- **summary:** Link to an amendment published at 80 FR 12779, Mar. 11, 2015.

This amendment was delayed indefinitely at 80 FR 58633, Sept. 30, 2015.

Each transmission line or main must be inspected to ensure that it is constructed in accordance with this part.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/49-cfr-192-305.json
- **markdown:** https://regulus.evalyn.ai/document/49-cfr-192-305.md
- **app url:** https://regulus.evalyn.ai/document/49-cfr-192-305
- **source url:** https://www.ecfr.gov/on/2026-08-18/title-49/section-192.305
**body:**

Link to an amendment published at 80 FR 12779, Mar. 11, 2015.

This amendment was delayed indefinitely at 80 FR 58633, Sept. 30, 2015.

Each transmission line or main must be inspected to ensure that it is constructed in accordance with this part.