# COLUMBIA GAS TRANSMISSION, LLC — Warning Letter

- **operation:** document
- **citation:** CPF 120181008W
- **title:** COLUMBIA GAS TRANSMISSION, LLC — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2018-03-27
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 191.22(c)(1)(i).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181008w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181008w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181008w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120181008W
**body:**

Warning Letter involving COLUMBIA GAS TRANSMISSION, LLC. PHMSA's enforcement data identifies the cited regulation as 191.22(c)(1)(i). The case was opened on 2018-03-27 and is reported as closed as of 2018-03-27. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120181008W_Warning Letter_03272018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120181008W/120181008W_Warning%20Letter_03272018.pdf

120181008W_Warning Letter_03272018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120181008W/120181008W_Warning%20Letter_03272018_text.pdf

120181008W_Warning Letter_03272018_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
March 27, 2018
Mr. Randal Broussard
US Gas Operations East, SVP
Columbia Gas Transmission, LLC
201 Energy Parkway
Suite 100
Lafayette, LA 70508
CPF 1-2018-1008W
Dear Mr. Broussard:
On January 12, 2018 a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.) reviewed
Operator Registry Notification F-20180112-18541 submitted by Columbia Gas Transmission,
LLC, a subsidiary of TransCanada (TransCanada).
As a result of the inspection, it is alleged that you have committed a probable violation of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The item inspected and
the probable violation is:
1. §191.22 National Registry of Pipeline and LNG Operators
…
(c) Changes. Each operator of a gas pipeline, gas pipeline facility, underground
natural gas storage facility, LNG plant, or LNG facility must notify PHMSA
electronically through the National Registry of Pipeline, Underground Natural Gas
Storage Facility, and LNG Operators at http://opsweb.phmsa.dot.gov of certain
events.
(1) An operator must notify PHMSA of any of the following events not later than
60 days before the event occurs:



CPF 1-2018-1008W
(i) Construction or any planned rehabilitation, replacement, modification, upgrade,
uprate, or update of a facility, other than a section of line pipe, that costs $10 million
or more. If 60-day notice is not feasible because of an emergency, an operator must
notify PHMSA as soon as practicable;
TransCanada failed to notify PHMSA of its construction or any planned rehabilitation,
replacement, modification, upgrade, uprate, or update of a facility, other than a section of line pipe,
that costs $10 million or more, as required by § 191.22.
On January 12, 2018, the PHMSA representative reviewed TransCanada’s construction
notification F-20180112-18541, dated January 12, 2018. Columbia submitted the “Type F”
(construction or rehabilitation of gas or liquid facilities) notification electronically through the
online National Registry of Pipeline and LNG Operators website.
TransCanada stated in the notification that the anticipated start date of field work activities was
01/04/2018. In follow-up to the notification, the PHMSA representative e-mailed TransCanada
inquiring about the status of the construction project. TransCanada responded, “The attached
document is the construction schedule for the loop line portion of ESU…” The Millennium
Pipeline Company- Eastern System Upgrade Construction Schedule, dated 01/17/18 (Record)
showed that construction activities began on 12/20/17. Additionally, TransCanada stated, “Since
this project includes modifications and adding two compressor units with 22,400 HP at multi
locations, the cost of the project is greater than $10M and I believe this project meets the reporting
requirement of 191.22 (c)(1)(i).”
Accordingly, TransCanada did not submit this construction notification in a timely manner.
TransCanada was required to submit this construction notification no later than 60 days before
construction occurred; however, it was submitted on 01/12/18, which was 68 days late.
Therefore, TransCanada failed to comply with the construction notification requirement in
§ 191.22(c)(1)(i).
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$209,002 per violation per day the violation persists, up to a maximum of $2,090,022 for a related
series of violations. For violations occurring prior to November 2, 2015, the maximum penalty
may not exceed $200,000 per violation per day, with a maximum penalty not to exceed $2,000,000
for a related series of violations. We have reviewed the circumstances and supporting documents
involved in this case, and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to correct the item(s) identified in this letter.
Failure to do so will result in TransCanada being subject to additional enforcement action.
Please be advised that all material you submit in response to this enforcement action is subject to
being made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. 552(b).
120181008W_Warning Letter_03272018_text
Page 2 of 3



CPF 1-2018-1008W
No reply to this letter is required. If you choose to reply, please submit all correspondence in this
matter to Robert Burrough, Director, PHMSA Eastern Region, 820 Bear Tavern Road, Suite 103,
West Trenton, NJ 08628. Please refer to CPF 1-2018-1008W on each document you submit, and
whenever possible provide a signed PDF copy in electronic format. Smaller files may be emailed
to robert.burrough@dot.gov. Larger files should be sent on a CD accompanied by the original
paper copy to the Eastern Region Office.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
120181008W_Warning Letter_03272018_text
Page 3 of 3
- **truncated:** false
- **body characters:** 6030