# DIXIE PIPELINE COMPANY LLC — Notice of Amendment

- **operation:** document
- **citation:** CPF 220025011M
- **title:** DIXIE PIPELINE COMPANY LLC — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2002-05-06
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 195.452(b)(6)(ii).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-220025011m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-220025011m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-220025011m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/220025011M
**body:**

Notice of Amendment involving DIXIE PIPELINE COMPANY LLC. PHMSA's enforcement data identifies the cited regulation as 195.452(b)(6)(ii). The case was opened on 2002-05-06 and is reported as closed as of 2004-12-23. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

220025011M_Order Directing Amendment_10232002.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220025011M/220025011M_Order%20Directing%20Amendment_10232002.pdf

220025011m_order directing amendment_10232002_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220025011M/220025011m_order%20directing%20amendment_10232002_text.pdf

cpf_2_2004_5017H.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220025011M/cpf_2_2004_5017H.pdf

220025011m_order directing amendment_10232002_text.pdf

O
US. Department
of Transportation
Research and
Special Programs
Administration
a00 Seventh Street, S W
Waahrnglnn, 0. C 20590
UCf 23 ii)Jl
Mr. Christopher Girrens
Vice President & General Manager
Dixie Pipeline Company
1117 Perimeter Center West
Suite 301
Atlanta, GA 30338
Re: CPF No. 2-2002-5011M
Dear Mr. Girrens:
Enclosed is the Order Directing Amendment issued by the Associate Administrator for
Pipeline Safety in the above-referenced case. It makes a finding of inadequate procedures and
requires that you amend your integrity management program procedures. When the terms of the
Order are completed, as determined by the Director, Southern Region, OPS, this enforcement action
will be closed. Your receipt of the Order Directing Amendment constitutes service of that document
under 49 C. F. R. I't 190. 5.
Owsnklyn M.
Pipeline Compliance Registry
Office of Pipeline Safety
Enclosure
CERTIFIED MAIL - RETURN RECEIPT RE UESTED
ZOV OS 2%



DEPARTMENT OF TRANSPORTATION
RESEARCH AND SPECIAL PROGRAMS ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
In the Matter of )
)
Dixie Pipeline Company, )
)
Respondent. )
CPF No. 2-2002-5011M
ORDER IRECTING AMENDMENT
During March 20-21, representatives of the Western and Southern Regions, Office of Pipeline Safety
(OPS), inspected Dixie Pipeline Company's (Respondent) integrity management program at
Respondent's facility in Atlanta, Georgia. As a result of the inspection, the Southern Regional
Director, OPS, issued to Respondent, by letter dated May 6, 2002, a Notice of Amendment (NOA).
The NOA alleged inadequacies in Respondent's integrity management program and proposed to
require amendment of Respondent's procedures to comply with the requirements of 49 C. F. R.
tj 195. 452(b).
Respondent responded to the NOA by letter dated June 5, 2002. Respondent did not contest the
allegations set forth in the NOA and did not request a hearing; consequently, Respondent waived its
right to one. However, Respondent described the actions it is taking to address the inadequacies in
its procedures that were identified in the NOA.
Accordingly, I find that Respondent's integrity management program procedures are inadequate to
ensure safe operation of its pipeline system. Pursuant to 49 U. S. C. $ 60108(a) and 49 C. F. R.
tj 190. 237, Respondent is ordered to make the following changes to its integrity management
program procedures. Respondent must-
l. Amend the procedures for identifying segments that could affect a high consequence area
to consider the zone beyond the high consequence area boundary and the pipeline
intersect.
2. Consider in its technical justification that non commercial navigable waterways, such as
streams, may act as a transport path beyond the 1/2-mile buffer for a highly volatile liquid
release.



3. Amend its segment identification process to include the most current ecological data in
the National Pipeline Mapping System.
4. Submit the amended procedures to the Regional Director, Southern Region, OPS within
30 days after receipt of this Order Directing Amendment.
5. The Regional Director may extend the period for complying with the required items if the
Respondent requests an extension and adequately justifies the reasons for the extension.
The terms and conditions of this Order Directing Amendment are effective upon receipt.
Failure to comply with this Order may result in the assessment of civil penalties of up to $25, 000 per
violation per day, or in the referral of the case for judicial enforcement.
OCT 2 3 2002
Date
Qacey Qasard
Associate Administrator
for Pipeline Safety