- **effective on:** 2026-08-18
- **summary:** (a) The requirements for decommissioning pipelines are listed in § 250.1750 through § 250.1754.

(b) The table in this section lists the requirements if you take a DOI pipeline out of service:

If you have the pipeline out of service for: Then you must: (1) 1 year or less, Isolate the pipeline with 
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/30-cfr-250-1006.json
- **markdown:** https://regulus.evalyn.ai/document/30-cfr-250-1006.md
- **app url:** https://regulus.evalyn.ai/document/30-cfr-250-1006
- **source url:** https://www.ecfr.gov/on/2026-08-18/title-30/section-250.1006
**body:**

(a) The requirements for decommissioning pipelines are listed in § 250.1750 through § 250.1754.

(b) The table in this section lists the requirements if you take a DOI pipeline out of service:

If you have the pipeline out of service for: Then you must: (1) 1 year or less, Isolate the pipeline with a blind flange or a closed block valve at each end of the pipeline. (2) More than 1 year but less than 5 years, Flush and fill the pipeline with inhibited seawater. (3) 5 or more years, Decommission the pipeline according to §§ 250.1750-250.1754.