# Auxiliary Power Sources [49 CFR 193.2613]

- **operation:** document
- **citation:** LAC 43:XIII §7913
- **title:** Auxiliary Power Sources [49 CFR 193.2613]
- **source type:** regulation
- **agency:** Louisiana Office of Conservation
- **status:** current
- **official:** true
- **published on:** Not available
- **effective on:** Not available
- **summary:** A. Each auxiliary power source must be tested monthly to check its operational capability and tested annually for capacity. The capacity test must take into account the power needed to start up and simultaneously operate equipment that would have to be served by that power source in an emergency. [4
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/la-lac-43-xiii-7913.json
- **markdown:** https://regulus.evalyn.ai/document/la-lac-43-xiii-7913.md
- **app url:** https://regulus.evalyn.ai/document/la-lac-43-xiii-7913
- **source url:** https://www.doa.la.gov/doa/osr/louisiana-administrative-code/
**body:**

A. Each auxiliary power source must be tested monthly to check its operational capability and tested annually for capacity. The capacity test must take into account the power needed to start up and simultaneously operate equipment that would have to be served by that power source in an emergency. [49 CFR 193.2613]

AUTHORITY NOTE: Promulgated in accordance with R.S. 30:551.C.

HISTORICAL NOTE: Promulgated by the Department of Natural Resources, Office of Conservation, LR 44:1056 (June 2018).
- **truncated:** false
- **body characters:** 496