# SUNOCO PIPELINE L.P. — Notice of Amendment

- **operation:** document
- **citation:** CPF 120185027M
- **title:** SUNOCO PIPELINE L.P. — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2018-08-22
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 195.402(c)(3).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-120185027m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-120185027m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-120185027m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/120185027M
**body:**

Notice of Amendment involving SUNOCO PIPELINE L.P.. PHMSA's enforcement data identifies the cited regulation as 195.402(c)(3). The case was opened on 2018-08-22 and is reported as closed as of 2018-10-05. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

120185027M_Closure letter_10052018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120185027M/120185027M_Closure%20letter_10052018.pdf

120185027M_Closure letter_10052018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120185027M/120185027M_Closure%20letter_10052018_text.pdf

120185027M_Notice of Amendment_08222018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120185027M/120185027M_Notice%20of%20Amendment_08222018.pdf

120185027M_Notice of Amendment_08222018_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120185027M/120185027M_Notice%20of%20Amendment_08222018_text.pdf

120185027M_Operator Response to Notice_09212018.pdf: https://primis.phmsa.dot.gov/enforcement-documents/120185027M/120185027M_Operator%20Response%20to%20Notice_09212018.pdf

120185027M_Notice of Amendment_08222018_text.pdf

NOTICE OF AMENDMENT
OVERNIGHT EXPRESS DELIVERY
August 22, 2018
Mr. Greg McIlwain
Senior Vice President of Operations
Sunoco Pipeline L.P.
1300 Main Street
Houston, TX 77002
CPF 1-2018-5027M
Dear Mr. McIlwain:
From April 3, 2017 to August 11, 2017, representatives of the Pipeline and Hazardous Materials
Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected
Sunoco Pipeline, L.P.’s (Sunoco) Mariner East 1 pipeline procedures for operations, maintenance,
and emergencies in Washington County, Pennsylvania.
On the basis of the inspection, PHMSA has identified the apparent inadequacy found within
Sunoco’s plans or procedures, as described below:
1. § 195.402 Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
Sunoco’s procedures for operating, maintaining and repairing its pipeline system in accordance
with each requirement of subpart F of Part 195 were inadequate. Specifically, Sunoco’s O&M
procedure SEC. 195.420. Valve Maintenance (Procedure) lacked detailed instructions necessary
for maintaining each valve that is necessary for the safe operation of its pipeline system, as required
by § 195.420(a).



CPF 1-2018-5027M
Section 195.420(a) states:
“Each operator shall maintain each valve that is necessary for the safe operation of its pipeline
systems in good working order at all times.”
During the inspection, the PHMSA inspector reviewed Sunoco’s mainline valve (MLV) inspection
records for the PHMSA Delmont to Plainfield unit. Several of the MLV inspection records listed
as “check valve # V-183.5C”; however, the check valve inspection information was missing for
several MLV inspection cycles required under § 195.420(b). Sunoco explained that due to the
unique design of the check valve it is difficult to inspect to determine if it is functioning properly,
as required by § 195.420(b).
In a post-inspection letter dated August 18, 2017, Sunoco stated:
“SPLP… plans to remove the check valves from the CMMS “DOT-Required” valve inspection
category and forms. SPLP will continue to conduct the regularly planned site inspections and list
these valves in the preventative maintenance category to document maintenance as a “facility
valve”, following SPLP O&M Manual Section 195.420.”
Regarding “facility valves”, Sunoco’s Procedure stated in part (emphasis added):
SPLP Requirements/Process Description…
2. Facility Valves (and other non-Main Live Valves)
I…
II. Facility valves shall be maintained as determined by SPLP to insure the safe
operation of the pipeline system.
The statement “Facility valves shall be maintained as determined by SPLP…” is inadequate
because it lacks detailed instructions necessary for maintaining each valve that is necessary for the
safe operation of its pipeline system, as required by § 195.420(a).
Therefore, Sunoco’s procedures did not adequately address the requirements of § 195.420(a).
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Compliance
Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. 552(b), along with the complete original document you must provide a
second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under §190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
120185027M_Notice of Amendment_08222018_text Page 2 of 3



CPF 1-2018-5027M
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that Sunoco maintain documentation of the safety improvement
costs associated with fulfilling this Notice of Amendment (preparation/revision of plans,
procedures) and submit the total to Robert Burrough, Director, PHMSA Eastern Region,
820 Bear Tavern Road, Suite 103, West Trenton, NJ 08628. Please refer to CPF 1- 2018-5027M
on each document you submit, and whenever possible provide a signed PDF copy in electronic
format. Smaller files may be emailed to robert.burrough@dot.gov. Larger files should be sent on
a CD accompanied by the original paper copy to the Eastern Region Office.
Additionally, if you choose to respond to this (or any other case), please ensure that any response
letter pertains solely to one CPF case number.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings
120185027M_Notice of Amendment_08222018_text Page 3 of 3

120185027M_Closure letter_10052018_text.pdf

OVERNIGHT EXPRESS DELIVERY
October 5, 2018
Mr. Greg McIlwain
Senior Vice President of Operations
Sunoco Pipeline L.P.
1300 Main Street
Houston, TX 77002
CPF 1-2018-5027M
Dear Mr. McIlwain:
From April 3 to August 11, 2017, a representative from the Pipeline and Hazardous Materials
Safety Administration, Office of Pipeline Saftey pursuant to Chapter 601 of 49 United States Code,
conducted an on-site pipeline safety inspection of Sunoco Pipeline, L.P. (Sunoco) Mariner East 1
pipeline for operations, maintenance and emergencies in Washington County, PA. As a result of
the inspection, Sunoco was issued a Notice of Amendment (NOA) on August 22, 2018, which
proposed amendment of its procedures.
On September 21, 2018, Sunoco submitted Energy Transfer’s Standard Operating Procedure
HLM.01, which replaced Sunoco’s previous procedure. My staff reviewed these procedures, and
it appears that the inadequacies outlined in this NOA have been corrected as a result.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false
- **body characters:** 8519