# WEST TEXAS GULF PIPELINE CO — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 420155012
- **title:** WEST TEXAS GULF PIPELINE CO — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2015-04-27
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.401(b)(1), 195.422(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420155012.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420155012.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420155012
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420155012
**body:**

Notice of Probable Violation involving WEST TEXAS GULF PIPELINE CO. PHMSA's enforcement data identifies the cited regulations as 195.401(b)(1),  195.422(a). The case was opened on 2015-04-27 and is reported as closed as of 2016-12-27. Proposed civil penalty: $207,300. Assessed civil penalty: $207,300. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420155012_Final Order_12012016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420155012/420155012_Final%20Order_12012016.pdf

420155012_Final Order_12012016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420155012/420155012_Final%20Order_12012016_text.pdf

420155012_NOPV PCP_04272015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420155012/420155012_NOPV%20PCP_04272015.pdf

420155012_NOPV PCP_04272015_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420155012/420155012_NOPV%20PCP_04272015_text.pdf

420155012_Operator Response and Request for Hearing_05222015.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420155012/420155012_Operator%20Response%20and%20Request%20for%20Hearing_05222015.pdf

420155012_Final Order_12012016_text.pdf

December 1, 2016
Mr. Michael J. Hennigan
President and Chief Executive Officer
Sunoco Pipeline, LP
1818 Market Street, Suite 1500
Philadelphia, PA 19106
Re: CPF No. 4-2015-5012
Dear Mr. Hennigan:
Enclosed please find the Final Order issued in the above-referenced case. It makes findings of
violation and assesses a total civil penalty of $207,300. This is to acknowledge receipt of
payment of $40,300, by wire transfer dated May 22, 2015. Item 1 of this enforcement action is
now closed. With respect to Item 2, the penalty payment terms are set forth in the Final Order,
which will close automatically upon receipt of payment of the remaining $167,000. Service of
the Final Order by certified mail is deemed effective upon the date of mailing, or as otherwise
provided under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Acting Associate Administrator
for Pipeline Safety
Enclosure
cc: Mr. Rodrick M. Seeley, Director, Southwest Region, OPS
Mr. David R. Chalson, Senior Vice President, Operations, Sunoco Pipeline, LP
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Sunoco Pipeline, LP, ) CPF No. 4-2015-5012
)
)
)
Respondent. )
___________________________________ )
FINAL ORDER
On March 1, 2015, pursuant to 49 U.S.C. § 60117, a representative of the Pipeline and
Hazardous Materials Safety Administration (PHMSA), Office of Pipeline Safety (OPS), initiated
an investigation of an incident involving the hazardous liquid pipeline system owned by West
Texas Gulf Pipeline Company and operated by Sunoco Pipeline, LP (SPLP or Respondent).
Respondent’s 580-mile system transports crude oil from West Texas gathering lines and
interconnects to Corsicana and Nederland, Texas markets.1
The investigation arose out of a failure near Dawson, Texas. On February 25, 2015, SPLP
reported to the National Response Center a release of crude oil at Mile Post (MP) 257 on the
Blum-to-Wortham section of Respondent’s pipeline system (Failure). The leak released
approximately 30 barrels of oil. The OPS Southwest Region received a copy of the telephonic
notice and contacted SPLP to initiate an investigation.
As a result of the investigation, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated April 27, 2015, a Notice of Probable Violation and Proposed Civil
Penalty (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed finding that
SPLP had committed various violations of 49 C.F.R. Part 195 and proposed assessing a total
civil penalty of $207,300 for the alleged violations.
Respondent responded to the Notice by letter dated May 22, 2015 (Response). SPLP did not
contest the allegation of violation of 49 C.F.R. § 195.422 (Item 1) and paid the proposed civil
penalty of $40,300, as provided in 49 C.F.R. § 190.227. Payment of the penalty serves to close
this portion of the case with prejudice. Respondent did contest the allegation of violation of
49 C.F.R. § 195.401(b) (Item 2) and requested a hearing.
By subsequent letter dated December 2, 2015 (Supplemental Response), SPLP withdrew its
request for a hearing and presented information seeking reduction of the proposed penalty with
1 Pipeline Safety Violation Report (Violation Report) (April 21, 2015), (on file with PHMSA), at 1.



CPF No. 4-2015-5012
Page 2
respect to Item 2, which authorized the entry of this Final Order without further notice. SPLP
also indicated that by its decision not to contest this allegation, the company did not “admit the
accuracy of the factual or legal assertions set forth in the [Notice].”2
FINDINGS OF VIOLATION
In its Response and Supplemental Response, SPLP did not contest the allegations in the Notice
that it violated 49 C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.422(a), which states:
§ 195.422 Pipeline repairs.
(a) Each operator shall, in repairing its pipeline systems, insure that
the repairs are made in a safe manner and are made so as to prevent
damage to persons or property.
(b) No operator may use any pipe, valve, or fitting, for replacement in
repairing pipeline facilities, unless it is designed and constructed as required
by this part.
The Notice alleged that Respondent violated 49 C.F.R. § 195.422(a) by failing to insure that the
pipeline repair it performed was made in a safe manner and made so as to prevent damage to
persons or property. Specifically, the Notice alleged that on or about February 25-26, 2015, in
response to the Failure, SPLP first installed a repair at the site of the Failure, and then installed a
second repair at an adjacent area of external corrosion. The second repair was made on a non-
through-wall anomaly adjacent to the failure origin with a PLIDCO © Smith+Clamp™. The
PLIDCO © Smith+Clamp™ is a pinhole-leak-repair clamp intended for through-wall pinhole
leaks, but only as a leak-stoppage device. It is not intended as a permanent repair unless it also
includes a PLIDCO © Weld+Cap™, which Respondent did not install. The installation of the
PLIDCO © Smith+Clamp™ was not an appropriate use of the product for the second repair and
was not used in a manner consistent with the manufacturer’s installation instructions or design.
The Notice alleged that the device used for the second repair was neither intended nor designed
for use as a permanent repair, and therefore, the installation was not made in a safe manner so as
to prevent damage to persons or property.
Respondent did not contest this allegation of violation. Accordingly, based upon a review of all
of the evidence, I find that Respondent violated 49 C.F.R. § 195.422(a) by failing to insure that a
pipeline repair was made in a safe manner and made so as to prevent damage to persons or
property.
Item 2: The Notice alleged that Respondent violated 49 C.F.R. § 195.401(b)(1), which states:
§ 195.401 General requirements.
(a) . . . .
2 Supplemental Response, at 1.



CPF No. 4-2015-5012
Page 3
(b) An operator must make repairs on its pipeline system according to
the following requirements:
(1) Non integrity management repairs. Whenever an operator discovers
any condition that could adversely affect the safe operation of its pipeline
system, it must correct the condition within a reasonable time. However, if
the condition is of such a nature that it presents an immediate hazard to
persons or property, the operator may not operate the affected part of the
system until it has corrected the unsafe condition. . . .
The Notice alleged that Respondent violated 49 C.F.R. § 195.401(b)(1) by failing to correct,
within a reasonable time, a condition that could adversely affect the safe operation of its pipeline
system. Specifically, the Notice alleged that SPLP had sufficient information when it performed
in-line inspections (ILI) on the pipeline segment from Blum Station to Wortham Station in 2006
and again in September 2011 to know that an unsafe condition existed but failed to correct it.
According to the Notice, the company’s 2006 ILI data showed the Failure site “as a feature at
Wheel Count 247894.01” and identified the feature as having approximately 17% metal loss.
The 2011 ILI data showed the same feature as having approximately 68% metal loss. Based
upon the calculated corrosion growth and assuming a straight-line basis for its continued growth,
the feature at the leak site was allegedly experiencing a corrosion growth rate of approximately
10.2% per year. This growth rate would predict a through-wall leak in less than five years.
SPLP, however, did not schedule its next ILI assessment until 2016, which was beyond the
predicted and actual remaining life of the feature at the Failure site.
The Notice further alleged that Respondent’s integrity management program (IMP) in place in
2011 contributed to SPLP’s failure to correct this known condition within a reasonable time.
According to the Notice, SPLP stated “that they did not have a process to look for variances
between the [ILI vendor’s] Draft Final to Final Report revisions or re-grading of features. . .” As
such, SPLP neither recognized the accelerated corrosion growth nor took prompt action to
correct it.
Respondent did not contest this allegation of violation, but asked for mitigation of the proposed
civil penalty, which I will address in the “Assessment of Penalty” section below. Accordingly,
based upon a review of all of the evidence, I find that Respondent violated 49 C.F.R.
§ 195.401(b)(1) by failing to correct, within a reasonable time, a condition that could adversely
affect the safe operation of its pipeline system.
These findings of violation will be considered prior offenses in any subsequent enforcement
action taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. § 60122, Respondent is subject to an administrative civil penalty not to exceed
$200,000 per violation for each day of the violation, up to a maximum of $2,000,000 for any



CPF No. 4-2015-5012
Page 4
related series of violations.3 In determining the amount of a civil penalty under 49 U.S.C.
§ 60122 and 49 C.F.R. § 190.225, I must consider the following criteria: the nature,
circumstances, and gravity of the violation, including adverse impact on the environment; the
degree of Respondent’s culpability; the history of Respondent’s prior offenses; and any effect
that the penalty may have on its ability to continue doing business; and the good faith of
Respondent in attempting to comply with the pipeline safety regulations. In addition, I may
consider the economic benefit gained from the violation without any reduction because of
subsequent damages, and such other matters as justice may require. The Notice proposed a civil
penalty of $167,000 for the violation in Item 2 cited above.
Item 2: The Notice proposed a civil penalty of $167,000 for Respondent’s violation of
49 C.F.R. § 195.401(b)(1), for failing to correct, within a reasonable time, a condition that could
adversely affect the safe operation of its pipeline system. As noted above, SPLP did not contest
the allegation of violation but argued that PHMSA should consider reducing the proposed
penalty. The company presented several arguments in favor of a penalty reduction. First, the
company stated that it disagreed with the assertion that its IMP lacked a process to identify
variances between what it termed the ILI vendor’s “electronic final report” and its final written
report in hard-copy format.4 On the contrary, SPLP asserted that there were documented
procedures in place designed to capture variances between the two versions and to make them
known to SPLP.5
Respondent asserted that the initial “electronic final report” from the ILI vendor in 2011
indicated a 45% metal loss of the feature located at Wheel Count 247894.01. The final report in
hard copy, however, indicated that the anomaly had an estimated 68% metal loss. According to
SPLP, its vendor failed to notify Respondent of this variance between the two reports or
otherwise to make SPLP aware of the vendor’s revision, as was required under SPLP’s “ILI
Vendor Requirements” document. As a result, the company stated that it then set the
reassessment interval at five years, based on the historic corrosion growth rate from 17% in 2006
to 45% in 2011. Respondent also argued that the metal-loss deviations could not be directly
attributed to corrosion growth. Finally, Respondent noted that since the time of the 2011 ILI
data analysis, it had made procedural modifications to its ILI reporting process, including
elimination of electronic final reports.
I reject the argument that any possible mistakes or shortcomings by SPLP’s vendor should serve
as a basis for reducing the proposed penalty. Even acknowledging that Respondent may have had
processes in place, SPLP itself concedes that the procedures were not strictly followed.6 It is
important to note that “[i]nformation about the actions of Respondent’s ILI vendor are
3 The Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011, Pub. L. No. 112-90, § 2(a)(1), 125 Stat.
1904, January 3, 2012, increased the civil penalty liability for violating a pipeline safety standard to $200,000 per
violation for each day of the violation, up to a maximum of $2,000,000 for any related series of violations.
4 Supplemental Response, at 3.
5 Respondent did not submit for the record copies of the actual procedures referenced in its Response.
6 Supplemental Response, at 4.



CPF No. 4-2015-5012
Page 5
immaterial to the assessment of a civil penalty. . . .” In the Matter of Tesoro Refining and
Marketing Company (Tesoro), Final Order, CPF No. 5-2007-5031 (Dec. 28, 2009) (available at
www.phsma.dot.gov/pipeline/enforcement). As the operator of a hazardous liquid pipeline,
SPLP is ultimately accountable for reviewing all reports from its contractors and agents and
making sure that any conditions that could adversely affect the safe operation of its pipeline are
promptly corrected.
I would also note that the penalty for this Item was not calculated or related in any way to
SPLP’s procedures, but rather Respondent’s failure to discover an unsafe condition and promptly
carry out needed repairs. I find that, with respect to culpability, Respondent failed to take
appropriate action to comply with a clearly applicable requirement by reviewing the vendor’s
final report, which showed the increased metal loss, and taking prompt action to correct the
condition.
Second, SPLP argued that the “nature, circumstances and gravity of the alleged violation were
comparatively minor… especially when the amount assessed in this instance is compared to
other penalties assessed by PHMSA for similar circumstances.”7 I disagree. The gravity of the
violation in this case was quite serious, insofar as it was a causal factor in the Failure. Because
of the violation, pipeline integrity was significantly compromised and resulted in a release of
crude oil that harmed the environment.8 In fact, SPLP is fortunate that the amount of the spill
was small and its impact limited; it could have easily resulted in a spill with far greater
consequences.
Third, Respondent claimed that the violation related to 2011, before the statutory maximum civil
penalty amount was increased.9 Respondent argued that because the Notice does not appear to
allege a multi-day violation, the maximum civil penalty amount should be no greater than
$100,000. In this case, SPLP failed to schedule an assessment prior to the condition reaching the
point at which it affected the pipeline's integrity. As stated in the Violation Report,
the violation was not limited to a single point in time, but, rather, constituted an ongoing failure
to correct an unsafe condition that continued for 1,043 days,10 well past the 2012 effective date
for the increased maximum civil penalty amounts. I find that the penalty proposed for this Item
was based upon the $200,000 maximum daily penalty that went into effect in January 2012 and
that the penalty was appropriately calculated.11
7 Id., at 4-5.
8 Violation Report, at 3.
9 The amendments enacted by the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011 (PL 112-90)
became effective January 3, 2012.
10 Violation Report, at 13.
11 In previous cases, PHMSA has held that “49 C.F.R. § 195.401(b) places an ongoing obligation on an operator to
correct discovered conditions that could affect the safety of the pipeline. . . .” and “[d]aily violations continue to
occur until the condition is corrected.” E.g., In the Matter of Equitable Production Company and MarkWest
Hydrocarbon Inc., Final Order, CPF No. 2-2006-5001 (Feb. 17, 2011) (available at
www.phmsa.dot.gov/pipeline/enforcement).



CPF No. 4-2015-5012
Page 6
Fourth, SPLP argued that it is entitled to a credit for its good-faith efforts, both following the
Failure and after the Notice was issued, to rectify its procedures for dealing with ILI vendors.
“There was no knowledge or intent either on the part of the ILI vendor or SPLP to fail to comply
with any regulatory requirements.”12 While I acknowledge and commend the steps that
Respondent took after the Failure and after receiving the Notice to correct the violation and
avoid future accidents, these are the actions that any prudent operator would be expected to take
under similar circumstances. PHMSA only recognizes and reduces a proposed penalty for those
good-faith efforts taken by an operator to interpret and follow the regulations prior to a violation,
not afterwards. As for the fact that there is no evidence that Respondent knowingly or
intentionally violated the regulation, this level of culpability was already taken into account in
proposing the penalty amount; otherwise, the penalty would have been higher.
Finally, SPLP argued that it has no prior history of violating §195.401(b) and that it derived no
economic benefit from the procedure that was in place at the time or from the incident itself.
While SPLP is correct that this Item does not constitute what PHMSA terms a “repeat offense”
of the same regulation, SPLP does have a history of seven prior safety violations within the five
years prior to this case. These prior violations did, in fact, serve to properly enhance the
proposed penalty here.13 As for the economic benefit, the proposed penalty was not based on
any purported economic gain by the operator.
Considering all of SPLP’s argument and the totality of the circumstances surrounding the failure,
I am unconvinced that a penalty reduction is warranted. While it may be true that the Failure
could potentially have been averted had SPLP’s ILI vendor followed the terms of their
agreement, this does not absolve the operator from full responsibility for the accident that
occurred. Accordingly, having reviewed the record and considered the assessment criteria, I
assess Respondent a civil penalty of $167,000 for violation of 49 C.F.R. § 195.401(b).
In summary, having reviewed the record and considered the assessment criteria for Item 2 cited
above, I assess Respondent a total civil penalty of $167,000.
Payment of the civil penalty must be made within 20 days of service. Federal regulations
(49 C.F.R. § 89.21(b)(3)) require such payment to be made by wire transfer through the Federal
Reserve Communications System (Fedwire), to the account of the U.S. Treasury. Detailed
instructions are contained in the enclosure. Questions concerning wire transfers should be
directed to: Financial Operations Division (AMK-325), Federal Aviation Administration,
6500 S MacArthur Blvd., Oklahoma City, Oklahoma 79169. The Financial Operations Division
telephone number is (405) 954-8845.
Failure to pay the $167,000 civil penalty will result in accrual of interest at the current annual
rate in accordance with 31 U.S.C. § 3717, 31 C.F.R. § 901.9 and 49 C.F.R. § 89.23. Pursuant to
those same authorities, a late penalty charge of six percent (6%) per annum will be charged if
12 Supplemental Response, at 5.
13 See, In the Matter of Sunoco Logistics Partners, LP, Final Order, C.P.F. No. 4-2010-5010 (Aug. 1, 2012) and
Decision on Petition for Reconsideration (Dec. 31, 2012) (available at www.phmsa.dot.gov/pipeline/enforcement).



CPF No. 4-2015-5012
Page 7
payment is not made within 110 days of service. Furthermore, failure to pay the civil penalty
may result in referral of the matter to the Attorney General for appropriate action in a district
court of the United States.
Under 49 C.F.R. § 190.243, Respondent has the right to submit a Petition for Reconsideration of
this Final Order. The petition must be sent to: Associate Administrator, Office of Pipeline
Safety, PHMSA, 1200 New Jersey Avenue, SE, East Building, 2nd Floor, Washington, DC
20590, with a copy sent to the Office of Chief Counsel, PHMSA, at the same address. PHMSA
will accept petitions received no later than 20 days after receipt of service of the Final Order by
the Respondent, provided they contain a brief statement of the issue(s) and meet all other
requirements of 49 C.F.R. § 190.243. The filing of a petition automatically stays the payment of
any civil penalty assessed but does not stay any other provisions of the Final Order, including
any required corrective actions. If Respondent submits payment of the civil penalty, the Final
Order becomes the final administrative decision and the right to petition for reconsideration is
waived.
The terms and conditions of this Final Order are effective upon service in accordance with
49 C.F.R. § 190.5.
December 1, 2016
___________________________________ __________________________
Alan K. Mayberry Date Issued
Acting Associate Administrator
for Pipeline Safety