# TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP) — Warning Letter

- **operation:** document
- **citation:** CPF 120181024W
- **title:** TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP) — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2018-12-12
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.481(a), 192.605(a), 192.615(c), 192.805(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181024w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181024w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120181024w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120181024W
**body:**

Warning Letter involving TEXAS EASTERN TRANSMISSION, LP (SPECTRA ENERGY PARTNERS, LP). PHMSA's enforcement data identifies the cited regulations as 192.481(a),  192.605(a),  192.615(c),  192.805(a). The case was opened on 2018-12-12 and is reported as closed as of 2018-12-12. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120181024W_Warning Letter_12122018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120181024W/120181024W_Warning%20Letter_12122018.pdf

120181024W_Warning Letter_12122018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120181024W/120181024W_Warning%20Letter_12122018_text.pdf

120181024W_Warning Letter_12122018_text.pdf

WARNING LETTER
OVERNIGHT EXPRESS DELIVERY
December 12, 2018
Michele Harradence
VP Gas Transmission & Midstream Operations
Texas Eastern Transmission, LP
5400 Westheimer Court
Houston, TX 77251-1642
CPF 1-2018-1024W
Dear Ms. Harradence:
From January 22, 2018 to August 28, 2018, representatives of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
(U.S.C.) inspected Texas Eastern Transmission, LP’s (Texas Eastern) “Spectra TX Eastern North”
system located throughout New Jersey, Pennsylvania, Maryland, West Virginia, Ohio and New
York.
As a result of the inspection, it is alleged that you have committed probable violations of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations (CFR). The items inspected
and the probable violations are:
1. § 192.481 Atmospheric Corrosion Control: Monitoring
(a) Each operator must inspect each pipeline or portion of pipeline that is exposed to
the atmosphere for evidence of atmospheric corrosion, as follows:
If the pipeline is located: Then the frequency of inspection is:
Onshore At least once every 3 calendar years, but
with intervals not exceeding 39 months
Offshore At least once each calendar year, but with
intervals not exceeding 15 months



CPF 1-2018-1024W
Texas Eastern failed to inspect each pipeline or portion of pipeline that is exposed to the
atmosphere for evidence of atmospheric corrosion at a frequency of at least once every 3 calendar
years, but with intervals not exceeding 39 months, at 46 inspection locations within its
Delmont Station.
During the inspection, the PHMSA inspector reviewed atmospheric corrosion inspection records
from 2012 – 2016 for Texas Eastern’s pipelines located in the North-East System.
The records demonstrated that Texas Eastern failed to inspect 46 atmospheric corrosion evaluation
locations within the Delmont Station at least once every 3 calendar years. Atmospheric corrosion
evaluations were performed on 11/14/2012, with next inspections due by 12/31/15. The next
atmospheric corrosion evaluations were performed on 3/9/2016.
Therefore, Texas Eastern failed to inspect portions of its pipelines exposed to the atmosphere for
evidence of atmospheric corrosion at least once every 3 calendar years at its Delmont Station.
2. § 192.605 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline, a manual of
written procedures for conducting operations and maintenance activities and for
emergency response. For transmission lines, the manual must also include
procedures for handling abnormal operations. This manual must be reviewed and
updated by the operator at intervals not exceeding 15 months, but at least one
each calendar year. This manual must be prepared before operations of a pipeline
system commence. Appropriate parts of the manual must be kept at locations
where operations and maintenance activities are conducted.
Texas Eastern failed to follow for each pipeline, a manual of written procedures for conducting
operations and maintenance activities. Specifically, Texas Eastern failed in 7 instances to take
remedial action in accordance with its procedure 2-5020 Atmospheric Pipe Inspection, versions
dated 1/2/12 and 10/7/14 (AC Procedures), on poor coating conditions requiring remedial action
within one year of the atmospheric corrosion inspections.
Texas Eastern’s AC Procedures each stated, “Sites identified as being of poor condition will be
evaluated by the Regional Technical staff to determine the appropriate follow-up action. Those
determined to require remedial action shall be completed within one year.”
During the inspection, the PHMSA inspector reviewed Texas Eastern’s atmospheric corrosion
inspection records from 2012 to 2015. The records revealed that Texas Eastern personnel became
aware of poor conditions of the coating, with remedial action required, but action was not taken
by Texas Eastern to remediate the conditions within one year. The following table outlines specific
locations where remedial actions were missed.
120181024W_Warning Letter_12122018_text Page 2 of 6



CPF 1-2018-1024W
Atmospheric Report
Location Description Inspection Date Coating Condition Remedial Action Required Corrosion Date Action Taken
Date Action Should have been
taken according to 2‐2050
7/2/2013 Poor Blank Surface Rust 6/1/2016 on or before 7/2/2014
19‐insertion meter 19‐779
8/3/2015 Poor Yes General Corosion 6/1/2016 on or before 8/3/2016
7/2/2013 Poor Blank Surface Rust 6/1/2016 on or before 7/2/2014
27‐insertion meter 27‐717
8/3/2015 Poor Yes General Corosion 6/1/2016 on or before 8/3/2016
5/6/2014 Poor Yes Blank 10/19/2016 on or before 5/6/2015
ESD by Main Gate
8/4/2015 Poor Yes Pitting <20% 10/19/2016 on or before 8/4/2016
ESD by rectifier at office
and ESD Nort
5/6/2014 Poor Yes Blank 10/19/2016 on or before 5/6/2015
8/4/2015 Poor Yes Pitting <20% 10/19/2016 on or before 8/4/2016
Basement Westinghouse
building
5/6/2014 Poor Yes Blank ? on or before 5/6/2015
8/4/2015 Poor Yes Pitting <20% ? on or before 8/4/2016
6/20/2012 Poor Yes General Corosion 10/17/2015 on or before 6/20/2013
Tomer X‐Over V#29‐94
4/17/2015 Poor No Surface Rust 10/17/2015 on or before 4/17/2016
Tomer Line #39 MLV
#39066
6/20/2012 Poor Yes General Corosion 10/17/2015 on or before 6/20/2013
4/17/2015 Poor No Surface Rust 10/17/2015 on or before 4/17/2016
Therefore, Texas Eastern failed to follow its written procedure regarding Atmospheric Pipe
Inspection remedial actions.
3. § 192.605 Procedural Manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline, a manual of
written procedures for conducting operations and maintenance activities and for
emergency response. For transmission lines, the manual must also include
procedures for handling abnormal operations. This manual must be reviewed and
updated by the operator at intervals not exceeding 15 months, but at least one
each calendar year. This manual must be prepared before operations of a pipeline
system commence. Appropriate parts of the manual must be kept at locations
where operations and maintenance activities are conducted.
Texas Eastern failed to follow its manual of written procedures for conducting emergency
response. Specifically, Texas Eastern failed to follow its Procedure Number 5-2010, Area
Emergency Response Procedures, dated 4/30/2014 (Procedure), which required personnel to be
trained annually on the Area Emergency Response Plan, pursuant to § 192.615(b)(2).
Section 192.615(b)(2) states:
(b) Each operator shall:
…
(2) Train the appropriate operating personnel to assure that they are knowledgeable of the
emergency procedures and verify that the training is effective.
Texas Eastern’s Procedure, section 7.2 - Training of the Emergency Response Procedures states
(emphasis added):
7.2 An Emergency Response Plan training session with area personnel shall be
conducted once each calendar year, but not to exceed fifteen (15) months. Area
personnel are responsible to review the Area Emergency Response Plan. The review is to
be documented on Form #7T-9.
During the field inspection at the Marietta Compressor Station, the PHMSA inspector reviewed
two #7T-9 Forms for the Marietta Compressor Station Emergency Response Plan training. The
#7T-9 Forms provided confirmed the annual training and attendance for 2015 and 2017. Texas
120181024W_Warning Letter_12122018_text Page 3 of 6



CPF 1-2018-1024W
Eastern could not provide the #7T-9 Form for the 2016 Marietta Compressor Station Emergency
Response Plan training, nor did they provide any other documentation to show the 2016 annual
training for the Marietta Compressor Station had taken place.
Additionally, Marietta’s pre-printed Emergency Response Plan training verification form #7T-9
for 2015 and 2017 was prepopulated with the names of personnel scheduled to attend the training,
with handwritten initials provided by the attendees. The 2015 and 2017 year’s #7T-9 training
attendance forms showed five personnel for each year had not initialed reflecting their attendance
at the training. The #7T-9 forms indicated that two of the personnel who did not have the training
in 2015 were also not trained in 2017.
Texas Eastern stated they did not have a process in place currently for either tracking personnel
who missed the required yearly Emergency Response Plan training, or for providing a make-up
training session to those who missed the training.
Therefore, Texas Eastern failed to follow its manual of written procedures for emergency response
by not training the Marietta staff annually on the Area Emergency Response Plan.
4. § 192.615 Emergency Plans
(c) Each operator shall establish and maintain liaison with appropriate fire, police
and other public officials to:
(1) Learn the responsibility and resources of each government organization that
may respond to a gas pipeline emergency;
(2) Acquaint the officials with the operator’s ability in responding to a gas pipeline
emergency;
(3) Identify the types of gas pipeline emergencies of which the operator notified
the officials; and
(4) Plan how the operator and officials can engage in mutual assistance to
minimize hazards to life or property.
Texas Eastern failed to establish and maintain liaison with appropriate fire officials to learn their
responsibilities and resources for responding to a gas pipeline emergency; to acquaint the fire
officials with Texas Eastern’s ability in responding to a gas pipeline emergency; to identify the
types of gas pipeline emergencies which Texas Eastern notices the fire officials of; and to plan
how Texas Eastern and the fire officials can engage in mutual assistance to minimize hazards to
life or property.
During the field inspection at the Eagle Compressor Station, the PHMSA inspector reviewed the
area Emergency Response Binder. Emergency Response contact numbers were listed for various
locations where Texas Eastern pipelines are located. Texas Eastern identified the Philadelphia
[International] Airport as an Emergency Contact for their 1-A pipeline. As indicated in the National
Pipeline Mapping System (NPMS), Texas Eastern’s 16” South Line 1-A pipeline is located within
a few hundred feet from a prominent active runway (#17/35) at the Philadelphia International
Airport (PHL). PHL serves as a large hub for a major airline and the airport can service over a
hundred thousand passengers daily.
120181024W_Warning Letter_12122018_text Page 4 of 6



CPF 1-2018-1024W
When requested by the PHMSA inspector, Texas Eastern failed to provide any records or evidence
of joint communication between Texas Eastern and PHL Officials or PHL Fire/Rescue Department
- Engine 78 (PHL Fire). No records were provided showing PHL or PHL Fire representatives had
attended any of the Paradigm Pipeline liaison meetings, showing that Texas Eastern had
information on the type of resources available at the PHL or PHL Fire department that would be
needed during a pipeline emergency for the airport location, or showing any joint communication
between Texas Eastern and PHL or PHL Fire officials.
Thus, Texas Eastern failed to establish and maintain liaison with appropriate fire, police, and other
public officials as required by § 192.615(c).
5. § 192.805 Qualification Program
Each operator shall have and follow a written qualification program. The program
shall include provisions to:
(a) Ensure through evaluation that individuals performing covered tasks are
qualified;
Texas Eastern failed to ensure through evaluation that individuals performing covered tasks are
qualified.
During the inspection, the PHMSA inspector reviewed Enbridge Compliance Atmospheric
Reports as well as Veriforce Field Verification Reports.
Texas Eastern Technician Candidate ID: tf-613037-01 did not have Task ID: 417OP: Atmospheric
Corrosion Monitoring, qualifying them to inspect for Atmospheric Corrosion. Candidate ID: tf-
613037-01 is listed on Enbridge Compliance Atmospheric Report as the technician who performed
this task in 76 instances on the Northeast System: Uniontown-Delmont.
When questioned, Texas Eastern stated that Candidate ID: tf-613037-01 was observed by another
technician that is qualified under Task ID: 417OP. However, Texas Eastern could not produce any
documentation to demonstrate that the individual was observed by a qualified individual when
performing the task.
Under 49 U.S.C. § 60122 and 49 CFR § 190.223, you are subject to a civil penalty not to exceed
$209,002 per violation per day the violation persists, up to a maximum of $2,090,022 for a related
series of violations. For violations occurring prior to November 2, 2015, the maximum penalty
may not exceed $200,000 per violation per day, with a maximum penalty not to exceed $2,000,000
for a related series of violations. We have reviewed the circumstances and supporting documents
involved in this case, and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to correct the item(s) identified in this letter.
Failure to do so will result in Texas Eastern Transmission, LP being subject to additional
enforcement action.
Please be advised that all material you submit in response to this enforcement action is subject to
being made publicly available. If you believe that any portion of your responsive material qualifies
for confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for confidential
120181024W_Warning Letter_12122018_text Page 5 of 6



CPF 1-2018-1024W
treatment redacted and an explanation of why you believe the redacted information qualifies for
confidential treatment under 5 U.S.C. 552(b).
No reply to this letter is required. If you choose to reply, please submit all correspondence in this
matter to Robert Burrough, Director, PHMSA Eastern Region, 840 Bear Tavern Road, Suite 300,
West Trenton, NJ 08628. Please refer to CPF 1-2018-1024W on each document you submit, and
whenever possible provide a signed PDF copy in electronic format. Smaller files may be emailed
to robert.burrough@dot.gov. Larger files should be sent on a CD accompanied by the original
paper copy to the Eastern Region Office.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
120181024W_Warning Letter_12122018_text Page 6 of 6