# SOUTHERN GULF LNG COMPANY LLC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 42022035NOPV
- **title:** SOUTHERN GULF LNG COMPANY LLC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2022-03-07
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 193.2801.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-42022035nopv.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-42022035nopv.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-42022035nopv
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/42022035NOPV
**body:**

Notice of Probable Violation involving SOUTHERN GULF LNG COMPANY LLC. PHMSA's enforcement data identifies the cited regulation as 193.2801. The case was opened on 2022-03-07 and is reported as closed as of 2022-12-12. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

42022035NOPV_Closure Letter_12122022_(21-209145).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_Closure%20Letter_12122022_(21-209145).pdf

42022035NOPV_Closure Letter_12122022_(21-209145)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_Closure%20Letter_12122022_(21-209145)_text.pdf

42022035NOPV_Final Order_05122022_(21-209145).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_Final%20Order_05122022_(21-209145).pdf

42022035NOPV_Final Order_05122022_(21-209145)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_Final%20Order_05122022_(21-209145)_text.pdf

42022035NOPV_NOPV PCO_03072022_(21-209145).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_NOPV%20PCO_03072022_(21-209145).pdf

42022035NOPV_NOPV PCO_03072022_(21-209145)_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_NOPV%20PCO_03072022_(21-209145)_text.pdf

42022035NOPV_Operator Response to Notice_04052022_(21-209145).pdf: https://primis.phmsa.dot.gov/enforcement-documents/42022035NOPV/42022035NOPV_Operator%20Response%20to%20Notice_04052022_(21-209145).pdf

42022035NOPV_Final Order_05122022_(21-209145)_text.pdf

May 12, 2022
VIA ELECTRONIC MAIL TO: kenneth grubb@kindermorgan.com
Mr. Kenneth Grubb
Chief Operating Officer
Southern Gulf LNG Company, LLC
1001 Louisiana Street, Suite 1000
Houston, Texas 77002
Re: CPF No. 4-2022-035-NOPV
Dear Mr. Grubb:
Enclosed please find the Final Order issued in the above-referenced case. It makes a finding of
violation and specifies actions that need to be taken to comply with the pipeline safety
regulations. When the terms of the compliance order are completed, as determined by the
Director, Southwest Region, this enforcement action will be closed. Service of the Final Order
by e-mail is effective upon the date of transmission and acknowledgement of receipt as provided
under 49 C.F.R. § 190.5.
Thank you for your cooperation in this matter.
Sincerely,
Alan K. Mayberry
Associate Administrator
for Pipeline Safety
Enclosures (Final Order and NOPV)
cc: Ms. Mary McDaniel, Director, Southwest Region, Office of Pipeline Safety, PHMSA
Mr. Jaime Hernandez, Director, Engineering, Codes & Standards, Southern Gulf LNG
Company, jaime_hernandez@kindermorgan.com
Ms. Carla Roark, Compliance Manager, Southern Gulf LNG Company,
carla_roark@kindermorgan.com
CONFIRMATION OF RECEIPT REQUESTED



U.S. DEPARTMENT OF TRANSPORTATION
PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION
OFFICE OF PIPELINE SAFETY
WASHINGTON, D.C. 20590
____________________________________
In the Matter of )
Southern Gulf LNG Company, LLC, ) CPF No. 4-2022-035-NOPV
)
)
)
Respondent. )
____________________________________)
FINAL ORDER
On March 7, 2022, pursuant to 49 C.F.R. § 190.207, the Director, Southwest Region, Office of
Pipeline Safety (OPS), issued a Notice of Probable Violation (Notice) to Southern Gulf LNG
Company, LLC (Respondent). The Notice proposed finding that Respondent had violated the
pipeline safety regulations in 49 C.F.R. Part 193. The Notice also proposed certain measures to
correct the violation. Respondent did not contest the allegation of violation or corrective
measures.
Based upon a review of all of the evidence, pursuant to § 190.213, I find Respondent violated the
pipeline safety regulation listed below, as more fully described in the enclosed Notice, which is
incorporated by reference:
49 C.F.R. § 193.2801 (Item 1) ─ Respondent failed to provide and maintain fire
protection according to sections 9.1 through 9.7 and section 9.9 of NFPA-59A-
2001 (incorporated by reference, see § 193.2013).
This finding of violation will be considered a prior offense in any subsequent enforcement action
taken against Respondent.
Compliance Actions
Pursuant to 49 U.S.C. § 60118(b) and 49 C.F.R. § 190.217, Respondent is ordered to take the
actions proposed in the enclosed Notice to correct the violation. The Director may grant an
extension of time to comply with any of the required items upon a written request timely
submitted by the Respondent and demonstrating good cause for an extension. Upon completion
of ordered actions, Respondent may request that the Director close the case. Failure to comply
with this Order may result in the assessment of civil penalties under 49 C.F.R. § 190.223 or in
referral to the Attorney General for appropriate relief in a district court of the United States.



CPF No. 4-2022-035-NOPV
Page 2
The terms and conditions of this order are effective upon service in accordance with 49 C.F.R.
§ 190.5.
May 12, 2022
___________________________________ _________________________
Alan K. Mayberry Date Issued
Associate Administrator
for Pipeline Safety

42022035NOPV_Closure Letter_12122022_(21-209145)_text.pdf

VIA ELECTRONIC MAIL
December 12, 2022
Kenneth Grubb
Chief Operating Officer
Southern Gulf LNG Company, LLC
1001 Louisiana Street, Suite 1000
Houston, Texas 77002
CPF 4-2022-035-NOPV
Dear Mr. Grubb:
From June 21, 2021, through August 25, 2021, a representative of the Pipeline and Hazardous
Materials Safety Administration (PHMSA) pursuant to Chapter 601 of 49 United States Code
(U.S.C.), inspected Southern Gulf LNG Company, LLC’s (SGLNG) plans and procedures for
Liquified Natural Gas (LNG) facilities located in Jackson County, Mississippi. As a result of the
inspection, PHMSA issued a Notice of Probable Violation (Notice) and Proposed Compliance
Order on March 07, 2022, and Final Order on May 12, 2022.
SGLNG submitted its response to the Final Order on June 20, 2022. PHMSA reviewed the
responses provided to demonstrate compliance with the Compliance Order and determined that
SGLNG has complied with the terms of the Final Order.
This letter is to inform you no further response in this case is required, and this case is now closed.
Thank you for your cooperation in this matter.
Sincerely,
Bryan Lethcoe
Director, Southwest Region
Pipeline and Hazardous Materials Safety Administration
cc: Carla Roark, Compliance Manager, Southern LNG, Carla_Roark@kindermorgan.com
Andrew Kohout, P.E., Director, Division of LNG Facility Reviews and Inspections,
Office of Energy Projects, Federal Energy Regulatory Commission,
andrew.kohout@ferc.gov