# NATIONAL FUEL GAS SUPPLY CORP — Warning Letter

- **operation:** document
- **citation:** CPF 120151005W
- **title:** NATIONAL FUEL GAS SUPPLY CORP — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2015-03-24
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.739(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120151005w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120151005w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120151005w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120151005W
**body:**

Warning Letter involving NATIONAL FUEL GAS SUPPLY CORP. PHMSA's enforcement data identifies the cited regulation as 192.739(a). The case was opened on 2015-03-24 and is reported as closed as of 2015-03-24. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120151005W_Warning Letter_03242015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120151005W/120151005W_Warning%20Letter_03242015.pdf

120151005W_Warning Letter_03242015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120151005W/120151005W_Warning%20Letter_03242015_text.pdf

120151005W_Warning Letter_03242015_text.pdf

U.S. Department Of Transportation Pipeline and 609.989.2171
Hazardous Materials
Safety Administration
820 Bear Tavern Road, Suite 103
West Trenton, NJ 08628
WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
March 24, 2015
John Pustulka
President
National Fuel Gas Supply Corporation
6363 Main Street
Williamsville, NY 14221
CPF 1-2015-1005W
Dear Mr. Pustulka:
From September 15 - 18, 2014, an inspector from the New York State Department of Public Service
(NYSDPS), acting as agents for the Pipeline and Hazardous Materials Safety Administration (PHMSA)
pursuant to Chapter 601 of 49 United States Code inspected the National Fuel Gas Supply Corporation
(NFG) Limestone Storage facilities in Cattaraugus County, NY.
As a result of the inspection, it appears that you have committed probable violations of the Pipeline Safety
Regulations, Title 49, Code of Federal Regulations. The items inspected and the probable violations are:
1. §192.739 Pressure limiting and regulating stations: Inspection and testing.
(a) Each pressure limiting station, relief device (except rupture discs), and pressure regulating
station and its equipment must be subjected at intervals not exceeding 15 months, but at least
once each calendar year, to inspections and tests to determine that it is—
NFG failed to inspect each pressure limiting station, relief device (except rupture discs), and Pressure
regulating station and its equipment at intervals not exceeding 15 months, but at least once each calendar
year. Specifically, NFG failed to inspect Regulator Unit #5, located at the Limestone Storage Facility in NY,
within a 15 month interval, as required by §192.739(a).
Regulator Unit #5 (RG 5) was inspected on the following dates:
1. August 22, 2012.
2. December 19, 2013. This is an interval of 15 months and 27 days.
3. October 21, 2014.
The inspection conducted on December 19, 2013 exceeded the 15 month requirement by 27 days.



1-2015-1005W
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $200,000 per
violation per day the violation persists up to a maximum of $2,000,000 for a related series of violations. For
violations occurring prior to January 4, 2012, the maximum penalty may not exceed $100,000 per violation
per day, with a maximum penalty not to exceed $1,000,000 for a related series of violations. We have
reviewed the circumstances and supporting documents involved in this case, and have decided not to conduct
additional enforcement action or penalty assessment proceedings at this time. We advise you to correct the
items identified in this letter. Failure to do so will result in National Fuel Gas Supply Corporation being
subject to additional enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 1-2015-1005W. Please send all correspondence in this matter to Byron Coy, PE, Director, PHMSA
Eastern Region, 820 Bear Tavern Road, Suite 103, W. Trenton, NJ 08628. Be advised that all material you
submit in response to this enforcement action is subject to being made publicly available. If you believe that
any portion of your responsive material qualifies for confidential treatment under 5 U.S.C. 552(b), along with
the complete original document you must provide a second copy of the document with the portions you
believe qualify for confidential treatment redacted and an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
Additionally, if you choose to respond to this (or any other case), please ensure that any response letter
pertains solely to one CPF case number.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
CC: NYSDPS – Mr. Kevin Speicher
120151005W_Warning Letter_03242015 2 of 2
- **truncated:** false
- **body characters:** 4493