# TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP) — Notice of Amendment

- **operation:** document
- **citation:** CPF 120111012M
- **title:** TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP) — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2011-06-13
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.225, 192.605(b)(1), 192.605(b)(2), 192.605(b)(3), 192.613(a), 192.615(a)(1), 192.615(a)(4), 192.615(a)(6), 192.615(a)(8).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120111012m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120111012m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120111012m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120111012M
**body:**

Notice of Amendment involving TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP). PHMSA's enforcement data identifies the cited regulations as 192.225,  192.605(b)(1),  192.605(b)(2),  192.605(b)(3),  192.613(a),  192.615(a)(1),  192.615(a)(4),  192.615(a)(6),  192.615(a)(8). The case was opened on 2011-06-13 and is reported as closed as of 2011-12-08. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120111012M_Closure Letter_12082011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_Closure%20Letter_12082011.pdf

120111012M_Closure Letter_12082011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_Closure%20Letter_12082011_text.pdf

120111012M_NOA_06132011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_NOA_06132011.pdf

120111012M_NOA_06132011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_NOA_06132011_text.pdf

120111012M_Operator Response and Request for Time Extension_07142011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_Operator%20Response%20and%20Request%20for%20Time%20Extension_07142011.pdf

120111012M_Operator Response and Revised Procedures_09282011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120111012M/120111012M_Operator%20Response%20and%20Revised%20Procedures_09282011.pdf

120111012M_Closure Letter_12082011_text.pdf

U.S. Department 820 Bear Tavern Road, Suite 103
Of Transportation West Trenton, NJ 08628
Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
UPS OVERNIGHT DELIVERY
December 08, 2011
Mr. J. Andy Drake, P.E.
Vice President, Transmission Services
Spectra Energy Transmission, LLC
5400 Westheimer Court
Houston, Texas 77056
CPF 1-2011-1012M
Dear Mr. Drake:
During the week of November 29, 2010, representatives from the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code, conducted an
on-site pipeline safety inspection of Spectra Energy Transmission Services’ (Spectra) procedures in
Houston, Texas. As a result of the inspection, Spectra was issued a Notice of Amendment on June
13, 2011, which proposed amendment of your procedures.
After being granted an extension by the Director of PHMSA’s Eastern Region, Spectra submitted its
amended procedures on September 28, 2011. My staff reviewed the amended procedures, and it
appears that the inadequacies outlined in this Notice of Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Byron Coy, P.E.
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false
- **body characters:** 2808