# SOURCEGAS ARKANSAS INC. — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 220023001
- **title:** SOURCEGAS ARKANSAS INC. — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2002-02-14
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 193.2503, 193.2605(a), 193.2619(c)(2), 193.2713(a)(2)(ii), 193.2719(a)(2).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-220023001.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-220023001.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-220023001
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/220023001
**body:**

Notice of Probable Violation involving SOURCEGAS ARKANSAS INC.. PHMSA's enforcement data identifies the cited regulations as 193,  193.2503,  193.2605(a),  193.2619(c)(2),  193.2713(a)(2)(ii),  193.2719(a)(2). The case was opened on 2002-02-14 and is reported as closed as of 2002-12-19. Proposed civil penalty: $6,000. Assessed civil penalty: $6,000. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

220023001_Final Order_12032002.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220023001/220023001_Final%20Order_12032002.pdf

220023001_Final Order_12032002.pdf

U.S Deoortrnent
of Tronsponotion
Reseorshqnd
SpeelolDrrg;crns Adrninlsfrcllon
400 Sevenlh Sfeel, S.W
Washington. D.C 20590
DEC - 3 l;11;
Mr. Charles Stevens
Vice President Transmission Operations
Arkansas Western Gas Company
1001 Sain Street
Fayetteville, AR 72703
Re: CPFNo.2-2002-3001
Dear Mr. Stevens:
Enclosed is the Final Order issued by the Associate Administrator for Pipeline Safety in the
above-referenced case. It makes findings ofviolation and assesses a civil penalty of$6,000. The
penalty payment terms are set forth in the Final Order. This enforcement action closes automatically
upon payment. Your receipt ofthe Final Order constitutes service of that document under 49 C.F.R.
$ l eO.s.
Sincerely,
Gwendolvn M.
Pipeline Compliance Registry
Office of Pipeline Safety
Enclosure
CERTIFIED MAIL - RETURN RECEIPT REOUESTED



DEPARTMENT OF TRANSPORTATION
RESEARCH AND SPECIAL PROGRAMS ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON. DC 20590
In the Matter of
Arkansas Westem Gas Company,
Respondent.
CPF No. 2-2002-3001
FINAL ORDER
On November l3 through 15, 2001, pursuant to 49 U.S.C. $ 60117, a representative of the Office
ofPipeline Safety (OPS) conducted an on-site pipeline safety inspection ofRespondent's facilities
and records near Blytheville, Arkansas. As a result ofthe inspection, the Director, Southem Region,
OPS, issued to Respondent, by letter dated February 14,2002, a Notice of Probable Violation and
Proposed Civil Penalty (Notice). In accordance with 49 C.F.R. $ 190.207, the Notice proposed
finding that Respondent had committed violations of 49 C.F.R. Part 193 and proposed assessing a
civil penalty of $6,000 for the alleged violations.
Respondent responded to the Notice by letter dated March 7, 2002 (Response). Respondent did not
contest the allegations of violation but provided information conceming the corrective actions it has
taken and requested mitigation of the proposed civil penalty. Respondent did not request a hearing;
consequently, Respondent waived its right to one.
FINDINGS OF VIOT,ATION
Uncontested ltem
Respondent did not contest the alleged violation of Item 3b in the Notice. Accordingly, I find that
Respondent violated the following section of 49 C.F.R. Part 193, as more fully described in the
Notice:
49 C.F.R. $ 193.2619 -- failing to inspect and test control systems intended for fire protection at
regular intervals not to exceed 6 months. Respondent exceeded the 6 month interval by 2 months
and 23 days.
This frnding ofviolation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.



ASSESSMENT OF PENALTY
Under 49 U.S.C. $ 60122, Respondent is subject to a civil penalty not to exceed $25,000 per
violation for each day of the violation up to a maximum of $500,000 for any related series of
violations.
49 U.S.C. S 60122 and 49 C.F.R. $ 190.225 require that, in determining the amount of the civil
penalty, I consider the following criteria: nature, circumstances, and gravity of the violation, degree
of Respondent's culpability, history of Respondent's prior offenses, Respondent's ability to pay the
penalty, good faith by Respondent in attempting to achieve compliance, the effect on Respondent's
ability to continue in business, and such other matters as justice may require.
In response to Item 3b, Respondent requested reduction or elimination of the proposed $6,000 civil
penalty for violation of 49 C.F.R. $ 193.2619(c)(2). Although Respondent agrees that the 6 month
maximum time interval between fire protection control system tests had been exceed, Respondent
contends that the system was "found to be in good working order" when tested, has historically
performed normally during testing, and no risk to persons or property actually existed, and thus, the
$6000 penalty should be eliminated or reduced.
The fact that no risk to person or property 4ctually existed is not a basis for reduction ofthe penalty.
It is altogether possible that the late testing would have shown that a risk did exist. The purpose of
$ 193.2619(c)(2) is to ensure that fire control systems will be fully functional and effective in the
event that a fire does occw. Where testing is not performed at regular intervals, as was the case here,
there is no way to verifr that fue control systems will function adequately. While eventual testing
revealed that the fire control systems were adequately frrnctional, there was no way outside of actual
testing of the system to determine whether the fire control system would work. Demonstrating the
historical functionality ofthe fire control system assures neither Respondent nor OPS that the system
is currently functional. Testing ofthe system occurred 2 months and 23 days past the expiration of
the 6 month interval, in violation of $ 193.2619(c)(2). Accordingly, having reviewed the record and
considered the assessment criteria, I assess Respondent a civil penalty of$6,000.
Payment of the civil penalty must be made within 20 days of service. Payment can be made by
sending a certified check or money order (containing CPF No. 2-2002-3001) payable to "U.S.
DepartmentofTransportation" to the Federal Aviation Administration, Mike MonroneyAeronautical
Center, Financial Operations Division (ANIZ-320),P.O. Box 25770, Oklahoma City, OK 73125'
Federal regulations (49 C.F.R $ 89.21(bX3)) also permit this payment to be made by wire transfer,
throughthe Federal Reserve Communications System (Fedwire), to the accountoftheU.S. Treasury.
Detailed instructions are contained in the enclosure, After completing the wire transfer, send a copy
of the electronic funds transfer receipt to the Office of the Chief Counsel (DCC- I ), Research and
Special Programs Administration, Room 8407, U.S. Department of Transportation, 400 Seventh
Street, SW, Washington, DC 20590-0001.



J
Questions concerning wire transfers should be directed to: Financial Operations Division (AMZ-
120), Federal Aviation Administration, Mike Monroney Aeronautical Center, P.O. Box 25770,
Oklahoma City, OK 73125; (405) 954-47t9.
Failure to pay the $6,000 civil penalty will result in accrual of interest at the current annual rate in
accordance with 31 U.S.C. 53717,31 C.F.R. $ 901.9 and 49 c.F.R. $ 89.23. Pursuant to those same
authorities, a late penalty charge of six percent (6%) per annum will be charged if payment is not
made within 110 days of service. Furthermore, failure to pay the civil penalty may result in refenal
of the matter to the Attomey General for appropriate action in an United States District Court.
WARNINGITEMS
The Notice did not propose a civil penalty or corrective action for Items 1,2,3a,4 and 5, but warned
Respondent that it should take appropriate conective action to correct the items. Respondent
presented information in its response showing that it has addressed the cited items. Respondent is
again warned that if OPS finds a violation in a subsequent inspection, enforcement action will be
taken.
Item I in the Notice alleges that Respondent failed to follow its manual ofwritten procedures for fire
prevention (49 C.F.R. $ 193.2503).
Item 2 in the Notice alleges that Respondent failed to perform electric and diesel fire water pump
start-up testing on a monthly basis, in accordance with 49 C.F.R. $ 193.2605.
Item 3a in the Notice alleges that Respondent failed to timely inspects its alam and fire detections
control systems, exceeding the 6 month interval by 25 days (49 C.F.R. g 193.2619(c)).
Item 4 in the Notice alleges that Respondent failed to provide a written initial training plan for
operation and maintenance instruction of applicable new personnel (49 c.F.R. $ 193.2713).
Item 5 in the Notice alleges that Respondent failed to keep a system of records showing that
personnel have undergone and satisfactorily completed continuing instruction in operations and
maintenance for the years 1999, 2000, and 2001 through November 14, 2001. Respondent also
failed to keep records of continuing instnrction in plant security for the years I 999 and 2000
(49 C.F.R. $ 193.2719).
Under 49 C.F.R. $ 190.215, Respondent has a right to petition for reconsideration of this Final
Otder. However, upon payment of the civil penalty, the case closes automatically and Respondent
waives the right to petition for reconsideration. The filing of the petition automatically stays the



4
payment ofany civil penalty assessed. The petition must be received within 20 days ofRespondent's
receipt of this Final Order and must contain a brief statement of the issue(s). The terms and
conditions ofthis Final Order are effective on receipt.
liLr.: 3 I ll)?
Date Issued
Stacey Gerard
Associate Administrator
for Pipeline Safety