# IMTT-PIPELINE — Notice of Amendment

- **operation:** document
- **citation:** CPF 120085007M
- **title:** IMTT-PIPELINE — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2008-10-03
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 191.15, 195.310(b)(10).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120085007m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120085007m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120085007m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120085007M
**body:**

Notice of Amendment involving IMTT-PIPELINE. PHMSA's enforcement data identifies the cited regulations as 191.15,  195.310(b)(10). The case was opened on 2008-10-03 and is reported as closed as of 2009-09-08. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120085007M_Notice of Amendment_10032008.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120085007M/120085007M_Notice%20of%20Amendment_10032008.pdf

120085007M_Notice of Amendment_10032008_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120085007M/120085007M_Notice%20of%20Amendment_10032008_text.pdf

120085007M_Notice of Amendment_10032008_text.pdf

NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
October 3, 2008
IMTT
Mr. Richard R. Fisette, Vice President
IMTT-Pipeline
250 E. 22nd St. P.O. Box 67
Bayonne, NJ 07002
CPF 1-2008-5007M
Dear Fisette:
On May 5-8, 2008, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected
your transmission pipeline in Bayonne, New Jersey.
On the basis of the inspection, PHMSA has identified the apparent inadequacies within
IMTT's plans or procedures, as described below:



1. §191.15 Transmission and gathering systems: Incident Report
§191.15(b) Where additional related information is obtained after a report
is submitted under paragraph (a) of this section, the operator shall make a
supplemental report as soon as practicable with a clear reference by date
and subject to the original report
IMTT - Pipeline procedures do not address filing a supplemental report, if needed,
in conjunction with filing original NRC reports.
2. §195.310 Records
§195.310(b)(10) Temperature of the test medium or pipe during the test period
Recording of temperature during a pipeline pressure test is not in IMTT -
Pipeline procedures. Temperatures are recorded on actual IMTT- Pipeline test reports.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.237. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document
you must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond
within 30 days of receipt of this Notice, this constitutes a waiver of your right to contest the
allegations in this Notice and authorizes the Associate Administrator for Pipeline Safety to
find facts as alleged in this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged
in this Notice, you may be ordered to amend your plans or procedures to correct the
inadequacies (49 C.F.R. § 190.237). If you are not contesting this Notice, we propose that
you submit your amended procedures to my office within 30 days of receipt of this Notice.
This period may be extended by written request for good cause. Once the inadequacies
identified herein have been addressed in your amended procedures, this enforcement action
will be closed.
In correspondence concerning this matter, please refer to CPF 1-2008-5007M and, for
each document you submit, please provide a copy in electronic format whenever
possible.
2



Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
3