# Transmission Lines: Testing of Repairs [49 CFR 192.719]

- **operation:** document
- **citation:** LAC 43:XIII §2919
- **title:** Transmission Lines: Testing of Repairs [49 CFR 192.719]
- **source type:** regulation
- **agency:** Louisiana Office of Conservation
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** A. Testing of Replacement Pipe. If a segment of transmission line is repaired by cutting out the damaged portion of the pipe as a cylinder, the replacement pipe must be tested to the pressure required for a new line installed in the same location. This test may be made on the pipe before it is insta
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2919.json
- **markdown:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2919.md
- **app url:** https://regulus.evalyn.ai/document/la-lac-43-xiii-2919
- **source url:** https://www.doa.la.gov/doa/osr/louisiana-administrative-code/
**body:**

A. Testing of Replacement Pipe. If a segment of transmission line is repaired by cutting out the damaged portion of the pipe as a cylinder, the replacement pipe must be tested to the pressure required for a new line installed in the same location. This test may be made on the pipe before it is installed. [49 CFR 192.719(a)]

B. Testing of Repairs Made by Welding. Each repair made by welding in accordance with §§2913, 2915, and 2917 must be examined in accordance with §1321. [49 CFR 192.719(b)]

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:501 et seq.

HISTORICAL NOTE: Promulgated by the Department of Natural Resources, Office of Conservation, LR 9:245 (April 1983), amended LR 10:537 (July 1984), LR 30:1268 (June 2004).
- **truncated:** false
- **body characters:** 738