# GULF SOUTH PIPELINE COMPANY, LLC — Notice of Amendment

- **operation:** document
- **citation:** CPF 12024060NOA
- **title:** GULF SOUTH PIPELINE COMPANY, LLC — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2024-12-20
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.12(c).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-12024060noa.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-12024060noa.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-12024060noa
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/12024060NOA
**body:**

Notice of Amendment involving GULF SOUTH PIPELINE COMPANY, LLC. PHMSA's enforcement data identifies the cited regulation as 192.12(c). The case was opened on 2024-12-20 and is reported as closed as of 2025-05-13. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

12024060NOA_Closure Letter_05132025_(24-296383).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12024060NOA/12024060NOA_Closure%20Letter_05132025_(24-296383).pdf

12024060NOA_Closure Letter_05132025_(24-296383)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12024060NOA/12024060NOA_Closure%20Letter_05132025_(24-296383)_text.pdf

12024060NOA_Notice of Amendment_12202024_(24-296383).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12024060NOA/12024060NOA_Notice%20of%20Amendment_12202024_(24-296383).pdf

12024060NOA_Notice of Amendment_12202024_(24-296383)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/12024060NOA/12024060NOA_Notice%20of%20Amendment_12202024_(24-296383)_text.pdf

12024060NOA_Operator Response to Notice_01172025_(24-296383).pdf: https://primis.phmsa.dot.gov/enforcement-documents/12024060NOA/12024060NOA_Operator%20Response%20to%20Notice_01172025_(24-296383).pdf

12024060NOA_Notice of Amendment_12202024_(24-296383)_text.pdf

NOTICE OF AMENDMENT
OVERNIGHT EXPRESS DELIVERY
December 20, 2024
Mr. Scott Hallam
President and Chief Executive Officer
Gulf South Pipeline Company, LLC
9 Greenway Plaza, Suite 2800
Houston, Texas 77046
CPF 1-2024-060-NOA
Dear Mr. Hallam:
From May 29th
, 2024 to June 13th, 2024 of the inspection, a representative of the Pipeline and
Hazardous Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States
Code (U.S.C.) inspected Gulf South Pipeline Company, LLC’s (Gulf South) procedures for
underground natural storage in Petal and Jackson, Mississippi.
As a result of the inspection, PHMSA has identified an apparent inadequacy found within Gulf
South’s plans or procedures. The item inspected and the inadequacy is described below:
1. § 192.12 Underground natural gas storage facilities.
(a) …
(c) Procedural manuals. Each operator of a UNGSF must prepare and
follow for each facility one or more manuals of written procedures for
conducting operations, maintenance, and emergency preparedness and
response activities under paragraphs (a) and (b) of this section. Each
operator must keep records necessary to administer such procedures and
review and update these manuals at intervals not exceeding 15 months, but
at least once each calendar year. Each operator must keep the appropriate
parts of these manuals accessible at locations where UNGSF work is being
performed. Each operator must have written procedures in place before
commencing operations or beginning an activity not yet implemented.
Gulf South’s written procedures for conducting operations and maintenance activities were
inadequate to ensure safe operation of a pipeline facility. Specifically, Gulf South failed to provide



adequate procedures that describe the process for converting maximum and minimum pressure at
the casing seat to a maximum and minimum wellhead pressure pursuant to API RP 1170, Section
9.1 (Section 9.1).
Section 9.1 states in part that “[m]aximum storage operating pressures shall be established by the
operator. The operator shall then convert the maximum and minimum pressure at the casing seat
to a maximum and minimum wellhead pressure if the wellhead is the monitoring point of record.”
During the inspection, PHMSA reviewed Gulf South’s procedure 1170-9-1 Operating Limits,
effective 05/01/2024, which Gulf South uses for establishing the maximum storage operating
pressure and found that the procedures were inadequate. The provided procedures did not describe
the specific process used by Gulf South to determine the maximum pressure of the cavern.
PHMSA also reviewed the procedures for converting the maximum and minimum pressure at the
casing seat to a maximum and minimum wellhead pressure. The procedures were inadequate and
did not describe the process used to convert these pressures.
Therefore, Gulf South’s written procedures required by § 192.12(c) were inadequate. Gulf South
must revise its procedures to address the deficiency outlined above.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Enforcement
Proceedings.
Please refer to this document and note the response options. Be advised that all material you submit
in response to this enforcement action is subject to being made publicly available. If you believe
that any portion of your responsive material qualifies for confidential treatment under 5 U.S.C. §
552(b), along with the complete original document you must provide a second copy of the
document with the portions you believe qualify for confidential treatment redacted and an
explanation of why you believe the redacted information qualifies for confidential treatment under
5 U.S.C. § 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under § 190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that Gulf South Pipeline Company, LLC maintain documentation
of the safety improvement costs associated with fulfilling this Notice of Amendment



(preparation/revision of plans, procedures) and submit the total to Robert Burrough, Director,
Eastern Region, Pipeline and Hazardous Materials Safety Administration. In correspondence
concerning this matter, please refer to CPF 1-2024-060-NOA and, for each document you submit,
please provide a copy in electronic format whenever possible.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Enforcement Proceedings

12024060NOA_Closure Letter_05132025_(24-296383)_text.pdf

VIA ELECTRONIC MAIL TO: scott.hallam@bwpipelines.com
May 13, 2025
Mr. Scott Hallam
President and Chief Executive Officer
Gulf South Pipeline Company, LLC
9 Greenway Plaza, Suite 2800
Houston, Texas 77046
CPF 1-2024-060-NOA
Dear Mr. Hallam:
From May 29th, 2024 to June 13th, 2024, a representative of the Pipeline and Hazardous Materials
Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code (U.S.C.)
inspected Gulf South Pipeline Company, LLC’s (Gulf South) procedures for underground natural
storage in Petal and Jackson, Mississippi. As a result of the inspection, Gulf South was issued a
Notice of Amendment on December 20, 2024.
Gulf South Pipeline Company, LLC submitted its amended procedures on January 17, 2025. My
staff reviewed the amended procedures, and it appears that the inadequacies outlined in this Notice
of Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Robert Burrough
Director, Eastern Region
Pipeline and Hazardous Materials Safety Administration