# PEMBINA COCHIN LLC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 32024071NOPV
- **title:** PEMBINA COCHIN LLC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2024-11-14
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.264(b)(1), 195.412(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-32024071nopv.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-32024071nopv.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-32024071nopv
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/32024071NOPV
**body:**

Notice of Probable Violation involving PEMBINA COCHIN LLC. PHMSA's enforcement data identifies the cited regulations as 195.264(b)(1),  195.412(a). The case was opened on 2024-11-14 and is reported as closed as of 2025-04-11. Proposed civil penalty: $43,500. Assessed civil penalty: $43,500. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

32024071NOPV_Closure Letter_04112025_(23-264063).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_Closure%20Letter_04112025_(23-264063).pdf

32024071NOPV_Closure Letter_04112025_(23-264063)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_Closure%20Letter_04112025_(23-264063)_text.pdf

32024071NOPV_Final Order_04102025_(23-264063).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_Final%20Order_04102025_(23-264063).pdf

32024071NOPV_Final Order_04102025_(23-264063)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_Final%20Order_04102025_(23-264063)_text.pdf

32024071NOPV_Operator Response to Notice_12142024_(23-264063).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_Operator%20Response%20to%20Notice_12142024_(23-264063).pdf

32024071NOPV_PCP PCO_11142024_(23-264063).pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_PCP%20PCO_11142024_(23-264063).pdf

32024071NOPV_PCP PCO_11142024_(23-264063)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/32024071NOPV/32024071NOPV_PCP%20PCO_11142024_(23-264063)_text.pdf

32024071NOPV_Final Order_04102025_(23-264063)_text.pdf

April 10, 2025
VIA ELECTRONIC MAIL TO: sburrows@pembina.com
Mr. Scott Burrows
President and Chief Executive Officer,
Pembina Pipeline Corporation
4000, 585-8 AVE SW
Calgary, AB Canada T2P 1G1
Re: CPF No. 3-2024-071-NOPV
Dear Mr. Burrows:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation, finds that the civil penalty amount of $43,500 has been paid in full, and specifies
actions that need to be taken to comply with the pipeline safety regulations. When the terms of
the compliance order are completed, as determined by the Director, Central Region, this
enforcement action will be closed. Service of the Final Order by e-mail is effective upon the
date of transmission and acknowledgement of receipt as provided under 49 CF.R § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure (Final Order)



cc: Gregory Ochs, Director, Central Region, Office of Pipeline Safety
Bob Bachmeier, Manager, Regulatory & Environment, US Operations,
bbachmeier@pembina.com
Scott Seibert, Director, Environmental & Regulatory, sseibert@pembina.com
Jeff Finch, Sr. Advisor, Regulatory Pembina US, jfinch@pembina.com
Heather Christie-Burns, Vice President, Transmission Pipelines, hcburns@pembina.com
Pete Marquart, Manager US Pipeline District, pmarquart@pembina.com
Ian Hunt, Director TBU Operations, ihunt@pembina.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
__________________________________________
In the Matter of )
Pembina Conchin, LLC, )
a subsidiary of Pembina Pipeline Corporation ) CPF No. 3-2024-071-NOPV
)
)
Respondent. )
__________________________________________)
FINAL ORDER
On November 14, 2024, pursuant to 49 CFR § 190.207, the Director, Central Region, Office of
Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to Pembina Conchin, LLC
(Respondent), a subsidiary of Pembina Pipeline Corporation. The Notice proposed finding that
Respondent had violated the pipeline safety regulations in 49 CFR Part 195 and proposed a civil
penalty of $43,500. The Notice also proposed certain measures to correct the violations.
Respondent did not contest the allegations of violation or corrective measures and paid the
proposed civil penalty on January 9, 2025. In accordance with § 190.208(a)(1), such payment
authorizes the entry of this final order.
Based upon a review of all the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulations listed below, as more fully described in the enclosed Notice, which is
incorporated by reference:
49 CFR § 195.264(b)(1) (Item 1) ─ Respondent failed to maintain and provide to
PHMSA documentation indicating that breakout tanks at Kankakee, Illinois, built
after October 2, 2000, complied with NFPA-30 impoundment capacities.
49 CFR § 195.412(a) (Item 2) ─ Respondent failed to maintain its pipeline right-
of-way (ROW). Specifically, portions of the ROW had significant tree and
vegetation overgrowth, while other portions had canopy overgrowth, all of which
impede aerial ROW inspections.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent. In accordance with 49 CFR § 190.223, Respondent is assessed
the proposed civil penalty amount of $43,500, which Respondent has already paid in full.



Compliance Actions
Pursuant to 49 U.S.C. § 60118(b) and 49 CFR § 190.217, Respondent is ordered to take the
actions proposed in the enclosed Notice to correct the violation. The Director may grant an
extension of time to comply with any of the required items upon a written request timely
submitted by the Respondent and demonstrating good cause for an extension. Upon completion
of the ordered actions, Respondent may request that the Director close the case. Respondent
previously submitted evidence to show appropriate actions have been taken to correct the
violations. This evidence is currently under review by the Director. Failure to comply with this
Order may result in the assessment of civil penalties under 49 CFR § 190.223 or in referral to the
Attorney General for appropriate relief in a district court of the United States.
The terms and conditions of this order are effective upon service in accordance with 49 CFR
§ 190.5.
___________________________________ _________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

32024071NOPV_Closure Letter_04112025_(23-264063)_text.pdf

VIA ELECTRONIC MAIL TO: SBurrows@Pembina.com; PMarquart@Pembina.com;
JFinch@Pembina.com; BBachmeier@Pembina.com;
April 11, 2025
Mr. Scott Burrows
President and Chief Executive Officer,
Pembina Cochin, LLC
4000, 585-8 AVE SW
Calgary, AB Canada T2P 1G1
RE: CPF 3-2024-071-NOPV
Dear Mr. Burrows:
On April 10, 2025, the Pipeline and Hazardous Materials Safety Administration (PHMSA)
issued to Pembina Cochin, LLC (Pembina) a Final Order in the above-referenced case. This
Order included a Compliance Order and Civil Penalty assessment. Based on our review of the
documentation provided by your staff and confirmation of payment of the civil penalty, it has
been determined that Pembina has complied with the terms of this Order.
Accordingly, this case is now closed, and no further action is contemplated with respect to the
matters involved in this case. Thank you for your cooperation in this matter.
Sincerely,
Gregory A. Ochs
Director, Central Region, Office of Pipeline Safety
Pipeline and Hazardous Materials Safety Administration
cc: Pete Marquart, Manager, US Pipeline District, Pembina Cochin, PMarquart@Pembina.com
Jeff Finch, Senior Regulatory Advisor, Regulatory US, Pembina Cochin,
JFinch@Pembina.com
Bob Bachmeier, Manager of Regulatory and Environmental, US Operations, Pembina
Cochin, BBachmeier@Pembina.com
- **truncated:** false
- **body characters:** 7681