# U.S DOT/PHMSA - Regulatory Impact Analysis - October 2016

**Citation:** 0900006482310371  
**Type / status:** rulemaking / current  
**Agency:** Pipeline and Hazardous Materials Safety Administration  
**Effective:** Not stated  
**Published:** Not stated

Regulatory Impact Analysis Pipeline Safety: Expanding the Use of Excess Flow Valves in Gas Distribution Systems to Applications Other Than Single-Family Residences PHMSA-2011-0009 Office of Pipeline Safety Pipeline and Hazardous Materials Safety Administration (PHMSA) U.S. Department of Transportation October 2016 1 The rule expands EFV coverage beyond the SFR requirement included in the Integrity Management (IM) rule that went into effect in 2010 to cover all lines that are suitable for an EFV and operate with known loads that do not exceed 1,000 SCFH.6 The rule also requires that manual shut-off valves (curb valves) be installed...

## Document text

<<<PAGE 1>>>

Regulatory Impact Analysis
Pipeline Safety: Expanding the Use of Excess Flow Valves in Gas Distribution Systems to
Applications Other Than Single-Family Residences
PHMSA-2011-0009
Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration (PHMSA)
U.S. Department of Transportation
October 2016
1

<<<PAGE 2>>>

Executive Summary
The Pipeline and Hazardous Materials Safety Administration (PHMSA) is amending the Federal
Pipeline Safety Regulations to require operators of gas distribution pipelines to install excess
flow valves (EFV) on all new or replaced residential and commercial service lines where the
known load does not exceed 1,000 Standard Cubic Feet per Hour (SCFH) and to install manual
shutoff valves on all other new or replaced lines. The purpose of this regulation is to improve
safety by mitigating the damages from sudden pipeline ruptures and breaks by quickly shutting
off the released gas. The rule addresses Section 22 in the Pipeline Safety, Regulatory Certainty,
and Job Creation Act of 2011 (hereafter, the Act; P.L. 112-90)1 and National Transportation
Safety Board (NTSB) recommendation P-01-2.
2
Section 22 of the Act requires PHMSA to issue a final report on the evaluation of the NTSB
recommendation on EFVs in applications other than service lines serving one single family
residence and, if appropriate, require by regulation the use of excess flow valves, or equivalent
technology, where economically, technically, and operationally feasible on new or entirely
replaced distribution branch services, multifamily facilities, and small commercial facilities. On
December 4, 2009, PHMSA amended the pipeline safety regulations to require the use of EFVs
for new or replaced gas lines servicing Single Family Residences (SFRs).3 While this
requirement met the mandate of the Pipeline Inspection, Protection, Enforcement and Safety Act
(PIPES Act) enacted in 2006, distribution branched services, multi-family facilities, commercial
properties, and industrial service lines were still not required to use EFVs. These structures are
susceptible to the same risks as SFR service lines.
4
In an effort to study the possible benefits and costs of expanding EFVs beyond SFR applications,
PHMSA began development of the Interim Evaluation Report in early 2009.
5 Based on the
Report and the comments received on the Report (see NPRM for discussion), PHMSA found that
expansion of EFVs is technically, operationally, and economically feasible where loads do not
exceed 1,000 SCFH irrespective of the customer classification. PHMSA acknowledges that
EFVs may not be practical for large apartment buildings and industrial or commercial users due
to inherent design complexity and continuous supply demands. PHMSA concludes that curb
valves will provide the best possible option for improved safety at this time in those situations
where loads exceed 1,000 SCFH.
1 Under the Act, PHMSA is required to study and issue a final report on EFVs and, if appropriate, to issue
regulations requiring the use of EFVs or equivalent technology, where “economically, technically and operationally
feasible”, for new or entirely replaced distribution branch services, multi-family lines, and small commercial service
lines.
2 National Transportation Safety Board, Natural Gas Explosion and Fire in South Riding, Virginia, July 7, 1998,
Pipeline Accident Report NTSB/PAR-01/01 (Washington, D.C.: NTSB, 2001).
3 74 FR 63906
4 Please see the NPRM for Discussion of the 2010 Rule
5 The report is in the docket at
http://www.regulations.gov/#!docketDetail;dct=FR%252BPR%252BN%252BO%252BSR;rpp=10;po=0;D=PHMS
A-2011-0009
1

<<<PAGE 3>>>

The rule expands EFV coverage beyond the SFR requirement included in the Integrity
Management (IM) rule that went into effect in 2010 to cover all lines that are suitable for an EFV
and operate with known loads that do not exceed 1,000 SCFH.6 The rule also requires that
manual shut-off valves (curb valves) be installed on all new or replaced lines where known loads
exceed 1,000 SCFH and the line does not fit into the exceptions in § 192.383. The regulation
incorporates PHMSA’s findings and its analysis of comments from the study mandated by the
Section 22 of P.L. 112-90. The rule also requires operators to notify customers of their right to
request installation of EFVs on existing service lines (other than those being newly installed or
replaced), though such installations may be at the customer’s expense, as the appropriate State
regulatory agency will determine all issues related to the costs of installation. The requirements
pertain to all distribution operators, including operators of petroleum gas systems that serve
fewer than 100 customers from a single source and operators of master meters.
7
PHMSA collects information on gas distribution infrastructure (number of main miles, number
of services, number of EFVs installed) through its gas distribution annual reports (PHMSA Form
F 7100.1-1) and detailed information on incidents that met the incident definition in § 191.3
through the incident reports (PHMSA Form F 7100.1). None of the reports ask for information
by customer classification or the load sizes. However, this regulatory impact assessment uses
existing PHMSA data combined with the information available from published sources to
quantify the costs and benefits of the regulation by customer classification as defined in the
Section 22 of the Act.
PHMSA acknowledges that gas distribution systems are generally safe, averaging 0.11
reportable incidents per 100,000 services in 2010-2013.8 The rule aims to mitigate the
consequences of rare but potentially high-consequence incidents on new and fully replaced
services. Since the quantified benefit estimate depends on the existing incident database, the
benefit may be underestimated as it is not possible to predict a high-consequence incident that
would have been prevented by the safety measure extended through the regulation. PHMSA’s
6 Docket Number: PHMSA-RSPA-2004-19854, “Pipeline Safety: Integrity Management Program for Gas
Distribution Pipelines.”
7 operators of petroleum gas systems which serve fewer than 100 customers from a single source and operators of
master meters are exempt from submitting Annual reports in accordance with 191.11
http://www.gpo.gov/fdsys/pkg/CFR-2004-title49-vol3/xml/CFR-2004-title49-vol3-sec191-11.xml
And Master meter system is defined as means a pipeline system for distributing gas within, but not limited to, a
definable area, such as a mobile home park, housing project, or apartment complex, where the operator purchases
metered gas from an outside source for resale through a gas distribution pipeline system. The gas distribution
pipeline system supplies the ultimate consumer who either purchases the gas directly through a meter or by other
means, such as by rents; in 191.3 http://www.gpo.gov/fdsys/pkg/CFR-2004-title49-vol3/xml/CFR-2004-title49-
vol3-sec191-3.xml
8 Number of gas distribution incidents other than on mains divided by the number of services. Incident definitions
and reporting thresholds are found in 49 CFR 191.3 and 49 CFR 191.9. In general, operators must report incidents
that result in any deaths, injuries requiring hospitalization, property damage over $50,000, and/or loss of 3 million
cubic feet of gas.
2

<<<PAGE 4>>>

incident database is also limited to incidents that occurred on DOT-jurisdictional pipes and meet
certain criteria (§191.3) and does not include EFV-preventable incidents that did not meet the
criteria, nor EFV-preventable incidents that occurred downstream of the DOT-jurisdictional
piping (such as in customer piping). In comparison, the cost estimate assumes every single
service line has either an EFV or a curb valve as it is impossible to estimate where multiple
services are protected by a single EFV or a curb valve. This one-to-one correspondence of a
valve and a service line could overestimate the number of valves with respect to smaller
multifamily residences.
PHMSA estimated quantitative costs and benefits per valve on new and replaced service lines
over the next 50 years, annualized at 7% and 3% discount rates. Costs were estimated using
docket submissions and other information on valve installation costs, combined with a forecast
of future installation volumes by customer category that is based on PHMSA annual report data
and other sources. Benefits were estimated using a 50-year forecast of EFV-preventable incident
consequences, which was developed using historical incident data from the period 2004-2015.
Section 7 of this document has more detailed information on the data sources, assumptions, and
methods used in estimating benefits and costs. Some costs and benefits could not be estimated
due to data limitations.
The quantified benefits of the rule, including avoided injuries, fatalities, and property damage,
are estimated to be $5.5 million when annualized and discounted at 7%. There will be additional
non-quantifiable benefits as discussed below. Estimated costs, also discounted and annualized,
are $10.6 million. Using the alternative 3% discount rate, the estimated quantified annualized
benefits are $10.5 million per year, and the estimated total annualized costs are $12.0 million per
year.
PHMSA has no data with which to distinguish single versus branched services, which differ only
in their underground configuration. As a result, PHMSA estimated the total impacts for all SFR
services in the economic analysis of the Distribution Integrity Management Program (DIMP)
rule, even though that rule did not apply to branched services. Therefore, to avoid double
counting, PHMSA did not include the costs and benefits for branched SFRs in this EFV analysis.
The following table summarizes the quantified cost-benefit estimates at a 7% discount rate.
3

<<<PAGE 5>>>

Table ES-1. Summary of Estimated Benefits and Costs ($ Millions)1
Customer Category Annualized Benefit Annualized Cost
Branched Line Single Family See note See note
Multifamily Residence 1.0 6.2
Small Commercial 1.6 1.1
Industrial/Other curb valve 3.0 3.0
All classifications:
Notification & recordkeeping
Not estimated 0.3
Total 5.5 10.6
Note: Benefits and costs for branched SFR services accounted for in economic analysis of previous
rulemaking (Distribution Integrity Management Program).
1. 50-year present value converted to annual equivalent using 7% discount rate.
In addition to the quantified benefits, the rule is also expected to have benefits that we were
unable to quantify. They include the following:
• Equity: Provides a fair and equal level of safety to members of society who do not live in
single-family residences
• Additional incident costs avoided for which no PHMSA incident data are available:
Mitigates the consequences (death, injury, property damage) of additional incidents that
are not reflected in PHMSA records because customer piping or equipment is involved
• Additional incident costs which are not recorded in incident reports, including costs of
evacuations, some emergency response costs, and business downtime
• Environmental externalities associated with methane release (discussed in Appendix B)
• Peace of mind for operators and customers
• Protection against seismic events and intentional tampering
The one-time cost of installing an EFV ($15-$50, best estimate $309) during new service or
replaced service is fairly small. According to the data analyzed, the benefits of incident prevention
on a per-EFV basis are also small because incidents involving these classifications are rare.
However, these incident prevention benefits will exist for up to 50 years, as PHMSA assumes that
EFVs and curb valves have a lifespan of 50 years.
The values are calculated based on the assumption that without the regulation, EFVs and curb
valves would not be installed in service lines (other than lines serving SFRs under the existing
regulations). With voluntary installation, the benefits and costs would be reduced proportionally.
9 The average cost of an EFV, ranging from $15-$50 is $32.50. PHMSA used $30 in this analysis as it does not have
any basis for constructing a weighted average cost (i.e., how many EFVs at $15 and how many at $50 or in
between). The analysis also does not account for future technology/manufacturing progress which typically reduces
the unit cost.
4

<<<PAGE 6>>>

The rule is assumed to affect approximately 1,289 natural gas distribution operators and on
average 222,114 services per year.
Industry sources provided PHMSA with a range of cost estimates for EFVs and curb valves. The
analysis in this document is based primarily on our best estimates, which fall roughly in the
middle of that range. In Appendix A, we present the results of sensitivity testing using the lower
and higher cost figures received; quantified benefits fall in between the low and high cost
estimates.
The benefits of this rule are based on high-cost, low-probability incidents. The incident data
analyzed suggest that incidents occurring on many of these service classifications are infrequent.
However, PHMSA’s Incident Report database does not capture service classification and just over
a decade’s worth of incident data (2004 to 2015) could be analyzed for this rulemaking. It is thus
unlikely that the cost-benefit analysis captured all of the incidents that could have been prevented
or mitigated by an EFV. Further, several of the incidents noted by the NTSB when they made
previous recommendations for EFV installation took place decades ago, such that comparable
incident causation data are not available in the PHMSA database. PHMSA’s historical data and
NTSB investigations show that incidents do occur on these lines, and when they do, they are
typically high-consequence events. Key incidents identified by NTSB include the 1994 explosion
at a retirement home in Allentown, Pennsylvania, which resulted in a fatality, 66 injuries, and $5
million in property damage, and the 1998 explosion in St. Cloud, Minnesota, which demolished a
pizzeria, apartments, a law office, a bar, and took four lives.10
Because PHMSA aims to provide an extra level of protection in areas where there are high
concentrations of people, a prevented or mitigated incident could prevent several injuries or
fatalities (and sometimes extensive property damage), thereby producing significant quantifiable
benefits, along with benefits that could not be quantified, such as avoided evacuations. There is
also substantial value in the perception of the safety and integrity of the natural gas distribution
system. Currently, certain SFR residents are the only people who have the added protection of
EFVs by federal regulation: anyone who is residing in a multi-family residence (MFR), no matter
if it is by choice or circumstance, is not being provided an equal opportunity to avoid incidents
like the ones that occurred at Allentown, Pennsylvania, and St. Cloud, Minnesota.
1 Introduction
10 National Transportation Safety Board, UGI Utilities, Inc., Natural Gas Distribution Pipeline Explosion and Fire,
Allentown, Pennsylvania, June 9, 1994, Pipeline Accident Report NTSB/PAR-96/01 (Washington, D.C.: NTSB,
1996) and National Transportation Safety Board, Natural Gas Pipeline Rupture and Subsequent Explosion, St.
Cloud, Minnesota, December 11, 1998, Pipeline Accident Report NTSB/PAR-00/01 (Washington, D.C.: NTSB,
2000)
5

<<<PAGE 7>>>

The Pipeline and Hazardous Materials Safety Administration (PHMSA) is amending the
requirements of §192.383 (b) by requiring the installation of excess flow valves (EFV) beyond
single-family residence (SFR) service lines to cover new or replaced branched service lines,
multi-family residences, and small commercial service lines serving a single customer with a
known load that does not exceed 1,000 SCFH. Additionally, PHMSA is adding §192.385 to
require the installation of manual shutoff valves (curb valves) on all new or replaced lines where
the installed meter capacity exceeds 1,000 SCFH.
The National Transportation Safety Board (NTSB) has identified, between 1970 and 2011, 11
significant incidents that could have been mitigated by the presence of an EFV and has issued
more than 20 recommendations concerning the installation of EFVs for both residential and
commercial applications. The NTSB’s recommendations culminated in the most recent Safety
Recommendation P-01-2, which states that PHMSA “require that excess flow valves be installed
in all new and renewed gas service lines, regardless of a customer’s classification, when the
operating conditions are compatible with readily available valves.”
PHMSA published an ANPRM (76 FR 72666, November 25, 2011) that included an Interim
Evaluation report on expanding the EFV requirement beyond single-family residences. The
Interim Evaluation, which had been posted online and received extensive feedback from
stakeholders, recommended that an economic analysis be performed that would take into account
alternatives, particularly curb valves; differentiate among the various classifications of
customers; and reflect the increase in EFVs already installed. The Interim Evaluation noted that a
survey would have to be performed in order to identify incidents and to find operators with
experience and data on operating EFVs beyond SFRs.
While the ANPRM was open for comments, President Obama signed the Pipeline Safety,
Regulatory Certainty, and Job Creation Act of 2011 into law. Section 22 of that law required
PHMSA to issue a final report on the evaluation of the NTSB’s recommendation on EFVs in
applications other than service lines serving one single family residence, and “if appropriate,
require by regulation the use of excess flow valves, or equivalent technology, where
economically, technically, and operationally feasible on new or entirely replaced distribution
branch services, multifamily facilities, and small commercial facilities.”
This rule addresses Section 22 of the Pipeline Safety, Regulatory Certainty, and Job Creation Act
of 2011 and NTSB Recommendation P-01-2. Section 22 of the Act requires PHMSA to conduct
a study on the expanded use of EFVs in applications other than SFR service lines. Based on the
study11 and the comments received on the study (see NPRM for discussion), PHMSA has
11 The report is in the docket at
http://www.regulations.gov/#!docketDetail;dct=FR%252BPR%252BN%252BO%252BSR;rpp=10;po=0;D=PHMS
A-2011-0009
6

<<<PAGE 8>>>

determined that expanding EFV installation will provide protection for the vast majority of gas
customers, irrespective of customer classification where known load size is less than or equals
1,000 SCFH, and is technically, operationally, and economically feasible. PHMSA
acknowledges that EFVs may not be practical for large apartment buildings and industrial or
commercial users due to inherent design complexity and continuous supply demands. PHMSA
concludes that curb valves will provide the best possible option for improved safety at this time
in situations where loads exceed 1,000 SCFH. PHMSA notes that this rule will satisfy the NTSB
recommendation and promote better public safety by ensuring all service lines, regardless of the
customer classification, have adequate protection through the installation of either an EFV or a
curb valve.
The requirements for distribution pipeline operators are described below.
1.1 Excess Flow Valves
The rule revises 49 CFR part 192 §383 by adding four new categories of service for which EFV
installation will be required on all new or replaced lines. The four new categories that will be
added to the existing requirement for SFRs served by a single service line are:
- Branched service lines to a SFR installed concurrently with the primary SFR service line
(a single EFV may be installed to protect both lines)
- Branched service lines to an SFR installed off a previously installed SFR service line that
does not contain an EFV
- Multi-family residences with known customer loads at time of service installation, based
on installed meter capacity, not exceeding 1,000 SCFH per service
- A single, small commercial customer, served by a single service line, with known
customer load at time of service installation, based on installed meter capacity, not
exceeding 1,000 SCFH per service.
PHMSA notes that the first two categories of branched service lines to SFRs cover the majority
of branched services. The benefits and costs of installing EFVs on service lines to SFRs were
analyzed as part of the DIMP rulemaking in 2009. As there is no data available for which
installed lines are single-service or branched service12
, and because incident data doesn’t
distinguish the two types of lines, there was no practical way to exclude branched lines from the
overall SFR calculations for DIMP. Indeed, the only difference between whether a service line is
single-service or branched is in the underground configuration, which is determined by the
installing operator on a case-by-case basis. The 2009 DIMP analysis found that installing EFVs
12 PHMSA’s Natural Gas Distribution Annual reports (PHMSA F7100.1-1) collect information on the number of
services per operator in each state as an aggregate number without service type classification.
7

<<<PAGE 9>>>

on lines serving SFRs would yield annual benefits in the range of $7 million to $17 million
against costs of $8 million. The safety benefits were calculated using the then-current $5.8
million value per statistical life and would thus be substantially higher using today’s $9.4 million
value. While PHMSA is not aware of a practical way to break down the benefits and costs of
EFV installation on branched lines serving SFRs specifically, installing EFVs on branched lines
is expected to have positive net benefits in light of the overall SFR results. Branched SFR is
excluded from the remainder of this analysis due to data limitations and to avoid duplication of
the costs and benefits incorporated in the DIMP analysis.
The present analysis categorizes the estimated new and replaced services by multifamily,
commercial, and industrial classifications and accounts for the cost of either an EFV or a curb
valve for every service. (Costs may be slightly overestimated as one can potentially have an EFV
or a curb valve servicing multiple customers/services).
The rule continues to include exceptions for excess flow valves for cases where installation
would not be feasible. These exceptions, now in part (c) of section 383, are:
- When the service line does not operate at a pressure of 10 psig or greater throughout the
year
- When the operator has prior experience with contaminants in the gas stream that could
interfere with the EFV’s operation or cause loss of service to the customer
- When an EFV could interfere with necessary operations or maintenance activities, such
as blowing liquids from the line
- When an EFV meeting performance standards in 192.381 is not commercially available
to the operator.
The exceptions reduce the potential cost of the regulation by acknowledging that there are
reasonable conditions that render EFV installation not operationally and technically feasible. As
there are no data available to estimate the proportion of lines that are exempt, the analysis will
assume that all lines with known loads under 1,000 SCFH have operating conditions suitable for
an EFV, thereby overestimating the cost.
The revision also adds a part (d) to section 383 that allows optional installation of EFVs if
requested by a customer. The analysis does not estimate the number of customer requests that
may occur in any given year or the resulting transfers.
Based on the findings and the comments on the Interim Report, PHMSA has determined that
expanding the installation of EFVs will provide protection for the vast majority of gas
distribution customers, irrespective of the customer classification, where loads does not exceed
1,000 SCFH. PHMSA has also deemed that EFVs may not be practical for large apartment
buildings and industrial or commercial users due to inherent design complexity and continuous
supply demands. For those situations (loads exceeding 1,000 SFCH), PHMSA concludes that
curb valves will provide the best possible option for improved safety at this time.
8

<<<PAGE 10>>>

1.2 Curb Valves
The rule adds §385 to Part 192. The addition requires operators to install a manual service line
shut-off valve (curb valve) on any new or replaced service line on which an EFV is not installed
in accordance with section 192.383(b).
The required use of curb valves for large commercial (greater than 1,000 SFCH) goes beyond the
Section 22 language of the Pipeline Safety, Job Creation, and Regulatory Certainty Act of 2011;
however, it is based on ANPRM comments received from industry, trade associations and other
stakeholders. PHMSA and industry in general determined that EFVs are not suitable for larger
commercial facilities over 1,000 SFCH. As mentioned above, curb valves are the best
alternative to an EFV and provide an effective added level of safety for these facilities.
PHMSA’s authority for regulating natural gas pipelines was first established by the Natural Gas
Pipeline Safety Act of 1968, Pub. L. No. 90-481, and has since been enlarged by additional
legislation. The Pipeline Safety Laws specifically delegate authority to DOT to develop,
prescribe, and enforce minimum Federal safety standards for the transportation of natural
gas. PHMSA has used this statutory authority to promulgate comprehensive minimum safety
standards. While the 2011 Act specifically directed PHMSA to require the installation of EFVs
on new and replaced branched lines serving SFRs, multi-family and small commercial facilities,
DOT’s underlying prior statutory authority under 49 USC § 60104 provides PHMSA with the
authority to require the installation of curb valves for large commercial facilities.
The remainder of this report analyzes the benefits and costs of the regulatory changes as required
by Section 1 of Executive Order 12866 (as amended by E.O.s 13258 (2002), 13422 (2007),
and 13497 (2009)) and Section 1 of Executive Order 13563 (2011).
13
2 Background
EFVs are designed to automatically stop the flow of a gas when the flow increases suddenly and
significantly, such as during a pipeline separation. They are used in the United States and around
the world to mitigate damage resulting from a sudden pipeline rupture caused by a natural
disaster, excavation damage, or other third-party damage. However, because they shut
automatically based on changes in flow, they can also shut when customers suddenly increase
13 The text of E.O. 12866 can be found here: http://www.archives.gov/federal-register/executive-
orders/pdf/12866.pdf and E.O. 13563 here:
http://www.whitehouse.gov/sites/default/files/omb/inforeg/eo12866/eo13563_01182011.pdf
9

<<<PAGE 11>>>

their gas load, causing an inconvenience for the customer and the company. Manual shutoff
valves, known as curb valves, are an alternative that avoids a false closure but requires a trained
responder to be on site to shut the valve, increasing the amount of gas that is released after an
incident.
PHMSA has moved towards greater installation rates of EFVs over the years while continuing to
recognize that EFV closures pose hazards of their own.
14 In 1996, PHMSA added 49 CFR
192.381 to the Pipeline Safety Regulations, which contains performance standards for EFVs. In
1998, responding to statutory mandates in Section 104 of the Pipeline Safety Act of 1992 (Pub.
L. 102-508), PHMSA added a requirement15 that required operators to notify customers in
writing about EFV availability; the safety benefits derived from installation; and any installation,
maintenance, and replacement costs16
.
In 2006, the Pipeline Integrity, Protection, Enforcement, and Safety (PIPES) Act of 2006
required that EFVs be installed on all new or replaced service lines serving one SFR where:
• The service line continuously operates at a pressure at or above 10 psig
• The service line is not connected to a gas stream with a prior history of contaminants
• The installation is not likely to cause a loss of service to the residence or to interfere with
necessary operations and maintenance
• EFVs are commercially available.
PHMSA issued Advisory Bulletin 08-04 encouraging operators to begin installing EFVs in
accordance with the Act. The final rule on natural gas distribution IM programs was officially
published December 4, 2009, and applied to lines installed or replaced after February 2, 2010 (74
FR 63906). However, the NTSB issued a response to PHMSA’s status update urging PHMSA to
make the rule applicable to all customers “regardless of their classification.”17
PHMSA then published an ANPRM that included an Interim Evaluation report on expanding the
EFV requirement beyond single-family residences (76 FR 72666, November 25, 2011). The
Interim Evaluation recommended that an economic analysis be performed that would take into
account alternatives, particularly curb valves; differentiate among the various classifications of
customers; and reflect the increase in EFVs already installed. The Interim Evaluation noted that a
14See FR Doc No: 94-18771, “Excess Flow Valve Installation on Service Lines” August 2, 1994 for discussion of
EFV closure costs and PHMSA’s 1996 cost-benefit analysis summarized in 61 FR 31449.
15 http://www.gpo.gov/fdsys/pkg/CFR-2002-title49-vol3/pdf/CFR-2002-title49-vol3-sec192-383.pdf
16 Distribution Integrity Management Rule (http://primis.phmsa.dot.gov/dimp/docs/DIMPFINALRULE.PDF)
removed this requirement in 2009.
17 NTSB response dated 9/22/2009. Correspondence available on the NTSB website here:
http://www.ntsb.gov/safetyrecs/private/history.aspx?rec=P-01-002&addressee=PHMSA
10

<<<PAGE 12>>>

survey would have to be performed in order to identify incidents and to find operators with
experience and data on operating EFVs beyond SFR applications.
Nineteen entities submitted comments to the ANPRM docket (PHMSA-2011-0009). Eleven
comments were from utility companies or associations, two were from manufacturers, one was
from a State regulator, one was from the NTSB, one was from a city government, and the
remainders were from the public.
In general, utilities supported an expansion of EFV installation, with limits on feasibility. The
American Gas Association, American Public Gas Association, Northeast Gas Association,
Southwest Gas Corporation, Nicor Gas Company, National Grid, Avista, and Laclede Gas all
supported a limited expansion. Mid-American Gas and the City of Ellensburg, WA, supported an
expansion as long as curb valves and EFVs were viewed as perfect substitutes for one another
and companies could select which valve best suited operational conditions. The Texas Pipeline
Association focused specifically on service lines extending from transmission and gathering
lines. Three companies (Southwest, Mid-American, and Nicor) cited maintenance issues with
ensuring access to curb valves, as well as delays in shutting off the gas in the event of a break.
Reasons cited for delays included the valve’s accessibility during an incident and the potential,
because curb valve boxes are above-ground, that curb valves could be buried or damaged by
third-parties, thereby making the valve inaccessible or inoperable. The State regulator noted that
upstream above-ground valves are already present on many large commercial and industrial
properties. The comments also noted that the categories provided in the Interim Evaluation were
not specific enough. The American Gas Association (AGA) and others suggested that the
threshold between small and large should be a load size of 1,000 SCFH (PHMSA 2011-0009-
0024).
Following the ANPRM, PHMSA developed a draft survey document aimed at identifying
incidents and operators with experience operating EFVs beyond SFRs. As a key component of
the survey, the research team developed customer categories based on the Interim Evaluation,
ANPRM comments, and discussions with operators. Key variables identified to separate
customers included load size, customer type, and load variability.18 The analysis eventually
resulted in seven categories: single family residential, small multi-family residential, large multi-
family residential, small space and water heat non-residential customers, large space and water
heat non-residential customers, small other non-residential customers, and large other non-
residential customers. The distinction between small and large was the 1,000 SCFH load size
mentioned in comments to the ANPRM.
Using the customer categories, the research team developed the survey recommended by the
Interim Evaluation report, aimed at gathering data on EFV and curb valve costs and benefits. The
18 Demand for heat and water is less variable that demand for other uses such as cooking or clothes drying, so space
and water heat customers were separated from other customers with more complex needs.
11

<<<PAGE 13>>>

survey was to be sent to all operators because industry comments suggested that experience with
EFV installation beyond SFRs was rare, so a sample may have excluded operators with relevant
data. The goal was to have a better understanding of the costs of EFVs on installations beyond
SFRs from operators who already deployed the technology and on the costs and effectiveness of
curb valves.
Nine companies were asked to pilot the census, and a copy was published in the Federal Register
as part of a notice of information collection on May 15, 2012 (77 FR 28669). The purpose of the
pilot was to ensure that operators were able to provide the requested data, that the questions were
clearly worded, and that the response categories cover the full range of possible responses.
Additionally, because the survey was developed using an online survey tool, Survey Gizmo, the
pilot also served as a test of the online functionality. The nine companies selected varied by size
(defined by number of service lines) and region of the country (East, Midwest, South, and West)
in order to ensure that there was variation along key factors that might impact responses. All
respondents had installed EFVs in the previous calendar year according to PHMSA’s annual
report data.
The pilot was conducted from May 24 to July 17, 2012. PHMSA sent an introductory letter to all
nine participants explaining the purpose and importance of the data collection. The Volpe Center
followed up with an email that described the study purpose and included the survey link. To
boost response, Volpe contacted participants by email and phone to encourage participation and
to answer any questions operators might have about the survey. The Volpe Center also
conducted telephone debriefs with each of the nine pilot respondents to obtain more detailed
feedback on their experience completing the survey.
Of the nine pilot respondents, only four attempted to complete the survey, but in most cases they
entered “0” as their response because the data was not available. Only one operator, whose
company comprised a small system of approximately 3,000 service lines that installed EFVs only
on single-family residences, provided responses by the different customer classifications. It took
the respondent 3 hours to sort their service lines into the requested categories. In the debrief
calls, the other respondents (five) indicated they could not provide the data being requested.
Both the census pilot and the docket comments on the notice of information collection (PHMSA
2012-0086) quickly revealed that company databases are not currently set up to provide the
necessary data. Load and customer type data are stored separately from data on EFVs and from
data on incidents, and grouping customers into the census categories would, according to these
pilot respondents, be a time-intensive and costly undertaking. Because only one respondent was
able to complete the survey, no data from the survey is included in this RIA.
As a result of the survey experience and feedback from pilot participants and industry comments
on the docket, including AGA’s docket comment (PHMSA 2012-0086-0003) stating a
preference for putting forth a consensus regulation rather than continuing the data collection
12

<<<PAGE 14>>>

efforts, PHMSA moved to continue the rulemaking process authorized by Section 22 of the
Pipeline Safety, Job Creation, and Regulatory Certainty Act of 2011 without further information
collection in order to avoid undue industry burden.
3 Regulatory Analysis
Executive Orders 12866 and 13563 direct all Federal agencies to consider the costs and benefits
of “significant regulatory actions.” Federal agencies are directed to develop a formal Regulatory
Impact Analysis consistent with Office of Management and Budget (OMB) Circular A-4 for all
“economically significant” rules, or those rules estimated to have an impact of $100 million in
1995 dollars or more in any one year. The Order also requires a determination as to whether a
rule could adversely affect the economy in terms of productivity and employment, the
environment, public health, safety, or State, local, or tribal governments. This requirement
applies to rulemakings that rescind or modify existing rules as well as to those that establish new
requirements. The goal of the analysis is to provide decision makers with a clear indication of the
most efficient alternative—that is, the alternative that generates the largest net benefits to society
ignoring distributional effects.
This rule falls below the $100 million a year in annual impact threshold. This regulatory
analysis:
- Identifies the target problem, including a statement of the need for the action
- Identifies available alternative approaches
- Defines the baseline
- Defines the scope and parameters of the analysis
- Defines and evaluates the costs and benefits of the action and the main alternatives
identified by the analysis
- Compares the costs and benefits
- Interprets the cost and benefit results.
4 Identification of the Problem and the Need for the Rule
Executive Order 12866 states that "Federal agencies should promulgate only such regulations as
are required by law, are necessary to interpret the law, or are made necessary by compelling
need, such as material failures of private markets to protect or improve the health and safety of
the public, the environment, or the well-being of the American people ..." Executive Order
13563 states that, to the extent permitted by law, agencies must (1) propose or adopt a regulation
only upon a reasoned determination that its benefits justify its costs (recognizing that some
benefits and costs are difficult to quantify); (2) tailor its regulations to impose the least burden on
13

<<<PAGE 15>>>

society, consistent with obtaining regulatory objectives, taking into account, among other things,
and to the extent practicable, the costs of cumulative regulations; (3) select, in choosing among
alternative regulatory approaches, those approaches that maximize net benefits (including
potential economic, environmental, public health and safety, and other advantages; distributive
impacts; and equity); (4) to the extent feasible, specify performance objectives, rather than
specifying the behavior or manner of compliance that regulated entities must adopt; and (5)
identify and assess available alternatives to direct regulation, including providing economic
incentives to encourage the desired behavior, such as user fees or marketable permits, or
providing information upon which choices can be made by the public.
PHMSA’s mission is to ensure the safety of the natural gas system. Recognizing the safety
benefits of EFV installation in natural gas distribution systems, Section 22 of the Pipeline Safety,
Job Creation, and Regulatory Certainty Act of 2011 directed PHMSA to, if appropriate, require
the installation of EFVs or equivalent technology, where economically, technically, and
operationally feasible on new or entirely replaced distribution branch services, multifamily
facilities, and small commercial facilities. In addition, PHMSA is responding to NTSB
recommendation P-01-2, which recommends that PHMSA “require that excess flow valves be
installed in all new and renewed gas service lines, regardless of a customer’s classification, when
the operating conditions are compatible with readily available valves.”
Overall, based on findings from the Interim Evaluation19and the comments received on the study
(see NPRM for discussion), PHMSA has determined that expanding the installation of EFVs via
this rule is appropriate.
The rule requires operators of gas distribution pipelines to install EFVs on all new or replaced
residential and commercial service lines where the known load does not exceed 1,000 SCFH and
install manual shutoff valves on all other new or replaced lines.
There is a market failure that the EFV requirements will help address. Natural gas distribution
operators do not always bear the full costs of an incident or explosion stemming from a service
line puncture or rupture. Even in cases where operators provide compensation for losses that can
be monetized, those monetary penalties do not necessarily capture the full impact on affected
parties, especially when a death or injury occurs. As a result, there is a negative externality
present in which the company may not take the full cost of a possible incident into account in its
decision-making. The negative externality can alter the company’s decision about safety
precautions, leading to a need for government to set minimum levels of safety precautions, such
as the installation of EFVs. In this particular case, some companies are already installing EFVs
beyond single-family residences, so the rule will bring all companies up to this safety standard
19 The report is in the docket at http://www.regulations.gov, item PHMSA-2011-0009-0002
14

<<<PAGE 16>>>

where economically and technically feasible and require manual shut-off valves on all other new
or replaced lines.
5 Identification of Available Alternative Approaches
PHMSA considered several alternatives to assure the necessary protection from incidents caused
by the puncture or rupture of service lines, with the intention of selecting the alternative that was
likely to result in the highest net benefits. PHMSA considered the following approaches:
- Baseline or “no action” scenario
- Customer notification requirement only
- Implement NTSB’s full recommendation and require that EFVs be installed in all new
and renewed gas service lines, regardless of a customer's classification, when the
operating conditions are compatible with readily available valves
- Develop a hybrid approach by requiring EFVs where loads are smaller and more stable,
making EFVs more feasible and requiring that any line not protected by an EFV be
protected by a manual shut-off valve.
After considering all of the alternatives, PHMSA selected the hybrid option.
5.1 No Action
The No Action alternative is the baseline against which PHMSA compared all other alternatives.
Regulatory analyses typically consider an alternative in which the agency would not take any
action because it would maintain the status quo. The status quo scenario is that some companies
would begin or continue voluntary installation of EFVs beyond SFRs based on their perceived
business case for doing so. In its comments to the information collection docket, the AGA noted
that its board of directors had voted to begin installing EFVs beyond single-family residences
starting June 2013 (PHMSA 2012-0086-003). However, voluntary installation does not lead to
uniformity. Uniformity ensures consistency and enforceable oversight, ensuring the safety of
natural gas service lines throughout the United States.
By not taking action, the Agency would be unresponsive to the congressional mandate in Section
22 of the Pipeline Safety, Job Creation, and Regulatory Certainty Act and to NTSB
recommendation P-01-2. Voluntary installation would not ensure uniformity and would leave
many lines without shutoff valves, especially the lines that would be covered by manual shutoff
valves under the rule.
5.2 Notification requirement only
15

<<<PAGE 17>>>

Under this alternative, PHMSA would not extend mandatory installation of EFVs beyond the
current rule covering single-family residences, but would issue new regulations requiring that
gas distribution operators inform customers of the option to have an EFV or curb valve installed,
with additional notifications when a service was replaced or newly installed. Costs, schedule,
and other details of the EFV installation would be determined by the appropriate State regulatory
agency. PHMSA rejected this alternative as unlikely to be effective in achieving widespread
EFV coverage and the associated safety benefits, due to low public awareness of EFVs and
relatively low rates of customer-initiated installations in places where this has been an option.20
Although the option for customer-initiated EFV installation is a useful adjunct to mandatory
installation on new and replaced services, PHSMA determined it would be adequate to address
the relevant safety concerns or NTSB recommendations.
5.3 Full implementation of NTSB’s recommendation to require that excess EFVs be
installed in all new and renewed gas service lines, regardless of a customer's
classification, when the operating conditions are compatible with readily available
valves
This alternative was determined by PHMSA to be infeasible. While EFVs provide safety benefits
by snapping shut automatically and rapidly due to changes in gas pressure, they have also been
known to shut in response to sudden increases in gas use such as the turning on of an industrial
oven. This is known as a “false closure.” False closures can cause considerable damage. One
docket comment noted that false closures can lead to harmful chemical releases if the gas used to
burn chemical waste in factories is suddenly shut off.21 False closures would also have
consequences in medical establishments, where a sudden loss of heat or hot water could cause
serious harm. While EFVs can be sized to prevent most false closures, there is still a chance for
false closures to occur, particularly for customers whose gas loads are more variable. Thus, the
potential for false closures render a universal EFV requirement impractical in many settings,
such as those with high and variable gas loads (over 1000 SCFH), low-pressure lines, lines with
contaminants, or where EFVs would interfere with maintenance or lead to loss of service.
20 K. Costello and P. Laurent, National Regulatory Research Institute (NRRI), Survey On Excess
Flow Valves: Installations, Cost, Operating Performance, And Gas Operator Policy, March 2007.
21 PHMSA-2011-0009-0015, Comment by Southwest Gas, submitted 03/21/2012
16

<<<PAGE 18>>>

5.4 Development of a hybrid approach requiring EFVs where loads are smaller and more
stable and requiring that any line not protected by an EFV be protected by a manual
shut-off valve.
This alternative was determined by PHMSA as the preferred regulatory option and is compared
in the document with the baseline “no action” alternative. While the quantified benefits
associated with this alternative do not always outweigh the costs, the potential unquantifiable
benefits and relatively low cost make this alternative preferable, especially from a safety point of
view, as an EFV can prevent or mitigate the consequences of rare, but severe and costly,
incidents.
This alternative requires that operators place EFVs or curb valves where they are most
operationally effective and where they most maximize the overall safety benefit. Excess flow
valves, which provide greater safety benefits than manual shut-off valves, will be required on
smaller, more stable loads that are similar to loads on single-family residences. The properties
affected by the rule have few negative operational impacts and will be protected with automatic
shut-off capabilities in the event of a pipeline rupture, saving life and property. Other lines,
including those serving public establishments and large commercial or industrial customers, will
obtain safety benefits from manual shut-off valves without the potential costs of a false closure.
The selected alternative mandates installation only on new and replaced services. PHMSA did
not consider it cost-effective to require the retrofitting of all existing services. For retrofits, the
benefits per valve would be essentially the same as calculated below (a range of $4 to $44 in
total present value at 7%, depending on customer type) but installation costs would be
significantly higher due to the need for excavation and additional labor costs. These costs will
vary by location and configuration, and could not be estimated with precision; however, PHMSA
agrees with commenters who described retrofit costs as significantly higher than for new
services.22
6 Industry Information
The gas distribution industry is complex, composed of some very small operators, including
master meter operators that serve only a few customers; medium-sized operators, many of which
are municipal agencies, serving between 1,000 and 50,000 customers; and some larger
companies operating sizable systems often in multiple States. The industry is also fluid, as
22 For example, AGA noted in their comments (PHMSA-2011-0009-0038) that the costs are “vastly greater.”
17

<<<PAGE 19>>>

companies may merge or municipalities sometimes decide to jointly provide services or offer a
contract to a third party to operate a system. The table below breaks down operator size by type,
based on operator data from the 2015 PHMSA annual report.
Under
1,000
service
lines
1,001-
50,000
lines
Over
50,000
lines
Private Sector
37% 32% 31%
Entity
Public Sector
Entity
49% 49% 2%
Other Entity 43% 52% 4%
Overall 45% 44% 11%
The regulatory changes will apply to all operators of gas distribution systems, including master
meter and LPG systems regulated under 49 CFR Part 192. The 2015 annual report database
contains 1,446 reports from gas distribution operators, with an estimated 1,329 unique operators
(i.e., those with a unique OPID) with 67.6 million service lines. Master meters and small LPG
systems comprise another group of 6,237 operators, with an unknown number of lines. Previous
benefit-cost analyses have assumed 100 lines per operator in this category, which leads to
roughly an additional 620,000 service lines impacted.23
7 Definition and Evaluation of the Benefits and Costs
7.1 Data Sources and Limitations
7.1.1 Data
23 The rest of this analysis is limited to those operators that submitted an annual report and does not cover master
meter and small LPGs. According to PHMSA’s Operator Management System, there are 5,324 master meter and
913 small LPG operators, for a total of 6,237 additional operators as of May 2016. Some operators that are affected
by this rule may be omitted from the analysis due to this lack of data, but no comments were received in either the
ANPRM docket or the information collection docket critiquing this omission, or even mentioning these categories of
operators at all.
18

<<<PAGE 20>>>

Cost data for the price of valves was taken from past benefit-cost analyses, docket comments,
and discussions with industry. The table below shows the cost data and the source.
Estimate Source
$20-30 per EFV Industry sources as summarized in DIMP
Rulemaking analysis24, variation based on
company size
$50 per EFV Mid-American Energy Docket Submission
$15-50 per EFV, $10-$100 per curb
Ranges provided by a representative from a gas
valve
operator in the Pacific Northwest with installation
experience, by telephone 8/15/2012
Quantifiable benefits were estimated using data from the PHMSA Incident Reports database as
summarized in the Interim Evaluation and updated in the Final Evaluation, plus review of
incidents that occurred more recently (2012 to 2015).
25 For both EFVs and curb valves, incidents
were filtered based on incident cause codes and other variables to isolate those incidents that
would have actually been prevented by the selected valve under the rule, and to exclude system
locations where valves would not have been required.
26
To determine the incident rate, rough estimates of the size of each customer category for the
years in the incident database were developed based on Table 8-1 of AGA’s GasFacts, “Gas
Industry Sales Customers by Class of Service.” While the ratio of customer to service line is not
exactly one, the ratio is close enough to approximate the size of the population. Table 8-1 only
goes through 2010. Because the share of residential lines has been steadily rising relative to
commercial and especially industrial lines over time, the 2010 shares were extended through
2012 rather than using the 2004-2010 average. The shares in 2010 were 92.7% residential, 7.1%
commercial, and 0.2% industrial.
Benefits and costs are all presented in real (i.e., inflation-adjusted) terms. Future costs and
benefits accrued over the 50-year lifespan of the valves are discounted to the present value using
24 Regulatory Impact Analysis, Pipeline Safety: Integrity Management Program for Gas Distribution Pipelines,
PHMSA-RSPA-2004-19854
25 PHMSA, “Final Report: NTSB Recommendation P-01-02,” November 2014, available on docket as document
PHMSA-2011-0009-0027.
26 Incidents were filtered using the following logic: (1) Eliminate "fire first" incidents (FF=YES), (2) Include only
incidents occurring on service or meter set (exclude main, other) using SYSTEM_PART_INVOLVED, (3) Exclude
where cause is corrosion (internal, external); fire/explosion as primary; body of pipe; component; joint; malfunction
of control/relief equip; threads stripped/broken pipe coupling; incorrect operation; miscellaneous and unknown,
using the CAUSE and CAUSE_DETAILS fields; (4) Exclude where MOP is less than 10 psig
19

<<<PAGE 21>>>

a real 7% discount rate. A 3% rate is also included to show how sensitive the estimates are to the
selection of a discount rate. At the end of the 50-year analysis period, valves installed in years 2
through 50 will still be providing benefits into the future. The remaining protection at the end of
the 50-year time frame is summed to reflect the remaining benefits of those valves.
For simplicity, this analysis presents the benefits and the costs of a single valve first and then
expands the analysis nationwide. Valves are not assumed to have network effects; in other
words, each EFV operates independently, and the costs and benefits of EFV installation simply
scale linearly.
This regulatory evaluation uses Departmental guidelines on valuing reduction of fatalities and
injuries by regulations as published by the Office of the Secretary of Transportation, U.S.
Department of Transportation.27 Because nationwide estimates include valves installed over a
50-year period, and USDOT now recommends that the monetary value of an injury or fatality
increase over time with the wage rate, benefits rise slightly over time as the equivalent injury
values rise. Benefits and costs are determined separately for multi-family EFVs, commercial
EFVs, and the industrial/other curb valves as each category has different incident rates and
severities, as well as different valve costs.
7.1.2 Assumptions and limitations
In order to perform the analysis with the limited data available, a number of assumptions were
made. First, for the benefits that are quantified here, the research team assumed that incident
rates and costs developed from past data would not change during the 50-year analysis period.
This assumption may not hold, since other safety improvements, such as 811 “Call Before You
Dig,
” could reduce the number of EFV-preventable incidents in the future. However, 811 is a
longstanding initiative, and its effects should largely already be reflected in the relatively recent
(2004-2015) incident data used in this analysis. Additionally, there is the chance that incident
costs could be somewhat higher in the future due to higher population densities, aging
infrastructure, or other factors.
Second, valve failure costs were excluded due to lack of data. Valve failure costs include the
replacement costs for EFVs that close and fail to reopen as designed, close falsely, or fail to
close in the event of an incident. They also include replacement costs for curb valves that fail to
close when operated. This omission acts to make the cost figures lower than they otherwise
would be. However, the difference appears to be very small. A previous study of EFVs found
that false closures and failed closures are very rare when EFVs are installed in settings where
27 Thomson, Kathryn and Carlos Monje. “Guidance on Treatment of the Economic Value of a Statistical Life (VSL)
in U.S. Department of Transportation Analyses.” June 17, 2015.
20

<<<PAGE 22>>>

they are currently used (mostly SFRs), occurring in about 1/100th of 1 percent of installed EFVs
among companies surveyed. 28
Third, some benefits are left un-monetized, particularly the value of avoided evacuations and lost
business revenue for residents and customers, and the value of avoided emergency response.
EFVs can prevent the need for evacuations by quickly stopping the flow of gas, reducing the
likelihood of an explosion or fire and therefore allowing residents and businesses to continue
operating normally or at the least shortening the disruption caused by the incident. Further, a
reduced likelihood of explosions or fire following a pipeline incident will cause fewer
emergency response teams to be mobilized and be unnecessarily subjected to fire and danger.
Additionally, there is often valuable time lost, once incidents occur, in waiting for the gas
company to shut off the supply of gas. In previous incidents (including St. Cloud, MN, 1998;
Bridgeport, AL, 1999), emergency responders, gas employees, and public citizens have been
killed or injured because gas continued to flow from a broken pipe to a place where it collected
and ignited. Ensuring that the supply of gas is quickly shut off will prevent these types of
incidents and allow emergency responders, should they need to respond, to attend to people more
quickly and safely.
In its investigation of a pipeline incident at a multi-family residence in Allentown, PA, in June of
1994,
29 the NTSB noted that the Department of Housing and Urban Development (HUD) did not
require the installation of EFVs on multi-family residences where residents receiving Federal
rent subsidies lived. HUD deferred to the Research and Special Programs Administration
(RSPA; later PHMSA) on this recommendation, arguing that the issue was under RSPA’s
purview. This rule will provide equal safety benefits to those members of society who are
receiving Federal housing subsidies, who earn lower incomes and cannot afford to live in SFRs,
or who simply choose to not live in SFRs. The NTSB found that, in the case of the Allentown
incident, it would have cost from $8-10 per apartment to have installed appropriate EFVs and gas
detectors. While “peace of mind,” “confidence in the safety of the gas distribution system,” and,
as a MFR resident, “knowing that they will receive the same technological protection and safety
benefits as someone living in a SFR” aren’t quantifiable benefits, they are certainly
unquantifiable benefits that need to be accounted for.
The environmental and climate-change benefits of reductions in lost gas are also not monetized
in the base case; Appendix B includes estimates of the climate change benefits of reductions in
lost gas. Therefore, the quantifiable benefits presented here somewhat understate the total
societal benefits.
28 Costello, K. and P. Laurent, Survey on Excess Flow Valves: Installations, Cost, Operating Performance, and Gas
Operator Policy, National Regulatory Research Institute, March 2007. The study identified 223 false closures and
26 failures to close out of approximately 2.5 million EFVs.
29 http://www.ntsb.gov/investigations/AccidentReports/Reports/PAR9601.pdf
21

<<<PAGE 23>>>

Fourth, while EFVs operate automatically, curb valves require manual intervention and therefore
will not be effective for all otherwise-eligible incidents. Based on PHMSA’s knowledge of curb
valves, this analysis uses an assumed 90% effectiveness rate to reflect the fact that there will be
cases in which not all incident consequences will be averted because of human and operational
factors (including ability to reach the valve and potential damage to the valve from third-parties).
Appendix A provides sensitivity analysis of other rates.
Fifth, the analysis does not include otherwise eligible and preventable incidents that are not
reportable to PHMSA, either because they are outside PHMSA’s jurisdiction or because they do
not meet the 30-day written reporting criteria as defined in §191.3. The PHMSA incident
database used in this analysis only includes data from incidents where there was a fatality, injury
requiring hospitalization, loss of property greater than $50,000, the unintentional release of more
than three million cubic feet of gas (for incidents since 2011), or where the operator felt the need
to report it. As a result, benefit numbers are lower than they would be if non-reported incidents
were included, particularly for EFVs, which are likely to be more effective than curb valves in
mitigating smaller incidents that could escape manual detection.
Sixth, PHMSA incident and annual reports do not collect information on customer classification;
the analysis uses incident data for which location and classification can be identified by the
research team. As a result, to be conservative, the analysis omits 53 incidents from the database
that are in other respects likely to be candidates due to an inability to determine incident location
and/or classification. For instance, the NTSB noted several instances in which an EFV could
have mitigated or outright prevented incidents where there were one or more fatalities, injuries,
or significant property damage30, including the ones occurring in 1968 at Hapeville, GA; 1972 in
Lake City, MN; 1974 in New York, NY; and 1979 in Stanardsville, VA.
Seventh, all calculations related to service lines, incident rates, and installation costs are based on
the assumption that one customer equals one service line, and will receive one EFV or curb
valve. PHMSA assumes that one EFV or curb valve will be installed on any service line31 and
estimated the costs accordingly. For a small portion of branched service lines where a single
EFV could serve the multiple branches, this assumption may slightly overestimate costs and
underestimate benefits, as this analysis assumes an EFV will be installed both close to the main
and on each service line itself.
Finally, while there is some evidence that operators may begin voluntarily expanding their
installations of EFVs beyond single-family residences, the analysis is calculated against a
30 http://www.ntsb.gov/investigations/AccidentReports/Reports/PAR9601.pdf; Appendix B
31 A service line represents one gas service or “customer.” In multi-family housing, there may be one service for
the entire building, or separate services individually metered for each unit. For consistency, this analysis uses
PHMSA definitions and estimates of services, and assumes that each relevant service will receive an EFV or curb
valve. As noted above, there may be limited cases where a single EFV could serve multiple services, in which case
total installation costs are slightly overstated.
22

<<<PAGE 24>>>

baseline of no voluntary installations. Therefore, if operators begin voluntary installation in
advance of this rule, then actual costs and benefits would be proportionately lower than
estimated here.
A summary table of the data limitations’ effect on estimates is included below.
Limitation Effect
Omission of valve failure costs Reduces costs for both EFVs and curb valves
Un-monetized benefits Reduces benefits for both EFVs and curb
valves
Omission of non-reported incidents Reduces benefits, particularly for EFVs
Omission of non-located incidents Reduces benefits
Assumption of 1 valve installed per line May reduce benefits and increase costs for
branched service lines
Assumption of no voluntary installations May overestimate both benefits and costs of
the rule, to the extent that there is voluntary
installation
7.2 Costs
There are two types of costs considered in a benefit-cost analysis, fixed and variable. Fixed costs
include program costs such as developing a compliance policy, choosing valves and assembling
an inventory, and training current employees. For the rule, these costs are believed to be minimal
and assumed to be zero for estimation purposes, because operators have already conducted these
activities for installing EFVs in single-family residential settings.
32 Similarly, because curb
valves are already an industry-recognized solution for larger installations, there will be little
additional training or materials assembly required.
For this rule, variable costs are equal to the price of a valve, installation, and maintenance. For
EFVs, PHMSA received estimates through informal discussions with an operator and via the
docket that were in the range of $15 to $50 per EFV. Operators did not provide details on the
reasons for the range in reported costs, though factors may include company size and customer
32 Docket Number: PHMSA-RSPA-2004-19854, “Pipeline Safety: Integrity Management Program for Gas
Distribution Pipelines.”
23

<<<PAGE 25>>>

characteristics. The DIMP rule used a cost range of $20 to $30 for EFVs. This analysis uses a
midrange cost estimate of $30, with sensitivity testing of lower ($15) and higher ($50) costs.
The $30 estimate includes additional labor costs resulting from EFV installation as reflected in
conversations with industry. The additional labor cost for an EFV ranges from zero to thirty
minutes with significant reductions as the crew’s installation experience for EFVs increases.33
These time requirements were included in operators’ estimates of total installation costs.
The analysis does not include potential costs from having to re-install an EFV in response to a
significant change in a customer’s gas usage, which might occur when a small commercial
building changes to a more gas-intensive tenant. The typical practice in the gas industry is for the
service line to be sized according to the high end of potential usage, so a change in gas usage can
ordinarily be accommodated without any change to the line or to its EFV. In an extreme case, the
service line would need to be re-sized, and the costs for a new EFV would be captured in the
estimates of “new or replaced” services as described in more detail below in Section 7.4.2.
In addition, there are potential costs from EFV failure. There are three types of potential EFV
failures. First, EFVs can have false closures (discussed above). Second, most EFVs are designed
to reset automatically, but the reset mechanism can fail. Third, a valve can fail to close when an
incident does occur. In each of these failure scenarios, operators and their customers incur costs,
ranging from a service visit and a brief loss of gas service to the need to dig up and replace the
valve. The Interim Evaluation contained estimates of the rates of each of these failure types from
a National Regulatory Research Institute (NRRI) survey, but the estimates were for single-family
residences and may not reflect operators’ concerns of increased load variability for the new
customers. Out of 2.5 million EFVs installed as of 2005 by respondents to the survey, the NRRI
survey found 223 false closures and 26 failures to close. Failures to reset were not captured, nor
were the costs of failure or the failure rate per line-year.
Ideally, the “Costs” section of this analysis would also include the costs of and updated rates for
valve failures, including valve replacement and repair. However, as mentioned above, reliable
data cannot be assembled for this by category, and companies have said that assembling it would
cost more than complying with the rule. It is also possible that failure costs will be negligible if
the failure rates remain what they are with currently installed EFVs.
For curb valves, an assumed average cost of $55 is used, with sensitivity testing of lower ($10)
and higher ($100). Again, costs appear to vary by operator but without clear patterns. As with
EFVs, these cost estimates from operators include the estimated incremental labor costs for
installation. In the case of curb valves, the additional labor required is for excavating the vault
and assembling the above-ground portion of the valve. The requirement applies only to new or
replaced lines, so the excavation costs for the line are not applicable, as the trench would be
open. Costs for manually operating the curb valve in the event of an incident are minimal and are
33 Estimates taken from conversations with industry representatives.
24

<<<PAGE 26>>>

assumed to be zero, given that some form of incident response is already required. Curb valves
are expected to have little hardware cost reduction over time as they are already standard
industry practice. Curb valve maintenance consists of keeping the locations accessible and free
from plants or debris. Based on information received from industry stakeholders, this work will
be coordinated with regularly scheduled maintenance that is already required, and have
essentially no incremental costs.
34 For the purposes of the analysis, curb valve maintenance costs
were therefore assumed to be zero.
Costs for EFVs and curb valves are assumed to remain constant (in inflation-adjusted terms) over
the analysis period. Although there is the possibility that costs could fall with manufacturing
innovations or economies of scale, the analysis assumes conservatively that costs remain
constant.
A small additional cost item is the requirement that certain customers be notified of their ability
to request an EFV installation. Operators have multiple options for fulfilling this requirement,
including something as simple as adding a short statement to customers’ monthly bills. PHMSA
estimates that approximately half of the 6,237 operators categorized as either master meter
operators or small LPG systems will be impacted, resulting in 3,119 operators. This estimate is
based on the premise that only half of these operators have systems that can accommodate an
EFV (based on operational characteristics). PHMSA also estimates that 1,329 gas distribution
operators will be impacted. Therefore, PHMSA estimates a total impacted community of 4,448
(3,119 master meter/small LPG operators and 1,329 gas distribution operators). PHMSA
estimates that each impacted operator will take approximately 30 minutes per year of staff time
to complete this notification, and an additional 30 minutes per year to maintain the associated
records, for a total of 1 hour per year. According to the Bureau of Labor Statistics, a compliance
officer in the natural gas distribution industry has average wages of $43.3635, with similar figures
for other occupations that may handle this requirement. With an adjustment for benefits and
other employer costs of employee compensation, the total loaded cost is approximately $63.11
per hour.36 Overall, the notification and recordkeeping is estimated to entail annual costs of
$280,713 per year (i.e., 4,448 operators * 1 hour/operator * $63.11/hour). Operators could
34 Operators already have to visit locations where curb valves will be for patrolling and leak surveys to comply with
other existing regulations, so there will be no additional travel costs and little to no additional labor required for
checking and operating the valve. For example, a member of the Gas Pipeline Advisory Committee (GPAC) noted
that “accessibility is something we can check on a relatively regular basis” and “we could align [physical operation
of the valve] with our meter change programs and other times when we would be shutting the service line off
anyway.”
35 Bureau of Labor Statistics, Occupational Employment Statistics, May 2015. Occupation code 13-041, industry
code 221200. http://www.bls.gov/oes/current/oes131041.htm
36 Bureau of Labor Statistics, Employer Cost of Employee Compensation (ECEC), December 2015.
http://www.bls.gov/news.release/pdf/ecec.pdf. Wages account for 68.7% of total ECEC for the average civilian
worker. An adjustment factor of 1.4556 (1/0.687) was applied to the wage rate to produce an estimate of total
“loaded” hourly costs.
25

<<<PAGE 27>>>

potentially also incur costs associated with fielding questions from customers about the EFV
notification. However, among docket commenters who responded to PHMSA’s question about
compliance costs, none provided relevant data on this topic (or even identified it as a cost
element). Based on the NRRI studies, only a tiny fraction of eligible customers request an EFV,
even for new services, so it appears that the number of customer enquiries related to retrofits will
likewise be very small. For example, if 1% of the approximately 25 million existing MFR and
small commercial customers enquired about the EFV notification, that is the rough equivalent of
one additional customer service call per operator per business day during the initial year after the
notification. PHMSA therefore expects that questions related to the EFV notification are unlikely
to lead to any measurable increase in staff time or costs for customer service centers.
7.3 Benefits
The benefits provided by either type of valve are the avoidance of incident-related fatalities,
injuries, and property damage over the course of the valve’s lifetime, with future values
discounted to present value. Because EFVs function automatically, they are assumed to prevent
100% of the relevant set of EFV-preventable incidents. This estimate is based in part on NRRI
survey data showing very small numbers of failed closures among operators using EFVs and the
absence of any PHMSA-reported incidents involving failed closures of EFVs. Curb valves are
assumed to have 90% effectiveness because human intervention is required; this assumption is
discussed in Section 7.1.2.
Each valve provides benefits in the form of protection from certain kinds of incidents for the life
span of the valve. Valves are assumed to last for 50 years, as stated in the manufacturer’s
specifications. In each year, the value provided by the valve is equal to the cost of the incidents
that are prevented by the valve multiplied by the likelihood that the incident will occur. The best
source available for the cost of an incident is the PHMSA incident database, though it is limited
to reportable incidents as discussed above.
The benefits are calculated by multiplying the average cost of an incident by the likelihood of an
incident occurring on a line within that customer class. The incident years used are March 2004
through December 2015. The cost of an incident is calculated using fatalities, injuries, and
property damage. Property damage includes the market value of lost gas as reported on the
incident form. Fatalities and injuries are converted to dollar terms using values from
departmental guidance documents: $9.4 million per fatality and $987,000 for an injury requiring
26

<<<PAGE 28>>>

hospitalization.
37 Per departmental guidance, the injury and fatality figures rise 1.07% per year to
account for wage increases over time.
The incident dataset does not include a known load size of the affected customer to use in
determining customer size. The closest approximation available in the database is operating
pressure and pipe size and material.38 Note that while the low-pressure lines will now require a
curb valve, there is no estimate available of the population of low-pressure lines and therefore no
way to generate a rate and include them in the benefits calculation. Similarly, SFR incidents may
include branched lines as well. As there are no defining characteristics separating single-family
service lines from branched lines other than the configuration of the underground piping, this
analysis does not separately analyze the case of branched lines serving SFRs; instead, based on
the findings from the DIMP RIA, EFVs for branched lines serving SFRs are assumed to have net
benefits just as EFVs do in the case of single-serve SFR lines.
To estimate an incident rate, the total number of service lines was taken from the annual report
databases for 2004-2011. The 2004 total was adjusted to reflect that incidents in February and
January were not included in the dataset, and the totals for 2012-2015 were calculated assuming
a 1% growth rate. The sector totals were then calculated by applying the proportions from Table
8-1 of AGA’s Gas Facts, “Gas Industry Sales Customers by Class of Service.
”39 (These
proportions are also used below to estimate the number of installed EFVs per customer class.)
Further, it was assumed that 99.9% of residential customers had known loads not exceeding
1,000 SCFH, while 85% of commercial customers had known loads not exceeding 1,000
SCFH.40 The adjusted totals were summed to provide a total number of line-years on which the
incidents occurred. A line-year is one service line for one year. The line-years are calculated in
the table below.
37 Thomson, Kathryn and Carlos Monje. “Guidance on Treatment of the Economic Value of a Statistical Life (VSL)
in U.S. Department of Transportation Analyses.” June 17, 2015. The injury number is equivalent to a “serious”
injury on the Abbreviated Injury Scale (AIS-3) and is 10.5% of the VSL.
38 The dataset contains eight incidents that occurred on steel or aluminum pipes ¾” NPS or larger with maximum
operating pressures over 100 psi. One of the eight had been classified as a commercial candidate incident for EFV
but was reclassified as industrial for this report based on further research that revealed that the incident occurred on
a diatomaceous earth mine. Four incidents were confirmed as industrial or agricultural by aerial view, two were not
findable, and one appeared to be a new single-family residence next to a field. For the last, there was no information
as to what had been there the year of the incident, so it remained in the dataset. There were also three additional
incidents classified as industrial EFV candidate incidents.
39 American Gas Association, Gas Facts, https://www.aga.org/gas-facts. The shares in 2010, the last available year
in the dataset, were 92.7% residential, 7.1% commercial, and 0.2% industrial. Because the share of residential lines
has been steadily rising relative to commercial and especially industrial lines over time, the 2010 shares were
extended through 2012 rather than using the 2004-2010 average.
40 Data for assumptions gathered in discussion with industry representatives 8/15/2012.
27

<<<PAGE 29>>>

Year MFR < 1,000
SCFH
Commercial <1,000
SCFH
Industrial/Other
2004 16,953,290 3,269,542 721,917
2005 20,383,567 3,891,653 851,908
2006 20,750,284 3,969,917 858,988
2007 20,995,915 3,978,199 858,556
2008 21,174,259 3,990,815 855,451
2009 21,240,908 3,987,022 869,822
2010 21,369,705 3,951,353 852,090
2011 21,540,204 3,982,879 858,888
2012 21,755,606 4,022,708 867,477
2013 21,973,162 4,062,935 876,152
2014 22,192,893 4,103,564 884,913
2015 22,414,822 4,144,600 893,763
Total Line-
Years 252,744,614 47,355,185 10,249,925
Additionally, there are several unquantified benefits from this rule. Requiring the installation of
EFVs on MFRs and branched lines serving SFRs will ensure that all members of society,
regardless of their choice of accommodation, will receive the same level of protection against
EFV-preventable incidents. Currently, only residents of SFRs served by single lines are afforded
this extra safety measure. A person’s dwelling can be dependent on many factors, including
affordability and convenience, and no person should receive fewer pipeline safety benefits than
others based on what type of structure they live in.
Further, more widespread EFV installation will help avoid more unnecessary, costly, and scary
evacuations. Evacuations from leaking gas that otherwise might have been prevented by an EFV
cause residents mental anguish and a loss of confidence in the natural gas distribution system.
They cause businesses lost productivity and commerce.
EFVs also are beneficial where emergency response is concerned. Because EFVs can prevent
incidents that emergency responders would otherwise have to respond to, expanded EFV
installation can help prevent emergency responder mobilization costs and resource costs. Should
emergency responders need to respond to an incident in an area where an EFV has activated,
they can respond more quickly, not having to wait for the gas to be shut off to enter the area and
not being subjected to further potential danger. This can help incident victims get the medical
assistance they need that much more quickly when time is so critical, and it can also help prevent
subsequent injuries or fatalities to emergency responders.
Further, these EFV provisions will help mitigate and prevent consequences of incidents that
involve customer piping, which is non-DOT jurisdictional. PHMSA does not collect data for
28

<<<PAGE 30>>>

incidents that occur on customer piping, but EFVs could prevent or mitigate some portion of
deaths, injuries, and property damage that occur from leaks or incidents on customer piping.
EFVs also protect against intentional pipeline tampering and can provide protection against
seismic events, which has not been accounted for in this analysis. Certain operators, depending
on their geographic region, install EFVs for seismic event protection, and many States encourage
EFV installation for just this purpose.
7.4 Calculations
7.4.1 Per Valve
The table below lays out the numbers of incidents, fatalities, injuries, and property damage by
category; the size of the category; and how the categories were determined. Multi-family
residences had the lowest average incident cost, while industrial/other had the highest average
incident cost, in part due to the high numbers of fatalities per industrial incident. Industrial/other
also had the highest incident rate per line-year. Commercial incidents had the highest property
damage values.
29

<<<PAGE 31>>>

Category/Valve
Multi-Family
Commercial/EFV
Industrial or
Source
Residential/EFV
Large Other/
Curb Valve
Number of
35
64
12
PHMSA incident
incidents 2004-2015
database
Fatalities
5
5
3
PHMSA incident
database
Injuries
12
29
2
PHMSA incident
PHMSAbicident
database
Property Damage
(2012 $)
$9,009,375
$38,103,710
$1,161,468
database
Average Incident
Cost (2012 $)
$1,938,668
$1,776,980
$2,611,289
Calculated
Line-years used in
PHMSA Annual
calculating incident
Reports
rate
252,744,614
47,355,185
10,249,925
Incident rate per
1.4 x 10-7
1.4 x 106
1.2 x 10-6
Calculated
line-year
Assumed Safety
100%
100%
90%
Assumption
Effectiveness
Initial Annual
$0.27
$2.40
$2.75
Calculated
Benefit Per Valve
(incident rate *
Installed
average incident
cost * safety
effectiveness rate
Category
Aerial photos of
Aerial photos of
Pipe size and
Determinants
incident site to
incident site to
pressure,
determine
determine category,
aerial photos
category, incident
incident report
and incident
report, incident
incident cause
report where
cause
available
As the table above shows, PHMSA identified 12 incidents between 2004 and 2015 involving
industrial facilities, or that PHMSA expects would have received a curb valve under the rule.
PHMSA was unable to determine the type of facility (e.g., industrial, commercial, multi-family
residence, other) involved in each incident because this information is not collected by PHMSA.
Although some information was available from aerial photos of the incident locations, PHMSA
30

<<<PAGE 32>>>

was unable to construct a definitive breakdown of estimated benefits for curb valves by customer
type; estimates here are thus based on the best available information.
To find an estimate of the total benefit of a valve for each category, the annual benefit is carried
out for 50 years, and the injury component is allowed to grow with the wage rate over time as
indicated in DOT guidance. Estimates were discounted using both a 7% and 3% rate. Annual
benefit numbers and the total benefit over 50 years for each category are found in the table
below.
Category
Initial Annual
Total Benefit
Total Benefit
Cost Per
Benefit Per
Over 50 Year
Over 50 Year
Valve
Valve Installed
Valve Lifespan, Valve Lifespan,
NPV at 7%
NPV at 3%
Multi-Family EFV
$0.27
$4.23
$8.37
$30
Commercial EFV
$2.40
$36.75
$71.85
$30
Industrial or Large
$2.75
$43.95
$87.48
$55
Other Curb Valve
7.4.2 Nationwide Estimate
The nationwide estimate was created by establishing a baseline number of lines installed each
year that are covered by the rule, forecasting the growth in installation over 50 years, and then
estimating the costs and benefits of valve use on those lines.
One EFV or curb valve, as relevant, is required on each eligible new or replaced service line.
According to PHMSA's annual report for 2011, 819,894 lines had been installed or replaced that
year. The industry estimates provided in comments to the ANPRM, such as those from
Southwest Gas, noted that roughly 95% of all new or replaced lines (for an estimated total of
778,899 lines) would be required to have EFVs under both the current regulations and this EFV
requirement. There were 597,740 EFVs installed in 2011. Assuming that all were required under
existing regulations 41
, this rule covers an additional 181,159 lines. A conservative cost estimate
includes all of these lines, though realistically some will be under 10 psi, have contaminants, etc.
Valves serving multi-family residences are assumed to make up 85% of the installed valves
41 It is possible that some of these installed EFVs represent non-mandatory installations on branched SFR services,
or other customer types, in which case the estimates that follow can be viewed as somewhat conservative (i.e., they
potentially overstate the number of services affected by the rule).
31

<<<PAGE 33>>>

while valves serving commercial properties are assumed to comprise 15% of the installed valves,
based on their relative shares of the overall network as estimated in AGA Gas Facts Table 8-1, as
noted above. Curb valves will be installed on the 5% of lines not covered by EFVs, or 40,955
lines. For the services to be covered by curb valves, it was not possible to create a breakdown by
customer classification, because PHMSA does not collect data on customer classification, and
the overall industry average as estimated by AGA Gas Facts would not be applicable to this
small subset of high-capacity lines. (In other words, service lines that are large enough to require
a curb valve would be much more likely to include industrial and other customer types.)
The estimate is based on the assumption that the number of installations rises 2% a year. As the
Industry Information section showed, installation rates are quite variable, but 2% is a decent
long-range estimate. Estimates at a 7% and 3% discount rate are shown here. Note that net
benefits are greatest for commercial settings.
Annualized Benefits and Costs by Customer Classification, 7% Discount Rate
Category
Number of
Annualized
Annualized Cost
Valves
Benefit (7%)
(7%)
Installed, Year
142
Multi-Family
EFV
153,985
$982,411
$6,204,591
Commercial EFV
27,174
$1,570,953
$1,094,934
Industrial/ Large
Other Curb
40,955
$2,959,482
$3,025,399
Valve
Notification and
Recordkeeping
$280,713
Total per Year,
7% Discount
222,114
$5,512,846
$10,605,637
Rate
42 Year 1 valve installation is based on new and replaced service lines in 2011.
32

<<<PAGE 34>>>

Annualized Benefits and Costs by Customer Classification, 3% Discount Rate
Category
Number of
Annualized Benefit
Annualized Cost
Valves
(3%)
(3%)
Installed,
Year 1
Multi-Family
EFV
153,985
$1,681,877
$7,069,443
Commercial
EFV
27,174
$3,014,836
$1,247,556
Industrial/
Large Other
40,955
$5,870,940
$3,447,107
Curb Valve
Notification
and
$280,713
Recordkeeping
Total per Year,
3% Discount
222,114
$10,567,653
$12,044,818
Rate
8
Summary and Conclusion
This rule extends the required installation of EFVs, require installation of manual shut-off valves
on larger industrial and multifamily residences, and require operators to notify customers of their
ability to request installation of EFVs when service lines are not being newly installed or
replaced. It is expected to generate safety benefits in the form of reduced fatalities, injuries, lost
product and other property damage from certain types of preventable incidents in gas
distribution. In the base case analysis, overall benefits over a 50-year period were estimated at
the annual equivalent of $5.5 million per year versus $10.6 million in compliance costs. In
sensitivity testing, total benefits fell within the expected low-to-high range of costs when using a
range for installation costs; total benefits were also slightly less than costs when using a 3%
discount rate.
Additionally, this regulation addresses Section 22 of the Pipeline Safety, Regulatory Certainty,
and Job Creation Act of 2011 and NTSB Recommendation P-01-2 and can be implemented at
33

<<<PAGE 35>>>

relatively minor cost. EFVs have been shown to be effective for SFRs based on findings from an
NRRI survey showing over 1,100 activations in 2005, each of which represents a potential
incident avoided, with only very small numbers of false and failed closures. Since 2010, PHMSA
has required EFVs to be installed on SFRs and is not aware of any significant issues with false
closures, failed closures, or other issues.
The requirements for installing EFVs on lines serving MFRs could result in the highest cost (in
monetary terms) of the new provisions. Although the monetized costs of these requirements
substantially exceed the monetized benefits, the benefits that have not been monetized (including
peace of mind and protection against high-consequence events equal to residents of SFRs,
avoided evacuations, and avoided emergency response) offset these costs. Further, PHMSA
concludes that this regulation is appropriate due to the potential to prevent a high-consequence
incident of the type identified just outside the analysis period (e.g., Santa Rosa, CA, Dec. 1991;
Allentown, PA, June 1994; St. Cloud, MN, Dec. 1998—all of which affected MFRs and would
have substantially impacted the monetized benefit figures).
We estimate the annualized net benefits of installing EFVs on lines serving MFRs are -$5.2
million per year (7% discount rate) or -$5.4 million per year (3% discount rate). We also
estimate that 153,985 EFVs will be installed on MFR services in year 1 of the analysis period,
rising to about 414,465 installations in year 50. Thus, for the rule to break even in with respect to
MFRs, PHMSA estimates that residents of MFRs would have to derive unquantified benefits
(such as peace of mind) from this provision at somewhere between $13 and $34 per EFV per
year ($5.2 to 5.4 million divided by 152,985 to 414,465 valves). Since that value would reflect
the combined valuation from all of the residents of a given MFR protected by an EFV, it appears
quite reasonable. Moreover, it is inequitable to allow residents of multi-family units to be
exposed to more risk and receive fewer safety benefits than SFR residents because of a
difference of accommodation, which may be dependent on many different factors including
affordability and convenience.
Another way of looking at the breakeven calculation is to examine the consequences of major
EFV-preventable incidents on MFR services. For example, the December 2005 incident in
Bergenfield, N.J., led to 3 fatalities, 2 injuries (or 5 injuries according to news media reports),
and $2.76 million in property damage and other quantified losses. Applying the DOT-standard
injury values used elsewhere in this analysis, the incident had total costs in the range of $33
million. Thus, at an annualized cost of $6.2 million per year, the MFR provision of the rule
would need to prevent an incident of this type roughly once every 5 years to reach breakeven.
Likewise, major industry stakeholders have expressed general support for the regulation, viewing
the expansion of EFV installation as a common-sense safety measure with minimal cost impact.
34

<<<PAGE 36>>>

Appendix A: Sensitivity Testing
Valve Costs: Low and High Scenarios, 7% Discount Rate
Category
Number
Annualized
Annualized Cost,
Annualized Cost,
of Valves
Benefit
Low Scenario ($15
High Scenario ($50
Installed,
EFV, $10 curb
EFV, $100 curb
Year 1
valve)
valve)
Multi-Family
153,985
$3,102,295
$10,340,985
EFV
$982,411
Commercial
27,174
$547,467
$1,824,890
EFV
$1,570,953
Industrial/
40,955
$550,073
$5,500,726
Large Other
Curb Valve
$2,959,482
Notification
$280,713
$280,713
and
Recordkeeping
TOTAL
222,114
$5,512,846
$4,480,548
$17,947,313
35

<<<PAGE 37>>>

Valve Costs: Low and High Scenarios, 3% Discount Rate
Category
Number of Annualized
Annualized Cost,
Annualized Cost,
Valves
Benefit
Low Scenario ($15 High Scenario ($50
Installed,
EFV, $10 curb
EFV, $100 curb
Year 1
valve)
valve)
Multi-Family
EFV
153,985
$1,681,877
$3,534,722
$11,782,405
Commercial
EFV
27,174
$3,014,836
$623,778
$2,079,259
Industrial/
Large Other
40,955
$5,870,940
$626,747
$6,267,467
Curb Valve
Notification
and Record-
$280,713
$280,713
keeping
TOTAL
222,114
$10,567,653
$5,065,959
$20,409,844
36

<<<PAGE 38>>>

Safety Effectiveness of Curb Valves: Low and High Scenarios, 7% Discount Rate
Category
Number Annualized
Annualized
Annualized Cost-
of Valves
Benefit, Low
Benefit,
Base Case
Installed, Scenario:
High Scenario:
Year 143
Curb valves
Curb valves 95%
80% Effective
Effective
Multi-Family
EFV
153,985
$982,411
$982,411
$6,204,591
Commercial
EFV
27,174
$1,570,953
$1,570,953
$1,094,934
Industrial/
Large Other
40,955
$2,630,651
Curb Valve
$3,123,898
$3,025,399
Notification
and Record-
keeping
$280,713
TOTAL
222,114
$5,184,015
$5,677,262
$10,605,637
43 Year 1 valve installation is based on new and replaced service lines in 2011.
37

<<<PAGE 39>>>

Safety Effectiveness of Curb Valves: Low and High Scenarios, 3% Discount Rate
Category
Number of Annualized
Annualized
Annualized Cost-
Valves
Benefit, Low
Benefit,
Base Case
Installed,
Scenario:
High Scenario:
Year 144
Curb valves
Curb valves 95%
80% Effective
Effective
Multi-Family
153,985
$1,681,877
$1,681,877
$7,069,443
EFV
Commercial
27,174
$1,247,556
EFV
$3,014,836
$3,014,836
Industrial/
40,955
$5,218,614
$6,197,104
$3,447,107
Large Other
Curb Valve
$280,713
TOTAL
222,114
$9,915,327
$10,893,817
$12,044,818
44 Year 1 valve installation is based on new and replaced service lines in 2011.
38

<<<PAGE 40>>>

Appendix B:
Including Benefits from Avoided Methane and Carbon Dioxide Emissions -- Reduced
Global Warming Potential (GWP)
Natural gas contains methane and carbon dioxide, heat-trapping gases that contribute to global
climate change and its attendant societal costs. To the extent that EFVs and curb valves reduce
the quantity of natural gas that would otherwise be lost to the atmosphere during pipeline
incidents, this will reduce the external costs associated with these gases’ global warming
potential (GWP). This sensitivity case examines the additional benefits that could be achieved
by including these impacts.
The Interagency Working Group on Social Cost of Carbon (SCC) has estimated the societal
harm of GWP from carbon dioxide emissions at $37 per metric ton in 2007 dollars.45 The $37
estimate was converted to 2012 dollars for comparability with other values used in this analysis
using the CPI-U; this yields an estimated $40.97 per ton of carbon dioxide emitted. (The
Interagency Working Group’s $37 value is based on a 3% discount rate and 2015 base year.
Note that there is no value currently available for the 7% discount rate that is also used in this
analysis, so the tables below use the SCC value associated with the 3% rate for both cases. Also,
the SCC listed is for the timeframe to 2050, slightly shorter than the 50-year timeframe used
here.)
Methane is generally understood to be a more potent greenhouse gas than carbon dioxide,
although with diminishing effects over time. While an official value for methane has not yet
been established, other rulemaking efforts46 have used a multiple of 25 times the social cost of
carbon dioxide emissions as an approximation (in the case, 25* $40.97, or $1024 per metric ton.)
The above estimates of GWP avoided are based on the average volume of lost gas by customer
category as reported for EFV-preventable incidents in 2010 to 2015. (Incident data for prior
years do not include information on the physical quantity of gas released.) Gas was assumed to
comprise 96% methane and 1% carbon dioxide based on industry averages. Volumes were
converted to mass using physical conversion factors at typical tariff pressure and temperature (1
atmosphere, 60 degrees Fahrenheit).
45 See November 2013 update, using 2015 base year and 3% discount rate.
http://www.whitehouse.gov/sites/default/files/omb/assets/inforeg/technical-update-social-cost-of-carbon-for
-regulator-impact-analysis.pdf
46 See, e.g., the Corporate Average Fuel Economy (CAFE) rulemaking,
http://www.nhtsa.gov/staticfiles/rulemaking/pdf/cafe/FRIA_2017-2025.pdf
39

<<<PAGE 41>>>

Sensitivity Case with Social Cost of Carbon: Benefits and Costs, 3% Discount Rate
Category
Number of
Annualized
Annualized
Annualized Cost
Valves
Benefit without
Benefit with
Installed, Year
1
Estimated GWP
Estimated GWP
Avoided
Avoided
Multi-Family
EFV
153,985
$1,681,877
$1,687,026
$7,069,443
Commercial
EFV
27,174
$3,014,836
$3,060,825
$1,247,556
Industrial/ Large
Other Curb
40,955
$5,910,021
$3,447,107
Valve
$5,870,940
Notification and
Recordkeeping
$280,713
TOTAL
222,114
$10,567,653
$10,657,871
$12,044,818
Sensitivity Case with Social Cost of Carbon: Benefits and Costs, 3% Discount Rate for
SCC and 7% Discount Rate for All Other Future Values
Category
Number of
Annualized
Annualized
Annualized Cost
Valves
Benefit without
Benefit with
Installed, Year
1
Estimated GWP
Estimated GWP
Avoided
Avoided
Multi-Family
153,985
EFV
$982,411
$985,401
$6,204,591
Commercial
27,174
EFV
$1,570,953
$1,597,667
$1,094,934
Industrial/ Large
Other Curb
40,955
$2,982,183
$3,025,399
Valve
$2,959,482
Notification and
$280,713
Recordkeeping
TOTAL
222,114
$5,512,846
$5,565,251
$10,605,637
40

## Provenance

- Official: Yes
- Source: <https://downloads.regulations.gov/PHMSA-2011-0009-0049/attachment_1.pdf>
- Source ID: `regulations-gov`
- SHA-256: `761f9c960e66e46920d48f1da4c375998ac18a9bae960eb3ffc3a330fe7ac6e8`
- Retrieved: 2026-08-20T02:22:46.679Z
- Exported: 2026-08-26T16:54:57.802Z
- Document slug: `regulations-gov-attachment-0900006482310371`

### Source metadata

```json
{
  "materialSubtype": "regulations_gov_agency_attachment",
  "parentDocumentId": "regulations-gov-document-phmsa-2011-0009-0049",
  "regulationsGovDocumentId": "PHMSA-2011-0009-0049",
  "docketId": "PHMSA-2011-0009",
  "attachmentId": "0900006482310371",
  "format": "pdf",
  "authorshipClass": "agency_authored",
  "rightsClass": "federal_work",
  "ingestionDecision": "ingest",
  "decisionBasis": [
    "organization:U.S DOT/PHMSA",
    "title:U.S DOT/PHMSA - Regulatory Impact Analysis - October 2016"
  ],
  "summaryEligibility": "eligible",
  "jurisdiction": "US"
}
```
