{"operation":"document","citation":"16 NYCRR 258.13","title":"258.13 Report of specifications for proposed construction.","source_type":"regulation","agency":"New York State Public Service Commission","status":"current","official":true,"published_on":null,"effective_on":null,"summary":"Transportation of Liquid Petroleum (Hazardous Liquid Pipelines). (a) The following maps, sketches, and drawings shall be filed with and as a part of the report of specifications:\n\n(1) three sets of current U.S. Geological Survey Maps (7½ or 15 minute) clearly indicating the entire route of the proposed construction or reconstruction and an area of one mile on either side of the route; and\n\n(2) three sets of strip maps and","machine_formats":{"json":"https://regulus.evalyn.ai/document/ny-nycrr-258-13.json","markdown":"https://regulus.evalyn.ai/document/ny-nycrr-258-13.md"},"app_url":"https://regulus.evalyn.ai/document/ny-nycrr-258-13","source_url":"https://govt.westlaw.com/nycrr/Document/I505e1da3cd1711dda432a117e6e0f345?viewType=FullText&originationContext=documenttoc&transitionType=CategoryPageItem&contextData=(sc.Default)","body":"(a) The following maps, sketches, and drawings shall be filed with and as a part of the report of specifications:\n\n(1) three sets of current U.S. Geological Survey Maps (7½ or 15 minute) clearly indicating the entire route of the proposed construction or reconstruction and an area of one mile on either side of the route; and\n\n(2) three sets of strip maps and design drawings showing details of the proposed construction or reconstruction.\n\n(b) A report of specifications identical in format with subdivision (c) of this section shall be submitted in triplicate. Where additional space is necessary, supply the requested information on attached sheets.\n\nSTATE OF NEW YORK\n\nDEPARTMENT OF PUBLIC SERVICE\n\nREPORT OF SPECIFICATIONS FOR PROPOSED CONSTRUCTION\n\nLIQUID PETROLEUM PIPELINE FACILITIES\n\nGeneral Information\n\nGeneral Information\n\n1. Corporation name Date ________\n\n2. Pipeline route:\n\n2. Pipeline route:\n\nFrom\n\nTo\n\n3. Length\n\n4. New construction or reconstruction\n\n5. Counties traversed\n\n6. Towns traversed\n\n7. Cities traversed\n\n8. Villages traversed\n\n9. Estimated starting date\n\n10. Estimated completion date\n\n11. Pipeline identification name or number\n\nPipe Specifications\n\nPipe Specifications\n\n1. Nominal outside diameter, D (inches)\n\n2. Nominal wall thickness, t (inches)\n\n3. Type and/or grade of pipe\n\n4. Manufacturer of steel\n\n5. Manufacturer of pipe\n\n6. Longitudinal joint type\n\n7. Specified minimum yield strength, SMYS (psi)\n\n8. Nominal ultimate strength (psi)\n\n9. Fracture toughness (minimum Charpy Energy in ft. lbs. at 20°F for buried pipe, −20°F for exposed pipe)\n\n10. Mill test pressure (psi)\n\n11. Is pipe new or used\n\n12. If used pipe is employed, describe inspection and reconditioning procedures\n\n13. Are the physical and chemical specifications of pipe to be verified by outside laboratories? If yes, by whom?\n\nOperating Pressure and Stress\n\nOperating Pressure and Stress\n\n1. Maximum operating pressure, P (psi)\n\n2. Calculated pipe stress (hoop stress) = PD/2t (psi)\n\n3. Ratio of pipe stress to SMYS (percent)\n\nWelding\n\nWelding\n\n1. Percentage of welds to be radiographed, by location\n\n2. How will the corporation certify the radiographic technician\n\nRailroad, Road, and Water Crossings\n\nRailroad, Road, and Water Crossings\n\n1. Railroad and road crossings:\n\n1. Railroad and road crossings:\n\nAttach a list giving the location of each and indicating whether each is cased or uncased (if uncased, provide reason), and if heavier wall carrier pipe is used.\n\nAttach a list giving the location of each and indicating whether each is cased or uncased (if uncased, provide reason), and if heavier wall carrier pipe is used.\n\n2. Lake, river, stream, or creek crossings:\n\n2. Lake, river, stream, or creek crossings:\n\nAttach a list giving the location of each and describing any special construction precautions to be followed.\n\nAttach a list giving the location of each and describing any special construction precautions to be followed.\n\n3. Pipeline encroachments:\n\n3. Pipeline encroachments:\n\nAttach a list of any encroachments to railroads or roads, by location, and describe any special construction precautions to be followed.\n\nAttach a list of any encroachments to railroads or roads, by location, and describe any special construction precautions to be followed.\n\nValves (see 49 CFR 195.260)\n\nValves (see 49 CFR 195.260)\n\n1. Number and spacing of manual sectionalizing valves\n\n2. Type, make, and location of any automatic valves to be used\n\nMinimum Cover and Clearance (see 49 CFR 195.248, 250)\n\nMinimum Cover and Clearance (see 49 CFR 195.248, 250)\n\nIf the minimum prescribed cover and/or clearance cannot be maintained, indicate the location, nature of problem, cover and/or clearance to be maintained, and any special precautions to be observed. Corrosion Control (see 49 CFR 195 Subpart H - Corrosion Control)\n\nIf the minimum prescribed cover and/or clearance cannot be maintained, indicate the location, nature of problem, cover and/or clearance to be maintained, and any special precautions to be observed. Corrosion Control (see 49 CFR 195 Subpart H - Corrosion Control)\n\n1. Type of field coating:\n\n1. Type of field coating:\n\nFor pipe (if not factory coated)\n\nFor welds and fittings\n\n2. Type of coating test:\n\n2. Type of coating test:\n\nBefore backfill\n\nAfter backfill\n\n3. Type of cathodic protection system\n\nPressure and Leakage Tests (see section 258.6 of this Part)\n\nPressure and Leakage Tests (see section 258.6 of this Part)\n\n1. Test pressure\n\n2. Test medium\n\n3. Test duration\n\n4. Length of test section(s)\n\nRight-of-Way\n\nRight-of-Way\n\n1. Has necessary right-of-way been obtained from each party having interest in the right-of-way? If not, what is the status?\n\n1. Has necessary right-of-way been obtained from each party having interest in the right-of-way? If not, what is the status?\n\n2. Have formal approval and all necessary permits been obtained from governmental agencies? If not, what is the status?\n\n2. Have formal approval and all necessary permits been obtained from governmental agencies? If not, what is the status?\n\nProducts Transported\n\nProducts Transported\n\nPipeline certified to transport the following liquid petroleum products:\n\nPipeline certified to transport the following liquid petroleum products:\n\n1.\n\n2.\n\n3.\n\n4.\n\n5.\n\nSignature of corporation officer\n\nSignature of corporation officer\n\nTitle\n\nTitle","truncated":false,"body_characters":5353}