# VIKING GAS TRANSMISSION CO — Corrective Action Order

- **operation:** document
- **citation:** CPF 320061015H
- **title:** VIKING GAS TRANSMISSION CO — Corrective Action Order
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2006-08-04
- **effective on:** Not available
- **summary:** CLOSED corrective action order.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-320061015h.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-320061015h.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-320061015h
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/320061015H
**body:**

Corrective Action Order involving VIKING GAS TRANSMISSION CO. The dataset does not identify a cited regulation for this case. The case was opened on 2006-08-04 and is reported as closed as of 2012-05-31. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320061015H_Closure Letter_05312012.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320061015H/320061015H_Closure%20Letter_05312012.pdf

320061015H_Closure Letter_05312012_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320061015H/320061015H_Closure%20Letter_05312012_text.pdf

CPF_NO_3-2006-1015H.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320061015H/CPF_NO_3-2006-1015H.pdf

320061015H_Closure Letter_05312012_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
May 31, 2012
Mr. Michel Nelson
Senior Vice President – Natural Gas Pipelines
ONEOK Partners, L.P.
100 West 5th Street
Tulsa, Oklahoma 74103-4240
CPF 3-2006-1015H
Dear Mr. Nelson:
On August 4, 2006, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Viking Gas Transmission Company a Corrective Action Order in the above-
referenced case. Based on our review of the documentation you provided, it has been
determined that you complied with the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to
the matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
David Barrett
Director, Central Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false
- **body characters:** 1580