- **operation:** document
- **citation:** LAC 43:XIII §2303
- **title:** General Requirements [49 CFR 192.503]
- **source type:** regulation
- **agency:** Louisiana Office of Conservation
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** A. No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been relocated or replaced, until: [49 CFR 192.503(a)] 1. it has been tested in accordance with this Chapter and §2719 to substantiate the maximum allowable operating pressure; and [49 CFR 192.503
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2303.json
- **markdown:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2303.md
- **app url:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2303
- **source url:** https://www.doa.la.gov/doa/osr/louisiana-administrative-code/
**body:**

A. No person may operate a new segment of pipeline, or return to service a segment of pipeline that has been relocated or replaced, until: [49 CFR 192.503(a)]

1. it has been tested in accordance with this Chapter and §2719 to substantiate the maximum allowable operating pressure; and [49 CFR 192.503(a)(1)]

2. each potentially hazardous leak has been located and eliminated. [49 CFR 192.503(a)(2)]

B. The test medium must be liquid, air, natural gas, or inert gas that is: [49 CFR 192.503(b)]

1. compatible with the material of which the pipeline is constructed; [49 CFR 192.503(b)(1)]

2. relatively free of sedimentary materials; and [49 CFR 192.503(b)(2)]

3. except for natural gas, nonflammable. [49 CFR 192.503(b)(3)]

C. Except as provided in §2305.A, if air, natural gas, or inert gas is used as the test medium, the following maximum hoop stress limitations apply. [49 CFR 192.503(c)]

Class Location

Maximum Hoop Stress Allowed as Percentage of SMYS

Natural Gas

Air or Inert Gas

1

80

80

2

30

75

3

30

50

4

30

40

D. Each joint used to tie in a test segment of pipeline is excepted from the specific test requirements of this Chapter, but each non-welded joint must be leak tested at not less than its operating pressure. [49 CFR 192.503(d)]

E. If a component other than pipe is the only item being replaced or added to a pipeline, a strength test after installation is not required, if the manufacturer of component certifies that: [49 CFR 192.503(e)]

1. the component was tested to at least the pressure required for the pipeline to which it is being added; [49 CFR 192.503(e)(1)]

2. the component was manufactured under a quality control system that ensures that each item manufactured is at least equal in strength to a prototype and that the prototype was tested to at least the pressure required for the pipeline to which it is being added; or [49 CFR 192.503(e)(2)]

3. the component carries a pressure rating established through applicable ASME/ANSI, Manufacturers Standardization Society of the Valve and Fittings Industry, Inc. (MSS) specifications, or by unit strength calculations as described in §1103. [49 CFR 192.503(e)(3)]

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.