# BAYOU CITY PIPELINE INC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 420065004
- **title:** BAYOU CITY PIPELINE INC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2006-02-07
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.452(b)(1), 195.452(b)(2), 195.452(d)(1).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420065004.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420065004.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420065004
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420065004
**body:**

Notice of Probable Violation involving BAYOU CITY PIPELINE INC. PHMSA's enforcement data identifies the cited regulations as 195.452(b)(1),  195.452(b)(2),  195.452(d)(1). The case was opened on 2006-02-07 and is reported as closed as of 2006-06-21. Proposed civil penalty: $20,000. Assessed civil penalty: $20,000. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420065004_Final Order_06212006.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420065004/420065004_Final%20Order_06212006.pdf

CPF_NO_4-2006-5004.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420065004/CPF_NO_4-2006-5004.pdf

420065004_Final Order_06212006.pdf

o
rt rd
U.S. Deportment
of Tronsporlotion
Plpeline ond
Hozordous moterlo|s Sofety
Aclminislrollon
',100 Seventh Street, S.W.
Washinglon, D.C. 20590
JUN 2 I m06
Mr. Richard Smiley
Engineer
Bois d'Arc Energy
600 Travis
Sfite 6275
Houston, Texas77002
Re: CPFNo.4-2006-5004
DearMr. Smiley:
Enclosed is the Final Order issued by the Associate Administrator for Pipeline Safety in.
the above-referenced case. It makes findings ofviolation and assesses a civil penalty of
$20,000. I acknowledge receip of and accept your wire transfer for $20,000 as payment in
full of the civil penalty assessed in the Final Order. The Final Order also acknowledges your
completion of the proposed compliance order items to comply with the pipeline safety
regulations. This case is now closed. Your receipt of the Final Order constitutes service of
that document under 49 C.F.R. $ 190.5.
Sincerely,
S""" n"--
James Reynolds
Pipeline Compliance Registry
Office of Pipeline Safety
Enclosure
cc: R. M. Seeley
Director, Southwest Region, PHP-400
CERTIF'IED MAIL - RETURN RECEIPT REOUESTED



DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFF'ICE OF PIPELINE SAF'ETY
wASrrrNcToN, D.c. 20590
In the Matter of
Bois d'Arc Energy,
Respondent
CPF No.4-2006-5004
)
I'INAL ORDER
on November 3,2005, pursuant to 49 u.s.c. $ 60117, representatives of the pipeline and
Hazardous Materials Safety Administration (PHMSA), OfIice of Pipeline Safety conducted an
on-site pipeline safety inspection of Respondent's facilities and records in Houston, Texas.
Asa result of the inspection, the Director, Southwest Region, PHMSA, issued to Respondent,
by letter dated February 7, 2006, a Notice of Probable Violation, Proposed Civil Penalty, and
Proposed compliance order (Notice). In accordance with 49 c.F.R. S 190-207,the Notice
proposed finding that Respondent had committed violations of 49 c.F.R. part 195 and
proposed assessing a civil penalty of $20,000 for the alleged violations. The Notice also
proposed ordering Respondent to take certain measures to correct the alleged violations.
Respondent responded to the Notice on February 28,2006by hansferring.filnds in the amount
of $20,000 as payment of the proposed civil penalty.
FINDINGS OF VIOLATION
In its Response, Respondent did not contest the alleged violations in the Notice. Accordingly,
I find that Respondent violated the following sections of 49 C.F.R. Part 195, as more fully
described in the Notice:
49 c.F.R. $ 195.452(b)(l) Q'{otice Item 1) - failing to establish a written integrity
management program for the Bayou city Pipeline for the period of February 18, 2003
through October 7, 2005;
49 C.F'R' S 195.452 (Notice ltem 2) -- failing to identify all pipeline segments for the
Bayou City Pipeline that could affect HCAs by November 18,2002; and



49 c.F.R. $$ 195.452(d)(l) (lrtrotice Item 3) - failing to complete 50 percent of the
baseline assessment of line pipe by August 16,2005.
These findings ofviolation will be considered prior offenses in any subsequenr
enforcement action taken against Respondent. Having reviewed the record and
considered the applicable penalty assessment criteria, I assess Respondent a civil penalty
of$20,000, already paid by Respondent.
COMPLIANCE ORDER
The Notice proposed a Compliance Order with respect to Item 3 of the Notice. Under 49
U.S.C. $ 60118(a), each person who engages in the transportation ofhazardous liquids or
who owns or operates a pipeline facility is required to comply with the applicable safety
standards established under chapter 601. The Director, central Region, PHMSA has
indicated that Respondent has taken the following actions specified in the Proposed
Compliance Order:
In regard to Notice Item 3, Respondent completed at least 50 percent of the
baseline assessment of the line pipe and sent documentation veriffing the
assessment to the Director, Southwest Region.
Accordingly, since compliance has been achieved with respect to this violation, the
compliance terms are not included in this Order. The terms and conditions of this Final
Order are effective on receipt.
o
JUN 2 1 m06
Date Issued
5-"
Administrator
Pipeline Safety