# PHILLIPS 66 PIPELINE LLC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 420165002
- **title:** PHILLIPS 66 PIPELINE LLC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2016-02-24
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 195.202, 195.246(a), 195.563(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-420165002.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-420165002.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-420165002
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/420165002
**body:**

Notice of Probable Violation involving PHILLIPS 66 PIPELINE LLC. PHMSA's enforcement data identifies the cited regulations as 195.202,  195.246(a),  195.563(a). The case was opened on 2016-02-24 and is reported as closed as of 2022-01-26. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

420165002_Closure Letter_01262022_(20-176184).pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Closure%20Letter_01262022_(20-176184).pdf

420165002_Closure Letter_01262022_(20-176184)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Closure%20Letter_01262022_(20-176184)_text.pdf

420165002_Final Order_07122019.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Final%20Order_07122019.pdf

420165002_Final Order_07122019_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Final%20Order_07122019_text.pdf

420165002_NOPV PCO_02242016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_NOPV%20PCO_02242016.pdf

420165002_NOPV PCO_02242016_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_NOPV%20PCO_02242016_text.pdf

420165002_Operator Hearing Exhibits Letter_09302016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Operator%20Hearing%20Exhibits%20Letter_09302016.pdf

420165002_Operator Request for Hearing_04282016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Operator%20Request%20for%20Hearing_04282016.pdf

420165002_Operator Response to Notice_04282016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Operator%20Response%20to%20Notice_04282016.pdf

420165002_Operator Statement of Issues_04282016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Operator%20Statement%20of%20Issues_04282016.pdf

420165002_Opertaor Request for Hearing Cover Letter_04282016.pdf: https://primis.phmsa.dot.gov/enforcement-documents/420165002/420165002_Opertaor%20Request%20for%20Hearing%20Cover%20Letter_04282016.pdf

420165002_Final Order_07122019_text.pdf

July 12, 2019
Mr. Todd Denton
President
Phillips 66 Pipeline, LLC
3010 Briarpark Drive, PWC-7109
Houston, Texas 77042
Re: CPF No. 4-2016-5002
Dear Mr. Denton:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation and specifies actions that need to be taken by Phillips 66 Pipeline, LLC to comply with
the pipeline safety regulations. When the terms of the compliance order have been completed, as
determined by the Director, Southwest Region, this enforcement action will be closed. Service
of the Final Order by certified mail is effective upon the date of mailing as provided under 49
C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosure
cc: Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Van P. Williams, Esq., Senior Counsel, Phillips 66 Pipeline, LLC, HST-13-N1348,
1075 W. Sam Houston Parkway N., Suite 200, Houston, Texas 77042
CERTIFIED MAIL - RETURN RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Phillips 66 Pipeline, LLC, ) CPF No. 4-2016-5002
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
On multiple occasions between April 13, 2015, through September 17, 2015, pursuant to 49
U.S.C. § 60117, representatives of the Pipeline and Hazardous Materials Safety Administration
(PHMSA), Office of Pipeline Safety (OPS), conducted an on-site pipeline safety inspection of a
highly volatile liquids (HVL) pipeline being constructed by Phillips 66 Pipeline, LLC (Phillips
66 or Respondent) at various locations in Texas. Phillips 66 Pipeline, LLC, a wholly owned
subsidiary of Phillips 66, operates more than 12,000 miles of pipelines in the United States that
transport both raw and finished petroleum products as well as various terminal facilities.1
As a result of the inspection, the Director, Southwest Region, OPS (Director), issued to
Respondent, by letter dated February 24, 2016, a Notice of Probable Violation and Proposed
Compliance Order (Notice). In accordance with 49 C.F.R. § 190.207, the Notice proposed
finding that Phillips 66 had violated 49 C.F.R. § 195.202 and proposed ordering Respondent to
take certain measures to correct the alleged violation.
Phillips 66 responded to the Notice by letter dated April 28, 2016.2 Respondent contested the
allegation and requested a hearing. Phillips 66 provided a pre-hearing submission by letter dated
September 30, 2016 and a hearing was subsequently held on October 13, 2016 in Houston,
Texas, before a PHMSA Presiding Official. At the hearing, Respondent was represented by
counsel. After the hearing, Respondent provided additional written material for the record, by
letter dated November 10, 2016. The Director submitted a region recommendation dated
December 28, 2017 and Respondent submitted a reply to the recommendation dated February 23,
2018.
1 Pipeline Safety Violation Report (Violation Report), (Feb. 24, 2016) (on file with PHMSA), at 1;
https://www.phillips66midstream.com/EN/Pages/pipelines.aspx (last accessed May 16, 2019).
2 On March 21, 2016, Phillips 66 requested a 30-day time extension to respond to the Notice, which was granted by
the Director on March 28, 2016.



CPF No. 4-2016-5002
Page 2
FINDING OF VIOLATION
The Notice alleged that Respondent violated 49 C.F.R. Part 195, as follows:
Item 1: The Notice alleged that Respondent violated 49 C.F.R. § 195.202, which states:
§ 195.202 Compliance with specifications or standards.
Each pipeline system must be constructed in accordance
with comprehensive written specifications or standards that
are consistent with the requirements of this part.
The Notice alleged that Respondent violated 49 C.F.R. § 195.202 by installing multiple pipes
through a single bore hole when using horizontal directional drilling (HDD) as part of its Mont
Belvieu to Sweeney, Texas highly volatile liquid (HVL) pipeline construction project without
having comprehensive written specifications for constructing the pipeline in this manner. The
Notice referenced §§ 195.246(a) and 195.563(a) and specifically alleged that the written
construction plans and procedures used by Phillips 66 to construct the HVL pipeline at the San
Bernard River crossing were not comprehensive enough to be consistent with the requirements
of Part 195 because they did not account for the additional stresses and possibility of damage to
the pipe or the impact on cathodic protection associated with pulling more than one pipe through
a HDD bore.
In its Response and at the hearing, Phillips 66 argued that the written specifications and
procedures it had in place at the time the multiple pipeline HDD installation at the San Bernard
River crossing was conducted in December 2014 fully complied with the regulations.
Respondent provided a copy of a written HDD standard P66PL-TIP-4010 which provided
guidance on HDD drilling in support of pipeline installation.3 Respondent also stated that its
contractors, Hard Rock Directional Drilling and Troy Construction, were experienced with
bundled HDD installations and had processes and procedures for deviations from a single pipe
HDD installation.4 In connection with the hearing, Phillips 66 also provided e-mail
correspondence with its contractors, a three-page drilling operations plan from Hard Rock
Directional Drilling, a two-page description of the ream and swab pass cutter diameters and
sequence, a Troy Construction daily progress report, a geotechnical exploration data report, a
pulling load summary, bore bumper system instructions, and various other field notes and
photographs.5 Phillips 66 argued that collectively these materials constituted comprehensive
procedures for installing multiple pipes through a single bore hole when using HDD.
Respondent also argued that no undue stress, damage, or other specific deficiency in the
construction had been shown that would warrant the issuance of a Notice of Probable Violation
and Proposed Compliance Order by OPS, and that the issue of adequate cathodic protection was
3 Response at 2.
4 Id.
5 Phillips 66 pre-hearing submission, Exhibits D–T. Phillips 66 is correct that there is no requirement that all
procedures used by an operator be contained in a single manual.



CPF No. 4-2016-5002
Page 3
not a valid concern due to its use of rubber bumpers during the pipe installation.6
With respect to Respondent’s argument that its HDD standard P66PL-TIP-4010 in place at the
time of construction, together with the various items in its exhibits, constituted comprehensive
procedures for installing multiple pipes through a single bore hole when using HDD, during the
hearing and in the region recommendation, OPS explained that the standard HDD process is
performed by pulling a single pipe through a horizontally directionally drilled bore hole with the
pipe being concentric to the bore hole. Respondent’s HDD standard P66PL-TIP-4010 is the
acknowledged procedure for this operation. According to OPS, however, “the existing Phillips
66 procedure did not address the complexities or integrity issues introduced by installing
multiple pipes through the same bore.”7 Specifically, OPS stated that the existing procedure did
not address the additional risks arising from a multiple pipe installation such as damage to the
pipe, damage to the pipe coating, the introduction of excessive stresses on a single pipe or pipes
depending on how the pipes are pulled, and the lack of adequate soil compaction around each
pipe to ensure adequate structural support among other things.8 OPS is correct that Respondent’s
HDD standard P66PL-TIP-4010 did not cover bundled HDD installations.
In the materials submitted by Phillips 66 in connection with the hearing, the closest thing to
written specifications for undertaking a bundled HDD installation at the San Bernard River
crossing is the Nov. 19, 2014 Specification Deviation Request for Troy Construction which
states, in its entirety:
P66 Integrity Group was contacted on 11/19/14 to grant approval to
install the HDD across the San Bernard River by bundling the two
(2) 10” & 16”. P66 Integrity Group granted approval to perform the
two bundles. Troy will place spacers on individual pipelines at 10
feet intervals to protect the pipe. After the pilot hole has been
drilled, the following will take place, the first reamer pass will be a
30” hole, then ream to 36”, followed by a 42”/48” reamer. The
driller plans to clean the hole with a 36”/40” swab pass before
pulling the pipe. The pull heads will be connected to a 2” plate
pinned back by a swivel.
The construction of a pipeline at a river crossing is a complex undertaking. Establishing
comprehensive construction plans in advance is critical because the pipeline operator is
responsible for overseeing its contractors and ensuring that detailed plans are followed and
quality control is maintained. River crossings are particularly sensitive areas for hazardous
liquid pipeline construction because once the pipe is in place accessing it for inspection or repair
6 Response at 2-3.
7 Region recommendation at 4.
8 Id.



CPF No. 4-2016-5002
Page 4
if a failure occurs can involve significant environmental and safety consequences.9 The planning
process must be sufficient to ensure appropriate measures are in place to address known risks
such as pipe stress and damage and coating damage when more than one pipe will be installed in
a single bore. These risks are not present in a standard single pipe installation. Therefore,
Respondent’s HDD standard P66PL-TIP-4010 was inadequate for the San Bernard River
crossing, even as supplemented by the extremely austere one-paragraph Specification Deviation
Request which did not even include procedures for the use of bumper rings, ensuring that the
bumper rings could not be damaged or torn off during the pull, or how to validate that adequate
spacing of 12-inches under Part 195 or electrical isolation required by the regulations would be
achieved.10 Notably, Phillips 66 subsequently did establish a written procedure in April of 2015
for bundled HDD installations in an Appendix A to HDD standard P66PL-TIP-4010 entitled
“Bundled Drills,” but it was not in place during the relevant period of December 2014 when the
construction took place.11
As for Respondent’s argument that no undue stress or pipe damage during the installation had
been shown by the post-installation integrity assessment, while this information is potentially
relevant to the proposed compliance order and whether it may be partially satisfied, it is not
dispositive on the question of whether there was an absence of comprehensive written
specifications for constructing the pipeline by installing multiple pipes through a single bore hole
when using HDD.12
Accordingly, after considering all of the evidence and the legal issues presented, I find that
Respondent violated 49 C.F.R. § 195.202 by installing multiple pipes through a single bore hole
when using HDD as part of its Mont Belvieu to Sweeney, Texas HVL pipeline construction
project without having comprehensive written specifications for constructing the pipeline in this
manner.
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
9 The purpose of the pipeline safety regulations is to provide adequate protection against risks to life, property, and
the environment. 49 U.S.C. § 60102.
10 See 49 C.F.R. §§ 195.250 and 195.575.
11 Phillips 66 pre-hearing submission, Exhibit C.
12 In its February 23, 2018 Reply to the Region Recommendation, Respondent took issue with various
representations made by OPS in the December 28, 2017 recommendation including the accuracy of Figures 1 and 2
and OPS’ assertions that there was a complete absence of certain procedures involving foreign crossings and
protective current, that decisions were made without proper approval, and that Phillips 66 made decisions “on the
fly.” I disregarded these statements by OPS and my findings in this Order are not based on them in any way
whatsoever.



CPF No. 4-2016-5002
Page 5
COMPLIANCE ORDER
The Notice proposed a compliance order with respect to Item 1 in the Notice for violation of 49
C.F.R. § 195.202. Under 49 U.S.C. § 60118(a), each person who engages in the transportation
of hazardous liquids or who owns or operates a pipeline facility is required to comply with the
applicable safety standards established under chapter 601.
In its Response, Phillips 66 noted that it had revised its written procedures for HDD to cover
bundled drills in April 2015. Respondent stated that it has performed an engineering critical
assessment (ECA) on the two 10-inch segments installed through a single HDD under the San
Bernard River and included a report of an inspection conducted by T.D. Williamson dated June
19, 2015.13 The Director has indicated that the documentation submitted by Respondent thus far
does not satisfy the requirements of the proposed compliance order.14 Accordingly, the
compliance terms are included in this order.
Pursuant to the authority of 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is
ordered to take the following actions to ensure compliance with the pipeline safety regulations
applicable to its operations:
1. With respect to the violation of § 195.202 (Item 1), Respondent must develop,
submit and execute a plan to evaluate the integrity of the multiple pipes that were
installed in this manner. The plan must include a means to evaluate each pipe for
metal loss; dents; dents with metal loss; cracks; the external coating; adequate
structural support of the pipes by the surrounding soil; whether the entire
circumference of each of the pipes is in contact with the soil so that each pipe is
protected from external corrosion by cathodic protection current; whether excessive
secondary stresses were introduced by the installation method; whether the minimum
required spacing requirements have been met; and whether the rubber spacers
installed on the pipes shield the pipes from cathodic protection current. Prior to
commencing implementation of the plan, Phillips 66 must submit the proposed plan
to the Director for approval.
2. Respondent must submit the plan described in Item 1 of this Compliance Order to
the Director for approval within thirty (30) days of the date of receipt of this Final
Order. Upon the Director’s approval of the plan, Phillips 66 must complete all
evaluations within ninety (90) days and submit the evaluation results, along with all
supporting documents and data, to the Director. If the evaluations indicate that the
installation introduced integrity threats in any of the pipes, Respondent must develop
a plan to mitigate the integrity threats and submit the mitigation plan to the Director
for approval with thirty (30) days of completing the evaluations. Upon approval of
the mitigation plan by the Director, Phillips 66 must submit documentation
demonstrating completion of all items in the mitigation plan to the Director within
one-hundred twenty (120) days of commencing the implementation of the approved
13 Phillips 66 post-hearing submission, Exhibit W.
14 Region recommendation at 6-7.



CPF No. 4-2016-5002
Page 6
mitigation plan.
The Director may grant an extension of time to comply with any of the required items upon a
written request timely submitted by the Respondent and demonstrating good cause for an
extension.
It is requested (not mandated) that Respondent maintain documentation of the safety
improvement costs associated with fulfilling this Compliance Order and submit the total to the
Director. It is requested that these costs be reported in two categories: (1) total cost associated
with preparation/revision of plans, procedures, studies and analyses; and (2) total cost associated
with replacements, additions and other changes to pipeline infrastructure.
Failure to comply with this Order may result in the administrative assessment of civil penalties
not to exceed $200,000, as adjusted for inflation (49 C.F.R. § 190.223), for each violation for
each day the violation continues or in referral to the Attorney General for appropriate relief in a
district court of the United States.
Under 49 C.F.R. § 190.243, Respondent may submit a petition for reconsideration of this Final
Order to the Associate Administrator, Office of Pipeline Safety, PHMSA, 1200 New Jersey
Avenue, SE, East Building, 2nd Floor, Washington, DC 20590, with a copy sent to the Office of
Chief Counsel, PHMSA, at the same address, no later than 20 days after receipt of service of this
Final Order by Respondent. Any petition submitted must contain a statement of the issue(s) and
meet all other requirements of 49 C.F.R. § 190.243. The terms of the order, including corrective
action, remain in effect unless the Associate Administrator, upon request, grants a stay.
The terms and conditions of this Final Order are effective upon service in accordance with 49
C.F.R. § 190.5.
July 12, 2019
___________________________________ __________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

420165002_Closure Letter_01262022_(20-176184)_text.pdf

ELECTRONIC MAIL - RETURN RECEIPT REQUESTED
January 26, 2022
Todd Denton
President
Phillips 66 Pipeline, L.P.
3010 Briarpark Drive, PWC-7109
Houston, Texas 77042
CPF 4-2016-5002
Dear Mr. Denton:
From April 13, 2015 through September 17, 2015, representatives of the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code
(U.S.C.), conducted an on-site pipeline safety inspection of the facilities and records of the Phillips
66 Pipeline, LLC (Phillips 66, the Operator) Mont Belvieu to Sweeney, TX HVL pipeline. As a
result of the inspection PHMSA issued a Notice of Probable Violation and Proposed Compliance
Order on February 24, 2016 and Final Order on July 12, 2019.
PHMSA staff reviewed your responses provided to demonstrate compliance with the Compliance
Order and determined that Phillips 66 has substantially complied with the terms of the Final Order.
This letter is to inform you no further responses in this case are required, and this case is now
closed. Thank you for your cooperation.
Sincerely,
Mary L. McDaniel, P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
- **truncated:** false
- **body characters:** 20752
