- **summary:** All below-ground Pipelines, where backfill is required, shall be installed with free-draining fill that completely passes through a 3/8-inch sieve, unless the Pipelines are otherwise protected; and any Pipeline: (1) not exceeding 2 inches in diameter shall be installed with at least 2 inches of fill above and below suc
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/ct-rcsa-16-280b-a33.json
- **markdown:** https://regulus.evalyn.ai/document/ct-rcsa-16-280b-a33.md
- **app url:** https://regulus.evalyn.ai/document/ct-rcsa-16-280b-a33
- **source url:** https://eregulations.ct.gov/eRegsPortal/Search/getDocument?guid=%7BE04F6097-0000-CC1C-9D68-25A0BA411C82%7D
**body:**

All below-ground Pipelines, where backfill is required, shall be installed with free-draining fill that completely passes through a 3/8-inch sieve, unless the Pipelines are otherwise protected; and any Pipeline: (1) not exceeding 2 inches in diameter shall be installed with at least 2 inches of fill above and below such Pipeline, prior to compaction; or (2) exceeding 2 inches in diameter shall be installed with at least 3 inches of fill below and on the sides and at least 6 inches above such Pipeline, prior to compaction.
- **truncated:** false
- **body characters:** 527