# TOTAL PEAKING SERVICES — Warning Letter

- **operation:** document
- **citation:** CPF 120163003W
- **title:** TOTAL PEAKING SERVICES — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2016-11-22
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 193.2017(a), 193.2639(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120163003w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120163003w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120163003w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120163003W
**body:**

Warning Letter involving TOTAL PEAKING SERVICES. PHMSA's enforcement data identifies the cited regulations as 193.2017(a),  193.2639(a). The case was opened on 2016-11-22 and is reported as closed as of 2016-11-22. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120163003W_Warning Letter_11222016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120163003W/120163003W_Warning%20Letter_11222016.pdf

120163003W_Warning Letter_11222016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120163003W/120163003W_Warning%20Letter_11222016_text.pdf

120163003W_Warning Letter_11222016_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
November 22, 2016
Anthony Marone
Senior Vice President, Gas Operations
AVANGRID Networks
180 Marsh Hill Rd.
Orange, CT 06477
CPF 1-2016-3003W
Dear Mr. Marone:
Between February 22-26, 2016, inspectors from the Connecticut Department of Energy and
Environmental Protection (CT DEEP), acting as agents for the Pipeline and Hazardous Materials
Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected
Total Peaking Services’s (TPS) procedures, records, and LNG plant facilities in Milford, CT.
As a result of the inspection, it appears that you have committed a probable violation of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and the
probable violation is:
1. §193.2017 Plans and procedures
(a) Each operator shall maintain at each LNG plant the plans and procedures required for
that plant by this part. The plans and procedures must be available upon request for
review and inspection by the Administrator or any State Agency that has submitted a
current certification or agreement with respect to the plant under the pipeline safety laws
(49 U.S.C. 60101 et seq.). In addition, each change to the plans or procedures must be
available at the LNG plant for review and inspection within 20 days after the change is
made.
TPS failed to maintain at each LNG plant the plans and procedures required for that plant by this
part. Specifically, the control box for the internal LNG tank shutoff valve was relocated on
January 29, 2013, but the change to the LNG plant plans and procedures was not made within 20
days after the relocation.
During the inspection, the CT DEEP reviewed TPS records from 2013 through
2015. Preventative Maintenance Work Order (WO) P102490 dated 5/1/2014 was generated to
conduct a test on the internal valve system. The WO identified the location of the valve as



1-2016-3003W
between CP30 building and the Expander Compressors. The location was crossed out and a
handwritten note stating “control box repiped and moved to the LNG pump house. redue (sp)
work order” was included in the corrective action section of the WO. The corrective action was
reviewed by TPS personnel and signed off on 5/12/2014 and 5/13/2014.
On 5/1/2015, TPS generated WO P103266 to conduct a test of the same valve that was tested in
2014. The WO generated in 2015 did not include the location comments that were noted on the
WO completed in 2014.
Thus, TPS failed to make each change to the plans or procedures available for review and
inspection within 20 days after the change was made.
2. §193.2639 Maintenance records.
(a) Each operator shall keep a record at each LNG plant of the date and type of each
maintenance activity performed on each component to meet the requirements of this part.
For each LNG facility that is designed and constructed after March 31, 2000, the operator
shall also maintain related periodic inspection and testing records that NFPA-59A-2001
(incorporated by reference, see §193.2013) requires. Maintenance records, whether
required by this part or NFPA-59A-2001, must be kept for a period of not less than five
years.
TPS failed to keep an accurate record of the date and type of each maintenance activity
performed on each component to meet the requirements of this part.
TPS utilizes a 500kW backup generator to supply auxiliary power to the plant in the event of an
emergency. TPS conducted an operational test of the generator on April 9, 2015 and recorded
the results of the test on WO P103170.
1. The corrective action section of the record indicated “ran emergency all in good working
order.”
2. The operational test section of the record indicated "0" output voltage on two of the three
phases of the output. The record also indicated "0" oil pressure, “0” water temperature,
and inconsistent frequency among the three outputs.
The “0” readings are inconsistent with the corrective action section of the record. The record
was signed by the TPS person that completed the work, as well as the TPS supervisor, with no
explanation of the apparent inconsistencies.
Under 49 United States Code, § 60122, you are subject to a civil penalty not to exceed $205,638
per violation per day the violation persists up to a maximum of $2,056,380 for a related series of
violations. For violation occurring between January 4, 2012 to August 1, 2016, the maximum
penalty may not exceed $200,000 per violation per day, with a maximum penalty not to exceed
$2,000,000 for a related series of violations. For violations occurring prior to January 4, 2012,
the maximum penalty may not exceed $100,000 per violation per day, with a maximum penalty
not to exceed $1,000,000 for a related series of violations. Also, for LNG facilities, an
additional penalty of not more than $50,000 for each violation may be imposed. We have
reviewed the circumstances and supporting documents involved in this case, and have decided
not to conduct additional enforcement action or penalty assessment proceedings at this time. We
advise you to correct the item(s) identified in this letter. Failure to do so will result in Total
Peaking Services being subject to additional enforcement action.
120163003W_Warning Letter_11222016 Page 2 of 3



1-2016-3003W
No reply to this letter is required. If you choose to reply, please address your correspondence to:
Byron Coy, PE, Director, PHMSA Eastern Region, 820 Bear Tavern Road, Suite 103, W.
Trenton, NJ 08628 and please refer to CPF 1-2016-3003W. Be advised that all material you
submit in response to this enforcement action is subject to being made publicly available. If you
believe that any portion of your responsive material qualifies for confidential treatment under 5
U.S.C. 552(b), along with the complete original document, you must provide a second copy of
the document with the portions you believe qualify for confidential treatment redacted, and an
explanation of why you believe the redacted information qualifies for confidential treatment
under 5 U.S.C. 552(b).
Additionally, if you choose to respond to this (or any other case), please ensure that any response
letter pertains solely to one CPF case number.
Sincerely,
Byron Coy, PE
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Cc: Karl Baker, CT DEEP
120163003W_Warning Letter_11222016 Page 3 of 3