# CLYDEBANK ROYAL STEWART ARMS — Warning Letter

- **operation:** document
- **citation:** CPF 220130017W
- **title:** CLYDEBANK ROYAL STEWART ARMS — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2013-05-02
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.455(a)(2), 192.457(b)(3), 192.481(a), 192.625(f), 192.721, 192.747.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-220130017w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-220130017w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-220130017w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/220130017W
**body:**

Warning Letter involving CLYDEBANK ROYAL STEWART ARMS. PHMSA's enforcement data identifies the cited regulations as 192.455(a)(2),  192.457(b)(3),  192.481(a),  192.625(f),  192.721,  192.747. The case was opened on 2013-05-02 and is reported as closed as of 2013-05-02. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

220130017W_warning letter_05022013.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220130017W/220130017W_warning%20letter_05022013.pdf

220130017W_warning letter_05022013_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/220130017W/220130017W_warning%20letter_05022013_text.pdf

220130017W_warning letter_05022013_text.pdf

WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
May 2, 2013
Ms. Sharon Wilson
Property Manager
Clydebank Royal Stewart Arms
1 Royal Stewart Parkway
Dunedin, FL 34698
CPF 2-2013-0017W
Dear Ms. Wilson:
On March 19, 2013, representatives of the Pipeline and Hazardous Materials Safety
Administration (PHMSA), Southern Region, Office of Pipeline Safety, pursuant to Chapter
601 of 49 United States Code, inspected the Clydebank Royal Stewart Arms master meter and
downstream piping and facilities at 1 Royal Stewart Parkway, Dunedin, Florida.
As a result of the inspection, it appears that Clydebank Royal Stewart Arms has committed
probable violations of the Pipeline Safety Regulations, Title 49, Code of Federal Regulations.
The items inspected and the probable violations are as follows:
1. §192.455 External corrosion control: Buried or submerged pipelines installed after
July 31, 1971.
(a) Except as provided in paragraphs (b), (c), and (f) of this section, each buried or
submerged pipeline installed after July 31, 1971, must be protected against external
corrosion, including the following:
... (2) It must have a cathodic protection system designed to protect the pipeline in
accordance with this subpart, installed and placed in operation within 1 year after
completion of construction.
Clydebank Royal Stewart Arms did not install, and place in operation within one year
after completion of construction, a cathodic protection system designed to protect a buried
pipeline against external corrosion.
Clydebank Royal Stewart Arms has 1480 feet of 2-6-inch BIW coated buried pipe. Some
of this pipe was installed after July 3, 1971, but Clydebank Royal Stewart Arms has not
installed a cathodic protection system designed to protect the pipeline against external
corrosion.



If the pipeline is located: Onshore Offshore 2. §192.457 External corrosion control: Buried or submerged pipelines installed
before August 1, 1971.
…. (b) Except for cast iron or ductile iron, each of the following buried or
submerged pipelines installed before August 1, 1971, must be cathodically protected
in accordance with this subpart in areas in which active corrosion is found:
…. (3) Bare or coated distribution line.
Clydebank Royal Stewart Arms has 1480 feet of 2-6-inch BIW coated buried pipe. Some
of this pipe was installed before August 1, 1971, but Clydebank Royal Stewart Arms has
not installed a cathodic protection system designed to protect the pipeline against external
corrosion. Moreover, Clydebank Royal Stewart Arms did not present to the PHMSA
inspector any records to demonstrate that there are no areas of active corrosion on these
lines. The methods and required time intervals an operator must use to determine if areas
of active corrosion exist on its pipelines are described in §192.465(e).
3. §192.481 Atmospheric corrosion control: Monitoring.
(a) Each operator must inspect each pipeline or portion of pipeline that is exposed to
the atmosphere for evidence of atmospheric corrosion, as follows:
Then the frequency of inspection is:
At least once every 3 calendar years, but with
intervals not exceeding 39 months
At least once each calendar year, but with intervals
not exceeding 15 months
... (c) If atmospheric corrosion is found during an inspection, the operator must
provide protection against the corrosion as required by Sec. 192.479.
Clydebank Royal Stewart Arms did not inspect its onshore pipeline exposed to the
atmosphere for evidence of atmospheric corrosion at least once every 3 calendar years, but
with intervals not exceeding 39 months. Moreover, Clydebank Royal Stewart Arms did
not provide protection against atmospheric corrosion in accordance with §192.479, which
requires pipelines to be properly cleaned and coated to prevent atmospheric corrosion.
The PHMSA inspector observed and photographed master meter with associated piping
that showed signs of atmospheric corrosion. This portion of pipeline had not been
properly cleaned and coated to prevent atmospheric corrosion.
4. §192.625 Odorization of gas.
... (f) To assure the proper concentration of odorant in accordance with this section,
each operator must conduct periodic sampling of combustible gases using an
instrument capable of determining the percentage of gas in air at which the odor
becomes readily detectable. Operators of master meter systems may comply with
this requirement by-
(1) Receiving written verification from their gas source that the gas has the proper
2



concentration of odorant; and
(2) Conducting periodic "sniff" tests at the extremities of the system to confirm that
the gas contains odorant.
Clydebank Royal Stewart Arms did not present to the PHMSA inspector any records to
demonstrate that it had assured the proper concentration of odorant in its pipeline system
by receiving written verification from its gas source that the gas has the proper
concentration of odorant or by conducting periodic "sniff" tests at the extremities of the
system to confirm that the gas contains odorant.
5. §192.721 Distribution systems: Patrolling.
(a) The frequency of patrolling mains must be determined by the severity of the
conditions which could cause failure or leakage, and the consequent hazards to
public safety.
(b) Mains in places or on structures where anticipated physical movement or
external loading could cause failure or leakage must be patrolled -
(1) In business districts, at intervals not exceeding 4 1/2 months, but at least four
times each calendar year; and
(2) Outside business districts, at intervals not exceeding 7 1/2 months, but at least
twice each calendar year.
Clydebank Royal Stewart Arms did not present to the PHMSA inspector any records to
show it patrolled its distribution system in the residential area at intervals not exceeding
7½ months, but at least twice each calendar year.
6. §192.747 Valve maintenance: Distribution systems.
(a) Each valve, the use of which may be necessary for the safe operation of a
distribution system, must be checked and serviced at intervals not exceeding 15
months, but at least once each calendar year.
(b) Each operator must take prompt remedial action to correct any valve found
inoperable, unless the operator designates an alternative valve.
Clydebank Royal Stewart Arms did not present to the PHMSA inspector any records to
demonstrate that it had checked and serviced its shut off (or key valve) which may be
necessary for the safe operation of its distribution system at intervals not exceeding 15
months, but at least once each calendar year.
Under 49 United States Code, §60122, Clydebank Royal Stewart Arms is subject to a civil
penalty not to exceed $200,000 per violation per day the violation persists up to a maximum
of $2,000,000 for a related series of violations. For violations occurring prior to
January 4, 2012, the maximum penalty may not exceed $100,000 per violation per day, with a
maximum penalty not to exceed $1,000,000 for a related series of violations. We have
reviewed the circumstances and supporting documents involved in this case and have decided
not to conduct additional enforcement action or penalty assessment proceedings at this time.
We advise you to correct the items identified in this letter. Failure to do so will result in the
Clydebank Royal Stewart Arms being subject to additional enforcement action.
3



No reply to this letter is required. If you choose to reply, in your correspondence please refer
to CPF 2-2013-0017W. Be advised that all material you submit in response to this
enforcement action is subject to being made publicly available. If you believe that any
portion of your responsive material qualifies for confidential treatment under 5 U.S.C. 552(b),
along with the complete original document you must provide a second copy of the document
with the portions you believe qualify for confidential treatment redacted and an explanation of
why you believe the redacted information qualifies for confidential treatment under 5 U.S.C.
552(b).
Sincerely,
Wayne T. Lemoi
Director, Office of Pipeline Safety
PHMSA Southern Region
4
- **truncated:** false
- **body characters:** 8816
