# Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release

- **operation:** document
- **citation:** PLD22FR002
- **title:** Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
- **source type:** incident
- **agency:** National Transportation Safety Board
- **status:** current
- **official:** true
- **published on:** 2024-01-02
- **effective on:** 2022-03-11
- **summary:** Accident. in Edwardsville, IL, USA. on 2022-03-11. Marathon Pipe Line LLC. Rupture/release
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/ntsb-case-pld22fr002.json
- **markdown:** https://regulus.evalyn.ai/document/ntsb-case-pld22fr002.md
- **app url:** https://regulus.evalyn.ai/document/ntsb-case-pld22fr002
- **source url:** https://www.ntsb.gov/investigations/Pages/PLD22FR002.aspx
**body:**

NTSB investigation PLD22FR002.

Event Type: Accident

Event Date: 2022-03-11

Event City: Edwardsville

Event State Or Region: IL

Event Country: USA

Pipeline Operator: Marathon Pipe Line LLC

Pipeline Type: Hazardous Liquid - Regulated

Accident Type: Rupture/release

Completion Status: Completed

Report Number: 2302

Report Date: 2023-12-18

Probable cause: The National Transportation Safety Board determines that the probable cause of the Edwardsville, Illinois, crude oil pipeline rupture was an overstress fracture of a girth weld from external loads caused by slope instability that had not been completely mitigated by Marathon before the accident.

Tier1Name: System operating

Tier2Name: Emergency shutoff

Tier1Name: System shutdown

Tier2Name: Emergency response

Tier1Name: System operating

Tier2Name: SCADA system event

Tier1Name: System operating

Tier2Name: Product leak/release

Finding Tier1Name: Pipeline

Finding Tier2Name: Pipeline structure

Finding Tier3Name: Joint/weld/seam

Finding Modifier Name: Failure

Finding Report Text: Pipeline - Pipeline structure - Joint/weld/seam - Failure

Finding Tier1Name: Environment/Infrastructure

Finding Tier2Name: Physical environment

Finding Tier3Name: Soil

Finding Modifier Name: Awareness of condition

Finding Report Text: Environment/Infrastructure - Physical environment - Soil - Awareness of condition

Official NTSB investigation data. NTSB findings determine probable cause and make safety recommendations; they do not adjudicate civil liability or regulatory violations.

What Happened
On March 11, 2022, at 8:15:21 a.m. local time, a 22-inch diameter crude oil pipeline operated by Marathon Pipe Line, LLC ruptured at a girth weld in Edwardsville, Illinois, resulting in the release of about 3,500 barrels of crude oil, some of which entered Cahokia Creek. The rupture occurred at milepost 6.2 on the Woodpat pipeline, and no injuries or fatalities occurred as a result of the rupture.

What We Found
We determined that the probable cause of the Edwardsville, Illinois, crude oil pipeline rupture was an overstress fracture of a girth weld from external loads caused by slope instability that had not been completely mitigated by Marathon before the accident.

PIR-23-02
<<<PAGE 1>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
Issued: December 18, 2023 Pipeline Investigation Report: PIR-23-02
Marathon Pipe Line LLC Pipeline Rupture
and Crude Oil Release
Edwardsville, Illinois
March 11, 2022
1 Factual Information
1.1 Accident Description
On March 11, 2022, at 8:15:21 a.m. local
time, a 22-inch diameter crude oil pipeline
operated by Marathon Pipe Line, LLC
(Marathon) ruptured at a girth weld in
Edwardsville, Illinois, resulting in the release of
about 3,500 barrels of crude oil, some of which
entered Cahokia Creek.1 (See figure 1.) The
rupture occurred at milepost 6.2 on the
Woodpat pipeline, the northernmost of three
parallel pipelines sharing one right-of-way and
the closest to the creek.2 Figure 2 shows the
alignment of Cahokia Creek, a tributary of the
Mississippi River. No injuries or fatalities
Figure 1. Ruptured pipeline and Cahokia
Creek. (Source: Marathon.)
1 (a) Visit www.ntsb.gov to find additional information in the public docket for this NTSB accident
investigation (case number PLD22FR002). Use the CAROL Query to search safety recommendations and
investigations. (b) All times in this report are local time unless otherwise noted. (c) A girth weld joins two
pipes along their circumference.
2 A milepost is a unit of measure used to define the location on a pipeline relative to a chosen starting
point in miles and fractions of miles.
1

<<<PAGE 2>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
occurred as a result of the rupture. Marathon estimated the cost of property damage and
emergency response to be $21,807,059.
Figure 2. Cahokia Creek and Mississippi River.
The Woodpat pipeline is operated from Marathon’s Pipeline Operations Center
(POC) in Findlay, Ohio, and is monitored and controlled by a supervisory control and
data acquisition system.3 The pipeline’s operating pressure at the time of failure was 467
pounds per square inch, gauge.
4 Additional pipeline specifications are presented in
table 1.
3 (a) Marathon’s POC monitors and controls the Marathon pipeline network 24 hours a day, 7 days a
week. (b) Supervisory control and data acquisition is a computer system used by operations centers to
gather and analyze real-time data.
4 The maximum operating pressure of the pipeline was 881 pounds per square inch, gauge.
2

<<<PAGE 3>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
Table 1. Woodpat pipeline specifications.
Pipeline Specification Value
Material Steel
Grade1 API-5L-X46
Longitudinal Seam Weld Low-frequency electric resistance welded
Wall Thickness 0.344 inch
Manufacturer Youngstown Sheet & Tube
Year Installed 1949
Flow Direction West to east
External Coating Type Coal tar enamel
Cathodic Protection Method Impressed current
1 American Petroleum Institute 5LX defines specific grades of carbon steel pipeline, each with a minimum yield strength.
The higher the grade of the pipeline, the higher the strength of the steel used to manufacture that pipeline.
About 8:15 a.m. on March 11, a rate-of-change alarm at Marathon’s POC showed
low suction pressure at the Roxana pump station, about 6 miles upstream of the rupture
site.
5 A 55-mile segment of the Woodpat pipeline was isolated at 8:23:18 a.m.6 Field
personnel identified the origin of the rupture at the girth weld about 9:51 a.m., and the
mainline block valves nearest the rupture location were closed about 10:07 a.m. to
reduce the length of the isolated pipeline segment to about 27 miles.
7
1.2 Emergency Response
Marathon deployed both internal and contracted oil spill removal organizations
(OSROs), which brought oil containment and recovery equipment to control the release
of oil and prevent it from traveling further downstream.8 The OSROs arrived at the
rupture location by 10:50 a.m. on March 11.
By the evening of March 12, Marathon had established 10 oil spill containment
sites along Cahokia Creek. Each of these sites were equipped with containment booms
5 Pump stations are positioned at various points to move product along the pipeline. The suction side
of a pump station is the lower-pressure input side.
6 When a segment of pipeline is isolated, valves are closed to halt the flow of product.
7 Mainline block valves are closed to isolate a pipeline segment.
8 US Environmental Protection Agency. 2022. Polrep #1: Initial Marathon Pipeline Release Wood River
to Patoka System.
3

<<<PAGE 4>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
and vacuum trucks.
9 No impacts on downstream potable water sources on the
Mississippi River were documented. In the area of the rupture, the OSROs dug an
interceptor trench, contained the oil-contaminated soil, and removed pooled oil.10
Recovered oil and contaminated water were temporarily stored in the vacuum trucks and
in portable frac tanks stationed near the accident site.
11 The OSROs took recovered
liquids to Marathon’s Wood River Station to separate the oil from the creek water and to
measure the recovery amounts.12
By April 1, 2022, the most severely contaminated soil had been removed from the
excavated area around the pipeline. In coordination with the Illinois Environmental
Protection Agency, Marathon conducted soil sample testing to determine the extent of
the soil contamination.
13 After testing and removal of contaminated soil, the pipeline was
backfilled with clean soil from an off-site source.
1.3 Integrity Management
In the years leading up to the accident, Marathon assessed the threat of external
loads on the Woodpat pipeline and took the below actions to address slope stability
issues near the accident location.
14
9 (a) A containment boom is a temporary floating barrier used to contain an oil spill. (b) Vacuum trucks
are used during a crude oil spill response to suction oil from surfaces.
10 An interceptor trench acts as a catchment area to prevent contaminants from spreading.
11 A frac tank is a large portable container used for temporary storage and separation of liquids such as
oil/water mixtures.
12 Marathon reported that the total recovered amount of oil (free oil plus oil recovered from solid
waste) was 3,362 barrels.
13 According to Marathon’s pipeline corridor soil sampling plan, soil sample testing was to be
conducted until the oil was not detectable by sight or smell and photoionization detector readings were
less than 50 parts per million. See Antea Group, 2022, Marathon Pipe Line LLC (MPL) Edwardsville
Response: Pipeline Corridor Soil Sampling Plan.
14 External loads are loads transmitted to a pipeline from an external source; for example, those
imposed by land movement.
4

<<<PAGE 5>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
• August 21, 2012: A caliper/inertial measurement unit (IMU) assessment for
mechanical damage and geometric anomalies was conducted.
15
• 2014: Concrete revetment mats were installed along the Cahokia Creek
bank to protect the pipeline from erosion found in 2012.16
• 2017: The revetment mats installed in 2014 were repaired, and additional
mats and riprap were installed.17
• January 5, 2018: A caliper/IMU assessment and bending strain analysis
found 18 areas with total bending strains of more than 0.125 percent—the
highest of which (0.34 percent) was near the rupture location.
18
Recommended mitigation efforts included in-situ strain monitoring, finite
element assessments, stress relief, further IMU assessments, pipeline
movement assessments, and pipeline replacement.19
• July 7, 2021: An investigation, completed in response to the 2018 IMU
assessment, indicated the left bank of Cahokia Creek was eroded, with
evidence of slope instability including recent failures, scarps, and
cracking.20 This investigation recommended increased monitoring of bank
instability, repeat depth-of-cover surveys, and additional reinforcement of
the bank. Based on this investigation, Marathon planned on conducting a
bending strain and pipeline movement analysis in 2022, but that was not
completed before the rupture occurred.
15 An IMU assessment provides mapping information that is aligned with in-line inspection tools to
locate pipeline anomalies, features, and fittings. Data from an IMU assessment can be used to calculate
curvature along a pipeline. See General Electric, 2012, Excerpt from circumferential magnetic flux leakage
final report.
16 Concrete revetment mats consist of flexible concrete connected by fiber rope and are used for
erosion control.
17 Riprap is piled or stacked rocks used for erosion control.
18 Bending strain, the change in pipeline length over original length caused by bending deformation, is
a common indicator of surrounding ground movement. See Rosen, 2019, Bending Strain Report: Marathon
Petroleum, 22” Crude Oil Pipeline Roxanna to Patoka Woodpat, January 2018.
19 A finite element assessment is the use of calculations, models, and simulations to predict and
understand the behavior of an object or structure under various physical conditions.
20 A scarp is a long, steep slope or cliff at the edge of a plateau or ridge, usually formed by erosion. See
GeoMorphic Solutions, 2021, Strain Investigation Feature No. 25 WPAT 22-inch ROW 15 Strain Investigation
Study.
5

<<<PAGE 6>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
• August 31, 2021: Another caliper/IMU assessment was completed. As of
the date of the accident, Marathon had not requested the strain report from
this assessment.
1.4 Postaccident Assessment and Testing
1.4.1 Geotechnical Assessment
After the accident, a hydrotechnical analysis and slope stability assessment
determined the earth movement at the rupture location was due to scouring in the creek
that was localized on the bank near the rupture location because of large, woody
debris.21 The assessment determined that the slope instability had continued after the
revetment mats and riprap were installed in 2014 and 2017.
1.4.2 Metallurgical Testing
While on scene, the National Transportation Safety Board (NTSB) observed
complete circumferential separation at a girth weld at the rupture origin. The NTSB
retained three sections of the Woodpat pipeline for metallurgical testing, which was
completed by a third-party contractor directed by the NTSB.
22 Inspections of the
fractured girth weld revealed weld defects. Scanning electron microscopy was
performed on the fracture features of the girth weld, and those features exhibited
characteristics consistent with overstress fracture.23
1.4.3 GPS Survey
The day after the rupture, Marathon performed GPS surveys of the Woodpat
pipeline after the rupture. Figure 3 displays the results from the 2022 GPS surveys (green
dotted line) with data from the IMUs conducted in 2018 (blue line) and 2021 (yellow
line).
21 Scouring is the removal of sediment from streambeds and streambanks by moving water. See
Geosyntec, 2022, Memorandum Addressing Cause of Ground Movement Edwardsville, Illinois.
22 One section came from the upstream side of the ruptured girth weld, including the upstream
fracture face; one came from the downstream side, including the downstream fracture face; and one
encompassed the next upstream girth weld, as an exemplar sample.
23 Scanning electron microscopy is used to obtain high-resolution images of pipe surfaces, particularly
of fracture surfaces, cracks, and other defects. See the NTSB Materials Laboratory Factual Report contained
in the docket for this investigation for further details.
6

<<<PAGE 7>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
Figure 3. IMU data for Woodpat pipeline from 2018 and 2021 and 2022 postaccident GPS
survey.
1.4.4 Failure Analysis
Marathon performed a failure analysis on the ruptured girth weld using the 2012,
2018, and 2021 IMU assessments. As part of the failure analysis, Marathon completed a
numerical analysis using calibrated models established by the 2018 and 2021 IMU data
and postaccident data to conduct a strain analysis and collect deviation-from-straight
values.
24 (See table 2.) The failure analysis indicated increased strain approximately 10
24 Marathon did not calculate deviation-from-straight values at the time of the 2018 and 2021 IMU
assessments.
7

<<<PAGE 8>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
feet from the rupture location, with maximum total strain near the ruptured girth weld
between 0.61 and 0.83 percent, and a deviation-from-straight value of just over 8 feet.
25
Table 2. Analysis of 2018 and 2021 IMU data and 2022 postaccident data.
Date Maximum Combined
Bending Strain (%)
Bending Strain near Girth
Horizontal Deviation from
Weld (%)
Straight1
2018 0.34 0.02 5.7 feet
2021 0.41 0.25 8 feet
2022
— 0.42 (estimated) 8.2 feet
(time of rupture)
1 These values were calculated in the postaccident numerical analysis.
1.5 Postaccident Actions
1.5.1 Marathon Pipeline LLC
Following the rupture, Marathon conducted repairs and remediation activities. All
girth welds that had not been removed were examined using ultrasonic phased array
testing.
26 Marathon also reevaluated its integrity management program and
standardized its method of geohazard threat identification, increased the use of in-line
inspection to locate pipeline segments at risk from geohazards, expanded training for
controllers, introduced technologies to assist employees with identifying geohazards,
and contributed to research projects related to geohazards.
On March 14, 2022, Marathon sent the Pipeline and Hazardous Materials Safety
Administration (PHMSA) a commitment letter that included specific actions the company
would take in response to the rupture. This included performing fitness-for-service
calculations on the unearthed girth welds in the area of the rupture, reinforcing repairs to
girth welds that were exposed during postaccident response, conducting a geotechnical
analysis of the Cahokia Creek bank, completing site evaluations at locations on the
Woodpat pipeline at which increased strain had been identified, summarizing events
that would trigger mitigative action, and completing a strain analysis from the 2021
25 Maximum total strain is the maximum membrane strain within 10 feet of the girth weld plus the
maximum bending strain. Tensile strain capacity in this area was calculated to be 0.29 percent. See ADV
Integrity, Inc., 2023, Edwardsville Failure Analysis: Final Report.
26 Ultrasonic phased array testing is often conducted in the field to determine if there are any defects in
the weld.
8

<<<PAGE 9>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
in-line inspection.27 Marathon also updated its geohazard susceptibility criteria and
applied the criteria to all its pipelines.28
On March 15, 2022, Marathon installed about 60 feet of new pipe to replace the
sections that had been removed and restarted the pipeline at 7:31 a.m.
On April 5, 2022, Marathon led an operator-to-operator information sharing
webinar, supported by the NTSB and PHMSA, for approximately 900 attendees, that
addressed details of the incident, response, and initial lessons learned.
1.5.2 Pipeline and Hazardous Materials Safety Administration
PHMSA oversaw the implementation of the activities outlined by Marathon in its
commitment letter. In June 2022, PHMSA published an advisory bulletin reminding the
pipeline industry of the threat of earth movement and for pipeline operators to monitor
and mitigate threats to pipeline integrity.29 In December 2022, PHMSA held a public
meeting reviewing recent geohazard failures including the Edwardsville rupture.
2 Analysis
In this accident, a 22-inch diameter crude oil pipeline operated by Marathon
ruptured at a girth weld in Edwardsville, Illinois, resulting in the release of about 3,500
barrels of crude oil, some of which entered Cahokia Creek. The NTSB’s postaccident
laboratory testing of the ruptured sections of pipe showed that the girth weld had
experienced an overstress fracture. A review of records showed that Marathon had
documented multiple indications of slope instability near the rupture location dating
back to 2012, when an integrity assessment identified erosion along the Cahokia Creek
bank. In 2014, Marathon installed concrete revetment mats to stabilize the bank.
27 Fitness-for-service calculations are quantitative engineering evaluations, based on guidance
contained in American Petroleum Institute Recommended Practice 579, that assess the structural integrity
of in-service components that may contain a flaw or damage or that may be operating under a specific
condition that might cause a failure.
28 Marathon’s revised geohazard assessment frequency is once a year for pipeline segments with
observed geohazard issues, every 3 years for segments determined to be susceptible to geohazards, and
every 5 years for segments designated for monitoring only.
29 For more information, see PHMSA Advisory Bulletin: Potential for Damage to Pipeline Facilities
Caused by Earth Movement and Other Geological Hazards. Also cited in the advisory bulletin was a 2020
pipeline rupture in Hillsboro, Kentucky. See NTSB, 2022, Enbridge Inc. Natural Gas Pipeline Rupture,
Hillsboro, Kentucky, May 4, 2020, NTSB/PIR-22-01.
9

<<<PAGE 10>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
In the years that followed, caliper/IMU assessments, strain analyses, and risk
assessments indicated that the site of the rupture continued to experience slope
instability and that further reinforcement of the creek bank was necessary. In 2017,
Marathon repaired previously installed revetment mats and added more mats and
riprap. However, postaccident analyses reviewed and conducted by the NTSB showed
that these actions, as well as Marathon’s actions in 2014, were ineffective in completely
protecting the pipeline from external loads that were due to slope instability. Marathon
did not take further action to stabilize the creek bank after 2017.
Although Marathon conducted IMU assessments in 2018 and 2021, it did not
deploy the strain monitoring recommended by the 2018 IMU assessment and bending
strain analysis, nor did it pursue finite element assessments, stress relief, pipeline
movement assessments, or pipeline replacement before the accident. Finite element
assessments would have facilitated a more-accurate assessment of the strain on the
pipeline and would have allowed Marathon to better foresee the pending safety issues
related to slope instability and deploy better strain mitigations that could have
prevented the rupture.
Further, a 2021 strain investigation, also based on the 2018 IMU data, indicated
that slope instability was still present and recommended monitoring and bank
reinforcement, but Marathon did not do this by the time of the accident. Marathon had
planned to conduct a bending strain and pipeline movement analysis in 2022, but the
rupture preceded such action.
As a result of this accident, Marathon revised its total bending strain action limits
to be more stringent, facilitating additional site investigations and remediation projects
for locations that could be at risk of geohazard-related damage. The company also
amended its geohazard assessment frequency, began collecting deviation-from-straight
values to analyze bending strain features, expanded methods to proactively identify
geohazard threats, and formalized the protocol to calculate total strain demand on
pipelines from strain features.
After the accident, PHMSA issued an advisory bulletin on damage to pipeline
facilities from earth movement and conducted a public meeting to discuss the
prevention of geohazard accidents. Marathon conducted a widely attended information-
sharing event on lessons learned from the rupture, supported by the NTSB and PHMSA.
3 Probable Cause
The National Transportation Safety Board determines that the probable cause of
the Edwardsville, Illinois, crude oil pipeline rupture was an overstress fracture of a girth
weld from external loads caused by slope instability that had not been completely
mitigated by Marathon before the accident.
10

<<<PAGE 11>>>

Marathon Pipe Line LLC Pipeline Rupture and Crude Oil Release
PIR-23-02
The NTSB is an independent federal agency charged by Congress with
investigating every civil aviation accident in the United States and significant events in the
other modes of transportation—railroad, transit, highway, marine, pipeline, and
commercial space. We determine the probable causes of the accidents and events we
investigate and issue safety recommendations aimed at preventing future occurrences. In
addition, we conduct transportation safety research studies and offer information and
other assistance to family members and survivors for each accident or event we
investigate. We also serve as the appellate authority for enforcement actions involving
aviation and mariner certificates issued by the Federal Aviation Administration (FAA) and
US Coast Guard, and we adjudicate appeals of civil penalty actions taken by the FAA.
The NTSB does not assign fault or blame for an accident or incident; rather, as
specified by NTSB regulation, “accident/incident investigations are fact-finding
proceedings with no formal issues and no adverse parties … and are not conducted for
the purpose of determining the rights or liabilities of any person” (Title 49 Code of
Federal Regulations section 831.4). Assignment of fault or legal liability is not relevant to
the NTSB’s statutory mission to improve transportation safety by investigating accidents
and incidents and issuing safety recommendations. In addition, statutory language
prohibits the admission into evidence or use of any part of an NTSB report related to an
accident in a civil action for damages resulting from a matter mentioned in the report
(Title 49 United States Code section 1154(b)).
For more detailed background information on this report, visit the NTSB Case
Analysis and Reporting Online (CAROL) website and search for NTSB accident ID
PLD22FR002. Recent publications are available in their entirety on the NTSB website.
Other information about available publications also may be obtained from the website or
by contacting —
National Transportation Safety Board
Records Management Division, CIO-40
490 L’Enfant Plaza, SW
Washington, DC 20594
(800) 877-6799 or (202) 314-6551
11
- **truncated:** false
- **body characters:** 24639
