# BUCKEYE PARTNERS, LP — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 120155021
- **title:** BUCKEYE PARTNERS, LP — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2015-12-15
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.402(a), 195.573(a)(1), 195.573(d).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120155021.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120155021.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120155021
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120155021
**body:**

Notice of Probable Violation involving BUCKEYE PARTNERS, LP. PHMSA's enforcement data identifies the cited regulations as 195.402(a),  195.573(a)(1),  195.573(d). The case was opened on 2015-12-15 and is reported as closed as of 2016-12-16. Proposed civil penalty: $270,600. Assessed civil penalty: $213,800. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120155021_Final Order_12072016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120155021/120155021_Final%20Order_12072016.pdf

120155021_Final Order_12072016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120155021/120155021_Final%20Order_12072016_text.pdf

120155021_NOPV_PCP_PCO_12152015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120155021/120155021_NOPV_PCP_PCO_12152015.pdf

120155021_NOPV_PCP_PCO_12152015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120155021/120155021_NOPV_PCP_PCO_12152015_text.pdf

120155021_Operator Response to Notice_01112016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120155021/120155021_Operator%20Response%20to%20Notice_01112016.pdf

120155021_Final Order_12072016_text.pdf

December 7, 2016
Mr. Clark Smith
President
Buckeye Partners, LP
One Greenway Plaza
Suite 600
Houston, TX 77046
Re: CPF No. 1-2015-5021
Dear Mr. Smith:
Enclosed please find the Final Order issued in the above-referenced case. It withdraws one of
the allegations of violation, makes other findings of violation, and assesses a reduced civil
penalty of $213,800. It further finds that Buckeye Partners, LP, has completed the actions
specified in the Notice to comply with the pipeline safety regulations. When the civil penalty
has been paid, this enforcement action will be closed. Service of the Final Order by certified
mail is deemed effective upon the date of mailing, or as otherwise provided under 49 C.F.R. §
190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Acting Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Robert Burrough, Acting Director, Eastern Region, PHMSA, OPS
Mr. Thomas. S (Scott) Collier, Vice President, Performance Assurance & Asset Integrity,
Buckeye Partners, LP, Five TEK Park, 9999 Hamilton Boulevard, Breinigsville,
Pennsylvania 18031
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
)
In the Matter of )
)
Buckeye Partners, LP, ) CPF No. 1-2015-5021
)
Respondent. )
____________________________________)
FINAL ORDER
From July 15 through July 19, 2013, pursuant to 49 U.S.C. § 60117, a representative of the
Pipeline and Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety
(OPS), conducted an on-site pipeline safety inspection of the records of Buckeye Partners, LP
(Buckeye or Respondent), at Respondent’s headquarters in Breinigsville, Pennsylvania,
including a review of survey records from Respondent’s Malvern and Booth inspection units in
Pennsylvania. Buckeye owns and operates approximately 6,000 miles of hazardous liquid
pipelines transporting refined products and highly volatile liquids, principally in the Northeastern
and upper Midwestern states.1
As a result of the inspection, the Director, Eastern Region, OPS (Director), issued to Respondent,
by letter dated December 15, 2015, a Notice of Probable Violation, Proposed Civil Penalty and
Proposed Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the Notice
proposed finding that Buckeye had violated 49 C.F.R. §§ 195.402 and 195.573 and proposed
assessing a civil penalty of $270,600 for the alleged violations. The Notice also proposed
ordering Respondent to take certain measures to correct one of the alleged violations.
Buckeye responded to the Notice by letter dated January 11, 2016 (Response). The company
contested only one of the allegations of violation and provided information concerning the
corrective actions it had already taken regarding another, referencing materials and information
submitted to the Eastern Region on November 24, 2015. Respondent did not request a hearing
and therefore has waived its right to one.
FINDINGS OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
1 http://www.buckeye.com/BusinessOperations/tabid/56/Default.aspx (last accessed May 27, 2016).



CPF No. 1-2015-5021
Page 2
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), which states, in
relevant part:
§ 195.402 Procedural manual for operations, maintenance, and
emergencies.
(a) General. Each operator shall prepare and follow for each pipeline
system a manual of written procedures for conducting normal operations and
maintenance activities and handling abnormal operations and emergencies. .
. .
The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a) by failing to follow, for
each pipeline system, a manual of written procedures for conducting normal operations and
maintenance activities and handling abnormal operations and emergencies. Specifically, the
Notice alleged that Buckeye failed to inspect electrical-isolation devices for proper operation
during annual corrosion control surveys, as required by Buckeye’s own procedures. According
to the Notice, Buckeye’s Maintenance Manual required the annual inspection of installed
electrical-isolation devices for proper operation. The Notice alleged that Buckeye’s electrical-
isolation survey records showed the company had failed to inspect electrical-isolation devices for
proper operation on 37 instances at 37 locations from 2011 to 2012.
Respondent did not contest this allegation of violation.2 Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(a) by failing to follow, for
each pipeline system, a manual of written procedures for conducting normal operations and
maintenance activities and handling abnormal operations and emergencies.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), as quoted above,
by failing to follow, for each pipeline system, a manual of written procedures for conducting
normal operations and maintenance activities and handling abnormal operations and
emergencies. Specifically, the Notice alleged that Buckeye failed to monitor pipelines “within or
near high-voltage AC corridors” for induced alternating-current (AC) interference on an annual
basis, as required by Buckeye’s own procedures. The Notice alleged that Buckeye’s
Maintenance Manual required pipelines within “high-voltage AC (HVAC) corridors” to be
monitored for induced AC interference on an annual basis. The Notice alleged that Buckeye’s
electrical surveys revealed AC corridors had not been identified or monitored for induced AC
interference in 140 instances from 2011 to 2012.
Respondent did not contest this allegation of violation.3 Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(a) by failing to follow, for
each pipeline system, a manual of written procedures for conducting normal operations and
maintenance activities and handling abnormal operations and emergencies.
2 Response at 1.
3 Id.



CPF No. 1-2015-5021
Page 3
Item 3: The Notice alleged that Respondent violated 49 C.F.R. § 195.402(a), as quoted above,
by failing to follow, for each pipeline system, a manual of written procedures for conducting
normal operations and maintenance activities and handling abnormal operations and
emergencies. Specifically, the Notice alleged that Buckeye failed to maintain and repair, within
one inspection cycle, test stations that had been found to be defective. According to the Notice,
Buckeye’s Maintenance Manual required that any test station found to be defective must be
repaired within one inspection cycle. The Notice alleged that inspection records from the
Respondent’s Malvern and Macungie mainlines showed invalid, missing or abnormally low test
station readings in five separate instances on three different segments, without corresponding
records reflecting repairs within one inspection cycle.
Respondent did not contest this allegation of violation.4 Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.402(a) by failing to follow, for
each pipeline system, a manual of written procedures for conducting normal operations and
maintenance activities and handling abnormal operations and emergencies.
Item 4: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(a)(1), which states:
§ 195.573 What must I do to monitor external corrosion control?
(a) Protected pipelines. You must do the following to determine
whether cathodic protection required by this subpart complies with
§195.571:
(1) Conduct tests on the protected pipeline at least once each calendar
year, but with intervals not exceeding 15 months. However, if tests at those
intervals are impractical for separately protected short sections of bare or
ineffectively coated pipelines, testing may be done at least once every 3
calendar years, but with intervals not exceeding 39 months.
The Notice alleged that Respondent violated 49 C.F.R. § 195.573(a)(1) by failing to conduct
external corrosion tests on a protected pipeline at least once each calendar year, but with
intervals not exceeding 15 months. Specifically, the Notice alleged that Buckeye failed to take
electrical measurements to demonstrate adequate levels of cathodic protection on a protected
pipeline at 11 different locations during the company’s 2011 annual survey.
Respondent did not contest this allegation of violation.5 Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.573(a)(1) by failing to conduct
external corrosion tests on a protected pipeline at least once each calendar year, but with
intervals not exceeding 15 months.
Item 5: The Notice alleged that Respondent violated 49 C.F.R. § 195.573(d), which states:
§ 195.573 What must I do to monitor external corrosion control?
4 Id.
5 Id.



CPF No. 1-2015-5021
Page 4
(a) ….
(d) Breakout tanks. You must inspect each cathodic protection system
used to control corrosion on the bottom of an aboveground breakout tank
to ensure that operation and maintenance of the system are in accordance
with API RP 651 (incorporated by reference, see § 195.3). However, this
inspection is not required if you note in the corrosion control procedures
established under § 195.402(c)(3) why complying with all or certain
operation and maintenance provisions of API RP 651 is not necessary for
the safety of the tank.
The Notice alleged that Respondent violated 49 C.F.R. § 195.573(d) by failing to inspect each
cathodic protection system used to control corrosion on the bottom of an aboveground breakout
tank to ensure that operation and maintenance of the system were in accordance with API RP
651, 3rd edition, January 2007 (RP 651). Specifically, the Notice alleged that Buckeye failed to
conduct electrical surveys on Tank 10 at the Booth station in Boothwyn, Pennsylvania, from
2010 through 2012.
In its Response, Buckeye acknowledged that it did not conduct electrical surveys on Tank 10 at
the Booth Station in 2011, but indicated that the tank was taken out of service on December 9,
2010, for an internal inspection and that product was cleared from the tank at that time.6
Buckeye explained that, as a result of its inspection, a new tank bottom was installed, which
included a new cathodic-protection system between the old floor and the new floor. This project
was not completed until April 27, 2012, and no product was in the tank until that time. Buckeye
argued that the company was not required to perform a cathodic-protection survey in 2010 on
Tank 10 because the tank was out-of-service while these installations were being made, with no
product in the tank from December 2010 through April 2012. Further, Buckeye stated that a
cathodic-protection survey was conducted in 2012 following the installation of the new tank
bottom.
After considering all of the evidence, I find that a cathodic protection survey of Tank 10 at Booth
Station was not required in 2011. Section 11.1.2 of API RP 651 states: “If tanks are empty, there
may be large areas of the bottoms which are not in contact with the underlying soil. Potential
surveys, in this case, may give misleading information.” The Recommended Practice further
instructs that “potential surveys should be conducted with an adequate level in the tank to
maximize contact of the tank bottom with the pad material.” Due to the repair work being
performed by Buckeye from December 2010 through April 2012, I find that it was unnecessary
for Respondent to perform a potential survey when there was an inadequate level of product in
the tank to meet the inspection provisions of RP 651. Based upon the foregoing, I hereby order
that Item 5 be withdrawn.
Findings of violation for Items 1-4 will be considered prior offenses in any subsequent
enforcement action taken against Respondent.
6 Id.



CPF No. 1-2015-5021
Page 5
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any
related series of violations.7 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a total
civil penalty of $270,600 for the violations cited above.
Item 1: The Notice proposed a civil penalty of $69,100 for Respondent’s violation of 49 C.F.R.
§ 195.402(a), for failing to follow, for each pipeline system, its own manual of written
procedures for conducting normal operations and maintenance activities and handling abnormal
operations and emergencies. Buckeye neither contested the allegation nor presented any
evidence or argument justifying a reduction in the proposed penalty. Accordingly, having
reviewed the record and considered the assessment criteria, I assess Respondent a civil penalty of
$69,100 for violation of 49 C.F.R. § 195.402(a).
Item 3: The Notice proposed a civil penalty of $90,700 for Respondent’s violation of 49 C.F.R.
§ 195.402(a), for failing to follow, for each pipeline system, its own manual of written
procedures for conducting normal operations and maintenance activities and handling abnormal
operations and emergencies. Buckeye neither contested the allegation nor presented any
evidence or argument justifying a reduction in the proposed penalty. Accordingly, having
reviewed the record and considered the assessment criteria, I assess Respondent a civil penalty of
$90,700 for violation of 49 C.F.R. § 195.402(a).
Item 4: The Notice proposed a civil penalty of $54,000 for Respondent’s violation of 49 C.F.R.
§ 195.573(a)(1) for failing to conduct tests on a cathodically protected pipeline at least once each
calendar year, but with intervals not exceeding 15 months. Buckeye neither contested the
allegation nor presented any evidence or argument justifying a reduction in the proposed penalty.
Accordingly, having reviewed the record and considered the assessment criteria, I assess
Respondent a civil penalty of $54,000 for violation of 49 C.F.R. § 195.573(a)(1).
Item 5: The Notice proposed a civil penalty of $56,800 for Respondent’s violation of 49 C.F.R.
§ 195.573(d), for failing to inspect each cathodic protection system used to control corrosion on
the bottom of an aboveground breakout tank, to ensure that operation and maintenance of the
system are in accordance with RP 651. As discussed above, Item 5 has been withdrawn. Based
upon the foregoing, I withdraw the proposed penalty for violation of 49 C.F.R. § 195.573(d).
7 The Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011, Pub. L. No. 112-90, § 2(a)(1), 125 Stat.
1904, January 3, 2012, increased the civil penalty liability for violating a pipeline safety standard to $200,000 per
violation for each day of the violation, up to a maximum of $2,000,000 for any related series of violations.



CPF No. 1-2015-5021
Page 6
In summary, having reviewed the record and considered the assessment criteria for each of the
Items cited above, I assess Respondent a total civil penalty of $213,800.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration, Mike
Monroney Aeronautical Center, P.O. Box 269039, Oklahoma City, Oklahoma 73125. The
Financial Operations Division telephone number is (405) 954-8845.
Failure to pay the $213,800 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Item 2, to correct an alleged violation of
49 C.F.R. § 195. Under 49 U.S.C. § 60118(a), each person who engages in the transportation of
hazardous liquids or who owns or operates a pipeline facility is required to comply with the
applicable safety standards established under chapter 601. The Director indicates that
Respondent has taken the following action specified in the proposed compliance order:
1. With respect to the violation of § 195.402(a) (Item 2), on November 24, 2015,
Respondent submitted its Interference Currents Procedure to PHMSA in response to
the Notice of Amendment issued in connection with a related proceeding, CPF No. 1-
2015-5016M. The Director has indicated this procedure satisfies the requirements of
the Notice’s Proposed Compliance Order with respect to Item 2.8
Accordingly, I find that compliance has been achieved with respect to this violation. Therefore,
the compliance terms proposed in the Notice are not included in this Order.
8 Region Recommendation, (January 21, 2016) (on file with PHMSA), at 2.



CPF No. 1-2015-5021
Page 7
The terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
December 7, 2016
___________________________________ _________________________
Alan K. Mayberry Date Issued
Acting Associate Administrator
for Pipeline Safety