# Transmission Lines: Leakage Surveys [49 CFR 192.706]

- **operation:** document
- **citation:** LAC 43:XIII §2906
- **title:** Transmission Lines: Leakage Surveys [49 CFR 192.706]
- **source type:** regulation
- **agency:** Louisiana Office of Conservation
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** A. Leakage surveys of a transmission line must be conducted at intervals not exceeding 15 months, but at least once each calendar year. However, in the case of a transmission line which transports gas in conformity with §2725 without an odor or odorant, leakage surveys using leak detector equipment 
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2906.json
- **markdown:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2906.md
- **app url:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2906
- **source url:** https://www.doa.la.gov/doa/osr/louisiana-administrative-code/
**body:**

A. Leakage surveys of a transmission line must be conducted at intervals not exceeding 15 months, but at least once each calendar year. However, in the case of a transmission line which transports gas in conformity with §2725 without an odor or odorant, leakage surveys using leak detector equipment must be conducted: [49 CFR 192.706]

1. in Class 3 locations, at intervals not exceeding seven and one-half months, but at least twice each calendar year; and [49 CFR 192.706(a)]

2. in Class 4 locations, at intervals not exceeding four and one-half months, but at least four times each calendar year. [49 CFR 192.706(b)]

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.

HISTORICAL NOTE: Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:244 (April 1983), amended LR 10:536 (July 1984), LR:21:823 (August 1995), LR 30:1267 (June 2004).
- **truncated:** false
- **body characters:** 886