# Pipeline Safety: Qualification of Pipeline Personnel

- **operation:** document
- **citation:** 63 FR 57269
- **title:** Pipeline Safety: Qualification of Pipeline Personnel
- **source type:** rulemaking
- **agency:** Research and Special Programs Administration
- **status:** proposed
- **official:** true
- **published on:** 1998-10-27
- **effective on:** Not available
- **summary:** This proposed rule would require pipeline operators to develop and maintain a written qualification program for individuals performing covered tasks on pipeline facilities. The intent of this qualification rule is to ensure a qualified workforce and to reduce the probability and consequence of incidents caused by human error. This NPRM proposes to create new subparts in the gas and hazardous liquid pipeline safety regulations. These would establish qualification requirements for individuals performing covered tasks, and would also amend certain training requirements in the hazardous liquid regulations. This proposed rule was developed through a negotiation process.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/federal-register-98-28662.json
- **markdown:** https://regulus.evalyn.ai/document/federal-register-98-28662.md
- **app url:** https://regulus.evalyn.ai/document/federal-register-98-28662
- **source url:** https://www.federalregister.gov/documents/1998/10/27/98-28662/pipeline-safety-qualification-of-pipeline-personnel
**body:**

Federal Register, Volume 63 Issue 207 (Tuesday, October 27, 1998) [Federal Register Volume 63, Number 207 (Tuesday, October 27, 1998)] [Proposed Rules] [Pages 57269-57279] From the Federal Register Online via the Government Publishing Office [ www.gpo.gov ] [FR Doc No: 98-28662] ----------------------------------------------------------------------- DEPARTMENT OF TRANSPORTATION Research and Special Programs Administration 49 CFR Parts 192 and 195 [Docket No. RSPA-98-3783; Notice 1] RIN 2137-AB38 Pipeline Safety: Qualification of Pipeline Personnel AGENCY: Research and Special Programs Administration (RSPA); Office of Pipeline Safety (OPS). ACTION: Notice of Proposed Rulemaking (NPRM). ----------------------------------------------------------------------- SUMMARY: This proposed rule would require pipeline operators to develop and maintain a written qualification program for individuals performing covered tasks on pipeline facilities. The intent of this qualification rule is to ensure a qualified workforce and to reduce the probability and consequence of incidents caused by human error. This NPRM proposes to create new subparts in the gas and hazardous liquid pipeline safety regulations. These would establish qualification requirements for individuals performing covered tasks, and would also amend certain training requirements in the hazardous liquid regulations. This proposed rule was developed through a negotiation process. DATES: RSPA must receive written comments to this proposed rule by December 28, 1998. ADDRESSES: Comments should be sent to the Dockets Facility, U.S. Department of Transportation, Plaza 401, 400 Seventh Street, SW, Washington, DC 20590-0001. Comments may also be filed electronically by e-mail at [email&#160;protected] . Comments should identify the docket number (RSPA-98-3783). Persons should submit the original document and one (1) copy. Persons wishing to receive confirmation of receipt of their comments must include a self-addressed stamped postcard. The Dockets Facility is open from 9 a.m. to 5 p.m., Monday through Friday, except on Federal holidays. Comments can also be viewed over the Internet on http://dms.dot.gov . FOR FURTHER INFORMATION CONTACT: Eben M. Wyman, (202) 366-0918, or by e-mail at [email&#160;protected] , regarding the subject matter of this notice; or the Dockets Unit, (202) 366-4453, for copies of this notice or other material in the docket. SUPPLEMENTARY INFORMATION: Table of Contents for Supplementary Information I. Introduction. II. Statutory Authority and Regulatory History. III. Negotiated Rulemaking. A. Members of the RSPA Negotiated Rulemaking Committee. B. Negotiated Rulemaking Committee Groundrules. C. Committee Meetings. IV. Scope. A. Persons Covered by the Proposed Rule. B. Operators are Responsible for Identifying Covered Tasks. C. Identification of Covered Tasks. 1. Tasks Performed on a Pipeline Facility. 2. Operation or Maintenance Tasks. 3. Tasks Performed Pursuant to a Requirement in 49 CFR part 192 or 195. 4. Tasks Affecting the Operation or Integrity of the Pipeline. [[Page 57270]] D. Amendments to Sec. 195.403. V. Definitions. VI. Qualification program. VII. Recordkeeping. VIII. General. I. Introduction Although no regulatory program is capable of completely eliminating human error, the objective of this proposed rule is to reduce the risk of accidents on pipeline facilities attributable to human error. This proposed rule for the qualification of individuals is intended to provide an additional level of safety. This proposed rule does not replace existing qualification requirements in 49 CFR part 192. However, it does remove the operations and maintenance training requirements of Sec. 195.403. The proposed rule does not diminish the importance of the safety requirements already in the pipeline safety regulations. These include requirements for safety design features, such as relief valves and over-pressure protection devices, to provide protection against human error and other causes of incidents and accidents. The proposed rule would require operators of pipelines to develop a qualification program to evaluate an individual's ability to perform covered tasks, and to recognize and react to abnormal operating conditions that may occur while performing covered tasks. The proposed rule would also set recordkeeping requirements that operators must follow to successfully demonstrate compliance, and the information that must be maintained on each individual who has been evaluated and deemed qualified to work on a pipeline facility. Finally, the proposed rule would specify the deadlines by which operators must develop and implement their qualification programs. This proposed rule allows operators with existing programs to modify those programs if necessary to ensure compliance with the minimum requirements of this proposed rule. The proposed rule would also require operators without a qualification program to establish a program to evaluate the qualifications of individuals performing certain operation and maintenance activities on those pipeline facilities that could affect pipeline operation or integrity. This proposed rule would establish a new subpart N in 49 CFR part 192 and a new subpart G in 49 CFR part 195. The proposal would amend the training regulations in 49 CFR 195.403. The emergency response training requirements remain as they appear in 49 CFR 195.403. II. Statutory Authority and Regulatory History Sections 106 and 205 of the Pipeline Safety Act of 1992 (Pub. L. 102-508) required the Department of Transportation to establish regulations requiring that ``all individuals responsible for the operation and maintenance of pipeline facilities be tested for qualifications and certified to operate and maintain those facilities.'' On August 3, 1994, RSPA published a notice of proposed rulemaking to establish specific training requirements for the qualification of pipeline workers (59 FR 39506). This proposal would have introduced qualification standards for personnel that perform, or supervise persons performing, regulated operations, maintenance, and emergency response functions. The purpose of the proposal was to improve pipeline safety by requiring operators to ensure the competency of pipeline personnel through training, testing, and periodic refresher training. In response to this notice, RSPA received 131 comments that expressed a wide variety of interests and concerns. Most commenters asserted that the proposal should have taken a more general approach to qualification with broad requirements for persons performing ``safety related'' functions. Commenters stated that the proposal was too prescriptive and that the many references to training requirements should be modified to focus the proposal on actual qualification, rather than on the methods(s) of achieving qualification. OPS' technical advisory committees, the Technical Pipeline Safety Standards Committee and the Technical Hazardous Liquid Pipeline Safety Standards Committee, disapproved of the proposal. These Committees passed several motions for amendments to the proposal. These motions were generally consistent with the written comments. Subsequently, the pipeline safety law was amended to require that ``all individuals who operate and maintain pipeline facilities shall be qualified to operate and maintain the pipeline facilities'' (49 U.S.C. 60102(a)). This law also requires that the ``qualifications applicable to an individual who operates and maintains a pipeline facility shall address the ability to recognize and react appropriately to abnormal operating conditions that may indicate a dangerous situation or a condition exceeding design limits'' (49 U.S.C. 60102(a)). Following review of the comments to the 1994 proposed rulemaking, as well as recommendations by the Technical Advisory Committees, and a petition for withdrawal and alternative proposal submitted collectively by the American Gas Association, the American Public Gas Association, and the Southern Gas Association, RSPA decided that a regulatory process other than traditional rulemaking would better address the issues surrounding operator qualifications. Consequently, RSPA issued a Notice of Withdrawal of the 1994 proposed rulemaking (61 FR 34413, July 22, 1996) and simultaneously issued a Notice of Intent to form a negotiated rulemaking committee to develop a proposed rule on the qualification of pipeline personnel (61 FR 34410, July 22, 1996). III. Negotiated Rulemaking RSPA understands that effective regulatory solutions to certain issues can be difficult for an agency to craft. In the typical rulemaking process, the participants often develop adversarial relationships that prevent effective communication and creative solutions. Exchange of ideas that may lead to solutions that are acceptable to all interested groups does not often occur in the traditional notice and comment rulemaking procedure. Negotiated rulemaking is conducted under authority of the Negotiated Rulemaking Act of 1990 and the Federal Advisory Committee Act. The process involves assembling representatives of the affected interests assemble to discuss a particular issue and all potential solutions. The goal is to reach consensus and prepare a proposed rule for consideration by the agency. After public comment on the proposed rule, the group may reconvene to review the comments and make recommendations for a final rule. This inclusive process is intended to make the proposed rule more acceptable to all affected interests and minimize the likelihood of petitions for reconsideration and litigation. RSPA believed that the negotiated rulemaking process would provide ample opportunity for all affected parties to present their views and to reach a consensus on a proposed qualification rule. Negotiated rulemakings have been used successfully by the Department of Transportation, including the Federal Aviation Administration, the United States Coast Guard, the Federal Highway Administration, and the National Highway Traffic Safety Administration, and the Federal Railroad Administration. In addition, the Environmental Protection Agency, and the Occupational Safety and Health Administration have successfully used the process. [[Page 57271]] A. Members of the RSPA Negotiated Rulemaking Committee The Federal Mediation and Conciliation Service (FMCS) served as the convenor and facilitator for the Negotiated Rulemaking Committee. FMCS chaired the negotiations, offered suggestions in attempting to reach the desired consensus, and helped determine the feasibility of negotiating particular issues. From the beginning of this process, RSPA met with FMCS on several occasions to discuss the issues that needed to be addressed and the interests that needed to be represented on a negotiated rulemaking committee. After a comprehensive search, (RSPA selected the following organizations, representing broad interests, to serve on the Negotiated Rulemaking Committee: 1. American Gas Association (A.G.A.): Represents a large number of gas distribution and a few transmission companies in the pipeline industry. A.G.A. members consist of both large and small operators. 2. American Petroleum Institute (API): Represents the interests of the hazardous liquid pipeline companies. API is the major trade association in the petroleum industry, and also represents the interests of operators of other hazardous liquid pipelines. 3. Interstate Natural Gas Association of America (INGAA): Represents the interests of the larger interstate gas transmission pipeline companies in the natural gas transportation industry. INGAA consists mainly of the larger interstate gas transmission pipelines. 4. American Public Gas Association (APGA): Represents publicly- owned and municipal gas companies. Although these public companies are generally small, they operate a large number of the distribution pipelines in American cities and suburbs. 5. National Propane Gas Association (NPGA): Represents the interests of propane marketing and distribution at the local level . NPGA is made up of both large and small companies. 6. Association of Texas Intrastate Natural Gas Pipelines: Represents the interests of intrastate natural gas transmission pipelines. 7. Midwest Gas Association (MGA): Represents over 300 investor- owned utilities, municipal utilities, contractors and manufacturers. MGA brought considerable expertise in pipeline personnel training issues. 8. NACE International, The Corrosion Society (NACE): An organization of corrosion experts. NACE works primarily on issues of corrosion and corrosion control systems. 9. National Association of Pipeline Safety Representatives (NAPSR): Represents state pipeline safety programs. Many of these organizations will incorporate the final rule on operator qualifications into their pipeline safety program. 10. National Association of Regulatory Utility Commissioners (NARUC): Represents the interests of the state utility commissioners, who regulate gas rates and terms of service in most of the fifty states. 11. National Association of State Fire Marshals: Represents the interests of state fire officials in state safety programs and the issue of qualification for emergency response. 12. International Union of Operating Engineers (IUOE): Represents the interests of a substantial number of pipeline construction and maintenance workers. 13. International Brotherhood of Electrical Workers (IBEW): Represents over 21,000 gas industry workers. 14. Office of Pipeline Safety (OPS): Served as the representative of RSPA, and the Designated Federal Official on the Negotiated Rulemaking Committee. B. Negotiated Rulemaking Committee Groundrules. Most of the procedures and protocols followed in the negotiation were established by the Committee. A set of Committee ``groundrules'' was developed by participants at the initial meeting. Issues discussed and agreed upon by the Committee included: how discussions would be conducted, possibility of subgroups to work on particular issues, expectations of Committee members, the Committee's role throughout the rulemaking process, audience participation, and other topics. The following are some of the more significant critical groundrules established by the Committee: 1. Membership: All organizations were allowed one seat at the table, and permitted to name one alternate to serve in their absence. 2. Good faith: All participants were expected to act in good faith on behalf of their organization. OPS agreed to issue the Committee's proposed rule as long as it was not in conflict with any other legal requirements. In turn, the Committee agreed to support the proposal following publication in the Federal Register. It was agreed that the Committee would be actively involved through publication of the final rule. 3. Conduct of meetings: Committee members reserved the right to bring constituents to the table to address the Committee, and could quietly consult with constituents during the course of the negotiation. All meetings were open to the public. The Committee agreed that there would be time scheduled on every meeting agenda for comment by the audience. 4. Public Record: RSPA kept a record of all Committee meetings. This record was placed in the public docket (Docket No. PS 94) and is publicly available. 5. Consensus: The goal of the negotiating process is consensus. The Committee developed its own definition of consensus for the purposes of this rulemaking, which was as follows: ``A decision which all members or designated alternates present at the meeting can agree upon. The decision may not be everyone's first choice, but they have heard it and everyone can live with it.'' C. Committee Meetings. The Committee convened a total of seven times between May, 1997, and January, 1998. Each negotiating session lasted a minimum of two days, with two sessions convening for two and a half days. The Committee reached final consensus on the NPRM in its last meeting in January, 1998. IV. Scope The Accountable Pipeline Safety and Partnership Act of 1996 required RSPA to adopt regulations requiring that ``all individuals who operate and maintain pipeline facilities shall be qualified to operate and maintain the pipeline facilities'' and ``shall address the ability to recognize and react appropriately to abnormal operating conditions that may indicate a dangerous situation or a condition exceeding design limits'' (49 U.S.C. 60102(a)). The Committee determined that a national qualification program conducted by RSPA, another federal agency, or a state agency, would not be an appropriate or practical response to this mandate. Such a system offers the advantages of national consistency, including the ability of contractor employees to work for different operators under a single qualification regime. However, it was determined that the complexity and cost of administering such a system, coupled with the difficulty of devising a system appropriate for the wide variations in the operations and maintenance procedures and facilities of individual operators, precluded this from being an effective option. The Committee determined the mandate would best be met by a non- prescriptive, performance based regulation requiring each operator to develop, or have developed, a written program for the qualification of individuals. This would allow each program to be tailored to the unique operations and practices of each operator. [[Page 57272]] A. Persons Covered by the Proposed Rule This proposed rule applies to operators subject to the requirements of 49 CFR parts 192 or 195. The rule applies to all individuals who perform covered tasks, regardless of whether they are employed by the operator, a contractor, a sub-contractor, or any other entity performing covered tasks on behalf of the operator. B. Operators are Responsible for Identifying Covered Tasks Under this proposed rule, the operator would be responsible for identifying which activities performed on the pipeline facility are covered tasks. The process for identifying covered tasks is set forth in 49 CFR 192.801 and 195.501 (``Scope'') of this proposed rule. The Committee discussed whether the regulator or the operator should be responsible for identifying covered tasks. Because of large differences between operations of pipelines across the country, a uniform list of tasks would not be useful, and could result in overall increased costs. For example, some operators do not have transmission lines in their systems, others operate only distribution lines, and others do not have compressors, pump stations, or storage facilities. Some operators perform a large number of covered tasks, while other, smaller, operators may have only a limited number of tasks that would be classified as covered tasks. Identification of covered tasks is a key component of the qualification requirements under this proposed rule. The Committee proposed that it would be more effective and practical to let each operator determine the covered tasks requiring qualification. However, some Committee members were concerned that if operators are allowed to determine the covered tasks, the proposed rule should also ensure that the regulators retain the authority to review each operator's determinations. Some Committee members objected to allowing each operator to identify covered tasks requiring individuals to be qualified. These members objected to the use of the words ``determined by,'' which could be interpreted to preclude regulators from questioning the operator's identification of covered tasks. The Committee decided to use the words ``identified by'' to mean the selection of covered tasks by the operator. The Committee concluded that the authority to allow pipeline safety regulators to require modifications to programs that fail to meet regulatory requirements was already within the scope of federal and state jurisdiction, as was the authority to question particular activities included as covered tasks by the operator. The Committee concluded that covered tasks would be activities identified by the operator. Therefore, under this proposed rule, the operator of a pipeline facility would be responsible for identifying which activities performed on that facility are covered tasks. The criteria for identifying such tasks on gas and hazardous liquid pipelines is set forth in 49 CFR 192.801 and 195.501, respectively. Although operators are responsible for identifying covered tasks for which individuals must be qualified, regulators remain responsible for reviewing operator qualification programs and ensuring that federal regulatory standards are applied and met nationwide. Regulators may question an operator's inclusion and exclusion of particular activities as covered tasks. Regulators may require modifications to programs that fail to meet the requirements of the rule. C. Identification of Covered Tasks The proposed rule includes a four-part test that each operator must use to determine whether an activity constitutes a covered task. A covered task is: (1) Performed on a pipeline facility; (2) an operations or maintenance task; (3) performed pursuant to a requirement in 49 CFR part 192 or 195; and (4) affects the operation or integrity of the pipeline. 1. Tasks performed on a pipeline facility. The phrase ``performed on a pipeline facility'' means an activity that is performed by an individual whose performance directly impacts the pipeline facility. An individual who works on a pipeline component that is physically connected to the pipeline system is performing work ``on a pipeline facility'' and may be subject to the proposed rules, regardless of whether or not product is flowing through the pipeline. However, a person who repairs a pipeline system or appurtenance, that has been removed from the system, would not be performing work on the pipeline, and therefore would not be performing a covered task. 2. Operations or maintenance tasks. The Federal pipeline safety law requires that all individuals who operate and maintain pipeline facilities be qualified to operate and maintain those facilities (49 U.S.C. 60102(a)(1)(C)). Most of the operations and maintenance activities on pipeline facilities are found in 49 CFR part 192, subparts L and M, or in 49 CFR part 195, subpart F. In addition, the regulations contain other subparts that include requirements for conducting operations and maintenance activities. For example, part 192, subpart I, establishes requirements for protecting metallic pipelines from external, internal, and atmospheric corrosion. The requirements to monitor corrosion control systems are operations activities. The requirements to take corrective action when deficiencies are found in a corrosion control program are maintenance activities. Therefore, the task of repairing pipelines affected by corrosion is also a maintenance activity. Certain tasks performed on pipeline facilities may be covered tasks when performed in the course of operation and maintenance activities, but not be covered tasks in the course of other activities. For example, the task of ``welding'' could be a covered task when performed as an operations and maintenance activity on a pipeline, such as when installing a weld-over sleeve to repair an anomaly. However, the task of ``welding'' is not a covered task under this subpart when performed during the fabrication of new installations, because this would not be an operations and maintenance task. However, welders are currently subject to qualification requirements in 49 CFR part 192, subpart E, and 195, subpart D. To comply with the proposed rule, welders would have to be additionally qualified to recognize and react to abnormal operating conditions when welding as a covered task. This also applies to other tasks such as ``plastic pipe joining'', for which the regulations contain specific requirements. 3. Tasks Performed Pursuant to a Requirement in 49 CFR part 192 or 195. Covered tasks include only those operations and maintenance activities required by 49 CFR part 192 or 195. Examples of covered tasks might include: Purging a pipeline because it is specifically required by 49 CFR 192.629; Leakage surveys of distribution lines, required by 49 CFR 192.723; Starting, operating, and shutting down gas compressor units, because 49 CFR 192.605(b)(7) specifically requires written procedures on these tasks, to provide safety during maintenance and operations; Inspection of navigable water crossings under 49 CFR 195.412; and Inspection of breakout tanks required by 49 CFR 195.432. Operators of pipeline facilities may voluntarily conduct operations and maintenance activities that are not [[Page 57273]] required by a specific provision in 49 CFR part 192 or 195. However, an activity does not necessarily become a covered task simply because an operator develops procedures for conducting the activity, and includes those procedures in its Operations and Maintenance Plan. For example, an operator may voluntarily choose to maintain a customer's buried piping, and include procedures for this activity in its Operations and Maintenance Plan. Because such maintenance is not specifically required by 49 CFR part 192 or 195, the associated maintenance activities are not covered tasks. It is possible for a task to be ``performed pursuant to a requirement in part 192 or 195'' even if the task is not specifically addressed by a particular section. The task need only be performed pursuant to the requirement contained in a particular section. For example, 49 CFR 195.428 states that each operator shall inspect overpressure protection devices and ensure these devices are operating adequately. Section 195.428 does not explicitly discuss calibrations that may be necessary to address low pressure shutdowns; yet such calibrations may be required to comply with the regulation. Therefore, the task of calibrating the overpressure protection devices to address low pressure shutdowns would be performed as a result of a requirement contained in part 195. 4. Tasks affecting the operation or integrity of the pipeline. Under the proposed rule, covered tasks include only those activities that could affect the operation or integrity of the pipeline. The main purpose of the proposed rule is to ensure safety of pipelines through qualification of individuals. Initial discussions centered around safety-related tasks and the need to categorize covered tasks as only those tasks as having safety implications. Some Committee members argued that most of the provisions in 49 CFR parts 192 and 195 regulate safety-related activities. It would therefore be redundant to include the word ``safe'' on pipeline operations addressed under this criteria. Therefore, it was decided to use the phrase, ``operation or integrity,'' because some tasks do not adversely affect the operation or integrity of the pipeline, even though they meet the other three criteria. The Committee decided to include a fourth criteria that must be satisfied for a task to be a covered task, namely that the task affects the operation or integrity of the pipeline. The Committee discussed the term ``operation'' as used here in the safety context of normal versus abnormal operation, where the latter could result in an unsafe condition. For example, the control of flow and pressure in pipelines could result in abnormal operation, if the pressure is allowed to rise above an acceptable limit. Therefore, in this example, activities that include controlling flow and pressure on a pipeline system would be considered covered tasks if the other three criteria for covered tasks were met. An additional example of a task affecting the integrity of the pipeline would be coating or jacketing of aboveground pipeline components. In the event atmospheric corrosion is present, coating or jacketing the component could affect the integrity of the pipeline. However, painting a pipeline for aesthetic reasons would not affect the integrity of the pipeline. The ``integrity'' of the pipeline refers to the pipeline's ability to operate safely and to withstand stresses imposed during operations. An example of a short-term effect on integrity would be exceeding the Maximum Allowable Operating Pressure (MAOP) for gas pipelines and Maximum Operating Pressure (MOP) for liquid pipelines. An example of a long-term effect would be failure from corrosion due to improper coating after repair of a welded joint. Because the term ``pipeline facility'' was used in the first criteria, the Committee also considered whether it would be appropriate to use the term ``pipeline facility,'' in the fourth criteria instead of the term ``pipeline''. Although some argued that consistency should be maintained, others stated that the primary goal of the proposed rule is to ensure the safe operation and integrity of the pipeline itself. Furthermore, the term ``pipeline'' as defined in 49 CFR parts 192 and 195 already encompasses the ``facilities'' targeted by the proposed rule. The Committee therefore agreed that this criterion should remain unchanged. If a task fails to meet any one of the four criteria, the task would not be considered a covered task under this proposed rule. The following are hypothetical examples of how the four-part test can be used to identify a covered task: Example 1: Leakage surveys on gas transmission pipelines. (1) Performed on a pipeline facility? Yes, because leakage surveys are performed immediately above the pipeline and on the pipeline right-of-way. (2) Is an operations and maintenance task? Yes, leakage surveys are conducted in the course of pipeline operations and maintenance activities. (3) Is performed as a requirement of this part? Yes, leakage surveys are required by 49 CFR 192.706 and 192.723. (4) Affects the operation or integrity of the pipeline? Yes, if a leakage survey is not properly conducted, a leak might not be detected resulting in a potentially hazardous situation. Since all four criteria are met, the leakage survey is a covered task. Example 2: Measuring pipe-to-soil potentials. (1) Performed on a pipeline facility? Yes, pipe-to-soil potentials are measured at cathodic test stations attached directly to the pipeline. (2) Is an operations and maintenance task? Yes, as pipe-to-soil potentials are read in the course of pipeline operations and maintenance activities. (3) Is performed as a requirement of this part? Yes, pipe-to- soil potential measurements are required by 49 CFR 192.465 and 195.416. (4) Affects the operation or integrity of the pipeline? Yes, pipe-to -soil potential measurements, if taken improperly will, not accurately reflect the level of cathodic protection being provided. While not affecting the immediate operation of the pipeline, the future integrity of the pipeline might be jeopardized (i.e. corrosion might develop), if inadequate cathodic protection is applied to the pipeline over a period of time. Since all four criteria are met, the measurement of pipe-to-soil potentials is a covered task. Example 3: Meter reading. (1) Performed on a pipeline facility? Yes, a meter is a part of a pipeline facility. (2) Is an operations and maintenance task? Yes, meters are read in the course of pipeline operations and maintenance activities. (3) Is performed as a requirement of this part? No, meter reading is not a requirement of 49 CFR part 192 or part 195. (4) Affects the operation or integrity of the pipeline? No, meter reading has no impact on pipeline operation or integrity. Because the task of meter reading fails at least one of the four criteria, meter reading is not considered a covered task. In identifying covered tasks, operators must consider specific tasks and not necessarily the job classification of individuals performing the tasks, because each job classification may incorporate several tasks. For example, an individual with the job classification, ``meter reader,'' may be assigned tasks other than reading a meter, such as distribution line patrolling under 49 CFR Part Sec. 192.721, that could be covered tasks. D. Amendments to Sec. 195.403 (Training) Section 195.403 currently prescribes the training requirements for operations, maintenance, and emergencies for operators of hazardous liquid pipelines. Because the proposed rule includes a qualification process for operations and maintenance activities, but does not [[Page 57274]] address emergency response qualification, 49 CFR 195.403 would be amended to retain emergency response training requirements. This rule proposes to remove the specific operations and maintenance training requirements addressed in 49 CFR 195.403. Persons performing operations and maintenance tasks would need to be qualified in accordance with the proposed rule. V. Definitions The definitions section of this proposed rule was developed to facilitate common understanding of key terms. The Committee began using a number of terms that were not commonly defined by all members. To facilitate communication, these terms were defined and are provided in the proposed rule. Abnormal Operating Condition An abnormal operating condition, as defined in this proposed rule, is ``a condition identified by the operator that may indicate a malfunction of a component or deviation from normal operations that may indicate a condition exceeding design limits or result in a hazard(s) to persons, property, or the environment.'' This definition is derived from Federal pipeline safety law (49 U.S.C. 60102), and 49 CFR 192.605 (c)(1)(v) and 49 CFR 195.402(d)(1)(v). ``Abnormal operating conditions'' is also referenced in the definition of the term ``qualified''. To be qualified, an individual needs to be able to properly perform assigned covered tasks and be able to recognize and react to an abnormal operating condition that may be encountered while performing the covered task. For example, this may include notifying the responsible parties or taking corrective action to mitigate the condition. As an example, an individual that has been qualified to perform leak surveys should be able to recognize and react to an abnormal operating condition such as blowing gas. Likewise, an individual who is qualified to perform control of gas pressure and flow should be able to recognize and react to an abnormal operating pressure in a pipeline segment. Not all atypical operating conditions are abnormal. An example of an atypical operating condition that is not abnormal is a pipeline which can (not to exceed MAOP or MOP) operate up to 200 pounds per square inch (psig), but which typically operates at 50 psig. Operating this pipeline at 150 psig could be atypical, but not abnormal. If however the atypical operating condition would cause the pressure in the pipeline to exceed its allowable limits or cause a hazard to persons, property or the environment, an abnormal operating condition would result. A qualified individual performing control of gas pressure and flow who observes an unanticipated pressure increase in such a pipeline segment should know to investigate the cause of the change before it reaches the MAOP/MOP of the line. Evaluation An evaluation of an individual's ability to perform a covered task is the process that assesses and documents the individual's qualifications to perform the covered task. Although the definition lists several acceptable methods for evaluation, the list is not all- inclusive. The evaluation of an individual's qualifications should be an objective, consistent process that documents an individual's ability to perform the covered task. This includes the individual's ability to recognize and react to abnormal operating conditions that the operator could reasonably anticipate the qualified individual will encounter while performing the covered task. The operator should establish the acceptance criteria for the evaluation method used (for example, for on-the-job training spell out the performance criteria; for a written exam establish the cutoff score). The following table was developed in Committee discussion and shows acceptable evaluation methods for `transitional', `initial' and `subsequent' qualification: ---------------------------------------------------------------------------------------------------------------- `Transitional' `Initial' qualification `Subsequent' Evaluation method qualification \1\ \2\ qualification \3\ ---------------------------------------------------------------------------------------------------------------- Written exam..................... YES...................... YES..................... YES Oral exam........................ YES...................... YES..................... YES Work performance history review.. YES...................... May not be used as the May not be used as the sole evaluation method. sole evaluation method after the three-year compliance date. Performance on-the-job........... YES...................... YES..................... YES On-the-Job Training.............. YES...................... YES..................... YES Simulation....................... YES...................... YES..................... YES Other............................ YES...................... YES..................... YES ---------------------------------------------------------------------------------------------------------------- Notes: \1\ `Transitional' qualification means qualification completed during the period between the effective date of the rule and the three-year compliance date, of individuals who have been performing a covered task on a regular basis prior to the effective date of the rule. \2\ `Initial' qualification means qualification, at any time, of individuals who were not performing a covered task on a regular basis prior to the effective date of the rule. \3\ `Subsequent' qualification means evaluation of an individual's qualification, after `transitional' or `initial' qualification, at the interval established by the operator. Under 49 CFR 192.809(c) and 195.509(c), a work performance history review may not be used as a sole evaluation method after {INSERT 38 MONTHS FOLLOWING PUBLICATION OF THE FINAL RULE} `Transitional' qualification may rely on a work performance history review as the sole evaluation method. `Initial' qualification may not rely on only a work performance history review. `Subsequent' qualifications may rely on work performance history review if used in conjunction with at least one other evaluation method. The operator must establish the parameters for the work performance history review. For example, a work performance history review may include: a search of existing records for documentation of an individual's past satisfactory performance of a covered task(s); verification that the individual's work performance history contains no indications of substandard work or involvement in an incident (part 192) or accident (part 195), caused by an error in performing a covered task; and, verification that the individual has successfully performed the covered task on a regular basis prior to the effective date of the rule. [[Page 57275]] Qualified Qualified, means that an individual has been evaluated and is able to properly perform a covered task(s), and recognize and react to abnormal operating conditions that may be encountered during the performance of the covered task(s). An individual may be qualified using any of the evaluation methods specified in the operator's written qualification program. VI. Qualification Program The Committee identified the following seven elements as requirementsd in the operator's qualification program: Paragraph (a) of 49 CFR 192.805 and 195.505 require operators to identify the covered tasks to be included in the qualification program. Whether an activity is a covered task would be determined using the four criteria in 49 CFR 192.801(b) or 195.501(b). Because operators are responsible for identifying covered tasks, va
- **truncated:** true
- **body characters:** 70616