# CITGO PIPELINE CO — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 420055012
- **title:** CITGO PIPELINE CO — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2005-03-03
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.402(a), 195.402(c)(3), 195.428(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420055012.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420055012.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420055012
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420055012
**body:**

Notice of Probable Violation involving CITGO PIPELINE CO. PHMSA's enforcement data identifies the cited regulations as 195.402(a),  195.402(c)(3),  195.428(a). The case was opened on 2005-03-03 and is reported as closed as of 2005-07-27. Proposed civil penalty: $14,000. Assessed civil penalty: $14,000. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420055012_Final Order_07142005.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420055012/420055012_Final%20Order_07142005.pdf

CITGO PIPELINE COMPANY (420055012)1.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420055012/CITGO%20PIPELINE%20COMPANY%20(420055012)1.pdf

420055012_Final Order_07142005.pdf

US. Department
of Transportation
Pipeline and
Hazarclous Materials Safety
Administration
400 Seventh Street, S.W.
Washington, D.C. 20590
JUL 1 4 2005
Mr. Jerry E. Thompson
President
CITGO Pipeline Company
6100 S. Yale
P.O. Box 3758
Tulsa, OK 741 02-3758
Re: CPF No. 4-2005-5012
Dear Mr. Thompson:
Enclosed is the Final Order issued by the Associate Administrator for Pipeline Safety in the
above-referenced case. It makes a finding of violation and assesses a civil penalty of $14,000. The
penaltypayment terms are set forth in the Final Order. This enforcement action closes automatically
upon payment. Your receipt of the Final Order constitutes service of that document under 49 C.F.R.
g 190.5.
Sincerely,
/ " ' Pipeline Compliance Registry
Office of Pipeline Safety
Enclosure
cc: R.M. Seeley
Director, Southwest Region, OPS
Jim Sanders
Manager, Region Pipeline and Terminal Facilities, CITGO
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, DC 20590
1
In the Matter of
CITGO Pipeline Company, ) CPF No. 4-2005-5012
Respondent 1
FINAL ORDER
On August 11-15, 25-29, and September 8-12, 2003, pursuant to 49 U.S.C. 5 60117, a
representative of the Office of Pipeline Safety (OPS), Research and Special Programs
Administration (RSPA), conducted an on-site pipeline safety inspection of Respondent's facilities
and records pertaining to the Sour Lake District, Eagle Line South, and Eagle Line North pipeline
systems in Oklahoma and Texas.' As a result of the inspection, the Director of the Southwest
Region, OPS, issued to Respondent a Notice of Probable Violation and Proposed Civil Penalty
(Notice) by letter dated March 3, 2005. In accordance with 49 C.F.R. 5 190.207, the Notice
proposed finding Respondent had violated 49 C.F.R. 195.428(a) and proposed assessing a civil
penalty of $14,000 for the alleged violation.
Respondent responded to the Notice by letter dated April 1,2005 (Response). In the Response, the
Respondent did not contest the violation alleged in the Notice. Instead, Respondent offered an
explanation for the violation, provided information concerning corrective action it has taken to
correct the violation, and requested the proposed civil penalty be reduced or eliminated.
Respondent did not request a hearing in the Response, and has therefore waived its right to one.
FINDING OF VIOLATION
In the Response, Respondent did not contest the violation alleged in the Notice. Accordingly, I find
Respondent violated the following section of 49 C.F.R. Part 195:
1 The Norman Y. Mineta Research and Special Programs Improvement Act, Pub. L. No. 108-426,118
Stat. 2423 (2004), created the Pipeline and Hazardous Materials Safety Administration (PHMSA) and
transferred the authority of RSPA exercised under chapter 601 of title 49, United States Code, to the
Administrator of PHMSA. See also 70 Fed. Reg. 8299, 8301-8302 (2005) (delegating authority to the
Administrator of PHMS A).



2
49 C.F.R. 5 195.428(a) - failing to determine by regular inspection and testing that each
pressure relief valve is functioning properly, is in good mechanical condition, and is
adequate from the standpoint of capacity and reliability of operation for the service in which
it is used. At the time Respondent's facilities were inspected, 10 of the 12 pressure relief
valves (PRV) tested at Arlington Station either would not open, opened above 1 10% of set
point, or could not be isolated for testing. Specifically, PRVs # 7 and 34 would not open,
PRVs # 5,9,13, 14, and 3 1 opened above 1 10% of their set points, and PRVs # 1 1,30 and
33 could not be isolated. Only PRVs # 19 and 37 tested acceptably.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. 5 60122, Respondent is subject to a civil penalty not to exceed $100,000 per
violation for each day of the violation up to a maximum of $1,000,000 for any related series of
violations. The Notice proposed a total civil penalty of $14,000 for the violation.
49 U.S.C. 5 60122 and 49 C.F.R. 5 190.225 require that in determining the amount of the civil
penalty I consider the following criteria: nature, circumstances, and gravity of the violation, degree
of Respondent's culpability, history of Respondent's prior offenses, Respondent's ability to pay the
penalty, good faith by Respondent in attempting to achieve compliance, the effect on Respondent's
ability to continue in business, and such other matters as justice may require.
Respondent's failure to determine the proper hnctioning of PRVs necessary for the safe operation
of its pipeline system created a risk to public safety and the environment. In the event
Respondent's pipeline facility were to experience a sudden increase in pressure, unintended
amounts of stress on the pipeline could cause a rupture if the pressure increase was not controlled
by the PRVs. Accordingly, it is vital that Respondent determine whether each PRV protecting the
system is functioning properly.
In its Response, Respondent requested that the proposed civil penalty be reduced or eliminated for
several reasons. Respondent explained that the valves cited in the Notice were routinely tested and
that the PRV failures were an isolated incident. Respondent also attributed the PRV failures to a
common manufacturer and installation position. Finally, Respondent detailed the corrective action
it has taken to ensure future compliance with 49 C.F.R. 5 195.428(a).
Respondent requested mitigation or elimination of the proposed civil penalty because it had
routinely tested the faulty PRVs and their failure was an isolated incident. Testing of the PRVs in
question does not justify reducing the civil penalty, because Respondent did not ensure that each
TRV was in proper operating condition. When OPS inspected the PRVs at the ,4rlingtcr, Stzticn,
10 of the 12 PRVs would not open, opened above 110% of set point or could not be isolated for
testing. The high percentage of failures at the Arlington Station was not representative of an
isolated incident.



3
Respondent also requested mitigation or elimination of the proposed civil penalty by attributing the
PRV failures to a common manufacturer and installation position. Respondent is responsible for
ensuring that each PRV on its pipeline system is compatible with requirements for the safe
operation of Respondent's system, regardless of the make or installation properties of the PRV.
Finally, Respondent requested mitigation or elimination of the proposed civil penalty based on
subsequent corrective action. Respondent has replaced the faulty PRVs as well as notified pipeline
operation managers to ensure station thermal relief valves are part of Respondent's inspection
program. Since Respondent is under an affirmative duty to comply with pipeline safety regulations
applicable to its pipeline system, I find the corrective action taken after the OPS inspection does not
justify reducing the civil penalty.
Accordingly, I find no justification for reducing the civil penalty in this case. Having reviewed the
record and considered the assessment criteria, I assess Respondent a civil penalty of $14,000.
Respondent has the ability to pay this penalty without adversely affecting its ability to continue in
business.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require this payment be made by wire transfer, through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be directed
to: Financial Operations Division (AMZ-120), Federal Aviation Administration, Mike Monroney
Aeronautical Center, P.O. Box 25082, Oklahoma City, OK 73125; (405) 954-8893.
Failure to pay the $14,000 civil penalty will result in accrual of interest at the current annual rate in
accordance with 31 U.S.C. 5 3717, 31 C.F.R. 5 901.9 and 49 C.F.R. 5 89.23. Pursuant to those
same authorities, a late penalty charge of six percent (6%) per annum will be charged if payment is
not made within 110 days of service. Furthermore, failure to pay the civil penalty may result in
referral of the matter to the Attorney General for appropriate action in a United States District
Court.
WARNING ITEMS
The Notice did not propose a civil penalty or corrective action for the following items but warned
Respondent that it should take appropriate action to correct the items. The warnings were for:
49 C.F.R. 5 195.402 - failing to prepare and follow for each pipeline system a manual of
written procedures for conducting normal operations and maintenance activities and
handling abnormal operations and emergencies. At the time of the inspection, Respondent
did not follow its written procedures concerning pig traps. On the Eagle Line North, at Bell
juilciion, MP 98.34, both the pig trzip main valve and kicker valve were found in the closed
position. Respondent's written company Policy states that, "all traps will be left open via
the kicker valve to prevent overpressure of the trap" and "during normal operations a valve
to this receiver will be left in the open position to prevent over pressuring of this receiver
trap."



49 C.F.R. $$ 195.402 and 195.430 - failing to follow written procedures for maintaining
properly operating firefighting equipment at each pump station and breakout tank area.
While Respondent's procedures require monthly inspection of its fire extinguishers,
Respondent did not perform monthly inspections for all fire extinguishers at the Sour Lake
tank farm in April, May, June, and July 2003.
Respondent is warned that if it does not take appropriate action to correct these items, enforcement
action will be taken if a subsequent inspection reveals a violation.
Under 49 C.F.R. $ 190.2 15, Respondent has a right to submit a Petition for Reconsideration of this
Final Order. The petition must be received within 20 days of Respondent's receipt of this Final
Order and must contain a brief statement of the issue(s). The filing of the petition automatically
stays payment of the assessed civil penalty. However, if Respondent submits payment for the civil
penalty, the Final Order becomes the final administrative action and the right to petition for
reconsideration is waived.
The terms and conditions of this Final Order are effective on receipt.
/7
Date Issued
~ s z c i a t e Administrator
for Pipeline Safety