy or adversely modify the designated critical habitat of the Houston
toad. This project, as designed, is not likely to adversely affect threatened or endangered
species or habitat.
There is little risk from operation of the pipeline. The risks that do exist
arise in the unlikely event of an accidental release of product from the pipeline.
response to this risk, and pursuant to the Settlement Stipulation, Longhorn will implement
numerous mitigation measures designed to avoid a release entirely or reduce the
magnitude and the impact of a release. Longhorn developed these mitigation measures in
response to risks identified by the Lead Agencies. Mitigation measures such as pipe
replacement and pipe lowering, in-line inspections, daily surveillance patrols over the
Edwards Aquifer recharge zone, enhanced damage prevention and public education
programs, and hydrostatic pressure testing greatly minimize the risk of an accidental
release from the pipeline in the first place. These efforts minimize the risk a release will
occur. In addition, Longhorn will install an enhanced leak detection system which will allow
pipeline operators to rapidly detect even a very small release over the Edwards Aquifer
recharge zone and portions of the contributing zone and respond quickly, thereby limiting
the amount of product released into the environment. Longhorn will also fund a refugium for
the Barton Springs Salamander.
99144ba2.v8
2

<<<PAGE 332>>>

Taken together, the Service can conclude that these measures are sufficient to ensure
operation of the pipeline will neither jeopardize the continued existence of any federally
listed species, nor adversely affect their habitat, and is not likely to adversely affect
threatened or endangered species or habitat along the pipeline route.
This BA is based upon: (1) the information that Longhorn (as designated non-federal
representative), provided as
part of the informal consultation including the Draft
Environmental Assessment and the Phase One BA), (2) information in the Service's office
(including information provided by the public and the plaintiffs in the lawsuit relating to the
Longhorn Pipeline), (3) field investigations, and (4) other sources of information.
99144ba2.v8
3

<<<PAGE 333>>>

2.0
CONSULTATION HISTORY
Informal and formal consultation between the Service, Longhorn, EPA, and OPS has been
Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
10 February, 1999
Meeting Between Service and Longhorn Representatives
25 February, 1999
Meeting Between Service and Longhorn Representatives
9 March, 1999
Meeting of Service and Radian (consultants writing EA for EPA and OPS)
22 March, 1999
Meeting Between Service and Longhorn Representatives
30 April, 1999
Meeting Between Service and Longhorn Representatives
11 May, 1999
Meeting Between Service and Longhorn Representatives
12 May, 1999
Meeting with the Plaintiffs to discuss the Settlement Agreement
1 June, 1999
Meeting with Barton Springs/Edwards Aquifer Conservation District
8 June, 1999
Meeting Between Service and Longhorn Representatives
11 June, 1999
Multi-Agency Field Tour of Longhorn Pipeline in and near Austin, Texas
29 June, 1999
Meeting Between Service and Longhorn Representatives
30 June, 1999
Telephone Conference Between Service and Department of Justice
19 July, 1999
Meeting Between Service and Longhorn Representatives
27 August, 1999
Meeting Between Service and Longhorn Representatives
10 September, 1999
Meeting Between Service and EPA
Meeting Between Service and Longhorn Representatives
13 September, 1999
Meeting Between Service, Austin and Regional Director
27 September, 1999
Meeting between Service Austin Office and Washington Office
Original Draft Biological Assessment Submitted to Service
30 September, 1999
Meeting Between Service and Longhorn Representatives
99144ba2.v8
4

<<<PAGE 334>>>

Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
4 November, 1999
Meeting Between Service and Longhorn Representatives
9 November, 1999
Meeting Between Service and Longhorn Representatives
16 November, 1999
EPA and OPS Longhorn Public Meeting, Austin
22 November, 1999
Meeting Between Service and Longhorn Representatives
7 December, 1999
Meeting Between Service and Longhorn Representatives
8 December, 1999
Meeting Between Service and EPA
15 December, 1999
Meeting Between Service and Longhorn Representatives
Service Issues Comments on Original Draft Biological Assessment
Service Issues Response to EPA Regarding EPA's initial Request for
Concurrence on a "Not Likely to Adversely Affect" Determination.
17 December, 1999
Meeting Between Service and Longhorn Representatives
6 January, 2000
Longhorn Requests Concurrence from Service for "Not Likely to Adversely Affect"
Meeting Between Service and Longhorn Representatives
for Maintenance and Construction Activities in Non-habitat Areas for Listed
Species.
10 January, 2000
EPA and OPS Longhorn Public Meeting, Austin
11 January, 2000
Meeting Between Service, EPA and OPS
17 January, 2000
Meeting Between Service and Longhorn Representatives
18 January, 2000
Meeting Between Service and Longhorn Representative
28 January, 2000
Initial Draft First Phase Biological Assessment received for review
7 February, 2000
Meeting Between Service and Longhorn Representatives
1 February, 2000
Telephone Conference Between Service and Congressman Doggett's Staff
3 February, 2000
of consultation
EPA and OPS designate Longhorn the "non-federal representative" for purposes
10 February, 2000
Received EPA Request for Formal Consultation
14 February, 2000
Received Second Draft of Phase One Biological Assessment For Review
17 February, 2000
Received Revised Final Phase One Biological Assessment
17 February, 2000
Received OPS Request for Formal Consultation
17 February, 2000
Service issued Phase One Biological Opinion
9 March, 2000
Il consultation with submission of initial draft of Phase Two Biological Assessment
Meeting between Service and Longhorn Representatives to initiate informal Phase
12 April 2000
Received Revised Draft Phase I! Biological Assessment
26 April 2000
Meeting Between Service and Longhorn Representatives
99144ba2.v8
5

<<<PAGE 335>>>

Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
6 June 2000
Meeting Between Service and Longhorn Representatives
23 June 2000
Meeting Between Service and Longhorn Representatives
30 June 2000
Meeting Between Service and Longhorn Representatives
21to 31 July 2000
Received supplemental information for the Phase II Biological Assessment
3 August 2000
Meeting Between Service and Longhorn Representatives
5 August 2000
Meeting Between Service and Longhorn Representatives
9 August 2000
Meeting Between Service and Longhorn Representatives
23 August 2000
Meeting Between Service and Longhorn Representatives
6 September 2000
Meeting Between Service, Lead Agency, and Longhorn Representatives
11 to 13 Sept. 2000
Received supplemental information for the Phase II Biological Assessment
99144ba2.v8

<<<PAGE 336>>>

3.0 DESCRIPTION OF THE PROPOSED ACTIONS
The following is an overview of the project as proposed by Longhorn and is provided to give
an overall context of the proposed project. The specific activities proposed for this Phase
Two BA are detailed in the following sections. This project overview differs slightly from the
project overview contained within the Phase One BA; specifically, this project overview
describes four connecting pipelines as opposed to the three previously described.
However, the differences implicate no change to the potential effects of the overall project
upon species, given that no potential habitat areas have been identified along the planned
route of the connecting pipelines.
3.1
Project Overview
Due to the expanding demand for refined products in El Paso and other markets in the
southwestern United States, the proposed Longhorn Pipeline will transport up to 225,000
barrels per day (bpd) of refined products to the El Paso Terminal and to the Equilon
Terminal in Odessa. From these terminals, products will be distributed by truck transport in
the El Paso and Odessa markets. Tanker trucks could transport refined products to Juarez
in Mexico. The Longhorn Pipeline will connect to the Kinder Morgan and Chevron pipelines
at El Paso, enabling shippers to transport products to Phoenix, Tucson, Albuquerque, and
other southwestern markets. Market conditions and shipper requirements will determine the
actual pattern of distribution of products to El Paso and to the Phoenix, Tucson,
Albuquerque, and other southwestern markets.
The Longhorn Pipeline System is designed for service in excess of fifty years from startup
and is made up of four main pipeline segments, several stations, and one terminal, as listed
below:
1.
New and refurbished 20-inch diameter pipeline from Galena Park Station to
Satsuma Station
2.
Refurbished 18-inch diameter pipeline from Satsuma Station to Crane Station
3
New 18-inch diameter pipeline from Crane Station to El Paso Terminal
4.
New lateral pipeline connections to Odessa and to other pipelines at El Paso
5.
New Pump Stations: GATX, Satsuma, Cedar Valley, Kimble County, Crane, and El
Paso
6.
El Paso Terminal
7.
Odessa Meter Station
Longhorn has constructed and will operate a 723-mile refined petroleum products pipeline
system from the GATX Terminal in Galena Park, Texas, to a refined petroleum products
terminal at El Paso, Texas (Figure 1). The pipeline also has a 28-mile intermediate
connection from a station in Crane County to a planned meter station in Odessa, Texas.
The pipeline consists of a combination of 20-inch and 18-inch diameter pipe from Galena
Park Station to El Paso Terminal and an 8-inch diameter pipeline from a station in Crane
County to a meter station in Odessa, Texas. The pipeline's initial capacity of 72,000 bpd
will be supplied by a new origin pump station at Galena Park and five new booster pump
stations, Satsuma, Cedar Valley, Kimble County, Crane, and El Paso.
99144ba2.v8
7

<<<PAGE 337>>>

98S00 M
rene ta
01
erie
493
0-r
01307o0/g pero bac
ле vol ago покоо.
07501
кото
AMARILLO
eno 2820ag0 nsm
30270
Oklahoma
Mexico es i-lo-ing
New
ron.
Louisiana
COULDNE
T WORTH
DALLA
ODESSA
TO COLOTINE
TACO
Mexico
cApu
KIMBLE COUNTY
ON
SaN/
ANTONIC
REDO
CHRISTI
Mexico
Gulf of
EXPLANATION
LONGHORN REFINED PRODUCTS PIPELINE
LONGHORN PIPELINE PUMP STATION:
RAD 39067
PUMP STATIONS
N
LONGHORN PIPELINE
1.05-
STATE OF TEXAS
NOT. TO SCALE
MAP SQURCES:
(htto:// www.tnns.state.tx.us/dota__oz.ntml), 1998
TEXAS NATURAL RESOURCE INFORMATION SYSTEM
LONGHORN PIPELINE

<<<PAGE 338>>>

An 8-inch diameter, 2,500-toot lateral that originates at the terminus of the existing Odessa
lateral will connect to a terminal facility in Odessa, Texas, owned by Equilon. Three 8.3-mile
lateral pipelines, which originate at the El Paso Terminal, will connect with Kinder Morgan
(formerly the Santa Fe Pacific pipeline) and Chevron pipelines in the El Paso area. The
connection to Kinder Morgan will consist of one 8-inch diameter pipeline and one 12-inch
diameter pipeline. The Chevron connection will consist of an 8-inch diameter pipeline. The
purpose of the lateral pipelines is to connect into Kinder Morgan and Chevron pipelines to
distribute product into the Phoenix, Tucson, and Albuquerque markets. Chevron operates
an 8-inch pipeline that delivers product to the Albuquerque market; Kinder Morgan operates
one 12-inch pipeline and one 8-inch pipeline serving the Tucson market. Other Kinder
Morgan pipelines connect Tucson to the Phoenix market.
One additional eight-inch pipeline, to be installed in the same right-of-way as the El Paso
laterals, will create a return system between the El Paso Terminal and the point of the
lateral pipeline connections to Kinder Morgan and Chevron. The return system will be used
to displace product from within the lateral pipelines back to the El Paso Terminal. The
return system will allow product of one type to be removed from a lateral pipeline, prior to
initiating delivery of a different product into one of the Kinder Morgan or Chevron pipelines,
thus facilitating quality control of products delivered to those pipelines. The return system
will be accomplished by installation of a manifold at the point where the lateral pipelines
connect to the Kinder Morgan and Chevron pipelines.
After startup, Longhorn plans to periodically increase capacity to reach an ultimate capacity
of 225,000 bpd. To reach this capacity, Longhorn will, in the future, build ten new booster
pump stations and will refurbish or reconstruct three existing stations at the following
locations:
Approximate Location
Station
(milepost to milepost)
Buckhorn
MP 67.5 - MP 77.5
Warda
Existing site
Bastrop
Existing site
Orotaga
MP 203.8 - MP 213.8
Eckert
Existing site
Llano
MP 265.0 - MP 275.0
Cartman
MP 334.0 - MP 344.0
Olson
MP 410.0 - MP 420.0
Big Lake
Approximately MP 373.4
Pecos
MP 516.2 - MP 526.2
Utica
MP 543.6 - MP 553.6
Cottonwood
Approximately MP 576.3
Harris
MP 642.6 - MP 652.6
The Longhorn project includes both new construction and refurbishment of an existing
99144ba2.v8
9

<<<PAGE 339>>>

pipeline that has been converted from its former use of transporting crude oil from West
Texas to the Gulf Coast area. The existing pipeline has been modified to transport refined
petroleum products, with flow going from east to west. Williams Pipe Line Company
(Williams) will be the contract operator of the Longhorn Pipeline System. Longhorn intends
to transport multiple grades of gasoline and distillates (i.e., various grades of diesel fuel and
jet tuel).
The GATX to El Paso segment of the Longhorn Pipeline will function as an interstate
common carrier pipeline for those product volumes that will be transported across state
lines through the Longhorn Pipeline connections with the Kinder Morgan and Chevron
pipelines that extend across the Texas border into New Mexico and Arizona. Product
volumes moved from GATX to El Paso for delivery at El Paso will be intrastate movements.
The Crane to Odessa segment of the Longhorn Pipeline is an intrastate common carrier
pipeline since it transports products solely within the State of Texas.
Table 2 lists a chronology of overall pipeline actions leading up to the present.
Table 2 - Chronology of Longhorn Pipeline Actions
1949-1950
Exxon constructed the original 18"/20" pipeline, Crane to Baytown, to transport crude oil.
1950-1990
Operation and Periodic maintenance/refurbishment.
1990
An internal inspection (smart pig) of the 20" pipeline was performed.
1995
An internal inspection of the 18" pipeline was performed.
1995-1996
The 18" and 20" pipelines were subjected to a hydrostatic pressure test and purged with
nitrogen.
Oct 21, 1997
Longhorn acquired the existing pipeline from Exxon.
1s Qtr. 98
Longhorn cleaned the existing pipeline to remove crude oil from the inner walls, so to
prepare the existing pipeline for use in petroleum products service. Construction of new
pump stations, terminals, and new pipeline sections began.
1998/1999
New Construction completion dates (dates shown are dates of substantial completion):
Galena Park Origin Station - August 1998
Satsuma Pump Station - August 1998
Cedar Valley Pump Station - July 1999
Crane Pump Station- March 1999
Kimble County Pump Station - July 1999
El Paso Terminal and Pump Station - August 1999
20" Pipeline, GATX to Tie-In to Existing 20" Pipeline, Houston - October 1998
8" Pipeline, Crane to Odessa - November 1998
18" Pipeline, Crane to El Paso - November 1998
(0.5 mile remains to be constructed to Odessa Meter Station)
Odessa Meter Station - In design
Equipment installation remaining at a few sites
Cleaning and refurbishment of the existing pipeline 18"/20"- March to November 1998
Pipeline Laterals - In design (from El Paso terminal to tie-in point with three interstate
1999
Longhorn commenced implementation of Environmental Assessment mitigation measures,
pipelines)
2000
including maintenance construction and investigation of potential pipeline flaws.
Longhorn continued implementation of Environmental Assessment related pipeline mitigation
testing of the Houston to Crane segment of the pipeline, investigation of potential pipeline
measures, including ROW maintenance and marking, maintenance construction, hydrostatic
flaws, and cathodic protection system improvements.
Additional details about the pipeline system, and its operation and maintenance, are
contained in Section 7.0 of the Longhorn
Pipeline Project Description prepared in
99144ba2.v8
10

<<<PAGE 340>>>

connection with the EA; a copy of the Project Description is provided in the accompanying
Phase Two Project Documentation Appendix at Tab 6.
For purposes of this Phase Two BA, Longhorn has identified the areas along the pipeline
where operating and maintenance activities "may affect" species and habitat. Areas of
potential effect include areas of potential species habitat along the pipeline route. Those
areas are identified in two documents: (a) Table 3, which lists pipeline stationing numbers
for potential habitat areas along the course of the pipeline; and (b) Figures 2 through 10
which graphically depict those same potential habitat areas.
This BA addresses those portions of the overall project that were not specifically identified
in the Phase One BA. Those items include pipeline operation, long-term maintenance,
planned additional construction and future unforeseen construction, potential pipeline
release and related emergency response, construction on the Edwards Aquifer recharge
zone and at Buescher State Park, hydrostatic pressure testing of approximately 60 miles of
pipeline that was not tested pursuant to the Phase One BA, internal treatment of the
pipeline with corrosion inhibitor, and right-of-way clearing over the Edwards Aquifer
recharge zone. Details of general construction procedures and environmental protection
guidelines for implementation of maintenance construction and pipeline testing activities are
contained in the Phase One BA and are not repeated herein.
Specific construction
procedures and environmental protection guidelines for the construction sites at Buescher
State Park (Houston toad habitat) and the Edwards Aquifer recharge zone are provided
below. Additional procedures and guidelines, as referenced in the following, are contained
in various parts of the Phase Two Project Documentation Appendix.
The EA assigned tier rankings to individual segments of the entire pipeline that identify
environmentally sensitive areas along the pipeline route. "Areas were identified as
sensitive based upon proximity and density of population, ground water (with an emphasis
on drinking water supplies), surface water, presence of threatened and endangered
species habitats, and proximity to recreational areas." See Draft Longhorn EA at Section
9.2.3. Sensitive
areas were divided into two categories, Tier | (sensitive) and Tier I!!
(hypersensitive); areas not designated as Tier II or Tier III are designated as Tier I. A
description of the methodology employed by the Lead Agencies to designate such sensitive
and hypersensitive areas is set forth in Appendix 9C of the EA, along with maps of those
areas. This Phase Two BA refers to such sensitive and hypersensitive areas.
99144ba2.v8
11

<<<PAGE 341>>>

Horizon
ENVIRONMENTAL SERVICES, INC.
Table 3: List of Endangered Species Habitat Areas
Along The Longhorn Pipeline
Houston to El Paso
Begin Station
2310+88
2013+44
End Station
2411+20
2279+20
County
Waller
Harris
Harris
Texas Prairie Dawn
Species
2684+00
4662+00
2831+84
Texas Prairie Dawn
5936+48
5095+20
4782+00
Fayette
Austin
Texas Prairie Dawn
5128+64
Navasota Ladies-Tresses
Navasota Ladies-Tresses -
Houston Toad
6723+20
6600+00
6638+72
5948+80
Bastrop
Fayette
9152+00
9011+20
9152+00
6864+00
Bastrop
Houston Toad
Travis/Hays
Travis
EA Recharge Zone
Houston Toad
9724+00
9657+12
9674+72
9961+60
Hays
Hays
Golden-Cheeked Warbler
EA Contributing Zone
9850+72
9762+72
10164+00
9945+76
10036+40
9926+40
Hays
Golden-Cheeked Warbler
Hays/Blanco.
Hays
Golden-Cheeked Warbler
10266+08
10461+44
10199+20
Golden-Cheeked Warbler
Blanco
Golden-Cheeked Warbler
11008+80
11080+96
11036+96
Blanco
Golden-Cheeked Warbler
Golden-Cheeked Warbler
11691÷68
11295+68
11441+76
11105+60
Blanco:
Blanco
Golden-Cheeked Warbler
Black-Capped Vireo
12114+08
11791+28
11751+52
12149+28
11821+92
Gillespie
Gillespie
Golden-Cheeked Warbler
Golden-Cheeked Warbler
12513+60
12633÷28
12596+32
12606+88
Gillespie
Gillespie
Golden-Cheeked Warbler
12631+52
Gillespie
Golden-Cheeked Warbier
Black-Capped Vireo
12921+92
12728+32
13043+36
13110+24
12953+60
Gillespie
Mason
Mason
Golden-Cheeked Warbler
Black-Capped Vireo
13203+52
13381+28
13277+44
13305+60
13217÷60
Mason
Golden-Cheeked Warbler
Golden-Cheeked Warbler
13513+28
13437+60
Mason
Mason
Black-Capped Vireo
Black-Capped Vireo
15153+60
14476+00
16329+28
13578+40
Mason
Kimble
Tobusch Fishhook Cactus
Black-Capped Vireo
15234+56
Kimble
Black-Capped Vireo
4/5/00
11 29 PM
indengered species hatreat ist
RAD 3907

<<<PAGE 342>>>

Louisiana
FIGURE 2
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
SHEET LOCATION MAP
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
LONGHORN PIPELINE
FIGURE 3
HOUSTON
HARRIS
FIGURE 4
AUSTIN
FIGURE 6
FAYETTE
FIGURE 5
RAVIS
AUSTIN
BASTROP
HAYS
FIGURE 8
LLANO 3
BLANCO
GILLESPIE
MASON
FIGURE 7
MENARD
KIMBLE
FIGURE 9
SCHLEICHER
FIGURE 1ó
NOT TO SCALE
RF AGAN!
CROCKETT
LONGHORN REFINED PRODUCTS
APPROXIMATE CITY LOCATIONS FOR
AS SUCE IN ATON (10/97
state.tx.ua/dato._oz.html), 1998
Mexico
UPTON
PIPELINE
REFERENCE
ODESSA
CRANE
CRANE
EXPLANATION
CRANE
SOURCES:
RAD 39072

<<<PAGE 343>>>

FIGURE 3
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
TEXAS PRAIRIE DAWN-FLOWER
HARRIS
EXAS PRAIRIE DAWN-FLOWEI
Hmenarys ferono
VAVASOTA LADIES -TRESSES
Saronthes ports"
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
On DAT
PIPELINE
• COUNTY BOUNDARY
- HIGHWAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
RAILWAYS
BRIDGES
CEMETERY
- LLP-2546 MAINTENANCE CONSTRUCTION
LOCATION
TEXAS PRAIRIE DAWN-FLOWER
WALLER
EXPLANATION
MC. SITE MMESTIOMON (RUNE 1999)
=:
MILES
PINE iSLAND
5 PEAS TOTA TREAD LURE DE: MATE PANTS OF
NAVILLE
359
2 RESOURCES TORTOR T 579/9
2 HIS TEN MOO BUT SINGE (197D, OF TOUS
5. HORIZON ENMRONMENTAL SERVICES.
* SURCES

<<<PAGE 344>>>

~ un HOUSTON TOAD I
(POTENTIAL HABITAT)
AUSTIN,
FIGURE 4
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELIN
WASHINGTON ~
NAVASOTA LADIES-TRESSES
TOMS PRAT DON-TOWER
AMONTA PIES -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
OLDENBURE
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—12P-2516 MUCITONMCE CONSTRUCTION
EXPLANATION
RAD 39074
MC. SITE DMESTIGITOM (UNE 1990)
NAVASOTA LADIES-TRESSES
FAYETTE +
ROTECTED MATHE PLANTS OF
VILES
00 5 50 0/9/90
2 TO TO NO BON SONE TIES OF TOUS.
OURCES
NO SOURCE

<<<PAGE 345>>>

Hono
FIGURE 5
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
RTLEY.
HOUSTON TO CRANE SEGMENT
COUNTIES OF: TEXAS
LONGHORN PIPELINE
HOUSTON O HoL ESOTE AREAS OF POTENTIAL FEDERALLY-LISTED
COLORADO
HOUSTON TOAD
(POTENTIAL HABITAT)
REPLACEMENT.
PIPE
HOUSTON TO ALSTOM
HOUSTON TOAD
Countaco ChO OMELER
AANO AAD VREO
TORsto coti PoK aCTUS
MAISOTA S PONt-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
LE DESIGNATED CRITICAL HABITA
— COUNTY BOUNDARY
→ J ACHMAY OR ANOR RONOS
CITY STREETS
RIVERS AND STREAMS
NTERMTTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
BASTROP
ROADS
RAILWAYS
BRIDGES
CEMETERY
- LLP-2516 MAINTENANCE CONSTRUCTION
LOCATION
EXPLANATION
WATTERSON
OCKNE
& HORIZON DIMRONMDYTAL SERMCES, INC, SITTE IMMESTIGMOM (RUNE 1999)
2. TeSORCES TORSTON S13T3 (3/87
2 TIS FSH MOO DUF SONOS 19ES, OF TOUS.
S. PON TEDA PASSED MATE DER ME PRATS. OF

<<<PAGE 346>>>

"ZONE'T
UKAWINU 990144-A29
NUMBER
FIGURE 6
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
EDWARDS RECHARCE
KŁVISED
BY
3/8/00
HAYS
DKAr 1
TRAVIS
MASON POTS-TRESSES
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
CONTRIBUTING ZONE
ORIPPING
GOLDEN-CHEEKED WARBLER
— COUNTY BOUNDARY
332 HIGHMAY OR MAVOR ROADS
CRY STREETS
RIVERS AND STREAMS
INTERMITTENT STREANS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MAATRANCE CONSTRUCTON
EXPLANATION
RAD 39076
DOES OF TOUS:
CE BE MATE PLAITS OF
ACHMENTAL SERMCES, NC. STE BMESTIEATION (INE 1990)
MILES
5763/9/94
Do Not Scole This Drawing
BLANÇO

<<<PAGE 347>>>

AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
BLACK-CAPPED VIREO
BLANCO
MAMOTA POTS TRESSES
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
→ CACHTY OR MANOR RONOS
— COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—LLP-2516 MUNTIONICE COMSTRUCTION
cORO
EXPLANATION
GOLDEN-CHEEKED WARBLER
man 20n77
PIPELINE
MILES
ÇILEŚPIE
DA SON (TO), OF TONS
LLANO
MPSOURCES
5 POET TOE

<<<PAGE 348>>>

ABAPPLE
PIPELINE
LLANÓ
FIGURE 8
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
| GOLDEN-CHEEKED WARBLER
> I BLACK-CAPPED VREO
HOUSTON TOND - DESIGNATED AREAS OF POTENTIAL FEDERALLY-LISTED
con
HILLTOR 7
GILLESPIE
HABITA Buto houstone)
ADO CARDO VARCO
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
2242
GOLDEN-CHEEKED WARBLER
COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
-IP-2516 LOCATONCE CONSTRUCTION
EXPLANATION
BLACK-CAPPED VIREO.
RAD 39078
MASON
1.5
MILES
a HORIZOM DIMRONMENTAL SERMICES, MC, SITE BESTOMOM (LUME 1990)
2 TAS TEN MONO BIA SINCE TOD, OF TOAS
PIPELINE
DO SOURCES.

<<<PAGE 349>>>

rook
-GILLESPIE
BLACK-CAPPED VIREO
88
FIGURE 9
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
HOUSTON TOAD - DESIGNATED AREAS OF POTENTIAL FEDERALLY -LISTED
MASON
HABITAT Buto houstonerais)
GOLDEN-CHEEKED WARBLER
(Dendracio chrysoporio)
Testroots tok carys
JAVASOTA LADIES-TRESSES
(arranthes port)
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
MOUNTAN
COUNTY BOUNDARY
→ Je HIGHMAY OR MUOR RONDS
CITY STREETS
RIVERS AND STREAMS
NTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— 11-2516 MAUATINANCE CONSTRUCTION
EXPLANATION
KIMBLE
#/**
RAn
LONDON
cook
TOBUSCH FISHHOOK CACTUS
3480 YATES
& HORIZON EMIRONMENTAL SERVICES, MC, SITE IMESTIGATIOM (SUME 1999)
TEACUP
ST PASSED OUR UST MONE PLANTS OF
2. THE AN AND DIA SOME TODD OF TOUS.
MENARD
377

<<<PAGE 350>>>

NUMOLN -
BLACK-CAPPED VIREO
CÁCTUS LOCATION
FIGURE 10
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
HOUSTON TO DEED AREAS OF POTENTIAL FEDERALLY-LISTED
DI
310/00
KIMBLE
TOAD - POTENTIAL
TRA PRAN I DONY FOWER
SOOTA POES-TESSES
EDWARDS RECHARGE ZONE
TOBUSCH FISHHOOK CACTUS
CONTRIBUTING ZONE
/
Pook
MENARD
→ CONNY OR MANOR ROADS
• COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTEOANCE CONSTRUCTION
EXPLANATION
RAD 39080
1674
SITE MMESTOKTON (RUME 1990)
MILES
PIPELINE
I SON (1092, OF TOUS
SUTTON
2 TrOot COUNTY
SCHLEICHER
SOURCES:

<<<PAGE 351>>>

3.2 Pipeline Operation
Operation of the Longhorn Pipeline essentially involves the pumping of refined petroleum
products through the pipeline to terminals at El Paso and Odessa, where the products are
stored in above-ground breakout tanks. From either terminal, the products will be loaded
into tank trucks for transport to distribution facilities (such as gas stations and fleet servicing
facilities). In addition, at the El Paso Terminal the products may be re-introduced into the
connecting pipelines,
and then to interstate pipelines operated by Kinder Morgan and
Chevron, for transport to southwestern markets.
The process of pumping refined products involves the following steps. First, products from
bulk storage tanks at the GATX terminal in Galena Park are introduced in batches to the
pipeline at the Longhorn GATX pump station. As the products proceed through the
pipeline, booster pump stations continue to move the product stream; those booster
stations include Satsuma Station in northwest Houston, Cedar Valley Station in Hays
County, Kimble County Station in Kimble County, and Crane Station in Crane County.
Product destined for Odessa is stored in above-ground breakout tanks prior to re-
introduction to the 8-inch pipeline between Crane and Odessa.
The pipeline system is operated and controlled remotely from the Williams control center in
Tulsa, Oklahoma, using the supervisory control and data acquisition (SCADA) system. The
SCADA system allows the controller to start and stop pumps, open and close valves, and
monitor the functions of the system components. Pump station and valve site operations
are managed by programmable logic controllers that interpret and execute commands from
the system controller. A multitude of sensors installed in the pipeline and its equipment
provide data to the controller and the automated leak detection system.
Primary
communications are conducted by satellite, with backup provided by land line systems.
Section 7.0 of the Longhorn Pipeline Project Description provides additional detail about
system operation; see Phase Two Project Documentation Appendix at Tab 6.
3.3 Long-Term Maintenance
Maintenance of the Longhorn Pipeline requires activities directed to specific components of
the system. For example, pumps and valves receive inspections and maintenance such as
lubrication; above-ground tanks receive inspections and maintenance; the right-of-way
(ROW) is mowed periodically, and ROW marker signs are erected and replaced as
necessary (see Phase One BA); and the pipe is periodically subjected to thorough
inspection and analysis that may dictate a variety of maintenance approaches. Additionally,
corrosion inhibitor is regularly injected into the product stream to prevent internal corrosion.
This Phase Two BA focuses on those maintenance activities that could occur within areas
of habitat identified during Phase One. Since the El Paso terminal is not within potential
habitat areas, terminal maintenance activities are not treated in this BA. Since Kimble
County Station is within a habitat area (Tobusch Fishhook Cactus) and Cedar Valley
Station is in an area of potential effect to the Barton Spring Salamander, station
maintenance descriptions will focus on activities conducted at those stations.
Valve Maintenance
99144ba2.v8
22

<<<PAGE 352>>>

Valve maintenance involves periodic inspections (twice per year, not to exceed 7 ½ months
between inspections, per 49 C.F.R. 195.420(a)) to ensure that the valve is not leaking and
to confirm that the valve is operable. Leak and overall condition inspection is visual, as
described
| in the Williams Operating and Maintenance Manuals, Maintenance and
Calibration section, Valve Maintenance and Calibration (Phase Two Project Documentation
Appendix at Tab 7). If a leak is identified, corrective action is taken to stop the leak and
perform cleanup of any product released. All lubricants are managed to prevent any
release to the environment; specific procedures are identified in the Williams System of
Manuals, Operating Manual, Section 12 (Phase Two Project Documentation Appendix at
Tab 7).
Pipeline Cleaning
Pipeline cleaning is conducted approximately twice per year to remove deposits from the
inner walls of the pipe. Pipe cleaning involves the introduction of a spherical or cylindrical
scraper (also known as a scraper pig) into the pipeline at a pump station; the scraper
travels within the product stream and is removed at a downstream station, along with any
debris collected along the way. Launching and receipt of the scrapers is accomplished by
way of scraper launchers and scraper receivers (traps, also known as strainers) that are
installed at the pump stations. Any debris removed from the pipeline is contained in drums,
and drip pans are employed to prevent release to the environment; disposal of the material
is conducted in accordance with applicable laws and regulations.
Pump Station Maintenance
Pump station maintenance protocols depend upon the equipment located at each individual
station; however, only two similarly equipped stations lie within habitat or in an area of
potential effect to species. Those are Kimble County station which is located in Tobusch
Fishhook Cactus habitat in Kimble County and Cedar Valley Station which is located in the
Edwards Aquifer contributing zone. Each of those stations contains minimal equipment,
the major components of which are pumps and electric motors, scraper launcher/traps,
above-ground station piping (to bypass a pump or the station as a whole), intake and
outflow (suction and discharge) remote-controlled motor operated block valves, and a
station control room. No tanks are located at those two stations.
Maintenance of the pump station equipment follows generally the same procedures
outlined above for valve maintenance, and below for painting of above-ground components.
Pumps require inspection and periodic calibration. Calibration requires that the pump
cases be opened for measurement of component tolerances. To do so, the pump is
isolated from the pressurized pipeline system, and the case is opened; product remaining
within the case is collected in a sump system for re-injection to the product stream. The
sump system is sealed and cathodically protected to prevent releases to the subsurface.
Drain pans are used if product cannot be drained to the sump; the drain pans are emptied
to the sump system for re-injection. Any debris removed from the pump case, along with
wipe rags, sorbent pads, and other disposable materials, are collected in a closed top
containment drum and stored on a concrete containment skid. The waste materials are
classified and then disposed of at an approved disposal facility.
99144ba2.v8
23

<<<PAGE 353>>>

Pipe cleaning debris (see foregoing section) is collected in strainers located at each pump
station. The strainers are located upon a concrete skid that contains any liquid from the
strainer and drains to the station sump system. Drain pans are used to contain any liquid
that will not drain directly to the sump system. Debris removed from the strainer is
collected in closed top containment drums and stored on a concrete containment skid. The
waste materials are classified and then disposed of at an approved disposal facility.
Painting Above-Ground Components
Above-ground pipeline components must be protected with coatings (Longhorn uses paint)
to prevent atmospheric corrosion (49 C.F.R. § 195.416(i)). Above-ground facilities include
pump equipment, valves, meter facilities, and the like. Maintenance of the coatings
requires periodic painting, typically on a 5 to 10 year cycle. Any waste materials generated
during painting are managed to prevent release to the environment. See the Williams
System of Manuals, Operating Manual, Section 12 and the Longhorn Environmental
Protection Plan (Phase Two Project
Documentation Appendix at Tabs 7 and 8,
respectively).
Pipe Integrity Maintenance - Introduction
Pipe integrity maintenance activities result from inspections and analyses that identify
potential threats to pipe integrity; maintenance may then occur to reduce the risk
associated with a particular threat.
In-Line Inspection
In-line inspection is the process of examining the pipe for flaws, corrosion anomalies,
dents, cracks, and other flaws using sophisticated electronic inspection devices known as
The technology applied is known as high resolution magnetic flux leakage
(MFL) and transverse field MFL, and geometry and ultrasonic inspections are performed as
well. Smart pigs identify anomalies and record the locations. The smart pig data is then
processed and analyzed, both manually and by computer, to determine whether or not the
identified anomalies represent pipe flaws that require corrective action. Next, the
anomalies are graded and prioritized for inspection; upon inspection, repairs are made, if
necessary, to offset the potential adverse effect of the specific flaw. Actions will range from
re-coating of a location not requiring repair, to replacement of the flawed pipe with a
cylinder of new pipe; typically minor repair such as application of a protective sleeve is all
that is necessary. Maintenance construction to investigate and repair flaws identified by
the in-line inspection will be conducted in accordance with the procedures set out in the
Phase One BA
An in-line inspection may produce data that indicates an immediate threat to pipeline
integrity, prompting an immediate inspection by excavating the pipe. If an actual threat
exists, a repair is made, and otherwise the pipe is coated and buried. In either event, the
protection of human health and safety and of the environment is accomplished while efforts
are undertaken to avoid all potential adverse effects. See LMP at Sec. 3.5.2.
Smart pigs are introduced and extracted from the operating pipeline through the scraper
launcher/trap at each pump station; however, some pipeline segments between pump
99144ba2.v8
24

<<<PAGE 354>>>

stations are long enough that the smart pig cannot complete the entire run. In such cases,
a temporary launcher/trap assembly is installed on the pipeline to allow removal of the
smart pig so that data may be downloaded, batteries recharged, and the smart pig re-
launched. Construction to install and remove the temporary launcher/trap assembly is
similar to construction to install a hydrostatic pressure test header as described in the
Phase One BA. Electronic tracking devices that monitor and record smart pig travel are set
on top of the ground during the tests.
The initial in-line inspections to be performed pursuant to Longhorn Mitigation
Commitment 11 shall consist of a high resolution MFL inspection within three (3) months of
system startup. The timing of subsequent in-line inspections of all types will be determined
by the Longhorn Pipeline System Integrity Plan and associated Operational Reliability
Assessment processes.; the LMP sets maximum intervals for certain tools See Longhorn
Mitigation Plan, Items 10, 11, 12, and 12A, and at Section 4.0. No more than three years
shall pass without at least one in-line inspection. Temporary launcher/trap assemblies, if
any are necessary, will be installed outside of areas of species habitat; thus, no effect upon
species is foreseen as a result of in-line inspections.
Hydrostatic Pressure Testing
Integrity maintenance of the pipeline could require periodic hydrostatic pressure testing, if
prompted by the Longhorn Operational Reliability Assessment (see LMP at Sec. 3.3 and
4.0). Hydrostatic pressure testing as prompted by the ORA could encompass different
segments of or all of the pipeline.
The Phase One BA describes in detail the processes
and activities involved in hydrostatic testing, and future testing will be conducted in
conformance with the Phase One BA in all respects to avoid potential adverse effects.
Corrosion Inhibitor Treatment
Shortly after the conclusion of this consultation, Longhorn will treat the pipeline to prevent
potential internal corrosion. As a matter of course, potential internal pipe corrosion is
managed through several means including the injection of corrosion inhibitors to the
product stream. Due to the delays encountered during the Environmental Assessment of
the Longhorn pipeline, however, product has not been transported and no corrosion
inhibitor has been applied.
At the urging of the Service, Longhorn elected not to inject corrosion inhibitor during the
hydrostatic and proof tests commenced in February. Due to the project delays associated
with the Environmental Assessment, Longhorn intends to treat the pipeline at its next
opportunity to reduce the potential for internal corrosion prior to project startup. This
process may be repeated from time to time as deemed necessary to maintain internal
pipeline integrity; however, Longhorn's present expectation is that only one such treatment
will be necessary.
The treatment process involves the introduction of a water and corrosion inhibitor mixture
into the pipeline at the GATX Terminal in Houston and the mixture pushed through the
pipeline with injected nitrogen gas pressure. This will not constitute a pressure test or
alteration of operating pressures.
Maximum pressures involved in the procedure would not
reach normal operating pressures. These pressures are significantly below the 1,100 to
99144ba2.v8
25

<<<PAGE 355>>>

1,500 psig pressures experienced during periodic hydrostatic testing of the pipeline. At
seven intervals along the pipeline (existing valve settings), surface equipment would be
needed to facilitate the handling of the water slug and pigs if the procedure is conducted
independent of product flow in the line. Those points typically would be:
MP 34.09
(Satsuma Station)
MP 134.67
(west side of Colorado River)
MP 151
(eastern Travis County)
MP 182
(Cedar Valley Station)
MP 227.9
(Eckert Station)
MP 358.7
(west of El Dorado)
MP 457.5 (Crane Station)
At these points, trucks and equipment would be employed to facilitate the launching and
recovery of pigs and nitrogen injection. The water mixture would be recovered into vacuum
trucks at Crane Station for proper disposal.
The corrosion inhibitor agent to be utilized is manufactured by Baker-Petrolite and goes by
the commercial name "Magnacide 575." Material Safety Data Sheets for this product are
included in the Phase Two Project Documentation Appendix.
Cathodic Protection
Maintenance of the cathodic protection system requires periodic inspection and testing and
potential system enhancements. Testing and inspection involves pipe-to-soil surveys,
close interval surveys, rectifier inspections, casing tests, and interference testing.
Pipe-to-soil potential surveys require that pipe-to-soil readings, measured in volts, be taken
at pre-existing test stations that are spaced along the pipeline. Survey personnel typically
travel along the pipeline in a pickup truck. Pipe-to-soil surveys will occur semi-annually in
EA-designated sensitive and hypersensitive areas and annually in other areas.
Close interval surveys require that pipe-to-soil potential readings be taken approximately
every three feet along the pipeline; thus, testing personnel walk the pipeline, typically in a
group of two to five, carrying testing equipment and data loggers. Close interval surveys will
be conducted annually in EA-designated hypersensitive areas and on the balance of the
pipeline as dictated by the Longhorn Pipeline System Integrity Plan and associated
Operational Reliability Assessment (see LMP at Sections 3 and 4, Tab 4).
Rectifier inspections include monthly visual inspection and recording of voltage and
amperage readings to ensure normal operation; bi-monthly inspections are required by the
pipeline safety regulations (49 C.F.R. § 195.416(c)). Casing testing may involve pipe-to-
soil potential readings and/or electrical current and resistance readings to determine if the
99144ba2.v8
26

<<<PAGE 356>>>

casing is in direct contact or electrolytically shorted to the carrier pipe. Interterence testing
involves pipe-to-soil readings and/or line current measurements to determine whether or
cathodic protection system is interfering with the cathodic protection current that protects
not a nearby metal object (such as a crossing or parallel pipeline) or the associated
the Longhorn pipeline.
Pipe-to-soil surveys, close interval surveys, casing testing, and foreign interference testing
may identify sections of pipe that require additional cathodic protection or other measures,
such as coating re-conditioning, shorted casing remediation, or installation of a bond
between the Longhorn pipeline and a source of foreign structure cathodic protection
interterence.
The addition of cathodic protection current most likely will occur through the installation of
sacrificial anode or impressed current ground beds. The procedure for installation of a
ground bed is contained in the Phase One BA, as is the procedure for coating
reconditioning. Shorted casing remediation involves removal of a direct metallic short (i.e.,
a spacer bolt or a short segment of the casing end in contact with the carrier pipe), or
draining electrolyte (water/mud) from the casing. Some casing remediations may require
installation of new pipe, often concrete coated, through the casing or the installation of
heavy wall thickness pipe, also with an abrasion resistant overcoat (i.e., concrete), bored
under the road/railroad crossing. Any such work in habitat areas will follow the
maintenance construction procedure outlined in the Phase One BA.
Installation of a bond (a cable) to a foreign source of cathodic protection interference would
involve a small excavation between the Longhorn Pipeline and the foreign structure, which
are by definition in close proximity. A cable is installed between the facilities and secured
to the pipe, usually by thermite welding. Typically, an interference bond installation will
occur at or very near a crossing of the pipelines. A bell-hole excavation of approximately
ten feet by ten feet, or one-hundred square feet, is sufficient. A depth to that of the deepest
line, normally six to eight feet, is needed for the installation. Note that only the top side of
the deeper line, not the entire circumference, needs to be exposed to accommodate lead
attachment. The cables are brought into an
aboveground test station for current flow and
pipe-to-soil potential monitoring. The test station will generally be set directly over the
pipelines' intersection. However, in some cases, if a fence line is nearby, the leads will be
extended to that fence and the test station installed at that location. The trench for leads
from the pipelines' intersection to the fence could range from ten to usually not more than
fifty feet and from 8 inches to three feet wide and approximately 30 inches deep or below
plow depth.
Typically, not more than one-hundred-fifty square feet of surface area is
disturbed for this trench and it typically remains within the pipeline rights-of-way. Coating
disturbed during cable installation is repaired. Any such work in habitat areas will follow the
maintenance construction procedure outlined in the Phase One BA.
Cathodic protection system maintenance construction is typically conducted completely
within the existing ROW. Though unexpected, the possibility exists that future construction
could require work to occur outside the existing ROW, since a particular site could be
attended with work space constraints (see procedure in the Phase One BA).
Depth of Cover
99144ba2.v8
27

<<<PAGE 357>>>

In 1998 Longhorn performed a depth of cover survey to determine the burial depth of the
pipeline. In response to the findings of that depth of cover survey, Longhorn has identified
a number of locations where the pipeline will be lowered or replaced. Examples of such
locations are represented by LMCs 5 and 18; those locations were identified through the
depth of cover survey and assigned priority either by Radian in the case of sensitive and
hypersensitive areas (LMC 5) or by Longhorn in the case of other lowerings (LMC 18). In
the coming years, the Longhorn Pipeline System Integrity Plan, Depth of Cover element,
will determine, on a risk-assessed basis, the order and timing of future pipeline lowerings.
The locations are prioritized by evaluating the potential for damage to the pipe.
As those locations are addressed, the activity will follow the maintenance construction
procedures described in the Phase One BA. Maintenance construction is typically
conducted completely within the existing ROW. Though unexpected, the possibility exists
that future construction could require work to occur outside the existing ROW, since a
particular site could be attended with work space constraints (see procedure in the Phase
One BA).
Removal of Encroachments
Longhorn has identified a number of encroachments that will be removed from the pipeline
ROW within one year of system startup, in accordance with the commitments of the LMP
(See LMC 16). The Service has requested Longhorn's assistance to increase landowner
awareness of species and habitat concerns in connection with encroachment removal.
Longhorn thus hereby commits to seek to include in any agreement with an encroaching
landowner the following acknowledgment:
Landowner is hereby informed that threatened or endangered species and/or
habitat may exist upon or in proximity to the Property [defined term to identify
the Longhorn ROW], and Landowner may have responsibilities to consult with
the U.S. Fish and Wildlife Service pursuant to the Endangered Species Act.
Longhorn acknowledges that the foregoing does not specifically prohibit by contract
Landowner activity that could cause adverse effects to species and habitat. Since any
agreement for encroachment removal would be voluntary, Longhorn cannot force
landowners to agree that adverse effects will be avoided. Landowners would simply refuse
to agree to such prohibitions, leaving Longhorn's power of eminent domain as the remedy.
The power of eminent domain does not include within its scope the authority to require
landowners to contractually agree to comply with applicable statutory requirements. In
summary, Longhorn agrees to raise awareness as much as it legally may.
Section 7.0 of the Longhorn Pipeline Project Description provides additional detail about
system operation and maintenance; see Phase Two Project Documentation Appendix at
Tab 6.
3.4 Emergency Response
Risk Based Approach - Longhorn Mitigation Plan
99144ba2.v8
28

<<<PAGE 358>>>

The EA process included the identification of pipeline mitigation measures that Longhorn
has committed to implement. Many of the pipeline mitigation measures were identified in
response to potential risks identified in the EA. The pipeline mitigation measures are
designed to reduce those risks by prioritizing the deployment of resources toward
the
following goals:
Prevention: Reduce the risk of a release by focusing on the four primary categories
of risk: outside force damage, corrosion, material defects, and improper operation.
Detection: Rapid identification of a pipeline release through use of the best available
leak detection technology system-wide, and sensor-based technology in the
Edwards Aquifer recharge zone.
• Release Volume Minimization: Optimal use of block valves, coupled with the
installation of additional check valves, will serve to reduce potential spill volumes,
including in areas of potential effect to species.
Control: Enhanced emergency response capability that employs thorough, detailed
pre-planning, resource identification, and resource retention.
A description of the manner in which those pipeline mitigation measures reduce risk is
presented in Longhorn's Risk Reduction Benefits Summary, Phase Two Project
Documentation Appendix at Tab 9.
Prevention - Reduce the Risk of a Release
Numerous pipeline mitigation measures are focused on reducing the risk of a pipeline
release; many pipeline mitigation measures reduce more than one risk category. For
example, hydrostatic pressure testing of the pipeline addresses outside force damage,
corrosion, and material defects by testing the pipeline to pressures that create a margin of
safety above operating pressures. Flaws that would create a potential for release during
operation are eliminated by raising and maintaining internal pipe pressure to at least 125%
of its operating pressure over an eight hour period.
The pipeline mitigation measures that reduce the risk of a release include the following:
:
Hydrostatic pressure testing (LMCs 1 and 2)
Replacement of an 19-mile segment over the Edwards Aquifer recharge and
contributing zones, with the additional protection of a concrete barrier over the pipe
(LMC 3)
•.
Cathodic protection system enhancements (LMC 4)
Lowering, replacing and/or reconditioning if necessary at least 38 locations (LMCs 5
and 18)
Removal of stopple fittings (LMC 6)
Investigation and repair if necessary of 7 potential pipeline flaws (LMCs 7 and 8)
Replacement of the crossing of Rabbs Creek (LMC 8)
Surge pressure in EA designated sensitive and hypersensitive areas will not exceed
maximum operating pressure (LMC 9)
99144ba2.v8
29

<<<PAGE 359>>>

• In-line inspection within 3 months of system startup and additional in-line inspections
according to the LMP, the Longhorn Pipeline System Integrity Plan and associated
Operational Reliability Assessment (LMCs 10, 11, and 12)
Increased frequency of cathodic protection system performance testing (LMCs 14
and 32)
•
Documentation of adequate pipeline span support and secondary containment at
tank facilities (LMCs 15 and 27)
•
Removal of encroachments to the pipeline ROW (LMC 16)
•
Clearing the ROW to excellent condition (LMC 17)
Analysis and remediation if necessary of stress corrosion cracking and earth
movement risks (such as water crossings and seismic activity) (LMC 19)
•
Increased frequency of pipeline surveillance patrols (LMC 20)
•
Increased frequency of pump station inspections and installation of remote cameras
at all pump stations (LMC 21)
Performance of a water crossing valve study, with DOT review and concurrence, of
additional check valves (LMC 22)
• Development of an enhanced public education program, with performance
monitoring (LMC 25)
The effect of the above mitigation measures is to significantly reduce risk far below pre-
mitigation levels.
Detect - Best Available Leak Detection Technology
Longhorn has committed to employ the best available, proven leak detection technology in
the pipeline industry. Pipeline mitigation measures that improve leak detection, thus
reducing the risk of an undetected leak, include the following:
• Enhanced, computational-based leak detection system-wide, and sensor-based leak
detection over the Edwards Aquifer recharge zone and the Slaughter Creek
watershed in the contributing zone (LMC 13)
Removal of encroachments to the pipeline ROW (LMC 16)
•
Clearing the ROW to excellent condition (LMC 17; see Phase One BA and the
Service's February 17, 2000 Biological Opinion)
•
Increased frequency of pipeline surveillance patrols (LMC 20)
•
Increased frequency of pump station inspections and installation of remote cameras
at all pump stations (LMC 21)
Development of an enhanced public education program, with performance
monitoring (LMC 25)
Minimize - Reduce Potential Release Volumes
Pipeline mitigation measures also focus on reduction of potential leak volumes:
•
Enhanced, computational-based leak detection system-wide, and sensor-based leak
detection
over the Edwards Aquifer recharge zone and the Slaughter Creek
watershed in the contributing zone (LMC 13)
99144ba2.v8
30

<<<PAGE 360>>>

•
Performance of a water crossing valve study, with DOT review and concurrence of
additional valves (LMC 22)
Install additional check valves, one over the Edwards Aquifer recharge zone and one
over the Edwards Aquifer contributing zone (this Phase Two BA; see section entitled
Edwards Aquifer Protections)
Control --Maximize Emergency Response Capability
Finally, Longhorn has committed to bolster its emergency response planning and
preparedness capability to reduce response times and to be prepared, in advance, with a
full response effort:
Ensure maximum 2-hour full response to EA designated sensitive areas, maximum 1
to 2 hours in hypersensitive areas, and maximum 1-hour response in the Edwards
Aquifer recharge zone and the Slaughter Creek watershed in the contributing zone
(LMC 23)
Establish a response center in South Austin (LMC 23)
Enhanced facility response plan will:
Address firefighting
in areas without Hazardous Materials response units
(LMC 24)
-
Provide detailed planning for areas with high populations of potentially
sensitive receptors (LMC 26)
Establish consistency with the City of Austin Barton Springs Oil Spill
Response Plan and the Service's Barton Springs Salamander Recovery Plan
(LMC 28)
-
Identify and provide detailed planning for multiple response locations within
the Edwards Aquifer recharge and contributing zones selected on the basis of
calculations of worst case times of transport to the recharge zone
In addition, Longhorn has included potential habitat areas on response plan maps and
included protection of such habitat areas in response planning and preparedness training,
in response to the Comment Letter (see Oil Pollution Act of 1990 Facility Response Plan).
Probability of Release and Risk Reduction
Longhorn has calculated the pre-mitigation probability of a pipeline release for the potential
habitat areas along the pipeline. Those figures are presented in the APR report at Tab 10
of the Phase Two Project Documentation Appendix. The basis for the probabilities
calculated is pre-mitigation data compiled by Radian for the Environmental Assessment.
Thus, the probabilities do not take into account the numerous risk-reducing pipeline
mitigation measures that Longhorn has committed to implement and is in the process of
implementing; see above section Prevention - Reduce the Risk of a Release, and Table 2,
Chronology of Longhorn Pipeline Actions.
The result, then, is that the possibility of a
release in the potential habitat areas will be further reduced from those shown in APR
report.
System-Wide Software-Based Leak Detection
99144ba2.v8
31

<<<PAGE 361>>>

The Longhorn Pipeline will employ the best available, technologically proven pipeline leak
detection system. The leak detection system is described in the following excerpt from
Item 13 of the LMP submitted in connection with the EA:
"Objective:
The objective of this program is to identify the Longhorn Release
identification time and the shutdown time required to minimize the size and
Detection Systems that will be employed to minimize both the leak
impact of a potential leak on the Longhorn Pipeline System.
Leak Detection Systems:
Leak detection for the unintended escape or potential loss of product
from Longhorn Pipeline incorporates the use of a combination of visual,
mechanical, and analytical processes, equipment, and models. Collectively,
Longhorn's Leak Detection System capabilities, which provide for several
areas of overlap, are designed to significantly reduce the likelihood of a
protracted period of undetected pipeline system breaches and continued
that would adversely contribute to human or
environmental exposure to hydrocarbon products. Heightened awareness of
the designated sensitive and hypersensitive areas along the Longhorn
pipeline has resulted in the employment of enhanced leak detection
technology and processes.
Longhorn's Leak Detection System is comprised of two primary components:
External Patrols; and Technology Based systems. By design, these two
areas of leak detection provide redundancy and assurance that a release will
be detected within the shortest time possible using current best available
technology.
External Patrols:
External Patrol of the Longhorn Pipeline System is primarily
accomplished through the targeted activities of Longhorn Operations and
directed third party surveillance contract personnel. Some of these activities
include aerial patrol, inspection of water crossings, ground based right-of-way
patrol, tank dike inspection, scheduled inspections of valve locations, surface
facilities, buried road crossings, and DOT regulatory based activities.
External Patrol is also enhanced through the incorporation of data
obtained through normal pipeline maintenance activities, such as those
accomplished via cathodic protection inspections, One-Call line spotting, and
physical pipeline examination during pipeline exposures.
Another important source of input under the category of External Patrol
results from the involvement of the general public, emergency response
organizations, contractors, and other third party sources. These groups are
specifically targeted via
• Longhorn's Damage Prevention Program (see
99144ba2.v8
32

<<<PAGE 362>>>

Longhorn Pipeline System Integrity Plan) and other activities which are
designed to instill awareness of the location of the pipeline corridor. Further,
active public education programs are designed to result in an increase in
public knowledge by which to primarily avoid, but to secondarily recognize,
any activities that could reasonably lead to adverse effects to the pipeline
system. With pipeline location awareness, product characteristic information,
and emergency response phone numbers and points of contact, the general
public, emergency responders, contractors, and other third party groups serve
as further insurance that system leaks can be minimized from third party
damage, may be recognized if one occurs, and in that case be communicated
to Longhorn Operations personnel.
External Patrol leak detection is dependent upon the physical
identification of some abnormality or change from the characteristics of the
surrounding area of the pipeline corridor. Physical evidence can include a
hydrocarbon odor, a sheen on a water surface, spraying product, bubbles
along the ground, discoloration of soil, areas of vegetation "browning," and
fires in near proximity to the pipeline assets. Similar to many other methods
of leak detection, External Patrol leak detection can readily identify a
moderate to major product release. Smaller leaks, be they from pinhole leaks
or leaking pipeline components, often require more time to trigger the physical
indicators such as defoliation or odor which indicate a potential product leak.
Technology Based:
Longhorn will employ a leak detection software system to monitor the
operation of its pipeline system. This system represents the current best
available, proven technology in the industry. The leak detection software is a
transient model that is designed to analyze and compare the actual pipeline
operations of pressures and flow rates against theoretical values during both
steady state and changing conditions. Deviations between actual and
theoretical values result in alarm indications and notification to the Operations
Control Center for subsequent review, analysis, investigation, and if
appropriate shutdown of the pipeline system.
Longhorn approached the selection of a computational based leak
detection software system through the employment of a highly respected third
party consultant who has demonstrated experience in the field of pipeline
SCADA systems and leak detection, along with a current understanding of
leak detection technologies and performance capabilities. Leak detection
performance requirements, based upon demonstrated industry achievable
levels and best available transient model technology, were developed by
Longhorn's consultant and approved by Longhorn's management.
Computational based Leak Detection "Requests For Proposals" were sent to
several prospective vendors, and responses were returned to Longhorn's
consultant for detailed review and evaluation. The review/analysis process
included clarifying discussions with the vendors, technical presentations, and
detailed reference checks with provided customer lists. This process yielded
two vendors who were judged to be capable of meeting the leak detection
99144ba2.v8
33

<<<PAGE 363>>>

performance requirements established by Longhorn. Further discussions with
the two "finalists" resulted in the selection of the computational based leak
detection software system that was determined to have the higher degree of
leak detection performance.
The software based leak detection system is fundamentally a volume
(mass) balance system that employs a fully transient model. The flow
balance calculated from flow measurements is corrected by the packing rate,
which is calculated by the "real-time" model. The resulting volume balance
allows calculation of potential leak indicators. A leak would be identified by
comparing the node flow balances at measurement points.
The model
dynamically tracks changes in the pipeline's flow rate. Variation between
modeled and measured flow shows up in the volume balance calculation.
The rate of change of all boundary measurements affects the leak detection
by affecting the model directly, as well as the dynamic thresholds. Leak
alarm thresholds are provided for each volume balance section and averaging
interval.
The SCADA system used for the Longhorn pipeline system operates
on Neles (formerly Valmet Automation) Oasys software version 5.2.
Longhorn operator Williams subscribes to the Neles maintenance program
which provides software program updates.
Williams maintains the most
a communeason and contin at the pie se
components. For example, in 1999 the SCADA system experienced 99.954%
reliability (after deduction for Y2K testing). The 0.046% down time for that
year is attributable to a single four-hour service outage. Thus, it is very
unlikely that the SCADA system would be out of service for any appreciable
amount of time.
A SCADA system outage could result in a loss of leak detection
system sensitivity. An outage which does not affect the entire SCADA system
can occur, for example, with the loss of data from a remote terminal unit
(RTU) at a pump station for more than three minutes, in which case an alarm
sounds in the Control Center to alert the controller.
Under such
circumstances, the system uses backup land line communications links to
reestablish communications. However, the leak detection system is able to
maintain its detection capability by modeling across the point of data loss. A
loss of SCADA communications that affected the entire system, for example
because of
a computer malfunction, would immediately be known to the
controller. If the SCADA system experiences any outage that results in a total
loss of leak detection capability for all or any portion of the pipeline for a
period in excess of 5 minutes, then the controller will take action to achieve
system shutdown within 30 minutes. In the event that the SCADA system
experiences an outage that does not result in a loss of leak detection
capability, but instead results in a diminished capability of the system to
detect a leak, then the controller will take action to achieve system shutdown
within 30 minutes if the capability of the system to detect leaks is diminished
99144ba2.v8
34

<<<PAGE 364>>>

to a level that would prevent Longhorn from meeting its "Leak Detection
Performance Commitment" set out below.
Further Enhancement:
In addition to the computational based leak detection system,
Longhorn has committed to employ additional technology to provide for more
Stringent leak detection across the environmentally sensitive Edwards Aquifer
Recharge Zone and the Slaughter Creek watershed in the Edwards Aquifer
Contributing Zone (the "Enhanced Leak Detection System"). In order to
achieve this capability, Longhorn plans to employ a hydrocarbon sensing leak
detection cable system that has clearly demonstrated the leak detection
capability to satisfy Longhorn's commitment contained within Mitigation
Commitment 13.
This system is designed to detect a leak as small as 0.0030467 barrel
per hour in twelve (12) to one hundred twenty (120) minutes from contact with
the leak detection cable, depending upon the product sensed by the system.
Several factors will make it probable that any released product will come into
contact with the leak detection cable within a minimum amount of time,
including the following: (a) the construction methods that Longhorn will
employ over the recharge and contributing zones during replacement of this
segment of pipe, including protection of all identified subsurface voids; and
(b) backfill materials used within the trench (primarily fine materials to provide
padding to the pipe and otherwise relatively porous media), coupled with the
primarily limestone geology of the Edwards outcrop and the fact of the in-
trench materials having been disturbed will cause any released product to
accumulate within the trench where the leak detection cable will be located.
Longhorn has committed to having this system in place prior to start-up of the
pipeline.
The hydrocarbon sensing leak detection system is based upon the
TraceTek hydrocarbon sensing cable manufactured by Raychem HTS.
Longhorn's ultimate choice of the TraceTek cable was made after Longhorn,
Williams and UTSI International Corporation performed exhaustive research
of leak detection technology potentially feasible for this particular application.
After detailed analysis of potentially feasible leak detection technologies, and
consultation with the Office of Pipeline Safety, the TraceTek cable was
identified as the current best available, proven technology in the industry.
The table below identifies the sensing capabilities of the TraceTek system.
Leak Detection Response:
With notification typically originating through the utilization of its
External Patrol and Technology Based components of its Leak Detection
System Capabilities,
Longhorn Pipeline will facilitate
the orderly and
controlled shutdown of its system within five (5) minutes of a probable leak
indication.
99144ba2.v8
35

<<<PAGE 365>>>

Longhorn maintains 24-hour surveillance of its pump stations,
motorized valve locations (MOV), terminals (pipe, pumps, valves, meters, and
tanks), and meter stations through its SCADA system.
(Truck loading
operations at the El Paso Terminal are monitored locally.) Twenty-four-hour
surveillance will also be maintained with respect to Longhorn's Enhanced
Leak Detection System. Pipeline operational data from these locations is
transmitted directly to the Tulsa Operations Control Center, where trained and
qualified Operations Control personnel monitor and provide equipment control
commands to the Longhorn system.
Operations Control personnel utilize the following methods for the
determination or suspicion of a probable leak indication:
•
Deviation outside normal operational thresholds from the
computational based transient leak detection software system in
a direction that is indicative of a leak;
•
Receipt of an alarm by the sensor cable system over the
Edwards Aquifer Recharge Zone;
Unexpected deviation outside minimum or maximum alarm
thresholds for system pressures and flow rates;
Rate of Change alarms that compare pressure or flow value
change versus time;
Operations Control personnel independent analysis of flowing
conditions;
•
Third party call of suspected or confirmed product leak;
•
Input from Field Operations Personnel;
Automatic closure of MOV's or stoppage of pipeline pumps; and
• Terminal high level alarms.
Analysis of a suspected pipeline leak is accompanied by an
identification of the location of the suspected leak.
Upon the detection, notification, and determination of a probable leak
indication, Operations Control personnel are trained to immediately shut down
the pump station(s) upstream to the leak location. The pump station
downstream to the leak location is either kept running or is started to assist
with the orderly movement of product away from the leak location. Following
the shut down of the upstream pump(s), the Operations Control personnel will
close the upstream MOV's from the leak location to prevent the introduction of
new product to the segment. Through the use of the SCADA system,
upstream pump stoppage and MOV closure are accomplished within five (5)
minutes from the identification of a probable leak indication.
The Longhorn Pipeline was designed to be shut down immediately
following a probable leak indication. Communication with field operations,
product origination or destination points and terminals are not required to shut
down the pipeline in an orderly or safe fashion. Operations Control personnel
are trained to notify the appropriate supply, destination, field operations, and
99144ba2.v8
36

<<<PAGE 366>>>

emergency responder personnel as soon as practical following the shut down
and isolation of the pipeline.
The above emergency shut down procedures will be documented and
tested for Operations Control personnel training certification prior to start-up
of the Longhorn Pipeline system.
The Longhorn pump stations utilize a Programmable Logic Controller
(PLC) to handle the start-up, sequencing, data transmittal, and shut down of
the equipment within the station. The Tulsa Operations Control Center sends
command signals to and receives operational data from the PLC's at each
pump station. The PLC's, coupled with the instrumentation contained at each
pump station, serve to protect the pump equipment from mechanical
disturbances such as vibration, abnormal motor winding or pump bearing
temperatures, loss of product through seal leaks, and fire sources. Internally,
the pump equipment is protected from conditions of high product flow, low
product flow, low system pressure, high system pressure, and excessive or
low motor amperage.
The PLC is programmed to provide both early
indication alarm and automatic pump shutdown in the event that designated
parameters are operated outside their intended range.
Pressure, flow, and tank level readings from across the pipeline
system are transmitted to the Tulsa Control Center via the SCADA system for
computational transient modeling
analysis and Operations Controller
interpretation of the physical data, as is the data generated by the Enhanced
Leak Detection System. The status of the sensor cable system over the
Edwards Aquifer Recharge Zone also is transmitted to the Tulsa Control
Center. Outside of the automatic shut down of pump units that are controlled
by the local pump station PLC's, shut down of equipment and isolation of
MOV's are originated by the Operations Controller.
Leak Detection Performance Commitment:
Longhorn is committed to implementing the best available leak detection
systems with the following design specifications:
SYSTEM DESIGN
LOCATION
SPECIFICATIONS
Tier I
1% of flow detected within one-half hour.
Tier lI
1% or more of flow detected within one-half hour.
Tier III
0.5% - 1% of flow detected within one hour.
Same as Tier II, except Edwards Aquifer recharge zone an
ontributing zone (Slaughter Creek watershed
Edwards Aquifer
barrel/hour from contact for the following products
Same as Tier Il, and sensor-based detection of 0.0030467
• Gasoline - 12 minutes
watershed)
: Diesel Fuel - 60 to 120 minutes
Jet Fuel - 50 to 70 minutes
99144ba2.v8
37

<<<PAGE 367>>>

The leak detection equipment will be installed prior to startup. The
computational based system will be adjusted to become operational over
approximately the first two weeks of pipeline operation and be further optimized
within 6 months of startup. The sensor-based system will be fully operational, at full
sensitivity, immediately upon startup. Leak detection capabilities will be
demonstrated and periodically tested."
UTSI International is Longhorn's third party leak detection consulting firm. Correspondence
describing leak detection system development and design is included in the Phase Two
Project Documentation Appendix at Tab 11, as are qualifications of the UTSI personnel
directly involved in system development and design. System shutdown is achievable
without field communications due to the fact that the SCADA system gives remote control
of all relevant system components to the pipeline control center in Tulsa.
The leak detection system software will not be inoperable during the fine-tuning period;
rather, it will be adjusted to its operating status over approximately the first two weeks, and
further optimized over as much as six months from startup. The sensor-based system over
the Edwards Aquifer recharge zone and Slaughter Creek watershed in the contributing
zone will be fully operational, at its full sensitivity, immediately upon system startup.
Emergency Response Preparation - Emergency Response Plan
The Williams System of Manuals contains an Emergency Response Plan volume, a copy of
which is included in the Phase Two Project Documentation Appendix at Tab 12. The
Emergency Response Plan provides direction to the employee first aware of an emergency
situation, including emergencies that involve a release of a transported commodity. The
priority for protection in the event of an emergency is appropriate: (1) human health and
safety; (2) the environment; and (3) property. Among the first duties of the first aware/first
responder role is to activate the applicable facility response plan (FRP; aka OPA '90 Plan).
A copy of the most recent draft of the Longhorn FRP (March 24, 2000) is hereby provided
as a separate Appendix; as development is completed, the final FRP will be provided to the
Service.
Oil Pollution Act of 1990 Facility Response Plan
Longhorn developed and distributed an FRP in 1998 and submitted same to DOT for
review and comment. The Settlement Stipulation that arose out of the NEPA lawsuit,
however, contained DOT's agreement that it would not approve, or allow Longhorn to
commence operations under, the FRP until the conclusion of the EA process. The FRP
was scrutinized during the
EA, and Longhorn committed to develop numerous
enhancements to the FRP as listed in this Phase Two BA at Section 3.4. The Service also
provided comments to enhance response capability over the EARZ/EACZ.
The FRP enhancements will serve to protect the environment as a whole, and listed
species and habitat in particular, as well as human health and safety. The LMP contains a
number of commitments to enhance the FRP, and those enhancements have been
developed and implemented to the extent possible:
99144ba2.v8
38

<<<PAGE 368>>>

•
Ensure maximum 2-hour full response to EA designated sensitive areas and
maximum 1 to 2 hours in hypersensitive areas (LMC 23)
Establish a response center in South Austin (LMC 23)
•
Enhanced facility response plan will:
-
Address firefighting in areas without Hazardous Materials response units
(LMC 24)
-
Provide detailed planning for areas with high populations of potentially
sensitive receptors (LMC 26)
-
Establish consistency with
the City of Austin Barton Springs Oil Spill
Response Plan and the Service's Barton Springs Salamander Recovery Plan
(LMC 28; these enhancements depend upon promulgation by the City of
Austin and the Service of their respective plans, neither of which has occurred
at this writing)
The EA took into account listed species and potential habitat when identifying areas to
designate as sensitive and hypersensitive (see Section 3.1, above). Thus, the FRP
benefits that are directed to sensitive and hypersensitive areas also are directed
at species
and habitat; see EA at Section 9.2.3 and Appendix 9C.
The development of a new
response center, to be located in south Austin, will limit the elapsed time between
notification of response personnel and implementation of a full response at any release
site. Longhorn will stage personnel and equipment to achieve a full response in sensitive
areas in less than two hours, and in one to two hours in hypersensitive areas. A response
time of 1 hour will prevail for the Edwards Aquifer recharge zone and Slaughter Creek
watershed in the contributing zone. A maximum 1 to 2 hour response time will apply in the
Barton Creek watershed in the contributing zone. More detailed, site-specific planning and
preparation will enable more rapid and more effective deployment on-site. Sensitive and
hypersensitive areas are interspersed along the pipeline route, with non-designated areas
between; therefore, segments between sensitive and hypersensitive areas benefit from
much the same treatment by virtue of proximity (See Longhorn FRP at Volumes II and III,
Sections 4 and 5). Stated another way, a Tier I area located near a Tier II or Tier III area,
or located between two areas of either Tier Il or Tier Ill status, will by definition be within the
reach of response crews within the same time periods stated above for sensitive (Tier II)
and hypersensitive (Tier III) areas.
Emergency Response Activities
The following paragraphs describe generally the sequence and character of activities that
occur at a pipeline release location. Each potential release would likely involve unique
circumstances, and, among other factors (see APR Companies, Phase Two Project
Documentation Appendix at Tab 10), the on-site response will vary with location, terrain,
weather conditions, product released, and release volume. The area of disturbance
caused by a response action varies depending upon the character of the response and by
nature of the release. The following description identifies the majority of typical response
activities.
The first responder(s) will immediately notify Longhorn Operations Control and the Area
Manager. They will take appropriate action to protect life and ensure safety of personnel.
They will additionally request Operations Control to notify the appropriate emergency
responders. Operations Control will coordinate company response activities until company
99144ba2.v8
39

<<<PAGE 369>>>

personnel arrive on scene.
When a leak is detected, Operations Control will shut down the pipeline following
procedures in the Operations Control Manual. Remote operated valves upstream of the
release will be closed and downstream valves may be closed or left open to allow drainup,
depending on conditions. The Longhorn First Responder assumes the role of Longhorn
Incident Commander (IC) until relieved. The Longhorn IC will work in cooperation with the
local emergency responders (reference Longhorn Emergency Response Plan from the
System of Operating Manuals).
Responders will conduct a preliminary assessment of the situation including potential health
and safety hazards. If someone is injured or if there is the potential for a fire or explosion,
emergency services will be called out. Assistance from public agencies for site control and
evacuations will be requested if necessary. Proper monitoring will be conducted to ensure
public and personnel safety, and that the necessary spill response contractors have been
mobilized to assist in containment and cleanup operations. Response contractors are
currently identified in the FRP Volume I, Section 8 and within each county-level response
zone plan (Volumes II and III). All or a portion of additional resources will be activated, as
necessary. For a major release, all resources may be activated. Appropriate regulatory
agencies will be notified.
Potentially affected sensitive areas will be identified. The designated Tier II and Tier I!
areas are identified on the strip maps in FRP Volumes || & III, Section 4. Additional
information on the Wildlife Sensitive Areas is located in Section 5 of Volumes || & III. The
topographic maps also locate sensitive features along and down gradient from the pipeline.
Any response activities will involve measures to protect the sensitive areas.
If there is the
potential to affect the Wildlife Sensitive Areas, the biological contractor will be included as
part of the response team.
A request for assistance to have potential ignition sources in the vicinity of the spill,
including motors, electrical pumps, electrical power, etc. shut down will be made. Local fire
departments and/or Boots & Coots, Eagle Environmental, or other release response
contractors will be notified if the use of fire suppressants is required. Longhorn responders
will shut down and control the source of the spill. This may include closing additional
valves, collection of pooled product at the pipeline location, digging out the pipeline,
collection of product from the pipeline and the pipeline ditch, and repair of the pipeline.
Longhorn responders will stabilize and contain the situation in coordination with appropriate
agencies. This may include berming, the deployment of containment and/or sorbent
booms, construction of dams, or trenching in a manner that limits the spread of the product.
The tactic used is dependent upon many factors including the location, the volume, type of
sensitive areas, weather, and similar factors. General response tactics are discussed in
the FRP at Volume I, Section 3. Site-specific tactical plans for selected sensitive areas are
located in Section 4 of Volumes II and III. Access points and possible response strategies
are identified in the tactical plans. The pre-identified access points were chosen on the
basis of calculations of worst case transport times, proximity to existing roads and other
access, and suitability for use. Within the Edwards Aquifer recharge and contributing
zones, multiple response locations with associated tactical plans have been identified along
the Barton, Slaughter and Williamson Creek watersheds in the event a release were to
99144ba2.v8
40

<<<PAGE 370>>>

reach a stream or tributary and potentially be transported toward the recharge zone. (see
LBG-Guyton, "Travel Times for Hypothetical Releases from Longhorn Pipeline within the
Pipeline Replacement Corridor in Austin, Texas," 2000 in the Project Documentation
Appendix). Additional access points may be utilized during an actual response. If indicated,
wildlife protection measures will be initiated.
Product recovery and removal operations will be initiated. This may include recovery of
free product from ground surface, water or trenches using vacuum trucks, skimmers or
sorbents. Excavation of contaminated soil may be utilized. In situ methods such as
biological treatment or controlled burns may be considered. Any technique used will
attempt to minimize disturbance to the environment. Additional information on recovery
techniques is located in Volume I, Section 3 of the FRP. All necessary approvals must be
obtained from applicable resource trustees.
Documentation procedures will be initiated. Documentation of all response actions taken,
including notifications, agency and media meetings, equipment and personnel mobilization
and deployment, and area impacted will be made. Spill tracking and surveillance
operations will be initiated. The extent of pollution may be determined via surveillance
aircraft. In the event of subsurface impacts, cave monitoring or water well monitoring may
be utilized. Photographers and/or videographers will be utilized.
The equipment and personnel required for a response are dependent on the specific
release situations. The volume, location, and the unique site characteristics will affect the
necessary resources. Some of the equipment such as transport vehicles, temporary
storage or tank trucks may be located at a staging area rather than at an active work site.
Site-specific resources are identified in the tactical plans within the FRP.
In general the major resources that may be utilized at the pipeline release response
location may include:
Vacuum Trucks (one or more at each recovery site depending on leak volume);
:
Trackhoe or backhoe for pipeline dig out;
Dirt moving equipment may include an additional backhoe or bulldozer and dump
trucks for containment and recovery operations;
Spill response trailer;
Sorbent Material;
•
Tanker Trucks and/or temporary storage;
•
Welder's Truck (for pipeline repair);
•
Boom Truck (for pipeline repair);
Miscellaneous transport vehicles;
Roll offs or drums for contaminated debris; and
•
Fire suppressant material if necessary.
Species Habitat Areas
Longhorn has implemented additional levels of planning and preparedness in the FRP
99144ba2.v8
41

<<<PAGE 371>>>

since September 1999. Human health and safety must take precedence during the
execution of an emergency response. If a release occurs within habitat, or at any location
where the release could adversely affect species or habitat, Longhorn will employ additional
measures to avoid any potential adverse effects to species or habitat. To do so, Longhorn
has incorporated into the FRP maps depicting areas of potential habitat both adjacent to
the pipeline and along pipeline sections from which a release could adversely affect
species or habitat. Longhorn also has identified numerous pre-planned containment and
recovery locations throughout the Edwards Aquifer recharge zone and the contributing
zone. Further, Longhorn has included in its FRP training regimen for emergency response
personnel the information necessary to identify such areas and prioritize response activities
toward such areas. Habitat areas along the pipeline have been mapped, and the maps
have been incorporated into the FRP along with descriptions of response actions that apply
in those areas (See Longhorn FRP at Volumes Il and III, Sections 4 and 5).
In addition, Longhorn will immediately engage a qualified biologist on-site to provide
direction to response personnel if a release location is near an area of potential habitat.
Personnel will be directed to avoid indirect effects such as traversing habitat areas to gain
site access.
They also will employ site and circumstance-specific measures to protect
species and habitat threatened by a release and thereby avoid adverse effects; for
example, were a release to ignite in Bastrop County, fire-fighting efforts would identify and
give heightened protection to habitat areas near the fire (see Buescher State Park Fire
Response Resources, in the Project Documentation Appendix).
Longhorn acknowledges the value of Service expertise in protecting species and habitat.
As such, Longhorn solicits Service participation in emergency response planning and
preparedness training with respect to species and habitat protection. Longhorn invites
Service participation in response training at response drills and table-top exercises.
Longhorn shall notify the Service of such training exercises, provide the Service an
opportunity to review and comment upon preparation for the training, and invite Service
participation during such training.
3.5
Edwards Aquifer Protections
The Edwards Aquifer in Travis and Hays Counties is a valued resource. In addition, the
Barton Springs Salamander, which resides in several spring outlets of the Edwards Aquifer,
is an endangered species that must be protected. Longhorn will implement a multitude of
measures both to ensure that the quality and integrity of the aquifer is preserved, and to
ensure the continued survival of the salamander. See document entitled Edwards Aquifer_
Protections, in the Project Documentation Appendix, which summarizes the various
protections.
Longhorn will implement conservation measures to avoid the possibility of impacts to the
aquifer that could result from a pipeline release over the recharge zone or upon the
contributing zone, should ever one occur. However, the Service has requested an analysis
of the potential effects if released product were to enter the aquifer.
Longhorn will implement a number of pipeline enhancements, including (a) replacement of
the pipe over the recharge zone and the contributing zone with new thicker-walled pipe; (b)
additionally protecting the new pipe with a reinforced concrete barrier; (c) installation of an
99144ba2.v8
42

<<<PAGE 372>>>

enhanced, sensor-based leak detection system through the recharge zone and the
Slaughter Creek watershed in the contributing zone; (d) installation of additional check
valves; and (e) daily inspections of the ROW (See Section 3.5.2). An extremely sensitive,
sensor-based leak detection system will complement a computational-based leak detection
system; jointly the systems will be capable of rapidly identifying potential small and large
leaks. Daily patrols will identify potential threats to the pipeline, and enhanced emergency
response capability will provide for rapid and effective release response.
Longhorn has commissioned thorough analyses of the Edwards Aquifer recharge zone and
contributing zone by experienced hydrogeologists, geologists, and biologists (See resumes
of Sherrod, Kreitler, Russo, Stein, Miller, Dorsey and Gasch, Phase Two Project
Documentation Appendix at Tab 13). The subsurface along the pipeline traverse of the
recharge zone has been studied by ground-penetrating radar, and subsequent
investigations demonstrated the absence of significant voids along the pipeline (See LBG-
Guyton letter to Vince Murchison dated 10 December, 1999, Phase Two Project
Documentation Appendix at Tab 14). The related topography has been mapped, and
surface drainage tendencies have been modeled. Local infrastructure has been surveyed
and analyzed to determine the potential implications to infrastructure components in the
unlikely event of a pipeline release; for example, roadways would interrupt the flow of a
hypothetical release that resulted in surface flow. Storm water detention ponds in and
around Austin receive detailed response planning.
Analysis of areas along the pipeline traverse of the recharge and contributing zones has
identified locations where the capacity of the pipeline trench to retain fluid could be
exceeded. Longhorn first will backfill the trench with fill that has been sized to result in high
porosity, which will have the effect of increasing the capacity of the trench to retain fluid if
any is released from the pipeline. At an estimated 18 locations at lower elevations,
however, the capacity of the trench could be exceeded if worst case discharge volumes are
used with the assumption of complete pipe drainage. At those locations, Longhorn will
install a berm containment system that has been designed both to contain any product that
may reach the surface and to prevent storm water accumulations that could compromise
the capacity of the containment systems. Those containment systems are described in the
analysis entitled "EARZ/EACZ Pipeline Replacement Trench and Berm Product
Containment Conceptual Design," "Response to Lead Agency Review of Conceptual
Design for Trench and Berm Product Containment for the EARZ/EACZ Longhorn Pipeline
Replacement," and "Response to USFWS' draft letter of 8/26/00," all of which are included
in the Project Documentation Appendix. Included with the conceptual design are diagrams
of the containment systems.
The containment systems will be constructed with
hydrocarbon-sensing valves that allow the passage of storm water but automatically close,
without human intervention, if hydrocarbons contact the valve.
Another preventive conservation measure Longhorn will employ is the installation of check
valves over the Edwards Aquifer recharge zone and over the contributing zone. The check
valves will be located in a manner that reduces potential volumes that could drain from the
pipeline in the event of a breach.
Check valves are one-way valves that allow product within the pipeline to flow in the
intended direction, i.e., downstream in the pipeline. However, check valves prevent flow in
99144ba2.v8
43

<<<PAGE 373>>>

the opposite direction, upstream, such that if for any reason product attempts to flow
backward, the valve closes to preclude flow in the upstream direction. A hypothetical
example illustrates the function of a check valve. If one assumes a pipeline breach on an
incline such that the pipeline flow is uphill, the contents of the pipeline could drain out of the
breach due to the forces of gravity. If one then assumes that a check valve was installed
along that incline (downstream on the pipeline), then the check valve would stop the
backward, downhill flow of the product from the pipeline, effectively reducing the volume of
product that could drain from the breach (gravity is not the only force to be factored into the
potential for draindown, as discussed below).
The check valves that Longhorn will install will be located to achieve just such effect. The
valve over the recharge zone will be placed at approximately milepost 171.5, near the
pipeline intersection with Whiteworth Loop in the Sendera Glen subdivision, which is
downhill of a gradual rise in the land surtace to the west. By being located near a low point
of the pipeline traverse of the recharge zone, the check valve will prevent the potential for
draindown of product from the check valve to a point approximating the western edge of the
recharge zone.
The valve over the contributing zone will be located at the existing
Edwards Aquifer West Valve, approximately milepost 175.5, about 2.1 miles east of U.S.
290 and about 1.8 miles west of the boundary of the recharge zone. Again, this valve is
located below a moderate incline to the west and will reduce the potential draindown
volume of a release between the two check valves. See APR report, Phase Two Project
Documentation Appendix at Tab 10.
Concerns have been raised by various parties, Longhorn opponents included, to the effect
that a breach in a pipeline allows all product in the pipeline between adjacent block valves
to drain out, but such is not the case. The California State Fire Marshall's office has
analyzed pipeline release volumes to determine the extent to which various components of
release volume contribute to total release volume (see Phase Two Project Documentation
Appendix at Tab 15). The analysis determined that draindown contributes only marginal
volumes to a release. Of the releases studied, in only 25% of the cases did the total
release volume exceed 4.5% of the potential draindown of the pipeline, while in just 10% of
the cases did the total release volume exceed 28% of the potential draindown. Among the
reasons for low draindown volumes is that for product to flow out of the pipeline, it must first
be displaced by air, similar to the manner in which water flows from a bottle that is turned
upside down. See APR Companies, Phase Two Project Documentation Appendix at Tab
10. Longhorn has calculated full line draindown for hypothetical releases to the east of the
recharge zone check valve described above; that volume is 3,875 barrels (162,750
gallons). However, if one applies the lessons of the California State Fire Marshall risk
assessment that volume is more realistically calculated as 1,147 barrels (48,174 gallons) at
28% draindown and 841 barrels (35,322 gallons) at 4.5% draindown. Despite the findings
of the California State Fire Marshall risk assessment, Longhorn has designed the bermed
areas described above using the assumption that all product escapes from the pipeline
segment affected by a release.
Using those more realistic assumptions, the potential threat to the Barton Springs
Salamander from a pipeline release in such areas is lower than previously understood.
Calculations of the effect of a release over the aquifer recharge zone performed by LBG-
Guyton (see Phase Two Project Documentation Appendix at Tab 16) demonstrate that the
potential for adverse effects to the salamander is greatly reduced. See Section 4.4 of this
99144ba2.v8
44

<<<PAGE 374>>>

BA and LBG-Guyton, Phase Two Project Documentation Appendix at Tab 16.
Nonetheless, Longhorn's conservation and mitigation measures will make it unlikely that
adverse effects to the aquifer will occur.
3.6
Pipeline Maintenance Construction
This section identifies
and describes incremental pipeline maintenance construction
activities, in addition to those that were the subject of the Phase One BA, that will be
implemented in two specific areas: (a) within Houston toad habitat in Bastrop County; and
(b) across and adjacent to the Edwards Aquifer recharge zone within Austin. Additional
maintenance construction will include planned, but unscheduled construction and future
additional, but currently unforeseen construction. Maintenance construction that occurs
outside the two presently identified areas will be subject to the maintenance construction
procedures described in the Phase One BA, as will maintenance construction in Houston
toad
habitat and the Edwards Aquifer recharge zone; however, this BA contains
descriptions of additional conservation measures that Longhorn will implement during the
maintenance construction activities over the Edwards Aquifer recharge zone.
The maintenance construction procedures referred to herein, and presented in detail in the
Phase One BA, are identified below:
1.
Pipeline Maintenance -- Construction Planning
2
Project Environmental Inspectors
3.
Site Preparation
4.
Site Entry
5.
Pipeline Lowering and/or Replacement - Open Terrain
6.
Pipeline Lowering and/or Replacement - Creek Crossing
3.6.1 Buescher State Park
Maintenance construction
activities planned within Buescher State Park (containing
Houston toad habitat) result both from the EA process and from Longhorn commitments to
reduce risks to species and habitat. The EA related project is the replacement of 671 feet
of pipe at mile post 127.94 (Hunt Branch) within Buescher State Park in Bastrop County,
Texas. Longhorn committed in the LMP (LMC 34) to replace the pipe since data on file at
the time indicated that the segment contains several shorter sections of Grade B pipe.
Longhorn has since identified file documentation that demonstrates that the existing pipe is
adequate for the design pressure; however, Longhorn remains willing to replace the pipe to
limit the potential for surge pressure-related damage and thus lower the risk of a release in
this habitat area. Two additional tasks have been identified to reduce the risk of a release
in Houston toad habitat: (a) lowering and replacement of the pipeline crossing of Dry
Branch in Buescher State Park (pipeline mile post 128.33); and (b) lowering and
replacement of the pipeline crossing of an unnamed creek approximately 1360 feet east of
the 671-foot replacement (pipeline mile post 127.72).
See additional engineering
information at Tab 17 of the Phase Two Project Documentation Appendix.
The three projects significantly reduce the potential for damage to the pipe in and near the
three creeks. Since land development does not occur within the state park, and taking into
99144ba2.v8
45

<<<PAGE 375>>>

account the pervasiveness and effect of the EA mitigation measures that focus on
identifying and preventing corrosion, on eliminating material defects, and on preventing
adverse consequences resulting from operator error, the greatest threat to the pipeline is
outside force damage within the creek beds. For a complete discussion of the risk
reduction realized by the creek crossing replacements, see APR Report (Phase Two
Project Documentation Appendix at Tab 10). Further, the replacements will limit the
potential volume of a release, should one occur, since the thicker and higher-grade new
pipe will be least likely to suffer a breach, by serving as low-point catchments for product
within the pipe that could escape if a release occurred at lower elevations.
The new creek crossing replacement pipe will have 0.375" wall thickness and be of
American Petroleum Institute Grade X56 or better. The burial depth of the pipe will be
determined on the basis of regulatory requirements (49 C.F.R. § 195.248) and site
conditions such as type of stream bed material and basin and channel configuration; the
pipe will be buried below a depth that would allow in-stream forces to pose a threat to
pipeline integrity.
3.6.2 Edwards Aquifer Protections
During informal consultation on the Longhorn Pipeline Project, the Service voiced concerns
about the pipeline crossing of the Edwards Aquifer recharge zone and the potential for
adverse effects to the Barton Springs Salamander. Adverse effects to the salamander may
be associated with water quality degradation within the aquifer (See Barton Springs
salamander listing final rule at Tab 18 of the Phase Two Project Documentation Appendix).
Typically, water quality degradation originates at the aquifer recharge and contributing
zones and is largely associated with residential and commercial development and the
creation of impervious cover. In addition, commercial and industrial operations and
vehicular roadway traffic create the potential both for chronic water quality degradation as a
result of ongoing activities and for acute water quality degradation in the event of a release
of deleterious materials to the watershed.
System operation and ongoing, long-term maintenance of the pipeline are not likely to
result in adverse effects to the salamander, for which critical habitat has not been
designated. ROW maintenance, pipeline inspection, valve maintenance, and similar such
activities are unlikely to result in adverse effects to the salamander inasmuch as the
activities are implemented in a manner that does not affect aquifer water quality.
Longhorn responded to the Service's concerns about water quality by identifying measures
that will not only reduce the potential for a pipeline release, but will protect water quality
and promote public efforts to ensure the survival of the species in the unlikely event of a
release that threatened the Barton Springs segment of the Edwards Aquifer. Longhorn
committed to implement the following measures and included the measures in its
Environmental Assessment mitigation commitments:
Replacement of over 3 miles of pipe over (and east of) the recharge zone and 15
miles of pipe over the full extent of the contributing zone with new, thicker walled
pipe (LMC 3).
•
99144ba2.v8
Installation of an enhanced, sensor-based leak detection system across the aquifer
46

<<<PAGE 376>>>

recharge zone and the Slaughter Creek watershed in the contributing zone to
complement the pipeline-system-wide computational-based leak detection system
(LMC 13).
Installation of check valves (one in the recharge zone and one in the contributing
zone) to minimize the volume of a potential release should one occur (see Section
3.3, Edwards Aquifer Protection).
Performance of daily pipeline surveillance patrols over the recharge zone (LMC 20).
Establishment of a refugium and captive breeding program for the Barton Springs
Salamander as a conservation measure to ensure the survival of the species in the
event of any perturbation to the extant population (LMC 33).
Further in response to concerns voiced by the Service, and concerns voiced also by the
Barton Springs/Edward Aquifer Conservation District, Longhorn will implement an additional
measure to reduce the risk of a release that could adversely affect water quality. Longhorn
commits to install a protective concrete barrier over the 5-foot-deep replacement pipe. The
barrier will be engineered with reinforced concrete to provide a protective covering over the
pipeline that will alert an errant excavator to the presence of the pipeline. The concrete will
be colored red to ensure ready notice of the presence of a protected structure. The
protection offered by the concrete barrier will provide further reduction of a threat to the
pipeline, third party damage, in the developing areas of south Austin, southwestern Travis
County, and northeastern Hays County (See additional information at Tab 19 of the Phase
Two Project Documentation Appendix).
Analysis of the pipeline traverse of the recharge and contributing zones has identified areas
where surface flow modeling indicates a tendency for surface flow toward known karst
features or toward Slaughter Creek, Barton Creek or Williamson Creek (see LBG-Guyton,
Phase Two Project Documentation Appendix at Tab 16 and associated figure). Those
areas include (a) from the fire station west of Brodie Lane to Deer Lane, toward the Karst
Preserve; (b) from the pipeline crossing of Deer Lane to a point just east of the Sendera
Creek. LBG-Guyton has recommended that measures be employed to divert surface flow
from those features, with the result that in the event of a release that results in surface flow,
the features and thus the Edwards Aquifer will not be subject to the potential for rapid
infiltration to the aquifer; see LBG-Guyton, Phase Two Project Documentation Appendix at
Tab 16.
Longhorn commits to employ such measures. Given the relatively low slope of surface
topography across the recharge zone, slight modifications during final surface grading will
accomplish the goal of protecting the sensitive features. Thus, planning for construction of
the replacement pipe will include the requirement that, during final grading, a low swale or
berm be created to protect those features. The precise location and design of these
surface flow control features are not easily predictable in advance of construction; thus,
Longhorn's geological, biological, and engineering consultants (LBG-Guyton, Horizon ESI,
Paragon Engineering, Bury + Partners) will make field recommendations to the contractor
as reclamation begins. These recommendations will be carried out by the Contractor at the
47

<<<PAGE 377>>>

direction of the on-site Environmental Inspector. Since the Longhorn Pipeline primarily
traverses the surface divide between the Williamson and Slaughter Creek drainage areas,
little if any surface flow of storm water will be affected, and no adverse effect to aquifer
recharge water quantity will occur.
Additional analysis has been performed with respect to the recharge and contributing
zones.
Surface flow modeling has identified surface flow tendencies along the pipeline,
and the calculations have been made of time of travel, to the recharge zone or recharge
features, of a hypothetical release under worst case stream flow conditions. See Drawing
199044-C2 and LBG-Guyton, "Travel Times for Hypothetical Releases from Longhorn
Pipeline within the pipeline Replacement Corridor in Austin, Texas," 2000 in the Project
Documentation Appendix. Longhorn has based its emergency response planning on the
results of those analyses, resulting in the multiple pre-planned response locations identified
in the Travis County and Hays/Blanco sections of the FRP. Multiple pre-planned response
locations enable response personnel to identify the optimum response locations for a
release along any segment of the recharge and contributing zones.
Longhorn also has identified locations across the recharge and contributing zones at which
a release of product could fill the trench and reach the surface. At those locations,
Longhorn will construct a bermed area that achieves two competing goals: (1) providing
containment in the unlikely event of a release that reaches the surface; and (2) preventing
the infiltration of storm water to the areas (which could otherwise compromise containment
capacity). The areas will be constructed of berms and swales along and/or across the
pipeline right-of-way. Storm water will be prevented from entering the bermed areas by the
placement of diversion berms. The presently identified locations of potential surface
presence of product, and the conceptual design of the bermed areas, is set forth in the
"Longhorn Pipeline EARZ/EACZ
Pipeline Replacement Trench and Berm Product Containment Conceptual Design" in the
Project Documentation Appendix (note that locations #1 and #20 are outside the applicable
replacement segment).
Longhorn will execute replacement of the pipe section that crosses the recharge zone
pursuant to a maintenance construction plan that does not include the segment across the
contributing zone (See Tabs 20 and 44 of the Phase Two Project Documentation
Appendix). Pipe replacement across the contributing zone shall be executed pursuant to
typical project construction plans developed during the Phase One consultation (but
including the sealing of identified karst features in the limestone trench; see additional
details in the following paragraphs).
Longhorn also has committed to replace an additional one-half mile (approximately) of pipe
east of the recharge zone. That area has been identified through surface flow modeling as
susceptible to seeing surface flows toward the recharge zone and Williamson Creek. All
new pipe will be buried to a depth of 5 feet to top of pipe and will be protected by a red
concrete barrier. This segment of the project
will be executed pursuant to project
construction plans containing the same protections as those developed pursuant to Phase
One of this consultation.
99144ba2.v8
48

<<<PAGE 378>>>

The maintenance project will employ numerous measures in excess of the maintenance
construction procedures described in the Phase One BA, identified specifically and by
qualified individuals and entities (See Phase Two Project Documentation Appendix at Tab
13 for resumes of Kreitler, Stein, Sherrod, Bury, and Miller) as protective of the Edwards
Aquifer and thus the salamander. The procedures build upon a solid base of construction
storm water best management practices (BMPs) that are implemented at every
construction site; moreover, Longhorn will implement procedures at least as stringent as
locally prescribed construction BMPs. Longhorn will design its construction project to
employ the construction BMPs promulgated by the Texas Natural Resource Conservation
Commission (TNRCC) for application during construction over the recharge zone.
During pipeline replacement, Longhorn will seal any identified karst features in the
limestone trench or exposed in the ROW following guidelines established by TRCC.
Upon encountering any karst feature during construction, the Contractor and on-site
Environmental Inspector will be required to immediately notify Longhorn's geological,
biological, and engineering consultants (Sherrod, Miller, Kreitler, Stein, Bose, Bury - see
resumes in Phase Two Project Documentation Appendix at Tab 13) who will promptly
inspect the field situation and prescribe proper sealing methods to the contractor.
_In
addition, immediate notice will be made to appropriate representatives of the City of Austin
and the Barton Springs/Edwards Aquifer Conservation District who may also provide
additional recommendations to Longhorn's specialists on proper sealing procedures. If
exceptionally large or deep voids or caverns are encountered, structural engineering
specialists will provide engineered recommendations for supporting the pipeline over the
void closure (example engineered recommendations encountered
20 and 44 of the Phase Two Project Documentation Appendix ). All void closure
recommendations will minimize potential adverse effects to the function of the void (ie.,
recharge capability or faunal habitat) while providing the maximum seal from the pipeline
and any potential releases. Not only does this address potential issues of impacts to
species during construction, but also provides significant aquifer protection and product
recovery benefits in the event of a release during operation. Pipeline releases should stay
within the pipeline trench and at land surface within the ROW where they can be more
easily contained and controlled.
First, the volume of a spill will be limited by the installation of check valves that reduce spill
volume to a probable maximum of 2100 barrels in the recharge zone. Additionally, the
APR report (Tab 10 of the Phase Two Project Documentation Appendix) concludes that
only about 28% of the line fill capacity between block valves might be released in 90% of
the release scenarios. Third, the topography across the recharge zone is relatively flat, and
rapid runoff away from the ROW will not likely occur; see LBG-Guyton Addendum Phase
Two Project Documentation Appendix at Tab 16. It is anticipated that with the flat terrain
and limited spill volume, potential product spills will remain on the ROW of the pipeline
where any caves and other karst features will have already been identified and been sealed
or protected during pipeline replacement.
Longhorn has, however, committed to implement a number of bermed containment areas
at locations where it is possible that product could reach the ground surface, and
accumulate, in the event of a release (see Sec. 3.5). The bermed areas are designed so
that any released product is captured within the trench and is captured if it rises to the
99144ba2.v8
49

<<<PAGE 379>>>

surface. The bermed areas also are designed to prevent storm water infiltration by run-on
and to shed storm water through outlets; however, the systems will collect product in the
event of a release by means of automatic, hydrocarbon sensing valves. These systems will
be designed and built of low-porosity materials but with the integrity to withstand major
storm events. The capacity of the bermed areas will be calculated to contain both a worst
case release (assuming complete pipe segment drainage) and precipitation generated by a
100-year storm event. Periodic inspection of the locations will be performed in conjunction
with regularly scheduled pipeline surveillance patrols.
Longhorn commits to perform a field test of both the trench sealing procedure and the berm
construction methods in conjunction with the maintenance construction project over the
recharge and contributing zones.
If the field test identifies design or construction flaws,
adjustments to design or construction techniques will be employed to achieve the desired
effect. See "Proposal to Perform Field Tests to Verify the Design and Construction of the
Pipeline Trench and Berms for the Longhorn Partners Pipeline over the Edwards Aquifer
Recharge Zone in Austin, Texas," in the Project Documentation Appendix.
As a result of the foregoing measures, the following defenses protect the Edwards Aquifer:
1.
New, thicker pipe; 2. Five foot burial depth;
3.
Concrete barrier;
4.
Enhanced leak detection;
5.
Sealing of all voids, fissures, vugs, and other potential recharge features in the
limestone trench;
6.
Trench backfill absorption enhancement;
Surface containment systems and berms; and
Enhanced response planning.
As described in Section 4.3 below, that risk will be further reduced by implementation of the
Edwards Aquifer Protection Plan during construction.
3.7 Hydrostatic Pressure Testing And Proof Testing
Longhorn committed to perform hydrostatic pressure tests and proof tests of the pipeline,
and those tests have proceeded during 2000. (See Phase One BA at Sec. 4.10 and LMP
Items 1 and 2.) Hydrostatic and proof testing of the pipeline has been ongoing, beginning
at the Longhorn GATX pump station in Galena Park (Houston) and proceeding westward to
Crane Station, but skipping the segments through Houston toad habitat in Bastrop County
and the Edwards Aquifer Recharge Zone in Travis County (refer to Phase One BA in the
Phase Two Project Documentation Appendix at Tab 1).
The hydrostatic and proof testing has occurred in segments, which were subdivided into
test sections of varying lengths. Due to sensitive aquatic species concerns, the Houston
toad and the Barton Springs Salamander, two test sections were not tested during the
overall Houston to Crane testing project. Those two sections are (a) Segment 4, Section 1,
which encompasses habitat for the endangered Houston toad and (b) all of Segment 5,
which encompasses eastern Travis County, the recharge zone of the Edwards Aquifer and
part of the adjacent contributing zone, areas of concern to the endangered Barton Springs
99144ba2.v8
50

<<<PAGE 380>>>

Salamander. Those sections will be hydrostatic pressure tested, after completion of Phase
Two consultation and after pipe replacement takes place, to complete the system integrity
testing.
Procedures for testing will follow those described in the Phase One BA. However, due to
the heightened sensitivity of these two locations, project environmental inspectors and spill
response equipment will be onsite and in constant ready status for immediate response
during the testing. Makeup water for the tests will originate from the Colorado River or from
local sources, and other than the potential for small amounts of residual diesel no
contaminants are foreseen in the test water. Since most of the tested line sections will be
newly installed pipe and since the prior hydrostatic testing will have flushed the pipe that is
not slated for replacement, significant contaminants are not expected to be present in the
test water. New pipe is expected to contain minimal manufacturing residue.
3.8 Right-of-Way Maintenance
ROW maintenance was considered by the Service in Phase One of this consultation with
the exception of one area, the Edwards Aquifer recharge zone; see Phase Two Project
Documentation Appendix at Tabs 1 and 2. ROW maintenance in the recharge zone will be
conducted in the same manner as described in the Phase One BA. In summary, the
conservation measures described in the Phase One BA are designed to prevent
disturbance of the earth, to preclude sedimentation, and to prevent the release or
distribution of herbicides to the environment.
3.9 Corrosion Inhibitor
The LC-50 concentrations of Magnacide 575 in the water column for freshwater fish and
aquatic invertebrates ranges from 19.4 ppm (ml/I) (Daphnia- 48 hr) to 119 ppm (mg/l) (trout -
96 hr). Reproductive capacity diminution in Daphnia was demonstrated to have an EC-50
of 0.154 ppm (ml/l). No-effect concentrations for this product on fish and aquatic
invertebrates was not available. LC-50 concentrations for dermal exposure to terrestrial
mammals (rabbit) is 2000 ppm (mg/kg).
Surface disturbance for the application of the corrosion inhibitor would be restricted to the
seven valve setting sites previously noted. Access to those sites would be from public
roads.
The mixture ratio for the proposed inhibitor in the pipeline is approximately 3500 to 4000
ppm. These concentrations exceed the LC-50 for aquatic organisms, and are also above
the lethal levels for terrestrial organisms. A release of this product in a surface tributary
stream could be toxic until such time as dilution in the water body reduces the toxicity
below limits.
99144ba2.v8
51

<<<PAGE 381>>>

For listed species, the risk is believed to be very minimal. Terrestrial plants such as the
Texas prairie dawn, Navasota ladies-tresses, and Tobusch fishhook cactus have very
minimal exposure risk as spilled product on the ground would either be confined very
quickly to topographically low areas or absorbed into the soil in a short distance from the
pipeline. Surveys conducted for these plant species along the Longhorn ROW (Report of
investigations - in progress) by Horizon in response to the requirements of the LMP did not
reveal the presence of any individuals of these species within or near the ROW.
The Houston toad would also be unlikely to be exposed to a spill if one occurs in Houston
toad habitat areas. During the late summer period when the activity is proposed to occur,
Houston toads are generally in estivation in deep sand burrows in uplands. Exposure to
spilled product would be extremely low probability. Additionally, Houston toad surveys
were conducted along portions of the line passing through the designated critical habitat for
the Houston toad.
No toads where found to occur within or adjacent to the ROW, or
downstream (report in preparation).
The only exposure avenue for the Barton Springs salamander would be entry of a large
volume of the corrosion inhibitor directly into the Edwards Aquifer through a point recharge
feature; however, the risk of a release of the corrosion inhibitor is demonstrably nominal as
discussed in the following paragraphs.
That the risk of a release of the inhibitor is low is based upon the fact that the inhibitor
treatment water will be moved through the pipeline at pressures significantly lower than the
pressure reached during the recently completed hydrostatic tests. The inhibitor will be
propelled by nitrogen injected at a maximum pressure of 285 pounds per square inch
gauge ("psig"). At the point of the inhibitor water batches, the pressure will range from
approximately 65 psig to 140 psig. In comparison, the hydrostatic tests induced pressures
ranging from approximately 1,100 psig to over 1,500 psig. Further, though some segments
were not tested
(22 miles across Buscher State Park in Bastrop County and 40 miles across the Edwards
Aquifer recharge and contributing zones in Travis and Hays Counties), the hydrostatic test
water was moved through those segments, and none was lost.
The following table compares the minimum hydrostatic test pressures to the maximum
treatment pressure.
Corrosion
Ratio
Hydrostatic
Inhibitor
Hydrostatic
Segment/Section'
Minimum(psig)?
Test
Maximum(psig)3
Treatment
Inhibitor
Test to
2(1802+63 - 4024+50)
1265.0
285
4.4
3 (4024+50 - 5964+47)
1113.0
285
3.9
4-1 (5964+47 - 7110+81)
6504
285
2.3
4-2 (7112+16 - 8004+00)
1113.0
285
3.9
99144ba2.v8
52

<<<PAGE 382>>>

Hydrostatic
Corrosion
Inhibitor
Ratio
Segment/Section'
Minimum(psig)?
Test
Treatment
Hydrostatic
Maximum(psig)
Inhibitor
Test to
5 (8004+00 - 10163+00)
500°
285
1.8
6 (10163+00 - 12039+37)
1235.0
285
4.3
7 (12360+00 - 14597+72)
1265.0
285
4.4
8 (14606+00 - 16992+40)
1113.0
285
3.9
1
Segments shown are those with threatened or endangered species or
habitat in proximity to the pipeline.
The pressures shown are test target pressures for segments actually
tested; all target pressures were met during the test.
Nitrogen will be injected at 285 psig and therefore is used as the
maximum; the pressures at the inhibitor batches will be lower, on the order of 65 to
140 psig;
This section was not hydrostatic tested, but experience pressures as
high as 650 psig (nitrogen) while adjacent sections were tested.
This segment was not hydrostatic tested, but experienced pressures
as high as 500 psig (nitrogen) while adjacent segments were tested.
The above data demonstrate that treatment pressures will be significantly lower than
were the hydrostatic test pressures. Since the hydrostatic test pressures were of such
higher magnitude, and since the pipeline has been repaired at the few locations of
hydrostatic test failures, the risk of a release is extremely low. In addition, regular,
ongoing pipeline surveillance is monitoring activity near the pipeline to protect from third
party damage that could threaten pipeline integrity.
Furthermore, Longhorn will take measures to prevent a release of the inhibitor to the
environment. Piping and materials management protocols that will be implemented serve
to ensure that the inhibitor is controlled at all times. Nonetheless, spill equipment and
supplies necessary to contain and immediately remove a release will be maintained along
the pipeline segments as the treatment procedure progresses westward. Finally, a
biologist will be maintained on stand-by during treatment across Bastrop, Travis and Hays
Counties, in the event of a release that could affect the Houston toad or the Barton Springs
salamander, to immediately advise response crews in release response and mitigation.
Therefore, no adverse affects to the Barton Springs salamander would be expected.
Exposure possibilities for the golden-cheeked warbler or black-capped vireo would be
Studies for the presence of the warbler and vireo in the springs of 1999 and 2000 along the
ROW did not reveal the presence of either bird species within or in close proximity to the
ROW (report in progress).
All ground activity associated with this process would be at previously disturbed valve
setting locations, none of which are within or near listed species habitat.
99144ba2.v8
53

<<<PAGE 383>>>

The recently completed hydrostatic testing has proven the Longhorn Pipeline to be sound.
The corrosion inhibitor solution would be pumped through the pipeline at significantly lower
pressures than the hydrotest. Little handling of material is required for the procedure. The
risk of a significant spill or release of the inhibitor material in the environment is extremely
low. Even if released, exposure or toxicity of the solution would not be significant for any of
the listed species.
99144ba2.v8
54

<<<PAGE 384>>>

4.0
AVOIDANCE AND CONSERVATION MEASURES
4.1
Avoidance
Longhorn will conduct pipeline operation, maintenance, construction, testing, and other
subject activities in a manner that avoids potential effects to species and habitat. Controls
and other measures designed to achieve that goal are described in the foregoing
descriptions of the various activities.
A number of those controls and measures are
summarized as follows:
•
Full implementation of the Longhorn Mitigation Plan;
•
Identifying and marking habitat areas for avoidance;
• Planning project implementation to avoid the potential for any effects;
• Using FERC qualified environmental inspectors with authority to alter
project
implementation procedures in areas of potential concern to species, including
application of incremental BMPs as a result of site-specific conditions;
Adjusting project timing to avoid breeding populations; for example, maintenance or
construction projects in Houston toad habitat will avoid the months of January
through June and projects in golden-cheeked warbler and black-capped vireo habitat
areas will be avoided from March 1 through August 1 and March 15 through
September 1, respectively;
Implementing storm water pollution control BMPs even when not required by permit;
Maintaining qualified
biologists in hydrostatic test project areas for immediate
response in the event of a test water release in a habitat area;
Avoiding work in areas of noise-sensitive species (i.e., golden-cheeked warbler and
black-capped vireo) during the breeding/nesting season. If work must occur in
habitat areas during noise-sensitive seasons, the Service will immediately be notified
for additional avoidance procedures.
Longhorn's Monitoring Commitment
Longhorn has committed to survey the existing ROW to determine the presence/absence of
listed species. The following summarizes the Longhorn Monitoring Commitment for each
potentially affected species.
•
Longhorn has completed surveys for the Texas prairie dawn within the potentially
suitable habitat areas to confirm its presence or absence. The surveys were
conducted within the ROW in areas identified as potential habitat in early April of
2000 to determine if the Texas prairie dawn was present, and if so, its distribution
and abundance. No prairie dawn were found, nor was any highly suitable habitat
99144ba2.v8
55

<<<PAGE 385>>>

identified.
Longhorn will conduct a fall survey (15 October to 15 November, 2000) for the
Navasota ladies'- tresses within the ROW if suitable climatic conditions occur to
determine the presence or absence of this species, and if present, its distribution
and abundance.
For the Tobusch fishhook cactus, Longhorn has conducted a blooming period survey
(late February 2000) within the ROW throughout Kimble County to determine the
species' distribution and abundance. No cacti were observed.
• A spring survey for the Houston toad in Buescher Park was conducted along and
downstream of the pipeline to determine the presence or absence of toads and their
overall distribution and abundance. No toads were detected in the park.
•
One to two additional Spring breeding season surveys (as acceptable to the Service)
will be conduced for the golden-cheeked warbler along and adjacent to the ROW
within the potential habitat areas to determine habitat utilization and overall
distribution
and abundance.
A survey for 2000 was conducted with no golden-
cheeked warblers being found in or near the ROW.
•
One to two additional spring breeding season surveys (as acceptable to the Service)
will be conduced for the black-capped vireo along and adjacent to the ROW within
the potential habitat areas to determine habitat utilization and overall distribution and
abundance. A survey for 2000 was conducted with no black-capped vireos being
found in or near the ROW.
4.2
Status of the Species/Environmental Baseline
The following is a review of the status of each species being considered in this biological
opinion that may be adversely affected by the proposed action. The Service has reviewed
the list of threatened and endangered species and identified potential impacts to the
following species.
Texas prairie dawn (Hymenoxys texana) - The Texas prairie dawn is a small, delicate
annual to 6 inches tall with single or branching stems. It has small yellow flowers blooming
in late March to early April. It occurs in sparsely vegetated areas of fine-sandy compacted
soil. Specifically, the species occurs in the northern part of the Gulf Coastal Prairie in
Harris and Fort Bend counties, where it is found in poorly drained depressions or saline
swales around the periphery of low, natural mounds (mima mounds) in open grasslands.
These mostly barren areas are sparsely vegetated, and the soil is often covered with a
blue-green alga (Nostoc sp.). It can also occur on disturbed soils such as rice fields,
vacant lots, pastures, and possibly pipeline ROW if the soil structure remains relatively
intact.
99144ba2.v8
56

<<<PAGE 386>>>

Kimble
Hudspeth
Hays
•
Gillespie
ich occur. in counties traversed by Longhorn Pipeline
Fayette
Ector
Page 1 of 2
Cootert
Federally-listed Threatened or Endangered Species
Blanco:
RAD 39117
Species - Federal Classification
American alligator: TSA
Atwater's prairie-chicken - E
Bald eagle - T(PDL?:
Barton Springs salamander « Ei
Ber Creek Cave harvestman E
Bik-cooped vireo E
Bone Cave harvestman E
Clear Creek sambusia - E
Comal Springs dryopid beetle - E
Somal Springs diffle beetle - E
Comanche Springs pupfish • E
ild-buckwheat-T
Devil's River Minnow. T
rican spotted owe Te
Footh Gave

<<<PAGE 387>>>

Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
M - Migrant Not Likely to be Adversely Affected
ce of Species: US Fish and Wildlife Service
PE - Proposed to be Listed as Endangered
FEDERAL CLASSIFICATION
PDL - Proposed to be De-listed
E - Listed Endangered.
T - Listed Threatened
Ward
Waller
TABLE 4
Federally-listed Threatened or Endangered Species which occur in counties traversed by Longliorn Pipeline
Upton
Page 2 of 2
000z
Schleicher
Reeves:
zOoO
Reagan
Menard
Mason
RAD 39118
Speciei - Federal Classificacion
low flycatcher - E
Smerkan Filigator - TSA
Atwater's prairie-chicken • E
bald eagle - T(PDL):
Barton Springs salamander • E
Bee Creek Cave harvestman: E
Black capped vireo •E
Bone Cave harvestman - E
Clear Creek gambusia: E
Comal Springs dryopid beetle • E
Coral Springs riffle beetle • E
Comanche Springs puplish • E
Devil's River Minnow - T
Fountan darter: E
Solden-cheeked warbler - E
m wild-buckwheat. T
eschmar Cave mold beetle - E:
Tooth Cave pseudose
ooth Cive spider - E:
a crane -E

<<<PAGE 388>>>

There are fewer than 35 known sites recorded for the species, and several have been lost
in recent years to urbanization in the Houston area. Most populations remaining are small,
and are on private land. Very few sites currently have any form of protection. The primary
threat to the species is habitat destruction as a result of urbanization, roadway construction,
and conversion of habitat for agricultural purposes.
An assessment of potentially suitable habitat for the Texas prairie dawn was conducted by
Horizon in early June 1999 along the Longhorn pipeline ROW in western Harris and
eastern Waller counties from the Satsuma Station on the west edge of Houston to near
Monaville in Waller County. Three areas along the ROW, one in Waller County and two in
Harris County, exhibited native range conditions with suitable soils that could be considered
potentially suitable habitat areas for the prairie dawn. All other areas along the pipeline
within the area investigated had been converted to row crop (corn), monoculture hay or
grazing pasture, or disturbed for land development. A survey for the prairie dawn has been
conducted within the potentially suitable habitat areas during early April 2000 with negative
results.
Navasota ladies'-tresses (Spiranthes parksii) - The Navasota ladies' tresses was listed
as endangered on May 6, 1982, without critical habitat. This member of the orchid family
occurs primarily in moist, sandy soils in small openings in post oak savanna vegetation.
The species is known to occur in Brazos, Burleson, Fayette, Freestone, Grimes, Jasper,
Leon, Madison, Robertson, and Washington counties (USFWS 1984b).
Currently, approximately 149 sites have been recorded, representing perhaps 75-80
distinct population areas, predominantly concentrated around two centers of distribution,
one in southern Brazos County and one in central Grimes County. Some of these recorded
sites have been damaged or destroyed since they were reported.
Together these
population centers contain the majority of known sites and individuals (Wilson 1993).
However, the majority of sites contain fewer than 25 recorded plants. It is known that for
this species not all individuals in a population are visible above ground in a given year, and
most of these sites have been visited only once, so demographic data on populations is
very limited. Nevertheless there is great concern among botanists that most of these sites
may not represent viable populations.
Navasota ladies'-tresses occur in a variety of moist sandy soils near drainages, in the Post
Oak Savannah vegetation associated with the Navasota, Brazos, and Trinity River
watersheds. Navasota ladies'-tresses are typically found on erosional remnants between
rills in slightly to moderately eroded areas along minor intermittent tributaries, from the
upper drainage head, extending along the edges of temporary streams to the flood plain of
permanent streams. Navasota ladies-tresses grow on sandy loam soils and are often
associated with post oak, blackjack oak, yaupon, slender bigelowia (Bigelowia nuttalli), and
Spiranthes cernua. Typical habitat consists of natural openings in upland Post Oak
Savanna vegetation (Poole and Riskind 1987, USFWS 1984b, Wilson 1993). Plants are
believed to be situated where subsurface flow or seepage of water occurs seasonally, a
common feature in other species of the genus (Arft and Ranker 1995, Kathy Parker, pers.
comm.). While Navasota ladies'-tresses is found in small naturally created openings in the
post oak woodlands, it cannot be regarded as a disturbance species, as it usually occurs in
99144ba2.v8
59

<<<PAGE 389>>>

well developed woodland and is not a colonizer of extensively disturbed areas. There are
few records in flood plain forests, open savannahs and shrublands that have experienced
little or no grazing pressure, and in hillside seepages.
Navasota ladies'-tresses is extremely slow-growing and long-lived. Rosette leaves support
the formation of a storage tuber between November and March that sequesters resources
in preparation for sending up a leafless bloom stalk at some future time. It is believed that
often plants require more than one year of photosynthate storage to successfully send up a
bloom stalk. If local conditions have not been favorable for forming sufficient below ground
reserves, the plant may not bloom (Wilson 1993).
Navasota ladies'-tresses apparently does not transplant well. In a mining project in Grimes
county by Texas Municipal Power Association (TMPA), plants in the impact area were
removed and transplanted into an adjacent habitat area. Plant survival has been low in
most sites (TMPA 1996). Similarly, in an experiment in Lick Creek Park near College
Station, Dr. Hugh Wilson planted some seedlings which survived into their second season,
but died prior to the third growing season (Wilson 1993).
Because of the low numbers of individuals reported from populations, the slow growing
nature of the plants, its unusual habitat requirements of openings in mature vegetation, and
its sensitivity to disturbance and transplanting attempts, the species is not regarded as
being very resilient, and recovery following any damage to a population is expected to be
slow.
The primary threat to Navasota ladies'-tresses is destruction or modification of habitat due
to urbanization, clearing for agricultural production, or mining (47 FR 19539, USFWS 1995,
1984b). Destruction of understory by feral pigs is also a problem in some areas. More than
40 known sites have been lost in the last ten years to mining or urbanization. Post oak
savannah in many of these counties continues to be converted to bermuda grass pasture.
Subsequently, habitat loss continues, particularly in the areas of Brazos and Grimes
counties where most sites are located. The City of College Station in Brazos County is
growing rapidly, particularly in the southern and southeastern fringes where most known
populations are located. Mining in Grimes County disturbs more than 7,000 acres every 5
years (Wilson 1993).
In Fayette County, the species is known from one small population approximately 6 miles
south of the pipeline and 2 miles north of the town of Fayette. Based on analysis of soil
distribution, vegetative cover, physiographic setting, and field assessment by Horizon in
November of 1999, two small areas of potential habitat for Navasota ladies'-tresses are
present along the pipeline corridor. Surveys for the species are scheduled to be conducted
along the pipeline in October 2000 if suitable climactic conditions occur.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii) - Tobusch fishhook cactus is a
rounded, biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5 inches in diameter.
There are 3 to 5 central spines with the upper 2 to 3 erect and straight and the lower central
spines hooked at the tip and spreading. The plants are very inconspicuous, and produce
cream to yellow flowers from February through early April. These cacti have been
demonstrated to be obligate outcrossers pollinated by native bees with a foraging distance
of about 1/4 mile, and seeds are dispersed by native ants.
99144ba2.v8
60

<<<PAGE 390>>>

Currently about 50 sites are recorded for the species, following a recent range-wide
representative survey. Most of the populations are extremely small (5-20 plants), with
individuals widely scattered. Known sites are separated by large distances. Most existing
populations are on private land, and there are very few protected sites. Demographic data
collected in monitoring studies over the last five years or so show that only one of the
known populations is even marginally viable. The species is extremely slow growing and
does not appear to reproduce until 10-17 years of age. It takes four successful
flowers/fruits to produce one seedling (Jackie Poole, Texas Parks and Wildlife, pers.
comm.). It is estimated that very few viable populations (10-15) remain over the 8 county
range of the species. The survival and recovery of the species will require restoration and
careful management, to provide sufficient numbers of populations and individuals in
effective proximity to each other for successful pollination (and gene flow) to ensure the
continuity of the species.
Studies examining the probable reasons for population declines are underway. Threats to
the species are believed to include inappropriate timing of range management practices
(such as fire and clearing practices that disturb the soil), extensive predation by beetle
grubs, loss of habitat to
real estate development, and some collection by cactus
enthusiasts.
An assessment of potentially suitable habitat and pedestrian survey for the cacti was
conducted by Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble
County, and no specimens were observed within the ROW. However, one Tobusch
fishhook cactus was observed about 50 feet north of the cleared ROW. An additional
survey of the entirety of the ROW through Kimble County was conducted by Horizon in late
February 2000 with negative findings for the cactus. However, as a conclusion of the
Phase One consultation, in the absence of complete surveys at that time, all of the ROW
within Kimble County was considered as potentially suitable habitat and fully compensated.
Golden-cheeked Warbler (Dendroica chrysoparia) -The golden-cheeked warbler is a
small, migratory songbird, 4.5 to 5 inches long, with a wingspan of about 8 inches. The
male has a black back, throat, and cap, and yellow cheeks with a black stripe through the
eye. Females are similar, but less colorful. The lower breast and belly of both sexes are
white with black streaks on the flanks. Typical nesting habitat is found in tall, dense,
mature stands of Ashe juniper (cedar) mixed with trees such as Texas (Spanish) oak,
Lacey oak, shin (scalybark) oak, live oak, post oak, Texas ash, cedar elm, hackberry,
bigtooth maple, sycamore, Arizona walnut, escarpment cherry, and pecan.
This type of
woodland generally grows in relatively moist areas such as steep-sided canyons and
slopes. A mix of juniper and deciduous trees on the slopes, along drainage bottoms, and in
creeks and draws provides ideal vegetation for birds. Warblers are also occasionally found
in drier, upland juniper-oak (i.e., live oak, post oak, blackjack oak) woodlands over flat
topography.
99144ba2.v8
61

<<<PAGE 391>>>

An assessment of potentially suitable habitat and surveys for the golden-cheeked warbler
was conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from
Austin, Texas, to the Mason/Kimble County line. Although no potentially suitable habitat
areas were observed within the Longhorn ROW, several areas were located adjacent to the
previously cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5
times during April and May on days with favorable weather conditions for bird activity, per
U.S. Fish and Wildlife Service guidelines (USFWS, 1994a). Surveys were conducted on 8,
9, 12, 27, 28 April, and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres were
spent at each site, based on habitat size. No golden-cheeked warblers were found to be
utilizing any of the potentially suitable habitat areas on or immediately adjacent to the
ROW. However, three years of survey are necessary to confirm presence/absence under
Service guidelines (USFWS 1994a). Additional surveys for the warbler are under way for
the Spring of 2000.
Black-capped Vireo (Vireo atricapillus) -The black-capped vireo is a 4.5 inch long,
insect-eating songbird. Mature males are olive green above and white below with faint
greenish-yellow flanks. The crown and upper half of the head is black with a partial white
eye-ring. The iris is brownish-red and the bill black. The plumage of the female is duller
than the male. Females have a dark slate gray head. In Texas, vireo habitat is found on
rocky limestone soils of the Edwards Plateau, Cross Timbers and Prairies, eastern Trans-
Pecos, and, to a limited extent, on igneous soils in the Chisos Mountains. Black-capped
vireos require shrub vegetation reaching to ground level for nesting cover. They typically
nest in shrublands.
An assessment of potentially suitable habitat and surveys for the black-capped vireo was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from
Austin, Texas to Crane County. Potentially suitable habitat areas were observed within the
Longhorn ROW as well as several areas located immediately adjacent to the previously
cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5 times during
April and May on days with favorable weather conditions for bird activity, per Service
guidelines (USFWS, 1994a). Surveys were conducted on April 8, 9, 12, 27, 28, and May 3,
11, and 19. An equivalent of 4 person-hours per 100 acres were spent at each site, based
on size. No black-capped vireos were found to be utilizing any of the potentially suitable
habitat areas on or immediately adjacent to the ROW. However, three years of survey are
necessary to confirm presence/absence under Service guidelines (USFWS 1994a).
Additional surveys for the vireos are under way for the Spring 2000.
Bald Eagle (Haliaeetus leucocephalus) -The bald eagle is a migrant and winter resident
in Texas. The bald eagle was recently down-listed from endangered to threatened due to
successful conservation efforts and is now proposed for de-listing. Migrating and wintering
bald eagles typically arrive in Texas in November and depart around February. They are
found primarily in association with reservoirs, rivers or other large bodies of water where
they feed on fish, carrion, and waterfowl. Nesting bald eagles in Texas are found in the
eastern portion of the state and along the coastal plain as far south as Calhoun and
Refugio counties. No bald eagle nests have been identified near the pipeline ROW,
however, bald eagles may occur along major waterways (Brazos and Colorado rivers, or
major tributaries with impoundments) downstream of the pipeline corridor. The Federal
Register, (Volume 64 No. 128, Tuesday, July 6, 1999; Page 36454) contains a proposed
rule to remove the bald eagle from the List of Threatened and Endangered Wildlife in the
99144ba2.v8
62

<<<PAGE 392>>>

Lower 48 States of the United States. Formal delisting is now anticipated to occur in July
2000.
Interior Least Tern (Sterna antillarum athalassos) - Premier nesting sites for the interior
least tern are salt flats, broad sandbars, and barren shores along wide, shallow rivers.
Important breeding habitat characteristics include: (1) presence of bare or nearly bare
ground and alluvial islands or sandbars for nesting; (2) availability of food (primarily small
fish); and (3) favorable water levels during the nesting season (so nests remain above
water). They usually nest on sites devoid of vegetation, but have been found in areas with
an average of 11 to 30% vegetative cover, composed of grasses, shrubs, and trees and
ranging from 1 to 3 feet in height. Vegetation, if present, is usually located well away from
the colony, with the exception of bugseed, eastern cottonwood, and sandbar willow. As
natural nesting sites have become sparse, birds have used sand and gravel pits, ash
disposal areas of power plants, reservoir shorelines, gravel levee roads, and other
manmade sites. The typical nesting period for the least tern in Texas is mid-April to mid-
August.
While the interior least tern has not been documented along the pipeline corridor, potential
habitat for the tern is present downstream of the pipeline along several major waterways
including the Brazos, Colorado, Llano, and James Rivers, and Squaw, Beaver, and Sandy
Creeks.
The seasonal occurrence (Spring and Summer) and potential nesting of least
terns is possible in these areas.
Barton Springs Salamander (Eurycea sosorum)- The Barton Spring Salamander was
listed as endangered in 1997, without critical habitat. The Barton Springs Salamander
belongs to a group of related salamanders that are endemic to the Edwards Plateau region
of central Texas. All members of this group are obligately aquatic because the adults retain
the larval, gill-breathing morphology throughout their lives.
The Barton Springs
Salamander, formally described in 1993, was first collected from Barton Springs in 1946
and has been found only at the four hydrologically connected outlets of Barton Springs in
Zilker Park within the City of Austin (Brune, 1981; Chippindale et. al., 1993). This
salamander is a small species, adults reaching 2.5 inches (about 68 mm) in total length
with reduced eyes and elongate, spindly limbs indicative of a semi-subterranean lifestyle.
Barton Springs Salamanders are found in the flowing, thermally constant water issuing from
the spring outlets in association with aquatic macrophytes, leaves and organic debris, and
gravel and rock substrates having little silt and sediment deposition. Water from the
contributing and recharge zones of the Barton Springs segment of the Edwards Aquifer
influences the conditions at Barton Springs. The main threat to the species has been
identified as degradation of water quality from future growth and development on the
Barton Springs segment of the Edwards Aquifer (Federal Register 62:23385). An
expanded discussion of the environmental baseline for the salamander is provided in the
Project Documentation Appendix at Tab 22.
Houston Toad (Bufo houstonensis) - The Houston toad was listed as endangered in 1970
(Federal Register, October 13, 1970) and Critical Habitat was designated in Bastrop and
Burleson counties in 1978 (Federal Register, January 31, 1978). Houston toads are
generally brown and speckled, although individual toad coloration can vary considerably.
Some may appear light brown, others almost black and they may also have a slightly
reddish, yellowish, or greyish hue. Two dark bands extend down from each eye to the
99144ba2.v8
63

<<<PAGE 393>>>

mouth. Their legs are also banded with darker pigment. A variable white stripe streaks
along the sides of the toad's body. Their undersides are usually pale with small, dark
spots. Males have a dark throat which appears bluish when distended. Adult Houston
toads are 2 to 3.5 inches long and like all toads, are covered with raised skin patches that
contain chemicals that make the toad distasteful and sometimes poisonous to predators.
The toad was eliminated from three counties (Harris, Fort Bend, Liberty) prior to the 1970s
due to habitat loss resulting from urban expansion. Although Houston toad populations
have been found in nine other counties (Austin, Bastrop, Burleson, Colorado, Lavaca, Lee,
Leon, Milam, Robertson), the Service is concerned about the long-term viability of these
populations. The small population in Lavaca County has not been seen since its discovery
in 1991; the population at the critical habitat site (Woodrow Lake) in Burleson County has
not been seen since 1983; and the population in Leon County lies within an expanding
residential area. The largest known population of Houston toads occurs within the pine/oak
woodland region of Bastrop County. This area also contains federally designated critical
habitat.
All known Houston toad populations occur along bands of geologic formations that support
deep sands. Six populations occur on a band running through Bastrop County northeast to
Freestone County. Three other populations occur on another band through Lavaca, Austin,
and Colorado counties (USFWS, 1994b). Houston toad habitat consists of rolling uplands
characterized by pine and/or oak woodlands (loblolly pine, post oak, blackjack or sandjack
oak) underlain by pockets of deep, sandy soils. Because their skin is semi-permeable to
water, Houston toads become dormant to escape harsh weather conditions, such as winter
cold (hibernation) and drought (estivation). They seek protection during this time by
burrowing into sand or hiding under rocks, leaf litter, logs or in abandoned animal burrows
(TPWD, 1993). Although Houston toads are typically associated with woodland habitat,
they also breed in and migrate across sparsely wooded and cleared areas near woodlands.
They may also breed in and traverse areas that do not support deep sandy soils, including
clay and gravel substrates, provided these areas are near woodlands underlain by pockets
of deep sandy soils.
Houston toads breed from January to June, with a peak in February and March. During the
breeding season, toads appear to move randomly from one breeding site to another,
achieving genetic transfer between populations that may appear isolated, thus creating a
metapopulation, an aggregation of
smaller
populations linked genetically
demographically and functioning almost as a single population. Presently, the most reliable
breeding sites are stock ponds and similar impoundments, though in wet years breeding
may occur wherever sufficient standing water is present.
For successful breeding, water
must persist for at least 30-60 days to allow egg hatching, tadpole maturation, and
emergence of toadlets. Mortality in young is high, due to predation and drying of breeding
sites, with significantly less than one percent of eggs laid believed to survive to adulthood
(USFWS, 1984a, 1994b, 1995).
The Houston toad is vulnerable to extinction primarily due to habitat loss, degradation, and
fragmentation. Over the last 50 years, the historic range of Houston toads has contracted
and
several populations have been lost. Threats include expanding urbanization and
conversion of woodlands to agricultural production areas, such as coastal bermuda
pastures, use of fertilizers and pesticides that impact the toad directly or its food supply,
99144ba2.v8
64

<<<PAGE 394>>>

and loss of suitable breeding habitat because of alterations in watershed drainages and
wetland alterations or destruction (such as degraded water quality, draining/filling of
wetlands, stocking with predatory fish, etc.).
Since Phase One of the Longhorn Pipeline project involved the continuation of
maintenance activities rather than new clearing or development, and minimization of these
continuing maintenance activities included long-term habitat protection for the Houston
toad, the
• Service concluded that Phase One of the project would provide a net
conservation benefit for this species. According to the Houston Toad Recovery Plan
(USFWS 1984a), Houston toad breeding sights have been recorded in Buescher State
Park south of Longhorn Pipeline. Houston toads have also been heard chorusing on the
adjacent property owned by the University of Texas to the north of Buescher State Park
and Longhorn Pipeline (USFWS, unpublished data). Dr. James R. Dixon of Texas A&M
University conducted a survey along the Longhorn Pipeline ROW and adjacent Phillips EZ
Pipeline ROW in 1991 with negative results, although areas of potential habitat were noted
(Horizon 1991).
Horizon Environmental Services, Inc. conducted a reevaluation of suitable habitat along the
Longhorn Pipeline ROW within Bastrop County. The field reconnaissance was conducted
on 2 June 1999 from the Colorado River, southeast of Bastrop, to FM 2104. Portions of the
area along the pipeline had recently been cleared and planted in improved grasses. Based
on field observations and discussions with the Service, two areas of suitable habitat were
identified along and adjacent to the pipeline ROW. One area includes Buescher State Park
from approximately 0.5 mile east of the eastern boundary of the park westward to near
Highway 71. The second area begins about 500 feet to the west of FM 2104 and extends
westward approximately 0.75 mile. The drainages in both of these areas flow south toward
the Colorado River. A breeding season survey of the habitat areas in Buescher State Park
has been conducted by Horizon during February and March of 2000 with negative results.
Comanche Springs Pupfish (Cyprinodon elegans) - The Comanche Springs pupfish
seldom exceeds 2 inches in total length. It is gray-green above and pale yellow to white
below, with clear to light orange fins. The sides are silvery white with blue-black blotches
forming a "stripe" along the side (often faint on the male). Males have black speckling on
the side and a black edge on the caudal (tail) fin.
Historically, this pupfish occurred in 2 separate spring systems of the Pecos River
drainage.
One was Comanche Springs, with headwaters (now almost always dry) within
the city limits of Fort Stockton, Texas, and the other was a group of springs near
Balmorhea. The pupfish population at Comanche Springs were extirpated (lost) when the
springs first went dry in 1955. At present, the species occurs primarily in aquatic habitat fed
by springflow from Phantom Lake, Griffin, and San Solomon Springs near Balmorhea,
Texas. The Longhorn Pipeline is not within the sub-watersheds of these springs where the
pupfish occur and groundwater contamination from product releases that would affect the
springs is extremely unlikely (Dr. Charles Kreitler, personal communication). Therefore,
this species is not likely to be adversely affected, but is addressed herein for information
purposes only.
Pecos Gambusia (Gambusia nobilis) - The Pecos Gambusia is a small (2-inches long),
live-bearing fish with a dark lateral stripe and a metallic gray-blue color. Females have a
99144ba2.v8
65

<<<PAGE 395>>>

black area on the abdomen that surrounds the anal fin and anus. The anal fin of males is
modified into a gonopodium, a tube-like structure used in fertilization of the female.
Historically, the Pecos Gambusia was restricted to the Pecos River basin in southeastern
New Mexico and western Texas. The species occurred from as far south as Fort Stockton,
Texas to as far north as Fort Sumner, New Mexico. The populations of Pecos Gambusia
that once existed at Leon Spring and Comanche Springs were lost when these springs
went dry during the mid-1950s.
Presently in Texas, populations of the Pecos Gambusia
occur near Balmorhea in aquatic habitat supported by springflow from Phantom Lake,
Griffin, San Solomon, and East Sandia Springs. A substantial population also occurs in
Leon Creek and in Diamond-Y Spring outflow north of Fort Stockton. The species also
occurs in a limited number of locations in New Mexico. The Longhorn Pipeline is not within
the sub-watersheds that support the Pecos Gambusia and groundwater contamination that
would affect any of the spring habitats is extremely unlikely (Dr. Charles Kreitler, personal
communication). Therefore, this species is not likely to be adversely affected, but is
addressed herein for information purposes only.
Devils River Minnow (Dionda diaboli) - The Devils River minnow is a small fish, with
adults reaching sizes of 1.0 to 2.1 inches standard length. The fish has a wedge-shaped
caudal spot and pronounced lateral stripe with double dashes extending through the eye to
the snout but not reaching the lower lip. The species has a narrow head with prominent
dark markings on scale pockets above the lateral line that produce a crosshatched
appearance when viewed from the top.
General habitat associations for Devils River minnow have been described as channels of
fast-flowing, spring-fed waters over gravel substrates. Although the species is closely
associated with the stream, rather than in the spring outflow itself.
The known historic range of the species includes the Devils River from Beaver Lake
downstream to near its confluence with the Rio Grande and four other tributaries of the Rio
Grande River not associated with the Devils River. The current distribution of Devils River
minnow is at 2 sites on the Devils River, 2 sites on San Felipe Creek, and 1 site on
Sycamore Creek (US Fish and Wildlife Service, 1998).
The Longhorn Pipeline ROW crosses the northern most extent of the Devils River
watershed, in excess of 100 river miles upstream from known populations of the minnow.
At this distance, it is unlikely that released product would reach the population areas of the
minnow in quantities to be toxic (James Miertschin, personal communication). This species
is also unlikely to be adversely affected, but is included herein for informational purposes.
Southwest Willow Flycatcher (Empidonax trailii extimus) - The southwest willow
flycatcher occurs in riparian woodlands along streams and rivers in Hudspeth, Culberson,
and El Paso counties. Specific localities of this species in the vicinity of the pipeline are not
known. It is possible this species could occur along the Pecos and Devil's rivers
downstream of the pipeline. This species would not likely be directly affected by any
activitiy associated with the pipeline. However, this species utilizes riparian woodlands that
could be affected by a major release of
product in a waterway. The methods for
assessment of such a potential, but unlikely, event are addressed in section 3.4.
99144ba2.v8
66

<<<PAGE 396>>>

4.3
Effects of the Actions
Pipeline Operation
Normal operation of the pipeline is not expected to result in any adverse effects to listed
species. There is a risk of an accidental release from the pipeline-a risk Longhorn has
significantly minimized through various pipeline mitigation measures.
Many of these
pipeline mitigation measures were developed directly as a result of consultation with the
Service, in order to significantly minimize the risk of a spill near listed species, such as the
pipe replacement in Buescher State Park and the replacement of 19 miles of pipe over the
Edwards Aquifer recharge and contributing zones. The occurrence of a pipeline release is
so unlikely as to be improbable; see APR report, Project Mitigation Appendix at Tab 10.
Recognized pipeline experts have concluded that the implementation of the LMP will
enable the Longhorn Pipeline to operate at the highest reasonable level of safety attainable
by current technology; see APR report at Tab 10 of the Phase Two Project Documentation
Appendix.
Kiefner & Associates, Inc. (Kiefner) performed an audit of the Longhorn pipeline segment
between Houston and Crane (Tab 23 in the Phase Two Project Documentation Appendix).
Keifner concluded that the pipeline was safe to operate, even prior to the EA, so long as
certain recommendations were followed. Longhorn has committed in the LMP to
implement all of Kiefner's recommendations. Kiefner further reported on the safety of the
pipeline system as it will stand after implementation of all EA pipeline mitigation measures.
Among Kiefner's conclusions:
Hydrostatic testing is the most important and positive way of proving that a pipeline
is fit for service; the 2000 hydrostatic and proof testing will remove any doubts about
the remote possibility that defects may have arisen since the 1995 hydrostatic test
•
After the pipeline is placed into service, better technology than hydrostatic testing
will be used to assure that no defect develops or grows in service to the point where
a service failure results
•
"Smart-Pig" technology will be utilized by Longhorn to locate and characterize
anomalies that may represent... time-dependent developing defects
Longhorn has taken the unprecedented step of committing to limit surge pressures
to no more than the maximum allowable operating pressure (MAOP) in sensitive and
hypersensitive areas... providing an extra margin of safety in the critical areas
Longhorn's pipeline surveillance programs will "go a long way" to preventing
excavation or construction activities from encroaching on the pipeline and possibly
damaging it
The new pipe in the Edwards Aquifer recharge zone "reduces the already low risk of
failure from corrosion and excavation damage," providing an extra margin of safety
• "The proposed operation of the pipeline does not create in my opinion, an
99144ba2.v8
67

<<<PAGE 397>>>

unreasonable risk"
See Kiefner & Associates, Inc., January 13, 2000, Phase Two Project Documentation
Appendix at Tab 23.
Further, APR Companies, a company that specializes in pipeline accident investigation, has
concluded that the Longhorn Pipeline will benefit from a significant reduction in release
probability; see Phase Two Project Documentation Appendix at Tab 10.
APR
(reference Tab 10 in the Phase Two Project Documentation Appendix) has
determined that the average probability of a release (1 in 1000 years per mile) is
significantly improved for the pipeline in general through implementation of the LMP with a
resulting 2 to 5 times reduction in spill probability. For the Edwards Aquifer recharge zone,
the likelihood of a release is reduced 5 to 10 times with implementation of extensive LMCs
for that area. A resulting probability for a release then becomes 1 in 5,000 to 10,000 years
per mile.
APR further estimates the potential worst-case spill scenario for the Edwards Aquifer
recharge zone. An earlier estimate approximated 5000 barrels of product released in a
major incident. Placement of a single check valve at or near mile post 171 within the
recharge zone limits the maximum line fill volume that could spill to 2088 barrels. However,
APR's analysis also takes into consideration other factors that influence line drain down
such as intervening topographic lows that will hold pipeline contents. Based on detailed
analysis of the topography along the line through the recharge zone, and average per unit
line drain downs from independent statistics, the probable worst-case spill volume would be
only about 1147 barrels in 90% of the potential spill scenarios and 841 barrels in 75% of
potential spill scenarios. Longhorn nonetheless has designed the replacement pipeline and
emergency response capability on the basis of unqualified worst case release volumes.
LBG-Guyton (reference Tab 16 in the Phase Two Project Documentation Appendix) has
developed a risk analysis for the Barton Springs Salamander based on the probable worst-
case spill volume combined with the measures to be implemented to prevent or minimize
released product entry to the aquifer, such as sealing voids in the pipeline trench and
grading surface drainage within the ROW to direct any surface flow away from identified
point recharge features. Bermed areas at lower elevations will serve to capture product
that reaches the surface in those low areas.
Their analysis concludes that product
concentrations that might reach the aquifer, and ultimately Barton Springs, would be on the
order of 0.2 to 0.002 ppb. Concentrations in the water column would be even less (in the
absence of MTBE; see Kreitler at Tab 16 and LMC 35). These levels are at nearly an order
of magnitude lower than measured levels of petroleum hydrocarbons found in the aquifer
and at Sunken Gardens Spring in the past (see Tab 22 in the Phase Two Project
Documentation Appendix).
Biotoxicological information assembled from existing literature and agency file sources for
salamanders (and other aquatic vertebrates), and their prey base (aquatic invertebrates),
indicate that concentrations of toxic product constituents (BTEX) in the water column in the
ppb range are generally below the "no effect" levels for most organisms (Horizon, 2000).
From the above analysis, levels of benzene reaching the springs would be in the 0.010 ppb
99144ba2.v8
68

<<<PAGE 398>>>

(ug/l) range, while toluene would be in the 0.014 ppb range. Horizon reports that EPA data
indicate acute toxicity to freshwater aquatic life, for benzene, occurs at about 5,300 ug/l
(ppb), while for toluene, the acute toxicity level is about 17,500 ug/ (ppb). The EPA
information notes that more sensitive species would have lower acute toxicity levels.
However, from the available information, concentrations reaching the springs under the
above scenarios would conservatively be several orders of magnitude lower than toxic
concentrations.
The LBG-Guyton analysis assumes that all or most of the probable worst-case spill volume
would reach the aquifer. From prior spill experience with the Longhorn (under previous
ownership) and Shell pipelines over the aquifer (1986 and 1987 incidents), 91 to 97 percent
of the spilled product (west Texas crude with a similar viscosity to some refined products)
was recovered at the surface. Those recovery volumes were in the absence of the void
sealing and surface contouring Longhorn will implement to further enhance product
recovery. Furthermore, modeling analyses by Rose (1986) and Ross (2000) indicate that
soil retention capacity of spilled petroleum product over the Edwards Aquifer recharge zone
would be in the range of 350 to 1600 barrels if spread over a 1 to 2 acre area with average
soil depth of 0.33 to 1.5 feet. This absorption capacity, combined with high evaporation
rates for refined products, and the potential for high levels of product recovery would
significantly, if not totally, reduce or eliminate the quantity of product that might reach the
aquifer, and ultimately Barton Springs.
The 1986 and 1987 incidents resulted in spills of 2245 barrels and 1139 barrels,
respectively (in the absence of a block valve). The 1986 spill resulted in hydrocarbon
fumes in caves in the vicinity, but no documented adverse effects to the salamander or the
aquifer. Under the above-described scenario of a probable worst-case spill for the
Longhorn Pipeline (with extremely low probability of occurrence), it is unlikely that adverse
effects to the salamander would result as a result of the enhanced Longhorn mitigation
measures.
In addition to those facets of system operation that limit potential consequences by
minimizing release volumes and ensuring a rapid and effective response to a release,
Longhorn's emergency response capability will be increased significantly through the LMP.
Longhorn will ensure a maximum response time (a) of 1 hour in the recharge zone and
Slaughter Creek watershed in the contributing zone; (b) in the Barton Creek watershed in
the contributing zone and in other EA designated sensitive and hypersensitive areas of 1
hour to 2 hours; Longhorn will provide for the establishment of a response center in Central
Texas, to be located in South Austin, to make certain that manpower and equipment is
always at the ready. Prior experience has demonstrated an average response time of 58
minutes (see Tab 24 in the Phase Two Project Documentation Appendix). Once on-scene,
the response crews will have
the advantage of thorough and detailed information relating to any area along the pipeline.
Longhorn has commissioned the preparation of detailed studies of numerous facets of the
pipeline ROW, and surrounding areas, to prepare its response crews in advance, if ever
necessary. The information developed and advantages gained as a result of the studies
includes the following:
Species habitat: Response personnel will have the information necessary to avoid
99144ba2.v8
69

<<<PAGE 399>>>

species habitat areas during response and prioritize protective activities in the event
of a release in or near a habitat area
• Topography: Advance knowledge of area topography allows advance planning for
both release drainage potential and control and capture locations
• Rivers and streams: Detailed planning has identified waterways at risk and
advantageous protective and control locations
• Water wells: Both public and private wells are mapped so that responders may
prioritize drinking water supplies for protection
• Known karst features: Particularly within the Edwards Aquifer recharge zone,
advance knowledge of karst features provides information that allows responders to
prioritize protection of the aquifer and thus the Barton Springs Salamander
•
Surface drainage potential: Flow modeling provides knowledge of the potential for
released product to flow overland, enabling responders to identify likely scenarios
relating both to habitat areas and to human health and safety issues; responders will
also have the ability to identify preemptive control and capture locations; surface
containment systems are designed to capture any release that reaches the ground
surface
Longhorn has synthesized this information into stand-alone maps (See Project
Documentation Appendix) and in its FRP; further, responders will be trained to use such
information during training and during table-top and live drills.
Where a potential release might affect listed species or habitat, the precise level of impact
cannot be predetermined due to the large number of variables at any given location. As a
result, any such attempt at prediction is likely to result in an inaccurate estimate.
Accordingly, Longhorn proposes to adopt a contingent methodology for calculating any such
effects. This methodology should be useful in the event there is a release from the Longhorn
pipeline but neither the Clean Water Act nor the Oil Pollution Act applies to the incident. In
such a case, and if Longhorn is liable for the damage, Longhorn will use the Habitat
Equivalency Analysis methodology to determine the amount of compensation for which
Longhorn is responsible.
Longhorn proposes using a methodology that is capable of assessing natural resource
damages, preferably the Habitat Equivalency Analysis (HEA) methodology developed by the
National Oceanic and Atmospheric Administration (NOAA). HEA is briefly described below.
A more detailed description of the HEA methodology is provided in Phase Two Project
Documentation Appendix at Tab 25).
Pursuant to the HEA methodology:
•
The duration and extent of injury are documented and estimated from the time of
injury until the resource recovers to baseline.
99144ba2.v8
70

<<<PAGE 400>>>

• The services provided by a compensatory project are documented and estimated
over the full lite of the project.
• The size of a compensatory project is calculated such that the total increase in
services provided by the compensatory project equals the total interim loss of
services due to the injury.
• The cost of the compensatory project is calculated.
Other methods exist for assessing natural resource damages under NOAA's regulations
governing Natural Resources Damages Assessments for oil spills pursuant to the Oil
Pollution Act of 1990 (OPA). 33 U.S.C. § § 2701 et seq. These methodologies may prove
more cost-effective than the HEA method and should be considered as well.
In the event of an accidental release from the pipeline in or near habitat for listed species,
an adverse effect could occur. The level of potential take is impossible to predict in
advance.
Long-term Maintenance
In general, most long-term maintenance is unlikely to result in any adverse effects to listed
species beyond those addressed in the Phase One consultation. The majority of long-term
maintenance involves ROW maintenance, above-ground facility upkeep, and periodic
pipeline testing. These activities were addressed in the Phase One consultation and
compensated accordingly. Certain maintenance activities may, however, require
construction or land disturbance beyond the existing ROW. Such events are not presently
determinable. In the event any such maintenance should necessitate access or
construction
within listed species habitat, the previously utilized Phase One BA
maintenance construction procedures (see
•Phase One BA in the Phase Two Project
Documentation Appendix at Tab 1) will be followed under the direction of FER qualified
environmental inspectors. To the extent feasible, all construction activity will be restricted
to the existing ROW within habitat areas, which was fully compensated during Phase One
of this consultation. If construction must exceed the ROW in an area of potential habitat,
the Service will be notified in advance and additional compensation, as required, will be
calculated and provided pursuant to the conditions set forth in the Phase One BA for the
given species, to the extent a specific location has not previously been compensated for
off-ROW impacts.
An additional area of potential Houston toad habitat has been identified in Austin County
since the Phase One consultation was completed. This habitat area is within the geologic
formation known to support two small Houston toad populations in Austin County
approximately 8 miles south of the pipeline corridor and other small populations in Colorado
and Lavaca counties further to the south. This area is characterized as patchy woodlands
approximately 3000 acres in extent surrounded and interspersed by improved grazing
pastures, and with marginally suitable soils (loamy fine sands less than 24 inches deep)
(SCS, 1984). The known populations of toads occur in the Catilla-Tremona soil association
which is comprised predominantly of sandy soils (SCS, 1984). The potential habitat area
99144ba2.v8
71

<<<PAGE 401>>>

occurs in the Tabor-Tremona-Chazos association which is comprised of loamy and sandy
which are not favorable for Houston toads (SCS, 1984). Surveys of this area for the
soils. The two associations are separated by several miles of clayey and clayey loam soils
Houston toad are not known to have been conducted in the past. A breeding season
survey is planned for spring of 2001. The pipeline ROW through this area traverses
approximately 12,000 linear feet (2.3 miles). The existing 50 ft wide ROW, therefore,
occupies 13.8 acres.
This area could be adversely affected by maintenance of the ROW
and is being addressed through the Phase One consultation.
Emergency Response
Potential impacts from an emergency response action could be highly variable depending
on location, season, site characteristics, spill characteristics, and type of equipment needed
to respond to a particular situation. Training of emergency response personnel will be
conducted to make them aware of species related issues, designated potential habitat
areas, and avoidance procedures. Avoidance of impacts will be achieved to the greatest
extent possible under any given emergency situation. However, control and containment of
a product release or fire will constitute a priority, and some level of impacts to designated
potential habitats could occur. Impacts could occur from clearing or grading to gain access
for emergency response equipment, building temporary containment structures outside of
the established ROW, or to remove contaminated soil and vegetation. If fire containment is
necessary, fire breaks may need to be dozed in advance of a fire. These activities could
result in direct or indirect impacts to potential habitat
Such impacts would be
assessed and mitigated in the same manner as described previously under the Pipeline
Operation section above.
Construction
Buescher State Park (Houston Toad): Construction of the replacement and lowering
projects within Buescher State Park will be contained within the existing 50 ft ROW, and/or
within the previously cleared ROWs of the other two adjacent pipelines. No clearing
beyond the limits of the existing ROWs will be conducted. Compensation based on the
extent of existing Longhorn ROW through Houston toad habitat was provided in the Phase
One consultation. Therefore, no additional impacts or compensation are required for this
construction. A breeding season survey for toads in the vicinity of the pipeline has been
completed, and no toad breeding activity was identified. However, special procedures will
be implemented for avoidance prior to and during construction to ensure no adverse effects
occur to the toad. Prior to any land disturbance, the construction zone will carefully be
inspected by qualified biologists to ascertain the possible presence of Houston toads. The
construction zone will then be completely encircled with silt fence (set into the ground) to
preclude Houston toads from entering the work space. The construction zone will be
inspected periodically by the biologists to ensure Houston toads have not entered the area.
Therefore, this construction is unlikely to result in adverse effects to the Houston toad or
designated critical habitat beyond those addressed and compensated for in the Phase One
consultation.
Edwards Aquifer Recharge Zone (Barton Springs Salamander): As described in
Section 3.5, a 3-mile segment across the aquifer recharge zone will be replaced with
99144ba2.v8
72

<<<PAGE 402>>>

heavier wall pipe for enhanced safety and integrity. Approximately one-half mile will be
replaced immediately east of the recharge zone.
The new pipe will also be lowered for
greater depth of cover to minimize the potential for third-party strikes. Further, a concrete
barrier will be installed over the pipeline to protect the pipeline from third party intrusion; the
barrier will be constructed with colored reinforced concrete to increase its deterrent effect.
A number of other safety and integrity enhancement measures will also be installed,
including a sensor-based leak detection system and additional check valves.
All these
enhancements will significantly reduce the potential for releases and potential release
volumes in the unlikely event of a pipeline release. Longhorn hereby provides to the
Service mill certificates for the pipe that will be installed, along with Construction
Specification CS4, the specifications that identify methods and procedures for pipeline
construction; see the accompanying Phase Two Project Documentation Appendix at Tabs
26 and 27.
The construction to accomplish these enhancements will involve deepening the existing
trench. Construction will occupy an average work space of 60 feet wide along the 3-mile
route. This construction space has been investigated for karst features and other sensitive
environmental resources. A detailed Edwards Aquifer Protection Plan has been developed
for the project that includes the implementation of all required best management practices
(BMPs) using as guidelines the City of Austin Land Development Code specifications and
the TNRCC Edwards Aquifer Rules for construction over the recharge zone (Phase Two
Project Documentation Appendix at Tab 28). Detailed construction plans will be developed
to identify both the design and location of water quality control structures, as well as non-
structural BMPs; those plans, which are currently under development, will be made
available to the Service upon preparation of reasonably complete draft documents.
The environmental protection plan also provides for FERC qualified environmental
inspectors to be onsite during the construction process to continuously review and evaluate
the efficiency of the recommended BMPs and to make changes as needed for maximum
environmental protection. The environmental inspectors will also react to any encounter of
subsurface voids by immediately notifying project geological and biological experts for
evaluation of the situation and to make recommendations for remedial actions. Remedial
actions will, at a minimum, comply with TRCC guidelines for closure of subsurface voids.
All encountered limestone voids, regardless of size, will be appropriately sealed within the
construction trench. This will prevent potential siltation into the aquifer via such voids
during construction, as well as provide additional protection from aquifer contamination in
the unlikely event of a product release during operation of the pipeline. In the event a large
void is encountered, geotechnical engineers will also be involved in evaluating and
recommending remedial actions. The City of Austin, TRCC, Barton Springs/Edwards
Aquifer Conservation District, and the Service will also be notified and informed of
recommended remedial actions. The trench has been designed with high porosity
containment capacity and bermed areas at locations where product could reach the
surface.
With the implementation of the Edwards Aquifer Environmental Protection Plan, the
construction across the Edwards Aquifer recharge zone is not expected to result in any
significant adverse impacts to the aquifer or the Barton Springs Salamander.
Edwards Aquifer Contributing Zone (Barton Springs Salamander): As described in
99144ba2.v8
73

<<<PAGE 403>>>

Section 3.5, approximately 15 miles of pipe in the contributing zone will be lowered and
replaced, and a check valve will be installed immediately downstream of the existing block
valve over the contributing zone (MP 175.5), even though the replacement is not necessary
(See "Edwards Aquifer Contributing Zone Protections" in The Project Documentation
Appendix). The replacements will be installed using heavier wall pipe than exists at this
time and will be lowered at least 5 feet below the ground surface. Construction over the
contributing zone will be conducted pursuant to the methods and procedures outlined in the
Phase One BA. The heavier, deeper pipe will reduce the risk of a release across the
contributing zone. The trench has been designed with high porosity containment capacity
and bermed areas at locations where product could reach the surface. The check valve will
reduce potential release volumes by immediately stopping flow upstream, in the event of a
release east of the block valve; as a result, the potential for drainage from higher-elevation
segments to the west of the check valve is eliminated during the time required for the block
valve to close. Moreover, at the Cedar Valley pump station, which is located in the
contributing zone upgradient of the pipeline crossing of Barton Creek, Longhorn has
committed to install secondary containment (LMC 27) and a remote monitoring camera
(LMC 21) before project startup. The secondary containment will provide protection to
Barton Creek, and remote cameras allow monitoring by the pipeline controllers.
Furthermore, the host of pipeline mitigation measures directed to Tier Il and III areas will
apply over much of the contributing zone, including hydrostatic pressure and proof testing,
enhanced leak detection, frequent patrols, cathodic protection system testing, in-line
inspection shortly after startup, surge pressure protection, and the establishment of a
response center in South Austin. See Section 3.4, Emergency Response.
4.4 Planned, But Unscheduled Construction
As described in Section 3.0, several additional improvements to the pipeline are planned to
take place, but have not been specifically designed or scheduled at this time. While many
of these improvements are located at existing above-ground facilities (valves, pump
stations, etc), the exact location and construction details are not yet known. It is believed
that the majority of these additional improvements will not occur in potential habitat areas,
but if so will not adversely affect listed species habitat, or can be designed to avoid habitat
areas.
In the event any such improvements should necessitate access or construction
within listed species habitat, the previously utilized Phase One BA maintenance
construction procedures (see Phase Two Project Documentation Appendix at Tab 1) will be
followed under the direction of FERC qualified environmental inspectors. To the extent
feasible, all construction activity will be restricted to the existing ROW within habitat areas,
which has been fully compensated. If construction must exceed the ROW in an area of
potential habitat, the Service will be notified in advance, and additional compensation, as
required, will be calculated and provided according to the procedures set forth in the Phase
One BA for the given species, to the extent a specific location has not previously been
compensated for off-ROW impacts.
4.5 Future Additional, But Currently Unforseen Construction
As described in Section 3.0, at various, but unpredictable, times and places in the future,
certain construction activities may be required for maintenance, repair, or testing of the
99144ba2.v8
74

<<<PAGE 404>>>

pipeline or attendant facilities. The majority of these future construction activities can be
designed to avoid any adverse effect to listed species to the extent the activities occur
within potential habitat areas.
In the event any such construction should necessitate
access or disturbance within listed species habitat, the previously utilized Phase One BA
maintenance construction procedures (see Phase Two Project Documentation Appendix at
Tab 1) will be followed under the direction of FERC qualified environmental inspectors. To
the extent feasible, all construction activity will be restricted to the existing ROW within
habitat areas, which has been fully compensated. If construction must exceed the ROW in
an area of potential habitat, the Service will be notified in advance, and additional
compensation, as required, will be calculated and provided pursuant to the conditions set
forth in the Phase One BA for the given species, to the extent a specific location has not
previously been compensated for off-ROW impacts.
4.6 Bays and Estuaries
The Longhorn Pipeline is in proximity to the Galveston/Trinity Bay system where it passes
through Houston. All surface drainage in the Houston area crossed by the Longhorn
Pipeline drains to the Galveston/Trinity Bay system ultimately through Buffalo Bayou and
the Houston Ship Channel.
Bay systems along the Texas coast, including the
Galveston/Trinity Bay system, are documented to support a number of listed threatened or
endangered sea turtles and marine mammals. Possible concern could exist in the event of
a catastrophic release event that product could reach the bay system in sufficient quantities
to be toxic or detrimental to those listed species.
Several factors are to be considered in this situation that result in an extremely low
probability for significant quantities of product to be released in a tributary or waterway that
would have direct inflow to Galveston and Trinity Bays. First, the Longhorn Pipeline is
buried very deep at the various waterway crossings in north Houston, such as Greens
Bayou (24 feet), Hunting Bayou (25.2 feet), ditch north of Hunting Bayou (33.1 feet), ditch
south of Hunting Bayou (28 feet), and others (See depths of cover in Project
Documentation Appendix). This significant depth greatly reduces the potential for third
party strike. Second, most of the area through east and north Houston is ranked as Tier 2
or 3 zones, thus being subject to the enhanced LMP provisions for Sensitive Areas, and
Hypersentitive areas.
Additionally, all the tributaries drain to Buffalo Bayou and the
Houston Ship Channel. Due to the large number of chemical, refining, and industrial
facilities situated along the Houston Ship Channel, there exists in place a comprehensive
spill response system and equipment to respond quickly to spills of any nature that occur in
the channel. It is unlikely that a significant spill from the Longhorn Pipeline would occur in a
sensitive drainage area, or would escape the Houston Ship Channel containment into the
bays.
4.7 Summary of Conservation Measures
99144ba2.v8
75

<<<PAGE 405>>>

The following provides a summary of the avoidance and conservation measures that
Longhorn commits to provide.
These measures are assured by the mandates of this
consultation and the overall NEPA process simultaneously ongoing with this consultation.
The implementation of these conservation measures for listed species assure that the
project will be unlikely to result in jeopardy or adverse modification of critical habitat for any
listed species and is not likely to adversely effect species or habitat.
Many of the mitigation measures of the Longhorn Mitigation Plan which were designed prior
to the Phase One or Phase Two consultation processes were intended to provide
protections for listed species, either directly or intrinsically. While all LMP features provide
significant safety and integrity enhancements for the pipeline as a whole that ultimately
benefit species protection, those described below provide specific enhancements which will
avoid potential impacts to listed species. Most of these features were incorporated into the
LMP prior to finalization of either of the consultation processes.
• LMCs 3, 5, 34 - Pipe replacement and lowering over the Edwards Aquifer recharge and
contributing zones, with trench and surface containment areas (Barton Springs
Salamander), Buescher State Park (Houston toad), Pedernales Falls State Park
(golden-cheeked warbler), and other locations in species habitat areas;
• LMC 22 - Analysis of, and if necessary, installation of additional valves to limit potential
release volumes (all species);
• LMC 13 - Addition of an enhanced pipeline leak detection system with additional
sensor-based leak detection over the recharge zone and slaughter creek watershed
in the contributing zone (all species);
• LMC 20 - Increased pipeline surveillance in EA designated sensitive and
hypersensitive areas and daily pipeline surveillance across the recharge zone (at
least once per week on-ground) (all species);
• LMC 23 - Establishment of a fully equipped Emergency Response Center in South
Austin (Barton Springs Salamander and Houston toad):
•
LMC 28 - Revised Facility Response Plan to incorporate features of the City of
Austin Barton Springs Oil Spill Contingency Plan and the U.S. Fish and Wildlife
Service's Barton Springs Salamander Recovery Plan as well as detailed response
planning based upon analysys of stream flow potential in the Edwards Aquifer
recharge and contributing zones. (Barton Springs Salamander);
•
LMC 33 - Establish a refugium for the Barton Springs Salamander and performance
of other conservation measures for listed species as may be determined appropriate
through consultation with the U.S. Fish and Wildlife Service (all species);
•
LMC 27 - Provide secondary containment around the Cedar Valley pump station
which lies within the Barton Springs/Edwards Aquifer contributing zone.
99144ba2.v8
76

<<<PAGE 406>>>

• LMC 35 - Longhorn has committed that it will not transport products containing
MTBE or similar aliphatic ether fuel additives in greater than trace amounts;
Though not a specific mitigation commitment, Longhorn has identified all potential
areas of concern for listed species along the pipeline corridor from Houston to El
Paso for purposes of assessment and avoidance.
An additional intrinsic benefit of increased patrol frequencies (LMC 20) is the result
that increased inspection and surveillance of the Longhorn Pipeline will enable
inspection personnel to coincidentally observe the adjacent pipelines that parallel the
Longhorn pipeline. This will provide the opportunity for identification of pipeline
emergency situations and threats to the integrity of those pipelines with greater
frequency than currently is the case.
In fulfillment of LMC 33, Longhorn has committed to a significant number of additional
mitigation features specific to listed species developed during the Phase One and Phase
Two consultation processes. These commitments become binding as a result of the
conclusion of the consultation processes and issuance of the Service's Biological Opinion,
and as incorporated into the LMP as it evolves during the EA process. These measures
have been developed during the two phases of consultation through discussions between
Longhorn, EPA, DOT, and the Service. These commitments are listed below by
consultation phase.
Phase One
• Provision of conservation funding for potentially affected species in the approximate
amount of $992,448 (all species).
• Monitoring studies of listed species within or adjacent to the ROW (all species).
• Minimization of maintenance construction work space in potential species habitat
areas (all species).
• Seasonal timing of maintenance activities to avoid critical breeding, nesting, or
blooming periods for listed species (all species).
• Use of special mowing/clearing processes and equipment in potential species
habitat areas to minimize ground disturbance (all species).
• Provision of FERC qualified environmental inspectors during maintenance activities
within potential species habitat areas (all species).
• Use of native grasses for restoration of disturbed areas during maintenance
activities (all species).
• Minimization of the use of herbicides for maintenance purposes (all species).
99144ba2.v8
77

<<<PAGE 407>>>

Phase Two
Detailed topographic and surface flow modeling to enhance spill response planning
efforts (all species).
Special investigative, preparation, and construction practices and techniques for
pipe replacement over the Edwards Aquifer Recharge Zone (Barton Springs
Salamander) including:
Intensive geological and biological field studies of the pipeline corridor to
Identity sensitive teatures and areas, including ground penetrating radar,
geotechnical coring,
karst identification, geological
and biological
investigations of identified features, and detailed geologic assessment for
recharge potential.
-
Use of enhanced best management practices for erosion and sedimentation
control during and after construction of new pipe.
-
Sealing of subsurface voids encountered during trench excavation.
-
Provision of a colored, reinforced concrete barrier over the new pipe for
enhanced protection from third party damage.
Grading of the surface over the new pipe installation to direct surface
drainage (potential
surface release away from identified sensitive
areas/features.
•
Lowering and replacement of 15 miles of pipe across the Edwards Aquifer
Contributing Zone.
Training for first responders and other spill response personnel for highest efficiency
and care in
species
areas
(all species) .
Cumulative Effects
Cumulative effects of future State, local or private actions that are reasonably certain to
occur in the action area are considered in this BA. Future Federal actions that are
unrelated to the proposed action are not considered in this section because they require
separate consultation pursuant to Section 7 of the Act. Because of the linear nature of the
pipeline and the long history of clearing and operations (about 50 years), no cumulative
effects from the activities proposed are anticipated. The majority of the counties involved in
the project are predominantly rural (see draft Environmental Assessment of the Proposed
Longhorn Pipeline System at Section 4.1.1.2), and imminent future actions identified are
not likely to result in jeopardy to the species and are not likely to adversely affect any listed
species or habitat.
The various mitigation measures required for the Longhorn Pipeline as a result of the
environmental review being conducted by the Lead Agencies or as a consequence of this
99144ba2.v8
78

<<<PAGE 408>>>

consultation can be expected to have net beneficial effects on the environment, including
listed species and their habitats. First, the Longhorn Pipeline itself will be improved,
providing a higher level of environmental protection than previously was the case for the
pipeline. Second, the Barton Springs Salamander refugium and captive breeding program
will help mitigate for risks posed not only by the Longhorn pipeline, but by the many other
existing sources of potential harm to the salamander, outlined above in the discussion of
the environmental baseline for the salamander.
In addition, some Longhorn-related mitigation measures will have the indirect or cumulative
effect of reducing environmental and species-related risks associated with the two other
petroleum pipelines in the area, especially over the Edwards Aquifer. For example, the
Longhorn Mitigation Plan requires increased surveillance along the pipeline route. While
most pipelines have weekly surveillance, Longhorn has committed to a patrol frequency of
once every 2.5 days for sensitive and hypersensitive areas. In the three-mile crossing of
the Barton Springs recharge zone, Longhorn will have daily patrols. This increased
frequency of patrol will facilitate early detection of leaks and third party activity in the are
of all three pipelines crossing the recharge zone.
Similarly, Longhorn's commitment to aggressive public education and awareness programs
will help reduce risks for all three pipelines crossing the Barton Springs recharge zone.
ublic awareness should deter individuals from acts that might risk catastrophic spills o
other accidents potentially affecting the environment and listed species
99144ba2.v8
79

<<<PAGE 409>>>

5.0 REFERENCES
Arft, A. and T. Ranker. 1995. Demography of the rare orchid Spiranthes diluvialis:
implications for conservation. Program and Abstracts, g'h annual meeting of the Society for
conservation Biology, June 7-11, Fort Collins, Colorado. Abstract, notes from presentation
attended. U.S. Fish and Wildlife Service, Austin, Texas.
Brune, G. 1981. Springs of Texas: Volume 1. Branch-Smith Inc. Fort Worth, Texas.
Chippindale, P., D. Hillis, and A. Price. 1990. Central Texas Salamander Studies. Section
6 report submitted by Texas Parks and Wildlife Department to U.S. Fish and Wildlife
Service. Federal Aid Project No: E-1-2, Job No. 3.4. Austin, Texas.
Horizon Environmental Services, Inc. 1991. Threatened or Endangered Species
Investigations - EZ Pipeline Project. Horizon Environmental Service, Inc. Austin, Texas.
Horizon Environmental Services, Inc. 2000. Biotoxicological Analysis a Potential Longhorn
Pipeline Product Release Over The Edwards Aquifer Recharge Zone, Barton Springs
Segment. Horizon Environmental Services, Inc. Austin, Texas.
Poole, J.M,. and D.H. Riskind. 1987. Endangered, Threatened, or Protected Native Plants
of Texas. Austin, Texas: Texas Parks and Wildlife Department, State of Texas.
U.S. Fish and Wildlife Service (USFWS). 1984a. Houston toad recovery plan. U.S. Fish
and Wildlife Service. Albuquerque, New Mexico. 73pp.
U.S. Fish and Wildlife Service (USFWS). 1984b. Navasota ladies'-tresses recovery plan.
U.S. Fish and Wildlife Service. Albuquerque, New Mexico.
U.S. Fish and Wildlife Service (USFWS). 1994a. Minimum Procedures for Determining the
Presence/Absence of Golden-Checked Warblers and Black-Capped Vireos. March 7, 1994
Memorandum, Austin Field Office.
U.S. Fish and Wildlife Service (USFWS). 1994b. Population and habitat viability
assessment: Houston toad (Bufo houstonensis). Workshop conducted by IUCN/SSC
Conservation Breeding Specialist Group in partial fulfillment of USFWS contract #94-172.
Apple Valley, Minnesota.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and Endangered Species of
Texas. Austin, Texas: US Fish and Wildlife Service, Revised June, 1995.
U.S. Fish and Wildlife Service (USFWS). Houston Toad Recovery Team. 1999. March 31-
April 1, 1999 Meeting Minutes. U.S. Fish and Wildlife Service, Austin, Texas.
U.S. Fish and Wildlife Service (USFWS). Final Rule to List the Barton Springs Salamander
as Endangered. 62 FR 23377. Apr. 30, 1997.
Texas Parks and Wildlife. 1993. Endangered species information for Hilltop Lakes. Texas
Parks and Wildlife Resource Protection Division, Austin, Texas.
99144ba2.v8
80

<<<PAGE 410>>>

Wilson, H. 1993. Contractors partial draft of recovery plan revision for Navasota ladies'-
tresses (unfinished contract). U.S. Fish and Wildlife Service, Austin, Texas.
(SCS) Soil Conservation Service. 1984. Soil Survey of Austin and Waller Counties, Texas.
United States Department of Agriculture.
99144ba2.v8
81

<<<PAGE 411>>>

Appendix 4B
Phase I and II Biological Assessments, Phase I Biological Opinion, and
Concurrence Letter

<<<PAGE 412>>>

Phase 1 Biological Assessment
February 14, 2000

<<<PAGE 413>>>

HJN 990144
BIOLOGICAL ASSESSMENT
LONGHORN PIPELINE PROJECT
MAINTENANCE ACTIVITIES
AND MINOR CONSTRUCTION
HOUSTON TO CRANE, TEXAS
Prepared For:
Longhorn Partners Pipeline, L.P.
US Environmental Protection Agency
Region 6
US Department of Transportation
Office of Pipeline Safety
Prepared By:
Horizon Environmental Services, Inc.
Austin - Beaumont - Houston - Shreveport
February 14, 2000
990144BA.v-6
- 2/14/2000

<<<PAGE 414>>>

TABLE OF CONTENTS
Section
Page
1.0
INTRODUCTION.
.1
2.0
PROJECT OVERVIEW.
.7
3.0
EXISTING ENVIRONMENT...
...9
3.1
GENERAL...
.9
3.2
VEGETATION........
..9
3.2.1 Gulf Prairies and Marshes Vegetational Area.
...9
3.2.2 Post Oak Savannah Vegetational Area...
12
3.2.3 Blackland Prairies Vegetational Area ...
.12
3.2.4 Edwards Plateau Vegetational Area.......
..13
3.2.5 The Trans-Pecos, Mountains and Basins Vegetational Area...
..13
3.3
WILDLIFE..............
..14
3.3.1 Austroriparian Biotic Province
..14
3.3.2 Texan Biotic Province.
..14
3.3.3 Balconian Biotic Province
..16
3.3.4 Kansan Biotic Province..
16
3.3.5 Chihuahuan Biotic Province
..16
3.4
THREATENED AND ENDANGERED SPECIES
17
4.0
PROJECT DESCRIPTION...
.37
4.1
RIGHT-OF-WAY CLEARING AND MARKING.
.37
4.2
PIPELINE MAINTENANCE-CONSTRUCTION PLANNING.
39
4.3
PROJECT ENVIRONMENTAL INSPECTORS
45
4.4
SITE PREPARATION.........
45
4.5
SITE ENTRY.......
..46
4.6
PIPELINE LOWERING AND/OR REPLACEMENT - OPEN TERRAIN
47
4.7
PIPELINE LOWERING AND/OR REPLACEMENT - CREEK CROSSINGS
51
990144BA.v-6
- 2/14/2000

<<<PAGE 415>>>

4.8
TRENCHING...
.51
4.9
BORING..
4.10
HYDROSTATIC TESTING - OVERVIEW OF ACTIVITIES
4.11 HYDROSTATIC TESTING - POTENTIAL FAILURE OF PIPELINE.
4.12 CATHODIC PROTECTION ENHANCEMENTS
4.13 SURGE PRESSURE PROTECTION
4.14 INVESTIGATIONS........
59
5.0
POTENTIAL IMPACTS (TAKE) AND COMPENSATION.
60
5.1
SPECIES-BY-SPECIES IMPACT ANALYSIS
64
5.2
AVOIDANCE AND MINIMIZATION
69
5.3
PROPOSED COMPENSATION FOR POTENTIAL TAKE
71
6.0
REFERENCES...................
............77
990144BA.v-6
2/14/2000

<<<PAGE 416>>>

LIST OF FIGURES
Figure
Page
1
LOCATION MAP ......
10
2
VEGETATIONAL AREAS OF TEXAS TRAVERSED BY THE
LONGHORN PIPELINE
11
3
BIOTIC PROVINCES OF TEXAS TRAVERSED BY THE
LONGHORN PIPELINE
15
4 - 12
AREAS OF FEDERALLY LISTED, THREATENED, OR
ENDANGERED SPECIES TRAVERSED BY THE LONGHORN
PIPELINE - HOUSTON TO CRANE .
..22-30
LIST OF TABLES
Table
Page
1
FEDERALLY LISTED THREATENED OR ENDANGERED
SPECIES WHICH OCCUR IN COUNTIES TRAVERSED BY THE
LONGHORN PIPELINE -HOUSTON TO CRANE
18
2
2000 MAINTENANCE CONSTRUCTION, TESTING AND
CLEARING, LONGHORN PIPELINE ..
40
3
ROW CLEARING AND ADDITIONAL MAINTENANCE
CONSTRUCTION IMPACTS - LONGHORN PIPELINE -
HOUSTON TO CRANE.
62
4
LONGHORN PIPELINE TAKE COMPENSATION
|.........75
APPENDIX
PROJECT DOCUMENTATION APPENDIX
ACCOMPANYING DOCUMENT
990144BA.v-6
2/14/2000

<<<PAGE 417>>>

1.0 INTRODUCTION
This Biological Assessment (BA) is prepared in connection with the draft
Environmental Assessment of the Longhorn Pipeline owned by Longhorn
Partners Pipeline, L.P. (Longhorn). That Environmental Assessment was the
product of a settlement reached in the matter of Spiller, et al v. Walker, et al
pending in the United States District Court in Austin, Texas. The plaintiffs in that
lawsuit alleged failure on the part of numerous federal agencies to adequately
analyze the potential environmental impacts of the Longhorn Pipeline. Though
the federal defendants and Longhorn denied the plaintiffs' allegations, the parties
reached a negotiated settlement that was approved by the Court on March 5,
1999. Parties to that settlement included Longhorn, the US Environmental
Protection Agency (EPA), the US Department of Transportation (DOT), the US
Department of Justice, the City of Austin, the Lower Colorado River Authority,
and the remaining plaintiffs.
As part of that Court ordered settlement, the agencies involved in the
original litigation were required to conduct an Environmental Assessment,
including specific consideration of species protected under the Endangered
Species Act (ESA). The Court ordered EPA and DOT, acting as Lead Agencies,
to be responsible for the Environmental Assessment, and ordered the
Department of Army to act as a cooperating agency. A draft Environmental
Assessment, with a preliminary Finding of No Significant Impact (FONSI), was
prepared by Radian International LLP at the direction of and pursuant to a work
plan approved by the Lead Agencies. As a result of the Environmental
Assessment, and with the support of the Lead Agencies, Longhorn has
committed to implement a slate of 34 pipeline mitigation measures. (The pipeline
mitigation measures are identified and described in the Longhorn Mitigation Plan
included in the accompanying Project Documentation Appendix at Tab 2). The
pipeline mitigation measures focus on two general areas: first, the enhancement
of pipeline integrity to reduce the probability of a pipeline release and to reduce
risks to pipeline integrity, and second, enhancement of emergency response
capability and development of plans for corrective action in the unlikely event of a
pipeline release. Both categories of pipeline mitigation measures are discussed
below in greater detail in Section 4.0, Project Description.
990144BA.v-6
- 2/14/2000

<<<PAGE 418>>>

Pursuant to Section 7 of the ESA, the Lead Agencies have requested
consultation with the US Fish and Wildlife Service (the Service) regarding the
Draft Environmental Assessment and the package of pipeline mitigation
measures upon which the Lead Agencies' preliminary FONSI is predicated. In
connection with the inter-agency consultation, Longhorn prepared and submitted
to the Service a draft BA on the entire pipeline project on September 27, 1999.
The Service responded to the September draft BA with comments and requests
for additional information in the form of a letter to Horizon Environmental
Services, Inc., dated December 15, 1999 (the Comment Letter - see
accompanying Project Documentation Appendix at Tab 12).
On February 3, 2000, the Lead Agencies designated Longhorn has a non-
federal representative for the purpose of consultation with the Service and
preparation of a BA on the Longhorn project.
The Spiller Court's order provides that issuance of any FONSI with regard
to the Longhorn project "shall be conditioned upon implementation" of measures
to protect public safety and the environment. Settlement Stipulation at 6. The
order also prohibits the DOT from authorizing Longhorn to commence operations
until Longhorn has implemented those mitigation measures upon which the
FONSI is conditioned. Settlement Stipulation at 7. The order contemplates that
Longhorn will apply for, and accept, such ESA permits as may be required in
connection with the implementation of any mitigation measures upon which a
FONSI may be conditioned. Id.
The results of this consultation by the Lead Agencies with the Service are
expected to be incorporated in the Record of Decision issued by the Lead
Agencies. If the Lead Agencies issue an EA/FONSI, the terms and conditions,
mitigatory measures and protections incorporated herein for the benefit of
species will be adopted and incorporated by Longhorn in its operating and
maintenance manuals submitted to, and enforceable by, DOT pursuant to the
Pipeline Safety Act (49 U.S.C. §60101, et seq.) or the Longhorn mitigation
commitments.
The Office of Pipeline Safety (OPS) administers DOT's regulatory program
to ensure the safe transportation of various hazardous liquids by pipeline under
990144BA.v-6
2
- 2/14/2000

<<<PAGE 419>>>

the Pipeline Safety Act. OPS is responsible for inspecting pipelines before they
are placed in service to ensure that they are in accordance with DOT's
regulations and are being operated safely. The OPS's published statement of its
authority is set out below:
The Department of Transportation's (DOI) Research
and
Special Programs
Administration (RSPA),
acting
through
the
Office
of Pipeline Safety
(OPS), administers
the Department's
national
regulatory
program
assure
the
safe
other
transportation of natural gas, petroleum, and
hazardous
materials
by pipeline. OPS
develops regulations and other approaches to risk
management
assure safety in
design,
construction,
testing,
operation,
maintenance,
emergency response of pipeline
facilities.
Although the Service and the Lead Agencies are in consultation with
respect to the entire proposed Longhorn Project, this consultation is being
approached in two distinct, yet related phases'. The first phase of the
consultation (Phase I) relates to pipeline maintenance, pipeline testing and the
first category of measures that Longhorn will take to fulfill its commitment to
ensure pipeline safety and integrity. These measures focus on pipeline integrity
enhancements such as a number of pipe replacements, lowering of some
sections of pipe, investigation of possible pipe flaws, hydrostatic pressure testing,
and similar actions.
The second phase of the consultation (Phase I) will be more directly
related to the actual operation of the pipeline, specifically the operation and
maintenance of the pipeline system and the potential effects of the unlikely event
of a pipeline release. Additional mitigation measures, such as internal pipeline
inspections and construction in two particular areas, also will be addressed in
Phase II. Those areas are (a) Houston toad habitat and (b) areas of potential
effect to the Barton Springs Salamander over the Edwards Aquifer Recharge
Zone. A two-stage consultation offers the most protection to the species,
because the second phase will benefit from and build upon species information
gathered in the first stage of review, while allowing the most efficient route to
402.14(k) provides a mechanism for the Service to review a project, and provide biological opinions on each
U.S. Fish and Wildlife regulations allow for a staged consultation. 50 C.F.R § 402.14(k). Section
incremental step.
990144BA.v-6
- 2/14/2000

<<<PAGE 420>>>

startup of the pipeline.
The Spiller settlement specifically contemplates that Longhorn will
undertake certain construction and maintenance activities prior to issuance of a
final agency decision in this matter. Settlement Stipulation at 8-11. The parties to
the settlement specifically agreed that any such investments by Longhorn in
Kimble, Menard, Hays, Travis, Caldwell, Bastrop and any counties within the
jurisdiction of the LCRA after August 25, 1998 would not be considered "for the
purposes of determining the reasonableness of alternatives" (Settlement
Stipulation at 11), meaning that these investments would not constitute
irretrievable commitments of resources for the purposes of the National
Environmental Policy Act or Section 7(d) of the ESA.
Phase I of the consultation focuses on near-term discrete tasks that are
requisite preliminary activities-tasks that Longhorn must complete before it can
place the pipeline into operation, such as right-of-way clearing and pipeline safety
mitigation measures. They will be implemented in a manner that avoids and
minimizes potential effects upon species and habitat.
Phase II of the consultation will focus on long-term programmatic
activities, operation and maintenance of the pipeline, and the possibility of an
emergency response. These activities are either (a) not necessarily discrete or
(b) not precisely estimable before the fact. Phase II activities carry different risks
from Phase I activities. For example, the operation and maintenance activities
are ongoing and long-term. Further, though the probability of a pipeline release
will be minimized as a result of the Longhorn Mitigation Plan, should a release
occur, it has the potential to result in adverse effects to species and habitat at
locations and of magnitudes that are difficult to predict with precision.
Nevertheless, because of the low risk of such a release and the comprehensive
nature of the Longhorn Mitigation Plan, Longhorn and the Lead Agencies believe
that it is appropriate to conclude that there is a reasonable likelihood that the
entire project is not likely to jeopardize the continued existence of any
endangered or threatened species or result in the destruction or adverse
modification of critical habitat. This is because the Phase I review is being
conducted against the backdrop of a larger mitigation package, which the Service
has had an opportunity to review. The Service had an opportunity to review and
990144BA.v-6
4
- 2/14/2000

<<<PAGE 421>>>

comment on the entire project based upon the September draft BA.
The two phases thus can be logically separated. Phase I of the Service's
review (this BA) will focus on those actions that are designed to make the
pipeline safer. The Service can complete this stage of review without pre-judging
whether or not the pipeline will be used. Phase II of the Service's review will
focus on whether and how the pipeline will be used. The Phase I procedures are
routine in the US pipeline industry, during operation, for periodic maintenance,
testing and repair of hazardous liquids and gas pipelines. However, to ensure
that the pipeline is safe, the Longhorn Mitigation Plan specifies that these
activities shall be conducted prior to startup of the Longhorn Pipeline under its
proposed use.
This BA encompasses Phase I of the consultation. Included in this phase
are maintenance of the pipeline right-of-way; maintenance construction to
replace and/or lower certain segments of the pipeline, along with investigation
and repair of possible flaws in the pipe at an identified number of locations;
enhancements to the pipeline cathodic protection system; and hydrostatic
pressure testing of the pipeline to ensure the integrity of the pipe for its intended
service. None of these activities constitutes an irreversible or irretrievable
commitment of resources, natural or monetary, which have the effect of
foreclosing the formulation or implementation of any reasonable and prudent
alternative measures.
This BA is provided to facilitate a formal Section 7 consultation between
the EPA, the DOT, and the Service to evaluate the potential for adverse effects
to listed species resulting from activities related to the implementation of pipeline
mitigation measures to improve pipeline integrity and thereby enhance pipeline
safety. Those pipeline mitigation measures are referred to hereafter in this BA as
projects. The specific maintenance and testing projects to be implemented are
described in detail in Section 4.0 of this BA.
Where appropriate, this BA generally comports with EPA Guidelines for
Ecological Risk Assessment. See Guidelines for Ecological Risk Assessment, 63
Fed. Reg. 26,846 (1998). For example, EPA guidelines suggest that a suitable
990144BA.v-6
5
- 2/14/2000

<<<PAGE 422>>>

assessment approach will identify the explicit, ecologically relevant expressions
of environmental value that are to be protected. See 63 Fed. Reg. at 26,858. To
that end, the BA guides project development, in part, by identifying particular
species of concern within the project area, and suggesting mitigation efforts
which will minimize exposure and impact to those species. Where uncertainty
has been encountered, doubt has been resolved in favor of the species, and in
this regard, the results of a precise application of EPA Guidelines have likely
been exceeded. Precise application of the Guidelines would likely reveal far
fewer areas of ecological sensitivity than have been assumed.
990144BA.v-6
6
• 2/14/2000|

<<<PAGE 423>>>

2.0
PROJECT OVERVIEW
Longhorn proposes to operate a 723-mile refined petroleum products
pipeline system from the GATX Terminal in Galena Park, Texas, to a refined
petroleum products terminal in El Paso, Texas. The pipeline also has a 28-mile
intermediate connection from a station in Crane County to a planned meter
station in Odessa, Texas. The pipeline consists of a combination of 20-inch and
18-inch diameter pipe from Galena Park Station to El Paso Terminal and an 8-
inch diameter pipeline from a station in Crane County to a meter station in
Odessa, Texas. Finally, three as yet to be built pipelines will connect the El Paso
terminal to interstate common carrier pipelines west of El Paso. The pipeline's
initial capacity of 72,000 barrels per day (bpd) will be supplied by a new pump
station at Galena Park and five newly constructed booster pump stations at the
following locations: Satsuma (Harris County), Cedar Valley (Hays County),
Kimble County (Kimble County), Crane (Crane County), and El Paso (El Paso
County).
Two new pipeline construction projects remain to be completed. An 8-inch
diameter, 2500-foot lateral that originates at the terminus of the existing Odessa
lateral will connect to a terminal facility in Odessa, Texas, owned by Equilon.
Three 8.3-mile lateral pipelines, which originate at the El Paso Terminal, will
connect with Kinder Morgan (formerly the Santa Fe Pacific pipeline) and Chevron
pipelines in the El Paso area. The connection to Kinder Morgan will consist of
one 8-inch diameter pipeline and one 12-inch diameter pipeline. The Chevron
connection will consist of an 8-inch diameter pipeline. The purpose of the lateral
pipelines is to connect into Kinder Morgan and Chevron pipelines to distribute
product into the Phoenix, Tucson, and Albuquerque (New Mexico) markets.
Chevron operates an 8-inch pipeline that delivers product to the Albuquerque
market; Kinder Morgan operates one 12-inch pipeline and one 8-inch pipeline
serving the Tucson market. Other Kinder Morgan pipelines connect Tucson to
the Phoenix market.
The proposed project includes both new construction and refurbishment of
990144BA.v-6
7
- 2/14/2000

<<<PAGE 424>>>

an existing pipeline that has been converted from its former use of transporting
crude oil from West Texas to the Gulf Coast area, the majority of which is
complete. As described in this chapter, the existing pipeline has been modified
to transport refined petroleum products, with flow going from east to west.
Williams Pipeline Company (later to become part of Williams Energy Services)
will be the contract operator of the Longhorn Pipeline System. Longhorn intends
to transport multiple grades of gasoline and distillates, which will include special
reformulated grades of gasoline needed to control air emissions in certain areas
of the Southwest.
The Longhorn Pipeline System is designed for service in excess of 50
years and is made up of four main pipeline segments, several stations, and one
terminal, as listed below:
• New and refurbished 20-inch diameter pipeline from Galena Park
Station to Satsuma Station
• Refurbished 18-inch diameter pipeline from Satsuma Station to Crane
Station
New 18-inch diameter pipeline from Crane Station to El Paso Terminal
New lateral pipeline connections to Odessa and to other pipelines at El
Paso
• New Pump Stations
• El Paso Terminal
• Odessa Meter Station
A detailed description of the Longhorn Pipeline System is included in the
Longhorn Pipeline Project Description section of the accompanying Project
Documentation Appendix at Tab 1. More detailed descriptions of the project
components that are subject to this BA are included in Section 4.0. Future
pipeline upgrades, repairs, and maintenance beyond that identified in this
document will be addressed in Phase II of the consultation.
990144BA.v-6
8
- 2/14/2000

<<<PAGE 425>>>

3.0
SEXISTING ENVIRONMENT
3.1
GENERAL
The Longhorn Pipeline traverses the State of Texas from east to west
originating in east Houston, Harris County and extending westward to Crane
Station, Crane County (Figure 1). Auxiliary lines extend from Crane Station
northward to Odessa and westward to El Paso in far west Texas. The area
traversed by the pipeline varies physiographically from flat or rolling coastal
prairie in the Houston region to hilly woodlands of the Edwards Plateau in central
Texas to the xeric Permian Basin region of west Texas.
3.2
VEGETATION
From east to west, the Longhorn Pipeline traverses the Gulf Prairies and
Marshes, Post Oak Savannah, Blackland Prairies, Edwards Plateau, and Trans-
Pecos, Mountains and Basins Vegetational Areas (Gould, 1975; Figure 2). The
following provides a summary description of each ecological region.
3.2.1 Gulf Prairies and Marshes Vegetational Area
This ecological region, approximately 9.5 million acres in extent, is divided
into the Coastal Prairie and Gulf Coast Marshlands. The Coastal Prairie is a
nearly level plain less than 150 feet above mean sea level (MSL) and dissected
by streams and rivers flowing into the Gulf of Mexico while the Gulf Coast
Marshlands are limited to narrow belts of low wet marsh immediately adjacent to
the coast and along waterways. Surface soils are acid sands, sandy loams, and
clays with low permeability and droughty in nature. Annual precipitation
averages from 20 inches in the west to 50 inches in the east (Gould, 1975).
The climax vegetation is largely grassland or post oak savannah (Gould,
1975). Ranches and rangelands are interspersed by farms. Most of the marsh
areas are grazed by cattle within large land holdings.
990144BA.v-6
9
- 2/14/2000

<<<PAGE 426>>>

MARILO Coo
Oklahoma
Mexico
New
LuBBOCK
• Т корт орт райм
Louisiana
ODESSA
MIDLAND
SAN ANGELO
Mexico
Mexico
DEL RIO
LAREDO
Mexico
Gulf of
- Longhor Refined Products Pipeline
for far:
2003
• 7i21
No.
FIGURE I
NOT TO SCALE
LONGHORN PIPELINE
LOCATION MAP
MAP SOURCES:
TEXAS NATURAL RESOURCE INFORMATION SYSTEM
LONGHORN PIPELINE

<<<PAGE 427>>>

Longhorn Refined Products Pipeline
10
MEXICO
GULF
VEGETATIONAL AREAS OF TEXAS
1. .
2.
Gulf Prairies and Marshes
Pineywoods
3.
4.
Post Oak Savannah
5.
Blackland Prairies
6.
South Texas Plains
Cross Timbers and Prairies
:50
8. Rolling Plains
7. Edwards Plateau
Mile
100
10. Trans-Pecos, Mountains and Basins
High Plains
Horizon
ENVIRONMENTAL SERVICES, INC.
FIGURE 2
LONGHORN PIPELINE
IN RELATION TO THE
Source:
Gould, 1975.
VEGETATIONAL AREAS OF TEXAS

<<<PAGE 428>>>

3.2.2 Post Oak Savannah Vegetational Area
This ecological region, approximately 8.5 million acres in extent, is
bordered by the Pineywoods region to the east and the Blackland Prairie region
to the west. The topography is gently rolling to hilly, and elevations range from
300 to 800 feet above mean sea level (MSL). Generally, surface soils of higher
elevations are light-colored, acidic sandy loams or sands while those of lower
elevations are darker, acidic sandy loams or clays. Annual precipitation
averages from 35 to 45 inches, and May or June is generally the high rainfall
month (Gould, 1975).
The Post Oak Savannah was historically dominated by prairie climax
grasses and scattered trees. The most prevalent trees were oaks and cedar elm.
The deterioration of the climax plant communities in the region is evidenced by
an increase of certain grass species, forb species, and woody species (Gould,
1975). Moderate to dense post oak dominated woodlands have developed in
many areas as a result of man's suppression of fire. The bottomland woodland
remains the most diverse vegetation type of this ecological area.
3.2.3 Blackland Prairies Vegetational Area
This ecological region, approximately 11.5 million acres in extent, includes
the San Antonio and Fayette Prairies. Land surface ranges in elevation from 300
to 800 feet, gently rolling to nearly level, and well dissected and rapidly drained.
Surface soils are fairly uniform, dark-colored calcareous clays
interspersed with gray acid sandy loams. Annual precipitation averages from 30
inches in the west to 40 inches in the east (Gould, 1975).
The climax native vegetation is true prairie (Gould, 1975). The majority of
this ecological area has been brought under cultivation. Farms are interspersed
among ranches and rangelands.
990144BA.v-6
12
- 2/14/2000

<<<PAGE 429>>>

3.2.4 Edwards Plateau Vegetational Area
This ecological region encompasses approximately 24 million acres in
west-central Texas. Land surface ranges in elevation from 100 to 3000 feet
above MSL, rough and well drained, and dissected by several river systems.
Surface soils are usually shallow and underlain by material ranging from
limestone or caliche to granite. Annual precipitation averages from 15 inches in
the west to over 33 inches in the east, and droughts are not uncommon (Gould,
1975).
The Edwards Plateau Vegetational Area is predominantly rangeland
(Gould, 1975). Bottomland areas of this ecological area having deeper soils
have been brought under cultivation. Small farms are interspersed among
ranches and rangelands.
3.2.5 Trans-Pecos, Mountains and Basins Vegetational Area
This ecological region encompasses approximately 19 million acres of
mountains and arid valleys in extreme west Texas. Land surface ranges in
elevation from 2500 to over 8500 feet, rough and well drained, and dissected by
several river systems.
Surface soils have developed from out-wash materials from mountains,
varied in texture, calcareous, and some areas are alkaline due to poor drainage.
Surface conditions include stony hills, clay flats, sands, salty-saline soils, gypsum
flats, deep upland, rough stony mountains, gravelly outwash, and badlands
(Gould, 1975). The average annual precipitation for the area is less than 12
inches while higher elevations can range from 16 to 20 inches (Gould, 1975).
Cultivated areas are confined largely to irrigable valleys. The majority of
land is in large holdings as native range. Ranch operations include cattle, sheep,
and goats.
3.3
WILDLIFE
990144BA.v-6
13
- 2/14/2000

<<<PAGE 430>>>

From east to west, the Longhorn Pipeline traverses the Austroriparian,
Texan, Balconian, Kansan, and Chihuahuan Biotic Provinces described by Blair
(1950; Figure 3). The following provides a summary description of each biotic
province.
3.3.1 Austroriparian Biotic Province
This province includes the Gulf coast plain from the Atlantic to eastern
Texas. The western boundary of this province in Texas is along a line running
approximately north from western Harris County to western Red River County.
The pine and hardwood forest of the Austroriparian is limited to the west by
available moisture.
The vertebrate fauna of the Austroriparian Province in Texas is typical of
the species in the province to the east. At least 47 species of mammals occur in
this province in Texas. Some 29 species of snakes, 10 lizards, 2 land turtles, 17
anurans, and 18 urodels are known to occur in the Texas part of this province
(Blair, 1950).
3.3.2 Texan Biotic Province
This province is a transitional area and is recognized as a broad ecotone
between the forests of the Austroriparian and Carolinian provinces of eastern
Texas and Oklahoma, and the grasslands of the western parts of these states.
The integration of woodlands and grasslands within the region results in a
mixture of wildlife species typical of the 2 general habitats. The vertebrate fauna
of the Texan Biotic Province consists of at least 49 species of mammals,
16 lizards, 2 land turtles, 39 snakes, 18 anurans (frogs and toads), and
5 urodeles (salamanders, newts, etc.) (Blair, 1950). No endemic vertebrates are
known from the Texan Province.
990144BA.v-6
14
- 2/14/2000

<<<PAGE 431>>>

Kansan
Navahonian
Texan
Balconian
Chihuahuan
MEXICO
Tamaulipan
of
GULF
Longhorn Refined Products Pipeline
we 3 070€
50
100
Miles
Horizon
ENVIRONMENTAL SERVICES, INC
FIGURE 3
LONGHORN PIPELINE
IN RELATION TO THE
BIOTIC PROVINCES OF TEXAS

<<<PAGE 432>>>

3.3.3 Balconian Biotic Province
This province is synonymous with the Edwards Plateau and is a
physiographically discrete unit. The name Balconian is derived from the
Balcones Fault Zone which forms the southern and eastern boundaries of this
province.
The vertebrate fauna of the Balconian Biotic Province is a mixture of
species characteristic of surrounding major provinces, even though its
characteristic vegetation is distinctly different. The vertebrate fauna consists of
57 species of mammals, 16 lizards, 1 land turtle, 36 snakes, 15 anurans (frogs
and toads), and 7 urodeles (salamanders, newts, etc.) (Blair, 1950). There are
several endemic vertebrates known from the Balconian Biotic Province.
3.3.4 Kansan Biotic Province
This province is divided into 3 distinct biotic districts: the Mixed-grass
District, Mesquite Plains District, and Short-grass Plains District. All of these
biotic districts have areas of dune sand. Moisture is deficient throughout the
Kansan Biotic Province, and there is a decrease in available moisture from east
to west. The Short-grass Plains District occurs in the area of Crane, Texas.
The vertebrate fauna of the Kansan Biotic Province is a mixture of species
from each of its biotic provinces. The vertebrate fauna consists of 59 species of
mammals, 14 lizards, 1 land turtle, 31 snakes, 9 anurans (frogs and toads), and
14 urodeles (salamanders, newts, etc.) (Blair, 1950). There are 6 endemic
vertebrates known from the Balconian Biotic Province.
3.3.5 Chihuahuan Biotic Province
Within Texas, the Chihuahuan Biotic Province includes all of the Trans-
Pecos Texas except the Guadalupe Mountains in Culberson County. The
physiography of the province includes desert basins, mountains, and major
waterways and drainages. Even though the climate of most of the province in
Texas is arid and seriously deficient of moisture for plant growth, vegetational
communities are very diverse.
990144BA.v-6
16
- 2/14/2000

<<<PAGE 433>>>

The vertebrate fauna of the Chihuahuan Biotic Province is extremely
diverse and many of the same species can be found in both desert basin and
mountain areas. The vertebrate fauna consists of 83 species of mammals,
22 lizards, 1 land turtle, 38 snakes, 13 anurans (frogs and toads), and 1 urodele
(salamanders, newts, etc.) (Blair, 1950). There are 6 endemic vertebrates known
from the Balconian Biotic Province.
3.4
THREATENED AND ENDANGERED SPECIES
Horizon Environmental Services,
Inc. (Horizon) has performed
investigations along the existing Longhorn Pipeline right-of-way (ROW) and
vicinity from Houston to Crane for the possible occurrence of all federally-listed,
threatened, or endangered species which are known to exist in all counties of
Texas traversed by the Longhorn Pipeline (Table 1). Following investigation of
the species which potentially occur in these counties, several species were
identified for which there was a possibility of occurrence within the area of
potential effect for pipeline maintenance construction, routine ROW maintenance,
hydrostatic pressure testing, and the remaining integrity related activities. The
area of potential direct effects for the Phase I activities includes the immediate,
existing 50-foot wide ROW, and those additional construction specific adjacent
areas up to 100 feet either side of the ROW, and other areas that could
reasonably and foreseeably be affected by the subject pipeline maintenance,
construction, and testing activities (ie., hydrotest releases). No areas of indirect
effect are anticipated due to avoidance and minimization procedures.
A biological investigation was conducted along the pipeline ROW and
immediately adjacent lands to determine if these species and/or suitable habitat
were present within the area of concern. Horizon conducted habitat
assessments and survey efforts throughout April, May, and June 1999 from
990144BA.v-6
17
- 2/14/2000

<<<PAGE 434>>>

Kimble
18ULS1
Hays
x3321
0 0o
ste even are mercies
192282623002
Harris
30-92 САлЕрих ИЗ оласТЕЯ
Gillespie
3003
Henbanensi
Fayette
densitem
sida
Ector
2ovi
2233
Table 1: Federally-listed Threatened or Endangered Species which occur in counties traversed by Longhorn Pipeline
Crockett
epot linen
Crane
00г)
soys boons
state br
2005100228/008
nucol Sne
Blanco
Sub be sha
X - Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
xx
20000000 254 волар и 1610р
Source of Species: US Fish and Wildlife Service
Bastrop
PDL - Proposed to be De-listed
E - Listed Endangered
Austin
*
T - Listed Threatened
Species - Federal Classification
American alligator - TSA
Attwater's prairie-chicken - E
Barton Springs salamander - E
Bee Creek Cave harvestman - E
Bald eagle - T(PDL)
Black-capped vireo - E
Bone Cave harvestman - E
Clear Creek gambusia - E
Comal Springs dryopid beetle - E
Comal Springs riffle beetle - E
Devil's River Minnow - PE
Golden-cheeked warbler - E
Kretschmar Cave mold beetle - E
Navasota Ladies-tresses - E
Fountain darter - E
Houston toad - E
Interior least tem - E
San Marcos gambusia - E
San Marcos salamander - T
Texas blind salamander - E
Texas prairie dawn-flower - E
Tobusch fishhook cactus - E
Tooth Cave ground beetle - E
Tooth Cave pseudoscorpion - E
Texas snowbells - E
Texas wild-rice - E
Tooth Cave spider - E
Whooping crane - E

<<<PAGE 435>>>

Downstream
Waller
0 x
Upton
Travis
0 0 0=
Schleicher
Table 1: Federally-listed Threatened or Endangered Species which occur in counties traversed by Longhorn Pipeline
Reagan
Menard
Mason
X - Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
Source of Species: US Fish and Wildlife Service
Llano
PDL - Proposed to be De-listed
E - Listed Endangered
T - Listed Threatened
Lee
Species - Federal Classification
American alligator - TSA
Attwater's prairie-chicken - E
Barton Springs salamander - E
Bee Creek Cave harvestman - E
Bald eagle - T(PDL)
Black-capped vireo - E
Bone Cave harvestman - E
Comal Springs dryopid beetle - E
Clear Creek gambusia - E
Comal Springs riffle beetle - E
Kretschmarr Cave mold beetle - E
Devil's River Minnow - PE
Golden-cheeked warbler. - E
Navasota Ladies-tresses - E
Fountain darter- E
Houston toad - E
Interior least tem - E
San Marcos gambusia - E
San Marcos salamander - T
Texas blind salamander - E
Texas prairie dawn-flower - E
Tobusch fishhook cactus - E
Tooth Cave ground beetle - E
Tooth Cave pseudoscorpion - E
Texas snowbells - E
Texas wild-rice - E
Tooth Cave spider - E
Whooping crane - E

<<<PAGE 436>>>

Crane Station, Crane County, Texas to Highway 6 in Houston, Harris County,
Texas. The portion of the pipeline extending from Crane to El Paso is not subject
to this BA since none of the subject activities will apply to that pipeline segment
area. Species which potentially occur in or near waterways downstream of the
pipeline were assessed based on literature and agency file information. In 1998,
the Service concurred with Longhorn's conclusion that the project was not likely
to adversely affect species and habitat along the pipeline segment between
Crane and El Paso (a copy of the Service's concurrence is included in the
accompanying Project Documentation Appendix at Tab 13).
As indicated in Table 1, many species have been excluded from further
consideration due to Horizon=s determination that the activities are not likely to
adversely affect these species. S
Horizon's determination was based on
information regarding distribution of the various species obtained from various
published, agency file, or personal communication sources such as the Texas
Parks and Wildlife Department, the US Fish and Wildlife Service, recognized
experts for certain species, published species documentation, and published
reference books. Those species indicated by an AO@ in Table 1 have been
determined not likely to occur within the area of potential effect. Those additional
species indicated by an AM@ are migrants that would not likely be affected.
Species indicated by an AX@ are those determined by Horizon-s studies to occur
or possibly occur in the area of potential effect for present purposes. Those
species are addressed in more detail below and on attached maps.
Texas Prairie Dawn-flower (Hymenoxys texana)
Small, delicate annual to 6 inches tall with single or branching stems.
Small yellow flowers blooming in late March to early April. Occurs in sparsely
vegetated areas of fine-sandy compacted soil. Specifically, the species occurs in
the northern part of the Gulf Coastal Prairie, where it is found in poorly drained
depressions or saline swales around the periphery of low, natural mounds (mima
mounds) in open grasslands. These mostly barren areas are sparsely vegetated,
and the soil is often covered with a blue-green alga (Nostoc sp.). It can also
occur on disturbed soils such as rice fields, vacant lots, and pastures if the soil
structure remains relatively intact.
990144BA.v-6
20
- 2/14/2000

<<<PAGE 437>>>

An assessment of potentially suitable habitat for the prairie dawn was
conducted by Horizon in early June 1999 along the Longhorn pipeline ROW in
western Harris and eastern Waller counties from the Satsuma Station on the
west edge of Houston to near Monaville in Waller County. Three areas along the
ROW, one in Waller County and two in Harris County, exhibited native range
conditions with suitable soils that could be considered potentially suitable habitat
areas for the prairie dawn (Figures 4 to 12). All other areas along the pipeline
within the area investigated had been converted to row crop (corn), monoculture,
hay or grazing pasture, or disturbed for land development. A survey for the
prairie dawn has not been conducted within the potentially suitable habitat areas
to confirm its presence or absence. Longhorn will conduct a survey of the ROW
within the potential habitat areas in March of 2000 to determine if the prairie
dawn is present, and if so, its distribution and abundance.
Navasota Ladies-tresses (Spiranthes parksil)
The Navasota Ladies-Tresses (NLT) occurs primarily in moist, sandy soils
in small openings amongst Post Oak Savannah vegetation associated with the
Navasota, Brazos, and Trinity River drainages. The plant has previously been
found in Brazos, Burleson, Freestone, Grimes, Fayette, Leon, Madison, Jasper,
Robertson, and Washington counties. NLT are typically found on erosional
remnants between rills in slightly to moderately eroded areas along minor
intermittent tributaries of the Navasota, Brazos, and Trinity Rivers. NLT grows on
sandy loam soils and is often associated with post oak, blackjack oak, yaupon,
slender bigelowia (Bigelowia nuttallii), and Spiranthes cernua. The species has
also been recorded in open savannahs and shrublands that have experienced
little or no grazing pressure, and in hillside seepages.
990144BA.v-6
21
_ 2/14/2000

<<<PAGE 438>>>

Louisiana
FIGURE 4
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
SHEET LOCATION MAP
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
LONGHORN PIPELINE
Gulf of Mexico
FIGURE 5
HOUSTON
HARRIS
WALLER
FIGURE 6
AUSTIN
FIGURE 8
FAYETTE
FIGURE 7
RAVIST
AUSTIN
BASTROP
HAYS
FIGURE 10
LLANO
BLANCO
GILLESPIE
MASON
FIGURE 9
MENARD
KIMBLE
FIGURE 11
SCHLEICHER
12°
NOT TO SCALE
FIGURE
REAGAN
CROCKETT
LONGHORN REFINED PRODUCTS
APPROXIMATE CITY LOCATIONS FOR
Mexico
2: TEXAS NATURAL SUE 10197)
(http://www.tnris.state.tx.us/data__az.html),1998
UPTON
PIPELINE
REFERENCE
ECTOR
ODESSA
CRANE
CRANE
EXPLANATION
CRANE

<<<PAGE 439>>>

FIGURE 5
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
DT-20a(K)
DAWN-FLOWE!
HARRIS
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT Bufo houstonenses
GOLDEN-CHEEKED WARBLER
(Dendracia chrysoporio)
BAD CADAD MIRED
(SPOTA POES -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
ROSTER OTT
TEXAS PRAIRIE
-10
- CR-/
- SURGE 4
PIPELINE/
COUNTY BOUNDARY
199 HIGHMAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
HERBON AGAIN LOCATIONS
LONGHORN PIPELINE
ROADS
BRIDGES
CEMETERY
—I1P-2516 MANTENICE CONSTRUCTION
TEXAS PRAIRIE DAWN-FLOWER
WALLER
EXPLANATION
##### RAILWAYS
-
-50756-3
1.5
MILES
PINE ISLAND
4. TROT: HOREON SNORIN SE IS 1909AE
8. HORIZON MPONMONTAL SERMICES, INC, SITE BMESTIGATION (JIME 1990)
5 PER TO PASS ME PAL BED MIS PUNTS OF
159
2. RESOURCES ORATION SET 1700
2. TS NEH MOD BIA SONG 10D, OF TEAS
529
SON SAMS

<<<PAGE 440>>>

USTIN,
WASHINGTON
FIGURE 6
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
NAVASOTA LADIES-TRESSES
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Condo CO MARGUER
BAD CAPPED VIREO
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
257
OLDENBURI
- CR-1
- SURGE 4
EE HONY OR MANOR ROMOS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— LIP-2546 MICATONICE CONSTRUCTION
EXPLANATION
- SITE 6-3
NAVASOTA LADIES-TRES:
FAYETTE
MILES
6. HORIZON EIMIRONMENTAL SERNCES, INC, SITE IMMESTGATION (JUNE 1999)
* PONTES TREAD ELBERT MATE PUNTS OF
2. RESOURCES TORTON SISTEN 37/
2. TAS ABA MO BE SERE 1OED, OF TOUS.
LEE
SOURCES

<<<PAGE 441>>>

FIGURE 7
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
SES-TEAS
COLORADO
HOUSTON TOAD
(POTENTIAL HABITAT)
PIPE REPLACEMENT
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - POTENTIAL
HOUSTON TOAD
- DESIGNATED CRITICAL HABITAT
HABITA (Bufo houstonemsis)
BAD CARD VIRED
MAMOTAY POTS-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
-67-1
- SURGE 4
- HIGHWAY OR MAJOR ROADS
BASTROP®
— COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—4P-2516 LOCATTMNICE CONSTRUCTON
EXPLANATION
- SITE 6-3
INC, SITE INSTIGATION (JUNE 1999)
DED MATE PUNTS OF
BUT SERE TOES OF TOAS
1. TOAS NATURAL DE
3. DETERMATION OF CRITICAL
8. HORIZON EMIROMMENTAL SERMICES,
2. Tot COUNTY
4. THREATE P

<<<PAGE 442>>>

FIGURE 8
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
EDWARDS
HAYS
TRAVİS
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Tomotocette tok CTUs
SANSON POTS -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
ONTRIBUTING ZONE
-CR-/
- SURGE 4
DRIPPING
SPRINGS
HIGHWAY OR MAJOR ROADS
• COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
HENDER ANG PETON LOCATIONS
LONGHORN PIPEUNE
GOLDEN CHEEKED MA
RONDS
RAILWAYS
BRIDGES
CEMETERY
—LLP-2516 MANTEMANCE CONSTRUCTION
EXPLANATION
--
######
— SITE 6-8
SITE 6-
PEDES MESTICATIONS, F REGUME
PONCORD SPORES, OF TEUS
6. HORIZON DRONENTAL SERMCES, INC, SITE ESTIGATON (UNE 1999)
* POTES PRES LA SEPT ME FURTS OF
BLANÇO
ME SAMOS

<<<PAGE 443>>>

FIGURE 9
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
BLACK-CAPPED VIREO
BLANCO
• GOLDEN-CHEEKED WARBLER
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
Taco Deto TobacTS
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-/
- SURGE 4
HIGHWAY OR MAJOR ROADS
WARBLER
- COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
MEMBER AS RATIN COCATIONS
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—LP-2516 MANTENNCE CONSTRUCTION
EXPLANATION
— SITE 6-3
Cool
PIPELINE
DIGORED SPECIES NESTIOMONS, EPPELME
ÇILLESPIE
3. OCTEPMATO, OE CEMEM, HA PS AR HT SIR RT
&. HORIZON EMIROMMENTAL SERVICES, MC, SITE INVESTIGATION (JUNE 1999)
SPORTED PRESSED FLOURE DET MIME PUNTS OF
2 TS TO ME BUT SAME TOE OF TENS
LLANO
SAT MATRA SEA
MAP SANCES
4. THREATEN HORROR

<<<PAGE 444>>>

ELINE
LIANO
FIGURE 10
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
E BLACK-CAPPED VIREO
y GOLDEN-CHÉEKED WARBLER
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOTTA TO NOLOTOROMENTAL
GILLESPIE
NAVASOTA LADIES-TRESSES
(Spironthes portsil)
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
LOVEY
CHERRY
2242
GOLDEN-CHEEKED WARBLER
- CR-/
- SURGE 4
COUNTY BOUNDARY
• HIGHWAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTERAMCE CONSTRUCTION
EXPLANATION
!
- S175 6-8
SITE
MASON
MC, SITE IMESTONOM (AME 1990)
DES OF TENS:
MILES
5 PRETE PASS ME UP DEPT ME RUNTS OF
ENTAL SERVES
PIPELINE
QURASS
MAR SOUPOSS
4. THREATENED OR DID
&. HORIZON

<<<PAGE 445>>>

-GILLESPIE
BLACK-CAPPED VIREO
FIGURE 11
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
MASON
0т-90 (K)
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT (Buto houstonensis)
MASOTA PORS-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-/
- SURGE 4
- COUNTY BOUNDARY
→ I HIGHNAY OR MOR ROADS
CITY STREETS -
RIVERS AND STREAMS
NTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— LLP-2546 MOCATIMANCE CONSTRUCTION
1-8 ALIS
SURGE 4.
871
EXPLANATION
иннинин
KIMBLE
- SITE 6-3
LONDON
TOBUSCH FISHHOOK CACTUS
3480 YATES
EACUP
POUNCERED SORDES oF TEMS.
6. HORIZON ENMRONMENTAL SERVICES, IMC., SITE IMVESTIGATION (JUME 1999)
SO PARCE PROTEST MADE PLANTS OF
MENARD
HAS SOURCES
I BEATENED OR EHDAN
2. THREATPNED AND

<<<PAGE 446>>>

BLACK-CAPPED VIREO
FIGURE 12
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
CACTÚS LOCATION
SITE 8-3
CPGB-s :
KIMBLE
CATHODIC PROTECTION ENHANCEMENTS
SURGE PRESSURE PROTECTION
HOUSTON TOAD - DESIGNATED
HABITAT (Bufo houstonents
COLDEN-CHEEKED WARBLER
Dendrocio chrysaparna
LAVASOTA LADIES-TRESSES
TOBUSCH FISHHOOK CACTUS
Spiranthes pantsi
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
- CR-1
- SURGE 4
MENARD
HEADER ANSARI LOCATIONS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
CITY STREETS
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTELANCE CONSTRUCTION
EXPLANATION
— SITE 6-2
B-8 JUIS
ANGERED SPECES, MISTATORS, EZ PROLAE
6. HORIZON EMRONMENTAL SERMCES, INC, SITE MESTONTOM (JUNE 1990)
5 PEAS TEE PRESIDE ST MINE PUNTS OF
2 RESOURCES TORMATION SITE 15P
ORVETT
SUTTON
SCHLEICHER
" Copperas
MAR SORCES
A THREATE

<<<PAGE 447>>>

In Fayette County, the species is known from one small population
approximately 6 miles south of the pipeline and 2 miles north of the town of
Fayette. Based on analysis of soil distribution, vegetative cover, physiographic
setting, and field assessment by Horizon in November of 1999, two small areas
of potential habitat for NLT are present along the pipeline corridor (Figures 4 to
12). No surveys for the species have been conducted along the pipeline.
Longhorn will conduct a Fall survey (15 October to 15 November, 2000) for this
species within the ROW if suitable climatic conditions occur to determine the
presence or absence of this species, and if present, its distribution and
abundance.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii)
Rounded, biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5
inches in diameter. There are 3 to 5 central spines with the upper 2 to 3 erect
and straight and the lower central spines hooked at the tip and spreading.
Occurs on limestone gravels of stream terraces, limestone ledges, ridges, and
openings on the rocky hills of live oak - juniper woodlands. The Tobusch
fishhook cactus has been documented in Kimble County. An assessment of
potentially suitable habitat and pedestrian survey for the cacti was conducted by
Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble
County, and no specimens were observed within the ROW. However, one
Tobusch fishhook cactus was observed approximately 50 feet north of the
cleared ROW (Figures 4 to 12). Longhorn will conduct a blooming period survey
(March to April 2000) within the ROW throughout Kimble County to determine the
species' distribution and abundance.
Houston Toad (Bufo houstonensis)
The Houston toad is 2.0 to 3.5 inches long with general coloration varying
from light brown to gray or purplish gray, sometimes with green patches. The
pale ventral (underneath) surfaces often have small dark spots. The toad is a
terrestrial amphibian associated with deep sandy soils within the Post Oak
Savannah vegetational area of east central Texas. The vegetation type of
currently known Houston toad sites can typically be described as pine or oak
990144BA.v-6
31
- 2/14/2000

<<<PAGE 448>>>

woodland or savannah, with native bunchgrasses and forbs (flowering plants)
present in open areas.
For breeding, including egg and tadpole development, Houston toads also
require still or slow-flowing bodies of water that persist for at least 30 days. The
source of ephemeral or permanent water should be located within one-half to
three-quarters miles of the toad=s hibernation/foraging habitat (deep sands
supporting woodland or savannah).
Critical habitat was designated for the Houston toad 31 January 1978, of
which a portion of Longhorn pipeline traverses through in Bastrop County
(Figures 4 to 12).
The Longhorn Pipeline ROW within the Houston toad Critical Habitat area
is immediately adjacent to the Phillips EZ Pipeline ROW which Horizon studied in
1991 for endangered species. As part of Horizon's studies, a Houston toad
survey was conducted along the EZ Pipeline corridor in 1991 by Dr. James R.
Dixon of Texas A&M University with negative results, although minor potential
habitat areas were noted (Horizon, 1991). Horizon conducted a reevaluation of
suitable habitat along the Longhorn Pipeline ROW within Bastrop County. The
field reconnaissance was conducted on 2 June 1999 from the Colorado River,
southeast of Bastrop, to FM 2104. Within the designated Critical Habitat,
portions of the area along the pipeline had been cleared and planted in improved
grasses. These areas were determined to be unsuitable for Houston toad
occupation.
Based on field observations, and confirmation by the Service, it was
determined that two areas of potentially suitable habitat existed along and
adjacent to the pipeline ROW. One area included Buescher State Park from
approximately 1/2 of a mile to the east of the eastern boundary of the park
westward to near Highway 71. The majority of this area contained a moderately
thick understory with all drainages flowing south toward the Colorado River.
The second area began approximately 500 feet to the west of FM 2104
and extended westward approximately 3/4 of a mile. This area contained two
stock tanks with the majority of the surrounding area exhibiting a moderately
990144BA.v-6
32
- 2/14/2000

<<<PAGE 449>>>

thick understory and pine re-growth. The drainages in this area also flowed to the
south toward the Colorado River.
One or more additional spring surveys (as acceptable to the Service) for
the toad will be conducted along and downstream of the pipeline to determine the
presence or absence of toads and their overall distribution and abundance.
Golden-cheeked Warbler (Dendroica chrysoparia)
The golden-cheeked warbler (GCW) is a small, migratory songbird, 4.5 to
5 inches long, with a wingspan of about 8 inches. The male has a black back,
throat, and cap, and yellow cheeks with a black stripe through the eye. Females
are similar, but less colorful. The lower breast and belly of both sexes are white
with black streaks on the flanks. Typical nesting habitat is found in tall, dense,
mature stands of Ashe juniper (cedar) mixed with trees such as Texas (Spanish)
oak, Lacey oak, shin (scalybark) oak, live oak, post oak, Texas ash, cedar elm,
hackberry, bigtooth maple, sycamore, Arizona walnut, escarpment cherry, and
pecan. This type of woodland generally grows in relatively moist areas such as
steep-sided canyons and slopes. A mix of juniper and deciduous trees on the
slopes, along drainage bottoms, and in creeks and draws provide an ideal mix of
vegetation for birds. Warblers are also occasionally found in drier, upland
juniper-oak (i.e. live oak, post oak, blackjack oak) woodlands over flat
topography.
An assessment of potentially suitable habitat and surveys for the GCW
was conducted by Horizon in April and May 1999 along the Longhorn pipeline
ROW from Austin, Texas, to the Mason/Kimble County line. Although no
potentially suitable habitat areas were observed within the Longhorn ROW,
several areas were located adjacent to the previously cleared permanent ROW.
All areas were surveyed by Horizon a minimum of 5 times during April and May
on days with favorable weather conditions for bird activity, per US Fish and
Wildlife Service guidelines (FWS, 1994). Surveys were conducted on 8, 9, 12,
27,28 April, and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres
were spent at each site, based on habitat size. No GCWs were found to be
utilizing any of the potentially suitable habitat areas on or immediately adjacent to
the ROW. One to two additional spring breeding season surveys (as acceptable
990144BA.v-6
33
- 2/14/2000

<<<PAGE 450>>>

to the Service) will be conduced for the GCW along and adjacent to the ROW
within the potential habitat areas to determine habitat utilization and overall
distribution and abundance.
Black-capped Vireo (Vireo atricapillus)
The black-capped vireo (BCV) is a 4.5 inch long, insect-eating songbird.
Mature males are olive green above and white below with faint greenish-yellow
flanks. The crown and upper half of the head is black with a partial white eye-
ring. The iris is brownish-red and the bill black. The plumage of the female is
duller than the male. Females have a dark slate gray head. In Texas, vireo
habitat is found on rocky limestone soils of the Edwards Plateau, Cross Timbers
and Prairies, eastern Trans-Pecos, and, to a limited extent, on igneous soils in
the Chisos Mountains. BCVs require shrub vegetation reaching to ground level
for nesting cover. They typically nest in shrublands.
An assessment of potentially suitable habitat and surveys for the BCV was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW
from Austin, Texas to Crane County. Potentially suitable habitat areas were
observed within the Longhorn ROW as well as several areas located immediately
adjacent to the previously cleared permanent ROW. All areas were surveyed by
Horizon a minimum of 5 times during April and May on days with favorable
weather conditions for bird activity, per US Fish and Wildlife Service guidelines
(FWS, 1994). Surveys were conducted on 8, 9, 12, 27, 28 April, and 3, 11, 19
May. An equivalent of 4 person-hours per 100 acres were spent at each site,
based on size. No BCVs were found to be utilizing any of the potentially suitable
habitat areas on or immediately adjacent to the ROW. One to two additional
spring breeding season surveys (as acceptable to the Service) will be conduced
for the BCV along and adjacent to the ROW within the potential habitat areas to
determine habitat utilization and overall distribution and abundance.
Bald Eagle (Haliaeetus leucocephalus)
The bald eagle is a migrant and winter resident in Texas. The bald eagle
was recently down-listed from endangered to threatened due to successful
conservation efforts and is now proposed for de-listing. Migrating and wintering
990144BA.v-6
34
- 2/14/2000

<<<PAGE 451>>>

bald eagles typically arrive in Texas in November and depart sometime in
February. They are found primarily in association with reservoirs, rivers or other
large bodies of water where they feed on fish, carrion, and waterfowl. Nesting
bald eagles in Texas are found in the eastern portion of the state and along the
coastal plain as far south as Calhoun and Refugio counties. No bald eagle nests
have been identified near the pipeline ROW, however, bald eagles may occur
along major waterways (Brazos and Colorado rivers, or major tributaries with
impoundments) downstream of the pipeline corridor.
The Federal Register, Volume 64 No. 128 (Tuesday, July 6, 1999; Page
36454) puts forth a proposed rule to remove the bald eagle from the List of
Threatened and Endangered Wildlife In the Lower 48 States of the United States
and de-listing is expected in the near future. The action is proposed because
available data indicates that the species has recovered.
Interior Least Tern (Sterna antillarum athalassos)
Premier nesting sites for the interior least tern are salt flats, broad
sandbars, and barren shores along wide, shallow rivers. Important breeding
habitat characteristics include: (1) presence of bare or nearly bare ground and
alluvial islands or sandbars for nesting; (2) availability of food (primarily small
fish); and (3) favorable water levels during the nesting season (so nests remain
above water). They usually nest on sites devoid of vegetation, but have been
found in areas with an average of 11 to 30% vegetative cover, composed of
grasses, shrubs, and trees and ranging from 1 to 3 feet in height. Vegetation, if
present, is usually located well away from the colony, with the exception of
bugseed, eastern cottonwood, and sandbar willow. As natural nesting sites have
become sparse, birds have used sand and gravel pits, ash disposal areas of
power plants, reservoir shorelines, gravel levee roads, and other manmade sites.
The typical nesting period for the least tern in Texas is mid-April to mid-August.
While the interior least tern has not been documented along the pipeline
corridor, potential habitat for the tern is present downstream of the pipeline along
several major waterways including the Brazos, Colorado, Llano, and James
Rivers, and Squaw, Beaver, and Sandy Creeks. The seasonal occurrence
990144BA.v-6
35
- 2/14/2000

<<<PAGE 452>>>

(spring and summer) and potential nesting of least terns is possible in these
areas.
Conclusions
In conclusion, of the 29 federally listed species of potential occurrence in
counties traversed by the Longhorn Pipeline between Houston and Crane, only 8
of those species are documented or estimated to occur within the area of
potential effect for the pipeline safety projects due to the presence of potentially
suitable habitat. None of the species have been documented to occur within the
existing ROW of the pipeline, but several have been documented within
proximity, either by suitable habitat, or by sightings of individuals. Additional
surveys for the Texas prairie dawn-flower, Navasota ladies-tresses, Tobusch
fishhook cactus, Houston toad golden-cheeked warbler, and black-capped vireo
will be conducted to further document their presence or absence and population
densities in the vicinity of the pipeline. These surveys must be conducted during
certain narrow seasons, and therefore, can only be conducted once per year.
The survey season for the prairie dawn, fishhook cactus, and Houston toad is
February to April. The season for the GCW and BCV are late March to late May.
The season for the ladies-tresses is October to November.
990144BA.v-6
36
• 2/14/2000

<<<PAGE 453>>>

4.0
PROJECT DESCRIPTION
Longhorn will
implement various pipeline safety and integrity
enhancements for the pipeline that include various methods of pipeline testing,
anomaly investigations, ROW maintenance, section replacements, cathodic
protection enhancements, and pipeline lowerings. Table 2 contains a summary of
the proposed projects relating to clearing, maintenance construction, hydrostatic
testing, and other integrity-related projects that are addressed in this BA (ref.
Project Documentation Appendix at Tab 2).
Following is a general description of these safety enhancement projects
and the methods by which they will be implemented for the Longhorn Pipeline
System. Additional detail may be found in Construction Specification CS4
contained in the accompanying Project Documentation Appendix at Tab 4.
4.1
RIGHT-OF-WAY CLEARING AND MARKING
Longhorn has committed to bring the surface of the ground within the
ROW into "excellent condition" in order to facilitate surveillance prior to startup of
the pipeline (ref. Project Documentation Appendix at Tab 2). Excellent condition
is that condition which provides a clear line of sight for aerial and ground
surveillance patrols in order to effectively monitor and inspect the ground surface
along the ROW. A clean and clearly marked ROW provides a distinctive line of
demarcation, indicating a change in land use, where surrounding terrain is
natural or heavily developed.
ROW maintenance will include mowing, brush-hogging, back-dragging, or
hand trimming of tall grass or woody re-growth, trimming of tree canopies
overhanging the ROW, setting signs, marking points of intersection (horizontal
bends) in the pipeline with PVC posts, and painting cross-fence posts.
ROW mowing is performed by a twin-blade mower or a brush-hog drawn
by a tractor, to a height between two and four inches. Back-dragging is a method
of clearing in rocky terrain; back-dragging involves pulling a dozer blade
backwards across the ground surface which has the effect of bending vegetation
over at the ground surface. Back-dragging typically does not result in the
990144BA.v-6
37
- 2/14/2000

<<<PAGE 454>>>

uprooting of vegetation. Rather, the vegetation is bent or broken just above the
ground surface. Back-dragging is used only in areas where rocks on the surface
pose a risk of damage to a mower or brush-hog. Weedy vegetation around
surface facilities such as valve settings is at times treated with herbicides such as
Roundup and Rodeo.
Hand trimming involves line trimmers, chain saws, and similar hand-held
equipment.
Tree canopies are trimmed by workers, using chain saws, that are
raised within reach of the canopies by a man-lift.
Steel sign posts are typically set by driving the posts directly into the
ground. PVC posts are set into shallow holes dug by post-hole digger. In limited
circumstances such as when vandals repeatedly remove pipeline markers, sign-
posts are dug by post-hole digger to allow the posts to be set into concrete.
Clearing within areas identified as endangered species habitat will not
result in any ground disturbance because only mechanical or hand cutting will be
employed. The term ground disturbance is intended to mean soil disturbance
that would result from grubbing brush and tree stumps; rather, they will be cut at
ground level. In limited circumstances, stumps directly over the pipeline, which
could have adverse effects on the pipe, will be hand-treated with minimal
amounts of non-aromatic and non-persistent herbicide to retard re-growth.
Herbicides will be applied in accordance with EPA-approved label directions.
These activities are routine and are conducted periodically by pipeline
operators in the United States.
All areas of the ROW are subject to periodic clearing form time to time.
ROW clearing occurs at intervals that depend upon the rate of vegetation growth,
typically averaging once per year in arid and semi-arid territory (generally, from
Austin to Crane) and typically averaging twice per year in territory with greater
rainfall (generally, Houston to Austin). Further, metropolitan areas may be
mowed as frequently as monthly to meet municipal ordinance requirements and
in response to landowner requests. ROW clearing will be conducted on a
schedule that avoids impacts to species; for example, Houston toad habitat will
be avoided during the warmer seasons (February through November) when
990144BA.v-6
38
- 2/14/2000

<<<PAGE 455>>>

toads are typically active and potentially upon the surface of the ROW, and plant
habitat areas are avoided during the respective blooming seasons.
4.2
PIPELINE MAINTENANCE - CONSTRUCTION PLANNING
Prior to project engineering and scheduling, each site is surveyed by
qualified personnel to determine whether or not the activity (a) may affect
threatened or endangered species and habitat, (b) may cause disturbance of
cultural resources, (c) may be subject to Clean Water Act Section 404 (U.S.
Army Corps of Engineers jurisdiction over dredge and fill materials in waters of
the United States), or (d) may be subject to other federal, state or local laws,
regulations or ordinances. Appropriate authorizations are obtained (such as this
consultation), and necessary requirements are identified and incorporated into
project planning and engineering documentation.
Project engineers and technicians perform site inspections to identify site-
specific conditions and features that require consideration in project planning,
such as site ingress/egress routes, workspace requirements, spoil management,
equipment storage, servicing and parking needs, and the like (ref. Tab 5,
Environmental Protection Plan, and Tab 6, Storm Water Pollution Prevention
Plan in the accompanying Project
Documentation Appendix). Such
considerations are incorporated into project planning and engineering activities.
Unless required by the particular project or by site conditions, workspace is
limited to the established ROW. Where workspace is required beyond the limits
of the established ROW, those areas have been incorporated into project
documentation.
990144BA.v-6
39
- 2/14/2000

<<<PAGE 456>>>

Comments
Avoid February through April
Avoid February through April
Avoid February through April
Avoid October through November
Avoid October through November
Avoid February through October
Avoid February through October
Avoid March 15 through September 1:
Avold March 15 through September 1.
Avoid March 15 through September 1
Avoid March 15 through September 1
Avoid March 15 through September 1
Avoid March 15 through September 1
Avold March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avold March through July
Avold March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Avoid March through July
Species
Texas Prairie Dawni
Texas Prairie Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Navasota Ladies-Tresses
Houston Toad
Houston Toad ::
EA Contributing Zone
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Black-Capped Vireo
Black-Capped Vireo
Tobusch Fishhook Cactus
TABLE 2
2000 MAINTENANCE ACTIVITIES
TESTING AND CLEARING
LONGHORN PIPELINE
County
Harris
Harris
Waller
Fayette
Fayette
Bastrop
Bastrop
Travis/Hays
Hays
Hays
Hays
Hays
Hays/Blanco
Blanco
Blanco
Blanco
Blanco
Gillespie
Gillespie
Gillespie
Gillespie
Gillespie i
Gillespie
Mason
Mason
Mason
Mason
Mason
Mason
Kimble
End Station
2279+20
2411+20
2831+84
5128+64
5948+80
6638+72
6864+00
9961+60
9674+72
9762+72
9926+40
10036+40
10199+20
10461+44
11036+96
11105+60
11441+76
11751+52
11821+92
12149+28
12606+88
12631+52
12728+32
12953+60
13110+24
13217+60
13305+60
13437+60
13578+40
16329+28
Right-of-Way Clearing (Maintenance) - See Comments for Avoidance Timing
Begin Station
2013+44
2310+88
2684+00
5095+20
5936+48
6600+00
6723+20
9152+00
9657+12
9724+00
9850+72
9945+76
10164+00
10266+08
11008+80
11080+96
11295+68
11691+68
11791+28
12114+08.
12513+60
12596+32
12633+28
12921+92
13043+36
13203+52
13277+44
13381+28
13513+28
14476+00
Site
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way 50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-or-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50*)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)
Right-of-Way (50)

<<<PAGE 457>>>

Comments
Avoid March 15 through September 1
nvestigation of possible dent; access from
improved road to ROW, then 1000 feet down
nvestigation of possible anomaly: access
from improved road to ROW, then 3000 feet
Site entry only, via 5936+48-5948+80
Lowering / Replacement; access. under
mproved road to ROW, then 1000 feet down
Lowering / Replacement; access from
Lowering / Replacement: access from
improved road to ROW, then 1000 feet down
improved road to field road, then via field road
Lowering / Replacement: access from
Lowering / Replacement; access from
improved road to ROW, then 600 feet down
Lowering / Replacement; access 800 feet
down ROW from Site LPP-2751
Lowering / Replacement; access from
improved road to ROW, then 2500 feet down
Investigation of possible dent; access from
improved road and dirt road to ROW, then
nvestigation of possible dent; access from
improved road to ROW, then 1000 feet down
nvestigation of possible dent; access from
Improved road, 3700 feet of unimproved road
to ROW. then 7000 feet to project site
ROW
down ROW
development
ROW
to project site.
ROW to project site
1300 feet down ROW
ROW
ROW
Species
Black-Capped Vireo
Texas Prairie-Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Barton Springs Salamander (EA Contributing Zone)
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Black-Capped Vireo
Black-Capped Vireo
EA Contributing Zone
County
Kimble
Harris
Harris
Fayette
Travis
Travis
Travis
Hays
Blanco
Blanco
Gillespie
Gillespie
Gillespie
Mason
Travis
End Station
15234+56
2073+52
2737+37
5931+12
9197+24
9222+24
9488+24
9807+42
10373+24
10381+24
11725+71
12659+39
12682+16
14012+73
Begin Station
15153+60
2073+52
2737+37
5926+74
9195+80
9220+80
9483+31
9807+10
10369+55
10380+60
11725+22
12659+39
12682+16.
14012+73
Hydrostatic Pressure Test - Header Installation Locations
9338+50
Site
Maintenance Construction
Right-of-Way (50")
DT-20a (K)
Crossing (K)
2008 (K) Ph. 1
LPP-2467
LPP.2471
LPP-2546
LPP-2627
LPP-2751
LPP-2753
2016
DT-12a (K)
DT-11
DT-9a (K).
Site 5-5

<<<PAGE 458>>>

Comments
CP Ground Bed - Kimble County Station
Coating Reconditioning
Coating Reconditioning
Coating Reconditioning
Species
Near Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Black-Capped Vireo
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Tobusch Fishhook Cactus
Texas Prairie Dawn
Texas Prairie Dawn
Navasota Ladies-Tresses
Barton Springs Salamander (EA Contributing Zone) and
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler and Black-Capped Vireo
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler
Golden-Cheeked Warbler and Black-Capped Vireo
Golden-Cheeked Warbler and Black-Capped Vireo
Black-Capped Vireo
Tobusch Fishhook Cactus and Black-Capped Vireo
Tobusch Fishhook Cactus and Black Capped Vireo
Texas Prairie Dawn
Houston Toad
Houston Toad
Tobusch Fishhook Cactus
County
Blanco
Blanco
Blanco
Mason
Kimble
Kimble
Kimble
Kimble
Harris-Waller
Waller
Fayette
Travis-Hays
Hays-Blanco
Blanco
Blanco
Blanco
Blanco-Gillespie
Gillespie
Gillespie-Mason
Mason
Mason
Kimble
Kimble
Harris
Bastrop
Bastrop
Kimble
2128+97
6612+99
7085+24
End Station
2415+50
3385+00
5966+47
10163+00
10265+00
10504+50
11188+00
11385+50
12033+73
12360+00
13040+00
13435+00
13910+00
14606+00
16992+40
15592+90
10163+00
10265+00
10742+50
11188+00
11385+50
12033+73
12360+00
13040+00.
13435+00
14373+00
2127+97
14606+00
6609+49
7084+74
Begin Station:
10163+00
10280+00
11385+50
13435+00
14606+00
15143+00
15586+00
16167+00
1802+63
2415+50
5039+00
9647+00
15592+90
Hydrostatic Pressure Test - Test Segments
Cathodic Protection Enhancements
Site
Site 6-1
Site 6-2
Site 6-6
Site 7-3
Site 8-1
Site 8-2
Site 8-3
Site 8-4
Segment 2
›Section 1
›Section 2
Segment 3
Section 2
›Section 6
Surge Pressure Protection
Segment 5.
Segment 6
> Section 1
> Section 2
›Section 4
> Section 5.
›Section 6
›Section 7
Segment7
›Section 1
›Section 2
›Section 3.
›Section 6
Segment 8 (all)
CR-1
CRA
CR-5
CPGB-5

<<<PAGE 459>>>

P 42 (aloiasua pota o, pus berapie is0 2:
:2 AN25 CACOODCE DuNG. шо д
: w Й becseegepe extnogou of Aru0o20.
DA caco sabuo anioos Osgow S s 0020
.. i. god me bbonte noucu po erockhon
Bypass Valve - Liano River East Bank; Same
Location as Hydrostatic Test Header Location,
s0 monic no s000sa0 at a
8
¡ oise to omel oi obreco biba.
mos miepentee sust uecoeism sit.et
600.
r gognno tuondu bicly sompue i
homo grin bioleg ais coucy
pes ga. piar exebueur co.coon
.23-
.3CS0 32 ir moa pA 700 i 0u0
Species
Tobusch Fishhook Cactus
O4 2!
•.txcile sucotubaer
: a00 0 00l00ne) touecs Colp
piespo Biotect pear wansdos
trciecr bpumuo msi
•A .
:3G
County
Kimble
280
s.::00.sm1bou e bebstey o
spo bucioct
aLoDü:
3 LeME0 A O3DeOU:
End Station
14606+51
amoura ne sioleci
7 ue pipee eug ynoigee
Begin Station
14606+51
W500 wedmustene
iiK:W0N S.00ORDU
Site
2 JGane
Surge 4.
nosge sednpen
its pudneuce o exeup)
S слома
higig roosgon sisb.

<<<PAGE 460>>>

Workspace beyond the limits of the established ROW may be required for
a number of reasons. First, avoidance of habitat or the natural terrain along one
side of the ROW may necessitate expansion of workspace along the opposite
side of the ROW. Second, a sloping surface gradient at a project site may require
that spoil removed from the pipeline trench be stockpiled with a wider base,
extending off of the ROW, than would be required at a project site with a level
surface. Further, a project to lower or replace pipe at a creek crossing may
require water diversion measures that necessitate a workspace wider than the
established ROW. In addition, though project equipment is typically aligned
along the existing pipeline ROW, project site conditions such as size, shape
and/or slope may require that equipment be centralized in an equipment
marshalling area (typically 25 ft. wide by 100 ft. long). for temporary storage,
security and/or service.
Biological surveys encompass both areas of potential surface disturbance
and areas within the zone of potential indirect construction impacts, such as
noise.
In addition, applicable project best management practices (BMPs) are
identified at this stage of project planning and incorporated into planning
documentation.
A Project Construction Plan is prepared for each individual project location
to document project planning. The Project Construction Plan contains the
following sections of detailed information:
a.
Description of Work for the Project
b. Responsibilities and Authorities
Safety Requirements
d.
Job Contacts and Notification Requirements Matrix
e.
Pre-Job Training Requirements
a.
Environmental Protection
b.
Project Schedule
C.
Forms / Documents Required
a.
Chronological Sequence of Events
b.
Appendices as follows:
i.
Appendix 1 - Location Map
ii. Appendix 2 - Drawings, Calculations, and
990144BA.v-6
43
- 2/14/2000

<<<PAGE 461>>>

ili.
Specifications
iV.
Appendix 3 - Environmental Protection Plan
V.
Appendix 4 - Storm Water Pollution
Vi.
Prevention Plan
vii.
Appendix 5 - Safety Procedures Document
vili.
Appendix 6 - Sample Forms
An example Project Construction Plan (Site LPP-2627, pipeline
lowering/replacement in Hays County, Texas) is included in the accompanying
Project Documentation Appendix, at Tab 3, for reference. A Project Construction
Plan relating to each project identified in Table 2 is presently under development;
Longhorn will provide to the Service a copy of each Project Construction Plan as
it is completed.
Project BMPs are defined as procedures and specifications by which
environmental controls will be implemented and include such items as
sedimentation and erosion controls, reclamation procedures, minimization and
avoidance procedures, inspection and reporting procedures, spill containment
and cleanup procedures, procedures for addressing unforeseen circumstances,
procedures for addressing foreseen, but unpredictable circumstances, and
others. Project BMPs are identified and adapted from technical guidance
manuals generally accepted as providing the appropriate environmental
protection measures, such as the Texas Natural Resource Conservation
Commission (TNRCC) technical guidance manual, Federal Energy Regulatory
Commission (FERC) Environmental Guidance Manuals, and the City of Austin
Environmental Criteria Manual. BMPs are incorporated within the Longhorn
Storm Water Pollution Prevention Plan (SWPPP); an example of an SWPPP is
included the accompanying Project Documentation Appendix at Tab 6.
990144BA.v-6
44
2/14/2000

<<<PAGE 462>>>

4.3
PROJECT ENVIRONMENTAL INSPECTORS
Longhorn and Williams shall employ the services of environmental
inspectors (such as Horizon and 3D/International) at every project site with
associated species-related constraints. These environmental inspectors are
qualified under FERC guidelines. The environmental inspector will remain at
each project site during the period of activity to ensure compliance with all project
constraints and project BMPs. The inspector is authorized to dictate any
additional project BMPs that may become necessary during the activity and to
modify work activities and progress to the extent necessary to ensure compliance
with project environmental constraints. However, in the event of a conflict
between project constraints and sound engineering practices, the inspector shall
consult with project engineers and the Service, as appropriate, to achieve project
goals while minimizing any impacts to the environment. The environmental
inspector retains oversight of site closure and performs, or supervises the
performance of, post-activity inspections of project BMPs until site stabilization is
achieved. The environmental inspector will produce appropriate documentation
for each construction location to include BMP compliance logs, photographs, as-
built dimensions of disturbance, and any encounters with listed species during
the construction process. The reports will be provided to the Service after
completion.
4.4
SITE PREPARATION
Prior to site entry, at locations where avoidance and/or minimization of
species effects has been recommended, a qualified biologist will clearly identify
areas for avoidance and will stake and/or flag such areas. The project
environmental inspector also surveys the site to ensure that all such avoidance
areas are clearly identified in accordance with conditions approved in the
consultation process and confirms other site-specific areas in which disturbances
may occur such as routes of ingress/egress, spoil management areas,
equipment marshalling areas, workspace areas, and the like. Project BMPs are
reviewed prior to site entry, and the locations of any necessary physical control
measures to be employed are identified.
A survey crew will precede the project equipment and mark the project
990144BA.v-6
45
- 2/14/2000

<<<PAGE 463>>>

boundaries. In addition, the pipeline centerline is marked at 100 foot to 200 foot
intervals.
4.5
SITE ENTRY
Upon site entry, the necessary project equipment is transported to the site
via the designated route for ingress/egress. Site access is achieved via
improved roadways and the established ROW, using the shortest available route
between improved roadways and the project site. Routes of ingress/egress take
into account any potential for effects to threatened and endangered species and
habitat that may exist along the ROW between the improved roadway and the
project site, as well as accounting for other potential impacts to the environment.
At times, equipment will remain on-site only during the time that it is in active use
to allow it to be shared between project sites in close proximity.
Prior to any excavation, site vegetation is removed, and project BMPs are
installed.
Site vegetation is cleared to the extent necessary for project
completion, so long as the vegetation is not located in areas identified for
avoidance. Clearing is accomplished by the methods described in Section 4.1,
Right-of-Way Clearing, though vegetation within the workspace may require
removal. Project BMPs are installed in accordance with project planning
documentation and in accordance with the site-specific SWPPP.
The following task descriptions identify process steps that occur once all
authorizations are obtained and regulatory requirements are identified and
incorporated into project planning and engineering documentation. Detailed
procedures for each of the activities summarized below are available in Pipeline
Construction Specification CS4, which is included in the accompanying Project
Documentation Appendix at Tab 4. In the event of a conflict between
Construction Specification CS4 and the site-specific components of the Project
Construction Plan, the Project Construction Plan controls.
4.6
PIPELINE LOWERING AND/OR REPLACEMENT - OPEN TERRAIN
Once the project site has been prepared and equipment brought onto the
location, the following major activities take place:
990144BA.v-6
46
- 2/14/2000

<<<PAGE 464>>>

•
Isolate pipeline segment to be replaced by cutting and plugging at
boundaries. Williams operating personnel will establish that the line
is unpressurized and properly isolated such that the contractor may
cut the pipeline at the project limit boundaries. Mechanical plug
devices will be utilized to prevent residual product leakage from the
pipeline segments or entry of foreign materials into the pipeline.
These devices shall be secured to prevent their loss or tampering.
•
Remove large rocks, if any, from ROW work area to appropriate
disposal/storage area. Trackhoes with buckets are used, unless
larger rocks require grapple capable (clam) buckets.
•
Remove and set aside topsoil spoil (double ditch practices).
Double-ditching will be required in areas where native plant
communities need to be re-established, or there are topsoil
improvements, such as sodded lawn areas and cultivated fields.
Double-ditching allows topsoil management by making two passes
to remove and segregate spoil; one to remove and set aside topsoil
and one to remove and set aside subsoils.
•
Remove overburden and expose pipe. Utilizing track hoes, remove
and set aside overburden from the pipeline and load and remove
excess amounts from the work site for disposal. Unsuitable
overburden (i.e., large rocks) will be disposed of in approved sites.
•
Cut pipe into subsections at road and water crossings. Expose and
cut the pipeline at road crossing boundaries to isolate the removal
section into subsections. Utilize drain pans to recover any
remaining liquids as the cut is made. Install mechanical plugs in all
exposed pipe ends.
•
Raise and crib pipe on side of trench. Properly manage any coating
which comes loose from the pipe.
990144BA.v-6
47
- 2/14/2000

<<<PAGE 465>>>

Prepare and wrap pipe for disposal. Double wrap the pipe sections
with 6-mil thickness plastic wrap, taping and sealing each wrapping
separately. Ensure that the ends are sealed to prevent any release
of coating.
•
Remove pipe from ROW. Load and remove the wrapped pipe
sections by truck. Care will be taken to preserve the plastic
wrapping on the pipe. Secure the pipe to the trailer and haul to the
disposal site for final disposition.
•
Cleanup and grade ROW for survey and trenching operations
•
Capture,
contain, and remove any remaining coating
materials/scraps using project-prescribed methods for asbestos
containing materials. Prepare the grade on either side of the ditch
to accommodate the trenching machinery, removing any large
rocks. Survey crew should mark and stake the centerline offsets as
required by the trenching crew.
•
Deepen trench to new depth. Depending upon the length of the
desired lowering and/or replacement, and depending upon whether
the trench is in soil or rock, a track-hoe or wheel trencher (rock
saw") deepens the trench to the new depth. A wheel trencher is
typically used for longer trenches and trenches in consolidated
rock. Dust generation is monitored during trenching, and a water
fog of the trenching mechanism may be employed to minimize
airborne dust in non-rural areas.
•
String new pipe along trench. As the ditch is prepared, the pipe
may be strung along the workpad in anticipation of measuring and
marking for bending, welding, and lowering operations. The survey
crew will note the pipe heat and identification numbers sequence
for the individual pieces as they are placed. The survey crew will
survey the new ditch profile and mark the pipe for calculated field
bends.
90144BA.v-
48
2/14/200

<<<PAGE 466>>>

•
Make field bends. The field bending crew will proceed ahead of the
welding crew to make any required field bends. The contractor
may also elect to set up field bending in one of the equipment
marshalling areas and perform bending there rather than on the
ROW.
Weld and Radiograph new pipeline. The welding crew will proceed
to weld the pipeline. Inspectors and survey will note the weld
numbers and identification of the welders for this activity. The
radiography crew will follow the welding crew. Inspection will be
per standard specification API 1104 and include 100% radiography
of all girth welds.
•
Apply weld joint coating and inspect pipeline coating for "holidays";
a holiday is a point where the coating fails to electrically insulate the
pipe. Weld joint coating will be applied as specified in the Project
Construction Plan. This will be by field-applied FBE (fusion bond
ероху). Following weld joint coating, the entire coating system will
be inspected for holidays and repaired as required.
•
Pad and lower pipe. Pad the ditch and lower the pipeline as
specified in Construction Specification CS4. Install ditch plugs as
required to stabilize pipeline during hydrotest and backfilling. The
pipeline coating will receive a final "jeeping" as the pipe is lowered
to ensure its integrity. Jeeping is the process of electrically
inspecting the pipeline coating to ensure that no "holidays" exist in
the coating, so named due to the "jeeping" sound the inspection
device emits when a holiday is identified.
•
Complete as-built survey. Complete as-built survey activities,
noting weld locations, pipe identification codes, and location and
stationing of bends, fittings and other such features for inclusion in
alignment sheet drawings.
•
Backfill and compact trench. Backfill and compact the ditch
according to Construction Specification CS4, maintaining sufficient
990144BA.v-6
49
- 2/14/2000

<<<PAGE 467>>>

cover to allow for settling. Install ditch breakers and silt fencing as
appropriate for surface erosion control until the site is stabilized.
•
Perform hydrostatic pressure test on new pipeline segment. Obtain
fresh water for pressure test and begin line fill behind a pig. The
test pressure and test duration will be established and specified in
the Project Construction Plan or in separate hydrostatic testing
plans.
Drain and dispose of hydrostatic test water. Upon completion of
the hydrostatic test, the test water is either pushed with nitrogen to
a subsequent test site or removed into mobile tanks for hauling to a
disposal facility. Test water is controlled to ensure that it is fully
contained in order to prevent discharge to the environment.
•
Perform Final Tie-Ins. Remove the test headers and make the final
tie-ins of the new pipe segment to the existing pipeline. The tie-in
welds will be 100% radiographed to ensure their integrity. Coat the
tie-in welds with an appropriate joint coating system compatible
with both FBE and coal tar coatings. The coating is inspected, or
"jeeped," and any holidays are repaired. The tie-in locations are
backfilled and compacted.
•
Clean, Grade, and Seed Right-of-Way. Following installation of
erosion control measures, re-seed the right-of-way with native
grass seed and/or sod as prescribed for the location. Re-install
pipeline markers and any traffic control devices to limit or restrict
ROW access by motor vehicles.
•
Perform Site Cleanup and Restoration. Clean up equipment
marshalling and material storage sites, ensure that the worksite
access roads are restored to prime condition, and that any road
access ways are cleaned and restored.
4.7
PIPELINE LOWERING AND/OR REPLACEMENT - CREEK CROSSING
50

<<<PAGE 468>>>

Pipeline lowering and/or replacement at creek crossings follows generally
the same sequence of activities described above for open terrain; however, the
additional activities described below apply to the actual creek crossing area. In
addition, creeks may be crossed by either trenching or boring. Each crossing
method is summarized separately below.
4.8
TRENCHING
A trenched crossing is lowered and replaced in much the same manner as
an open terrain project; however, incremental measures are employed to ensure
both that erosion and sedimentation are minimized and that no potentially
harmful materials are discharged to the waterway. Pipeline Construction
Specification CS4 provides additional details.
Cut Pipe at Creek Crossings. Expose and cut the pipeline at the
creek crossing boundaries to isolate the removal section into
subsections. Utilize drain pans to recover any remaining liquids as
the cut is made. Install mechanical plugs in all exposed pipe ends.
•
Implement Water Quality Protection Measures. Staging areas,
spoil storage areas, and additional workspace areas are located in
upland areas above the creek bed. Hazardous materials such as
chemicals, fuels, lubricating oils and any other potentially harmful
materials are maintained at least 100 feet from the water body.
BMPs are installed to prevent sedimentation. Flumes, dams,
equipment bridges and other diversion devices are installed as
necessary to perform "dry ditch" excavation.
•
Erosion control measures are employed after project completion to
ensure that stream flows do not cause erosion of disturbed areas
and subsequent sedimentation. Erosion controls protect against
sedimentation and prevent stream flow from removing pipeline
cover which could expose the pipe to steam bed forces. Erosion
control measures are site-specific, depending upon site conditions,
and include berms, dikes, water bars (perpendicular to the pipeline
990144BA.v-6
51
- 2/14/2000

<<<PAGE 469>>>

alignment), silt fences, staked hay bales, seeding, mulching,
hydromulching, riprap, and trench plugs.
4.9
BORING
Stream crossings may be installed by boring rather than trenching,
depending upon hydrologic and engineering considerations and soil types. The
existing pipeline may be abandoned in place after obtaining approvals from the
landowner and, if necessary, state and federal authorities, and after (a) filling the
pipe with an inert material such as grout or concrete, or (b) sealing the ends of
the pipe. The pipe may not be abandoned in place if its presence could interfere
with stream flows or interfere with future uses of the waterway.
Boring a stream crossing requires the use of a work space for installation
of bore pits in which the boring equipment operates. The boring operations
typically require a workspace approximately 100 to 250 feet wide by 150 feet
long. The workspaces are located above the high water mark unless topography
or other factors dictate otherwise. Typically, no instream soil disturbance occurs,
and BMPs are employed to ensure that spoil storage and other project activities
do not cause erosion or sedimentation.
From within the bore pits, the boring equipment creates a parabolic
pathway to the pit on the other side of the stream bed. Bored material is
circulated out of the bore and retained at the upland spoil storage area. The bore
is sealed with grout or bentonite to fill fissures along the course and to ensure
bore stability.
The new pipe is then pulled through the bore using equipment designed
for that purpose. Once the pipe is welded, inspected, surveyed, coated and
tested, the excavations are filled and compacted, and the site is restored. Site
restoration and stabilization is achieved in the same manner as described in
Section 4.6, Pipeline Lowering and/or Replacement - Open Terrain. Any
necessary erosion and sedimentation controls are employed, and the site is
inspected and maintained until final stabilization is reached.
990144BA.v-6
52
- 2/14/2000

<<<PAGE 470>>>

4.10 HYDROSTATIC TESTING - OVERVIEW OF ACTIVITIES
A hydrostatic pressure test is scheduled to be performed to ensure the
integrity of the system. This test is scheduled to commence in February 2000
and conclude in May 2000.
Hydrostatic testing will start at the Longhorn GATX pump station in
Galena Park (Houston) and proceed westward to Crane Station. The test
medium will be potable water from a local municipal supply source. In the event
some water is lost due to pipe failure, or if water is needed to fill longer test
sections, fresh make-up water will be acquired, by permit, from sources crossed
by the pipeline (i.e., from rivers or streams).
The hydrostatic testing occurs in segments, which are subdivided into
test sections of varying lengths. Factors that contribute to test section length
include (a) target test pressures; (b) pipe size and grade; (c) the presence or
absence of species and habitat; (d) the location of valves and pump stations; and
(e) elevation changes along the pipeline.
Due to additional factors, two test sections will not be tested during the
Houston to Crane hydrostatic testing project. Those two sections are (a)
Segment 4, Section 1, which encompasses habitat for the endangered Houston
toad and (b) Segment 5, Section 4, which encompasses the recharge zone of the
Edwards Aquifer and part of the adjacent contributing zone, areas of potential
effect to the endangered Barton Springs Salamander. Rather, those sections will
be tested after Phase II consultation relating to pipeline operation, maintenance
and emergency response, and after maintenance construction to replace pipeline
segments in those areas is completed.
The current hydrostatic testing schedule is as follows:
TEST SEGMENT
START DATE - END DATE
Segment 1
February 11 - February 13
Segment 2
February 14 - February 20
Segment 3
February 21 - February 27
53
221420

<<<PAGE 471>>>

Segment 4
February 28 - March 5 (Section 1 after
completion of maintenance construction (May))
Segment 5
After completion of maintenance construction (May)
Segment 6
March 6 - March 15
Segment 7
March 16 - March 26
Segment 8
March 27 - April 2
Segment 9
April 3 - April 9
Segment 10
April 10 - April 16
Segment 11
April 17 - April 23
As noted above, the test sections traversing Houston toad habitat and the
Edwards Aquifer Recharge Zone will not be tested until after the completion of
maintenance construction in those areas, which will not commence until after
completion of Phase II of this consultation. The start date for Segment 1
identifies the date that actual testing is scheduled to begin; however, for the
remaining test segments, the start date identifies the date on which test water is
scheduled to be introduced into that segment from the preceding segment. In
addition, any delay encountered during testing, such as to replace a failed
segment of pipe, will result in equivalent delays in the remainder of the test
schedule.
To facilitate hydrostatic testing of the pipeline, headers will be installed on
the pipeline at intervals along its length which divide the pipeline into segments
for discrete testing. There are forty (40) header sites involved in the test. A
general description of the installation of the test headers follows. Additional
information is provided in the accompanying Project Documentation Appendix at
Tab 8, including a graphic depiction of a typical header site. Headers vary in
configuration; however, all function similarly to allow the introduction of test
water, the pressurization of the test segment and the displacement, after testing,
of the test water to the following test section.
Prior to any work, the sites will be subject to an environmental,
endangered species, and archeological survey conducted by
qualified third-party biologists and archeologists. The headers will
be installed by excavating an area approximately 20 ft. wide x 80 ft.
long × 4 ft. deep around and under the pipeline. The spoil will be
990144BA.v-6
54
- 2/14/2000

<<<PAGE 472>>>

stored on the temporary work easement. The topsoil will be
segregated from the sub-grade for restoration of the site following
the hydrostatic test. Storm water management during construction
and testing will be by methods prescribed in the SWPPP, an
example of which is included in the Project Documentation
Appendix at Tab 6.
•
The exposed pipe will be cut and spread apart horizontally, and
pre-fabricated headers will be welded to each section. The
downstream header shall have a wire brush pig and displacement
pig inserted in it before it is welded on the pipeline. A 6-inch
temporary crossover pipe with valve will be installed between the
upstream and downstream header. Upon completion of the test,
the hydrostatic test water will be displaced into the next test
segment by nitrogen. The test section will be vented to atmosphere
and the temporary piping and headers will be removed. The
pipeline will be tied back together with a joint of new pre-tested pipe
and the joints will then be coated and wrapped to provide corrosion
protection. Coating is inspected for holidays, and repairs are made
if holidays are identified. The excavated area will be backfilled and
compacted with the subgrade material in the spoil pile followed by
the topsoil to finished grade to match the surrounding terrain. The
disturbed area is seeded with native grasses or sod, and BMPs are
inspected and maintained until the site is stabilized. Total surface
workspace requirements for test header installations are about 100
feet wide by 150 feet long along the pipeline.
4.11
HYDROSTATIC TESTING - POTENTIAL FAILURE OF PIPE
Hydrostatic testing of the existing Longhorn Pipeline between Houston and
Crane is expected to result in a number of failures. Some of those failures, and
actions taken to locate failure locations, could have effects upon both species
and habitat. However, the calculation of the effects of such failures is difficult to
estimate since the location of any such failure cannot be predicted and since the
volume of test water that may be discharged is difficult to predict.
990144BA.v-6
55
- 2/14/2000

<<<PAGE 473>>>

Calculations by a pipeline integrity consulting firm estimate that
approximately 18 to 20 failures will occur at the high test pressures planned.
Since the most likely failure location is at pipeline flaws, the location of the
expected failure cannot be predicted with any accuracy; at most, a minimal
number of recently replaced sections of pipe may be eliminated from
consideration. Therefore, the expected failures will approximate a random
distribution over the Houston to Crane segment. A finite number of failures could
be assigned to the habitat areas based upon the proportional share of pipeline
mileage in habitat areas; however, that methodology would probably result in
either overestimation or underestimation of the number of failures in habitat
areas.
In addition, the potential volume of test water discharged in the event of
failure is difficult to estimate. First, if a failure results in rapid depressurization of
the test segment, the volume of test water discharged will be the sum of (a) water
expelled as the pipe returns to atmospheric pressure, which depends upon test
pressure and test segment length, and (b) drainage from any adjacent segments
at elevations higher than the failure location. Second, if a failure results in a
slow depressurization of the test segment, it may be readily identifiable and
quickly contained. If a slow leak is difficult to locate, one or more investigative
excavations could be required to either search for the failure or plug a portion of
the segment so that lengths of pipe may be eliminated from the search.
Therefore, given that failure location and size cannot be predicted, potential
effects on species and/or habitat cannot be reasonably estimated in advance.
Another factor that makes such estimates difficult is the existence of residual
amounts of diesel fuel that remain in the pipeline from cleaning during 1998. As
the hydrostatic testing proceeds from east to west, the test water may be
expected to reflect relatively higher levels of hydrocarbon content; however,
those concentrations cannot be predicted. Spill response equipment such as
booms, sorbant pads, and other containment and cleanup equipment will be
maintained in the vicinity of the test sites during the procedure.
In summary, the locations of hydrostatic test failures cannot be predicted,
the volume of test water discharged may not be calculated, and the number of
investigative excavations cannot be predicted.
990144BA.v-6
56
- 2/14/2000

<<<PAGE 474>>>

4.12 CATHODIC PROTECTION ENHANCEMENTS
Enhancements of the pipeline cathodic protection system consist of (a)
installation of anode beds and (b) re-coating of sections of existing pipe. The
cathodic protection system protects the pipe from corrosion. These
enhancements are identified and described in the accompanying Project
Documentation Appendix at Tab 2, and the locations where activities may affect
species and habitat are identified in Table 2. Project planning is performed in a
manner similar to that described in Sections 4.3 through 4.5 above.
Installation of deep anode ground beds requires a series of vertical bores
within which sacrificial anodes are placed; the anodes within each bore and
among the series of bores are connected by subsurface wiring that is then
connected to the pipeline. The bores and wiring trenches are installed within the
existing ROW. During boring, a circulating pit is dug to contain cuttings removed
from the bore. After project completion, the pit is filled, excess cuttings are
removed for disposal, and the site is closed in the manner described in previous
discussions of construction site closure.
An example project work plan and related diagrams that provide additional
detail about deep ground-bed installation are included in the accompanying
Project Documentation Appendix at Tab 11.
Pipeline coating reconditioning involves the same activities required for a
pipeline lowering or replacement, with the exception of the process steps to
remove existing pipe and install new pipe. A coating replacement site undergoes
the project planning, site preparation, site entry, and site closure steps much as
described above in Sections 4.2 through 4.6. Since the pipe is not cut, any
residual liquids within the pipe do not present contamination potential. Asbestos
containing pipe coating is managed in accordance with the provisions of the
Environmental Protection Plan and the Project Construction Plan (ref. the
accompanying Project Documentation Appendix at Tabs 5 and 3, respectively).
All coating reconditioning is inspected, or "jeeped," and any holidays are
repaired.
4.13 SURGE PRESSURE PROTECTION
990144BA.v-6
57
- 2/14/2000

<<<PAGE 475>>>

To reduce the risk of over-pressurization of the pipeline, Longhorn will
implement system changes and operating practices to limit surge pressures to no
more than maximum operating pressure in sensitive and hypersensitive areas
identified by the Lead Agencies (ref. Project Documentation Appendix at Tab 2).
One system change involves the installation of over-pressure activated by-
pass systems that will allow a pressure spike to be relieved around certain gate
valves. The installation of a by-pass system involves the same process steps as
the installation and removal of a hydrostatic test header; see Section 4.10. The
by-pass system to be installed at the east bank of the Llano River will use the
same work location as the hydrostatic test header to be installed at that valve
site.
4.14
INVESTIGATIONS
Projects to investigate possible pipe dents and corrosion anomalies follow
the
same
planning
and
preparation procedures
for a pipeline
lowering/replacement, but on a lesser scale. Table 2 identifies relevant
information for, and the locations of, projects to investigate possible pipe dents
and corrosion anomalies.
Typical investigation sites require a trench approximately 20 feet in length.
If a dent or anomaly cannot be field repaired, a segment of pipe will be removed
and replaced, with the length replaced at least twice the pipe diameter. Coating
and coating inspection and repair, as well as site closure, follow the procedures
described in Section 4.0.
990144BA.v-6
58
- 2/14/2000

<<<PAGE 476>>>

5.0
POTENTIAL IMPACTS (TAKE) AND COMPENSATION
ATake@ of listed species is defined in the ESA and implementing
regulations as the act or attempted act of pursuing, hunting, shooting, wounding,
killing, trapping, capturing, collecting, harming, or harassing. Harm and harass
are defined as the act of disturbing individuals or modifying habitat to the extent
that wildlife are actually killed or injured by impairment of essential behavioral
patterns such as breeding, feeding, or sheltering.
Potential take of certain listed species could occur from a number of
actions or events associated with the implementation of the subject project
activities described in Section 4.0, including maintenance construction,
hydrostatic testing, ROW maintenance, and cathodic protection enhancements.
No individuals of any listed species have thus far been documented within the
existing pipeline ROW; however, the potential for incidental take cannot be
eliminated. Surveys and detailed habitat assessments have been conducted for
a number of species of concern, and additional surveys are scheduled for the
near future; however, the Service has recommended in the December 15, 1999
Comment Letter that additional surveys be conducted for several years into the
future to confirm the presence or absence of species within areas of potential
habitat. Furthermore, the hydrostatic testing project could affect habitat areas,
but no reasonable means exists to predict or to quantify the potential for take.
Alternatively, take may be assumed without reference to the presence or
absence of species. Assumed take will very likely result in overcompensation;
that is, since surveys have not identified individuals in the pipeline ROW,
assumed take will result in compensation for areas of potential habitat where
species utilization has, to date, not been confirmed.
That overcompensation will provide a net benefit to the species for several
reasons. First, surveys to date have not identified individuals in the area of
impact for the subject maintenance construction activities; thus, compensation
occurs even though there is no documented take. Second, Longhorn will
implement numerous controls to ensure that the project activities are conducted
first to avoid, and otherwise to minimize, potential effects to species and habitat.
Examples include identifying and marking habitat areas for avoidance; planning
project implementation to minimize the potential for any effects; use of FERC-
990144BA.v-6
59
- 2/14/2000

<<<PAGE 477>>>

qualified inspectors with authority to alter a project in areas with species related
concerns; adjusting project timing to avoid periods of activity and blooming
seasons; and implementing storm water pollution control BMPs even when not
required by permit. Thus, any potential adverse effects will be avoided or
minimized. Third, potential habitat has been assumed over broad areas when, in
fact, detailed surveys could reveal that occupied habitat is either absent or of
doubtful viability to a species. The end result is that the potentially affected
species benefit
by conservation efforts on a scale greater than any likely
incidental take.
Longhorn proposes, therefore, to assume an incidental take for the entire
width of the pipeline ROW traverse of broad areas of potential habitat. This
conservative assumption will result in overcompensation to the benefit of the
potentially affected species and habitats. Take is calculated based on the extent
of potentially suitable habitat within the established ROW (50-foot width x length)
and within temporary workspaces that exceed the ROW (i.e., equipment staging
areas, spoil management areas, and stream diversion areas, the size of which
varies by location). On that basis, the take for each species is calculated as
indicated in Table 3.
As discussed in Section 4.11, Hydrostatic Testing - Potential Failure of
Pipe, the locations of potential hydrostatic test failures cannot be accurately
predicted, the volume of test water discharged cannot be accurately predicted or
calculated, and the number of investigative excavations cannot be predicted. The
inability to accurately predict the potential impacts of hydrostatic test failures
precludes any pre-activity attempt to predict and/or estimate the potential effects
of test failures. Any such attempt would be likely to result in inaccurate
estimates. Therefore, Longhorn proposes to provide for a contingent
methodology for calculating any such effects.
990144BA.v-6
60
_ 2/14/2000|

<<<PAGE 478>>>

Table 3:
ROW Clearing/Maintenance and Additional Construction Impacts* Within
Listed Species Habitat - Longhorn Pipeline
ROW Clearing/Maintenance Area:
Texas Prairie Dawn
53,392 linear feet × 50 feet
61.3 acres
Navasota Ladies-tresses
4,576 linear feet x 50 feet
5.2 acres
Houston Toad
17,952 linear feet x 50 feet
20.6 acres
Golden-cheeked Warbler
90,096 linear feet x 50 feet
103.4 acres
Black-capped Vireo
36,256 linear feet x 50 feet
41.6 acres
Tobusch Fishhook Cactus
185,328 linear feet × 50 feet
212.7 acres
TOTAL ROW IMPACTS = 444.8 acres
Additional Maintenance Construction Area
Construction
Dimensions** Species
Impact
Site
Stationing
Acres
LPP-2753
LPP-2751
10369+55 - 10373+24
200 × 1033
200 × 1000
GCW
4.7
2016
10380+60 - 10381+24
200 × 806
GCW
GCW
4.6
Hydrostatic Header
3.7
And Test Sites
Site 6-6
Site 6-2
10280+00
50 × 100
GCW
50 × 100
GCW
0.1
0.1
11385+50
Site 8-2
Site 7-3
13435+00
15143+00
50 × 100
50 × 100
TFC
BCV
0.1
Site 8-3
15586+00
16167+00
50 × 100
TFC
0.1
Hydrostatic Transfer
Site 8-4
0.1
50 x 100
TFC
0.1
Sites
Site 6-1
Site 8-1
10163+00
50 x 150
GCW
0.2
And Surge-4
14606+00
50 × 150
TFC
0.2
TOTAL MAINTENANCE
CONSTRUCTION IMPACTS
14.0
TOTAL IMPACTS
458.8.
Of the methodologies available for calculating the effects of activities upon
2214200 G

<<<PAGE 479>>>

species and habitat, the most applicable is the Habitat Equivalency Analysis
(HEA) methodology developed by the National Oceanic and Atmospheric
Administration for Natural Resources Damages Assessments (NRDAs). The
HEA methodology is briefly described by the following steps:
The duration and extent of injury are documented and estimated
from the time of injury until the resource recovers to baseline;
•
The services provided by a compensatory project are documented
and estimated over the full life of the project;
•
The size of a compensatory project is calculated such that the total
increase in services provided by the compensatory project equals
the total interim loss of services due to the injury; and
•
The cost of the compensatory project is calculated.
A more detailed description of the HEA methodology is provided in
accompanying Project Documentation Appendix at Tab 10.
Longhorn's proposal, then, is to execute the following sequence of
measures in the event a hydrostatic test discharge occurs in areas of concern for
species and/or habitat:
•
In the event of a test failure, immediately notify a qualified biologist,
who will be maintained on standby along the test segment, and
direct the biologist to the failure site;
•
If a discharge occurs, the biologist will assist the identification of
response actions to minimize potential impacts to the environment;
and,
•
The biologist will perform a field survey to document the loss of,
destruction of, or injury to natural resources (a) at the location of
any excavation, whether the excavation is for location of a failure or
for repair of pipe; (b) within the area of impact of the test water; and
(c) in any other areas affected by the response to the test failure, as
at any other construction site.
The effects, if any, of the hydrostatic test failure upon species and/or
habitat will then be calculated pursuant to the HEA methodology. Longhorn shall
990144BA.v-6
62
• 2/14/2000|

<<<PAGE 480>>>

compensate for the value of any such adverse effects by paying the monetary
value of an appropriate compensation project to conservation efforts directed at
the preservation and recovery of the affected species and habitat in the region
where the impact occurred. For example, if a hydrostatic test resulted in a take
of golden-cheeked warbler or black-capped vireo habitat, Longhorn would
contribute the requisite monies to appropriate conservation entities acceptable to
the Service, such as Balcones Canyonlands Conservation Plan, The Texas
Nature Conservancy, or similar initiatives.
5.1
SPECIES BY SPECIES IMPACT ANALYSIS
Texas Prairie Dawn (Hymenoxys texana)
Potential impacts to the Texas prairie dawn may result from a number of
activities. Right-of-way maintenance will occur with the periodic (typically twice
per year) use of tractor drawn mowers. Tractors will be rubber-tired, but crushing
of plants could occur from time to time, particularly during blooming periods.
Mowing height will typically be 3 to 4 inches. Since only the blooming shoot is
usually that high, impacts from mowing are deemed to be minimal, except during
blooming. Impacts, while not believed to be significant, are quantified as the total
ROW (50') through the entire area of identified potential habitat. As indicated in
Table 3, this area constitutes approximately 61.3 acres. As an avoidance and
minimization measure, mowing will be scheduled to avoid the February through
April blooming season. A blooming season survey of the ROW and adjacent
areas is recommended to identify any plant locations for specific avoidance, if
present.
Three construction sites have been identified for completion in the near-
term, two dent investigations, and one anomaly investigation (ref. to Table 2).
Impact for these three construction areas will be contained within the existing 50'
ROW for relatively short distances along the pipeline (see Table 3). Within these
areas, excavation, temporary spoil storage, equipment movement, and grading
will likely result in elimination of any prairie dawn plants that may occur within the
ROW in the construction areas. The area of these impacts is already included in
the total ROW impact mentioned above.
990144BA.v-6
63
- 2/14/2000

<<<PAGE 481>>>

Navasota Ladies-tresses (Spiranthes parksil)
As in the case of the prairie dawn, periodic (twice per year) mowing with
rubber-tired tractor mowers may result in sporadic crushing of plants under
tractor tires or mower wheels, or cutting of bloom stalks. Impacts from periodic
mowing are again not expected to be significant, but in the absence of detailed
plant inventory information for the ROW, an assumed total impact for the ROW
through the identified potential habitat areas constitutes 5.2 acres (Table 3). As
an avoidance and minimization measure, mowing will be scheduled to avoid the
October and November blooming season. A blooming season survey of the
ROW and adjacent areas is recommended to identify any plant locations for
specific avoidance, if present.
No areas of construction are identified in the two potential habitat areas.
However, construction will occur just east of the most westerly potential habitat
area. The ROW is to be used for access to the construction zone (see Table 3).
It is presumed that heavy equipment movement along this portion of the ROW
will result in destruction of any plants growing at that locality. Access will be kept
within the existing 50' ROW; therefore, potential impacts have already been
calculated in the ROW maintenance value above.
Houston Toad (Bufo houstonensis)
Right-of-way maintenance will again include periodic mowing with rubber-
tired tractors.
Mowing could generally reduce grass thickness and height,
thereby improving mobility for Houston toads. However, since Houston toads are
mobile, the possibility exists for run-overs by tractor tires or jumping into the
mower blades by toads. Toads are predominantly active during a few months of
the year; therefore, the possibilities of encounter are fairly remote. As a means
of providing additional avoidance procedures, pipeline ROW maintenance will be
timed to occur in the late fall through early spring (November to January) when
the toads are generally inactive to limit the possibility of direct impact. In addition
to these avoidance procedures and the low likelihood of encounters, Longhorn
will assume that all areas of potential habitat traversed by the pipeline ROW are
suitable and will commit to compensate for the entire ROW width. From Table 3,
this amount is approximately 20.6 acres. Horizon has recommended a spring
990144BA.v-6
64
- 2/14/2000

<<<PAGE 482>>>

breeding season survey for the toad in the vicinity of, and downstream of the
pipeline to determine possible toad presence, population, and breeding areas
that could be affected.
No construction impacts to Houston toads are contemplated in this
consultation. Pipe replacements within the toad habitat area will be addressed in
the second phase consultation.
Edwards Aquifer Contributing Zone - Barton Springs Salamander
Right-of-way maintenance and four construction locations are presently
contemplated to occur within the contributing zone of the Edwards Aquifer in
Travis and Hays counties. The principal concern for impacts to listed species in
this area is by siltation from disturbed areas being transported by storm runoff to
streams that eventually run onto the Edwards Aquifer Recharge Zone, potentially
entering the aquifer, and lowering the quality of water utilized by the Barton
Springs salamander. While single projects are not likely to have any
demonstrable effects on the salamander, the cumulative effects of many
development projects throughout the recharge zone and contributing zone may
collectively cause negative impacts.
Right-of-way maintenance, consisting of mowing and trimming, is not likely
to result in any level of sedimentation or impacts since the activity will not result
in ground disturbance. Enhanced Best Management Practices (BMPs) will be
utilized throughout construction in disturbed areas to prevent sediment loads
from reaching the aquifer or significantly reduce such loads. BMPs are identified
in the Project Documentation Appendix, Stormwater Pollution Prevention Plan
(Tab 6). The BMPs will also include reclamation of disturbed areas immediately
following construction for rapid growth and stabilization of grasses and annuals.
As a result of these enhanced BMPs, no significant impacts to the aquifer
or Barton Springs salamander are contemplated.
Golden-cheeked Warbler - (Dendroica chrysoparia)
Golden-cheeked warbler habitat does not exist in the established ROW,
990144BA.v-6
65
- 2/14/2000

<<<PAGE 483>>>

but is presently adjacent to the ROW in a number of locations from Hays County
westward to Mason County. Right-of-way maintenance will not directly affect
warbler habitat, except for hand pruning of canopies which overhang the ROW.
Indirect effects may result from mowing noise or activity if birds are present in the
vicinity during maintenance activities. As a minimization procedure, Longhorn
will schedule maintenance activities to occur during the non-nesting season
(September 1 to March 1) within or near warbler habitat areas to avoid indirect
impacts. While no significant impacts are anticipated to occur, Longhorn will
mitigate for the full ROW width (50') through potential warbler habitat areas. The
area of potential effect is determined to be 103.4 acres (Table 3).
Six areas of pipeline maintenance construction or investigation are
anticipated to occur along the pipeline within areas identified as potential warbler
habitat (Table 2). Each of those areas are estimated to require additional
construction space in excess of the existing ROW by variable widths (Table 3).
The total additional impact to warbler habitat resulting from construction clearing
is 13.4 acres. The additional areas of temporary work space are needed in these
areas to facilitate temporary spoil storage, machinery access, pipe stacking, and
miscellaneous construction related activities. As avoidance and minimization
procedures, Longhorn will to the extent possible, schedule construction activities,
particularly clearing, to occur during the non-nesting period (September 1 to
March 1). As with the immediately impending construction schedule, clearing will
commence prior to March 1st and construction activities will continue continuously
until completion.
Total estimated impacts to potential warbler habitat are 116.8 acres.
Black-capped Vireo - (Vireo atricapillus)
Seven areas of potential black-capped vireo habitat exist along the ROW
between Blanco and Kimble counties. Black-capped vireo habitat, being an early
successional stage of brushy regrowth, does exist within the existing ROW in
locations where previous maintenance activities have not occurred in several
years. In this case, ROW maintenance will directly impact potential habitat within
the existing ROW. The area of direct impact for the full 50' width of the ROW
through the various habitat areas constitutes approximately 41.6 acres. Indirect
990144BA.v-6
66
- 2/14/2000

<<<PAGE 484>>>

impacts from ROW maintenance are not likely since maintenance activities will
be conducted during the non-nesting season (September 1 to March 15) for
vireos.
Four maintenance construction locations have been proposed within the
areas identified as potential vireo habitat (Table 2). Only one of those
construction sites will require clearing beyond the 50' ROW width. An additional
50' of temporary work space will be needed to facilitate temporary spoils storage,
equipment access, pipe layout and construction room. The additional acreage of
disturbance for this construction site is 0.1 acre.
The total area of impact to potential black-capped vireo habitat is 41.7
acres.
Tobusch Fishhook Cactus - (Ancistrocactus tobuschit)
Potential habitat for the fishhook cactus is very generally estimated from
general soils and plant distribution information to include the entire reach of the
pipeline's traverse of Kimble County. Without specific survey information for the
cactus, it is assumed that the entire ROW across Kimble County is potential
cactus habitat. As with the Texas prairie dawn and Navasota ladies-tresses, the
Tobusch fishhook cactus is low growing and not likely to be directly affected by
mowing, except for possible crushing by tractor tires. However, due to the
significant extent of large rocks within the ROW, mowing is not always feasible in
this region. A preferred method in rocky terrain is to back drag a bulldozer blade
across the ground which knocks down undesirable woody vegetation. This
activity can disrupt the ground surface and possibly injure or destroy cactus
plants. Therefore, direct impacts to fishhook cactus habitat may occur from time
to time. The total area occupied by the ROW across Kimble County is 212.7
acres.
Four test header installation locations are planned within the potential
fishhook cactus habitat. Each site will disturb an additional 50' width beyond the
ROW for the construction of the headers. The additional space is required to
facilitate temporary spoils storage, equipment access, pipe construction, and
testing equipment. The additional area of impact per site is between 0.1 and 0.2
990144BA.v-6
67
- 2/14/2000

<<<PAGE 485>>>

acre. The total additional impact to cactus habitat is 0.5 acre.
The total impact acreage for Tobusch fishhook cactus is 213.2 acres.
Other Species
Listed species that may occur away from or downstream of the pipeline
corridor (ie., bald eagle, interior least tern, American alligator, Barton Springs
salamander) are not likely to be adversely affected by the proposed maintenance
and minor construction activities. Any discharges of hydrotest waters are not
expected to contain levels of hydrocarbons or other toxic materials sufficient to
result in adverse impacts.
5.2
AVOIDANCE AND MINIMIZATION
Longhorn will, to the extent reasonably possible, conduct the maintenance
construction, testing, and other subject activities in a manner that avoids potential
effects to species and habitat. If avoidance is reasonably and practically
unachievable, Longhorn will conduct the activities in a manner that minimizes any
potential effects. Controls and other measures designed to achieve that goal are
described in the foregoing descriptions of the various activities. A number of
those controls and measures are summarized as follows:
1.
Identifying and marking habitat areas for avoidance;
2.
Planning project implementation to minimize the potential for any
effects;
3.
Use of FERC-qualified environmental inspectors with authority to
alter project implementation procedures in sensitive areas;
Adjusting project timing to avoid breeding populations; for example,
projects in Houston toad habitat will avoid the months of February
through November, and projects in GCW and BCV habitat areas
will avoid March through August and April through September,
respectively;
Implementing storm water pollution control BMPs even when not
required by permit;
6.
Maintaining qualified biologists in hydrostatic test project areas for
990144BA.v-6
68
- 2/14/2000

<<<PAGE 486>>>

immediate response in the event of a test water release in a habitat
area;
Avoiding, until project planning is accomplished, hydrostatic testing
over
the Edwards Aquifer recharge zone, portions of the
contributing zone, and in Houston Toad habitat areas; and
Conducting additional species surveys along the pipeline ROW to
determine actual presence or absence of species and populations
where present.
Additionally, work in areas of noise-sensitive species (i.e., GCW, BCV) will
be avoided during the breeding/nesting season. If work must occur in habitat
areas during a noise-sensitive seasons, the Service will immediately be notified.
Biological surveys of the habitat areas will be conducted prior to construction to
determine the presence or absence of species and specific locations if present.
Avoidance and minimization procedures, as appropriate to protect the species,
will be implemented based on these surveys.
5.3 PROPOSED COMPENSATION FOR POTENTIAL TAKE
Longhorn proposes the following steps for calculating compensation, for
funding that compensation, for implementing the process by which the
compensation is valued initially and in the future, and for assuring the Service,
the public and interested parties that the total compensation will be funded in full.
Longhorn has applied a formula recommended by the Service to
determine appropriate compensation. The formula is: Impact acreage × 1.2 x
fair market value of land in the area. This formula is modified for Houston toad
habitat to use a 3x multiplier instead of 1.2 due to the more critically imperiled
nature of the toad population in general. The Service also recommends the
application of a one-time 10% inflation factor to anticipate increases in land
values over time. Longhorn has calculated compensation for purposes of this BA
on the basis of this formula and best estimates of land values in the area of each
respective species. Longhorn proposes that actual land values be determined
for purposes of calculating compensation on the basis of land appraisals
according to the following process.
990144BA.v-6
69
- 2/14/2000

<<<PAGE 487>>>

Within 60 days following the Biological Opinion, Longhorn will engage two
licensed appraisers to determine the average value of land in the vicinity of the
impact areas for each species along the pipeline. If the two appraisals differ by
greater than 5%, then a third appraisal shall be engaged to reach a
determination. All appraisals shall take into account land uses and conditions in
such vicinity. The current calculation of compensation, set out below, will then
be revised based upon the average of the two or three, as the case may be,
appraisals.
Longhorn proposes a series of payments over time to fund the necessary
compensation, with such payments being made in a manner which will maximize
benefits to the potentially affected species. For example, maximum benefit to
the species may be achieved through Service concurrence that the initial
payment go toward conservation efforts directed to the Houston toad and the
Tobusch fishhook cactus; since those species face a relatively greater prospect
of decline than the remaining species.
Longhorn proposes to provide this compensation amount to one or more
conservation funds devoted to conservation of the affected species, on an annual
basis over a six year period. Future land values shall be determined on the basis
of appraisals performed every second year following the initial appraisals and
determined employing the same methodology as described above. The
remaining compensation due from Longhorn shall then be recalculated based
upon the compensation acreage remaining to be funded and the most recent
land appraisals for such acreage.
Longhorn has solicited the participation of the Service in the identification
of conservation funds that provide the greatest benefit to the affected species as
a whole. In particular, Longhorn's intent is for the funds to support conservation
efforts that employ preservation and recovery actions at least as comprehensive
as the actions recommended in the Service's December 15, 1999 Comment
Letter and in the relevant species recovery plans. Potential recipients may
include the National Fish and Wildlife Foundation, the Texas Parks and Wildlife
Department (TPWD), Texas Nature Conservancy, Texas Land Trust, Trust For
Public Lands, and similar comprehensive conservation initiatives. Longhorn
990144BA.v-6
70
- 2/14/2000

<<<PAGE 488>>>

prefers that the payments be directed to the National Fish and Wildlife
Foundation and TPWD.
This amortized payment scale will provide a reliable funding stream for the
subject species for an extended period to purchase and manage habitat areas,
enhance habitats, fund artificial propagation, and conduct other recovery efforts
identified by the various species' recovery plans.
The amortized payment schedule encourages an adaptive approach to
managing these species by allowing the Service to redirect the funds over time to
their highest and best use. As scientific research on the needs of these species
continues, the Service may find that resources for the protection of the species
should be redirected-perhaps to management and recovery practices of which
the scientific community is not yet aware. Rather than committing all the
conservation funds to one particular endeavor now, the amortized payment
schedule allows the Service to apply the funds strategically over time as
conservation priorities change and the understanding of the species grows.
An amortized payment schedule also allows the regulated community,
such as Longhorn, to commit a greater amount of funds than might otherwise be
available. A payment schedule such as this one may establish a useful
precedent that will provide an incentive for other private entities, including
pipelines, to enter into conservation agreements that otherwise may seem
financially prohibitive. This encourages voluntary compliance which ultimately
benefits the species.
The implementation of the Longhorn proposal will require that appraisals
be obtained for calculation of present-day compensation. Longhorn proposes to
accomplish the foregoing over the 60 day period following issuance of the
Service's biological opinion.
Longhorn may at its discretion, at any point in time, (a) pay all outstanding
compensation on the basis of the most recent appraised values; or (b) purchase
required acreage acceptable to the Service for any given species. Exercise of
the foregoing discretion shall reduce remaining obligations and security
requirements.
990144BA.v-6
71
- 2/14/2000

<<<PAGE 489>>>

Given the timing matters identified above, Longhorn will provide
assurance to the Service that the calculated compensation (refined on the basis
of actual land appraisals) will be funded on time and in full. Such assurance will
take the form of security that assures the Service that the compensation will be
funded. Longhorn proposes such methods as a bond, a letter of credit, an
escrow, or similar such mechanism reasonably acceptable to the Service.
The
security will cover compensation not proposed for immediate funding and the
one-time 10% escalation value applied to same. Longhorn makes this proposal
conditioned upon the requirement that, as payments are made or in-kind
compensation is provided, a corresponding reduction be made in the
compensation acreage outstanding and thus in the amount of security required.
At issuance of the Biological Opinion, Longhorn shall provide to the Service
reasonable evidence that the security is in place. The proposed payments, as
secured, will assure that the compensation acreage is in fact acquired to benefit
the species.
Based upon the Service's recommended formula, the impacts described in
Section 5.1, and best estimates of present land values, the present calculation of
compensation would be as follows:
Texas Prairie Dawn
61.3 acres × 1.2 = 73.56 acres x $3,000/ac + 10% = $242,748
Navasota Ladies-Tresses
5.2 acres × 1.2 = 6.24 acres x $1,000/ac + 10% = $ 6,864
Houston Toad
20.6 acres × 3.0 = 61.80 acres x $2,000/ac = $123,600
Golden-Cheeked Warbler
116.8 acres × 1.2 = 140.16 acres x $2,000/ac + 10% = $308,352
Black-Capped Vireo
990144BA.v-6
72
- 2/14/2000

<<<PAGE 490>>>

41.7 acres × 1.2 = 50.04 acres × $1,000/ac + 10% = $ 55,044
Tobusch Fishhook Cactus
213.2 acres × 1.2 = 255.84 acres x $1,000/ac = $255,840
Total Compensation
$992,448
The total compensation figure stated above is to be funded according to the
schedule in Table 4.
990144BA.v-6
73
2/14/2000

<<<PAGE 491>>>

Table 4
Longhorn Pipeline
Take Compensation
Bonded Amounts
Year
HT
TFC
TPD/NLT/GCW/BCV
TOTAL•
2000
123,600
255,840
379,440
2001
102,168
102,168
2002
102,168
102,168
2003
102,168
102,168
2004
102,168
102,168
2005
102,168
102,168
2006
102,168
102,168
TOTAL
123,600
255,840
613,008
992,448
Prepay Option
Longhorn may elect to prepay amounts earlier than scheduled with
corresponding drop in security and compensation requirements.
In-Kind Option
Longhorn may purchase required acreage acceptable to the Service with
corresponding drop in security and compensation requirements.
Subject to adjustment based upon appraisals to be obtained by Longhorn.
990144BA.v-6
74
- 2/14/2000

<<<PAGE 492>>>

Thus, the Longhorn proposal, which is tabulated in Table 4, may be
summarized as follows:
At issuance of Biological Opinion: Provide security for total
estimated compensation of $992,448;
During 60 days following Biological Opinion: Obtain land appraisals
to determine current value of total compensation;
3.
Within 30 days of Appraisals: Fund acreage attributable to Houston
Toad and Tobusch fishhook cactus based upon initial appraisals;
Adjust security requirement to reflect appraised values and initial
payment;
Annually following Biological Opinion:
a.
Scheduled payments are made; and
b.
A corresponding reduction is made in the compensation
acreage outstanding, and the required security is reduced to
an amount necessary to secure the then outstanding
compensation acreage; and
6.
Bi-Annually following Biological Opinion: Obtain appraisals to
determine average land values, and adjust security requirement to
reflect changes in land uses.
This commitment is being made without regard to whether or not the
pipeline is eventually placed into service; rather, this commitment is based upon
the level of take that occurs as described above.
990144BA.v-6
75
2/14/2000

<<<PAGE 493>>>

6.0 REFERENCES
Arroyo, Bryan. Threatened and Endangered Species of Texas. Austin, Texas:
US Fish and Wildlife Service, Revised June 1995.
Blair, W.F., The Biotic Provinces of Texas. Texas Journal of Science. 2:93-117,
1950.
Campbell, Linda. Endangered and Threatened Animals of Texas. Austin, Texas:
Texas Parks and Wildlife Department; Resource Protection Division,
Davis, W.D. & Schmidly, D.J.. The Mammals of Texas. Texas Parks and Wildlife
Department. Austin, Texas, 1994.
Gould, F.W.. Texas Plants: A Checklist and Ecological Summary. Texas A&M
University Agricultural Experiment Station. MP-585/Revised. College
Station, Texas, 1975.
Horizon Environmental Services, Inc. Threatened or Endangered Species
Investigations - EZ Pipeline Project. 1991.
Poole, Jackie M. and David H. Riskind. Endangered, Threatened, or Protected
Native Plants of Texas. Austin, Texas: Texas Parks and Wildlife
Department, 1987.
United States Fish and Wildlife Service. Determination of Critical Habitat for the
Houston toad. Federal Register 43(21):4022-4026. 1978.
United States Fish and Wildlife Service. Minimum Procedures for Determining
the Presence/Absence of Golden-Checked Warblers and Black-Capped
Vireos. March 7, 1994 Memorandum, Austin Field Office. 1994.
990144ba.v-6
- 2/14/2000
76

<<<PAGE 494>>>

Phase I FWS Biological Opinion
February 17, 2000

<<<PAGE 495>>>

ted States aND mere see the Inter gre
Ecological Services Field Office
FISH AND WILDLIFE SERVICE
10711 Burnet Road, Suite 200
(512) 490-0057 / 490-0974
Austin,
Texas
78758
(iax)
MARCH
18A9
February 17, 2000
Consultation Number
2-15-00-F-413
Gregg Cooke
Regional Administrator, Region 6
U.S. Environmental Protection Agency
1445 Ross Avenue, Suite 1200
Dallas, Texas 75202-2733
Rodrick Seeley
Regional Director, Southwest Region
U.S. Department of Transportation, Office of Pipeline Safety
2320 LaBranch Road, Room Number 2116
Houston, Texas 77004
Dear Mr. Cooke and Mr. Seeley:
The U.S. Environmental Protection Agency, Region 6 (EPA) (February 10, 2000) and the U.S.
Department of Transportation, Office of Pipeline Safety, Southwest Region (OPS) (February 17,
2000) submitted letters requesting consultation with a Biological Assessment for the proposed
Longhorn Pipeline Project, Maintenance Activities and Minor Construction, Houston to Crane,
Texas. This letter acknowledges the U.S. Fish and Wildlife Service's (Service) receipt of your
requests for the initiation of formal consultation under the Endangered Species Act of 1973 as
amended (U.S.C. 1531 et seq.) (ESA). The Longhorn Pipeline Partners L.P., is the applicant and
designated "non-federal Representative" for this project, and Horizon Environmental Services,
Incorporated, prepared the Biological Assessment for EPA, OPS, and Longhorn. All information
required of you to initiate consultation was either included with your letters or is otherwise
accessible for our consideration and reference. We have assigned this consultation the number 2-15-
00-F-413 and this number should be included in all future correspondence.
This letter also transmits the Service's biological opinion on the Longhorn Pipeline Project
Maintenance Activities and Minor Construction, Houston to Crane, Texas, proposed for
authorization by EPA and OPS. The Service is able to complete this consultation in the short time
frame because of the extensive coordination that occurred during informal consultation. This
Biological Opinion is only related to the activities proposed in this Phase One of the overall
consultation. The phased approach to this consultation is explained in further detail below.
1

<<<PAGE 496>>>

BIOLOGICAL OPINION
Longhorn Pipeline - Phase One
INTRODUCTION
This document represents the Service's biological opinion on the effects of the proposed actions
on the species listed in Texas. The Service has reviewed the proposed plans for the Longhorn
Pipeline Project Maintenance Activities and Minor Construction from Houston to Crane, Texas,
as outlined in the Biological Assessment provided by EPA and OPS. The first phase of the
consultation (Phase One) relates to pipeline right-of-way (ROW) maintenance (clearing and
marking, selected pipeline maintenance construction activities (pipe replacements and
lowering), and pipeline testing (investigation of possible flaws and hydrostatic pressure testing).
The Biological Assessment is hereby incorporated into this Biological Opinion by reference.
The Service will not duplicate all maps, tables, and figures but will instead refer to the Biological
Assessment. There are no species proposed for listing that would be impacted by the proposed
action, therefore, no conference opinion will be issued.
The draft Environmental Assessment on Longhorn Pipeline, and the associated Biological
Assessment are the product of a settlement reached in the matter of Spiller et al. v. Walker et al.
pending in the United States District Court in Austin, Texas (Appendix One). As part of the
Court ordered settlement, the agencies involved in the original litigation were required to
conduct an Environmental Assessment, including specifically, consideration of species listed
under the ESA. The Court ordered EPA and OPS, acting as Lead Agencies, to be responsible for
the Environmental Assessment.
The Court order provides that issuance of any finding of no significant impact (FONSI) with
regard to the proposed Longhorn Pipeline project "shall be conditioned upon implementation" of
measures to protect public safety and the environment (Settlement Stipulation at 6). The order
also prohibits the OPS from authorizing Longhorn to commence operations until Longhorn has
implemented those mitigation measures upon which any FONSI is conditioned (Settlement
Stipulation at 7). The order contemplates that Longhorn will apply for such ESA permits as may
be required in connection with the implementation of any mitigation measures upon which a
FONSI may be conditioned. (Settlement Stipulation at 7). The results of this consultation by the
Lead Agencies with the Service are expected to be incorporated in the Record of Decision issued
by the Lead Agencies. The terms and conditions, mitigatory measures and protections
incorporated herein for the benefit of species are expected to be adopted and incorporated by
Longhorn in its enforceable mitigation commitments or in its operating and maintenance
manuals subject to inspection by, and enforceable by OPS, pursuant to the Pipeline Safety Act
(49 USC 60101 et seq.).
The Court settlement specifies that Longhorn will undertake certain construction and
maintenance activities prior to issuance of a final agency decision in this matter (Settlement
Stipulation at 8-11). The parties to the settlement specifically agreed that any such investments
by Longhorn in Kimble, Menard, Hays, Travis, Caldwell, Bastrop and any counties within the
jurisdiction of the Lower Colorado River Authority after August 25, 1998 would not be
considered "for the purposes of determining the reasonableness of alternatives" (Settlement
Stipulation at 11).
2

<<<PAGE 497>>>

Although the Service and the Lead Agencies are in consultation with respect to the entire
proposed Longhorn project, this consultation is being approached in two distinct, yet related
phases. Service regulations allow for a staged consultation (50 CFR 402.14(k)) where the
Service reviews a project, and provides biological opinions on each incremental step provided
that no irreversible or irretrievable commitments of resources are made. The first phase of the
consultation (Phase One) relates to pipeline ROW maintenance (clearing and marking), selected
pipeline maintenance construction activities (pipe replacements and lowering), and pipeline
testing (investigation of possible flaws and hydrostatic pressure testing). The proposed actions
for Phase One are focused on activities that Longhorn wishes to perform before the final decision
on the environmental review process is made by EPA and OPS. The Service believes that, by
submitting the proposed action, EPA and OPS have made a determination that these activities
can proceed before the final environmental decision is made because these activities are
consistent with the current operational approvals for this pipeline and the settlement agreement.
The Longhorn Pipeline Partners wish to conduct these activities before a final decision is made
because of the potential delay in accomplishing this work due to seasonal constraints placed on
the activities by the presence of endangered or threatened species. The golden-cheeked warbler
and black-capped vireo are migratory birds that would be impacted less if this work were to
commence before the birds return to Central Texas from their wintering habitat in Mexico.
Because the pipeline is existing, routine maintenance is supposed to be occurring, and the
construction impacts proposed are prudent for whatever liquid would flow through the pipeline,
the Service believes that none of these activities constitute an irreversible or irretrievable
commitment of resources, natural or monetary, which have the effect of foreclosing the
formulation or implementation of any reasonable and prudent alternatives or measures. The
Service believes that these investments would not constitute irretrievable commitments of
resources for the purposes of Section 7(d) of the ESA. The Service has evaluated the proposed
activities only with regard to the potential impacts to listed species and compliance with the
ESA. This Biological Opinion does not indicate Service support for any alternatives, including
routing, in the EPA and OPS environmental review process and in no way should be viewed as a
factor in deciding the outcome of that process. Alternative routes may have less potential impact
to listed species. In the opinion of the Service, implementing the proposed projects before
completion of the environmental review process is a business decision made by the Longhorn
Pipeline Partners.
The second phase of the consultation (Phase Two) will be more directly related to the actual
operation of the pipeline, specifically the operation and maintenance of the pipeline system and
the potential effects of a pipeline release. The two phases can be logically separated. Phase One
of the Service's review will focus on those actions that are designed to make the pipeline safer.
The Service can complete this stage of review without pre-judging whether or not the pipeline
will be used. Phase Two of the Service's review will focus on whether and how the pipeline will
be used. It is anticipated that the consultation for the Longhorn Pipeline will also include a
Phase Two Biological Assessment and Biological Opinion that will address issues directly
related to the actual long-term operation and maintenance of the pipeline, specifically the
operation and maintenance of the pipeline system and the potential effects of emergency
response activities in the event of a pipeline release. Both EPA and OPS, within the Biological
3

<<<PAGE 498>>>

Assessment, have committed to continuing the next phase (Phase Two) of consultation.
Based on information available on the proposed project, the Service determines that there is a
reasonable likelihood that the entire project is not likely to jeopardize the continued existence of
any endangered or threatened species or result in the destruction or adverse modification of
critical habitat. During the Phase Two consultation, the Service may change this determination,
based on further review of the existing information or new information gathered during the
Environmental Assessment process or the Phase Two consultation.
This biological opinion is based on: (1) the information that EPA and OPS provided with a
request for formal consultation including the Biological Assessment, (2) the information
previously provided as part of the informal consultation (including the draft Environmental
Assessment), (3) information in our office (including information provided by the public and the
plaintiffs in the lawsuit on the Longhorn Pipeline), (4) field investigations, and (5) other sources
of information. In the request for formal consultation, EPA and OPS attached the Biological
Assessment and copies of all consultation documents for the activities proposed to be addressed
by this Biological Opinion on Phase One activities associated with the Longhorn Pipeline.
CONSULTATION HISTORY
Informal consultation between the Service, Longhorn, and the EPA has been in process since
February 1999. Longhorn was formally designated as the Non-federal Representative for
conducting informal consultation on behalf of the EPA and OPS on February 3, 2000. The
history of consultation (both informal and formal) actions follows in Table One.
Table One.
CONSULTATION HISTORY
DATE
HISTORY
10 February, 1999
Meeting Between Service and Longhorn Representatives
25 February, 1999
Meeting Between Service and Longhorn Representatives
9 March, 1999
Meeting of Service and Radian (consultants writing EA for EPA and OPS)
22 March, 1999
Meeting Between Service and Longhorn Representatives
30 April, 1999
Meeting Between Service and Longhorn Representatives
11 May, 1999
Meeting Between Service and Longhorn Representatives
12 May, 1999
Meeting with the Plaintiffs to discuss the Settlement Agreement
1 June, 1999
Meeting with Barton Springs/Edwards Aquifer Conservation District
8 June, 1999
Meeting Between Service and Longhorn Representatives
11 June, 1999
Multi-Agency Field Tour of Longhorn Pipeline in and near Austin, Texas
29 June, 1999
Meeting Between Service and Longhorn Representatives
4

<<<PAGE 499>>>

Table One.
CONSULTATION HISTORY
30 June, 1999
Telephone Conference Between Service and Department of Justice
19 July, 1999
Meeting Between Service and Longhorn Representatives
27 August, 1999
Meeting Between Service and Longhorn Representatives
10 September, 1999
Meeting Between Service and Longhorn Representative
Meeting Between Service and EP/
13 September, 1999
Meeting Between Service, Austin and Regional Director
27 September, 1999
leeting between Service Austin Office and Washington Offic
Original Draft Biological Assessment Submitted to Servic
30 September, 1999
Meeting Between Service and Longhorn Representatives
4 November, 1999
Meeting Between Service and Longhorn Representatives
9 November, 1999
Meeting Between Service and Longhorn Representatives
16 November, 1999
EPA and OPS Longhorn Public Meeting, Austin
22 November, 1999
Meeting Between Service and Longhorn Representatives
7 December, 1999
Meeting Between Service and Longhorn Representatives
8 December, 1999
Meeting Between Service and EPA
15 December, 1999
Meeting Between Service and Longhorn Representatives
Service Issues Comments on Original Draft Biological Assessment
"Not Likely to Adversely Affect" Determination.
Service Issues Response to EPA Regarding EPA's initial Request for Concurrence on a
17 December, 1999
Meeting Between Service and Longhorn Representatives
6 January, 2000
Meeting Between Service and Longhorn Representatives
Maintenance and Construction Activities in Non-habitat Areas for Listed Species.
Longhorn Requests Concurrence from Service for "Not Likely to Adversely Affect" for
10 January, 2000
EPA and OPS Longhorn Public Meeting, Austin
11 January, 2000
Meeting Between Service, EPA and OPS
17 January, 2000
Meeting Between Service and Longhorn Representatives
18 January, 2000
Meeting Between Service and Longhorn Representative
28 January, 2000
Draft First Phase Biological Assessment received for review
7 February, 2000
Meeting Between Service and Longhorn Representatives
1 February, 2000
Telephone Conference Between Service and Congressman Doggett's Staff
3 February, 2000
consultation
EPA and OPS designate Longhorn the "non-federal repersentative" for purposes of
10 February, 2000
Received EPA Request for Formal Consultation
5

<<<PAGE 500>>>

Table One.
CONSULTATION HISTORY
17 February, 2000
Received Revised Phase One Biological Assessment
17 February, 2000
Received OPS Request for Formal Consultation
DESCRIPTION OF THE PROPOSED ACTION
Project Overview - (Both Phase One and Phase Two)
The following is an overview of the project as proposed by Longhorn Pipeline and is provided to
give an overall context of the proposed project. The specific activities proposed for this
Biological Opinion are detailed in the next section.
Longhorn proposes to operate a 723-mile refined petroleum products (gasoline and jet fuel)
pipeline system from the GATX Terminal in Galena Park, Texas, (near Houston, Texas) to a
refined petroleum products terminal in El Paso, Texas. The pipeline also has a 28-mile
intermediate connection from a station in Crane County to a planned meter station in Odessa,
Texas. The pipeline consists of a combination of 20-inch and 18-inch diameter pipe from
Galena Park Station to El Paso Terminal and an 8-inch diameter pipeline from a station in Crane
County to a meter station in Odessa, Texas. Finally, three as yet to be built pipelines will
connect the El Paso terminal to interstate common carrier pipelines west of El Paso. The
pipeline's initial capacity of 72,000 barrels per day (bpd) will be supplied by a new pump station
at Galena Park and five newly constructed booster pump stations at the following locations:
Satsuma (Harris County), Cedar Valley (Hays County), Kimble County (Kimble County), Crane
(Crane County), and El Paso (El Paso County).
Two new pipeline construction projects remain to be completed. An 8-inch diameter, 2500-foot
lateral that originates at the terminus of the existing Odessa lateral will connect to a terminal
facility in Odessa, Texas, owned by Equilon. Three 8.3-mile lateral pipelines, which originate at
the El Paso Terminal, will connect with Kinder Morgan (formerly the Santa Fe Pacific pipeline)
and Chevron pipelines in the El Paso area. The connection to Kinder Morgan will consist of one
8-inch diameter pipeline and one 12-inch diameter pipeline. The Chevron connection will
consist of an 8-inch diameter pipeline. The purpose of the lateral pipelines is to connect into
Kinder Morgan and Chevron pipelines to distribute product into the Phoenix, Tucson, and
Albuquerque markets. Chevron operates an 8-inch pipeline that delivers product to the
Albuquerque market; Kinder Morgan operates one 12-inch pipeline and one 8-inch pipeline
serving the Tucson market. Other Kinder Morgan pipelines connect Tucson to the Phoenix
market.
The proposed project includes both new construction and refurbishment of an existing pipeline
that has been converted from its former use of transporting crude oil from West Texas to the
Gulf Coast area, the majority of which has been completed. As described in this chapter, the
existing pipeline has been modified to transport refined petroleum products, with flow going
from east to west. Williams Pipeline Company will be the contract operator of the Longhorn
6

<<<PAGE 501>>>

Pipeline System. Longhorn intends to transport multiple grades of gasoline and distillates,
which will include special reformulated grades of gasoline needed to control air emissions in
certain areas of the Southwest.
The Longhorn Pipeline System is designed for service in excess of 50 years and is made up of
four main pipeline segments, several stations, and one terminal, as listed below:
1.
New and refurbished 20-inch diameter pipeline from Galena Park to Satsuma;
2.
Refurbished 18-inch diameter pipeline from Satsuma Station to Crane Station;
3.
New 18-inch diameter pipeline from Crane Station to El Paso Terminal;
4.
New lateral pipeline connections to Odessa and to other pipelines at El Paso;
New Pump Stations;
6.
El Paso Terminal; and
7.
Odessa Meter Station.
A detailed description of the Longhorn Pipeline System is included in the Biological Assessment
(Project Documentation Appendix at Tab One). Future pipeline upgrades, repairs, and
maintenance beyond that identified in the Biological Assessment will be addressed in Phase Two
of the consultation.
Project Description (Actions addressed under this Biological Opinion)
This Biological Opinion only covers those portions of the overall project that have been
specifically identified in the Phase One - Biological Assessment. Appendix Two contains a list
of all of the activities covered in this Phase One consultation including ROW clearing and
maintenance, pipeline maintenance and construction, pipeline testing, and other integrity-related
projects.
Following is a description of each of these procedures and the methods by which they will be
implemented for the Longhorn Pipeline System. Additional detail may be found in Construction
Specification CS4 contained in the Biological Assessment (Project Documentation Appendix at
Tab Four.
Right-of-way (ROW) Clearing, Marking, and Maintenance
The existing pipeline ROW is about 50 feet wide and 723 miles long and most of it has been
routinely maintained and cleared for over 50 years. Longhorn has committed to bring the
surface of the ground within the ROW into "excellent condition" in order to facilitate
surveillance prior to startup of the pipeline (Biological Assessment - Project Documentation
Appendix at Tab 2). Excellent condition is that condition which provides a clear line of sight for
aerial and ground surveillance patrols in order to effectively monitor and inspect the ground
surface along the ROW. A clean and clearly marked ROW provides a distinctive line of
demarcation, indicating a change in land use, where surrounding terrain is natural or heavily
developed. These activities are routine and are conducted periodically by pipeline operators in
the United States.
7

<<<PAGE 502>>>

ROW maintenance will include mowing, brush-hogging, back-dragging, and/or hand trimming
of tall grass or woody re-growth, trimming of tree canopies overhanging the ROW, setting signs,
marking points of intersection (horizontal bends) in the pipeline with PVC posts, and painting
cross-fence posts. ROW mowing is performed by a twin-blade mower or a brush-hog drawn by
a tractor, to a height between two and four inches.
Back-dragging is a method of clearing in rocky terrain; back-dragging involves pulling a dozer
blade backwards across the ground surface which has the effect of bending vegetation over at the
ground surface. Back-dragging typically does not result in the uprooting of vegetation. Rather,
the vegetation is bent or broken just above the ground surface. Back-dragging is used only in
areas where rocks on the surface pose a risk of damage to a mower or brush-hog. Vegetation
around surface facilities such as valve settings is at times spot-treated, by hand application, with
herbicides such as Roundup and Rodeo.
Hand trimming involves line trimmers, chain saws, and similar hand-held equipment. Tree
canopies are trimmed by workers, using chain saws, that are raised within reach of the canopies
by a man-lift. Steel sign posts are typically set by driving the posts directly into the ground.
PVC posts are set into shallow holes dug by post-hole digger. In limited circumstances such as
when vandals repeatedly remove pipeline markers, sign-posts are dug by post-hole digger to
allow the posts to be set into concrete.
Clearing within areas identified as endangered species habitat will not result in any substantial
ground disturbance because only mechanical or hand cutting will be employed. The term ground
disturbance is intended to mean soil disturbance that would result from grubbing brush and tree
stumps. Back-dragging will result in some minor disturbance of the soil surface similar to
grubbing. In limited circumstances, stumps directly over the pipeline, which could have adverse
effects on the pipe, will be spot-treated by hand application, with minimal amounts of non-
aromatic and non-persistent herbicide to retard re-growth. Herbicides will be applied in
accordance with EPA-approved label directions.
All areas of the ROW are subject to periodic clearing from time to time. ROW clearing occurs at
intervals that depend upon the rate of vegetation growth, typically averaging once per year in
arid and semi-arid territory (generally, from Austin to Crane) and typically averaging twice per
year in territory with greater rainfall (generally, Houston to Austin). Further, metropolitan areas
may be mowed as frequently as monthly to meet municipal ordinance requirements and in
response to landowner requests. ROW clearing will be conducted on a schedule that avoids
impacts to species.
8

<<<PAGE 503>>>

Pipeline Maintenance - Construction Planning
Prior to project engineering and scheduling, each site is surveyed by qualified personnel to
determine whether or not the activity (a) may affect threatened or endangered species and
habitat, (b) may cause disturbance of cultural resources, (c) may be subject to Clean Water Act
Section 404 (U.S. Army Corps of Engineers jurisdiction over dredge and fill materials in waters
of the United States), or (d) may be subject to other federal, state or local laws, regulations or
ordinances. Appropriate authorizations are obtained (such as this consultation), and necessary
requirements are identified and incorporated into project planning and engineering
documentation.
Project engineers and technicians perform site inspections to identify site-specific conditions and
features that require consideration in project planning, such as site ingress/egress routes,
workspace requirements, spoil management, equipment storage, servicing and parking needs,
and the like (Biological Assessment - Project Documentation Appendix at Tab 5 and Tab 6).
Such considerations are incorporated into project planning and engineering activities. Unless
required by the particular project or by site conditions, workspace is limited to the established
ROW. Where workspace is required beyond the limits of the established ROW, those areas have
been incorporated into project documentation.
Workspace beyond the limits of the established ROW may be required for a number of reasons.
First, avoidance of habitat or the natural terrain along one side of the ROW may necessitate
expansion of workspace along the opposite side of the ROW. Second, a sloping surface gradient
at a project site may require that spoil removed from the pipeline trench be stockpiled with a
wider base, extending off of the ROW, than would be required at a project site with a level
surface. Further, a project to lower or replace pipe at a creek crossing may require water
diversion measures that necessitate a workspace wider than the established ROW. In addition,
though project equipment is typically aligned along the existing pipeline ROW, project site
conditions such as size, shape and/or slope may require that equipment be centralized in an
equipment marshaling area (typically 25 ft. wide by 100 ft. long) for temporary storage, security
and/or service.
Biological surveys encompass both areas of potential surface disturbance and areas within the
zone of potential indirect construction impacts, such as noise. In addition, applicable project
best management practices (BMPs) are identified at this stage of project planning and
incorporated into planning documentation.
A Project Construction Plan is prepared for each individual project location to document project
planning. The Project Construction Plan contains the following sections of detailed information:
Description of Work for the Project;
Responsibilities and Authorities;
Safety Requirements;
Job Contacts and Notification Requirements Matrix;
Pre-Job Training Requirements;
Environmental Protection;
Project Schedule;
Forms / Documents Required;
9

<<<PAGE 504>>>

Chronological Sequence of Events; and
Appendices as follows:
Appendix 1 - Location Map
Appendix 2 - Drawings, Calculations, and Specifications
Appendix 3 - Environmental Protection Plan
Appendix 4 - Storm Water Pollution Prevention Plan
Appendix 5 - Safety Procedures Document
Appendix 6 - Sample Forms
Project BMPs are defined as procedures and specifications by which environmental controls will
be implemented and include such items as sedimentation and erosion controls, reclamation
procedures, minimization and avoidance procedures, inspection and reporting procedures, spill
containment and cleanup procedures, procedures for addressing unforeseen circumstances,
procedures for addressing foreseen, but unpredictable circumstances, and others. Project BMPs
are identified and adapted from technical guidance manuals generally accepted as providing the
appropriate environmental protection measures, such as the Texas Natural Resource
Conservation Commission (TNRCC) technical guidance manual, Federal Energy Regulatory
Commission (FERC) Environmental Guidance Manuals, and the City of Austin Environmental
Criteria Manual. BMPs are incorporated within the Longhorn Storm Water Pollution Prevention
Plan (SWPPP); an example of an SWPPP is included the Biological Assessment (Project
Documentation Appendix at Tab 6).
Project Environmental Inspectors
Longhorn and Williams shall employ the services of environmental inspectors (such as Horizon
Environmental Service Inc. and 3D/International) at every project site with associated species-
related constraints. These environmental inspectors are qualified under FERC guidelines. The
environmental inspector will remain at each project site during the period of activity to ensure
compliance with all project constraints and project BMPs. The inspector is authorized to dictate
any additional project BMPs that may become necessary during the activity and to modify work
activities and progress to the extent necessary to ensure compliance with project environmental
constraints. However, in the event of a conflict between project constraints and sound
engineering practices, the inspector shall consult with project engineers and the Service, as
appropriate, to achieve project goals while minimizing any impacts to listed species or the
environment. The environmental inspector retains oversight of site closure and performs, or
supervises the performance of, post-activity inspections of project BMPs until site stabilization is
achieved. The environmental inspector will produce appropriate documentation for each
construction location to include BMP compliance logs, photographs, as-built dimensions of
disturbance, and any encounters with listed species during the construction process. The
completion reports for projects listed in Appendix Two, will be provided to the EPA, OPS, and
the Service, annually.
Site Preparation
Prior to site entry, at locations where avoidance and/or minimization of species effects has been
recommended, a qualified biologist will clearly identify areas for avoidance and will stake and/or
flag such areas. The project environmental inspector also surveys the site to ensure that all such
avoidance areas are clearly identified in accordance with conditions approved in the consultation
process and confirms other site-specific areas in which disturbances may occur such as routes of
10

<<<PAGE 505>>>

ingress/egress, spoil management areas, equipment marshaling areas, workspace areas, and
similar areas needed for construction. Project BMPs are reviewed prior to site entry, and the
locations of any necessary physical control measures to be employed are identified. A survey
crew will precede the project equipment and mark the project boundaries. In addition, the
pipeline centerline will be marked at 100-foot to 200-foot intervals.
Site Entry
Upon site entry, the necessary project equipment is transported to the site via the designated
route for ingress/egress. Site access is achieved via improved roadways and the established
ROW, using the shortest available route between improved roadways and the project site.
Routes of ingress/egress account for any potential for effects to threatened and endangered
species and habitat that may exist along the ROW between the improved roadway and the project
site, as well as accounting for other potential impacts to the environment. At times, equipment
will remain on-site only during the time that it is in active use to allow it to be shared between
nearby project sites. However, impacts to potential habitat for listed species from site
ingress/egress will be minimized to the maximum extent practicable.
Prior to any excavation, site vegetation is removed, and project BMPs are implemented. Site
vegetation is cleared to the extent necessary for project completion, so long as the vegetation is
not located in areas identified for avoidance. Clearing is accomplished by the methods described
in above (ROW Clearing), though vegetation within the workspace may require removal.
Project BMPs are installed in accordance with project planning documentation and in accordance
with the site-specific SWPPP.
Task Descriptions - (Process Once All Authorizations Are Obtained)
The following task descriptions identify process steps that occur once all authorizations are
obtained and regulatory requirements are identified and incorporated into project planning and
engineering documentation. Detailed procedures for each of the activities summarized below are
available in Pipeline Construction Specification CS4, which is included in the Biological
Assessment (Project Documentation Appendix at Tab 4). In the event of a conflict between
Construction Specification CS4 and the site-specific components of the Project Construction
Plan, the Project Construction Plan will be followed.
Pipeline Lowering and/or Replacement - Open Terrain
Once the project site has been prepared and equipment brought onto the location, the following
major activities take place.
•
The pipeline segment to be replaced is isolated by cutting and plugging at
boundaries. Williams operating personnel will establish that the line is not
pressurized and is properly isolated such that the contractor may cut the pipeline
at the project limit boundaries. Mechanical plug devices will be utilized to
prevent residual product leakage from the pipeline segments or entry of foreign
materials into the pipeline. These devices shall be secured to prevent their loss or
tampering.
11

<<<PAGE 506>>>

Remove large rocks, if any, from ROW work area to appropriate disposal/storage
area. Track hoes with buckets are used, unless larger rocks require grapple
capable (clam) buckets.
Remove and set aside topsoil spoil (double ditch practices). Double-ditching will
be required in areas where native plant communities need to be re-established, or
there are topsoil improvements, such as sodded lawn areas and cultivated fields.
Double-ditching allows topsoil management by making two passes to remove and
segregate spoil; one to remove and set aside topsoil and one to remove and set
aside subsoils.
Remove overburden and expose pipe. Utilizing track hoes, remove and set aside
overburden from the pipeline and load and remove excess amounts from the work
site for disposal. Unsuitable overburden (i.e., large rocks) will be disposed of in
approved sites.
Cut pipe into subsections at road and water crossings. Expose and cut the
pipeline at road crossing boundaries to isolate the removal section into
subsections. Utilize drain pans to recover any remaining liquids as the cut is
made. Install mechanical plugs in all exposed pipe ends.
Raise and crib pipe alongside the trench. Properly manage any coating which
comes loose from the pipe.
• Prepare and wrap pipe for disposal. Double wrap the pipe sections with 6-mil
thickness plastic wrap, taping and sealing each wrapping separately. Ensure that
the ends are sealed to prevent any release of coating.
• Remove pipe from ROW. Load and remove the wrapped pipe sections by truck.
Care will be taken to preserve the plastic wrapping on the pipe. Secure the pipe
to the trailer and haul to the disposal site for final disposition.
• Cleanup and grade ROW for survey and trenching operations.
•
Capture, contain, and remove any remaining coating materials/scraps using
project-prescribed methods for asbestos containing materials. Prepare the grade
on either side of the ditch to accommodate the trenching machinery, removing
any large rocks. Survey crew should mark and stake the centerline offsets as
required by the trenching crew.
•
Deepen trench to new depth. Depending upon the length of the desired lowering
and/or replacement, and depending upon whether the trench is in soil or rock, a
track-hoe or wheel trencher (rock saw") deepens the trench to the new depth. A
wheel trencher is typically used for longer trenches and trenches in consolidated
rock. Dust generation is monitored during trenching, and a water fog of the
trenching mechanism may be employed to minimize airborne dust in non-rural
areas.
12

<<<PAGE 507>>>

•
String new pipe along trench. As the ditch is prepared, the pipe may be strung
along the workpad in anticipation of measuring and marking for bending,
welding, and lowering operations. The survey crew will note the pipe heat and
identification numbers sequence for the individual pieces as they are placed. The
survey crew will survey the new ditch profile and mark the pipe for calculated
field bends.
Make field bends. The field bending crew will proceed ahead of the welding
crew to make any required field bends. The contractor may also elect to set up
field bending in one of the equipment marshaling areas and perform bending there
rather than on the ROW.
Weld and Radiograph new pipeline. The welding crew will proceed to weld the
pipeline. Inspectors will survey and note the weld numbers and identification of
the welders for this activity. The radiography crew will follow the welding crew.
Inspection will be per standard specification API 1104 and include 100%
radiography of all girth welds.
•
Apply weld joint coating and inspect pipeline coating for "holidays". A holiday
is a point where the coating fails to electrically insulate the pipe. Weld joint
coating will be applied as specified in the Project Construction Plan. This will be
by field-applied FBE (fusion bond epoxy). Following weld joint coating, the
entire coating system will be inspected for holidays and repaired as required.
Pad and lower pipe. Pad the ditch and lower the pipeline as specified in
Construction Specification CS4. Install ditch plugs as required to stabilize
pipeline during hydrotest and backfilling. The pipeline coating will receive a
final "jeeping" as the pipe is lowered to ensure its integrity. Jeeping is the
process of electrically inspecting the pipeline coating to ensure that no holidays
exist in the coating, so named due to the "jeeping" sound the inspection device
emits when a holiday is identified.
•
Complete as-built survey. Complete as-built survey activities, noting weld
locations, pipe identification codes, and location and stationing of bends, fittings
and other such features for inclusion in alignment sheet drawings.
Backfill and compact trench. Backfill and compact the ditch according to
Construction Specification CS4, maintaining sufficient cover to allow for settling.
Install ditch breakers and silt fencing as appropriate for surface erosion control
until the site is stabilized.
Perform hydrostatic pressure test on new pipeline segment. Obtain fresh water
for pressure test and begin line fill behind a pig. The test pressure and test
duration will be established and specified in the Project Construction Plan or in
separate hydrostatic testing plans.
•
Drain and dispose of hydrostatic test water. Upon completion of the hydrostatic
test, the test water is either pushed with nitrogen to a subsequent test site or
13

<<<PAGE 508>>>

removed into mobile tanks for hauling to a disposal facility. Test water is
controlled to ensure that it is fully contained in order to prevent discharge to the
environment.
•
Perform final tie-ins. Remove the test headers and make the final tie-ins of the
new pipe segment to the existing pipeline. The tie-in welds will be 100%
radiographed to ensure their integrity. Coat the tie-in welds with an appropriate
joint coating system compatible with both FBE and coal tar coatings. The coating
is inspected, or jeeped, and any holidays are repaired. The tie-in locations are
backfilled and compacted.
•
Clean, grade, and seed ROW. Following installation of erosion control measures,
re-seed the ROW with native grass seed and/or sod as prescribed for the location.
Re-install pipeline markers and any traffic control devices to limit or restrict
ROW access by motor vehicles.
•
Perform site cleanup and restoration. Clean up equipment marshaling and
material storage sites, ensure that the worksite access roads are restored to prime
condition, and that any road access ways are cleaned and restored.
Pipeline Lowering and/or Replacement - Creek Crossing
Pipeline lowering and/or replacement at creek crossings follows generally the same sequence of
activities described above for open terrain; however, the additional activities described below
apply to the actual creek crossing area. In addition, creeks may be crossed by either trenching or
boring. Each crossing method is summarized separately below.
Trenching
A trenched crossing is lowered and replaced in much the same manner as an open terrain project;
however, incremental measures are employed to ensure both that erosion and sedimentation are
minimized and that no potentially harmful materials are discharged to the waterway. Pipeline
Construction Specification CS4 in the Biological Assessment (Project Documentation Appendix
at Tab 4) provides additional details.
•
Cut pipe at creek crossings. Expose and cut the pipeline at the creek crossing
boundaries to isolate the removal section into subsections. Utilize drain pans to
recover any remaining liquids as the cut is made. Install mechanical plugs in all
exposed pipe ends.
•
Implement water quality protection measures. Staging areas, spoil storage areas,
and additional workspace areas are located in upland areas above the creek bed.
Hazardous materials such as chemicals, fuels, lubricating oils and any other
potentially harmful materials are maintained at least 100 feet from the water body.
BMPs are implemented to prevent sedimentation. Flumes, dams, equipment
bridges and other diversion devices are installed as necessary to perform "dry
ditch" excavation.
14

<<<PAGE 509>>>

•
Erosion control measures are employed after project completion to ensure that
stream flows do not cause erosion of disturbed areas and subsequent
sedimentation. Erosion controls protect against sedimentation and prevent
stream flow from removing pipeline cover which could expose the pipe to stream
bed forces. Erosion control measures are site-specific, depending upon site
conditions, and include berms, dikes, water bars (perpendicular to the pipeline
alignment), silt fences, staked hay bales, seeding, mulching, hydro-mulching, rip-
rap, and trench plugs.
Boring
Stream crossings may be installed by boring rather than trenching, depending upon hydrologic
setting, engineering considerations, and soil types. The existing pipeline may be abandoned in
place after obtaining approvals from the landowner and, if necessary, state and federal
authorities, and after (a) filling the pipe with an inert material such as grout or concrete, or (b)
sealing the ends of the pipe. The pipe may not be abandoned in place if its presence could
interfere with stream flows or interfere with future uses of the waterway.
Boring a stream crossing requires the use of a work space for installation of bore pits in which
the boring equipment operates. The boring operations typically require a workspace
approximately 100 to 250 feet wide by 150 feet long. The work spaces are located above the
high water mark unless topography or other factors dictate otherwise. Typically, no instream soil
disturbance occurs, and BMPs are employed to ensure that spoil storage and other project
activities do not cause erosion or sedimentation.
From within the bore pits, the boring equipment creates a parabolic pathway to the pit on the
other side of the stream bed. Bored material is circulated out of the bore and retained at the
upland spoil storage area. The bore is sealed with grout or bentonite to fill fissures along the
course and to ensure bore stability.
The new pipe is then pulled through the bore using equipment designed for that purpose. Once
the pipe is welded, inspected, surveyed, coated and tested, the excavations are filled and
compacted, and the site is restored. Site restoration and stabilization is achieved in the same
manner as described in above (Pipeline Lowering and/or Replacement - Open Terrain). Any
necessary erosion and sedimentation controls are employed, and the site is inspected and
maintained until final stabilization is reached.
Hydrostatic Testing - Overview of Activities
A hydrostatic pressure test is scheduled to be performed to ensure the integrity of the system.
This test is scheduled to commence in February 2000 and conclude in May 2000. Hydrostatic
testing will start at the Longhorn GATX pump station in Galena Park (Houston) and proceed
westward to Crane Station. The test medium will be potable water from a local municipal supply
source. In the event some water is lost due to pipe failure, or if water is needed to fill longer test
sections, fresh make-up water will be acquired, by permit, from sources crossed by the pipeline
(i.e., from rivers or streams) or other sources of fresh water.
The hydrostatic testing occurs in segments, which are subdivided into test sections of varying
lengths. Factors that contribute to test section length include:
15

<<<PAGE 510>>>

(a)
target test pressures;
(b)
pipe size and grade;
(c)
the presence or absence of species and habitat;
(d)
the location of valves and pump stations; and
(e)
elevation changes along the pipeline.
Due to additional factors, two test sections will not be tested during the Houston to Crane
hydrostatic testing project. Those two sections are areas that encompass habitat for the Houston
toad and areas of potential effect to the Barton Springs Salamander (including the recharge zone
and part of the adjacent contributing zone (on each side) of the Edwards Aquifer). Rather, those
sections will be tested after Phase Two consultation relating to pipeline operation, maintenance
and emergency response, and after maintenance construction to replace pipeline segments in
those areas is completed.
To facilitate hydrostatic testing of the pipeline, headers will be installed on the pipeline at
intervals along its length which divide the pipeline into segments for discrete testing. There are
forty (40) header sites involved in the test. A general description of the installation of the test
headers follows. Additional information is provided in the Biological Assessment (Project
Documentation Appendix at Tab 8). Headers vary in configuration; however, all function
similarly to allow the introduction of test water, the pressurization of the test segment and the
displacement, after testing, of the test water to the following test section.
•
Prior to any work, the sites will be subject to an environmental, endangered
species, and archeological survey conducted by qualified third-party biologists
and archeologists. The headers will be installed by excavating an area
approximately 20 ft. wide x 80 ft. long x 4 ft. deep around and under the pipeline.
The spoil will be stored on the temporary work easement. The topsoil will be
segregated from the sub-grade for restoration of the site following the hydrostatic
test. Storm water management during construction and testing will be by methods
prescribed in the SWPPP, an example of which is included in the Biological
Assessment (Project Documentation Appendix at Tab 6).
•
The exposed pipe will be cut and spread apart horizontally, and pre-fabricated
headers will be welded to each section. The downstream header shall have a wire
brush pig and displacement pig inserted in it before it is welded on the pipeline.
A 6-inch temporary crossover pipe with valve will be installed between the
upstream and downstream header. Upon completion of the test, the hydrostatic
test water will be displaced into the next test segment by nitrogen. The test
section will be vented to atmosphere and the temporary piping and headers will
be removed. The pipeline will be tied back together with a joint of new pre-tested
pipe and the joints will then be coated and wrapped to provide corrosion
protection. Coating is inspected for holidays, and repairs are made if holidays are
identified. The excavated area will be backfilled and compacted with the sub-
grade material in the spoil pile followed by the topsoil to finished grade to match
the surrounding terrain. The disturbed area is seeded with native grasses or sod,
and BMPs are inspected and maintained until the site is stabilized. Total surface
16

<<<PAGE 511>>>

workspace requirements for test header installations are about 100 feet wide by
150 feet long along the pipeline.
Hydrostatic Testing - Potential Failure of Pipe
The locations of potential hydrostatic test failures cannot be accurately predicted, the volume of
test water discharged cannot be accurately predicted or calculated, and the number of
investigative excavations cannot be predicted. The inability to accurately predict the potential
impacts of hydrostatic test failures precludes any pre-activity attempt to predict and/or estimate
the potential effects of test failures. Any such attempt would be likely to result in inaccurate
estimates. Therefore, Longhorn proposes to provide for a contingent methodology for
calculating any such effects.
Of the methodologies available for calculating the effects of activities upon species and habitat,
the most applicable is the Habitat Equivalency Analysis (HEA) methodology developed by the
National Oceanic and Atmospheric Administration for Natural Resources Damages Assessments
(NRDAs).
The HEA methodology is briefly described by the following steps.
•
The duration and extent of injury are documented and estimated from the time of
injury until the resource recovers to baseline.
The services provided by a compensatory project are documented and estimated
over the full life of the project.
•
The size of a compensatory project is calculated such that the total increase in
services provided by the compensatory project equals the total interim loss of
services due to the injury.
•
The cost of the compensatory project is calculated.
A more detailed description of the HEA methodology is provided in Biological Assessment
Project Documentation Appendix at Tab 10. Longhorn's will execute the following sequence of
measures in the event a hydrostatic test discharge occurs in areas of concern for species and/or
habitat:
In the event of a test failure, immediately notify a qualified biologist, who will be
maintained on standby along the test segment, and direct the biologist to the
failure site;
•
If a discharge occurs, the biologist will assist the identification of response
actions to minimize potential impacts to the environment; and,
•
The biologist will perform a field survey to document the loss of, destruction of,
or injury to natural resources (a) at the location of any excavation, whether the
excavation is for location of a failure or for repair of pipe; (b) within the area of
17

<<<PAGE 512>>>

impact of the test water; and (c) in any other areas affected by the response to the
test failure, as at any other construction site.
The effects, if any, of the hydrostatic test failure upon species and/or habitat will then be
calculated pursuant to the HEA methodology. Longhorn shall compensate for the value of any
such adverse effects by paying the monetary value of an appropriate compensation project to
conservation efforts directed at the preservation and recovery of the affected species and habitat
in the region where the impact occurred. For example, if a hydrostatic test resulted in a take of
golden-cheeked warbler or black-capped vireo habitat, Longhorn would contribute the requisite
monies to appropriate conservation entities acceptable to the Service, such as Balcones
Canyonlands Conservation Plan, The Texas Nature Conservancy, or similar initiatives.
Cathodic Protection Enhancements
Enhancements of the pipeline cathodic protection system consist of (a) installation of anode beds
and (b) re-coating of sections of existing pipe. The cathodic protection system protects the pipe
from corrosion. These enhancements are identified and described in the Biological Assessment
(Project Documentation Appendix at Tab 2), and the locations where activities may affect
species and habitat are identified in Appendix Two. Project planning is performed in a manner
similar to that described above.
Installation of deep anode ground beds requires a series of vertical bores within which sacrificial
anodes are placed; the anodes within each bore and among the series of bores are connected by
subsurface wiring that is then connected to the pipeline. The bores and wiring trenches are
installed within the existing ROW. During boring, a circulating pit is dug to contain cuttings
removed from the bore. After project completion, the pit is filled, excess cuttings are removed
for disposal, and the site is closed in the manner described in previous discussions of
construction site closure. An example project work plan and related diagrams that provide
additional detail about deep ground-bed installation are included in the Biological Assessment
(Project Documentation Appendix at Tab 11).
Pipeline coating reconditioning involves the same activities required for a pipeline lowering or
replacement, with the exception of the process steps to remove existing pipe and install new
pipe. A coating replacement site undergoes the project planning, site preparation, site entry, and
site closure steps much as described above. Since the pipe is not cut, any residual liquids within
the pipe do not present contamination potential. Asbestos containing pipe coating is managed in
accordance with the provisions of the Environmental Protection Plan and the Project
Construction Plan (Biological Assessment - Project Documentation Appendix at Tabs 5 and 3,
respectively). All coating reconditioning is inspected, or "jeeped," and any holidays are
repaired.
Surge Pressure Protection
To reduce the risk of over-pressurization of the pipeline, Longhorn will implement system
changes and operating practices to limit surge pressures to no more than maximum operating
pressure in sensitive and hypersensitive areas identified by the EPA and OPS. (Biological
Assessment - Project Documentation Appendix at Tab 2). One system change involves the
installation of over-pressure activated by-pass systems that will allow a pressure spike to be
relieved around certain gate valves. The installation of a by-pass system involves the same
18

<<<PAGE 513>>>

process steps as the installation and removal of a hydrostatic test header; see above (Hydrostatic
Testing - Overview of Activities). The by-pass system to be installed at the east bank of the
Llano River will use the same work location as the hydrostatic test header to be installed at that
valve site.
Investigations
Projects to investigate possible pipe dents and corrosion anomalies follow the same planning and
preparation procedures for a pipeline lowering/replacement, but on a lesser scale. Table 2
identifies relevant information for, and the locations of, projects to investigate possible pipe
dents and corrosion anomalies.
Typical investigation sites require a trench approximately 20 feet in length. If a dent or anomaly
cannot be field repaired, a segment of pipe will be removed and replaced, with the length
replaced at least twice the pipe diameter. Coating and coating inspection and repair, as well as
site closure, follow the procedures described in Section 4.0 of the Biological Assessment.
Avoidance and Minimization
Longhorn will, to the extent reasonably possible, conduct the maintenance construction, testing,
and other subject activities in a manner that avoids potential effects to species and habitat. If
avoidance is reasonably and practically not achievable, Longhorn will conduct the activities in a
manner that minimizes any potential effects. Controls and other measures designed to achieve
that goal are described in the foregoing descriptions of the various activities. A number of those
controls and measures are summarized as follows:
• Identifying and marking habitat areas for avoidance;
• Planning project implementation to minimize the potential for any effects;
Using FERC qualified environmental inspectors with authority to alter project
implementation procedures in sensitive areas;
Adjusting project timing to avoid breeding populations; for example, projects in
Houston toad habitat will avoid the months of January through June and projects
in golden-cheeked warbler and black-capped vireo habitat areas will be avoided
March 1 through August 1 and March15 through September 1, respectively;
•
Implementing storm water pollution control BMPs even when not required by
permit;
•
Maintaining qualified biologists in hydrostatic test project areas for immediate
response in the event of a test water release in a habitat area;
•
Avoiding, until project planning is accomplished, hydrostatic testing over the
Toad habitat areas; and
Edwards Aquifer recharge zone, portions of the contributing zone, and in Houston
19

<<<PAGE 514>>>

•
Conducting additional species surveys along the pipeline ROW to determine
actual presence or absence of species and populations where present.
Additionally, work in areas of noise-sensitive species (i.e., golden-cheeked warbler and black-
capped vireo) will be avoided during the breeding/nesting season. If work must occur in habitat
areas during noise-sensitive seasons, the Service will immediately be notified.
Proposed Minimization to Offset Impacts to Listed Species
Land Conservation Funding
The extent of the project and timetable for implementation prevent Longhorn from completing
detailed surveys for threatened and endangered species in all potential habitat where disturbance
or destruction may occur, due to the variable survey times for each species and extensive
amounts of habitat areas involved. Exact quantification of impacts to all listed species from
scheduled activities is not possible if the project is to be completed on a timely basis. Therefore,
Longhorn has requested that the Service prepare a biological opinion based on an evaluation of
impacts to potential habitat, rather than impacts to individuals or identified occupied habitat.
Longhorn proposes to provide benefits to the species based on potential habitat impacts as if it
were occupied. This will insure that all possible impacts are considered and provide maximum
species benefits. Longhorn will apply a standard formula to potential impacts to determine
appropriate minimization. The formula is: impact acreage × 1.2 x fair market value of land in the
area. This formula is modified for Houston toad habitat to use a 3x multiplier instead of 1.2 due
to the more critically imperiled nature of the toad population in general. Longhorn will also
apply a one-time 10% inflation factor to anticipate increases in land values over time.
Within 60 days following the Biological Opinion, Longhorn will engage two licensed appraisers
to determine the average value of land in the vicinity of the impact areas for each species along
the pipeline. If the two appraisals differ more than 5%, then a third appraisal shall be obtained to
reach a determination. All appraisals shall take into account land uses and conditions in the
vicinity. The current calculation of compensation, set out below, will then be revised based upon
the average of the two or three appraisals.
Longhorn proposes a series of payments over time to fund the habitat acquisition, with such
payments being made in a manner which will maximize benefits to the potentially affected
species. The initial payment will go toward conservation efforts directed to the Houston toad
and the Tobusch fishhook cactus because those species face a relatively greater prospect of
decline than the remaining species.
Longhorn will provide the land conservation funding amount to one or more conservation
organizations with funds devoted to conservation of the affected species. Payments will be made
on an annual basis over a six-year period. Future land values shall be determined on the basis of
appraisals performed every second year following the initial appraisals and determined
employing the same methodology as described above. The remaining compensation due from
Longhorn shall then be recalculated based upon the compensation acreage remaining to be
funded and the most recent land appraisals for such acreage.
20

<<<PAGE 515>>>

Longhorn and the Service will identify conservation organizations that provide the greatest
benefit to the affected species as a whole. Potential recipients may include the National Fish and
Wildlife Foundation, the Texas Parks and Wildlife Department (TPWD), Texas Nature
Conservancy, Texas Land Trust, Trust For Public Lands, the Hill Country Conservancy and
similar comprehensive conservation initiatives. The Service will also work with TPWD and
other partners to accomplish the greatest benefit for listed species.
Longhorn may at its discretion, at any point in time, (a) pay all outstanding compensation on the
basis of the most recent appraised values; or (b) purchase required acreage acceptable to the
Service for any given species.
Given the timing matters identified above, Longhorn will provide assurance to the Service that
the calculated compensation (refined on the basis of actual land appraisals) will be funded on
time and in full. Such assurance will take the form of security that assures the Service that the
compensation will be funded. Longhorn proposes such methods as a bond, a letter of credit, an
escrow, or similar such mechanism reasonably acceptable to the Service. The security will cover
compensation not proposed for immediate funding and the one-time 10% escalation value
applied to same. Longhorn makes this proposal conditioned upon the requirement that, as
payments are made or in-kind compensation is provided, a corresponding reduction be made in
the compensation acreage outstanding and thus in the amount of security required. Before
issuance of the Biological Opinion, Longhorn shall provide to the Service reasonable evidence
that the security is in place.
Based upon the formula, and the impacts described above, and assumed land values, the present
calculation of land conservation funds for minimizing adverse affects would be as follows in
Table Two.
Table Two. Proposed Minimization to Offset Impacts to Listed Species
Price
Inflation
Species
Acres
Multiplier
Acres
per acre
factor
Total ($)
Texas prairie
61.3
1.2
73.56
$3000
10%
242,748
dawn
Navasota
5.2
1.2
6.24
$ 1000
10%
6,864
ladies'-tresses
Houston toad
20.6
3.0
61.80
$2000
pay now
123,600
Golden-
116.8
12
140.16
$2000
10%
308,352
cheeked
warbler
Black-capped
41.7
1.2
50.04
$ 1000
10%
55,044
vireo
Tobusch
213.2
1.2
255.84
$1000
pay now
255,840
fishhook cactus
21

<<<PAGE 516>>>

Total
992,448
Longhorn's Monitoring Commitment
In addition to Longhorn's land conservation funding, they have also committed to survey the
existing ROW to determine the presence/absence of listed species. The following summarizes
the Longhorn Monitoring Commitment for each potentially affected species.
Longhorn will survey for the Texas prairie dawn within the potentially suitable
habitat areas to confirm its presence or absence. The survey will be conducted
within the ROW in areas identified as potential habitat in March of 2000 to
determine if the Texas prairie dawn is present, and if so, its distribution and
abundance.
Longhorn will conduct a Fall survey (15 October to 15 November, 2000) for the
Navasota ladies'- tresses within the ROW if suitable climatic conditions occur to
determine the presence or absence of this species, and if present, its distribution
and abundance.
•
For the Tobusch fishook cactus, Longhorn will conduct a blooming period survey
(March to April 2000) within the ROW throughout Kimble County to determine
the species' distribution and abundance.
One or more additional Spring surveys (as acceptable to the Service) for the
Houston toad will be conducted along and downstream of the pipeline to
determine the presence or absence of toads and their overall distribution and
abundance.
•
One to two additional Spring breeding season surveys (as acceptable to the
Service) will be conduced for the golden-cheeked warbler along and adjacent to
the ROW within the potential habitat areas to determine habitat utilization and
overall distribution and abundance.
•
One to two additional spring breeding season surveys (as acceptable to the
Service) will be conduced for the black-capped vireo along and adjacent to the
ROW within the potential habitat areas to determine habitat utilization and overall
distribution and abundance.
STATUS OF THE SPECIES/ENVIRONMENTAL BASELINE
Status of the Species and Distribution
The following is a review of the status of each species being considered in this biological
opinion that may be adversely affected by the proposed action. The Service has reviewed the list
of threatened and endangered species and identified potential impacts to the following species.
Texas prairie dawn (Hymenoxys texana) - The Texas prairie dawn is a small, delicate annual to
6 inches tall with single or branching stems. It has small yellow flowers blooming in late March
22

<<<PAGE 517>>>

to early April. It occurs in sparsely vegetated areas of fine-sandy compacted soil. Specifically,
the species occurs in the northern part of the Gulf Coastal Prairie in Harris and Fort Bend
counties, where it is found in poorly drained depressions or saline swales around the periphery of
low, natural mounds (mima mounds) in open grasslands. These mostly barren areas are sparsely
vegetated, and the soil is often covered with a blue-green alga (Nostoc sp.). It can also occur on
disturbed soils such as rice fields, vacant lots, pastures, and possibly pipeline ROW if the soil
structure remains relatively intact.
There are fewer than 35 known sites recorded for the species, and several have been lost in
recent years to urbanization in the Houston area. Most populations remaining are small, and are
on private land. Very few sites currently have any form of protection. The primary threat to the
species is habitat destruction as a result of urbanization, roadway construction, and conversion of
habitat for agricultural purposes.
An assessment of potentially suitable habitat for the Texas prairie dawn was conducted by
Horizon in early June 1999 along the Longhorn pipeline ROW in western Harris and eastern
Waller counties from the Satsuma Station on the west edge of Houston to near Monaville in
Waller County. Three areas along the ROW, one in Waller County and two in Harris County,
exhibited native range conditions with suitable soils that could be considered potentially suitable
habitat areas for the prairie dawn. All other areas along the pipeline within the area investigated
had been converted to row crop (corn), monoculture, hay or grazing pasture, or disturbed for
land development. A survey for the prairie dawn has not been conducted within the potentially
suitable habitat areas to confirm its presence or absence.
Navasota ladies'-tresses (Spiranthes parksii) - The Navasota ladies' tresses was listed as
endangered on May 6, 1982, without critical habitat. This member of the orchid family occurs
primarily in moist, sandy soils in small openings in post oak savanna vegetation. The species is
known to occur in Brazos, Burleson, Fayette, Freestone, Grimes, Jasper, Leon, Madison,
Robertson, and Washington counties (USFWS 1984b).
Currently, approximately 149 sites have been recorded, representing perhaps 75-80 distinct
population areas, predominantly concentrated around two centers of distribution, one in southern
Brazos County and one in central Grimes County. Some of these recorded sites have been
damaged or destroyed since they were reported. Together these population centers contain the
majority of known sites and individuals (Wilson 1993). However, the majority of sites contain
fewer than 25 recorded plants. It is known that for this species not all individuals in a population
are visible above ground in a given year, and most of these sites have been visited only once, so
demographic data on populations is very limited. Nevertheless there is great concern among
botanists that most of these sites may not represent viable populations.
Navasota ladies'-tresses occur in a variety of moist sandy soils near drainages, in the Post Oak
Savannah vegetation associated with the Navasota, Brazos, and Trinity River watersheds.
Navasota ladies'-tresses are typically found on erosional remnants between rills in slightly to
moderately eroded areas along minor intermittent tributaries, from the upper drainage head,
extending along the edges of temporary streams to the flood plain of permanent streams.
Navasota ladies-tresses grow on sandy loam soils and are often associated with post oak,
blackjack oak, yaupon, slender bigelowia (Bigelowia nuttallii), and Spiranthes cernua.. Typical
23

<<<PAGE 518>>>

habitat consists of natural openings in upland Post Oak Savanna vegetation (Poole and Riskind
1987, USFWS 1984b, Wilson 1993). Plants are believed to be situated where subsurface flow or
seepage of water occurs seasonally, a common feature in other species of the genus (Arft and
Ranker 1995, Kathy Parker, pers. comm.). While Navasota ladies'-tresses is found in small
naturally created openings in the post oak woodlands, it cannot be regarded as a disturbance
species, as it usually occurs in well developed woodland and is not a colonizer of extensively
disturbed areas. There are few records in flood plain forests, open savannahs and shrublands that
have experienced little or no grazing pressure, and in hillside seepages.
Navasota ladies'-tresses is extremely slow-growing and long-lived. Rosette leaves support the
formation of a storage tuber between November and March that sequesters resources in
preparation for sending up a leafless bloom stalk at some future time. It is believed that often
plants require more than one year of photosynthate storage to successfully send up a bloom stalk.
If local conditions have not been favorable for forming sufficient below ground reserves, the
plant may not bloom (Wilson 1993).
Navasota ladies'-tresses apparently does not transplant well. In a mining project in Grimes
county by Texas Municipal Power Association (TMPA), plants in the impact area were removed
and transplanted into an adjacent habitat area. Plant survival has been low in most sites (TMPA
1996). Similarly, in an experiment in Lick Creek Park near College Station, Dr. Hugh Wilson
planted some seedlings which survived into their second season, but died prior to the third
growing season (Wilson 1993).
Because of the low numbers of individuals reported from populations, the slow growing nature
of the plants, its unusual habitat requirements of openings in mature vegetation, and its
sensitivity to disturbance and transplanting attempts, the species is not regarded as being very
resilient, and recovery following any damage to a population is expected to be slow.
The primary threat to Navasota ladies'-tresses is destruction or modification of habitat due to
urbanization, clearing for agricultural production, or mining (47 FR 19539, USFWS 1995,
1984b). Destruction of understory by feral pigs is also a problem in some areas. More than 40
known sites have been lost in the last ten years to mining or urbanization. Post oak savannah in
many of these counties continues to be converted to bermuda grass pasture. Subsequently,
habitat loss continues, particularly in the areas of Brazos and Grimes counties where most sites
are located. The City of College Station in Brazos County is growing rapidly, particularly in the
southern and southeastern fringes where most known populations are located. Mining in Grimes
County disturbs more than 7,000 acres every 5 years (Wilson 1993).
In Fayette County, the species is known from one small population approximately 6 miles south
of the pipeline and 2 miles north of the town of Fayette. Based on analysis of soil distribution,
vegetative cover, physiographic setting, and field assessment by Horizon in November of 1999,
two small areas of potential habitat for Navasota ladies'-tresses are present along the pipeline
corridor. No surveys for the species have been conducted along the pipeline.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii) - Tobusch fishhook cactus is a rounded,
biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5 inches in diameter. There are 3 to 5
central spines with the upper 2 to 3 erect and straight and the lower central spines hooked at the
tip and spreading. The plants are very inconspicuous, and produce cream to yellow flowers from
February through early April. These cacti have been demonstrated to be obligate outcrossers
24

<<<PAGE 519>>>

pollinated by native bees with a foraging distance of about 1/4 mile, and seeds are dispersed by
native ants.
The species occurs on limestone gravels of stream terraces, limestone ledges, ridges, and
openings on the rocky hills of live oak - juniper woodlands in Bandera, Edwards, Kerr, Kimble,
Kinney, Real, Uvalde, and Val Verde counties. A significant number of populations have been
documented in Kimble County.
Currently about 50 sites are recorded for the species, following a recent range - wide
representative survey. Most of the populations are extremely small (5-20 plants), with
individuals widely scattered. Known sites are separated by large distances. Most existing
populations are on private land, and there are very few protected sites. Demographic data
collected in monitoring studies over the last five years or so show that only one of the known
populations is even marginally viable. The species is extremely slow growing and does not
appear to reproduce until 10-17 years of age. It takes four successful flowers/fruits to produce
one seedling (Jackie Poole, Texas Parks and Wildlife, pers. comm.). It is estimated that very few
viable populations (10-15) remain over the 8 county range of the species. The survival and
recovery of the species will require restoration and careful management, to provide sufficient
numbers of populations and individuals in effective proximity to each other for successful
pollination (and gene flow) to ensure the continuity of the species.
Studies examining the probable reasons for population declines are underway. Threats to the
species are believed to include inappropriate timing of range management practices (such as fire
and clearing practices that disturb the soil), extensive predation by beetle grubs, loss of habitat to
real estate development, and some collection by cactus enthusiasts.
An assessment of potentially suitable habitat and pedestrian survey for the cacti was conducted
by Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble County, and
no specimens were observed within the ROW. However, one Tobusch fishhook cactus was
observed about 50 feet north of the cleared ROW. All of the ROW within Kimble County has
been identified as potentially suitable habitat.
Golden-cheeked Warbler (Dendroica chrysoparia) - The golden-cheeked warbler is a small,
migratory songbird, 4.5 to 5 inches long, with a wingspan of about 8 inches. The male has a
black back, throat, and cap, and yellow cheeks with a black stripe through the eye. Females are
similar, but less colorful. The lower breast and belly of both sexes are white with black streaks
on the flanks. Typical nesting habitat is found in tall, dense, mature stands of Ashe juniper
(cedar) mixed with trees such as Texas (Spanish) oak, Lacey oak, shin (scalybark) oak, live oak,
post oak, Texas ash, cedar elm, hackberry, bigtooth maple, sycamore, Arizona walnut,
escarpment cherry, and pecan. This type of woodland generally grows in relatively moist areas
such as steep-sided canyons and slopes. A mix of juniper and deciduous trees on the slopes,
along drainage bottoms, and in creeks and draws provides ideal vegetation for birds. Warblers
are also occasionally found in drier, upland juniper-oak (i.e., live oak, post oak, blackjack oak)
woodlands over flat topography.
An assessment of potentially suitable habitat and surveys for the golden-cheeked warbler was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from Austin,
Texas, to the Mason/Kimble County line. Although no potentially suitable habitat areas were
25

<<<PAGE 520>>>

observed within the Longhorn ROW, several areas were located adjacent to the previously
cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5 times during
April and May on days with favorable weather conditions for bird activity, per U.S. Fish and
Wildlife Service guidelines (USFWS, 1994a). Surveys were conducted on 8, 9, 12, 27, 28 April,
and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres were spent at each site, based
on habitat size. No golden-cheeked warblers were found to be utilizing any of the potentially
suitable habitat areas on or immediately adjacent to the ROW. However, three years of survey
are necessary to confirm presence/absence under Service guidelines (USFWS 1994a).
Black-capped Vireo (Vireo atricapillus) -The black-capped vireo is a 4.5 inch long, insect-
eating songbird. Mature males are olive green above and white below with faint greenish-yellow
flanks. The crown and upper half of the head is black with a partial white eye-ring. The iris is
brownish-red and the bill black. The plumage of the female is duller than the male. Females
have a dark slate gray head. In Texas, vireo habitat is found on rocky limestone soils of the
Edwards Plateau, Cross Timbers and Prairies, eastern Trans-Pecos, and, to a limited extent, on
igneous soils in the Chisos Mountains. Black-capped vireos require shrub vegetation reaching to
ground level for nesting cover. They typically nest in shrublands.
An assessment of potentially suitable habitat and surveys for the black-capped vireo was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from Austin,
Texas to Crane County. Potentially suitable habitat areas were observed within the Longhorn
ROW as well as several areas located immediately adjacent to the previously cleared permanent
ROW. All areas were surveyed by Horizon a minimum of 5 times during April and May on days
with favorable weather conditions for bird activity, per Service guidelines (USFWS, 1994a).
Surveys were conducted on April 8, 9, 12, 27, 28, and May 3, 11, and 19. An equivalent of 4
person-hours per 100 acres were spent at each site, based on size. No black-capped vireos were
found to be utilizing any of the potentially suitable habitat areas on or immediately adjacent to
the ROW. However, three years of survey are necessary to confirm presence/absence under
Service guidelines (USFWS 1994a).
Bald Eagle (Haliaeetus leucocephalus) - The bald eagle is a migrant and winter resident in
Texas. The bald eagle was recently down-listed from endangered to threatened due to successful
conservation efforts and is now proposed for de-listing. Migrating and wintering bald eagles
typically arrive in Texas in November and depart around February. They are found primarily in
association with reservoirs, rivers or other large bodies of water where they feed on fish, carrion,
and waterfowl. Nesting bald eagles in Texas are found in the eastern portion of the state and
along the coastal plain as far south as Calhoun and Refugio counties. No bald eagle nests have
been identified near the pipeline ROW, however, bald eagles may occur along major waterways
(Brazos and Colorado rivers, or major tributaries with impoundments) downstream of the
pipeline corridor. The Federal Register, (Volume 64 No. 128, Tuesday, July 6, 1999; Page
36454) contains a proposed rule to remove the bald eagle from the List of Threatened and
Endangered Wildlife in the Lower 48 States of the United States.
Interior Least Tern (Sterna antillarum athalassos) - Premier nesting sites for the interior least
tern are salt flats, broad sandbars, and barren shores along wide, shallow rivers. Important
breeding habitat characteristics include: (1) presence of bare or nearly bare ground and alluvial
islands or sandbars for nesting; (2) availability of food (primarily small fish); and (3) favorable
26

<<<PAGE 521>>>

water levels during the nesting season (so nests remain above water). They usually nest on sites
devoid of vegetation, but have been found in areas with an average of 11 to 30% vegetative
cover, composed of grasses, shrubs, and trees and ranging from 1 to 3 feet in height. Vegetation,
if present, is usually located well away from the colony, with the exception of bugseed, eastern
cottonwood, and sandbar willow. As natural nesting sites have become sparse, birds have used
sand and gravel pits, ash disposal areas of power plants, reservoir shorelines, gravel levee roads,
and other manmade sites. The typical nesting period for the least tern in Texas is mid-April to
mid-August.
While the interior least tern has not been documented along the pipeline corridor, potential
habitat for the tern is present downstream of the pipeline along several major waterways
including the Brazos, Colorado, Llano, and James Rivers, and Squaw, Beaver, and Sandy
Creeks. The seasonal occurrence (Spring and Summer) and potential nesting of least terns is
possible in these areas.
Barton Springs Salamander (Eurycea sosorum)- The Barton Spring salamander was listed as
endangered in 1997, without critical habitat. The Barton Springs salamander belongs to a group
of related salamanders that are endemic to the Edwards Plateau region of central Texas. All
members of this group are obligately aquatic because the adults retain the larval, gill-breathing
morphology throughout their lives. The Barton Springs salamander, formally described in 1993,
was first collected from Barton Springs in 1946 and has been found only at the four
hydrologically connected outlets of Barton Springs in Zilker Park within the City of Austin
(Brune, 1981; Chippindale et. al., 1993). This salamander is a small species, adults reaching 2.5
inches (about 68 mm) in total length with reduced eyes and elongate, spindly limbs indicative of
a semi-subterranean lifestyle. Barton Springs salamanders are found in the flowing, thermally
constant water issuing from the spring outlets in association with aquatic macrophytes, leaves
and organic debris, and gravel and rock substrates having little silt and sediment deposition.
Water from the contributing and recharge zones of the Barton Springs segment of the Edwards
Aquifer influences the conditions at Barton Springs. The main threat to the species has been
identified as degradation of water quality from future growth and development on the Barton
Springs segment of the Edwards Aquifer (Federal Register 62:23385).
Houston Toad (Bufo houstonensis) - The Houston toad was listed as endangered in 1970
(Federal Register, October 13, 1970) and Critical Habitat was designated in Bastrop and
Burleson counties in 1978 (Federal Register, January 31, 1978). Houston toads are generally
brown and speckled, although individual toad coloration can vary considerably. Some may
appear light brown, others almost black and they may also have a slightly reddish, yellowish, or
greyish hue. Two dark bands extend down from each eye to the mouth. Their legs are also
banded with darker pigment. A variable white stripe streaks along the sides of the toad's body.
Their undersides are usually pale with small, dark spots. Males have a dark throat which appears
bluish when distended. Adult Houston toads are 2 to 3.5 inches long and like all toads, are
covered with raised skin patches that contain chemicals that make the toad distasteful and
sometimes poisonous to predators.
The toad was eliminated from three counties (Harris, Fort Bend, Liberty) prior to the 1970s due
to habitat loss resulting from urban expansion. Although Houston toad populations have been
found in nine other counties (Austin, Bastrop, Burleson, Colorado, Lavaca, Lee, Leon, Milam,
27

<<<PAGE 522>>>

Robertson), the Service is concerned about the long-term viability of these populations. The
small population in Lavaca County has not been seen since its discovery in 199l; the population
at the critical habitat site (Woodrow Lake) in Burleson County has not been seen since 1983; and
the population in Leon County lies within an expanding residential area. The largest known
population of Houston toads occurs within the pine/oak woodland region of Bastrop County.
This area also contains federally designated critical habitat.
All known Houston toad populations occur along bands of geologic formations that support deep
sands. Six populations occur on a band running through Bastrop County northeast to Freestone
County. Three other populations occur on another band through Lavaca, Austin, and Colorado
counties (USFWS, 1994b). Houston toad habitat consists of rolling uplands characterized by
pine and/or oak woodlands (loblolly pine, post oak, blackjack or sandjack oak) underlain by
pockets of deep, sandy soils. Because their skin is semi-permeable to water, Houston toads
become dormant to escape harsh weather conditions, such as winter cold (hibernation) and
drought (estivation). They seek protection during this time by burrowing into sand or hiding
under rocks, leaf litter, logs or in abandoned animal burrows (TPWD, 1993). Although Houston
toads are typically associated with woodland habitat, they also breed in and migrate across
sparsely wooded and cleared areas near woodlands. They may also breed in and traverse areas
that do not support deep sandy soils, including clay and gravel substrates, provided these areas
are near woodlands underlain by pockets of deep sandy soils.
Houston toads breed from January to June, with a peak in February and March. During the
breeding season, toads appear to move randomly from one breeding site to another, achieving
genetic transfer between populations that may appear isolated, thus creating a metapopulation, an
aggregation of smaller populations linked genetically and demographically and functioning
almost as a single population. Presently, the most reliable breeding sites are stock ponds and
similar impoundments, though in wet years breeding may occur wherever sufficient standing
water is present. For successful breeding, water must persist for at least 30-60 days to allow egg
hatching, tadpole maturation, and emergence of toadlets. Mortality in young is high, due to
predation and drying of breeding sites, with significantly less than one percent of eggs laid
believed to survive to adulthood (USFWS, 1984a, 1994b, 1995).
The Houston toad is vulnerable to extinction primarily due to habitat loss, degradation, and
fragmentation. Over the last 50 years, the historic range of Houston toads has contracted and
several populations have been lost. Threats include expanding urbanization and conversion of
woodlands to agricultural production areas, such as coastal bermuda pastures, use of fertilizers
and pesticides that impact the toad directly or its food supply, and loss of suitable breeding
habitat because of alterations in watershed drainages and wetland alterations or destruction (such
as degraded water quality, draining/filling of wetlands, stocking with predatory fish, etc.).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Houston toad, the Service
believes this phase of the project will provide a net conservation benefit for this species.
According to the Houston Toad Recovery Plan (USFWS 1984a), Houston toad breeding sights
have been recorded in Buescher State Park south of Longhorn Pipeline. Houston toads have also
been heard chorusing on the adjacent property owned by the University of Texas to the north of
Buescher State Park and Longhorn Pipeline (USFWS, unpublished data). Dr. James R. Dixon of
28

<<<PAGE 523>>>

Texas A&M University conducted a survey along the Longhorn Pipeline ROW and adjacent
Phillips EZ Pipeline ROW in 1991 with negative results, although areas of potential habitat were
noted (Horizon 1991).
Horizon Environmental Services, Inc. conducted a reevaluation of suitable habitat along the
Longhorn Pipeline ROW within Bastrop County. The field reconnaissance was conducted on 2
June 1999 from the Colorado River, southeast of Bastrop, to FM 2104. Portions of the area
along the pipeline had recently been cleared and planted in improved grasses. Based on field
observations and discussions with the Service, two areas of suitable habitat were identified along
and adjacent to the pipeline ROW. One area includes Buescher State Park from approximately
0.5 mile east of the eastern boundary of the park westward to near Highway 71. The second area
begins about 500 feet to the west of FM 2104 and extends westward approximately 0.75 mile.
The drainages in both of these areas flow south toward the Colorado River.
EFFECTS OF THE ACTIONS
Direct and Indirect Effects
Texas Prairie Dawn - Potential impacts to the Texas prairie dawn may result from a number of
activities. ROW maintenance will occur with the periodic (typically twice per year) use of
tractor drawn mowers. Tractors will be rubber-tired, and crushing of plants could occur from
time to time, particularly during blooming periods. Mowing height will typically be 3 to 4
inches. Since only the blooming shoot is usually that high, impacts from mowing are deemed to
be minimal, except during blooming. Longhorn has chosen to quantify impacts as the total
ROW (50 feet) through the entire area of identified potential habitat. This area constitutes
approximately 61.3 acres. As an avoidance and minimization measure, mowing will be
scheduled to avoid the February through April blooming season.
Three construction sites have been identified for completion in the near-term, two pipeline dent
investigations, and one anomaly investigation (Appendix Two). Impact for these three
construction areas will be contained within the existing 50 foot ROW for relatively short
distances along the pipeline. Within these areas, excavation, temporary spoil storage, equipment
movement, and grading will likely result in elimination of any prairie dawn plants that may
occur within the ROW in the construction areas. The area of these impacts is already included in
the total ROW impact mentioned above (61.3 acres).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Texas prairie dawn, the
Service believes this phase of the project will provide a net conservation benefit for this species.
Navasota Ladies'-tresses - As in the case of the prairie dawn, periodic (twice per year) mowing
with rubber-tired tractor mowers may result in sporadic crushing of plants under tractor tires or
mower wheels, or cutting of bloom stalks. Impacts from periodic mowing, in the absence of
detailed plant inventory information for the ROW, are quantified as of total impact for the ROW
through the identified potential habitat areas constitutes 5.2 acres. As an avoidance and
minimization measure, mowing will be scheduled to avoid the October and November blooming
29

<<<PAGE 524>>>

season. A blooming season survey of the ROW and adjacent areas will be conducted to identify
any plant locations for specific avoidance, if present.
No areas of construction are identified in the two potential habitat areas. However, construction
will occur just east of the most westerly potential habitat area. The ROW is to be used for access
to the construction zone. It is presumed that heavy equipment movement along this portion of
the ROW will result in destruction of any plants growing at that locality. Access will be kept
within the existing 50 foot ROW; therefore, potential impacts have already been calculated in the
ROW maintenance value above (5.2 acres).
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Navasota Ladies-tresses,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Tobusch Fishhook Cactus - Potential habitat for the fishhook cactus is very generally estimated
from general soils and plant distribution information to include the entire reach of the pipeline's
traverse of Kimble County. Without specific survey information for the cactus, it is assumed
that the entire ROW across Kimble County is potential cactus habitat. As with the Texas prairie
dawn and Navasota ladies'-tresses, the Tobusch fishhook cactus is low growing and not likely to
be directly affected by mowing, except for possible crushing by tractor tires. However, due to
the significant extent of large rocks within the ROW, mowing is not always feasible in this
region. A preferred method in rocky terrain is to back drag a bulldozer blade across the ground
which knocks down undesirable woody vegetation. This activity can disrupt the ground surface
and possibly injure or destroy cactus plants. Therefore, direct impacts to fishhook cactus habitat
may occur. The total area occupied by the ROW across Kimble County is 212.7 acres.
Four test header installation locations are planned within the potential fishhook cactus habitat.
Each site will disturb an additional 50-foot width beyond the ROW for the construction of the
headers. The additional space is required to facilitate temporary spoils storage, equipment
access, pipe construction, and testing equipment. The additional area of impact per site is
between 0.1 and 0.2 acre. The total additional impact to cactus habitat is 0.5 acre. The total
impact acreage for Tobusch fishhook cactus is 213.2 acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Tobusch fishhook cactus,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Golden-cheeked Warbler - Golden-cheeked warbler habitat does not exist in the established
ROW, but is presently adjacent to the ROW in a number of locations from Hays County
westward to Mason County. ROW maintenance will not directly affect warbler habitat, except
for hand pruning of canopies which overhang the ROW. Indirect effects may result from
mowing noise or activity if birds are present in the vicinity during maintenance activities. As a
minimization procedure, Longhorn will schedule maintenance activities to occur during the non-
30

<<<PAGE 525>>>

nesting season (September 1 to March 1) within or near warbler habitat areas to avoid indirect
impacts. The area of potential effect is determined to be 103.4 acres.
Six areas of pipeline maintenance, construction, or investigation are anticipated to occur along
the pipeline within potential warbler habitat (Appendix Two). Each of those areas are estimated
to require additional construction space in excess of the existing ROW by variable widths. The
total additional impact to warbler habitat resulting from construction clearing is 13.4 acres. The
additional areas of temporary work space are needed in these areas to facilitate temporary spoil
storage, machinery access, pipe stacking, and miscellaneous construction related activities. As
avoidance and minimization of project impacts, Longhorn will schedule clearing, to occur during
the non-nesting period (September 1 to March 1). As with the immediately impending
construction schedule, clearing will commence prior to March 1 and construction activities will
be continuous until completion. Total estimated impacts to potential warbler habitat are 116.8
acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the golden-cheeked warbler,
the Service believes this phase of the project will provide a net conservation benefit for this
species.
Black-capped Vireo - Seven areas of potential black-capped vireo habitat exist along the ROW
between Blanco and Kimble counties. Black-capped vireo habitat, being an early successional
stage of brushy regrowth, does exist within the existing ROW in places where previous
maintenance activities have not occurred in several years. In this case, ROW maintenance will
directly impact potential habitat within the existing ROW. The area of direct impact for the full
50 foot width of the ROW through the various habitat areas constitutes approximately 41.6 acres.
Indirect impacts from ROW maintenance are not likely since maintenance activities will be
conducted during the non-nesting season (September 1 to March 15) for vireos.
Four maintenance construction locations have been proposed within the areas identified as
potential vireo habitat (Table 2). Only one of those construction sites will require clearing
beyond the 50 foot ROW width. An additional 50 feet of temporary work space will be needed
to facilitate temporary spoils storage, equipment access, pipe layout and construction room. The
additional acreage of disturbance for this construction site is 0.1 acre. The total area of impact to
potential black-capped vireo habitat is 41.7 acres.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the black-capped vireo, the
Service believes this phase of the project will provide a net conservation benefit for this species.
Houston Toad - ROW maintenance will include periodic mowing with rubber-tired tractors. To
avoid mortality of toads that may occur within the ROW during mowing, maintenance activities
will be timed to occur in the late summer through fall (July through December) when the toads
tend to be less active and are not breeding. In addition to these avoidance procedures and the
low likelihood of encounters, Longhorn will assume that all areas of potential habitat traversed
31

<<<PAGE 526>>>

by the pipeline ROW are suitable habitat. This area (ROW width of 50 feet times length) is
about 20.6 acres. To minimize edge effects, the ROW will be maintained in native bunchgrasses
to facilitate dispersal and provide cover from predators. No construction impacts to Houston
toads are contemplated in this consultation. Pipe replacements within the toad habitat area will
be addressed in the second phase of consultation.
32

<<<PAGE 527>>>

Because of the toad's vulnerability to development activities, the Service believes that the
combined impact of the existing and anticipated habitat fragmentation and destruction in Bastrop
County could jeopardize its continued existence and adversely modify its critical habitat at some
point in the future, unless immediate efforts are implemented to protect enough remaining
habitat to support viable, self-sustaining populations. Several large, high quality, interconnected
habitat blocks are needed to promote population viability (USFWS 1994b, Houston Toad
Recovery Team 1999). The Houston Toad Recovery Team believes that 20,000-30,000 acres of
suitable (undeveloped) habitat in blocks of 5,000 acres or greater are needed to support a viable,
self-sustaining population of toads with low risk of extinction, with an absolute minimum of
15,000 acres provided this 15,000 acres is in large, interconnected blocks of the best habitat
remaining.
The Service intends to ensure the toad's long-term survival and recovery by ensuring that any
activities authorized under the Endangered Species Act provide long-term protection for the
Houston toad. Thus, any actions authorized by the Service must permit the persistence of at least
20,000-30,000 acres in large, unfragmented habitat blocks in Bastrop County. Toads must be
able to disperse between the habitat blocks through direct connections and/or through migration
corridors that allow dispersal to occur (i.e., multiple smaller upland habitat patches and riparian
corridors).
Currently, the habitat blocks north of Highway 21 and in and around Bastrop State Park are most
likely to continue to support toad populations, provided no additional habitat destruction occurs
that significantly disrupts normal feeding, breeding, and sheltering behavior. Since much of the
area south of Highway 71 has already been extensively fragmented by development, the Service
believes that this area is less likely to continue to support toads over the long-term. The area in
and around the University of Texas Science Park and Buescher State Park has potential to
support a population, provided enough habitat remains contiguous and undisturbed. Until
sufficient high quality habitat has been secured and managed to provide population viability in
perpetuity, the Service believes that any further development that would impact the integrity of
the remaining habitat blocks or their connections would jeopardize the toad and adversely
modify its critical habitat.
Without permanent habitat protection to ensure the persistence of the largest known population
of toads in Bastrop County, the Houston toad faces an imminent risk of extinction. Thus, it is
imperative that the impacts from any activity authorized by the Service provide habitat
protection and maintain migration corridors. By ensuring that all clearing and development
activities implement sufficient measures to minimize impacts, the Service believes many projects
in toad habitat can move forward without reducing the likelihood of survival and recovery of the
species. The Service will continue to assess the impacts of existing and proposed projects and
evaluate whether or not this goal is being achieved.
Since Phase One of the Longhorn Pipeline project involves the continuation of maintenance
activities rather than new clearing or development, and minimization of these continuing
maintenance activities will include long-term habitat protection for the Houston toad, the Service
believes this phase of the project will provide a net conservation benefit for this species.
33

<<<PAGE 528>>>

Other Species - Listed species that may occur away from or downstream of the pipeline corridor
(bald eagle, interior least tern, Barton Springs salamander) are not likely to be adversely affected
by the proposed maintenance and minor construction activities. Any discharges of hydrotest
waters are not expected to contain levels of hydrocarbons or other toxic materials sufficient to
result in adverse impacts.
Effects of Hydrostatic Testing - Potential Failure of Pipe
Hydrostatic testing of the existing Longhorn Pipeline between Houston and Crane is expected to
result in a number of failures. Some of those failures, and actions taken to locate failure
locations, could have effects upon both species and habitat. However, the calculation of the
effects of such failures is difficult to estimate since the location of any such failure cannot be
predicted and since the volume of test water that may be discharged is difficult to predict.
Calculations by a pipeline integrity consulting firm estimate that approximately 18 to 20 failures
will occur at the high test pressures planned. Since the most likely failure location is at pipeline
flaws, the location of the expected failure cannot be predicted with any accuracy; at most, a
minimal number of recently replaced sections of pipe may be eliminated from consideration.
Therefore, the expected failures will approximate a random distribution over the Houston to
Crane segment. A finite number of failures could be assigned to the habitat areas based upon the
proportional share of pipeline mileage in habitat areas; however, that methodology would
probably result in either overestimation or underestimation of the number of failures in habitat
areas.
In addition, the potential volume of test water discharged in the event of failure is difficult to
estimate. First, if a failure results in rapid depressurization of the test segment, the volume of
test water discharged will be the sum of (a) water expelled as the pipe returns to atmospheric
pressure, which depends upon test pressure and test segment length, and (b) drainage from any
adjacent segments at elevations higher than the failure location. Second, if a failure results in a
slow depressurization of the test segment, it may be readily identifiable and quickly contained.
If a slow leak is difficult to locate, one or more investigative excavations could be required to
either search for the failure or plug a portion of the segment so that lengths of pipe may be
eliminated from the search. Therefore, given that failure location and size cannot be predicted,
potential effects on species and/or habitat cannot be reasonably estimated in advance. Another
factor that makes such estimates difficult is the existence of residual amounts of diesel fuel that
remain in the pipeline from cleaning during 1998. As the hydrostatic testing proceeds from east
to west, the test water may be expected to reflect relatively higher levels of hydrocarbon content.
Those concentrations cannot be predicted but are not expected to contain levels of hydrocarbons
or other toxic materials sufficient to result in adverse impacts. Spill response equipment such as
booms, absorbent pads, and other containment and cleanup equipment will be maintained in the
vicinity of the test sites during the procedure.
In summary, the locations of hydrostatic test failures cannot be predicted, the volume of test
water discharged can not be calculated, and the number of investigative excavations cannot be
predicted. In the event of a pipeline failure in or near habitat for listed species, incidental take
may occur. The level of potential take is impossible to predict. Basically, take from failure of
the pipeline during this testing would require reinitiation of this consultation.
34

<<<PAGE 529>>>

Cumulative Effects
Cumulative effects of future State, local or private actions that are reasonably certain to occur in
the action area are considered in this biological opinion. Future Federal actions that are
unrelated to the proposed action are not considered in this section because they require separate
consultation pursuant to Section 7 of the Act. Because of the linear nature of the pipeline and the
long history of clearing (about 50 years) the Service anticipates no cumulative effects from the
activities proposed. The majority of the counties involved in the project are predominantly rural,
and imminent future actions identified that may affect each of the listed species are either not
considered to be of sufficient magnitude to result in jeopardy to the species or will include
minimization necessary to avoid jeopardy.
Conclusion
The Service in developing its biological opinion has thoroughly reviewed the proposed action
submitted by EPA, OPS, and Longhorn Pipeline Partners. This Biological Opinion is predicated
on the compliance and the full and complete adherence by EPA, OPS and the Longhorn Pipeline
Partners to the Description of the Proposed Action provided earlier in this document. In
consideration of the above and after reviewing the current status of the potentially affected
species, the environmental baseline for the action area, the effects of the proposed action
including direct, and indirect and cumulative effects, it is the Service's biological opinion that
the action as proposed by EPA, OPS, and the Longhorn Pipeline Partners for Longhorn Pipeline
Project Maintenance Activities and Minor Construction from Houston to Crane, Texas, is not
likely to jeopardize the continued existence of any Federally listed species. In addition the
proposed action is not likely to destroy or adversely modify the designated critical habitat of the
Houston toad. In addition, the Service concurs with the not likely to adversely affect
determination, made by EPA and OPS for areas that are not habitat for threatened or endangered
species.
INCIDENTAL TAKE STATEMENT
Section 9 of the ESA and Federal regulations pursuant to section 4(d) of the ESA prohibit the
take of endangered and threatened species, respectively, without special exemption. Take is
defined as to harass, harm, pursue, hunt, shoot, wound, kill, trap, capture or collect, or to attempt
to engage in any such conduct. Harm is further defined by the Service to include significant
habitat modification or degradation that results in death or injury to listed species by
significantly impairing essential behavioral patterns, including breeding, feeding, or sheltering.
Harass is defined by the Service as intentional or negligent actions that create the likelihood of
injury to listed species to such an extent as to significantly disrupt normal behavior patterns
which include, but are not limited to, breeding, feeding or sheltering. Incidental take is defined
as take that is incidental to, and not the purpose of, the carrying out of an otherwise lawful
activity. Under the terms of section 7(b)(4) and section 7(o)(2), taking that is incidental to and
not intended as part of the agency action is not considered to be prohibited taking under the Act
provided that such taking is in compliance with the terms and conditions of this Incidental Take
Statement.
The term take in the Endangered Species Act is not defined for plants and therefore plants are
not included in the incidental take statement of biological opinions. However, Federal agencies
35

<<<PAGE 530>>>

are required under section 7 (a)(1) of the Act to consult with the Service on actions that may
affect listed plants, and to insure that any agency action is not likely to jeopardize the continued
existence of the species or result in the destruction or adverse modification of critical habitat.
Further, section 7(a)(2) of the Act applies equally to plants and animals.
Amount or Extent of Take
The Service anticipates that the level of incidental take from the proposed activities will be low.
The seasonal restrictions placed on these activities, and alternative techniques planned for
sensitive habitat areas (land conservation funding), and other conservation actions planned
should avoid and minimize the potential for incidental take to the maximum extent practicable.
The amount or extent of incidental take resulting from the proposed action on listed species is
difficult to assess since comprehensive survey information is not available for all species that
could be affected. The approach taken for most of the potentially affected species is to assume
that they are present in the identified potential habitat areas and that take will occur. The
proposed action uses the potential habitat to define the possible extent of any take that could
occur. Based on the proposed action, the Service will assume incidental take for the entire width
of the pipeline ROW (and edge effects from the ROW) as it traverses broad areas of potential
habitat for listed species. Take is calculated based on the extent of suitable habitat within the
established ROW (50-foot width x length) and within temporary work spaces that exceed the
ROW (variable by location). The following summarizes by species the amount of potentially
suitable habitat that will be impacted by the proposed action (Table Three).
Table Three. Potential Suitable Habitat
Species
Area Impacted
Texas prairie dawn
61.3 acres
Navasota ladies'- tresses
5.2 acres
Houston toad
20.6 acres
Golden-cheeked warbler
116.8 acres
Black-capped vireo
41.7 acres
Tobusch fishhook cactus
213.2 acres
Effect of Take
In the accompanying biological opinion, the Service determined that the level of anticipated take
identified is not likely to result in jeopardy to the species or destruction or adverse modification
of critical habitat. Implementation of this project should result in net benefit to the species listed
above in Table Two, to the extent that conservation benefits planned exceed expected impacts to
the species.
Reasonable and Prudent Measures
The Service believes the following reasonable and prudent measures are necessary and
appropriate to minimize take associated with the proposed Phase One - Longhorn Pipeline
Project Maintenance Activities and Minor Construction Houston to Crane, Texas.
36

<<<PAGE 531>>>

The measures described below are non-discretionary, and must be undertaken by EPA and/or
OPS so that they become binding conditions on the Longhorn Pipeline Partners, as appropriate,
for the exemption in section 7(o)(2) to apply. EPA and OPS have a continuing duty to regulate
the activities addressed by this incidental take statement. If EPA or OPS, (1) fails to assume and
implement the terms and conditions or (2) fails to require the Longhorn Pipeline Partners to
adhere to the terms and conditions of the incidental take statement through enforceable terms and
conditions, the protective coverage of section 7(0)(2) may lapse.
In order to monitor the impact of incidental take, EPA, OPS, and/or Longhorn Pipeline Partners
must report the progress of the action and its impact on the species to the Service as specified in
the incidental take statement (below) [50 CFR §402.14(I)(3)].
Reasonable and Prudent Measure 1: The proposed actions, as described in the above
"PROJECT DESCRIPTION (Actions addressed under this Biological Opinion)" and the
accompanying Biological Assessment must be followed. In areas where the Biological
Assessment and the Biological Opinion are not in agreement, the Biological Opinion will be
followed. The Service will be available to clarify any questions that may arise during
implementation.
Reasonable and Prudent Measure 2: EPA and/or OPS must ensure that the activities are
carried out by the Longhorn Pipeline Partners as they are proposed. Monitoring of these
activities must be accomplished to ensure compliance. The level of monitoring must include
onsite review of activities with a relatively intense focus on the first year when construction will
occur. EPA and/or OPS must submit a monitoring plan detailing the level of monitoring that
will occur. Service concurrence with the level and type of monitoring proposed is a requirement.
Terms and Conditions
In order to be exempt from the prohibitions of section 9 of the Act, EPA and OPS must comply
with the following terms and conditions, which implement the reasonable and prudent measures
conditions are non-discretionary.
described above and outline required reporting/monitoring requirements. These terms and
Terms and Conditions to Implement Reasonable and Prudent Measure 1
This term and condition is effective immediately.
Terms and Conditions to Implement Reasonable and Prudent Measure 2
This term and condition is effective immediately. Given that the proposed work is scheduled to
begin with the issuance of this opinion, EPA and/or OPS must submit a monitoring plan
detailing the level of monitoring within two weeks of the receipt of the Biological Opinion. On
site review of the projects should begin before March 1, 2000.
Conservation Recommendations
Section 7(a)(1) of the Act directs Federal agencies to utilize their authorities to further the
purposes of the Act by carrying out conservation programs for the benefit of endangered and
threatened species. Conservation recommendations are discretionary agency activities to
37

<<<PAGE 532>>>

minimize or avoid adverse effects of a proposed action on listed species or critical habitat, to
help implement recovery plans, or to develop information.
It is recommended that in areas where surveys are completed ahead of destructive
project actions, any plants in the action area be protected and avoided wherever
possible. Where Tobusch fishook cactus plants are found that cannot be avoided
and will be destroyed by the project activities, the Service recommends these
plants be removed and transferred to the conservation collection of the Desert
Botanical Garden in Phoenix, Arizona, where they can be cultivated for seed
production and cryopreservation for use in future restoration work for the species.
Contact Desert Botanical Garden prior to removals to arrange transfer and obtain
any special instruction. In general, plants should be removed by digging at least a
one foot diameter area around the plant, carefully rinsing to bare root, thoroughly
drying the entire subsoil area and any wounds before transport (by placing on
newspapers in a cool shaded location) and then (when dry) carefully packing in
newspaper in a box, and then packing in a second box surrounded by protective
packing materials before express shipping.
•
It is recommended that maintenance practices be implemented that will help
minimize impacts to the vegetation community, fragmentation of Houston toad
habitat, and edge effects.
To facilitate dispersal for Houston toads that cross the ROW, Longhorn Pipeline
has agreed to maintain the ROW in native bunchgrasses rather than sod-forming
grasses, which inhibit movement. The height of native bunchgrass communities
shall be maintained several inches (i.e., ≥ 4 inches) above ground level to provide
adequate cover for toads.
•
Avoid using herbicides and pesticides in Houston toad areas. If herbicide use
cannot be avoided, direct application techniques shall be used to minimize
amount of application and areas of the habitat impacted. Avoiding the use of
herbicides and pesticides is particularly critical near any wetland areas and during
the breeding season (January through June). Avoiding the use of chemicals in
habitat minimizes the risk of harm through toxic effects to the toads and tadpoles
themselves or their food base.
•
To protect the Houston toad from predation by red imported fire ants (Solenopsis
invicta), periodically inspect the ROW for fire ant activity. Inspections should
occur when fire ants are most active. If fire ants are found, individually treat fire
ant mounds using commercial fire ant bait in accordance with label instructions.
Bait should be placed only near fire ant mounds and not near the mounds of
native ant species. To avoid affects on non-target species, apply bait when ants
are actively foraging and prevent accumulations of excess bait.
Reinitiation Notice
This concludes formal consultation for Phase One - Longhorn Pipeline Project Maintenance
Activities and Minor Construction Houston to Crane, Texas. As provided in 50 CFR $402.16,
38

<<<PAGE 533>>>

reinitiation of formal consultation is required where discretionary Federal agency involvement or
control over the action has been retained (or is authorized by law) and if: (1) the amount or
extent of incidental take is exceeded; (2) new information reveals effects of the agency action
that may affect listed species or critical habitat in a manner or to an extent not considered in this
opinion; (3) the agency action is subsequently modified in a manner that causes an effect to the
listed species or critical habitat not considered in this opinion; or (4) a new species is listed or
critical habitat designated that may be affected by the action. In instances where the amount or
extent of incidental take is exceeded, any operations causing such take must cease pending
reinitiation.
In closing we wish to thank EPA, OPS, and the Longhorn Pipeline Partners for the cooperation
and patience shown during this consultation. Thank you for your interest in protecting our
federal trust resources. If you have any questions, please contact Matthew Lechner (512) 490-
0057, extension 234.
Sincerely,
/s/ William M. Seawell (for)
David C. Frederick
Supervisor
39

<<<PAGE 534>>>

Appendix One
Confidential Settlement Agreement
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF TEXAS
AUSTIN DIVISION
Ethel Spiller, et al., Plaintiffs
versus
Robert M. Walker, et al. Defendants
CIVIL NO. A-98-CA-255-SS
Settlement Stipulation
40

<<<PAGE 535>>>

Appendix Three
Literature Cited
Arft, A. and T. Ranker. 1995. Demography of the rare orchid Spiranthes diluvialis: implications
for conservation. Program and Abstracts, 9*h annual meeting of the Society for Conservation
Biology, June 7-11, Fort Collins, Colorado. Abstract, notes from presentation attended. U.S.
Fish and Wildlife Service, Austin, Texas.
Brune, G. 1981. Springs of Texas: Volume 1. Branch-Smith Inc. Fort Worth, Texas.
Chippindale, P., D. Hillis, and A. Price. 1990. Central Texas Salamander Studies. Section 6
report submitted by Texas Parks and Wildlife Department to U.S. Fish and Wildlife Service.
Federal Aid Project No: E-1-2, Job No. 3.4. Austin, Texas.
Horizon Environmental Services, Inc. 1991. Threatened or Endangered Species Investigations -
EZ Pipeline Project. Horizon Environmental Service, Inc. Austin, Texas.
Poole, J.M,. and D.H. Riskind. 1987. Endangered, Threatened, or Protected Native Plants of
Texas. Austin, Texas: Texas Parks and Wildlife Department, State of Texas.
U.S. Fish and Wildlife Service (USFWS). 1984a. Houston toad recovery plan. U.S. Fish and
Wildlife Service. Albuquerque, New Mexico. 73pp.
U.S. Fish and Wildlife Service (USFWS). 1984b. Navasota ladies'-tresses recovery plan. U.S.
Fish and Wildlife Service. Albuquerque, New Mexico.
U.S. Fish and Wildlife Service (USFWS). 1994a. Minimum Procedures for Determining the
Presence/Absence of Golden-Checked Warblers and Black-Capped Vireos. March 7, 1994
Memorandum, Austin Field Office.
U.S. Fish and Wildlife Service (USFWS). 1994b. Population and habitat viability assessment:
Houston toad (Bufo houstonensis). Workshop conducted by IUCN/SSC Conservation Breeding
Specialist Group in partial fulfillment of USFWS contract #94-172. Apple Valley, Minnesota.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and endangered species of Texas
(revised). U.S. Fish and Wildlife Service. Austin, Texas.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and Endangered Species of Texas.
Austin, Texas: US Fish and Wildlife Service, Revised June, 1995.
U.S. Fish and Wildlife Service (USFWS). Houston Toad Recovery Team. 1999. March 31-April
1, 1999 Meeting Minutes. U.S. Fish and Wildlife Service, Austin, Texas.
Texas Parks and Wildlife. 1993. Endangered species information for Hilltop Lakes. Texas Parks
and Wildlife Resource Protection Division, Austin, Texas.
Wilson, H. 1993. Contractors partial draft of recovery plan revision for Navasota ladies'-tresses
(unfinished contract). U.S. Fish and Wildlife Service, Austin, Texas.
41

<<<PAGE 536>>>

Phase Il Biological Assessment
April 10, 2000
Addendum September 14, 2000
42

<<<PAGE 537>>>

Horizon Job No. 990144
PHASE TWO
BIOLOGICAL ASSESSMENT
OPERATION, LONG-TERM MAINTENANCE,
AND EMERGENCY RESPONSE,
LONGHORN PIPELINE PROJECT
HOUSTON TO EL PASO, TEXAS
PREPARED FOR:
LONGHORN PARTNERS PIPELINE
U.S. DEPARTMENT OF TRANSPORTATION
AND
U.S. ENVIRONMENTAL PROTECTION AGENCY
REGION 6
PREPARED BY:
HORIZON ENVIRONMENTAL SERVICES, INC.
AUSTIN - BEAUMONT - HOUSTON - SHREVEPORT
APRIL 10, 2000
Addendum September 14, 2000
99144ba2.v8

<<<PAGE 538>>>

TABLE OF CONTENTS
Section
Page
1.0
INTRODUCTION
1
2.0
CONSULTATION HISTORY
.4
3.0
DESCRIPTION OF THE PROPOSED ACTIONS.
7
3.1
Project Overview....
.7
3.2
Pipeline Operation
22
3.3
Long-Term Maintenance..
.22
3.4
Emergency Response.....
29
3.5
Edwards Aquifer Protections..
43
3.6
Pipeline Maintenance Construction.
46
3.6.1 Buescher State Park
46
3.6.2 Edwards Aquifer Protections.
47
3.7
Hydrostatic Pressure Testing And Proof Testing
51
3.8
Right-of-Way Maintenance
52
3.9
Corrosion Inhibitor ..
52
4.0
AVOIDANCE AND CONSERVATION MEASURES
55
Avoidance
55
4.2
Status of the Species/Environmental Baseline
57
4.3
Effects of the Actions....
68
4.4
Planned, But Unscheduled Construction ..
75
4.5
Future Additional, But Currently Unforseen Construction
76
4.6
Bays and Estuaries Issues.
76
4.7
Summary of Conservation Measures
77
5.0
REFERENCES
...81
99144ba2.v8

<<<PAGE 539>>>

LIST OF TABLES
Table
Page
1
Consultation History - Phases One And Two.
..4
2
Chronology of Longhorn Pipeline Actions..
10
3
List of Endangered Species Habitat Areas along the Longhorn Pipeline...
..12
4
Federally Listed Threatened or Endangered Species Which Occur
In Counties Traversed By The Longhorn Pipeline
Houston to El Paso........
.. 58 - 59
LIST OF FIGURES
Figure
Page
1
Location Map................
...8
2 - 10
Areas of Potential Threatened or Endangered Species Habitat Along
the Longhorn Pipeline - Houston to El Paso.
.. 13 - 21
APPENDIX
Phase Two Project Documentation Appendix
Accompanying Document
Longhorn Facility Response Plan
Accompanying Document
99144ba2.v8

<<<PAGE 540>>>

1.0 INTRODUCTION
This document is the Biological Assessment (BA) of the potential for effects, arising out of
the activities proposed by Longhorn Partners Pipeline, L.P. (Longhorn), on federally-listed
species in Texas. This BA presents data and information describing the proposed plans for
the second phase of consultation for the Longhorn Pipeline Project -- Operation,
Maintenance, and Response Activities, Houston to El Paso, Texas. The first phase of the
consultation (Phase One), which has already been completed, related to pipeline right-of-
way maintenance, clearing and marking, selected pipeline maintenance construction
activities (pipe replacements and lowering), and pipeline testing (investigation of possible
flaws and hydrostatic pressure testing). The Service found that Longhorn's Phase One
activities were not likely to jeopardize the continued existence of any federally listed
species, nor was it likely to destroy or adversely modify the designated critical habitat of the
Houston toad. The Phase One BA, dated February 14, 2000, and the Phase One Biological
Opinion (BO), dated February 17, 2000, are hereby incorporated into this Phase Two BA by
reference (see Phase Two Project Documentation Appendix at Tabs 1 and 2).
The draft Environmental Assessment (EA) of the proposed Longhorn Pipeline System and
these BAs are the product of a settlement reached in the matter of Spiller et al. v. Walker et
al. pending in the United States District Court in Austin, Texas (See Phase Two Project
Documentation Appendix at Tab 3; the Settlement Stipulation). As part of the Court
approved settlement, two agencies involved in the original litigation were required to
conduct an EA including, specifically, consideration of species listed under the Endangered
Species Act (ESA). The Court ordered the U.S. Environmental Protection Agency (EPA)
and the U.S. Department of Transportation (DOT), to be responsible for the EA. EPA and
the DOT Office of Pipeline Safety (OPS) act as Lead Agencies in the EA process. Radian
International LLC (Radian) is a contract preparer of the EA and works at the direction of the
Lead Agencies.
The Court order provides that issuance of any finding of no significant impact (FONSI) with
regard to the
proposed Longhorn Pipeline project "shall be conditioned upon
implementation" of measures to protect public safety and the environment (Settlement
Stipulation at 6). The order also prohibits OPS from authorizing Longhorn to commence
operations until Longhorn has implemented those mitigation measures upon which any
FONSI is conditioned (Settlement Stipulation at 7). The order contemplates that Longhorn
will apply for such ESA permits as may be required in connection with the implementation
of any mitigation measures upon which a FONSI may be conditioned. (Settlement
Stipulation at 7). The results of this consultation by the Lead Agencies with the Service are
expected to be incorporated in the Record of Decision issued by the Lead Agencies. The
terms and conditions, mitigatory measures and protections incorporated herein for the
benefit of species are expected to be adopted and incorporated by Longhorn in its
enforceable mitigation commitments or in its operating and maintenance manuals subject
to inspection by, and enforceable by, OPS pursuant to the Pipeline Safety Act (49 U.S.C.
60101 et seq.).
Although the Service and the Lead Agencies are in consultation with respect to the entire
proposed Longhorn pipeline project, this consultation is being approached in two distinct,
yet related phases.
Service regulations allow for a staged consultation (50 CFR
402.14(k)) where the Service reviews a project and provides biological opinions on each
99144ba2.v8
1

<<<PAGE 541>>>

incremental step, provided that no irreversible or irretrievable commitments of resources
are made.
This second phase of the consultation will be directly related to the actual operation of the
pipeline, specifically the operation and maintenance of the pipeline system and the potential
effects of a pipeline release and related emergency response. Like Phase One, Phase
Two activities also include implementation of some mitigation measures, specifically the
replacement of pipe in Buescher State Park (see Longhorn Mitigation Commitment 34
(LMC 34) of the Longhorn Mitigation Plan (LMP) dated September 1, 2000; see Phase Two
Project Documentation Appendix at Tab 4) and the replacement of some 19 miles of pipe
over the Edwards Aquifer recharge and contributing zones with thick-walled pipe. On its
own initiative, Longhorn will lower two other sections of pipe in Buescher Park where the
pipe crosses streams. Phase Two also includes (a) hydrostatic pressure testing of pipeline
segments not tested pursuant to Phase One, specifically, Houston toad habitat areas and
areas of potential effect to the Barton Springs Salamander, (b) treatment of the pipeline
internally with corrosion inhibitor, and (c) right-of-way clearing in areas of potential effect to
the Barton Springs Salamander.
Since none of the Phase Two work will be undertaken by Longhorn until this consultation is
complete, neither the federal agencies nor Longhorn will engage in any irreversible or
irretrievable commitment of resources during the course of the consultation.
The two phases have been logically separated. Phase One of the Service's review focused
on those actions that were designed to make the pipeline safer. That review did not pre-
judge whether or not the pipeline would be used. This second phase of the consultation
will focus on whether and how the pipeline will be used. New construction of pipe between
Crane and El Paso was reviewed by the Service in 1997 and resulted in a not likely to
adversely affect determination (See Tab 5 of the Phase Two Project Documentation
Appendix).
The Service can logically conclude that operation and maintenance of the Longhorn
Pipeline will not jeopardize the continued existence of any federally listed species, and that
it is not likely to destroy or adversely modify the designated critical habitat of the Houston
toad. This project, as designed, is not likely to adversely affect threatened or endangered
species or habitat.
There is little risk from operation of the pipeline. The risks that do exist
arise in the unlikely event of an accidental release of product from the pipeline.
response to this risk, and pursuant to the Settlement Stipulation, Longhorn will implement
numerous mitigation measures designed to avoid a release entirely or reduce the
magnitude and the impact of a release. Longhorn developed these mitigation measures in
response to risks identified by the Lead Agencies. Mitigation measures such as pipe
replacement and pipe lowering, in-line inspections, daily surveillance patrols over the
Edwards Aquifer recharge zone, enhanced damage prevention and public education
programs, and hydrostatic pressure testing greatly minimize the risk of an accidental
release from the pipeline in the first place. These efforts minimize the risk a release will
occur. In addition, Longhorn will install an enhanced leak detection system which will allow
pipeline operators to rapidly detect even a very small release over the Edwards Aquifer
recharge zone and portions of the contributing zone and respond quickly, thereby limiting
the amount of product released into the environment. Longhorn will also fund a refugium for
the Barton Springs Salamander.
99144ba2.v8
2

<<<PAGE 542>>>

Taken together, the Service can conclude that these measures are sufficient to ensure
operation of the pipeline will neither jeopardize the continued existence of any federally
listed species, nor adversely affect their habitat, and is not likely to adversely affect
threatened or endangered species or habitat along the pipeline route.
This BA is based upon: (1) the information that Longhorn (as designated non-federal
representative), provided as
part of the informal consultation including the Draft
Environmental Assessment and the Phase One BA), (2) information in the Service's office
(including information provided by the public and the plaintiffs in the lawsuit relating to the
Longhorn Pipeline), (3) field investigations, and (4) other sources of information.
99144ba2.v8
3

<<<PAGE 543>>>

2.0
CONSULTATION HISTORY
Informal and formal consultation between the Service, Longhorn, EPA, and OPS has been
Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
10 February, 1999
Meeting Between Service and Longhorn Representatives
25 February, 1999
Meeting Between Service and Longhorn Representatives
9 March, 1999
Meeting of Service and Radian (consultants writing EA for EPA and OPS)
22 March, 1999
Meeting Between Service and Longhorn Representatives
30 April, 1999
Meeting Between Service and Longhorn Representatives
11 May, 1999
Meeting Between Service and Longhorn Representatives
12 May, 1999
Meeting with the Plaintiffs to discuss the Settlement Agreement
1 June, 1999
Meeting with Barton Springs/Edwards Aquifer Conservation District
8 June, 1999
Meeting Between Service and Longhorn Representatives
11 June, 1999
Multi-Agency Field Tour of Longhorn Pipeline in and near Austin, Texas
29 June, 1999
Meeting Between Service and Longhorn Representatives
30 June, 1999
Telephone Conference Between Service and Department of Justice
19 July, 1999
Meeting Between Service and Longhorn Representatives
27 August, 1999
Meeting Between Service and Longhorn Representatives
10 September, 1999
Meeting Between Service and EPA
Meeting Between Service and Longhorn Representatives
13 September, 1999
Meeting Between Service, Austin and Regional Director
27 September, 1999
Meeting between Service Austin Office and Washington Office
Original Draft Biological Assessment Submitted to Service
30 September, 1999
Meeting Between Service and Longhorn Representatives
99144ba2.v8
4

<<<PAGE 544>>>

Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
4 November, 1999
Meeting Between Service and Longhorn Representatives
9 November, 1999
Meeting Between Service and Longhorn Representatives
16 November, 1999
EPA and OPS Longhorn Public Meeting, Austin
22 November, 1999
Meeting Between Service and Longhorn Representatives
7 December, 1999
Meeting Between Service and Longhorn Representatives
8 December, 1999
Meeting Between Service and EPA
15 December, 1999
Meeting Between Service and Longhorn Representatives
Service Issues Comments on Original Draft Biological Assessment
Service Issues Response to EPA Regarding EPA's initial Request for
Concurrence on a "Not Likely to Adversely Affect" Determination.
17 December, 1999
Meeting Between Service and Longhorn Representatives
6 January, 2000
Longhorn Requests Concurrence from Service for "Not Likely to Adversely Affect"
Meeting Between Service and Longhorn Representatives
for Maintenance and Construction Activities in Non-habitat Areas for Listed
Species.
10 January, 2000
EPA and OPS Longhorn Public Meeting, Austin
11 January, 2000
Meeting Between Service, EPA and OPS
17 January, 2000
Meeting Between Service and Longhorn Representatives
18 January, 2000
Meeting Between Service and Longhorn Representative
28 January, 2000
Initial Draft First Phase Biological Assessment received for review
7 February, 2000
Meeting Between Service and Longhorn Representatives
1 February, 2000
Telephone Conference Between Service and Congressman Doggett's Staff
3 February, 2000
of consultation
EPA and OPS designate Longhorn the "non-federal representative" for purposes
10 February, 2000
Received EPA Request for Formal Consultation
14 February, 2000
Received Second Draft of Phase One Biological Assessment For Review
17 February, 2000
Received Revised Final Phase One Biological Assessment
17 February, 2000
Received OPS Request for Formal Consultation
17 February, 2000
Service issued Phase One Biological Opinion
9 March, 2000
Il consultation with submission of initial draft of Phase Two Biological Assessment
Meeting between Service and Longhorn Representatives to initiate informal Phase
12 April 2000
Received Revised Draft Phase I! Biological Assessment
26 April 2000
Meeting Between Service and Longhorn Representatives
99144ba2.v8
5

<<<PAGE 545>>>

Table 1: CONSULTATION HISTORY - PHASES ONE AND TWO
DATE
HISTORY
6 June 2000
Meeting Between Service and Longhorn Representatives
23 June 2000
Meeting Between Service and Longhorn Representatives
30 June 2000
Meeting Between Service and Longhorn Representatives
21to 31 July 2000
Received supplemental information for the Phase II Biological Assessment
3 August 2000
Meeting Between Service and Longhorn Representatives
5 August 2000
Meeting Between Service and Longhorn Representatives
9 August 2000
Meeting Between Service and Longhorn Representatives
23 August 2000
Meeting Between Service and Longhorn Representatives
6 September 2000
Meeting Between Service, Lead Agency, and Longhorn Representatives
11 to 13 Sept. 2000
Received supplemental information for the Phase II Biological Assessment
99144ba2.v8

<<<PAGE 546>>>

3.0 DESCRIPTION OF THE PROPOSED ACTIONS
The following is an overview of the project as proposed by Longhorn and is provided to give
an overall context of the proposed project. The specific activities proposed for this Phase
Two BA are detailed in the following sections. This project overview differs slightly from the
project overview contained within the Phase One BA; specifically, this project overview
describes four connecting pipelines as opposed to the three previously described.
However, the differences implicate no change to the potential effects of the overall project
upon species, given that no potential habitat areas have been identified along the planned
route of the connecting pipelines.
3.1
Project Overview
Due to the expanding demand for refined products in El Paso and other markets in the
southwestern United States, the proposed Longhorn Pipeline will transport up to 225,000
barrels per day (bpd) of refined products to the El Paso Terminal and to the Equilon
Terminal in Odessa. From these terminals, products will be distributed by truck transport in
the El Paso and Odessa markets. Tanker trucks could transport refined products to Juarez
in Mexico. The Longhorn Pipeline will connect to the Kinder Morgan and Chevron pipelines
at El Paso, enabling shippers to transport products to Phoenix, Tucson, Albuquerque, and
other southwestern markets. Market conditions and shipper requirements will determine the
actual pattern of distribution of products to El Paso and to the Phoenix, Tucson,
Albuquerque, and other southwestern markets.
The Longhorn Pipeline System is designed for service in excess of fifty years from startup
and is made up of four main pipeline segments, several stations, and one terminal, as listed
below:
1.
New and refurbished 20-inch diameter pipeline from Galena Park Station to
Satsuma Station
2.
Refurbished 18-inch diameter pipeline from Satsuma Station to Crane Station
3
New 18-inch diameter pipeline from Crane Station to El Paso Terminal
4.
New lateral pipeline connections to Odessa and to other pipelines at El Paso
5.
New Pump Stations: GATX, Satsuma, Cedar Valley, Kimble County, Crane, and El
Paso
6.
El Paso Terminal
7.
Odessa Meter Station
Longhorn has constructed and will operate a 723-mile refined petroleum products pipeline
system from the GATX Terminal in Galena Park, Texas, to a refined petroleum products
terminal at El Paso, Texas (Figure 1). The pipeline also has a 28-mile intermediate
connection from a station in Crane County to a planned meter station in Odessa, Texas.
The pipeline consists of a combination of 20-inch and 18-inch diameter pipe from Galena
Park Station to El Paso Terminal and an 8-inch diameter pipeline from a station in Crane
County to a meter station in Odessa, Texas. The pipeline's initial capacity of 72,000 bpd
will be supplied by a new origin pump station at Galena Park and five new booster pump
stations, Satsuma, Cedar Valley, Kimble County, Crane, and El Paso.
99144ba2.v8
7

<<<PAGE 547>>>

98S00 M
rene ta
01
erie
493
0-r
01307o0/g pero bac
ле vol ago покоо.
07501
кото
AMARILLO
eno 2820ag0 nsm
30270
Oklahoma
Mexico es i-lo-ing
New
ron.
Louisiana
COULDNE
T WORTH
DALLA
ODESSA
TO COLOTINE
TACO
Mexico
cApu
KIMBLE COUNTY
ON
SaN/
ANTONIC
REDO
CHRISTI
Mexico
Gulf of
EXPLANATION
LONGHORN REFINED PRODUCTS PIPELINE
LONGHORN PIPELINE PUMP STATION:
RAD 39067
PUMP STATIONS
N
LONGHORN PIPELINE
1.05-
STATE OF TEXAS
NOT. TO SCALE
MAP SQURCES:
(htto:// www.tnns.state.tx.us/dota__oz.ntml), 1998
TEXAS NATURAL RESOURCE INFORMATION SYSTEM
LONGHORN PIPELINE

<<<PAGE 548>>>

An 8-inch diameter, 2,500-toot lateral that originates at the terminus of the existing Odessa
lateral will connect to a terminal facility in Odessa, Texas, owned by Equilon. Three 8.3-mile
lateral pipelines, which originate at the El Paso Terminal, will connect with Kinder Morgan
(formerly the Santa Fe Pacific pipeline) and Chevron pipelines in the El Paso area. The
connection to Kinder Morgan will consist of one 8-inch diameter pipeline and one 12-inch
diameter pipeline. The Chevron connection will consist of an 8-inch diameter pipeline. The
purpose of the lateral pipelines is to connect into Kinder Morgan and Chevron pipelines to
distribute product into the Phoenix, Tucson, and Albuquerque markets. Chevron operates
an 8-inch pipeline that delivers product to the Albuquerque market; Kinder Morgan operates
one 12-inch pipeline and one 8-inch pipeline serving the Tucson market. Other Kinder
Morgan pipelines connect Tucson to the Phoenix market.
One additional eight-inch pipeline, to be installed in the same right-of-way as the El Paso
laterals, will create a return system between the El Paso Terminal and the point of the
lateral pipeline connections to Kinder Morgan and Chevron. The return system will be used
to displace product from within the lateral pipelines back to the El Paso Terminal. The
return system will allow product of one type to be removed from a lateral pipeline, prior to
initiating delivery of a different product into one of the Kinder Morgan or Chevron pipelines,
thus facilitating quality control of products delivered to those pipelines. The return system
will be accomplished by installation of a manifold at the point where the lateral pipelines
connect to the Kinder Morgan and Chevron pipelines.
After startup, Longhorn plans to periodically increase capacity to reach an ultimate capacity
of 225,000 bpd. To reach this capacity, Longhorn will, in the future, build ten new booster
pump stations and will refurbish or reconstruct three existing stations at the following
locations:
Approximate Location
Station
(milepost to milepost)
Buckhorn
MP 67.5 - MP 77.5
Warda
Existing site
Bastrop
Existing site
Orotaga
MP 203.8 - MP 213.8
Eckert
Existing site
Llano
MP 265.0 - MP 275.0
Cartman
MP 334.0 - MP 344.0
Olson
MP 410.0 - MP 420.0
Big Lake
Approximately MP 373.4
Pecos
MP 516.2 - MP 526.2
Utica
MP 543.6 - MP 553.6
Cottonwood
Approximately MP 576.3
Harris
MP 642.6 - MP 652.6
The Longhorn project includes both new construction and refurbishment of an existing
99144ba2.v8
9

<<<PAGE 549>>>

pipeline that has been converted from its former use of transporting crude oil from West
Texas to the Gulf Coast area. The existing pipeline has been modified to transport refined
petroleum products, with flow going from east to west. Williams Pipe Line Company
(Williams) will be the contract operator of the Longhorn Pipeline System. Longhorn intends
to transport multiple grades of gasoline and distillates (i.e., various grades of diesel fuel and
jet tuel).
The GATX to El Paso segment of the Longhorn Pipeline will function as an interstate
common carrier pipeline for those product volumes that will be transported across state
lines through the Longhorn Pipeline connections with the Kinder Morgan and Chevron
pipelines that extend across the Texas border into New Mexico and Arizona. Product
volumes moved from GATX to El Paso for delivery at El Paso will be intrastate movements.
The Crane to Odessa segment of the Longhorn Pipeline is an intrastate common carrier
pipeline since it transports products solely within the State of Texas.
Table 2 lists a chronology of overall pipeline actions leading up to the present.
Table 2 - Chronology of Longhorn Pipeline Actions
1949-1950
Exxon constructed the original 18"/20" pipeline, Crane to Baytown, to transport crude oil.
1950-1990
Operation and Periodic maintenance/refurbishment.
1990
An internal inspection (smart pig) of the 20" pipeline was performed.
1995
An internal inspection of the 18" pipeline was performed.
1995-1996
The 18" and 20" pipelines were subjected to a hydrostatic pressure test and purged with
nitrogen.
Oct 21, 1997
Longhorn acquired the existing pipeline from Exxon.
1s Qtr. 98
Longhorn cleaned the existing pipeline to remove crude oil from the inner walls, so to
prepare the existing pipeline for use in petroleum products service. Construction of new
pump stations, terminals, and new pipeline sections began.
1998/1999
New Construction completion dates (dates shown are dates of substantial completion):
Galena Park Origin Station - August 1998
Satsuma Pump Station - August 1998
Cedar Valley Pump Station - July 1999
Crane Pump Station- March 1999
Kimble County Pump Station - July 1999
El Paso Terminal and Pump Station - August 1999
20" Pipeline, GATX to Tie-In to Existing 20" Pipeline, Houston - October 1998
8" Pipeline, Crane to Odessa - November 1998
18" Pipeline, Crane to El Paso - November 1998
(0.5 mile remains to be constructed to Odessa Meter Station)
Odessa Meter Station - In design
Equipment installation remaining at a few sites
Cleaning and refurbishment of the existing pipeline 18"/20"- March to November 1998
Pipeline Laterals - In design (from El Paso terminal to tie-in point with three interstate
1999
Longhorn commenced implementation of Environmental Assessment mitigation measures,
pipelines)
2000
including maintenance construction and investigation of potential pipeline flaws.
Longhorn continued implementation of Environmental Assessment related pipeline mitigation
testing of the Houston to Crane segment of the pipeline, investigation of potential pipeline
measures, including ROW maintenance and marking, maintenance construction, hydrostatic
flaws, and cathodic protection system improvements.
Additional details about the pipeline system, and its operation and maintenance, are
contained in Section 7.0 of the Longhorn
Pipeline Project Description prepared in
99144ba2.v8
10

<<<PAGE 550>>>

connection with the EA; a copy of the Project Description is provided in the accompanying
Phase Two Project Documentation Appendix at Tab 6.
For purposes of this Phase Two BA, Longhorn has identified the areas along the pipeline
where operating and maintenance activities "may affect" species and habitat. Areas of
potential effect include areas of potential species habitat along the pipeline route. Those
areas are identified in two documents: (a) Table 3, which lists pipeline stationing numbers
for potential habitat areas along the course of the pipeline; and (b) Figures 2 through 10
which graphically depict those same potential habitat areas.
This BA addresses those portions of the overall project that were not specifically identified
in the Phase One BA. Those items include pipeline operation, long-term maintenance,
planned additional construction and future unforeseen construction, potential pipeline
release and related emergency response, construction on the Edwards Aquifer recharge
zone and at Buescher State Park, hydrostatic pressure testing of approximately 60 miles of
pipeline that was not tested pursuant to the Phase One BA, internal treatment of the
pipeline with corrosion inhibitor, and right-of-way clearing over the Edwards Aquifer
recharge zone. Details of general construction procedures and environmental protection
guidelines for implementation of maintenance construction and pipeline testing activities are
contained in the Phase One BA and are not repeated herein.
Specific construction
procedures and environmental protection guidelines for the construction sites at Buescher
State Park (Houston toad habitat) and the Edwards Aquifer recharge zone are provided
below. Additional procedures and guidelines, as referenced in the following, are contained
in various parts of the Phase Two Project Documentation Appendix.
The EA assigned tier rankings to individual segments of the entire pipeline that identify
environmentally sensitive areas along the pipeline route. "Areas were identified as
sensitive based upon proximity and density of population, ground water (with an emphasis
on drinking water supplies), surface water, presence of threatened and endangered
species habitats, and proximity to recreational areas." See Draft Longhorn EA at Section
9.2.3. Sensitive
areas were divided into two categories, Tier | (sensitive) and Tier I!!
(hypersensitive); areas not designated as Tier II or Tier III are designated as Tier I. A
description of the methodology employed by the Lead Agencies to designate such sensitive
and hypersensitive areas is set forth in Appendix 9C of the EA, along with maps of those
areas. This Phase Two BA refers to such sensitive and hypersensitive areas.
99144ba2.v8
11

<<<PAGE 551>>>

Horizon
ENVIRONMENTAL SERVICES, INC.
Table 3: List of Endangered Species Habitat Areas
Along The Longhorn Pipeline
Houston to El Paso
Begin Station
2310+88
2013+44
End Station
2411+20
2279+20
County
Waller
Harris
Harris
Texas Prairie Dawn
Species
2684+00
4662+00
2831+84
Texas Prairie Dawn
5936+48
5095+20
4782+00
Fayette
Austin
Texas Prairie Dawn
5128+64
Navasota Ladies-Tresses
Navasota Ladies-Tresses -
Houston Toad
6723+20
6600+00
6638+72
5948+80
Bastrop
Fayette
9152+00
9011+20
9152+00
6864+00
Bastrop
Houston Toad
Travis/Hays
Travis
EA Recharge Zone
Houston Toad
9724+00
9657+12
9674+72
9961+60
Hays
Hays
Golden-Cheeked Warbler
EA Contributing Zone
9850+72
9762+72
10164+00
9945+76
10036+40
9926+40
Hays
Golden-Cheeked Warbler
Hays/Blanco.
Hays
Golden-Cheeked Warbler
10266+08
10461+44
10199+20
Golden-Cheeked Warbler
Blanco
Golden-Cheeked Warbler
11008+80
11080+96
11036+96
Blanco
Golden-Cheeked Warbler
Golden-Cheeked Warbler
11691÷68
11295+68
11441+76
11105+60
Blanco:
Blanco
Golden-Cheeked Warbler
Black-Capped Vireo
12114+08
11791+28
11751+52
12149+28
11821+92
Gillespie
Gillespie
Golden-Cheeked Warbler
Golden-Cheeked Warbler
12513+60
12633÷28
12596+32
12606+88
Gillespie
Gillespie
Golden-Cheeked Warbler
12631+52
Gillespie
Golden-Cheeked Warbier
Black-Capped Vireo
12921+92
12728+32
13043+36
13110+24
12953+60
Gillespie
Mason
Mason
Golden-Cheeked Warbler
Black-Capped Vireo
13203+52
13381+28
13277+44
13305+60
13217÷60
Mason
Golden-Cheeked Warbler
Golden-Cheeked Warbler
13513+28
13437+60
Mason
Mason
Black-Capped Vireo
Black-Capped Vireo
15153+60
14476+00
16329+28
13578+40
Mason
Kimble
Tobusch Fishhook Cactus
Black-Capped Vireo
15234+56
Kimble
Black-Capped Vireo
4/5/00
11 29 PM
indengered species hatreat ist
RAD 3907

<<<PAGE 552>>>

Louisiana
FIGURE 2
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
SHEET LOCATION MAP
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
LONGHORN PIPELINE
FIGURE 3
HOUSTON
HARRIS
FIGURE 4
AUSTIN
FIGURE 6
FAYETTE
FIGURE 5
RAVIS
AUSTIN
BASTROP
HAYS
FIGURE 8
LLANO 3
BLANCO
GILLESPIE
MASON
FIGURE 7
MENARD
KIMBLE
FIGURE 9
SCHLEICHER
FIGURE 1ó
NOT TO SCALE
RF AGAN!
CROCKETT
LONGHORN REFINED PRODUCTS
APPROXIMATE CITY LOCATIONS FOR
AS SUCE IN ATON (10/97
state.tx.ua/dato._oz.html), 1998
Mexico
UPTON
PIPELINE
REFERENCE
ODESSA
CRANE
CRANE
EXPLANATION
CRANE
SOURCES:
RAD 39072

<<<PAGE 553>>>

FIGURE 3
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
TEXAS PRAIRIE DAWN-FLOWER
HARRIS
EXAS PRAIRIE DAWN-FLOWEI
Hmenarys ferono
VAVASOTA LADIES -TRESSES
Saronthes ports"
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
On DAT
PIPELINE
• COUNTY BOUNDARY
- HIGHWAY OR MAJOR ROADS
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
RAILWAYS
BRIDGES
CEMETERY
- LLP-2546 MAINTENANCE CONSTRUCTION
LOCATION
TEXAS PRAIRIE DAWN-FLOWER
WALLER
EXPLANATION
MC. SITE MMESTIOMON (RUNE 1999)
=:
MILES
PINE iSLAND
5 PEAS TOTA TREAD LURE DE: MATE PANTS OF
NAVILLE
359
2 RESOURCES TORTOR T 579/9
2 HIS TEN MOO BUT SINGE (197D, OF TOUS
5. HORIZON ENMRONMENTAL SERVICES.
* SURCES

<<<PAGE 554>>>

~ un HOUSTON TOAD I
(POTENTIAL HABITAT)
AUSTIN,
FIGURE 4
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELIN
WASHINGTON ~
NAVASOTA LADIES-TRESSES
TOMS PRAT DON-TOWER
AMONTA PIES -TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
OLDENBURE
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—12P-2516 MUCITONMCE CONSTRUCTION
EXPLANATION
RAD 39074
MC. SITE DMESTIGITOM (UNE 1990)
NAVASOTA LADIES-TRESSES
FAYETTE +
ROTECTED MATHE PLANTS OF
VILES
00 5 50 0/9/90
2 TO TO NO BON SONE TIES OF TOUS.
OURCES
NO SOURCE

<<<PAGE 555>>>

Hono
FIGURE 5
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
RTLEY.
HOUSTON TO CRANE SEGMENT
COUNTIES OF: TEXAS
LONGHORN PIPELINE
HOUSTON O HoL ESOTE AREAS OF POTENTIAL FEDERALLY-LISTED
COLORADO
HOUSTON TOAD
(POTENTIAL HABITAT)
REPLACEMENT.
PIPE
HOUSTON TO ALSTOM
HOUSTON TOAD
Countaco ChO OMELER
AANO AAD VREO
TORsto coti PoK aCTUS
MAISOTA S PONt-TRESSES
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
LE DESIGNATED CRITICAL HABITA
— COUNTY BOUNDARY
→ J ACHMAY OR ANOR RONOS
CITY STREETS
RIVERS AND STREAMS
NTERMTTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
BASTROP
ROADS
RAILWAYS
BRIDGES
CEMETERY
- LLP-2516 MAINTENANCE CONSTRUCTION
LOCATION
EXPLANATION
WATTERSON
OCKNE
& HORIZON DIMRONMDYTAL SERMCES, INC, SITTE IMMESTIGMOM (RUNE 1999)
2. TeSORCES TORSTON S13T3 (3/87
2 TIS FSH MOO DUF SONOS 19ES, OF TOUS.
S. PON TEDA PASSED MATE DER ME PRATS. OF

<<<PAGE 556>>>

"ZONE'T
UKAWINU 990144-A29
NUMBER
FIGURE 6
AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
EDWARDS RECHARCE
KŁVISED
BY
3/8/00
HAYS
DKAr 1
TRAVIS
MASON POTS-TRESSES
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
CONTRIBUTING ZONE
ORIPPING
GOLDEN-CHEEKED WARBLER
— COUNTY BOUNDARY
332 HIGHMAY OR MAVOR ROADS
CRY STREETS
RIVERS AND STREAMS
INTERMITTENT STREANS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MAATRANCE CONSTRUCTON
EXPLANATION
RAD 39076
DOES OF TOUS:
CE BE MATE PLAITS OF
ACHMENTAL SERMCES, NC. STE BMESTIEATION (INE 1990)
MILES
5763/9/94
Do Not Scole This Drawing
BLANÇO

<<<PAGE 557>>>

AREAS OF POTENTIAL FEDERALLY-LISTED
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
BLACK-CAPPED VIREO
BLANCO
MAMOTA POTS TRESSES
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
→ CACHTY OR MANOR RONOS
— COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—LLP-2516 MUNTIONICE COMSTRUCTION
cORO
EXPLANATION
GOLDEN-CHEEKED WARBLER
man 20n77
PIPELINE
MILES
ÇILEŚPIE
DA SON (TO), OF TONS
LLANO
MPSOURCES
5 POET TOE

<<<PAGE 558>>>

ABAPPLE
PIPELINE
LLANÓ
FIGURE 8
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
| GOLDEN-CHEEKED WARBLER
> I BLACK-CAPPED VREO
HOUSTON TOND - DESIGNATED AREAS OF POTENTIAL FEDERALLY-LISTED
con
HILLTOR 7
GILLESPIE
HABITA Buto houstone)
ADO CARDO VARCO
EDMARDS RECHARGE ZONE
CONTRIBUTING ZONE
2242
GOLDEN-CHEEKED WARBLER
COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
-IP-2516 LOCATONCE CONSTRUCTION
EXPLANATION
BLACK-CAPPED VIREO.
RAD 39078
MASON
1.5
MILES
a HORIZOM DIMRONMENTAL SERMICES, MC, SITE BESTOMOM (LUME 1990)
2 TAS TEN MONO BIA SINCE TOD, OF TOAS
PIPELINE
DO SOURCES.

<<<PAGE 559>>>

rook
-GILLESPIE
BLACK-CAPPED VIREO
88
FIGURE 9
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
HOUSTON TOAD - DESIGNATED AREAS OF POTENTIAL FEDERALLY -LISTED
MASON
HABITAT Buto houstonerais)
GOLDEN-CHEEKED WARBLER
(Dendracio chrysoporio)
Testroots tok carys
JAVASOTA LADIES-TRESSES
(arranthes port)
EDWARDS RECHARGE ZONE
CONTRIBUTING ZONE
MOUNTAN
COUNTY BOUNDARY
→ Je HIGHMAY OR MUOR RONDS
CITY STREETS
RIVERS AND STREAMS
NTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
— 11-2516 MAUATINANCE CONSTRUCTION
EXPLANATION
KIMBLE
#/**
RAn
LONDON
cook
TOBUSCH FISHHOOK CACTUS
3480 YATES
& HORIZON EMIRONMENTAL SERVICES, MC, SITE IMESTIGATIOM (SUME 1999)
TEACUP
ST PASSED OUR UST MONE PLANTS OF
2. THE AN AND DIA SOME TODD OF TOUS.
MENARD
377

<<<PAGE 560>>>

NUMOLN -
BLACK-CAPPED VIREO
CÁCTUS LOCATION
FIGURE 10
THREATENED OR ENDANGERED
SPECIES HABITAT
TRAVERSED BY
LONGHORN PIPELINE
HOUSTON TO CRANE SEGMENT
COUNTIES OF TEXAS
LONGHORN PIPELINE
PIPELINE
HOUSTON TO DEED AREAS OF POTENTIAL FEDERALLY-LISTED
DI
310/00
KIMBLE
TOAD - POTENTIAL
TRA PRAN I DONY FOWER
SOOTA POES-TESSES
EDWARDS RECHARGE ZONE
TOBUSCH FISHHOOK CACTUS
CONTRIBUTING ZONE
/
Pook
MENARD
→ CONNY OR MANOR ROADS
• COUNTY BOUNDARY
CITY STREETS
RIVERS AND STREAMS
INTERMITTENT STREAMS
COMMUNITY BOUNDARIES
LONGHORN PIPELINE
ROADS
RAILWAYS
BRIDGES
CEMETERY
—11P-2516 MANTEOANCE CONSTRUCTION
EXPLANATION
RAD 39080
1674
SITE MMESTOKTON (RUME 1990)
MILES
PIPELINE
I SON (1092, OF TOUS
SUTTON
2 TrOot COUNTY
SCHLEICHER
SOURCES:

<<<PAGE 561>>>

3.2 Pipeline Operation
Operation of the Longhorn Pipeline essentially involves the pumping of refined petroleum
products through the pipeline to terminals at El Paso and Odessa, where the products are
stored in above-ground breakout tanks. From either terminal, the products will be loaded
into tank trucks for transport to distribution facilities (such as gas stations and fleet servicing
facilities). In addition, at the El Paso Terminal the products may be re-introduced into the
connecting pipelines,
and then to interstate pipelines operated by Kinder Morgan and
Chevron, for transport to southwestern markets.
The process of pumping refined products involves the following steps. First, products from
bulk storage tanks at the GATX terminal in Galena Park are introduced in batches to the
pipeline at the Longhorn GATX pump station. As the products proceed through the
pipeline, booster pump stations continue to move the product stream; those booster
stations include Satsuma Station in northwest Houston, Cedar Valley Station in Hays
County, Kimble County Station in Kimble County, and Crane Station in Crane County.
Product destined for Odessa is stored in above-ground breakout tanks prior to re-
introduction to the 8-inch pipeline between Crane and Odessa.
The pipeline system is operated and controlled remotely from the Williams control center in
Tulsa, Oklahoma, using the supervisory control and data acquisition (SCADA) system. The
SCADA system allows the controller to start and stop pumps, open and close valves, and
monitor the functions of the system components. Pump station and valve site operations
are managed by programmable logic controllers that interpret and execute commands from
the system controller. A multitude of sensors installed in the pipeline and its equipment
provide data to the controller and the automated leak detection system.
Primary
communications are conducted by satellite, with backup provided by land line systems.
Section 7.0 of the Longhorn Pipeline Project Description provides additional detail about
system operation; see Phase Two Project Documentation Appendix at Tab 6.
3.3 Long-Term Maintenance
Maintenance of the Longhorn Pipeline requires activities directed to specific components of
the system. For example, pumps and valves receive inspections and maintenance such as
lubrication; above-ground tanks receive inspections and maintenance; the right-of-way
(ROW) is mowed periodically, and ROW marker signs are erected and replaced as
necessary (see Phase One BA); and the pipe is periodically subjected to thorough
inspection and analysis that may dictate a variety of maintenance approaches. Additionally,
corrosion inhibitor is regularly injected into the product stream to prevent internal corrosion.
This Phase Two BA focuses on those maintenance activities that could occur within areas
of habitat identified during Phase One. Since the El Paso terminal is not within potential
habitat areas, terminal maintenance activities are not treated in this BA. Since Kimble
County Station is within a habitat area (Tobusch Fishhook Cactus) and Cedar Valley
Station is in an area of potential effect to the Barton Spring Salamander, station
maintenance descriptions will focus on activities conducted at those stations.
Valve Maintenance
99144ba2.v8
22

<<<PAGE 562>>>

Valve maintenance involves periodic inspections (twice per year, not to exceed 7 ½ months
between inspections, per 49 C.F.R. 195.420(a)) to ensure that the valve is not leaking and
to confirm that the valve is operable. Leak and overall condition inspection is visual, as
described
| in the Williams Operating and Maintenance Manuals, Maintenance and
Calibration section, Valve Maintenance and Calibration (Phase Two Project Documentation
Appendix at Tab 7). If a leak is identified, corrective action is taken to stop the leak and
perform cleanup of any product released. All lubricants are managed to prevent any
release to the environment; specific procedures are identified in the Williams System of
Manuals, Operating Manual, Section 12 (Phase Two Project Documentation Appendix at
Tab 7).
Pipeline Cleaning
Pipeline cleaning is conducted approximately twice per year to remove deposits from the
inner walls of the pipe. Pipe cleaning involves the introduction of a spherical or cylindrical
scraper (also known as a scraper pig) into the pipeline at a pump station; the scraper
travels within the product stream and is removed at a downstream station, along with any
debris collected along the way. Launching and receipt of the scrapers is accomplished by
way of scraper launchers and scraper receivers (traps, also known as strainers) that are
installed at the pump stations. Any debris removed from the pipeline is contained in drums,
and drip pans are employed to prevent release to the environment; disposal of the material
is conducted in accordance with applicable laws and regulations.
Pump Station Maintenance
Pump station maintenance protocols depend upon the equipment located at each individual
station; however, only two similarly equipped stations lie within habitat or in an area of
potential effect to species. Those are Kimble County station which is located in Tobusch
Fishhook Cactus habitat in Kimble County and Cedar Valley Station which is located in the
Edwards Aquifer contributing zone. Each of those stations contains minimal equipment,
the major components of which are pumps and electric motors, scraper launcher/traps,
above-ground station piping (to bypass a pump or the station as a whole), intake and
outflow (suction and discharge) remote-controlled motor operated block valves, and a
station control room. No tanks are located at those two stations.
Maintenance of the pump station equipment follows generally the same procedures
outlined above for valve maintenance, and below for painting of above-ground components.
Pumps require inspection and periodic calibration. Calibration requires that the pump
cases be opened for measurement of component tolerances. To do so, the pump is
isolated from the pressurized pipeline system, and the case is opened; product remaining
within the case is collected in a sump system for re-injection to the product stream. The
sump system is sealed and cathodically protected to prevent releases to the subsurface.
Drain pans are used if product cannot be drained to the sump; the drain pans are emptied
to the sump system for re-injection. Any debris removed from the pump case, along with
wipe rags, sorbent pads, and other disposable materials, are collected in a closed top
containment drum and stored on a concrete containment skid. The waste materials are
classified and then disposed of at an approved disposal facility.
99144ba2.v8
23

<<<PAGE 563>>>

Pipe cleaning debris (see foregoing section) is collected in strainers located at each pump
station. The strainers are located upon a concrete skid that contains any liquid from the
strainer and drains to the station sump system. Drain pans are used to contain any liquid
that will not drain directly to the sump system. Debris removed from the strainer is
collected in closed top containment drums and stored on a concrete containment skid. The
waste materials are classified and then disposed of at an approved disposal facility.
Painting Above-Ground Components
Above-ground pipeline components must be protected with coatings (Longhorn uses paint)
to prevent atmospheric corrosion (49 C.F.R. § 195.416(i)). Above-ground facilities include
pump equipment, valves, meter facilities, and the like. Maintenance of the coatings
requires periodic painting, typically on a 5 to 10 year cycle. Any waste materials generated
during painting are managed to prevent release to the environment. See the Williams
System of Manuals, Operating Manual, Section 12 and the Longhorn Environmental
Protection Plan (Phase Two Project
Documentation Appendix at Tabs 7 and 8,
respectively).
Pipe Integrity Maintenance - Introduction
Pipe integrity maintenance activities result from inspections and analyses that identify
potential threats to pipe integrity; maintenance may then occur to reduce the risk
associated with a particular threat.
In-Line Inspection
In-line inspection is the process of examining the pipe for flaws, corrosion anomalies,
dents, cracks, and other flaws using sophisticated electronic inspection devices known as
The technology applied is known as high resolution magnetic flux leakage
(MFL) and transverse field MFL, and geometry and ultrasonic inspections are performed as
well. Smart pigs identify anomalies and record the locations. The smart pig data is then
processed and analyzed, both manually and by computer, to determine whether or not the
identified anomalies represent pipe flaws that require corrective action. Next, the
anomalies are graded and prioritized for inspection; upon inspection, repairs are made, if
necessary, to offset the potential adverse effect of the specific flaw. Actions will range from
re-coating of a location not requiring repair, to replacement of the flawed pipe with a
cylinder of new pipe; typically minor repair such as application of a protective sleeve is all
that is necessary. Maintenance construction to investigate and repair flaws identified by
the in-line inspection will be conducted in accordance with the procedures set out in the
Phase One BA
An in-line inspection may produce data that indicates an immediate threat to pipeline
integrity, prompting an immediate inspection by excavating the pipe. If an actual threat
exists, a repair is made, and otherwise the pipe is coated and buried. In either event, the
protection of human health and safety and of the environment is accomplished while efforts
are undertaken to avoid all potential adverse effects. See LMP at Sec. 3.5.2.
Smart pigs are introduced and extracted from the operating pipeline through the scraper
launcher/trap at each pump station; however, some pipeline segments between pump
99144ba2.v8
24

<<<PAGE 564>>>

stations are long enough that the smart pig cannot complete the entire run. In such cases,
a temporary launcher/trap assembly is installed on the pipeline to allow removal of the
smart pig so that data may be downloaded, batteries recharged, and the smart pig re-
launched. Construction to install and remove the temporary launcher/trap assembly is
similar to construction to install a hydrostatic pressure test header as described in the
Phase One BA. Electronic tracking devices that monitor and record smart pig travel are set
on top of the ground during the tests.
The initial in-line inspections to be performed pursuant to Longhorn Mitigation
Commitment 11 shall consist of a high resolution MFL inspection within three (3) months of
system startup. The timing of subsequent in-line inspections of all types will be determined
by the Longhorn Pipeline System Integrity Plan and associated Operational Reliability
Assessment processes.; the LMP sets maximum intervals for certain tools See Longhorn
Mitigation Plan, Items 10, 11, 12, and 12A, and at Section 4.0. No more than three years
shall pass without at least one in-line inspection. Temporary launcher/trap assemblies, if
any are necessary, will be installed outside of areas of species habitat; thus, no effect upon
species is foreseen as a result of in-line inspections.
Hydrostatic Pressure Testing
Integrity maintenance of the pipeline could require periodic hydrostatic pressure testing, if
prompted by the Longhorn Operational Reliability Assessment (see LMP at Sec. 3.3 and
4.0). Hydrostatic pressure testing as prompted by the ORA could encompass different
segments of or all of the pipeline.
The Phase One BA describes in detail the processes
and activities involved in hydrostatic testing, and future testing will be conducted in
conformance with the Phase One BA in all respects to avoid potential adverse effects.
Corrosion Inhibitor Treatment
Shortly after the conclusion of this consultation, Longhorn will treat the pipeline to prevent
potential internal corrosion. As a matter of course, potential internal pipe corrosion is
managed through several means including the injection of corrosion inhibitors to the
product stream. Due to the delays encountered during the Environmental Assessment of
the Longhorn pipeline, however, product has not been transported and no corrosion
inhibitor has been applied.
At the urging of the Service, Longhorn elected not to inject corrosion inhibitor during the
hydrostatic and proof tests commenced in February. Due to the project delays associated
with the Environmental Assessment, Longhorn intends to treat the pipeline at its next
opportunity to reduce the potential for internal corrosion prior to project startup. This
process may be repeated from time to time as deemed necessary to maintain internal
pipeline integrity; however, Longhorn's present expectation is that only one such treatment
will be necessary.
The treatment process involves the introduction of a water and corrosion inhibitor mixture
into the pipeline at the GATX Terminal in Houston and the mixture pushed through the
pipeline with injected nitrogen gas pressure. This will not constitute a pressure test or
alteration of operating pressures.
Maximum pressures involved in the procedure would not
reach normal operating pressures. These pressures are significantly below the 1,100 to
99144ba2.v8
25

<<<PAGE 565>>>

1,500 psig pressures experienced during periodic hydrostatic testing of the pipeline. At
seven intervals along the pipeline (existing valve settings), surface equipment would be
needed to facilitate the handling of the water slug and pigs if the procedure is conducted
independent of product flow in the line. Those points typically would be:
MP 34.09
(Satsuma Station)
MP 134.67
(west side of Colorado River)
MP 151
(eastern Travis County)
MP 182
(Cedar Valley Station)
MP 227.9
(Eckert Station)
MP 358.7
(west of El Dorado)
MP 457.5 (Crane Station)
At these points, trucks and equipment would be employed to facilitate the launching and
recovery of pigs and nitrogen injection. The water mixture would be recovered into vacuum
trucks at Crane Station for proper disposal.
The corrosion inhibitor agent to be utilized is manufactured by Baker-Petrolite and goes by
the commercial name "Magnacide 575." Material Safety Data Sheets for this product are
included in the Phase Two Project Documentation Appendix.
Cathodic Protection
Maintenance of the cathodic protection system requires periodic inspection and testing and
potential system enhancements. Testing and inspection involves pipe-to-soil surveys,
close interval surveys, rectifier inspections, casing tests, and interference testing.
Pipe-to-soil potential surveys require that pipe-to-soil readings, measured in volts, be taken
at pre-existing test stations that are spaced along the pipeline. Survey personnel typically
travel along the pipeline in a pickup truck. Pipe-to-soil surveys will occur semi-annually in
EA-designated sensitive and hypersensitive areas and annually in other areas.
Close interval surveys require that pipe-to-soil potential readings be taken approximately
every three feet along the pipeline; thus, testing personnel walk the pipeline, typically in a
group of two to five, carrying testing equipment and data loggers. Close interval surveys will
be conducted annually in EA-designated hypersensitive areas and on the balance of the
pipeline as dictated by the Longhorn Pipeline System Integrity Plan and associated
Operational Reliability Assessment (see LMP at Sections 3 and 4, Tab 4).
Rectifier inspections include monthly visual inspection and recording of voltage and
amperage readings to ensure normal operation; bi-monthly inspections are required by the
pipeline safety regulations (49 C.F.R. § 195.416(c)). Casing testing may involve pipe-to-
soil potential readings and/or electrical current and resistance readings to determine if the
99144ba2.v8
26

<<<PAGE 566>>>

casing is in direct contact or electrolytically shorted to the carrier pipe. Interterence testing
involves pipe-to-soil readings and/or line current measurements to determine whether or
cathodic protection system is interfering with the cathodic protection current that protects
not a nearby metal object (such as a crossing or parallel pipeline) or the associated
the Longhorn pipeline.
Pipe-to-soil surveys, close interval surveys, casing testing, and foreign interference testing
may identify sections of pipe that require additional cathodic protection or other measures,
such as coating re-conditioning, shorted casing remediation, or installation of a bond
between the Longhorn pipeline and a source of foreign structure cathodic protection
interterence.
The addition of cathodic protection current most likely will occur through the installation of
sacrificial anode or impressed current ground beds. The procedure for installation of a
ground bed is contained in the Phase One BA, as is the procedure for coating
reconditioning. Shorted casing remediation involves removal of a direct metallic short (i.e.,
a spacer bolt or a short segment of the casing end in contact with the carrier pipe), or
draining electrolyte (water/mud) from the casing. Some casing remediations may require
installation of new pipe, often concrete coated, through the casing or the installation of
heavy wall thickness pipe, also with an abrasion resistant overcoat (i.e., concrete), bored
under the road/railroad crossing. Any such work in habitat areas will follow the
maintenance construction procedure outlined in the Phase One BA.
Installation of a bond (a cable) to a foreign source of cathodic protection interference would
involve a small excavation between the Longhorn Pipeline and the foreign structure, which
are by definition in close proximity. A cable is installed between the facilities and secured
to the pipe, usually by thermite welding. Typically, an interference bond installation will
occur at or very near a crossing of the pipelines. A bell-hole excavation of approximately
ten feet by ten feet, or one-hundred square feet, is sufficient. A depth to that of the deepest
line, normally six to eight feet, is needed for the installation. Note that only the top side of
the deeper line, not the entire circumference, needs to be exposed to accommodate lead
attachment. The cables are brought into an
aboveground test station for current flow and
pipe-to-soil potential monitoring. The test station will generally be set directly over the
pipelines' intersection. However, in some cases, if a fence line is nearby, the leads will be
extended to that fence and the test station installed at that location. The trench for leads
from the pipelines' intersection to the fence could range from ten to usually not more than
fifty feet and from 8 inches to three feet wide and approximately 30 inches deep or below
plow depth.
Typically, not more than one-hundred-fifty square feet of surface area is
disturbed for this trench and it typically remains within the pipeline rights-of-way. Coating
disturbed during cable installation is repaired. Any such work in habitat areas will follow the
maintenance construction procedure outlined in the Phase One BA.
Cathodic protection system maintenance construction is typically conducted completely
within the existing ROW. Though unexpected, the possibility exists that future construction
could require work to occur outside the existing ROW, since a particular site could be
attended with work space constraints (see procedure in the Phase One BA).
Depth of Cover
99144ba2.v8
27

<<<PAGE 567>>>

In 1998 Longhorn performed a depth of cover survey to determine the burial depth of the
pipeline. In response to the findings of that depth of cover survey, Longhorn has identified
a number of locations where the pipeline will be lowered or replaced. Examples of such
locations are represented by LMCs 5 and 18; those locations were identified through the
depth of cover survey and assigned priority either by Radian in the case of sensitive and
hypersensitive areas (LMC 5) or by Longhorn in the case of other lowerings (LMC 18). In
the coming years, the Longhorn Pipeline System Integrity Plan, Depth of Cover element,
will determine, on a risk-assessed basis, the order and timing of future pipeline lowerings.
The locations are prioritized by evaluating the potential for damage to the pipe.
As those locations are addressed, the activity will follow the maintenance construction
procedures described in the Phase One BA. Maintenance construction is typically
conducted completely within the existing ROW. Though unexpected, the possibility exists
that future construction could require work to occur outside the existing ROW, since a
particular site could be attended with work space constraints (see procedure in the Phase
One BA).
Removal of Encroachments
Longhorn has identified a number of encroachments that will be removed from the pipeline
ROW within one year of system startup, in accordance with the commitments of the LMP
(See LMC 16). The Service has requested Longhorn's assistance to increase landowner
awareness of species and habitat concerns in connection with encroachment removal.
Longhorn thus hereby commits to seek to include in any agreement with an encroaching
landowner the following acknowledgment:
Landowner is hereby informed that threatened or endangered species and/or
habitat may exist upon or in proximity to the Property [defined term to identify
the Longhorn ROW], and Landowner may have responsibilities to consult with
the U.S. Fish and Wildlife Service pursuant to the Endangered Species Act.
Longhorn acknowledges that the foregoing does not specifically prohibit by contract
Landowner activity that could cause adverse effects to species and habitat. Since any
agreement for encroachment removal would be voluntary, Longhorn cannot force
landowners to agree that adverse effects will be avoided. Landowners would simply refuse
to agree to such prohibitions, leaving Longhorn's power of eminent domain as the remedy.
The power of eminent domain does not include within its scope the authority to require
landowners to contractually agree to comply with applicable statutory requirements. In
summary, Longhorn agrees to raise awareness as much as it legally may.
Section 7.0 of the Longhorn Pipeline Project Description provides additional detail about
system operation and maintenance; see Phase Two Project Documentation Appendix at
Tab 6.
3.4 Emergency Response
Risk Based Approach - Longhorn Mitigation Plan
99144ba2.v8
28

<<<PAGE 568>>>

The EA process included the identification of pipeline mitigation measures that Longhorn
has committed to implement. Many of the pipeline mitigation measures were identified in
response to potential risks identified in the EA. The pipeline mitigation measures are
designed to reduce those risks by prioritizing the deployment of resources toward
the
following goals:
Prevention: Reduce the risk of a release by focusing on the four primary categories
of risk: outside force damage, corrosion, material defects, and improper operation.
Detection: Rapid identification of a pipeline release through use of the best available
leak detection technology system-wide, and sensor-based technology in the
Edwards Aquifer recharge zone.
• Release Volume Minimization: Optimal use of block valves, coupled with the
installation of additional check valves, will serve to reduce potential spill volumes,
including in areas of potential effect to species.
Control: Enhanced emergency response capability that employs thorough, detailed
pre-planning, resource identification, and resource retention.
A description of the manner in which those pipeline mitigation measures reduce risk is
presented in Longhorn's Risk Reduction Benefits Summary, Phase Two Project
Documentation Appendix at Tab 9.
Prevention - Reduce the Risk of a Release
Numerous pipeline mitigation measures are focused on reducing the risk of a pipeline
release; many pipeline mitigation measures reduce more than one risk category. For
example, hydrostatic pressure testing of the pipeline addresses outside force damage,
corrosion, and material defects by testing the pipeline to pressures that create a margin of
safety above operating pressures. Flaws that would create a potential for release during
operation are eliminated by raising and maintaining internal pipe pressure to at least 125%
of its operating pressure over an eight hour period.
The pipeline mitigation measures that reduce the risk of a release include the following:
:
Hydrostatic pressure testing (LMCs 1 and 2)
Replacement of an 19-mile segment over the Edwards Aquifer recharge and
contributing zones, with the additional protection of a concrete barrier over the pipe
(LMC 3)
•.
Cathodic protection system enhancements (LMC 4)
Lowering, replacing and/or reconditioning if necessary at least 38 locations (LMCs 5
and 18)
Removal of stopple fittings (LMC 6)
Investigation and repair if necessary of 7 potential pipeline flaws (LMCs 7 and 8)
Replacement of the crossing of Rabbs Creek (LMC 8)
Surge pressure in EA designated sensitive and hypersensitive areas will not exceed
maximum operating pressure (LMC 9)
99144ba2.v8
29

<<<PAGE 569>>>

• In-line inspection within 3 months of system startup and additional in-line inspections
according to the LMP, the Longhorn Pipeline System Integrity Plan and associated
Operational Reliability Assessment (LMCs 10, 11, and 12)
Increased frequency of cathodic protection system performance testing (LMCs 14
and 32)
•
Documentation of adequate pipeline span support and secondary containment at
tank facilities (LMCs 15 and 27)
•
Removal of encroachments to the pipeline ROW (LMC 16)
•
Clearing the ROW to excellent condition (LMC 17)
Analysis and remediation if necessary of stress corrosion cracking and earth
movement risks (such as water crossings and seismic activity) (LMC 19)
•
Increased frequency of pipeline surveillance patrols (LMC 20)
•
Increased frequency of pump station inspections and installation of remote cameras
at all pump stations (LMC 21)
Performance of a water crossing valve study, with DOT review and concurrence, of
additional check valves (LMC 22)
• Development of an enhanced public education program, with performance
monitoring (LMC 25)
The effect of the above mitigation measures is to significantly reduce risk far below pre-
mitigation levels.
Detect - Best Available Leak Detection Technology
Longhorn has committed to employ the best available, proven leak detection technology in
the pipeline industry. Pipeline mitigation measures that improve leak detection, thus
reducing the risk of an undetected leak, include the following:
• Enhanced, computational-based leak detection system-wide, and sensor-based leak
detection over the Edwards Aquifer recharge zone and the Slaughter Creek
watershed in the contributing zone (LMC 13)
Removal of encroachments to the pipeline ROW (LMC 16)
•
Clearing the ROW to excellent condition (LMC 17; see Phase One BA and the
Service's February 17, 2000 Biological Opinion)
•
Increased frequency of pipeline surveillance patrols (LMC 20)
•
Increased frequency of pump station inspections and installation of remote cameras
at all pump stations (LMC 21)
Development of an enhanced public education program, with performance
monitoring (LMC 25)
Minimize - Reduce Potential Release Volumes
Pipeline mitigation measures also focus on reduction of potential leak volumes:
•
Enhanced, computational-based leak detection system-wide, and sensor-based leak
detection
over the Edwards Aquifer recharge zone and the Slaughter Creek
watershed in the contributing zone (LMC 13)
99144ba2.v8
30

<<<PAGE 570>>>

•
Performance of a water crossing valve study, with DOT review and concurrence of
additional valves (LMC 22)
Install additional check valves, one over the Edwards Aquifer recharge zone and one
over the Edwards Aquifer contributing zone (this Phase Two BA; see section entitled
Edwards Aquifer Protections)
Control --Maximize Emergency Response Capability
Finally, Longhorn has committed to bolster its emergency response planning and
preparedness capability to reduce response times and to be prepared, in advance, with a
full response effort:
Ensure maximum 2-hour full response to EA designated sensitive areas, maximum 1
to 2 hours in hypersensitive areas, and maximum 1-hour response in the Edwards
Aquifer recharge zone and the Slaughter Creek watershed in the contributing zone
(LMC 23)
Establish a response center in South Austin (LMC 23)
Enhanced facility response plan will:
Address firefighting
in areas without Hazardous Materials response units
(LMC 24)
-
Provide detailed planning for areas with high populations of potentially
sensitive receptors (LMC 26)
Establish consistency with the City of Austin Barton Springs Oil Spill
Response Plan and the Service's Barton Springs Salamander Recovery Plan
(LMC 28)
-
Identify and provide detailed planning for multiple response locations within
the Edwards Aquifer recharge and contributing zones selected on the basis of
calculations of worst case times of transport to the recharge zone
In addition, Longhorn has included potential habitat areas on response plan maps and
included protection of such habitat areas in response planning and preparedness training,
in response to the Comment Letter (see Oil Pollution Act of 1990 Facility Response Plan).
Probability of Release and Risk Reduction
Longhorn has calculated the pre-mitigation probability of a pipeline release for the potential
habitat areas along the pipeline. Those figures are presented in the APR report at Tab 10
of the Phase Two Project Documentation Appendix. The basis for the probabilities
calculated is pre-mitigation data compiled by Radian for the Environmental Assessment.
Thus, the probabilities do not take into account the numerous risk-reducing pipeline
mitigation measures that Longhorn has committed to implement and is in the process of
implementing; see above section Prevention - Reduce the Risk of a Release, and Table 2,
Chronology of Longhorn Pipeline Actions.
The result, then, is that the possibility of a
release in the potential habitat areas will be further reduced from those shown in APR
report.
System-Wide Software-Based Leak Detection
99144ba2.v8
31

<<<PAGE 571>>>

The Longhorn Pipeline will employ the best available, technologically proven pipeline leak
detection system. The leak detection system is described in the following excerpt from
Item 13 of the LMP submitted in connection with the EA:
"Objective:
The objective of this program is to identify the Longhorn Release
identification time and the shutdown time required to minimize the size and
Detection Systems that will be employed to minimize both the leak
impact of a potential leak on the Longhorn Pipeline System.
Leak Detection Systems:
Leak detection for the unintended escape or potential loss of product
from Longhorn Pipeline incorporates the use of a combination of visual,
mechanical, and analytical processes, equipment, and models. Collectively,
Longhorn's Leak Detection System capabilities, which provide for several
areas of overlap, are designed to significantly reduce the likelihood of a
protracted period of undetected pipeline system breaches and continued
that would adversely contribute to human or
environmental exposure to hydrocarbon products. Heightened awareness of
the designated sensitive and hypersensitive areas along the Longhorn
pipeline has resulted in the employment of enhanced leak detection
technology and processes.
Longhorn's Leak Detection System is comprised of two primary components:
External Patrols; and Technology Based systems. By design, these two
areas of leak detection provide redundancy and assurance that a release will
be detected within the shortest time possible using current best available
technology.
External Patrols:
External Patrol of the Longhorn Pipeline System is primarily
accomplished through the targeted activities of Longhorn Operations and
directed third party surveillance contract personnel. Some of these activities
include aerial patrol, inspection of water crossings, ground based right-of-way
patrol, tank dike inspection, scheduled inspections of valve locations, surface
facilities, buried road crossings, and DOT regulatory based activities.
External Patrol is also enhanced through the incorporation of data
obtained through normal pipeline maintenance activities, such as those
accomplished via cathodic protection inspections, One-Call line spotting, and
physical pipeline examination during pipeline exposures.
Another important source of input under the category of External Patrol
results from the involvement of the general public, emergency response
organizations, contractors, and other third party sources. These groups are
specifically targeted via
• Longhorn's Damage Prevention Program (see
99144ba2.v8
32

<<<PAGE 572>>>

Longhorn Pipeline System Integrity Plan) and other activities which are
designed to instill awareness of the location of the pipeline corridor. Further,
active public education programs are designed to result in an increase in
public knowledge by which to primarily avoid, but to secondarily recognize,
any activities that could reasonably lead to adverse effects to the pipeline
system. With pipeline location awareness, product characteristic information,
and emergency response phone numbers and points of contact, the general
public, emergency responders, contractors, and other third party groups serve
as further insurance that system leaks can be minimized from third party
damage, may be recognized if one occurs, and in that case be communicated
to Longhorn Operations personnel.
External Patrol leak detection is dependent upon the physical
identification of some abnormality or change from the characteristics of the
surrounding area of the pipeline corridor. Physical evidence can include a
hydrocarbon odor, a sheen on a water surface, spraying product, bubbles
along the ground, discoloration of soil, areas of vegetation "browning," and
fires in near proximity to the pipeline assets. Similar to many other methods
of leak detection, External Patrol leak detection can readily identify a
moderate to major product release. Smaller leaks, be they from pinhole leaks
or leaking pipeline components, often require more time to trigger the physical
indicators such as defoliation or odor which indicate a potential product leak.
Technology Based:
Longhorn will employ a leak detection software system to monitor the
operation of its pipeline system. This system represents the current best
available, proven technology in the industry. The leak detection software is a
transient model that is designed to analyze and compare the actual pipeline
operations of pressures and flow rates against theoretical values during both
steady state and changing conditions. Deviations between actual and
theoretical values result in alarm indications and notification to the Operations
Control Center for subsequent review, analysis, investigation, and if
appropriate shutdown of the pipeline system.
Longhorn approached the selection of a computational based leak
detection software system through the employment of a highly respected third
party consultant who has demonstrated experience in the field of pipeline
SCADA systems and leak detection, along with a current understanding of
leak detection technologies and performance capabilities. Leak detection
performance requirements, based upon demonstrated industry achievable
levels and best available transient model technology, were developed by
Longhorn's consultant and approved by Longhorn's management.
Computational based Leak Detection "Requests For Proposals" were sent to
several prospective vendors, and responses were returned to Longhorn's
consultant for detailed review and evaluation. The review/analysis process
included clarifying discussions with the vendors, technical presentations, and
detailed reference checks with provided customer lists. This process yielded
two vendors who were judged to be capable of meeting the leak detection
99144ba2.v8
33

<<<PAGE 573>>>

performance requirements established by Longhorn. Further discussions with
the two "finalists" resulted in the selection of the computational based leak
detection software system that was determined to have the higher degree of
leak detection performance.
The software based leak detection system is fundamentally a volume
(mass) balance system that employs a fully transient model. The flow
balance calculated from flow measurements is corrected by the packing rate,
which is calculated by the "real-time" model. The resulting volume balance
allows calculation of potential leak indicators. A leak would be identified by
comparing the node flow balances at measurement points.
The model
dynamically tracks changes in the pipeline's flow rate. Variation between
modeled and measured flow shows up in the volume balance calculation.
The rate of change of all boundary measurements affects the leak detection
by affecting the model directly, as well as the dynamic thresholds. Leak
alarm thresholds are provided for each volume balance section and averaging
interval.
The SCADA system used for the Longhorn pipeline system operates
on Neles (formerly Valmet Automation) Oasys software version 5.2.
Longhorn operator Williams subscribes to the Neles maintenance program
which provides software program updates.
Williams maintains the most
a communeason and contin at the pie se
components. For example, in 1999 the SCADA system experienced 99.954%
reliability (after deduction for Y2K testing). The 0.046% down time for that
year is attributable to a single four-hour service outage. Thus, it is very
unlikely that the SCADA system would be out of service for any appreciable
amount of time.
A SCADA system outage could result in a loss of leak detection
system sensitivity. An outage which does not affect the entire SCADA system
can occur, for example, with the loss of data from a remote terminal unit
(RTU) at a pump station for more than three minutes, in which case an alarm
sounds in the Control Center to alert the controller.
Under such
circumstances, the system uses backup land line communications links to
reestablish communications. However, the leak detection system is able to
maintain its detection capability by modeling across the point of data loss. A
loss of SCADA communications that affected the entire system, for example
because of
a computer malfunction, would immediately be known to the
controller. If the SCADA system experiences any outage that results in a total
loss of leak detection capability for all or any portion of the pipeline for a
period in excess of 5 minutes, then the controller will take action to achieve
system shutdown within 30 minutes. In the event that the SCADA system
experiences an outage that does not result in a loss of leak detection
capability, but instead results in a diminished capability of the system to
detect a leak, then the controller will take action to achieve system shutdown
within 30 minutes if the capability of the system to detect leaks is diminished
99144ba2.v8
34

<<<PAGE 574>>>

to a level that would prevent Longhorn from meeting its "Leak Detection
Performance Commitment" set out below.
Further Enhancement:
In addition to the computational based leak detection system,
Longhorn has committed to employ additional technology to provide for more
Stringent leak detection across the environmentally sensitive Edwards Aquifer
Recharge Zone and the Slaughter Creek watershed in the Edwards Aquifer
Contributing Zone (the "Enhanced Leak Detection System"). In order to
achieve this capability, Longhorn plans to employ a hydrocarbon sensing leak
detection cable system that has clearly demonstrated the leak detection
capability to satisfy Longhorn's commitment contained within Mitigation
Commitment 13.
This system is designed to detect a leak as small as 0.0030467 barrel
per hour in twelve (12) to one hundred twenty (120) minutes from contact with
the leak detection cable, depending upon the product sensed by the system.
Several factors will make it probable that any released product will come into
contact with the leak detection cable within a minimum amount of time,
including the following: (a) the construction methods that Longhorn will
employ over the recharge and contributing zones during replacement of this
segment of pipe, including protection of all identified subsurface voids; and
(b) backfill materials used within the trench (primarily fine materials to provide
padding to the pipe and otherwise relatively porous media), coupled with the
primarily limestone geology of the Edwards outcrop and the fact of the in-
trench materials having been disturbed will cause any released product to
accumulate within the trench where the leak detection cable will be located.
Longhorn has committed to having this system in place prior to start-up of the
pipeline.
The hydrocarbon sensing leak detection system is based upon the
TraceTek hydrocarbon sensing cable manufactured by Raychem HTS.
Longhorn's ultimate choice of the TraceTek cable was made after Longhorn,
Williams and UTSI International Corporation performed exhaustive research
of leak detection technology potentially feasible for this particular application.
After detailed analysis of potentially feasible leak detection technologies, and
consultation with the Office of Pipeline Safety, the TraceTek cable was
identified as the current best available, proven technology in the industry.
The table below identifies the sensing capabilities of the TraceTek system.
Leak Detection Response:
With notification typically originating through the utilization of its
External Patrol and Technology Based components of its Leak Detection
System Capabilities,
Longhorn Pipeline will facilitate
the orderly and
controlled shutdown of its system within five (5) minutes of a probable leak
indication.
99144ba2.v8
35

<<<PAGE 575>>>

Longhorn maintains 24-hour surveillance of its pump stations,
motorized valve locations (MOV), terminals (pipe, pumps, valves, meters, and
tanks), and meter stations through its SCADA system.
(Truck loading
operations at the El Paso Terminal are monitored locally.) Twenty-four-hour
surveillance will also be maintained with respect to Longhorn's Enhanced
Leak Detection System. Pipeline operational data from these locations is
transmitted directly to the Tulsa Operations Control Center, where trained and
qualified Operations Control personnel monitor and provide equipment control
commands to the Longhorn system.
Operations Control personnel utilize the following methods for the
determination or suspicion of a probable leak indication:
•
Deviation outside normal operational thresholds from the
computational based transient leak detection software system in
a direction that is indicative of a leak;
•
Receipt of an alarm by the sensor cable system over the
Edwards Aquifer Recharge Zone;
Unexpected deviation outside minimum or maximum alarm
thresholds for system pressures and flow rates;
Rate of Change alarms that compare pressure or flow value
change versus time;
Operations Control personnel independent analysis of flowing
conditions;
•
Third party call of suspected or confirmed product leak;
•
Input from Field Operations Personnel;
Automatic closure of MOV's or stoppage of pipeline pumps; and
• Terminal high level alarms.
Analysis of a suspected pipeline leak is accompanied by an
identification of the location of the suspected leak.
Upon the detection, notification, and determination of a probable leak
indication, Operations Control personnel are trained to immediately shut down
the pump station(s) upstream to the leak location. The pump station
downstream to the leak location is either kept running or is started to assist
with the orderly movement of product away from the leak location. Following
the shut down of the upstream pump(s), the Operations Control personnel will
close the upstream MOV's from the leak location to prevent the introduction of
new product to the segment. Through the use of the SCADA system,
upstream pump stoppage and MOV closure are accomplished within five (5)
minutes from the identification of a probable leak indication.
The Longhorn Pipeline was designed to be shut down immediately
following a probable leak indication. Communication with field operations,
product origination or destination points and terminals are not required to shut
down the pipeline in an orderly or safe fashion. Operations Control personnel
are trained to notify the appropriate supply, destination, field operations, and
99144ba2.v8
36

<<<PAGE 576>>>

emergency responder personnel as soon as practical following the shut down
and isolation of the pipeline.
The above emergency shut down procedures will be documented and
tested for Operations Control personnel training certification prior to start-up
of the Longhorn Pipeline system.
The Longhorn pump stations utilize a Programmable Logic Controller
(PLC) to handle the start-up, sequencing, data transmittal, and shut down of
the equipment within the station. The Tulsa Operations Control Center sends
command signals to and receives operational data from the PLC's at each
pump station. The PLC's, coupled with the instrumentation contained at each
pump station, serve to protect the pump equipment from mechanical
disturbances such as vibration, abnormal motor winding or pump bearing
temperatures, loss of product through seal leaks, and fire sources. Internally,
the pump equipment is protected from conditions of high product flow, low
product flow, low system pressure, high system pressure, and excessive or
low motor amperage.
The PLC is programmed to provide both early
indication alarm and automatic pump shutdown in the event that designated
parameters are operated outside their intended range.
Pressure, flow, and tank level readings from across the pipeline
system are transmitted to the Tulsa Control Center via the SCADA system for
computational transient modeling
analysis and Operations Controller
interpretation of the physical data, as is the data generated by the Enhanced
Leak Detection System. The status of the sensor cable system over the
Edwards Aquifer Recharge Zone also is transmitted to the Tulsa Control
Center. Outside of the automatic shut down of pump units that are controlled
by the local pump station PLC's, shut down of equipment and isolation of
MOV's are originated by the Operations Controller.
Leak Detection Performance Commitment:
Longhorn is committed to implementing the best available leak detection
systems with the following design specifications:
SYSTEM DESIGN
LOCATION
SPECIFICATIONS
Tier I
1% of flow detected within one-half hour.
Tier lI
1% or more of flow detected within one-half hour.
Tier III
0.5% - 1% of flow detected within one hour.
Same as Tier II, except Edwards Aquifer recharge zone an
ontributing zone (Slaughter Creek watershed
Edwards Aquifer
barrel/hour from contact for the following products
Same as Tier Il, and sensor-based detection of 0.0030467
• Gasoline - 12 minutes
watershed)
: Diesel Fuel - 60 to 120 minutes
Jet Fuel - 50 to 70 minutes
99144ba2.v8
37

<<<PAGE 577>>>

The leak detection equipment will be installed prior to startup. The
computational based system will be adjusted to become operational over
approximately the first two weeks of pipeline operation and be further optimized
within 6 months of startup. The sensor-based system will be fully operational, at full
sensitivity, immediately upon startup. Leak detection capabilities will be
demonstrated and periodically tested."
UTSI International is Longhorn's third party leak detection consulting firm. Correspondence
describing leak detection system development and design is included in the Phase Two
Project Documentation Appendix at Tab 11, as are qualifications of the UTSI personnel
directly involved in system development and design. System shutdown is achievable
without field communications due to the fact that the SCADA system gives remote control
of all relevant system components to the pipeline control center in Tulsa.
The leak detection system software will not be inoperable during the fine-tuning period;
rather, it will be adjusted to its operating status over approximately the first two weeks, and
further optimized over as much as six months from startup. The sensor-based system over
the Edwards Aquifer recharge zone and Slaughter Creek watershed in the contributing
zone will be fully operational, at its full sensitivity, immediately upon system startup.
Emergency Response Preparation - Emergency Response Plan
The Williams System of Manuals contains an Emergency Response Plan volume, a copy of
which is included in the Phase Two Project Documentation Appendix at Tab 12. The
Emergency Response Plan provides direction to the employee first aware of an emergency
situation, including emergencies that involve a release of a transported commodity. The
priority for protection in the event of an emergency is appropriate: (1) human health and
safety; (2) the environment; and (3) property. Among the first duties of the first aware/first
responder role is to activate the applicable facility response plan (FRP; aka OPA '90 Plan).
A copy of the most recent draft of the Longhorn FRP (March 24, 2000) is hereby provided
as a separate Appendix; as development is completed, the final FRP will be provided to the
Service.
Oil Pollution Act of 1990 Facility Response Plan
Longhorn developed and distributed an FRP in 1998 and submitted same to DOT for
review and comment. The Settlement Stipulation that arose out of the NEPA lawsuit,
however, contained DOT's agreement that it would not approve, or allow Longhorn to
commence operations under, the FRP until the conclusion of the EA process. The FRP
was scrutinized during the
EA, and Longhorn committed to develop numerous
enhancements to the FRP as listed in this Phase Two BA at Section 3.4. The Service also
provided comments to enhance response capability over the EARZ/EACZ.
The FRP enhancements will serve to protect the environment as a whole, and listed
species and habitat in particular, as well as human health and safety. The LMP contains a
number of commitments to enhance the FRP, and those enhancements have been
developed and implemented to the extent possible:
99144ba2.v8
38

<<<PAGE 578>>>

•
Ensure maximum 2-hour full response to EA designated sensitive areas and
maximum 1 to 2 hours in hypersensitive areas (LMC 23)
Establish a response center in South Austin (LMC 23)
•
Enhanced facility response plan will:
-
Address firefighting in areas without Hazardous Materials response units
(LMC 24)
-
Provide detailed planning for areas with high populations of potentially
sensitive receptors (LMC 26)
-
Establish consistency with
the City of Austin Barton Springs Oil Spill
Response Plan and the Service's Barton Springs Salamander Recovery Plan
(LMC 28; these enhancements depend upon promulgation by the City of
Austin and the Service of their respective plans, neither of which has occurred
at this writing)
The EA took into account listed species and potential habitat when identifying areas to
designate as sensitive and hypersensitive (see Section 3.1, above). Thus, the FRP
benefits that are directed to sensitive and hypersensitive areas also are directed
at species
and habitat; see EA at Section 9.2.3 and Appendix 9C.
The development of a new
response center, to be located in south Austin, will limit the elapsed time between
notification of response personnel and implementation of a full response at any release
site. Longhorn will stage personnel and equipment to achieve a full response in sensitive
areas in less than two hours, and in one to two hours in hypersensitive areas. A response
time of 1 hour will prevail for the Edwards Aquifer recharge zone and Slaughter Creek
watershed in the contributing zone. A maximum 1 to 2 hour response time will apply in the
Barton Creek watershed in the contributing zone. More detailed, site-specific planning and
preparation will enable more rapid and more effective deployment on-site. Sensitive and
hypersensitive areas are interspersed along the pipeline route, with non-designated areas
between; therefore, segments between sensitive and hypersensitive areas benefit from
much the same treatment by virtue of proximity (See Longhorn FRP at Volumes II and III,
Sections 4 and 5). Stated another way, a Tier I area located near a Tier II or Tier III area,
or located between two areas of either Tier Il or Tier Ill status, will by definition be within the
reach of response crews within the same time periods stated above for sensitive (Tier II)
and hypersensitive (Tier III) areas.
Emergency Response Activities
The following paragraphs describe generally the sequence and character of activities that
occur at a pipeline release location. Each potential release would likely involve unique
circumstances, and, among other factors (see APR Companies, Phase Two Project
Documentation Appendix at Tab 10), the on-site response will vary with location, terrain,
weather conditions, product released, and release volume. The area of disturbance
caused by a response action varies depending upon the character of the response and by
nature of the release. The following description identifies the majority of typical response
activities.
The first responder(s) will immediately notify Longhorn Operations Control and the Area
Manager. They will take appropriate action to protect life and ensure safety of personnel.
They will additionally request Operations Control to notify the appropriate emergency
responders. Operations Control will coordinate company response activities until company
99144ba2.v8
39

<<<PAGE 579>>>

personnel arrive on scene.
When a leak is detected, Operations Control will shut down the pipeline following
procedures in the Operations Control Manual. Remote operated valves upstream of the
release will be closed and downstream valves may be closed or left open to allow drainup,
depending on conditions. The Longhorn First Responder assumes the role of Longhorn
Incident Commander (IC) until relieved. The Longhorn IC will work in cooperation with the
local emergency responders (reference Longhorn Emergency Response Plan from the
System of Operating Manuals).
Responders will conduct a preliminary assessment of the situation including potential health
and safety hazards. If someone is injured or if there is the potential for a fire or explosion,
emergency services will be called out. Assistance from public agencies for site control and
evacuations will be requested if necessary. Proper monitoring will be conducted to ensure
public and personnel safety, and that the necessary spill response contractors have been
mobilized to assist in containment and cleanup operations. Response contractors are
currently identified in the FRP Volume I, Section 8 and within each county-level response
zone plan (Volumes II and III). All or a portion of additional resources will be activated, as
necessary. For a major release, all resources may be activated. Appropriate regulatory
agencies will be notified.
Potentially affected sensitive areas will be identified. The designated Tier II and Tier I!
areas are identified on the strip maps in FRP Volumes || & III, Section 4. Additional
information on the Wildlife Sensitive Areas is located in Section 5 of Volumes || & III. The
topographic maps also locate sensitive features along and down gradient from the pipeline.
Any response activities will involve measures to protect the sensitive areas.
If there is the
potential to affect the Wildlife Sensitive Areas, the biological contractor will be included as
part of the response team.
A request for assistance to have potential ignition sources in the vicinity of the spill,
including motors, electrical pumps, electrical power, etc. shut down will be made. Local fire
departments and/or Boots & Coots, Eagle Environmental, or other release response
contractors will be notified if the use of fire suppressants is required. Longhorn responders
will shut down and control the source of the spill. This may include closing additional
valves, collection of pooled product at the pipeline location, digging out the pipeline,
collection of product from the pipeline and the pipeline ditch, and repair of the pipeline.
Longhorn responders will stabilize and contain the situation in coordination with appropriate
agencies. This may include berming, the deployment of containment and/or sorbent
booms, construction of dams, or trenching in a manner that limits the spread of the product.
The tactic used is dependent upon many factors including the location, the volume, type of
sensitive areas, weather, and similar factors. General response tactics are discussed in
the FRP at Volume I, Section 3. Site-specific tactical plans for selected sensitive areas are
located in Section 4 of Volumes II and III. Access points and possible response strategies
are identified in the tactical plans. The pre-identified access points were chosen on the
basis of calculations of worst case transport times, proximity to existing roads and other
access, and suitability for use. Within the Edwards Aquifer recharge and contributing
zones, multiple response locations with associated tactical plans have been identified along
the Barton, Slaughter and Williamson Creek watersheds in the event a release were to
99144ba2.v8
40

<<<PAGE 580>>>

reach a stream or tributary and potentially be transported toward the recharge zone. (see
LBG-Guyton, "Travel Times for Hypothetical Releases from Longhorn Pipeline within the
Pipeline Replacement Corridor in Austin, Texas," 2000 in the Project Documentation
Appendix). Additional access points may be utilized during an actual response. If indicated,
wildlife protection measures will be initiated.
Product recovery and removal operations will be initiated. This may include recovery of
free product from ground surface, water or trenches using vacuum trucks, skimmers or
sorbents. Excavation of contaminated soil may be utilized. In situ methods such as
biological treatment or controlled burns may be considered. Any technique used will
attempt to minimize disturbance to the environment. Additional information on recovery
techniques is located in Volume I, Section 3 of the FRP. All necessary approvals must be
obtained from applicable resource trustees.
Documentation procedures will be initiated. Documentation of all response actions taken,
including notifications, agency and media meetings, equipment and personnel mobilization
and deployment, and area impacted will be made. Spill tracking and surveillance
operations will be initiated. The extent of pollution may be determined via surveillance
aircraft. In the event of subsurface impacts, cave monitoring or water well monitoring may
be utilized. Photographers and/or videographers will be utilized.
The equipment and personnel required for a response are dependent on the specific
release situations. The volume, location, and the unique site characteristics will affect the
necessary resources. Some of the equipment such as transport vehicles, temporary
storage or tank trucks may be located at a staging area rather than at an active work site.
Site-specific resources are identified in the tactical plans within the FRP.
In general the major resources that may be utilized at the pipeline release response
location may include:
Vacuum Trucks (one or more at each recovery site depending on leak volume);
:
Trackhoe or backhoe for pipeline dig out;
Dirt moving equipment may include an additional backhoe or bulldozer and dump
trucks for containment and recovery operations;
Spill response trailer;
Sorbent Material;
•
Tanker Trucks and/or temporary storage;
•
Welder's Truck (for pipeline repair);
•
Boom Truck (for pipeline repair);
Miscellaneous transport vehicles;
Roll offs or drums for contaminated debris; and
•
Fire suppressant material if necessary.
Species Habitat Areas
Longhorn has implemented additional levels of planning and preparedness in the FRP
99144ba2.v8
41

<<<PAGE 581>>>

since September 1999. Human health and safety must take precedence during the
execution of an emergency response. If a release occurs within habitat, or at any location
where the release could adversely affect species or habitat, Longhorn will employ additional
measures to avoid any potential adverse effects to species or habitat. To do so, Longhorn
has incorporated into the FRP maps depicting areas of potential habitat both adjacent to
the pipeline and along pipeline sections from which a release could adversely affect
species or habitat. Longhorn also has identified numerous pre-planned containment and
recovery locations throughout the Edwards Aquifer recharge zone and the contributing
zone. Further, Longhorn has included in its FRP training regimen for emergency response
personnel the information necessary to identify such areas and prioritize response activities
toward such areas. Habitat areas along the pipeline have been mapped, and the maps
have been incorporated into the FRP along with descriptions of response actions that apply
in those areas (See Longhorn FRP at Volumes Il and III, Sections 4 and 5).
In addition, Longhorn will immediately engage a qualified biologist on-site to provide
direction to response personnel if a release location is near an area of potential habitat.
Personnel will be directed to avoid indirect effects such as traversing habitat areas to gain
site access.
They also will employ site and circumstance-specific measures to protect
species and habitat threatened by a release and thereby avoid adverse effects; for
example, were a release to ignite in Bastrop County, fire-fighting efforts would identify and
give heightened protection to habitat areas near the fire (see Buescher State Park Fire
Response Resources, in the Project Documentation Appendix).
Longhorn acknowledges the value of Service expertise in protecting species and habitat.
As such, Longhorn solicits Service participation in emergency response planning and
preparedness training with respect to species and habitat protection. Longhorn invites
Service participation in response training at response drills and table-top exercises.
Longhorn shall notify the Service of such training exercises, provide the Service an
opportunity to review and comment upon preparation for the training, and invite Service
participation during such training.
3.5
Edwards Aquifer Protections
The Edwards Aquifer in Travis and Hays Counties is a valued resource. In addition, the
Barton Springs Salamander, which resides in several spring outlets of the Edwards Aquifer,
is an endangered species that must be protected. Longhorn will implement a multitude of
measures both to ensure that the quality and integrity of the aquifer is preserved, and to
ensure the continued survival of the salamander. See document entitled Edwards Aquifer_
Protections, in the Project Documentation Appendix, which summarizes the various
protections.
Longhorn will implement conservation measures to avoid the possibility of impacts to the
aquifer that could result from a pipeline release over the recharge zone or upon the
contributing zone, should ever one occur. However, the Service has requested an analysis
of the potential effects if released product were to enter the aquifer.
Longhorn will implement a number of pipeline enhancements, including (a) replacement of
the pipe over the recharge zone and the contributing zone with new thicker-walled pipe; (b)
additionally protecting the new pipe with a reinforced concrete barrier; (c) installation of an
99144ba2.v8
42

<<<PAGE 582>>>

enhanced, sensor-based leak detection system through the recharge zone and the
Slaughter Creek watershed in the contributing zone; (d) installation of additional check
valves; and (e) daily inspections of the ROW (See Section 3.5.2). An extremely sensitive,
sensor-based leak detection system will complement a computational-based leak detection
system; jointly the systems will be capable of rapidly identifying potential small and large
leaks. Daily patrols will identify potential threats to the pipeline, and enhanced emergency
response capability will provide for rapid and effective release response.
Longhorn has commissioned thorough analyses of the Edwards Aquifer recharge zone and
contributing zone by experienced hydrogeologists, geologists, and biologists (See resumes
of Sherrod, Kreitler, Russo, Stein, Miller, Dorsey and Gasch, Phase Two Project
Documentation Appendix at Tab 13). The subsurface along the pipeline traverse of the
recharge zone has been studied by ground-penetrating radar, and subsequent
investigations demonstrated the absence of significant voids along the pipeline (See LBG-
Guyton letter to Vince Murchison dated 10 December, 1999, Phase Two Project
Documentation Appendix at Tab 14). The related topography has been mapped, and
surface drainage tendencies have been modeled. Local infrastructure has been surveyed
and analyzed to determine the potential implications to infrastructure components in the
unlikely event of a pipeline release; for example, roadways would interrupt the flow of a
hypothetical release that resulted in surface flow. Storm water detention ponds in and
around Austin receive detailed response planning.
Analysis of areas along the pipeline traverse of the recharge and contributing zones has
identified locations where the capacity of the pipeline trench to retain fluid could be
exceeded. Longhorn first will backfill the trench with fill that has been sized to result in high
porosity, which will have the effect of increasing the capacity of the trench to retain fluid if
any is released from the pipeline. At an estimated 18 locations at lower elevations,
however, the capacity of the trench could be exceeded if worst case discharge volumes are
used with the assumption of complete pipe drainage. At those locations, Longhorn will
install a berm containment system that has been designed both to contain any product that
may reach the surface and to prevent storm water accumulations that could compromise
the capacity of the containment systems. Those containment systems are described in the
analysis entitled "EARZ/EACZ Pipeline Replacement Trench and Berm Product
Containment Conceptual Design," "Response to Lead Agency Review of Conceptual
Design for Trench and Berm Product Containment for the EARZ/EACZ Longhorn Pipeline
Replacement," and "Response to USFWS' draft letter of 8/26/00," all of which are included
in the Project Documentation Appendix. Included with the conceptual design are diagrams
of the containment systems.
The containment systems will be constructed with
hydrocarbon-sensing valves that allow the passage of storm water but automatically close,
without human intervention, if hydrocarbons contact the valve.
Another preventive conservation measure Longhorn will employ is the installation of check
valves over the Edwards Aquifer recharge zone and over the contributing zone. The check
valves will be located in a manner that reduces potential volumes that could drain from the
pipeline in the event of a breach.
Check valves are one-way valves that allow product within the pipeline to flow in the
intended direction, i.e., downstream in the pipeline. However, check valves prevent flow in
99144ba2.v8
43

<<<PAGE 583>>>

the opposite direction, upstream, such that if for any reason product attempts to flow
backward, the valve closes to preclude flow in the upstream direction. A hypothetical
example illustrates the function of a check valve. If one assumes a pipeline breach on an
incline such that the pipeline flow is uphill, the contents of the pipeline could drain out of the
breach due to the forces of gravity. If one then assumes that a check valve was installed
along that incline (downstream on the pipeline), then the check valve would stop the
backward, downhill flow of the product from the pipeline, effectively reducing the volume of
product that could drain from the breach (gravity is not the only force to be factored into the
potential for draindown, as discussed below).
The check valves that Longhorn will install will be located to achieve just such effect. The
valve over the recharge zone will be placed at approximately milepost 171.5, near the
pipeline intersection with Whiteworth Loop in the Sendera Glen subdivision, which is
downhill of a gradual rise in the land surtace to the west. By being located near a low point
of the pipeline traverse of the recharge zone, the check valve will prevent the potential for
draindown of product from the check valve to a point approximating the western edge of the
recharge zone.
The valve over the contributing zone will be located at the existing
Edwards Aquifer West Valve, approximately milepost 175.5, about 2.1 miles east of U.S.
290 and about 1.8 miles west of the boundary of the recharge zone. Again, this valve is
located below a moderate incline to the west and will reduce the potential draindown
volume of a release between the two check valves. See APR report, Phase Two Project
Documentation Appendix at Tab 10.
Concerns have been raised by various parties, Longhorn opponents included, to the effect
that a breach in a pipeline allows all product in the pipeline between adjacent block valves
to drain out, but such is not the case. The California State Fire Marshall's office has
analyzed pipeline release volumes to determine the extent to which various components of
release volume contribute to total release volume (see Phase Two Project Documentation
Appendix at Tab 15). The analysis determined that draindown contributes only marginal
volumes to a release. Of the releases studied, in only 25% of the cases did the total
release volume exceed 4.5% of the potential draindown of the pipeline, while in just 10% of
the cases did the total release volume exceed 28% of the potential draindown. Among the
reasons for low draindown volumes is that for product to flow out of the pipeline, it must first
be displaced by air, similar to the manner in which water flows from a bottle that is turned
upside down. See APR Companies, Phase Two Project Documentation Appendix at Tab
10. Longhorn has calculated full line draindown for hypothetical releases to the east of the
recharge zone check valve described above; that volume is 3,875 barrels (162,750
gallons). However, if one applies the lessons of the California State Fire Marshall risk
assessment that volume is more realistically calculated as 1,147 barrels (48,174 gallons) at
28% draindown and 841 barrels (35,322 gallons) at 4.5% draindown. Despite the findings
of the California State Fire Marshall risk assessment, Longhorn has designed the bermed
areas described above using the assumption that all product escapes from the pipeline
segment affected by a release.
Using those more realistic assumptions, the potential threat to the Barton Springs
Salamander from a pipeline release in such areas is lower than previously understood.
Calculations of the effect of a release over the aquifer recharge zone performed by LBG-
Guyton (see Phase Two Project Documentation Appendix at Tab 16) demonstrate that the
potential for adverse effects to the salamander is greatly reduced. See Section 4.4 of this
99144ba2.v8
44

<<<PAGE 584>>>

BA and LBG-Guyton, Phase Two Project Documentation Appendix at Tab 16.
Nonetheless, Longhorn's conservation and mitigation measures will make it unlikely that
adverse effects to the aquifer will occur.
3.6
Pipeline Maintenance Construction
This section identifies
and describes incremental pipeline maintenance construction
activities, in addition to those that were the subject of the Phase One BA, that will be
implemented in two specific areas: (a) within Houston toad habitat in Bastrop County; and
(b) across and adjacent to the Edwards Aquifer recharge zone within Austin. Additional
maintenance construction will include planned, but unscheduled construction and future
additional, but currently unforeseen construction. Maintenance construction that occurs
outside the two presently identified areas will be subject to the maintenance construction
procedures described in the Phase One BA, as will maintenance construction in Houston
toad
habitat and the Edwards Aquifer recharge zone; however, this BA contains
descriptions of additional conservation measures that Longhorn will implement during the
maintenance construction activities over the Edwards Aquifer recharge zone.
The maintenance construction procedures referred to herein, and presented in detail in the
Phase One BA, are identified below:
1.
Pipeline Maintenance -- Construction Planning
2
Project Environmental Inspectors
3.
Site Preparation
4.
Site Entry
5.
Pipeline Lowering and/or Replacement - Open Terrain
6.
Pipeline Lowering and/or Replacement - Creek Crossing
3.6.1 Buescher State Park
Maintenance construction
activities planned within Buescher State Park (containing
Houston toad habitat) result both from the EA process and from Longhorn commitments to
reduce risks to species and habitat. The EA related project is the replacement of 671 feet
of pipe at mile post 127.94 (Hunt Branch) within Buescher State Park in Bastrop County,
Texas. Longhorn committed in the LMP (LMC 34) to replace the pipe since data on file at
the time indicated that the segment contains several shorter sections of Grade B pipe.
Longhorn has since identified file documentation that demonstrates that the existing pipe is
adequate for the design pressure; however, Longhorn remains willing to replace the pipe to
limit the potential for surge pressure-related damage and thus lower the risk of a release in
this habitat area. Two additional tasks have been identified to reduce the risk of a release
in Houston toad habitat: (a) lowering and replacement of the pipeline crossing of Dry
Branch in Buescher State Park (pipeline mile post 128.33); and (b) lowering and
replacement of the pipeline crossing of an unnamed creek approximately 1360 feet east of
the 671-foot replacement (pipeline mile post 127.72).
See additional engineering
information at Tab 17 of the Phase Two Project Documentation Appendix.
The three projects significantly reduce the potential for damage to the pipe in and near the
three creeks. Since land development does not occur within the state park, and taking into
99144ba2.v8
45

<<<PAGE 585>>>

account the pervasiveness and effect of the EA mitigation measures that focus on
identifying and preventing corrosion, on eliminating material defects, and on preventing
adverse consequences resulting from operator error, the greatest threat to the pipeline is
outside force damage within the creek beds. For a complete discussion of the risk
reduction realized by the creek crossing replacements, see APR Report (Phase Two
Project Documentation Appendix at Tab 10). Further, the replacements will limit the
potential volume of a release, should one occur, since the thicker and higher-grade new
pipe will be least likely to suffer a breach, by serving as low-point catchments for product
within the pipe that could escape if a release occurred at lower elevations.
The new creek crossing replacement pipe will have 0.375" wall thickness and be of
American Petroleum Institute Grade X56 or better. The burial depth of the pipe will be
determined on the basis of regulatory requirements (49 C.F.R. § 195.248) and site
conditions such as type of stream bed material and basin and channel configuration; the
pipe will be buried below a depth that would allow in-stream forces to pose a threat to
pipeline integrity.
3.6.2 Edwards Aquifer Protections
During informal consultation on the Longhorn Pipeline Project, the Service voiced concerns
about the pipeline crossing of the Edwards Aquifer recharge zone and the potential for
adverse effects to the Barton Springs Salamander. Adverse effects to the salamander may
be associated with water quality degradation within the aquifer (See Barton Springs
salamander listing final rule at Tab 18 of the Phase Two Project Documentation Appendix).
Typically, water quality degradation originates at the aquifer recharge and contributing
zones and is largely associated with residential and commercial development and the
creation of impervious cover. In addition, commercial and industrial operations and
vehicular roadway traffic create the potential both for chronic water quality degradation as a
result of ongoing activities and for acute water quality degradation in the event of a release
of deleterious materials to the watershed.
System operation and ongoing, long-term maintenance of the pipeline are not likely to
result in adverse effects to the salamander, for which critical habitat has not been
designated. ROW maintenance, pipeline inspection, valve maintenance, and similar such
activities are unlikely to result in adverse effects to the salamander inasmuch as the
activities are implemented in a manner that does not affect aquifer water quality.
Longhorn responded to the Service's concerns about water quality by identifying measures
that will not only reduce the potential for a pipeline release, but will protect water quality
and promote public efforts to ensure the survival of the species in the unlikely event of a
release that threatened the Barton Springs segment of the Edwards Aquifer. Longhorn
committed to implement the following measures and included the measures in its
Environmental Assessment mitigation commitments:
Replacement of over 3 miles of pipe over (and east of) the recharge zone and 15
miles of pipe over the full extent of the contributing zone with new, thicker walled
pipe (LMC 3).
•
99144ba2.v8
Installation of an enhanced, sensor-based leak detection system across the aquifer
46

<<<PAGE 586>>>

recharge zone and the Slaughter Creek watershed in the contributing zone to
complement the pipeline-system-wide computational-based leak detection system
(LMC 13).
Installation of check valves (one in the recharge zone and one in the contributing
zone) to minimize the volume of a potential release should one occur (see Section
3.3, Edwards Aquifer Protection).
Performance of daily pipeline surveillance patrols over the recharge zone (LMC 20).
Establishment of a refugium and captive breeding program for the Barton Springs
Salamander as a conservation measure to ensure the survival of the species in the
event of any perturbation to the extant population (LMC 33).
Further in response to concerns voiced by the Service, and concerns voiced also by the
Barton Springs/Edward Aquifer Conservation District, Longhorn will implement an additional
measure to reduce the risk of a release that could adversely affect water quality. Longhorn
commits to install a protective concrete barrier over the 5-foot-deep replacement pipe. The
barrier will be engineered with reinforced concrete to provide a protective covering over the
pipeline that will alert an errant excavator to the presence of the pipeline. The concrete will
be colored red to ensure ready notice of the presence of a protected structure. The
protection offered by the concrete barrier will provide further reduction of a threat to the
pipeline, third party damage, in the developing areas of south Austin, southwestern Travis
County, and northeastern Hays County (See additional information at Tab 19 of the Phase
Two Project Documentation Appendix).
Analysis of the pipeline traverse of the recharge and contributing zones has identified areas
where surface flow modeling indicates a tendency for surface flow toward known karst
features or toward Slaughter Creek, Barton Creek or Williamson Creek (see LBG-Guyton,
Phase Two Project Documentation Appendix at Tab 16 and associated figure). Those
areas include (a) from the fire station west of Brodie Lane to Deer Lane, toward the Karst
Preserve; (b) from the pipeline crossing of Deer Lane to a point just east of the Sendera
Creek. LBG-Guyton has recommended that measures be employed to divert surface flow
from those features, with the result that in the event of a release that results in surface flow,
the features and thus the Edwards Aquifer will not be subject to the potential for rapid
infiltration to the aquifer; see LBG-Guyton, Phase Two Project Documentation Appendix at
Tab 16.
Longhorn commits to employ such measures. Given the relatively low slope of surface
topography across the recharge zone, slight modifications during final surface grading will
accomplish the goal of protecting the sensitive features. Thus, planning for construction of
the replacement pipe will include the requirement that, during final grading, a low swale or
berm be created to protect those features. The precise location and design of these
surface flow control features are not easily predictable in advance of construction; thus,
Longhorn's geological, biological, and engineering consultants (LBG-Guyton, Horizon ESI,
Paragon Engineering, Bury + Partners) will make field recommendations to the contractor
as reclamation begins. These recommendations will be carried out by the Contractor at the
47

<<<PAGE 587>>>

direction of the on-site Environmental Inspector. Since the Longhorn Pipeline primarily
traverses the surface divide between the Williamson and Slaughter Creek drainage areas,
little if any surface flow of storm water will be affected, and no adverse effect to aquifer
recharge water quantity will occur.
Additional analysis has been performed with respect to the recharge and contributing
zones.
Surface flow modeling has identified surface flow tendencies along the pipeline,
and the calculations have been made of time of travel, to the recharge zone or recharge
features, of a hypothetical release under worst case stream flow conditions. See Drawing
199044-C2 and LBG-Guyton, "Travel Times for Hypothetical Releases from Longhorn
Pipeline within the pipeline Replacement Corridor in Austin, Texas," 2000 in the Project
Documentation Appendix. Longhorn has based its emergency response planning on the
results of those analyses, resulting in the multiple pre-planned response locations identified
in the Travis County and Hays/Blanco sections of the FRP. Multiple pre-planned response
locations enable response personnel to identify the optimum response locations for a
release along any segment of the recharge and contributing zones.
Longhorn also has identified locations across the recharge and contributing zones at which
a release of product could fill the trench and reach the surface. At those locations,
Longhorn will construct a bermed area that achieves two competing goals: (1) providing
containment in the unlikely event of a release that reaches the surface; and (2) preventing
the infiltration of storm water to the areas (which could otherwise compromise containment
capacity). The areas will be constructed of berms and swales along and/or across the
pipeline right-of-way. Storm water will be prevented from entering the bermed areas by the
placement of diversion berms. The presently identified locations of potential surface
presence of product, and the conceptual design of the bermed areas, is set forth in the
"Longhorn Pipeline EARZ/EACZ
Pipeline Replacement Trench and Berm Product Containment Conceptual Design" in the
Project Documentation Appendix (note that locations #1 and #20 are outside the applicable
replacement segment).
Longhorn will execute replacement of the pipe section that crosses the recharge zone
pursuant to a maintenance construction plan that does not include the segment across the
contributing zone (See Tabs 20 and 44 of the Phase Two Project Documentation
Appendix). Pipe replacement across the contributing zone shall be executed pursuant to
typical project construction plans developed during the Phase One consultation (but
including the sealing of identified karst features in the limestone trench; see additional
details in the following paragraphs).
Longhorn also has committed to replace an additional one-half mile (approximately) of pipe
east of the recharge zone. That area has been identified through surface flow modeling as
susceptible to seeing surface flows toward the recharge zone and Williamson Creek. All
new pipe will be buried to a depth of 5 feet to top of pipe and will be protected by a red
concrete barrier. This segment of the project
will be executed pursuant to project
construction plans containing the same protections as those developed pursuant to Phase
One of this consultation.
99144ba2.v8
48

<<<PAGE 588>>>

The maintenance project will employ numerous measures in excess of the maintenance
construction procedures described in the Phase One BA, identified specifically and by
qualified individuals and entities (See Phase Two Project Documentation Appendix at Tab
13 for resumes of Kreitler, Stein, Sherrod, Bury, and Miller) as protective of the Edwards
Aquifer and thus the salamander. The procedures build upon a solid base of construction
storm water best management practices (BMPs) that are implemented at every
construction site; moreover, Longhorn will implement procedures at least as stringent as
locally prescribed construction BMPs. Longhorn will design its construction project to
employ the construction BMPs promulgated by the Texas Natural Resource Conservation
Commission (TNRCC) for application during construction over the recharge zone.
During pipeline replacement, Longhorn will seal any identified karst features in the
limestone trench or exposed in the ROW following guidelines established by TRCC.
Upon encountering any karst feature during construction, the Contractor and on-site
Environmental Inspector will be required to immediately notify Longhorn's geological,
biological, and engineering consultants (Sherrod, Miller, Kreitler, Stein, Bose, Bury - see
resumes in Phase Two Project Documentation Appendix at Tab 13) who will promptly
inspect the field situation and prescribe proper sealing methods to the contractor.
_In
addition, immediate notice will be made to appropriate representatives of the City of Austin
and the Barton Springs/Edwards Aquifer Conservation District who may also provide
additional recommendations to Longhorn's specialists on proper sealing procedures. If
exceptionally large or deep voids or caverns are encountered, structural engineering
specialists will provide engineered recommendations for supporting the pipeline over the
void closure (example engineered recommendations encountered
20 and 44 of the Phase Two Project Documentation Appendix ). All void closure
recommendations will minimize potential adverse effects to the function of the void (ie.,
recharge capability or faunal habitat) while providing the maximum seal from the pipeline
and any potential releases. Not only does this address potential issues of impacts to
species during construction, but also provides significant aquifer protection and product
recovery benefits in the event of a release during operation. Pipeline releases should stay
within the pipeline trench and at land surface within the ROW where they can be more
easily contained and controlled.
First, the volume of a spill will be limited by the installation of check valves that reduce spill
volume to a probable maximum of 2100 barrels in the recharge zone. Additionally, the
APR report (Tab 10 of the Phase Two Project Documentation Appendix) concludes that
only about 28% of the line fill capacity between block valves might be released in 90% of
the release scenarios. Third, the topography across the recharge zone is relatively flat, and
rapid runoff away from the ROW will not likely occur; see LBG-Guyton Addendum Phase
Two Project Documentation Appendix at Tab 16. It is anticipated that with the flat terrain
and limited spill volume, potential product spills will remain on the ROW of the pipeline
where any caves and other karst features will have already been identified and been sealed
or protected during pipeline replacement.
Longhorn has, however, committed to implement a number of bermed containment areas
at locations where it is possible that product could reach the ground surface, and
accumulate, in the event of a release (see Sec. 3.5). The bermed areas are designed so
that any released product is captured within the trench and is captured if it rises to the
99144ba2.v8
49

<<<PAGE 589>>>

surface. The bermed areas also are designed to prevent storm water infiltration by run-on
and to shed storm water through outlets; however, the systems will collect product in the
event of a release by means of automatic, hydrocarbon sensing valves. These systems will
be designed and built of low-porosity materials but with the integrity to withstand major
storm events. The capacity of the bermed areas will be calculated to contain both a worst
case release (assuming complete pipe segment drainage) and precipitation generated by a
100-year storm event. Periodic inspection of the locations will be performed in conjunction
with regularly scheduled pipeline surveillance patrols.
Longhorn commits to perform a field test of both the trench sealing procedure and the berm
construction methods in conjunction with the maintenance construction project over the
recharge and contributing zones.
If the field test identifies design or construction flaws,
adjustments to design or construction techniques will be employed to achieve the desired
effect. See "Proposal to Perform Field Tests to Verify the Design and Construction of the
Pipeline Trench and Berms for the Longhorn Partners Pipeline over the Edwards Aquifer
Recharge Zone in Austin, Texas," in the Project Documentation Appendix.
As a result of the foregoing measures, the following defenses protect the Edwards Aquifer:
1.
New, thicker pipe; 2. Five foot burial depth;
3.
Concrete barrier;
4.
Enhanced leak detection;
5.
Sealing of all voids, fissures, vugs, and other potential recharge features in the
limestone trench;
6.
Trench backfill absorption enhancement;
Surface containment systems and berms; and
Enhanced response planning.
As described in Section 4.3 below, that risk will be further reduced by implementation of the
Edwards Aquifer Protection Plan during construction.
3.7 Hydrostatic Pressure Testing And Proof Testing
Longhorn committed to perform hydrostatic pressure tests and proof tests of the pipeline,
and those tests have proceeded during 2000. (See Phase One BA at Sec. 4.10 and LMP
Items 1 and 2.) Hydrostatic and proof testing of the pipeline has been ongoing, beginning
at the Longhorn GATX pump station in Galena Park (Houston) and proceeding westward to
Crane Station, but skipping the segments through Houston toad habitat in Bastrop County
and the Edwards Aquifer Recharge Zone in Travis County (refer to Phase One BA in the
Phase Two Project Documentation Appendix at Tab 1).
The hydrostatic and proof testing has occurred in segments, which were subdivided into
test sections of varying lengths. Due to sensitive aquatic species concerns, the Houston
toad and the Barton Springs Salamander, two test sections were not tested during the
overall Houston to Crane testing project. Those two sections are (a) Segment 4, Section 1,
which encompasses habitat for the endangered Houston toad and (b) all of Segment 5,
which encompasses eastern Travis County, the recharge zone of the Edwards Aquifer and
part of the adjacent contributing zone, areas of concern to the endangered Barton Springs
99144ba2.v8
50

<<<PAGE 590>>>

Salamander. Those sections will be hydrostatic pressure tested, after completion of Phase
Two consultation and after pipe replacement takes place, to complete the system integrity
testing.
Procedures for testing will follow those described in the Phase One BA. However, due to
the heightened sensitivity of these two locations, project environmental inspectors and spill
response equipment will be onsite and in constant ready status for immediate response
during the testing. Makeup water for the tests will originate from the Colorado River or from
local sources, and other than the potential for small amounts of residual diesel no
contaminants are foreseen in the test water. Since most of the tested line sections will be
newly installed pipe and since the prior hydrostatic testing will have flushed the pipe that is
not slated for replacement, significant contaminants are not expected to be present in the
test water. New pipe is expected to contain minimal manufacturing residue.
3.8 Right-of-Way Maintenance
ROW maintenance was considered by the Service in Phase One of this consultation with
the exception of one area, the Edwards Aquifer recharge zone; see Phase Two Project
Documentation Appendix at Tabs 1 and 2. ROW maintenance in the recharge zone will be
conducted in the same manner as described in the Phase One BA. In summary, the
conservation measures described in the Phase One BA are designed to prevent
disturbance of the earth, to preclude sedimentation, and to prevent the release or
distribution of herbicides to the environment.
3.9 Corrosion Inhibitor
The LC-50 concentrations of Magnacide 575 in the water column for freshwater fish and
aquatic invertebrates ranges from 19.4 ppm (ml/I) (Daphnia- 48 hr) to 119 ppm (mg/l) (trout -
96 hr). Reproductive capacity diminution in Daphnia was demonstrated to have an EC-50
of 0.154 ppm (ml/l). No-effect concentrations for this product on fish and aquatic
invertebrates was not available. LC-50 concentrations for dermal exposure to terrestrial
mammals (rabbit) is 2000 ppm (mg/kg).
Surface disturbance for the application of the corrosion inhibitor would be restricted to the
seven valve setting sites previously noted. Access to those sites would be from public
roads.
The mixture ratio for the proposed inhibitor in the pipeline is approximately 3500 to 4000
ppm. These concentrations exceed the LC-50 for aquatic organisms, and are also above
the lethal levels for terrestrial organisms. A release of this product in a surface tributary
stream could be toxic until such time as dilution in the water body reduces the toxicity
below limits.
99144ba2.v8
51

<<<PAGE 591>>>

For listed species, the risk is believed to be very minimal. Terrestrial plants such as the
Texas prairie dawn, Navasota ladies-tresses, and Tobusch fishhook cactus have very
minimal exposure risk as spilled product on the ground would either be confined very
quickly to topographically low areas or absorbed into the soil in a short distance from the
pipeline. Surveys conducted for these plant species along the Longhorn ROW (Report of
investigations - in progress) by Horizon in response to the requirements of the LMP did not
reveal the presence of any individuals of these species within or near the ROW.
The Houston toad would also be unlikely to be exposed to a spill if one occurs in Houston
toad habitat areas. During the late summer period when the activity is proposed to occur,
Houston toads are generally in estivation in deep sand burrows in uplands. Exposure to
spilled product would be extremely low probability. Additionally, Houston toad surveys
were conducted along portions of the line passing through the designated critical habitat for
the Houston toad.
No toads where found to occur within or adjacent to the ROW, or
downstream (report in preparation).
The only exposure avenue for the Barton Springs salamander would be entry of a large
volume of the corrosion inhibitor directly into the Edwards Aquifer through a point recharge
feature; however, the risk of a release of the corrosion inhibitor is demonstrably nominal as
discussed in the following paragraphs.
That the risk of a release of the inhibitor is low is based upon the fact that the inhibitor
treatment water will be moved through the pipeline at pressures significantly lower than the
pressure reached during the recently completed hydrostatic tests. The inhibitor will be
propelled by nitrogen injected at a maximum pressure of 285 pounds per square inch
gauge ("psig"). At the point of the inhibitor water batches, the pressure will range from
approximately 65 psig to 140 psig. In comparison, the hydrostatic tests induced pressures
ranging from approximately 1,100 psig to over 1,500 psig. Further, though some segments
were not tested
(22 miles across Buscher State Park in Bastrop County and 40 miles across the Edwards
Aquifer recharge and contributing zones in Travis and Hays Counties), the hydrostatic test
water was moved through those segments, and none was lost.
The following table compares the minimum hydrostatic test pressures to the maximum
treatment pressure.
Corrosion
Ratio
Hydrostatic
Inhibitor
Hydrostatic
Segment/Section'
Minimum(psig)?
Test
Maximum(psig)3
Treatment
Inhibitor
Test to
2(1802+63 - 4024+50)
1265.0
285
4.4
3 (4024+50 - 5964+47)
1113.0
285
3.9
4-1 (5964+47 - 7110+81)
6504
285
2.3
4-2 (7112+16 - 8004+00)
1113.0
285
3.9
99144ba2.v8
52

<<<PAGE 592>>>

Hydrostatic
Corrosion
Inhibitor
Ratio
Segment/Section'
Minimum(psig)?
Test
Treatment
Hydrostatic
Maximum(psig)
Inhibitor
Test to
5 (8004+00 - 10163+00)
500°
285
1.8
6 (10163+00 - 12039+37)
1235.0
285
4.3
7 (12360+00 - 14597+72)
1265.0
285
4.4
8 (14606+00 - 16992+40)
1113.0
285
3.9
1
Segments shown are those with threatened or endangered species or
habitat in proximity to the pipeline.
The pressures shown are test target pressures for segments actually
tested; all target pressures were met during the test.
Nitrogen will be injected at 285 psig and therefore is used as the
maximum; the pressures at the inhibitor batches will be lower, on the order of 65 to
140 psig;
This section was not hydrostatic tested, but experience pressures as
high as 650 psig (nitrogen) while adjacent sections were tested.
This segment was not hydrostatic tested, but experienced pressures
as high as 500 psig (nitrogen) while adjacent segments were tested.
The above data demonstrate that treatment pressures will be significantly lower than
were the hydrostatic test pressures. Since the hydrostatic test pressures were of such
higher magnitude, and since the pipeline has been repaired at the few locations of
hydrostatic test failures, the risk of a release is extremely low. In addition, regular,
ongoing pipeline surveillance is monitoring activity near the pipeline to protect from third
party damage that could threaten pipeline integrity.
Furthermore, Longhorn will take measures to prevent a release of the inhibitor to the
environment. Piping and materials management protocols that will be implemented serve
to ensure that the inhibitor is controlled at all times. Nonetheless, spill equipment and
supplies necessary to contain and immediately remove a release will be maintained along
the pipeline segments as the treatment procedure progresses westward. Finally, a
biologist will be maintained on stand-by during treatment across Bastrop, Travis and Hays
Counties, in the event of a release that could affect the Houston toad or the Barton Springs
salamander, to immediately advise response crews in release response and mitigation.
Therefore, no adverse affects to the Barton Springs salamander would be expected.
Exposure possibilities for the golden-cheeked warbler or black-capped vireo would be
Studies for the presence of the warbler and vireo in the springs of 1999 and 2000 along the
ROW did not reveal the presence of either bird species within or in close proximity to the
ROW (report in progress).
All ground activity associated with this process would be at previously disturbed valve
setting locations, none of which are within or near listed species habitat.
99144ba2.v8
53

<<<PAGE 593>>>

The recently completed hydrostatic testing has proven the Longhorn Pipeline to be sound.
The corrosion inhibitor solution would be pumped through the pipeline at significantly lower
pressures than the hydrotest. Little handling of material is required for the procedure. The
risk of a significant spill or release of the inhibitor material in the environment is extremely
low. Even if released, exposure or toxicity of the solution would not be significant for any of
the listed species.
99144ba2.v8
54

<<<PAGE 594>>>

4.0
AVOIDANCE AND CONSERVATION MEASURES
4.1
Avoidance
Longhorn will conduct pipeline operation, maintenance, construction, testing, and other
subject activities in a manner that avoids potential effects to species and habitat. Controls
and other measures designed to achieve that goal are described in the foregoing
descriptions of the various activities.
A number of those controls and measures are
summarized as follows:
•
Full implementation of the Longhorn Mitigation Plan;
•
Identifying and marking habitat areas for avoidance;
• Planning project implementation to avoid the potential for any effects;
• Using FERC qualified environmental inspectors with authority to alter
project
implementation procedures in areas of potential concern to species, including
application of incremental BMPs as a result of site-specific conditions;
Adjusting project timing to avoid breeding populations; for example, maintenance or
construction projects in Houston toad habitat will avoid the months of January
through June and projects in golden-cheeked warbler and black-capped vireo habitat
areas will be avoided from March 1 through August 1 and March 15 through
September 1, respectively;
Implementing storm water pollution control BMPs even when not required by permit;
Maintaining qualified
biologists in hydrostatic test project areas for immediate
response in the event of a test water release in a habitat area;
Avoiding work in areas of noise-sensitive species (i.e., golden-cheeked warbler and
black-capped vireo) during the breeding/nesting season. If work must occur in
habitat areas during noise-sensitive seasons, the Service will immediately be notified
for additional avoidance procedures.
Longhorn's Monitoring Commitment
Longhorn has committed to survey the existing ROW to determine the presence/absence of
listed species. The following summarizes the Longhorn Monitoring Commitment for each
potentially affected species.
•
Longhorn has completed surveys for the Texas prairie dawn within the potentially
suitable habitat areas to confirm its presence or absence. The surveys were
conducted within the ROW in areas identified as potential habitat in early April of
2000 to determine if the Texas prairie dawn was present, and if so, its distribution
and abundance. No prairie dawn were found, nor was any highly suitable habitat
99144ba2.v8
55

<<<PAGE 595>>>

identified.
Longhorn will conduct a fall survey (15 October to 15 November, 2000) for the
Navasota ladies'- tresses within the ROW if suitable climatic conditions occur to
determine the presence or absence of this species, and if present, its distribution
and abundance.
For the Tobusch fishhook cactus, Longhorn has conducted a blooming period survey
(late February 2000) within the ROW throughout Kimble County to determine the
species' distribution and abundance. No cacti were observed.
• A spring survey for the Houston toad in Buescher Park was conducted along and
downstream of the pipeline to determine the presence or absence of toads and their
overall distribution and abundance. No toads were detected in the park.
•
One to two additional Spring breeding season surveys (as acceptable to the Service)
will be conduced for the golden-cheeked warbler along and adjacent to the ROW
within the potential habitat areas to determine habitat utilization and overall
distribution
and abundance.
A survey for 2000 was conducted with no golden-
cheeked warblers being found in or near the ROW.
•
One to two additional spring breeding season surveys (as acceptable to the Service)
will be conduced for the black-capped vireo along and adjacent to the ROW within
the potential habitat areas to determine habitat utilization and overall distribution and
abundance. A survey for 2000 was conducted with no black-capped vireos being
found in or near the ROW.
4.2
Status of the Species/Environmental Baseline
The following is a review of the status of each species being considered in this biological
opinion that may be adversely affected by the proposed action. The Service has reviewed
the list of threatened and endangered species and identified potential impacts to the
following species.
Texas prairie dawn (Hymenoxys texana) - The Texas prairie dawn is a small, delicate
annual to 6 inches tall with single or branching stems. It has small yellow flowers blooming
in late March to early April. It occurs in sparsely vegetated areas of fine-sandy compacted
soil. Specifically, the species occurs in the northern part of the Gulf Coastal Prairie in
Harris and Fort Bend counties, where it is found in poorly drained depressions or saline
swales around the periphery of low, natural mounds (mima mounds) in open grasslands.
These mostly barren areas are sparsely vegetated, and the soil is often covered with a
blue-green alga (Nostoc sp.). It can also occur on disturbed soils such as rice fields,
vacant lots, pastures, and possibly pipeline ROW if the soil structure remains relatively
intact.
99144ba2.v8
56

<<<PAGE 596>>>

Kimble
Hudspeth
Hays
•
Gillespie
ich occur. in counties traversed by Longhorn Pipeline
Fayette
Ector
Page 1 of 2
Cootert
Federally-listed Threatened or Endangered Species
Blanco:
RAD 39117
Species - Federal Classification
American alligator: TSA
Atwater's prairie-chicken - E
Bald eagle - T(PDL?:
Barton Springs salamander « Ei
Ber Creek Cave harvestman E
Bik-cooped vireo E
Bone Cave harvestman E
Clear Creek sambusia - E
Comal Springs dryopid beetle - E
Somal Springs diffle beetle - E
Comanche Springs pupfish • E
ild-buckwheat-T
Devil's River Minnow. T
rican spotted owe Te
Footh Gave

<<<PAGE 597>>>

Known or Suspected to Occur Within Area of Potential Effect
TSA - Listed Threatened Due to Similarity of Appearance
O - Not Likely to Occur Within Area of Potential Effect
M - Migrant Not Likely to be Adversely Affected
ce of Species: US Fish and Wildlife Service
PE - Proposed to be Listed as Endangered
FEDERAL CLASSIFICATION
PDL - Proposed to be De-listed
E - Listed Endangered.
T - Listed Threatened
Ward
Waller
TABLE 4
Federally-listed Threatened or Endangered Species which occur in counties traversed by Longliorn Pipeline
Upton
Page 2 of 2
000z
Schleicher
Reeves:
zOoO
Reagan
Menard
Mason
RAD 39118
Speciei - Federal Classificacion
low flycatcher - E
Smerkan Filigator - TSA
Atwater's prairie-chicken • E
bald eagle - T(PDL):
Barton Springs salamander • E
Bee Creek Cave harvestman: E
Black capped vireo •E
Bone Cave harvestman - E
Clear Creek gambusia: E
Comal Springs dryopid beetle • E
Coral Springs riffle beetle • E
Comanche Springs puplish • E
Devil's River Minnow - T
Fountan darter: E
Solden-cheeked warbler - E
m wild-buckwheat. T
eschmar Cave mold beetle - E:
Tooth Cave pseudose
ooth Cive spider - E:
a crane -E

<<<PAGE 598>>>

There are fewer than 35 known sites recorded for the species, and several have been lost
in recent years to urbanization in the Houston area. Most populations remaining are small,
and are on private land. Very few sites currently have any form of protection. The primary
threat to the species is habitat destruction as a result of urbanization, roadway construction,
and conversion of habitat for agricultural purposes.
An assessment of potentially suitable habitat for the Texas prairie dawn was conducted by
Horizon in early June 1999 along the Longhorn pipeline ROW in western Harris and
eastern Waller counties from the Satsuma Station on the west edge of Houston to near
Monaville in Waller County. Three areas along the ROW, one in Waller County and two in
Harris County, exhibited native range conditions with suitable soils that could be considered
potentially suitable habitat areas for the prairie dawn. All other areas along the pipeline
within the area investigated had been converted to row crop (corn), monoculture hay or
grazing pasture, or disturbed for land development. A survey for the prairie dawn has been
conducted within the potentially suitable habitat areas during early April 2000 with negative
results.
Navasota ladies'-tresses (Spiranthes parksii) - The Navasota ladies' tresses was listed
as endangered on May 6, 1982, without critical habitat. This member of the orchid family
occurs primarily in moist, sandy soils in small openings in post oak savanna vegetation.
The species is known to occur in Brazos, Burleson, Fayette, Freestone, Grimes, Jasper,
Leon, Madison, Robertson, and Washington counties (USFWS 1984b).
Currently, approximately 149 sites have been recorded, representing perhaps 75-80
distinct population areas, predominantly concentrated around two centers of distribution,
one in southern Brazos County and one in central Grimes County. Some of these recorded
sites have been damaged or destroyed since they were reported.
Together these
population centers contain the majority of known sites and individuals (Wilson 1993).
However, the majority of sites contain fewer than 25 recorded plants. It is known that for
this species not all individuals in a population are visible above ground in a given year, and
most of these sites have been visited only once, so demographic data on populations is
very limited. Nevertheless there is great concern among botanists that most of these sites
may not represent viable populations.
Navasota ladies'-tresses occur in a variety of moist sandy soils near drainages, in the Post
Oak Savannah vegetation associated with the Navasota, Brazos, and Trinity River
watersheds. Navasota ladies'-tresses are typically found on erosional remnants between
rills in slightly to moderately eroded areas along minor intermittent tributaries, from the
upper drainage head, extending along the edges of temporary streams to the flood plain of
permanent streams. Navasota ladies-tresses grow on sandy loam soils and are often
associated with post oak, blackjack oak, yaupon, slender bigelowia (Bigelowia nuttalli), and
Spiranthes cernua. Typical habitat consists of natural openings in upland Post Oak
Savanna vegetation (Poole and Riskind 1987, USFWS 1984b, Wilson 1993). Plants are
believed to be situated where subsurface flow or seepage of water occurs seasonally, a
common feature in other species of the genus (Arft and Ranker 1995, Kathy Parker, pers.
comm.). While Navasota ladies'-tresses is found in small naturally created openings in the
post oak woodlands, it cannot be regarded as a disturbance species, as it usually occurs in
99144ba2.v8
59

<<<PAGE 599>>>

well developed woodland and is not a colonizer of extensively disturbed areas. There are
few records in flood plain forests, open savannahs and shrublands that have experienced
little or no grazing pressure, and in hillside seepages.
Navasota ladies'-tresses is extremely slow-growing and long-lived. Rosette leaves support
the formation of a storage tuber between November and March that sequesters resources
in preparation for sending up a leafless bloom stalk at some future time. It is believed that
often plants require more than one year of photosynthate storage to successfully send up a
bloom stalk. If local conditions have not been favorable for forming sufficient below ground
reserves, the plant may not bloom (Wilson 1993).
Navasota ladies'-tresses apparently does not transplant well. In a mining project in Grimes
county by Texas Municipal Power Association (TMPA), plants in the impact area were
removed and transplanted into an adjacent habitat area. Plant survival has been low in
most sites (TMPA 1996). Similarly, in an experiment in Lick Creek Park near College
Station, Dr. Hugh Wilson planted some seedlings which survived into their second season,
but died prior to the third growing season (Wilson 1993).
Because of the low numbers of individuals reported from populations, the slow growing
nature of the plants, its unusual habitat requirements of openings in mature vegetation, and
its sensitivity to disturbance and transplanting attempts, the species is not regarded as
being very resilient, and recovery following any damage to a population is expected to be
slow.
The primary threat to Navasota ladies'-tresses is destruction or modification of habitat due
to urbanization, clearing for agricultural production, or mining (47 FR 19539, USFWS 1995,
1984b). Destruction of understory by feral pigs is also a problem in some areas. More than
40 known sites have been lost in the last ten years to mining or urbanization. Post oak
savannah in many of these counties continues to be converted to bermuda grass pasture.
Subsequently, habitat loss continues, particularly in the areas of Brazos and Grimes
counties where most sites are located. The City of College Station in Brazos County is
growing rapidly, particularly in the southern and southeastern fringes where most known
populations are located. Mining in Grimes County disturbs more than 7,000 acres every 5
years (Wilson 1993).
In Fayette County, the species is known from one small population approximately 6 miles
south of the pipeline and 2 miles north of the town of Fayette. Based on analysis of soil
distribution, vegetative cover, physiographic setting, and field assessment by Horizon in
November of 1999, two small areas of potential habitat for Navasota ladies'-tresses are
present along the pipeline corridor. Surveys for the species are scheduled to be conducted
along the pipeline in October 2000 if suitable climactic conditions occur.
Tobusch Fishhook Cactus (Ancistrocactus tobuschii) - Tobusch fishhook cactus is a
rounded, biscuit-shaped cacti usually 2 to 3 inches tall and up to 3.5 inches in diameter.
There are 3 to 5 central spines with the upper 2 to 3 erect and straight and the lower central
spines hooked at the tip and spreading. The plants are very inconspicuous, and produce
cream to yellow flowers from February through early April. These cacti have been
demonstrated to be obligate outcrossers pollinated by native bees with a foraging distance
of about 1/4 mile, and seeds are dispersed by native ants.
99144ba2.v8
60

<<<PAGE 600>>>

Currently about 50 sites are recorded for the species, following a recent range-wide
representative survey. Most of the populations are extremely small (5-20 plants), with
individuals widely scattered. Known sites are separated by large distances. Most existing
populations are on private land, and there are very few protected sites. Demographic data
collected in monitoring studies over the last five years or so show that only one of the
known populations is even marginally viable. The species is extremely slow growing and
does not appear to reproduce until 10-17 years of age. It takes four successful
flowers/fruits to produce one seedling (Jackie Poole, Texas Parks and Wildlife, pers.
comm.). It is estimated that very few viable populations (10-15) remain over the 8 county
range of the species. The survival and recovery of the species will require restoration and
careful management, to provide sufficient numbers of populations and individuals in
effective proximity to each other for successful pollination (and gene flow) to ensure the
continuity of the species.
Studies examining the probable reasons for population declines are underway. Threats to
the species are believed to include inappropriate timing of range management practices
(such as fire and clearing practices that disturb the soil), extensive predation by beetle
grubs, loss of habitat to
real estate development, and some collection by cactus
enthusiasts.
An assessment of potentially suitable habitat and pedestrian survey for the cacti was
conducted by Horizon in April 1999 along portions of the Longhorn pipeline ROW in Kimble
County, and no specimens were observed within the ROW. However, one Tobusch
fishhook cactus was observed about 50 feet north of the cleared ROW. An additional
survey of the entirety of the ROW through Kimble County was conducted by Horizon in late
February 2000 with negative findings for the cactus. However, as a conclusion of the
Phase One consultation, in the absence of complete surveys at that time, all of the ROW
within Kimble County was considered as potentially suitable habitat and fully compensated.
Golden-cheeked Warbler (Dendroica chrysoparia) -The golden-cheeked warbler is a
small, migratory songbird, 4.5 to 5 inches long, with a wingspan of about 8 inches. The
male has a black back, throat, and cap, and yellow cheeks with a black stripe through the
eye. Females are similar, but less colorful. The lower breast and belly of both sexes are
white with black streaks on the flanks. Typical nesting habitat is found in tall, dense,
mature stands of Ashe juniper (cedar) mixed with trees such as Texas (Spanish) oak,
Lacey oak, shin (scalybark) oak, live oak, post oak, Texas ash, cedar elm, hackberry,
bigtooth maple, sycamore, Arizona walnut, escarpment cherry, and pecan.
This type of
woodland generally grows in relatively moist areas such as steep-sided canyons and
slopes. A mix of juniper and deciduous trees on the slopes, along drainage bottoms, and in
creeks and draws provides ideal vegetation for birds. Warblers are also occasionally found
in drier, upland juniper-oak (i.e., live oak, post oak, blackjack oak) woodlands over flat
topography.
99144ba2.v8
61

<<<PAGE 601>>>

An assessment of potentially suitable habitat and surveys for the golden-cheeked warbler
was conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from
Austin, Texas, to the Mason/Kimble County line. Although no potentially suitable habitat
areas were observed within the Longhorn ROW, several areas were located adjacent to the
previously cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5
times during April and May on days with favorable weather conditions for bird activity, per
U.S. Fish and Wildlife Service guidelines (USFWS, 1994a). Surveys were conducted on 8,
9, 12, 27, 28 April, and 3, 11, 19 May. An equivalent of 4 person-hours per 100 acres were
spent at each site, based on habitat size. No golden-cheeked warblers were found to be
utilizing any of the potentially suitable habitat areas on or immediately adjacent to the
ROW. However, three years of survey are necessary to confirm presence/absence under
Service guidelines (USFWS 1994a). Additional surveys for the warbler are under way for
the Spring of 2000.
Black-capped Vireo (Vireo atricapillus) -The black-capped vireo is a 4.5 inch long,
insect-eating songbird. Mature males are olive green above and white below with faint
greenish-yellow flanks. The crown and upper half of the head is black with a partial white
eye-ring. The iris is brownish-red and the bill black. The plumage of the female is duller
than the male. Females have a dark slate gray head. In Texas, vireo habitat is found on
rocky limestone soils of the Edwards Plateau, Cross Timbers and Prairies, eastern Trans-
Pecos, and, to a limited extent, on igneous soils in the Chisos Mountains. Black-capped
vireos require shrub vegetation reaching to ground level for nesting cover. They typically
nest in shrublands.
An assessment of potentially suitable habitat and surveys for the black-capped vireo was
conducted by Horizon in April and May 1999 along the Longhorn pipeline ROW from
Austin, Texas to Crane County. Potentially suitable habitat areas were observed within the
Longhorn ROW as well as several areas located immediately adjacent to the previously
cleared permanent ROW. All areas were surveyed by Horizon a minimum of 5 times during
April and May on days with favorable weather conditions for bird activity, per Service
guidelines (USFWS, 1994a). Surveys were conducted on April 8, 9, 12, 27, 28, and May 3,
11, and 19. An equivalent of 4 person-hours per 100 acres were spent at each site, based
on size. No black-capped vireos were found to be utilizing any of the potentially suitable
habitat areas on or immediately adjacent to the ROW. However, three years of survey are
necessary to confirm presence/absence under Service guidelines (USFWS 1994a).
Additional surveys for the vireos are under way for the Spring 2000.
Bald Eagle (Haliaeetus leucocephalus) -The bald eagle is a migrant and winter resident
in Texas. The bald eagle was recently down-listed from endangered to threatened due to
successful conservation efforts and is now proposed for de-listing. Migrating and wintering
bald eagles typically arrive in Texas in November and depart around February. They are
found primarily in association with reservoirs, rivers or other large bodies of water where
they feed on fish, carrion, and waterfowl. Nesting bald eagles in Texas are found in the
eastern portion of the state and along the coastal plain as far south as Calhoun and
Refugio counties. No bald eagle nests have been identified near the pipeline ROW,
however, bald eagles may occur along major waterways (Brazos and Colorado rivers, or
major tributaries with impoundments) downstream of the pipeline corridor. The Federal
Register, (Volume 64 No. 128, Tuesday, July 6, 1999; Page 36454) contains a proposed
rule to remove the bald eagle from the List of Threatened and Endangered Wildlife in the
99144ba2.v8
62

<<<PAGE 602>>>

Lower 48 States of the United States. Formal delisting is now anticipated to occur in July
2000.
Interior Least Tern (Sterna antillarum athalassos) - Premier nesting sites for the interior
least tern are salt flats, broad sandbars, and barren shores along wide, shallow rivers.
Important breeding habitat characteristics include: (1) presence of bare or nearly bare
ground and alluvial islands or sandbars for nesting; (2) availability of food (primarily small
fish); and (3) favorable water levels during the nesting season (so nests remain above
water). They usually nest on sites devoid of vegetation, but have been found in areas with
an average of 11 to 30% vegetative cover, composed of grasses, shrubs, and trees and
ranging from 1 to 3 feet in height. Vegetation, if present, is usually located well away from
the colony, with the exception of bugseed, eastern cottonwood, and sandbar willow. As
natural nesting sites have become sparse, birds have used sand and gravel pits, ash
disposal areas of power plants, reservoir shorelines, gravel levee roads, and other
manmade sites. The typical nesting period for the least tern in Texas is mid-April to mid-
August.
While the interior least tern has not been documented along the pipeline corridor, potential
habitat for the tern is present downstream of the pipeline along several major waterways
including the Brazos, Colorado, Llano, and James Rivers, and Squaw, Beaver, and Sandy
Creeks.
The seasonal occurrence (Spring and Summer) and potential nesting of least
terns is possible in these areas.
Barton Springs Salamander (Eurycea sosorum)- The Barton Spring Salamander was
listed as endangered in 1997, without critical habitat. The Barton Springs Salamander
belongs to a group of related salamanders that are endemic to the Edwards Plateau region
of central Texas. All members of this group are obligately aquatic because the adults retain
the larval, gill-breathing morphology throughout their lives.
The Barton Springs
Salamander, formally described in 1993, was first collected from Barton Springs in 1946
and has been found only at the four hydrologically connected outlets of Barton Springs in
Zilker Park within the City of Austin (Brune, 1981; Chippindale et. al., 1993). This
salamander is a small species, adults reaching 2.5 inches (about 68 mm) in total length
with reduced eyes and elongate, spindly limbs indicative of a semi-subterranean lifestyle.
Barton Springs Salamanders are found in the flowing, thermally constant water issuing from
the spring outlets in association with aquatic macrophytes, leaves and organic debris, and
gravel and rock substrates having little silt and sediment deposition. Water from the
contributing and recharge zones of the Barton Springs segment of the Edwards Aquifer
influences the conditions at Barton Springs. The main threat to the species has been
identified as degradation of water quality from future growth and development on the
Barton Springs segment of the Edwards Aquifer (Federal Register 62:23385). An
expanded discussion of the environmental baseline for the salamander is provided in the
Project Documentation Appendix at Tab 22.
Houston Toad (Bufo houstonensis) - The Houston toad was listed as endangered in 1970
(Federal Register, October 13, 1970) and Critical Habitat was designated in Bastrop and
Burleson counties in 1978 (Federal Register, January 31, 1978). Houston toads are
generally brown and speckled, although individual toad coloration can vary considerably.
Some may appear light brown, others almost black and they may also have a slightly
reddish, yellowish, or greyish hue. Two dark bands extend down from each eye to the
99144ba2.v8
63

<<<PAGE 603>>>

mouth. Their legs are also banded with darker pigment. A variable white stripe streaks
along the sides of the toad's body. Their undersides are usually pale with small, dark
spots. Males have a dark throat which appears bluish when distended. Adult Houston
toads are 2 to 3.5 inches long and like all toads, are covered with raised skin patches that
contain chemicals that make the toad distasteful and sometimes poisonous to predators.
The toad was eliminated from three counties (Harris, Fort Bend, Liberty) prior to the 1970s
due to habitat loss resulting from urban expansion. Although Houston toad populations
have been found in nine other counties (Austin, Bastrop, Burleson, Colorado, Lavaca, Lee,
Leon, Milam, Robertson), the Service is concerned about the long-term viability of these
populations. The small population in Lavaca County has not been seen since its discovery
in 1991; the population at the critical habitat site (Woodrow Lake) in Burleson County has
not been seen since 1983; and the population in Leon County lies within an expanding
residential area. The largest known population of Houston toads occurs within the pine/oak
woodland region of Bastrop County. This area also contains federally designated critical
habitat.
All known Houston toad populations occur along bands of geologic formations that support
deep sands. Six populations occur on a band running through Bastrop County northeast to
Freestone County. Three other populations occur on another band through Lavaca, Austin,
and Colorado counties (USFWS, 1994b). Houston toad habitat consists of rolling uplands
characterized by pine and/or oak woodlands (loblolly pine, post oak, blackjack or sandjack
oak) underlain by pockets of deep, sandy soils. Because their skin is semi-permeable to
water, Houston toads become dormant to escape harsh weather conditions, such as winter
cold (hibernation) and drought (estivation). They seek protection during this time by
burrowing into sand or hiding under rocks, leaf litter, logs or in abandoned animal burrows
(TPWD, 1993). Although Houston toads are typically associated with woodland habitat,
they also breed in and migrate across sparsely wooded and cleared areas near woodlands.
They may also breed in and traverse areas that do not support deep sandy soils, including
clay and gravel substrates, provided these areas are near woodlands underlain by pockets
of deep sandy soils.
Houston toads breed from January to June, with a peak in February and March. During the
breeding season, toads appear to move randomly from one breeding site to another,
achieving genetic transfer between populations that may appear isolated, thus creating a
metapopulation, an aggregation of
smaller
populations linked genetically
demographically and functioning almost as a single population. Presently, the most reliable
breeding sites are stock ponds and similar impoundments, though in wet years breeding
may occur wherever sufficient standing water is present.
For successful breeding, water
must persist for at least 30-60 days to allow egg hatching, tadpole maturation, and
emergence of toadlets. Mortality in young is high, due to predation and drying of breeding
sites, with significantly less than one percent of eggs laid believed to survive to adulthood
(USFWS, 1984a, 1994b, 1995).
The Houston toad is vulnerable to extinction primarily due to habitat loss, degradation, and
fragmentation. Over the last 50 years, the historic range of Houston toads has contracted
and
several populations have been lost. Threats include expanding urbanization and
conversion of woodlands to agricultural production areas, such as coastal bermuda
pastures, use of fertilizers and pesticides that impact the toad directly or its food supply,
99144ba2.v8
64

<<<PAGE 604>>>

and loss of suitable breeding habitat because of alterations in watershed drainages and
wetland alterations or destruction (such as degraded water quality, draining/filling of
wetlands, stocking with predatory fish, etc.).
Since Phase One of the Longhorn Pipeline project involved the continuation of
maintenance activities rather than new clearing or development, and minimization of these
continuing maintenance activities included long-term habitat protection for the Houston
toad, the
• Service concluded that Phase One of the project would provide a net
conservation benefit for this species. According to the Houston Toad Recovery Plan
(USFWS 1984a), Houston toad breeding sights have been recorded in Buescher State
Park south of Longhorn Pipeline. Houston toads have also been heard chorusing on the
adjacent property owned by the University of Texas to the north of Buescher State Park
and Longhorn Pipeline (USFWS, unpublished data). Dr. James R. Dixon of Texas A&M
University conducted a survey along the Longhorn Pipeline ROW and adjacent Phillips EZ
Pipeline ROW in 1991 with negative results, although areas of potential habitat were noted
(Horizon 1991).
Horizon Environmental Services, Inc. conducted a reevaluation of suitable habitat along the
Longhorn Pipeline ROW within Bastrop County. The field reconnaissance was conducted
on 2 June 1999 from the Colorado River, southeast of Bastrop, to FM 2104. Portions of the
area along the pipeline had recently been cleared and planted in improved grasses. Based
on field observations and discussions with the Service, two areas of suitable habitat were
identified along and adjacent to the pipeline ROW. One area includes Buescher State Park
from approximately 0.5 mile east of the eastern boundary of the park westward to near
Highway 71. The second area begins about 500 feet to the west of FM 2104 and extends
westward approximately 0.75 mile. The drainages in both of these areas flow south toward
the Colorado River. A breeding season survey of the habitat areas in Buescher State Park
has been conducted by Horizon during February and March of 2000 with negative results.
Comanche Springs Pupfish (Cyprinodon elegans) - The Comanche Springs pupfish
seldom exceeds 2 inches in total length. It is gray-green above and pale yellow to white
below, with clear to light orange fins. The sides are silvery white with blue-black blotches
forming a "stripe" along the side (often faint on the male). Males have black speckling on
the side and a black edge on the caudal (tail) fin.
Historically, this pupfish occurred in 2 separate spring systems of the Pecos River
drainage.
One was Comanche Springs, with headwaters (now almost always dry) within
the city limits of Fort Stockton, Texas, and the other was a group of springs near
Balmorhea. The pupfish population at Comanche Springs were extirpated (lost) when the
springs first went dry in 1955. At present, the species occurs primarily in aquatic habitat fed
by springflow from Phantom Lake, Griffin, and San Solomon Springs near Balmorhea,
Texas. The Longhorn Pipeline is not within the sub-watersheds of these springs where the
pupfish occur and groundwater contamination from product releases that would affect the
springs is extremely unlikely (Dr. Charles Kreitler, personal communication). Therefore,
this species is not likely to be adversely affected, but is addressed herein for information
purposes only.
Pecos Gambusia (Gambusia nobilis) - The Pecos Gambusia is a small (2-inches long),
live-bearing fish with a dark lateral stripe and a metallic gray-blue color. Females have a
99144ba2.v8
65

<<<PAGE 605>>>

black area on the abdomen that surrounds the anal fin and anus. The anal fin of males is
modified into a gonopodium, a tube-like structure used in fertilization of the female.
Historically, the Pecos Gambusia was restricted to the Pecos River basin in southeastern
New Mexico and western Texas. The species occurred from as far south as Fort Stockton,
Texas to as far north as Fort Sumner, New Mexico. The populations of Pecos Gambusia
that once existed at Leon Spring and Comanche Springs were lost when these springs
went dry during the mid-1950s.
Presently in Texas, populations of the Pecos Gambusia
occur near Balmorhea in aquatic habitat supported by springflow from Phantom Lake,
Griffin, San Solomon, and East Sandia Springs. A substantial population also occurs in
Leon Creek and in Diamond-Y Spring outflow north of Fort Stockton. The species also
occurs in a limited number of locations in New Mexico. The Longhorn Pipeline is not within
the sub-watersheds that support the Pecos Gambusia and groundwater contamination that
would affect any of the spring habitats is extremely unlikely (Dr. Charles Kreitler, personal
communication). Therefore, this species is not likely to be adversely affected, but is
addressed herein for information purposes only.
Devils River Minnow (Dionda diaboli) - The Devils River minnow is a small fish, with
adults reaching sizes of 1.0 to 2.1 inches standard length. The fish has a wedge-shaped
caudal spot and pronounced lateral stripe with double dashes extending through the eye to
the snout but not reaching the lower lip. The species has a narrow head with prominent
dark markings on scale pockets above the lateral line that produce a crosshatched
appearance when viewed from the top.
General habitat associations for Devils River minnow have been described as channels of
fast-flowing, spring-fed waters over gravel substrates. Although the species is closely
associated with the stream, rather than in the spring outflow itself.
The known historic range of the species includes the Devils River from Beaver Lake
downstream to near its confluence with the Rio Grande and four other tributaries of the Rio
Grande River not associated with the Devils River. The current distribution of Devils River
minnow is at 2 sites on the Devils River, 2 sites on San Felipe Creek, and 1 site on
Sycamore Creek (US Fish and Wildlife Service, 1998).
The Longhorn Pipeline ROW crosses the northern most extent of the Devils River
watershed, in excess of 100 river miles upstream from known populations of the minnow.
At this distance, it is unlikely that released product would reach the population areas of the
minnow in quantities to be toxic (James Miertschin, personal communication). This species
is also unlikely to be adversely affected, but is included herein for informational purposes.
Southwest Willow Flycatcher (Empidonax trailii extimus) - The southwest willow
flycatcher occurs in riparian woodlands along streams and rivers in Hudspeth, Culberson,
and El Paso counties. Specific localities of this species in the vicinity of the pipeline are not
known. It is possible this species could occur along the Pecos and Devil's rivers
downstream of the pipeline. This species would not likely be directly affected by any
activitiy associated with the pipeline. However, this species utilizes riparian woodlands that
could be affected by a major release of
product in a waterway. The methods for
assessment of such a potential, but unlikely, event are addressed in section 3.4.
99144ba2.v8
66

<<<PAGE 606>>>

4.3
Effects of the Actions
Pipeline Operation
Normal operation of the pipeline is not expected to result in any adverse effects to listed
species. There is a risk of an accidental release from the pipeline-a risk Longhorn has
significantly minimized through various pipeline mitigation measures.
Many of these
pipeline mitigation measures were developed directly as a result of consultation with the
Service, in order to significantly minimize the risk of a spill near listed species, such as the
pipe replacement in Buescher State Park and the replacement of 19 miles of pipe over the
Edwards Aquifer recharge and contributing zones. The occurrence of a pipeline release is
so unlikely as to be improbable; see APR report, Project Mitigation Appendix at Tab 10.
Recognized pipeline experts have concluded that the implementation of the LMP will
enable the Longhorn Pipeline to operate at the highest reasonable level of safety attainable
by current technology; see APR report at Tab 10 of the Phase Two Project Documentation
Appendix.
Kiefner & Associates, Inc. (Kiefner) performed an audit of the Longhorn pipeline segment
between Houston and Crane (Tab 23 in the Phase Two Project Documentation Appendix).
Keifner concluded that the pipeline was safe to operate, even prior to the EA, so long as
certain recommendations were followed. Longhorn has committed in the LMP to
implement all of Kiefner's recommendations. Kiefner further reported on the safety of the
pipeline system as it will stand after implementation of all EA pipeline mitigation measures.
Among Kiefner's conclusions:
Hydrostatic testing is the most important and positive way of proving that a pipeline
is fit for service; the 2000 hydrostatic and proof testing will remove any doubts about
the remote possibility that defects may have arisen since the 1995 hydrostatic test
•
After the pipeline is placed into service, better technology than hydrostatic testing
will be used to assure that no defect develops or grows in service to the point where
a service failure results
•
"Smart-Pig" technology will be utilized by Longhorn to locate and characterize
anomalies that may represent... time-dependent developing defects
Longhorn has taken the unprecedented step of committing to limit surge pressures
to no more than the maximum allowable operating pressure (MAOP) in sensitive and
hypersensitive areas... providing an extra margin of safety in the critical areas
Longhorn's pipeline surveillance programs will "go a long way" to preventing
excavation or construction activities from encroaching on the pipeline and possibly
damaging it
The new pipe in the Edwards Aquifer recharge zone "reduces the already low risk of
failure from corrosion and excavation damage," providing an extra margin of safety
• "The proposed operation of the pipeline does not create in my opinion, an
99144ba2.v8
67

<<<PAGE 607>>>

unreasonable risk"
See Kiefner & Associates, Inc., January 13, 2000, Phase Two Project Documentation
Appendix at Tab 23.
Further, APR Companies, a company that specializes in pipeline accident investigation, has
concluded that the Longhorn Pipeline will benefit from a significant reduction in release
probability; see Phase Two Project Documentation Appendix at Tab 10.
APR
(reference Tab 10 in the Phase Two Project Documentation Appendix) has
determined that the average probability of a release (1 in 1000 years per mile) is
significantly improved for the pipeline in general through implementation of the LMP with a
resulting 2 to 5 times reduction in spill probability. For the Edwards Aquifer recharge zone,
the likelihood of a release is reduced 5 to 10 times with implementation of extensive LMCs
for that area. A resulting probability for a release then becomes 1 in 5,000 to 10,000 years
per mile.
APR further estimates the potential worst-case spill scenario for the Edwards Aquifer
recharge zone. An earlier estimate approximated 5000 barrels of product released in a
major incident. Placement of a single check valve at or near mile post 171 within the
recharge zone limits the maximum line fill volume that could spill to 2088 barrels. However,
APR's analysis also takes into consideration other factors that influence line drain down
such as intervening topographic lows that will hold pipeline contents. Based on detailed
analysis of the topography along the line through the recharge zone, and average per unit
line drain downs from independent statistics, the probable worst-case spill volume would be
only about 1147 barrels in 90% of the potential spill scenarios and 841 barrels in 75% of
potential spill scenarios. Longhorn nonetheless has designed the replacement pipeline and
emergency response capability on the basis of unqualified worst case release volumes.
LBG-Guyton (reference Tab 16 in the Phase Two Project Documentation Appendix) has
developed a risk analysis for the Barton Springs Salamander based on the probable worst-
case spill volume combined with the measures to be implemented to prevent or minimize
released product entry to the aquifer, such as sealing voids in the pipeline trench and
grading surface drainage within the ROW to direct any surface flow away from identified
point recharge features. Bermed areas at lower elevations will serve to capture product
that reaches the surface in those low areas.
Their analysis concludes that product
concentrations that might reach the aquifer, and ultimately Barton Springs, would be on the
order of 0.2 to 0.002 ppb. Concentrations in the water column would be even less (in the
absence of MTBE; see Kreitler at Tab 16 and LMC 35). These levels are at nearly an order
of magnitude lower than measured levels of petroleum hydrocarbons found in the aquifer
and at Sunken Gardens Spring in the past (see Tab 22 in the Phase Two Project
Documentation Appendix).
Biotoxicological information assembled from existing literature and agency file sources for
salamanders (and other aquatic vertebrates), and their prey base (aquatic invertebrates),
indicate that concentrations of toxic product constituents (BTEX) in the water column in the
ppb range are generally below the "no effect" levels for most organisms (Horizon, 2000).
From the above analysis, levels of benzene reaching the springs would be in the 0.010 ppb
99144ba2.v8
68

<<<PAGE 608>>>

(ug/l) range, while toluene would be in the 0.014 ppb range. Horizon reports that EPA data
indicate acute toxicity to freshwater aquatic life, for benzene, occurs at about 5,300 ug/l
(ppb), while for toluene, the acute toxicity level is about 17,500 ug/ (ppb). The EPA
information notes that more sensitive species would have lower acute toxicity levels.
However, from the available information, concentrations reaching the springs under the
above scenarios would conservatively be several orders of magnitude lower than toxic
concentrations.
The LBG-Guyton analysis assumes that all or most of the probable worst-case spill volume
would reach the aquifer. From prior spill experience with the Longhorn (under previous
ownership) and Shell pipelines over the aquifer (1986 and 1987 incidents), 91 to 97 percent
of the spilled product (west Texas crude with a similar viscosity to some refined products)
was recovered at the surface. Those recovery volumes were in the absence of the void
sealing and surface contouring Longhorn will implement to further enhance product
recovery. Furthermore, modeling analyses by Rose (1986) and Ross (2000) indicate that
soil retention capacity of spilled petroleum product over the Edwards Aquifer recharge zone
would be in the range of 350 to 1600 barrels if spread over a 1 to 2 acre area with average
soil depth of 0.33 to 1.5 feet. This absorption capacity, combined with high evaporation
rates for refined products, and the potential for high levels of product recovery would
significantly, if not totally, reduce or eliminate the quantity of product that might reach the
aquifer, and ultimately Barton Springs.
The 1986 and 1987 incidents resulted in spills of 2245 barrels and 1139 barrels,
respectively (in the absence of a block valve). The 1986 spill resulted in hydrocarbon
fumes in caves in the vicinity, but no documented adverse effects to the salamander or the
aquifer. Under the above-described scenario of a probable worst-case spill for the
Longhorn Pipeline (with extremely low probability of occurrence), it is unlikely that adverse
effects to the salamander would result as a result of the enhanced Longhorn mitigation
measures.
In addition to those facets of system operation that limit potential consequences by
minimizing release volumes and ensuring a rapid and effective response to a release,
Longhorn's emergency response capability will be increased significantly through the LMP.
Longhorn will ensure a maximum response time (a) of 1 hour in the recharge zone and
Slaughter Creek watershed in the contributing zone; (b) in the Barton Creek watershed in
the contributing zone and in other EA designated sensitive and hypersensitive areas of 1
hour to 2 hours; Longhorn will provide for the establishment of a response center in Central
Texas, to be located in South Austin, to make certain that manpower and equipment is
always at the ready. Prior experience has demonstrated an average response time of 58
minutes (see Tab 24 in the Phase Two Project Documentation Appendix). Once on-scene,
the response crews will have
the advantage of thorough and detailed information relating to any area along the pipeline.
Longhorn has commissioned the preparation of detailed studies of numerous facets of the
pipeline ROW, and surrounding areas, to prepare its response crews in advance, if ever
necessary. The information developed and advantages gained as a result of the studies
includes the following:
Species habitat: Response personnel will have the information necessary to avoid
99144ba2.v8
69

<<<PAGE 609>>>

species habitat areas during response and prioritize protective activities in the event
of a release in or near a habitat area
• Topography: Advance knowledge of area topography allows advance planning for
both release drainage potential and control and capture locations
• Rivers and streams: Detailed planning has identified waterways at risk and
advantageous protective and control locations
• Water wells: Both public and private wells are mapped so that responders may
prioritize drinking water supplies for protection
• Known karst features: Particularly within the Edwards Aquifer recharge zone,
advance knowledge of karst features provides information that allows responders to
prioritize protection of the aquifer and thus the Barton Springs Salamander
•
Surface drainage potential: Flow modeling provides knowledge of the potential for
released product to flow overland, enabling responders to identify likely scenarios
relating both to habitat areas and to human health and safety issues; responders will
also have the ability to identify preemptive control and capture locations; surface
containment systems are designed to capture any release that reaches the ground
surface
Longhorn has synthesized this information into stand-alone maps (See Project
Documentation Appendix) and in its FRP; further, responders will be trained to use such
information during training and during table-top and live drills.
Where a potential release might affect listed species or habitat, the precise level of impact
cannot be predetermined due to the large number of variables at any given location. As a
result, any such attempt at prediction is likely to result in an inaccurate estimate.
Accordingly, Longhorn proposes to adopt a contingent methodology for calculating any such
effects. This methodology should be useful in the event there is a release from the Longhorn
pipeline but neither the Clean Water Act nor the Oil Pollution Act applies to the incident. In
such a case, and if Longhorn is liable for the damage, Longhorn will use the Habitat
Equivalency Analysis methodology to determine the amount of compensation for which
Longhorn is responsible.
Longhorn proposes using a methodology that is capable of assessing natural resource
damages, preferably the Habitat Equivalency Analysis (HEA) methodology developed by the
National Oceanic and Atmospheric Administration (NOAA). HEA is briefly described below.
A more detailed description of the HEA methodology is provided in Phase Two Project
Documentation Appendix at Tab 25).
Pursuant to the HEA methodology:
•
The duration and extent of injury are documented and estimated from the time of
injury until the resource recovers to baseline.
99144ba2.v8
70

<<<PAGE 610>>>

• The services provided by a compensatory project are documented and estimated
over the full lite of the project.
• The size of a compensatory project is calculated such that the total increase in
services provided by the compensatory project equals the total interim loss of
services due to the injury.
• The cost of the compensatory project is calculated.
Other methods exist for assessing natural resource damages under NOAA's regulations
governing Natural Resources Damages Assessments for oil spills pursuant to the Oil
Pollution Act of 1990 (OPA). 33 U.S.C. § § 2701 et seq. These methodologies may prove
more cost-effective than the HEA method and should be considered as well.
In the event of an accidental release from the pipeline in or near habitat for listed species,
an adverse effect could occur. The level of potential take is impossible to predict in
advance.
Long-term Maintenance
In general, most long-term maintenance is unlikely to result in any adverse effects to listed
species beyond those addressed in the Phase One consultation. The majority of long-term
maintenance involves ROW maintenance, above-ground facility upkeep, and periodic
pipeline testing. These activities were addressed in the Phase One consultation and
compensated accordingly. Certain maintenance activities may, however, require
construction or land disturbance beyond the existing ROW. Such events are not presently
determinable. In the event any such maintenance should necessitate access or
construction
within listed species habitat, the previously utilized Phase One BA
maintenance construction procedures (see
•Phase One BA in the Phase Two Project
Documentation Appendix at Tab 1) will be followed under the direction of FER qualified
environmental inspectors. To the extent feasible, all construction activity will be restricted
to the existing ROW within habitat areas, which was fully compensated during Phase One
of this consultation. If construction must exceed the ROW in an area of potential habitat,
the Service will be notified in advance and additional compensation, as required, will be
calculated and provided pursuant to the conditions set forth in the Phase One BA for the
given species, to the extent a specific location has not previously been compensated for
off-ROW impacts.
An additional area of potential Houston toad habitat has been identified in Austin County
since the Phase One consultation was completed. This habitat area is within the geologic
formation known to support two small Houston toad populations in Austin County
approximately 8 miles south of the pipeline corridor and other small populations in Colorado
and Lavaca counties further to the south. This area is characterized as patchy woodlands
approximately 3000 acres in extent surrounded and interspersed by improved grazing
pastures, and with marginally suitable soils (loamy fine sands less than 24 inches deep)
(SCS, 1984). The known populations of toads occur in the Catilla-Tremona soil association
which is comprised predominantly of sandy soils (SCS, 1984). The potential habitat area
99144ba2.v8
71

<<<PAGE 611>>>

occurs in the Tabor-Tremona-Chazos association which is comprised of loamy and sandy
which are not favorable for Houston toads (SCS, 1984). Surveys of this area for the
soils. The two associations are separated by several miles of clayey and clayey loam soils
Houston toad are not known to have been conducted in the past. A breeding season
survey is planned for spring of 2001. The pipeline ROW through this area traverses
approximately 12,000 linear feet (2.3 miles). The existing 50 ft wide ROW, therefore,
occupies 13.8 acres.
This area could be adversely affected by maintenance of the ROW
and is being addressed through the Phase One consultation.
Emergency Response
Potential impacts from an emergency response action could be highly variable depending
on location, season, site characteristics, spill characteristics, and type of equipment needed
to respond to a particular situation. Training of emergency response personnel will be
conducted to make them aware of species related issues, designated potential habitat
areas, and avoidance procedures. Avoidance of impacts will be achieved to the greatest
extent possible under any given emergency situation. However, control and containment of
a product release or fire will constitute a priority, and some level of impacts to designated
potential habitats could occur. Impacts could occur from clearing or grading to gain access
for emergency response equipment, building temporary containment structures outside of
the established ROW, or to remove contaminated soil and vegetation. If fire containment is
necessary, fire breaks may need to be dozed in advance of a fire. These activities could
result in direct or indirect impacts to potential habitat
Such impacts would be
assessed and mitigated in the same manner as described previously under the Pipeline
Operation section above.
Construction
Buescher State Park (Houston Toad): Construction of the replacement and lowering
projects within Buescher State Park will be contained within the existing 50 ft ROW, and/or
within the previously cleared ROWs of the other two adjacent pipelines. No clearing
beyond the limits of the existing ROWs will be conducted. Compensation based on the
extent of existing Longhorn ROW through Houston toad habitat was provided in the Phase
One consultation. Therefore, no additional impacts or compensation are required for this
construction. A breeding season survey for toads in the vicinity of the pipeline has been
completed, and no toad breeding activity was identified. However, special procedures will
be implemented for avoidance prior to and during construction to ensure no adverse effects
occur to the toad. Prior to any land disturbance, the construction zone will carefully be
inspected by qualified biologists to ascertain the possible presence of Houston toads. The
construction zone will then be completely encircled with silt fence (set into the ground) to
preclude Houston toads from entering the work space. The construction zone will be
inspected periodically by the biologists to ensure Houston toads have not entered the area.
Therefore, this construction is unlikely to result in adverse effects to the Houston toad or
designated critical habitat beyond those addressed and compensated for in the Phase One
consultation.
Edwards Aquifer Recharge Zone (Barton Springs Salamander): As described in
Section 3.5, a 3-mile segment across the aquifer recharge zone will be replaced with
99144ba2.v8
72

<<<PAGE 612>>>

heavier wall pipe for enhanced safety and integrity. Approximately one-half mile will be
replaced immediately east of the recharge zone.
The new pipe will also be lowered for
greater depth of cover to minimize the potential for third-party strikes. Further, a concrete
barrier will be installed over the pipeline to protect the pipeline from third party intrusion; the
barrier will be constructed with colored reinforced concrete to increase its deterrent effect.
A number of other safety and integrity enhancement measures will also be installed,
including a sensor-based leak detection system and additional check valves.
All these
enhancements will significantly reduce the potential for releases and potential release
volumes in the unlikely event of a pipeline release. Longhorn hereby provides to the
Service mill certificates for the pipe that will be installed, along with Construction
Specification CS4, the specifications that identify methods and procedures for pipeline
construction; see the accompanying Phase Two Project Documentation Appendix at Tabs
26 and 27.
The construction to accomplish these enhancements will involve deepening the existing
trench. Construction will occupy an average work space of 60 feet wide along the 3-mile
route. This construction space has been investigated for karst features and other sensitive
environmental resources. A detailed Edwards Aquifer Protection Plan has been developed
for the project that includes the implementation of all required best management practices
(BMPs) using as guidelines the City of Austin Land Development Code specifications and
the TNRCC Edwards Aquifer Rules for construction over the recharge zone (Phase Two
Project Documentation Appendix at Tab 28). Detailed construction plans will be developed
to identify both the design and location of water quality control structures, as well as non-
structural BMPs; those plans, which are currently under development, will be made
available to the Service upon preparation of reasonably complete draft documents.
The environmental protection plan also provides for FERC qualified environmental
inspectors to be onsite during the construction process to continuously review and evaluate
the efficiency of the recommended BMPs and to make changes as needed for maximum
environmental protection. The environmental inspectors will also react to any encounter of
subsurface voids by immediately notifying project geological and biological experts for
evaluation of the situation and to make recommendations for remedial actions. Remedial
actions will, at a minimum, comply with TRCC guidelines for closure of subsurface voids.
All encountered limestone voids, regardless of size, will be appropriately sealed within the
construction trench. This will prevent potential siltation into the aquifer via such voids
during construction, as well as provide additional protection from aquifer contamination in
the unlikely event of a product release during operation of the pipeline. In the event a large
void is encountered, geotechnical engineers will also be involved in evaluating and
recommending remedial actions. The City of Austin, TRCC, Barton Springs/Edwards
Aquifer Conservation District, and the Service will also be notified and informed of
recommended remedial actions. The trench has been designed with high porosity
containment capacity and bermed areas at locations where product could reach the
surface.
With the implementation of the Edwards Aquifer Environmental Protection Plan, the
construction across the Edwards Aquifer recharge zone is not expected to result in any
significant adverse impacts to the aquifer or the Barton Springs Salamander.
Edwards Aquifer Contributing Zone (Barton Springs Salamander): As described in
99144ba2.v8
73

<<<PAGE 613>>>

Section 3.5, approximately 15 miles of pipe in the contributing zone will be lowered and
replaced, and a check valve will be installed immediately downstream of the existing block
valve over the contributing zone (MP 175.5), even though the replacement is not necessary
(See "Edwards Aquifer Contributing Zone Protections" in The Project Documentation
Appendix). The replacements will be installed using heavier wall pipe than exists at this
time and will be lowered at least 5 feet below the ground surface. Construction over the
contributing zone will be conducted pursuant to the methods and procedures outlined in the
Phase One BA. The heavier, deeper pipe will reduce the risk of a release across the
contributing zone. The trench has been designed with high porosity containment capacity
and bermed areas at locations where product could reach the surface. The check valve will
reduce potential release volumes by immediately stopping flow upstream, in the event of a
release east of the block valve; as a result, the potential for drainage from higher-elevation
segments to the west of the check valve is eliminated during the time required for the block
valve to close. Moreover, at the Cedar Valley pump station, which is located in the
contributing zone upgradient of the pipeline crossing of Barton Creek, Longhorn has
committed to install secondary containment (LMC 27) and a remote monitoring camera
(LMC 21) before project startup. The secondary containment will provide protection to
Barton Creek, and remote cameras allow monitoring by the pipeline controllers.
Furthermore, the host of pipeline mitigation measures directed to Tier Il and III areas will
apply over much of the contributing zone, including hydrostatic pressure and proof testing,
enhanced leak detection, frequent patrols, cathodic protection system testing, in-line
inspection shortly after startup, surge pressure protection, and the establishment of a
response center in South Austin. See Section 3.4, Emergency Response.
4.4 Planned, But Unscheduled Construction
As described in Section 3.0, several additional improvements to the pipeline are planned to
take place, but have not been specifically designed or scheduled at this time. While many
of these improvements are located at existing above-ground facilities (valves, pump
stations, etc), the exact location and construction details are not yet known. It is believed
that the majority of these additional improvements will not occur in potential habitat areas,
but if so will not adversely affect listed species habitat, or can be designed to avoid habitat
areas.
In the event any such improvements should necessitate access or construction
within listed species habitat, the previously utilized Phase One BA maintenance
construction procedures (see Phase Two Project Documentation Appendix at Tab 1) will be
followed under the direction of FERC qualified environmental inspectors. To the extent
feasible, all construction activity will be restricted to the existing ROW within habitat areas,
which has been fully compensated. If construction must exceed the ROW in an area of
potential habitat, the Service will be notified in advance, and additional compensation, as
required, will be calculated and provided according to the procedures set forth in the Phase
One BA for the given species, to the extent a specific location has not previously been
compensated for off-ROW impacts.
4.5 Future Additional, But Currently Unforseen Construction
As described in Section 3.0, at various, but unpredictable, times and places in the future,
certain construction activities may be required for maintenance, repair, or testing of the
99144ba2.v8
74

<<<PAGE 614>>>

pipeline or attendant facilities. The majority of these future construction activities can be
designed to avoid any adverse effect to listed species to the extent the activities occur
within potential habitat areas.
In the event any such construction should necessitate
access or disturbance within listed species habitat, the previously utilized Phase One BA
maintenance construction procedures (see Phase Two Project Documentation Appendix at
Tab 1) will be followed under the direction of FERC qualified environmental inspectors. To
the extent feasible, all construction activity will be restricted to the existing ROW within
habitat areas, which has been fully compensated. If construction must exceed the ROW in
an area of potential habitat, the Service will be notified in advance, and additional
compensation, as required, will be calculated and provided pursuant to the conditions set
forth in the Phase One BA for the given species, to the extent a specific location has not
previously been compensated for off-ROW impacts.
4.6 Bays and Estuaries
The Longhorn Pipeline is in proximity to the Galveston/Trinity Bay system where it passes
through Houston. All surface drainage in the Houston area crossed by the Longhorn
Pipeline drains to the Galveston/Trinity Bay system ultimately through Buffalo Bayou and
the Houston Ship Channel.
Bay systems along the Texas coast, including the
Galveston/Trinity Bay system, are documented to support a number of listed threatened or
endangered sea turtles and marine mammals. Possible concern could exist in the event of
a catastrophic release event that product could reach the bay system in sufficient quantities
to be toxic or detrimental to those listed species.
Several factors are to be considered in this situation that result in an extremely low
probability for significant quantities of product to be released in a tributary or waterway that
would have direct inflow to Galveston and Trinity Bays. First, the Longhorn Pipeline is
buried very deep at the various waterway crossings in north Houston, such as Greens
Bayou (24 feet), Hunting Bayou (25.2 feet), ditch north of Hunting Bayou (33.1 feet), ditch
south of Hunting Bayou (28 feet), and others (See depths of cover in Project
Documentation Appendix). This significant depth greatly reduces the potential for third
party strike. Second, most of the area through east and north Houston is ranked as Tier 2
or 3 zones, thus being subject to the enhanced LMP provisions for Sensitive Areas, and
Hypersentitive areas.
Additionally, all the tributaries drain to Buffalo Bayou and the
Houston Ship Channel. Due to the large number of chemical, refining, and industrial
facilities situated along the Houston Ship Channel, there exists in place a comprehensive
spill response system and equipment to respond quickly to spills of any nature that occur in
the channel. It is unlikely that a significant spill from the Longhorn Pipeline would occur in a
sensitive drainage area, or would escape the Houston Ship Channel containment into the
bays.
4.7 Summary of Conservation Measures
99144ba2.v8
75

<<<PAGE 615>>>

The following provides a summary of the avoidance and conservation measures that
Longhorn commits to provide.
These measures are assured by the mandates of this
consultation and the overall NEPA process simultaneously ongoing with this consultation.
The implementation of these conservation measures for listed species assure that the
project will be unlikely to result in jeopardy or adverse modification of critical habitat for any
listed species and is not likely to adversely effect species or habitat.
Many of the mitigation measures of the Longhorn Mitigation Plan which were designed prior
to the Phase One or Phase Two consultation processes were intended to provide
protections for listed species, either directly or intrinsically. While all LMP features provide
significant safety and integrity enhancements for the pipeline as a whole that ultimately
benefit species protection, those described below provide specific enhancements which will
avoid potential impacts to listed species. Most of these features were incorporated into the
LMP prior to finalization of either of the consultation processes.
• LMCs 3, 5, 34 - Pipe replacement and lowering over the Edwards Aquifer recharge and
contributing zones, with trench and surface containment areas (Barton Springs
Salamander), Buescher State Park (Houston toad), Pedernales Falls State Park
(golden-cheeked warbler), and other locations in species habitat areas;
• LMC 22 - Analysis of, and if necessary, installation of additional valves to limit potential
release volumes (all species);
• LMC 13 - Addition of an enhanced pipeline leak detection system with additional
sensor-based leak detection over the recharge zone and slaughter creek watershed
in the contributing zone (all species);
• LMC 20 - Increased pipeline surveillance in EA designated sensitive and
hypersensitive areas and daily pipeline surveillance across the recharge zone (at
least once per week on-ground) (all species);
• LMC 23 - Establishment of a fully equipped Emergency Response Center in South
Austin (Barton Springs Salamander and Houston toad):
•
LMC 28 - Revised Facility Response Plan to incorporate features of the City of
Austin Barton Springs Oil Spill Contingency Plan and the U.S. Fish and Wildlife
Service's Barton Springs Salamander Recovery Plan as well as detailed response
planning based upon analysys of stream flow potential in the Edwards Aquifer
recharge and contributing zones. (Barton Springs Salamander);
•
LMC 33 - Establish a refugium for the Barton Springs Salamander and performance
of other conservation measures for listed species as may be determined appropriate
through consultation with the U.S. Fish and Wildlife Service (all species);
•
LMC 27 - Provide secondary containment around the Cedar Valley pump station
which lies within the Barton Springs/Edwards Aquifer contributing zone.
99144ba2.v8
76

<<<PAGE 616>>>

• LMC 35 - Longhorn has committed that it will not transport products containing
MTBE or similar aliphatic ether fuel additives in greater than trace amounts;
Though not a specific mitigation commitment, Longhorn has identified all potential
areas of concern for listed species along the pipeline corridor from Houston to El
Paso for purposes of assessment and avoidance.
An additional intrinsic benefit of increased patrol frequencies (LMC 20) is the result
that increased inspection and surveillance of the Longhorn Pipeline will enable
inspection personnel to coincidentally observe the adjacent pipelines that parallel the
Longhorn pipeline. This will provide the opportunity for identification of pipeline
emergency situations and threats to the integrity of those pipelines with greater
frequency than currently is the case.
In fulfillment of LMC 33, Longhorn has committed to a significant number of additional
mitigation features specific to listed species developed during the Phase One and Phase
Two consultation processes. These commitments become binding as a result of the
conclusion of the consultation processes and issuance of the Service's Biological Opinion,
and as incorporated into the LMP as it evolves during the EA process. These measures
have been developed during the two phases of consultation through discussions between
Longhorn, EPA, DOT, and the Service. These commitments are listed below by
consultation phase.
Phase One
• Provision of conservation funding for potentially affected species in the approximate
amount of $992,448 (all species).
• Monitoring studies of listed species within or adjacent to the ROW (all species).
• Minimization of maintenance construction work space in potential species habitat
areas (all species).
• Seasonal timing of maintenance activities to avoid critical breeding, nesting, or
blooming periods for listed species (all species).
• Use of special mowing/clearing processes and equipment in potential species
habitat areas to minimize ground disturbance (all species).
• Provision of FERC qualified environmental inspectors during maintenance activities
within potential species habitat areas (all species).
• Use of native grasses for restoration of disturbed areas during maintenance
activities (all species).
• Minimization of the use of herbicides for maintenance purposes (all species).
99144ba2.v8
77

<<<PAGE 617>>>

Phase Two
Detailed topographic and surface flow modeling to enhance spill response planning
efforts (all species).
Special investigative, preparation, and construction practices and techniques for
pipe replacement over the Edwards Aquifer Recharge Zone (Barton Springs
Salamander) including:
Intensive geological and biological field studies of the pipeline corridor to
Identity sensitive teatures and areas, including ground penetrating radar,
geotechnical coring,
karst identification, geological
and biological
investigations of identified features, and detailed geologic assessment for
recharge potential.
-
Use of enhanced best management practices for erosion and sedimentation
control during and after construction of new pipe.
-
Sealing of subsurface voids encountered during trench excavation.
-
Provision of a colored, reinforced concrete barrier over the new pipe for
enhanced protection from third party damage.
Grading of the surface over the new pipe installation to direct surface
drainage (potential
surface release away from identified sensitive
areas/features.
•
Lowering and replacement of 15 miles of pipe across the Edwards Aquifer
Contributing Zone.
Training for first responders and other spill response personnel for highest efficiency
and care in
species
areas
(all species) .
Cumulative Effects
Cumulative effects of future State, local or private actions that are reasonably certain to
occur in the action area are considered in this BA. Future Federal actions that are
unrelated to the proposed action are not considered in this section because they require
separate consultation pursuant to Section 7 of the Act. Because of the linear nature of the
pipeline and the long history of clearing and operations (about 50 years), no cumulative
effects from the activities proposed are anticipated. The majority of the counties involved in
the project are predominantly rural (see draft Environmental Assessment of the Proposed
Longhorn Pipeline System at Section 4.1.1.2), and imminent future actions identified are
not likely to result in jeopardy to the species and are not likely to adversely affect any listed
species or habitat.
The various mitigation measures required for the Longhorn Pipeline as a result of the
environmental review being conducted by the Lead Agencies or as a consequence of this
99144ba2.v8
78

<<<PAGE 618>>>

consultation can be expected to have net beneficial effects on the environment, including
listed species and their habitats. First, the Longhorn Pipeline itself will be improved,
providing a higher level of environmental protection than previously was the case for the
pipeline. Second, the Barton Springs Salamander refugium and captive breeding program
will help mitigate for risks posed not only by the Longhorn pipeline, but by the many other
existing sources of potential harm to the salamander, outlined above in the discussion of
the environmental baseline for the salamander.
In addition, some Longhorn-related mitigation measures will have the indirect or cumulative
effect of reducing environmental and species-related risks associated with the two other
petroleum pipelines in the area, especially over the Edwards Aquifer. For example, the
Longhorn Mitigation Plan requires increased surveillance along the pipeline route. While
most pipelines have weekly surveillance, Longhorn has committed to a patrol frequency of
once every 2.5 days for sensitive and hypersensitive areas. In the three-mile crossing of
the Barton Springs recharge zone, Longhorn will have daily patrols. This increased
frequency of patrol will facilitate early detection of leaks and third party activity in the are
of all three pipelines crossing the recharge zone.
Similarly, Longhorn's commitment to aggressive public education and awareness programs
will help reduce risks for all three pipelines crossing the Barton Springs recharge zone.
ublic awareness should deter individuals from acts that might risk catastrophic spills o
other accidents potentially affecting the environment and listed species
99144ba2.v8
79

<<<PAGE 619>>>

5.0 REFERENCES
Arft, A. and T. Ranker. 1995. Demography of the rare orchid Spiranthes diluvialis:
implications for conservation. Program and Abstracts, g'h annual meeting of the Society for
conservation Biology, June 7-11, Fort Collins, Colorado. Abstract, notes from presentation
attended. U.S. Fish and Wildlife Service, Austin, Texas.
Brune, G. 1981. Springs of Texas: Volume 1. Branch-Smith Inc. Fort Worth, Texas.
Chippindale, P., D. Hillis, and A. Price. 1990. Central Texas Salamander Studies. Section
6 report submitted by Texas Parks and Wildlife Department to U.S. Fish and Wildlife
Service. Federal Aid Project No: E-1-2, Job No. 3.4. Austin, Texas.
Horizon Environmental Services, Inc. 1991. Threatened or Endangered Species
Investigations - EZ Pipeline Project. Horizon Environmental Service, Inc. Austin, Texas.
Horizon Environmental Services, Inc. 2000. Biotoxicological Analysis a Potential Longhorn
Pipeline Product Release Over The Edwards Aquifer Recharge Zone, Barton Springs
Segment. Horizon Environmental Services, Inc. Austin, Texas.
Poole, J.M,. and D.H. Riskind. 1987. Endangered, Threatened, or Protected Native Plants
of Texas. Austin, Texas: Texas Parks and Wildlife Department, State of Texas.
U.S. Fish and Wildlife Service (USFWS). 1984a. Houston toad recovery plan. U.S. Fish
and Wildlife Service. Albuquerque, New Mexico. 73pp.
U.S. Fish and Wildlife Service (USFWS). 1984b. Navasota ladies'-tresses recovery plan.
U.S. Fish and Wildlife Service. Albuquerque, New Mexico.
U.S. Fish and Wildlife Service (USFWS). 1994a. Minimum Procedures for Determining the
Presence/Absence of Golden-Checked Warblers and Black-Capped Vireos. March 7, 1994
Memorandum, Austin Field Office.
U.S. Fish and Wildlife Service (USFWS). 1994b. Population and habitat viability
assessment: Houston toad (Bufo houstonensis). Workshop conducted by IUCN/SSC
Conservation Breeding Specialist Group in partial fulfillment of USFWS contract #94-172.
Apple Valley, Minnesota.
U.S. Fish and Wildlife Service (USFWS). 1995. Threatened and Endangered Species of
Texas. Austin, Texas: US Fish and Wildlife Service, Revised June, 1995.
U.S. Fish and Wildlife Service (USFWS). Houston Toad Recovery Team. 1999. March 31-
April 1, 1999 Meeting Minutes. U.S. Fish and Wildlife Service, Austin, Texas.
U.S. Fish and Wildlife Service (USFWS). Final Rule to List the Barton Springs Salamander
as Endangered. 62 FR 23377. Apr. 30, 1997.
Texas Parks and Wildlife. 1993. Endangered species information for Hilltop Lakes. Texas
Parks and Wildlife Resource Protection Division, Austin, Texas.
99144ba2.v8
80

<<<PAGE 620>>>

Wilson, H. 1993. Contractors partial draft of recovery plan revision for Navasota ladies'-
tresses (unfinished contract). U.S. Fish and Wildlife Service, Austin, Texas.
(SCS) Soil Conservation Service. 1984. Soil Survey of Austin and Waller Counties, Texas.
United States Department of Agriculture.
99144ba2.v8
81

<<<PAGE 621>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 4C
PROGRAMMATIC AGREEMENT

<<<PAGE 622>>>

Programmatic Agreement
among the
U.S. Environmental Protection Agency,
U.S. Department of Transportation,
Texas State Historic Preservation Officer,
Tribal Historic Preservation Officer(s) (or other Tribal official)
and the Advisory Council on Historic Preservation
regarding the
Longhor Pipeline Project in Texas
WHEREAS, the U.S. Environmental Protection Agency (EPA), and the
U.S. Department of Transportation (DOT) have agreed to prepare an Environmental Assessment
(EA) on the Longhorn Partners Pipeline Project in Texas (hereinafter referred to as the
Undertaking); and
WHEREAS, the EPA and DOT have determined that the Undertaking may have an effect
on "historic properties" (i.e., properties included in or eligible for inciusion in the National
Register of Historic Places), and have consulted with the State Historic Preservation Officer
(SHPO), applicable Tribal Historic Preservation Officers (THPO) and where there is no THPO
other appropriate Tribal officials, and the Advisory Council on Historic Preservation (ACHP),
pursuant to Subpart B of the ACHP's regulations (36 CFR Part 800) implementing Section 106
of the National Historic Preservation Act (NHPA); and
WHEREAS, the EPA and DOT will, as a part of the EA process, elicit the views of
interested federal and state agencies, environmental groups and the public with regard to the
Undertaking and its effect on historic properties; and
WHEREAS, the effects on historic properties cannot be fully determined prior to
approval of the Undertaking, and this PA addresses all phases of facilities construction for those
areas;
NOW, THEREFORE, the EPA, DOT, SHPO/THPO and ACHP agree that this PA is
consistent in theorince vior se following stipulations in order to saisy al aspects or EPA'S
and DOT's Section 106 responsibilities.
1

<<<PAGE 623>>>

the Secretary of the Interior for Histonic Preservation (48 CFR 44734-37). Survey and testing
at pa guidelnes of
work shall provide sufficient documentation to assess the eligibility, in consultation with the
SHPO/THPO, of the properties for inclusion in the National Register of Historic Places. Any
unresolved eligibility issue(s) between LPP and the SHPO/THPO will be forwarded to EPA and
DOT for submittal to the Keeper of the Register for final determination. LP shall submit a draft
report of survey investigations to the SHPO/THPO for review and comment, prior to initiating
:
test excavations designed to evaluate National Register eligibility, in order to allow the
!
SHPO/THPO to comment regarding sites requiring testing. Unless the SHPO/THPO notifies
LPP within 30 working days after receipt, the survey investigations shall be considered adequate
for Section 106 purposes. LPP shall provide a draft report of test excavations to the
SHPO/THPO, with a copy to ERA and DOT, to allow SHPO/THPO's review and
recommendation(s) on the National Register eligibility of tested sites. Unless the SHPO/THPO
objects to it within 30 working days after receipt, the draft testing report shall be considered
adequate for Section 106 purposes. If the SHPO/THPO objects or requests additional testing
information, the matter will be resolved between LPP and the SHPO/THPO. If the adequacy of
stipulation 7, below.
testing cannot be resolved between LPP and the SHPO/THPO, it shall be resolved according to
2. For historical and archeological properties determined by the SHPO/THPO, or the
for purposes of Section 106.
Keeper of the Register, to be ineligible for the National Register, no protection need be afforded
Bit lactims
3. For affected arseniagical properties determined eligible for inclusion to the National
elgile?
Register, and where it is not possible to avoid the potential adverse effects of the Undertaking,
LPP shall:
(a). Develop, in consultation with the SHPO/THPO, and implement a Data Recovery
Plan and Research Design (hereinafter referred to as the Plan). The Plan shall be consistent with
the Secretary of the Interior's Standards and Guidelines for Archeological Documentation (48
CFR 44734-37) and take into account the ACHP's publication, Treatment of Archeological
Properties.
(b). The Plan shall include, as appropriate, research, design, controlled earth work, report
schedules, monitoring, relocation, preservation, reburial, recordation, and curation of artifacts. It
shall specify, at a minimum: i) the property or properties where data recovery is to be carried out;
ii) any property or properties that will be destroyed, altered or transferred without data recovery;
ili) research investigations that will be conducted under the approved data recovery plans and, as
appropriate, will take into account any previous work conducted or other research in the area, and
2
.... ..

<<<PAGE 624>>>

and DOT.
(c). LPP shall submit the Plan to the SHPO/THPO, for review and approval, prior to
initiating any action that would adversely affect an eligible property. Unless the SHPO/THPO
objects within 30 calendar days after receipt, the Plan shall be implemented by LPP. If the
SHPO/THPO objects, and/or requests additional information or revisions to the Plan, the matter
will be resolved between LPP and the SHPO/THPO. If the matter cannot be resolved, it shall be
resolved according to stipulation 7, below.
4. For affected historie properties, other than archeological sites, determined eligible for
the National Register, and where it is not possible to avoid the adverse effects of the
Undertaking, LPP shall, in consultation with the SHPO/THPO and any identified interested
parties, including Indian tribes and other Native Americans identified by EPA or DOT, develop a
proposal to mitigate the adverse effects of the Undertaking on those properties. Then, LPP shall:
(a). Provide the SHPO/THPO, for review and approval, the mitigation proposal to ensure
the recordation, relocation, marketing and/or preservation of the property, taking into account the
Secretary of the Interior's Standards for Treatment of Historic Properties (36 CFR 68). In
determining what level of documentation to propose, LPP shall first contact the SHPO/THPO
and/or the National Park Service (NPS), Intermountain Field Office, 1220 South St. Francis Dr.,
Santa Fe, New Mexico 87504.
(b). Unless the SHPO/THPO objects within 30 calendar days after receipt, the mitigation
proposal shall be implemented by LPP. If the SHPO/THPO objects, or requests additional
information or revisions to the proposal, the matter shall be resolved between LPP and the
SHPO/THPO. If the proposal cannot be revolved, it shall be resolved according to stipulation 9,
below.
5. LPP, in coordination with the SHPO/THPO, shall ensure that all survey, evaluation,
data recovery, mitigation, and monitoring are conducted under the direct supervision of a
person(s) meeting, at a minimum, the qualifications set forth in the professional qualifications
standards in the Secretary of the Interior's Standards and Guidelines for Archeology and Historic
Preservation. If any cultural properties are discovered during construction or related ground
disturbing activities, LPP shall ensure that all activities are halted that may adversely effect an
cultural property, and immediately notify the SHPO/THPO, EPA and DOT. LPP shall allow the
SHPO/THPO a minimum of two working days to inspect the property. Based on the
SHPO/THPO's findings, determine with EPA and DOT, appropriate course of action based on
PA process beginning at Stipulation 1.
3

<<<PAGE 625>>>

7. Should LPP or the SHPO/THPO object within 30 calendar days to any plan, proposal,
requirement or specification pursuant to this PA, EPA and DOT shall consult with the objecting
party to resolve the objection. If EPA and DOT determine that the objection cannot be resolved,
EPA and DOT shall forward all pertinent documentation on the dispute to the ACHP. Within 30
days after receipt of all pertinent documentation, the ACHP will: a) provide the EPA and DOT
with its recommendation, which EPA and DOT shall take into account in reaching a final
decision; or b) notify EPA and DOT that it will comment pursuant to 36 CFR 800.7, and proceed
to comment. Any ACHP comment provided in response to such a request shall be taken into
account by EPA in accordance with 36 CFR 800.7(c)(2). Any recommendation or comment
provided by the ACHP shall be understood to pertain only to the subject of the dispute.
8. Should a member of the public, Indian tribe or other Native American, or other
interested person object at any time during implementation of the measures stipulated in this PA,
EPA and DOT shall take the objection into account and consult, as appropriate, with the
objecting party, the SHPO/THPO, the ACHP, and/or LPP. If EPA and DOT determine the
objection cannot be resolved, it shall follow stipulation 7, above.
9. Nothing herein shall preclude LPP from exercising any rights it may have to seek
appropriate review of any findings, determination or ruling which may be made by any
regulatory authority under this PA.
10. Upon written notice from the SHPO/THPO or the ACHP that any of the conditions
of this PA are being violated, the EPA and DOT shall consult with the SHPO/THPO and ACHP
to determine how the concern should be resolved.
11. If the EPA, DOT, SHPO/THPO or ACHP finds that the terms of this PA cannot be
met, or considers a change or revision to be appropriate, it shall request the other signatory
parties to consider an amendment of the PA. All amendments shall be executed in the same
manner as the original PA.
12. Any party to this PA may terminate it by providing 30 working days written notice to
the other parties, provided that the parties will consult during the period prior to termination to
seek amendments or other actions that would avoid termination. In the event of termination, the
EPA will comply with 36 CFR 800.3 through 800.6 for this Undertaking.
4

<<<PAGE 626>>>

(date)
the State Historic Prevervation Officer of Texas
the U.S. Department of Transportation
(dato
the Advisory Couracil oa Historic Preservation
the Vi. Jole 9/2/000
пате)
(date)
Concurrion Party.
Longhora Pipelis Parters, LP.
Carto
(Danse)
(date)
Tribal Siguanory (will Ill in Tribe names if any want to participare)
Dear Matader 4/2/0
Tribal Fistric Preseration Oicel
Mescaluo Apuche Tribe
TOTAL P. 11

<<<PAGE 627>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 4D
SHPO CONCURRENCE LETTER

<<<PAGE 628>>>

Horizon...
Environmental Services, Inc.
26 April 2007
RECEIVED
Mr. Bill Martin
APR 2 6 2007
Texas Historical Commission
P.O. Box 12276
TEXASHISTORICALCOMMISSION
Austin, Texas 78711-2276
RE:
Longhorn Partners Pipeline, L.P,
CONCUR
High Probability Maps
Waller through Crane Counties, Texas
by
Welln 1. Mak
Section 106
for F. Lawerence Oaks
HJN 050175 AR
State Historic Preservation Officer
Date
5/23/67
Dear Mr. Martin:
Track#
Please find enclosed a CD containing files of the delineated archeological high probability areas
along the Longhorn Partners Pipeline (LP) right-of-way (ROW) from Waller County through
Crane County, Texas.
The CD contains 21 PDF's of strip maps depicting: 1) the ROW
alignment on topographic quadrangles; 2) the delineated archeological high probability areas;
and 3) areas in the vicinity of the archeological high probabilities areas that have been
previously surveyed for cultural resources. In addition, the CD contains an Excel file depicting
the beginning and end mileposts of each high probability area as well as the counties in which
they are located. As you will recall, Jeff Blackmore and I met with you a few months ago and
went over the delineated high probability areas. The files on the CD reflect the identical areas
that we reviewed together with the exception of areas that have been recently surveyed with
negative results. These negative survey areas have been clipped from the stretches of high
probability areas, leaving only unsurveyed areas.
As previously discussed, it is Horizon's opinion that areas of the ROW beyond those of the
delineated high probability areas constitute low probability areas for significant cultural deposits
where formal cultural resources investigations are unwarranted.. As such, Horizon recommends
that cultural resources clearance be granted for all low probability areas along the ROW and
that all future maintenance and construction activities within these low probability areas along
the existing ROW be allowed to proceed without further consultation with your office. Only
those areas within the existing ROW delineated as high probability areas will be assessed for
cultural resources by a qualified archeologist prior to any impacts.
On behalf of Magellan Pipeline Company, L.P. (Magellan) and Longhorn Partners Pipeline, L.P.
(Longhorn), Horizon Environmental Services, Inc. (Horizon) is seeking documented consultation
with your office in regard to compliance with Section 106 of the National Historic Preservation
Act (NHPA) of 1966, as amended. Should you concur with Horizon's delineated high probability
hesitate to call me at (512) 328-2430.
areas and recommendations, please sign below. If you have any questions, please do not
1507 South IH 35 * Austin, Texas 78741 * 512.328.2430 * Fax 512.328.1804 * www.horizon-esi.com
CORPORATE HEADQUARTERS
WBE/DBE/HUB Certified

<<<PAGE 629>>>

Howzon.
Environmental Services, Inc.
Sincerely,
Tuss
Browntow
Russ Brownlow, MA, RPA
Principal / Cultural Resources Director
Horizon Environmental Services, Inc.
Concurrence
Date
Enclosures: 1 CD
Cc:
Jeff Blackmore
Project File

<<<PAGE 630>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.0 PIPELINE INTEGRITY ANALYSIS
5.1 INTRODUCTION
Chapter 5 focuses on the current operation, maintenance, and safety controls of the pipeline in
its current state. The focus of Chapter 6 is the potential changes in risk as a result of the
Proposed Project. Many aspects of risk and integrity will remain unchanged under the Proposed
Project.
This analysis relies on the documentation provided by the pipeline operator, including the
Longhorn Pipeline relative risk database, the PHMSA Audits, Operational Reliability Analysis
(ORAs), and the self-audits.
The Longhorn Pipeline System (System) initially transported crude liquids from Crane in West
Texas eastward to markets near Baytown, Texas until 1995. “Longhorn Partners Pipeline, L.P.
(“Longhorn”) was formed in 1995 with the goal of delivering refined petroleum products
(gasoline and other motor fuels) to markets in El Paso, with connections through other pipelines
to New Mexico and Arizona”.
Beginning in 1998, physical conversion began that included construction of pipeline segments
from Crane to El Paso, Crane to Odessa, and other ancillary pipelines and facilities. An
Environmental Assessment of the Proposed Longhorn Pipeline (1999 EA) was published in
2000, with a Finding of No Significant Impact (FONSI) issued by the Environmental Protection
Agency and PHMSA later that year. Further activities and system enhancements designed to
improve pipeline integrity began in accordance with commitments found in the Longhorn
Mitigation Plan (LMP). Operations of the re-structured pipeline system began in January of
2005.
It is useful to understand the history of mitigation and inspection of the Longhorn Pipeline from
November 2000 (FONSI issued) to current. The following is a high-level summary of the
mitigation and inspection of the Longhorn Pipeline.
• March 1999 - Settlement Agreement requires Environmental Assessment, which
ultimately leads to the Longhorn Mitigation Plan
• November 2000 - FONSI issued and LMP published
• 2001 – 2004 Pre-Startup Mitigation Commitment Activities Performed
• January, 2005 - Official startup date for the Longhorn Pipeline System
• February 2007 - High Resolution Magnetic Flux Leakage (HRMFL) in-line inspections
completed for Galena Park to Crane. Electronic Geometry Pig (EGP) inspection
completed in conjunction with HRMFL.
• January 2008 - Transverse Field MFL Inspection (TFI) in-line inspections completed on
Galena Park to Crane. Electronic Geometry Pig (EGP) inspection completed in
conjunction with TFI tool.
• November 2008 - HRMFL in-line inspections completed for Crane to El Paso
5-1

<<<PAGE 631>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• July, 2010 – Ultrasonic Wall Measurement Tool (UT) in-line inspections completed for
Galena Park to Crane. Electronic Geometry Pig (EGP) inspection completed in
conjunction with UT tool.
• November, 2011 – Replacement of approximately six miles of existing pipeline in the
Pedernales River watershed.
Presented herein is an overall summary of the pipeline’s general condition and attributes, as
reviewed in past inspections and tests and review of data associated with inspections and tests
done since 1999. This data is used for determining the structural integrity of the pipeline as well
as the system’s ability to withstand specified operating conditions. This chapter also examines
the pipeline’s leak history, including a review of leak incidents, frequencies, volumes, and
causes.
Design, maintenance, and operation of this system are regulated by PHMSA under 49 CFR Part
195 and the Texas Railroad Commission (RRC) (Tex. Admin Code 16 Part 1 Chapter 8
Subchapter D). Magellan’s System Integrity Plan (SIP) procedures specify the details of all O&M
activities. The procedures found in the Longhorn Pipeline System Integrity Plan (LPSIP) have
been integrated into Magellan’s SIP. LMP Commitments are identified in the SIP as “Assets
covered by the Mitigation Plan”, or the “Mitigation Plan.”
There are 39 Longhorn Mitigation Commitments in the LMP that require Magellan to conduct
inspections and testing that were either in addition to, or more frequent than, those required in
49 CFR Part 195 in the year 2000. These additional measures were expected to result in
increased detection of threats and an improved level of mitigation resulting in increased
assurance of integrity and associated reductions in risk. Although pipeline regulations have
increased significantly since the 1999 EA, some of the LMP provisions are still imposing
requirements that exceed current regulations.
5.1.1 Applicable Regulations
Magellan, as operator of the System, is subject to compliance with 49 CFR Parts 40, 190, 194,
195 and 199 as well as specific requirements within the LMP.
Per the requirements of the LMP and SIP-ADM-14.01 (Appendix 5A), a self-audit is conducted
annually for the purpose of ensuring that the LMP stated plan goals, objective, and
commitments are being met. The recent self-audit reports are available to the public via posting
on Magellan’s website.
Longhorn Pipeline is subject to PHMSA and the Texas RRC inspections. Findings from these
inspections are tabulated in Table 5.1.1-1 cover inspections from April 2005 through Sept 2009.
As an interstate pipeline, the Longhorn Pipeline is regulated by PHMSA. Applicable federal
regulations and other requirements, and guidance are listed and described below.
5-2

<<<PAGE 632>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.1.1.1 Pipeline Safety Regulations
Under Federal regulations, 49 CFR Parts 40, 190, 194, 195 and 199 are applicable to
hazardous liquid pipelines. Part 190 prescribes procedures used by PHMSA for regulating
pipeline safety. The PHMSA enforcement authority and civil and criminal penalties for violating
the Pipeline Safety Act are detailed in this regulation. Part 194 contains requirements for oil spill
response plans to reduce the environmental impact of onshore pipeline oil spills. Part 195
prescribes safety standards and reporting requirements for pipeline facilities used in the
transportation of hazardous liquids. Included in Part 195 are the IMP regulations (49 CFR Part
195.452), established in 2001 after establishment of the LMP. The IMP for liquid pipeline
operators specifies how pipeline operators must identify, prioritize, assess, evaluate, repair and
validate the integrity of hazardous liquid pipelines that could, in the event of a leak or failure,
affect HCAs within the United States. HCAs include population areas; areas containing drinking
water and ecological resources that are unusually sensitive to environmental damage; and
commercially navigable waterways. The rule requires a comprehensive plan to identify HCA’s,
and to assess risk and manage integrity in those areas. A formal and well documented
approach is required in order to effectively meet these newer regulations. Part 199 addresses
the requirements for drug and alcohol testing and references the procedures of Part 40.
5.1.1.2 Longhorn Mitigation Plan (LMP)
An Environmental Assessment (EA) of the Longhorn Pipeline was published in 2000. Following
the assessment, a FONSI was issued by the EPA and PHMSA after execution of the settlement
agreement which resulted in the Longhorn Mitigation Commitments (LMCs) outlined in the LMP.
These mitigation commitments consist of activities and system enhancements designed to
improve pipeline integrity generally over and above regulatory requirements. The LMP is
composed of 40 mitigation commitments and these are summarized in Appendix 9B.
Magellan submits annual reports to PHMSA (per LMC 38) that include information about the
status of mitigation commitments, implementation, the character of interim developments, and
results of any mitigation-related studies and analyses. The reports also summarize
developments related to its Operation Reliability Assessment (ORA). These reports are made
available to the public via Magellan’s internet website. Per LMC 39, any changes or
modifications proposed by Magellan to the LMP for the purpose of adapting to changing
technology and circumstances are made available to the public (and the mayors of Houston,
Austin, and El Paso, and the General Manager of the LCRA) at the time it is submitted to
PHMSA for approval and written concurrence.
5.1.1.3 National Oil and Hazardous Substance Pollution Contingency Plan
EPA regulations in 40 CFR Part 300 provide an organizational framework and procedures for
preparing to respond to discharges of oil and accidental releases of hazardous substances into
locations which present danger to public health or welfare. The document specifies
responsibilities among federal, state, and local regulatory agencies during an emergency
response. It establishes requirements for federal, regional, and area emergency response plans
5-3

<<<PAGE 633>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
and addresses procedures for the response of other persons as well. This document also
provides response plans per Comprehensive Environmental Response, Compensation, and
Liability Act requirements.
5.1.1.4 Spill Prevention, Control, and Countermeasures Plan (SPCC)
EPA regulations in 40 CFR 112 and Texas Commission on Environmental Quality (TCEQ) Spill
Prevention and Control (Chapter 327) include requirements for oil spill prevention,
preparedness, and response to prevent oil discharges to navigable waters and adjoining
shorelines. The rule requires specific facilities to prepare, amend, and implement SPCC Plans.
The SPCC rule is part of the Oil Pollution Prevention Regulation, which also includes the Facility
Response Plan (FRP) Rule.
5.1.1.5 Hazardous Waste Operations and Emergency Response (HAZWOPER)
OSHA regulations found in 29 CFR Part 1910.120 cover HAZWOPER activities. Hazardous
waste activities include clean-up operations required by a governmental body involving
hazardous substances at uncontrolled hazardous waste sites, corrective actions involving clean-
up operations at Resource Conservation and Recovery Act sites, voluntary clean-up operations
at sites recognized by governmental bodies as uncontrolled waste sites, and operations
involving hazardous wastes at treatment, storage, and disposal facilities. Emergency response
operations for releases of hazardous materials comply with requirements of paragraph (q) of
this regulation.
5.1.1.6 Transportation Security Administration (TSA) Pipeline Security
In April 2011, TSA Pipeline Security Division updated the TSA Pipeline Security Guidelines
which provide recommendations for pipeline industry security practices. These updated
guidelines incorporate changes to the DHS threat advisory system and supersede the 2002
DOT Pipeline Security Information Circular and the related Pipeline Security Contingency
Planning Guidance. Magellan participates in the TSA Corporate Security Review (CSR)
Program conducted by the Pipeline Security Division. The CSR Program is an on-site security
review with a pipeline company. CSRs help establish working relationships with key security
representatives in the pipeline industry as well as provide TSA with a general understanding of
a pipeline operator's security planning and implementation. Data obtained from CSRs aid in
establishing a baseline against which to evaluate minimum security standards in the pipeline
industry and identify coverage gaps. CSRs help to identify and share best practices observed
throughout the industry.
5.1.2 Information Analyzed
Magellan provided data for the operational years since the 1999 EA. These documents include
results from the recent In-Line Inspection (ILI), cathodic protection (CP) surveys, self-audit
reports, ORAs, regulatory audit reports, leak history, and other documents.
5-4

<<<PAGE 634>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
In assessing the pipeline integrity for the current FEA, additional inspections and audits were
not necessary for several reasons:
• Use of well-documented, recent inspections, even if conducted by the company being
audited, is a well-established protocol in regulatory auditing.
• Specialized, independent, and often “certified” third-party pipeline service companies
often prepared inspections and reports.
• The PHMSA audits can be relied upon as indications as to whether regulatory and LMCs
are being carried out since these audits are thorough, non-biased, and performed by
trained auditors.
• The ORAs and Self Audits can be relied upon as accurate data since they are performed
by reputable, independent pipeline experts with standing credentials.
5.1.2.1 Key Documents
Key documents that form the basis of the data presented here include:
• System Integrity Plan (SIP) (2011)
• Longhorn Pipeline System Integrity Plan (LPSIP)
• Longhorn Mitigation Plan (LMP)
• Final Longhorn Environmental Assessment (1999 EA)
• Longhorn Mitigation Plan progress reports
• Operational Reliability Analyses (ORA) from 2005 to 2009
• Proposed hydraulic profiles
• In-Line Inspection (ILI) anomaly lists
• Longhorn self-audits
• Facility Response Plans (FRPs)
• Det Norske Veritas (DNV) reports on ILI
• Process Hazard Analysis (PHA) reports from facilities
• Surge analyses
• Hydraulic profile graphics
• Scenario Based Risk Mitigation Analysis (SBRMA) - qualitative review with action plan
generation, used as continuation of Relative Risk Assessment (RRA) (per Section 3.5.10
of the LMP)
• Facility Risk Assessment - RRA for facilities
• Relative Risk Assessment (RRA) Manual
These documents include hundreds of pages of materials. Experienced subject matter experts
(SMEs) have reviewed all documents listed as part of regular ongoing integrity management
activities.
5-5

<<<PAGE 635>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.1.2.2 Databases
Recent inspection, survey, and test data is critical in assessing current pipeline conditions. Key
databases provided by Magellan include:
• Linefill – General pipe specification information including pipe diameter, wall thickness,
and grade
• Maximum Operation Pressure (MOP) Calculations
• Documentation of Repairs, (i.e. Pipeline Maintenance Reports and Correlation Reports)
• ILI vendor reports
• Potential spill volume calculations
• Pipeline depth of cover (DOC) survey reports
• Pipeline Relative Risk Assessments (RRA)
Results from integrity assessments, ILI and pressure tests, are used to characterize the pipe
wall with regards to past damages and certain feature types. Results also provide insights into
aggressiveness of exposure and effectiveness of mitigation, although the relative role of each
independently is often not discernible.
Magellan has procedures in place to integrate ILI information and to determine appropriate
responses.
5.2 CONSTRUCTION/EXISTING SYSTEM
The present and future condition of the Longhorn Pipeline is influenced by the original
construction and present O&M. This section examines the attributes and conditions of the
system based on available data and information. These attributes and conditions are relevant
for assessing risks in Chapter 6 and potential impacts analyzed in Chapter 7. Attributes such as
age, type of pipe, results of inspections and tests, in combination with O&M procedures and
mitigation measures (see Chapter 9), influence the integrity of the system.
5.2.1 General Attributes
The Longhorn Pipeline consists of various segments installed at different times, as described in
Chapter 3 of the 1999 EA. Most of the pipeline between Galena Park and Crane was built
between 1947 and 1953. Short sections were replaced as needed over the years. The 18-inch
pipeline connecting Crane to the El Paso Terminal was built in 1998, as was the 8-inch lateral
from Crane to Odessa. A new 9.1-mile section of 20-inch pipeline between the Galena Park
Station and the existing pipeline was installed in 1998.
The age and basic pipe characteristics of major sections of the pipeline, between the Galena
Park and El Paso are summarized in Table 5.2.1-1. The age of the pipeline is a factor in the
integrity evaluation because of the potential for deterioration if the pipeline was not adequately
maintained, and because of the potential issues associated with era of manufacturing and
5-6

<<<PAGE 636>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
construction practices. The direct effects of age on physical condition and pipe properties are
discussed later.
An overview of construction specifications utilized during original construction is provided in
Table 5.2.1-2. The table also provides specifications utilized by Williams as part of the
construction to convert the line to refined product service. In general, the specifications for
installation in recent years are more stringent and more detailed than the 1949 specifications.
This is relevant since some older features still exist in the current pipeline or influence the
probability of integrity issues. Some key differences are:
• The level of detail of the pipeline material specifications has increased.
• Minimum depth of cover and vertical clearance requirements have increased and new
requirements have been added (for example, at road crossings).
• Coating type has changed from coal tar enamel to fusion-bonded epoxy for new
construction.
• Field-applied coating at girth welds has changed.
• Welding requirements and techniques have changed.
• Hydrostatic testing pressure requirements have increased 55%, and test duration has
doubled.
• No CP was required in 1949; but now exists across the System.
Integrity Management activities and programs specified within the SIP that incorporate LMP and
49 CFR Part 195 requirements are designed to manage any integrity threats associated with
previous construction practices and material utilized.
5.2.2 Effects of Age
Age alone is not a reliable indicator of pipeline integrity as some pipelines have been in good
operating condition for more than 80 years.
Possible threats to pipeline integrity are not necessarily strongly correlated with the passage of
time, although the “area of opportunity” for something to go wrong obviously does increase with
the passage of time. Experts believe that there is no effect of age on the microcrystalline
structure of steel such that the strength and ductility properties of the pipe are adversely
affected.
The primary time-dependent phenomena are the potential for corrosion and for crack growth.
Therefore, the ways that the age of a pipeline can influence the potential for failures are through
corrosion, fatigue, environmental atmospheric corrosion (EAC), and possibly through
vulnerabilities introduced by older manufacturing and construction methods. These age effects
are well understood and once identified, mitigation can be applied that counteract these threats
with a degree of confidence. Magellan’s Operational Reliability Analysis (ORA) program is
designed to specifically address fatigue and other age related concerns.
5-7

<<<PAGE 637>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.2.3 Manufacturing and Construction Methods
Steelmaking technology, pipe manufacturing technology, coating technology, and construction
technology have all made significant advancements over the years. Table 5.2.1-1 shows pipe
specifications as provided in Magellan’s database. Manufacturing longitudinal weld seam
defects can lead to preferential corrosion or cracking of the seam. Any manufacturing defects
are evaluated through existing SIP inspection and mitigation procedures. The older portions of
this Longhorn Pipeline appear to have been manufactured and constructed with the best
practices of the time.
A higher susceptibility to certain failure mechanisms has been identified in older electric
resistance welding (ERW) and electric flash welded (EFW) pipe. This applies to pipe
manufactured with a low-frequency ERW process, typically seen in pipe which was
manufactured prior to 1970, or in an electric flash weld pipe made by A.O. Smith between the
years of 1930 and 1969 (History of Line Pipe Manufacturing in North America, J.F. Kiefner,
1996). On the Longhorn Pipeline, over 50% of the pipe was manufactured by either this low-
frequency ERW process or the EFW process.
ERW/EFW manufacturing creates a longitudinal weld seam in the pipe wall. Flaws that may
threaten the integrity of these weld seams have been identified as:
• Lack of fusion;
• Hook cracks;
• Nonmetallic inclusions;
• Misalignment;
• Excessive trim;
• Fatigue/corrosion fatigue;
• Selective corrosion (crevice corrosion);
• Hard spots; and
• Fatigue at lamination3/seam interface.
These mechanisms, failure databases, and supporting metallurgical investigations are more
fully described in technical literature references (DOT, 1989; Fields, 1989). Since 1970, the
conversion by pipe manufacturer to high-frequency ERW techniques along with improvements
in quality control has resulted in a more reliable weld seam. The integrity of low-frequency ERW
seams is evaluated through in-line inspection techniques that orient magnets to allow detection
of longitudinally oriented metal loss and cracks in the seam weld. These tools commonly
referred to as TFI tools were utilized on the Longhorn Pipeline system from Galena Park to
Crane in areas where older low-frequency ERW seams exist. These inspections and
subsequent remediation techniques are discussed further in later sections.
3 Laminations are metal separations occurring in the wall of the pipe, produced during the pipe manufacturing
process.
5-8

<<<PAGE 638>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Construction techniques have advanced. Newer pipelines benefit from better bending practices,
welding technologies (sometimes mechanically automated), inspection technologies, better
quality control practices, boring and drilling techniques, and typically deeper burials. Therefore,
with respect to advancements in technologies, it is not the passage of time that causes a threat,
but the recognition that older pipelines could have issues associated with the manufacturing and
coating processes based on the pipe vintage and the construction techniques employed.
Construction specifications are shown in Table 5.2.1-1. Pipeline defects or weaknesses that
may be inherent in older pipeline are detected through a combination of in-line inspections or
cathodic protection surveys. In-line inspection techniques can detect areas of metal loss caused
by poor coating quality or pre-mature deterioration. Depth of Cover Surveys can identify areas
that were initially laid to depths that could present an integrity issue today.
Similar to the discussion on pipe manufacturing techniques, the methods for welding pipe joints
have improved over the years. Girth welds today must pass a more stringent inspection than
welds from the original construction of the pipeline. Standards of acceptability of girth weld
imperfections have changed. Welding standards such as API 1104 (incorporated by reference
into 49 CFR Part 195) specify additional and different potential weld defects to be repaired than
the standards from 1950. However, some welding specifications and options for welder tests
were a part of the original Humble Oil Company construction specifications for the subject
pipeline. Pressure testing conducted as part of the pre-startup mitigation activities from 2000 –
2004 was designed to detect any injurious defects such as girth weld defects that could lead to
future integrity issues.
Arc burns, created during welding, are of concern due to the possibility of small cracks forming
around the “hard spot” which might be created from the arc burn. Identified arc burns are to be
repaired as required by the SIP. The TFI tool inspections were designed to detect cracks. All
cracks and crack-like indications were repaired following completion of the inspection.
A concern investigated in 1999 EA was the potential existence of non-steel components in the
older portions of the pipeline. Specifically, the possible use of cast-iron type materials, which are
weaker than steel, was investigated. Valves and pumps were refurbished prior to startup by a
national contractor specializing in such activities for the pipeline industry. No non-steel
components were identified.
5.2.4 Countering Age Effects
Potential effects of age are countered through a formal integrity management program, which
exists in the form of the SIP (which includes the LMP). This program includes practices for
identifying weaknesses in materials, flaws in damage prevention programs, and specifying
appropriate responses. Future inspection and testing is driven by the ORA. If the potential age-
related effects are properly controlled, the design life of pipeline steel is considered indefinite.
5-9

<<<PAGE 639>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.2.5 Maintenance Repairs and Rehabilitation
The major maintenance activities conducted on the System consist of repairs or replacement of
the following:
• CP system rectifiers and electrical circuitry;
• Test leads attached to the pipe;
• Casings and casing/pipe electrical isolation for road and railroad crossings;
• Pipe protective coatings, including paint on aboveground pipe and components;
• Pipe segments;
• Block and check valves;
• Pressure and temperature sensors;
• Pipe bridge supports for elevated stream crossings; and
• Pump station equipment, including pumps, valves, pipe and fittings, instrumentation,
controls, and tanks.
Magellan, as directed by the LMP, conducted numerous mitigation and rehabilitation projects
along the Longhorn Pipeline. These projects, known as Longhorn Mitigation Commitments
(LMCs), are summarized in Appendix 9B. LMC 3 required the replacement of approximately 19
miles of the existing pipeline over the Edwards Aquifer Recharge and Contributing zones in the
Austin area with thick walled pipe; the pipe was buried to a minimum depth of 5 feet and
protected by a concrete barrier cap. The pipe replacement included a segment over a three-mile
reach of the Edwards Aquifer Recharge Zone, a segment east of the Edwards Aquifer Recharge
Zone, and across the Edwards Aquifer Contributing Zone (approximately from MP 185.6 to MP
188.8) to the boundary of the Barton Creek Watershed. This measure was completed prior to
startup of the System (2005).
Per LMC 5, shallow or exposed pipe at 12 locations (including Marble Creek) was mitigated.
Certain sites listed in the LMP occurred within the Edwards Aquifer Recharge and Contributing
Zones (see above). The Marble Creek crossing was refurbished and replaced with new pipe.
This measure was completed prior to startup (2005). As detailed in Appendix 9B, per LMC 6,
various stopple fittings were removed prior to startup.
Per LMC 7, pipe at two locations, near Satsuma Station and in Waller County were replaced as
indicated by the 1995 ILI. This measure was completed prior to startup.
Per LMC 8, pipe at the Rabb’s Creek crossing was replaced and appropriate repairs were made
at five dent locations identified by the 1995 ILI. This was completed prior to startup.
Per the LCRA Settlement Agreement, and LMC 3, Magellan replaced approximately six miles of
existing pipeline in the Pedernales watershed that is characterized as having a time of travel for
a spill from Lake Travis of eight hours or less. The pipeline segment replacement crossing the
Pedernales River was completed prior to startup. Horizontal directional drill construction
methods were used to install the section of pipe under the Pedernales River.
5-10

<<<PAGE 640>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.2.6 Facilities
5.2.6.1 Tanks
All tanks and related equipment are required to be constructed in accordance with industry
standard American Petroleum Institute 650—Welded Steel Tanks for Oil Storage; American
Petroleum Institute 651 – CP of Aboveground Petroleum Storage Tanks; American Petroleum
Institute 2000 – Venting Atmospheric and Low Pressure Storage Tanks; American Petroleum
Institute 2003 – Protection Against Ignitions Arising Out of Static, Lightning, and Stray Currents;
American Petroleum Institute 2350 – Overfill Protection for Storage Tanks in Petroleum
Facilities; and National Fire Protection Association (NFPA) 30 – Flammable and Combustible
Liquids Code. The main purpose of the Tank Maintenance Inspection Program is to inspect all
tanks in accordance with American Petroleum Institute 653 inspection requirements and make
recommendations on necessary repairs to ensure the integrity of the tanks. Under PHMSA tank
rules, an annual inspection is required.
PHMSA (as part of its responsibilities under 49 CFR Part 195) periodically audits the
performance of Magellan’s tank maintenance program. PHMSA previously identified
deficiencies were corrected in a timely manner. No unresolved issues remain from past audits.
5.2.6.1.1 External or In-Service Inspections
All tanks are given a visual external inspection by an inspector certified in American Petroleum
Institute 653. This inspection is conducted at least every five years or at the quarter corrosion
rate life of the shell, whichever is less. The inspection includes a survey of the tank for
settlement activity, measurement of the shell thickness for corrosion, inspection of vents,
inspection for tank shell damage, floating roof inspection, fixed roof inspection, etc. The
inspection is performed by an American Petroleum Institute 653 certified inspector and
documented on an In-Service Inspection Form. The forms are retained in the records of the
Tank Maintenance Department.
5.2.6.1.2 Internal or Out-of-Service Inspection
All tanks are given a formal internal inspection to ensure the integrity of the tank bottom. This
inspection is initially conducted after ten years of operation. Subsequent inspections are
established in accordance with American Petroleum Institute 653. The inspection is performed
by inspectors certified pursuant to API 653 and documented on an Out-of-Service Inspection
Form. A copy of the documentation is retained in the Tank Maintenance Department’s records.
5.2.6.2 Pump Stations
Pump stations and valves are part of the System and significant to System integrity. The factors
affecting the integrity of the existing pump stations and mainline valves on the pipeline from
Galena Park to Crane are discussed and described in this section. Pump stations and valves
5-11

<<<PAGE 641>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
are discussed separately from the pipe portions of the pipeline. They consist of equipment items
and configurations that can be examined individually to evaluate their integrity and potential risk.
The purpose of pump stations along the pipeline is to provide the driving force to maintain liquid
product flow at a desired flow rate through the pipeline. Pump stations are located along the
pipeline at distances that are primarily determined by the pipeline elevation profile, the product
characteristics, and the desired product flow rate. The liquid product enters each station at a
relatively low pressure, and the pressure is increased through the station pumps.
Currently there exist four pump stations from Galena Park to Crane. In a pump station, the
product enters from the upstream side of the station and passes through a strainer to remove
any entrained particulate matter. The product then passes successively through the two pumps
in series where the pressure is increased to the level needed to maintain the desired flow rate to
the next downstream pump station. The pressure at the outlet of the second pump is regulated
by a pressure control valve to prevent excessively high pressure in the pipeline. The outlet
pressure is regulated at or below the MOP.
Check valves in each pump bypass line and in the mainline bypass line prevent recirculation or
reverse flow of the product back through the pipeline in the event of a pump shutdown or valve
closure. These check valves also permit the product to bypass either or both of the pumps.
Other major equipment present at some or all of the pump stations include relief and storage
tanks, booster pumps, scraper (pig) launchers and receivers, meter provers, pressure relief
tanks, and sump tanks. Scraper launchers and/or receivers are installed at eight sites. These
launchers and receivers are used for pigging.
All of the pumps are centrifugal models equipped with single mechanical seals. The pumps are
all driven by weather-protected Type II electric motors. The electrical systems and circuits are
designed to meet or exceed National Electric Code and Underwriters Laboratory specifications
to protect against ignition in hazardous atmospheres.
Most of the valves of interest to System integrity are large block or control valves in the size
range of 10 to 20 inches. There are also a number of small valves, usually one inch or less in
size, associated with instrumentation, and particularly, with thermal safety valves (TSVs). TSVs
are installed on any segment of pipe in liquid service that could be blocked in under any
circumstance. A blocked-in segment of line could be heated by the sun, ambient air, or other
sources. The liquid within the pipe segment could expand and, without the TSVs, could cause
the pipe or associated valves to rupture. Pressure due to liquid expansion causes a TSV to
open and drain liquid to the sump tank, thus preventing damage and a possible release of
product.
5.2.6.3 Mainline Block Valves
There are both block and check valves located on the Longhorn Pipeline. Block valves are
located at pump stations and other strategic points along the pipeline. Block valves are placed
to minimize draindown during maintenance and to minimize potential spill volumes. Check
5-12

<<<PAGE 642>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
valves prevent back flow and draindown in the event of an upstream failure or a flow reversal.
The characteristics and locations of these valves are described and discussed in this section.
Also presented are estimated maximum leak/spill volumes for selected sensitive locations.
The location and types of mainline valves on the existing Longhorn Pipeline are listed in Table
5.2.6-1 and illustrated on the valve schematic contained in Appendix 5B. The valves on the
section of the pipeline between the Galena Park and Satsuma stations are 20 inches in
diameter. The mainline valves located west of Satsuma Station are 18 inches in diameter. All
valves are constructed of steel and have an ANSI rating of 600. The valves are manufactured
by companies such as Daniels, Cooper, WKM, US Steel, and Kerotest. Closure time for the
remotely controlled block valves ranges from 90 seconds to 3.2 minutes depending on supplier
and model (Willbros, 1998). Closure rates have implications for surge potential. Risk and
evaluation of future surge potential is discussed in Section 6.2.1.3.
The mainline valves are installed in locations that can isolate the pumping stations, protect
certain environmentally sensitive areas, or isolate sections in long segments of the pipeline
unbroken by pumping stations. There are remote-controlled valves on the eastern (currently
upstream) side of several environmentally sensitive area crossings. In the current configuration,
these valves were often paired with a check valve and a manually operated valve on the
downstream side of the crossings. In the event of a pipeline leak in the sensitive areas, valves
can prevent additional drainage from upstream and downstream sections of the pipeline into the
sensitive areas, when such valves are closed in a timely manner.
Prior to start-up and per LMC 22, a study was conducted to quantify the benefits of additional
check valves. The Valve Study was performed by APR Companies and included
recommendations for the installation of seven (7) additional check valves.
Additionally per the LCRA Settlement agreement, nine additional check valves and two valves
were relocated at locations through the Colorado, Pedernales, Llano, and San Saba River
Basins to limit maximum drain down volumes. Table 5.2.6-2 illustrates valves installed per LMC
22 and the LCRA Settlement agreement. These valves were installed to minimize drain down
and the potential consequences of a leak. Table 5.2.6-3 illustrates potential maximum release
volumes under the Proposed Project.
5.3 NORMAL OPERATIONS
PHMSA regulations require that liquid pipeline companies prepare and follow a manual of
written procedures for conducting normal operations and maintenance activities and for
managing abnormal operations and emergency situations. Operation and maintenance of the
System follows the guidelines set forth in the SIP. The SIP incorporates PHMSA, OSHA, EPA,
and company requirements. The procedures found in the Longhorn System Integrity Plan
(LPSIP), which are documented in the LMP has been integrated into the SIP Procedures.
Surveys and studies that were performed in advance of the 1999 EA include:
5-13

<<<PAGE 643>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Depth-of-Cover Survey
• Exposed Pipe Survey
• CP/CIS
• Seismic activity
• Scour, erosion, flood potential at selected stream and river crossings
• Span evaluations
• Landslide potential
• Root cause analyses
These analyses provided data for Longhorn’s Risk Assessment and Integrity Management
Programs. They also provide Magellan with data to design and implement corrective actions
and to identify and resolve potential issues. Updates to these investigations are on-going as is
evidenced in relevant procedures in the SIP and their inclusion in the annual ORAs. The
procedures processes, programs within the SIP are designed to mitigate threats associated with
the following:
• Commodity Characteristics
• Internal Corrosion
• Hydrogen Blistering
• Surge and Hydraulic Profile
• Cracking
• Stress Corrosion Cracking
• Incorrect Operations
• Security
• Atmospheric Corrosion
• External Corrosion
• Third Party Damage
• External Forces
5.3.1 Threats
5.3.1.1 Commodity Characteristics
The pipeline system currently transports refined petroleum products (e.g. gasoline and
distillates) which the following programs are designed to address.
5.3.1.2 Internal Corrosion
Magellan’s Corrosion Control Program (SIP-ADM 7.04–001) in Element 7 of the SIP (Appendix
5A) contains procedures for addressing internal corrosion and for compliance with 49 CFR Part
195.579.
Mitigation includes running cleaning pigs twice a year or more often as needed in refined
product service to remove corrosive components and free water. Corrosion inhibitors are
5-14

<<<PAGE 644>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
injected at product origins to mitigate any corrosive effects of the product. Corrosion coupons or
other types of monitoring are used to determine the effectiveness of the inhibitor and the
potential extent of any corrosion. At least three times each calendar year, and not exceeding
intervals of 4.5 months, corrosion coupons are removed from the test locations and forwarded to
an appropriate laboratory for corrosion analysis. Coupon corrosion rates over 1 mpy of general
corrosion or pitting (including MIC) trigger a detailed analysis directed by NACE certified
corrosion control personnel. This analysis includes a review of incoming product quality sample
data, inhibitor injection rates, bacteria testing and, if necessary, inhibitor performance testing.
Deficiencies are required to be resolved within six (6) months of discovery, except those that
present a more urgent threat to pipeline integrity are corrected immediately.
As discussed in Section 5.3.5, Magellan has conducted inspections utilizing three different types
of intelligent in-line inspection tools (ILI) to detect and subsequently mitigate any affects of past
damages caused by internal corrosion. Table 5.3.1-1 provides details of the inspections
conducted and Table 5.3.1-2 provides details of the findings and subsequent repairs made to
each segment of the system.
Results from a 2007 in-line inspection of the Crane to El Paso segment revealed internal
corrosion damages along portions of an 84-mile portion of the line. Forty-two miles of that
segment had damages severe enough to warrant immediate pressure reduction and eventual
pipe replacement. This finding was unexpected based upon the fact that the pipe was relatively
new having been installed in 1998. There was no evidence that this internal metal loss damage
occurred during operation of the pipeline since startup in 2005.
Magellan engaged expert consultants to evaluate the corrosion. Potential for MIC, an often
accelerated corrosion rate mechanism, was identified. The investigation revealed that the
corrosion damage most likely occurred due to initial hydrostatic test water that was allowed to
remain in the pipe in low lying areas. Bacteria grew in this water and ultimately caused MIC.
Since the pipeline was not commissioned until years later severe internal corrosion occurred.
Proper drying and conditioning of the pipe would have most likely prevented this damage.
Magellan modified pressure testing procedures to heighten awareness that extensive corrosion
can occur following hydrostatic testing. UT inspections were conducted on a quarterly basis
from 2007 to 2011 at two locations along the 42-mile segment. No measurable corrosion growth
was detected in this process.
5.3.1.3 Hydrogen Blistering
A hydrogen blister is defined as a bulging of the internal or external pipe wall from the
accumulation of hydrogen pressure within a lamination or inclusion in the pipe wall. This
pressure is sufficient to deform the pipe wall locally. Cracking can occur if the pressure-induced
stresses are high enough.
A lamination is defined as a plane of non-fusion within the steel plate that occurs during the
manufacturing process. The lamination can be parallel to the inner and outer surfaces of the
5-15

<<<PAGE 645>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
pipe, inclined or sloping with respect to the inner and outer pipe surfaces. A lamination can also
be surface breaking or can occur in a stepwise manner through the wall thickness. If pipe wall
bulging is present at a lamination, it is considered a hydrogen blister.
The history of the 20 inch and 18 inch pipe previously in crude oil service prior to 1995 (valve J-
1 at MP 9.1 to Crane) indicates that no pipe lamination or hydrogen blister failures occurred
during service. However, hydrostatic testing prior to start-up in 2005 indicated the presence of
pipe laminations and hydrogen blistering at pipe laminations in the 18 inch segment from
Satsuma to Crane. The possibility of existing blisters represents a potential anomaly for the
Longhorn Pipeline system that could be adversely affected by pressure cycle induced fatigue
discussed further in Section 5.3.1.5. To mitigate the threat of existing blister growing in service
due to pressure cycle fatigue cracking, LMC 12 required an in-line inspection of the existing
pipeline from Galena Park to Crane with an ultrasonic (UT) wall measurement tool. The results
of this inspection are further discussed in Section 5.3.5.2.
The re-introduction of sour crude oil to the pipeline present a new threat of laminations growing
into hydrogen blisters. This new threat as a result of the Proposed Project is further discussed in
Section 6.3.1.2.
5.3.1.4 Surge and Hydraulic Profile
The pressures generated by pumping (including flow resistance) and the pressures created by
topography (elevation) effects combine to form a hydraulic profile. Pressures are controlled to a
level at or below MOP under normal operations.
Surge pressures are created when a moving fluid is suddenly brought to a halt. The kinetic
(moving) energy is converted to potential energy, resulting in an increase in pressure and the
creation of a pressure wave. In a fluid-filled pipeline, a positive pressure wave is propagated
upstream of the point where the fluid flow is interrupted. Flow interruptions in a pipeline are
usually due to valve closures or pump shutdowns. A negative pressure wave travels
downstream from the point of interruption. The pressure can decrease below the vapor pressure
of the liquid, and some of the liquid can vaporize, forming vapor cavities. Each cavity may be
large enough to separate the liquid into two segments. When the pressure in the system
equalizes, the vapor cavity will collapse. The velocities of the liquid can be very high during
these collapses, producing a significant pressure wave.
Applicable sections of 49 CFR Part 195 prohibit operating pressures from exceeding 110% of
MOP during surge or abnormal operating conditions. The LMP specifies that the normally
allowable temporary exceedance of MOP under surge conditions not be allowed to occur in Tier
3 (hypersensitive) areas. This means that in those areas, surge pressures are controlled to a
level lower than in other segments of the System and also below common industry practice.
Per LMC 31, Magellan performs a surge pressure analysis prior to any change in the system
that has the capacity to cause surge pressure to occur on the system. Magellan is required to
submit mitigation measures acceptable to PHMSA prior to any such change in the system.
5-16

<<<PAGE 646>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Submitted mitigation measures must adequately address any maximum allowable surge
pressures on the system identified by the surge pressure analysis.
Magellan follows 49 CFR Part 195 in determining MOP as the minimum of the following:
• The maximum internal pressure that does not generate stresses in excess of 72% of
pipe yield
• 80% of the minimum test pressure
• Component pressure rating OR 80% of the factory test pressure or prototype test
pressure of a component
Magellan’s processes related to safe pressures are designed to ensure that pressure containing
capabilities for all pipe conditions as identified by ILI tools or integrity tests are documented and
compared to safe allowable operating pressure to ensure that such features are not over
pressured.
Discharge pressure of operating pump stations are set to ensure that 100% of MOP is not
exceeded during normal operating conditions for any portion of the line. Surge pressure
analyses are completed to ensure that for worst-case operating conditions, surge pressure can’t
exceed the limits as defined within the LMP. This calculation is completed on 07-FORM-0746.
Upon completion of an integrity assessment, an analysis is completed for all metal loss
anomalies with Rupture Pressure Ratio (RPR) less than 1.00 to identify the discrete point
pressures of the anomaly (DPP, PDPP) per 7.03-ADM-007, ILI Analysis Guidelines (Appendix
5A). An RPR equal to 1.0 corresponds to a predicted burst stress equal to the Specified
Minimum Yield Strength of the pipe. This analysis takes into account discharge pump station set
points, elevation differences, and surge conditions to determine the maximum pressure
achievable at each specific defect location. For each feature location the design pressure for the
line and the upstream pump’s maximum discharge set point is determined. The maximum
elevation difference between the pressure source and the feature location combined with the
specific gravity of heaviest product is utilized to determine the static head pressure due to
elevation change. The calculated static head pressure is then added to the pump set point to
get maximum pressure at the feature location due to static head. A surge analysis is then
conducted for the feature location to determine maximum pressure due to surge. The static
head and surge maximum pressures at each feature location are then compared. The engineer
will then select the greater value to determine the maximum pressure at each location. This
value is used as PDPP for the anomaly location. Any feature with a calculated remaining
strength or burst pressure (PBURST) less than PDPP is repaired as an immediate condition.
Additionally any feature with a PBURST multiplied by 72% (PSAFE) less than PDPP is repaired
as a 180-day condition.
This procedure is repeated for any unrepaired features when an operating pressure increase is
considered in accordance with 7.07-ADM-002 (Appendix 5A). Any features that require repair
are mitigated prior to the pressure increase.
5-17

<<<PAGE 647>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.1.5 Cracking/Fatigue Monitoring
Fatigue, caused by cycles of applied stress, can result in crack initiation, activation, and
propagation. Internal pressure fluctuations during pipeline operation over long periods of time
are the main source of fatigue for most pipelines. Non-service-related fatigue loadings (such as
traffic over roadway crossings) are normally of minor magnitude and are not typically thought to
contribute significantly to fatigue stresses except in special circumstances.
Fatigue effects can be predicted and, therefore, controlled to a large extent. Material selection,
pressure testing, load cycle monitoring, and ILI with crack detection tools are the primary means
by which fatigue failures are prevented.
Manufacturing defects in or immediately adjacent to the longitudinal ERW or EFW seams of the
1950 line-pipe material are a source of seam cracks. These defects that may be initially too
small to fail at the operating or test pressures will grow through fatigue cracking driven by
pressure cycling and become large enough to cause a failure if exposed to sufficient numbers of
large pressure fluctuations.
The ORA Process Manual requires monitoring of pressure cycles during the operation of the
pipeline, calculating the worst-case crack growth in response to the pressure cycles, and
reassessing the integrity of the pipeline at appropriate intervals to find and eliminate growing
cracks before they become large enough to cause a failure of the pipeline. Table 5.3.1-3 shows
results of calculations from the 2010 ORA which identified the shortest time to failure of 92.1
years for Case 7 for the section of pipe from MP 295.2 to 405.1. Cases 4 and 6 are the only two
other sections which show reassessment intervals less than 100 years.
In accordance with LMC 10, Longhorn conducted an ILI and subsequent remediation with a TFI
tool designed to detect cracks and other manufacturing defects in the longitudinal seam weld.
These inspections were completed by January 2008. In accordance with LMC 12, Magellan
conducted an ILI and subsequent remediation of the existing pipeline from Galena Park to
Crane with an ultrasonic (UT) measurement tool. These inspections were completed by July
2010. The UT tool is designed to detect laminations and blistering of laminations which can lead
to cracking.
5.3.1.6 Stress Corrosion Cracking (SCC)
Modification to pressure cycle frequencies and intensities affects the threat of SCC. It is prudent
to retain SCC as a possible threat. Magellan conducts Non-Destructive Examination (NDE) to
examine for the presence of SCC through magnetic particle inspections. Magellan has not
detected any indications of SCC.
5-18

<<<PAGE 648>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.1.7 Incorrect Operations
As part of LMC 3.5, the incorrect operations mitigation program focuses on design, construction,
maintenance and operations to reduce the likelihood of human error. Incidents are tracked and
discussed to identify opportunities for improvement.
5.3.1.8 Security
Magellan’s existing procedures include provisions to address appropriate security measures as
defined in SIP-ADM-8.01 (Appendix 5A). This initiative provides a framework that complies with
the security regulations to protect the assets, employees, the environment, stakeholders, and
the community from security threats.
5.3.1.9 Atmospheric Corrosion
A relatively slow rate of metal loss is normally associated with atmospheric corrosion. The ability
to inspect most exposures reduces threats to integrity from this failure mechanism. Experience,
however, indicates that certain areas require special inspections to monitor corrosion. These
areas include casings, splash zones, insulation, below-grade chambers, and supports.
Preventative measures most often employed are the application and maintenance of a
protective paint coating. Magellan’s corrosion procedures are provided in SIP-ADM-7.04
(Appendix 5A), and contain special procedures to address these areas. The atmospheric
corrosion procedures require Magellan to:
• Identify all above grade and above water line structures/facilities or parts of
structures/facilities as subject for atmospheric corrosion inspection.
• Evaluate all facility above ground structures every year or more often as needed. This is
3 times the frequency required by regulation. Evaluate utilizing the SSPC-VIS-2;
Standard Method for Evaluating Degree of Rusting on Painted Steel Surfaces, General
Rusting Standard. Particular attention is given to pipe and soil to air interface areas,
under thermal insulation, under disbonded coatings, at pipe supports, in splash zones, at
deck penetrations, and in spans over water.
• Maintain a listing of all subject areas, including GPS coordinates, and updated as
needed in the CP Data Manager.
• Some structures/facilities with corresponding inspection requirements are:
- Pump stations, measuring stations, storage vessels and tankage, and miscellaneous
facilities (building, structure, piping and equipment);
- Initially buried pipe or related facilities now exposed to the atmosphere due to
intentional or unintentional reasons (i.e., erosion, subsidence, etc.);
- Pipe spans (supported and unsupported);
- Suspension bridges (piping and structure);
- Above-grade pipeline valves, expansion loops, and associated piping;
5-19

<<<PAGE 649>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
- Below-grade facilities in casings, vaults, or ‘cans’ (corrugated metal valve chambers,
etc.); and
- Some valves on the System are located in below ground chambers which can have
higher corrosion potential due to alternately wet-dry conditions.
5.3.1.10 External Corrosion
The corrosion control program, as further detailed in the System Integrity Plan (SIP), provides
for ongoing maintenance and evaluation of corrosion. The program addresses the monitoring
and mitigation of special forms of corrosion such as microbiological induced corrosion (MIC),
alternating current (AC) induced, stray current, selective seam corrosion, stress corrosion
cracking (SCC), internal corrosion.
Corrosion is time dependent and strongly influenced by the environmental conditions near the
pipe. It is reasonable to assume that without proper mitigation, that with increasing passage of
time the opportunity for corrosion damage increases.
Corrosion prevention measures can also be time-sensitive. In external corrosion control, the
degree to which a coating system is susceptible to age-related deterioration varies according to
the type of coating and its environment. Coating advancements have led to many improvements
in the coating products and applications both in the mill and in the field during construction.
Some coatings are more susceptible to disbondment, mechanical abrasion, and chemical
reaction. The CP system can also diminish in effectiveness as anode materials are consumed.
SIP–ADM 7.04 (Appendix 5A) provides processes to evaluate the effectiveness of CP systems.
Additionally, pipeline inspection and rehabilitation procedures are able to detect any areas of
metal loss caused by coating damage. Any deficiencies are mitigated in a timely manner in
accordance with regulatory and SIP requirements.
Prior to startup, CP systems were assessed and mitigated by the installation of ground beds,
performance of interference testing, coating replacement and mitigation of casings as identified
by CP surveys. Additionally, close interval pipeline surveys were completed for hypersensitive
areas and any pipeline segments not previously surveyed. Any corrosion-related conditions
were remediated prior to startup.
The potential for external corrosion for buried steel pipe depends on numerous factors including:
• Corrosivity of the soil
• Presence of bacteria promoting MIC
• Potential for AC induction
• Potential for selective seam corrosion
• Condition of the coating, evidenced by:
- Coating age and type;
- Quality of application and care during installation
- Damage potential (i.e., soil movements, lightning strikes, etc.)
5-20

<<<PAGE 650>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
- CP current density requirements; and
- Visual inspections.
• Effectiveness of CP system, evidenced by:
- Annual CP survey pipe-to-soil potentials;
- CIS pipe-to-soil potentials;
- Coating disbondment potential;
- Coating shielding potential; and
- ILI findings.
• Interference potential, depending on:
- Nearby utilities;
- Presence of casings; and
- Other nearby buried structures.
Corrosion induced metal loss damages to the exterior pipe wall occur when both the coating
and CP fail in the presence of a corrosive environment. These damages are detected by ILI and
repairs to both coating and CP are made as required.
Occurrences of external metal loss damages, presumably from external corrosion are identified
in each of the three ILI’s (MFL, TFI, and UT). The frequency and dimensions of damage
detected are noted by the ILI’s. These ILI findings are discussed in Section 5.3.5.2.1. For each
metal loss feature excavated, pipe to soil potential are measured to determine whether or not
CP is adequate for the location. If deficiencies are identified, remedial measures are completed
to ensure protection levels are obtained and to insure further metal loss damage does not occur.
Corrosion pits were detected and subsequently repaired during year 2000 pressure test. High
resolution MFL tools and Ultrasonic Wall Measurement Tools (UT) can detect pitting corrosion
anomalies with good accuracy and these inspections are routinely conducted. Pinhole corrosion
pitting represents a more specialized manifestation of corrosion, characterized as having short
length and width (less than 0.4 inch). Pinholes can be difficult to detect if not in the presence of
larger areas of pitting corrosion. It is rare to encounter pinhole corrosion without the presence of
other highly detectable corrosion features. Longhorn has not experienced any pinhole corrosion
of this kind. Pinhole corrosion is most often associated with larger areas of pitting corrosion that
are easily detectable by common ILI tools.
5.3.1.10.1 Pipe Coating.
Coatings prevent an electrolyte such as water and/or soil from making direct contact with the
pipe steel, thus eliminating the electrolytic path necessary for corrosion to occur. Coating for the
newer constructed sections of pipe consists of fusion-bonded epoxy (14 to 16 mils). Lilly 2040
Topcoat was used where additional coating protection was necessary, such as crossings.
Coatings on the refurbished 18-inch and 20-inch diameter pipeline consist of hot coal tar,
asbestos felt, and glass fiber. According to construction specifications, precautions were taken
in handling, bending, and backfilling the pipe to maintain the integrity of the coating.
5-21

<<<PAGE 651>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The fusion-bonded epoxy coating is applied to newer portions of the line. The original coal tar
coating, applied on the older portions of the line, was a widely used design and has proven to
have a long life span in many cases. Coatings are susceptible to age-related deterioration from
mechanical abrasion and chemical reaction from absorption of gases and liquids. Existing
corrosion control and integrity management procedures are designed to mitigate the effects of
any deterioration. Evidence of the current coating condition is found through visual inspection
reports, pipe-to-soil potential surveys, and detection of previous corrosion damages through in-
line inspection.
5.3.1.10.2 Cathodic Protection
CP provides an additional method of protection from corrosion. CP is the application of direct-
current electricity from an external source to oppose the discharge of corrosion current from
anodic areas. When a CP system is properly installed, all portions of the protected structure
(pipeline) collect current from the surrounding electrolyte (soil), and the entire exposed surface
becomes cathodic. Protective currents are provided from electrically connected anodes or from
an alternating current/direct current rectifier in conjunction with anodes. Anode beds have a
design life, become depleted over time, and must be replaced. Depleted anode beds are
detected by changes in CP and rectifier readings. The original number and location of these
systems is based on calculated demand for CP current. Additional systems are added as
necessary to maintain adequate CP on the pipeline and associated facilities.
CP on interstate hazardous liquid pipelines has been mandated by DOT since 1973. A CP
system is in place for the refurbished 18-inch and 20-inch diameter pipeline. Impressed current
CP systems are detailed in SIP-ADM-7.04 (Appendix 5A) and include the design and installation
of various configurations of CP systems. Part of the maintenance of the System requires
periodic replacement of inadequate anode beds.
The effectiveness of the CP system depends on the sufficiency of the voltage and current
provided along the pipeline. Periodic measurements of the voltage between the pipe and the
soil are required to verify the adequacy of the CP. Test leads or stations, installed at fixed
locations along the pipeline, are used for annual or semi-annual measurements of pipe-to-soil
voltages. These test stations consist of electrical wire connected to the pipe and brought to the
top of the ground over the pipe. Magellan conducts pipe-to-soil potential surveys at test lead
locations semi-annually over sensitive and hypersensitive areas which is twice the frequency
required by 49 CFR Part 195.416 (LMP Section 3.5.1.). Rectifiers, installed to provide the CP
current, are inspected monthly which is also twice the frequency required by regulation. Detailed
procedures for execution of corrosion monitoring and testing are in the SIP-ADM-7.04
(Appendix 5A).
An ‘exception’ is a voltage potential reading below an established criteria of -0.85 volts. Table
5.3.1-4 summarizes test point exceptions for the 2011 calendar year inspections. Magellan
manages exceptions in accordance with the LMP and Part 195.452. Magellan’s Corrosion
Control Program limits CP to a negative 1.2 volts to prevent excessive voltages. A voltage level
5-22

<<<PAGE 652>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
that is too high electrolyzes water, resulting in hydrogen (H2) liberation on any exposed pipeline
metal.
Close Interval Surveys record voltage readings at intervals shorter than test lead intervals and
are conducted periodically in hypersensitive (Tier 3) areas per the LMP. The CIS interval is
usually from 3 to 15 feet along the pipeline. Since corrosion problems can be localized, CIS
increases the opportunity for detecting potential problems compared with test lead station
readings. This is especially important in the ability to detect interferences. Protocol dictating
when and where CIS is conducted is found in LMP for Tier 3 areas and in SIP-ADM-7.04
(Appendix 5A) for all other areas.
The following lengths of System were inspected on the dates shown.
Longhorn Pipeline
CIS 2006-2011
Survey
Year
Survey Date
Range
Tier 3 Miles
Surveyed
Total Miles
Surveyed Comment
2006 February 21.98 112
2007 March to May 21.98 22.79
2008 February & March 21.98 30
2009 April & May 21.98 35
2010 June & July 21.98 37
2011 July & August 29.17 46 East Houston tie-in changes
Prior to 2011, there was a total of 21.98 miles of Tier 3 and 100% of this was inspected each
year per LMP requirements. In 2011, with the addition of pipe connecting to the East Houston
Terminal, additional Tier 3 mileage was added to the system and 100% of this was inspected
resulting in a total of 29.17 miles surveyed. CIS is not specifically mandated by regulations.
In addition to pipe-to-soil surveys, ILI also provides evidence of corrosion control effectiveness.
For each metal loss feature excavated, pipe to soil potential are measured to determine whether
or not CP is adequate for the location. If deficiencies are identified, remedial measures are
completed to ensure protection levels are obtained. Some ILI tools can infer potential
interferences from nearby metal pipelines or structures. The presence of nearby buried metal
can be detected by the magnetic flux leakage ILI tool.
5.3.1.10.3 IR Drop (CP Voltage Measurement Criteria)
A generally accepted criterion for CP pipe-to-soil voltage readings, as measured by a copper-
copper sulfate reference electrode, is at least -0.85 volts at the pipe-to-electrolyte boundary. A
more positive reading indicates decreased protection. The actual practice of ensuring adequate
levels of CP is often more complex than this simple criterion. Readings must be carefully
interpreted in light of the measurement system used. The reading of interest is the pipe-to-soil
potential directly at the pipe-soil interface. Since this reading cannot practically be taken directly,
5-23

<<<PAGE 653>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
a reading at the surface is taken and adjusted to reflect the reading at the pipe-soil interface.
The adjustment from readings taken to reading of interest is often termed “IR compensation,”
with the implication that "IR" or "IR drop" is the part of the voltage reading that should not be
considered in assessing the adequacy of CP. The surface readings can be taken with the
impressed electric current supply to the System turned either “on” or “instant off.” The IR drop
subtracts the voltage drop through the soil from the reading to yield the “true value” of the pipe-
to-reference electrode potential. The -0.85 volt is usually considered a conservative criterion
since a safety margin is already included for most soil conditions.
Magellan’s corrosion control program (SIP-ADM 7.04-001, Appendix 5A) in Element 7 of the SIP
contains procedures for addressing CP criteria including consideration for IR drop. Corrosion
Control Program in part provides the following (SIP-ADM 7.04-006, Appendix 5A):
2.4.1 IR drop is considered by taking potential readings directly over or as near as
practical to the structure surface. The effect on the potential measuring circuit is
kept to a minimum by using a high resistance volt meter and being mindful of
lead lengths and the condition, contact to structure and contact to electrolyte.
Furthermore, CP levels are to be evaluated utilizing CP criteria (SIP-ADM 7.04-006, Appendix
5A). Within the procedure are defined methods for considering the effects of IRF drop including
the use of:
• High resistance voltmeter
• Historical operating information
• Reference cell placement
• Calculation
• Current interruption
• Buried coupons
In addition to deficient CP voltage, excess voltage can also be a concern. In order to avoid
excess voltage, Magellan uses negative 1.2 volts as a limit on pipe-to-soil potentials as an
informal guideline. Episodes of more negative voltage potential are individually evaluated and
mitigated.
5.3.1.10.4 Casings
Casings were originally installed as a means to reduce the effects of vehicle loadings on the
buried pipe, to provide a path for leaks to be routed and detected without damaging the road or
railroad structure, and to facilitate less intrusive pipe replacements. Casings have the potential
to: 1) act as a shield so that protective CP currents cannot reach the carrier pipe, 2) create an
environment for unobservable atmospheric corrosion, 3) create an opportunity for a “short
circuit” in which the carrier pipe becomes anodic to the casing pipe and accelerated corrosion
occurs on the carrier pipe. In much of today’s construction practices, the use of casings is
avoided.
5-24

<<<PAGE 654>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Casings are checked annually in Tier 1 areas and semi-annually in Tier 2 and 3 areas to ensure
that they are not interfering with CP by being in an electrically shorted condition. If a short is
verified, an action plan is developed to clear the short within timeframes specified within the
LMP.
There is one-half mile of pipe encased in plastic casing through the Edwards Aquifer (Ref
SBRMA 2006) that was identified in early reviews (2006) as needing specific corrosion control
procedures. Magellan has developed and implemented SIP procedure 7.05-ADM-037, HDPE
Inspection and Dewatering Procedure, for this purpose. The procedure ensures that the casing
remains free of water through inspections at weekly intervals not to exceed 10 days and
following any rainfall event in excess of 0.1 inches, for the presence of water and hydrocarbon
vapors. Any water discovered is removed and analyzed.
5.3.1.10.5 Microbiologically Influenced Corrosion (MIC)
As defined within the Corrosion Control Program, 7.04-ADM-001 (Appendix 5A), in the event
that the pipeline system experiences one or more confirmed discoveries of injurious MIC, or
where accelerated corrosion from MIC is anticipated, a Bacteria Testing Protocol will be
established to evaluate future integrity threats from MIC. The line specific protocol will be
utilized until such time that the threat from MIC has been assessed and appropriate mitigation
actions have been taken. Testing for MIC shall be conducted in accordance with Bacteria
Testing – Serial Dilution Method. External MIC has not been identified on the Longhorn Pipeline.
5.3.1.10.6 AC Induced Corrosion.
Where pipelines are parallel to high voltage overhead lines for some distance high AC voltage
can be induced into the pipeline. Under certain conditions the AC current, as it diverts from the
steel into the soil, can lead to AC induced corrosion. AC induced corrosion has occurred along
isolated portions of a nine-mile segment in the Houston area. The potential for AC induced
corrosion is a function of proximity to sources of AC, source strength, configuration relative to
pipeline, soil characteristics, pipe coating, and other factors. Newer coatings tend to make pipe
more susceptible to AC induced corrosion.
A study was completed to determine where AC induced currents exceeded criteria. As a result
of the study, mitigation measures were employed through the installation of zinc anode beds.
The CP Database was updated to include any locations for the entire Longhorn system where
potential for AC induced corrosion occurs due to proximity of High Voltage Alternating Current
Systems. SIP-7.04-ADM-023 procedure (Appendix 5A) was developed and implemented to
identify and mitigate areas of induced AC. AC voltage readings are taken at over 30 points
along the System, as part of this procedure. Magellan continues to monitor these locations
annually as a part of ongoing CP system maintenance.
5-25

<<<PAGE 655>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.1.10.7 Stray Currents
Magellan manages the threat of metal in close proximity to a buried pipeline through foreign line
crossing surveys. One potential effect of nearby buried metallic structures or especially those
with their own CP systems is to divert electric current from the pipeline that is being protected.
Such impacts on CP systems from other buried metals or foreign CP systems are referred to as
“interferences.” Stray current corrosion can occur when nearby CP systems interfere and cause
one of the protected metallic structures to become anodic to the other. This can cause localized
and rapid metal loss. Owners of pipelines, whose CP systems have been found to be
interfering, normally cooperate by installing bonds between the systems. Some of these are
termed 'critical bonds' indicating that serious CP system malfunction is possible upon damage to
the bond. Magellan inspects critical bonds at least six times each calendar year, but with
intervals not exceeding 2 ½ months.
DC stray current was suspected as the cause of corrosion for two leaks that were detected near
MP 351. The first leak was identified during the hydrotesting before start-up, and the second
was detected during a repair when a corrosion anomaly started leaking after the area was grit
blasted. Although neither anomaly was reportable to PHMSA because they did not fail in-
service, they did highlight the potential for stray currents in the area. The Longhorn Pipeline is
paralleled for a good portion of its length between Crane and East Houston by two other
pipelines. A stray current survey study in the vicinity of MP 351 showed interference by one
pipeline where the Longhorn Pipeline acted as a ground bed. A total of 4,000 feet of affected
pipe was replaced. The remaining affected pipe was remediated with metal repair sleeves. A
second stray current survey after the replacement and repairs showed stray current was
reduced but still required remediation through changes to the CP system to prevent further stray
currents. Results were utilized to implement the changes to CP system to fully remediate stray
currents. The CP system is monitored in accordance with SIP-ADM-7.04 inspection procedures
and frequencies (Appendix 5A).
5.3.1.10.8 Selective Seam Corrosion
Some low frequency ERW pipe has an increased susceptibility to a special form of corrosion—
“selective seam corrosion (SSC)” or “crevice corrosion.” While CP is thought to be effective in
preventing formation of initiators of this type of corrosion, its effectiveness in stopping on-going
corrosion in an existing crevice depends on the current density and the electrolyte in the
crevice. Magellan conducted inspections (2007/2008) utilizing transverse flux (TFI) MFL which
is ideally suited to identify potential areas of selective seam corrosion. The In-Line Inspection
Analysis Guideline, 7.03-ADM-007, provides criteria for determining areas of SSC to investigate.
These inspections did not reveal any confirmed metallurgical indications of SSC. Any identified
areas of possible SSC were remediated in accordance with the Pipeline Defect Evaluation and
Repair Procedure, 7.01-ADM-001.
5-26

<<<PAGE 656>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.1.11 Third Party Damage
The purpose of damage prevention is to protect the pipeline from third-party damage.
Magellan’s Damage Prevention Program for the Longhorn Pipeline includes public outreach and
damage prevention protocols such as: permanent pipeline markers, ground and aerial
surveillance, One Calls, blasting monitoring, depth-of-cover surveys, ROW maintenance,
navigable water crossings inspections, and line spotting activities. These protocols and
procedures are detailed in SIP-ADM-7.05 (Appendix 5A) and incorporate processes to
proactively identify and manage risks to outside forces damage and achieve public safety.
Several aspects of Magellan’s overall damage prevention program as it applies to the Longhorn
Pipeline exceed regulatory requirements. Examples include:
• Definitive, quantifiable criteria for additional inspection related to anecdotal evidence of
third party activities;
• Extraordinary measurements of specific parameters such as near-misses,
encroachments, etc.;
• Special agreements with agricultural excavators; and
• Increased pipeline surveillance frequencies by aerial and/or ground patrol that are at a
minimum double the frequency required by regulation.
Additionally, per LMC 12a, Electronic Geometry Pig inspections are conducted every three
years to identify any potential damage to the pipeline caused by third parties.
5.3.1.11.1 One Call
Magellan has established a standardized One Call program to protect Company Assets from
damage due to excavation, encroachments, and other third party activities. Magellan has
established and maintains a One Call membership with respective state agencies and follows
industry standards to receive, record, respond and document One Call Locate Notifications.
5.3.1.11.2 Public Education
SIP-ADM-10.01, Public Awareness, as detailed in Appendix 5A ensures promotion of public
awareness of underground utilities, damage prevention and emergency preparedness.
Collectively, this initiative enhances public safety and minimizes damage to property, the
environment and the Longhorn Pipeline. Magellan’s Public Awareness Program was developed
to comply with the standards established in American Petroleum Institute’s Recommended
Practice (RP) 1162.
Per LMC 25, enhanced public education/damage prevention programs were developed to: (a)
ensure awareness among contractors and potentially affected public, (b) promote cooperation in
protecting the pipeline and (c) to provide information to affected communities with regard to
detection of and responses to well water contamination.
5-27

<<<PAGE 657>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The Public Awareness Program utilizes mailings, flyers, public meetings, emergency responder
meetings, periodic radio public service announcements, and newspaper ads to educate the
local public. Annual mailing to groups such as schools, residences, hospitals, churches,
retirement homes and other businesses include the following information:
• One-Call information
• Product identification information
• How to identify and report a suspected leak
• Personal safety guidelines in the event of a leak
• "Dig Safely" or Call 811 program information
Annual (not to exceed 15 months) mailings target a one-quarter (1/4) mile radius of the pipeline
in metropolitan areas and a one (1) mile radius in rural areas. Mailings include items such as
phone stickers, refrigerator magnets, and rulers to ensure that emergency contact information
and "Call 811" information will be readily available. Door-to-door visits with the public in areas
adjacent to the pipeline are performed in Tier II and III areas every two years (not to exceed 30
months).
Damage prevention flyers and “Call 811” literature is distributed to the public at county fairs,
trade shows, agricultural shows, feed stores, home and garden shows, and equipment rental
companies.
Non-emergency response government agencies that are exempt from one-call mandates, such
as city and county planning, zoning and building permit offices, and agricultural agencies are
contacted annually (not to exceed 15 months) with mailings and a personal visit to distribute
maps of the pipeline route and inform developers of the presence of the pipeline.
Reply cards and records of personal visits, along with third party damage incident scorecards,
are used to measure the effectiveness of the program.
Emergency response agencies within each county that the pipeline passes through are
contacted at intervals not to exceed 15 months, but at least once each calendar year, in person
and provided with maps of the system. Specific emergency response requirements and plans
are reviewed on an annual basis with applicable LEPC and emergency responders. Annual
emergency response drills are conducted.
5.3.1.11.3 Excavator Education
Excavator education is an important element of damage prevention in order to reduce the
likelihood of unintended third party damage caused from excavation activity. The program as
defined within the SIP-ADM-10.01, Public Awareness Initiative, focuses on promoting
cooperation and awareness throughout the following groups (Appendix 5A):
• General contractors (i.e., irrigation, dirt, fencing, plumbing, landscaping)
• Land owners
5-28

<<<PAGE 658>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Real estate developers
• Utility companies
• Mining and quarry operations
The identified excavators are provided with the following:
• Information on the "Dig Safely" program initiated by DAMQAT (Damage Prevention
Quality Action Team - a joint industry and government effort to educate the public on the
prevention of damages to all underground and submerged facilities).
• Information on the Texas One-Call system.
• Information about the location of the pipeline and products in the line.
• What to do in the event that unintentional damage of the pipeline occurs.
• Instructions on how to recognize and report a leak.
Direct mail flyers, written in English and Spanish, include items such as dashboard calendars
and stickers so that emergency contact information and "Dig Safely" information will be readily
available. Reply cards will be included to measure the damage prevention program
effectiveness.
Advertisements are placed in various trade journals and/or community publications along the
Longhorn right of way to reinforce the "Dig Safely" program and to instruct the excavators to use
the One-Call system.
5.3.1.11.4 Depth of Cover and Exposed Pipe
For pipelines under 49 CFR Part 195.248, requirements are that new pipe in industrial,
commercial, and residential areas should be buried to a depth of 36 inches for normal
excavation and 30 inches for rocky excavation. The depth of cover is 30 inches in other normal
areas of construction and there are special situations such as water bodies and ports requiring
depths ranging from 18 to 48 inches for newly constructed pipelines. Excepting the Gulf of
Mexico and its inlets, there is no explicit regulation requiring the maintenance of depth of cover.
Unintended exposures can occur from forces such as ground erosion and stream scouring.
Construction specifications of 1949 called for a minimum 24 inches of cover in soft terrain and
12 inches in rocky terrain. The current construction specifications call for a minimum depth of
cover of 30 inches or deeper in normal conditions as shown in Table 5.2.1-2. There is no
regulatory requirement to increase cover over an existing pipeline; however, as part of the LMC
18, 26 shallow or exposed areas were identified and remediated prior to startup by adding cover
to a depth of five feet or a concrete cap. In 2007, Magellan conducted a depth of cover survey
between Galena Park and Crane and as a result mitigated nine additional shallow cover areas.
For segments re-configured to aboveground, protection offered by cover is removed and the
pipeline is more vulnerable to damage from external threats. Damage from these external
threats is mitigated by installation of security fencing or appropriate physical barriers. Moving a
pipe segment aboveground also changes the potential for external corrosion. Atmospheric
5-29

<<<PAGE 659>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
corrosion is generally less severe and inspection ability is increased. Careful attention is placed
upon the coatings notably at ground-air interfaces and beneath supports due to higher
susceptibility at these locations. Special coatings and inspections, as required by the SIP, are
placed on piping and valves located in below ground chambers due to potential for alternating
wet-dry conditions. See Section 5.3.1.9 for more discussion on atmospheric corrosion.
5.3.1.11.5 Pipeline Markers
Permanent pipeline markers are used to notify the public of the general location of the Longhorn
Pipeline. Pipeline markers are installed and maintained in accordance with SIP procedure 7.05-
ADM-002 (Appendix 5A). Permanent pipeline markers are maintained in Tier I (general), Tier II
(Sensitive), and Tier III (Hypersensitive) areas as follows:
• Pipeline markers meet or exceed all requirements of 49 C.F.R. §195.410.
• Marker spacing for Tier I areas are placed within line-of-sight of each other. Exceptions
may be necessary for land use (i.e., cultivation), and landowner and tenant issues.
Discussions explaining the importance of line markers, as identified in our Public
Education program are held with landowners or tenants.
• Marker spacing for Tier II and III areas are placed such that if any one marker is
removed, the location of the pipeline can still be identified from either direction from any
point in between.
• All line markers are written in English and Spanish.
• Marker placement and density is evaluated routinely through aerial and ground
surveillance.
• Missing or damaged markers are replaced within 7 days of discovery.
• Markers are located at all aboveground facilities to identify the operator of the system.
• Markers are located on each side of each public road crossing, water crossing, and
railroad crossings.
5.3.1.11.6 Pipeline Surveillance
Most pipeline rights-of-way corridors are accessible through aerial surveillance, which is the
primary method of right-of-way inspection and damage prevention. Periodic conditions such as
weather, however, may render certain segments of the right-of-way inaccessible via fixed wing
aircraft or helicopter and thus ground surveillance can supplement air surveillance. In addition,
ground surveillance is utilized when vegetation temporarily obstructs aerial surveillance.
Pipeline surveillance is conducted in accordance with the SIP procedure 7.05-ADM-031
(Appendix 5A) and LMC 20. Surveillance intervals are conducted as follows:
• Tier II and III areas: Every 2.5 days, not to exceed 72 hours
• Tier I areas: Once a week, not to exceed 12 days, but at least 52 times per year
• Edwards Aquifer Recharge Zone: Daily (one day per week shall be a ground-level patrol)
5-30

<<<PAGE 660>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Aerial and ground surveillance frequency is increased across Tier II (sensitive) and Tier III
(hypersensitive) areas when the threat of flooding and/or severe erosion is identified near the
pipeline right-of-way.
Emergency situations identified during aerial or ground surveillance are immediately reported to
the Pipeline Control Center located in Tulsa, OK. All surveillance personnel and line spotters are
trained and certified in OSHA HAZWOPER to the first responder level.
Every consideration is given to endangered species when conducting ground surveillance in
and around the pipeline right-of-way. Maps depicting the location and habitat of endangered
species are utilized for this purpose.
5.3.1.11.7 Encroachments and ROW Maintenance
Per LMC 16, encroachments along the pipeline ROW were removed that could reasonably
obstruct prompt access to the pipeline for routine or emergency repair activities or that could
reasonably be expected to hinder leak detection or other problems. Potential encroachments
are evaluated using the guidelines found in the SIP. Per LMC 17, ROW was cleared prior to
startup, and is now continuously maintained.
5.3.1.12 External Forces
As a result of LMC 19, studies evaluating each of the following matters along the pipeline were
conducted and recommendations were implemented:
a. Scour, erosion, and flood potential
b. Seismic activity
c. Ground movement, subsidence, and aseismic faulting
d. Landslide potential
e. Soil stress
The predominant conclusion was that earth movements (Geohazards) present a low risk. In any
case, Magellan continues to manage external force threats as recommended by these studies
and as required by the SIP. Examples of activities to manage external force threats include:
1. Scheduled inspections occur at various water crossings at six-month and five-year
intervals. Inspections also occur after certain flood events to evaluate for scouring,
erosion and flood potential.
2. Studies are performed every six months to evaluate for ground movement, subsidence
and aseismic faulting.
3. Surveys are conducted every five years to evaluate landslide potential.
These studies and their conclusions remain valid for the System, and as such, the discussion as
found in the 1999 EA is still relevant. The Proposed Project may change failure potential from
these threats at certain locations where valves are re-configured and possibly at station
5-31

<<<PAGE 661>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
modifications. Threats are very location-dependent. An assessment of their frequency and
magnitude is part of the design process. Industry accepted design and construction practices
will ensure that integrity is not compromised by such threats.
5.3.1.12.1 Flooding
Scheduled inspections occur at various water crossings at six-month and five-year intervals.
Inspections also occur after certain flood events to evaluate for scouring, erosion and flood
potential. As a result of PHMSA Advisory ADB-11-04, Magellan implemented the Flooding
Conditions Procedure, 7.05-ADM-039 (Appendix 5A) to provide standards for recognition,
surveillance, and responses to flooding conditions near mainline pipelines.
5.3.1.12.2 Geohazards
Studies are performed every six months to evaluate for ground movement, subsidence and
aseismic faulting. Surveys are conducted every five years to evaluate landslide potential.
Additionally, the Earth Movement Inspection Procedure, 7.05-ADM-020 (Appendix 5A), provides
methods for the investigation and monitoring of areas of the pipeline identified as having high
susceptibility to earth movement or where earth movement has been identified. Pipeline
surveillance activities pay particular attention, within the target area, to signs or indicators of
earth movement or subsidence such as ground cracks, sink holes, erosion, heaving, or
buckling. ORAs since 2005 have updated geohazard threat analysis, especially aseismic
faulting threat. No new issues have been identified and some previously identified issues have
been recognized as being less severe than was initially (and conservatively) deemed plausible.
5.3.1.12.3 Crossings
The Longhorn Pipeline crosses creeks and rivers as well as man-made linear features such as
roads, railroads, or other pipelines. Rivers and creeks are subject to erosion that can dislodge
the pipeline. Vehicle traffic on roads and railroads can cause recurring stresses and vibrations in
the subsurface. For these reasons, pipelines are often fortified at crossings and protective
measures are specified depending on the circumstances. These can include thicker wall pipe
and increasing depth of burial and casings at road and railroad crossings. No new crossings or
modifications to existing crossings have been specified as part of the Proposed Project.
Magellan manages the integrity of overhead pipeline crossings with the Overhead Pipeline
Crossing Integrity Procedure, 7.05-ADM-030 (Appendix 5A). This procedure manages integrity
through a comprehensive risk-based program which identifies risk reduction projects to improve
structural component integrity.
Magellan manages the integrity of navigable buried river crossings with the Navigable Crossings
Inspection Procedure, 7.05-ADM-014 (Appendix 5A). This procedure requires inspection to
determine pipeline depths at these crossing at least once every five years per regulatory
requirements.
5-32

<<<PAGE 662>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Per LMC 15, an engineering analysis was conducted to verify that all pipeline spans were
adequately supported and protected from external loading. Subsequent remediation was
completed prior to startup in 2005.
5.3.2 Staffing and Training
Magellan employs field staff to cover the route of the Longhorn Pipeline. The System has
defined geographical support areas consisting of: field technicians, corrosion technicians,
maintenance coordinators, area supervisors, operators and operation managers. These teams
are supported by a centralized technical services team that includes engineering,
environmental, health and safety, regulatory compliance, training, corrosion and risk mitigation,
operations control, design, and real estate services.
Magellan has an established training program to instruct employees in safety, security,
environmental and operational compliance. Training is reviewed regularly to assure
effectiveness. Magellan’s training program consists of the following major components: new
employee orientation; annual training OJT; computer-based training (KnowledgeWire); web-
based training; vendor-led training schools/seminars; technical training; SIP/safety meetings
and supervisory training.
New Employee Orientation (NEO) is required for all field-based personnel to provide basic
training on the fundamentals of safety and operations. Emphasis is placed on employee safety.
The NEO class is three weeks in length. Week 1 and week 3 are spent in Tulsa at Magellan’s
headquarters and week 2 is spent at the employee’s home location. Additional computer-based
training (CBT) and site specific training at their home location are covered once the employee
has completed the NEO classes. New employees have 180 days to complete the majority of
their training requirements.
Annually, employees are required to attend mandatory training on a variety of safety and
compliance topics. Magellan employees utilize the Compliance Management System (CMS) for
training records. Key resource documents are available through Magellan’s intranet site,
Compass. Employees are also provided the opportunity to evaluate training. The evaluations
are collected, combined, reviewed and analyzed for improvement efforts.
Employees and supervisors may request additional training on special topics or topics that need
deeper study or development. The training department schedules additional classes based
upon those requests.
5.3.3 Risk Assessment Processes
Magellan’s risk management practices are relevant to this analysis since they provide some
evidence into future risk management potential. An examination of those practices is presented
here.
5-33

<<<PAGE 663>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Risk assessment and risk management performed by Magellan are detailed in the LMP and
SIP. Integrity Management Plan (IMP) regulations now mandate formal risk assessment and
can be found in 49 CFR Part 195.452. . The risk assessment defined in the 1999 EA and LMP
were designed prior to the Integrity Management regulations. An operator, whose system can
impact a pre-defined HCA, is required to place certain portions of the system under a formal
integrity management program which includes formal risk assessment.
Magellan’s current risk assessment tools being applied to the System include:
• ORA - annual evaluation of integrity issues; conducted by independent third party
• Data Management - physical data, collected by and contributed from an integrated team
of operational and technical subject matter experts, is the cornerstone of the “Risk
Management” process.
• Pipeline Risk Assessment or Relative Risk Assessment (RRA) - central element of LMP
and IMP compliance; follows 1999 EA risk assessment.
• Facility Risk Assessment (FRA) - special IMP process used in stations.
• PHA’s - SME-based techniques to identify hazards related to facilities.
• Preventive and Mitigative Measures Analysis (Section 6) and Scenario Based Risk
Mitigation Analysis (SBRMA) - qualitative review with action plan generation, used as
continuation of RRA (per Section 3.5.10 of the LMP).
These tools and processes are discussed below.
5.3.3.1 Operational Reliability Assessment (ORA)
An ORA is performed by an independent third party approved by PHMSA and results and
recommendations are reported to PHMSA and publicly posted via Magellan’s internet website.
Recommendations must be implemented as written by third party. The ORA is an ongoing
process completed annually.
The ORA Process Manual prescribes the scope, schedule, technical approach and procedures
for performing the ORA functions. As stated in the ORA manual:
“…the ORA will provide Longhorn with a technical evaluation of the integrity of its
pipeline assets and will provide specific recommendations that are intended to
either preserve long-term integrity or to mitigate areas of concern before they can
result in a threat of failure. An Office of Pipeline Safety (OPS) approved third party
consultant (ORA contractor) will perform the ORAs. The ORA contractor’s
recommendations will be related to integrity intervention methods and scheduled
for incorporation into the LPSIP. The ORA can be viewed as the second line of
defense (supporting the LPSIP) in maintaining the long-term integrity of the
pipeline system. The primary focus of the ORA is upon line pipe, while the LPSIP
covers a much broader set of operating and maintenance processes.”
5-34

<<<PAGE 664>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The ORA is a central element in managing integrity threats on the Longhorn Pipeline. Guidance
in determining appropriate response to new findings is a key aspect of each annual report.
Intervention, via inspection to detect and remove damages, is a central aspect of Magellan’s
integrity management program. The ORA provides the basis for intervention types and timing. A
probability of exceedance (PoE) methodology is used in the establishment of integrity
assessment intervals for corrosion. The PoE estimates are generated for both internal and
external corrosion in each annual ORA, according to the ORA manual. The PoE process is
discussed in Section 5.3.5.2.2.
The ORA also incorporates a process to determine crack remaining life and associated
reassessment intervals. A crack estimation of remaining life (in lieu of a PoE analysis for metal
loss) is conducted by determining frequency and amplitude of pressure cycles and subsequently
estimating the crack growth rates. The estimated remaining lives are then multiplied by a factor
of 0.45 as an added safety factor. The ORA also provides a qualitative evaluation of programs
and processes intended to control certain other failure mechanisms.
5.3.3.2 Data Management
Similar to other pipeline systems, Magellan assets have specific physical attributes that are
characterized by their construction materials, as well as, their installation and maintenance
methods. The products transported, operating parameters, and routing through population
density, land uses, and environmentally sensitive areas, further characterize the Magellan
pipeline system. Taken collectively, physical assets, products transported and operating
systems are factors that characterize the relative risks to the surrounding environment and
population. Physical data, collected by and contributed from an integrated team of operational
and technical subject matter experts, is the cornerstone of the “Risk Management” process.
Magellan uses ESRI (vendor) products for its Geographic Information System (GIS) and
currently employs an in-house developed pipeline data model known as the Technical
Information Exchange System (TIES) for some pipeline and facility data. Other data of record is
documented in a variety of different formats, such as:
• Pipeline Data (TIES - Oracle 11)
• Facility Data (TIES - Oracle 11)
• Depth of Cover Data (MS Access, MS Excel)
• In-line Inspection Data (MS Excel)
• Corrosion Data (American Innovations - CPDM)
• Close Interval Survey (MS Excel)
• Release Data (MS Access)
• High Consequence Area Data (MS Access)
• Risk Model (American Innovations - SQL Server 2005)
• Real Estate Data (LandROW - Oracle 11)
• Damage Prevention / One Call Data (MS Access, MS Excel)
• Operational Data Store (ODS - Oracle 11)
5-35

<<<PAGE 665>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Environmental Data (GIS, MS Excel)
• Emergency Response Data (GIS, MS Excel)
• Hydrostatic Test Data (MS Excel)
5.3.3.3 Pipeline Risk Assessment
Risk Management is the process of evaluating integrity related issues and allocating resources
in a manner that minimizes risk. Risk assessment is a core function within risk management.
Relative risk assessment (RRA) allows Magellan to target and focus on those assets posing the
highest risk to population and/or environment, so to facilitate the development of risk mitigation
programs. This enables the implementation of controls and measures with which to reduce the
likelihood of adverse events or to mitigate the potential consequences. The inherent value in
Magellan’s risk management approach is that it ensures that its resources (time, talent, and
money) are effectively employed in those areas of highest risk.
A RRA was included as a part of the 1999 EA to help identify or confirm high-risk areas along
the pipeline route. It was also used as a means to account for changes in absolute probabilities
likely to be achieved with changes in design and operational practices. The RRA model is one
of the risk assessment tools used by Magellan on the System. Magellan has maintained the
original segmentation and re-calculates RRA scores on a periodic basis. The Magellan RA
Index Sum is an overall measure of failure potential. The Index sum is divided into four sub-
categories. These correspond to possible failure modes, which are Third-Party Damage Index,
Corrosion Index, Design Index, and Incorrect Operations Index.
The Pipeline RRA process consists of the following process steps:
1. Gather Data needed for Assessment
2. Populate Relative Risk Model
3. Conduct Pipeline Risk Assessment
4. Populate Segments based on Risk Results
5. Conduct Assessment Planning
6. Conduct Integrity Assessments
7. Evaluate Assessment Results
8. Execute Mitigation
9. Conduct Preventive Mitigative Measures Analysis
10. Implement Additional Mitigation Measures
11. Update Pipeline Risk Model.
The LMP identified potential future benefits from an effective risk management program
including: “…a sharper focus on continuously identifying and reducing real risk issues, reduction
in accidents, prioritization of inspection programs, prioritization of maintenance plans, and
assistance in project design.”
5-36

<<<PAGE 666>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.3.4 Facility Risk Assessment
Similar to the Pipeline RRA, the facility risk assessment integrates the components that
influence facility integrity and combines them into an overall facility risk assessment score. This
risk assessment allows Magellan to target facility risk management activities and resources to
the highest priority areas. A scoring type assessment questionnaire is utilized to produce a
relative probability score and a relative consequence score. The major components of the risk
assessment include:
1. Facility Age
2. Complexity
3. Overfill Protection Evaluation
4. Over/Short Monitoring Evaluation
5. Mechanical Integrity
6. Corrosion Control
7. Incident History
8. Consequence Potential
The Facility Relative Risk Assessment Process is conducted via the following process steps:
1. Identification and grouping of facilities for risk scoring
2. Collection of data for assessment
3. Input information into risk assessment database.
4. Calculation of the relative risk score.
5. Prioritization of facilities
6. Utilization of risk ranking to prioritize projects within the various facility integrity
programs.
5.3.3.5 Process Hazard Analysis
PHAs are formal risk assessment/management tools used to assess the potential hazards
associated with station facilities of a pipeline system. There are a variety of methodologies that
can be used to conduct a PHA; however, Magellan has adopted the What if/Checklist and the
Hazard and Operability Study (HAZOP) methodologies. A HAZOP is a structured and
systematic analysis of a process that utilizes parameters and guide words to establish the cause
and effect of any potential hazard or deviation from the design intent. Each hazard/deviation is
evaluated by the HAZOP team to determine if the cause is credible, to establish the safeguards
in place to prevent the deviation and whether any additional recommendations are required to
meet an acceptable risk threshold. Each credible deviation is risk ranked according to severity
and likelihood using a subjective criterion by the HAZOP team. The severity score assigned for
each identified hazard is ranked without consideration of the safeguards currently in place. The
likelihood score assigned for each identified hazard is ranked based on the safeguards currently
in place to prevent the deviation. The likelihood score does not include the impact of any
recommendations. The impact of the recommendations on the likelihood score will be
considered during the subsequent PHA revalidations. A PHA has been conducted at each
5-37

<<<PAGE 667>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
facility per the requirements of the LMP with recommendations implemented. These PHAs are
required to be revalidated every five years.
5.3.3.6 Preventive and Mitigative Measures Analysis
Following the relative risk assessment of the various pipeline segments, the Scenario Based
Risk Mitigation Analysis (SBRMA) Program is executed. This program is designed to identify
preventive measures and/or modifications that can be recommended that would reduce the
risks to the environment and the population in the event of a product release. The relative risk
ranking results are used to allocate resources to reduce the overall operational risk.
As part of the SBRMA, a review is conducted of the risk model Index Sum and contributing
index scores to determine areas along the pipeline and within the facilities with the highest risk.
A meeting is then scheduled with the Longhorn Risk Analyst to discuss low scores and identify
target areas where scores could be raised by conducting mitigation measures. Any low risk
scores corresponding to high risk areas more than two standard deviations from the mean are
identified and a spreadsheet is prepared detailing the risk factors that are contributing to the low
risk scores for each high risk area identified. A roundtable meeting is held with appropriate
Subject Matter Experts (SME’s) and stakeholders to include: Field Operations, Pipeline Control,
Corrosion, Pipeline Integrity, One-Call, and Engineering to discuss areas of identified low risk
scores and determine any additional preventive or mitigative measure needed to reduce
pipeline and/or facility risk.
Additionally, following a mainline integrity assessment of HCA’s and Tier 2 and 3 areas,
Magellan initiates a Risk Analysis Process to determine if additional preventive or mitigation
measures are necessary. Additionally, following integrity related events such as an in-service
externally reportable release; a risk analysis will be conducted. For facilities releases or
releases from mainline components such as valves, flanges, and fittings, the Company Incident
Investigation Process will be followed. For facilities a risk analysis process to determine if
additional preventive or mitigative measures are necessary will be conducted on a prioritized
systematic basis.
Each analysis is lead from the centralized Asset Integrity group by the Asset Integrity Engineer /
Analyst and is designed to be a systematic approach to gathering data, conducting analyses,
formulating recommendations and implementing risk reduction measures. Following
documentation of the analysis, a roundtable discussion is held with appropriate stakeholders in
Operations Control, Field Operations, Corrosion, Pipeline Integrity, One Call, Damage
Prevention, and Engineering to discuss the results and finalize recommendations for additional
preventive and mitigative measures.
5.3.4 Control Systems (SCADA)
The operation of each pump station is controlled by a combination of local control systems and
remote monitoring via a centralized Supervisory Control and Data Acquisition (SCADA) system
located at the Magellan Operations Control Center. Each data source, transmitting information
5-38

<<<PAGE 668>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
to the SCADA system, communicates approximately every three seconds. The signals are
electronically transmitted by satellite communications. Telephone modems are in place as a
backup to the satellite system. The modem system can be used if there is an isolated failure in
satellite communications from individual stations or if there is a failure of the entire satellite
system. When all locations are being accessed with the backup modem system, the initial
connection can take up to three and one-half minutes to establish communication, then the
systems responds every three seconds.
Local control systems provide much of the protection against abnormal operation at each of the
pump stations. Table 5.3.4-1 lists emergency shutdown alarms and devices located at pump
stations. These local control systems are designed to provide an orderly shutdown of the pump
station if an alarm condition occurs or if certain operating parameters are violated. At the same
time that the shutdown sequence has been initiated, a shutdown alarm is transmitted to the
Magellan Operations Control Center.
Examples of local control systems are:
• A low suction pressure (typically less than 50 pounds per square inch gauge [psig] at
several stations) will cause the pump to automatically shut down.
• A pump discharge pressure above a specific pressure setting will also produce an
automatic pump shutdown.
Other sensors and controllers act in a similar manner. The primary objective of these local
controls is to prevent abnormal conditions from damaging the pipeline and pump station
equipment and potentially causing or contributing to a leak. The capability to detect smaller
leaks and to respond with appropriate action resides primarily with the controllers in the
Magellan Operations Control Center via the SCADA system. Per LMC 13, the leak detection
system is computational based and can detect 1% or less loss of flow within one-half hour over
the entire pipeline system. The system capability is periodically demonstrated through testing.
5.3.4.1 Leak Detection
Specialized leak detection was required as part of the LMP. LMC 13 required an enhanced leak
detection and control system to be installed to include a transient model based leak detection
system utilizing 9 meter stations (6 clamp on meters and 3 turbine meters). Longhorn met LMC
13 in 2000 by installing a pipeline leak detection system (PLDS), a software package designed
and provided by Energy Solutions International, Ltd. A routine analysis is continuous and
ongoing to verify that PLDS meets the accuracy parameters of the LMP. PLDS is based on the
real time simulation of the flow in the pipeline and is comprised of a rigorous transient computer
model driven by SCADA data. PLDS verifies the pipeline instrumentation integrates
hydraulically and alarms when it detects drifts in calibration, wrong measurements, or missing
product from the pipeline. Leak detection is performed by viewing sections of pipe bounded by
meters. On the Longhorn Pipeline, both turbine meters and ultrasonic devices (strap on meters)
are used to monitor and analyze the hydraulics in smaller segments. PLDS detects leaks in
pipelines by performing accurate transient compensated volume (mass) balance calculations for
5-39

<<<PAGE 669>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
defined sections of the pipeline each SCADA scan. SCADA scans and model calculations are
performed every three seconds.
PLDS complies with the American Petroleum Institute RP 1130 1st edition, of September 2007.
This system also adheres to the sensitivity guidelines set forth in LMC 13 shown in the table
below.
Location System Design Specifications
Tier 1 1% of flow detected within one-half hour
Tier 2
and 3
1% or more of flow detected within one-half hour
0.5% - 1% of flow detected within one hour
PLDS alarms are passed back to SCADA. Upon receiving the probable leak indication, the
controller proceeds with the line shutdown. The line shutdown is achieved within five minutes or
less. Table 5.3.4-1a details the PLDS alarms and required responses.
Per Magellan procedure, 9.02-ADM-082, Magellan is required to demonstrate and test the leak
detection system on a periodic basis to ensure the sensitivities meet the requirements outlined
in Longhorn Mitigation Plan Commitment 13. As example, on November 19th, 2011 at 15:28,
with the pipeline flowing at 2800 BPH, the leak detection system alarmed in the 10 minute
window when product was diverted into a pig trap, which holds a maximum of 20 BBLs. The
volume of 20 BBLs at the noted flow rate results in 0.7% sensitivity. Leak detection sensitivities
are calculated and reviewed monthly by the Magellan Leak Detection analyst.
Larger leaks are signaled by an alarm in the Magellan Operation Control Center indicating that
the pressure and/or flow rate has deviated outside of preset parameter limits. These limits are
20% for pressure and 12% for flow rates and may be periodically reviewed and changed based
on analysis of historical data. Thus, a decrease in flow greater than 12% from the target rate
would cause an alarm at the Control Center within six seconds of the time the sensor detected
the low flow rate. When a pressure or flow parameter alarm occurs, the controller reviews the
pipeline operation and checks the pipeline. If no cause is apparent, controller proceeds with the
line shutdown. The line shutdown is achieved within five minutes or less. Mainline isolation
valves will be closed, and the pipeline will be kept under pressure to determine its integrity and
to identify the location of any leak.
Additionally, as part of LMC 13, a leak detection system was installed over the Edwards Aquifer
Recharge Zone and the Slaughter Creek watershed in the Edwards Aquifer Contributing Zone
that will detect a leak of extremely minute volume in twelve (12) to one hundred twenty (120)
minutes from contact, depending upon the product sensed by the system. The leak detection
system consists of a buried hydrocarbon sensing cable system designed to meet the leak
detection performance specifications. The pipeline system is designed to achieve emergency
shut down within five minutes of a probable leak indication.
5-40

<<<PAGE 670>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.4.2 Control Room Procedures
For the purposes of monitoring and control from the Magellan Operations Control Center in
Tulsa, Oklahoma, the Magellan Pipeline System is divided into eight consoles. The Longhorn
Pipeline is assigned to Console One. Each console is under the control of a Pipeline Controller
who continually monitors the pipeline operations. Each of these controllers works a 12-hour
shift. A supervisor is generally present in the control center on weekdays and is on call at other
times. Controllers can start and stop flow of product into the pipeline from supply points, start
and stop pumps, operate valves, and monitor pipeline pressures, flow rates, product densities,
and temperatures. The control room is therefore an important component of the leak detection
system since potential leak indications are diagnosed and responded to from there. Detailed
procedures for all control room operations are contained in the SIP.
Recent PHMSA regulation CFR 195.446 requires robust Control Room practices in the areas of
controller fatigue mitigation, alarm management, change management, lessons learned from
operating experience, training and compliance validation. Several American Petroleum Institute
standards are incorporated by reference in CFR 195.446 such as American Petroleum Institute
RP 1165 and American Petroleum Institute RP 1168 (section 5/7). CFR 195.446 must be fully
implemented by August 2012 and will be audited by PHMSA.
5.3.5 Pipeline Inspection and Testing
Pipeline integrity is ensured by two main efforts: (1) the detection and removal of any integrity
threatening anomalies to ensure the current pipe integrity; and (2) the avoidance of future
threats to the integrity. A defect is considered to be any undesirable pipe anomaly such as a
crack, gouge, dent, or metal loss, which could lead to a leak or spill during operations. Possible
defects include seam weaknesses associated with low-frequency ERW and electric flash
welded pipe, dents or gouges from past excavation damage or other external forces, external
corrosion wall loss, internal corrosion wall loss, lamination defects, pipe body cracks,
circumferential weld defects, and hard spots.
The purpose of inspection and testing is to validate the structural integrity of the pipeline and its
ability to sustain the operating pressures and other anticipated loads. The protocol is to test
and/or inspect the pipeline system at frequent enough intervals to ensure pipeline integrity
despite the possible advancement of time-dependent failure mechanisms.
Inspections and testing methods consist of those mandated by regulations as well as those that
are independently initiated by the operator. Some methods of inspection and testing are listed in
Table 5.3.5-1.
The results of testing and inspection are critical inputs into the risk assessment. Risk factors that
are strongly influenced by these results include:
• Knowledge of active failure mechanisms such as corrosion, cracking, and external
forces
5-41

<<<PAGE 671>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Knowledge of effectiveness of mitigation of all threats
• Knowledge of pipe’s ability to resist future failure mechanisms
• Analysis of ability to successfully intervene in a failure scenario, thus preventing that
failure.
Current integrity management regulations recognize three methods by which integrity can be
assessed: pressure testing, ILI, and direct assessment. Magellan uses the first two methods.
Within the liquid pipeline industry, direct assessment is only utilized when pressure testing or ILI
is not an option. Information on pressure testing and ILI is discussed in this section.
5.3.5.1 Pressure Testing
A pressure test is used to confirm the ability of the pipeline to sustain its specified operating
pressure and establish a safety margin relative to MOP. Hydrostatic pressure testing, often
called ‘hydrotesting,’ is the most common form of pressure testing. In this document, phrases
such as pressure test and hydrostatic test are used interchangeably with the former being the
more general descriptor.
Pressure testing is beneficial in countering integrity concerns by removing critical defects.
Pressure testing to a level significantly higher than operating pressure (usually 1.25 times MOP
or more) adds a margin of safety since any defects of a size and configuration that would cause
the pipe to fail operating pressures, would have been detected during such pressure tests.
Remaining flaws that did not fail at test pressure should not fail at the lower pressure associated
with MOP unless further flaw growth occurs.
The safety margin provided by the pressure test will normally decrease over time because the
test only verifies the pipe integrity at the time of the test. The probability of defect growth and
addition since the test date must be considered. Since a new defect could be introduced at any
time or defect growth could accelerate in a localized region, the test usefulness is tied to other
operational aspects of the pipeline. Introduction of new defects could come from a variety of
sources, such as third-party activities or corrosion. For this reason, pressure test data have a
finite lifetime as a measure of pipeline integrity without other supporting evidence such as
documentation of continuing CP, monitoring of internal corrosion, ILI, a strong damage
prevention program, and fatigue analysis. All of these are aspects of Magellan’s SIP.
Prior to startup (2005), Longhorn hydrostatically tested the pipeline for a minimum of 8 hours in
accordance with 49 CFR Part 195 Subpart E requirements from East Houston to Crane
including all hypersensitive (Tier 3) and sensitive (Tier 2) areas.
A summary of pressure tests performed on the System from 1995 through 2004 is shown in
Table 5.3.5-2. The more recent tests performed between 2005 and 2011 are shown in Table
5.3.5-3.
5-42

<<<PAGE 672>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.5.2 In-Line Inspection (ILI)
For a pressurized pipeline, the pipe wall thickness is designed to safely accommodate the
expected operating stresses, including normal operating pressure, surge pressure, external
forces (e.g., traffic loadings), the weight of the pipe itself, and other factors. Loss of wall
thickness reduces the pipe’s ability to withstand such loads. In addition, any abrupt changes in
wall thickness or shape can amplify the stress level in the pipe wall, potentially contributing to
failure. Therefore, the detection of anomalies, which reduce the wall thickness or which have the
potential to amplify the stress level in the wall, is an important preventative measure.
ILI, also called “smart pigging” or “intelligent pigging,” is the use of an electronically
instrumented device, travelling inside the pipeline that measures characteristics of a pipe wall.
The industry began to use these tools in the 1980s. The pipe conditions found which may
require further inspection are referred to as anomalies.
General and detailed discussions of these tools are available in the technical literature. PHMSA
regulations require that all new pipe installations be designed to accommodate ILI devices. The
pipeline diameter, fittings, valves, and other parts of the pipeline must therefore be able to
accommodate the passage of these devices. The PHMSA Integrity Management Plan (IMP)
regulations recognize ILI as a valid technology for integrity assessment in an IMP. The state-of-
the-art for ILI has advanced to the point that many pipeline companies are basing integrity
management programs primarily around such inspections.
Many pipe anomalies that are of a size that would not be detectable under a normal pressure
test can be detected through ILI. However, anomaly detection is not 100% accurate even with
the most advanced techniques. Many factors affect the number and size of undetected flaws.
These include conditions under which the inspection is made such as speed of travel, fluid
properties, and distance traveled; tool type; tool accuracy; calibration; and interpretation of data
among others. Uncertainties regarding true system strength will remain even after inspection,
and similar to the pressure test, ILI test results are valid for a finite time period. General types of
anomalies that can be detected and characterized to varying degrees by ILI include:
• Geometric anomalies (dents, wrinkles, out-of-round pipe);
• Metal loss (gouging and general, pitting, and channeling corrosion); and
• Laminations, cracks, or crack-like features.
More significant features (i.e., those that have larger dimensions) are more reliably detected.
Some examples of available ILI devices are: geometry tools, magnetic flux leakage tools, and
ultrasonic tools. These can be further categorized based on their configurations for increased
sensitivity to certain flaw types. For example, a circumferential Magnetic Flux Leakage (MFL)
tool uses the MFL detection technology in a specialized way to increase sensitivity to crack
detection and sizing
Each of these tools has specific applications. Most tools can detect previous third-party damage
or impacts from other outside forces. Geometry tools are used to locate pipe deformations such
5-43

<<<PAGE 673>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
as dents or out-of-round areas. Magnetic flux leakage tools identify areas of metal loss.
Ultrasonic wall thickness tools detect general wall thinning and laminations. So called “crack
tools” are specifically designed to detect cracks, especially those whose orientation is difficult to
detect by other means.
Currently, no single tool is superior in detecting all types of anomalies. Depending on vendor
specifications and ILI tool type, detection thresholds can vary. The degree of resolution (the
ability to characterize an anomaly) also depends on anomaly size, shape, and orientation in the
pipe. The probability of detecting an anomaly using ILI increases with increasing anomaly size.
Smaller anomalies as well as certain anomaly shapes and orientations have lower detection
thresholds than others. Vendors report detection thresholds for various anomaly types and
orientations with probabilistic detection capabilities. Higher confidence detection thresholds for
general corrosion are commonly stated as a depth sizing accuracy of ±10 to 15% of wall
thickness, for MFL type ILI.
Severity of an anomaly is a function of not only depth but also other dimensions and orientation.
Several industry-accepted methods exist for determining severity of certain anomaly types and
for evaluating the remaining strength in corroded pipe. ASME B31G, ASME B31G Modified, and
RSTRENG are examples. These calculation routines require measurements of the dimensions
and configuration of corroded areas. Depending upon the depths and proximity to one another,
some areas will have sufficient remaining strength despite the corrosion damage. The
calculation determines whether the area must be repaired. Metal loss is characterized as
“significant” based upon the depth or the ratio between the predicted failure pressure and the
operating pressure. This generally accepted method is a valid approach for addressing
corrosion integrity concerns. Magellan was required to run three separate types of ILI tools as
part of the commitments under the LMP. These three tools included: 1) Magnetic Flux Leak
(MFL), 2) Transverse Flux Inspection (TFI), and 3) Ultrasonic Wall Measurement (UT). ILI tool
run dates are shown in Table 5.3.1-1.
5.3.5.2.1 ILI Findings
MFL Inspection (December 2005 - November 2008) LMC 11 required conducting a high-
resolution MFL inspection in the pipeline between Galena Park (Valve J-1) and Crane within
three months of startup (2005). Although delayed by unforeseen circumstances (low throughput
of product and the presence of debris in the pipeline), the inspections were completed on all
required segments by February 2007. Inspections for the Crane to El Paso segment were
completed by November 2008. Electronic Geometry Pig (EGP) inspections were conducted in
conjunction with the MFL inspections (as per LMC 12a) to evaluate for pipeline deformation
resulting from dents and mechanical damage.
TFI Inspection (March 2007 – January 2008) LMC 10 required that a ILI crack detection tool run
be performed no more than three years after system startup. These tool run inspections were
completed by January 2008 and associated rehabilitation was completed. Electronic Geometry
Pig (EGP) inspections were conducted in conjunction with the TFI inspections (as per LMC 12a)
to evaluate for pipeline deformation resulting from dents and mechanical damage.
5-44

<<<PAGE 674>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
UT Inspection (September 2009 – July 2010) Per LMC 12, Longhorn conducted an ILI of the
existing pipeline (Valve J1 to Crane) with an UT wall measurement tool to verify wall thickness
as described by the SIP (Section 3.5.2 and the associated ORA (Section 4.0). This inspection
was completed in 2010 and subsequent remediation was completed following the inspections.
Electronic Geometry Pig (EGP) inspections were conducted in conjunction with the UT tool
inspections (as per LMC 12a) to evaluate for pipeline deformation resulting from dents and
mechanical damage.
The presence of laminations as detected by the UT wall measurement tool becomes more
important under the Proposed Project due to the potential for hydrogen blistering in Crude Oil
Service. This was discussed in more detail in section 5.3.1.3. A total of 8183 laminations were
identified by the UT tool. These are summarized as follows:
• Galena Park to Satsuma – 1695 (1689 planar, 6 variable depth)
• Satsuma to Warda – 1082 (290 planar, 777 intermittent, 6 bulging, 2 sloping, 7 variable
depth)
• Warda to Cedar Valley – 541 (140 planar, 392 intermittent, 3 bulging, 2 sloping, 4
variable depth)
• Cedar Valley to Eckert – 594 (134 planar, 446 intermittent, 14 variable depth)
• Eckert to Ft. McKavett – 1907 (612 planar, 1255 intermittent, 2 bulging, 12 sloping, 26
variable depth)
• Ft. McKavett to Crane – 2364 (600 planar, 1743 intermittent, 10 bulging, 8 sloping, 3
variable depth)
Magellan’s In-Line Analysis Technical Specification, 7.03-ADM-003, requires the vendor to
identify lamination indications detected in the pipeline. Based upon criteria determined by third
party consultants and Magellan, the following features are designated as meeting criteria for
investigation:
• Sloping
• Bulging
• Surface Breaking
• Hydrogen Blisters
• Laminations interacting with other features are evaluated to determine if investigation
and repair is warranted.
The features are then added to the dig list for excavation and repair per 7.03-ADM-007, Section
15.1; 7.03-ADM-003, Section 5.4. Repairs are conducted in accordance with 7.01-ADM-001,
Pipeline Defect Evaluation and Repair Procedure. All injurious laminations were repaired.
Table 5.3.1-2 provides a summary of anomalies detected by ILI tool type for all three ILI’s
conducted since the pressure test.
5-45

<<<PAGE 675>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.5.2.2 Follow-up Excavations
After receiving an ILI indication of a potentially injurious anomaly, an excavation is required to
more accurately inspect the pipe and make repairs. Excavating to inspect the pipe is also used
to validate the ILI results and determine the actual sizing inaccuracies associated with a specific
ILI.
Certain anomalies identified by ILI are investigated and repaired according to pre-established
criteria. Some criteria are mandated by regulation. For example, certain anomalies on pipe
segments within High Consequence Areas (HCAs) require investigation and repair within
specified time constraints. Other criteria are voluntarily adopted by an operator or specified by
the LMP. The criteria in use by Magellan are specified in SIP-ADM-7.03 (Appendix 5A) and are
in accordance with the requirements of the 49 CFR Part 195 and the LMP. A summary of the
criteria is contained in Table 5.3.5-4.
In addition to the established criteria, a Probability of Exceedance (PoE) analysis is also
performed on all detected metal loss anomalies. This process is outlined in the LMP and is used
to calculate the probability for every anomaly that its tool-predicted dimensions are actually
larger than predicted dimensions by an amount sufficient to reach depth or pressure based
repair criteria. The analysis further utilizes established estimated corrosion rates to predict when
each anomaly would reach repair criteria. Response plans are then formulated to investigate all
anomalies well in advance of their predicted time to failure. Following the initial MFL inspection,
anomalies with calculated probabilities greater than 1 in 10 million (1E-7) were addressed. This
equates to any metal loss anomaly with a depth greater than 34% of the pipe wall thickness or
calculated safe pressure less than the maximum operating pressure at the location of the
feature. This ensures that each feature has a safety factor of 1.39 times maximum operating
pressure. Additionally, following the UT, MFL, and future metal loss inspections a corrosion
growth rate is applied to all metal loss anomalies to determine when the feature might grow to a
POE level of 1E-5 or depth of 44%. The time interval for unaddressed metal loss to grow to a
POE level of 1E-5 is then determined to be the re-assessment interval. As a result of these
repair criteria, any metal loss features with a remaining strength less than 1.39 times the
maximum operating pressure at the location of the feature or with indicated depths greater than
44% have been repaired.
In some instances, anomalies will be investigated by Magellan even when not mandated by the
pre-established criteria or POE process. Regarding the criteria for repair and the way in which
such repairs and replacements were undertaken, there are no findings of inadequacies in the
ORAs, self-audits, or PHMSA audits.
Table 5.3.1-2 provides a summary of anomalies repaired by ILI tool type for all three ILI’s
conducted since the pressure test.
5-46

<<<PAGE 676>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
5.3.5.3 Visual and NDE Inspections
This section is restricted to a discussion of coating inspection and inspection of pipe that is
exposed. Visual inspections are required by regulations whenever a buried pipe is exposed and,
as a matter of course, for other parts of the System that are normally observable. Routine
inspections of the System as a whole are covered in the section on Third Party Damage
(5.3.1.11).
Magellan’s SIP Element 7.04–ADM–005 (Appendix 5A) details specific steps to take and
documentation for all pipe that is unearthed that includes coating condition, soil conditions,
evidence of corrosion, and other useful information. Spreadsheets of results of ILI-prompted
excavations were provided for this FEA. Comments by inspectors provide valuable insight into
conditions found, accuracy of ILI reports, and possibilities for future damages. The data is
evaluated and written comments are considered by Magellan’s subject matter experts.
5.4 ACCIDENTAL RELEASES
5.4.1 Leak Analysis
This section analyzes the spill history of the System. The purpose is to analyze the historical
frequency, causes, and consequences of past leaks and spills, as an indicator of possible future
performance. Data on releases provided by Magellan has been summarized in Table 5.4.1-1 -
Pipeline and Facility Spill Data Since 2002; Table 5.4.1-2 - Summary of Cause of Release for
Facilities; and Table 5.4.1-3 - Summary of Cause of Release for Pipeline.
There have been 42 documented leaks since 2002. Of these, 38 have occurred in facilities and
4 on the pipeline. All have impacted soil and none have impacted water bodies. One release
was of water used for hydrotesting, 2 were water/product mixes, one was IVD additive, one was
corrosion inhibitor, and one was hydraulic fluid and the remaining 36 were hydrocarbon
products (diesel, gasoline, oil, etc.).
The largest release, 119 barrels, was of hydrotest water prior to start of operations. Slightly over
7.5 barrels of additive/hydrocarbons were released between July 2002 and January 2005 in 14
incidents prior to start of operations related to various commissioning activities. Since
operations began, there have been 28 documented releases amounting to 44 barrels. There
were four incidents over 5 barrels accounting for 29 of the 44 barrels. Eight of the 28 releases
were of a nature to be classified as reportable under PHMSA definitions. One of the eight was
classified as a pipeline release and the remaining were classified as facility releases.
5.4.1.1 Leak Causes
As noted above, the primary locations of leaks were in facilities. These include rotating
equipment mechanical failures (e.g., pump seal failures), tank corrosion, or operating errors
(e.g., not taking action to stop a relief tank overflow caused by equipment malfunction). Table
5.4.1-2 shows the causes for the 38 facility leaks. The leading cause was equipment failure
5-47

<<<PAGE 677>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
(21), followed by human error (16). Table 5.4.1-3 shows the causes for the four pipeline leaks.
The leading cause was equipment failure. Three of the four incidents resulted from small valves
of 2 inch or lesser size malfunctioning. The fourth was a leak that initiated during a repair
operation.
In compliance with SIP-ADM 13.02 (Appendix 5A), Magellan conducts incident investigations
and incorrect operations mitigation review for the Longhorn assets on a quarterly basis to
assess data and reduce the potential for human error in the design, construction, maintenance,
and operational activities that could impact the mechanical integrity of the assets,
5.4.1.2 Comparisons with Other Pipeline Leak Data
Magellan contracted with Allegro Energy Consulting to extract mainline pipe only incident data
for the years 2010-2011 as a benchmark comparision for the risk threshold of 1E-4 mainline
incidents/year. This equates to 0.1 incidents/1000mile-year. This compares to the onshore
pipeline PHMSA reportable incident rate for mainline pipe only of 0.830 incidents/1000mile-year
for crude oil pipelines or 0.695 incidents/1000mile-year for crude and refined product pipelines
combined. The Texas reportable incident rate for mainline pipe only was reported to be 1.057
incidents/1000mile-year for crude oil pipelines and 0.838 incidents/1000mile-year for crude and
refined product pipelines combined.
Tables 5.4.1-4 and 5.4.1-5 show the overall pipeline and facilities incident rate for Texas and US
reportable incidents for the decade 2001 to 2010. This data is compared in Table 5.4.1-6 to
Longhorn Reportable incidents for the period since commissioning activities began in 2002 and
the period since operations began in January 2005. This table shows that leak volumes and
incident frequencies for the Longhorn pipeline are below the averages for other Texas and US
pipeline populations since the start of operations and commissioning.
5.4.2 Spill and Emergency Response Plan
This section deals with the response of the operator, contractors, and public agencies to a
pipeline spill. Compliance with regulations, adequacy of planning/preparations to protect
sensitive areas, response time, and coordination between various response entities are
considered in effective emergency response planning.
5.4.2.1 Compliance with Regulations
Planning and responding to spills from pipeline operations is regulated under several different
federal and state programs, including:
• 49 CFR Part 194;
• 49 CFR Part 195;
• Oil Pollution Act of 1990;
• OSHA HAZWOPER; and
5-48

<<<PAGE 678>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• TCEQ Spill Prevention and Control (Texas Administrative Code Chapter 327).
In addition, there are various industry guidelines that suggest the format and content of an
appropriate emergency-planning program. The ANSI B31.4 and American Petroleum Institute
Recommended Practice 1129 are examples of such guidelines that were used for comparison
to the Longhorn emergency response planning.
Present operations are formalized under the following: Longhorn Pipeline Oil Spill FRP;
Magellan SIP. The FRP is specific to the Longhorn Pipeline and was developed primarily to
comply with the requirements of OPA ‘90 and 49 CFR Part 194. The plan was originally
submitted to PHMSA on November 2, 1998 for review and approval, then updated on March 24,
2000. The FRP is reviewed annually and modified as needed. The most recent PHMSA
submittal was October 8, 2012 and reflects the pipeline reversal and change in product. The
FRP contains information on spill response planning, training, resources and procedures. The
plan includes:
• Notification procedures for initiating a response and for regulatory reporting;
• Release detection procedures and release mitigation procedures;
• Description of initial response actions, including immediate response steps, securing the
source of the spill, safety and health considerations, storage/disposal of waste materials,
endangered species and wildlife rehabilitation, and documentation of the response;
• Description of response teams and their responsibilities (all operations and maintenance
personnel have the authority to act as the Incident Commander/ Qualified Individual);
• Communication equipment;
• Personnel and resources available for responding to a spill, including the operator and
oil spill response contractors (Employees are generally located within a one-hour
response time along the pipeline. The operator has response agreements with
emergency response contractors that have equipment and personnel located in
Houston, San Antonio, Austin, Eastland, Midland/Odessa, and El Paso. The contractors
are required to meet or exceed the requirements of 49 CFR Part 194); and
• Containment and diversion booming strategies to protect human life and sensitive
resources.
The pipeline is mapped on 1:100,000 US Geological Survey (USGS) topographic maps that
indicate any lakes, rivers, and streams within five miles of the pipeline. The topographic maps
also indicate the potential down gradient flow direction from the pipeline locations.
Environmentally sensitive areas are mapped within a radius of one mile of the pipeline per 49
CFR 194.103. Beyond 49 CFR Part 194 requirements, detailed mapping on USGS 7.5-minute
topographic maps is included for at least 15-miles downstream on river crossings and in the
Houston and Austin areas. Mapping also includes aerial photos of the Houston and Austin
areas.
The spill training program for field employees includes spill response training, incident command
training, and OSHA’s HAZWOPER training. Tabletop exercises or Mock Drills are conducted
annually for the Longhorn system and included as part of the spill training. Magellan encourages
5-49

<<<PAGE 679>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
and invites local response agencies to participate in periodic tabletop and spill response
exercises.
An Austin Sub-area Plan was prepared to provide more detailed response information beyond
the scope of OPA Plan requirements. This plan includes map locations for known caves and
detailed response strategies for the creek crossings in the Austin area.
Magellan meets yearly with Local Emergency Planning Committees to work towards appropriate
emergency response awareness.
Volume I of the FRP presents emergency planning information that is general in nature and
common to all portions of the pipeline. Volume II of the FRP addresses specific response zones
and sensitive along the pipeline system.
Within each of these two response zones, a number of sensitive areas have been identified for
a higher degree of specific planning:
• Initial Response Actions (IRAs); and
• Tactical Response Plans (TRPs).
The Longhorn FRP complies with the requirements for emergency planning and preparedness
in the applicable regulations.
5.4.2.2 Sensitive Areas Response
This subsection addresses how the Longhorn FRP has identified and planned response for
sensitive areas along the pipeline. As discussed in the previous subsection, Volumes I and II of
the FRP includes IRAs and TRPs in Section 4 to address specific response issues. The IRAs
are multi-page tabular checklists of emergency planning information that include:
• Initial responder actions;
• Area Supervisor/Qualified Individual actions;
• Estimated response times for Magellan and contractor personnel;
• Local emergency management agencies;
• Listing of environmentally sensitive areas near the pipeline section;
• Contractor resources that would be used in the response;
• Fire and public safety cautions; and
• Information about threatened and endangered species.
One IRA is typically done for each county that the pipeline crosses. The TRPs are on a folded
11x17-inch page presented in a color page layout format.
The TRPs include:
• Color map showing the route to access the site
5-50

<<<PAGE 680>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Tabular driving directions to access the site
• Text box containing the response strategy
• Tables estimating the personnel and equipment required to implement the response
• Photos and/or drawings illustrating the implementation of the strategy (such as where
booms or dams would be installed, where the vacuum truck would park and similar
considerations); and
• Series of photos assembled into a panoramic view of the site with annotations added for
directions of flow of any water bodies.
There are typically several TRPs per county. The TRPs are primarily associated with water
crossings and sites down gradient from water crossings where spilled oil can be contained and
collected.
The FRP also includes a detailed set of pipeline routing maps that show highways, population
centers, schools, hospitals, parks/recreation areas, aquifers, water intakes, and waterways.
These maps have been further annotated to show areas of known karst formations (caves),
potential work sites near the pipeline, road and creek crossings, and details on the Edwards
Aquifer. A complete listing of sensitive areas is provided along with a reference to the map or
maps on which they are shown, as well as contact information for the sensitive areas. Volume 3
of the FRP contains detailed information as to public and private groundwater sources along the
pipeline. The volume also contains engineering drawings for water filtration systems for a series
of public water systems along the pipeline. In the event of a release, the water filtration systems
can be quickly constructed and attached to public water systems.
The LMP has specific requirements related to spill and emergency response within sensitive
areas. The following summarizes those mitigation commitments.
Per LMC 23, a response center was established in South Austin which includes available
response equipment and personnel such that under normal conditions, a maximum two
hour, full response can be assured. Response resources have been developed at several
locations to assure attainment of the proposed response times. Response personnel and
equipment are in place.
Per LMC 24, Facilities Response Plans were revised to better address firefighting outside of
metropolitan areas (Houston, Austin, and El Paso) where HAZMAT units do not exist.
Training of selected volunteer Fire Department personnel that are staging emergency
response equipment trailers and enhanced Facility Response plans have been completed
and ongoing training is conducted.
Per LMC 26, Facility Response Plans were revised prior to startup to include more detailed
response planning for areas adjacent to the pipeline ROW which have high populations of
potentially sensitive receptors.
Per LMC 27, secondary containment was installed at the Cedar Valley pump station in Hays
County.
5-51

<<<PAGE 681>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Per LMC 28, Facility Response Plans were revised as necessary, to make them consistent to
the extent practicable, with the City of Austin’s Barton Springs Oil Spill Contingency Plan
and the U.S. Fish and Wildlife Service’s Barton Springs Salamander Recovery Plan.
Per LMC 30, provisions were made prior to startup to provide alternate water supplies to certain
municipalities and private well users as detailed in Longhorn’s contingency plans.
Per LMC 40, the river gauge at the Pedernales River is monitored to anticipate the possibility of
a flood event. When the river stage reaches 100,000 cfs at the gauge, Longhorn will
immediately shut down the pipeline until the river has receded below the action level
(100,000 cfs) at the gauge. Magellan personnel will inspect the pipeline to determine
whether it is safe before resuming pipeline operations. This measure will be implemented
for the operational life of the pipeline system.
5.4.2.3 Recent Emergency Response Experience
There have been no releases requiring emergency response from area Hazmat Response
Teams since the start of operations. However, as part of the response plans, annual mock
response drills are conducted to test emergency response capabilities.
5.4.2.4 Trench Integrity Assessment – Edwards Aquifer Recharge Zone
The pipeline crosses the Edwards Aquifer Recharge Zone south of Austin in Travis County.
This 3-mile segment of pipeline has undergone several enhancements designed to mitigate the
impacts to the environment from a pipeline release. These enhancements include thicker-
walled pipe; enhanced leak detection consisting of a hydrocarbon sensing cable; a control
system designed to achieve emergency shutdown with 5-minutes; and a sealed trench with
associated mitigation structures. The stated purpose of the pipeline trench design and sealing
protocol used along this 3-mile segment of pipeline was to ensure that no material volume of the
pipeline product would exit the trench and infiltrate into the underlying aquifer in the unlikely
event of a pipeline leak.
Two separate reports assessing the condition of the trench have been prepared by companies
and individuals who were directly involved in the original trench design, construction, and proof
of concept preparation. The first report, entitled, “Trench Integrity and Construction Methodology
of the Magellan Longhorn Pipeline from Mile Post 169.88 to 188.8” (October 2012), was
prepared by LBG-Guyton Associates and Hatch Mott MacDonald. The purpose of this
assessment was to evaluate the integrity of the trench design and to assess material
deterioration (Appendix 5C). According to the report, there are several factors controlling the
service life of the concrete and gunite used to seal the trench. The primary risk factors affecting
service life were determined to be: leaching; delayed ettringite formation; sulfate attack; acid
and base attack; salt crystallization; freezing and thawing; abrasion, erosion and cavitation;
thermal damage; and seismic and structural loads. The findings of the investigation indicate that
the service life for the gunite/concrete trench is expected to last 50 or more years. This
5-52

<<<PAGE 682>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
prediction is made with a high level of confidence considering the engineering safeguards
utilized during construction, lack of seismic and structural loads, and lack of physical and
chemical deterioration.
The second report, entitled “Trench Integrity Inspection Report of the Magellan Longhorn
Pipeline from Mile Post 169.88 to 173.38” (November 2012), was prepared by LBG-Guyton
Associates (Appendix 5D). This report summarizes a visual inspection of the sealed trench at
two separate locations within the recharge zone. Extraordinary precautions were taken during
excavation to minimize potential impact to the existing trench structure. A vacuum truck was
used which allows efficient excavation with air into hard soils without harming underground
utilities. The inspection revealed that the gunite and trench were in excellent condition at both
locations. The trench floor and walls were dry and the various components of the trench (fill
material, hydrocarbon sensing cable conduit, gunite liner and cap) appeared to be in original
condition after ten years. The poly coat spot treatment sealant was the only material observed
that exhibited any signs of deterioration (peel cracks and divots). This hand application of
sealant was used sporadically on blemeshes, surface anamolies, or lateral discontinuities to
ensure the underlying gunite provided a water-tight seal. It is possible that some of this
deterioration may have occurred during excavation activities. Based on these observations, it
was concluded that the pipeline trench design and sealing protocol used within the Edwards
Aquifer Recharge Zone will continue to prevent a material volume of fluid from exiting the trench
and infiltrating into the underlying aquifer.
The conclusions of these two investigations suggest that the trench, road bore pits, diversion
berms, and trench sealing materials are performing as originally designed and would be
effective in containing a product release along the length of the trench. A detailed discussion of
the trench design is provided in the report entitled, “Results of Proof of Concept Tests to Verify
the Design and Construction Methods for the Longhorn Partners Pipeline Trench Over the
Edwards Aquifer Recharge Zone in Austin, Texas” prepared by LBG-Guyton Associates,
December 2001. This document has been uploaded to the docket and is available for review.
5.4.3 Consequence Potential (CoF)
This FEA uses a fixed distance buffer, 1,250 feet either side of the centerline, combined with an
overland flow spill analysis to evaluate receptor damage potential at distances from the pipeline.
This is called the “Zone of Potential Impact” and is used to determine potential impacts
described in Chapter 7.
For the overland flow analysis, product drain down volume is calculated for selected points
along the pipeline. The potential drain down volume is then combined with 5 minutes of
maximum flow volume to arrive at a total maximum estimated release volume for a selected
point on the pipeline. Maximum estimated release volumes for selected points along the pipeline
are shown in Table 5.2.6-3. These volumes are calculated based upon proposed locations of
Remotely Controlled Valves (RCVs) for the Proposed Project.
5-53

<<<PAGE 683>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
The estimated maximum release volumes are overlaid onto a USGS Digital Elevation Model
(DEM) 30-meter grid. A “Least Resistance Path” algorithm is used to determine topological flow
direction across the DEM grid. Flow distance is determined by “filling” each DEM grid with a
one-half inch of product volume and continuing with the flow direction until the total product
volume for the selected point is exhausted.
Although 100-ft grids were ‘filled’ in this process, a flow path line was generated. To produce a
polygon from the flow paths, a 400-ft buffer (200 feet either side of the line) was added. This
allowed a safety factor of at least one grid (on a diagonal (171 feet for a 100-ft square grid)).
Thermal effects, surface flow resistance, soil penetration, inclusion of local flow-enabling
features smaller than the DEM resolution, and other process details have not been provided.
The rigorous calculations performed in the 1999 EA offer confirmation of currently used hazard
zones.
5.5 CONCLUSIONS
The existing processes, programs and procedures as detailed within the SIP form the
cornerstone of integrity for the pipeline and facilities assets that make up the System. The
procedures within the SIP are influenced and shaped by applicable regulations including the
LMP and industry standards. The execution of the LMCs and associated procedures within the
LMP have resulted in an operating pipeline system with a low incident rate as envisioned and
stipulated in the 1999 EA.
5.6 REFERENCES
Allegro Energy Group, Data provided to Radian International, 1999.
Deaver, R.L., Memorandum, “Longhorn Project – Analysis of DOT Accident Reports on Exxon
Pipeline Company,” 1998. Department of Transportation Office of Pipeline Safety,
dot.ops.gov.
Fields, R.J., E.N. Pugh, D.T. Read, J.H. Smith, “As Assessment of the Performance and
Reliability of Older ERW Pipelines,” US Department of Commerce, NISTIR 89-4136, July
1989.
Fluor Daniel Williams Brothers (FDWBC), Longhorn Partners Pipeline, Phase 1 Environmental
Site Assessment, Volume 1, September 1995, pp. 1-116
Harris, O.B., Telephone Contact Report, May 18, 1999. IT Corporation. “Study of Aseismic
Faults and Regional Subsidence Along Longhorn Partners Pipeline,” June 14, 2000.
Johnston, D.C. and J.F. Kiefner, “Audit of Existing Portions of Longhorn Pipeline,” Kiefner &
Associates, February 24, 1999.
Johnston, D.C., and Kiefner, J.F., “Audit of Existing Portions of Longhorn Pipeline”, February 24,
1999, Final Report to Jenkins and Gilchrist.
Kiefner & Associates, Mock ORA, RAD 41578-41656, October 2000.
5-54

<<<PAGE 684>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Kiefner, J.F. and Vieth, P.H., “When Does a Pipeline Need Revalidation? The Influence of
Defect Growth Rates and Inspection Criteria on an Operator’s Maintenance Program” in
Pipeline Rules of Thumb Handbook. E.W. McAllister (Ed.), Gulf Publishing Co., Houston,
Texas, 1998.
Kiefner, J.F., Johnston, D.C., “Root Cause Analysis of Accidental Releases on the Former
Exxon 18-inch Kemper-to-Satsuma Crude Oil Pipeline (Longhorn Mitigation Commitment
19C, Longhorn Mitigation Plan)”, April, 2004, Final Report to Longhorn Pipeline Partners
King, F., “Hydrogen Effects on Carbon Steel Used Fuel Containers”, December 2009, Nuclear
Waste Management Organization Report TR-2009-29
Lees, F.P., “Loss Prevention in the Process Industries,” Vol. 3, Butterworth’s, 1996. Longhorn
Partners Pipeline, Longhorn PDEA, Longhorn Project Description, March 1, 1999.
Longhorn Mitigation Plan, Introduction, revised September 11, 2000.
Longhorn Partners Pipeline, “Integrity Management System - Expectations and Guidelines,”
URS Radian No. 1049.
Longhorn Pipeline Final Draft Environmental Assessment, 2000. URS Radian.
Longhorn Pipeline Partners, “OPA Plan (DOT),” URS Radian No. 206. LUFT (1988) “Leaking
Underground Fuel Tank Manual: Guidelines for Site Assessment, Cleanup, and
Underground Storage Tank Closure,” State of California Leaking Underground Fuel
Tank Task Force, May 1988.
M. Beller, K. Reber, U. Schneider, “Tools, Vendors, Services - A Review Of Current In-Line
Inspection Technologies”, 2002 Conference Proceedings: “The Pipeline Pigging
Conference,” Pipe and Pipeline International, Kuala Lumper, June 30-July 2, 1998.
McDaniel, Mary (Railroad Commission of Texas), Letter and Enclosed “Evaluation Report of a
Liquid Pipeline Carrier,” to Mr. James C. Thomas, Office of Pipeline Safety, DOT,
Houston, Texas, April 30, 1996.
Muhlbauer, W.K., “Pipeline Risk Management Manual, 2nd Edition,” Gulf Publishing Co., 1996.
National Association of Corrosion Engineers (NACE), 2003, “Review of Published Literature on
Wet H2S Cracking of Steels through 1989”, September 2003, Item No. 24185, NACE
International.
National Association of Corrosion Engineers (NACE), Standard Recommended Practice,
Control of External Corrosion on Underground or Submerged Metallic Piping Systems,
RP 0169-96, Item No. 21001, NACE International, Houston, Texas, 1996 (ISBN 1-
57590-035-1).
Pearson, M., Meeting contact with Mike Pearson, Williams Energy Services, April 28, 1999.
Pennwell Maps, http://www.mapsearch.com/ines.html
Proceedings of the 1996 Pipeline Reliability Conference. “Designing a Cost-Effective and
Reliable Pipeline Leak-Detection System,” Houston, Gulf Publishing Company and
Scientific Surveys Ltd., 1996.
Railroad Commission, Letter, Safety Evaluation of EPC pipeline from Crane to Satsuma, April
30, 1996,
URS Radian No. 148. Title 49, Code of Federal Regulations, Part 192, “Transportation of
Natural and Other Gas by Pipeline: Minimum Federal Safety Standards.
5-55

<<<PAGE 685>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
URS Radian, Compilation of Data Summaries and Other Supporting Information to Longhorn
Environmental Assessment, August 1999.
5-56

<<<PAGE 686>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 5
TABLES

<<<PAGE 687>>>

Audit Date 4/1/2004 4/1/2004
4/11/2005
4/11/2005 4/11/2005 4/11/2005 4/22/2005 10/14/2005 10/14/2005 10/14/2005 10/14/2005 8/8/2006 8/8/2006 8/8/2006 8/8/2006 Table 5.1.1-1 Compliance Audit Findings
Summary of Finding Remediation
1A. failure to ensure through evaluations that individuals
performing covered tasks are qualified not contested
1B. Respondent failed to provide records to demonstrate that three hundred
and fifteen (3 15) of its employees were properly qualified to perform the
covered task under Respondent's operator qualification (OQ) program
1. On December 29,
2005, Respondent submitted additional
records.
Item 1 - IMP failed to include a technically justifiable method for identifying
segments that could affect an HCA. Overland Spread analysis criticized; drain-
down criticized
Modified overland spread calculation
method. Adjusted HCAs and conducted
additional digs
Item 2A - Failure to follow procedure for assessing Highest risk first Withdrawn By PHMSA
Item 2B - Relative risk scores did not adequately reflect PoF. Modified risk algorithms
Item 3 - Inadequate procedures for placement of EFRD's Modified procedures
LMC Inadequacies in addressing low flow conditions identified by PHMSA Respond to PHMSA recommendations for
procedural changes
Procedures did not reference American Petroleum Institute 1104 19th Ed Procedures corrected
1A. Did not inspect rectifiers monthly
1B. Did not inspect critical bonds monthly
Caused by failure of employee, duties
transferred to a NACE certified employee.
2C. Many valves not protected from vandalism
LH formally disagrees with "fencing"
interpretation but installs fencing in spirit of
cooperation (420065032 PHMSA LH
Fencing Response 06-20-08.doc)
Procedures did not reference American Petroleum Institute 1104 19th Ed Procedures corrected
1. insufficient line marking Completed
2. Exceeding valve maint interval
3.Some valves not protected from vandalism
Completed
4. Failure to adequately inspect breakout tanks according to Sec 4 American
Petroleum Institute 653
Completed
5. Failure to adequately inspect CP on B/O tank according to American
Petroleum Institute 651
Completed

<<<PAGE 688>>>

Table 5.1.1-1 Compliance Audit Findings (continued)
Audit Date Summary of Finding Remediation
8/8/2006 6. Failure to follow LMP for Leak Detect sensitivities and response time, video
monitoring of PS, ROW maint, encroachments
Completed
5/14/2007
Procedures do not adequately address the following:
1. Procedures to be located where activities are performed
2.A. Welding procedure and qualification records, and record retainage.
2.B. Piping Matrix Table to require visual examination
2.C. American Petroleum Institute 1104 ref (9 instead of 6) in procedures
2.D. Pressure tests without leakage.
2.E. Emergency Training cycle
2.F. Placement of line markers
2.G. movement of HVL PL under pressure
2H. Fire extinguisher inspection
2.I. Excavator notification for temp marker
2. J. MOP reduction resulting from corrosion pitting
3. Immediate response areas
4. 110% of MOP limit in start or SD
5. PL Inspection after Abnormal Ops
6. Reviews for effectiveness of Abnormal Ops
7. Minimizing volume of spill
8. Handling of RR traffic during Emergency
Revision of procedures
8/20/2007 Exceeding 15-mo interval for Emergency Training Revise from instructions
12/17/2009 1. Failure to follow LMP, LMC 39 Modified procedures

<<<PAGE 689>>>

Table 5.2.1-1a Pipe Characteristics
Segment
Segment
Length
(mi) Diameter Manufacturer
Seam
Type
Year
Built Type
ERW-
HF American
Petroleum
Institute 5L
X-52
Galena Park to East
Houston 9.55 20" U.S. Steel
American
Steel
1998
ERW-
HF 2010
American
Petroleum
Institute 5L
X-52
East Houston to
Crane 457 18"/20" A.O. Smith
EFW-
LF and
ERW-
LF
1947,
1950,
1953
American
Petroleum
Institute 5L
X-45, X-
52, GR B
U.S. Steel
ERW-
HF 1998
American
Petroleum
Institute 5L
X-65
Crane to El Paso 235 18"
Procarsa
ERW-
HF 2008
American
Petroleum
Institute 5L
X-52, X-
65
Crane to Odessa 29.27 8.625" California
Steel
ERW-
HF 1998
American
Petroleum
Institute 5L
X-60
Note: Predominant pipe information shown for each segment
Wall
Thickness
(in) 0.312,
0.344,
0.375 0.25,
0.344,
0.375 0.250,
0.281,
0.312,
0.375
0.281,
0.375, 0.5
0.281,
0.375, 0.5
0.188,
0.25
Coating
Fusion Bond Epoxy
Fusion Bond Epoxy
Coal Tar
Fusion Bond Epoxy
Fusion Bond Epoxy
Fusion Bond Epoxy

<<<PAGE 690>>>

LINE 6643 6643 6643 6643 6643 6643 6643 6643 6643 6643 6643 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 6645 Table 5.2.1-1b Pipe Characteristics Detail by Manufacturer
MANUFACTURER SEAM_TYPE YEAR_BUILT FEET MILES
AMERICAN STEEL ERW-HF 2010 13525.60 2.56
HALL LONGMORE ERW-HF 2011 24.00 0.00
HUSTEEL ERW-HF 2010 3594.80 0.68
HUSTEEL ERW-HF 2011 333.25 0.06
HYSCO ERW-HF 2010 1465.50 0.28
HYSCO ERW-HF 2011 126.00 0.02
STUPP STEEL ERW-HF 2010 17.60 0.00
U.S. STEEL ERW-HF 1998 31093.15 5.89
U.S. STEEL SMLS 1998 21.00 0.00
U.S. STEEL ERW-HF 2010 176.80 0.03
U.S. STEEL SMLS 2011 34.50 0.01
A.O. SMITH EFW 1947 134.75 0.03
A.O. SMITH EFW 1950 1743291.52 330.17
A.O. SMITH EFW 1953 264398.10 50.08
A.O. SMITH EFW 1967 24981.20 4.73
AMERICAN STEEL ERW-HF 1984 5291.00 1.00
AMERICAN STEEL ERW-HF 1995 47.00 0.01
AMERICAN STEEL ERW-HF 2000 5523.53 1.05
AMERICAN STEEL ERW-HF 2002 2433.00 0.46
AMERICAN STEEL ERW-HF 2004 1648.00 0.31
AMERICAN STEEL SMLS 2004 98.00 0.02
AMERICAN STEEL ERW-HF 2005 988.00 0.19
AMERICAN STEEL ERW-HF 2006 24.50 0.00
AMERICAN STEEL SMLS 2006 49.50 0.01
AMERICAN STEEL ERW-HF 2007 4018.00 0.76
AMERICAN STEEL ERW-HF 2008 68.00 0.01
AMERICAN STEEL ERW-HF 2010 4695.60 0.89
AMERICAN STEEL ERW-HF 2011 22001.00 4.17
APA PIPE CORP. ERW-HF 2010 212.00 0.04
CORUS ERW-HF 2006 17.00 0.00
CORUS SMLS 2006 16.00 0.00
HUSTEEL ERW-HF 2008 4856.00 0.92
HUSTEEL ERW-HF 2010 16103.70 3.05
KAWASAKI STEEL ERW-HF 1999 128.00 0.02
KAWASAKI STEEL ERW-HF 2000 108.50 0.02
KAWASAKI STEEL ERW-HF 2001 18.00 0.00
KAWASAKI STEEL ERW-HF 2002 465.75 0.09
KAWASAKI STEEL ERW-HF 2004 59.50 0.01
KAWASAKI STEEL ERW-HF 2010 47.00 0.01
KAWASHO ERW-HF 2007 45.00 0.01
MANNESMANN ERW-HF 2010 2154.00 0.41

<<<PAGE 691>>>

Table 5.2.1-1b Pipe Characteristics Detail by Manufacturer (continued)
LINE MANUFACTURER SEAM_TYPE YEAR_BUILT FEET MILES
6645 NAPA (FORMERLY KAISER) DSAW 2000 1534.00 0.29
6645 NAPA (FORMERLY KAISER) DSAW 2001 1904.50 0.36
6645 NAPA (FORMERLY KAISER) DSAW 2002 3695.00 0.70
6645 NAPA (FORMERLY KAISER) DSAW 2004 22.00 0.00
6645 NAPA (FORMERLY KAISER) DSAW 2010 9.00 0.00
6645 NIPPON STEEL ERW-HF 1998 2.00 0.00
6645 NIPPON STEEL ERW-HF 1999 229.00 0.04
6645 NIPPON STEEL ERW-HF 2000 361.75 0.07
6645 NIPPON STEEL ERW-HF 2002 2153.75 0.41
6645 NIPPON STEEL ERW-HF 2004 154.75 0.03
6645 PROCARSA ERW-HF 2008 212657.80 40.28
6645 STUPP STEEL ERW-HF 1998 5.00 0.00
6645 STUPP STEEL ERW-HF 2002 4794.50 0.91
6645 STUPP STEEL ERW-HF 2010 17.70 0.00
6645 SUMITOMO STEEL ERW-HF 1998 189.50 0.04
6645 SUMITOMO STEEL ERW-HF 2004 376.00 0.07
6645 TULSA TUBE SMLS 2004 11.00 0.00
6645 U.S. STEEL ERW-HF 1984 201.10 0.04
6645 U.S. STEEL ERW-HF 1998 1064683.30 201.64
6645 U.S. STEEL SMLS 1998 29.00 0.01
6645 U.S. STEEL ERW-HF 1999 85.30 0.02
6645 U.S. STEEL ERW-HF 2000 10693.10 2.03
6645 U.S. STEEL ERW-HF 2001 3011.00 0.57
6645 U.S. STEEL ERW-HF 2002 111576.00 21.13
6645 U.S. STEEL ERW-HF 2004 130.45 0.02
6645 U.S. STEEL SMLS 2004 59.00 0.01
6645 U.S. STEEL ERW-HF 2006 190.50 0.04
6645 U.S. STEEL ERW-HF 2008 48.75 0.01
6645 U.S. STEEL ERW-HF 2010 141.40 0.03
6645 UNITED ERW-HF 1998 124.00 0.02
6645 UNKNOWN ERW-LF 1947 124378.45 23.56
6645 UNKNOWN ERW-LF 1950 202.00 0.04
6645 UNKNOWN ERW-LF 1953 2515.00 0.48
6645 UNKNOWN ERW-HF 1979 346.00 0.07
6645 UNKNOWN ERW-HF 1982 598.00 0.11
6645 UNKNOWN ERW-HF 1987 84.00 0.02
6645 UNKNOWN ERW-HF 1988 677.50 0.13
6645 UNKNOWN ERW-HF 1995 654.00 0.12
6645 UNKNOWN ERW-HF 1998 1244.80 0.24
6645 UNKNOWN SMLS 1998 38.00 0.01
6645 UNKNOWN ERW-HF 2002 11.00 0.00
6648 AMERICAN STEEL ERW-HF 1998 134.00 0.03

<<<PAGE 692>>>

Table 5.2.1-1b Pipe Characteristics Detail by Manufacturer (continued)
LINE MANUFACTURER SEAM_TYPE YEAR_BUILT FEET 6648 AMERICAN STEEL SMLS 1998 19.50 6648 CALIFORNIA STEEL INDUSTRIES ERW-HF 1998 148237.00 6648 CALIFORNIA STEEL INDUSTRIES ERW-HF 2004 1296.66 6648 TEX-TUBE STEEL ERW-HF 2004 348.00 6648 U.S. STEEL ERW-HF 2004 4350.88 6648 U.S. STEEL SMLS 2004 135.91 MILES
0.00
28.08
0.25
0.07
0.82
0.03

<<<PAGE 693>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) Coating Seam Type 6643: Galena Park to East Houston 1998 5LX-52 0.0250 20 0.312 EPOXY PAINT ERW-HF 6643: Galena Park to East Houston 1998 5LX-52 5.8596 20
0.312,0.344,0
.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 1998
5LX-
52,GR. B 0.0043 20 0.375 PAINT ERW-HF 6643: Galena Park to East Houston 1998 GR. B 0.0040 20 0.375 PLASTIC TAPE/PAINT SMLS 6643: Galena Park to East Houston 2010 5LX-52 0.0018 20 0.375 FBE/PAINT ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 2.5617 20 0.25,0.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 0.6806 20 0.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 0.2776 20 0.25,0.344 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 0.0015 20 0.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 0.0335 20 0.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2010 5LX-52 0.0002 20 0.375 PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-60 0.0011 16 0.375 PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-60 0.0017 20 0.375 FBE/PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-42 0.0042 20 0.5 FBE/PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-42 0.0030 20 0.5 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2011 5LX-60 0.0599 20 0.375 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2011 5LX-42 0.0158 20 0.5 FUSION BOND EPOXY ERW-HF 6643: Galena Park to East Houston 2011 5LX-52 0.0043 20 0.375 FUSION BOND EPOXY SMLS 6643: Galena Park to East Houston 2011 5LX-42 0.0015 20 0.5 PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-60 0.0004 20 0.375 PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-42 0.0039 20 0.5 PAINT ERW-HF 6643: Galena Park to East Houston 2011 5LX-52 0.0023 20 0.375 PAINT SMLS 6645: East Houston to El Paso 1947 5LX-45 0.0255 18 0.281 COAL TAR EFW 6645: East Houston to El Paso 1947 GR. B 1.4363 20 0.312,0.375 COAL TAR ERW-LF 6645: East Houston to El Paso 1947 GR. B 0.0009 20 0.312 EPOXY PAINT ERW-LF 6645: East Houston to El Paso 1947 GR. B 0.0993 20 0.312,0.375 PLASTIC TAPE ERW-LF 6645: East Houston to El Paso 1947 5LX- 22.0200 20 0.312,0.375 UNKNOWN ERW-LF Manufacturer
U.S. STEEL
U.S. STEEL
U.S. STEEL
U.S. STEEL
STUPP STEEL
AMERICAN STEEL
HUSTEEL
HYSCO
STUPP STEEL
U.S. STEEL
HUSTEEL
HUSTEEL
HUSTEEL
HYSCO
HALL LONGMORE
HUSTEEL
HYSCO
U.S. STEEL
HALL LONGMORE
HUSTEEL
HYSCO
U.S. STEEL
A.O. SMITH
UNKNOWN
UNKNOWN
UNKNOWN
UNKNOWN

<<<PAGE 694>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 42,GR. B
6645: East Houston to El Paso 1950 5LX-45 326.3091 18
0.281,0.287,0
.312,0.375 6645: East Houston to El Paso 1950 5LX-46 0.0038 18 0.281 6645: East Houston to El Paso 1950 5LX-45 0.0502 18 0.281 6645: East Houston to El Paso 1950 5LX-45 0.1602 18 0.281,0.312 6645: East Houston to El Paso 1950 5LX-45 0.3121 18 0.281,0.312
6645: East Houston to El Paso 1950 5LX-45 0.0280 18 0.281 6645: East Houston to El Paso 1950
5LX-
45,5LX-
46 2.8237 18
0.281,0.287,0
.312,0.375 6645: East Houston to El Paso 1950 GR. B 0.0254 18 0.375 6645: East Houston to El Paso 1950 5LX-45 0.0076 18 0.281 6645: East Houston to El Paso 1950
5LX-
45,GR. B 0.4778 18 0.312,0.375 6645: East Houston to El Paso 1950
5LX-
42,5LX-
46 0.0091 18 0.312,0.375 6645: East Houston to El Paso 1953 5LX-52 50.0127 18 0.25,0.375 6645: East Houston to El Paso 1953 5LX-52 0.4763 18 0.25 6645: East Houston to El Paso 1953 5LX-52 0.0186 18 0.25
6645: East Houston to El Paso 1953 5LX-52 0.0441 18 0.25 6645: East Houston to El Paso 1967 5LX-65 4.7142 18 0.281,0.312 6645: East Houston to El Paso 1967 5LX-65 0.0045 18 0.281
6645: East Houston to El Paso 1967 5LX-65 0.0125 18 0.281 6645: East Houston to El Paso 1979 GR. B 0.0655 20 0.375 6645: East Houston to El Paso 1982 GR. B 0.0106 20 0.312 Coating COAL TAR COAL TAR EPOXY PAINT EPOXY/PE NON-SHIELDING TAPE
(RD-6) PAINT PLASTIC TAPE PLASTIC TAPE TAR SET UNKNOWN UNKNOWN COAL TAR COAL TAR NON-SHIELDING TAPE
(RD-6) PLASTIC TAPE COAL TAR NON-SHIELDING TAPE
(RD-6) PLASTIC TAPE COAL TAR EPOXY/PE Seam Type EFW ERW-LF EFW EFW EFW EFW EFW ERW-LF EFW EFW ERW-LF EFW ERW-LF EFW EFW EFW EFW EFW ERW-HF ERW-HF Manufacturer
A.O. SMITH
UNKNOWN
A.O. SMITH
A.O. SMITH
A.O. SMITH
A.O. SMITH
A.O. SMITH
UNKNOWN
A.O. SMITH
A.O. SMITH
UNKNOWN
A.O. SMITH
UNKNOWN
A.O. SMITH
A.O. SMITH
A.O. SMITH
A.O. SMITH
A.O. SMITH
UNKNOWN
UNKNOWN

<<<PAGE 695>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6645: East Houston to El Paso 1982 GR. B 0.1027 20 0.312 6645: East Houston to El Paso 1984
5LX-
42,5LX-
52,GR. B 1.0015 18 0.281,0.375 6645: East Houston to El Paso 1984 GR. B 0.0006 18 0.375 6645: East Houston to El Paso 1984 GR. B 0.0381 18 0.375 6645: East Houston to El Paso 1987 GR. B 0.0159 20 0.312 6645: East Houston to El Paso 1988 GR. B 0.0867 20 0.375 6645: East Houston to El Paso 1988 5LX-42 0.0416 20 0.375
6645: East Houston to El Paso 1995 5LX-45 0.0089 18 0.281 6645: East Houston to El Paso 1995 5LX-46 0.0284 18 0.281 6645: East Houston to El Paso 1995 5LX-42 0.0028 18 0.375 6645: East Houston to El Paso 1995 5LX-42 0.0068 18 0.5 6645: East Houston to El Paso 1995 5LX-52 0.0715 18 0.375 6645: East Houston to El Paso 1995
5LX-
42,5LX-
52 0.0144 18 0.375 6645: East Houston to El Paso 1998 5LX-52 0.0359 18 0.375 6645: East Houston to El Paso 1998
5LX-
52,5LX-
65 197.7403 18 0.281,0.375 6645: East Houston to El Paso 1998 5LX-42 0.2335 18 0.5 6645: East Houston to El Paso 1998 5LX-65 0.0030 18 0.281
6645: East Houston to El Paso 1998
5LX-
52,5LX-
65 0.0448 18 0.281,0.375 6645: East Houston to El Paso 1998 5LX-65 0.0009 18 0.375 6645: East Houston to El Paso 1998 5LX-65 0.2788 18 0.281,0.375 Coating PLASTIC TAPE COAL TAR PLASTIC TAPE PLASTIC TAPE PLASTIC TAPE COAL TAR ENAMEL EXTRUDED
POLYETHYLENE COAL TAR COAL TAR EPOXY/PLASTIC TAPE FUSION BOND EPOXY PLASTIC TAPE UNKNOWN FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY NON-SHIELDING TAPE
(RD-6) PAINT PLASTIC TAPE PLASTIC TAPE Seam Type ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF Manufacturer
UNKNOWN
AMERICAN STEEL
AMERICAN STEEL
U.S. STEEL
UNKNOWN
UNKNOWN
UNKNOWN
AMERICAN STEEL
UNKNOWN
UNKNOWN
UNKNOWN
UNKNOWN
UNKNOWN
SUMITOMO STEEL
U.S. STEEL
UNKNOWN
U.S. STEEL
U.S. STEEL
STUPP STEEL
U.S. STEEL

<<<PAGE 696>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6645: East Houston to El Paso 1998 5LX-65 0.0235 18 0.281 6645: East Houston to El Paso 1998 5LX-52 0.0060 18 0.375 6645: East Houston to El Paso 1998 5LX-52 0.0023 18 0.375 6645: East Houston to El Paso 1998 GR. B 0.0072 18 0.281 6645: East Houston to El Paso 1998 5LX-52 3.5689 20
0.312,0.344,0
.375 6645: East Houston to El Paso 1998 5LX-52 0.0004 20 0.375 6645: East Houston to El Paso 1998 5LX-52 0.0029 20 0.375 6645: East Houston to El Paso 1998 GR. B 0.0055 20 0.375 6645: East Houston to El Paso 1999 5LX-52 0.0242 18 0.375 6645: East Houston to El Paso 1999 5LX-52 0.0434 18 0.375 6645: East Houston to El Paso 1999 5LX-65 0.0152 18 0.281 6645: East Houston to El Paso 1999 5LX-65 0.0009 20 0.312 6645: East Houston to El Paso 2000 5LX-65 0.2894 18
0.375,0.385,0
.406 6645: East Houston to El Paso 2000
5LX-
52,5LX-
60,5LX-
65 1.0461 18
0.281,0.312,0
.375,0.385 6645: East Houston to El Paso 2000 5LX-52 0.0205 18 0.375 6645: East Houston to El Paso 2000
5LX-
52,5LX-
65 0.0080 18 0.375 6645: East Houston to El Paso 2000
5LX-
52,5LX-
65 2.0051 18
0.281,0.312,0
.375 6645: East Houston to El Paso 2000 5LX-52 0.0040 18 0.375 6645: East Houston to El Paso 2000 5LX-52 0.0049 18 0.375 6645: East Houston to El Paso 2000 5LX-65 0.0011 18 0.385 Coating PLASTIC TAPE PLASTIC TAPE/PAINT PLASTIC TAPE/PAINT PLASTIC TAPE/PAINT FUSION BOND EPOXY PAINT PAINT PLASTIC TAPE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT PLASTIC TAPE Seam Type ERW-HF ERW-HF ERW-HF SMLS ERW-HF ERW-HF ERW-HF SMLS ERW-HF ERW-HF ERW-HF ERW-HF DSAW
ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF DSAW
Manufacturer
UNITED
U.S. STEEL
UNKNOWN
UNKNOWN
U.S. STEEL
NIPPON STEEL
U.S. STEEL
U.S. STEEL
KAWASAKI STEEL
NIPPON STEEL
U.S. STEEL
U.S. STEEL
NAPA (FORMERLY
KAISER)
AMERICAN STEEL
KAWASAKI STEEL
NIPPON STEEL
U.S. STEEL
NIPPON STEEL
U.S. STEEL
NAPA (FORMERLY
KAISER)

<<<PAGE 697>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6645: East Houston to El Paso 2000 5LX-65 0.0152 18 0.281 6645: East Houston to El Paso 2000
5LX-
56,5LX-
60 0.0513 20 0.375 6645: East Houston to El Paso 2000 5LX-52 0.0053 20 0.375 6645: East Houston to El Paso 2001 5LX-65 0.3607 18 0.375,0.385 6645: East Houston to El Paso 2001 5LX-65 0.0034 18 0.375 6645: East Houston to El Paso 2001 5LX-65 0.5694 18 0.281,0.375 6645: East Houston to El Paso 2001 5LX-65 0.0009 18 0.375 6645: East Houston to El Paso 2002 5LX-65 0.4114 18 0.375 6645: East Houston to El Paso 2002 5LX-65 0.6998 18 0.38,0.385 6645: East Houston to El Paso 2002 5LX-65 0.4608 18 0.281 6645: East Houston to El Paso 2002
5LX-
52,5LX-
65 0.0812 18 0.375 6645: East Houston to El Paso 2002
5LX-
52,5LX-
60,5LX-
65 0.0563 18 0.375 6645: East Houston to El Paso 2002 5LX-65 0.9080 18 0.375,0.385 6645: East Houston to El Paso 2002
5LX-
65,5LX-
70 20.7193 18
0.281,0.375,0
.385 6645: East Houston to El Paso 2002 5LX-65 0.0011 18 0.375
6645: East Houston to El Paso 2002 5LX-52 0.0071 18 0.375 6645: East Houston to El Paso 2002 5LX-52 0.0018 18 0.375 6645: East Houston to El Paso 2002 5LX-52 0.0021 18 0.375 Coating UNKNOWN FUSION BOND EPOXY PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT COAL TAR/EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY NON-SHIELDING TAPE
(RD-6) PAINT PAINT UNKNOWN Seam Type ERW-HF ERW-HF ERW-HF DSAW
ERW-HF ERW-HF ERW-HF ERW-HF DSAW
ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF Manufacturer
U.S. STEEL
NIPPON STEEL
NIPPON STEEL
NAPA (FORMERLY
KAISER)
KAWASAKI STEEL
U.S. STEEL
U.S. STEEL
U.S. STEEL
NAPA (FORMERLY
KAISER)
AMERICAN STEEL
KAWASAKI STEEL
NIPPON STEEL
STUPP STEEL
U.S. STEEL
U.S. STEEL
KAWASAKI STEEL
NIPPON STEEL
UNKNOWN

<<<PAGE 698>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6645: East Houston to El Paso 2002
5LX-
56,5LX-
60,5LX-
65 0.3498 20 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0018 18 0.375 6645: East Houston to El Paso 2004 5LX-65 0.0090 18 0.375 6645: East Houston to El Paso 2004 5LX-65 0.0042 18 0.385 6645: East Houston to El Paso 2004 5LX-65 0.0472 18 0.281,0.375 6645: East Houston to El Paso 2004 5LX-65 0.0095 18 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0009 18 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0712 18 0.375 6645: East Houston to El Paso 2004 5LX-65 0.0119 18 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0010 18 0.375 6645: East Houston to El Paso 2004
5LX-
52,GR. B 0.0126 18 0.375 6645: East Houston to El Paso 2004
5LX-
65,GR. B 0.0036 18 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0011 18 0.375 6645: East Houston to El Paso 2004 5LX-65 0.0002 18 0.281 6645: East Houston to El Paso 2004 5LX-52 0.0112 18 0.375 6645: East Houston to El Paso 2004
5LX-
52,5LX-
60 0.2566 20 0.375 6645: East Houston to El Paso 2004 5LX-60 0.0134 20 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0186 20 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0038 20 0.375 6645: East Houston to El Paso 2004 5LX-60 0.0008 20 0.375 6645: East Houston to El Paso 2004 5LX-60 0.0015 20 0.375 6645: East Houston to El Paso 2004 5LX-52 0.0045 20 0.375 Coating FUSION BOND EPOXY COAL TAR COAL TAR FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT PAINT PLASTIC TAPE PLASTIC TAPE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT PLASTIC TAPE PLASTIC TAPE/PAINT Seam Type ERW-HF ERW-HF ERW-HF DSAW
ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF SMLS ERW-HF ERW-HF SMLS ERW-HF SMLS ERW-HF ERW-HF SMLS ERW-HF ERW-HF ERW-HF ERW-HF Manufacturer
NIPPON STEEL
KAWASAKI STEEL
U.S. STEEL
NAPA (FORMERLY
KAISER)
AMERICAN STEEL
KAWASAKI STEEL
NIPPON STEEL
SUMITOMO STEEL
U.S. STEEL
TULSA TUBE
NIPPON STEEL
U.S. STEEL
TULSA TUBE
U.S. STEEL
U.S. STEEL
AMERICAN STEEL
NIPPON STEEL
AMERICAN STEEL
AMERICAN STEEL
NIPPON STEEL
NIPPON STEEL
AMERICAN STEEL

<<<PAGE 699>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6645: East Houston to El Paso 2005 5LX-65 0.1871 18 0.375 6645: East Houston to El Paso 2006
5LX-
52,5LX-
65 0.0084 18 0.375 6645: East Houston to El Paso 2006 5LX-65 0.0010 18 0.375 6645: East Houston to El Paso 2006 5LX-52 0.0032 18 0.375 6645: East Houston to El Paso 2006
5LX-
52,5LX-
65 0.0277 18 0.375 6645: East Houston to El Paso 2006 5LX-65 0.0060 18 0.375 6645: East Houston to El Paso 2006 5LX-65 0.0036 18 0.375 6645: East Houston to El Paso 2006 5LX-65 0.0034 18 0.375 6645: East Houston to El Paso 2006 5LX-52 0.0030 18 0.375 6645: East Houston to El Paso 2007 5LX-65 0.7610 18 0.281 6645: East Houston to El Paso 2007 5LX-52 0.0085 18 0.375 6645: East Houston to El Paso 2008 5LX-52 0.9197 18 0.375,0.5 6645: East Houston to El Paso 2008 5LX-65 40.2555 18 0.281,0.375 6645: East Houston to El Paso 2008 5LX-52 0.0129 18 0.375 6645: East Houston to El Paso 2008 5LX-65 0.0206 18 0.375 6645: East Houston to El Paso 2008 5LX-65 0.0075 18 0.375,0.5 6645: East Houston to El Paso 2008 5LX-65 0.0017 18 0.281 6645: East Houston to El Paso 2010 5LX-52 0.0068 18 0.375 6645: East Houston to El Paso 2010 5LX-65 0.0017 18 0.385 6645: East Houston to El Paso 2010
5LX-
52,5LX-
65 0.4127 18 0.281,0.375 6645: East Houston to El Paso 2010 5LX-65 0.0402 18 0.375 6645: East Houston to El Paso 2010 5LX-52 0.0021 18 0.375 6645: East Houston to El Paso 2010 5LX- 0.4080 18 0.375 Coating FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT PAINT PAINT PLASTIC TAPE PLASTIC TAPE PLASTIC TAPE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT PAINT PLASTIC TAPE FBE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY Seam Type ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF SMLS ERW-HF SMLS SMLS ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF DSAW
ERW-HF ERW-HF ERW-HF ERW-HF Manufacturer
AMERICAN STEEL
U.S. STEEL
AMERICAN STEEL
CORUS
U.S. STEEL
AMERICAN STEEL
AMERICAN STEEL
AMERICAN STEEL
CORUS
AMERICAN STEEL
KAWASHO
HUSTEEL
PROCARSA
AMERICAN STEEL
PROCARSA
U.S. STEEL
U.S. STEEL
KAWASAKI STEEL
NAPA (FORMERLY
KAISER)
AMERICAN STEEL
APA PIPE CORP.
KAWASAKI STEEL
MANNESMANN

<<<PAGE 700>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 52,5LX-
65
6645: East Houston to El Paso 2010 5LX-65 0.0011 18 0.281 6645: East Houston to El Paso 2010 5LX-52 0.0018 20 0.375 6645: East Houston to El Paso 2010 5LX-52 0.4755 20 0.375 6645: East Houston to El Paso 2010 5LX-52 3.0492 20 0.375 6645: East Houston to El Paso 2010 5LX-52 0.0016 20 0.375 6645: East Houston to El Paso 2010 5LX-52 0.0268 20 0.375 6645: East Houston to El Paso 2010 5LX-52 0.0007 20 0.375 6645: East Houston to El Paso 2011 5LX-65 4.1669 18 0.281,0.375 6648: Crane to Odessa 1998 GR. B 0.0037 8.625 0.322 6648: Crane to Odessa 1998 5LX-46 0.0227 8.625 0.25 6648: Crane to Odessa 1998
5LX-
42,5LX-
60 28.0741 8.625 0.188,0.25 6648: Crane to Odessa 1998 5LX-46 0.0027 8.625 0.25 6648: Crane to Odessa 1998 5LX-42 0.0011 8.625 0.25 6648: Crane to Odessa 2004
5LX-
52,5LX-
60 0.0781 8.625 0.25,0.322 6648: Crane to Odessa 2004
5LX-
52,5LX-
60,GR. B 0.8110 8.625
0.188,0.277,0
.322 6648: Crane to Odessa 2004 GR. B 0.0109 8.625 0.322 6648: Crane to Odessa 2004 5LX-52 0.0014 8.625 0.322 6648: Crane to Odessa 2004 5LX-60 0.0009 8.625 0.277 6648: Crane to Odessa 2004 GR. B 0.0006 8.625 0.322 6648: Crane to Odessa 2004 5LX-60 0.0020 8.625 0.188 Coating PAINT FBE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY FUSION BOND EPOXY PAINT FUSION BOND EPOXY FBE/PAINT FUSION BOND EPOXY FUSION BOND EPOXY PAINT PAINT EPOXY/PE EPOXY/PE EPOXY/PE EPOXY/PLASTIC TAPE EPOXY/PLASTIC TAPE FBE/PAINT FUSION BOND EPOXY Seam Type ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF ERW-HF SMLS ERW-HF ERW-HF
ERW-HF ERW-HF
ERW-HF
ERW-HF SMLS ERW-HF
ERW-HF SMLS ERW-HF Manufacturer
AMERICAN STEEL
STUPP STEEL
AMERICAN STEEL
HUSTEEL
STUPP STEEL
U.S. STEEL
HUSTEEL
AMERICAN STEEL
AMERICAN STEEL
AMERICAN STEEL
CALIFORNIA STEEL
INDUSTRIES
AMERICAN STEEL
CALIFORNIA STEEL
INDUSTRIES
CALIFORNIA STEEL
INDUSTRIES
U.S. STEEL
U.S. STEEL
CALIFORNIA STEEL
INDUSTRIES
U.S. STEEL
U.S. STEEL
U.S. STEEL

<<<PAGE 701>>>

Table 5.2.1-1c Pipe Characteristics Detail by Coating Type (continued)
Segment Name
Year
Built Grades
Segment
Length
(mi)
Diameter
(in)
Wall
Thickness
(in) 6648: Crane to Odessa 2004
5LX-
52,5LX-
60 0.1660 8.625 0.25,0.322 6648: Crane to Odessa 2004 5LX-42 0.0659 8.625 0.322 6648: Crane to Odessa 2004
5LX-
60,GR. B 0.0101 8.625 0.277 6648: Crane to Odessa 2004 GR. B 0.0143 8.625 0.322 PAINT PAINT PAINT PAINT Coating Seam Type ERW-HF
ERW-HF ERW-HF SMLS Manufacturer
CALIFORNIA STEEL
INDUSTRIES
TEX-TUBE STEEL
U.S. STEEL
U.S. STEEL

<<<PAGE 702>>>

Table 5.2.1-2 Overview of Pipeline Construction Specifications
Discussions with Magellan reveal that their construction specifications are the same as the
Williams CS4 specifications shown in the table below.
Section
1949, Humble Oil
Kemper (Crane) –
Satsuma
1998, Williams CS4
Galena Park Station -
Satsuma, Station (9.1 miles)
Refurbishing Satsuma
Station-Kemper Station,
Odessa Lateral, Crane
Station - El Paso Terminal
49 CFR Part 195* see
note below
Minimum Depth of Cover (inches)
Normal Excavation
Industrial, Commercial,
Residential
24 36 36
Water body > 100 ft
(high water marks)
24 48 48
Drainage Ditches 24 36 36
Other 24 30 30
Rock Excavation
Industrial, Commercial,
Residential
12 30 30
Water body > 100 ft
(high water marks)
4 (concrete) 18 18
Drainage Ditches 12 36 36
Other 12 18 18
Crossings
Hard-surfaced road
(cased)
Vented casing, Kapco rock
shield in addition to
coating, seal bushings
Vented casing, 1.25 inch
reinforced concrete jacket, seal
bushings; 4 ft clearance to
road foundation, 3 ft to bottom
of drainage ditch.
Installation must
withstand traffic loads.
Railroad Same as hard-surfaced
road
Cased: 5 ft 6 inch clearance to
top of RR ties, 3 ft to bottom of
drainage ditch; Uncased: 10 ft
to top of ties, 6 ft to bottom of
drainage ditch.
Installation must
withstand traffic loads.
River Weighted so it will not float
when empty (2-inch
concrete sheaths), split
offset weld sleeves over
welds, Kapco Rock shield
over ends.
With riprap: rock plugs (typ. 50
ft to each side, 3 ft clearance
from top of pipe to base of rock
plug, 8 ft to river bottom; w/o
riprap min 4 ft to river bottom;
concrete weights as required.
Cover specified as 48
inches for normal
excavation and 18
inches for rock
excavation.
Irrigation canal Open cut, 5 ft of cover Covered under
general depth of cover
or drainage ditches.

<<<PAGE 703>>>

Table 5.2.1-2 Overview of Pipeline Construction Specifications (continued)
Section
1949, Humble Oil
Kemper (Crane) –
Satsuma
1998, Williams CS4
Galena Park Station -
Satsuma, Station (9.1 miles)
Refurbishing Satsuma
Station-Kemper Station,
Odessa Lateral, Crane
Station - El Paso Terminal
49 CFR Part 195* see
note below
Bar ditch 30-inch clearance, including 6-
inch concrete slab
Covered under
general depth of cover
or drainage ditches.
Other Pipe 12-inch clearance, pass
below
24 inch normal, 12 inch in rock Clearance of 12
inches from other
underground
structures.
Coating and Wrapping
Regular Weld, clean, prime (coal
tar base), dry, coal tar
enamel & asbestos PL felt
machine-applied to 94
mils, cool.
GATX-Crane: Fusion bond
epoxy; Crane-El Paso: weld,
clean, hot enamel (94 mil min.
yard applied, 18 mil glass mat
wrapped and embedded,
poured molten enamel, coal tar
PL felt wrapped.
Specified in general
terms
River Crossings Weld, clean, prime (coal
tar base), dry, double coat
coal tar enamel, glass mat
wrapper, coat coal tar
enamel, asbestos PL felt
and Kraft paper, yard-
applied in Houston.
Same as regular Specified in general
terms
Welds AWS Class E-6010
electrodes or similar
American Petroleum Institute
Standard 1104 (17th Ed. Sep
88), Sect. IX of ASME Boiler
and Pressure Vessel Code
American Petroleum
Institute Standard
1104 and Section IX
of ASME Boiler and
Pressure Vessel Code
Hydrostatic Testing 1000 psi, 4 hours 1525-1575 psi, 8 hours §195.303
CP Not mentioned Specified in detail §195.414
Per 49 CFR Part 195.210 – No pipeline may be located within 50 feet of any private dwelling, or
any industrial building or place of public assembly in which persons work, congregate, or
assemble, unless it is provided with at least 12 inches of cover in addition to that described
above.

<<<PAGE 704>>>

Table 5.2.6-1 Valve Locations and Types for the Longhorn Pipeline
Longhorn Milepost Valve Type Valve Location
0.00 Motor Operated Block Valve MOV 8 - BOL-Galena Park Station
0.00 Remotely Operated Block Valve GS1 - Galena Park Station
1.86 Motor Operated Block Valve MOV 107 Holland Ave.- Incoming Line “B”
1.77 Motor Operated Block Valve MOV 106 Holland Ave.- Outgoing Line “A”
5.34 Manual Block Valve GS2 (Wallisville Rd.)
9.47 Motor Operated Block Valve MOV 231 - East Houston Term.
9.47 Motor Operated Block Valve MOV 233 - East Houston Term. - Incoming
2.36 Motor Operated Block Valve MOV 237 - East Houston Term. - Outgoing
2.36 Motor Operated Block Valve MOV 235 - East Houston Term.
7.46 Manual Block Valve GS3 (S. SIDE CADDO ST.)
11.98 Remotely Operated Block Valve GS5 (MESA RD./FM 527)
21.20 Remotely Operated Block Valve GS-6 (SWEETWATER LANE)
34.09 Remotely Operated Block Valve GS7
34.09 Motor Operated Block Valve Satsuma Station - Incoming
34.14 Motor Operated Block Valve Satsuma Station - Outgoing
34.14 Remotely Operated Block Valve SE1
63.78 Motor Operated Block Valve SE2 (E. SIDE BRAZOS RIVER)
64.08 CHECK SE3 (W. SIDE BRAZOS RIVER)
64.08 Manual Block Valve SE3 (W. SIDE BRAZOS RIVER)
112.89 Motor Operated Block Valve SE4
112.90 Manual Block Valve G2 Warda Station - INCOMING
112.90 Manual Block Valve G7 Warda Station - OUTGOING
112.96 Manual Block Valve SE5
133.87 Motor Operated Block Valve SE6 (E. SIDE COLORADO RIVER)
134.67 CHECK SE7 (W. SIDE COLORADO RIVER)
134.67 Manual Block Valve SE7 (W. SIDE COLORADO RIVER)
139.34 BURIED CHECK CV8 (SH 304)
149.19 BURIED CHECK CV9 (FM 535)
166.67 Remotely Operated Block Valve SE8 (US HWY. 81)
171.53 BURIED CHECK SENDERA MESA DRIVE (AUSTIN AQUIFER)
172.29 BURIED CHECK BECKETT RD. (AUSTIN AQUIFER)
174.94 BURIED CHECK SILVER MTN. RD. (AUSTIN AQUIFER)
175.51 Remotely Operated Block Valve SE9 RAMBLE 3 ST. (AUSTIN AQUIFER)

<<<PAGE 705>>>

Table 5.2.6-1 Valve Locations and Types for the Longhorn Pipeline
Longhorn Milepost Valve Type Valve Location
175.51 BURIED CHECK RAMBLE 3 ST. (AUSTIN AQUIFER)
177.13 BURIED CHECK US HWY. 290 (AUSTIN AQUIFER)
181.60 Motor Operated Block Valve Cedar Valley - INCOMING
181.65 Motor Operated Block Valve Cedar Valley - OUTGOING
181.65 Motor Operated Block Valve SE10
185.88 BURIED CHECK FITZHUGH CREEK (AUSTIN AQUIFER)
186.48 BURIED CHECK OAK FOREST DRIVE (AUSTIN AQUIFER)
192.45 Manual Block Valve SE10A (E. SIDE FLAT CREEK)
193.39 CHECK CV3 (W. SIDE FLAT CREEK)
194.38 BURIED CHECK
194.76 BURIED CHECK CV10 ULRICH RD.
198.64 Remotely Operated Block Valve SE11 (E. SIDE PEDERNALES RIVER)
198.97 CHECK SE12 (W. SIDE PEDERNALES RIVER)
198.97 Motor Operated Block Valve SE12 (W. SIDE PEDERNALES RIVER)
199.58 BURIED CHECK CV4 (W. SIDE PEDERNALES RIVER)
203.46 BURIED CHECK CV5 (CYPRESS MILL RD.)
205.50 BURIED CHECK CV11 (US HWY. 281)
211.90 Manual Block Valve
SE13 (BETWEEN HICKORY/WHITE OAK
CKS.)
211.98 BURIED CHECK
CV6 (BETWEEN HICKORY/WHITE OAK
CKS.)
214.21 BURIED CHECK CV7 (W. SIDE WHITE OAK CREEK)
227.90 Manual Block Valve SE14
227.93 Remotely Operated Block Valve G2 Eckert - Incoming
227.94 Remotely Operated Block Valve G7 Eckert - Outgoing
228.02 Manual Block Valve SE15
276.46 Remotely Operated Block Valve SE16 (E. SIDE LLANO RIVER, STA. NO. 181)
276.64 CHECK
SE17 (W. SIDE LLANO RIVER, STA. NO.
181)
276.64 Manual Block Valve
SE17 (W. SIDE LLANO RIVER, STA. NO.
181)
280.95 BURIED CHECK CV12 (US HWY. 377)
284.37 BURIED CHECK CV13
288.91 Manual Block Valve SE18 (CR 370)
295.19 Remotely Operated Block Valve SE 19 KIMBLE STATION
295.19 CHECK CV1
295.21 Manual Block Valve SE20
321.95 Manual Block Valve SE21

<<<PAGE 706>>>

Table 5.2.6-1 Valve Locations and Types for the Longhorn Pipeline
Longhorn Milepost Valve Type Valve Location
324.68 BURIED CHECK CV14 (CR 245)
338.75 BURIED CHECK CV15 (W. SIDE ANTELOPE DRAW)
346.58 BURIED CHECK CV16 (FM 190)
358.70 Manual Block Valve SE22
373.44 Motor Operated Block Valve
SE23 INCOMING (FORMERLY BIG LAKE,
STA. NO. 179)
373.45 Manual Block Valve
SE24 OUTGOING (FORMERLY BIG LAKE,
STA. NO. 179)
416.63 Manual Block Valve SE25 (SH 1555)
457.54 Remotely Operated Block Valve SE26 Crane Station
457.54 Motor Operated Block Valve Crane Station - INCOMING
457.55 Motor Operated Block Valve Crane Station - OUTGOING
457.55 Remotely Operated Block Valve SE27
492.26 Manual Block Valve SE26A (FM 1219)
523.63 Manual Block Valve SE27A (CR 170)
526.17 Manual Block Valve SE28 (FM1216)
526.17 BURIED CHECK SE28 (FM 1216)
528.06 LEVER LOCK CHECK (W. SIDE US HWY 285)
555.10 Manual Block Valve SE29 (CR 222)
576.32 FIRE GATE SE30 COTTONWOOD STA.
576.33 Manual Block Valve G3 COTTONWOOD STA. INCOMING
576.33 Manual Block Valve G9 COTTONWOOD STA. OUTGOING
576.33 Remotely Operated Block Valve SE31 COTTONWOOD STA.
607.10 Manual Block Valve SE32 (SH 54)
638.86 Manual Block Valve SE33 (FM 1111)
668.37 Manual Block Valve SE34
694.41 Motor Operated Block Valve SE35 - EL PASO TERMINAL
694.41 Remotely Operated Block Valve EOL - EL PASO TERMINAL

<<<PAGE 707>>>

Table 5.2.6-2 Locations of Check Valves Installed per LCRA Settlement and Valve Studies
River Basin
Approximate
Current Station
Location (Check
Valve)
Approximate
Proposed Station
Location (RCV)
Location Description Notes
7110+58 7154+40 Near Colorado River Relocated -
Colorado River between
Austin and Bastrop
(maximum drain down
volume of 300,000 gallons)
7357+15 7386+72 Near Bastrop, TX Relocated – LCRA
7877+23 7818+62 Close to Jenkins Road Relocated – LCRA
9056+27 9056+27
Sandera Mesa Drive
(Edwards Aquifer) No change in location - APR
Edwards Aquifer
9266+77 9266+77
Ramble 3 St.
(Edwards Aquifer) No change in location - APR
10210+24 10218+91 Near Flat Creek Relocated - APR
10263+24 10263+24 Ulrich Rd and Co Rd 301 No change in location – LCRA
10503+95 10503+95 Near the Pedernales River No change in location -
Pedernales River (maximum
drain down volume of
200,000 gallons)
10538+00 10538+00 West Side of Pedernales R. No change in location - APR
10742+50 10742+50 Near Cottonwood Creek No change in location – APR
10850+40 10810+80 Near Hwy 281 Relocated – LCRA
11192+24 11192+24 Near FM 1323 and Sandy
School Rd No change in location - APR
11310+24 11267+52 Near White Oak Relocated – APR

<<<PAGE 708>>>

Table 5.2.6-2 Locations of Check Valves Installed per LCRA Settlement and Valve Studies (continued)
River Basin
Approximate
Current Station
Location (Check
Valve)
Approximate
Proposed Station
Location (RCV)
Location Description Notes
Relocated –
14606+59 14616+10 Near the Llano River
Llano River (maximum drain
down volume of 250,000
gallons)
14834+24 14834+24 Hwy 377 near London, TX No change in location – LCRA
15014+74 14920+70 London, TX Relocated – LCRA
17143+24 17143+24 Co. RD 245 No change in location – LCRA
San Saba River (maximum
drain down volume of
350,000 gallons)
17886+00 18038+18 Eldorado, TX Relocated - LCRA
18299+24 18303+12 Hwy 190 W. of Eldorado, TX Relocated - LCRA

<<<PAGE 709>>>

Table 5.2.6-3 Estimated Maximum Release Volumes
Maximum Drain
Volume
Loss during
detection and
Pipeline Shutdown
Total Maximum
Release
Location Station, Ft bbl gal bbl gal bbl gal
Brazos River 3378+79 502 21,091 781 32,800 1,283 53,891
Colorado River Basin
7000+04 to
7999+04 4,549 191,061 781 32,800 5,330 223,861
Colorado River Crossing 7100+33 1,241 52,108 781 32,800 2,022 84,908
Edwards Aquifer - General
8756+15 to
9146+82 2,645 111,089 781 32,800 3,426 143,889
Pedernales River Basin
10100+04 to
11410+04 3,249 136,472 781 32,800 4,030 169,272
Pedernales River Crossing 1049480 2,570 107,937 781 32,800 3,351 140,737
Llano River Basin
14506+04 to
15554+04 3,486 146,398 781 32,800 4,267 179,198
Llano River Crossing 14601+52 561 23,573 781 32,800 1,342 56,373
San Saba River Basin
17043+04 to
18299+04 5,878 246,891 781 32,800 6,659 279,691
San Saba River Crossing 17140+00 1,950 81,883 781 32,800 2,731 114,683
Note: As an additional measure of conservatism, an additional (2000 – 781) 1219 bbls was
added to these volumes for purposes of calculating and determining the zone of potential impact
for this FEA.

<<<PAGE 710>>>

Galena Park to Satsuma
MP 0 to MP 34.1
Satsuma to Warda
MP 34.1 to
MP 112.9
Warda to
Cedar Valley
MP 112.9 to
MP 181.6
Cedar Valley to
Eckert
MP 181.6 to
MP 227.9
Eckert to
Ft McKavett
MP 227.9 to
MP 321.9
Pipeline Table 5.3.1-1 ILI Tool Runs
Threats Addressed
Tool
Date of Tool
Run
Corrosion
Pressure-
Cycle
Induced
Fatigue
Laminations
and
Hydrogen
Blisters
Third Party
Damage
Deformation 10-Jun-04 X
HRMFL * 28-Oct-04 X X
HRMFL ** 14-Dec-05 X X
TFI 6-Jul-07 ‡ X X
Deformation 5-Oct-07 X
Deformation 11-Sep-09 X
UT 22-Sep-09 X X X
Next Required Assessment 22-Sep-14 2200 11-Sep-12 11-Sep-12
HRMFL/Deformation 21-May-06 X X
Deformation 15-Dec-07 X
TFI 20-Dec-07 ‡ X X
Deformation 12-Oct-09 X
UT 24-Nov-09 X X X
Next Required Assessment 24-Nov-14 2057 12-Oct-12 12-Oct-12
HRMFL/Deformation 21-Jul-06 X X
TFI 19-Sep-07 ‡ X X
Deformation 16-Oct-07 X
Deformation 16-Dec-09 X
UT 24-Jan-10 X X X
Next Required Assessment 24-Jan-15 2162 16-Dec-12 16-Dec-12
HRMFL/Deformation 15-Feb-07 X X
TFI 22-Mar-07 ‡ X
Deformation 25-Jan-10 X
UT 20-Feb-10 X X X
Next Required Assessment 20-Feb-15 2066 25-Jan-13 25-Jan-13
HRMFL/Deformation 19-Dec-06 X X
TFI 9-Nov-07 ‡ X X
Deformation 23-Jan-08 X
Deformation 27-Mar-10 X
UT 25-Jun-10 X X X
Next Required Assessment 25-Jun-15 2048 27-Mar-13 27-Mar-13
Tool Date of Tool Threats Addressed

<<<PAGE 711>>>

Table 5.3.1-1 ILI Tool Runs (continued)
Segment Run
Corrosion
Pressure-
Cycle
Induced
Fatigue
Laminations
and
Hydrogen
Blisters
Third
Party
Damage
HRMFL/Deformation 12-Oct-06 X X
Ft.McKavett to
Deformation 21-Dec-07 X
Crane
MP 321.9 to
MP 457.5
TFI 8-Jan-08 ‡ X X
UT 8-Jul-10 X X X
Deformation 5-Aug-10 X
Next Required Assessment 8-Jul-15 2049 8-Jul-13 8-Jul-13
Crane to
Cottonwood
Deformation 2-May-07 X
MP 457.5 to
MP 576.3
HRMFL/Deformation 21-Nov-08 X X
Next Required Assessment 21-Nov-13 Not
susceptible 21-Nov-13 21-Nov-
13
Deformation 2-May-07 X
Cottonwood
to El Paso
MP 576.3 to
MP 694.4
HRMFL/Deformation 27-Mar-08 X X
Next Required Assessment 27-Mar-13 Not
susceptible 27-Mar-13 27-Mar-
13
Crane to
HRMFL/Deformation 8-Jun-11 X X
Odessa
Next Required Assessment 8-Jun-16 Not
susceptible 8-Jun-16 8-Jun-16
* The MFL tool run in Oct-04 was not a complete run
** The MFL tool run in Dec-05 was used to complete the Oct-04 MFL run
‡ The TFI was used to remediate Phase I and Phase II corrosion anomalies and in some cases was used to
remediate POE anomalies, but was not used to set the next corrosion reassessment using the POE process.

<<<PAGE 712>>>

Pipeline
Segment 20" Galena Park to
Satsuma
(MP 0 to MP 34.09)
18" Satsuma to
Warda
(MP 34.09 to
112.89)
18" Warda to
Cedar Valley
(MP 112.89 to MP
181.6)
Table 5.3.1-2 ILI Features Summary
Item EGP & MFL EGP & TFI
EGP &
UTWM
ILI Year 2004 & 2005 2007 2009
ILI Dents
23 (including
<2%) 2 3
ILI Metal Loss 5,9001 8,8091 3371
ILI Seam Weld Features N/A 17 N/A
ILI Girth Weld Anomalies 89 0 0
ILI Laminations N/A N/A 1,695
No. Dents Repaired 3 1 1
No. Metal Loss Repaired 47 14 3
No. Seam Weld Features Repaired N/A 17 N/A
No. Girth Weld Anomalies Repaired 9 0 0
No. Laminations Repaired N/A N/A 6
ILI Year 2006 2007 2009
ILI Dents 10 5 4
ILI Metal Loss 2,1391 93,9871 7331
ILI Seam Weld Features N/A 4 N/A
ILI Girth Weld Anomalies 18 0 0
ILI Laminations N/A N/A 1,082
No. Dents Repaired 3 0 6
No. Metal Loss Repaired 15 21 14
No. Seam Weld Features Repaired N/A 4 N/A
No. Girth Weld Anomalies Repaired 5 0 0
No. Laminations Repaired N/A N/A 12
ILI Year 2006 2007 2009 & 2010
ILI Dents 24 7 10
ILI Metal Loss 3,8271 141,9601 1,5781
ILI Seam Weld Features N/A 6 N/A
ILI Girth Weld Anomalies 1 0 2
ILI Laminations N/A N/A 541
No. Dents Repaired 3 0 3
No. Metal Loss Repaired 67 42 22
No. Seam Weld Features Repaired N/A 6 N/A
No. Girth Weld Anomalies Repaired 1 0 0
No. Laminations Repaired N/A N/A 6

<<<PAGE 713>>>

Table 5.3.1-2 ILI Features Summary (continued)
Pipeline
Segment Item EGP & MFL EGP & TFI
EGP &
UTWM
ILI Year 2007 2007 2010
ILI Dents 49 46 16
ILI Metal Loss 13,0111 82,0101 1,0061
ILI Seam Weld Features N/A 3 N/A
18" Cedar Valley to
Eckert
(MP 181.6 to MP
227.9)
ILI Girth Weld Anomalies 2 0 3
ILI Laminations N/A N/A 594
No. Dents Repaired 8 1 7
No. Metal Loss Repaired 52 30 5
No. Seam Weld Features Repaired N/A 3 N/A
No. Girth Weld Anomalies Repaired 2 0 0
No. Laminations Repaired N/A N/A 0
ILI Year 2006 2007 & 2008 2010
ILI Dents 86 90 30
ILI Metal Loss 61,1671 82,9741 4861
ILI Seam Weld Features N/A 3 N/A
18" Eckert to Ft.
McKavett
(MP 227.9 to MP
321.9)
ILI Girth Weld Anomalies 56 0 0
ILI Laminations N/A N/A 1,907
No. Dents Repaired 18 9 5
No. Metal Loss Repaired 116 10 11
No. Seam Weld Features Repaired N/A 3 N/A
No. Girth Weld Anomalies Repaired 6 0 0
No. Laminations Repaired N/A N/A 14
ILI Year 2006 2007 & 2008 2010
ILI Dents 54 35 14
ILI Metal Loss 3,3701 75,5991 1,4271
ILI Seam Weld Features N/A 42 N/A
18" Ft. McKavett to
Crane
(MP 321.9 to MP
457.5)
ILI Girth Weld Anomalies 0 0 2
ILI Laminations N/A N/A 2,364
No. Dents Repaired 8 0 4
No. Metal Loss Repaired 50 14 24
No. Seam Weld Features Repaired N/A 42 N/A
No. Girth Weld Anomalies Repaired 0 0 1
No. Laminations Repaired N/A N/A 18
Note 1: Differences in numbers of metal loss features include: (1) Features under sleeves are not
reported in UT inspections, (2) Multiple features in MFL inspection are included in one feature in UT
inspection (fewer features per joint and longer lengths), and (3) Low level features in MFL inspections not
reported in UT inspection due reporting, detection thresholds.

<<<PAGE 714>>>

Table 5.3.1-3 Pressure-Cycle-Induced Fatigue Cracking Analysis from the 2010 ORA for the
Current Westward Product Flow Direction
Description
Station
Number, feet
MP,
miles
Diameter,
inches
Wall
Thickness,
inches
Pipe
Grade
Time to
Failure,
years1
Reassessment
Interval, years2
Case 1 1998 ERW pipe at Galena Park 0+00 0 20 0.312 X52 > 500 > 225
Case 2 Transition to 1950 ERW pipe at MP9
downstream of Galena Park 480+09 9.1 20 0.312 Grade B 428.6 193.1
Case 3 Transition to heavy wall 1950 EFW pipe 1067+46 20.2 20 0.375 Grade B > 500 > 225
Case 4 1950 EFW pipe at Satsuma 1802+61 34.1 18 0.281 X45 110.9 50.0
Case 5 Transition to heavy wall 1950 EFW pipe 1821+42 34.5 18 0.375 Grade B 344.0 155.0
Case 6 1950 EFW pipe downstream of
Cedar Valley 10037+72 190.1 18 0.312 X45 131.9 59.4
Case 7 1950 EFW pipe at Kimble County 15589+07 295.2 18 0.281 X45 92.1 41.5
Case 8 Transition to 1950 ERW pipe at Kemper
(former Exxon Station) 21387+88 405.1 18 0.25 X52 > 500 > 225
Case 9 1998 ERW pipe at Crane 24158+39 457.5 18 0.281 X65 > 500 > 225
1 Hypothetical, based on assumptions detailed in ORA
2 Based on 0.45 times the hypothetical time to failure

<<<PAGE 715>>>

Table 5.3.1-4 Test Point Exceptions for 2011
Segment Name Milepost Location Description Longhorn
Tier
Inspection
Date
Structure
P/S
Remarks
East Houston to
Kimble 221.972 Bottom of Canyon E of
Creek 1 10/06/2011 -0.592 -1.187 Test station
repaired.
East Houston to
Kimble 147.685 Jenkins Rd 247 ESD 2 05/03/2011 -0.68 East Houston to
Kimble 116.847 FM 448 ESD 1 10/26/2011 -0.784 Corrected
P/S MP 147.204 rectifier
repaired.
Warda and Zack
Lane rectifiers were
adjusted.
-1.411 -0.95
East Houston to
Kimble 25.8 TP E of MP 26 3 09/28/2011 -0.765 -1.285 Test station
repaired.
East Houston to
Kimble 18.674 ESD Hardy Toll Rd 2 04/28/2011 0 -1.658 Test station
repaired.
East Houston to
Kimble 15.727 Keith Rd 2 09/28/2011 -0.333 -1.359 Test station
repaired.
Ft. McKavett to
Kemper 344.895 -15' 3 05/06/2011 0.038 -1.03
Data reading error
[reading 3' away
was -1.162]
Kemper to Crane 441.715 +15' 1 06/02/2011 -0.821 -2.64
Kemper to Crane 441.714 +12' 1 06/02/2011 -0.812 -2.64
Kemper to Crane 441.713 +9' 1 06/02/2011 -0.833 -2.642
Kemper to Crane 441.712 +6' 1 06/02/2011 -0.812 -2.649
Kemper to Crane 441.71 FGN LINE XING IN
PASTURE 1 06/02/2011 -0.819 -2.647 Kemper to Crane 441.709 -3' 1 06/02/2011 -0.817 -2.645
New ground bed
was installed at
MP440.
Kemper to Crane 441.708 -6' 1 06/02/2011 -0.816 -2.654
Kemper to Crane 441.707 -9' 1 06/02/2011 -0.814 -2.651
Kemper to Crane 441.706 -12' 1 06/02/2011 -0.71 -2.655
Kemper to Crane 441.705 -15' 1 06/02/2011 -0.717 -2.662

<<<PAGE 716>>>

Table 5.3.1-4 Segment Name Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Kemper to Crane Test Point Exceptions for 2011 (continued)
Milepost Location Description Longhorn
Tier
Inspection
Date
441.235 +15' 1 06/02/2011 441.234 +12' 1 06/02/2011 441.233 +9' 1 06/02/2011 441.232 +6' 1 06/02/2011 441.231 +3' 1 06/02/2011 441.23 441.229 CANYON REEF PL XING -3' 1 06/02/2011 1 06/02/2011 441.228 -6' 1 06/02/2011 441.227 -9' 1 07/28/2011 441.226 -12' 1 06/02/2011 441.225 -15' 1 06/02/2011 Structure
P/S
-0.464 -0.442 -0.401 -0.378 -0.335 -0.296 -0.312 -0.368 -0.73 -0.437 -0.457 Corrected
P/S -2.308
-2.281
-2.272
-2.272
-2.266
-2.2 -2.314
-2.36
-2.413
-2.44
-2.448
Remarks
New ground bed
was installed.

<<<PAGE 717>>>

Table 5.3.4-1 Alarm and Shutdown Devices
Device description Device # Time
Delay Immediate Lockout
Non-
Lockout
Shutdown
Annunciate
Pump Case Hi-Temp. 95 X X X
Pump Seal Leak 96 X X X
Flow Switch 98 X X X
Motor Vibration 99M startup
only X X
Pump Vibration 99P startup
only X X
Low Suction Pressure 21 X X X
High discharge Pressure 25 X X X
Thrust Bearing Hi-Temp. 38E X X X
Motor Outboard Bearing Hi-Temp. 38A X X X
Motor Inboard Bearing Hi-Temp. 38B X X X
Pump Inboard Bearing Hi-Temp. 38C X X X
Pump Outboard Bearing Hi-Temp. 38D X X X
Motor Overload 49A X X X
Motor Windings Hi-Temp. 49B X X X
Low Pump Lube Oil Pressure 63LOPP startup
only X X
Low Motor Lube Oil Pressure 63LOPM startup
only X X
AC Power Failure 97PF X X X
Station Alarm 86ST X X X
Overcurrent 50-51 X X X
Switchgear Phase Failure 47-27 X X X
Hazardous Gas Detector 45HA X X X
Sump Hi-Level 17 X X
Low DC Power 80 X X X
Low Station Air 63A X X X
Fire Detector 45FA X X X
Miscellaneous Lockout (Normally High
Case Psi) MLI X X X

<<<PAGE 718>>>

Table 5.3.4-1 Alarm and Shutdown Devices (continued)
Device description Device # Time
Delay Immediate Lockout
Non-
Lockout
Shutdown
Annunciate
Fire Eye Self Check 45FSC X X
Loss of Genius Block (derived) X X X
Sequence Failure (derived) X X
Start Attempts Failure (derived) X X
Lockout - defined as an immediate shutdown that requires a physical reset only allowed on-site.
Non-Lockout Shutdown - defined as an immediate shutdown that does not require a reset. A restart can be made with no other action required.
Notes: "Local" shutdown devices initiate a pump shutdown and transmit an indicator Unit Lock-Out alarm to the Magellan Operations Control Center. The
alarm sent to the Control Center does not normally identify the cause of the shutdown (e.g., motor overload, low suction pressure, etc.), but it alerts the
Control Center to the pump shutdown. A technician must go to the pump and correct the problem causing the shutdown before it can be restarted.

<<<PAGE 719>>>

Table 5.3.4-1a Leak Detection System Alarm and Response Table
Description Condition
LEAK DETECTION PLDS EMERG-LO
Indicates A system indication of a line integrity anomaly, requiring investigation.
Note: The Longhorn Mitigation Plan requires a controlled shutdown and isolation of the Longhorn
pipeline within 5 minutes of the indication.
Response 1. Perform an Investigation Event Shutdown per the 9.02-ADM-002 Startup and
Shutdown.
2. Investigate line integrity via trends and event records.
3. Notify the Supervisor or Leak Detection Analyst (LDA).
a. If after shutdown, an abnormal or unexpected pressure drop occurs, then proceed to
Emergency Code Red Procedure in Emergency Code Red – Investigation Procedure
event.
b. If after shutdown and investigation, the Supervisor, LDA, and Controller agree it is a
false alarm, then the Supervisor may approve restarting the line.
Document in Logmate. Classify the cause as a “Data Failure”, or an “Irregular Operating
Condition”, or as a “Possible Commodity Loss”
Description Condition
PLDS LOW
Indicates A system indication of a line integrity anomaly, requiring investigation.
Response
1. Monitor all pressures and flow rates throughout the line for deviation and investigate line integrity via
trends and event records.
• If investigation indicates release, proceed to 9.02-ADM-011 Emergency – Code Red –
Investigation Event.
• If investigation does not indicate release, notify the Supervisor or Leak Detection Analyst (LDA).

<<<PAGE 720>>>

Table 5.3.5-1 Basic Inspection and Test Methods
Inspection or Test Type Purpose Attributes
Pressure Testing (Hydrotesting) Serves as a pre-service integrity validation of
the pipe and components by pressurizing to a
level above the maximum operating pressure.
Destructively eliminates injurious defects. The
time, duration, and elevation above MOP, are
primary factors in reducing the probabilities of
flaw growth that could result in an in-service
failure.
Confirms the SMYS of the steel.
A regulatory requirement for new pipe sections,
to uprate existing pipe sections, and conversion
from vapor to liquid service.
Done by sectioning line according to terrain
elevations. One or more valve sections can be
included within test segment.
Requirements and procedures defined in
regulations and industry standards.
The hydrotesting service is often provided by a
specialty contractor overseen by operating
company staff.
CP Inspections and Surveys Determines the adequacy of CP voltages and
currents for protecting the pipeline against
corrosion and to detect areas of potentially
defective coating.
Rectifier inspections are done to ensure that the
rectifiers are in service and providing the
required impressed current for CP.
Station tests or surveys are done to measure
CP voltages at test station locations. This also
includes readings taken at pipe casings under
roads and railway crossings.
Close-interval surveys are done to measure CP
voltages along the length of the pipeline
between CP test stations at intervals of a few
feet and provide a more complete
understanding of the CP voltages.
In-Line Inspection (ILI) Detects areas of anomalies, such as metal Automated internal inspection tools or “smart

<<<PAGE 721>>>

Table 5.3.5-1 Basic Inspection and Test Methods (continued)
Inspection or Test Type Purpose loss, deformations, cracks, etc. Manual Ultrasonic Wall Thickness
Measurement
Determines wall thickness and identifies areas
of possible corrosion by direct measurement of
pipe wall.
Visual Surveys Identifies any adverse conditions associated
with coating or pipe, such as corrosion, dents,
scrapes, gouges or deteriorating or damaged
coating.
Ground Patrols and Aerial Surveys Identifies external conditions that might
adversely affect the pipeline, such as third
party activity and right-of-way (ROW)
encroachments. Also used as a means of
detecting leaks.
Attributes
pigs” vary in anomaly types that can be detected
and terms of degree of resolution.
Services are provided by a specialty pigging
contractor. Results often require expertise in
interpreting data.
Either part or all of a pipeline is pigged
depending on the location of pig launching and
receiver equipment and the size and geometry
of the pipeline system.
Manually held instrument used in conjunction
with exposed pipe inspections. Requires coating
removal.
Done in conjunction with finding exposed pipe or
exposing pipe for inspection by digging at
various pipe locations. The bare pipe can only
be examined when the coating is removed.
These apply more to the effects of external
factors on the pipeline and the detection of leaks
than to factors associated with the conditions of
the pipe itself. They complement visual surveys.

<<<PAGE 722>>>

Section Name Sec. 1-1 (1 of 3) Sec. 2-1 (2 of 3) Sec. 3-1 (3 of 3) Satsuma Station Sec. 1-1 (1 of 3) Sec. 2-1 (2 of 3) Sec. 3-1 (3 of 3) Sec. 13B Sec. 13A Sec. 4-1 (1 of 2) Sec. 2-1 (2 of 2) Sec. 1-1 (1 of 4) Sec. 2-1 (2 of 4) Sec. 3-1 (3 of 4) Sec. 5-3 (4 of 4) Sec. 1-1 (1 of 7) Sec. 2-1 (2 of 7) Sec. 3-2 (3 of 7) Sec. 4-1 (4 of 7) Sec. 5-1 (5 of 7) Sec. 7 Sec. 6A & B Sec. 7-1 (7 of 7) Sec. 1-1 (1 of 6) Sec. 2-1 (2 of 6) Sec. 3-1 (3 of 6) Sec. 4-1 (4 of 6) Sec. 5-1 (5 of 6) Sec. 6-1 (6 of 6) Sec. 1-1 (1 of 4) Sec. 2-2 (2 of 4) Sec. 6-12 (3 of 4) Sec. 4-2 (4 of 4) Sec. 1-1 (1 of 4) Sec. 2-1 (2 of 4) Sec. 2A & B Table 5.3.5-2 Summary of Hydrostatic Tests
Date of
Testing
Beginning Test
Section (ft)
End Test
Section (ft)
Diameter
(in)
Min Pressure
(psig)
Pipe
Grade
2/11/2000 0 62,018 20 994 B
2/12/2000 62,018 128,628 20 995 B
2/11/2000 128,628 180,013 20 996 B
11/2/1998 180,013 180,263 18/16 1321 X-52
2/24/2000 180,263 241,637 18 1269 X-45
2/26/2000 241,637 338,598 18 1276 X-45
2/26/2000 338,598 402,659 18 1278 X-45
12/4/1995 338,364 462,200 18 1217 X-45
12/4/1995 462,200 596,078 18 1274 X-45
5/24/2002 595,962 711,251 18 1276 X-45
3/27/2000 711,251 800,291 18 1278 X-45
6/12/2002 800,280 852,896 18 1280 X-45
6/12/2002 852,896 896,366 18 1414 X-45
6/25/2002 896,366 997,465 18 2724 X-45
5/13/2002 997,465 1,016,229 18 1419 X-45
4/12/2000 1,016,128 1,026,620 18 1416 X-45
4/12/2000 1,026,620 1,048,852 18 1418 X-45
4/17/2000 1,048,852 1,074,458 18 1418 X-45
4/13/2000 1,074,458 1,118,725 18 1415 X-45
4/14/2000 1,118,725 1,138,673 18 1409 X-45
11/20/1995 1,118,844 1,203,340 18 1243 X-45
11/20/1995 1,203,340 1,460,647 18 1245 X-45
4/15/2000 1,203,733 1,236,231 18 1273 X-45
5/4/2000 1,236,231 1,304,029 18 1265 X-45
5/4/2000 1,304,029 1,343,575 18 1265 X-45
5/5/2000 1,343,575 1,391,175 18 1265 X-45
5/5/2000 1,391,175 1,412,541 18 1265 X-45
5/6/2000 1,412,541 1,436,741 18 1265 X-45
5/6/2000 1,436,741 1,460,755 18 1265 X-45
5/16/2000 1,460,755 1,514,472 18 1123 X-45
4/27/2002 1,514,472 1,559,154 18 1122 X-45
4/30/2002 1,559,154 1,616,691 18 1269 X-45
5/31/2000 1,616,691 1,699,642 18 1414 X-45
6/14/2000 1,699,642 1,758,799 18 1270 X-45
6/14/2000 1,758,799 1,829,913 18 1271 X-45
11/10/1995 1,699,421 1,893,964 18 1261 X-45

<<<PAGE 723>>>

Table 5.3.5-2 Summary of Hydrostatic Tests (continued)
Section Name Date of
Testing
Beginning Test
Section (ft)
End Test
Section (ft)
Diameter
(in)
Min Pressure
(psig)
Pipe
Grade
Sec. 4-1 (4 of 4) 6/14/2000 1,879,753 1,926,702 18 1272 X-45
Sec. 1 11/10/1995 1,893,964 2,135,340 18 1232 X-45
Kemper Station 4/26/1998 2,135,318 2,138,788 18 1275 X-65
Sec. 15 (Kemper to
Crane) 8/23/1995 2,138,780 2,333,459 18 1260 X-52
Sec. 1-1 (1 of 2) 7/1/2000 2,159,919 2,263,600 18 1307 X-52
Sec. 2-4 (2 of 2) 7/11/2000 2,263,600 2,415,817 18 1301 X-52
Sec. 1-1 10/25/1998 2,409,841 2,647,839 18 1970 X-65
Sec. 2-1 10/25/1998 2,647,839 2,849,320 18 1898 X-65
Sec. 3-1 10/27/1998 2,849,320 2,954,141 18 1833 X-65
Sec. 4-1 11/11/1998 2,954,141 3,000,851 18 1915 X-65
Sec. 5-1 11/12/1998 3,000,851 3,064,837 18 1857 X-65
Sec. 6-1 11/12/1998 3,064,837 3,090,948 18 1839 X-65
Sec. 7-2 11/12/1998 3,090,948 3,110,611 18 1850 X-65
Sec. 8-2 11/12/1998 3,110,611 3,133,500 18 1859 X-65
Sec. 9-1 11/13/1998 3,133,500 3,144,342 18 1858 X-65
Sec. 10-1 11/13/1998 3,144,342 3,166,108 18 1843 X-65
Sec. 11-1 11/14/1998 3,166,108 3,192,195 18 1861 X-65
Sec. 12-1 11/14/1998 3,192,195 3,282,242 18 1832 X-65
Sec. 13-1 11/14/1998 3,282,242 3,403,336 18 1840 X-65
Sec. 14-1 11/22/1998 3,403,336 3,489,788 18 1835 X-65
Sec. 15-1 11/21/1998 3,489,788 3,528,408 18 1831 X-65
Sec. 16-1 (El Paso) 11/21/1998 3,528,408 3,666,344 18 1837 X-65
Sec. 1 (Crane to
Odessa) 10/10/1998 0 148,396 8.625 1856 X-60
Sec. 1 (Odessa
Lateral Extension) 10/7/2004 148,396 154,482 8.625 1936 B
Four leaks were reported during the 1995 hydrostatic testing (From Kemper to Crane):
Origin of Leak Station No. (ft) Milepost Repairs
Hydrogen blister 2,146,607 406.6 Replaced 43' of
18" pipe
Leak in pipe body 2,160,888 409.3 Replaced 45' of
18" pipe
Hydrogen blister 2,190,051 414.8 Installed full wrap
18" long
ERW seam failure 2,242,311 424.7 Replaced 60' of
18" pipe

<<<PAGE 724>>>

Table 5.3.5-3 Summary of Hydrostatic Tests (2005 to 2011)
Valve Section Name Date of Testing
Diameter
(in)
Min Pressure
(psig)
Pipe
Grade
Crane Station to El Paso 1998 18 1,833 X65
18 2,023 X65
Various MP 77 to MP 404* 1999-2000
18 1,872 X60
18 1,850 X65
20 995 Gr B
Galena Park to Crane Station 2000
18 1,122 X45
18 1,279 X45
18 1,280 X45
Multiple Sections MP112.8 to MP 306.2** 2002
18 2,724 X65
Hwy 130 Adjustment MP 158.64 (508 ft.) 2005 18 1,852 X65
Crane – Monahann (42 mile replacement)
MP 486.8 – MP 528 2008 18 1838 X65
MP 350.8 – MP 351.5 2007 18 1875 X65
Multiple Test Sections – Tuckerton Road
Relocation MP 36 – MP 39.2 2011 18 1825 X52
Ped River Basin Replacements MP 188.4 –
MP 196.6 – Various sections 2011 18 1265 X65
East Houston Loop Installation 2010 20 1221 X52
*Hydrostatic tests of various line replacements were conducted between MP 77 and MP 404 from 1999 to 2000
**A total of 82.1 miles of both new and original 1950-pipe.
Leaks during testing occurred in 2002. See details in Chapter 5.

<<<PAGE 725>>>

Table 5.3.5-4 Summary of ILI Repair Criteria
Feature Location Schedule ILI identified condition
HCA Immediate1 Metal loss features (including SWFA, SWFB, ASWML and SWML) with predicted depths greater
than or equal to 80% of the wall thickness
HCA Immediate2
Features with predicted burst pressure, PBURST, less than PDPP requires reduce operating
pressure or shutdown pipeline until repair is made.
Metal loss calculation using 85% Area RSTRENG criterion or CorLASTM (Flow Stress
Criterion, 85% Area)
SWFA, SWFB, ASWML, or SWML calculation using CorLASTM (Fracture Mechanics
Criterion)
HCA Immediate2 Non-HCA 5 day
Top-side dents (above the 4 and 8 o’clock positions) predicted to contain associated metal loss,
cracking or a stress riser.
HCA Immediate2 Top-side dents with a predicted depth greater than 6% of the nominal pipe diameter.
Non-HCA 60 day
HCA Immediate2 Significant features in the judgment of the person evaluating the inspection and test assessment
Non-HCA 5 day
results.
All 5 day Metal loss greater than 70% wall thickness
HCA 60 day Top-side dents with a predicted depth greater than 3% of the pipeline diameter (greater than 0.250”
in depth for a pipeline diameter less than Nominal Pipe Size (NPS) 12).
HCA 60 day Bottom-side dents (below 4 and 8 o’clock positions) predicted to contain any metal loss, cracking,
or a stress riser.
All 180 day3 Dents with any of the following: Metal loss, corrosion, exceeds 6% of the pipe outside diameter, or
located in a longitudinal seam or girth weld.
HCA 180 day Top-side dents with a predicted depth greater than 2% of the pipeline’s diameter (0.250” in depth
for a pipeline diameter less than NPS 12).
All 180 day Features where the calculation of remaining strength of the pipe shows an operating pressure,
PSAFE, that is less than PDPP at the location of the anomaly.
HCA 180 day Areas of general corrosion with a predicted metal loss greater than 50% of nominal wall.
HCA 180 day
Features with predicted metal loss greater than 50% of nominal wall that are located at a crossing
of another pipeline, or are in an area with widespread circumferential corrosion, or are in an area
that could affect a girth weld.
HCA 180 day Potential crack indications that when excavated are determined to be a crack.
All 180 day3 Cracks located in the pipe body, girth weld, and longitudinal seam that are determined to be
injurious to the integrity of the pipeline.
6A-19

<<<PAGE 726>>>

Table 5.3.5-4 Summary of ILI Repair Criteria (continued)
Feature Location Schedule ILI identified condition
All 180 day Corrosion of or along a longitudinal seam weld (as identified by the ILI service provider as being
axially oriented seam weld metal loss).
HCA 180 day Gouge or grooves with a predicted depth greater than 12.5% of nominal wall.
All 180 day3 Gouges or grooves greater than 50% of nominal wall thickness.
All 180 day3 Casing shorts with associated metal loss.
All 180 day3 Girth weld anomalies
All 180 day3 Corrosion within 3” of either side and/or across girth welds
All Based upon
judgment
Severe Mill related defects such as laminations or hard spots. Injurious laminations are determined
to be those that are sloping, surface breaking, bulging or interacting with other features.
Any condition identified by ILI that could impair the integrity of the pipeline should be repaired as appropriate.
Note 1: Requires shutdown of the pipeline until the repair is made.
Note 2: Requires shutdown of the pipeline or reduction of the operating pressure until the repair is made.
Note 3: Indications which shall be investigated within 6 months of receipt of vendor report; mitigation action, if necessary, will occur after evaluation by excavation.

<<<PAGE 727>>>

Table 5.4.1-1 Pipeline and Facility Spill Data Since 2002
Release Date Location Name Location Type
PHMSA
Reportable
Product
Released Released To
BBLs
Released
Total BBLs
Recovered
7/19/2002 Warda Facility No Water Soil 119.048 0.000
8/19/2004 El Paso Facility No
IVD Additive
(Hydrocarbo
ns)
Concrete
Containment 0.071 0.071
8/29/2004 Crane Facility No Hydrocarbon
s/Crude Oil
Soil 0.714 0.714
9/17/2004 El Paso Facility Yes Diesel Soil 0.298 0.298
9/19/2004 El Paso Facility No Fuel, Diesel -
Low Sulfur
Soil 0.071 0.071
10/1/2004 Eckert Facility No Gasoline Soil 0.357 0.167
10/22/2004 El Paso Junction Facility Yes Fuel, Diesel -
Low Sulfur
Soil 0.238 0.238
10/26/2004 El Paso Facility Yes Fuel, Diesel -
Low Sulfur
Soil 0.238 0.238
11/11/2004 Odessa Facility Yes Gasoline Soil 0.357 0.357
11/29/2004 East Edwards
Aquifer Valve
Pipeline No Gasoline Soil 0.036 0.024
12/4/2004 El Paso Facility No Gasoline,
Regular,
Unleaded
Soil 10.310 0.310
12/18/2004 Crane Facility Yes Gasoline Soil 4.762 1.191
1/8/2005 Crane Facility No Gasoline,
Regular,
Unleaded
Soil 0.119 0.119
1/12/2005 Mainline Block
Valve SE11
Pipeline No Gasoline Soil 0.071 0.048
4/24/2005 Odessa Facility Yes Diesel Soil 7.290 7.200
7/18/2005
Warda to Cedar
Valley Pipeline Yes Gasoline Soil 5.000 5.000

<<<PAGE 728>>>

Table 5.4.1-1 Pipeline and Pump Station Spill Data Since 2002 (continued)
Release Date Location Name Location Type
PHMSA
Reportable
Product
Released Released To
BBLs
Released
Total BBLs
Recovered
12/27/2005 Kimble Facility No Gasoline Soil 0.071 0.071
12/29/2005 Crane Facility No Diesel Soil 0.095 0.095
10/19/2006 El Paso Facility No Diesel
Concrete
Pad 11.310 1.310
11/14/2006
Ft. McKavett to
Crane Pipeline No Gasoline Soil 0.548 0.548
4/23/2007 Galena Park Facility Yes Gasoline Soil/ Gravel 5.714 5.500
5/15/2007 El Paso Facility No Gasoline
Secondary
Containment 13.000 3.000
10/24/2007 El Paso Facility No Transmix Soil 0.048 0.048
12/21/2007 Diamond Junction Facility No Transmix Soil 0.071 0.071
1/23/2008 Galena Park Facility No
Corrosion
Inhibitor Gravel 10.238 0.238
2/1/2008 El Paso Facility No Gasoline Soil 0.071 0.071
2/13/2008 El Paso Facility No Gasoline Soil 0.071 0.071
2/20/2008 El Paso Facility No Diesel
Soil &
Containment 13.571 3.571
4/29/2008 Crane Facility Yes Diesel Soil 0.952 0.952
5/8/2008 El Paso* Facility No Diesel Soil 111.300 9.300
9/5/2008 El Paso Facility No
Contact
Water with
Diesel Soil 10.595 0.000
9/18/2008 Galena Park Facility Yes Gasoline
Soil and
Gravel 0.238 0.238
10/20/2008 Crane Facility Yes Diesel
Gravel and
Soil 0.119 0.000
3/31/2009 El Paso Facility No
Water, with
hydrocarbon
sheen Soil, Gravel 10.429 0.486
10/30/2009 El Paso FACILITY No
Hydraulic
Fluid Soil 10.286 0.286

<<<PAGE 729>>>

Table 5.4.1-1 Pipeline and Pump Station Spill Data Since 2002 (continued)
Release Date Location Name Location Type
PHMSA
Reportable
Product
Released Released To
BBLs
Released
Total BBLs
Recovered
1/16/2010 El Paso Facility No Diesel
containment
pad and soil 0.071 0.071
1/18/2010 El Paso Facility No N Grade Soil 0.024 0.024
5/17/2010 El Paso Facility No Gasoline Soil 0.095 0.095
11/29/2010 Crane Facility Yes Gasoline Soil/Gravel 0.238 0.238
2/3/2011 El Paso Facility No Diesel
concrete and
soil 10.476 0.476
3/21/2011 Satsuma Facility No Gasoline Soil/Gravel 0.048 0
6/23/2011 Warda Facility Yes Gasoline
Soil and
Gravel 2.357 1.767
Note 1 - Spill did not occur on PHMSA Regulated asset

<<<PAGE 730>>>

Release
Date
7/19/2002
8/19/2004
8/29/2004 9/17/2004
9/19/2004 10/1/2004 10/22/2004
10/26/2004 11/11/2004 12/4/2004 12/18/2004 1/8/2005
4/24/2005
12/27/2005 12/29/2005 Table 5.4.1-2 Summary of Cause of Release for Facilities
Cause Code
Name Incident Summary (Cause of Release)
Human Error -
Contractor Error
While pumping of hydrostatic test water into a storage facility tank manifold system, a valve
was left open releasing the material onto soil
Human Error -
Contractor Error
During the first filling, the IVD additive Tank was found to have a small leak at the base. After
removing the wax tape to locate the leak, it was found that a temporary plug had been driven
into a one-half inch threaded fitting.
Equipment Failure Not Specified
Human Error -
Company
Personnel
While receiving pipeline pigs during commissioning, the scraper trap was drained to the
normal system, to the separator/sump. On the launcher, a plug was left out of the drain,
allowing the product to rise and overflow the drain pan.
Equipment Failure
During commissioning of Tank four, water draw pig tail upper valve was leaking from a weep
hole.
Equipment Failure A dead-end blind flange was found to be dripping.
Human Error -
Company
Personnel A fitting was left open on the line.
Equipment Failure Flange Leak on Scraper Trap.
Other Possible Drain Line
Equipment Failure Pump Mechanical Seal on Tank Pump #1 failed.
Equipment Failure
A TSV released from a valve body and filled the sump. The sump high-level alarm failed to
operate. The sump overflowed.
Human Error -
Contractor Error
The relief piping going to the relief tank was closed off. All the valves blocked it and we were
blowing nitrogen through the piping. Some gasoline still inside piping came out the two inch
valve nearest the relief tank side.
Human Error -
Company
Personnel Drain valve opened and overfilled sump.
Equipment Failure
Both pump seals failed. Seal drain lines clogged. Product spilled from pump skid onto
ground.
Equipment Failure While draining mainline strainer to the sump.

<<<PAGE 731>>>

Table 5.4.1-2 Summary of Cause of Release for Facilities (continued)
Release
Date
Cause Code
Name Incident Summary (Cause of Release)
10/19/2006 Equipment Failure
Volumetric Prover at the Truck Loading Rack Overflowed while the meter was being
calibrated.
4/23/2007 Equipment Failure Tubing Failure on a baring box cooling line.
5/15/2007 Equipment Failure
A driver started loading Regular Unleaded Gasoline into his tanker truck when he noticed
his fuel tank leaking.
10/24/2007
Human Error -
Company
Personnel
Leak on a flange and spilled approx. two gallons of product on the ground. During tank
maintenance technician used a LOTO template. The template did not meet the exact scope
of work, closing the valves did not allow for thermal relief.
12/21/2007
Human Error -
Contractor Error
In a drain down at the pipeline a release of 1.5 - 3 gallons of transmix (primarily diesel) to
soil.
During a construction project, secondary containment in place during drain-up and was
removed. Decision was made to install a skillet in upstream valve, secondary containment
was not used and product hit the ground when they opened the flange.
1/23/2008
Human Error -
Driver
A cam lock fitting on the discharge side of a semi-truck vibrated loose causing product to
spill. Driver did not wire-tie or secure fitting to prevent cam-lock from vibrating open per
9.01-ADM-185 (Appendix 5A).
2/1/2008 Equipment Failure
1/2 pipe TSV (terminal relief valve) connection came loose and began to leak. An operator
discovered the release and secured the valve. The leak resulted in approximately three
gallons spilled onto the top soil. T
2/13/2008
Human Error -
Company
Personnel
There was a thermal relief block valve that was partially closed and not "car sealed" per
procedure at tank 12 thus over pressuring the rack manifold causing a spill of material on the
ground. Failure to follow LOTO procedures.
2/20/2008 Equipment Failure
Diesel fuel leak partially outside containment, inside terminal at Filter F-3. Approximately 25
gallons in containment, 125 gallons outside containment released to soil. Toptech
configuration issue, causing tank 15 pump to turn on inadvertently.
4/29/2008
Human Error -
Contractor Error
While equalizing the levels between Tank 53 and Tank 52 to put T52 into service, product
was discovered leaking from the tank inlet valve’s flange. This flange was split to remove a
skillet after completion of American Petroleum Institute 653 tank inspection and not properly
re-installed.
5/8/2008 Equipment Failure A broken nipple on a pressure release valve on a pump going to the truck rack.

<<<PAGE 732>>>

Table 5.4.1-2 Summary of Cause of Release for Facilities (continued)
Release
Date
Cause Code
Name Incident Summary (Cause of Release)
9/5/2008
Human Error -
Contractor Error
A contractor was removing the liquid contents (water and diesel) from the secondary
containment for a temporary diesel storage tank and walked away during the transfer. The
55-gallon drum in which the liquid was being pumped overfilled. Magellan/Contract personnel
responded to the incident and took immediate steps to contain the release.
9/18/2008
Human Error -
Company
Personnel
A mainline strainer O-ring failed while pumping product from the sump to the mainline. In
early Sept. maintenance was performed in GP; valve indicator stems were identified as
broken on MOV 3 & 4 but not repaired, O-ring was not replaced when strainer was opened
as required and sump pump internal relief (either failure or set at wrong value) did not shut
down the pump of which over pressured the reinjection line.
10/20/2008
Human Error -
Contractor Error
Tank 51 was being re-filled from the mainline pipeline with diesel. The onsite technician was
monitoring the tank refilling activities and noticed weeping from under the tank. Upon
discovering the weeping, the technician contacted operations control who in turn terminated
the tank filling.
3/31/2009
Human Error -
Company
Personnel
A technician was preparing prover for a water draw. The Technician was in the process of
flushing the prover with water. In order to do this he had to open the vent valve located on
the prover to prevent the prover from air locking. While filling the prover with water, the
technician returned to his truck to talk with another technician. The facility engineer arrived
on site and noticed water coming from the vent and notified the technicians.
10/30/2009 Equipment Failure
Contractor (CTI) transport truck loading tank bottoms for transport broke hydraulic hose on
truck and spilled approximately 12 gallons of hydraulic fluid on ground.
1/16/2010 Equipment Failure
Leaking flange on filter vessel spilled diesel in containment area and sprayed some on
ground.
1/18/2010 Equipment Failure
While doing the morning walk down an operator noticed a small leak coming from the Pump
on Tank 17. After investigating it was found to be the pump seal.
5/17/2010
Human Error -
Company
Personnel Found gasoline leaking from a plug hole on the stripper pump
11/29/2010 Equipment Failure
The seal on the prover valve stem leaked. The containment under the valve was only
partially effective due to high winds in the area.
The 4 way prover valve was originally installed upside down, this has been corrected.

<<<PAGE 733>>>

Table 5.4.1-2 Summary of Cause of Release for Facilities (continued)
Release
Date
Cause Code
Name Incident Summary (Cause of Release)
2/3/2011 Equipment Failure
The O-rings on rack diesel filter vessels F7 & F8 started to leak. Impacted area was cleaned
up. Reviewed proper torqueing procedure, tagged bolts on vessel flange to assist with
sequence, replaced gasket, and placed copy of filter change procedure at vessel site. Did
not determine root cause of gasket failure.
3/21/2011 Equipment Failure
A nipple cracked on a mainline unit at Satsuma Station released a mist of product. The
nipple was connected to drain piping that likely vibrated and caused the failure. The cracked
nipple was replaced and the drain piping was removed as it is not necessary.
6/23/2011 Equipment Failure Stem packing on the valve was identified as the leak source and was repaired.

<<<PAGE 734>>>

Release
Date 11/29/04 01/12/05 07/18/05
11/14/06 Table 5.4.1-3 Summary of Cause of Release for Pipeline (Not Facilities)
Cause Code Incident Summary (Cause of Release)
Equipment Failure Drip found emanating from valve stem on 1" ball valve upstream of SE8.
Equipment Failure -
Valve Steam leak from ½-inch ball valve.
Equipment Failure -
Cracked/Leaking
Fitting
2” nipple cracked while injecting product into pig launching barrel.
Corrosion -
External
Crew was prepping anomaly found during ILI tool run for repair. While sandblasting the
affected area in preparation for installing a sleeve product started misting from a pinhole
in the pipeline.

<<<PAGE 735>>>

Table 5.4.1-4 Texas Reportable Incidents and Frequencies
Texas
All
Incidents1 Significant
Incidents2
Miles Existing in 2010 50,8343 50,834
Incidents 2001-2010 9943 3333
Gross Barrels Spilled 291,2453 287,8663
Avg Incidents/yr 99.4 33.30
Incidents/1000mi-Yr 1.96 0.66
Avg BBL/Yr 29,125 28,787
Avg BBL/mi-Yr 0.57 0.57
Table 5.4.1-5 US Reportable Incidents and Frequencies
US All
Incidents1 Significant
Incidents2
Miles Existing in 2010 170,961 170,961
Incidents 2001-2010 3,444 1,153
Gross Barrels Spilled 1,052,896 1,042,588
Avg Incidents/yr 344.40 115.30
Incidents/1000mi-Yr 2.01 0.67
Avg BBL/Yr 105,290 104,259
Avg BBL/mi-Yr 0.62 0.61
All data are from PHMSA for 49 CFR Part 195 Jurisdictional Hazardous Liquid
Pipelines hazardous liquid pipeline operators
1All Reportable incidents as defined by PHMSA
2Significant Incidents as defined by PHMSA:
http://primis.phmsa.dot.gov/comm/reports/safety/SigPSI.html?nocache=5235 3Extracted from: http://primis.phmsa.dot.gov/comm/reports/safety/TX_detail1
42009 mileage from the Natural Gas Transmission, Gas Distribution, and Hazardous Liquid Pipeline
Annual Mileage, Nov 30, 2011, as reported from:
http://phmsa.dot.gov/portal/site/PHMSA/menuitem.
5Extracted from: http://primis.phmsa.dot.gov/comm/reports/safety/AllPSI.html
6Extracted from: http://primis.phmsa.dot.gov/comm/reports/safety/SigPSI.html
Table 5.4.1-6 Longhorn Reportable Incident Frequencies
Longhorn
2002 – 2011
(9.5 years)*
Longhorn
1/27/05-2011
(6.5 years)*
Texas
Pipelines
2001 – 2010
US
Pipelines
2001 - 2010
Pipe Spill Frequency
(spills/year/1,000 miles) 1.89 1.70 1.96 2.01
Pipe Spill Volume
(bbl/year/mile) .004 .005 0.57 0.62
*Note: Data gathered through mid-2011. Data based upon 722.5 miles of the Longhorn system. 13 reportable leaks
totaling 28 bbls since 2002 and 8 reportable leaks totaling 22 bbls since 2005.

<<<PAGE 736>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 5
APPENDICES

<<<PAGE 737>>>

ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 5A
REFERENCED PROCEDURES OF THE 2012 MAGELLAN SIP

<<<PAGE 738>>>

APPENDIX 5A
REFERENCED PROCEDURES OF THE MAGELLAN 2012 SIP
SIP-ADM 7.01-001
SIP-ADM 7.03
SIP-ADM 7.03-003
SIP-ADM 7.03-007
SIP-ADM 7.04
SIP-ADM 7.04-001
SIP-ADM 7.04-005
SIP-ADM 7.04-006
SIP-ADM 7.04-023
SIP-ADM 7.05
SIP-ADM 7.05-002
SIP-ADM 7.05-014
SIP-ADM 7.05-020
SIP-ADM 7.05-030
SIP-ADM 7.05-031
SIP-ADM 7.05-037
SIP-ADM 7.05-039
SIP-ADM 7.07-002
SIP-ADM 8.01
SIP-ADM 9.01-185
SIP-ADM 10.01
SIP-ADM 13.02
SIP-ADM 14.01

<<<PAGE 739>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 1 of 16
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for identification,
analysis and repair of pipeline defects when necessary.
2.0 PROCEDURE
2.1 General
2.1.1 Exceptions—This procedure may not apply to the following conditions:
2.1.1.1 Emergency situations such as a major pipeline release
2.1.1.2 Threaded piping
2.1.2 DEFECT ASSESSMENT, RSTRENG ANALYSIS OF CORROSION OR KAPA,
NONDESTRUCTIVE TESTING, MAINTENANCE WELDING, COATING
APPLICATION, AND INSTALLATION OF REPAIRS (E.G., CLAMPS,
COMPOSITE REPAIRS) ARE COVERED TASKS.
2.1.3 WELDING ON LINES THAT ARE UNDER INTERNAL PRESSURE (LIVE LINE
WELDING) SHALL BE DONE IN ACCORDANCE WITH COMPANY WELDING
PROCEDURES AND PRACTICES. REFER TO SPECIFICATION 101,
MAINTENANCE WELDING (EXCLUDING ETHYLENE PIPELINES).
2.2 PRECAUTIONS
2.2.1 ALL EXPOSED BELL AND SPIGOT GIRTH WELDS SHALL BE REINFORCED
BY MEANS OF SLEEVING
2.2.2 IF NEEDED (WHEN PIPE IS NOT RESTING ON THE GROUND) THE PIPE
SHOULD BE ADEQUATELY SUPPORTED PRIOR TO BACKFILLING.
CONSIDERATION SHOULD BE GIVEN TO USING DIRT PLUGS OR
SANDBAGS AT SPACING INTERVALS NOT TO EXCEED 20 FEET
PARTICULARLY IN AREAS WHERE ADDITIONAL WEIGHT HAS BEEN
APPLIED BY INSTALLATION OF SLEEVING.
2.2.3 ALL EXPOSED GIRTH WELDS (INCLUDING BELL AND SPIGOT JOINTS)
SHALL BE SUPPORTED (SUPPORTS TO BE PLACED ON EACH SIDE OF
THE GIRTH WELD NOT TO EXCEED 5 FEET) VIA SANDBAGS OR
EQUIVALENT SETTLEMENT RESISTANT SUPPORTS PRIOR TO
BACKFILLING.
2.2.4 PIPELINE DEFECTS DISCOVERED THROUGH INTEGRITY TESTS SUCH AS
IN-LINE INSPECTIONS (ILI), PRESSURE TEST, AND ROUTINE
MAINTENANCE SHALL BE ASSESSED AND REPAIRED, IN A TIMELY AND
CONSISTENT MANNER UTILIZING AND COMPLYING WITH COMPANY
PROCEDURES, INDUSTRY STANDARDS AND APPLICABLE REGULATIONS
(DOT 195.452) AND RECOMMENDED PRACTICES.
2.2.5 PIPELINE DEFECTS (INCLUDING GENERAL OR LOCALIZED CORROSION)
CONFIRMED THROUGH ACTUAL FIELD FINDINGS (NOT REPORTED BY ILI
TOOL) THAT MEET THE CRITERIA OF A PRESSURE REDUCING DEFECT
SHALL BE REPAIRED IMMEDIATELY. UPON DISCOVERY, A PRESSURE
AND OR RATE REDUCTION, OR LINE SHUTDOWN SHALL BE
CONSIDERED.
2.2.6 PIPELINE DEFECTS NOT REPAIRED BY MEANS OF FULL ENCIRCLEMENT
SLEEVING AND OR PIPE REPLACEMENT SHOULD BE NON-
DESTRUCTIVELY TESTED PRIOR TO RECOATING.

<<<PAGE 740>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 2 of 16
2.2.7 2.2.8 2.2.9 ALL REPAIRS ARE MADE IN A SAFE MANNER AND ARE MADE SO AS TO
PREVENT DAMAGE TO PERSONS OR PROPERTY AND TO COMPLY WITH
DOT 195.422.
All materials used for repairs or replacement such as sleeves, pipe, fittings, and
valves shall meet the minimum design requirements of the asset.
ENSURE THAT THE SITE AND/OR BELL HOLE ARE SAFE, PRIOR TO AND
DURING PIPELINE EXCAVATION ACTIVITIES. FOR SPECIFIC GUIDELINES
TO TRENCHING, REFER TO THE EXCAVATION SAFETY PROCEDURE.

<<<PAGE 741>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 3 of 16
2.2.10 DETERMINE IF THE COATING CONTAINS ASBESTOS, BEFORE
AUTHORIZING OR ALLOWING ANY PIPELINE COATING REMOVAL. TO THE ASBESTOS PERFORMANCE PROCEDURE.
REFER
2.2.11 IF THE DEFECT APPEARS TO BE ASSOCIATED WITH PRODUCT LOSS
(LEAKING), TAKE APPROPRIATE MEASURES AS INDICATED BY THE
EMERGENCY RESPONSE PLANS TO SHUT THE LINE IN OR REDUCE THE
2.3 PRESSURE IN THE PIPELINE TO A SAFE PRESSURE BASED ON THE
PRELIMINARY EVALUATION, FEATURE SITE AND PIPELINE OPERATION
INFORMATION.
2.2.12 WHEN CLEANING PIPE (I.E. SAND BLASTING OR POWER BRUSHING) FOR
PREPARATION OF EVALUATING, REPAIRING, OR COATING PIPELINE
DEFECTS EXERCISE EXTREME CARE AS ACTUAL DEPTH OF DEFECT
MAY BE GREATER THAN REPORTED OR PREDICTED. TO ENSURE SAFE
WORK PRACTICES LIGHTLY CLEAN PIPE UNTIL IT IS EVIDENT THAT
SUFFICIENT REMAINING WALL EXIST TO ALLOW THOROUGH CLEANING
OF THE DEFECT.
REVIEW AND PERFORM THE FOLLOWING GENERAL STEPS FOR EVALUATION OF
ALL DEFECTS
2.3.1 2.3.2 2.3.3 2.3.4 UPON COMPLETION OF THE EXCAVATION, PHOTOGRAPH THE REPAIR
SITE PRIOR TO REMOVING THE COATING.
PREPARE THE SITE AND PIPELINE FOR A DETAILED EVALUATION OF THE
DEFECT AFTER IT HAS BEEN DETERMINED IT IS SAFE TO WORK ON OR
NEAR THE PIPELINE. THIS INCLUDES REMOVING COVER TO FULLY
EXPOSE THE PIPE, COATING REMOVAL AND APPROPRIATELY CLEANING
THE FEATURE TO BE EVALUATED IN ORDER TO MAKE DETAILED
MEASUREMENTS OF THE FEATURE AND TO DETERMINE THE TYPE OF
DEFECT.
DOCUMENT ALL DEFECT INFORMATION ON PIPELINE MAINTENANCE
REPORT.
VISUALLY DETERMINE THE TYPE OF DEFECT THEN USE THE
APPROPRIATE PART OF THIS PROCEDURE, LISTED BELOW, TO ASSIST
WITH FEATURE EVALUATION AND THE RECOMMENDED REPAIR
OPTIONS. REFER TO TABLE 1 FOR A DETAILED LISTING OF REPAIR
OPTIONS. UNDER SPECIAL CIRCUMSTANCES, THE MANAGER OF ASSET
INTEGRITY CAN APPROVE DEVIATIONS FROM THE
APPROVED/PREFERRED REPAIR METHODS LISTED IN TABLE 1.
2.3.4.1 CORROSION—PARAGRAPH 2.4
2.3.4.2 PIPE BODY GOUGES AND/OR MILL DEFECTS—PARAGRAPH
2.5
DENTS AND DENTS WITH ASSOCIATED GOUGES/STRESS
RISERS—PARAGRAPH 2.6
2.3.4.4 ARC BURNS—PARAGRAPH 2.7
2.3.4.5 WELD DEFECTS—PARAGRAPH 2.8
2.3.4.6 STRESS CORROSION CRACKING (SCC)—PARAGRAPH 2.9
2.3.4.7 SELECTIVE SEAM CORROSION (SSC)- PARAGRAPH 2.10
2.3.4.8 HARD SPOTS—PARAGRAPH 2.12
2.3.4.3

<<<PAGE 742>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 4 of 16
2.4 2.5 2.6 2.3.4.9 BUCKLING—PARAGRAPH 2.13
2.3.4.10 CRACKS- LONG SEAM AND PIPE BODY- PARAGRAPH 2.13
EVALUATE AND SELECT REPAIR OPTIONS FOR CORROSION
2.4.1 AFTER CAREFULLY REVIEWING THE CORROSION FOOTPRINT OR
CHARACTERISTICS, CLEAN THE AREA SUITABLY TO AID IN THE
EVALUATION OF THE CORROSION. WHEN CLEANING PIPE (I.E. SAND
BLASTING OR POWER BRUSHING) FOR PREPARATION OF EVALUATING,
REPAIRING, OR COATING PIPELINE DEFECTS EXERCISE EXTREME CARE
AS ACTUAL DEPTH OF DEFECT MAY BE GREATER THAN REPORTED OR
PREDICTED. TO ENSURE SAFE WORK PRACTICES LIGHTLY CLEAN PIPE
UNTIL IT IS EVIDENT THAT SUFFICIENT REMAINING WALL EXIST TO
ALLOW THOROUGH CLEANING OF THE DEFECT.
2.4.2 IF DETERMINED NECESSARY, MEASURE THE LENGTH (IN THE
LONGITUDINAL DIRECTION) AND DETERMINE THE DEPTH OF THE
DEEPEST PITTING WITHIN A CORRODED AREA OR A SEGMENT OF THAT
AREA. THE CORROSION ANALYSIS CRITERION FOR RSTRENG OR KAPA
REQUIRES DIVISION OF THE PITTED AREA INTO SEGMENTS OF
CONSISTENT PREDETERMINED LENGTHS AND MEASUREMENT OF THE
MAXIMUM DEPTHS WITHIN EACH SEGMENT. REFER TO RSTRENG
ANALYSIS OF CORROSION PROCEDURE FOR DETAILS.
2.4.3 REFER TO PARAGRAPH 2.16 OF THIS PROCEDURE FOR CORROSION
REPAIR METHODS AND OPTIONS.
2.4.4 NOTIFY ASSET INTEGRITY FOR ASSISTANCE WITH REPAIR OPTIONS
WHEN INTERNAL CORROSION IS FOUND OR SUSPECTED.
EVALUATE AND SELECT REPAIR OPTIONS FOR PIPE BODY GOUGES AND/OR
MILL DEFECTS
2.5.1 MEASURE THE DEFECT CIRCUMFERENTIAL WIDTH, LENGTH AND DEPTH
AT THE DEEPEST POINT AND SEVERAL OTHER POINTS ALONG ITS
LENGTH. MEASURE THE ANGLE, WHEN APPLICABLE, OF THE DEFECT
RELATIVE TO THE RUN OF THE PIPELINE.
2.5.2 REFER TO TABLE 1 OF THIS PROCEDURE FOR GOUGES, PIPE BODY
AND/OR MILL DEFECTS REPAIR METHODS AND OPTIONS.
2.5.3 IF THE REPAIR IS MADE BY REMOVING THE DEFECT BY MEANS OF
SANDING/GRINDING, UPON COMPLETION, THE AREA SHALL BE
NONDESTRUCTIVELY INSPECTED TO ENSURE THAT A STRESS RISER,
STRESS CONCENTRATION, CRACK OR OTHER INJURIOUS DEFECT DOES
NOT EXIST PRIOR RECOATING THE AREA.
EVALUATE AND SELECT REPAIR OPTIONS FOR DENTS
2.6.1 MEASURE THE DENT AREA (THE LENGTH, CIRCUMFERENCE AND DEPTH
AT THE DEEPEST POINT). EXAMINE THE BOTTOM OF THE DENT FOR
SCRATCHES, GOUGES, GROOVES, METAL LOSS OR HEAVILY WORK-
HARDENED MATERIAL. MEASURE SCRATCH, GOUGE, GROOVE OR
METAL LOSS, IF PRESENT, LENGTH AND DEPTH AT THE DEEPEST POINT
ALONG ITS LENGTH.
2.6.2 (REFERENCE SECTION, WHEN REQUIRED FOR USE WITH TABLE 1) ANY
DENT THAT EXCEEDS 2% OR 0.250” IN NPS < 12”, WITH OR WITHOUT
VISIBLE METAL LOSS, SHALL BE REPAIRED WITH A TYPE B SLEEVE.

<<<PAGE 743>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 5 of 16
2.7 2.6.3 DENTS 2% OR LESS IN NPS <12” THAT ARE PROVEN BY
NONDESTRUCTIVE INSPECTION THAT A STRESS RISER, STRESS
CONCENTRATION, CRACK OR OTHER INJURIOUS DEFECT DOES NOT
EXIST WITHIN THE DENT MAY BE RECOATED.
REFER TO PARAGRAPH 2.16 OF THIS PROCEDURE FOR DENT REPAIR
METHODS AND OPTIONS.
EVALUATE AND SELECT REPAIR OPTIONS FOR ARC BURNS
2.7.1 NOTE: IF THE ARC BURN IS ON A NEW LINE UNDER
CONSTRUCTION, THE ARC BURN SHALL BE REMOVED AS A CYLINDER, PER
THE ONSHORE CONSTRUCTION SPECIFICATIONS.
2.8 2.7.2 EXAMINE ARC BURNS FOR CRACKING AND DEPTH.
2.7.3 REFER TO SPECIFICATION 101: MAINTENANCE WELDING (EXCLUDING
ETHYLENE PIPELINES) PARAGRAPH 7.0 AND PARAGRAPH 2.16 OF THIS
PROCEDURE FOR ARC BURN REPAIR METHODS AND OPTIONS.
EVALUATE AND SELECT REPAIR OPTIONS FOR WELD DEFECTS
2.8.1 EXAMINE WELD DEFECTS VISUALLY IN ACCORDANCE WITH
SPECIFICATION 100, CONSTRUCTION AND FABRICATION OF PIPELINES
AND RELATED PIPING SYSTEMS AND SPECIFICATION 101, MAINTENANCE
2.9 WELDING (EXCLUDING ETHYLENE PIPELINES). EVALUATE WELDS THAT
HAVE BEEN X-RAYED IN ACCORDANCE WITH LATEST APPROVED API
SPECIFICATION.
2.8.2 REPAIR ALL IN-SERVICE JOINT WELDS IN ACCORDANCE WITH
SPECIFICATION 101 – MAINTENANCE WELDING (EXCLUDING ETHYLENE
PIPELINES). THIS WILL USUALLY REQUIRE THE USE OF A SMALL TYPE B
REPAIR SLEEVE COMMONLY CALLED A “WEDDING BAND”.
2.8.3 THE ONLY REPAIR ALLOWED ON A LONG-SEAM WELD IS GRINDING OR
SANDING TO REMOVE SURFACE DEFECTS THAT DO NOT EXCEED 12.5%
(REFERENCE 2.5.3) OF THE PARENT METAL WALL THICKNESS. REPAIR
ALL OTHER WELD DEFECTS BY INSTALLING A FULL ENCIRCLEMENT
TYPE B REPAIR SLEEVE OR CUTTING OUT A CYLINDER OF PIPE AND
REPLACING IT WITH NEW PIPE.
EVALUATE AND SELECT REPAIR OPTIONS FOR LAMINATION DEFECTS
2.9.1 EXAMINE PIPE FOR LAMINATION BY NON DESTRUCTIVE TESTING OF THE
SURFACE IN THE AREA OF CONCERN.
2.9.2 DOCUMENT THE LENGTH, ORIENTATION, PROXIMITY TO SEAM AND
GIRTH WELD IF RELEVANT, AND NOTE ADDITIONAL INTERACTIVE
FEATURES (METAL LOSS, CRACKS, DENTS, ETC.), IF APPLICABLE NOTE
SLOPING, BULGING, SURFACE BREAKING, AND BLISTERING.
2.9.3 REPAIRS WILL BE MADE IN ACCORDANCE WITH SECTION 2.15.
2.9.4 INSPECT THE FULL CIRCUMFERENCE OF THE PIPELINE WHERE THE
SLEEVE ENDS ARE TO BE WELDED TO THE PIPELINE USING AN
ULTRASONIC THICKNESS INSTRUMENT AND/OR A MAGNETIC PARTICLE
INSPECTION TECHNIQUE. ENSURE THERE ARE NO SURFACE CRACKS,
LAMINATIONS OR THIN WALL THAT COULD AFFECT THE INTEGRITY OF
THE DEFECT, WELD, OR SLEEVE.

<<<PAGE 744>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 6 of 16
2.10 EVALUATE AND SELECT REPAIR OPTIONS FOR STRESS CORROSION CRACKING
(SCC)
2.10.1 2.10.2 2.10.3 EXAMINE PIPE FOR STRESS CORROSION CRACKING (SCC) BY NON
DESTRUCTIVE TESTING AND OR MAGNETIC PARTICLE INSPECTION OF
THE SURFACE IN THE AREA OF CONCERN. DOCUMENT THE FINDINGS
WITH PHOTOGRAPHS WHEN POSSIBLE OR DRAW A SKETCH SHOWING
THE AREA AFFECTED BY CRACKING. DOCUMENT THE LENGTH,
DENSITY, SPACING AND GENERAL LOCATION OF THE CRACKS RELATIVE
TO OTHER SURFACE CONDITIONS SUCH AS LONGITUDINAL AND JOINT
WELDS.
NOTIFY ASSET INTEGRITY FOR ASSISTANCE WITH REPAIR OPTIONS
WHEN SCC IS FOUND OR SUSPECTED.
IF SCC IS DISCOVERED ON ASSETS COVERED BY THE MITIGATION PLAN,
REFER TO THE ORA PROCESS MANUAL DECISION TREE PRIOR TO
EVALUATING AND REPAIRING.
DOCUMENT WHETHER OR NOT SCC WAS DISCOVERED ON PIPELINE
MAINTENANCE REPORT.
2.11 EVALUATE AND SELECT REPAIR OPTIONS FOR SELECTIVE SEAM CORROSION
2.10.4 (SSC)
2.11.1 2.12 2.11.2 2.11.3 2.12.1 EXAMINE PIPE FOR SELECTIVE SEAM CORROSION (SSC) BY
EVALUATING THE LONGITUDINAL SEAM WELD FOR LOCALIZED
CORROSION LOCATED ALONG THE BOND LINE OF LOW FREQUENCY
ELECTRIC RESISTANCE WELDING (LR-ERW) AND ELECTRIC FLASH
WELDING (EFW) PIPING, THAT LEADS TO THE DEVELOPMENT OF A
WEDGE SHAPED GROOVE THAT IS OFTEN FILLED WITH CORROSION
PRODUCTS. DOCUMENT THE FINDINGS WITH PHOTOGRAPHS WHEN
POSSIBLE OR DRAW A SKETCH SHOWING THE AREA AFFECTED BY
SELECTIVE SEAM CORROSION.
NOTIFY ASSET INTEGRITY FOR ASSISTANCE WITH REPAIR OPTIONS
WHEN SSC IS FOUND OR SUSPECTED.
DOCUMENT WHETHER OR NOT SSC WAS DISCOVERED ON THE PIPELINE
MAINTENANCE REPORT.
2.13 EVALUATE AND SELECT REPAIR OPTIONS FOR HARD SPOTS
MEASURE HARD SPOT AREA (THE LENGTH AND CIRCUMFERENCE) AND
MAP THE HARDNESS USING CALIBRATED PORTABLE TESTING
EQUIPMENT.
2.12.2 MEASURE THE HARDNESS AND MAKE A SKETCH SHOWING THE
HARDNESS DISTRIBUTION. USE THE FOLLOWING CRITERIA WHEN
EVALUATING HARD SPOTS: REPAIR ALL HARD SPOTS WHEN THE
MAXIMUM HARDNESS EXCEEDS ROCKWELL C 35. REFER TO
PARAGRAPH 2.16 OF THIS PROCEDURE FOR HARD SPOT REPAIR
METHODS AND OPTIONS.
EVALUATE AND SELECT REPAIR OPTIONS FOR BUCKLING/RIPPLES/WRINKLES
2.13.1 NOTIFY ASSET INTEGRITY FOR ASSISTANCE WITH REPAIR CRITERIA
AND REPAIR METHODS AND OPTIONS.
2.13.2 REFER TO PARAGRAPH 2.13 OF THIS PROCEDURE FOR BUCKLING

<<<PAGE 745>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 7 of 16
2.14 2.15 REPAIR METHODS AND OPTIONS.
EVALUATE AND SELECT REPAIR OPTIONS FOR LONG SEAM AND PIPE BODY
CRACKS
2.14.1 EXAMINE PIPE FOR CRACKING BY NON-DESTRUCTIVE TESTING AND
MAGNETIC PARTICLE INSPECTION OF THE SURFACE IN THE AREA OF
CONCERN. DOCUMENT THE FINDINGS WITH PHOTOGRAPHS WHEN
POSSIBLE OR DRAW A SKETCH SHOWING THE AREA AFFECTED BY
CRACKING. DOCUMENT THE LENGTH, DENSITY, SPACING AND GENERAL
LOCATION OF THE CRACKS RELATIVE TO OTHER SURFACE CONDITIONS
SUCH AS LONGITUDINAL AND JOINT WELDS.
2.14.2 REFER TO TABLE 1 OF THIS PROCEDURE FOR CRACK IN PIPE BODY OR
WELD SEAM FOR REPAIR METHODS AND OPTIONS.
REPAIR METHODS AND OPTIONS FOR FEATURES OR DEFECTS
2.15.1 REFER TO THE CHART BELOW FOR EVALUATING REPAIR OPTIONS.
UNDER SPECIAL CIRCUMSTANCES, THE MANAGER OF ASSET INTEGRITY
CAN APPROVE DEVIATIONS FROM THE APPROVED/PREFERRED REPAIR
METHODS LISTED IN THE FOLLOWING CHART.
Table 1
Repair Method
Re-Coat Defect Type
Grind
/Sand
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
HCA Immediate Condition
Metal loss >80% (external)
Assets Covered by Mitigation Plan >70% N N N X T N O
Metal loss >80% (internal)
Assets Covered by Mitigation Plan >70%
N N N O T N X
PBURST < PDPP at location of anomaly
(external)
N N O X T O O
PBURST < PDPP at location of anomaly
(internal)
N N N X T N O
Dents above 4:00 and 8:00 with any
indicated metal loss, cracking, or stress
riser
(See Paragraph 2.6.2)
N N N X T N O
Dents above 4:00 and 8:00 with a depth
>6% of nominal pipe diameter N N N X T O O

<<<PAGE 746>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE Asset Integrity 01/01/12 Re-Coat Defect Type
Grind
/Sand
(See Paragraph 2.6.2)
HCA 60-Day Condition
Dents above 4:00 and 8:00 with a
depth>3% of nominal pipe diameter
(>0.250” in depth for a pipeline diameter
<NPS 12)
(See Paragraph 2.6.2)
N N Dents below 4:00 and 8:00 with any
indicated metal loss, cracking, or stress
riser
(See Paragraph 2.6.2)
N N HCA 180-Day Condition
Dents >2% of nominal pipe diameter
(>0.250” in depth for a pipeline diameter
<NPS 12) that affects pipe curvature at a
girth weld or longitudinal seam weld
(See Paragraph 2.6.2)
N N Dents above 4:00 and 8:00 with a depth
>2% of pipeline diameter (>0.250” in depth
for a pipeline diameter <NPS 12)
(See Paragraph 2.6.2)
N N Dents below 4:00 and 8:00 with a depth
>6% of pipeline diameter
(See Paragraph 2.6.2)
N N PSAFE<PDPP at location of anomaly
(external) N N PSAFE<PDPP at location of anomaly (internal) N N Crack in pipe body or weld seam N N 7.01–ADM–001
Revision: 9 Page 8 of 16
Repair Method
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
O X T O O
N X T N O
N X T N O
O X T O O
N X T O O
O X T O O
O X T N O
N X T N O

<<<PAGE 747>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 9 of 16
Repair Method
Re-Coat Defect Type
Grind
/Sand
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
Corrosion of or along a longitudinal seam
weld (Selective Seam Corrosion) N N N X T N O
Gouges or grooves >12.5% nominal wall
thickness N N N X T N O
Other Conditions
N N N X T N O
Leaking defect
Metal loss <12.5% nominal wall thickness X N N N N N N
Non-Injurious Planar Laminations X N O O T N O
Sloping Laminations N N N X T N O
Bulging Laminations N N N X T N O
Surface Breaking Laminations N N N X T N O
Hydrogen Blisters N N N X T N O
Laminations interacting with Deformations N N N X T N O
Arc burn N X N O N N O
Hard spot N N Gouges or grooves <12.5% nominal wall
thickness X X Buckling
O X N O Repair by cutout, pumpkin, Type B sleeve, or call Asset
Integrity for assistance
N N N
N N N
SCC suspected Call Asset Integrity for assistance
Leaking mechanical (Dresser) coupling Repair by tightening, using housing (pumpkin), or cutout
Mechanical leaks (valves and fittings) Repair in accordance with manufacturer’s guidelines or cutout
and replace
2.15.2
2.15.3 THIS TABLE OUTLINES THE APPROVED/PREFERRED METHOD (X),

<<<PAGE 748>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 10 of 16
2.16 OPTIONAL (O), AND TEMPORARY ONSHORE OR PERMANENT OFFSHORE
(T) METHODS OF REPAIRING IMPERFECTIONS OR DEFECTS. THE
METHODS THAT ARE NOT PERMITTED (N) ARE ALSO INDICATED. THE
OPTIONAL METHODS LISTED DO NOT REPRESENT ALL OPTIONAL
METHODS BUT IDENTIFY NORMALLY ACCEPTED OPTIONS. A
TEMPORARY REPAIR MAY BE MADE USING ANY METHOD DEEMED
SUITABLE USING SOUND ENGINEERING JUDGMENT. FOR DETAILED
INFORMATION ON REPAIR METHODS, REFER TO PARAGRAPH 2.17 OF
THIS PROCEDURE.
GENERAL NOTES ON REPAIR METHODS
2.16.1 2.16.2 2.16.3 2.16.4 2.16.5 2.16.6 DEFECTS REPAIRED BY GRINDING AND/OR SANDING, INSTALLING A
TYPE “A” SLEEVE, TYPE “B” SLEEVE, COMPOSITE REINFORCED SLEEVE
OR REPLACING THE AFFECTED PIPE AS A CYLINDER ARE ALL
PERMANENT REPAIRS. BOLT-ON OR MECHANICAL REPAIR CLAMPS
USED ONSHORE ARE CONSIDERED TEMPORARY REPAIRS THEREFORE;
REPLACE OR UPGRADE THEM WITH A PERMANENT REPAIR AS SOON AS
FEASIBLE OR WITH APPROVAL OF THE MANAGER, ASSET INTEGRITY, A
PROPERLY WELDED MECHANICAL OR BOLT-ON CLAMP IS CONSIDERED
A PERMANENT REPAIR FOR ONSHORE APPLICATIONS.
WHEN PRACTICAL, REPAIR DEFECTS BY SLEEVING. THERE ARE TWO
NORMALLY USED METHODS OF SLEEVING NON-LEAKING DEFECTS:
TYPE “A” AND TYPE “B” SLEEVE. BASE THE DECISION TO USE ONE TYPE
OVER THE OTHER ON THE SPECIFIC FIELD CIRCUMSTANCES AND TABLE
1
TYPE “A” FULL ENCIRCLEMENT WELDED STEEL SLEEVE CAN BE USED
TO REPAIR DEFECTS. THIS SLEEVE CANNOT BE USED ON LEAKING
DEFECTS OR TO PROVIDE LONGITUDINAL REINFORCEMENT TO THE
PIPELINE. REFER TO PARAGRAPH 2.17.3 FOR DETAILED INFORMATION
ABOUT INSTALLING TYPE “A” SLEEVES.
REPAIR LEAKING DEFECTS BY SLEEVING WITH A TYPE “B” SLEEVE WHEN
PRACTICAL. TYPE “B” SLEEVES REQUIRE WELDING ON THE
PRESSURIZED PIPE AND SHOULD NOT BE USED TO REPAIR OTHER
DEFECTS EXCEPT UNDER SPECIAL CIRCUMSTANCES. REFER TO
PARAGRAPH 2.17.4 FOR DETAILED INFORMATION ABOUT INSTALLING
TYPE “B” SLEEVES.
REPAIR OF LEAKING DEFECTS CAUSED BY ISOLATED CORROSION MAY
BE MADE BY INSTALLING A BOLT-ON LEAK CLAMP (ON-SHORE
TEMPORARY) OR A TYPE “B” SLEEVE.
USE COMPOSITE REINFORCEMENT SLEEVES TO REPAIR DEFECTS THAT
HAVE BEEN GROUND OUT, WERE CAUSED BY CORROSION OR DENTS
ON LOW STRESS PIPELINES WITHOUT SCRATCHES.
2.16.7 CAUTION: DO NOT USE COMPOSITE SLEEVES TO
REPAIR LEAKING DEFECTS OR CRACKING. REFER TO PARAGRAPH
2.17.5 FOR DETAILS.
2.16.8 REPAIR SUBMERGED PIPELINES IN NAVIGABLE WATERS CONTAINING
LEAKING DEFECTS BY MECHANICALLY APPLYING A FULL
ENCIRCLEMENT SLEEVE OR BY INSTALLING A NEW SECTION OF PRE-
TESTED PIPE.

<<<PAGE 749>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 11 of 16
2.16.9 REPAIR ANY DEFECT BY REMOVING THE DEFECTIVE COMPONENT
(VALVE, FITTING, ETC.) OR A CYLINDER OF PIPE CONTAINING THE
DEFECT AND INSTALLING A NEW COMPONENT OR CYLINDER OF PIPE.
2.16.10 PATCHES ARE NOT AN APPROVED REPAIR METHOD.
2.17 REPAIR PROCEDURES
2.17.1 REPAIR DEFECT BY GRINDING AND/OR SANDING, AS FOLLOWS
2.17.2 CAUTION: PRIOR TO PERFORMING ANY
GRINDING OR SANDING ON A LIVE LINE, EVALUATE THE DEFECT TO BE
REPAIRED. IF IT IS ESTIMATED THAT THE DEFECT IS POTENTIALLY
GREATER THAN 10% OF THE NOMINAL WALL THICKNESS, DO NOT
PERFORM ANY GRINDING OR SANDING OPERATIONS AND
IMMEDIATELY REFER TABLE 1 TO DETERMINE THE APPROPRIATE
REPAIR METHOD, SUCH AS INSTALLING A SLEEVE.
2.17.3 2.17.2.1 2.17.2.2 2.17.2.3 2.17.2.4 2.17.2.5 REMOVE THE DEFECT BY GRINDING AND/OR SANDING.
AFTER GRINDING OR SANDING, IF THE REMAINING WALL
THICKNESS IS LESS THAN 88% OF NOMINAL, REEVALUATE
THE INTEGRITY OF THE PIPELINE AND GRIND AREA USING
RSTRENG (REFER TO RSTRENG ANALYSIS OF CORROSION)
OR KAPA AND INSTALL A REINFORCING SLEEVE IF
NECESSARY. THE TRANSITION FROM THE AREA WHERE THE
DEFECT WAS REMOVED TO THE SURROUNDING
UNDISTURBED MATERIAL SHALL BE SMOOTH.
NONDESTRUCTIVELY INSPECT ALL AREAS WHERE DEFECTS
HAVE BEEN REMOVED BY GRINDING, USING MAGNETIC
PARTICLE OR DYE PENETRANT INSPECTION METHOD TO
ENSURE THE ENTIRE DEFECT HAS BEEN REMOVED. DURING
NDT, PAY PARTICULAR ATTENTION TO ANY INDICATIONS OF
CRACKING.
IF THE REMAINING WALL THICKNESS PASSES RSTRENG
CALCULATIONS, THE AREA DOES NOT REQUIRE SLEEVING
AND MAY BE PROPERLY CLEANED AND RECOATED.
IF THE REMAINING WALL THICKNESS IS LESS THAN
REQUIRED BY RSTRENG CALCULATION, PERFORM A REPAIR.
THE AREA DOES NOT REQUIRE BLEND GRINDING OR
SANDING WHEN THE DEFECT REQUIRES TYPE “A” OR TYPE
“B” SLEEVING.
REPAIR DEFECT USING A TYPE “A” SLEEVE (NON-PRESSURE
CONTAINING), AS FOLLOWS
2.17.3.1 PREPARE THE PIPELINE TO INSTALL THE TYPE “A” SLEEVE BY
REMOVING ALL OF THE COATING AND THOROUGHLY POWER
BRUSH OR BLAST CLEANS THE PIPE SURFACE IN THE AREA
THE SLEEVE WILL COVER.
2.17.3.2 FABRICATE OR OBTAIN A SLEEVE WITH THE SAME OR
GREATER OVERALL STRENGTH (WALL THICKNESS X YIELD
STRENGTH) AS THE PIPELINE BEING REPAIRED. REFER TO
SPECIFICATION 101—MAINTENANCE WELDING (EXCLUDING

<<<PAGE 750>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 12 of 16
2.17.3.3 ETHYLENE PIPELINES) ATTACHMENT A FOR DETAILS.
USE A SLEEVE THAT IS AT LEAST 4 INCHES IN LENGTH.
ENSURE THAT THE SLEEVE COVERS THE DEFECT(S) PLUS A
MINIMUM OF 2" PAST THE DEFECT(S) ON EACH END. REFER
TO SPECIFICATION 101—MAINTENANCE WELDING
2.17.4 2.17.3.4 2.17.3.5 2.17.3.6 2.17.3.7 2.17.3.8 (EXCLUDING ETHYLENE PIPELINES) FOR DESIGN DETAILS.
CLEAN THE INSIDE AND OUTSIDE SURFACE OF THE SLEEVE
BY THOROUGHLY POWER BRUSHING OR ABRASIVE
BLASTING.
APPLY A HARDENABLE FILLER MATERIAL SUCH AS AN EPOXY
IN DENTS, CORROSION PITS, AND/OR ADJACENT TO THE
LONG SEAM OF THE PIPE TO COMPLETELY FILL VOID AREAS
BEFORE INSTALLING THE SLEEVE.
APPLY SLEEVE WITH BACKING STRIP TO PIPELINE ENSURING
IT IS TIGHT. THE EFFECTIVENESS OF THE SLEEVE DEPENDS
ON ITS SNUGNESS AROUND THE PIPE.
APPLY THE SLEEVE TO PIPELINE ENSURING A SNUG FIT.
WELD PER SPECIFICATION 101—MAINTENANCE WELDING
(EXCLUDING ETHYLENE PIPELINES) AND THE SPECIFIED
WELDING PROCEDURE.
SEAL THE ENDS OF THE STEEL SLEEVE WITH A MASTIC BAR,
THEN A SHRINK SLEEVE AND COAT THE EXTERIOR OF THE
SLEEVE FOLLOWING COATINGS—SELECTION, APPLICATIONS
AND MAINTENANCE.
REPAIR DEFECT USING A TYPE “B” SLEEVE (PRESSURE CONTAINING), AS
FOLLOWS:
2.17.4.1 2.17.4.2 PREPARE THE PIPELINE TO INSTALL THE TYPE “B” SLEEVE BY
REMOVING ALL THE COATING AND THOROUGHLY POWER
BRUSH OR BLAST CLEAN THE PIPE SURFACE IN THE AREA
THE SLEEVE WILL COVER.
FABRICATE OR OBTAIN A SLEEVE WITH THE SAME OR
GREATER OVERALL STRENGTH (WALL THICKNESS X YIELD
STRENGTH) AS THE PIPELINE BEING REPAIRED. REFER TO
SPECIFICATION 101—MAINTENANCE WELDING ATTACHMENT
2.17.4.3 A FOR DETAILS.
USE A SLEEVE THAT IS AT LEAST FOUR INCHES IN LENGTH.
ENSURE THAT THE SLEEVE COVERS THE DEFECT(S) PLUS A
MINIMUM OF 2" PAST THE DEFECT ON EACH END. TYPE B
SLEEVES MAY BE USED FOR LEAKING OR NON-LEAKING
DEFECTS INCLUDING CIRCUMFERENTIALLY ORIENTED
DEFECTS. WHEN MULTIPLE SLEEVES ARE USED, A TYPE B
SLEEVE SHOULD NOT BE TERMINATED WITHIN ONE-HALF
PIPE DIAMETER OR 4 INCHES FROM A GIRTH WELD
WHICHEVER IS GREATER. THE DISTANCE BETWEEN
SLEEVES SHOULD BE AT LEAST ONE PIPE DIAMETER.
SEPARATED SLEEVES MAY BE SPACED LESS THAN ONE PIPE
DIAMETER APART IF JOINED BY A WELDED BRIDGING SLEEVE
OR MADE CONTINUOUS BY BUTT-WELDING THEM TOGETHER.

<<<PAGE 751>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 13 of 16
2.17.4.4 2.17.4.5 2.17.4.6 2.17.4.7 2.17.4.8 WHEN INSTALLED AT A NON-LEAKING DEFECT, A TYPE B
SLEEVE MAY BE INSTALLED IN A MANNER THAT REDUCES
THE HOOP STRESS IN THE CARRIER PIPE. METHODS FOR
ACCOMPLISHING THIS INCLUDE LOWERING THE PRESSURE
BEFORE THE SLEEVE IS INSTALLED, APPLYING EXTERNAL
MECHANICAL FORCE, OR PREHEATING THE SLEEVE TO
FACILITATE A “SHRINK-FIT.”
INSPECT THE FULL CIRCUMFERENCE OF THE PIPELINE
WHERE THE SLEEVE ENDS ARE TO BE WELDED TO THE
PIPELINE USING AN ULTRASONIC THICKNESS INSTRUMENT
AND/OR A MAGNETIC PARTICLE INSPECTION TECHNIQUE.
ENSURE THERE ARE NO SURFACE CRACKS, LAMINATIONS OR
THIN WALL THAT COULD AFFECT THE INTEGRITY OF THE
WELD OR SLEEVE.
CLEAN THE INSIDE AND OUTSIDE SURFACE OF THE SLEEVE
BY THOROUGHLY POWER BRUSHING OR ABRASIVE
BLASTING.
APPLY A HARDENABLE FILLER MATERIAL SUCH AS AN EPOXY
IN DENTS, CORROSION PITS, AND/OR ADJACENT TO THE
LONG SEAM OF THE PIPE TO COMPLETELY FILL VOID AREAS
BEFORE INSTALLING THE SLEEVE.
APPLY THE SLEEVE WITH BACKING STRIP TO PIPELINE
ENSURING A SNUG FIT. WELD PER SPECIFICATION 101—
MAINTENANCE WELDING (EXCLUDING ETHYLENE PIPELINES)
AND THE SPECIFIED WELDING PROCEDURE.
NONDESTRUCTIVELY TEST THE COMPLETED LONGITUDINAL
GROOVE WELD AND CIRCUMFERENTIAL FILLET WELDS IN
COMPLIANCE WITH SPECIFICATION 101—MAINTENANCE
2.17.4.9 WELDING (EXCLUDING ETHYLENE PIPELINES).
COAT THE EXTERIOR OF THE SLEEVE WITH PRIMER AND RD-6
TAPECOAT FOLLOWING COATINGS—SELECTION,
APPLICATIONS AND MAINTENANCE.
2.17.5 REPAIR DEFECT USING AN APPROVED COMPOSITE REINFORCED
SLEEVE
2.17.5.1 2.17.5.2 2.17.5.3 2.17.5.4 2.17.5.5 DO NOT USE A COMPOSITE SLEEVE TO REPAIR LEAKS,
CRACKS, OR WELD DEFECTS. REFER TO TABLE 1 FOR
SPECIFICS.
A QUALIFIED PERSON(S) MUST INSTALL COMPOSITE
SLEEVES.
PREPARE THE PIPELINE TO INSTALL THE COMPOSITE
REINFORCED SLEEVE(S) IN ACCORDANCE WITH THE
MANUFACTURER'S SPECIFICATIONS. USUALLY ABRASIVE
BLASTING IS REQUIRED.
INSTALL THE COMPOSITE SLEEVE PER MANUFACTURER’S
SPECIFIC REQUIREMENTS AND SPECIFICATIONS.
INSTALL METALLIC (CARON STEEL) BANDING AT ONE-FOOT
INTERVALS ON THE SLEEVE FOR THE PURPOSE OF ILI TOOL

<<<PAGE 752>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 14 of 16
2.17.5.6 IDENTIFICATION.
COAT THE EXTERIOR OF THE SLEEVE WITH PRIMER AND RD-6
TAPECOAT FOLLOWING COATINGS—SELECTION,
APPLICATIONS AND MAINTENANCE. AS AN ALTERNATIVE, A
2.17.6 “HEAT SHRINK SLEEVE” THAT FULLY ENCOMPASSES THE
LENGTH AND CIRCUMFERENCE OF THE COMPOSITE SLEEVE
MAY ALSO BE USED, IF THE ENDS OF THE COMPOSITE
SLEEVE ARE APPROPRIATELY FILLED IN ORDER TO PREVENT
ANY AIR GAPS. THE HEAT SHRINK SLEEVE MUST EXTEND
PAST THE ENDS OF THE COMPOSITE SLEEVE BY AT LEAST 4
INCHES FOR PROPER ENCAPSULATION/COATING OF THE
COMPOSITE SLEEVE AND COVER ADJACENT BARE STEEL
AREAS, WHICH MAY RESULT IN THE USE OF MULTIPLE HEAT
SHRINK SLEEVES.
REPAIR DEFECTS USING A BOLT-ON MECHANICAL CLAMP
2.17.6.1 INSTALL PROPERLY DESIGNED FULL ENCIRCLEMENT
MECHANICAL CLAMP BY COVERING THE DEFECT.
2.17.6.2 FOLLOW ALL MANUFACTURERS’ INSTRUCTIONS WHEN
INSTALLING MECHANICAL CLAMP.
2.17.6.3 REPLACE MECHANICAL CLAMPS WITH A PERMANENT REPAIR
AS SOON AS FEASIBLE. PROPERLY WELDED MECHANICAL
CLAMPS ARE CONSIDERED PERMANENT REPAIRS FOR
ONSHORE APPLICATIONS, UPON APPROVAL BY THE
MANAGER OF ASSET INTEGRITY.
2.17.6.4 WELD + ENDS OR SIMILAR COMPRESSION TYPE FITTINGS
SHALL NOT BE USED TO JOIN PIPE TOGETHER WITHOUT A
WRITTEN JOB SPECIFIC INSTALLATION PROCEDURE
INCLUDING REVIEWING AND FOLLOWING MANUFACTURES
PROCEDURES TO ENSURE CORRECT INSTALLATION AND
OTHER NECESSARY SAFETY MEASURES FOR SAFE AND
RELIABLE OPERATION OF THE PIPELINE SYSTEM. CALL
MANAGER OF ASSET INTEGRITY FOR FURTHER GUIDANCE, IF
NECESSARY.
2.17.6.5 COAT THE EXTERIOR OF THE SLEEVE WITH PRIMER AND RD-6
TAPECOAT FOLLOWING COATINGS—SELECTION,
APPLICATIONS AND MAINTENANCE.
2.17.7 REPAIR DEFECTS BY CUTTING OUT A CYLINDER OF PIPE AND
REPLACING IT WITH NEW PIPE
2.17.7.1 2.17.7.2 2.17.7.3 2.17.7.4 PRIOR TO CUTTING OR WELDING CHECK FOR LEL’S WITH HAZ
GAS DETECTOR
REMOVE PIPE OR FITTING CONTAINING THE DEFECT AS A
CYLINDER.
ENSURE ANY REMOVED SECTION HAS HAD ADEQUATE TIME
FOR VENTILATION PRIOR TO CUTTING AND TRANSPORTING.
WHENEVER POSSIBLE, ENSURE THAT THE REPLACEMENT
PIPE HAS A LENGTH OF NOT LESS THAN ONE-HALF THE PIPE
DIAMETER OR NOT LESS THAN 3 INCHES WHICHEVER IS

<<<PAGE 753>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 15 of 16
2.17.7.5 2.17.7.6 GREATER.
THE REPLACEMENT PIPE, FITTING, OR VALVE SHALL HAVE A
GREATER THAN OR EQUAL DESIGN PRESSURE AS THE
EXISTING PIPE OR FITTING AND SHALL BE PRE-TESTED.
PIPE ENDS SHOULD BE CHECKED FOR MAGNETISM PRIOR TO
WELDING. IF WELDING QUALITY BECOMES AN ISSUE, STEPS
TO REDUCE OR TEMPORARILY ELIMINATE THE MAGNETIC
FIELD ON THE PIPE ENDS SHOULD BE TAKEN.
2.17.8 NOTE: PRIOR TO INSTALLING
PRETESTED PIPE, ENSURE THE APPROPRIATE RECORDS
(I.E., MTRS, HYDROSTATIC TEST RECORDS) HAVE BEEN
LOCATED, THOROUGHLY REVIEWED, AND VERIFIED
ACCURATE.
2.17.8.1 2.17.8.2 2.17.8.3 ENSURE LEL’S HAVE BEEN REMOVED FROM WORK AREA
PRIOR TO INSTALLING NEW PIPE
INSTALL THE REPLACEMENT MATERIAL IN ACCORDANCE
WITH SPECIFICATION 101, MAINTENANCE WELDING
(EXCLUDING ETHYLENE PIPELINES).
COAT THE EXTERIOR OF THE NEW AND ADJACENT PIPE (AS
NEEDED) WITH PRIMER AND RD-6 TAPECOAT FOLLOWING
COATINGS—SELECTION, APPLICATIONS AND MAINTENANCE.
2.17.9 REPAIR DEFECTS BY RECOAT
2.17.9.1 2.17.9.2 PREPARE THE PIPELINE TO INSTALL COATING BY REMOVING
ALL OF THE EXISTING COATING AND THOROUGHLY POWER
BRUSH OR BLAST CLEAN THE PIPE SURFACE IN THE AREA OF
THE RECOAT.
COAT THE EXTERIOR OF THE SLEEVE WITH PRIMER AND RD-6
TAPECOAT FOLLOWING COATINGS—SELECTION,
APPLICATIONS AND MAINTENANCE.
2.18 2.17.9.3 AFTER APPLICATION OF THE RD-6 COATING, INSTALL
METALLIC BANDING (CARBON STEEL) FOUR INCHES FROM
EACH END OF THE RECOAT AREA AND COAT THE METALLIC
BANDS WITH RD-6 COATING.
DOCUMENT ALL REPAIRS ON THE PIPELINE MAINTENANCE REPORT AND
ENSURE A COPY IS SENT TO THE RECORDS COORDINATOR IN TULSA.
3.0 DEFINITIONS
3.1 3.2 3.3 3.4 Arc Burn: Localized points of surface melting caused by arcing between electrode or
ground and pipe surface.
Bolt-On Fitting: Any onshore or offshore attachment to a pipeline that is attached via
bolts.
Composite Reinforcement Sleeve: A nonmetallic sleeve used to repair some nonleaking
pipeline defects.
Dent: An area of the pipe where the local curvature is no longer part of a circular arc
having the same radius as the pipe. The local indentation shall be considered a dent if

<<<PAGE 754>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 16 of 16
the measured distance between the lowest point of the indentation and a prolongation of
the original contour of the pipe exceeds the value equivalent to 2% of the pipe’s diameter.
3.5 Hard Spot: Localized spot where the hardness of the material is greater than
surrounding material.
3.6 MIC: Microbiologically induced corrosion.
3.7 RSTRENG: A modified corrosion assessment criterion to predict a minimum failure
pressure based on detailed corrosion depth and length measurements.
3.8 3.9 Stress Corrosion Cracking (SCC): Cracking which results from stress induced corrosion.
Selective Seam Corrosion (SSC): Localized corrosion located along the
bond line of low-frequency electric resistance welding (LR-ERW) and electric
flash welding (EFW) piping, that leads to the development of a wedge
shaped groove that is often filled with corrosion products.
3.10 Type A Sleeve: A band of steel that encircles the pipeline and is not welded to the
pipeline.
3.11 Type B Sleeve: A band of steel that encircles the pipeline and is welded to a pipeline at
the ends forming a pressure vessel and is normally used for a leaking defect but may be
used for non-leaking defects under special circumstances.
3.12 Wedding Band: A short (Usually 6 to 12 inches in length) Type B Sleeve that
encompasses a joint weld.
3.13 Weld Defect: A weld imperfection located in a seam or girth weld.

<<<PAGE 755>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 17 of 16
System Integrity Plan Change Log
Date Change
Location
Change
By
2.2 Clyde Clausen Mike Pearson 2.12 Clyde Clausen Mike Pearson 2.3 Clyde Clausen Mike Pearson 07/23/02
Various Clyde Clausen Mike Pearson Various Clyde Clausen Mike Pearson 2.6.3 Clyde Clausen Mike Pearson 08/08/02 2.4.3 & 2.13.1 Clyde Clausen Mike Pearson 11/21/03 All Clyde Clausen Mike Pearson 12/22/03 1.0 Clyde Clausen Mike Pearson 12/22/03 2.1.2 Clyde Clausen Mike Pearson 12/22/03 2.1.3 Clyde Clausen Mike Pearson 12/22/03 2.1.4 Clyde Clausen Mike Pearson 12/22/03 2.1.5 Clyde Clausen Mike Pearson 12/22/03 2.2.3 Clyde Clausen Mike Pearson 12/22/03 2.6 Clyde Clausen Mike Pearson 12/22/03 2.12 Clyde Clausen Mike Pearson 12/22/03 2.14.7 Clyde Clausen Mike Pearson 12/22/03 2.15.4.5 Clyde Clausen Mike Pearson 12/22/03 2.15.6.4 Clyde Clausen Mike Pearson 11/21/04 All Clyde Clausen Mike Pearson 9/9/04 2.7 Clyde Clausen Mike Pearson 9/9/04 2.14.3.2 Clyde Clausen Mike Pearson 9/9/04 2.14.3.3 Clyde Clausen Mike Pearson 9/9/04 2.14.6.2 Clyde Clausen Mike Pearson 9/9/04 2.14.6.3 Clyde Clausen Mike Pearson 9/9/04 2.14.6.4 Clyde Clausen Mike Pearson Brief Description of Change
Detailed how to perform a visual assessment.
Added a repair method to the table for
Natural Gas.
Provided details on reference sections.
Replaced Paragraph 6.12 reference with 2.13.
Paralleled repair language with the Welding manual
to alleviate conflicts and inconsistencies.
Added section for dent repair clarification.
Added repair method deviation approval process.
Annual Review
Deleted Purpose of this procedure is to establish,
inserted analysis and repair of
Deleted Pump piping and Tanks
Deleted DOT Part 195 governs the repairs Williams
utilizes for certain pipeline repairs. These regulatory
parts and subparts may be referenced within this
document.
Added OQ qualification paragraph
Added live line welding paragraph
Deleted paragraph, and re‐worded
Deleted Caution Note
Become 2.11. Rewrote repair options for
buckling/ripples
Become 2.13.7. Deleted offshore pipeline
Become 2.14.4.5. Added (Carbon Steel)
Become 2.14.6.4. Modified Note to read ensure the
appropriate records (i.e. MTRs, Hydrostatic Test
Records) have been located, thoroughly reviewed,
and verified accurate.
Annual Review
Modified Paragraph within Note
Deleted Ethylene Pipelines
Modified Paragraph for changes due to new
regulated requirements
Modified Paragraph for changes due to new
regulated requirements
Modified Paragraph
Added new Paragraph

<<<PAGE 756>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE Asset Integrity 01/01/12 11/20/05 All Clyde Clausen Mike Pearson 01/01/06 4.4 Clyde Clausen Mike Pearson 01/01/06 2.6.2 Clyde Clausen Mike Pearson 01/01/06 2.12.1 Clyde Clausen Mike Pearson 01/01/06 References Mike Pearson 1/26/06 2.14.6.3 Clyde Clausen Mike Pearson 1/26/06 2.14.6.5 Clyde Clausen Mike Pearson 2/15/06 2.1.5 Clyde Clausen Mike Pearson 11/16/06 All Clyde Clausen Mike Pearson 11/16/06 2.3.3.7 Clyde Clausen Mike Pearson 11/16/06 2.9.3 Clyde Clausen Mike Pearson 11/16/06 2.10 Clyde Clausen Mike Pearson 11/16/06 4.9 Clyde Clausen Mike Pearson 1/10/07 2.2.4 Clyde Clausen Mike Pearson 1/10/07 2.4.1 Clyde Clausen Mike Pearson 1/10/07 2.2.3 Clyde Clausen Mike Pearson 5/8/07 2.2.4 Clyde Clausen Mike Pearson 5/8/07 2.1.1 Clyde Clausen Mike Pearson 6/28/07 2.2.1 Clyde Clausen Mike Pearson 6/28/07 2.2.2 Clyde Clausen Mike Pearson 6/28/07 2.5.3 Clyde Clausen Mike Pearson 6/28/07 2.8.3 Clyde Clausen Mike Pearson 11/16/07 All Clyde Clausen Mike Pearson 4/01/08 2.2.1 Dennis Vasicek Clyde Clausen 4/01/08 2.2.2 Dennis Vasicek Clyde Clausen 4/01/08 2.2.3 Dennis Vasicek Clyde Clausen 7.01–ADM–001
Revision: 9 Page 18 of 16
Annual Review
Added definition
Minor modifications
Incorporated HCA Repair Criteria
removed
Minor Modification to Paragraph‐ (Added Valve)
Minor Modification to Paragraph‐ (Change
Specification 100 to Specification 101)
Removed Pressure reduction requirements from
Paragraph.
Annual Review
Added 2.3.3.7
Added Paragraph
Added 2.10
Added Definition
Added precaution for cleaning pipe.
Added precaution for cleaning pipe to existing
paragraph.
Added Paragraph to comply with 195.422.
Added Paragraph to comply with 195.422.
Removed reference to MPC
Added Paragraph
Added Paragraph for pressure reductions for defects
that can’t be repaired in 8 hours.
Added Paragraph for non‐destructive testing repairs
that have been removed by grinding/sanding.
Added reference to paragraph
Conducted Annual Review
Added: All exposed bell and spigot girth welds shall
be reinforced by means of sleeving
Added: If needed (when pipe is not resting on the
ground) the pipe should be adequately supported
prior to backfilling. Consideration should be given to
using dirt plugs or sandbags at spacing intervals not
to exceed 20 feet particularly in areas where
additional weight has been applied by installation of
sleeving
Added: All exposed girth welds (including bell and
spigot joints) shall be supported (supports to be
placed on each side of the girth weld) via sandbags
or equivalent settlement resistant supports prior to
backfilling.

<<<PAGE 757>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE Asset Integrity 01/01/12 11/14/08 All Dennis Vasicek Clyde Clausen 12/18/08 2.1.3 Dennis Vasicek Clyde Clausen 12/18/08 2.2.5 Dennis Vasicek Clyde Clausen 12/18/08 2.3.1 Dennis Vasicek Clyde Clausen 12/18/08 2.3.4.10 Dennis Vasicek Clyde Clausen 12/18/08 2.13 Dennis Vasicek Clyde Clausen 12/18/08 2.16.3.8 Dennis Vasicek Clyde Clausen 8/21/09 All Clyde Clausen Doug Chabino 8/21/09 2.2.3 Clyde Clausen Doug Chabino 8/21/09 2.2.6 Clyde Clausen Doug Chabino 11/30/09 All Clyde Clausen Doug Chabino 11/30/09 2.16.5.4 Clyde Clausen Doug Chabino 11/30/09 2.16.6.1 Clyde Clausen Doug Chabino 11/30/09 2.16.6.3 Clyde Clausen Doug Chabino 11/30/09 2.16.6.7 Clyde Clausen Doug Chabino 9/3/10 2.1.2, 2.4.2,
2.16.1.1
Clyde Clausen Doug Chabino 9/3/10 2.9.3 Clyde Clausen Doug Chabino 9/3/10 2.14.1 Clyde Clausen Doug Chabino 9/3/10 All Clyde Clausen Doug Chabino 9/1/11 All Clyde Clausen Doug Chabino 9/1/11 2.14.1 Clyde Clausen Doug Chabino 12/31/11 All 6/12/12 2.14 Table Clyde Clausen Doug Chabino 7.01–ADM–001
Revision: 9 Page 19 of 16
Conducted Annual Review
Minor modification (installation of repairs, i.e.
composite/clamps) to paragraph
Minor Modification to paragraph
Added paragraph to photograph repair site prior to
removing coating
Added Section for Cracks
Added Section for Cracks
Minor Modifications to paragraph
Conducted Annual Review, See modifications below
Added not to exceed 5’ to paragraph
Added requirement to NDE pipeline defects that are
not repaired by means of sleeving or pipe
replacement
Removed reference to contact Pipeline Integrity and
added Asset Integrity
Added Paragraph
Added Paragraph
Added Paragraph
Added Paragraph
Added utilization of KAPA for conducting pressure
assessments
Added new paragraph to refer to the ORA process
manual decision tree if SCC is discovered on assets
covered by the mitigation plan
Added Immediate repair criteria for Assets covered
by the mitigation plan to repair table
Conducted Annual Review
Conducted Annual Review
Added Lamination Repair Options to Table
2012 Annual Review complete
Modified Lamination Repair Table

<<<PAGE 758>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 1 of 4
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity by establishing consistent processes
for integrity testing.
2.0 DESCRIPTION
2.1 The Company utilizes pressure testing, in‐line inspection (ILI), or a combination thereof, to assess
and validate the physical integrity of its pipeline system. In addition to standardized pipeline
construction and maintenance practices, the Company adheres to a comprehensive Integrity
Management Program that incorporates the use of appropriate integrity testing technologies
and rehabilitation practices in order to assist in identifying, understanding and controlling
pipeline risk and integrity threats.
2.2 A priority rating system based on relative risk is established to select pipeline segments for
integrity testing schedules. The frequency of reassessments will be determined by the processes
established within the Integrity Management Plan.
3.0 STANDARDS
3.1 The Project Manager shall:
3.1.1 Consult with the Pipeline or Facility Risk Engineer, as appropriate for type of asset, to
ensure review of applicable asset integrity factors is completed prior to testing.
3.1.2 Coordinate the execution of pressure testing projects in accordance with the Pressure
Testing Procedure.
3.1.3 Complete the appropriate Hydrostatic Test Documentation (Hydrostatic Test
Documentation for Liquids) and remit with the required attachments to the Records
3.1.4 Coordinator within thirty days of the pressure test.
Coordinate the execution of ILI projects in accordance with the In‐Line Inspection
Procedure.
3.2 The Records Coordinator shall:
3.3 3.4 3.2.1 Review pressure test documentation for thoroughness and adequacy, and retain in
Asset Integrity file repository for useful life of the facillity.
3.2.2 Notify the Pipeline Surge Engineer following receipt of pressure test records.
3.2.3 Input the new pressure test data and the new calculated Maximum Operating Pressure
(MOP) information into the Hydrostatic Test Database within 60 days following receipt
of the pressure test records.
The Manager of Asset Integrity Engineering shall:
3.3.1 Coordinate changes to system pressure settings with Operations Control and/or
Operations Manager as applicable.
The Pipeline Integrity Supervisor shall:
3.4.1 Determine the effect(s) on the MOP of the corresponding asset(s) following notice of
receipt of pressure test documentation.
3.4.2 Coordinate the execution and documentation of integrity testing and rehabilitation

<<<PAGE 759>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 2 of 4
3.4.3 3.4.4 plans of existing assets.
Notify the Manager of Asset Integrity Engineering of any required adjustments to
system operating pressures due to integrity testing results.
Maintain and annually review the In‐Line Inspection Procedure and Pressure Testing
Procedure for use on Company operated assets.
3.5 The Pipeline Integrity Engineer shall:
3.5.1 Immediately evaluate reports from the ILI vendor and generate a Dig List in accordance
with In‐Line Inspection Procedure.
3.5.2 Notify the Pipeline Integrity Coordinator that the Dig List has been developed in order to
initiate project execution of feature investigations and rehabilitation, as required.

<<<PAGE 760>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 3 of 4
System Integrity Plan Change Log
Date Change
Location
Change By Approved By Brief Description of Change
10/16/03 All Clyde Clausen Michael Pearson 10/23/03 2.1 & 2.2 Clyde Clausen Michael Pearson 10/23/03 3.2 Clyde Clausen Michael Pearson 10/23/03 3.4.2 Clyde Clausen Michael Pearson 10/23/03 3.5 Clyde Clausen Michael Pearson 10/23/03 3.7.2 Clyde Clausen Michael Pearson 9/29/04 All Mike Pearson Michael Pearson 9/29/04 3.13 Clyde Clausen Michael Pearson 9/29/04 3.3.1 Clyde Clausen Michael Pearson 9/29/04 3.4.3 Clyde Clausen Michael Pearson 10/16/05 All Clyde Clausen Michael Pearson 10/16/06 All Clyde Clausen Michael Pearson 10/16/06 Entire
Document
Clyde Clausen Michael Pearson 10/16/06 3.1.2 Clyde Clausen Michael Pearson 10/16/06 3.1.4 Clyde Clausen Michael Pearson 10/16/06 3.2.1 Clyde Clausen Michael Pearson 10/16/06 3.2.2 Clyde Clausen Michael Pearson 10/16/06 3.3.1 Clyde Clausen Michael Pearson 10/16/06 3.3.2 Clyde Clausen Michael Pearson 10/16/06
Clyde Clausen Michael Pearson 3.3.2
10/16/06 3.4.4 Clyde Clausen Michael Pearson 10/16/06
Clyde Clausen Michael Pearson 3.5
10/16/06 3.6 Clyde Clausen Michael Pearson 09/11/07 All Clyde Clausen Michael Pearson 9/11/07 3.2.2
Michael Pearson Conducted 2003 Annual Review, (See Change Log)
Minor modifications to Paragraph
Inserted responsibilities of Pipeline Integrity
Coordinator.
Added new responsibility to Pipeline Integrity or
Facility Supervisor.
Added Operations Control Manager responsibilities
Added new responsibility to Pipeline Integrity
Engineer.
Conducted 2004 Annual Review, (See Change Log)
Changed 2 weeks to thirty days
Added responsibility to Asset Integrity Manager
Added new responsibility to Pipeline Integrity or
Facility Supervisor.
Conducted 2005 Annual Review‐ (No Changes)
Conducted 2006 Annual Review‐ (See Change Log)
Revised job titles to reflect recent organizational
changes.
Minor Modification to Paragraph
Minor Modification to Paragraph
Minor Modification to Paragraph
Minor Modification to Paragraph
Deleted Paragraph
Moves up and becomes 3.3.1
Moved responsibility under Pipeline Integrity/ Risk
Engineering Supervisor: Determine the effect(s) on
the MOP of the corresponding asset(s) following
notice of receipt of pressure test documentation
Minor Modification to Paragraph
Deleted Operations Control Manager
Requirements as it is covered within 7.07
Operating Pressures.
Deleted Asset Integrity Analyst Responsibilities
Conducted 2007 Annual ,(See Change Log)
Deleted Risk Engineer and Inserted Pipeline Surge
Engineer. Deleted two weeks.

<<<PAGE 761>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 4 of 4
9/11/07 3.3 Clyde Clausen Michael Pearson 9/11/07 3.4 Clyde Clausen Michael Pearson 9/11.07 3.4.3 Clyde Clausen Michael Pearson 1/1/09 8/21/09 All Clyde Clausen Doug Chabino 8/21/09 3.1.3 Clyde Clausen Doug Chabino 8/21/09 Section 4 Clyde Clausen Doug Chabino 01/01/11 Deleted Director, Inserted Manager Asset Integrity
Engineering
Deleted Risk Engineering and made sole
responsibility of Pipeline Integrity Supervisor
Deleted Director and inserted Manager Asset
Integrity Engineering
2008 annual review complete – no changes
Conducted Annual Reivew
Removed Gas Reference
Removed Gas Link
Reviewed, no changes

<<<PAGE 762>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 1 of 13
1.0 OBJECTIVE
1.1 The purpose of this specification defines Company in-line inspection (ILI) requirements for ILI
service providers (Vendors).
2.0 SCOPE
2.1 This requirement specification shall be provided to ILI vendors when Company wishes to inspect
specific pipeline segments.
2.2 This specification covers:
2.2.1 Company responsibilities
2.2.2 Vendor responsibilities
2.2.3 Technical criteria for assessing metal loss indications using MFL ILI tools; crack-like,
metal loss, and seam weld indications using circumferential MLF ILI technology (i.e. TFI,
AFD, SWML) and USCD ILI tools; laminations and metal loss using ultrasonic wall
measurement (USWM) ILI tools, and geometry indications using EGP ILI tools.
2.3 This procedure incorporates API 1163, ILI Systems Qualification Standard, First Edition, August
2005; NACE Standard PR 0102-2002; and ANSI/ASNT ILI-PQ-2005 where applicable.
3.0 COMPANY RESPONSIBILITIES
3.1 3.2 3.3 3.4 3.5 Company will furnish alignment sheets (strip maps), GPS/Street atlas files, trap revision
drawings, pipeline data listing, and information pertaining to flow rates and product physical
properties to enable Vendor to match ILI tool capabilities to the provided data.
Company will complete and submit the Information Worksheet (Questionnaire) provided by the
Vendor. Company will provide sufficient data, such as EGP and/or profile gauge plate l reports,
etc., to allow Vendor to determine whether or not line modifications including launching and
receiving facilities are required to enable ILI tools to successfully navigate the pipeline.
Company may perform modifications, if required, to the pipeline to enable ILI tools to the
successfully navigate pipeline.
Company will clean the pipeline based on a review of prior cleaning records to ensure optimum
ILI results. Cleaning data will be reviewed with the Vendor to determine and agree on the
adequacy of the line cleanliness to achieve the performance specification.
Company will provide adequate lifting equipment at the launching and receiving traps to facilitate
the installation and removal of ILI tools.
Company will provide personnel to assist Vendor in inserting ILI tools into the launch trap,
removing the ILI tools from the receiving facility, and operating launcher and receiver facilities.
3.6 3.7 3.8 3.9 3.10 Company will provide a suitable area near the job site for equipment preparation, cleaning,
refurbishment, and field data processing.
Company will provide a suitable area (if available at receive location) to clean the ILI tools and
dispose of contaminated pig components, cleaning materials and pipeline debris extracted from
the pipeline as a result of the ILI tool run.
Company will attempt to operate pipeline facilities to maintain an adequate and steady flow rate
through pipeline during ILI run.
Company will supply reporting format for providing ILI results to Company.
Following field examination of pipeline features, Company will provide collected data of physical
measurements of reported features to Vendor.

<<<PAGE 763>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 2 of 13
4.0 VENDOR RESPONSIBILITIES
4.1 Performance Specification
4.1.1 Vendor shall provide a written performance specification that includes, but is not limited
to the following:
4.1.1.1 Optimum ILI tool travel velocity
4.1.1.2 ILI tool velocity range and description of impact on data resolution if ILI tool is
operated at various velocity levels outside of specified velocity range.
4.1.1.3 ILI tool length and weight
4.1.1.4 ILI tool maximum permissible bore restriction
4.1.1.5 ILI tool sensor type
4.1.1.6 Number of sensors
4.1.1.7 Sensor sample rate in terms of longitudinal distance of sensor travel between
samples
4.1.1.8 4.1.1.9 Office where data analysis will be performed
Method and approach to analysis and reporting of non-corrosion pipeline
features and specific pipeline features (mill related defects, ID reductions
indications, and pipeline sleeves or patches).
4.1.1.10 Detection and sizing thresholds
4.1.1.11 ILI tool tolerances and sizing accuracy (statement as to percent of time
identified tolerances are met) for:
4.1.1.11.1 Odometer in relation to feature location
4.1.1.12 4.1.1.11.2 Feature depth
4.1.1.11.3 Feature length
4.1.1.11.4 Feature orientation (i.e. circumferential position or o’clock
position)
Performance criterion (Probability of Identification) for the classification of
specific features including inside diameter (ID) and outside diameter (OD)
discrimination.
4.1.1.13 Acceptance limits on lost data considering axial length of lost data and/or
number of sensor(s) affected during the ILI and/or number of adjacent
sensors of lost data.
4.1.1.14 AGM placement specifications (maximum depth of line, distance from casing,
etc.).
4.1.1.15 ILI tool bend radius and wall thickness specification.

<<<PAGE 764>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 3 of 13
4.2 Field Activities
4.2.1 4.2.2 4.2.3 4.2.4 4.2.5 4.2.6 Vendor shall provide fully functioning ILI tools prepared for service and compatible with
the pipe specifications, pipeline operational characteristics, and agreed performance
specification.
4.2.1.1 4.2.1.2 4.2.1.3 Mainline block valves may have valve seat spaces that must be spanned by
ILI tool. Vendor shall confirm that ILI tools can successfully negotiate such
spans without incurring damage or impacting the quality of the final results.
Mainline check valves may or may not be pinned open during ILI run and the
ILI tools are expected to negotiate such check valves without incurring
damage or impacting the quality of the final results.
Tees may or may not be barred. ILI tools are expected to negotiate such
tees and any crosses without incurring damage or impacting the quality of
the final results.
Vendor shall notify Company of specific ILI tools to be used and shall supply ILI tools
that provide adequate battery life and storage capability to minimize number of ILI runs
required.
Vendor shall identify to Company when flow rate changes may affect the agreed
performance specification.
Vendor shall account for actual flow rates and make provisions for the ILI tools to
effectively inspect each section relative to the ILI tool battery and data storage
limitations.
Vendor shall supply an above ground marker system (AGM) to facilitate the location of
pipe features using Company’s established AGM locations.
Vendor shall provide a sufficient number (minimum of eight (8)) of properly functioning
AGM devices to provide benchmark reference on the pipeline. Company will provide
tracking personnel for the placement (at approximately 1.0 mile intervals) and retrieval of
devices. Vendor shall provide above ground reference number and odometer count for
each reference site.
4.2.7 Based on the technical drawings and other information provided to Vendor by Company,
Vendor shall advise Company if design and dimensions of pipeline, including launching
and receiving facilities, are suitable for ILI tool launching and receiving.
4.2.8 If required by Company, Vendor shall provide an EGP and/or a profile/gauge plate ILI
tool of such configuration to detect variations in pipeline geometry that may restrict
passage of the ILI tools or prevent complete ILI of the pipeline. EGP or profile/gauge
plate ILI tool shall be equipped with a detection system for tracking and locating
purposes. A minimum of two receivers shall be provided.
4.2.9 Vendor shall provide labor, supervision, inspection, per diem, materials, ILI tools,
vehicles, equipment, and equipment transportation as required. Vendor shall supply
technical support regarding care and handling of ILI tools during launch and receive
activities. Vendor shall provide certifications of supervisor and team members prior to
arriving on-site.
4.2.10 If required by Company, Vendor shall provide programming and calibration of the ILI
tools prior to ILI runs including checks of onboard computer hardware and software.
4.3 Data Analysis
4.3.1 Vendor shall provide Company with information within 24 hours of the removal of any
electronic ILI tool from the receiver trap as to whether the inspection tool functioned
correctly (anticipated memory usage/total distance) and logged the appropriate data. If
the ILI tool did not function correctly or if upon review the logged data is considered by

<<<PAGE 765>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 4 of 13
Company and Vendor to be unsatisfactory, both parties will schedule a rerun as soon as
reasonably possible, unless otherwise directed by Company.
4.3.2 Vendor shall make available on a twenty-four (24) hour per day basis and at no
additional cost to Company, appropriate home office based personnel certified to level III
in analysis to support the Company while the Company prepares for and/or performs
any direct examinations of features reported by the preliminary or final report.
4.3.3 4.3.4 Vendor shall provide a phone list of appropriate support personnel.
Vendor shall make available to Company, if required by the Company, a fully trained
and qualified individual to provide field assistance to the Company during any direct
examination of features reported by Vendor. Vendor shall provide unit cost pricing for
providing such field support.
4.3.5 Company will be permitted to assign a representative, consultant or otherwise, to audit
the data analysis process on a periodic basis, to ensure data analysis process is being
performed to Company specifications.
4.3.6 Vendor shall use trained and qualified personnel for data analysis.
4.4 Documentation
4.4.1 Vendor shall issue an AGM integrity report whereby the distances between above
ground markers per the odometer of ILI tool is compared to corresponding Company
GPS and established AGM locations.
4.4.2 Vendor shall provide an analysis report containing a data summary with measurements
in imperial units in hard and electronic copy including the following:
4.4.2.1 Performance specification applicable to the pipeline segment, including the
essential variables, the method(s) used to qualify the performance
specification, and equipment specifications.
4.4.2.2 Names and certification levels of Vendor representatives who analyzed data,
produced the report, and approved the report.
4.4.2.3 Executive summary.
4.4.2.4 Fully described data quality issues
4.4.2.5 Data analysis parameters used to produce the report.
4.4.2.6 Certifications of ILI tool calibration.
4.4.2.7 Designation and location of critical pipeline features including, but not limited
to: pipeline valves, welds, sleeve repairs, casings, heavy wall pipe, taps, tees
and AGM locations.
4.5 Reporting Timescales and Other Requirements
4.5.1 Prior to any verbal or written report, Vendor shall perform QA/QC that not only satisfies
Vendor requirements in API 1163, Section 11, but also ensures that report is thorough,
complete, correct, and delivered in accordance with this Specification.
4.5.2 Vendor shall provide verbal report within 5 business days of completing successful EGP
ILI run. Report shall specifically address presence of any bore restrictions in excess of
10% of the pipe diameter so that a determination can be made about the ability of the
MFL/circumferential MFL/ultrasonic /other ILI tool to safely negotiate the pipeline.
4.5.3 Vendor shall provide an adequate number of reference locations to identify the location
of features. Reference locations shall provide distance to nearest upstream and
downstream AGM locations, length of joint containing feature, and lengths of five pipe
joints immediately upstream and downstream.

<<<PAGE 766>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 5 of 13
4.5.4 4.5.5 4.5.6 4.5.7 4.5.8 4.5.9 4.5.10 4.5.11 4.5.12 4.5.13 Vendor shall provide bi-weekly status report that includes status of data analysis and
anticipated report delivery date.
Vendor shall provide preliminary report (if required) within 21 business days of a
successful ILI run. Vendor shall notify Company (in writing) if timing cannot be
achieved. Preliminary report is required for the following indications:
4.5.5.1 Metal loss greater than 80% nominal wall thickness
4.5.5.2 ID reductions that might prevent passage of a MFL, circumferential MFL,
ultrasonic or other ILI tool
4.5.5.3 Assets Covered Per Mitigation Plan:
4.5.5.3.1 Metal Loss greater than 70% nominal wall thickness
4.5.5.3.2 Top of pipe (above 4 and 8 o’clock) ID reductions with indicated
metal loss
4.5.5.3.3 4.5.5.3.4 Significant anomaly that in the judgment of the data evaluator
requires immediate action
Top of the pipe (above 4 and 8 o’clock) ID reductions without
indicated metal loss and greater than 6% of pipe outside
diameter
4.5.5.3.5 Cracks to the extent preliminary indications are an established
TFI tool reporting procedure
Vendor shall provide electronic draft report of the pipeline listing, wall thickness listing,
weld comparison (when historical listing is provided by Company), and AGM location
information prior to issuing the final report. Company will review and provide comments
within 5 business days following receipt.
Vendor shall ship a final report within 5 business days of receipt of Company comments
to electronic draft report.
Unless otherwise indicated, Vendor shall provide two (2) copies of final report as part of
the base cost. Hard copy reports shall be provided in a 3 ring binder using 8 ½” x 11”
paper.
Final report shall be delivered to Company no later than 180 days after the ILI tool is
removed from the receive scraper trap and shall include ILI run date, final report issue
date and, if appropriate, final report re-issue date. Vendor shall notify Company in
writing if this timing cannot be met and shall demonstrate through documentation that it
was impracticable to deliver information within 180 days. If Company determines that it
was practical to obtain the report within the 180 days, an ILI tool may be re-run.
Vendor shall provide software for viewing the raw signal trace data and other data
presentations. Vendor shall automatically provide software updates.
Vendor will manually review enough features to validate the accuracy of Vendor’s
automated sizing system. Vendor will indicate which features were manually reviewed.
If a discrepancy is identified in a final report that requires further evaluation, re-grade,
and/or re-issue by Vendor, Vendor shall deliver revised final report within two weeks of
discrepancy being identified. If data is re-graded, Vendor shall provide written
correspondence documenting basis of discrepancies and proposed corrective actions.
Upon completion of rehabilitiation activities by Company, Company will provide Vendor
with actual field findings. Vendor will review data and provide feedback regarding tool
performance and if regrade or rerun is warranted.

<<<PAGE 767>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 6 of 13
Vendor will schedule quarterly reviews with Company to discuss tool scheduling and
performance, report delivery timelines and other performance standards.
4.5.14 5.0 technical Criteria
5.1 Metal Loss Interaction Criterion
5.1.1 5.1.2 Vendor shall group metal loss indications spaced less than 6 times the wall thickness
(6t) apart in either axial or circumferential directions (called interacting) together to form
a cluster. A reported metal loss anomaly may consist of an individual metal loss
indication or a cluster of two or more interacting metal loss indications.
Length and width reported for a cluster is the sum of individual indications plus metal
interaction length or width, up to 6t in either direction. Peak depth reported for a cluster
is the peak depth of the deepest metal loss indication in the cluster. A graphical
presentation is as follows:
5.1.2.1 Expanded pig call boxes that overlap should be considered as interacting.
P ig C a ll B o x # 1
P ig C a ll B o x # 2
P ig C a ll B o xe s e xp a n d e d '3 t' in e a ch d ire ctio n
5.2 Metal Loss Assessment Criterion
5.2.1 Vendor shall use RSTRENG 85% Area criterion (RSTRENG85% Area) to evaluate
corrosion metal loss indications based upon the reported peak depth and axial length.
5.2.1.1 Predicted Failure Stress

Failure
SMYS =

)000,10(

   
- 1

- 1
85.0

 
d

t
 
85.0

 
d

t
 
M
1-

  
 
where:
Failure = Predicted failure stress, psi
 = Flow stress, f{SMYS}, psi
SMYS = Specified minimum yield strength, psi.
d = depth of metal loss, inch
t = Nominal wall thickness of pipe, inch

<<<PAGE 768>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 7 of 13
Dt
d/t = depth-to-wall thickness ratio of the metal loss
M = Folias factor, f{L, D, t}
L = Axial length of the corrosion, inch
D = Nominal outside diameter of the pipe, inch
2
L
For

1 = 0.6275 + M50,
2
L
0.003375 -
Dt

2 2
 
L

Dt
 
For
2
L
0.032 = M50, >
Dt
2
L
3.3 +
Dt
5.2.1.2 Rupture Pressure Ratio, RPR

   
- 1

85.0
- 1
85.0

Failure
SMYS

)000,10(

 
d

t
 
RPR

=
SMYS
SMYS

 
d

t
 
M
1-

  
 
5.2.1.3 Predicted Burst Pressure, PBurst
- 1
85.0

 
d

t
 
P


Burst Failure

 
2
t

SMYS =
D
 

)000,10(

 

2
t

D
 
   
- 1

85.0

 
d

t
 
M
1-

  
 
5.2.2 5.2.3 Provide an RPR value and PSafe pressure value for all metal loss features.
If instructed by Company, Vendor shall perform RSTRENG Effective Area Assessment
of data for metal loss indications and shall produce a projected corrosion profile. Vendor
shall evaluate this profile using the iterative calculation procedure in RSTRENG
Effective Area analysis. An example profile is shown below:

<<<PAGE 769>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 8 of 13
Direction of Flow
30% 30%
10%
Cluster
20%
50%
Projected Corrosion
Profile
Wall Thickness
5.3 Crack-like and Longitudinal Seam Weld Assessment Criterion Circumferential MFL (TFI, AFD,
SMFL) and ultrasonic crack detection (USCD)
5.3.1 Vendor shall identify ‘crack-like’ indications detected in pipeline, whether in pipe body or
in longitudinal seam weld (LSW).
5.3.2 Vendor shall identify each indication of the following detected anomalies associated with
LSW.
Axial Seam Weld Metal Loss (ASWML)
5.3.2.6 Seam Weld Anomaly (SWA)
5.3.3 5.3.4 5.3.2.1 Seam Weld Features ‘A’ (SWFA
5.3.2.2 Seam Weld Features ‘B’ (SWFB)
5.3.2.3 Seam Weld Dents (SWD)
5.3.2.4 Seam Weld Metal Loss (SWML)
5.3.2.5 Potential pipe body metal loss indications (but not “crack-like” or other indications
associated with LSW) reported by Vendor shall be assessed in accordance with Metal
Loss Interaction Criterion and Metal Loss Assessment Criterion above).
Company or designee will assess SWFA, SWFB, SWML, and ASWML indications using
CorLASTM (fracture criterion) or comparable analysis.

<<<PAGE 770>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 9 of 13
5.4 Ultrasonic Wall Measurement Assessment Criterion
5.4.1 5.4.2 5.4.3 5.4.4 5.4.5 Pipeline Integrity Engineer or designee will consult with ILI vendor and Magellan’s third
party consultant to establish reporting and evaluation criteria guidelines.
All laminations as identified by tools reporting capabilities will be included in final
report
Vendor shall identify each indication of the following detected anomalies:
5.4.3.1 Sloping laminations
5.4.3.2 Bulging laminations
5.4.3.3 Laminations interacting with dents, metal loss, cracks, girth and
seam welds and other reported features
5.4.3.4 Surface breaking laminations
5.4.3.5 Hydrogen blisters
5.4.3.6 Planar, intermittent or variable depth laminations
5.4.3.7 Other significant indications within the capability of the tool’s
detection
Vendor shall evaluate Metal loss as identified in section 5.1 and 5.2 and 5.5
Vendor shall evaluate deformation indications as identified in section 5.6
5.5 Metal Loss in Seamless Pipe
5.5.1 Vendor shall report sections of pipe containing “areas of interest” where
seamless pipe noise pattern data is to the extent that the data analyst is
challenged to accurately predict metal loss dimensions.
5.6 Geometry Assessment Criterion
5.6.1 Vendor shall report all deformations >2% of pipe diameter. Vendor shall report
confirmed correlated deformations and geometric anomalies (regardless of
depth) with associated metal loss, deformation >2% of pipe diameter associated
with LSW, and deformation >2% of pipe diameter affecting pipe curvature of
girth welds. In addition, vendor shall report all deformations and geometric
anomalies that interact with laminations.
5.7 5.6.2 Vendor shall report data related to geometric indications within tool capability to
detect such indications. Tool must be able to detect deformation indications 2%
(or 0.250” for pipe less than or equal to 12” NPS) and greater.
5.6.3 If EGP ILI run occurs prior to or after an MFL/circumferential MLF UT pipeline
inspection, Vendor shall integrate EGP and MFL/circumferential MFL UT data
into a single final report. If Vendor cannot issue integrated final report within 180
days of the first successful ILI run, Vendor shall immediately notify Company
and issue individual final reports.
Field Evaluation of ILI Tool Results
5.7.1 ILI tool data shall be reviewed in the field and compared to the specifications
referenced in acceptance limits on lost data in Performance Specification
section.

<<<PAGE 771>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 10 of 13
5.7.2 If ILI tool data is not of sufficient quality to allow Vendor to meet detection and
sizing thresholds in Performance Specification, ILI tool will be scheduled for a
re-run.
5.8 ILI Reporting
5.8.1 The following shall be included in pipeline listing (Microsoft Excel format) for
each feature:
5.8.1.1 Sequential girth weld number or reference number
5.8.1.2 Feature type
5.8.1.3 Relative distance to upstream weld (as measured from the start of
the metal loss or ID reduction indication ), feet
5.8.1.4 Absolute odometer distance, feet
5.8.1.5 Joint length, feet
5.8.1.6 Comments
5.8.1.7 Internal or external location
5.8.1.8 Peak depth of metal loss (% w.t.), crack-like (% w.t.) or ID reduction
(%OD) indication
5.8.1.9 Axial length, inches
5.8.1.10 Width, inches (metal loss indications only)
5.8.1.11 Orientation (deepest point of metal loss cluster or centerline of ID
reduction indication), clock position
5.8.1.12 RPR (calculated using RSTRENG 85% Area criterion)
5.8.1.13 Nominal wall thickness, inches
5.8.2 5.8.1.14 Predicted Safe Pressure, (calculated using RSTRENG 85% Area
criterion), psig
5.8.1.15 Approximate engineering station (based on alignment sheets and
AGM benchmarks)
5.8.1.16 5.8.1.17 5.8.1.18 GPS coordinate, if requested by Company
Pipe type (ERW, SAW, DSAW, or seamless)
Longitudinal seam orientation (for circumferential MFL or ultrasonic
ILI)
5.8.1.19 SMYS, psi
5.8.1.20 Relative distance to upstream weld (as measured from deepest point
of metal loss or ID reduction indication), feet
5.8.1.21 Indication of which features have been manually reviewed
The following shall be reported for each change in pipe wall thickness, type or
grade in wall thickness listing:
5.8.2.1 Absolute odometer distance, feet
5.8.2.2 Nominal wall thickness, inches
5.8.2.3 Pipe type

<<<PAGE 772>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 11 of 13
5.8.2.4 SMYS, psi
Data shall be presented with enough significant digits to reproduce results.
5.8.3 6.0 DEFINITIONS
6.1 Terms and terminology shall be used in accordance with API 1163 Section 4 unless
otherwise specified herein. Vendor shall get approval in writing from Company to use
other terminology. Additional definitions are as follows:
6.1.1 6.1.2 6.1.3 6.1.4 6.1.5 6.1.6 Seam Weld Feature A (SWFA): Seam weld indication that exhibits possible “crack‐like”
characteristics.
Seam Weld Feature B (SWFB): Seam weld indication that exhibits some, but not all
“crack‐like” characteristics.
Seam Weld Metal Loss (SWML): Metal loss indication (including any part of a cluster)
that encroaches upon the longitudinal seam weld (LSW).
Axial Seam Weld Metal Loss (ASWML): Metal loss indication (including any part of a
cluster) that encroaches upon LSW and is less than 2‐inches wide with a length‐to‐
width aspect ratio equal to or greater than 5:1
Seam Weld Deformation (SWD): Deformation that encroaches upon the LSW
6.1.7 Seam Weld Anomaly (SWA): Feature other than a SWFA, SWFB, SWML, or SWD that
encroaches upon or is immediately adjacent to LSW and is thought to be non‐injurious.
Geometric Anomaly: Internal diameter reduction indication below reporting
requirements specified in 49 CFR 195.452h

<<<PAGE 773>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 12 of 13
System Integrity Plan Change Log
Date Change
Location
Change By Approved By Brief Description of Change
11/01/05 All Clyde Clausen Mike Pearson Conducted Annual Review
01/01/06 2.52 Clyde Clausen Mike Pearson Added: Longhorn Specific
10/30/06 All Clyde Clausen Mike Pearson Conduct annual review
12/8/06 All Clyde Clausen Mike Pearson Removed all references to RSTRENG Effective Area.
4/30/07 3.3.3.1 Clyde Clausen Mike Pearson Added paragraph for Longhorn Specific requirements.
6/26/07 2.4.2.1 Clyde Clausen Mike Pearson Added Paragraph
6/26/07 2.5.8 Clyde Clausen Mike Pearson Modified Paragraph
6/26/07 3.3.3 Clyde Clausen Mike Pearson Modified paragraph to change seam criteria to two times the
wall thickness. Removed Longhorn Specific 3.3.3.1.
6/26/07 3.4.1 Clyde Clausen Mike Pearson Modified paragraph to reflect dent reporting criteria.
6/26/07 3.6.3 Clyde Clausen Mike Pearson Added paragraph
7/10/08 Document Dennis Vasicek Clyde Clausen Changed “contractor” to “vendor”
7/10/08 1.0 Dennis Vasicek Clyde Clausen Added Section 1.0 Purpose and paragraph 1.1
7/10/08 2.0 Dennis Vasicek Clyde Clausen Added Section 2.0 Scope and paragraphs 2.1 through 2.3.3
7/10/08 3.1 Dennis Vasicek Clyde Clausen Revised sentence
7/10/08 3.2 Dennis Vasicek Clyde Clausen Removed, “If requested” from the third sentence
7/10/08 3.3 Dennis Vasicek Clyde Clausen Changed, “will” to, “may”
7/10/08 3.4 Dennis Vasicek Clyde Clausen Rewrote paragraph
7/10/08 3.11 Dennis Vasicek Clyde Clausen Reworded sentence
7/10/08 3.12 Dennis Vasicek Clyde Clausen Added paragraph
7/10/08 4.1.1 Dennis Vasicek Clyde Clausen Reworded sentence
7/10/08 4.1.1.4 Dennis Vasicek Clyde Clausen Added paragraph
7/10/08 4.1.1.9 Dennis Vasicek Clyde Clausen Changed, “defect” to, “anomaly” and added clarification to
last sentence.
7/10/08 4.2.1 Dennis Vasicek Clyde Clausen Added clarification to the sentence
7/10/08 4.2.2 Dennis Vasicek Clyde Clausen Revised sentence
7/10/08 4.2.3 Dennis Vasicek Clyde Clausen Added last sentence regarding tool performance
specification related to flow rate changes
7/10/08 4.2.8 Dennis Vasicek Clyde Clausen Added “prevent” to first sentence
7/10/08 4.2.10 Dennis Vasicek Clyde Clausen Replaced last sentence with, “The certification levels of the
supervisor and other team members shall be advised to the
Company by the vendor’s project manager prior to a team
arriving on-site.”
7/10/08 4.2.13 Dennis Vasicek Clyde Clausen Added clarification to sentence
7/10/08 4.2.14 Dennis Vasicek Clyde Clausen Deleted sentence
7/10/08 4.2.15 Dennis Vasicek Clyde Clausen Deleted sentence
7/10/08 4.3.2 Dennis Vasicek Clyde Clausen Added “certified to level III in analysis” and change “defects”
to “anomalies”
7/10/08 4.3.5 Dennis Vasicek Clyde Clausen Deleted second sentence
7/10/08 4.4.2.1 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.4.2.2 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.4.2.3 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.4.2.4 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.4.2.5 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.4.2.7 Dennis Vasicek Clyde Clausen Reworded paragraph
7/10/08 4.4.2.10 Dennis Vasicek Clyde Clausen Removed sentence
7/10/08 4.5 Dennis Vasicek Clyde Clausen Added, “and Other Requirements”
7/10/08 4.5.1 Dennis Vasicek Clyde Clausen Added sentence
7/10/08 4.5.6 Dennis Vasicek Clyde Clausen Added clarification to the first sentence
7/10/08 4.5.9 Dennis Vasicek Clyde Clausen Added, “final report”
7/10/08 5.2.3 Dennis Vasicek Clyde Clausen Added paragraph
7/10/08 5.3.3 Dennis Vasicek Clyde Clausen Deleted paragraph related to seam assessment width
7/10/08 5.3.3.4 Dennis Vasicek Clyde Clausen Divided Seam Weld Metal Loss into two categories and
added paragraphs 5.3.3.4.1 and 5.3.3.4.2
7/10/08 5.3.4 Dennis Vasicek Clyde Clausen Changed, “valid” to, “used” and added, “but not for the seam
weld assessment”
7/10/08 5.4 Dennis Vasicek Clyde Clausen Added Metal Loss in Seamless Pipe paragraph and
paragraph 5.4.1
7/10/08 5.6.2 Dennis Vasicek Clyde Clausen Added paragraph

<<<PAGE 774>>>

Magellan Midstream Partners, L.P.
IN-LINE INSPECTION TECHNICAL SPECIFICATION 7.03–ADM–003
Asset Integrity 01/01/12 Revision: 5 Page 13 of 13
12/19/08 Dennis Vasicek Clyde Clausen Conducted annual review and made minor wording
modifications
01/01/10 4.5.3 Removed “Longhorn”
4.5.5 Changed to Bi-weekly
4.5.6 Added weld comparison
5.3.3.4.2 Removed: separate listin of seam weld metal loss features
athat are axially oriented metal loss
5.7.1.8/5.7.1.1
4/5.7.1.15/
New. Deleted Upstream reference location/distance and
downstream reference
Definitions
Section
Added
01/01/11 Reviewed, no changes
9/1/11 All Clyde Clausen Doug Chabino Re‐worked and Re‐formatted entire document
12/31/11 All 2012 Annual Review complete
6/18/12 5.6.1 Clyde Clausen Doug Chabino Clarified reporting dent criteria in section 5.6.1

<<<PAGE 775>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 1 of 18
1.0 OBJECTIVE
1.1 The Objective of this procedure is to establish the process to analyze In‐Line Inspection (ILI) data to
identify features that require repair per DOT 49 CFR 195.452.
2.0 INDEX
1.0 OBJECTIVE ........................................................................................................................................ 1
2.0 INDEX ................................................................................................................................................. 1
3.0 PROCEDURE ..................................................................................................................................... 1
4.0 PRELIMINARY REPORTS ................................................................................................................. 1
5.0 ELECTRONIC DRAFT REPORTS ...................................................................................................... 1
6.0 FINAL REPORTS ................................................................................................................................ 1
7.0 INTEGRITY CONDITIONS ................................................................................................................. 2
8.0 9.0 DISCRETE POINT PRESSURE (DPP) ANALYSIS ............................................................................ 5
SEAM WELD ASSESSMENT ............................................................................................................. 6
10.0 ULTRASONIC WALL MEASUREMENT ASSESSMENT ................................................................... 7
11.0 CASING ANALYSIS ............................................................................................................................ 8
12.0 DENT REVIEW AND DEPTH OF COVER CORRELATION .............................................................. 8
13.0 PROJECTED CORROSION GROWTH ANALYSIS ........................................................................... 9
14.0 CALIBRATION DIGS ......................................................................................................................... 9
15.0 DIG LIST ........................................................................................................................................... 10
16.0 ILI SUMMARY DOCUMENT ............................................................................................................. 11
17.0 CORRELATION AND TOOL TOLERANCE ASSESSMENT............................................................ 11
18.0 DEFINITIONS .................................................................................................................................... 12
19.0 REFERENCES .................................................................................................................................. 13
3.0 PROCEDURE
3.1 3.2 3.3 3.4 This guideline incorporates API 1163, In‐line Inspection Systems Qualification Standard, First Edition,
August 2005; NACE Standard RP0102‐2002; and ANSI/ASNT ILI‐PQ‐2005 where applicable.
This guideline is applicable to federal and/or state jurisdictional pipelines and/or facilities. Elements
of this program may be used, in whole or part, on non‐jurisdictional assets as deemed appropriate.
Assets Covered Per Mitigation Plan operate under Longhorn Mitigation Plan requirements in addition
to applicable Federal, State, and Local regulations and Company guidelines, processes or best
practices.
The Pipeline Integrity Engineer and Pipeline Integrity Data Coordinator will utilize this Guideline in
conjunction with the In‐Line Inspection Procedure when conducting analyses of Inspection data.
.

<<<PAGE 776>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 1 of 17
4.0 PRELIMINARY REPORTS
4.1 In‐line Inspection Vendor (Vendor) will provide Preliminary Report (if required) within 21
business days of a successful tool run. Features requiring a Preliminary Report are described in
In‐Line Inspection Technical Specification.
4.2 If features meeting preliminary reporting criteria are reported by Vendor, Pipeline Integrity
Engineer will:
4.2.1. 4.2.2. 4.2.3. Notify Supervisor of Pipeline Integrity Engineering via email.
Initiate immediate investigation and repair process described in In‐Line Inspection
Procedure if feature is located in an HCA.
4.3 Ensure that appropriate response is executed within 5 days of receipt of Preliminary
Report for features reported on Assets Covered Per Mitigation Plan in accordance with
Longhorn Mitigation Plan, Section 3.5.2.
4.2.4. Request Pipeline Integrity Data Analyst to prepare dig sheets.
4.2.5. Provide excavation findings to Vendor upon completion of any field investigations.
Pipeline Integrity Data Analyst will:
4.3.1. Prepare dig sheets using Procedure for Creating Dig Sheets.
4.3.2. Prepare Rehab Book for inspector in accordance with Project File Index Form.
5.0 ELECTRONIC DRAFT REPORTS
5.1 Vendor will provide an electronic Draft Report as specified in In‐Line Inspection Technical
Specification.
5.2 Pipeline Integrity Data Analyst will verify electronic Draft Report as specified in AGM Verification
Guidelines.
Verify electronic Draft Report as specified in ILI Data Verification Guidelines.
5.3 Pipeline Integrity Engineer will:
5.3.1. 5.3.2. Approve electronic Draft Report or provide Vendor any comments within 5 business
days of receipt of electronic Draft Report. If discrepancies are identified, Vendor will be
required to make necessary modifications before issuance of Final Report.
6.0 FINAL REPORTS
6.1 Pipeline Integrity Engineer will
6.1.1. 6.1.2. Perform QA/QC review of Final Report to ensure it is thorough, complete, correct and
delivered in accordance with In‐Line Inspection Technical Specification.
6.1.1.1. If a significant issue is observed, Pipeline Integrity Engineer will
immediately reject Final Report and notify Vendor in writing.
Declare the date of discovery (Discovery) within 5 business days of receipt of a valid
Final Report but not later than 180 days after the day ILI tool was trapped in the
receiver.
6.1.2.1. 6.1.3. Pipeline Integrity Engineer will calculate 60‐day and 180‐day due dates for
HCA conditions based on counting forward from Discovery date.
For Assets Covered Per Mitigation Plan Send a copy of MFL Final Report to Operational

<<<PAGE 777>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 2 of 17
6.2 6.1.4. 6.1.5. 6.1.6. Reliability Assessment (ORA) Contractor for Probability of Exceedance (POE) analysis,
girth weld evaluation and metal loss within 3 inches of girth weld for.
Copy electronic documents (i.e. pipeline listing, NWT report, AGM listing and mapping
files, LAPA [if provided], certification of calibration) to appropriate line section folder on
network drive.
Perform detailed analysis of ILI data to identify: immediate, 60‐day, 180‐day and 6‐
month (where applicable) features, DPP features, casings to be worked, ID reduction
review, and other features potentially requiring investigation.
Schedule a Pre‐Job Roundtable meeting with various stakeholders (as appropriate: Asset
Integrity Maintenance Supervisor, Asset Integrity Engineer, Supervisor Corrosion
Control, Pipeline Integrity Coordinator, Real Estate Representative, Pipeline Integrity
Data Analyst, Supervisor of Pipeline Integrity Engineering and Manager of Asset
Integrity) to discuss ILI Summary document, features to be investigated, and other
concerns (e.g. integrated depth of cover and corrosion control data) identified by Final
Report.
Pipeline Integrity Data Analyst will:
6.2.1. Prepare dig sheets using Procedure for Creating Dig Sheets.
6.2.2. Prepare a project field book using Project File Index Form.
6.2.3. Obtain completed project field book from chief inspector and perform checks on
information accumulated during rehabilitation upon completion of rehabilitation
activities.
7.0 INTEGRITY CONDITIONS
7.1 7.2 7.3 Pipeline Integrity Engineer will obtain High Consequence Area (HCA) begin and end location
information from Risk Analyst or from HCA database and calculate corresponding odometer
locations to mark in Final Report.
Pipeline Integrity Engineer will identify the following conditions:
HCAS And Areas That Could Affect HCAs
7.3.1. Immediate Repair Conditions
7.3.1.1. Discovery of an immediate repair condition is to be established no later
than 5 business days after condition is reported to Company. Within 5
business days of identification of an immediate repair condition, Pipeline
Integrity Engineer will initiate immediate investigation and repair process
in accordance with In‐Line Inspection Procedure.
7.3.1.2. Until immediate condition is repaired, the following operating conditions
may be implemented (dependent upon the type of feature).
7.3.1.2.1. Reduce operating pressure so that at the location of the
anomaly, discrete point pressure (PDPP) does not exceed
operating pressure (PSAFE), or PDPP does not exceed the
pressure calculated by the formula in Section 451.7 of
ASME/ANSI B31.4, or
7.3.1.2.2. Reduce operating pressure so that PDPP does not exceed 80%

<<<PAGE 778>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 3 of 17
7.3.1.3. 7.3.1.4. of highest operating pressure actually experienced at location
of anomaly within 60‐days preceding inspection, or
7.3.1.2.3. Shutdown pipeline.
Metal loss features (including SWFA, SWFB, ASWML and SWML) with
predicted depths greater than or equal to 80% of the wall thickness
requires reducing operating pressure per 7.3.1.2.2 or shutdown pipeline
until repair is made.
Features with predicted burst pressure, PBURST, less than PDPP requires
reduce operating pressure per 7.3.1.2.1 or shutdown pipeline until repair is
made.
7.3.1.4.1. 7.3.1.4.2. Metal loss calculation using 85% Area RSTRENG criterion or
CorLASTM (Flow Stress Criterion, 85% Area)
SWFA, SWFB, ASWML, or SWML calculation using CorLASTM
(Fracture Mechanics Criterion)
7.3.1.5. Top‐side dents (above the 4 and 8 o’clock positions) predicted to contain
associated metal loss, cracking or a stress riser requires reducing operating
pressure per 7.3.1.2.2 or shutdown pipeline until repair is made.
7.3.1.6. Top‐side dents with a predicted depth greater than 6% of the nominal pipe
diameter requires reducing operating pressure per 7.3.1.2.2 or shutdown
pipeline until repair is made.
7.3.1.7. Significant features in the judgment of the person evaluating the
inspection and test assessment results requires reducing operating
pressure or shutdown pipeline based upon type of feature and engineering
analysis until repair is made.
7.3.1.8. Deformation anomaly characterized as a pipeline device or repair intrusion
such as pig‐sig, IFD, tube, flow improver nozzle, heavy weld, etc. will not be
considered an “Immediate Condition.”
7.3.2. 60‐Day Repair Conditions
7.3.2.1. Top‐side dents with a predicted depth greater than 3% of the pipeline
diameter (greater than 0.250” in depth for a pipeline diameter less than
Nominal Pipe Size (NPS) 12).
7.3.2.2. Bottom‐side dents (below 4 and 8 o’clock positions) predicted to contain
any metal loss, cracking, or a stress riser.
7.3.3. 180‐day Repair Conditions
7.3.3.1. Dents with a predicted depth greater than 2% of the pipeline’s diameter
(0.250” in depth for a pipeline diameter less than NPS 12) that affects pipe
curvature at a girth weld or a longitudinal seam weld.
7.3.3.2. Top‐side dents with a predicted depth greater than 2% of the pipeline’s
diameter (0.250” in depth for a pipeline diameter less than NPS 12).
7.3.3.3. Bottom‐side dents with a predicted depth greater than 6% of the pipeline’s
diameter.
7.3.3.4. Features where the calculation of remaining strength of the pipe shows an

<<<PAGE 779>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 4 of 17
7.4 operating pressure, PSAFE, that is less than PDPP at the location of the
anomaly.
7.3.3.5. Areas of general corrosion with a predicted metal loss greater than 50% of
nominal wall
7.3.3.6. Features with predicted metal loss greater than 50% of nominal wall that
are located at a crossing of another pipeline, or are in an area with
widespread circumferential corrosion, or are in an area that could affect a
girth weld
7.3.3.7. Potential crack indications that when excavated are determined to be a
crack.
7.3.3.8. Corrosion of or along a longitudinal seam weld (as identified by the ILI
service provider as being axially oriented seam weld metal loss)
7.3.3.9. Gouge or grooves with a predicted depth greater than 12.5% of nominal
wall
7.3.4. Other Conditions
7.3.4.1. Conditions identified by ILI that could impair the integrity of the pipeline
should be repaired as appropriate.
Non‐HCAS And Areas Not Affecting HCAS
7.4.1. The following anomalies will be immediately evaluated and scheduled for excavation if
deemed necessary. However, all HCA Immediate Conditions shall take priority:
7.4.1.1. Metal loss (including SWFA, SWFB, ASWML, and SWML) greater than or
equal to 80% wall thickness
7.4.1.2. Features with predicted burst pressure Pburst, less than discrete point
pressure, PDPP.
7.4.1.3. 7.4.1.2.1. Metal Loss calculation using 85% Area RSTRENG Criterion or
CorLAS™ (Flow Stress Criterion, 85% Area)
7.4.1.2.2. SWFA, SWFB, ASWML, or SWML calculation using CorLAS™
(Fracture Mechanics Criterion)
Top‐side dents with any indicated metal loss, cracking or stress riser
7.4.2. The following anomalies will be evaluated and scheduled for excavation and repair prior
to the next integrity assessment if deemed necessary:
7.4.2.1. Features where PSAFE is less than PDPP at location of anomaly.
7.4.2.2. Bottom‐side dents with associated metal loss.
7.4.2.3. Girth weld anomalies
7.4.2.4. Dents in excess of 6% of pipe diameter.
7.4.2.5. Dents located in the girth weld or longitudinal seam that exceed 2% of pipe
diameter for NPS 12 and larger or 0.250” for pipe diameters less than NPS
12.
7.4.2.6. Gouges, scratches, or grooves that exceed 12.5% metal loss.
7.4.2.7. Severe mill related defects (lamination, hard spots, etc.).

<<<PAGE 780>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 5 of 17
7.4.2.8. Crack‐like anomalies located in girth weld, longitudinal seam weld, or pipe
7.5.2. 8.0 7.5 7.6 body.
7.4.2.9. Field confirmed casing shorts with associated metal loss.
7.4.2.10. Other significant anomalies.
7.4.2.11. Features identified for tool calibration purposes.
Assets Covered Per Mitigation Plan
7.5.1. Initiation of a response must be implemented within 5 days of receipt of report for
these features in accordance with Longhorn Mitigation Plan Section 3.5.2
7.5.1.1. Metal loss greater than 70% wall thickness
7.5.1.2. Top‐side dents with any indicated metal loss
7.5.1.3. Significant anomalies that in the judgment of the data evaluator require
immediate action
initiation of a response must be implemented within 60 days of receipt of report for
these features in accordance with Longhorn Mitigation Plan Section 3.5.2.
7.5.2.1. Top‐side dents without indicated metal loss and with depths greater than
6% of the pipe diameter
7.5.3. The following indications shall be investigated within 6 months of the receipt of report
in accordance with Longhorn Mitigation Plan Section 3.5.2.
7.5.3.1. Dents with any of the following: Metal loss, corrosion, exceeds 6% of the
pipe outside diameter, or located in a longitudinal seam or girth weld
Features where remaining strength of pipe results in a safe operating
pressure, PSAFE, that is less than the current MOP at the location of the
anomaly using a suitable safe operating pressure calculating criterion.
7.5.3.3. Casing shorts with associated metal loss
7.5.3.4. Girth weld anomalies
7.5.3.5. Corrosion within 3” of either side and/or across girth welds as determined
by ORA contractor
7.5.3.6. Preferential corrosion of or along seam welds.
7.5.3.7. Gouges or grooves greater than 50% of nominal wall thickness
7.5.3.8. Cracks located in the pipe body, girth weld, and longitudinal seam that are
determined to be injurious to the integrity of the pipeline.
As an alternative to direct examination, an API 579 Fitness‐For‐Service level 1, 2, and/or 3
Engineering Critical Assessment may be performed in order to substantiate the need for direct
examination activity.
DISCRETE POINT PRESSURE (DPP) ANALYSIS
8.1 Pipeline Integrity Engineer will populate discrete point pressure (DPP) spreadsheet with
anomalies with rupture pressure ratio (RPR) less than 1.0. RPR is PBURST divided by pipe design
pressure. PSAFE is design factor multiplied by PBURST. RPR will be less than 1.0 when PBURST of an
anomaly is less than pipe design pressure (100% SMYS). DPP data sources include:
7.5.3.2.

<<<PAGE 781>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 6 of 17
8.1.1. ILI Final Report
8.1.2. Corrosion Growth spreadsheet
8.1.3. Seam Weld Assessment analysis
8.2 Pipeline Integrity Data Analyst will:
8.2.1. Calculate stations using Total AGMs Form and obtain elevations using alignment sheets
for features requiring DPP analysis.
8.2.2. Use alignment sheets to determine if any metal loss features greater than 50% are
located within 50’ of a foreign pipeline crossing and will indicate on appropriate tab in
the DPP spreadsheet.
8.3 Asset Integrity Engineer will complete DPP analysis taking into account pump set points,
elevation differences, and surge conditions.
8.3.1. Determine, through available records, design pressure for line and upstream pump
maximum discharge set point.
8.3.2. Determine maximum elevation difference between pressure source and feature
location.
8.3.3. Determine static head pressure due to elevation change calculated using specific gravity
of heaviest product.
8.3.4. Add static head pressure to pump set point to get PDPP at feature location due to static
head (Static PDPP).
8.3.5. For incompressible liquid pipelines, conduct surge analysis at each feature location to
determine PDPP due to surge (Surge PDPP).
8.3.6. Compare static PDPP and surge PDPP at each feature location. Select greater value to be
used as PDPP for anomaly location.
8.4 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
9.0 SEAM WELD ASSESSMENT
9.1 Pipeline Integrity Engineer or designee will conduct seam weld assessment (SWA) when ILI tool is
either circumferential flux leakage (aka TFI, AFD, or SWML ILI) or ultrasonic crack detection
(USCD) ILI technology.
9.2 The following anomalies will be assessed and considered for investigation and/or remediation.
9.2.1. Seam Weld Feature A (SWFA)
9.2.2. Seam Weld Feature B (SWFB)
9.2.3. Axial Seam Weld Metal Loss (ASWML)
9.2.4. Seam Weld Deformation (SWD)
9.2.5. Axial Planar features
9.2.6. Crack‐Field
9.2.7. Notch‐Like

<<<PAGE 782>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 7 of 17
9.2.8. Weld Anomaly
9.2.9. Other integrity features in the judgment of the person evaluating the data
9.3 Pipeline Integrity Engineer or designee will calculate Pburst and Psafe using CorLAS™ (fracture
criterion) or similar remaining strength calculation and using appropriate fracture toughness for
SWFA, SWFB, ASWML and SWML anomalies.
9.4 Pipeline Integrity Engineer or designee may use MFL data, when available, to identify additional
potential SWML anomalies, defined as those within 2 inches of LSW. For these integrated SWML
anomalies, Pipeline Integrity Engineer or designee will calculate Pburst and Psafe for all internal and
external anomalies, using 85% Area RSTRENG™ or CorLAS™ (flow stress criterion, 85% Area)
9.5 Pipeline Integrity Engineer will add to DPP spreadsheet features requiring direct examination
when PBURST is less than pipe design pressure (100% SMYS) and features identified in SWA report
as requiring DPP analysis. RPR and PBURST values listed in SWA report will be used in DPP
spreadsheet.
9.6 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
10.0 ULTRASONIC WALL MEASUREMENT ASSESSMENT
10.1 Pipeline Integrity Engineer or designee will conduct ultrasonic wall measurement (USWM)
assessment when ILI tool is USWM ILI technology.
10.2 Pipeline Integrity Engineer or designee will consult with ILI vendor and Magellan’s third party
consultant to establish reporting and evaluation criteria guidelines. If needed, modifications will
be made to Magellan’s In‐Line Inspection Technical Specification. All laminations as identified by
tools reporting capabilities will be included in final report.
10.3 The following Laminations will be evaluated and considered for investigation and/or
remediation.
10.3.1. Sloping laminations
10.3.2. Bulging laminations
10.3.3. Surface breaking laminations
10.3.4. Hydrogen blisters
10.3.5. Laminations interacting with deformations, metal loss, cracks, girth and seam welds,
and other reported features
10.3.6. Other integrity features in the judgment of the person evaluating the data.
10.4 When applicable, Pipeline Integrity Engineer or designee will review the USWM data for seam
weld features and perform calculations described in the Seam Weld Assessment process.
10.5 Pipeline Integrity Engineer or designee will identify and evaluate all reported deformations
identified by EGP (Electronic Geometry Pigs) or other applicable ILI inspections that correlate and
interact with existing laminations.
10.6 Pipeline Integrity Engineer or designee may use previous ILI data, when available, to identify
additional metal loss anomalies and significant features (i.e. cracks, girth welds, long seam, etc.)
that may be potentially associated with laminations. For integrated metal loss anomalies > 20%
deep, Pipeline Integrity Engineer or designee will calculate PBURST and PSAFE for all internal and

<<<PAGE 783>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 8 of 17
external anomalies using CorLASTM (Fracture Mechanics Criterion)
10.7 Pipeline Integrity Engineer will add to DPP spreadsheet features requiring direct examination
when PBURST is less than pipe design pressure (100% SMYS) and features identified in USWM
report as requiring DPP analysis. RPR and PBURST values listed in USWM report will be used in DPP
spreadsheet.
10.8 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
10.9 Pipeline Integrity Engineer will place all features requiring investigation on the dig list
11.0 CASING ANALYSIS
11.4 Pipeline Integrity Data Analyst will notify Pipeline Integrity Engineer if any casings need to be
added to Dig List.
11.5 Pipeline Integrity Engineer will identify casings with metal loss in Final Report.
12.0 11.1 Pipeline Integrity Engineer will create a list of casings with casing begin and end locations in
order of absolute distance.
11.2 Pipeline Integrity Data Analyst will determine casings that require rehabilitation. Pipeline
Integrity Data Analyst will:
11.2.1. Add metal loss information from Final Report to designate number of metal loss
features and maximum and minimum depths of metal loss inside each casing.
11.2.2. Check with Pipeline Integrity Engineer to determine if any casings are scheduled to be
investigated due to required ILI investigations.
11.2.3. Review corrosion database for potential shorted or elevated casings.
11.2.4. Request Corrosion Technician field verify casings as required.
11.3 Corrosion Technician will resolve discrepancies and perform field verification of casings as
required, notify Pipeline Integrity Data Analyst about casings that need to be investigated during
pipeline rehabilitation, and incorporate field verification findings into corrosion database.
DENT REVIEW AND DEPTH OF COVER CORRELATION
12.1 Pipeline Integrity Engineer will create a top‐side dent list and a dent comparison list. The dent
comparison list will match current dent callouts to previous ILI run dent callouts.
12.2 Pipeline Integrity Engineer may request previous run Vendor to verify data signal to determine if
current dents were visible in previous run data.
12.3 Pipeline Integrity Data Analyst will review depth of cover database and/or spreadsheets, if
available, to determine depth of cover and land use for each identified top‐side dent.
12.4 Pipeline Integrity Engineer will:
12.4.1. Add top‐side dents located in cultivation with depth of cover less than 18” to the Dig List
for investigation.
12.4.2. Add top‐side dents where no depth of cover information is available to the Dig List as
“stake only” digs to determine land use and depth of cover. Further investigation of
these features may be necessary pending land use and depth of cover information.

<<<PAGE 784>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 9 of 17
13.0 PROJECTED CORROSION GROWTH ANALYSIS
13.1 13.2 13.3 13.4 13.5 13.6 13.7 Pipeline Integrity Engineer will analyze metal loss indications to establish a re‐assessment
interval based on projected corrosion growth (PCG). Pipeline Integrity Engineer will:
13.1.1. Create PCG analysis spreadsheet and input vital pipeline and ILI data for each metal loss
anomaly and corrosion growth time period (typically 6.2 years)
13.1.2. Input 110% MOP for line segment
13.1.3. Input year of construction and year of inspection
13.1.4. Calculate PCG rate for each metal loss anomaly assuming linear corrosion growth
starting at time of construction based on the following formula where d/t is depth of
metal loss (percentage of wall thickness) as reported by ILI tool.
PCG rate = Reported (d/t) / Years
Where multiple inspections have been conducted utilizing like technologies, Pipeline Integrity
Engineer will calculate a run comparison PCG rate for each metal loss anomaly with a reported
peak depth ≥ 25% wall thickness by comparing current reported peak depth with a previous
reported peak depth and dividing by years between inspections.
13.2.1. Pipeline Integrity Engineer will input run comparison PCG rate into a separate run
comparison projected corrosion growth analysis spreadsheet.
13.2.2. For features indicating “Consider Remediation”, Pipeline Integrity Engineer will contact
previous run Vendor to verify feature sizing. Revised feature sizing will be updated in
the run comparison spreadsheet and a new PCG rate will be calculated.
13.2.3. For features indicating a10 mils per year or greater PCG rate, Pipeline Integrity Engineer
will contact previous run Vendor to verify feature sizing. Revised feature sizing will be
updated in the run comparison spreadsheet and a new PCG rate will be calculated.
Pipeline Integrity Engineer will calculate a 6.2‐year projected depth of corrosion, (d/t) Projected,
based on the following formula. This assessment can also be performed for intervals other than
6.2‐years but (d/t) cannot exceed 1.00 (i.e., depth exceeds wall thickness).
(d/t) Projected = (d/t) Reported + 6.2*PCG rate
Pipeline Integrity Engineer will calculate PBURST based on (d/t) Projected and add metal loss
indications for which PBURST is less than 110% MOP to DPP analysis spreadsheet. DPP analysis will
be conducted as described in Discrete Point Pressure Analysis section.
Pipeline Integrity Engineer will consider adding to Dig List metal loss anomalies for which (d/t)
Projected exceeds 80% wall thickness.
Pipeline Integrity Engineer will consider adding to Dig List metal loss anomalies for which the PCG
rate is 10 mils per year or greater.
Assets Covered Per Mitigation Plan
13.7.1. Identify locations where (d/t) Projected exceeds 70% wall thickness and consider adding
to Dig List.
14.0 CALIBRATION DIGS
14.1 If deemed necessary by the Company and/or Vendor, Pipeline Integrity Engineer will add
calibration investigations of potential anomalies to Dig List in order to confirm performance of
the ILI tool as described in Correlation and Tool Tolerance Assessment Section.

<<<PAGE 785>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 10 of 17
14.2 When possible, Pipeline Integrity Engineer will add to Dig List a minimum of one calibration
investigation in seamless pipe.
15.0 DIG LIST
15.1 15.2 15.3 15.4 15.5 15.6 15.7 15.8 Pipeline Integrity Engineer will create dig List and include the following:
15.1.1. Immediate conditions and preliminary digs performed prior to receipt of Final
Report.
15.1.2. Integrity Conditions (HCA and non‐HCA)
15.1.3. DPP features identified through DPP Analysis
15.1.4. “Features > 50%” located at foreign crossings, in an area of general corrosion, or
any areas that affect a girth weld.
15.1.5. Potential crack‐like anomalies, including SFWA, SFWB, ASWML, and SWD and other
features identified through Seam Weld Assessment
15.1.6. Laminations and other features identified through section 10 of the Ultrasonic Wall
Measurement Assessment
15.1.7. Casings identified through Casing Analysis
15.1.8. Dents identified through Dent Review
15.1.9. Metal loss features identified through Projected Corrosion Growth Analysis
15.1.10. Calibration Digs
Pipeline Integrity Engineer will compare proposed Dig List to information from previous
rehabilitation projects for locations where anomalies have been previously investigated
and will consider eliminating these anomalies from Dig List.
Pipeline Integrity Engineer will mark digs in Final Report and document appropriate
comments for dig list.
Pipeline Integrity Engineer will give Final Report and proposed Dig List to Supervisor of
Pipeline Integrity Engineering or Manager Asset Integrity for review.
Supervisor of Pipeline Integrity Engineering or Manager of Asset Integrity will review ILI
Final Report and proposed Dig List, including:
15.5.1. External metal loss indications reported inside casings
15.5.2. Potential interactions of metal loss indications reported in seamless pipe
15.5.3. Past ILI records and dig results, leak history, corrosion growth analysis, and
previous Executive Summary of Risk Analysis.
15.5.4. Send approval of proposed dig list with any additional proposed digs, if
applicable, to Pipeline Integrity Engineer.
Pipeline Integrity Engineer will incorporate changes requested by Supervisor of Pipeline
Integrity Engineering or Manager of Asset Integrity.
Pipeline Integrity Engineer will contact Vendor to manually verify location and feature
sizing of dig list features. Vendor comments may be added to the dig list.
Pipeline Integrity Data Analyst will create dig sheets using Procedure for Creating Dig
Sheets.

<<<PAGE 786>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 11 of 17
16.0 ILI SUMMARY DOCUMENTS
16.1 Pipeline Integrity Engineer will complete ILI Summary document.
17.0 CORRELATION AND TOOL TOLERANCE ASSESSMENT
17.1 17.2 17.3 17.4 17.5 When inspecting potential anomalies in the field, NDE contractor and Pipeline Integrity
Coordinator will use their best efforts to try to understand how/why ILI tool reported
various defects observed in the field and will capture this in Pipeline Maintenance Report.
Pipeline Integrity Coordinator should be consulted and discrepancies should be resolved
in the field before coating and backfilling when possible.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will review NDE reports and
compare ILI reported anomaly dimensions to actual defect dimensions observed in the
field.
17.2.1. Comparisons will be used to develop a depth unity plot and data correlation
report for each ILI run.
17.2.2. Anomalies to be correlated will include detectible metal loss, SWFA, SWFB,
ASWML, SWML and ID reductions.
For Assets Subject to Company Consent Decree Effective 9/4/08,
17.3.1. Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will complete
comparison described above within three (3) months following completion of
anomaly investigations associated with each ILI run. Comparison will include a
statistically valid number of anomalies.
17.3.1.1. For ILI runs where an insufficient number of anomalies are identified
to perform a statistically valid comparison analysis, anomaly
comparisons may include other indications such as casings, girth
welds, previous repairs, and other pipeline appurtenances. In these
instances, Pipeline Integrity Engineer or Pipeline Integrity Data
Analyst will document actual versus predicted indication
characteristics for each ILI run.
17.3.2. Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will develop two (2)
sets of unity plots (length of axial oriented anomaly and depth into pipe wall)
within three (3) months following completion of anomaly investigations
associated with each ILI run intended to inspect ERW longitudinal seam weld.
17.3.2.1. ILI cracks/anomalies include detectible seam weld and HAZ features
and indications
17.3.2.2. For ILI runs where an insufficient number of seam and HAZ
anomalies are identified to perform a statistically valid comparison
analysis, anomaly comparisons may include other indications. In
these instances, Pipeline Integrity Engineer or Pipeline Integrity Data
Analyst will document actual versus predicted indication
characteristics for each ILI run.
Pipeline Integrity Engineer will review unity plots and data correlation reports and will
consider additional excavations, regrading, engineering evaluation assessments, or re-
running ILI tool if observed defect sizes are consistently outside of Vendor specified
tolerances.
If comparison described above suggests that Vendor undersized (or “undercalled”, as in
anomalies were observed to be more severe than predicted) anomalies, Pipeline Integrity
Engineer will take tool tolerances into account to recalculate corrosion growth rate and

<<<PAGE 787>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 12 of 17
consider requesting Vendor regrade data, performing any necessary additional digs, or
refining reassessment interval.
17.5.1. A statistically valid representation of investigated anomalies must be present in
order to determine undersize percentages. Outlying investigated features may
be discounted.
17.5.2. For metal loss,
17.5.2.1. Add average undersize percentage of anomalies that were
undersized to peak depth of uninvestigated metal loss anomalies in
Projected Corrosion Growth spreadsheet.
17.5.2.2. Recalculate corrosion growth rate
17.5.2.3. 17.5.2.4. Recalculate PBURST and PSAFE to compare with PDPP
If, within 6.2 years, an unrepaired metal loss feature is predicted to
reach 80% peak depth (70% peak depth for Assets Covered Per
Mitigation Plan) or if PBURST is predicted to be less than PDPP, it
should be added to Dig List.
17.5.3. For ID reductions,
17.6 17.7 17.8 17.9 17.5.3.1. If the comparison indicates an average undersize of features, add
average undersize percentage of all anomalies to depth of
uninvestigated ID reductions
17.5.3.2. Compare new depth to repair criteria and add ID reductions meeting
repair criteria to Dig List.
Pipeline Integrity Engineer may consider a Probability of Exceedance (POE) analysis
(required for Assets Covered Per Mitigation Plan) or other engineering analysis as an
alternative means to assess tool tolerances in order to determine if additional direct
examinations are required.
17.6.1. When direct examination activities result in a statistically significant sample size
of observed defects, actual tool performance will be used. Otherwise, Vendor
specified tolerance may be used.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will summarize examination
results from Pipeline Maintenance Report and NDE sheets and create a data correlation
report. Significant discrepancies should be resolved by Vendor and by NDE contractor.
Pipeline Integrity Engineer will provide completed data correlation report to Vendor.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will notify Supervisor of
Pipeline Integrity Engineering that data correlation, unity plots and projected corrosion
growth are complete and that additional digs are/are not necessary.
18.0 DEFINITIONS
18.1 Terms and terminology will be used in accordance with API 1163 Section 4, unless otherwise
specified herein. Additional definitions are as follows:
18.1.1. Seam Weld Feature A (SWFA): Seam weld indication that exhibits possible “crack‐
like” characteristics
18.1.2. Seam Weld Feature B (SWFB): Seam weld indication that exhibits some, but not all
“crack‐like” characteristics
18.1.3. Seam Weld Metal Loss: SWML. Metal loss indication (including any part of a cluster)

<<<PAGE 788>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 13 of 17
18.1.4. 18.1.5. 18.1.6. 18.1.7. 18.1.8. 18.1.9. 18.1.10. that encroaches upon the longitudinal seam weld (LSW).
Axial Seam Weld Metal Loss (ASWML): Metal loss indication (including any part of a
cluster) that encroaches upon the LSW and is less than 2‐inches wide with a length‐
to‐width aspect ratio equal to or greater than 5:1
Seam Weld Deformation (SWD): Deformation that encroaches upon the LSW
Seam Weld Anomaly (SWA): Feature other than a SWFA, SWFB, SWML, or SWD that
encroaches upon or is immediately adjacent to the LSW and is thought to be non‐
injurious.
PBURST: Estimated burst (failure) pressure for an anomaly as calculated according to a
given standard or practice (e.g., RSTRENG™, ASME B31G, CorLAS™)
PSAFE: PBURST multiplied by a design factor (e.g., 0.72)
PDPP: Discrete point operating pressure at a given location
Design Factor, F: from ASME B31.4, ASME B31.8, or ASME B31.11. For onshore
hazardous liquid pipelines, F is typically equal to 0.72. For natural gas pipelines, F
ranges from 0.40 to 0.72 depending on class location
19.0 REFERENCES
19.1 Regulatory
19.1.1. 49 CFR Part 195.452
19.2 Related Policies/Procedures
19.2.1. In‐Line Technical Specification
19.2.2. ILI Data Verification Guidelines
19.2.3. AGM Verification Guideline
19.2.4. 19.2.5. In‐Line Inspection Procedure
Procedure for Creating Dig Sheets

<<<PAGE 789>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 14 of 17
System Integrity Plan Change Log
Date Change Location Change By Approved By 11/08/04 All Clyde Clausen Mike Pearson 11/04/05 All Clyde Clausen Mike Pearson 10/30/2006 All Clyde Clausen Mike Pearson 10/30/2006 2.4.1.2
Mike Pearson Larry Franklin
10/30/2006 2.4.1.19 Dennis Vasicek Mike Pearson 10/30/2006 2.4.1.20
Mike Pearson Dennis Vasicek
10/30/2006 2.4.1.22
Mike Pearson Larry Franklin
10/30/2006 2.4.1
Mike Pearson Larry Franklin
10/30/2006 2.4
Mike Pearson Dennis Vasicek
10/30/2006 2.7.1
Mike Pearson Larry Franklin
10/30/2006 2.7.1 Larry Franklin Mike Pearson 10/30/2006 2.7.1.6
Mike Pearson Larry Franklin
10/30/2006 2.9.1
Mike Pearson Larry Franklin
10/30/2006 2.9.1
Mike Pearson Larry Franklin
10/30/2006 2.9.1.2 Larry Franklin Mike Pearson 10/30/2006 2.9.1 Larry Franklin Mike Pearson 10/30/2006 2.10.1.1
Mike Pearson Larry Franklin
10/31/2006 2.4.1.32.3.10 Larry Franklin Mike Pearson 10/31/2006 2.4.1.33 Larry Franklin Mike Pearson 10/31/2006 2.4.1.34 Larry Franklin Mike Pearson Brief Description of Change
Created New Procedure
Conducted Annual Review
Conduct Annual Review
Added Certification of Calibration and Street Atlas
files
Added “with metal loss”
Added “If ILI vendor does not provide GPS
Coordinates”
Modified to reflect send email to Pipeline Integrity
Data Coordinator
Insert 2.4.1.24 Determine casings that require
rehabilitation based on casing flowchart
Insert 2.4.16 Compare proposed dig list to
information from previous rehabilitation projects
Insert 2.7.1.4 Process casings using ‘Casing
Comparison’ spreadsheet
Delete 2.7.1.5
Minor modification to paragraph, add link to
Rehab book Checklist
2.9.1.1 Insert Receive ‘Casing Comparison’ from
PIDC
Minor modification to 2.9.1.2 to add ‘Casing
Comparison’ comparison
Delete 2.9.1.1.1 through 2.9.1.1.3
Insert 2.9.1.3
Added “if ILI vendor does not provide GPS
coordinates”
Insert 2.4.1.32.3.10
Insert 2.4.1.33
Insert 2.4.1.34

<<<PAGE 790>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 15 of 17
01/01/08 7/10/08 2.2.1.5 Dennis Vasicek Clyde Clausen 7/10/08 2.2.1.6 Dennis Vasicek Clyde Clausen 7/10/08 2.2.1.7 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.4.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.5 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.6 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.18.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.21 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.22 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.30 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.31.3.8 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.31.3.10 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.31.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.1 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.32.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.3 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.6 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.33.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.13 Dennis Vasicek Clyde Clausen Reviewed, no changes
Added paragraph and subparagraphs
Added paragraph
Added paragraph
Added paragraph
Added paragraph
Changed 5 years to 6 years
Added paragraph
Added paragraph
Added paragraph
Changed 100% to 80%
Deleted paragraph and sub‐paragraphs pertaining
to sending email to GIS Coordinator to input GPS
information for casings
Deleted paragraph about receiving GPS
coordinators for casings from GIS Coordinator
Added sentence to clarify 60 and 180‐day dates
for HCAs
Added, “(as identified by the ILI vendor as being
axially oriented)”
Removed condition, “A girth weld anomaly as
identified by ILI vendor”
Added paragraph and subparagraphs
Added sentence, “However, all HCA Immediate
Conditions shall take priority.”
Added paragraph and subparagraphs
Added paragraph
Added paragraph and subparagraphs
Added paragraph and subparagraph
Modified paragraph
Modified paragraph and added subparagraphs

<<<PAGE 791>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 16 of 17
7/10/08 2.4.14.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.14.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.15 Dennis Vasicek Clyde Clausen 7/10/08 2.4.16 Dennis Vasicek Clyde Clausen 7/10/08 2.4.17 Dennis Vasicek Clyde Clausen 7/10/08 2.4.23 Dennis Vasicek Clyde Clausen 7/10/08 2.4.24 Dennis Vasicek Clyde Clausen 7/10/08 2.4.25 Dennis Vasicek Clyde Clausen 7/10/08 2.4.26 Dennis Vasicek Clyde Clausen 7/10/08 2.4.30 Dennis Vasicek Clyde Clausen 7/10/08 2.4.31 Dennis Vasicek Clyde Clausen 7/10/08 2.4.31 Dennis Vasicek Clyde Clausen
7/10/08 2.7.1.8 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.9 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.10 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.11 Dennis Vasicek Clyde Clausen 7/10/08 2.10 Dennis Vasicek Clyde Clausen
7/10/08 2.10 Dennis Vasicek Clyde Clausen
Reworded paragraph
Reworded paragraph
Added paragraph
Added paragraph and subparagraphs
Modified paragraph
Added paragraph
Added paragraph
Added paragraph
Removed Area Facility Integrity Engineer and
added Supervisor Corrosion Control
Added paragraph
Deleted paragraph about Post Job roundtable
Added paragraph and sub‐paragraphs about
calculating the average undersize of repaired
anomalies
Added paragraph
Added paragraph
Added paragraph
Added paragraph
Removed section containing “The GIS Coordinator
shall:”
Added section pertaining to “Pipeline Integrity
Coordinator” and three subparagraphs
7/10/08 2.11 Dennis Vasicek Clyde Clausen
12/19/08 2.4.1.9.2 Dennis Vasicek Clyde Clausen 12/19/08 2.4.14.2 Dennis Vasicek Clyde Clausen Added section pertaining to “Supervisor Pipeline
Integrity or Manager Pipeline Integrity” and four
subparagraphs
Removed reference to LAPA RPR’s
Added reference to UT ILI
12/19/08 2.4.14.2.1 Dennis Vasicek Clyde Clausen 12/22/08 Global Dennis Vasicek Clyde Clausen Added, “and match girth welds between the
reports”
Changed “vendor” to “service provider”

<<<PAGE 792>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 17 of 17
12/22/08 2.4.1.31.4 Dennis Vasicek Clyde Clausen
12/22/08 2.4.1.32.6 Dennis Vasicek Clyde Clausen
12/22/08 Dennis Vasicek Clyde Clausen 3/4/09 All Dennis Vasicek Clyde Clausen
01/01/10 2.2.1.1 all All
2.4.1.8 (Old) 2.4.1.8 (new) 2.4.1.12.3 2.4.1.12.4 2.4.1.12.5/2.4.1.13/
2.4.1.14/2.4.1.16
2.4.1.21 – 2.4.1.24 2.4.1.25‐2.4.1.30 60‐day repair
cond/180 day/ Non
HCAS
2.4.14.1 – 2.4.14.2.4 2.4.15/2.4.20‐2.4.22 01/01/11 9/1/11 All Clyde Clausen Doug Chabino 12/31/11 all
12/31/11 All 6/18/12 10.2.5 Clyde Clausen Doug Chabino
Deleted section referencing expired Consent
Decree (for acquired Shell assets)
Deleted section referencing expired Consent
Decree (for acquired Shell assets)
Conducted annual review
Added references to consent decree – not a
significant change so version not updated
Added “internal diameter”
Changed Longhorn to Mitigation Plan
General cleanup/updating to reflect current
process
Deleted: ref – Pipeline Listing ss
Reworded DPP information
Added “add to DPP ss.
Added – create Run Comparison ss
deleted
Deleted
Moved after dig list
Dents at 4/8 o’clock changed to top‐side dents/
bottom side dents
Deleted
Deleted
Reviewed, no changes
Re‐worked and Re‐formatted entire
document
Replaced Rehab Book Checklist with
Project File Index Form and AGM Calc
Spreadsheet with Total AGMs Form
2012 Annual Review complete
Added Laminations interacting with
deformations to section 10.2.5

<<<PAGE 793>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 18 of 17

<<<PAGE 794>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL SIP–ADM–7.04
Asset Integrity 09/06/11 Revision: 7 Page 1 of 6
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity by establishing a consistent and
effective corrosion control process.
2.0 DESCRIPTION
2.1 This initiative outlines the standards and processes necessary to mitigate external and internal
corrosion. These include, but are not limited to, the following: system evaluations; coating
selection and application; criteria for cathodic protection; and cathodic protection system design,
installation, operations and maintenance to mitigate external corrosion and cleaning, treating
and monitoring the pipeline for the prevention of internal corrosion.
2.2 All of the standards are developed through sound corrosion engineering concepts and are
applied under the direction of qualified personnel trained in the corrosion control field.
Corrosion related data will be processed in the overall Risk Management process to
determine/modify the frequency of future inspections, surveys and other corrosion mitigation
measures or new developing technologies.
3.0 STANDARDS
3.1 The Manager of Asset Integrity shall:
3.1.1 Maintain the Corrosion Control Program for Company operated assets.
3.1.2 Coordinate the implementation, execution, and documentation of the work required by
the Corrosion Control Program.
3.1.3 Monthly review corrosion control exceptions and associated remedial action plans.
3.2 The Corrosion Technician shall:
3.2.1 Execute and document the work required by the Corrosion Control Program including
Pipe‐to‐Soil Potential Surveys, Close Interval Surveys, Atmospheric Corrosion
Inspections, Insulating Flanges, Foreign Line Crossings, Rectifier Inspection Surveys,
Bond Surveys, Remedial Actions, etc.
3.3 The Operations Supervisor shall:
3.3.1 Coordinate the execution of pipeline maintenance/cleaning pigging in accordance with
the Corrosion Control Program.
3.3.2 Coordinate the inspection of additive/corrosion inhibitor pumps for proper operation and
injection rate and ensure that prompt and proper repairs are made. Maintain corrosion
inhibitor chemical inventories at proper levels.
3.3.3 Coordinate the collection and delivery of product samples to the Company’s laboratory
for analysis in accordance with the Corrosion Control Program.
3.3.4 Coordinate the installation, removal, and replacement of internal corrosion coupons in
accordance with the Corrosion Control Program.
3.4 The Supervisor of Laboratory Testing shall:

<<<PAGE 795>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL SIP–ADM–7.04
Asset Integrity 09/06/11 Revision: 7 Page 2 of 6
3.4.1 Distribute, collect, analyze, and document internal corrosion coupons in accordance with
the Corrosion Control Program.
3.4.2 Analyze and document product samples per the Corrosion Control Program.
3.5 The Supervisor of Quality Control shall:
3.5.1 Notify the Corrosion Specialist when internal product quality tests identify free water,
Haze Rating >3, or NACE Corrosion Rating <C.
3.6 The Quality Control Program Consultant shall:
3.6.1 Notify the Corrosion Specialist when external product quality tests identify free water,
Haze >3, or NACE Rating <C.
3.7 The Corrosion Specialist shall:
3.7.1 Identify and maintain a list of Internal Corrosion Coupon Monitoring and Inhibitor
Injection Locations.
Review internal corrosion coupon, product quality control reports (PQCR), and product
sampling data to identify/investigate exceptions per criteria established in the Corrosion
Control Program.
Conduct analysis and recommend internal corrosion coupon monitoring, product
sampling, and inhibitor injection locations for new, existing, acquired, or otherwise
modified pipeline sections.
Review and update the internal corrosion coupon, product sampling, and inhibitor
injection tasks in the Preventative Maintenance Manual.
3.7.2 3.7.3 3.7.4

<<<PAGE 796>>>

Date 07/03/02 9/29/03 9/29/03
9/29/03 9/29/03
9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 Magellan Midstream Partners, L.P.
CORROSION CONTROL SIP–ADM–7.04
Asset Integrity 09/06/11 Revision: 7 Page 3 of 6
System Integrity Plan Change Log
Change
Location
Changed By Approved By Brief Description of Change
Rick
5.3
Wooldridg
Michael
Pearson
Added Cathodic Protection Exception Report measure.
e
Modified 2.1 with the underlined language to address the
addition of internal corrosion issues: This initiative outlines
the Standards and processes necessary to mitigate external
and internal corrosion. These include but are not limited
Rick
2.1
Wooldridg
Michael
Pearson
e
to: system evaluations; coating selection and application;
criteria for cathodic protection; and cathodic protection
system design, installation, operations and maintenance to
mitigate external corrosion and cleaning, treating and
monitoring the pipeline for the prevention of internal
corrosion.
Initiative
Name and
1.1
Rick
Michael
Pearson
Deleted “External” from “External Corrosion Control” to
broaden the SIP to include Internal Corrosion issues.
Wooldridge
Rick
3.1
Wooldridge
Michael
Pearson
Changed “Supervisor of Pipeline Integrity” to
“Manger of Asset Integrity” to address title changes.
3.1.1,
3.2.1,
3.2.2, and
5.1
Rick
Wooldridge
Michael
Pearson
Changed “External Corrosion Control Program” to
“Corrosion Control Program” in order to include
Internal Corrosion issues.
Rick
3.1.1
Wooldridge
Michael
Pearson
Removed “or exceed the” to not require compliance plus
Rick
3.2.3
Wooldridge
Michael
Pearson
Deleted entire paragraph as it will be addressed in 3.2.1,
Produce an annual Atmospheric Corrosion Report……
Rick
3.2.2
Wooldridge
Michael
Pearson
Replaced “Cathodic Protection” with “Corrosion Control” in
order to address the addition of internal corrosion issues
Rick
3.2.2
Wooldridge
Michael
Pearson
Changed “Manager of Pipeline Integrity” to “Manager of
Asset Integrity” to address title changes.
Rick
3.2.2
Wooldridge
Michael
Pearson
Remove “and/or shorted casings” since shorted casings are
addressed during integrity assessments and not as stand
alone corrosion exceptions.
Rick
3.2.2
Wooldridge
Michael
Pearson
Added “exposed pipe and interface areas requiring
paint/coating and internal corrosion rates exceeding the
established threshold” in order to include atmospheric and
internal corrosion exceptions as part of the new Corrosion
Control SIP.
3.4 Rick Michael Added: “The Manager of Operations Shall” from the

<<<PAGE 797>>>

9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/29/03 9/30/03 Magellan Midstream Partners, L.P.
CORROSION CONTROL SIP–ADM–7.04
Asset Integrity 09/06/11 Revision: 7 Page 4 of 6
Wooldridge Pearson original Internal Corrosion Control SIP document.
Rick
3.4.1
Wooldridge
Michael
Pearson
Added: “Execute the maintenance/cleaning pigging
program according to O&M Procedures”.
Deleted: “and ensure that any batch treatments are
completed within the system's program frequency
guidelines. Complete pigging reports and submit to the
Corrosion Technician” from the original Internal Corrosion
Control SIP document.
Rick
3.4.2
Wooldridge
Michael
Pearson
Added: “3.4.2 Perform monthly inspection of Inspect
additive corrosion inhibitor pumps for proper operation
and injection rate monthly and assure ensure that prompt
and proper repairs are made. Maintain corrosion inhibitor
chemical inventories at proper levels. Deleted: “Assure that
proper repairs are made or that the Corrosion Technician is
contacted immediately. Complete the Chemical Injection
Check list and submit copies to the Corrosion Technician
and Corrosion Control Specialist” from the original Internal
Corrosion Control SIP document since it is no longer
applicable.
Rick
3.4.3
Wooldridge
Michael
Pearson
Added: “Collect samples associated with pigging runs and
handle according to O&M Procedures” from the original
Internal Corrosion Control SIP document.
Replaced: “Internal Corrosion Control Program” with
“O&M Procedures” to reflect MMP processes (as opposed
to WMB Midstream).
Rick
4.1
Wooldridge
Michael
Pearson
Replaced: “Protection Exceptions” with “Corrosion
Control Exceptions” to add clarity.
Rick
4.2
Wooldridge
Michael
Pearson
Deleted: “Atmospheric Corrosion Exceptions” as they
are included in 4.1
Rick
4.3
Wooldridge
Michael
Pearson
Added: “Pipeline releases related to corrosion” since
eliminating it is the primary goal
5.2
Rick
Wooldridge
Michael
Pearson
Added: “O&M Maintenance/Cleaning Pigging Procedures”
5.3
Rick
Wooldridge
Michael
Pearson
Added: “O&M Product Sampling Procedures”
Rick
3.2.1
Wooldridge
Michael
Pearson
Added: “Coordinate the implementation, execution and
documentation of the work required by the External
Corrosion Control Program” in order to clarify the roles and
responsibilities of the Supervisor.
Rick
3.3.1
Wooldridge
Michael
Pearson
Added: “Execute and document” to imply
performance of work.
3.4.4 Rick Michael Added: “Install, remove, replace, and process internal

<<<PAGE 798>>>

9/30/03 10/6/03 8/11/04 8/11/04 10/16/06 10/16/06 10/16/06 09/11/07 9/10/07 9/10/07 9/10/07 9/10/07 1/1/09 7/17/09 11/16/09 Magellan Midstream Partners, L.P.
CORROSION CONTROL Asset Integrity 09/06/11 Wooldridge Pearson Rick
5.4
Wooldridge
Michael
Pearson
Annual
Review
Michael
Pearson
Michael
Pearson
Rick
3.4
Wooldridge
Michael
Pearson
Rick
3.5
Wooldridg
Michael
Pearson
e
Rick
3.5
Wooldridge
Michael
Pearson
Rick
3.6
Wooldridge
Michael
Pearson
Rick
3.6
Wooldridge
Michael
Pearson
Rick
ALL
Wooldridge
Michael
Pearson
Rick
3.1.3
Wooldridge
Michael
Pearson
Rick
3.1
Wooldridge
Michael
Pearson
Rick
3.2.1
Wooldridge
Michael
Pearson
Rick
3.2.2
Wooldridge
Michael
Pearson
All E7
Rick
Wooldridge
3.5.2
Rick
Wooldridge Larry Davied
All E7
Rick
Wooldridge
SIP–ADM–7.04
Revision: 7 Page 5 of 6
corrosion coupons in accordance with O&M
procedures.”
Added: “O&M Internal Corrosion Coupon Procedures”
Conduct annual review of the Corrosion Control SIP in
accordance to 3.1.1
Changed “Manager” to “Supervisor”
Conduct annual review of the Corrosion Control SIP in
accordance to 3.1.1
Added responsibilities for the Supervisor Laboratory
Testing
Added responsibilities for the Corrosion Specialist
Conducted 2006 annual review of the Corrosion Control SIP
in accordance to 3.1.1 (see change log)
Conducted 2007 annual review, (see change log)
Replaced Produce an annual Corrosion Control Exception
Report, along with associated Remedial Action Plan, and
forward to the Director of Asset Integrity with Annually
review corrosion control exceptions and associated
remedial action plans.
Added Manager deleted Supervisor
Added “Remedial Actions”
Deleted Conduct detailed analyses of all available
Corrosion Control Program data within their area of
responsibility. Provide a summary of findings, including
associated recommendations for remedial action, to the
Corrosion Specialist within 90 days following completion of
the surveys.
2008 annual review complete – no changes
Added: “product quality control reports (PQCR)”
2009 annual review complete – with minor clean‐up issues.

<<<PAGE 799>>>

8/9/10 9/6/11 CORROSION CONTROL Asset Integrity All; 3.5, 3.6 E7
Rick
3.1.3
Wooldridge
Magellan Midstream Partners, L.P.
SIP–ADM–7.04
09/06/11 Revision: 7 Page 6 of 6
Rick
Wooldridge
2010 annual review; Added 3.5 and 3.6 Responsibilities for
the Supervisor of Quality Control and Program Consultant
to further enhance notifications when off spec product is
present in the pipeline…as required per the DOT advisory
related to internal corrosion.
Rick
Wooldridge
Changed annual to monthly to reflect actual practice

<<<PAGE 800>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 1 of 27
TABLE OF CONTENTS
1.0 SCOPE
2.0 EXTERNAL CORROSION CONTROL
2.1 External Coating
2.2 Cathodic Protection
2.3 Corrosion Control Criteria
2.4 IR Drop Consideration
2.5 New Construction
2.6 Cathodic Protection Surveys
2.7 Cathodic Protection Rectifiers
2.8 Foreign Crossings and Interference Currents
2.9 Electrical Isolation
2.10 Test Leads
2.11 Exposed Pipe Examination
2.12 Stress Corrosion Cracking Analysis
2.13 Microbiological Influenced Corrosion (MIC)
2.14 Induced AC Corrosion
3.0 ATMOSPHERIC CORROSION CONTROL
3.1 Inspection
3.2 Paint/Coating
4.0 INTERNAL CORROSION CONTROL
4.1 Introduction
4.2 Product Evaluation
4.3 Internal Corrosion Mitigation
4.4 Internal Corrosion Monitoring
4.5 Internal Examination

<<<PAGE 801>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 2 of 27
5.0 QUALIFICATION
5.1 Supervisor
5.2 Operator Qualification
6.0 CORROSION CONTROL RECORDS
7.0 INTEGRITY MANAGEMENT PLAN INTEGRATION
8.0 DEFICIENCIES IN CORROSION CONTROL

<<<PAGE 802>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 3 of 27
1.0 SCOPE
1.1 This program is applicable to federal and/or state jurisdictional pipelines and/or
facilities. Elements of this program may be used in whole or part on non‐jurisdictional
assets as deemed appropriate.
1.2 Texas Specific: In addition to applicable Federal, State, and Local regulations, as well as,
Magellan guidelines, process, or best practices, certain pipeline system assets in Texas
operate under the requirements of the Mitigation Plan.
2.0 EXTERNAL CORROSION CONTROL
2.1 External Coating 195.557, 195.559, 195.561, 16 TAC 8.305(2‐3), 192.455(a)(1) and
192.461.
2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 All buried or submerged newly constructed, relocated, replaced or otherwise
changed steel lines shall be coated, including mainlines, terminal and station
piping.
The external coating shall be applied on a properly prepared surface and have
sufficient adhesion to the metal surface to effectively resist underfilm
migration of moisture.
The coating shall be sufficiently ductile to resist cracking and have sufficient
strength to resist damage due to handling and soil stress.
The coating shall have properties compatible with the cathodic protection
system.
Electrically insulating type coatings shall have low moisture absorption and
high electrical resistance.
The coated pipe shall be electrically inspected using a coating deficiency
(holiday) detector prior to installation. Any damage found that impairs the
effectiveness of the coating shall be repaired. Furthermore, the coating shall
be protected from damage resulting from adverse ditch conditions or damage
from supporting blocks.
Backfilling operations will be inspected to ensure that rocks, hard lumps of
earth, etc. are not backfilled directly onto the pipe where they may damage
the effectiveness of the pipeline coating.
Precautions will be taken to minimize damage to the coating during
installation if coated pipe is installed by boring, driving, or other similar
method.

<<<PAGE 803>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 4 of 27
2.2 2.1.9 Joints, fittings, and tie‐ins shall be coated with material(s) compatible with the
coating(s) on the pipe.
2.1.10 Coatings selection, application, and maintenance shall be performed as
prescribed in Coatings – Selection, Applications, and Maintenance.
Cathodic Protection – 195.563, 195.565, 192.452, 192.453, 192.455 and 192.457
2.2.1 2.2.2 2.2.3 2.2.4 On facilities including newly constructed, relocated, replaced or otherwise
changed pipelines, a cathodic protection system will be installed to mitigate
corrosion.
A cathodic protection system will be installed for breakout tanks to mitigate
corrosion. The systems shall be installed in accordance with API
Recommended Practice 651, unless noted in this volume why compliance with
all or certain provisions of API Recommended Practice 651 is not necessary for
the safety of the breakout tank. Noted conditions that will cause compliance
with 651 to not be observed may be but are not limited to tanks set on
concrete, asphalt pads, or where studies conducted in accordance with API
653 indicate that corrosion will not affect the safe operation of the tank.
On facilities including newly constructed, relocated, replaced, or otherwise
changed pipelines and tanks, a temporary cathodic system shall be provided
as soon as practical during construction and a permanent cathodic protection
system shall be provided within one year of completed construction.
Refer to Design and Installation of an Impressed Current Deep Groundbed and
Design and Installation of an Impressed Current Surface Groundbed for more
2.3 information.
2.2.5 Soil Resistivity may influence the design considerations for cathodic
protection systems as well as development of the Relative Risk Score for the
line segment. See Soil Resistivity Overview for a general description of
expected soil resistivity identified by state.
Corrosion Control Criteria 195.571, 192.463
2.3.1 Magellan adheres to the cathodic protection regulations in Part 195,
“Transportation of Hazardous Liquids by Pipeline” and to the cathodic
protection regulations in Part 192, “Transportation of Natural and Other Gas
by ”pipeline: Minimum Federal Safety Standards,” of the DOT/Pipeline and
Hazardous Materials Safety Administration Pipeline Safety Regulations.
2.3.2 When practical, Magellan requires maintaining a polarized potential of at least
–0.850 volts as measured between the structure surface and a saturated

<<<PAGE 804>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 5 of 27
2.4 2.3.3 2.3.4 2.3.5 2.3.6 2.3.7 copper‐copper sulfate reference electrode that is in contact with the
electrolyte (earth, soil, water, etc.). Where injurious aerobic bacteria has been
identified, or is suspected, a polarized potential of ‐.950 volts or more
negative is required. This voltage measurement shall be determined with the
protective current applied and IR drop considered as described in paragraph
2.4 below.
Assets covered by the Mitigation Plan: For Tier II and Tier III areas, where
practical a polarized pipe‐to‐soil potential of ‐.850 volts will be maintained.
During close interval surveys, potential drops other than those across the
structure to electrolyte boundary will be considered by interrupting the
cathodic protection current source(s) and recording the ON” and “OFF” pipe‐
to‐soil potentials Once established, the “ON” potential and “Off” potential will
be utilized to correct future pipe‐to‐soil potential readings until such time as
the system configuration or coating condition changes, or a new close interval
survey is performed.
When a ‐0.850 volt potential is not practical, the following criteria are
acceptable when approved by the Supervisor of Corrosion Control:
2.3.4.1 A minimum negative (cathodic) polarization shift of 100 millivolts
The 100‐millivolt polarization decay criteria specify a minimum negative
(cathodic) polarization voltage shift of 100 millivolts, measured between the
structure surface and a reference electrode contacting the electrolyte.
Overprotection will be monitored and minimized through the analysis of data
from annual pipe‐to‐soil surveys, close interval surveys, and pipeline visual
inspections. A practical value of ‐1.2 volts (polarized) in reference to a
copper/copper sulfate electrode will be used as value beyond which
monitoring for overprotection shall be considered.
Refer to Cathodic Protection Criteria for more information.
IR Drop Consideration 195.571 and 192.463 (a)
2.4.1 IR drop is considered by taking potential readings directly over or as near as
practical to the structure surface. The affect on the potential measuring circuit
is kept to a minimum by using a high resistance voltmeter and being mindful
of lead lengths and condition, contact to structure and contact to electrolyte.
2.4.2 Cathodic protection level should be evaluated utilizing Cathodic Protection
Criteria.
2.5 New Construction 195.563 and 192.455(a)(2)

<<<PAGE 805>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 6 of 27
2.6 2.5.1 On newly constructed facilities and/or pipelines, a temporary cathodic system
shall be provided as soon as practical during construction and a permanent
cathodic protection system shall be provided within one year of completed
construction.
2.5.2 Newly constructed facilities shall be included in and be managed in
accordance with the Magellan System Integrity Plan within one year of
completed construction.
2.5.3 On newly constructed facilities and/or pipelines, corrosion personnel,
qualified under the Operator Qualification Ruling or with NACE Certification,
shall be utilized to identify, mitigate, and monitor for inadequate cathodic
protection and detrimental interference currents, prior to and during
construction. Refer to Section 2.8, Foreign Crossings and Interference
Currents and 2.14, Induced AC Corrosion below.
Cathodic Protection Surveys 195.573 (a) (d) and 192.465
2.6.1 A cathodic protection survey shall be conducted on each buried, in contact
with the ground, submerged pipeline facility, and/or breakout tank in its
pipeline system that is under cathodic protection once each calendar year
with intervals not to exceed fifteen months. Pertinent survey information shall
be recorded in the Cathodic Protection Data Manager (CPDM) within 30 days
after the survey.
2.6.2 Assets covered by the Mitigation Plan: Pipe‐to‐soil surveys shall be performed
annually not to exceed 15 months in Tier I areas and semi‐annually not to
exceed 7.5 months in Tier II and Tier III areas. Deficiencies will be resolved
within one (1) year of discovery, except deficiencies of such a nature they
present a more urgent threat to pipeline integrity, in which case corrections
will be done immediately.
2.6.3 Pipe‐to‐soil readings shall be obtained at pre‐assigned locations identified as
necessary to determine the adequacy of cathodic protection. These locations
can include, but are not limited to, test stations, cased crossings, and above
ground appurtenances. Refer to Measuring a Pipe‐to‐Soil Potential for more
information.
2.6.4 For aboveground breakout tanks where corrosion of the tank bottom is
controlled by a cathodic protection system, the cathodic protection system
shall be inspected to ensure it is operated and maintained in accordance with
API Recommended Practice 651, unless noted in this volume why compliance
with all or certain provisions of API 651 is not necessary for the safety of a

<<<PAGE 806>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 7 of 27
2.6.5 2.6.6 particular breakout tank. Noted conditions that will cause compliance with
651 to not be observed may be but are not limited to tanks set on concrete,
asphalt pads, or where studies conducted in accordance with API 653 indicate
that corrosion will not affect the safe operation of the tank. Pertinent survey
information shall be recorded in the Cathodic Protection Data Manager
(CPDM) within 30 days after the survey.
2.6.4.1 Potential surveys taken on above‐ground storage tanks should be
conducted with an adequate level in the tank to maximize the
contact of the tank bottom with the cushion material. Adequate
level is typically at least 3 feet of liquid. Tank levels shall be
recorded along with potential measurements. Tanks with
inadequate levels shall be re‐surveyed the same calendar year, once
adequate levels are attained.
Additional corrosion control surveys, including but not limited to close interval
pipe‐to‐soil surveys, will be conducted where practical and determined
necessary by sound engineering practices. Indicators of the necessity to
conduct such surveys shall include risk assessments, annual pipe‐to‐soil
surveys, internal inspection data, pipe inspection, or other related corrosion
information or testing.
At a minimum, close interval pipe‐to‐soil surveys will be considered under the
following circumstances:
2.6.6.1 When identified through risk assessment including Section 6
analysis required by the Integrity Management Plan.
2.6.6.2 Assets covered by the Mitigation Plan: Close Interval surveys in Tier
III areas will be conducted annually not to exceed 15 months. For
Tier I and II areas close interval surveys will be managed through the
Relative Risk Assessment Process within the System Integrity Model
and conducted as necessary. Deficiencies will be resolved within
one (1) year of discovery, except deficiencies of such a nature they
present a more urgent threat to pipeline integrity, in which case
corrections will be done immediately.
2.6.6.3 External Corrosion identified on the pipeline with a peak depth
greater than 50% of the nominal wall, within 50 feet of a foreign
pipeline crossing. Close interval survey may not be required if pipe‐
to‐soil data collected at the location indicates that cathodic
protection interference is not a concern.

<<<PAGE 807>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 8 of 27
2.6.6.4 2.6.6.5 2.6.6.6 Areas of inadequate cathodic protection as identified by pipe‐to‐soil
surveys. Close interval survey may not be required if remediation of
the low potentials includes the addition, modification, or
adjustment of an impressed current cathodic protection that
provides cathodic protection current beyond the area of inadequate
potentials.
Areas of interference from a foreign cathodic protection current
source. Locations of potential interference include but are not
limited to, construction of new cathodic protection systems near
the pipeline, changes in current output from foreign cathodic
protection systems, and a reduction in cathodic protection levels
without a corresponding reduction in output from the existing
cathodic protection system.
In each case, the Close Interval Survey shall be conducted at spacing
close enough to identify potential integrity threats and extend
beyond the area of likely influence. Refer to Close Interval Pipe‐to‐
Soil Survey and Testing for Interference Currents and Remedial
Measures for more information.
2.7 Cathodic Protection Rectifiers 195.573 (c) and 192.465 (b)
2.7.1 Each cathodic protection rectifier shall be inspected for proper operation at
least six times each calendar year with intervals between inspections not to
exceed 2 ½ months. Pertinent survey information shall be recorded in the
Cathodic Protection Data Manager (CPDM) within 30 days after survey. Refer
to Rectifier Inspection, Cathodic Protection System Troubleshooting
(Groundbed), and Rectifier Troubleshooting for more information.
2.8 2.7.2 Assets covered by the Mitigation Plan: Each cathodic protection rectifier shall
be inspected for proper operation at least twelve (12) times each calendar
year with intervals between inspections not to exceed 45 days. Deficiencies
will be resolved within one (1) month of discovery, except deficiencies of such
a nature they present a more urgent threat to pipeline integrity, in which case
corrections will be done immediately.
Foreign Crossings and Interference Currents 195.573(c), 195.577, 16 TAC 7.86(5)(c),
192.465 (c) and 192.473
2.8.1 During each cathodic survey, a check of the integrity of each bond that exists
across insulating flanges or other unions of pipeline facilities and each
interference bond shall be made. Reverse current switches, diodes and

<<<PAGE 808>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 9 of 27
interference bonds whose failure would jeopardize structure protection shall
be inspected six times each calendar year with intervals between inspections
not to exceed 2 ½ months. Pertinent survey information shall be recorded in
the Cathodic Protection Data Manager (CPDM) within 30 days after the
survey. Refer to Electrical Bond Inspection for more information.
2.8.2 2.8.3 Impressed current cathodic protection systems or galvanic anode systems will
be designed and installed to minimize any adverse effects on existing
underground metallic structures.
Stray current interference testing, including, but not limited to close interval
pipe‐to‐soil surveys, will be conducted where practical and determined
necessary by sound engineering practices. Indicators of the necessity to
conduct such tests shall include annual pipe‐to‐soil surveys, internal
inspection data, pipe inspection, or other related corrosion information or
testing. Pertinent survey information shall be recorded on Magellan Foreign
Line Interference Test Form. Refer to Testing for Interference Currents and
Remedial Measures for more information.
2.9 2.8.4 Texas Intrastate Pipeline specific: Whenever suspected areas of interference
are identified, testing will be conducted within 6 months to determine the
extent of interference, and appropriate action will be taken.
2.8.5 For Interference Currents related to Induced AC refer to Section 2.14, Induced
AC Corrosion below.
Electrical Isolation 195.575 and 192.467
2.9.1 Each buried or submerged pipeline shall be electrically isolated from other
underground metallic structures, unless the pipeline and the other structures
are electrically interconnected and cathodically protected as a single unit.
2.9.2 One or more insulating devices shall be installed where electrical isolation of a
portion of a pipeline is necessary to facilitate the application of corrosion
control.
2.9.3 During each cathodic survey, a check of the integrity of insulating flanges or
other unions of pipeline facilities shall be made if inadequate cathodic
protection levels are found.
2.9.4 Shorted Casings
2.9.4.1 During each cathodic protection survey, readings may be taken at
each cased crossing to detect any location where the carrier pipe
may be shorted to the casing pipe.

<<<PAGE 809>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 10 of 27
2.9.4.2 2.9.4.3 If the casing potential is greater than ‐.800 volts, the casing shall be
tested to determine whether an electrolytic short to the carrier pipe
is present. Corresponding classification data documenting the status
of the casing shall be recorded in the Cathodic Protection Data
Manager (CPDM). Refer to Shorted Casing Testing for more
information.
If the casing potential is within 100 millivolts of the pipeline
potential, the casing shall be tested to determine whether a short to
the carrier pipe is present. Corresponding classification data
documenting the status of the casing shall be recorded in the
Cathodic Protection Data Manager (CPDM). Refer to Shorted Casing
Testing for more information.
2.9.4.4 Following internal inspection of a pipeline, the resulting smart pig
data will be integrated with and compared to the casing information
in the corrosion control database. Where the carrier pipe within the
casing exhibits corrosion‐caused metal loss, a risk evaluation will be
conducted and action will be taken to mitigate the corrosion if
deemed necessary.
NOTE: For line sections integrity tested by hydrostatic test, a risk
evaluation will be conducted at each shorted casing and action
taken to clear the short and/or mitigate the corrosion if deemed
necessary.
2.9.4.5 2.9.4.6 Assets covered by the Mitigation Plan: If a shorted casing is verified,
a plan of action shall be developed within three (3) months from the
time of discovery. The practicality of clearing the short will be
considered before any other measures are used. Action shall be
taken to clear the short (a) in Tier I areas within six (6) months of
development of the action plan; and (b) in Tier II and III areas within
three (3) months of development of the action plan.
If clearing the short is impractical, the location can be monitored for
leaks, or the casing/pipe interstice may be filled with a high
dielectric corrosion inhibiting material. If the casing is monitored
using leak detection equipment, the test must be performed twice
each calendar year not exceeding 7.5 months. If monitored using
internal inspection (smart pig) equipment, the inspection must be
made at intervals as determined in the Magellan, Integrity
Management Plan. These alternative measures, or any other

<<<PAGE 810>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 11 of 27
2.10 measures approved by the Manager of Asset Integrity may be
employed until it is practical to clear the short.
2.9.4.7 Assets covered by the Mitigation Plan: In the interim, from the time,
a short is verified and action is taken to clear the short, the location
will be inspected for corrosion or the casing /pipe interstice may be
filled with a high dielectric corrosion inhibiting material. During any
interval that a casing has been determined to be shorted, casing will
be monitored. Tier I areas will be monitored twice per year at
intervals not exceeding 7.5 months. Tier II and III areas will be
monitored monthly at intervals not exceeding 6 weeks.
2.9.5 Insulating devices installed in areas where a combustible atmosphere is
reasonable to foresee shall be installed with precautions to prevent arcing.
2.9.6 Pipelines in close proximity to electrical transmission tower footings, ground
cables, or counterpoise, or in other areas where it is reasonable to foresee
fault currents or an unusual risk of lightning, shall be protected against
damage from fault currents or lightening and protective measures taken at
insulating devices.
Test Leads 195.567, 192.469 and 192.471
2.10.1 All cathodically protected pipelines and breakout tankage shall have a
sufficient number of test stations or other locations for electrical
measurement to determine the adequacy of the cathodic protection system.
2.10.2 For design purposes, test lead spacing on pipelines shall be approximately one
mile. This spacing shall be affected by conditions along the pipeline.
2.10.3 Breakout tankage will be monitored at the four quadrants.
2.10.4 The test leads shall be connected directly to the structure by Thermit welding
or other process, which prevents stress concentration on the pipe and is
approved by the Supervisor of Pipeline Integrity.
2.10.5 Test leads shall be maintained so that electrical measurements can be
obtained in order to ensure adequate protection. For locations where repair
of the test station is impractical, and a reading is necessary to determine the
adequacy of cathodic protecting, an insulated probe rod may be used to
contact the pipe and obtain the reading. This measure may be utilized until
which time the test lead is repaired.
2.10.6 During installation, test leads shall be installed with enough looping or slack to
prevent the test leads from undue stress or breakage during backfilling. Test

<<<PAGE 811>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 12 of 27
leads installed in conduit shall be suitably insulated from the conduit. Refer to
Attaching Cathodic Protection Test Leads for more information.
2.11 2.10.7 Bared test lead wire and bared metallic area at the point of connection to
pipeline must be coated with an electrical insulation material compatible with
the pipe coating and the insulation on the wire.
Exposed Pipeline Examination 195.569 and 192.459
2.11.1 When any buried pipeline is exposed, either intentionally or unintentionally,
the exposed portion shall be visually inspected for evidence of external
corrosion. Refer to Examining and Documenting the Condition of an
Underground Pipeline or Related Facility When Exposed for more information.
2.11.2 When external corrosion requiring remedial action is found, further
investigation will be conducted, circumferentially and longitudinally beyond
the exposed portion (by visual examination, indirect method, or both) to
determine the extent of the corrosion in the vicinity of the exposed portion.
Refer to Pipeline Defect Evaluation and Repair for more information.
2.11.3 If the extent of corrosion cannot be determined, plans and scheduling for
further investigation or the use of an internal inspection device shall be
developed based on the severity of the corrosion encountered.
2.11.4 If the exposed pipe is to remain exposed, proper pipeline markers shall be
installed and the pipe shall be monitored for atmospheric corrosion in
accordance with paragraph 3.1.1 below.
2.12 Stress Corrosion Cracking (SCC)
2.12.1 Basic SCC awareness information is available to operation and maintenance
employees in Stress Corrosion Cracking Information.
2.12.2 The risks associated with SCC are identified and assessed per the Magellan
Risk Assessment Methodology book, and include factors such as age of the
2.12.3 2.12.4 pipeline, coating type, operating stress level, proximity of pump stations and
history of SCC.
In the event that a pipeline system has experienced one or more confirmed
incidents of SCC a systematic identification and examination of other potential
locations of SCC will be conducted based upon the observations of conditions
associated with the confirmed SCC incident.
Areas of the pipeline identified as having high susceptibility to SCC, or any
other locations identified for SCC investigation, will be investigated per Stress
Corrosion Cracking Investigation.

<<<PAGE 812>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 13 of 27
2.12.5 2.12.6 Pipe cutouts sent to a metallurgical lab for analysis will be investigated for
SCC. Results of this analysis will be provided in a comprehensive report
provided to Asset Integrity.
SCC field examinations will be performed by a NDE Technician trained in the
detection of SCC on buried pipelines and will be documented in the Pipeline
Maintenance Report.
2.12.7 If SCC is determined to be present, a review of the pipeline as defined in
Section 6 of the IMP will be conducted, to be followed by a re‐assessment
interval recommendation per Section 7 of the IMP.
2.12.8 Annually, confirmed SCC occurrences will be reviewed to determine if changes
to the SCC assessment criteria are necessary.
2.13 Microbiological Influenced Corrosion (MIC)
2.13.1 In the event that a pipeline system has experienced one or more confirmed
discoveries of injurious MIC, or where accelerated corrosion from MIC is
anticipated, a Bacteria Testing Protocol shall be established to evaluate future
2.13.2 2.13.3 integrity threats from MIC.
The line specific protocol shall be utilized until such time that the threat from
MIC has been assessed and appropriate mitigation actions have been taken.
Testing for MIC shall be conducted in accordance with Bacteria Testing – Serial
Dilution Method.
2.14 Induced AC Corrosion 195.577 192.473
2.14.1 AC potential surveys shall be conducted on each buried, in contact with the
ground, submerged pipeline facility near high voltage power lines once each
calendar year with intervals not to exceed fifteen months. Recording
voltmeters should be considered in areas where high voltage transmission
lines parallel the pipeline over long distances. Pertinent survey information
shall be recorded in the Cathodic Protection Data Manager (CPDM) within 30
days after the survey. Refer to Testing for Induced AC and Remedial Measures
for more information.
2.14.2 AC potentials greater than 5 volts will be evaluated to determine if additional
testing or remedial actions are required. Refer to Testing for Induced AC and
Remedial Measures for more information.

<<<PAGE 813>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 14 of 27
2.14.3 Remedial actions are required where through testing or calculations, AC
current discharge densities are found to be at or greater than 100 A/m2 or AC
potentials are greater than 15 volts. Remedial action may be required where
AC current discharge densities range from 20‐100 A/m2. Refer to Testing for
Induced AC and Remedial Measures for more information.
3.0 ATMOSPHERIC CORROSION CONTROL
3.1 Inspection 195.581, 195.583, 192.479 and 192.481, and 16 TAC 8.305(1)
3.1.1 Facilities and/or pipelines, other than Breakout Tanks, shall be inspected at
least once every three (3) calendar years with intervals not exceeding 39
months for onshore and at least once each calendar year, with intervals not
exceeding 15 months, for offshore. Refer to Atmospheric Corrosion
Inspections for more information.
NOTE: Atmospheric corrosion inspections on exposed pipelines must be
conducted visually.
3.1.2 Assets covered by the Mitigation Plan: Facilities and/or pipelines, other than
Breakout Tanks, shall be inspected annually for atmospheric corrosion. Refer
to Atmospheric Corrosion Inspections for more information.
3.1.3 Breakout Tanks shall be inspected at least once every five (5) years with
intervals not exceeding 60 months. Refer to Atmospheric Corrosion
Inspections for more information.
3.2 3.1.4 Assets covered by the Mitigation Plan: Corrective action for deficiencies found
during atmospheric surveys shall be determined and completed as soon as
practical. Deficiencies will be resolved within one (1) year of discovery, except
deficiencies of such a nature they present a more urgent threat to pipeline
integrity, in which case corrections will be done immediately.
Coating 195.581, 195.583, 192.479 and 192.481
3.2.1 A suitable coating shall be applied to all new aboveground facilities to prevent
atmospheric corrosion damage. Refer to Coatings – Selection, Applications,
and Maintenance for more information.
3.2.2 A suitable coating shall be applied to all soil‐to‐air interface areas to prevent
atmospheric and electrolytic corrosion damage. Refer to Coatings – Selection,
Applications, and Maintenance for more information.
3.2.3 A suitable coating shall be applied to all aboveground facilities to prevent
further atmospheric corrosion damage if, through the guidelines established

<<<PAGE 814>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 15 of 27
in the Atmospheric Inspection Procedure, a Rust Rating of 2‐G or worse is
identified. Refer to Coatings – Selection, Applications, and Maintenance for
more information.
3.2.4 The coating conditions on exposed assets shall be documented in the
Atmospheric Corrosion database (CPDM).
4.0 INTERNAL CORROSION CONTROL
4.1 Introduction 195.579 and 192.477
4.1.1 The corrosive effects of pipeline cargoes (hazardous liquids or carbon dioxide)
shall be investigated and if found to be corrosive, adequate steps shall be
taken to mitigate internal corrosion. If steps are taken to mitigate corrosion,
the effectiveness of the steps shall be monitored using corrosion coupons
and/or other methods.
4.1.2 Circumstance or condition [such as those listed below] that could cause,
promote, or increase the likelihood of internal corrosion should be promptly
reviewed and internal corrosion mitigation plans implemented as appropriate.
4.1.2.1 Type of commodity
4.1.2.2 Flow rate
4.1.2.3 Velocity
4.1.2.4 Operating Pressure
4.1.2.5 Topography
4.1.2.6 Amount of foreign material and/or contaminants present in the
pipeline and/or commodity stream such as sand, silt, water, or
other materials that could cause or promote internal corrosion
4.1.2.7 Amount of sulfur, salts, acids, hydrogen sulfide, carbon dioxide or
other corrosive material present and corrosive effect based upon
partial pressures of material in the pipeline
4.1.2.8 Presence of microbes
4.1.2.9 Temperature
4.1.2.10 Pipe configuration, design, and material specifications

<<<PAGE 815>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 16 of 27
4.1.2.11 Operating conditions, including but not limited to, steady state
conditions, slack line conditions, upset conditions in the pipeline
system, and upset conditions in upstream facilities such as refineries
or processing facilities
4.2 Product Evaluation
4.2.1 Crude Oil or natural gas containing water in the liquid phase, solids, and other
corrosive constituents such as bacteria, H2S, CO2 and O2, are considered
potentially corrosive.
4.2.2 Refined Petroleum Products are evaluated using NACE TM 0172‐2001,
“Determining Corrosive Properties of Cargoes in Petroleum Product
Pipelines”. Petroleum products are considered "corrosive" if they do not meet
at least a "C" rating on this test. Assets covered by the Mitigation Plan have a
target NACE rating of “A”
4.2.3 Natural Gas Liquids are evaluated using ASTM D 1838, "Standard Test Method
for Copper Strip Corrosion by Liquefied Petroleum Gases.” Natural gas liquids
are considered "corrosive" if they fail to meet the Number 1 classification on
this test.
4.2.4 Free water in any product is potentially corrosive
4.2.4.1 Refer to Bacteria Testing – Serial Dilution Method for more
information.
4.3 Internal Corrosion Mitigation
4.3.1 Adequate steps, including eliminating the possibility of free water, removing
corrosive components, or injecting corrosion inhibitor will be taken whenever
investigation of the corrosive effect of the product on the metal indicates it is
necessary.
4.3.2 Cleaning pigs
4.3.2.1 procedures as required.
4.3.2.2 To reduce the potential for unnecessary shut downs and/or
unmanageable product contamination, pipelines with no history of
pigging or those with significant amounts of known debris should
not be pigged until adequate precautions and/or contingency plans
have been developed.
Pipeline cleaning pigs should be utilized system wide on mainline
piping. Refer to Perform Pigging Operations or location specific

<<<PAGE 816>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 17 of 27
4.3.2.3 4.3.2.4 4.3.2.5 4.3.2.6 4.3.2.7 4.3.2.8 The frequency for routine cleaning operations of mainline product
piping should be 2 times per year, approximately every 6 months.
The frequency for routine cleaning operations of mainline crude
piping should be 26 times per year, approximately every two weeks.
Frequencies of cleaning pig runs may be adjusted as necessary
based upon product upsets and the analysis of results of previous
cleaning pig runs. Cleaning of facility piping, pipelines without
launching or receiving equipment, and/or other non‐piggable
sections should be conducted as required on a case by case basis.
Pipelines transporting NH3 do not require routine pigging, but
should be cleaned if excessive debris is identified prior to In‐line
inspection tool runs.
Pipeline pigging or repigging operations should also be considered
when excessive debris is identified in the pipeline, following
transportation of a corrosive (off spec) product, in preparation for
integrity testing with a in‐line inspection tool, following hydrostatic
testing of a pipeline, etc.
Although the presence of debris in the receiving scraper trap does
not necessarily indicate the quantity of material removed from the
pipeline, it should be taken into consideration when determining
the frequency of the cleaning pig operations. The physical condition
of the pigs should also be taken into consideration, as a badly worn
pig may be the result of excessive pipeline debris.
During normal cleaning operations, a combination cup and brush
pig (1st pig) followed, as soon as practical, by a combination cup and
disc pig (2nd pig) should be utilized.
Where excessive debris and paraffin buildup is thought to exist,
specialty pigs such as pin‐wheel, Pit Boss™, scraper/plow blade
attachments, and magnetic cleaning pigs shall be utilized as
necessary based upon sound engineering judgment.
Significant separation between the multiple pigs is not required and
separation by more than a few yards will actually decrease the
effectiveness of the operation.
Cleaning pigs should be maintained in accordance with the
manufactures recommendations. Pigs worn beyond the
manufactures recommend tolerance should not be used.

<<<PAGE 817>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 18 of 27
4.3.2.9 If a pig is to be run in a line which has not been pigged in many
years or in a line which is suspected to be un‐piggable, soft low
density Polly Pigs should be utilized until confidence is achieved that
normal cleaning pigs will successfully traverse the pipeline. Specialty
pigs with tracking devices may also be warranted if there is concern
that the pigs may become stuck in the pipeline.
4.3.2.10 Normal cleaning operations should be conducted at a continuous 3
ft/sec or less where practical.
4.3.2.11 Caution should be observed when pigging lines that start and stop.
Debris may fall out in front of the pig causing the pig to become
stuck.
4.3.3 Corrosion Inhibitor
4.3.3.1 When a corrosion inhibitor is used to mitigate internal corrosion, a
sufficient quantity to protect the entire part of the system the
inhibitor is designed to protect will be used. Initial inhibitor injection
rates will be based on product characteristics of the product to be
inhibited .For refined product systems a hydrocarbon soluble, water
dispersible corrosion inhibitor shall be utilized (Smart Chemical
SCSF260 or equivalent). For crude pipeline systems, a highly water
dispersible/soluble blend of corrosion inhibitors shall be utilized
(Smart Chemical SCCI865 or equivalent).
4.3.3.2 Assets covered by the Mitigation Plan: Inhibitors are required to
control potential internal corrosion.
NOTE: Whenever a corrosion inhibitor injection pump, internal coating, or
other equipment to mitigate internal corrosion, is installed or removed a
Pipeline Maintenance Report shall be completed.
4.3.4 When installing a tank bottom lining in an aboveground breakout tank, the
lining shall be installed in accordance with API Recommended Practice 652
unless noted in this volume why compliance with all or certain provisions of
API Recommended Practice 652 is not necessary for the safety of the tank.
4.4 Internal Corrosion Monitoring
4.4.1 When corrosion inhibitors are used to mitigate internal corrosion, coupons or
other types of monitoring will be used to determine the effectiveness of the
inhibitor and the potential extent of any corrosion. Refer to Coupon Handling
and ER Probes for more information

<<<PAGE 818>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 19 of 27
NOTE: Whenever new coupon holding devices or ER Probes are installed, a
Pipeline Maintenance Report shall be completed.
4.4.2 4.4.3 4.4.4 At least twice each calendar year, and not exceeding intervals of 7 ½ months,
corrosion coupons shall be removed from the test locations and forwarded to
an appropriate laboratory for corrosion analysis (Reference NACE RPO775 for
more information).
Assets covered by the Mitigation Plan: At least three times each calendar
year, and not exceeding intervals of 4.5 months, corrosion coupons shall be
removed from the test locations and forwarded to an appropriate laboratory
for corrosion analysis.
New corrosion coupons will be installed at this time. Any alternate or
supporting corrosion monitoring methods will be accomplished at the same
minimum frequency. Pertinent monitoring data shall be documented in the
Internal Corrosion Database and/or the appropriate inspection forms. Refer to
Coupon Handling and ER Probes for more information.
NOTE: There may be instances in which a product is not corrosive, and
therefore not inhibited. Corrosion coupons may be used to periodically
evaluate these products. In these instances, coupon monitoring may be less
frequent than twice per calendar year and 7 ½ month intervals.
4.4.5 4.4.6 4.4.7 Effectiveness of inhibitor will be based on the inhibitor’s success in reducing
the internal corrosion rate to an acceptable level. This level of acceptability
may be different for each pipeline, but is typically <1 MPY for refined products
and <3 MPY for crude. General corrosion rates can be classified as Low<1
mpy, Moderate 1.0 – 4.9 mpy. Sever >10 mpy.
Internal corrosion rates greater than >1 MPY (refined products) or >3 MPY
(crude) on inhibited pipelines shall be followed up with a detailed analysis
regarding injection rates, hydro‐tests, or other unusual activities or
circumstances. Action plans shall be developed if deemed necessary using
sound engineering judgment.
Assets covered by the Mitigation Plan: Coupon corrosion rates over 1 mpy of
general corrosion or pitting (including MIC) will trigger a detailed analysis
directed by NACE certified corrosion control personnel. This analysis will
include a review of incoming product quality sample data, inhibitor injection
rates, bacteria testing and, if necessary, inhibitor performance testing.
Deficiencies will be resolved within six (6) months of discovery, except

<<<PAGE 819>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 20 of 27
4.5 4.4.8 4.4.9 deficiencies of such a nature they present a more urgent threat to pipeline
integrity, in which case corrections will be done immediately.
For crude pipeline systems, water sample traps will be mounted on the
bottom of the pipe to facilitate the collection and analysis of free water. These
locations will be inspected for water monthly and if a sufficient amount of
water is present (typically >1 pint) this water shall be analyzed for bacteria,
pH, iron, manganese, chlorides, and inhibitor residual (Reference API RP‐45,
NACE TM0194, NACE RP0192, and ASTM D2327 for more information).
Bacteria counts in excess of 10‐100 colonies/ml., pH readings outside a range
of 4‐8, inhibitor residual less than ~10ppm, or an increase in iron, manganese,
or chlorides could indicate an increase threat to internal corrosion. Water and
debris brought into receiving traps during pigging operations will be tested to
determine its potential to cause internal corrosion if determined to be
necessary after consultation with the Corrosion Specialist.
Crude assets covered by the Mitigation Plan: Coupon/water sample collection
points will be located in facilities at origination points, along the pipeline
system, and end points. Locations chosen for initial sampling points include Ft.
McKavett, Cedar Valley, Satsuma, and East Houston. Additional coupon/water
sample collection points may be installed as determined necessary through
hazard analysis.
Internal Examination 195.579(c) and 192.475 (b)
4.5.1 Whenever any pipe is removed from the pipeline for any reason, the internal
surface shall be inspected for evidence of corrosion. Refer to Examining and
Documenting the Condition of an Underground Pipeline or Related Facility
When Exposed for more information.
4.5.2 4.5.3 4.5.4 When corrosion requiring remedial action is found, further investigation will
be conducted both circumferentially and longitudinally (by visual examination,
indirect method, or both) to determine the extent of the corrosion. Remedial
actions will follow if necessary. Refer to Pipeline Defect Evaluation and Repair
for more information.
If the extent of corrosion cannot be determined, plans and scheduling for
further investigation or the use of an internal inspection device shall be
developed based on the severity of the corrosion encountered.
The internal condition of the pipelines shall be documented on the Pipeline
Maintenance Report.
5.0 QUALIFICATION

<<<PAGE 820>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 21 of 27
5.1 Supervisor Qualification 195.555 and 192.453
5.1.1 Magellan Asset Integrity Supervisors shall be knowledgeable of Magellan
corrosion control procedures, including but not limited to those for design,
installation, operation, and maintenance of internal and external corrosion
control systems.
5.1.2 Supervisors may be registered professional engineers, or persons recognized
as corrosion specialists or cathodic protection specialists by NACE, and/or
their professional activities include suitable experience in corrosion control.
5.2 Operator Qualification
5.2.1 Operator Qualification (OQ) is required for personnel to perform identified
Covered Tasks. Refer to Operator Qualification (OQ) – Covered Tasks for more
information.
5.2.2 Assets covered by the Mitigation Plan: All Corrosion related activities shall be
applied under the direction of competent personnel trained in the field of
corrosion control. Corrosion control data shall be reviewed by NACE certified
corrosion personnel.
6.0 CORROSION CONTROL RECORDS 195.404 and 192.491
6.1 Records or maps shall be maintained to show the location of:
6.1.1 Cathodically protected pipelines
6.1.2 Cathodic protection facilities, including galvanic anodes, installed after
January 28, 2002
6.1.3 Neighboring structures bonded to cathodic protection systems.
6.2 Records or maps shall be maintained showing a stated number of anodes, installed in a
stated manner or spacing. Specific distances to each buried anode need not be shown.
6.3 Records shall be maintained of each analysis including root cause analysis, check,
demonstration, examination, inspection, investigation, review, survey, and test required
in sufficient detail to demonstrate the adequacy of corrosion control measures or that
corrosion requiring control measures does not exist. These records shall be maintained
for a minimum of 5 years.
6.4 All pipe to soil survey, rectifier inspection, and foreign line crossing pipe to soil potential
data will be recorded in the appropriate corrosion control database. All close interval
pipe to soil potential data will be recorded in a hard copy report as well as the
appropriate electronic format, atmospheric inspection data and exposes pipe visual
inspection data will be documented on the appropriate forms and distributed

<<<PAGE 821>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 22 of 27
appropriately, and will feed into and be processed in overall LPSIP by populating
appropriate portions of the relative risk model.
6.5 As long as the pipeline remains in service, records shall be maintained for:
6.5.1 Exposed portions of buried pipelines
6.5.2 Cathodic protection surveys, including close interval or comparable surveys
6.5.3 Internal corrosion coupon examination records and records of internal
examination of removed pipe
7.0 INTEGRITY MANAGEMENT PLAN INTEGRATION
7.1 In accordance with the Integrity Management Plan, the Pipeline Risk Engineer will
conduct integrated analysis with the External Corrosion Control Program Manager
and/or SMEs to ensure effective integration of data, recommendations, and/or program
enhancements identified during risk assessments and analysis.
7.2 Recommendations or process changes identified by the External Corrosion Control
Program Manager and/or SMEs as a result of the integrated analysis will be
communicated to and discussed with Pipeline Risk Engineer in accordance with the
Magellan IMP.
7.3 Mitigation measures or process changes conducted by the External Corrosion Control
Program Manager and/or SMEs as a result of the integrated analysis will be
communicated to and discussed with Pipeline Risk Engineer in accordance with the
Magellan IMP.
7.4 Whenever a line is added or removed from the Corrosion Control Program or elements
of the Corrosion Control Program (i.e. External, Internal, Atmospheric), the Pipeline Risk
Analyst shall be notified in order to update the Risk Assessment Model. All pipelines
included in the Corrosion Control Program shall be maintained in accordance with the
program guidelines and criteria. Corrosion Control records or data from new
construction or pipeline acquisition activities shall be entered into the Corrosion Control
database within one year. Pipelines not included in the program are not maintained in
accordance with the program and as such, corrosion can be expected. See Inactive
Pipelines and Abandoning Pipeline Segments for more details.
8.0 DEFICIENCIES IN CORROSION CONTROL
8.1 Deficiencies in Corrosion Control shall be corrected in a reasonable time.
8.1.1 Unless otherwise specified in this program, a reasonable time to correct
deficiencies is defined as by the next scheduled inspection.

<<<PAGE 822>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 23 of 27
8.1.2 8.1.3 In the case where deficiencies cannot be complete by the next scheduled
inspection; planning, scheduling, progress, assessment, testing, monitoring,
and/or other process that demonstrates that the threat in being addressed in
a prudent and practical manner may be utilized until such time the deficiency
has been resolved.
A cause analysis will be performed to identify contributing factors and root
causes of anomalies/deficiencies identify by corrosion control surveys.

<<<PAGE 823>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 24 of 27
System Integrity Plan Change Log
Date Change
Location
Changed By Approved
By
Brief Description of Change
1.1, 1.2 Rick Wooldridge Michael Pearson Revised regulation number 192.461 to 192.452.
1.1.1 Rick Wooldridge Michael Pearson 10/08/02
Replaced “newly buried” with “jurisdictional, newly
constructed, relocated, replaced or otherwise changed.”
1.2.1 Rick Wooldridge Michael Pearson
Added: “including newly constructed, relocated, replaced or
otherwise changed pipelines.”
1.6.1 Rick Wooldridge Michael Pearson
11/20/02
Added “Pertinent survey information shall be recorded in the
Cathodic Protection Data Manager (CPDM) within 30 days
after the survey.”
1.6.3, 1.71, 1.81 Rick Wooldridge Michael Pearson Added: “within 30 days after the survey.”
1.9.4.2 Rick Wooldridge Michael Pearson
Removed wording related to “metallic” or “electrolytic” type
of short.
1.9.4.3 Rick Wooldridge Michael Pearson Added wording related to specific requirements for 192
05/06/03
1.10.3 Rick Wooldridge Michael Pearson Removed references to “permanent reference cells.”
2.1.2 Rick Wooldridge Michael Pearson Changed “39” months to “36” months to align with 192
regulations.
05/16/03 5.0 Rick Wooldridge Michael Pearson Added 5.0, Integrity Management Plan Integration.
6/13/03 2.1.3 Rick Wooldridge Michael Pearson Added 2.1.3 Breakout Tanks shall be inspected………..
10/1/03 1.2.1, 1.6.1 Rick Wooldridge Michael Pearson Changed “Manager of Pipeline Integrity” to “Manager of
Asset Integrity to reflect title changes.
10/1/03 2.1.1 Rick Wooldridge Michael Pearson
Deleted entire paragraph “On Jurisdictional facilities each
pipeline that is exposed…” The criteria for coating are
depicted in the new 2.13.
10/1/03 2.1.3 Rick Wooldridge Michael Pearson
Added, “A suitable coating shall be applied to all soil‐to‐air
interface areas to prevent atmospheric and electrolytic
corrosion damage. Refer to Coatings – Selection, Applications
and Maintenance.” in order to clarify the coating criteria.
Added, “A suitable coating shall be applied to all aboveground
facilities to prevent further atmospheric corrosion damage if,
through the guidelines established in the Atmospheric
Inspection Procedure, a Rust Rating of 2‐G or worse is
identified. Refer to Coatings – Selection, Applications and
Maintenance.” in order to clarify the coating criteria.
10/1/03 4.1.1 Rick Wooldridge Michael Pearson
Changed “Williams Pipeline Integrity Supervisors” to
“Magellan Asset Integrity Supervisors” in order to reflect
changes in title.
Inserted: Internal Corrosion Program
10/1/03 3.0 Rick Wooldridge Michael Pearson
10/1/03 6.1, 6.2, 6.3 Rick Wooldridge Michael Pearson
Changed “risk engineer” to “Pipeline Risk Engineer” in order
to reflect changes in title and clarify implied responsibilities
(i.e. pipeline vs facility)
11/30/03 1.2.3 Rick Wooldridge Michael Pearson
Added, “On jurisdictional facilities…cathodic protection
system shall be provided within one year of completed
construction”.
11/30/03 1.5.2 Rick Wooldridge Michael Pearson
Added, “Newly constructed facilities shall be included in and
be managed in accordance with the Magellan System
Integrity Plan….
11/30/03 2.5.3 Rick Wooldridge Michael Pearson Added, “On newly constructed facilities, corrosion personnel,
qualified under the Operator Qualification Ruling or with

<<<PAGE 824>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 25 of 27
NACE Certification, shall be utilized to identify, mitigate, and
monitor for inadequate cathodic protection and detrimental
interference currents, prior to and during construction. Refer
to Section 1.8, Foreign Crossings and Interference Currents
below.”
11/30/03 1.6.5 Rick Wooldridge Michael Pearson Added entire section related to CIS
11/30/03 1.11.4 Rick Wooldridge Michael Pearson
Deleted, “The external condition of the pipelines shall be
reported on Form 02‐LEG‐1035 – Encroachment Agreement
(Short Form), Form 02‐OPR‐1581 – Maintenance Report, or
equivalent form.”
12/1/03 1.0 Rick Wooldridge Michael Pearson Added Index and renumbered
12/1/03 9.0 Rick Wooldridge Michael Pearson Added Definitions
12/1/03 8.0 Rick Wooldridge Michael Pearson Added References
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “DETERMINING CORROSIVE PROPERTIES OF
CARGOES IN PETROLEUM PRODUCTS PIPELINES”
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “Refer to Copper Strip Corrosion by Liquefied
Petroleum (LP) Gases.”
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “and Field Gas Analysis For CO2, H2S, O2 and Dew
Point.”
12/1/03 8.2 Rick Wooldridge Michael Pearson
Deleted, “NOTE: Corrosivity of liquid products (refined
petroleum products and natural gas liquids) is rarely
evaluated
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “Corrosive gas shall not be transported by pipeline,
……considered to be potentially corrosive.”
12/1/03 4.6 Rick Wooldridge Michael Pearson Rewrite to be consistent with External Examination
3/23/04 4.4.2 Rick Wooldridge Michael Pearson
Added: Effectiveness of inhibitor will be based on the
inhibitors success.. typically <1 MPY for refined
products.
3/23/04 4.4.3 Rick Wooldridge Michael Pearson Added: Internal corrosion rates greater than >1 MPY on
inhibited pipelines…..engineering judgment.
6/5/2004 3.1.1 Rick Wooldridge Michael Pearson
Note: Atmospheric corrosion inspections on exposed
pipelines may be conducted visually or through the use
of an in-line inspection device capable of identifying and
sizing corrosion.
11/5/2004 2.2.2, 2.6.3 Rick Wooldridge Michael Pearson
Modified for clarification: Noted conditions that will cause
compliance with 651 to not be observed may be but are
not limited to tanks set on concrete, asphalt pads or
where studies conducted in accordance with API 653
indicate that corrosion will not affect the safe operation of
the tank.
11/30/2004 2.9.4.1 Rick Wooldridge Michael Pearson Replaced “shall” with “may” for 195 lines and added the
192 language.
1/3/05 3.3.1 Rick Wooldridge Michael Pearson Deleted: Operate Auto-Injection Pumps, Added: Internal
Corrosion Remediation
1/3/05 3.4.4 Rick Wooldridge Michael Pearson Replaced reference to OJT with “Refer to Coupon
Handling and ER Probes” for more information.
1/3/05 3.4.4 Rick Wooldridge Michael Pearson Reviewed the procedure for accuracy and effectiveness.
4/7/05 Overall Rick Wooldridge Michael Pearson Minor modification and editorials added to provide
clarification…no process changes.
5/16/05 1.9.4.3 Rick Wooldridge Michael Pearson
Added: “Note: For line sections integrity tested by
hydrostatic test a risk evaluation will be conducted at
each shorted casing and action taken to clear the short
and/or mitigate the corrosion if deemed necessary.”
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Basic SCC awareness information is available to
operation and maintenance employees in Stress

<<<PAGE 825>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 26 of 27
Corrosion Cracking Information.
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: In the event that a pipeline system has
experienced one or more confirmed incidents of SCC a
systematic identification and examination of other
potential locations of SCC will be conducted based upon
the observations of conditions associated with the
confirmed SCC incident.
7/6/05 1.12 Rick Wooldridge Michael Pearson Added: or any other locations identified for SCC
investigation,
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Pipe cutouts sent to a metallurgical lab for
analysis will be investigated for SCC. Results of this
analysis will be provided in a comprehensive report
provided to Asset Integrity.
Added: SCC examinations will be performed by a NDE
Technician trained in the detection of SCC on buried
pipelines and will be documented in the Pipeline
Maintenance Report.
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Annually, confirmed SCC occurrences will be
reviewed to determine if changes to the SCC
assessment criteria are necessary.
8/1/05 1.12 Rick Wooldridge Michael Pearson No confirmed SCC occurrences to review.
11/7/05 All Rick Wooldridge Michael Pearson Added LPP Mitigation and Shell CD requirements.
11/7/05 3.3.2 Rick Wooldridge Michael Pearson Added cleaning pig requirements.
12/14/05 3.5.2 Rick Wooldridge Michael Pearson Added “circumferentially and longitudinally”
1/4/06 1.13, 7.13 Rick Wooldridge Michael Pearson Added MIC related information to the program.
03/06/06 2.9.4.3 Rick Wooldridge Michael Pearson Deleted “clear the short and/or” mitigate the corrosion …
4/6/2006 3.2.1 Rick Wooldridge Michael Pearson
Added: Refer to Coatings – Selection, Applications, and
Maintenance for more information.
4/6/2006 2.13.1 Rick Wooldridge Michael Pearson Replaced “incidents” with “discoveries” and added
“injurious”.
4/6/2006 4.4.1 Rick Wooldridge Michael Pearson Replaced “Internal Corrosion Remediation” with “Auto
Injection Pumps”.
9/8/2006 8.0, 10.0 Rick Wooldridge Michael Pearson
Section 8 ‐ Deficiencies in Corrosion Control was added and
references to “as soon as practical” were removed from the
document. Section 10 – Definitions was update to include
“reasonable time”.
9/8/2006 ALL Rick Wooldridge Michael Pearson
Reviewed entire document…minor editorial changes, no
process changes.
10/26/2006 2.3.4.2, 2.3.6 Rick Wooldridge Michael Pearson Removed references to Net Protective current criteria
11/30/06 TOC Rick Wooldridge Michael Pearson Added 2.14 ‐ AC Corrosion
11/30/06 2.5.3 Rick Wooldridge Michael Pearson Changed “Section 1.8 to 2.8 “and added “2.14, Induced AC
Corrosion” in the last sentence.
11/30/06 2.8.4 Rick Wooldridge Michael Pearson
Added Section 2.8.4 “For interference currents related to
AC.........”
11/30/06 2.14 Rick Wooldridge Michael Pearson
Added new Section – “2.14 Induced AC Corrosion” and
subsections 2.14.1, 2.14.2 and 2.14.3
11/30/06 9.1 Rick Wooldridge Michael Pearson
Added link to “Testing for Induced AC and Remedial Measures
in Related Policies/Procedures
11/30/06 10 Rick Wooldridge Michael Pearson
Added the definition for Induced AC Corrosion to Section 10 –
Definitions
11/30/06
Deleted
12/7/09
3.2.4 Rick Wooldridge Michael Pearson
Added: Longhorn Specific: A suitable coating shall be applied
to all aboveground facilities and soil‐to‐air interface areas to
prevent corrosion damage. All areas with signs of coating
degradation and/or corrosion shall be coated/recoated. Refer

<<<PAGE 826>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 27 of 27
to Coatings – Selection, Applications and Maintenance for
more information.
4/25/07 2.1 David Stewart Michael Pearson Added 16 TAC 7.86(3) to regulation references.
4/25/07 2.1.6 David Stewart Michael Pearson Added “…using a coating deficiency (holiday) detector…”
4/25/07 2.1.9 David Stewart Michael Pearson
Added new paragraph, “Joints, fittings, and tie‐ins shall be
coated with material(s) compatible with the coating(s) on the
pipe.” Old 2.1.9 reference to Coatings – Selection,
Applications, and Maintenance becomes 2.1.10.
4/25/07 2.8 David Stewart Michael Pearson Added 16 TAC 7.86(5)(c) to regulation references.
4/25/07 2.8.4 David Stewart Michael Pearson
Added new paragraph, “Texas Intrastate Pipeline specific:
Whenever suspected areas of interference are identified,
testing will be conducted within 6 months to determine the
extent of interference, and appropriate action will be taken.”
Old 2.8.4 reference to AC testing becomes 2.8.5.
1/1/08 4.2.2 David Stewart Rick Wooldridge Added natural gas
1/15/08 2.6.4.1 David Stewart Rick Wooldridge
Added paragraph requiring adequate levels in AST’s when
taking potential readings, as well as requirement to document
the tank levels.
2/15/08 2.3.2 Rick Wooldridge Larry Davied
Added: “Where injurious aerobic bacteria has been identified,
or is suspected, a polarized potential of ‐.950 volts or more
negative is required.”
2/20/08 All E7 Rick Wooldridge 2007 annual review
9/08/08 3.1.1 Rick Wooldridge Larry Davied
Removed the note “or through the use of an in‐line inspection
device capable of identifying and sizing corrosion…at the
request of PHMSA
09/25/08 1.3 Rick Wooldridge Larry Davied Remove references to Shell’s Consent Decree
09/25/08 All E7 Rick Wooldridge 2008 annual review, no changes
11/06/08 4.3.2.3 Rick Wooldridge Larry Davied
Pipelines transporting NH3 do not require routine pigging, but
should be cleaning if excessive debris is identified and/or
prior to In‐line inspection tool runs.
11/16/09 All E7 Rick Wooldridge 2009 annual review; Removed references to Longhorn
12/07/09 4.1.1 E7 Rick Wooldridge
Removed…Pipeline cargoes shall be periodically evaluated for
corrosivity. Added: The corrosive effects of pipeline cargoes
(hazardous liquids or carbon dioxide) shall be investigated.
12/07/09 4.1.2 E7 Rick Wooldridge
Added: Circumstance or condition [such as those listed
below] that could cause, promote, or increase the likelihood
of internal corrosion should be promptly reviewed and
internal corrosion mitigation plans implemented as
appropriate.
12/07/09 4.1.2.1 thru 4.1.2.11 E7 Rick Wooldridge
Added: 4.1.2.1 Type of commodity, 4.1.2.2 Flow rate, 4.1.2.3
Velocity, 4.1.2.4 Operating Pressure, 4.1.2.5
Topography, 4.1.2.6 Amount of foreign material and/or
contaminants present in the pipeline and/or commodity
stream such as sand, silt, water, or other materials that could
cause or promote internal corrosion, 4.1.2.7 Amount of
sulfur, salts, acids, hydrogen sulfide, carbon dioxide or other
corrosive material present and corrosive effect based upon
partial pressures of material in the pipeline 4.1.2.8 Presence
of microbes, 4.1.2.9 Temperature, 4.1.2.10 Pipe
configuration, design, and material specifications, 4.1.2.11
Operating conditions, including but not limited to, steady

<<<PAGE 827>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 28 of 27
state conditions, slack line conditions, upset conditions in the
pipeline system, and upset conditions in upstream facilities
such as refineries or processing facilities
03/03/10 10 E7 Rick Wooldridge Deleted “Definitions”
03/03/10 8.1.3 Jimmy Puckett Rick Wooldridge
Information added to provide a single specific location that
addresses LMP requirements…cause analysis will be
performed to identify contributing factors and root causes of
anomalies/deficiencies identify by corrosion control surveys.
03/03/10 6.4 Jimmy Puckett Rick Wooldridge
Information added to provide a single specific location that
addresses LMP requirements…All pipe to soil survey, rectifier
inspection, and foreign line crossing pipe to soil potential data
will be recorded in the appropriate corrosion control
database. All close interval pipe to soil potential data will be
recorded in a hard copy report as well as the appropriate
electronic format, atmospheric inspection data and exposes
pipe visual inspection data will be documented on the
appropriate forms and distributed appropriately, and will feed
into and be processed in overall LPSIP by populating
appropriate portions of the relative risk model.
3/25/10 6.3 DOT Rick Wooldridge
Modified: Records shall be maintained of each root cause
analysis...to read Records shall be maintained for each
analysis including root cause analysis.
8/9/10 2.3.4 E7 – Ken Lybarger Rick Wooldridge Changed Supervisor of Asset Integrity to Supervisor of
Corrosion Control
8/9/10 2.10.4 E7 – Ken Lybarger Rick Wooldridge
Changed Supervisor of Asset Integrity to Supervisor of
Pipeline Integrity to maintain consistency with pipeline
welding procedures.
2010 annual review; 2.4.2 was simplified to say, “Cathodic
protection level should be evaluated utilizing Cathodic
08/09/10 All E7 Rick Wooldridge
Protection Criteria.”. This change was necessary to
improve/clarify the process for IR drop consideration.
Deleted: “4.2.1 Products entering the system shall be
sampled in accordance with D 4057‐95 (2000) ‐ Standard
Practice for Manual Sampling of Petroleum and Petroleum
Products, D 5842‐95 (2000) ‐Standard Practice for Sampling
and Handling of Fuels for Volatility Measurement, and D
4177‐95 (2000) Standard Practice for Automatic Sampling of
Petroleum and Petroleum Products”. This change removes
unnecessary and likely incomplete information.
10/10/11 4.3.2.3 Rick Wooldridge Doug Chabino
2011 Annual Review;
Added: The frequency for routine cleaning operations of
mainline crude piping should be 26 times per year,
approximately every two weeks. Frequencies of cleaning pig
runs may be adjusted as necessary based upon product
upsets and the analysis of results of previous cleaning pig
runs.
12/31/11 All 2012 Annual Review complete
2/16/12 4.3.2.3 Rick Wooldridge Doug Chabino Added clarification to facility piping
5/15/12 2.9.4.4 Rick Wooldridge Doug Chabino
Added section to require testing for electrolytic shorted
casings
5/15/12 2.9.4 Rick Wooldridge Doug Chabino Removed references to 192 (Gas) assets
5/15/12 4.3.2.6 Rick Wooldridge Doug Chabino
Added: Where excessive debris and paraffin buildup is
thought to exist, specialty pigs such as pin‐wheel, Pit Boss™,

<<<PAGE 828>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 29 of 27
scraper/plow blade attachments, and magnetic cleaning pigs
shall be utilized as necessary based upon sound engineering
judgment.
5/15/12 4.3.3.1 Rick Wooldridge Doug Chabino
Added: For refined product systems a hydrocarbon soluble,
water dispersible corrosion inhibitor shall be utilized (Smart
Chemical SCSF260 or equivalent). For crude pipeline systems,
a highly water dispersible/soluble blend of corrosion
inhibitors shall be utilized (Smart Chemical SCCI865 or
equivalent).
5/15/12 4.4.5 Rick Wooldridge Doug Chabino Added: and <3 MPY for crude.
5/15/12 4.4.8 Rick Wooldridge Doug Chabino
Added: (Reference API RP‐45, NACE TM0194, NACE RP0192,
and ASTM D2327 for more information) and For crude
pipeline systems, water sample traps will be mounted on the
bottom of the pipe to facilitate the collection and analysis of
free water. These locations will be inspected for water
monthly and if a sufficient amount of water is present
(typically >1 pint) this water shall be analyzed for bacteria,
pH, iron, manganese, chlorides, and inhibitor residual.
Bacteria counts in excess of 10‐100 colonies/ml., pH readings
outside a range of 4‐8, inhibitor residual less than ~10ppm, or
an increase in iron, manganese, or chlorides could indicate an
increase threat to internal corrosion. Water and debris
brought into receiving traps during pigging operations will be
tested to determine its potential to cause internal corrosion if
determined to be necessary after consultation with the
Corrosion Specialist.
5/15/2012 4.4.9 Rick Wooldridge Doug Chabino
Added: Crude assets covered by the Mitigation Plan:
Coupon/water sample collection points will be located in
facilities at origination points, along the pipeline system, and
end points. Locations chosen for initial sampling points
include Ft. McKavett, Cedar Valley, Satsuma, and East
Houston. Additional coupon/water sample collection points
may be installed as determined necessary through hazard
analysis.
5/15/2012 4.4.2, 4.4.8 Rick Wooldridge Doug Chabino Added references to Standard documents
5/15/2012 2.14 Rick Wooldridge Doug Chabino
Recording voltmeters should be considered in areas where
high voltage transmission lines parallel the pipeline over long
distances.

<<<PAGE 829>>>

Magellan Midstream Partners, L.P.
EXAMINING AND DOCUMENTING THE CONDITION OF AN
UNDERGROUND PIPELINE OR RELATED FACILITY WHEN EXPOSED
7.04–ADM–005
Asset Integrity 0/01/11 Revision: 3 Page 1 of 4
1.1 3.13.1 Purpose
The purpose of this procedure is to establish a standardized method for examining and
documenting the condition of an underground pipeline or related facility when exposed or
removed from the system for any reason.
3.13.2 2.0 PROCEDURE
NOTE: Each time a buried pipeline or related underground facility is exposed for any reason (intentionally
or unintentionally), it must be thoroughly inspected and the conditions noted on the Pipeline Maintenance
Report. Additionally, each time pipe is removed from the system; the internal surface of the pipe must be
inspected for evidence of corrosion.
2.1 2.2 Performing and Documenting the Coating Examination
2.1.1 Perform an inspection of the pipe coating, if coated, and note the type of coating.
2.1.2 Note the condition of the coating.
2.1.2.1 Well Bonded: Coating is considered “well bonded” if it is intact and doing
its intended job with good adhesion and minimal holidays.
2.1.2.2 Partially Bonded: Coating is considered “partially bonded” if it is lightly
damaged, shows evidence of deterioration or some loss of adhesion and
is not shielding the cathodic protection.
2.1.2.3 Totally Disbonded: Coating is considered “totally Disbonded” if it is
damaged, losing adhesion shown by coating falling off the pipe, and/or
shielding the cathodic protection.
2.1.3 Note any evidence of soil stress if the coating appears to be deformed and ineffective
as if pulled or stretched from its normal status.
2.1.4 Note the environment in which the pipe is in at the exposed site by identifying the
total depth of cover, in inches, from top of the pipe to the ground surface.
2.1.5 If after completing the pipeline inspection, the exposed section is recoated, note the
details of the coating material used.
2.1.5.1 Reference Coatings – Selection, Application, and Maintenance procedure.
Performing and Documenting the Corrosion Examination
2.2.1 Perform an inspection of the pipe and confirm the general pipe specifications. Most of
the general pipe information can be found on alignment sheets.
2.2.2 If the internal portion of the pipe is exposed from being cut, coupon extracted, or
other reasons, include the internal surface in the corrosion examination.
2.2.3 Note the condition of the pipe when there is evidence of corrosion, SCC, third party
damage, pipe defects, or other conditions of concern.
2.2.4 The following external corrosion examination is only necessary if damaged coating
and corrosion or SCC has been identified. If the coating is not damaged to the point of
being able visually inspect the pipe surface, or if the pipe surface is not corroded or
SCC is not noted, go to step 2.2.9.
2.2.5 Measuring Corrosion and Pipe Wall Thickness

<<<PAGE 830>>>

Magellan Midstream Partners, L.P.
EXAMINING AND DOCUMENTING THE CONDITION OF AN
UNDERGROUND PIPELINE OR RELATED FACILITY WHEN EXPOSED
7.04–ADM–005
Asset Integrity 0/01/11 Revision: 3 Page 2 of 4
2.2.6 2.2.7 2.2.8 2.2.9 2.3 Documentation
2.3.1 2.2.5.1 Clean the pit(s)
2.2.5.2 Position the pit gauge over the corrosion to be measured.
2.2.5.3 Obtain the pit depth following the manufactures procedures for the
specific pit gauge utilized.
2.2.5.4 Divide the measured pit depth by the nominal wall thickness of the pipe
to determine the percentage depth of the corrosion.
2.2.5.4.1 Nominal wall thickness may be obtained from the alignment
sheets, from the Line Fill Database (contact Asset Integrity), or
by physical measurement.
2.2.5.4.2 Measure wall thickness utilizing ultrasonic thickness equipment
following the manufactures recommend procedures.
Use the following corrosion definitions to describe the type and extent of the
corrosion found.
2.2.6.1 Minor Pitting: Corrosion exhibiting metal loss less than 12.5% of the pipe
wall.
2.2.6.2 Moderate Pitting: Concentrated area of uniform metal loss without
isolated pitting.
2.2.6.3 Severe Pitting: Concentrated area of metal loss appearing as a dimple,
crater or depression in the steel surface.
If corrosion is in excesses of 12.5% of the pipewall or any dents, gouges, or SCC is
observed, contact a Supervisor of Asset/Pipeline Integrity, Pipeline Risk Engineer, or
Pipeline Integrity Engineer/Coordinator immediately.
2.2.7.1 Refer to Pipeline Defect Evaluation and Repair and RSTRENG Analysis of
Corrosion procedures if additional data gathering and/or analysis are
required.
If SCC is observed initiate Pipeline Defect Evaluation and Repair Procedure.
Any pipeline or related facility that will remain exposed to the atmosphere after initial
inspection should then be inspected in accordance with Atmospheric Corrosion
Inspection procedure.
Each time a buried pipeline or related underground facility is exposed for any reason
(intentionally or unintentionally), it must be inspected, and the conditions
documented on the Pipeline Maintenance Report.
End of Procedure

<<<PAGE 831>>>

Magellan Midstream Partners, L.P.
EXAMINING AND DOCUMENTING THE CONDITION OF AN
UNDERGROUND PIPELINE OR RELATED FACILITY WHEN EXPOSED
7.04–ADM–005
Asset Integrity 0/01/11 Revision: 3 Page 3 of 4
System Integrity Plan Change Log
Date Change
Location
Changed
By
Approved
By
Brief Description of Change
12/1/03 Change
Log Rick Wooldridge Wooldridge
Rick
Added “Changed By”
12/1/03 2.0 Rick Wooldridge Rick
Wooldridge
Added Note: Examining the condition of an underground pipeline
or related facility when exposed is a Covered Task. Reference
Operator Qualification (OQ) – Covered Tasks.
12/1/03 2.1.5.1 Rick Wooldridge Rick
Wooldridge
2.1.5.1 Reference “Coatings and/or Paint – Selection,
Applications and Maintenance”.
12/1/03 2.2.6 Rick Wooldridge Rick
Wooldridge
2.2.6 Investigation.
If SCC is observed initiate Stress Corrosion Cracking
12/1/03 3.2.3, 3.2.4 Rick Wooldridge Rick
Wooldridge
Updated procedure list
1/1/06 All E7 Rick
Wooldridge
2005 annual review, no changes
1/1/07 All E7 Rick
Wooldridge
2006 annual review, no changes
01/01/08 All E7 Rick
Wooldridge
2007 annual review, no changes
4/1/08 2.2.4 Rick Wooldridge Rick
Wooldridge
Added for clarification
11/19/08 2.1.1 Rick Wooldridge Rick
Wooldridge
Deleted: Most of the general coating information can be found on
alignment sheets.
11/19/08
E7 All
Rick
Wooldridge
2008 annual review, no changes
11/17/09
E7 All
Rick
Wooldridge
2009 annual review, minor clean-up changes
08/10/10
E7 All
Rick
Wooldridge
2010 annual review; Revised numbering
12/31/11
2012 Annual Review complete – no changes
All

<<<PAGE 832>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 1 of 9
1.0 Purpose
1.1 The purpose of this procedure is to establish standardized cathodic protection (CP) criteria to be
used to confirm adequate external corrosion control for Company facilities.
2.0 PROCEDURE
2.1 2.2 2.3 Identifying CP Criteria to be Used
2.1.1 Selecting which CP criteria to use
2.1.1.1 Use the –0.850 volts Pipe‐to‐Soil (P/S) potential criteria as the primary criteria for all
facilities.
2.1.1.2 Use the 100 millivolt shift criteria whenever the –0.850 volts P/S criteria cannot be
achieved or as directed by the Manager of Asset Integrity.
2.1.1.3 The criteria employed must be specified in the Cathodic Protection Data Manager for
the facility, segment, or individual test point.
Using the –0.850 Volts P/S Criteria
2.1.2 Take P/S potentials per procedure Measuring a Pipe‐to‐Soil Potential.
2.1.3 P/S reading must be at least –0.850 volts, with reference to a saturated copper‐copper sulfate
reference half‐cell, while the protective current is applied.
2.1.4 Voltage (IR) drops shall be considered per section 2.5 below.
2.1.5 Whenever –0.850 volts P/S is not achieved, the 100 millivolt shift criteria should be applied,
unless corrective actions are planned to remediate the low potential.
100 Millivolts Voltage Shift (Polarization Formation) Criteria
2.3.1 To use the 100 millivolt shift criteria as established by the polarization formation method,
follow the procedure described below.
2.3.2 For Existing Pipelines Or Facilities
2.3.2.1 Turn off and/or disconnect all known sources of CP influence.
2.3.2.2 Allow sufficient time for the piping or facility to depolarize.
2.3.2.3 Conduct a complete P/S survey (near native state survey).
2.3.2.4 Near native state survey, results may not be totally native state due to unknown
galvanic anodes or foreign impressed and stray current influences. If other CP
influences are located, these should be shut down and a new survey performed in the
areas of influence.
2.3.3 Apply CP to the Pipeline or Facility
2.3.3.1 Turn on and/or reconnect all known sources of CP influence.
2.3.3.2 Allow sufficient time for the structure to polarize or re‐polarize for existing structures.
2.3.4 Conduct an Interrupted P/S Survey Of The Pipeline Or Facility
2.3.4.1 Install and place in operation interrupter equipment in all influential CP current
sources affecting the pipeline or facility being tested.
2.3.4.2 Synchronize all interrupters.

<<<PAGE 833>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 2 of 9
2.3.5 2.3.6 2.3.7 2.3.4.3 Use at least an 80% duty cycle (“On” cycle set to 8 seconds and “Off” cycle set to 2
seconds). Keep the “Off” cycle as short as possible to prevent polarization decay but
long enough to read after any spike (“Instant Off”) as shown in Figure 1 “Polarization
Formation”.
2.3.4.4 After starting the interruption of all current sources, read the “On” potential during
the “On” cycle and take the “Off” potential reading instantly after any spike.
Conduct a complete P/S survey, recording both the “Instant Off” and the “On” potential
readings.
Calculate for the 100 millivolt shift.
2.3.6.1 Subtract the Native State or Near Native State potential from the “Instant Off”
potential for each location.
To meet the 100 millivolt shift criteria, the results must be greater than 100 millivolt.
2.4 2.3.8 Establish Individual Test Point “ON” criteria based on the 100 millivolt test.
2.3.8.1 When 100 millivolt or more shift occurs, the “On” potential reading is established as
the P/S criteria, with CP on, for a particular test point.
2.3.8.2 As long as there are no significant changes in the environment, structure, coating, CP
systems, etc., this established “On” criteria can be used for satisfying the 100 millivolt
criteria through the monitoring of the “On” potentials.
100 Millivolts Voltage Shift (Polarization Decay) Criteria
2.4.1 To use the 100 millivolt shift criteria as established by the polarization decay method
2.4.1.1 Install and place in operation interrupter equipment in all influential CP current
sources effecting the pipeline or facility being tested.
2.4.1.2 Synchronize all interrupters
2.4.1.3 Use at least an 80% duty cycle (“On” cycle set to 8 seconds and “Off” cycle set to 2
seconds). The “Off” cycle should be kept as short as possible to prevent polarization

<<<PAGE 834>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 3 of 9
2.4.2 2.4.3 2.4.4 decay, but long enough to read after any spike (“Instant Off”) as shown in Figure 2.
2.4.1.4 Conduct a complete P/S survey, recording both the “Instant Off” and the “On”
potential readings. Mark each spot of electrode placement.
Calculate Targeted Near Native State P/S Potentials as Follows:
2.4.2.1 Subtract 100millivolt from the “Instant Off” potential reading for each test point. This
is the targeted near native state P/S potential.
Test For Polarization Decay To Targeted Near Native State P/S Potentials As Follows:
2.4.3.1 Turn off and/or disconnect all known sources of CP influence.
2.4.3.2 Conduct a complete P/S survey, recording “Off” potential readings.
2.4.3.3 Observe and record polarization decay potentials. When polarization decay potentials
reach targeted near native state P/S potentials, stop decay test to retain as much
polarization as possible
2.4.3.4 Targeted near native state potentials may not be totally native state due to unknown
galvanic anodes or foreign impressed and stray current influences and a small amount
of remaining polarization.
2.4.3.5 Turn on or reconnect all known sources of CP influence as soon as possible to
reestablish polarization.
Establish Individual Test Point “On” criteria based on the 100 millivolt shift, polarization decay
2.5 test.
2.4.5 When 100 millivolt or more shift occurs, the “On” potential reading is established as the P/S
criteria, with CP on, for that test point.
2.4.6 As long as there are no significant changes in the environment, structure, coating, CP systems,
etc., these established “On” criteria can be used for satisfying the 100 millivolt criteria through
the monitoring of the “On” potentials.
Methods for IR Drop Consideration
2.5.1 In accordance with Ohm’s Law of E (volts) = I (current) x R (resistance), any time current flows
through a resistance, a voltage drop is produced. For cathodic protection purposes, the current
flow in the soil (electrolyte) is the I and the soil resistance is R and the resulting voltage drop is
E in volts. Therefore, if the amount of current or the resistance is very low, the resulting
voltage or IR drop would also be low or considered negligible. The voltage drop, commonly
called the IR Drop, needs to be considered when taking pipe‐to‐soil measurements. See figure
below for a depiction of the IR Drop location in P/S measurements below.

<<<PAGE 835>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 4 of 9
2.5.2 Various IR Drop correction techniques can be utilized to consider the IR Drop factor in P/S
measurements. These include but not limited to the following:
Which Method(s) For Considering Voltage Drop (IR) In P/S Measurements
Method Process Comments
High
Resistance
Voltmeter
See
Section
2.5.3
Historical
Operating
Information
See
Section
2.5.4
Reference
Cell
Placement
See
Section
2.5.5
Is affected by proximity to the current sorce
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Requires knowledge of various operating factors and historical
information
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
May be affected by the proximity to current sorce
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Calculation
See
Section
2.5.6
Time consuming and requires various calculations
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Current
Interruption
See
Section
2.5.7
For proper use, requires synchronized interruption of all current
sources
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Buried
Coupons
See
Section
2.5.8
Requires installation of special test stations containing coupons
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations

<<<PAGE 836>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 5 of 9
2.5.3 High Resistance Voltmeter Method
2.5.3.1 This method considers IR drop by minimizing current flow through the
measurement circuit, thus decreasing voltage drops associated with the
mechanical and electrolytic components of the circuit.
2.5.3.2 A high resistance voltmeter (>50,000 ohm) is necessary to reduce the voltage
drop in the external circuit.
2.5.4 Historical Operating Information Method
2.5.4.1 This method utilizes recent and historical operating information to determine
if the cathodic protection system is properly protecting the structure at
existing voltage levels.
2.5.4.2 The lack of corrosion related leaks or repairs in conjunction with consistent
cathodic protection levels and coating condition indicates the adequacy of
cathodic protection.
2.5.5 Reference Cell Placement Method
2.5.5.1 Since the amount or quantity of the IR drop is directly proportional to the
distance between the reference cell and the structure to be measured, the
simplest method for considering IR drop is to minimize this distance.
2.5.5.2 To minimize IR drop at test stations:
2.5.5.2.1 The reference cell should be placed over the centerline of the
structure to be tested.
2.5.5.2.2 Permanent reference cells can be placed in close proximity to
the buried structure.
2.5.5.2.3 If a quantitative voltage drop reading is required for the
location, then a surface reading can be obtained with a portable
reference cell and then by subtracting the reference cell reading,
the voltage drop is obtained.
3.13.3 Surface Reading – Reference cell reading = IR or voltage drop
2.5.5.2.4 The pipeline can be probed and a small diameter/long cylinder
reference cell inserted into the hole where the probing occurred.
This cell is then placed very close to the pipe’s surface without
contacting the pipe.
2.5.5.2.5 A plastic or non‐conductive tube can be installed directly over
the pipeline. The tube should be within one or two inches of the
structure, but not contacting the coating. The tube can be filled
with soil or left open and the reference cell lowered into the
tube for voltage measurements.
2.5.5.3 To minimize IR drop when taking P/S measurements where the structure has
been excavated, the reference cell should be placed in close proximity to the
structure.

<<<PAGE 837>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 6 of 9
3.13.4
2.5.5.4 To minimize IR drop when taking P/S measurements on structures that
extend above grade, the reference cell should be placed in close proximity to
the structure.
3.13.5
2.5.6 Calculation Method
2.5.6.1 2.5.6.2 2.5.6.3 2.5.6.4 2.5.6.5 This method utilizes an extrapolation calculation for considering the IR drop
as further noted below and in Figures 2 and 3 below.
2.5.6.1.1 When potential measurements are taken in close proximity to
another structure, this method will not be valid.
Obtain a P/S measurement directly over the structure or pipeline.
Move the reference cell six feet perpendicular away from the first reading
and obtain a second pipe‐to‐soil reading, called the offset potential.
Obtain the centerline depth of the structure.
Calculate the true or IR free potential using the following formula:
TR = D – A[(E – D)/C] TR = True reading in millivolts
3.13.6 3.13.7
3.13.8

<<<PAGE 838>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 7 of 9
3.13.9

<<<PAGE 839>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 8 of 9
2.5.7 Using Current Interruption
2.5.7.1 2.5.7.2 2.5.7.3 This method utilizes current interruption to obtain what is commonly called
an “Instant Off” potential. The basis for this method is that the IR or voltage
drop disappears when the current is turned off according to Ohms law of E = I
x R. However, care must be exercised when using this option as polarization
may be lost when the interrupters are installed or during the interruption
cycle. Therefore, an 80% duty cycle (8 seconds On and 2 seconds Off) is
suggested.
For proper consideration of IR drop in this method, all current sources must
be interrupted. Foreign current sources must also be interrupted, shut off or
not in operation at the time of consideration.
To consider IR drop in this manner, the following steps should be followed:
2.5.7.3.1 Synchronize all interrupters to be utilized for this type of survey
or consideration method.
2.5.7.3.2 Install the interrupters on all known current sources to include
bonds and foreign and Company cathodic protection facilities.
2.5.7.3.3 Record the “On” and “Instant Off” potentials for the structure
being tested.
2.5.7.3.4 Remove all interrupters and return all facilities to normal
operation.
2.5.7.4 Soil Coupons
2.5.7.4.1 2.5.7.4.2 2.5.7.4.3 2.5.7.4.4 To decrease or eliminate possible errors associated with
“current interruption” coupons can be installed next to the
pipeline simulating a coating defect (holiday).
The coupon should be installed in similar backfill as the structure
to be monitored and installed in accordance with the
manufacture’s recommendation.
The “Off” reading is obtained by measuring the potential of the
coupon while removing it from the cathodic protection circuit.
Polarization decay and Native potential readings can be
obtained while the coupon is disconnected from the cathodic
protection system.
3.13.10

<<<PAGE 840>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 9 of 9
System Integrity Plan Change Log
Date Change
Location
Chan
ged
By
Approv
ed By
Brief Description of Change
12/1/03 Change Log Rick Wooldridge Michael Pearson Added “Changed By”
12/1/03 Document Rick Wooldridge Michael Pearson Replaced Williams with Company
12/1/03 2.3 Rick Wooldridge Michael Pearson
Deleted, “For newly constructed pipelines or facilities, the
Corrosion Technician shall conduct a complete P/S
survey before application of CP. Mark each spot of
electrode placement
1/1/06 All E7 Michael Pearson 2005 annual review complete – no changes
10/26/06 2.1.1.3, 2.5, 4.7 Rick Wooldridge Michael Pearson Removed references to net protective current
01/01/08 All E7 Rick Wooldridge 2007 annual review complete – no changes
1/1/09 All E7 Rick Wooldridge 2008 annual review complete – no changes
11/17/09 All E7 Rick Wooldridge 2009 annual review complete – minor clean-up changes
8/3/10 All E7 Rick Wooldridge
2010 annual review – This procedure was rewritten to
further clarify Magellan’s process for IR Drop
consideration [including the incorporation of historical
corrosion rates and growth calculations].
1/17/11 Various Larry Davied Rick Wooldridge 2011 annual review, Minor revisions
12/31/11 All 2012 Annual Review complete

<<<PAGE 841>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for identifying and mitigating
induced AC.
2.0 PROCEDURE
2.1 Determining the need for induced AC testing.
2.1.1 Determine the need for induced AC testing based on the potential effects on facilities
from High Voltage Alternating Current (HVAC). Primary influences of HVAC systems
include: [see NACE RPO177‐2000 for more information].
2.1.1.1 Resistive Coupling
2.1.1.2 Capacitive Coupling
2.1.1.3 Inductive Coupling
2.1.1.4 Power Arc
2.1.1.5 Lightning
2.1.1.6 Switch Surges or other Transients
2.1.2 Tests that may indicate Induced AC include the following:
2.1.2.1 Inadequate Pipe‐to‐Soil (P/S) potential readings
2.1.2.2 AC potential readings
2.1.2.3 Predictive modeling
2.1.3 Likely areas for Induced AC:
2.1.3.1 Pipelines or facilities that enter or exit the electrical gradient of an HVAC
system
2.1.3.2 Pipelines or facilities paralleling in close proximity to an HVAC system
2.1.3.3 Pipelines or facilities in close proximity to an HVAC Sub‐Station
2.1.3.4 Pipelines or facilities in close proximity to HVAC Towers and/or grounding
systems
2.2 Testing for and Determining the Effects of Induced AC
2.2.1 Identify test leads and/or above ground appurtenances to be tested based on
information in 2.1.3 above.
2.2.2 Measure the AC potential using an AC voltmeter. Contact resistance should be
sufficiently low to preclude measurement errors. Suitable references for measurements
include:
2.2.2.1 2.2.2.2 2.2.2.3 A metal rod inserted into the earth until no further increases in AC
potential are noted.
Bare pipeline casings, if adequately isolated from the carrier pipe.
Tower legs or power system neutrals, in close proximity to the affected
structure.

<<<PAGE 842>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 2 of 5
2.2.2.4 Reference electrodes designed for gathering cathodic protection data (i.e.
half‐cells, permanent reference electrodes, etc.)
CAUTION: Meter connections may present a hazard during switching
surges, lightning strikes, or fault conditions.
2.2.3 Analyze the AC P/S reading from step 2.2.2 of this procedure to determine if soill
resistivity data is required. Criteria includes:
2.2.3.1 AC potentials greater than 10 volt
2.2.3.2 Human shock hazards have been identified (electrical shocks may occur at
a voltage below the 15 volt threshold recommended by NACE, while not
life threatening, mitigation may be necessary to address these shocks.)
2.2.3.3 Areas were AC potentials are cyclic, unstable, or inconsistent over time.
2.2.3.4 Areas were AC corrosion has been identified
2.2.4 If soil resistivity measurements are not required go to 2.7 below.
2.3 Soil Resistivity
2.3.1 Collect soil resistivity measurements at each location as selected per 2.2.3.
2.4 AC Current Density
2.4.1 Using the AC voltage measured in 2.2.2 and the soil resistivity measured in 2.3.1
determine the calculated AC current discharge density per the AC current density
calculator in section 2.4.2. Note: Holiday size should be selected based on the typical
holiday size expected on the pipeline.
2.4.2 AC Current Density Calculator
Calculating AC Current Density
Inputs
AC Voltage 10 volts
Soil Resistivity 5000 ohm-cm
Holiday Size 6 cm2
AC Current Density 18.42633309 A/m2
AC Corrosion Potential
AC corrosion not likely
Cathodic Protection Criteria
100mv polorization
AC Mitigative Action
No action required
AC Voltage Measured or calculated
Soil Resistivity Measured or expected

<<<PAGE 843>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 3 of 5
2.4.3 2.4.4 2.4.5 The AC Current Density Calculator utilizes the relationship between the AC driving
voltage, soil resistivity, and the estimated size of the coating holiday from which current
can discharge, to estimate the discharge density. Where a more precise current
discharge density is required coupon test stations should be installed.
Determine the potential for AC corrosion
2.4.4.1 AC Current Density <20 A/m2 = AC Corrosion not likely
2.4.4.2 AC Current Density >20 A/m2 but <100 A/m2 = AC Corrosion unpredictable
2.4.4.3 AC Current Density >100 A/m2 = AC Corrosion is likely
Determine the need for mitigative action (see AC current density calculator in section
2.4.2)
2.4.5.1 2.4.5.2 2.4.5.3 2.4.6 AC Current Density <20 A/m2 = No action required
AC Current Density >20 A/m2 = Action required
Rule of Thumb: When the AC potential, in millivolts (mV), is greater than or
equal to the resistance of the soil, in ohm‐cm; a more detailed analysis
and/or mitigation is typically required.
Determine the criteria for cathodic protection ((see AC current density calculator in
section 2.4.2)
2.4.6.1 2.4.6.2 2.5 2.6 AC Current Density <20 A/m2 = 100 mV polarization
AC Current Density >20 A/m2 but <500 A/m2 = 150 mV to 250mv
polarization
2.4.6.3 AC Current Density >500 A/m2 = Cathodic protection is not effective in
mitigating corrosion
Mitigative Action – Cathodic Protection can be effective at mitigating AC corrosion
2.5.1 Measure and/or calculate the target ON potential for each test point within the area
affected by Induced AC.
2.5.1.1 Target ON is the potential, with current applied, where polarization equal
to the native potential, plus the cathodic protection criteria established in
2.4.6 is achieved.
2.5.2 Document the Target ON potential in the Corrosion Database (CPDM).
2.5.3 Utilize the target ON potential as the criteria for cathodic protection. This criteria may
be used as long as there are no significant changes in the environment, structure,
coating, cp systems, etc.
2.5.4 Supplemental cathodic protection and/or coating rehabilitation will be required if the
adequate cathodic protection potentials are not achieved.
Mitigative Action – In addition to adequate cp as defined in 2.5, managing the negative effects
from Induced AC or lightning is accomplished by reducing the interference voltage and/or
providing a path to ground for damaging current.
2.6.1 Select and install the appropriate grounding equipment. This equipment may include:
2.6.1.1 Grounding rods (typically made of zinc, copper, graphite or cast‐iron)

<<<PAGE 844>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 4 of 5
2.6.1.2 2.6.1.3 installed where the pipeline enters and exits the electrical gradient of a
HVAC system and at select locations where the pipeline parallels the
HVAC system.
Grounding ribbons (typically made of zinc or copper) installed parallel
with and directly connected to the pipeline along the distance where the
pipeline is influenced by the HVAC system.
Ground mats (typically made of zinc or copper) should be installed at
valves, metallic vents, cathodic protection test stations, and other above
ground appurtenances where electrical contact with the affected
structure is possible. Grounding mats should be large enough to extend
beyond the area on which a person may be standing when contacting the
affected structure and close enough to the surface that step and touch
potentials are adequately reduced.
3.13.11 NOTE: If the ground rod material used has a
native voltage potential less negative than
the ‐1 volt (as compared to copper‐copper
sulfate electrode) an isolation device must
be installed to block the flow of DC, while
passing AC. Caution is advised when using
grounding material with a native potential
more negative than the pipeline as the
ground will be anodic to the pipeline and
thus corrode.
2.6.1.4 2.6.1.5 Where AC surge currents or lighting is a concern, electrical bonds
designed to pass AC, should be installed across insulating flanges to
prevent arcing.
Groundbeds utilized for cathodic protection of the pipeline or facility will
provide mitigative grounding as described above. However, precautions
should be taken to protect the electrical equipment and wiring from
lighting and surge current damage.
3.0 Monitoring
3.1 Induced AC and lightning mitigation equipment should be monitored to ensure its continued
effectiveness.
3.2 In areas where induced AC currents have been identified, coupon test stations should be
installed and monitored.
4.0 DOCUMENTATION
4.1 Data collected as part of this procedure shall be documented in appropriate sections of the
Corrosion Control database (CPDM).

<<<PAGE 845>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 5 of 5
System Integrity Plan Change Log
Date Change
Location
Changed
By Brief Description of Change
Approved By
12/06/06 NEW
Rick
Woolridge
Michael
Pearson
New procedure
01/01/08 All E7
Rick
Wooldridge
Reviewed, no changes
All E7 1/1/09
Rick
Wooldridge
2008 annual review complete – no changes
All E7 01/01/10
Rick
Wooldridge
E7 Review; no changes
All E7 01/01/11
Rick
Wooldridge
E7 Review, no changes
9/28/11 2.2.3.1
John
McMahan
Rick
Wooldridge
E7 Review; Changed 1 volt to 10 volts
12/31/11 All 2012 Annual Review complete

<<<PAGE 846>>>

Magellan Midstream Partners, L.P.
OUTSIDE FORCES DAMAGE PREVENTION PROGRAM SIP–ADM–7.05
Asset Integrity 1/01/12 Revision: 8 Page 1 of 3
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity by establishing a consistent and
comprehensive Outside Forces Damage Prevention Program.
2.0 DESCRIPTION
2.1 This initiative incorporates processes to proactively identify and manage risks to outside forces
damage and achieve public safety.
2.2 This program is intended to prevent outside forces damage in the areas of permanent pipeline
markers, ground and aerial surveillance, One Calls, blasting, depth‐of‐cover, right‐of‐way
maintenance, navigable water crossings and line spotting activities.
3.0 STANDARDS
3.1 The Employee shall:
3.1.1 Upon discovery or notification of blasting activity, immediately notify the Asset Integrity
Engineer.
3.1.2 Upon discovery or notification of an encroachment activity, immediately notify the Real
Estate Representative.
3.2 The Asset Integrity Engineer shall:
3.2.1 Investigate, analyze and document the effect of blasting operations per the Blasting
Damage Prevention Procedure. Define recommendations and communicate to the
appropriate Company personnel and the blasting company within 48 hours of the
request. Forward the blasting investigation results, calculations and notes to the
Records Coordinator.
3.2.2 Conduct an engineering impact study per the General Encroachment Requirements to
evaluate potential impacts to Company assets resulting from Third‐Party Encroachment
notifications.
3.3 The Real Estate Representative shall:
3.3.1 Upon notification of an encroachment, initiate the Encroachment Procedure.
3.4 The Field Supervisors shall:
3.4.1 Inspect the surface conditions on or adjacent to each pipeline right‐of‐way in
accordance with the Inspection of Right‐of‐Way Procedure.
3.4.2 Investigate, respond and document right‐of‐way defects identified per the Inspection of
Right‐of‐Way Procedure.
3.5 The Supervisor of Pipeline Integrity shall:
3.5.1 Maintain the Depth of Cover Program (DOC) and the Right‐of‐Way (ROW) Maintenance
Program.
3.5.2 Coordinate the implementation, execution, and documentation of the work required by
the DOC and ROW Maintenance Program.

<<<PAGE 847>>>

Magellan Midstream Partners, L.P.
OUTSIDE FORCES DAMAGE PREVENTION PROGRAM SIP–ADM–7.05
Asset Integrity 1/01/12 Revision: 8 Page 2 of 3
3.6 The Pipeline Integrity Coordinator shall:
3.6.1 3.6.2 Execute and document the work required by the Depth of Cover Program.
Execute and document the work required by the Right‐of‐Way (ROW) Maintenance
Program.
3.6.3 Upon notification of flooding conditions initiate the process outlined in the Flood
Conditions Procedure and update management on a regular basis.
Evaluate marker placement relative to the Mark Lines Procedure. Replace or repair
3.7 The Asset Locator shall:
3.7.1 3.7.2 missing and damaged markers as necessary.
Complete Pipeline Maintenance Report and the Short Form Encroachment Agreement
3.7.3 and submit to the Records Coordinator.
Contact the appropriate Real Estate Representative and utilize Encroachment
Agreements before allowing any encroachment to the existing right‐of‐way using the
general Encroachment Requirements.
3.7.4 3.7.5 Respond to all dispatched One Call tickets in accordance with the One Call Program.
Respond to One Call notifications, and mark Company pipeline assets in accordance with
the One Call Program and the Line Locating Procedure.
3.7.6 Notify the Pipeline Integrity Coordinator of Flood Conditions and follow the Flood
Conditions Procedure.
3.8 3.9 3.10 The One Call Team Lead shall:
3.8.1 Maintain the One Call Program as described in the One Call Program.
The One Call Coordinator shall:
3.9.1 Analyze and administer One Call notifications in accordance with the One Call Program.
The Regulatory Compliance Coordinator shall:
3.10.1 Implement the One Call Violation Process including initiating a review with the Legal
3.10.2 Department to determine the appropriate path forward.
Advise PHMSA as described in the Flood Conditions Procedure.

<<<PAGE 848>>>

Magellan Midstream Partners, L.P.
OUTSIDE FORCES DAMAGE PREVENTION PROGRAM SIP–ADM–7.05
Asset Integrity 1/01/12 Revision: 8 Page 3 of 3
System Integrity Plan Change Log
Date Change
Location
Change By Approved By: Brief Description of Change
9/29/04 3.2 Bronson Michael Pearson Moved 3.2.2 & 3.2.3 from “Field Based Supervisors”
9/29/04 3.4 Bronson Michael Pearson Changed title to “Field Based Supervisors” from
“Field Based Managers”
9/29/04 3.5 Bronson Michael Pearson Changed Title to “Pipeline Integrity Engineer” from
“Engineering & Construction Manager”
9/29/04 3.6 Bronson Michael Pearson Added 3.6.2 ROW Maintenance Program & 3.6.3
Overhead Crossing Program
9/29/04 3.7 Bronson Michael Pearson Deleted ROW Maintenance Program and moved to
Pipeline Integrity Coordinator
9/29/04 3.7.5 Bronson Michael Pearson Added Short Form Encroachment
9/29/04 3.8 Bronson Michael Pearson Added 3.8 & 3.8.1 One Call Analyst
9/29/04 3.9 Bronson Michael Pearson Added 3.9.1 & 3.9.3 One Call Violations
9/29/04 4.0 Bronson Michael Pearson Added “1‐Call Violation Process Map” link
9/29/04 All Bronson Michael Pearson Conducted 2004 Annual Review
11/15/05 All Greg Walker Michael Pearson Conducted 2005 Annul Review
01/01/06 3.2, 3.3, 3.6 Greg Walker Michael Pearson Changed titles to reflect re‐organization in Asset
Integrity
01/01/06 3.1.6 Greg Walker Michael Pearson Deleted Pipeline Maintenance Procedure.
01/01/06 3.2 Greg Walker Michael Pearson Changed title to Risk Engineer.
01/01/06 3.1 Greg Walker Michael Pearson Removed AI Manager Responsibilities
6/5/06 5.0 Greg Walker Michael Pearson Deleted Measures
01/01/07 All Greg Walker Michael Pearson Conducted 2006 Annual Review
9‐11‐07 All Greg Walker Michael Pearson Conducted 2007 Annual Review. See change log
9‐11‐07 3.3.1 Greg Walker Michael Pearson Change Encroachment Process to Encroachment
Procedure
9‐11‐07 All Greg Walker Michael Pearson Updated Titles per Org changes.
9‐25‐08 All Greg Walker Doug Chabino Removed Shell Consent Decree References –
Annual Review
12/31/09 3.1.3 Kelli Riddle Kelli Riddle removed
1/1/10 All Annual review complete
9/3/10 3.2.2 Dennis Vasicek Added reference to 7.05‐ADM‐035 – General
Encroachment Requirements
3.6.3, 3.7.6,
3.10.2
added
12/31/11 All 2012 Annual Review complete

<<<PAGE 849>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized process for safely marking the
Company rights‐of‐way (ROW) with permanent line markers, in order to:
1.1.1 1.1.2 1.1.3 1.1.4 Meet all applicable DOT requirements.
Effectively delineate the pipeline corridor.
Promote public and community awareness.
Identify the pipeline location for effective damage prevention.
2.0 SCOPE
2.1 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on non‐jurisdictional assets as deemed
appropriate.
2.2 Assets covered per the Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, other specific marker
requirements may be stated within the Mitigation Plan. Refer to the Mitigation Plan for those
requirements.
2.3 Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree. For the period of the Consent Decree,
these systems will follow the applicable process and procedures (see Consent Decree for
applicable programs).
3.0 PROCEDURE
3.1 Consider using the most appropriate marker type, as dictated by the existing conditions.
3.1.1 3 inch PVC schedule 40 pipe with 3” cap, black/red color coded decal six inches from top
of post, with warning decal or warning sign as appropriate. Refer to the Standards List.
3.1.2 Flexible fiberglass composite markers.
3.1.3 Bullet style markers.
3.2 The following special tools/equipment/materials as required for permanent pipeline marking:
3.2.1 Applicable assembled marker post or marker.
3.2.2 Pipeline Warning Decals. Refer to the Standards List.
3.2.3 “Pipeline Under Pavement” decals/or signs where applicable.
3.2.4 Color‐coded decals or stickers.
3.2.5 Signs must include “Warning” followed by “Petroleum Pipeline” with letters at least 1
inch high with an approximate stroke of ¼ inch, Company name and 24 hr phone
number.
3.2.6 Posthole digger.
3.2.7 Shovel.
3.2.8 Appropriate post driver.

<<<PAGE 850>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 2 of 5
3.2.9 Auger.
3.3 Markers must be placed and maintained over each buried pipeline at the following locations:
3.3.1 Each public road crossing.
3.3.2 Each railroad crossing.
3.3.3 Where the line is above ground in areas that are accessible to the public
3.3.4 In sufficient numbers along the remainder of each buried line so that its location is
accurately known. Where practical and appropriate, use the following guidelines to
establish locations for additional pipeline marker placement:
 Interior cross fences
 Both sides of creeks and rivers
 Both ends of all pipeline exposures
 Developed area, commercial and residential
 Vast areas with few fences or areas with changing elevations that limits marker
visibility.
 Markers should not be placed in an area that impedes and/or prevents landowners
or tenants (e.g. ranchers, farmers businesses, etc.) from conducting daily activities,
or where prohibited by local ordinances. These are best handled on a ‘case by case’
basis; consult immediate Supervisor with questions or unique circumstances.
3.4 Installation of Pipeline Markers:
3.4.1 When applicable, notify landowner prior to entering property.
3.4.2 When excavating activities are required pertaining to installation of marker posts, follow
applicable state One Call regulations. (i.e. use of an auger or posthole digger, etc.)
3.4.3 Locate pipeline per Pipeline Locating Procedure.
3.4.4 Dig post hole for 3” post or drive markers as appropriate.
3.4.5 When required, install milepost numbers directly below warning decal or warning sign
(at road crossings and valve sites).
3.4.6 For pipelines paralleling roadways located under the surface of the roadway where
marker placement is not practical, markers should be placed at the nearest location
adjacent to the pipeline and a “pipeline under pavement” decal placed beneath the
existing Company warning decal.
3.4.7 Pipeline markers will be placed as close to the line as possible, however, when a marker
is offset a greater distance than five feet from the pipeline; notify the appropriate Asset
Integrity Supervisor.
3.5 Assets covered per the Mitigation Plan:
3.5.1 3.5.2 All markers shall be within line of sight of one another in Tier I Areas.
If one marker is removed, the location of the pipeline can still be identified from either
direction from any point in between Tier II and Tier III Areas

<<<PAGE 851>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 3 of 5
3.6 3.5.3 3.5.4 3.5.5 3.5.6 3.5.7 3.5.8 All line markers will be written in English and Spanish.
Marker placement and density will be evaluated routinely through aerial and ground
surveillance.
Missing and damaged markers will be replaced within seven days of discovery.
Markers will be located at all aboveground facilities to identify the operator of the
system.
When practical fence crossings will have fence post on either side painted bright yellow
to aid in the identification of the pipeline easement width.
Documentation will be completed using Mitigation Right of Way Inspection Form,
making appropriate comments including: Stationing, GPS coordinate (where possible),
land use change or increased density due to Tier I, Tier II and Tier III requirements, etc.
Install aerial milepost markers on jurisdictional lines that are patrolled by aerial methods as
follows:
NOTE: Aerial Markers are for reference only and may not reflect exact stationing.
3.6.1 3.6.2 3.6.3 3.6.4 3.6.5 3.6.6 Construct Aerial Markers on a triangle framework with mile number identified facing up
and down stream. Numbers should be of sufficient size to be seen by aerial patrol pilots
with the number being black on a yellow background. Refer to the Standards List.
Use heavy gauge aluminum or fiberglass, with decal numbers and arrows.
Aerial marker numbers should be assigned to match the nearest milepost number as
documented on alignment sheets.
Place along all mainline ROW, positioned so that they are legible as a pilot flies the line.
Place at public road crossings or other appropriate points (distance between markers
generally not to exceed one mile).
Use special markers with arrows slanted left, right or vertical to direct pilot around
locations requiring deviation of flight.

<<<PAGE 852>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 4 of 5
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
010/01/05 Reviewed, no changes
Troy Bronson 01/01/06 2.2.7
Replaced “Examples of universal wastes include lead acid batteries, pesticides,
thermostats with liquid mercury, and florescent light bulbs.” With “Pipeline
markers will be placed as close to the line as possible, however, when a marker is
offset a greater distance than 5’ from the pipeline, a Maintenance Report will be
generated documenting the placement and reason why.”
01/01/06 2.4.1 Troy Bronson Added “Follow applicable state one‐call regulations pertaining to installation of
marker posts.”
01/01/06
Troy Bronson 2.5.1
Replaced “Numbers on signs to be 4” X 6” with the number being black on a
yellow background.” With “Numbers should be of sufficient size to be seen by
aerial patrol pilots with the number being black on a yellow background.
Recommended size of the sign is 6” x 15” with numbers 4 ½ ” x 13 ½ “.”
01/01/06 2.5.5 Troy Bronson Removed note box: When more than 1 pipeline mile is traveled and a public road
is passed without seeing a marker, the marker is considered to be missing.
01/01/06 4.2.1 Troy Bronson Added Line Locating link
01/01/06 2.2.2 Troy Bronson Added “where applicable”.
01/01/06 Applicability Dan Egner Added complete section
01/01/06 1.0 thru 1.1.4 Dan Egner Major modification
01/01/06 2.1 thru 2.1.3 Dan Egner Major modification
01/01/06 2.2.1 Dan Egner Changed to “Applicable markers”
01/01/06 2.2.9 Dan Egner Added “appropriate”
01/01/06 2.3.1 Dan Egner Removed “railroad”
01/01/06 2.3.2 Dan Egner Added “Both sides of all railroad crossings”
01/01/06 2.3.3 Dan Egner Added “appropriate and practical”
01/01/06 2.3.6 Dan Egner Added complete subpart
01/01/06 2.2.6.1 Dan Egner Added for the Consent Decree
01/01/06 2.3.10 thru
2.3.15
Dan Egner Added for the Longhorn Pipeline
01/01/06 2.4.1 Dan Egner Added “where applicable”
01/01/06 2.5.7 Dan Egner Removed (…”only”) added (…”and valve sites”)
01/01/06 2.6 Dan Egner Added NOTE:
01/01/06 2.6.3 Dan Egner Major modification
01/01/06 2.7 thru 2.7.1 Dan Egner Added subparts
01/01/06 2.8 thru 2.8.3 Dan Egner Added subparts
01/01/06 2.9 thru 2.9.2 Dan Egner Added subparts
01/01/06 4.1.2 Dan Egner Added regulation
01/01/06 4.3.2 Dan Egner Added form
01/01/06 5.5 Dan Egner Added definition
01/01/06 Removed references, renamed links
02/01/06 3.3 Clyde Clausen Added section 3.3
02/01/06 3.4 Clyde Clausen Modified section 3.4
02/01/06 3.5 & 3.6 Clyde Clausen Added 3.5 and 3.6 (Consent and Longhorn Specific)
02/01/06 3.7 Clyde Clausen Modified paragraph 3.7
02/01/06 3.8 Clyde Clausen Deleted and incorporated into 3.7
02/01/06 3.9 Clyde Clausen Deleted and incorporated into 3.5

<<<PAGE 853>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 5 of 5
2/3/06 3.2.3 Troy Bronson Changed “sign” to “decal”.
2/3/06 3.2.5 Troy Bronson Deleted “Cordless Drill”
2/3/06 3.7.7 Troy Bronson Insert “standards” link.
2/3/06 3.7.8 Troy Bronson Changed “Sign” to “Decal”.
2/3/06 3.7.9 Troy Bronson Changed “Sign” to “Decal”.
2/3/06 3.7.10 Troy Bronson Changed “contact” to “notify”.
1/1/07 3.7 Greg Walker Link to Pipeline Locating Procedure
5/22/07 3.0 Greg Walker Consolidate procedures. Added information about Warning sign details.
5/22/07 3.3.4 Greg Walker Added clarification where markers should be placed.
12/12/08 2.3 Tim Boudreaux Modified the Consent Decree statement to exclude the previous Consent Order.
12/12/08 4.0 Tim Boudreaux Deleted Pipeline Marker Repair report form link.
12/12/08 4.4 Tim Boudreaux Included Longhorn Mitigation Plan.
01/01/2009 Tim Boudreaux Conducted annual review with no changes.
01/01/2009 3.5.7 Tim Boudreaux Included Longhorn specific documentation requirements.
3‐26 3.5.6 Greg Walker Included Longhorn specific documentation requirements.
9/01/09 2.2 Tim Boudreaux Deleted Longhorn Specific
9/01/09 3.5 Tim Boudreaux Changed Longhorn Specific to Assets covered per Mitigation Plan
9/01/09 3.5.8 Tim Boudreaux Deleted Longhorn
9/01/09 4.4 Tim Boudreaux Deleted Longhorn
9/01/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual review complete – no changes

<<<PAGE 854>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 1 of 5
1.0 Objective
1.1 To establish standardized and consistent processes for pipeline operations and maintenance in
regards to Navigable River Crossing Inspections.
2.0 SCOPE
2.1 2.2 2.3 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on nonjurisdictional assets as deemed
appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices. This pipeline operates
under the requirements of the Mitigation Plan.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree (see Consent Decree for applicable
programs).
3.0 PURPOSE
3.1 Navigable River Crossings
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 The Pipeline Integrity Coordinator shall annually review the list of pipeline crossings of
navigable rivers contained in this procedure to ensure the crossings are inspected within
the required timeframe.
Pipeline Integrity shall be responsible for having these inspections made and for
maintaining the records of such inspections. The inspection records shall be maintained
for five years or until another inspection is performed. The results of such inspections
will be compared with the previous crossing records to determine any change. Should
the inspection indicate that repairs need to be made to the crossing, Pipeline Integrity
shall be responsible for having suitable repairs performed.
Each pipeline crossing under a DOT identified navigable waterway will be inspected at
intervals not exceeding five years. For this inspection, navigable waterways are defined
as waterways subject to commercial barge traffic.
The inspection shall be conducted by third party personnel qualified to carry out such
inspections and to prepare permanent records of their findings.
The inspections shall determine the pipeline location and any exposed pipe within the
limits of the navigable waterway and the right‐of‐way immediately adjacent on each
side.
The permanent records shall be of sufficient detail to compare with the previous
crossing records to determine any change in the location of the pipeline. They shall also
indicate if any, the length and location of exposed pipeline. The third party inspector
will prepare both plan and profile drawings detailing the findings of the inspection.
4.0 PROCEDURE
4.1 Navigable River Crossing Inspections

<<<PAGE 855>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 2 of 5
4.2 4.3 4.1.1 Contractor will reestablish base line indicated on plan drawing and accurately determine
route of the pipeline through the river with reference to this line. The length of this
traverse will extend between convenient points on the banks. These points will be
above water level and at least 50 feet from the edge of the water.
4.1.2 Location of pipe will be determined by the use of an induced tone or
transmitter/receiver pipe locator.
4.1.3 The river bottom and banks between reference points will be profiled over the pipe with
elevations referenced to the existing bench mark shown on drawing. If existing
benchmark has been destroyed, Contractor will set a new bench mark in as permanent a
manner as possible.
4.1.3.1 Profile data will also include elevation of water level and top of pipe at all
exposed and suspended sections. Vertical measurements for profile may
be made by use of a portable Fathometer or weighted sounding chain. On
pipeline inspections where sufficient cover cannot be determined from the
profile, a diver is required to complete the inspection.
4.1.4 A diver will make passes over each pipe at intervals of 20 feet or less and if exposed or
suspended pipe is located, the diver will follow these sections with continuous passes.
He will also determine size and location of any build‐up of debris against exposed or
suspended pipe section, the condition of pipe and/or pipe coating, the nature of the
river bottom at the pipe, and any other underwater condition that may appear to
adversely affect the safety of the pipeline crossing such as scouring of the river bottom
or undercutting of the banks. Sonar equipment may be used to detect exposed pipe
instead of a diver.
Forward results of this survey and the inspection individual written reports for each crossing site.
Submit reports to the Pipeline Integrity Project Manager and include, at least the following:
4.2.1 A list of all exposed and suspended pipe sections located by station numbers
and showing clearance between pipe and river bottom.
4.2.2 Identification of changes from last inspection.
4.2.3 Recommendations for repair.
Contractor will supply plan and profile sheets of each pipeline surveyed at the crossing
site. One plan and profile sheet will be used for each single pipeline crossing the stream.
4.3.1 Show dual lines. Include the river bottom and adjacent banks between reference points
in the drawings.
4.3.2 Show the condition of the pipe coating, all obstructions and sharp objects, all unusual
conditions, such as exposed or suspended pipe, and the location and elevation of
benchmarks used by Contractor in the drawings. The profile drawing of the pipeline will
extend to a minimum of fifty (50) feet beyond the edge of the water on each side of the
river.
4.3.3 Show pipe, river bottom and water elevations from previous inspections (when known)
on the drawings.
4.3.4 Retain the inspection records that relate to the navigable river inspections for five years
or until a new inspection is performed.

<<<PAGE 856>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 3 of 5
4.4 The following crossings are listed as being across navigable waters:
Navigable River Crossings
State Line Section Waterway #Of Spare
Lines
Eng. Station Date Last
Inspection
Date Next
Inspection
Delaware Wilmington 10” Pipeline Christina River 0 66+18 06/11/10 06/11/15
Illinois 106#3‐12" TCS IL‐Wilmington Illinois River 0 26507+04 08/12/08 08/12/13
036 #5‐8" Des Moines‐ MS River Mississippi River 0 9026+14 05/14/07 05/14/12
037 #6‐12" Des Moines‐ MS River Mississippi River 0 9028+96 05/14/07 05/14/12
Iowa 054 #5‐12 Irv ‐ Sioux Falls Missouri River 1 12520+79 08/17/11 08/17/16
Nebraska/
Iowa
West Leg NH3 Missouri River 0 14272+87 08/18/11 08/18/16
Kansas 006 #3‐8" Barnsdall ‐ KC Kansas River 0 10171+48 08/08/08 08/08/13
007 #4‐12 Barnsdall ‐ KC Kansas River 0 10178+52 08/08/08 08/08/13
008 #5‐12" Barnsdall ‐ KC Kansas River 0 10187+55 08/08/08 08/08/13
023 #4‐8" Argentine ‐ KC Kansas River 0 164+00 08/08/08 08/08/13
Kansas/
Missouri
18th Street to Riverside 8” Missouri River 0 10370+33 09/01/11 09/01/16
Louisiana GeoNet Bayou Black 1 08/19/08 08/19/13
Minnesota 069 #7‐8" Rose ‐ Mpls. Air Minnesota River 0 661+44 05/15/07 05/15/12
070 #6‐12" Rosemount ‐ Willmar Minnesota River 0 760+59 05/15/07 05/15/12
121#3‐8" StPP (Aranco) ‐ Pine Bend Mississippi River 0 113+45 05/16/07 05/16/12
007 #4‐12” Des Moines to
Minneapolis
Mississippi River 1 12740+77 05/16/07 05/16/12

<<<PAGE 857>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 4 of 5
Navigable River Crossings
State Line Section Waterway #Of Spare
Lines
Eng. Station Date Last
Inspection
059 #1‐6" Alex ‐ Grand Forks Red River of The
North
0 5222+47 05/18/07 060 #2‐8" Alex ‐ Fargo Red River of The
North
0 5217+64 05/18/07 Missouri 080 #7‐8” Olathe to Columbia Missouri River 0 6714+85 08/22/11 095 #7‐16" Wathena ‐ Des Moines Missouri River 0 9775+35 08/23/11 105 #3‐12 ' TCS MO ‐ IL Line Mississippi River 1 24398+70 08/10/08 Oklahoma 013 #1‐12” Tulsa‐Barnsdall Arkansas 0 48+35 09/21/10 012 #4‐12” Tulsa‐Barnsdall Arkansas 0 48+24 09/21/10 108 #4‐12” Tulsa‐Tulsa Jct. Arkansas 1 48+24 09/21/10 Oklahoma Verdigris Lateral 6” NH3 Verdigris River 0 6426+05 03/04/09 Texas Amerada Hess Houston Ship
Channel
3 151+00 03/31/09 Texas City to Pasadena 18” Clear Lake 0 729+00 04/25/09 Wisconsin 047 #1‐8" Newport ‐ Bateman St. Croix River 0 620+13 05/17/07 Date Next
Inspection
05/18/12
05/18/12
08/22/16
08/23/16
08/10/13
09/21/15
09/21/15
09/21/15
03/04/14
03/31/14
04/25/14
05/17/12

<<<PAGE 858>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 5 of 5
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
12/22/04 New Procedure Tim Boudreaux Removed Navigable River Crossing section from Pipeline
Maintenance Document and created new Procedure for Navigable
River Crossings.
12/22/04 3.1.2 Tim Boudreaux Included text “On pipeline inspections where sufficient cover cannot
be determined from the profile, a diver is required to complete the
inspection.
12/15/05 3.4 Tim Boudreaux Included inspection dates on Amerada Hess pipelines and included new
asset inspection for Wilmington 10” pipeline.
12/15/05 Intro Tim Boudreaux Included Applicability Statement.
1/1/07 List Tim Boudreaux Updated list for 2006 completed inspections.
01/01/08 Reviewed, no changes
12/18/08 2.3 Tim Boudreaux Modified Consent Decree Specific.
12/18/08 4.4 Tim Boudreaux Updated List of navigable inspections.
01/01/09 Tim Boudreaux Annual Review with no changes.
9/01/09 2.2 Tim Boudreaux Deleted Longhorn
9/01/09 4.4 Tim Boudreaux Updated list of navigable inspections
9/01/09 5.1 Tim Boudreaux Deleted Longhorn
9/01/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
09/02/11 3.1.1 Dennis Vasicek
Added sentence regarding Pipeline Integrity Coordinator’s
annual review of list of navigable river crossings
09/02/11 4.4 Dennis Vasicek
Added 18th Street to Riverside 8” crossing of the Missouri
River and Texas City to Pasadena 18” crossing of Clear Lake
09/02/11 4.4 Dennis Vasicek Updated inspection dates
12/31/11 All 2012 Annual Review complete

<<<PAGE 859>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 1 of 3
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for
the investigation and monitoring of areas of the pipeline identified as
having high susceptibility to earth movement or where earth movement
has been identified.
E: Characterizing an area, as having high susceptibility to earth movement
does not imply certainty that earth movement will occur or that earth
movement is not possible outside an area of high susceptibility.
2.0 SCOPE
2.1 2.2 2.3 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on nonjurisdictional assets as deemed
appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, This pipeline operates
under the requirements of the Mitigation Plan.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations,
as well as Company guidelines, process, or best practices, the Company’s Consent
Decree Pipeline Systems operate under the requirements of the Consent Decree (see
Consent Decree for applicable programs.
3.0 PROCEDURE
3.1 Identifying Areas for Inspection. Specific pipeline segments may have regulatory
requirements outside DOT 49 CFR. Please refer to those specific Plans for their
individual requirements, as listed above in Applicability.
3.1.1 Identify areas to be inspected as defined by the Earth Movement Section of the Depth
of Cover Program.
3.2 below.
3.2.1 Select the appropriate inspection method using the guidelines established in 3.2.1 and 3.2.2
3.3 3.4 3.5 Use aerial patrol for inspection and monitoring of areas with high susceptibility to
earth movement. If aerial patrol is the selected inspection method go to 3.3 below.
3.2.2 Use close visual inspection in areas where earth movement has been identified. If
close visual inspection is the selected inspection method go to 3.4 below.
Performing Inspection and Monitoring Utilizing Aerial Patrol
3.3.1 Conduct aerial patrol in accordance with the Inspection of Right‐of‐Way Procedure.
Pay particular attention, within the target area, to signs or indicators of earth movement
or subsidence such as ground cracks, sink holes, erosion, heaving, buckling, etc.
3.4.1 If earth movement is identified go to 3.5 below otherwise go to 3.6 below.
Performing Inspection and Monitoring Utilizing Close Visual Inspection

<<<PAGE 860>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 2 of 3
3.5.1 Conduct close visual inspection in accordance with the Inspection of Right‐Of‐Way
Procedure.
3.5.2 Document the nature of the earth movement specifying the type of movement, extent
of the affected area (length, width, depth), age, characteristics, soil type, etc. using
both a written description and photography (where possible).
3.13.12 NOTE: Notify the appropriate Asset Integrity Engineer as
soon as practical to discuss additional data requests and
the next course of action.
3.6 Documentation
3.6.1 Use the Pipeline Maintenance Report to document any findings, with copies sent to
the Asset Integrity Engineer for continued evaluation.
4.0 Definitions
4.1 4.2 Earth Movement: Unintended movement of the soil around the pipeline.
High Susceptibility (to earth movement): An area along the pipeline identified through risk
assessment as having a higher likelihood of earth movement as compared to other relative
locations.
3.13.13

<<<PAGE 861>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 3 of 3
System Integrity Plan Change Log
Date CHANGE
LOCATION
Changed By Brief Description of Change
1/4/03 New Rick Wooldridge New Procedure
01/01/06 Applicability Tim Boudreaux Included language to direct to Longhorn and Shell specific
requirements.
01/01/06 2.1.1 Tim Boudreaux Included: “Specific pipeline segments may have regulatory
requirements outside DOT 49 CFR Parts 195 or Parts 192.
Please refer to those specific Plans for their individual
requirements, as listed above in Applicability”.
Applicability
2.0
Changed to Scope
01/01/07 Reviewed, no changes
01/01/08 Reviewed, no changes
12/18/08 2.3 Tim Boudreaux Modified Consent Decree Specific.
01/01/09 Tim Boudreaux Annual Review with no changes.
9/03/09 2.2 Tim Boudreaux Removed Longhorn and Replaced with Assets covered per
Mitigation Plan
9/03/09 4.3 Tim Boudreaux Removed Longhorn and Replaced with Assets
covered per Mitigation Plan
9/03/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 862>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 1 of 6
1.0 Purpose
1.1 The purpose of this procedure is to effectively manage Overhead Pipeline Crossing
maintenance through a comprehensive risk-based program which identifies risk reduction
projects to improve structural component integrity and ultimately keep the product in the
pipe.
2.0 SCOPE
2.1 2.2 2.3 Consent Decree Specific: : In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, the Company’s
Consent Decree Pipeline Systems operate under the requirements of the Consent
Decree. For the period of the Consent Decree, these systems will follow the applicable
process and procedures (see Consent Decree for applicable programs).
3.0 PROcedure
3.1 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities. The
Manager of Asset Integrity may utilize elements of this program in whole or part on
nonjurisdictional assets as deemed appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, this pipeline operates
under the requirements of the Mitigation Plan.
The Overhead Pipeline Crossing Integrity Program will cover all above ground pipeline crossings,
which are cable supported. This Inspection Procedure is structured in a cycle of four recurring
categories:
3.1.1 Gather Data
3.1.1.1 3.1.1.2 Select the initial inspections based on historical knowledge of the condition
of the structures using stakeholder, SME, risk data, and process efficiency
information. Select subsequent inspections using risk data and further
historical knowledge of the structures. The baseline inspections should be
completed within six years and re‐inspections will be conducted on a
timeframe based on the inspection findings and recommendations but not
to exceed ten years from the previous inspection.
Use the following three project‐specific standard forms for the overhead
pipeline structure inspections.
3.1.1.2.1 Use the Basic Data Form to list all the relevant historical and
geometrical information about the structure. Prior to the
initial inspection, locate any available information on the
structures so that as much information as possible may be
filled out on the Basic Data Form. During the field inspection,
this information should then be checked and the remainder
of the information gathered.
3.1.1.2.2 Use the Inspection Report Form during the field inspection to
evaluate and record the existing conditions of the
components on the overhead pipeline structure. Each
component listed is preceded by a box to be used for a rating
number to evaluate the condition of the component and
followed by a line to be used for a verbal description of any

<<<PAGE 863>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 2 of 6
3.1.1.3 3.1.1.4 problems encountered.
3.1.1.2.3 The Photo Log Sheet is used in the field to document
photographs taken of the different overhead pipeline
structures inspected.
The development of a systematic method of inspection for each type of
overhead pipeline structure is important. A well‐planned sequence will
provide a working guide for the inspector and will ensure a systematic and
thorough inspection of all components of the structure.
For the overhead pipeline structure, the components of the structure
should be inspected in the following order:
3.1.1.4.1 Foundations
3.1.1.4.2 Base plates and connections to foundations
3.1.1.4.3 Cable anchorage
3.1.1.4.4 Tower frames
3.1.1.4.5 Saddles
3.1.1.4.6 Main cable
3.1.1.4.7 Suspender cables
3.1.1.4.8 Pipe supports
3.1.1.4.9 Pipeline
NOTE: There are other considerations observed during the
inspection, which will be documented, such as: bank
degradation, obvious flood levels, threatening outside
forces (trees or other structures), right‐of‐way
visibility/marking, public access and vandalism.
3.1.1.5 3.1.1.6 The thoroughness of an inspection is as important as the sequence. Use a
checklist during the inspection to prevent the possibility of any
components being overlooked. The Inspection Form can be used as a basic
outline for the checklist.
Complete full documentation reports for each inspection using the
Overhead Inspection Basic Data Form, the Overhead Inspection Report
Form and the Overhead Inspection Photo Log Sheet. Pipeline Integrity shall
maintain these records for further analysis.
3.1.2 Analyze the Data
3.1.2.1 List all findings on the Inspection Report Form. Use the numerical rating
system (see Table 1 below) to evaluate the condition of the components.
The number best describing the component in the worst condition should
be placed in the box next to the name of the component. Include a written
description for clarification or further explanation. From this information
the SME will make recommendations for maintenance repairs, completion
time limits for making those repairs and a general cost estimate based on

<<<PAGE 864>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 3 of 6
“Rule of Thumb” estimates.
Table 1
Rating Number Rating Description Rating Examples
6 Good Condition 5 Potential Problem 4 Minor Problem 3 Major Problem 2 Critical Problem There are no apparent problems
Rust, corrosion or cracked foundation
Loose bolts, cables, or spalled foundation
Moderate structural cracking or repainting
Major structural defects
3.1.2.2 Analyze the individual component ratings further and give weighted scores
to achieve an overall Relative Risk Index. This will assist in our maintenance
prioritization efforts.
3.1.2.3 Asset Integrity Personnel shall review, approve/reject or submit alternative
recommendations. Repair recommendations will be risk ranked in
accordance to criteria set forth in the Overhead Crossing Inspection
Relative Risk Index Formula.
3.1.2.4 The DOC Coordinator will schedule the maintenance according to these
recommendations and list them on the Annual Integrity Plan.
3.1.3 Develop The Mitigation Plan
3.1.3.1 The DOC Coordinator will assign a Project Manager to complete the
maintenance work. The Project Manager will follow Project Life Cycle for
completing the task.
3.1.3.2 The Project Manager shall follow the recommended maintenance schedule
according to the annual integrity plan for repairs unless otherwise
approved to proceed with any additional repairs, which would improve the
integrity of the structure at a significant cost savings.
3.1.3.3 The Project Manager shall be responsible for all planning, estimating,
contracting and execution of the maintenance repairs.
3.1.3.4 An AFE and Project Plan must be submitted and approved by the DOC
Coordinator before any work may begin, unless the work needed is
considered an emergency and immediate attention is necessary, in which a
courtesy call to the DOC Coordinator is all that is required. The afe request
and documentation of the work performed may follow the repair, in this
case. During the plan development, consult with Area Operations, Asset
Integrity Personnel and third party SME Resources.
3.1.4 Execute the Mitigation Plan
3.1.4.1 Following the approval of the project plan, the Project Manager may
allocate resources and execute the Mitigation Plan while integrating in
synergies with other MMP departments and programs.
4.0 OVERHEAD pipeline cROSSING Prioritization Guidelines

<<<PAGE 865>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 4 of 6
4.1.1.2 4.1 The Overhead Pipeline Crossing Integrity Program, along with any resulting mitigation initiatives,
will be prioritized in accordance with the following guidelines:
4.1.1 Each structure will receive an initial risk prioritization number based on the Pipeline Risk
Model. Factors that may influence the prioritization might be local historical knowledge
of inferior structural conditions, past large water flow events, line strikes, near misses
and HCA locations.
4.1.1.1 The first phase of the inspections will include the top 20% of the structures
listed as highest risk according to the pipeline risk model.
All other structures will follow in 20% groupings according to the risk
model.
4.2 Following the Overhead Pipeline inspection, each structure will receive a relative risk index
number. Maintenance will be performed on the structures that receive the lowest relative risk
index score in accordance with the Integrity Management Plan (IMP).
5.0 Data Management and Initiative Implementation
5.1 Data initially obtained and periodically updated via the Overhead Pipeline Crossing Integrity
Program will be centralized and maintained in a formal database. Pipeline Integrity will utilize
the database as an input to its overall risk management process, which includes the relative risk
assessment process.
5.2 Pipeline Integrity will further manage the recommendation and funding process associated with
the implementation of this initiative.
6.0 REFERENCES
6.1 Regulatory – 49 CFR Part 195 – U.S. D.O.T. Pipeline Safety Regulations
6.2 Related Policies/Procedures
6.2.1 Pipeline Defect Evaluation and Repair Procedure
6.2.2 RSTRENG Analysis of Corrosion
6.2.3 6.2.4 Asbestos Safety Procedure
6.2.5 Excavation Safety Procedure
6.2.6 Welding and Radiographic Procedures
6.2.7 Specification 100—Construction And Fabrication Of Pipelines And Related Piping
Systems
6.2.8 6.3 Forms and Attachments
6.3.1 Pipeline Maintenance Report
6.3.2 6.3.3 6.3.4 Coatings – Selection, Applications and Maintenance
Specification 101—Maintenance Welding (Excluding Ethylene Pipelines)
Prioritization for Exposed Pipe (Flow Chart)
Prioritization for Shallow Pipe (Flow Chart)
Shallow Pipe Resolution Process (Flow Chart)

<<<PAGE 866>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 5 of 6
7.0 DEFINITIONS
7.1 Stakeholder: Any person or group directly involved with this initiative.
7.2 SME: Subject Matter Expert.
7.3 7.4 7.5 7.6 7.7 7.8 7.9 Risk Data: Furnished by the Risk Assessment Group for specific pipeline segments.
Process Efficiencies: Planning optimization of time, materials, labor and funding.
Basic Data Form: A standard form to list the relevant historical and geometrical information
about the structure.
Inspection Report Form: A standard form used during the field inspection to evaluate and
record the existing conditions of the components.
Photo Log Sheet: A standard form for documenting and organizing photos taken at the
inspection site.
Rule of Thumb Estimates: Standard costs associated to specific work in the pipeline industry, as
an average. It is not region specific.
Relative Risk Index Formula: Process by which all component ratings are correlated to give a
final overall Risk Score to assist with process management.

<<<PAGE 867>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 6 of 6
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
1/31/05 All Tim Boudreaux New Procedure
01/01/07 Reviewed, no changes
01/01/08 Reviewed, no changes
12/17/08 2.1 Tim Boudreaux Eliminated redundant sentence.
12/17/08 2.2 Tim Boudreaux Modified Consent Decree Specific.
12/17/08 5.1, 5.2 and 5.3 Tim Boudreaux Removed link for Data record sheet, inspection report and photo log
sheet.
01/01/09 Tim Boudreaux Annual Review with no changes made.
9/03/09 2.2 Tim Boudreaux Deleted Longhorn and changed to Assets covered per Mitigation Plan
9/03/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
09/02/11 3.1.1.1 Dennis Vasicek Revised third sentence to, “The baseline inspections should be
completed within six years and re‐inspections will be conducted on a
timeframe based on the inspection findings and recommendations but
not to exceed ten years from the previous inspection.”
12/31/11 All 2012 Annual Review complete

<<<PAGE 868>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to address specific requirements of the Mitigation Plan related to inspection of the
surface conditions on or adjacent to each pipeline right‐of‐way (ROW). This document is to be utilized along with
the Magellan Midstream Partners, L.P. Inspection of Right of Way Procedure.
2.0 PROCEDURE
NOTE: Persons performing inspection shall comply with all state and federal laws, rules, regulations, statutes, ordinances
or codes and Mitigation Commitments as may be required. In its contracts with inspection contractors, the Company shall
identify requirements specifically related to the petroleum industry. It shall be the obligation of such contractors to comply
and maintain appropriate records
2.1 Methods of Inspection
2.1.1 Aerial Patrol: As described below and in Inspection of Right of Way Procedure.
2.1.2 Ground Patrol: As described below and in Inspection of Right of Way Procedure. Also Refer to the
guidelines in the Threatened and Endangered Species Avoidance And Minimization Timing Restrictions.
2.2 Patrol Requirements
2.2.1.4 Edwards Aquifer Recharge Zone – Daily (once per week shall be a ground‐level
patrol)
2.3 2.2.1 The specified frequency of surveillance shall meet the following requirements:
2.2.1.1 Tier 1 Areas – Once a week, not to exceed 12 days, but at least 52 times per year
2.2.1.2 Tiers 2 and 3 Areas – Every two and one‐half (2.5) days, not to exceed 72 hours
2.2.1.3 Aerial and ground surveillance frequency will be increased across Tier II (Sensitive)
and Tier III (Hypersensitive) areas when the threat of flooding and/or severe erosion
is identified near the pipeline right‐of‐way.
Aerial Patrol and Ground Patrol Notification
2.3.1 Patrol Pilots will be required to contact the Austin Operations Office each morning to communicate the
ability to fly or not to fly, “No‐Fly”, their identified patrol segments. Segments are identified as follows:
2.3.1.1 LP 301 Galena Park to Pecos River (MP 0 – MP 528)
2.3.1.2 LP 303 Crane to El Paso (MP 457 – MP 695), Crane to Odessa (MP 0 – MP 28) and El
Paso to El Paso Jct. (MP 0 – 10)
2.3.1.3 Austin Operation Office will record notification of flight and await completed Right‐
of‐Way Patrol Report by Aerial/Ground form.
2.3.1.4 The Austin FOA will record each patrol on a patrol tracking spreadsheet to insure the
required number of flights are made and file with monthly reports.
2.3.1.5 Upon receipt of the Right‐of‐Way Patrol Report by Aerial/Ground form. The One Call
Group will create a One Call ticket and the field locator will respond to the Aerial
Patrol in Ticket View.
2.3.1.6 Right‐of‐Way (ROW) Inspection Report will be sent to Austin Operations Office and
the One Call Group at the end of the flight day or within 12 hours of flight

<<<PAGE 869>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 2 of 5
2.3.1.7 completion.
All emergency sightings by pilot will be called into the Company One‐Call Center. The
Company One‐Call Center will send to the field as an emergency ticket under the
heading A/P (Aerial Patrol). All A/P emergency tickets will be responded to
immediately by field personnel. Non‐emergency sightings will be reported on Right‐
of‐Way Patrol Report by Aerial/Ground form and responded to within 3 working days
and documented by the appropriate personnel upon receipt of the report.
NOTE: Daily patrols of these segments shall continue until confirmation of flight by the
Patrol Pilot has been received.
2.3.2 2.3.3 Each and every morning, the person on call will contact the Austin Area Office message center by calling 1‐
512‐394‐4099, enter mail box number of 4044, and the password of 404400 and verify the pilots ability to
patrol there segment. If a no fly is reported an alert will be issued to personnel to be prepared for ground
patrol procedures. First Level Each area COM will maintain a list of personnel designated to patrol a
section of the Tier 2 and 3 segments in their area and provide that person with the required maps and
other information that will describe in detail the patrol section
On the morning of the second day of notification of “No‐Fly” from the patrol pilot, personnel will be
instructed to proceed with Second Level Procedures. Second Level Procedure – Tier 2 and 3 segments shall
be initiated. The required notification will be made to the ground patrol personnel and unless notified
other wise will begin patrol of the assigned area the next morning. All sightings that can not be dealt with
at the time will be called to One Call. Second Level segments need to be completed within one and one‐
half (1.5) days of the second day notification and sightings will be recorded on Right‐of‐Way Patrol Report
By Aerial/Ground form.
2.3.4 On the morning of the fifth consecutive day of notification from the Patrol Pilot of “No‐Fly”, Third Level
Procedures will be initiated. Third Level Procedures – Tier 1 areas shall be initiated. Each area COM will
maintain a list of personnel designated to patrol a section of the Tier 1 segments in there area and provide
that person with the required maps and other information that will describe in detail the patrol section.
The required notification will be made to the ground patrol personnel and unless notified other wise will
begin patrol of the assigned area the next morning. All sightings that can not be dealt with at that time will
be called to One Call. Second Level segments need to be completed within one and one‐half (1.5) days of
the second day notification and sightings will be recorded on Right‐of‐Way Patrol Report By Aerial/Ground
form.
2.4 Ground Patrol Observation
2.4.1 Ground Patrol personnel patrolling the right of way need to observe Conditions that may adversely affect
the safe operating condition of the pipeline system. Observations need to be documented for continued
inspection, maintenance or repair activities. Observations shall be documented on the following forms.
2.4.1.1 Right‐of‐Way (ROW) Inspection Report: Marking repairs, erosion, cathodic
2.4.1.2 2.4.1.3 2.4.1.4 2.4.2 Inspection observations that should be included in the patrol are listed below:
protection issues and span conditions
Right‐of‐Way Patrol Report By Aerial/Ground Form: Document the section inspected
for Department of Transportation (DOT) compliance
Pipeline Maintenance Report: Leak, corrosion, pipe and erosion repairs
Encroachment Agreement (Short Form): Third party crossings on the ROW

<<<PAGE 870>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 3 of 5
2.4.2.1 2.4.2.2 2.4.2.3 2.4.2.4 2.4.2.5 2.4.2.6 Erosion: Creek, ravines, sink holes, exposed pipe/spans and agricultural land
Right‐of‐Way: Clearing/mowing, marking condition and spacing, over‐hanging trees
and gate needs
Third Party Activity: Dozer, trenching, boring, building construction or fencing
activities on or near the ROW
Leak Indications: Vapors, odor, dead vegetation, rainbow on water or stains on
piping or valves. Vent pipes at road crossings should be inspected for the presents of
vapors.
Pipe Damage: Indication of coating damage (paint or other protective coating) or
pipe damage at exposures or spans. Spans need to be inspected to determine any
pipe deviation or denting from previous patrols.
Cathodic Protection: Inspect test leads (conduit and face plates) and rectifier
locations for visible damage to the rectifier or third activity in the anode field. Verify
Anode Field Schematics are available inside the rectifier.
2.4.3 Reporting
2.4.3.1 During each patrol, emergency situations identified during aerial or ground
surveillance will be immediately reported to the designated Pipeline Control Center.
Aerial Patrol personnel shall remain at report location until otherwise instructed by
Operation. All surveillance personnel and line spotters will be trained and certified in
Occupational Safety and Health Administration (OSHA) Hazardous Waste Operations
and Emergency Response Standard (HAZWOPER) to the first responder level.
2.5 Ground Patrols (Special Conditions)
2.5.1 Several areas have been identified as requiring ground based patrols. These areas will be patrolled at the
intervals specified until circumstances warrant a change in the need for ground‐based patrol or the patrol
frequency.
2.5.2 Patrol Method
2.5.2.1 not be dealt with at that time will be called to One Call.
2.5.2.2 Silver Mountain Road – Special Containment Inspection:
 An area from milepost 174.09 to 174.94, FM 1826 through Silver Mountain Road
has been cased with High Density Polyethylene (HDPE) pipe. This casing requires
 Various methods may be used to conduct a ground‐based patrol. The method used
will be driven by surface conditions, equipment availability and the extensive
nature of the patrol. All terrain vehicles, pickup trucks or walking may be used as
each situation warrants.
Edwards Aquifer Recharge Zone – Austin
 Daily patrols of the Edwards Aquifer Recharge Zone, from Brodie Lane to Slaughter
Lane, milepost 169.79 to 173.64, are required with one (1) ground based patrol
each week. Geology in this area is known to be highly porous and provides ready
access to the aquifer from surface runoff or a hydrocarbon spill. Patroller will
complete Right‐of‐Way Patrol Report by Aerial/Ground form. All sightings that can

<<<PAGE 871>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 4 of 5
weekly inspection for water infiltration and the presence of hydrocarbon vapors.
Refer to HDPE Inspection and Dewatering procedure.
Document the inspection and file the documentation in accordance with Section 3.0 of this procedure.
2.5.3 3.0 RECORDS
3.1 Written Pilot Reports
3.2 3.1.1 Pilots shall make a written report using the Right‐of‐Way Patrol Report By Aerial/Ground form of all
specified and other material observations as soon as practical following each flight, but in no case more
than 12 hours of flight completion with all required information:
3.1.1.1 Date of inspection
3.1.1.2 Name of person conducting the inspection
3.1.1.3 Identification of the pipeline(s), line section or right‐of‐way segment
3.1.1.4 Location of the observations by mile post number
3.1.1.5 Description of observation
3.1.1.6 Identity of Company staff, date and time (If observation was verbally reported to
Operations Control)
Company Action Taken and Recordkeeping
3.2.1 Employees shall take appropriate action, respond to pilot observations within 3 business days of pilot
report and maintain a record of such response. Such disposition records shall reference or be linked to the
report of the pilot and indicate as is applicable:
3.2.1.1 Date initially investigated by company personnel
3.2.1.2 What action was taken or will be taken
3.2.1.3 The status or disposition of the item observed or if the observation is or is not a
relevant action item
3.2.1.4 All “Non‐Emergency” observations will be responded to in One Call Ticket View
within 3 working days of aerial patrol.
3.2.1.5 Date each reported observation is resolved
3.2.1.5.1 Non‐Emergency sightings and comments will be evaluated by aerial patrol for
removal.
3.2.1.5.2 With respect to observations that were previously reported, it is not necessary
to reinspect and generate a new report, provided there is not a material change
in the status or risk of the reported observation.
3.2.1.5.3 Records of the pilot observation and Company action taken shall be maintained
for a period of two (2) years or until the next regulatory agency inspection,
whichever is longer.

<<<PAGE 872>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 5 of 5
Date Change
Location 12/15/2005 1.0, 3.0 and 6.0 01/01/2006 01/01/2007 01/01/2008 06/03/2008 2.3.1.7 & 2.3.1.8 01/01/2009 03/31/2009 2.2.1.3 03/31/2009 2.3.1.1 03/31/2009 2.3.1.7 03/31/2009 3.2.1 03/31/2009 3.2.1.3.1 4/29/09 2.5.2.3 4/29/09 2.5.2.4 9/03/09 header 9/03/09 2.4.3.1 9/03/09 3/4/10 2.4.3.1 01/01/11 12/31/11 All System Integrity Plan Change Log
Brief Description of Change
Included link to “Inspection of Right of Way procedure”
Deleted references section
Reviewed, no changes
Reviewed, no changes
Added “emergency”.
Annual Review with no changes.
Changed to 2.2.1.4 and added new 2.2.1.3
Changed flight segment - extended to Pecos River
Added “within 3 working days” and added requirement to put one-call ticket
number on aerial patrol form
Added “within 3 business days of pilot report”
Added section
Boggy Creek ROW Cleared. Visible to aerial patrol. Daily foot patrol
discontinued. Removed this section.
Re-numbered due to removal of Boggy Creek
Changed Longhorn Specific to Assets covered per Mitigation Plan, date and
revision number
Changed Longhorn to Assets covered per Mitigation Plan
Annual Review with changes listed above
Changed “assets covered by mitigation plan” to designated pipeline center – not
a version change
Reviewed, no changes
2012 Annual Review complete

<<<PAGE 873>>>

Magellan Midstream Partners, L.P.
HOUSTON‐EL PASO SPECIFIC HDPE INSPECTION AND DEWATERING
PROCEDURE
7.05‐ADM‐037
Asset Integrity 01/01/10 Revision: 1 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to outline the steps required to ensure the double cased section
of the Houston–El Paso Pipeline remains free of water.
2.0 DESCRIPTION
2.1 Compliance with this procedure is the responsibility of the Area Supervisor who is accountable
for the geographic area of pipelines unless such responsibilities are otherwise delegated in
writing.
2.2 Once per calendar year, not to exceed 15 months between events, the Environmental Specialist
shall collect a sample of any water collected in the HDPE sections and have them analyzed for
any constituents of concern.
3.0 PROCEDURE
3.1 3.1.1 Frequency of High Density Polyethylene (HDPE) Pipe Inspections:
Inspect both sections of the HDPE pipe at weekly intervals not to exceed 10 days and
following any rainfall event in excess of 0.1 inches, for the presence of water and
hydrocarbon vapors.
3.2 Description of HDPE Areas:
NOTE: The ball valves on top of the drain pipes are to be locked in the closed position at all
times when not in use.
3.2.1 Two sections of HDPE encased pipe are present on the Houston–El Paso Pipeline in
Travis County, Texas. The “East Section” runs from ESN 9192+16 to 9198+90. The “West
Section” runs from ESN 9214+95 to 9236+95. Both HDPE sections have two‐inch drain
pipes located at the topographically lowest points of the HDPE encased section. These
drain pipes serve as the point to inspect for water accumulation in the HDPE casing and
also for dewatering.
3.2.2 The total depth of each drain pipe is embossed on a stainless steel tag affixed to the
two‐inch ball valve.
3.3 Special Considerations:
3.3.1 No avoidance periods or timing restrictions are applicable for any endangered species in
the HDPE areas.
3.3.2 Limit travel to and from the HDPE areas to the right‐of‐way (ROW) unless permission for
alternative means of ingress or egress has been granted by the landowner.
3.3.3 Conduct all work during normal business hours and avoid excessive noise and travel
when possible because the HDPE areas of the Houston‐El Paso Pipeline are in close
proximity to residences.
3.4 HDPE Inspection for the presence of hydrocarbon:
3.4.1 Tools/Equipment needed:
3.4.1.1 Houston–El Paso Master Key.
3.4.1.2 HDPE Inspection Form.
3.4.1.3 LEL Meter.

<<<PAGE 874>>>

Magellan Midstream Partners, L.P.
HOUSTON‐EL PASO SPECIFIC HDPE INSPECTION AND DEWATERING
PROCEDURE
7.05‐ADM‐037
Asset Integrity 01/01/10 Revision: 1 Page 2 of 5
3.4.2 3.4.3 3.4.4 Remove the lids on pull boxes 35A, 36A, 39 and 42C.
In each pull box on top of the 8” flange, unlock and open the 1” ball valve.
Using an LEL Meter, sample the air inside the HDPE section for the presence of
hydrocarbon vapor.
NOTE: If a hydrocarbon odor is detected, immediately contact Operations Control at
(888) 465‐9512 and your immediate supervisor. Do not proceed with the remainder of
the procedure.
3.5 3.4.5 Record the results of the LEL Meter on the HDPE Inspection Form
HDPE Inspection for the presence of water:
3.5.1 Tools/Equipment needed:
3.5.2 3.5.3 3.5.1.1 Houston–El Paso Master Key.
3.5.1.2 Solinst Model “Mini 101” water level meter.
3.5.1.3 HDPE Inspection Form.
3.5.1.4 Dewatering Pump.
Turn the water level meter on and perform a battery test to ensure the meter is
operable.
Fully open the two ball valves and determine if a hydrocarbon odor is present.
NOTE: If a hydrocarbon odor is detected, immediately contact Operations Control at
(888) 465‐9512 and your immediate supervisor. Do not proceed with the remainder of
the procedure.
3.5.4 Lower the water level meter tape down the drain pipe until the probe touches the
bottom of the drain pipe or the audible alarm on the water level meter sounds.
3.5.5 If the audible alarm on the water level meter sounds, take the measurement of the
depth to water and compare it to the total depth of the stand pipe embossed on the
stainless steel tag. If the difference between the total depth of the stand pipe and the
depth to water exceeds 4‐inches, proceed to the dewatering procedure outlined below.
3.5.6 Record the findings of the HDPE Inspection on the HDPE Inspection Form.
3.6 Dewatering:
3.6.1 Tools/Equipment needed:
3.6.1.1 Dewatering Pump.
3.6.1.2 Solinst Model “Mini 101” water level meter.
3.6.1.3 HDPE Inspection Form.
3.6.1.4 LEL Meter.
3.6.1.5 Supply of sorbent pads.
3.6.2 Dewatering Guidelines:

<<<PAGE 875>>>

Magellan Midstream Partners, L.P.
HOUSTON‐EL PASO SPECIFIC HDPE INSPECTION AND DEWATERING
PROCEDURE
7.05‐ADM‐037
Asset Integrity 01/01/10 Page 3 of 5
3.6.2.1 3.6.2.2 Revision: 1 Secure a water filter sock to the end of the pump discharge line when
dewatering each HDPE section.
Route the discharge line should to a vegetated area on the ROW such that
discharged water does not enter any surface water.
CAUTION: Always use caution when operating any electrical source near
water. Inspect the power cable on the pump for nicks or abrasions
before every use. Take care to direct the discharge water away from the
generator and prevent the water from pooling in the immediate work
area.
3.6.3 Dewatering the east HDPE section:
NOTE: It is critical that all vent valves be fully open prior to initiating the dewatering
procedure. Failure to do so will result in damage to the HDPE end seals.
3.6.3.1 3.6.3.2 3.6.3.3 3.6.3.4 3.6.3.5 3.6.3.6 3.6.3.7 3.6.3.8 Open the ½‐inch ball valve at HDPE risers 35A and 36A.
Open drain line “East 1” (ESN 9196+22).
Connect the pump to the two‐inch drain line and place sorbent pads at the
discharge end of pump for visual verification of product.
Start pump and monitor the discharge to ensure continuous flow.
When the pump no longer has a steady discharge, turn the pump “OFF”
and wait approximately three minutes for additional water to collect in the
drain pipe.
Restart the pump and continue to dewater until a steady stream is no
longer present.
Remove the pump from the two‐inch drain pipe and use the water level
meter to verify that less than four inches of water remain in the drain pipe.
If greater than four inches of water remain, repeat the dewatering
procedure until less than four inches of water remains.
Record the pump run time and the estimated volume of water removed on
the HDPE Inspection Form.
3.6.4 3.6.3.9 Close the two‐inch drain valve and ½‐inch ball valves at risers 35A and 36A
and secure with a Houston–El Paso padlock.
Dewatering the west HDPE section:
NOTE: It is critical that all vent valves be fully open prior to initiating the dewatering
procedure. Failure to do so will result in damage to the HDPE end seals.
3.6.4.1 3.6.4.2 Open the two‐inch valve on drain pipes “West 1” (ESN 9221+22) and “West
2” (ESN 9227+37).
Open the ½‐inch ball valves at HDPE risers 39 and 42 and 42C.

<<<PAGE 876>>>

Magellan Midstream Partners, L.P.
HOUSTON‐EL PASO SPECIFIC HDPE INSPECTION AND DEWATERING
PROCEDURE
7.05‐ADM‐037
Asset Integrity 01/01/10 Page 4 of 5
3.6.4.3 3.6.4.4 3.6.4.5 3.6.4.6 3.6.4.7 Revision: 1 Turn the pump to the “ON” position and monitor the pump discharge to
ensure continuous flow.
When the pump no longer has a steady discharge, turn the pump “OFF”
and wait approximately three minutes for additional water to collect in the
drain pipe.
Restart the pump and continue to dewater until a steady stream is no
longer present.
Remove the pump from the drain pipe and use the water level meter to
verify that less than four inches of water remain in the drain pipe. If
greater than four inches of water remain, repeat the dewatering
procedure until less than four inches of water remains.
Record the pump run time and the estimated volume of water removed on
the HDPE Inspection Form.
3.6.4.8 3.6.4.9 Repeat 3.6.4.3 – 3.6.4.7 of this procedure on the “West 2” drain pipe.
Close the two‐inch drain valve and ½‐inch ball valves at risers 39, 42 and
42C and secure with a Houston–El Paso padlock.

<<<PAGE 877>>>

Magellan Midstream Partners, L.P.
HOUSTON‐EL PASO SPECIFIC HDPE INSPECTION AND DEWATERING
PROCEDURE
7.05‐ADM‐037
Asset Integrity 01/01/10 Revision: 1 Page 5 of 5
System Integrity Plan Change Log
Date Change
Location
Brief Description of Change
4/1/08 All new
1/1/09 2008 annual review complete – no changes
01/01/10 Reviewed, no changes
2/1/10 4.0 Updated and corrected – not a version change
01/01/11 Reviewed, no changes

<<<PAGE 878>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 1 of 4
3.13.14 PURPOSE
The purpose of this procedure is to provide a standardized method for continued surveillance due to severe flooding
conditions on mainline piping at water crossings.
3.13.15 SCOPE
The severe flooding conditions will trigger Field Personnel to direct their resources in a manner that will
enable them to determine the potential effects of flooding on the pipeline system.
3.13.16 Procedure
The Asset Locator shall:
 Watch for the potential for damage to the pipeline caused by flooding and report it to the Pipeline Integrity
Coordinator.
 Report evaluations of the pipeline to the Pipeline Integrity Coordinator.
 Coordinate their responses to flood conditions with Pipeline Integrity Coordinator.
The Pipeline Integrity Coordinator shall:
 Distribute the attached form to the affected stakeholders and obtain the data for updates to management.
 Evaluate the accessibility of pipeline facilities that may be in jeopardy, such as valve settings, which are
needed to isolate water crossings or other sections of a pipeline.
 Extend regulator vents and relief stacks above the level of anticipated flooding, as appropriate for Natural
Gas lines.
 Coordinate with emergency and spill responders on pipeline locations and condition. Provide maps and
other relevant information to such responders.
 Consider deploying personnel so that they will be in position to take emergency actions, such as shut
down, isolation, or containment. List appropriate personnel or contractors that may respond, identify the
point of contact or the QI.
 Determine if facilities that are normally above ground (e.g., valves, regulators, relief sets, etc) have
become submerged and are in danger of being struck by vessels or debris; if possible, such facilities
should be marked with an appropriate buoy with Coast Guard approval.
 Perform frequent patrols, including appropriate over flights, to evaluate right-of way conditions at water
crossings during flooding and after waters subside. Determine if flooding has exposed or undermined
pipelines as a result of new river channels cut by the flooding or by erosion or scouring.
 Perform surveys to determine the depth of cover over pipelines and the condition of any exposed
pipelines, such as those crossing scour holes. Information gathered by these surveys should be shared
with affected landowners. Agricultural agencies may help to inform farmers of the potential hazard from
reduced cover over pipelines. Where appropriate, surveys of underwater pipe should include the use of
visual inspection by divers or instrumented detection.
 Ensure that line markers are still in place or replaced in a timely manner. Notify contractors, highway
departments, and other involved in post-flood restoration activities of the presence of pipelines and the
risks posed by reduced cover.
The Compliance Coordinator shall:
Advise the appropriate PHMSA Regional Office or State Pipeline safety authority if a pipeline has suffered
damage, is shut-in, or is being operated at a reduced pressure as a precautionary measure as a result of
flooding, before returning the line to service, increasing its operating pressure, or otherwise changing its
operating status. PHMSA or the state will review all available information and advise the operator, on a
case by case basis, whether and to what extent a line can safely be returned to full service.

<<<PAGE 879>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 2 of 4
MAINLINE FLOODING COMPLIANCE FORM
COMPLETED BY: DATE COMPLETED:
LINE SECTION NAME: FLOOD AREA:
SECTION 1: TASKS
1. FLOOD TYPE
(COMPLETE QUESTIONS 1‐10)
1. ARE THE PIPELINE FACILITIES ACCESSIBLE? YES NO 2. ARE VALVE SETTINGS ACCESSIBLE? YES NO 3. HAS PERSONNEL BEEN DEPLOYED TO BE IN POSITION TO TAKE EMERGENCY ACTIONS, SUCH AS SHUT DOWN,
ISOLATION, OR CONTAINMENT?
YES NO 4. HAVE FACILITIES THAT ARE NORMALLY ABOVE GROUND BECOME SUBMERGED AND IN DANGER OF BEING
STRUCK BY A VESSEL OR DEBRIS?
YES NO 5. HAS A MORE FREQUENT PATROL PROGRAM BEEN INITIATED? YES NO 6. HAS COMMUNICATION TO THE EMERGENCY AND SPILL RESPONDERS OF PIPELINE LOCATIONS AND
CONDITIONS TAKEN PLACE? (NOTE BELOW IF MAPS AND PIPELINE INFORMATION WERE GIVEN)
YES NO 7. CAN IT BE DETERMINED IF THE PIPELINE IS EXPOSED OR UNDERMINED AS A RESULT OF FLOODING, EROSION
OR SCOURING?
YES NO 8. ARE UNDERWATER SURVEYS BEING PERFORMED TO DETERMINE DEPTH OF COVER OVER PIPELINES DURING
FLOODING CONDITIONS OF EXPOSED PIPELINES, SUCH AS THOSE CROSSING SCOUR HOLES?
YES NO 9. ARE THE PIPELINE MARKERS STILL IN PLACE? YES NO 10. HAS INFORMATION OBTAINED DURING SURVEY BEEN SHARED WITH AFFECTED LANDOWNERS IN AREAS
WHERE COVER MAY HAVE BEEN REMOVED OVER THE PIPELINE? POST FLOOD ?
YES NO 2. ARE ADDITIONAL PREVENTATIVE OR MITIGATIVE MEASURES RECOMMENDED TO PREVENT A RELEASE OR DRAINAGE FROM A
FLOODED AREA?
(COMPLETE THE DISCUSSION SECTION WITH COMMENTARY AND CONSIDERATION FOR THE BELOW RISK FACTORS)
 GENERAL PROFILE/TERRAIN OF THE AREA SURROUNDING THE PIPELINE
 SURVEYS OF UNDERWATER PIPE / VISUAL INSPECTION BY DIVERS OR INSTRUMENTED DETECTION
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A

<<<PAGE 880>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 3 of 4
SECTION 1: TASKS
 CHARACTERISTICS OF THE PRODUCT TRANSPORTED
 AMOUNT OF PRODUCT THAT COULD BE RELEASED
 THE SWIFTNESS OF LEAK DETECTION AND SHUTDOWN CAPABILITIES INCLUDING THE LOCATION OF RESPONSE PERSONNEL
 THE POTENTIAL RATE AND VOLUME OF LEAKAGE
 THE POTENTIAL FOR PRODUCT TO REACH AN IGNITION SOURCE
 DAMAGED LINE, SHUT IN OR OPERATIONS AT A REDUCED PRESSURE AS A PRECAUTIONARY MEASURE AS A RESULT OF FLOODING,
REQUIRE ADVISING THE PHMSA REGIONAL OFFICE OR STATE PIPELINE SAFETY AUTHORITY BEFORE RETURNING THE LINE TO
SERVICE, INCREASING THE OPERATING PRESSURE OR CHANGING ITS OPERATING STATUS.
DISCUSSION OR COMMENTS:

<<<PAGE 881>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 4 of 4
SIP CHANGE LOG
Date Change Location Brief Description of Change
1/1/12 new

<<<PAGE 882>>>

Magellan Midstream Partners, L.P.
EVAULATING OPERATING PRESSURES 7.07.002
Asset Integrity Page 1 of 3

<<<PAGE 883>>>

Magellan Midstream Partners, L.P.
EVAULATING OPERATING PRESSURES 7.07.002
Asset Integrity Page 2 of 3

<<<PAGE 884>>>

Magellan Midstream Partners, L.P.
EVAULATING OPERATING PRESSURES Asset Integrity 7.07.002
Page 3 of 3

<<<PAGE 885>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 1 of 8
1.0 OBJECTIVE
1.1 2.0 DESCRIPTION
2.1 3.0 STANDARDS
The objective of this initiative is to provide a framework that complies with the security regulations governing the
Company and that protects the assets, employees, the environment, stakeholders and the community from security
threats.
This initiative incorporates the security requirements required by regulations applicable to Company assets and
operations. The Company will follow the landlord’s policies for security in the Bank of Oklahoma (BOK) Tower
located in Tulsa, Oklahoma. At any other leased and/or rented office space(s) the landlord’s policies will provide the
minimum security requirements for that office space.
Without Exception, Personnel Safety Is the First Priority.
3.1 The Director of Environmental, Health, Safety & Security (EHS&S) shall:
3.1.1 3.1.2 Serve as the Company Corporate Security Officer.
Establish a Security Management Team (SMT) responsible for ensuring Company security awareness to
employees and implementing security measures at the workplace, as needed. Convene as needed to
address security‐related topics/incidents.
Notify the SMT within 24 hours of any security incident at a Company asset, to include a summary of
notifications made and actions taken.
Maintain Minimum Physical Security Standards for Company assets.
3.1.3 3.1.4 3.1.5 Annually review the notification information in the Security Events Procedure.
3.1.6 Annually review the Company asset list with the SMT to validate the Company DOT Critical List.
3.1.7 Annually update Company contact information to the Transportation Security Administration (TSA) and the
Office of Pipeline Safety (OPS) for execution of notification protocols by each agency, as required.
3.2 The Operations Supervisor shall:
3.2.1 Develop, maintain and comply with the Facility Security Plan (FSP) using the Facility Security Plan
(Nonmarine) Template for facilities that have a loading rack and/or other loading area(s) (i.e.,
butane/ethanol/biodiesel), and facilities that ship loads of more than 792 gallons of hazardous liquids.
Complete a Facility Vulnerability Assessment (FVA) template prior to the development of the FSP. Address
any vulnerability identified by the FVA in the FSP.
3.2.1.1 Develop a FVA/FSP for any newly purchased loading rack/loading area facilities within 60 days
of purchase.
NOTE: The FSP for each marine facility will be developed on a site specific basis and
should comply with all United States Coast Guard (USCG) requirements.
NOTE: The Corporate Security Officer may determine (based on site specific factors)
that additional facilities (i.e., tank farm, pump station, etc.) require a FSP. If an
additional facility is determined to need a FVA and FSP, the Corporate Security Officer
will advise the Supervisor to ensure completion of these documents.
3.2.2 Conduct an annual (once per calendar year) review of the FSP and the FVA with all employees to ensure
familiarity with the plan and to identify inaccuracies or improvement opportunities. If there are any

<<<PAGE 886>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 2 of 8
Revision: 9 improvements, update the FSP and submit to the EHS&S Compliance Specialist for uploading into the
Livelink Security Folder.
3.2.3 3.2.4 3.2.5 3.2.2.1 Note any changes in owner, operator or Corporate Security Officer in the annual review.
3.2.2.2 Complete the In‐Depth Security Training Form.
Revise and update the FSP when major changes involving the facility status or security organizations occur,
or as necessary to reflect other changing circumstances. Communicate these changes to affected
personnel via a SIP meeting, or via email if unable to attend an SIP meeting. Send the revised FSP to the
Safety Compliance Specialist for uploading into the Livelink Security Folder.
3.2.3.1 The following conditions at a minimum require a change to the FSP within 30 days:
3.2.3.1.1 Local Facility Security Officer change.
3.2.3.1.2 Modification of physical security.
3.2.3.1.3 Security procedure change.
3.2.3.1.4 Change in the facility’s configuration that materially alters the information
included in the FSP.
3.2.3.1.5 Change in the type of products handled, stored, or transferred that materially
alters the required response resources.
3.2.3.1.6 Any other changes that materially affect the implementation of the FSP.
Include all other conditions in the annual review.
Annually assess the facility using the Minimum Physical Security Standards.
Assess newly acquired facilities within 60 days of purchase and annually thereafter.
Use the appropriate Visitor Log and Safety Guidelines (Inland or Marine) for visitor identification,
3.2.3.2 3.2.4.1 verification and monitoring at each manned facility. Maintain completed logs locally as required. Conduct a
Visitor Safety Orientation for all visitors prior to their leaving the main office area.
NOTE: “Visitor” is defined as anyone, Company employee, contractor, or other, who
is not assigned to work at the facility. “Visitor” is not intended to include drivers,
cleaning crews, or delivery services (e.g., UPS, FEDEX, etc.).
3.2.6 Maintain the Key Control Log at the facility, listing by name and contact information whoever has been
provided keys and/or automatic gate openers for the facility.
NOTE: This requirement applies to employees who have keys and/or automatic gate
openers permanently assigned to them until termination or transfer, and temporary
keys and/or automatic gate openers that may be occasionally loaned to a contractor,
cleaning crew, or utility worker for occasional access to remote facilities.
3.2.7 3.2.8 3.2.9 3.2.10 Ensure all employees newly assigned to the facility receive Security Awareness Training within 90 days of
assignment to the facility.
Report any employee threat or threat to an employee to the Corporate Security Officer or Alternate
Corporate Security Officer with appropriate recommendations for ensuring workplace security.
Conduct annual drills and/or exercises as outlined in 6 CFR 27.255 and the Chemical Facility Anti‐Terrorism
Standards (CFATS) Site Security Plan if the facility is regulated by CFATS. CFATS facilities will be notified of
their status by the Alternate Corporate Security Officer.
3.2.9.1 Document security drills and exercises on the Security Drills and Exercises Form.
Comply with the Notification Procedure as outlined in Security Events.

<<<PAGE 887>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 3 of 8
3.3 The Field Supervisor shall:
3.3.1 Periodically, not to exceed three years, review the Security Events Procedure and the Guidelines for
Reporting a Suspicious Call and/or Bomb Threat to a Facility with all employees to ensure they are aware of
At USCG regulated facilities, annually update Company contact information for execution of notification
what constitutes a Security Event
3.4 The Marine Terminal Supervisor shall:
3.4.1 Register all individuals who are assigned at a USCG regulated facility more than 90 days, into the HomePort
Database (or alternative approved registration format) within 30 days of their start date. This includes
employees, temporary employees, and/or contractors. If an individual has not previously been registered,
register the individual within five days, (but no later than the 90 days), at the point it is determined that
he/she will need access beyond the 90‐day period.
3.4.2 Ensure all new hire employees obtain a Transportation Workers Identification Credential (TWIC) upon
accepting an offer of employment.
3.4.3 Escort all new hire employees until they have acquired their TWIC card to allow unescorted access to the
facility.
3.4.4 protocols.
3.4.5 At USCG regulated facilities, annually update Company contact information to the USCG for execution of
notification protocols, as required.
3.4.6 Conduct security drills/exercises in accordance with 33 CFR 105.220 at all facilities regulated by the USCG.
3.4.6.1 Conduct drills every three months.
3.4.6.2 Conduct exercises annually, not to exceed 18 months between events.
3.4.6.3 Document security drills and exercises on the Security Drills and Exercises Form.
3.4.7 Maintain security related records at all facilities regulated by the USCG (33 CFR 105) for a period of two
years.
3.4.8 Submit and maintain approved USCG Facility Security Plans as regulated by 33 CFR 105.
3.5 The Operations Manager shall:
3.5.1 If employees are officed in a leased or rented space in excess of 30 days, determine if security measures
beyond the landlord’s polices are required and implement as needed.
3.5.2 For marine facilities:
3.5.2.1 Assign, in writing, a Facility Security Officer (FSO) for all facilities regulated by the Maritime
Transportation Security Act and provide training for the FSO to serve in that capacity.
3.5.2.2 For marine terminals, review security incidents, which are considered Security Sensitive
Information, with the personnel specified in the FSP.
3.5.2.3 Submit a 33 CFR 105 compliant FSP for newly acquired facilities regulated by the USCG to the
applicable Captain of the Port 60 days prior to close, or as soon as practical based on
confirmation of closing the acquisition.
3.5.3 Complete the Facility Security Plan (Nonmarine) Template (including the FVA) for all newly acquired
nonmarine facilities within 60 days of purchase and submit to the EHS&S Compliance Specialist.
NOTE: The Corporate Security Officer may determine based on site specific factors,
that additional facilities (i.e., tank farm, pump station, etc.) require a FSP. If an
additional facility is determined to need a FVA and FSP, the Corporate Security Officer
will advise the Supervisor to ensure completion of these documents.

<<<PAGE 888>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 4 of 8
Revision: 9 3.5.4 Prepare and submit grant applications for security related costs, as applicable.
3.6 The Alternate Corporate Security Officer shall:
3.6.1 Submit “Top Screen” information to the Department of Homeland Security in compliance with CFATS:
3.6.1.1 When a facility is newly acquired.
3.6.1.2 When there are material modifications to an existing facility’s operations or site including
facility real estate or tank expansions.
3.6.1.3 On a resubmission schedule noted in CFATS regulations.
3.6.2 Coordinate the development of CFATS Security Vulnerability Analysis (SVA) and Site Security Plans (SSP) for
facilities that fall under CFATS regulations and submit when required by regulation.
3.6.3 Coordinate a drill and exercise program for CFATS facilities and facilities that are considered TSA critical.
3.6.4 Coordinate a TSA Critical Facility Workgroup to assess Company facilities against the TSA critical facility
standards.
3.6.5 Notify Operations of any facilities considered Transportation Security Administration (TSA) Critical.
3.6.6 Coordinate with Operations to develop Site Security Plans to comply with TSA guidelines.
3.6.7 Develop a Chemical Terrorism Vulnerability Information (CVI) based records retention program for CFATS
facilities.
3.6.8 Perform the duties of the Corporate Security Officer as needed.
3.7 The Project Manager shall:
3.7.1 Identify all contractors who have the potential to conduct work at a USCG regulated facility beyond a 90‐
day period on the job plan and/or project plan. Provide the Facility Supervisor the names of the contractors
listed on the job plan and/or project plan as soon as available, but no later than 30 days after the project
start date.
3.7.2 Require all contractors who conduct work at a USCG regulated facility to require their employees who will
be working in Company facility “Restricted” or “Secure” areas to obtain a TWIC card. Contractor employees
that do not have a TWIC, are required to be escorted at all times in these areas in compliance with 33 CFR
105.
3.8 The Security Management Team (SMT) shall:
3.8.1 Review security incidents and/or security breaches for nonmarine facilities to assess whether or not any
additional workplace security is warranted.
3.8.2 Review reported employee threats or threats to an employee to determine if additional security measures
and/or other actions are warranted.
3.8.3 Determine if a national, regional, or facility‐specific security threat could impact or change:
3.8.3.1 The Company’s Security Threat Level and/or
3.8.3.2 Require additional security measures at one or more of the Company’s facilities.
NOTE: The SMT is only tasked to address Company workplace security
issues/concerns. Employees visiting non‐Company facilities should comply with the
security requirements in‐place at those locations.
3.9 3.10 The EHS&S Compliance Specialist shall:
3.9.1 Upload the FSP to the Livelink Security Folder upon receipt.
The Supervisor of Pipeline Integrity Engineering shall:

<<<PAGE 889>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 5 of 8
Revision: 9 3.10.1 Conduct a security analysis using the Valve Security Process to determine the appropriate security
measures to be implemented to protect against vandalism and unauthorized entry for DOT regulated
exposed facilities located outside of a facility (e.g., terminal, pump station or tank farm).
3.10.2 Reassessments should be considered whenever circumstances arise that suggests the need for a
reassessment. Types of circumstances may include security events, encroachments, land use changes,
threats, etc.
3.11 The Vice President of Technical Services shall:
3.11.1 Implement security measures as identified.
3.12 The Employee shall:
3.12.1 Report any personal or work‐related threat (verbal, written, etc.) to you or another employee to Supervisor
immediately.
3.12.2 Make notifications as described in the Security Level Procedures.
3.12.3 Make primary and secondary notifications if the Corporate Security Officer or the Alternate Corporate
Security Officer cannot be reached, and if the situation requires immediate notification. Notify the
Corporate Security Officer via voicemail or email that such notification(s) have been made.
3.12.4 Comply with the Security Events Procedure.
3.12.5 Comply with the Security Level Procedure.
3.12.6 Complete the Security Awareness Training within 90 days of assignment to a facility (terminals and tank
farms only).
3.12.7 Complete the Key Control Log as directed by Supervisor.
3.12.8 Lock all manually operated block valves upon completion of activity and prior to leaving the area.
3.12.9 Lock all gates and key buildings (manned and unmanned) anytime the facility is not occupied.
3.12.10 Complete the Visitor Log after verifying that a visitor has left the facility for the day and has not signed out
or notified Company personnel that he/she has left the facility.
3.12.11 Successfully obtain a TWIC card when unescorted access is required to secure areas of Company marine
facilities.
3.12.12 Complete the Declaration of Security Form for every vessel that comes to the dock only if the
Marsec level is elevated to level 2 and higher.

<<<PAGE 890>>>

DATE 1/1/05 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 7/1/06 1/1/07 01/01/07 Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 6 of 8
System Integrity Plan Change Log
LOCATION BRIEF DESCRIPTION OF CHANGE
2.1 Added any other leased/rented office
3.1.1 Added
3.1.3 Added
3.1.5 Added
3.1.7 Added
3.2.3 Deleted
3.2.4 Added note box
3.2.5 Rephrased
3.2.6 Added
3.2.7 Added
3.2.8 Added
3.2.10 Added
3.3.2 Added
3.3.3 Added
3.4 Added
3.5 Added
3.1 Deleted “ Develop and maintain a Company Security Plan to comply with all regulatory security
requirements, including the Department of Homeland Security, Transportation Security Agency and the
Department of Transportation (TSA), the United States Coast Guard (USCG) and the Office of Pipeline
Safety (OPS).
NOTE: The Company Security Plan is a protected document with
limited employee access.
3.1 Deleted Annually validate and document that the Company’s facilities are in compliance with the
Company Security Plan and document.
Develop and maintain security related procedures, as required
3.19 Added for physical changes/improvements made to assets for the primary purpose of meeting the
Minimum Physical Security standards and/or security enhancements
3.2.2 Added site‐specific
3.1.8 Added
3.3.4 deleted “ records associated with training, drills and exercises and incidents/breaches of security for a
minimum”
3.2.11 added
3.2.3 added
3.2.4 Changed to 1 year from 3
2.1 Added “ At any other leased and/or rented office space(s) the landlord’s policies will provide the
minimum security requirements for that office space"
3.3.5 Deleted “Specifically, all Company marine facilities are required to conduct a security drill once every
three months.
3.5, 3.51, 3.5.2 and
3.5.3
Added
3.5.3.2 Note box added
3.6.1 Added
3.6.5 Added
4.0 Deleted link to Company Security Plan
4.0 Added “ Workplace Violence Policies and Guidance“
3.1.2 and 3.1.3 added
3.3.6 and 3.3.7 Added
3.3.7 Split “Complete a Security Vulnerability Assessment and the Facility Security Template for all newly
acquired non‐marine facilities within 60 days of purchase”. Into 2 responsibilities. Added as 3.1.9
3.3.7 Deleted “Assess the facility periodically using the Minimum Physical Security Standards.
3.2.12 and 3.6.1 Added to comply with new USCG regulations.
3.1.2 Added “convene as needed to address ….”
3.1.6 deleted

<<<PAGE 891>>>

1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 01/01/09
01/01/10 7/1/10 01/01/11 12/31/11 12/31/11 Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 7 of 8
3.2.8 Combined with 3.2.7
3.3.7 Changed timeframe to 60 days. Added reference to SVA
3.6.1 Rephrased
3.8 added
3.9 and 3.10 added
3.11.7, 3.11.8 added
3.2.13, 3.2.10 added
3.6 added
3.1.8 Added
3.1.6 Added SMT reviews DOT “Critical” list.
3.2.1 plus note Clarify when a FSP is required at Non‐marine loading facilities.
3.2.3 Added requirements including timeframe for changes to FSP.
3.2.15 Added (moved) responsibility for updating COTP with contact information from the Director of EHS to
Operations Supervisor.
3.2.16 Added (moved) responsibility for completing drills and exercises from the Operations Manager to the
Operations Supervisor.
3.3.5 Added requirement for Submittal and maintain FSP for Marine terminals as required by 33 CFR 105.
3.6.2 Added TWIC credential requirements for contractors.
3.11.9 Added requirement for all affected employees at marine facilities to obtain TWIC as needed.
3.1.10 new
3.2.16.3 new
3.11 New role/responsibilities
3.12.2.1 New
3.12.9 new
3.3 Added marine area supervisor
3.3.2 Added date
3.1.9 Renamed form Facility Vulnerability Assessment
3.2.4 Changed frequency
3.2.8 Changed supervisor role from providing training to ensuring they receive
3.2.5 Changed frequency
3.2.10 Added CFATS language
3.5 Added Alternate Security officer duties
4.2, 4.5, 4.9,
4.10,4.13
Changed name of link to
3.1.8, 3.1.9 Removed. “Maintain BU summary for assest changes/improvements” and “complete FVA for new;y
acquired marine facilities”
3.2.2.2 Removed, added annual (once per calendar year) to 3.2.2
3.2.1.1 New
3.4.3 Changed submission to EHSS Compliance Specialist (was Dir EHSS)
3.2.1 Modified per new requlatory requirement for facilities shipping > 792 gallons of hazardous liquids.
Reviewed, no changes
3.3.6.2 Removed “once per calendar year not to exceed 365 days”, replaced with
“annually, not to exceed 18 months” as per 33 CFR 105.220.
3.11.12 added
3.2.2.2 added
3.2.8 Removed “or newly hired at a facility
3.3 Added field supervisor
3.4 Revised to marine terminal supervisor
All 2012 Annual Review complete

<<<PAGE 892>>>

Magellan Midstream Partners, L.P.
TEMPORARY TRANSFER OPERATIONS USING PORTABLE
PUMPS OR NITROGEN THROUGH HOSES 9.01–ADM–185
Operations 01/01/12 Revision: 2 Page 1 of 3
Purpose:
Establish appropriate controls for transfer operations using
portable pumps, hoses, or nitrogen.
Tools:
Valve wrench
Portable pump
Hoses
Pipe wrench
Drip pans
Sight glass
Absorbent pads
Various wrenches
Safety, Health and Environmental
Considerations:
Depending upon the type of product, the employee
should use the MSDS and take appropriate safety
measures. Proper body positioning should be
used while performing tasks involving physical or
strenuous activity to minimize exposure to strain.
NOTE: nitrogen is an asphyxiation hazard and
precautions should be taken to keep the head/face
away from it.
PPE Required:
Appropriate personal protective equipment should
be used per the Workplace Hazard Assessment,
Job Plan, site specific procedure and/or the MSDS.
Step 1. Frequency
2. Identification
3. Action
Action
DETERMINE when to use portable pumps, hoses or nitrogen. Examples include:
- Preparing tanks for cleaning
- Performing tank bottom water draw
- Tank to tank transfers
- Loading or Unloading bulk additive
- Loading petroleum contact water
IDENTIFY type of pump to be used or if nitrogen will be used to push the product
IDENTIFY type of hoses and connections to be used
IDENTIFY site specific transfer procedure that will be used in conjunction with this
procedure.
REMAIN (employee, contractor, or driver) in the immediate vicinity to monitor the
operation of product transfers involving the use of portable pumps, hoses, or
nitrogen.
NOTE: The transfer need not be attended if all of the following criteria are met:
 Hoses are flanged and bolted or threaded
 Hoses are properly rated for the maximum pressure or vacuum to which
they could be exposed, and
 Hoses are physically checked every 2 hours during operation.
STOP the transfer operation and secure the area (e.g., close valves, provide thermal
pressure relief) if the operation must be left unattended for any period of time.

<<<PAGE 893>>>

Magellan Midstream Partners, L.P.
TEMPORARY TRANSFER OPERATIONS USING PORTABLE
PUMPS OR NITROGEN THROUGH HOSES 9.01–ADM–185
Operations 01/01/12 Revision: 2 Page 2 of 3
INSPECT hoses and fittings (including condition and placement of gaskets)
CAUTION: Use special consideration and caution when working near nitrogen.
SET pump and hoses to reduce potential hazards:
 Inside containment if practical.
 Minimize the number of hoses and fittings by using the most direct route.
 Utilize isolation valves at each end of hoses.
 Consider using a check valve at the discharge end of hose to minimize drain-
up
BOND or ground equipment
SECURE all fittings with straps or wire-ties to prevent hoses from inadvertently
disconnecting during operation.
CONTINUE following site specific transfer procedure

<<<PAGE 894>>>

Magellan Midstream Partners, L.P.
TEMPORARY TRANSFER OPERATIONS USING PORTABLE
PUMPS OR NITROGEN THROUGH HOSES 9.01–ADM–185
Operations 01/01/12 Revision: 2 Page 3 of 3
Date Change Location 01/01/07 Global 01/01/07 PPE and SH&E 01/01/08 01/01/09 Step 3 01/01/10 01/01/11 12/31/11 Global 12/31/11 System Integrity Plan Change Log
Brief Description of Change
New procedure
Updated to reflect strain considerations
Reviewed, no changes
Deleted “quick connect lock” from SECURE action
Reviewed, no changes
Reviewed, no changes
Added nitrogen to title and procedure; inhalation warning..
2012 annual review complete

<<<PAGE 895>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Revision: 8 Page 1 of 5
1.0 OBJECTIVE
1.1 1.2 1.3 The objective of this initiative is to promote public awareness of underground utilities, damage prevention
and emergency preparedness. Collectively, this initiative will enhance public safety and minimize damage
to property, the environment and Company assets. The Company’s Public Awareness Program was
developed to comply with the standards established in American Petroleum Institute’s (API)
Recommended Practice (RP) 1162.
Company management supports Public Awareness through Company policy, management participation,
and allocation of resources and funding as described in the System Integrity Plan Magellan Management
Commitment and Support Introduction and the Management Support Cover Letter.
Public Awareness is a critical component of our overall safety program. The Public Awareness Program
includes the following lines:
Company Name Product PHMSA Operator Identification
Number
Magellan Pipeline Company, L.P. HVL 22610
Magellan Pipeline Company, L.P. Refined 22610
Magellan Pipelines Holdings, L.P. Refined 31579
Magellan Terminals Holdings, L.P. Crude 31580
Magellan Terminals Holdings, L.P. Refined 31580
Magellan Ammonia Pipeline, L.P. Ammonia 12105
Osage Pipe Line Company, LLC Crude 14391
2.0 DESCRIPTION
2.1 The Company’s Pipeline Awareness Program for DOT 195 jurisdictional lines will include information and
provide instruction to the affected public, emergency officials, local public officials and excavators on the
following:
2.1.1 Pipeline purpose and reliability.
2.1.2 Awareness of hazards or potential hazards and prevention measures.
2.1.3 Damage Prevention Awareness.
2.1.4 One Call requirements.
2.1.5 How to recognize, report and respond to leaks and/or emergencies involving Company operated
pipelines and facilities.
2.1.6 How to identify the location of Company operated pipelines, rights-of-way, facilities, and
description of the purpose of pipeline markers and the information on them.
2.1.7 Emergency Preparedness Communications.
2.1.8 The “Call Before You Dig!” Campaign and the national One Call number 811.
2.1.9 How to access a list of pipeline operators through the National Pipeline Mapping System (NPMS).
2.1.10 How to obtain additional information.

<<<PAGE 896>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 2 of 5
Revision: 8 2.2 This initiative provides guidance to Company employees on the communication of Emergency Response
Plans (ERPs) to Local Emergency Planning Committees (LEPC) and Emergency Response Agencies
(ERA).
3.0 STANDARDS
3.1 The One Call Supervisor and Public Awareness & Communications Specialist shall:
3.1.1 3.1.2 Administer the Public Awareness Program for DOT jurisdictional assets.
Determine annually, the acceptable pipeline awareness programs and annual mailings for the
upcoming year. Develop the message content of these programs as described in the Message
Content Guidelines.
3.1.3 Perform an annual audit of the Public Awareness Program to ensure the program has been
developed and implemented according to the guidelines in RP 1162. Document on the Annual Self
Assessment.
3.1.4 3.1.5 3.1.6 3.1.7 3.1.8 3.1.9 3.1.10 Perform an Effectiveness Evaluation of the Public Awareness Program before September 1st every
four years in accordance to the guidelines in RP 1162.
Maintain all program evaluations, including current results, follow-up actions, expected results and
annual assessments for five years.
Implement the Annual Mailings Procedure annually.
Conduct a pretest of public awareness materials for audience appeal, message clarity,
understandability, and retention before they are widely used. A pretest can be performed using a
small representative audience that is not involved with the development of the Public Awareness
Program.
Annually review and update the public education and damage prevention section of Magellan’s
Internet Site, if necessary.
Maintain and annually update the Public Awareness Folder in Livelink and the Emergency
Response Guide.
Coordinate with Asset Integrity and Operations personnel to ensure that the ERP Summary Folders are
prepared, maintained and distributed to the appropriate LEPC and/or specific local ERAs.
3.1.11 Approve any deviations from the print ad or radio ad standards upon request.
3.1.12 Oversee public education efforts for assets covered per the Mitigation Plan to ensure that ERAs
within each county that the pipeline passes through will be contacted annually (not to exceed 15
months) in person and provided with maps of the system.
3.2 The Operations Manager shall:
3.2.1 Communicate Emergency Response Plans to LEPC/ERAs.
3.2.2 Maintain a current address listing of LEPC/ERAs that could respond to a Company emergency.
Provide this mailing list to the Public Awareness and Communications Specialist for the annual
Mail Out Program.
3.2.3 3.2.4 Maintain an ongoing LEPC/ERAs meeting schedule.
In addition to annual mailings to LEPCS/ERAs, conduct meetings on a rotating basis, with a
minimum of 25% of the listed LEPC/ERAs once every 12 months, not to exceed 15 months.
Conduct a meeting with each listed LEPC/ERAs at least once in a four-year calendar period.
3.2.5 Conduct meetings following the LEPC/ERA Meeting Requirements. For Intrastate pipelines in
Texas, conduct face-to-face meetings with designated ERA officials annually per the LEPC/ERA
Meeting Requirements.
3.2.6 Complete the LEPC/ERA/Stakeholder Meeting Form for each meeting. Distribute the appropriate
updated response plan documentation (ERP, ERAP, etc.) during each meeting.
3.2.7 Complete, at a minimum, one supplemental outreach activity per year within each operating area.

<<<PAGE 897>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 3 of 5
Revision: 8 Consider external factors along the pipeline system and assess if some additional level of public
awareness communications is warranted of if other supplemental/enhanced outreach activities are
needed.
3.2.7.1 Use the Relevant Factors Assessment in making the evaluation and the Approved
Media and Delivery Methods Procedure to determine the appropriate activity.
NOTE: are required.
There may be circumstances where multiple outreach activities
3.2.7.2 For each Supplemental/Enhanced Outreach Activity, complete the
LEPC/ERA/Stakeholder Meeting Form, provide supporting documentation and send to
the District Office or location and the Public Awareness and Communication
Specialist.
Maintain copies of all materials provided to each stakeholder audience in the local files for five
3.2.8 years.
3.2.9 File the completed LEPC/ERA/Stakeholder Meeting Form for five years.
3.3 The Employee shall:
3.3.1 Use the LEPC/ERA/Stakeholder Meeting Form to conduct and document pipeline safety
awareness discussions with ERAs, public education and third party damage prevention
stakeholder groups. Forward completed forms to the appropriate area office.
3.4 The One Call Coordinator shall:
3.4.1 Request documentation from state One Call Centers for their community outreach or public
awareness activities. Information may be obtained by website if available or phone solicitation.
Sort the information by state and retain for five years.
NOTE: Most state One Call Centers provide public awareness activities; Magellan
can incorporate these activities into its Public Awareness Program.
3.5 3.6 3.4.2 3.4.3 3.4.4 3.4.5 Request address listings from each applicable state One Call agency and the Company internal
database of all contractors and individuals engaged in excavation activities during the previous 12
months in each state where Company assets are located. Forward the data to the vendor for
incorporation into the annual mailings.
Advise the Operations Managers, Asset Integrity Supervisors, and Operations Control Manager of
the annual mail out messages at least ten days before distributing the mail outs.
Utilize the Company Damage Prevention Newsletter to inform employees about the Public
Awareness Program objectives.
File the LEPC/ERA forms and Supplemental/Enhanced activity documentation in the appropriate
Damage Prevention folder in Livelink.
The Regulatory Compliance Coordinator shall:
3.5.1 Initiate biennial (beginning January 15, 2005 and every two years thereafter) Educational Center Surveys in
accordance with the Texas Public School Survey Procedure for Railroad Commission of Texas regulated
assets.
The Operations Supervisor in Texas shall:
1.1.1 Conduct public school surveys (psb) upon notification from the Regulatory Compliance Coordinator.
Forward the PSB Survey information to the Regulatory Compliance Coordinator within 60 days of the
request, but no later than December 15th
.

<<<PAGE 898>>>

Date 1/1/05 1/1/05 1/1/05 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/06 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 9-10-07 9/10/07 9/10/07 9/10/07 9/10/07 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 10/08/08 1/1/09 02/01/09 7/28/09 07/28/09 07/28/09 Magellan Midstream Partners, L.P.
PUBLIC AWARENESS Community Relations 01/01/12 Page 4 of 5
Change Change All
3.2.6 Greg Walker
3.2.1 All
2.1 3.0 3.0 3.2.2 3.5 3.5.2 3.5.3 Greg Walker
3.5.4 Multiple 3.1.6 3.2.4 3.4.1, 3.4.2 3.2.3 3.2.2 All
1.0 3.1.3 Greg Walker
2.1.1, 2.1.7 3.2.1.1 All
3.2.1.6 3.4.1 Greg Walker
3.2.2 3.3.1 All
3.1.8 3.1.10 3.2.2.5 3.3.1 Greg Walker
3.4.1 3.5.1 3.5.2 3.5.4 3.5.5 3.6, 3.7 3.5.2 All Greg Walker 3.1.7
Mike
3.2 SIP–ADM–10.01
Revision: 8 SYSTEM INTEGRITY PLAN CHANGE LOG
Brief Description of Change
Conducted 2004 Annual Review see change log
Moved responsibility to develop and maintain lists of Emergency responders to Operations
Supervisors as new Section 10 3 1 5
Added Public Education and Third Party Damage Prevention Program
Conducted 2005 Annual Review see change log
Deleted the objectives of a public awareness program
Deleted information about the federal stds. the procedure was developed under.
Developed Magellan’s “Commitment to the Program.”
Deleted Operator’s responsibility of overseeing and approving budgetary responsibility.
Changed OneCall Analyst to OneCall Coordinator
Deleted request for address of Contractors form OneCall and documentation of Awareness
Program distributed Also requirement to have this information forwarded to Operations Mgr
Deleted requirement to establish and maintain the Public Awareness Program and annual
review of program
Deleted references to National Alliance Programs.
Added content for API RP1162 compliance.
Added “to determine if additional outreach programs are needed.”
added
clarified
Added retention time and location
Rephrased and defined summary report
Conducted 2006 Annual Review see change log
Added Management Support Documentation: E1 Goals and Management Support Cover
Letter
Added Effectiveness Evaluation Requirements
added
added
Conducted 2007 Annual Review see change log
Moved this to new section entitled, “3.3 Longhorn Specific Requirements:”
Added One Call membership requirement in response to PHMSA Clearing House
comments
Added additional Relevant Factors and clarified direction for Supplemental Outreach
Activities in response to PHMSA Clearing House comments
Added new wording to this section
Conducted 2008 Annual Review see change log
Deleted – Monitor activities and determine if additional is needed.
Added from E12-Maintain Public Awareness folder and ER Guide. This replaces the
previous ERP distribution process
Added location for supplemental documentation
Added administrator for Longhorn. Moved previous 3.3.1 to 3.3.2
Deleted Operations Manager or Asset Integrity (AI) Supervisor and changed to appropriate
area office
Added option for website retrieval and retention time. Deleted distribution to Operations
Managers/ AI Supervisors
Added Manager of Damage Prevention for incorporation into the annual mailings. Deleted
distribution to Operations Manager/AI Supervisors
Added: Include PA objectives in One-Call newsletter
Added: File Supplemental Documents in Livelink folder
Moved from SIP 7.08
Changed Title to Mgr of Damage Prevention and Design Services
Conducted 2009 Annual Review see change log
Changed “Pipeline” to “Public”
Changed the title to, “Assets Covered Per Mitigation Plan”

<<<PAGE 899>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 5 of 5
Date Change Change 07/28/09 3.3.2.3 Hampton 07/28/09 3.3.4 07/28/09 3.3.5 07/28/09 3.4
07/28/09 3.6.2 07/28/09 3.6.4 01/01/11 2.1 3.1 3.1/3.2.2/3.2.7 8/29/11 2.1 8/29/11 3.1 3.1.4 8/29/11 3.2.2 8/29/11 3.2.7.2 12/31/11 All Revision: 8 Brief Description of Change
Added “And Design Services”
Deleted Section Maintain the information sent from the One Call Coordinator in the Local file
for five years Added “For Five Years”
This information includes documentation of the Public Awareness activities
Deleted Section
Added “ And Magellan’s Internal Database” Deleted “Sort this information by operating area
and forward to the manager of Damage Prevention and Design Services” Added “Forward
Deleted “Include Public Awareness Objectives in the One Call Newsletter.” Added “ Utilize
Removed DOT 192
Changed Mgr of Design Services and Compliance to One Call Team
Changed title to One Call Team Leader
Added list of specific pipeline assets covered by the PAP.
Changed title to One Call Supervisor Public Awareness Comm. Spec.
Added date
Changed title to Public Awareness Comm. Spec.
Changed title to Public Awareness Comm. Spec.
2012 Annual Review complete

<<<PAGE 900>>>

Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 1 of 7
1.0 OBJECTIVE
1.1 The objectives of this initiative are to investigate selected incidents for probable cause, identify corrective actions to
prevent recurrence, complete a management review, and communicate findings and lessons learned.
2.0 DESCRIPTION
2.1 This initiative is applicable to all classified incidents. For assets covered by the Mitigation Plan, those classifications
are Minor, Significant, Major, Repair, and Near Miss. For all other Company operated assets, the classifications are
Minor, Serious, Major, and Near Miss.
2.2 Incident type and classification will be used to determine responsibility for initiating investigations.
2.3 Incident investigations should identify the probable cause, the corrective actions and lessons learned. The detail
and resource commitment associated with an incident investigation and the management level involved should be
commensurate with the incident's severity and/or loss potential.
3.0 STANDARDS
3.1 The Employee shall:
3.1.1 Participate in incident investigations as requested by their Supervisor.
3.2 The Supervisor shall:
NOTE: For all incidents the management group responsible for supervising the activity that results
in an incident or that is operating the associated asset when an incident occurs is accountable for
initiating the incident reporting and incident investigation and completing the required
documentation. If the management groups involved cannot reach consensus on these responsibilities
the issue should be raised to the next level of management.
3.2.1 3.2.2 Initiate and complete a draft Incident Investigation Report for Serious, Significant or Major
incidents only upon approval from the Associate General Counsel of Operations, the Vice
President of Operations, the Vice President of Technical Services, and the Director of
Environmental, Health, Safety and Security.
Initiate and complete a draft Incident Investigation Report for the following types of Minor
incidents within five working days of the event:
3.2.2.1 OSHA Recordable Injury/Illness.
3.2.2.2 Third Party Property Damage (including motor vehicle damage)
3.2.2.3 Incorrect execution of an OQ Task.
3.2.2.4 Fire.
3.2.2.5 Explosion.
3.2.2.6 Agency Reportable Release.
3.2.2.7 One Call Violation.
3.2.2.8 Incident involving a Process Safety Management (PSM), Risk Management Program
(RMP) or Mitigation Plan asset.
NOTE: For PSM/RMP facilities, an incident investigation team shall be
established consisting of at least one person knowledgeable in the
process involved, including a contract employee if the incident

<<<PAGE 901>>>

Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 2 of 7
involved work of the contractor, and other persons with appropriate
knowledge and experience to thoroughly investigate and analyze the
incident.
NOTE: For LMP facilities, an incident investigation team shall be
established consisting of at least two persons knowledgeable in the
process involved, including a contract employee if the incident
involved work of the contractor, and other persons with appropriate
knowledge and experience to thoroughly investigate and analyze the
incident.
NOTE: All incident investigations on PSM/RMP and LMP assets must
be initiated within 48 hours of the event.
3.2.2.9 Repair Incident for LMP covered assets if required by the Repair Investigation
Decision Tree.
3.2.3 3.2.4 3.2.5 3.2.6 3.2.7 For all other Minor incidents, provide recommendation to the Manager on whether an
investigation should be conducted.
Forward the draft Incident Investigation Report to the Manager and the Safety Specialist upon
completion of the draft.
Complete revisions based on feedback from the Manager, Safety Specialist and Director within
five working days of receipt. Forward final Incident Investigation Report to the Field Office
Administrator/Compliance Coordinator‐Mitigation Plan for posting.
Investigate and document all Near Miss events that could have resulted in a release or a
catastrophic release at a designated PSM//RMP asset using the Incident Investigation Report as
promptly as possible but no later than 48 hours following the incident. Forward the Incident
Investigation Report to the Manager and Safety Specialist within two working days of completion.
Review Hazard/Near Miss Reports within 30 days of receipt, identify additional corrective actions
3.2.8 as appropriate, document on card and forward to Safety Specialist. Consult with Manager to
determine if an incident investigation is warranted.
Consult with the Manager of Compliance and share lessons learned, as appropriate, from the
Incident Investigation Reports and the Hazard/Near Miss Reports with all affected personnel
3.3 whose job tasks are relevant to the incident findings, including contract employees where
applicable.
3.2.9 Forward completed One Call Incident Investigation Reports to the One Call group for review.
3.2.10 Update the Incident Investigation Report when new information is obtained, forward for posting,
and make any new notifications if required.
The Associate General Counsel of Operations, the Vice President of Operations, the Vice President of Technical
Services, and the Director of Environmental, Health, Safety and Security shall:
3.3.1 Assemble upon notification of a Serious, Significant, or Major incident to determine whether a
management directed incident investigation should be conducted. If so:
3.3.2 Determine if the investigation will be directed by Legal.

<<<PAGE 902>>>

Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 3.3.3 3.3.2.1 3.3.2.2 3.3.2.3 Page 3 of 7
Define the scope of the investigation, identify the Lead Investigator, and determine
completion timetable for management directed incident investigations
Review management directed incident investigation results and approve resulting action
items.
At the conclusion of the investigation, assemble the Incident Investigation Group, the lead
investigator and any other identified stakeholders to review the incident and approve the
significant lessons learned that should be conveyed to affected stakeholders.
Communicate to the responsible party whether the II will be management directed or field
directed.
3.4 The Manager shall:
3.4.1 Review all (except those “management” led) draft Incident Investigation Reports and
Hazard/Near Miss Incident Investigation Reports to ensure that the reports are complete and
include all relevant information within five working days of receipt. Forward approval or
suggested revisions to the Supervisor.
3.4.2 Forward any draft Incident Investigation Report involving a MVA or with the potential for human
factors to be a contributing cause to the appropriate Director upon completion of the manager
review.
3.4.3 Obtain consensus from the Manager of Compliance if an Incident Investigation for a Minor
Incident where an investigation is not required, will not be conducted.
3.5 The Safety Specialist shall:
3.5.1 Review all (except those “management” led) draft Incident Investigation Reports and
Hazard/Near Miss Incident Investigation Reports to ensure that the reports are complete and
include all relevant information within five business days of receipt. Forward approval or
suggested revisions to the Supervisor.
3.6 The Field Office Administrator/Compliance Coordinator‐Mitigation Plan shall:
3.6.1 Post completed Incident Investigation Reports and Hazard/Near Miss Reports in Livelink.
3.6.2 Place action items resulting from Incident Investigations into CMS for tracking and
documentation of completion.
3.7 The Director shall:
3.7.1 Review draft Incident Investigation Reports for causes and contributing factors related to MVA
and human involvement incidents within five working days of receipt. Forward approval or
suggested revisions to the Manager and Supervisor.
3.8 The Manager of Asset Integrity Engineering shall:
3.8.1 Review and analyze all Incident Investigation Reports to identify trends and common issues that
should be shared within the Company.
3.8.2 Prepare and distribute a quarterly summary of Incident Investigation Report findings and
recommendations to the applicable Operations and Technical Services stakeholders as
appropriate. Coordinate quarterly meetings to discuss and review these findings.

<<<PAGE 903>>>

3.9 3.10 Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 4 of 7
The Health and Safety Specialist shall:
3.9.1 3.9.2 Review and analyze all Incident Investigation Reports to identify trends and common issues that
should be shared within the Company.
Prepare and distribute a quarterly summary of Incident Investigation Report findings and
recommendations to the Manager of Asset Integrity Engineering for distribution to appropriate
Asset Integrity Engineers.
The Asset Integrity Engineer supporting assets covered by the LMP shall:
3.10.1 Conduct an Incorrect Operations Mitigation review on a quarterly basis.

<<<PAGE 904>>>

Date 10-1-2004 10-1-2004 10‐1‐2004 10‐1‐2004 10‐1‐2004 10‐1‐2004 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 4/20/06 01/01/07
1/17/07 10/20/07 1/2009 Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 5 of 7
System Integrity Plan Change Log
Change Location Brief Description of Change
2.1 Added all OSHA recordable injuries shall be investigated and possibly investigate NOVs
3.2.1 Added all OSHA recordable injuries shall be investigated
3.2.1.2 Added investigate all incidents that require a 7000‐1 filing
3.2.1.3 Added that the management group that is responsible for the incident initiates the incident
investigation.
3.2.1.4 Added team members shall be knowledgeable of the assets involved.
4.0 Added link to Incident Investigation Form
3.2.1 Added Consult with legal on all incidents involving 3rd party to determine the level of
investigation required.
4.2 Added incident investigation guidelines.
3.2.2 Added fires/explosions
3.8.2 Added “NOTE” box “Within 24 hours or as soon as possible, gather material evidence
important to the investigation such as video, photographs, employee logs, injury reports,
etc.”
3.2.3 Changed to a note box
3.2.2, 3.2.2.2, 3.2.2.3 Deleted “Incident Investigation Guidelines”
3.2.2.3 Deleted “with a determination of whether performance of a Covered Task contributed to
the incident.”
3.2.3 Rephrased
3.6.7 Added
3.8.1 Added
3.5.1 Deleted
3.2.1 Modified to include all serious and major incidents
Purpose Lessons Learned added
Description 2.1 Reworded, Supervisor investigation deleted
2.2 Reworded – Lessons Learned added
3.2.1 2‐day reporting req added
3.2.2, 3.2.3 5‐day reporting req added, 2‐day forwarding and Incident Investigation Report link added
3.2.4 New
3.2.3 – 3.2.6 (old) Deleted
3.3.1 Reworded – CMS added and IIR link added
3.3.2 (old) Deleted – draft IIR
3.4 (old) Director resp deleted
3.4.1 IIR link added
3.5.1, 3.5.2 New
3.6.1 – 3.6.6 Safety Rep resp deleted (see 3.5 for new rsp)
3.6 Monthly req added, IIR link added
3.7, 3.8 New
3.8 (old) Lead Incident Investigator resp deleted
3.5.1 Added requirement to post incident reports.
All Annual Review
1.1 modified
2.1 modified
3.1.2 added
3.2.2 modified
3.2.2 – 2nd notebox added
3.2.3 modified
3.3 (2007) removed
3.3.1 notebox modified
3.4.1 and 3.4.2 modified
3.5 and 3.5.1 modified
3.6.2 modified
2.1 updated language

<<<PAGE 905>>>

Date 1/2009 1/2009 1/2009 1/2009
8/2009 8/2009 8/2009 8/2009 01/01/10 3/4/10 7/1/10 09/01/10 09/01/10 09/01/10 09/01/10 09/01/10 04/08/11 04/08/11 04/08/11 7/19/11 12/31/11 12/31/11 12/31/11 12/31/11 12/31/11 12/31/11 12/31/11 12/31/11 12/31/11 Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 6 of 7
Change Location Brief Description of Change
2.3 modified
3.2.2 updated language
3.2.3 updated language
3.8 added
4.3 inserted Incorrect Operations Mitigation Program document
3.2.4 Added
3.2.6 Modified name of decision tree
3.5.2 New
3.2.2 Added additional language to Note Box, NOV’s, removed some language
3.3 Changed General Counsel to Associate GC; Added AGC requirements (3.3.1 and 3.3.2);
modified 3.3.3, added other
3.5.2 Added Near Miss language
3.7 Removed Environmental Specialists requirement
Minor rewording, updated responsibility titles
3.2.1.9 noteboxes Added/clarified LMP requirements – not a version change
3.2.1 added
1.1. Added “to prevent recurrence” as result of regulatory inspector suggestion
1.1. Reworded for clarification
3.2.2. Moved Minor incident note box to end of 3.2. for clarity
3.2.2. Removed Legal Dept note box. No longer necessary due to 3.2.1.
3.2.2.3. Removed parens, 3rd party dmg is serious under SIP and contractor is not a third party
3.2.5 Removed reference to Safety Rep
3.2.7/3.2.8/3.5 Changed Safety Rep to Safety Specialist
3.2.6 Changed Safety Rep to Safety Specialist and added FOA
3.5.2/ 3.5.3.1 (now
3.6.1/3.6.2)
Moved to FOA
3.5.3 deleted
3.5.4 (now 3.2.9) Moved to supervisor
3.8 (now 3.9) Changed from SIP Coordinator to Health and Safety Specialist shall
3.9.2 Modified to reflect managerial decision
3.10 Removed to reflect managerial decision
3.2 note Moved from below
3.2.2 removed
3.2.3 clarified
3.2.8 removed
3.2.11 Removed redundancy with onecall
3.2.14 added
3.2.15 revised
3.3.3 Added for clarification
3.4.1, 3.5.1 Clarified

<<<PAGE 906>>>

Date 12/31/11 12/31/11 12/31/11 12/31/11 Magellan Midstream Partners, L.P.
INCIDENT INVESTIGATION SIP–ADM–13.02
Incident Management 01/01/12 Revision: 13 Page 7 of 7
Change Location Brief Description of Change
3.6.2 Removed psm/rmp
3.2.10/3.6 Added compliance coordinator
3.4.2, 3.7 Changed to all directors
All 2012 Annual Review complete

<<<PAGE 907>>>

Magellan Midstream Partners, L.P.
INTERNAL AUDITS AND INSPECTIONS SIP–ADM–14.01
Compliance Management 01/01/12 Revision: 8 Page 1 of 5
1.0 OBJECTIVE
1.1 The objective of this initiative is to describe the methods used to assess the status, effectiveness and the level of
compliance with SIP and other applicable regulations.
2.0 DESCRIPTION
2.1 This initiative applies to various means of assessing and verifying compliance to the SIP and other applicable
regulations.
2.2 This initiative also applies to Facility Safety Reviews.
2.3 This initiative includes the effectiveness requirements for the assets covered by the Mitigation Plan.
3.0 STANDARDS
3.1 The General Auditor shall:
3.2 3.1.1 Establish an annual SIP audit schedule based on factors that may include but are not limited to, risk
assessment, management requests or business needs. Submit the SIP audit schedule and protocol to the
SIP Oversight Council for review and approval by February 28th and discuss with Legal to determine
applicability of federal and state self disclosure regulations and policies.
3.1.2 Complete SIP audits in accordance with the annual SIP audit schedule.
3.1.3 Report the SIP audit results to the local leadership immediately upon completion of the site visit.
3.1.4 Work with local leadership to ensure corrective action plans are developed to address deficiencies prior to
distribution of the audit report.
3.1.5 Document and distribute the results of the audits to appropriate personnel within 60 days of completion of
the fieldwork.
3.1.6 Present summary findings to the SIP Oversight Council at scheduled SIP Oversight Council meetings.
The Director of Environmental, Health, Safety and Security (EHS&S) shall:
3.2.1 Review, with assistance from the Legal Department, proposed audits to determine if it is
appropriate to conduct any of the proposed audits pursuant to a Federal or State Audit Privilege
regulation or policy. This applies to internal environmental, safety, and security related compliance
audits.
3.2.2 Coordinate, if applicable, through the Legal Department to provide written notification to the
appropriate state or federal agency 30 days prior to a scheduled audit.
3.2.3 Assess deficiencies and areas of noncompliance discovered during audits. In consultation with
Legal, determine an action plan and assign responsibilities. Comply with state or federal
requirements for disclosing, addressing and documenting closure of action items.

<<<PAGE 908>>>

Magellan Midstream Partners, L.P.
INTERNAL AUDITS AND INSPECTIONS SIP–ADM–14.01
Compliance Management 01/01/12 Revision: 8 Page 2 of 5
3.3 The Supervisor of Facility Integrity Engineering shall:
3.3.1 Conduct a Process Safety Management (PSM)/Risk Management Program (RMP) audit at the Company
PSM facilities using the PSM/RMP Audit Checklist at least every three years. The audit shall be conducted
by someone knowledgeable in the process.
Certify the audit adequately evaluated compliance with the PSM/RMP regulations through the audit sign‐
off in CMS.
Enter action items from the PSM/RMP audits into CMS within 30 days of audit completion. Initial action
item due dates should not exceed six months from completion of the audit.
Retain the completed audit form at the facility for at least two previous audits and file in Livelink here:
(Section O ‐ Compliance Audits).
3.3.2 3.3.3 3.3.4 3.4 The Marine Facility Security Officer shall:
3.4.1 Conduct a Marine Security Plan Audit annually at each marine facility utilizing the Marine Security Plan
Audit Form.
3.4.2 Maintain a copy at the field location and retain for three years.
3.5 The Supervisor shall:
3.5.1 Conduct and document a Facility Safety Review at each manned facility in their area of responsibility once
per calendar year, not to exceed 18 months, and at each unmanned facility at least once every two
calendar years using the Facility Safety Review.
3.5.2 Use the Facility Safety Review Guidance Document as a guide to complete this form.
3.5.3 Maintain a copy of the completed form in the Facility Safety Review Livelink folder. Retain the current and
previous inspection and retain.
3.5.4 Forward any corrective actions identified during the Facility Safety Review to the Field Office Administrator
for entry into CMS.
3.6 The Mitigation Plan (MP) Asset Integrity Engineer shall:
3.6.1 Coordinate a self‐audit annually for the assets covered by the Mitigation Plan and upon notification of a
throughput increase. Provide a copy of the audit report to applicable Company representatives.
3.7 The Air Specialist/Environmental Specialist shall:
3.7.1 Follow the procedures listed in Environmental Compliance Management.
3.8 The Asset Integrity Analyst shall:
3.8.1 Distribute the required performance update reports quarterly for the assets covered by the Mitigation
Plan.
3.9 The Mitigation Plan (MP) Compliance Coordinator shall:
3.9.1 Maintain and update scorecards to measure Program Effectiveness for the assets covered by the
Mitigation Plan.
3.10 The Employee shall:
3.10.1 When functioning as Lead Auditor:
3.10.1.1 Assemble the appropriate stakeholders to comprise an Audit Team, as necessary.
3.10.1.1.1 Notify the Director of EHS&S prior to conducting an audit to determine if the
Company will invoke Audit Privilege.
Communicate team responsibilities to the Audit Team prior to conducting the
audit/inspection.
3.10.1.2

<<<PAGE 909>>>

Magellan Midstream Partners, L.P.
INTERNAL AUDITS AND INSPECTIONS SIP–ADM–14.01
Compliance Management 01/01/12 Revision: 8 3.10.1.3 Page 3 of 5
Utilize the appropriate form(s) when conducting the audit/inspection. Obtain the appropriate
audit protocol and documentation requirements from the Director of EHS&S if performing an
audit in conjunction with Audit Privilege.
NOTE: Some audits/inspections may have specific protocols developed by
regulatory agencies, or others, and approved by the Audit Team for use in
lieu of, or in conjunction with, Company audit/inspection forms.
3.10.1.4 3.10.1.5 3.10.1.6 3.10.1.7 3.10.1.8 3.10.1.9 Review the audit/inspection with the Supervisor(s) and other appropriate personnel.
Communicate and review the discovery of any deficiencies or noncompliance with the
location management to determine whether the Legal Department should be immediately
consulted for validation and potential disclosure.
3.10.1.5.1 Notify the Director of EHS&S of any deficiencies or noncompliance discovered
during an audit conducted under Audit Privilege.
Conduct a post audit meeting with the area leadership team upon completion of the audit in
order to validate the findings and recommendations of the audit/inspection and to assign
responsibility for completion of action items.
Record and track the corrective action items identified during the audit utilizing CMS.
Complete and distribute the final audit report within 30 days of the completion of the
audit/inspection if not otherwise specified.
Distribute as appropriate and retain the audit work papers and final report at the field
location for three years, unless otherwise noted on the specific form.

<<<PAGE 910>>>

Magellan Midstream Partners, L.P.
INTERNAL AUDITS AND INSPECTIONS Compliance Management 01/01/12 Revision: 8 SIP–ADM–14.01
Page 4 of 5
System Integrity Plan Change Log
Date Change
Location
Brief Description of Change
9‐17‐04
Element #14
2005 Annual review and update:
Remove Safety and Training Supervisor, and Legal.
Add General Auditor, Sup of Facilities Integrity, and
Supervisor of Environmental.
Add Action Item Resolution initiative from Element #1.
Review and update forms and links.
11‐15‐04 Element #14 Add Response to Written Regulatory Inquiries from Element #7.
1/1/06
2006 review
Changed Facility Inspection timing from “not to exceed 15 months”, to “not to exceed 18 months”.
Added Audit Privilege Matrix and Voluntary Audit Process Map links.
Added Link for Marine Security Plan Audit Form.
1/1/06 3.1.5 Added
1/1/06 3.1.6 Changed to quarterly presentation from 30 days of completion of review.
1/1/06 3.2.2 Deleted documentation retention information.
1/1/06 3.5 Added Facility Security Officer duties
1/1/06 3.6
Combined Inspection Procedure document into Initiative under “All Employees Shall.”. New to
procedure
01/01/06 3.6.2 Added
01/01/07 2.2 Added
01/01/07 3.2.1 rephrased
01/01/07 3.2.3 Rephrased to reflect CMS (AI Tracking removed)
01/01/07 3.3 Changed from Sup of Facility Integrity to Supervisor of Risk Engineering
01/01/07 3.4 Added Dir of HSS&S and responsibilities and deleted Supervisor of Envir and responsibility
01/01/07 3.6.1.1.1 added
01/01/07 3.6.1.3 01/01/07 3.6.1.5.1 Added “Obtain the appropriate audit protocol and documentation requirements from the Director of
EHS&S if f i di i j i i h A di P i il ”
Added
01/01/07 3.6.1.7 added
01/01/07 3.6.2 Deleted (Notify ES of noncomp issues per Voluntary Audit Process Map)
01/01/07 3.6.1.9 Added (deleted Doc Retention Guideline)
1/1/08 3.1.6 Modified to SIP Oversight Council
1/1/08 3.3 Corrected title
1/1/08 All Clarified PSM/RMP
1/1/08 2.3 added
1/1/08 3.6, 3.7 added
1/1/09 D. Chancellor Annual Review
1/1/09 Heading Added INTERNAL to the heading
1/1/09 3.2.1 Reworded by Paul Pratt
1/1/09 3.2.2 Deleted by Paul Pratt
1/1/09 3.2.4 Reworded by Paul Pratt
1/1/09 3.4.2 Added retention location and period
1/1/09 3.6 Clarified
1/1/09 3.8.1.9 Added distribution, retention location, and wording “unless otherwise noted on the specific form”
1/1/10 Annual review for 2010
1/1/10 2.3, 3.6, 3.7 Removed Longhorn reference and reworded to just Mitigation Plan
1/1/10 3.6 Added section for the Environmental Specialist
1/1/10 3.5.2 Clarified retention per the form
9/1/10 All 2011 SIP Review done 3rd Qrt 2010
9/1/10 3.1.1 Deleted January 1st of each year added “submittal to SIP Council by 2/28 and involving legal for self
di l l i d li i R d i b l l d i l di

<<<PAGE 911>>>

Magellan Midstream Partners, L.P.
INTERNAL AUDITS AND INSPECTIONS SIP–ADM–14.01
Compliance Management 01/01/12 Revision: 8 Page 5 of 5
Date Change
Location
Brief Description of Change
9/1/10 3.2.1 9/1/10 3.2.1.1 Deleted Annual SIP audit schedule, added proposed audits Recommendation by legal and internal
di
Deleted “work with General Auditor Recommendation by legal and internal audit
9/1/10 3.3.1 – 3.3.4 Broke up paragraph into sections – Recommendation by AI Engineering
9/1/10 3.3.2 Added Certification statement ‐ Recommendation by AI Engineering regulatory requirement
9/1/10 3.3.3 Added Action item due dates should not exceed 6 months‐ Recommendation by AI Engineering
9/1/10 3.5.1 9/1/10 3.6.1 Deleted as a guideline – Recommendation; form should be completed in its entirety until specific
id li i
Deleted paragraph as this is in SIP ADM 6.05 added reference to procedure
9/1/10 4.4 Deleted Environmental review form and added E6 Environmental Compliance Management
04/08/11 3.5 Changed Safety Rep to Supervisor
04/08/11 3.5.2 Changed from maintain copy of the completed form at the location and in the in
04/08/11 3.5.3 Modified
12/1/11 Annual Review for 2012
12/1/11 2.2, 3.5.1, Changed name of form & link to Facility Safety Review
12/1/11 3.5.2 Added the Guidance Document (new document created to give more clarity to
12/1/11 3.5.3 Removed “location” for filing as Livelink is available to everyone; deleted
12/1/11 12/1/11 3.6 3.6.1/3.9.2 Added the Mitigation Plan (MP) Asset Integrity Engineer
Moved 3.9.2 from the MP Compliance Coordinator to the MP AI Engineer
12/1/11 3.3.4 Added Livelink folder location
12/31/11 All 2012 Annual Review complete

<<<PAGE 912>>>

ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 5B
VALVE SCHEMATIC

<<<PAGE 913>>>

LOCATION: 171
SATSUMA STATION
LOCATION: 711
EAST HOUSTON TERMINAL
LOCATION: 480
HOLLAND AVE. JCT. STATION
GALENA PARK STATION
LOCATION: 170
Xт-(мо)
MAGELLAN
INSAN FANA DE
LONGHORN PIPELINE
PIPELINE COMPANY, LP.
PROCESS 100 DACRAM
DRAWING NUMBER
TAFE
APPROVED
SECTON
LP-PF-1_8

<<<PAGE 914>>>

WARDA STATION (EXISTING-FUTURE)
LOCATION: 177
SA 501288 EO
MADELTAN PIECELL AN
LONGHORN PIPELINE
COMPANY, LP.
PROST 200 DIAGRAM
ORNING MUSE
NONE
SECTON
APPROVED
LP-PF-2_8

<<<PAGE 915>>>

BASTROP STATION (EXISTING)
LOCATION:
6081250015
® arens
MADELTAN PIPELINE COME
LONGHORN PIPELINE
PIPELINE COMPANY, LP.
PROCESS FLOW DIAGRAM
SHT. 3 OF 8
_ ZRI 8/11/04 SCALE
RAWING NUMBE
ONE TAFE
APPROVED
SECTION
LP-PF-3_8

<<<PAGE 916>>>

LOCATION: 172
CEDAR VALLEY STATION
_HICKORY GREEK
PEDERALES RNER
FAT CREEK
57 1813826
51 1090537
STA 10742+78
MP 203.46
STA 1059657 8
51 10 19657 -
MADELTAN PIPELINE COME
PIPELINE COMPANY, LP.
LONGHORN PIPELINE
PROCESS 40V DIAGRAN
4 OF 8
_ ZRI 8/11/04 SCALE
DRAWING NUMBER
NONE
TAFE
APPROVED
SECTION
LP-PF-4_8

<<<PAGE 917>>>

LOCATION: 178
ECKERT STATION (EXISTING-FUTURE
#7999|
55A 165076200
5TA 1202836 80
5TA 1502847A
51 1627648
MMAGELLAN
LONGHORN PIPELINE
PIPELINE COMPANY, LP.
PROCEST 5 O BAGRAM
DRAWING NUMBER
NoNE
TAFE
LP-PF-5_8

<<<PAGE 918>>>

FORT MCKAVETT STATION
LOCATION: 186
LOCATION: 173
KIMBLE COUNTY STATION
SIA 158621 23
MAGELLAN PIPELINE COMPANY, LP
PROCESS FLOW DIAGRAM
LONGHORN PIPELINE
SHT. 6 OF 8
ZRI 8/11/04 SCALE
DRAWING NUMBER
NONE ARE.
APPROVED
LP-PF-6_8

<<<PAGE 919>>>

KEMPER STATION
BIG LAKE STATION-179 (FUTURE)
MADELAN PAGELLAN
PIPELINE COMPANY, LP.
LONGHORN PIPELINE
PROST 100 DACRAM
ORNING MUS
NONE
SECTON
LP-PF-7_8

<<<PAGE 920>>>

CRANE STATION-174
50 20618
55A 278682 8 2
STA 2252582
STA 248155
TA 27828065
SIA 2781618 :
STA 2 48-58
50 20 572-
MAGELLAN PIPELINE COMPANY, LP.
MISTREAM PARTNEA LA
PROCESS FLOW DIAGRAM
LONGHORN PIPELINE
SHT. 8 OF 8
ZRI 8/11/04 SCALE
DRAWING NUMBER
NONE ARE.
APPROVED
LP-PF-8_8

<<<PAGE 921>>>

ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 5C
TRENCH INTEGRITY AND CONSTRUCTION METHODOLOGY OF THE
MAGELLAN LONGHORN PIPELINE FROM MILE POST 169.88 TO 188.8

<<<PAGE 922>>>

TRENCH INTEGRITY
AND CONSTRUCTION METHODOLOGY
OF THE MAGELLAN LONGHORN PIPELINE:
MILE POST 169.88 TO 188.8
Prepared for:
Zephyr Environmental Corporation
October 15, 2012
LBG-Guyton Associates
1101 South Capital of Texas Highway
Suite B-220
Austin, Texas 78746

<<<PAGE 923>>>

Table of Contents
BACKGROUND ..................................................................................................................................................... 1
PROOF OF CONCEPT ............................................................................................................................................ 2
Figure 1: Typical Cross Section of Trench ............................................................................................................. 3
TRENCH CONSTRUCTION ..................................................................................................................................... 4
SERVICE LIFE OF GUNITE-LINED TRENCH .............................................................................................................. 5
LEACHING ........................................................................................................................................................ 5
DELAYED ETTRINGITE FORMATION .................................................................................................................. 5
SULFATE ATTACK ............................................................................................................................................. 5
ACID AND BASE ATTACK ................................................................................................................................... 6
SALT CRYSTALLIZATION .................................................................................................................................... 6
FREEZING AND THAWING ................................................................................................................................ 6
ABRASION, EROSION AND CAVITATION ............................................................................................................ 6
THERMAL DAMAGE.......................................................................................................................................... 6
SEISMIC / STRUCTURAL LOADS ........................................................................................................................ 7
CONTAINMENT STRUCTURES ............................................................................................................................... 7
RISKS AND HAZARDS ............................................................................................................................................ 7
LONG-TERM INTEGRITY ....................................................................................................................................... 8
CONCLUSION ....................................................................................................................................................... 9
REFERENCES ...................................................................................................................................................... 10
Appendix A Trench Construction Photos
Appendix B Supporting Documents

<<<PAGE 924>>>

BACKGROUND
The ultimate goal of the Longhorn pipeline trench design and sealing protocol used within the Edwards
Aquifer Recharge Zone (EARZ) was to prevent a material volume of fluid from infiltrating into any
recharge feature exposed within the trench over a short period of time. To achieve this goal, the
trench, road bore pits, diversion berms and trench sealing materials were designed to collectively
capture and contain any potential product release. This secondary containment system was
constructed in order to prevent significant product migration to either a groundwater recharge feature
or surface water feature that might directly or indirectly recharge the Edwards aquifer (LBG-Guyton
Associates, 2001).
The focus of this report is to summarize the trench design and the materials and methodologies that
were utilized to prevent material impacts within the EARZ. However, it should be noted here that the
trench itself was only the final in a series of safeguards that were put in place to prevent product
migration from the pipeline to the aquifer.
Other design elements of the integrated safeguard system consist of:
1. 2. 3. 4. 5. 6. 7. 8. Lowering of the pipe relative to ground elevation,
Replacement of the original pipe with an improved thicker walled (0.375 in), higher grade (X65)
pipe and improved fusion bond epoxy outer coating,
Placement of a leak detection cable that will detect a 0.003 bbl/hr leak of crude oil in 100 to
200 minutes (Magellan PHMSA letter, 2012),
Backfilling with high-permeability fill materials,
As-built trench and bore pit capacity designed to contain five minutes of unchecked flow during
a 100-yr/24-hr design event (10-in rainfall),
Subsurface (bore pits) and surface diversion structures (berms) to contain product exceeding
the design capacity of the trench (Paragon, 2001a),
Bore pit sumps with standpipes for vacuum-removal of accumulated water, and
Flow restriction devices (automatic check valves, remote-controlled block valves).
In addition, maintenance elements of the integrated safeguard system include:
1. 2. ROW access restrictions to prevent heavy loads from crossing the pipeline,
Monitoring of pressure gradients in conjunction with a hydraulic leak detection system
monitored remotely at a control room manned 24/7,
3. 4. Flow gradients and potential water accumulation in the trench,
The maintenance of containment berms and the low-permeability clay ditch crown installed
over the pipeline trench, and
5. Scheduled daily aerial surveillance.
1

<<<PAGE 925>>>

PROOF OF CONCEPT
In order to verify the effectiveness and integrity of the trench sealing techniques and design features
utilized over the EARZ, Longhorn agreed to perform a Proof of Concept (POC) field test to demonstrate
that the applied materials and methodologies would prevent a material volume of fluid from
infiltrating into any recharge feature exposed in the trench cut. The criteria for success were threefold:
1) evaluation of the rate of water loss after a 24-hour period, 2) quantification of tracer dye
concentrations made during the over-excavation of the test trench and 3) analysis of potential tracer
concentrations in samples from Barton Springs and local water wells (LBG-Guyton Associates, 2001).
To test the trench sealing techniques, six trenches were excavated in series within the ROW in the
Leached/Collapsed Member of the Edwards Formation. POC tests were performed in two of the six
trenches which exhibited the largest number and variety of features thus making them the most
difficult to seal. Three different sealing approaches were utilized during the POC. The trench materials
and methodologies determined to be most effective for the POC field test were subsequently
implemented across the approximately 3-mile segment of the pipeline replacement corridor (PRC)
within the EARZ. The results of the POC indicated that the trench sealing materials successfully
prevented direct infiltration of a material volume of water over the test period.
A typical cross section of the trench is shown in Figure 1.
2

<<<PAGE 926>>>

Figure 1: Typical Cross Section of Trench
3

<<<PAGE 927>>>

TRENCH CONSTRUCTION
Potential hydrogeologic features were identified, photographed and spot cemented prior to
continuous sealing. Continuous sealing of the trench floor and walls consisted of:
1) 2) 3) 4) 5) Application (pour) of a wall-to-wall concrete and aggregate mix on the trench floor.
High velocity spray application of polypropylene ¾” fiber-reinforced gunite on trench walls
(Paragon, 2001b, see Appendix B).
Inspection of gunite thickness (nail test) integrity and consistency.
Repair of any gunite spider cracks or flaws with an overcoat of the Magnacoat epoxy-
polyurethane mix sealant (Magnacoat, 2002)
Application of an epoxy-polyurethane joint seal to the cove of the trench (Appendix B)
Materials placed in the trench (below the concrete cap) after the continuous sealing phase included:
6) 7) 8) Six-inches of pea-size gravel were placed on the trench floor as padding.
18-inch diameter product pipe placed in trench.
Hydrocarbon-sensing leak-detection cable (Tyco TraceTek TT5000), sheathed in a perforated
PVC conduit, were placed on top of pea gravel between 18-inch product pipe and trench wall.
(Magellan PHMSA letter, 2012, see Appendix B)
9) Additional pea gravel backfilled to a height of approximately 6 inches above the product pipe
10) A 3-feet thick layer of aggregate backfill (with an average lab porosity of 43%) was placed in the
trench to provide structural integrity and containment capacity (see Appendix B)
Installation of a concrete cap and ditch crown involved the following procedures:
11) To enhance the bonding between the concrete cap and the gunite walls, a bonding agent was
applied to the gunite walls at the top of the aggregate backfill prior to pouring the concrete cap.
12) A four-inch layer of fiberglass-reinforced red-dyed concrete was then poured on top of the
trench materials to complete the upper seal (to prevent any influx of precipitation into the
trench) and provide a warning indicator for any potential future excavation.
13) A low-permeability clayey soil was placed above the concrete cap to grade and the same
material was used to construct an additional six-inch crown on top of the trench in order to
shed runoff away from the trench.
Photos of the various trench components are included in Appendix A.
4

<<<PAGE 928>>>

SERVICE LIFE OF GUNITE-LINED TRENCH
There are several important factors controlling the service life of concrete or gunite. These primary risk
factors affecting service life are described below:
LEACHING
Water containing little or no calcium ions (soft water) or acidic ground water can hydrolyze or dissolve
the alkali oxides and calcium containing products resulting in increased permeability of the concrete.
The potential for this leaching action to occur is highly unlikely as the gunite is bonded to the face of
the Edwards Limestone where the expected Total Dissolved Solids (TDS) usually range from 250 to 350
mg/l. The cations for the typical Edwards water are dominated by calcium and magnesium. In addition,
the rate of leaching is a function of the permeability of the concrete and that the gunite has a low
permeability due to the application method.
DELAYED ETTRINGITE FORMATION
Generally, delayed ettringite formation (DEF) is seen as a form of internal sulfate attack. Concrete
undergoing DEF can exhibit expansion and cracking. DEF is believed to be a result of improper heat
curing of the concrete where the normal ettringite formation is suppressed. The development of DEF is
dependent on the amount of sulfate available, curing temperature and on the presence of water
during the service life. (Hine, 1996)
DEF almost certainly will not occur because the groundwater in vicinity of the trench has sulfate
concentrations that are typically less than 50 mg/L, which are considered minimal. In addition, the
gunite cure process was not accelerated and the gunite is not frequently exposed to significant
amounts of water. The trench was installed above the water table and its’ design inhibits water from
entering the trench. For these reasons, DEF is not considered a potential threat.
SULFATE ATTACK
Sulfates present in the aggregates, soils, and ground water can react with the calcium hydroxide and
the hydrated tri-calcium hydroxide to form gypsum and ettringite, respectively. These reactions can
result in deleterious expansion and produce concretes with reduced strength because of
decomposition and expansion of the hydrated calcium aluminates. In addition to the chemical attack
described above, sulfates can also attack concrete physically. As groundwater enters the concrete by
capillary action and diffusion and evaporates, the sulfate salts concentrate, sometimes generating
pressures large enough to cause cracking.
The Edwards Aquifer is composed of a freshwater zone and a sulfidic, saline water zone. The sulfidic,
saline zone is located to the east and down dip from the gunite trench which is in the freshwater zone
where the sulfate concentrations are typically less than 50 mg/L. Concentrations of sulfate (SO4) in the
5

<<<PAGE 929>>>

ground water less than 150 mg/L are considered minimal exposure conditions. In both the chemical
and physical sulfate attack, the common link is the requirement for the sulfate solution to enter the
pore spaces of the concrete. Studies have shown that it is essential to limit the ability of the sulfates
from entering the concrete; this is done by reducing the permeability of the concrete (minimizing the
water-to-cementitious materials ratio and provide good curing). In that the presence of sulfate
concentrations are considered minimal, a chemical or physical sulfate attack is not considered a
potential factor for the deterioration of the gunite trench.
ACID AND BASE ATTACK
Acids can combine with calcium compounds in the hydrated cement causing it to become soluble and
therefore leachable. This leaching will increase the concrete’s porosity and permeability. The main
factors for this type of attack are the type of acid, its’ concentration and pH. The soils of the Edwards
Aquifer recharge zone should be expected to be basic (with pH values >7.0).
Basic solutions, particularly solutions containing high concentrations of sodium and potassium
hydroxide (>20%), can cause concrete to degenerate.
It should be noted that gunite is resistant to mild acid and base chemical attacks, due to its’ low w/cm
(low permeability).
SALT CRYSTALLIZATION
Crystal growth within the concrete can result in internal pressures causing cracks in concrete. This type
of physical attack results from repeated crystallization due to the evaporation of salt laden water in the
pores of the concrete. Because of the inherit design of the trench, in that it inhibits the entry of water
into the trench and the low permeability of the gunite, salt crystallization is not a potential damage
scenario.
FREEZING AND THAWING
Concrete is susceptible to damage if saturated with water and exposed to freezing/thawing cycles.
Since the gunite trench will not experience these temperature fluctuations due to its’ burial, the
potential for damage to occur from this type of physical attack is minimal.
ABRASION, EROSION AND CAVITATION
These types of physical attack result in the loss of surface material. Because of the trench’s burial
depth, none of these physical attacks are considered a potential damage scenario.
THERMAL DAMAGE
Elevated temperatures and thermal gradients affect concrete’s strength and stiffness. Surface spalling
can occur if the rate of heating is high and the permeability is low. Typically, a design oriented
6

<<<PAGE 930>>>

approach is used when considering thermal loads on concrete structures. In the case of the gunite
trench, thermal loads and their impact on the gunite trench are considered negligible due its’ burial
depth and inherent lack of temperature cycles.
SEISMIC / STRUCTURAL LOADS
In service stresses induced by mechanical loads such as fault movement and vehicular traffic are
considered minimal as the faults identified in the recharge zone are not active, and daily inspection of
the pipeline right of way limits uncontrolled vehicular traffic.
CONTAINMENT STRUCTURES
The trench is designed to be a conduit for product to migrate under the force of gravity to either a road
bore pit or diversion berm.
Bore pits were installed on both sides of all road crossings to provide additional containment capacity.
The elevation of the bore pit floor is a minimum of 2.5 feet lower than the trench floor. The dimensions
of the berms vary, depending on the containment capacity required in each particular drain-down
section; however, the typical length of the bore pit is a minimum of 55 feet. The sealing protocol for
the bore pits is identical to the trench; however, a geotextile fabric was added between the bore pit fill
and the concrete cap for stability. A 4-inch sump with an above-grade riser in each bore pit provides
both a method of inspection as well as a means for water or product removal (Paragon, 2001a).
Diversion berms were designed to divert surface flow away from certain known karst features within
the EARZ. The floors of the berm structures contain a 6-inch thick clay material liner. There are four
berms located on the EARZ and just east of the EARZ between approximately Deer Lane (west of Brodie
Lane) and the corner of Cameron Loop Road (east of Brodie Lane). These structures protect the Goat
Cave Karst Preserve, Deer Park Cave, the Blowing Sink Tract and the Dry Branch of Williamson Creek.
RISKS AND HAZARDS
Naturally-occurring hazards that could potentially undermine the integrity of the trench include
(hydro) geologic hazards such as earthquakes, subsidence, aseismic movement along fault planes,
earth material failure or deformation, scour, erosion, and flood potential (Longhorn Pipeline Partners,
2001).
There is a 0.19% chance of a major earthquake within 50 kilometers of Austin, Texas within the next 50
years. The largest earthquake within 100 miles of Austin, Texas was a 3.9 Magnitude in 2008 (USGS
Earthquake Hazards Program). Although earthquakes do occur in south-central Texas, they are not
considered a significant risk factor to the integrity of the pipeline and associated structures.
7

<<<PAGE 931>>>

Fault locations identified in the Geologic Assessment of the 3-mile ROW within the EARZ (Horizon,
2000) were published by the USGS (Small, et. al., 1996). There are nine mapped faults within the
Balcones Fault Zone (BFZ) that transect the EARZ segment of the ROW. These faults typically are
southwest-northeast trending normal faults that are downthrown toward the east-southeast. The BFZ
was last active in the early Miocene, which was approximately 15 million years ago (Young, 1972).
There are four faults in the Houston area that are being monitored for aseismic movement, but they
are not considered as an issue in this report.
Materials failure such as structural wall collapse due to lateral pressure is inhibited by the presence of
limestone bedrock as well as the materials that fill the trench, which lend structural stability to the
entire trench system within the EARZ. Additionally no shrink-swell clays (vertisols) were encountered in
the trench in the EARZ. The Del Rio Clay (a vertisol) is located just east of the EARZ in the Edwards
Aquifer Transition Zone (EATZ). The EARZ and EATZ are separated by fault S-1 (Small, et. al., 1996).
Gunite was not applied to trench walls east of this fault.
The Del Rio Clay typically fails via bulging from increasing principal stress difference, which is alleviated
with drying. The presence of the trench and associated high-permeability fill material within the low-
permeability clay will provide a preferential flow path for water. The trench fill physically inhibits
significant expansive movement by the native materials, provides a flow conduit for water, and serves
to inhibit bulging failure within the Del Rio by reducing the water content of the clay adjacent to the
trench (Tonan, 2009).
Water forces that might affect the pipeline were the subject of numerous studies which concluded that
the most significant concerns associated with water include scour, erosion, flood potential and the
effects of floodwater movement across the ROW. Thus, the pipeline crossing at Barton Creek was
replaced (lowered) to minimize the threat of stream bed scour (Longhorn Mitigation Plan, 2000). This
stream crossing is located west of the EARZ.
LONG-TERM INTEGRITY
In the Longhorn Mitigation Plan (LMP), Longhorn has committed to 40 mitigation measures to address
the four leading causes of pipeline failures which are: 1) outside force damage, 2) corrosion, 3)
operator error and 4) material defects. Longhorn created a System Integrity Program (SIP) in order to
analyze and manage the various risks inherent to pipeline operations in order to ensure long-term
safety and minimize environmental impacts. Longhorn also committed to perform annual Operational
Reliability Assessments (ORAs). The LMP, LMP first and second supplements, annual ORA summary
reports, LPSIP self-audit reports and commitment implementation status reports are available online
for years 2008 through 2011. A few examples of the long-term maintenance commitments that have
been committed to in order to extend the service life of the trench include:
8

<<<PAGE 932>>>

1. Restricting access to the ROW in order to keep traffic and heavy loads off of the pipeline
2. 3. structures.
Monitoring and removal of water accumulated in trench bore pits via sumps with risers.
Maintenance of the low permeability soil crowns on the trench and the bore bits to keep water
off of the trench structures.
In a third-party review of the engineering design prepared for U.S. Fish & Wildlife, Dr. Konuk reviewed
the engineering design report (Paragon, 2001a) and the alignment sheets and stated the following:
“Considering the quality of the new line pipe, the conservativeness of the design, and the
prevention measures from the third-party damage, including the protective concrete slabs, and
the redundant leak detection system (cable), the author considers the risk posed by this segment
to be very low, well below the historical records collected from other pipelines.[…] The author
believes that, assuming that all the operations procedures are implemented and commitments
to improve these procedures as more experience is gained from the pipeline followed, the
probability of a significant leak, defined as a release of product more than one barrel, in this
three mile section should be much smaller than the score of 1 incident per 2000 years per mile
of pipe. Also the author cannot see any design improvements that can significantly decrease this
risk score for this three-mile segment.” (Konuk, 2001, see Appendix B).
CONCLUSION
Service life prediction for the gunite trench is not an exact science because the trench is buried;
however the engineering safeguards utilized during installation, lack of seismic/structural loads, lack of
physical and chemical deterioration factors relative to the trench components lead to a high level of
confidence that the trench integrity remains intact. With similar structures lasting 50+ years it is
reasonable to expect this trench to last at least this time period, given the lack of degradation
processes.
9

<<<PAGE 933>>>

REFERENCES
ACI Committee, 2000. Service-Life Prediction State-of-the-Art Report, by the American Concrete Institute, Committee
365.
Hime, William G., July – August, 1996. Delayed Ettringite Formation – A Concern for Precast Concrete?, PCI Journal,
Precast / Prestressed Concrete Institute
Horizon, 2000. Geologic Assessment for Longhorn Pipeline 3-mile Right-of-Way, Edwards Aquifer Recharge Zone,
Travis County, Texas, June, 2000.
LBG-Guyton Associates, 2001. Results of Proof of Concept Tests To Verify the Design and Construction Methods for
the Longhorn Partners Pipeline Trench over the Edwards Aquifer Recharge Zone in Austin, Texas, December,
2001.
Konuk, I., PhD. 2001. Review of Engineering Design Basis for Containment – Nineteen Mile Replacement Section,
Longhorn Partners Pipeline, L.P., prepared for U.S. Fish & Wildlife Service, dated November 31, 2001.
Longhorn Pipeline Partners, 2000. The Longhorn Mitigation Plan, dated September 11, 2000, at
http://www.magellanlp.com/longhorninfo.aspx
Magellan PHMSA letter, dated February 14, 2012, RE: Longhorn Pipeline Reversal – LMP changes.
Magnacoat Industrial Coatings, 2002. Information Request for News Release, Bayer/Magnacoat Spray Elastomer
Coating, Longhorn Pipeline 19-mile Pipeline Replacement Project, Travis and Hays Counties, Texas,
December-July 2002.
Paragon Engineering Services, Inc., 2001a. Engineering Design basis for Containment, Nineteen Mile Replacement
Section 18” Products Pipeline, October 2001.
Paragon Engineering Services, Inc., 2001b. Trench Gunite Sealing Specification, Specification Number: 99059-SP-001.
RCP, 2011. 2010 Annual System Integrity Plan Self-Audit Reports for Magellan Midstream Partners, L.P. Longhorn
Pipeline, dated December 16, 2011.
Small, T.A., et. al., 1996. Geologic Framework and Hydrogeologic Characteristics of the Edwards Aquifer Outcrop
(Barton Springs Segment), Northeastern Hays and Southwest Travis Counties, Texas. U.S. Geologic Survey
Water-Resources Investigations 96-4306.
Tonon, F., et. al., 2009. Effect of Verification Cores on Tip Capacity of Drilled Shafts (with emphasis on the material
properties of four clay shales (Del Rio Clay, Eagle Ford Shale, Taylor Marl, and Navarro Shale) in central Texas,
Center for Transportation Research at the University of Texas at Austin, Technical Report 0-5825-1, October
2008, revised February 2009.
USGS Earthquakes Hazards Program website http://earthquake.usgs.gov/aboutus/, a component of the multi-agency
National Earthquake Hazards Reduction Program.
Young, K., 1972. Mesozoic History, Llano Region in Geology of the Llano Region and Austin Area Field Excursion
Guidebook 13, edited by Barnes, V.E. et. al., Bureau of Economic Geology, University of Texas at Austin
10

<<<PAGE 934>>>

Appendix A
Trench Construction Photos

<<<PAGE 935>>>

Trench Cut (Flags Mark Potential Features for Inspection)
Bore Pit (Corran Ferry Road)

<<<PAGE 936>>>

Boring under Corran Ferry Road
Trench Inspection

<<<PAGE 937>>>

Trench Inspection
Feature at 9138+40

<<<PAGE 938>>>

Feature at 9296+50
Spot Cementing

<<<PAGE 939>>>

Spot Cementing
Concrete Floor

<<<PAGE 940>>>

Concrete Floor
Core l
Concrete Floor Core

<<<PAGE 941>>>

Gunite Crew
Gunite Crew (from trench inspection box)

<<<PAGE 942>>>

-2-4-02
9038-00
Gunite Wall
POC*2
CORE 2
Gunite Core

<<<PAGE 943>>>

Gunite Bore Pit Wall
Gunite Core with FIbers

<<<PAGE 944>>>

Gunite Bore Pit (Sendera Mesa)
Sealant Application

<<<PAGE 945>>>

Contact between Gunite and Sealant
Cove Seal

<<<PAGE 946>>>

Sealed Trench
05/30/2002cg
Sealed Trench

<<<PAGE 947>>>

Gunite Inspection
COK
Sealed Weld on Pipe

<<<PAGE 948>>>

Pipeline on Pad
Leak-Detection Cable PVC Conduit

<<<PAGE 949>>>

Concrete Cap and Gunite-Cap Seal
Bore Pit Geotextile Fabric and Concrete Cap

<<<PAGE 950>>>

Appendix B
Supporting Documents

<<<PAGE 951>>>

Longhorn Partners Pipeline
Nineteen Mile Pipeline
Segment Replacement
18” Products Pipeline
Project
99059-SP-001 November 2, 2001
Trench Gunite Sealing Specification
Specification Number: 99059-SP-001
REVISION A B 0 1 2
STATUS For Review For Construction
Prepared By: GAT
Checked By: JRB
Approved By:
Project Manager JRB
Date of Issue: 2-Nov-01
S:\Projects\Magellan\Magellan Longhorn\white paper\references\Gunnite Spec 99059-SP-001 2Nov01.doc

<<<PAGE 952>>>

Longhorn Partners Pipeline
Nineteen Mile Pipeline
Segment Replacement
18” Products Pipeline
Project
99059-SP-001 November 2, 2001
Dry Mix Shotcrete Application Equipment
The dry mix shotcrete equipment shall be the feed bowl type as per ACI 506R-10 3.2.2.2 such as
Ridley Rotary Gunite Machine Model C-9A and the equipment shall be operate by a qualified
applicator.
Dry mix shotcrete material performance specification.
1. Portland Cement Type I – 760 lbs / cy
2. Aggregate gradation ACI 506R-8 2.4.1 – 2878 lbs / cy
3. Water – 266 lbs / cy
4. Harbourite polypropylene ¾” fibers manufactured by Synthetic Industries, Chattanooga, TN
– 4 lbs / cy
5. Compressive Strength (7 days) – f ‘c > 4,000 PSI
S:\Projects\Magellan\Magellan Longhorn\white paper\references\Gunnite Spec 99059-SP-001 2Nov01.doc Page 2 of 2

<<<PAGE 953>>>

Information Request for News Release
Bayer / Magnacoat Spray Elastomer Coating
Longhorn Pipeline 19-Mile Pipeline Replacement Project
Travis and Hays Counties, Texas
December - July 2002
Bayer's questions presented in italics.
1. Details about the pipeline project to the extent possible without revealing
sensitive or proprietary information:
How long is the section of pipeline that was repaired or rebuilt?
What will the pipeline transport?
Who owns the pipeline?
This project consisted of the full replacement of approximately nineteen miles of
18-inch steel pipeline through the city of Austin, Texas and nearby environs in
Travis and adjoining Hays Counties, Texas.
This distance crosses the
environmentally sensitive Edwards Aquifer Recharge Zone and Contributing
Zone as will be discussed below.
The pipeline will transport refined petroleum products, namely: unleaded
gasoline, Diesel fuel, and jet fuel.
The pipeline is owned by Longhorn Pipeline Partners, LLP of Dallas, Texas.
2. Were there any sensitive environmental requirements or concerns that the
pipeline project had to address or comply with that could be discussed int eh
news release? i.e. groundwater safety?
The pipeline replacement project occurred as the result of an environmental
lawsuit and subsequent settlement negotiated with agencies of the Federal
Government. Chief among the concerns in the suit was protection of sensitive
groundwater resources of the Edwards Aquifer Recharge Zone (EARZ) from
sources of potential pollution.
3. Describe the problem posed by the Longhorn Pipeline project that caused
your engineering firm and / or the pipeline's owners to look for a solution that
would seal the concrete floor and gunnite walls.
One of the settlement stipulations of the project was that no material volume of
pipeline product would be allowed to leave the pipeline right of way in the unlikely
event of a pipeline leak. To ensure that this stipulation was met, a design had to
be implemented that would essentially capture any product released within the
Bayer Magnacoat News Release information.doc
1
6/7/2012

<<<PAGE 954>>>

confines of the pipeline trench so that it could be recovered, thus preventing it
from entering the groundwater supply. Approximately three miles of the nineteen
miles replaced crossed the EARZ. This zone is geologically characterized by
very porous rock formations often providing very direct paths for surface water to
enter the groundwater system. This three mile long section was treated with the
gunnite / concrete trench lining, further sealed at the wall and floor junctures with
the elastomeric material and a select gravel backfill material providing interstitial
storage for a fluid release.
4. What specific properties or performance were you seeking in a material?
As the trench design specified spray-applied gunnite to the trench walls and a
poured concrete floor, the leak integrity of the wall-to-floor joint had to be
ensured. This leak integrity was ensured by a combination of controlled joint
geometry, the use of a synthetic bonding agent between the gunnite wall and
concrete floor, and finally, the over-coating of the entire joint area with the
Magnacoat synthetic elastormer product to seal any remaining gaps.
The Magnacoat product was selected because it met the requirements for
longevity, flexibility, resistance to deterioration whether exposed to acidic or
alkaline
soils, and resistance to deterioration if ever exposed to refined
hydrocarbon products. As with the gunnite and concrete materials, the
Magnacoat elastomer could not electrically interfere with the pipeline cathodic
protection corrosion prevention measures.
5. Were there any local, state, or federal guidelines the material would have to
meet?
There are, at this time, neither governmental requirements nor guidelines for the
provision tor or design of lined pipeline trenches such as that implemented by
Longhorn Pipeline.
However, this design was submitted and reviewed by the
local, state, and federal agencies having oversight participation in this project.
6. What lead you to Mike Swearingen and his Magnacoat Industrial Coatings
business?
From its inception, this project was deemed newsworthy in the Austin, Texas
press. As Longhorn conducted full-scale mockup testing of the sealed trench
design, Mike Swearingen read published accounts regarding the project in the
Austin newspapers. He approached Longhorn suggesting that the Magnacoat
product might have application in meeting Longhorn's stringent design and
performance criteria for the sealed trench.
Bayer Magnacoat News Release information.doc
2
6/7/2012

<<<PAGE 955>>>

7. Why was the material solution proposed by Mike Swearingen appealing to
your firm or the pipeline owner?
The unprecedented sensitivity of this project required Longhorn Pipeline and the
engineering design team to make every reasonable effort to ensure the long-term
performance of the trench design. Because the sealed trench design is buried
below ground, inspection and routine maintenance of materials for the trench
seal would be problematic if not impossible in the future. For this reason, all
materials chosen for use in the design had to demonstrate long-term
performance in the environment in which they were installed with no subsequent
maintenance. The Magnacoat product met these performance criteria. It seems
an ideal match for the design challenge to which it is applied.
8. Was your engineering company pleased with the installation and performance
of the spray polyurethane elastomer?
As with any first-time or unique engineering solution, there are bugs to be worked
trenches with remote devices to meet excavation safety requirements,
out. For this project, there were challenges in applying the product in deep
scheduling challenges, and the cooperation of the local weather conditions to
ensure optimal application conditions. Magnacoat worked diligently to meet
these challenges and both they and their product performed as expected.
9. Would you consider using this material again for a project with similar
requirements?
Should another project with similar requirements present itself for such a
solution, this product should certainly be considered.
Bayer Magnacoat News Release information.doc
3
6/7/2012

<<<PAGE 956>>>

Pipeline Replacement Corridor (PRC)
Longhorn Pipeline Trench Fill Data
Austin, Texas
Sample
Pre-trenching sample data
ID
Sample
Porosity
Field
Porosity
Permeability
cm/sec
Absorption
Comments
TCS-066
TCS-063
44
TCS-262
8/8/2001
42
large gravel
TCS-066
8/8/2001
8/8/2001
48.7
3.3
7.9
6.1
2.2
2.8
pea gravel
medium gravel
TCS-063
48.7
51.9
2.4
medium gravel
large gravel
Vulcan - 1" dirty
Yarrington - 1-2" mixed
/ulcan - 1" clean
12/17/2001
12/17/2001
46
12/17/2001
12/17/2001
43
49.1
48.7
1.6
Yarrington - 1* mixed
48
45.8
1.4
Yarrington - 3/4" pipe bedding
Yarrington - 3/4" crushed
12/17/2001
12/17/2001
42
43
45.4
44.2
2.2
1.4
East End
PRC sample data
38
40.7
2.1
1.4
East End
East End
1/22/2002
1/21/2002
40.5
1/31/2002
40
field measurement
40
field measurement
field measurement
West End 1
East End 1
2/4/2002
2/8/2002
43.2
43.1
1.0
West End 3
West End 2
2/14/2002
2/13/2002
44.1
43.4
1.1
0.4
RR 12 stockpile
1.2
Cedar Valley station
West End 5
West End 4
2/27/2002
43.7
0.6
Cedar Valley station
West End 7
West End 6
2/22/2002
43.6
0.4
0.5
Kinser Ranch
Fitzhugh Place
3/4/2002
East End 2
3/12/2002
3/6/2002
45.9
45.6
0.8
0.4
Kinser Ranch
Fitzhugh Place
West End 8
East End 3
3/12/2002
3/12/2002
41.6
40.8
41.6
0.9
1.3
Cameron Loop
Deer Lane
West End 9
East End 4
West End 10
4/2/2002
3/27/2002
42.7
42.4
0.7
1.0
btn 290 and Derecho - from padder
Fitzhugh xing at Barton
East End 5
4/18/2002
4/17/2002
41.7
0.5
at Ramble Three - from padder
42.4
1.1
1.2
FM 1826
East End 6
East End 7
4/26/2002
43.0
47.0
west side Slaughter
Average - PRC samples
6/9/2002
0.8
0.9
Slaughter xing
43.3
Slaughter east borepit
Note: All lab results provided by Trinity Engineering/Kleinfelder, Austin, Texas.

<<<PAGE 957>>>

MAGERLAN
PO BOX 22186
One Williams Center
MIDSTREAM PARTNERS, L.P.
Tulsa, OK 74172-2186
Via Certified Mail - Hardcopy Requested
February 14, 2012
Mr. R.M. Seeley, Director
Southwest Region, Pipeline Hazardous Materials and Safety Administration
8701 South Gessner, Suite 1110
Houston, TX 77074
Re: Longhorn Pipeline Reversal - LMP Changes
Dear Mr. Seeley,
As previously communicated, Magellan Midstream Partners is developing a project,
which is currently under NEPA review, to reverse the Longhorn Pipeline from Crane
to Houston, Texas to transport crude oil. As part of this Proposed Project, Magellan
has evaluated the Longhorn Mitigation Plan (LMP) requirements and proposes the
following changes to the LMP contingent upon approval of the Proposed Project:
1. Mitigation Appendix - Item 13. This item currently outlines a leak detection
performance commitment for the hydrocarbon sensing leak detection cable
that was installed and currently functional over the Edwards Aquifer Recharge
Zone and the Slaughter Creek watershed in the Edwards Aquifer Contributing
Zone. The current commitment does not contain a performance specification
for crude oil. Magellan is proposing to add the performance commitment for
crude oil as follows (red text):

<<<PAGE 958>>>

• Page 2 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Leak Detection Performance Commitment:
Longhorn is committed to implementing the best available leak detection systems with the
following design specifications:
SYSTEM DESIGN
LOCATION
SPECIFICATIONS
Tier I
1% of flow detected within one-half hour.
Tier II
•.
.5%- 1% of flow detected within one hou
% or more of flow detected within one-half hou
Tier III
•
Same as Tier II, except Edwards Aquifer Recharge Zone.
Edwards Aquifer
Recharge Zone and
Same as Tier II, and sensor-based detection of 0.0030467
barrel/hour from contact for the following products:
(Slaughter Creek
Contributing Zone
Gasoline - 12 minutes
watershed)
:
Diesel Fuel - 60 to 120 minutes
: Crude Oil - 100 to 2000 minutes
Jet Fuel - 50 to 70 minutes
Magellan contracted with Tyco Thermal Controls to conduct tests of the
sensitivity of the existing TT-5000 leak cable on two different types of crude oil
currently anticipated to be transported on the Longhom System. See Report
# TT 1106-006 (Attachment #1). These tests confirmed the cable sensitivity
as published by TraceTek. See Attachment #2. Additionally, Magellan
contracted with Spartan Engineering Inc. to evaluate the existing systems
capabilities in crude oil compared to other direct detection methods. Spartan
determined that the existing leak detection cable is the best available
technology for crude oil. The Spartan report is contained herein as
Attachment #3.

<<<PAGE 959>>>

• Page 3 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
2. Mitigation Appendix - Item 22. - This item was completed prior to original
start-up in 2005 and required the installation or relocation of check valves
to mitigate potential drain down volumes. Due to the elevation profile of
the line, check valves would not effectively mitigate a leak when flowing in
the reverse direction.
Therefore, as part of the proposed project,
Magellan is proposing to replace currently installed check valves specified
by Mitigation Item 22 with remotely controlled valves (RCV). Both devices
are considered Emergency Flow Restricting Devices (EFRD's) in
accordance with 49 CFR 195.450. In some cases RCV's will be relocated
for greater accessibility to power utilities and for maintenance and thus
minimize the environmental impact of the change. Potential drain down
volumes affected by these modifications will remain below maximum drain
volumes as specified within Mitigation Appendix Item 22. All RCV's will be
in place and functional prior to initiating crude flow from Crane to Houston.
River Basin
Station Location
Approximate Current
Approximate
(Check Valve)
Proposed Station
Location Description
Notes
Pedernales
10210+24
Location (RCV)
River (maximum
10210+24
Near Flat Creek
No change in location
drain down
200,000 gallons)
volume of
10263+24
10263+24
Ulrich Rd and Co Rd 301
No change in location
10503+95
10503+95
Near the Pedernales River
No change in location
10538+00
10538+00
West Side of Pederales R.
No change in location
10742+50
10742+50
Near Cottonwood Creek
No change in location
10850+40
10810+80
Near Hwy 281
Relocated
11192+24
11192+24
School Rd
Near FM 1323 and Sandy
No change in location
11310+24
11267+52
Near White Oak
Relocated
between Austin
Colorado River
7110+58
7154÷40
Near Colorado River
Relocated
(maximum drain
and Bastrop
7357+15
7386+72
Near Bastrop, TX
Relocated
300,000 gallons)
down volume of
7877+23
7824+96
Close to Jenkins Road
Relocated
(maximum drain
Liano River
14606+59
14612+40
Near the Liano River
Relocated
250,000 gallons)
down volume of
14834+24
14834+24
Hwy 377 near London, TX
No change in location
15014+74
14988+86
London, TX
Relocated
(maximum drain
San Saba River
17143+24
17143+24
Co. RD 245
No change in location
350,000 gallons)
down volume of
17886+00
17946+72
Eldorado, TX
Relocated
18299+24
18299+24
Hwy 190 W. of Eldorado, TX No change in location

<<<PAGE 960>>>

• Page 4 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
See Attached Drain down Summary (Attachment #4) and Drain Down profiles
(Attachment #5) illustrating changes to drain down associated with the new
locations of some of the required EFRD's.
3. Section 2.1 - System Description - This language will replace section 2.1 and
2.2 in its entirety.
The pipeline system covered under the Longhorn Mitigation Plan is made up of two distinct
systems. The first system transports refined products from Odessa to El Paso, Texas.
The refined product system with an initial capacity of 64,000 bpd is made up of the following
segments:
• A 29 mile, 8" pipeline from Odessa, Texas to a station in Crane County (Crane
Station).
A 237 mile, 18" pipeline from Crane Station to El Paso Terminal. Pumping units cou
otentially be added at an existing site called Cottonwood Station to assist wit
expansion of capacity.
• Four, 9.4 mile, lateral pipelines connecting El Paso Terminal to El Paso Junction (also
known as the El Paso Laterals).
i. El Paso to Kinder Morgan, 12"
ili. El Paso to Chevron, 8"
ii. El Paso to Kinder Morgan, 8"
iv. Kinder Morgan 8" Flush Line
The crude oil system with an initial capacity of 135,000 barrels per day is made up of the
following segments:
intermediate pumping stations
A 424 mile, 18" pipeline from Crane Station to Satsuma Station with the following
• Cedar Valley - Hays County, TX
Kimble County - Kimble County, TX
• A 32 mile, 20" pipeline from Satsuma Station to East Houston Terminal.
• A 9 mile, 20" pipeline from East Houston Terminal to 9* street junction.
• A 1 mile inactive and purged section of 20" pipeline from gth street junction to Galena
Park Terminal.
bpd. To reach this capacity, Magellan may, in the future, build the following pump stations:
Based upon shipper demand, Magellan may increase capacity of the crude system to 225,000
• Texon
• Barnhart
• I
Cartman
Eckert (existing scraper trap site)
James River
•
Bastrop (existing site)
• Industry
Warda (existing scraper strap site)
Buckhorn
Satsuma (existing scraper trap site)

<<<PAGE 961>>>

• Page 5 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Per Mitigation Commitment Item 39, this change to the LMP is submitted for PHMSA
eview and approval. The proposed change in the form of this letter is made
available to the public by posting on the Magellan website. Copies of this letter are
made available to the General Manager of the Lower Colorado River Authority
(LCRA) and to the Mayors of Houston, Austin, and El Paso at the addresses shown
below. If you have any questions or need additional information, please contact me
at your convenience.
Sincerely,
Doug Chabino
Director, Asset Integrity
Office phone: (918) 574-7326
Cell phone: (918) 645-3342
doug.chabino@magellanlp.com
Cc:
Rebecca S. Motal
General Manager, LCRA
Austin, Texas 78703
3700 Lake Austin Blvd.
Mayor Annise D. Parker
City of Houston
P.O. Box 1562 Houston, TX 77251
Mayor Lee Leffingwell
301 W. 2nd St. 2nd Floor
Office: City Hall
Austin, Texas 78701
#2 Civic Center Plaza
Mayor John Cook
10th floor of City Hall
El Paso, Texas 79901

<<<PAGE 962>>>

• Page 6 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Attachment 1
Tyco Thermal Controls
Report # TT 1106-006

<<<PAGE 963>>>

tyco
TraceTok
Thermal Controls
Magellan West Texas Crude Oil (Intermediate & Sour)
TT-5000 Response Time
307 Constitution Drive
Tyco Thermal Controls
Menlo Park, CA
Report # TT 1106-006
(7/21/2011)
Lail Bednes
Prepared by:
Neil Bednar
Approved by:
Ken McCoy
(Report# TT 1106-006)
Tyco Thermal Controls Proprietary
Page 1 of 3

<<<PAGE 964>>>

TEST: TT5000 Response Time to WTI and WTS
1. Applicable Standards
None
2. Test Description
electrical resistance of each segment, so that the elapsed time to reach 10 kg (alarm threshold) could
be measured.
The segments of sensor cable were inserted into clear plastic tubing and then gently depressed to
form a low spot in the center of each test cable. 5 ml of crude oil was injected into the open end of
temperature which averaged 20.3 °C during the test period for samples #1 #2, #4, and #5. The
each tube and allowed to form a pool in the low spot. Tests were conducted at ambient lab
ambient temperature was 21.2 °C during the test period for samples # 3 and #6
Fig. 1 TT5000 WTI and WTS detection
time test setup.
Fig. 1 Crude oil pooling in specimen tubes.
The resistance between the two internal sensor electrodes in the center of the cable core is monitored
to determine sensor cable response. The beginning resistance value is essentially an open circuit and
remains a very high resistance until the cable jacket has absorbed sufficient oil to cause the cable to
"trip'. The detection time is indicated by a very precipitous drop in the resistance between the
electrodes from greater than 50 MS to less than 10 kg.
time as the point where the resistance between electrode wires drops below 10k. Electrical resistance
We noted the start time at the moment when the cable was exposed to the crude oil and the ending
and time were measured by a Fluke Data Logger and computer.
3. Test Responsibility
Neil Bednar
(Report# TT 1106-006)
Tyco Thermal Controls Proprietary
Page 2 of 3

<<<PAGE 965>>>

4. Test Results
All samples reached alarm threshold of less than 10 kg in less than four hours. The WTI was
detected in an average of 92 minutes and the WTS was detected in an average of 184 minutes at
room temperature. Às temperature rises, the detection time will decrease on the order of
approximately one half the reaction time for every 10°C as a rule of thumb.
Specimen Number
(#)
Type of Crude Oil
Time to Alarm
Average Time to
1
(min)
WTI
99
Alarm (min)
3
2
WTI
94
92
WTI
83
4
WTS
186
WTS
WTS
189
184
177
5. Equipment Used
Description
Datalogger
Manufacturer
Fluke
Model
Hydra
Software rev
NA
Serial No.
6095601
6. References
Neil Bednar's Lab book 1344-30
(Report# TT 1106-006)
Tyco Thermal Controls Proprietary
Page 3 of 3

<<<PAGE 966>>>

• Page 7 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Attachment #2
Trace Tek Chemical Response

<<<PAGE 967>>>

TraceTek Chemical Response
TraceTek.
response times at 20 deg C under laboratory test conditions. For critical applications, customers should
NOTE: This data is provided for general reference only and is not guaranteed. Values are nominal
Controls for more information.
confirm response times based on application specific installation parameters. Contact Tyco Thermal
Tyco, TraceTek and the TraceTek logo are trademarks of Tyco Thermal Controls LLC or its affiliates.
Group
Chemical
TT3000
TT5000
(TT5001
1/010 Notes
Acid
Acetic Acid 25% /
СНЗСО-ОН
Yes
Yes
Acetic acid
50%~99.4% /
Yes
Yes
СНЗСООН
FeCI3
Ferric Chloride /
Yes
9.5~37% / HCI
Hydrochloric acid
Yes
Yes
/ HF
Hydrofluoric acid 49%
Yes
Nitric acid 15~65%
Yes il
Yes
/ H2S04
Sulfuric acid 25-98%
Yes
Yes
Alcohol
Ethanol (95% in H2O)
/ CH3-CH2-OH
Yes
60 min
CH2-OН
Ethanol 100% / CH3-
60 min
ilisopropanol
Yes
90 min
(IPA) / (CH3)2 CHOH i
Isopropyl Alcohol
90 min
CH40
Methanol (100%) /
45 min
a.k.a. wood spirit, wood alcohol, methyl alcohol
in H20)
[Methanol (up to 95%
Yes
fetection at 95% concentration. Sensitivity increase
Ip to 150mm of TT3000 must be wetted fo
(less cable must be wet) for lower concentrations.
Caustic
Sodium hydroxide
(concentrated) /
Yes
Also known as Caustic Soda
NaOH
Sodium Hypochlorite /
NaOCI
Yes
Fuel
Diesel #1
| 60 min |
Diesel #2
120 min
Fuel oil #6
*
@ 60 C
* no response @ 20 C, 41~64 hrs @ 40 C, 9~11 hrs
gasoline
9~20
min*
48 min
• depends on grade and type of gasoline
gasoline vapor
3 days
5 days
Jet A
50 min
4~11
hrs
Jet B
Yes
Yes
JP-10
40 min
JP-4
15 min
<5 hrs
JP-5
70 min
<4 hrs
JP-7
25 min
10 hrs

<<<PAGE 968>>>

TraceTek Chemical Response
Trace Tek.
response times at 20 deg C under laboratory test conditions. For critical applications, customers should
NOTE: This data is provided for general reference only and is not guaranteed. Values are nominal
Controls for more information.
confirm response times based on application specific installation parameters. Contact Tyco Thermal
Tyco, TraceTek and the TraceTek logo are trademarks of Tyco Thermal Controls LLC or its affiliates.
Group
Chemical
HOOD MEADO ATTORe
i Do Notes
Fuel
kerosene
47 min
Light Sweet Crude
3 hrs
Hydraulic
fluid
Automotive
transmission fluid
4-8 hrs
Response time may vary considerably by brand and
Dextron I/ brand ~8.3 hrs Ford brand 4.1 hrs
type.
brake fluid (DOT 3)
hrs*
~30
hydraulic oil
days*
3~8
"depends on type
Lubricant
SAE 20 motor oil
<1 day
SAE 30 motor oil
2 days
Other
Aliphatic
(generic)
hydrocarbon
Varies
Fuels and oils are typically aliphatic (long chain) HC's,
translates into viscosity (longer = heavier) and hence
with some aromatics blended in. Length of chain
into longer response times.
Hydroxide / NH4OH
Ammonium
Yes
must be in solution; will not detect dry form
anisole
Yes
1.7 hrs
33 min
carbon disulfide
3 min
chloroform
12 min
10 min
dimethylformamide
Yes
2 hrs
Dowtherm A
10 hrs
90 min
Dowtherm J = alkylated aromatic
Dowtherm A = diphenyl oxide / biphenyl blend
ethyle acetate
20 min
ethylene glycol
Yes
Formaldehyde
temperature. (Boiling Point -21C) When it is dissolved
See Formalin. Formaldehyde is a gas at room
in water (remember the frogs in your biology class) it is
called formalin. Usually the commercial concentration
is 40% in H20
Formalin
Yes
(dissolved in H20, typically 40% solution).
This is the typical liquid form of Formaldehyde
Freon TF
22 min
: 42 min
gum turpentine
10 min
20 min
(heptane
10 min
60 min
Hydrogen Peroxide /
H202
Yes
mineral spirits
Mobiltherm 603
20 min
<9 hrs
<4 hrs
Naptha
15 min
PCB
<9 hrs

<<<PAGE 969>>>

TraceTek Chemical Response
Trace Tek.
NOTE: This data is provided for general reference only and is not guaranteed. Values are nominal
confirm response times based on application specific installation parameters. Contact Tyco Thermal
response times at 20 deg C under laboratory test conditions. For critical applications, customers should
Controls for more information.
Tyco, TraceTek and the TraceTek logo are trademarks of Tyco Thermal Controls LLC or its affiliates.
Group
Chemical
TT3000
TT5000
TT5001
TT7000
Notes
Other
Prestone antifreeze
Yes
Shell Diala X transformer oil
13 hrs
Transformer oils vary considerably.
styrene monomer
20 min
8 min
(tetrahydrothiophene
25 min
27 min
Solvent
/methanol
50/50 methylene chloride
< 10 min
Blend of methylene chloride and
methanol
acetone
| 10 min
Acetone (30% in H20)
Yes
Acetone 50% in 20)
Yes
80 min
butyl acetate
20 min
carbon tetrachloride
20 min
20 min
chlorobenzene
21 min
10 min
cyclohexane
32 min
dichloromethane
13 min
5 min
Ethyl benzene
Yes
Methy! Ethyle Ketone (MEK)
10 min
T73000
Avoid exposure to TT1000 or
Methylene Chloride
~5 min
N-methyl pyrrolodone
60 min
(dissolves kynar)
Will damage TT3000 / TT1000
toluene
18 min
10 min
[trichloroethane
20 min
trichloroethylene
8 min
(xylene
20 min
35 min

<<<PAGE 970>>>

• Page 8 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Attachment #3
Pipeline Leak Detection Systems Direct
Detection
Spartan Engineering, Inc.

<<<PAGE 971>>>

Pipeline Leak
Detection Systems -
Direct Detection
Prepared for:
MAGELLAN MIDSTREAM PARTNERS, L.P.
October 18, 2011
(R3)
By:
SPARTAN
ENGINEERING INC.

<<<PAGE 972>>>

CONTENTS
1.0
Overview
2.0
Executive Summary
3.0
Types of Leak Detection Systems
3.1
General
3.2
Liquid Sensing Leak Detection
3.3
Vapor Sensing Leak Detection
3.4
Fiber Optic Leak Detection
3.5
Ultrasonic/Acoustical Leak Detection
3.6
Comparison
4.0
Conclusions and Recommendations
5.0
Appendix
5.1
Corporate Contact Info
5.2
Tycho Thermal Controls Data
5.3
Asel-Tech Data
5.4
Nitor Technologies Data
5.5
Sensornet Data

<<<PAGE 973>>>

1.0 Overview
Magellan is interested in currently available technology for early detection of pipeline leaks that
can be employed on the section of the Longhorn pipeline traversing the Edwards Aquifer.
Additionally, because the Longhorn Reversal project will introduce crude oil to the line, there is
interest in the capability of these systems to adequately detect crude oil.
This report focuses on the direct sensing style of pipeline leak detection systems that are most
capable of detecting small leaks. The direct methods include liquid sensing cables, fiber optic
cables, vapor sensing tubing, and ultrasonic sensing. Information on these direct sensing methods
(and companies that can provide them) has been compiled from an extensive search and is
included in appendices of this report.
1

<<<PAGE 974>>>

2.0 Executive Summary
Each of the four direct pipeline leak detection technologies investigated will detect crude oil. Direct
detection methods are best at detecting leaks that are less than about 0.5% of the pipeline flow
rate, while computational methods are best at detecting leaks that are greater than about 0.5% of
the pipeline flow. Therefore, to cover all circumstances, it is recommended Magellan maintain
both types of systems. For the direct sensing method, it is recommended to retain the existing
Tyco TraceTek TT5000 system. It has the advantage of already being in place, it has the ability to
detect leaks as small as 0.01 GPH, it can locate leaks accurately, and it has proven to be reliable.
The liquid sensing cable systems are the most sensitive for detecting small leaks with a 2-3 hour
response time. The existing Tyco TraceTek TT5000 is extremely robust and reliable and capable of
detecting leaks as low as 0.01 GPH and is not impacted as much because of soil porosity, soil
temperature and low vapor pressure as the other systems reviewed. See Section 3.2 under Tyco
TraceTek TT5000 for a detailed discussion.
Vapor sensing systems are not as sensitive to small leaks or to leaking materials with very low vapor
pressures, such as heavy oils. Additionally, response time is more dependent on soil porosity and
soil temperature than the liquid sensing systems. The minimum detectable leak size is 0.04 GPH, in
high-sensitivity mode. See Section 3.4 under Nitor Technologies for a detailed discussion.
Fiber-optic cable systems and acoustic sensing systems are very poor at detecting small leaks.
These units rely on either a change in temperature or an acoustic footprint to detect leaks. These
systems are very reliable when detecting leaks of highly volatile liquids but they are not suitable for
crude oil since the leak does not develop a sufficient differential temperature (essentially ground
temperature) nor does it develop enough acoustic energy to allow the system to reliably detect a
small leak. Additionally, the reliability decreases as the vapor pressure of the material to be
detected approaches zero. See Section 3.4 Fiber Optic Leak Detection and Section 3.5
Ultrasonic/Acoustical Leak Detection for a brief discussion.
2

<<<PAGE 975>>>

3.0 Types of Leak Detection Systems
3.1 General
The available pipeline leak detection systems (LDS) fall, generally, into two broad classes; 1)
discussed because this topic is beyond the scope of this report.
Direct detection, and 2) Computational/Statistical. Computational/Statistical will not be
API Publication 1149 outlines methods for calculating the size of a leak in terms of the total
pipeline flow rate. This leak rate is often described as a percent of the total pipeline flow with
the total flow given to estimate the leak size.
The direct detection methods are associated with efforts to detect leaks with sensing systems
that can locate the leak within a few meters of its origin. These include: 1) Liquid Sensing leak
detection, 2) Vapor sensing leak detection, 3) Fiber-optic leak detection, and (4)
Ultrasonic/Acoustical leak detection.
Direct leak detection depends upon a sensing system in the area around the location that has
been deemed to be most sensitive to the effects of a pipeline leak. These detection techniques
depend upon a change in some physical property associated with the pipeline, the pipeline
surroundings, or changes to a sensor based on some characteristic of the leaking fluid. These
can be summarized as: 1) the conductivity (or electrical resistance) of the cable; 2) localized
temperature changes; 3) some characteristic physical effect that is always associated with a
leak, such as the presence of vapor, or the sound associated with a leak.
3.2 Liquid Sensing Leak Detection
Liquid sensing cables are buried beneath or adjacent to a pipeline and are specifically designed
to detect changes in transmitted energy pulses as a result of impedance differentials induced
by contact with hydrocarbon liquids.
Safe energy pulses are continuously sent by a
microprocessor through the cable. The pulses are reflected and returned to the micro-
processor. Based on the specific installation of the cable, a baseline reflection map is stored in
the memory of the microprocessor. When a leak occurs, a portion of the cable is saturated
with fluid. The fluid alters the impedance of the sensing cable, which in turn alters the
reflection pattern returning to the microprocessor. The change in signal pattern causes the
microprocessor to register a leak alarm that also locates the position of the altered impedance.
Controller interface software is available to provide real-time information on leak detection and
record keeping. Cable types are chosen for each application based on the specific type of fluid
being monitored.
The cable detects a leak independently of the leak rate and thus is a good choice for small
leaks, which are more difficult to detect than large leaks. The sensor cable responds directly to
the presence of the liquid and not to the rate at which it arrived. Additionally, the leak
detection cable can report the spill location to an accuracy of a few feet.
Liquid sensing leak detection is typically marketed as a self-contained leak detection and
location system, including all hardware and software. Advantages include relatively high

<<<PAGE 976>>>

accuracy in determining leak location, no modifications to existing pipeline, and simple
software configuration and maintenance.
A system that detects oil leaks based on a change in electrical resistance is the Tyco TraceTek
TT5000. The Tyco system can locate leaks to within a few feet of their source. An analysis of
the Tyco TraceTek TT5000 leak detection cable currently used on the Longhorn Pipeline System
is provided to determine its applicability to a crude oil pipeline.
Iyco TraceTek TT5000 Leak Detection Cable
The Tyco TraceTek TT5000 leak detection cable currently in use on the Longhorn Pipeline
System is usable for detecting crude oil leaks, as demonstrated by Tyco (see Table below). The
minimum detectable leak size is 0.01 GPH. The TraceTek cable system is apparently the only
electrical conductivity cable available. It should be noted that after a leak is detected by the
cable, the portion of the cable that was exposed to the leak must be replaced.
Tyco Thermal Controls has performed testing on three different oils, West Texas Intermediate
summarized in the table below.
(WTI), West Texas Sour (WTS) and ARCO North Slope Oil. The results of these tests are
TT5000 Response Time
Oil Type
Temperature 68°F
Temperature 104°F
WTI
92 to 93 minutes
15-20 to 22 min
WTS
184 to 190 minutes
42 to 45 min
ARCO North
Slope
180 minutes
42 minutes
The results indicate that the TT5000 will respond to the presence of a WTS oil leak within about
3-hours after the sensor cable has been in contact with the oil. In other words, for very small
leaks the TT5000 will always set off an alarm.
3.3 Vapor Sensing Leak Detection
The Leak Alarm System for Pollutants (LASP) consists of a vapor sensing tube installed along the
entire length of the pipeline. This tube is impervious to water but allows petroleum vapors to
pass and accumulate. A vacuum pump periodically draws the air from the tube and passes the
air stream through a sensor which detects the presence of petroleum vapors. Detectable
substances include a wide range of gases, hydrocarbon liquids and vapors, halogenated
hydrocarbons, landfill gases, water vapor, and many others. This vapor sensing system has the
potential to detect leaks of all sizes; however, very small leaks can take 30 hours or more to
detect.
The detection tube is manufactured in the form of a cable and is highly permeable to the
substances to be detected in the particular application. If a leak occurs, the substances to be
measured come into contact with the tube in the form of vapor, or gas dissolved in water. In
the event of a leak, some of the leaking substance diffuses into the tube. After a period of time
4

<<<PAGE 977>>>

has passed, enough vapor will accumulate inside the tube so that when the air in the tube is
pulled past the detector there will be enough vapor to produce an accurate identification of the
substances surrounding the tube. The detector unit at the end of the sensor tube is equipped
with gas sensors so that an increase in gas concentration results in a pronounced "leakage
peak," which is proportional to the concentration of the vapor from the leaking medium at the
sensor tube surface.
A disadvantage of the LASP technology is that the time required to draw a vapor slug to the
detector will vary substantially because of diurnal and seasonal changes causing decreased leak
location accuracy.
Nitor Technologies, Inc. PROWLER LDS
Nitor Technologies, Inc. carries the PROWLER system and has upgraded the LASP system
technology. The published minimum detectable leak size is 0.04 GPH. However, this leak rate is
not referenced with a statement about the volatility and temperature of the leaking substance
was not specified in the literature.
Vapors emitted by the leaking crude oil diffuse into the PROWLER tubing and reach a steady
state or equilibrium concentration. The PROWLER pump is then activated to move the vapors
in the tubing to the detector, where measurements are made. Depending on soil porosity and
oil vapor pressure, several hours may be required for gases and vapors to migrate from the leak
site to the PROWLER tubing. To see a change from the baseline condition, a minimum of two
runs is needed, each taking as long as 15 minutes.
The PROWLER can locate the position of the leak to within 1% of the length of the pipeline. For
a twenty mile long section of pipeline, the accuracy would be less than 1100 feet. Using
secondary test points, the location of the leak can be determined to within 50 feet. More
precise leak location requires that a spike of tracer gas, such as Hydrogen or Ethane, be injected
at the front end near the inlet-air dryer unit.
For sizeable leaks, the density of the crude oil has little impact on response time. However, at
very low leak rates the crude oil and the vapors emitted by the crude oil require more time to
move through soil. Very small leaks of a heavy crude oil, as well as the vapors emitted by that
oil, will move through the soil much slower than the rates observed for lighter refined products
and their vapors to move through the soil.
The reliability of vapor sensing systems is lower than the liquid sensing cable systems. The
system is prone to set point drift and requires chromatographs that can lose sensitivity unless
properly calibrated and maintained.
A second sensor tube can be installed that continuously draws a vacuum. This option allows for
a more rapid detection of large leaks (greater than 0.5% to 1.00% of flow) while still enabling
the detection of small leaks by the periodic removal of the tubing air from the other tube.
Operating with two tubes in this manner is recommended by the manufacturer.
3.4 Fiber Optic Leak Detection
5

<<<PAGE 978>>>

The fiber-optic sensing leak detection method involves the installation of a fiber-optic cable
along the entire length of the pipeline. The substances to be measured come into contact with
the cable when a leak occurs, changing the temperature of the cable. The distributed fiber-
optical temperature-sensing technique offers the possibility to measure temperature along the
determined, leading to leak detection.
pipeline. Scanning the entire length of the fiber, the temperature profile along the fiber is
Optical fiber sensor cables have been demonstrated to be useful for the measurement of a
wide variety of physical and chemical parameters because they have: 1) an immunity to
wide variety of measured quantities, 4) avoidance of electric sparks, 5) resistance to harsh
electromagnetic interference, 2) avoidance of ground loops, 3) capability of responding to a
environments, 6) remote operation, 7) capability of multiplexing, and 8) ease of integration into
large-scale fiber networking and communication systems. The reliability of the optical fiber
cables is questionable for long-term use because of their fragility and the possibility of false
positive signals caused by the presence of groundwater. For small crude oil leaks under low
pressure, the leaking substance will have adequate time to thermally equilibrate with the
material that surrounds the pipeline and the thermal sensor. Since the liquids and sensor will
sensor to determine. This makes the fiber-optic LDS less desirable for crude oil applications. In
be at the same temperature there will be little or no differential temperature for the fiber-optic
fact, no reference has been found where fiber optic cable has been used in the determination
and location of crude oil leaks from pipelines.
Two of the companies that supply fiber-optic based LDS's are Sensornet and Westminster, Intl.
The Sensornet Fiber-Optic Based LDS
The Sensornet fiber-optic cable system allows the inference of a leak by detecting the change in
temperature of the fiber-optic cable when it becomes exposed to the leaking fluid or a change
in temperature of the space around the cable caused by the nearby presence of the leaking
fluid. To date, the use of Sensornet's leak detection system has been for the detection of leaks
on and around highly pressurized natural gas liquid products such as ethane, ethylene,
propane, Y-grade products, and ammonia.
Westminster, International Fiber-Optic Based LDS
Westminster International appears to be in the private sector security business. They propose
leaking from pipelines and storage tanks.
that their fiber-optic cable systems be used to detect temperature changes caused by NGL's
3.5 Ultrasonic/Acoustical Leak Detection
Leak detection in pipelines using acoustic emission technology is based on the principle that an
leak occurs, the resulting low frequency acoustic signal is detected and analyzed by system
escaping liquid creates an acoustic signal as it passes through a perforation in the pipe. When a
processors. Deviations from the baseline acoustic profile would signal an alarm. The received
signal is stronger near the leak site, thus enabling leak location.
6

<<<PAGE 979>>>

Asel-Tech
Asel-Tech has developed an acoustic/mass-balance/computational LDS that holds the
possibility of improving the computational technology. Response time can be as short as a
minute for leaks that are large enough to be acoustically detectable; however, the system's
ability to detect small leaks is greatly reduced in low vapor pressure liquids that cannot
generate sufficient acoustic energy to be detected over background noise.
3.6 Comparison
The following table summarizes the properties of the various direct leak detection systems:
Leak
Detection
Response Time
Detectable Leak Size
System
TraceTek
Tyco
The detection response time is not dependent
Leak rates lower than 0.01 GPH
upon the leak rate. It is dependent upon the soil
are detectable over a long
TT5000 Leak
porosity and the substance temperature. From
period of time. The cable is
Detection
the data supplied by Tyco for Magellan: the
responsive to both small and
Cable
response time for the WTS heavy crude is about
large leaks. Response is not
45 minutes at 104°F and 190 minutes at 68°F; and
for WTI light crude about 22 minutes at 68°F and
dependent on the leak rate.
The TT5000 is immune to the
93 minutes at 68°F. As a comparison, response
presence of water.
times for data done by Tyco for Arco on their
North Slope crude: 42 minutes at 104°F and 180
minutes at 68°F. Leak location is typically within
"a few meters" of the leak.
Nitor Vapor
Sensing
The detection response time is dependent upon the leak rate, the soil porosity, and
System -
the oil volatility. In the high speed mode the system can detect leaks of 600 to 1300
High Speed
GPH within a few hours. Large leaks, 12600 GPH or larger, can be detected in less
Mode
than 30 minutes. Additional response time factors include calibration frequency and
the type and sensitivity of the chromatograph. The maximum detectable leak has no
upper limit. The system is immune to the presence of water.
Nitor Vapor
As with the high speed mode, the detection response time is dependent upon the
Sensing
leak rate, the soil porosity, calibration frequency, and the oil volatility. In the high
System -
sensitivity mode detection time for the PROWLER is determined by the system's
High
setup parameters but is often given as 12 hours. While the published minimum
Sensitivity
Mode
detectible leak rate is about 0.04 GPH the response time for this small leak rate may
be as long or longer than 30 days. The system is immune to the presence of water
Fiber Optic
The leak detection time for a fiber optic system Fiber optic LDS is responsive to
Leak
depends upon the time required for the leak to both small and large leaks.
Detection -
cause a temperature change in the cable.
Response time is dependent on
Sensornet
Response times are very fast for high volatility
the vapor pressure of the
and West- fluids like ethane, but for small low pressure
minster
leaking material and on the leak
crude oil leaks there may not be a response.
rate.
7

<<<PAGE 980>>>

Leak
Detection
Response Time
Detectable Leak Size
System
Hybrid
Asel-Tech has developed an acoustic/mass-
Leaks less than about 0.1% of
Computa-
balance/computational LDS that holds the
total flow may not be detected.
tional LDS - possibility of improving the computational
Leaks that are greater than 0.5%
Asel-Tech
technology. Response time can be as short as a
to 1% of total flow can be
minute for leaks that are large enough to be
detected.
acoustically detectable.
4.0 Conclusions and Recommendations
Each of the four direct pipeline leak detection technologies investigated will detect crude oil. For
small leaks that are less than about 0.1% to 0.5% of the total pipeline flow rate, the TraceTek
TT5000 is the most sensitive to crude oil. The Prowler vapor sensing system can also detect oil but
its response time will be slower than the TT5000 because the loss of sensitivity associated with low
vapor pressure crude oil. For leaks that are greater than 0.5% to 1% of the total pipeline flow rate,
the fiber-optic cable and acoustic detection systems provide the fastest response time, giving
indication of a leak in less than a minute after being contacted by the leaking substance. However,
the Sensornet and Westminster fiber-optic systems may be less sensitive to crude oil than the
other three leak detection systems because there will be little if any temperature change
associated with a leak from a low pressure crude oil pipeline. Acoustic leak detection systems are
also hampered by crude oil at low pressures because small leaks will not generate enough acoustic
energy to be detected over the background noise.
Because direct detection methods are best at detecting leaks that are less than 0.5% of the pipeline
flow rate, and while computational methods are best at detecting leaks that are greater than about
0.5% of the pipeline flow, it is recommended that Magellan maintain both types of systems. For
the direct sensing method, it is recommended to retain the existing Tyco Trace-Tech system. It has
the advantages of already being in place, it can pinpoint the leak accurately, and has been proven
to be reliable. The Nitor system is not recommended for detecting small leaks because the
response time due to the low volatility crude oil is too great to detect them in a timely manner.
The Sensornet, Westminster, and Asel-Tech systems are not recommended for use in detecting
small leaks from low pressure crude oil applications for the reasons noted in section 3.4, above.
8

<<<PAGE 981>>>

5.0 Appendix
5.1 Corporate Contact Information
Tyco Thermal Controls LLC
2415 Bay Road
Redwood City, CA 94063-3032
Tel: (800) 545-6258
Fax: (650) 474-7215
TraceTek TT5000
http://www.tycothermal.com/
Asel-Tech
Sao Carlos, Brazil
Brazilian Corporation
USA (281) 619-5754
USA (281) 990-2574
http://asel-tech.com/
PROWLER
Nitor Technologies, Inc.
2750 Constitution Boulevard
Beaver Falls, Pennsylvania 15010
Telephone (724) 891-4115
Fax (724) 847-6444
http://www.nitortechnologies.com/
Sensornet
(British Company)
2002 Timberloch PL
Suite 200, The Woodlands
TX 77380, USA
Alan Sanderson
Ph: +1 281-296-5827
alan.sanderson@tendeka.com
http://www.sensornet.co.uk/
Westminster, International, Ltd
Westminster House, Blacklocks Hill
Banbury
Oxfordshire
OX17 2BS
United Kingdom
+44 (0) 1295 756300 Phone
+44 (0) 1295 756302 Fax
Use website to make contact
www.wi-ltd.com
9

<<<PAGE 982>>>

• Page 9 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Attachment #4
Drain Down Summary

<<<PAGE 983>>>

Longhorn Pipeline Reversal
LMP Changes
Drain Down Summary - Attachment #4
Page 1 of 1
Colorado Basin
Valve 1
Location
Existing MP
Valve 3
Valve 2
139.34|
134.67
Proposed MP
135.51
Existing Station
Proposed Station
149.19
139.91
7357+15
7110+58
7154+93
148.08
7877+23
7818-22
Pederales Basin
Vaive 4
Valve 5
205.49
214.21
20175-
10849+87|
11310+29
11268+05
10810+80
Liano Basin
Valve 7
Valve 6
236511
14606+59
15014+74
4616+1
4987+8
San Saba Basin
Valve 8
338.75
339.91
17886+00
17947+25
Colorado
drain down (gal)
Existing Max
Proposed Max
116,622
99,203
Drain down (gal)
Drain down (gal)
Settlement Max
Between Bastrop and Valve 1
191,061
120,344
300,000
Between Valve 1 and Valve 2
263,689|
191,061
300,000
Between Valve 3 and Austin
Between Valve 2 and Valve 3
263,689
300,000
300,000
Pedernales
Between Valve 4 and MP 211.97
Between MP 203.44 and Valve 4
80,634
84,365
43,423
Between Valve 5 and End of Basin
136,472|
55,830
131,510|
200,000
Between MP 211.97 and Valve 5
136,472
37,220|
200,000
200,000
200,000
Llano
Between MP 276.46 and Valve 6
Between MP 280.94 and Valve 7
Between Vaive 6 and MP 280.94
107,937
23,573[
23,573
Between Valve 7 and End of Basin
126,547
94,290
107,937
250,000
250,000
140,241
250,000
250,000
San Saba
Between Valve 8 and MP 346.57
Between MP 324.68 and Valve 8
275,426
181,136|
241,928
270,463
350,000]
350,000|
proposed valve relocations with drain down volumes 1-25-12.xlsx

<<<PAGE 984>>>

• Page 10 - Longhorn Pipeline Reversal- LMP Changes
2/14/2012
Attachment #5
Drain Down Volumes

<<<PAGE 985>>>

Attachment 5 - Drain Down Volumes
East Houston to Crane 18"
Bastrop to Austin
To Houston
To Crane
1000.00
350000
300000
- 250000
200000
Elevation (ft)
Volume (gal)
500.00
150000
100000
N
- 50000
0.00
0
133
143
153
Milepost (miles)
- Elevation
-- Proposed Valves
-• Non relocated valves
- Existing, Valves
- Proposed Draindown
- Original Draindown

<<<PAGE 986>>>

Attachment 5 - Drain Down Volumes
East Houston to Crane 18"
Pedernales River Basin
To Houston
To Crane
2500.00
250000
200000
2000.00
- 150000
Volume (gal)
1500.00
100000
1000.00
50000
500.00 +
191
201
211
221
Milepost (miles)
- Elevation
-Proposed Valves
-• Non relocated valves
→ Existing Valves
— Proposed Draindown
— Original Draindown

<<<PAGE 987>>>

Attachment 5 - Drain Down Volumes
East Houston to Crane 18"
Llano River Basin
To Houston
To Crane
2500.00
350000
300000
250000
- 200000
Elevation (ft)
Volume (gal)
2000.00
150000
- 100000
1500.00
276
286
Milepost (miles)
— Elevation
→-Proposed Valves
-• Non relocated valves
Existing Valves
—- Proposed Draindown
——- Original Draindown

<<<PAGE 988>>>

Attachment 5 - Drain Down Volumes
East Houston to Crane 18"
San Saba River Basin
To Houston
To Crane
3000.00
400000
350000
300000
250000
Elevation (ft)
2500.00
150000
100000
- 50000
2000.00 +
323
333
343
Milepost (miles)
— Elevation
-- Proposed Valves
- Non relocated valves
- Existing Valves
- Proposed Draindown
-- Original Draindown

<<<PAGE 989>>>

Review of Engineering Design Basis for Containment - Nineteen Mile
Replacement Section
Longhorn Partners Pipeline, L.P.
Report prepared for US Fish & Wildlife Service
November 30, 2001
Prepared by
Dr. Ibrahim Konuk
39 Rocky Hill Road
Princeton, NJ 08540
Tel: (732) 355-1544

<<<PAGE 990>>>

Table of Contents
Section
Page
1.0 Introduction and Purpose
2
2.0 General Discussion of Effectiveness of the Proposed Containment System for
2
Different Pipeline Failure Scenarios
3.0 Comments on the Design Basis Document and the Performance of the
4
Proposed Containment System
4.0 Observations and Recommendations
5
Appendix: List of Documents
7

<<<PAGE 991>>>

1.0 Introduction and Purpose
Longhorn Pipeline Partners (Longhorn) decided to replace about 18 mile section of the
Longhorn Pipeline from the mile post 169.8 (Station 8965+00) to the mile post 188.8
(Station 9968+64). This pipeline segment crosses the Edwards Aquifer area: Edwards
Recharge Zone, a segment about three miles long, starting at about mile post 170, and the
Contributing Zone about 15 Miles in length to the west of the recharge zone. As part of
this replacement program, Longhorn designed a product containment system, which
would contain any released product or divert it to designated berm locations in case of a
pipeline failure involving a product release. This system involves a specially designed
pipeline trench of different depth and size depending on the location, road bore pits on
either side of all the road crossings, and diversion berms at select locations that would
promote any product reaching the surface to be diverted to designated locations. The U.S
Fish & Wildlife Service (Service) and Longhorn Pipeline Partners have requested that the
author review the proposed containment plan and comment on the validity of the
calculations prepared to support the system design and the effectiveness of this system
for the purpose of containment of any product release from the pipeline.
This document presents an overall assessment of the proposed containment system in
case of various size pipeline ruptures or leaks. It verifies the sample calculations provided
in the design basis document (Reference 1). It also comments on the assumptions used in
deriving the spill volumes.
The author would like to note that two reports were prepared by the author in 1999 and
2000 on the pipeline risks and effectiveness of the mitigation measures to prevent or limit
the risks resulting from a pipeline leak for the original pipeline that covered an area from
the mile post 170 to the milepost 179. The proposed pipeline replacement plan contains
this area and it addresses or voids all of the issues raised in those two reports. The
proposed containment system addresses issues that were not directly within the scope of
those two reports.
This work was requested by the U.S. Fish and Wildlife Service and paid for by the
Longhorn Pipeline Partners. The author would like to note that he received full
cooperation from Longhorn and Service officials in conducting this work.
2.0 General Discussion of Effectiveness of the Proposed Containment
System for Different Pipeline Failure Scenarios
The following few paragraphs are taken from the report prepared by the author on August
31,2001:
"The pipeline is well above the current code of practice and exceeds the requirements
of the current applicable regulations. In addition, the company agreed to apply a very
stringent public awareness and third party education programs including extensive
signage. The company is also going install a secondary leak detection system in this
three-mile segment to detect small leaks.
2

<<<PAGE 992>>>

During a telephone conference arranged prior to the June 23 meeting, the author
pointed out that the procedure for the remediation of the potential unsupported
sections over any caves or cavities found during the trenching operation is left to the
contractor. The company has agreed to develop procedures in advance and incorporate
them into the construction specifications that will be used for contracting the
installation of the pipe. During the June 23 meeting, the company representatives
explained that all cavities would be grouted and, where the cavity is larger than a
certain size, a (steel) reinforced concrete support will be constructed. In addition,
during the June 23 meeting, it was explained that red colored fiber reinforced concrete
slabs would cover the pipeline trench, to reduce third party intrusion.
Considering the quality of the new line pipe, the conservativeness of the design, and
the prevention measures from the third party damage, including the protective
concrete slabs, and the redundant leak detection system (cable), the author considers
the risk posed by this segment to be very low, well below the historical records
collected from other pipelines. Although some attempt has been made to estimate this
risk in References 1 and 2, these estimates are grossly conservative for this segment of
the pipeline. The author believes that, assuming that all the operations procedures are
implemented and commitments to improve these procedures as more experience is
gained from the pipeline followed, the probability of a significant leak, defined as a
release of product more than one barrel, in this three mile section should be much
smaller than the score of 1 incident per 2000 years per mile of pipe. Also the author
cannot see any other design improvements that can significantly decrease this risk
score for this three-mile segment.
Longhorn is to be commended for the risk reduction measures proposed over the
Recharge zone of the Edwards Aquifer. The author believes that the risk from this
pipeline is reduced by at least one order of magnitude when compared to the
Contributing Zone, which is discussed in the next section."
At the time, these comments were directed towards the pipe replacement plan, which
applied only to a subsection of the contributing zone. These observations now apply to
the whole of the recharge and contributing zones. It should, therefore be noted that the
scenarios discussed in this section are, in general, a very low probability - well below the
risks posed by most engineering systems. They are included for the sake of completeness
and also to clarify the context of assessments presented in this report on the containment
system.
Small and medium size leaks (from 1/10th
'of inch to several inches) can result from
corrosion or a construction defect fatigue (dent and gouge) coupled with corrosion or a
small weld defect opening. Longhorn will employ measures during the construction and
commissioning to ensure that no such defects exist in the pipeline when it is
commissioned. In addition, they intend to utilize monitoring procedures that would detect
such defect before it leads to a failure. The probability of such a failure would be
extremely low if the monitoring procedures that were presented to the author during the
review of the original pipe are being applied. The detection of such defects is well within
the capabilities of the inspection tools planned to be used by Longhorn. The chance of a
corrosion defect leading to failure is, therefore, a very unlikely scenario due to the fact
3

<<<PAGE 993>>>

that Longhorn is committed to regular monitoring. Longhorn is planning to X-ray 100%
of the field welds. It is also very unlikely that a weld defect could lead to such a failure.
Even if a leak occurred, it should normally happen at relatively low pressure close to the
design or the operating pressure of the pipeline. If a small or medium size leak happens
during the normal operation of the pipeline at around 350 psi, the pore pressures within
the trench in the vicinity of the failure location would gradually increase until the pipeline
is shut-down. Since the maximum shutdown period is 5 minutes, if we assume that 350-
psi would be maintained during that period at the rupture point, the pore pressures may
reach to these levels several yards away from the failure location. Although all the
construction joints in the pipeline trench are planned to be sealed, it is possible that a
small quantity of the product may seep through some of the weak points between the
cover slabs and the trench wall. It is very difficult to predict the volume of seepage
without conducting some kind of pressure tests in a sample trench. However, the author
would not recommend such a test as the likelihood of this occurrence is too low and the
potential volume of product that can seep is extremely small.
Large leaks can result from operator error such as accidental closing of valves and/or a
brittle crack propagation event initiated at a defect by a similar over-pressurization
condition. Normal maximum design pressure for the proposed 18 inch × 0.375 inch pipe
is about 2000 psi depending on the safety factor used. The actual burst pressure for this
pipe would be 2 to 3 times higher for a properly manufactured and inspected line pipe of
this grade. In addition, the quality of the steel (high toughness) to be used for this pipeline
is such that a brittle crack propagation event is extremely unlikely. Given current pipeline
constructions standards and commitment by Longhorn to inspect the pipeline during
construction and commissioning, and to monitor it during operation, the probability of a
large leak occurrence is too small to be meaningfully calculated. However, if such a leak
occurred, it would likely mean that the product pressure at failure location could reach a
fairly high pressure (compared to 350psi normal operating pressure in this segment). In
this case, the transient pore pressures developed in the trench may be high enough to lift
the pipeline cover and some of the concrete slabs and discharge some of the product to
the surface before a steady state condition is reached. At that point, a normal drain-down
process would start as intended by the designers of the containment system. The quantity
of material reaching the soil surface would depend on the location and the pressure at
failure. Given the overall design of this pipeline and considering that this 18-mile
segment is bound by pipe with lower pressure rating, this scenario could not reasonably
be considered in the design. As it is stated above, it is included in this report for the sake
of completeness.
Regular third party damage scenarios are also very unlikely due to the installation of
reinforced and specially colored concrete slabs. Regular construction equipment can
normally not penetrate through the trench cover. As it is practice for commercial oil and
gas pipeline designs, intentional third party damage is not included in the design. In the
same way, major construction interference scenarios are also not considered, as
appropriate precautions would be expected before such construction operations take place
close to or within the pipeline right-of-way. The author would like to note again that the
Longhorn pipeline, in the subject area, is designed against all required (by codes and
regulations) load and failure conditions that can reasonably be incorporated in a pipeline
4

<<<PAGE 994>>>

design. The design also incorporates features that address scenarios resulting from such
failure conditions.
3.0 Comments on the Design Basis Document and the Performance of the
Proposed Containment System
Based on the discussion presented in the previous section, in the rest of this document,
he tocus Will be on the small size leaks. The containment system provides a combinatior
of Containment Trench, Road Bore Pits, Containment Berms, diversion berms, and Flow
Restricting Devices. The overall objective of the system is to capture any released
product within the pipeline trench or divert any excess volume to the Containment
Berms. The pipeline trench is designed to include material with large porosity, which
would provide the first line of defense by providing the space for the leaked product. The
pipeline trench would be inspected by using sumps (pipes) to ensure that voids in the fill
material are not filled with water. The sumps also can be used to remove any water that
may seep into the trench. The Containment Berms are designed to capture any excess
product. They would be equipped with special hydrocarbon sensing devices to allow the
rainwater to drain out but not the product in case of a pipeline leak. The berms are always
designed to be positioned on the lower side of the trench that they drain. This is done to
promote gravity drainage. The trench size and berms are designed to contain the product
released during the shut-down period (5 minutes) at worst case rate, subsequent drain-
down volume, about 1% allowance for the pipeline expansion due to pressure, 12 hours
10 inch rain storm water (stated to be the 100 year rain storm). Flow Restricting devices
are to be installed in eight locations to isolate different sections of the pipeline and
minimize the drain volumes. These devices are check-valves and remotely operated
block-valves. The elevation profile between these devices or the highest applicable drain-
down point is kept between about 40 feet to 130 feet.
Reference 1 describes design features as part of the containment system for 51 locations.
Some of these features are coupled in function. The volume of containment for the
relevant part of the trench considering the appropriate elevations and the berm or bore
pits are calculated in each case. The direction of drainage is clearly specified.
Sample calculations are provided in Reference 1 for one pipeline trench location and one
road crossing. The Reference 1 also contains sample drawings for the trench and bore pits
at those locations. The author would like to confirm that the sample calculations provided
in Reference 1 are correct and are based on valid assumptions. However, the graph
provided in Appendix B appears to contain some shift in the horizontal scale in
comparison to the figures provided in the Excel printout included in the same appendix. It
is recommended that this graph be re-drawn at a larger scale if it is to be used for the
purpose described in the next section. The author would like to note that some of the
extreme scenarios discussed in the previous section are not discussed or mentioned in
Reference 1.

<<<PAGE 995>>>

4.0 Observations and Recommendations
It is recommended that the description of the 51 containment features (locations) and the
graph included in the Appendix C be provided to all emergency response personnel along
with the regulatory authorities (after it is updated to a larger scale). Any deviation in
observed volumes in case of a pipeline failure occurrence should be explained in order to
ensure that other unknown pathways do not provide drainage.
The author observes that great effort is gone into design of the containment system. It is
recommended that this be complimented by similar supervision of the construction
procedures so that intended quality is maintained throughout, thus not creating any weak
points in the system. The author would like to mention that the proposed system is the
most comprehensive global containment system for any pipeline in North America
known to the author although local containment berms have been used in some instances.
6

<<<PAGE 996>>>

Appendix: List of Documents
Engineering Design Basis for Containment - Nineteen Mile Replacement Section 18" Products
2.
Pipeline Alignment Sheets from 6645-AL-0076A1 (Station 8965+00) to 6645-AL-0080G (Station
Pipeline, L.P., Prepared by Paragon Engineering Services, Inc., October 2001.
9982+00), Dated 8/31/00 to 9/12/00.
Revised on November 30, 2001, 2001.
November 16, 2001.
7

<<<PAGE 997>>>

ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 5D
TRENCH INTEGRITY INSPECTION REPORT OF THE MAGELLAN
LONGHORN PIPELINE FROM MILE POST 169.88 TO 173.38

<<<PAGE 998>>>

TRENCH INTEGRITY INSPECTION REPORT
OF THE
MAGELLAN LONGHORN PIPELINE:
EDWARDS AQUIFER RECHARGE ZONE (EARZ)
MILE POST 169.88 TO 173.38
Prepared for:
Zephyr Environmental Corporation
and
Magellan Midstream Partners, L.P.
November 11, 2012
LBG-Guyton Associates
1101 South Capital of Texas Highway
Suite B-220
Austin, Texas 78746

<<<PAGE 999>>>

Introduction
The Magellan Longhorn pipeline extends from El Paso, Texas through the greater Austin area and
terminates at Magellan’s East Houston facility. The pipeline is located north of and runs roughly
parallel to the IH-10 corridor (Figure 1). Magellan proposes both a reversal of the flow direction
within the existing Longhorn pipeline as well as a change of service from refined petroleum to crude
oil.
This report documents an assessment of the gunite liner in the trench and associated containment
system integrity across the Edwards Aquifer Recharge Zone (EARZ) segment of the pipeline
replacement corridor and provides a detailed report of the excavation activities for Magellan’s
records.
Inspection Sites
Magellan excavated and inspected the trench. The goal of the inspection was to determine the
current integrity of the gunite liner and other trench components to determine if the system would
continue to meet the intended design purpose – to prevent a material volume of fluid from
infiltrating into any recharge features exposed in the trench.
To accomplish this goal, two inspection sites were selected: 1) east of Mopac, and 2) west of
Escarpment Boulevard (Figure 1). The Mopac excavation and refill activities took place between
October 16 and October 26, 2012; activities at the Escarpment site occurred between October 22 and
October 26, 2012. Inspection activities at Mopac and Escarpment were conducted on October 22 and
October 24, respectively.
Excavation Methodology
Vacuum excavation was utilized in order to minimize potential impact to the existing trench
structure. The VacMasters System 4000 was used, which allows for efficient digging with air into hard
soils without harming underground utilities.
All air excavation work was performed while: 1) standing at grade on the sidewall of the trench; 2)
standing on the concrete cap in the trench; or 3) standing on fill materials in the trench at an
elevation higher than the top of pipe. Once the top of the fill material in the trench was greater than
four feet below grade, the workers were harnessed and continued to excavate from grade.
One truck was used at the Mopac site and two trucks were operated at the Escarpment site to
minimize total excavation time and the associated noise to adjacent homeowners. Fill materials were
piled adjacent to the excavation, and were ultimately used to refill the trench. Materials removed
from the trench were sorted; fines were placed separate from trench gravel/aggregate. The broken
concrete cap was placed further from the trench for eventual removal by a third-party hauler.
1

<<<PAGE 1000>>>

Photos of excavation operations are included as Appendix A.
The first step in the excavation process consisted of locating the top of the concrete cap. Five
transects perpendicular to the ROW (at each site) were vacuum-excavated until the concrete cap was
encountered. The dimensions of the transects were approximately 5’ long x 1’ wide x 2.5’ deep, and
were located about 20 feet apart (Figure 2). Silt fences were installed at both locations during
excavation of the transects.
Once the concrete cap was located in the subsurface, the excavation footprint was generally defined
by the transect locations. Each footprint was expanded slightly beyond the outermost transects to
dimensions of approximately 100’ long by 5’ wide, and the materials above the concrete cap were
subsequently removed using a backhoe.
Figure 2. Trench Transects and Excavation Footprint (not to scale)
Once the concrete cap was exposed at the Mopac excavation, the cap was initially cut with a Stihl cut-
off machine and masonry blade. The sawing approach was quickly abandoned due to slow progress
and an associated dust nuisance. Thereafter, a jackhammer was used to break through the concrete
cap, as it proved to be a much more efficient (and dustless) method. A jackhammer was used at the
Escarpment excavation to break through the entire section of concrete cap. Once the cap had been
broken up, it was removed to a separate spoil pile on the ROW. The concrete cap was removed off-
site and disposed of at 973 Materials in Del Valle, Texas.
The remainder of the trench fill material was then removed via vacuum excavation into segregated
piles on the ROW. The tank capacity of the VacMasters 4000 is less than 3 cu. yds. and approximately
60 cu. yds. of fill was removed from each excavation. The fill materials were allowed to slope from
the end of the concrete cap cut to the floor of the trench with an approximate 3:1 to 4:1 slope, which
left about 50 feet of gunite wall exposed on both sides of the trench excavation. A total of
approximately 200 linear feet of gunite wall was exposed in both trenches.
2

<<<PAGE 1001>>>

Trench Inspection
Overall, the gunite liner and trench were in excellent condition at both locations. The trench floor and
walls were dry and the various components of the trench (fill, pipe, conduit, gunite liner and cap)
appeared to be in original condition after ten years. The gunite liner was inspected at Sta. 9063+83
(Mopac) and Sta. 9114+54 (Escarpment) on October 22 and October 24, respectively. The gunite liner
was observed to be smooth and continuous, both laterally and vertically, with only a few minor
variances from the as-built condition. Photos of the trench inspection are included as Appendix B.
The minor anomalies observed during inspection of the 200 ft of trench that was uncovered for
inspection include: 1) minor divots in the poly coat sealant that occurred during fill removal, 2) peel
cracks where the poly coat spot-treatment sealant separated from the gunite liner, and 3) infrequent
penetration by small roots (two roots observed in a total 200 feet of exposed wall).
The two roots (1/4 – 1/2 in. dia.) were found during the trench inspection at the Mopac site. One root
was located above the concrete cap; one root was located below the cap. No radial cracking of gunite
around the roots was observed. Hair-like roots were also present in the poly sealant material but
were not observed to significantly penetrate the gunite or compromise the integrity of the gunite
liner. The peel cracks are places where the poly sealant had separated from the gunite, however the
gunite was observed to be completely intact behind the peel and crack features. The divots were
small (<4 in dia.) areas where the gunite separated and fell from the wall only after the trench fill was
removed. There is no evidence that the poly seal was not intact prior to excavation.
Overall, the gunite and trench were in excellent condition at both locations. The trench floor and
walls were dry and the various components of the trench (fill, pipe, conduit, gunite liner and cap)
appeared to be in pristine condition after ten years. The poly coat spot-treatment sealant was
observed to have a dark color that during initial inspection appeared to be moist sections of the walls.
However, upon further inspection, it was determined that the discolored swatches on the gunite wall
were associated with the poly sealant and not associated with moisture. The dark poly patches at the
Mopac site had numerous hair-like roots growing within the poly seal only. The roots did not expand
beyond the poly patches. The poly coat spot-treatment sealant was the only material observed that
exhibited any signs of deterioration (peel cracks and divots) which we suspect may have occurred
during excavation activities.
Photos of the trench inspection are included as Appendix B.
Trench Reconstruction
The features in the trench noted above (divots, cracks, peels and roots) were repaired with materials
recommended by the original gunite contractor: Shep-Patch Plus powder and acrylic polymer. The
tree root was clipped flush with the wall surface and then patched. It should be noted that the tree
root itself was observed to essentially fill the penetration hole that it had created in the gunite. Once
3

<<<PAGE 1002>>>

the gunite patches had dried, the fill gravel was put back into the trench to the level of the original
concrete cap. Since the red dye in the original cap had stained the trench wall, the desired depth of
the fill material was easy to determine.
Approximately six cu. yd. of concrete was poured to cap each excavation. The red dye that was added
to the concrete, CSI #120 Conduit Red, is a synthetic iron oxide (Fe203) that is lightfast, chemical and
weather resistant.
After the concrete cap had set, the original fill and native soils that were excavated from above the
concrete cap were put back over the new cap. A trench crown was also constructed parallel to the
pipe to allow for settling of the soils and to help divert runoff away from the excavation.
Photos of the trench re-construction are included as Appendix C.
Conclusions
Overall, the gunite and trench were in excellent condition at both locations. The trench floor and
walls were dry and the various components of the trench (fill, pipe, conduit, gunite liner and cap)
appeared to be in original condition after ten years. The poly coat spot-treatment sealant was the
only material observed that exhibited any signs of deterioration (peel cracks and divots) which we
suspect may have occurred during excavation activities.
The minor anomalies observed during inspection include: 1) minor divots in the poly coat sealant that
occurred with fill removal, 2) peel cracks, where the poly coat spot-treatment separated from the
gunite liner, and 3) infrequent penetration of small roots (two roots between 1/4 and 1/2 in. dia.
observed in a total 200 feet of exposed wall).
The minor anomalies were repaired prior to refill activities and are not considered significant enough
to compromise the trench integrity or the original design goals of the liner. We therefore conclude
that the pipeline trench design and sealing protocol used within the Edwards Aquifer Recharge Zone
(EARZ) will continue to prevent a material volume of fluid from infiltrating into any recharge feature
exposed within the trench during a potential spill event. The trench, road bore pits, diversion berms
and trench sealing materials are performing well to collectively capture and contain any potential
product release. The secondary containment system is functioning as designed and constructed in
order to prevent significant product migration to either a groundwater recharge feature or surface
water feature that might directly or indirectly recharge the Edwards aquifer.
4

<<<PAGE 1003>>>

EXPLANATION
Longhorn Pipeline ROW
Edwards Aquifer Zones
Edwards Aquifer Contributing Zone
Edwards Aquifer Contributing Zone within the Transition Zone
Edwards Aquifer Transition Zone LBG-GUYTON ASSOCIATES
*Service Layer Credits: Image courtesy of USGS © 2012 Microsoft
Corporation ImagePatch.com © 2010 NAVTEQ © AND +N
0 2,000
1,000
Feet
Figure 1
Trench Excavation Location Map
Edwards Aquifer Recharge Zone (EARZ)
Austin, Texas

<<<PAGE 1004>>>

Appendix A
Trench Excavation Photos

<<<PAGE 1005>>>

Silt Fence Installation (Mopac)
Vacuum Excavation Truck (Mopac)
A-1

<<<PAGE 1006>>>

Trench Transect Cut to Tag Concrete Cap (Mopac)
Trench Transect Cut, note Gunite Wall (Mopac)
A-2

<<<PAGE 1007>>>

Removing Fill above Concrete Cap (Mopac)
Concrete Cap Surface (Mopac)
A-3

<<<PAGE 1008>>>

Saw Cut in Concrete Cap (Mopac)
Breaking Concrete Cap (Mopac)
A-4

<<<PAGE 1009>>>

Broken Concrete Cap (Mopac)
Cement Cap, note Fiberglass (Mopac)
A-5

<<<PAGE 1010>>>

Removing Trench Fill (Mopac)
Pipe, Product Sensor-Cable Conduit and Electrical Conduit (Mopac)
A-6

<<<PAGE 1011>>>

Fill removed, note exposed Cove and original Concrete Cap Contact (Escarpment)
Trench Ready for Inspection (Escarpment)
A-7

<<<PAGE 1012>>>

Appendix B
Trench Inspection Photos

<<<PAGE 1013>>>

Escarpment Excavation – South Wall, looking West
Escarpment Excavation – South Wall, looking East
B-1

<<<PAGE 1014>>>

Escarpment Excavation – North Wall, looking West
Escarpment Excavation – North Wall, looking East
B-2

<<<PAGE 1015>>>

Divots in Gunite Wall – Mopac Excavation, South Wall
Divots in Gunite Wall – Mopac Excavation, South Wall
B-3

<<<PAGE 1016>>>

Peel (Poly Coat separated from Gunite) – Mopac Excavation, North Wall
Peel – Mopac Excavation, North Wall
B-4

<<<PAGE 1017>>>

Vertical Cracks in Poly Coat – Mopac Excavation, South Wall
Vertical Cracks in Poly Coat – Mopac Excavation, South Wall
B-5

<<<PAGE 1018>>>

Root in Gunite (<1/2 in dia) – Mopac Excavation, North Wall
Hair-like Roots in Poly Coat – Mopac Excavation, South Wall
B-6

<<<PAGE 1019>>>

Appendix C
Trench Refill Photos

<<<PAGE 1020>>>

Divot Patches - Mopac Excavation – South Wall
Gunite Patch Materials
C-1

<<<PAGE 1021>>>

New Concrete Cap - Mopac Excavation, looking East
Pouring New Cap - Escarpment Excavation, looking East
C-2

<<<PAGE 1022>>>

Red Dye Material used in New Concrete Cap
Fill to Grade with Crown – Mopac Excavation, looking WestC-3

<<<PAGE 1023>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
6.0 PIPELINE RISK ASSESSMENT
6.1 INTRODUCTION
This chapter provides a detailed assessment of risks associated with the operation of the
System under the proposed reversal and change of product. This risk assessment addresses
new and changing threats that may result from the reversal and change of product of the system
and measures the change in risk from current operations of the existing assets in refined
product service to operations under the Proposed Project.
The risk assessment concludes that the risk associated with the Proposed Project will be lower
than those experienced under current operations as a result of the mitigation measures outlined
in Chapter 9. The Proposed Project introduces different risks to the System, however; additional
proposed mitigation measures are seen to offset all potential probability of failure (PoF)
increases.
The 1999 EA used an indexing risk assessment model (relative risk model) as a basis for
developing a risk profile. The relative risk model is still widely used in the industry today;
however this risk assessment utilized a quantitative model which provides a greater degree of
granularity for assessing risk along the system. The proprietary Quantitative Risk Assessment
(QRA) model was developed and used by Kent Muhlbauer, P.E. in assessing the risks for the
Proposed Project. The QRA is the most rigorous and complex risk assessment model available
and is used in the chemical, nuclear, and aerospace industries and more limited in the
petrochemical industry (Muhlbauer, 2004). The QRA is used in the pipeline industry as a robust
alternative to the relative risk assessments in part because of its data intensive requirements.
The QRA provides an absolute risk assessment of all possible failure events. As further
described by Muhlbauer, it is a “rigorous and mathematical and statistical technique that relies
heavily on historical failure data and event-tree/fault –tree analyses. Initiating events such as
equipment failure and safety system malfunction are flowcharted forward to all possible
concluding events, with probabilities being assigned to each branch along the way.”
(Muhlbauer,2004).
To assist the reader, the Risk Assessment methodology, definitions, and generally the more
technical aspects, are included in Appendix 6A with the more discrete processes and
procedures to manage these risks outlined in the main body of Chapter 6 below.
6.2 THREATS
This Section focuses on the change in threats that will be introduced by (i) the change in
product service from refined products to Permian Basin crude oil, (ii) the reversal of flow, and
(iii) new facilities. The changing threats associated with the change in product service include
the following:
6-1

<<<PAGE 1024>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Internal Corrosion
• Hydrogen Blistering
The changing threats associated with the reversal of flow from Crane to East Houston include
the following:
• Surge Pressure and Hydraulic Profile
• Cracking
• Stress Corrosion Cracking
The changing threats associated with new facilities include the following:
• Incorrect Operations
• Security Threats
The following threats will not be affected to a relevant extent by the Proposed Project. These
threats will continue to be managed by existing processes and procedures. Some
enhancements to data management and risk assessment processes are described in this
section.
• Atmospheric Corrosion
• External Corrosion
• Third Party Damage
• External Forces
6.2.1.1 Internal Corrosion
The System is currently in refined product service, however; historically the pipeline was in
crude oil service for a period of about 45 years. Under the Proposed Project, internal corrosion
potential is increased compared to current operations, due to the re-introduction of sweet and
sour crude to the System. Representative crude samples of the two types of crude oil that will
be transported (i.e. West Test Intermediate and West Texas Sour) were analyzed by an
independent laboratory. West Test Intermediate (WTI) indicated no measurable H2S (less than 1
PPM). West Texas Sour (WTS) indicated H2S concentrations of 10 PPM (See Appendix 6B for
further information). It should be recognized that crude characteristics vary across the Permian
Basin but these samples are considered representative. The increased potential is primarily due
to the presence of constituents in the crude oil, primarily H2S, which in the presence of water
and oxygen can cause internal corrosion.
As discussed below, internal corrosion can be reduced through mitigation by eliminating air and
the use of an inhibitor. EnhanceCo cites prior work from Dr. Sheldon Evans that corrosion can
be reduced through mitigation by eliminating air and the use of an inhibitor (Appendix 6C).
Additional corrosion rate reductions can be achieved by removing water and solids from the line
with the use of an aggressive cleaning pig program. Water can settle in low spots in the pipeline
6-2

<<<PAGE 1025>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
and solids can promote entrapment of water and/or microbes, both of which can be a source of
corrosion.
Regular running of cleaning tools is designed to eliminate water and debris that may settle in
low areas during periods of time when the pipeline is not flowing. Water and debris brought into
the receiving trap by the cleaning tools will be tested to determine its potential to cause internal
corrosion. Water will be tested per American Petroleum Institute RP-45. Monitoring will include
select coupons located on the bottom of the pipe in low spots, where water and solids are likely
to accumulate. These locations will be monitored for water and corrosion products, and coupons
will be examined for the presence of pitting corrosion and pitting corrosion rates.
A Drag Reducing Agent (DRA) will be injected into the pipeline to minimize friction loss on the
pipe walls and thus minimize the need for additional pumping stations or higher operating
pressures at select locations. DRA will be injected in low concentrations in the range of 85 parts
per million (0.0085%). A safety data sheet for LiquidPowerTM Flow Improver, the DRA chosen
for the crude oil application, is included in Appendix 6D.
The DRA, LiquidPowerTM Flow Improver, is shown through testing to not increase the corrosivity
of the crude oil. A series of tests were conducted to consider any potential effect of the DRA on
the corrosivity of crude oil or crude oil/salt water mixtures. These tests were corrosion wheel
tests, a widely used oil industry adaptation of ASTM standards (G-31 and G-46), based on
weight loss of metal coupons placed in the test environment in a sealed vessel and rotated on a
wheel or axle at constant temperature. The coupons utilized in the tests were made of cold-
rolled mild steel stock. Corrosion rates were measured under two atmospheres for the crude oil:
inert with nitrogen and oxidized with air. For the crude oil/salt water tests, the mixtures were
sparged and blanketed with CO2. All tests were conducted at 70°F, and utilized Alaska North
Slope (ANS) crude oil. ANS is similar in properties to the WTS crude. Half of the crude oil
samples were treated with 150 ppm DRA to compare with the untreated crude oil. All tests were
conducted in triplicate.
The results of the corrosion tests are shown in the Table below. Any pitting is reflected in the
table as a pitting index which varies from one to three. An index of 1 means no observable
pitting; an index of 3 means lots of pitting. The test results indicate that addition of DRA to a
crude oil system does not increase the corrosion rate of the system.
Corrosion Rate
Average
(MPY) change with
Crude Oil Corrosion Wheel
Vapor
Corrosion
Pit
150ppm DRA
Test Results Liquid
Space
Rate (MPY)
Index
added*
Crude oil Nitrogen 0.8 1 No change
Crude oil Air 0.7 1 Decrease by 0.1
50% crude oil/50% saltwater CO2 4.6 3 No change
*Test conducted with LiquidPowerTM Flow Improver and ANS crude oil
Detailed protocols governing the use of corrosion inhibitor injection, frequency of maintenance
pigging, coupon installations, monitoring of coupons, and sampling are discussed in Section
6-3

<<<PAGE 1026>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
9.3.2.2. Magellan currently operates an interstate pipeline transporting sour crude and mitigation
measures have been shown to be effective in controlling internal corrosion.
The continued use of metal loss ILI tools will enable Magellan to monitor any localized corrosion
metal loss along the entire length of the pipeline. Mitigation discussed in Chapter 9 includes
periodic re-assessments of the threat of external corrosion due to potential damages caused by
internal corrosion. Table 5.3.1-1 details the currently established integrity assessment intervals
per the Operational Reliability Assessment (ORA) Process to evaluate the internal corrosion
threat. Corrosion rates established through the ORA are completed by third party consultant
approved by PHMSA. These corrosion rates are utilized as part of the Probability of
Exceedance (POE) analysis process. This process evaluates each unrepaired feature to ensure
a low probability of a feature growing to a level that would exceed repair criteria. All corrosion
features identified by the ILI tools are repaired to a level to ensure that remaining strength of
pipe exceeds 1.39 times the maximum pressure allowed at the location of the feature. This
maximum pressure determined includes any potential surge pressures as evidenced by pipeline
surge analysis.
Mitigation measures that target general internal corrosion are also effective in controling threats
associated with internal corrosion selective to the longitudinal seam weld. Magellan’s processes
and procedures contained within the SIP Integrity Management Program, SIP-ADM-7.06
(Appendix 6E), provide for determinations of re-assessment intervals to evaluate the integrity of
longitudinal seam welds. Future longitudinal seam weld inspections are designed to detect any
indications of corrosion along the longitudinal seam, which could be selective seam weld
corrosion.
Additionally, Magellan’s processes for evaluation of future metal loss features identified by MFL
or UT tools are integrated with seam location information gathered from the TFI tools. This
information is utilized to evaluate any metal loss of or along the longitudinal seam. This
evaluation will determine if high corrosion rates are occurring at selected areas which may
indicate selective seam corrosion is occurring. Through the ORA process, any information
indicating areas of high corrosion rates would be investigated. Information gathered from the
investigation of features would be used to establish appropriate re-inspection intervals via the
POE and ORA processes.
The risk assessment model completed for this FEA established estimates of risk along the
entire length of the pipeline associated with internal corrosion. The estimates are represented
as a PoF. For this FEA, PoF has been quantified for all portions of the System. Estimates are
based on integration of all available location-specific information, producing a PoF profile along
the pipeline route. This profile produced over 32,000 segments (average segment length is
approximately 100 ft.), demonstrating a high level of resolution.
Based on the proposed mitigation for internal corrosion, the PoF associated with internal
corrosion for the Proposed Project is less than the existing PoF for current operations in refined
product service.
6-4

<<<PAGE 1027>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
6.2.1.2 Hydrogen Blistering
National Association of Corrosion Engineers (NACE) discusses failure causes associated with
H2S (NACE International, 2003). Hydrogen blistering is the major threat of failure resulting from
H2S in pipelines with hydrogen induced cracking (HIC) being the failure mechanism once
blisters have formed. Hydrogen from anaerobic corrosion is an important source of absorbed
hydrogen for steel. The lattice hydrogen concentration is a function of the severity of the
corrosive environment and generally increases with the presence of H2S.
Based upon literature reviews, the failure mechanisms associated with blistering and H2S
follows this process as summarized below (King, 2009). The time to failure is difficult to predict
because the process involves many steps as described below.
1. Hydrogen must be absorbed by the steel. Although determining the absorption rate is
difficult, it appears related to the concentration of H2S, H2O and the pH of the fluid.
2. Hydrogen (H+) must be diffused and recombined into molecular hydrogen (H2) at a
lamination site. The chemical composition of the site would affect the rate at which
atomic hydrogen combines and forms H2. It is thought that certain elements in the matrix
such as sulfur and manganese increase the absorption or conversion of H+ to H2.
3. An H2 buildup would increase the pressure at the lamination until the lamination breaks,
forming a hydrogen gas filled cavity or blister.
4. A blister would continue to grow and create a deformation toward the ID of the pipe and
a stress concentration at the tips or in the center of the blister.
5. The stress concentration could eventually be large enough to cause crack initiation.
6. HIC cracks can grow and connect along the ID of the pipeline, causing a pressure
connection between the lamination and the inside of the pipe.
7. Once the crack becomes large enough, the inner ligament can no longer carry hoop
stress resulting in the outer ligament carrying all the stress. This is approximately double
the normal load on the pipe steel since laminations tend to form at the mid-wall position
in pipe steel.
8. The outer ligament may fail from crack initiation created during the link-up of individual
laminations during blister formation. The crack may be influenced by HIC causing a
through-wall crack to form resulting in a release of product.
Prior history on the original pipeline in crude oil service shows this to be a slow process. There
were no in-service failures caused by hydrogen blisters in the 23 failures reported during the 29
year interval from 1966-1995 (Johnson and Kiefner, 1999) where failure records exist. In 1995,
45 years after the pipeline was built, there were two documented hydrotest failures from blisters
at Sta. No. 16518+08 (MP 312.8) and Sta. No. 16661+01 (MP 315.5) (Kiefner and Johnson,
2004).
In this risk assessment, laminations are considered to be potential crack initiation points. They
are modeled as having no immediate reduction on current strength but rather serve as locations
of future crack initiation if the lamination becomes a blister. With the re-introduction of a source
6-5

<<<PAGE 1028>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
of hydrogen, blister and crack formation is again a potential integrity threat. To model this in a
risk assessment, lamination locations, as detected by in-line inspection (ILI), are treated as
potential blister locations. These locations are modeled to be crack initiators and are assessed
in Section 6.2.1.4, Cracking/Fatigue Monitoring.
Monitoring of corrosion on the inside of the pipe with coupons and ILI and regular pipeline
cleaning with pigs can help monitor and minimize the hydrogen generating environment.
After running a UT wall measurement ILI tool in 2009 and 2010, Magellan has documentation
on the locations of the laminations that existed in the original pipeline. In the formation of a
blister, the outside ligament is held taught and the inside ligament is the one capable of
deforming inward thus allowing for detection by a deformation ILI. LMC 12A requires
deformation inspection every three years. The 45-year life of the blister that failed during the
hydrostatic test is 15 times this required inspection interval and ILI should be capable of
monitoring for blister formation and allowing for remediation before any HIC cracking penetrates
both the internal and external ligament.
The ILI inspections combined with a preventative program to monitor and keep water out of the
pipeline from crude production can keep the potential of hydrogen blister failures to a very low
likelihood. As part of the mitigation discussed in Section 9.3.2.3, Magellan will maintain
sufficiently low probabilities of blister formation via existing inspections and analyses as per SIP-
ADM-7.03, Integrity Testing and Rehabilitation (Appendix 6E). Ongoing risk analysis will identify
if any additional mitigation measures, such as more frequent integrity testing, is required.
As discussed above, the risk assessment for hydrogen blistering has been included as part of
the Cracking/Fatigue Monitoring assessment (Section 6.2.1.4). PoF estimates derived from risk
assessment modeling indicate that risk levels can be managed to levels at or below those
associated with current operations when mitigation is applied.
6.2.1.3 Surge and Hydraulic Profile
As a result of the flow reversal, change in product, and change in flow rates, the hydraulic
profiles will change. The pipe on the east side of the pump stations are presently the suction
side and normally experience lower pressure. Under the Proposed Project, this suction side will
become the discharge side (downstream side) and experience the higher pressures produced
by the pumping stations. It is likely that some pipe segments have not experienced the elevated
operating pressures that will be produced in the reversed mode. Furthermore, there will be
additional pumping stations installed as part of Phase 2 and these new pump stations will again
produce pressures in localized areas that are likely higher than the historical pressure of the
past 10 years.
As a result of the changing hydraulic profile under the Proposed Project, the potential surge
pressures along the pipeline route will change. As detailed in Section 9.3.2.4, a surge analysis
has been conducted to ensure that mitigation measures employed as a part of the Proposed
6-6

<<<PAGE 1029>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Project ensure that safe operating pressure levels are not exceeded. Mitigation
recommendations submitted to PHMSA for approval (under 49 CFR Part 195) consist of a
combination of relief systems and high pressure control switches to limit surge pressure to less
than 100% MOP in Tier 2 and 3 areas. Surge pressures are limited to 110% in remaining areas.
Appendix 6F contains an Operating Pressure Summary Table that contains the maximum surge
pressures for each pump station segment as compared to the MOP of the pipeline in that
segment. Appendix 6F contains a table of overpressure protective devices utilized to prevent
and/or mitigate surge.
Appendix 6A details the PoF estimates for surge and overpressure potentials. The risk
assessment model established PoF estimates at all points along the pipeline route. Algorithms
modeling the surge threat are shown in Appendix 6A. PoF estimates derived from risk
assessment modeling indicate that risk levels can be managed to levels at or below those
associated with current operations when mitigation as detailed in Section 9.2.3.4 is applied. This
mitigation includes overpressure protective devices to maintain operating pressures at safe
levels.
6.2.1.4 Cracking/ Fatigue Monitoring
Pressure-cycle-induced fatigue-crack-growth of defects will continue to be a potential threat to
the integrity of the Longhorn Pipeline. Manufacturing defects in or immediately adjacent to the
longitudinal ERW or EFW seams of the pre-1970 line-pipe material contained in the existing
pipeline are considered to be the primary concern. The concern is that a defect that initially may
be too small to fail at the operating pressure will grow through fatigue cracking driven by
pressure cycling and become large enough to cause a failure if exposed to sufficient numbers of
large pressure fluctuations. The ORA Process Manual requires monitoring of pressure cycles
during the operation of the pipeline, calculating the worst-case crack growth in response to the
pressure cycles, and reassessing the integrity of the pipeline at appropriate intervals to find and
eliminate growing cracks before they become large enough to cause a failure of the pipeline.
Table 5.3.1-3 shows calculations from the 2010 ORA which identified the shortest time to failure
of 92.1 years and a reassessment interval of 41.5 years. There are only two other sections
which show reassessment intervals less than 100 years. This analysis shows that the pressure
cycles at Cedar Valley and Kimble County produce the shortest fatigue lives and the shortest
reassessment interval for the original pipe.
The locations with the greatest threat for pressure-cycle-induced fatigue cracking will change
because the location of the most aggressive pressure cycles will change. A preliminary
assessment using the new flow direction for the existing pre-1970 pipeline from Crane to
Galena Park shows this threat can be managed with the existing procedures as part of the
ORA. The effects of pressure cycles on the pipe that is currently on the suction side of each
station were examined to determine the effect of reversed flow on the pipeline. The shortest
time to failure for any of the pre-1970 existing pipe is 83.9 years from the previous TFI tool run
completed in 2009. This occurs at the 1950 EFW pipe at Satsuma using Cedar Valley cycle
data. The lessening aggressiveness of the cycles as distance increases from the station
discharge was not taken into account (the 0.281-inch pipe is over 10 miles from the station) so
6-7

<<<PAGE 1030>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
this estimate is more conservative than if a pressure drop between the pump and the pipe had
been taken into account.
Using the factor of safety of 2.22 (45% of the fatigue life as defined within Section 4 of the LMP),
the reassessment interval would be in 37.8 years. Although shorter in time, this is similar to the
reassessment intervals calculated for westerly flow. This verifies there is no immediate threat
from pressure-cycle-induced fatigue cracking and will allow a year of actual data to be collected
and analyzed to obtain a more accurate estimate of remaining life from fatigue growth once the
pipeline flow has been reversed.
In order to investigate worst-case scenarios, doubling and tripling of cycles was investigated.
Doubling the cycles will cut the fatigue life in half resulting in a fatigue life of 42.0 years and a
reassessment interval of 18.9 years. Similarly, tripling the cycles will reduce the fatigue life by
two-thirds resulting in a fatigue life of 28.0 years and a reassessment interval of 12.6 years.
Even these worst case scenarios will allow the pipeline to operate for a year to obtain new
operating data and calculate estimates of time to failure and reassessment intervals. Within one
year from start-up of the pipeline in crude oil service in the reversed direction, third-party ORA
contractor will conduct a pressure cycle analysis and determine reassessment intervals for
cracks. This calculation will also be completed as part of the annual ORA each subsequent
year.
Through risk assessment modeling, a crack-related failure potential is estimated. A discussion
of factors considered and algorithms modeling this threat are contained in Appendix 6A. PoF
estimates derived from risk assessment modeling indicate that risk levels can be managed to
levels at or below those associated with current operations when mitigation is applied. This
mitigation as detailed in Section 9.3.2.5 includes continued active monitoring of pressure cycles
and subsequent integrity testing through ILI and rehabilitation to mitigate cracking.
6.2.1.5 Stress Corrosion Cracking (SCC)
Modification to pressure cycle frequencies and intensities affects the threat of SCC. It is prudent
to retain SCC as a possible threat.
In the same manner through risk assessment modeling, a SCC crack-related failure potential is
estimated. Discussion of SCC risk assessment modeling is included in Appendix 6A. PoF
estimates derived from risk assessment modeling indicate that risk levels of SCC can be
managed to levels at or below those associated with current operations when mitigation is
applied. This mitigation includes conducting Non-Destructive Examination (NDE) to examine for
the presence of SCC through magnetic particle inspections and active management of pressure
cycles.
6.2.1.6 Incorrect Operations
The Proposed Project will change the potential for failure due to human error with the
introduction of new facilities. These new facilities include new aboveground valves sites
6-8

<<<PAGE 1031>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
replacing buried check valves as well as new pump stations, new equipment and more complex
facilities added as part of the Proposed Project. Facilities tend to be the locations of most
incorrect operations incidents or initiators of incidents elsewhere along the pipeline. Facilities
are defined as above ground or chambered portions of the System that are comprised of
components other than mainline pipe. Pump stations, tank farms, metering stations, valve sites
and others are considered to be facilities. Typical scenarios that might lead to a breach of
integrity or spill that are modeled as incorrect operations include;
• Overpressure due to pumping against a closed valve or other blockage
• Blocked-in, liquid-full component over pressured by heat source such as sunlight
• Overpressure due to incorrect setting of safety equipment
• Overfilling of tank or sump due to improper execution of procedure and/or failure of
safety equipment
Through risk assessment modeling a failure potential from incorrect operations is estimated.
Discussion of incorrect operations modeling is included in Appendix 6A. PoF estimates derived
from risk assessment modeling indicate that risk levels associated with incorrect operations can
be managed to levels at or below those associated with current operations when mitigation is
applied. This mitigation as discussed in section 9.3.2.7 and section 9.3.3.2 of Chapter 9 will
ensure a high reliability of redundant controls and safety systems typical of pipeline operations.
Formal analyses such as HAZOP and subsequent Layer of Protection Analysis (LOPA) will be
conducted. Protective devices and engineering controls specified by this analysis will be applied
prior to start-up. Ongoing risk assessments further described in Chapter 9 will measure and
maintain PoF associated with incorrect operations below specified levels. Successful application
of these risk assessments and subsequent mitigations ensures that the risks associated with
incorrect operations are reduced by the Proposed Project to levels below current operations.
6.2.1.7 Security
The addition of new facilities brings about additional security risks due to more exposed
equipment that is in view of the public that could result in an increased risk of terrorism,
vandalism, tampering, or theft. Magellan’s existing procedures include provisions to address
appropriate security measures as defined in SIP-ADM-8.01 (Appendix 6E). This initiative
provides a framework that complies with the security regulations to protect the assets, the
employees, the environment, the stakeholders, and the community from security threats.
In general, the Longhorn Pipeline is not thought to be more vulnerable than other pipeline
systems. Standard or above-average security measures will be in place in accordance with the
LMP and SIP which would generally include fences, locks, increased patrols, and surveillance
cameras.
The FBI has published a report summarizing 318 terrorism events between 1980 and 2005
(USDOJ/FBI, 2012). The terrorism events include all successful and foiled plots. Only 1 foiled
plot related to potential pipeline attack was recorded. In 2005, a terrorist plan to carry out violent
6-9

<<<PAGE 1032>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
attacks against pipeline systems and energy facilities in Pocatello, Idaho was prevented
(Halcrow, 2011). This system has not experienced terrorism or sabotage.
Through risk assessment modeling, a failure potential from security threats is estimated.
Discussion of incorrect operations modeling is included in Appendix 6A. PoF estimates derived
from risk assessment modeling indicate that risk levels associated with security threats can be
managed to levels at or below those associated with current operations when mitigation is
applied. This mitigation as discussed in section 9.3.2.8 includes security measures such as
security fencing, monitoring cameras, physical barriers, and locks to adequately limit access
and mitigate security threats. Successful application of these mitigations ensures that the risks
associated with security threats are reduced by the Proposed Project to levels below current
operations.
6.2.1.8 Atmospheric Corrosion
At locations where below ground pipelines are brought above ground such as at existing check
valve sites or new facilities, the threat of atmospheric corrosion will change. These locations
represent an insignificant percentage of the total pipeline mileage affected by the Proposed
Project. It is plausible to predict lower PoF when pipe segments are re-located above ground. In
most scenarios, buried metal corrosion rates exceed atmospheric corrosion rates. In the
majority of scenarios, with proper installation and maintenance, the corrosion potential for above
ground segments should be less than for buried segments. Magellan’s existing procedures
contained in 7.04-ADM-002 (Appendix 6E) establish standardized methods for monitoring,
inspecting, and reporting atmospheric corrosion conditions on aboveground facilities. Surveys
are conducted annually at above ground piping and facilities. Any exposed pipes are visually
inspected when the pipeline is exposed for any reason. Design Standards housed within SIP-
ADM-4.01 (Appendix 6E) provide specifications for coatings on new installations of above
grounding piping, supports, and transition areas to protect from atmospheric corrosion. The
Coating Selection Application and Maintenance Procedure, 7.04-ADM-016 (Appendix 6E),
provides a standardized reference for the selection, application, and maintenance of coatings
used to prevent corrosion.
6.2.1.9 External Corrosion
The Proposed Project is not seen to change the potential for failure related to external corrosion
including special forms of external corrosion such as: microbiological influenced corrosion
(MIC), AC-induced corrosion, stray current, and selective seam corrosion.
Factors affecting external corrosion include:
• Soil conditions
• Pipe coating
• Cathodic protection system effectiveness
• Environmental conditions
• Metallurgical properties of the pipe
6-10

<<<PAGE 1033>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
These factors affecting external corrosion are not anticipated to change. The fluid (or product)
inside the pipeline has no effect on the outside of the pipeline or how the outside of the pipeline
interacts or is affected by the environment around the pipeline. Therefore these threats and how
they are managed and monitored does not need to change because of the change in product or
flow direction. Threats from these causes are monitored by the ORA and if an increase in risk
occurs it can be accounted for in the ORA process.
6.2.1.9.1 Pipe Coatings
Existing corrosion control and integrity management procedures contained in the SIP are
designed to mitigate the effects of deterioration of pipe coatings. Evidence of the current coating
condition is found through visual inspection reports, pipe-to-soil potential surveys, and detection
of previous corrosion damages through ILI.
Design Standards housed within SIP-ADM-4.01 (Appendix 6E) provide specifications for
coatings on new installations of buried piping, areas to protect from external corrosion. The
Coating Selection Application and Maintenance Procedure, 7.04-ADM-016 (Appendix 6E),
provides a standardized reference for the selection, application, and maintenance of coatings
used to prevent corrosion.
Mitigation discussed in Chapter 9 includes periodic re-assessments of the threat of external
corrosion due to potential damages caused by pipe coating failure. Corrosion rates are
established through the ORA completed by a third party consultant approved by PHMSA. These
corrosion rates are utilized as part of the POE analysis process. This process evaluates each
unrepaired feature to ensure a low probability of a feature growing to a level that would exceed
repair criteria. All corrosion features identified by the ILI tools are repaired to a level to ensure
that remaining strength of pipe exceeds 1.39 times the maximum pressure allowed at the
location of the feature. This maximum pressure determined includes any potential surge
pressures as evidenced by pipeline surge analysis.
6.2.1.9.2 Cathodic Protection and CP Verifications
The Corrosion Control Program, 7.04-ADM-001 (Appendix 6E), provides detailed procedures
and processes designed to maintain cathodic protection (CP) systems to prevent external
corrosion of buried pipelines. These procedures detail the corrosion control survey frequencies
specific to the Longhorn Pipeline and specified in the LMP:
• Pipe to Soil Potential Surveys – Conducted annually (not to exceed 15 months) in Tier 1
areas and semi-annually (not to exceed 7 ½ months) in Tier 2 and Tier 3 areas.
• Close Interval Pipe to Soil Potential Surveys are conducted annually in Tier 3 areas.
• Foreign Line Crossing Surveys – Critical Bonds are inspected six times each calendar
year with intervals between inspections not to exceed 2 ½ months.
• Rectifier Inspection Surveys are conducted monthly (not to exceed 45 days) at each
cathodic protection rectifier. This is double the frequency required by 49 CFR Part 195.
6-11

<<<PAGE 1034>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Corrective actions for noted pipe to soil deficiencies are determined and completed as soon as
practical depending on the severity of the situation with respect to location of the pipeline and
the potential for damage. All deficiencies are resolved with one year of discovery, except
deficiencies of such a nature that present a more urgent threat to pipeline integrity, in which
case corrections are completed immediately.
Corrective action for noted deficiencies in rectifier components are determined and completed
as soon as practical, depending on the severity of the situation with respect to location of the
pipeline and the potential for damage. All rectifier component deficiencies are resolved within
one (1) month of discovery except deficiencies of such nature they present a more urgent threat
to pipeline integrity, in which case corrections are made immediately.
Rectifier outages are typically triggered by a natural event, such as a thunderstorm. A pattern or
trend of rectifier outages triggers a detailed analysis by NACE certified corrosion control
personnel. This inspection includes the use of a multimeter and/or various other electrical
testing equipment as well as visual inspection of the rectifier components. System
enhancements identified during this analysis to mitigate against any such pattern or trend are
implemented as soon as practical, not to exceed six months.
6.2.1.9.3 IR Drop (CP Voltage Measurement Criteria)
The adjustment from readings taken to reading of interest is often termed “IR compensation,”
with the implication that "IR" or "IR drop" is the part of the voltage reading that should not be
considered in assessing the adequacy of CP. The surface readings can be taken with the
impressed electric current supply to the System turned either “on” or “instant off.” The IR drop
subtracts the voltage drop through the soil from the reading to yield the “true value” of the pipe-
to-reference electrode potential. The -0.85 volt is usually considered a conservative criterion
since a safety margin is already included for most soil conditions.
Magellan’s Corrosion Control Program, 7.04-ADM-001 (Appendix 6E) of the SIP contains
procedures for addressing CP criteria including consideration for IR drop. The Corrosion Control
Program in part provides that IR drop is considered by taking potential readings directly over or
as near as practical to the structure surface. The effect on the potential measuring circuit is kept
to a minimum by using a high resistance volt meter and being mindful of lead lengths and the
condition, contact to structure and contact to electrolyte.
Furthermore, CP levels are to be evaluated utilizing CP criteria within procedure 7.04-ADM-006
(Appendix 6E) that defines methods for considering the effects of IR drop including the use of:
• High resistance voltmeter
• Historical operating information
• Reference cell placement
• Calculation
• Current interruption
6-12

<<<PAGE 1035>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Buried coupons
In addition to deficient CP voltage, excess voltage can also be a concern. In order to avoid
excess voltage, Magellan uses -1.2 volts pipe to soil potential as a limit on pipe-to-soil voltage
as an informal guideline. Episodes of higher voltage are individually evaluated and mitigated.
6.2.1.9.4 Casings
The Proposed Project is not seen to change the external corrosion threat associated with
casings. The integrity of pipe in casings in managed through procedures contained in the
Corrosion Control Program, 7.04-ADM-001 (Appendix 6E).
During each CP survey, readings are taken at each cased crossing to detect any location where
the carrier pipe may be shorted to the casing pipe. If the casing potential is within 100 millivolts
of the pipeline potential, the casing is investigated to determine whether a metallic short to the
carrier pipe is present. If a short is verified, a plan of action shall be developed within three
months from the time of discovery. The practicality of clearing the short will be considered
before any other measures are used. Action shall be taken to clear the short (a) in Tier 1 areas
within six months of development of the action plan; and (b) in Tier 2 and Tier 3 areas within
three months of development of the action plan.
In the interim, from the time a short is verified and action taken to clear the short, the location
will be inspected for corrosion or the casing/pipe interstitial space may be filled with a high
dielectric corrosion inhibiting material. During any interval that a casing has been determined to
be shorted, the casing/pipe interstitial space will be monitored. Tier 1 areas will be monitored
twice per year at intervals not to exceed 7 ½ months. Tier 2 and 3 areas will be monitored
monthly at intervals not to exceed six weeks.
The integrity of the carrier pipe inside casings in further verified through ILI. Corrosion rates are
established through the ORA completed by third party consultant approved by PHMSA. These
corrosion rates are utilized as part of the POE analysis process. This process evaluates each
unrepaired feature to ensure a low probability of a feature growing to a level that would exceed
repair criteria. All corrosion features identified by the ILI tools are repaired to a level to ensure
that remaining strength of pipe exceeds 1.39 times the maximum pressure allowed at the
location of the feature. This maximum pressure determined includes any potential surge
pressures as evidenced by pipeline surge analysis.
6.2.1.9.5 Microbiological Influenced Corrosion (MIC)
The Proposed Project is not seen to change the threat associated with external MIC nor has it
manifested as an injurious mechanism to the Longhorn Pipeline.
The pipeline is evaluated on a periodic basis through integrity testing by ILI tools. Table 5.3.1-1
provides re-inspection dates for each segment to evaluate the corrosion threat associated with
MIC. Through the ORA completed by third party consultant approved by PHMSA, new corrosion
6-13

<<<PAGE 1036>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
rates will be established after each ILI. This evaluation will determine if high corrosion rates are
occurring at selected areas which may indicate injurious MIC. Through the ORA process any
new information regarding areas of high corrosion rates would be considered to establish
appropriate features to investigate. Information gathered from the investigation of features
would be used to establish appropriate re-inspection intervals via the POE and ORA processes.
Additionally, as defined within the Corrosion Control Program, 7.04-ADM-001 (Appendix 6E), in
the event that the pipeline system experiences one or more confirmed discoveries of injurious
MIC, or where accelerated corrosion from MIC is anticipated, a Bacteria Testing Protocol will be
established to evaluate future integrity threats from MIC. The line specific protocol will be
utilized until such time that the threat from MIC has been assessed and appropriate mitigation
actions have been taken. Testing for MIC shall be conducted in accordance with Bacteria
Testing – Serial Dilution Method.
6.2.1.9.6 AC Induced Corrosion
The Proposed Project is not seen to change the threat associated with AC induced corrosion.
The SIP procedure, 7.04-ADM-023 (Appendix 6E), establishes a standardized method for
identifying and mitigating induced AC. AC potential surveys are conducted on each buried, in
contact with the ground, submerged pipeline facility, and/or breakout tank near high voltage
power lines once each calendar year with intervals not to exceed fifteen months. AC potentials
greater than 5 volts will be evaluated to determine if additional testing or remedial actions are
required. To mitigate corrosion, remedial actions will be required where through testing or
calculations, AC current discharge densities are found to be greater than 20 A/m2
. To reduce
step and touch shock hazards remedial actions and/or protective devices, such as ground mats,
are required if AC potentials exceed 15 volts. Recording voltmeters are considered in areas
where high voltage transmission lines parallel the pipeline over long distances.
The pipeline is evaluated on a periodic basis through integrity testing by ILI tools. Table 5.3.1-1
provides re-inspection dates for each segment to evaluate the corrosion threat associated with
AC induced corrosion. Through the ORA completed by third party consultant approved by
PHMSA, new corrosion rates will be established after each ILI. This evaluation will determine if
high corrosion rates are occurring at selected areas which may indicate AC induced corrosion is
occurring. Through the ORA process any new information regarding areas of high corrosion
rates would be considered to establish appropriate features to investigate. Information gathered
from the investigation of features would be used to establish appropriate re-inspection intervals
via the POE and ORA processes.
6.2.1.9.7 Stray Currents
The Proposed Project is not seen to change the threat of external corrosion due to stray
currents. Stray current interference testing, including, but not limited to close interval pipe-to-soil
surveys, will be conducted where practical and determined necessary by sound engineering
practices. Indicators of the necessity to conduct such tests shall include annual pipe-to-soil
surveys, internal inspection data, pipe inspection, or other related corrosion information or
6-14

<<<PAGE 1037>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
testing. Pertinent survey information shall be recorded on Magellan Foreign Line Interference
Test Form. Procedure 7.04-ADM-015 (Appendix 6E), Testing for Interference Currents and
Remedial Measures, establishes a standardized method for identifying, testing for and
mitigating the harmful effects of interference currents.
Table 5.3.1-1 provides re-inspection dates for each segment to evaluate the corrosion threat
associated with stray currents or interference. Through the ORA completed by third party
consultant approved by PHMSA, new corrosion rates will be established after each ILI. This
evaluation will determine if high corrosion rates are occurring at selected areas which may
indicate corrosion due to stray currents in occurring. Through the ORA process any new
information regarding areas of high corrosion rates would be considered to establish appropriate
features to investigate. Information gathered from the investigation of features would be used to
establish appropriate re-inspection intervals via the POE and ORA processes.
6.2.1.9.8 Selective Seam Corrosion (SSC)
The Proposed Project is not seen to change the threat associated with external corrosion
selective to the pipeline longitudinal seam weld. Per the requirements of the LMP, a TFI smart
pig inspection was conducted. The TFI tool is designed to identify any corrosion of or along the
longitudinal seam. The Inline Inspection Analysis Guideline, 7.03-ADM-007, provides criteria for
determining areas of SSC to investigate. These inspections did not reveal any confirmed
metallurgical indications of SSC on the Longhorn Pipeline. Any identified areas of potential SSC
were remediated in accordance with the Pipeline Defect Evaluation and Repair Procedure, 7.01-
ADM-001. Magellan’s processes and procedures contained within the SIP Integrity
Management Program, SIP-ADM-7.06 (Appendix 6E), provide for determinations of re-
assessment intervals to evaluate the integrity of longitudinal seam welds. Future longitudinal
seam weld inspections are designed to detect any potential indications of corrosion of or along
the longitudinal seam which could potentially be corrosion that is selective to the seam weld.
Additionally, Magellan’s processes for evaluation of future metal loss features identified by MFL
or UT tools are integrated with seam location information gathered from the TFI tools. This
information is utilized to evaluate any metal loss of or along the longitudinal seam. This
evaluation will determine if high corrosion rates are occurring at selected areas which may
indicate SSC is occurring. Through the ORA process any new information regarding areas of
high corrosion rates would be considered to establish appropriate features to investigate.
Information gathered from the investigation of features would be used to establish appropriate
re-inspection intervals via the POE and ORA processes.
6.2.1.10 Third Party Damage
Minimal changes to threats from third party damage will occur as a result of the Proposed
Project due to localized areas where above ground valve sites and facilities are added. For the
overall system the aggregation of local changes should not become a significant driver of risk,
even under conservative estimates.
6-15

<<<PAGE 1038>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Damage prevention programs incorporated within the SIP meet or exceed industry standard
requirements of performance. The program is a comprehensive approach designed to educate
the public and to prevent accidents resulting from excavation activities. Through cooperative
efforts with excavators and the public, this program creates widespread awareness on the
importance of damage prevention. The program exceeds 49 CFR Part 195 requirements in the
areas of permanent pipeline markers, ground and aerial surveillance, excavator education,
public education, and line spotting activities to achieve uncompromising public safety.
Per the LMP and LMC 12a, Magellan conducts Electronic Geometry Pig (EGP) Inspections
every three years which exceeds regulatory requirements. These inspections are a final
intervention to prevent failure from third party damage. Proactive mitigation programs such as
One Call, Public Education, Excavator Education, Depth of Cover monitoring and maintenance,
Pipeline Marking, Pipeline Surveillance, Encroachment Management, and ROW maintenance
are all designed to prevent third party damage to the pipeline. These programs are detailed in
the following sections. Magellan annually evaluates the effectiveness of these programs through
the Annual Third Party Damage Prevention Program Assessment. This assessment evaluates
the potential for inadvertent third party damages through the evaluation of one-call activity
levels, tracking of unauthorized encroachments, physical hits, near misses, mechanical damage
repairs, and ILI results. This assessment is provided to the third-party ORA contractor to be
incorporated into recommendations including integrity inspection intervals.
6.2.1.10.1 One Call
Magellan has established a standardized One Call program to protect company assets from
damage due to excavation, encroachments, and other third party activities. Magellan has
established and maintains a One Call membership with respective state agencies and follows
industry standards to receive, record, respond, and document One Call Locate Notifications.
6.2.1.10.2 Public Education
Magellan will revise public awareness programs to account for changes in product
characteristics from refined product to crude oil. Public education is an important element for
insuring widespread awareness and cooperation to protect the public, property, and the
environment. This program as defined within the SIP-ADM-10.01 (Appendix 6E), Public
Awareness Initiative, utilizes mailings, flyers, public meetings, emergency responder meetings,
periodic radio public service announcements, and newspaper ads to educate the local public.
Annual mailings to groups such as schools, residences, hospitals, churches, retirement homes,
and other businesses include the following information:
• One Call information
• Product identification information
• How to identify and report a suspected leak
• Personal safety guidelines in the event of a leak
• "Dig Safely" or Call 811 program information
6-16

<<<PAGE 1039>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Annual (not to exceed 15 months) mailings target a one-quarter (1/4) mile radius of the pipeline
in metropolitan areas and a one-mile radius in rural areas. Mailings include items such as phone
stickers, refrigerator magnets, and rulers to ensure that emergency contact information and
"Call 811" information will be readily available. Door-to-door visits with the public in areas
adjacent to the pipeline are performed in Tier 2 and 3 areas every two years (not to exceed 30
months).
Damage prevention flyers and “Call 811” literature are distributed to the public at county fairs,
trade shows, agricultural shows, feed and seed stores, home and garden shows, and equipment
rental companies.
Non-emergency response government agencies that are exempt from one-call mandates, such
as city and county planning, zoning and building permit offices, and agricultural agencies are
contacted annually (not to exceed 15 months) with mailings and a personal visit to distribute
maps of the pipeline route and inform developers of the presence of the pipeline.
Reply cards and records of personal visits, along with third party damage incident scorecards,
are used to measure the effectiveness of the program.
Emergency response agencies within each county that the pipeline passes through are
contacted at intervals not to exceed 15 months, but at least once each calendar year, in person
and provided with maps of the system. Specific emergency response requirements and plans
are reviewed on an annual basis with applicable LEPC and emergency responders. Annual
emergency response drills are conducted.
6.2.1.10.3 Excavator Education
Excavator education is an important element of damage prevention in order to reduce the
likelihood of unintended third party damage caused from excavation activity. The program as
defined within the SIP-ADM-10.01 (Appendix 6E), Public Awareness Initiative, focuses on
promoting cooperation and awareness throughout the following groups:
• General contractors (i.e., irrigation, dirt, fencing, plumbing, landscaping)
• Land owners
• Real estate developers
• Utility companies
• Mining and quarry operations
The identified excavators are provided with the following:
• Information on the "Dig Safely" program initiated by DAMQAT (Damage Prevention
Quality Action Team - a joint industry and government effort to educate the public on the
prevention of damages to all underground and submerged facilities).
• Information on the Texas One-Call system.
6-17

<<<PAGE 1040>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Information about the location of the pipeline and products in the line.
• What to do in the event that unintentional damage of the pipeline occurs.
• Instructions on how to recognize and report a leak.
Direct mail flyers, written in English and Spanish, include items such as dashboard calendars
and stickers so that emergency contact information and "Dig Safely" information will be readily
available. Reply cards will be included to measure the damage prevention program
effectiveness.
Advertisements are placed in various trade journals and/or community publications along the
Longhorn right of way to reinforce the "Dig Safely" program and to instruct the excavators to use
the One-Call system.
6.2.1.10.4 Depth of Cover and Exposed Pipe
Changes in exposure will occur at locations where valves are reconfigured and at station
modifications due to potential external impacts. Risk changes will occur for several short
segments of pipe. For the overall system, the aggregation of local changes should not become
a significant driver of risk, even under conservative estimates. The aggregation represents less
than 0.1% of the total System mileage associated with the project.
Threats from third party damage are mitigated through the SIP Depth of Cover (DOC) Program,
7.05-ADM-009 (Appendix 6E). The purpose of the DOC Program is to manage risks associated
with areas of shallow or exposed pipe. Land use, population density, environmental issues and
changes to the absolute depth of cover are expected to change over time. Continual monitoring
of these changes is performed through DOC Surveys, Aerial Patrols, In-Line (Smart Pig)
Inspections, One-Calls and Line Spotting. Through a formalized DOC Mitigation Process risks
are managed through a variety of methods, all designed to reduce the likelihood of unintended
outside force damage and consequential damages to a defined level. The DOC Program
focuses effort and resources to those areas of highest relative risk. The investigative and
resulting mitigation processes consequently focus on High Consequence Areas (HCAs) and on
the defined areas of hypersensitive (Tier 3), sensitive (Tier 2), and other (Tier 1), in descending
order.
6.2.1.10.5 Pipeline Markers
Permanent pipeline markers are used to notify the public of the general location of the pipeline.
Pipeline marker are installed and maintained in accordance with SIP procedure 7.05-ADM-002
(Appendix 6E). Permanent pipeline markers are maintained in Tier 1 (general), Tier 2
(Sensitive), and Tier 3 (Hypersensitive) areas as follows:
• Pipeline markers meet or exceed all requirements of 49 C.F.R. §195.410.
• Marker spacing for Tier 1 areas are placed within line-of-sight of each other. Exceptions
may be necessary for land use (i.e., cultivation), and landowner and tenant issues.
6-18

<<<PAGE 1041>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Discussions explaining the importance of line markers, as identified in our Public
Education program are held with landowners or tenants.
• Marker spacing for Tier 2 and 3 areas are placed such that if any one marker is
removed, the location of the pipeline can still be identified from either direction from any
point in between.
• All line markers are written in English and Spanish.
• Marker placement and density is evaluated routinely through aerial and ground
surveillance.
• Missing or damaged markers are replaced within 7 days of discovery.
• Markers are located at all aboveground facilities to identify the operator of the system.
• Markers are located on each side of each public road crossing, water crossing, and
railroad crossing.
6.2.1.10.6 Pipeline Surveillance
Most pipeline rights-of-way corridors are accessible through aerial surveillance, which is the
primary method of right-of-way inspection and damage prevention. Periodic conditions such as
weather, however, may render certain segments of the right-of-way inaccessible via fixed wing
aircraft or helicopter and thus ground surveillance can supplement air surveillance. In addition,
ground surveillance is utilized when vegetation temporarily obstructs aerial surveillance.
Pipeline surveillance is conducted in accordance with the SIP procedure 7.05-ADM-031
(Appendix 6E). Surveillance intervals are conducted as follows:
• Tier 2 and 3 areas: Every 2.5 days, not to exceed 72 hours
• Tier 1 areas: Once a week, not to exceed 12 days, but at least 52 times per year
• Edwards Aquifer Recharge Zone: Daily (one day per week shall be a ground-level patrol)
Aerial and ground surveillance frequency is increased across Tier 2 (sensitive) and Tier 3
(hypersensitive) areas when the threat of flooding and/or severe erosion is identified near the
pipeline right-of-way.
Emergency situations identified during aerial or ground surveillance are immediately reported to
the Pipeline Control Center located in Tulsa, Oklahoma. All surveillance personnel and line
spotters are trained and certified in OSHA HAZWOPER to the first responder level.
Every consideration is given to endangered species when conducting ground surveillance in
and around the pipeline right-of-way. Maps depicting the location and habitat of endangered
species are utilized for this purpose.
6.2.1.10.7 Encroachments and ROW Maintenance
Magellan manages encroachments in accordance with 7.05-ADM-012 (Appendix 6E),
Encroachment Procedure and the requirements of the LMP. Execution of this procedure
ensures that:
6-19

<<<PAGE 1042>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
• Encroachments do not hinder the ability to safely operate and maintain the assets.
• Pipeline adjustments are designed in accordance with sound engineering judgment to
ensure compliance with governing regulations.
• The respective rights and privileges in the easements are maintained.
• Proper reimbursement for work performed.
An encroachment is any infringement on the pipeline and associated ROW. An encroachment is
any activity or structure that materially or unreasonably interferes with or impedes the pipeline(s)
or easement rights.
In accordance with the LMP and SIP procedure 7.05-ADM-003 (Appendix 6E), Right-of-Way
Maintenance Program, ground cover is mowed to a level so that all pipeline markers, including
painted fence posts, are visible from the air and while standing on the ground. High canopy
vegetation is cleared or trimmed to the extent necessary to allow clear visibility. All debris is
cleared from the right-of-way.
6.2.1.11 External Forces
The Proposed Project will not change the potential of failure related to geohazards such as
seismic activity, aseismic faulting, landslides, scouring, subsidence, inclement weather, or
unrelated adjacent fires. Magellan will instruct emergency responders to contact Magellan in the
event that wildfires are threatening the facility. In the event of wildfires, facilities threatened will
be shut-down and blocked-in.
Magellan continues to manage external force threats as recommended by studies conducted as
part of the 1999 EA and as required by the SIP. These studies and their conclusions remain
valid for the System, and as such, the discussion as found in the 1999 EA is still relevant. The
Proposed Project may change failure potential from these threats at certain locations where
valves are re-configured and possibly at station modifications. Threats are very location-
dependent. An assessment of their frequency and magnitude is part of the design process.
Industry accepted design and construction practices will ensure that integrity is not
compromised by such threats.
6.2.1.11.1 Flooding
Scheduled inspections occur at various water crossings at six-month and five-year intervals.
Inspections also occur after certain flood events to evaluate for scouring, erosion and flood
potential. As a result of PHMSA Advisory ADB-11-04, Magellan implemented the Flooding
Conditions Procedure, 7.05-ADM-039 (Appendix 6E) to provide standards for recognition,
surveillance, and responses to flooding conditions near mainline pipelines.
6-20

<<<PAGE 1043>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
6.2.1.11.2 Geohazards
Studies are performed every six months to evaluate for ground movement, subsidence and
aseismic faulting. Surveys are conducted every five years to evaluate landslide potential.
Additionally, the Earth Movement Inspection Procedure, 7.05-ADM-020 (Appendix 6E), provides
methods for the investigation and monitoring of areas of the pipeline identified as having high
susceptibility to earth movement or where earth movement has been identified. Pipeline
surveillance activities pay particular attention, within the target area, to signs or indicators of
earth movement or subsidence such as ground cracks, sink holes, erosion, heaving, or
buckling. ORAs since 2005 have updated geohazard threat analysis, especially aseismic
faulting threat. No new issues have been identified and some previously identified issues have
been recognized as being less severe than was initially (and conservatively) deemed plausible.
6.2.1.11.3 Crossings
Magellan manages the integrity of overhead pipeline crossings with the Overhead Pipeline
Crossing Integrity Procedure, 7.05-ADM-030 (Appendix 6E). This procedure manages integrity
through a comprehensive risk-based program which identifies risk reduction projects to improve
structural component integrity.
Magellan manages the integrity of buried navigable river crossings with the Navigable Crossings
Integrity Procedure, 7.05-ADM-014 (Appendix 6E). This procedure requires inspection to
determine pipeline depths at these crossing at least once every five years per regulatory
requirements.
6.2.2 Staffing and Training
Magellan anticipates staffing additions as a result of the Proposed Project. Increased frequency
and locations of cleaning pig operations, coupon monitoring, and sampling will result in the need
for additional manpower. New facilities that include tanks, rotating equipment, and valves will
create a need for new maintenance and operating tasks. New employees will be trained in
accordance with requirements outlined in the SIP-ADM-2.01 and the Company Operator
Qualification Program per SIP-ADM-2.02 (Appendix 6E).
6.2.3 Risk Assessment Processes
6.2.3.1 ORA
Section 3.3 of the LPSIP requires Magellan to perform an ORA on an annual basis (not to
exceed 15 months). The ORA adjusts integrity verification frequencies in response to the
changing uncertainties over time in response to environmental changes along the pipeline route
and in response to data collected from integrity testing, additional attributes, changed attributes,
root cause analysis results, or other programs identified in the LPSIP. As discussed in Section
5.3.3.1, the ORA is a key program to monitor and maintain the integrity of the System. The
fatigue analysis and monitoring program previously discussed in Section 6.2.1.4 will be
6-21

<<<PAGE 1044>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
executed in accordance with the existing LMP requirements as discussed in Section 9.3.2.5 to
model pressure cycles and crack growth rates in the reversed flow direction. Additional process
improvements to the ORA are detailed as mitigation measures in Chapter 9.
6.2.3.2 Data Management
Magellan manages existing integrity data through processes defined within the SIP. These data
management processes provide support for the risk assessment processes currently in
compliance with 49 CFR 195.452 and the LMP requirements. Under the Proposed Project the
following integrity factors were considered:
• Product specifications
• Operating parameters
• Pipe specifications (i.e., date, seam type, wall, grade, coating, etc.)
• Stress levels
• Surge potential
• Depth of cover
• Internal corrosion control
• Locations of potential increased internal corrosion (i.e., low spots, dead legs)
• Drain volumes
• Pumps, valves, and other facilities
A matrix showing the risk implications of physical changes under the Proposed Project is shown
in Appendix 6G. Enhancements are discussed in Section 9.3.2 to address the enhancements to
data collection, maintenance, and integration processes. This includes conversion to an
electronic data management model that will provide greater automation and flexibility to
integrate data and conduct risk assessments.
6.2.3.3 Pipeline Risk Assessment
Magellan’s existing pipeline risk model meets the requirements of 49 CFR Part 195.452 and
LMP Commitments. Changes in commodity characteristics, internal corrosion threats, pressure
cycles, surge potentials, incorrect operations, security threats, and facility complexity lead to
changes in Magellan’s pipeline risk model, risk assessment and management processes
currently in place. Enhancements to risk assessment, data management, and risk assessment
processes are included as part of the mitigations detailed in Section 9.3.3.4. To facilitate
enhanced risk management, a risk profile or PoF profile quantifying risks within each portion of
the system will be generated. This profile will utilize integrated data and incorporate a dynamic
segmentation process to identify enhancements and mitigation measures necessary to maintain
PoF desired levels.
6.2.3.4 Facility Risk Assessment
Conceptually, managing the integrity of stations and terminals is similar to main line pipe. The
various elements described in the integrity management programs apply to pipeline stations and
6-22

<<<PAGE 1045>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
terminals, as well as to the pipeline itself. However, some aspects of data gathering, risk
assessment, inspection tools and techniques, and mitigation are specific to pump stations and
terminals.
The data used for facility assessments will vary from that used to model a pipeline. The
relatively more complex nature of facility piping including manifolds, numerous valves, flanged
connections, CP systems, dead legs/low flow piping legs, and auxiliary and instrumentation
piping are considered in facility assessments.
The procedure for a Facility Relative Risk Assessment can be found in the Facility Risk Ranking
Tool Instruction Sheet within the Facility Risk Assessment Model.
6.2.3.5 PHA/LOPA
As a result of the project, new facilities, equipment, and valve sites will be modified or added to
accommodate the change to crude oil and reversed flow direction. These changes create a
need for rigorous analysis of process hazards and subsequent evaluation of protection
measures and safeguard to mitigate hazards. As a requirement of the LMP, Magellan is
required to conduct PHAs (HAZOP, What/If checklists, etc.). An additional industry available
method to evaluate sufficiency of safeguards to mitigate hazards is called LOPA. LOPA is a
semi-quantitative risk analysis technique. The technique evaluates risks by orders of magnitude
of the selected accident scenarios and builds on the information developed in qualitative hazard
evaluation (e.g. PHA). This enhanced level of analysis is not currently required by regulation or
the LMP. LOPA is included as part of the mitigations detailed in Chapter 9 (Section 9.3.3.2).
6.2.4 Control Systems (SCADA)
6.2.4.1 Leak Detection
LMC 13 outlines the requirements of leak detection systems for the Longhorn Pipeline. The
LMP requires employing the best available leak detection software system for modeling of
operational transients. Such a system is classified as Computational Pipeline Monitoring (CPM)
system per 49 CFR Part 195 and American Petroleum Institute 1130 which provides guidance
on how pipeline companies should operate and maintain CPM systems.
For the Longhorn System, a means to detect leaks by monitoring pressure, flow and volume
balancing through pipeline leak detection system (PLDS) and SCADA is in place. The pipeline
will be shut down within 5 minutes in the event of a PLDS alarm, issued at 1% of normal flow in
a 30 minute window and 0.5 – 1% normal flow in a 60 minute window.
Magellan currently complies with both LMP and American Petroleum Institute Recommended
Practice 1130 first edition of September 2007 and will ensure compliance for the reversal and
conversion to crude oil service. Magellan will perform an American Petroleum Institute 1149
theoretical study to determine necessary enhancements to PLDS prior to start-up. The study will
provide a theoretical based assessment on future leak detection capabilities, and determine
6-23

<<<PAGE 1046>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
required system adjustments. The adjustments will be configured in PLDS and within the Stoner
Pipeline Simulator. Pipeline Controllers in the training simulator environment will be trained prior
to starting the real line operation. The training will focus on achieving emergency shutdown
within five minutes of a probable leak indication, and other abnormal operating conditions (AOC)
scenarios.
Magellan will perform tuning of PLDS with data generated by the simulation. Per LMC 13, this
will be completed prior to start-up in reversed crude service. CPM will be adjusted to become
operational over approximately two weeks of pipeline operation and be further optimized within
6 month per LMC 13.
Additionally, LMC 13 currently outlines a leak detection performance commitment for the
hydrocarbon sensing leak detection cable that was installed and currently functional over the
Edwards Aquifer Recharge Zone and the Slaughter Creek watershed in the Edwards Aquifer
Contributing Zone. The current commitment does not contain a performance specification for
crude oil. Magellan is proposing to add the performance commitment of 100 to 200 minutes
from contact for crude.
This performance commitment was determined based upon testing conducted by Tyco Thermal
Controls to determine the sensitivity of the existing TT-5000 leak cable on WTI and WTS
crudes. The Report # TT 1106-006 is included in Appendix 6H. These tests confirmed the cable
sensitivity as published by TraceTek, the manufacturer of the leak detection cable. Additionally,
Magellan contracted with Spartan Engineering Inc. to evaluate the existing systems capabilities
in crude oil compared to other direct detection methods. Spartan determined that the existing
leak detection cable is the best available technology for crude oil. The Spartan report is also
provided in Appendix 6H.
6.2.4.2 Control Room Procedures
As a result of the Proposed Project, any line specific Operations Control procedures will be
modified prior to start-up. All applicable Operations Control employees will be trained on any
new or revised operating and/or maintenance procedures. Appropriate pressure settings will be
established and the Maximum Pressure Charts will be updated with these settings.
PHMSA regulation CFR 195.446 has specific requirements related to SCADA point to point
verification, change management and training which will be applicable to this project.
Compliance with CFR 195.446 and other internal Magellan practices will be completed prior to
start-up.
6.2.5 Pipeline Inspection and Testing
6.2.5.1 Pressure Testing
New pipeline, pump station, or breakout station pressure testing will be conducted in
accordance with 7.03-ADM-001 Pressure Testing Procedure and applicable regulatory
6-24

<<<PAGE 1047>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
requirements (Appendix 6E). This procedure establishes the requirements, process, and
documentation for pressure testing.
6.2.5.2 In-Line Inspections (ILI)
Future integrity tests intervals are established in accordance with the ORA and in conjunction
with the procedures established within the IMP contained within SIP-ADM-7.06 (Appendix 6E).
Table 5.3.1-1 provides a summary of re-assessment intervals for each segment. Integrity tests
and subsequent rehabilitation is conducted in accordance with the procedures outlined in SIP-
ADM-7.03 (Appendix 6E), Integrity Testing and Rehabilitation and applicable regulatory
requirements.
6.2.6 Spill and Emergency Response Plans
Magellan’s existing Emergency Response Procedures, in compliance with regulatory
requirements as detailed in Section 5.4.2 and requirements within the LMP, are designed to
minimize the impact of pipeline emergencies by establishing, employing and maintaining a
consistent system of Emergency Response and Preparedness (ER&P) standards and
procedures. The ER&P Program is coordinated using three distinct processes: (1)
Preparedness, (2) Training, and (3) Response. The program provides a process of developing
and maintaining a system of emergency response plans and equipment and subsequent
training to utilize the system.
The existing response plans have been enhanced by adding over 120 site specific tactical
response plans that provide the location, equipment, personnel needed, and response tactics to
respond to a theoretical pipeline release. These tactical plans have been recently reviewed for
accuracy. As a result in the change in commodity, the emergency response tactics will be
reviewed prior to start-up to determine any necessary modifications. The enhanced response
plans also identify both groundwater and surface water intakes that could potentially be
impacted by a refined product spill and the methodology for identifying replacement water
sources in the event of an impact, or, detailed engineering designs for bolt-on application of a
water scrubbing system in the case of a municipal surface water treatment system. As a result
of the crude reversal, the potential impacts are being identified and the water scrubbing systems
are being reviewed to ensure they are consistent with the current designs of the individual
treatment centers.
6.2.7 Worst Case Spill Volume
The worst case spill volumes for both the 19-mile segment within the Edwards Aquifer
Contributing and Recharge Zones and for the remainder of the Longhorn Pipeline is calculated
assuming that the pipeline is operating at a maximum system capacity of 225,000 barrels per
day. Then, it is assumed that the pipeline is completely severed, allowing crude to freely flow
from the pipe at a rate of approximately 160 barrels per minute. Although Magellan has agreed
to a five-minute shut down time (LMC 13) and has trained its employees to meet this timeline,
the worst case spill assumes that it actually take Magellan 12.5 minutes (2.5 times the agreed
6-25

<<<PAGE 1048>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
upon time frame) to shut down the pipeline. Once the pipeline has been shut down, the product
from the nearest closed valves to the rupture site will flow from the pipe. This is known as the
“drain down volume.” The worst case drain down volume is calculated by assuming the least
favorable topography (i.e. a downhill slope from the nearest valve to the rupture site) and
farthest distance between valves.
Due to topography and valve placement, the worst case spill volume within the 19-mile Edwards
Aquifer Contributing and Recharge Zone is 5,131 barrels. This volume includes 2,000 barrels of
crude oil which would flow from a completely severed pipe at a rate of about 160 barrels per
minute for 12.5 minutes (2.5 times the LMP requirement). The remaining volume of 3,131
barrels could drain from the severed pipe once the system was shut down.
The worst case spill volume for the Longhorn Pipeline not within the 19-mile segment of the
Edwards Aquifer Contributing Recharge Zone is 22,087 barrels. This includes 2,000 barrels of
crude oil which would flow from a completely severed pipe at a rate of about 160 barrels per
minute for 12.5 minutes. The remaining volume of 20,087 barrels could drain from the severed
pipe once the system was shut down.
This worst case spill volume was utilized to conduct an overland flow analysis and determine
potential environmental receptors that could potentially be affected by a spill (zone of potential
impact). The analysis led to new designations of Tier II and Tier III areas along the ROW.
6.3 CONSEQUENCE POTENTIAL (COF)
Consequence potential varies along the System as a function of variables such as:
• Low spots/drain
• Leak detection capabilities
• Ignition probability
• Dispersion/migration potential
• Receptor sensitivities
As a part of Magellan’s existing annual procedures within SIP-ADM-7.06 (Appendix 6E),
additional analyses to strengthen knowledge of consequence potential will be completed.
Results of these analyses will be integrated with PoF estimates and receptor sensitivities (see
Chapter 7) to identify locations were additional risk mitigation may be warranted. While risk
thresholds, responsive to changing consequential potential along the System, have not been
identified, PoF thresholds have been established under the Proposed Project and are to be
maintained as a minimum at all locations.
The focus of this chapter is on PoF but an observation regarding overall risk is that potential
consequences of human fatality and injury are reduced by the Proposed Project due to the
reduced ignition potential of crude oil compared to the refined products currently transported.
6-26

<<<PAGE 1049>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Hazard zone determination is discussed in Chapter 5 and applied as part of the potential
impacts analyses in Chapter 7.
6.4 CONCLUSIONS
Based upon the mitigation detailed in Chapter 9, System-wide risk is reduced under the
Proposed Project. PoF risk measurements equate to a target under 0.0001 (1E-4) PHMSA
reportable incidents per mile-year at all mainline portions of the System. This equates to a
PHMSA reportable failure about once every 20 years somewhere along the mainline portions of
the System. This incident rate is superior to current Longhorn incident rates as well as the
average performance of US hazardous liquid transmission pipelines, as shown in Chapter 5. At
facilities, Magellan commits to limit PoF risk measurement to an average of 0.01 (1E-2) PHMSA
reportable incidents per facility per year. This equates to a PHMSA reportable spill once every
2.6 years System-wide, assuming a count of 39 facilities over the 496 miles of the Proposed
Project. (These target values will be reviewed as detailed in Chapter 9.). This target incident
rate is superior to current Longhorn incident rates for the last seven years. Comparison to US
Hazardous Liquid transmission pipeline incident rates is not available since identification of
‘facility’ is not reliably done in the comparison database.
The risk assessment concludes that the Proposed Project, with the mitigations outlined in
Chapter 9, will experience incident rates lower than current operations. The Proposed Project
introduces new threats, but additional project mitigations are seen to offset any increase in risk
as measured by PoF. In addition, potential consequences of human fatality and injury are
reduced by the Proposed Project due to the reduced ignition potential of crude oil compared to
the refined products currently transported.
6.5 REFERENCES
CorrPro report June-July 2010, Magellan Longhorn Tier 3, Segment 1-56 CIS on ~37 miles of
pipeline.
Email: Ref Halcrow: National Grid USA Service, Co, Inc., Risk Assessment for Gas Pipeline
Adjacent to Marine Parkway Bridge Agreement No. 573927 Final Report August 2011
Halcrow, 2011. National Grid USA Service, Co., Inc.: Risk Assessment for Gas Pipeline
Adjacent to Marine Parkway Bridge, Agreement No. 573927, Final Report, May 2011,
Halcrow, Inc.
Johnston, D.C., and Kiefner, J.F., “Audit of Existing Portions of Longhorn Pipeline”, February 24,
1999, Final Report to Jenkins and Gilchrist.
King, F., “Hydrogen Effects on Carbon Steel Used Fuel Containers”, December 2009, Nuclear
Waste Management Organization Report TR-2009-29
6-27

<<<PAGE 1050>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Muhlbauer, W.K., Pipeline Risk Management Manual (Elsevier Inc. 3rd Ed. 2004).
NACE International, Review of Published Literature on Wet H2S Cracking of Steels through
1989”, September 2003, Item No. 24185, NACE International 2003
Project Scope: “Magellan Pipeline LP Technical Services Texas Pipeline Project Prepared By
Robert A. Jackson”
U.S. Department of Justice / FBI, Terrorism 2002-2005 http://www.fbi.gov/stats-
services/publications/terrorism-2002-2005/terror02_05.pdf, page 11, accessed May
2012.
University of Texas (UT) analyses by DNV—multiple reports
6-28

<<<PAGE 1051>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
CHAPTER 6
APPENDICES

<<<PAGE 1052>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6A
RISK ASSESSMENT METHODOLOGY

<<<PAGE 1053>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6A
Risk Assessment Methodology
This risk assessment concluded that the Proposed Project, with the mitigations outlined in
Chapter 9, will experience incident rates lower than current operations. The Proposed Project
introduces new threats, but additional project mitigations are seen to offset probability of failure
(PoF) increases.
The following methodology, risk assessment comparisons and PoF assessments of various
threats are intended to provide the framework for the conclusions stated in Chapters 6 and 9.
Risk estimates of the existing System in refined product service are generated based on
available information. Risk levels under the Proposed Project are predicated on commitments to
design, operate, and maintain in a manner that ensures that the levels of risk of the Proposed
Project are at or below the baseline levels of risk for the current operation. Associated mitigation
measures are in place to perform robust and conservative4 risk measurements to ensure
acceptable risk levels as part of the overall risk management process.
In the absence of the additional mitigation discussed in Chapter 9, there is evidence that the
Proposed Project could result in increased incident rates compared to current operations. This
evidence is predicated on a conservative assumption regarding aspects of the Proposed Project
including the following:
• Location-specific number and severity of potential surge events,
• Frequency and compositions of sour crude shipments,
• Potential for blister formation and subsequent cracking,
• Pressure cycling severity, and
• Internal corrosion potential in new service
Mitigations, described in Chapter 9, are designed to maintain the PoF (from all failure
mechanisms below a pre-determined, specified level). Overall conclusions are that the risk
management enhancements will improve risk management and reduce failure potential from
current levels.
Maintaining all portions of the pipeline at or below specified levels requires that each
independent threat be kept lower than this so that the combination of all threats remains below
the threshold. Since new threats are introduced by the Proposed Project, those must be offset
by mitigations in order to keep overall PoF at all locations below the threshold. Uncertainty due
to passage of time is to be modeled as an increased PoF and must also be offset under this
commitment.
4 Using inputs and relationships that tend to overstate the risk and treating increased uncertainty as increased risk.
6A-1

<<<PAGE 1054>>>

APPENDIX 6A (continued)
These thresholds effectively cap maximum allowable PoF at all points along the System. The
threshold PoF level is below the PoF level associated with current operations, as is evidenced
by both the PoF assessment and the recent incident rates.
Although future risk estimates are predicated on successful mitigation, the underlying processes
to identify and manage those future mitigations are defined in Chapter 9 and are well
established standards of integrity management. Threshold risk levels are achievable as is
demonstrated by other operating pipelines and by the operational history of the System.
However, given certain specific characteristics of the Longhorn System and its intended future
operation, reaching and maintaining those levels will require additional mitigations and risk
management (See Chapter 9).
Risk Assessment Definitions:
For purposes of assessing PoF, ‘failure’ is defined in terms of loss of integrity and/or spills
emanating directly from a system component, rather than a more broad definition that includes
operability and serviceability criteria. Similarly, references to incidents and incident rates refer to
loss of integrity and spills, unless otherwise specified.
Other relevant terms that are used in specific ways in this report include anomaly, damage, and
weakness. Anomalies are indications that are deemed to be abnormal—they may or may not
represent damages, weaknesses, or otherwise indicate active failure mechanisms. Anomalies
are most often used in referring to ILI indications, but can also apply to overline surveys and
other inspections. Damages include metal loss, enlarged cracks, dents, and other potentially
weakening features that have been introduced into a pipeline system since installation. A
weakness is a location of reduced strength. A weakness may be caused by damage or by the
imperfect manufacture or installation of a component.
PHMSA reporting criteria were changed in 2002 to include spill amounts of hazardous liquids
greater than 5 gallons. Using this more stringent reporting regime, ‘failure’, for purposes of this
risk assessment, is equivalent to ‘reportable failure’ where reportable refers to criteria in 49 CFR
Part 195.50. Defining ‘failure’ in this context provides consistency with widely known criteria
defining what level of incident warrants additional action. This also avoids potential confusion
related to use of incident statistics from Magellan’s internal practice of documenting minor
incidents that do not rise to the level of ‘reportable’ by the PHMSA definition.
Failures also include spills that do not involve damages to integrity-containing components. For
example, overfilling of a sump or tank is considered a failure for this risk assessment when the
PHMSA criteria are met.
The PoF is an estimate of probability of failure, expressed as a percentage over a specified time
period for a specified portion of the System. Frequencies and probabilities can be
interchangeable when values are numerically very small. Otherwise, a conversion from
frequency to probability is calculated, based on an underlying relationship. Time dependent
failure mechanisms on a pipeline include corrosion and cracking. These require the estimation
6A-2

<<<PAGE 1055>>>

APPENDIX 6A (continued)
of a Time to Failure (TTF) as part of the overall estimate of PoF. Time independent failure
mechanisms such as third party damage and human error are estimated directly from frequency
of events and benefits of mitigation and resistance to failure.
In this analysis, a TTF is determined from each time-dependent failure mechanism for each
pipe segment. An assumed relationship between TTF and PoF ensures that, when TTF is
small (short time to potential failure), then the PoF is large, but as TTF gets longer, the PoF
dramatically decreases. This is intuitive since, for example, a segment with a TTF of 50 years
has very, very low PoF in the early years, up until the time near year 50,when PoF rapidly
increases toward 100%. This is akin to the ‘failure free’ period commonly seen in reliability
probability distributions such as exponential distributions and Weibull distributions.
To ensure that PoF is appropriately high when TTF is low, especially considering the
uncertainty surrounding the TTF estimate, the following relationship is used in the PoF
profiles:
if(TTF_ext99<1,iif(TTF_ext<[year of interest],0.99,1/TTF_ext),1/([factor]*TTF_ext))
This relationship ensures appropriate consideration of the full range of TTF values. For
segments passing the initial conditionals (ie, segments with longer TTF’s) in this relationship,
the factor relating a large TTF with early years’ PoF will determine the PoF.
The terms “threshold” and “maintain” or” maintenance” are used in conjunction with mitigation
under the Proposed Project. These terms are used in the same way that they apply to well-
known industry recognition of actionable limits such as pipe-to-soil voltage criteria for measuring
CP effectiveness. Threshold refers to a trigger that prompts additional action. Maintenance
refers to intent to continuously meet or improve upon a threshold. Instances where thresholds
are not met are expected. When issues are identified, the operator is obligated to, as soon as
reasonably possible, take action to address the issue and ensure that thresholds are again met.
Conservatism
A risk assessment should employ a target level of conservatism. Depending on the intended
use of the risk assessment results, various levels of conservatism might be appropriate.
When an assessment uses conservative inputs, layers of conservatism are created, resulting in
an overall conservatism greater than the sum of the individual inputs. This is an intentional use
of excess conservatism done to encourage future data collection as a means of risk reduction
and, more importantly, to ensure that risks are fully understood and not underestimated. This
approach is employed in the estimation of future risks under the Proposed Project.
A less conservative estimate is generated for the profile of current PoF levels. Use of less
conservatism in assessing the current state ensures that, in a comparison with the Proposed
Project, an artificially low ‘hurdle’ has not been set. Otherwise, conservatively estimated risk
6A-3

<<<PAGE 1056>>>

APPENDIX 6A (continued)
levels, showing higher risks than actually exist, would generate targets that are unrealistically
high and achievable with minimal mitigation.
The more conservative risk assessment, tending to over-estimate actual risks, generated for the
future risks under the Proposed Project uses inputs biased towards over-estimation of risk. In
the absence of a stronger technical basis for any required input, conservative but plausible
values are chosen. This higher level of conservatism is intentional and useful since it better
supports decision-making in several ways:
• If a project is deemed to have acceptable risk, even under conservative assumptions,
then more rigorous analysis is unnecessary.
• Underestimation of risk is often a more costly long-term error than overestimation.
• Conservative defaults highlight knowledge gaps, encouraging acquisition of better
information.
• More conservatism at the segment level (individuals) identifies location-specific risk
management opportunities.
• More conservatism in overall assessment reduces the chances of undesirable
aberrations in performance of specific pipeline segments (see discussion of predictive
capability below). Less conservative assumptions are sometimes needed for practical
reasons. For instance, a depth of cover survey may contain a gap in data points with
sufficient cover indicated on either side of the gap. It would be counter-productive to
assume that the depth of the pipeline is “0 inches” where data is not available, even
though such an assumption would be very conservative.
Sources of conservatism in the current assessment include the following:
• combining ILI data from three ILI’s, thereby treating duplicate anomalies as new
anomalies,
• use of MOP to represent normal operating pressures along all points even though most
segments would rarely experience such high pressure, and
• assumption of more aggressive failure mechanisms when information is incomplete
All assumptions will be re-examined for consistency with appropriate levels of conservatism as
part of the risk assessment enhancements in Chapter 9.
Measurement Units for Inputs
In this risk assessment, all factors are expressed as measurements rather than a score or point
assignment. Measurements include corrosion and crack growth rates (mpy), event frequencies
(e.g., events per mile-year), and percent effectiveness. As an example of the latter, a mitigation
measure estimated to be 70% effective means that 7 out of the next 10 events are ‘blocked’ by
that mitigation measure.
The use of consistent measurement units provides more precise and consistent input into a risk
assessment. It also facilitates validation and future refinement of inputs.
6A-4

<<<PAGE 1057>>>

APPENDIX 6A (continued)
Where actual measurement data is unavailable, the measurement is estimated by expert
judgment. While not as desirable as an actual measurement for a specific characteristic at a
specific location, experience shows that expert judgment based estimates will normally be of
sufficient accuracy. In this application, ‘sufficient accuracy’ means that input values assumed by
experts will produce risk estimates close enough to actual values that decisions can be reliably
made based on the produced estimates. Expert judgment based inputs are further refined via
the use of conservatism. By acknowledging the role of conservatism, a range of possible inputs
is identified, corresponding to the possible range of actual values under varying levels of
conservatism. This results in more insight into possible ranges of actual risks.
Predictive Capability
A desirable output of any risk assessment is accurate predictions of future failure potential. The
predictive capability of any risk assessment is highly dependent upon the available information
and the predictability of the system being studied.
Predictive capability must be judged with knowledge of the level of conservatism employed in
making the predictions (see previous discussion). A conservative assessment will produce
many ‘false positives’ while use of less conservatism will miss some indicators of higher risk,
producing ‘false negatives’. The balance between these two, losing sensitivity in order to reduce
nuisance alarms or tolerating nuisance alarms in order to avoid missing something significant, is
an important consideration for modeling, diagnostic, and monitoring systems such as a risk
assessment. In the conservative aspect of this risk assessment, a higher rate of false positives
is tolerated to ensure that few false negatives (missing actual risk issues) occur.
The actual risks associated with a given pipe segment will vary over time. It is best expressed
as a probability distribution that encompasses plausible failure scenarios with their associated
probabilities of occurrence. This probability distribution characterizes the expected behavior of a
population of pipeline segments.
Aggregated Data versus Individual Data
Part of the inaccuracies inherent in probabilistic prediction lie in inferring behaviors of individual
data based on behaviors of aggregated data. The latter is much more reliably estimated. An
individual pipeline segment may have radically different experience from its neighbors but still
be within expected behavior ranges of the population pipeline segments. Behavior of the
collection of individuals, the population, is shown by the range of possibilities of the individuals.
Each individual can demonstrate behavior anywhere within this range of possibilities and still be
consistent with the population.
Part of the prediction process is identifying a theoretical population of pipeline segments that
fairly represents the segment(s) being evaluated. Some segments may belong to a theoretical
population with very low failure probabilities and low potential consequences. Other segments
may be better characterized as belonging to less desirable populations, higher failure potential
6A-5

<<<PAGE 1058>>>

APPENDIX 6A (continued)
and/or higher consequence potential. A goal of the risk estimate is to correctly place each
segment into its representative population.
The 34,000+ event changes along the pipeline routes generated the final count of dynamic
segments for use in the risk assessment. Using all data in a dynamic segmentation process
results in over 32,000 segments, each with PoF characteristics unique from its neighbors.
Average segment length is about 100 ft. A risk profile must have sufficient resolution to
accurately portray real changes in risk levels along a route. This sufficiency is evidenced by
segment length. Segment length should reflect the frequency with which conditions or
pipeline characteristics change.
Min
Max
Avg Segment
Length of Pipeline
Line ID
Segment
Segment
Length (ft)
(ft)
Length (ft)
Length (ft)
Galena Park
to East
1 107 1744 50,000
Houston
(6643)
East
Houston to
0.101 74 1300 3,654,000
Crane (6645)
Crane to
Odessa
1 1119 24277 154,000
(6648)
These concepts are the basis for the calibration of the initial PoF estimates as discussed below.
To support risk management, PoF from various threats or from various pipeline segments are
often combined. To ensure that thresholds levels are met, appropriate aggregation of individual
threat levels must be made. Algorithms in the table below produce PoF values for each
segment, taking into account the segment’s length. PoF for each segment therefore includes
length effects. A normalization is performed to generate ‘per mile’ PoF estimates to compare to
threshold levels. This simply extrapolates segments’ PoF values to a hypothetical 5,280 ft
length, under an assumption of PoF being proportional to length.
To aggregate either the length-sensitive or the normalized values, a probabilistic summation is
required to ensure that masking of higher values does not occur and that the aggregation of
lower-valued threats is fairly represented. At each location along the System, the individual PoF
values from each threat are combined using an OR gate approach, illustrated as follows:
PoF = 1 – (1 – Pof1) x (1 - PoF2) x . . . (1 – PoFn)
The same relationship is used to combine PoFs from a collection of segments to show their
combined PoF. The probabilistic summation is required to ensure that PoF thresholds
established by the mitigations of the Proposed Project are met.
6A-6

<<<PAGE 1059>>>

APPENDIX 6A (continued)
Estimates produced by this risk assessment are concluded to be accurate representations of
the behavior of the entire pipeline, the population of all individual pipeline segments, over long
periods of time. Performance of subsets of the overall population over shorter periods of time
may vary significantly from the overall performance. The use of conservatism ensures that such
performance aberrations do not result in unacceptable estimates that could lead to inappropriate
risk management decisions. For example, as the overall behavior estimate is increasingly
biased towards over-estimation, the chances of unexpected behavior of a portion of the system
decreases.
PoF Estimates
In the current PoF profile, a measurement or estimate is made of the exposure, mitigation, and
resistance related to every failure mechanism, as defined below:
• Exposure - likelihood or aggressiveness of force or failure mechanism acting on the pipe
when no mitigation applied. This can be thought of as a measure of the attack on the
system.
• Mitigation - actions that reduce or block the force or failure mechanism from the pipe.
This can be thought as the defense against the attack, usually consisting of multiple
mitigation measures.
• Resistance - the system’s ability to resist a force or failure mechanism applied to the
pipe.
Probability of Damage—damage without immediate failure—also emerges from these
definitions. Using the first two terms without the third—exposure and mitigation, but not
resistance—yields the probability of damage.
Probability of Damage (PoD) = f (exposure, mitigation)
Probability of Failure (PoF) = f (PoD, resistance)
Damage does not always result in immediate failure. Some damage may trigger or accelerate a
time-dependent failure mechanism. Calculation of both PoD and PoF values creates an
opportunity to gain better understanding of their respective risk contributions.
In this risk assessment, all calculations result in measurements units, just as with inputs to the
assessment. Exposures are measured as either material degradation rates (measured in mpy)
or event frequencies (measured in events per mile-year). Mitigations and resistance are
measured in percentage effectiveness.
Risk Assessment Comparison
This risk assessment measures the change in risk from current operations of the existing assets
in refined product service to operations under the Proposed Project. Risks associated with
current operations are termed ‘Baseline’.
6A-7

<<<PAGE 1060>>>

APPENDIX 6A (continued)
Baseline risk reflects current operations characterized as transportation of refined product
flowing through approximately 496 miles of pipeline and 4 pump stations from Galena Park to
Crane and Crane to Odessa. A system characterization and discussion of current operations,
maintenance, and safety controls is provided in Chapter 5.
PoF profiles are generated to understand the baseline risk and the risk presented by the
Proposed Project. As a collection of thousands of pipeline segments, a profile shows
discrimination along the pipeline, identifying changes in risk corresponding to changes in the
pipeline itself, its hydraulic profile, and its surroundings.
Risk estimates that treat the entire pipeline as a single facility are also produced. This approach
has been used to characterize a pipeline that is assumed to have risks consistent with some
comparable population of other pipelines whose risks have been measured over time. Since risk
varies along any pipeline, this process must assume average or worst case conditions exist
everywhere or perform some type of grouping of pipe and environmental characteristics. It also
relies on a representative population, such as incident rates from comparable US transmission
pipelines, to characterize the subject pipeline.
Estimates produced from this generalized approach can be valid characterizations of the risks
presented by populations of pipeline segments over long periods of time. Predictions of
behaviors of populations are more reliable than predictions of behavior of individuals. The
population-based estimates are therefore useful in calibrating a collection of pipeline segments
to the expected behavior of the underlying population from which the segments are thought to
arise.
PoF profiles for the existing system and the Proposed Project have been produced. The focus is
on threats to System integrity and accompanying changes in risk that will occur due to the
Proposed Project.
The System has experienced leaks, mostly in facilities, since its initiation of operations in 2005.
These releases were always contained within property boundaries. Experiences of leaks,
damages, ILI anomalies, and near misses are relevant to baseline risk levels and are detailed in
Chapter 5.
Baseline risk levels include both past damages and potential for future damages. Past events
on the System are discussed in Chapter 5. Incident rates are calculated and compared to other
representative pipelines, as discussed below.
INTEGRITY THREATS
The following integrity threats were addressed in the risk assessment and explained further
below:
POF ASSESSMENT FOR INTERNAL CORROSION
6A-8

<<<PAGE 1061>>>

APPENDIX 6A (continued)
If not properly mitigated, localized, pitting corrosion from sour crude effects may occur. The risk
assessment model estimates show high internal corrosion damage without mitigation measures
employed. The estimates are represented as a PoF. For this FEA, PoF has been quantified for
all portions of the System. Estimates are based on integration of all available location-specific
information, producing a PoF profile along the pipeline route. This profile produced over 32,000
segments (average segment length is approximately 100 ft.), demonstrating a high level of
resolution.
In this PoF assessment, the PoF profile is calibrated using incident histories that reflect the past
performance of the System in both crude and product operation, and similar pipeline systems.
For generation of the current PoF profile, probability of failure by internal corrosion is assessed
as follows. Unmitigated corrosion rates and effectiveness of mitigations along the pipeline are
estimated, using low spots and ILI-findings as the main distinguishing aspects. An estimate of
current pipe wall thickness, adjusted for possible weaknesses by previous damages and
manufacturing/construction, is theoretically degraded by the mitigated corrosion rate to predict a
time to failure. A relationship between this predicted time to failure and probability of failure
within a certain time period is then used to produce the PoF estimate.
This risk assessment models aggressiveness of internal corrosion as a function of accumulation
potential, previous ILI identified damages, and estimates of plausible internal corrosion rates
under current and future product transport plans. Current corrosion rates, reflecting the transport
of refined product (very low corrosivity), are modeled to range from 1 to 3 mpy multiplied by an
accumulation potential of 1 to 3, for a final range of 1 to 9 mpy unmitigated corrosion potential.
Future unmitigated corrosion rates of sour crude oil are modeled to range from 10 to 30 mpy,
also multiplied by the same 1 to 3 factor, for a final range of from 10 to 90 mpy unmitigated
corrosion potential.
Background for these modeling assumptions is presented below.
For this analysis, several sources of potential corrosion rate information were examined as
noted in the following discussions.
Internal corrosion rates as reported in the ORA state that 1-3 mills per year were generally
assumed in previous Magellan analyses (ORA, 2008). Internal corrosion coupon rates are
reported in each ORA. Magellan proposes a mitigation measure to improve the monitoring of
future internal corrosion potential, as discussed in Chapter 6and Chapter 9.
Chapter 5 reports on internal corrosion damages to portions of the System from Crane to
Cottonwood, non-operational circumstances. In 2008, corrosion was detected and determined
to be as a result of remnant pressure test water left in the pipe. This pipeline segment was
subsequently replaced. This damage is not thought to be reflective of current in-service
corrosion rates but provides insight into possible corrosion under special circumstances.
6A-9

<<<PAGE 1062>>>

APPENDIX 6A (continued)
As noted in the discussion on data integration, a damage rate in mills per year (mpy) (i.e.
1/1000 inch per year) is estimated from ILI anomaly findings and associated measurements.
The rate is modeled to be the maximum depth of any anomaly of type ‘metal loss internal’
appearing within each 100 ft segment of pipe, divided by 10 years to arrive at a percent wall
thickness per year. This is multiplied by nominal pipe wall thickness to arrive at mpy. This
calculation is performed for anomaly type ‘metal loss internal’ and used in this analysis. This
analysis produces the following histogram (see figure below). The vertical axis shows the
combined lengths of pipeline segments with the corresponding corrosion growth rates (on
horizontal axis).
Histogram of Modeled Internal Corrosion Rates
400000
350000
300000
250000
200000
150000
100000
50000
0
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 18 19
Modeled Internal Corrosion Rate, mpy*
*mpy int- internal corrosion rate = 1/1000 inch per year
The use of 10 years reflects a plausible time period under which corrosion damage could have
occurred. The 1950 vintage pipe was in sour crude service for periods of its service life (1999
EA). The pipeline’s more recent operational life was in a product service believed to be non-
corrosive except under upset conditions.
Some ILI TFI internal metal loss anomalies are identified as false positives according to ORA
2010. It is conservative to assume all indications are correct. Therefore, all ILI indications
remain in the risk profile.
Corrosion Rates under Proposed Project
Internal corrosion can result from the transport of sour crude oil containing H2S because of the
oxidation potential that can occur when H2S is in the presence of water and/or oxygen. Because
6A-10

<<<PAGE 1063>>>

APPENDIX 6A (continued)
of this potential, the corrosion rates for the Proposed Project has been evaluated by an
independent third party internal corrosion expert (see 6C).
Mitigation under the Proposed Project is designed to address these other constituents. To
recognize the additional internal corrosion mechanism created by the Proposed Project, the
future corrosion rates are modeled to be significantly higher than those estimated using the
previously discussed procedure at each location along the pipeline. As additional data is
acquired from the mitigation activities corrosion rate assumptions can be adjusted.
Accumulation Potential
Internal corrosion in a pipeline transporting hydrocarbons typically occurs where corrosive
constituents, usually heavier than the hydrocarbon, accumulate and are in contact with the pipe
wall for periods of time. Water and solids can settle in low spots in the pipeline and promote
entrapment of other corrosive agents and/or microbes, both of which can be a source of
accelerated corrosion. Where Microbiologically Induced Corrosion (MIC) processes become
active, corrosion rates can be very high.
To acknowledge changes in corrosion potential along the route, locations of higher drain down
volumes are assumed to be more likely locations of contaminant accumulation and therefore
internal corrosion, if mitigation fails. Similarly, where lesser drain down volume occurs, there is
lowered expectation of accumulation potential. Under these assumptions, probabilities are
assigned to each location based on drain volume to that location.
Inspection Intervention
Preventing damages through mitigation is logically the preferred method of managing the threat
of internal corrosion. Intervention through integrity testing is a necessary aspect of risk
management of internal corrosion mechanisms. Successful scheduling of intervention requires
an understanding of potential corrosion rates. The uncertainty surrounding anomaly sizing is
well defined in the ORA’s Probability of Exceedance (POE) process for metal loss. Magellan
has investigated methods to estimate corrosion growth rates (mpy) when data from like-tool
technical data is not available (i.e. TFI vs, MFL vs, UT). Under the mitigations of the Proposed
Project, the ORA processes are enhanced related to corrosion growth rate estimates.
The continued use of metal loss ILI tools will enable the monitoring of any localized corrosion
metal loss along the pipeline. In addition, ILI as an intervention tool reduces failure potential
since it can interrupt the accumulation of damages prior to failure. This is taken into account in
the risk assessment by examining the highest PoF that may occur before the next ILI (5 year
intervals assumed).
Mitigation Effectiveness
EnhanceCo conducted an independent analysis and cites prior work from Dr. Sheldon Evans
(see Appendix 6C) that internal corrosion rates when transporting sour crude can be controlled
by eliminating air and the use of an inhibitor. Additional rate reductions may be achievable by
removing water and solids from the line with the use of an aggressive cleaning pig program.
6A-11

<<<PAGE 1064>>>

APPENDIX 6A (continued)
EnhanceCo cites the need for important mitigations when transporting sour crude, including:
• Use of corrosion inhibitors
• Coupon monitoring at preferential accumulation points
• Monitoring for MIC
• Regular cleaning pigs to eliminate water and debris that may settle in low areas
during periods of time when the pipeline is not flowing as sufficient velocities to
sweep potential accumulations.
• Avoidance of low flow and stagnant conditions
These mitigation measures are included in Section 9.3.2.2 and are proven to be effective based
on years of transport of sour crude oils in other pipelines.
For purposes of this FEA risk profile, estimates of mitigation effectiveness are made and applied
consistently along all portions of the pipeline. Since the modeled exposure rate varies according
to some location-specific characteristics, the modeled corrosion rates will vary. Current activities
to control internal corrosion involve control of product specification entering the pipeline,
monitoring by coupon, and ILI. For purpose of generating the PoF profile, the current internal
corrosion control activities conducted for transport of refined product is assigned a numerical
estimate of effectiveness. This effectiveness is chosen as a plausible value that, when coupled
with estimates of aggressiveness of current product transport, yields conservative but plausible
values for PoF less than or equal to 1E-4 for a population of pipeline segments. Mitigation
effectiveness is assumed for generation of a risk profile of the Proposed Project. Effectiveness
values are conservative. However, they reflect the proposed additional mitigation measures
and, when coupled with the high estimates for aggressiveness of corrosion, conservative results
are produced.
POF ASSESSMENT FOR SURGE
The probability of a surge of a magnitude threatening any portion of the System can be
estimated from an analysis of potential surge initiators, the effectiveness of surge prevention or
mitigation, and the hydraulic behavior of the surge event.
For the purpose of conducting this risk assessment analysis surge pressures were assumed
using conservative estimates at all points. This presents an overstated estimate for this threat at
most locations and does not allow discrimination along the pipeline with regards to surge
potential, pipe stress levels, and effectiveness of safety devices. This risk assessment does
discriminate regarding Maximum Allowable Surge Pressure (MASP) and presence of potential
weaknesses.
For conservative modeling purposes only, a PoD associated with surge was modeled. A PoD
associated with surge is modeled to be one event in 10 years for 480 miles of pipeline. With the
assumption of no resistance, the PoF equals this value. Under future conditions of the
Proposed Project, increases are conservatively forecast for probabilities and aggressiveness of
surges. Unmitigated surge frequencies are modeled to be 0.5 per year at all locations under
6A-12

<<<PAGE 1065>>>

APPENDIX 6A (continued)
future operations. Future resistance level is modeled to be inversely proportional to stress level,
the latter calculated as shown in the PoF algorithm table below.
Under future conditions of the Proposed Project, increases are conservatively forecast for
probabilities and aggressiveness of surges. Unmitigated surge frequencies are modeled at all
locations under future operations. Resistance is modeled to be inversely proportional to stress
level, the latter calculated as shown below.
The theoretical available pipe wall is placed into the Barlow internal pressure equation to
calculate the maximum pressure to which the pipe wall could be subjected. This pressure is
compared to the MASP. When MASP exceeds the tolerable pressure of the theoretical pipe wall
available, pipe failure is forecast upon application of the surge pressure.
When left unmitigated, the results show pipe potentially subjected to surge pressures beyond
their conservatively adjusted pressure containing capacity, under the assumptions used. Surge
will be mitigated with industry standard protective devices to keep surge pressures within
regulatory and LMP requirements. Additionally, events which can ultimately lead to surge
overpressures are mitigated with administrative and engineering controls. Modeled
exceedances of safe pressures are believed to be due solely to conservatism and limitations in
current data.
Surge Mitigation
An analysis was performed by Willbros Engineering to determine whether surge pressures can
occur that exceed 110% MOP limits. Those limits are defined by 49 CFR Part 195. Per the
Longhorn Mitigation Plan (LMP), Commitment Item 31, Magellan will be seeking PHMSA
approval of the measures to mitigate surge.
LMC 31 states that “Longhorn shall perform a surge pressure analysis prior to any increase in
the pumping capacity above those rates for which analyses have been performed or any other
change which has the capability to change the surge pressures in the system. Longhorn will be
required to submit mitigation measures acceptable to DOT/OPS prior to any such change in the
system, which mitigation measures will adequately address any MASP problems on the system
identified by the surge pressure analysis.”
To demonstrate on-going risk management of this threat, mitigations as detailed in Chapter 9
are designed to measure and take appropriate steps to ensure failure potential from this threat
does not exceed a pre-determined level at any location along the System. Coupled with the
commitment to improve data management and risk analyses, risk levels can be managed to
levels at or below those associated with current operations. This ensures that future PoF are
less than 1E-4 and below current levels.
After completion of the final surge analysis and PHA/LOPA process as discussed in section
9.3.3.2, overpressure protection measures will be established and approved by PHMSA in
accordance with the LMP. A combined effectiveness of 99.9999% from all mitigation measures
is used. This value indicates a simultaneous failure of all overpressure-prevention measures
6A-13

<<<PAGE 1066>>>

APPENDIX 6A (continued)
once in every 10,000 demands. This value is chosen based on a review of systems in place
including proposed pressure regulation and safety devices. Given the high reliability of
redundant control/safety systems typical of pipeline operations, a value this high is realistic.
POF ASSESSMENT FOR CRACKING AND FATIGUE MONITORING
The actual rate of crack growth is dependent upon the three phases of crack advancement
through a material: initiation, activation, propagation. Factors such as crack configuration,
stress level, frequency and magnitude of stress cycles, and metallurgy are important
considerations in crack growth rates.
Based on the issues and evidence noted above, several cracking failure mechanisms are
included in this PoF analysis. Fatigue, sulfide stress cracking, hydrogen-induced cracking from
blistering, and SCC are rare, but possible phenomena.
Probability of failure by cracking is assessed as follows. Unmitigated cracking rates and
effectiveness of mitigations along the pipeline are estimated. An estimate of current pipe wall
thickness, adjusted for possible weaknesses in manufacturing/construction, is theoretically
degraded by the mitigated cracking rate to predict a time to failure. A relationship between this
predicted time to failure and probability of failure within a certain time period is then used to
produce the PoF estimate.
Exposure: Fatigue and Hydrogen Assisted Cracking
For risk assessment purposes, the likelihood of the existence of cracks must be estimated,
activation is assumed, and then a relationship for the constant crack growth phase can be used
to estimate propagation rate. The likelihood of incorrect assumptions in the crack growth
calculations is also considered.
Initiation
Initiation is a function of the probability of a feature of sufficient size and characteristics to
provide a starting point from which a crack can emerge. Outside force damages (i.e. gouges),
Low Frequency ERW and EFW longitudinal seam defects, girth weld imperfections, arc burns,
and laminations are identified as possible initiation points in the System, in addition to other
weaknesses possibly introduced by the pipe manufacturing or construction process. The
probability of an initiating point is modeled to be related to the frequency of relevant anomalies
detected by ILI, especially crack-sensitive ILI (TFI). Some fraction of the population of detected
anomalies is assumed to be potential crack initiators.
While some of the relationships between anomalies and initiation points are currently unknown,
the algorithms used to generate the PoF profile (detailed below) reflect the reasonable
assumption that either deeper seam-type anomalies or a higher incidence rate of manufacturing
defects or laminations leads to higher potential for crack initiation points.
Activation
6A-14

<<<PAGE 1067>>>

APPENDIX 6A (continued)
Activation, as used here, is the probability that conditions exist to begin a crack from an initiating
point. One form of activation is sufficient cyclic fatigue at a susceptible location, including
possible fatigue sources of internal pressure cycles, external pressure (load) cycles, and others.
This potential is addressed in the annual ORA via analyses of actual internal pressure cycling
on an assumed initiator defect and applied to crack growth models. No source of significant
external force fatigue cycling on the System has been identified.
Another form of activation is modeled as the probability of atomic hydrogen at a lamination. A
literature review has found no models to predict the progression from a lamination to a blister to
a failure on a pipe. This assessment assumes greater crack probability at locations of more
and/or larger unrepaired laminations.
In addition to these identified activation mechanisms, some probability of activation for other
potential mechanisms, is assumed. Assumed probabilities are conservative.
Propagation
Propagation is modeled as a function of stress level and material toughness, with the latter
being inferred by pipe age. Surge potential is included in the stress consideration, noting that
rate of loading influences failure potential.
Three regions of crack growth (propagation through a material) are identified and include: near
threshold, linear, and instability. Many structures operate in the linear region. The Paris equation
is popularly used to model crack behavior in this region. Crack growth rate versus stress
intensity is approximately linear in this region and lies roughly between 10-6 and 10-3 in/cycle
according to various literature sources. Crack growth rate increases with increasing applied
stress. Most of the life of the component is spent while the crack length is relatively small.
Stress concentrators play a significant role in fatigue initiation.
Under future conditions, increases are conservatively forecast for probabilities of both initiation
and activation. Pending acquisition of more accurate estimates of actual measured operation
pressure cycles, the following assumptions are incorporated into the TTF estimates along the
pipeline for the Proposed Project.
.
• fatigue cycling equivalent to three times currently estimated, shown as increased
crack propagation rates
• all anomalies of types ‘manufacturing’, ‘lamination’, ‘seam’, and ‘girth’ are considered
to be initiation points
• higher activation probability at all of these anomalies
To account for inaccuracies and limitations in tool technology associated with the intervention
process, the following assumptions are incorporated into the analysis:
• Undetected or under-sized initiation points exist at a rate proportional to the identified
initiation points.
• Anomalies remain for every anomaly that is repaired.
6A-15

<<<PAGE 1068>>>

APPENDIX 6A (continued)
These assumptions are reasonable, conservative, and useful for PoF estimates and lead to
increased crack growth rate estimates, lower TTF, and increased PoF compared to the current
operation, unless mitigation is applied. Using the existing commitment under the LMP to
schedule intervention at 0.45 of the estimated TTF, leads to a modeled shortened intervention
timing until actual pressure cycles are re-evaluated after reverse flow.
Mitigation and Intervention
Intervention is often the most practical option for risk management of fatigue cracking
mechanisms. Reducing damage potential is the preferred approach to risk management. There
are some cracking damage prevention opportunities. Prevention of blistering may be possible
through the control of internal corrosion. Preventing the introduction of water and other corrosive
agents, monitoring of potential corrosion on the inside of the pipe, and regular sweeping of
accumulations with cleaning pigs can minimize the hydrogen generating environment. A direct
assessment (DA) type process as defined in the ORA Process Manual is one of the tools
currently used to manage the threat of SCC. In addition, a magnetic particle inspection is
conducted at every excavation.
Other crack damage prevention typically involves unrealistic changes in product or operating
parameters. Intervention therefore plays an important role in crack risk management.
Intervention acknowledges that damage might be occurring, but interrupts damage progression
that would otherwise result in failure.
Successfulness of intervention depends on timeliness of inspection, ability to detect potentially
injurious anomalies, and error free remediation of those anomalies. Using conservative
assumptions, cracking Time to Failure’s (TTFs) and associated PoFs are calculated along the
pipeline by applying cracking growth rates to effective pipe wall estimates.
For all cracking failure mechanisms, integrity assessment is seen as a critical intervention
aspect of risk management. Intervention, as the final opportunity to prevent failure, under the
Proposed Project mitigations is designed to prevent PoF from exceeding 1E-4 failures per mile-
year during intervals between interventions.
Mitigations detailed in Chapter 9 add both conservatism and robustness to the intervention
process. TTF estimates that drive the intervention timing are to be improved, as are
considerations for the range of potential damage rates that could occur.
Incorrect Operations
An important aspect of assessing this threat is a modeled variable called ‘overpressure
potential’. This modeled variable is a measure of the potential to overpressure a portion of the
pipeline through human error or certain equipment failures. From a risk standpoint, the worst
situation is where a pipeline could be immediately over pressured in a relatively simple scenario.
The best case is where there are no pressure sources powerful enough to overpressure the
pipeline under any condition or where an overpressure scenario is only achievable after a long
period of multiple, undetected operational missteps.
6A-16

<<<PAGE 1069>>>

APPENDIX 6A (continued)
Given the relatively low compressibility of fluids and higher operating pressures and flow rates,
the System is judged to be susceptible to overpressure unless engineered safeguards are in
place. Engineered safeguards that include redundant overpressure protection devices such as
pressure transmitters, fail-safe switches, and pressure relief valves are in place and tested in
accordance with regulatory requirements.
The potential for failure due to incorrect operations often shows little variation along a pipeline
route since many aspects of this failure mode are not location specific. Examples of system-
wide consistency in human error potential aspects includes: training, the use of procedures, risk
assessments, condition of maps and records, and the presence of error-prevention devices.
Location-specific aspects of human error potential which do change for the Proposed Project
are as follows:
• Locations of higher human activity such as stations
• Potential for overpressure (higher where the surge potential and pipe stresses are
higher);
• Construction and design (higher for the older portions of pipeline and included in pipe
strength analysis).
Mitigation measures have been defined after completion of the final surge analysis and are
designed to prevent PoF from exceeding 1E-4 failures per mile-year. The LMP requires
Magellan to submit mitigation measures acceptable to PHMSA prior to any change which could
impact surge pressures. Other safety system designs are assumed to be similar to existing
operational schemes. A relatively high reliability value can be assigned to mitigation
effectiveness when several levels of safety redundancies are included in the proposed control
schemes. A formal LOPA type analysis, required as mitigation in Chapter 9, will be conducted
once pump station designs, including safety systems, are finalized.
Algorithms modeling this threat are shown at the end of this document and are discussed as
follows:
Profile of Current PoF from Incorrect Operations
To generate a risk profile, a measurement or estimate is made for the exposure, mitigation, and
resistance related to this threat. Although these values are currently assumed, based upon
similar existing operational schemes, it is necessary to establish a model that is well-structured
and ready to utilize more accurate information. A related mitigation requires such a structure to
demonstrate achievement of the risk level.
The failure potential from this threat is modeled to reflect the following:
• Leak history
• Previous human error incidents
• Increased complexity with addition of more pump stations, inhibitor injection, need for
regular maintenance (cleaning) pigging.
6A-17

<<<PAGE 1070>>>

APPENDIX 6A (continued)
Since the System is to undergo a new operation with new equipment, new procedures, and
perhaps newly assigned personnel, the human error potential could initially be higher. Pending
full HAZOP-type analyses to identify and quantify issues, and application of risk-based
mitigation measures, it is conservative to assume the Proposed Project brings an increase in
failure potential from incorrect operations. Additional mitigation is intended to offset this potential
increase as discussed in Chapter 9.
Given the changes brought on by the Proposed Project, the accompanying increase in
complexity, and some uncertainty regarding future operations, the estimated failure rate for the
current operation is increased to show a future failure rate for the mainline. Similarly, at facilities,
the rate is increased to account for changes and uncertainties. The future PoF values used in
the PoF profile are generated by the algorithm(s) shown at the end of this document...
Exposure
The assessment does not discriminate location-specific characteristics along the mainline such
as overpressure potential, safety device effectiveness, and source pressure influences. It is
conservatively assumed that all portions are connected to sources that can theoretically
generate pressures exceeding System capabilities. Overpressure potential is assumed to
represent most of the incorrect operations exposure and is assumed to apply to all segments.
For initial quantification of this threat at all mainline segments, an estimate of unmitigated event
frequency is first made. Incorrect operations events threatening the mainline will typically be
generated at facility locations. Additional potential overpressure events such as surges and
thermal overpressure of blocked in components is assumed to be included in this exposure
value.
Mitigation
A reliable set of mitigation measures against overpressure is assumed based upon information
provided for the Proposed Project. A combined effectiveness of 99.9999% from all mitigation
measures is used. This value indicates a simultaneous failure of all overpressure-prevention
measures once in every 10,000 demands. This value is chosen based on a review of systems in
place including proposed pressure regulation and safety devices. Given the high reliability of
redundant control/safety systems typical of pipeline operations, a value this high is realistic.
Formal analyses such as Layer of Protection Analysis (LOPA) following formal PHA’s will be
conducted as part of the mitigation of the Proposed Project described in Chapter 9. Depending
on measured risks, additional location-specific mitigation may be required, such as: additional
redundancy in safety systems, additional training, and changes to processes and procedures.
Changes to the assets will result in new or modified site specific operating procedures. Magellan
establishes operating procedures as per SIP-ADM-9.01 (Appendix 6E) to prevent adverse
impacts to the public, employees, environment, and the community. These operating
procedures will be revised and employees will be trained prior to startup. Additionally these
changes will result in new or modified maintenance procedures. Magellan has established
Mechanical Integrity and Tank Integrity Programs to maintain the integrity of all equipment and
tanks through risk based inspections and preventive maintenance.
6A-18

<<<PAGE 1071>>>

APPENDIX 6A (continued)
To assess on-going risk management of Incorrect Operations, mitigation as described in
Chapter 9 will maintain risk level thresholds during the intervals between intervention
opportunities at or below risk levels that existed prior to the implementation of the Proposed
Project. The threshold selected as appropriate for all threats combined is 1E-4 failures per mile-
year at each non-facility portion and 0.01 per year at each facility. These values are below the
estimated current levels for the threat of incorrect operations alone. Therefore, successful
application of this mitigation measure ensures that the risks associated with this failure
mechanism are reduced by the Proposed Project to levels below current.
Security
The threat level currently appears to be low compared to other threats. The frequency of
integrity threatening events on US transmission pipelines is less than 1E-6 per mile-year. This is
based on a FBI report showing one pipeline-related incident in 25 years and assuming 400,000
miles of potential US targets with increased attack potential in recent years (USDOJ/FBI, 2012).
This pipeline risk assessment established a probability of failure from security threats. Security
threats are modeled to change by the Proposed Project. Stations, casings with vents, and valve
locations are thought to be more susceptible sites on the System due to visibility and ease of
access. Locations where cover condition are changed would experience an increased threat
and these would normally generate only minor changes in overall PoF. This threat at other
locations is relevant due to the commitment to maintain PoF levels below pre-established
thresholds under the Proposed Project.
Algorithms modeling this threat are shown at the end of this document and are discussed as
follows:
In general, the Longhorn Pipeline is not thought to be more vulnerable than other pipeline
systems. Standard or above-average security measures will be in place in accordance with the
LMP and SIP which would generally include fences, locks, increased patrols, and surveillance
cameras.
The FBI has published a report summarizing 318 terrorism events between 1980 and 2005
(USDOJ/FBI, 2012). The terrorism events include all successful and foiled plots. Only 1 foiled
plot related to potential pipeline attack was recorded. In 2005, a terrorist plan to carry out violent
attacks against pipeline systems and energy facilities in Pocatello, Idaho was prevented.
(Halcrow) This system has not experienced terrorism or sabotage.
The threat level currently appears to be low compared to other threats. The frequency of
integrity threatening events on US transmission pipelines is less than 1E-6 per mile-year. This is
based on the U.S. Department of Justice’s, FBI report, Terrorism 2002-2005, showing one
pipeline-related incident in 25 years and assuming 400,000 miles of potential US targets with
increased attack potential in recent years (USDOJ/FBI, 2012).
6A-19

<<<PAGE 1072>>>

APPENDIX 6A (continued)
For purposes of PoF profiling, the algorithms shown at the end of this document are used to
estimate PoF from security threats. Logically some portions of the System make more attractive
targets, either from the standpoint of ease of access or potential consequences. Pending
analyses of such locations, only distinctions between above- and below-grade portions of the
System are made. The calculations assume an incident every 5 years at above-ground
locations and 10% of this incident rate elsewhere for both current and future PoF.
Mitigation
As part of the Proposed Project, mitigations detailed in Chapter 9 are designed to improve data
management and tracking related to location-specific sabotage threats and maintain this
knowledge in a database. This should improve estimates of PoF. Additional mitigations in
Chapter 9 to improve risk assessment and risk management, and to maintain PoF levels below
1E-4 and will reduce failure potential from this threat when applied successfully.
Magellan’s existing procedures contained in SIP-ADM-8.01 (Appendix 6E) provide for security
measures such as security fencing, monitoring cameras, physical barriers, and locks to
adequately limit access and mitigate security threats.
PoF Assessment for Accidental Releases (predictions, frequency, Comparisons,
Calibration)
Leak Predictions
A very generalized approach to risk assessment for a long, linear asset, such as a transmission
pipeline, uses summary values representing all portions of the system. The summary values
either assume a consistent set of characteristics and conditions exist along the entire route or
that the variations along the system are defined by a ‘population’ of pipeline segments. The set
of characteristics and conditions can be based on ‘worst case’ seen anywhere along the route
or, more commonly, is based on an assumed set of characteristics and conditions embedded in
a population of pipelines from which a comparable incident rate is to be derived. As an example
of the latter, an average incident rate for US hazardous liquid transmission pipelines, perhaps
filtered by decade of construction or other parameter, is obtained. Then, under the assumption
that the subject pipeline ‘behaves’ like this comparison population, that incident rate is applied to
all portions of the subject pipeline. Effectively, this means that the subject pipeline is thought to
be a part of the population of pipelines to which a comparison is being made. Sometimes this
approach includes a subsequent step to adjust this ‘baseline’ incident rate for portions of the
subject pipeline, where it is postulated that the subject pipeline has differing characteristics
and/or conditions sufficient to warrant a deviation from a rate implied by the overall average of
the comparison population.
Historical leak and spill frequency data, discussed in Chapter 5 for various spill sizes, were used
as inputs into probability estimates. Since data is limited in both quantity and quality, additional
estimates, often based on expert judgments are required in all assessments of real world,
complex systems.
6A-20

<<<PAGE 1073>>>

APPENDIX 6A (continued)
Regardless of the specific assumptions and methodology employed, results of such generalized
analyses should not be used in isolation. They can easily over or understate the actual
probability of future failures at specific locations or in short time periods. Behaviors of
populations of segments over long periods of time are more reliably predicted than individual
behaviors. The probabilities calculated here are intended to complement the risk profile
discussed in previous sections.
Leak Frequency
In a generalized analysis as described previously, historical leak frequencies are sometimes
used to predict future leak frequencies. In this type of analysis, there are no considerations for
the changing PoF along the length of the pipeline. Leak frequencies are assumed to be
uniformly distributed in time and space. This is not an accurate reflection of real risks so this
type of analysis is limited in its ability to characterize risk.
“Reportable” spill or leak refers to DOT criteria for formal reporting of accidents at 49 CFR
§195.50. A spill size of 50 bbl was one of the triggers requiring the incident to be reported
through 2001. Most pre-2002 incidents in DOT spill databases predominantly contain spills of 50
barrels or greater, although there are cases where a different criterion has mandated the
reporting of an incident. Beginning in 2002, the reportable leak criterion based on volume spilled
was reduced to 5 gallons.
Magellan records incidents and leaks that do not meet minimum reporting criteria. These minor
events are treated as learning opportunities. As discussed in Chapter 5, the Longhorn system
has experienced 42 leaks since 2004, where 13 of those met minimum PHMSA reporting
criteria (2 of those are noted to be ‘agency reportable’ but not ‘DOT reportable’, in data
provided). Since such minor leaks are recognized by regulating agencies as having minimal
consequence, they are not included in the following historical leak calculations.
Comparisons with other Pipeline Leak Data
Three "frequency of reportable leak" cases are examined. These cases use only historical data
with no consideration given to possible benefits of future mitigation or to changes in leak rates
along the System. They include all failure mechanisms that historically generated reportable
incidents. Therefore, some failure mechanisms not affected by the Proposed Project are
included. The cases examined are as follows:
Case 1 Comparable Pipelines (Texas and US hazardous liquid pipeline leak rate)
The total leak incident rate for reportable incidents on Texas hazardous liquids pipelines, from
2001-2010 is 1.96 incidents per 1000 mile-year for all incidents using the assumptions shown in
Table 5.4.1-4.
6A-21

<<<PAGE 1074>>>

APPENDIX 6A (continued)
The total leak incident rate for reportable incidents on US hazardous liquids pipelines, from
2001-2010 is 2.01 incidents per 1000 mile-year for all incidents using the assumptions shown in
Table 5.4.1-5.
For the 496 miles of the Proposed Project, these historical rates, if appropriate for the Proposed
Project, suggest a reportable incident rate of 496 miles x 2 reportable incidents per 1000 mile-
year/1000 = 1.0 reportable leak per year
Magellan contracted with Allegro Energy Consulting to extract mainline pipe only incident data
for the years 2010-2011 as a benchmark comparision for the risk threshold of 1E-4 mainline
incidents/year. This equates to 0.1 incidents per 1000 mile-year.
The mainline pipe only incident rate for reportable incidents on US hazardous liquids pipelines,
from 2010-2011 is 0.830 incidents per 1000 mile-year for crude oil pipelines or 0.695
incidents/1000 mile-year for crude and refined product pipelines combined.
The mainline pipe only incident rate for reportable incidents on Texas hazardous liquid pipelines
from 2010-2011 was reported to be 1.057 incidents/1000mile-year for crude oil pipelines and
0.838 incidents/1000 mile-year for crude and refined product pipelines combined.
Case 2 (System operation since January 2005, reportable leak rate)
The reportable incident rate for 722.5 miles of this System in 6.5 years is 13 incidents or leaks.
(Incident rate) = (13 leaks) / (722.5 miles x 6.5 years) * 1000 = 1.70 incidents per 1000 mile-
year.
Excluding reportable spills at stations, the reportable leak rate is 1. Therefore: (Incident rate) =
(1 leak) / (722.5 miles x 6.5 years) * 1000 = 0.2 incidents per 1000 mile-year for mainline
portions.
If the historical reportable rate is more appropriately derived from only the 496 miles of the
Proposed Project (the one reportable incident on the mainline occurred in Travis County), then ,
(Incident rate) = (1 leak) / (496 miles x 6.5 years) * 1000 = 0.3 incidents per 1000 mile-year for
mainline portions.
The expectation generated by values produced in this case would be (496 miles/1000 miles) x
(0.2 to 0.3) = 0.1 to 0.15 reportable leaks per year.
Case 3 (Longhorn operation since January 2005, overall leak rate)
The overall leak rate, regardless of spill size or reportable nature, on the 722.5 miles of the
System is 28 in 6.5 years. (Incident rate) = (28 leaks) / (722.5 miles x 6.5 years) * 1000 = 6.0
per 1000 mile-year.
Excluding spills at stations, the leak rate for all leak types is 4. (Incident rate) = (4 leaks) / (722.5
miles x 6.5 years) * 1000 = 0.85 per 1000 mile-year along the mainline.
6A-22

<<<PAGE 1075>>>

APPENDIX 6A (continued)
This case makes use of Magellan’s practice of documenting even very minor and
inconsequential leaks. Therefore, very conservative results emerge, compared to an analysis
limiting historical data to more significant leaks. For the 496 miles of the System, the
expectation generated by this case would range from 0.85 to 6.0 failures per 1000 mile-year.
This equates to between 0.4 and 3 leaks per year System-wide.
Summary of Cases
The above analysis suggests that, if the System performs either like it has in the past or as an
average of other liquid pipelines, then reportable failure rates in the range of 0.1 to 1.0
reportable leaks per year are to be expected.
These leak frequency estimates have a high degree of uncertainty as predictors of the future.
The use of averages alone to describe the comparable populations is one example of possible
significant mischaracterization of incident rates. Using subsets of the industry-wide data in
attempts to better characterize similar populations might entail filtering by decade of
construction, diameter, product, or other parameter deemed to produce a better comparable.
However, each filtering further reduces the amount of data available for comparison. No data
set that would better refine these estimates are known to be available.
As noted earlier, frequencies and probabilities like these are statistically valid only over long
periods of time for large populations of pipelines. Short time periods and short lengths of
pipeline can have radically different experience and still be appropriately represented by these
frequencies.
Calibration of PoF Profile
Each of these cases can be compared to the PoF profile estimates for the same locations. This
provides a check on the plausibility of the assumptions used in the PoF profile. Approximately
90% of the PoF profile segments show values between 1E-3 and 0.1 failures per mile-year.
These segments are short in length, so their respective PoF values are scaled from a few feet
up to a mile. The remaining 10% of the profile show higher PoF values, thought to be due to
errors in data or excessive conservatism in one or more specific failure mechanisms.
Based on the comparisons, the PoF profile shows exaggerated amounts of conservatism when
segments are scaled to longer lengths or numerous segments are combined. As discussed
earlier, a high level of conservatism is beneficial in several ways and is intentionally included in
initial PoF estimates. For other purposes, less conservative estimates are more appropriate.
Using a value of 0.0005 failures/mile-year, consistent with the comparison cases above,
suggests that the profile currently overestimates PoF by a factor that is estimated under certain
assumptions. This factor can be used to adjust individual segment PoF estimates so that the
population of segments carries an expectation consistent with past behavior of this and similar
systems. Adjusting the profile with estimates of population behaviors preserves the location-
specific understanding generated by the profile without biasing the overall expectations with
excessive conservatism.
6A-23

<<<PAGE 1076>>>

APPENDIX 6A (continued)
Using this approach, a calibration factor is applied to the PoF profile values. This value
recognizes the uncertainties in several key aspects of the Proposed Project and includes a level
of conservatism (i.e., includes historically dominant facility leaks). As with other modeling
relationships employed in this analysis, alternative underlying assumptions may be appropriate,
depending on availability of additional information and/or desire for different levels of
conservatism. Using this calibration factor to adjust each segment’s PoF, the following PoF
estimates are produced for the 496 miles evaluated:
PoF Estimates
Per Segment (of varying length) Per mile
Min Avg Max Sum Min Avg Max
fails/mi-
fails/mi-
fails/mi-
Scenario fails/yr fails/yr fails/yr fails/yr
yr
yr
yr
PoF current
state, calibrated 5E-09 8E-05 1E-02 2.8 3E-05 1.8E-01 9.9E-01
PoF future state
(Unmitigated),
calibrated 1E-08 1E-03 2E-02 48.8 5E-05 9E-01 9.9E-01
The value of 2.8 failures per year estimated for the current state equates to about 0.006 failures
per mile-year for this System. This is in the range of values produced in the conservative Case 3
(leak history for mainline and facilities). Some of the high ‘per mile’ values in the PoF profile
estimates for the PoF Future State (unmitigated) are due to extrapolation of pipe with very
localized ILI-detected damage (very short segment length), to one mile lengths, effectively
treating the local damages as if they extend for an entire mile. This does not materially impact
the overall assessment since these per-mile values have limited use here.
To examine certain location-specific changes in PoF brought about by the Proposed Project,
segments involved in proposed valve reconfigurations can be viewed independently.
When examining potential risks at specific locations along the System route, estimates
generated by the adjusted PoF profile are applied to specific receptors potentially present at
those locations.
Overall, this risk assessment concluded that the Proposed Project, with the mitigations outlined
in Chapter 9, will experience incident rates lower than current operations. The Proposed Project
introduces new threats, but additional project mitigations are seen to offset PoF increases.
The POF Algorithms used in the risk assessment are provided in the table below.
6A-24

<<<PAGE 1077>>>

APPENDIX 6A (continued)
PoF Algorithms (Updated)
The algorithms applied to the database to generate PoF profile (with brief descriptions) are shown below:
RA Model Element
Units
Algorithm for Current Operation PoF
Algorithm for Future Operation PoF
Estimates
Estimates
Description
pipe_wall*iif(val([repair_ID])>0,1,smaller(
pipe_wall iit|val([repair_D])>0,1,lit [above
pipe_wall_avail
inches
1-nz(maxofseam_depth,0),(1-
_graF future',1,smaller(1-
nz(maxofmaxofpeak_depth,0)),nz(minofm
nz(maxofseam_depth, 0), (1-
apparent effective pipe wall
nz(maxofmaxofpeak_depth,0)),nz(minofmi
thickness, based on ILl info
inofrpr,1)))
nofrpr,1)))
mpy_ext_ILI
Mpy
nz([MaxOfdmg_rate_vel_ext]*[pipe_wall]*
iif([above_grd]=future',0,nz([MaxOfdmg_r
1000,0)
ate_vel_ext]*[pipe_wall]*1000,0))
ILI-implied corr rate
mpy_int_ILl
Mpy
nz([MaxOfdmg_rate_vel_int]*[pipe_wall]*
nz([MaxOfdmg_rate_vel_int]*[pipe_wall]*1
1000,0)
000,0) *1.5
ILI-implied corr rate
(Ipipe_wall_avail]*1000)/larger(0,mpy_ext
([pipe_wall_avail]*1000)/larger(0,mpy_ext_
TTF_ext
years
_ LI,mpy_ext_general*mpy_ext_accel"(1-
ILl,mpy_ext_general*mpy_ext_accel*(1-
TTF
corr_ext mit))
corr_ext mit))
TTF_ext99
years
([pipe_wall_avail]*1000)/larger(0,mpy_ext
([pipe_wall_avail]*1000)/larger(0,mpy_ext_
_LI,mpy_ext_general*mpy_ext_accel)
ILI,mpy_ext_general*mpy_ext_accel)
worst case TTF
TTF_int
years
([pipe_wall_avail]*1000)/larger(0,mpy_int
([pipe_wall_avail]*1000)/larger(0,mpy_int_
LI,mpy int general* (1-corr_int _mit))
ILI,mpy_int_general*(1-corr_int_mit))
TTF
TTF_int99
years
(Ipipe_wall_avail]*1000)/larger(0,mpy_int
(Lpipe_wall_availl*1000)/larger(0,mpy_int_
_LI,mpy_int_general)
ILI,mpy_int_general)
worst case TTF
general corrosion rate;
mpy_ext_general
Mpy
iif([above_grd]="present",3,16)
lif([above_grd|=future",,if[above_grd|=
atmospheric or soil; low
present, 3, 16))
corrosivity if aerial, high if
buried
mpy_ext_accel
Mpy
iif([above_grd]='present",2,1)
if([above_grd]=future", 2,if[above_grd]=
increase in mpy to account
present",2,1))
for 'hot spots' such as
air/ground interface
6A-25

<<<PAGE 1078>>>

APPENDIX GA (continued)
corr_ext_mit
%
smaller(999,0.99999,exp(-
smaller(999,0.99999,exp(-
% eff of mitigation, per
[gaps/ft/CIS_fctr*len))
[gaps/ft]/CIS_fctr*len))
linear ft
CIS_fctr
factor
larger(0,1,11-(year(now())-
larger(0,1,11-(year(now())-
factor to decrease modeled
year(nz(CIS_date,1900))))
year(nz(CIS_date, 1900))))
mitigation gap rate when
recent CIS is available
mpy_int_general
Mpy
iif(drain_low=0,1,nz(drain_low/10000*3,1))
iif(drain_low=0,10,nz(drain_low/10000*30,
internal corrosion mpy;
based on low spot
corr_int_mit
%
effectiveness of mitigation;
modeled to decrease mpy
len
Ft
[sectioned1_by_ID].endstation-
[sectioned1_by_ID].endstation-
[sectioned1_by_ID].begstation
[sectioned1_by_ID].begstation
segment length
prob of one or more
initiation points, takes larger
iif/val([repair_ID])>0,0.00001, larger(nz(ma
iif(val([repair_ID])>0,0.00001,larger(nz(ma
of seam anomaly depth or
crack_initiate
%
xofseam_depth, 0.00001), nz(sumofman_d
xofseam_depth,0.00001),nz(sumofman_de
fraction of surface area
ef_rate,0.00001), nz(sumoflam_rate,0.0000
f_rate, 0.00001),nz(sumoflam_rate,0.00001)
impacted by laminations or
manufacturing anomalies;
non-conservative
assumption of 100%
PoDetection
prob of initiating point
crack_activate
%
0.0001
0.1
activating a crack; constant,
pending improved info
crack_propagate
Mpy
2
6
mpy crack growth rate,
based on ORA max
assume no mitigation;
(pipe_wall_avail*1000)/larger((crack_initia
(pipe_wall_avail*1000)/larger((crack_initia
resistance is pipe wall anc
TTF_crack
years
te*crack_activate*crack_propagate), 0,0.0
te*crack_activate*crack_propagate), 0,0.00
0001)
001)
Presume ro bo r ra ire
effective
TTF_SCC
years
(pipe_wall_avail*1000)/(SCC_mpy)
(pipe_wall_avail*1000)/(SCC_mpy)
TTF
6A-26

<<<PAGE 1079>>>

APPENDIX 6A (continued)
probabilistic mpy, length-
sensitive (mpy/ft); based on
SCC_mpy
Mpy
1.68350168350168E-06*len
Round(nz([mop1]/[2st/d],1.0),3)*(1e-
no failures in 50 yrs, 450
4) *len*10
miles, 0.2" pipe; ie, had
there been X prob-mpy for
450 miles over 50 yrs, 0.200"
wall pipe would fail now
calibrate for incident
occurring now at abvgrd
PoF _sabotage
failures 11490°5 flabove gra]=present; 1,10)) 11490°5'i|[above grd] = present, 1, ilab location; 1 incident in Syr
/year
en/5280
ove_grd]= future', 1,10))) *len/5280
for System mileage; 10X
less for buried
mit_cover
%
lif([above_grd]=present", 0,0.9)
iif([above_grd]='present",0, iif|[above_grd]
='future",0,0.9))
mit eff of cover
mit_other_excav
%
0.9
0.9
combined mit eff of all other
measures
assume cover (and anything
else used) is 99% eff against
mit_impacts
%
iif([above_grd]="present",0.2,0.99)
iif(jabove_grd]=present, 0.2,if|[above_gr
impacts; if no cover, then
d]=future',0.2,0.99))
other measures 20%
(barriers, distance, trees,
ditches, etc
events/
exp_impacts
mile-
0.1
0.1
freg of unmitigated 'events',
year
per mile of pipe per yr
events/
exp_excav
mile-
0.2
0.2
freq of unmitigated 'events',
per mile of pipe per yr
year
6A-27

<<<PAGE 1080>>>

APPENDIX 6A (continued)
resistance; fraction of
damages not manifesting as
failures; 80% resistance to
res _ext_force
%
iif(pipe_wall_avail>0.3,0.8,0.5)
iif(pipe_wall_avail>0.3,0.8,0.5)
failure when pipe wall
thickness exceeds 0.3", 50%
otherwise; includes ILI
anomalies as reductions in
pipe wall thickness
PoF_excav
failures
1-exp(-exp_excav*len/5280*(1-(1-(1-
1-exp(-exp_excav*len/5280*(1-(1-(1-
/year
mit_cover)*(1-mit_other_excav)))*(1-
mit_cover)*(1-mit_other excav)))*(1-
probability of damage
res_ext_force))
res _ext force))
PoF_impacts
failures
1-exp(-exp_impacts*len/5280*(1-
1-exp(-exp_impacts len/5280*(1-
/year
mit_impacts)* (1-res_ext_force))
mit_impacts)*(1-res_ext force))
probability of damage
MOP1
Psig
longhorn_MAOP_fixed.mop
longhorn_MAOP_fixed.mop
use MOP from database, not
RRA
0
0
0
0
[2st/d]
Psig
2"[pipe_wall_avail]*[smys]/[pipe_size]
2*[pipe_wall_avail]*[smys]/[pipe_size]
Barlow formula for
maximum internal pressure
% of allowable pressure
surge_stress
%
Round(nz([masp]/[2st/d],1.0),3)*100
Round(nz([masp]/[2st/d],1.0),3)*100
consummed by surge
pressure
events/
surge_freq
mile-
0.5
0.5
event count, system-wide
year
surge_resis
%
iif(surge_stress>100,0,1-
current resist included in
surge_stress/100)
PoD rate
PoD_surge
damag
1 iif(surge_stress<100,0,surge_freq)*len/52
calibrate to 1 incident in
0.000204*len/5280
10yrs for System mileage;
es/year
no mitigation
PoF_surge
failures
|I 1-exp(-(PoD_surge*(1-surge_resis)))
III 1-exp(-(PoD_surge*(1-surge_resis)))
Lyear
probability of failure
6A-28

<<<PAGE 1081>>>

APPENDIX 6A (continued)
PoF_IncOps failures
/year
smaller(0,0.99,iif([above_grd]='present',0.
6/20,2e-7)*len)
iif([above_grd]='present',0.8/20,iif([above_
grd]='future',0.8/20,1.5*2e-7))*len
includes equip; 13 spills in
facilities since 2000; PHA
rate is 0.6 per yr per facility
(even valve site) with facility
= 20 ft of pipe; for non-
facility, use mainline rate = 3
equip fails since 04, assume
450 miles
6A-29

<<<PAGE 1082>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6B
CRUDE OIL SPECIFICATIONS

<<<PAGE 1083>>>

lntertek Report of Analysis NTERI
Client: Magellan Pipeline Co. L.P. Job Location: Cushing, OK USA
Our Reference Number: US180-0000069
Client Reference Number:
None
Sample ID: 2011-CUSH-000076-001
Sample Designated As: Crude
Vessel/Location: Odessa, TX
Representing: MAGELLAN- ODESSA- 7-12-11- WTS
Date Taken: 15-July-2011
Date Submitted: 15-July-2011
Date Tested:21-July-2011
Drawn By:Ciient
Method
ASTM D287
ASTM D4294
ASTM D445
ASTM D5191
ASTM D4007 _MOD
ASTM D97
ASTM D4530
ASTM D664
ASTM D5708
Test
Result
Units
ASTM D7169
UOP 163
API Gravity (Hydrometer Method)
API Gravity @ 60 °F
31.9
Sulfur Content in Petroleum Products by ED-XRF
Sulfur Content
2.00
Kinematic I Dynamic Viscosity
Test Temperature
37.8
Kinematic Viscos~ty
5.540
Vapor Pressure of Petroleum Products (Mini-Method)
Dry Vap?r Pressure Equival~nt, ASTM
3.13
Water and Sediment in Crude Oil
Solvent
STODDARD SOL VENT
Total Water and Sediment
0.05
Pour Point of Petroleum Products
Pour Point
-15
Pour Point
5.0
Micro Carbon Residue
Average M
icro Method Carbon Residue
_
3.45
Acid Number of Petroleum Products by Potentiometric Titration
Procedure Used A
Acid Number
0.10
Metals by ICP-AES
Procedure
Test Method B
Nickel Content
5.21
Vanadium Content
9.60
Boiling Point Distribution of Samples with Residues by High Temperature GC
Boiling Point Distribution See Attached Report
Hydrogen Sulfide and Mercaptan Sulfur
H2S
10
Mercaptan Sulfur
521
Wt%
eSt
i
ps_
Vol%
Wt%
mg KOH/g
m(Jikg
mg/kg
ppmWt
ppmWt
Page 1 of 2
688224
804 E. North Street, Cushing, Oklahoma 74023 USA
Tel : 918-306-4206 Fax.: 918-306-4208 Email: amerusa.cushing@intertek.com
21-Jul-2011 14:02
US180-0000069

<<<PAGE 1084>>>

lntertek Report of Analysis R
This report has been reviewed for accuracy, completeness, and comparison against specifications when available. The reported results are
only representative of the samples submitted for testing and are subject to confirmation upon completion of the final report, which may contain
warnings, exceptions and terms and conditions which are pertinent to the data supplied herein. It is the position of lntertek that the final report
is the prevailing document, and that the use of interim documents by the client is at their own risk. This report shall not be reproduced except in
full without written approval of the laboratory.
Date:
Signed : --------------------------~~~------------------------lntertek
---------------------------------
Kevin Gilbert, Branch Manager
)
Page 2 of 2
688224
804 E. North Street, Cushing, Oklahoma 74023 USA
Tel.: 918-306-4206 Fax.: 918-306-4208 Email: amerusa.cushing@intertek.com
21-Jul-2011 14:02
US180-0000069

<<<PAGE 1085>>>

lntertek Report of Analysis E I
Client: Magellan Pipeline Co. L.P. Job Location: Cushing, OK USA
Our Reference Number: US180-0000069
Client Reference Number:
None
Sample ID: 2011-CUSH-000076-002
Sample Designated As: Crude
Vessel/Location: Odessa, TX
Representing: MAGELLAN- ODESSA -7-12-11- WTI
Date Taken: 15-July-2011
Date Submitted:15-July-2011
Date Tested:21-July-2011
Drawn By: Client
Method
Test
Result
Units
ASTM D287
ASTM D4294
ASTM D445
ASTM D5191
ASTM D4007 _MOD
ASTM D97
ASTM D4530
ASTM D664
ASTM D5708
ASTM D7169
UOP 163
API Gravity (Hydrometer Method)
API Gravity @ 60 °F
40.3
Sulfur Content in Petroleum Products by ED-XRF
Sulfur Content
0.405
Kinematic I Dynamic Viscosity
Test Temperature
37.8
Kinem
atic Visco~ity
_
2.858
Vapor Pressure of Petroleum Products (Mini-Method)
Dry Vap?r Pressure Equiv~lent, ASTM
5.40
Water and Sediment in Crude Oil
Solvent
STODDARD SOL VENT
Total Water and Sediment
. . .
0.05
Pour Point of Petroleum Products
Pour Point
<-30
Pour Point
<-22.0
Micro Carbon Residue
Av~ra~e Micro Method Carbon Residue
1.04
Acid Number of Petroleum Products by Potentiometric Titration
Procedure Used A
Acid Number
0.20
Metals by ICP-AES
Procedure
Test Method B
Nickel Content
0.961
Vanadium Content
1.55
Boiling Point Distribution of Samples with Residues by High Temperature GC
Boiling Point Distrib~tion See Attached Report
Hydrogen Sulfide and Mercaptan Sulfur
H2S
< 1
Mercaptan Sulfur
164
O API
WI%
o c
eSt
psi
Vol%
oc
O F
Wt%
mg KOH/g
ppm WI
ppmWt
Page 1 of 2
688222
804 E. Nort/7 Street, Cushing, Oklahoma 74023 USA
Tel.: 918-306-4206 Fax.: 918-306-4208 Email: amerusa.cushing@intertek.com
21-Jul-2011 14:01
US180-0000069

<<<PAGE 1086>>>

) lntertek Report of Analysis I TE
IM
This report has been reviewed for accuracy, completeness, and comparison against specifications when available. The reported results are
only representative of the samples submitted for testing and are subject to confirmation upon completion of the final report, which may contain
warnings, exceptions and terms and conditions which are pertinent to the data supplied herein. It is the position of lntertek that the final report
is the prevailing document, and that the use of interim documents by the client is at their own risk. This report shall not be reproduced except in
full without written approval of the laboratory.
Signed: ____________ __,----,-------------
lntertek
Kevin Gilbert, Branch Manager
Date:
-------------------
)
Page 2 of 2
688222
804 E. North Street, Cushing, Oklahoma 74023 USA
Tel.: 918-306-4206 Fax.: 918-306-4208 Email: amerusa.cushing@intertek.com
21-Jul-2011 14:01
us 180-0000069

<<<PAGE 1087>>>

11-CUSH-76-001
Injected On: 20-Jul-11, 15:53:54 by TB
Page: 1
Procedure File: D7169 Cushing.prc
Data File: C:Chem32/1DATAID716SID7169 2011-07-20 10-49-54\006F0601.D1006F0601.CDF
Blank File: C:Chem32/DATAID71651D7169 2011-07-20 10-49.541001 F0102. D1001 F0102.CDF
Calib File:
C:ICHEM3211 DATA10628111D7169 2011-06-28 08-56-13\002F0201.DI002F0201 CDF
Solvent Exclusions: Mins
BaseLine Zero:
4.86315
Quench Region:
[0.202...0.392] Mins - QF: 1.930
Response Factor:
1.59399996846332E-6
Uncorr Total Sample Area:
5.8562E5
Corr Total Sample Area:
5.7122E5
Start Of Material (mins):
0.135
End Of Material (mins):
29.850
SOM Thrsh:
(0.00001000%)
EOM Thrsh: (0.00001000%)
Sample Weight (g):
0.1049
Solvent Weight (g):
10.5344
Material Search Restricted To: NO RESTRICTION
Material End Forced To:
NO FORCE
Warnings:
Material Bal (W1%):
92.35 Wt%
D7169 HiTemp Simulated Distillation Plot
миллени
12 04
High Temp D7169 Boiling Point Distribution
*IBP ... 94.59
1.00%... 99.75
15.00% ... 289.35
16.00%... 302.45
31.00% ... 453.88
30.00% ... 443.59
46.00%... 598,23
45.00% ... 587.53
61.00% ... 760.68
60.00%.. 749.10
76.00% ... 956.10
75.00%.. 940.58
90.00%.. 1255.40
3.00%.. 172,65
2.00% ... 157.09
18.00% ... 318.59
17.00% ... 312.97
32,00% ,.. 462.33
33.00%.. 472.97
47,00%,. 604.78
48.00% ... 615.62
62.00% ... 772.79
63.00% ... 784.26
78.00%.. 989.79
77.00% ... 973.13
91.00%.. 1285,50
92.35%.. 1327.1
92.00% ... 1315.90
4.00%.. 185.73
5.00% ... 193.21
19.00%.. 329.64
20.00% ... 342.58
35.00% ... 490.52
34.00% .... 482.33
50.00% ... 636.42
49.00%... 625.93
6.00% ... 209.31
21.00% ... 350.30
36.00% ... 501.98
51.00% … 648.47
65.00% ... 807.35
64.00%.. 795.49
79.00% ... 1007.20
66.00% ... 819.25
80.00% ... 1026.40
FBP
>1328
81.00% ... 1046.00
%Recovery: 92.35
% Residue - 7.65
8.00% ... 227.37
7.00% ... 213.05
22.00%:.. 358.87
23,00%.. 372.53
37.00%.. 510.42
38.00% ... 519.73
53.00% … 670.16
52.00% 658.18
67.00%.. 831.35
68.00%.. 844.10
83.00% ... 1085.90
82.00% 1065.20
10.00% ... 244.13
9.00% ... 237.75
24.00%... 383.98
25.00% ... 391.82
40.00% ... 540.69
39.00%.. 529.89
54.00%.. 680.44
11.00% ... 258.96
26.00%.. 404.07
41.00%... 549.82
55.00% ... 692.37
69.00% 857.26
56.00%... 702.68
70.00% ... 871.12
84.00%.. 1107.00
71.00%.. 884.35
86.00%... 1152.50
85.00% ... 1129.40
13.00%.. 273.62
12.00%.. 267.04
27.00% ..416.33
28.00% ... 423.31
43.00% ... 570.35
42.00% .560.59
58.00%.. ..725.22
57.00%.. 714.43
72.00%.. 897.87
73.00% ... 912.17
88.00% ... 1199.10
87.00%.. 1175.20
14.00% ... 278.80
29.00% ... 432.55
44,00% 577.86
59.00% ... 736.58
74.00% ... 926.80
Warning:
Items preceded by * denote material eluted prior to the earliest retention time or later than the latest retention time in the current calibration
89.00%... 1224.40
High Temp D7169 Cut Point Distribution
Cut Point Range
..% Off
Cut Point #1 ~ (54.00 - 220.00]-l-0,000 - 1.003Min.] ~ 7.2225%
Cut Point #3 - (1020.00 - 1641.00)- 20.052 - 40.297 Min.] - 12,6697%
Cut Point #2 ~ [220.00 - 1020.00] [1.003 - 20.052Min.] ~ 72.4565%
Simdist-2000
7/20/20114:43:28 PM

<<<PAGE 1088>>>

11 -CUSH-76-002
Injected On: 20-Jul-11, 16:42:59 by TB Data File: C.\Chem32\1\0ATA\07169107169 2011·07·20 10-49-54\007F0701 .DI007F0701 COF
Blank File: C:IChem3211 IOATAI071691 07169 2011-07-20 10-49-541001 F01 02.01001 F01 02.COF
Calib File: C:ICHEM321110ATAI062811107169 2011-06-28 08·58-131002F0201 .D\002F0201 .COF
Solvent Exclusions: Mins
Quench Region: [0.202 .. . 0.392] Mins - QF: 1 .930
Uncorr Total Sample Area: 6.0276E5
Corr Total Sample Area: 5.9333E5
Page: 1
Procedure File: 0 7169 Cushing.prc
BaseLine Zero:
Response Factor:
4.90957
1.59399996846332E-6
Start Of Material (mins): 0.135 End Of Material (mins) : 29.883
SOM Thrsh: (0.00001000%) EOM Thrsh: (0.00001000%)
Material Search Restricted To: NO RESTRICTION
Material End Forced To: NO FORCE
Warnings:
D7169 HiTemp Simulated Distillation Plot
Sample Weight (g)
Solvent Weight (g):
0.1044
10.4698
Material Bal (Wt%):
95.79 Wt%
· ~
.. ,
High Temp D7169 Boiling Point Distribution
*IBP ... 87.79 15.00% ... 222.82 30.00% ... 344.12
*1 .00% .. . 93 .70 16.00%. . 228.61 31.00% .. . 351 .68
45.00% ... 488.48
60.00% ... 643.68
75.00% ... 832.62
90.00% ... 1110.00
46.00% ... 498.31
61.00% .. . 654.35
76.00% -
. 846.78
91 .00% ... 1138.70
2.00% . . 97.10 17.00% ... 238.10 32.00% . . 360.08
47.00% - - 508.51
62.00% ... 667.65
77.00% ... 861 .66
92.00% -- · 1169.70
3.00% . . 99.62 18.00% ... 240.99 33.00% ... 372.94
48.00% ... 518.63
63.00% ... 678.90
78.00% ... 876.70
93.00% ... 1203.20
4.00% ... 147.47 19.00% -
. 248.10 34.00% .. . 383.72
49.00% ... 527.76
64.00% . . 692.27
79.00% -- - 891.50
94.00% .
- 1243.70
5.00% ... 155.78 20.00% ... 259.40 35.00% ... 390.46
50.00% ... 539.34
65.00% ... 703.64
80.00% ... 906.91
95.00% ... 1290.80
6.00% 160.30 21 .00% - - 266.60 36.00% ... 402.08
7.00% ·- - 166.52 22.00% ... 273.76 37.00% .. 412.93
8.00% ... 176.17 23.00% ... 280.54 38.00% 421.49
9 .00% .. 186.46 24.00% 288.75 39.00% .. . 430.19
51 .00% ... 549.36
66.00% .. 716.00
81 .00% - - 922.98
95.79% ... 1328.1
52.00% 560.87
67.00% ... 728.91
82.00%-- -938.18
FBP >1328
53.00% ... 571 .36
54 .00% .. 578.32
68.00%- . 741.59
69.00% ... 754.86
83.00% -- - 955.25
84 .00% --- 974.34
% Residue - 4.21
%Recovery: 95.79
10.00% ... 192.12 25.00% ... 300.50 40.00% ... 440.63
11 .00% .. . 196.79 26.00% ... 304.53 41 .00%- . 450.23
55.00% ... 588.86
70.00% ... 768.20
85.00% ... 993.43
56.00% ... 599.90
71.00% --- 780.79
86.00% ... 1013.60
12.00% ... 209.66 27.00% ... 316.26 42 .00% ... 457 .98
57.00% ... 608.43
72.00% .. . 792.83
87.00% .
- 1036.50
13.00% ... 211.16 28.00% .. 324.45 43 .00% ... 469 .80
58.00% ... 620.73
73.00% ... 806.05
88.00% ... 1059.40
14.00% . . 212.54 29.00% ... 331 .80 44 .00% ... 479.64
59.00% ... 630.30
74.00% ... 819.25
89.00% - - 1083.80
Warning: Items preceded by • denote material eluted prior to the earliest retention time or later than the latest retention time in the current calibration
High Temp D7169 Cut Point Distribution
Cut Point Range ... % Off
Cut Point #1- [54.00 · 220.00]-[·0.000 - 1.003Min.]- 14.7639%
Cut Point #2- [220.00- 1020.00]-[1.003- 20.052Min.] -71 .5183%
Cut Point #3- [1020.00 -1641.00]-[20.052- 40.297Min.]- 9.5097%
Simdist-2000 7/21/2011 8:20:52 AM

<<<PAGE 1089>>>

Whole Crude Analysis
CRUDE : Eagleford
LOCATION : Texas
REPRESENTATIVE OF :
REPORT NO. : U2010.011
LAB WORK BY : Clinton Assay Lab
CONTACT : EMRE F. Hagardorn
REPORT BY : EMRE B. J. Throop
REPORT DATE: Prepared for external release on August 23, 2010
APPROVED BY : EMRE M. D. Monahan
EMRE F. Hagardorn
EMRE M Hamrick
ASSAY COMMENTS:
This assay information is provided to you courtesy of ExxonMobil Research and Engineering Company (EMRE) and is based on a range of data and information. While care has been
taken in preparing these materials, no representations, warranties or guarantees are made as to their accuracy, reliability, quality, correctness or completeness. Each user must make its
own determination and judgment on applying any information in this assay. Any and all use of this information shall be the sole responsibility of the user, and the user releases EMRE,
parent and its affiliates from any and all claims arising from its use and shall defend and hold EMRE, its parent and its affiliates harmless from any third party claims arising from the
user's application or use of the assay information.

<<<PAGE 1090>>>

TABLE 1 WHOLE CRUDE PROPERTIES (DRY BASIS)
CRUDE Eagleford
DATE August 19, 2010
CRUDE BALANCE
GRAVITY API 40.1 40.4
SPECIFIC GRAVITY 60/60 .8246 .8229
SULFUR WGT% 0.13 0.13
MERCAPTAN SULFUR WGT PPM <2
POUR POINT DEG F 24
NITROGEN WGT % 0.034 0.032
BASIC NITROGEN WGT % 0.006 0.006
CON CARBON WGT % 0.54 0.53
SALT CONTENT PTB
REID VAPOR PRESSURE PSI 2.8
NEUT. NUMBER MG KOH/GM 0.05 0.05
H2S DISSOLVED WGT PPM 0
H2O BY DISTILLATION VOL % 0.00
VANADIUM WGT PPM 0.10 0.06
NICKEL WGT PPM 0.20 0.05
VISCOSITIES DEG F DEG C CRUDE
CST AT 40 4.4 10.05
60 15.6 6.98
77 25.0 5.35
80 26.7 5.12
100 37.8 3.93
104 40.0 3.74
122 50.0 3.06
140 60.0 2.56
LIGHT HYDROCARBONS % ON CRUDE
VOLUME% WEIGHT%
ETHANE 0.00 0.00
PROPANE 0.19 0.12
ISOBUTANE 0.16 0.11
NORMAL BUTANE 0.80 0.57
ISOPENTANE 0.79 0.61
NORMAL PENTANE 1.32 1.02
VOLUME % DISTILLED AT 10 DEGREE F INTERVALS
DEG F 0 10 20 30 40 50 60 70 80 90
0 0.18 0.24 0.30 0.42 0.60 0.78 0.95 1.16 1.51 1.85
100 2.36 2.86 3.52 4.34 5.17 6.02 6.88 7.76 8.67 9.59
200 10.53 11.49 12.47 13.48 14.51 15.56 16.63 17.73 18.85 19.99
300 21.15 22.34 23.54 24.77 26.01 27.28 28.55 29.84 31.14 32.45
400 33.76 35.08 36.39 37.70 39.00 40.29 41.57 42.84 44.09 45.32
500 46.53 47.72 48.89 50.05 51.18 52.30 53.40 54.49 55.56 56.62
600 57.66 58.68 59.69 60.69 61.67 62.64 63.60 64.54 65.48 66.40
700 67.31 68.21 69.09 69.97 70.83 71.68 72.52 73.35 74.16 74.96
800 75.75 76.53 77.30 78.05 78.80 79.53 80.25 80.97 81.67 82.36
900 83.04 83.71 84.37 85.02 85.66 86.29 86.92 87.53 88.13 88.71
1000 89.28 89.84 90.37 90.89 91.40 91.88 92.35

<<<PAGE 1091>>>

TABLE 1A
Eagleford
Balance Whole Crude
GRAVITY API 40.4 40.1
SPECIFIC GRAVITY 60/60 0.8246
SULFUR WGT% 0.13
Ni WGT PPM 0.20
V WGT PPM 0.10
POUR POINT DEG F 24
WATER VOL% 0.00
Fraction Wt % Crd Cum Wt % Vol % Crd Cum Vol % API Gravity
-200/160 160/360 360/530 530/650 650/1049 1049/FBP 5.4 5.4 20.1 25.5 21.2 46.7 12.8 59.6 31.3 90.8 9.2 100.0 6.9 6.9
21.7 28.6 21.5 50.1 12.6 62.6 29.2 91.8 8.2 100.0 53.9
42.5
37.3
29.1
21.7
z
VOL % ON CRUDE
8.2%
6.9%
21.7%
-200/160
160/360
360/530
530/650
650/1049
1049/FBP
29.2%
21.5%
12.6%

<<<PAGE 1092>>>

TABLE 2 CUT QUALITIES Eagleford 40.1 API
------- TEMP ------- -- NORMALIZED VOLUME % -- ------- GRAVITY ------- -- NORMALIZED WEIGHT % -- MERC RI --------------------- DEG F ---------------------- VOL %
DEG DEG ON DEG SPEC ON SULFUR SULF AT 67 ANIL PER 10
F C CRUDE CUM MID API 60/60 CRUDE CUM MID WGT % PPM DEG C PT. POUR CLOUD FREEZE DEG F
-175 -115 0.00 0.00 0.00 246.8 0.3740 0.00 0.00
0 -18 0.18 0.18 0.09 147.0 0.5081 0.11 0.11
25 -4 0.15 0.33 0.25 119.8 0.5631 0.10 0.21
68 20 0.77 1.10 0.71 110.8 0.5840 0.54 0.76
90 32 0.76 1.85 1.47 94.9 0.6250 0.57 1.33
115 46 1.26 3.11 2.48 92.7 0.6311 0.97 2.30
158 70 3.59 6.71 4.91 77.5 0.6769 2.95 5.25 3.78 0.0002 <2 185 85 2.42 9.12 7.91 69.5 0.7040 2.07 7.32 6.29 0.0003 <2 212 100 2.56 11.68 10.40 63.5 0.7258 2.26 9.58 8.45 0.0004 2 248 120 3.66 15.34 13.51 57.6 0.7483 3.33 12.91 11.25 0.0005 2 275 135 2.94 18.28 16.81 53.0 0.7668 2.74 15.65 14.28 0.0007 3 0.8349
0.8963
0.9481
1.0167
1.0889
302 150 3.10 21.38 19.83 50.0 0.7795 2.94 18.59 17.12 0.0008 3 1.1481
320 160 2.16 23.54 22.46 48.1 0.7880 2.07 20.65 19.63 0.0010 3 1.4181 129.1 -107 -101 -94 1.2000
347 175 3.35 26.90 25.22 46.5 0.7948 3.24 23.89 22.27 0.0012 3 1.4204 133.3 -97 -90 -84 1.2407
374 190 3.47 30.36 28.63 45.1 0.8011 3.37 27.26 25.58 0.0016 3 1.4232 138.3 -85 -78 -71 1.2852
401 205 3.53 33.89 32.13 44.1 0.8059 3.46 30.72 28.99 0.0020 3 1.4261 143.2 -73 -65 -58 1.3074
428 220 3.54 37.44 35.67 43.3 0.8096 3.49 34.21 32.47 0.0026 3 1.4290 148.1 -61 -52 -45 1.3111
455 235 3.50 40.93 39.19 42.6 0.8129 3.45 37.66 35.94 0.0033 4 1.4320 153.1 -48 -39 -32 1.2963
482 250 3.40 44.34 42.63 41.8 0.8164 3.37 41.04 39.35 0.0046 4 1.4349 158.3 -35 -26 -19 1.2593
509 265 3.27 47.60 45.97 41.0 0.8204 3.26 44.30 42.67 0.0085 4 1.4379 163.6 -22 -13 -7 1.2111
536 280 3.13 50.73 49.17 40.0 0.8249 3.14 47.43 45.87 0.0227 4 1.4408 168.9 -9 0 6 1.1593
563 295 3.00 53.73 52.23 39.0 0.8300 3.03 50.46 48.95 0.0570 4 1.4436 174.2 4 12 18 1.1111
590 310 2.88 56.62 55.18 37.9 0.8355 2.93 53.39 51.93 0.1062 1.4464 179.4 16 24 617 325 2.77 59.39 58.00 36.6 0.8416 2.84 56.22 54.81 0.1539 1.4490 184.3 28 35 650 343 3.25 62.64 61.02 35.2 0.8490 3.35 59.58 57.90 0.1916 1.4518 189.2 41 47 671 355 2.00 64.64 63.64 33.9 0.8556 2.08 61.65 60.62 0.2140 1.4542 193.1 51 57 1.0667
1.0259
0.9848
0.9524
698 370 2.49 67.13 65.88 32.7 0.8616 2.61 64.26 62.96 0.2309 1.4563 196.4 60 65 725 385 2.41 69.53 68.33 31.6 0.8674 2.54 66.80 65.53 0.2459 1.4585 199.8 68 752 400 2.32 71.85 70.69 30.8 0.8718 2.46 69.25 68.03 0.2570 1.4607 203.3 76 779 415 2.23 74.08 72.97 30.2 0.8749 2.37 71.62 70.44 0.2645 1.4628 206.8 82 806 430 2.14 76.22 75.15 29.8 0.8773 2.28 73.91 72.76 0.2690 1.4649 210.7 88 0.9222
0.8926
0.8593
0.8259
0.7926
833 445 2.06 78.28 77.25 29.4 0.8796 2.20 76.10 75.01 0.2713 1.4669 215.2 93 851 455 1.33 79.61 78.94 28.9 0.8820 1.42 77.52 76.81 0.2721 1.4687 219.3 96 887 475 2.55 82.15 80.88 28.2 0.8858 2.74 80.26 78.89 0.2726 1.4707 225.1 100 914 490 1.82 83.97 83.06 27.4 0.8906 1.97 82.24 81.25 0.2737 1.4732 232.5 104 950 510 2.32 86.29 85.13 26.6 0.8948 2.52 84.76 83.50 0.2769 1.4756 240.1 107 0.7630
0.7389
0.7083
0.6741
0.6444
968 520 1.11 87.41 86.85 26.1 0.8979 1.22 85.98 85.37 0.2823 1.4779 246.4 110 995 535 1.59 89.00 88.21 25.7 0.9002 1.74 87.72 86.85 0.2897 1.4797 251.2 112 1022 550 1.48 90.48 89.74 25.2 0.9030 1.62 89.34 88.53 0.3010 1.4821 256.6 114 1049 565 1.36 91.83 91.16 24.7 0.9059 1.49 90.83 90.09 0.3126 1.4845 261.7 117 FBP FBP 8.17 100.00 21.7 0.9240 9.17 100.00 0.3714 46
0.6167
0.5889
0.5481
0.5037

<<<PAGE 1093>>>

TABLE 2A CUT QUALITIES Eagleford 40.1 API
TEMP MID ----------------- CENTISTOKES AT ------------------- SMOKE LUMIN NEUT ------- VOLUME % ------- ----------- WEIGHT % ------------- --------------- WEIGHT PPM -----------------
F VOL % -30 F 100 F 150 F 210 F MM NO NO PARA NAPH AROM N2 BN2 CCAR FE NI V NA
185 7.91 64.7 30.6 4.7
212 10.40 55.8 38.6 5.6
248 13.51 55.1 33.5 11.4
275 16.81 57.8 28.2 14.0
302 19.83 51.8 29.8 18.4
320 22.46 2.22 0.80 0.63 0.49 30.8 71 52.6 29.4 18.0
347 25.22 2.73 0.90 0.69 0.54 29.9 69 53.9 26.8 19.3
374 28.63 3.59 1.03 0.78 0.60 28.7 66 52.0 32.1 15.9
401 32.13 4.90 1.19 0.88 0.66 27.6 63 42.0 46.0 12.0
428 35.67 6.97 1.40 1.01 0.74 26.4 60 0.04 41.7 44.7 13.6
455 39.19 10.33 1.65 1.16 0.83 25.2 57 0.04 49.0 36.1 14.9 0.000 0.000
482 42.63 15.88 1.97 1.34 0.94 24.0 54 0.05 50.6 33.4 16.0 0.000 0.000
509 45.97 25.39 2.37 1.55 1.06 22.7 51 0.06 51.3 34.0 14.6 0.000 0.000
536 49.17 42.53 2.90 1.80 1.20 21.5 48 0.07 53.8 33.6 12.5 0.001 0.000
563 52.23 73.11 3.56 2.11 1.36 20.2 45 0.09 53.6 33.1 13.2 0.001 0.000
590 55.18 4.43 2.49 1.54 0.10 0.003 0.001
617 58.00 5.59 2.98 1.77 0.11 0.006 0.001
650 61.02 7.25 3.65 2.06 0.11 0.013 0.003
671 63.64 9.12 4.36 2.37 0.10 0.022 0.004 <0.005 <0.1 <0.1 <0.1 <0.1
698 65.88 11.29 5.15 2.70 0.09 0.032 0.005 <0.005 <0.1 <0.1 <0.1 <0.1
725 68.33 14.32 6.22 3.14 0.08 0.043 0.005 0.01 <0.1 <0.1 <0.1 <0.1
752 70.69 18.21 7.53 3.65 0.07 0.051 0.005 0.01 <0.1 <0.1 <0.1 <0.1
779 72.97 23.25 9.15 4.27 0.07 0.057 0.006 0.02 <0.1 <0.1 <0.1 <0.1
806 75.15 29.82 11.17 5.01 0.06 0.059 0.007 0.03 <0.1 <0.1 <0.1 <0.1
833 77.25 38.51 13.72 5.91 0.06 0.059 0.008 0.04 <0.1 <0.1 <0.1 <0.1
851 78.94 47.97 16.36 6.80 0.05 0.059 0.009 0.07 <0.1 <0.1 <0.1 <0.1
887 80.88 62.80 20.28 8.07 0.05 0.060 0.010 0.12 <0.1 <0.1 <0.1 <0.1
914 83.06 87.20 26.34 9.92 0.05 0.061 0.012 0.21 <0.1 <0.1 <0.1 <0.1
950 85.13 122.51 34.51 12.27 0.04 0.063 0.013 0.34 <0.1 <0.1 <0.1 0.1
968 86.85 166.14 43.94 14.83 0.04 0.066 0.015 0.49 0.1 <0.1 <0.1 0.3
995 88.21 215.45 53.97 17.42 0.04 0.068 0.016 0.62 0.1 <0.1 <0.1 0.4
1022 89.74 297.69 69.69 21.27 0.03 0.072 0.017 0.77 0.1 0.1 0.1 0.6
1049 91.16 416.26 90.82 26.14 0.03 0.076 0.019 0.89 0.1 0.1 0.1 0.8
FBP 3511.28 487.79 96.01 0.02 0.150 0.033 5.06 4.3 0.5 0.6 10.0

<<<PAGE 1094>>>

TABLE 3 CALCULATED BLENDS Eagleford 40.1 API
TEMP RANGE CUT RANGE VOLUME % API SPEC WGT % ABP SULFUR MERC RI ----------------- DEG F ------------------ DIE CI 90 SMK LUM NEUT
DEG F DEG C VOLUME % YIELD MID GRAV GRAV YIELD F WGT% PPM 67 C ANIL POUR CLD FRZ IND IND MM NO. NO.
68/158 20/70 1.1/6.7 5.6 3.9 83.0 0.6596 4.5
68/185 20/85 1.1/9.1 8.0 5.1 78.8 0.6730 6.6
68/212 20/100 1.1/11.7 10.6 6.4 74.8 0.6858 8.8
68/248 20/120 1.1/15.3 14.3 8.2 70.1 0.7018 12.2
68/302 20/150 1.1/21.4 20.3 11.2 64.2 0.7231 17.8
68/374 20/190 1.1/30.4 29.3 15.7 58.4 0.7453 26.5
158/212 70/100 6.7/11.7 5.0 9.2 66.3 0.7152 4.3 185 0.0004 2
158/650 70/343 6.7/62.6 55.9 34.7 45.6 0.7992 54.3 404 0.0317
185/302 85/150 9.1/21.4 12.3 15.3 55.7 0.7559 11.3 244 0.0006 2
212/248 100/120 11.7/15.3 3.7 13.5 57.6 0.7483 3.3 230 0.0005 2
212/302 100/150 11.7/21.4 9.7 16.5 53.7 0.7639 9.0 257 0.0007 3
248/302 120/150 15.3/21.4 6.0 18.4 51.5 0.7733 5.7 275 0.0008 3
248/374 120/190 15.3/30.4 15.0 22.9 48.4 0.7866 14.4 311 0.0011 3
302/374 150/190 21.4/30.4 9.0 25.9 46.4 0.7956 8.7 338 0.0013 3 1.4209 134.2 -94 -87 -80 62 34 30 68
302/401 150/205 21.4/33.9 12.5 27.6 45.7 0.7985 12.1 352 0.0015 3 1.4224 136.7 -87 -79 -73 62 37 29 67
302/455 150/235 21.4/40.9 19.6 31.2 44.7 0.8031 19.1 379 0.0020 3 1.4253 141.7 -73 -63 -56 63 41 28 64
302/509 150/265 21.4/47.6 26.2 34.5 43.9 0.8070 25.7 406 0.0032 3 1.4281 146.7 -57 -46 -39 64 46 27 61 0.04
302/536 150/280 21.4/50.7 29.4 36.1 43.4 0.8089 28.9 419 0.0053 3 1.4295 149.2 -49 -37 -31 65 47 26 60 0.04
302/698 150/370 21.4/67.1 45.7 44.3 40.7 0.8217 45.7 500 0.0605 1.4368 163.1 -1 13 66 53 320/650 160/343 23.5/62.6 39.1 43.1 41.2 0.8193 38.9 485 0.0440 1.4357 161.1 -12 1 66 53 347/698 175/370 26.9/67.1 40.2 47.0 39.9 0.8257 40.4 523 0.0683 1.4391 166.9 4 17 67 55 0.06
0.06
0.07
374/482 190/250 30.4/44.3 14.0 37.4 42.9 0.8111 13.8 428 0.0031 3 1.4305 150.6 -52 -43 -36 65 48 26 59 0.04
374/536 190/280 30.4/50.7 20.4 40.6 42.2 0.8147 20.2 455 0.0070 4 1.4332 155.8 -37 -27 -21 66 52 25 56 0.05
401/509 205/265 33.9/47.6 13.7 40.8 42.2 0.8147 13.6 455 0.0047 4 1.4334 155.7 -40 -30 -24 66 52 25 56 0.05
401/650 205/343 33.9/62.6 28.8 48.3 39.8 0.8260 28.9 526 0.0588 1.4401 168.3 -1 10 67 58 428/536 220/280 37.4/50.7 13.3 44.1 41.4 0.8185 13.2 482 0.0095 4 1.4363 161.0 -27 -17 -11 67 56 23 53 0.06
509/590 265/310 47.6/56.6 9.0 52.1 39.0 0.8300 9.1 550 0.0610 1.4435 174.0 5 13 68 64 509/650 265/343 47.6/62.6 15.0 55.1 37.7 0.8362 15.3 580 0.1069 1.4463 179.2 19 27 68 66 536/650 280/343 50.7/62.6 11.9 56.7 37.1 0.8392 12.1 593 0.1287 1.4478 181.9 25 32 68 67 590/650 310/343 56.6/62.6 6.0 59.6 35.8 0.8456 6.2 620 0.1743 1.4505 186.9 36 42 67 70 590/698 310/370 56.6/67.1 10.5 61.9 34.7 0.8513 10.9 644 0.1955 1.4526 190.4 45 52 66 70 0.07
0.09
0.09
0.10
0.11
0.10
650/698 343/370 62.6/67.1 4.5 64.9 33.2 0.8590 4.7 674 0.2234 1.4553 194.9 56 62 65 72 650/752 343/400 62.6/71.9 9.2 67.3 32.2 0.8644 9.7 701 0.2378 1.4575 198.3 65 650/851 343/455 62.6/79.6 17.0 71.1 31.0 0.8706 18.0 751 0.2521 1.4611 204.7 77 650/1049 343/565 62.6/91.8 29.2 77.2 29.1 0.8810 31.3 850 0.2660 1.4677 218.0 93 752/851 400/455 71.9/79.6 7.8 75.7 29.7 0.8780 8.3 802 0.2688 1.4655 212.3 89 779/995 415/535 74.1/89.0 14.9 81.5 27.9 0.8878 16.1 887 0.2753 1.4717 228.1 101 851/950 455/510 79.6/86.3 6.7 83.0 27.5 0.8902 7.2 901 0.2744 1.4731 232.3 104 851/1049 455/565 79.6/91.8 12.2 85.7 26.5 0.8955 13.3 950 0.2847 1.4767 242.3 108 950/1049 510/565 86.3/91.8 5.5 89.1 25.4 0.9019 6.1 1000 0.2969 1.4812 254.3 114 995/1049 535/565 89.0/91.8 2.8 90.4 25.0 0.9044 3.1 1022 0.3066 1.4833 259.0 116 64 64 63 63 64 64 64 65 65 0.09
0.09
0.07
0.06
0.06
0.05
0.05
0.04
0.03
0.03
1049/FBP 565/FBP 91.8/100.0 8.2 21.7 0.9240 9.2 0.3714 46 0.02
995/FBP 535/FBP 89.0/100.0 11.0 22.5 0.9189 12.3 0.3550 56 950/FBP 510/FBP 86.3/100.0 13.7 23.1 0.9150 15.2 0.3417 64 851/FBP 455/FBP 79.6/100.0 20.4 24.5 0.9069 22.5 0.3201 72 752/FBP 400/FBP 71.9/100.0 28.2 25.9 0.8989 30.8 0.3063 77 698/FBP 370/FBP 67.1/100.0 32.9 26.7 0.8947 35.7 0.2986 79 650/FBP 343/FBP 62.6/100.0 37.4 27.4 0.8904 40.4 0.2899 81 563/FBP 295/FBP 53.7/100.0 46.3 29.1 0.8812 49.5 0.2646 84 428/FBP 220/FBP 37.4/100.0 62.6 32.0 0.8654 65.8 0.2038 93 0.02
0.03
0.03
0.04
0.05
0.05
0.06
0.06

<<<PAGE 1095>>>

TABLE 3A CALCULATED BLENDS Eagleford 40.1 API
RANGE CUT RANGE ----------- VISCOSITY IN CENTISTOKES AT ------------- --------- VOLUME % --------- ----------------------- WEIGHT % -------------------- --------------- WEIGHT PPM ----------------
DEG F VOLUME % -30 F 100 F 150 F 210 F PARA NAPH AROM AR NR N2 BN2 CCAR FE NI V NA
68/158 1.1/6.7
68/185 1.1/9.1
68/212 1.1/11.7
68/248 1.1/15.3
68/302 1.1/21.4
68/374 1.1/30.4
158/212 6.7/11.7 60.2 34.7 5.2
158/650 6.7/62.6 51.8 34.0 14.1
185/302 9.1/21.4 55.1 32.4 12.6
212/248 11.7/15.3 55.1 33.5 11.4
212/302 11.7/21.4 54.9 30.7 14.4
248/302 15.3/21.4 54.7 29.0 16.3
248/374 15.3/30.4 53.6 29.3 17.1
302/374 21.4/30.4 2.87 0.92 0.71 0.55 52.9 29.5 17.7 13.6 19.1
302/401 21.4/33.9 3.32 0.99 0.76 0.58 49.8 34.1 16.1 12.0 21.6
302/455 21.4/40.9 4.57 1.16 0.86 0.65 48.2 36.4 15.4 10.9 23.5
302/509 21.4/47.6 6.43 1.35 0.98 0.73 48.9 35.7 15.4 10.9 22.9
302/536 21.4/50.7 7.67 1.47 1.05 0.77 49.4 35.5 15.1 10.6 22.6
302/698 21.4/67.1 2.33 1.53 1.05 10.1 20.8
320/650 23.5/62.6 2.14 1.43 1.00 14.9 9.8 21.3
347/698 26.9/67.1 2.69 1.71 1.15 9.5 21.2
374/482 30.4/44.3 8.46 1.52 1.08 0.79 45.8 40.1 14.1 9.4 25.8
374/536 30.4/50.7 12.55 1.80 1.24 0.88 47.9 38.1 13.9 9.2 24.1
401/509 33.9/47.6 12.64 1.80 1.24 0.88 48.1 37.2 14.8 9.9 24.1
401/650 33.9/62.6 2.83 1.77 1.18 14.7 9.3 21.0
428/536 26.9/50.7 19.67 2.15 1.43 0.99 51.1 34.3 14.6 9.8 21.9 0.000 0.000
509/590 47.6/56.6 3.54 2.10 1.35 13.2 8.0 19.1 0.002 0.000
509/650 47.6/62.6 4.44 2.50 1.55 8.7 18.3 0.005 0.001
536/650 50.7/62.6 5.02 2.75 1.66 8.9 17.9 0.006 0.001
590/650 56.6/62.6 6.42 3.32 1.92 9.6 17.3 0.010 0.002
590/698 56.6/67.1 7.80 3.86 2.16 10.1 17.3 0.017 0.003
650/698 62.6/67.1 10.25 4.78 2.55 10.7 17.4 0.027 0.004 <0.005 <0.1 <0.1 <0.1 <0.1
650/752 62.6/71.9 12.85 5.71 2.94 11.0 17.2 0.037 0.005 0.01 <0.1 <0.1 <0.1 <0.1
650/851 62.6/79.6 19.12 7.84 3.78 10.9 16.6 0.047 0.006 0.02 <0.1 <0.1 <0.1 <0.1
650/1049 62.6/91.8 40.57 14.25 6.08 11.1 15.3 0.055 0.009 0.20 <0.1 <0.1 <0.1 0.1
752/851 71.9/79.6 32.03 11.83 5.25 10.9 15.9 0.058 0.007 0.04 <0.1 <0.1 <0.1 <0.1
779/995 74.1/89.0 70.70 22.24 8.66 11.0 14.6 0.062 0.011 0.22 <0.1 <0.1 <0.1 0.1
851/950 79.6/86.3 86.08 26.06 9.83 11.0 14.3 0.061 0.012 0.22 <0.1 <0.1 <0.1 <0.1
851/1049 79.6/91.8 139.12 38.10 13.25 11.3 13.5 0.066 0.014 0.44 <0.1 <0.1 <0.1 0.3
950/1049 86.3/91.8 260.04 62.60 19.56 11.6 12.6 0.071 0.017 0.70 0.1 0.1 <0.1 0.5
995/1049 89.0/91.8 348.91 79.00 23.45 11.7 12.0 0.074 0.018 0.83 0.1 0.1 0.1 0.7
1049/FBP 91.8/100.0 3511.28 487.79 96.01 0.150 0.033 5.06 4.3 0.5 0.6 10.0
995/FBP 89.0/100.0 1827.97 290.94 64.30 0.131 0.029 3.99 3.3 0.4 0.4 7.7
950/FBP 86.3/100.0 1117.56 197.07 47.51 0.118 0.026 3.32 2.6 0.3 0.4 6.2
851/FBP 79.6/100.0 439.33 94.01 26.68 0.100 0.022 2.32 1.8 0.2 0.2 4.3
752/FBP 71.9/100.0 193.06 48.87 15.97 0.089 0.018 1.71 1.3 0.2 0.2 3.1
698/FBP 67.1/100.0 126.59 34.92 12.25 0.083 0.016 1.47 1.1 0.1 0.2 2.7
650/FBP 62.6/100.0 87.88 26.14 9.75 0.077 0.015 1.30 1.0 0.1 0.1 2.4
563/FBP 53.7/100.0 45.94 15.71 6.55 0.064 0.012 1.06
428/FBP 37.4/100.0 17.37 7.42 3.68 0.048 0.009 0.80

<<<PAGE 1096>>>

TABLE 4 GASOLINES & NAPHTHAS Eagleford 40.1 API
15/5 CUT POINTS DEG F VT 68/158 68/212 158/212 212/302 248/374 302/374 158/302
DEG C VT 20/70 20/100 70/100 100/150 120/190 150/190 70/150
YIELD CUT RANGE VOL % 1.1/6.7 1.1/11.7 6.7/11.7 11.7/21.4 15.3/30.4 21.4/30.4 6.7/21.4
YIELD ON CRUDE VOL % 5.6 10.6 5.0 9.7 15.0 9.0 14.7
MIDPOINT VOL % 3.9 6.4 9.2 16.5 22.9 25.9 14.1
GRAVITY API 83.0 74.8 66.3 53.7 48.4 46.4 57.8
SPECIFIC GRAVITY 60/60 0.6596 0.6858 0.7152 0.7639 0.7866 0.7956 0.7474
DENSITY AT 15 C KG/DM3 0.6592 0.6853 0.7146 0.7632 0.7859 0.7948 0.7467
TOTAL SULFUR WGT % 0.0004 0.0007 0.0011 0.0013 0.0006
MERCAPTAN SULFUR WGT PPM 2 3 3 3 2
REID VAPOR PRESSURE PSI 2.80 0.70 1.50
ANILINE POINT DEG F 134.2
RESEARCH OCTANE NUMBER
CLEAR 70.1 62.3 53.3 46.2 42.8 41.8 48.0
PARAFFINS VOL % NAPHTHENES VOL % AROMATICS VOL % 60.2 54.9 53.6 52.9 56.7
34.7 30.7 29.3 29.5 32.1
5.2 14.4 17.1 17.7 11.3
CARBON WGT % 83.80 84.39 85.00 85.72 85.88 85.92 85.49
HYDROGEN WGT % 16.20 15.61 15.00 14.28 14.12 14.08 14.51
YIELD ON CRUDE WGT % 4.5 8.8 4.3 9.0 14.4 8.7 13.3

<<<PAGE 1097>>>

TABLE 5 HYDROCARBON ANALYSIS Eagleford 40.1 API
15/5 CUT POINT DEG F VT IBP TO 68 YIELD CUT RANGE VOL % 0.0 TO 1.1 YIELD CUT RANGE WT% 0.0 TO 0.8
15/5 CUT POINT DEG C VT IBP TO 20 YIELD ON CRUDE VOL % 1.10 YIELD ON CRUDE WT% 0.76
% ON CUT % ON CUT % ON CUT
COMPONENT VOL WGT COMPONENT VOL WGT COMPONENT VOL WGT
METHANE 0.00 0.00
ETHANE 0.15 0.10
PROPANE 16.95 15.14
ISOBUTANE 14.43 14.29
N-BUTANE 67.04 68.91
ISOPENTANE 1.42 1.56
N-PENTANE 0.00 0.00
CYCLOPENTANE 0.00 0.00
2,2-DIMETHYLBUTANE 0.00 0.00
2,3-DIMETHYLBUTANE 0.00 0.00
2-METHYLPENTANE 0.00 0.00
3-METHYLPENTANE 0.00 0.00
N-HEXANE 0.00 0.00
METHYLCYCLOPENTANE 0.00 0.00
BENZENE 0.00 0.00
CYCLOHEXANE 0.00 0.00
2,2-DIMETHYLPENTANE 0.00 0.00
2,4-DIMETHYLPENTANE 0.00 0.00
2,2,3-TRIMETHYLBUTANE 0.00 0.00
2-METHYLHEXANE 0.00 0.00
c+t-1,3-DiMe-Cyclopentanes 0.00 0.00
3-METHYLHEXANE 0.00 0.00
c+t-1,2-DiMe-Cyclopentanes 0.00 0.00
N-HEPTANE 0.00 0.00
METHYLCYCLOHEXANE 0.00 0.00
TOLUENE 0.00 0.00
VOL % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
0.00 0.15 16.95 67.04 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.43 1.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.15 16.95 81.47 1.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.15 16.95 81.47 1.42 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84.15
15.85
100.00
0.00
0.00
0.00
0.00
100.0
WGT % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
0.00 0.10 15.14 68.91 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 14.29 1.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 15.14 83.20 1.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.10 15.14 83.20 1.56 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 84.15
15.85
100.00
0.00
0.00
0.00
0.00
100.0
GC component subset and carbon number data from simulating 15/5 tower cuts

<<<PAGE 1098>>>

TABLE 6 HYDROCARBON ANALYSIS Eagleford 40.1 API
15/5 CUT POINT DEG F VT 68 TO 158 YIELD CUT RANGE VOL % 1.1 TO 6.7 YIELD CUT RANGE WT% 0.8 TO 5.3
15/5 CUT POINT DEG C VT 20 TO 70 YIELD ON CRUDE VOL % 5.61 YIELD ON CRUDE WT% 4.50
% ON CUT % ON CUT % ON CUT
COMPONENT VOL WGT COMPONENT VOL WGT COMPONENT VOL WGT
METHANE 0.00 0.00
ETHANE 0.00 0.00
PROPANE 0.00 0.00
ISOBUTANE 0.00 0.00
N-BUTANE 1.15 1.01
ISOPENTANE 13.86 13.01
N-PENTANE 23.56 22.33
CYCLOPENTANE 1.98 2.23
2,2-DIMETHYLBUTANE 0.32 0.32
2,3-DIMETHYLBUTANE 1.58 1.56
2-METHYLPENTANE 13.55 13.49
3-METHYLPENTANE 7.99 7.95
N-HEXANE 20.99 20.93
METHYLCYCLOPENTANE 6.41 7.26
BENZENE 1.46 1.94
CYCLOHEXANE 3.69 4.34
2,2-DIMETHYLPENTANE 0.20 0.21
2,4-DIMETHYLPENTANE 0.60 0.62
2,2,3-TRIMETHYLBUTANE 0.02 0.02
2-METHYLHEXANE 1.01 1.04
c+t-1,3-DiMe-Cyclopentanes 0.30 0.34
3-METHYLHEXANE 0.64 0.66
c+t-1,2-DiMe-Cyclopentanes 0.13 0.15
N-HEPTANE 0.00 0.00
METHYLCYCLOHEXANE 0.00 0.00
TOLUENE 0.00 0.00
VOL % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
0.00 0.00 0.00 1.15 23.56 20.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.86 23.44 2.80 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.15 37.42 44.43 2.80 0.00 0.00 0.00 0.00 0.00 0.00 1.98 6.41 0.66 0.00 0.00 0.00 0.00 0.00 0.00 3.69 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.98 10.10 0.66 0.00 0.00 0.00 0.00 0.00 0.00 1.46 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.15 39.40 55.99 3.47 0.00 0.00 0.00 0.00 0.00 0.00 45.70
40.10
85.81
9.05
3.69
12.74
1.46
100.0
WGT % CRUDE N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
0.00 0.00 0.00 1.01 22.33 20.93 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 13.01 23.31 2.90 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.01 35.34 44.25 2.90 0.00 0.00 0.00 0.00 0.00 0.00 2.23 7.26 0.75 0.00 0.00 0.00 0.00 0.00 0.00 4.34 0.00 0.00 0.00 0.00 0.00 0.00 0.00 2.23 11.60 0.75 0.00 0.00 0.00 0.00 0.00 0.00 1.94 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.01 37.57 57.78 3.65 0.00 0.00 0.00 0.00 0.00 0.00 44.27
39.22
83.49
10.24
4.34
14.58
1.94
100.0
GC component subset and carbon number data from simulating 15/5 tower cuts

<<<PAGE 1099>>>

TABLE 7 HYDROCARBON ANALYSIS Eagleford 40.1 API
15/5 CUT POINT DEG F VT 158 TO 374 YIELD CUT RANGE VOL % 6.7 TO 30.4 YIELD CUT RANGE WT% 5.3 TO 27.3
15/5 CUT POINT DEG C VT 70 TO 190 YIELD ON CRUDE VOL % 23.66 YIELD ON CRUDE WT% 22.01
% ON CUT % ON CUT % ON CUT
COMPONENT VOL WGT COMPONENT VOL WGT COMPONENT VOL WGT
ETHANE 0.00 0.00 2,4-DIMETHYLHEXANE 0.53 0.49 C9 ISOPARAFFINS 8.02 7.64
PROPANE 0.00 0.00 TOLUENE 2.98 3.43 C9 NAPHTHENES 8.39 8.77
ISOBUTANE 0.00 0.00 2,3-DIMETHYLHEXANE 0.39 0.36 C9 CYCLOHEXANES 5.34 5.60
N-BUTANE 0.00 0.00 2-METHYLHEPTANE 2.83 2.63 C9 CYCLOPENTANES 2.51 2.55
ISOPENTANE 0.00 0.00 4-METHYLHEPTANE 0.98 0.91 N-NONANE 5.85 5.56
N-PENTANE 0.00 0.00 3,4-DIMETHYLHEXANE 0.04 0.04 ISOPROPYLBENZENE 0.20 0.23
CYCLOPENTANE 0.00 0.00 C8 NAPHTHENES 7.68 5.86 N-PROPYLBENZENE 0.33 0.38
2,2-DIMETHYLBUTANE 0.00 0.00 3-METHYLHEPTANE 1.82 1.69 C9 TRIMETHYL-PARAFFINS 0.41 0.39
2,3-DIMETHYLBUTANE 0.00 0.00 C+T-1,4-DIME-CYCLOHEXANES 0.79 0.83 C8 TRIMETHYL-PARAFFINS 0.25 0.23
2-METHYLPENTANE 0.00 0.00 1,1-DIMETHYLCYCLOHEXANE 0.27 0.28 1,2,3-TRIME-CYCLOHEXANES(MI) 0.30 0.32
3-METHYLPENTANE 0.06 0.05 C+T-1,3-DIME-CYCLOHEXANES 1.80 1.87 1,2,4-TRIME-CYCLOHEXANES(MI) 1.37 1.44
N-HEXANE 0.96 0.84 N-PROPYLCYCLOPENTANE 0.11 0.12
METHYLCYCLOPENTANE 0.53 0.52 ISOPROPYLCYCLOPENTANE 0.01 0.01
BENZENE 0.45 0.53 C+T-1-ME-3-ET-CYCLOPENTANES 0.14 0.15
CYCLOHEXANE 1.25 1.29 C+T-1-ME-2-ET-CYCLOPENTANES 0.22 0.22
2,2-DIMETHYLPENTANE 0.05 0.05 1-METHYL,1-ETHYLCYCLOPENTANE 0.06 0.06
2,4-DIMETHYLPENTANE 0.20 0.18 C+T-1,2-DIME-CYCLOHEXANES 1.01 1.05
2,2,3-TRIMETHYLBUTANE 0.01 0.00 N-OCTANE 6.22 5.79
3,3-DIMETHYLPENTANE 0.04 0.04 ETHYLCYCLOHEXANE 1.76 1.83
1,1-DIMETHYLCYCLOPENTANE 0.26 0.26 2,2-DIMETHYLHEPTANE 0.14 0.13
2-METHYLHEXANE 2.00 1.81 2,6-DIMETHYLHEPTANE 1.28 1.21
C+T-1,3-DIME-CYCLOPENTANES 0.82 0.81 ETHYLBENZENE 0.73 0.84
3-METHYLHEXANE 2.20 2.00 3,3-DIMETHYLHEPTANE 0.17 0.17
C+T-1,2-DIME-CYCLOPENTANES 0.81 0.81 PARAXYLENE 0.79 0.91
N-HEPTANE 6.53 5.92 METAXYLENE 2.23 2.56
METHYLCYCLOHEXANE 4.81 4.91 2,3-DIMETHYLHEPTANE 1.16 1.10
ETHYLCYCLOPENTANE 0.17 0.17 3,4-DIMETHYLHEPTANE 0.02 0.02
1,1,2-TRIMETHYLCYCLOPENTANE 0.16 0.15 4-METHYLOCTANE 1.00 0.95
1,1,3-TRIMETHYLCYCLOPENTANE 0.43 0.42 2-METHYLOCTANE 1.10 1.05
2,2-DIMETHYLHEXANE 0.06 0.06 3-METHYLOCTANE 1.48 1.40
2,5-DIMETHYLHEXANE 0.34 0.32 ORTHOXYLENE 1.35 1.55
VOL % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
23.97
30.71
8.95
20.92
30.84
14.48
0.00 0.00 0.00 0.00 0.00 0.96 6.53 6.22 5.85 4.14 0.27 0.00 0.00 0.00 0.00 0.06 5.02 7.37 8.02 8.02 2.23 0.00 0.00 0.00 0.00 0.00 0.00 0.00 1.01 11.55 13.59 13.88 12.16 2.50 0.00 0.00 54.69
0.00 0.53 2.06 2.05 2.51 1.57 0.24 0.01 0.00 1.25 4.81 5.63 5.34 3.36 0.50 0.01 0.00 0.00 1.78 6.87 7.68 8.39 5.34 0.76 0.02 0.00 0.45 2.98 5.10 5.02 0.91 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.25 21.41 26.36 27.29 18.40 3.27 0.02 0.00 100.0
WGT % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
22.38
29.09
9.06
21.74
31.91
16.63
0.00 0.00 0.00 0.00 0.00 0.84 5.92 5.79 5.56 4.00 0.27 0.00 0.00 0.00 0.00 0.05 4.55 6.86 7.64 7.79 2.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.89 10.47 12.65 13.20 11.79 2.47 0.00 0.00 51.46
0.00 0.52 2.05 2.04 2.55 1.63 0.25 0.01 0.00 1.29 4.91 5.86 5.60 3.53 0.53 0.01 0.00 0.00 1.82 6.97 7.90 8.77 5.63 0.81 0.02 0.00 0.53 3.43 5.86 5.77 1.04 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 3.23 20.86 26.40 27.74 18.46 3.30 0.02 0.00 100.0
GC component subset and carbon number data from simulating 15/5 tower cuts

<<<PAGE 1100>>>

TABLE 8 HYDROCARBON ANALYSIS Eagleford 40.1 API
15/5 CUT POINT DEG F VT IBP TO 374 YIELD CUT RANGE VOL % 0.0 TO 30.4 YIELD CUT RANGE WT% 0.0 TO 18.6
15/5 CUT POINT DEG C VT IBP TO 190 YIELD ON CRUDE VOL % 30.36 YIELD ON CRUDE WT% 27.26
% ON CUT % ON CUT % ON CUT
COMPONENT VOL WGT COMPONENT VOL WGT COMPONENT VOL WGT
ETHANE 0.01 0.00 2,4-DIMETHYLHEXANE 0.41 0.39 C9 ISOPARAFFINS 6.25 6.15
PROPANE 0.61 0.42 TOLUENE 2.32 2.76 C9 NAPHTHENES 6.54 7.06
ISOBUTANE 0.523 0.401 2,3-DIMETHYLHEXANE 0.302 0.291 C9 CYCLOHEXANES 4.165 4.512
N-BUTANE 2.642 2.101 2-METHYLHEPTANE 2.207 2.119 C9 CYCLOPENTANES 1.954 2.055
ISOPENTANE 2.617 2.224 4-METHYLHEPTANE 0.762 0.732 N-NONANE 4.562 4.479
N-PENTANE 4.362 3.744 3,4-DIMETHYLHEXANE 0.030 0.029 ISOPROPYLBENZENE 0.158 0.187
CYCLOPENTANE 0.366 0.373 C8 NAPHTHENES 5.983 6.358 N-PROPYLBENZENE 0.260 0.307
2,2-DIMETHYLBUTANE 0.059 0.053 3-METHYLHEPTANE 1.421 1.421 C9 TRIMETHYL-PARAFFINS 0.317 0.316
2,3-DIMETHYLBUTANE 0.292 0.261 C+T-1,4-DIME-CYCLOHEXANES 0.620 0.620 C8 TRIMETHYL-PARAFFINS 0.192 0.188
2-METHYLPENTANE 2.509 2.261 1,1-DIMETHYLCYCLOHEXANE 0.209 0.209 1,2,3-TRIME-CYCLOHEXANES(MI) 0.235 0.255
3-METHYLPENTANE 1.522 1.371 C+T-1,3-DIME-CYCLOHEXANES 1.401 1.401 1,2,4-TRIME-CYCLOHEXANES(MI) 1.068 1.158
N-HEXANE 4.632 4.184 N-PROPYLCYCLOPENTANE 0.089 0.089
METHYLCYCLOPENTANE 1.598 1.638 ISOPROPYLCYCLOPENTANE 0.011 0.011
BENZENE 0.621 0.747 C+T-1-ME-3-ET-CYCLOPENTANES 0.112 0.112
CYCLOHEXANE 1.660 1.769 C+T-1-ME-2-ET-CYCLOPENTANES 0.174 0.174
2,2-DIMETHYLPENTANE 0.079 0.074 1-METHYL,1-ETHYLCYCLOPENTANE 0.047 0.047
2,4-DIMETHYLPENTANE 0.264 0.248 C+T-1,2-DIME-CYCLOHEXANES 0.786 0.786
2,2,3-TRIMETHYLBUTANE 0.007 0.007 N-OCTANE 4.848 4.848
3,3-DIMETHYLPENTANE 0.042 0.040 ETHYLCYCLOHEXANE 1.371 1.371
1,1-DIMETHYLCYCLOPENTANE 0.248 0.255 2,2-DIMETHYLHEPTANE 0.109 0.109
2-METHYLHEXANE 1.742 1.629 2,6-DIMETHYLHEPTANE 0.995 0.995
C+T-1,3-DIME-CYCLOPENTANES 0.691 0.712 ETHYLBENZENE 0.570 0.570
3-METHYLHEXANE 1.836 1.717 3,3-DIMETHYLHEPTANE 0.136 0.136
C+T-1,2-DIME-CYCLOPENTANES 0.657 0.676 PARAXYLENE 0.618 0.618
N-HEPTANE 5.088 4.763 METAXYLENE 1.736 1.736
METHYLCYCLOHEXANE 3.751 3.954 2,3-DIMETHYLHEPTANE 0.902 0.902
ETHYLCYCLOPENTANE 0.130 0.137 3,4-DIMETHYLHEPTANE 0.013 0.013
1,1,2-TRIMETHYLCYCLOPENTANE 0.122 0.124 4-METHYLOCTANE 0.782 0.782
1,1,3-TRIMETHYLCYCLOPENTANE 0.334 0.341 2-METHYLOCTANE 0.860 0.860
2,2-DIMETHYLHEXANE 0.048 0.046 3-METHYLOCTANE 1.150 1.150
2,5-DIMETHYLHEXANE 0.267 0.258 ORTHOXYLENE 1.051 1.051
VOL % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
30.18
31.91
62.09
8.64
16.97
26.36
11.54
0.00 0.01 0.61 2.64 4.36 4.63 5.09 4.85 4.56 3.22 0.20 0.00 0.00 0.52 2.62 4.38 4.44 5.74 6.25 6.24 1.72 0.00 0.00 0.00 0.01 0.61 3.17 6.98 9.01 9.52 10.59 10.82 9.46 1.92 0.00 0.00 0.37 1.60 1.73 1.60 1.95 1.22 0.18 0.01 0.00 1.66 3.75 4.39 4.16 2.61 0.39 0.01 0.00 0.37 3.26 5.48 5.98 6.54 4.14 0.59 0.01 0.00 0.62 2.32 3.98 3.91 0.70 0.01 0.00 0.00 0.00 0.01 0.61 3.17 7.34 12.89 17.32 20.55 21.26 14.31 2.52 0.01 0.00 100.0
WGT % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
27.78
30.41
58.20
9.00
18.21
28.10
13.70
0.00 0.00 0.42 2.10 3.74 4.18 4.76 4.66 4.48 3.22 0.21 0.00 0.00 0.40 2.22 3.95 4.15 5.52 6.15 6.27 1.76 0.00 0.00 0.00 0.00 0.42 2.50 5.97 8.13 8.91 10.18 10.63 9.48 1.96 0.00 0.00 0.37 1.64 1.78 1.64 2.05 1.31 0.20 0.01 0.00 1.77 3.95 4.72 4.51 2.83 0.42 0.01 0.00 0.37 3.41 5.73 6.36 7.06 4.51 0.64 0.02 0.00 0.75 2.76 4.71 4.64 0.83 0.01 0.00 0.00 0.00 0.00 0.42 2.50 6.34 12.29 17.40 21.25 22.33 14.82 2.62 0.02 0.00 100.0
GC component subset and carbon number data from simulating 15/5 tower cuts

<<<PAGE 1101>>>

TABLE 9 HYDROCARBON ANALYSIS Eagleford 40.1 API
15/5 CUT POINT DEG F VT IBP TO 428 YIELD CUT RANGE VOL % 0.0 TO 37.4 YIELD CUT RANGE WT% 0.0 TO 34.2
15/5 CUT POINT DEG C VT IBP TO 220 YIELD ON CRUDE VOL % 37.44 YIELD ON CRUDE WT% 34.21
% ON CUT % ON CUT % ON CUT
COMPONENT VOL WGT COMPONENT VOL WGT COMPONENT VOL WGT
ETHANE 0.00 0.00 2,4-DIMETHYLHEXANE 0.33 0.32 C9 ISOPARAFFINS 5.07 4.91
PROPANE 0.50 0.34 TOLUENE 1.89 2.20 C9 NAPHTHENES 5.30 5.63
ISOBUTANE 0.42 0.32 2,3-DIMETHYLHEXANE 0.24 0.23 C9 CYCLOHEXANES 3.38 3.60
N-BUTANE 2.14 1.68 2-METHYLHEPTANE 1.79 1.69 C9 CYCLOPENTANES 1.58 1.64
ISOPENTANE 2.12 1.77 4-METHYLHEPTANE 0.62 0.58 N-NONANE 3.70 3.57
N-PENTANE 3.54 2.99 3,4-DIMETHYLHEXANE 0.02 0.02 ISOPROPYLBENZENE 0.13 0.15
CYCLOPENTANE 0.30 0.30 C8 NAPHTHENES 4.85 5.07 N-PROPYLBENZENE 0.21 0.24
2,2-DIMETHYLBUTANE 0.05 0.04 3-METHYLHEPTANE 1.15 1.09 C9 TRIMETHYL-PARAFFINS 0.26 0.25
2,3-DIMETHYLBUTANE 0.24 0.21 C+T-1,4-DIME-CYCLOHEXANES 0.50 0.53 C8 TRIMETHYL-PARAFFINS 0.16 0.15
2-METHYLPENTANE 2.03 1.80 1,1-DIMETHYLCYCLOHEXANE 0.17 0.18 1,2,3-TRIME-CYCLOHEXANES(MI) 0.19 0.20
3-METHYLPENTANE 1.23 1.09 C+T-1,3-DIME-CYCLOHEXANES 1.14 1.20 1,2,4-TRIME-CYCLOHEXANES(MI) 0.87 0.92
N-HEXANE 3.76 3.34 N-PROPYLCYCLOPENTANE 0.07 0.07
METHYLCYCLOPENTANE 1.30 1.31 ISOPROPYLCYCLOPENTANE 0.01 0.01
BENZENE 0.50 0.60 C+T-1-ME-3-ET-CYCLOPENTANES 0.09 0.09
CYCLOHEXANE 1.35 1.41 C+T-1-ME-2-ET-CYCLOPENTANES 0.14 0.14
2,2-DIMETHYLPENTANE 0.06 0.06 1-METHYL,1-ETHYLCYCLOPENTANE 0.04 0.04
2,4-DIMETHYLPENTANE 0.21 0.20 C+T-1,2-DIME-CYCLOHEXANES 0.64 0.67
2,2,3-TRIMETHYLBUTANE 0.01 0.01 N-OCTANE 3.93 3.72
3,3-DIMETHYLPENTANE 0.03 0.03 ETHYLCYCLOHEXANE 1.11 1.18
1,1-DIMETHYLCYCLOPENTANE 0.20 0.20 2,2-DIMETHYLHEPTANE 0.09 0.09
2-METHYLHEXANE 1.41 1.30 2,6-DIMETHYLHEPTANE 0.81 0.78
C+T-1,3-DIME-CYCLOPENTANES 0.56 0.57 ETHYLBENZENE 0.46 0.54
3-METHYLHEXANE 1.49 1.37 3,3-DIMETHYLHEPTANE 0.11 0.11
C+T-1,2-DIME-CYCLOPENTANES 0.53 0.54 PARAXYLENE 0.50 0.58
N-HEPTANE 4.13 3.80 METAXYLENE 1.41 1.64
METHYLCYCLOHEXANE 3.04 3.16 2,3-DIMETHYLHEPTANE 0.73 0.71
ETHYLCYCLOPENTANE 0.11 0.11 3,4-DIMETHYLHEPTANE 0.01 0.01
1,1,2-TRIMETHYLCYCLOPENTANE 0.10 0.10 4-METHYLOCTANE 0.63 0.61
1,1,3-TRIMETHYLCYCLOPENTANE 0.27 0.27 2-METHYLOCTANE 0.70 0.67
2,2-DIMETHYLHEXANE 0.04 0.04 3-METHYLOCTANE 0.93 0.90
2,5-DIMETHYLHEXANE 0.22 0.21 ORTHOXYLENE 0.85 0.99
VOL % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
28.85
29.72
58.56
9.13
18.14
29.65
11.79
0.00 0.00 0.50 2.14 3.54 3.76 4.13 3.93 3.70 3.23 2.37 1.55 0.00 0.42 2.12 3.55 3.60 4.65 5.07 5.11 3.38 1.51 0.30 0.00 0.00 0.50 2.57 5.66 7.31 7.72 8.59 8.77 8.35 5.75 3.06 0.30 0.30 1.30 1.40 1.29 1.58 1.13 0.90 1.22 0.00 1.35 3.04 3.56 3.38 2.48 1.99 2.27 0.08 0.30 2.64 4.44 4.85 5.30 4.51 3.52 3.94 0.14 0.50 1.89 3.22 3.36 1.40 1.09 0.33 0.00 0.00 0.00 0.50 2.57 5.96 10.45 14.05 16.66 17.43 14.25 10.36 7.33 0.44 100.0
WGT % CUT N-PARAFFINS ISOPARAFFINS TOTAL PARAFFINS CYCLOPENTANES CYCLOHEXANES TOTAL NAPHTHENES AROMATICS TOTAL C1 C2 C3 C4 C5 C6 C7 C8 C9 C10 C11 C12 C13 TOTAL
26.55
28.16
54.71
9.47
19.26
31.50
13.79
0.00 0.00 0.34 1.68 2.99 3.34 3.80 3.72 3.57 3.18 2.37 1.57 0.00 0.32 1.77 3.15 3.31 4.40 4.91 5.05 3.40 1.54 0.30 0.00 0.00 0.34 2.00 4.76 6.49 7.11 8.12 8.48 8.22 5.77 3.11 0.30 0.30 1.31 1.42 1.31 1.64 1.20 0.97 1.33 0.00 1.41 3.16 3.77 3.60 2.64 2.13 2.46 0.09 0.30 2.72 4.58 5.07 5.63 4.90 3.84 4.31 0.16 0.60 2.20 3.76 3.92 1.64 1.28 0.39 0.00 0.00 0.00 0.34 2.00 5.06 9.80 13.89 16.96 18.03 14.77 10.88 7.80 0.47 100.0
GC component subset and carbon number data from simulating 15/5 tower cuts

<<<PAGE 1102>>>

TABLE 10 KEROSINES Eagleford 40.1 API
15/5 CUT POINTS DEG F VT 302/401 302/455 302/509 374/482 374/536 302/428
DEG C VT 150/205 150/235 150/265 190/250 190/280 150/220
YIELD CUT RANGE VOL % 21.4/33.9 21.4/40.9 21.4/47.6 30.4/44.3 30.4/50.7 21.4/37.4
YIELD ON CRUDE VOL % 12.5 19.6 26.2 14.0 20.4 16.1
MIDPOINT VOL % 27.6 31.2 34.5 37.4 40.6 29.4
GRAVITY API 45.7 44.7 43.9 42.9 42.2 45.2
SPECIFIC GRAVITY 60/60 0.7985 0.8031 0.8070 0.8111 0.8147 0.8009
DENSITY AT 15 C KG/DM3 0.7977 0.8023 0.8062 0.8103 0.8139 0.8002
TOTAL SULFUR WGT % 0.002 0.002 0.003 0.003 0.007 0.002
MERCAPTAN SULFUR WGT PPM 3 3 3 3 4 3
SMOKE POINT MM 29.1 27.9 26.7 25.8 24.7 28.5
LUMINOMETER NUMBER 67.0 64.0 61.0 59.0 56.0 65.0
FREEZE POINT DEG F -73 -56 -39 -36 -21 -65
CLOUD POINT DEG F -79 -63 -46 -43 -27 -71
POUR POINT DEG F -87 -73 -57 -52 -37 -80
ANILINE POINT DEG F 136.7 141.7 146.7 150.6 155.8 139.3
DIESEL INDEX 62 63 64 65 66 63
NEUT. NO. MG/GM 0.04 0.04 0.05
REFRACTIVE INDEX 67 DEG C 1.4224 1.4253 1.4281 1.4305 1.4332 1.4239
NAPHTHALENES VOL % 2.00
VISC @ -30 F/-34.4 C CST 3.32 4.57 6.43 8.46 12.55 3.88
VISC @ 100 F/37.8 C CST 0.99 1.16 1.35 1.52 1.80 1.07
VISC @ 104 F/40.0 C CST 0.97 1.13 1.32 1.48 1.74 1.04
VISC @ 140 F/60.0 C CST 0.79 0.91 1.04 1.15 1.33 0.85
VISC @ 210 F/98.9 C CST 0.58 0.65 0.73 0.79 0.88 0.61
VISC @ 212 F/100.0 C CST 0.58 0.64 0.72 0.78 0.87 0.61
PARAFFINS VOL % 49.8 48.2 48.9 45.8 47.9 48.0
NAPHTHENES VOL % 34.1 36.4 35.7 40.1 38.1 36.5
AROMATICS VOL % 16.1 15.4 15.4 14.1 13.9 15.5
CARBON WGT % 85.89 85.93 85.99 86.00 86.01 85.91
HYDROGEN WGT % 14.11 14.07 14.01 13.99 13.98 14.09
YIELD ON CRUDE WGT % 12.1 19.1 25.7 13.8 20.2 15.6

<<<PAGE 1103>>>

TABLE 11 MIDDLE DISTILLATES Eagleford 40.1 API
15/5 CUT POINTS DEG F VT 401/509 509/590 590/650 590/698 320/650 401/650 302/698 158/650
DEG C VT 205/265 265/310 310/343 310/370 160/343 205/343 150/370 70/343
YIELD CUT RANGE VOL % 33.9/47.6 47.6/56.6 56.6/62.6 56.6/67.1 23.5/62.6 33.9/62.6 21.4/67.1 6.7/62.6
YIELD ON CRUDE VOL % 13.7 9.0 6.0 10.5 39.1 28.8 45.7 55.9
MIDPOINT VOL % 40.8 52.1 59.6 61.9 43.1 48.3 44.3 34.7
GRAVITY API 42.2 39.0 35.8 34.7 41.2 39.8 40.7 45.6
SPECIFIC GRAVITY 60/60 0.8147 0.8300 0.8456 0.8513 0.8193 0.8260 0.8217 0.7992
DENSITY AT 15 C KG/DM3 0.8139 0.8291 0.8447 0.8504 0.8184 0.8251 0.8209 0.7984
TOTAL SULFUR WGT % 0.0047 0.0610 0.1743 0.1955 0.0440 0.0588 0.0605 0.0317
DIESEL INDEX ANILINE POINT DEG F 155.7 174.0 186.9 190.4 161.1 168.3 163.1
65.7 67.8 67.0 66.1 66.4 67.0 66.4
CETANE INDEX (90) 52.1 64.1 70.0 70.1 53.1 58.2 53.1
CLOUD POINT DEG F -30 13 42 52 1 10 13
POUR POINT DEG F -40 5 36 45 -12 -1 -1
REFRACTIVE INDEX 67 DEG C 1.4334 1.4435 1.4505 1.4526 1.4357 1.4401 1.4368
NEUT. NO. MG/GM 0.05 0.09 0.11 0.10 0.06 0.07 0.06 0.05
A. RINGS N. RINGS VISC @ 100 F/37.8 C CST 1.80 3.54 6.42 7.80 2.14 2.83 2.33
VISC @ 104 F/40.0 C CST 1.74 3.37 6.03 7.30 2.06 2.71 2.24
VISC @ 140 F/60.0 C CST 1.33 2.30 3.72 4.36 1.54 1.92 1.65
VISC @ 150 F/65.6 C CST 1.24 2.10 3.32 3.86 1.43 1.77 1.53
VISC @ 175 F/79.4 C CST 1.06 1.72 2.58 2.95 1.22 1.48 1.29
VISC @ 210 F/98.9 C CST 0.88 1.35 1.92 2.16 1.00 1.18 1.05
VISC @ 212 F/100.0 C CST 0.87 1.33 1.89 2.13 0.99 1.17 1.04
6.2 6.5 5.7 5.3 6.0 6.1 5.8
23.0 20.8 21.6 22.3 22.7 21.8 22.6
NITROGEN WGT % 0.0020 0.0100 0.0170
YIELD ON CRUDE WGT % 13.6 9.1 6.2 10.9 38.9 28.9 45.7 54.3

<<<PAGE 1104>>>

TABLE 12 GAS OILS Eagleford 40.1 API
15/5 CUT POINTS DEG F VT 650/752 752/851 851/950 950/1049 650/851 650/1049 851/1049 995/1049
DEG C VT 343/400 400/455 455/510 510/565 343/455 343/565 455/565 535/565
YIELD CUT RANGE VOL % 62.6/71.9 71.9/79.6 79.6/86.3 86.3/91.8 62.6/79.6 62.6/91.8 79.6/91.8 89.0/91.8
YIELD ON CRUDE VOL % 9.2 7.8 6.7 5.5 17.0 29.2 12.2 2.8
MIDPOINT VOL % 67.3 75.7 83.0 89.1 71.1 77.2 85.7 90.4
GRAVITY API 32.2 29.7 27.5 25.4 31.0 29.1 26.5 25.0
SPECIFIC GRAVITY 60/60 0.8644 0.8780 0.8902 0.9019 0.8706 0.8810 0.8955 0.9044
DENSITY AT 15 C KG/DM3 0.8635 0.8771 0.8893 0.9009 0.8697 0.8801 0.8945 0.9034
TOTAL SULFUR WGT % 0.2378 0.2688 0.2744 0.2969 0.2521 0.2660 0.2847 0.3066
ANILINE POINT DEG F 198.3 212.3 232.3 254.3 204.7 218.0 242.3 259.0
CON CARBON WGT % 0.01 0.04 0.22 0.70 0.02 0.20 0.44 0.83
POUR POINT DEG F 65 89 104 114 77 93 108 116
REFRACTIVE INDEX 67 DEG C 1.4575 1.4655 1.4731 1.4812 1.4611 1.4677 1.4767 1.4833
NEUT. NO. MG/GM 0.09 0.06 0.05 0.03 0.07 0.06 0.04 0.03
NITROGEN WGT % 0.037 0.058 0.061 0.071 0.047 0.055 0.066 0.074
VISC @ 100 F/37.8 C CST 12.85 32.03 86.08 260.04 19.12 40.57 139.12 348.91
VISC @ 104 F/40.0 C CST 11.90 29.14 76.85 227.26 17.57 36.73 123.05 303.18
VISC @ 140 F/60.0 C CST 6.56 14.03 31.98 79.94 9.13 17.05 47.58 101.95
VISC @ 150 F/65.6 C CST 5.71 11.83 26.06 62.60 7.84 14.25 38.10 79.00
VISC @ 175 F/79.4 C CST 4.19 8.11 16.56 36.43 5.59 9.59 23.30 44.89
VISC @ 210 F/98.9 C CST 2.94 5.25 9.83 19.56 3.78 6.08 13.25 23.45
VISC @ 212 F/100.0 C CST 2.88 5.13 9.58 18.95 3.71 5.94 12.87 22.69
BASIC NITROGEN WGT % 0.0050 0.0070 0.0120 0.0170 0.0060 0.0090 0.0140 0.0180
VANADIUM WGT PPM <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 <0.1 0.1
NICKEL WGT PPM <0.1 <0.1 <0.1 0.1 <0.1 <0.1 <0.1 0.1
IRON WGT PPM <0.1 <0.1 <0.1 0.1 <0.1 <0.1 <0.1 0.1
A. RINGS N. RINGS 4.2 4.0 4.0 4.7 4.1 4.1 4.3 5.0
24.0 24.7 26.6 29.8 24.1 24.9 27.9 30.7
YIELD ON CRUDE WGT % 9.7 8.3 7.2 6.1 18.0 31.3 13.3 3.1

<<<PAGE 1105>>>

TABLE 13 RESIDUA Eagleford 40.1 API
15/5 CUT POINTS DEG F VT 650/FBP 698/FBP 752/FBP 851/FBP 950/FBP 995/FBP 1049/FBP
DEG C VT 343/FBP 370/FBP 400/FBP 455/FBP 510/FBP 535/FBP 565/FBP
YIELD ON CRUDE VOL % 37.4 32.9 28.2 20.4 13.7 11.0 8.2
GRAVITY API 27.4 26.7 25.9 24.5 23.1 22.5 21.7
SPECIFIC GRAVITY 60/60 0.8904 0.8947 0.8989 0.9069 0.9150 0.9189 0.9240
DENSITY AT 15 C KG/DM3 0.8895 0.8938 0.8980 0.9059 0.9140 0.9179 0.9229
TOTAL SULFUR WGT % 0.29 0.30 0.31 0.32 0.34 0.36 0.37
CON CARBON WGT % 1.30 1.47 1.71 2.32 3.32 3.99 5.06
NITROGEN WGT % 0.077 0.083 0.089 0.100 0.118 0.131 0.150
BASIC NITROGEN WGT % 0.0150 0.0160 0.0180 0.0220 0.0260 0.0290 0.0330
NEUT. NO. MG/GM 0.05 0.05 0.04 0.03 0.03 0.02 0.02
POUR POINT DEG F 81 79 77 72 64 56 46
VISC @ 100 F/37.8 C CST 87.88 126.59 193.06 439.33 1117.56 1827.97 3511.28
VISC @ 104 F/40.0 C CST 78.32 112.02 169.48 379.7 948.73 1537.18 2915.84
VISC @ 140 F/60.0 C CST 32.17 43.53 61.85 122.5 265.62 399.26 685.55
VISC @ 150 F/65.6 C CST 26.14 34.92 48.87 94.01 197.07 290.94 487.79
VISC @ 175 F/79.4 C CST 16.52 21.44 29.03 52.31 101.66 144.17 229.12
VISC @ 210 F/98.9 C CST 9.75 12.25 15.97 26.68 47.51 64.3 96.01
VISC @ 212 F/100.0 C CST 9.5 11.91 15.5 25.8 45.73 61.75 91.91
VISC @ 275 F/135 C CST 4.75 5.7 7.05 10.64 16.82 21.35 29.27
ABS. VISC @ 140 F POISES 1.59 1.95 2.5 4.1 7.37 10.16 15.83
SOFTENING POINT DEG F -26.6 -16.7 -6. 12.6 30.7 39.2 49.7
PEN. @ 77 F / 25 C MM >400 >400 >400 >400 >400 >400 >400
PEN. @ 39 F / 4 C MM >400 >400 >400 >400 >400 >400 >400
SODIUM WGT PPM 2.4 2.7 3.1 4.3 6.2 7.7 10.0
VANADIUM WGT PPM 0.1 0.2 0.2 0.2 0.4 0.4 0.6
NICKEL WGT PPM 0.1 0.1 0.2 0.2 0.3 0.4 0.5
IRON WGT PPM 1.0 1.1 1.3 1.8 2.6 3.3 4.3
MNI WGT % 0.10 0.10 0.10 0.20 0.20 0.30 0.40
NHI WGT % 0.10 0.10 0.10
YIELD ON CRUDE WGT % 40.4 35.7 30.8 22.5 15.2 12.3 9.2

<<<PAGE 1106>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6C
ENHANCECO REPORT

<<<PAGE 1107>>>

EnhanceCo
Consulting Services Monitoring Equipment
September 7, 2011
Mr. Rick Wooldridge
Manager Asset Integrity
Magellan Midstream Partners, LP
Dear Sir:
EnhanceCo has been asked to review the potential for internal corrosion on the Longhorn
Pipeline that will be reversed and bring West Texas Intermediate Crude from Crane, Texas, to
the Gulf Coast.
The operating conditions provided include (see Intertek Reports of Analysis # 076-001/002):
Line Diameter of 18"*
Estimated volume of 135,000 bbl/day
API gravity of 31/40
BS&W content of .05/.05 %
Hydrogen Sulfide (HoS) : 10/<1 ppm
Ambient temperature
ANSI 600 pressure, estimated at 1000 psi
Factors influencing corrosion rates with these conditions would include:
Flow velocity of 4.95 ft/second
Flow regime: agitated pool (expect some water accumulation at low points)
Water volume based on 1% BS&W = 1350 bbl/day
Water volume based on .05% BS&W = 67.5 bbl/day
Early corrosion studies of West Texas Sour Crude indicated raw corrosion rates in the range of
30 MPY (see attached graph). If more specific raw and protected corrosion rates are desired,
laboratory tests of specific samples of crude can be conducted.
With proper evaluation and selection of corrosion inhibitor products, a minimum of 90%
protection from raw corrosion rates should be expected at or near a rate of 3 MPY. As this rate
is still above normally accepted protection in pipelines, additional protection in the form of
aggressive pigging should be used. This will not only remove accumulated water but also any
solids that may contribute to under-deposit corrosion and/or bacterial corrosion. An aggressive
monitoring program will be needed, with corrosion coupons mounted at the 6 o'clock position,
analysis of any liquids or solids from the pigging process, and periodic corrosion inhibitor
residuals.
2714 Cypress Point Drive, Suite E Missouri City, TX 77459 Telephone: 281-499-4426 Fax: 281-261-5617
e-mail: rust@enhanceco.net web: www.enhanceco.net

<<<PAGE 1108>>>

EnhanceCo
Consulting Services Monitoring Equipment
The attached graph shows corrosion rates of West Texas Crude with and without corrosion
inhibitor, as well as the effect of Oxygen on corrosion rates. For pipeline applications this may
introduced in the loading and unloading of product).
only be important when crude is delivered to terminals by truck (where air is most likely
Rick, please call with questions or comments.
Tom Pickthall
Thomas W. Pickthall
EnhanceCo, Inc.
Corrosion Rates (West Texas Sour Crude)
Dr. Sheldon Evans, Conoco Inc.
300
250
200
MPY
150
100
50
No Air/No
Inhibitor
Inhibitor/No
Air
Inhibitor
Air/No
Inhibitor/Air
Dr: Sheldon Evans, Conoco Inc.
No Air/No Inhibitor
CONDITION
MPY
Inhibitor/No Air
30
Air/No Inhibitor
285
3
Inhibitor/Air
275
2714 Cypress Point Drive, Suite E Missouri City, TX 77459 Telephone: 281-499-4426 Fax: 281-261-5617
e-mail: rust@enhanceco.net web: www.enhanceco.net

<<<PAGE 1109>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6D
DRAG REDUCING AGENT MSDS

<<<PAGE 1110>>>

ransition SDS: Product is now manufactured by Phillips 66 Compan
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
mergency, Customer Service and Technical phone numbers have NOT change
LP™M 100 Flow Improver
ConocoPhillips
Flow Improver Solutions
Safety Data Sheet
Section 1: Identification of the substance or mixture and of the supplier
Product Name:
SDS Number:
472980
LP™M 100 Flow Improver
Intended Use:
Flow Improver
Manufacturer:
ConocoPhillips Specialty Products Inc.
Houston, TX 77079-1175
600N. Dairy Ashford
United States of America
Emergency Health and Safety Number:
+1 703-527-3887 (USA, 24 hours)
+1 800-424-9300 (USA, 24 hours)
Customer Service:
Telephone: +1 832-486-2834
Telefax: +1 832-486-2881
SDS Information:
URL: www.conocophillips.com
Email: MSDS@conocophillips.com
Section 2: Hazard(s) Identification
This material is not considered hazardous according to OSHA criteria.
NFPA
Section 3: Composition/ Information on Ingredients
Component
Water
7732-18-5
CASRN
Concentration
Non-hazardous Materials
1 All concentrations are percent by weight unless ingredient is a gas. Gas concentrations are in percent by volume.
Proprietary
35 - 45
55 - 65
Section 4: First Aid Measures
attention.
Eye Contact: If irritation or redness develops from exposure, flush eyes with clean water. If symptoms persist, seek medical
Skin Contact: First aid is not normally required. However, it is good practice to wash any chemical from the skin.
Inhalation (Breathing): First aid is not normally required. If breathing difficulties develop, move victim away from source of
exposure and into fresh air in a position comfortable for breathing. Seek immediate medical attention.
Ingestion (Swallowing): First aid is not normally required; however, if swallowed and symptoms develop, seek medical attention.
Medical Conditions Aggravated by Exposure: None Known
Date of Issue: 12-Jan-2012
472980 - LP ™ 100 Flow improver
Status: FINAL
Page 1/6

<<<PAGE 1111>>>

Emergency, Customer Service and Technical phone numbers have NOT changed.
Transition SDS: Product is now manufactured by Phillips 66 Company.
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
472980 - LP™ 100 Flow Improver
Date of Issue: 12-Jan-2012
Status: FINAL
Page 2/6
Section 5: Fire-Fighting Measures
NFPA 704 Hazard Class
Health: 0 Flammability: 0 Instability: 0
(O-Minimal, 1-Slight, 2-Moderate, 3-Serious, 4-Severe)
rupture in the heat of a fire.
Unusual Fire & Explosion Hazards: No unusual fire or explosion hazards are expected. If container is not properly cooled, it can
Extinguishing Media: Use extinguishing agent suitable for type of surrounding fire.
protective clothing. When the potential chemical hazard is unknown, in enclosed or confined spaces, a self contained breathing
Fire Fighting Instructions: For fires beyond the initial stage, emergency responders in the immediate hazard area should wear
apparatus should be worn. In addition, wear other appropriate protective equipment as conditions warrant (see Section 8).
containers from immediate hazard area if it can be done safely. Water spray may be useful in minimizing or dispersing vapors and
Isolate immediate hazard area and keep unauthorized personnel out. Stop spill/release if it can be done safely. Move undamaged
to protect personnel. Cool equipment exposed to fire with water, if it can be done safely.
Hazardous Combustion Products: Combustion may yield carbon monoxide and oxides of nitrogen.
See Section 9 for Flammable Properties including Flash Point and Flammable (Explosive) Limits
Section 6: Accidental Release Measures
persons down wind of the spill/release, isolate immediate hazard area and keep unauthorized personnel out. Wear appropriate
Personal Precautions: Stay upwind and away from spill/release. Avoid direct contact with material. For large spillages, notify
information on hazards and precautionary measures.
protective equipment, including respiratory protection, as conditions warrant (see Section 8). See Sections 2 and 7 for additional
Environmental Precautions: Stop spill/release if it can be done safely. Prevent spilled material from entering sewers, storm
drains, other unauthorized drainage systems, and natural waterways. Use water sparingly to minimize environmental contamination
and reduce disposal requirements. If spill occurs on water notify appropriate authorities and advise shipping of any hazard.
cleanup of any spill is recommended. Dike far ahead of spill for later recovery or disposal. Absorb spill with inert material such as
Methods for Containment and Clean-Up: Notify relevant authorities in accordance with all applicable regulations. Immediate
sand or vermiculite, and place in suitable container for disposal. If spilled on water remove with appropriate methods (e.g.
accordance with local regulations.
skimming, booms or absorbents). In case of soil contamination, remove contaminated soil for remediation or disposal, in
regulations may influence or limit the choice of appropriate actions to be taken. See Sectión 13 for information on appropriate
Recommended measures are based on the most likely spillage scenarios for this material; however local conditions and
disposal.
Section 7: Handling and Storage
and wear appropriate personal protective equipment (see section 8).
Precautions for safe handling: Wear eye/face protection. Wash thoroughly after handling. Use good personal hygiene practices
procedures such as ASTM D-4276 and 29CFR 1910.146. Do not wear contaminated clothing or shoes.
Spills will produce extremely slippery surfaces. Do not enter confined spaces such as tanks or pits without following proper entry
well-ventilated areas. Store only in approved containers. Keep away from any incompatible material (see Section 10). Protect
Conditions for safe storage: Keep containers) tightly closed and properly labeled. Use and store this material in cool, dry,
container(s) against physical damage.
Section 8: Exposure Controls / Personal Protection
Note: State, local or other agencies or advisory groups may have established more stringent limits. Consult an industrial
hygienist or similar professional, or your local agencies, for further information.

<<<PAGE 1112>>>

Emergency, Customer Service and Technical phone numbers have NOT changed.
Transition SDS: Product is now manufactured by Phillips 66 Company.
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
472980 - LP ™ 100 Flow Improver
Date of Issue: 12-Jan-2012
Status: FINAL
Page 3/6
controls may be necessary if working with the product in enclosed areas and/or at elevated temperatures.
Engineering controls: General ventilation should be adequate for normal conditions of intended use. Additional engineering
ye/Face Protection: The use ot eye/tace protection is not normally required; however, good industrial hygiene practice sugges
le use of eye protection that meets or exceeds ANSI Z.87.1 whenever working with chemicals
use of gloves or other appropriate skin protection whenever working with chemicals.
Skin/Hand Protection: The use of skin protection is not normally required; however, good industrial hygiene practice suggests the
conditions that could result in significant airborne exposures may require the use of NIOSH approved respiratory protection. An
Respiratory Protection: Respiratory protection is not normally required under intended conditions of use. Emergencies or
industrial hygienist or other appropriate health and safety professional should be consulted for specific guidance under these
situations.
available information. Users should consult with the specific manufacturer to confirm the performance of their protective
Suggestions provided in this section for exposure control and specific types of protective equipment are based on readily
equipment. Specific situations may require consultation with industrial hygiene, safety, or engineering professionals.
Section 9; Physical and Chemical Properties
are not intended to be specifications.
Note: Unless otherwise stated, values are determined at 20°C (68°F) and 760 mm Hg (1 atm). Data represent typical values and
Appearance:
Physical Form:
Liquid
Opaque White
Odor:
Odor Threshold:
Mild
No data
pH:
Vapor Pressure:
10.0-12.3
Vapor Density (air=1):
> 1
23.8 mm Hg @ 77F / 25°C
Melting/Freezing Point:
Initial Boiling Point/Range:
32 °F / 0 °C
212 °F / 100 °C
Solubility in Water:
Specific Gravity (water=1):
Partition Coefficient (n-octanol/water) (Kow):
Partial
0.87 - 0.94 @ 60°F (15.6°C)
No data
Viscosity:
Bulk Density:
8.09 Ibs/gal
Flash Point:
Evaporation Rate (nBuAc=1):
350 cP @ 555s-1 @ 77°F / 25°C (Non-Newtonian)
No data
Lower Explosive Limits (vol % in air):
No data
N/A
Upper Explosive Limits (vol % in air):
Auto-ignition Temperature:
No data
No data
Section 10: Stability and Reactivity
Stability: Stable under normal ambient and anticipated conditions of use.
Conditions to Avoid: Avoid high temperatures and all sources of ignition.
Materials to Avoid (Incompatible Materials): Avoid contact with strong oxidizing agents
Hazardous Decomposition Products: Not anticipated under normal conditions of use.
Hazardous Polymerization: Not known to occur.
Section 11: Toxicological Information
Information on Toxicological Effects of Substance/Mixture
Acute Toxicity
Hazard
Additional Information
LC50/LD50 Data

<<<PAGE 1113>>>

Transition SDS: Product is now manufactured by Phillips 66 Company.
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
Emergency, Customer Service and Technical phone numbers have NOT changed.
472980 - LP™M 100 Flow Improver
Date of Issue: 12-Jan-2012
Status: FINAL
Page 4/6
Inhalation
Unlikely to be harmful
>5 mg/L (mist,
estimated)
Skin Absorption
Unlikely to be harmful
> 2 g/kg (estimated)
Ingestion (Swallowing)
Unlikely to be harmful
> 5 g/kg (estimated)
Aspiration Hazard: Not an aspiration hazard.
Skin Corrosion/Irritation: Not expected to be irritating.
Serious Eye Damage/Irritation: Not expected to be irritating.
Signs and Symptoms: No known effects of overexposure.
sensitization (or are below the concentration threshold for classification).
Skin Sensitization: No information available on the mixture, however none of the components have been classified for skin
for respiratory sensitization (or are below the concentration threshold for classification).
Respiratory Sensitization: No information available on the mixture, however none of the components have been classified
components have been classified for target organ toxicity (or are below the concentration threshold for classification).
Specific Target Organ Toxicity (Single Exposure): No information available on the mixture, however none of the
components have been classified for target organ toxicity (or are below the concentration threshold for classification).
Specific Target Organ Toxicity (Repeated Exposure): No information available on the mixture, however none of the
carcinogenicity (or are below the concentration threshold for classification)
Carcinogenicity: No information available on the mixture, however none of the components have been classified for
Germ Cell Mutagenicity: No information available on the mixture, however none of the components have been classified for
germ cell mutagenicity (or are below the concentration threshold for classification).
Reproductive Toxicity: No information available on the mixture, however none of the components have been classified for
reproductive toxicity (or are below the concentration threshold for classification).
Section 12: Ecological Information
Toxicity: Not expected to be harmful to aquatic organisms based on test data from the individual components or similar materials.
Persistence and Degradability: Not expected to persist in the environment if spilled or released.
Bioaccumulative Potential: Not expected to bioaccumulate in the environment based on its physical properties
Mobility in Soil: Expected to have low mobility in soil and sediments with adsorption being the predominant physical process
Other Adverse Effects: None anticipated.
Section 13: Disposal Considerations
and local requirements in addition to federal regulations.
The generator of a waste is always responsible for making proper hazardous waste determinations and needs to consider state
exhibit characteristics of hazardous waste.
This material, if discarded as produced, would not be a federally regulated RCRA "listed" hazardous waste and is not believed to
Section 9 for physical/chemical properties. It is possible that the material as produced contains constituents which are not required
See Sections 7 and 8 for information on handling, storage and personal protection and
to be listed in the MSDS but could affect the hazardous waste determination. Additionally, use which results in chemical or physical
change of this material could subject it to regulation as a hazardous waste.
Container contents should be completely used and containers should be emptied prior to discard.
Section 14: Transport Information
U.S. Department of Transportation (DOT)

<<<PAGE 1114>>>

Transition SDS: Product is now manufactured by Phillips 66 Company.
Emergency, Customer Service and Technical phone numbers have NOT changed.
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
Date of Issue: 12-Jan-2012
472980 - LP™ 100 Flow Improver
Status: FINAL
Page 5/6
Shipping Description:
Not regulated
International Maritime Dangerous Goods (IMDG)
Shipping Description:
Not regulated
UN/ID #:
International Civil Aviation Org. / International Air Transport Assoc. (ICAO/IATA)
Not regulated
Packaging Instruction #:
LTD. QTY
Passenger Aircraft
Cargo Aircraft Only
Max. Net Qty. Per Package:
Section 15: Regulatory Information
This material does not contain any chemicals subject to the reporting requirements of SARA 302 and 40 CFR 372.
CERCLA/SARA - Section 302 Extremely Hazardous Substances and TPQs (in pounds):
CERCLA/SARA - Section 311/312 (Title Ill Hazard Categories)
Acute Health:
Chronic Health:
No
Fire Hazard:
Pressure Hazard:
No
No
Reactive Hazard:
No
This material does not contain any chemicals subject to the reporting requirements of SARA 313 and 40 CFR 372.
CERCLA/SARA - Section 313 and 40 CFR 372:
EPA (CERCLA) Reportable Quantity (in pounds):
This material does not contain any chemicals with CERCLA Reportable Quantities
California Proposition 65:
reproductive harm at concentrations that trigger the warning requirements of California Proposition 65.
This material does not contain any chemicals which are known to the State of California to cause cancer, birth defects or other
International Hazard Classification
None
GHS Classification:
Canada:
MSDS contains all the information required by the Regulations.
This product has been classified in accordance with the hazard criteria of the Controlled Products Regulations (CPR) and the
WHMIS Hazard Class:
None
All components are either listed on the US TSCA Inventory, or are not regulated under TSCA
National Chemical Inventories
All components are either on the DSL, or are exempt from DSL listing requirements.
U.S. Export Control Classification Number: EAR99
Section 16: Other Information
Status:
Date of Issue:
12-Jan-2012
Previous Issue Date:
FINAL
Revised Sections or Basis for Revision:
18-Jun-2008
Identified Hazards (Section 2)
Physical Properties (Section 9)
Toxicological (Section 11)
SDS Number:
472980
Environmental hazards (Section 12)

<<<PAGE 1115>>>

Transition SDS: Product is now manufactured by Phillips 66 Company.
For SDS information please email SDS@P66.com or visit www.Phillips66.com.
Emergency, Customer Service and Technical phone numbers have NOT changed.
472980 - LP ™ 100 Flow Improver
Date of Issue: 12-Jan-2012
Status: FINAL
Page 6/6
ACGIH = American Conference of Governmental Industrial Hygienists; CASRN = Chemical Abstracts Service Registry Number; CEILING = Ceiling
Guide to Abbreviations:
Agency; GHS = Globally Harmonized System; IARC = International Agency for Research on Cancer; INSHT = National Institute for Health and
Limit (15 minutes); CERCLA = The Comprehensive Environmental Response, Compensation, and Liability Act; EPA = Environmental Protection
Protection Association; NTP = National Toxicology Program; OSHA = Occupational Safety and Health Administration; PEL = Permissible Exposure
Safety at Work; IOPC = International Oil Pollution Compensation; LEL = Lower Explosive Limit; NE = Not Established; NFPA = National Fire
Value (ACGIH); TWA = Time Weighted Average (8 hours); UEL = Upper Explosive Limit; WHMIS = Worker Hazardous Materials Information
Limit (OSHA); SARA = Superfund Amendments and Reauthorization Act; STEL = Short Term Exposure Limit (15 minutes); TLV = Threshold Limit
System (Canada)
The information presented in this Material Safety Data Sheet is based on data believed to be accurate as of the date this Material
Disclaimer of Expressed and implied Warranties:
Safety Data Sheet was prepared. HOWEVER, NO WARRANTY OF MERCHANTABILITY, FITNESS FOR ANY PARTICULAR
COMPLETENESS OF THE INFORMATION PROVIDED ABOVE, THE RESULTS TO BE OBTAINED FROM THE USE OF THIS
PURPOSE, OR ANY OTHER WARRANTY IS EXPRESSED OR IS TO BE IMPLIED REGARDING THE ACCURACY OR
responsibility is assumed for any damage or injury resulting from abnormal use or from any failure to adhere to recommended
INFORMATION OR THE PRODUCT, THE SAFETY OF THIS PRODUCT, OR THE HAZARDS RELATED TO ITS USE. No
practices. The information provided above, and the product, are furnished on the condition that the person receiving them shall
the risk of their use. In addition, no authorization is given nor implied to practice any patented invention without a license.
make their own determination as to the suitability of the product for their particular purpose and on the condition that they assume

<<<PAGE 1116>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6E
REFERENCED PROCEDURES OF THE MAGELLAN 2012 SIP

<<<PAGE 1117>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6E
REFERENCED PROCEDURES OF THE MAGELLAN 2012 SIP
CHAPTER 6:
SIP-ADM 2.01
SIP-ADM 2.02
SIP-ADM 4.01
SIP-ADM 7.01
SIP-ADM 7.03
SIP-ADM 7.03-001
SIP-ADM 7.04-001
SIP-ADM 7.04-002
SIP-ADM 7.04-006
SIP-ADM 7.04-015
SIP-ADM 7.04-016
SIP-ADM 7.04-023
SIP-ADM 7.05-002
SIP-ADM 7.05-003
SIP-ADM 7.05-009
SIP-ADM 7.05-012
SIP-ADM 7.05-014
SIP-ADM 7.05-020
SIP-ADM 7.05-030
SIP-ADM 7.05-031
SIP-ADM 7.05-039
SIP-ADM 7.06
SIP-ADM 8.01
SIP-ADM 10.01

<<<PAGE 1118>>>

Magellan Midstream Partners, L.P.
TRAINING SIP–ADM–2.01
Training 01/01/12 Revision: 8 Page 1 of 4
1.0 OBJECTIVE
1.1 The objective of this initiative is to describe the roles and responsibilities associated with
regulatory required training.
2.0 DESCRIPTION
2.1 This initiative represents a baseline of regulatory training requirements as defined by the
Company and enables Company personnel, including new and transferred employees, to acquire
the knowledge and skills needed to work in a safe, healthy and productive manner and to comply
with all training requirements of applicable laws and regulations.
3.0 STANDARDS
3.1 All Employees shall:
3.1.1 Complete federal, state or facility‐specific training as identified on the Training Matrix,
or by the immediate supervisor.
3.1.2 Complete assigned training as identified on the Individual Training Plan prior to
performing applicable tasks independently when newly assigned to field operations.
NOTE: An explanation of the ITP is contained in the plan.
3.2 3.3 3.1.3 Complete professional or Company mandated training as identified by the immediate
supervisor.
3.1.4 Document attendance at training sessions on the Training Roster.
Leadership shall (as defined on the training matrix):
3.2.1 Assign applicable training requirements per the Individual Training Plan to any employee
new or newly transferred to field operations within 30 days of their start date. Upon
completion of the training requirements the ITP form shall be sent to the Training
Department and a copy maintained locally.
3.2.2 Review and communicate Training Matrix requirements to all existing employees
annually.
3.2.3 Identify and communicate any facility‐specific, or state required training to direct
reports.
3.2.4 Discuss and review each direct report’s Emergency Response Training skills
annually not to exceed 15 months. Provide suggestions as necessary to make
the Training more effective. Document the review and any suggestions on the
Emergency Response Training Evaluation Form. Maintain the completed form
locally. This is intended for any direct report that would reasonably respond in an
emergency.
3.2.4.1 Send a copy of suggested changes (if any) to the Training Supervisor within
seven days of completing the form.
The Supervisor of Training and Staffing shall:
3.3.1 Ensure training requirements and tools are reviewed, developed, and documented to
comply with all federally regulated and legally required training.

<<<PAGE 1119>>>

Magellan Midstream Partners, L.P.
TRAINING SIP–ADM–2.01
Training 01/01/12 Revision: 8 Page 2 of 4
3.3.2 3.3.3 3.3.4 3.3.5 3.3.6 Provide guidance to leadership as requested, in order to help ensure compliance with
state and local training requirements.
Meet with all directors and managers to determine nonregulatory and noncompliance
training needs for the following year’s training plans by the end of the 4th quarter.
Maintain and communicate available training materials and tools to the Company
annually, or as changes are made.
Maintain training records in a compliance management system for Company employees
and work with appropriate business group representatives to ensure compliance with
data management.
Maintain an Emergency Response curriculum that is compliant to DOT 195.403 and.
Incorporate improvement suggestions into training annually. At a minimum this
curriculum shall provide instructions for employees to:
3.3.6.1 Carry out the emergency response procedures applicable to their
assignment.
3.3.6.2 Know what the characteristics and hazards of the hazardous liquids or
carbon dioxide transported are, including, in case of flammable HVL,
flammability of mixtures with air, odorless vapors, and water reactions.
3.3.6.3 Recognize conditions that are likely to cause emergencies, predict the
consequences of facility malfunctions or failures and hazardous liquids or
carbon dioxide spills, and take appropriate corrective action.
3.3.6.4 Take steps necessary to control any accidental release of hazardous liquid
or carbon dioxide and to minimize the potential for fire, explosion, toxicity,
or environmental damage.
3.3.6.5 Learn the potential causes, types, sizes and consequences of fire
would/could be and how to appropriately use portable fire extinguishers
and other on‐site fire control equipment, involving (when feasible), a
simulated pipeline emergency condition.
3.4 All Managers shall:
3.5 3.6 3.4.1 Assist the Manager of Training and Staffing in identifying training topics necessary to
meet regulatory requirements and/or facility‐specific issues (e.g., Process Safety
Management requirements).
The Field Office Administrator Shall:
3.5.1 Assist in the coordination of scheduling dates and locations for any training in their area.
The Supervisor at Marine Facilities Shall:
3.6.1 Complete the requirements in the Marine Person‐In‐Charge Qualification as needed to
certify individuals to perform dock transfer operations.

<<<PAGE 1120>>>

Magellan Midstream Partners, L.P.
TRAINING SIP–ADM–2.01
Training 01/01/12 Revision: 8 Page 3 of 4
SYSTEM INTEGRITY PLAN CHANGE LOG
Date Location Brief Description of Change
1/1/05 1.1 Rephrased
2.1 Rephrased
3.1.1 Rephrased, combined 3.1.1 and 3.1.2 (2004)
3.2.1 Added requirement for review of operations and maintenance procedures
3.2.4 Removed requirement
3.3.4, 3.3.5 Removed requirements from 2004
3.4 Added Safety Representatives
3.4.1 Removed requirement from2004
3.4.3 Rephrased into 3.4.1 2005
3.4.3 Added for 2005
3.5 Removed standard from 2004
1/1/06 3.2.1 Changed to 180 days from one week
01/01/06 1.1 Deleted “provide training that will reduce risk to Company employees, the public, environment and
property as well as provide professional development to Company employees as appropriate” and added
“describe the roles and responsibilities associated with regulatory required training.”
01/01/06 2.1 Added “training requirements of”
01/01/06 3.3.2 Added “to leadership”
01/01/06 3.4.1 Deleted “training team” added “Training Supervisor”
01/01/06 3.4.2 Added training matrix
01/01/06 3.2.4 Moved from 12.01
01/01/06 3.2.4 Deleted “Evaluate participating employees during emergency response exercises and/or actual spill
events, as appropriate, utilizing the Emergency Response Training Document.”
01/01/06 3.2.4 added
3.2.4 Modified to correlate with modified form
3.3.1 Deleted standard regarding training matrix as this is covered in annual review.
1/1/07
3.3.5, 3.3.6 added
01/01/08 Reviewed, no changes
6/24/08 3.2.4 Added clarification for “not to exceed 15 months”
1/1/09 All Annual review complete
1/1/09 3.1.2, 3.2.1, Added
1/1/09 3.2 Modified
01/01/10 3.3.3 Changed from Oct to end of 4th qtr
3.3.4 Changed from qtrly to annually
3.1.4 Moved from All Mgrs section
3.5 (old) Removed General Consul and VP HR responsibilities
LINKS Removed non referenced links, obsolete links
01/01/10 3.1 Removed note box that referenced :How to Use TM”
01/01/11 Updated Supervisor of Training to Supervisor of Training and Staffing – new title
04/08/11 3.1.1/3.4 Removed reference to safety rep
12/31/11 3.2 Renamed the role of all supervisors to all leadership and clarified applicability
(training matrix, emergency response)
12/31/11 3.2.4 Clarified
12/31/11 3.5 FOA directive added (moved from manager)

<<<PAGE 1121>>>

Magellan Midstream Partners, L.P.
TRAINING SIP–ADM–2.01
Training 01/01/12 Revision: 8 Page 4 of 4
12/31/11 3.6 added
12/31/11 3.2.1 Added “Upon completion of the training requirements the ITP form shall be sent to
the Training Department and a copy maintained locally.”
12/31/11 All 2012 Annual Review complete

<<<PAGE 1122>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 1 of 8
1.0 OBJECTIVE
1.1 The objective of this initiative is to describe the primary processes used to comply with
DOT’s Operator Qualification (OQ) requirements. As such, this initiative and its
associated procedures comprise the majority of the Company OQ Plan.
2.0 DESCRIPTION
2.1 This initiative applies to the following components of the Company OQ Plan:
2.1.1 Identification of Covered Tasks
2.1.2 The evaluation process
2.1.3 Span of control
2.1.4 Suspending, assessing and reevaluation of qualified employees
2.1.5 Reevaluation intervals
2.2 2.1.6 Training as related to qualification
2.1.7 Notification for significant changes to the Plan
2.1.8 Program Effectiveness
This initiative does not include the following OQ Plan processes which are addressed in
their respective elements.
2.2.1 Change Management
2.2.2 Contractor Management
2.2.3 Definitions
2.2.4 Abnormal Operating Conditions (AOC)
3.0 STANDARDS
3.1 The OQ Coordinator shall:
3.1.1 3.1.2 Maintain and document the criteria for the Company Subject Matter Experts
(SMEs) who will review the Company Covered Tasks with input from leadership,
as appropriate. Maintain the list of Company SMEs for the Covered Tasks.
Maintain and document Evaluator Criteria.
3.1.3 Annually, or as needed, coordinate a review with the Company SMEs to review:
(1) The Covered Task List, (2) The qualification requirements for contractors and
(3) The evaluation materials and procedures. Revise as needed.
NOTE: The tasks on the Covered Task List shall, at a minimum, meet the four
part test as defined by PHMSA regulations.
3.1.4 3.1.5 Schedule evaluator training as needed. Maintain the Evaluator List showing
trained evaluators and the task categories they may evaluate. Update the
Evaluator List after completion of evaluator training, as necessary or applicable.
Develop, maintain and administer proctor training as needed. Maintain a list of
trained proctors on the Proctor List.
NOTE: Change communication is not required for updates to the Evaluator List

<<<PAGE 1123>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 2 of 8
or the Proctor List.
3.1.6 Establish and maintain the Covered Task List. The Covered Task list shall
document at least:
3.1.6.1 3.1.6.2 NOTE: Work Performance History Review and Observation During
on the Job Performance are not allowable evaluation methods.
3.1.7 3.1.8 3.1.9 3.1.10 3.1.11 3.1.12 3.1.13 The name, number and description of the covered task.
The type of evaluation method(s) allowed.
3.1.6.3 The reevaluation interval.
3.1.6.4 Span of control (criteria for directing and observing).
Develop and maintain the Written Evaluations, Study Guides and Answer Keys
for those Covered Tasks requiring a written examination for qualification.
Maintain document control to limit access to tests and answer keys to the
proctors.
Maintain and administer the Merger & Acquisition Procedure for incorporating
acquired employees into the Company OQ plan.
Manage and maintain ISN as the Company’s OQ record-keeping system for
employees and for contractors. Records shall be maintained for five years. At a
minimum, the record-keeping shall consist of:
3.1.9.1 The identification of the Qualified Individual.
3.1.9.2 Identification of the Covered Tasks that the individual is qualified to
perform.
3.1.9.3 Date(s) of current qualification.
3.1.9.4 Qualification method(s).
Work with appropriate leadership to identify any mutual assistance arrangements
and ensure that mutual assistance individuals are appropriately qualified to
perform Covered Tasks.
Oversee the Company OQ Plan as needed to ensure compliance. Oversight
may consist of, but is not limited to, maintaining the OQ Protocol cross-reference,
conducting spot-checks of OQ processes, initiating changes to the OQ Plan, and
making final determination for any exception(s) to the plan that may be brought
forward.
Review any site-specific procedures for a Covered Task prior to local
implementation.
Develop and maintain OQ effectiveness measures and provide periodic updates
to management. Effectiveness measures may include:
3.1.13.1 Adequacy of training for specific covered task(s).
3.1.13.2 Adequacy of evaluation(s) to determine if individual has required
knowledge, skills, and abilities.
3.1.13.3 Adequacy of individual to recognize AOC(s).
3.1.13.4 Adequacy of individual to take appropriate action after an AOC.

<<<PAGE 1124>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 3 of 8
3.2 3.1.14 Send the OPS Information Resource Manager, and state agencies as applicable,
the revised OQ Plan within 60 days of approval and implementation of any
significant modifications. At a minimum, significant modifications would include:
3.1.14.1 Increasing evaluation intervals.
3.1.14.2 Increasing span of control ratios.
3.1.14.3 Eliminating covered tasks.
3.1.14.4 Mergers and/or acquisition changes.
3.1.14.5 Evaluation method changes such as written vs. observation.
3.1.14.6 Wholesale changes made to OQ plan.
3.1.15 Provide guidance to management regarding OQ qualifications in the unlikely
event of a large workforce displacement due to events such as natural disasters,
pandemics, workforce stoppages, etc.
3.1.15.1 Notify PHMSA in writing within 90 days of a workforce displacement
if personnel were utilized to perform covered tasks who did not meet
the Company OQ requirements.
The Subject Matter Expert shall:
3.2.1 Upon request from the OQ Coordinator, utilize their experience and knowledge to
review and recommend as necessary, modifications to covered tasks in their
area of experience on the Covered Task List.
3.2.2 Upon request from the OQ Coordinator review and update the Task Category
Criteria of the Evaluator Criteria .
3.2.3 Upon request from the OQ Coordinator review and update the Evaluation
Checklists for covered tasks in their area of expertise.
3.3 All Supervisors shall:
3.3.1 Identify individuals to serve as Company SMEs for the covered task review when
requested by the OQ Coordinator.
3.3.2 Require evaluators to meet evaluator requirements as shown on the Evaluator
Criteria before conducting OQ evaluations.
3.3.3 Prior to any employee’s initial or non-routine evaluation, assess training needs,
document and provide training using the Individual Training Plan (ITP). Maintain
the ITP locally for three years.
NOTE: Operations Controllers shall comply with required Operations Control
training requirements in lieu of the ITP for OQ training and documentation.
3.3.4 Coordinate the evaluation with the individual and the evaluator or proctor upon
completion of OQ training or as required. Allow a sufficient amount of time to
pass before scheduling an evaluation following a failed evaluation; normally this
time is three days for a performance type evaluation or the next business day for
a written evaluation. Inform the individual they are not to perform a Covered
Task after failing an evaluation unless they perform it in accordance with the
Span of Control or have successfully been reevaluated. For performance type
evaluations, discuss the evaluation with the individual and sign the completed
OQ Checklist upon receipt and forward to the appropriate OQ Records
Administrator.

<<<PAGE 1125>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 4 of 8
NOTE: Evaluations following a failed evaluation are considered “non-routine.”
3.3.5 Determine applicable Covered Task(s) for each employee in the work group and
provide information to the OQ Records Administrator for documentation in ISN.
Review and submit updates as required, such as following a job scope change or
reorganization.
NOTE: AOC evaluations are required for all employees performing OQ covered
tasks.
3.3.6 3.3.7 Upon notification of an incident (as defined in the 7000-1 Report) determine if an
employee’s performance of a covered task contributed to that incident or if the
performance cannot be ruled out as contributing to the incident. If the
determination is affirmative:
3.3.6.1 Assess the employee’s actions in performing the covered task,
including a procedure review if appropriate, and determine whether
the employee’s relevant OQ task(s) should be suspended.
3.3.6.2 If the employee’s relevant OQ task(s) are not suspended:
3.3.6.2.1. Determine if any additional action is required such as a
more thorough procedure review, submitting a
suggestion to revise the procedure, refresher training,
etc., and document on the Corrective Action section of
the Incident Report.
3.3.6.3 If the employee’s relevant OQ task(s) are suspended:
3.3.6.3.1. Inform the employee that they are not allowed to perform
the applicable Covered Task until they have completed
any training or requalification actions.
3.3.6.3.2. Notify the OQ Records Coordinator when feasible to
document the assessment results and suspension (if
applicable) in ISN.
3.3.6.3.3. Provide training and reevaluation for the
individual(s). Document on the Individual Training Plan
(ITP).
3.3.6.4 Determine if any information regarding this incident or the safe
performance of the applicable covered task beyond the standing
incident review agenda item should be included in a SIP meeting.
Include this information on the SIP meeting agenda if warranted.
Require reevaluation for any employee if there is reason to believe the employee
is no longer qualified. The employee shall be suspended from performing the
covered task until he/she has successfully completed the applicable OQ
evaluation. The suspension and reevaluation shall be documented in ISN.
These evaluations shall be considered non-routine.

<<<PAGE 1126>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 5 of 8
Examples of situations that may raise concerns about an individual’s ability to
perform a Covered Task include, but are not limited to:
 Loss of motor skills, vision, or other impairment as evidenced by written
notification from a licensed health care professional.
 Statement from the employee regarding his/her qualification.
 Prolonged period of not performing the task.
 Unsatisfactory execution of the task such as during the job or during an
inspection.
 Substantiated complaints from a third party or another employee regarding
incorrect performance of the task.
 Involvement in a near miss or other incident (as defined in SIP) or AOC.
 Observation of the employee performing the covered task incorrectly.
3.3.8 Submit site-specific procedures for a Covered Tasks to the OQ Coordinator for
review and approval prior to implementation.
3.3.9 Quarterly review employees OQ records to ensure that the records are correct
and to schedule any evaluations prior to expiration.
3.4 All Managers shall:
3.4.1 Designate an OQ Records Administrator to maintain OQ records in ISN.
3.5 The OQ Evaluator shall:
3.5.1 3.5.2 Attend evaluator training in order to be considered an OQ evaluator.
Conduct OQ evaluations according to the Evaluation Procedure and the Covered
Task List.
3.6 The OQ Proctor shall:
3.6.1 Conduct OQ written evaluations in accordance with the rules and guidelines
provided in Proctor Training. Maintain the confidentiality of the written evaluations
and answer keys.
3.7 The Employee shall:
3.7.1 Complete any training prior to initial or nonroutine OQ evaluations as described
on the Individual Training Plan (ITP).
3.7.2 Complete OQ evaluations as scheduled and as described in the Evaluation
Procedure.
3.7.3 Perform Covered Tasks as required per the Span of Control as shown on the
Covered Task List.
3.7.4 Inform contractor employees of their specific expectations following an incident or
AOC via the Job Plan and/or ATW.
3.8 The OQ Records Administrator shall:
3.8.1 Enter and update OQ records in ISN upon receipt from Supervisor as described
in ISN Directions for Entering OQ Evaluations.
3.8.1.1 3.8.1.2 Enter completed evaluations within two weeks of receipt.
Enter suspensions or revocations as soon as feasible.

<<<PAGE 1127>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 6 of 8
3.9 3.8.2 Maintain no more than one set of paper copies of evaluations. Ensure that these
records have been completed per the ISN Directions for Entering OQ
Evaluations. Return any deficient paperwork to the supervisor for correction prior
to filing and entering into ISN.
The Vice President of Operations shall:
3.9.1 Provide the most qualified workforce possible in the unlikely event of a large
workforce displacement due to events such as natural disasters, pandemics,
workforce stoppages, etc. Qualification considerations will be based, but not
limited to, the following factors:
3.9.1.1 Current Company OQ qualifications.
3.9.1.2 Previous task experience.
3.9.1.3 Task training.
3.9.1.4 Previous Company OQ qualifications.
3.9.1.5 Current or previous OQ qualifications outside of Company OQ
requirements.

<<<PAGE 1128>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 7 of 8
SYSTEM INTEGRITY PLAN CHANGE LOG
DATE LOCATION BRIEF DESCRIPTION OF CHANGE
1/1/05 1.1 Shortened objective. DOT references were redundant.
2.1 Separated description into two standards.
3.1.1 Separated various elements of OQ Plan into separate standards.
3.1.2 Change Management is covered in 11.02 (2005)
3.1.3 Moved to standard 3.1.1 (2005)
3.2.1 Rephrased and moved to 3.3.4 (2005)
3.2.2 Rephrased and moved to 3.3.7 (2005)
3.2.3 Rephrased and moved to 3.3.3 (2005)
3.2.4 Deleted – record-keeping system will do
3.2.5 Rephrased and moved to evaluation procedure (2005)
3.2.6 Deleted
3.4.1 Deleted
3.4.2 Rephrased and moved to 3.5.2 (2005)
3.5.1 Deleted
All others Added
4/12/04 1.1 Included DOT 192 part N
3.2.3 Note box Added guidance for when qualification may need to be evaluated
3.2.4 Note box Added 3‐year re‐qualification requirement
3.2.7 Added mutual assistance standard
3.3.1 Note box Added evaluation requirements for mutual assistance
3.4.1 Note box Included options for qualifying on AOCs
01/01/06 3.1.10 Corrected mutual assistance employees to mutual assistance individual. Low
impact change.
1/1/06 3.6 Added record-keeping responsibilities
1/1/06 3.3.6 and 3.3.7 Clarified
1/1/06 3.1.12 Added
01/01/06 3.0 Deleted “Maintain the Evaluation Procedure”
1.1 Added clarification to explain this initiative’s role in the OQ Plan.
2.0 Modified to list OQ Plan elements.
3.1.1, 3.1.3, 3.3.2 Minor modifications
3.1.4, 3.1.5, 3.1.7,
3.1.12, 3.2.3
added
3.1.9 Combined contractors and employees - ISN

<<<PAGE 1129>>>

Magellan Midstream Partners, L.P.
OPERATION QUALIFICATION SIP–ADM–2.02
Training 01/01/12 Revision: 8 Page 8 of 8
3.1.14 Added specific criteria
3.3.3 Modified training requirements
3.3.4 added
3.3.6 Modified suspension/revocation standards
3.3.7 Modified
3.3.8 added
1/1/07
3.4 Added Managers responsibilities
3.6 Added proctor standards
3.4.2 Modified for training requirements
3.4.4 Added span of control requirements
3.7 Modified
01/01/08 Reviewed, no changes
All Annual review complete
3.1.5 added
3.3.3 Revised to ITP
1/1/09
3.3.5 Modified to include AOCs
3.3.6 revised
3.7.4 added
3.9 added
2/01/09 3.3.3 Changed from 5 to 3 yrs
3.7.1 Changed from OQ Training sheet to ITP
01/01/10 all Activated inactive links
3.1.13, 3.1.14 Modified per PHMSA advisory
3.1.6.2 Added notebox to support PHMSA advisory
01/01/11 Reviewed, no changes
03/09/11 3.1.3 Note Removed DOT 192 and DOT 195 reference and added PHMSA regulations.
12/31/11 3.1.13 Added “may” since list is not inclusive
12/31/11 3.2 Clarified process
12/31/11 3.3.3 Clarified process
12/31/11 3.3.4 Added language to clarify process for written evaluations and for
performance evaluations
12/31/11 3.3.9 added
12/31/11 all 2012 annual review complete

<<<PAGE 1130>>>

Magellan Midstream Partners, L.P.
PROJECT MANAGEMENT SIP–ADM–4.01
Project Management 01/01/12 Revision: 8 Page 1 of 4
1.0 OBJECTIVE
1.1 The objective of this initiative is to describe the process used to manage projects.
2.0 DESCRIPTION
2.1 The Project Management initiative applies to the development, design, project management,
construction, commissioning, and post project performance assessment of new and modified
assets.
Non‐complex repairs and like‐kind replacements are generally excluded from this initiative.
2.2 The assets that comprise the Galena Park to El Paso pipeline, Crane to Odessa Pipeline and the
associated facilities are covered by the Mitigation Plan.
2.2.1 The Mitigation Plan places specific requirements in addition to applicable Federal, State
and Local regulations, Company SIP requirements, Company guidelines, process, or best
practices. Refer to the Mitigation Plan for those requirements.
3.0 STANDARDS
3.1 The Project Sponsor shall:
3.1.1 Notify Legal and the Director of Environmental, Health, Safety and Security of any new
type of business or operation involving Company assets upon discovery to determine if
there are regulatory, permitting, or licensing requirements for construction or operation
of new or modified assets.
3.1.2 Review and approve the Definitive Project Plan and the Authorization for Expenditure
(AFE).
3.1.3 Advise management of project deviations that impact cost, timing, or functionality, and
obtain approvals in accordance with the Company’s Delegation of Authority policy.
3.1.4 Obtain Supplemental AFE approvals in accordance with Magellan’s AFE Policy.
3.2 The Project Manager shall:
3.2.1 Utilize the applicable Company Standards (Design and Construction) List on all projects.
3.2.2 If deviation from a Company standard is desired, consult and obtain approval from the
Subject Matter Expert (SME), as designated in the Company Standards (Design and
Construction) List on and the Director of Engineering and Construction or Director of
3.2.3 3.2.4 Asset Integrity prior to proceeding.
Require design drawings be reviewed and stamped by a Professional Engineer who is
appropriately licensed if:
3.2.3.1 Required by any local, state or federal code or law.
3.2.3.2 Required by contract.
3.2.3.3 Required by Project Manager or Project Sponsor.
Prepare and obtain approval on a Definitive Project Plan prior to AFE submittal.

<<<PAGE 1131>>>

Magellan Midstream Partners, L.P.
PROJECT MANAGEMENT SIP–ADM–4.01
Project Management 01/01/12 Revision: 8 Page 2 of 4
NOTE: The Definitive Project Plan includes the Objective, Description, Cost Estimate
and Basis, Schedule, OBS, Risks, and Core Project Team and Project Sponsor Approvals.
3.2.5 3.2.6 3.2.7 3.2.8 Comply with the Environmental Aspects of Project Management Procedure. Engage
with appropriate Environmental SME(s) as required during the project and prior to
each of the following milestones: Permit Submittal, Start of Design, Start of
Construction and Start Up.
Comply with the Project Final Checkout Scheduling Guideline as soon as the AFE is
signed.
Provide quality control during construction activities to ensure compliance with
industry codes, government regulations and Company standards.
Select on‐site inspectors in accordance with the Contract Inspector Selection Matrix as
applicable or necessary.
3.2.9 For PSM/RMP projects, validate and document that new and modified equipment are
designed, installed, tested, and operated in accordance with design specifications and
manufacturer’s instructions. Validate and document that associated maintenance
materials, spare parts, and equipment are suitable for the process application. Place
these documented validations and other PSM/RMP documentation in the local
PSM/RMP files (or manual). Utilize the Documentation Checklist for New PSM/RMP
Facilities as a guideline for identifying the required PSM/RMP documents.
3.2.10 3.2.11 Manage project costs and provide updates to the Core Project Team and Project
Sponsor on anticipated deviations in costs, schedule and scope deviations in advance of
their occurrence.
Obtain approvals using the Project Change Document for deviations in the Definitive
Project Plan that result in more than a $10,000 or a five percent increase in the total
3.2.12 3.2.13 3.2.14 3.2.15 3.2.16 AFE.
Notify the Project Sponsor when the forecast of AFE expenditures exceeds the currently
approved AFE amount by $100,000 or when the forecast of AFE expenditures is greater
than $10,000 and 15% of the currently approved AFE amount.
Submit cost estimates for Supplemental AFEs as requested by the Project Sponsor.
Obtain Company approvals for service contract revisions (typically an RFS) when the
sum of accumulated changes exceeds $100,000, or when the sum of accumulated
changes is greater than $10,000 and 15% of the currently approved service contract.
3.2.14.1 Compare labor rates for specific RFS contracts with the rates in the
contractor’s current Master Service Agreement (MSA). If those rates
exceed rates established in the MSA, then obtain written approval from
the next level of Management.
Prepare and submit the Notice of Completion Form to Property Accounting when the
project is mechanically complete, placed into service, or determined to be ready for
service.
Provide project documentation to Operations and the Asset Integrity Record
Coordinator upon project completion.

<<<PAGE 1132>>>

Magellan Midstream Partners, L.P.
PROJECT MANAGEMENT SIP–ADM–4.01
Project Management 01/01/12 Revision: 8 Page 3 of 4
3.2.17 3.2.18 3.2.16.1 Provide copies of all project governmental and regulatory permits to local
operations and to Project Support to post on Livelink.
Solicit Stakeholder input on whether a Post Project Assessment Survey should be
conducted for projects that require a Supplemental AFE or that exceed $500,000 in total
costs. Summarize the Stakeholder input and submit to the Core Project Team and
Project Sponsor.
Conduct a Post Project Assessment Survey for projects completed in excess of
3.3 3.4 $10,000,000, or as requested by the Core Project Team.
The Project Management Element Owner shall:
3.3.1 Maintain the Project Life Cycle Process (PLC) Reference Materials.
The Core Project Team shall:
3.4.1 3.4.2 Determine if the Post Project Assessment Survey should be conducted for Projects less
Review and approve the Definitive Project Plan and the AFE.
than $10,000,000.

<<<PAGE 1133>>>

Magellan Midstream Partners, L.P.
PROJECT MANAGEMENT SIP–ADM–4.01
Project Management 01/01/12 Revision: 8 Page 4 of 4
System Integrity Plan Change Log
Date Location Brief Description of Change
1/1/05 3.1.6 Added PSM requirements including Note Box
1/1/06 SIP‐ADM‐4.01 Reviewed, no changes
04‐FORM‐4020 and
4030
Reviewed, no changes
2.1 Added post project assessment
3.1. 3.3, 3.4 added
1/1/07
3.2 Deleted PLC standard, modified Company Standards List
standards, added 3.2.8 – 3.2.14
01/01/07 OBJ and DESCRIP reworded
1/17/07 3.2.10 Added more specific requirements for supplemental AFE.
1/25/07 3.2.10 Added “Company” to clarify that the approval is internal.
1/1/09 3.1.3, 3.1.4, 3.2.1.3.1,
3.2.5
added
12/31/09 3.2.8 revised
12/31/09 3.2.11.1 added
12/31/09 All Annual review complete with the change above
12/31/10 All Annual review complete with the changes listed below.
12/31/10 3.2.5 Created an additional process for Environmental review of
projects.
12/31/10 3.2.12, 3.2.13 Separated supplemental AFEs and service contract revisions
into 2 standard s to clarify the role of the project sponsor for
AFE supplements.
12/31/10 2.2, 2.2.1 Added Reference to Mitigation Plan in E4.
2.1 Added note to further define application of project
management initiative.
3.2.1, 3.2.2 Updated link to point directly to the “Company Standards
List” instead of E&C website.
3.2.2 Added “Director of Asset Integrity” as option for deviation
approval.
12/31/11
3.2.4 Updated to reflect current process of Definitive Project Plan
required for AFE submittal.
3.2.12 Removed 2nd half of requirement
3.1.4 Added per AFE policy
3.2.13 added
12/31/11 All 2012 Annual Review complete

<<<PAGE 1134>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECTS REQUIRING REPAIRS AND REPAIR
PROCEDURE
SIP–ADM–7.01
Asset Integrity 01/01/12 Revision: 6 Page 1 of 2
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity by establishing a consistent process
for inspecting, evaluating, and repairing pipeline defects.
2.0 DESCRIPTION
2.1 Pipeline defects discovered through integrity tests such as in‐line inspections (ILI), hydrostatic
tests, or routine maintenance shall be assessed and repaired, in a timely and consistent manner
utilizing and complying with Company procedures, industry standards and applicable regulations
and recommended practices.
3.0 STANDARDS
3.1 The Employee shall:
3.1.1 3.1.2 Comply with the applicable Welding and Radiographic Procedures at all times.
3.1.3 3.2 The Records Coordinator shall:
3.2.1 Upon discovery or notification of a pipeline defect, immediately evaluate and repair the
defect in accordance with the Pipeline Defect Evaluation and Repair Procedure.
Complete the Pipeline Maintenance Report and forward to the Records Coordinator.
Review Pipeline Maintenance Report detail and notify Pipeline Mapping Coordinator of
3.2.2 any pipe record changes.
Update TIES database for any pipe record changes or when pipe data discrepancies are
discovered.

<<<PAGE 1135>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECTS REQUIRING REPAIRS AND REPAIR
PROCEDURE
SIP–ADM–7.01
Asset Integrity 01/01/12 Revision: 6 Page 2 of 2
System Integrity Plan Change Log
Date Change
Location
Changed By Approved By Brief Description of Change
9/29/04 All Clyde Clausen Michael Pearson 9/29/04 2.1 Clyde Clausen Michael Pearson 9/29/04 3.1 Clyde Clausen Michael Pearson 9/29/04 3.2 Clyde Clausen Michael Pearson Clyde Clausen Michael Pearson Conducted 2004 Annual Review, (See Change Log)
Minor modification to 2.1
Changed Asset Integrity Manager to Pipeline
Integrity Supervisor
Changed paragraph order of 3.2.1, 3.2.2 and 3.2.3
Changed Measure to: The number of pipeline
defects repaired, documented, and
categorized (Immediate, 60‐day, 180‐day,
9/29/04 5.1
and other) in accordance with section
8.2.2 of the Integrity Management
Program.
10/16/05 All Clyde Clausen Michael Pearson 10/16/06 All Clyde Clausen Michael Pearson 10/16/06 1.1 Clyde Clausen Michael Pearson 10/16/06 2.1 Clyde Clausen Michael Pearson 10/16/06 3.2.3 Clyde Clausen Michael Pearson 10/16/06 4.4 Clyde Clausen Michael Pearson 10/16/06 5.0 Clyde Clausen Michael Pearson 09/11/07 All Clyde Clausen Michael Pearson 9/11/07 3.2.3 Clyde Clausen Michael Pearson 9/11/08 All Clyde Clausen Doug Chabino 9/11/08 3.2.4 Clyde Clausen Doug Chabino 8/21/09 All Clyde Clausen Doug Chabino 01/01/11 9/1/11 All Clyde Clausen Doug Chabino 9/1/11 3.2 & 3.2.1 & Clyde Clausen Doug Chabino 12/31/11 All Conducted 2005 Annual Review, No Changes
Conducted 2006 Annual Review, (See Change Log)
Minor Modification to paragraph
Minor Modifications to paragraph and removed
d fi i i f “ i li d f ”
Added: For the Chase and Orion systems, complete
h PL 0746 Pi d C i R
Added Link
Deleted the Measure section
Conducted 2007 Annual Review, (See Change Log)
Removed reference to 30 days
Conducted 2008 Annual Review
Removed reference to Complete Pipeline Crossing
R f C D A Al R d h
Conducted Annual Review, minor changes to remove
d li i d d i l
Reviewed, no changes
Conducted Annual Review
Added Record Coordinator responsibilities
2012 Annual Review complete

<<<PAGE 1136>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 1 of 16
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for identification,
analysis and repair of pipeline defects when necessary.
2.0 PROCEDURE
2.1 General
2.1.1 2.1.2 2.1.3 Exceptions—This procedure may not apply to the following conditions:
2.1.1.1 Emergency situations such as a major pipeline release
2.1.1.2 Threaded piping
Defect assessment, RSTRENG Analysis of Corrosion or KAPA, Nondestructive
Testing, Maintenance Welding, Coating Application, and installation of repairs
(e.g., clamps, composite repairs) are Covered Tasks.
Welding on lines that are under internal pressure (live line welding) shall be done
in accordance with Company welding procedures and practices. Refer to
Specification 101, Maintenance Welding (Excluding Ethylene Pipelines).
2.2 Precautions
2.2.1 2.2.2 2.2.3 2.2.4 2.2.5 2.2.6 2.2.7 2.2.8 2.2.9 All exposed bell and spigot girth welds shall be reinforced by means of sleeving
If needed (when pipe is not resting on the ground) the pipe should be adequately
supported prior to backfilling. Consideration should be given to using dirt plugs or
sandbags at spacing intervals not to exceed 20 feet particularly in areas where
additional weight has been applied by installation of sleeving.
All exposed girth welds (including bell and spigot joints) shall be supported
(supports to be placed on each side of the girth weld not to exceed 5 feet) via
sandbags or equivalent settlement resistant supports prior to backfilling.
Pipeline defects discovered through integrity tests such as in-line inspections
(ILI), pressure test, and routine maintenance shall be assessed and repaired, in a
timely and consistent manner utilizing and complying with Company procedures,
industry standards and applicable regulations (DOT 195.452) and recommended
practices.
Pipeline defects (including general or localized corrosion) confirmed through
actual field findings (not reported by ILI tool) that meet the criteria of a pressure
reducing defect shall be repaired immediately. Upon discovery, a pressure and or
rate reduction, or line shutdown shall be considered.
Pipeline defects not repaired by means of full encirclement sleeving and or pipe
replacement should be non-destructively tested prior to recoating.
All repairs are made in a safe manner and are made so as to prevent damage to
persons or property and to comply with DOT 195.422.
All materials used for repairs or replacement such as sleeves, pipe, fittings, and
valves shall meet the minimum design requirements of the asset.
Ensure that the site and/or bell hole are safe, prior to and during pipeline
excavation activities. For specific guidelines to trenching, refer to the Excavation
Safety Procedure.

<<<PAGE 1137>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 2 of 16
2.3 2.4 2.2.10 Determine if the coating contains asbestos, before authorizing or allowing any
pipeline coating removal. Refer to the Asbestos Performance Procedure.
2.2.11 If the defect appears to be associated with product loss (leaking), take
appropriate measures as indicated by the Emergency Response Plans to shut
the line in or reduce the pressure in the pipeline to a safe pressure based on the
preliminary evaluation, feature site and pipeline operation information.
2.2.12 When cleaning pipe (i.e. sand blasting or power brushing) for preparation of
evaluating, repairing, or coating pipeline defects exercise extreme care as actual
depth of defect may be greater than reported or predicted. To ensure safe work
practices lightly clean pipe until it is evident that sufficient remaining wall exist to
allow thorough cleaning of the defect.
Review and Perform the Following General Steps For Evaluation of All Defects
2.3.1 Upon completion of the excavation, photograph the repair site prior to removing
the coating.
2.3.2 Prepare the site and pipeline for a detailed evaluation of the defect after it has
been determined it is safe to work on or near the pipeline. This includes
removing cover to fully expose the pipe, coating removal and appropriately
cleaning the feature to be evaluated in order to make detailed measurements of
the feature and to determine the type of defect.
2.3.3 2.3.4 Document all defect information on Pipeline Maintenance Report.
Visually determine the type of defect then use the appropriate part of this
procedure, listed below, to assist with feature evaluation and the recommended
repair options. Refer to Table 1 for a detailed listing of repair options. Under
special circumstances, the Manager of Asset Integrity can approve deviations
from the approved/preferred repair methods listed in Table 1.
2.3.4.1 Corrosion—Paragraph 2.4
2.3.4.2 Pipe body gouges and/or mill defects—Paragraph 2.5
2.3.4.3 Dents and Dents with associated gouges/stress risers—Paragraph
2.6
2.3.4.4 Arc Burns—Paragraph 2.7
2.3.4.5 Weld Defects—Paragraph 2.8
2.3.4.6 Stress Corrosion Cracking (SCC)—Paragraph 2.9
2.3.4.7 Selective Seam Corrosion (SSC)- Paragraph 2.10
2.3.4.8 Hard Spots—Paragraph 2.12
2.3.4.9 Buckling—Paragraph 2.13
2.3.4.10 Cracks- Long Seam and Pipe Body- Paragraph 2.13
Evaluate and Select Repair Options For Corrosion
2.4.1 After carefully reviewing the corrosion footprint or characteristics, clean the area
suitably to aid in the evaluation of the corrosion. When cleaning pipe (i.e. sand
blasting or power brushing) for preparation of evaluating, repairing, or coating
pipeline defects exercise extreme care as actual depth of defect may be greater
than reported or predicted. To ensure safe work practices lightly clean pipe until it
is evident that sufficient remaining wall exist to allow thorough cleaning of the
defect.

<<<PAGE 1138>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 3 of 16
2.5 2.6 2.7 2.4.2 If determined necessary, measure the length (in the longitudinal direction) and
determine the depth of the deepest pitting within a corroded area or a segment of
that area. The corrosion analysis criterion for RSTRENG or KAPA requires
division of the pitted area into segments of consistent predetermined lengths and
measurement of the maximum depths within each segment. Refer to RSTRENG
Analysis of Corrosion Procedure for details.
2.4.3 Refer to Paragraph 2.16 of this procedure for corrosion repair methods and
options.
2.4.4 Notify Asset Integrity for assistance with repair options when internal corrosion is
found or suspected.
Evaluate and Select Repair Options for Pipe Body Gouges and/or Mill Defects
2.5.1 Measure the defect circumferential width, length and depth at the deepest point
and several other points along its length. Measure the angle, when applicable, of
the defect relative to the run of the pipeline.
2.5.2 Refer to Table 1 of this procedure for gouges, pipe body and/or mill defects
repair methods and options.
2.5.3 If the repair is made by removing the defect by means of sanding/grinding, upon
completion, the area shall be nondestructively inspected to ensure that a stress
riser, stress concentration, crack or other injurious defect does not exist prior
recoating the area.
Evaluate and Select Repair Options for Dents
2.6.1 Measure the dent area (the length, circumference and depth at the deepest
point). Examine the bottom of the dent for scratches, gouges, grooves, metal loss
or heavily work-hardened material. Measure scratch, gouge, groove or metal
loss, if present, length and depth at the deepest point along its length.
2.6.2 (Reference Section, when required for use with Table 1) Any dent that exceeds
2% or 0.250” in NPS < 12”, with or without visible metal loss, shall be repaired
with a Type B sleeve. Dents 2% or less in NPS <12” that are proven by
nondestructive inspection that a stress riser, stress concentration, crack or other
injurious defect does not exist within the dent may be recoated.
2.6.3 Refer to Paragraph 2.16 of this procedure for dent repair methods and options.
Evaluate and Select Repair Options for Arc Burns
NOTE: If the arc burn is on a new line under construction, the arc burn shall be
removed as a cylinder, per the Onshore Construction Specifications.
2.8 2.7.1 2.7.2 Examine arc burns for cracking and depth.
Refer to Specification 101: Maintenance Welding (Excluding Ethylene Pipelines)
Paragraph 7.0 and Paragraph 2.16 of this procedure for arc burn repair methods
and options.
Evaluate and Select Repair Options for Weld Defects
2.8.1 Examine weld defects visually in accordance with Specification 100, Construction
and Fabrication of Pipelines and Related Piping Systems and Specification 101,
Maintenance Welding (Excluding Ethylene Pipelines). Evaluate welds that have
been X-rayed in accordance with latest approved API specification.

<<<PAGE 1139>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 4 of 16
2.9 2.10 2.11 2.12 2.8.2 Repair all in-service joint welds in accordance with Specification 101 –
Maintenance Welding (Excluding Ethylene Pipelines). This will usually require
the use of a small Type B repair sleeve commonly called a “wedding band”.
2.8.3 The only repair allowed on a long-seam weld is grinding or sanding to remove
surface defects that do not exceed 12.5% (reference 2.5.3) of the parent metal
wall thickness. Repair all other weld defects by installing a full encirclement Type
B repair sleeve or cutting out a cylinder of pipe and replacing it with new pipe.
Evaluate and Select Repair Options for Lamination defects
2.9.1 Examine pipe for Lamination by non destructive testing of the surface in the area
of concern.
2.9.2 Document the length, orientation, proximity to seam and girth weld if relevant,
and note additional interactive features (metal loss, cracks, dents, etc.), if
applicable note sloping, bulging, surface breaking, and blistering.
2.9.3 Repairs will be made in accordance with section 2.15.
2.9.4 Inspect the full circumference of the pipeline where the sleeve ends are to be
welded to the pipeline using an ultrasonic thickness instrument and/or a magnetic
particle inspection technique. Ensure there are no surface cracks, laminations or
thin wall that could affect the integrity of the defect, weld, or sleeve.
Evaluate and Select Repair Options for Stress Corrosion Cracking (SCC)
2.10.1 Examine pipe for Stress Corrosion Cracking (SCC) by non destructive testing
and or magnetic particle inspection of the surface in the area of concern.
Document the findings with photographs when possible or draw a sketch
showing the area affected by cracking. Document the length, density, spacing
and general location of the cracks relative to other surface conditions such as
longitudinal and joint welds.
2.10.2 Notify Asset Integrity for assistance with repair options when SCC is found or
suspected.
2.10.3 If SCC is discovered on Assets covered by the mitigation plan, refer to the ORA
process manual decision tree prior to evaluating and repairing.
2.10.4 Document whether or Not SCC was discovered on Pipeline Maintenance Report.
Evaluate and Select Repair Options for Selective Seam Corrosion (SSC)
2.11.1 Examine pipe for Selective Seam Corrosion (SSC) by evaluating the longitudinal
seam weld for localized corrosion located along the bond line of low frequency
electric resistance welding (LR-ERW) and Electric Flash Welding (EFW) piping,
that leads to the development of a wedge shaped groove that is often filled with
corrosion products. Document the findings with photographs when possible or
draw a sketch showing the area affected by selective seam corrosion.
2.11.2 Notify Asset Integrity for assistance with repair options when SSC is found or
suspected.
2.11.3 Document whether or Not SSC was discovered on the Pipeline Maintenance
Report.
Evaluate and Select Repair Options for Hard Spots
2.12.1 Measure hard spot area (the length and circumference) and map the hardness
using calibrated portable testing equipment.

<<<PAGE 1140>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 5 of 16
2.13 2.14 2.15 2.12.2 Measure the hardness and make a sketch showing the hardness distribution.
Use the following criteria when evaluating hard spots: Repair all hard spots when
the maximum hardness exceeds Rockwell C 35. Refer to Paragraph 2.16 of this
procedure for hard spot repair methods and options.
Evaluate and Select Repair Options for Buckling/Ripples/Wrinkles
2.13.1 Notify Asset Integrity for assistance with repair criteria and repair methods and
options.
2.13.2 Refer to Paragraph 2.13 of this procedure for buckling repair methods and
options.
Evaluate and Select Repair Options for Long Seam and Pipe Body Cracks
2.14.1 Examine pipe for cracking by non-destructive testing and magnetic particle
inspection of the surface in the area of concern. Document the findings with
photographs when possible or draw a sketch showing the area affected by
cracking. Document the length, density, spacing and general location of the
cracks relative to other surface conditions such as longitudinal and joint welds.
2.14.2 Refer to Table 1 of this procedure for crack in pipe body or weld seam for repair
methods and options.
Repair Methods and Options for Features or Defects
2.15.1 Refer to the chart below for evaluating repair options. Under special
circumstances, the Manager of Asset Integrity can approve deviations from the
approved/preferred repair methods listed in the following chart.
Table 1
Defect Type
Re-Coat Grind
/Sand
Repair Method
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
HCA Immediate Condition
Metal loss >80% (external)
Assets Covered by Mitigation Plan >70% N N N X T N O
Metal loss >80% (internal)
Assets Covered by Mitigation Plan >70%
N N N O T N X
PBURST < PDPP at location of anomaly
(external)
N N O X T O O
PBURST < PDPP at location of anomaly
(internal)
N N N X T N O
Dents above 4:00 and 8:00 with any
indicated metal loss, cracking, or stress
riser
N N N X T N O

<<<PAGE 1141>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 6 of 16
Repair Method
Defect Type
Re-Coat Grind
/Sand
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
(See Paragraph 2.6.2)
Dents above 4:00 and 8:00 with a depth
>6% of nominal pipe diameter
(See Paragraph 2.6.2)
N N N X T O O
HCA 60-Day Condition
Dents above 4:00 and 8:00 with a
depth>3% of nominal pipe diameter
(>0.250” in depth for a pipeline diameter
<NPS 12)
(See Paragraph 2.6.2)
N N O X T O O
Dents below 4:00 and 8:00 with any
indicated metal loss, cracking, or stress
riser
(See Paragraph 2.6.2)
N N N X T N O
HCA 180-Day Condition
Dents >2% of nominal pipe diameter
(>0.250” in depth for a pipeline diameter
<NPS 12) that affects pipe curvature at a
girth weld or longitudinal seam weld
(See Paragraph 2.6.2)
N N N X T N O
Dents above 4:00 and 8:00 with a depth
>2% of pipeline diameter (>0.250” in depth
for a pipeline diameter <NPS 12)
(See Paragraph 2.6.2)
N N O X T O O
Dents below 4:00 and 8:00 with a depth
>6% of pipeline diameter
(See Paragraph 2.6.2)
N N N X T O O
PSAFE<PDPP at location of anomaly
(external) N N O X T O O

<<<PAGE 1142>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 7 of 16
Repair Method
Defect Type
Re-Coat Grind
/Sand
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
PSAFE<PDPP at location of anomaly (internal) N N O X T N O
Crack in pipe body or weld seam N N N X T N O
Corrosion of or along a longitudinal seam
weld (Selective Seam Corrosion) N N N X T N O
Gouges or grooves >12.5% nominal wall
thickness N N N X T N O
Other Conditions
N N N X T N O
Leaking defect
Metal loss <12.5% nominal wall thickness X N N N N N N
Non-Injurious Planar Laminations X N O O T N O
Sloping Laminations N N N X T N O
Bulging Laminations N N N X T N O
Surface Breaking Laminations N N N X T N O
Hydrogen Blisters N N N X T N O
Laminations interacting with Deformations N N N X T N O
Arc burn N X N O N N O
Hard spot N N O X N N N
Gouges or grooves <12.5% nominal wall
thickness X X Buckling
N O Repair by cutout, pumpkin, Type B sleeve, or call Asset
Integrity for assistance
N N N
SCC suspected Call Asset Integrity for assistance
Leaking mechanical (Dresser) coupling Repair by tightening, using housing (pumpkin), or cutout
Mechanical leaks (valves and fittings) Repair in accordance with manufacturer’s guidelines or cutout

<<<PAGE 1143>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 8 of 16
Repair Method
Defect Type
Re-Coat Grind
/Sand
Type
“A”
Type
“B”
Bolt
On
Composite Cut
Out
and replace
2.16 2.15.2 This table outlines the approved/preferred method (X), optional (O), and
temporary onshore or permanent offshore (T) methods of repairing imperfections
or defects. The methods that are not permitted (N) are also indicated. The
optional methods listed do not represent all optional methods but identify
normally accepted options. A temporary repair may be made using any method
deemed suitable using sound engineering judgment. For detailed information on
repair methods, refer to Paragraph 2.17 of this procedure.
General Notes on Repair Methods
2.16.1 Defects repaired by grinding and/or sanding, installing a type “A” sleeve, type “B”
sleeve, composite reinforced sleeve or replacing the affected pipe as a cylinder
are all permanent repairs. Bolt-on or mechanical repair clamps used onshore are
considered temporary repairs therefore; replace or upgrade them with a
permanent repair as soon as feasible or with approval of the Manager, Asset
Integrity, a properly welded mechanical or bolt-on clamp is considered a
permanent repair for onshore applications.
2.16.2 When practical, repair defects by sleeving. There are two normally used
methods of sleeving non-leaking defects: type “A” and type “B” sleeve. Base the
decision to use one type over the other on the specific field circumstances and
Table 1
2.16.3 2.16.4 2.16.5 2.16.6 Type “A” full encirclement welded steel sleeve can be used to repair defects.
This sleeve cannot be used on leaking defects or to provide longitudinal
reinforcement to the pipeline. Refer to Paragraph 2.17.2 for detailed information
about installing type “A” sleeves.
Repair leaking defects by sleeving with a type “B” sleeve when practical. Type
“B” sleeves require welding on the pressurized pipe and should not be used to
repair other defects except under special circumstances. Refer to Paragraph
2.17.3 for detailed information about installing type “B” sleeves.
Repair of leaking defects caused by isolated corrosion may be made by installing
a bolt-on leak clamp (On-Shore Temporary) or a type “B” sleeve.
Use composite reinforcement sleeves to repair defects that have been ground
out, were caused by corrosion or dents on low stress pipelines without scratches.
CAUTION: Do not use composite sleeves to repair leaking defects or cracking.
Refer to paragraph 2.17.4 for details.
2.16.7 2.16.8 Repair submerged pipelines in navigable waters containing leaking defects by
mechanically applying a full encirclement sleeve or by installing a new section of
pre-tested pipe.
Repair any defect by removing the defective component (valve, fitting, etc.) or a

<<<PAGE 1144>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 9 of 16
cylinder of pipe containing the defect and installing a new component or cylinder
of pipe.
2.16.9 Patches are not an approved repair method.
2.17 Repair Procedures
2.17.1 Repair defect by grinding and/or sanding, as follows
CAUTION: Prior to performing any grinding or sanding on a live line, evaluate
the defect to be repaired. If it is estimated that the defect is potentially greater
than 10% of the nominal wall thickness, do not perform any grinding or sanding
operations and immediately refer Table 1 to determine the appropriate repair
method, such as installing a sleeve.
2.17.2 2.17.1.1 Remove the defect by grinding and/or sanding. After grinding or
sanding, if the remaining wall thickness is less than 88% of nominal,
reevaluate the integrity of the pipeline and grind area using
RSTRENG (Refer to RSTRENG Analysis of Corrosion) or KAPA and
install a reinforcing sleeve if necessary. The transition from the area
where the defect was removed to the surrounding undisturbed
material shall be smooth.
2.17.1.2 2.17.1.3 Nondestructively inspect all areas where defects have been removed
by grinding, using magnetic particle or dye penetrant inspection
method to ensure the entire defect has been removed. During NDT,
pay particular attention to any indications of cracking.
If the remaining wall thickness passes RSTRENG calculations, the
area does not require sleeving and may be properly cleaned and
recoated.
2.17.1.4 If the remaining wall thickness is less than required by RSTRENG
calculation, perform a repair.
2.17.1.5 The area does not require blend grinding or sanding when the defect
requires type “A” or type “B” sleeving.
Repair Defect Using a Type “A” Sleeve (Non-pressure Containing), as Follows
2.17.2.1 Prepare the pipeline to install the type “A” sleeve by removing all of
the coating and thoroughly power brush or blast cleans the pipe
surface in the area the sleeve will cover.
2.17.2.2 2.17.2.3 2.17.2.4 2.17.2.5 Fabricate or obtain a sleeve with the same or greater overall strength
(wall thickness x yield strength) as the pipeline being repaired. Refer
to Specification 101—Maintenance Welding (Excluding Ethylene
Pipelines) Attachment A for details.
Use a sleeve that is at least 4 inches in length. Ensure that the
sleeve covers the defect(s) plus a minimum of 2" past the defect(s)
on each end. Refer to Specification 101—Maintenance Welding
(Excluding Ethylene Pipelines) for design details.
Clean the inside and outside surface of the sleeve by thoroughly
power brushing or abrasive blasting.
Apply a hardenable filler material such as an epoxy in dents,
corrosion pits, and/or adjacent to the long seam of the pipe to

<<<PAGE 1145>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 10 of 16
2.17.3 completely fill void areas before installing the sleeve.
2.17.2.6 Apply sleeve with backing strip to pipeline ensuring it is tight. The
effectiveness of the sleeve depends on its snugness around the
pipe.
2.17.2.7 Apply the sleeve to pipeline ensuring a snug fit. Weld per
Specification 101—Maintenance Welding (Excluding Ethylene
Pipelines) and the specified welding procedure.
2.17.2.8 Seal the ends of the steel sleeve with a mastic bar, then a shrink
sleeve and coat the exterior of the sleeve following Coatings—
Selection, Applications And Maintenance.
Repair Defect Using a Type “B” Sleeve (Pressure Containing), as follows:
2.17.3.1 Prepare the pipeline to install the type “B” sleeve by removing all the
coating and thoroughly power brush or blast clean the pipe surface in
the area the sleeve will cover.
2.17.3.2 2.17.3.3 2.17.3.4 2.17.3.5 2.17.3.6 2.17.3.7 2.17.3.8 Fabricate or obtain a sleeve with the same or greater overall strength
(wall thickness x yield strength) as the pipeline being repaired. Refer
to Specification 101—Maintenance Welding Attachment A for
details.
Use a sleeve that is at least four inches in length. Ensure that the
sleeve covers the defect(s) plus a minimum of 2" past the defect on
each end. Type B sleeves may be used for leaking or non-leaking
defects including circumferentially oriented defects. When multiple
sleeves are used, a Type B sleeve should not be terminated within
one-half pipe diameter or 4 inches from a girth weld whichever is
greater. The distance between sleeves should be at least one pipe
diameter. Separated sleeves may be spaced less than one pipe
diameter apart if joined by a welded bridging sleeve or made
continuous by butt-welding them together. When installed at a non-
leaking defect, a Type B sleeve may be installed in a manner that
reduces the hoop stress in the carrier pipe. Methods for
accomplishing this include lowering the pressure before the sleeve is
installed, applying external mechanical force, or preheating the
sleeve to facilitate a “shrink-fit.”
Inspect the full circumference of the pipeline where the sleeve ends
are to be welded to the pipeline using an ultrasonic thickness
instrument and/or a magnetic particle inspection technique. Ensure
there are no surface cracks, laminations or thin wall that could affect
the integrity of the weld or sleeve.
Clean the inside and outside surface of the sleeve by thoroughly
power brushing or abrasive blasting.
Apply a hardenable filler material such as an epoxy in dents,
corrosion pits, and/or adjacent to the long seam of the pipe to
completely fill void areas before installing the sleeve.
Apply the sleeve with backing strip to pipeline ensuring a snug fit.
Weld per Specification 101—Maintenance Welding (Excluding
Ethylene Pipelines) and the specified welding procedure.
Nondestructively test the completed longitudinal groove weld and

<<<PAGE 1146>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 11 of 16
2.17.4 2.17.5 2.17.6 circumferential fillet welds in compliance with Specification 101—
Maintenance Welding (Excluding Ethylene Pipelines).
2.17.3.9 Coat the exterior of the sleeve with primer and RD-6 Tapecoat
following Coatings—Selection, Applications and Maintenance.
Repair Defect Using an Approved Composite Reinforced Sleeve
2.17.4.1 Do not use a composite sleeve to repair leaks, cracks, or weld
defects. Refer to Table 1 for specifics.
2.17.4.2 2.17.4.3 A qualified person(s) must install composite sleeves.
Prepare the pipeline to install the composite reinforced sleeve(s) in
accordance with the manufacturer's specifications. Usually abrasive
blasting is required.
2.17.4.4 Install the composite sleeve per manufacturer’s specific
requirements and specifications.
2.17.4.5 Install metallic (Caron Steel) banding at one-foot intervals on the
sleeve for the purpose of ILI tool identification.
2.17.4.6 Coat the exterior of the sleeve with primer and RD-6 Tapecoat
following Coatings—Selection, Applications and Maintenance. As an
alternative, a “heat shrink sleeve” that fully encompasses the length
and circumference of the Composite sleeve may also be used, if the
ends of the composite sleeve are appropriately filled in order to
prevent any air gaps. The heat shrink sleeve must extend past the
ends of the Composite sleeve by at least 4 inches for proper
encapsulation/coating of the Composite sleeve and cover adjacent
bare steel areas, which may result in the use of multiple heat shrink
sleeves.
Repair Defects Using a Bolt-On Mechanical Clamp
2.17.5.1 Install properly designed full encirclement mechanical clamp by
covering the defect.
2.17.5.2 Follow all manufacturers’ instructions when installing mechanical
clamp.
2.17.5.3 Replace mechanical clamps with a permanent repair as soon as
feasible. Properly welded mechanical clamps are considered
permanent repairs for onshore applications, upon approval by the
Manager of Asset Integrity.
2.17.5.4 Weld + Ends or similar compression type fittings shall not be used to
join pipe together without a written job specific installation procedure
including reviewing and following manufactures procedures to
ensure correct installation and other necessary safety measures for
safe and reliable operation of the pipeline system. Call Manager of
Asset Integrity for further guidance, if necessary.
2.17.5.5 Coat the exterior of the sleeve with primer and RD-6 Tapecoat
following Coatings—Selection, Applications and Maintenance.
Repair Defects by Cutting Out a Cylinder Of Pipe and Replacing it with New Pipe
2.17.6.1 2.17.6.2 Prior to cutting or welding check for LEL’s with Haz Gas detector
Remove pipe or fitting containing the defect as a cylinder.

<<<PAGE 1147>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 12 of 16
2.17.6.3 2.17.6.4 2.17.6.5 2.17.6.6 Ensure any removed section has had adequate time for ventilation
prior to cutting and transporting.
Whenever possible, ensure that the replacement pipe has a length of
not less than one-half the pipe diameter or not less than 3 inches
whichever is greater.
The replacement pipe, fitting, or valve shall have a greater than or
equal design pressure as the existing pipe or fitting and shall be pre-
tested.
Pipe ends should be checked for magnetism prior to welding. If
welding quality becomes an issue, steps to reduce or temporarily
eliminate the Magnetic field on the pipe ends should be taken.
NOTE: Prior to installing pretested pipe, ensure the appropriate
records (i.e., MTRs, Hydrostatic Test Records) have been located,
thoroughly reviewed, and verified accurate.
2.17.6.7 Ensure LEL’s have been removed from work area prior to installing
new pipe
2.17.6.8 Install the replacement material in accordance with Specification
101, Maintenance Welding (Excluding Ethylene Pipelines).
2.17.6.9 Coat the exterior of the new and adjacent pipe (as needed) with
primer and RD-6 Tapecoat following Coatings—Selection,
Applications and Maintenance.
2.17.7 Repair defects by Recoat
2.17.7.1 Prepare the pipeline to install coating by removing all of the existing
coating and thoroughly power brush or blast clean the pipe surface in
the area of the recoat.
2.18 2.17.7.2 Coat the exterior of the sleeve with primer and RD-6 Tapecoat
following Coatings—Selection, Applications and Maintenance.
2.17.7.3 After application of the RD-6 coating, install metallic banding (Carbon
Steel) four inches from each end of the recoat area and coat the
metallic bands with RD-6 coating.
Document all repairs on the Pipeline Maintenance Report and ensure a copy is sent to
the Records Coordinator in Tulsa.
3.0 DEFINITIONS
3.1 3.2 Arc Burn: Localized points of surface melting caused by arcing between electrode or
ground and pipe surface.
Bolt-On Fitting: Any onshore or offshore attachment to a pipeline that is attached via
bolts.
3.3 Composite Reinforcement Sleeve: A nonmetallic sleeve used to repair some nonleaking
3.4 pipeline defects.
Dent: An area of the pipe where the local curvature is no longer part of a circular arc
having the same radius as the pipe. The local indentation shall be considered a dent if
the measured distance between the lowest point of the indentation and a prolongation of
the original contour of the pipe exceeds the value equivalent to 2% of the pipe’s diameter.

<<<PAGE 1148>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 13 of 16
3.5 Hard Spot: Localized spot where the hardness of the material is greater than
surrounding material.
3.6 MIC: Microbiologically induced corrosion.
3.7 RSTRENG: A modified corrosion assessment criterion to predict a minimum failure
pressure based on detailed corrosion depth and length measurements.
3.8 3.9 Stress Corrosion Cracking (SCC): Cracking which results from stress induced corrosion.
Selective Seam Corrosion (SSC): Localized corrosion located along the
bond line of low-frequency electric resistance welding (LR-ERW) and electric
flash welding (EFW) piping, that leads to the development of a wedge
shaped groove that is often filled with corrosion products.
3.10 Type A Sleeve: A band of steel that encircles the pipeline and is not welded to the
pipeline.
3.11 Type B Sleeve: A band of steel that encircles the pipeline and is welded to a pipeline at
the ends forming a pressure vessel and is normally used for a leaking defect but may be
used for non-leaking defects under special circumstances.
3.12 Wedding Band: A short (Usually 6 to 12 inches in length) Type B Sleeve that
encompasses a joint weld.
3.13 Weld Defect: A weld imperfection located in a seam or girth weld.

<<<PAGE 1149>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE 7.01–ADM–001
Asset Integrity 01/01/12 Revision: 9 Page 14 of 16
System Integrity Plan Change Log
Date Change
Location
Change
By
2.2 Clyde Clausen Mike Pearson 2.12 Clyde Clausen Mike Pearson 2.3 Clyde Clausen Mike Pearson 07/23/02
Various Clyde Clausen Mike Pearson Various Clyde Clausen Mike Pearson 2.6.3 Clyde Clausen Mike Pearson 08/08/02 2.4.3 & 2.13.1 Clyde Clausen Mike Pearson 11/21/03 All Clyde Clausen Mike Pearson 12/22/03 1.0 Clyde Clausen Mike Pearson 12/22/03 2.1.2 Clyde Clausen Mike Pearson 12/22/03 2.1.3 Clyde Clausen Mike Pearson 12/22/03 2.1.4 Clyde Clausen Mike Pearson 12/22/03 2.1.5 Clyde Clausen Mike Pearson 12/22/03 2.2.3 Clyde Clausen Mike Pearson 12/22/03 2.6 Clyde Clausen Mike Pearson 12/22/03 2.12 Clyde Clausen Mike Pearson 12/22/03 2.14.7 Clyde Clausen Mike Pearson 12/22/03 2.15.4.5 Clyde Clausen Mike Pearson 12/22/03 2.15.6.4 Clyde Clausen Mike Pearson 11/21/04 All Clyde Clausen Mike Pearson 9/9/04 2.7 Clyde Clausen Mike Pearson 9/9/04 2.14.3.2 Clyde Clausen Mike Pearson 9/9/04 2.14.3.3 Clyde Clausen Mike Pearson 9/9/04 2.14.6.2 Clyde Clausen Mike Pearson 9/9/04 2.14.6.3 Clyde Clausen Mike Pearson 9/9/04 2.14.6.4 Clyde Clausen Mike Pearson Brief Description of Change
Detailed how to perform a visual assessment.
Added a repair method to the table for
Natural Gas.
Provided details on reference sections.
Replaced Paragraph 6.12 reference with 2.13.
Paralleled repair language with the Welding manual
to alleviate conflicts and inconsistencies.
Added section for dent repair clarification.
Added repair method deviation approval process.
Annual Review
Deleted Purpose of this procedure is to establish,
inserted analysis and repair of
Deleted Pump piping and Tanks
Deleted DOT Part 195 governs the repairs Williams
utilizes for certain pipeline repairs. These regulatory
parts and subparts may be referenced within this
document.
Added OQ qualification paragraph
Added live line welding paragraph
Deleted paragraph, and re‐worded
Deleted Caution Note
Become 2.11. Rewrote repair options for
buckling/ripples
Become 2.13.7. Deleted offshore pipeline
Become 2.14.4.5. Added (Carbon Steel)
Become 2.14.6.4. Modified Note to read ensure the
appropriate records (i.e. MTRs, Hydrostatic Test
Records) have been located, thoroughly reviewed,
and verified accurate.
Annual Review
Modified Paragraph within Note
Deleted Ethylene Pipelines
Modified Paragraph for changes due to new
regulated requirements
Modified Paragraph for changes due to new
regulated requirements
Modified Paragraph
Added new Paragraph

<<<PAGE 1150>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE Asset Integrity 01/01/12 11/20/05 All Clyde Clausen Mike Pearson 01/01/06 4.4 Clyde Clausen Mike Pearson 01/01/06 2.6.2 Clyde Clausen Mike Pearson 01/01/06 2.12.1 Clyde Clausen Mike Pearson 01/01/06 References Mike Pearson 1/26/06 2.14.6.3 Clyde Clausen Mike Pearson 1/26/06 2.14.6.5 Clyde Clausen Mike Pearson 2/15/06 2.1.5 Clyde Clausen Mike Pearson 11/16/06 All Clyde Clausen Mike Pearson 11/16/06 2.3.3.7 Clyde Clausen Mike Pearson 11/16/06 2.9.3 Clyde Clausen Mike Pearson 11/16/06 2.10 Clyde Clausen Mike Pearson 11/16/06 4.9 Clyde Clausen Mike Pearson 1/10/07 2.2.4 Clyde Clausen Mike Pearson 1/10/07 2.4.1 Clyde Clausen Mike Pearson 1/10/07 2.2.3 Clyde Clausen Mike Pearson 5/8/07 2.2.4 Clyde Clausen Mike Pearson 5/8/07 2.1.1 Clyde Clausen Mike Pearson 6/28/07 2.2.1 Clyde Clausen Mike Pearson 6/28/07 2.2.2 Clyde Clausen Mike Pearson 6/28/07 2.5.3 Clyde Clausen Mike Pearson 6/28/07 2.8.3 Clyde Clausen Mike Pearson 11/16/07 All Clyde Clausen Mike Pearson 4/01/08 2.2.1 Dennis Vasicek Clyde Clausen 4/01/08 2.2.2 Dennis Vasicek Clyde Clausen 4/01/08 2.2.3 Dennis Vasicek Clyde Clausen 7.01–ADM–001
Revision: 9 Page 15 of 16
Annual Review
Added definition
Minor modifications
Incorporated HCA Repair Criteria
removed
Minor Modification to Paragraph‐ (Added Valve)
Minor Modification to Paragraph‐ (Change
Specification 100 to Specification 101)
Removed Pressure reduction requirements from
Paragraph.
Annual Review
Added 2.3.3.7
Added Paragraph
Added 2.10
Added Definition
Added precaution for cleaning pipe.
Added precaution for cleaning pipe to existing
paragraph.
Added Paragraph to comply with 195.422.
Added Paragraph to comply with 195.422.
Removed reference to MPC
Added Paragraph
Added Paragraph for pressure reductions for defects
that can’t be repaired in 8 hours.
Added Paragraph for non‐destructive testing repairs
that have been removed by grinding/sanding.
Added reference to paragraph
Conducted Annual Review
Added: All exposed bell and spigot girth welds shall
be reinforced by means of sleeving
Added: If needed (when pipe is not resting on the
ground) the pipe should be adequately supported
prior to backfilling. Consideration should be given to
using dirt plugs or sandbags at spacing intervals not
to exceed 20 feet particularly in areas where
additional weight has been applied by installation of
sleeving
Added: All exposed girth welds (including bell and
spigot joints) shall be supported (supports to be
placed on each side of the girth weld) via sandbags
or equivalent settlement resistant supports prior to
backfilling.

<<<PAGE 1151>>>

Magellan Midstream Partners, L.P.
PIPELINE DEFECT EVALUATION AND REPAIR PROCEDURE Asset Integrity 01/01/12 11/14/08 All Dennis Vasicek Clyde Clausen 12/18/08 2.1.3 Dennis Vasicek Clyde Clausen 12/18/08 2.2.5 Dennis Vasicek Clyde Clausen 12/18/08 2.3.1 Dennis Vasicek Clyde Clausen 12/18/08 2.3.4.10 Dennis Vasicek Clyde Clausen 12/18/08 2.13 Dennis Vasicek Clyde Clausen 12/18/08 2.16.3.8 Dennis Vasicek Clyde Clausen 8/21/09 All Clyde Clausen Doug Chabino 8/21/09 2.2.3 Clyde Clausen Doug Chabino 8/21/09 2.2.6 Clyde Clausen Doug Chabino 11/30/09 All Clyde Clausen Doug Chabino 11/30/09 2.16.5.4 Clyde Clausen Doug Chabino 11/30/09 2.16.6.1 Clyde Clausen Doug Chabino 11/30/09 2.16.6.3 Clyde Clausen Doug Chabino 11/30/09 2.16.6.7 Clyde Clausen Doug Chabino 9/3/10 2.1.2, 2.4.2,
2.16.1.1
Clyde Clausen Doug Chabino 9/3/10 2.9.3 Clyde Clausen Doug Chabino 9/3/10 2.14.1 Clyde Clausen Doug Chabino 9/3/10 All Clyde Clausen Doug Chabino 9/1/11 All Clyde Clausen Doug Chabino 9/1/11 2.14.1 Clyde Clausen Doug Chabino 12/31/11 All 6/12/12 2.14 Table Clyde Clausen Doug Chabino 7.01–ADM–001
Revision: 9 Page 16 of 16
Conducted Annual Review
Minor modification (installation of repairs, i.e.
composite/clamps) to paragraph
Minor Modification to paragraph
Added paragraph to photograph repair site prior to
removing coating
Added Section for Cracks
Added Section for Cracks
Minor Modifications to paragraph
Conducted Annual Review, See modifications below
Added not to exceed 5’ to paragraph
Added requirement to NDE pipeline defects that are
not repaired by means of sleeving or pipe
replacement
Removed reference to contact Pipeline Integrity and
added Asset Integrity
Added Paragraph
Added Paragraph
Added Paragraph
Added Paragraph
Added utilization of KAPA for conducting pressure
assessments
Added new paragraph to refer to the ORA process
manual decision tree if SCC is discovered on assets
covered by the mitigation plan
Added Immediate repair criteria for Assets covered
by the mitigation plan to repair table
Conducted Annual Review
Conducted Annual Review
Added Lamination Repair Options to Table
2012 Annual Review complete
Modified Lamination Repair Table

<<<PAGE 1152>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 1 of 4
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity by establishing consistent processes
for integrity testing.
2.0 DESCRIPTION
2.1 The Company utilizes pressure testing, in‐line inspection (ILI), or a combination thereof, to assess
and validate the physical integrity of its pipeline system. In addition to standardized pipeline
construction and maintenance practices, the Company adheres to a comprehensive Integrity
Management Program that incorporates the use of appropriate integrity testing technologies
and rehabilitation practices in order to assist in identifying, understanding and controlling
pipeline risk and integrity threats.
2.2 A priority rating system based on relative risk is established to select pipeline segments for
integrity testing schedules. The frequency of reassessments will be determined by the processes
established within the Integrity Management Plan.
3.0 STANDARDS
3.1 The Project Manager shall:
3.1.1 Consult with the Pipeline or Facility Risk Engineer, as appropriate for type of asset, to
ensure review of applicable asset integrity factors is completed prior to testing.
3.1.2 Coordinate the execution of pressure testing projects in accordance with the Pressure
Testing Procedure.
3.1.3 Complete the appropriate Hydrostatic Test Documentation (Hydrostatic Test
Documentation for Liquids) and remit with the required attachments to the Records
3.1.4 Coordinator within thirty days of the pressure test.
Coordinate the execution of ILI projects in accordance with the In‐Line Inspection
Procedure.
3.2 The Records Coordinator shall:
3.3 3.4 3.2.1 Review pressure test documentation for thoroughness and adequacy, and retain in
Asset Integrity file repository for useful life of the facillity.
3.2.2 Notify the Pipeline Surge Engineer following receipt of pressure test records.
3.2.3 Input the new pressure test data and the new calculated Maximum Operating Pressure
(MOP) information into the Hydrostatic Test Database within 60 days following receipt
of the pressure test records.
The Manager of Asset Integrity Engineering shall:
3.3.1 Coordinate changes to system pressure settings with Operations Control and/or
Operations Manager as applicable.
The Pipeline Integrity Supervisor shall:
3.4.1 Determine the effect(s) on the MOP of the corresponding asset(s) following notice of
receipt of pressure test documentation.
3.4.2 Coordinate the execution and documentation of integrity testing and rehabilitation

<<<PAGE 1153>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 2 of 4
3.4.3 3.4.4 plans of existing assets.
Notify the Manager of Asset Integrity Engineering of any required adjustments to
system operating pressures due to integrity testing results.
Maintain and annually review the In‐Line Inspection Procedure and Pressure Testing
Procedure for use on Company operated assets.
3.5 The Pipeline Integrity Engineer shall:
3.5.1 Immediately evaluate reports from the ILI vendor and generate a Dig List in accordance
with In‐Line Inspection Procedure.
3.5.2 Notify the Pipeline Integrity Coordinator that the Dig List has been developed in order to
initiate project execution of feature investigations and rehabilitation, as required.

<<<PAGE 1154>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 3 of 4
System Integrity Plan Change Log
Date Change
Location
Change By Approved By Brief Description of Change
10/16/03 All Clyde Clausen Michael Pearson 10/23/03 2.1 & 2.2 Clyde Clausen Michael Pearson 10/23/03 3.2 Clyde Clausen Michael Pearson 10/23/03 3.4.2 Clyde Clausen Michael Pearson 10/23/03 3.5 Clyde Clausen Michael Pearson 10/23/03 3.7.2 Clyde Clausen Michael Pearson 9/29/04 All Mike Pearson Michael Pearson 9/29/04 3.13 Clyde Clausen Michael Pearson 9/29/04 3.3.1 Clyde Clausen Michael Pearson 9/29/04 3.4.3 Clyde Clausen Michael Pearson 10/16/05 All Clyde Clausen Michael Pearson 10/16/06 All Clyde Clausen Michael Pearson 10/16/06 Entire
Document
Clyde Clausen Michael Pearson 10/16/06 3.1.2 Clyde Clausen Michael Pearson 10/16/06 3.1.4 Clyde Clausen Michael Pearson 10/16/06 3.2.1 Clyde Clausen Michael Pearson 10/16/06 3.2.2 Clyde Clausen Michael Pearson 10/16/06 3.3.1 Clyde Clausen Michael Pearson 10/16/06 3.3.2 Clyde Clausen Michael Pearson 10/16/06
Clyde Clausen Michael Pearson 3.3.2
10/16/06 3.4.4 Clyde Clausen Michael Pearson 10/16/06
Clyde Clausen Michael Pearson 3.5
10/16/06 3.6 Clyde Clausen Michael Pearson 09/11/07 All Clyde Clausen Michael Pearson 9/11/07 3.2.2
Michael Pearson Conducted 2003 Annual Review, (See Change Log)
Minor modifications to Paragraph
Inserted responsibilities of Pipeline Integrity
Coordinator.
Added new responsibility to Pipeline Integrity or
Facility Supervisor.
Added Operations Control Manager responsibilities
Added new responsibility to Pipeline Integrity
Engineer.
Conducted 2004 Annual Review, (See Change Log)
Changed 2 weeks to thirty days
Added responsibility to Asset Integrity Manager
Added new responsibility to Pipeline Integrity or
Facility Supervisor.
Conducted 2005 Annual Review‐ (No Changes)
Conducted 2006 Annual Review‐ (See Change Log)
Revised job titles to reflect recent organizational
changes.
Minor Modification to Paragraph
Minor Modification to Paragraph
Minor Modification to Paragraph
Minor Modification to Paragraph
Deleted Paragraph
Moves up and becomes 3.3.1
Moved responsibility under Pipeline Integrity/ Risk
Engineering Supervisor: Determine the effect(s) on
the MOP of the corresponding asset(s) following
notice of receipt of pressure test documentation
Minor Modification to Paragraph
Deleted Operations Control Manager
Requirements as it is covered within 7.07
Operating Pressures.
Deleted Asset Integrity Analyst Responsibilities
Conducted 2007 Annual ,(See Change Log)
Deleted Risk Engineer and Inserted Pipeline Surge
Engineer. Deleted two weeks.

<<<PAGE 1155>>>

Magellan Midstream Partners, L.P.
INTEGRITY TESTING AND REHABILITATION SIP–ADM–7.03
Asset Integrity 01/01/10 Revision: 6 Page 4 of 4
9/11/07 3.3 Clyde Clausen Michael Pearson 9/11/07 3.4 Clyde Clausen Michael Pearson 9/11.07 3.4.3 Clyde Clausen Michael Pearson 1/1/09 8/21/09 All Clyde Clausen Doug Chabino 8/21/09 3.1.3 Clyde Clausen Doug Chabino 8/21/09 Section 4 Clyde Clausen Doug Chabino 01/01/11 Deleted Director, Inserted Manager Asset Integrity
Engineering
Deleted Risk Engineering and made sole
responsibility of Pipeline Integrity Supervisor
Deleted Director and inserted Manager Asset
Integrity Engineering
2008 annual review complete – no changes
Conducted Annual Reivew
Removed Gas Reference
Removed Gas Link
Reviewed, no changes

<<<PAGE 1156>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 1 of 11
1.0 OBJECTIVE
1.1 The objective of this procedure is to establish the requirements, process, and documentation for
pressure testing.
2.0 SCOPE
2.1 2.2 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on non‐jurisdictional assets as deemed
appropriate.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree. For the period of the Consent Decree,
these systems will follow the applicable process and procedures identified within the Inspection
and Maintenance Manuals (refer to Consent Decree for applicable programs). Exceptions and/or
variations to these processes are identified in the System of Operating Manuals‐ Disclaimer.
3.0 PROCEDURE
3.1 General
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 3.1.7 Pressure tests are planned and conducted in order to meet stated acceptance criteria
and pressure test objectives.
Each new pipeline system and each pipeline system in which pipe has been relocated or
replaced, or that part of a pipeline system that has been relocated or replaced (tie‐ins),
must be pressure tested without leakage.
In‐place pressure testing is not required for repairs if the individual joints of the pipe
have been previously tested to the applicable requirements and documentation in
accordance with the requirements outlined in Section 3.10 Records is available.
Pressure tests must include all pipe and attached fittings, including components.
Pressure testing is not required for a single new component other than pipe that is the
only item being added or replaced if the manufacturer certifies that either:
3.1.4.1 The component was hydrostatically tested at the factory; or
3.1.4.2 The component was manufactured under a quality control system that
ensures each component is at least equal in strength to a prototype that
was hydrostatically tested at the factory.
All hydrostatic test failures shall be removed from the pipeline and consideration shall
be given to submit the failed section for metallurgical review per Analysis of Pipe
Cutouts. Results of the metallurgical review will be integrated into the overall Integrity
Management Plan.
Upon completion of a successful pressure test, prior to relieving test pressure contact
the Pipeline or Facility Integrity Engineer for hydrostatic test acceptance approval.
Upon completion of a successful pressure test of a line segment, in addition to the bi‐
annual requirement, Operations should consider running cleaning pigs within 2 months
after startup.
3.1.8 Test Medium
3.1.8.1 For Liquid Pipelines, water shall be used as the test medium except as

<<<PAGE 1157>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 2 of 11
provided in 49 CFR 195.306.
3.1.9 The Project Manager shall:
3.1.10 3.1.11 3.1.9.1 Ensure the pipeline is properly cleaned, filled, tested, de‐watered; test
water disposed of, and dried. Drawings and Right‐of‐Way and Permit
Stipulations should be referenced for special requirements.
3.1.9.2 Special consideration shall be given to the injection of corrosion inhibitors
to prevent internal corrosion to preserve the line in the event that the
start‐up or introduction of product into the line is delayed after completion
of dewatering and drying of the line. Consult with the Manager of Asset
Integrity and Corrosion Control Specialist to determine necessary
mitigation measures and timing of implementation
3.1.9.3 Complete all required test records including charts, reports, forms, and
calculations. The Contractor testing supervisor and the Company Inspector
shall sign the test chart and the hydrostatic test log upon successful
completion of a hydrostatic test. All test records along with test
equipment calibration records and completed calculations shall be sent to
Asset Integrity Engineering promptly for approval and filing.
3.1.9.4 Consider if anti‐freeze, methanol, glycol, corrosion inhibitors, biocides or
other chemicals are needed. Consult the Supervisor, Asset Integrity for
specifics and notify the Environmental Specialist prior to applying for a
hydrostatic test discharge permit if additives are to be used.
3.1.9.5 Determine the test method, test pressure, and the test duration of
pipelines and complete the proper documentation (Hydrostatic Test Form)
to ensure the desired MAOP or MOP is achieved. The MAOP/MOP
documentation shall be retained for the useful life of the pipeline.
Pipeline taps to vent air are permitted but the pipeline should only be excavated and
exposed to install a tap after alternative methods have been evaluated and ruled out. If
pipeline taps to vent air are required, consult with Manager of Asset Integrity for
approval and to initiate a detailed work plan to include involvement of all key
stakeholders. Prior to excavating the pipeline to install a tap, a detailed work plan shall
be written. The plan shall consider a detailed review of the following, but not limited to;
original construction records, previous ILI logs, leak history, drawings and alignment
sheets, line fill data, and maintenance reports. Land topography must be evaluated and
a determination made whether there is the potential for existing inherent mechanical
stresses in the pipeline. This includes a review of previous work activity or previous
events in the area. If the determination is made that there could be inherent mechanical
stresses in the pipeline due to topography or events mentioned above, then extra
length and width of ditch shall be excavated in the vicinity of the planned tap to allow
the pipe to flex and relieve existing stress. This guidance shall be provided in the
detailed work plan. Taps on in‐service lines shall be piped to an atmospheric tank.
If the pipeline is being tested to satisfy Integrity Management requirements,
consideration should be given to conducting a spike test.
3.2 Responsibilities
3.2.1 Sponsor – Manager of Asset Integrity
3.2.2 Implementation

<<<PAGE 1158>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 3 of 11
3.3 3.2.2.1 The Project Manager is responsible to ensure pipelines are tested to the
proper pressure and for the required duration.
3.2.2.2 The Manager of Asset Integrity is responsible for audits.
Hydrostatic Test Job Plan (prior to any testing activities)
3.3.1 The Project Manager shall:
3.3.1.1 Ensure a Test Job Plan is completed and followed. The Test Job Plan shall
include, but not be limited to, the following information:
3.3.1.1.1 The schedule and sequence of cleaning, filling, testing,
dewatering and drying the test sections, including which
sections will be filled from or dewatered to adjacent sections
3.3.1.1.2 The location of test manifolds, fill‐water sources, de‐water
areas, air compressors, pressure recorders, deadweights and
temperature recorders
3.3.1.1.3 Fill‐meter types and quantities
3.3.1.1.4 Contractor shall provide containment structure material and
design for pumps near streams and wetlands
3.3.1.1.5 Dewater structure material, design, discharge line size and
type, maximum discharge rate.
NOTE: Project Manager shall ensure discharge piping is
designed for the expected discharge pressures and shall
ensure discharge piping is anchored to prevent whipping in
the event of failure.
3.3.1.1.6 3.3.1.1.7 3.3.1.1.8 3.3.1.1.9 3.3.1.1.10 3.3.1.1.11 Air compressor quantity and rating (c.f.m. at psig.)
Quantity, model, range and accuracy for temperature
recorders, pressure recorders, electronic pressure gauges,
deadweight gauges and fill‐volume meters
Types and quantity for each of the following: cleaning pigs, fill
pigs, de‐water pigs and drying pigs
Drying equipment, procedure and specified dew point, if
required
Contractor shall design and provide spill containment
material and equipment at fill site
Method to control speed of fill pig with back‐pressure to
prevent acceleration on downhill sections.
Ensure that necessary permits are obtained to complete the pressure test and identify
who needs to be notified.
3.3.2 3.4 Safety
3.4.1 3.4.2 Pressure test shall be implemented by qualified personnel.
Personnel safety and environmental impact shall be considered during the planning of a

<<<PAGE 1159>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 4 of 11
pressure test project.
3.4.3 Persons not directly engaged in the testing operation shall remain out of the test area
during testing. No work shall be permitted on the pipeline after 50  of test pressure is
achieved.
3.4.4 Personnel, test trailer, pressure recorders and deadweight gauges shall be located a safe
distance from the facility being tested. If the test manifold or facility contains a
longitudinal seam, the test equipment shall be located on the side opposite the seam
when possible.
3.4.5 Pipe, hose and fittings shall be manufactured to proper pressure rating and in good
condition. Hoses and pipes shall be anchored to prevent whipping in the event of
failure.
3.4.6 Prior to pressurization, the pipeline shall be completely backfilled except test‐header
locations, pipeline valves, flanged or screwed connections, or any other locations where
leakage could be expected or pipe that cannot be backfilled such as an existing span.
3.4.7 While separating and isolating piping for a hydrostatic test, consider the use of a solid
blind flange without a tapped hole whenever possible.
3.4.8 Signs shall be installed and placed over the pipeline in critical areas notifying the public
when testing is in progress. Individuals living in close proximity to the pipeline shall be
notified prior to project implementation.
3.5 Special Equipment Requirements
3.5.1 The pipe temperature recorder shall be located in an insulated housing and the capillary
line shall be insulated to the sensing bulb, which shall be taped to the pipeline after
removal of the coating. The sensing bulb shall be installed an appropriate distance from
the test header so as not to be affected by the temperature of the pressure water
injected into the pipeline. For buried/underground pipelines, the line shall be excavated
at a location with typical depth of cover for placement of the temperature sensing bulb.
The pipeline will be backfilled and tamped around the sensing bulb.
3.6 Certification of Test Equipment
3.6.1 Consistent with the calibration requirements in API RP 1110 – Pressure Testing of Liquid
Petroleum Pipelines, electronic pressure gauges or deadweight gauges shall be
calibrated in accordance with NIST standards by an approved third‐party, within the
previous 12 months. Certificates of calibration with instrument serial numbers must be
reviewed prior to starting any testing.
3.6.2 Pressure recorders (continuous recording chart recorders) shall be calibrated
immediately before each use (using the deadweight tester) or calibrated in accordance
with the manufacturer’s recommendations. Certificates of calibration with instrument
serial numbers must be reviewed prior to starting any testing.
3.6.3 An approved third party shall properly calibrate temperature recorders within the
previous 12 months. Certificates of calibration with instrument serial numbers must be
reviewed prior to starting any testing.
3.7 Filling for a Hydrostatic Test
3.7.1 Prior to filling each test section, the facility shall be checked carefully to ensure the
facility is ready—including checking that pipe, hose, flange and fitting connections are

<<<PAGE 1160>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 5 of 11
properly installed and block valves used for filling are in open position. Other valves
that are part of the test but not used for fill connections should be in the half open
position and plugged or blind‐flanged. TOR nipples that are installed with check valve
plugs should have the check valve plugs removed and replaced with solid TOR plugs for
the duration of the test. Upon completion of the test the TOR check valve plugs may be
returned.
3.7.2 Filling shall be continuous from start of filling until test section(s) is/are completely
filled. The Project Manager shall consider means to control the speed of the fill pig with
back‐pressure to prevent acceleration on downhill sections. After test section(s) is/are
filled, connections shall be checked for leaks with air vented as required.
3.8 Hydrostatic Testing
3.8.1 Project Manager shall initiate completion of Hydrostatic Test Documentation (Liquids)
for liquid pipelines or Hydrostatic Test Documentation (Gas) taking into consideration
pressure rating of pipe fittings, flanges, and valves; previous pressure test records; and
appropriate design calculations.
3.8.2 If a pipeline segment is determined to be susceptible to longitudinal seam oriented
failures and hydrostatic testing is the chosen integrity assessment, then a spike test shall
be performed in addition to the normal test in accordance with 49 CFR 195 Subpart E. A
spike test is generally conducted at a pressure of at least 1.39 x MOP for 10–30 minutes
prior to the normal 49 CFR 195 Subpart E test. All pipeline hydrostatic test failures shall
be removed from the pipeline and consideration shall be given to submit the failed
section to a metallurgist for failure analysis and reporting.
3.8.3 The pipeline shall be tested for the duration and at the minimum test pressure
identified in the Hydrostatic Test Documentation (Liquids) or Hydrostatic Test
Documentation (Gas). Pressure tests must be maintained at or above the minimum test
3.8.4 3.8.5 3.8.6 3.8.7 3.8.8 pressure (equal to 125 percent or more of the MOP) for a minimum of four (4)
continuous hours. If the tested pipeline segment cannot be visually inspected during
the pressure test, an additional four (4) hours of testing is required. The test pressure
during the additional four (4) hours may be reduced to a minimum of 110 percent of the
desired MOP.
Valves must be tested in the half‐open position to prevent seal damage.
Below‐grade valves and flanged connections shall be considered for excavation
Adequate time shall be allowed for temperature stabilization prior to starting testing
unless circumstances dictate otherwise.
Prior to start of testing, new charts shall be installed on the pressure and temperature
recorders so that the full test is on the same chart. The Contractor shall record the time,
pipe temperature, ambient temperature, dead‐weight pressure readings and the
location of the dead‐weights (mile posts and engineering stations) on forms at testing
start and as specified in Test Plan. Any volume of water added or drained to maintain
test pressure must be measured accurately and volumes recorded along with time, pipe
and ambient temperatures, if required by Test Plan.
If the test pressure drops below the specified minimum at any time during the test, a
determination shall be made regarding the existence of a leak. If the determination is
made that a leak does not exist, the test section shall be re‐pressurized and the entire
test restarted.

<<<PAGE 1161>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 6 of 11
3.8.8.1 For pressure drops or losses that don’t fall below specified minimum test
pressure requirements, determine if pressure losses correspond with
measured temperature loss using industry accepted calculation method.
3.9 Crossings
3.9.1 Water, railroad, and highway crossing carrier pipe shall be hydrostatically pre‐tested for
a minimum of 2 hours before installation, and again for 8 hours after pulled in place by
boring process, except for in‐service pipelines in place.
3.10 Records
3.10.1 3.10.2 3.10.3 3.10.4 Upon completion of a successful hydrostatic test, the Pipeline or Facility Integrity
Engineer shall conduct a final review of all pertinent records and documentation
associated with the project per 3.10.3 and 3.10.4 of this section.
Complete, signed original records shall be maintained for the useful life of the facility for
each test. Handwritten records must be legible.
Pressure recorder and temperature recorder charts shall provide the following
information:
3.10.3.1 Company name
3.10.3.2 Test Supervisor and pipeline Contractor
3.10.3.3 Project name
3.10.3.4 AFE number
3.10.3.5 Test medium, source and quality
3.10.3.6 Facility tested (pipeline or fabricated assembly name)
3.10.3.7 Pipe outside diameter, wall thickness and grade
3.10.3.8 Beginning and ending milepost and engineering stations
3.10.3.9 Location of pipeline test section or final fabrication location (section,
township, range, county and state)
3.10.3.10 Recorder location
3.10.3.11 Recorder model and serial number
3.10.3.12 Beginning time, date and test pressure
3.10.3.13 Ending time, date and test pressure
3.10.3.14 Signatures of Test Supervisor and Company Inspector
Record packages for each pipeline test section shall include the following:
3.10.4.1 Test‐section profiles (where elevation differences in the section under test
exceed 100 feet) with corrected manifold locations and test pressures.
3.10.4.2 Pipeline Facility Test Reports, signed by Test Supervisor and Company
Inspector
3.10.4.3 Pressure and temperature recorder charts
3.10.4.4 Pipeline Failure Report and charts and photos of leaks and failures
3.10.4.5 Hydrostatic Test Documentation form Hydrostatic Test Documentation

<<<PAGE 1162>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 7 of 11
(Liquids) or Hydrostatic Test Documentation (Gas) completed and signed
3.11 by the Project Manager, Contract Test Supervisor, and Test Inspector.
3.10.4.6 Certifications for all temperature and pressure recorders and gauges
3.10.4.7 All records shall be sent to Pipeline Integrity for approval and retention for
the useful life of the tested segment.
Completion of Pressure Test Assessment
3.11.1 A Pressure Test Integrity Assessment will be considered complete and accepted upon
completion of a successful pressure test without leakage meeting the requirements set
forth within Section 3.8 and 3.10 of this procedure.
3.12 Dewatering
3.12.1 Block valves shall be in the fully open position for de‐watering. Water shall be drained
from the valve bodies after the dewatering is complete.
3.12.2 At the end of a successful test, the pipeline pressure shall be lowered by slowly releasing
water while maintaining a positive pressure at the highest point of the test section to
prevent air‐lock. Water shall be displaced using pigs driven either by air or nitrogen.
Refer to Section 3.7 regarding hydrostatic test water discharge piping.
3.12.3 The Project Manager shall ensure water is discharged as outlined in Right‐of‐Way and
Permit Stipulations.
3.12.4 The Project Manager shall consider using hammer unions on high‐pressure hoses
connected to frac tanks and/or vacuum trucks during the dewatering process.
3.12.5 Dewatering of the pipeline shall be complete when no free water is received with the
running of a new pig through the pipeline.
3.12.6 After a new pipeline has been de‐watered a gauge plate/sizing ring shall be run. Any
defects found that might require the line be opened to the atmosphere for repair shall
be corrected prior to drying.
3.13 Drying
3.13.1 Project Manager shall determine the required dew point for drying. Specific dew point
shall be selected based upon industry standards to meet moisture specifications for the
delivered product.
3.13.2 Bleed any residual moisture from valve bodies
3.14 Integrity Assessment Integration
3.14.1 The Project Manager shall conduct a pre and post data review with Asset Integrity
Representatives (i.e. Corrosion, Risk Engineering, Pipeline Integrity, etc.) to ensure
integration of the other pipeline integrity attributes.
4.0 DEFINITIONS
4.1 4.2 Maximum Operating Pressure (MOP) For Liquid Pipelines: The maximum pressure at which a
pipeline or segment of a pipeline may be operated under 49 CFR 195.
Dew Point: The temperature at which water vapor begins to condensate out of a gas at
atmospheric pressure

<<<PAGE 1163>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 8 of 11
System Integrity Plan Change Log
Date Change
Location
y Approve
d By
Brief Description of Change
11/08/03 All Clyde Clausen Mike Pearson Conducted Annual Review
12/03/03 1.0 Clyde Clausen Mike Pearson Purpose to Objective
12/03/03 2.1.3 Clyde Clausen Mike Pearson Data Resources to Pipeline Integrity; changed grammar of
paragraph
12/03/03 2.1.4 Clyde Clausen Mike Pearson Internal Corrosion Specialist to Supervisor, Asset Integrity
12/03/03 2.1.7 Clyde Clausen Mike Pearson Added: f the pipeline is being tested to satisfy Integrity
Management requirements, consideration should be given
to conducting a spike test.
12/03/03 2.2.1 Clyde Clausen Mike Pearson Changed: Manager of Pipeline Integrity to Manager of Asset
Integrity
12/03/03 2.2.2 B Clyde Clausen Mike Pearson Same as 2.2.1
12/03/03 2.3 Clyde Clausen Mike Pearson Re‐formatted numbering of sub‐paragraphs
12/03/03 2.3 Clyde Clausen Mike Pearson Added 2.3.15
12/03/03 2.4.1 Clyde Clausen Mike Pearson Changed to read 50  of test pressure is achieved
12/03/03 2.4.4 Clyde Clausen Mike Pearson Added: or pipe that cannot be backfilled such as an existing
span
12/03/03 2.4.5 Clyde Clausen Mike Pearson Added: in critical areas
12/03/03 2.5.1 Clyde Clausen Mike Pearson Change Ambient to pipeline temperature; Added: an
appropriate distance from the test header so as not to be
effected by the temperature of the pressure water injected
into the pipeline
12/03/03 2.6 Clyde Clausen Mike Pearson Changed Calibration to Certification
12/03/03 2.6.1 Clyde Clausen Mike Pearson Changed immediately prior to start to within the previous
12 months
12/03/03 2.7.1 Clyde Clausen Mike Pearson Added: TOR nipples that are installed with check valve plugs
should have the check valve plugs removed and replaced
with solid TOR plugs for the duration of the test. Upon
completion of the test the TOR check valve plugs may be
returned
12/03/03 2.8.1 Clyde Clausen Mike Pearson Changed WES to MMP; Added: taking into consideration
pressure rating of pipe fittings, flanges, and valves; previous
pressure test records; and appropriate design calculations
12/03/03 2.8.2 Clyde Clausen Mike Pearson Added: If a pipeline segment is determined to be
susceptible to longitudinal seam oriented failures and
hydro‐static testing is the chosen integrity assessment, then
in addition to the normal 195 Sub Part E test a spike test
would need to be performed. A spike test is generally
conducted at a pressure of at least 1.39 x MOP for 30 – 60
minutes prior to 195 Sub Part E test. All pipeline hydrostatic
test failures will be removed from the pipeline and sent to a
metallurgist for failure analysis and reporting.
12/03/03 2.8.3 Clyde Clausen Mike Pearson Changed WES to MMP
12/03/03 2.8.6 Clyde Clausen Mike Pearson Added: unless circumstances dictate otherwise
12/03/03 2.8.8 Clyde Clausen Mike Pearson Deleted reference to Offshore
12/03/03 2.9.1 Clyde Clausen Mike Pearson Deleted Offshore; Changed Engineering Manager to
Technical Services
12/03/03 2.9.1 B Clyde Clausen Mike Pearson Changed Engineering Manager to Technical Services

<<<PAGE 1164>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 9 of 11
12/03/03 2.12.3 Clyde Clausen Mike Pearson Deleted on company for WES xx (under development
12/03/03 2.13.1 Clyde Clausen Mike Pearson Added: hydrostatically pre‐tested for 4 hours before
installation, and again for 8 hours after pulled
in place by boring process, except for in‐
service pipelines in place.
12/03/03 2.14.3 G Clyde Clausen Mike Pearson Added: All records shall be sent to Pipeline Integrity for
retention
12/03/03 2.15 Clyde Clausen Mike Pearson Added: 2.15.5 After pipeline has been de‐watered a gauge
plate/sizing ring shall be run. Any defects found that might
require the line be opened to the atmosphere for repair
shall be corrected prior to drying.
12/03/03 2.16 Clyde Clausen Mike Pearson Deleted: and Gauging
12/03/03 2.1.6.1 Clyde Clausen Mike Pearson Changed grammar of paragraph; Deleted: reference to
running gauge pig
12/03/03 4.0 Clyde Clausen Mike Pearson Added: 4.3 Dew point is the temperature at which water
vapor begins to condensate out of a gas at atmospheric
pressure
12/03/03 2.9, 2.10,
2.11, 2.12,
2.14,
Clyde Clausen Mike Pearson Re‐formatted numbering of sub‐paragraphs
11/07/04 All Clyde Clausen Mike Pearson Conducted Annual Review
12/10/04 2.1.3 Clyde Clausen Mike Pearson Reworded 2nd sentence. Added: “for approval and filing” to
last sentence.
12/10/04 2.1.6 Clyde Clausen Mike Pearson Added: Hydrostatic Test Form No. 07‐FORM‐13
12/10/04 2.3.8 Clyde Clausen Mike Pearson Added: (Note: Project Manager shall ensure discharge
piping is designed for the expected discharge pressures and
shall ensure discharge piping is anchored to prevent
whipping in the event of failure.)
12/10/04 2.7.2 Clyde Clausen Mike Pearson Reworded 2nd sentence
12/10/04 2.8.1 and
2.8.3
Clyde Clausen Mike Pearson Changed Hydrostatic Test Form Numbers
12/10/04 2.8.2 Clyde Clausen Mike Pearson Reworded 2nd sentence
12/10/04 2.8.3 Clyde Clausen Mike Pearson Added: “for hazardous liquids pipelines”
12/10/04 2.8.6 Clyde Clausen Mike Pearson Changed grammar
12/10/04 2.8.8 Clyde Clausen Mike Pearson Changed grammar of paragraph
12/10/04 2.9.2 Clyde Clausen Mike Pearson Reformatted numbering of sub‐paragraphs
12/10/04 2.10.1 Clyde Clausen Mike Pearson Changed grammar of 1st sentence
12/10/04 2.14.3.5 Clyde Clausen Mike Pearson Changed Hydrostatic Test Form Numbers
12/10/04 2.14.3.7 Clyde Clausen Mike Pearson Added: “approval and”
12/10/04 2.15.2 Clyde Clausen Mike Pearson Changed grammar of paragraph and added reference to
Paragraph 2.3.8
12/10/04 2.15.5 Clyde Clausen Mike Pearson Added: “new”
12/10/04 2.16.1 Clyde Clausen Mike Pearson Changed grammar and corrected paragraph number
11/05/05 All Clyde Clausen Mike Pearson Conducted Annual Review
01/01/06 2.6 Dennis Vasicek Mike Pearson Changed Paragraph 2.6.1 and added paragraphs 2.6.2 and
2.6.3.
01/01/06 Applicability Dennis Vasicek Mike Pearson Added Applicability Section.
01/01/06 2.1 Dennis Vasicek Mike Pearson Added 2.1.1 through 2.1.3.
01/01/06 2.3.2 Dennis Vasicek Mike Pearson Reworded paragraph

<<<PAGE 1165>>>

Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 10 of 11
01/01/06 2.8.3 Dennis Vasicek Mike Pearson Reworded paragraph to be more consistent with DOT Part
195.304.
01/01/06 2.9 Dennis Vasicek Mike Pearson Grouped all of Gas Testing sections under 2.9.
01/01/06 2.12.4 Dennis Vasicek Mike Pearson Added consideration for using hammer unions on discharge
hoses.
01/01/06 All Clyde Clausen Mike Pearson Deleted References
10/30/06 All Clyde Clausen Mike Pearson Conducted annual review
10/30/06 3.1.1 Dennis Vasicek Mike Pearson Reworded paragraph to be more consistent with DOT Part
195.302
10/30/06 3.1.5.4 Dennis Vasicek Mike Pearson Added second sentence
10/30/06 3.3.1.1.4 Dennis Vasicek Mike Pearson Deleted paragraph
10/30/06 3.3.1.1.5 Dennis Vasicek Mike Pearson Deleted paragraph
10/30/06 3.3.1.1.7 Dennis Vasicek Mike Pearson Added electronic pressure gauges
10/30/06 3.5.1 Dennis Vasicek Mike Pearson Reworded paragraph to further clarify using a buried pipe
temperature sensing bulb.
10/30/06 3.6.1 Dennis Vasicek Mike Pearson Added electronic pressure gauges
10/30/06 3.10.1 Dennis Vasicek Mike Pearson Changed 4 hours to a minimum of 2 hours
10/30/06 3.11.3.7 Dennis Vasicek Mike Pearson Added “for the useful life of the tested segment”
1/5/07 3.1.4 Clyde Clausen Mike Pearson Added Paragraph requiring all hydrostatic test failures be
sent in for metallurgical review per SIP 7.02
1/5/07 3.1.5 Clyde Clausen Mike Pearson Added Paragraph requiring Engineering or Project Manager
approval
1/5/07 3.1.6 Clyde Clausen Mike Pearson Added Paragraph to consider running cleaning pigs 2
months after a successful hydrostatic test.
1/5/07 3.11.1 Clyde Clausen Mike Pearson Added Paragraph requiring final review of records and
documentation by Pipeline or Facility Integrity Engineer.
1/5/07 3.14.2 Clyde Clausen Mike Pearson Added Paragraph to bleed residual moisture from valve
bodies.
1/5/07 3.15 & 3.15.1 Clyde Clausen Mike Pearson Added Integrity Assessment Integration section and
paragraph for pre and post data review with AI
representatives.
5/23/07 3.1.2* Deaundra chancellor Clyde Clausen Modified to include “without leakage”
6/26/07 3.1.1 Clyde Clausen Mike Pearson Added paragraph
6/26/07 3.12 Clyde Clausen Mike Pearson Added Section
6/26/07 3.4.1 Clyde Clausen Mike Pearson Added paragraph
6/26/07 3.4.2 Clyde Clausen Mike Pearson Added paragraph
6/26/07 3.11.2 Clyde Clausen Mike Pearson Modified Paragraph
12/14/07 3.11.4.1 Dennis Vasicek Clyde Clausen Modified to include “(where elevation differences in the
section under test exceed 100 feet)”
01/31/08 global Updated hydrostatic links
12/22/08 3.9.1.1 Dennis Vasicek Clyde Clausen Revised paragraph for compliance with CFR Part 192.503
12/22/08 3.9.11 Dennis Vasicek Clyde Clausen Clarified facility type in the table as non‐jurisdictional gas
gathering lines
12/22/08 Dennis Vasicek Clyde Clausen Annual Review
1/12/09 3.6.1 Doug Chabino Clyde Clausen Added “Consistent with the calibration requirements in SIP
9.01‐ADM‐077”
8/7/09 3.6.1 Dennis Vasicek Clyde Clausen Replaced, “SIP 9.01‐ADM‐077” with “API RP 1110 – Pressure
Testing of Liquid Petroleum Pipelines”
8/28/09 3.1.5 Dennis Vasicek Clyde Clausen Reworded paragraph and inserted “consideration shall be
given to submit the failed section to metallurgical analysis”
8/28/09 3.9 Dennis Vasicek Clyde Clausen Removed Section 3.9 Gas Testing
9/1/09 3.2.1 Dennis Vasicek Clyde Clausen Changed “Director” to “Manager”

<<<PAGE 1166>>>

9/1/09 9/2/09 9/4/09 10/9/09 11/9/09 11/9/09 11/9/09 11/9/09 5/27/10 5/27/10 5/27/10 12/1/10 01/01/11 03/09/11 9/1/11 9/1/11 9/1/11 9/1/11 9/1/11 12/31/11 12/31/11 Magellan Midstream Partners, L.P.
PRESSURE TESTING 7.03–ADM–001
Asset Integrity 01/01/12 Revision: 13 Page 11 of 11
3.2.2.2 Dennis Vasicek Clyde Clausen Changed “Director” to “Manager”
3.11.1 Dennis Vasicek Clyde Clausen Removed reference to Gas Testing section and corrected
reference to 3.10
3.9.1.3 Dennis Vasicek Clyde Clausen Added comment to notify Environmental Specialist if
additives are to be used.
3.8.2 Dennis Vasicek Clyde Clausen Revised typical duration of spike test and reworded
paragraph to be consistent with 3.1.5 revision
2.2 Dennis Vasicek Clyde Clausen Removed Longhorn Specific paragraph
3.1.6 Dennis Vasicek Clyde Clausen Removed “or Project Manager”
3.1.9.2 Dennis Vasicek Clyde Clausen Revised requirement to submit records to “Pipeline
Integrity” to “Asset Integrity Engineering”
Dennis Vasicek Clyde Clausen Annual Review
3.1.3 Chabino Clausen In‐place pressure testing is not required for repairs if>>>>
3.1.4 Chabino Clausen Added.. Pressure tests must include all pipe and attached
fittings, including components.
3.1.5. Chabino Clausen Modified to reference Analysis of Pipe Cutouts program.
3.1.10 Dennis Vasicek Clyde Clausen Added precautionary language about excavating a pipeline
to install a tap
3.4.7 Added dec 1 2010 email from Clyde Clausen
3.1.8.2/5.1 Removed reference to DOT 192
All Clyde Clausen Doug Chabino Conducted Annual Review
3.8.5 Clyde Clausen Doug Chabino Added Shall be considered for excavation to
paragraph
3.8.8.1 Clyde Clausen Doug Chabino Added paragraph
3.1.9.2 Clyde Clausen Doug Chabino Added new paragraph under Project Manager
Shall:
3.1.10 Clyde Clausen Doug Chabino Added guidance to paragraph
4.0 (old) Removed Links section
All 2012 Annual Review complete

<<<PAGE 1167>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 1 of 18
1.0 OBJECTIVE
1.1 The Objective of this procedure is to establish the process to analyze In‐Line Inspection (ILI) data to
identify features that require repair per DOT 49 CFR 195.452.
2.0 INDEX
1.0 OBJECTIVE ........................................................................................................................................ 1
2.0 INDEX ................................................................................................................................................. 1
3.0 PROCEDURE ..................................................................................................................................... 1
4.0 PRELIMINARY REPORTS ................................................................................................................. 1
5.0 ELECTRONIC DRAFT REPORTS ...................................................................................................... 1
6.0 FINAL REPORTS ................................................................................................................................ 1
7.0 INTEGRITY CONDITIONS ................................................................................................................. 2
8.0 9.0 DISCRETE POINT PRESSURE (DPP) ANALYSIS ............................................................................ 5
SEAM WELD ASSESSMENT ............................................................................................................. 6
10.0 ULTRASONIC WALL MEASUREMENT ASSESSMENT ................................................................... 7
11.0 CASING ANALYSIS ............................................................................................................................ 8
12.0 DENT REVIEW AND DEPTH OF COVER CORRELATION .............................................................. 8
13.0 PROJECTED CORROSION GROWTH ANALYSIS ........................................................................... 8
14.0 CALIBRATION DIGS ......................................................................................................................... 9
15.0 DIG LIST ........................................................................................................................................... 10
16.0 ILI SUMMARY DOCUMENT ............................................................................................................. 10
17.0 CORRELATION AND TOOL TOLERANCE ASSESSMENT............................................................ 11
18.0 DEFINITIONS .................................................................................................................................... 12
19.0 REFERENCES .................................................................................................................................. 13
3.0 PROCEDURE
3.1 3.2 3.3 3.4 This guideline incorporates API 1163, In‐line Inspection Systems Qualification Standard, First Edition,
August 2005; NACE Standard RP0102‐2002; and ANSI/ASNT ILI‐PQ‐2005 where applicable.
This guideline is applicable to federal and/or state jurisdictional pipelines and/or facilities. Elements
of this program may be used, in whole or part, on non‐jurisdictional assets as deemed appropriate.
Assets Covered Per Mitigation Plan operate under Longhorn Mitigation Plan requirements in addition
to applicable Federal, State, and Local regulations and Company guidelines, processes or best
practices.
The Pipeline Integrity Engineer and Pipeline Integrity Data Coordinator will utilize this Guideline in
conjunction with the In‐Line Inspection Procedure when conducting analyses of Inspection data.
.

<<<PAGE 1168>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 1 of 18
4.0 PRELIMINARY REPORTS
4.1 In‐line Inspection Vendor (Vendor) will provide Preliminary Report (if required) within 21
business days of a successful tool run. Features requiring a Preliminary Report are described in
In‐Line Inspection Technical Specification.
4.2 If features meeting preliminary reporting criteria are reported by Vendor, Pipeline Integrity
Engineer will:
4.2.1. 4.2.2. 4.2.3. Notify Supervisor of Pipeline Integrity Engineering via email.
Initiate immediate investigation and repair process described in In‐Line Inspection
Procedure if feature is located in an HCA.
4.3 Ensure that appropriate response is executed within 5 days of receipt of Preliminary
Report for features reported on Assets Covered Per Mitigation Plan in accordance with
Longhorn Mitigation Plan, Section 3.5.2.
4.2.4. Request Pipeline Integrity Data Analyst to prepare dig sheets.
4.2.5. Provide excavation findings to Vendor upon completion of any field investigations.
Pipeline Integrity Data Analyst will:
4.3.1. Prepare dig sheets using Procedure for Creating Dig Sheets.
4.3.2. Prepare Rehab Book for inspector in accordance with Project File Index Form.
5.0 ELECTRONIC DRAFT REPORTS
5.1 Vendor will provide an electronic Draft Report as specified in In‐Line Inspection Technical
Specification.
5.2 Pipeline Integrity Data Analyst will verify electronic Draft Report as specified in AGM Verification
Guidelines.
Verify electronic Draft Report as specified in ILI Data Verification Guidelines.
5.3 Pipeline Integrity Engineer will:
5.3.1. 5.3.2. Approve electronic Draft Report or provide Vendor any comments within 5 business
days of receipt of electronic Draft Report. If discrepancies are identified, Vendor will be
required to make necessary modifications before issuance of Final Report.
6.0 FINAL REPORTS
6.1 Pipeline Integrity Engineer will
6.1.1. 6.1.2. Perform QA/QC review of Final Report to ensure it is thorough, complete, correct and
delivered in accordance with In‐Line Inspection Technical Specification.
6.1.1.1. If a significant issue is observed, Pipeline Integrity Engineer will
immediately reject Final Report and notify Vendor in writing.
Declare the date of discovery (Discovery) within 5 business days of receipt of a valid
Final Report but not later than 180 days after the day ILI tool was trapped in the
receiver.
6.1.2.1. 6.1.3. Pipeline Integrity Engineer will calculate 60‐day and 180‐day due dates for
HCA conditions based on counting forward from Discovery date.
For Assets Covered Per Mitigation Plan Send a copy of MFL Final Report to Operational

<<<PAGE 1169>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 2 of 18
6.2 6.1.4. 6.1.5. 6.1.6. Reliability Assessment (ORA) Contractor for Probability of Exceedance (POE) analysis,
girth weld evaluation and metal loss within 3 inches of girth weld for.
Copy electronic documents (i.e. pipeline listing, NWT report, AGM listing and mapping
files, LAPA [if provided], certification of calibration) to appropriate line section folder on
network drive.
Perform detailed analysis of ILI data to identify: immediate, 60‐day, 180‐day and 6‐
month (where applicable) features, DPP features, casings to be worked, ID reduction
review, and other features potentially requiring investigation.
Schedule a Pre‐Job Roundtable meeting with various stakeholders (as appropriate: Asset
Integrity Maintenance Supervisor, Asset Integrity Engineer, Supervisor Corrosion
Control, Pipeline Integrity Coordinator, Real Estate Representative, Pipeline Integrity
Data Analyst, Supervisor of Pipeline Integrity Engineering and Manager of Asset
Integrity) to discuss ILI Summary document, features to be investigated, and other
concerns (e.g. integrated depth of cover and corrosion control data) identified by Final
Report.
Pipeline Integrity Data Analyst will:
6.2.1. Prepare dig sheets using Procedure for Creating Dig Sheets.
6.2.2. Prepare a project field book using Project File Index Form.
6.2.3. Obtain completed project field book from chief inspector and perform checks on
information accumulated during rehabilitation upon completion of rehabilitation
activities.
7.0 INTEGRITY CONDITIONS
7.1 7.2 7.3 Pipeline Integrity Engineer will obtain High Consequence Area (HCA) begin and end location
information from Risk Analyst or from HCA database and calculate corresponding odometer
locations to mark in Final Report.
Pipeline Integrity Engineer will identify the following conditions:
HCAS And Areas That Could Affect HCAs
7.3.1. Immediate Repair Conditions
7.3.1.1. Discovery of an immediate repair condition is to be established no later
than 5 business days after condition is reported to Company. Within 5
business days of identification of an immediate repair condition, Pipeline
Integrity Engineer will initiate immediate investigation and repair process
in accordance with In‐Line Inspection Procedure.
7.3.1.2. Until immediate condition is repaired, the following operating conditions
may be implemented (dependent upon the type of feature).
7.3.1.2.1. Reduce operating pressure so that at the location of the
anomaly, discrete point pressure (PDPP) does not exceed
operating pressure (PSAFE), or PDPP does not exceed the
pressure calculated by the formula in Section 451.7 of
ASME/ANSI B31.4, or
7.3.1.2.2. Reduce operating pressure so that PDPP does not exceed 80%

<<<PAGE 1170>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 3 of 18
7.3.1.3. 7.3.1.4. of highest operating pressure actually experienced at location
of anomaly within 60‐days preceding inspection, or
7.3.1.2.3. Shutdown pipeline.
Metal loss features (including SWFA, SWFB, ASWML and SWML) with
predicted depths greater than or equal to 80% of the wall thickness
requires reducing operating pressure per 7.3.1.2.2 or shutdown pipeline
until repair is made.
Features with predicted burst pressure, PBURST, less than PDPP requires
reduce operating pressure per 7.3.1.2.1 or shutdown pipeline until repair is
made.
7.3.1.4.1. 7.3.1.4.2. Metal loss calculation using 85% Area RSTRENG criterion or
CorLASTM (Flow Stress Criterion, 85% Area)
SWFA, SWFB, ASWML, or SWML calculation using CorLASTM
(Fracture Mechanics Criterion)
7.3.1.5. Top‐side dents (above the 4 and 8 o’clock positions) predicted to contain
associated metal loss, cracking or a stress riser requires reducing operating
pressure per 7.3.1.2.2 or shutdown pipeline until repair is made.
7.3.1.6. Top‐side dents with a predicted depth greater than 6% of the nominal pipe
diameter requires reducing operating pressure per 7.3.1.2.2 or shutdown
pipeline until repair is made.
7.3.1.7. Significant features in the judgment of the person evaluating the
inspection and test assessment results requires reducing operating
pressure or shutdown pipeline based upon type of feature and engineering
analysis until repair is made.
7.3.1.8. Deformation anomaly characterized as a pipeline device or repair intrusion
such as pig‐sig, IFD, tube, flow improver nozzle, heavy weld, etc. will not be
considered an “Immediate Condition.”
7.3.2. 60‐Day Repair Conditions
7.3.2.1. Top‐side dents with a predicted depth greater than 3% of the pipeline
diameter (greater than 0.250” in depth for a pipeline diameter less than
Nominal Pipe Size (NPS) 12).
7.3.2.2. Bottom‐side dents (below 4 and 8 o’clock positions) predicted to contain
any metal loss, cracking, or a stress riser.
7.3.3. 180‐day Repair Conditions
7.3.3.1. Dents with a predicted depth greater than 2% of the pipeline’s diameter
(0.250” in depth for a pipeline diameter less than NPS 12) that affects pipe
curvature at a girth weld or a longitudinal seam weld.
7.3.3.2. Top‐side dents with a predicted depth greater than 2% of the pipeline’s
diameter (0.250” in depth for a pipeline diameter less than NPS 12).
7.3.3.3. Bottom‐side dents with a predicted depth greater than 6% of the pipeline’s
diameter.
7.3.3.4. Features where the calculation of remaining strength of the pipe shows an

<<<PAGE 1171>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 4 of 18
7.4 operating pressure, PSAFE, that is less than PDPP at the location of the
anomaly.
7.3.3.5. Areas of general corrosion with a predicted metal loss greater than 50% of
nominal wall
7.3.3.6. Features with predicted metal loss greater than 50% of nominal wall that
are located at a crossing of another pipeline, or are in an area with
widespread circumferential corrosion, or are in an area that could affect a
girth weld
7.3.3.7. Potential crack indications that when excavated are determined to be a
crack.
7.3.3.8. Corrosion of or along a longitudinal seam weld (as identified by the ILI
service provider as being axially oriented seam weld metal loss)
7.3.3.9. Gouge or grooves with a predicted depth greater than 12.5% of nominal
wall
7.3.4. Other Conditions
7.3.4.1. Conditions identified by ILI that could impair the integrity of the pipeline
should be repaired as appropriate.
Non‐HCAS And Areas Not Affecting HCAS
7.4.1. The following anomalies will be immediately evaluated and scheduled for excavation if
deemed necessary. However, all HCA Immediate Conditions shall take priority:
7.4.1.1. Metal loss (including SWFA, SWFB, ASWML, and SWML) greater than or
equal to 80% wall thickness
7.4.1.2. Features with predicted burst pressure Pburst, less than discrete point
pressure, PDPP.
7.4.1.3. 7.4.1.2.1. Metal Loss calculation using 85% Area RSTRENG Criterion or
CorLAS™ (Flow Stress Criterion, 85% Area)
7.4.1.2.2. SWFA, SWFB, ASWML, or SWML calculation using CorLAS™
(Fracture Mechanics Criterion)
Top‐side dents with any indicated metal loss, cracking or stress riser
7.4.2. The following anomalies will be evaluated and scheduled for excavation and repair prior
to the next integrity assessment if deemed necessary:
7.4.2.1. Features where PSAFE is less than PDPP at location of anomaly.
7.4.2.2. Bottom‐side dents with associated metal loss.
7.4.2.3. Girth weld anomalies
7.4.2.4. Dents in excess of 6% of pipe diameter.
7.4.2.5. Dents located in the girth weld or longitudinal seam that exceed 2% of pipe
diameter for NPS 12 and larger or 0.250” for pipe diameters less than NPS
12.
7.4.2.6. Gouges, scratches, or grooves that exceed 12.5% metal loss.
7.4.2.7. Severe mill related defects (lamination, hard spots, etc.).

<<<PAGE 1172>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 5 of 18
7.4.2.8. Crack‐like anomalies located in girth weld, longitudinal seam weld, or pipe
7.5.2. 8.0 7.5 7.6 body.
7.4.2.9. Field confirmed casing shorts with associated metal loss.
7.4.2.10. Other significant anomalies.
7.4.2.11. Features identified for tool calibration purposes.
Assets Covered Per Mitigation Plan
7.5.1. Initiation of a response must be implemented within 5 days of receipt of report for
these features in accordance with Longhorn Mitigation Plan Section 3.5.2
7.5.1.1. Metal loss greater than 70% wall thickness
7.5.1.2. Top‐side dents with any indicated metal loss
7.5.1.3. Significant anomalies that in the judgment of the data evaluator require
immediate action
initiation of a response must be implemented within 60 days of receipt of report for
these features in accordance with Longhorn Mitigation Plan Section 3.5.2.
7.5.2.1. Top‐side dents without indicated metal loss and with depths greater than
6% of the pipe diameter
7.5.3. The following indications shall be investigated within 6 months of the receipt of report
in accordance with Longhorn Mitigation Plan Section 3.5.2.
7.5.3.1. Dents with any of the following: Metal loss, corrosion, exceeds 6% of the
pipe outside diameter, or located in a longitudinal seam or girth weld
Features where remaining strength of pipe results in a safe operating
pressure, PSAFE, that is less than the current MOP at the location of the
anomaly using a suitable safe operating pressure calculating criterion.
7.5.3.3. Casing shorts with associated metal loss
7.5.3.4. Girth weld anomalies
7.5.3.5. Corrosion within 3” of either side and/or across girth welds as determined
by ORA contractor
7.5.3.6. Preferential corrosion of or along seam welds.
7.5.3.7. Gouges or grooves greater than 50% of nominal wall thickness
7.5.3.8. Cracks located in the pipe body, girth weld, and longitudinal seam that are
determined to be injurious to the integrity of the pipeline.
As an alternative to direct examination, an API 579 Fitness‐For‐Service level 1, 2, and/or 3
Engineering Critical Assessment may be performed in order to substantiate the need for direct
examination activity.
DISCRETE POINT PRESSURE (DPP) ANALYSIS
8.1 Pipeline Integrity Engineer will populate discrete point pressure (DPP) spreadsheet with
anomalies with rupture pressure ratio (RPR) less than 1.0. RPR is PBURST divided by pipe design
pressure. PSAFE is design factor multiplied by PBURST. RPR will be less than 1.0 when PBURST of an
anomaly is less than pipe design pressure (100% SMYS). DPP data sources include:
7.5.3.2.

<<<PAGE 1173>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 6 of 18
8.1.1. ILI Final Report
8.1.2. Corrosion Growth spreadsheet
8.1.3. Seam Weld Assessment analysis
8.2 Pipeline Integrity Data Analyst will:
8.2.1. Calculate stations using Total AGMs Form and obtain elevations using alignment sheets
for features requiring DPP analysis.
8.2.2. Use alignment sheets to determine if any metal loss features greater than 50% are
located within 50’ of a foreign pipeline crossing and will indicate on appropriate tab in
the DPP spreadsheet.
8.3 Asset Integrity Engineer will complete DPP analysis taking into account pump set points,
elevation differences, and surge conditions.
8.3.1. Determine, through available records, design pressure for line and upstream pump
maximum discharge set point.
8.3.2. Determine maximum elevation difference between pressure source and feature
location.
8.3.3. Determine static head pressure due to elevation change calculated using specific gravity
of heaviest product.
8.3.4. Add static head pressure to pump set point to get PDPP at feature location due to static
head (Static PDPP).
8.3.5. For incompressible liquid pipelines, conduct surge analysis at each feature location to
determine PDPP due to surge (Surge PDPP).
8.3.6. Compare static PDPP and surge PDPP at each feature location. Select greater value to be
used as PDPP for anomaly location.
8.4 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
9.0 SEAM WELD ASSESSMENT
9.1 Pipeline Integrity Engineer or designee will conduct seam weld assessment (SWA) when ILI tool is
either circumferential flux leakage (aka TFI, AFD, or SWML ILI) or ultrasonic crack detection
(USCD) ILI technology.
9.2 The following anomalies will be assessed and considered for investigation and/or remediation.
9.2.1. Seam Weld Feature A (SWFA)
9.2.2. Seam Weld Feature B (SWFB)
9.2.3. Axial Seam Weld Metal Loss (ASWML)
9.2.4. Seam Weld Deformation (SWD)
9.2.5. Axial Planar features
9.2.6. Crack‐Field
9.2.7. Notch‐Like

<<<PAGE 1174>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 7 of 18
9.2.8. Weld Anomaly
9.2.9. Other integrity features in the judgment of the person evaluating the data
9.3 Pipeline Integrity Engineer or designee will calculate Pburst and Psafe using CorLAS™ (fracture
criterion) or similar remaining strength calculation and using appropriate fracture toughness for
SWFA, SWFB, ASWML and SWML anomalies.
9.4 Pipeline Integrity Engineer or designee may use MFL data, when available, to identify additional
potential SWML anomalies, defined as those within 2 inches of LSW. For these integrated SWML
anomalies, Pipeline Integrity Engineer or designee will calculate Pburst and Psafe for all internal and
external anomalies, using 85% Area RSTRENG™ or CorLAS™ (flow stress criterion, 85% Area)
9.5 Pipeline Integrity Engineer will add to DPP spreadsheet features requiring direct examination
when PBURST is less than pipe design pressure (100% SMYS) and features identified in SWA report
as requiring DPP analysis. RPR and PBURST values listed in SWA report will be used in DPP
spreadsheet.
9.6 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
10.0 ULTRASONIC WALL MEASUREMENT ASSESSMENT
10.1 Pipeline Integrity Engineer or designee will conduct ultrasonic wall measurement (USWM)
assessment when ILI tool is USWM ILI technology.
10.2 Pipeline Integrity Engineer or designee will consult with ILI vendor and Magellan’s third party
consultant to establish reporting and evaluation criteria guidelines. If needed, modifications will
be made to Magellan’s In‐Line Inspection Technical Specification. All laminations as identified by
tools reporting capabilities will be included in final report.
10.3 The following Laminations will be evaluated and considered for investigation and/or
remediation.
10.3.1. Sloping laminations
10.3.2. Bulging laminations
10.3.3. Surface breaking laminations
10.3.4. Hydrogen blisters
10.3.5. Laminations interacting with deformations, metal loss, cracks, girth and seam welds,
and other reported features
10.3.6. Other integrity features in the judgment of the person evaluating the data.
10.4 When applicable, Pipeline Integrity Engineer or designee will review the USWM data for seam
weld features and perform calculations described in the Seam Weld Assessment process.
10.5 Pipeline Integrity Engineer or designee will identify and evaluate all reported deformations
identified by EGP (Electronic Geometry Pigs) or other applicable ILI inspections that correlate and
interact with existing laminations.
10.6 Pipeline Integrity Engineer or designee may use previous ILI data, when available, to identify
additional metal loss anomalies and significant features (i.e. cracks, girth welds, long seam, etc.)
that may be potentially associated with laminations. For integrated metal loss anomalies > 20%
deep, Pipeline Integrity Engineer or designee will calculate PBURST and PSAFE for all internal and

<<<PAGE 1175>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 8 of 18
external anomalies using CorLASTM (Fracture Mechanics Criterion)
10.7 Pipeline Integrity Engineer will add to DPP spreadsheet features requiring direct examination
when PBURST is less than pipe design pressure (100% SMYS) and features identified in USWM
report as requiring DPP analysis. RPR and PBURST values listed in USWM report will be used in DPP
spreadsheet.
10.8 Pipeline Integrity Engineer will add anomalies in HCA with PBURST < PDPP to dig list as immediate
repair conditions (priority conditions in non‐HCA) and will add anomalies in HCA with PSAFE < PDPP
to dig list as 180‐day conditions (secondary conditions in non‐HCA).
10.9 Pipeline Integrity Engineer will place all features requiring investigation on the dig list
11.0 CASING ANALYSIS
11.4 Pipeline Integrity Data Analyst will notify Pipeline Integrity Engineer if any casings need to be
added to Dig List.
11.5 Pipeline Integrity Engineer will identify casings with metal loss in Final Report.
12.0 11.1 Pipeline Integrity Engineer will create a list of casings with casing begin and end locations in
order of absolute distance.
11.2 Pipeline Integrity Data Analyst will determine casings that require rehabilitation. Pipeline
Integrity Data Analyst will:
11.2.1. Add metal loss information from Final Report to designate number of metal loss
features and maximum and minimum depths of metal loss inside each casing.
11.2.2. Check with Pipeline Integrity Engineer to determine if any casings are scheduled to be
investigated due to required ILI investigations.
11.2.3. Review corrosion database for potential shorted or elevated casings.
11.2.4. Request Corrosion Technician field verify casings as required.
11.3 Corrosion Technician will resolve discrepancies and perform field verification of casings as
required, notify Pipeline Integrity Data Analyst about casings that need to be investigated during
pipeline rehabilitation, and incorporate field verification findings into corrosion database.
DENT REVIEW AND DEPTH OF COVER CORRELATION
12.1 Pipeline Integrity Engineer will create a top‐side dent list and a dent comparison list. The dent
comparison list will match current dent callouts to previous ILI run dent callouts.
12.2 Pipeline Integrity Engineer may request previous run Vendor to verify data signal to determine if
current dents were visible in previous run data.
12.3 Pipeline Integrity Data Analyst will review depth of cover database and/or spreadsheets, if
available, to determine depth of cover and land use for each identified top‐side dent.
12.4 Pipeline Integrity Engineer will:
12.4.1. Add top‐side dents located in cultivation with depth of cover less than 18” to the Dig List
for investigation.
12.4.2. Add top‐side dents where no depth of cover information is available to the Dig List as
“stake only” digs to determine land use and depth of cover. Further investigation of
these features may be necessary pending land use and depth of cover information.
13.0 PROJECTED CORROSION GROWTH ANALYSIS

<<<PAGE 1176>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 9 of 18
13.1 13.2 13.3 13.4 13.5 13.6 13.7 Pipeline Integrity Engineer will analyze metal loss indications to establish a re‐assessment
interval based on projected corrosion growth (PCG). Pipeline Integrity Engineer will:
13.1.1. Create PCG analysis spreadsheet and input vital pipeline and ILI data for each metal loss
anomaly and corrosion growth time period (typically 6.2 years)
13.1.2. Input 110% MOP for line segment
13.1.3. Input year of construction and year of inspection
13.1.4. Calculate PCG rate for each metal loss anomaly assuming linear corrosion growth
starting at time of construction based on the following formula where d/t is depth of
metal loss (percentage of wall thickness) as reported by ILI tool.
PCG rate = Reported (d/t) / Years
Where multiple inspections have been conducted utilizing like technologies, Pipeline Integrity
Engineer will calculate a run comparison PCG rate for each metal loss anomaly with a reported
peak depth ≥ 25% wall thickness by comparing current reported peak depth with a previous
reported peak depth and dividing by years between inspections.
13.2.1. Pipeline Integrity Engineer will input run comparison PCG rate into a separate run
comparison projected corrosion growth analysis spreadsheet.
13.2.2. For features indicating “Consider Remediation”, Pipeline Integrity Engineer will contact
previous run Vendor to verify feature sizing. Revised feature sizing will be updated in
the run comparison spreadsheet and a new PCG rate will be calculated.
13.2.3. For features indicating a10 mils per year or greater PCG rate, Pipeline Integrity Engineer
will contact previous run Vendor to verify feature sizing. Revised feature sizing will be
updated in the run comparison spreadsheet and a new PCG rate will be calculated.
Pipeline Integrity Engineer will calculate a 6.2‐year projected depth of corrosion, (d/t) Projected,
based on the following formula. This assessment can also be performed for intervals other than
6.2‐years but (d/t) cannot exceed 1.00 (i.e., depth exceeds wall thickness).
(d/t) Projected = (d/t) Reported + 6.2*PCG rate
Pipeline Integrity Engineer will calculate PBURST based on (d/t) Projected and add metal loss
indications for which PBURST is less than 110% MOP to DPP analysis spreadsheet. DPP analysis will
be conducted as described in Discrete Point Pressure Analysis section.
Pipeline Integrity Engineer will consider adding to Dig List metal loss anomalies for which (d/t)
Projected exceeds 80% wall thickness.
Pipeline Integrity Engineer will consider adding to Dig List metal loss anomalies for which the PCG
rate is 10 mils per year or greater.
Assets Covered Per Mitigation Plan
13.7.1. Identify locations where (d/t) Projected exceeds 70% wall thickness and consider adding
to Dig List.
14.0 CALIBRATION DIGS
14.1 14.2 If deemed necessary by the Company and/or Vendor, Pipeline Integrity Engineer will add
calibration investigations of potential anomalies to Dig List in order to confirm performance of
the ILI tool as described in Correlation and Tool Tolerance Assessment Section.
When possible, Pipeline Integrity Engineer will add to Dig List a minimum of one calibration

<<<PAGE 1177>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 10 of 18
investigation in seamless pipe.
15.0 DIG LIST
15.1 15.1.1. 15.1.2. 15.1.3. 15.1.4. 15.1.5. 15.1.6. Pipeline Integrity Engineer will create dig List and include the following:
Immediate conditions and preliminary digs performed prior to receipt of Final
Report.
Integrity Conditions (HCA and non‐HCA)
DPP features identified through DPP Analysis
“Features > 50%” located at foreign crossings, in an area of general corrosion, or
any areas that affect a girth weld.
Potential crack‐like anomalies, including SFWA, SFWB, ASWML, and SWD and other
features identified through Seam Weld Assessment
Laminations and other features identified through section 10 of the Ultrasonic Wall
Measurement Assessment
15.1.7. Casings identified through Casing Analysis
15.1.8. Dents identified through Dent Review
15.1.9. Metal loss features identified through Projected Corrosion Growth Analysis
15.1.10. Calibration Digs
15.2 15.3 15.4 15.5 15.6 15.7 15.8 Pipeline Integrity Engineer will compare proposed Dig List to information from previous
rehabilitation projects for locations where anomalies have been previously investigated
and will consider eliminating these anomalies from Dig List.
Pipeline Integrity Engineer will mark digs in Final Report and document appropriate
comments for dig list.
Pipeline Integrity Engineer will give Final Report and proposed Dig List to Supervisor of
Pipeline Integrity Engineering or Manager Asset Integrity for review.
Supervisor of Pipeline Integrity Engineering or Manager of Asset Integrity will review ILI
Final Report and proposed Dig List, including:
15.5.1. External metal loss indications reported inside casings
15.5.2. Potential interactions of metal loss indications reported in seamless pipe
15.5.3. Past ILI records and dig results, leak history, corrosion growth analysis, and
previous Executive Summary of Risk Analysis.
15.5.4. Send approval of proposed dig list with any additional proposed digs, if
applicable, to Pipeline Integrity Engineer.
Pipeline Integrity Engineer will incorporate changes requested by Supervisor of Pipeline
Integrity Engineering or Manager of Asset Integrity.
Pipeline Integrity Engineer will contact Vendor to manually verify location and feature
sizing of dig list features. Vendor comments may be added to the dig list.
Pipeline Integrity Data Analyst will create dig sheets using Procedure for Creating Dig
Sheets.
16.0 ILI SUMMARY DOCUMENTS

<<<PAGE 1178>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 11 of 18
17.0 16.1 Pipeline Integrity Engineer will complete ILI Summary document.
CORRELATION AND TOOL TOLERANCE ASSESSMENT
17.1 17.2 17.3 17.4 17.5 When inspecting potential anomalies in the field, NDE contractor and Pipeline Integrity
Coordinator will use their best efforts to try to understand how/why ILI tool reported
various defects observed in the field and will capture this in Pipeline Maintenance Report.
Pipeline Integrity Coordinator should be consulted and discrepancies should be resolved
in the field before coating and backfilling when possible.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will review NDE reports and
compare ILI reported anomaly dimensions to actual defect dimensions observed in the
field.
17.2.1. Comparisons will be used to develop a depth unity plot and data correlation
report for each ILI run.
17.2.2. Anomalies to be correlated will include detectible metal loss, SWFA, SWFB,
ASWML, SWML and ID reductions.
For Assets Subject to Company Consent Decree Effective 9/4/08,
17.3.1. Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will complete
comparison described above within three (3) months following completion of
anomaly investigations associated with each ILI run. Comparison will include a
statistically valid number of anomalies.
17.3.1.1. For ILI runs where an insufficient number of anomalies are identified
to perform a statistically valid comparison analysis, anomaly
comparisons may include other indications such as casings, girth
welds, previous repairs, and other pipeline appurtenances. In these
instances, Pipeline Integrity Engineer or Pipeline Integrity Data
Analyst will document actual versus predicted indication
characteristics for each ILI run.
17.3.2. Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will develop two (2)
sets of unity plots (length of axial oriented anomaly and depth into pipe wall)
within three (3) months following completion of anomaly investigations
associated with each ILI run intended to inspect ERW longitudinal seam weld.
17.3.2.1. ILI cracks/anomalies include detectible seam weld and HAZ features
and indications
17.3.2.2. For ILI runs where an insufficient number of seam and HAZ
anomalies are identified to perform a statistically valid comparison
analysis, anomaly comparisons may include other indications. In
these instances, Pipeline Integrity Engineer or Pipeline Integrity Data
Analyst will document actual versus predicted indication
characteristics for each ILI run.
Pipeline Integrity Engineer will review unity plots and data correlation reports and will
consider additional excavations, regrading, engineering evaluation assessments, or re-
running ILI tool if observed defect sizes are consistently outside of Vendor specified
tolerances.
If comparison described above suggests that Vendor undersized (or “undercalled”, as in
anomalies were observed to be more severe than predicted) anomalies, Pipeline Integrity
Engineer will take tool tolerances into account to recalculate corrosion growth rate and
consider requesting Vendor regrade data, performing any necessary additional digs, or
refining reassessment interval.

<<<PAGE 1179>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 12 of 18
17.5.1. A statistically valid representation of investigated anomalies must be present in
order to determine undersize percentages. Outlying investigated features may
be discounted.
17.5.2. For metal loss,
17.5.2.1. Add average undersize percentage of anomalies that were
undersized to peak depth of uninvestigated metal loss anomalies in
Projected Corrosion Growth spreadsheet.
17.5.2.2. Recalculate corrosion growth rate
17.5.2.3. 17.5.2.4. Recalculate PBURST and PSAFE to compare with PDPP
If, within 6.2 years, an unrepaired metal loss feature is predicted to
reach 80% peak depth (70% peak depth for Assets Covered Per
Mitigation Plan) or if PBURST is predicted to be less than PDPP, it
should be added to Dig List.
17.5.3. For ID reductions,
17.6 17.7 17.8 17.9 17.5.3.1. If the comparison indicates an average undersize of features, add
average undersize percentage of all anomalies to depth of
uninvestigated ID reductions
17.5.3.2. Compare new depth to repair criteria and add ID reductions meeting
repair criteria to Dig List.
Pipeline Integrity Engineer may consider a Probability of Exceedance (POE) analysis
(required for Assets Covered Per Mitigation Plan) or other engineering analysis as an
alternative means to assess tool tolerances in order to determine if additional direct
examinations are required.
17.6.1. When direct examination activities result in a statistically significant sample size
of observed defects, actual tool performance will be used. Otherwise, Vendor
specified tolerance may be used.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will summarize examination
results from Pipeline Maintenance Report and NDE sheets and create a data correlation
report. Significant discrepancies should be resolved by Vendor and by NDE contractor.
Pipeline Integrity Engineer will provide completed data correlation report to Vendor.
Pipeline Integrity Engineer or Pipeline Integrity Data Analyst will notify Supervisor of
Pipeline Integrity Engineering that data correlation, unity plots and projected corrosion
growth are complete and that additional digs are/are not necessary.
18.0 DEFINITIONS
18.1 Terms and terminology will be used in accordance with API 1163 Section 4, unless otherwise
specified herein. Additional definitions are as follows:
18.1.1. Seam Weld Feature A (SWFA): Seam weld indication that exhibits possible “crack‐
like” characteristics
18.1.2. Seam Weld Feature B (SWFB): Seam weld indication that exhibits some, but not all
“crack‐like” characteristics
18.1.3. Seam Weld Metal Loss: SWML. Metal loss indication (including any part of a cluster)
that encroaches upon the longitudinal seam weld (LSW).
18.1.4. Axial Seam Weld Metal Loss (ASWML): Metal loss indication (including any part of a

<<<PAGE 1180>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 13 of 18
18.1.5. 18.1.6. 18.1.7. 18.1.8. 18.1.9. 18.1.10. cluster) that encroaches upon the LSW and is less than 2‐inches wide with a length‐
to‐width aspect ratio equal to or greater than 5:1
Seam Weld Deformation (SWD): Deformation that encroaches upon the LSW
Seam Weld Anomaly (SWA): Feature other than a SWFA, SWFB, SWML, or SWD that
encroaches upon or is immediately adjacent to the LSW and is thought to be non‐
injurious.
PBURST: Estimated burst (failure) pressure for an anomaly as calculated according to a
given standard or practice (e.g., RSTRENG™, ASME B31G, CorLAS™)
PSAFE: PBURST multiplied by a design factor (e.g., 0.72)
PDPP: Discrete point operating pressure at a given location
Design Factor, F: from ASME B31.4, ASME B31.8, or ASME B31.11. For onshore
hazardous liquid pipelines, F is typically equal to 0.72. For natural gas pipelines, F
ranges from 0.40 to 0.72 depending on class location
19.0 REFERENCES
19.1 Regulatory
19.1.1. 49 CFR Part 195.452
19.2 Related Policies/Procedures
19.2.1. In‐Line Technical Specification
19.2.2. ILI Data Verification Guidelines
19.2.3. AGM Verification Guideline
19.2.4. 19.2.5. In‐Line Inspection Procedure
Procedure for Creating Dig Sheets

<<<PAGE 1181>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 14 of 18
System Integrity Plan Change Log
Date Change Location Change By Approved By 11/08/04 All Clyde Clausen Mike Pearson 11/04/05 All Clyde Clausen Mike Pearson 10/30/2006 All Clyde Clausen Mike Pearson 10/30/2006 2.4.1.2
Mike Pearson Larry Franklin
10/30/2006 2.4.1.19 Dennis Vasicek Mike Pearson 10/30/2006 2.4.1.20
Mike Pearson Dennis Vasicek
10/30/2006 2.4.1.22
Mike Pearson Larry Franklin
10/30/2006 2.4.1
Mike Pearson Larry Franklin
10/30/2006 2.4
Mike Pearson Dennis Vasicek
10/30/2006 2.7.1
Mike Pearson Larry Franklin
10/30/2006 2.7.1 Larry Franklin Mike Pearson 10/30/2006 2.7.1.6
Mike Pearson Larry Franklin
10/30/2006 2.9.1
Mike Pearson Larry Franklin
10/30/2006 2.9.1
Mike Pearson Larry Franklin
10/30/2006 2.9.1.2 Larry Franklin Mike Pearson 10/30/2006 2.9.1 Larry Franklin Mike Pearson 10/30/2006 2.10.1.1
Mike Pearson Larry Franklin
10/31/2006 2.4.1.32.3.10 Larry Franklin Mike Pearson 10/31/2006 2.4.1.33 Larry Franklin Mike Pearson 10/31/2006 2.4.1.34 Larry Franklin Mike Pearson Brief Description of Change
Created New Procedure
Conducted Annual Review
Conduct Annual Review
Added Certification of Calibration and Street Atlas
files
Added “with metal loss”
Added “If ILI vendor does not provide GPS
Coordinates”
Modified to reflect send email to Pipeline Integrity
Data Coordinator
Insert 2.4.1.24 Determine casings that require
rehabilitation based on casing flowchart
Insert 2.4.16 Compare proposed dig list to
information from previous rehabilitation projects
Insert 2.7.1.4 Process casings using ‘Casing
Comparison’ spreadsheet
Delete 2.7.1.5
Minor modification to paragraph, add link to
Rehab book Checklist
2.9.1.1 Insert Receive ‘Casing Comparison’ from
PIDC
Minor modification to 2.9.1.2 to add ‘Casing
Comparison’ comparison
Delete 2.9.1.1.1 through 2.9.1.1.3
Insert 2.9.1.3
Added “if ILI vendor does not provide GPS
coordinates”
Insert 2.4.1.32.3.10
Insert 2.4.1.33
Insert 2.4.1.34

<<<PAGE 1182>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 15 of 18
01/01/08 7/10/08 2.2.1.5 Dennis Vasicek Clyde Clausen 7/10/08 2.2.1.6 Dennis Vasicek Clyde Clausen 7/10/08 2.2.1.7 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.4.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.5 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.12.6 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.18.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.21 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.22 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.30 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.31.3.8 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.31.3.10 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.31.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.1 Dennis Vasicek Clyde Clausen
7/10/08 2.4.1.32.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.3 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.4 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.32.6 Dennis Vasicek Clyde Clausen 7/10/08 2.4.1.33.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.13 Dennis Vasicek Clyde Clausen Reviewed, no changes
Added paragraph and subparagraphs
Added paragraph
Added paragraph
Added paragraph
Added paragraph
Changed 5 years to 6 years
Added paragraph
Added paragraph
Added paragraph
Changed 100% to 80%
Deleted paragraph and sub‐paragraphs pertaining
to sending email to GIS Coordinator to input GPS
information for casings
Deleted paragraph about receiving GPS
coordinators for casings from GIS Coordinator
Added sentence to clarify 60 and 180‐day dates
for HCAs
Added, “(as identified by the ILI vendor as being
axially oriented)”
Removed condition, “A girth weld anomaly as
identified by ILI vendor”
Added paragraph and subparagraphs
Added sentence, “However, all HCA Immediate
Conditions shall take priority.”
Added paragraph and subparagraphs
Added paragraph
Added paragraph and subparagraphs
Added paragraph and subparagraph
Modified paragraph
Modified paragraph and added subparagraphs

<<<PAGE 1183>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 16 of 18
7/10/08 2.4.14.1 Dennis Vasicek Clyde Clausen 7/10/08 2.4.14.2 Dennis Vasicek Clyde Clausen 7/10/08 2.4.15 Dennis Vasicek Clyde Clausen 7/10/08 2.4.16 Dennis Vasicek Clyde Clausen 7/10/08 2.4.17 Dennis Vasicek Clyde Clausen 7/10/08 2.4.23 Dennis Vasicek Clyde Clausen 7/10/08 2.4.24 Dennis Vasicek Clyde Clausen 7/10/08 2.4.25 Dennis Vasicek Clyde Clausen 7/10/08 2.4.26 Dennis Vasicek Clyde Clausen 7/10/08 2.4.30 Dennis Vasicek Clyde Clausen 7/10/08 2.4.31 Dennis Vasicek Clyde Clausen 7/10/08 2.4.31 Dennis Vasicek Clyde Clausen
7/10/08 2.7.1.8 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.9 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.10 Dennis Vasicek Clyde Clausen 7/10/08 2.7.1.11 Dennis Vasicek Clyde Clausen 7/10/08 2.10 Dennis Vasicek Clyde Clausen
7/10/08 2.10 Dennis Vasicek Clyde Clausen
Reworded paragraph
Reworded paragraph
Added paragraph
Added paragraph and subparagraphs
Modified paragraph
Added paragraph
Added paragraph
Added paragraph
Removed Area Facility Integrity Engineer and
added Supervisor Corrosion Control
Added paragraph
Deleted paragraph about Post Job roundtable
Added paragraph and sub‐paragraphs about
calculating the average undersize of repaired
anomalies
Added paragraph
Added paragraph
Added paragraph
Added paragraph
Removed section containing “The GIS Coordinator
shall:”
Added section pertaining to “Pipeline Integrity
Coordinator” and three subparagraphs
7/10/08 2.11 Dennis Vasicek Clyde Clausen
12/19/08 2.4.1.9.2 Dennis Vasicek Clyde Clausen 12/19/08 2.4.14.2 Dennis Vasicek Clyde Clausen Added section pertaining to “Supervisor Pipeline
Integrity or Manager Pipeline Integrity” and four
subparagraphs
Removed reference to LAPA RPR’s
Added reference to UT ILI
12/19/08 2.4.14.2.1 Dennis Vasicek Clyde Clausen 12/22/08 Global Dennis Vasicek Clyde Clausen 12/22/08 2.4.1.31.4 Dennis Vasicek Clyde Clausen Added, “and match girth welds between the
reports”
Changed “vendor” to “service provider”
Deleted section referencing expired Consent

<<<PAGE 1184>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 17 of 18
12/22/08 2.4.1.32.6 Dennis Vasicek Clyde Clausen
12/22/08 Dennis Vasicek Clyde Clausen 3/4/09 All Dennis Vasicek Clyde Clausen
01/01/10 2.2.1.1 all All
2.4.1.8 (Old) 2.4.1.8 (new) 2.4.1.12.3 2.4.1.12.4 2.4.1.12.5/2.4.1.13/
2.4.1.14/2.4.1.16
2.4.1.21 – 2.4.1.24 2.4.1.25‐2.4.1.30 60‐day repair
cond/180 day/ Non
HCAS
2.4.14.1 – 2.4.14.2.4 2.4.15/2.4.20‐2.4.22 01/01/11 9/1/11 All Clyde Clausen Doug Chabino 12/31/11 all
12/31/11 All 6/18/12 10.2.5 Clyde Clausen Doug Chabino
Decree (for acquired Shell assets)
Deleted section referencing expired Consent
Decree (for acquired Shell assets)
Conducted annual review
Added references to consent decree – not a
significant change so version not updated
Added “internal diameter”
Changed Longhorn to Mitigation Plan
General cleanup/updating to reflect current
process
Deleted: ref – Pipeline Listing ss
Reworded DPP information
Added “add to DPP ss.
Added – create Run Comparison ss
deleted
Deleted
Moved after dig list
Dents at 4/8 o’clock changed to top‐side dents/
bottom side dents
Deleted
Deleted
Reviewed, no changes
Re‐worked and Re‐formatted entire
document
Replaced Rehab Book Checklist with
Project File Index Form and AGM Calc
Spreadsheet with Total AGMs Form
2012 Annual Review complete
Added Laminations interacting with
deformations to section 10.2.5

<<<PAGE 1185>>>

Magellan Midstream Partners, L.P.
IN‐LINE INSPECTION ANALYSIS GUIDELINES 7.03–ADM–007
Asset Integrity 01/01/12 Revision: 4 Page 18 of 18

<<<PAGE 1186>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 1 of 29
TABLE OF CONTENTS
1.0 SCOPE
2.0 EXTERNAL CORROSION CONTROL
2.1 External Coating
2.2 Cathodic Protection
2.3 Corrosion Control Criteria
2.4 IR Drop Consideration
2.5 New Construction
2.6 Cathodic Protection Surveys
2.7 Cathodic Protection Rectifiers
2.8 Foreign Crossings and Interference Currents
2.9 Electrical Isolation
2.10 Test Leads
2.11 Exposed Pipe Examination
2.12 Stress Corrosion Cracking Analysis
2.13 Microbiological Influenced Corrosion (MIC)
2.14 Induced AC Corrosion
3.0 ATMOSPHERIC CORROSION CONTROL
3.1 Inspection
3.2 Paint/Coating
4.0 INTERNAL CORROSION CONTROL
4.1 Introduction
4.2 Product Evaluation
4.3 Internal Corrosion Mitigation
4.4 Internal Corrosion Monitoring
4.5 Internal Examination

<<<PAGE 1187>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 2 of 29
5.0 QUALIFICATION
5.1 Supervisor
5.2 Operator Qualification
6.0 CORROSION CONTROL RECORDS
7.0 INTEGRITY MANAGEMENT PLAN INTEGRATION
8.0 DEFICIENCIES IN CORROSION CONTROL

<<<PAGE 1188>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 3 of 29
1.0 SCOPE
1.1 This program is applicable to federal and/or state jurisdictional pipelines and/or
facilities. Elements of this program may be used in whole or part on non‐jurisdictional
assets as deemed appropriate.
1.2 Texas Specific: In addition to applicable Federal, State, and Local regulations, as well as,
Magellan guidelines, process, or best practices, certain pipeline system assets in Texas
operate under the requirements of the Mitigation Plan.
2.0 EXTERNAL CORROSION CONTROL
2.1 External Coating 195.557, 195.559, 195.561, 16 TAC 8.305(2‐3), 192.455(a)(1) and
192.461.
2.1.1 2.1.2 2.1.3 2.1.4 2.1.5 2.1.6 2.1.7 2.1.8 All buried or submerged newly constructed, relocated, replaced or otherwise
changed steel lines shall be coated, including mainlines, terminal and station
piping.
The external coating shall be applied on a properly prepared surface and have
sufficient adhesion to the metal surface to effectively resist underfilm
migration of moisture.
The coating shall be sufficiently ductile to resist cracking and have sufficient
strength to resist damage due to handling and soil stress.
The coating shall have properties compatible with the cathodic protection
system.
Electrically insulating type coatings shall have low moisture absorption and
high electrical resistance.
The coated pipe shall be electrically inspected using a coating deficiency
(holiday) detector prior to installation. Any damage found that impairs the
effectiveness of the coating shall be repaired. Furthermore, the coating shall
be protected from damage resulting from adverse ditch conditions or damage
from supporting blocks.
Backfilling operations will be inspected to ensure that rocks, hard lumps of
earth, etc. are not backfilled directly onto the pipe where they may damage
the effectiveness of the pipeline coating.
Precautions will be taken to minimize damage to the coating during
installation if coated pipe is installed by boring, driving, or other similar
method.

<<<PAGE 1189>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 4 of 29
2.2 2.1.9 Joints, fittings, and tie‐ins shall be coated with material(s) compatible with the
coating(s) on the pipe.
2.1.10 Coatings selection, application, and maintenance shall be performed as
prescribed in Coatings – Selection, Applications, and Maintenance.
Cathodic Protection – 195.563, 195.565, 192.452, 192.453, 192.455 and 192.457
2.2.1 2.2.2 2.2.3 2.2.4 On facilities including newly constructed, relocated, replaced or otherwise
changed pipelines, a cathodic protection system will be installed to mitigate
corrosion.
A cathodic protection system will be installed for breakout tanks to mitigate
corrosion. The systems shall be installed in accordance with API
Recommended Practice 651, unless noted in this volume why compliance with
all or certain provisions of API Recommended Practice 651 is not necessary for
the safety of the breakout tank. Noted conditions that will cause compliance
with 651 to not be observed may be but are not limited to tanks set on
concrete, asphalt pads, or where studies conducted in accordance with API
653 indicate that corrosion will not affect the safe operation of the tank.
On facilities including newly constructed, relocated, replaced, or otherwise
changed pipelines and tanks, a temporary cathodic system shall be provided
as soon as practical during construction and a permanent cathodic protection
system shall be provided within one year of completed construction.
Refer to Design and Installation of an Impressed Current Deep Groundbed and
Design and Installation of an Impressed Current Surface Groundbed for more
2.3 information.
2.2.5 Soil Resistivity may influence the design considerations for cathodic
protection systems as well as development of the Relative Risk Score for the
line segment. See Soil Resistivity Overview for a general description of
expected soil resistivity identified by state.
Corrosion Control Criteria 195.571, 192.463
2.3.1 Magellan adheres to the cathodic protection regulations in Part 195,
“Transportation of Hazardous Liquids by Pipeline” and to the cathodic
protection regulations in Part 192, “Transportation of Natural and Other Gas
by ”pipeline: Minimum Federal Safety Standards,” of the DOT/Pipeline and
Hazardous Materials Safety Administration Pipeline Safety Regulations.
2.3.2 When practical, Magellan requires maintaining a polarized potential of at least
–0.850 volts as measured between the structure surface and a saturated

<<<PAGE 1190>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 5 of 29
2.4 2.3.3 2.3.4 2.3.5 2.3.6 2.3.7 copper‐copper sulfate reference electrode that is in contact with the
electrolyte (earth, soil, water, etc.). Where injurious aerobic bacteria has been
identified, or is suspected, a polarized potential of ‐.950 volts or more
negative is required. This voltage measurement shall be determined with the
protective current applied and IR drop considered as described in paragraph
2.4 below.
Assets covered by the Mitigation Plan: For Tier II and Tier III areas, where
practical a polarized pipe‐to‐soil potential of ‐.850 volts will be maintained.
During close interval surveys, potential drops other than those across the
structure to electrolyte boundary will be considered by interrupting the
cathodic protection current source(s) and recording the ON” and “OFF” pipe‐
to‐soil potentials Once established, the “ON” potential and “Off” potential will
be utilized to correct future pipe‐to‐soil potential readings until such time as
the system configuration or coating condition changes, or a new close interval
survey is performed.
When a ‐0.850 volt potential is not practical, the following criteria are
acceptable when approved by the Supervisor of Corrosion Control:
2.3.4.1 A minimum negative (cathodic) polarization shift of 100 millivolts
The 100‐millivolt polarization decay criteria specify a minimum negative
(cathodic) polarization voltage shift of 100 millivolts, measured between the
structure surface and a reference electrode contacting the electrolyte.
Overprotection will be monitored and minimized through the analysis of data
from annual pipe‐to‐soil surveys, close interval surveys, and pipeline visual
inspections. A practical value of ‐1.2 volts (polarized) in reference to a
copper/copper sulfate electrode will be used as value beyond which
monitoring for overprotection shall be considered.
Refer to Cathodic Protection Criteria for more information.
IR Drop Consideration 195.571 and 192.463 (a)
2.4.1 IR drop is considered by taking potential readings directly over or as near as
practical to the structure surface. The affect on the potential measuring circuit
is kept to a minimum by using a high resistance voltmeter and being mindful
of lead lengths and condition, contact to structure and contact to electrolyte.
2.4.2 Cathodic protection level should be evaluated utilizing Cathodic Protection
Criteria.
2.5 New Construction 195.563 and 192.455(a)(2)

<<<PAGE 1191>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 6 of 29
2.6 2.5.1 On newly constructed facilities and/or pipelines, a temporary cathodic system
shall be provided as soon as practical during construction and a permanent
cathodic protection system shall be provided within one year of completed
construction.
2.5.2 Newly constructed facilities shall be included in and be managed in
accordance with the Magellan System Integrity Plan within one year of
completed construction.
2.5.3 On newly constructed facilities and/or pipelines, corrosion personnel,
qualified under the Operator Qualification Ruling or with NACE Certification,
shall be utilized to identify, mitigate, and monitor for inadequate cathodic
protection and detrimental interference currents, prior to and during
construction. Refer to Section 2.8, Foreign Crossings and Interference
Currents and 2.14, Induced AC Corrosion below.
Cathodic Protection Surveys 195.573 (a) (d) and 192.465
2.6.1 A cathodic protection survey shall be conducted on each buried, in contact
with the ground, submerged pipeline facility, and/or breakout tank in its
pipeline system that is under cathodic protection once each calendar year
with intervals not to exceed fifteen months. Pertinent survey information shall
be recorded in the Cathodic Protection Data Manager (CPDM) within 30 days
after the survey.
2.6.2 Assets covered by the Mitigation Plan: Pipe‐to‐soil surveys shall be performed
annually not to exceed 15 months in Tier I areas and semi‐annually not to
exceed 7.5 months in Tier II and Tier III areas. Deficiencies will be resolved
within one (1) year of discovery, except deficiencies of such a nature they
present a more urgent threat to pipeline integrity, in which case corrections
will be done immediately.
2.6.3 Pipe‐to‐soil readings shall be obtained at pre‐assigned locations identified as
necessary to determine the adequacy of cathodic protection. These locations
can include, but are not limited to, test stations, cased crossings, and above
ground appurtenances. Refer to Measuring a Pipe‐to‐Soil Potential for more
information.
2.6.4 For aboveground breakout tanks where corrosion of the tank bottom is
controlled by a cathodic protection system, the cathodic protection system
shall be inspected to ensure it is operated and maintained in accordance with
API Recommended Practice 651, unless noted in this volume why compliance
with all or certain provisions of API 651 is not necessary for the safety of a

<<<PAGE 1192>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 7 of 29
2.6.5 2.6.6 particular breakout tank. Noted conditions that will cause compliance with
651 to not be observed may be but are not limited to tanks set on concrete,
asphalt pads, or where studies conducted in accordance with API 653 indicate
that corrosion will not affect the safe operation of the tank. Pertinent survey
information shall be recorded in the Cathodic Protection Data Manager
(CPDM) within 30 days after the survey.
2.6.4.1 Potential surveys taken on above‐ground storage tanks should be
conducted with an adequate level in the tank to maximize the
contact of the tank bottom with the cushion material. Adequate
level is typically at least 3 feet of liquid. Tank levels shall be
recorded along with potential measurements. Tanks with
inadequate levels shall be re‐surveyed the same calendar year, once
adequate levels are attained.
Additional corrosion control surveys, including but not limited to close interval
pipe‐to‐soil surveys, will be conducted where practical and determined
necessary by sound engineering practices. Indicators of the necessity to
conduct such surveys shall include risk assessments, annual pipe‐to‐soil
surveys, internal inspection data, pipe inspection, or other related corrosion
information or testing.
At a minimum, close interval pipe‐to‐soil surveys will be considered under the
following circumstances:
2.6.6.1 When identified through risk assessment including Section 6
analysis required by the Integrity Management Plan.
2.6.6.2 Assets covered by the Mitigation Plan: Close Interval surveys in Tier
III areas will be conducted annually not to exceed 15 months. For
Tier I and II areas close interval surveys will be managed through the
Relative Risk Assessment Process within the System Integrity Model
and conducted as necessary. Deficiencies will be resolved within
one (1) year of discovery, except deficiencies of such a nature they
present a more urgent threat to pipeline integrity, in which case
corrections will be done immediately.
2.6.6.3 External Corrosion identified on the pipeline with a peak depth
greater than 50% of the nominal wall, within 50 feet of a foreign
pipeline crossing. Close interval survey may not be required if pipe‐
to‐soil data collected at the location indicates that cathodic
protection interference is not a concern.

<<<PAGE 1193>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 8 of 29
2.6.6.4 2.6.6.5 2.6.6.6 Areas of inadequate cathodic protection as identified by pipe‐to‐soil
surveys. Close interval survey may not be required if remediation of
the low potentials includes the addition, modification, or
adjustment of an impressed current cathodic protection that
provides cathodic protection current beyond the area of inadequate
potentials.
Areas of interference from a foreign cathodic protection current
source. Locations of potential interference include but are not
limited to, construction of new cathodic protection systems near
the pipeline, changes in current output from foreign cathodic
protection systems, and a reduction in cathodic protection levels
without a corresponding reduction in output from the existing
cathodic protection system.
In each case, the Close Interval Survey shall be conducted at spacing
close enough to identify potential integrity threats and extend
beyond the area of likely influence. Refer to Close Interval Pipe‐to‐
Soil Survey and Testing for Interference Currents and Remedial
Measures for more information.
2.7 Cathodic Protection Rectifiers 195.573 (c) and 192.465 (b)
2.7.1 Each cathodic protection rectifier shall be inspected for proper operation at
least six times each calendar year with intervals between inspections not to
exceed 2 ½ months. Pertinent survey information shall be recorded in the
Cathodic Protection Data Manager (CPDM) within 30 days after survey. Refer
to Rectifier Inspection, Cathodic Protection System Troubleshooting
(Groundbed), and Rectifier Troubleshooting for more information.
2.8 2.7.2 Assets covered by the Mitigation Plan: Each cathodic protection rectifier shall
be inspected for proper operation at least twelve (12) times each calendar
year with intervals between inspections not to exceed 45 days. Deficiencies
will be resolved within one (1) month of discovery, except deficiencies of such
a nature they present a more urgent threat to pipeline integrity, in which case
corrections will be done immediately.
Foreign Crossings and Interference Currents 195.573(c), 195.577, 16 TAC 7.86(5)(c),
192.465 (c) and 192.473
2.8.1 During each cathodic survey, a check of the integrity of each bond that exists
across insulating flanges or other unions of pipeline facilities and each
interference bond shall be made. Reverse current switches, diodes and

<<<PAGE 1194>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 9 of 29
interference bonds whose failure would jeopardize structure protection shall
be inspected six times each calendar year with intervals between inspections
not to exceed 2 ½ months. Pertinent survey information shall be recorded in
the Cathodic Protection Data Manager (CPDM) within 30 days after the
survey. Refer to Electrical Bond Inspection for more information.
2.8.2 2.8.3 Impressed current cathodic protection systems or galvanic anode systems will
be designed and installed to minimize any adverse effects on existing
underground metallic structures.
Stray current interference testing, including, but not limited to close interval
pipe‐to‐soil surveys, will be conducted where practical and determined
necessary by sound engineering practices. Indicators of the necessity to
conduct such tests shall include annual pipe‐to‐soil surveys, internal
inspection data, pipe inspection, or other related corrosion information or
testing. Pertinent survey information shall be recorded on Magellan Foreign
Line Interference Test Form. Refer to Testing for Interference Currents and
Remedial Measures for more information.
2.9 2.8.4 Texas Intrastate Pipeline specific: Whenever suspected areas of interference
are identified, testing will be conducted within 6 months to determine the
extent of interference, and appropriate action will be taken.
2.8.5 For Interference Currents related to Induced AC refer to Section 2.14, Induced
AC Corrosion below.
Electrical Isolation 195.575 and 192.467
2.9.1 Each buried or submerged pipeline shall be electrically isolated from other
underground metallic structures, unless the pipeline and the other structures
are electrically interconnected and cathodically protected as a single unit.
2.9.2 One or more insulating devices shall be installed where electrical isolation of a
portion of a pipeline is necessary to facilitate the application of corrosion
control.
2.9.3 During each cathodic survey, a check of the integrity of insulating flanges or
other unions of pipeline facilities shall be made if inadequate cathodic
protection levels are found.
2.9.4 Shorted Casings
2.9.4.1 During each cathodic protection survey, readings may be taken at
each cased crossing to detect any location where the carrier pipe
may be shorted to the casing pipe.

<<<PAGE 1195>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 10 of 29
2.9.4.2 2.9.4.3 If the casing potential is greater than ‐.800 volts, the casing shall be
tested to determine whether an electrolytic short to the carrier pipe
is present. Corresponding classification data documenting the status
of the casing shall be recorded in the Cathodic Protection Data
Manager (CPDM). Refer to Shorted Casing Testing for more
information.
If the casing potential is within 100 millivolts of the pipeline
potential, the casing shall be tested to determine whether a short to
the carrier pipe is present. Corresponding classification data
documenting the status of the casing shall be recorded in the
Cathodic Protection Data Manager (CPDM). Refer to Shorted Casing
Testing for more information.
2.9.4.4 Following internal inspection of a pipeline, the resulting smart pig
data will be integrated with and compared to the casing information
in the corrosion control database. Where the carrier pipe within the
casing exhibits corrosion‐caused metal loss, a risk evaluation will be
conducted and action will be taken to mitigate the corrosion if
deemed necessary.
NOTE: For line sections integrity tested by hydrostatic test, a risk
evaluation will be conducted at each shorted casing and action
taken to clear the short and/or mitigate the corrosion if deemed
necessary.
2.9.4.5 2.9.4.6 Assets covered by the Mitigation Plan: If a shorted casing is verified,
a plan of action shall be developed within three (3) months from the
time of discovery. The practicality of clearing the short will be
considered before any other measures are used. Action shall be
taken to clear the short (a) in Tier I areas within six (6) months of
development of the action plan; and (b) in Tier II and III areas within
three (3) months of development of the action plan.
If clearing the short is impractical, the location can be monitored for
leaks, or the casing/pipe interstice may be filled with a high
dielectric corrosion inhibiting material. If the casing is monitored
using leak detection equipment, the test must be performed twice
each calendar year not exceeding 7.5 months. If monitored using
internal inspection (smart pig) equipment, the inspection must be
made at intervals as determined in the Magellan, Integrity
Management Plan. These alternative measures, or any other

<<<PAGE 1196>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 11 of 29
2.10 measures approved by the Manager of Asset Integrity may be
employed until it is practical to clear the short.
2.9.4.7 Assets covered by the Mitigation Plan: In the interim, from the time,
a short is verified and action is taken to clear the short, the location
will be inspected for corrosion or the casing /pipe interstice may be
filled with a high dielectric corrosion inhibiting material. During any
interval that a casing has been determined to be shorted, casing will
be monitored. Tier I areas will be monitored twice per year at
intervals not exceeding 7.5 months. Tier II and III areas will be
monitored monthly at intervals not exceeding 6 weeks.
2.9.5 Insulating devices installed in areas where a combustible atmosphere is
reasonable to foresee shall be installed with precautions to prevent arcing.
2.9.6 Pipelines in close proximity to electrical transmission tower footings, ground
cables, or counterpoise, or in other areas where it is reasonable to foresee
fault currents or an unusual risk of lightning, shall be protected against
damage from fault currents or lightening and protective measures taken at
insulating devices.
Test Leads 195.567, 192.469 and 192.471
2.10.1 All cathodically protected pipelines and breakout tankage shall have a
sufficient number of test stations or other locations for electrical
measurement to determine the adequacy of the cathodic protection system.
2.10.2 For design purposes, test lead spacing on pipelines shall be approximately one
mile. This spacing shall be affected by conditions along the pipeline.
2.10.3 Breakout tankage will be monitored at the four quadrants.
2.10.4 The test leads shall be connected directly to the structure by Thermit welding
or other process, which prevents stress concentration on the pipe and is
approved by the Supervisor of Pipeline Integrity.
2.10.5 Test leads shall be maintained so that electrical measurements can be
obtained in order to ensure adequate protection. For locations where repair
of the test station is impractical, and a reading is necessary to determine the
adequacy of cathodic protecting, an insulated probe rod may be used to
contact the pipe and obtain the reading. This measure may be utilized until
which time the test lead is repaired.
2.10.6 During installation, test leads shall be installed with enough looping or slack to
prevent the test leads from undue stress or breakage during backfilling. Test

<<<PAGE 1197>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 12 of 29
leads installed in conduit shall be suitably insulated from the conduit. Refer to
Attaching Cathodic Protection Test Leads for more information.
2.11 2.10.7 Bared test lead wire and bared metallic area at the point of connection to
pipeline must be coated with an electrical insulation material compatible with
the pipe coating and the insulation on the wire.
Exposed Pipeline Examination 195.569 and 192.459
2.11.1 When any buried pipeline is exposed, either intentionally or unintentionally,
the exposed portion shall be visually inspected for evidence of external
corrosion. Refer to Examining and Documenting the Condition of an
Underground Pipeline or Related Facility When Exposed for more information.
2.11.2 When external corrosion requiring remedial action is found, further
investigation will be conducted, circumferentially and longitudinally beyond
the exposed portion (by visual examination, indirect method, or both) to
determine the extent of the corrosion in the vicinity of the exposed portion.
Refer to Pipeline Defect Evaluation and Repair for more information.
2.11.3 If the extent of corrosion cannot be determined, plans and scheduling for
further investigation or the use of an internal inspection device shall be
developed based on the severity of the corrosion encountered.
2.11.4 If the exposed pipe is to remain exposed, proper pipeline markers shall be
installed and the pipe shall be monitored for atmospheric corrosion in
accordance with paragraph 3.1.1 below.
2.12 Stress Corrosion Cracking (SCC)
2.12.1 Basic SCC awareness information is available to operation and maintenance
employees in Stress Corrosion Cracking Information.
2.12.2 The risks associated with SCC are identified and assessed per the Magellan
Risk Assessment Methodology book, and include factors such as age of the
2.12.3 2.12.4 pipeline, coating type, operating stress level, proximity of pump stations and
history of SCC.
In the event that a pipeline system has experienced one or more confirmed
incidents of SCC a systematic identification and examination of other potential
locations of SCC will be conducted based upon the observations of conditions
associated with the confirmed SCC incident.
Areas of the pipeline identified as having high susceptibility to SCC, or any
other locations identified for SCC investigation, will be investigated per Stress
Corrosion Cracking Investigation.

<<<PAGE 1198>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 13 of 29
2.12.5 2.12.6 Pipe cutouts sent to a metallurgical lab for analysis will be investigated for
SCC. Results of this analysis will be provided in a comprehensive report
provided to Asset Integrity.
SCC field examinations will be performed by a NDE Technician trained in the
detection of SCC on buried pipelines and will be documented in the Pipeline
Maintenance Report.
2.12.7 If SCC is determined to be present, a review of the pipeline as defined in
Section 6 of the IMP will be conducted, to be followed by a re‐assessment
interval recommendation per Section 7 of the IMP.
2.12.8 Annually, confirmed SCC occurrences will be reviewed to determine if changes
to the SCC assessment criteria are necessary.
2.13 Microbiological Influenced Corrosion (MIC)
2.13.1 In the event that a pipeline system has experienced one or more confirmed
discoveries of injurious MIC, or where accelerated corrosion from MIC is
anticipated, a Bacteria Testing Protocol shall be established to evaluate future
2.13.2 2.13.3 integrity threats from MIC.
The line specific protocol shall be utilized until such time that the threat from
MIC has been assessed and appropriate mitigation actions have been taken.
Testing for MIC shall be conducted in accordance with Bacteria Testing – Serial
Dilution Method.
2.14 Induced AC Corrosion 195.577 192.473
2.14.1 AC potential surveys shall be conducted on each buried, in contact with the
ground, submerged pipeline facility near high voltage power lines once each
calendar year with intervals not to exceed fifteen months. Recording
voltmeters should be considered in areas where high voltage transmission
lines parallel the pipeline over long distances. Pertinent survey information
shall be recorded in the Cathodic Protection Data Manager (CPDM) within 30
days after the survey. Refer to Testing for Induced AC and Remedial Measures
for more information.
2.14.2 AC potentials greater than 5 volts will be evaluated to determine if additional
testing or remedial actions are required. Refer to Testing for Induced AC and
Remedial Measures for more information.

<<<PAGE 1199>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 14 of 29
2.14.3 Remedial actions are required where through testing or calculations, AC
current discharge densities are found to be at or greater than 100 A/m2 or AC
potentials are greater than 15 volts. Remedial action may be required where
AC current discharge densities range from 20‐100 A/m2. Refer to Testing for
Induced AC and Remedial Measures for more information.
3.0 ATMOSPHERIC CORROSION CONTROL
3.1 Inspection 195.581, 195.583, 192.479 and 192.481, and 16 TAC 8.305(1)
3.1.1 Facilities and/or pipelines, other than Breakout Tanks, shall be inspected at
least once every three (3) calendar years with intervals not exceeding 39
months for onshore and at least once each calendar year, with intervals not
exceeding 15 months, for offshore. Refer to Atmospheric Corrosion
Inspections for more information.
NOTE: Atmospheric corrosion inspections on exposed pipelines must be
conducted visually.
3.1.2 Assets covered by the Mitigation Plan: Facilities and/or pipelines, other than
Breakout Tanks, shall be inspected annually for atmospheric corrosion. Refer
to Atmospheric Corrosion Inspections for more information.
3.1.3 Breakout Tanks shall be inspected at least once every five (5) years with
intervals not exceeding 60 months. Refer to Atmospheric Corrosion
Inspections for more information.
3.2 3.1.4 Assets covered by the Mitigation Plan: Corrective action for deficiencies found
during atmospheric surveys shall be determined and completed as soon as
practical. Deficiencies will be resolved within one (1) year of discovery, except
deficiencies of such a nature they present a more urgent threat to pipeline
integrity, in which case corrections will be done immediately.
Coating 195.581, 195.583, 192.479 and 192.481
3.2.1 A suitable coating shall be applied to all new aboveground facilities to prevent
atmospheric corrosion damage. Refer to Coatings – Selection, Applications,
and Maintenance for more information.
3.2.2 A suitable coating shall be applied to all soil‐to‐air interface areas to prevent
atmospheric and electrolytic corrosion damage. Refer to Coatings – Selection,
Applications, and Maintenance for more information.
3.2.3 A suitable coating shall be applied to all aboveground facilities to prevent
further atmospheric corrosion damage if, through the guidelines established

<<<PAGE 1200>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 15 of 29
in the Atmospheric Inspection Procedure, a Rust Rating of 2‐G or worse is
identified. Refer to Coatings – Selection, Applications, and Maintenance for
more information.
3.2.4 The coating conditions on exposed assets shall be documented in the
Atmospheric Corrosion database (CPDM).
4.0 INTERNAL CORROSION CONTROL
4.1 Introduction 195.579 and 192.477
4.1.1 The corrosive effects of pipeline cargoes (hazardous liquids or carbon dioxide)
shall be investigated and if found to be corrosive, adequate steps shall be
taken to mitigate internal corrosion. If steps are taken to mitigate corrosion,
the effectiveness of the steps shall be monitored using corrosion coupons
and/or other methods.
4.1.2 Circumstance or condition [such as those listed below] that could cause,
promote, or increase the likelihood of internal corrosion should be promptly
reviewed and internal corrosion mitigation plans implemented as appropriate.
4.1.2.1 Type of commodity
4.1.2.2 Flow rate
4.1.2.3 Velocity
4.1.2.4 Operating Pressure
4.1.2.5 Topography
4.1.2.6 Amount of foreign material and/or contaminants present in the
pipeline and/or commodity stream such as sand, silt, water, or
other materials that could cause or promote internal corrosion
4.1.2.7 Amount of sulfur, salts, acids, hydrogen sulfide, carbon dioxide or
other corrosive material present and corrosive effect based upon
partial pressures of material in the pipeline
4.1.2.8 Presence of microbes
4.1.2.9 Temperature
4.1.2.10 Pipe configuration, design, and material specifications

<<<PAGE 1201>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 16 of 29
4.1.2.11 Operating conditions, including but not limited to, steady state
conditions, slack line conditions, upset conditions in the pipeline
system, and upset conditions in upstream facilities such as refineries
or processing facilities
4.2 Product Evaluation
4.2.1 Crude Oil or natural gas containing water in the liquid phase, solids, and other
corrosive constituents such as bacteria, H2S, CO2 and O2, are considered
potentially corrosive.
4.2.2 Refined Petroleum Products are evaluated using NACE TM 0172‐2001,
“Determining Corrosive Properties of Cargoes in Petroleum Product
Pipelines”. Petroleum products are considered "corrosive" if they do not meet
at least a "C" rating on this test. Assets covered by the Mitigation Plan have a
target NACE rating of “A”
4.2.3 Natural Gas Liquids are evaluated using ASTM D 1838, "Standard Test Method
for Copper Strip Corrosion by Liquefied Petroleum Gases.” Natural gas liquids
are considered "corrosive" if they fail to meet the Number 1 classification on
this test.
4.2.4 Free water in any product is potentially corrosive
4.2.4.1 Refer to Bacteria Testing – Serial Dilution Method for more
information.
4.3 Internal Corrosion Mitigation
4.3.1 Adequate steps, including eliminating the possibility of free water, removing
corrosive components, or injecting corrosion inhibitor will be taken whenever
investigation of the corrosive effect of the product on the metal indicates it is
necessary.
4.3.2 Cleaning pigs
4.3.2.1 procedures as required.
4.3.2.2 To reduce the potential for unnecessary shut downs and/or
unmanageable product contamination, pipelines with no history of
pigging or those with significant amounts of known debris should
not be pigged until adequate precautions and/or contingency plans
have been developed.
Pipeline cleaning pigs should be utilized system wide on mainline
piping. Refer to Perform Pigging Operations or location specific

<<<PAGE 1202>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 17 of 29
4.3.2.3 4.3.2.4 4.3.2.5 4.3.2.6 4.3.2.7 4.3.2.8 The frequency for routine cleaning operations of mainline product
piping should be 2 times per year, approximately every 6 months.
The frequency for routine cleaning operations of mainline crude
piping should be 26 times per year, approximately every two weeks.
Frequencies of cleaning pig runs may be adjusted as necessary
based upon product upsets and the analysis of results of previous
cleaning pig runs. Cleaning of facility piping, pipelines without
launching or receiving equipment, and/or other non‐piggable
sections should be conducted as required on a case by case basis.
Pipelines transporting NH3 do not require routine pigging, but
should be cleaned if excessive debris is identified prior to In‐line
inspection tool runs.
Pipeline pigging or repigging operations should also be considered
when excessive debris is identified in the pipeline, following
transportation of a corrosive (off spec) product, in preparation for
integrity testing with a in‐line inspection tool, following hydrostatic
testing of a pipeline, etc.
Although the presence of debris in the receiving scraper trap does
not necessarily indicate the quantity of material removed from the
pipeline, it should be taken into consideration when determining
the frequency of the cleaning pig operations. The physical condition
of the pigs should also be taken into consideration, as a badly worn
pig may be the result of excessive pipeline debris.
During normal cleaning operations, a combination cup and brush
pig (1st pig) followed, as soon as practical, by a combination cup and
disc pig (2nd pig) should be utilized.
Where excessive debris and paraffin buildup is thought to exist,
specialty pigs such as pin‐wheel, Pit Boss™, scraper/plow blade
attachments, and magnetic cleaning pigs shall be utilized as
necessary based upon sound engineering judgment.
Significant separation between the multiple pigs is not required and
separation by more than a few yards will actually decrease the
effectiveness of the operation.
Cleaning pigs should be maintained in accordance with the
manufactures recommendations. Pigs worn beyond the
manufactures recommend tolerance should not be used.

<<<PAGE 1203>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 18 of 29
4.3.2.9 If a pig is to be run in a line which has not been pigged in many
years or in a line which is suspected to be un‐piggable, soft low
density Polly Pigs should be utilized until confidence is achieved that
normal cleaning pigs will successfully traverse the pipeline. Specialty
pigs with tracking devices may also be warranted if there is concern
that the pigs may become stuck in the pipeline.
4.3.2.10 Normal cleaning operations should be conducted at a continuous 3
ft/sec or less where practical.
4.3.2.11 Caution should be observed when pigging lines that start and stop.
Debris may fall out in front of the pig causing the pig to become
stuck.
4.3.3 Corrosion Inhibitor
4.3.3.1 When a corrosion inhibitor is used to mitigate internal corrosion, a
sufficient quantity to protect the entire part of the system the
inhibitor is designed to protect will be used. Initial inhibitor injection
rates will be based on product characteristics of the product to be
inhibited .For refined product systems a hydrocarbon soluble, water
dispersible corrosion inhibitor shall be utilized (Smart Chemical
SCSF260 or equivalent). For crude pipeline systems, a highly water
dispersible/soluble blend of corrosion inhibitors shall be utilized
(Smart Chemical SCCI865 or equivalent).
4.3.3.2 Assets covered by the Mitigation Plan: Inhibitors are required to
control potential internal corrosion.
NOTE: Whenever a corrosion inhibitor injection pump, internal coating, or
other equipment to mitigate internal corrosion, is installed or removed a
Pipeline Maintenance Report shall be completed.
4.3.4 When installing a tank bottom lining in an aboveground breakout tank, the
lining shall be installed in accordance with API Recommended Practice 652
unless noted in this volume why compliance with all or certain provisions of
API Recommended Practice 652 is not necessary for the safety of the tank.
4.4 Internal Corrosion Monitoring
4.4.1 When corrosion inhibitors are used to mitigate internal corrosion, coupons or
other types of monitoring will be used to determine the effectiveness of the
inhibitor and the potential extent of any corrosion. Refer to Coupon Handling
and ER Probes for more information

<<<PAGE 1204>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 19 of 29
NOTE: Whenever new coupon holding devices or ER Probes are installed, a
Pipeline Maintenance Report shall be completed.
4.4.2 4.4.3 4.4.4 At least twice each calendar year, and not exceeding intervals of 7 ½ months,
corrosion coupons shall be removed from the test locations and forwarded to
an appropriate laboratory for corrosion analysis (Reference NACE RPO775 for
more information).
Assets covered by the Mitigation Plan: At least three times each calendar
year, and not exceeding intervals of 4.5 months, corrosion coupons shall be
removed from the test locations and forwarded to an appropriate laboratory
for corrosion analysis.
New corrosion coupons will be installed at this time. Any alternate or
supporting corrosion monitoring methods will be accomplished at the same
minimum frequency. Pertinent monitoring data shall be documented in the
Internal Corrosion Database and/or the appropriate inspection forms. Refer to
Coupon Handling and ER Probes for more information.
NOTE: There may be instances in which a product is not corrosive, and
therefore not inhibited. Corrosion coupons may be used to periodically
evaluate these products. In these instances, coupon monitoring may be less
frequent than twice per calendar year and 7 ½ month intervals.
4.4.5 4.4.6 4.4.7 Effectiveness of inhibitor will be based on the inhibitor’s success in reducing
the internal corrosion rate to an acceptable level. This level of acceptability
may be different for each pipeline, but is typically <1 MPY for refined products
and <3 MPY for crude. General corrosion rates can be classified as Low<1
mpy, Moderate 1.0 – 4.9 mpy. Sever >10 mpy.
Internal corrosion rates greater than >1 MPY (refined products) or >3 MPY
(crude) on inhibited pipelines shall be followed up with a detailed analysis
regarding injection rates, hydro‐tests, or other unusual activities or
circumstances. Action plans shall be developed if deemed necessary using
sound engineering judgment.
Assets covered by the Mitigation Plan: Coupon corrosion rates over 1 mpy of
general corrosion or pitting (including MIC) will trigger a detailed analysis
directed by NACE certified corrosion control personnel. This analysis will
include a review of incoming product quality sample data, inhibitor injection
rates, bacteria testing and, if necessary, inhibitor performance testing.
Deficiencies will be resolved within six (6) months of discovery, except

<<<PAGE 1205>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 20 of 29
4.5 4.4.8 4.4.9 deficiencies of such a nature they present a more urgent threat to pipeline
integrity, in which case corrections will be done immediately.
For crude pipeline systems, water sample traps will be mounted on the
bottom of the pipe to facilitate the collection and analysis of free water. These
locations will be inspected for water monthly and if a sufficient amount of
water is present (typically >1 pint) this water shall be analyzed for bacteria,
pH, iron, manganese, chlorides, and inhibitor residual (Reference API RP‐45,
NACE TM0194, NACE RP0192, and ASTM D2327 for more information).
Bacteria counts in excess of 10‐100 colonies/ml., pH readings outside a range
of 4‐8, inhibitor residual less than ~10ppm, or an increase in iron, manganese,
or chlorides could indicate an increase threat to internal corrosion. Water and
debris brought into receiving traps during pigging operations will be tested to
determine its potential to cause internal corrosion if determined to be
necessary after consultation with the Corrosion Specialist.
Crude assets covered by the Mitigation Plan: Coupon/water sample collection
points will be located in facilities at origination points, along the pipeline
system, and end points. Locations chosen for initial sampling points include Ft.
McKavett, Cedar Valley, Satsuma, and East Houston. Additional coupon/water
sample collection points may be installed as determined necessary through
hazard analysis.
Internal Examination 195.579(c) and 192.475 (b)
4.5.1 Whenever any pipe is removed from the pipeline for any reason, the internal
surface shall be inspected for evidence of corrosion. Refer to Examining and
Documenting the Condition of an Underground Pipeline or Related Facility
When Exposed for more information.
4.5.2 4.5.3 4.5.4 When corrosion requiring remedial action is found, further investigation will
be conducted both circumferentially and longitudinally (by visual examination,
indirect method, or both) to determine the extent of the corrosion. Remedial
actions will follow if necessary. Refer to Pipeline Defect Evaluation and Repair
for more information.
If the extent of corrosion cannot be determined, plans and scheduling for
further investigation or the use of an internal inspection device shall be
developed based on the severity of the corrosion encountered.
The internal condition of the pipelines shall be documented on the Pipeline
Maintenance Report.
5.0 QUALIFICATION

<<<PAGE 1206>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 21 of 29
5.1 Supervisor Qualification 195.555 and 192.453
5.1.1 Magellan Asset Integrity Supervisors shall be knowledgeable of Magellan
corrosion control procedures, including but not limited to those for design,
installation, operation, and maintenance of internal and external corrosion
control systems.
5.1.2 Supervisors may be registered professional engineers, or persons recognized
as corrosion specialists or cathodic protection specialists by NACE, and/or
their professional activities include suitable experience in corrosion control.
5.2 Operator Qualification
5.2.1 Operator Qualification (OQ) is required for personnel to perform identified
Covered Tasks. Refer to Operator Qualification (OQ) – Covered Tasks for more
information.
5.2.2 Assets covered by the Mitigation Plan: All Corrosion related activities shall be
applied under the direction of competent personnel trained in the field of
corrosion control. Corrosion control data shall be reviewed by NACE certified
corrosion personnel.
6.0 CORROSION CONTROL RECORDS 195.404 and 192.491
6.1 Records or maps shall be maintained to show the location of:
6.1.1 Cathodically protected pipelines
6.1.2 Cathodic protection facilities, including galvanic anodes, installed after
January 28, 2002
6.1.3 Neighboring structures bonded to cathodic protection systems.
6.2 Records or maps shall be maintained showing a stated number of anodes, installed in a
stated manner or spacing. Specific distances to each buried anode need not be shown.
6.3 Records shall be maintained of each analysis including root cause analysis, check,
demonstration, examination, inspection, investigation, review, survey, and test required
in sufficient detail to demonstrate the adequacy of corrosion control measures or that
corrosion requiring control measures does not exist. These records shall be maintained
for a minimum of 5 years.
6.4 All pipe to soil survey, rectifier inspection, and foreign line crossing pipe to soil potential
data will be recorded in the appropriate corrosion control database. All close interval
pipe to soil potential data will be recorded in a hard copy report as well as the
appropriate electronic format, atmospheric inspection data and exposes pipe visual
inspection data will be documented on the appropriate forms and distributed

<<<PAGE 1207>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 22 of 29
appropriately, and will feed into and be processed in overall LPSIP by populating
appropriate portions of the relative risk model.
6.5 As long as the pipeline remains in service, records shall be maintained for:
6.5.1 Exposed portions of buried pipelines
6.5.2 Cathodic protection surveys, including close interval or comparable surveys
6.5.3 Internal corrosion coupon examination records and records of internal
examination of removed pipe
7.0 INTEGRITY MANAGEMENT PLAN INTEGRATION
7.1 In accordance with the Integrity Management Plan, the Pipeline Risk Engineer will
conduct integrated analysis with the External Corrosion Control Program Manager
and/or SMEs to ensure effective integration of data, recommendations, and/or program
enhancements identified during risk assessments and analysis.
7.2 Recommendations or process changes identified by the External Corrosion Control
Program Manager and/or SMEs as a result of the integrated analysis will be
communicated to and discussed with Pipeline Risk Engineer in accordance with the
Magellan IMP.
7.3 Mitigation measures or process changes conducted by the External Corrosion Control
Program Manager and/or SMEs as a result of the integrated analysis will be
communicated to and discussed with Pipeline Risk Engineer in accordance with the
Magellan IMP.
7.4 Whenever a line is added or removed from the Corrosion Control Program or elements
of the Corrosion Control Program (i.e. External, Internal, Atmospheric), the Pipeline Risk
Analyst shall be notified in order to update the Risk Assessment Model. All pipelines
included in the Corrosion Control Program shall be maintained in accordance with the
program guidelines and criteria. Corrosion Control records or data from new
construction or pipeline acquisition activities shall be entered into the Corrosion Control
database within one year. Pipelines not included in the program are not maintained in
accordance with the program and as such, corrosion can be expected. See Inactive
Pipelines and Abandoning Pipeline Segments for more details.
8.0 DEFICIENCIES IN CORROSION CONTROL
8.1 Deficiencies in Corrosion Control shall be corrected in a reasonable time.
8.1.1 Unless otherwise specified in this program, a reasonable time to correct
deficiencies is defined as by the next scheduled inspection.

<<<PAGE 1208>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 23 of 29
8.1.2 8.1.3 In the case where deficiencies cannot be complete by the next scheduled
inspection; planning, scheduling, progress, assessment, testing, monitoring,
and/or other process that demonstrates that the threat in being addressed in
a prudent and practical manner may be utilized until such time the deficiency
has been resolved.
A cause analysis will be performed to identify contributing factors and root
causes of anomalies/deficiencies identify by corrosion control surveys.

<<<PAGE 1209>>>

A
Fugitive VOC Emissions for Each New Pump Station and Meter Station In Service
Equipment Type
Representative
Equipment
Count per
Station1 Service
VOC Emission Factors2,3
VOC Emissions for
Pipeline Pump
Station
VOC Emissions for
Pipeline Meter
Station4
(kg/hr/source) (lb/hr/source)
Daily
(lb/day)
Annual
(tpy)
Daily
(lb/day)
Annual
(tpy)
Valves 44 Light liquid 0.000043 0.0000948 0.100 0.0183
Pump seals 383 Light liquid 0.00054 0.00119 10.945 1.9974
Flanges 11 Light liquid 0.000008 0.0000176 0.005 0.0008
Other 5 Light liquid 0.00013 0.000287 0.034 0.0063
TOTAL: 11.08 2.02 0.059 0.011
1Equipment counts are based on the average number of valves, pump seals, flanges, and other equipment for the following Orion pipeline
pump stations: Black River, Centerville, Chico, Clyde, Cresson, Grandview, Henrietta, Hueco, Kermit, Marlin, Maypearl, Midland, Waco,
2Source: Protocol for Equipment Leak Emission Estimates, U.S. EPA, EPA-453/R-95-017, November 1995, Table 2-3
3Emission factors are actually for total organic compounds, which inculde methane and ethane; therefore, these factors are conservative for representing VOC emissions
4Total annual VOC emissions per operating metering station based on total VOC emissions for Odessa meter station, as presented in Appendix 7I of original EA
Notes:
1. Pumps will operate on electricity from the existing grid; therefore, no combustion-related emissions will be generated at the pump and meter stations.
2. Number of new pipeline pump stations for 'Connected Actions': Number of new pipeline meter stations for 'Connected Actions': 8 (DeLeon, Iatan, Black River, Wink, Odessa (2), and Midland-Oxy, and Cottonwood)
6 (Black River, Wink, Odessa, Crane, Midland-Oxy, and El Paso)
(Connected Actions are those associated with the Orion pipeline expansion)
3. Number of new pipeline pump stations for Longhorn pipeline: 9 (Buckhorn, Industry, Warda, Bastrop, Eckert, James River, Cartman, Barnhart, and Texon)
Number of new pipeline meter stations for Longhorn pipeline: 6 (Crane (outgoing), Texon, Barnhart, Bastrop, Warda, and Industry)

<<<PAGE 1210>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 25 of 29
NACE Certification, shall be utilized to identify, mitigate, and
monitor for inadequate cathodic protection and detrimental
interference currents, prior to and during construction. Refer
to Section 1.8, Foreign Crossings and Interference Currents
below.”
11/30/03 1.6.5 Rick Wooldridge Michael Pearson Added entire section related to CIS
11/30/03 1.11.4 Rick Wooldridge Michael Pearson
Deleted, “The external condition of the pipelines shall be
reported on Form 02‐LEG‐1035 – Encroachment Agreement
(Short Form), Form 02‐OPR‐1581 – Maintenance Report, or
equivalent form.”
12/1/03 1.0 Rick Wooldridge Michael Pearson Added Index and renumbered
12/1/03 9.0 Rick Wooldridge Michael Pearson Added Definitions
12/1/03 8.0 Rick Wooldridge Michael Pearson Added References
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “DETERMINING CORROSIVE PROPERTIES OF
CARGOES IN PETROLEUM PRODUCTS PIPELINES”
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “Refer to Copper Strip Corrosion by Liquefied
Petroleum (LP) Gases.”
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “and Field Gas Analysis For CO2, H2S, O2 and Dew
Point.”
12/1/03 8.2 Rick Wooldridge Michael Pearson
Deleted, “NOTE: Corrosivity of liquid products (refined
petroleum products and natural gas liquids) is rarely
evaluated
12/1/03 8.2 Rick Wooldridge Michael Pearson Deleted, “Corrosive gas shall not be transported by pipeline,
……considered to be potentially corrosive.”
12/1/03 4.6 Rick Wooldridge Michael Pearson Rewrite to be consistent with External Examination
3/23/04 4.4.2 Rick Wooldridge Michael Pearson
Added: Effectiveness of inhibitor will be based on the
inhibitors success.. typically <1 MPY for refined
products.
3/23/04 4.4.3 Rick Wooldridge Michael Pearson Added: Internal corrosion rates greater than >1 MPY on
inhibited pipelines…..engineering judgment.
6/5/2004 3.1.1 Rick Wooldridge Michael Pearson
Note: Atmospheric corrosion inspections on exposed
pipelines may be conducted visually or through the use
of an in-line inspection device capable of identifying and
sizing corrosion.
11/5/2004 2.2.2, 2.6.3 Rick Wooldridge Michael Pearson
Modified for clarification: Noted conditions that will cause
compliance with 651 to not be observed may be but are
not limited to tanks set on concrete, asphalt pads or
where studies conducted in accordance with API 653
indicate that corrosion will not affect the safe operation of
the tank.
11/30/2004 2.9.4.1 Rick Wooldridge Michael Pearson Replaced “shall” with “may” for 195 lines and added the
192 language.
1/3/05 3.3.1 Rick Wooldridge Michael Pearson Deleted: Operate Auto-Injection Pumps, Added: Internal
Corrosion Remediation
1/3/05 3.4.4 Rick Wooldridge Michael Pearson Replaced reference to OJT with “Refer to Coupon
Handling and ER Probes” for more information.
1/3/05 3.4.4 Rick Wooldridge Michael Pearson Reviewed the procedure for accuracy and effectiveness.
4/7/05 Overall Rick Wooldridge Michael Pearson Minor modification and editorials added to provide
clarification…no process changes.
5/16/05 1.9.4.3 Rick Wooldridge Michael Pearson
Added: “Note: For line sections integrity tested by
hydrostatic test a risk evaluation will be conducted at
each shorted casing and action taken to clear the short
and/or mitigate the corrosion if deemed necessary.”
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Basic SCC awareness information is available to
operation and maintenance employees in Stress

<<<PAGE 1211>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 26 of 29
Corrosion Cracking Information.
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: In the event that a pipeline system has
experienced one or more confirmed incidents of SCC a
systematic identification and examination of other
potential locations of SCC will be conducted based upon
the observations of conditions associated with the
confirmed SCC incident.
7/6/05 1.12 Rick Wooldridge Michael Pearson Added: or any other locations identified for SCC
investigation,
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Pipe cutouts sent to a metallurgical lab for
analysis will be investigated for SCC. Results of this
analysis will be provided in a comprehensive report
provided to Asset Integrity.
Added: SCC examinations will be performed by a NDE
Technician trained in the detection of SCC on buried
pipelines and will be documented in the Pipeline
Maintenance Report.
7/6/05 1.12 Rick Wooldridge Michael Pearson
Added: Annually, confirmed SCC occurrences will be
reviewed to determine if changes to the SCC
assessment criteria are necessary.
8/1/05 1.12 Rick Wooldridge Michael Pearson No confirmed SCC occurrences to review.
11/7/05 All Rick Wooldridge Michael Pearson Added LPP Mitigation and Shell CD requirements.
11/7/05 3.3.2 Rick Wooldridge Michael Pearson Added cleaning pig requirements.
12/14/05 3.5.2 Rick Wooldridge Michael Pearson Added “circumferentially and longitudinally”
1/4/06 1.13, 7.13 Rick Wooldridge Michael Pearson Added MIC related information to the program.
03/06/06 2.9.4.3 Rick Wooldridge Michael Pearson Deleted “clear the short and/or” mitigate the corrosion …
4/6/2006 3.2.1 Rick Wooldridge Michael Pearson
Added: Refer to Coatings – Selection, Applications, and
Maintenance for more information.
4/6/2006 2.13.1 Rick Wooldridge Michael Pearson Replaced “incidents” with “discoveries” and added
“injurious”.
4/6/2006 4.4.1 Rick Wooldridge Michael Pearson Replaced “Internal Corrosion Remediation” with “Auto
Injection Pumps”.
9/8/2006 8.0, 10.0 Rick Wooldridge Michael Pearson
Section 8 ‐ Deficiencies in Corrosion Control was added and
references to “as soon as practical” were removed from the
document. Section 10 – Definitions was update to include
“reasonable time”.
9/8/2006 ALL Rick Wooldridge Michael Pearson
Reviewed entire document…minor editorial changes, no
process changes.
10/26/2006 2.3.4.2, 2.3.6 Rick Wooldridge Michael Pearson Removed references to Net Protective current criteria
11/30/06 TOC Rick Wooldridge Michael Pearson Added 2.14 ‐ AC Corrosion
11/30/06 2.5.3 Rick Wooldridge Michael Pearson Changed “Section 1.8 to 2.8 “and added “2.14, Induced AC
Corrosion” in the last sentence.
11/30/06 2.8.4 Rick Wooldridge Michael Pearson
Added Section 2.8.4 “For interference currents related to
AC.........”
11/30/06 2.14 Rick Wooldridge Michael Pearson
Added new Section – “2.14 Induced AC Corrosion” and
subsections 2.14.1, 2.14.2 and 2.14.3
11/30/06 9.1 Rick Wooldridge Michael Pearson
Added link to “Testing for Induced AC and Remedial Measures
in Related Policies/Procedures
11/30/06 10 Rick Wooldridge Michael Pearson
Added the definition for Induced AC Corrosion to Section 10 –
Definitions
11/30/06
Deleted
12/7/09
3.2.4 Rick Wooldridge Michael Pearson
Added: Longhorn Specific: A suitable coating shall be applied
to all aboveground facilities and soil‐to‐air interface areas to
prevent corrosion damage. All areas with signs of coating
degradation and/or corrosion shall be coated/recoated. Refer

<<<PAGE 1212>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 27 of 29
to Coatings – Selection, Applications and Maintenance for
more information.
4/25/07 2.1 David Stewart Michael Pearson Added 16 TAC 7.86(3) to regulation references.
4/25/07 2.1.6 David Stewart Michael Pearson Added “…using a coating deficiency (holiday) detector…”
4/25/07 2.1.9 David Stewart Michael Pearson
Added new paragraph, “Joints, fittings, and tie‐ins shall be
coated with material(s) compatible with the coating(s) on the
pipe.” Old 2.1.9 reference to Coatings – Selection,
Applications, and Maintenance becomes 2.1.10.
4/25/07 2.8 David Stewart Michael Pearson Added 16 TAC 7.86(5)(c) to regulation references.
4/25/07 2.8.4 David Stewart Michael Pearson
Added new paragraph, “Texas Intrastate Pipeline specific:
Whenever suspected areas of interference are identified,
testing will be conducted within 6 months to determine the
extent of interference, and appropriate action will be taken.”
Old 2.8.4 reference to AC testing becomes 2.8.5.
1/1/08 4.2.2 David Stewart Rick Wooldridge Added natural gas
1/15/08 2.6.4.1 David Stewart Rick Wooldridge
Added paragraph requiring adequate levels in AST’s when
taking potential readings, as well as requirement to document
the tank levels.
2/15/08 2.3.2 Rick Wooldridge Larry Davied
Added: “Where injurious aerobic bacteria has been identified,
or is suspected, a polarized potential of ‐.950 volts or more
negative is required.”
2/20/08 All E7 Rick Wooldridge 2007 annual review
9/08/08 3.1.1 Rick Wooldridge Larry Davied
Removed the note “or through the use of an in‐line inspection
device capable of identifying and sizing corrosion…at the
request of PHMSA
09/25/08 1.3 Rick Wooldridge Larry Davied Remove references to Shell’s Consent Decree
09/25/08 All E7 Rick Wooldridge 2008 annual review, no changes
11/06/08 4.3.2.3 Rick Wooldridge Larry Davied
Pipelines transporting NH3 do not require routine pigging, but
should be cleaning if excessive debris is identified and/or
prior to In‐line inspection tool runs.
11/16/09 All E7 Rick Wooldridge 2009 annual review; Removed references to Longhorn
12/07/09 4.1.1 E7 Rick Wooldridge
Removed…Pipeline cargoes shall be periodically evaluated for
corrosivity. Added: The corrosive effects of pipeline cargoes
(hazardous liquids or carbon dioxide) shall be investigated.
12/07/09 4.1.2 E7 Rick Wooldridge
Added: Circumstance or condition [such as those listed
below] that could cause, promote, or increase the likelihood
of internal corrosion should be promptly reviewed and
internal corrosion mitigation plans implemented as
appropriate.
12/07/09 4.1.2.1 thru 4.1.2.11 E7 Rick Wooldridge
Added: 4.1.2.1 Type of commodity, 4.1.2.2 Flow rate, 4.1.2.3
Velocity, 4.1.2.4 Operating Pressure, 4.1.2.5
Topography, 4.1.2.6 Amount of foreign material and/or
contaminants present in the pipeline and/or commodity
stream such as sand, silt, water, or other materials that could
cause or promote internal corrosion, 4.1.2.7 Amount of
sulfur, salts, acids, hydrogen sulfide, carbon dioxide or other
corrosive material present and corrosive effect based upon
partial pressures of material in the pipeline 4.1.2.8 Presence
of microbes, 4.1.2.9 Temperature, 4.1.2.10 Pipe
configuration, design, and material specifications, 4.1.2.11
Operating conditions, including but not limited to, steady

<<<PAGE 1213>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 28 of 29
state conditions, slack line conditions, upset conditions in the
pipeline system, and upset conditions in upstream facilities
such as refineries or processing facilities
03/03/10 10 E7 Rick Wooldridge Deleted “Definitions”
03/03/10 8.1.3 Jimmy Puckett Rick Wooldridge
Information added to provide a single specific location that
addresses LMP requirements…cause analysis will be
performed to identify contributing factors and root causes of
anomalies/deficiencies identify by corrosion control surveys.
03/03/10 6.4 Jimmy Puckett Rick Wooldridge
Information added to provide a single specific location that
addresses LMP requirements…All pipe to soil survey, rectifier
inspection, and foreign line crossing pipe to soil potential data
will be recorded in the appropriate corrosion control
database. All close interval pipe to soil potential data will be
recorded in a hard copy report as well as the appropriate
electronic format, atmospheric inspection data and exposes
pipe visual inspection data will be documented on the
appropriate forms and distributed appropriately, and will feed
into and be processed in overall LPSIP by populating
appropriate portions of the relative risk model.
3/25/10 6.3 DOT Rick Wooldridge
Modified: Records shall be maintained of each root cause
analysis...to read Records shall be maintained for each
analysis including root cause analysis.
8/9/10 2.3.4 E7 – Ken Lybarger Rick Wooldridge Changed Supervisor of Asset Integrity to Supervisor of
Corrosion Control
8/9/10 2.10.4 E7 – Ken Lybarger Rick Wooldridge
Changed Supervisor of Asset Integrity to Supervisor of
Pipeline Integrity to maintain consistency with pipeline
welding procedures.
2010 annual review; 2.4.2 was simplified to say, “Cathodic
protection level should be evaluated utilizing Cathodic
08/09/10 All E7 Rick Wooldridge
Protection Criteria.”. This change was necessary to
improve/clarify the process for IR drop consideration.
Deleted: “4.2.1 Products entering the system shall be
sampled in accordance with D 4057‐95 (2000) ‐ Standard
Practice for Manual Sampling of Petroleum and Petroleum
Products, D 5842‐95 (2000) ‐Standard Practice for Sampling
and Handling of Fuels for Volatility Measurement, and D
4177‐95 (2000) Standard Practice for Automatic Sampling of
Petroleum and Petroleum Products”. This change removes
unnecessary and likely incomplete information.
10/10/11 4.3.2.3 Rick Wooldridge Doug Chabino
2011 Annual Review;
Added: The frequency for routine cleaning operations of
mainline crude piping should be 26 times per year,
approximately every two weeks. Frequencies of cleaning pig
runs may be adjusted as necessary based upon product
upsets and the analysis of results of previous cleaning pig
runs.
12/31/11 All 2012 Annual Review complete
2/16/12 4.3.2.3 Rick Wooldridge Doug Chabino Added clarification to facility piping
5/15/12 2.9.4.4 Rick Wooldridge Doug Chabino
Added section to require testing for electrolytic shorted
casings
5/15/12 2.9.4 Rick Wooldridge Doug Chabino Removed references to 192 (Gas) assets
5/15/12 4.3.2.6 Rick Wooldridge Doug Chabino
Added: Where excessive debris and paraffin buildup is
thought to exist, specialty pigs such as pin‐wheel, Pit Boss™,

<<<PAGE 1214>>>

Magellan Midstream Partners, L.P.
CORROSION CONTROL PROGRAM 7.04–ADM–001
Asset Integrity 02/19/12 Revision: 11 Page 29 of 29
scraper/plow blade attachments, and magnetic cleaning pigs
shall be utilized as necessary based upon sound engineering
judgment.
5/15/12 4.3.3.1 Rick Wooldridge Doug Chabino
Added: For refined product systems a hydrocarbon soluble,
water dispersible corrosion inhibitor shall be utilized (Smart
Chemical SCSF260 or equivalent). For crude pipeline systems,
a highly water dispersible/soluble blend of corrosion
inhibitors shall be utilized (Smart Chemical SCCI865 or
equivalent).
5/15/12 4.4.5 Rick Wooldridge Doug Chabino Added: and <3 MPY for crude.
5/15/12 4.4.8 Rick Wooldridge Doug Chabino
Added: (Reference API RP‐45, NACE TM0194, NACE RP0192,
and ASTM D2327 for more information) and For crude
pipeline systems, water sample traps will be mounted on the
bottom of the pipe to facilitate the collection and analysis of
free water. These locations will be inspected for water
monthly and if a sufficient amount of water is present
(typically >1 pint) this water shall be analyzed for bacteria,
pH, iron, manganese, chlorides, and inhibitor residual.
Bacteria counts in excess of 10‐100 colonies/ml., pH readings
outside a range of 4‐8, inhibitor residual less than ~10ppm, or
an increase in iron, manganese, or chlorides could indicate an
increase threat to internal corrosion. Water and debris
brought into receiving traps during pigging operations will be
tested to determine its potential to cause internal corrosion if
determined to be necessary after consultation with the
Corrosion Specialist.
5/15/2012 4.4.9 Rick Wooldridge Doug Chabino
Added: Crude assets covered by the Mitigation Plan:
Coupon/water sample collection points will be located in
facilities at origination points, along the pipeline system, and
end points. Locations chosen for initial sampling points
include Ft. McKavett, Cedar Valley, Satsuma, and East
Houston. Additional coupon/water sample collection points
may be installed as determined necessary through hazard
analysis.
5/15/2012 4.4.2, 4.4.8 Rick Wooldridge Doug Chabino Added references to Standard documents
5/15/2012 2.14 Rick Wooldridge Doug Chabino
Recording voltmeters should be considered in areas where
high voltage transmission lines parallel the pipeline over long
distances.

<<<PAGE 1215>>>

Magellan Midstream Partners, L.P.
ATMOSPHERIC CORROSION INSPECTIONS 7.04–ADM–002
Asset Integrity 01/01/11 Revision: 4 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for monitoring,
inspecting, and reporting atmospheric corrosion conditions on aboveground facilities.
2.0 PROCEDURE
2.1 Identifying Areas For Inspection
2.1.1 Identify all above grade and above water line structures/facilities or parts of
structures/facilities as subject for atmospheric corrosion inspection.
2.1.2 Select an appropriate number of representative locations in each facility to
adequately evaluate the facility for atmospheric corrosion. Particular attention
should be given to pipe and soil to air interface areas, under thermal insulation,
under disbonded coatings, at pipe supports, in splash zones, at deck
penetrations, and in spans over water.
2.1.3 Maintain a listing of all subject areas, including GPS coordinates, and updated
as needed in the Cathodic Protection Data Manager.
2.1.4 Some structures/facilities with corresponding inspection requirements are:
2.1.4.1 Pump/Compressor stations, measuring and regulating stations,
storage vessels and tankage, and miscellaneous facilities (building,
structure, piping and equipment):
2.1.4.1.1 Pipe ground transition/interface areas
2.1.4.1.2 Pipe above grade coatings
2.1.4.1.3 Pipe condition at building wall entry/exit
2.1.4.1.4 Structure and equipment coating condition
2.1.4.2 Underground pipe or related facilities exposed to the atmosphere
due to intentional or unintentional reasons (i.e., erosion,
subsidence, etc.)
2.1.4.3.1 Pipe ground level transition and above ground coating
conditions
2.1.4.3 Pipe spans (supported and unsupported)
2.1.4.3.1 Pipe ground level transition and above ground coating
conditions
2.1.4.4 2.1.4.3.2 Pipe support and traffic guard coating conditions
Suspension bridges (piping and structure):
2.1.4.4.1 Physical condition of structural steel towers,
assemblies, clamps, pipe hanger system, bolts, cables,
cable hardware, cable anchorages, and concrete
foundations
2.1.4.4.2 Pipe ground level transition and above ground coating
conditions
2.1.4.5 Pipeline valves, expansion loops, and associated piping:
2.1.4.5.1 Pipe ground level transition coating condition

<<<PAGE 1216>>>

Magellan Midstream Partners, L.P.
ATMOSPHERIC CORROSION INSPECTIONS 7.04–ADM–002
Asset Integrity 01/01/11 Revision: 4 Page 2 of 5
2.2 2.3 2.1.4.5.2 Pipe above grade coating condition
2.1.4.5.3 Structure (pipe supports) coating condition
Preparing the surface for inspection and or remedial action
2.2.1 The surface to be inspected shall be visible and sufficiently clean, based on the
judgment of the inspector, to allow for an accurate assessment of corrosion.
2.2.2 Valves and/or other equipment located inside valve cans should be inspected
from the surface if possible. If entry into the valve can is required, the
procedures for Confined Space entry shall be followed.
2.2.3 Surface rust and/or oxidation may be removed using a hand or power wire
brush and water or abrasive blasting. Files, hammers, or any other equipment
that may damage the pipe should not be used.
2.2.4 If pipe or pipe support movement is required:
2.2.4.1 Contact the Risk Engineer to determine the maximum movement
allowable for the specific pipe and/or support.
2.2.4.2 Install a temporary support or lift the pipe using pipe protective
devices such as pipe saddles or hoist with proper rigging
techniques if applicable.
2.2.4.3 2.2.4.4 2.2.4.5 2.2.4.6 2.2.4.7 2.2.4.8 Remove the existing pipe support, if necessary.
Perform the visual inspection as indicated in 2.4 below.
Replace the pipe support, if necessary.
Lower the pipe or raise the support to the desired position.
Remove the temporary pipe support, if applicable.
Adjust the support height to ensure a level pipe or as directed by
the Risk Engineer.
Performing visual inspection of surfaces
2.3.1 Visually inspect all surfaces and assign a visual “corrosion” condition code on
the Atmospheric Corrosion Inspection data gathering form, in the data logger,
or in the Cathodic Protection Data Manager in accordance with SPCC-VIS 2;
Standard Method for Evaluating Degree of Rusting on Painted Steel Surfaces,
General Rusting Standard.
NOTE: Given the similarity between the General Rusting and Spot Rusting
SPCC-VIS 2 Standards, the General Rusting Standard (1-G...9-G) is to be
used for all assets.
NOTE: If pitting corrosion, corrosion is in excesses of 12.5% of the pipewall
or any dents, gouges, or SCC is observed, contact an Asset Integrity
Supervisor, Risk Engineer, or Pipeline Integrity Engineer/Coordinator
immediately.
2.3.2 For Rust Ratings of 2-G or less, utilize the comment section on the
Atmospheric Corrosion Inspection data gathering form, in the data logger, or in
the Cathodic Protection Data Manager to quantify and describe the structure

<<<PAGE 1217>>>

Magellan Midstream Partners, L.P.
ATMOSPHERIC CORROSION INSPECTIONS 7.04–ADM–002
Asset Integrity 01/01/11 Revision: 4 Page 3 of 5
2.3.3 and/or coating damage. Transfer of hardcopy data to the CPDM System should
take place as soon as practical following the inspection.
Visually inspect the soil-to-air interface area and classify the “interface coating”
as Adequate or Inadequate on the Atmospheric Corrosion Inspection data
gathering form, in the data logger, or in the Cathodic Protection Data Manager.
Transfer of hardcopy data to the CPDM System should take place as soon as
practical following the inspection.
NOTE: The interface coating is adequate if it adequately prevents corrosion
at the site where the pipeline first comes in contact with the soil.
2.3.4 2.4 Remedial actions
2.4.1 2.5 Documentation
2.5.1 2.5.2 Replicate the Cathodic Protection Data Management System.
Areas of atmospheric concern requiring inspection and/or remedial action will
be addressed in accordance with the External Corrosion Control Program and
Atmospheric Corrosion Workflows.
Areas of exposed pipe identified through routine corrosion work, aerial patrol,
Depth-of-Cover survey, etc. shall be entered into the Cathodic Protection Data
Management System to ensure follow-up inspection.
Documentation of atmospheric corrosion inspection data is handled in the
Cathodic Protection Data Management System.
End of Procedure

<<<PAGE 1218>>>

Magellan Midstream Partners, L.P.
ATMOSPHERIC CORROSION INSPECTIONS 7.04–ADM–002
Asset Integrity 01/01/11 Revision: 4 Page 4 of 5
System Integrity Plan Change Log
Date CHANGE
LOCATION
Changed By Approved
By Brief Description of Change
10/03/02 2.2.1 Rick
Wooldridge
Michael
Pearson
Revised note before 2.2.2 to point to correct procedure.
5/13/03 2.1.1 Rick
Wooldridge
Michael
Pearson
Added NOTE: Select an appropriate number………………
5/13/03 2.3.2 Rick
Wooldridge
Michael
Pearson
Delete reference to the Manager of Equipment Technology
5/13/03 2.4.2 Rick
Wooldridge
Michael
Pearson
Delete entire section as it relates to the Manager of
Equipment Technology
5/13/03 2.2.4 Rick
Wooldridge
Michael
Pearson
Added 2.2.4 Update the Cathodic Protection Data
Management System (BASS)
10/29/03 1.0, 2.1.1 Rick
Wooldridge
Michael
Pearson
Deleted “and offshore” and “Note”
10/29/03 2.2 Rick
Wooldridge
Michael
Pearson
2.2. was completely rewritten to utilize SPCC-VIS 2
guidelines and processes.
10/29/03 2.3.1 Rick
Wooldridge
Michael
Pearson
Replaced “The Supervisor of Pipeline Integrity….” “with
Areas of atmospheric concern requiring inspection …..”.
10/29/03 2.0 Rick
Wooldridge
Michael
Pearson
Added “Note: performing an atmospheric corrosion
inspection is a covered task and should only be performed
by those qualified in accordance with the operator
qualification ruling”.
10/29/03 4.0 Rick
Wooldridge
Michael
Pearson
Deleted “Platform” and “Splash Zone”
08/11/04 2.2 Rick
Wooldridge
Michael
Pearson
Added Section 2.2 – “Preparing the surface for inspection
and or remedial action” and its subsections.
08/11/04 2.2, 2.5 Rick
Wooldridge
Michael
Pearson
Added provisions for how to use In-Line Inspection data to
conduct atmospheric corrosion inspections
8/11/04 ALL Rick
Wooldridge
Michael
Pearson
Reviewed procedure for accuracy and effectiveness.
1/1/06 All E7 Michael
Pearson
Reviewed, no changes
5/12/06 2.3.2 Rick
Wooldridge
Michael
Pearson
Added: Valves and/or other equipment located inside valve
cans should be inspected from the surface if possible. If
entry into the valve can is required, the procedures for
Confined Space entry shall be ollowed.
01/01/08 All E7 Larry Davied 2007 review, no changes
09/08/08 2.2, 2.5 Rick
Wooldridge
Larry Davied Removed references to using ILI data to perform
atmospheric inspections
09/08/08 2.2, 2.5 Rick
Wooldridge
Larry Davied Added: Particular attention should be given to pipe and soil
to air interface areas, under thermal insulation, under
disbonded coatings, at pipe supports, in splash zones, at
deck penetrations, and in spans over water.
11/19/08 ALL E7 Rick
Wooldridge
2008 review, no changes

<<<PAGE 1219>>>

Magellan Midstream Partners, L.P.
ATMOSPHERIC CORROSION INSPECTIONS 7.04–ADM–002
Asset Integrity 01/01/11 Revision: 4 Page 5 of 5
Date CHANGE
LOCATION
Changed By Approved
By Brief Description of Change
11/17/09 ALL E7 Rick
2009 review, minor clean-up changes
Wooldridge
08/10/10 ALL E7 Rick
Wooldridge
2010 review; Deleted all references to BASS
12/31/11 ALL 2012 Annual Review complete – no changes

<<<PAGE 1220>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 1 of 9
The purpose of this procedure is to establish standardized cathodic protection (CP) criteria to be
used to confirm adequate external corrosion control for Company facilities.
1.0 PURPOSE
1.1 2.0 PROCEDURE
2.1 2.2 2.3 Identifying CP Criteria to be Used
2.1.1 Selecting which CP criteria to use
2.1.1.1 Use the –0.850 volts Pipe-to-Soil (P/S) potential criteria as the primary criteria for
all facilities.
2.1.1.2 Use the 100 millivolt shift criteria whenever the –0.850 volts P/S criteria cannot
be achieved or as directed by the Manager of Asset Integrity.
2.1.1.3 The criteria employed must be specified in the Cathodic Protection Data
Manager for the facility, segment, or individual test point.
Using the –0.850 Volts P/S Criteria
2.1.2 2.1.3 2.1.4 2.1.5 Take P/S potentials per procedure Measuring a Pipe-to-Soil Potential.
P/S reading must be at least –0.850 volts, with reference to a saturated copper-copper
sulfate reference half-cell, while the protective current is applied.
Voltage (IR) drops shall be considered per section 2.5 below.
Whenever –0.850 volts P/S is not achieved, the 100 millivolt shift criteria should be
applied, unless corrective actions are planned to remediate the low potential.
100 Millivolts Voltage Shift (Polarization Formation) Criteria
2.3.1 2.3.2 To use the 100 millivolt shift criteria as established by the polarization formation method,
follow the procedure described below.
For Existing Pipelines Or Facilities
2.3.2.1 Turn off and/or disconnect all known sources of CP influence.
2.3.2.2 Allow sufficient time for the piping or facility to depolarize.
2.3.2.3 Conduct a complete P/S survey (near native state survey).
2.3.2.4 Near native state survey, results may not be totally native state due to unknown
galvanic anodes or foreign impressed and stray current influences. If other CP
influences are located, these should be shut down and a new survey performed
in the areas of influence.
2.3.3 Apply CP to the Pipeline or Facility
2.3.3.1 Turn on and/or reconnect all known sources of CP influence.
2.3.3.2 Allow sufficient time for the structure to polarize or re-polarize for existing
structures.
2.3.4 Conduct an Interrupted P/S Survey Of The Pipeline Or Facility
2.3.4.1 Install and place in operation interrupter equipment in all influential CP current
sources affecting the pipeline or facility being tested.
2.3.4.2 Synchronize all interrupters.

<<<PAGE 1221>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 2 of 9
2.3.5 2.3.6 2.3.7 2.3.4.3 Use at least an 80% duty cycle (“On” cycle set to 8 seconds and “Off” cycle set to
2 seconds). Keep the “Off” cycle as short as possible to prevent polarization
decay but long enough to read after any spike (“Instant Off”) as shown in Figure
1 “Polarization Formation”.
2.3.4.4 After starting the interruption of all current sources, read the “On” potential during
the “On” cycle and take the “Off” potential reading instantly after any spike.
Conduct a complete P/S survey, recording both the “Instant Off” and the “On” potential
readings.
Calculate for the 100 millivolt shift.
2.3.6.1 Subtract the Native State or Near Native State potential from the “Instant Off”
potential for each location.
To meet the 100 millivolt shift criteria, the results must be greater than 100 millivolt.
2.4 2.3.8 Establish Individual Test Point “ON” criteria based on the 100 millivolt test.
2.3.8.1 When 100 millivolt or more shift occurs, the “On” potential reading is established
as the P/S criteria, with CP on, for a particular test point.
2.3.8.2 As long as there are no significant changes in the environment, structure,
coating, CP systems, etc., this established “On” criteria can be used for satisfying
the 100 millivolt criteria through the monitoring of the “On” potentials.
100 Millivolts Voltage Shift (Polarization Decay) Criteria
2.4.1 To use the 100 millivolt shift criteria as established by the polarization decay method
2.4.1.1 Install and place in operation interrupter equipment in all influential CP current
sources effecting the pipeline or facility being tested.
2.4.1.2 Synchronize all interrupters
2.4.1.3 Use at least an 80% duty cycle (“On” cycle set to 8 seconds and “Off” cycle set to
2 seconds). The “Off” cycle should be kept as short as possible to prevent

<<<PAGE 1222>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 3 of 9
2.5 2.4.2 2.4.3 2.4.4 2.4.5 2.4.6 polarization decay, but long enough to read after any spike (“Instant Off”) as
shown in Figure 2.
2.4.1.4 Conduct a complete P/S survey, recording both the “Instant Off” and the “On”
potential readings. Mark each spot of electrode placement.
Calculate Targeted Near Native State P/S Potentials as Follows:
2.4.2.1 Subtract 100millivolt from the “Instant Off” potential reading for each test point.
This is the targeted near native state P/S potential.
Test For Polarization Decay To Targeted Near Native State P/S Potentials As Follows:
2.4.3.1 Turn off and/or disconnect all known sources of CP influence.
2.4.3.2 Conduct a complete P/S survey, recording “Off” potential readings.
2.4.3.3 Observe and record polarization decay potentials. When polarization decay
potentials reach targeted near native state P/S potentials, stop decay test to
retain as much polarization as possible
2.4.3.4 Targeted near native state potentials may not be totally native state due to
unknown galvanic anodes or foreign impressed and stray current influences and
a small amount of remaining polarization.
2.4.3.5 Turn on or reconnect all known sources of CP influence as soon as possible to
reestablish polarization.
Establish Individual Test Point “On” criteria based on the 100 millivolt shift, polarization
decay test.
When 100 millivolt or more shift occurs, the “On” potential reading is established as the
P/S criteria, with CP on, for that test point.
As long as there are no significant changes in the environment, structure, coating, CP
systems, etc., these established “On” criteria can be used for satisfying the 100 millivolt
criteria through the monitoring of the “On” potentials.
Methods for IR Drop Consideration
2.5.1 In accordance with Ohm’s Law of E (volts) = I (current) x R (resistance), any time current
flows through a resistance, a voltage drop is produced. For cathodic protection purposes,
the current flow in the soil (electrolyte) is the I and the soil resistance is R and the
resulting voltage drop is E in volts. Therefore, if the amount of current or the resistance is
very low, the resulting voltage or IR drop would also be low or considered negligible. The
voltage drop, commonly called the IR Drop, needs to be considered when taking pipe-to-
soil measurements. See figure below for a depiction of the IR Drop location in P/S
measurements below.

<<<PAGE 1223>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 4 of 9
High
Resistance
Voltmeter
See
Section
2.5.3
2.5.2 Various IR Drop correction techniques can be utilized to consider the IR Drop factor in
P/S measurements. These include but not limited to the following:
Which Method(s) For Considering Voltage Drop (IR) In P/S Measurements
Method Process Comments
Is affected by proximity to the current sorce
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Requires knowledge of various operating factors and historical
information
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
May be affected by the proximity to current sorce
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Historical
Operating
Information
See
Section
2.5.4
Reference
Cell
Placement
See
Section
2.5.5
Calculation
See
Section
2.5.6
Time consuming and requires various calculations
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Current
Interruption
See
Section
2.5.7
For proper use, requires synchronized interruption of all current
sources
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations
Buried
Coupons
See
Section
2.5.8
Requires installation of special test stations containing coupons
Integrity testing procedures should incorporate historical
corrosion rates and growth calculations

<<<PAGE 1224>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 5 of 9
2.5.3 High Resistance Voltmeter Method
2.5.3.1 This method considers IR drop by minimizing current flow through the
measurement circuit, thus decreasing voltage drops associated with the
mechanical and electrolytic components of the circuit.
2.5.3.2 A high resistance voltmeter (>50,000 ohm) is necessary to reduce the
voltage drop in the external circuit.
2.5.4 Historical Operating Information Method
2.5.4.1 This method utilizes recent and historical operating information to
determine if the cathodic protection system is properly protecting the
structure at existing voltage levels.
2.5.4.2 The lack of corrosion related leaks or repairs in conjunction with
consistent cathodic protection levels and coating condition indicates the
adequacy of cathodic protection.
2.5.5 Reference Cell Placement Method
2.5.5.1 Since the amount or quantity of the IR drop is directly proportional to the
distance between the reference cell and the structure to be measured,
the simplest method for considering IR drop is to minimize this distance.
2.5.5.2 To minimize IR drop at test stations:
2.5.5.2.1 The reference cell should be placed over the centerline of
the structure to be tested.
2.5.5.2.2 Permanent reference cells can be placed in close proximity
to the buried structure.
2.5.5.2.3 If a quantitative voltage drop reading is required for
the location, then a surface reading can be obtained
with a portable reference cell and then by
subtracting the reference cell reading, the voltage
drop is obtained.
Surface Reading – Reference cell reading = IR or
voltage drop

<<<PAGE 1225>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 6 of 9
2.5.5.2.4 The pipeline can be probed and a small diameter/long
cylinder reference cell inserted into the hole where the
probing occurred. This cell is then placed very close to the
pipe’s surface without contacting the pipe.
2.5.5.2.5 A plastic or non-conductive tube can be installed directly
over the pipeline. The tube should be within one or two
inches of the structure, but not contacting the coating. The
tube can be filled with soil or left open and the reference cell
lowered into the tube for voltage measurements.
2.5.5.3 To minimize IR drop when taking P/S measurements where the structure
has been excavated, the reference cell should be placed in close
proximity to the structure.
2.5.5.4 To minimize IR drop when taking P/S measurements on structures that
extend above grade, the reference cell should be placed in close
proximity to the structure.

<<<PAGE 1226>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 7 of 9
2.5.6 Calculation Method
2.5.6.1 This method utilizes an extrapolation calculation for considering the IR
drop as further noted below and in Figures 2 and 3 below.
2.5.6.1.1 When potential measurements are taken in close proximity
to another structure, this method will not be valid.
2.5.6.2 Obtain a P/S measurement directly over the structure or pipeline.
2.5.6.3 Move the reference cell six feet perpendicular away from the first reading
and obtain a second pipe-to-soil reading, called the offset potential.
2.5.6.4 Obtain the centerline depth of the structure.
2.5.6.5 Calculate the true or IR free potential using the following formula:
TR = D – A[(E – D)/C] TR = True reading in millivolts

<<<PAGE 1227>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 8 of 9
2.5.7 Using Current Interruption
2.5.7.1 This method utilizes current interruption to obtain what is commonly
called an “Instant Off” potential. The basis for this method is that the IR
or voltage drop disappears when the current is turned off according to
Ohms law of E = I x R. However, care must be exercised when using this
option as polarization may be lost when the interrupters are installed or
during the interruption cycle. Therefore, an 80% duty cycle (8 seconds
On and 2 seconds Off) is suggested.
2.5.7.2 For proper consideration of IR drop in this method, all current sources
must be interrupted. Foreign current sources must also be interrupted,
shut off or not in operation at the time of consideration.
2.5.7.3 To consider IR drop in this manner, the following steps should be
followed:
2.5.7.3.1 2.5.7.3.2 2.5.7.3.3 2.5.7.3.4 2.5.7.4 Soil Coupons
2.5.7.4.1 2.5.7.4.2 2.5.7.4.3 2.5.7.4.4 Synchronize all interrupters to be utilized for this type of
survey or consideration method.
Install the interrupters on all known current sources to
include bonds and foreign and Company cathodic protection
facilities.
Record the “On” and “Instant Off” potentials for the structure
being tested.
Remove all interrupters and return all facilities to normal
operation.
To decrease or eliminate possible errors associated with
“current interruption” coupons can be installed next to the
pipeline simulating a coating defect (holiday).
The coupon should be installed in similar backfill as the
structure to be monitored and installed in accordance with
the manufacture’s recommendation.
The “Off” reading is obtained by measuring the potential of
the coupon while removing it from the cathodic protection
circuit.
Polarization decay and Native potential readings can be
obtained while the coupon is disconnected from the cathodic
protection system.

<<<PAGE 1228>>>

Magellan Midstream Partners, L.P.
CATHODIC PROTECTION CRITERIA 7.04–ADM–006
Asset Integrity 01/01/12 Revision: 2 Page 9 of 9
System Integrity Plan Change Log
Date Change
Location
Chan
ged
By
Approv
ed By
Brief Description of Change
12/1/03 Change Log Rick Wooldridge Michael Pearson Added “Changed By”
12/1/03 Document Rick Wooldridge Michael Pearson Replaced Williams with Company
12/1/03 2.3 Rick Wooldridge Michael Pearson
Deleted, “For newly constructed pipelines or facilities, the
Corrosion Technician shall conduct a complete P/S
survey before application of CP. Mark each spot of
electrode placement
1/1/06 All E7 Michael Pearson 2005 annual review complete – no changes
10/26/06 2.1.1.3, 2.5, 4.7 Rick Wooldridge Michael Pearson Removed references to net protective current
01/01/08 All E7 Rick Wooldridge 2007 annual review complete – no changes
1/1/09 All E7 Rick Wooldridge 2008 annual review complete – no changes
11/17/09 All E7 Rick Wooldridge 2009 annual review complete – minor clean-up changes
8/3/10 All E7 Rick Wooldridge
2010 annual review – This procedure was rewritten to
further clarify Magellan’s process for IR Drop
consideration [including the incorporation of historical
corrosion rates and growth calculations].
1/17/11 Various Larry Davied Rick Wooldridge 2011 annual review, Minor revisions
12/31/11 All 2012 Annual Review complete

<<<PAGE 1229>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 1 of 9
PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for identifying, testing for
and mitigating the harmful effects of interference currents.
2.0 PROCEDURE
2.1 2.1.1 Determining the Need for Interference Current Testing.
2.1.2 2.1.3 Determine the need for interference current testing based on the potential effects on
facilities from foreign DC currents. Primary sources of potential interference are:
2.1.1.1 Static DC current: other (foreign) Cathodic Protection (CP) systems (foreign
usually refers to other companies, but can refer to other systems operated
by the same company, i.e., foreign refers to any system not part of the
system being reviewed/surveyed/examined/tested, etc.)
2.1.1.2 Dynamic DC currents: direct current (DC) operated traction systems, such
as DC railroads, subways, tramways, and mining equipment/carts
2.1.1.3 Stray currents: either static or dynamic, from an unknown source
2.1.1.4 Other sources may include welding operations, railroad signal batteries,
HVDC transmission systems and related ground electrodes, chlorine and
aluminum plants which utilize high DC currents, telluric forces, battery
chargers, etc.
Cathodic protection tests that may indicate potential interference include the following:
2.1.2.1 Low Pipe‐to‐Soil (P/S) potential area tests
2.1.2.2 Hot spot or cell‐to‐cell surveys
2.1.2.3 Line current surveys
Determine the need for interference current testing based on the potential effects of
Company CP systems on foreign facilities. Some reasons for testing are:
2.1.3.1 Request from foreign company
2.1.3.2 Installation of new CP system
2.1.3.3 Significant increase in output of an existing CP system
2.1.3.4 Installation of a new foreign pipeline or facility
2.1.3.5 Installation of a new pipeline or facility
2.1.3.6 Drastic unexplained change in P/S or current readings on CP surveys
2.1.3.7 Installation of new HVDC or HVAC power transmission systems
2.1.3.8 Any other significant change in the environment that might affect CP
current flow/direction/consumption

<<<PAGE 1230>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 2 of 9
2.1.3.9 2.1.4 Potential contributors to the possibility for having interference current
may include:
2.1.3.9.1 Poor to no coating
2.1.3.9.2 High rectifier circuit resistance
Likely areas where interference may be suspect are
2.1.4.1 Pipelines or facilities within the ground bed gradient of a foreign CP system
2.1.4.2 Pipelines or facilities located between a foreign CP system and its
corresponding facility
2.1.4.3 Paralleling or crossing foreign pipelines
2.1.4.4 Buried isolation locations
2.1.4.5 Metallic structures that will provide a low total resistance path for the DC
current in question to complete its electrical circuit
2.2 Testing for and Determining the Effects of Interference Current
NOTE: Whenever possible, all interference testing should be a cooperative endeavor and
performed mutually. Any testing conducted on or from foreign facilities/systems should be
done with the permission and/or jointly with the foreign companies.
NOTE: When possible, coordinate interference testing with local Corrosion Control
Coordinating Committees
2.2.1 2.2.2 Identify all possible foreign static and dynamic DC current sources. (For the purpose of
this procedure, foreign refers to all systems not part of the facility being tested.)
Interrupt each foreign static DC current source and, whenever possible, each dynamic
DC current source while conducting a P/S survey (spot or CIS) over the effected area
(area in question or suspect of interference current discharge). Reference Measuring a
Pipe‐to‐Soil Potential.
1.1.1 NOTE: Use an 80% duty cycle (8 seconds “On” and 2 seconds “Off”) in the
interruption of current sources when checking for interference. The Supervisor of
Corrosion Control may approve other duty cycles.
2.2.3 Analyze the P/S readings from step 2.2.2 of this procedure to determine if:
2.2.3.1 2.2.3.2 2.2.3.3 Interrupted current caused a change in the P/S readings from the Off to On
Interrupted current caused a more negative P/S reading from the Off to On
Interrupted current caused a more positive P/S reading from the Off to On

<<<PAGE 1231>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 3 of 9
2.2.4 2.2.3.4 For each test point, add the P/S potential change (net effect) resulting
from all foreign DC current sources to get the magnitude of the
interference for that point or location:
2.2.3.4.1 If the total effect is Zero, there is no interference
2.2.3.4.2 If the total effect is a negative (‐) figure, the point is a current
pick‐up area
2.2.3.4.3 If the total effect is a positive (+) figure, the point is a current
discharge area
2.2.3.4.4 The magnitude of the total effect will determine whether the
interference must be mitigated or whether it is
inconsequential
To test for foreign dynamic DC currents that can not be interrupted (mostly DC traction
systems), conduct a continuous P/S test at each test point in question per the following
steps.
2.2.4.1 Install a data logger or similar equipment at each location capable of
continuously recording P/S readings for a predetermined time span.
Reference Measuring a Pipe‐to‐Soil Potential.
2.2.4.2 Analyze recorded P/S data that was recorded from step 2.2.4.1 of this
procedure.
2.2.4.2.1 Fluctuating P/S readings with no apparent reason indicates
possible interference. Further review of the recorded data
should be conducted to determine if the fluctuating pattern
can be correlated to local DC operating systems
2.2.4.2.2 Comparing P/S readings from each point taken at the same time
may help to indicate which point is a current pick‐up or
discharge point
2.2.4.2.3 At test points exhibiting fluctuating P/S readings higher than
baseline values may indicate that the point is a current pick‐
up area
2.2.4.2.4 At test points exhibiting fluctuating P/S readings lower than
baseline values may indicate that the point is a current
discharge area
2.2.4.2.5 If the baseline P/S is unknown, it may be determined from the
logged readings taken during the continuous testing
2.2.4.2.6 The magnitude of the difference in the lowest or highest P/S
reading and the baseline P/S reading will determine whether

<<<PAGE 1232>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 4 of 9
2.3 2.4 the interference must be mitigated or whether it is
inconsequential
2.2.5 Locate the unknown interfering DC current source.
2.2.5.1 In order to locate potential areas of interference, one or more of the
following surveys should be conducted:
2.2.5.1.1 Hot spot or cell to cell survey
2.2.5.1.2 Close interval survey
2.2.5.1.3 DCVG survey
2.2.5.1.4 By conducting one of more of the above noted surveys, it
may be possible to locate the point(s) of current
discharge/pickup and/or to track the current to or from its
source
2.2.6 If the attempts to locate or identify the interference source are successful, perform
either step 2.2.2 or step 2.2.4 of this procedure to evaluate the effects of the
interference source.
Determining the Need for Interference Current Mitigation:
2.3.3 Review the data from section 2.2 of this procedure. The magnitude of the interference
will determine whether the interference current must be mitigated or if it will be
considered inconsequential.
2.3.3.1 A shift in the P/S potential reading that results in a potential of ‐1.000 Volt
or more negative, (IR drop free) shall be considered inconsequential,
unless field testing dictates otherwise.
2.3.3.2 A shift in the P/S potential reading that results in a potential between ‐
0.850 volts to –1.000 volts (IR drop free) may require mitigation,
depending upon field testing and site conditions.
2.3.3.3 A shift in the P/S potential reading that results in a potential less than ‐
0.850 volts will require mitigation.
Selecting the Type of Mitigation
2.4.1 Eliminate or reduce the potential for current exchange by physically changing the
environment or facility. Suggested mitigating actions to reduce current exchange
include:
2.4.1.1 Recoat the current discharge areas or current pick‐up areas on the
pipeline/facility in question. Reference Coatings – Selection, Application,
and Maintenance.
2.4.1.2 Install a highly resistive material between the pipeline/facility in question
and the foreign pipeline/facility.

<<<PAGE 1233>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 5 of 9
2.4.1.3 Reduce high rectifier circuit resistance by installing a new groundbed.
Reference Design and Installation of an Impressed Current Deep
Groundbed or Design and Installation of an Impressed Current Surface
Groundbed.
2.4.1.4 Relocate foreign CP groundbed or entire CP system
2.4.1.5 Move electrical isolation devices from below ground to above ground
2.4.1.1 If practical, increase the distance between foreign and Company facilities
2.4.1.2 Improve/repair DC traction systems isolation between rails and the earth
(ballast, ties, padding)
2.4.1.3 Improve/repair DC traction systems electrical connection across rail
ends/joints
2.4.2 Design considerations for mitigating potential interference effects include the following:
2.4.2.1 Design of a CP system with groundbed gradient located outside of any
existing pipeline/facility
2.4.2.2 Design of a groundbed to reduce interference potential. Deep groundbeds
have less potential to cause interference than a conventional/surface
groundbed
2.4.2.3 Route new pipelines/facilities outside any potential interference current
pick‐up area or groundbed gradient. If at all possible, avoid placing a new
pipeline between a foreign groundbed and the structure being protected
2.4.3 Mitigation by electrical bonding
2.4.3.1 Select the appropriate bond type. Some types of bonds are:
2.4.3.1.1 Solid bonds (no control on amount of current or direction of
current)
2.4.3.1.2 Resistance bonds (control on amount of current)
2.4.3.1.3 Diode bonds (control on direction of current)
2.4.3.1.4 Resistance diode bonds (control on both direction and amount of
current)
2.4.3.2 Select a bonding location as close as practical to the current discharge
point or current source.
2.4.3.3 Install cathodic protection cables. Reference Attaching Cathodic Protection
Cables.
2.4.3.4 Install a shunt where practical to provide a means for measuring bond
current direction and magnitude.

<<<PAGE 1234>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 6 of 9
2.4.4 2.4.3.5 Classify the bond as “critical to Magellan, critical to Foreign, or Courtesy
(see definitions)
Mitigation by installing a galvanic anode to serve as a sacrificial discharge or drain point:
2.4.4.1 Locate point of current discharge.
2.4.4.2 Install the galvanic anode(s). Reference Attaching Cathodic Protection
Cables and Standard Drawing – Magnesium Anode Typical Mounting.
2.4.5 Mitigate by installing a new CP system to provide additional CP current to counter the
effects of the interference current. Reference Design and Installation of an Impressed
Current Deep Groundbed or Design and Installation of an Impressed Current Surface
Groundbed.
2.4.5.1 2.4.5.2 Identify a groundbed location within the area of cathodic protection
interference.
Install a groundbed within the area of cathodic protection interference.
1.1.2 NOTE: Groundbeds must be designed and installed so as to avoid
causing interference to other facilities.
2.4.6 Designing Mitigation Bonds
2.4.6.1 Conducting a P/S correction adjustment test.
2.4.6.1.1 Locate the point of maximum interference current discharge
(control test point) using a close interval survey
2.4.6.1.2 Chose the proposed bond location based on accessibility and the
following:
2.4.6.1.2.1 2.4.6.1.2.2 2.4.6.2 2.4.6.3 2.4.6.4 Where the two pipelines cross
Where the two paralleling pipelines come
closest together
2.4.6.1.2.3 Where the pipeline comes closest to a
facility
2.4.6.1.2.4 At a point of ownership with an electrical
isolating kit
Install a temporary shunted resistance bond
Interrupt the interfering current source by installing an interrupter with at
least an 80% duty cycle setting.
Read the interrupted (Off/On) P/S potentials and the interfering bond
current at the control test point.

<<<PAGE 1235>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 7 of 9
2.4.6.5 Start the test with the bond resistance at a maximum, allowing zero bond
current flow.
2.4.6.6 Slowly decrease the bond resistance until the Off/On P/S potential
readings are the same.
2.4.6.7 Measure the bond resistance and then install a resistor as close as possible
to that measured resistance. The current rating of the resistor must be at
least as high as the planned current flow.
2.4.7 Installing Convenience/Courtesy Bonds
2.4.7.1 Install convenience/courtesy bonds for foreign pipelines/facilities,
whereby:
2.4.7.1.1 2.4.7.1.2 2.4.7.1.3 2.4.7.1.4 2.4.7.1.5 CP current is temporarily exchanged when agreed upon by a
foreign pipeline/facility
Sufficient CP current is available
Does not jeopardize the cathodic protection levels of the
providing pipeline/facility
Mutually agreed upon by all parties involved
Reference Attaching Cathodic Protection Cables.
2.7 Documentation
1.1.3 2.7.1 Interference testing data must be documented and recorded on the
Cathodic Protection Interference Test Form.

<<<PAGE 1236>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 8 of 9
System Integrity Plan Change Log
Date Change
Location
Changed
By
Approved
By
Brief Description of Change
12/01/03 Change Log
Rick
Wooldridge
Michael
Pearson Added, “Changed By”
12/01/03 2.0
Rick
Wooldridge
Michael
Pearson
Added, “Note: Testing for interference currents and remedial measures on a
DOT regulated asset is a covered task and should only be performed by those
qualified in accordance with the operator qualification ruling. Reference
Operator Qualification (OQ) ‐ Covered Tasks.
12/01/03 2.1.1
Rick
Wooldridge
Michael
Pearson Deleted, “from “One Calls” or interference testing committees.”
12/01/03 2.1.2
Rick
Wooldridge
Michael
Pearson
Deleted, “Review results of routine cathodic protection surveys and close
interval cathodic protection surveys for signs of possible interference.”
12/01/03 2.1.3
Rick
Wooldridge
Michael
Pearson Deleted, “Review information/notices/reports of installation or intent to
install new foreign CP systems or pipeline/facility.”
12/01/03 2.1.4 Rick
Wooldridge
Michael
Pearson Deleted, “Review new pipeline encroachment reports or notices.”
12/01/03 2.7.2
Rick
Wooldridge
Michael
Pearson
Deleted, “Interference testing data should be electronically transferred to
the Cathodic Protection Data Management System (BASS) for retention and
analysis.”
12/01/03 2.7.3
Rick
Wooldridge
Michael
Pearson
Deleted, “The data should be retained for use in the design and
implementation of any necessary remedial action.”
12/01/03 2.7.4
Rick
Wooldridge
Michael
Pearson
Deleted, “The data shall be considered to be accurate based on the pipe,
cathodic protection, and environmental conditions at the time of the
survey.”
12/01/03 2.7.5
Rick
Wooldridge
Michael
Pearson
Deleted, “Survey data on a particular pipe segment shall no longer be
considered to be representative if there is a significant replacement or
recoating of pipeline or a change in the applied cathodic protection within
the segment.”
12/01/03 2.2.2
Rick
Wooldridge
Michael
Pearson Deleted, “Test for foreign static and dynamic DC current sources”.
12/01/03 5.0
Rick
Wooldridge
Michael
Pearson Deleted “Responsibilities” section as it is not part of the standard format.
1/1/06 All
Rick
Wooldridge
Michael
Pearson 2005 annual review, no changes
01/01/07 All E7
Rick
Wooldridge 2006 annual review, no changes
01/01/08 All E7
Rick
Wooldridge 2007 annual review, no changes
10/14/08 All E7
Rick
Wooldridge 2008 annual review, no changes

<<<PAGE 1237>>>

Magellan Midstream Partners, L.P.
TESTING FOR INTERFERENCE CURRENTS AND REMEDIAL
MEASURES
7.04–ADM–015
Asset Integrity 01/01/11 Revision: 3 Page 9 of 9
11/18/09 All E7
Rick
Wooldridge
2009 annual review; Removed references and links; other minor
modifications
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 1238>>>

Magellan Midstream Partners, L.P.
COATINGS—SELECTION APPLICATION AND
MAINTENANCE PROCEDURE
7.04–ADM–016
Asset Integrity 01/01/10 Revision: 2 Page 1 of 2
PURPOSE
1.1 The purpose of this procedure is to communicate a standardized reference for the
selection, application, and maintenance of coatings used to prevent corrosion.
2.0 PROCEDURE
Selection, Application, and Maintenance of coatings includes both minor coating repairs and major coating
projects. This document and its associated links are intended as a reference for OQ training purposes
and for the development of a Project Scope/Job Plan. They are not intended as a step‐by‐step procedure
or to replace a project specific Job Plan. The specifications below may be used all or in part as required
by the individual Project Manager and assignments to both “Company” and “Contractor” may be applied
accordingly.
2.1 Reference applicable Company protective coating specifications
Atmospheric Coating Standards And Specifications
Plant Applied Fusion Bonded Epoxy (FBE) And Abrasive Resistant Overlays (ARO)
External Coatings For Field Joints, Soil‐to‐Air Interface, and Coating Repairs
2.1.1 2.1.2 2.1.3 2.2 Documentation
2.2.1 Documentation for below ground coatings on pipelines and related facilities is stored in
the Linefill Database system.
2.2.2 Documentation for above ground coatings on pipelines, tanks, and related facilities is
stored in the Atmospheric Corrosion database.
2.2.3 Documentation of coating installation and repairs conducted per this procedure should
be documented Project Plan, Job Book, and/or Pipeline Maintenance Report as
applicable.

<<<PAGE 1239>>>

Magellan Midstream Partners, L.P.
COATINGS—SELECTION APPLICATION AND
MAINTENANCE PROCEDURE
7.04–ADM–016
Asset Integrity 01/01/10 Revision: 2 Page 2 of 2
System Integrity Plan Change Log
Date Change
Location
Changed
By
Changed
By
Brief Description of Change
10/29/03 Change
Log
Rick
Wooldridge
Michael
Pearson Added “changed by” to the change log
Michael Pearson 10/29/03 1.1 Rick
Wooldridge
Replaced “establish” with “communicate”.
Revised paragraph to make it easier to
understand.
10/29/03
2.1,
3.2.1,
3.2.2
Michael Pearson
Rick Wooldridge
Removed “Williams”
Michael Pearson 10/29/03 2.1.1 Rick Wooldridge
Removed THE WILLIAMS COMPANIES
SPECIFICATION 15.11.07 LATEST EDITION
Michael Pearson 10/29/03 2.2.1 Rick Wooldridge
Deleted “Record information concerning
below and above ground coatings on
pipelines and related facilities on the
Maintenance Report.”
10/29/03 2.2.1,
2.2.2
Michael Pearson Rick Wooldridge
Split below ground and above ground data
storage locations to clarify.
Michael Pearson 10/29/03 2.0 Rick Wooldridge
Added “Note: The application of coatings is a
covered task and should only be performed by
those qualified in accordance with the operator
qualification ruling.”
1/1/06 All E7 Michael Pearson 2005 review, no changes
01/01/7 All E7 Michael Pearson 2006 review, no changes
01/01/08 All E7 Rick Wooldridge 2007 review, no changes
09/12/08 All E7 Rick Wooldridge 2008 review, reformatted, minor modifications
11/19/09 All E7 Rick Wooldridge 2009 annual review, minor word changes
8/10/10 All E7 Rick
Wooldridge 2010 annual review; Updated links
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 1240>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for identifying and mitigating
induced AC.
2.0 PROCEDURE
2.1 Determining the need for induced AC testing.
2.1.1 Determine the need for induced AC testing based on the potential effects on facilities
from High Voltage Alternating Current (HVAC). Primary influences of HVAC systems
include: [see NACE RPO177‐2000 for more information].
2.1.1.1 Resistive Coupling
2.1.1.2 Capacitive Coupling
2.1.1.3 Inductive Coupling
2.1.1.4 Power Arc
2.1.1.5 Lightning
2.1.1.6 Switch Surges or other Transients
2.1.2 Tests that may indicate Induced AC include the following:
2.1.2.1 Inadequate Pipe‐to‐Soil (P/S) potential readings
2.1.2.2 AC potential readings
2.1.2.3 Predictive modeling
2.1.3 Likely areas for Induced AC:
2.1.3.1 Pipelines or facilities that enter or exit the electrical gradient of an HVAC
system
2.1.3.2 Pipelines or facilities paralleling in close proximity to an HVAC system
2.1.3.3 Pipelines or facilities in close proximity to an HVAC Sub‐Station
2.1.3.4 Pipelines or facilities in close proximity to HVAC Towers and/or grounding
systems
2.2 Testing for and Determining the Effects of Induced AC
2.2.1 Identify test leads and/or above ground appurtenances to be tested based on
information in 2.1.3 above.
2.2.2 Measure the AC potential using an AC voltmeter. Contact resistance should be
sufficiently low to preclude measurement errors. Suitable references for measurements
include:
2.2.2.1 2.2.2.2 2.2.2.3 A metal rod inserted into the earth until no further increases in AC
potential are noted.
Bare pipeline casings, if adequately isolated from the carrier pipe.
Tower legs or power system neutrals, in close proximity to the affected
structure.

<<<PAGE 1241>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 2 of 5
2.2.2.4 Reference electrodes designed for gathering cathodic protection data (i.e.
half‐cells, permanent reference electrodes, etc.)
CAUTION: Meter connections may present a hazard during switching
surges, lightning strikes, or fault conditions.
2.2.3 Analyze the AC P/S reading from step 2.2.2 of this procedure to determine if soill
resistivity data is required. Criteria includes:
2.2.3.1 AC potentials greater than 10 volt
2.2.3.2 Human shock hazards have been identified (electrical shocks may occur at
a voltage below the 15 volt threshold recommended by NACE, while not
life threatening, mitigation may be necessary to address these shocks.)
2.2.3.3 Areas were AC potentials are cyclic, unstable, or inconsistent over time.
2.2.3.4 Areas were AC corrosion has been identified
2.2.4 If soil resistivity measurements are not required go to 2.7 below.
2.3 Soil Resistivity
2.3.1 Collect soil resistivity measurements at each location as selected per 2.2.3.
2.4 AC Current Density
2.4.1 Using the AC voltage measured in 2.2.2 and the soil resistivity measured in 2.3.1
determine the calculated AC current discharge density per the AC current density
calculator in section 2.4.2. Note: Holiday size should be selected based on the typical
holiday size expected on the pipeline.
2.4.2 AC Current Density Calculator
Calculating AC Current Density
Inputs
AC Voltage 10 volts
Soil Resistivity 5000 ohm-cm
Holiday Size 6 cm2
AC Current Density 18.42633309 A/m2
AC Corrosion Potential
AC corrosion not likely
Cathodic Protection Criteria
100mv polorization
AC Mitigative Action
No action required
AC Voltage Measured or calculated
Soil Resistivity Measured or expected

<<<PAGE 1242>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 3 of 5
2.4.3 2.4.4 2.4.5 The AC Current Density Calculator utilizes the relationship between the AC driving
voltage, soil resistivity, and the estimated size of the coating holiday from which current
can discharge, to estimate the discharge density. Where a more precise current
discharge density is required coupon test stations should be installed.
Determine the potential for AC corrosion
2.4.4.1 AC Current Density <20 A/m2 = AC Corrosion not likely
2.4.4.2 AC Current Density >20 A/m2 but <100 A/m2 = AC Corrosion unpredictable
2.4.4.3 AC Current Density >100 A/m2 = AC Corrosion is likely
Determine the need for mitigative action (see AC current density calculator in section
2.4.2)
2.4.5.1 2.4.5.2 2.4.5.3 2.4.6 AC Current Density <20 A/m2 = No action required
AC Current Density >20 A/m2 = Action required
Rule of Thumb: When the AC potential, in millivolts (mV), is greater than or
equal to the resistance of the soil, in ohm‐cm; a more detailed analysis
and/or mitigation is typically required.
Determine the criteria for cathodic protection ((see AC current density calculator in
section 2.4.2)
2.4.6.1 2.4.6.2 2.5 2.6 AC Current Density <20 A/m2 = 100 mV polarization
AC Current Density >20 A/m2 but <500 A/m2 = 150 mV to 250mv
polarization
2.4.6.3 AC Current Density >500 A/m2 = Cathodic protection is not effective in
mitigating corrosion
Mitigative Action – Cathodic Protection can be effective at mitigating AC corrosion
2.5.1 Measure and/or calculate the target ON potential for each test point within the area
affected by Induced AC.
2.5.1.1 Target ON is the potential, with current applied, where polarization equal
to the native potential, plus the cathodic protection criteria established in
2.4.6 is achieved.
2.5.2 Document the Target ON potential in the Corrosion Database (CPDM).
2.5.3 Utilize the target ON potential as the criteria for cathodic protection. This criteria may
be used as long as there are no significant changes in the environment, structure,
coating, cp systems, etc.
2.5.4 Supplemental cathodic protection and/or coating rehabilitation will be required if the
adequate cathodic protection potentials are not achieved.
Mitigative Action – In addition to adequate cp as defined in 2.5, managing the negative effects
from Induced AC or lightning is accomplished by reducing the interference voltage and/or
providing a path to ground for damaging current.
2.6.1 Select and install the appropriate grounding equipment. This equipment may include:
2.6.1.1 Grounding rods (typically made of zinc, copper, graphite or cast‐iron)

<<<PAGE 1243>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 4 of 5
2.6.1.2 2.6.1.3 installed where the pipeline enters and exits the electrical gradient of a
HVAC system and at select locations where the pipeline parallels the
HVAC system.
Grounding ribbons (typically made of zinc or copper) installed parallel
with and directly connected to the pipeline along the distance where the
pipeline is influenced by the HVAC system.
Ground mats (typically made of zinc or copper) should be installed at
valves, metallic vents, cathodic protection test stations, and other above
ground appurtenances where electrical contact with the affected
structure is possible. Grounding mats should be large enough to extend
beyond the area on which a person may be standing when contacting the
affected structure and close enough to the surface that step and touch
potentials are adequately reduced.
NOTE: If the ground rod material used has a native voltage potential
less negative than the ‐1 volt (as compared to copper‐copper sulfate
electrode) an isolation device must be installed to block the flow of DC,
while passing AC. Caution is advised when using grounding material
with a native potential more negative than the pipeline as the ground
will be anodic to the pipeline and thus corrode.
2.6.1.4 2.6.1.5 Where AC surge currents or lighting is a concern, electrical bonds
designed to pass AC, should be installed across insulating flanges to
prevent arcing.
Groundbeds utilized for cathodic protection of the pipeline or facility will
provide mitigative grounding as described above. However, precautions
should be taken to protect the electrical equipment and wiring from
lighting and surge current damage.
3.0 MONITORING
3.1 Induced AC and lightning mitigation equipment should be monitored to ensure its continued
effectiveness.
3.2 In areas where induced AC currents have been identified, coupon test stations should be
installed and monitored.
4.0 DOCUMENTATION
4.1 Data collected as part of this procedure shall be documented in appropriate sections of the
Corrosion Control database (CPDM).

<<<PAGE 1244>>>

Magellan Midstream Partners, L.P.
TESTING FOR INDUCED AC AND REMEDIAL MEASURES 7.04‐ADM‐023
Asset Integrity 1/1/12 Revision: 1 Page 5 of 5
System Integrity Plan Change Log
Date Change
Location
Changed
By Brief Description of Change
Approved By
12/06/06 NEW
Rick
Woolridge
Michael
Pearson
New procedure
01/01/08 All E7
Rick
Wooldridge
Reviewed, no changes
All E7 1/1/09
Rick
Wooldridge
2008 annual review complete – no changes
All E7 01/01/10
Rick
Wooldridge
E7 Review; no changes
All E7 01/01/11
Rick
Wooldridge
E7 Review, no changes
9/28/11 2.2.3.1
John
McMahan
Rick
Wooldridge
E7 Review; Changed 1 volt to 10 volts
12/31/11 All 2012 Annual Review complete

<<<PAGE 1245>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized process for safely marking the
Company rights‐of‐way (ROW) with permanent line markers, in order to:
1.1.1 1.1.2 1.1.3 1.1.4 Meet all applicable DOT requirements.
Effectively delineate the pipeline corridor.
Promote public and community awareness.
Identify the pipeline location for effective damage prevention.
2.0 SCOPE
2.1 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on non‐jurisdictional assets as deemed
appropriate.
2.2 Assets covered per the Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, other specific marker
requirements may be stated within the Mitigation Plan. Refer to the Mitigation Plan for those
requirements.
2.3 Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree. For the period of the Consent Decree,
these systems will follow the applicable process and procedures (see Consent Decree for
applicable programs).
3.0 PROCEDURE
3.1 Consider using the most appropriate marker type, as dictated by the existing conditions.
3.1.1 3 inch PVC schedule 40 pipe with 3” cap, black/red color coded decal six inches from top
of post, with warning decal or warning sign as appropriate. Refer to the Standards List.
3.1.2 Flexible fiberglass composite markers.
3.1.3 Bullet style markers.
3.2 The following special tools/equipment/materials as required for permanent pipeline marking:
3.2.1 Applicable assembled marker post or marker.
3.2.2 Pipeline Warning Decals. Refer to the Standards List.
3.2.3 “Pipeline Under Pavement” decals/or signs where applicable.
3.2.4 Color‐coded decals or stickers.
3.2.5 Signs must include “Warning” followed by “Petroleum Pipeline” with letters at least 1
inch high with an approximate stroke of ¼ inch, Company name and 24 hr phone
number.
3.2.6 Posthole digger.
3.2.7 Shovel.
3.2.8 Appropriate post driver.

<<<PAGE 1246>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 2 of 5
3.2.9 Auger.
3.3 Markers must be placed and maintained over each buried pipeline at the following locations:
3.3.1 Each public road crossing.
3.3.2 Each railroad crossing.
3.3.3 Where the line is above ground in areas that are accessible to the public
3.3.4 In sufficient numbers along the remainder of each buried line so that its location is
accurately known. Where practical and appropriate, use the following guidelines to
establish locations for additional pipeline marker placement:
 Interior cross fences
 Both sides of creeks and rivers
 Both ends of all pipeline exposures
 Developed area, commercial and residential
 Vast areas with few fences or areas with changing elevations that limits marker
visibility.
 Markers should not be placed in an area that impedes and/or prevents landowners
or tenants (e.g. ranchers, farmers businesses, etc.) from conducting daily activities,
or where prohibited by local ordinances. These are best handled on a ‘case by case’
basis; consult immediate Supervisor with questions or unique circumstances.
3.4 Installation of Pipeline Markers:
3.4.1 When applicable, notify landowner prior to entering property.
3.4.2 When excavating activities are required pertaining to installation of marker posts, follow
applicable state One Call regulations. (i.e. use of an auger or posthole digger, etc.)
3.4.3 Locate pipeline per Pipeline Locating Procedure.
3.4.4 Dig post hole for 3” post or drive markers as appropriate.
3.4.5 When required, install milepost numbers directly below warning decal or warning sign
(at road crossings and valve sites).
3.4.6 For pipelines paralleling roadways located under the surface of the roadway where
marker placement is not practical, markers should be placed at the nearest location
adjacent to the pipeline and a “pipeline under pavement” decal placed beneath the
existing Company warning decal.
3.4.7 Pipeline markers will be placed as close to the line as possible, however, when a marker
is offset a greater distance than five feet from the pipeline; notify the appropriate Asset
Integrity Supervisor.
3.5 Assets covered per the Mitigation Plan:
3.5.1 3.5.2 All markers shall be within line of sight of one another in Tier I Areas.
If one marker is removed, the location of the pipeline can still be identified from either
direction from any point in between Tier II and Tier III Areas

<<<PAGE 1247>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 3 of 5
3.6 3.5.3 3.5.4 3.5.5 3.5.6 3.5.7 3.5.8 All line markers will be written in English and Spanish.
Marker placement and density will be evaluated routinely through aerial and ground
surveillance.
Missing and damaged markers will be replaced within seven days of discovery.
Markers will be located at all aboveground facilities to identify the operator of the
system.
When practical fence crossings will have fence post on either side painted bright yellow
to aid in the identification of the pipeline easement width.
Documentation will be completed using Mitigation Right of Way Inspection Form,
making appropriate comments including: Stationing, GPS coordinate (where possible),
land use change or increased density due to Tier I, Tier II and Tier III requirements, etc.
Install aerial milepost markers on jurisdictional lines that are patrolled by aerial methods as
follows:
NOTE: Aerial Markers are for reference only and may not reflect exact stationing.
3.6.1 3.6.2 3.6.3 3.6.4 3.6.5 3.6.6 Construct Aerial Markers on a triangle framework with mile number identified facing up
and down stream. Numbers should be of sufficient size to be seen by aerial patrol pilots
with the number being black on a yellow background. Refer to the Standards List.
Use heavy gauge aluminum or fiberglass, with decal numbers and arrows.
Aerial marker numbers should be assigned to match the nearest milepost number as
documented on alignment sheets.
Place along all mainline ROW, positioned so that they are legible as a pilot flies the line.
Place at public road crossings or other appropriate points (distance between markers
generally not to exceed one mile).
Use special markers with arrows slanted left, right or vertical to direct pilot around
locations requiring deviation of flight.

<<<PAGE 1248>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 4 of 5
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
010/01/05 Reviewed, no changes
Troy Bronson 01/01/06 2.2.7
Replaced “Examples of universal wastes include lead acid batteries, pesticides,
thermostats with liquid mercury, and florescent light bulbs.” With “Pipeline
markers will be placed as close to the line as possible, however, when a marker is
offset a greater distance than 5’ from the pipeline, a Maintenance Report will be
generated documenting the placement and reason why.”
01/01/06 2.4.1 Troy Bronson Added “Follow applicable state one‐call regulations pertaining to installation of
marker posts.”
01/01/06
Troy Bronson 2.5.1
Replaced “Numbers on signs to be 4” X 6” with the number being black on a
yellow background.” With “Numbers should be of sufficient size to be seen by
aerial patrol pilots with the number being black on a yellow background.
Recommended size of the sign is 6” x 15” with numbers 4 ½ ” x 13 ½ “.”
01/01/06 2.5.5 Troy Bronson Removed note box: When more than 1 pipeline mile is traveled and a public road
is passed without seeing a marker, the marker is considered to be missing.
01/01/06 4.2.1 Troy Bronson Added Line Locating link
01/01/06 2.2.2 Troy Bronson Added “where applicable”.
01/01/06 Applicability Dan Egner Added complete section
01/01/06 1.0 thru 1.1.4 Dan Egner Major modification
01/01/06 2.1 thru 2.1.3 Dan Egner Major modification
01/01/06 2.2.1 Dan Egner Changed to “Applicable markers”
01/01/06 2.2.9 Dan Egner Added “appropriate”
01/01/06 2.3.1 Dan Egner Removed “railroad”
01/01/06 2.3.2 Dan Egner Added “Both sides of all railroad crossings”
01/01/06 2.3.3 Dan Egner Added “appropriate and practical”
01/01/06 2.3.6 Dan Egner Added complete subpart
01/01/06 2.2.6.1 Dan Egner Added for the Consent Decree
01/01/06 2.3.10 thru
2.3.15
Dan Egner Added for the Longhorn Pipeline
01/01/06 2.4.1 Dan Egner Added “where applicable”
01/01/06 2.5.7 Dan Egner Removed (…”only”) added (…”and valve sites”)
01/01/06 2.6 Dan Egner Added NOTE:
01/01/06 2.6.3 Dan Egner Major modification
01/01/06 2.7 thru 2.7.1 Dan Egner Added subparts
01/01/06 2.8 thru 2.8.3 Dan Egner Added subparts
01/01/06 2.9 thru 2.9.2 Dan Egner Added subparts
01/01/06 4.1.2 Dan Egner Added regulation
01/01/06 4.3.2 Dan Egner Added form
01/01/06 5.5 Dan Egner Added definition
01/01/06 Removed references, renamed links
02/01/06 3.3 Clyde Clausen Added section 3.3
02/01/06 3.4 Clyde Clausen Modified section 3.4
02/01/06 3.5 & 3.6 Clyde Clausen Added 3.5 and 3.6 (Consent and Longhorn Specific)
02/01/06 3.7 Clyde Clausen Modified paragraph 3.7
02/01/06 3.8 Clyde Clausen Deleted and incorporated into 3.7
02/01/06 3.9 Clyde Clausen Deleted and incorporated into 3.5

<<<PAGE 1249>>>

Magellan Midstream Partners, L.P.
PIPELINE MARKING PROCEDURE 7.05–ADM–002
Asset Integrity 01/01/10 Revision: 7 Page 5 of 5
2/3/06 3.2.3 Troy Bronson Changed “sign” to “decal”.
2/3/06 3.2.5 Troy Bronson Deleted “Cordless Drill”
2/3/06 3.7.7 Troy Bronson Insert “standards” link.
2/3/06 3.7.8 Troy Bronson Changed “Sign” to “Decal”.
2/3/06 3.7.9 Troy Bronson Changed “Sign” to “Decal”.
2/3/06 3.7.10 Troy Bronson Changed “contact” to “notify”.
1/1/07 3.7 Greg Walker Link to Pipeline Locating Procedure
5/22/07 3.0 Greg Walker Consolidate procedures. Added information about Warning sign details.
5/22/07 3.3.4 Greg Walker Added clarification where markers should be placed.
12/12/08 2.3 Tim Boudreaux Modified the Consent Decree statement to exclude the previous Consent Order.
12/12/08 4.0 Tim Boudreaux Deleted Pipeline Marker Repair report form link.
12/12/08 4.4 Tim Boudreaux Included Longhorn Mitigation Plan.
01/01/2009 Tim Boudreaux Conducted annual review with no changes.
01/01/2009 3.5.7 Tim Boudreaux Included Longhorn specific documentation requirements.
3‐26 3.5.6 Greg Walker Included Longhorn specific documentation requirements.
9/01/09 2.2 Tim Boudreaux Deleted Longhorn Specific
9/01/09 3.5 Tim Boudreaux Changed Longhorn Specific to Assets covered per Mitigation Plan
9/01/09 3.5.8 Tim Boudreaux Deleted Longhorn
9/01/09 4.4 Tim Boudreaux Deleted Longhorn
9/01/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual review complete – no changes

<<<PAGE 1250>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM 7.05–ADM–003
Pipeline Integrity 01/01/12 Revision: 7 Page 1 of 6
1.0 PURPOSE
1.1 The purpose of this program is to safely maintain Company pipeline rights‐of‐way, in order to
comply with DOT requirements (Line Markings); (Inspection of Rights‐of‐Way) and Transmission
Lines: Patrolling.
2.0 SCOPE
2.1 This program is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on nonjurisdictional assets as deemed
appropriate.
2.2 Assets covered per the Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, other specific right of way
maintenance requirements may be stated within the Mitigation Plan. Refer to the Mitigation
Plan for those requirements.
2.3 Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Magellan guidelines, process, or best practices, Magellan’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree, (see Consent Decree for applicable
programs).
3.0 DESCRIPTION
3.1 The Right‐of‐Way Maintenance Program is a systematic and comprehensive method to
effectively manage pipeline rights of way maintenance as related to :
3.1.1 Locating Line: The Pipeline Locating Procedure covers locating underground pipeline
facilities for any reason. These may include, but not limited to One Call Program, line
locates, Right of Way marking, clearing, mowing, spraying, surveying, inspection, or any
maintenance or damage prevention activity.
3.1.2 Marking the line. The Pipeline Marking Procedure covers temporary or permanent
mainline facility marker requirements and placements in order to raise public awareness
of the location and type of underground facility and therefore reduce the risk of
accident, injury or damage.
3.1.3 Pipeline surveillance, ground and aerial surveillance. The Inspection of Right‐of‐Way
Procedure covers DOT regulated pipeline surveillance for Refined Product, NGL and
3.1.4 Natural Gas transportation facilities.
Clearing Right of Way. The Right‐of‐ Way Clearing Procedure covers major vegetation
3.1.5 clearing activity along Company mainline right of way corridors.
Mowing Right of Way. The Right‐of‐Way Mowing Procedure covers moderate
3.1.6 vegetation clearing activity along Company mainline right of way corridors, as well as
vegetation control at road crossings.
Spraying Right of Way. The Right‐of‐Way Spraying Procedure covers vegetation control
3.1.7 activity using herbicidal applications along Company mainline right‐of‐way corridors, as
well as vegetation control at road crossings.
Identification and Managing Encroachments. The Encroachment Process and the
Encroachment Guidelines aid in identifying, mitigating and documenting easement
encroachments along the Company transportation facilities rights‐of‐way.

<<<PAGE 1251>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM 7.05–ADM–003
Pipeline Integrity 01/01/12 Revision: 7 Page 2 of 6
4.0 PROGRAM
4.1 Gather Right of Way Data
4.1.1 4.1.2 Gather pertinent data for evaluating and managing right‐of‐way and included in the
spreadsheet and/or electronic filing system (database). Pertinent data includes, but is
not limited to; line segment, geographical location, condition of right‐of‐way, type of
vegetation, maintenance needs, maintenance history, risk score, etc. The appropriate
procedure listed above should be reviewed to ensure complete data is acquired for each
type of maintenance activity.
Conduct training, for Assets covered per the Mitigation Plan, on Endangered and
Threatened Species and their Habitats for all third party contractors. Coordination of
4.1.3 clearing activities and use of the biologist developed maps depicting the location and
habitats of endangered species should be utilized to avoid or minimize adverse effects
during this maintenance activity.
Obtain pertinent data through aerial surveillance or ground surveillance (walking the
line) depending on specific requirements. Annually, a company representative will
accompany the aerial patrol pilot to identify areas where excavation activity or leak
detection cannot be identified by air. Annual inspections should be performed during
high vegetation growth months in order to effectively identify these visibility issues, The
results of the annual inspection should be documented on the Right of Way Inspection
and Assessment Form and copies sent electronically to the appropriate Right of Way
4.2 4.3 Initiative Manager and Field Supervisor.
Assess the Right of Way Data
4.2.1 Develop a plan to systematically address areas of concerns and properly maintain the
right‐of‐way, after all pertinent data regarding the right‐of‐way condition has been
collected and entered into the Right of Way Inspection and Assessment Form.
4.2.2 Prioritize the plan on the following factors (but not limited to):
4.2.2.1 Prioritization scores based on annual inspections (aerial or ground patrols)
regarding ability to clearly identify and view surface conditions.
4.2.2.2 Concerns or comments from previous regulatory audits or
inspections or specific regulatory mandated requirements imposed
for pipeline section operations.
4.2.2.3 Accessibility for operations and maintenance personnel.
4.2.2.4 Third party activity trends (based on One Calls).
4.2.2.5 Real Estate Services commitments or concerns.
4.2.2.6 Accurate and visible marking of the lines.
Mitigation Planning for Right of Way Maintenance:
4.3.1 Develop plans to address areas of concerns on a prioritized basis; highest priority areas
receive attention first. Optimum time of year (season) or specific facility requirements
such as, the Mitigation Plan, may affect this plan.
4.3.1.1 Assets covered per the Mitigation Plan: Ground cover will be mowed to a

<<<PAGE 1252>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM 7.05–ADM–003
Pipeline Integrity 01/01/12 Revision: 7 Page 3 of 6
4.4 4.3.2 4.3.3 4.3.4 4.3.5 4.3.6 4.3.7 level so that all pipeline markers, including painted fence posts, will
be visible from the air and while standing on the ground. High
canopy vegetation will be cleared or trimmed to the extent
necessary to allow clear visibility.
Address both the short‐term and long‐term needs for proper right‐of‐way maintenance
in the plans.
Solicit bids and costs estimates for the plan. Consult herbicidal manufactures for
assistance in identifying the proper herbicides and application methods for various
geographical areas.
Submit plan to the initiative manager or proper authority for approval.
Submit plan to Pipeline Integrity for inclusion into Area Integrity Plan.
Update and revise the right‐of‐way plan systematically as information is received and
processed.
Consult Environmental Specialists and Pipeline Integrity Real Estate Representatives
before implementing initial clearing projects.
Right of Way Maintenance Execution
4.4.1 Follow Project Life Cycle as related to maintenance projects which include, but are not
limited to:
4.4.1.1 Assign a Project Manager.
4.4.1.2 4.4.1.3 4.4.1.4 4.4.1.5 Initiate the Right of Way Review.
Develop a project plan and scope and submit to all stakeholders for
review prior to starting the maintenance.
Make contacts with the landowners prior to starting the
maintenance on the property.
Complete the maintenance and all documentation associated with
the project and submit all completion reports to the Pipeline
Integrity Coordinator.
5.0 REFERENCES
5.1 Related Policies/Procedures
5.1.1 One Call Program
5.1.2 Pipeline Locating Procedure
5.1.3 Pipeline Marking Procedure
5.1.4 Inspection of Right‐of‐Way Procedure
5.1.5 Right‐of‐ Way Clearing Procedure
5.1.6 Right‐of‐Way Mowing Procedure
5.1.7 Right‐of‐Way Spraying Procedure
5.1.8 Encroachment Process

<<<PAGE 1253>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM 7.05–ADM–003
Pipeline Integrity 01/01/12 Revision: 7 Page 4 of 6
Endangered and Threatened Species and their Habitats
Right of Way Inspection and Assessment Form
5.1.9 Encroachment Guidelines
5.1.10 Mitigation Plan
5.1.11 5.1.12 Project Life Cycle
5.2 Forms and Attachments
5.2.1 07‐Form 1585 5.2.2 07‐Form‐1583 On Ground Right of Way Assessment Worksheet
5.2.3 07‐Form‐7035 Encroachment Agreement (Short Form)
5.2.4 07‐Form‐1581 Pipeline Maintenance Report
6.0 DEFINITIONS
6.1 Jurisdictional Lines: Pipeline segments falling under the jurisdiction of a state (i.e., Texas
Railroad Commission or PSC) and/or federal regulating authority (i.e., Department of
Transportation).
6.2 Spraying: The practice of applying herbicides to control undesirable vegetation growth.
6.3 Mowing: The practice of utilizing various light equipment, such as, mowers, brush hog, weed
eater, hand thrasher, etc. to clear right of way of moderate vegetation.
6.4 Clearing: The practice of utilizing heavy equipment, such as dozers, track hoes, chippers,
shredders, hydro axes, chainsaws, etc. to clear right of way of heavy vegetation.

<<<PAGE 1254>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM 7.05–ADM–003
Pipeline Integrity 01/01/12 Revision: 7 Page 5 of 6
System Integrity Plan Change Log
Date Change Location Change By Brief Description of Change
12/22/03 1.0 Clyde Clausen Deleted Purpose, Inserted Objective
12/22/03 1.1 Clyde Clausen Deleted the purpose of this procedure is
12/22/03 2.2.9 Clyde Clausen Inserted Pipeline Integrity Real Estate Representatives
12/22/03 3.2 & 3.3 Clyde Clausen Deleted 3.2 and 3.3
10/28/05 1.0 Tim Boudreaux Deleted Objective and included Purpose
Tim Boudreaux Included the purpose statement
10/28/05 1.1
Tim Boudreaux 10/28/05 2.0, 3.0, 4.0
Included all new program description, including the sub‐numbered
sections
11/10/05 Header Tim Boudreaux Included the Applicability statement in the opening Paragraph.
11/16/05 1.0 Tim Boudreaux Complete rewrite of Purpose section.
11/16/05 2.0 Tim Boudreaux Included all of Description section.
11/17/05 3.0 Tim Boudreaux Rewrite all of Program document in this section.
11/17/05 4.0 Tim Boudreaux Included regulatory numbers and all policy/procedure and form links.
11/17/05 5.0 Tim Boudreaux Included definitions for clearing, mowing, visibility and accessibility.
01/01/07 Reviewed, no changes
10/30/07 All Tim Boudreaux Conducted 2007 Annual Review see change log
10/30/07 4.1.4 Tim Boudreaux Included text on Annual Aerial Patrol Surveys.
10/30/07 4.2.2.1 Tim Boudreaux Changed the paragraph to include Prioritization scores.
10/30/07 4.2.2.3 Tim Boudreaux Eliminated Aerial Patrol comments.
10/30/07 5.2.2 Tim Boudreaux Included Aerial Patrol Annual Inspection Form.
10/30/07 5.2.3 Tim Boudreaux Included On Ground Right of Way Assessment Worksheet.
12/19/08 2.3 Tim Boudreaux Modified Consent Decree Specific.
12/19/08 4.1 Tim Boudreaux Deleted all of previous 4.1.3 Consent Decree Specific.
12/19/08 4.3.1 Tim Boudreaux Deleted reference to CV02‐1178.
12/19/08 5.1.12 Tim Boudreaux Deleted link to CV02‐1178.

<<<PAGE 1255>>>

Magellan Midstream Partners, L.P.
RIGHT‐OF‐WAY MAINTENANCE PROGRAM Pipeline Integrity 01/01/12 12/19/08 5.1.13 Tim Boudreaux 12/19/08 5.1.14 Tim Boudreaux 12/19/08 6.5 Tim Boudreaux 12/19/08 6.6 Tim Boudreaux 01/01/09 Tim Boudreaux 4/3/09 4.3.1.1 Tim Boudreaux 9/01/09 2.2 Tim Boudreaux 9/01/09 4.1.2 Tim Boudreaux 9/01/09 4.3.1 Tim Boudreaux 9/01/09 5.1.10 Tim Boudreaux 9/01/09 Tim Boudreaux 9/02/10
5.2.6, 5.2.7, 5.2.8,
5.2.9, 5.2.10, 5.2.11,
5.2.12, 5.2.13
Tim Boudreaux 9/02/10 Tim Boudreaux 9/02/11 4.1.3 Dennis Vasicek
9/02/11 4.2 Dennis Vasicek
9/02/11 4.3.7 Dennis Vasicek 9/02/11 5.2 Dennis Vasicek
12/31/11 All 7.05–ADM–003
Revision: 7 Page 6 of 6
Deleted link to On the Ground Survey (OTG).
Deleted line to Line of Sight Survey (LOS).
Deleted definition for Visibility (no longer valid).
Deleted definition for Accessibility (no longer valid).
Annual Review with no changes.
Added Longhorn Commitment
Deleted Longhorn, added Assets covered per the Mitigation Plan
Deleted Longhorn
Deleted Longhorn
Deleted Longhorn
Annual Review with changes listed above
Deleted links to all PL forms
Annual Review with changes listed above
Replaced reference to “Aerial Patrol Annual Inspection
Form” with “Right of Way Inspection and Assessment
Form”. Revised distribution list for the Right of Way
Assessment Form. Deleted last three sentences.
Replaced, “a spreadsheet or electronic filing system”
with, “the Right of Way Inspection and Assessment
Form.”
Added Environmental Specialists
Removed, “07‐Form‐1574 Inspection of Right of Way
Report” and “07‐Form 1584 Aerial Patrol Annual
Inspection Form”. Added, “07‐Form‐1585 Right of Way
Inspection and Assessment Form”
2012 Annual Review complete

<<<PAGE 1256>>>

Magellan Midstream Partners, L.P.
DEPTH OF COVER PROGRAM 7.05–ADM–009
Asset Integrity 01/01/11 Revision: 4 Page 1 of 4
1.0 PURPOSE
1.1 The purpose of the Depth of Cover (DOC) Program is to manage risks associated with
areas of shallow or exposed pipe and earth movements along the Company’s pipeline
system.
1.1.1 1.1.2 1.1.3 The DOC program is an on-going process. Land use, population density,
environmental issues and changes to the absolute depth of cover are expected
to change over time. Consequently, depth of cover data will become outdated as
land uses change, land erosion occurs and topsoils are moved over time as a
result of wind, rain and mechanical forces. Continual monitoring of these
changes is performed through Depth of Cover Surveys, Aerial Patrols, In-Line
(Smart Pig) Inspections, One-Calls and Line Spotting.
Secondly, through a formalized DOC Mitigation Process, this Program intends to
manage the associated risks through a variety of methods, all designed to reduce
the likelihood of unintended outside force damage and consequential damages to
a defined level.
The DOC Program prioritizes those areas of highest relative risk. The
investigative and resulting mitigation processes will consequently focus on High
Consequence Areas (HCAs) and then the Non-HCAs. Furthermore, as HCAs
are modified over time due to changing population and environmental concerns,
the DOC prioritizations will also be modified. Assets covered per Mitigation Plan
(pg. 96 section 3.5.8 Item 3) specifically states the investigative and resulting
mitigation processes will consequently focus on the defined areas of
hypersensitive (Tier III), sensitive (Tier II), and other (Tier I), in descending order.
2.0 SCOPE
2.1 2.2 2.3 This procedure is applicable to federal and/or state jurisdictional pipelines and/or
facilities. Elements of this program may be utilized in whole or part on nonjurisdictional
assets as deemed appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices. This pipeline
system operates under the requirements of the Mitigation Plan.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations,
as well as Company guidelines, process, or best practices, the Company’s Consent
Decree Pipeline Systems operate under the requirements of the Consent Decree. For
the period of the Consent Decree, these systems will follow the applicable process and
procedures (see Consent Decree for applicable programs).
3.0 PROGRAM ELEMENTS
3.1 Shallow and Exposed Pipe
3.1.1 Shallow and exposed pipe locations are identified, prioritized, and mitigated in
accordance with Depth of Cover Procedure. A review of the pipeline as defined in
Section 6 of the IMP will be conducted, to be followed by a re‐assessment interval
recommendation per Section 7 of the IMP.
3.1.1.1 Aerial patrols, operational activities, public input and other means may
require depth of cover surveys based upon land use, environmental
concerns, population density, and construction and excavation activity
levels.

<<<PAGE 1257>>>

Magellan Midstream Partners, L.P.
DEPTH OF COVER PROGRAM 7.05–ADM–009
Asset Integrity 01/01/11 Revision: 4 Page 2 of 4
3.1.1.2 Depth of cover surveys will be conducted in accordance with the Depth of
Cover Procedure.
3.1.1.3 Communication to landowners, tenants, developers and local authorities
will be conducted as necessary to ensure an appropriate awareness of the
location and risks of the pipeline and to coordinate appropriate pipeline
adjustments in anticipation of and in connection with construction and
development activities.
3.2 Earth Movement
3.2.1 Risks associated with Earth Movement are identified and assessed per the Company Risk
Assessment Methodology book, and include factors such as landslide potential, seismic
activity, scour, and history of earth movement.
3.2.1.1 Any areas of the pipeline identified as having high susceptibility to earth
movement factors or where earth movement has been identified will be
investigated and monitored per the Earth Movement Inspection
Procedure.
3.2.1.1.1 3.2.1.1.2 Initial investigation of areas identified as having high
susceptibility to earth movement will be conducted within
one year.
Reinspection and/or monitoring of areas identified as having
high susceptibility to earth movement or where earth
movement has been identified will be conducted per the
Earth Movement Inspection Procedure.
3.2.1.2 If earth movement is determined to be present, a review of the pipeline as
defined in Section 6 of the IMP will be conducted, to be followed by a re‐
assessment interval recommendation per Section 7 of the IMP.
3.2.1.3 Action items identified during the execution of the Earth Movement
Inspection Procedure or through Section 6, Risk Analysis will be
documented and tracked in the Asset Integrity Plan.
3.3 Navigable Waterway Crossing Inspections
3.3.1 Navigable River crossing inspections are conducted in accordance with the Navigable
River Inspections Procedure.
3.3.1.1 Navigable waterways are derived from the Bureau of Transportation
Statistics National Waterways Network database.
3.4 Overhead Pipeline Crossing
3.4.1 The purpose is to effectively manage Overhead Pipeline Crossing maintenance
through a comprehensive risk-based program which identifies risk reduction
projects to improve structural component integrity.
3.4.1.1 Each Overhead Pipeline Crossing structure will receive an initial risk
prioritization number based on the Pipeline Risk Model. The first phase of
the inspections will include the top 20% of the structures listed as highest
risk based on historical water flow events, proximity to HCA’s, and
historical structural knowledge. All other structures will follow (20%) per

<<<PAGE 1258>>>

4.0 Magellan Midstream Partners, L.P.
DEPTH OF COVER PROGRAM 7.05–ADM–009
Asset Integrity 01/01/11 Revision: 4 Page 3 of 4
year, not to exceed six years. Reinspections will start over upon completion
and will be conducted per the Overhead Pipeline Crossing Inspection
Procedure.
3.4.1.2 Overhead Pipeline Crossing Inspections are conducted in accordance with
the Overhead Pipeline Crossing Inspection Procedure.
3.4.1.3 Maintenance will be performed on structures following the Overhead
Pipeline Crossing Inspections as necessary per the Overhead Pipeline
Crossing Inspection Procedure.
DATA MANAGEMENT AND INITIATIVE IMPLEMENTATION
4.1 Data initially obtained and periodically updated via the DOC program will be centralized and
maintained in the DOC database.
4.2 Pipeline Integrity will further manage the recommendation and funding process associated with
the implementation of DOC mitigation initiatives.
4.3 Action items associated with the DOC program will be documented and tracked in the Asset
Integrity Plan.

<<<PAGE 1259>>>

Magellan Midstream Partners, L.P.
DEPTH OF COVER PROGRAM 7.05–ADM–009
Asset Integrity 01/01/11 Revision: 4 Page 4 of 4
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
1/09/04 1.2.2 Tim Boudreaux Included Navigable River inspections paragraph.
1/09/04 2.1.3.2 Tim Boudreaux Excluded Certified letters and maps.
1/09/04 2.1.4.3 Tim Boudreaux Replaced “WES” with “MMP”
1/09/04 3.1.1.1 – 3.1.1.3 Tim Boudreaux Modified the prioritization definitions with the current updated version.
1/09/04 4.1 Tim Boudreaux Deleted “ORA”.
1/09/04 5.1.7 Tim Boudreaux Included a link to the Navigable River Inspection procedure.
12/17/04 1.1 Tim Boudreaux Change text and included Earth Movement Statement.
12/17/04 1.1.1 Tim Boudreaux Changed text to: “is an on-going process”
12/17/04 1.2 Tim Boudreaux Changed numbering format.
12/17/04 1.2.1 Tim Boudreaux Changed numbering format.
12/17/04 1.2.2 Tim Boudreaux Included this paragraph on Navigable River Inspections.
12/17/04 2.1 – 2.1.4.3 Tim Boudreaux Deleted most of this section because it is listed in the procedural
document. Revised the Program Element to include 2.1 Shallow and
Exposed Pipe, 2.2 Earth Movement and 2.3 Navigable River Inspections.
12/17/04 3.0 Tim Boudreaux Eliminated DOC Prioritization Guidelines since these are listed in the
DOC Procedures and DOC Guidelines. Modified the Data Management
section and renumbered.
12/17/04 5.0 Tim Boudreaux Modified References to include only related links within this document.
Other links may be found within the Procedures and other documents.
12/17/04 6.0 Tim Boudreaux Eliminated Forms and Attachments that may be found in other more
pertinent documents.
11/30/04 2.2 Rick Wooldridge Added Earth Movement and its supporting discussions
01/01/06 Intro Tim Boudreaux Added Applicability Statement
01/01/06 2.4 Clyde Clausen Added Overhead Pipeline Crossing Section
01/01/06 References Renamed links
01/01/06 Applicability Renamed scope and changed location in doc
01/01/07 Reviewed, no changes
01/01/08 Reviewed, no changes
10/27/08 1.1.1 Tim Boudreaux Included continued monitoring statement.
10/27/08 1.1.3 Tim Boudreaux Modification to Longhorn link and reference to Tier levels.
12/8/08 2.3 Tim Boudreaux Modified Consent Decree Specific statement.
01/01/2009 Tim Boudreaux Annual Review with no changes.
9/01/09 1.1.3 Tim Boudreaux Deleted Longhorn
9/01/09 2.2 Tim Boudreaux Deleted Longhorn
9/01/09 3.1.1 Tim Boudreaux Included IMP Section 6 review language
9/01/09 5.6 Tim Boudreaux Added Assets covered per
9/01/09 Tim Boudreaux Annual Review with changes listed above
3/1/10 3.1.1 Tim Boudreaux Replaced “Guidelines” with “Procedure”
3/1/10 5.2 Tim Boudreaux Removed Depth of Cover Guidelines
9/1/10 Tim Boudreaux Annual Review with no changes
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 1260>>>

Magellan Midstream Partners, L.P.
ENCROACHMENT PROCEDURE 7.05–ADM‐012
Asset Integrity 01/01/10 Revision: 4 Page 1 of 4
1.0 PURPOSE
1.1 The purpose of this procedure is to insure safety to the surrounding public, to protect the
environment from accidental product releases and to protect the usefulness and value of rights
of way owned or operated by Magellan Midstream Partners, L.P. or its affiliated companies
(hereinafter, “Company”).
2.0 SCOPE
2.1 The provisions of this document outline procedures to be followed by any person or entity when
planning construction or other activities that could affect rights of, or assets owned or operated
by Company, on or near easements or rights of way owned or operated by the Company. The
use of the words “shall” or “will” when referring to actions or procedures specified in this
document are to be interpreted as the Company’s preferred method of operation, but are not to
be construed as absolutes which would not allow for exceptions to the preferred method of
operation in particular situations with proper approval and documentation of the reasons for
such exceptions.
2.2 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on non‐jurisdictional assets as deemed
appropriate.
2.3 Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, this pipeline operates
under the requirements of the Mitigation Plan.
2.4 Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
the Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline
Systems operate under the requirements of the Consent Decree. For the period of the Consent
Decree, these systems will follow the applicable process and procedures (see Consent Decree for
applicable programs).
3.0 PROCEDURES
3.1 All Employees shall:
3.1.1 If the notification of an encroachment originates from the One Call Center or was
discovered by Field Personnel, immediately forward the encroachment details to the
appropriate Asset Locator.
3.1.2 If the notification of an encroachment did not originate from the One Call Center or was
not discovered by Field Personnel, immediately forward the encroachment details to
the appropriate Real Estate Representative.
3.1.3 Any Employee who observes or learns of a land use change which may impact any
Company Easement Tract shall report such change to the Company Real Estate
Representative and Company Asset Integrity Risk Engineer for the area where the land is
located and provide them the information on the land use change.
3.1.4 On each occasion where an Employee meets with a landowner or tenant, the Employee
shall request the landowner or tenant notify the Company at any and every time when
the land use will be changed for land on or adjacent to a Company Easement Tract.

<<<PAGE 1261>>>

Magellan Midstream Partners, L.P.
ENCROACHMENT PROCEDURE 7.05–ADM‐012
Asset Integrity 01/01/10 Revision: 4 Page 2 of 4
3.2 All Asset Locator Personnel shall:
3.2.1 3.2.2 Check the depth of cover over its pipeline(s) and for any other potential impacts to
Company pipelines and facilities.
Evaluate the type of encroachment activity and determine if the Encroachment
Agreement (Short Form) is applicable. Encroachment Agreement (Short Form) is to be
used only for the following type encroachments that adhere to the General
Encroachment Requirements:
3.2.3 3.2.4 3.2.2.1 Unpaved Residential Driveway
3.2.2.2 Temporary Equipment Crossing
3.2.2.3 Gas Line
3.2.2.4 Water Line
3.2.2.5 Telephone Cable
3.2.2.6 Sprinkler System
3.2.2.7 Fence
3.2.2.8 Fiber Optic Cable
3.2.2.9 Drain Tile
3.2.2.10 Television Cable
3.2.2.11 Electric Line
3.2.2.12 Other Pipeline
3.2.2.13 Other low impact encroachments (after receiving approval from the Real
Estate Representative and Risk Engineer)
If applicable complete and execute the Encroachment Agreement (Short Form) and
forward to the Records Coordinator.
If the Encroachment Agreement (Short Form) is not applicable, Field Personnel shall
3.2.5 send the encroachment notification to the Real Estate Representative.
Monitor and inspect the encroachment activity to insure the General Encroachment
Requirements are met.
3.3 The Real Estate Representative shall:
3.3.1 Upon discovery or notification of an encroachment employ the Encroachment Process
Map.
3.3.2 3.3.3 3.3.4 Evaluate the type of encroachment activity, gather all available information regarding
the type of encroachment, and send the information to the Asset Locator if the
encroachment meets the Encroachment Agreement (Short Form) requirements, or to
the Risk Engineer for an Impact Review if the Encroachment Agreement (Long Form) is
appropriate.
After receiving the Impact Review from the Risk Engineer notify the encroaching party
of the impact to Company facilities.
Prepare, negotiate and execute the Encroachment Agreement (Long Form) and any

<<<PAGE 1262>>>

Magellan Midstream Partners, L.P.
ENCROACHMENT PROCEDURE 7.05–ADM‐012
Asset Integrity 01/01/10 Revision: 4 Page 3 of 4
3.3.5 3.3.6 other applicable agreements.
Send a copy of Encroachment Agreement (Long Form) to the Asset Locator and to the
Records Coordinator.
Send fully executed and recorded original Encroachment Agreement (Long Form) and
other applicable agreements to the Real Estate Right of Way Tract File for permanent
retention.
NOTE: The Real Estate Representative will use 1 of the 3 preapproved Encroachment
Agreement (Long Form) documents after evaluating the type of encroachment.
3.4 The Risk Engineer shall:
3.4.1 3.4.2 3.4.3 3.4.4 Upon receiving the encroachment information from the Real Estate Representative,
evaluate the integrity risks to any Company facility, conduct an engineering assessment,
prepare an Impact Review and forward to the Real Estate Representative.
Execute any required pipeline adjustment or relocation made necessary by the
proposed encroachment in accordance with SIP 4.01 Project Management. Longhorn
personnel will manage and execute all major adjustments or relocations on the
Longhorn System.
Manage the financial and reimbursement duties for any pipeline adjustment or
relocation.
Send project documentation to the Records Coordinator.
3.5 The Records Coordinator shall:
3.5.1 Review project documentation and ensure that all Company maps, drawings and
records are updated.

<<<PAGE 1263>>>

Magellan Midstream Partners, L.P.
ENCROACHMENT PROCEDURE 7.05–ADM‐012
Asset Integrity 01/01/10 Revision: 4 Page 4 of 4
System Integrity Plan Change Log
Date Change
Location
Change BY Brief Description of Change
12/22/04 Clyde Clausen Created Internal Encroachment Document. Made
numerous changes and re‐formatted the entire
document.
12/22/04 4.5.7 Clyde Clausen Added Directional Drill Requirements
12/22/04 Clyde Clausen Inserted Change Log into document
01/01/05 Reviewed, no changes
01/01/06 Clyde Clausen Incorporated Shell and Longhorn specific requirements
throughout document
01/01/06 Changed Magellan to “Company”
01/01/07 Bill Klein
Removed redundant information that was already
contained in the General Encroachment Requirements.
Listed specific employee roles and responsibilities. Re‐
formatted the entire document.
01/01/08 Reviewed, no changes
01/01/09 2.4 Bill Klein
01/01/10 2.3 Changed Longhorn to Mitigation
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 1264>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 1 of 5
1.0 OBJECTIVE
1.1 To establish standardized and consistent processes for pipeline operations and maintenance in
regards to Navigable River Crossing Inspections.
2.0 SCOPE
2.1 2.2 2.3 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on nonjurisdictional assets as deemed
appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices. This pipeline operates
under the requirements of the Mitigation Plan.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations, as well as
Company guidelines, process, or best practices, the Company’s Consent Decree Pipeline Systems
operate under the requirements of the Consent Decree (see Consent Decree for applicable
programs).
3.0 PURPOSE
3.1 Navigable River Crossings
3.1.1 3.1.2 3.1.3 3.1.4 3.1.5 3.1.6 The Pipeline Integrity Coordinator shall annually review the list of pipeline crossings of
navigable rivers contained in this procedure to ensure the crossings are inspected within
the required timeframe.
Pipeline Integrity shall be responsible for having these inspections made and for
maintaining the records of such inspections. The inspection records shall be maintained
for five years or until another inspection is performed. The results of such inspections
will be compared with the previous crossing records to determine any change. Should
the inspection indicate that repairs need to be made to the crossing, Pipeline Integrity
shall be responsible for having suitable repairs performed.
Each pipeline crossing under a DOT identified navigable waterway will be inspected at
intervals not exceeding five years. For this inspection, navigable waterways are defined
as waterways subject to commercial barge traffic.
The inspection shall be conducted by third party personnel qualified to carry out such
inspections and to prepare permanent records of their findings.
The inspections shall determine the pipeline location and any exposed pipe within the
limits of the navigable waterway and the right‐of‐way immediately adjacent on each
side.
The permanent records shall be of sufficient detail to compare with the previous
crossing records to determine any change in the location of the pipeline. They shall also
indicate if any, the length and location of exposed pipeline. The third party inspector
will prepare both plan and profile drawings detailing the findings of the inspection.
4.0 PROCEDURE
4.1 Navigable River Crossing Inspections

<<<PAGE 1265>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 2 of 5
4.2 4.3 4.1.1 Contractor will reestablish base line indicated on plan drawing and accurately determine
route of the pipeline through the river with reference to this line. The length of this
traverse will extend between convenient points on the banks. These points will be
above water level and at least 50 feet from the edge of the water.
4.1.2 Location of pipe will be determined by the use of an induced tone or
transmitter/receiver pipe locator.
4.1.3 The river bottom and banks between reference points will be profiled over the pipe with
elevations referenced to the existing bench mark shown on drawing. If existing
benchmark has been destroyed, Contractor will set a new bench mark in as permanent a
manner as possible.
4.1.3.1 Profile data will also include elevation of water level and top of pipe at all
exposed and suspended sections. Vertical measurements for profile may
be made by use of a portable Fathometer or weighted sounding chain. On
pipeline inspections where sufficient cover cannot be determined from the
profile, a diver is required to complete the inspection.
4.1.4 A diver will make passes over each pipe at intervals of 20 feet or less and if exposed or
suspended pipe is located, the diver will follow these sections with continuous passes.
He will also determine size and location of any build‐up of debris against exposed or
suspended pipe section, the condition of pipe and/or pipe coating, the nature of the
river bottom at the pipe, and any other underwater condition that may appear to
adversely affect the safety of the pipeline crossing such as scouring of the river bottom
or undercutting of the banks. Sonar equipment may be used to detect exposed pipe
instead of a diver.
Forward results of this survey and the inspection individual written reports for each crossing site.
Submit reports to the Pipeline Integrity Project Manager and include, at least the following:
4.2.1 A list of all exposed and suspended pipe sections located by station numbers
and showing clearance between pipe and river bottom.
4.2.2 Identification of changes from last inspection.
4.2.3 Recommendations for repair.
Contractor will supply plan and profile sheets of each pipeline surveyed at the crossing
site. One plan and profile sheet will be used for each single pipeline crossing the stream.
4.3.1 Show dual lines. Include the river bottom and adjacent banks between reference points
in the drawings.
4.3.2 Show the condition of the pipe coating, all obstructions and sharp objects, all unusual
conditions, such as exposed or suspended pipe, and the location and elevation of
benchmarks used by Contractor in the drawings. The profile drawing of the pipeline will
extend to a minimum of fifty (50) feet beyond the edge of the water on each side of the
river.
4.3.3 Show pipe, river bottom and water elevations from previous inspections (when known)
on the drawings.
4.3.4 Retain the inspection records that relate to the navigable river inspections for five years
or until a new inspection is performed.

<<<PAGE 1266>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 3 of 5
4.4 The following crossings are listed as being across navigable waters:
Navigable River Crossings
State Line Section Waterway #Of Spare
Lines
Eng. Station Date Last
Inspection
Date Next
Inspection
Delaware Wilmington 10” Pipeline Christina River 0 66+18 06/11/10 06/11/15
Illinois 106#3‐12" TCS IL‐Wilmington Illinois River 0 26507+04 08/12/08 08/12/13
036 #5‐8" Des Moines‐ MS River Mississippi River 0 9026+14 05/14/07 05/14/12
037 #6‐12" Des Moines‐ MS River Mississippi River 0 9028+96 05/14/07 05/14/12
Iowa 054 #5‐12 Irv ‐ Sioux Falls Missouri River 1 12520+79 08/17/11 08/17/16
Nebraska/
Iowa
West Leg NH3 Missouri River 0 14272+87 08/18/11 08/18/16
Kansas 006 #3‐8" Barnsdall ‐ KC Kansas River 0 10171+48 08/08/08 08/08/13
007 #4‐12 Barnsdall ‐ KC Kansas River 0 10178+52 08/08/08 08/08/13
008 #5‐12" Barnsdall ‐ KC Kansas River 0 10187+55 08/08/08 08/08/13
023 #4‐8" Argentine ‐ KC Kansas River 0 164+00 08/08/08 08/08/13
Kansas/
Missouri
18th Street to Riverside 8” Missouri River 0 10370+33 09/01/11 09/01/16
Louisiana GeoNet Bayou Black 1 08/19/08 08/19/13
Minnesota 069 #7‐8" Rose ‐ Mpls. Air Minnesota River 0 661+44 05/15/07 05/15/12
070 #6‐12" Rosemount ‐ Willmar Minnesota River 0 760+59 05/15/07 05/15/12
121#3‐8" StPP (Aranco) ‐ Pine Bend Mississippi River 0 113+45 05/16/07 05/16/12
007 #4‐12” Des Moines to
Minneapolis
Mississippi River 1 12740+77 05/16/07 05/16/12

<<<PAGE 1267>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 4 of 5
Navigable River Crossings
State Line Section Waterway #Of Spare
Lines
Eng. Station Date Last
Inspection
059 #1‐6" Alex ‐ Grand Forks Red River of The
North
0 5222+47 05/18/07 060 #2‐8" Alex ‐ Fargo Red River of The
North
0 5217+64 05/18/07 Missouri 080 #7‐8” Olathe to Columbia Missouri River 0 6714+85 08/22/11 095 #7‐16" Wathena ‐ Des Moines Missouri River 0 9775+35 08/23/11 105 #3‐12 ' TCS MO ‐ IL Line Mississippi River 1 24398+70 08/10/08 Oklahoma 013 #1‐12” Tulsa‐Barnsdall Arkansas 0 48+35 09/21/10 012 #4‐12” Tulsa‐Barnsdall Arkansas 0 48+24 09/21/10 108 #4‐12” Tulsa‐Tulsa Jct. Arkansas 1 48+24 09/21/10 Oklahoma Verdigris Lateral 6” NH3 Verdigris River 0 6426+05 03/04/09 Texas Amerada Hess Houston Ship
Channel
3 151+00 03/31/09 Texas City to Pasadena 18” Clear Lake 0 729+00 04/25/09 Wisconsin 047 #1‐8" Newport ‐ Bateman St. Croix River 0 620+13 05/17/07 Date Next
Inspection
05/18/12
05/18/12
08/22/16
08/23/16
08/10/13
09/21/15
09/21/15
09/21/15
03/04/14
03/31/14
04/25/14
05/17/12

<<<PAGE 1268>>>

Magellan Midstream Partners, L.P.
NAVIGABLE RIVER CROSSING INSPECTIONS
PROCEDURE
7.05–ADM–014
Asset Integrity 01/01/12 Revision: 6 Page 5 of 5
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
12/22/04 New Procedure Tim Boudreaux Removed Navigable River Crossing section from Pipeline
Maintenance Document and created new Procedure for Navigable
River Crossings.
12/22/04 3.1.2 Tim Boudreaux Included text “On pipeline inspections where sufficient cover cannot
be determined from the profile, a diver is required to complete the
inspection.
12/15/05 3.4 Tim Boudreaux Included inspection dates on Amerada Hess pipelines and included new
asset inspection for Wilmington 10” pipeline.
12/15/05 Intro Tim Boudreaux Included Applicability Statement.
1/1/07 List Tim Boudreaux Updated list for 2006 completed inspections.
01/01/08 Reviewed, no changes
12/18/08 2.3 Tim Boudreaux Modified Consent Decree Specific.
12/18/08 4.4 Tim Boudreaux Updated List of navigable inspections.
01/01/09 Tim Boudreaux Annual Review with no changes.
9/01/09 2.2 Tim Boudreaux Deleted Longhorn
9/01/09 4.4 Tim Boudreaux Updated list of navigable inspections
9/01/09 5.1 Tim Boudreaux Deleted Longhorn
9/01/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
09/02/11 3.1.1 Dennis Vasicek
Added sentence regarding Pipeline Integrity Coordinator’s
annual review of list of navigable river crossings
09/02/11 4.4 Dennis Vasicek
Added 18th Street to Riverside 8” crossing of the Missouri
River and Texas City to Pasadena 18” crossing of Clear Lake
09/02/11 4.4 Dennis Vasicek Updated inspection dates
12/31/11 All 2012 Annual Review complete

<<<PAGE 1269>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 1 of 3
1.0 PURPOSE
1.1 The purpose of this procedure is to establish a standardized method for
the investigation and monitoring of areas of the pipeline identified as
having high susceptibility to earth movement or where earth movement
has been identified.
E: Characterizing an area, as having high susceptibility to earth movement
does not imply certainty that earth movement will occur or that earth
movement is not possible outside an area of high susceptibility.
2.0 SCOPE
2.1 2.2 2.3 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities.
Elements of this program may be utilized in whole or part on nonjurisdictional assets as deemed
appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, This pipeline operates
under the requirements of the Mitigation Plan.
Consent Decree Specific: In addition to applicable Federal, State, and Local regulations,
as well as Company guidelines, process, or best practices, the Company’s Consent
Decree Pipeline Systems operate under the requirements of the Consent Decree (see
Consent Decree for applicable programs.
3.0 PROCEDURE
3.1 Identifying Areas for Inspection. Specific pipeline segments may have regulatory
requirements outside DOT 49 CFR. Please refer to those specific Plans for their
individual requirements, as listed above in Applicability.
3.1.1 Identify areas to be inspected as defined by the Earth Movement Section of the Depth
of Cover Program.
3.2 below.
3.2.1 Select the appropriate inspection method using the guidelines established in 3.2.1 and 3.2.2
3.3 3.4 3.5 Use aerial patrol for inspection and monitoring of areas with high susceptibility to
earth movement. If aerial patrol is the selected inspection method go to 3.3 below.
3.2.2 Use close visual inspection in areas where earth movement has been identified. If
close visual inspection is the selected inspection method go to 3.4 below.
Performing Inspection and Monitoring Utilizing Aerial Patrol
3.3.1 Conduct aerial patrol in accordance with the Inspection of Right‐of‐Way Procedure.
Pay particular attention, within the target area, to signs or indicators of earth movement
or subsidence such as ground cracks, sink holes, erosion, heaving, buckling, etc.
3.4.1 If earth movement is identified go to 3.5 below otherwise go to 3.6 below.
Performing Inspection and Monitoring Utilizing Close Visual Inspection

<<<PAGE 1270>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 2 of 3
3.5.1 Conduct close visual inspection in accordance with the Inspection of Right‐Of‐Way
Procedure.
3.5.2 Document the nature of the earth movement specifying the type of movement, extent
of the affected area (length, width, depth), age, characteristics, soil type, etc. using
both a written description and photography (where possible).
NOTE: Notify the appropriate Asset Integrity Engineer as soon as practical to discuss
additional data requests and the next course of action.
3.6 Documentation
3.6.1 Use the Pipeline Maintenance Report to document any findings, with copies sent to
the Asset Integrity Engineer for continued evaluation.
4.0 DEFINITIONS
4.1 4.2 Earth Movement: Unintended movement of the soil around the pipeline.
High Susceptibility (to earth movement): An area along the pipeline identified through risk
assessment as having a higher likelihood of earth movement as compared to other relative
locations.

<<<PAGE 1271>>>

Magellan Midstream Partners, L.P.
EARTH MOVEMENT INSPECTION PROCEDURE 7.05–ADM–020
Asset Integrity 01/01/10 Revision: 3 Page 3 of 3
System Integrity Plan Change Log
Date CHANGE
LOCATION
Changed By Brief Description of Change
1/4/03 New Rick Wooldridge New Procedure
01/01/06 Applicability Tim Boudreaux Included language to direct to Longhorn and Shell specific
requirements.
01/01/06 2.1.1 Tim Boudreaux Included: “Specific pipeline segments may have regulatory
requirements outside DOT 49 CFR Parts 195 or Parts 192.
Please refer to those specific Plans for their individual
requirements, as listed above in Applicability”.
Applicability
2.0
Changed to Scope
01/01/07 Reviewed, no changes
01/01/08 Reviewed, no changes
12/18/08 2.3 Tim Boudreaux Modified Consent Decree Specific.
01/01/09 Tim Boudreaux Annual Review with no changes.
9/03/09 2.2 Tim Boudreaux Removed Longhorn and Replaced with Assets covered per
Mitigation Plan
9/03/09 4.3 Tim Boudreaux Removed Longhorn and Replaced with Assets
covered per Mitigation Plan
9/03/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
12/31/11 All 2012 Annual Review complete – no changes

<<<PAGE 1272>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 1 of 6
1.0 PURPOSE
1.1 The purpose of this procedure is to effectively manage Overhead Pipeline Crossing
maintenance through a comprehensive risk-based program which identifies risk reduction
projects to improve structural component integrity and ultimately keep the product in the
pipe.
2.0 SCOPE
2.1 2.2 2.3 Consent Decree Specific: : In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, the Company’s
Consent Decree Pipeline Systems operate under the requirements of the Consent
Decree. For the period of the Consent Decree, these systems will follow the applicable
process and procedures (see Consent Decree for applicable programs).
3.0 PROCEDURE
3.1 This procedure is applicable to federal and/or state jurisdictional pipelines and/or facilities. The
Manager of Asset Integrity may utilize elements of this program in whole or part on
nonjurisdictional assets as deemed appropriate.
Assets covered per Mitigation Plan: In addition to applicable Federal, State, and Local
regulations, as well as Company guidelines, process, or best practices, this pipeline operates
under the requirements of the Mitigation Plan.
The Overhead Pipeline Crossing Integrity Program will cover all above ground pipeline crossings,
which are cable supported. This Inspection Procedure is structured in a cycle of four recurring
categories:
3.1.1 Gather Data
3.1.1.1 3.1.1.2 Select the initial inspections based on historical knowledge of the condition
of the structures using stakeholder, SME, risk data, and process efficiency
information. Select subsequent inspections using risk data and further
historical knowledge of the structures. The baseline inspections should be
completed within six years and re‐inspections will be conducted on a
timeframe based on the inspection findings and recommendations but not
to exceed ten years from the previous inspection.
Use the following three project‐specific standard forms for the overhead
pipeline structure inspections.
3.1.1.2.1 Use the Basic Data Form to list all the relevant historical and
geometrical information about the structure. Prior to the
initial inspection, locate any available information on the
structures so that as much information as possible may be
filled out on the Basic Data Form. During the field inspection,
this information should then be checked and the remainder
of the information gathered.
3.1.1.2.2 Use the Inspection Report Form during the field inspection to
evaluate and record the existing conditions of the
components on the overhead pipeline structure. Each
component listed is preceded by a box to be used for a rating
number to evaluate the condition of the component and
followed by a line to be used for a verbal description of any

<<<PAGE 1273>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 2 of 6
3.1.1.3 3.1.1.4 problems encountered.
3.1.1.2.3 The Photo Log Sheet is used in the field to document
photographs taken of the different overhead pipeline
structures inspected.
The development of a systematic method of inspection for each type of
overhead pipeline structure is important. A well‐planned sequence will
provide a working guide for the inspector and will ensure a systematic and
thorough inspection of all components of the structure.
For the overhead pipeline structure, the components of the structure
should be inspected in the following order:
3.1.1.4.1 Foundations
3.1.1.4.2 Base plates and connections to foundations
3.1.1.4.3 Cable anchorage
3.1.1.4.4 Tower frames
3.1.1.4.5 Saddles
3.1.1.4.6 Main cable
3.1.1.4.7 Suspender cables
3.1.1.4.8 Pipe supports
3.1.1.4.9 Pipeline
NOTE: There are other considerations observed during the
inspection, which will be documented, such as: bank
degradation, obvious flood levels, threatening outside
forces (trees or other structures), right‐of‐way
visibility/marking, public access and vandalism.
3.1.1.5 3.1.1.6 The thoroughness of an inspection is as important as the sequence. Use a
checklist during the inspection to prevent the possibility of any
components being overlooked. The Inspection Form can be used as a basic
outline for the checklist.
Complete full documentation reports for each inspection using the
Overhead Inspection Basic Data Form, the Overhead Inspection Report
Form and the Overhead Inspection Photo Log Sheet. Pipeline Integrity shall
maintain these records for further analysis.
3.1.2 Analyze the Data
3.1.2.1 List all findings on the Inspection Report Form. Use the numerical rating
system (see Table 1 below) to evaluate the condition of the components.
The number best describing the component in the worst condition should
be placed in the box next to the name of the component. Include a written
description for clarification or further explanation. From this information
the SME will make recommendations for maintenance repairs, completion
time limits for making those repairs and a general cost estimate based on

<<<PAGE 1274>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 3 of 6
“Rule of Thumb” estimates.
Table 1
Rating Number Rating Description Rating Examples
6 Good Condition 5 Potential Problem 4 Minor Problem 3 Major Problem 2 Critical Problem There are no apparent problems
Rust, corrosion or cracked foundation
Loose bolts, cables, or spalled foundation
Moderate structural cracking or repainting
Major structural defects
3.1.2.2 Analyze the individual component ratings further and give weighted scores
to achieve an overall Relative Risk Index. This will assist in our maintenance
prioritization efforts.
3.1.2.3 Asset Integrity Personnel shall review, approve/reject or submit alternative
recommendations. Repair recommendations will be risk ranked in
accordance to criteria set forth in the Overhead Crossing Inspection
Relative Risk Index Formula.
3.1.2.4 The DOC Coordinator will schedule the maintenance according to these
recommendations and list them on the Annual Integrity Plan.
3.1.3 Develop The Mitigation Plan
3.1.3.1 The DOC Coordinator will assign a Project Manager to complete the
maintenance work. The Project Manager will follow Project Life Cycle for
completing the task.
3.1.3.2 The Project Manager shall follow the recommended maintenance schedule
according to the annual integrity plan for repairs unless otherwise
approved to proceed with any additional repairs, which would improve the
integrity of the structure at a significant cost savings.
3.1.3.3 The Project Manager shall be responsible for all planning, estimating,
contracting and execution of the maintenance repairs.
3.1.3.4 An AFE and Project Plan must be submitted and approved by the DOC
Coordinator before any work may begin, unless the work needed is
considered an emergency and immediate attention is necessary, in which a
courtesy call to the DOC Coordinator is all that is required. The afe request
and documentation of the work performed may follow the repair, in this
case. During the plan development, consult with Area Operations, Asset
Integrity Personnel and third party SME Resources.
3.1.4 Execute the Mitigation Plan
3.1.4.1 Following the approval of the project plan, the Project Manager may
allocate resources and execute the Mitigation Plan while integrating in
synergies with other MMP departments and programs.
4.0 OVERHEAD PIPELINE CROSSING PRIORITIZATION GUIDELINES

<<<PAGE 1275>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 4 of 6
4.1.1.2 4.1 The Overhead Pipeline Crossing Integrity Program, along with any resulting mitigation initiatives,
will be prioritized in accordance with the following guidelines:
4.1.1 Each structure will receive an initial risk prioritization number based on the Pipeline Risk
Model. Factors that may influence the prioritization might be local historical knowledge
of inferior structural conditions, past large water flow events, line strikes, near misses
and HCA locations.
4.1.1.1 The first phase of the inspections will include the top 20% of the structures
listed as highest risk according to the pipeline risk model.
All other structures will follow in 20% groupings according to the risk
model.
4.2 Following the Overhead Pipeline inspection, each structure will receive a relative risk index
number. Maintenance will be performed on the structures that receive the lowest relative risk
index score in accordance with the Integrity Management Plan (IMP).
5.0 DATA MANAGEMENT AND INITIATIVE IMPLEMENTATION
5.1 Data initially obtained and periodically updated via the Overhead Pipeline Crossing Integrity
Program will be centralized and maintained in a formal database. Pipeline Integrity will utilize
the database as an input to its overall risk management process, which includes the relative risk
assessment process.
5.2 Pipeline Integrity will further manage the recommendation and funding process associated with
the implementation of this initiative.
6.0 REFERENCES
6.1 Regulatory – 49 CFR Part 195 – U.S. D.O.T. Pipeline Safety Regulations
6.2 Related Policies/Procedures
6.2.1 Pipeline Defect Evaluation and Repair Procedure
6.2.2 RSTRENG Analysis of Corrosion
6.2.3 6.2.4 Asbestos Safety Procedure
6.2.5 Excavation Safety Procedure
6.2.6 Welding and Radiographic Procedures
6.2.7 Specification 100—Construction And Fabrication Of Pipelines And Related Piping
Systems
6.2.8 6.3 Forms and Attachments
6.3.1 Pipeline Maintenance Report
6.3.2 6.3.3 6.3.4 Coatings – Selection, Applications and Maintenance
Specification 101—Maintenance Welding (Excluding Ethylene Pipelines)
Prioritization for Exposed Pipe (Flow Chart)
Prioritization for Shallow Pipe (Flow Chart)
Shallow Pipe Resolution Process (Flow Chart)

<<<PAGE 1276>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 5 of 6
7.0 DEFINITIONS
7.1 Stakeholder: Any person or group directly involved with this initiative.
7.2 SME: Subject Matter Expert.
7.3 7.4 7.5 7.6 7.7 7.8 7.9 Risk Data: Furnished by the Risk Assessment Group for specific pipeline segments.
Process Efficiencies: Planning optimization of time, materials, labor and funding.
Basic Data Form: A standard form to list the relevant historical and geometrical information
about the structure.
Inspection Report Form: A standard form used during the field inspection to evaluate and
record the existing conditions of the components.
Photo Log Sheet: A standard form for documenting and organizing photos taken at the
inspection site.
Rule of Thumb Estimates: Standard costs associated to specific work in the pipeline industry, as
an average. It is not region specific.
Relative Risk Index Formula: Process by which all component ratings are correlated to give a
final overall Risk Score to assist with process management.

<<<PAGE 1277>>>

Magellan Midstream Partners, L.P.
OVERHEAD PIPELINE CROSSING INTEGRITY PROCEDURE 7.05–ADM–030
Asset Integrity 01/01/12 Revision: 3 Page 6 of 6
System Integrity Plan Change Log
Date Change
Location
Change By Brief Description of Change
1/31/05 All Tim Boudreaux New Procedure
01/01/07 Reviewed, no changes
01/01/08 Reviewed, no changes
12/17/08 2.1 Tim Boudreaux Eliminated redundant sentence.
12/17/08 2.2 Tim Boudreaux Modified Consent Decree Specific.
12/17/08 5.1, 5.2 and 5.3 Tim Boudreaux Removed link for Data record sheet, inspection report and photo log
sheet.
01/01/09 Tim Boudreaux Annual Review with no changes made.
9/03/09 2.2 Tim Boudreaux Deleted Longhorn and changed to Assets covered per Mitigation Plan
9/03/09 Tim Boudreaux Annual Review with changes listed above
01/01/11 Reviewed, no changes
09/02/11 3.1.1.1 Dennis Vasicek Revised third sentence to, “The baseline inspections should be
completed within six years and re‐inspections will be conducted on a
timeframe based on the inspection findings and recommendations but
not to exceed ten years from the previous inspection.”
12/31/11 All 2012 Annual Review complete

<<<PAGE 1278>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 1 of 5
1.0 PURPOSE
1.1 The purpose of this procedure is to address specific requirements of the Mitigation Plan related to inspection of the
surface conditions on or adjacent to each pipeline right‐of‐way (ROW). This document is to be utilized along with
the Magellan Midstream Partners, L.P. Inspection of Right of Way Procedure.
2.0 PROCEDURE
NOTE: Persons performing inspection shall comply with all state and federal laws, rules, regulations, statutes, ordinances
or codes and Mitigation Commitments as may be required. In its contracts with inspection contractors, the Company shall
identify requirements specifically related to the petroleum industry. It shall be the obligation of such contractors to comply
and maintain appropriate records
2.1 Methods of Inspection
2.1.1 Aerial Patrol: As described below and in Inspection of Right of Way Procedure.
2.1.2 Ground Patrol: As described below and in Inspection of Right of Way Procedure. Also Refer to the
guidelines in the Threatened and Endangered Species Avoidance And Minimization Timing Restrictions.
2.2 Patrol Requirements
2.2.1.4 Edwards Aquifer Recharge Zone – Daily (once per week shall be a ground‐level
patrol)
2.3 2.2.1 The specified frequency of surveillance shall meet the following requirements:
2.2.1.1 Tier 1 Areas – Once a week, not to exceed 12 days, but at least 52 times per year
2.2.1.2 Tiers 2 and 3 Areas – Every two and one‐half (2.5) days, not to exceed 72 hours
2.2.1.3 Aerial and ground surveillance frequency will be increased across Tier II (Sensitive)
and Tier III (Hypersensitive) areas when the threat of flooding and/or severe erosion
is identified near the pipeline right‐of‐way.
Aerial Patrol and Ground Patrol Notification
2.3.1 Patrol Pilots will be required to contact the Austin Operations Office each morning to communicate the
ability to fly or not to fly, “No‐Fly”, their identified patrol segments. Segments are identified as follows:
2.3.1.1 LP 301 Galena Park to Pecos River (MP 0 – MP 528)
2.3.1.2 LP 303 Crane to El Paso (MP 457 – MP 695), Crane to Odessa (MP 0 – MP 28) and El
Paso to El Paso Jct. (MP 0 – 10)
2.3.1.3 Austin Operation Office will record notification of flight and await completed Right‐
of‐Way Patrol Report by Aerial/Ground form.
2.3.1.4 The Austin FOA will record each patrol on a patrol tracking spreadsheet to insure the
required number of flights are made and file with monthly reports.
2.3.1.5 Upon receipt of the Right‐of‐Way Patrol Report by Aerial/Ground form. The One Call
Group will create a One Call ticket and the field locator will respond to the Aerial
Patrol in Ticket View.
2.3.1.6 Right‐of‐Way (ROW) Inspection Report will be sent to Austin Operations Office and
the One Call Group at the end of the flight day or within 12 hours of flight

<<<PAGE 1279>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 2 of 5
2.3.1.7 completion.
All emergency sightings by pilot will be called into the Company One‐Call Center. The
Company One‐Call Center will send to the field as an emergency ticket under the
heading A/P (Aerial Patrol). All A/P emergency tickets will be responded to
immediately by field personnel. Non‐emergency sightings will be reported on Right‐
of‐Way Patrol Report by Aerial/Ground form and responded to within 3 working days
and documented by the appropriate personnel upon receipt of the report.
NOTE: Daily patrols of these segments shall continue until confirmation of flight by the
Patrol Pilot has been received.
2.3.2 2.3.3 Each and every morning, the person on call will contact the Austin Area Office message center by calling 1‐
512‐394‐4099, enter mail box number of 4044, and the password of 404400 and verify the pilots ability to
patrol there segment. If a no fly is reported an alert will be issued to personnel to be prepared for ground
patrol procedures. First Level Each area COM will maintain a list of personnel designated to patrol a
section of the Tier 2 and 3 segments in their area and provide that person with the required maps and
other information that will describe in detail the patrol section
On the morning of the second day of notification of “No‐Fly” from the patrol pilot, personnel will be
instructed to proceed with Second Level Procedures. Second Level Procedure – Tier 2 and 3 segments shall
be initiated. The required notification will be made to the ground patrol personnel and unless notified
other wise will begin patrol of the assigned area the next morning. All sightings that can not be dealt with
at the time will be called to One Call. Second Level segments need to be completed within one and one‐
half (1.5) days of the second day notification and sightings will be recorded on Right‐of‐Way Patrol Report
By Aerial/Ground form.
2.3.4 On the morning of the fifth consecutive day of notification from the Patrol Pilot of “No‐Fly”, Third Level
Procedures will be initiated. Third Level Procedures – Tier 1 areas shall be initiated. Each area COM will
maintain a list of personnel designated to patrol a section of the Tier 1 segments in there area and provide
that person with the required maps and other information that will describe in detail the patrol section.
The required notification will be made to the ground patrol personnel and unless notified other wise will
begin patrol of the assigned area the next morning. All sightings that can not be dealt with at that time will
be called to One Call. Second Level segments need to be completed within one and one‐half (1.5) days of
the second day notification and sightings will be recorded on Right‐of‐Way Patrol Report By Aerial/Ground
form.
2.4 Ground Patrol Observation
2.4.1 Ground Patrol personnel patrolling the right of way need to observe Conditions that may adversely affect
the safe operating condition of the pipeline system. Observations need to be documented for continued
inspection, maintenance or repair activities. Observations shall be documented on the following forms.
2.4.1.1 Right‐of‐Way (ROW) Inspection Report: Marking repairs, erosion, cathodic
2.4.1.2 2.4.1.3 2.4.1.4 2.4.2 Inspection observations that should be included in the patrol are listed below:
protection issues and span conditions
Right‐of‐Way Patrol Report By Aerial/Ground Form: Document the section inspected
for Department of Transportation (DOT) compliance
Pipeline Maintenance Report: Leak, corrosion, pipe and erosion repairs
Encroachment Agreement (Short Form): Third party crossings on the ROW

<<<PAGE 1280>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 3 of 5
2.4.2.1 2.4.2.2 2.4.2.3 2.4.2.4 2.4.2.5 2.4.2.6 Erosion: Creek, ravines, sink holes, exposed pipe/spans and agricultural land
Right‐of‐Way: Clearing/mowing, marking condition and spacing, over‐hanging trees
and gate needs
Third Party Activity: Dozer, trenching, boring, building construction or fencing
activities on or near the ROW
Leak Indications: Vapors, odor, dead vegetation, rainbow on water or stains on
piping or valves. Vent pipes at road crossings should be inspected for the presents of
vapors.
Pipe Damage: Indication of coating damage (paint or other protective coating) or
pipe damage at exposures or spans. Spans need to be inspected to determine any
pipe deviation or denting from previous patrols.
Cathodic Protection: Inspect test leads (conduit and face plates) and rectifier
locations for visible damage to the rectifier or third activity in the anode field. Verify
Anode Field Schematics are available inside the rectifier.
2.4.3 Reporting
2.4.3.1 During each patrol, emergency situations identified during aerial or ground
surveillance will be immediately reported to the designated Pipeline Control Center.
Aerial Patrol personnel shall remain at report location until otherwise instructed by
Operation. All surveillance personnel and line spotters will be trained and certified in
Occupational Safety and Health Administration (OSHA) Hazardous Waste Operations
and Emergency Response Standard (HAZWOPER) to the first responder level.
2.5 Ground Patrols (Special Conditions)
2.5.1 Several areas have been identified as requiring ground based patrols. These areas will be patrolled at the
intervals specified until circumstances warrant a change in the need for ground‐based patrol or the patrol
frequency.
2.5.2 Patrol Method
2.5.2.1 not be dealt with at that time will be called to One Call.
2.5.2.2 Silver Mountain Road – Special Containment Inspection:
 An area from milepost 174.09 to 174.94, FM 1826 through Silver Mountain Road
has been cased with High Density Polyethylene (HDPE) pipe. This casing requires
 Various methods may be used to conduct a ground‐based patrol. The method used
will be driven by surface conditions, equipment availability and the extensive
nature of the patrol. All terrain vehicles, pickup trucks or walking may be used as
each situation warrants.
Edwards Aquifer Recharge Zone – Austin
 Daily patrols of the Edwards Aquifer Recharge Zone, from Brodie Lane to Slaughter
Lane, milepost 169.79 to 173.64, are required with one (1) ground based patrol
each week. Geology in this area is known to be highly porous and provides ready
access to the aquifer from surface runoff or a hydrocarbon spill. Patroller will
complete Right‐of‐Way Patrol Report by Aerial/Ground form. All sightings that can

<<<PAGE 1281>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 4 of 5
weekly inspection for water infiltration and the presence of hydrocarbon vapors.
Refer to HDPE Inspection and Dewatering procedure.
Document the inspection and file the documentation in accordance with Section 3.0 of this procedure.
2.5.3 3.0 RECORDS
3.1 Written Pilot Reports
3.2 3.1.1 Pilots shall make a written report using the Right‐of‐Way Patrol Report By Aerial/Ground form of all
specified and other material observations as soon as practical following each flight, but in no case more
than 12 hours of flight completion with all required information:
3.1.1.1 Date of inspection
3.1.1.2 Name of person conducting the inspection
3.1.1.3 Identification of the pipeline(s), line section or right‐of‐way segment
3.1.1.4 Location of the observations by mile post number
3.1.1.5 Description of observation
3.1.1.6 Identity of Company staff, date and time (If observation was verbally reported to
Operations Control)
Company Action Taken and Recordkeeping
3.2.1 Employees shall take appropriate action, respond to pilot observations within 3 business days of pilot
report and maintain a record of such response. Such disposition records shall reference or be linked to the
report of the pilot and indicate as is applicable:
3.2.1.1 Date initially investigated by company personnel
3.2.1.2 What action was taken or will be taken
3.2.1.3 The status or disposition of the item observed or if the observation is or is not a
relevant action item
3.2.1.4 All “Non‐Emergency” observations will be responded to in One Call Ticket View
within 3 working days of aerial patrol.
3.2.1.5 Date each reported observation is resolved
3.2.1.5.1 Non‐Emergency sightings and comments will be evaluated by aerial patrol for
removal.
3.2.1.5.2 With respect to observations that were previously reported, it is not necessary
to reinspect and generate a new report, provided there is not a material change
in the status or risk of the reported observation.
3.2.1.5.3 Records of the pilot observation and Company action taken shall be maintained
for a period of two (2) years or until the next regulatory agency inspection,
whichever is longer.

<<<PAGE 1282>>>

Magellan Midstream Partners, L.P.
ASSETS COVERED PER MITIGATION PLAN RIGHT‐OF‐WAY INSPECTION
PROCEDURE
7.05–ADM–031
Asset Integrity 01/01/12 Revision: 10 Page 5 of 5
Date Change
Location 12/15/2005 1.0, 3.0 and 6.0 01/01/2006 01/01/2007 01/01/2008 06/03/2008 2.3.1.7 & 2.3.1.8 01/01/2009 03/31/2009 2.2.1.3 03/31/2009 2.3.1.1 03/31/2009 2.3.1.7 03/31/2009 3.2.1 03/31/2009 3.2.1.3.1 4/29/09 2.5.2.3 4/29/09 2.5.2.4 9/03/09 header 9/03/09 2.4.3.1 9/03/09 3/4/10 2.4.3.1 01/01/11 12/31/11 All System Integrity Plan Change Log
Brief Description of Change
Included link to “Inspection of Right of Way procedure”
Deleted references section
Reviewed, no changes
Reviewed, no changes
Added “emergency”.
Annual Review with no changes.
Changed to 2.2.1.4 and added new 2.2.1.3
Changed flight segment - extended to Pecos River
Added “within 3 working days” and added requirement to put one-call ticket
number on aerial patrol form
Added “within 3 business days of pilot report”
Added section
Boggy Creek ROW Cleared. Visible to aerial patrol. Daily foot patrol
discontinued. Removed this section.
Re-numbered due to removal of Boggy Creek
Changed Longhorn Specific to Assets covered per Mitigation Plan, date and
revision number
Changed Longhorn to Assets covered per Mitigation Plan
Annual Review with changes listed above
Changed “assets covered by mitigation plan” to designated pipeline center – not
a version change
Reviewed, no changes
2012 Annual Review complete

<<<PAGE 1283>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 1 of 4
PURPOSE
The purpose of this procedure is to provide a standardized method for continued surveillance due to severe flooding
conditions on mainline piping at water crossings.
SCOPE
The severe flooding conditions will trigger Field Personnel to direct their resources in a manner that will
enable them to determine the potential effects of flooding on the pipeline system.
PROCEDURE
The Asset Locator shall:
 Watch for the potential for damage to the pipeline caused by flooding and report it to the Pipeline Integrity
Coordinator.
 Report evaluations of the pipeline to the Pipeline Integrity Coordinator.
 Coordinate their responses to flood conditions with Pipeline Integrity Coordinator.
The Pipeline Integrity Coordinator shall:
 Distribute the attached form to the affected stakeholders and obtain the data for updates to management.
 Evaluate the accessibility of pipeline facilities that may be in jeopardy, such as valve settings, which are
needed to isolate water crossings or other sections of a pipeline.
 Extend regulator vents and relief stacks above the level of anticipated flooding, as appropriate for Natural
Gas lines.
 Coordinate with emergency and spill responders on pipeline locations and condition. Provide maps and
other relevant information to such responders.
 Consider deploying personnel so that they will be in position to take emergency actions, such as shut
down, isolation, or containment. List appropriate personnel or contractors that may respond, identify the
point of contact or the QI.
 Determine if facilities that are normally above ground (e.g., valves, regulators, relief sets, etc) have
become submerged and are in danger of being struck by vessels or debris; if possible, such facilities
should be marked with an appropriate buoy with Coast Guard approval.
 Perform frequent patrols, including appropriate over flights, to evaluate right-of way conditions at water
crossings during flooding and after waters subside. Determine if flooding has exposed or undermined
pipelines as a result of new river channels cut by the flooding or by erosion or scouring.
 Perform surveys to determine the depth of cover over pipelines and the condition of any exposed
pipelines, such as those crossing scour holes. Information gathered by these surveys should be shared
with affected landowners. Agricultural agencies may help to inform farmers of the potential hazard from
reduced cover over pipelines. Where appropriate, surveys of underwater pipe should include the use of
visual inspection by divers or instrumented detection.
 Ensure that line markers are still in place or replaced in a timely manner. Notify contractors, highway
departments, and other involved in post-flood restoration activities of the presence of pipelines and the
risks posed by reduced cover.
The Compliance Coordinator shall:
Advise the appropriate PHMSA Regional Office or State Pipeline safety authority if a pipeline has suffered
damage, is shut-in, or is being operated at a reduced pressure as a precautionary measure as a result of
flooding, before returning the line to service, increasing its operating pressure, or otherwise changing its
operating status. PHMSA or the state will review all available information and advise the operator, on a
case by case basis, whether and to what extent a line can safely be returned to full service.

<<<PAGE 1284>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 2 of 4
MAINLINE FLOODING COMPLIANCE FORM
COMPLETED BY: DATE COMPLETED:
LINE SECTION NAME: FLOOD AREA:
SECTION 1: TASKS
1. FLOOD TYPE
(COMPLETE QUESTIONS 1‐10)
1. ARE THE PIPELINE FACILITIES ACCESSIBLE? YES NO 2. ARE VALVE SETTINGS ACCESSIBLE? YES NO 3. HAS PERSONNEL BEEN DEPLOYED TO BE IN POSITION TO TAKE EMERGENCY ACTIONS, SUCH AS SHUT DOWN,
ISOLATION, OR CONTAINMENT?
YES NO 4. HAVE FACILITIES THAT ARE NORMALLY ABOVE GROUND BECOME SUBMERGED AND IN DANGER OF BEING
STRUCK BY A VESSEL OR DEBRIS?
YES NO 5. HAS A MORE FREQUENT PATROL PROGRAM BEEN INITIATED? YES NO 6. HAS COMMUNICATION TO THE EMERGENCY AND SPILL RESPONDERS OF PIPELINE LOCATIONS AND
CONDITIONS TAKEN PLACE? (NOTE BELOW IF MAPS AND PIPELINE INFORMATION WERE GIVEN)
YES NO 7. CAN IT BE DETERMINED IF THE PIPELINE IS EXPOSED OR UNDERMINED AS A RESULT OF FLOODING, EROSION
OR SCOURING?
YES NO 8. ARE UNDERWATER SURVEYS BEING PERFORMED TO DETERMINE DEPTH OF COVER OVER PIPELINES DURING
FLOODING CONDITIONS OF EXPOSED PIPELINES, SUCH AS THOSE CROSSING SCOUR HOLES?
YES NO 9. ARE THE PIPELINE MARKERS STILL IN PLACE? YES NO 10. HAS INFORMATION OBTAINED DURING SURVEY BEEN SHARED WITH AFFECTED LANDOWNERS IN AREAS
WHERE COVER MAY HAVE BEEN REMOVED OVER THE PIPELINE? POST FLOOD ?
YES NO 2. ARE ADDITIONAL PREVENTATIVE OR MITIGATIVE MEASURES RECOMMENDED TO PREVENT A RELEASE OR DRAINAGE FROM A
FLOODED AREA?
(COMPLETE THE DISCUSSION SECTION WITH COMMENTARY AND CONSIDERATION FOR THE BELOW RISK FACTORS)
 GENERAL PROFILE/TERRAIN OF THE AREA SURROUNDING THE PIPELINE
 SURVEYS OF UNDERWATER PIPE / VISUAL INSPECTION BY DIVERS OR INSTRUMENTED DETECTION
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A
N/A

<<<PAGE 1285>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 3 of 4
SECTION 1: TASKS
 CHARACTERISTICS OF THE PRODUCT TRANSPORTED
 AMOUNT OF PRODUCT THAT COULD BE RELEASED
 THE SWIFTNESS OF LEAK DETECTION AND SHUTDOWN CAPABILITIES INCLUDING THE LOCATION OF RESPONSE PERSONNEL
 THE POTENTIAL RATE AND VOLUME OF LEAKAGE
 THE POTENTIAL FOR PRODUCT TO REACH AN IGNITION SOURCE
 DAMAGED LINE, SHUT IN OR OPERATIONS AT A REDUCED PRESSURE AS A PRECAUTIONARY MEASURE AS A RESULT OF FLOODING,
REQUIRE ADVISING THE PHMSA REGIONAL OFFICE OR STATE PIPELINE SAFETY AUTHORITY BEFORE RETURNING THE LINE TO
SERVICE, INCREASING THE OPERATING PRESSURE OR CHANGING ITS OPERATING STATUS.
DISCUSSION OR COMMENTS:

<<<PAGE 1286>>>

Magellan Midstream Partners, L.P.
FLOOD CONDITIONS PROCEDURE 7.05‐ADM‐039
Asset Integrity 1/01/12 Revision: 0 Page 4 of 4
SIP CHANGE LOG
Date Change Location Brief Description of Change
1/1/12 new

<<<PAGE 1287>>>

Magellan Midstream Partners, L.P.
INTEGRITY MANAGEMENT SIP–ADM–7.06
Asset Integrity 1/01/11 Revision: 7 Page 1 of 4
1.0 OBJECTIVE
1.1 The objective of this initiative is to maintain asset integrity through the Integrity Management Plan.
2.0 DESCRIPTION
2.1 2.2 2.3 Products transported, operating parameters, materials of construction, installation, maintenance methods and
routing through a variety of population densities, land uses and environmentally defined areas characterize pipeline
systems and facility assets.
Taken collectively, a pipeline's or a facility’s physical attributes, products transported and operating systems are
factors that characterize the relative risks to the surrounding environment and areas of population. Physical data,
collected by and contributed from an integrated team of operating, technical, commercial and subject matter
experts, is the cornerstone of Integrity Management.
Maintaining integrity of abandoned or inactive segments is also included in Integrity Management.
2.3.1 Abandoned is defined as a pipeline facility that is permanently removed from service and is purged of
product.
2.3.2 Inactive is defined as a line that is removed from active service and purged of product, but may be
returned to service in the future.
3.0 STANDARDS
3.1 The Director of Asset Integrity shall:
3.1.1 Execute and maintain the Integrity Management Plan.
3.1.2 Develop Annual Asset Integrity Plans. Include input from key stakeholders such as Asset Integrity,
Operations, Commercial, Environmental and results from section six and seven analysis of the Integrity
Management Plan.
3.2 3.3 3.1.3 Coordinate the execution and track progress of the Asset Integrity Plan. Distribute a monthly Asset
Integrity Plan Report.
The Manager of Asset Integrity Engineering shall:
3.2.1 Complete the PHMSA Annual Report for Hazardous Liquid Systems and send to the Sr. Vice President of
Operations and Technical Services for certification and approval. Send approved reports to PHMSA.
3.2.2 Publish a quarterly report that contains data regarding the leaks that occurred during the previous quarter.
The Senior Vice President of Operations and Technical Services shall:
3.3.1 Review, approve and certify the PHMSA Annual Report for Hazardous Liquid Systems upon receipt. Send
approved and certified reports to the Manager of Asset Integrity Engineering.

<<<PAGE 1288>>>

Magellan Midstream Partners, L.P.
INTEGRITY MANAGEMENT SIP–ADM–7.06
Asset Integrity 1/01/11 Revision: 7 Page 2 of 4
3.4 The Employee shall:
3.4.1 Document and notify the Asset Integrity Engineer of any new threats to the integrity of the assets (i.e.,
third party construction, new population, new environmental, potential over pressure issues, right‐of‐way
issues, over‐stressed piping, and lack of adequate tank overfill protection, pitting corrosion on tanks or
piping, etc.) or operational changes.
3.5 The Project Manager shall:
3.5.1 Document and notify the Asset Integrity Engineer of any proposed change to the Company assets for risk
consideration.
3.5.2 Utilize Project Life Cycle to place active pipelines in an abandoned or inactive status, or to convert a line to
service. Comply with the Abandoning Pipeline Segments and/or Inactivating Pipeline Segments or
Conversion to Service procedures, as appropriate.
3.6 The Asset Integrity Engineer shall:
3.6.1 Utilize the Risk Analysis for New/Modified Pipelines process in consultation with the Project Manager for
3.7 completion and documentation of risk analysis when constructing or significantly altering pipelines.
The Supervisor of Pipeline Integrity shall:
3.7.1 Maintain the Abandoning Pipeline Segments Procedure, the Inactivating Pipeline Segments Procedure and
the Conversion to Service Procedure.
3.8 The Records Coordinator shall:
3.8.1 Segments and Conversion to Service procedures.
Retain and file all records as described in the Abandoning Pipeline Segments, Inactivating Pipeline

<<<PAGE 1289>>>

Date 2004
10/10/05 01/01/06 01/01/06 01/01/06
01/01/06 01/01/06 01/01/06
01/01/06 01/01/06 01/01/06 Magellan Midstream Partners, L.P.
INTEGRITY MANAGEMENT SIP–ADM–7.06
Asset Integrity 1/01/11 Revision: 7 Page 3 of 4
System Integrity Plan Change Log
Change Location Changed By Approved By: Brief Description of Change
Chabino Michael Pearson Integrated 7.12 into this initiative
Chabino Michael Pearson Removed the Project Manager
requirement to Notify the Facility Risk
Engineer of the incoming documents for
input/updating of the Facility Risk Model
per the Facility Risk Management Program
within 30 days of project completion.
Chabino Michael Pearson Removed the Project Manager
requirement to complete a Pipeline
Maintenance report and associated
documentation within 30 days of
completion of a pipeline project and
forward to the Pipeline Integrity Records
coordinator. It was redundant.
Chabino Michael Pearson Changed title from Facility Integrity
Supervisor to Risk Engineering Supervisor
Chabino Michael Pearson All
Eliminated the Facility Risk Management
program and incorporated it into the
Integrity Management Plan. Conducted
2004 Annual Review
All Chabino Michael Pearson Conducted 2005 Annual Review
Michael Pearson 2.3, 3.3.4, 3.3.5, 3.7 Pearson
Added standards to include abandoning
and inactivating activities
3.3.1
Pearson Michael Pearson Added statement to include Conversion to
Service requirements.
Chabino Michael Pearson 3.5
Added requirement for Pipeline Risk
Engineer to utilize risk analysis process for
new/modified pipelines
3.1.1 Chabino/Pearson Michael Pearson Removed “required” and “High
Consequence Areas”
3.2.1 Chabino/Pearson Michael Pearson Changed Asset Integrity Manager to Risk
Engineer
Chabino/Pearson Michael Pearson 3.3.1
Removed reference to Conversion to
Service procedure since redundant to new
3.3.4
3.3.2 and 3.3.3 Chabino/Pearson Michael Pearson Moved PHA requirements to Element 11
3.3.4 Chabino/Pearson Michael Pearson Combined 3.3.4 and 3.3.5
3.4.1 Chabino/Pearson Michael Pearson Changed 30 days to 45 days

<<<PAGE 1290>>>

01/01/06 01/01/06
06/06/06 06/06/06 06/06/06 10/16/06 05/17/07 09/11/07 9/11/07 9/11/07 9/11/07 02/04/08 10/23/08 01/01/10 08/30/10 01/01/11 12/31/11 Magellan Midstream Partners, L.P.
INTEGRITY MANAGEMENT SIP–ADM–7.06
Asset Integrity 1/01/11 Revision: 7 Page 4 of 4
3.4.2 Chabino/Pearson Michael Pearson Moved PHA requirements to Element 11
Chabino/Pearson Michael Pearson 3.5.2
Removed Pipeline Risk Engineer
requirement to comply with Conversion to
Service Procedure
3.4.1 Chabino/Pearson Michael Pearson Minor Modification to Paragraph. Deleted
45 days and inserted quarterly.
3.6 Chabino/Pearson Michael Pearson Deleted Facility Risk Engineer or Terminal
Operations Manager.
3.7 Chabino/Pearson Michael Pearson Deleted word Mapping out of title.
All Chabino/Pearson Michael Pearson Conducted 2006 Annual Review, no
changes
3.2 Chabino/Pearson Michael Pearson Added Paragraph 3.2 new responsibilities
for VP Operations
All Chabino/Pearson Michael Pearson Conducted 2007 Annual Review (see
change log)
3.1 Chabino/Pearson Michael Pearson Removed Director and inserted Manager of
AI Engineering
3.5 Chabino/Pearson Michael Pearson Removed Supervisor and inserted Manager
of AI Engineering
3.6 Chabino/Pearson Michael Pearson Removed Risk Engineer and inserted AI
Engineer
3.1
Combined Asset Integ Eng Mgr
responsibilities
3.3 and 3.4 Matt Argo Doug Chabino 2008 annual review. Changed title
Reviewed, no changes
3.8.2 Matt Argo Doug Chabino Removed 3.8.2, class location surveys
3.1 Changed title to Director
3.2
Moved 3.2.1 and 3.2.2 to Mgr of AI Eng
responsibility
Updated VP title to Sr VP of Operartions
3.8
Removed Compliance Coordinator
responsibilities
All 2012 annual review complete – no changes

<<<PAGE 1291>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 1 of 7
1.0 OBJECTIVE
1.1 2.0 DESCRIPTION
2.1 3.0 STANDARDS
The objective of this initiative is to provide a framework that complies with the security regulations governing the
Company and that protects the assets, employees, the environment, stakeholders and the community from security
threats.
This initiative incorporates the security requirements required by regulations applicable to Company assets and
operations. The Company will follow the landlord’s policies for security in the Bank of Oklahoma (BOK) Tower
located in Tulsa, Oklahoma. At any other leased and/or rented office space(s) the landlord’s policies will provide the
minimum security requirements for that office space.
Without Exception, Personnel Safety Is the First Priority.
3.1 The Director of Environmental, Health, Safety & Security (EHS&S) shall:
3.1.1 3.1.2 Serve as the Company Corporate Security Officer.
Establish a Security Management Team (SMT) responsible for ensuring Company security awareness to
employees and implementing security measures at the workplace, as needed. Convene as needed to
address security‐related topics/incidents.
Notify the SMT within 24 hours of any security incident at a Company asset, to include a summary of
notifications made and actions taken.
Maintain Minimum Physical Security Standards for Company assets.
3.1.3 3.1.4 3.1.5 Annually review the notification information in the Security Events Procedure.
3.1.6 Annually review the Company asset list with the SMT to validate the Company DOT Critical List.
3.1.7 Annually update Company contact information to the Transportation Security Administration (TSA) and the
Office of Pipeline Safety (OPS) for execution of notification protocols by each agency, as required.
3.2 The Operations Supervisor shall:
3.2.1 Develop, maintain and comply with the Facility Security Plan (FSP) using the Facility Security Plan
(Nonmarine) Template for facilities that have a loading rack and/or other loading area(s) (i.e.,
butane/ethanol/biodiesel), and facilities that ship loads of more than 792 gallons of hazardous liquids.
Complete a Facility Vulnerability Assessment (FVA) template prior to the development of the FSP. Address
any vulnerability identified by the FVA in the FSP.
3.2.1.1 Develop a FVA/FSP for any newly purchased loading rack/loading area facilities within 60 days
of purchase.
NOTE: The FSP for each marine facility will be developed on a site specific basis and
should comply with all United States Coast Guard (USCG) requirements.
NOTE: The Corporate Security Officer may determine (based on site specific factors)
that additional facilities (i.e., tank farm, pump station, etc.) require a FSP. If an
additional facility is determined to need a FVA and FSP, the Corporate Security Officer
will advise the Supervisor to ensure completion of these documents.
3.2.2 Conduct an annual (once per calendar year) review of the FSP and the FVA with all employees to ensure
familiarity with the plan and to identify inaccuracies or improvement opportunities. If there are any

<<<PAGE 1292>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 2 of 7
Revision: 9 improvements, update the FSP and submit to the EHS&S Compliance Specialist for uploading into the
Livelink Security Folder.
3.2.3 3.2.4 3.2.5 3.2.2.1 Note any changes in owner, operator or Corporate Security Officer in the annual review.
3.2.2.2 Complete the In‐Depth Security Training Form.
Revise and update the FSP when major changes involving the facility status or security organizations occur,
or as necessary to reflect other changing circumstances. Communicate these changes to affected
personnel via a SIP meeting, or via email if unable to attend an SIP meeting. Send the revised FSP to the
Safety Compliance Specialist for uploading into the Livelink Security Folder.
3.2.3.1 The following conditions at a minimum require a change to the FSP within 30 days:
3.2.3.1.1 Local Facility Security Officer change.
3.2.3.1.2 Modification of physical security.
3.2.3.1.3 Security procedure change.
3.2.3.1.4 Change in the facility’s configuration that materially alters the information
included in the FSP.
3.2.3.1.5 Change in the type of products handled, stored, or transferred that materially
alters the required response resources.
3.2.3.1.6 Any other changes that materially affect the implementation of the FSP.
Include all other conditions in the annual review.
Annually assess the facility using the Minimum Physical Security Standards.
Assess newly acquired facilities within 60 days of purchase and annually thereafter.
Use the appropriate Visitor Log and Safety Guidelines (Inland or Marine) for visitor identification,
3.2.3.2 3.2.4.1 verification and monitoring at each manned facility. Maintain completed logs locally as required. Conduct a
Visitor Safety Orientation for all visitors prior to their leaving the main office area.
NOTE: “Visitor” is defined as anyone, Company employee, contractor, or other, who
is not assigned to work at the facility. “Visitor” is not intended to include drivers,
cleaning crews, or delivery services (e.g., UPS, FEDEX, etc.).
3.2.6 Maintain the Key Control Log at the facility, listing by name and contact information whoever has been
provided keys and/or automatic gate openers for the facility.
NOTE: This requirement applies to employees who have keys and/or automatic gate
openers permanently assigned to them until termination or transfer, and temporary
keys and/or automatic gate openers that may be occasionally loaned to a contractor,
cleaning crew, or utility worker for occasional access to remote facilities.
3.2.7 3.2.8 3.2.9 3.2.10 Ensure all employees newly assigned to the facility receive Security Awareness Training within 90 days of
assignment to the facility.
Report any employee threat or threat to an employee to the Corporate Security Officer or Alternate
Corporate Security Officer with appropriate recommendations for ensuring workplace security.
Conduct annual drills and/or exercises as outlined in 6 CFR 27.255 and the Chemical Facility Anti‐Terrorism
Standards (CFATS) Site Security Plan if the facility is regulated by CFATS. CFATS facilities will be notified of
their status by the Alternate Corporate Security Officer.
3.2.9.1 Document security drills and exercises on the Security Drills and Exercises Form.
Comply with the Notification Procedure as outlined in Security Events.

<<<PAGE 1293>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 3 of 7
3.3 The Field Supervisor shall:
3.3.1 Periodically, not to exceed three years, review the Security Events Procedure and the Guidelines for
Reporting a Suspicious Call and/or Bomb Threat to a Facility with all employees to ensure they are aware of
At USCG regulated facilities, annually update Company contact information for execution of notification
what constitutes a Security Event
3.4 The Marine Terminal Supervisor shall:
3.4.1 Register all individuals who are assigned at a USCG regulated facility more than 90 days, into the HomePort
Database (or alternative approved registration format) within 30 days of their start date. This includes
employees, temporary employees, and/or contractors. If an individual has not previously been registered,
register the individual within five days, (but no later than the 90 days), at the point it is determined that
he/she will need access beyond the 90‐day period.
3.4.2 Ensure all new hire employees obtain a Transportation Workers Identification Credential (TWIC) upon
accepting an offer of employment.
3.4.3 Escort all new hire employees until they have acquired their TWIC card to allow unescorted access to the
facility.
3.4.4 protocols.
3.4.5 At USCG regulated facilities, annually update Company contact information to the USCG for execution of
notification protocols, as required.
3.4.6 Conduct security drills/exercises in accordance with 33 CFR 105.220 at all facilities regulated by the USCG.
3.4.6.1 Conduct drills every three months.
3.4.6.2 Conduct exercises annually, not to exceed 18 months between events.
3.4.6.3 Document security drills and exercises on the Security Drills and Exercises Form.
3.4.7 Maintain security related records at all facilities regulated by the USCG (33 CFR 105) for a period of two
years.
3.4.8 Submit and maintain approved USCG Facility Security Plans as regulated by 33 CFR 105.
3.5 The Operations Manager shall:
3.5.1 If employees are officed in a leased or rented space in excess of 30 days, determine if security measures
beyond the landlord’s polices are required and implement as needed.
3.5.2 For marine facilities:
3.5.2.1 Assign, in writing, a Facility Security Officer (FSO) for all facilities regulated by the Maritime
Transportation Security Act and provide training for the FSO to serve in that capacity.
3.5.2.2 For marine terminals, review security incidents, which are considered Security Sensitive
Information, with the personnel specified in the FSP.
3.5.2.3 Submit a 33 CFR 105 compliant FSP for newly acquired facilities regulated by the USCG to the
applicable Captain of the Port 60 days prior to close, or as soon as practical based on
confirmation of closing the acquisition.
3.5.3 Complete the Facility Security Plan (Nonmarine) Template (including the FVA) for all newly acquired
nonmarine facilities within 60 days of purchase and submit to the EHS&S Compliance Specialist.
NOTE: The Corporate Security Officer may determine based on site specific factors,
that additional facilities (i.e., tank farm, pump station, etc.) require a FSP. If an
additional facility is determined to need a FVA and FSP, the Corporate Security Officer
will advise the Supervisor to ensure completion of these documents.

<<<PAGE 1294>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 4 of 7
Revision: 9 3.5.4 Prepare and submit grant applications for security related costs, as applicable.
3.6 The Alternate Corporate Security Officer shall:
3.6.1 Submit “Top Screen” information to the Department of Homeland Security in compliance with CFATS:
3.6.1.1 When a facility is newly acquired.
3.6.1.2 When there are material modifications to an existing facility’s operations or site including
facility real estate or tank expansions.
3.6.1.3 On a resubmission schedule noted in CFATS regulations.
3.6.2 Coordinate the development of CFATS Security Vulnerability Analysis (SVA) and Site Security Plans (SSP) for
facilities that fall under CFATS regulations and submit when required by regulation.
3.6.3 Coordinate a drill and exercise program for CFATS facilities and facilities that are considered TSA critical.
3.6.4 Coordinate a TSA Critical Facility Workgroup to assess Company facilities against the TSA critical facility
standards.
3.6.5 Notify Operations of any facilities considered Transportation Security Administration (TSA) Critical.
3.6.6 Coordinate with Operations to develop Site Security Plans to comply with TSA guidelines.
3.6.7 Develop a Chemical Terrorism Vulnerability Information (CVI) based records retention program for CFATS
facilities.
3.6.8 Perform the duties of the Corporate Security Officer as needed.
3.7 The Project Manager shall:
3.7.1 Identify all contractors who have the potential to conduct work at a USCG regulated facility beyond a 90‐
day period on the job plan and/or project plan. Provide the Facility Supervisor the names of the contractors
listed on the job plan and/or project plan as soon as available, but no later than 30 days after the project
start date.
3.7.2 Require all contractors who conduct work at a USCG regulated facility to require their employees who will
be working in Company facility “Restricted” or “Secure” areas to obtain a TWIC card. Contractor employees
that do not have a TWIC, are required to be escorted at all times in these areas in compliance with 33 CFR
105.
3.8 The Security Management Team (SMT) shall:
3.8.1 Review security incidents and/or security breaches for nonmarine facilities to assess whether or not any
additional workplace security is warranted.
3.8.2 Review reported employee threats or threats to an employee to determine if additional security measures
and/or other actions are warranted.
3.8.3 Determine if a national, regional, or facility‐specific security threat could impact or change:
3.8.3.1 The Company’s Security Threat Level and/or
3.8.3.2 Require additional security measures at one or more of the Company’s facilities.
NOTE: The SMT is only tasked to address Company workplace security
issues/concerns. Employees visiting non‐Company facilities should comply with the
security requirements in‐place at those locations.
3.9 3.10 The EHS&S Compliance Specialist shall:
3.9.1 Upload the FSP to the Livelink Security Folder upon receipt.
The Supervisor of Pipeline Integrity Engineering shall:

<<<PAGE 1295>>>

Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Page 5 of 7
Revision: 9 3.10.1 Conduct a security analysis using the Valve Security Process to determine the appropriate security
measures to be implemented to protect against vandalism and unauthorized entry for DOT regulated
exposed facilities located outside of a facility (e.g., terminal, pump station or tank farm).
3.10.2 Reassessments should be considered whenever circumstances arise that suggests the need for a
reassessment. Types of circumstances may include security events, encroachments, land use changes,
threats, etc.
3.11 The Vice President of Technical Services shall:
3.11.1 Implement security measures as identified.
3.12 The Employee shall:
3.12.1 Report any personal or work‐related threat (verbal, written, etc.) to you or another employee to Supervisor
immediately.
3.12.2 Make notifications as described in the Security Level Procedures.
3.12.3 Make primary and secondary notifications if the Corporate Security Officer or the Alternate Corporate
Security Officer cannot be reached, and if the situation requires immediate notification. Notify the
Corporate Security Officer via voicemail or email that such notification(s) have been made.
3.12.4 Comply with the Security Events Procedure.
3.12.5 Comply with the Security Level Procedure.
3.12.6 Complete the Security Awareness Training within 90 days of assignment to a facility (terminals and tank
farms only).
3.12.7 Complete the Key Control Log as directed by Supervisor.
3.12.8 Lock all manually operated block valves upon completion of activity and prior to leaving the area.
3.12.9 Lock all gates and key buildings (manned and unmanned) anytime the facility is not occupied.
3.12.10 Complete the Visitor Log after verifying that a visitor has left the facility for the day and has not signed out
or notified Company personnel that he/she has left the facility.
3.12.11 Successfully obtain a TWIC card when unescorted access is required to secure areas of Company marine
facilities.
3.12.12 Complete the Declaration of Security Form for every vessel that comes to the dock only if the
Marsec level is elevated to level 2 and higher.

<<<PAGE 1296>>>

DATE 1/1/05 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 01/01/06 7/1/06 1/1/07 01/01/07 Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 6 of 7
System Integrity Plan Change Log
LOCATION BRIEF DESCRIPTION OF CHANGE
2.1 Added any other leased/rented office
3.1.1 Added
3.1.3 Added
3.1.5 Added
3.1.7 Added
3.2.3 Deleted
3.2.4 Added note box
3.2.5 Rephrased
3.2.6 Added
3.2.7 Added
3.2.8 Added
3.2.10 Added
3.3.2 Added
3.3.3 Added
3.4 Added
3.5 Added
3.1 Deleted “ Develop and maintain a Company Security Plan to comply with all regulatory security
requirements, including the Department of Homeland Security, Transportation Security Agency and the
Department of Transportation (TSA), the United States Coast Guard (USCG) and the Office of Pipeline
Safety (OPS).
NOTE: The Company Security Plan is a protected document with
limited employee access.
3.1 Deleted Annually validate and document that the Company’s facilities are in compliance with the
Company Security Plan and document.
Develop and maintain security related procedures, as required
3.19 Added for physical changes/improvements made to assets for the primary purpose of meeting the
Minimum Physical Security standards and/or security enhancements
3.2.2 Added site‐specific
3.1.8 Added
3.3.4 deleted “ records associated with training, drills and exercises and incidents/breaches of security for a
minimum”
3.2.11 added
3.2.3 added
3.2.4 Changed to 1 year from 3
2.1 Added “ At any other leased and/or rented office space(s) the landlord’s policies will provide the
minimum security requirements for that office space"
3.3.5 Deleted “Specifically, all Company marine facilities are required to conduct a security drill once every
three months.
3.5, 3.51, 3.5.2 and
3.5.3
Added
3.5.3.2 Note box added
3.6.1 Added
3.6.5 Added
4.0 Deleted link to Company Security Plan
4.0 Added “ Workplace Violence Policies and Guidance“
3.1.2 and 3.1.3 added
3.3.6 and 3.3.7 Added
3.3.7 Split “Complete a Security Vulnerability Assessment and the Facility Security Template for all newly
acquired non‐marine facilities within 60 days of purchase”. Into 2 responsibilities. Added as 3.1.9
3.3.7 Deleted “Assess the facility periodically using the Minimum Physical Security Standards.
3.2.12 and 3.6.1 Added to comply with new USCG regulations.
3.1.2 Added “convene as needed to address ….”
3.1.6 deleted

<<<PAGE 1297>>>

1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/07 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 1/1/08 01/01/09
01/01/10 7/1/10 01/01/11 12/31/11 12/31/11 Magellan Midstream Partners, L.P.
OPERATION ASSET PROTECTION SIP–ADM–8.01
Security 01/01/12 Revision: 9 Page 7 of 7
3.2.8 Combined with 3.2.7
3.3.7 Changed timeframe to 60 days. Added reference to SVA
3.6.1 Rephrased
3.8 added
3.9 and 3.10 added
3.11.7, 3.11.8 added
3.2.13, 3.2.10 added
3.6 added
3.1.8 Added
3.1.6 Added SMT reviews DOT “Critical” list.
3.2.1 plus note Clarify when a FSP is required at Non‐marine loading facilities.
3.2.3 Added requirements including timeframe for changes to FSP.
3.2.15 Added (moved) responsibility for updating COTP with contact information from the Director of EHS to
Operations Supervisor.
3.2.16 Added (moved) responsibility for completing drills and exercises from the Operations Manager to the
Operations Supervisor.
3.3.5 Added requirement for Submittal and maintain FSP for Marine terminals as required by 33 CFR 105.
3.6.2 Added TWIC credential requirements for contractors.
3.11.9 Added requirement for all affected employees at marine facilities to obtain TWIC as needed.
3.1.10 new
3.2.16.3 new
3.11 New role/responsibilities
3.12.2.1 New
3.12.9 new
3.3 Added marine area supervisor
3.3.2 Added date
3.1.9 Renamed form Facility Vulnerability Assessment
3.2.4 Changed frequency
3.2.8 Changed supervisor role from providing training to ensuring they receive
3.2.5 Changed frequency
3.2.10 Added CFATS language
3.5 Added Alternate Security officer duties
4.2, 4.5, 4.9,
4.10,4.13
Changed name of link to
3.1.8, 3.1.9 Removed. “Maintain BU summary for assest changes/improvements” and “complete FVA for new;y
acquired marine facilities”
3.2.2.2 Removed, added annual (once per calendar year) to 3.2.2
3.2.1.1 New
3.4.3 Changed submission to EHSS Compliance Specialist (was Dir EHSS)
3.2.1 Modified per new requlatory requirement for facilities shipping > 792 gallons of hazardous liquids.
Reviewed, no changes
3.3.6.2 Removed “once per calendar year not to exceed 365 days”, replaced with
“annually, not to exceed 18 months” as per 33 CFR 105.220.
3.11.12 added
3.2.2.2 added
3.2.8 Removed “or newly hired at a facility
3.3 Added field supervisor
3.4 Revised to marine terminal supervisor
All 2012 Annual Review complete

<<<PAGE 1298>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Revision: 8 Page 1 of 5
1.0 OBJECTIVE
1.1 1.2 1.3 The objective of this initiative is to promote public awareness of underground utilities, damage prevention
and emergency preparedness. Collectively, this initiative will enhance public safety and minimize damage
to property, the environment and Company assets. The Company’s Public Awareness Program was
developed to comply with the standards established in American Petroleum Institute’s (API)
Recommended Practice (RP) 1162.
Company management supports Public Awareness through Company policy, management participation,
and allocation of resources and funding as described in the System Integrity Plan Magellan Management
Commitment and Support Introduction and the Management Support Cover Letter.
Public Awareness is a critical component of our overall safety program. includes the following lines:
The Public Awareness Program
Company Name Product PHMSA Operator Identification
Number
Magellan Pipeline Company, L.P. HVL 22610
Magellan Pipeline Company, L.P. Refined 22610
Magellan Pipelines Holdings, L.P. Refined 31579
Magellan Terminals Holdings, L.P. Crude 31580
Magellan Terminals Holdings, L.P. Refined 31580
Magellan Ammonia Pipeline, L.P. Ammonia 12105
Osage Pipe Line Company, LLC Crude 14391
2.0 DESCRIPTION
2.1 The Company’s Pipeline Awareness Program for DOT 195 jurisdictional lines will include information and
provide instruction to the affected public, emergency officials, local public officials and excavators on the
following:
2.1.1 Pipeline purpose and reliability.
2.1.2 Awareness of hazards or potential hazards and prevention measures.
2.1.3 Damage Prevention Awareness.
2.1.4 One Call requirements.
2.1.5 How to recognize, report and respond to leaks and/or emergencies involving Company operated
pipelines and facilities.
2.1.6 How to identify the location of Company operated pipelines, rights-of-way, facilities, and
description of the purpose of pipeline markers and the information on them.
2.1.7 Emergency Preparedness Communications.
2.1.8 The “Call Before You Dig!” Campaign and the national One Call number 811.
2.1.9 How to access a list of pipeline operators through the National Pipeline Mapping System (NPMS).
2.1.10 How to obtain additional information.

<<<PAGE 1299>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 2 of 5
Revision: 8 2.2 This initiative provides guidance to Company employees on the communication of Emergency Response
Plans (ERPs) to Local Emergency Planning Committees (LEPC) and Emergency Response Agencies
(ERA).
3.0 STANDARDS
3.1 The One Call Supervisor and Public Awareness & Communications Specialist shall:
3.1.1 3.1.2 Administer the Public Awareness Program for DOT jurisdictional assets.
Determine annually, the acceptable pipeline awareness programs and annual mailings for the
upcoming year. Develop the message content of these programs as described in the Message
Content Guidelines.
3.1.3 Perform an annual audit of the Public Awareness Program to ensure the program has been
developed and implemented according to the guidelines in RP 1162. Document on the Annual Self
Assessment.
3.1.4 3.1.5 3.1.6 3.1.7 3.1.8 3.1.9 3.1.10 Perform an Effectiveness Evaluation of the Public Awareness Program before September 1st every
four years in accordance to the guidelines in RP 1162.
Maintain all program evaluations, including current results, follow-up actions, expected results and
annual assessments for five years.
Implement the Annual Mailings Procedure annually.
Conduct a pretest of public awareness materials for audience appeal, message clarity,
understandability, and retention before they are widely used. A pretest can be performed using a
small representative audience that is not involved with the development of the Public Awareness
Program.
Annually review and update the public education and damage prevention section of Magellan’s
Internet Site, if necessary.
Maintain and annually update the Public Awareness Folder in Livelink and the Emergency
Response Guide.
Coordinate with Asset Integrity and Operations personnel to ensure that the ERP Summary Folders are
prepared, maintained and distributed to the appropriate LEPC and/or specific local ERAs.
3.1.11 Approve any deviations from the print ad or radio ad standards upon request.
3.1.12 Oversee public education efforts for assets covered per the Mitigation Plan to ensure that ERAs
within each county that the pipeline passes through will be contacted annually (not to exceed 15
months) in person and provided with maps of the system.
3.2 The Operations Manager shall:
3.2.1 Communicate Emergency Response Plans to LEPC/ERAs.
3.2.2 Maintain a current address listing of LEPC/ERAs that could respond to a Company emergency.
Provide this mailing list to the Public Awareness and Communications Specialist for the annual
Mail Out Program.
3.2.3 3.2.4 Maintain an ongoing LEPC/ERAs meeting schedule.
In addition to annual mailings to LEPCS/ERAs, conduct meetings on a rotating basis, with a
minimum of 25% of the listed LEPC/ERAs once every 12 months, not to exceed 15 months.
Conduct a meeting with each listed LEPC/ERAs at least once in a four-year calendar period.
3.2.5 Conduct meetings following the LEPC/ERA Meeting Requirements. For Intrastate pipelines in
Texas, conduct face-to-face meetings with designated ERA officials annually per the LEPC/ERA
Meeting Requirements.
3.2.6 Complete the LEPC/ERA/Stakeholder Meeting Form for each meeting. Distribute the appropriate
updated response plan documentation (ERP, ERAP, etc.) during each meeting.
3.2.7 Complete, at a minimum, one supplemental outreach activity per year within each operating area.

<<<PAGE 1300>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 3 of 5
Revision: 8 Consider external factors along the pipeline system and assess if some additional level of public
awareness communications is warranted of if other supplemental/enhanced outreach activities are
needed.
3.2.7.1 Use the Relevant Factors Assessment in making the evaluation and the Approved
Media and Delivery Methods Procedure to determine the appropriate activity.
NOTE: are required.
There may be circumstances where multiple outreach activities
3.2.7.2 For each Supplemental/Enhanced Outreach Activity, complete the
LEPC/ERA/Stakeholder Meeting Form, provide supporting documentation and send to
the District Office or location and the Public Awareness and Communication
Specialist.
Maintain copies of all materials provided to each stakeholder audience in the local files for five
3.2.8 years.
3.2.9 File the completed LEPC/ERA/Stakeholder Meeting Form for five years.
3.3 The Employee shall:
3.3.1 Use the LEPC/ERA/Stakeholder Meeting Form to conduct and document pipeline safety
awareness discussions with ERAs, public education and third party damage prevention
stakeholder groups. Forward completed forms to the appropriate area office.
3.4 The One Call Coordinator shall:
3.4.1 Request documentation from state One Call Centers for their community outreach or public
awareness activities. Information may be obtained by website if available or phone solicitation.
Sort the information by state and retain for five years.
NOTE: Most state One Call Centers provide public awareness activities; Magellan
can incorporate these activities into its Public Awareness Program.
3.5 3.6 3.4.2 3.4.3 3.4.4 3.4.5 Request address listings from each applicable state One Call agency and the Company internal
database of all contractors and individuals engaged in excavation activities during the previous 12
months in each state where Company assets are located. Forward the data to the vendor for
incorporation into the annual mailings.
Advise the Operations Managers, Asset Integrity Supervisors, and Operations Control Manager of
the annual mail out messages at least ten days before distributing the mail outs.
Utilize the Company Damage Prevention Newsletter to inform employees about the Public
Awareness Program objectives.
File the LEPC/ERA forms and Supplemental/Enhanced activity documentation in the appropriate
Damage Prevention folder in Livelink.
The Regulatory Compliance Coordinator shall:
3.5.1 Initiate biennial (beginning January 15, 2005 and every two years thereafter) Educational Center Surveys in
accordance with the Texas Public School Survey Procedure for Railroad Commission of Texas regulated
assets.
The Operations Supervisor in Texas shall:
1.1.1 Conduct public school surveys (psb) upon notification from the Regulatory Compliance Coordinator.
Forward the PSB Survey information to the Regulatory Compliance Coordinator within 60 days of the
request, but no later than December 15th
.

<<<PAGE 1301>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS Community Relations 01/01/12 Page 4 of 5
Date Change Change 1/1/05 All
1/1/05 3.2.6 Greg Walker
1/1/05 3.2.1 1/1/06 All
1/1/06 2.1 1/1/06 3.0 1/1/06 3.0 1/1/06 3.2.2 1/1/06 3.5 1/1/06 3.5.2 1/1/06 3.5.3 Greg Walker
1/1/06 3.5.4 1/1/06 Multiple 1/1/06 3.1.6 1/1/06 3.2.4 1/1/06 3.4.1, 3.4.2 1/1/06 3.2.3 1/1/06 3.2.2 1/1/07 All
1/1/07 1.0 1/1/07 3.1.3 Greg Walker
1/1/07 2.1.1, 2.1.7 1/1/07 3.2.1.1 9-10-07 All
9/10/07 3.2.1.6 9/10/07 3.4.1 Greg Walker
9/10/07 3.2.2 9/10/07 3.3.1 10/08/08 All
10/08/08 3.1.8 10/08/08 3.1.10 10/08/08 3.2.2.5 10/08/08 3.3.1 Greg Walker
10/08/08 3.4.1 10/08/08 3.5.1 10/08/08 3.5.2 10/08/08 3.5.4 10/08/08 3.5.5 1/1/09 3.6, 3.7 02/01/09 3.5.2 7/28/09 All Greg Walker 07/28/09 3.1.7
Mike
07/28/09 3.2 SIP–ADM–10.01
Revision: 8 SYSTEM INTEGRITY PLAN CHANGE LOG
Brief Description of Change
Conducted 2004 Annual Review see change log
Moved responsibility to develop and maintain lists of Emergency responders to Operations
Supervisors as new Section 10 3 1 5
Added Public Education and Third Party Damage Prevention Program
Conducted 2005 Annual Review see change log
Deleted the objectives of a public awareness program
Deleted information about the federal stds. the procedure was developed under.
Developed Magellan’s “Commitment to the Program.”
Deleted Operator’s responsibility of overseeing and approving budgetary responsibility.
Changed OneCall Analyst to OneCall Coordinator
Deleted request for address of Contractors form OneCall and documentation of Awareness
Program distributed Also requirement to have this information forwarded to Operations Mgr
Deleted requirement to establish and maintain the Public Awareness Program and annual
review of program
Deleted references to National Alliance Programs.
Added content for API RP1162 compliance.
Added “to determine if additional outreach programs are needed.”
added
clarified
Added retention time and location
Rephrased and defined summary report
Conducted 2006 Annual Review see change log
Added Management Support Documentation: E1 Goals and Management Support Cover
Letter
Added Effectiveness Evaluation Requirements
added
added
Conducted 2007 Annual Review see change log
Moved this to new section entitled, “3.3 Longhorn Specific Requirements:”
Added One Call membership requirement in response to PHMSA Clearing House
comments
Added additional Relevant Factors and clarified direction for Supplemental Outreach
Activities in response to PHMSA Clearing House comments
Added new wording to this section
Conducted 2008 Annual Review see change log
Deleted – Monitor activities and determine if additional is needed.
Added from E12-Maintain Public Awareness folder and ER Guide. This replaces the
previous ERP distribution process
Added location for supplemental documentation
Added administrator for Longhorn. Moved previous 3.3.1 to 3.3.2
Deleted Operations Manager or Asset Integrity (AI) Supervisor and changed to appropriate
area office
Added option for website retrieval and retention time. Deleted distribution to Operations
Managers/ AI Supervisors
Added Manager of Damage Prevention for incorporation into the annual mailings. Deleted
distribution to Operations Manager/AI Supervisors
Added: Include PA objectives in One-Call newsletter
Added: File Supplemental Documents in Livelink folder
Moved from SIP 7.08
Changed Title to Mgr of Damage Prevention and Design Services
Conducted 2009 Annual Review see change log
Changed “Pipeline” to “Public”
Changed the title to, “Assets Covered Per Mitigation Plan”

<<<PAGE 1302>>>

Magellan Midstream Partners, L.P.
PUBLIC AWARENESS SIP–ADM–10.01
Community Relations 01/01/12 Page 5 of 5
Date Change Change 07/28/09 3.3.2.3 Hampton 07/28/09 3.3.4 07/28/09 3.3.5 07/28/09 3.4
07/28/09 3.6.2 07/28/09 3.6.4 01/01/11 2.1 3.1 3.1/3.2.2/3.2.7 8/29/11 2.1 8/29/11 3.1 3.1.4 8/29/11 3.2.2 8/29/11 3.2.7.2 12/31/11 All Revision: 8 Brief Description of Change
Added “And Design Services”
Deleted Section Maintain the information sent from the One Call Coordinator in the Local file
for five years Added “For Five Years”
This information includes documentation of the Public Awareness activities
Deleted Section
Added “ And Magellan’s Internal Database” Deleted “Sort this information by operating area
and forward to the manager of Damage Prevention and Design Services” Added “Forward
Deleted “Include Public Awareness Objectives in the One Call Newsletter.” Added “ Utilize
Removed DOT 192
Changed Mgr of Design Services and Compliance to One Call Team
Changed title to One Call Team Leader
Added list of specific pipeline assets covered by the PAP.
Changed title to One Call Supervisor Public Awareness Comm. Spec.
Added date
Changed title to Public Awareness Comm. Spec.
Changed title to Public Awareness Comm. Spec.
2012 Annual Review complete

<<<PAGE 1303>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6F
SURGE ANALYSIS SUMMARY

<<<PAGE 1304>>>

Milepost 2.4 2.4 2.4 2.4 12.0 12.0 21.2 21.2 34.1 34.1 34.1 63.8 63.8 64.1 64.1 112.9 112.9 112.9 133.9 133.9 135.5 135.5 139.3 139.3 141.8 FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6F
SURGE ANALYSIS SUMMARY
MITIGATIONS UPDATED
Valve Description Surge Mitigation ROV 235 (East Houston Terminal) PRV-235 ROV 235 (East Houston Terminal) PRS-01 ROV 236 (East Houston Terminal) PRS-02 ROV 237 (East Houston Terminal) PRS-03 ROV (Mesa Road/FM527) GS5 PRS-01 ROV (Mesa Road/FM527) GS5 PRV-01 ROV (Sweetwater Lane) GS6 PRS-11 ROV (Sweetwater Lane) GS6 PRV-11 Satsuma ROV (GS7) PRS-01 Satsuma MOV2 PRS-02 Satsuma MOV4 PRS-04 Satsuma ROV14 (SE1) PRS-14 Satsuma MOV12 PRS-12 Satsuma MOV13 PRS-13 Satsuma overall PRV-01 ROV (E. Side Brazos River) SE2 PRV-11 ROV (E. Side Brazos River) SE2 PRS-11 ROV (W. Side Brazos River) SE3 PRS-01 ROV (W. Side Brazos River) SE3 PRV-01 ROV (Warda Sta) Incoming SE4 PRS-04 ROV (Warda Sta) Incoming SE5 PRS-05 Warda overall PRV-01 ROV (E. Side Colorado River) SE6 PRV-01 ROV (E. Side Colorado River) SE6 PRS-01 ROV (W. Side Colorado River) SE7 PRS-01 ROV (W. Side Colorado River) SE7 PRV-01 ROV (SH 304) SE 7A (formerly CV8) PRS-01 ROV (SH 304) SE 7A (formerly CV8) PRV-01 Bastrop Control Valve PCV-01 Bastrop Control Valve (Bypass Surge Relief) PRV-01 Bastrop MOV4 PRS-04 Bastrop MOV5 PRS-05 Bastrop MOV6 PRS-06 Bastrop MOV7 PRS-07 Bastrop MOV2 PRS-02 Bastrop MOV3 PRS-03 Bastrop ROV1 PRS-01 Set Pressure
340 psig
340 psig
340 psig
340 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
650 psig
625 psig
625 psig
625 psig
650 psig
650 psig
650 psig
650 psig
640 psig
640 psig
646 psig
850 psig
850 psig
850 psig
850 psig
850 psig
850 psig
850 psig
850 psig

<<<PAGE 1305>>>

Milepost 148.3 148.3 166.7 166.7 171.5 171.5 172.3 172.3 174.9 174.9 175.5 175.5 177.1 177.1 181.6 181.7 185.9 185.9 186.9 186.9 194.3 194.3 198.6 198.6 199.0 199.0 199.6 199.6 203.5 203.5 211.9 211.9 216.6 FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Valve Description Surge Mitigation Set Pressure
ROV (FM535) SE7B (formerly CV9) PRS-01 825 psig
ROV (FM535) SE7B (formerly CV9) PRV-01 825 psig
ROV (U.S. HWY 81) SE8 (East Aquifer) PRS-01 825 psig
ROV (U.S. HWY 81) SE8 (East Aquifer) PRV-01 825 psig
ROV (Sendera Mesa Drive) (Austin Aquifer) PRS-01 700 psig
ROV (Sendera Mesa Drive) (Austin Aquifer) PRV-01 700 psig
ROV (Beckett Rd) (Austin Aquifer) PRS-01 700 psig
ROV (Beckett Rd) (Austin Aquifer) PRV-01 700 psig
ROV (Silver Mtn Road) (Austin Aquifer) PRS-01 680 psig
ROV (Silver Mtn Road) (Austin Aquifer) PRV-01 680 psig
ROV (Ramble 3 St) (Austin Aquifer) SE9 PRS-01 660 psig
ROV (Ramble 3 St) (Austin Aquifer) SE9 PRV-01 660 psig
ROV (US HWY 290) (Austin Aquifer) PRS-01 610 psig
ROV (US HWY 290) (Austin Aquifer) PRV-01 610 psig
Cedar Valley Control Valve PCV-01 660 psig
Cedar Valley Control Valve (Bypass Surge Relief) PRV-01 850 psig
Cedar Valley High Pressure Shutdown PSH-01 710 psig
Cedar Valley MOV8 PRS-08 735 psig
Cedar Valley MOV9 PRS-09 735 psig
Cedar Valley MOV10 PRS-10 735 psig
Cedar Valley ROV6 PRS-06 735 psig
Cedar Valley MOV11 PRS-11 850 psig
Cedar Valley MOV12 PRS-12 850 psig
Cedar Valley MOV13 PRS-13 850 psig
ROV (Fitzhugh Creek) (Austin Aquifer) PRS-01 815 psig
ROV (Fitzhugh Creek) (Austin Aquifer) PRV-01 815 psig
ROV (Oak Forest Drive) (Austin Aquifer) PRS-01 780 psig
ROV (Oak Forest Drive) (Austin Aquifer) PRV-01 780 psig
ROV (Ulrich Rd) (formerly CV10) PRS-01 840 psig
ROV (Ulrich Rd) (formerly CV10) PRV-01 840 psig
ROV (E. Side Pedernales River) SE11 PRV-01 900 psig
ROV (E. Side Pedernales River) SE11 PRS-01 900 psig
ROV (W. Side Pedernales River) SE12 PRS-01 900 psig
ROV (W. Side Pedernales River) SE12 PRV-01 900 psig
ROV (W. Side Pedernales River) SE4 (formerly CV4) PRS-02 900 psig
ROV (W. Side Pedernales River) SE4 (formerly CV4) PRV-02 900 psig
ROV (Cypress Mill Rd, CR 301) (formerly CV5) PRS-01 925 psig
ROV (Cypress Mill Rd, CR 301) (formerly CV5) PRV-01 925 psig
ROV (W Side Sandy School Rd) SE13 (formerly CV6) PRS-01 900 psig
ROV(W Side Sandy School Rd) SE13 (formerly CV6) PRV-01 900 psig
ROV (W. Side White Oak Creek) SE13A (formerly CV7) PRS-01 775 psig

<<<PAGE 1306>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
Milepost Valve Description Surge Mitigation Set Pressure
216.6 ROV (W. Side White Oak Creek) SE13A (formerly CV7) PRV-01 775 psig
227.9 ROV (Eckert Sta) SE 14 PRV-01 700 psig
227.9 ROV (Eckert Sta) SE 14 PRS-01 700 psig
276.5 ROV (E. Side Llano River) SE16 PRV-01 820 psig
276.5 ROV (E. Side Llano River) SE16 PRS-01 820 psig
276.8 ROV (W. Side Llano River) SE17 PRS-01 820 psig
276.8 ROV (W. Side Llano River) SE17 PRV-01 820 psig
281.0 ROV (US HWY 377) (formerly CV12) PRS-01 750 psig
281.0 ROV (US HWY 377) (formerly CV12) PRV-01 750 psig
282.6 ROV, SE17A (formerly CV13) PRS-01 680 psig
282.6 ROV, SE17A (formerly CV13) PRV-01 680 psig
295.2 Kimble County Control Valve PCV-01 561 psig
Kimble County Control Valve (Bypass Surge Relief) PRV-01 700 psig
Kimble County High Pressure Shutdown PSH-01 611 psig
Kimble County MOV12 PRS-12 636 psig
Kimble County MOV13 PRS-13 636 psig
Kimble County MOV14 PRS-14 636 psig
Kimble County MOV2 PRS-2 636 psig
Kimble County MOV4 PRS-4 636 psig
Kimble County ROV (SE19) PRS-1 636 psig
Kimble County MOV11 PRS-11 636 psig
324.7 ROV (CR 245) (formerly CV14) PRS-01 850 psig
324.7 ROV (CR 245) (formerly CV14) PRV-01 850 psig
341.7 ROV (W. Side Antelope Draw) SE21A (formerly CV15) PRS-01 850 psig
341.7 ROV (W. Side Antelope Draw) SE21A (formerly CV15) PRV-01 850 psig
346.7 ROV (FM 190) SE21B (formerly CV16) PRS-01 850 psig
346.7 ROV (FM 190) SE21B (formerly CV16) PRV-01 850 psig
457.5 Crane Control Valve PCV-01 853 psig
Crane High Pressure Shutdown PSH-01 903 psig
9.5 East Houston Control Valve PCV-293 860 psig
East Houston High Pressure Shutdown PSH-293 910 psig
1.8 Holland Ave ROV-107 PRS-107 700 psig
1.8 Holland Ave ROV-107 PRV-107 700 psig
0.9 North Houston Ship Channel ROV-100 PRS-100 700 psig
2.5 Speed Jct ROV-200 PRV-201 700 psig
Note: PRV = Pressure Relief Valve
PRS = Pressure Reversal Switch
PCV = Pressure Control Valve
PSH = Pressure Shutdown Switch

<<<PAGE 1307>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
SURGE ANALYSIS SUMMARY
OPERATING PRESSURE SUMMARY
Segment Description Pump Station
Maximum
Discharge Set
Pressure (psig) MOP (psig)
Maximum Pressure
Normal Operations
(Steady State) (psig)
Maximum Surge
Pressure (psig)
Crane 853 853 820 550 850
900
Crane (MP 457.54) to MP 415.3 (Texon) MP 415.3 (Texon) to MP 341.6 1034 953 MP 341.6 to MP 295.2 (Kimble County) 853 1012 390 910
MP 295.2 (Kimble County) to MP 181.6 (Cedar Valley) Kimble County 561 959 525 955
MP 181.6 (Cedar Valley) to MP 141.72 (Bastrop) Cedar Valley 660 1012 675 960
Bastrop (PCV
MP 141.72 (Bastrop) to MP 112.9 (Warda)
only) MP 112.9 (Warda) to MP 69.0 646 965 590 750
MP 69.0 to MP 34.1 (Satsuma) MP 34.1 (Satsuma) to MP 2.4 (East Houston) 646 646 646 1012 1012 786 575 550 540 950
795
750
MP 9.47 (East Houston) to MP 1.21 (9th Ave.) East Houston 860 936 860 925

<<<PAGE 1308>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6G
RISK IMPLICATION MATRIX

<<<PAGE 1309>>>

Pro~ed Action Valve reconfigurations Change hydraulic profile Change in product Change in O&M Station reconfigurations Use of existing System Details Possible Initial Impact on PoF Impact on CoF PoF assumptions
Reduction in PoF ext corr change In potential release volumes Reduction in PoF third party drain abn corr < soil corr; hot spot
added; no AC issues; no
shielding
1,607 rt of pipe replaced at 271ocations Increase in Pof impacts leak detect increase in PoF sabotage
impacts>excav exp; mit does
not offset impact exp; same
pipe wall
increase in PoF geotech Reduction in other PoF from removal of anomalies
erosion, flood, freeze,
windstorm, fire, lightning
reverse flow increase in PoF cracking change in toxicity
higher viscosity product higher Howrate increase in PoF ext carr Increase in Pof int carr change in hazard zone
dimensions
change in rupture potential
increase in PoF inc ops, incl surge -43 miles>100%SMYS_avail
crude oil increase In PoF Inc ops, incl surge
sour crude Increase in Pof int corr
paraffin formation increase in PoF surge
ORA injection paraffin formation increase in PoF inc ops
increase in PoF surge
int corr control
maintenance pigging
inhibitor injection Reduction in PoF int corr
Monitoring
IMP
Inhibitor injection change in rupture potential
ORA injection
change in pumps change in pum~related
devices
increase in PoF inc ops, inc! surge
currently existing weaknesses pre-existing active failure mechanisms
increase in all PoF increase rupture potential in possibly-weak areas
change In rupture potential
-43 miles>100%SMYS_avail

<<<PAGE 1310>>>

FINAL ENVIRONMENTAL ASSESSMENT OF THE LONGHORN PIPELINE REVERSAL
APPENDIX 6H
SPARTAN ENGINEERING REPORT

<<<PAGE 1311>>>

Pipeline Leak
Detection Systems -
Direct Detection
Prepared for:
MAGELLAN MIDSTREAM PARTNERS, L.P.
October 18, 2011
(R3)
By:
SPARTAN
ENGINEERING INC.

<<<PAGE 1312>>>

CONTENTS
1.0
Overview
2.0
Executive Summary
3.0
Types of Leak Detection Systems
3.1
General
3.2
Liquid Sensing Leak Detection
3.3
Vapor Sensing Leak Detection
3.4
Fiber Optic Leak Detection
3.5
Ultrasonic/Acoustical Leak Detection
3.6
Comparison
4.0
Conclusions and Recommendations
5.0
Appendix
5.1
Corporate Contact Info
5.2
Tycho Thermal Controls Data
5.3
Asel-Tech Data
5.4
Nitor Technologies Data
5.5
Sensornet Data

<<<PAGE 1313>>>

1.0 Overview
Magellan is interested in currently available technology for early detection of pipeline leaks that
can be employed on the section of the Longhorn pipeline traversing the Edwards Aquifer.
Additionally, because the Longhorn Reversal project will introduce crude oil to the line, there is
interest in the capability of these systems to adequately detect crude oil.
This report focuses on the direct sensing style of pipeline leak detection systems that are most
capable of detecting small leaks. The direct methods include liquid sensing cables, fiber optic
cables, vapor sensing tubing, and ultrasonic sensing. Information on these direct sensing methods
(and companies that can provide them) has been compiled from an extensive search and is
included in appendices of this report.

<<<PAGE 1314>>>

2.0 Executive Summary
Each of the four direct pipeline leak detection technologies investigated will detect crude oil. Direct
detection methods are best at detecting leaks that are less than about 0.5% of the pipeline flow
rate, while computational methods are best at detecting leaks that are greater than about 0.5% of
the pipeline flow. Therefore, to cover all circumstances, it is recommended Magellan maintain
both types of systems. For the direct sensing method, it is recommended to retain the existing
Tyco TraceTek TT5000 system. It has the advantage of already being in place, it has the ability to
detect leaks as small as 0,01 GPH, it can locate leaks accurately, and it has proven to be reliable.
The liquid sensing cable systems are the most sensitive for detecting small leaks with a 2-3 hour
response time. The existing Tyco TraceTek TT5000 is extremely robust and reliable and capable of
detecting leaks as low as 0.01 GPH and is not impacted as much because of soil porosity, soil
temperature and low vapor pressure as the other systems reviewed. See Section 3.2 under Tyco
TraceTek TT5000 for a detailed discussion.
Vapor sensing systems are not as sensitive to small leaks or to leaking materials with very low vapor
pressures, such as heavy oils. Additionally, response time is more dependent on soil porosity and
soil temperature than the liquid sensing systems. The minimum detectable leak size is 0.04 GPH, in
high-sensitivity mode. See Section 3.4 under Nitor Technologies for a detailed discussion.
Fiber-optic cable systems and acoustic sensing systems are very poor at detecting small leaks.
These units rely on either a change in temperature or an acoustic footprint to detect leaks. These
systems are very reliable when detecting leaks of highly volatile liquids but they are not suitable for
crude oil since the leak does not develop a sufficient differential temperature (essentially ground
temperature) nor does it develop enough acoustic energy to allow the system to reliably detect a
small leak. Additionally, the reliability decreases as the vapor pressure of the material to be
detected approaches zero.
See Section 3.4 Fiber Optic Leak Detection and Section 3.5
Ultrasonic/Acoustical Leak Detection for a brief discussion.

<<<PAGE 1315>>>

3.0 Types of Leak Detection Systems
3.1 General
The available pipeline leak detection systems (LDS) fall, generally, into two broad classes; 1)
discussed because this topic is beyond the scope of this report.
Direct detection, and 2) Computational/Statistical. Computational/Statistical will not be
API Publication 1149 outlines methods for calculating the size of a leak in terms of the total
pipeline flow rate. This leak rate is often described as a percent of the total pipeline flow with
the total flow given to estimate the leak size.
The direct detection methods are associated with efforts to detect leaks with sensing systems
that can locate the leak within a few meters of its origin. These include: 1) Liquid Sensing leak
detection, 2) Vapor sensing leak detection, 3) Fiber-optic leak detection, and (4)
Ultrasonic/Acoustical leak detection.
Direct leak detection depends upon a sensing system in the area around the location that has
been deemed to be most sensitive to the effects of a pipeline leak. These detection techniques
depend upon a change in some physical property associated with the pipeline, the pipeline
surroundings, or changes to a sensor based on some characteristic of the leaking fluid. These
can be summarized as: 1) the conductivity (or electrical resistance) of the cable; 2) localized
temperature changes; 3) some characteristic physical effect that is always associated with a
leak, such as the presence of vapor, or the sound associated with a leak.
3.2 Liquid Sensing Leak Detection
Liquid sensing cables are buried beneath or adjacent to a pipeline and are specifically designed
to detect changes in transmitted energy pulses as a result of impedance differentials induced
by contact with hydrocarbon liquids. Safe energy pulses are continuously sent by a
microprocessor through the cable. The pulses are reflected and returned to the micro-
processor. Based on the specific installation of the cable, a baseline reflection map is stored in
the memory of the microprocessor. When a leak occurs, a portion of the cable is saturated
with fluid. The fluid alters the impedance of the sensing cable, which in turn alters the
reflection pattern returning to the microprocessor. The change in signal pattern causes the
microprocessor to register a leak alarm that also locates the position of the altered impedance.
Controller interface software is available to provide real-time information on leak detection and
record keeping. Cable types are chosen for each application based on the specific type of fluid
being monitored.
The cable detects a leak independently of the leak rate and thus is a good choice for small
leaks, which are more difficult to detect than large leaks. The sensor cable responds directly to
the presence of the liquid and not to the rate at which it arrived. Additionally, the leak
detection cable can report the spill location to an accuracy of a few feet.
Liquid sensing leak detection is typically marketed as a self-contained leak detection and
location system, including all hardware and software. Advantages include relatively high
3

<<<PAGE 1316>>>

software configuration and maintenance.
accuracy in determining leak location, no modifications to existing pipeline, and simple
A system that detects oil leaks based on a change in electrical resistance is the Tyco TraceTek
TT5000. The Tyco system can locate leaks to within a few feet of their source. An analysis of
the Tyco TraceTek TT5000 leak detection cable currently used on the Longhorn Pipeline System
is provided to determine its applicability to a crude oil pipeline.
Iyco TraceTek TT5000 Leak Detection Cable
The Tyco TraceTek TT5000 leak detection cable currently in use on the Longhorn Pipeline
System is usable for detecting crude oil leaks, as demonstrated by Tyco (see Table below). The
minimum detectable leak size is 0.01 GPH. The TraceTek cable system is apparently the only
electrical conductivity cable available. It should be noted that after a leak is detected by the
cable, the portion of the cable that was exposed to the leak must be replaced.
Tyco Thermal Controls has performed testing on three different oils, West Texas Intermediate
(WTI), West Texas Sour (WTS) and ARCO North Slope Oil. The results of these tests are
summarized in the table below.
TT5000 Response Time
Oil Type
Temperature 68°F
Temperature 104°F
WTI
92 to 93 minutes
15-20 to 22 min
WTS
184 to 190 minutes
42 to 45 min
ARCO North
Slope
180 minutes
42 minutes
The results indicate that the TT5000 will respond to the presence of a WTS oil leak within about
3-hours after the sensor cable has been in contact with the oil. In other words, for very small
leaks the TT5000 will always set off an alarm.
3.3 Vapor Sensing Leak Detection
The Leak Alarm System for Pollutants (LASP) consists of a vapor sensing tube installed along the
entire length of the pipeline. This tube is impervious to water but allows petroleum vapors to
pass and accumulate. A vacuum pump periodically draws the air from the tube and passes the
air stream through a sensor which detects the presence of petroleum vapors. Detectable
substances include a wide range of gases, hydrocarbon liquids and vapors, halogenated
hydrocarbons, landfill gases, water vapor, and many others. This vapor sensing system has the
potential to detect leaks of all sizes; however, very small leaks can take 30 hours or more to
detect.
The detection tube is manufactured in the form of a cable and is highly permeable to the
substances to be detected in the particular application. If a leak occurs, the substances to be
measured come into contact with the tube in the form of vapor, or gas dissolved in water. In
the event of a leak, some of the leaking substance diffuses into the tube. After a period of time

<<<PAGE 1317>>>

has passed, enough vapor will accumulate inside the tube so that when the air in the tube is
pulled past the detector there will be enough vapor to produce an accurate identification of the
substances surrounding the tube. The detector unit at the end of the sensor tube is equipped
with gas sensors so that an increase in gas concentration results in a pronounced "leakage
peak," which is proportional to the concentration of the vapor from the leaking medium at the
sensor tube surface.
A disadvantage of the LASP technology is that the time required to draw a vapor slug to the
detector will vary substantially because of diurnal and seasonal changes causing decreased leak
location accuracy.
Nitor Technologies, Inc. PROWLER LDS
Nitor Technologies, Inc. carries the PROWLER system and has upgraded the LASP system
technology. The published minimum detectable leak size is 0.04 GPH. However, this leak rate is
not referenced with a statement about the volatility and temperature of the leaking substance
was not specified in the literature.
Vapors emitted by the leaking crude oil diffuse into the PROWLER tubing and reach a steady
state or equilibrium concentration. The PROWLER pump is then activated to move the vapors
in the tubing to the detector, where measurements are made. Depending on soil porosity and
oil vapor pressure, several hours may be required for gases and vapors to migrate from the leak
site to the PROWLER tubing. To see a change from the baseline condition, a minimum of two
runs is needed, each taking as long as 15 minutes.
The PROWLER can locate the position of the leak to within 1% of the length of the pipeline. For
a twenty mile long section of pipeline, the accuracy would be less than 1100 feet. Using
secondary test points, the location of the leak can be determined to within 50 feet. More
precise leak location requires that a spike of tracer gas, such as Hydrogen or Ethane, be injected
at the front end near the inlet-air dryer unit.
For sizeable leaks, the density of the crude oil has little impact on response time. However, at
very low leak rates the crude oil and the vapors emitted by the crude oil require more time to
move through soil. Very small leaks of a heavy crude oil, as well as the vapors emitted by that
oil, will move through the soil much slower than the rates observed for lighter refined products
and their vapors to move through the soil.
The reliability of vapor sensing systems is lower than the liquid sensing cable systems. The
system is prone to set point drift and requires chromatographs that can lose sensitivity unless
properly calibrated and maintained.
A second sensor tube can be installed that continuously draws a vacuum. This option allows for
a more rapid detection of large leaks (greater than 0.5% to 1.00% of flow) while still enabling
the detection of small leaks by the periodic removal of the tubing air from the other tube.
Operating with two tubes in this manner is recommended by the manufacturer.
3.4 Fiber Optic Leak Detection
5

<<<PAGE 1318>>>

The fiber-optic sensing leak detection method involves the installation of a fiber-optic cable
along the entire length of the pipeline. The substances to be measured come into contact with
the cable when a leak occurs, changing the temperature of the cable. The distributed fiber-
optical temperature-sensing technique offers the possibility to measure temperature along the
pipeline. Scanning the entire length of the fiber, the temperature profile along the fiber is
determined, leading to leak detection.
Optical fiber sensor cables have been demonstrated to be useful for the measurement of a
wide variety of physical and chemical parameters because they have: 1) an immunity to
electromagnetic interference, 2) avoidance of ground loops, 3) capability of responding to a
wide variety of measured quantities, 4) avoidance of electric sparks, 5) resistance to harsh
environments, 6) remote operation, 7) capability of multiplexing, and 8) ease of integration into
large-scale fiber networking and communication systems. The reliability of the optical fiber
cables is questionable for long-term use because of their fragility and the possibility of false
positive signals caused by the presence of groundwater. For small crude oil leaks under low
pressure, the leaking substance will have adequate time to thermally equilibrate with the
material that surrounds the pipeline and the thermal sensor. Since the liquids and sensor will
be at the same temperature there will be little or no differential temperature for the fiber-optic
sensor to determine. This makes the fiber-optic LDS less desirable for crude oil applications. In
fact, no reference has been found where fiber optic cable has been used in the determination
and location of crude oil leaks from pipelines.
Two of the companies that supply fiber-optic based LDS's are Sensornet and Westminster, Intl.
The Sensornet Fiber-Optic Based LDS
The Sensornet fiber-optic cable system allows the inference of a leak by detecting the change in
temperature of the fiber-optic cable when it becomes exposed to the leaking fluid or a change
in temperature of the space around the cable caused by the nearby presence of the leaking
fluid. To date, the use of Sensornet's leak detection system has been for the detection of leaks
on and around highly pressurized natural gas liquid products such as ethane, ethylene,
propane, Y-grade products, and ammonia.
Westminster, International Fiber-Optic Based LDS
Westminster International appears to be in the private sector security business. They propose
that their fiber-optic cable systems be used to detect temperature changes caused by NGL's
leaking from pipelines and storage tanks.
3.5 Ultrasonic/Acoustical Leak Detection
Leak detection in pipelines using acoustic emission technology is based on the principle that an
leak occurs, the resulting low frequency acoustic signal is detected and analyzed by system
escaping liquid creates an acoustic signal as it passes through a perforation in the pipe. When a
processors. Deviations from the baseline acoustic profile would signal an alarm. The received
signal is stronger near the leak site, thus enabling leak location.

<<<PAGE 1319>>>

Asel-Tech
Asel-Tech has developed an acoustic/mass-balance/computational LDS that holds the
possibility of improving the computational technology. Response time can be as short as a
minute for leaks that are large enough to be acoustically detectable; however, the system's
ability to detect small leaks is greatly reduced in low vapor pressure liquids that cannot
generate sufficient acoustic energy to be detected over background noise.
3.6 Comparison
The following table summarizes the properties of the various direct leak detection systems:
Leak
Detection
Response Time
Detectable Leak Size
System
Tyco
The detection response time is not dependent
Leak rates lower than 0.01 GPH
TraceTek
upon the leak rate. It is dependent upon the soil
are detectable over a long
TT5000 Leak
Detection
porosity and the substance temperature. From
period of time. The cable is
the data supplied by Tyco for Magellan: the
responsive to both small and
Cable
response time for the WTS heavy crude is about
large leaks. Response is not
45 minutes at 104°F and 190 minutes at 68°F; and
for WTI light crude about 22 minutes at 68°F and
dependent on the leak rate.
The TT5000 is immune to the
93 minutes at 68°F. As a comparison, response
presence of water.
times for data done by Tyco for Arco on their
North Slope crude: 42 minutes at 104°F and 180
minutes at 68°F. Leak location is typically within
"a few meters" of the leak.
Nitor Vapor
Sensing
The detection response time is dependent upon the leak rate, the soil porosity, and
System -
the oil volatility. In the high speed mode the system can detect leaks of 600 to 1300
High Speed
GPH within a few hours. Large leaks, 12600 GPH or larger, can be detected in less
Mode
than 30 minutes. Additional response time factors include calibration frequency and
the type and sensitivity of the chromatograph. The maximum detectable leak has no
upper limit. The system is immune to the presence of water.
Nitor Vapor
As with the high speed mode, the detection response time is dependent upon the
Sensing
leak rate, the soil porosity, calibration frequency, and the oil volatility. In the high
System -
sensitivity mode detection time for the PROWLER is determined by the system's
High
setup parameters but is often given as 12 hours. While the published minimum
Sensitivity
detectible leak rate is about 0.04 GPH the response time for this small leak rate may
Mode
be as long or longer than 30 days. The system is immune to the presence of water.
Fiber Optic
The leak detection time for a fiber optic system
Fiber optic LDS is responsive to
Leak
depends upon the time required for the leak to
both small and large leaks.
Detection -
cause a temperature change in the cable.
Response time is dependent on
Sensornet
Response times are very fast for high volatility
the vapor pressure of the
and West-
fluids like ethane, but for small low pressure
leaking material and on the leak
minster
crude oil leaks there may not be a response.
rate.
7

<<<PAGE 1320>>>

Detection
Leak
Response Time
Detectable Leak Size
System
Hybrid
Asel-Tech has developed
Computa-
an acoustic/mass- Leaks less than about 0.1% of
tional LDS -
balance/computational LDS that holds the
possibility of improving the computational
total flow may not be detected.
Leaks that are greater than 0.5%
Asel-Tech
technology. Response time can be as short as a
minute for leaks that are large enough to be
to 1% of total flow can be
acoustically detectable.
detected.
4.0 Conclusions and Recommendations
Each of the four direct pipeline leak detection technologies investigated will detect crude oil. For
small leaks that are less than about 0.1% to 0.5% of the total pipeline flow rate, the TraceTek
T15000 is the most sensitive to crude oil. The Prowler vapor sensing system can also detect oil but
its response time will be slower than the TT5000 because the loss of sensitivity associated with low
vapor pressure crude oil. For leaks that are greater than 0.5% to 1% of the total pipeline flow rate,
the fiber-optic cable and acoustic detection systems provide the fastest response time, giving
indication of a leak in less than a minute after being contacted by the leaking substance. However,
the Sensornet and Westminster fiber-optic systems may be less sensitive to crude oil than the
other three leak detection systems because there will be little if any temperature change
associated with a leak from a low pressure crude oil pipeline. Acoustic leak detection systems are
also hampered by crude oil at low pressures because small leaks will not generate enough acoustic
energy to be detected over the background noise.
Because direct detection methods are best at detecting leaks that are less than 0.5% of the pipeline
flow rate, and while computational methods are best at detecting leaks that are greater than about
0.5% of the pipeline flow, it is recommended that Magellan maintain both types of systems. For
the direct sensing method, it is recommended to retain the existing Tyco Trace-Tech system. It has
the advantages of already being in place, it can pinpoint the leak accurately, and has been proven
to be reliable. The Nitor system is not recommended for detecting small leaks because the
response time due to the low volatility crude oil is too great to detect them in a timely manner.
The Sensornet, Westminster, and Asel-Tech systems are not recommended for use in detecting
small leaks from low pressure crude oil applications for the reasons noted in section 3.4, above.
8

<<<PAGE 1321>>>

5.0 Appendix
5.1 Corporate Contact Information
Tyco Thermal Controls LLC
2415 Bay Road
Redwood City, CA 94063-3032
Tel: (800) 545-6258
Fax: (650) 474-7215
TraceTek TT5000
http://www.tycothermal.com/
Asel-Tech
Sao Carlos, Brazil
Brazilian Corporation
USA (281) 619-5754
USA (281) 990-2574
http://asel-tech.com/
Nitor Technologies, Inc.
PROWLER
2750 Constitution Boulevard
Beaver Falls, Pennsylvania 15010
Telephone (724) 891-4115
Fax (724) 847-6444
http://www.nitortechnologies.com/
Sensornet
(British Company)
2002 Timberloch PL
Suite 200, The Woodlands
TX 77380, USA
Alan Sanderson
Ph: +1 281-296-5827
alan.sanderson@tendeka.com
http://www.sensornet.co.uk/
Westminster, International, Ltd
Banbury
Westminster House, Blacklocks Hill
Oxfordshire
OX17 2BS
United Kingdom
+44 (0) 1295 756300 Phone
+44 (0) 1295 756302 Fax
www.wi-ltd.com
Use website to make contact
9

## Provenance

- Official: Yes
- Source: <https://downloads.regulations.gov/PHMSA-2012-0175-0072/attachment_1.pdf>
- Source ID: `regulations-gov`
- SHA-256: `867a08a0d87e3c73603a84ed45bc77dd3d1aadfc0ebddecd97b366ea66253f94`
- Retrieved: 2026-08-20T02:22:46.679Z
- Exported: 2026-08-25T07:18:47.651Z
- Document slug: `regulations-gov-attachment-09000064811add8f`

### Source metadata

```json
{
  "materialSubtype": "regulations_gov_agency_attachment",
  "parentDocumentId": "regulations-gov-document-phmsa-2012-0175-0072",
  "regulationsGovDocumentId": "PHMSA-2012-0175-0072",
  "docketId": "PHMSA-2012-0175",
  "attachmentId": "09000064811add8f",
  "format": "pdf",
  "authorshipClass": "agency_authored",
  "rightsClass": "federal_work",
  "ingestionDecision": "ingest",
  "decisionBasis": [
    "organization:U.S. DOT/PHMSA",
    "title:U.S. DOT/PHMSA - Final Environmental Assessment of the Longhorn Pipeline Reversal - Volume 1 of 2: Chapters 1-6"
  ],
  "summaryEligibility": "eligible",
  "jurisdiction": "US"
}
```
