# TRINITY PIPELINE GP LLC — Notice of Amendment

- **operation:** document
- **citation:** CPF 420075014M
- **title:** TRINITY PIPELINE GP LLC — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2007-05-02
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 195.402(a), 195.402(c)(3).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420075014m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420075014m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420075014m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420075014M
**body:**

Notice of Amendment involving TRINITY PIPELINE GP LLC. PHMSA's enforcement data identifies the cited regulations as 195.402(a),  195.402(c)(3). The case was opened on 2007-05-02 and is reported as closed as of 2007-11-13. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420075014M_notice letter_05022007.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420075014M/420075014M_notice%20letter_05022007.pdf

420075014M_notice letter_05022007.pdf

U.S. Department
of Transportation
Pipeline and
Hazardous Materials Safety
Administration
8701 South Gessner, Suite 11 10
Houston, TX 77074
NOTICE OF AMENDMENT
CERTIFIED MAIL - RETURN RECEIPT REQUESTED
May 2,2007
Mr. Barry F. Petty, Managing Partner
Trinity C02 LLC
401 West Wall Street
Midland, TX 79701
CPF 4-2007-5014M
Dear Mr. Petty:
On July 17-20, 2006, a representative of the Pipeline and Hazardous Materials Safety
Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code inspected your
procedures for operations and maintenance in Hobbs, New Mexico.
On the basis of the inspection, PHMSA has identified the apparent inadequacies found within
Trinity C02, LLC (Trinity), as described below:
1. 5195.402 Procedural manual for operations, maintenance, and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline system a
manual of written procedures for conducting normal operations and maintenance
activities and handling abnormal operations and emergencies. This manual shall
be reviewed at intervals not exceeding 15 months, but at least once each calendar
year, and appropriate changes made as necessary to insure that the manual is
effective. This manual shall be prepared before initial operations of a pipeline
commence, and appropriate parts shall be kept at locations where operations and
maintenance activities are conducted.
A. 5195.402 Procedural manual for operations, maintenance, and emergencies.



(c) Maintenance and normal operations. The manual required by paragraph (a)
of this section must include procedures for the following to provide safety
during maintenance and normal operations:
(10) Abandoning pipeline facilities, including safe disconnection from an
operating pipeline system, purging of combustibles, and sealing abandoned
facilities left in place to minimize safety and environmental hazards. For each
abandoned offshore pipeline facility or each abandoned onshore pipeline
facility that crosses over, under or through commercially navigable waterways
the last operator of that facility must file a report upon abandonment of that
facility in accordance with 9195.59
of this part.
Trinity's procedures need to specify more detail in the process for abandonment of pipelines.
B. 9195.406 Maximum operating pressure.
(a) Except for surge pressures and other variations from normal operations,
no operator may operate a pipeline at a pressure that exceeds any of the
following:
(1) The internal design pressure of the pipe determined in accordance with
9195.106. However, for steel pipe in pipelines being converted under 9195.5, if
one or more factors of the design formula (9195.106) are unknown, one of the
following pressures is to be used as design pressure:
(i) Eighty percent of the first test pressure that produces yield under section
N5.0 of Appendix N of ASME B31.8, reduced by the appropriate factors in
99195.106(a) and (e); or
(ii) If the pipe is 323.8 mm (12% in) or less outside diameter and is not tested
to yield under this paragraph, 1379 kPa (200 psig).
(2) The design pressure of any other component of the pipeline.
(3) Eighty percent of the test pressure for any part of the pipeline which has
been pressure tested under Subpart E of this part.
(4) Eighty percent of the factory test pressure or of the prototype test pressure
for any individually installed component which is excepted from testing under
9195.305.
(5) For pipelines under 99195.302(b)(l) and (b)(2)(i), that have not been
pressure tested under Subpart E of this part, 80 percent of the test pressure or
highest operating pressure to which the pipeline was subjected for 4 or more
continuous hours that can be demonstrated by recording charts or logs made
at the time the test or operations were conducted.
Trinity needs to specify procedures for establishing Maximum Operating Pressure.
C. 9195.406 Maximum operating pressure.
(b) No operator may permit the pressure in a pipeline during surges or other
variations from normal operations to exceed 110 percent of the operating
pressure limit established under paragraph (a) of this section. Each operator



must provide adequate controls and protective equipment to control the
pressure within this limit.
Trinity's procedures need to specify that during surges or other variations from normal
operations the pressure in the pipeline is not permitted to exceed 110 percent of the operating
pressure limit established under paragraph (a) of this section and that adequate controls and
protective equipment to control the pressure within this limit must be provided.
D. 5195.569 Do I have to examine exposed portions of buried pipelines?
Whenever you have knowledge that any portion of a buried pipeline is exposed,
you must examine the exposed portion for evidence of external corrosion if the
pipe is bare, or if the coating is deteriorated. If you find external corrosion
requiring corrective action under Sec. 195.585, you must investigate
circumferentially and longitudinally beyond the exposed portion (by visual
examination, indirect method, or both) to determine whether additional
corrosion requiring remedial action exists in the vicinity of the exposed portion.
Trinity's procedures need to specify that if you find external corrosion during examination of
exposed pipe you must investigate circumferentially and longitudinally beyond the exposed
portion to determine whether additional corrosion requiring remedial action exists in the vicinity
of the exposed portion.
E. 5195.579 What must I do to mitigate internal corrosion?
(a) General. If you transport any hazardous liquid or carbon dioxide that would
corrode the pipeline, you must investigate the corrosive effect of the hazardous
liquid or carbon dioxide on the pipeline and take adequate steps to mitigate
internal corrosion.
(b) Inhibitors. If you use corrosion inhibitors to mitigate internal corrosion, you
must--
(1) Use inhibitors in sufficient quantity to protect the entire part of the pipeline
system that the inhibitors are designed to protect;
(2) Use coupons or other monitoring equipment to determine the effectiveness
of the inhibitors in mitigating internal corrosion; and
(3) Examine the coupons or other monitoring equipment at least twice each
calendar year, but with intervals not exceeding 7 112 months.
(c) Removing pipe. Whenever you remove pipe from a pipeline, you must
inspect the internal surface of the pipe for evidence of corrosion. If you find
internal corrosion requiring corrective action under Sec. 195.585, you must
investigate circumferentially and longitudinally beyond the removed pipe (by
visual examination, indirect method, or both) to determine whether additional
corrosion requiring remedial action exists in the vicinity of the removed pipe.
Trinity needs to specify procedures for mitigating internal corrosion.
F. 5195.589 What corrosion control information do I have to maintain?



(c) You must maintain a record of each analysis, check, demonstration,
examination, inspection, investigation, review, survey, and test required by this
subpart in sufficient detail to demonstrate the adequacy of corrosion control
measures or that corrosion requiring control measures does not exist. You
must retain these records for at least 5 years, except that records related to
195.569,195.573(a) and (b), and 195.579(b)(3) and (c) must be retained for as
long as the pipeline remains in service.
Trinity's procedures need to specify that records for pipe-to-soil potentials and internal corrosion
coupons will be retained for as long as the pipeline remains in service.
2. s195.402 Procedural manual for operations, maintenance, and emergencies.
(c) Maintenance and normal operations. The manual required by paragraph (a) of
this section must include procedures for the following to provide safety during
maintenance and normal operations:
(3) Operating, maintaining, and repairing the pipeline system in accordance with
each of the requirements of this subpart and subpart H of this part.
A. s195.222 Welders: Qualification of welders.
(a) Each welder must be qualified in accordance with section 6 of API 1104
(ibr, see 195.3 or section IX of the ASME Boiler and Pressure Vessel Code, (ibr,
see § 195.3) except that a welder qualified under an earlier edition than listed in §
195.3 may weld but may not re-qualify under that earlier edition.
Trinity's procedures need to reference the correct section pertaining to the latest incorporated
by reference edition of API 11 04. The correct section for welder qualification is section 6 of API
1 104 1 91h ~dition.
B. s195.222 Welders: Qualification of welders.
(b) No welder may weld with a welding process unless, within the preceding 6
calendar months, the welder has-
(1) Engaged in welding with that process; and
(2) Had one welded tested and found acceptable under section 9 of API 1104
Trinity's procedures need to specify that welders may not weld with a particular welding process
unless, within the preceding 6 calendar months, the welder has (1) Engaged in welding with
that process; and (2) Had one weld tested and found acceptable under Section 9 of API 1104.
C. s195.226 Welding: Arc burns.
(b) An arc burn may be repaired by completely removing the notch by
grinding, if the grinding does not reduce the remaining wall thickness to less
than the minimum thickness required by the tolerances in the specification to
which the pipe is manufactured. If a notch is not repairable by grinding, a
cylinder of the pipe containing the entire notch must be removed.



Trinity's procedures need to specify that arc burn repairs require verification of removal of the
metallurgical notch by nondestructive testing.
D. 9195.266 Construction records.
A complete record that shows the following must be maintained by the operator
involved for the life of each pipeline facility:
(a) The total number of girth welds and the number nondestructively tested,
including the number rejected and the disposition of each rejected weld.
Trinity's procedures need to specify that records of the total number of girth welds and the
number nondestructively tested, including the number rejected and the disposition of each weld
must be maintained for the life of the facility.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. 5 60108(a) and 49 C.F.R. 5 190.237. Enclosed
as part of this Notice is a document entitled Response Options for Pipeline Operators in
Compliance Proceedings. Please refer to this document and note the response options. Be
advised that all material you submit in response to this enforcement action is subject to being
made publicly available. If you believe that any portion of your responsive material qualifies for
confidential treatment under 5 U.S.C. 552(b), along with the complete original document you
must provide a second copy of the document with the portions you believe qualify for
confidential treatment redacted and an explanation of why you believe the redacted information
qualifies for confidential treatment under 5 U.S.C. 552(b). If you do not respond within 30 days
of receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this
Notice and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in
this Notice without further notice to you and to issue a Final Order.
If, after opportunity for a hearing, your plans or procedures are found inadequate as alleged in
this Notice, you may be ordered to amend your plans or procedures to correct the inadequacies
(49 C.F.R. 5 190.237). If you are not contesting this Notice, we propose that you submit your
amended procedures to my office within 30 days of receipt of this Notice. This period may be
extended by written request for good cause. Once the inadequacies identified herein have been
addressed in your amended procedures, this enforcement action will be closed.
In your correspondence on this matter, please refer to CPF 4-2007-5014M and for each
document you submit, please provide a copy in electronic format whenever possible.
Sincerely,
Director, southwest Region
Pipeline and Hazardous
Materials Safety Administration
Enclosure: Response Options for Pipeline Operators in Compliance Proceedings