# SEA ROBIN PIPELINE CO — Notice of Amendment

- **operation:** document
- **citation:** CPF 420112002M
- **title:** SEA ROBIN PIPELINE CO — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2011-03-21
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.13(c).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420112002m.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420112002m.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420112002m
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420112002M
**body:**

Notice of Amendment involving SEA ROBIN PIPELINE CO. PHMSA's enforcement data identifies the cited regulation as 192.13(c). The case was opened on 2011-03-21 and is reported as closed as of 2011-11-21. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420112002M_Closure Letter_11212011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420112002M/420112002M_Closure%20Letter_11212011.pdf

420112002M_Closure Letter_11212011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420112002M/420112002M_Closure%20Letter_11212011_text.pdf

420112002M_NOA_03212011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420112002M/420112002M_NOA_03212011.pdf

420112002M_NOA_03212011_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420112002M/420112002M_NOA_03212011_text.pdf

420112002M_Operator Response to NOA_04222011.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420112002M/420112002M_Operator%20Response%20to%20NOA_04222011.pdf

420112002M_Closure Letter_11212011_text.pdf

CERTIFIED MAIL - RETURN RECEIPT REQUESTED
November 21, 2011
Mr. Eric Amundsen
Vice President and Chief Asset Integrity Officer
Sea Robin Pipeline Company
5444 Westheimer Road
Houston, TX 77056-5306
CPF 4-2011-2002M
Dear Mr. Amundsen:
On September 20-23 and December 7, 2010, representatives from the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code,
conducted an on-site pipeline safety inspection of Sea Robin Pipeline Co. procedures for the
offshore natural gas transmission pipeline system, Unit ID 1874- Sea Robin Transmission in
Erath, LA. As a result of the inspection, Sea Robin Pipeline Co. was issued a Notice of
Amendment on March 21, 2011, which proposed amendment of your procedures.
Sea Robin submitted its amended procedures on April 22, 2011. My staff reviewed the amended
procedures, and it appears that the inadequacies outlined in this Notice of Amendment have been
corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
R. M. Seeley
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false