# GAS TRANSMISSION NORTHWEST LLC — Notice of Probable Violation

- **operation:** document
- **citation:** CPF 520041007
- **title:** GAS TRANSMISSION NORTHWEST LLC — Notice of Probable Violation
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2004-02-24
- **effective on:** Not available
- **summary:** CLOSED notice of probable violation citing 192.13(c), 192.481.
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520041007.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520041007.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520041007
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520041007
**body:**

Notice of Probable Violation involving GAS TRANSMISSION NORTHWEST LLC. PHMSA's enforcement data identifies the cited regulations as 192.13(c),  192.481. The case was opened on 2004-02-24 and is reported as closed as of 2005-06-20. Proposed civil penalty: $20,000. Assessed civil penalty: $12,500. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520041007_final order_03102005.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520041007/520041007_final%20order_03102005.pdf

520041007_final order_03102005.pdf

rD
U.S. Deportmeni
of Tronsporblbn
Reieorch ond
Speciol Progromt
Administrolion
4OO Sevenlh Sl S.W
Washrnglon. D C 20590
l\,14R 1 0 Z(]i;:
Mr. Bob T. Howard
Vice President
Gas Transmission Norlhwest
1400 SW Fifth Avenue, Suite 900
Portland, OR 97201
Dear Mr. Howard:
Enclosed is the Final Order issued by the Associate Administrator for Pipeline Safety in the
above-referenced case. It makes findings ofviolation and assesses a civil penalty of$12,500' The
penalty payment and terms are set forth in the Final Order. This enforcement action closes
automatically upon payment. Your receipt of the Final Order constitutcs service of that document
under 49 C.F.R. Q 190.5.
Sincerely,
l\/
-+o.,- l7l---
James Reynolds
Pipeline Compliance RegistrY
Office of Pipeline SafetY
Enclosure
Mr. Kevin Cowan, Gas Transmission Northwest
Mr. Alan Rathbun, washington Utilities and Transportation commission
Mr. Chris Hoidal, Director, OPS, Westem Regior



DEPARTMENT OF TRANSPORTATION
RJSEARCH AND SPECIAL PROGRAMS ADMINISTRATION
OFF'ICE OF PIPELINE SAFETY
WASHINGTON. DC 20590
In the Matter of
GAS TRANSMISSION NORTHWEST
CORPORATION
Respondent.
CPF No. 5-2004-1007
FINAL ORDER
During May 19 and23 and between May 28 and29,2003, pursuantto 49 U.S.C. $ 60117,
representatives of Washington Utilities and Transporlation Commission (WUTC), as agent for the
Office of Pipeline Safety (OPS) conducted an on-site pipeline safety inspection of Respondent's
natural gas pipeline facilities and records in the State of Washington. As a result of the inspection,
the Director, Westem Region, OPS, issued to Respondent, by letter dated February 24,2004, a
Notice of Probable Violation and Proposed Civil Penalty (Notice). In accordance with 49 C.F.R.
5190.207, the Notice proposed finding that Respondent had violated 49 C.F.R. $$ 192.13
andl92.48i andproposedassessingacivilpenaltyof$20,000fortheallegedviolations.
Respondent responded to the Notice by letter dated March 19, 2004 (Response). Respondent
contested the allegations ofviolation, offered information to explain the allegations and requested
that the proposed civil penalty be eliminated. Respondent submitted a request for a heanng by e-
mail on July 21, 2004. In accordance with {ii90.209, Respondent's hearing request was denied, as
the request was made more than 30 days after receipt of the Notice.
F'INDINGS OF VIOLATION
Item 1 of the Notice alleged that Respondent violated 49 C.F.R. $192.13 (c) by not maintaining,
modifying as appropriate, and following the plans, procedures, and programs that it is required to
establish under this part. The OPS inspection revealed that Respondent did not foilow written
procedures detailing the use of a plasma arc cutting torch to remove a 4?-inch road casing during a
Lighwayproj ect. According to the procedures, the welder simulates the conditions to test the cutting
method andotherdetails oftheprocedure priorto conductingthe actual operation. Theprocedures
provided for the use ofa heat shield.
However, Respondent did not perform the simulation test nor was a heat shield used during the
operation. The plasma arc made contact with the wall of the pipeline and caused three "divot" like
defects. Respondent repaired the damage to the pipeline in accordance with its procedures.



2
The Notice also alleged that Respondent did not provide documentation to demonstrate that it
followed procedures to conductpre-job briefings, as required by Respondent's OMI KK-71 Pre-Job
Briefing dated 5llT l}1r Respondent's procedures require pre-job briefing be conducted every day
to provide instructions to employees when conducting non-routine tasks until thc job is complete.
In its response to Item l, Respondent contended that OPS lacked jurisdiction regarding the removal
of the 42-inch road crossing casing because the removal ofroad casings is not explicitly covered by
49 C.F.R. Part 192 nor is it included in Respondent's IO&M Plan. Alternatively, it is Respondent's
position that it should not be found in violation because of one employee's choice not to follow the
company's written procedures for removal of a road crossing casing. Respondent contended that a
briefing rvas held the first day of the job.
As lor Respondent's jurisdictional argument, the alleged violation stemmed fiom Respondent's
failure to follow its own written procedure for removing casings in a manner that protected the pipe
from damage and in conducting and documenting pre-job briefings with respect to the casing
activity. It is irrelevant the Respondent had not included the procedures in its IO&M Plan since the
activity in connection with a highlvay project is not a routine one. However, it is an excavation
activity for which 49 C.F.R. fi 192.614 requires written procedures to protect the pipeline from
damage. ln this case, following the procedure might have prevented the damage that occurred here.
It is also irrelevant that removal of casing is not explicitly mentioned in Part 192. Most of the
regulations inPart 192, including 49 C.F.R. $ 192.614, are performance regulations that allow an
operator to craft regulations appropriate to the operations of its pipeline. With respect to the pre-job
briefings, Respondent has adopted the procedure for pre-job briefings to be applied whenever the
safety of some maintenance activity would be improved by it. Respondent recognized the
importance of a pre-job briefing on this project by conducting one and cannot then fail to follow the
procedure.
As for Respondent's argument that the incident would not have occured but for the actions of one
employee, an employer is ultimately responsible for the actions of its employees. This is a well-
settled rule of law that comes into play when the employer has the right and ability to control or
sgpervise the activities of an employee. An employer's responsibility is not diminished or affected
bythe fact that an individual failed to follow Respondent's procedures and failed to consult with
management or the engineer who developed the road casing removal procedures.
Ultimately, Respondent is responsible for compliance with the pipeline safety regulations. The
Notice identified instances inwhichResponcient failedto followthe plans,procedures, andprograms
established under $ 192.13. Respondent failed to demonstrate that pre-job briefings were conducted.
Assuming arguendo, that a f,rrst daypre-jobbriefingwasheld, the proceduresrequireddailybriefing-
Also' Respondent's internal investigation revealed that some individuals that worked on the job did
not atienri ihe aiieged iii'si day briefing. P\espondent's failure to foilow the written plans and
procedures for removal of the road casing and failure to provide daily instructions to employees
conducting this non-routine task resulted in damage to the pipeline. Accordingly, I find that
Respondent violated 49 C.F.R. $ 192.13 by failing to foilow the plans, procedures, and progtams as
required.



J
Item 2 of the Notice alleged that Respondent violated 49 C.F.R. $192.481 by not inspecting
Mainline Valve 6-2 and Mainline Valve 6-3 for atmospheric corrosion at least once every 3 calendar
years, but with intervals not exceeding 39 months. The defects on Mainline Yalve 6-2 included
disbonded coating on mainline blowdown stacks #13 and #14 with an indication of some visible rust
but no corrosion. The defects identified on Mainline Valve 6-3 included coating deflects and
indications of corrosion at the air-to-soil interface on mainline blowdown stacks #13 and #14. The
Notice also alleged that similar air-to-soil interface conditions were observed on miscellaneous
piping at Compressor Stations 6 (Rosalia) and 8 (Wa11u1a). However, no remedial action had been
taken to correct the condition until initiation of the OPS inspection on May 19, 2003.
In its initial response to Item 2, Respondent argued that effective inspection and remediation
procedures were in piace at the time of the inspection. In support of its position, Respondent further
argued that it cond'-rcted inspections during and al-ter the OPS inspection anC no coating ."',,as found
with severe damage, that at no time in its 40 years of operations has any above ground piping needed
to be replaced due to atmospheric corrosion and that during the OPS inspection it initiated
remediation. With respect to the allegation that simiiar air-to-soil interface conditions were obsen'ed
on miscellaneous piping at Compressor Station 6 (Rosalia) and 8 (Wallula), Respondent suggested
that closer obserrration was needed to assess the vent line for possible coating deficiencies at Station
8 and the blow-down stack at Station 6 to assess the condition of the coating. Respondent argued
that while its subsequent assessment found that the coating at both locations had some deterioration
at the surface due to the effects ofultraviolet light, the coating was bonded to the pipe above the soil
line and there was no deteriorated coating below the soil line. Respondent stated that both locations
had been inspected for atmospheric corrosion within the past three years and both sites were found
to be free from deterioration requiring remediation.
Although Respondent argued that effective inspection and remediation procedures were in place, a
review of Respondent's exposed pipe reports revealed defects on Mainline valve 6-2 and Mainline
6-3 that were originally identihed on April 16, 2001 . In fact, Respondent acknowledged the poor
performance of a supewisory empioyee in addressing this matter during 2001 and 2002. The
evidence showed that no remedial action had been taken to correct the condition until initiation of
the OPS inspection on May 19, 2003. Accordingly, I find that Respondent violated 49 C.F.R.
$ r92.48 | .
These findings ofviolation will be considered prior offenses in any subsequent enforcement action
taken against Respondent.
ASSESSMENT OF PENALTY
Under 49 U.S.C. g 60122, Respondent is subject to a civil penalty not to exceed $100,000 per
" i n l o + i n - l ^ r - 4 ^ 1 " n . . , u q j / ^ F v r r h c r t r v
. , i n l o t i n n " n t ^ . - " ' ; - . r ' " - ' " ^ f q l n n n O O O F n r a n r r r e l n t e d c e r i e c n f
violations. TheNoticeproposedatotalcivilpenaltyof$20,000forviolationof49C.F.R.$$192.13
and 192.481.



4
49 U.S.C. $ 60122 and 49 C.F.R. $ 190.225 require that, in determining the amount of the civil
penalty, I consider the following criteria: nature, circumstances, and gravity of the violation, degree
of Respondent's culpability, history of Respondent's prior offenses, Respondent's ability to pay the
penalty, good faith by Respondent in attempting to achieve compliance, the effect on Respondent's
ability to continue in business, and such other matters as justice may requirc.
The proposed penalty for Item 1 is $5,000 for violation of 49 C.F.R. $ 192.13, as Respondent failed
to follow the written plans and procedures for removal of the road casing and failed to provide daily
inshuctions to employees conducting this non-routine task resulted in damage to the pipeline.
Respondent argued that the proposed civil penalty is inappropriate, as Respondent's investigation
revealed that the incident occurred because ofan individual who failed to follow procedures and
failed to consult rvith rnar..agement or the engineer r,r,,hs dsr,rslsped the road casing removal
procedure. Respondent contended that a briehng was held the first day of the job. Respondent
advised that because it takes the circumstances surrounding the casing removal seriously, an
investigation was initiated to identify safety concerns, resolutions to those concems and any
necessaryproglam improvements. Respondent argued that the immediate disciplinary actions that
resulted in termination of the individual's employment and the implementation of program
improvements which resulted from the intemal investigation are pritigating factors that support
elimination of the proposed civil penalty. Respondent advised that it did not take the occurrence
lightly and that the resulting actions substantiate that stance as well as its overall commitment to
pipeline safety and integrity. Respondent argued that the incident would not have occurred but for
the actions of one employee who made an individual choice not to follow the procedures.
Respondent further advised that the results of the investigation were shared with OPS, WUTC and
Respondent's employees.
When an employee acts within the scope ofhis authority, as the employer's representative, and fails
to take appropriate action, that failure is attributable to the employer. The primary objective of the
Federal gas pipeline safety standards is public safety and failure to follow procedures could adversely
affect public safety. Respondent failed to follow its manual of written procedures for conducting
operations, maintenance activities and emergency response. Operators are ultimately responsible
for their own compliance with pipeline safety laws and regulations even in the face of mistakes,
omissions or commissions that occur within its employee's scope of duties. Accordingly, having
reviewed the record and considered the assessment criteria, I assess Respondent a civil penalty of
$5,000. Accordingly, I find Respondent violated 49 C.F.R. $ 192.13(c).
The proposed penalty for Item 2 is $15,000 for violation of 49 C.F.R. $192.481, as Respondent
failed to inspect for atmospheric conosion at least once every 3 calendar years, but with intervals not
exceeding 39 months. Respondent requested reconsideration of the proposed civil penalty.
A l i L ^ , , ^ L D a - - ^ ^ ; - h + . ' - " - , - I , L o r i + l " a o a f f a n t i r ' , . i - c ^ . . + i ^ - . - . 1 ' - - . , l i r ! i n n n r n n , - r l r r r o c
. a , r r , \ r u E , ' d , s u r u
Respondent's exposed pipe repofis revealed defects on the subject areas that were originally
identifiecl on April i 6, 2001. The pipe was cleaned and re-coated onMay 22,2003. Documentation
is essential to provide the Operator a useful review tool for operating practices and procedures.



5
A determination is made that Respondent took remedial action prior to the conclusion of the OPS
inspection to comply with the regulations, which justifies mitigation of the proposed civil penalty.
Accordingly, having reviewed the record and considered the assessment criteria, I assess Respondent
a civil penalty ofS7,500.
Payrnent of the civil penalty must be made within 20 days of service. Payment may be made by
sending a certified check or money order (containing the CPF Number for this case) payable to
"U.S. Department of Transportation" to the Federal Aviation Administration, Mike Monroney
Aeronautical Center, Financial Operations Division (NMZ-I2}), P.O. Box 25082, Oklahoma City,
oK 7312s.
Federal regulations (49 C.F.R. $ 89.21 (bX3)) also permit this payment to be made by wire transfer,
through the Federal Resen'e Communications System (Fedwire), to the account ol-the U.S. Trcasury.
Detailed instructions are contained in the encloswe. Questions conceming wire transfers should be
directed to: Financial Operations Division (AMZ-120), Federal Aviation Administration, Mike
MoruoneyAeronautical Center, P.O. Box 25082, Oklahoma City, OK 73125, (405) 954-8893.
Failure to pay the $5,000 civil penalty will result in accrual of interest at the current annual rate in
accordance with 31 U.S.C. fi 37I7 ,31 C.F.R. g 901.9 and 49 C.F.R. $ 89.23. Pursuant to those same
authorities, a late penalty charge of six percent (6%) per annum will be charged if payment is not
made within 110 days of service. Furthermore, failure to pay the civil penalty may result in referral
of the matter to the Attomey General for appropriate action in an United States District Court.
Under 49 C.F.R. S 190.215, Respondent has a right to petition for reconsideration of this Final
Order. The petition must be received within 20 days of Respondent's receipt of this Final Order and
must contain a brief statement of the issue(s). The filing of a petition automatically stays the
payment of any civil penalty assessed. All other terms of the order, including any required corrective
action, remain in full effect unless the Associate Administrator, upon written request, grants a stay.
The terms and conditions of this Final Order are effective upon receipt.
Failure to comply with this Final Order may result in the assessmenl of civil penalties of up to
$100,000 per violation per day, or in the referral ofthe case forjudicial enforcement.
MAR 10 2C05
Siacey Gerard Date Issue<lAssociate Administrator
for Pioeline Safetv
- **truncated:** false
- **body characters:** 17142
