# DTE MIDSTREAM APPALACHIA, LLC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 12020011NOPV
- **title:** DTE MIDSTREAM APPALACHIA, LLC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2020-09-03
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 192.605(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-12020011nopv.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-12020011nopv.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-12020011nopv
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/12020011NOPV
**body:**

Notice of Probable Violation involving DTE MIDSTREAM APPALACHIA, LLC. PHMSA's enforcement data identifies the cited regulation as 192.605(a). The case was opened on 2020-09-03 and is reported as closed as of 2020-10-29. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

12020011NOPV_Closure Letter_10292020_(20-172056).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_Closure%20Letter_10292020_(20-172056).pdf

12020011NOPV_Closure Letter_10292020_(20-172056)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_Closure%20Letter_10292020_(20-172056)_text.pdf

12020011NOPV_Final Order_10232020_(20-172056).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_Final%20Order_10232020_(20-172056).pdf

12020011NOPV_Final Order_10232020_(20-172056)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_Final%20Order_10232020_(20-172056)_text.pdf

12020011NOPV_Operator Response to Notice_09182020_(20-172056).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_Operator%20Response%20to%20Notice_09182020_(20-172056).pdf

12020011NOPV_PCO_09032020_(20-172056).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_PCO_09032020_(20-172056).pdf

12020011NOPV_PCO_09032020_(20-172056)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12020011NOPV/12020011NOPV_PCO_09032020_(20-172056)_text.pdf

12020011NOPV_Final Order_10232020_(20-172056)_text.pdf

October 23, 2020
VIA ELECTRONIC MAIL TO: richard.redmond@dteenergy.com
Mr. Richard L. Redmond, Jr.
Executive Vice President
DTE Midstream Appalachia, LLC
Fifth Floor, 1000 Noble Energy Drive
Canonsburg, Pennsylvania 15317
Re: CPF No. 1-2020-011-NOPV
Dear Mr. Redmond:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation and specifies actions that need to be taken to comply with the pipeline safety
regulations. When the terms of the compliance order are completed, as determined by the
Director, Eastern Region, this enforcement action will be closed. Service of the Final Order by
electronic mail is effective upon the date of transmission as provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
cc: Mr. Robert Burrough, Director, Eastern Region, Office of Pipeline Safety, PHMSA
Mr. Philip Coleman, Director – Codes and Regulatory, DTE Midstream Appalachia,
LLC, philip.coleman@dteenergy.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
)
In the Matter of )
)
DTE Midstream Appalachia, LLC, ) CPF No. 1-2020-011-NOPV
a subsidiary of DTE Energy Company, )
)
Respondent. )
)
FINAL ORDER
On September 3, 2020, pursuant to 49 C.F.R. § 190.207, the Director, Eastern Region, Office of
Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to DTE Midstream
Appalachia, LLC (Respondent). The Notice proposed finding that Respondent had violated the
pipeline safety regulations in 49 C.F.R. Part 192. The Notice also proposed certain measures to
correct the alleged violation. Respondent did not contest the allegation of violation or corrective
measures.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulation listed below, as more fully described in the enclosed Notice, which is
incorporated by reference:
49 C.F.R. § 192.605(a) (Item 1) ─ Respondent failed to follow its manual of
written procedures for conducting operations and maintenance activities and for
emergency response. Specifically, Respondent failed to train appropriate
operating personnel to assure they are knowledgeable of its emergency
procedures, and then verify the training’s effectiveness in accordance with
§ 192.615(b)(2), as required by Respondent’s emergency response procedures.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
COMPLIANCE ACTIONS
Pursuant to 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the
actions proposed in the enclosed Notice to correct the violation. The Director may grant an
extension of time to comply with any of the required items upon a written request timely
submitted by the Respondent and demonstrating good cause for an extension. Upon completion



CPF No. 1-2020-011-NOPV
Page 2
of ordered actions, Respondent may request that the Director close the case. Failure to comply
with this Order may result in the assessment of civil penalties under 49 C.F.R. § 190.223 or in
referral to the Attorney General for appropriate relief in a district court of the United States.
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
October 23, 2020
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

12020011NOPV_Closure Letter_10292020_(20-172056)_text.pdf

OVERNIGHT EXPRESS DELIVERY
October 29, 2020
Mr. Richard Redmond
President
DTE Midstream Appalachia, LLC
1000 Noble Energy Drive
Canonsburg, PA 15317
CPF 1-2020-011-NOPV
Dear Mr. Redmond:
On October 23, 2020, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to DTE Midstream Appalachia, LLC a Final Order in the above-referenced case. This Order
included a Compliance Order. Based on our review of the documentation you provided it has been
determined that you have complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration