# HAR 6-77-185 Test requirements for reinstating service lines

- **operation:** document
- **citation:** HAR 6-77-185
- **title:** HAR 6-77-185 Test requirements for reinstating service lines
- **source type:** regulation
- **agency:** Hawaii Public Utilities Commission
- **status:** current
- **official:** true
- **published on:** 1994-04-15
- **effective on:** 1994-09-03
- **summary:** subsection (b), each disconnected service line must be tested in the same manner as a new service line, before being reinstated. (b) Each service line temporarily disconnected from the main must be tested from the point of disconnection to the service line valve in the same manner as a new service l
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/hi-har-har-6-77-185.json
- **markdown:** https://regulus.evalyn.ai/document/hi-har-har-6-77-185.md
- **app url:** https://regulus.evalyn.ai/document/hi-har-har-6-77-185
- **source url:** https://puc.hawaii.gov/wp-content/uploads/2026/04/HAR-6-77-Transp-of-Gas-03-31-2026.pdf
**body:**

subsection (b), each disconnected service line must be tested in the same manner as a new service line, before being reinstated. (b) Each service line temporarily disconnected from the main must be tested from the point of disconnection to the service line valve in the same manner as a new service line, before reconnecting. However, if provisions are made to maintain continuous service, such as by installation of a bypass, any part of the original service line used to maintain continuous service need not be tested. [Eff ] (Auth: HRS '269-6) (Imp: 49 C.F.R. '192.725, October 1, 1990)
- **truncated:** false
- **body characters:** 589