# NATURAL GAS PIPELINE CO OF AMERICA (KMI) — Warning Letter

- **operation:** document
- **citation:** CPF 320071005W
- **title:** NATURAL GAS PIPELINE CO OF AMERICA (KMI) — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2007-01-30
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.743(b).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-320071005w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-320071005w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-320071005w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/320071005W
**body:**

Warning Letter involving NATURAL GAS PIPELINE CO OF AMERICA (KMI). PHMSA's enforcement data identifies the cited regulation as 192.743(b). The case was opened on 2007-01-30 and is reported as closed as of 2007-01-30. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320071005W_Warning Letter_01302007.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320071005W/320071005W_Warning%20Letter_01302007.pdf

320071005W_Warning Letter_01302007.pdf

@
U.S. DeDortment
of Tronsporfotion
Pipeflne ond
Hozordou3 tYloteriots gotely
Adminisfrqflon
901 Locust Sf6et, Suite /162
Kansas City, MO 64106-2641
WARNING LETTER
CERTIF'IED MAIL - RETURN RECEIPT REOUESTED
January 30,2007
Mr. M. Dwayne Burton
V.P. Gas Pipelines
Kinder Morgan GP, Inc.
500 Dallas St. (One Allen Center)
Houston, TX 77002
cPF 3-2007-100sw
Dear Mr. Burton:
On September 18-22, September 25-28, October 16-19 and October 23-26,2006, a
representative of the Pipeline and Hazardous Materials Safety Administration (PHMSA)
pursuant to Chapter 601 of49 United States Code inspected your records and facilities for
Kinder Morgan GP, Irc's Natural Gas Pipeline Company of America O\IGPL) pipelines in
Missouri and Illinois.
As a result of the inspection, it appears that you have committed a probable violation of the
Pipeline Safety Regulations, Title 49, Code of Federal Regulations. The item inspected and
the probable violation is:
1. $192.743 Pressure limiting and regulating stations: Capacity of relief devices.



(b) If review and calculations are used to determine if a device has sufficient
capacity, the-calculated capacity must be compared with the rated or
experimentally determined relieving capacity of the deyice for the conditions
under which it operates. After the initial calculations, subsequdnt calculations
need not be made if the annual review documents that parameters haYe not
changed to cause the rated or experimentally determined relieving capacity to be
insufficient.
The PHMSA representative reviewed relief capacity documentation at two locations that was
determined to be inaccurate as follows:
r At Hammond, on the Lovington, Illinois M&R station, the relief valve capacity was
calculated at a set point of500 psig when it should have been calculated at a set point
of 95 psig. NGPL personnel re-calculated the capacity at the correct set point and
found that the relief valve capacity was still adequate for this application.
o At Hammond, on the GMW 2800 HP compressors, the relief valve capacity was not
accurately calculated because the specific orifice size was not identified. NGPL
personnel determined the actual orifice size in the reliefvalve, recalculated the
capacity and the relief valve was found to be adequately sized.
Under 49 United States Code, 5 60122, you are subject to a civil penalty not to exc.eed
$100,000 for each violation for each day the violation persists up to a maximum of
$1,000,000 for any related series of violations. We have reviewed the circumstances and
supporting documents involved in this case, and have decided not to conduct additional
enforcement action or penalty assessment proceedings at this time. We advise you to correct
the item identified in this letter. Be advised that failure to do so will result in NGPL beine
subject to additional enforcement action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer
to CPF 3-2007-1005W.
Sincerelv.
tfur"#tmae'
Director, Central Region
Pipeline and Hazardous Materials Safety Adminishation