# -20 Reports.

- **operation:** document
- **citation:** 49 CFR 179.300-20
- **title:** -20 Reports.
- **source type:** regulation
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** 2026-08-18
- **summary:** (a) Before a tank is placed in service, the inspector shall furnish to the builder, tank owner, Bureau of Explosives and the Secretary, Mechanical Division, Association of American Railroads, a report in approved form certifying that the tank and its equipment comply with all the requirements of thi
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/49-cfr-179-300-20.json
- **markdown:** https://regulus.evalyn.ai/document/49-cfr-179-300-20.md
- **app url:** https://regulus.evalyn.ai/document/49-cfr-179-300-20
- **source url:** https://www.ecfr.gov/on/2026-08-18/title-49/section-179.300-20
**body:**

(a) Before a tank is placed in service, the inspector shall furnish to the builder, tank owner, Bureau of Explosives and the Secretary, Mechanical Division, Association of American Railroads, a report in approved form certifying that the tank and its equipment comply with all the requirements of this specification.

(b) For builder's Certificate of Construction, see § 179.5 (b), (c), and (d).

[29 FR 18995, Dec. 29, 1964. Redesignated at 32 FR 5606, Apr. 5, 1967, and amended by Amdt. 179-10, 36 FR 21355, Nov. 5, 1971]
- **truncated:** false
- **body characters:** 523