# General Requirements [49 CFR 192.553]

- **operation:** document
- **citation:** LAC 43:XIII §2503
- **title:** General Requirements [49 CFR 192.553]
- **source type:** regulation
- **agency:** Louisiana Office of Conservation
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** A. Pressure Increases. Whenever the requirements of this Chapter require that an increase in operating pressure be made in increments, the pressure must be increased gradually, at a rate that can be controlled, and in accordance with the following. [49 CFR 192.553(a)] 1. At the end of each increment
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2503.json
- **markdown:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2503.md
- **app url:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2503
- **source url:** https://www.doa.la.gov/doa/osr/louisiana-administrative-code/
**body:**

A. Pressure Increases. Whenever the requirements of this Chapter require that an increase in operating pressure be made in increments, the pressure must be increased gradually, at a rate that can be controlled, and in accordance with the following. [49 CFR 192.553(a)]

1. At the end of each incremental increase, the pressure must be held constant while the entire segment of the pipeline that is affected is checked for leaks. [49 CFR 192.553(a)(1)]

2. Each leak detected must be repaired before a further pressure increase is made, except that a leak determined not to be potentially hazardous need not be repaired, if it is monitored during the pressure increase and it does not become potentially hazardous. [49 CFR 192.553(a)(2)]

B. Records. Each operator who uprates a segment of pipeline shall retain for the life of the segment a record of each investigation required by this Chapter, of all work performed, and of each pressure test conducted, in connection with the uprating. [49 CFR 192.553(b)]

C. Written Plan. Each operator who uprates a segment of pipeline shall establish a written procedure that will ensure that each applicable requirement of this Chapter is complied with. [49 CFR 192.553(c)]

D. Limitation on Increase in Maximum Allowable Operating Pressure. Except as provided in §2505.C, a new maximum allowable operating pressure established under this Chapter may not exceed the maximum that would be allowed under §§2719 and 2721 for a new segment of pipeline constructed of the same materials in the same location. However, when uprating a steel pipeline, if any variable necessary to determine the design pressure under the design formula (§905) is unknown, the MAOP may be increased as provided in §2719.A.1. [49 CFR 192.553(d)]

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.

HISTORICAL NOTE: Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:239 (April 1983), amended LR 10:531 (July 1984), LR 24:1312 (July 1998), LR 30:1258 (June 2004).