# ENSTAR NATURAL GAS CO — Warning Letter

- **operation:** document
- **citation:** CPF 520080010W
- **title:** ENSTAR NATURAL GAS CO — Warning Letter
- **source type:** enforcement
- **agency:** Pipeline and Hazardous Materials Safety Administration
- **status:** historical
- **official:** true
- **published on:** 2008-04-23
- **effective on:** Not available
- **summary:** CLOSED warning letter citing 192.905, 192.917, 192.933, 192.933(d), 192.945(a).
- **machine formats:** - **json:** https://regulus.evalyn.ai/document/phmsa-enforcement-520080010w.json
- **markdown:** https://regulus.evalyn.ai/document/phmsa-enforcement-520080010w.md
- **app url:** https://regulus.evalyn.ai/document/phmsa-enforcement-520080010w
- **source url:** https://primis.phmsa.dot.gov/enforcement-data/case/520080010W
**body:**

Warning Letter involving ENSTAR NATURAL GAS CO. PHMSA's enforcement data identifies the cited regulations as 192.905,  192.917,  192.933,  192.933(d),  192.945(a). The case was opened on 2008-04-23 and is reported as closed as of 2008-04-23. Open the official case record for notices, responses, orders, and the latest status.

Official case documents:

520080010W_warning letter_04232008.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520080010W/520080010W_warning%20letter_04232008.pdf

520080010w_warning letter_04232008_text.pdf: https://primis.phmsa.dot.gov/enforcement-documents/520080010W/520080010w_warning%20letter_04232008_text.pdf

520080010w_warning letter_04232008_text.pdf

U. S Department
of Transportation
Pipeline and
Hazardous Materials Safety
Administration
12300 W Dakota Ave, Suite 110
Lakewood, CO 80228
WARNING LETTER
CERTIFIED MAIL - RETURN RECEIPT RE UESTED
April 23, 2008
Mr. John Lau
Director, Transmission Operations
Alaska Pipehne Company
401 E International Airport Road
P 0 Box 190288
Anchorage, AK 99519-0288
CPF 5-2008-0010W
Dear Mr Lau
On May 7-11, 2007, representatives of the Pipehne and Hazardous Materials Safety
Administration (PHMSA), pursuant to Chapter 601 of 49 United States Code, inspected Alaska
Pipehne Company's Integrity Management program m Anchorage, Alaska.
As a result of the inspection, it appears that you have committed probable violations of the
Pipehne Safety Regulations, Title 49, Code of Federal Regulations. The items inspected and the
probable violations are.
g 192. 903 What definitions apply to this subpart? The following definitions apply to
this subpart:
High consequence area means an area established by one of the methods described
in paragraphs (1) or (2) as follows:
(2) The area within a potential impact circle containing — (ii) An identified site.
Identified site means each of the following areas: (b) A building that is occupied by
twenty (20) or more persons on at least five (5) days a week for ten (10) weeks in
any twelve (12)-month period. (The days and weeks need not be consecutive. )



Examples include, but are not limited to, religious facilities, office buildings,
community centers, general stores, 4-H facilities, or roller skating rinks.
$ 192. 905 How does an operator identify a high consequence area? (a) General. To
determine which segments of an operator's transmission pipeline system are
covered by this subpart, an operator must identify the high consequence areas. An
operator must use method (1) or (2) from the definition in g 192. 903 to identify a
high consequence area. An operator may apply one method to its entire pipeline
system, or an operator may apply one method to individual portions of the pipeline
system. An operator must describe in its integrity management program which
method it is applying to each portion of the operator's pipeline system. The
description must include the potential impact radius when utilized to establish a
high consequence area. (See appendix E. I. for guidance on identifying high
consequence areas. )
(b)(1) Identified sites. An operator must identify an identified site, for purposes of
this subpart, from information the operator has obtained from routine operation
and maintenance activities and from public officials with safety or emergency
response or planning responsibilities who indicate to the operator that they know of
locations that meet the identified site criteria. These public officials could include
officials on a local emergency planning commission or relevant Native American
tribal officials.
An HCA was added on 11/30/05 to the BAP as a new HCA, however this was identified
as the Beluga Power Plant which was m existence and should have been identified as an
origmal HCA by the December 17, 2004 date
iiEvidence i APC Annual HCA Report for 2005
g 192. 907 What must an operator do to implement this subpart'?
(a) General. No later than December 17, 2004, an operator of a covered pipeline
segment must develop and follow a written integrity management program that
contains all the elements described in g 192. 911 and that addresses the risks on each
covered transmission pipeline segment.
(b) Implementation Standards. In carrying out this subpart, an operator must follow
the requirements of this subpart and of ASME/ANSI B31. 8S (ibr, see g 192. 7) and
its appendices, where specified. An operator may follow an equivalent standard or
practice only when the operator demonstrates the alternative standard or practice
provides an equivalent level of safety to the public and property. In the event of a
conflict between this subpart and ASME/ANSI B31. 8S, the requirements in this
subpart control.
$ Bl. 91'l How t4es an operator i6enti4y potential threats to pipeline integrity and
use the threat identification in its integrity program?



(a) Threat identification. An operator must identify and evaluate all potential
threats to each covered pipeline segment. Potential threats that an operator must
consider include, but are not limited to, the threats listed in ASME/ANSI B31. 8S
(ibr, see g 192. 7), section 2, which are grouped under the following four categories:
(1) Time dependent threats such as internal corrosion, external corrosion, and
stress corrosion cracking; (2) Static or resident threats, such as fabrication or
construction defects; (3) Time independent threats such as third party damage and
outside force damage; and (4) Human error.
APC has no documented evaluation for mteractmg threats and there are no program
procedures to define how an evaluation is to be performed
iiEvidence i APC IMP Plan, Section 4. 10
3 g 192. 933 What actions must be taken to address integrity issues?
(a) General requirements An operator must take prompt action to address all
anomalous conditions that the operator discovers through the integrity assessment.
In addressing all conditions, an operator must evaluate all anomalous conditions
and remediate those that could reduce a pipeline's integrity. An operator must be
able to demonstrate that the remediation of the condition will ensure that the
condition is unlikely to pose a threat to the integrity of the pipeline until the next
reassessment of the covered segment. If an operator is unable to respond within the
time limits for certain conditions specified in this section, the operator must
temporarily reduce the operating pressure of the pipeline or take other action that
ensures the safety of the covered segment. If pressure is reduced, an operator must
determine the temporary reduction in operating pressure using ASME/ANSI B31G
(ibr, see g 192. 7) or AGA Pipeline Research Committee Project PR — 3 — 805
("RSTRENG", ibr, see g 192. 7) or reduce the operating pressure to a level not
exceeding 80% of the level at the time the condition was discovered. (See appendix
A to this part 192 for information on availability of incorporation by reference
information). A reduction in operating pressure cannot exceed 365 days without an
operator providing a technical justification that the continued pressure restriction
will not jeopardize the integrity of the pipeline.
Two anomahes were identified m HCAs during ILI of the City Gate pipehne that met the
criteria for immediate conditions Pressure reductions were not taken by APC upon
discovery of these two anomahes and repairs were completed approximately one month
and approximately 5 months after discovery of these conditions, respectively.
(Evidence l
Excavation Inspection Forms — East City Gate — 5/16/05 & 9/13/05, and other
excavation report data.
4. g 192, . 907%hat must an operator do to implement this subpart?



(a) General. No later than December 17, 2004, an operator of a covered pipeline
segment must develop and follow a written integrity management program that
contains all the elements described in g 192. 911 and that addresses the risks on each
covered transmission pipeline segment.
(b) Implementation Standards. In carrying out this subpart, an operator must follow
the requirements of this subpart and of ASMK/ANSI B31. 8S (ibr, see g 192. 7) and
its appendices, where specified. An operator may follow an equivalent standard or
practice only when the operator demonstrates the alternative standard or practice
provides an equivalent level of safety to the public and property. In the event of a
conflict between this subpart and ASMK/ANSI B31. 8S, the requirements in this
subpart control.
g 192. 933 What actions must be taken to address integrity issues?
(d) Special requirements for scheduling remediation. — (1) Immediate repair
conditions. An operator's evaluation and remediation schedule must follow ASME/
ANSI B31. 8S, section 7 in providing for immediate repair conditions. To maintain
safety, an operator must temporarily reduce operating pressure in accordance with
paragraph (a) of this section or shut down the pipeline until the operator completes
the repair of these conditions. An operator must treat the following conditions as
immediate repair conditions:
(i) A calculation of the remaining strength of the pipe shows a predicted failure
pressure less than or equal to 1. 1 times the maximum allowable operating pressure
at the location of the anomaly. Suitable remaining strength calculation methods
include, ASME/ANSI B31G; RSTRENG; or an alternative equivalent method of
remaining strength calculation. These documents are incorporated by reference
and available at the addresses listed in appendix A to part 192.
(ii) A dent that has any indication of metal loss, cracking or a stress riser.
(iii) An indication or anomaly that in the judgment of the person designated by the
operator to evaluate the assessment results requires immediate action.
The two immediate repair conditions on the City Gate pipehne noted m 3 above, were
not scheduled for repair m accordance with the requirements of ASME B31. 8S-2001,
Section 7.
(Evidence i
Excavation Inspection Forms — East City Gate — 5/16/05 R, 9/13/05, and other
excavation report data
g 192. 907 What must an operator do to implement this subpart?
(a) General. No later than December 17, 2004, an operator of a covered pipeline
segment must develop anh follow a written integrity management yrogram that



contains all the elements described in g 192. 911 and that addresses the risks on each
covered transmission pipeline segment.
g 192. 945 What methods must an operator use to measure program effectiveness?
(a) General. An operator must include in its integrity management program
methods to measure, on a semi-annual basis, whether the program is effective in
assessing and evaluating the integrity of each covered pipeline segment and in
protecting the high consequence areas. These measures must include the four
overall performance measures specified in ASME/ANSI B31. SS (ibr, see $192. 7),
section 9. 4, and the specific measures for each identified threat specified in
ASME/ANSI B31. 8S, Appendix A.
APC had not collected data as of the inspection on the threat-specific measures listed in
Table 9 of ASME B31. 8S and has no process to do so.
(Evidence l APC IMP Plan, Section 10.
Under 49 United States Code, $ 60122, you are subject to a civil penalty not to exceed $100, 000
for each violation for each day the violation persists up to a maximum of $1, 000, 000 for any
related series of violations. We have reviewed the circumstances and supporting documents
involved in this case, and have decided not to conduct additional enforcement action or penalty
assessment proceedings at this time. We advise you to correct the items identified in this letter.
Failure to do so will result in Alaska Pipeline Company being subject to additional enforcement
action.
No reply to this letter is required. If you choose to reply, in your correspondence please refer to
CPF 5-2008-0010W. Be advised that all material you submit in response to this enforcement
action is subject to being made publicly available. If you believe that any portion of your
responsive material qualifies for confidential treatment under 5 U. S. C. 552(b), along with the
complete original document you must provide a second copy of the document with the portions
you believe qualify for confidential treatment redacted and an explanation of why you believe
the redacted information qualifies for confidential treatment under 5 U. S. C. 552(b).
Sincerely,
Chris Hoidal
Director, Western Region
Pipeline and Hazardous Materials Safety Administration
cc: PHP-60 Compliance Registry
PHP-500 J. Strawn (4118987)