# Enbridge Inc. Natural Gas Pipeline Rupture and Fire

- **operation:** document
- **citation:** PLD20LR001
- **title:** Enbridge Inc. Natural Gas Pipeline Rupture and Fire
- **source type:** incident
- **agency:** National Transportation Safety Board
- **status:** current
- **official:** true
- **published on:** 2022-06-08
- **effective on:** 2020-05-04
- **summary:** Accident. in Hillsboro, KY, USA. on 2020-05-04. Enbridge Inc.. Rupture/fire
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/ntsb-case-pld20lr001.json
- **markdown:** https://regulus.evalyn.ai/document/ntsb-case-pld20lr001.md
- **app url:** https://regulus.evalyn.ai/document/ntsb-case-pld20lr001
- **source url:** https://www.ntsb.gov/investigations/Pages/PLD20LR001.aspx
**body:**

NTSB investigation PLD20LR001.

Event Type: Accident

Event Date: 2020-05-04

Event City: Hillsboro

Event State Or Region: KY

Event Country: USA

Pipeline Operator: Enbridge Inc.

Pipeline Type: Gas Transmission - Regulated

Accident Type: Rupture/fire

Completion Status: Completed

Report Number: PIR2201

Report Date: 2022-05-31

Probable cause: The National Transportation Safety Board determines that the probable cause of the pipeline rupture was Enbridge Inc.’s analysis of an active landslide that did not fully address uncertainties associated with pipeline defects, landslide movement, and corresponding pipeline response.

Tier1Name: Emergency response

Tier2Name: Emergency shutoff

Tier1Name: System operating

Tier2Name: Fire (post-release)

Tier1Name: System operating

Tier2Name: Pipe structural malfunction/failure

Finding Tier1Name: Organizational

Finding Tier2Name: Support/oversight/monitoring

Finding Tier3Name: Safety programs

Finding Modifier Name: Pipeline operator

Finding Report Text: Organizational - Support/oversight/monitoring - Safety programs - Pipeline operator

Official NTSB investigation data. NTSB findings determine probable cause and make safety recommendations; they do not adjudicate civil liability or regulatory violations.

What Happened
On May 4, 2020, about 4:36 p.m. local time, a 30-inch diameter interstate natural gas transmission pipeline owned and operated by Enbridge Inc. (Enbridge) ruptured about 3 miles east–northeast of Hillsboro, Kentucky, resulting in a fire. [1] The rupture occurred on Line 10 at a hillside location that was previously identified by Enbridge for geotechnical monitoring because of an active landslide.[2]

Line 10 was the northernmost of three parallel pipelines—Lines 10, 15, and 25—along the same right-of-way. At the time of the rupture, Line 10’s operating pressure was about 674 pounds per square inch, gauge.[3] The rupture occurred at a girth weld at an elevation of about 923 feet.[4] There were no fatalities or injuries, and Enbridge estimated the cost of property damage and emergency response at $11.7 million.

(a) For more detailed information about this investigation, see the public docket and search for number PLD20LR001. Use the CAROL Query to search safety recommendations and investigations. (b) All times in this report are local time unless otherwise noted.

The rupture occurred on a Texas Eastern Transmission, Limited Partnership, pipeline. Texas Eastern Transmission is an indirect, 100-percent-owned subsidiary of Enbridge Inc.

The maximum allowable operating pressure of the pipeline was 936 pounds per square inch, gauge.

A girth weld is used to join two pipes along their circumference. The girth weld that ruptured had been hydrostatically tested before the pipeline’s initial service in 1952 and retested in 1986; a hydrostatic test involves filling the pipeline with water at a predetermined pressure to test the pipeline’s integrity.

What We Found
We determined that the probable cause of the pipeline rupture was Enbridge Inc.’s analysis of an active landslide that did not fully address uncertainties associated with pipeline defects, landslide movement, and corresponding pipeline response.

PIR-22-01
<<<PAGE 1>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
Issued: May 31, 2022 Pipeline Investigation Report: PIR-22/01
Enbridge Inc. Natural Gas Pipeline Rupture
Hillsboro, Kentucky
May 4, 2020
Figure 1. Ruptured pipeline. (Source: BGC
Engineering USA, Inc.)
1. Factual Information
1.1 Accident Summary
On May 4, 2020, about 4:36 p.m.
local time, a 30-inch diameter interstate
natural gas transmission pipeline owned
and operated by Enbridge Inc. (Enbridge)
ruptured about 3 miles east–northeast of
Hillsboro, Kentucky, resulting in a fire.
1 (See
figure 1.) The rupture occurred on Line 10
at a hillside location that was previously
identified by Enbridge for geotechnical
monitoring because of an active landslide.2
Line 10 was the northernmost of
three parallel pipelines—Lines 10, 15 and
25—along the same right-of-way. At the
time of the rupture, Line 10’s operating
pressure was about 674 pounds per
square inch, gauge.
3 The rupture occurred
at a girth weld at an elevation of about 923
1 (a) For more detailed information about this investigation, see the public docket and search for
number PLD20LR001. Use the CAROL Query to search safety recommendations and investigations. (b) All
times in this report are local time unless otherwise noted.
2 The rupture occurred on a Texas Eastern Transmission, Limited Partnership, pipeline. Texas
Eastern Transmission is an indirect, 100-percent-owned subsidiary of Enbridge Inc.
3 The maximum allowable operating pressure of the pipeline was 936 pounds per square inch, gauge.
1

<<<PAGE 2>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
feet.4 There were no fatalities or injuries, and Enbridge estimated the cost of property
damage and emergency response at $11.7 million.
1.2 Integrity Management
In the years before the rupture, several indications were available to Enbridge that
Line 10 was exposed to external loads (loads transmitted to a pipeline from an external
source):
• Results of an April 17, 2018, in-line inspection (ILI) indicated pipeline
movement of about 4.2 feet.5
• On October 9, 2018, Enbridge identified the rupture location as a potential
geohazard.
• On April 16, 2019, an aerial patrol observed erosion on the right-of-way near
the rupture location.
• Results of a June 7, 2019, ILI indicated pipeline movement of about 5.2 feet.
• A July 8, 2019, ground inspection identified scarps.
6
In 2019 and 2020, Enbridge evaluated Line 10 for geohazard threats. After a site
assessment in October 2019 and analysis comparing the strain exerted on the pipeline
(tensile strain demand) to the strain capacity of the pipeline (tensile strain capacity),
Enbridge determined that urgent action was not required but recommended monitoring
and mitigation of the identified threats.
7
In February 2020, Enbridge held a multidisciplinary review meeting to determine
the monitoring and mitigation plan for this location. Based on estimated tensile strain
demand and other geotechnical considerations, Enbridge planned to install strain
gauges and improve drainage. According to Enbridge, they also planned to complete
4 A girth weld is used to join two pipes along their circumference. The girth weld that ruptured had
been hydrostatically tested before the pipeline’s initial service in 1952 and retested in 1986; a hydrostatic
test involves filling the pipeline with water at a predetermined pressure to test the pipeline’s integrity.
5 In-line inspection is an internal pipeline inspection technique that uses magnetic flux leakage,
ultrasound, eddy current or other sensing technology to locate and characterize indications of defects, such
as metal loss or deformation in the pipeline.
6 A scarp is a steep surface of exposed material produced by differential, or non-uniform, ground
surface movement.
7 (a) The tensile strain demand is the amount of strain that is being exerted on the system or material,
whereas the tensile strain capacity is the amount of strain that the system or material can withstand; strain
can be expressed as a ratio or percentage. (b) Enbridge estimated a tensile strain demand of 0.6 percent
by adding the maximum bending strain at a girth weld to the estimated axial strain. (c) The tensile strain
capacity analysis assumed a flaw 2 inches in length and 0.0394 inches in depth. (d) After applying a safety
factor, Enbridge determined that the tensile strain capacity threshold was 1 percent for the girth welds.
2

<<<PAGE 3>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
additional monitoring, mitigation and stress relief in summer 2020. The rupture occurred
before the monitoring and mitigation activities were completed.
1.3 Postaccident
1.3.1 Postaccident Geotechnical Assessment
Following the rupture, a contractor directed by the National Transportation Safety
Board (NTSB) found that the area around the incident site was highly susceptible to
landslides and determined that Line 10 was situated in past landslide deposits at the
rupture location. The contractor concluded that Line 10 was installed within a landslide
feature that was accelerating, causing a rapid increase in strain on the pipeline before
the rupture. The contractor indicated that landslide acceleration in the 6 months before
the rupture was likely driven by high levels of precipitation, pre-existing cracks in the soil,
ground water movement along the pipeline trenches, and loading from grading
activities.
1.3.2 Postaccident Metallurgical Testing and Tensile Strain Analysis
Other contractors directed by the NTSB evaluated the ruptured girth weld,
removed and evaluated exemplar girth welds, and estimated the tensile strain demand
and capacity. Two incomplete penetration and lack of root fusion defects were identified
on the fracture face of the ruptured girth weld.8 One defect was about 7 inches long and
0.13 inches deep. The other defect was about 4.9 inches long and 0.10 inches deep.
The objective of the tensile strain demand analysis was to estimate the strain on
the pipeline caused by land movement at the failure location. The results of the pre- and
post-rupture tensile strain demand analyses are shown in Table 1. The analyses assessed
overall performance and did not account for known defects.
8 (a) Incomplete penetration defects occur when the weld root is not completely filled. (b) Lack of root
fusion defects occur when the weld fails to fuse one side of the joint in the root. (c) The root is the point at
which the weld metal intersects the base metal and extends furthest into the weld joint.
3

<<<PAGE 4>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
Table 1. Estimated tensile strain demand
Pipeline
Configuration
Pre-Rupture Analyses
(Enbridge)
Post-Rupture
Analyses
(NTSB Investigation)
April 2018 N/A 1.8%
July 2019 0.6% N/A
May 2020 N/A 3.0%
Further, tensile strain capacity analysis was performed to determine the amount of
strain that a pipe section with a representative girth weld could withstand. The tensile
strain capacity was estimated by evaluating exemplar girth welds, fabricating and testing
material property samples, and developing a finite element model. The model used to
estimate tensile strain capacity explicitly included flaws found in the exemplar girth welds
that were up to 4 inches in length. The estimated tensile strain capacity was between 1.3
percent and 2 percent.
1.3.3 Postaccident Actions
1.3.3.1 Enbridge
Enbridge issued several new procedures for managing geohazards, including for
estimating tensile strain capacity, conducting multidisciplinary reviews, and determining
appropriate response actions. Enbridge reported that the new procedures would result
in a reduced tensile strain capacity threshold (0.5 percent) on Line 10 in the area where
the rupture occurred, which, given the information available before the incident, would
trigger a high-priority response action.9 Additionally, Enbridge acknowledged that the
pre-rupture strain demand methodology may have underestimated the actual strain
demand. Enbridge indicated that it would continue to work with its contractors to
determine whether a different method with an appropriate level of conservatism should
be applied.
1.3.3.2 Pipeline and Hazardous Materials Safety Administration
On June 1, 2020, the Pipeline and Hazardous Materials Safety Administration
(PHMSA) issued an amended Corrective Action Order to Enbridge that required
corrective actions be taken with respect to Lines 10, 15 and 25 for failures on August 1,
9 The high-priority response action requires a site visit within 48 hours, site-specific monitoring plan
within 30 days, immediate pressure reduction or shutdown, and drainage installation, if appropriate, for
site-specific conditions.
4

<<<PAGE 5>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
2019, near Danville, Kentucky, and May 4, 2020, near Hillsboro, Kentucky.10 The order
required Enbridge to reduce the operating pressure of the affected segment, review
prior ILI results, and review and assess its emergency response plans, operations, and
public awareness program. Further, on December 21, 2021, PHMSA issued a Notice of
Probable Violation, Proposed Civil Penalty, and Proposed Compliance Order to
Enbridge alleging probable violations related to the Hillsboro accident.
On May 26, 2022, PHMSA issued an advisory bulletin, citing the Hillsboro
accident among others, that reminds owners and operators of gas and hazardous liquid
pipelines of the potential for damage to pipeline facilities caused by earth movement in
variable, steep, and rugged terrain and for varied, changing subsurface geological
conditions. The bulletin states that changing weather patterns, including increased
rainfall and higher temperatures, can result in flooding, soil saturation, and erosion
impacting soil stability surrounding pipeline facilities. PHMSA’s advisory bulletin further
lists pipeline safety actions operators should consider to ensure pipeline safety.
11
2. Analysis
In 2018, Enbridge identified the rupture location as a potential geohazard. They
took action to analyze the active landslide and started taking steps to mitigate the hazard
before the rupture. However, Enbridge’s pre-rupture analysis estimated a girth weld
tensile strain demand that was at least three times lower than post-rupture analysis later
indicated. The post-rupture analysis demonstrated that in April 2018 or earlier Enbridge
could have foreseen the likelihood that the tensile strain demand would exceed the
strain capacity due to documented land movement at the site.
Like all analyses, tensile strain demand and capacity calculations include certain
modeling assumptions and associated uncertainties that must be considered in any
decision-making that relies on the results. Notably, Enbridge’s pre-rupture analyses did
not appropriately consider uncertainties such as weld defects, changes in the slope and
direction of the landslide that could increase the susceptibility of the girth welds to
fracture, acceleration of the landslide, or the response of the pipeline to these factors. As
10 The August 1, 2019, rupture that occurred near Danville, Kentucky, is currently under investigation by
the NTSB. Additional information can be found in the public docket for NTSB investigations (number
PLD19FR002) by accessing the NTSB Dockets Link at www.ntsb.gov.
11 The suggested actions include, but are not limited to, monitoring geological and environmental
conditions near facilities, including changing weather patterns; identifying areas surrounding pipelines that
may be prone to large earth movement; developing design, construction, and monitoring plans and
procedures and developing mitigation measures to remediate identified locations; and tracking changes in
ground conditions. For more information, see PHMSA Advisory Bulletin: Potential for Damage to Pipeline
Facilities Caused by Earth Movement and Other Geological Hazards,
https://www.phmsa.dot.gov/news/phmsa-advisory-bulletin-potential-damage-pipeline-facilities-caused-
earth-movement-and-other.
5

<<<PAGE 6>>>

Enbridge Inc. Natural Gas Pipeline Rupture
PIR-22/01
a result, Enbridge determined that no immediate action was needed to mitigate the
identified geohazard threat and therefore did not take necessary actions before the
rupture.
As a result of this accident, Enbridge issued new procedures for estimating tensile
strain capacity, conducting multidisciplinary reviews, and determining appropriate
response actions, reporting the new procedures would result in a reduced tensile strain
capacity threshold. Further, PHMSA took enforcement action against Enbridge. PHMSA
also issued an advisory bulletin on damage to pipeline facilities from earth movement in
rugged, steep terrain, citing the Hillsboro accident among recent land movement
events.
3. Probable Cause
The National Transportation Safety Board determines that the probable cause of
the pipeline rupture was Enbridge Inc.’s analysis of an active landslide that did not fully
address uncertainties associated with pipeline defects, landslide movement, and
corresponding pipeline response.
The National Transportation Safety Board (NTSB) is an independent federal agency dedicated to
promoting aviation, railroad, highway, marine, and pipeline safety. Established in 1967, the agency is
mandated by Congress through the Independent Safety Board Act of 1974, to investigate transportation
accidents, determine the probable causes of the accidents, issue safety recommendations, study
transportation safety issues, and evaluate the safety effectiveness of government agencies involved in
transportation. The NTSB makes public its actions and decisions through accident reports, safety studies,
special investigation reports, safety recommendations, and statistical reviews.
The NTSB does not assign fault or blame for an accident or incident; rather, as specified by NTSB
regulation, “accident/incident investigations are fact-finding proceedings with no formal issues and no
adverse parties … and are not conducted for the purpose of determining the rights or liabilities of any
person” (Title 49 Code of Federal Regulations section 831.4). Assignment of fault or legal liability is not
relevant to the NTSB’s statutory mission to improve transportation safety by investigating accidents and
incidents and issuing safety recommendations. In addition, statutory language prohibits the admission into
evidence or use of any part of an NTSB report related to an accident in a civil action for damages resulting
from a matter mentioned in the report (Title 49 United States Code section 1154(b)).
For more detailed background information on this report, visit the NTSB investigations website and
search for NTSB accident ID PLD20LR001. Recent publications are available in their entirety on the NTSB
website. Other information about available publications also may be obtained from the website or by
contacting—
National Transportation Safety Board
Records Management Division, CIO-40
490 L’Enfant Plaza, SW
Washington, DC 20594
(800) 877-6799 or (202) 314-6551
6
- **truncated:** false
- **body characters:** 18296