# EQUITRANS MIDSTREAM CORPORATION — Notice of Amendment

- **operation:** document
- **citation:** CPF 120131017M
- **title:** EQUITRANS MIDSTREAM CORPORATION — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2013-08-20
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.225(a), 192.605(b)(1), 192.605(b)(2), 192.605(c)(4).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120131017m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120131017m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120131017m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120131017M
**body:**

Notice of Amendment involving EQUITRANS MIDSTREAM CORPORATION. PHMSA's enforcement data identifies the cited regulations as 192.225(a),  192.605(b)(1),  192.605(b)(2),  192.605(c)(4). The case was opened on 2013-08-20 and is reported as closed as of 2014-01-30. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120131017M_Closure Letter_01302014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120131017M/120131017M_Closure%20Letter_01302014.pdf

120131017M_Closure Letter_01302014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120131017M/120131017M_Closure%20Letter_01302014_text.pdf

120131017M_Notice of Amendment_08202013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120131017M/120131017M_Notice%20of%20Amendment_08202013.pdf

120131017M_Notice of Amendment_08202013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120131017M/120131017M_Notice%20of%20Amendment_08202013_text.pdf

120131017M_Operator Response_09162013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120131017M/120131017M_Operator%20Response_09162013.pdf

120131017M_Notice of Amendment_08202013_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
NOTICE OF AMENDMENT
OVERNIGHT EXPRESS DELIVERY
August 20, 2013
Robert Cooper, VP of Engineering
EQT Midstream
625 Liberty Avenue,
Pittsburgh, PA 15222
CPF 1-2013-1017M
Dear Mr. Cooper:
From May to September 2011, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), Office of Pipeline Safety (OPS), and interstate agents from the Public Service
Commission of West Virginia, pursuant to Chapter 601 of 49 United States Code inspected EQT
Midstream’s (EQT’s) procedures and records for Operations and Maintenance, as well as Design and
Construction, at its headquarter office in Pittsburgh, Pennsylvania, and a portion of its pipeline facilities
in Pennsylvania and West Virginia.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within EQT’s
plans or procedures, as described below:
1. §192.225 Welding Procedures.
(a) Welding must be performed by a qualified welder in accordance with welding procedures
qualified under section 5 of API 1104 (incorporated by reference, see §192.7) or section IX of
the ASME Boiler and Pressure Vessel Code " Welding and Brazing Qualifications"
(incorporated by reference, see §192.7) to produce welds meeting the requirements of this
subpart. The quality of the test welds used to qualify welding procedures shall be determined by
destructive testing in accordance with the applicable welding standard(s).
EQT’s welding procedures, Design & Construction Manual – Welding & Joining, was inadequate
because it did not mention the API 1104 version incorporated by reference in 49 C.F.R. 192 for the
welder and the welding procedures.
2. §192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of this section
must include procedures for the following, if applicable, to provide safety during maintenance
and operations.
(1) Operating, maintaining, and repairing the pipeline in accordance with each of the
requirements of this subpart and Subpart M of this part.



EQT’s procedures for inspecting and testing relief devices in a compressor station in its manual,
specifically Operations and Maintenance Manual, Section 7.23 Compressor Stations: Inspection and
Testing of Pressure Relief Devices [§192.731], was inadequate because the guidelines in the supplemental
procedure did not ensure that the gauge was calibrated to accurately determine and adjust the shutdown
switch trips at the proper set point. Particularly, EQT’s supplemental procedure, MP085 Maintain, Test
and Repair Overpressure Protection Devices under Engine/Compressor High Discharge Pressure
Shutdown Test General Procedure, lacks specific details on the use of a calibrated gauge to test the
shutdown set point.
3. §192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . .
(b) Maintenance and normal operations. The manual required by paragraph (a) of this section
must include procedures for the following, if applicable, to provide safety during maintenance
and operations. . .
(2) Controlling corrosion in accordance with the operations and maintenance requirements of
Subpart I of this part.
EQT’s procedure for corrosion control in its manual of written procedures, specifically Operations and
Maintenance Manual October 2009, Section 8.15 Atmospheric corrosion Control – Monitoring
[§192.481], and related procedure, Inspect for Atmospheric Corrosion, Revision No. 0, Revision Date
October 30, 2009, was inadequate because it lacked detailed instructions to monitor atmospheric
corrosion.
The aforementioned procedures were general and provided no guidance on how to give particular
attention to pipe at soil-to-air interfaces, under thermal insulation, under disbonded coatings, at pipe
supports in splash zones and in spans over water in accordance with section 192.481(b). EQT’s corrosion
control procedure does not specify how it determines where to give particular attention to piping under
thermal insulation such as by sampling inspection checkpoints prone to corrosion. Furthermore, EQT’s
corrosion control procedure refers to above-ground pipeline and does not consider portions of below-
ground pipeline that are exposed to the atmosphere.
EQT only requires a visual “[examination of] exposed portions of pipelines and soil-to-air interfaces
located at aboveground block valves, pig traps and station piping.” During the field inspection at Copley
Compressor Station and Pratt Compressor Station, PHMSA inspectors observed pipe under thermal
insulation and pipe supports.
Also, EQT’s procedure for corrosion control only requires that “[r]egular inspections should be made to
ensure above-ground pipeline facilities are protected against atmospheric corrosion.” (emphasis added).
During the field inspection, PHMSA inspectors observed portions of below-ground pipeline that were
exposed to the atmosphere.
4. §192.605 Procedural manual for operations, maintenance, and emergencies.
(a) . . .
(c) Abnormal operation. For transmission lines, the manual required by paragraph (a) of this
section must include procedures for the following to provide safety when operating design limits
have been exceeded: . . .
(4) Periodically reviewing the response of operator personnel to determine the effectiveness of
the procedures controlling abnormal operation and taking corrective action where deficiencies
are found.
120131017M_NOA_08202012 Page 2 of 3



EQT’s procedure for abnormal operation in its manual, specifically Operations and Maintenance (O&M)
Manual October 2009, Section 4.4 Reviewing the Effectiveness of Abnormal Operating Procedures
[§192.605(c)(4)], is inadequate because it does not specify the job title(s) of the individual(s) who are
responsible for reviewing and correcting the abnormal operating procedures.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.237. Enclosed as part of
this Notice is a document entitled Response Options for Pipeline Operators in Compliance
Proceedings. Please refer to this document and note the response options. Be advised that all material
you submit in response to this enforcement action is subject to being made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5 U.S.C.
552(b), along with the complete original document you must provide a second copy of the document with
the portions you believe qualify for confidential treatment redacted and an explanation of why you
believe the redacted information qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not
respond within 30 days of receipt of this Notice, this constitutes a waiver of your right to contest the
allegations in this Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as
alleged in this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged in this Notice,
you may be ordered to amend your plans or procedures to correct the inadequacies (49 C.F.R. § 190.237).
If you are not contesting this Notice, we propose that you submit your amended procedures to my office
within 45 days of receipt of this Notice. This period may be extended by written request for good cause.
Once the inadequacies identified herein have been addressed in your amended procedures, this
enforcement action will be closed.
It is requested (not mandated) that EQT maintain documentation of the safety improvement costs
associated with fulfilling this Notice of Amendment (preparation/revision of plans, procedures) and
submit the total to Byron Coy, PE, Director, Eastern Region, Pipeline and Hazardous Materials Safety
Administration. In correspondence concerning this matter, please refer to CPF 1-2013-1017M and, for
each document you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Byron Coy, P.E.
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
120131017M_NOA_08202013 Page 3 of 3

120131017M_Closure Letter_01302014_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
OVERNIGHT EXPRESS DELIVERY
January 30, 2014
Robert Cooper
Vice President of Engineering
EQT Midstream
625 Liberty Avenue,
Pittsburgh, PA 15222
CPF 1-2013-1017M
Dear Mr. Cooper:
From May to September 2011, representatives from the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code, conducted an on-
site pipeline safety inspection of EQT Midstream procedures and records for Operations and
Maintenance, as well as Design and Construction, at its headquarter office in Pittsburgh,
Pennsylvania, and a portion of its pipeline facilities in Pennsylvania and West Virginia. As a
result of the inspection, EQT Midstream was issued a Notice of Amendment on August 20, 2013,
which proposed amendment of its procedures.
EQT Midstream submitted its amended procedures on September 16, 2013. My staff reviewed
the amended procedures, and it appears that the inadequacies outlined in this Notice of
Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Byron Coy, P.E.
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false
- **body characters:** 10982