# MIDSHIP PIPELINE COMPANY, LLC — Notice of Amendment

- **operation:** document
- **citation:** CPF 42021058NOA
- **title:** MIDSHIP PIPELINE COMPANY, LLC — Notice of Amendment
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2021-11-01
- **effective on:** Not available
- **summary:** CLOSED notice of amendment citing 192.615(b)(3).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-42021058noa.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-42021058noa.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-42021058noa
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/42021058NOA
**body:**

Notice of Amendment involving MIDSHIP PIPELINE COMPANY, LLC. PHMSA's enforcement data identifies the cited regulation as 192.615(b)(3). The case was opened on 2021-11-01 and is reported as closed as of 2021-11-30. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42021058NOA_Closure Letter_11302021_(21-200343).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021058NOA/42021058NOA_Closure%20Letter_11302021_(21-200343).pdf

42021058NOA_Closure Letter_11302021_(21-200343)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021058NOA/42021058NOA_Closure%20Letter_11302021_(21-200343)_text.pdf

42021058NOA_Notice of Amendment_11012021_(21-200343).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021058NOA/42021058NOA_Notice%20of%20Amendment_11012021_(21-200343).pdf

42021058NOA_Notice of Amendment_11012021_(21-200343)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021058NOA/42021058NOA_Notice%20of%20Amendment_11012021_(21-200343)_text.pdf

42021058NOA_Operator Response to Notice_11052021_(21-200343).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42021058NOA/42021058NOA_Operator%20Response%20to%20Notice_11052021_(21-200343).pdf

42021058NOA_Closure Letter_11302021_(21-200343)_text.pdf

ELECTRONIC MAIL - RETURN RECEIPT REQUESTED
November 30, 2021
Aaron Stephenson
Senior Vice President, Operations
Midship Pipeline Company, LLC
700 Milam Street, Suite 1900
Houston, Texas 77002
CPF 4-2021-058-NOA
Dear Mr. Stephenson:
From March 29, 2021 through June 8, 2021, a representative from the Pipeline and Hazardous
Materials Safety Administration (PHMSA), pursuant to chapter 601 of 49 United States Code,
conducted a pipeline safety inspection of Midship Pipeline Company, LLC’s (Midship)
procedures for operations, maintenance, and emergencies in Houston, Texas. As a result of the
inspection, Midship was issued a Notice of Amendment on November 1, 2021, which proposed
amendment of your procedures.
Midship submitted copies of its amended procedures on November 5, 2021. My staff reviewed
the amended procedures, and it appears that the inadequacies outlined in this Notice of
Amendment have been corrected.
This letter is to inform you no further action is necessary and this case is now closed. Thank you
for your cooperation.
Sincerely,
Mary L. McDaniel P.E
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration

42021058NOA_Notice of Amendment_11012021_(21-200343)_text.pdf

NOTICE OF AMENDMENT
ELECTRONIC MAIL - RETURN RECEIPT REQUESTED
November 1, 2021
Aaron Stephenson
Senior Vice President, Operations
Midship Pipeline Company, LLC
700 Milam Street, Suite 1900
Houston. Texas 77002
CPF 4-2021-058-NOA
Dear Mr. Stephenson:
From March 29, 2021 through June 8, 2021, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code,
inspected Midship Pipeline Company, LLC’s (Midship) procedures for operations, maintenance,
and emergencies.
Based on the inspection, PHMSA has identified an apparent inadequacy found within Midship’s
plans or procedures, as described below:
1. § 192.615 Emergency plans
(a) Each operator shall establish written procedures to minimize the hazard resulting
from a gas pipeline emergency. . .
(b) Each operator shall:
(1) . . .
(3) Review employee activities to determine whether the procedures were
effectively followed in each emergency.
Midship’s Pipeline Emergency Response Plan, ERP-PPL-6110 (Dated November 1, 2020) is
inadequate because it does not include steps for personnel to follow when reviewing an
employee’s activities during an emergency, to determine whether that employee effectively
followed the procedures during such emergency. Specifically, Section 24.2 Review After
Emergency of Midship’s Pipeline Emergency Response Plan requires that the plan “be
reviewed by the VP Pipeline Operations for effectiveness of the procedures used after an
emergency.”



The procedure does not, however, include the necessary steps for reviewing the employee’s
activities or employee’s actions during the emergency as part of the review process.
Midship’s procedure must be amended or supplemented to include steps guiding the review of
the activities of an employee during an emergency as part of the post-emergency review
process for the effectiveness review of the emergency procedures used during the emergency.
Response to this Notice
This Notice is provided pursuant to 49 U.S.C. § 60108(a) and 49 C.F.R. § 190.206. Enclosed as
part of this Notice is a document entitled Response Options for Pipeline Operators in Compliance
Proceedings. Please refer to this document and note the response options. Be advised that all
material you submit in response to this enforcement action is subject to being made publicly
available. If you believe that any portion of your responsive material qualifies for confidential
treatment under 5 U.S.C. 552(b), along with the complete original document, you must provide a
second copy of the document with the portions you believe qualify for confidential treatment
redacted and an explanation of why you believe the redacted information qualifies for confidential
treatment under 5 U.S.C. 552(b).
Following the receipt of this Notice, you have 30 days to submit written comments, revised
procedures, or a request for a hearing under § 190.211. If you do not respond within 30 days of
receipt of this Notice, this constitutes a waiver of your right to contest the allegations in this Notice
and authorizes the Associate Administrator for Pipeline Safety to find facts as alleged in this Notice
without further notice to you and to issue an Order Directing Amendment. If your plans or
procedures are found inadequate as alleged in this Notice, you may be ordered to amend your plans
or procedures to correct the inadequacies (49 C.F.R. § 190.206). If you are not contesting this
Notice, we propose that you submit your amended procedures to my office within 30 days of
receipt of this Notice. This period may be extended by written request for good cause. Once the
inadequacies identified herein have been addressed in your amended procedures, this enforcement
action will be closed.
It is requested (not mandated) that Midship Pipeline Company, LLC maintain documentation of
the safety improvement costs associated with fulfilling this Notice of Amendment
(preparation/revision of plans, procedures) and submit the total to Mary L. McDaniel P.E, Director,
Southwest Region, Pipeline and Hazardous Materials Safety Administration. In correspondence
concerning this matter, please refer to CPF 4-2021-058-NOA and, for each document you submit,
please provide a copy in electronic format whenever possible.
Sincerely,
Mary L. McDaniel P.E.
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
2