{"operation":"document","citation":"P-82-001","title":"NTSB Safety Recommendation P-82-001","source_type":"guidance","agency":"National Transportation Safety Board","status":"guidance","official":true,"published_on":"1982-04-16","effective_on":"1982-04-16","summary":"AS A RESULT OF ITS INVESTIGATION OF THIS ACCIDENT, THE NTSB RECOMMENDS THAT THE PACIFIC GAS AND ELECTRIC COMPANY: TRAIN AND EQUIP COMPANY PERSONNEL WHO RESPOND TO EMERGENCY CONDITIONS IN THE OPERATION OF EMERGENCY SHUTDOWN VALVES.","machine_formats":{"json":"https://regulus.evalyn.ai/document/ntsb-recommendation-p-82-001.json","markdown":"https://regulus.evalyn.ai/document/ntsb-recommendation-p-82-001.md"},"app_url":"https://regulus.evalyn.ai/document/ntsb-recommendation-p-82-001","source_url":"https://data.ntsb.gov/carol-main-public/sr-details/P-82-001","body":"NTSB safety recommendation P-82-001.\n\nAS A RESULT OF ITS INVESTIGATION OF THIS ACCIDENT, THE NTSB RECOMMENDS THAT THE PACIFIC GAS AND ELECTRIC COMPANY: TRAIN AND EQUIP COMPANY PERSONNEL WHO RESPOND TO EMERGENCY CONDITIONS IN THE OPERATION OF EMERGENCY SHUTDOWN VALVES.\n\nPriority: CLASS II\n\nOverall Status: Closed - Acceptable Action\n\nIssued Date: 1982-04-16\n\nAdopted Date: 1982-02-25\n\nOverall Date Closed: 1982-08-31\n\nSynopsis: ON AUGUST 25, 1981, IN DOWNTOWN SAN FRANCISCO, CALIFORNIA, A 16-INCH NATURAL GAS MAIN OWNED BY THE PACIFIC GAS AND ELECTRIC COMPANY (PG & E) WAS PUNCTURED BY A DRILL THAT AN EXCAVATION CONTRACTOR WAS USING TO SET TIEBACKS FOR ANCHORING HIS EXCAVATION SHORING. ESCAPING NATURAL GAS BLEW UPWARD AND CARRIED INTO THE EMBARCADERO COMPLEX AND OTHER NEARBY BUILDINGS. THERE WAS NO IGNITION; HOWEVER, THE GAS STREAM ENTRAINED AN OIL CONTAINING POLYCHLORINATED BIPHENYL (PCB). FALL-OUT AFFECTED AN EIGHT-SQUARE-BLOCK AREA OF THE CITY'S FINANCIAL DISTRICT COVERING BUILDINGS, CARS, TREES, PEDESTRIANS, POLICE, AND FIREMEN. APPROXIMATELY 30,000 PERSONS WERE SAFELY EVACUATED FROM THE AREA IN 45 MINUTES. NO ONE WAS KILLED OR SERIOUSLY INJURED, ALTHOUGH MANY PERSONS WERE SPRAYED WITH THE PCB OIL MIST.\n\nProbable Cause: None\n\nNtsbnumber: DCA81MP020\n\nReport Number: PAR-82-01\n\nAddressee Name: Pacific Gas and Electric Company\n\nAddressee Status: Closed - Acceptable Action\n\nAddressee Date Closed: 1982-08-31\n\nAddressee Acronym: PG&E\n\nAddressee Organization Type: P-Private Industry\n\nCommunication Date: 1982-08-31\n\nCommunication Type: Official Correspondence\n\nCommunication Contents: We have reviewed your June 21, 1982, response to the National Transportation Safety Board's Safety Recommendations P-82-1, -2, and -3 which were issued as a result of our investigation of the natural gas leak at a construction site in San Francisco, California on August 25, 1981. The Board is pleased that, as a result of problems identified during this accident, emergency response training has been intensified at your company with special attention being given to locating and operating emergency shutdown valves. Based on this information, we have placed P-82-l in a \"Closed-Acceptable Action\" status. We would appreciate receiving an outline of the training program described. The effort to update and verify emergency shutdown diagrams and to inspect such valves twice annually is acceptable in fulfilling the intent of P-82-2. We have placed this recommendation in a \"Closed-Acceptable Action\" status. Your new standard on servicing and lubrication of valves along with the two letters to division gas superintendents dated September 3, 1981, and November 20, 1981, are·acceptable in fulfilling the intent of P-82-3. This safety recommendation has been classified as \"Closed-Acceptable Action.\" We would appreciate receiving a copy of the new standards as well as copies of the two letters mentioned. Your comments concerning the rapidity of system shutdown during the accident have been placed in the docket for this accident and will be considered a part of the public record. We appreciate the time and effort you have spent in reviewing and acting upon our recommendations.\n\nAddressee Acronym: PG&E\n\nAddressee Organization Type: P-Private Industry\n\nCommunication Date: 1983-01-19\n\nCommunication Type: Official Correspondence\n\nCommunication Contents: Thank you for your October 5, 1982, letter providing further information we requested in our August 31, 1982, letter concerning the National Transportation Safety Board's Safety Recommendations P-82-1, -2, and -3 which stemmed from the pipeline accident in San Francisco on August 25, 1981. We appreciate the additional information provided as requested in our August 31, 1982, letter. Your cooperation in implementing our recommendations is appreciated.\n\nAddressee Acronym: PG&E\n\nAddressee Organization Type: P-Private Industry\n\nCommunication Date: 1982-06-21\n\nCommunication Type: Official Correspondence\n\nCommunication Contents: -From Howard M. McKinley, Vice President, Gas Operations: Emergency response training for PG and E employees has been, and will continue to be, an ongoing program. As a result of problems which became apparent during the August 25, 1981 incident, a plan was initiated in early September 1981, to intensify this training. This program was conducted in San Francisco, as well as in the other twelve operating divisions of the company, and the Pipe Line Operations Department which operates the major transmission lines. To meet the specific recommendation in P-82-1, special attention is being directed to training in the locating and operation of emergency shutdown valves. Additional valve keys are also being provided to crews who could be called upon in an emergency. This training will be completed by July 15, 1982.\n\nAddressee Acronym: PG&E\n\nAddressee Organization Type: P-Private Industry\n\nCommunication Date: 1982-10-05\n\nCommunication Type: Official Correspondence\n\nCommunication Contents: -From Howard M. McKinley, Vice President, Gas Operations: This letter is in response to your August 31, 1982 letter concerning the National Transportation Safety Board recommendations P-82-1, 2, and .3. we are pleased that the action taken by Pacific Gas and Electric Company (PG and E) subsequent to the August 25, 1981 incident was satisfactory, and that these three recommendations now have a Closed-Acceptable Action status. In conjunction with your comments on the additional training recommended in P-82-1, you requested an outline of the training program described in our June 21, 1982 letter. We have attached a copy of the Employee Training Program section of the PGandE Gas Department Emergency Plan. This is the outline which must be followed by each of the thirteen operating divisions when developing an emergency training program to meet the requirements of its specific area. As indicated in our June 21, 1982 letter, this normal training program had been intensified from September 1981 to June 1982. Specifically, this program provided for over one thousand man-hours of additional time spent on emergency shutdown training and exercises, and was directed toward local gas operating supervisors, engineers, and mechanics. These people were required to review and study all the emergency shutdown references pertaining to their systems and to inspect each valve. Supervisors from our General Office visited the division and district offices providing direction where required and, by conducting performance tests, verified that the training objectives were being attained. The objectives included a thirty-minute limit for formulating an effective shutdown plan for a randomly chosen section of pipeline or main, and then a faultless execution of the plan. Visits were repeated as required for assurance of competency. Copies of the September 3, 1981 and November 20, 1981 letters to the division gas superintendents concerning emergency shutdown valves and a copy of Gas Standard F-11, Valve Lubrication and Maintenance Requirements, are also enclosed, as requested in your letter. With respect to other recommendations made in NTSB-PAR-82-1, California has recently passed legislation (Assembly Bill No. 3019) signed into law on September 29, 1982, which requires that every owner of a subsurface installation, except the Department of Transportation, must become a member of and participate in a regional notification center. It further states that no excavation permit issued by any local agency shall be valid unless it has an identification number indicating that the regional notification center has been notified of the proposed excavation work. I am confident that positive actions taken by PG and E since the August 25, 1981 incident and the recently passed legislation on notification centers and permits reduce the chances of future similar dig-ins.","truncated":false,"body_characters":7865}