# MARATHON PIPE LINE LLC — Corrective Action Order

- **operation:** document
- **citation:** CPF 320145005H
- **title:** MARATHON PIPE LINE LLC — Corrective Action Order
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2014-07-24
- **effective on:** Not available
- **summary:** CLOSED corrective action order.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-320145005h.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-320145005h.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-320145005h
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/320145005H
**body:**

Corrective Action Order involving MARATHON PIPE LINE LLC. The dataset does not identify a cited regulation for this case. The case was opened on 2014-07-24 and is reported as closed as of 2017-08-04. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

320145005H_Closure Letter_08042017.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320145005H/320145005H_Closure%20Letter_08042017.pdf

320145005H_Closure Letter_08042017_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320145005H/320145005H_Closure%20Letter_08042017_text.pdf

320145005H_Corrective Action Order_07242014.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320145005H/320145005H_Corrective%20Action%20Order_07242014.pdf

320145005H_Corrective Action Order_07242014_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/320145005H/320145005H_Corrective%20Action%20Order_07242014_text.pdf

320145005H_Closure Letter_08042017_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
August 4, 2017
Timothy J. Aydt
President
Marathon Pipe Line LLC
539 South Main Street
Findlay, Ohio 45840
CPF 3-2014-5005H
Dear Mr. Aydt:
On July 24, 2014, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Marathon Pipe Line LLC a Corrective Action Order in the above-referenced case.
This Order included a requirement to take corrective actions on your pipeline. Based on our
review of the documentation you provided it has been determined that you have complied with
the terms of this Order.
Accordingly, this case is now closed and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Allan C. Beshore
Director, Central Region, OPS
Pipeline and Hazardous Materials Safety Administration

320145005H_Corrective Action Order_07242014_text.pdf

JULY 24, 2014
VIA CERTIFIED MAIL AND FAX TO: 419-421-3125
Mr. Craig O. Pierson
President
Marathon Pipe Line LLC
539 South Main Street
Findlay, Ohio 45840
CPF No. 3-2014-5005H
Dear Mr. Pierson:
Enclosed is a Corrective Action Order. It finds that continued operation of the Marathon Pipe
Line (MPL) Patoka facility would be hazardous to life, property, and the environment without
immediate corrective action. The Corrective Action Order requires you to take certain corrective
actions to protect the public, property, and the environment in connection with the leak at the
MPL Patoka Station facility that was reported to the National Response Center on June 29, 2014.
Service is being made by certified mail and facsimile. Your receipt of this Corrective Action
Order constitutes service of that document under 49 C.F.R. § 190.5. The terms and conditions of
this Order are effective upon receipt.
We look forward to the successful resolution of the concerns arising out of this leak to ensure the
safe operation of the pipeline systems. Please direct any questions on this matter to Karen
Butler, Supervisor of the Accident Team, Central Region, OPS, at (816) 329-3835.
Sincerely,
Jeffrey D. Wiese
Associate Administrator
for Pipeline Safety
Enclosure: Corrective Action Order and Copy of 49 C.F.R. §190.233
cc: Ms. Linda Daugherty, Deputy Associate Administrator for Field Operations, OPS
Mr. Randy Bishop, Regulatory and Compliance Supervisor, Marathon Pipe Line LLC



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Marathon Pipe Line LLC, ) CPF No. 3-2014-5005H
)
)
)
Respondent. )
____________________________________)
CORRECTIVE ACTION ORDER
Purpose and Background
This Corrective Action Order (Order) is being issued, under authority of 49 U.S.C. § 60112, to
Marathon Pipe Line LLC (Marathon or Respondent), the operator of the Patoka Station pipeline
facility located in Marion County, Illinois. The Patoka Station pipeline facility consists of main
line, breakout tanks, piping, pumps, equipment, and related support facilities. Marathon also
operates multiple crude oil pump stations and tank farms throughout the PHMSA Central
Region. The Marathon Patoka Station facility receives crude oil from the Roxana to Patoka,
Woodpat, and Capline Patoka pipelines, stores crude oil in 12 breakout tanks, and transports
crude oil on the Patoka to Martinsville, Patoka to Owensboro, and Patoka to Robinson pipelines.
This Order finds that continued operation of the Patoka Station facility without corrective action
would be hazardous to life, property, or the environment and requires Respondent to take
immediate action to ensure the safe operation of the pipeline facility.
On June 29, 2014, Respondent reported to the National Response Center a leak at its Patoka
Station near Patoka, Illinois in Marion County. Respondent estimates the volume of the product
spill to be approximately 1,126 barrels of crude oil.
Pursuant to 49 U.S.C. § 60117, the Pipeline and Hazardous Materials Safety Administration
(PHMSA), Office of Pipeline Safety (OPS), initiated an investigation of the failure. OPS
determined that the release originated from the Patoka Station facility, and the apparent cause of
the leak is internal corrosion of pipe utilized in moving product in and out of Tank 1284. The
preliminary findings of the investigation are as follows:
Preliminary Findings
• At approximately 04:45 AM CDT on June 29, 2014, Respondent discovered a leak at its
Marathon Patoka Station facility.



2
• A Marathon employee was called out to respond to a high salt-water alarm the morning
of June 29, 2014, and identified the leak. The employee called back to the control room
and indicated that a leak was present. The control room shutdown the incoming and
outgoing pipelines. Employees isolated Tank 1284 and stopped the leak.
• The leak was reported by Marathon to the National Response Center at 07:13 AM EDT
on June 29, 2014 (NRC report # 1087454).
• The town of Vernon, Illinois is located approximately 1/4 mile north of the facility and
the town of Patoka, Illinois is located 1-1/2 miles south of the facility.
• The leak occurred at the Marathon Patoka Station facility located in a rural area of South
Central Illinois and is adjacent to Illinois State Highway 51. The facility is in an
Unusually Sensitive Area (USA) associated with drinking water. However, no drinking
water is known to have been impacted by the spill.
• Various state and federal agencies, including the U.S. Environmental Protection Agency,
assisted with initial activities to contain the crude oil. Those activities included, but were
not limited to a road closure, site assessment, and reporting.
• The spilled amount is reported to be approximately 1,126 barrels. The crude oil covered
a large portion of the Marathon facility and migrated offsite to an Illinois State Highway
51 roadside ditch.
• The cause of the leak is under investigation, but appears to be two holes in piping
associated with Tank 1284.
• The leak’s origins are located in a section of 20” diameter, 0.375” wall thickness pipe
installed in 2012. Two holes in the pipe were observed at the 6 o’clock position
approximately 9 feet apart and involved more than one joint of pipe.
• Visual examination of the holes suggests internal corrosion as the apparent cause of the
leaks.
• Based on PHMSA’s experience with piping involved in internal corrosion failures in
general, perforations of a 0.375” wall thickness pipe installed in 2012 indicate a very
aggressive corrosion rate.
• In 2008, PHMSA issued an Advisory Bulletin ADB-08-08 entitled “Proper Identification
of Internal Corrosion Risk.” In this Advisory Bulletin, PHMSA emphasized to the
regulated community its responsibilities with respect to determining the need for internal
corrosion preventive and mitigative measures.
• Not including this latest leak at Patoka, since 2008 Marathon has reported to PHMSA six
crude oil leaks associated with internal corrosion. These six leaks resulted in the reported
spill volume of 447 barrels of crude oil.
• At PHMSA’s request prior to this failure, Marathon Pipe Line, LLC had designed and
committed to engage in an improvement plan for internal corrosion threat mitigation.
The implementation of this improvement plan however had not resulted in the direct
assessment of the area that failed in the Patoka Station.



3
• Marathon Pipe Line, LLC has reported a specific leak history of the following at Patoka
Station:
o 3/26/2012 Seal Failure of 1.6 barrels
o 3/30/2011 Mixer Seal Failure of 0.15 barrels
o 11/10/2004 Bracket weld failure of 38 barrels
o 11/10/2004 Internal Corrosion failure of 40 barrels
o 7/10/2003 Equipment Failure of 10 barrels
• As a result of a 2013 leak due to internal corrosion of a crude oil relief line at the
Marathon Martinsville, Illinois facility, Marathon committed to conducting a system-
wide analysis of the threat of internal corrosion to its facilities and was working on
updating internal corrosion plans, procedures, and processes.
• MPL does have a Direct Assessment program. The failed pipe had not received a Direct
Assessment survey according to the operator. One other location at the Patoka facility
had a repair sleeve installed in May of 2014 (defect was reported to have been found as
48% thru wall). This repair sleeve was installed as a result of the Direct Assessment
program and improvements as previously committed to PHMSA.
• The accident investigation is ongoing.
Determination of Necessity for Corrective Action Order and Right to Hearing
Under 49 U.S.C. § 60112 and 49 C.F.R. § 190.233, the Associate Administrator for Pipeline
Safety (Associate Administrator) may issue a corrective action order after providing reasonable
notice and the opportunity for a hearing if he finds that a particular pipeline facility is or would
be hazardous to life, property, or the environment. The terms of such an order may include the
suspended or restricted use of a pipeline facility, physical inspection, testing, repair, replacement,
or any other action as appropriate. The Associate Administrator may also issue a corrective
action order without providing any notice or the opportunity for a hearing if he finds that a
failure to do so expeditiously will result in likely serious harm to life, property or the
environment. The opportunity for a hearing will be provided as soon as practicable after the
issuance of the CAO in such cases.
After evaluating the foregoing preliminary findings of fact, I find that the continued operation of
the pipeline without corrective measures would be hazardous to life, property and the
environment. Additionally, after considering the age of the failed pipe and Marathon’s failure
history, circumstances surrounding this leak, the proximity of the pipeline to populated areas,
water bodies, drinking water resources, public roadways, and high consequence areas, the
hazardous nature of the product the pipeline transports, and the ongoing investigation to
determine the cause of the failure, I find that a failure to issue this Order expeditiously to require
immediate corrective action would likely result in serious harm to life, property, and the
environment.
Accordingly, this Corrective Action Order is issued without prior notice and opportunity for a
hearing. The terms and conditions of this Order are effective upon receipt.



4
Within 10 days of receipt of this Order, Respondent may request a hearing, to be held as soon as
practicable, by notifying the Associate Administrator for Pipeline Safety in writing, delivered
personally, by mail or by fax at (202) 366-4566. The hearing will be held in Kansas City,
Missouri, on a date that is mutually convenient to PHMSA and Respondent.
After receiving and analyzing additional data in the course of this investigation, PHMSA may
identify other corrective measures that need to be taken. Respondent will be notified of any
additional measures required and amendment of this Order will be considered. To the extent
consistent with safety, Respondent will be afforded notice and an opportunity for a hearing prior
to the imposition of any additional corrective measures.
Required Corrective Action
Pursuant to 49 U.S.C. § 60112, Marathon Pipe Line LLC is ordered to immediately take the
following corrective actions to ensure the safe operation of the Patoka Station facilities and any
other facilities determined to be susceptible to internal corrosion:
1. Within 60 days of receipt of this Order, complete 3rd party mechanical and metallurgical
testing and failure analysis of the failed pipe, including analysis of soil samples,
corrosion products, and any foreign materials if applicable. The testing and analysis shall
be completed as follows:
A. Document the chain-of-custody when handling and transporting the failed pipe section
and other evidence from the failure site;
B. Submit and utilize mechanical and metallurgical testing protocols as approved by the
Director, Central Region;
C. Prior to commencing the mechanical and metallurgical testing, provide the Regional
Director with the scheduled date, time, and location of the testing to allow a PHMSA
representative to witness the testing; and
D. Ensure that the testing laboratory distributes all resulting reports in their entirety
(including all media), whether draft or final, to the Regional Director at the same time
as they are made available to Respondent.



5
2. Within 90 days following receipt of this order, submit an Integrity Work Plan (IWP) to
the Director, Central Region, OPS for approval. The plan must provide for the
verification of the integrity of the Patoka Station piping and must address all factors
known or suspected in the leak of June 29, 2014, including, but not be limited to the
integration of information from the following:
A. Complete a root cause failure analysis associated with the June 29, 2014 release and
identify any contributory causes. Provide, maintain, and submit a project schedule
associated with all elements of the internal root cause analysis including but not
limited to:
i. ii. iii. iv. v. Scoping document of the root cause failure analysis;
Internal procedures associated with root cause failure analysis;
Multiple methods used to determine root cause and contributory
causes, and updates on each method as it progresses;
List of contributory factors including a review of control room
activities for several days prior to the failure, control room activities
during the release including completed emergency response, and
control room associated restart activities; and
Final summary of the root cause failure process including any
internal lessons learned and if findings are applicable to other
locations within the Marathon system.
B. Perform the integration of the results of the root cause failure analyses and other
actions required by this Order, with all relevant operating data, including all
historical repair information, construction, operating, maintenance, testing,
metallurgical analysis or other third-party consultation information, assessment data
for the facility and internal corrosion management processes and documents. Data
gathering activities must include a review of the failure history of the facility
(including in-service and pressure test failures) and development of a written report
to be approved by the Director containing all available information regarding dates
and causes of leaks and failures.
C. Perform additional field testing, inspections, and evaluations to determine whether
and to what extent the conditions associated with this failure are present at other
facilities. Include a detailed description of the criteria to be used for the evaluation
and prioritization of facilities anomalies. Upon completion of testing, inspections,
and evaluations provide a report for the Director’s approval that summarizes all
corrective actions or plans.



6
3. Within 90 days of receipt of this Order, review the existing leak detection system
applicable to Patoka Station facility and identify leak detection enhancements that could
improve the facility leak detection response. Include in this review surveillance and
hazardous vapor monitoring as possible enhancement methods to help immediately
identify leaks. Submit for the Director’s approval, a summary report including leak
detection enhancement methods for the Patoka Station facility before the facility returns
to unattended status and the associated implementation schedule.
4. Within 90 days of the receipt of this Order, review the topography and water runoff
patterns associated with the Patoka Station and design improvements to mitigate crude
oil migration off site in the event of another facility leak at this location. Submit a
schedule for implementation to the Regional Director.
5. Within 6 months of the receipt of this Order, complete an expedited API 653 inspection
on Tank 1284. When performing this tank inspection, take any additional required
measures as may be necessary to sufficiently address metallurgical report findings from
1A above or API 653 findings from Tank 1285 that is in a similar commodity service.
Report any findings and identified proposed actions resulting from the API 653
inspection on Tank 1284 to the Regional Director within 30 days of the completed
inspection.
6. Provide quarterly update written reports to the Regional Director on progress regarding
all elements required in this CAO.
7. Prior to the failure, the Marathon Patoka facility was not manned 24 hours a day and
this could have contributed to the large spill volume. As a condition of the previous
restart of the Patoka facility, Marathon agreed to provide 24-hour continuous on-site
manned patrolling. This manned patrolling activity shall continue until Marathon has
determined after the execution of the approved IWP that no other Patoka Station piping
is at risk of an internal corrosion failure. Provide 24 hour advance notification to the
Regional Director should Patoka Station facility be returned to unmanned operations.
8. It is requested but not required that Respondent maintain documentation of the costs
associated with implementation of this order. Include in each quarterly report the to-
date total costs associated with: (1) preparation and revision of procedures, studies and
analyses; (2) physical changes to pipeline infrastructure, including repairs, replacements
and other modifications; and (3) environmental remediation, if applicable.
The Director may grant an extension of time for compliance with any of the terms of this Order
upon a written request timely submitted demonstrating good cause for an extension.
With respect to each submission that under this Order requires the approval of the Director, the
Director may: (a) approve, in whole or part, the submission; (b) approve the submission on
specified conditions; (c) modify the submission to cure any deficiencies; (d) disapprove in whole
or in part, the submission, directing that Respondent modify the submission, or (e) any
combination of the above. In the event of approval, approval upon conditions, or modification
by the Director, Respondent must take all actions required by the submission as approved or



7
modified by the Director. If the Director disapproves all or any portion of the submission,
Respondent must correct all deficiencies within the time specified by the Director, and resubmit
it for approval. If a resubmitted item is disapproved in whole or in part, the Director may again
require Respondent to correct the deficiencies in accordance with the foregoing procedure, and
the Director may otherwise proceed to enforce the terms of this Order.
Be advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), you must provide, along with the complete original
document, a second copy of the document with those portions you believe qualify for
confidential treatment redacted, along with an explanation of why you believe the redacted
information qualifies for confidential treatment under 5 U.S.C. 552(b).
In your correspondence on this matter, please refer to “CPF No. 3-2014-5005H” and for each
document you submit, please provide a copy in electronic format whenever possible. The
actions required by this Corrective Action Order are in addition to and do not waive any
requirements that apply to Respondent’s pipeline system under 49 C.F.R. Part 195, under any
other order issued to Respondent under authority of 49 U.S.C. § 60101 et seq., or under any other
provision of Federal or State law.
Respondent may appeal any decision of the Director to the Associate Administrator for Pipeline
Safety. Decisions of the Associate Administrator shall be final.
Failure to comply with this Order may result in the assessment of civil penalties and in referral to
the Attorney General for appropriate relief in United States District Court pursuant to
49 U.S.C. § 60120.
The terms and conditions of this Corrective Action Order are effective upon receipt.
__________________________________ __________________
Jeffrey D. Wiese Date Issued
Associate Administrator
for Pipeline Safety